A21 to

Average Speed Camera Study

May 2015

A21 Lamberhurst to Hastings

Issue and revision record

Revision Date Originator Checker Approver Description

First Issue for A 21 April 2015 Internal Use Only

B 22 May 2015 Second Issue

C 28 May 2015 Third Issue

This document is issued for the party which commissioned it We accept no respons bility for the consequences of this and for specific purposes connected with the above-captioned document being relied upon by any other party, or being used project only. It should not be relied upon by any other party or for any other purpose, or containing any error or omission which used for any other purpose. is due to an error or omission in data supplied to us by other parties.

This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it.

A21 Lamberhurst to Hastings

Content

Chapter Title Page

Executive Summary i

1. Introduction 1 1.1 Objective ______1

2. Existing Conditions 3 2.1 Background ______3 2.2 Speed Limits ______3 2.3 Layout and Highway Cross-Section ______3 2.4 Personal Injury Collision Data ______6 2.5 Associated Schemes for the A21 corridor ______6 2.5.1 Planned (funded) Works ______7

3. Proposed ASC Scheme 8 3.1 Overview of Proposed Operating System ______8

4. Proposed Camera Location Sites 10 4.1 Camera Site Locations ______10 4.2 Delivery Design and Engineering considerations ______15 4.2.1 Highway Land ______15 4.2.2 Power Supply ______15 4.2.3 Street Lighting ______15 4.2.4 Communications ______15 4.2.5 Utilities (Statutory Undertakers Plant) Assessment ______15 4.2.6 Structural Assessment (Desktop) ______16 4.2.7 Environmental Assessment (Desktop) ______17 4.2.8 Geotechnical Assessment (Desktop) ______20 4.2.9 Sight Line Assessment ______21 4.2.10 Road Safety and Traffic Engineering Assessment ______21 4.2.11 Speed limit signs ______21 4.2.12 TechMAC maintenance requirements - vehicle hardstanding and access for operatives. ______22 4.2.13 Consultation ______24

5. ASC Complimentary Measures 25 5.1 Identified schemes to enhance Speed Limits and proposed Average Speed Cameras ______25

6. Preliminary Scheme Costs 27 6.1 Capital Expenditure Costs (Equipment Supply, Installation and Commissioning) ______27 6.2 Supplementary Construction Costs ______28 6.3 Design for Construction Considerations ______29 6.4 Maintenance ______30 6.5 Annual Costs and Whole Life Costs ______30

7. Conclusions and Recommendations 31

300274SS05/MAC/ITD/001/C 28 May 2015

A21 Lamberhurst to Hastings

Appendices 32 Appendix A. Project Brief ______33 Appendix B. Vysionics camera and infra-red pole and foundation details ______34 Appendix C. General Layout Drawings (SS-15-8327-1011 – 23) ______35 Appendix D. Camera Site Layout Drawings (SS-15-8327-2601-34) and Typical Grass Grid Hardstanding Detail for Maintenance Vehicles (SS-15-8327-100) ______36 Appendix E. Extracts from Area 4 BBMMjv ‘MAYRISE’ Database ______37 Appendix F. Desktop Environmental Assessment ______38 Appendix G. BBMMjv LNMS Scheme Drawing Numbers LNMS/13-7058 1201 to 1207 ______39 Appendix H. BBMMjv A21 ASC Scheme Estimate ______40

300274SS05/MAC/ITD/001/C 28 May 2015

A21 Lamberhurst to Hastings

Executive Summary

The A21 route south of the Lamberhurst Bypass is rural in nature, serving the main urban areas of , Hurst Green, , John’s Cross and, Woodman’s Green. It also serves as the main access route to Hastings from and the north. Highways England has a desire to install average speed cameras (ASCs) along part of the A21 corridor over a distance of approximately 26km.

Further to discussions between prospective supplier, Vysionics ITS, Highways England and Balfour Beatty Mott MacDonald joint venture, Vysionics ITS has prepared a budgetary proposal for a SPECS3 VECTOR speed management and enforcement scheme for the A21. The SPECS3 VECTOR solution would be used to monitor and control vehicle speeds on the A21 between Lamberhurst and Hastings.

The scheme comprises the provision of 34 ASCs placed along the route, essentially at locations where there is a change in local speed limit.

Principally, the proposed ASC locations are suitable, however, a number of matters need to be addressed further prior to the scheme being implemented.

. Consultation - Further structured consultation with key stakeholders (local MP, Sussex Safer Roads Partnership, local parish councils and adjoining property owners where ASCs are proposed to be situated) is required.

. Environmental - There are a number of matters that will be required to be addressed further including the application of the Record of Determination / Notification of Determination (ROD/NOD) process and the preparation of an appropriate assessment screening matrix (AASM). Part of the study area is also close to an area of outstanding natural beauty (AONB) and there are likely to be impacts in terms of cultural heritage and nature conservation. This will therefore require further environmental assessment reporting as the scheme progresses.

. Geotechnical - The majority of the cutting slopes are likely to involve some minor cutting and re-grading of the slope and installation of some form of erosion protection and/or reinforcement. The foundations in embankments will be more complicated, which may require placing additional fill materials or increasing the depth of foundations. Therefore further geotechnical assessment reporting will be required as the scheme progresses.

. Land ownership - Initial assessment of land boundary information suggests that land required for works is within the public highway and therefore no land acquisition is considered necessary.

300274SS05/MAC/ITD/001/C 28 May 2015

i

A21 Lamberhurst to Hastings

. Structural Assessment - Preliminary information supplied by Vysionics which has been reviewed internally by BBMMjv is regarded as being appropriate to task. Further detailed structural assessment of the camera foundations and mountings at individual sites will be required as the scheme progresses. Furthermore, as the current intention is to provide ASCs on passively safe posts, on the whole, no significant provision of new vehicle road restraint systems (VRRS) is required.

. Statutory Undertakers’ Plant/Apparatus - The principal concern is the availability or requirement to provide a robust, independent power supply to a number of individual camera site locations. This is likely to require the provision of additional ducting and cabling.

. Communications - This will be required between the individual camera locations in order to process speed data ascertained from the individual ASC sites. Historically, this has been achieved through fixed communications (e.g. BT phone line). However, it is understood that there is strong mobile communication signal available from at least one network. Therefore, the proposed ASC operation will communicate by means of a 3G data SIM, built into the camera head.

. Maintenance - Further consideration will need to be given in terms of the provision of vehicle hardstanding such that operatives can periodically access the ASC sites should they need to do so.

. Existing Speed Limits - There are a number of current local proposals through some of the settlements on the A21 route (e.g. Hurst Green, ) where existing speed limits are to be reviewed / revised. Furthermore, this proposed ASC scheme will require the provision of additional signing to advise drivers of the enforcement measures in place. Therefore, coordination will be needed to ensure that changes to signing are complimentary and should be addressed through further consultation with Sussex Safer Roads Partnership.

300274SS05/MAC/ITD/001/C 28 May 2015

ii

A21 Lamberhurst to Hastings

1. Introduction

1.1 Objective

Highways England has commissioned the Balfour Beatty Mott MacDonald joint venture (BBMMjv) to investigate the provision of average speed cameras (ASCs) on the A21, south of Lamberhurst to Hastings (the northern suburb of Baldslow) (see Figure 1.1 overleaf). The objective is to advance to concept/outline design stage, a layout for camera locations and to identify the principal constraints to further scheme development.

This report considers, amongst other matters, the following:

 Land requirements (including verge widths);

 Visibility (to and from the cameras);

 Extent of speed limit;

 Utilities and power supply;

 Geotechnical constraint; and

 Environmental impacts.

It does not seek to justify the appropriateness of the scheme in terms of:

 Assess the road safety record of the route section, specifically, analysis of personal injury accident data; or

 Undertake any journey time analysis.

A copy of the study proposal is shown in Appendix A.

The structure of this report is as follows:

Section 2 – overview of existing conditions;

Section 3 – overview of the proposed scheme;

Section 4 – proposed camera location sites;

Section 5 – ASC Complimentary Measures;

Section 6 – Preliminary Scheme Costs; and

Section 7 – Conclusions and Recommendations.

300274SS05/MAC/ITD/001/C 28 May 2015

1

A21 Lamberhurst to Hastings

2. Existing Conditions

2.1 Background

The A21 forms part of a north-south link between the M25 at Junction 5 near in West and the Hastings Borough boundary on the south coast in . The proposed scheme relates to the specific section south of the Lamberhurst Bypass the route is rural in nature serving the main urban areas of Flimwell, Hurst Green, Robertsbridge and John’s Cross plus a number of other local villages. It also serves as the main access route to Hastings from London and the North.

The route has historically suffered from a poor collision record and anecdotally, ranks high as one of the Highways England’s routes with such a record. It is also often experiences poor journey time reliability due to its susceptibility to incidents.

ASCs have been in operation on a number of major highway schemes for many years now, essentially in support of traffic management measures (i.e. reduced speed limits) during the construction stage. Most recently, Highways England has witnessed a high degree of compliance with temporary speed limits placed for the construction works associated with the A23 Handcross to Warninglid improvement in West Sussex.

Senior officers in Highways England, now wish to investigate the introduction of similar ‘permanent’ measures on sections of the all-purpose trunk road (APTR) network following consultation with key local stakeholders such as elected members and representatives of safety camera partnerships.

The section of the A21 in East Sussex is almost 22km in length, is and generally rural in nature with eight urban/semi-urban sections. These urban/semi urban sections are: Flimwell, Hurst Green, Robertsbridge, John’s Cross, Woodman’s Green and .

2.2 Speed Limits

Commensurate with the horizontal and vertical alignment of the A21 throughout the study length and the provision of frontage access and activity, there are a range of posted speed limits in place. The principal settlements of Hurst Green and, John’s Cross have a 30mph posted speed limit, whilst Flimwell and Kent Street are subject to a 50mph posted speed limit.

The remaining sections of the A21 comprise a mix of 40mph, 50mph, 60mph posted limits (or National Speed Limit applies).

2.3 Layout and Highway Cross-Section

All of the A21 throughout the scheme extents comprises rural single 2-way (S2) carriageway except for a short section of (D2AP) north of Flimwell (with a 60mph posted speed limit). The principal settlements noted above, have a high degree of frontage access and associated pedestrian and vehicular activity. Through Hurst Green there is on road parking by local residents and access is required to a range of premises including residential, retail, commercial and educational.

Outside of these settlements, the A21 often has a sinuous alignment both in terms of its horizontal and vertical profile. Being rural in nature, there is a diverse mix of traffic types, including agricultural vehicles and there is little provision for pedestrians and other non-motorised users (NMUs). During hours of darkness there is little or no street lighting present.

300274SS05/MAC/ITD/001/C 28 May 2015

3

A21 Lamberhurst to Hastings

The A21 is mostly unlit during the hours of darkness. However there is a system of high pressure sodium lighting at: -

. The A268 junction in Flimwell;

. Northbridge Street , Robertsbridge;

. John’s Cross Road junction south of Robertsbridge,

. John’s Cross Roundabout; and

. The section south of the A28 Westfield Lane junction.

The numerous bends and crests together with the narrow verges have resulted in limited forward visibility at various sections of this route.

The highway cross-section is often limited to 3.5m in each direction with or without a highway edge line or hard strip.

At the northern end of the scheme corridor, south-east of Lamberhurst, the carriageway is divided by a central median and further south there is a wide S2 section of carriageway which forms the Robertsbridge bypass. These sections are subject to the national speed limit for a single carriageway.

Figure 2-1 overleaf shows an overview of the change in speed limits throughout the scheme corridor.

300274SS05/MAC/ITD/001/C 28 May 2015

4

A21 Lamberhurst to Hastings

Constraints such as cost, journey reliability and environment have impacted on the justification of improvement schemes on the A21. The resultant development of the route, as a whole, is inconsistent and has not kept-up with comparable routes.

Provision for NMUs is scant with many properties that access directly the A21 having no foot/cycleway or crossing facilities. This limits local travel options and fosters car dependency, the result manifesting in a concentration of collisions in the built-up areas. Established and growing demand in leisure and utility cycling cannot be met and bus services are excluded from the most needy patrons.

Overall, from the motorists’ perspective, a scarcity of such facilities detracts from the appearance of the highway leading to a failure to recognise the need to drive carefully.

2.4 Personal Injury Collision Data

From the BBMMjv report ‘A21 Project Plan Safety Improvements’ dated September 2014, The study summarised the personal injury collisions (PICs) for the previous past five calendar years (understood to be 2009 – 2013). These were recorded as follows:

• A total 210 PICs. • Of these, there were 10 Fatal, 49 Serious and 151 Slight. • Darkness PICs accounted for 60 (29%). • Inappropriate speed was recorded as a primary contributory factor in 46 of these PICS (22%). • Inappropriate speed/behaviour as a contributory factor accounted for 134 PICs (64%). • Nose to Tail, Access Conflicts and Loss of Control accounted for the most prevalent collision types.

It is not clear as to the exact extent of the search area. A review of PICs has not been included in this current study at this stage.

The same September 2014 report acknowledges that case studies of existing ASC sites demonstrate a potential reduction of between 40% and 70% in all PICs. It, in turn, referred to the earlier 2010 Local Speed Limit Review of the A21, which estimated a reduction of 42% in all PICs as a consequence of the installation of ASCs.

2.5 Associated Schemes for the A21 corridor

According to the A21 Project Plan Safety Improvements study, the following is a summary list of proposed improvement schemes for the A21 corridor within the study area:

300274SS05/MAC/ITD/001/C 28 May 2015

6

A21 Lamberhurst to Hastings

2.5.1 Planned (funded) Works

Works currently planned for construction by March 2015:

North of Hurst Green to Swiftsden

New planned 50 mph speed limit, from the existing 30mph gateway to the north of Hurst Green to include the A229 at Coopers Corner and to include the BP garages and continue to include the properties to the north of the B2099.

Whatlington/Woodman’s Green

New planned extension of the existing 40mph speed limit to the south of the village of Woodman’s Green to include Stream Lane.

Paygate Lane

New planned extension of the existing 50mph speed limit from Kent Street to the north of the B2244, to include the semi urban area to the north of Kent Street.

Mobile speed limit enforcement

At this stage, it is not clear as to whether the provision of enforcement bays (including signage) will be required and this will become evident following additional consultation with the Sussex Safer Roads Partnership.

Renewal Programme

It is understood that there is currently an Area 4 renewal programme for the A21 including resurfacing, drainage and footway repairs, though the exact location and nature of such improvements has not yet been defined by the Area 4 BBMMjv team.

300274SS05/MAC/ITD/001/C 28 May 2015

7

A21 Lamberhurst to Hastings

3. Proposed ASC Scheme

3.1 Overview of Proposed Operating System

SPECS is a speed enforcement system, which uses linked Automatic Number Plate Recognition (ANPR) cameras to monitor the average speed of traffic over a section of road, or network of roads. The Highways Agency has implemented both temporary and permanent SPECS installations on a variety of routes in order to improve road safety and to encourage more reliable journey times. ASCs are a beneficial tool as they provide a visual cue to road users to observe speed limits and they are effective over greater distances than fixed or mobile enforcement systems.

SPECS cameras continuously capture images of vehicles as they pass through the field of view. From this, ANPR is used to capture vehicle registration plate details and when the same vehicle is recorded by any other camera connected to the system, the average speed of the vehicle is calculated over the known baseline distance. If a vehicle passes two or more ASCs within a time, determined by the separation of the cameras and the speed limit, then the vehicle’s details are recorded and sent to a remote operator who may issue a Notice of Intended Prosecution (NIP).

Highways England supplier, Vysionics ITS, has developed the SPECS3 VECTOR, which is a fully self- contained compact intelligent camera which integrates all of the functionality of the roadside equipment into a single camera enclosure. One VECTOR camera is the functional equivalent of two current SPECS3 cameras connected to a single SPECS3 POD outstation. This offers many benefits such as reduced roadside structures, installation and equipment cost and higher reliability along with some key technical advances.

Cameras can be installed in front or rear-facing orientation and violations can be recorded between multiple locations and multiple lanes within the system. Rear facing cameras enable motorcycle number plates to be read.

Figure 3-1: Configuration types for SPECS3 VECTOR operation

Source: Vysionics Proposal Document (P2143P), September 2014.

300274SS05/MAC/ITD/001/C 28 May 2015

8

A21 Lamberhurst to Hastings

Each camera unit has an infrared ANPR camera and an infrared illuminator, which enables number plates to be read. A colour day/night overview camera is also included, which enables overview images to be captured in daylight and in most street lit environments. Infrared floodlights can be installed where street lighting is not available and visible lighting is undesirable, making overview image capture possible in complete darkness. The key features of this system are:

 Every camera can be an entry and/or an exit camera;  Every camera can cover up to 2 lanes of single or bi‐ directional traffic;  All offence data is collected remotely;  Journeys can be calculated between any valid camera locations;  Forward or rear facing links can be configured (cannot mix direction in one link). Rear facing cameras can also record motorcycle number plates;  Any entry lane to any exit lane can be monitored;  Enforcement links can be from 75m to 20km+;  SPECS3 VECTOR can be operated alongside existing SPECS3 equipment; and  Results in lower installation costs when compared to earlier versions of the SPECS system.

Vysionics camera and infra-red pole and foundation details are shown at Appendix B.

300274SS05/MAC/ITD/001/C 28 May 2015

9

A21 Lamberhurst to Hastings

4. Proposed Camera Location Sites

4.1 Camera Site Locations

Table 4-1 overleaf provides a summary of proposed camera locations based on desktop and site survey work undertaken by Vysionics in their document ‘Budgetary Proposal SPECS3 VECTOR’ (Doc. Ref. P2143P, dated September 2014).

The ASCs are proposed at 34 sites which will cover each change of speed limit. The VECTOR3 system proposed by Vysionics now requires only one camera post per site, and that the proposed posts for mounting of these cameras are passively safe. Therefore, on the whole, no vehicle road restraint systems (VRRS) will be required.

Site locations are shown contextually in Drawing Numbers SS-15-8327-1011 to 1016 (at Appendix C) and individually in Drawing Numbers SS-15-8327-2601 to 2634 (at Appendix D).

300274SS05/MAC/ITD/001/C 28 May 2015

10

A21 Lamberhurst to Hastings

Table 4-1: Summary of proposed ASC sites based on Vysionics Survey Assessment of A21 corridor

(TQ)

Red (IR) Red

-

MM Camera MM Ref.No. Camera Location (Section) Gridref. Cameras Live ZoneCameras Infra Columns VergeCent / Reserve Setbackfrom carriageway Roadwidth (m) Comments (Power Supply)

Section N/B There is established street lighting at Scotney Castle Roundabout to 67987,35011 >2m 7.1 the north. Therefore, approximately 100m of ducting and supply may 1 1 North 2 0 2 Verge be required. Section S/B Limited due to 69559,33734 7 Possible supply from overhead lines. 2 1 Mid 0 2 2 Verge fence Section 71446,31855 Cent >2m 24m ‐ Illuminated supply at end of National Speed Limit section 3 1 2 0 2 Res incl. South cent res Section N/B 2 North 71531,31715 >2m 7.35 Illuminated supply at end of National Speed Limit section Verge 4 N/B 1 0 1 Section S/B 2 North 71549,31729 >2m 3.9 Illuminated supply at end of National Speed Limit section Verge 5 S/B 1 0 1 Section There is likely to be a supply available due to the presence of traffic 2 71545,31272 S/B >2m 13 6 2 0 2 signals 75m to the south. South Verge

Section There is likely to be a supply available due to the presence of traffic 71607,31025 N/B >2m 9.7 7 3 North 0 2 2 signals 150m to the north. Verge

Section 71956,29616 S/B >2m 8.5 Potential supply from JTIC equipment #2490 8 3 Mid 2 0 2 Verge

300274SS05/MAC/ITD/001/C 28 May 2015

11

A21 Lamberhurst to Hastings

(TQ)

.

Red (IR) Red

-

MM Camera MM Ref.No. Camera Location (Section) Gridref Cameras Live ZoneCameras Infra Columns VergeCent / Reserve Setbackfrom carriageway Roadwidth (m) Comments Section S/B 3 72458,29139 >2m 8 Nearby overhead lines, but in field so potential wayleaves required Verge 9 South 2 0 2 Section 72570,28926 S/B Nearby power lines, but in adjoining field / property so potential 10 4 North 2 0 2 Verge >2m 8 wayleaves required. Alternatively, feeder pillar on opposite side of road Section S/B Feeder pillar north of A229 at Cooper’s Corner, but could be removed 4 73274,28012 >2m 11 Verge under proposed improvements. 11 South 2 0 2 Section N/B limited due to There is likely to be an established supply in Hurst Green. Therefore, 73242,27792 8 12 5 North 2 0 1 Verge hedgerow potentially an additional 300m of ducting and supply may be required. Section S/B 5 Mid ‐ 73353,27388 1m ‐ grassy area 6.5 Nearby street lighting supply in Hurst Green. Verge 13 North 2 0 1 Section S/B 1m ‐ back of 5 Mid ‐ 73388,27147 Traffic Signals Supply from adjacent PUFFIN crossing to the north. Verge f/way (TBC) 14 South 2 0 1 7 Section 73542,26683 N/B 1m ‐ back of 15 5 2 0 1 Verge f/way (TBC) 8 Potential supply from 20mph variable message sign South Section N/B 1m ‐ back of 73571,26510 Potential supply from 20mph variable message sign 16 6 North 2 0 2 Verge f/way (TBC) 8 Section S/B Possible power from pole near Beach House Lane, approximately 6 73767,25932 >2m Verge 150m to the north 17 South 2 0 2 8

300274SS05/MAC/ITD/001/C 28 May 2015

12

A21 Lamberhurst to Hastings

(TQ)

Red (IR) Red

-

MM Camera MM Ref.No. Camera Location (Section) Gridref. Cameras Live ZoneCameras Infra Columns VergeCent / Reserve Setbackfrom carriageway Roadwidth (m) Comments

Section S/B Possible power from pole near Beach House Lane, approximately 73778,25820 18 7 North 2 0 2 Verge >2m 8 320m to the north Section S/B 7 74007,24539 Very limited Traffic signals supply estimated to be approximately 250m away Verge 19 South 2 0 2 8 Section S/B No immediate power supply source. Street lighting at Northbridge 74149,23847 >1.5m 20 9 North 0 2 2 Verge 8 Street roundabout approximately 300m to the north (TBC)

Section 73850,22515 S/B Potential power supply from pole supply nearby at Poppinghole Lane 21 9 Mid 2 0 2 >2m 8.7 Verge Section Nearest potential supply at John’s Cross approximately 150m to the 9 74246,21442 S/B 22 2 0 2 >2m 7.8 south (TBC) South Verge Section 74945,20788 N/B 23 11 2 0 2 Verge >2m 7.5 Potential supply provided from existing illuminated sign, TSR&GD 505 North Section 11 75925,19992 S/B 6.4 Power supply available on western side of road 24 2 0 2 >2m South Verge Section 76085,19756 25 12 2 0 2 N/B >2m 6.5 Possible power supply from local source (TBC) North Verge Section 76680,18784 12 Possible power supply from local source in Whatlington approximately 26 2 0 2 N/B >2m 7 500m to the north (TBC) South Verge

300274SS05/MAC/ITD/001/C 28 May 2015

13

A21 Lamberhurst to Hastings

(TQ)

Red (IR) Red

-

MM Camera MM Ref.No. Camera Location (Section) Gridref. Cameras Live ZoneCameras Infra Columns VergeCent / Reserve Setbackfrom carriageway Roadwidth (m) Comments Section Possible power supply from local source in Whatlington approximately 13 76786,18614 S/B 27 2 0 2 Very Limited 7.3 600m to the north (TBC) North Verge Section TBC - Possible power supply from local infrastructure in 13 78030,17117 S/B 28 2 0 2 Limited 8 Seddlescombe approximately 150mto the south. South Verge Section 78213,16812 29 14 2 0 2 N/B 1.5m (Approx.) 10 Potential Traffic Master supply (opposite Crazy Lane) North Verge Section 78521,16102 30 14 2 0 2 S/B Very Limited 6.5 TBC – Possible power supply from local infrastructure. South Verge Section 78805,15751 31 15 2 0 2 N/B >2m 6.5 JTIS Camera #4336 North Verge Section 79084,15306 32 15 2 0 2 N/B 1.5m (Approx.) 6.5 Supply for existing VAS ‐ note passive safe disconnect chamber South Verge Section 79209,15080 16 TBC – this is situated approximately 150m south of the settlement of 33 2 0 2 N/B >2m 6.5 Kent Street North Verge Section 79876,13609 34 16 2 0 2 N/B >2m TBC Adjacent powered street lights. South Verge

300274SS05/MAC/ITD/001/C 28 May 2015

14

A21 Lamberhurst to Hastings

4.2 Delivery Design and Engineering considerations

4.2.1 Highway Land

Information obtained from the BBMMjv Area 4 land records database indicates that proposed sites for the ASCs are within area designated as public highway and it is understood that no additional third party land will need to be acquired.

4.2.2 Power Supply

The locations of many of the cameras are likely to be rural. As such, current permanent electricity supply may not be provided in places. Therefore, a permanent, robust electrical supply will be required.

Table 4-1 above identifies a number of locations where an additional power supply is required and as such as part of the scheme development phase, new feeder pillars to all locations are to be installed.

Reference should also be made to nearby powered assets in the Area 4 BBMMjv inventory which are shown in extracts from the MAYRISE database at Appendix E.

4.2.3 Street Lighting

With respect to street lighting, enforcement during the hours of darkness will be required. As the route corridor is predominantly unlit, this will require infra-red (IR) lighting units. As part of the proposal, Vysionics will supply passively safe lighting columns with infra-red lighting units to all locations, to enable such enforcement. Furthermore, Vysionics has assumed that BBMMjv will install these and that Vysionics will align the lighting as part of the camera installation process.

4.2.4 Communications

With respect to mobile or fixed communications as the A21 is predominantly a rural environment and as such, can be susceptible to poor mobile signal. However, Vysionics have identified that there is strong 3G signal coverage from at least one network provider.

SPECS3 outstations require a network connection with a fixed IP address, usually via a 3G data SIM, built into the camera head. Vysionics testing and surveys show that all sites do have a 3G communications signal available on at least one mobile network (although this was weak at some locations).

Mott MacDonald understands that data is retained by the camera unit (outstation) and communicated via a 3G signal when the relevant signal is strong enough.

4.2.5 Utilities (Statutory Undertakers Plant) Assessment

No specific New Roads and Street Works Act (NRWSA) searches have been carried out in connection with this study. However, preliminary information has been sought from a database of statutory undertakers plan maintained by BBMMjv as part of the Area 4 commission.

300274SS05/MAC/ITD/001/C 28 May 2015

15

A21 Lamberhurst to Hastings

Drawing Numbers SS-15-8327-2601 to 2634 show the proposed layout for the respective ASC sites and the presence of utilities plant obtained from previous enquiries of the A21 corridor (from current records held by BBMMjv).

Nevertheless, there will be a requirement to issue the appropriate C1/C2 NRSWA notices as the scheme develops. From this, specific proposals can be obtained from the relevant power supply company.

Vysionics has indicated that independent power supplies (solar panel or hydrogen fuel cells) can be incorporated at individual sites however, it would be desirable to have a robust independent network supply. This will be assessed and determined as part of value engineering and costs of power supply determined at detailed design.

4.2.6 Structural Assessment (Desktop)

Details pertaining to the ASC pole and foundations have been developed by Vysionics. These have also been the subject to an internal review by Mott MacDonald.

The key points arising from this initial BBMMjv review are as follows:

 Masts may need ‘Structures Approval in Principle’ due to their height.

 The poles on which the proposed ASCs are to be mounted are 6 or 9m high. The majority of the load on the foundation is due to wind pressure however, wind loading should not be a material factor due to both the distance from the coast and the height above sea level.

 Proposed footings for the ASC posts are generally small pad foundations.

 It is understood that the posts/columns shown in the Vysionics Drawing No.s S130622-1 and S130622-are passively safe. Therefore, it is unlikely that specific VRRS will be required.

 An anomaly over the planting depth for the column has been identified. Drawing Numbers S130622-1 and S130622-2 provided by Vysionics shows that the metal column will extend 1200 mm into the ground. Section AA of the supplied Waterman Moylan drawing indicates this as 1m.

 From the CCTV mast design, the Waterman Moylan drawings supplied shows a planted foundation which BD94/07 does NOT permit for CCTV masts. This is preclusion is understood to be so as to limit lateral deflection/vibration in order to aid picture quality.

 An analysis undertaken for the spread footing has assumed the base depth of 1.2 m to be consistent with the SAPA drawings provided by Vysionics. This gives a slightly larger base with plan dimensions of 1m x 1m. An allowable soil bearing pressure of 80 kN/m2 has been assumed.

 The adequacy of the Vysionics (SAPA) posts has not been assessed. This is understood to be a proprietary product and therefore assumed that the supplier has already determined allowable loads.

300274SS05/MAC/ITD/001/C 28 May 2015

16

A21 Lamberhurst to Hastings

4.2.7 Environmental Assessment (Desktop)

The proposals have also been the subject of a desktop environmental assessment. The key findings are presented in Table 4-2 below.

Table 4-2: Summary of Desktop Environmental Assessment

Summary Comment The proposed Scheme is located within a “sensitive Area”, High AONB and the total Scheme footprint is likely to be more than a hectare in area. Therefore the RoD/NoD Requirement for a process would be triggered. Record of Determination (RoD) and Notice of Determination (NoD) The proposed scheme would pass over watercourses which flow downstream into Dungeness to Pett Level Special Protection Area (SPA) located approximately 30km Appropriate Assessment southeast and Dungeness SPA and Special Area of Conservation (SAC) located Screening Matrix (AASM) approximately 32km south east.

Therefore an Appropriate Assessment Screening Matrix (AASM) would need to be completed following receipt of the final design of the proposed scheme. Air Quality The proposed Scheme is not located within an Air Quality Management Area (AQMA). Brief Overview of Likely Approximately 600 residential receptors have been identified within 200m of the Environmental proposed Scheme. Constraints The proposed Scheme is currently at the feasibility stage, and as such, the duration of works and TM details are not known. Adverse impacts would be anticipated as a result of construction activities due to the temporary production of dust.

The proposed Scheme would not alter any junction layout or carriageway widths. However, there is the potential for a permanent change in traffic speeds as a result of the proposed scheme, with the proposed scheme likely to result in altered speeds for all vehicle types (i.e. including HGV’s and cars). Therefore there is the potential for operational effects on all 600 residential receptors. This will be assessed in further detail within the IRF 281a Environmental Scoping Assessment. Cultural Heritage One Conservation Area (Robertsbridge Conservation Area (located approximately 50m

west), one Registered Park and Garden (Scotney Castle Grade I Listed, located adjacent to the east) and over 100 Listed Buildings have been identified within 300m of the proposed Scheme (of which approximately have been identified within 20m of the proposed Scheme). Within 1km of the proposed Scheme a further 400+ Listed Buildings, two Scheduled Ancient Monuments (SAM) and one Conservation Area have been identified.

Various Archaeological remnants have been found within the 1km of the Scheme including Medieval Brickworks 10m to the east of the proposed Scheme. No Registered Battlefields or World Heritage Sites have been identified within 1 km of the proposed Scheme.

Despite the close proximity of Scotney Castle Grade I Listed Park and Garden (adjacent to proposed ASC, drawing SS-15-8327-1011) to the Scheme, effects on this heritage feature are unlikely to be significant given good existing screening conditions, with a large number of trees either side of the road. However consultation with the local planning authority is likely to be a requirement, given the height of the ASC structures and the Registered Park and Garden adjacent to the proposed location of an ASC.

300274SS05/MAC/ITD/001/C 28 May 2015

17

A21 Lamberhurst to Hastings

Effects on Robertsbridge Conservation Area and all nearby Listed Buildings would be addressed on a case by case basis with potentially significant effects on their local character and setting (effects are not likely on Listed Buildings structural integrity) with the installation of a 6m high ASC’s. Effects on these heritage features would be assessed in full within the IRF 281a Environmental Scoping Assessment.

Landscape The entirety of the proposed Scheme is located within National Character Area 72 High Weald and High Weald Area of Outstanding Natural Beauty (AONB). A number of visual receptors are located within the proposed works area. Views are largely intermittent along the A21 alignment with hedgerows and trees present alongside the majority of the A21 road.

Adverse effects are likely upon the High Weald AONB and on visual receptors (variable in location) within the vicinity of the Scheme, as a result of the installation of 6m high ASC structures. Measures to minimise effects could be incorporated within the scheme design, this could include siting of cameras (to avoid key views) and sensitive colouring of cameras where possible. Effects on these landscape features and visual receptors would be assessed in full within the IRF 281a Environmental Scoping Assessment.

Since the entirety of the proposed scheme would be located within the High Weald AONB, the proposed Scheme would also require consultation with High Weald AONB before works can proceed.

Geology and Soils Excavations may be required. No geologically sensitive receptors have been identified within 50m of the proposed works. However, the section of the A21 road likely to be effected was constructed before 1990. Therefore there is the potential for contaminated land to be present, as fill material used before 1990 can be from an unknown source, with the potential for hazardous material being previously used. This would be addressed within the IRF281 Environmental Scoping Assessment. No geologically sensitive sites are present within 50m of the proposed Scheme, and therefore, impacts on the local geology and soil would be negligible once the proposed scheme is operational.

Nature Conservation The proposed Scheme would pass over watercourses which flow downstream into Dungeness to Pett Level SPA (located approximately 30km southeast) and Dungeness SPA and SAC (located approximately 32km south east). Two Sites of Special Scientific Interest (SSSI) have been identified within close proximity of the proposed Scheme including: Combwell Wood SSSI (located approximately 10m from A21 near High Weald) and Scotney Castle SSSI (located approximately 5m from A21 near Lamberhurst). Therefore further assessment in the form of an Appropriate Assessment Screening Matrix (AASM) would need to be completed following receipt of the final Scheme design.

Non-statutory ecological designations have been identified within 300m of the proposed Scheme including: Sussex and Kent coastal and floodplain grazing marsh, lowland meadows, ancient and semi-natural woodland, deciduous woodland, traditional orchard and wood pasture and parkland BAP priority habitats.

The presence or likely absence of protected species in the area is unknown. However, over 100 ponds have been identified within 500m of potential ASC locations (approximately 76 within 250m). Due to the requirement for excavations within the highways verge and likely ducting requirements for the Scheme, further habitat suitability appraisal would be required to determine the likely presence/ absence of GCN within the work extents, and to determine the requirement for targeted ecological surveys.

300274SS05/MAC/ITD/001/C 28 May 2015

18

A21 Lamberhurst to Hastings

ASCs are anticipated to be installed within close proximity to Combwell Wood SSSI and Scotney Castle SSSI. The qualifying features of Combwell Wood SSSI are unlikely to be effected by the proposed Scheme. Dormice are a qualifying feature of Scotney Castle SSSI. Therefore, although it is unlikely that works would be undertaken outside of HA land in those locations (thus ruling out the requirement for CROW assent); adverse effects on the qualifying features of Scotney Castle SSSI could result from the Scheme. In addition, further habitat suitability appraisal would be required to determine the likely presence/ absence of dormice within the work extents, and to determine the requirement for targeted ecological surveys.

Materials If works fall above the BBMMJV £150k threshold, a Site Waste Management Plan (SWMP) would be required.

Noise and Vibration Over 1000 residential receptors have been identified within 500m of the proposed Scheme. Two areas designated as ‘first priority locations’ (Whisketts Farm and Stonecrouch) and two ‘other’ priority locations (High Weald) would be located within the Scheme extents. The effect of the proposed Scheme upon the noise environment for these properties would be dependent upon the duration of the works and the type of construction plants involved. Details regarding time and duration of works are yet to be confirmed. The potential requirement for working time restrictions would be controlled by setting out appropriate mitigation measures in Appendix 1/9 ‘Control of Noise and Vibration’ of the specification of highways works.

The measures would be agreed in consultation with the Local Authority’s Environmental Health Officer (EHO), and where appropriate, mitigation in accordance with BS5228 ‘Code of Practice for Noise and Vibration Control on Construction and Open Sites’ would be specified once sufficient construction details are known.

Adverse effects during construction are anticipated with a number of residential receptors located within close proximity of works. The permanent change in speed limits and installation of ASCs has the potential to result in noise level changes, with the potential for a change in traffic speeds. The addition of ASCs to the A21 road also has the potential to discourage vehicle travellers to continue using this road and could increase traffic flows on other roads in the wider area. These issues would be fully addressed following receipt of the final design of the Scheme within the IRF 281a Environmental Scoping Assessment.

Effects on Travellers No cycle paths have been identified alongside the proposed scheme. However, various footpaths and Public Rights of Way have been identified within the vicinity of the proposed scheme in residential areas such as Hurst Green. Details of TM and duration of works are yet to be confirmed.

Overall effects on all travellers are not likely to be significant as a result of the proposed scheme. However, the aim of the Scheme would be to improve road safety for users, and as a result, Beneficial effects are anticipated for All Travellers following the implementation of the scheme. Impacts on non-motorised users are likely to be minimal during construction and operation periods.

Community and Private Assets The section of A21 road affected several settlements (including Hastings, Robertsbridge, Hurst Green etc.) and passes within 500m of a number of key community facilities including: schools, museums and places of worship. Works are unlikely to be undertaken off HA land.

Adverse effects are anticipated on community facilities during works as a result of delays due to traffic management. . However, significant effects would be unlikely during the construction and operation phases; with severance of community facilities unlikely to occur and temporary/ permanent land acquisition unlikely to be required.

300274SS05/MAC/ITD/001/C 28 May 2015

19

A21 Lamberhurst to Hastings

Road Drainage and the Water Environment Over 100 ponds have been identified within 500m of the 32-34 individual ASCs. The proposed Scheme would not be located within a Groundwater Protection Zone. Three primary rivers run underneath the section of A21 road under consideration; including: the , the River Rother and the River Line. The proposed Scheme would not require drainage works; however works to ducting are likely be required.

If best practice methodology is employed in accordance with CIRIA C532 Control of Water Pollution from construction sites during construction, then the risk of pollution to waterbodies within 500m is low and no residual impacts on the Water environment would be anticipated

The full (desktop) Environmental Assessment is provided at Appendix F.

4.2.8 Geotechnical Assessment (Desktop)

BBMMjv’s Geotechnical Team based at Kings Hill has undertaken a preliminary desktop assessment of the proposals in order to identify any initial material matters that would need to be addressed should the proposals develop to detailed design and implementation stage.

Based on the information supplied, the following camera locations may have an impact on the geotechnical asset: These are summarised as follows: -

Camera Site No. Comment

5 2m set back will involve removing part of a cutting slope

6 May require removing part of a cutting slope depending on the exact location of the camera

9 2m set back may cause the foundation to affect the crest of an embankment slope

17 2m set back will involve removing part of a cutting slope

19 May affect the crest of a low height embankment depending on the exact location

20 Depending on offset, the crest of an embankment slope may be affected

21 May affect a cutting slope but is unlikely May affect a cutting slope but is unlikely 23 Offset is likely to involve removing part of a low height cutting slope 24 May affect a cutting slope but is unlikely 26 Will involve removing part of a low height cutting slope 27 May require removing part of a cutting slope depending on the exact location of the 33 camera.

300274SS05/MAC/ITD/001/C 28 May 2015

20

A21 Lamberhurst to Hastings

The majority of the cutting slopes are likely to involve minor cutting and re-grading of the slope and installing some form erosion protection and/or reinforcement. The foundations in embankments will be more complicated depending on their location relative to the slope crest/slope. These may require placing additional fill materials or increasing the depth of foundations.

In order to assess this fully we will need confirmation of the exact location of the camera foundations and possibly topographic surveys of these to obtain slope geometry.

The proposal for the scheme also identifies that street lighting and ducting will be required. Progression to detailed design will also require details of these locations and the foundation type of the lighting columns to be assessed.

As this scheme is an improvement a ‘Statement of Intent’ in accordance with HD22/08 will be required to inform Highways England of the scope of the works, the geotechnical risk and the extent of future geotechnical reporting.

Should further geotechnical design be required, all of the HD22 reports (Preliminary Sources Study, Ground Investigation Report and Geotechnical Design Report) are able to be covered in a single Geotechnical Report.

4.2.9 Sight Line Assessment

From initial site inspections carried out by Mott MacDonald on 5th and 13th March, it is considered that there are sufficient sight lines afforded to the respective camera locations.

4.2.10 Road Safety and Traffic Engineering Assessment

Standard details provided by Vysionics indicate that camera columns / posts as frangible and therefore, passively safe.

In most instances, vehicle road restraint systems (VRRS) are not required. At Site 3 (Section 1 South), the proposed ASC location is in the central median which currently has VRRS, understood to be for separation/protection of opposing traffic flows. In the event that the scheme progresses, it is considered prudent to assess and where applicable extend / replace the existing VRRS.

4.2.11 Speed limit signs

BBMMjv drawing numbers LNMS/13-7058/1201, 1202, 1203, 1204, 1205, 1206 and 1207 (in Appendix G) show proposed alterations to the existing speed limits at Hurst Green, Whatlington and Sedlescombe.

The Department for Transport (DfT) circular 01/2007 Use Of Speed and Red Light Cameras for Traffic Enforcement: Guidance on Deployment, Visibility and Signing provides information on the type and location of signs in support of ASCs. Sections 38 – 44 of the 01/2007 sets out the parameters for the type, location and conspicuity of speed camera signs.

300274SS05/MAC/ITD/001/C 28 May 2015

21

A21 Lamberhurst to Hastings

For fixed speed and red-light enforcement, a camera sign must be placed not more than 1 km from the first camera housing in the direction being enforced (including or excluding side roads at the discretion of the partnership). For fixed speed enforcement, co-located camera and speed limit repeater signs, or the sign shown in diagram 880 where appropriate, must be placed to allow the signs and speed camera to be visible to the driver in the same view.

Hence new speed camera signs to TSR&GD reference 878 and 880 will be required to be placed at regular intervals along the scheme corridor.

Figure 4-1: Typical signing requirements

Sign Ref. to TSR&GD 878 (prefixed with ‘Average’) Sign Ref. to TSR&GD 880

Notwithstanding, the conspicuity of ASCs will need to be considered with camera installations predominantly yellow in colour to enhance road user awareness. However, in some heritage sensitive areas, alternative column colours (e.g. moss green) may be required or be appropriate.

4.2.12 TechMAC maintenance requirements - vehicle hardstanding and access for operatives.

It is understood that maintenance operations post-implementation will fall under the TechMac Framework contract.

Although the footprint of the ASC installations is relatively small, the installations may periodically require convenient parking nearby. The A21 for much of the length of the scheme is narrow, with wooded sections, embankments etc. on either side. A suitable maintenance bay may require significant engineering in some locations. At the northernmost end of the scheme there is a section of grasscrete. However, in most locations there is currently no suitable provision.

Provision of additional vehicle hardstanding or footway links (for maintenance operatives) may require additional environmental consideration in terms of vegetation removal and disturbance to wildlife habitats.

300274SS05/MAC/ITD/001/C 28 May 2015

22

A21 Lamberhurst to Hastings

Table 4-2 provides a summary of maintenance vehicle parking consideratios where there is currently no provision or limited to scope to provide such a facility.

Table 4-3: Summary of Maintenance Vehicle Parking Considerations

Maintenance Vehicle Parking Considerations

MM Camera MM Ref.No. Camera Location (Section) Direction N/B Potential for wide verge side parking on northbound verge. Construction of hardstanding may impact on visibility for 4 Section 2 North N/B adjoining property accesses. Confirm with TechMac provider. S/B Potential for maintenance vehicle to utilise Flimwell Close (private Road) to the north of Camera Site 5. Otherwise TM 5 Section 2 North S/B potentially required for maintenance activities. Confirm with TechMac provider. S/B Parking available in forecourt on northbound carriageway. 6 TechMac Contractor would be required to cross the A21 at Section 2 South Flimwell traffic signals. Confirm with TechMac provider. S/B Parking available in public lay-by on northbound carriageway. 8 TechMac Contractor would be required to cross the A21 Section 3 Mid adjacent to this. Confirm with TechMac provider. N/B Potential for verge side parking on northbound verge. 12 Construction of hardstanding may impact on frontage of Section 5 North residential property. Confirm with TechMac provider and liaise with property owner. N/B Potential for maintenance vehicle to park in car park for Hurst 15 Section 5 South Green Primary School. Confirm with TechMac provider and liaise with school. N/B ** Limited scope for provision of parking for maintenance 16 vehicle. Potentially relocate Camera Site 16 to eastern side Section 6 North of A21. S/B Parking available in public lay-by on northbound carriageway. 19 TechMac Contractor would be required to cross the A21 Section 7 South adjacent to this. Confirm with TechMac provider. S/B ** Limited scope for provision of parking for maintenance 20 Section 9 North vehicle on A21 Robertsbridge Bypass S/B Parking available in public lay-by on southbound 22 carriageway. TechMac Contractor would be required to walk Section 9 South approximately 150m in nearside verge adjacent to the A21. Confirm with TechMac provider. N/B TM Maintenance activities to be undertaken under Temporary 25 Section 12 North Traffic Management (TTM) N/B TM Maintenance activities to be undertaken under Temporary 32 Section 15 South Traffic Management (TTM) N/B TM Maintenance activities to be undertaken under Temporary 33 Section 16 North Traffic Management (TTM) N/B TM Maintenance activities to be undertaken under Temporary 34 Section 16 South Traffic Management (TTM)

300274SS05/MAC/ITD/001/C 28 May 2015

23

A21 Lamberhurst to Hastings

4.2.13 Consultation

Consultation has been undertaken by Highways England and BBMMjv with key stakeholders, namely Sussex Police, Sussex Safer Roads Partnership, local Parish and County Councillors and Members of Parliament and the scheme carries this support. The scheme also carries the support of the relevant Highways England Director (David Brewer, NDD). Further consultation on enforcement will be required as the scheme develops, particularly with respect to locations of ASCs in villages and other similar areas where properties may be affected.

300274SS05/MAC/ITD/001/C 28 May 2015

24

A21 Lamberhurst to Hastings

5. ASC Complimentary Measures

5.1 Identified schemes to enhance Speed Limits and proposed Average Speed Cameras

A range of complementary safety focussed or speed reducing engineering measures are being developed by BBMMjv in addition to those mentioned above including, improved pedestrian and cyclist facilities, crossing facilities, as well as appropriate signing to further enhance the route and impress the village environment upon motorists.

The following is a list of location specific improvement measures identified in the BBMMjv A21 Project Plan Safety Improvements and Average Speed Cameras note (dated September 2014): -

Vinehall Street, Whatlington

Junction improvements have been proposed by a property owner at the junctions of the B2089 whereby they are willing to provide East Sussex County Council (ESCC) with the land to construct a single modern junction, to standard, in a more suitable location. This will then reduce the number of entrances onto the A21 from two sub-standard, to one high quality junction. This is in early stages of development, however, it is understood that discussions as to feasibility of this have been held with ESCC and this is likely to be a developer/local authority lead scheme.

B2244 Tollgate Road Junction, Seddlescombe

This junction has been subject to minor improvements in the past, which have reduced collisions but locally, the impression remains that the junction layout is inherently unsafe. Nearby commercial development offers the scope to finance the conversion of this junction to a roundabout and enhance provision for non-motorised users. It is understood that this proposal is in the early stages of development, but would greatly compliment the proposed A21 ASC Scheme.

Kent Street, north of Hastings

Kent Street currently has no footway provision and sub-standard bus stop facilities. Proposals to support the 40mph speed limit through this village include measures to create a village environment both as a visual message to motorists in order to encourage them to adhere to posted speed limits and assist pedestrians and other NMUs. Proposals include the provision of additional street lighting, a shared-use cycle track through the village to and improvements to the bus stops at the Blueman’s Lane junction.

Swiftsden, near Hurst Green

Swiftsden, like Kent Street does not present a village environment to motorists. Identified proposals to support a 40mph posted speed limit include upgrading the footway to a lit cycle track, providing better signs and vehicle actuated signs (VAS) as well as providing new centre of road traffic islands.

300274SS05/MAC/ITD/001/C 28 May 2015

25

A21 Lamberhurst to Hastings

Mobile and/or Permanent Variable Message Signs (VMS)

There is a desire by Highways England to install and utilise fixed or mobile variable message signs (VMS) which can display relevant information to road users which can positively influence the driver experience. These units are capable of advising of a range of scenarios including informing of delays, emergency works and congestion whether planned or live. They can also advise of actual journey times between locations, underpinning Highways England’s mission statement for safer roads, reliable journeys and informed travellers.

CCTV cameras

Appropriately positioned closed circuit television (CCTV) cameras can enhance the information available to Highways England and the service provider. It can be used to manage the deployment of response teams, and can be used to provide the VMS signs with live information. It is not clear at this stage to what extent additional CCTV is to be provided.

Additional measures required to support the ASC Project

In addition to the ASCs, some existing highway features will need to be replaced or altered and some new signs will need to be installed. These primarily relate to ensuring that speed limit signs and signs warning of camera enforcement are provided and correctly located.

Junction improvements are also being provided at Baldslow (north of Hastings) and Coopers Corner (north of Hurst Green). In addition gateway treatments for all villages and settlements along the A21 are being considered by Highways England in addition to the provision of enhanced gateways where they already exist.

Identified improvements to the existing village environment are proposed for Whatlington (which would benefit from a shared-use facility throughout), along with the Silver Hill, Sedlescombe, Woodman’s Green, Vinehall Street, John’s Cross and Northbridge Street.

300274SS05/MAC/ITD/001/C 28 May 2015

26

A21 Lamberhurst to Hastings

6. Preliminary Scheme Costs

6.1 Capital Expenditure Costs (Equipment Supply, Installation and Commissioning)

Vysionics have provided initial budgetary costs for the supply of camera equipment for the route, and give an indication of budgetary requirements. Detailed costs would be based on further surveys to be carried out with BBMMjv.

Two Vysionics costing summaries have been provided and are set out in Tables 6-1 and 6-2 as follows: -

. Option1 – all rear-facing camera configuration; and

. Option 2 – front & rear facing camera configuration.

In addition, preliminary costings have been collated for design and construction activities to be undertaken by BBMMjv as enabling works for the ASC project. These are shown at Table 6-3.

Table 6-1: Summary of Vysionics Scheme Costs – Option 1

Element Description Cost Roadside 60 x Live VECTOR Cameras Item 6 x Zone VECTOR Cameras 33 x SPECS Camera Columns 63 x Infrared Lighting Columns and Lighting units Back office 3 x additional ERCUs Item Set‐up SPECS3 VECTOR Installation and calibration – ANPR 30 days Team Support Engineering and Project Management Item Item

Total Solution Cost

Source: Vysionics Proposal Document (P2143P), September 2014.

300274SS05/MAC/ITD/001/C 28 May 2015

27

A21 Lamberhurst to Hastings

6.4 Maintenance

There will be a requirement for maintenance activities associated with the Vysionics supply, installation and commissioning of ASC equipment. This will comprise camera calibration, inspection and cleansing of equipment. In addition to the above, there will be annual Area 4 BBMMjv and TechMac activities associated with routine maintenance of inventory added to the Highways England network.

6.5 Annual Costs and Whole Life Costs

Annual costs and whole life costs for the ASC scheme are considered to comprise of the following principal elements: -

 Annual power supply;

 Annual TechMac maintenance requirements;

 Residual Area 4 maintenance for increase in assets (e.g. grasscrete hardstandings and footways);

 Operator resource requirements through the Sussex Safer Roads Partnership;

 Deployment and operation of Mobile VMS;

 Temporary Traffic Management (TTM) associated with the above; and

 Purchase / retention of stock of ASC units;

These will need to be assessed as part of the detailed design process.

300274SS05/MAC/ITD/001/C 28 May 2015

30

A21 Lamberhurst to Hastings

7. Conclusions and Recommendations

The broad conclusions and recommendations of this report are as follows; -

1. There are considered to be no material constraints to the proposed provision of Average Speed Cameras (ASCs) along the A21 route corridor from a structural, environmental or geotechnical perspective.

2. Implement proposed posted speed limit changes at Kent Street and Swiftsden and review existing and proposed speed limit signs throughout the study corridor.

3. Undertake current statutory undertaker’s apparatus search (NRSWA C1/C2 notices) for the 34 average speed camera (ASC) site locations proposed.

4. In most instances, no additional vehicle road restraint systems (VRRS) are deemed to be required.

5. Some further geotechnical assessment work will be required to establish mitigation works for camera positions adjacent to cuttings or embankments.

6. Bespoke power supplies will need to be established for a number of the proposed ASC sites.

7. Additional signing will need to be provided in accordance with the Department for Transport (DfT) circular 01/2007 ‘Use of Speed and Red Light Cameras for Traffic Enforcement: Guidance on Deployment, Visibility and Signing’.

8. Exact TechMac requirements will need to be established for residual maintenance activities and costs.

9. Annual power supply costs, residual Area 4 maintenance costs for increase in assets (e.g. grasscrete hardstandings and footways), operator resource requirements (through the Sussex Safer Roads Partnership), deployment requirements for the operation of mobile VMS and purchase / retention of stock of ASC units will need to be determined;

10. Additional structured liaison with stakeholders as to proposed camera locations will be required.

300274SS05/MAC/ITD/001/C 28 May 2015

31

A21 Lamberhurst to Hastings

Appendices

Appendix A. Project Brief ______33 Appendix B. Vysionics camera and infra-red pole and foundation details ______34 Appendix C. General Layout Drawings (SS-15-8327-1011 – 23) ______35 Appendix D. Camera Site Layout Drawings (SS-15-8327-2601-34) and Typical Grass Grid Hardstanding Detail for Maintenance Vehicles (SS-15-8327-100) ______36 Appendix E. Extracts from Area 4 BBMMjv ‘MAYRISE’ Database ______37 Appendix F. Desktop Environmental Assessment ______38 Appendix G. BBMMjv LNMS Scheme Drawing Numbers LNMS/13-7058 1201 to 1207 ______39 Appendix H. BBMMjv A21 ASC Scheme Estimate ______40

300274SS05/MAC/ITD/001/C 28 May 2015

32

A21 Lamberhurst to Hastings

Appendix A. Project Brief

300274SS05/MAC/ITD/001/C 28 May 2015

33

A21 Lamberhurst to Hastings

Appendix B. Vysionics camera and infra- red pole and foundation

300274SS05/MAC/ITD/001/C 28 May 2015

34

A21 Lamberhurst to Hastings

Appendix C. General Layout Drawings (SS-15-8327-1011 – 23)

300274SS05/MAC/ITD/001/C 28 May 2015

35

A21 Lamberhurst to Hastings

Appendix D. Camera Site Layout Drawings (SS-15-8327-2601-34) and Typical Grass Grid Hardstanding Detail for Maintenance Vehicles (SS- 15-8327-100)

300274SS05/MAC/ITD/001/C 28 May 2015

36

A21 Lamberhurst to Hastings

Appendix E. Extracts from Area 4 BBMMjv ‘MAYRISE’ Database

300274SS05/MAC/ITD/001/C 28 May 2015

37

A21 Lamberhurst to Hastings

Appendix F. Desktop Environmental Assessment

300274SS05/MAC/ITD/001/C 28 May 2015

38

A21 Lamberhurst to Hastings

Appendix G. BBMMjv LNMS Scheme Drawing Numbers LNMS/13- 7058 1201 to 1207

300274SS05/MAC/ITD/001/C 28 May 2015

39

A21 Lamberhurst to Hastings

Appendix H. BBMMjv A21 ASC Scheme Estimate

300274SS05/MAC/ITD/001/C 28 May 2015

40