NEW CITY DESIGNED FOR LIVING YEARS YEARS New Moscow CITY DESIGNED FOR LIVING

2017 / INTRODUCTION NEW MOSCOW — CITY DESIGNED FOR LIVING

Probably the most ambitious project in .

It is the first time in the modern history of Russia when borders of two largest territorial entities of Russian Federation are changing so profoundly.

Throughout its history, Russian capital hasn’t seen a project of its expansion more ambitious than New Moscow.

The goverment puts the main accent on polycentrism, on creat- ing alternative centers for business, leisure and residence in order to leave present monocentricity and circularity, because of which millions of people from Moscow and its suburbs rush to the one and only historical city center every day.

We want to implement world’s best experience and urbanistic solutions for the development of new territories, so that Moscow citizens could be proud of their city and the life there could be really comfortable. Sergey Sobyanin Mayor of Moscow

2 3 / CONTENTS NEW MOSCOW — CITY DESIGNED FOR LIVING New

Moscow GOALS OF THEGOALS PROJECT CIRCULAR MIGRATION OF CITIZENS IMPLEMENTATION PROJECT MOSCOW» «NEW THE FOR RESOURCES INTERNATIONAL URBAN PLANNING CONTEST URBAN INTERNATIONAL RESULTING OF PROGRESS EXPECTATIONS OF MOSCOW THE EXPANSION FROM OF THE STRATEGIES DEVELOPMENT TERRITORIES MOSCOW NEW INDEX OF THE ESTIMATED DEVELOPMENT TERRITORY MOSCOW NEW THE PROCESS GOVERMENT OF MAYOR, ROLE DETERMINATIVE REALIZATION PROJECT IN OF MOSCOW AND STROYKOMPLEX THE DEVELOPMENT FOR DEPARTMENT MOSCOW TERRITORIES OF NEW NEW MOSCOW FORMATION PREREQUISITES PREREQUISITES FORMATION NEW MOSCOW

18 26 28 30 32 34 38 40 42 / CONTENTS NEW MOSCOW — CITY DESIGNED FOR LIVING Infra- structure

FIRE STATIONS SYSTEMS SURVEILLANCE VIDEO GLOBAL LOGISTIC HUB LOGISTIC GLOBAL SAFE CITY ORGANIZATION AND DEVELOPMENT OF POWER SUPPLY SYSTEM ORGANIZATION AND DEVELOPMENT OF NATURAL GAS SUPPLY SYSTEM ORGANIZATION AND DEVELOPMENT OF HEAT SUPPLY SYSTEM SYSTEM DISCHARGE AND SUPPLY WATER OF DEVELOPMENT AND ORGANIZATION WORKPLACES: DRIVING FORCE OF THE NEW MOSCOW DEVELOPMENT WORKPLACES OF STRUCTURE MOSCOW NEW OF PARKS SCIENCE CYCLING ROUTES CYCLING PARKING SPACE ROAD NETWORK DEVELOPMENT IN NEW MOSCOW STANDARDS AND APPROACHES FOR ROADS OF NEW MOSCOW SCHEME ORGANIZATION SUBWAY ROUTES TRAM FOR APPROACHES AND STANDARDS ROUTESBUS TRANSPORT BUS FOR APPROACHES AND STANDARDS ZONES NATURAL IN INFRASTRUCTURE SPORT MOSCOW NEW OF FACILITIES SPORT PUBLIC TRANSPORT INTERCHANGES TRANSPORTPUBLIC INTERCHANGES ENGINEERING DEVELOPMENT INFRASTRUCTURE RESOURCES RECREATIONAL SITES HERITAGE CULTURAL WORKPLACES WORKPLACES NEW 100000 ROAD CONSTRUCTION CONSTRUCTION ROAD IN NEW MOSCOW SUBWAY TRAM MOSCOW NEW IN MOSCOW NEW IN RAILWAYS BUS TRANSPORTATION SPORT FACILITIES AREAS MOSCOW OF NEW FUNCTIONAL OF NEW MOSCOW ESTATE PROPERTY COMMISSIONING AMOUNT AMOUNT PROPERTY COMMISSIONING ESTATE PLANNING DEVELOPMENT URBAN IN INVESTMENT IN NEW MOSCOW

48 62 66 70 76 82 86 88 98 102 104 110 116 118 120 122 / CONTENTS NEW MOSCOW — CITY DESIGNED FOR LIVING Polycentrism VIEW OF THE RESIDENTIAL AREA INTRODUCTION MOSCOW NEW IN MODEL FORMATION POLYCENTRIC INSIDE POLYCENTRES OF FUNCTIONAL CREATION THE METROPOLIS CITY THE POLYCENTRIC IN ROUTINE DAILY

136 138 140 142 / CONTENTS NEW MOSCOW — CITY DESIGNED FOR LIVING From urbanization centers URBAN PLANNINGURBAN CASE ACTIVITY RUBLEVO-ARKHANGELSKOE CENTERS: URBAN PLANNING ACTIVITY CENTERS: CASE URBAN PLANNING ACTIVITY CENTERS: TSKAD(EAST) CASE URBAN PLANNING ACTIVITY CENTERS: TSKAD(WEST) CASE URBAN PLANNING ACTIVITY CENTERS: SEREDNEVO CASE URBAN PLANNING CASE ACTIVITY CENTERS: SKOLKOVO PROJECT REALIZATION USING THE EXAMPLE OF ADMINISTRATIVE BUSINESS CENTER IN KOMMUNARKA IN CENTER BUSINESS ADMINISTRATIVE OF EXAMPLE THE USING REALIZATION PROJECT QUARTERS RESIDENTIAL INSIDE PLANNING ENVIRONMENT CITY BASIC PRINCIPLES OF URBAN DEVELOPMENT FORMATION STANDARDS ARCHITECTURAL RENOVATION AREA RESIDENTIAL INTRODUCTION MOSCOW OF NEW GROWTH POINTS to citizens KOMMUNARKA CASE PLANNING CENTERS: ACTIVITY URBAN 148 150 152 164 166 168 170 172 174 / CONTENTS NEW MOSCOW — CITY DESIGNED FOR LIVING Information SOCIAL OBJECTS SOCIAL COMPOUNDS RESIDENTIAL PROPERTY COMMERCIAL ROADS AND SUBWAY NEW MOSCOW — NEW HISTORY — NEW MOSCOW NEW OPINIONS PRIVATE THE LAST 5 YEARS OVER OBJECTS IMPLEMENTED PARTICIPANTS PROJECT CONTACT DETAILS INSTAGRAM: #НОВАЯМОСКВА INSTAGRAM: #НОВАЯМОСКВА

180 184 186 220 222 224 Evaluation of the environmental situation in the attached territories by Moscow residents based on the data of the Russian Public Opinion Research Centre

82.1% Positive feedback 5.7% Negative feedback

Nearly half of the territory of New Moscow is covered with green planting and is classified specially protected green area. It guarantees ecological friendly environment and excellence of recreational infrastructure to citizens of New Moscow.

14 15 PART 1 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

1.1 New Moscow Formation Prerequisites 1.1.1 Circular Migration of Citizens 1.1.2 Resources for the «New Moscow» Project Implementation 1.2 Goals of the «New Moscow» Project 1.3 International Urban Planning Contest 1.4 Expectations of Progress Resulting from the Expansion of Moscow 1.5 Development Strategies of the New Moscow Territories 1.6 Estimated index of the New Moscow territory development 1.7 The process 1.8 Determinative role of mayor, goverment and stroykomplex of Moscow in project realization 1.9 Department for the development of New Territories Moscow

16 17 PART 1.1 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

New Moscow formation prerequisites

2010 2017 Having officially expanded its administrative boundaries on July 1, 2012, Moscow significantly increased its rank in the rating of the largest world megacities

The project was officially presented This step prevented further uncon- city development. This model suggests in mass media on the 11th of July, trolled residential construction in balanced distribution of population 2011 and was entitled “New Moscow” areas not provided with proper infra- and employment so that connected on the analogy of the Indian capital structure. More than 50 million square territories are not becoming another modernization project — “New Delhi” meters of residential space will be commuter town, but a dynamically that had just celebrated its 100th an- built in new areas and approximately developing center. niversary. As a matter of curiosity, the a million of jobs for highly skilled pro- Population density before and extension of both capitals had been fessionals will be provided. It can surely be said that the foun- after borders expansion, person per km2 10 588 4 910 implemented in south-west direction. dation of the new historical stage of ppl sq km ppl sq km New administrative districts will get city-planning policy of the capital i.e. There were a few driviers of this prominent transport and territorial modernization of traditional mono- transformation. The city was devel- development and new infrastructure. centric structure of Moscow and oping, but was not able to expand creation of modern, well-thought and further. New conveniently located During the coordination stage of comfortable urban environment with territories were essential, in order to the development plan of new territo- developed infrastructure, full-featured prevent stagnation of the metropolis. ries, one of the ideas being discussed centers of business, culture and social was to transfer a part of authorities activities, has been laid. Adjacent territories up to the and capital functions to New Moscow. borders of Kaluga region had been Connected territories will see signifi- Residents of New Moscow and Historically, Moscow has always been increasing its territory via merging chosen for joining Moscow. These cant modernization in every direction. people from the capital itself will areas had low urbanization levels, Level of availability of social welfare be able to appreciate a new level of with adjacent settlements. good environment conditions and a objects in these places was extremely comfort, which will make their lives significant amount of green planting. low before. The situation will change and life of future generations more The first significant expansion up to the boundaries of Moscow Ring Transportation and city-planning for the better now. Transport network stable and really convenient. reformation could be made here as creation will increase accessibility Road was in 1960, when a number of surrounding villages and cottage soon as practicable. of new districts to the main part of the city. Subway, public transport communities were included into the city area. That is when, for example, Besides, any rapid-growing me- network, including high-speed trams tropolis faces high population density will connect territories that have been Kuntsevo, Tushino, and became a part of the metropolis. sooner or later. Moscow wasn’t an ex- badly or not at all connected with ception - population had grown at 1,5 each other. The boundaries of the capital underwent further changes in 1984. million people during the period from 2000 to 2010. This provoked a high in- The capital has been developing However, it was only in 2011 when the most profound transformation of ner circular migration of citizens, thus according to monocentric model until demanding reconsideration of traffic recently and has become a center of the administrative borders took place, which could be comparable to the flows destribution and bold changes. attraction with high concentration It should be noted that connection of workplaces. The unprecedented millennium-old history of Moscow territory expansion. of new territories has solved another project of Moscow extension allows urban issue of Moscow region. transferring to polycentric model of

18 19 PART 1.1.1 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

Circular migration

Regular surveys of the Russian Public of citizens Opinion Research Centre confirm that no less than 40% of Moscow residents are ready to move to the attached 40% territories for permanent living and working. With the progress of the «New Moscow» project, the percentage Since the beginning of the 20th century the population Further urban thickening of the city within the existing of such citizens continues to grow. of Moscow has increased in nearly ten times, and for the boundaries would inevitably lead to citizens’ life quality past few decades of the construction boom the city has reduction. Significant economic potential of Moscow region, become extremely dense. In addition, the majority of the giving cumulatively up to 30% of GDP of Russia, needed population has settled in commuter towns, remote from a more balanced urban planning that would provide a new workplaces. With the growth of welfare of Moscow citizens stimulus to the economy development, welfare growth, and city motorization, the daily load on transport infra- and level of citizens’ comfort. structure has become critical. The territories connected to Moscow will become a Being a powerful economical center, the city has also self-sufficient place for living with the infrastructure, a created circular migration flows of work force from adjacent lot of jobs and recreational areas. The authorities expect regions, though the biggest pressure was put by the over- that many people living in the south, south-west and west grown agglomeration of satellite cities, with the population areas of the capital will find jobs closer to home and daily comparable to big European cities. The said processes, circular migration from the suburbs to the city center and and urban planning initiatives, were often random rather back will be significantly reduced. than systematic and regular. MOSCOW REGION

MOSCOW REGION

As can be seen from the scheme, a land plot chosen for the extension of Moscow borders is the calmest and not loaded with transport and migration if compared with other areas. However, even in this case, it requires serious solutions in the reconstruction of old and construction of new connections to the city. Circular migtration flows

Large labor centers

KALUGA REGION Labor centers under creation

Current population density, persons/ha

200 to 412

100 to 200

50 to 100

5 to 50 Satellite cities 0 to 5

20 21 The newly-acquired territories are already connected to Moscow with almost every type of modern public transport, in addition to the highways: subway, commuter trains, and buses. Subsequently, high-speed tram launch is also planned.

How Moscow citizens get to New Moscow, according to the Russian Public Opinion Research Centre

6,6% By subway 8,9% By subway

14,7% By bus and shared taxis

67,7% By car

22 23 PART 1.1.2 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

THOUSAND Resources for the HECTARES «New Moscow» Project 40 280 340 Implementation 360 TOTAL AVAILABLE AREA 20 OF TROITSKY AND 250 280 Having no analogues in the modern history of Russia, the complex terri- NOVOMOSKOVSKY 280 360 ADMINISTRATIVE tory development program is based on the collaboration of investment DISTRICTS FOR URBAN initiatives of Moscow City Government and business community. After PLANNING NEEDS just a few years from the start of its realization, the city has received 280 415 30 the growth of the tax base and payments to the budget. 280 280 40 260 Implementing the urban planning program of the complex As a result, the attracted volume of investments from New Moscow development till 2035 the city makes an non-budgetary sources will be at least 5.8 trillion rubles. advance infrastructure development at city budget cost Residents of New Moscow will get urban environment- 50 and cost of the natural monopolies, totally amounting comfortable for living, working and recreation and modern 120 more than 1 trillion rubles. well-paid jobs, businesses will be able to implement the 415 breakthrough investment projects and to receive planned

Mechanisms included into the program ensure the profits. 80 60 growth of investment attractiveness of the New Moscow 420 territory. Residential, industrial, public and business, com- Efforts made by Moscow City Government create a munal and other commercial real estate is placed in the sustainably growing tax base for the city budget which by undeveloped area of over 40 thousand hectares, which 2020 will ensure coverage of current New Moscow costs 60 results in creation of new workplaces and formation of and its transformation into a driving force of economic new centers of urbanization within a single metropolis. and social development of the metropolis in the future. 100

80

207 100 80

Planned amount of investments into 60 real estate, bln RUB

3 65

2013 2020 2025 2030 2035 2040 Cost of land, mln RUB /ha

Budget spending on the New Moscow territory service 30

Budget revenue from new territories Accessibility by car during rush hours, min

24 25 PART 1.2 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

Development of modern Provision of the territory Creation of sufficient transport infrastructure with modern reliable amount of recreational objects of engineering objects and places of GOАinfrastructure cultural leisure

Preservation of the most Providision of hight-quality favorable environmental social infrastructure. Assurance conditions of optimal quantity of new work- places of the «New Moscow» project

Achievement of these goals will ensure balanced integrated development and environmental safety of the territory, which results in comfortable and LSfavorable environment for the citizens.

26 27 PART 1.3 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

International Urban Planning Contest

Contest on the creation of the concept of Moscow agglomeration Detailed information: development was held in 2012 initiated by the Working Group under http://stroi.mos.ru/o-konkurse the President of the Russian Federation, Governments of Moscow and Moscow Region, the Union of Architects of Russia, Russian Academy of Architecture and Construction Science.

Architectural bureau «Ostozhenka» Chernikhov architectural and design Urban Planning Group of the Russian Ricardo Bofill Group(Spain) Antoine Grumbach Et Associes (France) Urban Design Associates Group (USA) Creation of commuting hubs as potential devel- workshop Academy of Architecture and Construction Creation of three major clusters: polyfunction- Creation of the new quality of urban environment. Creation of a compact new city in Kommunarka Sciences opment and formation of polycentric structure. Creation of the single subject of the Russian Fed- al cluster in Novomoskovsky area, innovational Development of the environmentally-friendly using the radial transport system and chanelling. Search of ways and resources of the inner develop- eration. Creation of the agency/corporation on the Creation of the satellite city «ring» around Moscow. cluster in Troitsk and governmental cluster in transport. Development of the new centers of the ment of the capital. Active use of development of Moscow agglomeration. Displace- Kommunarka. urban planning activity. Active development of the the Moscow River potential. ment of the old low-productivity subway lines. industries from the central part of the city and development of the «clean» industries, creative industries and cultural entrepreneurship.

Contest results has revealed the winner in two nominations — «Development of Moscow Agglomeration» and «Development of «Big Moscow» on the basis of polycentric model — to be Antoine Grumbach et Associes, a French-Rus- L’AUC Group (France) OMA Group (The Netherlands) Studio Ass Secchi-Vigano Group (Italy) sian team; the best project of the formation of administrative and business Creation of the «linear» city in the area Distribution of the federal government bodies Urban development based on the sustainable of expansion. among several Moscow satellite cities. centralization, ecology and developed center on the attached territories was the idea of Urban Design Associates transport system. team from USA.

28 29 PART 1.4 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

Enhancement expectations The majority of residents of both new and «old» Mos- workplaces, provision of the citizens with the objects of cow mention the positive results of the city boundaries social, transport and engineering infrastructure. Notably, extension. Thanks to the single urban planning policy with recreational objects in the territory of New Moscow are in the result of the extension respect to spatial development the following tasks are initially designed to grant access to the city residents as being solved: problem of the mutual consideration of the well as to the outside visitors including foreigners. of Moscow interests of the city, developers and residents, creation of

Citizens of New Moscow ↓ Citizens of “old“ Moscow ↓

Transport operation 31% 51%

City improvement 37% 63%

New work places organization 57% 51%

Home building development 55% 62%

Problems with migrants 17% 22%

Ecology 26% 31%

According to VCIOM survey

30 31 PART 1.5 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

Principles of new territory The main task is to create comfortable urban environment and make New Moscow modern in terms of urban planning development in the city of technologies. To provide the advanced development of transport, Moscow engineering and social infrastructure. To make a partial shift of the business activity centers to the attached territories and relieve the historical city center.

Polycentrism, as a basis for creating Preserving environmental centers of urban development activity framework

Comfortable and eco-friendly Priority: low- and mid-rise residential environment for human living complex construction

Workplaces within a walking distance, Developed transport and engineering and as a result — reduction of circular migration infrastructure

32 33 PART 1.6 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

Estimated index of the Moscow City Government foresees a huge potential in the modernization of new ter- Data is provided in comparison between situation in 2012 and forecast for 2035 ritories. Special attention is put on the development of the following directions: social based on the statistics and various analytic sphere, creation of road and public transport network, construction of commercial social and economic models New Moscow territory and residential property, maintenance of existing natural framework and development of recreational potential. The territory of Troitsky and Novomoskovsky administrative development districts will undoubtedly take leadership practically within all major points in Russia.

232 1500 84,8 1000 0,4 0,7 1,2 11,9 611 2100 0,41 3,8

Population, Workplaces, Workplaces, Area of the consumer Street and road network length, The road network density, thousand people thousand per one citizen market objects, mln sq m km km/sq km

18 30 0,33 1,3 10 82 0 20+ 0 72 0,8 0,5

Accomodation provision, Workplaces, Places in kindergartens, Amount of subway stations Length of subway lines, km Roads load factor sq m per person per one employable person thousand

26 163 14 52,2 24 126 3 86 32 12000 12,5 300

Places in schools, Non-residential property, Real estate, Parklands Park area, ha Moscow City budget income from Troitsky thousand mln sq m mln sq m and Novomoskovsky administrative area, bln rubles

34 35 PART 1.6 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

Creating a comfortable space for human living involves the formation of intense social infrastructure. The «New Moscow» project uses a city beneficial approach to the social facilities construction by attracting not only the budget funds but also investors’ money.

Thus, by 2035 more than a half of the infrastructure will be built at the expense of extra-budgetary sources.

Estimated data till 2035

БОЛЕЕ

HEALTHCARE PARKS SCHOOLS SPORT FACILITIES KINDERGARTENS FACILITIES

36 37 PART 1.7 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

The process

The position of the city is to collaborate in the most transparent way with partners implementing various investment projects. Careful study and analysis of incoming questions and suggestions allows the mutual consideration of interests of the city and developers.

Using the skills from various disciplines, including urban planning, transport planning, project management, environmental psychology, and information design allows quick implementation of the projects conceived in New Moscow

Complies

Check for compliance Development of the Preparation of a land Expert Obtainment of the Putting into with Land Use and Development Construction plot development plan examination construction permit operation project concept Development Regulations

Investment project approved for Checking the project technical and implementation is transferred to economic indicators for compliance urban planning and construction with Moscow City Land Use and Complex of Moscow City for Development Regulation consideration of its compliance with Moscow City Land Use and Does not comply Development Regulation

Development of the territory planning project (TPP) or arrangement of alterations in the current TPP

Approval of the developed TPP (alterations in the TPP) with the executive authorities of Moscow City

Public hearing

Approval of the TPP Publication of the Moscow City regulatory act regarding approval of the TPP (alterations of the TPP) and amendments to Land Use and Development Regulations

38 39 PART 1.8 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

The main priorities of the Moscow Government are to de- provision of social, and transport services to residents of General Plan, construction of subway lines and motorways, velop the territories attached to Moscow, create favorable New Moscow, smooth functioning of life support systems approval of future facilities projects, and quality control conditions for living, working, studying, and recreation at a high level of the capital standards. of construction works, constructive engagement with of the population. Grand-scale plans and strategic deci- investors and local government agencies. sions concerning issues of the urban planning policy are Executive authorities of the capital, comprising a part developed and approved by the Mayor of the city Sergey of the Construction complex of Moscow, are the most Sobyanin, with active involvement of all its structures. active participants of the comprehensive transformation of new territories. The list of tasks daily performed by de- At the same time, everyday matters of stable function- partments, committees, and other structural subdivisions ing of systems of education, health, culture, and recrea- of the Construction complex of the capital in New Moscow tion, safety, mass sports, are being addressed, as well as includes the development of territorial schemes and the

40 41 PART 1.9 / NEW MOSCOW NEW MOSCOW — CITY DESIGNED FOR LIVING

Department for the Development of New Territories of Moscow

In order to implement the urban planning policy of the The Government of Moscow has given the Department Moscow Government on the attached territories, the Mayor for the Development of New Territories of Moscow City a of the city Sergey Sobyanin signed Resolution 239-PP key role to play in ensuring comprehensive and balanced on Formation of the Department for the Development of development of New Moscow, consolidated decision making, New Territories of Moscow City dated May 22, 2012. controlling conformity of urban planning documentation with the current standards, and providing transparency The Department was assigned the large-scale and long- of procedures and improvement of timing for issue of term objectives: construction and utility connection permits.

• Ensuring the coordination of the work of executive Functions and powers of the Department ensure the authorities of Moscow when preparing and implement- implementation of the unified urban planning policy for ing the program of the development of the attached spatial development of New Moscow taking into account territories; the interests of the city, developers, and residents of new territories. • Development and submission of drafts of legal acts related to planning, construction, social and economic Creation of new workplaces, provision of the population development of new territories for the consideration by with facilities of social, transport, and utility infrastructures. the Mayor of the city and the Government of Moscow; Our approaches, based on the open partnership with • On the grounds and pursuant to federal laws, making developers and partners, and responsibility of all parties, decisions on approval of technical specifications for succeeded in the increase of the investment appeal of the preparation and amendments of documents of new territories, their stable complex development. The Powers of the department: territorial planning, urban planning zoning, documenta- successful coordination of this work by the Department tion on area planning, as well as territorial and industry resulted in the implementation of major investment projects. schemes of New Moscow.

Ensuring the coordination of the Approval of technical specifications Awarding public orders for design- Acceptance of completed con- interaction of executive authorities for the preparation and/or amend- ing, constructing, and reconstruct- struction and reconstruction of the city of Moscow with gov- ments of documents of territorial ing of capital construction facilities facilities in the territory attached ernmental institutions in relation planning, urban planning zoning, financed from the budget funds of to Moscow financed from the to preparation of documents of documentation on area planning, the city of Moscow. budget funds of the city of Moscow territorial planning, urban planning territorial and industrial schemes in order to obtain the permits for zoning, and documentation on area of the territories attached to the putting the facilities into operation. planning, as well as designing of city of Moscow. capital construction facilities in the territory of New Moscow.

42 43 353,9 350

291,7

269,3

232

185,6 163,5

123,5 107 84,8

2012 2013 2014 2015 2016

Population, thousands of people Workplaces, thousand

Steady increase in the rate of housing construction in New Moscow is closely connected to the growth of non-residential property. The latter will ensure new workplaces and provide the residents with the opportunity to find job close to their new home.

44 45 PART 2 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

2.1 Road construction 2.5.2 Sport facilities of New Moscow 2.1.1 Road network development in New Moscow 2.6 Safe city 2.1.2 Standards and approaches for roads of New Moscow 2.6.1 Fire stations 2.1.3 Parking space 2.6.2 Video surveillance systems 2.1.4 Cycling routes 2.7 Functional areas of New Moscow 2.2 Public transport 2.8 Estate property commissioning amount in New Moscow 2.2.1 Subway in New Moscow 2.9 Investment in urban planning development of New Moscow 2.2.1.1 Subway organization scheme 2.10 Workplaces 2.2.2 Tram in New Moscow 2.10.1 Workplaces: driving force of the New Moscow development 2.2.2.1 Standards and approaches for tram routes 2.10.2 Structure of workplaces 2.2.3 Railways in New Moscow 2.10.3 Science Parks of New Moscow 2.2.4 Bus transportation 2.10.4 100000 new workplaces 2.2.4.1 Bus routes 2.2.4.2 Standards and approaches for bus transport 2.2.5 Public transport interchanges 2.2.6 Global logistic hub 2.2.7 Engineering infrastructure development 2.2.7.1 Organization and development of power supply system 2.2.7.2 Organization and development of natural gas supply system 2.2.7.3 Organization and development of heat supply system 2.2.7.4 Organization and development of water supply and discharge system 2.3 Recreational resources 2.4 Cultural heritage sites 2.5 Sport facilities 2.5.1 Sport infrastructure in natural zones

46 47 PART 2.1 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Road construction KILOMETERS

One of the main activities of the Government of Moscow is the construction of a transport framework which will connect all parts of the attached territories together and 2 100 to the city center, will provide the necessary mobility of the population and business with their exponential growth STREET AND ROAD NETWORK LENGTH in the coming decades.

KILOMETERS 700 KILOMETERS NEW PRIMARY ROADS 460 CONSTRUCTION

PRIMARY ROADS KM sq KM RENOVATION 3,8

DENSITY OF THE ROAD NETWORK

48 49

PART 2.1.1 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Vnukovskoe Road network development Mosrentgen Moskovsky in New Moscow Kokoshkino Moscow ring road Kievskoe highway

Sosenskoe Marushkinskoe Kaluzhskoye highway Until 2035, the overall street and road network length will comprise 2100 kilometers, including 1156.8 km Filimonovskoe of roads (including overpasses, flyovers, and interchanges). Multifunctional infrastructure of motorway will also be developed. Eight roads with the total length of 66,57 km are being engineered at the present time.

Bicycle lanes Roads of New Moscow have According to the targeted investment program bicycle lanes of the city of Moscow around 218,9 km of

Varshavskoe highway roads will be constructed and renovated to the Voskresenskoe year 2020. Pervomayskoe Scherbinka Desenovskoe In 5 years the following roads has been constructed and renovated Troitsk in New Moscow: Ryazanovskoe

• Central road in the village of Kommunarka with access to Butovo district (connects the territories of old and New Moscow); • Road from Kievskoe highway to Kaluzhskoe highway (the village of Salaryevo — the village of Mamyri); Krasnopakhorskoe • Road from Borovskoe highway to Kievskoe highway, from the Guardrails village of to Moskovsky City. Fast lanes of roads and mo- • Road from Borovskoe highway to Gorky st. torways of New Moscow are equipped with guardrails TSKAD • «Kaluzhskoe highway» road, Stage one. Novofedorovskoe Kievskoe Schapovskoe Vostochny dubler

Roads being constructed and renovated: Mikailovo- New interchanges Yartsevskoe At crossings of Moscow Ring Road and Kievskoe highway as well as Moscow • Road from Zheleznodorozhnaya st. to Moscow region Ring Road and Kaluzhskoe highway. Outdated clover junctions are supple- • railroad crossing, Kokoshkino village Voronovskoe mented by directional exits. • railroad crossing, Krekshino village • Road fromBorovskoe highway to Botakovo countryside • Flyover in Pervomaiskoe village Filling stations Fuel filling stations for • «М3-Ukraine-Yamontovo» road every motor vehicle Road landscaping • «Akademika Semenova st.» road prolongation alongside every road and Landscaped safety highway. • «-Butovo-Vidnoe» road islands and roadside areas • «Kaluzhskoe highway», Stage two Klenovskoe • Central Ring Road «TSKAD» Improved regional roads Meet the highest standards Moscow Ring Road interchanges of comfort and safety

Under design and construction: Highways of city-wide status Forecast till 2035 Rogovskoe

50 51 PART 2.1.2 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Standards and approaches Sections of standard motorway All new roads in New Moscow are being built with respect All exits are being equipped with acceleration lanes. In to modern comfort and security requirements. Trunk addition to this all new roads are being developed and built for roads of New Moscow roads and radial highways connecting the territory with with consideration of bike lanes and pavements, lighting “old” Moscow are being equipped with median barriers systems and modern public transport stops wit safe bays. and anti-noise screens on mandatory basis.

Flyovers and transport hubs Comfortable connection Acessibility between various roads Connection of living districts of New in New Moscow Outdoor lighting Moscow with main motorways Modern road lighting systems for safe travel in the dark

Roadbed Modern roadbed provides com- fortable and safe driving

Comfortable bus stops Convenient bus stops for the passengers of public transport

Anti-noise screens along the roads Minimizing the impact of the noise on living and public areas of the city

Landscaping Pedestrian area Bike lanes Landscaping of Roadbed Barrier median Roadbed Commuter transport Road and bus Bus stops with Pedestrian area Bike lanes Landscaping of of living area roads bays stops lighting safety islands living area

52 53 PART 2.1.2 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Standards and approaches Стандарты и подходы Highway Radial highways connecting the territory with «old» Moscow are for roads of New Moscow equipped with anti-noise screens, для веломаршрутов comfortable exits to motorways with acceleration lanes

Streets and inner-block roads laid within city blocks, equipped Freeways with parking lots, and bike lanes Four-, six-lane roads, connecting settlements and districts of the city. When going through housing estates freeways are equipped with anti-noise screens

Safe bike lanes Along the city, they duplicate all traffic directions that allows getting to any part of the city by bike

54 55 PART 2.1.3 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Parking space

City’s main tasks during parking lots planning and placing are the following: everyday usage comfort for the residents, traffic safety, esthetic image of the city preservation, additional Moscow city budget income. It is planned to significantly improve the technological base of parking spaces and automate service provision to the citizens in years to come.

Adjunct and open parking lots 01 Flat, underground and combined parking slots are placed inside or close to capital development objects. The most convenient for apartment house inhabitants and business centers workers. Moscow parking space is being built according to Mostly free of charge. the New Moscow transport system development program aiming at lowering the amount of cars long parked at the traffic way and transport speed increasing in the city center. At the present moment New Moscow demands constantly raising amount of parking lots.

Interceptive parking lots 02 Inside new neighborhood units built according The main task of this type of parking lots is to provide vehicle to the complex territory development, various keeping within 24 hours, while the citizens use various public types of parking lots are being placed depending transportation. Generally placed near subway stations and Multilevel construction transfer hubs. Equipped with surveillance system, access on its proximity to residential houses, sales outlets, monitoring and checkout terminals. Inside the boundaries of multilevel con- social objects, etc. On the borders of multi-storey struction 55-90% of parking spots are residential buildings multi-level parking lots are placed in vehicle sheds and driveways. often situated. This solution allows organizing The rest are situated on the parking lots adjacent to the road network or open the “carless yard” concept for the inhabitants of areas while the standard is 1 parking slot these houses. per 80-90 square meters.

03 Vehicle sheds and shared use parking lots Specially equipped places for temporary vehicle storage. Could be separate one- or multi-storey buildings with parking ramps, automatic elevators or could be a fenced territory with allocation on separate place. Could be paid or free of charge.

Amont of parking spaces in New Moscow meeting modern standards 1500 m

Maximum distance of parking spots beyond residential areas

Parking lots within road network

Private house building 04 One of the most demanded types of city parking spots during 100% of parking spots are located every day driving and infrastructure usage. Municipal policy is within the boundaries of private house aimed at civilization of this type of parking spots and correct building. The standard is 1 parking slot traffic organization in these areas, planning of special areas per 150 square meters. with lowest traffic impact and provision of priority for short term scarce parking spots.

2012 2017 2035

56 57 PART 2.1.4 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Cycling routes in «Living history» city park in New Moscow Cycling routes Rastoropovo to Ostaf’evo airport →

KILOMETERS to Kaluga hwy. → hwy. Kaluga to All new roads in New Moscow are built with consideration for bike lanes placement. Safe bike lanes should duplicate Nikul’skoe all traffic directions in order to be able to get to any point of the city via bicycle. This initiative is based not only on Ostafyevo international practice and research, but also on positive 35 Prometey to Ostaf’evo manor → feedback of Moscow residents to bike lanes in historical part of the city along the roads connecting different districts and near outbound routes. OF CYCLING ROUTES WILL BE BUILT BY 2025 Veteran

Mostovskoe

Andreevskoe

According to scandinavian practice full-featured bike Main cycling routes Leisure spots lane duplicating the road increases the amount of cyclists by 20% and decreases vehicle traffic by 10%.

Bike lanes growth from 2012 year in big metropolises with identical weather conditions Bicycle usage frequency in big metropolises with identical weather conditions exemplified by Copenhagen

+200%

New York

+72%

Montreal 68% 50% +50%

Vancouver Using the bike every day Using the bike at least once a week

58 59 PART 2.2 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Prospective development of public transport in New Moscow involves creation of multipath route network of buses and shared taxis, building of new high-speed tram and subway lines and renovation and development of present directions of railways. Many routes of various transport types combine in transport hubs for citizens’ convenience.

60 61 PART 2.2.1 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Subway in New Moscow

KILOMETERS

MORE THAN 72

LENGTH EXTENSION OF TROITSKY AND 20 NOVOMOSKOVSKY ADMINISTRATIVE DISTRICTS SUBWAY NEW STATIONS 4 NETWORK

NEW ELECTRIC ENGINE HOUSES

Moscow Metro — is the most convenient and fastest public transport. At the time of connection of new territories to Moscow they had no subway stations. At the present moment the active subway network building is in progress in New Moscow. Subway development plans implementation will allow significant improvement of transport linking of New Moscow and other city districts.

62 63 PART 2.2.1.1 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Subway organization scheme Borovskoe highway Govorovo Rasskazovka Rumjantsevo

Pykhtino Salaryevo Slavjansky Transition to typical Vnukovo airport mir Subway organization scheme in Troitsky and Novomosk- station design ovsky Administrative districts (TINAO) involves building new It will decrease building costs to 15- Filatov lug Mamyri lines: 20%. However the inner design is cus- tom made with unique design concept. Prokshino • Kalinino-Solntsevo line prolongation to Vnukovo airport; Kommunarka

prolongation to Moskovskoe and Stolbovo Sosenskoe settlements;

Sosenskoe Butovo • Troitsk city — Ulitsa Novatorov station — Central part Voskresenskoe of the city;

Desna • Ryazanovskoe settlement — Birulevo East district — Birulevo west district — Nagatinsky creek.

Strosyrovo Subway lines in New Moscow designed in a way providing Andreevskoe transport communication of downtown with New Moscow Ryazanovskoe urbanization centers (Salaryevo, Kommunarka, Troitsk, etc.) nearby. Shallow stations are prefferred while constructing the Tarasovo New subway car New Moscow subway, because they are built faster and cheaper. Spanish method Building shallow stations New subway trains ride quiet and smooth, have good noise and ther- of subway construction and cut-and-over tunnels mal isolation. Due to rational inner space usage they can transport up Suppose building with widespread Those stations are cheaper by an aver- to 2000 passengers. European technology - two railways age 2 million rubles and built with platforms on the sides. much faster. Building speed is greatly increased because the tunnel is carved through Current subway lines wit one tunneling machine of large and lines outside TINAO diameter instead of two.

Planned subway lines

One pass through Light and sound door Video surveillance Baclash-free Progressive conditioning Passenger evacuation all train cars opening indication in the cabin car mesh and air purification system landing ramps in the cabin

64 65 PART 2.2.2 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Tram in New Moscow

AROUND 600 KILOMETERS 178 TRAM STOPS

Tram is a brand new public transport in New Moscow. It calls for OVERALL TRAM NETWORK improvement of New Moscow districts’ transport availability by connecting LENGTH BY 2035 them with each other and with transport hubs where people can change for bus, subway or car. Modern tram cars and multipath tram line will significantly improve the speed and quality of transport service for 3 New Moscow citizens, including mobility impared people. NEW TRAM DEPOTS

66 67 PART 2.2.2.1 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Vnukovskoe Mosrentgen Standards and approaches Moskovsky for tram routes Kokoshkino Sosenskoe Marushkinskoe Filimonovskoe

Comfortable, eco-friendly, fast and cheap compared to subway construction - New Moscow tram will allow transferring of many passengers without additional load on road network. Voskresenskoe Tram actuated traffic lights Securing the priority of tram Pervomayskoe Scherbinka transit. Desenovskoe Troitsk Building of several high-speed tram lines will begin in the Tram lines will represent a relatively dense route network Ryazanovskoe short term. All necessary work on corridor securing in that connects territories in need of public transport master layout plan was made and currently approved on development: large residential areas, airports, business the overall scheme. This transport type aimed at New Mos- activity centers and recreational zones. cow and Moscow districts’ transport availability increase. Krasnopakhorskoe Novofedorovskoe

Mikailovo- Kievskoe Schapovskoe Yartsevskoe

Guardrails and specific rail IT solution road construction, Electronic validator for ride ex- Voronovskoe that exclude car entry and penses and interactive navigation pedestrian access. system for passengers Klenovskoe

Rogovskoe

Trains with cabs in front and tail ends Turning without traffic circles (similar to subway trains)

Cars with low floor level and many doors Increasing of passengers’ boarding and deboarding speed

68 69 PART 2.1.3 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Railways in New Moscow 93 КИЛОМЕТРОВ NEW TRAINS WILL BE INCLUDED INTO SUBURBAN 85 TRAFFIC SCHEDULE

NEW AND RENOVATED RAIL ROADS WILL BE BUILT IN 5 TINAO

CROSSOVERS IN KURSK AND KIEV DIRECTIONS OF 2 MOSCOW RAILWAY

NEW HALT PLATFORMS

Moscow railway is the key element of Moscow transport hub that provides service to millions of passengers annually. As part of government support throught the offices of Moscow City Government and Russian Railways railway infrastructure of Moscow transport hub is being actively developed: new rail roads and stations are being built, the rolling stock is being renewed.

70 71 PART 2.2.3 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Kiev direction of Moscow railway hub Kursk direction of Moscow railway hub development development

Railroad infrastructure development is necessary for effective Vnukovo airport Moscow railway Smolensk direction and seamless transport communication between the city center and New Moscow territories and for fulfillment of increasing demand for Airport Zdravnitsa passenger rail travel.

Podol’sk 299 660 ppl Perkhushkovo

Lesnoy gorodok Znamya Oktyabrya 8 909 ppl Lesnoy gorodok 7 394 ppl

Vnukovskoe village Vnukovo 6 914 ppl Bykovo village Podol’sk 10 927 ppl

Silikatnaya Michurinets

Ostafyevo

Peredelkino Novoperedelkino Shcherbinka 120 737 ppl Shcherbinka Speed 160 km/h Support sysems for disabled 42 642 ppl people Butovo Yuzhnoye Butovo Solnechnaya Solntsevo 122 410 ppl 204 226 ppl

Skolkovo Moscow

Moscow

Inner air conditioning and Commuter train traffic increase for WC in every car Commuter train traffic increase for heating project implementation project implementation

92 140 68 104 Solnechnaya — Lesnoy gorodok Tsaritsino — Podol’sk

20 48 Lines under construction Lesnoy gorodok — Airport Moscow railway will have new trains equipped Free Internet for passengers with air conditioning, wi-fi, toilets and systems Current lines for disabled people. Changed profile of current main railways Moscow-Kievskaya - Novoperedelkino train route is currently planned. Current railway stations 18 46 Railway stations under construction and renovation Planned railway stations Airport — Vnukovo Terminal

72 73 PART 2.2.4 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Bus transportation 760 KILOMETERS NEW BUS STOPS BY 2020 190

NEW ROADS FOR NEW 8 ROUTES BY 2020

BUS DEPOTS IN TINAO

Gradual extension and reconstruction of the street and road network in New Moscow stimulates bus transport active development. Appearance of new routes, decrease in travel time, and purchase of new, modern buses stimulates improvement of transport service for New Moscow citizens.

74 75 PART 2.2.4.1 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Vnukovskoe Mosrentgen Bus routes Moskovsky

Kokoshkino

Sosenskoe Wheelchair ramps for Marushkinskoe Filimonovskoe disabled people Buses will be equipped with New Moscow transport development includes several directions. mechanical folding ramps for wheelchairs and baby carriage. Not only the expansion of road network, but also improvement of land transport connection. Voskresenskoe

Pervomayskoe Scherbinka

Troitsk Desenovskoe New Moscow road network reconstruction and develop- These systems allow quick changes in public transport Ryazanovskoe ment will become a basis for elaboration of current and schedules and routes increasing the transport service creation of new bus routes. Renewed routes will be planned quality for New Moscow citizens. in a way that helps passengers save up to 30% of time. Krasnopakhorskoe Most loaded routes headway will be decreased in more than 2 times. Additionally, new GLONASS based real-time Novofedorovskoe control and monitor systems of transport movement are Schapovskoe Mikailovo- currently being implemented. Kievskoe Yartsevskoe

Voronovskoe Public transport intellectual information system Bus stop working range Qualitative step forward for traffic members communication in com- Bus stop availability radius doesn’t exceed 500 meters. It stimulates parison to common transport systems. New Moscow sitizens on using the public transport.

Klenovskoe

Few types of buses Routes will have a few types of transport: buses and shared taxis. Separate lanes for buses Rogovskoe Separate lanes for buses and shared taxis.

THOUSAND KM

Next generation bus stops Bright, having free wi-fi and phone chargers. Easy naviga- 500 м 5,4 tion and ticket counter. 109

OVERALL ROUTE LENGTH ACTIVE ROUTES OVERALL

76 77 PART 2.2.4.2 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Standards and approaches COMFORTABLY ALLOCATED IN for bus transport BUS CABIN PASSENGERS

New Moscow bus transport development includes sev- For example: wide implementation of separate lanes for eral ways. Not only the expansion of road network, but buses or organization of traffic in loaded areas with pri- also active usage of new and worked out methods and ority to public transport. technologies of land transport connection improvement.

Comfortable Technical safety All buses are equipped with climate Buses comply with technical regulations control systems keeping comfortable of UNECE. Buses age is not more than temperature the year around. 2 years.

Lighting Roof equipped with automatic Information board lighting Video surveillance Shows transport arrival time Video monitoring protects from vandalism Wi-Fi Free Wi-Fi at every bus stop

Glazing Maps and schemes USB-port Eco-friendly Accessibility Modern

Low glazing protects from New maps and schemes for USB-ports for device Renewed fleet wit low СО2 emission All buses have low floors. The major- Information boards, cabin information wind and dirt comfortable navigation charging ity of buses is easily accessible by placement requirements, connection to disabled people. «Our city» system.

78 79 PART 2.2.5 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Public transport interchanges

21%

DECREASE IN USING THE INDIVIDUAL TRANSPORT DUE TO INTERCHANGE HUB 15%

DECREASE IN TRAVEL TIME

Transport interchange hub - the passenger complex, performing functions of passenger flows redistribution between various transport types and routes. Usually, interchange hubs appear in large transport junction points in order to optimize passenger carriage and to decrease logistic expenses.

80 81 PART 2.2.5 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Transport Rasskazovka interchange hubs 24 Michurinets

HUBS PLANNED Filatov lug Mamyri Transport interchange hub is a nodal element of social Twenty four transport hubs are planned to build by 2035 TO BUILD BY 2035 Krekshino and transport purpose in city planning structure. Hubs on the territory of New Moscow in order to provide pas- Filimonovskoe Prokshino perform interchanges between various types and routes sengers with comfort and convenience, and to effectively of urban, regional, interurban and personal transport and connect all types of public and personal transport within Mar’ino Stolbovo against each other, and also provides social infrastructure unified system. Owing to them tens of thousands of people Pervomaiskoe Sosenki service to passengers. will be able to comfortably move around the territory of Yamontovo Desna New Moscow and also get to the center of the city and its districts fast. Desenevskoe Scherbinka

Starosyrovo Vatutinki Yakovlevo Ryazanovskoe In addition to unification of all types of transport the project implies: Tarasovo creation and renovation of social spaces, street-retail, planting, improvement of territory, parking spaces, hotel and business complexes and residential objects, and also improvement of traffic organization and passenger loading zones.

Train

Warm compartments Bus Social zones, shops, pas- sages. Subway

Enclosed passages Train platforms Tram Glazed warm passages between Platforms for high-speed hub zones trains. Car

Parking spots Interceptive parkings

Main principles of Transport interchange hub: Subway lines Underground subway Consumer proximity. Availability of Minimal distanced between multi- Accessibility of shops and services lines 1 work places and accomodation. 2 modal interchanges. 3 for passengers.

82 83 What kind of transport should be developed in New Moscow according to its residents? Based on the data of Russian Public Opinion Research Center

14,2% Buses Equally large-scale transformations should 15,3% take place in the road network, public transport Commuter trains as well as infrastructure for cyclists and pedestrians.

19,2% High-speed tram

30,7% Conditions for personal transport

84 85 PART 2.2.6 / INFRASTRUCTURE

North-west region of Russia, The Baltic states, Northland Global (М11 federal highway) logistic hub Moscow Ring Road The trunk road connects all districts of Moscow, thus providing the The hallmark of New Moscow is its majority of carriage within the capital and also serves as a transit advantageous location amid major corridor. Currently the grand-scale reconstruction of the Ring road is international transport corridors occuring: exits are being upgraded, lanes number is being increased, andadvanced transport system 34% acceleration lanes are being built. The capacity and average speed are expected to significantly increase GROSS REGIONAL PRODUCT after the work is done. Existence of large hubs of railroad, air and water transport allows OF RUSSIA IS PRODUCED IN provision of high quality transport services to people and business CENTRAL FEDERAL DISTRICT units, comfortable travelling conditions and efficiency of all types of haulage including international.

New Moscow territory can take on a role of big distributing hub Western Europe due to this factor. This hub gives opportunities on handling of the (М1 and М9 federal highways) cargo from various transport types by connecting all cargo traffic in one place that allows developers to minimize cargo processing time and to increase range of services. It increases availability and MLN PEOPLE Vnukovo Airport quality of logistic services for freight traffic. 15 million passengers annually, 55 flights per hour in pear periods. Acoustic engi- neering with modern program complexes Central Ring Road is in progress, special air corridors that In future it is going to be one of the comply with all international noise level most up-to-date and technically standards are worked out. The grand advanced roads in Russia, having 4 Aeropolis project with convention and to 8 lanes, which will unite the whole expo centers, hotels, business centers, 40 Moscow agglomeration, main radial is planned to be created on the basis of directions and relieve Moscow from Vnukovo air hub LIVING IN CENTRAL FEDERAL transit transport. It is one of the Ostafyevo Airport biggest infrastructure projects with DISTRICT the cost around 1 trillion rubles. The most up-to-date business airport in Central region. Is developed by Gazprom

BLN DOLLARS

50 Bekasovo station The biggest freight yard in Europe. A Russian South, large distribution center development South Caucasus, MAKE SALES VOLUME ONLY IN project is in progress on its basis, also Southern Europe Turkey, Iran, СCentral Asia, EUROPE-CHINA TRANSPORT about 3 mln square meters of business At the intersection of international transport corridors (М3 federal highway) and storage spaces for international and India, China CORRIDOR russian companies are being built. (М2 and М4 federal highways)

86 87 PART 2.2.7 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Engineering infrastructure development THOUSAND CUBIC METERS PER DAY

New Moscow energy capacity will increase in heat supply by more BLN CUBIC METERS PER 350 than 2 times, in power supply by more than 4 times. The proportion YEAR of the population provided with central water supply will increase WATER by 5 times and natural gas network coverage will increase by more than 6 times. 2

NATURAL GAS

GCAL PER HOUR 2 050

MEGAWATT HEAT 1 800

POWER

88 89 PART 2.2.7.1 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Vnukovskoe Mosrentgen Organization Moskovsky and development of Kokoshkino Sosenskoe power supply system Marushkinskoe Filimonovskoe

Planned power consumption increase in the territory of Cable power lines Voskresenskoe Underground cable power line TINAO is estimated around 1800-2000 megawatt. In- assembly in the territory of admin- Pervomayskoe Scherbinka creased energy consumption is planned to recompense istration and business center in via the reinforcement of external Moscow power system Kommunarka village. Desenovskoe Troitsk links with electricity from and Smolenskaya Ryazanovskoe NPPs via 500 kilowatt long-distance power network and 500 kilowatt Sof’ino substation building.

Building of eight 220-kilowatt electric substations with Krasnopakhorskoe 250 kilometers of power lines and five 110-kilowatt power plants with 50 kilometers of power lines is planned as part Building of enclosed high-voltage substation using the Novofedorovskoe of region power network development and reconstruction. concept of digital substation Schapovskoe Mikailovo- Kievskoe Engineering and building of 220 kilowatt Khovanskaia substa- Yartsevskoe TINAO power supply scheme is intended to change tion as part of reserve increase of electric power and energy current sink from 35 to 20 kilowatt with future 35 kilowatt supply reliability on connected territories. It is decided to build Khovanskaia substation enclosed in order to reduce noise level main substations re-equipment. and increase environmental friendliness. The future substation building is designed with compliance to world trends in power supply construction aimed at improvement of aesthetic view of Voronovskoe Building of intellectual power network with elements of buildings. oscillating sources on the basis of solar panels with energy accumulation systems on 6 (10) – 20 kilowatt power lines, creating of new 20 kilowatt distribution line according to biradiate scheme from different power sources, elimination Klenovskoe of dead-end power supply schemes and transfer network voltage from 6 kilowatt to 10 and 20 kilowatt.

Rogovskoe ELECTRICAL KILOMETERS SUBSTATIONS Existing lines Projected lines Powerplants capacity till 2025

Building of long-distance power 500 kW 500 kW 500 kW networks 220 kW 220 kW 220 kW Reinforcement of external Moscow power system links for additional power 110 kW 110 kW 110 kW Using the aesthetic supporting poles for high-voltage supplement from Kalininskaya and 35 kW 35 kW 35 kW 400 14 power lines Smolenskaya NPPs via long-distance Steelwork of the power line poles fits naturally into the modern city power lines and 500 kilowatt substa- tions building Existing powerplants POWER LINES WITH VOLTAGE CAPACITY image. Steelwork of the power line poles doesn’t require any special or additional maintenance during operation. New powerplants

MORE THAN 110 KILOWATT EXCEEDING Powerplants under reconstruction 200 MEGAWATT

90 91 PART 2.2.7.2 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Vnukovskoe Mosrentgen Organization and development Moskovsky of natural gas supply system Kokoshkino Sosenskoe Marushkinskoe Filimonovskoe Dispatching control stations Purify natural gas from mechanical impurities, con- densed water and moisture; reduce passing through Currently the maximum limit of natural gas consumption located in TINAO in gas reducing stations that will lead gas volume, reduce pressure and add odorant before delivery to the consumer. in new territories makes 296 thousand cubic meters per to a prominent decrease of its protective zones. At the Voskresenskoe hour. According to TINAO territory development schemes present time Mosgaz is developing a main scheme of maximum hour consumption of natural gas will increase Moscow city gas supply till 2035 with consideration for Pervomayskoe to 1,3 million cubic meters per hour by 2035. connected territories commissioned by Fuel and Energy Scherbinka Department of Moscow city. Desenovskoe Currently as part of Gazprom investment program Gaz- Troitsk Ryazanovskoe prom Transgaz Moscow is conducting pre-project phase This scheme considers alternatives of future gas dis- of large main gas supplement facilities building on the tribution system development both on the basis of the border of TINAO (Dispatching control station 20 and 21). current one under the supervision of SUE Mosoblgaz and regarding construction of new networks. Krasnopakhorskoe Building of these objects will solve the issue with facility shortage on major part of the territory and allow According to preliminary estimates it is needed to build Novofedorovskoe turning current gas distribution stations (Selyatino, Zor’ka, not less than 5 thousand kilometers of gas distribution Schapovskoe Mikailovo- Voskresenskoe, Erino, Mikhailovskoe, Krasnaya Pahra) lines in order to provide all TINAO gas consumers. Kievskoe Yartsevskoe

Voronovskoe

Hot tapping Using the technology of “hot tapping” in order to avoid gas consumers cut offs and to decrease greenhouse gas emissions during cutting-ins Klenovskoe

Rogovskoe Block-type gas distribution stations Using typical block-type gas distributing stations, especially for residential area gas MILLION CUBIC distribution. METERS PER HOUR

Existing gas distributing station

Existing gas reduction station Gas reduction station in project or Enclosed gas pipeline installation methods Plastic tube lines reconstruction

1,3 With development of gas distribution system it is planned to use modern building Resistance against corrosion, chemicals and Existing gas pipeline technologies, such as wider usage of enclosed gas pipeline installation in order deleterious substances. Low gas permeability, Projected gas pipeline MAXIMUM HOUR GAS to minimize the amount of ground cuts and human impact on the environment. facilitated delivery and assembling, durability. Existing high pressure gas pipeline CONSUMPTION BY 2035

92 93 ЧАСТЬ 2.2.7.3 / ИНФРАСТРУКТУРА NEW MOSCOW — CITY DESIGNED FOR LIVING

Vnukovskoe Mosrentgen

Organization and development Moskovsky of heat supply system Kokoshkino Sosenskoe Marushkinskoe Filimonovskoe

Consumption supplement is proposed to be made by at the expense of investment programs of heating supply Computer model of central heating system will allow assumption of optimal economically viable increasing of current impact zones of heat generators companies and with attraction of financial resources of solutions with respect to normal heating and hydrau- and by building and reconstruction of 5 power supply territory developers and also due to renovation of 70% lic values Voskresenskoe facilities of medium power and 88 boiler-houses in the of current heating sources with old equipment. Pervomayskoe territory of TINAO. Scherbinka Heating of low rise and cottage houses will generally Troitsk Desenovskoe

In order to fulfill consumers’ needs the construction rely on automatic boilers. Introduction of mathematic Ryazanovskoe and renovation of main heating systems with 460 kilome- computer model of central heating system will allow cal- ters of overall length in the territory of TINAO is needed. culation of potential consequences of planned events thus enabling assumption of optimal economically viable Multilevel, industrial and other development will be solutions on adjustment, regulation and modernization of Novofedorovskoe Krasnopakhorskoe supplied with central heating from heat power sources central heating system to supply consumers with normal (power parks) and boiler-houses of various output built heating and hydraulic values. Schapovskoe Mikailovo- Kievskoe Yartsevskoe At the present time the thermal capacity in TINAO makes 950 Gcal per hour. Planned increase of thermal capacity in TINAO territory Voronovskoe by 2030 is estimated at 2000 Gcal per hour* Reconstruction of existent heating system Klenovskoe Equipment upgrade and software implementation for heating regulation in New Moscow. * Main objects

APPROXIMATELY KILOMETERS Rogovskoe

Upgraded power supply facilities Five eco-friendly power supply facilities are going to 90 350 be built in TINAO

BOILER-HOUSES UNDER MEW MAIN HEATING SYSTEMS Trigeneration Power supply facilities RECONSTRUCTION AND WITH DIAMETER EXCEEDING Using the schemes of combined cooling, heating and District heating station BRAND NEW 600 MM power including utilization of absorbtion refrigerators Boiler-house

Existing boiler-houses

Projected boiler-houses

94 95 PART 2.2.7.4 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Vnukovskoe ЗСВ Mosrentgen Organization and development Moskovsky

Kokoshkino of water supply and discharge Sosenskoe system Marushkinskoe Filimonovskoe Western water treatment plant — the main water supply source of New Moscow The Moscow city water supply facility retrieving Water supply Water discharge water from the Moskva River for purification. Projected capacity is 1700 thousand cubic Voskresenskoe meters a day.. Pervomayskoe Planned increase of overall power supply of New Moscow Water discharge system concept in TINAO is governed by Scherbinka at 348 thousand cubic meters per day, with 266 thousand the absence of large water objects on the territory and Desenovskoe Troitsk cubic meters per day from Moscow water supply system this doesn’t allow building new large sewage treatment Ryazanovskoe and 82 thousand cubic meters per day from underground facilities. sources. In this regard it has been decided to forward 270 Krasnopakhorskoe Reconstruction of West water treatment plant will be thousand cubic meters per day drain channels from the Novofedorovskoe done for supplement of new territories with water, current territory of Novomoskovsky Administrtive District to Kievskoe operating margin on to 300 thousand cubic meters a day. Moscow sewers system, because the largest Kur’yanovo

Building and reconstruction of 714 kilometers of water sewage treatment facilities of Mosvodokanal have suf- Schapovskoe supply lines including main water supply facilities with ficient capacity margin, also Yuzhno-Butovskie sewage Mikailovo- Yartsevskoe overall length of 78 kilometers. Building and reconstruc- treatment facilities will be reconstructed with capacity tion of 19 water supply regulation stations and 80 water increase at 30 thousand cubic meters per day. intake structures with installation of modern drinking Voronovskoe water purification systems. It will give the opportunity of total elimination of indi- vidual sewage caissons and cesspools.

Water distribution will be organized due to the build- Ozone generators of Western ing of control network of main water conduits and big About 40 local low-power water purification facilities water treatment facility. distribution facilities. Main water conduits with diameters with sewage water purification levels to the norms of Existing classic two-step technological scheme from 600 to 1000 mm will be laid alongside the main “fish farm” will be built in the territory of Troitsky and will be supplemented by other progressive Klenovskoe radial highways (Kaluzhskoe highway, Kievskoe highway, Novomoskovsky Administrative District. methods such as ozone treatment with sorption on absorbent coal and membrane filtering. Borovskoe highway, Varshavskoe highway). Later on they will be united into one network due to the building of di- rect main conduits (example: 600 mm diameter conduit alongside Solntsevo-Butovo-Vidnoe road). Rogovskoe

KILOMETERS

Water distribution and water-intake stations Kur’yanovo sewage treatment System of membrane Water purification facilities Deferrization plant facilities treatment of sewage water reconstruction in Marushkino Water-intake facilities maintaining Main water supply lines flow village Water discharge system in districts operation will be upgraded as well as Water distribution systems remote to Moscow Ring Road will Modern technologies like mem- with building of UV sanitation system water treatment systems which include be partially centralized due to local brane treatment and UV sanitation and mechanical sedimentation dehy- deferrization and sanitation of water. 714 water treatment facilities. of purification facilities are to be dration workshop. Water disposal objects utilized during the reconstruction Main water disposal lines of water purification facilities WATER SUPPLY Local water disposal

96 97 PART 2.3 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Vnukovskoe Mosrentgen Recreational Moskovsky Kokoshkino

Sosenskoe resources Marushkinskoe Filimonovskoe

Voskresenskoe PARK AREAS Unique nature as well as the total amount of green Pervomayskoe Scherbinka plantings on attached territories will bring Moscow the Desenovskoe leadership position in terms of environmental conditions Troitsk Ryazanovskoe among the world capitals.

Historically, the least developed area of Moscow sub- urbs, with a minimum number of industrial enterprises 86 Krasnopakhorskoe has retained the best features that nature can give to the citizen in terms of leisure activities, wellness and ARE PLANNED TO BE environment comfortable for living. The abundance of Novofedorovskoe ORGANIZED AT THE Schapovskoe water resources - clear lakes and rivers offers great op- Mikailovo- TERRITORY OF NEW Kievskoe portunities for the tourism industry. Yartsevskoe MOSCOW Every Moscow citizen can now visit truly protected, unspoiled locations without leaving the boundaries of the city. At the same time many parks and squares of Voronovskoe urban settlements are gently renovated. Quality of work and improvement of standards match the Government THOUSAND HECTARES of Moscow programs that were highly evaluated by the residents of the capital in the past few years. Klenovskoe Strict control over the preservation of the ecological environment will ensure that future generations of citi- zens will be able to spend time in the places enjoyed by 12 their parents. WILL BE THE TOTAL AREA OF PARKS AND RECREATIONAL Rogovskoe ZONES AT THE TERRITORY OF NEW MOSCOW

Suggested park lands

Recreational and touristic areas

Specially protected green territories Forecast till 2035.

98 99 Expenses of the city, aimed at the establishment and maintenance of recreation areas, reconstruction of waste treatment facilities, and other activities related to the conservation of sustainably favorable environment, bln rubles

Maintenance of recreational areas and facilities Creation of recreational areas and facilities

11,9 10,2

8,8

7,9

6,7

5,7 10,8 9,7 8,8

7,9 6,6 2,8 5,6

2,8

2012 2013 2014 2015 2016 2017 2018

Citizens of Moscow see the benefits for families with children living in the newly-included territories in a comfortable urban environment.

100 101 PART 2.4 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Cultural heritage sites

After the extension of Moscow boundaries, it has received not only new territories, but also 175 new objects — monuments, assemblies, historic and archaeological heritage objects.

CHURCH OF ELIJAG THE PROPHET IN IZVARINO VORONOVO HOMESTEAD VVEDENSKOE-BORISOVKA TEMPLE COMPLEX HOUSE OF BAKER FILIPPOV ZOSIMA FEMALE MONASTERY A church in the former estate of Abrikosov V. A. — Family estate of Volinsky family — descendants of A new complex of churches successfully styled on eminent examples of wooden architecture of the Russian North. Built on Situated on site of the ancient Peremyshl’ for- Operational female monastery, founded by Saint the successor of the founder of Babayevsky Candy factory. Dmitry Donskoi warchief, noted for the Battle of site of the vanished village, in which, according to the legend, miraculous icon had appeared. tress-city. Belonged to Filippov D. I. the owner of Zosima Verkhovsky in the first third of XIX century. Kulikovo. famous Moscow bakery.

Voronovo homestead One of the oldest Moscow regional homesteads. Till the middle of 2012 Voronovo vilage belonged to Podolsk district of the Moscow region and then has been connected to New Moscow.

The said list includes 48 monuments and assemblies, 121 One of the main challenges facing the Government of archaeological and 5 historic and military objects. 17 of Moscow is probably to make these historic places and them are of federal importance, 31 are of regional impor- objects accessible and attractive to visitors. tance, and the rest 127 objects fall within the category of recently identified cultural heritage objects. Monitoring To provide in full with engineering communications of all objects was promptly performed. Following its re- and transport infrastructure, include the objects into sult, work on organizing the documentation support for the tourist routes, popular among Moscow residents and monuments, as well as their repair and restoration works guests of the capital. were started.

VALUEVO HOMESTEAD OSTAFYEVO HOMESTEAD Domain of earl Musin-Pushkin A. I. - discoverer of the first russian work of literature «The Tale of Igor’s Campaign» Homested of Vyazemskie. Visited by Zhukovsky, Griboedov, Pushikin and Gogol. The manor is so picturesque that many Soviet films have been shot there.

102 103 PART 2.5 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Sport 17 facilities MONUMENTS OF FEDERAL TOTAL IMPORTANCE 700

NEW SPORT 127 CONSTRUCTIONS MORE THAN RECENTLY IDENTIFIED CULTURAL HERITAGE OBJECTS 150

NEW FLAT 31 CONSTRUCTIONS

MONUMENT MORE THAN OF REGIONAL IMPORTANCE Creation of conditions for sport and physical activities encourages the 130 establishment of healthy lifestyle in New Moscow, enhances the quality of life, and supports people’s health and working efficiency. Consecutive LARGE SPORT government policy involves not only building of sporting venues but also CONSTRUCTIONS re-equipment of street playgrounds, complex development of natural 300 environment framework and improvement for outdoor sport activities.

BUILDINGS AND CONSTRUCTIONS

104 105 PART 2.5.1 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Sport infrastructure in natural zones

Summer leisure areas Winter sport trails

One of the peculiarities of the New Moscow territory is proximity and integrity of natural zones into existing settlements. New urban planning projects are also planned with respect to this advantage that allows organization of comfortable places for outdoor sport activities close to residential areas or business parks.

A variety of projects is being implemented and already exists. They give the opportunity to literally step outside and take on the ski-track or ride the bicycle down the forest trails depending on the season. In addition to this, special areas for water sports, horse riding trails and group activities are Bike lanes Horse riding Swimming holes Places for water Fishing places Tourist routes Winter ski trails being organized trails sports PART 2.5.2 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Sport facilities of New Moscow

New sport facilities of various scales are built and recon- Equestrian centers structed, and old sport facilities are reequipped in Moscow annually. These facilities range from fitness centers and children playgrounds to immense high-technology stadiums and world-class ice stadiums.

In the first place such sport promotion is supported by the government policy aimed at people health improvement. The second important factor is understanding of healthy lifestyle importance and sport benefits by considerable number of people.

Physical culture schools Commercial fitness centers

Gyms in schools

Swimming pools

Stadiums and multifunctional complexes Seasonal playgrounds for outdoor sport activities

Courts and enclosed playgrounds Sports and recreation centers

108 109 PART 2.6 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Safe city

People safety issues have always been and remain one Efforts of government authorities of the city of Moscow of the key priorities for Moscow Government. In order to and law-enforcement authorities of Russian Federation, solve these issues the government has developed “Safe who also solve safety issues, should provide reduction of city” government program of the city of Moscow, which is threat growth rates and ultimately guarantee the protection also being implemented in the territory of New Moscow. of citizens and city objects from crime, terrorist attacks and emergency situations.

BLN RUBLES 1

ANNUAL AMOUNT OF 100% FINANCING IN TINAO SAFETY

SECURING THE TERRITORY WITH SYSTEMS OF INDOOR AND OUTDOOR 50% VIDEO SURVEILLANCE BY 2035

EXPECTED DECREASE OF ROAD ACCIDENTS BY 2035

110 111 PART 2.6.1 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Fire stations

Vnukovskoe Mosrentgen MORE THAN Sixteen fire stations are to be built in New Moscow till the Moskovsky end of 2021. They will be located in Scherbinka, Marushkino village, Klenovo and Mikhailovo-Yartsevo. Kokoshkino

Sosenskoe Distances between settlements of New Moscow are Marushkinskoe Filimonovskoe relatively long, but at the same time there are regula- tions on fire truck response time that call for creation of 200 a denser network. In addition to fire stations budget will finance construction of driveways and supplement of all FIRE TEAMS WILL APPEAR IN necessary engineering infrastructure NEW MOSCOW BY 2035 Voskresenskoe

Scherbinka Pervomayskoe Desenovskoe Troitsk Ryazanovskoe

Krasnopakhorskoe Existent stations action radius

Novofedorovskoe Schapovskoe Kievskoe Mikailovo- Action radius of stations under construction Yartsevskoe

Amount of new fire stations by 2021. Voronovskoe

16 Fire station project in Klenovskoe village with six car spaces Klenovskoe 14 13 Location of fire-fighting units in the territory of settlements and urban districts is determined by the condition that the first unit response time within settlements and urban Fire station districts must not exceed 10 minutes and not exceed 20 Rogovskoe 9 minutes in rural settlements. 20 minutes max Conditions and methods of fire-fighting units place- 6 ment in the territory of settlements and urban districts is stated in fire safety regulations.

2016 2018 2019 2020 2021

112 113 PART 2.6.2 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Governmental information system for gathering, processing and storage of video materials from cameras installed Video surveillance around the city is designed to increase life quality of people of Moscow city and provide necessary security level. Members of Federal authorities, Mayor of Moscow and his authorized officials, law-enforcement and executive au- systems thorities are granted access to the city video surveillance system.

City video surveillance Road video surveillance

Increase of effectiveness Increase of crime solving Decrease of crime and Yard cleanness, Traffic congestion data Decrease of traffic accidents Crime control and prevention Budget revenues from of municipal services vandalism levels decrease of budget pressure gathering and analysis rate imposed fines administaration on services of housing and utility sector employees.

114 115 PART 2.7 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Functional areas

Vnukovskoe of New Moscow Mosrentgen Moskovsky Major part of free territory is divided between Kokoshkino zones of mixed functionality Sosenskoe Marushkinskoe Filimonovskoe

Looking at the diagram of the functional division of New Moscow territory the natural formation of sustainable urban development centers of activity becomes obvious. Major part of free territory is divided between zones of mixed Voskresenskoe functionality, such as «public-residential», «natural-public» or «natural-industrial and residential». Pervomayskoe Scherbinka Desenovskoe Troitsk Ryazanovskoe

MORE THAN Krasnopakhorskoe

Novofedorovskoe Schapovskoe Mikailovo- Kievskoe 1 500 Yartsevskoe

OBJECTS BUILT IN NEW MOSCOW Voronovskoe FROM 2012 TO 2016 Types of functional zones

Public

Residential Klenovskoe Industrial

Such division will allow the formation of multi-function- Natural al environment with the simultaneous development of Public-residential natural, engineering and transport framework. Urban Public-industrial planning activity zones projected for the development are combined with the formed points of the natural con- Industrial-residential centration of population. Rogovskoe Natural-public Natural-residential

In these very zones the active development of residen- Natural-industrial

tial property, workplaces creation, as well as placement Natural-public-residential

of the major objects of engineering and transport infra- Natural-public-industrial structure is planned. Natural-industrial-residential

Public-industrial-residential

Agricultural

Functionality provided by general plans of Troitsky and Scherbinka urban districts

116 117 PART 2.8 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Estate property commissioning amount in New Moscow 100+

MILLION SQUARE METERS Property size of more than 11 million square meters in total is cur- rently put to use. The overall size of objects planned for construction and reconstruction by 2035 is more than 100 million square meters, including about 56 million square meters of residential buildings and about 47 million square meters of public-business, production, mu- nicipal and other non-residential buildings. The total real estate fund of New Moscow including existing and objects under construction will make about 127 million square meters. 65 * According to approved territorial schemes of Novomoskovsky Administrative district and Troitsky Administrative District MILLION SQUARE METERS 8,2

MILLION SQUARE 5,2 METERS

MILLION SQUARE 2,6 METERS

MILLION SQUARE 0,6 METERS

MILLION SQUARE METERS

in 2012 till 2014 till 2015 till 2016 till 2025 till 2035

118 119 PART 2.9 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Investment in urban planning development of New Moscow TRILLION RUBLES

New Moscow development is mainly focused on attract- ical culture and sports facilities, as well as transport ing extra-budgetary investment through public-private infrastructure within the scope of powers assigned. partnership taking into account interests of people who Construction of residential and commercial property will reside in this territory. The city budget is involved in and creation of workplaces is carried out mainly at the the creation of health care, educational, cultural, phys- expense of investors.

TRILLION RUBLES 7,0 5,9 TOTAL INVESTMENT IN 2013-2035 TRILLION RUBLES 2,5 INVESTMENT TILL 2030 TRILLION RUBLES INVESTMENT TILL 2020

TRILLION RUBLES 0,43 0,12 INVESTMENT TILL 2015

INVESTMENT TILL 2013

120 121 PART 2.10 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Workplaces

Any regional development includes not only residential Commercial business has dominating role in workplaces property construction, but also provision of citizens with structure with 69 thousand positions. About 20 thousand workplaces and active leisure. Over the 5 years 10 million people are employed in each of the following sectors: square meters of property including 7 million square me- manufacturing, social sphere and construction. Amount ters of the residential one have been built in New Moscow. of jobs in construction sector will remain unchanged for 1 mln Almost all employable people of New Moscow have jobs 10-15 years. About 10 thousand workplaces are located owing to the creation of 183 thousand of workplaces. on the first floor of residential houses. WORKPLACES IN NEW MOSCOW BY 2035

BLN RUBLES 300

ESTIMATED NEW MOSCOW BUDGET INCOME IN 2035 65 (IN PRICES OF 2017)

SCIENCE PARKS

122 123 PART 2.10.1 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Workplaces: driving force of the New Moscow development 1000

Availability of labor, land, and infrastructural resources will become 890 a key factor for the breakthrough development of New Moscow. They will pave the way for creation of highly productive, competitive, and export-oriented jobs.

275 Workplaces, thousand 183 123,5 163,5 84,8 107 52,2 47,5

29,7

Non-residential property area, million square mters 12,3 Planning projects approved for TINAO include placement of 7, 9 required quantity of commercial property. This factor together 5,2 5,8 6,4 5,1 with financial model and investors’ interest in the territory for the last 5 years give confidence in provision of new citizens with all necessary business and production infrastructure.

Moscow budget income in real prices of 2017, bln rub.

MORE THAN 12,5 15 17,3 19,7 26,7 70 125 210 300

2012 2013 2014 2015 2016 2020 2025 2030 2035 PART 2.10.2 / INFRASTRUCTURE PART 2.10.3 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Work places Science Parks structure of New Moscow

Sixty per cent of one million newly created workplaces in provision of people with all kinds of social and other ser- Science Park is a property complex uniting research and According to IASP, Science Park is an organization New Moscow will be of high-tech nature, they will ensure vices according to norms and standards, in compliance development institutions, objects of industry, business and managed by specialized professionals, whose main aim the income level of people, business and the city essen- with leading world’s capital metropolises and achievement exhibition centers, educational institutions and service is to increase the wealth of its community by promoting tial for expanded reproduction of human capital able of leadership in high-tech applications that ensure com- objects as vehicles, driveways, residential settlements, the culture of innovation and the competitiveness of its to compete in the international market. Top-priorities in petitive advantage of Moscow on international markets. security. International Association of Science Parks and associated businesses and knowledge-based institutions. creation of workplaces are the following: Areas of Innovation (IASP) gives the following definition To enable these goals to be met, a Science Park stimu- of the object of innovation infrastructure. lates and manages the flow of knowledge and technology Technospark Science Park Skolkovo Science Park amongst universities, R&D institutions, companies and markets.

Priority investment Special investment Science Park status acquisition roadmap project status contract Succession of actions for commercial organization to acquire the status of man- assignment agement authority of techno polis, Technology Park or industrial park in Moscow City and annual confirmation of the management authority status

The department prepares the Government of Moscow Award of status of managing Project registration of the project on acquisition of status decides on acquisition of authority Agreement with the Declaran of managing authority for further status of managing authority Government of Moscow approval of a Science Park

Submission of the application DEPARTMENT OF SCIENCE, TYPES The committee decides whether on acquisition of status INDUSTRIAL POLICY AND Opinion of an expert body to assign or decline a status of OF GOVERNMENT of managing authority ENTREPRENEURSHIP managing authority acquisition Support at the SUPPORT Bank support of a Science Park OF MOSCOW expense of with government government funds participation Denial on acquisition of status of Copy of the protocol and the managing authority letter with reasons of denial

Support of the Criminal code and residents

Estimated growth of Science Parks number by 2035

BLN RUBLES BLN RUBLES 0 2 13 45 60 65 300 120 Technospark Skolkovo ESTIMATED MOSCOW BUDGET INCOME FROM NEW TERRITORIES 2035 IS ACCOUNED FOR SCIENCE PARKS 2012 2016 2020 2025 2030 2035

126 127 PART 2.10.4 / INFRASTRUCTURE NEW MOSCOW — CITY DESIGNED FOR LIVING

Paris — 30% Social sector London — 28% New York — 21% Singapore — 22% 26% Seoul — 24%

Paris— 18% Manufacturing industry London— 14% New York — 14% Singapore — 25% 25% Seoul — 23% Workplaces created within 5 years

Paris — 22% Consumer market London — 19% New York — 22% Singapore — 12% Seoul — 15%

18% Rostelecom Scherbinsky Elevator Plant TEN Electronics BIOSPARK Tisnum Science Park Rostelecom is a Russian telecommu- One of the main lifting equipment man- Design center which develops elec- Biospark – is the first biological Tisnum Science Park territory has five nication company with government ufacturers that produces the widest tronic devices including ones based laboratory of open type in Russia. manufacturing companies, four of

Paris — 6% involvement. It renders services in variety of elevators and electric lifting on flexible displays by Plastic Logic. There you can order a sophisticated which are located in new production Logistics and communication London — 11% local and long-distant telecommuni- devices in Russia and abroad. The company conducts all design molecular research of any complexity facilities. New York — 13% cation, broadband Internet, interactive and development work during the and get qualitative results in time. Singapore — 15% television, cellular communication, High-technology workplaces crea- creation of end product (development The Science Park offers workplac- Seoul — 13% 16% etc. According to company’s data its tion provides growth of labor produc- of electrical schemes, compilation of The laboratory also has a show- es for professionals with the scope of In addition to presented cases hundreds of companies duly appreciated emerging service is rendered to more than 100 tivity, increases competitiveness not hardware components, packaging and room with equipment made by Belgian competency in engineering, project opportunities of work spaces in New million residents of Russia. only in domestic market, but also on software writing). company – Trinean. This show-room development, model engineering, pro- Moscow and have already transferred the international level and serves as a will soon be expanded with advanced gramming, and also for professionals here their manufactures and offices. About nine thousand workplaces measure of import substitution. One of the few companies in the models of research equipment of in manufacturing process standardi- were created in Comcity in 2016. Rost- world specialized in engineering of other brands. zation, automation and optimization. Financial activity elecom has rented five floors with total flexible electronics. Located in Tech- Paris — 6% London — 11% area of 48 thousand square meters. nospark nanocenter, the company 8% New York — 13% Four and a half thousand employees of works in close cooperation with head- Singapore — 15% various company divisions have moved line players of the market. Requests Seoul — 13% to New Moscow. on solutions development come from Fuel and Energy Complex 4% around the world – from Australia to Western Europe. 3% Construction

Workplaces amount comparison in total structure share

128 129 24,1% Visit New Moscow for business reasons

68,4% Visit New Moscow for personal needs

Today many highly skilled professionals have to travel to the central part of Moscow to work. The newly-created technopolises, hi-tech clusters, science parks and other point objects will allow them to find a job close to their homes.

130 131 NEW MOSCOW — CITY DESIGNED FOR LIVING

Since the attachment of the new territories, Moscow City the same time an advance implementation of the strategic the road from Borovskoe and Kievskoe highways; the interaction between authorities, land owners, businesses and Government has done a great work on the development objectives of New Moscow development is being realized. road from Borovskoe highway to Gorky street. Stage two the public over the past 5 years, efficient mechanisms and and approval of territorial and urban planning and docu- of Kaluzhskoe highway reconstruction has been started. rules of implementation of territory development projects mentation. Transport and engineering infrastructure necessary for Metro stations «Rumyantsevo» and «Salaryevo» were were designed. Today we can certainly say that these actions the construction of real estate is being established at priority opened as well. created a favorable institutional environment necessary for Based on the results of public discussion the territorial rates. A lot of work has been done to improve transport the development of New Moscow in the upcoming years. schemes of Troitsky and Novomoskovsky administrative accessibility of the new territories, the following roads were Over the past years, 537 blocks of flats were built in the areas were approved. New Moscow General Development put into operation: Tsentralnaya street in Kommunarka newly-acquired territories as well as 47 social infrastructure Plan for the period till 2035 and Land Use and Develop- with access to Butovo district; Mamyri – Salaryevo road, facilities, park lands have been equipped. More than 100 ment Regulations, have been developed and approved. At a highway connecting Borovskoe and Kievskoe highway; thousand workplaces have been created. On the basis of

132 133 PART 3 / POLYCENTRISM NEW MOSCOW — CITY DESIGNED FOR LIVING

3.1 Introduction 3.2 Polycentric model formation in New Moscow 3.3 Creation of functional polycenters inside the metropolis 3.4 Daily routine in the polycentric city 3.4.1 View of the residential area

134 135 School Office PART 3.1 / POLYCENTRISM NEW MOSCOW — CITY DESIGNED FOR LIVING

Bank Fuel Station VNUKOVSKOE Fuel Station School Airport Mall Moscow Government’s goal for active ongoing development of new territories requires a review of relations between the center and Hospital Pharmacy the periphery. Market School

Auto-service The need for a more even distribution of workplaces in the devel- Restaurant opment of engineering and transport infrastructure of New Moscow MOSKOVSKY Office needs the formation of a unified model of polycentric development,

Police FILIMONOVSKOE Market relevant for the center and for the attached territories.

Dept Kindergarten Polyclinic Market Station Mall

Colledge Clinic Market Manufacture SOSENSKOE

MARUSHKINSKOE Restaurant Office

Mall Bank

School Station Manufacture

Police

Fuel Station Warehouse Office Carpool

Office Manufacture PERVOMAISKOE Mall Garage Fitness Center

VOSKRESENSKOE Office Mall

Kindergarten Bank Warehouse

Market Station DESENEVSKOE Office

Business Center Bank SCHERBINKA Cinema

Sports school Warehouse Office Supermarket Kindergarten

TROITSK RYAZANOVSKOE Office Bank Police

Parking School Market

NOVOFEDOROVSKOE Hospital Bank KRASNOPAKHORSKOE School Bank

Office

MIKHAILOVO-YARTSEVSKOE

Polyclinic Bank Pharmacy Manufacture Marketplace

Fuel station Depot

Warehouse Office SCHAPOVSKOE Market Clinic Office Manufacture ATM

136 137 Farm PART 3.2 / POLYCENTRISM NEW MOSCOW — CITY DESIGNED FOR LIVING

Polycentric model formation in New Moscow Monocentric model of Moscow Historically developed monocentric model in Moscow has recently been changing to polycentrism due to the efforts of the urban planners and the government, as well as within implementation of the New Moscow project.

Today the traditional model of metropolis with a single Modern metropolises to which the Russian capital belongs social, economic and cultural center of attraction ceased steadily head their development toward polycentrism. to be the only possible one. Taking the world’s experience Within the imple¬mentation of this principle the main focus Polycentric model of New Moscow Polycentric model saves the historical center of the Government of Moscow worded the new principle of is made on the creation of workplaces in the outskirts, the city in the form it exists, but allows reallocating the city development — polycentrism, the essence of construction of hotels and tourist apartment hotels in its traffic flows from the center to other areas. which is the creation of new center of attraction at the center, as well as renovation of the abandoned industrial periphery. areas

138 139 PART 3.3 / POLYCENTRISM NEW MOSCOW — CITY DESIGNED FOR LIVING

Creation of functional polycenters inside the metropolis

One of the key factors of life quality in modern prosperous metropolises 1,5 km is the ability of getting all the neces- sary services near the place of living or work, the absence of necessity of making daily rides to the administrative center of the city and overall minimi- zation of logistic expenses.

In New Moscow it is achieved by the scope of necessary social infra- structure objects in microdistricts, convenient shopping malls, availability of government services through the Microdistrict radius City districts Polycentric links network of modern multifunctional Convenient environment with all Creation of autonomous districts Formation of functional polycentres centers basic infrastructure facilities is with all necessary infrastructure within megalopolis will allow to formed in walking distance within for a comfortable living: residential connect the districts without a the radius of 1.5 kilometers. property, offices, healthcare single centre. This model eliminates facilities, educational institutions circular migration throughout the and objects of culture and day. recreation.

140 141 PART 3.4 / POLYCENTRISM NEW MOSCOW — CITY DESIGNED FOR LIVING

Productive time to the hours spent in traffic ratio 1,5 hours Daily routine Time spent in traffic in the polycentric city Polycentric city Monocentric city

2,5–3 hours Time spent in traffic

365 hours per year

On average, the difference in time that is spent in traffic in the mono- and polycentric cities is more than 1 hour per day. This means that for the year time savings compose 365 hours or 15 days.

7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00

17-00 Video conference in 8-30 13-00 the office Home to office Negotiations in the bicycle ride office 17-30 18-45 20-00 Car service Shopping in the super- 24hrs ATM market 16-00 7-00 9-00 14-00 Business meeting in 18-00 19-00 22-00 a business center Jogging in the park Work in the office or Lunch in a cafe near Kindergarten Training in the Movie premiere in near home in Co-Working the office fitness center the cinema

20-10 Dinner in a nearby restaurant

142 143 PART 3.4.1 / POLYCENTRISM NEW MOSCOW — CITY DESIGNED FOR LIVING

School Transport hub 1,4 km 1,2 km Recreational area with promenade and leisure zones 1,3 km

Cinema 1,0 km

Fitness center Bike trails 0,5 km Office 0,4 km Highway to the city center 0,5 km Банк 0,3 км

Multifunctional center 0,2 km Shopping mall 0,3 km

City Hall 0,2 км

Parking lot 30 m

ПарковкаParking lot 0,25 кмkm

144 145 PART 4 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

4. Introduction 4.1 Growth points of New Moscow 4.2 Urban planning activity centers: Kommunarka case 4.2.1 Project realization using the example of administrative business center in Kommunarka 4.2.2 City environment planning inside residential quarters 4.2.3 Basic principles of urban development formation 4.2.4 Architectural standards 4.2.5 Residential area renovation 4.3 Urban planning activity centers: Rublevo-Arkhangelskoe case 4.4 Urban planning activity centers: Salaryevo case 4.5 Urban planning activity centers: TSKAD (East) case 4.6 Urban planning activity centers: TSKAD (West) case 4.7 Urban planning activity centers: Serednevo case 4.8 Urban planning activity centers: Skolkovo case

146 147 PART 4 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

The «New Moscow» project represents a new approach to the development of a modern metropolis. Any transformation of the territories, from planning to construction, is aimed at creating the best conditions for every citizen. Current and future generations of Moscow citizens will be able to live in a comfortable, reasonably planned city that meets all modern standards of comfort and safety.

The concept involves creation of a small compact pedestrial district, as opposed to automotive suburbs. Any point of attraction — transport stops, stores, hospitals, recreational facilities - should be accesible in a few minutes walking distance. The city, according to the ideologists of the new urbanism, should be available for a person without a car.

Inside this area one can do without a car, at least it could be suc¬cessfully replaced by bicycle. Different parts of the city are easier and faster to reach by means of a high-speed public transport.

148 149 PART 4.1 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

30 3,5 50 107 ROGOVO 90 5,5 AGROCLUSTER 8,0 6,5

VORONOVO CLUSTER KLENOVO KIEVSKY AGROCLUSTER 103 LOGISTICS 130 11,0 CLUSTER 8,0 60 35 8,0 TROITSK 140 INNOVATION-SCIENTIFIC 4,0 185 CLUSTER YARTSEVO 10,0 RYAZANOVO 17,1 MEDICAL CARE CLUSTER HISTORICAL RECREATION SCHAPOVO COMPLEX CLUSTER

VNUKOVO KOMMUNARKA AEROPOLIS MULTI FUNCTIONAL 118 ADVINISTRATIVE 55 BUSINESS CLUSTER 6,1 7,4

MOSRENTGEN MULTI FUNCTIONAL CLUSTER

RUMYANTSEVO SCIENCE PARK

Growth points Sectors of the economy in growth points: Other communal, social and personal services Healthcare and social services The planned number of jobs, thousand Education Public administration and defense; social insurance 35 The total area of real estate Real estate, rent and services Financial activities proposed for construction, of New Moscow 4,0 mln cubic m Transport and communications Hotels and restaurants Wholesale and retail trade; repair of motor vehicles, motorcycles, household Manufacturing goods and personal items Production and distribution of electricity, gas and water Construction

Agriculture, hunting and forestry 150 PART 4.2 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

Urban planning activity centers: Kommunarka case

«BACHURINO» comprehensive development project MLN sq M

School 17,1

TOTAL AMOUNT OF «NOVAYA ZVEZDA» comprehensive CONSTRUCTION development project

MLN sq M Prefecture 9,63 Medical complex with perinatal center RESIDENTIAL PROPERTY CONSTRUCTION

MLN sq M

«BUNINSKIE LUGA» comprehensive development project THOUSAND OF PPL THOUSAND 7,47

NON-RESIDENTIAL PROPERTY CONSTRUCTION

199 185 «YAMONTOVO» comprehensive Comprehensive develop- development project ment project with «Sambo-70» school PROJECTED POPULATION WORKPLACES

152 153 PART 4.2.1 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

The aspect ratio of transport types in passenger traffic structure Project realization using the example of administrative business center in Kommunarka

Public and business zone

46,04% 5,8% «Kommunarka» subway station Mixed public and business Cultural premises Concept of zones of commuting hub premises Troitsky and Novomoskovsky 26,61% 5,44% administrative area Prefect’s office Residential premises Hotels Railroad Bike lane 10,48% 3,43% Educational premises Administrative and business premises Taxi parking School for 1200 pupils Ground 1,53% 0,66% and kindergarten for 200 transport Fostering premises Municipal premises children Pedestrian stop crossing

Library Railway station with covered Hub facility walkway with commercial School for 1200 pupils objects and kindergarten for 200 children

«Stolbovo» subway station Bicycle parking

Residential property and Multiconfessional kindergartens for 310 Interceptive parking Administrative business center (ABC) in Kommunarka religious complex children will be one of the key points of economic growth in the Pedestrian National Research Technological crossing territory of New Moscow. According to the project plan, University MISIS campus Kommunarka center will consist of four main parts: res- Subway exit with covered walkway idential, educational, medical care and administrative. Public and business premises

Road ABC project plan envisages the development of road Multifunctional public transport network connecting the territory to the major and business complex traffic arteries - Kaluzhskoe highway, highways of urban significance «Solntsevo — Butovo — Vidnoe» and «Moscow Ring Road — the village of Kommunarka —«Ostafyevo airport», as well as with Eastern alternative of Kaluzhskoe MLN square METERS highway.

In addition, creation of number of regional impor¬tance «Sosenki» subway station streets is planned as well as the central highway in the village of Kommunarka with the access to Butovo area, road «Kommunarka-Zimenki» as well as road segment KOMMUNARKA 4,82 from M-3 «Ukraine» — the village of Sosenki — the vil- lage of Yamontovo till the «Kommunarka —«Ostafyevo» airport» highway. TOTAL AMOUNT OF CONSTRUCTION IN ABC

154 155 PART 4.2.2 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

City environment planning inside residential quarters

30 MINUTES

Will take to get to Moscow City center by car or public transport

15 MINUTES

Will take to get from home to work, regardless of urban traffic

My new home in ABC residential area

Implementation of integrated territorial development concept provides residents with a number of advantages — modern architectural solutions, improvement of public areas in line with global trends, carefully designed and using the latest research in the field of urbanism, logistics connection inside the area, the availability of infrastructure — healthcare facilities, kindergartens, 5 schools and cultural centres. Homogeneous composition of the residents of these districts will lead to the formation of a favorable social environment and MINUTES will boost social and professional relationships.

Will take to get home from the main infrastructure objests by foot

156 157 PART 4.2.3 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

Basic principles of urban development formation

1 2 3 4 Division into districts Urban environment Complex development Multifunctional • Division of private (courtyard) of human scale • Orientation towards public transport environment formation and public (street) spaces • Comfortable proportions of street • Orientation towards availability within walking • Not more than 60% of one function • Organization of coherent city structure distance and courtyard spaces • Public ground floors • Diversity of architectural solutions • Mixing of functions • Organization of access, solution of domestic needs within own district

5 6 Adherence to principles Public transport of green construction and availability within • Transformation of nature framework into parks walking distance • Adherence of principles of green construction • Subway, railway, LRT/BRT, buses • Availability within walking distance and by bycicle

158 159 PART 4.2.4 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

Architectural standards

New Moscow is changing right in front of our eyes with construction thresholds will decrease from Moscow Ring modernization of public areas, development of infrastruc- Road towards periphery. In addition, a characteristic ture, implementation of ambitious architectural projects feature of a modern approach to residential districts and and creation of workplaces. It is a totally new and unique micro districts design planning in New Moscow is the town in its scale experience for Moscow. It is important for all planning pattern that forms an enclosed perimeter of processes of project implementation to be regulated and district building with utilization of ground floors for neces- for transformations to be harmonic. sary public organizations along main streets and avenues for upgrade of quality of the created city environment. During development of urban planning documentation Developed architectural standards call for improvement Sections of different type Shifted sections placement Level variety of sections Presence of corner sections the territory of New Moscow has been divided into several of aesthetic image of settlements and making the visual arrangement urbanization regions. Number of floors and residential context more homogeneous.

Translucent constructions Minimum level difference between High-grade territory maintenance Well-thought technological solutions Walk-through passages to residential Variety of adjacent sections finishing on ground floors street and functional rooms at the project stage area from the street and from the courtyard

Projects meeting the requirements stated in Resolution №305-PP will be granted benefits for land rental.

Presnya City residential compound

Moscow 40 fl. Ring Road Schapovo Pervomaiskoe Troitsk Desenevskoe Moskovsky Kommunarka Salaryevo Rumyantsevo New Moscow profile 30 fl. One of the principles of city environment and architecture formation comfortable for human is low-rise construction. As can be seen in averaged values of height profile of connected territories it is the closest to the world’s ideal of 5-10 storeys. 25 fl. Salaryevo Park Pozitiv residential compound Government assigned norms in approved Site Plans guarantee the maintaining Novaya Zvezda residential compound Pervi Moskovsky residential compound ZILArt residential of this major asset for future citizens and workers. gorod-park compound Novie Vatutinki residential 20 fl. residential compound Troika residential compound compound Tatyanin Park residential compound Rasskazovo A-101 residential compound 15 fl. residential compound Rogovo Novonikolskoe Pekin’s Gardens residential compound residential compound Yamontovo residential compound Solnechni residential compound 10 fl.

Metropolis residential compound Akvarel’ Andersen residential compound 5 fl. residential compound

Grafskie ponds residential compound

160 161 PART 4.2.5 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

Residential area renovation

Qualitative changes of this program from the previous one launched in 1998 in «old» Moscow are: relocation only in own district, new apartment size is bigger than of demolished ones, improved finishing of comfort class, possibility of inclusion of shared accommodations and dormitories into the program, consideration of tenants’ opinions and voting on every house, as- sistance in relocation, possibility of rejection of relocation at every stage, Houses can be additionally strict requirements for new houses construction and district formation. included according to the resuls of current residents’ voting Modernization of residential areas of New Moscow will be Renovation of residential area means the process of conducted in terms of centralized renovation program substitution and reconstruction of residential area ele- of the city of Moscow. Preferred variant will be district ments (residential units and its’ parts) abandoned in the migration. result of functional and physical deterioration with new elements and objects. Such scheme will allow people, moved to the new accommodation, to save the opportunity of daily com- Renovation of residential area is a circular process munication with friends who will be still living nearby. The that generally includes the succession of residential basic premise of the city is to relocate citizens to new unit transformation and methods of renovation: the new districts, provided with all necessary infrastructures – construction, refurbishment, modernization, restoration, social and transport. reconstruction, residential units demolition and erection of new objects.

HOUSES INCLUDED INTO THE FIRST ROW OF TINAO RENOVATION PROGRAM VOTING

I can assure you that against peoples’ will their houses won’t be included in renovation program. And on the contrary if the house technical condition fits requirements of the program and tenants Application of participation in Voting of house tenants on «Active Approval of participation in the Inclusion in renovation program want to participate, they are free to enter residential renovation program citizen» portal or in multifunctional program of not less than 2/3 of center «My Documents» or during apartments in the house general tenant meeting Dmitry Vladimirovich Nabokin, Praefect of TINAO, at the weekly meeting on renovation program with district citizens

162 163 PART 4.3 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

Urban planning activity centers:

Rublevo-Arkhangelskoe case Shooping center

MLN sq M The environment, attracting professionals from around the globe, is being created in Ru- Financial center blevo-Arkhangelskoe. It is a joint area uniting financial as well as consulting, legal, audit and other companies. Office buildings with associat- ed infrastructure for meetings and negotiations 4,11 are located within the walking distance from each other that allows optimization of everyday communication. TOTAL AMOUNT OF CONSTRUCTION Residential districts’ planning was based upon principles of human scale comfortable environment, gradation of city space to private courtyards, where neighbors know each other, and streets filled with various public functions. MLN sq M 2,63

RESIDENTIAL PROPERTY CONSTRUCTION

«RUBLEVO» comprehensive development project MLN sq M

THOUSAND OF PPL THOUSAND 1,48

Park territory NON-RESIDENTIAL PROPERTY 66,5 76,3 CONSTRUCTION

PROJECTED POPULATION WORKPLACES

164 165 PART 4.4 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

Urban planning activity centers: Salaryevo case

MLN sq M Salaryevo is the multifunctional terri- tory represented by office, residential, trade and manufacturing districts. It is Administrative and busi- Hub / bus terminal Trade and manufac- also planned to locate a big transport ness area turing area interchange hub that allows comfort- able transport type changes between 6,75 subway, bus or personal car.

TOTAL AMOUNT OF CONSTRUCTION

MLN sq M 3,0

RESIDENTIAL PROPERTY CONSTRUCTION

Comprehensive residential development MLN sq M

THOUSAND OF PPL THOUSAND 3,75

NON-RESIDENTIAL PROPERTY CONSTRUCTION

Comprehensive residential 69,7 98,9 development

PROJECTED POPULATION WORKPLACES

166 167 PART 4.5 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

Urban planning activity centers: TSKAD (East) case

MLN sq M Residential development Manufacturing complex 3,27

TOTAL AMOUNT OF CONSTRUCTION The section of the TSKAD held on the territory of New Moscow

MLN sq M 1,87

RESIDENTIAL PROPERTY CONSTRUCTION

Science Park

Logistic center

Commercial and manufactur- ing complex MLN sq M

THOUSAND OF PPL THOUSAND 1,40 In the eastern part of the functional planning establishment adjacent to the Central Ring Road the key role is given to the organization of NON-RESIDENTIAL PROPERTY workplaces in manufacturing and storage sector. Several industrial CONSTRUCTION parks providing comfortable working conditions for manufactures 11,6 44,4 of small and medium enterprises are meant to be built.

PROJECTED POPULATION WORKPLACES

168 169 PART 4.6 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

Urban planning activity centers: TSKAD (West) case

Logistic center MLN sq M Science Park

Residential development 2,38

TOTAL AMOUNT OF The section of the TSKAD held CONSTRUCTION on the territory of New Moscow

MLN sq M 1,08 Trade and manufacturing area RESIDENTIAL PROPERTY CONSTRUCTION

MLN sq M

Manufacturing and storage complex THOUSAND OF PPL THOUSAND 1,10 In the western part of the functional planning establishment adjacent to the Central Ring Road the key role is given to the organization NON-RESIDENTIAL PROPERTY of workplaces in trade and exhibition, and manufacturing sectors. CONSTRUCTION Several Science Parks providing comfortable conditions for B2B 9,10 34,7 sales are meant to be built.

PROJECTED POPULATION WORKPLACES

170 171 PART 4.7 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

Urban planning activity centers: Serednevo case

MLN sq M

Comprehensive development project 2,27

TOTAL AMOUNT OF CONSTRUCTION

Technopolice MLN sq M Design and manufacture of new transport types

Technopolice 1,35 Design and manufacture in energy saving sphere RESIDENTIAL PROPERTY CONSTRUCTION

Technopolice Design and manufacture of new materials MLN sq M

THOUSAND OF PPL THOUSAND 0,92 Serednevo micro-district is a modern micro-district designed with respect to provision of social and recreational infrastructure of its NON-RESIDENTIAL PROPERTY own and adjacent territories. Apart from residential micro-districts CONSTRUCTION three technopolises are supposed to be organized. High-technology 30,1 26,1 workspaces in energy saving, designing and manufacturing of new materials and transport types will be created there.

PROJECTED POPULATION WORKPLACES

172 173 PART 4.8 / FROM URBANIZATION CENTERS TO CITIZENS NEW MOSCOW — CITY DESIGNED FOR LIVING

Urban planning activity centers: Skolkovo case

SkolTech MLN sq M

Transport hub 2,55

TOTAL AMOUNT OF CONSTRUCTION Plato IFC

MLN sq M 0,75

RESIDENTIAL PROPERTY CONSTRUCTION

Sberbank Science Park MLN sq M

THOUSAND OF PPL THOUSAND Skolkovo Innovation Center — a contemporary science and technol- 1,78 ogy innovation complex of development and commercialization of IT Cluster new technologies, is being built in Moscow. It is the first Science City built from scratch during post-Soviet time. The complex will provide NON-RESIDENTIAL PROPERTY special economic conditions for companies working in top-priority CONSTRUCTION fields of Russian economy modernization: telecommunication and 19,2 24,6 space, biomedical technologies, energy efficiency, information technologies and also nuclear technologies.

PROJECTED POPULATION WORKPLACES

174 175 What kind functions should TINAO territory fulfill according to Moscow citizens?

9% Administration, location of government authorities

37% Location of educational and science institutions

28% Comfortable life in individual houses close to nature

22% 28% Organization Construction of of manufactures residential micro-districts

One of the main conditions for the new territory integration to Moscow and its further development is balanced distribution of various functional zones in settlements based on real demands of people and promising economic agenda.

176 177 PART 5 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

5.1 New Moscow — new history 5.2 Private opinions 5.3 Objects implemented over the last 5 years 5.6 Project participants 5.5 Instagram: #НОВАЯМОСКВА 5.6 Contact details

Integration with Moscow has opened up grand opportunities for the new territory. Together with citizens we will make New Moscow comfortable for life and work...

Sergey Sobyanin Mayor of Moscow

178 179 PART 5.1 / INFORMATION

New Moscow – January 20 Opening of the station «Rumyantsevo» by the Mayor of the city Sergey Sobyanin. new history The station «Rumyantsevo» of the Moscow January Metro was opened, it became the first station in Highway crossing in Scherbinka over the the territory of New Moscow. It is situated on the Kursk direction railroad has been put into first line of the Metro — Sokolnicheskaya. operation. August 1 May 21 March 19 The first million of square meters of housing was Opening of the first turn of the business park «K2» in New Moscow in the village of Nikolo-Khovanskoe. The Mayor of Moscow Sergey Sobyanin intro- commissioned in New Moscow. Sergey Sobyanin visited the first international office center of A duced to the Moscow City Duma a package of The first million of square meters of housing was commissioned class — «K2» business park in the territory of Troitsky and Novo- September bills that determined the administrative and from the moment of attaching new territories to Moscow. One moskovsky administrative areas. territorial structure of the new territories of fourth of the first million of square meters are the houses of low- The beginning of implementation January 1 rise and individual housing construction. Moscow after its expansion since July 1, 2012. of medical complex project in More than 100 thousand new workplaces Kommunarka. have been created. December 31 August 20 July 1 End of construction and commissioning April 17 The Prime Minister of the Russian Federation of the first subway stations in New Dmitriy Medvedev took part in the opening of Opening of the road Kommunarka — Butovo December 7 in New Moscow. Moscow. Chelyshev Aleksey Valentinovich September 5 the first turn of the COMCITY office park. Decision on Expanding the Territory of Moscow. The construction of the subway stations was appointed as a prefect of the two new Commissioning of the first office park of such scale The Mayor of Moscow Sergey Sobyanin opened a new road The international jury took the decision in the «Rumyantsevo» and «Salaryevo» was finished. The Moscow City Duma adopted a Resolution «On areas of Moscow — Troitsky and Novo- and level in Russia. The Prime Minister Dmitriy Med- that connected the village of Kommunarka with the area of competition of developing a concept of the May 25 The commissioning of the stations was Approval of the Agreement on Changing the Border be- moskovsky, that were created later on vedev noted, that COMCITY had become an example Yuzhnoe Butovo, 6 km. in length. Moscow agglomeration. performed. The Deputy Mayor of Moscow March tween the Constituent Entities of the Russian Federation: July 1, 2012 during the implementation of Four module clinics were simultaneously con- of the city-in-city format that is new for Russia. checked the readiness of Moscow City and Moscow Region». The corresponding the project of Moscow expansion. During The winner in two categories «Moscow Agglomeration structed and commissioned in the territory of New Moscow City Land Use and the stations in the territory of New Moscow. Resolution was approved on December 7, 2011 by the the transition period these two areas were Development» and «Big Moscow Development» became Moscow during half a year from extra- budgetary Development Regulation and the Moscow Region Duma. to be governed by one prefecture a French and Russian team Grumbach Wilmotte resources. General Plan have been approved. 2011 2012 2013 2014 2015 2016 2017

December 27 November February 9 August 18 December July 1

The Federation Council approved «Agree- Since November 2013 by the Order of Sergei Sobyanin opened a Two facilities of New Moscow became The authorities of Moscow approved the 47 new social objets have been built. ment on Changing the Border between the the Mayor of Moscow Nabokin Dmitriy modern kindergarten in Troitsk. the finalists of the contest the «Best territorial scheme of development of Troitsky Constituent Entities of the Russian Feder- Vladimirovich was appointed as the prefect A new two-storey building of a Completed Project of 2014 in the field of and Novomoskovsky administrative areas. construction». ation: Moscow City and Moscow Region». of Troitsky and Novomoskovsky preschool institution for 125 children In the territory of New Moscow more than 700 km of 148 thousand hectares of territory were administrative areas of Moscow City. with an area of 3.5 thousand square The Mayor of Moscow Sergey Sobyanin handed roads and 45 km. of Metro lines will be built. By 2025 included into Moscow. meters constructed under an the awards for the «Best Completed Project they plan to build 55.9 mln square meters of real es- individual project in the neighborhood of Construction of Multi-Family Dwellings of tate for various purposes in Troitsky and Novomosk- of Solnechny. Enhanced Comfort» to «Troitsk Construction ovsky administrative areas, including in the territory Company» for the residential complex of Novomoskovsky administrative area — 34.7 mln May 22 «Solnechny», and to «Antemona Limited» for the square meters, and in Troitsky administrative area — best completed project of construction of office 21.2 mln square meters. It is also supposed that by By the Decision of the Government of Moscow the buildings for Comcity office park. 2035 1.5 mln people will live and 1 mln workplaces will February 15 Department for the Development of New Territories August 7 be created in Troitsky and Novomoskovsky adminis- Opening of the anniversary 200th station of Moscow was created. It was headed by Zhidkin trative areas. of the «Salaryevo». Vladimir Fyodorovich. (Resolution No. 239-PP of the Opening of a road between Kievskoe It is located beyond the Moscow Ring Road between Government of Moscow) and Borovsky highways. The Mayor of Moscow Sergey Sobyanin traffic on the Kievskoe highway and the village of Salaryevo. reconstructed road with a length of 2.9 km. between Kievskoe and Borovskoe highways

180 181 NEW MOSCOW — CITY DESIGNED FOR LIVING

2035

MILLION MILLION MILLION sq METERS 1,5 1 100

NEW RESIDENTS ADDITIONAL NEW OBJECTS OF WORKPLACES CONSTRUCTION

182 183 PART 5.2 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

14 private stories about New Moscow

Private Opinions

The «New Moscow» project has already entered into the lives of hundred thousands of people bringing additional opportunities

184 185 PART 5.2 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

The main challenge for the developers set This year, the capital investment of MUPGC by the Government of Moscow was complex de- into the development and reconstruction of power velopment of new territories. It does not mean grid facilities of New Moscow will amount to more only housing construction in the open fields, but than 1.6 billion roubles. arrangement of a proper comfortable living en- Within the investment program MUPGC will vironment with workplaces, social facilities, park reconstruct 14 high-voltage substations (SS). lands and commercial facilities. The implemented complex measures are Furthermore,therequirementstothe construc- aimed to increase the reliability and quality of tion of these facilities are not lower than those for consumers’ electric supply, putting into operation the Moscow ones. As a result — many residents new facilities due to high rate of construction of old areas of the capital moved to New Moscow. and development prospects of New Moscow Over the past three years the population of this territories. territory has grown by more than one third.

Evgeniy Golubchenko Marina Rezvova Director of «New Moscow» MUPGC Subsidiary Deputy General Director of «Krost» Concern

1 2

184 185 PART 5.2 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

To implement ambitious programmes of social One cannot help being happy about the fact sphere upgrading we lacked only one thing — that together with intensive housing construction a clear plan: where to construct, how much to in New Moscow a great number of commercial construct, and to what extent. Indeed such facil- facilities is created. ities as schools, kindergartens and other social Car service centres, shopping centres, clinics facilities are closely bound with the population and schools, business centres — it all gives peo- and utility line diagrams. ple of different specializations a chance to find a Now we have such document — it is the Gen- well-paid job to their liking. Moreover not far from eral Plan of Moscow. For three years hundreds of their place of living. experts have been making calculations on how For three years the number of people em- the demographic and economic processes will ployed in New Moscow has doubled. The employ- develop in New Moscow. And now, thanks to these ment departments of the State Public Institution calculations, we have exact figures of demand of «Employment Centre» of Troitsky and Novomosk- each settlement for any given facilities. ovsky administrative areas strive to assist people in this issue with maximum quickness and quality: 20 employment minifairs and 7 free seminars will be held for the residents desiring to set up their Dmitriy Nabokin Prefect of Troitsky and Novomoskovsky administrative areas own business.

Yury Lebed Director of Employment Centre of Troistky and Novomoskovsky administrative areas

3 4

184 185 PART 5.2 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

Opening of a wholesale food centre FOOD In May 2005, Systematika Group of Compa- CITY has given me an opportunity to do business nies has successfully finished its moving into the in an absolutely new way. A class Comcity office park . Now all the compa- nies belonging to Systematika Group are united I buy high-qulity vegetables and fruits by in one office area. small lots at rather reasonable prices there and sell them in my three outlets in New Moscow. Joining of all employees of the group gives us additional opportunities for impementation of An excellent access, goods quality, practice ambitious projects. We are sure that in near future of business relations with partners — everything the leading IT teams will gather in Comcity office is up to the mark. My buyers are satisfied, I am park; and the consolidation of the best special- going to expand my business. ists will help the development of the innovation technologies of the country.

Nikolay Krivosheev Entrepreneur Andrey Kudryavtsev Executive Vice President of GCS

5 6

184 185 PART 5.2 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

A year ago a road from Kommunarka to We, the residents of the gardeners’ non- Yuzhnoe Butovo was opened after reconstruction. commercial partnership «Scherbinka-2», deci- A modern motorway connected New Moscow and ded to sign the property of the power grid off to the area of Yuznoe Butovo. It is now very conven- MUPGC, PJSC that is the owner of the power grid ient for us, elderly people, to get there to solve in Troitsky and Novomoskovsky administrative pension issues, visit a clinic. areas. There is a subsidiary of this enterprise operating in our area. And many issues of tech- Bus service is perfect. And it is twice quicker. nological connection to and maintenance of the For all residents of the new neighbourhoods it is power grid ceased to be a problem. very good to reach a in somewhat 15 minutes. We could only dream of such transport Power supply became reliable and uninter- availability earlier. ruptible thanks to the power engineers. But it is not the only thing we benefitted from attaching So we feel the advantages of attaching to new territories to Moscow. the big Moscow. I wish they would build Metro to Kommunarka. We are looking forward to it. By 2035 as we know the whole system of public utilities of New Moscow will have become modern and provided convenient and comfortable life for the families living in the houses of private Ivan Grigoryevich Nikonov housing construction. Veteran of labour, settlement of Kommunarka

Evgeniy Chubarov Gardeners’ Non-Commercial Partnership «Scherbinka-2»

7 8

184 185 PART 5.2 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

Here in Scherbinka we create conditions for As a mother of two children I am happy that all- round children development. For example many kindergartens are constructed in New recently a long awaited children and youth cen- Moscow. They are nice, cozy, different from each tre has opened. Here future talented actors and another, they are equipped with swimming pools actresses are born to the delight of parents. and everything necessary for children and per- sonnel. Unfortunately, I could not manage to send There has already been a premiere in the Chil- my elder son to the kindergarten, our turn hasn’t dren’s Drama Theatre «Sfera» staging «A Crystal come yet, and this autumn he will go to school. Shoe». Small actors and theatre visitors were excited. New interesting performances and new But my younger son Georgiy is lucky, next meetings are waiting ahead. year he will surely go to the kindergarten: the authorities of Moscow undertook to construct a kindergarten for 125 children in our locality of Mosrentgen this year. It means my child will go Tatyana Sychyova there and my husband and I will be able to work. Children and Youth Centre Deputy Director

Tatyana Kryukova A mother of two children, locality of Mosrentgen

9 10

184 185 PART 5.2 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

After attaching to the Big Moscow we, the I have read about New Moscow, even seen residents of the settlement of Marushkinskoe, an interesting program on TV. But as they say a soon felt the changes. picture is worth a thousand words... So, at the first opportunity when I was on a business trip The problem of water quality was serious. I visited Rumyantsevo, Voronovo, Kommunarka. Harmful impurity was twice or even three times I was impressed by the scale of construction of higher than the normal level. And we have children. houses, office and other buildings designated for We even had to address the Mayor. creating workplaces. There was a prompt reply to our request: I think I will be able to find a job as a program- the water supply has already been laid along the mer and my wife, she is a designer, will also be able Borovsky highway. As the city authorities assured to get a job. For example I liked Comsity office the works will soon be over. The water here will be centre very much. And it is very important that pure and healthy. We are very grateful for this. the Metro is nearby. I consider that New Moscow is a prospective territory, the area where you can make your dreams come true and apply your skills. Vladimir Andreev A resident of the settlement of Marushkinskoe

Viktor Ignatyev A tourist from Sverdlovsk Region

11 12

184 185 PART 5.2 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

I attentively trace the development of the In May, a new football field with synthetic new territories attached to Moscow in 2012. I am grass was opened in the territory of Voronovo glad that in the neighbouring region this process Sport Complex. It will allow having classes and comprises the essential aspects of living: modern trainings not only in summer, but also in spring and comfortable housing, social facilities — schools, autumn. The field is equipped with an electronic kindergartens, clinics are constructed, workplac- scoreboard and benches for the supporters. es, road and transport infrastructure are created. In near future lighting will be installed, it will Some of my aquaitances already think of allow the guys to practice in the evening. moving for permanent residence to New Moscow.

Aleksey Volodin Sergey Erofeev Director of Voronovo Sport Complex Kaluga Region

13 14

184 185 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

Objects MILLION sq METERS implemented over the last 5 years 11

OF RESIDENTIAL AND COMMERCIAL PROPERTY As of now, millions of square meters of modern socially significant objects have been constructed in New Moscow. Each project rep- resents a unique ar¬chitectural and functional solution and sets a real example of comfort for all cities of Russia. 4

ROADS

47 «SOLNECHNY» RESIDENTIAL COMPLEX A housing complex of mid-estate residential development. Houses of the complex match the existing wooden landscape with the pedestrian area. SOCIAL INFRASTRUCTURE Troitsk City OBJECTS 5

PARKS 2 SCHOOL NO. 1392 NAMED AFTER D.V. RYABINKIN «PEREDELKINO BLIZHNEE» RESIDENTIAL COMPLEX «NOVYE VATUTINKI» RESIDENTIAL COMPLEX AND CLINIC One of the most advanced schools of Russia for 1100 pupils. SUBWAY Large-scale project with a multi- functional infrastructure. It includes more than a doz- Clinic for 550 visits per shift. Desenovskoe settlement en of child care institutions, hospitals and clinics, a sports stadium and other objects. Desenovskoe settlement, near the village of Desna STATIONS Vnukovskoe settlement, Rasskazovka village

186 187 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

«YAKOVLEVSKOE» PARK A sport and entertainment park. A picturesque pine-tree forest creates a wall along its borders. The park is named after the forest. Novofyodorovskoe settlement, Yakovlevskoe village

«K-2» BUSINEES PARK A business park in the village of Sosenskoe that will provide workplaces for 6 thousand people

«EDALGO» RESIDENTIAL COMPOUND Residential Complex of business class for 1747 flats. Sosenskoe settlement, Kommunarka village

188 189 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

190 191 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

«YUZHNY» NEIGHBOURHOOD One of neighborhoods of the big project «Novye Vatutinki» that became an example of the complex development of the territory. Desenovskoe settlement

«IZUMRUDNY» COTTAGE VILLAGE Low-rise development with a total area of 20 ha, including cottages, «GARDEN PARK EDALGO» town houses, multi-family dwellings. A developed infrastructure: RESIDENTIAL COMPOUND a shopping centre, a kindergarten and recreational areas. A residential complex City of Troitsk of business class. Kommunarka village

192 193 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

«BUNINSKUE LUGA» RESIDENTIAL COMPOUND FOODCITY The compound of comfort class includet into complex development of Buninsky neighborhood. The largest wholesale and retail complex in the Several modern residential buildings will be included into the complex. country for selling vegetables and fruits. Sosenskoe settlement Sosenskoe settlement

«KRASNAYA PAKHRA» PARK The first of the modern parks of New Moscow. The project provides for the further equipment and expansion of the park up to 9.8 ha. Krasnopakhorskoe settlement

194 195 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

196 197 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

BOROVSKOE HIGHWAY — KIEVSKOE HIGHWAY ROAD Connects Borovskoe and Kievskoe highways, goes from the village of Rasskazovka to the town of Moskovskiy.

KOMMUNARKA — BUTOVO ROAD The central road in the village of Kommunarka going to the area of Butovo

KIEVSKOE HIGHWAY — KALUZHSKOE HIGHWAY ROAD Road from Kievskoe highway to Kaluzhskoe highway through the village of Salaryevo to the village of Mamyri.

198 199 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

200 201 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

PRESCHOOL GENERAL EDUCATIONAL INSTITUTION FOR 290 CHILDREN «Buninskii» neighborhood, Sosenskoe settlement

ADMINISTRATIVE AND SHOPPING COMPLEX An administrative and shopping as well as production and warehouse complex. Moskovsky settlement, Lapshinka village

«GAZTECHNOPARK» BUSINESS CENTER PRESCHOOL GENERAL EDUCATIONAL A business center having the area of 21.5 thousand square meters. There will be production, INSTITUTION FOR 250 CHILDREN administrative, warehouse and shopping areas, as well as areas of social nature. «Pervy Moskovsky gorod park» residential compound, Sosenskoe settlement, Gazoprovod village Moskovsky settlement

202 203 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

«ECOPARK GORCHAKOVO» RESIDENTIAL COMPOUND 18 three-, four- and five-storey dwelling houses. The total area of the development is 64 thousand square meters. Pervomayskoe settlement

ZAPADNAYA DOLINA The concept of the Architectural Suburb «Zapadnaya Dolina» provides for the construction of cottages, town houses, and flats, as well as office areas, public and recreational areas. Marushkinskoe settlement

«ANDERSEN» RESIDENTIAL COMPOUND A project of integrated development of the territory «NIKOLIN PARK» RESIDENTIAL COMPOUND with its own recreational area. The total area of the The complex includes 11 dwelling houses of various number of floors (from 5 to 9 floors), development is 19.6 ha. a kindergarten with a swimming pool, tennis court and other infrastructure. Desenovskoe settlement Sosenskoe settlement

204 205 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

«VYAZEMSKOE» TOWN HOUSE BLOCK More than 50 semi-detached houses near a forest and a river in the nearest to Moscow Ring Road territory of New Moscow. Sosenskoe settlement

«BUTOVSKIE ALLEI» NEIGHBOURHOOD 29 three-storey comfortable houses constructed under an individual architectural project, joined into 4 blocks and surrounded with a complete infrastructure complex. Sosenskoe settlement, Stolbovo village

206 207 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

«KIEVSKOE - 22» LOGISTICS CENTER The first unique warehouse facility in New Moscow. The total area of the complex is 114 thousand square meters. Pervomayskoe settlement

SCHOOL FOR 1375 PUPILS «Pervy Moskovsky gorod park» residential compound,

Moskovsky settlement

208 209 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

«LEGENDA 18» RESIDENTIAL COMPOUND The project with «vertical city» concept — first floors of the massive building will have parking lot and social objects, including the park on the roof of the parking lot Kommunarka village

«G10» BUSINESS PARK «G10» business park is projected to occupy 230 thousand square meters. in addition it is planned to build a hotel complex and rooms for conferences, negotiations and business meetings Mosrentgen settlement

DUBROVKA FITNESS The center of attraction for many sport lovers. Dubrovka has the most advanced equipment and located in the residential compound of the same name Sosenki settlement

210 211 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

212 213 PART 5.3 / INFORMATION 215 NEW MOSCOW — CITY DESIGNED FOR LIVING

«SALARYEVO» SUBWAY STATION The anniversary 200th station of the Moscow Metro opened on 15 February 2016.

«RUMYANTSEVO» SUBWAY STATION CONSTRUCTION OF PERSPECTIVE SUBWAY STATIONS The station is located in the Sokolniki line between the stations «Troparevo» and «Salaryevo». In total, it is planned to build about 65 kilometers of new metro lines in the territories Already carries more than 26 thousand people per day. attached to Moscow by 2035. In addition to the construction sites of Sokolniki and Kalininsko-Solntsevskaya lines, the possibility of building a new line from the station «Ulitsa Novatorov» of Third interchange circuit to the administrative and business center in Kommunarka is examined.

214 215 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

216 217 PART 5.3 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

COMCITY A-class office park with total area of 430,000 square meters, has become the headquarters for many leading Russian companies Moskovsky settlement

218 219 PART 5.4 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

«MIC» GROUP • PPF REAL ESTATE RUSSIA • «SLAVYANSKIY MIR» GROUP • CJSC «MIG» • «STORM PROPERTIES» LLC • CJSC «KIEVSKAYA PLOSHCHAD» • JSC «А-101 DEVELOPMENT»

CONCERN «KROST» • «LAND-YUG» LLC • GK «ABSOLUT» • «MORTON» GROUP • «PIK» GROUP • «MOSKOVSKAYA INZHENERNO-STROITELNAYA KOMPANIYA (MISK)» LLC

«INVESTTRUST» LLC • RDI GROUP • «IMPERIAL TRUST» LLC • CJSC «RUBLEVO-ARKHANGELSKOYE» • CJSC «EXPOCENTRE» • CONSTANTA MANAGEMENT COMPANY

HINES INTERNATIONAL • «INGRAD» LLC • « SU-155» GROUP ОJSC «SBERBANK RUSSIA» • STATE CORPORATION «BANK FOR DEVELOPMENT AND FOREIGN ECONOMIC

AFFAIRS (VNESHECONOMBANK)» • «KUZNETSKOVSKIY KOMBINAT» LLC • ОJSC «KOMKOR» • «ALLIANCEINVESTSTROY» LLC • SISTEMATIKA GROUP • «OSTAFYEVO»

INTERNATIONAL AIRPORT • «VNUKOVO» INTERNATIONAL AIRPORT • OJSC «ROSTELECOM» • PJSC «GAZPROM» • ORACLE CORPORATION LLC • «RUSAL» CJSC

«YAZOVSKAYA SLOBODA INVEST» • «POLIR-М» LLC • «PHARMSTANDARD» LLC • PROJECT INSTITUTE «VLADIMIRAVTODORPROEKT» LLC • «ALLTECH DEVELOPMENT» LLC

BORK COMMUNICATION GROUP • MR GROUP • «INSTITUTE «KANALSTROYPROEKT» LLC • OJSC «MOSCOW CITY TELEPHONE NETWORK (MGTS)» • RUSSIAN HOUSING

DEVELOPMENT FOUNDATION • ОJSC «RUSSIAN RAILWAYS» • CJSC «GRADPROEKT» • IKEA«TRANSTROYINVEST» LLC • OJSC «MOEK» • ОJSC «MOESK» • OJSC «SO-UPS»

OJSC «ROSSETI» • OJSC «FGC UES (FEDERAL GRID COMPANY OF UNIFIED ENERGY SYSTEM)» • JSC «MOSVODOKANAL» • NAMIKS • «MANGAZEYA DEVELOPMENT» LLC

«AGROKOMBINAT MOSKOVSKIY» LLC • I-TECO COMPANY • «RUSFISHWORLD» LLC • BOSTON CONSULTING GROUP • «MOSP» LLC • «TERIBERSKIY BEREG» LLC

«BRISTOL» GROUP • «STRELKA» INSTITUTE • THE MOSCOW TIMES • OJSC «MOSPROEKT–3» • «STROITEL +» LLC • CJSC «WURTH RUS» • CJSC «PROMGP»

«JILSTROY» LLC • «KORTROS» GROUP • «GEMAINVEST» • SEZAR GROUP • «VECTOR INVESTMENTS» LLC • «FRIZ-INVEST» • X5 RETAIL GROUP • «MCKINSEY &

COMPANY» • LSR GROUP • «INZHKOMPROEKT» • NATIONAL UNIVERSITY OF SCIENCE AND TECHNOLOGY • «MISIS»ROSAVTODOR STATE COMPANY • RUSSIAN

STATE LIBRARY • OJSC «ACRON» • OJSC «VTB BANK» • «VELES DEVELOPMENT» LLC • «MIELE» GROUP • «RENOVA» GROUP • «GVSU «CENTRE» • «PROJECT

2018» LLC • «VTM-DORPROEKT» LLC • «AUTORUS» LLC • «INSTITUTE «KANALSTROYPROEKT» «MAXIFLORA» LLC • «BALSTROYRESURS» LLC • «A.A. CHERNIKHOV

ARCHITECTURAL DESIGN WORKSHOP» LLC • «TPO «RESERVE» • SERGEY TKACHENKO ARCHITECTURAL WORKSHOP BUREAU • URBAN DESIGN ASSOCIATES

— PITSBURG (USA) • OJSC «MOSINZHPROEKT» • STUDIO ASSOCIATO SECCHI –VIGANÒ – MILAN (ITALY) • «ARCHITECTURAL BUREAU OSTOZHENKA» • RUSSIAN

ACADEMY OF ARCHITECTURE AND CONSTRUCTION SCIENCES (RAACS) • ОМА GROUP (THE NETHERLANDS) • ANTOINE GRUMBACHET ASSOCIES (FRANCE

ГРУППА L’AUC (FRANCE) • ГРУППА RICARDO BOFILL (SPAIN) • DAILY BUSINESS NEWSPAPER «KOMMERSANT» • DAILY NEWSPAPER «IZVESTIYA» • NEWSPAPER «TRUD»

DAILY BUSINESS NEWSPAPER «VEDOMOSTI» • NEWSPAPER «VECHERNYAYA MOSKVA» • NEWSPAPER «KOMSOMOLSKAYA PRAVDA» • NEWSPAPER «GAZETA.RU»

NEWSPAPER «MOSKOVSKAYA PERSPEKTIVA» • MAGAZINE «CAPITAL STYLE» • «STABLE» LLC • «OPIN» DEVELOPMENT GROUP • STROYINVESTTOPAZ • AND OTHERS

220 221 PART 5.5 / INFORMATION NEW MOSCOW — CITY DESIGNED FOR LIVING

Instagram users’ photos with hashtag #новаямосква 222 223 PART 5.6 / INFORMATION

Contact details

DEPARTMENT FOR THE DEVELOPMENT OF NEW TERRITORIES OF MOSCOW

Vozdvizhenka street 8/1, building 1, Moscow City (m. , m. Arbatskaya, m. Borovitskaya)

Fax: +7 (495) 957-93-01 Website: http://drnt.mos.ru E-mail: [email protected] Design and production: www.videinfra.com production: and Design

224

DEPARTMENT FOR THE DEVELOPMENT OF NEW TERRITORIES OF MOSCOW