To: Ashford Joint Transportation Board

By: KCC Highways and Transportation

Date: 11th September 2018

Subject: Highway Works Programme 2018/19

Classification: Information Only

Summary: This report updates Members on the identified schemes approved for construction in 2018/19

1. Introduction

This report provides an update and summarises schemes that have been programmed for delivery in 2018/19

Footway and Carriageway Improvement Schemes– see Appendix A

Drainage Repairs & Improvements – see Appendix B

Street Lighting – see Appendix C

Transportation and Safety Schemes – See Appendix D

 Integrated Transport Schemes – see Appendix D1   Casualty Reduction Measures – see Appendix D2    S106 Developer Funded – see Appendix D3

Developer Funded Works – see Appendix E

PROW – Appendix F

Bridge Works – Appendix G

Traffic Systems – see Appendix H

Combined Member Fund – see Appendix I

Conclusion 1. This report is for Members information.

1 Contact Officers:

The following contact officers can be contacted on 03000 418181

Toby Howe Highway Manager (East) Lisa Willoughby Ashford District Manager Alan Casson Road and Footway Asset Manager Katie Moreton Drainage & Structures Manager Sue Kinsella Street Lighting Manager Toby Butler Intelligent Transport Systems Manager Andrew Hutchinson PROW Jamie Hare Developer Funded Work Nikola Floodgate Transportation and Safety Schemes

Appendix A – Footway and Carriageway Improvement Schemes

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.

Surface Treatments - Contact Officer Clive Lambourne

Micro Surfacing

Road Name Parish Extent of Works Current Status

Wicken Lane A20 to Westwell Lane Completed

From The Gate Lodge Swain Road Completed Ingleden to Swain Farm From Road for 250 Amage Road Completed metres From Rye Road for 117 Stocks Road Completed metres west bound

Green Lane Charing Whole Lane Completed

New House Lane Egerton/Charing Whole Length Completed

From junction with Water Lane The Street Completed to Zion Baptist Church Postponed – To be programmed for Nairne Close Whole Length September or October From Staple Road to Crown Wye Road Wye with Hinxhill Completed Lodge

Chessenden Lane Smarden Whole Length Completed

Just after William Judge Close Appledore Road Tenterden Completed to Tassels Entrance Pot Kiln Lane to Bull Lane Road Bethersden Completed through wooded section Crescent connecting to A20 Westwell Lane Westwell Completed end to end

Shawlands Lane From Hookstead to Cripple Hill Completed

From Bower Road to Surface Church Road Completed Change by Steel Gates From Smarden Road to The Street Completed School

Glebeland Egerton/Charing Whole Length Completed Thornden Wood Chestfield Whole Length Completed Road

Surface Treatments - Contact Officer Clive Lambourne

Surface Dressing

Road Name Parish Extent of Works Current Status

Matalan Roundabout to Great

Great Chart Road Ashford Chart Roundabout then to Completed Tar Pot Lane south for 600 Newchurch Road Completed metres Iden Lane to Stonebridge Egerton Road Egerton/Charing Completed Green Road

Newchurch Road Bilsington B2067 to Tar Pot Lane Completed

30 mph to Hopes Grove Smallhythe Road Tenterden Completed Nurseries Appledore Rd to Knockwood Woodchurch Road Tenterden Completed Road

Mulberry Hill A28 to Cobbs Hill Completed

Evegate Mill Lane Calleywell Lane to Stream Completed

From double S Bend (End of Peening Quarter Wittersham Micro) to right hand bend after Completed Road village

Canterbury Road Brabourne Plain Rd to start of 30 mph Completed

Leacon Lane to Old Water Pluckley Road Charing Treatment Works at Lady Completed Dane

Machine Resurfacing – Contact Officer Byron Lovell

Road Name Parish Extent of Works Current Status

Retexturing Bell Lane Smarden 100m both sides of Completed carriageway around bends Retexturing

From roundabout at bottom of Charing Hill Charing Charing Hill junction with A20 Completed to bend at Rd Retexturing A251 Faversham Rd around bends between Pested Completed Lane junctions A2042 Romney Retexturing Marsh Road Ashford Completed Circulatory of roundabout Roundabout Wye Road Cow Lees to "Robertsdane" Completed

Godinton Road to Regents East Street Ashford Completed Place

Green Lane to approximately Programmed 11th A28 Ashford Road Bethersden 80m past Gascoigne Road September 2018 North Approx 200m around sharp Programmed 13th Street/Tenterden bends between Redhill Bridge September 2018 Road and property 'The Pines' B2080 Tenterden From Red Hill Bridge to 200m To be programmed Appledore Road East February 2019 Between properties 'The To be programmed Road Bilsington Beehive' and 'Herne House/ February 2019 Hern Hill farm' A28 Canterbury The Old Mill public House to To be programmed Kennington Road Willington Farm February 2019

Between Plummer Lane and To be programmed A28 Road Tenterden Cranbrook Road February 2019 A28 Canterbury Road, A252 Canterbury To be programmed Chilham Chilham (A252 jnt at Bagham Road February 2019 X-roads) A2042 Wellesley Between High Street and St To be programmed Ashford Road Johns Lane February 2019 B2229 Brookfield Area of traffic lights at junction To be programmed Roadd / Leacon Ashford with Leacon Road February 2019 Road

Footway Improvement - Contact Officer Neil Tree

Extent and Description of Road Name Parish Current Status Works

From the roundabout at the A20 to the junction with Charing Hill Charing Completed Pilgrims Way. (Footway Protection)

Between Faversham Road Programmed to start Church Road Kennington and The Street. week commencing 3rd (Footway Protection) September 2018.

Appendix B – Drainage Repairs & Improvements

Drainage Repairs & Improvements - Contact Officer Katie Moreton

Road Name Parish Description of Works Current Status

Church Yard Ashford Replacement of Aco channels Works Complete

Bank Street Ashford Replacement of Aco channels Works Complete

High Street Ashford Replacement of Aco channels Works Complete

Works programmed for Highbury Lane Tenterden Replacement of channels September 2018

Works programmed for Hastings Road Rolvenden Installation of new drainage system September 2018

Appendix C – Street Lighting

Structural testing of KCC owned street lights has identified the following as requiring replacement. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.

Street Lighting Column Replacement – Contact Officer Sue Kinsella

Road Name Parish Description of Works Status Works programmed for completion by Queen Street Victoria Replacement of 7 no street light end October 2018 Works programmed for completion by Canterbury Road Kennington Replacement of 1 no street light end October 2018 Works programmed for completion by Belmore Park Stour Replacement of 2 no street light end October 2018 Works programmed for completion by Cowdrey Close Highfield Replacement of 1 no street light end October 2018 Works programmed for completion by Drake Road Highfield Replacement of 1 no street light end October 2018 Works programmed for completion by East Hill Victoria Replacement of 1 no street light end October 2018 Works programmed for completion by Knoll Lane Beaver Replacement of 1 no street light end October 2018 Juniper Clos Works programmed for completion by Replacement of 1 no street light end October 2018

Works programmed for completion by Kennington Road North Replacement of 1 no street light end October 2018 Works programmed for completion by Trinity Road Replacement of 1 no street light end October 2018 Works programmed for completion by Loudon Path Godinton Replacement of 1 no street light end October 2018 Works programmed for completion by Great Chart Replacement of 1 no street light Bypass end October 2018 Works programmed for completion by Edinburgh Road Victoria Replacement of 1 no street light end October 2018 Works programmed for completion by Hollington Place Victoria Replacement of 1 no street light end October 2018 Works programmed for completion by Foley Close Highfield Replacement of 2 no street light end October 2018 Works programmed for completion by Foster Road Highfield Replacement of 2 no street light end October 2018 Works programmed for completion by Kingfisher Close Highfield Replacement of 1 no street light end October 2018 Works programmed for completion by Lacton Way Highfield Replacement of 1 no street light end October 2018 Works programmed for completion by Luckhurst Road Highfield Replacement of 1 no street light end October 2018 Works programmed for completion by Nightingale Close Highfield Replacement of 1 no street light end October 2018 Works programmed for completion by Shepherd Drive Highfield Replacement of 1 no street light end October 2018 Works programmed for completion by Woolmer Drive Highfield Replacement of 1 no street light end October 2018 Works programmed for completion by Canterbury Road Kennington Replacement of 1 no street light end October 2018 Works programmed for completion by Faversham Road Kennington Replacement of 1 no street light end October 2018 Works programmed for completion by Road Norman Replacement of 1 no street light end October 2018 Works programmed for completion by Kennington Road North Willesborough Replacement of 1 no street light end October 2018 Works programmed for completion by Longbridge Park Farm north Replacement of 1 no street light end October 2018 Works programmed for completion by Middle Street Victoria Replacement of 1 no street light end October 2018 Works programmed for completion by Somerset Road Victoria Replacement of 1 no street light end October 2018 Works programmed for completion by Grampion Close Stour Replacement of 1 no street light end October 2018 Works programmed for completion by Heathfield Road Stour Replacement of 1 no street light end October 2018 Works programmed for completion by Victoria Replacement of 1 no street light Wellesley Road end October 2018

Appendix D – Transportation and Safety schemes

The Schemes Planning & Delivery Team are implementing a number of schemes within the Ashford District, in order to meet County Council’s strategic targets (for example, addressing traffic congestion, or improving road safety). Contact Officer – Darren Hickman

D1 - INTEGRATED TRANSPORT SCHEMES Local Transport Plan funded non-casualty reduction schemes

Road Name Parish Description of Works Current Status

Ashford International Handed over to contractor for Ashford Pedestrian / cycle ramp Station delivery

Permanent closure of Highfield Lane from the HS1 bridge to Kingsford Highfield Lane, Mersham Mersham Complete Street, with turning head to be built at the Kingsford Street junction. Public consultation responses High Street, Biddenden Biddenden Junction reconfiguration being analysed

D2 - CASUALTY REDUCTION MEASURES Identified to address a known history of personal injury crashes

Road Name Parish Description of Works Current Status Signing works complete. Lining Drovers Roundabout, Improvements to existing works postponed due to weather. Ashford Ashford signing and lining Now due to be carried out in August 2018

Station Road junction Installation of segregated Handed over to contractor for Ashford with Tannery Lane cycle route delivery

Installation of a ‘virtual table top’. Works to include red high friction across the Bethersden Road crossroads with granite junction with Tenterden Biddenden Complete setts laid across the Road carriageway in an aim to better highlight the crossroads to drivers. , Proposed signing and Handed over to contractor for Road Shadoxhurst and lining delivery Ruckinge Upgrade of existing Kingsnorth Turbo roundabout at junction of Design complete, safety audit has Kingsnorth Roundabout A2042 / Bad Münstereifel been ordered Road / Malcom Sargent

D3 - S106 Developer Funded

Road Name Parish Description of Works Current Status Upgrade of traffic signal junctions at Elwick Elwick Road traffic Road/Station Road Ashford Works complete signals junction and also Victoria Way/Station Road junction. Upgrading of bridge to enable buses to cross Bridgefield bus route Kingsnorth Works complete and serve the east side of the development

Appendix E – Developer Funded Works

Developer Funded Works (Section 278 Agreement Works) – Contact Officer Jamie Hare

Scheme Name Mastergov File Parish Description of Current Status Ref No Works

New controlled Newtown Road - pedestrian crossing Remedial works due to be AS0419 Newtown, Ashford Former railway site and construction of completed shortly site entrance

A28 Chart Road, Rearrange junction Works Complete and in Brunswick Road AS2081 Godinton alignment maintenance period Junction

New footway and relocation of Street lighting remedial works Farrow Court AS003012 Stanhope pedestrian crossing outstanding. facilities

New Development Works Complete and in Ashford Road AS003049 Chilham Access and maintenance period Pedestrian Crossing

New Access to Works completed and in Cudworth Road AS003024 Willesborough development maintenance

New Access to Works Complete and in Ashdown Court AS003038 Ashford development and maintenance footway works Access to be updated Warren Site A, AS003002 Ashford for new housing Works completed Ashford Road development

Works completed and in Old Abattoir Site AS003011 Aldington New Access maintenance period

Change of road Wesley School alignment to Works completed and in AS003028 Singleton Road introduce on street maintenance period parking

Cheesemans New principal road to Works complete and in AS0418 Green PAR developments maintenance period

New Housing Kings Avenue AS003006 Ashford Adopted Development

New Proposed Tenterden Site 1 AS003036 Tenterden Housing Works commenced Development

New Proposed Works complete and in Chilmington Green AS003054 Great Chart Housing maintenance period Development

New vehicle cross Works complete and in Hopewell School, AS003033 Ashford overs and street maintenance period due to be St Stephens Walk lighting works adopted

Wilesborough New cycleway/ Works completed and in Dykes, Sheepfold AS003046 Kingsnorth footway tying in to maintenance Lane existing network

Amendments to the Technical approval granted Dover Place AS003051 Ashford junction and works to waiting on start date (may not the footway required progress due to funding)

Calleywell Lane New Access for Works complete and in AS003039 Aldington (Taylor Wimpey) development maintenance period

Proposed New Carlton Road, Works completed and in AS003099 Ashford Vehicular Access for maintenance period. Ashford Network Rail

Chilmington New mini roundabout Works Complete and in Access D – Coulter AS003097 Ashford and amendments to maintenance period Road the existing highway. Blackwall Road Proposed widening of Works completed in AS003080 Willesborough South carriageway maintenance period

Works complete and in Essella Road AS003067 Willesborough New Junction maintenance period

Faversham Road AS003140 Challock New Junction Works commenced

Henwood AS003090 Ashford New junction Works completed

Aldi Site Works completed, remedial AS003161 Ashford New junction Victoria Road works required

Curious Brewery Works have commenced on Site AS003164 Ashford New junction site Victoria Road

Station Road AS003160 Pluckley Road widening In technical audit stage

New junction and Austin Road AS003157 Ashford In technical audit stage vehicle cross overs

Charter House AS003151 Ashford New footway In technical audit stage

Re-surfacing enter Watery Lane AS003150 Works complete road to Tar Mac plant

Works complete in Boxley AS003145 Ashford New Vehicle Access maintenance period

New Traffic Signals Newtown Road AS003143 Ashford (Designer Outlet Works ongoing Scheme)

B2042 Designer New Slip Road to AS003092 Ashford Works ongoing Outlet proposed car park Amendments to the Kimberley Way AS003093 Ashford existing roundabout Works ongoing Roundabout to increase capacity

Appendix F – Public Rights of Way

Public Rights of Way – Contact Officer – David Fleck Path No Parish Description of Works Current Status AB31 – Urban Tenterden Repairs to surface Job pulled, other agency Footpath between (Developer) High Street and Bells Lane AW339 Byway Shadoxhurst Repairs to surface Due to the extent of 4x4 damage the work has been postponed (unknown date) AT254 Byway High Halden Repairs to surface 4x4 damage Out to tender (Due 13/08/2018) AW51 Westwell Repairs to surface (Drainage issues) Out to tender NDW Byway (Due 13/08/2018)

Appendix G – Bridge Works

Bridge Works – Contact Officer Katie Moreton

Road Name Parish Description of Works Current Status

No planned works

Appendix H – Traffic Systems

There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; local residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.

Traffic Systems - Contact Officer: Toby Butler

Location Description of Works Current Status

No traffic signal refurbishment work being carried

out this year

Appendix I – Combined Member Fund

Combined Member Fund programme update for the Ashford District. The following schemes are those which have been approved for funding by both the relevant Member and by Simon Jones, Director of Highways, Transportation and Waste. The list only includes schemes, which are  in design  at consultation stage  Handed over for delivery  Recently completed on site.

The list is up to date as of 6th August 2018.

The details given below are for highway projects only. This report does not detail

 Contributions Members have made to other groups such as parish councils  Highway studies  Traffic/ non-motorised user surveys funded by Members.

More information on the schemes listed below can be found via Kent Gateway, the online database for all Combined Member Grant schemes and studies, or by contacting the Traffic and Safety Engineer for the Combined Member Grant Ashford District.

Mike Angell Details of Scheme Status

1718-CMG-AS-438 Shadoxhurst village Handed over to contractor for delivery Proposed speed reduction from 40mph to 30mph

Clair Bell Details of Scheme Status

1718-CMG-AS-437 Harville Road, Wye Proposed speed reduction from 60mph to 40mph Handed over to contractor for delivery

Charlie Simkins Details of Scheme Status 1718-CMG-AS-436 Swan Lane, Works complete with snagging to be Lining and realignment of Swan Lane junction with The Street carried out

Mike Hill Details of Scheme Status

18/19-CMG-AS-556 Maytham Road, Rolvenden Handed over to contractor for delivery Proposed advanced warning signs

18/19-CMG-AS-555 Hastings Road, Rolvenden Handed over to contractor for delivery Proposed scheme 20mph zone

George Koowaree Details of Scheme Status

18/19-CMG-AS-577 Tennyson Road, Ashford Handed over to contractor for delivery Pedestrian dropped kerbs

1.1 Legal Implications

1.1.1 Not applicable

1.2 Financial and Value for Money Considerations

1.2.1 Not applicable

1.3 Risk Assessment

1.3.1 Not applicable

Contact: Lisa Willoughby / Toby Howe 03000 418181