Social Monitoring Report

Project Number: 47100-004 August 2019

Period: July 2018 – December 2018

IND: Power Transmission and Distribution System Improvement Project

Submitted by Madhya Pradesh Power Transmission Company Ltd., Jabalpur

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

From: [email protected] on behalf of mptransco Sent: Tuesday, June 4, 2019 10:56 AM To: Jyotirmoy Banerjee Cc: Neha Munjal Subject: Fwd: Edited 5th Social Monitoring Report (SMR) for the period July 2018 to December 2018.

Respected Sir

As desired the Edited 5th Social Monitoring Report (SMR) for the period July 2018 to December 2018 is enclosed for your kind perusal please.

Regards.

R.BHATTI

Social Monitoring Report

Reporting Period: July 2018 to December 2018

IND: Madhya Pradesh Power Transmission and Distribution System Improvement Project

Loan no. 3066 IND Prepared by, Government of Madhya Pradesh through MP Transco Madhya Pradesh, Reporting Period: July 2018 to December 2018

i

ABBREVIATIONS

ADB – Asian Development Bank EA – Executing Agency AP – Affected People ESMU – Environmental and Social Management Unit GHG – Greenhouse Gas GoMP – Government of Madhya Pradesh GoI – Government of India GRC – Grievance Redress Committee HSE – Health Safety Environment IA – Implementing Agency IEE – Initial Environmental Examination Ltd. – Limited LAA – Land Acquisition Act LAO – Land Acquisition Officer MFF – Multi-Tranche Financing Facility PAP – Project Affected Persons PMU – Project Management Unit ROW – Right of Way RF – Resettlement Framework RP – Resettlement Plan RPD – Resettlement Planning Document S/S – Sub Station SEIA – Summary Environmental Impact Assessment SIEE – Summary Initial Environmental Examination SRPD – Short Resettlement Planning Document T&D – Transmission and Distribution T/L – Transmission Line T & T – Transmission and Transformation XIDAS – Xavier Institute of Development Action and Studies

ii

TABLE O+F CONTENTS

Abbreviations ii 1.0 INTRODUCTION 1 1.1 Project Background and Description 1 1.2 Purpose of the Report 14 1.3 Social Safeguard Categorization 14 2.0 Project Implementation Status 15 2.1 Overview of Social Impacts 15 2.2 Project affected Persons 15 2.3 Impacts on Land 22 2.4 Impacts on Structure 25 2.5 Crop Damage 25 2.6 Impacts on Trees 31 2.7 Impacts on Livelihood 33 2.8 Impacts on Common Property Resources 33 3.0 Compensation 33 3.1 Land Compensation 33 3.2 Compensation Status for Crop, Trees and Land Damaged 34 3.3 Relocation of CPR’s 34 4.0 Consultation and Disclosures 35 4.1 Consultation 35 4.2 Disclosures 35 5.0 Grievance Redress Mechanism 36 6.0 Institutional Arrangements 38 7.0 Monitoring and Evaluation 39 8.0 Conclusion 40 Annexure: Annexure-1: Public Consultation Attendance List 41 Annexure-2: Photographs of site visit and Consultation 44 Annexure 3: Sample copy of Crop Compensation paid to farmers 45 Tables & Figures: Table-1: Details of Transmission Lines and project status 3 Table-2: Details of Substations and Feeder Bays and project status 12 Table-3: Affected Persons: Transmission Lines 15 Table-4: Details of Land Allotment– Substation 22 Table-5: Crop Damaged in TL’s 25 Table-6: Details of Tree Cutting in Transmission Lines 31 Table-7: Grievance Redress Status 36

iii

1.0 Introduction 1.1. Project Background and Description 1.1.1 The Government of Madhya Pradesh (GOMP) through the Government of India (GOI) has availed a financing facility from the Asian Development Bank (ADB) to fund the Power Sector Investment Program in the State of Madhya Pradesh. Madhya Pradesh Power Transmission Company Limited (MPPTCL) is utilizing the finance availed for the construction of new and up gradation of existing power transmission network. The main features include power evacuation and transmission through 400 kV, 220 kV, and 132 kV transmission lines along with associated Substations and Feeder Bays. It is being implemented under ADB Loan no. 3066 which is implemented by MPPTCL, Jabalpur. A Resettlement Plan (RP) report for TRANSCOM was submitted for ADB’s approval in September, 2013. However, during the course of commencement of the works, there were route alignment changes in some transmission lines, further some new lines were also added to the same project and some were dropped as they were no longer necessary. In case of substations also, two substations were dropped from the original scope of work. In light of these changes, the RP report of September 2013 was further updated and submitted for ADB’s approval. The updated RP report was approved and disclosed by ADB in June, 2017. The updated RP of June 2017 was again updated to incorporate further changes in route and design elements of various lines. This updated RP report was approved and disclosed by ADB in September, 2017.

1.1.2 The power sector investments are necessary to support continued investment in the state power sector, which is necessary for economic growth and poverty reduction. The loan availed will be utilized to finance the expansion and augmentation of the transmission and distribution (T&D) networks. The proposed investments are necessary to: (i) facilitate increased power transfers to accommodate increased demand and economic growth; (ii) improve supply-side energy efficiency by system de-bottlenecking and reducing technical losses; (iii) reduce the intensity of greenhouse gas (GHG) and other emissions via improved system efficiency; (iv) support expanded private sector participation in distribution system operations and other energy services; and (v) facilitate poverty reduction via improved electricity services and economic growth.

1.1.3 A social monitoring report for the period July 2014 to December 2016 was submitted for ADB’s approval which was accepted and disclosed on ADB’s site. Subsequently, second monitoring report for the period January 2017 to June 2017, third monitoring report for the period July 2017 to December 2017 and fourth monitoring report for the period January 2018 to June 2018 were also accepted and disclosed on ADB’s site.This social monitoring report provides information pertaining to the project for the period July 2018 to December 2018. The report is prepared by Xavier Institute of Development Action and Studies (XIDAS) for MPPTCL.

1

1.1.4 The project is categorized as “B” for Involuntary Resettlement (IR) and “C” for Indigenous Peoples as per the ADB’s SPS. The core principles are consistent with the standards of the original safeguards documents and loan covenants. The RP covers the involuntary resettlement impact caused by the project activity. The main features of the project include power evacuation and transmission through 400 kV, 220 kV, and 132 kV transmission lines and construction of substations. It is being implemented by MPPTCL, Jabalpur under ADB Loan no. 3066.

1.1.5 The project will have no adverse involuntary resettlement impacts. There will be no physical or economic displacement of people. All the proposed substations of the project will be built on government waste land (except Palohabada where 0.4 hectares of private land has been acquired). As there is very little private land acquisition for the project so far, impacts associated with land acquisition are deemed to be minor. Few people persons who live along the transmission line corridors will suffer from temporary impacts limited to loss of one season’s crops and a few trees along the Right of Way (RoW) of the power lines. Wherever towers are placed on private land, such land will not be acquired, and EA/IAs are required to pay appropriate compensation for crop damages if any, during construction, in accordance with the Resettlement Plan (RP).

1.1.6 The Madhya Pradesh Power transmission Company (MPPTCL) is the executing agency (EAs) as well as implementing agencies (IAs) for the project. MPPTCL has established project management units (PMUs) for implementing the project. Each PMU is required to designate a social development specialist within the PMU along with other engineering units to address the social and resettlement issues of the program. For RP, PMU will do the overall coordination, preparation, planning, implementation, and financing. The EA ensures that key institutions including local governments are involved in RP updating and implementation. The PMUs are responsible for managing the site activities related to safeguards, and work closely with the field level staff.

The proposed project comprises of transmission lines and substations along with associated feeder bays that are spread in various regions of the state of Madhya Pradesh. The details of projects works including status is given below in Table 1 and Table 2.

The details of projects work viz. lines, substations and feeder bays along with project status during this monitoring period are given below in Table no. 1.0 and Table no. 2 respectively. There are changes in length and alignment in case of some lines. For the subprojects where the length and alignment has changed by more than 500 metres, the reason for such changes has also been mentioned under remarks section. For length changes less than 500 metres, it is largely due to design elements requirements and does not result in any significant impact.

2

Table no. 1: Details of Transmission Lines and project status

S. Name of Line Total Total Route Remarks Project Status No Works Route Length in Length in Km. (As per Km. (As SMR July to per SMR December Jan to 2018, present June reporting 2018) period) Jabalpur 1 LILO of 400kv 3.375 3.375 No change Stub Setting: 9 Seoni to Bhilai completed of 10 S/C line at Tower Erection: 8 Balaghat/Kirnapur completed of 10 (D/C) M/s BHEL Stringing: 2X1.615 2 LILO of 132kV 4.7 4.7 No change Completed Balaghat- Seoni/ Katangi line at Waraseoni 132kV S/s (2XD/C) M/s Industrial House 3 LILO of both 1.99 1.99 No change Completed circuit of 132kV Balaghat- Bhanegaon Line at Balaghat/Kirnapur 400kV S/s (2XD/C) M/s Industrial House 4 Second circuit of 32.218 32.218 No change Completed Tikamgarh- Budhera 132kV DCSS Line M/s B.S. Ltd. 5 Narsinghpur 220- 24.43 24.43 No change Stub Setting: 76 Devnagar 132kV completed of 81 DCSS Line M/s Tower Erection: 11 Bajaj completed of 81 Stringing: Not started yet 6 Karakbel- 24.522 24.522 No change Stub Setting: 84 Belkheda 132kV completed of 88 DCSS line M/s Tower Erection: 62 KDBL completed of 88 Stringing: 1X 9.28 7 Narsinghpur 26.62 26.62 No change Stub Setting: 52 220KV Karakbel completed of 52 132KV DCS line Tower Erection: 38 M/s KDBL completed of 52 Stringing: Not started yet 8 Panagar 220-Patan 22.749 22.749 No change Stub Setting: 39 132kV DCSS line completed of 74 M/s Bajaj Tower Erection: Not started yet Stringing: Not started yet

3

S. Name of Line Total Total Route Remarks Project Status No Works Route Length in Length in Km. (As per Km. (As SMR July to per SMR December Jan to 2018, present June reporting 2018) period) 9 Chhindwara 220- 31.600 31.600 No change Completed Saori 132kV DCSS line M/s Kalptaru 10 Chichli 220- 25.606 25.606 No change Stub Setting: 73 Palohabada 132kV completed of 88 DCSS line M/s Tower Erection: 54 Kalptaru completed out of 88 Stringing: Not started yet 11 132kv DCSS line 38.942 38.942 No change Stub Setting: 134 from Damoh completed of 134 220kv to Patera Tower Erection: 133 132 kv substation completed of 134 M/s Kalptaru Stringing: 1 x 36.12 12 Second circuit of 36.17 36.17 No change Completed 132kV Tap Line from Balaghat- Katangi M/s B.S.Ltd. Satna 13 Second circuit 34 34 No change Completed 132kV of Chhatarpur- Khajuraho line M/s B.S.Ltd. 14 LILO of second 5.693 5.693 No change Completed ckt of Bansagar- Satna 220kV line at Kotar 220kV S/s M/s Vikran 15 LILO of Satna - 11.047 11.047 No change Stub Setting: 12 Maihar 132kV line completed of 36 at Satna-II 132kV Tower Erection: 5 S/s M/s Vikran completed out of 36 Stringing: 2X0.609 16 LILO of second 5.684 5.684 No change Completed ckt of Birsinghpur - Amarkantak 220kV line at Shahdol 220kV s/s M/s Vikran 17 Birsinghpur 220- 44.821 44.821 No change Stub Setting: 167 Shahdol 132kV completed of 167 DCDS line M/s Tower Erection: 167 Vikran completed of 167 Stringing:2 x 43.703 18 LILO of 132 1.14 1.14 No change Stub Setting: 6 Tikamgarh- completed of 6 Bijawar line for Tower Erection: 4 Bada Malehra M/s completed out of 6

4

S. Name of Line Total Total Route Remarks Project Status No Works Route Length in Length in Km. (As per Km. (As SMR July to per SMR December Jan to 2018, present June reporting 2018) period) Bajaj Stringing: Not started yet 19 LILO of one 32.782 32.782 No change Stub Setting: 49 circuit of Ashta completed of 104 400-Dewas 220 kv Tower Erection: Not D/C line at Chapda started yet 220kv S/s (D/C) Stringing: Not started M/s Bajaj yet 20 400 - 37.583 37.583 No change Stub Setting: 120 Depalpur 220kv completed of 120 DCSS line M/s Tower Erection: 63 Bajaj completed of 120 Stringing: Not started yet 21 Dewas 220- Agrod 19.374 19.374 No change Completed 132kv DCSS line M/s Swastik Mechnical

22 220 - 15.35 15.35 No change Stub Setting: 51 Teesgaon 132kv completed of 53 DCSS line M/s Tower Erection: 21 Bajaj completed out of 53 Stringing: Not started yet 23 LILO of both 8.163 8.163 No change Stub Setting: 22 Circuit of 400 kv completed of 22 Nagda-Rajgarh Tower Erection: 19 line at completed of 22 (2 x D/C) M/s Stringing: 4 x 3.0 BHEL 24 Second Circuit of 35.65 35.65 No change Completed 132kv line M/s B.S.Ltd. 25 LILO of 132 18.997 18.997 No change Stub Setting: 52 Bikayan completed of 66 line at 132 Kv sub- Tower Erection: 6 station Bistan M/s completed of 66 Bajaj Stringing: Not started yet 26 LILO of 132kv 1.895 1.895 No change Completed Chegaon line at Pandhana M/s B.S.Ltd. 27 LILO - 3.1 3.1 No change Completed Kukshi DCSS line at Singhana (D/C)

5

S. Name of Line Total Total Route Remarks Project Status No Works Route Length in Length in Km. (As per Km. (As SMR July to per SMR December Jan to 2018, present June reporting 2018) period) M/s B.S.Ltd. 28 LILO of 132Kv 1.9 1.9 No change Completed Khargone - Julwaniya line at 132Kv S/S Talakpura M/s B.S.Ltd. 29 Julwaniya 400- 62.9 62.9 No change Stub Setting: 120 Kukshi 220kv line completed of 190 (D/C) M/s Bajaj Tower Erection: 34 completed of 190 Stringing: Not started yet 30 220kV DCDS 39.322 39.217 No change Completed (400 PGCIL) to line 31 Chhegaon 220- 57.76 57.76 No change Completed Singot 132kV 32 Chhanera 220- 30.179 30.179 No change Completed Khirkiya 132kV DCDS Line M/s Kalptaru Bhopal 33 Bairagarh 220 - 9.049 9.049 No change Completed Intkhedi 132kv DCDS line M/s P. S. Associated 34 Second circuit of 21.44 21.44 No change Completed Bairagarh – Shyampur M/s P. S. Associated 35 Second circuit of 48.27 48.27 No change Completed Gairatganj - Vidisha 220 132kv line M/s Punj Lyod 36 Shujalpur- 52 52 No change Stub Setting: 131 Narsinghgarh completed of 144 220kv DCSS line Tower Erection: 24 (Initially charged completed of 144 on 132kv) M/s Stringing: Not started Bajaj yet 37 LILO of one 2.868 2.868 No change Yet to start circuit of Bhopal - Hosangabad 220kv D/C line at Adampur 220kv S/s (D/C) M/s Bajaj

6

S. Name of Line Total Total Route Remarks Project Status No Works Route Length in Length in Km. (As per Km. (As SMR July to per SMR December Jan to 2018, present June reporting 2018) period) 38 Udaipura -Silvani 28.068 28.068 No change Stub Setting: 77 132kv DCSS line completed of 77 M/s Bajaj Tower Erection: 76 completed of 77 Stringing: Not started yet 39 LILO of Vidisha- 0.162 0.162 No change Completed Bairasiya Line at Salamatpur 132 KV S/s M/s P. S. Associated 40 Mugaliyachhaap 17.2 17.2 No change Completed 220- Bikisganj 132kV DCDS line M/s Punj Lyod

41 132kv Rajgarh 27.956 27.956 No change Completed (Biaora) –Khujner/ Sindaota Line M/s Punj Lyod 42 LILO of one ckt of 18.221 18.221 No change Completed Vidisha Gairatganj at Raisen 132kV S/s M/s Punj Lyod Itarsi 43 Second circuit of 57 57 No change Completed Betul 220 Gudgaon 132kv line M/s Punj Lyod 44 Chichli 220- 47.56 47.56 No change Completed Udaipura 132kv DCDS line (220kv line charged at 132kv) M/s B.S. Ltd.

45 Betul400 1.88 1.88 No change Completed (PGCIL)- Betul 220kV DCDS line M/s Punj Lyod 46 LILO of 220kV 38.864 38.864 No change Stub Setting: 135 Sarni-Pandhurna completed of 135 at 400kV Tower Erection: 117 (PGCIL) completed of 135 Substation Betul Stringing: Not started M/s Punj Lyod yet 47 Betul 220- 35.245 35.245 No change Completed Bisnoor/Masod

7

S. Name of Line Total Total Route Remarks Project Status No Works Route Length in Length in Km. (As per Km. (As SMR July to per SMR December Jan to 2018, present June reporting 2018) period) 132kV DCSS line M/s Punj Lyod Ujjain 48 Badnagar 220- 28.26 28.26 No change Completed Chhayan 132kv DCSS line M/s Swastik Mechnical 49 LILO of both 6.6 7.614 Revision of profile Stub Setting: 6 circuits of 220kV due to RoW issues. completed of 6 Badnagar-Ratlam Tower Erection: 4 DC line at 400kV completed out of 6 S/s Badnawar M/s Stringing: Not started NKR yet

50 LILO of both ckt of 14.5 14.5 No change Stub Setting: 60 Gandhisagar- completed of 60 Suwasra /Garoth Tower Erection: 59 132kV line at completed out of 60 Bhanpura 220kV Stringing: 4X14.28 S/s M/s Kalptaru Ratlam 51 LILO of 132kv 3 1.235 The earlier length Stub Setting: 8 Badod - Garoth was an estimation completed of 8 line at Shyamgarh which has been Tower Erection: 3 (D/C) M/s Bajaj finalized now. completed out of 8 Stringing: Not started yet 52 LILO of Ratlam- 9 7.414 The earlier length Stub Setting: 24 132kv was an estimation completed of 28 S/c line at which has been Tower Erection: Not DCDS finalized now. started yet (D/C) M/s Bajaj Stringing: Not started yet 53 LILO of second .5 .5 No change Completed ckt of Badod - Kota/Madok 220kV line at Bhanpura 220kV S/s M/s Kalptaru 54 LILO of second 12.2 12.2 No change Stub Setting: 31 ckt of Nagda- completed of 31 Neemuch 220kV Tower Erection: 31 line at Daloda completed of 31 220kV S/s M/s Stringing: 2 x 4.953 Kalptaru 55 LILO of Nagda 1.244 1.244 No change Completed 220-Ratadiya 132kV line at Unhel M/s Kalptaru Gwalior

8

S. Name of Line Total Total Route Remarks Project Status No Works Route Length in Length in Km. (As per Km. (As SMR July to per SMR December Jan to 2018, present June reporting 2018) period) 56 LILO of 132 KV 13.68 13.68 No change Completed Gwalior- Karera– Pichhore Line at Chinaur M/s Bajaj

57 LILO of 132 KV 0.108 0.108 No change Stub Setting: 2 Gwalior- Dabra – completed of 2 Datia –Pichhore Tower Erection: 2 Line at Dabra completed of 2 M/s Bajaj Stringing: Not started yet 58 Datiya 220- 34.038 34.038 No change Completed Bhander 132kV DCSS Line M/s Bajaj 59 Mehgaon 220- 29.74 29.74 No change Completed Pratappura 132kV DCSS line M/s Bajaj 60 Sabalgarh 220- 19.655 19.655 No change Completed Kelaras 132kV DCSS Line M/s Ba jaj 61 Malanpur 220- 14.5 14.5 No change Completed Gohad 132kV DCDS Line M/s. Bajaj 62 220 KV DCDS 94.512 94.512 No change Completed Morena 400 KV (CWRTL Adani) – Sabalgarh DCDS Line M/s L&T 63 220kv (Jarerua) 0.5 0.5 No change Completed DCDS LILO of Morena 400kV S/s (Adani)-Sabalgarh at Morena 220kV substation M/s L&T 64 Bhonra-Kapasi 22.569 22.569 No change Completed 132 kv DCSS line M/s L&T 65 Kolaras-Mada 20.293 20.293 No change Completed 132kV DCSS line M/s L&T 66 132kv DCDS 25.374 25.374 No change Stub Setting: Guna 220-Bhonra 75completed of 78 line M/s L&T Tower Erection: 70 completed of 78 Stringing:2 x 14.041

9

S. Name of Line Total Total Route Remarks Project Status No Works Route Length in Length in Km. (As per Km. (As SMR July to per SMR December Jan to 2018, present June reporting 2018) period) 67 LILO of one 7.396 7.396 No change Completed circuit of Malanpur- Mehgaon line at 400 KV S/s (CWRTL Adani) Morena M/s L&T 68 2nd circuit of 34.686 34.686 No change Completed Shivpuri 220- Kolaras 132kV DCSS line M/s L&T 69 2nd ckt of 28.708 28.708 No change Completed Malanpur- Morar 132kV line M/s L&T Sagar 70 Khurai- Khimlasa 20.937 20.937 No change Stub Setting: 71 132kV DCSS line completed of 71 M/s Bajaj Tower Erection: 30 completed of 71 Stringing: Not started yet

71 LILO of Mungaoli 8.32 8.32 No change Completed Traction Feeder to Mungaoli (D/C) M/s B.S. Ltd. 72 Ashoknagar 220- 30 30 No change Completed Kothiya 132kV DCSS Line M/s Bajaj 73 Sagar220- Rehli 38.458 38.583 Minor change Completed 132kV DCSS line M/s Kalptaru 74 2nd ckt of Sagar 8.77 8.77 No change Completed 220-Sagar 132kV (I/C) M/s Kalptaru 75 Stringing of 3rd 31.3 31.3 No change Completed conductor from Bina220 to Mungaoli M/s Kalptaru Mandsaur 76 LILO of both ckt 4.382 4.382 No change Completed of Badod- Kota/Modak 220kV line at Suwasra 220kV S/s (2XD/C M/s Kalptaru

10

S. Name of Line Total Total Route Remarks Project Status No Works Route Length in Length in Km. (As per Km. (As SMR July to per SMR December Jan to 2018, present June reporting 2018) period) 77 LILO of one ckt of 22.077 21.503 No change Completed Neemuch 220- Mandsaur 132kV line at Budha 132kvS/s M/s Kalptaru 78 LILO of both 1.423 1.423 No change Completed circuit of 132kV Gandhisagar- Suwasara/Garoth line at Suwasara 220kV Sub-station

11

Table no. 2: Details of Substations and Feeder Bays and project status S. Substation Name Capacity and associated Project Status No Feeder Bays (Given in percentage; C=Civil foundations S=Structure works E=Equipment works) Jabalpur 1 Balaghat/Kirnapur 400/132kv (2 x 100+40MVA) +400kv Completed FB(2) +132kv FB(4) 2 Waraseoni 132kV 40MVA+132kV FB(2) Completed 3 BadaMalehra 132/33kV 40 MVA+132kV FB(1) C:81% S: Not started yet E: Not started yet 4 Deonagar 132/33kV 40 MVA+132kV FB(1) C:100% S:97% E:Not started yet 5 Belkheda 132/33kV 40MVA+132kV FB(1) C:100% S: 100% E: 99% 6 Karakbel 132/33kV 40MVA+132kV FB(2) C:88% S: 17% E: Not started yet 7 Saori 132/33kV S/s (1X50) MVA; 132kV FB(1) Completed 8 Palohabada 132/33kV S/s (1X50) MVA; 132kV FB(1) C:99% S:79% E:61% 9 Patera 132/33kV S/s (1X50) MVA; 132kV FB(1) Completed Satna 10 Additional Transformer at Sidhi 220 (2nd) +160 MVA Completed 11 Additional Transformer at Kotar 220 (2nd) +160 MVA Completed 12 Additional Transformer at Chhatarpur (2nd) +160 MVA Completed 13 Satna-II 132/33kV S/s (2X50) MVA; 132kV FB(2) Completed 14 Shahdol 220/132kV S/s (Upgradation) (1X60) MVA; 220kV Completed FB(2)+132kV FB(1) Indore 15 Badnawar 400/220kv (2x315MVA) + 400kv FB Completed (4) + 220kv FB (4) +125MVAR bus Reactor 16 Upgradation of Chapda 132kv S/S to 220kv (1x160MVA) + 220kv C:89% FB(2) S:71% E:Nil 17 Upgradation of Depalpur 132kv S/s to 220kv (1x160MVA) + 220kv FB C:87% (1) S:8% E:Not started yet 18 Agrod 132/33kV 40MVA+132kV FB(1) Completed Barwaha 19 400/220kv additional transformer at 1x315 MVA Completed Chhegaon 400kv S/S 20 Teesgaon 132/33kV 40MVA+132kV FB(1) C:96% S:88% E:1% 21 Bistan 132/33 kV 40 MVA+ 132kV FB(1) C:75% S:Not started yet E:Not started yet 22 Pandhana 132/33kV 40MVA+132kV FB(2) Completed

12

S. Substation Name Capacity and associated Project Status No Feeder Bays (Given in percentage; C=Civil foundations S=Structure works E=Equipment works) 23 Singhana 132/33kV 40MVA+132kV FB(2) Completed 24 Talakpura 132/33kV 40MVA+132kV FB(1) Completed 25 Kukshi 220/132kv 160 MVA + 220kv FB(2) C:94% +132kv FB(1) S:Not started yet E:Not started yet 26 Chhanera 220/132kV S/s (2X160+1X50) MVA Completed 220kV FB(2)+132kV FB(3) 27 Singot 132/33kV S/s (1X50)MVA; 132kV FB(1) Completed Bhopal 28 Salamatpur 132kv/33kv 40 MVA +132kv FB(1) Completed 29 Intkhedi 132kv /33kv 63 MVA +132kv FB(2) Completed 30 400/220kv additional transformer at Bhopal 1x315 MVA Completed 400kv S/S 31 Additional Transformer at Mandideep 220 +160 MVA Completed (2nd) 32 Narsinghgarh 132/33kv 40MVA +132kv FB(1) C: 37% S:Not started yet E:Not started yet 33 Adampur 220/33kv 2x50MVA + 220kv FB(2) C:62% S:24% E:Not started yet 34 Bilkisganj 132/33kV S/s (1X50) MVA; 132kV FB(1) Completed 35 Khujner/sindaota132/33kV (1X50) MVA; 132kV FB(1) Completed 36 Bisnoor/Masod 132/33kV (1X50) MVA; 132kV FB(1) Completed Itarsi 37 Additional Transformer at Betul 220 (2nd) +160 MVA Completed 38 Silvani 132kv /33kv 40 MVA +132kv FB(1) C:98% S:38% E:Not started yet 39 Udaipura 132/33kv 40MVA + 132kv FB(2) Completed Ujjain 40 Chhayan 132/33kV 40MVA+132kV FB(1) Completed 41 400kv Bus Reactor at Nagda 400kv S/S 1X125 MVAR Completed 42 Shyamgarh 132/33kV 40MVA+132kV FB(2) C:46% S: Not started yet E: Not started yet 43 Suwasra 220/132kV S/s (2X160+1X50) MVA Completed 220kV FB(4)+132kV FB(4) 44 Unhel 132/33kV S/s (1X50) MVA; 132kV FB(2) Completed 45 Budha 132/33kV S/s (1X50) MVA; 132kV FB(2) Completed Gwalior 46 Chinaur 132/33kV 40MVA+132kV FB(1) Completed 47 Bhander 132/33kV 63MVA+132kV FB(2) Completed 48 Pratappura 132/33kV 40MVA+132kV FB(1) Completed 49 Kelaras 132/33kV 63MVA+132kV FB(1) Completed 50 Gohad 132/33kV 63MVA+132kV FB(2) Completed 51 Kapasi/ Paranth 132/33kv (1X50) MVA; 132kV FB(1) Completed

13

S. Substation Name Capacity and associated Project Status No Feeder Bays (Given in percentage; C=Civil foundations S=Structure works E=Equipment works) 52 Mada 132/33kV S/s (1X50) MVA; 132kV FB(1) Completed Sagar 53 Khimlasa 132/33kV 40MVA+132kV FB(1) C:53% S: Not started yet E: Not started yet 54 Mungaoli 132/33kV 63MVA+132kV FB(2) Completed 55 Kothiya 132/33kV 40MVA+132kV FB(1) Completed 56 Rehli 132/33kV S/s (1X50) MVA; 132kV FB(1) Completed

1.2 Purpose of the Report The report captures the overall social safeguards implementation progress in compliance to project’s Resettlement Framework and regulatory requirements. The various social safeguard related issues addressed during the reporting period has also been covered, with reference to the progress achieved and current status of reporting period.

1.2.1 The current report covers the implementation progress of social safeguards during July 2018 to December 2018.

1.3 Social Safeguard Categorisation 1.3.1 As per the Resettlement Plan prepared for the project, the project components are categorized as ‘B’ for Involuntary Resettlement (IR) and “C” for Indigenous Peoples according to ADB’s Safeguard Policy Statement, 2009 (SPS).

14

2.0 Project Implementation Status

2.1 Overview of Social Impacts 2.1.1 The Resettlement Plan (RP) prepared for the project has identified social impacts due to damages to crop, and other losses. The total compensation (for crop damages) distributed is Rs. 14,21,17,190. All substations so far are located on government waste land and no land has been acquired for the substations (except Palohabada where 0.4 hectares of private land has been acquired). The project will not have any impact on forest or forest dwelling communities. The land requirement for all the proposed substations is estimated to be 118.127 ha approximately. In case of transmission lines, land required for each tower bases will not exceed 9 square meters per 132 kV lines tower, 36 square meters per 220 kV lines tower and 289 square meters 400 kV lines tower. Therefore, only a very small amount of land will be consumed for the bases of transmission towers per person. For construction of sub- stations, land used is government waste land and no private acquisition land has taken place yet. In case of Transmission lines, compensation is being duly paid to affected farmers for loss of income.

2.2 Project Affected Persons 2.2.1 The construction of substations is not likely to affect any person as all substations so far are built on government wasteland (except Palohabada where 0.4 hectares of private land has been acquired). For transmission lines, as per data available, total affected persons so far are 9688. The implementation of transmission lines has affected 9688 persons, thus, a total of 9688 farmers have been paid compensation till date a sample copy of the processed compensation details of farmers has been attached as annexure 3. Which includes persons whose land is damaged, and trees and crops are coming within transmission corridor. During this reporting period, assessment of crop loss within transmission corridor is pending for some transmission lines due to either construction activity is not yet started or because of land record related matter. The compensation for constructioning access roads is also included in the crop compensation that is paid to the farmers. The details of affected persons for Transmission Lines are provided in Table No. 3.

Table no. 3: Affected Persons: Transmission Lines S. Name of Line Works No. of APs as per Area in Compensation No assessment hac. in Rs. Jabalpur 1 LILO of 400kv seoni to Bhilai S/C line at Foundation 12 2.375 311979 Balaghat/Kirnapur (D/C) Erection 11 1.723 283459 Stringing 0 0 0 Total 23 4.098 595438 2 LILO of 132kV Balaghat- Seoni/ Katangi line at Foundation 17 1.742 234525 Waraseoni 132kV S/s (2XD/C) Erection 9 0.604 83250 Stringing 0 0 0 Total 26 2.346 317775

15

S. Name of Line Works No. of APs as per Area in Compensation No assessment hac. in Rs. 3 LILO of both circuit of 132kV Balaghat- Foundation 9 1.28 186299 Bhanegaon Line at Blaghat/Kirnapur 400kV S/s Erection 9 1.1615 152444 (2XD/C) Stringing 15 1.653 119016 Total 33 4.0945 457759 4 Second circuit of Tikamgarh- Budhera 132kV Foundation 0 0 0 DCSS Line Erection 0 0 0 Stringing 34 1.065 86300 Total 34 1.065 86300 5 Narsinghpur 220- Devnagar 132kV DCSS Line Foundation 164 17.3795 2587195 Erection 17 2.1865 351730 Stringing 0 0 0 Total 181 19.566 2938925 6 Karakbel- Belkheda 132kV DCSS line Foundation 163 31.411 6246967 Erection 23 4.289 1356850 Stringing 0 0 0 Total 186 35.7 7603817 7 Narsinghpur 220kV Karakbel 132KV DCS line Foundation 138 19.245 2577426 Erection 39 4.648 1498125 Stringing 0 0 0 Total 177 23.892 4075551 8 Panagar 220-Patan 132kV DCSS line Foundation 24 8.63 657300 Erection 0 0 0 Stringing 0 0 0 Total 24 8.63 657300 9 Chhindwara 220- Saori 132kV DCSS line Foundation 128 15.6972 2380822 Erection 168 16.3838 2762562 Stringing 151 10.0405 1373440 Total 447 42.1215 6516824 10 Chichli 220- Palohabada 132kV DCSS line Foundation 17 2.85 750625 Erection 0 0 0 Stringing 0 0 0 Total 17 2.85 750625 11 132kv DCSS line from Damoh 220kv to Patera Foundation 298 54 5325950 132 kv substation Erection 223 50.835 5018210 Stringing 212 42.77 3907260 Total 733 147.605 14251420 12 Second circuit of 132kV Tap Line from Balaghat- Foundation 0 0 0 Katangi Erection 0 0 0 Stringing 333 62.337 495061 Total 333 62.337 495061 Satna 13 Second circuit 132kV of chhatarpur- Khajuraho Foundation 0 0 0 line Erection 0 0 0 Stringing 177 0 1842250 Total 177 0 1842250 14 LILO of second ckt of Bansagar-Satna 220kV line Foundation 0 0 0

16

S. Name of Line Works No. of APs as per Area in Compensation No assessment hac. in Rs. at Kotar 220kV S/s Erection 0 0 0 Stringing 88 0 1579450 Total 88 0 1579450 15 LILO of Satna - Maihar 132kV line at Satna-II Data for TLs are being collected 132kV S/s 16 LILO of second ckt of Birsinghpur - Amarkantak Foundatio 7 0 185700 220kV line at Shahdol 220kV s/s Erection 54 0 2425000 Stringing 0 0 0 Total 61 0 2610700 17 Birsinghpur 220-shahdol 132kV DCDS line Foundatio 17 0 344020 Erection 119 0 3092300 Stringing 0 0 0 Total 136 0 3436320 18 LILO of 132 Tikamgarh-Bijawar line for Data for TLs are being collected BadaMalehra Indore 19 LILO of one circuit of Ashta 400-Dewas 220 kv Foundation 23 3.25 443517 D/C line at Chapda 220kv S/s (D/C) Erection 0 0 0 Stringing 0 0 0 Total 23 3.25 443517 20 Pithampur 400 - Depalpur 220kv DCSS line Foundation 172 22.104 2941510 Erection 53 186.575 766173 Stringing 0 0 0 Total 225 208.679 3707683 21 Dewas 220- Agrod 132kv DCSS line Foundation 38 7.413 627020 Erection 0 0 0 Stringing 0 0 0 Total 38 7.413 627020 22 Dhar 220 - Teesgaon 132kv DCSS line Foundation 30 4.773 528253 Erection 0 0 0 Stringing 0 0 0 Total 30 4.773 528253 23 LILO of both Circuit of 400 kv Nagda-Rajgarh Foundation 11 2.191 186404 line at Badnawar (2 x D/C) Erection 9 1.898 195800 Stringing 0 0 0 Total 20 4.089 382204 24 Second Circuit of Kukshi Alirajpur 132kv line Foundation 0 0 0 Erection 0 0 0 Stringing 141 2.647 3865092 Total 141 2.647 3865092 Barwaha 25 LILO of 132 Khargone Bikayan line at 132 Kv Data for TLs are being collected sub-station Bistan 26 LILO of 132kv Chegaon Nepanagar line at Foundation 18 0.68 285390 Pandhana Erection 13 0.123 192831 Stringing 18 1.17 174308 Total 49 1.973 652529

17

S. Name of Line Works No. of APs as per Area in Compensation No assessment hac. in Rs. 27 LILO Manawar - Kukshi DCSS line at Singhana Foundation 133 13.817 1247024 (D/C) Erection 56 10.41 532274 Stringing 43 15.124 216820 Total 232 39.351 1996118 28 LILO of 132Kv Khargone -Julwaniya line at Foundation 7 0 69811 132Kv S/S Talakpura Erection 8 3.101 87347 Stringing 0 0 0 Total 15 3.101 157158 29 Julwaniya 400- Kukshi 220kv line (D/C) Foundation 116 14.657 1705858 Erection 34 5.943 627756 Stringing 0 0 0 Total 150 20.6 2333614 30 220kV DCDS Khandwa (400 PGCIL) to Chhanera Foundation 55 10.472 1330108 Line* Erection 56 11.491 1341624 *Earlier TPS- Chhanera 220kV DCDS Line Alignment changed Stringing 0 0 0 Total 111 21.963 2671732 31 Chhegaon 220- Singot 132kV DCSS Line Foundation 193 37.9512 3467275 Erection 219 50.42 3611913 Stringing 45 4.891 543548 Total 457 93.2622 7622736 32 Chhanera 220- Khirkiya 132kV DCSS Line Foundation 49 8.2409 1294570 Erection 5 0.925 175707 Stringing 234 26.1114 3055160 Total 288 35.2773 4525437 Bhopal 33 Bairagarh 220 - Intkhedi 132kv DCDS line Foundation 24 5.237 337170 Erection 13 1.2191 118234 Stringing 29 2.0391 276311 Total 66 8.4952 731715 34 Second circuit of Bairagarh – Shyampur Foundation 1 0.1465 40258 Erection 0 0 0 Stringing 22 0.6885 60630 Total 23 0.835 100888 35 Second circuit of Gairatganj - Vidisha 220 132kv Foundation 52 7.6266 692661 line Erection 0 0 0 Stringing 289 15.2984 840841 Total 341 22.925 1533502 36 Shujalpur- Narsinghgarh 220kv DCSS line Foundation 54 6.608 583650 (Initially charged on 132kv) Erection 0 0 0 Stringing 0 0 0 Total 54 6.608 583650 37 LILO of one circuit of Bhopal - Hosangabad Data for TLs are being collected 220kv D/C line at Adampur 220kv S/s (D/C) 38 Udaipura -Silvani 132kv DCSS line Foundation 89 9.154 1020780 Erection 6 0.4707 70605

18

S. Name of Line Works No. of APs as per Area in Compensation No assessment hac. in Rs. Stringing 0 0 0 Total 95 9.6247 1091385 39 LILO of Vidisha- Bairasiya Line at Salamatpur Foundation 2 0.196 26973 132 KV S/s Erection 0 0 0 Stringing 0 0 0 Total 2 0.196 26973 40 Mugaliyachhaap 220- Bikisganj 132kV DCDS line Foundation 35 8.0667 920105 Erection 0 0 0 Stringing 0 0 0 Total 35 8.0667 920105 41 132kv Rajgarh (Biaora) –Khujner/ Sindaota Line Data for TLs are being collected 42 LILO of one ckt of Vidisha Gairatganj at Raisen Data for TLs are being collected 132kV S/s Itarsi 43 Second circuit of Betul 220 Gudgaon 132kv line Foundation 0 0 0 Erection 0 0 0 Stringing 188 343.635 727932 Total 188 343.635 727932 44 Chichli 220- Udaipura 132kv DCDS line (220kv Foundation 225 460.4319 5659933 line charged at 132kv) Erection 175 137.807 4625170 Stringing 0 0 0 Total 400 598.2389 10285103 45 Betul 400 (PGCIL)- Betul 220kV DCDS line Foundation 15 3.001 220880 Erection 0 0 0 Stringing 5 0.402 21420 Total 20 3.403 242300 46 Lilo of 220kV Sarni-Padnhurna at 400kV (PGCIL) Foundation 142 26.489 1826285 s/s Betul Erection 7 0.8675 70420 Stringing 0 0 0 Total 149 27.3565 1896705 47 Betul 220- Bisnoor/Masod 132kV DCSS line Foundation 41 7.558 523800 Erection 0 0 0 Stringing 0 0 0 Total 41 7.558 523800 Ujjain 48 Badnagar 220- Chhayan 132kv DCSS line Foundation 216 30.5505 3704160 Erection 79 10.805 755825 Stringing 13 1.2505 175360 Total 308 42.606 4635345 49 LILO of Badnagar -Ratlam 220kv D/C line at Foundation 35 6.2275 810521 Badnagar 400kv S/s (2xD/C) Erection 56 10.6905 837188 Stringing 0 0 0 Total 91 16.918 1647709 50 LILO of both ckt of Gandhisagar - Suwasra/Garoth Foundation 78 20.1097 2580090 132kV line at Bhanpura 220kV S/s Erection 43 2.3313 352867 Stringing 0 0 0

19

S. Name of Line Works No. of APs as per Area in Compensation No assessment hac. in Rs. Total 121 22.441 2932957 Ratlam 51 LILO of 132kv Badod - Garoth line at Shyamgarh Data for TLs are being collected (D/C) 52 LILO of Ratlam - Meghnagar 132kv S/c line at Foundation 35 6.0618 745990 Petlawad DCDS (D/C) Erection 0 0 0 Stringing 0 0 0 Total 35 6.0618 745990 53 LILO of second ckt of Badod - Kota/Madok Foundation 0 0 0 220kV line at Bhanpura 220kV S/s Erection 0 0 0 Stringing 0 0 0 ( Small line, crop compensation not required) Total 0 0 0 54 LILO of second ckt of Nagda- Neemuch 220kV Foundation 46 6.6772 1521938 line at Daloda 220kV S/s Erection 76 6.6704 1584561 Stringing 34 2.7715 145507 Total 156 16.1191 3252006 55 LILO of Nagda 220-Ratadiya 132kV line at Unhel Foundation 13 1.2525 194594 Erection 14 3.805 317592 Stringing 13 0.5155 70895 Total 40 5.573 583081 Gwalior 56 LILO of 132 KV Gwalior- Karera Pichhor Line at Foundation 30 5.165 361728 Chinaur Erection 0 0 0 Stringing 10 1.033 46160 Total 40 6.198 407888 57 LILO of 132 KV Gwalior- Dabra – Datia – Data for TLs are being collected Pichhore Line at Dabra 58 Datiya220- Bhander 132kV DCSS Line Foundation 0 0 0 Erection 0 0 0 Stringing 18 2.218 132556 Total 18 2.218 132556 59 Mehgaon 220-Pratappura 132kV DCSS line Foundation 125 13.012 1097785 Erection 46 9.455 441374 Stringing 43 15.124 216820 Total 214 37.591 1755979 60 Sabalgarh 220- Kelaras 132kV DCSS Line Foundation 41 30.019 585579 Erection 51 57.801 535225 Stringing 0 0 0 Total 92 87.82 1120804 61 Malanpur 220- Gohad 132kV DCDS Line Foundation 76 15.122 861153 Erection 26 6.552 342265 Stringing 80 18.0924 277975 Total 182 39.7664 1481393 62 220 KV DCDS Morena 400 KV (CWRTL Adani) Data for TLs are being collected – Sabalgarh DCDS Line 63 220kv DCDS LILO of Morena 400kV s/s (Adani) Foundation 675 408.442 7431667 to Sabalgarh at Morena 220kV (Jarerua) s/s Erection 434 254.398 4325004 Stringing 53 38.912 305722

20

S. Name of Line Works No. of APs as per Area in Compensation No assessment hac. in Rs. Total 1162 701.752 12062393 64 Bhonra-Kapasi 132 kv DCSS line Foundation 186 0 2314949 Erection 0 0 0 Stringing 0 0 0 Total 186 0 2314949 65 Kolaras-Mada 132kV DCSS line Foundation 83 11.043 945001 Erection 5 0.424 34200 Stringing 168 14.08 944281 Total 256 25.547 1923482 66 132kv DCDS Guna 220-Bhonra line Foundation 60 0 896944 Erection 0 0 0 Stringing 0 0 0 Total 60 0 896944 67 LILO of one circuit of Malanpur- Mehgaon line at Foundation 42 32.204 701470 400 KV S/s (CWRTL Adani) Morena Erection 29 16.925 530600 Stringing 27 17.04 100240 Total 98 66.169 1332310 68 2nd circuit of Shivpuri 220- Kolaras 132kV DCSS Foundation 0 0 0 line Erection 0 0 0 Stringing 42 3.8709 200000 Total 42 3.8709 200000 69 2nd ckt of Malanpur- Morar 132kV line Foundation 0 0 0 Erection 0 0 0 Stringing 73 65.33 500980 Total 73 65.33 500980 Sagar 70 Khurai- Khimlasa 132kV DCSS line Foundation 69 10.167 669218 Erection 0 0 0 Stringing 0 0 0 Total 69 10.167 669218 71 LILO of Mungaoli Traction Feeder to Mungaoli Data for TLs are being collected (D/C) 72 Ashoknagar 220-Kothiya 132kV DCSS Line Foundation 73 22.287 1299707 Erection 70 10.792 642428 Stringing 50 7.266 217443 Total 193 40.345 2159578 73 Sagar220- Rehli 132kV DCSS line Foundation 145 33.968 1814885 Erection 59 11.552 713071 Stringing 0 0 0 Total 204 45.520 2527956 74 2nd ckt of Sagar 220-Sagar 132kV (I/C) Data for TLs are being collected 75 Stringing of 3rd conductor from Bina 220 to Foundation 53 39.4595 958956 Mungaoli Erection 43 11.967 721648 Stringing 83 60.45 760402 Total 179 111.876 2441006 Mandsaur 76 LILO of both ckt of Badod- Kota/Modak 220kV Data for TLs are being collected line at Suwasra 220kV S/s (2XD/C)

21

S. Name of Line Works No. of APs as per Area in Compensation No assessment hac. in Rs. 77 LILO of one ckt of Neemuch 220-Mandsaur Data for TLs are being collected 132kV line at Budha 132kvS/s 78 LILO of both ckt of 132kV Gandhisagar-Suwasra / Data for TLs are being collected Garoth line at Suwasra 220kV S/s *Earlier LILO of both ckt of Badod-Suwasra / Garoth 132kV line at Suwasra 220kV S/s Grand Total No. of APs as per Area in Compensation in assessment ha. Rs. Foundation 4600 1506.4412 77264378 Erection 2357 907.2493 41573632 Stringing 2731 777.8257 23279180 Total 9688 3191.5147 142117190

2.3 Impacts on Land 2.3.1 The construction of sub-stations is on government waste land (except Palohabada where 0.4 hectares of private land has been acquired). A total of 118.127ha of land has been allotted so far.

Table no. 4: Details of Land Allotment– Substation S. Substation Name Capacity and Area Affected (in Ownership No associated Feeder hectares) Bays Jabalpur 1 Balaghat/Kirnapur (2 x 100+40MVA) 10.840 Government Land 400/132kv +400kv FB(2) +132kv FB(4) 2 Waraseoni 132kV 40MVA+132kV 2.00 Government Land FB(2) 3 BadaMalehra 132/33kV 40 MVA+132kV 1.00 Government Land FB(1) 4 Deonagar 132/33kV 40 MVA+132kV 1.2 Government Land FB(1) 5 Belkheda 132/33kV 40MVA+132kV 2.7 Government Land FB(1) 6 Karakbel 132/33kV 40MVA+132kV 1.63 Government Land FB(2) 7 Saori 132/33kV S/s (1X50) MVA; 132kV 1.00 Government Land FB(1) 8 Palohabada 132/33kV S/s (1X50) MVA; 132kV 1.6 1.2 Government FB(1) Land and 0.4 private land 9 Patera 132/33kV S/s (1X50) MVA; 132kV 1.00 Government Land FB(1) Satna 10 Additional Transformer at +160 MVA The additional - Sidhi 220 (2nd) component is placed inside existing substation land and no land is acquired for same. 11 Additional Transformer at +160 MVA The additional - Kotar 220 (2nd) component is placed inside existing

22

S. Substation Name Capacity and Area Affected (in Ownership No associated Feeder hectares) Bays substation land and no land is acquired for same. 12 Additional Transformer at +160 MVA The additional - Chhatarpur (2nd) component is placed inside existing substation land and no land is acquired for same. 13 Satna-II 132/33kV S/s (2X50) MVA; 132kV 4.060 Government Land FB(2) 14 Shahdol 220/132kV S/s (1X60) MVA; 220kV 1.00 Government Land (Upgradation) FB(2)+132kV FB(1) Indore 15 Badnawar 400/220kv (2x315MVA) + 16.00 Government Land 400kv FB (4) + 220kv FB (4) +125MVAR bus Reactor 16 Upgradation of Chapda (1x160MVA) + 5.33 Government Land 132kv S/S to 220kv 220kv FB(2) 17 Upgradation of Depalpur (1x160MVA) + 1.00 Government Land 132kv S/s to 220kv 220kv FB (1) 18 Agrod 132/33kV 40MVA+132kV 0.72 Government Land FB(1) Barwaha 19 400/220kv additional 1x315 MVA The additional - transformer at Chhegaon component is placed 400kv S/S inside existing substation land and no land is acquired for same. 20 Teesgaon 132/33kV 40MVA+132kV 1.00 Government Land FB(1) 21 Bistan 132/33 kV 40 MVA+ 132kV 2.25 Government Land FB(1) 22 Pandhana 132/33kV 40MVA+132kV 1.07 Government Land FB(2) 23 Singhana 132/33kV 40MVA+132kV 1.00 Government Land FB(2) 24 Talakpura 132/33kV 40MVA+132kV 2.220 Government Land FB(1) 25 Kukshi 220/132kv 160 MVA + 220kv 1.00 Government Land FB(2) +132kv FB(1) 26 Chhanera 220/132kV S/s (2X160+1X50) MVA 1.00 Government Land 220kV FB(2)+132kV FB(3) 27 Singot 132/33kV S/s (1X50)MVA; 132kV 1.00 Government Land FB(1) Bhopal 28 Salamatpur 132kv/33kv 40 MVA +132kv 1.00 Government Land FB(1) 29 Intkhedi 132kv /33kv 63 MVA +132kv 1.00 Government Land FB(2) 30 400/220kv additional 1x315 MVA The additional -

23

S. Substation Name Capacity and Area Affected (in Ownership No associated Feeder hectares) Bays transformer at Bhopal component is placed 400kv S/S inside existing substation land and no land is acquired for same. 31 Additional Transformer at +160 MVA The additional - Mandideep 220 (2nd) component is placed inside existing substation land and no land is acquired for same. 32 Narsinghgarh 132/33kv 40MVA +132kv 6.00 Government Land FB(1) 33 Adampur 220/33kv 2x50MVA + 220kv 1.00 Government Land FB(2) 34 Bilkisganj 132/33kV S/s (1X50) MVA; 132kV 1.96 Government Land FB(1) 35 Khujner/sindaota132/33kV (1X50) MVA; 132kV 2.6 Government Land FB(1) Itarsi 36 Additional Transformer at +160 MVA The additional - Betul 220 (2nd) component is placed inside existing substation land and no land is acquired for same. 37 Silvani 132kv /33kv 40 MVA +132kv 1.29 Government Land FB(1) 38 Udaipura 132/33kv 40MVA + 132kv 6.073 Government Land FB(2) 39 Bisnoor/Masod 132/33kV (1X50) MVA; 132kV 1.00 Government Land FB(1) Ujjain 40 Chhayan 132/33kV 40MVA+132kV 0.25 Government Land FB(1) 41 400kv Bus Reactor at 1X125 MVAR The additional - Nagda 400kv S/S component is placed inside existing substation land and no land is acquired for same. 42 Shyamgarh 132/33kV 40MVA+132kV 2.74 Government Land FB(2) Gwalior 43 Chinaur 132/33kV 40MVA+132kV 2.31 Government Land FB(1) 44 Bhander 132/33kV 63MVA+132kV 0.99 Government Land FB(2) 45 Pratappura 132/33kV 40MVA+132kV 1.71 Government Land FB(1) 46 Kelaras 132/33kV 63MVA+132kV 2.142 Government Land FB(1) 47 Gohad 132/33kV 63MVA+132kV 1.00 Government Land FB(2) 48 Kapasi/ Paranth 132/33kv (1X50) MVA; 132kV 2.25 Government Land FB(1) 24

S. Substation Name Capacity and Area Affected (in Ownership No associated Feeder hectares) Bays 49 Mada 132/33kV S/s (1X50) MVA; 132kV 2.5 Government Land FB(1) Bina 50 Khimlasa 132/33kV 40MVA+132kV 0.789 Government Land FB(1) 51 Mungaoli 132/33kV 63MVA+132kV 2.225 Government Land FB(2) 52 Kothiya 132/33kV 40MVA+132kV 2.388 Government Land FB(1) 53 Rehli 132/33kV S/s (1X50) MVA; 132kV 3.54 Government Land FB(1) Ratlam 54 Suwasra 220/132kV S/s (2X160+1X50) MVA 7.5 Government Land 220kV FB(4)+132kV FB(4) 55 Unhel 132/33kV S/s (1X50) MVA; 132kV 1.00 Government Land FB(2)

56 Budha 132/33kV S/s (1X50) MVA; 132kV 1.45 Government Land FB(2)

2.4 Impacts on Structure All sub-stations sites so far except Palohabada are identified on government wasteland and do not impact any structure. In case of Palohabada, 0.4hectares of private land has been acquired through mutual consent. In case of transmission lines; no impact on any kind of structure has been identified till this reporting.

2.5 Crop Damage 2.5.1 The sub-stations sites are mostly on government wasteland so far ( except for Palohabada where 0.4 hectares has been acquired through mutual consent) and do not impact any standing crop. In case of transmission lines, contractors usually carry out project works post harvesting of crop, so as to minimize impact on standing crop. However, this is not possible in all cases and compensation is paid to farmers for loss of income due to damage of crops and tress etc. The kind of crop damaged due to construction of transmission lines is given below in table 5.

Table no. 5: Crop Damaged in TL’s

S. Name of Line Works Work Affected Crop No Description Jabalpur 1 LILO of 400kv Seoni to Bhilai S/C line at Foundation Gram Balaghat/Kirnapur (D/C) M/s BHEL Erection Paddy, Arhar Stringing ------2 LILO of 132kV Balaghat- Seoni/ Katangi Foundation Wheat, Gram line at Waraseoni 132kV S/s (2XD/C) M/s Erection Wheat, Gram Industrial House Stringing ------3 LILO of both circuit of 132kV Balaghat- Foundation Arhar, Gram

25

S. Name of Line Works Work Affected Crop No Description Bhanegaon Line at Balaghat/Kirnapur Erection Gram 400kV S/s (2XD/C) M/s Industrial House Stringing Paddy 4 Second circuit of Tikamgarh- Budhera Stringing Urad 132kV DCSS Line M/s B.S. Ltd. 5 Narsinghpur 220- Devnagar 132kV DCSS Foundation Sugarcane, Wheat, Gram, Masoor, Line M/s Bajaj Arhar Erection Sugarcane Stringing ------6 Karakbel- Belkheda 132kV DCSS line M/s Foundation Wheat, Sugarcane, Mung, Arhar, KDBL Masoor, Urad, Watermelon, Bottle Gourd Erection Sugarcane Stringing 7 Narsinghpur 220KV Karakbel 132KV DCS Foundation Wheat, Gram, Sugarcane, Masoor line M/s KDBL Erection Sugarcane, Arhar, Wheat, Coriander, Gram Stringing ------8 Panagar 220-Patan 132kV DCSS line M/s Foundation Wheat, Urad Bajaj Erection ------Stringing ------9 Chhindwara 220- Saori 132kV DCSS line Foundation Potato, Corn, Gram, wheat, Garlic, M/s Kalptaru Arhar, Cauliflower, Mung, Onion, Ginger, Pumpkin, Coriander Erection Corn, Arhar, Soyabean, Groundnut, Cauliflower, Ladyfinger, Ginger Stringing Cauliflower, Mung, Tomato, Pea, Garlic 10 Chichli 220- Palohabada 132kV DCSS line Foundation Arhar, Sugarcane M/s Kalptaru Erection ------Stringing ------11 132kv DCSS line from Damoh 220kv to Foundation Mung, Gram, Wheat Patera 132 kv substation M/s Kalptaru Erection Urad, Mung, Rice, Arhar Stringing Urad, Mung, Pea, Brinjal, Rice 12 Second circuit of 132kV Tap Line from Stringing Gram, Wheat Balaghat-Katangi M/s B.S.Ltd. Satna 13 Second circuit 132kV of Chhatarpur- Stringing Wheat Khajuraho line M/s B.S.Ltd. 14 LILO of second ckt of Bansagar-Satna Stringing Wheat 220kV line at Kotar 220kV S/s M/s Vikran 15 LILO of Satna - Maihar 132kV line at Data for TLs being collected Satna-II 132kV S/s 16 LILO of second ckt of Birsinghpur – Foundation Wheat Amarkantak 220kV line at Shahdol 220kV Erection Wheat, Alsi s/s M/s Vikran 17 Birsinghpur 220-Shahdol 132kV DCDS line Foundation Wheat M/s Vikran Erection Wheat Stringing ------18 LILO of 132 Tikamgarh-Bijawar line for Data for TLs being collected BadaMalehra Indore

26

S. Name of Line Works Work Affected Crop No Description 19 LILO of one circuit of Ashta 400-Dewas Foundation Gram, Garlic, Onion, Potato, 220 kv D/C line at Chapda 220kv S/s (D/C) Soyabean, Arhar, Mustard, Corn, M/s Bajaj Cotton Erection ------Stringing ------20 Pithampur 400 - Depalpur 220kv DCSS line Foundation Potato, Gram, Coriander, Wheat, M/s Bajaj Corn, Ladyfinger, Paddy, Garlic, Mung Erection Onion, Gram, Wheat, Coriander, Garlic Stringing ------21 Dewas 220- Agrod 132kv DCSS line M/s Foundation Wheat, Gram, Onion, Corn Swastik Mechnical Erection ------Stringing ------22 Dhar 220 - Teesgaon 132kv DCSS line M/s Foundation Wheat, Gram, Coriander, Ladyfinger, Bajaj Soyabean Erection ------Stringing ------23 LILO of both Circuit of 400 kv Nagda- Foundation Soyabean Rajgarh line at Badnawar (2 x D/C) M/s Erection Gram, Wheat, Pea, Garlic BHEL Stringing ------24 Second Circuit of Kukshi Alirajpur 132kv Stringing Wheat, Gram, Groundnut, Corn line M/s B.S.Ltd. Barwaha 25 LILO of 132 Khargone Bikayan line at 132 Data for TLs being collected Kv sub-station Bistan M/s Bajaj 26 LILO of 132kv Chegaon Nepanagar line at Foundation Onion, Wheat Pandhana M/s B.S.Ltd. Erection Onion, Wheat, Corn, Soyabean Stringing Chilly, Arhar, Gram 27 LILO Manawar - Kukshi DCSS line at Foundation Chilly, Wheat Singhana (D/C) M/s B.S.Ltd. Erection Onion, Garlic Stringing Onion, Garlic 28 LILO of 132Kv Khargone -Julwaniya line Foundation Chilly, Cotton, Arhar at 132Kv S/S Talakpura M/s B.S.Ltd. Erection Cotton Stringing ------29 Julwaniya 400- Kukshi 220kv line (D/C) Foundation Cotton, Chilly, Corn, Wheat M/s Bajaj Erection Cotton, Wheat, Gram Stringing ------30 220kV DCDS Khandwa (400 PGCIL) to Foundation Gram, Chilly, Cotton, Arhar, Onion, Chhanera line Chilly Erection Gram, Chilly Stringing ------31 Chhegaon 220- Singot 132kV DCSS Line Foundation Gram, Chilly, Soyabean, Arhar M/s Kalptaru Erection Soyabean, Arhar, Onion, Chilly, Cotton Stringing Gram, Chilly 32 Chhanera 220- Khirkiya 132kV DCDS Line Foundation Arhar, Wheat, Gram, Soyabean M/s Kalptaru Erection Arhar, Watermelon

27

S. Name of Line Works Work Affected Crop No Description Stringing Arhar, Gram Bhopal 33 Bairagarh 220 - Intkhedi 132kv DCDS line Foundation Soyabean, Wheat M/s P. S. Associated Erection Wheat, Gram Stringing Coriander, Wheat, Garlic 34 Second circuit of Bairagarh – Shyampur Foundation Onion M/s P. S. Associated Erection ------Stringing Onion, Gilki, Bitter Gourd, Soyabean, Arhar, Coriander 35 Second circuit of Gairatganj - Vidisha 220 Foundation Gram, Wheat, Arhar 132kv line M/s Punj Lyod Stringing Wheat, Gram, Garlic, Masoor 36 Shujalpur- Narsinghgarh 220kv DCSS line Foundation Wheat, Gram, Masoor, Coriander, (Initially charged on 132kv) M/s Bajaj Onion Erection ------Stringing ------37 LILO of one circuit of Bhopal - Data for TLs being colected Hosangabad 220kv D/C line at Adampur 220kv S/s (D/C) 38 Udaipura -Silvani 132kv DCSS line M/s Foundation Gram, Wheat, Arhar, Pea, Masoor, Bajaj Coriander, Sugarcane Erection Mung Stringing ------39 LILO of Vidisha- Bairasiya Line at Foundation Wheat Salamatpur 132 KV S/s M/s P. S. Erection ------Associated Stringing ------40 Mugaliyachhaap 220- Bikisganj 132kV Foundation Wheat, Ladyfinger DCDS line M/s Punj Lyod Erection ------Stringing ------41 132kv Rajgarh (Biaora) –Khujner/ Sindaota Data for TLs being collected Line 42 LILO of one ckt of Vidisha Gairatganj at Data for TLs being collected Raisen 132kV S/s Itarsi 43 Second circuit of Betul 220 Gudgaon Stringing Gram, Wheat, Sugarcane 132kv line M/s Punj Lyod 44 Chichli 220- Udaipura 132kv DCDS line Foundation Mung, Arhar, Paddy, Gram (220kv line charged at 132kv) M/s B.S. Ltd. Erection Arhar, Paddy, Sugarcane, Mung, Gram, Wheat Stringing ------45 Betul400 (PGCIL)- Betul 220kV DCDS Foundation Gram, Wheat, Arhar, Soyabean line M/s Punj Lyod Erection ------Stringing Soyabean 46 LILO of 220kV Sarni-Pandhurna at Foundation Soyabean, Wheat, Gram, Arhar, 400kV (PGCIL) Substation Betul M/s Sugarcane Punj Lyod Erection Soyabean, Gram Stringing ------47 Betul 220- Bisnoor/Masod 132kV DCSS Foundation Arhar, Soyabean, Gram line M/s Punj Lyod Erection ------Stringing ------

28

S. Name of Line Works Work Affected Crop No Description Ujjain 48 Badnagar 220- Chhayan 132kv DCSS line Foundation Wheat, Garlic, Gram M/s Swastik Mechnical Erection Wheat Stringing Wheat, Garlic, Onion, Gram 49 LILO of Badnagar -Ratlam 220kv D/C line Foundation Gram, Garlic, Wheat at Badnagar 400kv S/s (2xD/C) Erection Soyabean, Gram, Garlic, Wheat Stringing ------50 LILO of both ckt of Gandhisagar - Foundation Gram, Garlic, Wheat, Coriander Suwasra/Garoth 132kV line at Bhanpura Erection Coriander, Onion, Gram, Garlic 220kV S/s Stringing ------51 LILO of 132kv Badod - Garoth line at Data for TLs being collected Shyamgarh (D/C) Ratlam 52 LILO of Ratlam- Meghnagar 132kv S/c line Foundation Soyabean, Onion, Wheat at Petlawad DCDS (D/C) M/s Bajaj Erection ------Stringing ------53 LILO of second ckt of Badod - Kota/Madok Small line: No compensation required 220kV line at Bhanpura 220kV S/s M/s Kalptaru 54 LILO of second ckt of Nagda- Neemuch Foundation Garlic, Gram 220kV line at Daloda 220kV S/s M/s Erection Garlic, Gram, Alsi Kalptaru Stringing Garlic, Gram 55 LILO of Nagda 220-Ratadiya 132kV line at Foundation Garlic, Gram, Wheat Unhel M/s Kalptaru Erection Garlic, Soyabean, Gram, Wheat Stringing Garlic, Gram, Wheat Gwalior 56 LILO of 132 KV Gwalior- Karera Pichhor Foundation Moong, Wheat, Pea, Gram, Mustard Line at Chinaur Erection ------Stringing Tilli, Urad, Bazra, Gawar 57 LILO of 132 KV Gwalior- Dabra – Datia – Data for TLs being collected Pichhore Line at Dabra 58 Datiya 220- Bhander 132kV DCSS Line Foundation ------M/s Bajaj Erection ------Stringing Urad, Mung, Bajra 59 Mehgaon 220-Pratappura 132kV DCSS line Foundation Mustard, Sesame, Wheat, Gram, M/s Bajaj Masoor Erection Sesame, Garlic, Mustard Stringing Mustard, Arhar, Sesame, Mung, Bajra 60 Sabalgarh 220- Kelaras 132kV DCSS Line Foundation Bajra, Arhar, Mustard, Sesame M/s Bajaj Erection Sesame, Ladyfinger, Wheat, Mustard, Garlic, Urad 61 Malanpur 220- Gohad 132kV DCDS Line Foundation Sesame, Mustard, Gram, Wheat M/s. Bajaj Erection Sesame Stringing Paddy, Sesame, Mung,Mustard 62 220 KV DCDS Morena 400 KV (CWRTL Data for TLs being collected Adani) – Sabalgarh DCDS Line 63 220kv DCDS LILO of Morena 400kV s/s Foundation Wheat, Tilli, Bazra, Mustard, Gram, (Adani) to Sabalgarh at Morena 220kV Arhar

29

S. Name of Line Works Work Affected Crop No Description (Jarerua) s/s Erection Gram, Wheat, Mustard,Moong, Arhar Stringing Wheat, Mustard, Gram 64 Bhonra-Kapasi 132 kv DCSS line Foundation Bazra, Mustard, Gram Erection ------Stringing ------65 Kolaras-Mada 132kV DCSS line Foundation Gram, Soyabean, Sugarcane, Wheat Erection Wheat Stringing Tomato, Peanut, Mustard, Gram, Soyabean, Onion, Urad 66 132kv DCDS Guna 220-Bhonra line Foundation Wheat, Gram, Mustard, Coriander, Soyabean, Urad, Moong Erection ------Stringing ------67 LILO of one circuit of Malanpur- Mehgaon Foundation Wheat, Mustard, Paddy, Bazra line at 400 KV S/s (CWRTL Adani) Erection Tilli, Bazra, Wheat, Moong Morena Stringing Tilli, Paddy, Jawar, Bazra 68 2nd circuit of Shivpuri 220- Kolaras 132kV Stringing Tomato, Urad, Soyabean, Sweet DCSS line Potato, Peanut 69 2nd ckt of Malanpur- Morar 132kV line Stringing Bajra, Paddy, Sesame, Mung, Urad, M/s L&T Arhar Sagar 70 Khurai- Khimlasa 132kV DCSS line Foundation Gram, Masoor, Wheat M/s Bajaj Erection ------Stringing ------71 LILO of Mungaoli Traction Feeder to Data for TLs being collected Mungaoli (D/C) 72 Ashoknagar 220-Kothiya 132kV DCSS Foundation Soyabean, Wheat, Gram, Sugarcane Line M/s Bajaj Erection Wheat, Soyabean, Urad, Masoor Stringing Sugarcane, Gram, Coriander, Wheat 73 Sagar220- Rehli 132kV DCSS line Foundation Gram, Onion, Wheat, Masoor, M/s Kalptaru Soyabean, Mung Erection Soyabean, Gram 74 2nd ckt of Sagar 220-Sagar 132kV (I/C) Data for TLs being colected 75 Stringing of 3rd conductor from Bina 220 to Foundation Wheat, Soyabean Mungaoli M/s Kalptaru Erection Wheat, Soyabean, Gram Stringing Gram, Wheat, Masoor, Soyabean Mandsaur 76 LILO of both ckt of Badod- Kota/Modak Data for TLs being collected 220kV line at Suwasra 220kV S/s (2XD/C) 77 LILO of one ckt of Neemuch 220-Mandsaur Data for TLs being collected 132kV line at Budha 132kvS/s 78 LILO of both ckt of 132kV Gandhisagar- Data for TLs being collected Suwasra / Garoth line at Suwasra 220kV S/s 2.6 Impacts on Tree At all sub-stations sites, tree cutting was not involved as they are on government wasteland. In case of transmission lines, numbers of trees that will be cut are given in table 6 below.

30

Table no. 6: Details of Tree Cutting in Transmission Lines S. Name of Line Works Total no of No trees to be cut. Nil means no trees will be cut. Jabalpur 1 LILO of 400kv seoni to Bhilai S/C line at Balaghat/Kirnapur (D/C) 30 2 LILO of 132kV Balaghat- Seoni/ Katangi line at Waraseoni 132kV S/s (2XD/C) 170 3 LILO of both circuit of 132kV Balaghat-Bhanegaon Line at Balaghat/Kirnapur 400kV 38 S/s (2XD/C) 4 Second circuit of Tikamgarh- Budhera 132kV DCSS Line 1452 5 Narsinghpur 220- Devnagar 132kV DCSS Line Nil 6 Karakbel- Belkheda 132kV DCSS line Nil 7 Narsinghpur 220KV Karakbel 132KV DCS line Nil 8 Panagar 220-Patan 132kV DCSS line Nil 9 Chhindwara 220- Saori 132kV DCSS line 205 10 Chichli 220- Palohabada 132kV DCSS line Nil 11 132kv DCSS line from Damoh 220kv to Patera 132 kv substation 18 12 Second circuit of 132kV Tap Line from Balaghat-Katangi 532 Satna 13 Second circuit 132kV of Chhatarpur- Khajuraho line 1822

14 LILO of second ckt of Bansagar-Satna 220kV line at Kotar 220kV S/s 175 15 LILO of Satna - Maihar 132kV line at Satna-II 132kV S/s NIl 16 LILO of second ckt of Birsinghpur - Amarkantak 220kV line at Shahdol 220kV s/s 520 17 Birsinghpur 220-shahdol 132kV DCSS line 1050 18 LILO of 132 Tikamgarh-Bijawar line for BadaMalehra 100 Indore 19 LILO of one circuit of Ashta 400-Dewas 220 kv D/C line at Chapda 220kv S/s (D/C) 1 20 Pithampur 400 - Depalpur 220kv DCSS line 14 21 Dewas 220- Agrod 132kv DCSS line 3 22 Dhar 220 - Teesgaon 132kv DCSS line Nil 23 LILO of both Circuit of 400 kvNagda-Rajgarh line at Badnawar (2 x D/C) Nil 24 Second Circuit of KukshiAlirajpur 132kv line 492 Barwaha 25 LILO of 132 KhargoneBikayan line at 132 Kv sub-station Bistan Nil 26 LILO of 132kv ChegaonNepanagar line at Pandhana Nil 27 LILO Manawar - Kukshi DCSS line at Singhana (D/C) Nil 28 LILO of 132Kv Khargone -Julwaniya line at 132Kv S/S Talakpura Nil 29 Julwaniya 400- Kukshi 220kv line (D/C) Nil 30 220kV DCDS Khandwa(400 PGCIL) to Chhanera line (Earlier 220kV DCDS Malwa NIl TPS-Chhanera line)* *Earlier Malwa TPS- Chhanera 220kV DCDS Line alignment Changed 31 Chhegaon 220- Singot 132kV DCDS Line Nil 32 Chhanera 220- Khirkiya 132kV DCDS Line Nil Bhopal 33 Bairagarh 220 - Intkhedi 132kv DCDS line Nil 34 Second circuit of Bairagarh – Shyampur Nil

31

S. Name of Line Works Total no of No trees to be cut. Nil means no trees will be cut. 35 Second circuit of Gairatganj - Vidisha 220 132kv line Nil 36 Shujalpur- Narsinghgarh 220kv DCSS line (Initially charged on 132kv) Nil 37 LILO of one circuit of Bhopal - Hoshangabad 220kv D/C line at Adampur 220kv S/s Nil (D/C) 38 Udaipura -Silvani 132kv DCSS line Nil 39 LILO of Vidisha- Bairasiya Line at Salamatpur 132 KV S/s Nil 40 Mugaliyachhaap 220- Bikisganj 132kV DCDS line Nil 41 132kv Rajgarh (Biaora) –Khujner/ Sindaota Line Nil 42 LILO of one ckt of VidishaGairatganj at Raisen 132kV S/s Nil Itarsi 43 Second circuit of Betul 220 Gudgaon 132kv line Nil 44 Chichli 220- Udaipura 132kv DCDS line (220kv line charged at 132kv) 47 45 Betul400 (PGCIL)- Betul 220kV DCDS line Nil 46 LILO of 220kV Sarni-Pandhurna at 400kV (PGCIL) Substation Betul Nil 47 Betul 220- Bisnoor/Masod 132kV DCSS line Nil Ujjain 48 Badnagar 220- Chhayan 132kv DCSS line Nil 49 LILO of both circuits of 220kV Badnagar-Ratlam DC line at 400kV S/s Badnawar Nil 50 LILO of both ckt of Gandhisagar - Suwasra/Garoth 132kV line at Bhanpura 220kV S/s Nil Ratlam 51 LILO of 132kv Badod - Garoth line at Shyamgarh (D/C) 3 52 LILO of Ratlam - Meghnagar 132kv S/c line at Petlawad DCDS (D/C) Nil 53 LILO of second ckt of Badod - Kota/Madok 220kV line at Bhanpura 220kV S/s Nil 54 LILO of second ckt of Nagda- Neemuch 220kV line at Daloda 220kV S/s 33 55 LILO of Nagda 220-Ratadiya 132kV line at Unhel Nil Gwalior 56 LILO of 132 KV Gwalior- Karera Pichhor Line at Chinaur Nil 57 LILO of 2nd circuit of 132kV Gwalior-Dabra /Datia-Pichore line at Dabra Nil 58 Datiya220- Bhander 132kV DCSS Line Nil 59 Mehgaon 220-Pratappura 132kV DCSS line Nil 60 Sabalgarh 220- Kelaras 132kV DCSS Line Nil 61 Malanpur 220- Gohad 132kV DCDS Line (M/S. Bajaj) Nil 62 220 KV DCDS Morena 400 KV (CWRTL Adani) – Sabalgarh DCDS Line Nil 63 220kv DCDS LILO of Morena 400kV S/s (Adani) to Sabalgarh at Morena 220kV Nil (Jarerua) s/s 64 Bhonra-Kapasi 132 kv DCSS line Nil 65 Kolaras-Mada 132kV DCSS line Nil 66 132kv DCDS Guna 220-Bhonra line Nil 67 LILO of one circuit of Malanpur- Mehgaon line at 400 KV S/s (CWRTL Adani) Nil Morena 68 2nd circuit of Shivpuri 220- Kolaras 132kV DCSS line Nil 69 2nd ckt of Malanpur- Morar 132kV line Nil Sagar 70 Khurai- Khimlasa 132kV DCSS line Nil

32

S. Name of Line Works Total no of No trees to be cut. Nil means no trees will be cut. 71 LILO of Mungaoli Traction Feeder to Mungaoli (D/C) Nil 72 Ashoknagar 220-Kothiya 132kV DCSS Line Nil 73 Sagar220- Rehli 132kV DCSS line Nil 74 2nd ckt of Sagar 220-Sagar 132kV (I/C) Nil 75 Stringing of 3rd conductor from Bina220 to Mungaoli Nil Mandsaur 76 LILO of both ckt of Badod- Kota/Modak 220kV line at Suwasra 220kV S/s (2XD/C) 17 77 LILO of one ckt of Neemuch 220-Mandsaur 132kV line at Budha 132kvS/s 88 78 LILO of both circuit of 132kV Gandhisagar-Suwasara/Garoth line at Suwasara 220kV Nil Sub-station* *Earlier LILO of both ckt of Badod-Suwasra / Garoth 132kV line at Suwasra 220kV S/s

2.7 Impact on Livelihood Impacts on livelihood are temporary and compensation is paid for transmission lines construction and stringing works. Once the lines are built, regular agriculture activity can be carried out. Hence, the livelihood is not affected in any permanent manner.

2.8 Impacts on Common Property Resources (CPR) The sub-stations site and the transmission lines identified for the project do not impact any CPR’s.

3.0 Compensation

3.1 Land Compensation 3.1.1 A total of 0.4 hecatres of private land has been acquired for the project and compensation of INR 26,96,800 lakhs has been paid.

3.2 Compensation Status for Crop, Trees and Land Damaged 3.2.1. Cumulatively till end of reporting period, INR. Rs. 14,21,17,190has been paid to affected persons for loss of their standing crops and land damaged due to tower footings. The payment for land damage, loss of crop and trees is presently underway for some lines.

3.3 Relocation of CPR’s Impact on CPR’s is not recorded till end of reporting period. However, if any such impact is identified, after assessment and after verification the replacement cost shall be provided in line with provision in the project’s RP.

33

4.0 Consultation and Disclosures

4.1 Consultation

4.1.1 The implementation of R&R activities is a multifaceted task demanding constant monitoring during various stages of implementation. Engagement of stakeholders during various stages of project is necessary due to dynamics at different stakeholder level that might create more challenges for the program implementation. A continuous engagement with affected persons is necessary to ensure their participation, identify problems, creates ownership on program and for smooth sailing of the project. Attendance list of people who participated in consultation process is given in annexure 1 and photographs of site visits are given in annexure 2.

4.1.2. During this reporting period, site visits were undertaken for holding direct consultations with affected persons. The main objective of the site visits were to understand and check the compensation disbursement process to the affected persons for land damaged. Public consultation was organised with affected persons for various transmission lines.

4.1.3 The key findings of the consultation meetings were:  People were generally supportive of the project but wanted construction activity to be completed during non cropping season and between harvests.  People wanted to receive regular updates about statuses of their compensation and cheque amount.  Affected persons were satisfied in general and were willing to support the project.

4.2 Disclosures 4.2.1 To ensure transparency in planning and active involvement of APs and other stakeholders, the project information, Short Resettlement Plan report will be uploaded in the official website of the EA and ADB. The final resettlement plan will be uploaded after the final approval from ADB. The summary of the final RP will be made available in vernacular language. The official of IA will continue interact with affected persons and information dissemination through consultation will continue throughout Investment Program implementation period.

34

5.0 Grievance Redress Mechanism 5.1 The Grievance redress committee is set up by MP Transco-PMU and consists of representatives from the local Panchayat Head, a District Revenue Commissioner, representative from the EPC Contractor(s) only during construction phase, designated staff of MP Transco-PMU on safeguards, Manager/Director of MP Transco-PMU, and a witness of the complainant/affected person .

5.2. Responsibilities: The GRC is expected to: (i) resolve issues on land acquisition (if any), compensation to temporary damages to crops and plants, and other use of land such as borrow areas for transmission towers and substations; (ii) convene twice a month to review complaints lodged (if any), (iii) record the grievances and resolve the issues within a month (30 days) from the date the grievance was filed, (iv) report to the complainant(s) the status of grievance resolution and the decisions made.

5.3. Procedures: Minor grievances on compensation or environmental issue during construction will be resolved onsite through the EPC Contractor(s) Project Site Engineer. As a formal process of grievance resolution, the procedure is described below.

(i) Affected persons (APs) are informed in writing by MP Transco-PMU (or designated representative) of the damages and entitlements for compensation. If the APs are satisfied, compensation can be claimed from MP Transco-PMU through the EPC Contractor(s). If the APs are not satisfied, they can request for clarification from MP Transco-PMU. If the APs are not convinced with the outcome, they can file the grievance to the GRC with the help of MP Transco-PMU who will provide the written documentation.

(ii) The GRC conducts a hearing of the grievance in the presence of the APs and will provide a decision within 15 days from the receipt of the complaint. Minutes of the meeting are approved by MP Transco-PMU and provided to the APs including the decision made by the GRC. If the APs are satisfied with the GRC decision, they can claim the compensation from MP Transco-PMU and/or EPC Contractor(s).

(iii) Records of all grievances received for the subprojects are summarized region-wise in table 7.0.

Table no. 7: Grievance Redress Status S. No Name of Region Total no. of Grievances Remarks grievances Settled received 1. Jabalpur NIL NA NA 2. Satna NIL NA NA 3. Indore NIL NA NA 4. Barwaha NIL NA NA

35

S. No Name of Region Total no. of Grievances Remarks grievances Settled received 5. Bhopal NIL NA NA 6. Itarsi NIL NA NA 7. Ujjain NIL NA NA 8. Ratlam NIL NA NA 9. Gwalior NIL NA NA 10. Sagar NIL NA NA

36

6.0 Institutional Arrangements 6.1. The Madhya Pradesh Power Transmission Company Ltd. (MPPTCL) serves as the executing agencies (EAs) and implementing agencies (IAs) for the project. MPPTCL have established project management units (PMUs) to implement the ADB loans in Madhya Pradesh Power Sector Program. They serve as PMUs of the proposed project. Field level staff/engineer is deputed at divisional level who assumes primary responsibility for the environmental and social assessment as well as implementation of RPs for their respective components. Each PMU is required to designate a social development specialist within the PMU along with other engineering units to address the social and resettlement issues of the program. For RP implementation, PMU carried out the overall coordination, preparation, planning, implementation, and financing. The EA ensures that key institutions including local governments are involved in RP updating and implementation. The PMUs are responsible for managing the site activities related to safeguards and work closely with the field level staff.

37

7.0 Monitoring and Evaluation 7.1 Monitoring is the responsibility of the EAs/IAs. Regular monitoring activities are carried out internally by MPPTCL and their PMUs to assess resettlement implementation progress and identifying potential difficulties and problems. RP implementation is closely monitored through internal monitoring arrangements, to assess resettlement progress and identify potential difficulties and problems.

7.2 MPPTCL monitors the progress of implementation of safeguard plans, verifies the compliance with safeguard measures and their progress toward intended outcomes, documents and discloses monitoring results identifies necessary corrective and preventive actions in the periodic monitoring reports and submits periodic monitoring reports (bi-annual) on safeguard measures as agreed with ADB.

7.3 PMU will be responsible for managing and maintaining affected person databases, documenting the results of the affected person census. Semi-annual monitoring reports documenting progress on resettlement implementation and resettlement plan completion reports will be provided to ADB for review.

7.5 During this reporting period, the consultant has visited various project sites to conduct field visits and to scrutinize overall implementation of social and environmental measures of the project.

7.6. Monitoring and evaluation reports documenting progress on resettlement implementation and RP completion reports will be provided bi-annually by the PMU to ADB for review.

38

8.0 Conclusion 8.1 The allotment of government waste land is completed for construction of all substations and for one substation, Palohabada private land has been acquired. In case of transmission lines, compensation is being duly paid by cheque to affected persons. A total of 9688 farmers have been paid compensation till date.

8.2 During this reporting period, in case of four transmission lines, there have been changes in length and alignment. In case of a few lines, it is due to estimate (during route survey) and actual difference in measurement while in some cases, it is due to RoW issues. The changes in length are minor and not likely to cause any residual impacts.

8.3. Executing Agency is closely monitoring and coordinating with respective departments to expedite RP activities implementation and resolving of any social issues, to complete all social safeguard activities. All divisions are required to maintain grievance registers for recording any grievances from the public.

39

Annexure 1: Public Consultation Attendance List

40

41

42

Annexure 2: Photographs of site visit and Consultation

43

Annexure 3: Sample copy of Crop Compensation paid to farmers

44

(English Translation) Crop Compensation paid to farmers for crop damage during construction of 132 kv DCSS Damoh- Patera line, Tehsil- Damoh, District -Damoh

S. Location Name of Work Name of Farmer Father/Hus. Village Tehsil Khasra No. Crop Area in Rate Compensation No. no. and Name (Block) Sqr. Amount (Rs.) work Meter 1 20/2 Erection (Road) Aalok Kumar Pande Ram Kishan Gunji Damoh 164, 162 Moong 270x5 10/- 13500 Pande 2 20/2 Erection (Road) Urmila Pande Ram Kishan Gunji Damoh 165,158 Moong 270x5 10/ 13500 Pande 3 22A/2 Erection (Road) Damodar Yadav Komal Singh Gunji Damoh 192/2, 190/1 Moong 290x5 10/ 14500 Yadav 4 19/1,19/2 Foundation Dilip Ahirwar Sammu Gunji Damoh 145 Moong 200x5 10/ 10000 (Road) 5 24/0 Erection Babulal Sahu Kishri Sahu Hindoriya Damoh 1339,1342/1, Moong 70x35 10/ 24500 1342/3 6 24A/0 Erection Sachin Sahu Lal Sahu Hindoriya Damoh 249/7, 323 Moong 70x70 10/ 49000 7 22/0 Erection Pyarelal Kasiram Hindoriya Damoh 942, 943, 1007 Moong 70x70 10/ 49000 Chaourasiya Chaurasiya 8 22A/1 Erection (Road) Gopal PrasadYadav Halku Ram Hindoriya Damoh 989/3, 989/9 Moong 300x5 10/ 15000 Yadav 9 25/1 Erection Jay Prakash Aathiya Bhure Kherwa Damoh 122 Moong 50x50 10/ 25000 10 22/1 Erection Sachendra Singh Malkhan Singh Hindoriya Damoh 1010/1, 1019, Moong 50x50 10/ 25000 Thakur 120/1 11 20/8 Erection (Road) Punnalal Patel Uttam Singh Hindoriya Damoh 581/1, 135/1 Moong 50x50 10/ 25000 12 20A/1 Erection Bhojraj Soni Mohan Lal Soni Hindoriya Damoh 1054/1, Moong 50x50 10/ 25000 13 20/8 Erection Md. Yaasin Abdul Halim Hindoriya Damoh 158/1, 158/2, Moong 300x5 10/ 15000 158/3, 158/4 14 20A/0 Erection Halki Bai Sadhu Ram Hindoriya Damoh 3/11 Moong 60x60 10/ 36000 Ahilwal 15 22A/2 Erection (Road) Rajesh Sundar Hindoriya Damoh 175/1 Moong 280x5 10/ 14000

45

16 20/8 Erection (Road) Md. Salim Khan Abdul Halim Hindoriya Damoh 47/2 Moong 100x5 10/ 5000 Khan 17 22A/2 Erection Durga Bai Yadav Dashrath Yadav Hindoriya Damoh 961/2, 962/2, Moong 50x50 10/ 25000 961/7 18 25/2 Erection Dayaram Aathiya Chetu Lal Kherwa Damoh 103/1, 259/4, Moong 50x50 10/ 25000 896 19 25/1 Erection Komal Yadav Gopal Yadav Hindoriya Damoh 1050/2, Moong 60x30 10/ 18000 20 21/1 Erection Nanhe Lal Sahu Parmanand Sahu Hindoriya Damoh 1050/2,1050/5 Moong 60x30 10/ 18000 1050/4 21 21/2 Erection (Road) Gopal Prasad Yadav Halku Yadav Hindoriya Damoh 929, 938/3, Moong 330x5 10/ 16500 974/2 22 19/1 Erection (Road) Hari Singh Puran Singh Gunji Damoh 117,118,380, Moong 60x60 10/ 36000 378/1 23 22A/3 Erection (Road) Pratima Jain - Hindoriya Damoh 173/2 Moong 290x5 10/ 14500 24 19/2 Erection Dropti Bai Heera Singh Gunji Damoh 384/2, 387, Moong 60x60 10/ 36000 388 25 22/0 Erection Komal Prasad Gopal Prasad Hindoriya Damoh 1050/2, Moong 70x70 10/ 49000 26 22/0 Erection (Road) Komal Prasad Gopal Prasad Hindoriya Damoh 1050/2, Moong 100x5 10/ 5000 27 21/0 Erection JagdishYd Singh Bhujbal Singh Hindoriya Damoh 224,1050/4 235/1, Moong 60x60 10/ 36000 Thakur 1002/1 28 24/0 Erection Chandra Prakash Bhuwani Singh Hindoriya Damoh 317, 320, 330 Moong 70x70 10/ 49000 Pyasi 29 24/0 Erection (Road) Chandra Prakash Bhuwani Singh Hindoriya Damoh 317, 320, 330 Moong 300x5 10/ 15000 Pyasi 30 22B/0 Erection Gopal Prasad Yadav Halku Yadav Hindoriya Damoh 998/6, 1051/5, Moong 70x70 10/ 49000 1052/5

46