Infrastructure

Quarterly Infrastructure Program (Aug 2020 – Oct 2020)

Please note that this program is subject to change without notice

WORKS BRANCH

Road Construction

Name Description Expected Expected Start Completion Date Date Alford Street Carpark, Rehabilitation of carpark. Jul Oct Bunya Mountains Car Park Widening existing road to allow for Oct Nov Upgrade pedestrian access, upgrade of current footpaths and carpark.

Dingo Creek Car Park, Upgrade carpark to bitumen seal standard Sep Oct

Hood Street, Kerb and Channel upgrade. Sep Sep

Nanango State School Pedestrian facilities upgrade. Oct Oct

Niagara Road Flood damage repairs and road Sep May 2021 reconstruction.

Peterson Drive, Kingaroy Widening existing sealed road near Oct Jan 2021 Sommerfelds Lane.

Gravel Resheeting & Heavy Formation Grading

Name Description Expected Expected Start Date Completi on Date Burra Burri Road Gravel Resheet Jul Sep Franklins Road Gravel Resheet & Flood Damage Jul Sep Friebergs Road Gravel Resheet, Flood Damage & Drainage Jul Aug Glenmore Road Gravel Resheet & Flood Damage Aug Sep

Maidenwell Upper Gravel Resheet Oct Oct Yarraman Road Reedy Creek Road Gravel Resheet Oct Nov Ryan Reagon Road Gravel Resheet Oct Nov

Page 1 of 4 Silverleaf Road Shoulder Grading Aug Aug

Patrol Grading

Locality Description Expected Expected Start Completion Date Date Alice Creek Alice Creek Road, Williams Road, Barbours Aug Aug Road, Tuites Road, Clarks Road, Dascombes Road, Parkers Road, Ellesmere Road Ballogie Barret Road, Lewis Duff Roads Oct Oct

Benarkin North Bradley Road Sep Sep

Williams Road Oct Oct Blackbutt Margaret Street, Haynes Kite Miller Road, Sep Sep Langton Road, Gibson Road Googa Creek Road, Ogilvie Road Sep Sep

Ness Wilson Road Oct Oct Booie Booie Crawford Road Sep Sep

Radunzs Road, Mt Hope Road, Perret Road, Oct Oct Nystrom Road, Reinbotts Road, Haydens road, Jorgensens Road, Millards Road. Redvale Road, Schellbachs Road, Haydens Road, Birt Road, Millers Road, Karingal Road, McAuliffes Road Manar Road, Jerrards Road, Slacks Road, Aug Aug Allies Creek Road, Krugers Road, Quiet Glenn Road, Seilers Lane, Coes Boundary Road Brooklands Brooklands Peron Road, Greenslade Road Aug Aug

Charlestown Old Wondai Road, Bessons Road Sep Sep

Coolabunia Wiedens Road, Franklins Road Sep Sep

Corndale Childs Road, McLennans Road Oct Oct

Coverty K Duff Road, Wolf Road Oct Oct

Crawford Zolner Road, Champneys Road, Irwins Road Aug Aug

Durong Staines Road, Woltmanns Road, Paines Aug Aug Road

Jacksons Road Sep Sep Ridge Road, Iron Bark Road, Shellytop Oct Oct Road, McLean Road

Page 2 of 4

Ellesmere Oaky Creek Back Road Aug Aug

Goodger Tigells Road, Neale Road, Staiers Road, Sep Sep Whiterock Road, Buttsworth Road, Edenvale South Road

Gordonbrook Linds Road, Cooleys Road, Carews Road, Aug Aug Findowie Road, Trouts Road Haly Creek Flagstone Road, Findlays Road, Bookless Aug Aug Road, Haly Creek Road, Mustons Road Kingaroy Mount Wooroolin Road, Borcharts Road, Aug Aug Bridgett and Carroll Road, Irene Street, Ushers Road, Tessmanns North Road, Millers Road North, Klass and Townes Road Memerambi Lamperds Road, Wenzels Road, Meehans Aug Aug Road Memerambi Cemetery Road, Oil Seeds Road, Crittenden Road McDonald Road Oct Oct Nukku North Road, Nukku Road, Ulampa Sep Sep Creek Road Taabinga Rattenburys Road, Toomeys Road, Sep Sep Pamela Drive, Harder Road, Wild Deer Drive, Sep Sep Old Esk Road Stretton Drive Sep Sep Old Wondai South Road, Memerambi Aug Aug Barkers Creek Road, Carseldine Road Wigton Gayndah Hivesville Road Jul Aug

Roadside Slashing / Boom Mowing

Locality Description Expected Expected Start Completion Date Date North McLaughlin Road, Williams Road Aug Aug Blackbutt Service Road, Griffin Road Aug Aug Anita Road, Crumpton Drive Aug Aug Brooklands Brooklands Road Sep Sep Nanango Carbeen Crescent Aug Aug Taromeo Taromeo Rise Aug Aug

Page 3 of 4

WATER and WASTEWATER BRANCH

Water Main Replacement Name Description Expected Start Expected Date Completion Date Kingaroy CBD Transformation Alford St (Youngman – Short) Water Main Replacement November November Kingaroy St East side Water Main Replacement November December Kingaroy St West side Water Main Replacement November December Haly St Northern side Water Main Replacement December December Haly St South side Water Main Replacement January February Glendon St Water Main Replacement February March Youngman St North Water Main Replacement September October Reen St Water Main Replacement September October Wondai Haly St (Hodge to Scott St) Water Main Replacement August September Regional Replace 700 Water Meters August March

Additional Water and Wastewater Works Name Description Expected Start Expected Date Completion Date Kingaroy Orana Reservoir Roof replacement and August October structural upgrades Kingaroy Sewer Re-lining sewer mains November June

Nanango Nanango Sewer Trunk main replacement August October

Wondai Scott St Reservoir Roof replacement August October

Page 4 of 4