Westcoast Energy Inc. Westcoast Energy Inc. fonds. – 1897-2002, predominant 1949-2002. 5.2 m of textual records and other material.

Administrative History: Headquartered in , , Westcoast Energy Inc. is a natural gas company with operations across and interests in international energy companies. Its main activities include natural gas gathering, processing, transmission, storage, distribution and marketing, as well as power generation and other energy services services. Its predecessor company, Westcoast Transmission Company Limited, was incorporated by a special act of Parliament in 1949. It was established by Frank McMahon, an oilman who had began company West Turner Petroleums in 1936 with his brothers George and John. After making a substantial oil strike in 1939, McMahon purchased two smaller companies and merged them with West Turner in 1947 to form a holding company called Pacific Petroleums. That year, the company was drilling in Leduc, Alberta and made a huge oil strike which ignited, creating a huge fire. The publicity received by the fire generated a lot of investor income for “Pacific Pete,” and McMahon used this money to form Westcoast Transmission Company Limited, a natural gas company. Westcoast Transmission received government approval to construct, at Taylor, B.C., a 1,046-kilometre, 30-inch mainline natural pipeline, the first “big inch” pipeline in Canada, and the first natural gas processing plant in British Columbia. Construction on the pipeline began in 1955, and when completed in 1957, natural gas flowed at a rate of 400 million cubic feet per day, from Northeast British Columbia to the Canada-U.S. border. This was the beginning of the development of the natural gas industry in British Columbia. In the 1960s, the demand for natural gas grew, and Westcoast began construction of a second gas processing plant at Fort Nelson, as well as a 402-kilometre mainline expansion and gas gathering system extending into Northern British Columbia, Alberta, the Yukon, and Northwest Territories. By 2000, the company, called Westcoast Energy Inc. since 1988, had a gathering, processing and transmission system consisting of 5,600 kilometres of pipeline and five gas processing plants, including plants at Pine River, Boundary Lake and Saratoga, and three sulphur recovery plants. In 1968, subsidiary company Pacific Northern Gas began to bring gas to West- central B.C and some West Coast communities. In 1974, Foothills Pipe Lines Ltd., in which Westcoast Transmission had a 50% interest, was founded for the purpose of constructing and operating the Canadian portion of the Alaska Natural Gas Transporation System; the project was completed in 1981. In the late 1980s, plans were made to bring natural gas over to from the mainland. Pacific Coast Energy, a subsidiary company in which Westcoast had 50% interest, assumed responsibility for the construction of the 550-kilometre pipeline, which included the fourth deepest underwater pipeline in the world. The pipeline began operations in 1991. In 1990, Westcoast Energy acquired Centra Gas Inc. (formerly Inter-City Gas Utilities), which had markets on Vancouver Island, Alberta, Manitoba, and Ontario. When Westcoast Energy acquired Pacific Coast Energy Corporation in full in 1995, it merged the company with existing operations on Vancouver Island, forming Centra Gas Vancouver Island. In 1992, the company had acquired Union Energy Inc. and its subsidiary companies, including Union Gas Limited, which had a clientele of 650,000 in South-western Ontario; this acquisition

3 made Westcoast Energy Inc. the largest natural gas distributor in Canada. In 1998, Union Gas and Centra Gas Ontario were joined under the Union Gas name. In the 1990s Westcoast Energy expanded its interests to include companies specializing in gas-related services and other types of energy production. It formed Westcoast Power, a developer, builder, and operator of electrical power and cogeneration facilities, in 1991. 1993 saw the creation of Westcoast Gas Services, a gas marketing company created through a merger of subsidiary companies Unigas and Canadian Hydrocarbons Marketing, and NGX Canada (Natural Gas Exchange), a company establishing electronic gas trading centres in Canada and at points along the Canada-U.S. border. Westcoast Energy sold NGX Canada in 2000. NrG Information Services was formed in 1994, from a merger of Westcoast Energy with three other large pipeline companies, to assist with electronic commerce transactions between natural gas companies. In 1997, Westcoast Energy established Westcoast Capital Corporation, an energy sector investment company, as well as a retail energy services business through its subsidiary Union Energy. Westcoast Energy also joined with The Coastal Corporation of Houston, Texas to form Engage Energy, which became North America’s fourth largest marketer of natural gas and electricity. In 2000, Westcoast Energy left the partnership, retaining control of Engage Energy Canada. Another information services company, Enlogix Inc. was established by Westcoast Energy in 1998. In the late 1990s, Westcoast Energy was still involved in several major pipeline construction projects in North America. The company completed construction of a 568- km section of the Maritimes & Northeast Pipeline in 1999, bringing gas to customers in the Maritimes and the North-eastern United States. The following year, construction was completed on two pipelines in which Westcoast Energy had an interest: the , from Western Canada to Chicago, and the , from Chicago to New York City. Westcoast Energy also owns 100% of the 251-kilometre Empire State Pipeline, which transports natural gas from Niagara Falls to upper New York State. A west-to-east corridor for Western Canadian natural gas will be established with the addition of the Millennium West Pipeline (100% Westcoast Energy interest) and the Millennium Pipeline (21% Westcoast Energy interest), which will connect to bring gas from Ontario to New York City and the eastern United States. Westcoast Energy has also recently expanded its business interests beyond North America; Westcoast Energy International is involved in projects around the world, which have included interests in Australia, Indonesia, China, Australia, and Mexico. In March 2002, Westcoast Energy Inc. was acquired for $8 billion by the U.S. company .

4 Scope and content: Fonds consists of records created or accumulated by Westcoast Energy Inc., its predecessor company Westcoast Transmission Company, Limited, and their subsidiary companies. Records relate to the activities of these companies and the gas and energy industry in British Columbia and North America, and have been arranged into the following eleven series: Legal and financial records (1950-1996); Record books (1949-1980); Subject files (1949-2000); Corporate publications (1950-2002); Publications relating to Westcoast Energy Inc. and its subsidiary companies (1957-2002); Books, articles, and other publications relating to the energy industry in British Columbia and North America (1897-1996); Executive speeches and addresses (1957- 1997); Video recordings (1978-1995); Scrapbook (1957); Photographs and slides ([195-]- 1994); and Maps and Plans (1945-1994).

Source of title: Title based on contents of fonds.

Physical description note: Includes ca. 2870 photographs, 270 slides, 67 maps and plans, 3 record books, 1 scrapbook, 3 books, 7 videotapes and 2 audio reels.

Restrictions: No restrictions on access.

Acquisition information: Records in this fonds acquired from Duke Energy in 2003.

Accruals: Further accruals are expected.

5 SERIES DESCRIPTIONS

Legal and financial records. -- 1950-1996. 1.10 m of textual records. Series consists of legal and financial records of Westcoast Energy Inc., its predecessor company Westcoast Transmission Company Limited, and its subsidiary companies. Series has been arranged into two sub-series: Legal and financial records: Westcoast Energy Inc., and Legal and financial records: Subsidiary companies. Title based on contents of series.

Legal and financial records: Westcoast Energy Inc. -- 1950-2001. 89.5 cm of textual records. Sub-series consists of legal and financial records of Westcoast Energy Inc. and its predecessor company, Westcoast Transmission Company Limited. Includes trust indentures, proxy statements, prospectuses, offers to shareholders, documents pertaining to National Energy Board applications, and Securities & Exchange Commission forms. Title based on contents of sub-series.

Legal and financial records: Subsidiary companies. -- 1960-1996. 20.5 cm of textual records. Sub-series consists of legal and financial records of subsidiary companies of Westcoast Energy Inc. and its predecessor company, including Centra Gas Ontario Ltd., Gas Trunk Line of British Columbia, Ltd., ICG-Greater Winnipeg Gas Company, Pacific Northern Gas Co. Ltd., Union Gas Ltd., Union Gas-Centra Gas Ontario Inc., Westcoast Petroleum Ltd., and Westcoast Production Co. Ltd. Records include memoranda of association, agreements, trust indentures, prospectuses, notices and offers to shareholders, as well as some documents regarding Westcoast’s interests in these companies. Title based on contents of sub-series.

Record books. -- 1949-1980. 3 record books. Series consists of company record books, including Westcoast Transmission Company Ltd. minute books and related documents (1949-1960), and a log book and a guest book of the Fort Nelson Gas Processing Plant. Title based on contents of series.

Subject files. -- 1949-2000 1.25 m of textual records. Series consists of subject files created by Westcoast, consisting of promotional material, newspaper clippings, booklets, journals, magazines, articles, newsletters, corporate publications, reports, documents, biographies, photographs, and an organizational chart. Subject files pertain to Westcoast Transmission Company Ltd., Westcoast Energy Inc., Frank M. McMahon, corporate executives, Westcoast plants, Westcoast projects, such as the Pipeline, the Alaska Highway Project, the Foothills project, the

6 Mackenzie Valley Pipeline, and the Vancouver Island Pipeline, official ceremonies, and the Westcoast building. Title based on contents on series.

Corporate publications. -- 1950-2002. 1.70 m of textual records. Series consists of corporate publications of Westcoast Transmission Company Limited, Westcoast Energy Inc., and their subsidiary companies. Series has been divided into the following sub-series: Annual and interim reports – Westcoast Energy Inc. (1958-2002), Annual and interim reports – Subsidiary companies (1963-2002), General reports – Westcoast Energy Inc. (1955-1999), General reports – Subsidiary companies (1961-1968), Booklets and brochures – Westcoast Energy Inc. (1950-1998), Books and pamphlets – Subsidiary companies ([1962- 1998]), Press releases and information sheets (1967-[1996]), Newsletters – Westcoast Energy Inc. (1958-2000), Newsletters – Subsidiary companies (1993- 1998). Title based on contents of sub-series.

Annual and interim reports – Westcoast Energy Inc. -- 1958-2002. 52 cm of textual records. Sub-series consists of reports produced on an annual or quarterly basis by Westcoast Energy Inc. and its predecessor company Westcoast Transmission Company Limited. Title based on contents of sub-series.

Annual and interim reports – Subsidiary companies. -- 1963-2002. 45.5 cm of textual records. Sub-series consists of reports produced on an annual or quarterly basis by subsidiary companies of Westcoast Energy Inc. and its predecessor company Westcoast Transmission Company Limited. Subsidiary companies include Centra Gas Ontario Inc., Gas Trunk Line of British Columbia, Ltd., ICG-Greater Winnipeg Gas Company, Pacific Northern Gas Ltd., Union Gas Ltd., Westcoast Petroleum Ltd., and Westcoast Production Co. Ltd. Title based on contents of sub-series.

General reports – Westcoast Energy Inc. -- 1955-1999. 36.5 cm of textual records. Sub-series consists of various unrelated reports produced by or for, or accumulated by Westcoast Transmission Company Limited and Westcoast Energy Inc. Title based on contents of sub-series.

7 General reports – Subsidiary companies. -- 1961-1968. 5 cm of textual records. Sub-series consists of reports pertaining to petroleum, natural gas and crude oil reserves, prepared for West Coast Production Co. Ltd. and Western Pacific Products & Crude Oil Pipelines Ltd. Title based on contents of sub-series.

Booklets and brochures – Westcoast Energy Inc. -- 1950-1998. 7.5 cm of textual records. Sub-series consists of booklets and brochures produced by Westcoast Transmission Company Limited and Westcoast Energy Inc. Includes promotional material about the Company, as well as booklets and brochures relating to Company plants and projects, and natural gas in British Columbia/ Title based on contents of sub-series.

Books and pamphlets – Subsidiary companies. -- [1962-1998]. 3 cm of textual records. Sub-series consists of books and pamphlets produced by and pertaining to Westcoast’s subsidiary companies Engage Energy, Pacific Northern Gas Ltd., Union Gas Ltd., Westcoast Capital Corporation, and Western Pacific Products & Crude Oil Pipelines Ltd. Title based on contents of sub-series.

Press releases and information sheets. -- 1967-[1996]. 2 cm of textual records. Sub-series consists of Westcoast Transmission Company Limited and Westcoast Energy Inc. press releases, fact cards and information sheets. Title based on contents of sub-series.

Newsletters – Westcoast Energy Inc. -- 1958-2000. 17 cm of textual records. Sub-series consists of newsletters published by Westcoast Transmission Company Limited and Westcoast Energy Inc. Title based on contents of sub-series.

Newsletters – Subsidiary companies -- 1993-1998. 2 cm of textual records. Sub-series consists of newsletters published by Westcoast’s subsidiary companies Centra Gas Ontarion Inc. and Union Gas Limited. Title based on contents of sub-series.

8 Publications relating to Westcoast Energy Inc. and its subsidiary companies. 1957-2002. .45 m of textual records. Series consists of journal and magazine articles, reports, and books published by outside sources and relating to Westcoast Transmission Company Limited, Westcoast Energy Inc., and their subsidiary companies, including Consumer’s Gas Company Limited, Union Gas Limited, and Western Pacific Products & Crude Oil Pipelines Ltd. Title based on contents of series.

Books, articles, and other publications relating to the energy industry in British Columbia and North America. -- 1897-1996. .43 m of textual records. Series consists of books, reports, journal articles, and newsletters relating to the energy industry, in particular the gas and oil industries, in British Columbia and North America. Title based on contents of series.

Executive speeches and addresses. -- 1957-1997. .25 cm of textual records. 2 audio reels. Series consists of transcripts and sound recordings of speeches and addresses made by executive members. Title based on contents of series.

Video recordings. -- 1978-1995. 7 videotapes. Series consists of video recordings of television interviews, documentary pieces, and profiles concerning Westcoast Transmission Company Ltd. and Westcoast Energy Inc. Title based on contents of series.

Scrapbook. -- 1957. 1 scrapbook. Series consists of a scrapbook commemorating the completion of the Peace River pipeline in October 1957. Includes photographs of the ceremony and events at the McMahon Plant near Fort St. John and of the luncheon held at the Hotel Vancouver, to celebrate the arrival of natural gas in the Lower Mainland. Scrapbook also includes an audio recording of Frank McMahon’s speech at the luncheon, newspaper clippings, and memorabilia. Title based on contents of series.

9 Photographs and slides. – [195-]-1994. ca. 2870 photographs : b&w and col. ca. 270 slides : b&w and col. Series consists of photographs and slides related to construction projects, plants, stations, aerial crossings, executive members, company and special events, including W.A.C. Bennett’s P.G.E. Tour to Prince George in 1956, the opening of the Peace River Pipeline in 1957 and Princess Margaret’s tour of Compressor Station No. 1 in 1958, the Westcoast building , annual general meetings, employees, and rigs and drilling. Title based on contents of series.

Maps and plans. – 1945-[1991]. 67 maps and plans. 3 books. Series consists of maps and plans relating to pipeline construction projects carried out by Westcoast and to natural gas resources in British Columbia and Alberta.

10 FILE LIST

Box/Folder Date(s) Legal and financial records

Legal and financial records of Westcoast Energy Inc.

1 1-3 Westcoast Transmission Co. Ltd.: Consents of 1956-1971 Holders of Bonds

1 4 Westcoast Transmission Co. Ltd.: Supplemental 1957-1987 and Warrant Indentures

1 5 Westcoast Transmission Co. Ltd.: Trust Indenture, 1970 December 15, 1970

1 6 Westcoast Transmission Co. Ltd.: Financial 1971 documents

1 7 Westcoast Transmission Company Ltd. and The [1983] Canada Trust Company Trustee: Fifth Supplemental Indenture to a Trust Indenture dated as of the 1st day of April, 1973, Providing for the Issue of Debentures, April 5, 1983

1 8 Proxy Statements [photocopies] 1967-1979

1 9 Westcoast Energy Inc.: Proxy 1980-1992

1 10-11 Westcoast Transmission Co. Ltd. / Westcoast 1957-1996 Energy Inc.: Prospectus (English)

1 12-14 Westcoast Transmission Co. Ltd. / Westcoast 1983-1996 Energy Inc.: Short Form Prospectus (English)

1 15 Westcoast Transmission Co. Ltd.: Propectus 1979-1987 (French)

1 16-17 Westcoast Energy Inc.: Prospectus (French) 1988-1994

1 18 Westcoast Transmission Co. Ltd. / Westcoast 1985, 1988, Energy Inc.: Dividend Reinvestment and Share 1998 Purchase Plan -- Prospectus and Offering Circular

1 30 Westcoast Energy Inc.: OSC Regulation Stock 1987-1993 Performance, Jan. 1987-1993

11 1 19 Offer by Westcoast Transmission Holdings, Ltd…to 1982 holders of shares of Westcoast Petroleum Ltd. to purchase for cash all the outstanding shares…. April 2, 1982

1 20 Westcoast Transmission Co. Ltd. / Westcoast 1982, 1988, Energy Inc.: Information Memorandum – Short 1991 Term Promissory Notes

1 21 Westcoast Energy Inc.: Investor Information, June 1991 1991

1 22 Westcoast Energy Inc.: Shareholder notices and 1992, documents 2001-2002

1 23 Arrangement involving Westcoast Energy Inc. and 2001 Duke Energy Corporation – Notice of Special Meeting of Security Holders and Management Proxy Circular…November 8, 2001

1 24 The Oil and Gas Conservation Board…IN THE 1958 MATTER OF an Application by Alberta and Southern Gas Co. Ltd. …Submission of C. Henry Keplinger, March 1958

1 25 Westcoast Transmission Company, Ltd.: 1950-1970 Conservation Board Permits (1950-1970); Dept. of Trade & Commerce Canada: Licence to Export, June 27, 1955, Huntingdon, B.C.; National Energy Board of Canada: Licence to Export, April 11, 1960, Kingsgate, B.C. (S.A. Project)

1 26 National Energy Board: Intervention of the Attorney- 1965 General of the Province of British Columbia… IN THE MATTER of Applications of Alberta and Southern Gas Co., Ltd., and of Alberta Natural Gas Company, and of Trans-Canada Pipe Lines Limited… for a Licence for the Export of Gas, 1965, Vol. 3

1 27-28 National Energy Board: Intervention of the Attorney- 1965 General of the Province of British Columbia… IN THE MATTER of Applications of Alberta and Southern Gas Co., Ltd., and of Alberta Natural Gas Company, and of Trans-Canada Pipe Lines Limited… for a Licence for the Export of Gas, Vol. 4

12 1 29 N[ational] E[nergy] B[oard] -- Sept. 1966 Meeting 1966 with Staff: Transcripts from tapes

2 1 Reservoir Data and Estimated Recoverable Pipeline 1969 Gas Reserves in the Clarke Lake, Yoyo, , Cabin, Louise, and Slave Point / Elk Point Reservoirs. Pacific Petroleums Ltd., November 1969 (a report). [used by Pacific Petroleum at intervention of hearing in support of an application by WTCL]

2 2 Reservoir Data and Estimated Recoverable Pipeline 1970 Gas Reserves in the Clarke Lake, Yoyo, Kotcho Lake, Cabin, Louise, and Petitot River Slave Point / Elk Point Reservoirs – Supplement to the November 1969 report. Pacific Petroleums Ltd., July 1970.

2 3 …IN THE MATTER OF an application by Inter-City 1970 Gas Limited for licences for the exportation and importation of gas…Intervention [by Westcoast Transmission Company Limited], May 7, 1970

2 4 …IN THE MATTER OF an application by Westcoast 1971 Transmission Company Limited pursuant to Part III of the Act for a Certificate of Public Convenience and Necessity, Reply to Deficiency Letter Dated 6 April 1971, Vol. II

2 5 …IN THE MATTER OF an application by Westcoast 1973 Transmission Company Limited pursuant to Part III of the Act for a Certificate of Public Convenience and Necessity, Reply to Deficiency Letter dated August 14, 1973, vol. III

2 6 …IN THE MATTER OF an application by Westcoast 1979 Transmission Company Limited pursuant to Part III of the Act for a Certificate of Public Convenience and Necessity, Junior-Sierra Pipeline, Vol. VII, 15 March 1979

2 7 Westcoast Transmission Company Ltd.: Petrofina 1972 Brief, revised November, 1972

2 8 The “National Energy Board Act”: Application by 1974 Westcoast Transmission Company Limited, Laprise Compressor Station, Increase Compressor

13 Horsepower, February 1974

2 9 Westcoast Transmission Company Ltd. – National 1977 Energy Board: Silver-Dahl Pipeline Application (Class “A”), Vol. III (Part 3) – Alignment Sheets, Dated August 15, 1977

2 10 Alaska Highway Project 48” Alternative Policy -- 1977 Direct Testimonies, Feb. 28, 1977

2 11 Westcoast’s NEB Rate Application (Sept. 15, 1977) 1977 -- A.A. Arneson’s Work Papers

2 12 National Energy Board: Westcoast’s Application 1977-1979 Relative to Rates, Tolls & Tariffs dated September 15, 1977, Revised Financial Data for the Base Year and Test Year Period, January 22, 1979

2 13 National Energy Board: Response to Deficiency 1980 Letter No. 1, May 1, 1980

2 14 Westcoast Transmission Company Limited: 1983 Proposal to Conduct a Desk Audit of the Vancouver Departments, September 1983 by Price Waterhouse Associates

2 15 Westcoast Transmission Company Ltd.: Desk Audit 1984 of the Vancouver Departments, March 1984 (Price Waterhouse Associates)

2 16 Westcoast Transmission Company Limited: 1984 Response to National Energy Board Information Request of August 9, 1984 re:…Desk Audit of the Vancouver Departments dated March 1984, September 21, 1984

2 17 Material Supplied to the National Energy Board re: 1991 Kobes Injunction Field Compressor Station #3, October 3, 1991

2/ 18-20/ Westcoast Transmission Co. Ltd. / Westcoast 1980-1990 4 1 Energy Inc.: Form 10-K – Securities & Exchange Commission, , D.C., 20549

4 2 Westcoast Energy Inc.: Form 8-K – Securities & 1982, 1989- Exchange Commission, Washington, D.C. 20549 1990

14 2 21-25 Westcoast Transmission Co. Ltd. / Westcoast 1982-1991 Energy Inc.: Form 10-Q – Securities & Exchange Commission, Washington, D.C., 20549

2 26 Westcoast Transmission Co. Ltd.: Form 8 – 1987 Securities & Exchange Commission, Washington, D.C., April 9, 1987

2 27 Westcoast Energy Inc.: Form S-3 – Securities & 1990 Exchange Commission, Washington, D.C., 20549, February 23, 1990

2 28-30 Westcoast Energy Inc.: Form 6-K – Securities & 1991-1998 Exchange Commission, Washington, D.C., 20549

3 1-3 Westcoast Energy Inc.: Form 40-F – Securities & 1991-2000 Exchange Commission, Washington, D.C., 20549

Legal and financial records of subsidiary companies

3 4 Centra Gas Ontario – Prospectus 1993, 1995

3 5 Gas Trunk Line of British Columbia Ltd.: Gas 1960-1961 Transportation Contracts with Westcoast Transmission Co. Ltd.

4 3 Gas Trunk Line of British Columbia, Ltd.: 1961 Prospectus 1961 [photocopy]

3 6-7 Gas Trunk Line of British Columbia Ltd.: Trust 1961-1964 Indentures, 1961-1964 and Deposit Agreement

3 8 Gas Trunk Line of British Columbia Ltd.: Bond 1961-1964 Purchase Agreement (1961); 15 months report ended June 30, 1962; Letter to shareholders May 8, 1964

4 4 Prospectus: Gas Trunk Line of British Columbia 1961, 1964 Ltd., 1961 / An Offer by Westcoast Transmission Co. Ltd. to the Holders of Common Shares of Gas Trunk Line of British Columbia Ltd., 1964

3 9-10 ICG – Greater Winnipeg Gas Company: 1982-1989 Miscellaneous Financial Reports and Documents

3 11 Pacific Northern Gas Ltd.: Trust Indentures 1975, 1979, 1982, 1987

15 3 12 Pacific Northern Gas Ltd.: Prospectus 1975, 1987

3 13 Pacific Northern Gas Ltd.: Regulatory documents 1995-1996

3 36 Union Gas Limited: Information Memorandum – 1982 Short Term Promissory Notes

3 14 Memorandum of Association of Westcoast 1969 Diversified Industries Ltd. [certified copy]

3 15 Westcoast Petroleum Ltd.: Notices to 1972-1982, Shareholders, AGM notices and agendas 1987

3 16 Westcoast Petroleum Ltd.: Trust Indenture / 1978 Company Abstract

4 6 Westcoast Petroleum Ltd.: Form 10-K – Securities 1978-1981 & Exchange Commission, Washington, D.C., 20549

4 6 Westcoast Petroleum Ltd.: Form 10-Q – Securities 1981 & Exchange Commission, Washington, D.C., 20549

3 17 Westcoast Petroleum Ltd.: Form 8-K – Securities & 1982 Exchange Commission, Washington, D.C., 20549

3 18 Westcoast Production Co. Ltd. – Prospectuses, 1969-1971 statements, etc.

3 19 Westcoast Production Co. Ltd. and Western Pacific 1971 Products & Crude Oil Pipelines Ltd.: Information Circular [re: amalgamation into Westcoast Petroleum Ltd.], August 6, 1971

Record books

4 6 Historical Vertical Files: Westcoast Transmission 1949-1960 Co. Ltd. – Minute Books and Documents

F12A/4/3 Fort Nelson Gas Process Plant Log Book, Oct. 13, 1964-1965 1964 to Feb. 22, 1965

3 20 Guest Book, Fort Nelson Process Plant, October 1966-1980 15, 1966-October 17, 1980

16 Subject files 3 21-23 Alaska Highway Pipeline Project [Newspaper 1975-1979 clippings]

3 24 Alaska Highway Gas Pipeline [Newspaper 1980-1982 Clippings]

3 25 Alaska Highway Gas Pipeline [Newspaper 1983-1984 Clippings]

3 26 Alaska Highway Gas Pipeline [Newspaper 1987-1989 Clippings]

3 27 F.M. McMahon: Statement to Borden Commission 1958 in Victoria, B.C., April 21, 1958

3 28-32 Frank M. McMahon & Election, 1960 [newspaper 1960 clippings]

3 33 Personalities: F.M. McMahon Attacks [newspaper 1961 clippings]

3 34 Frank M. McMahon: Clippings and photograph re: 1964-1966 Canadian Industrial Development Award (1964), Biographical Information, and 1966 Address to Truck Loggers Association

3 35 News Releases and Clippings re: Death of Frank 1986 McMahon (including biography), May 26, 1986

5 1-2 Gas Trunk Line of B.C. [newspaper clippings], 1962-1965 1962-1965

5 3 Historical Newspapers: Borden Commission – 1957-1958 Correspondence

5 4 Historical Newspapers: Borden Commission – 1957-1958 Favorable Comments

5 5-10 Historical Newspapers: Borden Commission – 1954-1959 General

5 11 Historical Newspapers: Borden Commission -- 1955-1959 Hearing Material [Submissions, statements, and other material]

17 4/ 7-8/ Historical Newspapers: Borden Commission – 1957-1959 5 12-13 Miscellaneous [reports, statements, submissions, newsletters, articles]

5 14-15 Historical Newspapers: Borden Commission – 1957-1958 Negative Views

5 16 Historical Newspapers: Westcoast Transmission – 1951 Newspaper clippings

5 17 Historical Newspapers: Westcoast Transmission – 1952 Newspaper clippings

5 18 Historical Newspapers: Westcoast Transmission – 1953 Newspaper clippings

5 19-21 Historical Newspapers: Westcoast Transmission – 1954 Newspaper clippings

5 22-23 Historical Newspapers: Westcoast Transmission – 1955 Newspaper clippings

5 24 Historical Newspapers: Westcoast Transmission – 1956 Newspaper clippings

5 25 Historical Newspapers: Westcoast Transmission – 1949-1952, Newspaper Clippings 1957

5 26 Historical Newspapers: Westcoast Transmission – 1959-1960 Newspaper Clippings [photocopies]

4 9 Historical Newspapers: Westcoast Transmission – 1970 Newspaper clippings

5 27-30 Historical Newspapers: Westcoast & Pacific – 1950-1973 General

6 1-5 Historical Newspapers: Westcoast & Pacific – 1956-1957, General No. 2 1959, 1972

6 6 Historical Newspapers: Westcoast Transmission – 1964 Westcoast opens in Ft. Nelson 1964

6 7 Historical Newspapers: Westcoast Transmission – 1964-1965 Westcoast opens in Ft. Nelson 1965

18 6 8-10 Historical Vertical Files: Gas, Natural [documents. 1952-1966, reports, and publications] predominant 1952-1954

6 11 Historical Vertical Files: [Westcoast Energy Inc. – 1990 Organization Chart, June 15, 1990]

6 12 Historical Vertical Files: [Opening of Peace Pipeline 1957-1958 and McMahon Plant (1957) and ] P.G.E. Trip (1958) – Newspaper clippings [and negatives]

6 13-14 Historical Vertical Files: Union Gas [Promotional 1991-1993 Material]

6 15 Historical Vertical Files: Vancouver Island Pipeline 1981-1995

6 16 Historical Vertical files: Westcoast Transmission Co. 1948-1950 Ltd. – Publicity

4 10-13 Historical Vertical Files: Westcoast Transmission & 1949-1960, Pacific – Miscellaneous [publications and articles] 1980 No. 1

4 14-15 Historical Vertical Files: Westcoast Transmission & 1949-1963, Pacific – Miscellaneous [publications and articles] 1979-1980 No. 2

6 17 Historical Vertical Files: Newspaper articles [re: 1961 picket at Westcoast Transmission Company, Ltd., Jan. 1961]

6 18 Historical Vertical Files: [Westcoast Transmission / 1966-1991 Westcoast Energy promotional material]

6 19-21 Historical Vertical Files: Westcoast Energy [Articles, 1969, 1990- reports, publications, etc.] 1998

6 22-23 Historical Vertical Files: Westcoast Energy [Articles] 1986-1996, 2000

6 24 Mackenzie Valley Pipeline [newspaper clippings] 1987-1989

6 25-26 Official Opening – Organization 1957

6 27 Overhead visuals for J. Kavanaugh’s Speech, 1989 October 24, 1989

19 6 28 The Westcoast Building – Articles, booklets, and [1969-1988] other material

12 23 The Westcoast Building and Adjoining Development [ca. 1990] Lands

6 29 Westcoast Energy Inc: ASC Regulation Stock 1987-1993 Performance

6 30 Westcoast Energy Inc. – Biographies: John 1970-1989 Anderson

6 31 Westcoast Energy Inc. – Biographies: Joel Bell 1971

6 32 Westcoast Energy Inc. – Biographies: Norm Didur 1990-1991

6 33 Westcoast Energy Inc. – Biographies: D.L. Helliwell 1979

6 34 Westcoast Energy Inc. – Biographies: Andrew [ca. 1979] Janisch

6 35 Westcoast Energy Inc. – Biographies: Frank M. 1980-1986 McMahon

6 36 Westcoast Energy Inc. – Biographies: Douglas 1964-1972 Owen

6 37 Westcoast Energy Inc. – Biographies: Derek H. 1982 Parkinson, F.C.A.

6 38 Westcoast Energy Inc. – Biographies: Edwin C. 1972-1983 Phillips,

6 39 Westcoast Energy Inc. – Biographies: Ron 1989 Rutherford

6 40 Westcoast Energy Inc. – Biographies: James M. 1990 Stanford

6 41 Westcoast Energy Inc. – Biographies: Wesley R. 1989 Twiss

6 42 Westcoast Energy Inc. – Biographies: John B. 1988 Zaozirny

6 43 Westcoast Energy Inc. – Corporate Centre 1995

20 6 44 Westcoast Energy: First quarter results 1992 and [ca. 1992] graphics

6 45-46 Westcoast Energy [magazine articles re: Westcoast 1979, 1990- Energy Inc., Ed Phillips, Michael Phelps] 1995

6 47 Westcoast Energy [newspaper articles] 1987

6 48 Westcoast Energy [newspaper articles] 1988

6 49 Westcoast Energy [newspaper articles] 1989

4 16 Westcoast Energy Inc., 1990 [newspaper articles] 1990

7 1 Westcoast Energy Inc. [newspaper articles] 1991

7 2 Westcoast Energy Inc. Newspaper Articles 1991-1993

7 3 Westcoast Energy Inc., Pipeline Division: Strategic 1993-1994 Plan

7 4 Westcoast Name Change [Press] 1988-1989

7 5 Westcoast Petroleum [newspaper clippings] 1982-1989

7 27 The Westcoast Story – Dedication ceremony, Fort 1957 St. John and Vancouver, October 1957

7 27 The Westcoast Story – ’s Report / 1956 Westcoast Transmission Company, Ltd.

7 28 Script for the Westcoast Story, October 1957 1957

4 17 Westcoast Transmission Co. Ltd. 1982-1984

4 18 Westcoast Transmission Co. Ltd. 1985-1986

7 6-8 Westcoast Transmission Company Limited: History 1949-1953

7 9 Westcoast Transmission Company Ltd. : 1981 Organization Charts (Foothills Project)

7 10 Westcoast Transmission Co. Ltd.: Political Attacks 1957-1958 [newspaper clippings],

21 7 11-12 Westcoast Transmission Company Ltd.: [Misc. 1956-1992, publications, press releases, company information] 2000

Corporate publications

Annual and interim reports – Westcoast Energy Inc.

7 13-18 Westcoast Transmission Co. Ltd.: Annual Reports 1958-1988 1957-1987

7 19-23 Westcoast Energy Inc.: Annual Reports, 1988- 1989-2001 2000 [1998-2000 include Corporate Review]

7 24 Westcoast Energy Inc., a Duke Energy Company: 2002 Annual Report, 2001

F12A/4/3 Westcoast Energy Inc.: Systems & Strategic 1998 Pipeline Connections – Annual Report 1998.

7/ 25-26/ Westcoast Transmission Co. Ltd. / Westcoast 1958-2002 8 1-4 Energy Inc.: Interim Reports 1958, 1961, 1964, 1967-2002

7 29 Westcoast Transmission Co. Ltd.: Annual meeting 1977 and shareholder information

8 5-10 Westcoast Energy Inc.: Annual Information Form 1983-2001

8 11 Westcoast Energy Inc.: Progress in Sustainable 1995, 1997- Development – Biennial Review 1995, 1997; 1999 Summary 1999; Annual Review 1998, 1999

8 12-16 Westcoast Transmission Co. Ltd.: Ten-Year 1982-1986 Review

8 17-18 Westcoast Energy Inc.: Ten Year Review 1987-1988

8 19-22 Westcoast Transmission Co. Ltd.: Financial 1981-1985 Reports

8 23 Gas Annual Report S.I.C. 515 1981 of Westcoast Transmission Company Limited to Statistics Canada and National Energy Board, Ottawa, For the Year ended December 31, 1980

22 8 24 Westcoast Energy Inc., Pipeline Division: Five 1991 Year System Development Plan, 1992-1996

8 24 Westcoast Energy Inc., Pipeline Division: 1992 1992 Five Year System Development Outlook: 1993- 1997

8 25 Westcoast Energy Inc., Pipeline Division: 1994 – 1994 Five Year System Development Outlook: 1995- 1999

Annual and interim reports – Subsidiary companies

9 1 Centra Gas Ontario Ltd.: Annual Reports 1990- 1991-1995 1994

9 2 Centra Gas Ontario Ltd.: Annual Information Forms 1992-1994

9 3 Centra Gas Ontario Ltd.: Interim Reports 1991-1997

9 4 Gas Trunk Line of British Columbia, Ltd: Annual 1963-1966 Reports, 1962-1965

9 5 ICG – Greater Winnipeg Gas Company: Annual 1985-1990 Reports 1984-1989

9 6 ICG – Greater Winnipeg Gas Company: Interim 1987-1990 Reports

9 7-11 Pacific Northern Gas Ltd.: Annual Reports, 1968- 1969-2002 2001

9 12 Pacific Northern Gas Ltd.: Reports to Shareholders 1970-1976

9 13 Pacific Northern Gas Ltd.: Interim Statements 1978-2002

9 14-15 Pacific Northern Gas Ltd.: Annual Information 1992-2001 Form

9 16 Pacific Northern Gas Ltd.: Notice of Annual 1971-1979, General Meeting of Shareholders 1981, 1983-1987

9 17 Pacific Northern Gas Ltd.: Executive Summary – 1994 Integrated Resource Plan, August 1994

23 9 18-24 Union Gas Ltd.: Annual Reports, 1973-2000 1974-2001 [missing 1986]

9 25 Union Gas Ltd.: Employees Annual Report, 1993 1994

9 26 Union Gas Ltd.: 64th Annual Meeting, 1976; 65th 1974, Annual meeting, 1977; Preliminary Report on 1976-1977 results of Operations, for the fiscal year ended March 31, 1974

9 27 Union Gas Ltd.: Annual Information Forms 1991, 1992, 1995, 1996

9 28-29 Union Gas Ltd.: Interim Reports 1976-2002

9 30 Union Gas – Centra Gas Ontario Inc.: Annual 1996 Report, 1995

9 31-32 Westcoast Petroleum Ltd.: Annual Reports, 1971- 1972-1982 1981

9/ 33/ Westcoast Petroleum Ltd.: Annual Reviews, 1982- 1983-1992 10 1-3 1991

10 4 Westcoast Petroleum Ltd.: Interim Reports, 1971- 1971-1980, 1980, 1982 1982

10 6 Westcoast Production Co. Ltd.: Annual reports, 1970-1972 1969-1971

10 7 Westcoast Production Co. Ltd.: Interim Reports 1970 1970

General reports – Westcoast Energy Inc.

10 9 Westcoast Transmission Company Ltd.: The 1955 Deliverability of Alberta Natural Gas for Provincial and Export Supply, October 27, 1955

10 10 Report: Natural Gas Market in Service Area of 1955 Inland Natural Gas Co. Ltd., Westcoast Transmission Company, Ltd., , Alberta, Nov. 10, 1955

24 10 11 Natural Gas Reserves of The Peace River Area, 1956 Alberta and British Columbia – Prepared for Westcoast Transmission Company, Ltd., Calgary, Alta. by E.P. Ogier of Shreveport, Louisiana, January 1956.

10 12 Westcoast Transmission Company Ltd.: Review 1956 and Study of Economic Feasibility of Proposed Natural Gas Pipeline Project in Canada, February 1956 by New York: Commonwealth Services, Inc.

12 25 Sturgeon Lake Area – Post-Devonian Structural 1958 Analysis by A. McGugan, September 1958

10 13 The National Energy Board: Estimated Market 1959 Requirements for Natural Gas, Province of British Columbia, 1960-1969 inclusive, Westcoast Transmission Company, Ltd., November 1959

10 14 Natural Gas Reserves Growth and Exploration 1960 Trend in Northeastern British Columbia by Lloyd K. Turner, Westcoast Transmission Co. Ltd., April 1960

11 7 Westcoast Transmission Company, Ltd: Boundary 1961 Lake South Area

10 15 Westcoast Transmission Company Ltd.: Natural 1965 Gas and Oil Resources of Northeastern British Columbia

10 16-17 Westcoast Transmission Company Ltd. / 1968-1988 Westcoast Energy Inc.: Miscellaneous Investor Research Reports and Bulletins, 1968-1988

10 18 List by Fields of Gas Purchase Contracts of [1970] Westcoast Limited & Westcoast (Alberta), 1950- 1970

14 7 Westcoast Transmission Company Ltd.: Gas Plant 1973 Unit Catalogue

10 8 Westcoast Transmission Company Ltd: Historical 1973-1977 Statistics Book

25 14 8 District of Stewart, Stewart, British Columbia: 1976 Harbour Development Plan by Stother Management Ltd., Vancouver, B.C.

12 26 British Columbia Harbour Board: Master Plan 1978 Study for the Port of Stewart, B.C. / Swan Wooster Engineering Co. Ltd. of Vancouver, B.C.

12 27 Port of Stewart Proposal to Alaska – Yukon Gas 1978 Transmission Pipeline, April 17, 1978

10 19 Westcoast Transmission Company Ltd., August 1978 1978 (Report by Woods, Gordon & Co.)

10 20-22 Westcoast Transmission Company, Ltd: Efficiency 1980 and Productivity, March 1980

14 10 The President’s Alaska Natural Gas Transportation 1981 Act Waiver Recommendation: Hearing before the Committee on Energy and Natural Resources, United States Senate…October 22, 23, and 26 1981 / Committee on Energy and Natural Resources. – Washington, D.C.: U.S. Government, 1981.

10 23 Westcoast Transmission Company Limited: 1981 Pipeline Mileage to Date [March 1981]

10 24 Westcoast Transmission Company Limited: 1981 Pipeline Mileage [Statistics], December 31, 1981

10 25-27 Final Report: Management and Operations 1982 Review, Westcoast Transmission Company, Limited, June 1982

10 28 Westcoast Transmission Company Ltd: Pipeline 1983 Statistics

10 29 Optimal Allocation of British Columbia Surplus Gas 1985 to the Western Canada LNG Project – Prepared for Petro-Canada Inc. by Marvin Schaffer & Associates Ltd., September 1985

10 30 Westcoast Energy Inc.: Mid-1988 Economic 1988 Review, Corporate Development Division, June 27, 1988

26 10 31 Leadership in the 1990s: Developing Champions of [ca. 1990] Change – Developed and presented by Dr. Neill Miller for Westcoast Energy [photocopy]

10 32-33 Westcoast Energy Profiles 1991

10 34 Westcoast Energy Inc. [Study of Gas Purchasing 1991 and Sales Procedures], October 1991

10 35 Westcoast Energy Inc.: Standard Testing of 1991 Moisture Analyzers, May 13, 1991

10 36 Westcoast Energy Environmental Review 1994 1993/1994

12 24 An Institutional Investment: Westcoast Energy Inc., 1995 September 7, 1995 – Prepared by Nesbitt Burns Managed Futures Corp.

10 37 Ergonomic Evaluation: Westcoast Energy Inc., 1995 Northern District by Darren Buckler, UBC, 1995

10 38 Westcoast Energy Inc., Pipeline Division: Success 1995 Sharing Guide, October 1995

10 39 Westcoast Energy Inc.: A Report on the Corporate 1995 Centre, August 1995

10 40 Emergency Planning Zone Definition for Sour Gas 1996 Pipelines – Prepared for Westcoast Energy Inc. by Dovan Environmental (Michael J. Zelensky), August 1996

10 41 Westcoast Energy Inc.: VCR [Voluntary Challenge 1997 and Registry] Action Plan 1997

10 41 VCR [Voluntary Challenge and Registry] Progress 1999 Report 1999

General reports – Subsidiary companies

Pacific Coast Energy Corporation

F12A/4/4 Recreation & Visual Resource Assessment for 1989 Pacific Coast Energy Corporation by Regional Consulting Ltd., Nov. 1989

27 Westcoast Production Co. Ltd.

11 1 Evaluation of the P. & N.G. Reserves and Holdings 1968 of Westcoast Production Co. Ltd., as of May 1, 1968, by J.C. Sproule and Associates Ltd. [photocopy]

Western Pacific Products & Crude Oil Pipelines Ltd.

11 2 Crude Oil Reserves and Productivity: Northeastern 1964 British Columbia – Prepared for Western Pacific Products & Crude Oil Pipelines Ltd. by W.J. McPherson Consulting Ltd., Calgary, December 1964

11 2 Crude Oil Reserves and Productivity: Northeastern 1966 British Columbia – Prepared for Western Pacific Products & Crude Oil Pipelines Ltd. by W.J. McPherson Consulting Ltd., Calgary, December 1966

11 3 Revision of the Reserves and Productivity 1961 Estimates of the Boundary Lake Oil Field, Northern British Columbia, Canada, November 1961 – Prepared for Western Pacific Products & Crude Oil Pipelines Ltd. by McPherson-Hale Consultants Limited

Booklets and brochures – Westcoast Energy Inc.

12 42 Natural Gas for the People of Northern Alberta and British Columbia, to be provided by the pipeline system of Westcoast Transmission Company Limited / Westcoast Transmission Company Limited. – Calgary, Alberta : Westcoast Transmission, [ca. 1950].

11 4 Natural Gas in Alberta and British Columbia and its Development for the Benefit of Canada / Westcoast Transmission Company Ltd. – Calgary : Westcoast Transmission, 1950. [photocopy]

11 5 Westcoast Transmission: The Story of a Pipeline / Westcoast Transmission Company Ltd. – [Vancouver, B.C.] : Westcoast Transmission, [ca. 1958].

28 11 6 Natural Gas – The Perfect Fuel for Home and Industry / Westcoast Transmission Company Ltd. – [Vancouver, B.C.] : Westcoast Transmission, [196-].

11 8 The Story of Natural Gas / Westcoast Transmission Company Ltd. – Vancouver, B.C. : Westcoast Transmission, 1962.

11 10 Proposed: A Major Petrochemical Development for British Columbia / Petrochemical Project. – Vancouver, B.C.: Petrochemical Project,1981.

11 11 Rim Gas: Energy for the Pacific / Rim Gas Project. – Calgary : Rim Gas Project, 1982.

11 12 Westcoast Transmission Company Limited: An Enterprise in Energy / Westcoast Transmission Company Ltd. – Vancouver, B.C. : Westcoast Transmission, 1984.

11 13 Westcoast Energy: A Vital Source of Your Energy Future / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, 1988.

11 14 Westcoast Energy [Major investment program] / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, 1988.

12 18 Career Achievement Program / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, [ca. 1990].

12 19 Fort Nelson Independent Power Project / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, [ca. 1990].

12 20 Fort Nelson Gas Process and Sulphur Recovery Plant, Fort Nelson, B.C. / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, [1990].

12 20 McMahon Plant, Taylor, B.C. / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, [1990].

12 20 Pine River Gas Process and Sulphur Recovery Plant, Chetwynd, B.C. / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, [1990].

12 20 Saratoga Processing Company Limited / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, [1990].

29 12 20 Sulphur Products Plant, Prince George, B.C. / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, [1990].

11 15 Westcoast Energy Inc.: Regional Roots, National Reach / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, [1992].

11 15 Westcoast Energy Inc.: Serving more than one million customers / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, [1993].

11 9 Westcoast Energy 1994 Stats Book / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, 1994.

11 15 Westcoast Energy is committed to…/ Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, [1995].

11 12 British Columbia Natural Gas – Fuelling Industry / BC Gas Utility Ltd, Westcoast Energy Inc., et al. – Vancouver, B.C. : BC Gas Utility Ltd., [1994].

12 21 Westcoast Energy 1996 Calendar – Vancouver, B.C. : Westcoast Energy Inc., 1996.

11 16 The Eastern Pipeline Project – BHP Petroleum Pty. Ltd. and Westcoast Energy (Australia) Pty. Ltd. / Melbourne: The Eastern Pipeline Project, 1995.

12 22 Westcoast Energy: Aboriginal Relations – Sharing a Vision / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy, 1998.

Books and pamphlets – Subsidiary companies

11 17 Engage Energy / Engage Energy. – Calgary : Engage Energy, 1997.

11 18 Pipeline to the Pacific: The Story of Pacific Northern Gas. Ltd. / Pacific Northern Gas. Ltd. – [British Columbia]: Pacific Northern Gas. Ltd., [1970]. 11 19 The World of Union Gas: Answers to Questions most often asked by Customers / Union Gas. -- Chatham, Ont.: Union Gas, [1991].

11 20 Union Gas: Dawn Operations Centre / Union Gas, Dawn Operations Centre. – Dresden, Ont. : Union Gas [1998].

30 11 21 Westcoast Capital Corporation / Westcoast Capital Corporation. – Calgary : Westcoast Capital Corporation, [ca. 1997].

11 18 Pipeline to Progress: The Story of Western Pacific / Western Pacific Products & Crude Oil Pipelines Ltd. – Vancouver, B.C.: Western Pacific Products & Crude Oil Pipelines Ltd., [1962].

Press releases and information sheets

11 22 Westcoast Transmission Co. Ltd.: Press Releases 1967-1978

11 23 Press Releases: Westcoast Petroleum Ltd. (1982); 1982-1988 Westcoast Transmission Company Limited (1985); Pacific Coast Energy Corporation (1988)

11 24 Westcoast Transmission Company Ltd. / 1980-1989 Westcoast Energy Inc. Fact Cards

11 25 Fact Sheet: Westcoast Transmission Company 1981 Ltd.

11 26 “Eastern Pipeline: Bringing the Energy of Choice” [1996] Information Sheets 1-8, 10-12, 20

Newsletters – Westcoast Energy Inc.

11 27 Changing Times. -- Vancouver, B.C.: Westcoast Energy Inc. Summer 1995

11 28 Eco-Line: Environmental and Cost Awareness for Westcoast Staff and Families. – Vancouver, B.C.: Westcoast Energy Inc., Eco-Line Committee. December 1991 Spring/Summer 1992 Fall 1992 Spring 1993

11 29 The Energizer. -- Vancouver, B.C.: Westcoast Energy, Health Section. [pre-1989] September 1989 Autumn 1993

11 30-31 Energy Times. -- Vancouver, B.C.: Westcoast Energy Inc., Corporate Communications. Vol. 1, Issues 1-5 (Apr. - Dec. 1995) Special photo edition (Nov. 1995)

31 Vol. 1, Issues 6-9 (Feb. -Sep. 1996) Vol. 1, Issue 11-13 (Feb. - Jul. 1997) Vol. 1, Issue 16-20 (Apr. - Dec. 1998) Vol. 1, Issue 21-26 (Feb. - Nov. 1999) Vol. 1, Issue 27-28 (Mar. - May 2000)

11 32-35 The Flame. -- Vancouver, B.C. : Westcoast Energy Inc. Summer 1988 Autumn 1988 Spring 1989 Summer 1989 Autumn 1989 Winter 1989 Spring 1990 Summer 1990 Winter 1990 Spring 1991 Summer 1991 Autumn 1991 Winter 1991 Spring 1992 Summer 1992 Fall 1992 Winter 1992 Spring 1993 Fall 1993 Winter 1993 Winter 1994

11 36 The Information Pipeline. -- Vancouver, B.C. : Westcoast Energy Inc, Information Systems & Technology Division. Issue 1 (Mar. 1995) Issue 2 (Jul. 1995) Issue 3 (Nov. 1995) Issue 4 (Mar. 1996) Issue 5 (May 1996)

11 37 The Mile 285 post [Fort Nelson Plant]. – Fort Nelson : Westcoast Energy Inc., Fort Nelson Plant. vol.2, Issue 2 (August 3, 1993) 11 38 The Pipeline. -- Vancouver, B.C. : Wescoast Transmission Company Limited. Vol.1, nos. 1-3 (Sep. - Nov. 1962) Vol.1, no. 8-11, 13 (Mar. - Dec. 1963) Vol. 2, nos. 2-5 (May - Aug. 1964)

32 11 38-42 Pipeline. -- Vancouver, B.C. : Wescoast Transmission Company Limited. Vol. 2, nos. 6-9 (Sep. - Dec. 1964) Vol. 3, nos. 1-12 (Jan. - Dec. 1965) Vol. 4, nos. 1-3, 5-12 (Jan. - Dec 1966) Vol. 5, no. 1-10 (Jan. - Oct. 1967) Vol. 6, no. 11 (Nov. 1967) Vol. 7, no. 12 (Dec. 1967) Vol. 8, nos. 1-12 (Jan. - Dec. 1968) Vol. 9, nos. 1-11 (Jan. - Dec. 1969) Vol. 10 (Jan. - May 1970) Winter 1970 Spring 1971 Winter 1971 Summer 1971

11 43-49 Pipeline News. -- Vancouver, B.C. : Westcoast Transmission Company Limited. Vol. 1, nos. 1-6 (Jan. - Nov. 1971) Vol. 2, nos. 1-6 (Feb. - Dec. 1972) Vol.3, nos. 1-11 (Jan - Dec. 1973) Vol. 4, nos. 1-11 (Jan. - Dec. 1974) Vol. 5, nos. 1-9 (Jan. - Dec. 1975) Vol. 6, nos. 1-6 (Jan./Feb. - Dec. 1976) Vol. 7, nos. 1-6 (Jan./Feb. - Dec. 1977) Vol. 8, nos. 1-7 (Mar. - Dec. 1978) Vol. 9, nos. 1-6 (Jan. - Dec. 1979) Vol. 10, nos. 1-5 (Feb. - Dec. 1980) Vol. 11, nos. 1-5 (Mar. - Dec. 1981/Jan. 1982) Feb./Mar. 1982 - Dec. 1982/Jan. 1983 Feb./Mar. 1983 - Dec. 1983/Jan. 1984 Feb./Mar. 1984 - Nov./Dec. 1984 Feb. - Dec. 1985 Jun. - Dec. 1986 Mar. - Dec. 1987 Spring 1988

11 49 Pipeline News. -- Vancouver, B.C. : Westcoast Energy Inc., Pipeline Division. Vol. 1, Issue 1 (September 1994) Vol. 2, Issue 1 (April 1995) Vol. 2, Issue 2 (Oct. 1995)

11 50 Pipeline Report: Eastern Gas Pipeline Community Newsletter. -- [Melbourne] : BHP Petroleum and Westcoast Energy (Australia)

33 Issues 2 - 5 (Jul. - Dec. 1995) Issues 6 - 8 (May - Oct. 1996) Issue 9 (Apr. 1997)

11 51 Westcoast Connection. -- Vancouver, B.C. : Westcoast Energy, Utility Services Marketing Division Winter 1991-1992 Spring 1992 Fall 1992 Winter 1992-1993 Spring/Summer 1993 Spring 1994

11 51 Westcoast Connection. -- Vancouver, B.C. : Westcoast Energy, Customer and Service Marketing Division Summer 1994 Fall 1994 Winter 1995 Summer 1995

11 52 Westcoast Energy and the Environment. -- Vancouver, B.C.: Westcoast Energy Inc. No. 1 (June 1993) No. 2 (Sept. 1993) No. 3 (Dec. 1993) No. 4 (Apr. 1994) No. 5 (Jun. 1994)

11 38 The Westcoast News. -- Vancouver, B.C. : Westcoast Transmission Company Limited. Vol 1, nos. 1-5 (Jan./Feb. 1958 - Nov./Dec. 1958) Vol 2, no. 1 (Jan./Feb. 1959)

11 53 Westcoast News. - Vancouver, B.C. : Westcoast Energy Inc., Community Affairs. Jan. 1994 July 1994 Issue 6 (Nov. 1994) Issues 7-10 (Mar. - Nov. 1995) Supplement (Nov. 1995) Issues 11 – 13 (Mar. - Dec. 1996) Issue 16 (Sept. 1997) Issues 19-21 (Jun. - Nov./Dec. 1998) Issue 22 (April 1999)

34 Newsletters – Subsidiary companies

11 54 Foresight. - Chatham, Ont. : Centra Gas Ontario Inc. / Union Gas Limited. December 1997

11 55 Union Gas Connections: Energy in the Making. -- Chatham, Ont. : Union Gas and Centra Gas. July 25, 1997 September 1997 December 1997 February 27, 1998 June 29, 1998

11 54 Union Gas Interconnects. -- Chatham, Ont. : Union Gas. June 1996

11 56 Union Gas Times. -- Chatham, Ont. : Union Gas Human Resources Dept. Vol. 3, Issue 3 (Mar. 1993) Vol. 5, Issue 13 (Sept. 8, 1995)

Publications relating to Westcoast Energy Inc. and its sudsidiary companies

Journals and magazines 12 28 BC Business. – Burnaby: Canadian Wide Magazines Ltd. Vol. 18, no. 8 [Issue titled: “Whatever happened to Westcoast Transmission? Mike Phelps Put a Little ENERGY Into It,” pp. 12-19]

12 28 Canadian Shareowner. – Windsor, Ont. : Canadian Shareowner Magazine Inc. November 1994 [See article “Westcoast Energy Inc.: Major League Gas Distributor,” pp. 26-29]

F12A/4/3 Construction Alberta News Supplement: “In-site presents Focus North”. – : Construction Alberta News Ltd. September 19, 1977 [See article “The Alaska Highway Pipeline Project”]

12 29 Executive: for the men of decision. – [?] : Hugh C. Maclean. August 1960 [Reprint from; “New Challenge for oilman Frank McMahon”]

35 12 30 George Cross Newsletter: Western Canadian Investments. – Vancouver, B.C.: George Cross. No. 131 (July 7, 1961). [Re: WTCL’s interest in Western Pacific Products & Crude Oil Pipelines Ltd.]

4 19 Maclean’s. – Montreal : Maclean-Hunter Publishing Corporation. January 5, 1957 [See article “Frank McMahon’s five lucky lives,” pp. 14-15, 39-43]

F12A/4/3 Opportunity in Canada. – Winnipeg: Fleet Publications Limited. 1979 (Special Report)

12 31 Partners: The Executive Magazine from Unisys Canada. – North York, Ont.: Unisys Canada Ltd. Fall 1990 [See article “On-Site: Westcoast Energy,” pp. 7-10]

12 32 The Sunday Sun: Weekend magazine. – Vancouver, B.C. Vol. 6, no. 30 (July 8, 1956) [See article “McMahon Always Strikes it Rich,” p. 12]

12 31 Time [U.S. edition]. – Chicago : Time Inc. Vol. 52, no. 17 (October 27, 1958) [See article “Canada: British Columbia at 100”, pp. 32-39]

Reports 12 33 Equity Review of Westcoast Transmission by DSA Research, October, 1982

12 34 Research Report on Westcoast Transmission Company Limited by The Value Line Investment Survey, October 11, 1985

12 35 Westcoast Transmission Company Ltd.: The Newest Ticket Symbol on the New York Stock Exchange [ca. 1964]

12 36 Westcoast Transmission Company Limited: Report by the Financial Post Corporation Service, 1979

Books 13 1 190 Independent Power Companies: Profiles of Industry players and Projects / Global Power Reports. – New York : McGraw-Hill, 1998.

12 37 Blue Flame of Service: A History of Union Gas Company and the National Gas Industry in Southwestern Ontario / Victor Lauriston ; edited by Ted Karry. – Hamilton, Ont.: United Gas Company of Canada, Ltd., 1961. [photocopy]

36 13 2 Builders of British Columbia: An Industrial History / G.W. Taylor. – Victoria, B.C. : Morriss Publishing, 1982

4 20 Canada: The Growth of a Great Nation / Auge International. − Mexico: Auge International, [1976?]

13 3 Continental Reach: The Westcoast Energy Story / Peter C. Newman. – Vancouver, B.C.: Douglas & McIntyre, 2002.

13 4 Design and Technology in Architecture / David Guise. – New York : John Wiley & Sons, 1985. [Incls. case study of Westcoast building]

13 5 The Financial Post 100 Best Companies to Work for in Canada / Jim Harris, Eva Innes, and Jim Lyon. – Toronto : Harper Collins, 1990.

13 6 The Financial Post Selects the 100 Best Companies to Work for in Canada / Jim Harris, Eva Innes, and Jim Lyon. – Toronto : Collins, 1986.

13 7 Guts and Guile: True Tales from the Backrooms of the Pipeline Industry / Ed Phillips ; foreword by Richard J. Doyle. – Vancouver, B.C.: Douglas & McIntyre, 1990.

13 8 Pipeline: TransCanada and the Great Debate -- A History of Business and Politics / William Kilbourn. – Toronto : Clarke, Irwin, 1970.

13 9 Profiles of U.S. and Canadian Natural Gas Pipeline Companies / Interstate Natural Gas Association of America. – Washington, D.C.: Interstate Natural Gas Association of America, 1995.

13 10 A Tradition of Service: The Story of Consumers’ Gas / Consumers’ Gas Company Limited. – Toronto : Consumers’ Gas Company Limited, 1993.

13 11 Union Gas: The First 75 Years / Win Miller; edited by Terry Diggle. – Chatham, Ont.: Union Gas Limited, 1986.

13 12 Wildcatters: The Story of Pacific Petroleums and Westcoast Transmission / Earle Gray. – Toronto: McClelland & Stewart, 1982.

37 Books, articles and other publications relating to the energy industry in British Columbia and in North America

13 13 A.G.A. Gas measurement Manual / edited by H.S. Bean and C.E. Terrell. – New York : American Gas Association, Inc., 1963.

13 14 American Gas Association 1978 Operating Section Proceedings / American Gas Association. – Arlington, Va. : American Gas Association, 1978.

13 15 Canada: Into the 1980s, The Financial Post Report on the Nation / The Financial Post. – Toronto: Maclean-Hunter Ltd., 1980.

12 38 Chronological summary of the development of the oil and gas industry in British Columbia, January 11, 1974 by D.P. McDonald.

12 39 The Current Status of the San Juan Basin, October 1952 by Ralph E. Davis, New York [report]

F12A/4/4 Final Environmental Statement – Crude Oil Transportation Systems Proposed by Northern Tier Pipeline Company, Northwest Energy Company, Kitimat Pipe Line Ltd., Trans Mountain Oil Pipe Line Corporation, Vols. 1-4 / Bureau of land management, US Department of the Interior. – US Department of the Interior, 1979.

12 40 Government of Alberta Emergency Response Plan for a Sour Gas Release / Publics Safety Services, Government of Alberta. – Calgary: Government of Alberta, 1988.

4 21-22 Historical Survey: Electric Service Areas in British Columbia / B.C. Energy Board. – Victoria, B.C. : Province of British Columbia, 1964.

14 1 Institute of Gas Technology, 50th Anniversary: Publications for 1941 to August 1991 / Institute of Gas Technology. – Chicago : Institute of Gas Technology, 1991.

14 2 Manual of Oil and Gas Terms / Charles J. Meyers and Howard R. Williams. – Albany, N.Y. : Matthew Bender & Company, 1964.

14 3 Natural Gas Reserves of Peace River Area, British Columbia and Alberta / G.S. Hume and A. Ignatieff. – Ottawa : Canada. Dept. of Mines and Technical Surveys, 1952.

38 12 41 Oilweek. – Calgary: Maclean Hunter Canadian Publishing. Vol. 43, no. 3 (Jan. 20, 1993)

14 4 Pacific Coast Gas Association: A Century of Excellence / editied by Gordon Blackley. – [San Francisco] : Pacific Coast Gas Association, 1993.

4 23 Petroleum Communication Foundation Newsletter. – Calgary, Alta. : Petroleum Communication Foundation. April 1992 August 1992 March 1993 September 1993 November 1994

14 5 Proceedings of the Annual Meetings of the Pacific Gas Association, 1893-1897. – Pacific Coast Gas Association. – Oakland, Calif. : Oakland Enquirer Publishing Co., 1897.

4 24 Public Utilities Commission of the State of Daily Calendar, Feb. 4, 1991…

F12A/4/3 Twenty Years of PCGA Annual Meetings / Pacific Coast Gas Association. – Glendale, Calif. : Chapman Publication Services, 1988

14 6 Vancouver 1996: The Annual Meeting of the Trilateral Commission / The Trilateral Commission. – New York: The Trilateral Commission, 1996.

Executive speeches and addresses

SP 94:1 Westcoast Transmission Co. Ltd.: Opening 1957 ceremonies; Westcoast luncheon (2 audio reels)

12 1-3 Speeches 1960-1975 (vol.1) 1960-1975

12 4-6 Speeches 1975-1981 (vol. 2) 1975-1980

12 7-11 Speeches 1981-1992 (vol.3) 1981-1992

12 12-14 Speeches 1993-present (vol. 4) 1993-1997

12 15 Address by Kelly Gibson, Chairman of Foothills 1976 Pipelines Ltd. and Westcoast Transmission Co. Ltd. to Toronto financial community, 1976

39 12 16 The Alaska Highway Gas Pipeline Project: Address 1979 by John Anderson, Vice-President and Chief Operating Officer, Westcoast Transmission Company Limited...to International Pipe Line Contractors Association XIII Annual Convention, Monaco, September 25-29, 1979

12 17 Address by John Anderson, President, Westcoast 1981 Transmission Company, Limited to the Western Investment Seminar, Richmond, B.C., June 17, 1981.

Video recordings

VT 20:1 Westcoast Transmission Company Limited: Master 1978-1979 Tape 01, Dec. ‘78-Dec. ’79 (Interviews on Energy, BCTV and CBC]

VT 20:2 Westcoast Transmission, CBC Footage: Hon. R. [198-] McClelland: CBC Interview with Paul Raugust

VT 20:3 Off air monitoring of Webster show, March 5, 1980 1981 (Ed Phillips BCTV interview with Jack Webster)

VT 20:4 Pipeline from the Peace to the Pacific, Westcoast 1986 Transmission, March 31, 1986

VT 20:5 Forget the Future: The Energy to Improve Gas 1992 Supply Business Unit – Rachel Brandi

VT 20:6 Westcoast Energy: A Corporate Profile, January 1994 1994

VT 20:7 Westcoast Energy: CBUT 8:44pm, June 30, 1995 1995

Scrapbooks

F12A/4/3 Scrapbook: Westcoast Transmission : Opening 1957 ceremonies, October 7-8, 1957.

40 Maps and plans:

Loc./Folder From subject file Historical Vertical Files: Pacific Petroleum – Maps: 21:5 1 Peace River / British Columbia. Department of Lands. – Scale 1” = 4 miles. -- January 2, 1945. -- 1 map : col. ; 70 x 106 cm.

21:5 1 Map prepared by Westcoast Transmission Co. Ltd. showing Cities, Towns, Villages and Municipal Districts in British Columbia and Alberta which have been notified…as of the application to the Parliament of Canada to incorporate the Company and the Purposes thereof / John Wylie. -- No scale given. -- April 1949. --1 map : photocopy ; 75 x 102 cm

21:5 1 The New Railway Routing Map of Alberta / Mundy Map Co., Vancouver, B.C. -- No scale given. -- Aug. 1949. -- 1 map : blueline print ; 74 x 67 cm.

21:5 1 Western Canada Routing Map / Mundy Map Co., Vancouver, B.C. -- No scale given. -- May 1949. -- 1 map : blueline print ; 74 x 91 cm.

21:5 1 Natural Gas for Pacific Northwest, Showing Principal Projects / [?] -- [Alberta] : [?], [195-?]. -- 1 map : blueline print ; 63 x 88 cm.

21:5 1 Map Prepared by Westcoast Transmission Co. Ltd. showing Main Line, Branch Lines, Proposed Branch Line, Gathering Lines / Westcoast Transmission Co. Ltd. -- No scale given. -- [ca. 1960]. 1 map : blueline print ; 98 x 51 cm.

21:5 1 Map Prepared by Westcoast Transmission Co. Ltd. showing Main Line, Branch Lines, Proposed Branch Line, Gathering Lines / Westcoast Transmission Co. Ltd. -- No scale given. -- [ca. 1960]. 1 map : photocopy ; 28 x 22 cm.

21:5 1 [British Columbia, Alberta and Northern United States] / [S.l.], [s,n.]. -- Scale indeterminable. -- [n.d]. -- 1 map section only : col. ; 56 x 72 cm.

41 21:5 1 Gas Fields of Alberta / Link & Nauss Ltd. – No scale given. -- [n.d.]. -- 1 map : photocopy ; 28 x 22 cm.

21:5 1 Pincher Creek plan showing crown leases. -- n.d.

21:5 2 Classification of Proven Gas Fields by Geographical Areas Suited to Long Term Provincial and Export Supply in Province of Alberta / Westcoast Transmission Company, Limited, Calgary, Alberta. -- Scale 1” = 50 miles. -- [196-?]. -- 1 map : col. ; 44 x 27.5 cm.

21:5 2 Portion of N.E. British Columbia & N.W. Alberta showing Existing & Proposed Gas Pipelines / Westcoast Transmission Company Limited, Calgary, Alberta. No scale given. – [ca. 1960]. – 1 map : blackline print ; 39 x 26 cm.

21:5 2 Map showing Proposed Pipelines and Market Areas of Westcoast Transmission Company Limited and Pacific Corporation, El Paso Natural Gas Company / Westcoast Transmission Company Ltd., Lethbridge, Alberta. -- Scales 1/2” = 50 miles. -- [ca. 1960]. -- 1 map : blueprint ; 31.5 x 43.5 cm.

21:5 2 Map showing Proposed Pipelines and Market Areas of Westcoast Transmission Company Limited and Pacific Northwest Pipeline Corporation, El Paso Natural Gas Company / Westcoast Transmission Company Ltd., Lethbridge, Alberta. -- Scales 1/2” = 50 miles. -- [ca. 1960]. -- 1 map : photocopy ; 31.5 x 43.5 cm.

21:5 3 Westcoast Transmission Company, Limited: Compressor Station Plot Plan, Nig Creek Field Compressor Station, Drawing No. NA- A-100 [architectural drawing] / Canadian Bechtel Limited, Agent, Vancouver, B.C. -- Scale 1” = 40’. -- January 29, 1963. -- 1 architectural drawing : blueline print ; 70 x 104 cm.

21:5 3 Westcoast Transmission Company, Limited: Piping & Instrument Diagram, Main Gas & Emergency Blowdown System, Nig Creek Field Compressor Station, Drawing No. NA-A-101 [architectural drawing] / Canadian Bechtel Limited, Agent, Vancouver, B.C. -- Not drawn to scale. -- January 28, 1963. -- 1 architectural drawing : blueline print ; 70 x 104 cm.

21:5 3 Westcoast Transmission Company, Limited: Piping & Instrument Diagram, Main Gas & Emergency Blowdown System, Nig Creek Field Compressor Station, Drawing No. NA-A-102 [architectural drawing] / Canadian Bechtel Limited, Agent, Vancouver, B.C. -- Not drawn to scale. -- January 28, 1963. -- 1 architectural drawing : blueline print ; 70 x 104 cm.

42 21:5 3 Westcoast Transmission Company, Limited: Equipment Layout -- Compressor & Aux. Building, Nig Creek Field Compressor Station, Drawing No. NA-A-103 [architectural drawing] / Canadian Bechtel Limited, Agent, Vancouver, B.C. -- Scale 1/8” = 1’0”. -- January 27, 1963. -- 1 architectural drawing : blueline print ; 70 x 104 cm.

21:5 3 Westcoast Transmission Company, Limited: Equipment Layout -- Diagram of Emergency Shutdown Conditions, Nig Creek Field Compressor Station, Drawing No. NA-A-104 [architectural drawing] / Canadian Bechtel Limited, Agent, Vancouver, B.C. -- Not drawn to scale. -- January 28, 1963. -- 1 architectural drawing : blueline print ; 70 x 104 cm.

21:5 4 Westcoast Transmission Company, Limited: Equipment Layout -- Site Location Map, Compressor Station No. 2, Drawing No. 2A- A-121 [architectural drawing] / Canadian Bechtel Limited, Agent, Vancouver, B.C. -- Scale 1” = 100’0”. -- January 19, 1963. -- 1 architectural drawing : blueline print ; 70 x 104 cm.

21:5 4 Westcoast Transmission Company, Limited: Equipment Layout – Compressor Station Plot Plan, Compressor Station No. 2, Drawing No. 2A-A-122 [architectural drawing] / Canadian Bechtel Limited, Agent, Vancouver, B.C. -- Scale 1” = 20’0”. -- January 19, 1963. -- 1 architectural drawing : blueline print ; 70 x 104 cm.

21:5 4 Westcoast Transmission Company, Limited: Equipment Layout -- Main Gas System, Station No. 2, Drawing No. 2A-A-123 [architectural drawing] / Canadian Bechtel Limited, Agent, Vancouver, B.C. -- Not drawn to scale. -- January 28, 1963. -- 1 architectural drawing : blueline print ; 70 x 104 cm.

21:5 4 Westcoast Transmission Company, Limited: Diagram of Fuel Gas System, Compressor Station No. 2, Drawing No. 2A-A-124 [architectural drawing] / Canadian Bechtel Limited, Agent, Vancouver, B.C. -- Not drawn to scale. -- January 19, 1963. -- 1 architectural drawing : blueline print ; 70 x 104 cm.

21:5 4 Westcoast Transmission Company, Limited: Equipment Layout -- Compressor & Aux. Bldg., Station No. 2, Drawing No. 2A-A-125 [architectural drawing] / Canadian Bechtel Limited, Agent, Vancouver, B.C. -- Scale 1/8” = 1’0”. -- January 19, 1963. -- 1 architectural drawing : blueline print ; 70 x 104 cm.

43 21:5 4 Westcoast Transmission Company, Limited: Diagram -- Emergency Shutdown Conditions, Compressor Station No. 2, Drawing No. 2A-A-126 [architectural drawing] / Canadian Bechtel Limited, Agent, Vancouver, B.C. -- Not drawn to scale. -- January 19, 1963. -- 1 architectural drawing : blueline print ; 70 x 104 cm.

14 10- The Briefcase Land Office with Deeper Rights, Alberta - British 13 Columbia. Calgary : Nickel Map Service Ltd., [1979-1991]

F12A/4/4 Environmental Impact Assessment of the proposed Grizzly Pipeline & Pine River Gas Plant: Map Folio, June 1977 for Westcoast Transmission Company Limited / – Vancouver, B.C. : C.D. Schultz & Company Ltd., 1977.

21:5 5 Gas System Maps / Westcoast Energy Inc. – Vancouver, B.C. : Westcoast Energy Inc., 1990. [42 maps]

F12A/4/3 Western L.N.G. Project Pipeline, Vol. 4, Part V – Environmental Maps / Westcoast Transmission Company Limited. – Vancouver, B.C. : Westcoast Transmission Company Ltd., 1983.

F12A/4/3 Vancouver Island Natural Gas System: Corridor & Route Nomination – Atlas / B.C. Hydro & Power Authority Gas Engineering Division. – Vancouver, B.C. : B.C. Hydro, 1980.

44 Westcoast Energy Inc. fonds

RBSC-ARC-1608

Photograph inventory according to box numbers:

Box number Photograph Identifier Notes

Photo Box 1 BC 2009/1-128

Photo Box 2 BC 2009/129-254

Photo Box 3 BC 2009/255-445

Photo Box 4 BC 2009/446-609

Photo Box 5 BC 2009/614-1216 Large photographs

Photo Box 6 BC 2009/610-1059 Small photographs

Photo Box 7 BC 2009/1217-1775 Large photographs

Photo Box 8 BC 2009/1343-2839 Small photographs

Photo Box 9 BC 2009/1777-2870 This box has 15 unidentified prints/negatives at the end of the box, (numbered 1 through 8)

Photo Box 10 BC 2009/2871-3046, 3074-3139 Slides

Photographs and Slides

No. TITLE DATE ORIGINAL #

BC 2009/264 Construction – Alberta to California Pipeline [195-] ABC-1-1

BC 2009/265 Construction – Alberta to California [195-] ABC-1-2 Pipeline: Welding pipes at Kingsgate, B.C.

BC 2009/266 Construction – Alberta to California [195-] ABC-2-1 Pipeline: A valve in the main pipeline near Blairmore, Alberta

BC 2009/267 Construction – Alberta to California Pipeline [195-] ABC-2-2

BC 2009/268 Construction – Alberta to California Pipeline [195-] ABC-3-1

BC 2009/138 Aerial Crossings – Agassiz, Quesnel & 1956 AC-AR-1-1 Rosedale: Pouring concrete for foundations for Quesnel River Crossing, August 1956

BC 2009/139 Aerial Crossings – Agassiz, Quesnel & [1956] AC-AR-1-2 Rosedale: Quesnel River Crossing [construction]

BC 2009/140 Aerial Crossings – Agassiz, Quesnel & [1956] AC-AR-2-1 to -141 Rosedale [construction] 2-2

BC 2009/142 Aerial Crossings – Agassiz, Quesnel & 1956 AC-AR-3-1 Rosedale: Quesnel River Aerial Crossing, looking north, October 31, 1956

BC 2009/143 Aerial Crossings – Agassiz, Quesnel & [1956] AC-AR-3-2 to -147 Rosedale [construction] 5-2

BC 2009/ 148 Aerial Crossings – Agassiz, Quesnel & 1957 AC-AR-6-1 Rosedale: Agassiz, Rosedale crossing [construction], July 18, 1957

BC 2009/149 Aerial Crossings – Agassiz, Quesnel & [ca. 1956] AC-AR-6-2, -151 Rosedale [construction] 7-1, 9-1

BC 2009/152 Aerial Crossings – Agassiz, Quesnel & [198-] AC-AR-13-1 Rosedale [workmen standing on crossing]

BC 2009/153 Aerial Crossings – Agassiz, Quesnel & [198-] AC-AR-13-2 -155 Rosedale [construction] to 14-2

BC 2009/ Aerial Crossings – Agassiz, Quesnel & [198-?] AC-AR-15-2 1749 Rosedale

45 BC 2009/156 Aerial Crossings – Agassiz, Quesnel & [ca. 1956?] AC-AR-16-1 -158 Rosedale to 17-1

BC 2009/159 Aerial Crossings – Agassiz, Quesnel & [197-?] AC-AR-17-2 -162 Rosedale to 19-1

BC 2009/163 Aerial Crossings – Agassiz, Quesnel & [ca. 1956?] AC-AR-19-2 –166 Rosedale to 21-1

BC 2009/797 Aerial Crossings – Agassiz, Quesnel, & 1958 AC-AR-21-2, -798 Rosedale: 30” pipeline crossing at Flood 26-2

BC 2009/167 Aerial Crossings – Agassiz, Quesnel & [197-?] AC-AR-22-1 Rosedale

BC 2009/168 Aerial Crossings – Agassiz, Quesnel & [ca. 1956?] AC-AR-25-1 -171 Rosedale to 26-2

BC 2009/172 Aerial Crossings – Agassiz, Quesnel & [197-?] AC-AR-27-2 Rosedale

BC 2009/173 Aerial Crossings – Agassiz, Quesnel & [ca. 1956?] AC-AR-32-1 -174 Rosedale to 32-2

BC 2009/88- Aerial Crossings -- Peace River [1956] AC-PE-1-1 to 89 [construction] 1-2

BC 2009/90 Aerial Crossings -- Peace River: Crossing 1956 AC-PE-2-1 foundation being put in, Taylor Flat, B.C., August 1956.

BC 2009/91 Aerial Crossings -- Peace River [1956] AC-PE-2-2 [construction]

BC 2009/92 Aerial Crossings -- Peace River [1956] AC-PE-3-1

BC 2009/93 Aerial Crossings -- Peace River: First 1956 AC-PE-3-2 section, 40’ North Tower at Peace River, September 1956

BC 2009/94 Aerial Crossings -- Peace River [1956] AC-PE-4-1 [construction]

BC 2009/95 Aerial Crossings -- Peace River: [Pipeline] [1956] AC-PE-4-2 Crossing, South Bank. Tower and concrete protective works in center and wind cable and tower guy anchors left and right.

BC 2009/96 Aerial Crossings -- Peace River: Anchor, [1956] AC-PE-5-1 October [1956]

46 BC 2009/97 Aerial Crossings -- Peace River: North Bank, [1956] AC-PE-5-2 with tower at right and tower guy anchor and wind cable anchor in foreground

BC 2009/98 Aerial Crossings -- Peace River: Looking [1956] AC-PE-6-1 north-west from South Bank. Tower guy cables in place. Back stay cables hung on tower. Construction cables hung tower to tower.

BC 2009/99 Aerial Crossings -- Peace River: Looking [1956] AC-PE-6-2 northward from South Bank of River, with main cables in central foreground and wind cable and guy anchors at right

BC 2009/100 Aerial Crossings -- Peace River [1956] AC-PE-7-1

BC 2009/101 Aerial Crossings -- Peace River: Tower [1956] AC-PE-7-2

BC 2009/102 Aerial Crossings -- Peace River: Looking [1956] AC-PE-8-1 southward from mid-stream, with erecting crew working on travelling platform suspended from main cable

BC 2009/103 Aerial Crossings -- Peace River: Looking [1956] AC-PE-8-2 southward from North Bank, 30” main line on slope in background

BC 2009/104 Aerial Crossings -- Peace River [1956] AC-PE-9-1

BC 2009/105 Aerial Crossings -- Peace River: Pipeline [1956] AC-PE-9-2 suspension bridge across the Peace River, near starting point of the Westcoast pipeline at Taylor, B.C….

BC 2009/254 Aerial Crossings -- Peace River 1957 AC-PE-10-2

BC 2009/106 Aerial Crossings -- Peace River, July 1957 1957 AC-PE-11-2

BC 2009/107 Aerial Crossings -- Peace River [ca. 1957] AC-PE-12-1 -109 to 13-1

BC 2009/110 Aerial Crossings -- Peace River, at Taylor, [ca. 1957] AC-PE-13-2 B.C.

BC 2009/111 Aerial Crossings -- Peace River [ca. 1957] AC-PE-14-1 -112 to 14-2

BC 2009/ Aerial Crossings – Savona: [Construction] [195-] AC-SA-1-1 to 1584-1600 12-2

47 BC 2009/113 Aerial Crossings – Shelley: Launching 1956 AC-SH-1-1 to -114 platform and two-inch cable stringing 1-2 operation for at Shelley, B.C., August 1956

BC 2009/115 Aerial Crossings – Shelley: Cable drums 1956 AC-SH-2-1 supplying two-inch cable being strung across Fraser River at Shelley, B.C., August 1956

BC 2009/116 Aerial Crossings – Shelley [construction] [1956] AC-SH-2-2

BC 2009/117 Aerial Crossings – Shelley: Two-inch cable 1956 AC-SH-3-1, -118, 120 being strung across Fraser River at Shelley, 3-2, 4-2 B.C., August 1956

BC 2009/119 Aerial Crossings – Shelley: Fraser River 1956 AC-SH-4-1 crossing at Shelley, B.C., with cable pulling winch on north anchor, September 1956

BC 2009/121 Aerial Crossings – Shelley [construction] [1956] AC-SH-5-1

BC 2009/122 Aerial Crossings – Shelley: Connecting pipe 1956 AC-SH-5-2 saddles to cable being strung across Fraser River at Shelley, B.C., August 1956

BC 2009/123 Aerial Crossings – Shelley [construction] [1956] AC-SH-6-1 to -127 8-2

BC 2009/128 Aerial Crossings – Shelley: [Pipe being [1956] AC-SH-9-1 to -137 threaded through hangers] 15-1

BC 2009/796 Aerial Crossings – Shelley: [Men walking [1956] AC-SH-9-2 across cables]

BC 2009/382 Annual General Meetings: April 20, 1978 1978 AGM1-4E-1 –383 to 4E-2

BC 2009/384 Annual General Meetings: April 19, 1979 1979 AGM1-13-1 to –388 17-1

BC 2009/786 Construction – Alaska Highway Gas 1978 AHGP-1-2 Pipeline: [Ceremony for beginning of construction, R.L. Pierre in centre and Edwin C. Phillips on right]

BC 2009/375 Construction – Alaska Highway Gas 1978 AHGP-5-1 to –378 Pipeline: [Ceremony] 6-2

BC 2009/379 Construction – Alaska Highway Gas 1978 AHGP-7-1 Pipeline: [Construction]

48 BC 2009/787 Construction – Alaska Highway Gas 1978 AHGP-7-2 Pipeline: [Beginning of construction, men moving pipes]

BC 2009/788 Construction – Alaska Highway Gas 1978 AHGP-8-1 Pipeline: [Beginning of construction, men welding pipes]

BC 2009/380 Construction – Alaska Highway Gas 1978 AHGP-8-1 to –381 Pipeline: [Ceremony] 8-2

BC 2009/255 Annual Report Photos: 1976, Westcoast 1976 ARP-3-1 Transmission Office Building (cover)

BC 2009/819 Annual Report Photos, 1970-1979: Grizzly 1977 ARP-3B1 Valley Construction, North of Chetwynd (1977 Annual Report)

BC 2009/256 Annual Report Photos: 1977, Northeast of 1977 ARP-3B-1 Chetwynd

BC 2009/257 Annual Report Photos: 1977, Northeast of 1977 ARP-3B-2 Chetwynd 36” pipeline loop

BC 2009/258 Annual Report Photos: 1977, Weld to 36” 1977 ARP-4B-1 section of pipe between Taylor and Willow Flats, B.C. (cover)

BC 2009/259 Annual Report Photos: 1977, Fort Nelson 1977 ARP-4C-1 Sulphur Plant

BC 2009/260 Annual Report Photos: 1977, Massive block 1977 ARP-4C-2 of sulphur removed from sour natural gas at Fort Nelson Sulphur Plant

BC 2009/261 Annual Report Photos: 1977, Compressor 1977 ARP-4D-1 Unit Booster Station #1 at Taylor, B.C.

BC 2009/262 Annual Report Photos: 1977, [Man operating 1977 ARP-4D-2 machinery]

BC 2009/ Annual Report Photos, 1970-1979: Edwin C. 1977 ARP-4E-1 1767 Phillips standing in front of pipe, next to welder

BC 2009/818 Annual Report Photos, 1980-1989: 1983 ARP-42-2 Westcoast Hall at the Orpheum Theatre in Vancouver, B.C.

BC 2009/263 Annual Report Photos: 1983, Kadluk 0-07 1983 ARP2-43-1 well, a Westcoast Petroleums joint venture

49 BC 2009/ Aitken Creek: [Views of buildings and 1989 ATC-1-1-1 to 1613 - 1632 machinery] 4-1-2

BC 2009/269 Construction – Beaver River: Near Beaver 1971 BR-3-1 River A-2 location

BC 2009/270 Construction – Beaver River 1971 BR-3-2 to -271 4-1

BC 2009/272 Construction – Beaver River: [Pipe welding] 1971 BR-5-1

BC 2009/273 Construction – Beaver River 1971 BR-6-1

BC 2009/ Booster Stations – Stoddart #10: November 1981 BSS-2-1-1 to 1360 - 1365 1981 [Interior view] 2-2-2

BC 2009/ Construction – 1956-1957: North of Prince [1956] C-1-1-1 to 1777-1782 George C-1-2-2

BC 2009/ Construction – 1956-1957: North of Prince 1956 C-1-2-3 to 1783-1792 George, November 1956 C-2-2-4

BC 2009/ Construction – 1956-1957: North of Prince 1956 C-3-1-1 to 1793- 1800 George, July 27, 1956 C-3-2-2

BC 2009/ Construction – 1956-1957: North of Prince 1956 C-4-1-1 to 1801-1802 George; Installing gate valve, July 27, 1956 C-4-1-2

BC 2009/ Construction – 1956-1957: North of Prince [1957] C-4-1-3 to 1803-1804 George, Crossing at Savona C-4-1-4

BC 2009/ Construction – 1956-1957: North of Prince 1957 C-4-2-1 1805 George, Station # 7 at Savona, August 1957

BC 2009/ Construction – 1956-1957: North of Prince 1957 C-4-2-2 1806 George, Gate Valve, August 1957

BC 2009/ Construction – 1956-1957: North of Prince 1957 C-4-2-3 to 1807-1808 George, Thompson River Crossing at C-4-2-4 Savona, August 1957

BC 2009/ Construction – 1956-1957: North of Prince 1956 C-5-1-1 to 1809-1820 George, [Pipeline construction and crew, C-6-1-4 Pine Pass], August 1956

BC 2009/ Construction – 1956-1957: , 1956 C-6-2-1 to 1821-1828 August 1956 C-7-1-4

BC 2009/ Construction – 1956-1957: Taylor Flat, 1956 C-7-2-1 to 1829-1834 crossing, August 1956 C-8-1-2

50 BC 2009/ Construction – 1956-1957: Taylor Flat, 1956 C-8-1-3 1835 Pacific Petroleums building, August 1956

BC 2009/ Construction – 1956-1957: Fort St. John 1956 C-8-1-4 1836 sign, August 1956

BC 2009/ Construction – 1956-1957: Taylor Flat, 1956 C-8-2-1 to 1837-1838 August 1956 C-8-2-2

BC 2009/ Construction – 1956-1957: Savona, August 1956 C-9-1-1 to 1839-1841 1956 C-9-1-3

BC 2009/ Construction – 1956-1957: Quesnel River, 1956 C-9-1-4 to 1843-1846 August 1956 C-9-2-3

BC 2009/ Construction – 1956-1957: Shelley River 1956 C-9-2-4 1847 Crossing, August 1956

BC 2009/ Construction – 1956-1957: Spread at Savona, 1956 C-10-1-1 to 1848-1855 B.C., August 1956 C-10-2-4

BC 2009/ Construction – 1956-1957: Shelley River 1956 C-11-1-1 to 1856-1875 Crossing, August 1956 C-13-2-1

BC 2009/ Construction – 1956-1957: Prince George, 1956 C-13-2-2 to 1876-1892 August 1956 C-15-2-4

BC 2009/ Construction – 1956-1957: Dutton-Williams 1956 C-16-1-1 to 1893-1946 Brothers Spread in Pine Pass, August 1956 C-23-2-3 [Includes photographs of camp chefs]

BC 2009/ Construction – 1956-1957: Fraser River at 1956 C-24-1-1 to 1947-1975 Shelley Crossing, November 1956 C-27-2-2

BC 2009/ Construction – 1956-1957: July 27, 1956 1956 C-28-1-1 to 1976-2043 C-36-2-4

BC 2009/ Construction – 1956-1957: Agassiz 1957 C-37-1-1 to C- 2044-2046 Crossing, October 1957 37-1-3

BC 2009/ Construction – 1956-1957: Farmer checking 1957 C-37-1-4 2047 right-of-way, October 1957

BC 2009/ Construction – 1956-1957: Automatic valve 1957 C-37-2-1 2048 near Agassiz, October 1957

BC 2009/ Construction – 1956-1957: Operator houses 1957 C-37-2-2 2049 at Savona, October 1957

51 BC 2009/ Construction – 1956-1957: Savona 1957 C-37-2-3 2050 Compressor Station, October 1957

BC 2009/ Construction – 1956-1957: Operator houses 1957 C-37-2-4 2051 at Savona, October 1957

BC 2009/ Construction – 1956-1957: Fraser River at 1956 C-38-1-1 to 2052-2059 Shelley crossing, November 1956 C-38-2-4

BC 2009/ Construction – 1956-1957: November 1956 1956 C-39-1-1 2060

BC 2009/ Construction – 1956-1957: Quesnel River 1956 C-39-2-1 to C- 2061-2062 Crossing, November1, 1956 39-2-2

BC 2009/ Construction – 1956-1957: 1956 C-39-2-3 to C- 2063-2064 Crossing, November 1, 1956 39-2-4

BC 2009/ Construction – 1956-1957: North of Prince 1956 C-40-1-1 to C- 2065-2079 George, November 1, 1956 41-2-4

BC 2009/ Construction – 1956-1957: Moving Clarke 1957 C-42-1-1 to 2080-2093 units (engines), February 25, 1957 C-43-2-2

BC 2009/ Construction – 1956-1957: February 25, 1957 C-43-2-3 to 2094-2095 1957 C-43-2-4

BC 2009/ Construction – 1956-1957: Installation of 1957 C-44-1-1 to 2096-2099 Clarke engine, February 25, 1957 C-44-1-4

BC 2009/ Construction – 1956-1957: February 25, 1957 C-44-2-1 to C- 2100-2103 1957 44-2-4

BC 2009/ Construction – 1956-1957: Moving Clarke 1957 C-45-1-1 to 2104-2121 units (engines), February 25, 1957 C-47-2-2

BC 2009/ Construction – 1956-1957: Welders in Pine 1957 C-48-1-1 to C- 2122-2124 Pass, August 1957 48-1-3

BC 2009/ Construction – 1956-1957: Pipe gang on last 1957 C-48-2-1 to C- 2125-2134 mile in Pine Pass, August 1957 49-2-2

BC 2009/ Construction – 1956-1957: Welding 1957 C-49-2-3 2135 inspector checking the hot pass, August 1957

BC 2009/ Construction – 1956-1957: Welders in Pine 1957 C-49-2-4 2136 Pass, August 1957

BC 2009/ Construction – 1956-1957: Making a tie-in in 1957 C-50-1-1 to C- 2137-2141 Pine Pass, August 1957 50-2-1

52 BC 2009/ Construction – 1956-1957: Padding pipe 1957 C-50-2-2 2142 before backfilling, Pine Pass, August 1957

BC 2009/ Construction – 1956-1957: Coat and wrap 1957 C-50-2-3 to C- 2143-2144 machine in Pine Pass, August 1957 50-2-4

BC 2009/ Construction – 1956-1957: Bijou Creek, Pine 1957 C-51-1-1 2145 Pass, August 1957

BC 2009/ Construction – 1956-1957: Hydrostatic test 1957 C-51-1-2 2146 equipment, August 1957

BC 2009/ Construction – 1956-1957: Bijou Creek, Pine 1957 C-51-1-3 to C- 2147-2149 Pass, August 1957 51-2-1

BC 2009/ Construction – 1956-1957: Gas Valve 1957 C-51-2-2 2150 Installation, Pine Pass, August 1957

BC 2009/ Construction – 1956-1957: Making a tie-in in 1957 C-51-2-3 2151 Pine Pass, August 1957

BC 2009/ Construction – 1956-1957: [Coating pipes] [ca. 1956] C-52-1 1771

BC 2009/ Construction – 1956-1957: [Lowering pipe], 1956 C-53-1-1 to C- 2152-2159 July 27, 1956 53-2-4

BC 2009/ Construction – 1956-1957: Jack Burkhalter, 1956 C-54-1-1 2160 November 1956

BC 2009/ Construction – 1956-1957: Abe Barnard, 1956 C-54-1-2 2161 Material, November 1956

BC 2009/ Construction – 1956-1957: Ken Kenna, 1956 C-54-1-3 2162 November 1956

BC 2009/ Construction – 1956-1957: Hank Mogg, 1956 C-54-1-4 2163 November 1956

BC 2009/ Construction – 1956-1957: Lloyd Johnson, 1956 C-54-2-1 2164 Bill Heinrich, November 1956

BC 2009/ Construction – 1956-1957: Cliff Minter, 1956 C-54-2-2 2165 Foreman, November 1956

BC 2009/ Construction – 1956-1957: Foremen Mark 1956 C-54-2-3 2166 Wilson, Alan Williams, and Norman Reid, November 1956

BC 2009/ Construction – 1956-1957: Unidentified 1956 C-54-2-4 2167 employee, November 1956

53 BC 2009/ Construction – 1956-1957: Hank Mogg, 1956 C-55-1-1 2168 November 1956

BC 2009/ Construction – 1956-1957: Ken Kenna, 1956 C-55-1-2 2169 November 1956

BC 2009/ Construction – 1956-1957: (l-r): Bruce 1956 C-55-1-3 2170 Moffat, Dorothy Foster, Ken Kenna, Doug Couzens, Nelson Moore, Cecilia McMillan, and Dave Salisbury, November 1956

BC 2009/ Construction – 1956-1957: Henry Emerson, 1956 C-55-1-4 2171 November 1956

BC 2009/ Construction – 1956-1957: (l-r): Ralph 1956 C-55-2-1 2172 Bucher, Mike Finnerty, Bob Blair, November 1956

BC 2009/ Construction – 1956-1957: Paul Killian, 1956 C-55-2-2 2173 November 1956

BC 2009/ Construction – 1956-1957: Unidentified 1956 C-55-2-3 2174 crew members, November 1956

BC 2009/ Construction – 1956-1957: Cliff Pool, 1956 C-55-2-4 2175 November 1956

BC 2009/ Construction – 1956-1957: Parsnip River, 1956 C-56-1-1 2176 November 1, 1956

BC 2009/ Construction – 1956-1957: Quesnel River 1956 C-56-1-2 to 2177-2180 crossing, November 1, 1956 C-56-2-1

BC 2009/ Construction – 1956-1957: North of Prince 1956 C-56-2-2 to C- 2181-2182 George, November 1, 1956 56-2-3

BC 2009/ Construction – 1956-1957: Shelley Crossing 1956 C-57-1-1 to 2183-2205b at the Fraser River, November 1, 1956 C-59-2-4

BC 2009/ Construction – 1956-1957: Clarke engine 1957 C-60-1-1 to 2206-2213 installation, February 1957 C-60-2-4

BC 2009/ Construction – 1956-1957: Parsnip River 1957 C-61-1-1 to 2214-2228 camp, approaching Pine Pass, July 16, 1957 C-62-2-4

BC 2009/ Construction – 1956-1957: McLeod Lake 1957 C-63-1-1, 2229, 2233- Compressor Station, July 17, 1957 C-63-2-1 to 2235 C-63-2-3

54 BC 2009/ Construction – 1956-1957: Parsnip River 1957 C-63-1-2 to 2230-2232, camp, approaching Pine Pass, July 17, 1957 C-63-1-4, 2236-2271 C-63-2-4 to C- 69-2-1

BC 2009/ Construction – 1956-1957: Welding on last 1957 C-70-1-1 to 2272-2283 mile through Pine Pass, B.C., August 1957 C-71-1-4

BC 2009/ Construction – 1956-1957: Sideboom 1957 C-71-2-1 to 2284-2291 Operator, August 1957 C-72-1-4

BC 2009/ Construction – 1956-1957: Making a tie-in in 1957 C-72-2-1 2292 Pine Pass, August 1957

BC 2009/ Construction – 1956-1957: Wrapping by 1957 C-72-2-2 to 2293-2295 hand where tie-in was made, Pine Pass, C-72-2-4 August 1957

BC 2009/ Construction – 1956-1957: Water pump and 1957 C-73-1-1 to 2296-2299 storage tank, August 1957 C-73-1-4

BC 2009/ Construction – 1956-1957: Quesnel River 1957 C-73-2-1 to 2300-2303 Crossing, August 1957 C-73-2-4

BC 2009/ Construction – 1956-1957: Operators Houses 1957 C-74-1-1 to 2304-2307, at Station #5, Quesnel, August 1957 C-74-1-4, 2310-2311 C-74-2-3 to C- 74-2-4

BC 2009/ Construction – 1956-1957: [Quesnel River?], 1957 C-74-2-1 to 2308-2309 August 1957 C-74-2-2

BC 2009/ Construction – 1956-1957: Gas Intake and 1957 C-75-1-1 2312 Scrubbers, Station #5, Quesnel, August 1957

BC 2009/ Construction – 1956-1957: Generator Room, 1957 C-75-1-2 to 2313-2315 Station #5, Quesnel, August 1957 C-75-1-4

BC 2009/ Construction – 1956-1957: Operators Houses 1957 C-75-2-1 2316 at Station #5, Quesnel, August 1957

BC 2009/ Construction – 1956-1957: Compressor 1957 C-75-2-2 to 2317-2319 Station #5, Quesnel, August 1957 C-75-2-4

BC 2009/ Construction – 1956-1957: Peace River 1957 C-76-1-1 2320 Aerial Crossing, August 1957

BC 2009/ Construction – 1956-1957: Scrubber at Stn. 1957 C-76-1-2 2321 1, Taylor Flat, B.C., August 1957

55 BC 2009/ Construction – 1956-1957: Compressor 1957 C-76-1-3 2322 Station #1, Taylor Flat, B.C., August 1957

BC 2009/ Construction – 1956-1957: Gas processing 1957 C-76-1-4 2323 Plant, Taylor Flat, B.C., August 1957

BC 2009/ Construction – 1956-1957: Peace River 1957 C-76-2-1 to C- 2324-2327 Aerial Crossing, August 1957 76-2-4

BC 2009/ Construction – 1956-1957: Coat and wrap in 1957 C-77-1-1 to C- 2328-2331 Pine Pass, August 1957 77-1-4

BC 2009/ Construction – 1956-1957: Generator Room, 1957 C-77-2-1 to C- 2332-2334 Station #5, Quesnel, August 1957 77-2-3

BC 2009/ Construction – 1956-1957: Nordberg 1957 C-77-2-4 2335 Engines at Station #5, Quesnel, August 1957

BC 2009/ Construction – 1956-1957: Ingersoll-Rand 1957 C-78-1-1 2336 Engines at Station #1, Taylor Flat, B.C., August 1957

BC 2009/ Construction – 1956-1957: Gas processing 1957 C-78-1-2 to C- 2337-2338 Plant, Taylor Flat, B.C., August 1957 78-1-3

BC 2009/ Construction – 1956-1957: Power Station, 1957 C-78-1-4 to C- 2339-2341 Taylor Flat, B.C., August 1957 78-2-2

BC 2009/ Construction – 1956-1957: Peace River 1957 C-78-2-3 2342 Aerial Crossing, August 1957

BC 2009/ Construction – 1956-1957: Compressor 1957 C-78-2-4 2343 Station #1, Taylor Flat, B.C., August 1957

BC 2009/ Construction – 1956-1957Fort St. John signs, 1957 C-79-1-1 2344 August 1957

BC 2009/ Construction – 1956-1957: Gathering 1957 C-79-1-2 2345 System, Fort St. John, August 1957

BC 2009/ Construction – 1956-1957: Can. Bechtel staff 1957 C-79-1-3 to C- 2346-2347 at Station #1, (l-r): Ed Polloway, Tom 79-1-4 Arnold, Jack Pickell, Red Shannon (Westcoast), George Pickell, August 1957

BC 2009/ Construction – 1956-1957: Can. Bechtel staff 1957 C-79-2-1 2348 at Station #1, (l-r): Ed Polloway, Ernest Townsend, Jack Pickell, Bill Ruffo, and George Pickell, August 1957

56 BC 2009/ Construction – 1956-1957: Pacific 1957 C-79-2-2 2349 Petroleums Building, Fort St. John, August 1957

BC 2009/ Construction – 1956-1957: Span at Bijou 1957 C-79-2-3 to C- 2350-2351 Creek, Pine Pass, August 1957 79-2-4

BC 2009/ Construction – 1956-1957: [Welding pipes] [ca. 1956] C-80-1 1770

BC 2009/ Construction – 1956-1957: Hot Pass Welders [1957] C-80-2 2352 at Savona, August 1957

BC 2009/ Construction – 1956-1957: Cleland-Kent 1956-1957 C-81-1-1 to 2353-2529 (Western) Ltd. Photographs taken during C-96-2-1 construction of the Westcoast transmission (Series 1687) Company Limited mainline in 1956 and 1957

BC 2009/ Construction – 1956-1957: Cleland-Kent 1956-1957 C-97-1-1 to 2530-2587 (Western) Ltd. Photographs taken during C-101-2-4 construction of the Westcoast transmission (Series 1688) Company Limited mainline in 1956 and 1957

BC 2009/ Construction – 1956-1957: Cleland-Kent 1956-1957 C-102-1-1 to 2588-2707 (Western) Ltd. Photographs taken during C-120-1-4 construction of the Westcoast transmission (Series 1743) Company Limited mainline in 1956 and 1957

BC 2009/ Construction – 1956-1957: Cleland-Kent 1956-1957 C-121-1-1 to 2708-2939 (Western) Ltd. Photographs taken during C-132-2-6 construction of the Westcoast transmission (Series 1787) Company Limited mainline in 1956 and 1957

BC 2009/ Construction – 1956-1957: Parsnip River 1957 C-132-1-1 to 2840-2847 Camp, approaching Pine Pass, July 16, 1957 C-132-2-4

BC 2009/ Construction – 1956-1957: Aerial Span over 1957 C-133-1-1 to 2848-2849 Ralston Creek, August 1957 C-133-1-2

BC 2009/ Construction – 1956-1957: Making a tie-in in 1957 C-133-1-3 to 2850-2851 Pine Pass, August 1957 C-133-1-4

BC 2009/ Construction – 1956-1957: Cleaning out 1957 C-133-2-1 2852 ditch where slides occurred, Pine Pass, August 1957

57 BC 2009/ Construction – 1956-1957: Aerial Span over 1957 C-133-2-2 to 2853-2855 Ralston Creek, August 1957 C-133-2-4

BC 2009/ Construction – 1956-1957: Scrubber at 1957 C-135-1-1 to 2856-2857 Station #5, Savona, August 1957 C-135-1-2

BC 2009/ Construction – 1956-1957: Tie-in at Savona, 1957 C-135-1-3 to 2858-2861 August 1957 C-135-2-2

BC 2009/ Construction – 1956-1957: Peace River 1957 C-135-2-3 2862 Aerial Crossing, August 1957

BC 2009/ Construction – 1956-1957: Thompson River 1957 C-134-1-1 to 2863-2864 Crossing, August 1957 C-134-1-2

BC 2009/ Construction – 1956-1957: Station #5, 1957 C-134-1-3 2865 Savona, August 1957

BC 2009/ Construction – 1956-1957: Herb Miller at 1957 C-134-1-4 to 2866-2867 Savona, August 1957 C-134-2-1

BC 2009/ Construction – 1956-1957: Chuck Lester and 1957 C-134-2-2 2868 Russ Kransfelder at Savona, August 1957

BC 2009/ Construction – 1956-1957: Hot Pass Welders 1957 C-134-2-3 to 2869-2870 at Savona, August 1957 C-134-2-4

BC 2009/821 Construction – [Pipeline construction] (1985 1985 CAR-7-1 Annual Report)

BC 2009/493 Construction – 1985 Annual Report [1985] CAR-14-1 to -494 14-2

BC 2009/ Construction – 1985 Annual Report: 1985 CAR-19-2 1769 [Lowering of pipes]

BC 2009/458 Construction – Chetwynd Extension: [1970] CCE-1-2, –460 Clearing beside Alaska Highway 2-2, 5-1

BC 2009/461 Construction – Chetwynd Extension [1970] CCE-8-1

BC 2009/462 Construction – Chetwynd Extension: [1970] CCE-8-2 Blasting of a 1,200 foot-long trench beneath the Reace River

BC 2009/464 Construction – Chetwynd Extension [1970] CCE-11-1, 12- -469 1, 16-1, 17-2, 19-1, 19-2

BC 2009/463 Construction – Chetwynd Extension: [Men [1970] CCE-22-1 laying pipes]

58 BC 2009/470 Construction – Chetwynd Extension: [Men [1970] CCE-24-1 laying pipes]

BC 2009/471 Construction – Chetwynd Extension: [Men [1970] CCE-24-2, -474 welding pipes] 26-1 to 26-2, 30-1

BC 2009/475 Construction – Chetwynd Extension: [Men [1970] CCE-30-2 to -477 moving pipes] 33-1

BC 2009/478 Construction – Chetwynd Extension: [Men [1970] CCE-33-2 laying pipes]

BC 2009/479 Construction – Chetwynd Extension: [Men [1970] CCE-37-1 to -480 moving pipes] 37-2

BC 2009/481 Construction – Chetwynd Extension: [1970] CCE-41-1 to -482 [Clearing land] 41-2

BC 2009/483 Construction – Chetwynd Extension: [Pipes [1970] CCE-47-1 and machinery]

BC 2009/484 Construction – Chetwynd Extension: [Men [1970] CCE-47-2 to -485 laying pipes] 48-1

BC 2009/486 Construction – Chetwynd Extension: [Man [1970] CCE-48-2 preparing pipes]

BC 2009/487 Construction – Chetwynd Extension: [Men [1970] CCE-54-1 surveying bottom of trench]

BC 2009/488 Construction – Chetwynd Extension: [River 1970 CCE-54-2 crossings]

BC 2009/489 Construction – Chetwynd Extension 1970 CCE-55-1 to -492 56-2

BC 2009/867 Construction – Coat and Wrap Machine: 1956 CCW-1-1 Taking equipment across highway in the Fraser Valley, May 1956

BC 2009/868 Construction – Coat and Wrap Machine: 1956 CCW-1-2 Clean and prime working section between Angels Peak and Boulder Mountain, looking upstream, July 27, 1956

BC 2009/869 Construction – Coat and Wrap Machine: [195-] CCW-2-1 [Crew at work]

59 BC 2009/870 Construction – Coat and Wrap Machine: [195-] CCW-2-2 Preheater (foreground) used during cold weather before the coating and wrapping take place

BC 2009/865 Construction – Coat and Wrap Machine: [195-] CCW-3-1 to -866 [Crew at work] 3-2

BC 2009/871 Construction – Coat and Wrap Machine: [195-] CCW-4-1 [Preheater used during cold weather before the coating and wrapping take place]

BC 2009/872 Construction – Coat and Wrap Machine: 1955 CCW-4-2 Cleaning machine and coat and wrap near southern end of the WCT 30” gas line, October 28, 1955

BC 2009/873 Construction – Coat and Wrap Machine [195-] CCW-5-1

BC 2009/874 Construction – Coat and Wrap Machine: 1956 CCW-5-2 Cleaning and priming, north of Tolmie Road, Chilliwack, Sumas Prairie, April 20, 1956

BC 2009/875 Construction – Coat and Wrap Machine: [195-] CCW-6-1 [Crew at work]

BC 2009/876 Construction – Coat and Wrap Machine [195-] CCW-6-2 to -877 7-1

BC 2009/878 Construction – Coat and Wrap Machine: [195-] CCW-7-2 to -882 [Crew at work] 9-1, 10-2

BC 2009/883 Construction – Laquer-like appearance [195-] CCW-11-1 distinguishes pipe which has been cleaned by knives and wire brushes and coated with primer, all in one operation

BC 2009/884 Construction – Coat and Wrap Machine: [195-] CCW-11-2 [Crew at work]

BC 2009/885 Construction – Coat and Wrap Machine: [195-] CCW-12-1 Pine Pass Area

BC 2009/886 Construction – Coat and Wrap Machine: [195-] CCW-12-2 Mile Post Nine, looking north

BC 2009/887 Construction – Coat and Wrap Machine: [195-] CCW-13-1 Looking south toward dope operations, M.P. 449

60 BC 2009/888 Construction – Coat and Wrap Machine: [195-] CCW-13-2 [Crew at work]

BC 2009/889 Construction – Coat and Wrap Machine: [195-] CCW-14-1 [Crew at work with] Cleaning machine

BC 2009/890 Construction – Coat and Wrap Machine: [195-] CCW-14-2 [Crew at work]

BC 2009/891 Construction – Coat and Wrap Machine: [195-] CCW-15-1 Preheater (foreground) used during cold weather before the coating and wrapping take place

BC 2009/892 Construction – Coat and Wrap Machine: [1956] CCW-15-2 Preheating, clean and prime, M.P. 42

BC 2009/893 Construction – Coat and Wrap Machine: 1956 CCW-16-1 Preheating pipe, M.P. 42, November 23, 1956

BC 2009/894 Construction – Coat and Wrap Machine: 1956 CCW-16-2 Cleaning and priming, north of Tolmie Rd., Chilliwack, and Sumas Prairie

BC 2009/895 Construction – Coat and Wrap Machine: [195-] CCW-17-1 to -904 [Crew at work] 21-2

BC 2009/905 Construction – Coat and Wrap Machine: [1956] CCW-22-1 to -906 [Crew at work in the Fraser Valley] 22-2

BC 2009/907 Construction – Coat and Wrap Machine: 1956 CCW-23-1 Coating and wrapping just south of Tolmie Rd., Sumas Prairie, Chilliwack, B.C., April 20, 1956

BC 2009/908 Construction – Coat and Wrap Machine: 1955 CCW-23-2 Adjusting coat and wrap machine for the “kick off” run on WCT 36” line near Huntingdon, B.C., October 26, 1955

BC 2009/909 Construction – Coat and Wrap Machine: 1956 CCW-24-1 Clean and prime north of Tolmie Rd., Sumas Prairie, Chilliwack, April 20, 1956

BC 2009/910 Construction – Coat and Wrap Machine: 1956 CCW-22-1, -912 Fraser Valley, near Chilliwack, B.C. 25-1 to 25-2

BC 2009/913 Construction – Coat and Wrap Machine [195-] CCW-26-1

61 BC 2009/914 Construction – Coat and Wrap Machine [195-] CCW-26-2 [crew at work in the Fraser Valley]

BC 2009/915 Construction – Coat and Wrap Machine: [195-?] CCW-27-1-1 (neg) [Crew at work]

BC 2009/916 Construction – Coat and Wrap Machine: [195-?] CCW-27-1-2 (neg) [Crew at work]

BC 2009/917 Construction – Coat and Wrap Machine: [196-?] CCW-27-1-3 -918 [Crew at work] to 27-1-4

BC 2009/919 Construction – Coat and Wrap Machine: [195-] CCW-27-2-1 [Crew at work]

BC 2009/920 Construction – Coat and Wrap Machine [197-] CCW-28-1-1

BC 2009/921 Construction – Coat and Wrap Machine: [195-?] CCW-28-1-2 [Crew at work]

BC 2009/922 Construction – Coat and Wrap Machine: [195-] CCW-28-1-3 -928 [Crew at work] to 28-2-3

BC 2009/929 Construction – Coat and Wrap Machine: [ca. 1980] CCW-29-1 [Crew at work]

BC 2009/ Construction – Historic: Clearing forest [1956] CH-1-1 to 1078 - 1083 3-2

BC 2009/ Construction – Historic: Clearing forest, [1956] CH-4-1 1084 main trunk of the B.C. line near Charlie Lake

BC 2009/ Construction – Historic: Brush clearing and 1956 CH-4-2 1085 burning along the right-of-way in the Fraser Valley near Hope, B.C., February 1956

BC 2009/ Construction – Historic: Grading near M.P. 6 [1956] CH-5-1 1086

BC 2009/ Construction – Historic: Clearing forest at [1956] CH-5-2 1087 M.P. 100.0

BC 2009/ Construction – Historic: Clearing forest at [1956] CH-6-1 1088 M.P. 85.0

BC 2009/ Construction – Historic: [View of cleared [1956] CH-6-2 to 1089 - 1091 area covered in snow] 7-2

BC 2009/ Construction – Historic: Clearing forest [1956] CH-8-1 to 1092 - 1093 8-2

62 BC 2009/ Construction – Historic: Clearing forest, 1956 CH-9-1 1094 Approaching Pine Pass area, September 1956

BC 2009/ Construction – Historic: Clearing forest [1956] CH-9-2 to 1095 - 1096 10-1

BC 2009/ Construction – Historic: Clearing forest, [1956] CH-10-2 1097 ditching through swamp, M.P. 40, November 23, 1956

BC 2009/ Construction – Historic: Clearing forest, [1956] CH-11-1 to 1098 - 1099 grading looking south, M.P. 117.7 11-2

BC 2009/ Construction – Historic: Clearing forest, [1956] CH-12-1 to 1100 - 1101 grading M.P. 59 12-2

BC 2009/ Construction – Historic: Clearing forest [1956] CH-13-1 to 1102 - 1103 13-2

BC 2009/ Construction – Historic: Clearing forest: [1956] CH-14-1 1104 Right-of-way at west approach to Septinus Creek, M.P. 14

BC 2009/ Construction – Historic: Clearing forest [1956] CH-14-2 to 1105 - 1106 15-1

BC 2009/ Construction – Historic: Clearing forest, 1956 CH-15-2 1107 cleared and graded right-of-way near Merritt, B.C., May 1956

BC 2009/ Construction – Historic: Clearing forest, [1956] CH-16-2 1108 completed Pine River crossing, M.P. 31.5, looking downstream

BC 2009/816 Construction – Historic: Looking South into 1955 CH-17-1 Pine River Valley

BC 2009/ Construction – Historic: Ditcher [1956] CH-17-2 to 1109 - 1111 18-2

BC 2009/ Construction – Historic: Ditcher [197-?] CH-19-1 1112

BC 2009/ Construction – Historic: Crew loading 1956 CH-19-2, 1113, 1115, ditcher on Quesnel River, July 8, 1956 20-2 1757

BC 2009/ Construction – Historic: Ditcher crossing the 1956 CH-20-1 1114 Quesnel River, July 8, 1956

63 BC 2009/ Construction – Historic: Backhoe operations, [1956] CH-21-1 1116 looking North, M.P. 523

BC 2009/ Construction – Historic: Ditching machine [1956] CH-21-2 1117 looking East, vicinity M.P. 523

BC 2009/ Construction – Historic: Ditching machine [1956] CH-22-1 1118 looking South, vicinity M.P. 523

BC 2009/ Construction – Historic: Ditching machine [1956] CH-22-2 1119 looking South along ROW vicinity M.P. 523

BC 2009/ Construction – Historic: Looking North in [1956] CH-23-1 1120 ditch near M.P. 523

BC 2009/ Construction – Historic: Rooter making 1956 CH-23-2 1121 preliminary cut in rocky ground in preparation for ditching machine, Merritt, B.C., May 1956

BC 2009/ Construction – Historic: Ditching looking [1956] CH-24-1 1122 South along ROW vicinity M.P. 113.6

BC 2009/ Construction – Historic: Backfilling, M.P. [1956] CH-24-2 1123 28.5

BC 2009/ Construction – Historic: Ditcher [1956] CH-25-1 1124, 1756

BC 2009/ Construction – Historic: Looking South at a 1957 CH-25-2 1125 point 600’ North of the Nicola River, Pipeline M.P. 528.7, January 12, 1957

BC 2009/ Construction – Historic: Ditcher [1956] CH-26-1 1126

BC 2009/ Construction – Historic: Pipe preparation for 1955 CH-26-2 1127 welding, boring in the rain for a road crossing near Huntingdon, B.C. on the international border, October 26, 1955

BC 2009/ Construction – Historic: Pipe preparation for [ca. 1956] CH-27-1 1128 welding

BC 2009/ Construction – Historic: Pipe preparation for 1957 CH-27-2 1129 welding, looking North along right-of-way, M.P. 528.5, January 12, 1957

64 BC 2009/ Construction – Historic: Pipe preparation for 1957 CH-28-1 1130 welding, looking North along right-of-way, M.P. 528.5, January 12, 1957

BC 2009/ Construction – Historic: Pipe preparation for [ca. 1956] CH-28-2 to 1131 - 1134 welding 30-1

BC 2009/ Construction – Historic: Pipe buffing gang 1955 CH-30-2 1135 near “kick-off” at Huntington, B.C. on the international border, October 26, 1955

BC 2009/ Construction – Historic: Pipe preparation for [ca. 1956] CH-31-1 1136 welding

BC 2009/ Construction – Historic: Backhoe excavating 1955 CH-31-2 1137 for road crossing near Huntingdon, October 26, 1955

BC 2009/ Construction – Historic: Pipe preparation for [ca. 1956] CH-32-1 to 1138 - 1139 welding 32-2

BC 2009/ Construction – Historic: [Backhoe [ca. 1956] CH-33-1 1140 excavating]

BC 2009/ Construction – Historic: Pipe preparation for [ca. 1956] CH-33-2 1141 welding

BC 2009/ Construction – Historic: Ditching machine at 1956 CH-34-1 1142 work near Quesnel, B.C., July 1956

BC 2009/ Construction – Historic: Pipe preparation for [ca. 1956] CH-34-2 1143 welding

BC 2009/ Construction – Historic: [Bird’s eye view of [ca. 1956] CH-35-1 1144 construction area]

BC 2009/ Construction – Historic: Pipe preparation for [ca. 1956] CH-35-2 1145 welding

BC 2009/ Construction – Historic: Pipe preparation for [ca. 1956] CH-36-1 1146 welding, receiving scraper assembly, 18” ft. St. John line

BC 2009/ Construction – Historic: Pipe preparation for [ca. 1956] CH-36-2 1147 welding, installing construction pig

BC 2009/ Construction – Historic: Lowering pipes [ca. 1956] CH-37-1 1758

BC 2009/ Construction – Historic: Pipe preparation for [ca. 1956] CH-37-1, 1148 - 1150 welding 38-1, 39-1

65 BC 2009/ Construction – Historic: Lowering in of [ca. 1956] CH-38-2 1764 pipes

BC 2009/ Construction – Historic: Joined sections of [ca. 1956] CH-40-1 1151 pipe; welding operations, Pine River area, Mile 28, east of Alaska Highway, Taylor to Dawson Creek pipeline

BC 2009/ Construction – Historic: Joined sections of 1955 CH-40-2 1152 pipe; firing line near Huntingdon, B.C., October 26, 1955

BC 2009/ Construction – Historic: Joined sections of 1955 CH-41-1 1153 pipe; lining-up and welding pipe section near “kick-off” at Huntingdon, B.C., October 26, 1955

BC 2009/ Construction – Historic: Joined sections of 1956 CH-41-2 1154 pipe; pipe string ready for lowering in; well points beside pipe are for removing subsurface water, May 1956

BC 2009/ Construction – Historic: Joined sections of [ca. 1956] CH-42-1 to 1155 - 1156 pipe 42-2

BC 2009/ Construction – Historic: Joined sections of 1955 CH-43-1 1157 pipe, “kick-off”, October 26, 1955

BC 2009/ Construction – Historic: Joined sections of 1967 CH-43-2 1158 pipe, gas line, Lulu Island to Sea Island, February 1967

BC 2009/815 Construction – Historic: Man using detector 1956 CH-44-1 to check for flaws in wrapping, May 1956

BC 2009/ Construction – Historic: Joined sections of [ca. 1956] CH-44-2 1159 pipe

BC 2009/ Construction – Historic: Ditch digging [ca. 1956] CH-45-1 1160

BC 2009/ Construction – Historic: Ditch digging, [ca. 1956] CH-45-2 1766 [Fraser Valley]

BC 2009/ Construction – Historic: Ditch digging, line- 1955 CH-46-1 1161 up gang going through wet and muddy terrain near Huntingdon, B.C., October 26, 1955

66 BC 2009/ Construction – Historic: Ditch digging, [ca.1956] CH-46-2, 47-1 1162 - 1163 [Fraser Valley]

BC 2009/ Construction – Historic: Side boom tractors 1957 CH-47-2 1164 at work setting in Westcoast mainline 30” pipe in 1957

BC 2009/ Construction – Historic: Lowering in of [ca. 1957?] CH-47-2 1761 pipes, north-east of Prince George

BC 2009/ Construction – Historic: Laying pipeline into [ca.1956] CH-48-1 to 1165 - 1167 a ditch 49-2

BC 2009/ Construction – Historic: Lowering pipe into 1956 CH-50-2 1168 ditch, Quesnel, B.C., July 1956

BC 2009/ Construction – Historic: Laying pipeline into [ca.1956] CH-51-1 1169 a ditch

BC 2009/ Construction – Historic: Laying pipeline into [ca.1956] CH-51-2 1170 a ditch, 30” pipeline being laid in Quesnel, B.C.

BC 2009/ Construction – Historic: Laying pipeline into [ca.1956] CH-52-1 1171 a ditch

BC 2009/ Construction – Historic: Laying pipeline into [ca.1956] CH-52-2 1172 a ditch, Mile Post 13, looking North

BC 2009/ Construction – Historic: Laying pipeline into [ca.1956] CH-53-1 1173 - 1174 a ditch

BC 2009/ Construction – Historic: Laying pipeline into [ca.1956] CH-54-1 1175 a ditch, ditching, M.P. 69

BC 2009/ Construction – Historic: Firing line at work 1956 CH-54-2(a) 1176 near Quesnel, B.C., July 1956

BC 2009/ Construction – Historic: Welding, north of 1956 CH-54-2(b) 1177 Quesnel, B.C., July 1956

BC 2009/ Construction – Historic: Lowering pipe into 1956 CH-55-1(a) 1178 ditch through a small stream near Quesnel, B.C., July 1956

BC 2009/ Construction – Historic: Lowering pipe into 1956 CH-55-1(b), 1179 - 1180 ditch through a small stream near Quesnel, 55-2 B.C., July 1956

BC 2009/ Construction – Historic: Looking North 1956 CH-56-1 1181 along ROW vicinity M.P. 524

67 BC 2009/ Construction – Historic: Closing final gaps in 1957 CH-56-2 1182 the Westcoast Transmission pipeline through British Columbia in Prince George, June 28, 1957

BC 2009/ Construction – Historic: Lowering pipe into [ca. 1956] CH-57-2 to 1183 - 1184 ditch 58-1

BC 2009/ Construction – Historic: Construction up a [ca. 1956] CH-58-2 1185 hill, Mile Post 9, looking south

BC 2009/ Construction – Historic: Construction up a [ca. 1956] CH-59-1 to 1186 - 1188 hill 60-1

BC 2009/ Construction – Historic: Construction up a 1956 CH-60-2 to 1189 - 1190 hill, pipe in ditch dug over Cottonwood 61-1 Canyon hill near Quesnel, B.C., July 1956

BC 2009/ Construction – Historic: Construction up a [ca. 1956] CH-61-2 1191 hill

BC 2009/ Construction – Historic: Construction up a [ca. 1956] CH-62-1 1192 hill, looking south at Loon Lake, M.P. 452

BC 2009/ Construction – Historic: Construction up a [ca. 1956] CH-62-2 1193 hill

BC 2009/ Construction – Historic: Construction up a [ca. 1956] CH-63-1 1194 hill, Pine River area

BC 2009/ Construction – Historic: [Construction [195-] CH-63-1 1750 uphill]

BC 2009/ Construction – Historic: Construction up a [ca. 1956] CH-63-2 1195 hill

BC 2009/ Construction – Historic: Construction up a [ca. 1956] CH-64-1 1196 hill, Cottonwood Canyon

BC 2009/ Construction – Historic: Cottonwood Canyon [ca. 1956] CH-64-1 1765

BC 2009/ Construction – Historic: Construction up a 1956 CH-64-2 1197 hill, pipe gang seen from the top of Boulder Mountain, M.P. 609.3, or Ruby Creek jump- off looking upstream, July 27, 1956

BC 2009/ Construction – Historic: Construction up a [ca. 1956] CH-65-1 1198 hill

68 BC 2009/820 Construction – Historic: [Pipeline [1977] CH-65-2 Construction, Grizzly Valley]

BC 2009/ Construction – Historic: Construction up a 1956 CH-66-1 1199 hill, padding of ditch and pipe at the foot of Agassiz jump off, M.P. 613.3, looking downstream, July 27, 1956

BC 2009/ Construction – Historic: Construction down 1956 CH-66-2 1200 a hill, View of top of Angels Peak, looking downstream, July 27, 1956

BC 2009/ Construction – Historic: Construction down [ca. 1956] CH-67-2 to 1201 - 1203 a hill 69-1

BC 2009/ Construction – Historic: Construction down 1956 CH-69-2 1204 a hill, pipe laying in hilly terrain near Quesnel, B.C., July 1956

BC 2009/ Construction – Historic: Construction down 1956 CH-70-1 1205 a hill, Stoney Creek, looking South, early September 1956

BC 2009/ Construction – Historic: Construction down [ca. 1956] CH-70-2 to 1206 - 1208 a hill 71-1(b)

BC 2009/ Construction – Historic: Construction down [ca. 1956] CH-71-2 1209 a hill, welding M.P. 68

BC 2009/ Construction – Historic: Construction down [ca. 1956] CH-72-1 1210 a hill

BC 2009/ Construction – Historic: Construction down [ca. 1956] CH-72-2 1211 a hill, 4” Mile 25 East Alaska Highway, Taylor to Dawson Creek Pipeline

BC 2009/ Construction – Historic: Construction down [ca. 1956] CH-73-2 1212 a hill

BC 2009/ Construction – Historic: Construction down 1956 CH-74-1 1213 a hill, lowering section of pipe down slope of Cottonwood Canyon, where it will be tied in to pipe at bottom, July 1956

BC 2009/ Construction – Historic: Construction down 1956 CH-74-2 1214 a hill, Cottonwood Canyon, July 1956

BC 2009/ Construction – Historic: Construction down 1956 CH-75-1 1215 a hill, Construction down a hill, Cottonwood Canyon, July 1956

69 BC 2009/ Construction – Historic: Construction down 1956 CH-75-2 1216 a hill, lowering section of pipe down slope of Cottonwood Canyon, where it will be tied in to pipe at bottom, July 1956

BC 2009/ Construction – Historic: Construction down [ca. 1956] CH-76-1 1217 a hill

BC 2009/ Construction – Historic: Water running [ca. 1956] CH-76-2 1218 through welded pipeline

BC 2009/ Construction – Historic: Ditching, M.P. 95 [ca. 1956] CH-77-1 1219

BC 2009/ Construction – Historic: Water running 1957 CH-77-2 1220 through welded pipeline, looking south at Nicola River, M.P. 528.8, January 12, 1957

BC 2009/794 Construction – Historic: Coquihalla river 1956 CH-78-1 crossing near Hope, B.C., February 1956

BC 2009/ Construction – Historic: Water running 1956 CH-78-2 1221 through welded pipeline, 30” pipe at Dead Man’s Creek, near Savona, B.C., August 1956

BC 2009/ Construction – Historic: Water running [ca. 1956] CH-79-1 1222 through welded pipeline, Coquihalla

BC 2009/ Construction – Historic: Water running [ca. 1956] CH-79-2 to 1223 - 1226 through welded pipeline 81-1

BC 2009/ Construction – Historic: Water running [ca. 1956] CH-81-2 1227 through welded pipeline, Coquihalla River, looking downstream

BC 2009/ Construction – Historic: Water running 1956 CH-82-2 to 1228 - 1231 through welded pipeline, [Coquihalla River 84-1 crossing near Hope, B.C., February 1956]

BC 2009/ Construction – Historic: Water running [ca. 1956] CH-84-2 1232 through welded pipeline

BC 2009/ Construction – Historic: Ditching, 1956 CH-85-1 1233 Cottonwood Canyon, July 23, 1956

BC 2009/ Construction – Historic: Water running [ca. 1956] CH-85-2 to 1234 - 1236 through welded pipeline 86-2

BC 2009/ Construction – Historic: Water running [ca. 1956] CH-87-1 1237 through welded pipeline, 30” pipe weighted

70 for river crossing

BC 2009/ Construction – Historic: Water running 1960 CH-87-2 1238 through welded pipeline, December 1960

BC 2009/ Construction – Historic: Water running 1956 CH-88-1 1239 through welded pipeline, September 1956

BC 2009/ Construction – Historic: Preparations and [ca. 1956] CH-88-2 1240 lowering of pipe into ditch, M.P. 10, looking North

BC 2009/ Construction – Historic: Preparations and [ca. 1956] CH-89-1 to 1241 - 1242 lowering of pipe into ditch 89-2

BC 2009/ Construction – Historic: Preparations and 1956 CH-90-1 1243 lowering of pipe into ditch, Firing line at work near Quesnel, B.C., July 1956

BC 2009/ Construction – Historic: Preparations and [ca. 1956] CH-91-1 to 1244 – 1245 lowering of pipe into ditch 91-2

BC 2009/ Construction – Historic: Preparations and 1955 CH-92-1 1246 lowering of pipe into ditch; boring for a road crossing near Huntingdon, B.C., October 26, 1955

BC 2009/ Construction – Historic: Preparations and [ca. 1956] CH-92-2 to 1247 - 1252 lowering of pipe into ditch 95-1

BC 2009/ Construction – Historic: Preparations and 1956 CH-95-2 1253 lowering of pipe into ditch, lowering in pipe in the Fraser Valley, near Chilliwack, B.C., May 1956

BC 2009/ Construction – Historic: Preparations and [ca. 1956] CH-96-1 1254 lowering of pipe into ditch

BC 2009/ Construction – Historic: Preparations and 1956 CH-96-2 to 1255 - 1256 lowering of pipe into ditch, lowering in pipe 97-1 in the Fraser Valley, near Chilliwack, B.C., May 1956

BC 2009/ Construction – Historic: Preparations and 1956 CH-97-2 to 1257-1261 lowering of pipe into ditch, positioning CH-99-2 swamp weights on pipe in the Fraser Valley, near Chilliwack, B.C., May 1956

BC 2009/ Construction – Historic: Preparations and [ca. 1956] CH-100-1 to 1262 - 1266 lowering of pipe into ditch 102-1

71 BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-102-2 to 1267 - 1268 workers at construction site 103-1

BC 2009/ Construction – Historic: Machinery and 1956 CH-103-2 1269 workers at construction site, checking the depth of pipe in Pine River Pass, B.C., August 1956

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-104-1 to 1270 - 1271 workers at construction site 104-2

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-105-1 1272 workers at construction site, 2.5 miles north of

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-105-2 1273 workers at construction site

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-106-1 1274 workers at construction site, [M.P. 34]

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-106-2 1275 workers at construction site, kick off

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-107-1 1276 workers at construction site, gathering system, R/Wcamp, August [1956?]

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-107-2 1277 workers at construction site [camp]

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-108-1 1278 workers at construction site

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-108-2 1279 workers at construction site, gate valve, M.P. 31

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-109-1 to 1280 - 1285 workers at construction site 111-2

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-112-1 to 1286 - 1287 workers at construction site, kick off 112-2

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-113-1 1288 workers at construction site

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-113-2 1289 workers at construction site, camp at Pine Valley, M.P. 72

72 BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-114-1 to 1290 - 1291 workers at construction site 114-2

BC 2009/ Construction – Historic: Machinery and 1956 CH-115-1 1292 workers at construction site, automatic welding machine at Kersley double jointing plant near Quesnel, May 1956

BC 2009/ Construction – Historic: Machinery and 1956 CH-115-2 1293 workers at construction site, double jointing plant at Kersley, B.C.; 40’ lengths of pipe are welded together to save time on the right of way, May 1956

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-116-1 to 1294 - 1295 workers at construction site 116-2

BC 2009/ Construction – Historic: Machinery and 1956 CH-117-1 1296 workers at construction site, drilling for blasting on right-of-way near Hope, B.C., February 1956

BC 2009/ Construction – Historic: Machinery and 1957 CH-117-2 1297 workers at construction site, looking north at C.P.R. crossing, pipeline M.P. 528.3, near Merritt, B.C., January 12, 1957

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-118-1 1298 workers at construction site

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-118-2 1299 workers at construction site, [?] valve

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-119-1 to 1300 -1303 workers at construction site 121-1

1302 negs. Construction – Historic: Machinery and [ca. 1956] CH-124 workers at construction site [2 negatives]

1304 Construction – Historic: Machinery and 1956 CH-121-2 workers at construction site, loading pipe onto stringing trucks near Hixon, August 1956

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-122-1 to 1305 - 1306 workers at construction site, clean and purge 122-2

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-123-1-1 1307 workers at construction site, Quesnel

73 BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-123-1-2 1308 workers at construction site, Cottonwood Canyon, ditching clam and backhoe

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-123-1-3 1309 workers at construction site

BC 2009/ Construction – Historic [ca. 1956] CH-123-2-2 1310

BC 2009/ Construction – Historic: [Clearing bush] [ca. 1956] CH-125-1 1311

BC 2009/ Construction – Historic: [Crew clearing [ca. 1956] CH-125-2 to 1312 - 1315 bush] 127-1

BC 2009/ Construction – Historic: [Crew digging [ca. 1956] CH-127-2 to 1316 - 1317 ditch] 128-1

BC 2009/ Construction – Historic: Trenching in winter [ca. 1956] CH-128-2 1318 weather for Westcoast’s gathering line

BC 2009/ Construction – Historic: [Trenching in winter [ca. 1956] CH-129-1 1319 weather]

BC 2009/ Construction – Historic: Lowering side [ca. 1956] CH-129-2 to 1320-1345 booms, pipeline transport, preparation and CH-139-2, connection CH-141-1-1 to CH-143-1-3

BC 2009/ Construction – Historic: Machinery and [ca. 1956] CH-120-2 1762 workers at construction site

BC 2009/ Construction – Historic: [Welding pipes] [ca. 1957] CH-135-1 1755

BC 2009/ Construction – Historic: [View of camp] [ca. 1956] CH-140-1 1347

BC 2009/ Construction – Historic: Ditch digging, [ca. 1956] CH-142-2 1768 [Fraser Valley]

BC 2009/ Construction – Historic: Lowering side [ca. 1956] CH-144 1346 booms, pipeline transport, preparation and (a-b) (negs) connection [2 negatives]

BC 2009/312 Looping – Coquihalla: [Construction] 1979 CL-6-1 to -313 6-2

BC 2009/314 Looping – Coquihalla: [Construction: 1979 CL-18-1 pipeline being lowered in to ditch]

74 BC 2009/315 Looping – Coquihalla: Westcoast 1979 CL-19-1 Transmission 36” main, in Northern British Columbia

BC 2009/ Construction – Misc.: Junior Sierra, Jan. – 1980 CM-1-1 to 2-2 1485 - 1488 Mar. 1980

BC 2009/ Construction – Misc.: Yoyo construction, 1969 CM-6-1-1 1489 showing yellowjacket that shattered in the extreme cold and fell off of pipe

BC 2009/ Construction – Misc.: Yoyo construction, 1969 CM-6-1-2 1490 upstream end, Y3 tie-in

BC 2009/ Construction – Misc.: Yoyo construction, 1969 CM-6-1-3 1491 breaking front to make road crossing at Y3

BC 2009/ Construction – Misc.: Yoyo construction, 1969 CM-6-1-4 1492 bell hole for tie-in at M.P. 36.9

BC 2009/ Construction – Misc.: Yoyo construction, ‘S’ 1969 CM-6-2-1 1493 bend for Y3 tie-in

BC 2009/ Construction – Misc.: Yoyo construction, 1969 CM-6-2-2 1494 road crossing for tie-in at Y3

BC 2009/ Construction – Misc.: Yoyo construction, 1969 CM-6-2-3 1495 upstream tie-in at Y3 valve

BC 2009/795 Construction – Misc.: Clearing right-of-way, 1965 CM-10-1 Coquihalla, August 31, 1965

BC 2009/ Construction – Misc.: Clearing right-of-way, 1979 CM-13-1 to 1496 - 1497 Coquihalla, June 26, 1979 13-2

BC 2009/ Construction – Misc.: Construction, 1964 1964 CM-17-1 to 1498 - 1503 20-2

BC 2009/ Construction – Misc.: Grading mountainside 1956 CM-30-1 1504 right-of-way in Pine Pass, B.C., August 1956

BC 2009/ Construction – Misc.: Bending machine in 1956 CM-30-2 to 1505 - 1507 Pine Pass, B.C., August 1956 32-2

BC 2009/790 Construction – Miscellaneous: River section 1956 CM-32-1 ready to be laid in bottom of Pine River, Pine Pass, B.C., August 1956

BC 2009/ Construction – Misc.: Dutton-Williams Bros. 1956 CM-33-1 to 1508 - 1509 construction camp in Pine Pass, August 1956 33-2

75 BC 2009/ Construction – Misc: Installation of flood 1974 CM-46-1-1 to 1510-1515 underwater crossing, March 1974 CM-46-2-2

BC 2009/ Construction – Misc: Amine contractors [195-] CM-51-1 1516

BC 2009/ Construction – Misc: Foremost vehicle [195-] CM-51-2, 1517 - 1518 54-1

BC 2009/ Construction – Misc: Valves and meters for [195-] CM-54-2 1519 controlling the flow of natural gas from a well

BC 2009/ Construction – Misc: Sending scrapper [195-] CM-67-1 to 1520 - 1521 assembly, 18” Fort St. John line 67-2

BC 2009/ Construction – Misc: 18” Fort St. John line, [195-] CM-68-1 1522 looking north from Taylor

BC 2009/1-4 Compressor Stations – Australian No. 5 [1967] CSA-3-1 to 4-2

BC 2009/5-7 Compressor Stations – Australian No. 5: Pad 1967 CSA-5-1 to preparation for Clarke engine, March 1967 6-1

BC 2009/8 Compressor Stations – Australian No. 5: [1967] CSA-6-2 Conduit in electrical equipment room

BC 2009/9- Compressor Stations – Australian No. 5 [1967] CSA-7-1 to 17 13-1

BC 2009/18 Compressor Stations – Australian No. 5: [1967] CSA-13-2 Electrical control room and generators

BC 2009/19 Compressor Stations – Australian No. 5: [1967] CSA-14-1 Coolers and pumps between two engines

BC 2009/20- Compressor Stations – Australian No. 5 [1967] CSA-14-2 to 27 18-1

BC 2009/28 Compressor Stations – Australian No. 5: [1967] CSA-18-2 Basement piping

BC 2009/497 Compressor Stations – Hope #8B [197-?] CSH-8-1, -498 10-1

BC 2009/515 Compressor Stations – Misc.: 150 Mile 1968 CSM-9-1 House, Stn. 6-A

76 BC 2009/516 Compressor Stations – Misc.: Azouzetta [ca. 1968] CSM-12-1 Lake, Station 2B

BC 2009/517 Compressor Stations – Misc. [ca. 1968] CSM-12-2

BC 2009/499 Compressor Stations – Hope #8B: Valve 1969 CSH-13-1 to -501 change out program, mainline shutdown 14-1

BC 2009/518 Compressor Stations – Misc: Summit Lake 1981 CSM-17-1 Compressor Stn. #4A, Cooper RR high efficiency turbines, May 21, 1981

BC 2009/519 Compressor Stations – Misc: Station 8A, 1969 CSM-23-1 to –520 Kingsvale, July 1969 23-2

BC 2009/521 Compressor Stations – Misc: Kingsvale 1969 CSM-25-1 Compressor Station #8A, July 1964

BC 2009/29- Compressor Stations -- McLeod Lake No. 3 [1957] CSML-1-1 to 31 2-1

BC 2009/32 Compressor Stations -- McLeod Lake No. 3: 1957 CSML-2-2 Looking into Northwest corner of Auxilliary area showing temporary heating system, January 31, 1957

BC 2009/33- Compressor Stations -- McLeod Lake No. 3, 1956 CSML-3-1 to 37 December 1, 1956 5-1

BC 2009/38 Compressor Stations -- McLeod Lake No. 3: 1956 CSML-5-2 Auxilliary area and firewall looking south- east, December 1, 1956

BC 2009/39 Compressor Stations -- McLeod Lake No. 3: 1956 CSML-6-1 General view of site looking north-west, December 1, 1956

BC 2009/40 Compressor Stations -- McLeod Lake No. 3: 1956 CSML-6-2 December 1, 1956 view of compressor room looking north

BC 2009/41- Compressor Stations -- McLeod Lake No. 3 [1956] CSML-7-1 to 44 8-2

BC 2009/45 Compressor Stations -- McLeod Lake No. 3: 1957 CSML-9-1 January 31, 1957, Looking north-east into compressor room area showing main compressor being moved into place and skidways

77 BC 2009/46 Compressor Stations -- McLeod Lake No. 3: 1957 CSML-9-2 January 31, 1957, View of power conduit runs and templates for “M.C.C.” in Auxilliary area electrical room

BC 2009/47 Compressor Stations -- McLeod Lake No. 3: 1957 CSML-10-1 January 31, 1957, General view of site looking south-west

BC 2009/48 Compressor Stations -- McLeod Lake No. 3 [1957] CSML-10-2 [Men working on equipment]

BC 2009/49- Compressor Stations -- McLeod Lake No. 3 [1957] CSML-12-1 to 62 31-2

BC 2009/175 Compression Stations – Rosedale #9: 1966 CSR-6-1 Construction, April 4, 1966

BC 2009/176 Compression Stations – Rosedale #9 [ca. 1967] CSR-10-1

BC 2009/177 Compression Stations – Rosedale #9: Valve 1969 CSR-12-1 after blow-down, condensation on the outside [in Pipeline News, June 1969]

BC 2009/178 Compression Stations – Rosedale #9: Gordie 1969 CSR-12-2 Clark working on small amount of pressure left in the closed off mainline after blow- down [in Pipeline News, June 1969]

BC 2009/179 Compression Stations – Rosedale #9: 1969 CSR-13-1 Blowdown, Rosedale, 1969, Valve change out

BC 2009/180 Compression Stations – Rosedale #9 [1969] CSR-13-2

BC 2009/181 Compression Stations – Rosedale #9: 1967 CSR-18-1 Interior, October 1967, featuring employee Rudy Dick

BC 2009/182 Compression Stations – Rosedale #9: 1967 CSR-19-1 Interior, October 1967, featuring employees Rudy Dick and Ken Charman

BC 2009/183 Compression Stations – Rosedale #9: 1967 CSR-19-2 [Equipment], October 1967

BC 2009/184 Compression Stations – Rosedale #9: 1967 CSR-20-1 Interior, October 1967

78 BC 2009/185 Compression Stations – Rosedale #9: 1967 CSR-20-2 Interior, October 1967, featuring employees Rudy Dick and Bob Merrell

BC 2009/186 Compression Stations – Rosedale #9, March 1967 CSR-21-1, -188 1967 25-1 to 25-2

BC 2009/189 Compression Stations – Rosedale #9: Blow- 1966 CSR-56-1 down and valve replacement, 8-4, July 4, 1966 [in Pipeline News, July 1966]

BC 2009/190 Compression Stations – Rosedale #9, Tie-in 1966 CSR-56-2

BC 2009/191 Compression Stations – Rosedale #9: Blow- 1966 CSR-57-1 down and valve replacement, 8-4, July 4, 1966 [in Pipeline News, July 1966]

BC 2009/192 Compression Stations – Rosedale #9 [in 1966 CSR-57-2 Pipeline News, July 1966]

BC 2009/502 Compressor Stations – Savona #7: [195-?] CSS-1-1 to -503 [Construction] 1-2

BC 2009/504 Compressor Stations – Savona #7 [195-?] CSS-1B-1

BC 2009/505 Compressor Stations – Savona #7 1968 CSS-8-1 -506

BC 2009/507 Compressor Stations – Savona #7: [ca. 1968] CSS-17-1 to -508 Machinery 17-2

BC 2009/509 Compressor Stations – Savona #7: Stacked 1967 CSS-18-2 to –510, 512 36” pipe at Savona during Westcoast 19-2 Transmission Company Limited’s expansion program, May 1967

BC 2009/511 Compressor Stations – Savona #7 [ca. 1968] CSS-26-1

BC 2009/513 Compressor Stations – Savona #7: [Tour of [ca. 1968] CSS-27-1 interior]

BC 2009/514 Compressor Stations – Savona #7: [Interior] [ca. 1968] CSS-27-2

BC 2009/316 Compressor Stations – Taylor #1: 1956 CST-1-1 to -318 [Construction], November 15, 1956 1-2, 3-1

BC 2009/319 Compressor Stations – Taylor #1: Taylor 1956 CST-3-2 Flats Warehouse, November 15, 1956

BC 2009/320 Compressor Stations – Taylor #1: 1956 CST-5-1 [Construction], November 15, 1956

79 BC 2009/321 Compressor Stations – Taylor #1: Grading [1956] CST-6-1 on 18” on top of Taylor Bluff looking South over Peace River

BC 2009/332 Compressor Stations – Taylor #1: 1956 CST-9-1 [Construction]

BC 2009/322 Compressor Stations – Taylor #1: [1956] CST-9-2 Foundation excavation for compressor station looking North

BC 2009/323 Compressor Stations – Taylor #1: (l-r): Cliff [1956] CST-11-1 Turner (P.N.W. Measurement), Lloyd Harleston, and P. Bouchard (B.C.E.)

BC 2009/324 Compressor Stations – Taylor #1: (l-r): R.C. [ca. 1956] CST-11-2 Appling, Cliff Turner (P.N.W. Measurement), R.D. Rickett’s pilot, Lloyd Harleston, D.R. Pflug, P. Bouchard (B.C.E.), and R.D. Ricketts (P.N.W.)

BC 2009/325 Compressor Stations – Taylor #1 [ca. 1957] CST-19-1

BC 2009/326 Compressor Stations – Taylor #1: [ca. 1957] CST-19-2 Compressor Station No. 1 and McMahon Plant at Taylor, B.C.

BC 2009/327 Compressor Stations – Taylor #1 [ca. 1956] CST-37-1

BC 2009/328 Compressor Stations – Taylor #1: [Interior [ca. 1957] CST-37-2 view, men discussing machinery]

BC 2009/329 Compressor Stations – Taylor #1: [Interior [ca. 1957] CST-38-1 view, man checking machinery]

BC 2009/330 Compressor Stations – Taylor #1: [Interior [ca. 1956] CST-38-2 view]

BC 2009/331 Compressor Stations – Taylor #1: [Interior [ca. 1980?] CST-50-1 view]

BC 2009/298 Compressor Stations – Unidentified stations, 1978 CSU-15-1-1 plants: Excess steam condenser, west side, winter 1978-1979

BC 2009/299 Compressor Stations – Unidentified stations, 1978 CSU-15-1-2 plants: 48” Line T-10, #2 Cond. to T-12; 48” Line T-12, Regen. blower to heater, winter 1978-1979

80 BC 2009/300 Compressor Stations – Unidentified stations, 1978 CSU-15-2-1 plants: Expansion Joint D-Line, winter 1978- 1979

BC 2009/301 Compressor Stations – Unidentified stations, 1978 CSU-15-2-2 plants: Boiler stack, winter 1978-1979

BC 2009/302 Compressor Stations – Unidentified stations, [ca. 1978] CSU-17-1-1 to -304 plants: [Aerial view of plant] 17-2-1

BC 2009/305 Compressor Stations – Unidentified stations, [ca. 1978] CSU-17-2-2, -306 plants 28-1

BC 2009/307 Compressor Stations – Unidentified stations, [198-?] CSU-28-2 plants

BC 2009/308 Compressor Stations – Unidentified stations, [196-?] CSU-30-1 to -309 plants: Station 3A 30-2

BC 2009/310 Compressor Stations – Unidentified stations, [ca. 1978?] CSU-54-1 to -311 plants 54-2

BC 2009/282 Compressor Stations – Willow Flats #2: 1963 CSW-21-1 to -283 [Construction], August 21, 1963 21-2

BC 2009/284 Compressor Stations – Willow Flats #2: [1963] CSW-24-1 [Bird’s eye view]

BC 2009/285 Compressor Stations – Willow Flats #2: [1963] CSW-24-2 Future site of Stn. No. 2, Little Prairie, with pig catcher and launcher, and mainline block valve in the foreground

BC 2009/286 Compressor Stations – Willow Flats #2: 1963 CSW-31-2 [Inside view, various gauges and controls], October 15, 1963

BC 2009/287 Compressor Stations – Willow Flats #2: 1963 CSW-32-2 [Inside view], October 15, 1963

BC 2009/288 Compressor Stations – Willow Flats #2: 1963 CSW-34-1 [Inside view], October 15, 1963

BC 2009/289 Compressor Stations – Willow Flats #2: 1963 CSW-34-2, -292 October 15, 1963 36-1 to 37-1

BC 2009/293 Compressor Stations – Willow Flats #2 1992 CSW-38-1

BC 2009/525 Construction – Welding [195-?] CW-10-1

BC 2009/526 Construction – Welding [ca. 1970] CW-10-2

81 BC 2009/527 Construction – Welding [196-?] CW-11-2

BC 2009/528 Construction – Welding: At top of Boulder 1956 CW-12-1 Mountain at Ruby Creek jump off, looking upstream, July 27, 1956

BC 2009/529 Construction – Welding [ca. 1960?] CW-12-2

BC 2009/789 Construction – Welding [ca. 1957] CW-13-1

BC 2009/530 Construction – Welding: [On the Westcoast 1957 CW-13-2 Transmission mainline]

BC 2009/531 Construction – Welding [196-?] CW-14-1 to -532 14-2

BC 2009/533 Construction – Welding [ca. 1956] CW-16-1 to -534 16-2

BC 2009/539 Construction – Welding: Final tie-in, [ca. 1957] CW-21-2 Coquihalla Pass

BC 2009/540 Construction – Welding: Making a tie-in at 1956 CW-21-2 the foot of the Agassiz jump-off looking upstream, July 27, 1956

BC 2009/537 Construction – Welding: [Near Agassiz 1957 CW-22-1 meter station], August 1957

BC 2009/536, Construction – Welding: Near Agassiz meter [1957] CW-22-2, 538 station 23-2

BC 2009/535 Construction – Welding: Making a tie-in at 1956 CW-23-1 the foot of the Agassiz jump-off looking upstream, July 27, 1956

BC 2009/930 Construction – Westpac Pipeline: One mile 1961 CWP-1-1 station #3, McLeod Lake vicinity, cat skinner on right of way, May 1, 1961

BC 2009/931 Construction – Westpac Pipeline: Quesnel 1961 CWP-1-2 metering station north, shows slashing, May 1, 1961

BC 2009/932 Construction – Westpac Pipeline: [Crew [ca. 1960] CWP-2-1 to -934 clearing area (unidentified)] 3-1

BC 2009/935 Construction – Westpac Pipeline: Lac La 1961 CWP-3-2 Hache, location of pump station, showing surveyors, May 1, 1961

82 BC 2009/936 Construction – Westpac Pipeline: Quesnel 1961 CWP-4-1 meter station, shows slashing, May 1, 1961

BC 2009/937 Construction – Westpac Pipeline: Lac La 1961 CWP-4-2 to -939 Hache, location of pump station, showing 5-2 surveyors, May 1, 1961

BC 2009/940 Construction – Westpac Pipeline: [View of [ca. 1961] CWP-6-1 to -942 trench] 7-1

BC 2009/943 Construction – Westpac Pipeline: Railway [ca. 1961] CWP-7-2 to -947 cars carrying pipes 9-2

BC 2009/948 Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-10-1 work]

BC 2009/949 Construction – Westpac Pipeline: [Showing [ca. 1961] CWP-10-2 cleared area]

BC 2009/950 Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-11-1 clearing area]

BC 2009/951 Construction – Westpac Pipeline: Railway [ca. 1961] CWP-11-2 cars carrying pipes

BC 2009/952 Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-12-1 to -954 unloading pipes from truck] 13-1

BC 2009/955 Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-13-2 to -958 loading pipes from railway cars to truck] 15-1

BC 2009/959 Construction – Westpac Pipeline: [Aerial [ca. 1961] CWP-15-2 view of pipeline construction site]

BC 2009/960 Construction – Westpac Pipeline: Ditching 1961 CWP-16-2 to -962 welding at Taylor Plant, May 1, 1961 17-2

BC 2009/963 Construction – Westpac Pipeline: Twelve 1961 CWP-18-1 carloads of pipe for the construction of the Westcoast pipeline from Kamloops to Taylor, B.C., July 30, 1961

BC 2009/964 Construction – Westpac Pipeline: [Showing [ca. 1961] CWP-18-2 pipeline trench]

BC 2009/965 Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-19-1 to -966 work] 19-2

BC 2009/967 Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-20-1 welding pipes]

83 BC 2009/968 Construction – Westpac Pipeline: [View [ca. 1961] CWP-20-2 to -969 showing cleared area] 21-1

BC 2009/970 Construction – Westpac Pipeline: [View of [ca. 1961] CWP-21-2 to -971 pipeline trench] 22-1

BC 2009/972 Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-22-2 to -973 moving pipes] 23-2

BC 2009/974 Construction – Westpac Pipeline: [View of [ca. 1961] CWP-24-1 cleared area and pipeline trench in background]

BC 2009/975 Construction – Westpac Pipeline: [View of [ca. 1961] CWP-24-2 to -979 pipeline trench] 26-2

BC 2009/980 Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-27-1 work]

BC 2009/981 Construction – Westpac Pipeline: [Western [ca. 1961] CWP-27-2 Pacific Products & Crude Oil Co. Ltd. pipeline being laid north of Prince George]

BC 2009/982 Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-28-1 laying pipes]

BC 2009/983 Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-28-2 moving pipes]

BC 2009/984 Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-29-1 to -985 spraying tar on pipes] 29-2

BC 2009/986 Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-30-1 moving pipes]

BC 2009/987 Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-30-2 work]

BC 2009/988 Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-31-1 to -989 wrapping and coating pipes] 31-2

BC 2009/990 Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-32-1 work, Williams Lake, B.C.]

BC 2009/991 Construction – Westpac Pipeline [ca. 1961] CWP-32-2

BC 2009/992 Construction – Westpac Pipeline: [View of [ca. 1961] CWP-33-1 pipeline trench]

BC 2009/993 Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-33-2 wrapping and coating pipes]

84 BC 2009/994 Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-34-1 to -995 work] 34-2

BC 2009/996 Construction – Westpac Pipeline: [View of [ca. 1961] CWP-35-1 to -997 pipeline trench] 35-2

BC 2009/998 Construction – Westpac Pipeline: Tar crews 1961 CWP-36-1 near Road; Construction of the pipeline running from Fort St. John to Nelson, B.C., August 3, 1961

BC 2009/999 Construction – Westpac Pipeline: [View of [ca. 1961] CWP-36-2 pipeline trench]

BC 2009/ Construction – Westpac Pipeline: Sanding 1961 CWP-37-1 1000 and doping crews, pipeline construction north of Quesnel River, August 3, 1961

BC 2009/ Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-37-2 1001 work]

BC 2009/ Construction – Westpac Pipeline: [View of [ca. 1961] CWP-38-1 1002 pipeline trench]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-38-2 1003 digging pipeline trench]

BC 2009/ Construction – Westpac Pipeline [ca. 1961] CWP-39-1 to 1004 - 1005 39-2

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-40-1 1006 digging pipeline trench]

BC 2009/ Construction – Westpac Pipeline [ca. 1961] CWP-40-2 1007

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-41-1 1008 welding pipes]

BC 2009/ Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-41-2 to 1009 - 1011 work] 42-2

BC 2009/ Construction – Westpac Pipeline [ca. 1961] CWP-43-1 1012

BC 2009/ Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-43-2 1013 work]

BC 2009/ Construction – Westpac Pipeline: Ditching 1961 CWP-44-1 to 1014 – 1016 machine, August 3, 1961 45-1

85 BC 2009/ Construction – Westpac Pipeline: [View of [ca. 1961] CWP-45-2 1017 pipeline trench]

BC 2009/ Construction – Westpac Pipeline: Ditching 1961 CWP-46-1 to 1018 - 1020 machine, August 3, 1961 47-1

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-47-2 1021 moving pipes]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-48-1 1022 welding pipes]

BC 2009/ Construction – Westpac Pipeline: [View of [ca. 1961] CWP-48-2 1023 pipeline trench]

BC 2009/ Construction – Westpac Pipeline: Ditching 1961 CWP-49-1 to 1024 - 1025 machine, August 3, 1961 49-2

BC 2009/ Construction – Westpac Pipeline: [Truck [1961] CWP-50-1 1026 loaded with pipes]

BC 2009/ Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-50-2 to 1027 - 1028 work] 51-1

BC 2009/ Construction – Westpac Pipeline: [View of [ca. 1961] CWP-51-2 1029 construction area]

BC 2009/ Construction – Westpac Pipeline: [View of [ca. 1961] CWP-52-1 1030 pipeline trench]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-52-2 1031 wrapping and coating pipes]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-53-1 to 1032 - 1033 moving pipes] 53-2

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-54-1 to 1034 - 1035 wrapping and coating pipes] 54-2

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-55-1 to 1036 - 1037 laying pipes] 55-2

BC 2009/ Construction – Westpac Pipeline: [View of [ca. 1961] CWP-56-1 1038 pipeline trench]

BC 2009/ Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-56-2 to 1039 - 1041 work] 57-2

BC 2009/ Construction – Westpac Pipeline: [View of [ca. 1961] CWP-58-1 1042 trench digging machinery]

86 BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-58-2 1043 digging trench]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-59-1 1044 wrapping and coating pipes]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-59-2 1045 moving pipes]

BC 2009/ Construction – Westpac Pipeline: [View of [ca. 1961] CWP-60-1 to 1046 - 1047 pipeline trench covered in snow] 60-2

BC 2009/ Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-61-1 1048 work]

BC 2009/ Construction – Westpac Pipeline: [View of [ca. 1961] CWP-61-2 1049 construction area]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-62-2 1050 laying pipes]

BC 2009/ Construction – Westpac Pipeline: [View of [ca. 1961] CWP-63-1 1051 crew]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-63-2 to 1052 - 1053 wrapping and coating pipes] 64-1

BC 2009/ Construction – Westpac Pipeline: [Crew at [ca. 1961] CWP-64-2 to 1054 - 1055 work] 65-1

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-65-2 1056 wrapping and coating pipes]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-66-1 1057 clearing construction area]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-66-2 1058 moving pipes from railway cars onto trucks]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-67-1 1059 wrapping and coating pipes]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-67-2 1060 moving pipes]

BC 2009/ Construction – Westpac Pipeline: Western [ca. 1961] CWP-68-1 1061 Pacific Products and Crude Oil Co. Ltd. laying pipeline across the Quesnel River

BC 2009/ Construction – Westpac Pipeline Western [ca. 1961] CWP-69-1

87 1062 Pacific Products and Crude Oil Co. Ltd. laying pipeline across the Quesnel River

BC 2009/ Construction – Westpac Pipeline: [View of [ca. 1961] CWP-69-2 1063 river]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-70-1 1064 moving pipe in front of aerial crossing]

BC 2009/ Construction – Westpac Pipeline: [Crew [ca. 1961] CWP-70-2 1065 laying pipeline]

BC 2009/ Construction – Westpac Pipeline: Western [ca. 1961] CWP-71-1 to 1066 - 1076 Pacific Products and Crude Oil Co. Ltd. 75-1-3 laying pipeline across the Quesnel River

BC 2009/ Construction – Westpac Pipeline [ca. 1961] CWP-75-2-1 1077

BC 2009/360 Displays and Exhibits – Westcoast [198-?] D-6-1 and 2 Transmission Logos [on negative-type paper]

BC 2009/361 Displays and Exhibits – Orifice Meter [196-?] D-7-1 to 9-1 -365 Measurement System

BC 2009/366 Displays and Exhibits – Electronic Chart [196-?] D-9-2 Integrator

BC 2009/350 Early Gas Market Development: [Men filling [1957] EGMD-1-1 to -353 railway car with “Natural gas arrives in 2-2 British Columbia” sign]

BC 2009/354 Early Gas Market Development: 1967 EGMD-3-1 to -359 [Construction of] 8” gas line – Lulu Island to 5-2 Sea Island, February 1967

BC 2009/ McMahon, Frank: [Portrait] [ca. 1970?] FM-5-2 1398

BC 2009/ McMahon, Frank: [Portrait] [195-?] FM-12-1 to 1396 - 1397 12-2

BC 2009/ McMahon, Frank: Standing in front of [195-] FM-14-2 1399 airplane, (l-r): L.M. Clark, F.M. McMahon, J.W. Farris, Lloyd Gilmour, George McMahon, Norman Whitall, John McMahon, and C.H. Wright

BC 2009/ McMahon, Frank: [Portrait] [ca. 1970?] FM-15-1-1 1400

88 BC 2009/ McMahon, Frank: Frank McMahon’s horse [196-?] FM-15-1-2 1401 [photograph of painting]

BC 2009/ McMahon – Frank McMahon and family 1968 FMF-1-2 to 1572 - 1573 visit Fort St. John and Savona, September 2-1 1968: Frank McMahon (left) at Fort St. John plant

BC 2009/ McMahon – Frank McMahon and family 1968 FMF-11-2 1574 visit Fort St. John and Savona, September 1968: [Exterior view]

BC 2009/803 McMahon – Frank McMahon and family 1968 FMF-12-1 visit Fort St. John and Savona

BC 2009/ McMahon – Frank McMahon and family 1968 FMF-15-2 1575 visit Fort St. John and Savona, September 1968: [Aerial view]

BC 2009/ McMahon – Frank McMahon and family 1968 FMF-16-1 1576 visit Fort St. John and Savona, September 1968: [Crew moving pipe], Savona

BC 2009/ McMahon – Frank McMahon and family 1968 FMF-16-2 1577 visit Fort St. John and Savona, September 1968: [Construction], Savona

BC 2009/ McMahon – Frank McMahon and family 1968 FMF-19-1 1578 visit Fort St. John and Savona, September 1968: [View of construction], Savona

BC 2009/ McMahon – Frank McMahon and family 1968 FMF-25-1 1579 visit Fort St. John and Savona, September 1968: [Frank McMahon (left) talking to two unidentified men]

BC 2009/ McMahon – Frank McMahon and family 1968 FMF-28-1, 1580 - 1582 visit Fort St. John and Savona, September 28-2, 31-1 1968: [View of interior of plant]

BC 2009/ McMahon – Frank McMahon and family 1968 FMF-31-2 1583 visit Fort St. John and Savona, September 1968: [Frank McMahon overlooking Fort St. John plant]

BC 2009/809 Fort Nelson: New Westcoast Transmission [ca. 1982] FN-1-1-1 sign, with Plant Manager Glen Ireland and Secretary standing in front

BC 2009/822 Fort Nelson: Model of Fort Nelson Gas [ca. 1967] FN-29-1 Processing Plant

89 BC 2009/ Booster Stations – Fort Nelson #12: Scrubber [197-] FNBS-1-1-1 1351 building

BC 2009/ Booster Stations – Fort Nelson #12: Steam [197-] FNBS-1-1-2 1352 piping

BC 2009/ Booster Stations – Fort Nelson #12: Cooling [197-] FNBS-1-1-3 1353 the steam injection glands

BC 2009/ Booster Stations – Fort Nelson #12: Scrubber [197-] FNBS-1-1-4 1354 building

BC 2009/ Booster Stations – Fort Nelson #12: [Exterior [197-] FNBS-1-2-1 1355 view]

BC 2009/ Booster Stations – Fort Nelson #12: [197-] FNBS-1-2-2 1356 Compressor building

BC 2009/ Booster Stations – Fort Nelson #12: Steam [197-] FNBS-1-2-3 1357 piping

BC 2009/ Booster Stations – Fort Nelson #12: [Exterior [197-] FNBS-1-2-4 1358 view]

BC 2009/ Booster Stations – Fort Nelson #12: [Interior [197-?] FNBS-4-1 1359 view]

BC 2009/389 Gas Plants – Fort Nelson Plant construction, 1967 FNC-1-1 plant site

BC 2009/806 Gas Plants – Fort Nelson plant construction, 1967 FNC-1-2 May 1967

BC 2009/390 Gas Plants – Fort Nelson Plant construction, 1967 FNC-2-1 to -392 May 1967 3-1

BC 2009/393 Gas Plants – Fort Nelson Plant construction [1967] FNC-3-2, -394 10-1

BC 2009/395 Gas Plants – Fort Nelson Plant construction: 1974 FNC-16-1 Sulphur Recovery Unit, chipping top of pile, June 20, 1974

BC 2009/396 Gas Plants – Fort Nelson Plant construction: 1974 FNC-16-2 Sulphur Recovery Unit, two Sulfreen Reactors and their foundations, looking south-west, June 20, 1974

BC 2009/397 Gas Plants – Fort Nelson Plant construction: 1974 FNC-16-3 Sulphur Recovery Unit, converter foundations looking north-west, June 20,

90 1974

BC 2009/398 Gas Plants – Fort Nelson Plant construction: 1974 FNC-16-4 Sulphur Recovery Unit, off-loading Sulfreen Reactor, June 20, 1974

BC 2009/399 Gas Plants – Fort Nelson Plant construction: 1974 FNC-17-5 Sulphur Recovery Unit, dressing concrete on Sulfreen Reactor foundation, June 20, 1974

BC 2009/400 Gas Plants – Fort Nelson Plant construction: 1974 FNC-17-6 Sulphur Recovery Unit, access road, June 20, 1974

BC 2009/401 Gas Plants – Fort Nelson Plant construction: 1974 FNC-17-7 Sulphur Recovery Unit, Sulfreen Reactors off-loading at site, June 20, 1974

BC 2009/402 Gas Plants – Fort Nelson Plant construction: 1974 FNC-17-8 Sulphur Recovery Unit, K.O. drum received from KAPS, Edmonton, June 20, 1974

BC 2009/403 Gas Plants – Fort Nelson Plant construction: 1974 FNC-17-9 Sulphur Recovery Unit, Exist Thermal Oxidizer, looking east from site, June 20, 1974

BC 2009/404 Gas Plants – Fort Nelson Plant construction: 1974 FNC-17-10 Sulphur Recovery Unit, Sulfreen Reactor, June 20, 1974

BC 2009/405 Gas Plants – Fort Nelson Plant construction: 1974 FNC-18-11 Sulphur Recovery Unit, rat-hole drill on its way, June 20, 1974

BC 2009/406 Gas Plants – Fort Nelson Plant construction: 1974 FNC-18-12 Sulphur Recovery Unit, belling tool and drill, June 20, 1974

BC 2009/407 Gas Plants – Fort Nelson Plant construction: 1974 FNC-18-13 Sulphur Recovery Unit, construction office (on the verge), June 20, 1974

BC 2009/408 Gas Plants – Fort Nelson Plant construction: 1974 FNC-18-14 Sulphur Recovery Unit, converters, last two items to be off-loaded, June 20, 1974

BC 2009/409 Gas Plants – Fort Nelson Plant construction: 1974 FNC-18-15 Sulphur Recovery Unit, third Sulfreen Reactor, making ready for 15 mile trip to site, June 20, 1974

91 BC 2009/410 Gas Plants – Fort Nelson Plant construction: 1974 FNC-19-16 Sulphur Recovery Unit, cat holds barge fast to shore, June 20, 1974

BC 2009/411 Gas Plants – Fort Nelson Plant construction: 1974 FNC-19-17 Sulphur Recovery Unit, temporary ramp to barge, June 20, 1974

BC 2009/412 Gas Plants – Fort Nelson Plant construction: 1974 FNC-19-18 Sulphur Recovery Unit, Pat Garrett holding down his corner, June 20, 1974

BC 2009/413 Gas Plants – Fort Nelson Plant construction: 1974 FNC-19-19 Sulphur Recovery Unit, converters heading to shore, June 20, 1974

BC 2009/414 Gas Plants – Fort Nelson Plant construction [1967?] FNC-23-1, -418 24-1 to 24-2, 27-1 to 27-2

BC 2009/419 Gas Plants – Fort Nelson Plant interior: [1969] FNP-3-1 Norm Watson checking lubrication monitor on one of 3 Westinghouse 13,000 h.p. non- condensing steam turbines

BC 2009/420 Gas Plants – Fort Nelson Plant interior: [1969] FNP-3-2 Steam powered compressor station, with 3 Ingersoll-Rand centrifugal compressors (left) driven by 13,000 h.p. Westinghouse steam turbines

BC 2009/421 Gas Plants – Fort Nelson Plant interior: 1969 FNP-12-1 Boilers, powerhouse, October 1, 1969

BC 2009/422 Gas Plants – Fort Nelson Plant interior: 1969 FNP-12-2, -423 Powerhouse, October 1, 1969 19-1

BC 2009/424 Gas Plants – Fort Nelson: Fort Nelson Pit, 1968 FNP1-3-1 benefits program lectures

BC 2009/425 Gas Plants – Fort Nelson: [View of portion 1968 FNP1-3-2 of exterior]

BC 2009/426 Gas Plants – Fort Nelson: [View of portion 1968 FNP1-13-2 of exterior, from above]

BC 2009/427 Gas Plants – Fort Nelson: [View of portion 1968 FNP1-14-1, -428 of exterior] 15-1

BC 2009/429 Gas Plants – Fort Nelson: [Interior view] 1968 FNP1-15-2

92 BC 2009/430 Gas Plants – Fort Nelson: [View of portion 1968 FNP1-16-1 of exterior]

BC 2009/431 Gas Plants – Fort Nelson: [View of section 1968 FNP1-16-2 of plant]

BC 2009/432 Gas Plants – Fort Nelson: [Exterior view] 1967 FNP1-22-1

BC 2009/433 Gas Plants – Fort Nelson: [Exterior view], 1965 FNP1-27-1 to -434 April 1965 27-2

BC 2009/435 Gas Plants – Fort Nelson: July 1967 1967 FNP1-32-1

BC 2009/436 Gas Plants – Fort Nelson [ca. 1967] FNP1-32-2

BC 2009/437 Gas Plants – Fort Nelson: [Exterior view] [ca. 1967] FNP1-52-1, -440 53-1 to 53-2, 56-1

BC 2009/807 Gas Plants – Fort Nelson: [Exterior view] [1973] FNP1-52-2

BC 2009/808 Gas Plants – Fort Nelson: [Aerial view] 1973 FNP1-55-1

BC 2009/441 Gas Plants – Fort Nelson: [Exterior view in [ca. 1967] FNP1-56-2 winter]

BC 2009/442 Gas Plants – Fort Nelson: [Exterior view] [ca. 1980] FNP2-1-1 to -447 3-2

BC 2009/448 Gas Plants – Fort Nelson: [Aerial view] [198-?] FNP2-7-1

BC 2009/449 Gas Plants – Fort Nelson: [Aerial view] [ca. 1980?] FNP2-8-1

BC 2009/450 Gas Plants – Fort Nelson: [Aerial view] [198-?] FNP2-9-1

BC 2009/451 Gas Plants – Fort Nelson: Sulphur plant [ca. 1982] FNP2-9-2

BC 2009/452 Gas Plants – Fort Nelson: [Aerial view] [ca. 1980] FNP2-13-1

BC 2009/453 Gas Plants – Fort Nelson: [Aerial view], 1982 FNP2-13-2 January 1982

BC 2009/454 Gas Plants – Fort Nelson: [Exterior view] [ca. 1990?] FNP2-15-1 to -455 15-2

BC 2009/456 Gas Plants – Fort Nelson: Sulphur plant [ca. 1982] FNP2-16-1 to -457 16-2

BC 2009/ Gas Plants – Fort Nelson [199-] FNP2-20-2-1 1775

93 BC 2009/ British Columbia – Fort St. John [aerial [196-?] FSJ-2-2 1483 view]

BC 2009/ British Columbia – Fort St. John [view of [195-] FSJ-8-1 1484 pipeline]

BC 2009/541 Construction – Fraser Valley Upgrading, 1973 FVU-9-2 to –554, 778 August 31, 1973 26-1

BC 2009/555 Construction – Fraser Valley Upgrading [1973] FVU-26-2 to -564 35-1

BC 2009/565 Construction – Fraser Valley Upgrading: [1973] FVU-42-2 [Concrete blocks]

BC 2009/566 Construction – Fraser Valley Upgrading: [1973] FVU-43-1 [Stacked-up pipes]

BC 2009/567 Construction – Fraser Valley Upgrading: [1973] FVU-44-1 to -569 [View of pipeline] 45-1

BC 2009/570 Construction – Fraser Valley Upgrading [1973] FVU-45-2

BC 2009/830 Construction – Gathering Systems: Nig [195-] GS-1-1 Creek to Laprise Creek 12” line; Contractor’s field camp to accommodate 120 men

BC 2009/831 Construction – Gathering Systems [ca. 1960] GS-1-2

BC 2009/832 Construction – Gathering Systems: [Work [ca. 1960] GS-2-1 crew moving pipes]

BC 2009/833 Construction – Gathering Systems: [ca. 1960] GS-3-1 Gathering line near plant, [Work crew moving pipes]

BC 2009/834 Construction – Gathering Systems: [ca. 1960] GS-4-1 Gathering lines, [Work crew laying pipes]

BC 2009/835 Construction – Gathering Systems: [ca. 1960] GS-4-2 Gathering lines near Taylor, B.C., [Work crew moving pipes]

BC 2009/836 Construction – Gathering Systems: [ca. 1960] GS-4-2 Gathering lines near Taylor, B.C., [Work crew laying pipes]

BC 2009/837 Construction – Gathering Systems: [ca. 1960] GS-5-1 to -839 Gathering lines, [Work crew laying pipes] 6-1

94 BC 2009/840, Construction – Gathering Systems: Buick [1960] GS-6-2, 7-2 842 Creek to Nig Creek, 16” line clearing operations in timber country

BC 2009/841 Construction – Gathering Systems: Nig [ca. 1960] GS-7-1 Creek to Laprise Creek 12” line, clearing 50’ right of way

BC 2009/843 Construction – Gathering Systems: Buick [1960] GS-8-1 Creek to Nig Creek 16” line, burning timber on right-of-way prior to grading

BC 2009/844 Construction – Gathering Systems: Nig [ca. 1960] GS-8-2 Creek to Laprise Creek 12” line, grading of right-of-way following clearing

BC 2009/845 Construction – Gathering Systems: Nig [ca. 1960] GS-9-1 Creek to Laprise Creek 12” line, Athey wagons stringing pipe on right-of way

BC 2009/846 Construction – Gathering Systems: Nig [ca. 1960] GS-9-2 Creek to Laprise Creek 12” line, Athey wagons delivering pipe to right-of way, with partial muskeg in right foreground

BC 2009/847 Construction – Gathering Systems: Nig [ca. 1960] GS-10-1 Creek to Laprise Creek 12” line, Athey wagons delivering pipe on right-of way, and completed machine ditch

BC 2009/848 Construction – Gathering Systems: Buick [1960] GS-10-2 Creek to Nig Creek 16” line, completed ditch and pipe stringing on right-of-way

BC 2009/849 Construction – Gathering Systems: Buick [1960] GS-11-1 Creek to Nig Creek 16” line, machine ditching operations

BC 2009/850 Construction – Gathering Systems: Nig [ca. 1960] GS-11-2 Creek to Laprise Creek 12” line, Backhoe making ditch in permafrost on south side of creek crossing, with ditch made by ditching machine in background

BC 2009/851 Construction – Gathering Systems: Nig [ca. 1960] GS-12-1 Creek to Laprise Creek 12” line, bending machine at work

BC 2009/852 Construction – Gathering Systems: Buick [1960] GS-12-2 Creek to Nig Creek 16” line, line-up and tack-welding crew

95 BC 2009/853 Construction – Gathering Systems [ca. 1960] GS-13-1

BC 2009/854 Construction – Gathering Systems: Buick [1960] GS-13-2 Creek to Nig Creek 16” line, line-up and tack-welding operations

BC 2009/855 Construction – Gathering Systems: Nig [ca. 1960] GS-14-1 Creek to Laprise Creek 12” line, coating and wrapping machine working on primed pipe

BC 2009/856 Construction – Gathering Systems: Buick [1960] GS-14-2 Creek to Nig Creek 16” line, application of hot enamel and glass wrapper

BC 2009/857 Construction – Gathering Systems: Nig [ca. 1960] GS-15-1 Creek to Laprise Creek 12” line, tractors lowering completed pipeline into ditch

BC 2009/779 Construction – Gathering Systems: Natural [1957] GS-15-2 gas entering Vancouver

BC 2009/858 Construction – Gathering Systems: Buick 1960 GS-16-1 Creek to Nig Creek 16” line, contractor’s field camp including kitchens, dining rooms, washrooms and bunkhouses, with VHF portable radio tower in foreground

BC 2009/859 Construction – Gathering Systems [198-] GS-16-2

BC 2009/860 Construction – Gathering Systems: Buick 1960 GS-17-1-1 Creek to Nig Creek 16” line, open ditch with pipe stringing

BC 2009/861 Construction – Gathering Systems: Buick 1960 GS-17-1-2 Creek to Nig Creek 16” line, line-up and tack welding

BC 2009/862 Construction – Gathering Systems: Buick 1960 GS-17-1-3 to -863 Creek to Nig Creek 16” line, contractor’s 17-1-4 camp facilities

BC 2009/864 Construction – Gathering Systems: Buick 1960 GS-17-1-5 Creek to Nig Creek 16” line, final welding just ahead of the coating and lowering in crew

BC 2009/584 Construction – Grizzly Valley: Spindles 1978 GV-4-1 to -585 wrap corrosion proof plastic around pipeline 4-2 prior to lowering it into trench, September 24, 1978

96 BC 2009/587 Construction – Grizzly Valley: Work crew 1978 GV-8-2 welds pipeline, September 24, 1978

BC 2009/586 Construction – Grizzly Valley: Work crew 1978 GV-20-1 lowers a section of pipeline into trench, September 24, 1978

BC 2009/588 Construction – Grizzly Valley: Work crew 1978 GV-29-1 member welds pipeline, August 22, 1978

BC 2009/589 Construction – Grizzly Valley: Blasting 1978 GV-29-1 right-of-way, August 22, 1978

BC 2009/590 Construction – Grizzly Valley: Aerial view 1978 GV-31-2 of cleared site for Pine River Plant, with housing for construction workers at left- centre, pipeline right-of-way at lower left, and construction road to site at lower right

BC 2009/591 Construction – Grizzly Valley: Pipeline 1978 GV-32-1 construction, Station No. 2, mainline entering station from Fort Nelson, August 22, 1978

BC 2009/592 Construction – Grizzly Valley: Pipeline 1978 GV-37-1 to -593 construction, August 22, 1978 37-2

BC 2009/594 Construction – Grizzly Valley: Opening 1978 GV-41-1 ceremonies, November 1978, with Ed Phillips on left

BC 2009/595 Construction – Grizzly Valley: Bill Bennett 1978 GV-41-2 speaking at opening ceremonies, November 1978

BC 2009/596 Construction – Grizzly Valley: Bill Bennett 1978 GV-42-1 receiving art piece at opening ceremonies, November 1978

BC 2009/597 Construction – Grizzly Valley: [View of 1978 GV-47-1 pipeline]

BC 2009/598 Construction – Grizzly Valley: [Pipeline 1978 GV-47-2, -599 construction] 48-1

BC 2009/600 Construction – Grizzly Valley: [Work crew 1978 GV-48-2 welding pipeline] [oversize]

BC 2009/601 Construction – Grizzly Valley: [Pipeline 1978 GV-51-1 construction]

97 BC 2009/602 Construction – Grizzly Valley: [Pipeline 1978 GV-52-1 construction, lowering of pipeline]

BC 2009/603 Construction – Grizzly Valley: [Pipeline 1978 GV-52-2 construction, laying of pipeline]

BC 2009/603 Construction – Grizzly Valley: [Pipeline 1978 GV-52-2 neg. neg. construction, laying of pipeline]

BC 2009/604 Construction – Grizzly Valley: [Work crew 1978 GV-53-1 welding pipeline]

BC 2009/605 Construction – Grizzly Valley: [Pipeline 1978 GV-53-2 construction]

BC 2009/606 Construction – Grizzly Valley: Work crew 1978 GV-54-1, 54-2 -607 and machinery lower steel pipe into waiting [oversize] trench

BC 2009/606 Construction – Grizzly Valley: Work crew 1978 GV-54-1 neg. neg. and machinery lower steel pipe into waiting trench

BC 2009/608 Construction – Grizzly Valley: Tractors with 1978 GV-55-1 side-booms and large crane lowering 30-inch [oversize] pipe into trench on steep grade, August 22, 1978

BC 2009/608 Construction – Grizzly Valley: Tractors with 1978 GV-55-1 neg. side-booms and large crane lowering 30-inch neg. pipe into trench on steep grade, August 22, 1978

BC 2009/609 Construction – Grizzly Valley: [Pipeline 1978 GV-55-2 construction] [oversize]

BC 2009/342 Housing – New Housing – Fort Nelson, July 1966 H-1-1-1 to H- –345 1966 1-2-2

BC 2009/346 Housing at Compressor Stn. No. 7, Savona [196-] H-16-1 to –347 (near Kamloops, B.C.) 16-2

BC 2009/348 Housing at Fort St. John, B.C. [196-] H-33-1 to –349 33-2

BC 2009/793 Meter Stations – Huntingdon Station [195-] HMS-1-1

BC 2009/804 Meter Stations – Huntingdon Station 1959 HMS-2-2 (featured in 1959 Annual Report)

98 BC 2009/ Meter Stations – Huntingdon Station: [Man [195-] HMS-2A-1 to 1547 – 1548 taking measurements] 2A-2

BC 2009/ Meter Stations – Huntingdon Station: [ca. 1957] HMS-3-1 1549 [Exterior view]

BC 2009/ Meter Stations – Huntingdon Station: [ca. 1957] HMS-3-2 1550

BC 2009/805 Meter Stations – Huntington Station 1971 HMS-5-2

BC 2009/ Meter Stations – Huntingdon Station: [195-] HMS-8-1 1551 [Interior view]

BC 2009/ Meter Stations – Huntingdon Station: [Man [195-] HMS-8-2, 9-1 1552 - 1553 taking measurements]

BC 2009/ Meter Stations – Huntingdon Station: [Man [195-] HMS-9-2 1554 working]

BC 2009/ Construction – Jedney Bubbles Pipeline: 1959 JB-1-1 to 6-2 1601-1612 September 1959

BC 2009/ Construction – Jedney Bubbles Pipeline: 1959 JB-7-1-1 1612 neg. September 1959

BC 2009/ Booster Stations – Kobes Creek: Kobes [ca. 1960?] KCB-5-1 to 1348-1349 Compressor Station 5-2

BC 2009/ Booster Stations – Kobes Creek [ca. 1960?] KCB-6-1 1350

BC 2009/367 Kern River: From 1985 annual report 1985 KR-1-1-1 to –374 1-2-4

BC 2009/227 Gas Plants – McMahon Plant [ca. 1957] MCM1-1-1 to –229 2-1

BC 2009/230 Gas Plants – McMahon Plant: [Interior, men [ca. 1957?] MCM1-2-2 working]

BC 2009/231 Gas Plants – McMahon Plant: [Interior, man [ca. 1957?] MCM1-6-1 at work on machinery]

BC 2009/232 Gas Plants – McMahon Plant: [Construction] [1957] MCM1-6-2

BC 2009/233 Gas Plants – McMahon Plant: [Construction] 1957 MCM1-13-1

BC 2009/234 Gas Plants – McMahon Plant: [Interior] 1957 MCM1-13-2

BC 2009/235 Gas Plants – McMahon Plant: [Construction] [1957] MCM1-14-1

99 BC 2009/236 Gas Plants – McMahon Plant: Construction [1957] MCM1-14-2 -237 view

BC 2009/238 Gas Plants – McMahon Plant: Inside refinery [1957] MCM1-21-1

BC 2009/239 Gas Plants – McMahon Plant: [Men viewing [1957] MCM1-21-2 plant]

BC 2009/240 Gas Plants – McMahon Plant: [Man [1957] MCM1-23-1 checking guages]

BC 2009/241 Gas Plants – McMahon Plant: [Man sitting in [1957] MCM1-23-2 a control room]

BC 2009/242 Gas Plants – McMahon Plant: Bridge failure, [ca. 1957] MCM1-31-1 Taylor, B.C.

BC 2009/243 Gas Plants – McMahon Plant [ca. 1960] MCM1-31-2

BC 2009/244 Gas Plants – McMahon Plant: January 1961 1961 MCM1-32-1

BC 2009/245 Gas Plants – McMahon Plant [ca. 1960] MCM1-32-2

BC 2009/246 Gas Plants – McMahon Plant: Interior of 1961 MCM1-33-1 M.F. Alkyletian Unit pump and motor room, January 1961

BC 2009/247 Gas Plants – McMahon Plant: Overall plant [1961] MCM1-33-2 view showing Plant C at left, Plant B centre and Plant A on the right

BC 2009/248 Gas Plants – McMahon Plant: [Bird’s eye [ca. 1960] MCM1-40-1 -249 view] to 40-2

BC 2009/250 Gas Plants – McMahon Plant: [Showing [ca. 1960] MCM1-43-1 flames from wells]

BC 2009/251 Gas Plants – McMahon Plant: [Bird’s eye [ca. 1960] MCM1-43-2 view]

BC 2009/252 Gas Plants – McMahon Plant: [Bird’s eye [ca. 1960] MCM1-45-1 view] (mounted on board)

BC 2009/253 Gas Plants – McMahon Plant: [Interior view, [ca. 1960] MCM1-45-2 man working on machinery]

BC 2009/340 Gas Plants – McMahon Plant [Bird’s eye 1978 MCM2-1-1, -341 view] 2-1

BC 2009/814 Gas Plants – McMahon Plant [aerial view] [ca. 1990] MCM2-1-2

100 BC 2009/ Moving Clarke Units (Engines): Willow 1966 MCU-1-2 1555 Flats, October 1966

BC 2009/ Moving Clarke Units (Engines): Clarke 1966 MCU-6-1 to 1556-1557 engine installation at Station #2, Willow 6-2 Flats

BC 2009/ Moving Clarke Units (Engines): Installation 1967 MCU-19-1 to 1558-1561 of Clarke engine at Hope CS-8B, April 1967; 26-1 Crossing the Coquihalla River

BC 2009/ Moving Clarke Units (Engines): Engine 1968 MCU-33-1 1562 move to Hope Station 8B

BC 2009/ Moving Clarke Units (Engines): Engine 1968 MCU-33-2 1563 move to Hope Station 8B; Welder

BC 2009/ Moving Clarke Units (Engines): Engine 1968 MCU-38-1 1564 move to Hope Station 8B

BC 2009/ Moving Clarke Units (Engines): [Engine [1968] MCU-38-2 1565 move to Hope Station 8B] (Pipeline News, vol. 8, no. 5)

BC 2009/ Moving Clarke Units (Engines): Engine 1968 MCU-40-1 to 1566-1568 move to Hope Station 8B 41-1

BC 2009/ Moving Clarke Units (Engines): Engine 1968 MCU-41-2 1569 move to Hope Station 8B (Pipeline News, vol. 8, no. 5)

BC 2009/ Moving Clarke Units (Engines): Station #3 [ca. 1968] MCU-48-1 to 1570-1571 48-2

BC 2009/495 Looping – Misc.: Rosedale, Summer 1991 1991 ML-14-1-2 to -496 14-2-2

BC 2009/ Opening Ceremonies: Fleet of chartered 1957 OC-1-1 1523 planes bringing people to Fort St. John, B.C. to celebrate the completion of the Peace River pipeline

BC 2009/ Opening Ceremonies: People arriving in Fort 1957 OC-1-2 to 1524-1526 St. John, B.C. on fleet of chartered planes to OC-2-2 celebrate the completion of the Peace River pipeline

BC 2009/ Opening Ceremonies: People at airport after 1957 OC-3-1 1527 arriving in Fort St. John, B.C. to celebrate the completion of the Peace River pipeline

101 BC 2009/783 Opening Ceremonies: George McMahon 1957 OC-4-2 speaking at the ceremony to commemorate the completion of the Peace River pipeline in Fort St. John, B.C., October 7, 1957

BC 2009/ Opening Ceremonies: Hotel Vancouver 1957 OC-5-1 1528 luncheon to celebrate the completion of the Peace River pipeline -- Frank McMahon (far left) and W.A.C. Bennett (second from left)

BC 2009/ Opening Ceremonies: Hotel Vancouver 1957 OC-5-2 to 6-2 1529-1531 luncheon to celebrate the completion of the Peace River pipeline

BC 2009/ Opening Ceremonies: Hotel Vancouver 1957 OC-7-1 1532 luncheon to celebrate the completion of the Peace River pipeline -- W.A.C. Bennett turns lever with A.E. Grauer (left) and Frank M. McMahon watching

BC 2009/785 Opening Ceremonies: Frank M. McMahon 1957 OC-8-2 speaks at Hotel Vancouver luncheon to celebrate the official opening of the Peace River pipeline -- W.A.C. Bennett (far left) and A.E. Grauer (second from left) watching

BC 2009/ Opening Ceremonies: People at airport after 1957 OC-9-2 1533 arriving in Fort St. John, B.C. to celebrate the completion of the Peace River pipeline

BC 2009/ Opening Ceremonies: Betty McMahon 1957 OC-10--1 1534 (second from right) and other women at Hotel Vancouver luncheon to celebrate the completion of the Peace River pipeline

BC 2009/ Opening Ceremonies: McMahon brothers, (l- 1957 OC-11-1(a) 1535 r): John, Frank, and George at Hotel Vancouver luncheon to celebrate the completion of the Peace River pipeline

BC 2009/ Opening Ceremonies: McMahon brothers, (l- 1957 OC-11-1(b) 1536 r): John, Frank, and George Hotel Vancouver luncheon to celebrate the completion of the Peace River pipeline

BC 2009/ Opening Ceremonies: Speakers’ platform for 1957 OC-14-2 1537 Fort St. John, B.C. ceremony to celebrate the completion of the Peace River pipeline

102 BC 2009/ Opening Ceremonies: Opening of the Peace 1957 OC-16-1 to 1538 - 1539 River pipeline at Fort St. John, B.C. by the 16-2 Hon. William F. Kiernan (right) with George McMahon standing by

BC 2009/ Opening Ceremonies: Opening of the Peace 1957 OC-17-1 to 1540 - 1541 River pipeline at Fort St. John, B.C. by the 17-2 Hon. Ray Reierson (left) with George McMahon standing by

BC 2009/ Opening Ceremonies: Flaring oil well at 1957 OC-18-1 to 1542 - 1543 ceremony for the opening of the Peace River 18-2 pipeline at Fort St. John, B.C.

BC 2009/ Opening Ceremonies: George McMahon and 1957 OC-19-1 1544 two unidentified men at the opening of the Peace River pipeline at Fort St. John, B.C.

BC 2009/ Opening Ceremonies: Frank McMahon (left) 1957 OC-19-2 1545 and unidentified man at the opening of the Peace River pipeline at Fort St. John, B.C.

BC 2009/ Opening Ceremonies: Frank and Betty 1957 OC-20-1 1546 McMahon at the opening of the Peace River pipeline at Fort St. John, B.C.

BC 2009/723 People – Don Berkely (featured in The 1990 P-1-1 Flame, Spring 1990)

BC 2009/724 People – [Man pointing in control room] [1990] P-1-2

BC 2009/725 People – [Man standing next to equipment [198-?] P-4-1 being moved]

BC 2009/726 People – [Employees in workroom] [ca. 1970] P-4-2

BC 2009/727 People – [Man standing beside truck] [196-?] P-9-1-1

BC 2009/728 People – Fort Nelson Toastmasters members [ca. 1970] P-24-1

BC 2009/729 People – [Men posing with trophies] 1969 P-24-1

BC 2009/193 Prince George: Sulphur Dioxide plant [198-?] PG-3-1-1 to –194 3-1-2

BC 2009/195 Prince George: Pulp & Paper [196-?] PG-21-1 to -198 22-2

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-1-1 1366 August 31, 1956: [W.A.C. Bennett (third from left) and Frank McMahon (fourth from

103 left) with others viewing pipeline construction]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-1-2 1367 August 31, 1956: [W.A.C. Bennett (second from left) and Frank McMahon (third from left) with others viewing pipeline construction]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-2-2 to 1368-1369 August 31, 1956: [Frank McMahon (left) and 3-1 W.A.C. Bennett viewing pipeline construction]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-3-2 1370 August 31, 1956: [W.A.C. Bennett (centre) and others at pipeline construction site]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-4-1 1371 August 31, 1956: [Frank McMahon (left), W.A.C. Bennett (centre) and unidentified man at pipeline construction site]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-4-2 1372 August 31, 1956: [W.A.C. Bennett and Frank McMahon with others viewing pipeline construction]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-5-1 1373 August 31, 1956: [Unidentified men at pipeline construction site]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-5-2 1374 August 31, 1956: [W.A.C. Bennett and Frank McMahon with others at pipeline construction site]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-6-1 to 1375-1378 August 31, 1956: [Frank McMahon (left) and 7-2 W.A.C. Bennett viewing pipeline construction]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-8-1 to 1379-1380 August 31, 1956: [Frank McMahon] 8-2

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-9-1 1381 August 31, 1956: [Frank McMahon (right) looking at atlas with unidentified man]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-9-2, 1382-1383 August 31, 1956: [View of pipeline 11-1

104 construction area]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-11-2 1384 August 31, 1956: [W.A.C. Bennett giving speech at ceremony]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-12-1 1385 August 31, 1956: [W.A.C. Bennett waving from train]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-13-1 1386 August 31, 1956: [W.A.C. Bennett on platform at ceremony]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-13-2 1387 August 31, 1956: [W.A.C. Bennett giving speech at ceremony]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-14-1 1388 August 31, 1956: [W.A.C. Bennett with two unidentified women]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-14-2 1389 August 31, 1956: [Aerial view of Fort St. John area]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-15-1 1390 August 31, 1956: [W.A.C. Bennett giving speech at banquet, while Frank McMahon (centre) listens]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-15-2 1391 August 31, 1956: [Frank McMahon standing at banquet, with W.A.C. Bennett sitting to his right]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-16-1 1392 August 31, 1956: [Frank McMahon (centre) presenting W.A.C. Bennett (left) with a special hard hat]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-16-2 1393 August 31, 1956: [W.A.C. Bennett (far left), Frank McMahon (second from left) and two unidentified men don special hard hats]

BC 2009/ Bennett’s – P.G.E. Trip to Fort St. John, 1956 PGET-21-1 to 1394 - 1395 August 31, 1956: [Frank McMahon standing 21-2 in front of pipes]

105 BC 2009/ Pipe in Transit: Vancouver Harbour, 1956 PIT-1-1 to 1674-1688 February 1956 2-1, 10-2, 11-1, 12-1, 22-1 to 24-2, 27-1, 27-2, 36-1

BC 2009/ Pipe in Transit: [ca. 1956] PIT-2-2 1693

BC 2009/ Pipe in Transit: Peace River railway sign [ca. 1956] PIT-3-1 1694

BC 2009/ Pipe in Transit: On a train, February 1956 1956 PIT-3-2 to 1695-1701 6-2

BC 2009/ Pipe in Transit: In holding yard [ca. 1956] PIT-7-1, 14-1 1702-1704 29-1

BC 2009/ Pipe in Transit: Piles of pipe at Savona, B.C., 1956 PIT-7-2, 8-1 1707-1708 May 1956

BC 2009/ Pipe in Transit: Unloading pipe from PGE [1956] PIT-8-2 1709 yards in Prince George

BC 2009/ Pipe in Transit: Transporting pipe by truck [1956] PIT-9-2, 1710-1712 18-1, 40-2

BC 2009/ Pipe in Transit: Transporting pipe by train [ca. 1956] PIT-12-2 to 1713-1728 13-2, 14-2 to 16-2, 19-1, 21-1, 25-1, 25-2, 26-2, 30-1, 33-1, 38-2 to 39-2

BC 2009/ Pipe in Transit: In holding yard 1967 PIT-17-1, 1705-1706 28-1

BC 2009/ Pipe in Transit: Transporting pipe by train, 1967 PIT-17-2 1730 Japanese pipes in Vancouver Harbour, March 1967

BC 2009/ Pipe in Transit: Transporting pipe by train, 1970 PIT-26-1 1731 36-inch pipe, unloaded from Japanese ships, Centennial Pier, early September 1970, for 1970-1971 looping program

BC 2009/ Pipe in Transit: Japanese pipe at Vancouver 1967 PIT-31-1 to 1732-1735 Harbour 32-2

106 BC 2009/ Pipe in Transit [ca. 1960] PIT-33-2 1736

BC 2009/ Pipe in Transit: Pipe used in Fort Nelson [1956] PIT-34-2, 1689-1692 Chetwynd extension at Vancouver Harbour 35-1, 37-1, 37-2

BC 2009/ Pipe in Transit: Transporting pipe by train, [ca. 1956] PIT-38-1 1729 pipe arriving for Westcoast’s gathering line in yards at Taylor, B.C.

BC 2009/ Pipe in Transit: Unloading pipe at Centennial 1971 PIT-41-1 1737 Pier

BC 2009/ Pipe in Transit: [Unloading pipe at P.G.E. [1964] PIT-41-2 1738 yards in Fort St. John, B.C.]

BC 2009/799 Pacific Petroleums: [Frank McMahon (left) 1958 PP-12-1 inspecting Pacific Petroleums truck with two men]

BC 2009/800 Pacific Petroleums: Management Committee, [1958] PP-36-1 (l-r): M. Youell, L.M. Clark, W.J. MacIntosh, A.P. Bowsher, K.H. Gibson, J.B. Ballem. M. Rasmussen, R.E. Manahan

BC 2009/801 Pacific Petroleums: George McMahon at [ca. 1960] PP-36-2 desk

BC 2009/802 Pacific Petroleums: George McMahon [ca. 1960] PP-38-1 (sitting) and Kelly Gibson

BC 2009/333 Gas Plants – Pine River 1978 PRGP-1-1

BC 2009/334 Gas Plants – Pine River: [Bird’s eye view], 1979 PRGP-2-1 to –336 Summer 1979 2-2, 4-1

BC 2009/337 Gas Plants – Pine River: [Construction] [1979] PRGP-4-2

BC 2009/338 Gas Plants – Pine River: [Bird’s eye view], 1980 PRGP-11-1 to –339 May 1980 11-2

BC 2009/ Gas plants – Pine River Gas Plant [199-] PRGP-21-1-1 1773-1774 to 21-1-2

BC 2009/704 People at Work: Fort Nelson Process boiler 1969 PW-1-1 control panel and room, February 1969

BC 2009/705 People at Work: Fort Nelson Process control 1969 PW-1-2 room, February 1969

107 BC 2009/706 People at Work: Fort Nelson Power panel, 1969 PW-2-1 February 1969

BC 2009/707 People at Work: [Fort Nelson plant, February 1969 PW-2-2 to -710 1969] 4-2

BC 2009/711 People at Work: Texaco NFA Boundary 1956 PW-4-2 Lake, B.C.’s first oil well, August 1956

BC 2009/571 Picketing Westcoast Transmission: B.C. 1961 PWCT-1-1 to -583 Federation of Unemployed pickets Frank 6-2 McMahon, January 18, 1961

BC 2009/199 Rigs & Drilling [ca. 1960] RD-1-1 to –206 4-2

BC 2009/207 Rigs & Drilling: Drilling for oil in Peace 1961 RD-15-1 River wheat field, September 25, 1961

BC 2009/208 Rigs & Drilling [ca. 1960] RD-15-2

BC 2009/791 Rigs & Drilling: Fort St. John, early gas well [195-] RD-18-1

BC 2009/792 Rigs & Drilling: Drilling for natural gas for [195-] RD-25-2 the Westcoast Transmission Company’s pipeline on the banks of the Peace River

BC 2009/209 Rigs & Drilling: [Oil drillers at work on [ca. 1960] RD-35-1 to – 216 well] 35-2, 37-1 to 38-2, 41-1 to 41-2

BC 2009/217 Rigs & Drilling: Oil drillers at work on well [ca. 1960] RD-46-1 in the Boundary Lake oilfield about 45 miles east of Fort St. John

BC 2009/218 Rigs & Drilling: [Oil driller at work on top [ca. 1960] RD-46-2 of machinery]

BC 2009/219 Rigs & Drilling: Near Fort St. John, 1986 RD-69-1 to –220 February 10, 1986 69-2

BC 2009/221 Rigs & Drilling: [Near Fort St. John] [1986] RD-72-1 to –222 72-2

BC 2009/223 Rigs & Drilling: Boundary Lake Gas RD-82-1-1 to –226 Processing Plant 82-1-4

BC 2009/ Royal Tour: Royal car outside Compressor 1958 RT-1-1 1402 Station No. 1

108 BC 2009/ Royal Tour: Frank McMahon tours Princess 1958 RT-1-2 to 3-1 1403 - 1405 Margaret around Compressor Station No. 1

BC 2009/ Royal Tour: Princess Margaret views Peace 1958 RT-3-2 to 1406-1410, River aerial crossing with Frank M. 6-1 1748, 1751 McMahon

BC 2009/810 Royal Tour: Princess Margaret views Peace 1958 RT-5-1 River aerial crossing with Frank M. McMahon

BC 2009/ Royal Tour: Frank McMahon tours Princess 1958 RT-6-2 1752 Margaret around Compressor Station No. 1

BC 2009/ Royal Tour: Princess Margaret at 1958 RT-7-1 1411 Compressor Station No. 1

BC 2009/ Royal Tour: Princess Margaret receives 1958 RT-7-2 to 8-1 1412 - 1413 flowers from child

BC 2009/ Royal Tour: Frank McMahon tours Princess 1958 RT-9-1 1753 Margaret around inside of Compressor Station No. 1

BC 2009/ Royal Tour: Frank McMahon tours Princess 1958 RT-9-2 to 1414-1444, Margaret around Compressor Station No. 1 26-1 1754

BC 2009/811 Royal Tour: Frank M. McMahon explains a 1958 RT-11-1 map to Princess Margaret

BC 2009/812 Royal Tour: Frank M. McMahon chats with 1958 RT-19-1 Princess Margaret

BC 2009/813 Royal Tour: Frank M. McMahon chats with 1958 RT-25-1 Princess Margaret

BC 2009/ Safety Exercises: Scott Air Pak exercises, 1974 SE-1-1-1 1445 July 1974

BC 2009/ Safety Exercises: Scott Air Pak exercises, 1974 SE-1-1-2 1446 July 1974, (l-r): Roy Hoefner, T. Kato, and John de [Coit?] timing the test

BC 2009/ Safety Exercises: Scott Air Pak exercises, 1974 SE-1-1-3 to 1447 - 1448 July 1974: John Sifton 1-1-4

BC 2009/ Safety Exercises: Scott Air Pak exercises, 1974 SE-1-2-1, 1449, 1451 July 1974: G. Herberg 1-2-3

109 BC 2009/ Safety Exercises: Scott Air Pak exercises, 1974 SE-1-2-2 1450 July 1974: McBergh

BC 2009/ Safety Exercises: Scott Air Pak exercises, 1974 SE-1-2-4 1452 July 1974: Grant Larson with John de [Coit?] timing the test

BC 2009/ Safety Exercises: Rescumatic Safety Drill [ca. 1974] SE-4-1-1 to 1453-1463 5-1-3

BC 2009/ Safety Exercises: Fire Fighting Demo, 1964 1964 SE-7-1-1 to 1464-1475 7-2-6

BC 2009/ Safety Exercises: Fire training, Kobes Creek 1971 SE-15-1-1 to 1476-1481 Stn. 1 & 2, Savona 16-1-2

BC 2009/ Safety Exercises: Fire training [1971?] SE-19-1 1482

BC 2009/274 Looping – Savona: [Construction] 1968 SL-1-2 to 3-2, -280 5-2 to 7-2

BC 2009/281 Looping – Savona: [Construction, pipe 1968 SL-9-2 welding]

BC 2009/294 Gas Plants – Saratoga [ca. 1990] SP-1-2-3, -296 2-1-1, 3-2-3

BC 2009/297 Gas Plants – Saratoga: [View of plant], from [1990] SP-17-1 The Flame (Spring 1990)

BC 2009/ Survey and Scenic: Surveyors near Clinton, 1955 SS-1-1 to 2-1 1633-1635 B.C., July 7, 1955

BC 2009/ Survey and Scenic: Surveyors at Boston Bar 1955 SS-3-1 1636 Creek near Coquihalla Canyon, B.C., July 27, 1955

BC 2009/ Survey and Scenic: Surveyors near Othello, 1955 SS-4-1 1637 B.C., July 27, 1955

BC 2009/ Survey and Scenic: Surveyors at Coquihalla 1955 SS-5-1 to 8-1 1638-1644 Canyon, B.C., July 27, 1955

BC 2009/ Survey and Scenic: Surveying the right-of- 1956 SS-9-1 1645 way near Agassiz in Fraser Valley, February 1956

BC 2009/ Survey and Scenic: Loon Lake [ca. 1955] SS-10-1 to 1646-1651 12-2

110 BC 2009/ Survey and Scenic: Miscellaneous and [1955] SS-13-1 to 1652-1673 unidentified surveys 23-2

BC 2009/522 Gas Plants – Taylor Gas Plant: [Night view] [1991] TP-55-1

BC 2009/523 Gas Plants – Taylor Gas Plant: [View of 1991 TP-56-B-1 [oversize] section of plant at night]

BC 2009/524 Gas Plants – Taylor Gas Plant: [View of 1991 TP-56B-2 [oversize] section of plant at night]

BC 2009/826 Construction – Vancouver Island Pipeline 1981 VIP-4-2 Project: [Vessel with pipeline construction equipment at sea]

BC 2009/610 Construction – Vancouver Island Pipeline 1981 VIP-20-2-1 to -611 Project: [Vessel with pipeline construction 20-2-2 equipment at sea]

BC 2009/612 Construction – Vancouver Island Pipeline [ca. 1980] VIP-20-2-3 to -613 Project: [Map showing pipeline] 20-2-4

BC 2009/614 Construction – Vancouver Island Pipeline [ca. 1980] VIP-21-1 Project: [Pipeline construction]

BC 2009/615 Construction – Vancouver Island Pipeline [ca. 1980] VIP-21-2 Project: [Work crew welding pipes]

BC 2009/616 Construction – Vancouver Island Pipeline [ca. 1980] VIP-22-1 Project: [Work crew lowering pipeline]

BC 2009/617 Construction – Vancouver Island Pipeline [ca. 1980] VIP-22-2 Project: [Work crew moving pipeline]

BC 2009/618 Construction – Vancouver Island Pipeline [ca. 1980] VIP-23-1 Project: [Pipes lined up on ground]

BC 2009/619 Construction – Vancouver Island Pipeline [ca. 1980] VIP-23-2 Project: [Work crew moving pipeline]

BC 2009/620 Construction – Vancouver Island Pipeline [ca. 1980] VIP-24-1 Project: [Work crew connecting pipes]

BC 2009/621 Construction – Vancouver Island Pipeline [ca. 1990] VIP-44-1-1 to -703 Project: Pipeline Construction from 58-1-3 Richmond, B.C.

BC 2009/829 Construction – Vancouver Island Pipeline [1980] VIP-88-1-3 Project: Can Dive

111 BC 2009/827 Construction – Vancouver Island Pipeline [1980] VIP-95-1-2 to -828 Project: [Vessel with pipeline construction 95-2-1 equipment at sea]

BC 2009/825 Construction – Vancouver Island Pipeline [ca. 1990] VIP-S1-1-1 Project: [Stena Apache vessel]

BC 2009/ Awards, Meetings, Parties (Westcoast): 1958 WAM-6-1-3 1745 - 1746 Halloween Party to 8-1-1

BC 2009/ Awards, Meetings, Parties (Westcoast): 1966 WAM-8-2-2 1747 Pageant, (l-r): Crystal Bryant (Princess, Miss Westcoast Transmission), Donella Paige (Queen, Miss Savona Lumber), and Darlene Minor (Princess, Miss Kamloops Yacht Club)

BC 2009/ Westcoast – Building Construction: [1968] WCB-4-1 1759 [Executives break ground]

BC 2009/ Westcoast – Building Construction: [1968] WCB-17-1 1760 [Building during construction]

BC 2009/ Westcoast – Executives, 1970-1979: Mr. Ed [197-] WE1-2-2-3 1744 Johnson

BC 2009/780 Westcoast Executives 1970-1979: Edwin C. 1977 WEI-15B-1 Phillips

BC 2009/ Westcoast – Executives,1970-1979: Edwin 1977 WE1-15D-2, 1739, 1772 C. Phillips [standing in front of pipe and 15C-2 machinery, next to welders]

BC 2009/ Westcoast – Executives, 1970-1979: Edwin [197-] WE1-41-2 1763 C. Phillips (left), President and Chief Executive Officer, and John Anderson, Executive Vice-President and Chief Operating Officer

BC 2009/ Westcoast -- Executives, 1980-1989: John 1985 WE2-56-1, 1740 - 1741 Anderson [portrait] 57-1

BC 2009/ Westcoast – Executives, 1980-1989: Edwin [198-] WE2-85-1-1, 1742 - 1745 C. Phillips [portrait] WE2-87-1-1 to 87-2-2

BC 2009/721 Westcoast – Misc. Events: [Frank M. 1969 WME-35-1 McMahon (centre) and others examine silver tray presented to McMahon at Pacific Petroleums Ltd. event]

112 BC 2009/722 Westcoast – Misc. Events: [Frank M. 1969 WME-35-2 McMahon (second from right) conversing with others at Pacific Petroleums Ltd. event]

BC 2009/718 Westcoast – Misc. Events: [Silver tray 1969 WME-36-1 inscribed “To Frank M. McMahon In Deep Appreciation and Recognition of Your Outstanding Contribution as a Director and Officer of Pacific Petroleums Ltd., 1969”]

BC 2009/719 Westcoast – Misc. Events: [Kelly Gibson 1969 WME-36-2 (left) shaking Frank M. McMahon’s hand at Pacific Petroleums Ltd. event]

BC 2009/720 Westcoast – Misc. Events: [Kelly Gibson 1969 WME-37-1 presenting Frank M. McMahon’s with silver tray at Pacific Petroleums Ltd. event]

BC 2009/ Westcoast – Misc. Events: Westcoast [ca. 1956] WME-73-1 1743 Transmission truck with slogan “Developing the North through Natural Gas”

BC 2009/755 Westcoast – Misc. Events: Compressors 1964 WME-74-1 group meeting, May 1964

BC 2009/756 Westcoast – Misc. Events: Pipeline group 1964 WME-75-1 meeting, May 1964

BC 2009/757 Westcoast – Misc. Events: Meeting [1964] WME-75-2

BC 2009/63- Aerial Crossings – Westpac [ca. 1956] WPAC-1-1 to 82 10-2

BC 2009/83 Aerial Crossings – Westpac: Completing the [ca. 1956] WPAC-11-1 aerial pipeline crossing at Shelly, BC, with men in foreground working on Western Pacific Products pipeline; completed tower and line of Westcoast Transmission natural gas pipeline on the left.

BC 2009/84 Aerial Crossings – Westpac [ca. 1956] WPAC-11-2

BC 2009/85- Aerial Crossings – Westpac [Men working [ca. 1956] WPAC-12-1 86 on the crossing] to 12-2

BC 2009/87 Aerial Crossings – Westpac [ca. 1956] WPAC-13-1

BC 2009/758 Sports – Westcoast: Softball team, 1968 WS-4-1-1 to –761 Vancouver 4-2-2

113 BC 2009/762 Sports – Westcoast: Gals vs. guys softball 1957 WS-10-1-1 to –769 match 10-2-4

BC 2009/770 Sports – Westcoast: Fort Nelson “Gassers” 1976 WS-14-1-1 to –773 hockey team 14-1-4

BC 2009/774 Sports – Westcoast: Peter Stewart Skydiving 1969 WS-22-1-1 to -775 (Pipeline News, Apr./May 1969) WS-22-1-2

BC 2009/776 Sports – Westcoast: Westcoast Transmission 1968 WS-23-1 Co. Ltd. 1968 P.R.L.H.A. Bull Riding Champion

BC 2009/777 C.P. Pickell presents trophy to Bun Burles 1969 WS-23-2 who won the open cutting competition at the Fort St. John stampede (Pipeline News, August 1969)

BC 2009/730 Sports – Golf: Chuck Starr golfing in Fort St. 1969 WSG-1-1-1 John (Pipeline News, June 1969)

BC 2009/731 Sports – Golf: Neil Laidlaw golfing in Fort 1969 WSG-1-1-2 St. John (Pipeline News, June 1969)

BC 2009/732 Sports – Golf: Pipe ‘N Gas Club 1964 WSG-2-1-1 Tournament, Birch Bay, June 20, 1964

BC 2009/733 Sports – Golf: Pipe ‘N Gas Club 1964 WSG-2-1-2 to –739 Tournament, Birch Bay, June 20, 1964 2-2-2

BC 2009/740 Sports – Golf: Vancouver golf tournament 1973 WSG-8-1-1 to -754 9-2-3

BC 2009/ [Fort St. John (?) plant at night] [199-] 1776

BC 2009/712 Aerial view of McMahon Plant, January 1961 1961

BC 2009/713 Fort Nelson Plant, May 1967 1967

BC 2009/714 [Pipeline construction] [195-]

BC 2009/715 [Construction], Fort Nelson Plant, May 1967 1967

BC 2009/716 Aerial view of Pine River Plant, March 1981 1981 [oversize]

BC 2009/717 Annual report 1975/76: [Man at control [1975] station]

BC 2009/817 [Section of plant, showing machinery] [196-?]

114 BC 2009/781 McMahon Cogeneration Plant Official 1993 Opening Ceremony, September 15, 1993

BC 2009/823 Aerial crossing [oversize] [196-?] -824

115 Slides

BC 2009/ Gathering and Transportation: Northern District [ca. 1990] 3129 Pipeline Headquarters

BC 2009/ Taylor N.L.G. Sulphur Plant sign [199-] 3130

BC 2009/ Aerial view of plant 1991 3131

BC 2009/ Westcoast Energy Building [198-?] 3132

BC 2009/ Westcoast Energy Building [ca. 1970] 3133

BC 2009/ Frank McMahon [ca. 1960] 3134

BC 2009/ Unidentified employees cutting 25th 1982 3135 Anniversary cake

BC 2009/ Westcoast Energy logo [ca. 1989] 3136

BC 2009/ Westcoast Transmission logo [198-] 3137

BC 2009/ Powell River [ca. 1990] 3138

BC 2009/ Compressor/Boosters: General – Anatanon at [ca. 1990] 3139 Prince George (unloading)

BC 2009/ Compressor / Boosters: Stn. 2, Willow Flats [ca. 1990] 1 3111

BC 2009/ Pipeline Offices: Pipeline Storage, Charlie Lake [ca. 1987] 2 3112

BC 2009/ Artsy Shot [Westcoast Transmission helmet] [ca. 1987] 8 3113

BC 2009/ Pipeline Transmission: Construction – 1994 10 3114 “Halfway Looping, Fort Nelson Mainline”

BC 2009/ Pipeline Transmission: Right-of-way, Grizzly [1994] 18 3115 Pipeline, south of Pine River

116 BC 2009/ Pipeline Transmission: Right-of-way, Grizzly 1994 35 3116 Pipeline, March 1994

BC 2009/ People at Work: Field Personnel – Sulphur [1994] 56 3117 trains, Pine River

BC 2009/ Pipeline Transmission: Construction – Murray 1994 56 3118 River Crossing, Right-of-Way facing north

BC 2009/ People at Work: Field personnel, Huntingdon [ca. 1987] 87 3119

BC 2009/ People at Work: Field personnel, McMahon [ca. 1987] 131 3120

BC 2009/ Pipeline Transmission: Construction – Grizzly 1994 151 3121 Loop, N. Sukunka Crossing pipe to trench

BC 2009/ Pipeline Transmission: Construction – Grizzly 1994 166 3122 Loop, N. Sukunka Crossing fluming river

BC 2009/ Pipeline Transmission: Construction – Grizzly 1994 195 3123 Loop, N. Sukunka; compl. S. Crossing

BC 2009/ People at Work: Field Personnel, Pine River 1994 216 3124 lowering pipe

BC 2009/ Pipeline Transmission: Construction – Grizzly 1994 216, 236 3125-3126 Loop, N. Sukunka Crossing pipe to trench

BC 2009/ Gas Plants: Aerials, Fort Nelson facing 1994 259 3127 northwest

BC 2009/ Pipeline Transmission: Construction – Grizzly 1994 272 3128 Loop, N. Sukunka Crossing pipe to trench

BC 2009/ Station 9 Tie-in [197-?] 9TI-3, 7,10 2930-2932

BC 2009/ 1964 Peace River Aerial Crossing 1964 AC-1 2933

BC 2009/ Aerial Crossing [unidentified] [197-?] AC-18 2934

BC 2009/ Taylor Aerial Crossing [197-?] AC-46 2935

BC 2009/ Miscellaneous Aerial Crossings [unidentified] [198-] AC-64, 65, 74, 2936-2939 76

117 BC 2009/ Miscellaneous Construction: Bending [ca. 1980] B-35, 54 2940-2940a

BC 2009/ Beaver River Extension 1971 BRE-5, 15 2941-2941a

BC 2009/ Beaver River – Pointed Mountain [1971] BRE-31 2942

BC 2009/ Beaver River Extension 1971 BRE-33, 35 2943-2943a

BC 2009/ Booster Stations: Kobes Booster Station [ca. 1963] BS-13 2961

BC 2009/ Booster Stations: 20” Scraper Barrel, Alaska 1963 BS-18B 2962 Highway Line, May 1963

BC 2009/ Booster Stations: Kobes, Station #2 – Typical 1964 BS-30 2963 wellhead dehydration unit, February 1964

BC 2009/ Coquihalla Loop: Clearing Right-of-Way 1979 CL-13, 41, 54 2944-2946

BC 2009/ Coquihalla Loop: Lowering In 1979 CL-57 2947

BC 2009/ Coquihalla Loop: Pipeline Construction 1979 CL-78 2948

BC 2009/ Coquihalla Loop: Ditching 1979 CL-95 2949

BC 2009/ Coquihalla Loop: Clearing Right-of-Way 1979 CL-143 2950

BC 2009/ Clarke Lake Construction 1964 CLC-2, 3, 6 2964- 2964b

BC 2009/ Compressor Stations: Interior [ca. 1990?] CS-108 2951

BC 2009/ Compressor Stations: [Exterior view] [ca. 1990?] CS-117 2952

BC 2009/ Compressor Stations: Station 8-A Turbine [ca. 1970] CS-120 2953 Control Panel

BC 2009/ Compressor Stations: Station 6-A, 150 Mile [ca. 1962] CS-126 2954 House

118 BC 2009/ Compressor Stations: Station # 9, Rosedale, 1967 CS-137 2955 B.C., March 1967

BC 2009/ Compressor Stations: [Exterior view] [ca. 1980?] CS-148 2956

BC 2009/ Compressor Stations: Station #2 1978 CS-161 2957

BC 2009/ Compressor Stations: Huntingdon Meter Station 1979 CS-175 2958

BC 2009/ Compressor Stations: Huntingdon Meter Station 1986 CS-257 2959

BC 2009/ Compressor Stations: Huntingdon Meter Station 1986 CS-267 2960

BC 2009/ Fort Nelson Extension 1964 FNE-1, 46, 71, 2965-2969 75, 190

BC 2009/ Fort Nelson Plant: Construction, May 1964 1964 FNP-17, 18 2970-2971

BC 2009/ Fort Nelson Plant: January 1964 1964 FNP-21 2972

BC 2009/ Fort Nelson: Plant and terrain [ca. 1990] FNP-51 2973

BC 2009/ Fort Nelson Plant: [ca. 1990] FNP-73 2974

BC 2009/ Fort Nelson Sulphur Plant [ca. 1964] FNP-79 2975

BC 2009/ Fort Nelson: Plant and terrain [ca. 1990] FNP-88 2976

BC 2009/ Fort St. John Plant: [Aerial view of buildings] [ca. 1990] FSJ-20 2977

BC 2009/ Fort St. John Plant: Pipeline Office [ca. 1990] FSJ-22 2978

BC 2009/ Fraser Valley Pipeline Upgrade [1973] FVU-29, 36, 2979-2991 97, 116, 226, 267, 278, 295, 319, 333, 340, 399, 427

119 BC 2009/ Grizzly Valley: Pipeline Right-of-Way [1978] GV-23 2992

BC 2009/ Grizzly Valley: Pipeline Construction [1978] GV-36 2993

BC 2009/ Grizzly Valley: River Crossing Construction [1978] GV-103 2994

BC 2009/ Grizzly Valley: Coating and Wrapping [1978] GV-128 2995

BC 2009/ Grizzly Valley: Pipeline Construction [1978] GV-163 2996

BC 2009/ Grizzly Valley: Pipeline Construction [1978] GV-174 2997

BC 2009/ Grizzly Valley: B.C. Rail Crossing [1978] GV-200 2998

BC 2009/ Grizzly Valley: [Welding] [1978] GV-290 2999

BC 2009/ Grizzly Valley: Opening Ceremonies, 1978 GV-378 3000 November 1978

BC 2009/ Hudson Hope, September 1991 1991 HH-145 3001

BC 2009/ Historic Pipeline Construction [ca. 1990] HPC-1, 6 3002-3002a

BC 2009/ Mile 285 Gas Installation [197-?] IN-59 3003

BC 2009/ McMahon Plant [197-?] IN-74 3004

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-0 2871 Pipeline Project

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-1 2872 Pipeline Project: Foothills Organization Chart

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-2 2873 Pipeline Project: Foothills Segment Companies Sections

120 BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-3 2874 Pipeline Project: Alaska Segment Companies

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-4 2875 Pipeline Project: Segment Company (Southern Legs)

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-4A 2876 Pipeline Project: Segment Company (Southern Legs)

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-5 2877 Pipeline Project: Map showing line from Prudhoe Bay to Chicago & California

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-6 2877a Pipeline Project: Dempster lateral, McKenzie Delta, Beaufort Sea, and Prudhoe Bay

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-7 2878 Pipeline Project: Map of pipe sizes

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-8 2879 Pipeline Project: Proposed rebuild

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-9 2880 Pipeline Project: Proposed rebuild – enlarged

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-10 2881 Pipeline Project: Manpower requirements

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-11 2882 Pipeline Project: Map showing pipe sizes

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-12 2883 Pipeline Project: Canadian section spread

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-13 2884 Pipeline Project: Material quantities

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-14 2885 Pipeline Project: Personnel round trips

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-15 2886 Pipeline Project: Passenger miles

BC 2009/ John Anderson Speech re: Alaska Highway Gas [1979] JA-16B 2887 Pipeline Project: Map of project showing Alaska oil line

121 BC 2009/ Japanese Pipe Arrival 1964 JP-1, 11, 17, 3005-3007 19

BC 2009/ Lowering-in [ca. 1980] LI-37, 41, 49, 3008-3011 58

BC 2009/ Lowering-in: Bow River Crossing [198-?] LI-70 3012

BC 2009/ Lowering-in: Chilliwack, September 1973 1973 LI-77, 81 3013-3014

BC 2009/ Lowering-in: Polyurethane pad at bottom of [198-] LI-93 3015 trench

BC 2009/ Lowering-in: Polyurethane fire protection [198-] LI-94 3016

BC 2009/ [Frank McMahon display] [1990] MAP-120 3017

BC 2009/ McMahon Plant, Taylor, B.C. 1991 MPE-33 3018

BC 2009/ Mini-Sub, Vancouver Island 1972 MS-158 3019

BC 2009/ Prince George: Sulphur Products 1988 PG-10 3020

BC 2009/ Prince George 1964 PG-12 3021

BC 2009/ Prince George: Office 1991 PG-13 3022

BC 2009/ Prince George 1988 PG-25, 47 3021-3022

BC 2009/ Pipe in Transit 1962 PIT-6, 11, 19, 3023-3026 140

BC 2009/ Pine River Plant: Construction [197-] PRP-7, 12, 21, 3027-3032 31, 113, 151

BC 2009/ Pine River Plant, November 1979 1979 PRP-209 3033

BC 2009/ Pine River Plant: Peter Jones in front of plant 1990 P-279 3034 safety sign, March 1990

122 BC 2009/ Pine River Plant: Plant piping [197-] PRP-345, 365 3035-3036

BC 2009/ Pine River Plant: Interior [197-] PRP-406 3037

BC 2009/ Pine River Plant: Aerial, August 1984 1984 PRP-423 3038

BC 2009/ Pine River Plant 1993 PRP-437, 440, 3039-3041 446

BC 2009/ People at work [ca. 1990] PW-10 3042

BC 2009/ [Untitled] 1990 RB-18 3043

BC 2009/ River crossing [ca. 1963] RC-5, 7 3044

BC 2009/ Rigel – Fort St. John: [Exterior and interior [ca. 1990] RL-11, 23, 3045-3074 views] 133

BC 2009/ Right-of-way, Riprap [ca. 1980] ROW-85 3075

BC 2009/ Right-of-way [Construction] [ca. 1980] ROW-181 3076

BC 2009/ Stringing [ca. 1980?] S-24 3076a

BC 2009/ Sikanni River [ca. 1990] SK-17, 48, 3077-3083 [no #], 178, 224, 275, 284

BC 2009/ Pipeline Construction: Tommy Lakes Gasfield 1992 TL-102, 152, 3084-3086 174

BC 2009/ Taylor Sulphur Plant [196-] TP-1A, 3, 6, 3087-3090 33

BC 2009/ Taylor Sulphur Plant: June 1964 1964 TP-81 3091

BC 2009/ Taylor Plant: [Aerial views] [197-?] TP-85, 104 3092-3093

BC 2009/ Taylor Plant: [Exterior view], October 1986 1986 TP-126 3094

123 BC 2009/ McMahon Plant Pumphouse, January 1964 1964 TP-163 3095

BC 2009/ Taylor Complex, October 1986 1986 TP-164 3096

BC 2009/ Taylor Plant: [View of employees] [ca. 1990] TP-230 3097

BC 2009/ Taylor Plant: [Aerial crossing] [ca. 1990] TP-244 3098

BC 2009/ Taylor Plant: [Aerial view] [ca. 1990] TP-245, 259 3099

BC 2009/ Taylor Plant: [View of plant at night] [ca. 1990] TP-319 3100

BC 2009/ [Vancouver Island] 1990 VI-59 to 2888-2898 VI-72

BC 2009/ Vancouver Island Pipeline: Bending crew [ca. 1990] VIP-12 3101 [oversized slide]

BC 2009/ Vancouver Island Pipeline: [Underwater [ca. 1990] VIP-927, 935 3102-3103 construction]

BC 2009/ Welding [196-]- W-48, 65, 104 3104 [197-]

BC 2009/ Westcoast Name Change 1988 WNC-4, 8, 11, 3105-3108 20

BC 2009/ Westpete: Pine River Mustang [ca. 1990] WP-400 to 2899-2916 407, 409 to 418

BC 2009/ Westpete: Kamloops [ca. 1990] WP-648 2917

BC 2009/ Westpete: Alberta [ca. 1990] WP-649 2918

BC 2009/ Westpete: Crystal [1986] WP-650 to 2919-2922 653

BC 2009/ Westpete [ca. 1990] WP-654 2923

124 BC 2009/ Westpete: MEP116 [ca. 1990] WP-655 2924

BC 2009/ Westpete: MEP117 [ca. 1990] WP-656 2924a

BC 2009/ Westpete: Drilling rig near Fort St. John, 1991 WP-657 to 2925-2928 September 1991 660

BC 2009/ Westpete [ca. 1990] WP-661 2929

BC 2009/ Westcoast Signs: Compressor Station 4B, Hixon [ca. 1980] WS-1 3109

BC 2009/ Westcoast Signs: Compressor Station 7, Savona [ca. 1980] WS-2 3110

125