To: Joint Transportation Board

By: KCC Highways, Transportation & Waste

Date: 16th October 2019

Subject: Highway Forward Works Programme – 2019/20 onwards

Classification: Information Only

Summary: This report updates Members on the identified schemes approved for construction

1. Introduction

This report provides an update and summarises schemes that have been programmed for delivery in 2019/20.

Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2019/20 and 2020/21) and Year Three to Five (2021/22 to 2023/24) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year. For some assets this interim programme covers approximately the first six months of 2019/20, whilst for others it includes most of the works planned for the whole year.

This programme is subject to regular review and may change for several reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.

Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A

Drainage Repairs & Improvements – see Appendix B

Street Lighting – see Appendix C

Transportation and Safety Schemes – see Appendix D  Casualty Reduction Measures  Externally funded schemes  Local Growth Fund

Developer Funded Works – see Appendix E

Bridge Works – see Appendix F

Traffic Systems – see Appendix G

Combined Member Fund – see Appendix H

Conclusion 1. This report is for Members’ information.

Contact Officers:

The following contact officers can be contacted on 03000 418181

Kirstie Williams Highway Manager Mid Susan Laporte Maidstone District Manager Alan Casson Strategic Asset Manager Earl Bourner Drainage & Structures Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Jamie Hare Development Agreements Manager Jamie Watson Schemes Programme Manager Appendix A – Footway and Carriageway Improvement Schemes

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.

Machine Resurfacing – Contact Officer Mr Byron Lovell

Road Name Parish Extent of Works Current Status

From the B2163 Upper Street Programmed 21st A274 Maidstone Road Langley to Warmlake Road November 2019

Watt Tyler Way and Wyke nd A20 King Street Maidstone Programmed 2 Manor Road December 2019

From Lancet Lane to Programmed A229 Linton Road Loose Rosemount Close 30th November 2019

From bridge deck over th Forstal Road Aylesford Programmed 8 motorway to Beddow Way November 2019

From Loose Road (through Programmed A229 Sheals Crescent Maidstone Hayle Road, College Road, 14th November Mill Street) to Bishops Way 2019

Mill Street and A249 Mote Programmed A229 Palace Avenue Maidstone Road 27th November 2019

A249 Mote Road to Old Programmed A229 Upper Stone Street Maidstone Road 11th December 2019

Maidstone Gyratory to To be A20/A26 Rocky Hill Maidstone Terrace Road programmed 2020

Footway Improvement - Contact Officer Mr Neil Tree

Road Name Parish Extent and Description of Current Status Works

From the junction with Square Hill Road to Willow Way Completed Mote Road Maidstone (Northern side) (Footway Reconstruction)

Entire length Winifred Road Completed (Footway Reconstruction). Entire length Royston Road Bearsted Completed (Footway Reconstruction).

Entire length Rosemary Road Bearsted Completed (Footway Reconstruction).

Entire length Designed and to Trenton Close Allington (Footway Reconstruction). be programmed.

Entire length Beverley Road Completed (Footway Protection)

Entire length Egremont Road Bearsted Completed (Footway Protection)

Entire length Roseholme Maidstone Completed (Footway Protection)

Entire length Wesley Close Barming Completed (Footway Protection)

Entire length Broomshaw Road Barming Completed (Footway Protection)

Surface Treatments – Contact Officer Mr Jonathan Dean

Micro Surfacing

Road Name Parish Extent and Description of Current Status Works

Glebe Lane Maidstone Tonbridge Road to Farleigh Completed (Barming) Lane

Maidstone Gatland Lane (Barming) Farleigh Lane to Fant Lane Completed

Lenham Faversham Road Whole Road Completed

Lenham West Street Faversham Road to Flint Lane (West Street) Lenham Completed

Marden Marden Road Battle Lane to "Mountain Farmhouse" Completed

Marden Maidstone Road "Hartridge" to 150m north of j/w Lane (Kiln Farm) Completed Road Chain Gate Road to Station Platts Heath / Approach, Lenham Completed Lenham

Headcorn Road Headcorn Road to Sandway Sandway Road Completed

Sandway Road Headcorn Road to "Little Sandway Biggen" Completed

Gallants Lane Lower Road to Heath Road Completed

River Beult bridge (Clapper Hunton Road Marden Green) to "Reed Court Completed Cottages"

Boughton Old Tree Lane/Cliff Hill Monchelsea From The Quarries to Combe To Be Bank House - Programmed

Sandway Road Platts Heath Around "Sandway Triangle" Completed

Kenward Road Hunt Street to Yalding Hill Completed

Bow Road Wateringbury Corner after bridge to Hunt Completed Street

Smith’s Hill Yalding To Be Confirmed Completed

Surface Treatments – Contact Officer Mr Jonathan Dean

Surface Dressing

Road Name Parish Extent and Description of Current Status Works

Near j/w Old Mill Road to j/w A20 Ashford Road Roundwell Programmed for August 2019

A20 Ashford Road Old Ashford Road to Hollingbourne Northdown Close Programmed for August 2019 Programmed for Charlton Lane From Chartway Street to Church Lane August 2019 Appendix B - Drainage

Drainage Repairs & Improvements - Contact Officer Earl Bourner Road Name Parish Description of Works Current Status Work is in progress. Green Repair the culvert and edge of Hopefully completed by Lane road/ verge/ ditch. 1/9/19.

Tufa Relocation of soakaway Completed Close

Cleansing works Smith’s complete further Investigation works Hill investigation required at Shingle Barn Lane. It has been identified that the issue is due to The Surface water system the Southern Water Maidstone Broadway surcharging system. Southern Water will now be responsible for this site Dray Further investigation works Corner Headcorn Awaiting start date required Road

Dunn Repair broken pipe Awaiting start date Street

Fisher Reports of broken pipes and Maidstone Awaiting start date Street repairs to be carried out

Lower East Farleigh Repair broken pipes Awaiting start date Road

West Hunton Repair broken pipes Awaiting start date Street

Originally programmed To carry out a drainage CCTV for 18/8/19, abandoned The survey and cleanse to locate due to TM issues on the Street outfall of system and check for day. New programme defects. date is Sunday 8/9/19.

Sheals To carry out drainage CCTV Maidstone Awaiting start date Crescent investigation.

Appendix C – Street Lighting

Column replacement testing of KCC owned streetlights has identified the following as requiring replacement. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.

Street Lighting Column Replacement – Contact Officer Sue Kinsella

Road Name Column Parish Description of Works Status Lit Sign Replacement KWAI502 Completion end Warwick Place Maidstone September 2019 Lit Sign replacement KWAI501 Completion end Warwick Place Maidstone September 2019 Replacement of Street Light KBFE010 Completion by Brishing Lane Maidstone December 2019 Replacement of Street Light High Street KHDO053 Completed Lit Sign replacement Milton Street KMCW503 Maidstone Completed Lit Sign replacement Whitmore KWCR501 Completion by Maidstone Street December 2019 Replacement of Street Light KSFA029 Completion by Station Road Staplehurst December 2019 Replacement of Street Light Castle Dene KCAO002 Maidstone Completed Replacement of Street Light Impton Lane KIAC001 Boxley Completed Replacement of Street Light Maynards KMBY002 Marden Completed Replacement of Street Light KEAQ003 Completion by Egerton Road December 2019 Replacement of Street Light KKAM009 Completion by King Street Maidstone December 2019 Replacement of Street Light Woodlands KXEF107 Boxley Completed Replacement of Street Light KHFD002 Completion by March Howard Drive Allington 2020

Replacement of Street Light KHFD016 Completion by March Howard Drive Allington 2020 Replacement of Street Light KTCI016 Completion by March Trevor Drive Allington 2020 Replacement of Street Light ERNEST KEBA004 Completion by March ALLINGTON DRIVE 2020 Replacement of Street Light LEONARD KLBG004 Completion by March ALLINGTON CLOSE 2020 Replacement of Street Light BRACKEN KBIC008 Completion by March BOXLEY HILL 2020 Replacement of Street Light OLD KOAI001 Completion by March CHATHAM BOXLEY 2020 ROAD Replacement of Street Light BELLGROVE KBIF001 Completion by March BOXLEY COURT 2020 Replacement of Street Light BRACKEN KBIC008 Completion by March BOXLEY HILL 2020 Replacement of Street Light WILDFELL KWFE016 Completion by March BOXLEY CLOSE 2020 Replacement of Street Light VICTORIA KVAJ003 Completion by March BRIDGE STREET 2020 Replacement of Street Light CORNWALLIS KCFT005 Completion by March BRIDGE ROAD 2020 Replacement of Street Light TRAPHAM KTCF006 Completion by March BRIDGE ROAD 2020 Replacement of Street Light PALMAR KPAF007 Completion by March BRIDGE ROAD 2020 Replacement of Street Light PEMBROKE KPAW014 & Completion by March ROAD HUNTON 2020 Replacement of Street Light DERINGWOOD KDAL005 Completion by March DRIVE & 2020 Replacement of Street Light DERINGWOOD KDAL006 DOWNSWOOD Completion by March DRIVE & OTHAM 2020 Replacement of Street Light DERINGWOOD KDAL007 DOWNSWOOD Completion by March DRIVE & OTHAM 2020 Replacement of Street Light DERINGWOOD KDAL009 DOWNSWOOD Completion by March DRIVE & OTHAM 2020 Replacement of Street Light DERINGWOOD KDAL021 DOWNSWOOD Completion by March DRIVE & OTHAM 2020 Replacement of Street Light DERINGWOOD KDAL022 DOWNSWOOD Completion by March DRIVE & OTHAM 2020 Replacement of Street Light TONBRIDGE KTBU017 Completion by March FANT ROAD 2020 Replacement of Street Light TONBRIDGE KTBU022 Completion by March FANT ROAD 2020 Replacement of Street Light TONBRIDGE KTBU031 Completion by March FANT ROAD 2020 Replacement of Street Light TONBRIDGE KTBU036 Completion by March FANT ROAD 2020 Replacement of Street Light TONBRIDGE KTBU046 Completion by March FANT ROAD 2020 Replacement of Street Light TONBRIDGE KTBU050 Completion by March FANT ROAD 2020 Replacement of Street Light TONBRIDGE KTBU051 Completion by March FANT ROAD 2020 Replacement of Street Light TONBRIDGE KTBU055 Completion by March FANT ROAD 2020 Replacement of Street Light MANSFIELD KMFW202 Completion by March FANT WALK 2020 Replacement of Street Light WHITMORE KWCR005 Completion by March FANT STREET 2020 Replacement of Street Light DOVER KDBB004 Completion by March FANT STREET 2020 Replacement of Street Light KGAS006 Completion by March GLEBE LANE FANT 2020 Replacement of Street Light TERMINUS KTAD009 Completion by March FANT ROAD 2020 Replacement of Street Light OAKWOOD KOAD003 Completion by March HEATH COURT 2020 Replacement of Street Light KHCH005 Completion by March HEATH ROAD HEATH 2020 Replacement of Street Light QUEENS KQAG004 Completion by March HEATH ROAD 2020 Replacement of Street Light QUEENS KQAG019 Completion by March HEATH ROAD 2020 Replacement of Street Light CHARLBURY KCBH001 Completion by March HEATH CLOSE 2020 Replacement of Street Light STANFORD KSEI001 Completion by March HEATH DRIVE 2020 Replacement of Street Light KMCT002 Completion by March MILL WALK HEATH 2020 Replacement of Street Light ST PETERS KSCE001 Completion by March HIGH STREET BRIDGE 2020 Replacement of Street Light COLLEGE KCFC005 Completion by March HIGH STREET ROAD 2020 Replacement of Street Light KLCU003 Completion by March LOWER ROAD HIGH STREET 2020 Replacement of Street Light KUBR010 Completion by March UPPER ROAD HIGH STREET 2020 Replacement of Street Light KKAM021 Completion by March KING STREET HIGH STREET 2020 Replacement of Street Light KLBS011 Completion by March LINTON ROAD LOOSE 2020 Replacement of Street Light KLCQ094 Completion by March LOOSE ROAD MAIDSTONE 2020 Replacement of Street Light EGERTON KEAQ001 Completion by March NORTH ROAD 2020 Replacement of Street Light KBCG001 NORTH Completion by March ROAD DOWNS 2020 Replacement of Street Light BICKNOR KBCG010 NORTH Completion by March ROAD DOWNS 2020 Replacement of Street Light BICKNOR KBCG011 NORTH Completion by March ROAD DOWNS 2020 Replacement of Street Light BICKNOR KBCG012 NORTH Completion by March ROAD DOWNS 2020 Replacement of Street Light BICKNOR KBCG037 NORTH Completion by March ROAD DOWNS 2020 Replacement of Street Light BICKNOR KBCG041 NORTH Completion by March ROAD DOWNS 2020 Replacement of Street Light BICKNOR KBCG042 NORTH Completion by March ROAD DOWNS 2020 Replacement of Street Light ASHFORD KABO063 NORTH Completion by March ROAD DOWNS 2020 Replacement of Street Light ASHFORD KABO064 NORTH Completion by March ROAD DOWNS 2020 Replacement of Street Light WALLIS KWAD016 Completion by March PARK WOOD AVENUE 2020 Replacement of Street Light KBBS005 Completion by March BELL ROAD PARK WOOD 2020 Replacement of Street Light KGCA002 SHEPWAY Completion by March GREENFIELDS NORTH 2020 Replacement of Street Light MARION KMBK002 SHEPWAY Completion by March CRESCENT NORTH 2020 Replacement of Street Light MARION KMBK004 SHEPWAY Completion by March CRESCENT NORTH 2020 Replacement of Street Light MARION KMBK009 SHEPWAY Completion by March CRESCENT NORTH 2020 Replacement of Street Light CRANBORNE KCGL014 SHEPWAY Completion by March AVENUE NORTH 2020 Replacement of Street Light LONGFIELD KLCN001 SHEPWAY Completion by March PLACE NORTH 2020 Replacement of Street Light HOLTYE KHER002 SHEPWAY Completion by March CRESCENT NORTH 2020 Replacement of Street Light HOLTYE KHER006 SHEPWAY Completion by March CRESCENT NORTH 2020 Replacement of Street Light HOLTYE KHER007 SHEPWAY Completion by March CRESCENT NORTH 2020 Replacement of Street Light RUTLAND KRCC002 SHEPWAY Completion by March WAY NORTH 2020 Replacement of Street Light DENTON KDAJ003 SHEPWAY Completion by March CLOSE NORTH 2020 Replacement of Street Light KTDS001 SHEPWAY Completion by March THE SPINNEY NORTH 2020 Replacement of Street Light SUTTON KSGF006 SHEPWAY Completion by March ROAD SOUTH 2020 Replacement of Street Light SUTTON KSGF007 SHEPWAY Completion by March ROAD SOUTH 2020 Replacement of Street Light SUTTON KSGF039 SHEPWAY Completion by March ROAD SOUTH 2020 Replacement of Street Light KENNINGTON KKAD005 SHEPWAY Completion by March CLOSE SOUTH 2020 Replacement of Street Light CAMBRIDGE KCAC016 SHEPWAY Completion by March CRESCENT SOUTH 2020 Replacement of Street Light GRAVENEY KGBL003 SHEPWAY Completion by March ROAD SOUTH 2020 Replacement of Street Light GRAVENEY KGBL009 SHEPWAY Completion by March ROAD SOUTH 2020 Replacement of Street Light CRANBROOK KCGM001 SHEPWAY Completion by March CLOSE SOUTH 2020 Replacement of Street Light KEBB006 SHEPWAY Completion by March ESSEX ROAD SOUTH 2020 Replacement of Street Light WESTMARSH KWBT003 SHEPWAY Completion by March CLOSE SOUTH 2020 Replacement of Street Light KIAB004 SHEPWAY Completion by March IFIELD CLOSE SOUTH 2020 Replacement of Street Light WINGHAM KWDI005 SHEPWAY Completion by March CLOSE SOUTH 2020 Replacement of Street Light FREEMAN KFCN002 SHEPWAY Completion by March WAY SOUTH 2020 Replacement of Street Light NORRINGTON KNAR007 Completion by March SOUTH ROAD 2020 Replacement of Street Light CRANBROOK KCGN068 Completion by March STAPLEHURST ROAD 2020 Replacement of Street Light CRANBROOK KCGN073 Completion by March STAPLEHURST ROAD 2020 Replacement of Street Light STATION KSFA018 Completion by March STAPLEHURST ROAD 2020 Replacement of Street Light STATION KSFA021 Completion by March STAPLEHURST ROAD 2020 Replacement of Street Light STATION KSFA024 Completion by March STAPLEHURST ROAD 2020 Replacement of Street Light KHDO057 Completion by March HIGH STREET STAPLEHURST 2020 Appendix D – Transportation and Safety Schemes

The Schemes Planning & Delivery team is implementing schemes within the Maidstone district, in order to meet Kent County Council’s (KCC) strategic targets (for example, addressing traffic congestion or improving road safety). Casualty reduction measures have been identified to address a known history of personal injury crashes. Current status correct as of 23/9/19.

Casualty Reduction Measures

Location Parish Description of Works Lead officer Current Status

Great Danes Hollingbourne Signing and road Jennie Works complete Roundabout marking improvements Watson Mill Street/Palace Maidstone Lining refreshing Jennie Works partially Avenue Watson completed in October 2018 – Yellow box markings completed – Contractor to return to refresh white lining

A20 Ashford Road, Lenham Scheme to make Jennie Works are Lenham changes to junction Watson substantially complete – Minor snagging items to be completed Springfield Maidstone Signing and road Paul Leary Following detailed Roundabout - A229 marking improvements analysis, tree clearance only to Royal Engineers be carried out Road St Faiths Street/ Maidstone Signing and road Jennie Works passed to Fairmeadow marking improvements Watson contractor – Programmed for 8 October (weather dependent) A229 Lower Stone Maidstone Introduction of red-light Jennie ITS Team Street/ Knightrider camera monitoring Watson arranging red light camera monitoring Street survey survey over 7 days – Date to be confirmed Boxley Maidstone Signing and road Jennie Works complete 6 Road/Sandling marking improvements Watson September 2019 Lane, roundabout A20 Ashford Hollingbourne Signing and road Jennie At design stage – Road/M20 Slip marking improvements Watson Scheme to be progressed this financial year Integrated Transport Schemes – all other LTP funded non-casualty reduction schemes Lead Location Parish Description of Works Current Status officer Upgrade of signing and Works completed May East Paul East Farleigh Bridge lining for bridge width 2019. Minor snagging Farleigh Leary restriction items to be carried out Works completed May Mote Park Cycleway Paul 2019. Minor snagging Maidstone Upgrade of cycle route (Phase 1) Leary items to be carried out. Signing and road Works handed over to marking improvements contractor – Mote Park Cycleway Paul Maidstone between Chancery Anticipated (Phase 2) Leary Lane and Maidstone completion late House December 2019

Local Growth Fund

Local Growth Fund programme update for the Maidstone Borough.

The Department for Transport (DfT) added £100m to the Local Growth Fund (LGF) pot in order to fund Local Sustainable Transport Fund Style schemes. KCC were successful in securing LGF for the following sustainable transport style bids1) Kent Thameside – Integrated door-to-door journeys and 2) West Kent – Tackling Congestion. The objective of the capital bids is to boost economic growth by decreasing carbon emissions and reducing congestion.

The schemes aim to:

 improve access to employment and services  reduce the need to travel by the private car  enhance pedestrian, cycle and public transport facilities  improve sustainable transport connections

The following schemes have been submitted as part of the successful Kent Thameside LSTF this financial year.

Scheme Status MAIDSTONE The newly appointed Asbestos and demolition specialist Rhodar are now on EAST STATION site and have begun demolition of the public house. This is currently running IMPROVEMENTS to programme, under asbestos controlled conditions, with most of the roof now removed. The whole ground floor has been cleared of all soft items, such as the bar, doors, partitions, etc, and the basement has been cleared in preparation for backfilling the area to provide protection to the tunnel during the demolition works. The expected completion of the overall programme will be clearer once the demolition of the pub is further completed but is currently expected to be in May/June 2020. Any public enquiries are being dealt with by Network Rail. Additional KSIP funding has now been confirmed to progress further highway improvements and walking and cycling connections to the station. Appendix E – Developer Funded Works

Developer Funded Works (Section 278 Agreement Works) Maidstone Borough - Contact Officer Claremarie Vine, other officers for sites Jamie Hare, Aaron Divall, Steven Noad, Sarah Parris, Andy Padgham, Steve A Stickels

Offi Description of Scheme Name File Ref. Parish Current Status cer Works

BP Tudor Service CV Pedestrian crossing point Alterations to Station, London MA003072 Allington and additional signage still existing access Road to do. Bell Farm, North MA003098 SN Barming New accesses Agreement signed; Street to split sites, highway works largely shared surface completed. and new crossing point

New access, crossing point Cross Keys MA003100 JH Bearsted Agreement signed and parking area

AD New Bellmouth Barty Farm, MA003278 Bearsted and Lining Agreement Signed Roundwell works

AP Formation of Bicknor Road MA003256 Bicknor hard surfaced Awaiting technical approval passing places

SP New access, High Friction surfacing Heath footway works, Boughton re-laid. Inspection due Road/Church MA003111 yellow lines and Monchelsea for start of maintenance. Street crossing upgrade

CV Works completed on Two accesses Boughton both accesses, Hubbards Lane MA003084 to minor Monchelsea developments pedestrian crossing point to add

AP New housing Lyewood Farm, MA3247 Boughton development Awaiting technical approval Green Lane Monchelsea MA3248 and access

Goya New access and Works complete except Development, St footway work to MA003123 SP Boxley for new gulley. Michaels Close, new commercial Aylesford properties

Maidstone Studios, MA003110 Boxley Zebra crossing Defective High Friction New Cut Road SP and pedestrian surfacing requires crossing points further attention

CV Waitrose car St Michaels Close, Final remedials due MA003103 Boxley park, new Aylesford access

Widening of Agreement Signed road and new SP Forstal Lane MA003141 Coxheath footpath with Awaiting works start date access to new development

Heath Road CV New access and Works completed and in MA003063 Coxheath (North side) Footway work maintenance

Land north of Access to new Agreement signed Heath Road Phase MA3257 Coxheath SP development 2 Awaiting works start date

Access to new Access & footway development completed further 2 Linden Farm, MA003107 Coxheath and footway link accesses to restore to Stockett Lane SP to community footway near completion hall of development.

Parking restrictions, Gatland House, signage, road Works completed, MA003081 Fant ward Gatland Lane CV markings and Remedials to do tactile crossings for new school

Realignment of Church Road to form new Bell Farm, Ashford MA003094 CV access onto Road Works completed and in A20. New maintenance. footway along A20

New access and Works ongoing on site alterations to SP currently in conjunction Mayfield Nursery, existing MA003135 Harrietsham with Harrietsham Ashford Road Highway to improvement scheme adjoin upcoming Scheme Works

Access to 2 new properties and AP Forge Meadows MA3253 Headcorn vehicle Awaiting technical approval crossovers to existing properties

Access Gibbs Farm Grigg Lane & SP Technical approval granted, MA3250 Headcorn development; Wheeler Street agreement in progress zebra crossing on Wheeler St

Access onto New accesses Grigg Lane Grigg Lane, Grigg Lane and and Lenham Road in CV Lenham Road, MA003050 Headcorn Lenham Road. place, New footway Grigg Footway on Lane completed Grigg Lane

Signalised crossroads Kings AP Technical approval granted, MA3262 Headcorn (linked to Road/Millbank Agreement in progress Road MA3150)

New Footway to Works completed and in Lenham Road site and extends Maintenance MA003062 CV Headcorn (North side) speed limit boundary

Lenham Road CV Agreement prepared MA003057 Headcorn New footway (South side)

CV New footway Works completed and in Oak Lane and MA003048 Headcorn plus junction maintenance Wheeler Street improvements

SP Access to new Agreement signed Ulcombe Road MA003150 Headcorn development

2 new accesses Awaiting works start date Wheeler Street, - off Wheeler MA003137 SP Headcorn Headcorn Street and Kingsland Grove

AP New access to Eyhorne Street MA3198 Hollingbourne Awaiting technical approval development JH New access to Ledian Farm MA003086 Leeds development at Now Adopted Ledian Farm CV In maintenance; streetlight 8 Faversham Road MA003032 Lenham New access to replace

CV Approaching end of New footway Old Ashford Road MA003018 Lenham maintenance, bus stop plus access location to amend.

The Paddocks, CV New access, MA3114 Lenham Footway built, remaining Ashford Road traffic island, (Grove House, Old speed reduction works to complete Oct 19 Ashford Road) to 50mph & f/way link to Faversham Rd

AP Main and emergency Westwood Park, MA003305 Lenham accesses to new Awaiting technical approval Ham Lane housing development

Royal Engineers JH Access to New MA3312 Maidstone Under Technical Review Rd/Mill Lane Development

531 Tonbridge CV Service layby for MA003045 Maidstone In maintenance Road new retail unit

Change of road Bicknor Green, priorities and MA003053 AD Maidstone Works mostly complete Gore Court Road widening / upgrading

SP Works complete now in Hartnup Street MA003138 Maidstone New Access maintenance.

Heath Road, SP New access and Agreement signed MA003134 Maidstone Coxheath new footway awaiting start date

Hermitage Lane, JH New Traffic (opp. Maidstone MA003060 Maidstone Near to adoption signal junction Hospital)

New access for Hermitage Lane/ development MA003070 AD Maidstone Works complete Howard Drive (opposite the quarry entrance)

Junction works to facilitate Bus AD Howard Drive MA003303 Maidstone Gateway Agreement Signed entrance to Croudace site

New access to Agreement signed Maidstone School School and New SP of Science, New MA003197 Maidstone roundabout and Awaiting road space and Cut Road alterations to start date Highway

McDonalds drive- CV New access, Approaching the end of through, Hart MA003013 Maidstone improvements to maintenance - remedial Street Hart Street. works due AD New bellmouth junction and associated Oakapple Lane/ ancillary works Works Complete – in MA003046 Maidstone Hermitage Lane for new maintenance development including new bus stop Royal Engineers SP New footpaths Awaiting funds and works MA003127 Maidstone Road to development start date

The Poplars, AP Access to new Approval granted; MA3254 Maidstone Ashford Road development Agreement due for signing CV Some stopping Works complete up of highway and Wallis Avenue redevelopment MA003085 Maidstone Phase 3, Parkwood of old carpark and shops area opp. Longshaw Road SP Town Centre Week St/Gabriel’s Completed and inspected MA003120 Maidstone Public Realm Hill for maintenance improvements

Heath Road MA3326 JH Linton New Access Under Technical review

SP New Access Albion Road, S278 works part MA003132 Marden and Marden completed. development

Goudhurst Road, CV Install Zebra Church Green Completed – in MA3118 Marden crossing near (Plain Road Maintenance rail station. development)

CV Refurbish Zebra Goudhurst crossing outside Road/West End Work completed and in MA3118 Marden school and Bus (Plain Road maintenance Borders to add Development) by Library stops.

SN New Agreement signed; Howland Road MA003088 Marden development highway works largely access complete

CV Works in maintenance. New bellmouth Remedial works near MAP Depot, MA003012 Marden junction and completed and interactive Goudhurst Road footway speed sign awaiting installation CV New access on Napoleon Drive each road for MA003079 Marden Works Completed and Plain Road new housing development

CV New access and Access substantially The Parsonage, MA003066 Marden associated completed, village Goudhurst Road MA003067 upgrade works gateway to be agreed

CV Upgrade of Due for adoption. existing access Bell Lane MA003030 Staplehurst for new development

SP Realignment Realignment complete and Fishers Farm and new access Pile Lane open (East) Headcorn MA3106 Staplehurst at Headcorn Road (Redrow) Road/Pile Lane junction

Fishers Farm SP New access Works commenced on (West), Headcorn MA3037 Staplehurst onto Headcorn both S278 and S38 Road (Bovis) Road

CV New Works on highway almost Hen and Duckhurst Roundabout for completed. HFS delayed Farm, Marden MA003109 Staplehurst development by utility works. Road access

CV Ped crossing to Marden Road, Oliver Road MA003019 Staplehurst junction Works completed Staplehurst markings and bus boarders

SP New access for Works completed and on Woodford Park MA003099 Staplehurst 9 dwellings to maintenance.

Access to new Appleacres, Sutton development Technical Approval given MA003152 SP Maidstone Road Valence and footway awaiting Legal Agreement works

Upgrade existing Vehicle CV The Oaks, Sutton crossing access MA003078 Works complete Maidstone Road Valence to Bellmouth with tactile crossing.

Upgrade of Footway works carried out; Valdene Industrial Sutton existing MA003054 CV access works due Estate Valence bellmouth and extension to f/w Oct 2019. New access to Cripple Street development, Due for adoption – MA003093 CV Tovil Maidstone widening and remedials due footway works

New access Site opposite speed limit cottages 129-147 CV Works completed and in MA003007 Tovil relocation, new Dean maintenance footway and bus Street/Farleigh Hill stop provision

CV New Footway and crossing Remedials completed – in Tovil Green Lane MA003095 Tovil point to side of maintenance site

Relocate access to new SP development at Hampstead Lane MA3101 Yalding Into maintenance period old depot adj. station. Minor footway works

New access to development SP and speed Technical Approval Vicarage Road MA003121 Yalding restraints on Granted existing Highway

SP New footway Bentletts Yard, Awaiting Technical and replaced Claygate Road, MA003357 approval although some surface to Laddingford works already carried out existing access

Old Ashford Road, SP New access and Awaiting Technical MA003356 Lenham Adj Groom Way footway Approval Developer Funded Works (Section 106 Works)

File Ref. Road Name Parish Description of Works Current Status 18/19-S106- A20 Ashford Harrietsham Village improvement Phase 1 Works completed in MA-486 Road works: 2 phase approach. June 2019. KCC investigating Phase 1 which consisted how phase 2 can be brought of narrowing the forward. Kent County Council carriageway, widening are to collect the remaining footways to allow shared S106 contribution from footway/cycleway, altering Bellway Homes now less the the controlled crossing, indexation. provision of central islands and changes to the speed Please see separate report. limits and associated signing and lining. Phase 2 will include relocating street lighting columns to better suit the new road layout and to extend the lighting to include all the 30mph limit. Resurfacing of the carriageway to hide the old white lining and then new lining to the recently installed layout. . 18/19-S106- Linton Linton/Loose Junction/signal upgrade Finalising designs however MA-819 Crossroads the estimated cost of the alterations is significantly above the S106 contributions available. KCC is to investigate how any funding gap can be dealt with. It is hoped that a public consultation can be undertaken around October/November with implementation in 2020 pending all land, environmental and funding issues being resolved.

Appendix F – Bridge Works

Bridge Works – Contact Officer Earl Bourner

Road Name Parish Description of Works Current Status No planned works Appendix G – Traffic Systems

There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.

Traffic Systems - Contact Officer: Toby Butler

Location Description of Works Current Status

A26 Tonbridge Road near Milton Street, Refurbishment of traffic Programmed August 2019 Maidstone signal-controlled crossing

Refurbishment of traffic B2162 Twyford Bridge, Yalding To be Programmed signals

Refurbishment of traffic Programmed September A229 Fairmeadow/ Medway Street signal-controlled junction 2019

Replacement of signal Programmed September A20 London Road near Broadway controller 2019

A20 Tonbridge Road near Station Replacement of signal Programmed September Approach controller 2019 Appendix H - Combined Member Grant programme update

Member Highway Fund programme update for the Maidstone district

The following schemes are those, which have been approved for funding by both the relevant Member and by Simon Jones, Director of Highways, Transportation and Waste. The list only includes schemes, which are

 in design  at consultation stage  about to be programmed  Recently completed on site.

The list is up to date as of 23/9/19

The details given below are for highway projects only. This report does not detail  Contributions Members have made to other groups such as parish councils  highway studies  traffic/ non-motorised user surveys funded by Members.

More information on the schemes listed below can be found by contacting the District Manager for the Maidstone district, Susan Laporte.

Dan Daley and Rob Bird

Details of Scheme Status 18/19-CMG-MA-722 – Queens Avenue, Maidstone

Construction of build out for part one way Works Complete

Eric Hotson

Details of Scheme Status 19/20-CMG-MA-923 – Church Hill,

Traffic Regulation Order application for speed limit reduction TRO sealed - Complete

Paulina Stockell

Details of Scheme Status 19/20-CMG-MA-947 – Darman Lane, Laddingford, Yalding TRO sealed - Traffic Regulation Order application for speed limit reduction Complete 1.1 Legal Implications

1.1.1 Not applicable.

1.2 Financial and Value for Money Considerations

1.2.1 Not applicable.

1.3 Risk Assessment

1.3.1 Not applicable.

Contacts: Kirstie Williams/ Susan Laporte 03000 418181