Social Monitoring Report

Semestral Report April 2019

PRC: Xi’an Urban Road Network Improvement Project

Prepared by Xi’an Municipal Government for People’s Republic of and the Asian Development Bank.

NOTE

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Xi’an Urban Road Network Improvement Project

External Monitoring and Evaluation Report for RP Implementation (Phase VIII)

Shaanxi River Engineering Technology Research Center Feb 2019

Contents

I. Overall progress ...... 3

II. Impact of Land Acquisition and Demolition ...... 7

III. Monitoring of Land Acquisition and Demolition ...... 18

1. Monitoring scope ...... 18

2. Monitoring method ...... 19

3. Monitoring process ...... 20

4. Monitoring information and data analysis ...... 20

IV. Land Acquisition, Demolition and Resettlement ...... 24

1. Progress of land acquisition ...... 24

2. Progress of house demolition ...... 28

V. Execution of Resettlement Policy ...... 38

1. Land acquisition...... 38

2. Housing acquisition ...... 43

3. Economy recovery ...... 53

4. Other facilities ...... 60

5. The resettlement information of affected households ...... 61

6. Payment of compensation fee ...... 62

VI. Public Participation ...... 67

VII. Conclusions and Suggestions ...... 78

1. Conclusion ...... 78

2. Suggestions ...... 79 Contents of Tables

Table 1 Distribution of the Affected Area ...... 8

Table 2 Summarization of Update Data and Planning Data of Land Acquisition and Demolition

Impact ...... 11

Table 3 Statistics of affected attachments and infrastructures of each subproject ...... 15

Table 4 Questionnaire on basic information of 950 affected sampling households ...... 23

Table 5 Implementation schedule for land acquisition (By the end of Jan 2019) ...... 25

Table 6 Implementation progress of residential housing acquisition (up to the end of Jan 2019) ...... 32

Table 7 Implementation progress of housing acquisition of enterprise and public institution (up to the

end of Jan 2019) ...... 35

Table 8 Actual implementation standard for land acquisition ...... 39

Table 9 Actual executive standards of housing acquisition ...... 43

Table 10 Compensation standard table for auxiliary facilities ...... 60

Table 11. Housing Resettlement Information of Affected Households (by February 2019) ...... 61

Table 12 Compensation expense payment situation for land acquisition and house demolition ...... 64

Table 13 Information disclosure ...... 68

Table 14 Public participation of relocation and resettlement ...... 70 Contents of Figures

Figure 1 Location plan for the subprojects ...... 2

Figure 2 Situation map of construction site of road and pipeline corridor in Keji 2nd Road ...... 29

Figure 3 Situation map of construction site of west section of the Keji 2nd Road ...... 29

Figure 4 Situation map of construction site of middle section of the Keji 2nd Road ...... 30

Figure 5 The plant sites of Sirui Advanced Materials Co., Ltd. located at the No.12, Zhangba

7th Road, Xi’an Hi-tech Industries Development Zone ...... 56

Figure 6 Jingye Apartment in Xi’an Hi-tech Industries Development Zone ...... 56

Figure 7 The plant sites of Shaanxi Sirui Advanced Materials Co., Ltd. located at the No.60, Weiyi

Road, Xi’an Hi-tech Industries Development Zone ...... 57

Figure 8 Staff’s dormitory in plant site of Shaanxi Sirui Advanced Materials Co., Ltd. located at the

Yuhua Industry Park ...... 57

Figure 9 Fund flow diagram ...... 64

Xi’an Urban Road Network Improvement Project Funded by the ADB

Loan External Monitoring Report for RP Implementation

Xi’an serves as the capital as well as the political, economic and cultural center of Shaanxi Province. As one of the most important growth poles in West China, Xi’an realized urban average annual growth rate of population of 1.85% and annual growth rate of GDP of 13.5% from 2000 to 2007. Between 2003 and 2007, the annual growth rate for total number of registered vehicles was 12.2%. An urban road network as the foundation of a city’s development is a powerful guarantee for the normal operation of various basic functions of a city and the development of social economy. In recent years, the construction level, service level and operation efficiency of urban traffic infrastructure in Xi’an have been improved greatly, but there are still some problems. For example, the road network is incomplete, the links among different roads are limited, and some roads have too much traffic; urban entrance and exit have traffic jams, and it is difficult to connect with the suburban expressways; east-west and south-north arterial roads in old urban area are faced with big pressures; there are less pedestrian crossing facilities, and pedestrians, vehicles and non-motor vehicles intermingle in a manner that impacts all three adversely; the lack of parking facilities forces vehicles to park on the roadside, exacerbating traffic congestion. To build an efficient, convenient, and environmentally advantageous modern traffic system, perfect urban infrastructure system, and comprehensively improve urban service functions, Xi’an plans to make use of an ADB loan for the improvement of Xi’an Urban Road Network, and attempts to promote the construction and systematic management of urban integrated transportation system by an all-round and overall scheme, thus facilitating the sustainable development of urban economy. The project will build connecting lines for urban road, interchanges, develop bus priority, construct non-motor vehicles roads, improve pedestrian safety, construct comprehensive

1

transportation hub, enhance traffic management, and control traffic emission. In January 2012, Xi’an and ADB signed an agreement on loan of US$ 150 million. In order to better solve the urban traffic problems, relieve traffic jam, improve road safety, enhance the urban carrier function and ensure a rapid, sound and ordered development of the city, Xi’an Municipal People’s Government uses the loan of Asian Development Bank (ADB for short) to initiate the urban road network improvement and public facilities construction project in Xi’an, the project covers five parts, including (i) road network improvement; (ii) pedestrian traffic and safety; (iii) comprehensive transportation facilities; (iv) intelligent transport system (ITS) and safety education for drivers; (v) environment protection enhancement. Besides, the project provides EA/IA with consulting service for project management and capacity building. See Figure 1 for the location plan of road network improvement subprojects.

Figure 1 Location plan for the subprojects Only subprojects 1 and 3 in this project involve resettlement. In 2011, the resettlement plan was prepared. In September 2012, the IA confirmed the first five subprojects (east section of Kunming Road, Zhuhong Road-North 2nd Ring Interchange, Zhuhong Road-Fengcheng 4th Road Interchange, Hongmiaopo Interchange and Xinghuo Road Interchange) and finished their initial

2

design schemes. In March 2013, the resettlement plan was updated in accordance with the initial design for the first subprojects; the updated plan was submitted to ADB for review and approved in September 2013 (hereinafter referred to as the “updated resettlement report for the first subprojects”). In April 2014, the IA confirmed the initial design scheme of Fengcheng 8th Road-Taihua Road Interchange, and updated the resettlement plan based on the initial design; the updated plan was submitted to ADB for review and approved in December 2014 (hereinafter referred to as the “updated resettlement report for Fengcheng 8th Road-Taihua road subproject”). In April 2014, the IA confirmed the initial design scheme of Dazhai Road subproject; in November 2015, ADB approved the updated resettlement plan for Dazhai Road. In September 2015, the IA confirmed the initial design scheme for Keji 2nd Road subproject. In May 2016, ADB approved the updated resettlement plan for Keji 2nd Road. In July 2016, the IA confirmed the initial design scheme for Parking Lot subproject of Xi’an National Civil Aerospace Industrial Base. In November 2016, the PMO submitted the updated resettlement plan for the Parking Lot of Xi’an National Civil Aerospace Industrial Base. The monitoring report of this term mainly updates the immigrates resettlement situation of Hongmiaopo Interchange Sub-project, Xinghuo Road Interchange Sub-project and Keji 2nd Road Interchange Sub-project, including the number of affected households, area of the house to be demolished and the resettlement; there’s no progress made in other subprojects, and no update content to be made.

I. Overall progress 1. The overall progress for road and bridge improvement subprojects is as below: (1)Kunming Road: Using domestic fund for construction has already been arranged. In original design, after extension, Kunming Road would cover the polluted watercourse, while according to modified design, a river crossing bridge is to be constructed, which will become a part of Xi’an express way. At present, the express way is under construction, and will be finished in 2019. (2)Fengcheng 8th Road-Beichen Avenue Interchange: because the construction of another side of Fengcheng 8th Road has not stared, and construction

3

would involve numerous resettlement and power line reset, hence, the construction for the interchange has been suspended. (3) Zhuhong Road-North 2nd Ring Interchange: The original design scheme involved the demolition of Sinohydro Corporation Engineering Bureau 15 Co., Ltd. Community, but only 89% of residents agreed to relocate in the social stability risk evaluation required by Xi’an Municipal People’s Government, which failed to meet the requirement of 95%. Therefore, the original design for the west-north loop ramp in is changed into the west-north directional ramp scheme, avoiding the demolition of the Sinohydro Corporation Engineering Bureau 15 Co., Ltd. Community. The land acquisition and demolition for the interchange has been finished. At present, the construction works of the interchange were completed. The interchange has been open to traffic. (4) Zhuhong Road-Fengcheng 4th Road Interchange: According to the updated resettlement report for the first subprojects, Zhuhong Road-Fengcheng 4th Road Interchange does not involve land acquisition and demolition. Construction of roads and supporting equipment for the interchange has been completed, and all the project engineering have been completed; the interchange was opened on May 26, 2016. Now the interchange has been open to traffic. (5) Hongmiaopo Interchange: The interchange project was handed over to construction site in September 2016. It was completed on July 31, 2017, and open to traffic. At present, the interchange is fully open to traffic. (6) Xinghuo Road Interchange: The interchange project was completed on July 31, 2017 and open to traffic. At present, the interchange has been fully open to traffic. (7) Fengcheng 8th Road-Taihua Road Interchange: Up to the end of July 2018, the land acquisition and demolition related to the project have been fully completed, and has been handed over to construction site. Now bridge deck engineering is basically completed, realizing traffic in east-west and south-north two directions. The construction unit is carrying out construction for greening, All have been completed; the interchange mainlines and directional ramp bridges are all opened to traffic, thus realizing the connectivity of interchanges. (8) Dazhai Road: Now the roads in the range of the two industrial parks (Yuhua Industrial Park and Heping Industrial Park) involved in construction of Dahzai Road have been comprehensively completed, in which, the passage from Beishiqiao Village to Minqizhai Village was accomplished on May 17, 2018.

4

(9) Keji 2nd Road: House demolitions for former remained 29 affected households of Xiaoyanzhuang Village and staff building of Xi’an International University are all completed. Up to May 2018, land acquisition and demolition involved in Keji 2nd Road was basically completed. In which, house demolition for east section of staff building (No. 1) of Xi’an International University was completed in May 2017; resettlement for 29 affected households of Xiaoyanzhuang Village was completed in July 2017, meanwhile, all the house demolition involved was completed, with a floor area of 46186m2. At the end of July, the site was handed over to construction unit. At present, the utility tunnel is under construction, after its construction, the construction for roads will start. Now the roads at the east and west end have been completed, it is planned to have transport service by the end of March 2019 (Half of the Road). 2. Comprehensive traffic facility subproject covers four comprehensive traffic hubs (Xi'an North Railway Station, Xi'an National Civil Aerospace Industrial Base, Yuhuazhai and Xi'an International Trade & Logistics Park), five multistorey parking garages and five refueling stations (included in four comprehensive traffic hubs, with the addition of Mujiangwang Refueling Station). The overall implementation schedule is as below: (1) Four comprehensive traffic hubs: the land for Bus Parking Lot of Xi’an North Railway Station was handed over to Xi’an Urban Infrastructure Construction Investment Group in December 2014. Xi’an Urban Infrastructure Construction Investment Group Co., Ltd. has obtained written decision on state-owned construction land allocation as well as the approval from land resources department, and relevant procedures has been handled; contract for Bus Parking Lot of Xi’an North Railway Station was signed in December 2016, and contractor entered the site in February 2017. Now, the construction has been started, and the construction is expected to be finished before December 31, 2018. Yuhuazhai Comprehensive Transfer Station has been cancelled clearly. For the land that land acquisition of original project site is unavailable, and the new site proposed by local government is too far from metro station to construct transportation junction, Xi’an Urban and Rural Construction Commission and Xi’an Urban Infrastructure Construction Investment Group Co., Ltd. will remove the transportation junction from project content.

5

Design scheme and land occupation for Traffic Hub of Xi’an International Trade & Logistics Park has not been determined, and Traffic Hub Scheme is still in researching, because inter-city rail transportation station and long-distance bus station will be built near the planned transportation hub. Due to influence of site selection and processing relevant procedure, implementation is clearly suspended. Xi'an Urban and Rural Construction Commission and Xi’an Urban Infrastructure Construction Investment Group Co., Ltd. proposed to establish two traffic hubs in the east and the north of the city, covering construction project of No.2 Company of Xi’an Public Transportation Corporation in Dongxiaozhai (Dongxiaozhai Bus Parking Lot, west of Weiyang Road) and Station of Xigao Public Transportation Co., Ltd. (Xigao Bus Parking Lot, south of Jingpu Road); and has submitted the Due Diligence Report under the requirement of ADB. The relevant procedures in early stage are in process; Due to the change of position, ADB inspection team decided to cancel the Bus Parking Lot of No.2 Company of Xi’an Public Transportation Corporation (Dongxiaozhai Bus Parking Lot). The site of transportation hub project in Xi’an National Civil Aerospace Industrial Base has been determined, and land acquisition area of 62.3mu 1 has been reconfirmed. On December 12, 2012, land acquisition and demolition office of Xi’an National Civil Aerospace Industrial Base signed land acquisition and demolition contract with Village Committee of Xinzhaizi Village in Changan Weiqu Subditrict, in which land acquisition area is 800mu, including land acquisition area of 62.3mu for the project. In July 2016, after initial design of the project, remeasurement and counting for arable land and ground attachment in the range of the project was carried out. In May 2017, checking for all ground attachments and signing of Compensation Agreement for 30 affected households were completed, and compensation fee of CNY 78 thousand per mu for ground attachment was paid (including land cleanup fee ), totaling CNY 3,381.3 thousand for 43.35mu. In June 2017, demolition for temporary building and cleanup for site were completed, and site was handed over at the end of the month. By May 2018, land acquisition and demolition involved in the

1 Bus Parking Lot of Xi’an National Civil Aerospace Industrial Base needs an occupation of land of 2.9hectare (43.35mu). According to the investigation, the land occupation impact of the project was confirmed. Because part of the land of the affected households is within the project scope but the other part is not within the scope, the acquisition of part of the land may affect the subsequent use of land if only a part of land is acquired, it is needed to acquire the entire land at the time of acquiring the land. Hence, the subproject acquired 4.15 hectare (62.3mu) of land finally.

6

project were all completed; at present, construction contract signing and commencement are in preparation. Procurement Evaluation Report for first round bidding of civil engineering contract of bus parking lot was approved in February 2017. Because audit unit found out that there was bidding collusion, rebidding was required, and it started from December 2017, Procurement Evaluation Report was approved by ADB on May 10th,2018. It is estimated that construction will start after signing contract.

(2) Five multistorey parking garages: two multi-layer parking lots will be built in Yuhuazhai Comprehensive Traffic Hub and Xi’an International Trade & Logistics Park, and the other three will be built beside old city wall (Lejuchang, Nanguoshang Village and Xizhan Community). By the end of May 2018, land for five multi-layer parking lots were unable to be acquired, hence, the site shall be reselected. Project office proposed to establish East Fucun Road Parking Lot. Now, it has submitted the Due Diligence Report required by ADB and obtained the reply and approval of ADB to establish East Fucun Road Underground Parking Lot. In addition, civil engineering procurement contract was signed in May 2017. Now it is under construction. (3) Refueling station: It is planned to establish five compressed gas stations, four of which will be built in the four bus parking lots and the other one will be built in Mujiangwang. Due to the delay of construction of bus parking lot, the construction of gas stations was also delayed. The compressed gas station built in Mujiangwang will be reconstructed in bus maintenance station. At present, the gas stations confirmed include: Bus Parking Lot of Xi’an National Civil Aerospace Industrial Base, Refueling Station in Xi’an North Railway Station, Refueling Station of No.5 Company of Xi’an Public Transportation Corporation. In which, there is no land acquisition and resettlement of affected persons involved in Refueling Station of Xi’an North Railway Station and Refueling Station of No.5 Company of Xi’an Public Transportation Corporation, and land acquisition and resettlement has been completed for Bus Parking Lot of Xi’an National Civil Aerospace Industrial Base. Problems related to resettlement for all affected households and residents have been solved properly and the due diligence report have been approved by ADB.

II. Impact of Land Acquisition and Demolition Xi’an Urban Road Network Improvement Project with ADB loan belongs to urban road and infrastructure construction project. The project is expected to promote the

7

urban integrated traffic systematic construction and systematic management through a comprehensive and whole scheme, thus promoting the urban economic sustainable development. The project will build a connection road for urban road short slab, build open interchange to promote public transportation priority, build bicycle line to improve the pedestrian safety, build comprehensive traffic facilities to enhance traffic management, and control gas emission. And the road & bridge improvement subproject and comprehensive traffic facilities subproject is affected by land acquisition in the project. After completing the preliminary design scheme of the project, Project Implementation Agency updated the original resettlement plan (first draft) and investigated the impact of LA&R accordingly. The affected area includes three economic & technological development zones, six subdistricts, two industrial parks in five administrative districts (Weiyang , , Chang’an District, Yanta District, ) of Xi’an, and Xi’an International Trade & Logistics Park, Preservation Office, and Weiyang Daxing Reconstruction Office. After implementation of the project, the project implementation agency made an inventory and record of the number and type of affected objects. 1. Affected districts Affected districts in this project involve Weiyang District, Lianhu District, Chang’an District, Yanta District and Baqiao District in Xi’an. See Table 1 for details.

Table 1 Distribution of the Affected Area

Subdistrict office/ Engineering County/ Economic and Category Type No. name district technological development zone Yanta 1 Keji 2th Road XHTZ District Yanta Road & bridge District, Yuhua Industrial Park, improvement 2 Dazhai Road Lianhu Heping Industrial Park subproject (Xi’an Road District Municipal Public East section of Lianhu Utility Bureau) 3 Yuhuazhai Subdistrict Kunming Road District West section of Lianhu 4 Yuhuazhai Subdistrict Kunming Road District

8

Zhuhong Economic and Road-Fengcheng Weiyang 5 Technological 4th Road District Development Zone Interchange Xi’an Economic & Technological Zhuhong Development Zone, Road-North 2nd Weiyang 6 Weiyang Palace Ring Road District Subdistrict, Weiyang Interchange District Daxing Reconstruction Office Weiyang Daming Palace Hongmiaopo District, Interchange 7 Preservation Office, Interchange Lianhu Daxing New District District Weiyang Daming Palace Xinghuo Road District, 8 Preservation Office, Interchange Lianhu Daxing New District District Fengcheng 8th Road-Beichen Weiyang 9 Tanjia Subdistrict Avenue District Interchange Fengcheng 8th Weiyang 10 Road-Taihua Road Tanjia Subdistrict District Interchange Bus Parking Lot of Xi’an Economic & Weiyang 11 Xi'an North Technological District Railway Station Development Zone Bus Parking Lot Bus parking Comprehensive Subproject of Xi’an Economic & Technological lot traffic facility National Civil Chang’an Development Zone of 12 subproject (Xi’an Aerospace District Xi’an National Civil Urban Industrial Base Aerospace Industrial Base Infrastructure Investment Yuhuazhai Group Co., Ltd.) Comprehensive Metro Transfer Station Yanta 13 Yuhua Industrial Park transfer hub (some station in District the west of Xi’an City)

9

Comprehensive Transfer Hub of Baqiao Xi’an International Trade & 14 Xi’an International District Logistics Park Trade & Logistics Park Yuhuazhai Parking Yanta 15 Yuhua Industrial Park Lot District Parking Lot of Xi’an International Baqiao Xi’an International Trade & 16 Trade & Logistics District Logistics Park Park Multistorey Parking Lianhu Yuhuazhai Subdistrict Urban 17 Garage of Xizhan District Office Multistorey Community Parking Ring Road-Taihua Xincheng Garage 18 Road Multistorey Taihua Subdistrict District Parking Garage Xianning Road- Dongguannan Beilin 19 Dongguannan Subdistrict Street Multistorey District Parking Garage East Fucun Road Chang’an 20 XHTZ Parking Lot District Mujiangwang Baqiao 21 Hongqi Subdistrict Refueling Station District Refueling Station Economic & Technological

of Xi’an National Chang’an Development Zone of 22 Civil Aerospace District Xi’an National Civil Industrial Base Aerospace Industrial Base Refueling Station Refueling Weiyang Economic & Technological 23 of Xi’an North Station District Development Zone Railway Station Yuhuazhai Yanta 24 Yuhuazhai Subdistrict Refueling Station District Refueling Station of Xi’an Baqiao Xi’an International Trade & 25 International Trade District Logistics Park & Logistics Park

2、Type and Category of the Impact

10

Table 2 Summarization of Update Data and Planning Data of Land Acquisition and Demolition Impact

Land Enterprises and Residential housing acquisition institutes in the Updated resettlement Updated Category Type No. Project name updated plan resettlement plan resettlement Area Households Amount Area(m2) plan(ha.) (m2) 1 Keji 2nd Road 17.18 74 87849.48 6 63863.45 2 Dazhai Road 9.2 29 14930.13 15 37004.56

Road 3 East Section of Kunming Road 71000 13.34 0 2 Road and 4 West Section of Kunming Road interchange improvement Zhuhong Road –-Fengcheng 4th 5 0 0 0 0 0 subproject Road Interchange (MPUA) Interchange Zhuhong Road- North 2nd Ring 6 0.67 0 0 12 11,719 Road Interchange

7 Hongmiaopo Interchange 0.52 0 0 1 7,855

2 Enterprises in the updated resettlement plan 2013 refers to the demolition of the community of Sinohydro Corporation Engineering Bureau 15 Co., Ltd. But in the assessment of social stability risk required by Xi’an Municipal People’s Government, only 89% residents agree with the relocation, which fails to reach the requirement of 95%. Therefore, the original scheme of left-handed annular west- north loop ramp from was changed into left-handed directional ramp, keeping away from the community of Sinohydro Corporation Engineering Bureau 15 Co., Ltd.

11

8 Xinghuo Road Interchange 1.33 0 0 03 0

Fengcheng 8th Road - Beichen 9 10 Not updated Not updated Road Interchange

Fengcheng 8th Road - Taihua 10 5.633 0 2 4,960 Road Interchange

Bus Parking Lot of Xi’an North 11 6.67 Not updated Not updated Railway Station Bus Parking Lot Bus parking lot of Xi'an National 12 6.67 0 0 0 0 Civil Aerospace Industrial Base Comprehensive traffic facility Yuhuazhai Comprehensive subproject 13 Transfer Station (some station in 3.33 (Xi’an Urban the west part of Xi’an City) Metro transfer hub Infrastructure Comprehensive Hub Station of Investment 14 Xi'an International Trade & 3.33 Not updated Not updated Group Co., Ltd.) Logistics Park

15 Yuhuazhai Bus Parking Lot 0.53 Urban multistorey parking garage Parking Lot of Xi'an International 16 0 Trade & Logistics Park

3 Xinghuo Road Interchange involves the relocation of multiple enterprises, institutes and stores, but there is no the relevant data in the updated resettlement plan 2013.

12

Multistorey Parking Garage of 17 0 Xizhan Community

Ring Road-Taihua Road 18 0.53 Multistorey Parking Garage

Xianning Road- Dongguannan 19 0.53 Street Multistorey Parking Garage

20 Mujiangwang Refueling Station 0.55

Refueling Station of Xi’an National 21 0.55 Civil Aerospace Industrial Base

Refueling Station of Xi’an North 22 0.55 Refueling station Railway Station

23 Yuhuazhai Refueling Station 0.55

Refueling Station of Xi’an 24 International Trade & Logistics 0.55 Park Total 82.213 103 102779.61 27 197402.01

13

The project implementation agency will be responsible for compensating and recovering the ground attachments and infrastructure according to the replacement price. The ground attachments demolished in each subproject include 3,034 mature trees, 97,812 young trees, 1,950m fencing, two toilets, and 14,860 m2 lawn. Besides, the affected special facilities include 18,105m electric wire, 12,990m telecommunication wire, 242 power poles, 1,093m communication optical cables, 28 transformers, 14 high-voltage towers, 12,858m water pipes, 1 overpass, 2 emergency communication stations, and 227 street lamps, 11 motor-pumped well, and 2,058m water canal. See Table-3 for details, the data in the table is the original data of the resettlement plan.

14

Table 3 Statistics of affected attachments and infrastructures of each subproject

West Zhuhon Zhuhong Fengchen Section of Dazhai g Road - Road - g 8th Fengcheng Keji 2nd Road Fengche North 2nd Road - 8th Road - Kunming Hongmia Xinghuo Road (West (Yanhuan Item Unit ng 4th Ring Beichen Taihua XCAIB Bus Road opo Road Bypass- Road - West Total Road Road Avenue Road Parking Lot North 3rd Ring Intercha Interchan Interchan Interchange Zhangba Road) nge ge ge Road Mature Eac (3000) — (0)278 (20)20 (6)6 (55)55 (40) (50)159 — (180)446 3034 trees h 2030 Young Eac (500) (5030) (4300) (400)344 — (30)38 (20)26 (0) 21 (300) (21)80 97812 trees h 92243 1300 3460 Fencin (1610) M (200)220 — — (50)50 — — — (50)140 — 1950 g 1540 Eac Toilet — — — — (0)1 — (1)0 — (4)1 — 2 h (7000) (2500) (2000) (800) (400) (800) Lawn M2 — — (1160) — 14860 7000 2500 2000 1050 400 750 Electric (3000) (0) (0) (500) (0) (1800) (2000) (8000) (4000) M (1600) 18105 wire 3000 400 500 500 2000 1200 0 7705 1200 Teleco (2400) (0) (500) (0) (1500) (1500) (8000) (2400) mmunic M — (1000) 12990 2400 300 500 1800 1500 0 3490 2000 ation

15

wire

Power Piec (90)90 — (6)6 (4)5 (38)40 (20) (36)26 (2)4 (120)25 (50)26 242 pole e Optical M (400)400 — — — — — — — (1500)693 — 1093 cable Transfo Eac (25)25 — — — 2(2) — — (3)0 (22)1 — 28 rmer h High-vo Eac ltage — — — (0)2 12(12) — — — — — 14 h tower Water (6000) (300) (400) 2107 (900) (5300) M — (400) — — 12858 pipe 6000 1200 700 (2107) 91 2360 Overpa Eac — — — — (0)1 — — — — — 1 ss h Emerge ncy Eac commu — — — (0)2 — — — — — — 2 h nication station Street Eac — — — — — — (0)119 — — (0)108 227 lamp h Motor-p Eac umped — — — — — — (2)0 (3)11 — — 11 h well

16

Ditch M — — — — — (2000) — (0)58 (400)0 — 2058 Color steel M2 (0)2496 2496 tent Pigsty M2 (0)442.86 442.86

17

III. Monitoring of Land Acquisition and Demolition The external monitoring and evaluation of resettlement is made mainly for the monitoring and evaluation of the implementation effect of resettlement, the relocation and construction of special facilities and infrastructures and the use performance of the capital input for resettlement. It mainly includes the resettlement monitoring for urban demolition residents and urban commercial shops, demolition and resettlement monitoring for urban temporary building and illegal building, resettlement monitoring for affected enterprises, public institutions, rural demolition residents, and peasants’ production after land acquisition, monitoring for the operation of resettlement agency and resettlement of vulnerable people, as well as investigation into the living standard of affected population and the monitoring and evaluation of resettlement effect. 1. Monitoring scope The monitoring investigation of this project includes three aspects: (1) Follow-up investigation into the impact of land acquisition and demolition; (2) Investigation of social economy for affected area; (3) Follow-up investigation into the living standard of affected people. The main points for the follow-up investigation of land acquisition and demolition are shown as follows: a. The number of occupied land, demolished buildings and various special facilities as well as affected population in the implementation area of this project; b. The cost and replacement cost for demolition content of the project as well as the compensation for demolition; c. The economic conditions of the affected households; d. The economic conditions of the affected areas; e. The bearing capacity of affected people for land acquisition and demolition; f. The affected people’s opinions and attitudes towards land acquisition and demolition and resettlement policy as well as the economic rehabilitation strategies. g. The opinion and attitude of the general public for the construction of this project. The main points for the social economic investigation of affected areas are shown as follows: a. The general situation of administrative region in the project implementation area; b. The annual major economic indicator of the project during implementation; c. The distribution of the poor; d. The living conditions of ethnic minorities and women;

18

e. The strategy and status of agricultural production and economy rehabilitation in the aforesaid affected areas; The main points for the follow-up investigation of living standard of affected population: a. The information of affected villages includes population, cultivated land and per capita income level; b. The information of sampling households include the employment structure, average asset, per capita income level and the income ratio of relevant production activities; c. The formulation and implementation of economic rehabilitation strategy; d. The affected people’s attitudes and opinions towards land acquisition and demolition and resettlement policy as well as the economic rehabilitation strategy. 2. Monitoring method For the monitoring and investigation of the project impact, it adopts participatory monitoring which gradually becomes mature worldwide in recent years, and the traditional methods for monitoring investigation is also used. The adoption of participatory methods is a highlight of this investigation; its advantage is that by making interested party and non-interested party (independent person) affected by the project as the participator of monitoring investigation, it has realistic and positive significance in the control and analysis of the content, progress and result of monitoring, enhancement of the objectivity, systematicness and effectiveness of monitoring, promotion of understanding and recognition among interest parties related to the project, reduction of the negative effects during implementation of the project, and promotion of the successful implementation of the project. The major process and methods for the monitoring investigation of this project are as follows: (1) According to the requirements of participatory monitoring principle, a main step of the land acquisition and demolition monitoring is to form project land acquisition and demolition monitoring advisory committee composed of representatives of project implementation agency, local government officials of project area, representatives of the masses affected by project land acquisition and demolition, representatives of communities in project area and independent expert representatives, etc. The advisory committee can not only provide advisory opinions for content, procedure, progress and other major problems of monitoring work, but also directly participate in the centralized monitoring survey and daily monitoring of the project. In this way, since some members of the advisory committee just live in the project area, they can conveniently conduct continuous, detailed and in-depth monitoring survey on land acquisition and demolition activities of the project

19 and the impact, so as to avoid careless omission and deviation of survey data due to space-time limitation in the past. (2) Use of traditional monitoring survey tools, including on-site survey, in-home questionnaire, dictation records, gathering relevant personnel for informal discussion, visit of relevant competent organization, inquiry of statistical data, local chronicles and literatures on laws and regulations. 3. Monitoring process By March 2013, the preliminary design for the first batch of subprojects had been completed, and external monitoring for land acquisition, demolition and resettlement had been conducted as scheduled. Up to now, a system monitoring survey and baseline survey have been completed in each project: Monitoring work is mainly conducted from two aspects, one is the estimation of monitoring personnel for the influence quantity in project area, while the other is the monitoring of economic life level for the collective and family in project affected area, including the follow-up survey for overview of social and economic condition and development level, and the follow-up survey for 950 affected households randomly selected from four districts. The survey information mainly focuses on industrial structure, economic advantages and restriction factor, degree of impact of land acquisition and demolition, and main measures for economic recovery in future, apart from the basic information of the households. 4. Monitoring information and data analysis A. Description of socioeconomic status of affected districts Weiyang District: Weiyang District is located in the northern suburbs of Xi’an, with geographic position of 34°14'50"N~34°26'22"N and 108°47'08E~109°02'21"E. It reaches Bahe River in the east, adjacent to Baqiao District; is near to Qiqu River in the west, and borders on City; is adjacent to Xincheng District and Lianhu District across North Longshou Road in the south; is close to Weihe River in the north and faces Gaoling County and Xianyang City across the river; borders on Yanta District and Chang’an District in the southwest. It covers an area of 262.14km2 in total. Weiyang District is the administration center of Xi’an, and its name is derived from Weiyang Palace Site of the Han Dynasty, implying “everlasting prosperity”. It governs 10 subdistricts, 212 administrative villages and 44 communities, with the total population of more than 850,800, with urbanization rate of 96.86%, total households of 203,600, registered population of 617,779 (all are urban population). The GDP of the District in the 20 year of 2018 was about 90 billion CNY, increased by 7.5%, the fix investment amounted to 80 billion CNY, the industrial added value above the designated size was 24.5 billion CNY, increased by 9.5%; the total retail sales of consumer goods is 61 billion CNY, increased by 10%; the general budgetary revenues of local governments was 3.541 billion CNY, increased by 10.25%, the taxation account for 87.37%; the urban per capita disposable income was 41000 CNY, increased by 7.7%; 12665 job vacancies were created in urban area, the transfer employment of rural labor was 12810 people; 2 medical and nursing institutions for the old were built, 545 beds were added, the subsistence allowances for urban and rural residents was increased to 660 CNY per head per month. Lianhu District: Lianhu District is located in the northwest of the urban area of Xi’an. North Avenue, Beiguan Central Street, and Longshou Village in the east border on Xincheng District; Xi’an-Huxian Railway in the west and Wei 26th Street in the north connects with Weiyang District; the moat and Dahuan River in the south are adjacent to Beilin District and Yanta District. Lianhu District covers an area of 38km2, with total population of 722.300. It governs nine subdistricts and the district government is located at No.159 of Beiyuanmen Subdistreet. The starting point of Silk Road is at Lianhu District, and there are many Silk Road scenic spots such as large-scale sculpture of Silk Road, Tang West Market, Tang West Market Museum, etc. This district possesses well-developed transportation network, and there is Longhai Railway and Xi’an-Huxian Railway across the border, as well as Ring Road, 2nd Ring Road, and other streets and roads. In 2018, each department and unit of the District Government enforced their responsibilities, the execution, implementation with the spirit of iron army, and made great many productive jobs in terms of steadying the growth, promoting investment, optimizing environment, benefiting people’s lives and facilitating development. The GDP growth rate, general public budget income, industrial added value above scale and other economic indicator ranked the first matrix of the city; road cleaning service outsourcing, medical system reform, construction of safe Lianhu, one-for-all problem solution reform also was in the top of the city and gained excellent performance. Of which, In the year of 2018, the GDP of Lianhu District was 82.073 billion CNY, the growth rate was about 7.1%, The industrial total added value above designated size was 11.5 billion CNY, grew at the speed of 5.0%, the growth speed of investment in the fixed asset of the entire society was 3.8%, reaching 24.94 billion CNY; the total retail sales of consumer goods was 43 billion CNY, the added value of culture industry increased by 17%; 18979 job vacancies were created, the registered urban unemployment rate was under 4%, the urban per capita disposable 21 income increased by over 7.6%, 12 thousand people are included in the insurance system, the coverage of urban medical insurance rate reached 99.6%, ranking the first in the city, it’s science and technology, education, culture, health and other social undertakings enjoyed the all-round development. Yanta District: Located in the south of Xi’an, Yanta District is close to Chanhe River in the east and connects Baqiao District, spans Zaohe River in the west, reaches Shaoling Plateau and the north slope of Fengqi Plateau in the south and connects Chang’an Dsitrict. South 2nd Ring Road in the north is adjacent to Weiyang District, Lianhu District, Beilin District, and Xincheng District. It is the base of national, provincial, and municipal hi-tech industries, scientific research, and higher education, as well as the business center and popular tourist destination. It governs eight subdistricts, 89 community neighborhood committees, and 119 villagers committees. The district covers an area of 149km2, the year-end cultivated area is 19.53km2, and the irrigation area is 7.01km2. The year-end total population is 288,547, registered total population is 869,503, increased by 24,619 with the growth rate of 2.91%. The permanent resident population is 1,231,100 with urbanization rate of 100%. There is Big Wild Goose Pagoda, Qinglong Temple, Duling Mausoleum of Emperor Xuan of the Han Dynasty, Qujiang Pool Heritage Site, Shaanxi History Museum, etc. There are 22 regular higher educational institutions such as Xi’an Jiaotong University, , etc., 12 private higher learning institutions of over 1,000 students, such as Xi'an Eurasia University, etc., and 55 provincial or above scientific research institutes. Also, there is Xi’an Hi-tech Industries Development Zone in the west, and Qujiang New District and Chanba Ecological District in the east. With the unique pattern of one district and various systems, it becomes a well-known scientific, educational, cultural and tourist area in China. The GDP of the District was 175.798 billion CNY in the year 2018, with an growth rate of 8.3%, the industrial added value above designated size reached 13.83 billion CNY, with an growth rate of 14.0%; investment in fixed assets grew by 4.0%, and retail sales of consumer goods reached 84.75 billion CNY , increased by 8%; the local fiscal income is 4.84 billion CNY, increased by 7.8%, both the taxation scale and share rank the top in the city; 10 community home residence service stations were built, 455 beds were added, the urban per capita disposable income is estimated to be 43710 CNY, ranking firmly among the top in the province. Chang’an District: Chang’an is in the hinterland of the Central Shaanxi Plain, close to Qinling Mountains in the south. It is at 108°38'E-109°14'E and 33°47'N-34°18'N, next to in the 22 east, close to and in the south, bordering on Huxian County and Xianyang in the west, and neighboring to Yanta District and Baqiao District in the north. In terms of the terrain, it is tableland in the east, mountains in the south, and rivers in the west, with the lowest latitude of 384.7m, and the highest altitude of 2,886.7m, generally high in the east and south and low in west and north. The south-north length is 55km, and the east-west width is 52km. It embraces the downtown area of Xi’an from the west and south, and has mountains, rivers and tablelands. It covers an area of 1,580km2 in total, and has ten subdistricts, four towns and 11 townships under its jurisdiction, with the population of 1.03 million. Chang’an District boasts superior location and convenient traffic. The location of Chang’an District People’s Government is only 8.7km away from the center of Xi’an City. Under the macro-environment of “New Normal Economy”, Chang’an District pushes the “super-normal development” by “abnormal action”. in the year of 2018, the GDP of the District is 85 billion CNY, increased by 8.5%; the industrial added value above designated size increased by 11.2%; the total investment in fixed assets reached 63 billion CNY, increased by 16%; retail sales of consumer goods totaled 25.86 billion CNY; local fiscal income general budget reached 2.44 billion CNY; the urban per capita disposable income reached 40244 CNY, increased by 7.5%; rural per capita disposable income reached 19862 CNY, increased by 8.9%, under the background of economy slowdown, Chang’an District maintained its high growth based on a high growth level, showing its strong leading force. B. Survey data of sampling households The samples of sampling survey on social and economic development level in the areas affected by project land acquisition and demolition for Xi’an Urban Network Improvement Project with ADB Loan are 950 households randomly selected from affected households in Weiyang District, Lianhu District, Yanta District and Chang’an District, and the sampling rate reaches up to 37.8% of the total 2,513 affected households. The main summary data can be seen in Table 4.

Table 4 Questionnaire on basic information of 950 affected sampling households Survey item 950 households Time (year) 2017 2018

Population (person) 2200 2200 Gross annual family income (RMB 144021 154102 Yuan) Productive Annual expenditure 17347 125980 18423 134117

23 expenditure per household (RMB (RMB Yuan) Yuan) Living expenditure 108633 115694 (RMB Yuan)

Per capital housing (m2) 32 32 Value of manufacturing machine 5 7 (RMB ten thousand Yuan) Value of main living supplies (RMB 10 13 ten thousand Yuan) According to the survey, the gross family income of 950 affected households was 144,021 CNY in 2017 and 154,102 CNY in 2018; while the expenditure was 125,980 CNY in 2017 and 134,117 CNY in 2018. And there was an increase in both income and expenditure of 950 households.

IV. Land Acquisition, Demolition and Resettlement Except that the projects of Keji 2nd Road, Fengcheng 8th Road – Beichen Interchange have not been commenced, the other sites of road & bridge sub-project of ADB urban network improvement project have been handed over and constructed. By the end of June 2018, the progress of land acquisition and demolition is as below: 1. Progress of land acquisition Keji 2nd Road: Up to June 2018, all the land use of Keji 2nd Road involves the collective land of four villages of Dingjiaqiao Village, Xiaoyanzhuang Village, Yuhuazhai Village and Yingfazhai Village, totaling 257.76mu (17.18ha.) have been acquired, and land acquisition has been comprehensively completed. In May 2017, Xi’an Urban Village (Shantytowns) Reconstruction Office signed land acquisition agreement with Xiaoyanzhuang Village, with a total land acquisition of over 300mu land (including 76.66mu (5.11ha) collective land of Xiaoyanzhuang Village involved in Keji 2nd Road Project ). In September, about CNY 25 million was paid for land acquisition, and the land acquisition of former remained collective land was completed. Dazhai Road: Land acquisition involved in the project has been completed, and the whole project site has been handed over. Road construction is in smooth process, and the engineering achieved greater progress. The Administrative Committee of Yuhua Industrial Park accomplished land acquisition for about 100mu in Dazhai Road (west of Fuyuan 2nd Road)4, with a land acquisition cost of CNY 13 million. About 20m land has not been

4 The latest information provided by Yuhua Industrial Park in 2018 ADB Delegation Meeting. 24 acquired in Erfuzhuang Village at Dazhai Road, which will be acquired at the same time with urban reconstruction. North 2nd Ring Road: Xi’an Municipal Public Utility Bureau has actually obtained the project land of 24.2 mu (1.61 ha.) provided after the urban village reconstruction of Fanbei Village. Demolition issue for a public toilet remained in ADB inspection period in September 2014 was resolved at the end of May5. Bus parking lot of Xi’an North Railway Station: Land acquisition of bus parking lot in Xi’an Bei Railway Station has been completed, with a total land acquisition of 120.91mu (8.06ha), in which, land use of ADB project is 78mu (5.2ha), also authorized land and authorized greenbelt of 42,91mu (2.86ha). The land was actually handed to Xi’an Urban Infrastructure Construction Investment Group, which has obtained relevant national construction land allocation written decision and project approval of land department, with relevant procedure completed. Bus Parking Lot of Xi’an National Civil Aerospace Industrial Base: On December 12, 2012, Land Acquisition and Demolition Office of Xi’an National Civil Aerospace Industrial Base signed land acquisition agreement with villager committee of Xinzhaizi Village of Weiqu Subdistrict Office of Chang’an District, the acquisition scope: to the boundary of Xiaojing Village in the east, to the boundary of Xinhe and Jiuzhaizi Village boundary in the south, to the boundary of Sifujing Village in the west, and to the boundary of Xibei Village in the north. The area of land acquired is about 800 mu, and the actual measured area is 838.5120 mu. In the project, 62.3 mu of land is confirmed to acquired, and the land within the scope has been acquired.

Table 5 Implementation schedule for land acquisition (By the end of Jan 2019)

Land APs Actual APs No acquisitio ( ) Category Type Project name n in the (person ha (person . updated ) ) RP (ha) Road & bridge 1 Keji 2nd Road 17.18 6533 17.18 6320 improvement 2 Dazhai Road 9.2 585 06 535 Road sub-project East section of 13.34 1000 0 0 3 (Xi’an Kunming Road

5 In April 2015, Weiyang District Daxing Office signed the agreement with Jintao Company, and the demolition was completed in May 2015. A toilet was built 800m away from the original site for the use of Jintao Company in a manner of reconstruction, with the same area of original site. Besides, the relocation subsidy of CNY 15,000 is provided and the original contract agreement is still valid. 68.4ha of land obtained use right in the way of renting 25

Municipal West section of 0 0 0 4 Public Utility Kunming Road

Bureau) Zhuhong 0 0 0 0

Road-Fengcheng 5 4th Road

Interchange

Zhuhong 273 1.61 0

6 Road-North 2nd 0.67

Ring Interchange

Hongmiaopo 0.52 131 0 456 7 Interchange Interchang Xinghuo Road 1.33 0 0 2000 e 8 Interchange

Fengcheng 8th 10 0 0 0

Road-Beichen 9 Avenue

Interchange

Fengcheng 8th 5.633 175 0 228

10 Road-Taihua Road

Interchange

Bus Parking Lot of 6.67 0 8.06 0

Comprehensiv 11 Xi’an North Railway e traffic facility Station Bus subproject Bus Parking Lot of 0 4.15 0 parking lot (Xi'an Xi’an National Civil 12 6.67 Infrastructure Aerospace

Construction Industrial Base

Investment Metro Yuhuazhai 0 0 0

Group Co. Ltd.) transfer 13 Comprehensive 3.33

hub Transfer Station

26

(some station in the

west part of Xi’an

City)

Comprehensive 0 0 0

Transfer Hub of

Xian Station of 14 3.33 Xi'an International

Trade & Logistics

Park

Yuhuazhai Bus 0 0 0 15 0.53 Parking Lot

Bus Parking Lot of 0 0 0

Xi’an International 16 0 Trade & Logistics

Park

Urban Multistorey Parking 0 0 0 multistorey 17 Garage of Xizhan 0 parking Community garage Ring Road-Taihua 0 0 0

18 Road Multistorey 0.53

Parking Garage

Xianning 0 0 0

Road-Dongguanna 19 0.53 n Street Multistorey

Parking Garage

Mujiangwang 0 0 0 20 0.55 Refueling Station Refueling Refueling Station of 0 0 0 station 21 Bus Parking Lot of 0.55

Xi’an National Civil

27

Aerospace

Industrial Base

Refueling Station of 0 0 0

22 Xi’an North Railway 0.55

Station

Yuhuazhai 0 0 0 23 0.55 Refueling Station

Refueling Station of 0 0 0

Xi’an International 24 0.55 Trade & Logistics

Park

Total 82.213 8697 31.1 9539 2. Progress of house demolition Keji 2nd Road: House demolition for former remained 29 affected households in Xioayanzhuang Village and staff building of Xi’an International University has been completed. In which, house demolition for east section of staff building (No. 1) of Xi’an International University was complete in May 2017, resettlement for 29 affected households in Xioayanzhuang Village was completed in July 2017, at the same time, all house demolition involved was completed, with a total floor area of about 50,000 m2, and construction site was handed over to construction unit at the end of July. Up to Jan 31, 2019, all house demolition involved in Keji 2nd Road has been completed, road construction site has been handed over, and municipal unit is implementing utility tunnel construction (see Fig. 2-4). The road is under construction, part of the east end and west end have been completed, it is planned to have transport service by the end of March, 2019 (Half of the Road).

28

Figure 2 Situation map of construction site of road and pipeline corridor in Keji 2nd Road

Figure 3 Situation map of construction site of west section of the Keji 2nd Road

29

Figure 4 Situation map of construction site of middle section of the Keji 2nd Road Dazhai Road: All the affected houses in the range of the two industrial parks (Yuhua Industrial Park and Heping Industrial Park) involved in the construction of Dazhai Road has been dismantled up to July 25, 2018, the leftover problems of the project have been solved, and all house demolition involved have been finished which involves the residents’ houses of 29 households in Erfuzhuang Village, with the total demolition area of 14,930.13 m2. All these houses have been demolished. And involved 11 enterprises in Yuhua Industrial Park of Yanta District are demolished, with the demolition area of about 16,336.26m2. The demolition of the houses of the four enterprises involved in Heping Industrial Park has been finished with a total demolition area of 35,936.78 m2. Road construction has almost been finished, in which, the construction of section from Beishiqiao Village to Minqizhai Village has been finished on May 17, 2018. Interchange of Hongmiaopo: The impacted households total 107, 106 households (residents) are included, the residence area affected is about 5375 m2, one enterprise and public institution is included, the affected area is about 557m2, the area of the house affected is about 5932 m2.Up to January 2019, land acquisition of all the houses involved in the project has been completed, and the total house demolition area is 5,929.16 m2. To date, the acquisition of all the impacted houses has been completed. Xinghuo Road Interchange: The impacted households total 76, including 65 individual households (residents), 11 enterprise and public institutions, and the total area of impacted house is about 9,906m2. Land acquisition and house demolition involved in the project was completed before June 31, 2017. Because the project design changes, the 11 impacted

30 households in Fenghe Village and the railway maintenance building at the west side of Xinghuo Road Interchange and railway collapsed houses will not be impacted. By January 2019, the acquisition of all the impacted houses has been completed, all the impacted houses have been demolished, and the demolition area is 9,800 m2, including 5,944 m2 of residential area and 3,870m2 of non-residential area. Fengcheng 8th Road-Taihua Road Interchange: All the affected houses for the project have been dismantled with a housing area of 19,115 m2, in which, the 57 shops involved at the corner of northeast have been dismantled in August 2016. The involved greening square and temporary building at the corner of northwest have been dismantled before November 30, 2016. So far, the major body of the flyover has almost been finished, the two directions of east-west and south-north are all open to traffic.

31

Table 6 Implementation progress of residential housing acquisition (up to the end of Jan 2019)

Residential housing

Category Type No. Engineering name Updated RP Actual Amou (m2) APs (m2)Area nt Area (m2) (person) Amount (m2) APs (person)

1 74 87849.48 293 74 93749.48 293 Keji 2nd Road

Road 2 Dazhai Road 29 14930.13 110 29 14930.13 110

Road & bridge 3 East section of Kunming Road 0 0 0 0 improvement 4 West section of Kunming Road

subproject Zhuhong Road-Fengcheng 4th 5 0 0 0 0 0 0 (Xi’an Road Interchange

Municipal Zhuhong Road-Fengcheng 4th 6 0 0 0 0 0 0 Public Utility Interchange Road Interchange

Bureau) Zhuhong Road-North 2nd Ring 7 0 0 0 106 53757 0 Interchange

8 Hongmiaopo Interchange 0 0 0 65 38708 0

7 The actual demolition area comes from the Liaison Office for Xincheng District and Lianhu District in The Protection and Transform Office for the Site of the Damingong Palace in Xi’an Qujiang 8 The actual demolition area comes from the Liaison Office for Xincheng District and Lianhu District in The Protection and Transform Office for the Site of the Damingong Palace in Xi’an Qujiang 32

9 Xinghuo Road Interchange Not updated 0 0 0 0

Fengcheng 8th Road-Beichen 10 0 0 0 0 0 0 Avenue Interchange

Bus Parking Lot of Xi'an North 11 0 0 0 0 Railway Station Bus parking lot Bus Parking Lot of Xi’an National 12 0 0 0 0 Civil Aerospace Industrial Base Comprehensive Yuhuazhai Comprehensive traffic facility 13 Transfer Station (some station in 0 0 0 0 subproject Metro transfer the west part of Xi’an city) (Xi’an Urban hub Comprehensive Transfer Hub of Infrastructure Not updated 14 Xi’an International Trade & 0 0 0 0 Construction Logistics Park Investment Urban 15 Yuhuazhai Bus Parking Lot 0 0 0 0 Group Co., multistorey 16 Bus Parking Lot of Xi’an Ltd.) parking garage International Trade & Logistics 0 0 0 0

Park

17 Multistorey Parking Garage of 0 0 0 0 Xizhan Community

33

18 Ring Road-Taihua Road 0 0 0 0 Multistorey Parking Garage

19 Xianning Road- Dongguannan

Street Multistorey Parking 0 0 0 0

Garage

Refueling 20 Mujiangwang Refueling Station 0 0 0 0

Station 21 Refueling Station of Bus Parking

Lot of Xi’an National Civil 0 0 0 0

Aerospace Industrial Base

22 Refueling Station of Xi'an North 0 0 0 0 Railway Station

23 Yuhuazhai Refueling Station 0 0 0 0

24 Refueling Station of Xi’an

International Trade & Logistics 0 0 0 0

Park

Total 103 102779.61 403 274 117924.6 403

34

Table 7 Implementation progress of housing acquisition of enterprise and public institution (up to the end of Jan 2019)

Category Type No. Engineering name Enterprise and public institution

Updated resettlement plan Actual Amount Area APs Amou (m2) APs (m2) (person) nt Area (m2) (person) Road & bridge Road 1 Keji 2nd Road 6 63863.45 6240 5 53347.2 5440 improvement 2 Dazhai Road 15 37004.56 475 14 35936.78 425 subproject 3 East section of Kunming Road 2 71,000 1000 0 0 0

(Xi’an 4 West section of Kunming Road 0 0

Municipal Interchange 5 Zhuhong Road-Fengcheng 4th 0 0 0 0 0 0

Public Utility Road Interchange

Bureau) 6 Zhuhong Road-North 2nd Ring 1 11,719 273 0 0 0

Interchange

7 Hongmiaopo Interchange 1 7,855 131 1 557 456

8 Xinghuo Road Interchange 09 0 0 11 5944 2000

9 Fengcheng 8th Road-Beichen Not updated 0 0 0

Avenue Interchange

10 Fengcheng 8th Road-Taihua 2(31) 4,960 175 1(20) 19115 228

9 Xinghuo Road Interchange involves demolition of several enterprises and public institutions and stores; however, this data is not available in the updated Resettlement Plan in 2013.

35

Road Interchange

Comprehensive Bus parking lot 11 Bus Parking Lot of Xi'an North Not updated 0 0 0 0 traffic facility Railway Station subproject 12 Bus Parking Lot of Xi’an 0 0 0 0

(Xi’an Urban National Civil Aerospace

Infrastructure Industrial Base

Construction Metro transfer 13 Yuhuazhai Comprehensive 0 0 0 0

Investment hub Transfer Station (some station

Group Co., in the west part of Xi’an city)

Ltd.) 14 Comprehensive Transfer Hub 0 0 0 0

of Xi’an International Trade &

Logistics Park

Urban 15 Yuhuazhai Bus Parking Lot 0 0 0 0

multistorey 16 Bus Parking Lot of Xi’an 0 0 0 0

parking garage International Trade & Logistics

Park

17 Multistorey Parking Garage of 0 0 0 0

Xizhan Community

18 Ring Road-Taihua Road 0 0 0 0

36

Multistorey Parking Garage

19 Xianning Road- Dongguannan 0 0 0 0

Street Multistorey Parking

Garage

Refueling 20 Mujiangwang Refueling 0 0 0 0

Station Station

21 Refueling Station of Bus 0 0 0 0

Parking Lot of Xi’an National

Civil Aerospace Industrial

Base

22 Refueling Station of Xi'an 0 0 0 0

North Railway Station

23 Yuhuazhai Refueling Station 0 0 0 0

24 Refueling Station of Xi’an 0 0 0 0

International Trade & Logistics

Park

Total 27 196402 8294 32 114899.98 8549

37

Zhuhong Road-North 2nd Ring Interchange: The lands of the project all are state-owned land. Up to now, the land acquisition and demolition of this interchange has been completed. Zhuhong Road-Fengcheng 4th Road Interchange: According to the updated resettlement report of first batch of subprojects, Zhuhong Road-Fengcheng 4th Road Interchange does not involve land acquisition and demolition. However, it involves the removal of some woods and water supply pipes, and this work has already been done.

V. Execution of Resettlement Policy 1. Land acquisition

See the actual executive standards for land acquisition of all projects in Table 8.

38

Table 8 Actual implementation standard for land acquisition

Category Type No. Project name Land acquisition standards in the Actual updated resettlement plan Road Keji 2nd Road Cultivated land, construction land (third

category land), construction land (second RMB 150,000 Yuan/mu

1 category land), homestead, nursery: RMB (including social security

150,000 Yuan/mu (including social security fee)

fee) Current rental: RMB 3,500 Road & bridge Dazhai Road RMB 125,000 Yuan/mu (including social Yuan/mu (first batch); RMB improvement security fee). No difference for cultivated 5,000 Yuan/mu (renewal of 2 the second batch); uniform subproject land, nursery, homestead, and construction collection when urban (Xi’an land village reconstruction

Municipal 3 East section of Kunming Road RMB 100,000 Yuan/mu Not implemented

Public Utility 4 West section of Kunming Road

Bureau) Zhuhong Road-Fengcheng 4th 5 - - Road Interchange

Zhuhong Road-North 2nd Ring - Interchange 6 RMB 100,000 Yuan/mu Interchange

7 Hongmiaopo Interchange RMB 120,000 Yuan/mu Not implemented

8 Xinghuo Road Interchange RMB 120,000 Yuan/mu Not implemented 39

Category Type No. Project name Land acquisition standards in the Actual updated resettlement plan Fengcheng 8th Road-Beichen Not updated Not implemented 9 Avenue Interchange

Fengcheng 8th Road-Taihua RMB 120,000 Yuan/mu RMB 100,000 Yuan/mu- 10 Road Interchange RMB 120,000 Yuan/mu

Bus Parking Lot of Xi'an North Not updated RMB 844,000 Yuan/mu 11 Railway Station

Bus parking lot Bus Parking Lot of Xi’an RMB 68,000 Yuan/mu Comprehensive 12 National Civil Aerospace traffic facility Industrial Base subproject Metro transfer hub Yuhuazhai Comprehensive Not implemented (Xi’an Urban 13 Transfer Station Infrastructure Comprehensive Transfer Not implemented Construction 14 Hub of Xi’an International Investment Trade & Logistics Park Group Co., Urban multistorey 15 Yuhuazhai Bus Parking Lot Not implemented Ltd.) parking garage Bus Parking Lot of Xi’an Not implemented

16 International Trade & Logistics

Park 40

Category Type No. Project name Land acquisition standards in the Actual updated resettlement plan Multistorey Parking Garage of Not implemented 17 Xizhan Community

Ring Road-Taihua Road Not implemented 18 Multistorey Parking Garage

Xianning Road- Dongguannan Not implemented

19 Street Multistorey Parking

Garage

Mujiangwang Refueling Not implemented 20 Station

Refueling Station of Bus

Parking Lot of Xi’an National 21 RMB 68,000 Yuan/mu Civil Aerospace Industrial

Refueling Station Base

Refueling Station of Xi'an Not implemented 22 North Railway Station

23 Yuhuazhai Refueling Station Not implemented

Refueling Station of Xi’an 24 Not implemented International Trade & Logistics 41

Category Type No. Project name Land acquisition standards in the Actual updated resettlement plan Park

42

2. Housing acquisition See the actual executive standards of housing acquisition of each project in Table 9.

Table 9 Actual executive standards of housing acquisition

Land acquisition standards in Category Type No. Engineering name Actual the updated RP Enterprise and public 45 households in Dingjiaqiao has been institution: resettled, all of which select resettlement of Reinforced concrete structure house property rights. There are 186 RMB 1,264 Yuan/m2, settlement houses, with actual resettlement brick-concrete structure RMB area of 15,770m2, in which, 37 households 710 Yuan/m2, other structures select 115m2 of house, totaling 39 sets; 18 RMB 350 Yuan/m2 households select 95m2 of house, with a Removal compensation: confirm total of 22 sets; 14 households select 85m2 through negotiation with equity of house, with a total of 22 sets; and 32 department; households select 75m2 of house, totaling Road and Resettlement compensation 63 sets; and 23 households select 65m2 of fee(temporary): compensate house, 40 sets in total. interchange according to the compensation 29 households in Xiaoyan Village have standards for enterprise, and pay moved, all of them are compensated in improvement 0.35% of the evaluated value of house property exchanging, the actual area Road 1 Keji 2nd Road houses involved in acquisition of rehabilitation is 13997 m2, the subproject(Xi’An per month resettlement building are mainly built in the Shutdown subsidy(temporary): house type of 50、90、120m2, the detailed Municipal Public negotiate according to the house exchange resettlement is executed income of the first six months of according to the policies stipulated in The Utility Bureau) enterprise; Implementation Plan for Compensation and Residential house: Resettlement for Demolition and Relocation Brick-concrete structure: RMB of the Third and Fourth Groups of 2 3,500 Yuan/m (monetary Xiaoyanzhuang Village in Yuhua Area of Xi resettlement for the first and 'an High-tech Industries Development Zone; 2 second floor), RMB 774 Yuan/m Implementation Rules for Compensation (beyond the first and second and Resettlement for Demolition and floor); Relocation of the Third and Fourth Groups Removal subsidy: RMB 1,000 of Xiaoyanzhuang Village in Yuhua Area of Yuan/household Xi 'an High-tech Industries Development Temporary transitional fee: RMB Zone; Supplementary Agreement, the 43

360 Yuan/person/month, the detailed policies of house exchange is as proper transitional period is follows: supposed to be 30 months; It is stipulated in the Xi 'an High-tech Living subsidy for transitional Industries Development Zone Yuhua period: RMB 410 District Xiaoyanzhuang Village Third, Forth Yuan/month/person, the proper Groups of Shantytown Reconstruction transition period is supposed to Compensation Resettlement be 30 months Implementation Plan that, in principle, the resettlement floor area per capita of agricultural population shall be not less than 65m2. Each people shall be granted a compensation house of 15 m2 for business purpose. It is stipulated in the Xi 'an High-tech Industries Development Zone Yuhua Area Xiaoyanzhuang Village Third, Forth Groups of Shantytown Reconstruction Compensation Resettlement Implementation Rules that, within the bonus period, according to the "area used by the household" of homestead written in the Collective Land Using Certificate held by the relocation household, the one-floor or two-floor building built on this land shall be relocated by the rule of “a new one for a demolished one”, which means to interchange without making compensations, the maximum area of interchange resettlement shall not exceed 333 m2. It is stipulated in Supplementary Agreement that: Those who have signed the Settlement and Compensation Agreement in time and deliver the house, in the event four or more people are included in one household, the replacing house settlement shall go with the standard of 100m2 per capita.

44

For the first and second floor buildings with a floor area less than 30m2 (including 30m2) as specified in the Collective Land Using Certificate, the transition subsidy shall be 6 CNY per square meter per month; As for the part that exceeds 30m2, it shall be 4 Yuan per square meter per month, or the agricultural population demolished in the "Collective Land Using Certificate", they could also choose the standard of 360 CNY per head per month to calculate the transition fee, choose one from the above-mentioned two. Those who sign the Relocation Compensation Agreement within the publicity award period and deliver the house will enjoy the relevant incentive: The relocation household who are also registered agricultural population and participate in the collective property distribution, will be given the allowance of 300 CNY per month per head, transition fees 7 CNY per square meter, calculated according to the exchange residence area, the transition period lasts for 36 months, and will be made an one-off payment according to the agreement; each agricultural population will be awarded a house of 15m2 for business purpose, for those who deliver the house within the bonus period, another house of 5m2 for business purpose will be given to them; the entity resettlement households that have delivered the houses on time within the bonus period for demolition and relocation, and those who have the "Collective Land Using Certificate" or are qualified in the confirmation of homestead right enjoy a parking space free of charge. 45

Other Policies: 1.Locational price for the compensation and demolition of Xiaoyanzhuang Village is 900 CNY per m2. 2.A bonus of 200 Yuan per m2 will be given to the unfinished third and fourth floor of the buildings built on the legal homestead. 3.For those who signed the Relocation Agreement within the bonus period, the evaluated price of residual value of the building outside the replacement area (brick building) will enjoy a certain uprising. The enterprises involved shall be compensated based on the valuation price offered by evaluation company. Enterprise and public 20 households from other villages: has been compensated according to the institution: evaluation of evaluation company. Brick-concrete structure RMB 9 households within the village: still in transitional period, and the transition fee is 774 Yuan/m2, other structures RMB 6 Yuan/ m2/ month. Because some RMB 350 Yuan/m2 farmers have not been resettled with six months designated in the agreement, so the Transitional fee: RMB 500 transitional allowance received is RMB Yuan/person/month, the proper 90,000 Yuan/household/year, the fee is 2 Dazhai Road three times of fee not overdue. transitional period is supposed to At present, reconstruction (has not be less than 24 months; commenced and not formulated compensation standard) of urban village Removal payment: confirm has not been carried on. through negotiation with equity 16 enterprises and public institutions: resettlement through monetary department; compensation method (according to the Shutdown subsidy: negotiate evaluation price of evaluation company)

according to the income of the

46

first six months of enterprise; Residential house: Brick-concrete structure: RMB 2,900 Yuan/m2 (resettlement due to urban village transformation, conversion into money for equity swap parts), RMB 774 Yuan/m2 (monetary compensation); Relocation subsidy: RMB 1,000 Yuan/household Temporary transitional fee: RMB 6 Yuan/household/month/ m2, the essential transitional period is supposed to be 30 months; Living subsidy for transitional period: RMB 410 Yuan/month/person, the proper transitional period is supposed to be 30 months Residential house: 3 East section of Kunming Road Not implemented Brick-concrete structure: RMB 4 West section of Kunming Road 3,200 Yuan/m2; Not implemented Zhuhong Road-Fengcheng 4th Other structures: RMB 1,500 No house acquisition 5 Yuan/m2; Road Interchange Interchange Removal subsidy: RMB 1,000 nd Zhuhong Road-North 2 Ring Yuan/household - 6 Road Interchange Temporary transitional fee: RMB

47

4 Yuan/household/month/m2, the The enterprises involved shall be essential transitional period is 7 Hongmiaopo Interchange compensated based on the valuation price supposed to be 30 months; Enterprise and public offered by evaluation company. institution: The enterprises involved shall be Brick-concrete structure: RMB 3,200 Yuan/m2; compensated based on the valuation price Other structures: RMB 1500 offered by evaluation company. Yuan/m2; Removal fee: confirm through negotiation with equity 8 Xinghuo Road Interchange department; Transitional fee: RMB 500 Yuan/person/month, the proper transitional period is supposed to be 24 months; Shutdown subsidy: negotiate according to the income of the first six months of enterprise Fengcheng 8th Road-Beichen Not updated Not implemented 9 Avenue Interchange

Enterprise and public The enterprises involved shall be institution: Fengcheng 8th Road-Taihua compensated based on the valuation price 10 Brick-concrete structure: RMB Road Interchange 3,200 Yuan/m2; offered by evaluation company;

Brick-concrete (non-residential ) 57 shops are resettled in cash

48

and other structures: RMB 1,500 compensation (based on the valuation price Yuan/m2; offered by evaluation company) Removal fee: confirm through negotiation with equity department; Transitional fee: RMB 500 Yuan/person/month, the proper transitional period is supposed to be 24 months; Shutdown subsidy: negotiate according to the income of the first six months of enterprise; Bus Parking Lot of Xi’an North Not updated No house acquisition Comprehensive 11 Railway Station transportation Bus Parking Lot of Xi’an No house acquisition facilities Bus parking 12 National Civil Aerospace subproject( Xi’an lot Industrial Base Urban Yuhuazhai Comprehensive Not implemented Infrastructure 13 Transfer Station Construction Metro Comprehensive Transfer Hub of Investment transfer 14 Xi'an International Trade & Group Co., Ltd) junction Logistics Park

49

station 15 Yuhuazhai Bus Parking Lot

Bus Parking Lot of Xi'an

16 International Trade & Logistics

Park

Urban Multistorey Parking Garage of 17 Multistorey Xizhan Community parking Ring Road-Taihua Road 18 garage Multistorey parking garage

Xianning Road-Dongguan

19 Nanjie Multistorey parking

garage

Refueling Station of Xi’an No house acquisition

20 National Civil Aerospace

Industrial Base Bus Parking Lot

Refueling Mujiangwang Refueling Not implemented 21 station Station

Refueling Station of Xi’an North No house acquisition 22 Railway Station

23 Yuhuazhai Refueling Station Not implemented

50

Refueling Station of Xi’an Not implemented

24 International Trade & Logistics

Park

51

Keji2nd Road: The buildings which cover an area of 147096.7 m2 are demolished for this project, among which, the area of the civil houses is 93749.48 m2. 45 households moved away from Dingjiaqiao, involving a total demolition area of 43139.9 m2, among which, the area for exchange is 14999.46m2; 29 households moved away from Xiaoyanzhuang Village, involving a total demolition area of 46186 m2, the area for exchange is about 13997 m2. Dazhai Road: Up to July 25, 2018, the demolition of involved land acquisition has been finished, in which, the residential houses of 29 households in Erfuzhuang Village, Yanta District involved have been dismantled with a total demolition of 14,930.13 m2, the houses of involved 11 enterprises in Yuhua Industrial Park, Yanta District have been dismantled with a total demolition of 16,336.26m2, the houses of involved 4 enterprises in Heping Industrial Park, Lianhu District have been dismantled with a total demolition area of 35,936.78 m2. Zhuhong Road-North 2nd Ring: the land for the project shall be provided by Fanbei Urban Village after transformation. The land is planned to be land for roads, and is levied by Fanbei Village; Municipal Public Utility Bureau doesn’t need to contribute fund. Xinghuo Road Interchange: The project obtained the approval of Decision of Xi’an Municipal People's Government on House Acquisition (Shi Fang Zheng Gao Zi [2016] No.2) on August 4, 2016, and 11 enterprise and public

10 institutions and 65 individual households were impacted by land acquisition and house demolition. In which, 1 household (enterprise) accepted physical resettlement, the resettlement site is located in Bafuzhuangyuan Community, Hanyuan Road, Xincheng District, the resettlement building has been completed and the key will be given to the enterprise; 75 households accepted monetary resettlement, and the acquisition compensation has been completed in August 2017. Hongmiaopo Interchange: The project obtained the approval of Decision of Xi’an Municipal People's Government on House Acquisition (Shi Fang

10 The data from last report shows that there are 9 enterprise and public institutions and 67 individual households. In the investigation, Xinghuo Road project Office told that the former one is basic data, and that of this time is confirmed data.

52

Zheng Gao Zi [2016] No.1) on March 22, 2016, totally 107 households signed the Agreement on Resettlement, in which, 69 households accepted monetary resettlement. According to the stipulations of compensation plan for house acquisition of Hongmiaopo Interchange Project, the households involved in house acquisition who choose monetary compensation will be compensated according to the estimated value of the house involved in acquisition,and will be given a subsidy in accordance with 20% of the estimated value of the house

11 involved in acquisition . 38 households chose physical resettlement, the resettlement sites are Zhujiang New Town Community at North 2nd Ring Road in Weiyang District and Harmonious City Community at Wenjing Road in Lianhu District, in which, 32 households are resettled in Zhujiang New Town Community and two households are resettled in Harmonious City Community. The buildings for resettlement are delivered in October 2016 and all the households have moved into the two communities. Fengcheng 8th Road – Taihua Road: About 191,15m2 floor area has been demolished, and 120,000m3 waste has been cleared for the project, including the waste hill and construction waste in the southeast and northeast corner of the interchange. In which, the 57 stores involved at the northeast corner have been demolished in August 2016, the waste within the red line of road has also been cleared completely and the site has been turned over at the end of August; the greened square and temporary buildings at the northwest corner involved all have been demolished, and the site has been turned over by November 30, 2016. 3. Economy recovery Keji 2nd Road: The resettlement building in Dingjiaqiao Community at the urban village reconstruction resettlement community of Dingjiaqiao Village is located at the west side of Dingjiaqiao Village. Resettlement building project occupies an area of 37.8 mu, with total construction area of about 170,000 m2,

11The data statistics in last report is that 109 households signed the agreement, 73 households accepted monetary resettlement and 34 households accepted physical resettlement. During the process of this investigation, the staff of Hongmiaopo Project Office told that the previous data is a real situation data, but the data of this time is the final established data.This “compensation” is additional 20% subsidy according to the stipulation of House Acquisition Compensation Scheme for the project of Hongmiaopo Interchange, levied residents who choose to be compensated by currency should be compensated based on the estimated value of the levied house, and will be given an extra 20% compensation according to the estimated value of the levied house.According to the survey, in order to encourage monetary resettlement and speed up the demolition process, the policy was determined after discussion with the relocated households.

53

among which, residence area is 140,000 m2, a total of 340 households are resettled. On October 18, 2011, the resettlement building project in Dingjiaqiao Village was started, with four resettlement buildings, 1,487 sets of apartment. There are five kinds of areas of resettlement apartments, 65 m2, 75 m2, 85 m2, 95 m2 and 115 m2 respectively. On April 22, 2015, the work of moving back to Dingjiaqiao Village was started. By the end of April 2015, the reconstruction work of urban village has been completed basically. 29 households involved in Xiaoyanzhuang Village agreed to be resettled, and so far, they have all moved and all the houses have been dismantled, the 29 households will be incorporated to the urban village transformation of Xi’an, and will be resettled and compensated together with the whole village according to the urban reconstruction plan 6. The reconstruction of urban village project has been started and is in the process, in the afternoon of February 11, 2018, Yuhuazhai Subdistrict, Urban Reconstruction Office of Yuhua Area, the village Party branch and village committee of Xiaoyanzhuang Village, and its villager’s representatives of 3rd. and 4th group had a relevant discussion on the reconstruction of the 3rd and 4th group of Xiaoyanzhuang Village, they all agreed to plan the resettlement building for Xiaoyanzhuang Village at the southwest corner of the cross of Keji 2nd Road and Jingwu Road. The demolition area of enterprise and public institution is 63,863.45 m2, in which 6 enterprises and public institutions are involved, and the specific resettlement details are as follows: (1)For the impact of Shaanxi Sirui Industrial Co., Ltd. suffered from land acquisition and house demolition, Yuhua Demolition Office in Hi-tech Industries Development Zone has reached a consensus with the enterprise regarding the demolition matter and has signed an agreement. The enterprise chose an integral allocation. The project implementation organization and the local government assist in the selection of resettlement for units to be demolished, and handling of relevant procedures; The enterprise re-selected the new plant site near Jinye 1st Road, Xi'an High-tech Industries Development Zone, and started the new plant construction and equipment relocation. During this period, the enterprise made a normal production and operation without affecting by land acquisition and house demolition. The affected staff did not have a downtime and their lodging problem has received the attention and support of the government who offered

54

a green channel for the staff and gave priority to their application for public rental apartments in Xi’an Hi-tech Industries Development Zone (Jingye Apartment). Now part of staff have applied for the public rental apartment and lived there, which greatly solves the lodging and living improvement problem. The new plants and production workshops were opened to use in June 2015. Xi’an High-tech Industries Development Zone has done great help to the development of this enterprise during its growth process. Now it renamed Shaanxi Siri Advanced Materials Co., Ltd., with two production and operation sites. One is located at No. 12, Zhangba 7th Road, Xi’an Hi-tech Industries Development Zone, Xi'an City, Shaanxi Province, covering an area of 72 mu, and its main equipment are the office buildings and production workshops (see Figure 5, 6), and the staff there are still lodging in the Jingye Apartment of Xi’an Hi-tech Industries Development Zone; The other is located at No. 60 Weiyi Road, Xi’an Hi-tech Industries Development Zone, Xi'an, Shaanxi Province (in the Yuhua Industrial Park), covering an area of 40 mu, including production workshops and five-story staff quarters (see Figures 7, 8). The combination of high-quality industrial environment and Sirui's own industries bring strong development momentum. In 2018, the company achieved a 21% increase in sales revenue, surpassed CNY 480 million while achieving safety production with zero industry injury. In recent years, the company's efficiency and staff’s income are stable. Now the staff' s per capita wage reaches 4000-4500 RMB/month, which is higher than before.

55

Figure 5 The plant sites of Shaanxi Sirui Advanced Materials Co., Ltd. located at the No.12, Zhangba 7th Road, Xi’an Hi-tech Industries Development Zone

Figure 6 Jingye Apartment in Xi’an Hi-tech Industries Development Zone

56

Figure 7 The plant sites of Shaanxi Sirui Advanced Materials Co., Ltd. located at the No.60, Weiyi Road, Xi’an Hi-tech Industries Development Zone

Figure 8 Staff’s dormitory in plant site of Shaanxi Sirui Advanced Materials Co., Ltd. located at the Yuhua Industry Park (2) Xi’an Nylon Products Factory is the one to be dismantled in whole. After receiving monetary compensation, it selected a new address in Chang’an District, built a factory, restored production, and the all affected staff has removed to the new factory. (3) The demolition of Dingjiaqiao Agriculture Product Market will impact 200 tenants in the market. Tenants run business at

57

designated positions and pay booth fees to market manager without undertaking the construction cost. Moreover, they signed short-term contracts with the market and pay booth fees every half a year. Therefore, the demolition has little impact on them. The similar market can be found in Hujiazhuang, 500m away from former market, Yuhuazhai Community, 2km away from former market; hence, tenant is able to find suitable place nearby to operate continuously; the market owner can obtain monetary compensation of market construction and booth construction. (4) The road construction will impact a dormitory building of Xi’an International University (XAIU) including 48 teacher households. Yuhuazhai Urban Transformation Office of Hi-tech Industrial Development Zone reaches an agreement with XAIU through negotiation that XAIU should undertake removal, transition and resettlement compensation of its employees affected by land acquisition and demolition; the settlement building shall be undertaken by the new community project implementing unit of XAIU and the number of compensated buildings should be equal to the demolished number. (5) The land acquisition and demolition of the project will separate Xi’an Bodi School into two parts. Yuhuazhai Urban Transformation Office will build a foot bridge on the east section of Keji 2nd Road for the school, so as to connect the two campuses and ensure the personal safety of teachers, students and pedestrians as well as smooth traffic. (6) Tenants in Fenghui Apartment all signed short-term contracts with landlord, and they will negotiate the payment time for rent, which are usually one or three months. Therefore, demolition has little impact on tenants, and they can find another place to live. The owner of Huifeng Apartment can receive monetary compensation in one time in accordance with the evaluated price given by the evaluation company. Dazhai Road: According to the requirement of municipal government and the working arrangement of District Committee and Government, as a village team to be constructed as “Quality Xi’an” of Xi’an City, Erfuzhuang will start its reconstruction in 2018, displacement and resettlement in 2019. The 9 households can receive transitional compensation with each passing year since 2011 in the order of contracting time. The compensation standard is CNY 5 /m2 per month for house with an area of 30m2 or below with one or two floors; as for houses with an area of over 30m2, the compensation for the part of over 302 is CNY 3 /m2 per month. Because of failure in completing

58

resettlement within the 6 months stipulated in the contract, currently some of the households have received annual transitional compensation of about CNY 90,000, which triples the overdue payment. In addition, CNY 360 Yuan/ person/ month of transitional living allowance should be provided for affected peasant household in accordance with subsistence allowances for the urban poor. After visit and investigation on site, one enterprise transformed into a building materials market within the 11 enterprises in Yuhua Industrial Park, Yanta District, two of them still operate in the park, the other eight enterprises has moved away and do not operate any more after they received the compensation, in which, Shaanxi Delong Industry and Trade Co., Ltd. is affected by the house demolition, do not operate any more, it has transformed into Erfuzhuang Building Materials Market after a rebuilding, the market is located at No. 2, Fuyuan Road, Yuhuazhai Subdistrict, Xi’an, and is implementing the unified management with independent facade rooms and shops, individual households can operate respectively. So far, all the operation households in the market do their business smoothly, the income level of affected people have been increased, and their living condition improved greatly. Xi’an Huatong Electrical Equipment Co., Ltd. is located a No.17, Fuyuan 2nd Road, Yuhua Industrial Park, Yanta District, Xi’an, part enclosure buildings involved within the boundary lines of road of Dazhai Road have been dismantled, and the corresponding compensation has been paid. Because of the small impact of land acquisition and house demolition on the company, it still operates in normal at the original address in Yuhua Industrial Park, and the operation has not been affected by this land acquisition and house demolition. For Tianwei Food Co., Ltd., part of the warehouse and plant building has been dismantled, which is not a large scale, hence the company also still do their business normally in the park, the operation of the company has been affected little, the living condition and income level of affected people are not affected.

Fengcheng 8th Road-Taihua Road: As a whole, most lessee will not do their previous experienced business after they received the cash compensation, but some lessee still operate in the building materials market at Fengcheng 8th Road, according to the commitment to the affected lessee

59

made by Xi’an Daming Palace Hongqi Building Materials Market, the affected lessee has been offered proper settlement in the market, and can go on operating the business, their operating conditions are not affected, as well as their income level. After a visit and investigation, the former Meiyu Stairs mainly sells stairs with a annual profit of CNY 40000 and an operation area of 20 m2, now it moved to the building materials market at Fengcheng 8th Road, going on their business with an operation area of 30 m2, the annual profit is not affected. 4. Other facilities

According to the evaluation of legal assessment agency, compensation should be made in accordance with replacement price of facilities. Compensation standard is shown as follows:

Table 10 Compensation standard table for auxiliary facilities

Compensation Compensation

standard standard Category Unit Category Unit (RMB (RMB

Yuan/unit) Yuan/unit)

Mature trees Tree 300-500 Electric wire M 10

Telecom Young trees Tree 50 M 10 wire

Enclosure M 100 Pole Piece 330

Optical Greenhouse M 100 M 100 cable

Toilet M2 1000 Transformer Transformer 30000

High Motor-pumped Room 100000 voltage Tower 1500000 well tower

Lawn Well 5 Canal M 100

Grave M2 1000 Water pipe M 50

60

B Various special facilities, including water conservancy facility, communication facility, electric power facility, etc., should be compensated by professional assessment agencies in accordance with actual construction cost or replacement price. 5. The resettlement information of affected households The information on the resettlement compensation of the affected households of all the sub-projects, including the number of affected families, compensation payment in cash, house compensation, place of relocation or name of the community and the date of resettlement, is listed in Table 11.

Table 11. Housing Resettlement Information of Affected Households (by February 2019)

Name of the Number of Compensatio Settleme Place of the

Project the n in Cash nt House communities Expected

Household (CNY) (m2) date for

Affected resettleme

nt

Keji 2nd Road 29 Southwest March

Households 15121265.00 13997 corner of the 2023

in crossroad of

Xiaoyanzhu Keji 2nd Road

ang Village and Jing 5th

Road

Xinghuo 76 71390000.00 2399.49 Bafuzhuangyua March

Road households n Community 2019

Interchange

Hongmiaopo

Interchange 107 Zhujiang New December

households 26500000.00 2406.89 Urban 2016

Community and

61

Harmonious

City

Community

Da Zhailu12 10

households

6. Payment of compensation fee Based on compensation policies and standards set out in the RP, Xi’an Project Management Office (PMO) and the project implementation agency shall directly pay the various compensation funds to affected people, enterprises and public institutions during the implementation of the project. Funds flow is shown in Figure 2 and the specific amount paid is shown in Table 12. By the end of Jan 2019, the payment of compensation fees for relocation and resettlement is as follows: Keji 2nd Road: CNY 1,200,000 and CNY 14,688 have been paid to two temporary buildings on the road respectively; RMB 6,969,955 Yuan has been paid to Fenghui Apartment; monetary compensation of RMB 9,900,300 Yuan has been paid to Xi’an Bodi School; CNY 123,500,000 has been paid to Shaanxi Sirui Industry Co., Ltd. Total payment reaches CNY 141,584,943. The 29 affected families in Xiaoyanzhuang Village were paid 15,121,265 CNY as resettlement compensation, and the total compensation for this sub-project was 156,706,208 CNY. Dazhai Road: Compensations have been made for nursery stocks of Minqizhai Village and Erfuzhuang Village as well as 29 homesteads in Erfuzhuang Village, totaling CNY 31,542,231 for 128 households. In 2016, transitional fees and living allowance of CNY 857,040 have been paid to 9 households; CNY 12,917,607 has been paid to 10 enterprises affected by Dazhai Road Project. The involved building within the boundary lines of roads and the four enterprises in Heping Industrial Park have been paid

12 Because Er Fu Zhuang Dazhai Road Urban Reformation Plan has not been approved and the urban reformation has not started yet, information about the resettlement of 10 affected households in Dazhai Road is not updated.

62

compensation of CNY 23,875,500 and an advance payment of CNY 4.5 million is paid to Jianxin Door & Window Plant. Hongmiaopo Interchange: 106 households and one enterprise and public institution were involved, in which, 69 households accepted monetary resettlement and 38 households accepted physical resettlement, totally CNY 26.5 million was paid for demolition compensation. Xinghuo Road Interchange: 65 individual households and 11 enterprises and public institutions were involved, 1 enterprise accepted physical resettlement and 75 households accepted monetary resettlement, totally CNY 71.39 million was paid for demolition compensation. Bus Parking Lot of Aviation Base: The total payment for compensation is CNY 6.35 million Bus Parking Lot of XHTZ: The total cost of compensation is CNY 3.087663 million Fengcheng 8th Road – Taihua Road Interchange: the land acquisition and demolition of the interchange project involves southeast corner, northeast corner and northwest corner of the interchange, and the demolition work in above places has been completed basically. Up to July 2018, the signing of house demolition and compensation agreement and the compensation payment for the affected enterprise and public institution and individuals has been completed, total CNY 42.15 million of compensation for land acquisition and house demolition has been paid, in which, CNY 39.09 million is the compensation for house demolition and CNY 3.06 million is the compensation for land acquisition (45 mu)

63

ADB Xi’an Municipal

Project Office of Xi’an

Xi’an Urban Infrastructure

Enterprise (house Villagers Villager (house, Residential Property owner and other Committee (land tree and other house (compensation compensation compensation person property) (property fees for various fees) fee) owner) infrastructures) Figure 9 Fund flow diagram

Table 12 Compensation expense payment situation for land acquisition and house demolition

Compensation paid for

land acquisition and Category Type No. Project name house demolition (CNY

Ten thousand)

Road & bridge 1 Keji 2nd Road 15670.6208

improvement 2 Dazhai Road 4873.761 Road sub-project 3 Kunming Road 0

(Xi’an Zhuhong

Municipal Road-Fengcheng 4 0 Public Utility Interchange 4th Road

Bureau) Interchange

64

Compensation paid for

land acquisition and Category Type No. Project name house demolition (CNY

Ten thousand)

Zhuhong

5 Road-North 2nd 0

Ring Interchange

Hongmiaopo 6 2650.00 Interchange

Xinghuo Road 7 7139.00 Interchange

Fengcheng 8th

8 Road-Beichen 0

Avenue Interchange

Fengcheng 8th

9 Road-Taihua Road 4215.00

Interchange

Bus Parking Lot of

10 Xi’an North Railway 10248.1176

Comprehensive Station traffic facility Bus Parking Lot of subproject Xi’an National Civil 11 635.00 (Xi'an Bus parking Aerospace

Infrastructure lot Industrial Base

Construction Yuhuazhai

Investment Comprehensive

Group Co. Ltd.) 12 Transfer Station 308.7663

(some station in the

west part of Xi’an

65

Compensation paid for

land acquisition and Category Type No. Project name house demolition (CNY

Ten thousand)

City)

Comprehensive

Transfer Hub of

13 Xian Station of Xi'an 0 Metro International Trade transfer hub & Logistics Park

Yuhuazhai Bus 14 0 Parking Lot

Bus Parking Lot of

Xi’an International 15 0 Trade & Logistics

Park

Multistorey Parking

16 Garage of Xizhan 0

Urban Community

multistorey Ring Road-Taihua

parking 17 Road Multistorey 0

garage Parking Garage

Xianning

Road-Dongguannan 18 0 Street Multistorey

Parking Garage

Mujiangwang 19 0 Refueling Station

Refueling 20 Refueling Station of 0

66

Compensation paid for

land acquisition and Category Type No. Project name house demolition (CNY

Ten thousand)

station Bus Parking Lot of

Xi’an National Civil

Aerospace

Industrial Base

Refueling Station of

21 Xi’an North Railway 0

Station

Yuhuazhai 22 0 Refueling Station

Refueling Station of

Xi’an International 23 0 Trade & Logistics

Park

Bus Parking Lot of

24 Xi’an North Railway 0

Station

Total 45740.2657

VI. Public Participation Due to the adjustment of implementation plans of various subprojects, consultant experts have updated the RP at earlier stage, complemented the adjusted contents, and emphasized on the investigation and consultation for the impacts of land acquisition and demolition of the second batch of implemented subprojects. The table below refers to the for public participation and consultation carried out for surveying the impacts of land acquisition and demolition of subprojects in the updated stage of the RP.

67

1. By Jan 31, 2019, during project implementation period, major information disclosure activities conducted for relevant subprojects are shown in Table 13:

Table 13 Information disclosure

Project Time Channel Disclosed information

Website of April 2011 Draft of the RP ADB

Website of

Xi’an

March 2012 Municipal Project information

People’s

Government

General Xi’an Evening February 2012 Project information project Paper

Website of Final draft of the first batch of RPs September 2013 ADB of subprojects

Website of Updated RP for Fengcheng 8th December 2014 ADB Road-Taihua Road Interchange

Website of Updated RP for Dazhai Road December 2015 ADB project

Website of Updated RP for Keji 2nd Road May 2016 ADB project

Introduction to North 2nd Ring

Notice posting Interchange project, November 2012 – and information disclosure and relevant North 2nd February 2013, resourcing of introduction to land acquisition and Ring Road October 2013– materials and demolition of the project, December 2013 information RP and resettlement information

booklet

November 2012 - Notice posting Introduction to Hongmiaopo and

68

Hongmiaop February 2013, and Xinghuo Road Interchange project,

o October 2013 - resourcing of information disclosure and relevant

December 2013, materials and introduction to land acquisition and

information demolition of the project, and

notice of compensation plan for March 22, 2016 - Notice posting housing acquisition of Hongmiaopo June 22, 2016 Interchange project

Notice of land acquisition plan of December 23, 2015 Notice posting Hongmiaopo Interchange

Notice of Compensation Plan Xinghuo March 22, (consultative draft) for Housing Road Notice posting 2016~June 22, 2016 Acquisition of Xinghuo Road

Interchange Project

Introduction to Fengcheng 8th

Road-Taihua Road Interchange Notice posting project, Fengcheng and February - June information disclosure and relevant 8th resourcing of 2015 introduction to land acquisition and Road-Taihu materials and demolition of the project, a Road information RP and resettlement information

booklet

Information disclosure of land February - April Notice posting acquisition and demolition of 2015 project

Meeting Daizhai publicity, Information disclosure and relevant Road May 2011 – July resourcing of introduction to land acquisition and 2014 materials and demolition of the project

information

69

Notice posting

and

December 2015 resourcing of Report of project resettlement pan

materials and

information

Information disclosure of land January 2014 – Notice posting acquisition and demolition of June 2015 project

Working conference of land

Conference acquisition for villagers from 29 January 11, 2016 discussion households in Xiaoyanzhuang

Village

Keji 2nd Preliminary negotiation conference Conference Road October 2016 for compensation plan of land discussion acquisition

Negotiation conference of

compensation plan of land July 3, 2017~July Conference acquisition for villagers from 29 11, 2017 discussion households in Xiaoyanzhuang

Village

2. By Jan 31, 2019, during project implementation, major information disclosure and public participation activities conducted for relevant subprojects are shown in Table 14:

Table 14 Public participation of relocation and resettlement

Project Time Place Participant Content/ activity

North Dormitory Leaders and Surveys on the November 2012 – 2nd Ring area of resident affected physical June 2014 Road Sinohydro representatives of quantity of the

70

Corporation Urban project and

Engineering Reconstruction resettlement

Bureau 15 Office of Economic intention, and

Co., Ltd. Development Zone consultation of RP

and Sinohydro

Corporation

Engineering Bureau

15 Co., Ltd.

Consultations of November 2012 – Leaders of compensation and June 2015 Daming Palace Preservation and RP Renovation Office, Survey on the Fangxin Lianhu District People’s affected physical Community Government and quantity of the April – May, 2015 Fangxin Food Plant, as well as resident project and representatives of resettlement Fangxi Community intention

Xi’an Urban and Demonstration:

Rural Construction compensation plan

Commission, Xi’an for housing Hongmi Daming Municipal acquisition of aopo Palace Development and Hongmiaopo

Preservation Reform Interchange December17, 2015 and Commission, Xi’an project formulated

Renovation City Planning by Xi’an Qujiang

Office Bureau, Xi’an Daming Palace

Housing Security Heritage Site

and Management Preservation and

Bureau, Xi’an Renovation Office

71

Legislative Office,

Xi’an Lianhu District

Construction

Bureau,

Hongmiaopo

Subdistrict Office,

Construction Bureau

of Daming Palace

Preservation and

Renovation Office,

Urban (Shanty)

Reconstruction

Office of Daming

Palace,

representatives of

households involved

in land acquisition,

etc.

Xi’an Municipal

People’s

Government, Xi ’an Notice on Daming Qujiang New District determining Palace Administrative housing Preservation Committee, Xi’an acquisition of March 22, 2016 and Qujiang Daming Hongmiaopo Renovation Palace Heritage Site Interchange Office Preservation and project

Renovation Office,

representatives of

72

households involved

in land acquisition,

etc.

Notice on

compensation plan Xi’an Qujiang of housing Daming Palace Daming acquisition for Heritage Site Palace Hongmiaopo March 22, Preservation and Preservation Interchange 2016~June 22, Renovation Office, and project, 2016 representatives of Renovation home-entry households involved Office publicity, removal in land acquisition, and relocation, etc. and house

estimation

Daming Palace

Preservation and Discussion and Renovation Office, July 2016~October signature of PMO affected enterprises 2016 compensation and institutions, agreement residents from 104

households

Daxing New District,

Daming Palace

Preservation and Consultations of November 2012 – Fenghe Renovation Office, compensation and Xinghu June 2015 Village Lianhu District RP o Road People’s

Government,

73

Fenghe Village

Daming Palace Survey on the Preservation and affected physical Renovation Office, South of quantity of the Lianhu District April – May 2015 West Ziqiang project and People’s Road resettlement Government and 4 intention, and affected enterprises consultation of RP and institutions

Notice on

Compensation

Plan (Consultative Daming Palace Draft) for Housing Preservation and Acquisition of March 22, Renovation Office, South of Hongmiaopo 2016~June 22, Lianhu District West Ziqiang Interchange 2016 People’s Road Project, Government and 4 home-entry affected enterprises publicity, removal and institutions and relocation,

and house

estimation

Xi’an Qujiang

Daming Palace Discussion and Heritage Site July 2016~October signature of PMO Preservation and 2016 compensation Renovation Office, agreement affected enterprises

and institutions,

74

merchants, and

residents

Survey on social

economy and March – April 2014 resettlement

intention

Survey on the

affected physical

quantity of the Weiyang District Fengch April – May 2014 Construction project, and

eng 8th Bureau, Tanjia consultation of Tanjia Subdistrict Office, Road-T affected enterprises compensation and Subdistrict aihua and commercial resettlement policy Office tenants Road Verification of February – June affected physical 2015 quantity

Discussion and

June – December signature of

2016 compensation

agreement

Xi’an Urban Road Verification of Network affected physical Improvement Project Office, Yanta quantity and May – June, 2017 District People’s survey on Government, Lianhu District Urban resettlement Yuhua Reconstruction condition Industrial Office, affected Daizhai July 14 - July 16, people (including Survey on affected Park representatives, Road 2014 physical quantity women July 17, 2014 representatives and Survey on social

75

affected economy and representatives of Erfuzhuang Village, resettlement Minqizhai Village, intention Heping Industrial Park, enterprises Consultation of July 17, 2014 – compensation and and communities), resettlement policy October 19, 2014 Resettlement Group and resettlement and design unit plan Publication of

Affected people, compensation November 2015 enterprises and public institutions standard, means of appeal, etc.

Lianhu District Consultation of Urban Heping compensation and January Reconstruction Industrial Office, affected resettlement policy 2016~June 2016 people (enterprises Park and resettlement and public institutions) plan Lianhu District Urban Discussion and July Reconstruction signature of 2016~December Office, affected people (enterprises compensation 2016 and public agreement institutions) Administrative

Committee of Xi’an Survey on affected

Hi-tech Industries physical quantity January 2014 – Development Zone, and consultation of June 2015 Xi’an Hi-tech affected villages, compensation and Industries enterprises and resettlement policy Developmen public institutions Keji 2nd t Zone Publication of Road Affected people, November 2015 enterprises and compensation public institutions standard, means

76

of appeal, etc.

Communicate and

Xi’an Urban Road determine the Network work plan for joint Xi’an Hi-tech Improvement Project Office, XHTZ area between June 2016~August Industries Yuhuazhai sections along the 2016 Developmen Urban-village Comprehensive road, and t Zone Reconstruction communicate for Office, Yuhuazhai Villagers Committee matters for road

land transfer

Xi’an Bodi School,

road construction XHTZ Yuhuazhai unit, and pipe rack Urban-village builder convoke Xi’an Hi-tech Comprehensive September several Industries Reconstruction 2016~October construction Developmen Office, affected 2016 docking t Zone people, enterprises, conferences and public institutions, coordination construction unit conference for

road land transfer

XHTZ Yuhuazhai

Urban-village Preliminary Xi’an Hi-tech Comprehensive consultation for Industries Reconstruction November 2016 compensation plan Developmen Office, Yuhuazhai of land acquisition t Zone Subdistrict Office, and demolition Xiaoyanzhuang

Villagers Committee

77

XHTZ Yuhuazhai Problems on Urban-village Xi’an Hi-tech pipeline, footbridge November 19, Comprehensive Industries and etc. found in 2016; November Reconstruction Developmen Xi’an International 23, 2016; Office, enterprises, t Zone University during public institutions, road construction construction unit

XHTZ Yuhuazhai

Urban-village

Comprehensive Discussion and Reconstruction consultation of July 3, 2017-July Office, Yuhuazhai Gaoke Hotel compensation plan 11, 2017 Subdistrict Office, for land acquisition representatives from and demolition 29 households in

Xiaoyanzhuang

Village

Yuhuazhai .Location of Subdistrict, Urban Resettlement Meeting Reconstruction Building, Room of Office of Yuhua Discussion and 2018.2.11 Guanzhong Area, Village negotiation of February 11, 2018 Custom Committee and compensation Park, Villager’s scheme for land Fufeng, Representatives of acquisition and Xiaoyanzhuang house demolition Village

VII. Conclusions and Suggestions 1. Conclusion

78

(1) Land acquisition work of the subproject in this monitoring was carried out in an orderly manner, and was in strict accordance with the unified compensation standards for land acquisition and demolition, which ensures that the legal rights and interests of the masses were not infringed. Regulating demolition behavior, reducing demolition disputes, maintaining harmony and stability can ensure the openness and transparency of demolition, thus realizing the legal demolition, transparent demolition and harmonious demolition. Up to 31 Jan, 2019, land acquisition involved in the subprojects of this monitoring has been completed basically, housing demolition work involved has been basically completed, and various construction works are being proceeded orderly. (2) Relevant responsible institutions of various subprojects are complete with clear assignment of responsibility and also boast prefect system and high-quality personnel; meanwhile, the leader groups have been established for various subprojects with detailed working division and responsibility definition. During the implementation period, different public participation activities have been convoked for various subprojects in accordance with actual demands, and wide discussion on compensation standard and policy as well as resettlement methods has been carried out with relocated people, and their suggestions were also collected. Among them, for the subprojects, we formulated the acquisition compensation scheme and preferential measures that comply with the willingness of most relocated households according to the actual situation during the acquisition process, which ensures the smooth proceeding of the acquisition work. (3) The principle of public participation has been fully implemented and the interests of vulnerable groups and women are guaranteed. (4) During implementation process of each subproject in the monitoring, no complaints have been received, and no petition arising from land acquisition and demolition occurred. It shows that the masses are satisfied with land acquisition and demolition work of the project. 2. Suggestions The monitoring and consultation obtained the great support of Xi’an Urban and Rural Construction Commission, Xi’an Urban Infrastructure Construction Investment Group Co., Ltd. and various responsible departments in

79

administrative districts of subprojects, which ensured the smooth implementation of projects. Apart from expressing our appreciation to relevant institutions, following suggestions are proposed for future land acquisition and demolition: (1) Accelerate the efficiency in handling land acquisition procedure and land use certificate. According to relevant national policies, land acquisition must be conducted strictly conforming to the process. Therefore, efficiency of handling land acquisition procedure is suggested to be accelerated to legalize the land use, so as to provide legal protection for the smooth completion of land acquisition and demolition and following implementation of engineering construction. (2) Timely and sufficient payment of compensation for affected people is undoubtedly the key point and basic work for land acquisition and demolition. However, the implementation of other supporting policies should not be ignored. For example, some resettlement households actively coordinate with project construction and move to new houses timely, but backward construction of roads, water, electricity and other supporting facilities bring about difficulties to the household. The project office is suggested to investigate these possible situations and coordinate with relevant departments for implementing compensation policy as soon as possible. (3) It is suggested the project implementation unit should avoid significant changes during design and construction period, and maintain the consistency and stability of the project, so as to avoid repeated works. (4) Avoid data advancement during data summarization. Conclusion, analysis and evaluation of working progress should be made objectively in accordance with actual impacts, so as to avoid passiveness. (5) Enhance the filing for resettlement people. Pay attention to preservation of relevant materials in the resettlement process and establish archives for land acquisition and demolition. Special personnel should be designated for archive management, so as to provide basic materials for completion acceptance and monitoring evaluation. (6) Continuously strengthen the supports for vulnerable groups and resettlement people and further improve and strictly implement recovery programs.

80

(7) Continuously improve public participation in project implementation period, and ensure the transparent and convenient ways for appeal and complaint.

81