APPENDIX VIII

(See paragraph 6)

FROM 1M

(II) Basic Information

SI. Areas Distance in Kilometer /Details No

“Granite Building Stone Quarry” Of Mr . Rajesh Roy , Managing Partner Universal (viii) Name of the Mining Lease site Granites Alanadu P. O ,

Boundary Latitude (N) Longitude (E)

Pillar No

(ix) Location / site 1 09°44'31.6" 76° 43'43.7"

G.P.S. Coordinate 2 09°44'34.1" 76° 43'42.9"

3 09°44'34.5" 76° 43'42.3"

4 09°44'35.7" 76° 43'45.0"

5 09°44'35.2" 76° 43'45.3"

6 09°44'32.8" 76° 43'46.7"

7 09°44'32.4" 76° 43'44.8"

(x) Size of Mining Lease (Hectare) 00.9912 Ha

(xi) Capacity of mining Lease (TPA) 43395 MT

(xii) Period of Mining Lease 5 Years

(xiii) Expected cost of the project 75 Lakhs

(xiv) Contact Information Mr. Rajesh Roy , Managing Partner Universal Granites Alanadu P. O , Kottayam. Mob: 9447368652

Environment Sensitivity

1 Distance of project site from rail or Culvert , Vezhanganma 0.700 Km road bridge over the concerned river , rivulet , nallah etc.

Distance from Infrastructural facilities 2

Railway Line Kottayam 30 Km

National Highway N H 49 - Theni 40 Km

State Highway Ponkunnam – Road 5 Km

Major District Road Vezhanganma- Ullandu 0.185 Km

Any Other Road Vezhanganma- Ullandu 0.185 Km

Electrical Transmission line pole or 0.303 Km tower

Canal or check dam or reservoirs or lake Nil or ponds

In take for drinking water pump house 12 ward jalavidharana padhathy 2 Km in take for irrigation canal pumps

Areas protected under international

3 conventions , national or local legislation for their ecological , Nil landscape , cultural or other related value.

4 Areas which are important or sensitive Nil for ecological reasons – wetlands , water courses or other water bodies , coastal zone , biospheres , mountains , forests

Areas used by protected important or 5 Nil sensitive species of flora or fauna for breeding , nesting , foraging , resting , over wintering , migration

Inland , costal , marine or underground 6 Nil water

7 State , National boundaries Nil

8 Routes or facilities used by the public for Nil access to recreation or other tourist , pilgrim areas

9 Defense installations Nil

10 Densely populated or built up area Barananganam 4 Km

Distance from nearest human habitation 0.126 Km

Areas occupied by sensitive man made Hospital : Govt Hospital Ulanadu 2 Km 11 land uses ( hospitals , Schools , Places of Worship , Community facilities ) School : Vezhanganma L P school 0.800 Km

Church : Vezhanganma St. Joseph Church 1.5 Km

Mosque : 7 Km

Temple : Vezhanganma Sree Mahadeva Temple 1.5 Km

Areas containing important , high quality 12 Nil or scarce resources ( ground water resources , surface resources , forestry , agriculture , fisheries , tourism , minerals)

13 Areas already subjected to pollution or Nil environmental damage ( Those where existing legal environmental standards are exceeded )

14 Areas susceptible to natural hazard Nil which could cause the project to present environmental problems ( Earthquakes , subsidence , landslides , erosion , flooding or extreme or adverse climatic conditions )

15 Is proposed mining site located over or near fissure / fracture for ground water Nil recharge

16 Whether the proposal involves approval or clearance under the

following regulation or Act , namely :- (a) The forest ( conservation ) Act , Nil 1980 : (b) The wildlife ( protection ) Act , 1972 : (c) The coastal regulation zone notification , 2011 . If yes , details of the same and their status to be given .

17 Forest land involved ( Hectares ) Nil

18 Whether there is any litigation pending against the project and / or Nil land in which the project is propose to be set up ?

(a) Name of the Court (b) Case No: (c) Orders or directions of the court, if any and its relevance with the proposed project .

“ I hereby given undertaking that the data and information given in the application & enclosures & true to the best of my knowledge & belief & I am aware that if any part of the date & information submitted is found to be false or misleading at any stage the project will be rejected & clearance give if any to the project will be revoked at our risk & cost “.

Date : 07-06-2017 Signature of project proponent along

Place : Alanad

Rajesh Roy

Managing Partner

Universal Granites

Alanadu P O

Kottayam