Request for Information Downtown Redmond Link Extension (DRLE) Project

To: Prospective Proposers From: Procurement & Contracts Division Date: January 16, 2018 Downtown Redmond Link Extension (DRLE) Project

Sound Transit is requesting industry comments on its upcoming Downtown Redmond Link Extension (DRLE) Project, located in the City of Redmond in King County, . Sound Transit anticipates utilizing the Design-Build delivery method for this Project. The Project will extend light rail for 3.4 miles from the Redmond Technology Center Station at NE 40th Street to Downtown Redmond. Project elements include a double-track guideway (elevated and at-grade), one elevated station, one at-grade station, structured and surface parking, civil and site work, roadway work, and bus transit facilities. Sound Transit is providing prospective proposers interested in the Project an opportunity to review the Project and provide feedback. At this time, Sound Transit is only requesting comments and will not provide any responses. Sound Transit requests that prospective Proposers submit comments by January 26, 2018. Please submit all comments to: Petra Payne Sr. Design & Construction Contracts Specialist Sound Transit 401 S. Jackson Street Seattle, WA 98104-2826 Email: [email protected]

The information contained in this document is subject to change prior to the issuance of the Request for Qualifications.

Downtown Redmond Link Extension RFI P a g e | 1 January 2018

Request for Information Downtown Redmond Link Extension (DRLE) Project

Sound Transit is particularly seeking the industry’s perspective and feedback related to:

 Whether there are concerns with performing the Design-Build work for the DRLE Project near and under SR-520 corridor, rebuilding the on and off ramps at the SR-202/SR-520 interchange, and working in downtown?

 Potential locations for staging areas are identified in the attached drawings. Of these potentials, please identify which locations would be beneficial for the Project. What are some concerns if the footprint of the staging area is limited?

 In general, the Project Requirements for the Design-Build contract will have prescriptive requirements for items such as the guideway footprint, right-of- way, roadway typical sections, and transit system components. Where do you believe Sound Transit can gain the highest value from having performance- based requirements (versus prescriptive requirements) on this Project?

 Based on the initial information on the scope and complexity of the Project and the Design-Build delivery method, what are the potential major challenges for the DRLE Project?

 Additional questions and comments with respect to this Project; whether it is scope, contract delivery method (Design-Build), or procurement process – are welcome. Sound Transit Project Delivery Team Structure Design-Build construction projects at Sound Transit are delivered by a dedicated project team consisting of construction managers, engineers, architects, operations and maintenance personnel, and project control specialists, as well as individuals representing procurement and contracts, stakeholders, right-of-way acquisition, government relations, permitting, environmental, planning, community outreach and related disciplines throughout the duration of the project.

Downtown Redmond Link Extension RFI P a g e | 2 January 2018

Request for Information Downtown Redmond Link Extension (DRLE) Project

In addition, Sound Transit anticipates engaging the services of a Design-Build Project Management (DBPM) consultant to augment the Sound Transit project team during design and construction. The DBPM will participate in contract administration, design oversight and review, construction oversight, quality verification, and safety and environmental compliance oversight. Key Stakeholders Since the initiation of the DRLE planning phase in 2011, Sound Transit has forged strong working relationships with the “Authorities Having Jurisdiction (AHJ)” including City of Redmond, King County and WSDOT. Stakeholder outreach is ongoing with major public and private utility operators. DRLE Design Build Project Description Project Scope Voters approved funding for preliminary engineering for the Redmond Link Extension in the 2008 Sound Transit 2 (ST2) ballot measure. Due to the recession in 2007-2009 resulting in a large reduction in tax revenues, the ST2 program was realigned to maintain affordability. Sound Transit Board suspended some projects and project phases until funding could be identified. Preliminary Engineering for the DRLE Project resumed in 2016 after funding approval for (ST3). This Project is now part of the voter-approved ST3 plan to add 50 more miles of light rail throughout the region.

The Project consists of Light Rail Transit (LRT) civil and systems works from the Redmond Technology Center at NE 40th Street to Downtown Redmond.

The alignment for the revised preferred alternative starts at the Redmond Technology Center station and runs parallel to the east side of SR-520 as it travels north to the SR-520/West Lake Sammamish Parkway NE interchange. The profile in this section is at-grade and retained cut with cut and cover sections under 40th, 51st and 60th Streets. The alignment transitions to elevated guideway on a new bridge, crossing the Sammamish River. The elevated alignment then transitions to an at- grade section along SR-520 as it crosses the North edge of Marymoor Park to the SE Redmond Station. From the SE Redmond Station, the alignment crosses at-grade underneath SR-520 before rising to cross over Bear Creek. The SR-202/SR-520 interchange off-ramp and on-ramp are reconstructed over the at-grade guideway. Downtown Redmond Link Extension RFI P a g e | 3 January 2018

Request for Information Downtown Redmond Link Extension (DRLE) Project

The alignment stays elevated from Bear Creek to downtown Redmond within the south edge of the Redmond Central Connector easement. An elevated spans 166th Avenue NE, and the light rail line terminates east of 164th Avenue NE with tail tracks (Figure1).

Figure 1 – DRLE Revised Preferred Alternative

Downtown Redmond Link Extension RFI P a g e | 4 January 2018

Request for Information Downtown Redmond Link Extension (DRLE) Project

The DRLE Project, subject to final Sound Transit Board Action, consists of the following major elements:  Approximately 3.4 miles of turnkey double-track elevated, retained cut and at- grade light rail guideway including systems.  Two stations: - An at-grade station in SE Redmond in the vicinity of Marymoor Park. - An elevated station in Downtown Redmond at 166th Avenue NE.  Bus transit, park-and-ride, and parking facilities development.  Reconstruction of freeway ramps at SR-202/SR-520 interchange to allow at- grade light rail guideway at this location.  Parking of about 1,400 stalls – a combination of structured and surface parking located at the SE Redmond Station.  Cut and cover crossings including retaining walls, utility relocation and decking.  Facility accommodations and systems elements consisting of conduits and duct banks, traction power substations, signal houses, overhead catenary system, signal and communications systems.  Roadway work, sidewalk construction and landscaping associated with light rail facilities.  Utility work including both public and private re-locations.

Downtown Redmond Link Extension RFI P a g e | 5 January 2018

Request for Information Downtown Redmond Link Extension (DRLE) Project

SE Redmond Station

Figure 2 – Representative configuration of SE Redmond Station

Downtown Redmond Link Extension RFI P a g e | 6 January 2018

Request for Information Downtown Redmond Link Extension (DRLE) Project

The station platform is at grade, tucked close to the SR-520 right-of-way and the northeast boundary of the Marymoor Park. A key element at the station involves providing 1,400 parking spaces split between a parking garage for 1,100 stalls to the east of the SE Redmond Station platform with frontage on NE 70th Street, and 300 surface parking spaces, located to the west of the station platform. Bus transit is integrated into the ground floor/street level of the parking garage.

The geometry of the station, guideway and traffic impacts necessitates localized changes in alignment with NE 70th Street and improvements to the street section.

There could be potential trail connections with the East Lake Sammamish Trail to the SE Redmond Station. Additional considerations for the station are bus facilities, storm water and utility approaches and strategy.

Downtown Redmond Link Extension RFI P a g e | 7 January 2018

Request for Information Downtown Redmond Link Extension (DRLE) Project

Downtown Redmond Station

Figure 3 – Representative configuration of Downtown Redmond Station

Downtown Redmond Link Extension RFI P a g e | 8 January 2018

Request for Information Downtown Redmond Link Extension (DRLE) Project

The elevated station platform straddles 166th Ave NE opposite the Redmond Town Center commercial development. The station location facilitates integration of bus and rail. Key considerations for the station are tail track configuration, bus facilities, utilities strategy and Redmond Central Connector access, and restoration work at the 76th Street and the Redmond Central Connector.

Downtown Redmond Link Extension RFI P a g e | 9 January 2018

Request for Information Downtown Redmond Link Extension (DRLE) Project

Project Goals The purpose of the DRLE Project is to extend the Sound Transit system to Downtown Redmond with the following goals:  Complete this Project in time to allow revenue service in 2024 which will complete the vision of a light rail spine from downtown Seattle to downtown Redmond.  Deliver the Project within the budget and schedule approved by Sound Transit Board.  Minimize disruption to surrounding area during construction.  Compliant construction practices with safety and environmental requirements.  Deliver a high quality transit facility that is durable, efficient and sustainable – for the safe use by the public.  Successful completion of systems integration and connection to the existing Link Light Rail system.  Smooth transition to Sound Transit Operations.  Meet Sound Transit’s goals and objectives regarding participation by Small Businesses and Disadvantaged Business Enterprises, Equal Employment Opportunity, and positive labor relations.  Maintain positive working relationships with stakeholders.  Develop a successful partnership with the Design-Build Contractor

Downtown Redmond Link Extension RFI P a g e | 10 January 2018

Request for Information Downtown Redmond Link Extension (DRLE) Project

Project Schedule/Milestones Anticipated procurement and Project milestones for both contracts include:

DRLE DBPM

 DBPM team Notice-to-Proceed (Phase 1): 2Q 2018 DRLE Design-Build  Design-Build RFQ issued*: 2Q 2018  Design-Build Firms Shortlisted: 3Q 2018  Issue Request for Proposal (RFP): 3Q 2018  Design-Build Draft Proposal Submittal Due: 4Q 2018  Design-Build Final Proposals Due: 1Q 2019  Design-Build Contract Award/Notice-to-Proceed: 2Q 2019  Revenue Service: 2024 * After Sound Transit Board’s selection of the Project to be built.

During the proposal phase, Sound Transit plans to require the short-listed Design- Build firms to submit early proposal drafts. The early proposal drafts will be reviewed with specific focus on the aesthetic of the stations and garage facilities, adjoining public spaces and urban design elements and the interfaces with WSDOT. The review will also include an RFP-compliance check to ensure the proposal is in accordance with the intent of the RFP, avoid fatal flaws and improve the responsiveness of the final proposal. The early proposal drafts and Sound Transit review comments for those drafts will be for information only, therefore non-binding.

Downtown Redmond Link Extension RFI P a g e | 11 January 2018

Request for Information Downtown Redmond Link Extension (DRLE) Project

Estimated Design-Build Cost The estimated Design-Build cost for the Project is $500 to $600 million in 2017 dollars.

Planning and Environmental Approvals

The Downtown Redmond Link Extension was included as Segment E in the East Link Environmental Impact Statement (EIS) prepared pursuant to the National Environmental Policy Act (NEPA) and State Environmental Policy Act (SEPA) and published in July 2011. The Federal Transit Administration (FTA) and Federal Highway Administration issued Records of Decision in November 2011. Since then, conditions in the Project area have changed affecting how the segment can be constructed and operated. Sound Transit has updated the Project design, and the Sound Transit Board identified the revised preferred alternative in June 2017. Sound Transit and FTA are currently preparing a NEPA Re-evaluation and SEPA addendum to address changes in the Project. Sound Transit Board selection of the Project to be built is anticipated after completion of NEPA and SEPA review in the second quarter of 2018.

Sound Transit will compile a list of the environmental permit commitments and provide them to the Design-Build Contractor for incorporation into the Project.

Agreements and Permitting

Sound Transit will obtain lease agreements with WSDOT for the Temporary Construction Air Space Lease (TCAL) and permanent Air Space Lease (ASL) for work relating to Project improvements within SR-520 and SR-202 corridors.

Sound Transit is coordinating with City of Redmond and King County on the Project permitting and agreements. The coordination includes Design-Build process, station location workshops, urban design goals, and identification and resolution of various engineering and design issues. It is expected that final agreements with the City of Redmond and King County will be reached in 2018.

Permits to be obtained by the Design-Build Contractor include, but are not limited to, City’s Site Plan Entitlements (SPEs), Coordinated Civil Reviews (CCRs), Building Permits and their associated trade permits (mechanical, electrical, fire alarm, fire

Downtown Redmond Link Extension Page | 12 January 2018 RFI

Request for Information Downtown Redmond Link Extension (DRLE) Project

sprinkler/standpipe, etc.), Demolition Permits, Clearing & Grading Permits, Right-of- Way Permits, and Temporary Noise Variance Permits; Department of Ecology’s Construction Stormwater General Permit; and WSDOT General Permits, for items not already covered under the TCAL or ASL.

Right-of-Way

Sound Transit is currently in the pre-acquisition phase of securing public and private fee acquisitions, permanent and temporary easements, and WSDOT TCALs and ASLs. A Right-of-Way acquisition schedule will be provided with the Design-Build RFP.

Major Utility Relocations

Utility relocations will be required for the cut and cover work at major road intersections along the alignment, stations, parking garage, as well as columns/deep foundations for the elevated guideway sections.

The “Utility Technical Memorandum” developed for the Project will identify all major utilities and will be included with the Design-Build RFP. The Design-Build Contractor will be responsible to coordinate and cooperate with the public and private utility owners, investigate utilities, relocate utilities, or protecting them in place. Utilities to be encountered on the Project include, but are not limited to, overhead and buried electrical lines, overhead and buried telecommunications (including fiber optic), overhead and buried TV cable, Intelligent Transportation Systems (ITS), signal interconnects, gas mains, water mains, sewer mains, utility vaults and hand holes, and service connections. Funding

In November 2016, voters approved the ST3 plan, which includes funds for the design and construction of the DRLE. Sound Transit intends to utilize a combination of FTA and Local Funds for this Project.

Project Risks and Potential Allocation

Sound Transit is in the process of updating and refining a Risk Matrix for the Project. Major identified risks will be presented during the Industry Outreach Event on January 31, 2018. The notification for the outreach event will be published via eBid.

Downtown Redmond Link Extension Page | 13 January 2018 RFI

Request for Information Downtown Redmond Link Extension (DRLE) Project

With respect to geotechnical information, Sound Transit intends to provide Design- Build proposers with a Geotechnical Data Report and a Geotechnical Baseline Report.

Based on available geologic mapping and subsurface drilling information contained in historical borehole records, the subsurface conditions along the western part of the alignment (approx. 1.7 miles) are anticipated to primarily consist of glacial till with some areas of mapped advance outwash. From the vicinity of Sammamish River to the end of the alignment, younger alluvium deposits including peats underlain by sands and gravels in varying density are anticipated.

The guideway section along Marymoor Park and the SE Redmond Station area will present geotechnical challenges due to the high probability of peat, high water table, and hydric soils.

Artifacts of archeological significance were observed during potholing and preliminary soil investigation north of Marymoor Park.

Historical borehole records used for this preliminary characterization of the subsurface along the DRLE corridor were obtained from the Washington State Department of Natural Resources (DNR), WSDOT, City of Redmond, Microsoft Corporation (Microsoft), and previous Golder Associates Inc. projects.

Procurement Methodology

This Project will be procured and delivered using the Design-Build methodology in accordance with “RCW 39.10 Alternative Public Works Contracting Procedures.” Contractor Selection – Sound Transit will use a two-phase process (RFQ/RFP) in selecting the Design-Build firm to be awarded this contract. RFQ Phase – Sound Transit intends to short-list three of the best-qualified firms that provided a submittal to the RFQ. The RFQ Selection Criteria may include:

 Firm(s)’ experience working effectively together in design and construction of light rail transit projects.  Qualifications and commitment of Key Personnel.  Project Understanding and Approach.

Downtown Redmond Link Extension Page | 14 January 2018 RFI

Request for Information Downtown Redmond Link Extension (DRLE) Project

 Small/Disadvantage Business Enterprise (S/DBE): the Project will have an

S/DBE Goal established by Sound Transit for design and construction.  Equal Employment Opportunity (EEO) experience. RFP Phase – Sound Transit will select the best value proposal (technical and cost) received from the short-listed firms. The RFP evaluation criteria and scoring are yet to be determined. In addition, Sound Transit may request Best and Final Offers (BAFOs) from the short-listed firms.

Contract Price – The Design-Build contract price will be lump sum based. Honorarium – Sound Transit will provide an honorarium (amount yet to be determined) to the short-listed firms submitting responsive proposals to the RFP as determined by Sound Transit. The firm awarded the Contract will not receive an honorarium. Alternative Technical Concepts (ATCs) – ATCs submitted by short-listed firms during the RFP phase shall be confidential. Sound Transit will retain copyright of all ATCs. Only ATCs accepted in writing by Sound Transit prior to submission of proposals will be allowed to be incorporated into the Contract. Negotiation – Sound Transit will negotiate with the selected firm prior to award of the Design-Build contract. If an agreement cannot be reached between the selected firm and Sound Transit, negotiations will be terminated. Sound Transit may then begin negotiations with the next best qualified proposer. Provisional Sum – Sound Transit may include provisional sums in the contract to be used for specific elements of the works that are not defined in enough detail for pricing. Incentives – Sound Transit has not identified incentives, or Award Fees, in this Contract at this time. Insurance Requirements – All insurance for design and construction shall be acquired by the Design-Build Contractor and include the following items:

 Commercial General Liability  Commercial Automobile Liability

Downtown Redmond Link Extension Page | 15 January 2018 RFI

Request for Information Downtown Redmond Link Extension (DRLE) Project

 Contractor’s Pollution Liability  Builder’s Risk  Professional Liability  Railroad (ST) Protective Liability Minimum coverage levels have yet to be established for this Project. Proposers will be required by the RFQ to submit letters from their insurance brokers and bonding companies confirming their ability and capacity to provide the required insurance coverages and bonding amounts for the Project. Conflicts of Interest

Firms precluded from participation in DRLE Design-Build procurement will be identified in the RFQ. Firms are encouraged to submit a Conflict of Interest Inquiry if they have concerns regarding any ongoing, past, or future work performed by their firm on Sound Transit projects. Conflicts of interest or unfair competitive advantage queries will be addressed on a case-by-case basis. Communication/Public Disclosure

All communications will be directed through the assigned Contract Specialist during the procurement process. Proposals submitted by the Shortlisted Firms are exempt from public disclosure until Sound Transit has issued notification of the highest scoring finalist (RCW 39.10.470).

Drawings

Conceptual DRLE Project plans and profiles including potential staging area locations are attached.

Downtown Redmond Link Extension Page | 16 January 2018 RFI

REQUEST FOR QUALIFICATIONS ARCHITECTURAL & ENGINEERING SERVICES

DOWNTOWN REDMOND LINK EXTENSION DBPM

RFQ NO. RTA/AE 0195-15

REFERENCE DOCUMENTS

DECEMBER 2017

ST = EB 778+78.94 / SOUND TRANSIT DOWNTOWN REDMOND LINK EXTENSION 0+00 ST = EB 778+78.94 EQNBK= WB D 778+70.10

N 06°55'43" W W 06°55'43" N EQNBK= WB D 778+70.10 LEGEND:

N 06°55'43" W W 06°55'43" N EQNAHD= WB E 778+78.94

/ EQNAHD= WB E 778+78.94

N 06°55'43" W 06°55'43" N N 06°55'43" W 06°55'43" N

/

/ BEGIN STATION PLATFORM /

EB 779+52.16

/

WB E 780+00 780+00 E E WB WB EB 780+00 EB

/

EB 780+00 EB WB E 780+00 E WB

/

/

/

/

/ /

ENGINEERING . PLANNING ENVIRONMENTAL SCIENCES

/

/

/ / 4990+00

280 300 320 340 360 380 400 420 440

5+00

/

/

/

/

EB 4991+00 EB /

BP = EB 4991+00.00 / /

353.7 -1.50% PVI 4991+00.00 END STATION PLATFORM 50.00' EB 783+32.16

344.21 EL 344.21 / /

^

PVC EB 4991+50.00 TS = EB 4991+61.60 ^ /

EL 343.461 FACE OF BUMPING POST END EASTLINK FACE OF BUMPING POST

EB 784+07.91 / FACE OFFACE BUMPING POSTOF BUMPING POST EB 784+07.91 WB E 784+07.91

WB E 784+07.91 BEGIN REDMOND LINK EXTENSION LINK REDMOND BEGIN

END EASTLINK END ^ ^

362.7 POE = EB 784+38.32 / POE = EB 784+38.32 BEGIN REDMOND LINK EXTENSION POE= WB E 784+38.32 WB E 784+38.32

342.87 /

7+53

/

^

^

/

/

/

/

/

/ /

/

/ / /

/

SC = EB 4992+71.60 / / 364.8 / 342.63 LVC 450.00' / / PVI EB 4993+75.00 / / / / / / 366.1 EL 340.09 /+361' / / 343.65 CS = EB 4993+79.17 / / / /

+355'

+354' /

EB 4995+00 / ^ ^

+352.87'

4995+00 /

+351.9'

353.5 / ^ 345.93 ^ /

ST = EB 4994+89.17 /

/

^ ^ /

/

354.4 PVT EB 4996+00.00 MICROSOFT BUILDING 50 ^ ^ 349.46 EL 349.46 / /

/

/

200.00'

4.17%

^ /

357.1 ^ 353.63 /

/

/

^

/ ^

/ 361.0 PVC EB 4998+00.00 /

PARKING GARAGE ^

357.80 EL 357.796 ^ / MICROSOFT

/

^

/ ^

/

364.6 /

^ ^

361.66 /

EB 5000+00

/

^

/ ^ 5000+00

/ P

/

369.6 P

^

SB #1 ^

364.92 /

/

^

/ ^

/

371.8 / ^ ^

367.58 /

/

^

LVC 800.00' / TS = EB 5001+16.13 ^

/ PROPOSED DESIGN REFINEMENTS - SEGMENT E ROADWAY BUILD NEW /

368.5 PVI EB 5002+00.00 ^ ^

369.64 EL 374.46 /

SC = EB 5002+06.13 /

^

^ /

/ /

370.0 ^ ^

371.09 / /

^

^ /

MICROSOFT BUILDING 83 /

TOP OF RAIL AT EB TRACK / ^ TRACK PLAN & PROFILE 372.0 ^

371.94 /

EB 5005+00 / ROADWAY REBUILD

^

^ /

5005+00 /

/ ^ 373.4 ^

372.19 /

CS = EB 5005+27.35 /

^

^

/ /

/ ^

374.0 PVT EB 5006+00.00 ^ 371.83 EL 371.83 ST = EB 5006+17.35 / /

^

^

/ /

/ ^

374.0 ^ /

371.17 EX GRADE AT EB TRACK /

^

^

/

/ /

374.0 ^

/

370.52 (

/

^

550.00' -0.66% /

(

/ /

375.8 ^

/

369.86 EB 5010+00 (

/

^ /

5010+00 ( / /

374.9 ^

369.20 / /

^

^

/

/ TS = EB 5010+85.06 / ^

372.2 ^

368.55 / /

^

^ PVC EB 5011+50.00 /

EL 368.217 / / ^ 368.8 ^

367.82 / /

^ ^

SC = EB 5012+65.06 /

/

/ ^ ^ REV. NO. DWG NO. SHEET OF 369.9

366.59 / LVC 900.00' /

^

^

/

/ / ^

370.0 ^ /

364.78 5015+00 EB

/ ^

^ /

5015+00 / / ^ 369.8 ^

362.40 / /

N ^

^ /

5016+00

/ / PVI EB 5016+00.00 ^

369.1 ^ 280 300 320 340 360 380 400 420 440

359.44 EL 365.26 / /

^ 5016+00 240 260 280 300 320 340 360 380 400 369.1 PVI EB 5016+00.00 359.44 EL 365.26

366.0 355.91 LVC 900.00' 362.0 351.81

359.6 347.13 5020+00 356.4 341.88 PVT EB 5020+50.00 EL 339.03 350.5 336.12

348.0 330.29

343.9 324.64

338.8 319.61 5025+00 341.1 315.22

339.2 311.46

332.1 308.32

323.7 305.36

314.6 302.40 5030+00 306.0 299.44

299.5 296.48

295.4 293.53

293.1 290.57

291.7 287.61 5035+00 291.7 284.65

290.0 281.69

290.0 278.73

286.3 275.77

276.0 272.81 5040+00 275.3 269.85

274.0 266.89

270.0 263.93

266.0 260.97 5044+00 262.4 240 260 280 300 320 340 360 380 258.01 400 EB 5015+00 SOUND TRANSIT DOWNTOWN REDMOND LINK EXTENSION LEGEND: /

^

5016+00 240 260 280 300 320 340 360 380 400 / ^ MICROSOFT BUILDING 88

369.1 PVI EB 5016+00.00 /

359.44 / ^ EL 365.26 ^

/

/

/ ^ ^ 366.0 /

/

355.91 PARKING GARAGE ^ ^ /

MICROSOFT

/

/ ^ ^

LVC 900.00' / ENGINEERING . PLANNING ENVIRONMENTAL SCIENCES 362.0

351.81 /

^ ^

/

/ /

^ ^

359.6 / 347.13 / ^

^

/

/ /

5020+00 ^

^ / 356.4 CS = EB 5019+74.37 5020+00 EB

341.88 / ^

^ /

PVT EB 5020+50.00 / /

EL 339.03 ^ ^ MICROSOFT BUILDING 88

350.5 /

/ -5.83%

336.12 175.00' ^

^ /

/

ST = EB 5021+54.37 /

^ ^

/

348.0 /

330.29 ^

PVC EB 5022+25.00 ^ /

EL 328.834 /

/

^ ^

/

343.9 /

/ 324.64 ^

TS = EB 5023+20.03 ^ /

/

^

^ /

338.8 / LVC 450.00'

/

319.61 ^ ^

/

/

/ / / / / / / / / / / / / / / / / / PVI EB 5024+50.00 /

5025+00 EL 315.72

341.1 5025+00 EB 315.22 SC = EB 5025+00.03 / / / / / / / / / / / / / / 339.2 / / 311.46 / / /

/ ^ PVT EB 5026+75.00 /

332.1 EL 309.06 ^ / 308.32 ^

/ CS = EB 5026+93.31 ^ /

^ / EX GRADE AT EB TRACK

/

323.7 ^

/ 305.36 ^

/ / ^

^ / TOP OF RAIL AT EB TRACK /

314.6 ^ / 302.40 ^ ST = EB 5028+73.31 /

/ ^

^ / 5030+00 /

EB 5030+00

306.0 ^ / 299.44 ^ /

/

^ / ( PROPOSED DESIGN REFINEMENTS - SEGMENT E /

299.5 /

TS = EB 5030+47.63 ^ 296.48 ( / /

(/ ^ /

295.4 / ( ^ 293.53 /

/ / ( SC = EB 5032+26.94 ( /

293.1 / TRACK PLAN & PROFILE (

290.57 /

^ / / ( / ^

291.7 / (

287.61 /

^ /

( 5035+00 /

^

291.7 5035+00 EB /

/

284.65 ( /

^

/

(

/ ^ /

290.0 NW / (

281.69 1950.00' -2.96% /

^

/ (

CS = EB 5036+89.46 /

/ ^

290.0 /

(

278.73 / /

^

( /

/

286.3 / ^

( 275.77 /

ST = EB 5038+68.77 /

(

/ ^

/

/ 276.0 (

^

272.81 /

/

NW

/ ^ ^

5040+00

/ EB 5040+00 EB

275.3 / ^ ^

269.85 /

/

/

^ ^

NW /

274.0 / ^ ^

266.89 /

/

/ ^ ^

/

/

NW ^ ^ REV. NO. DWG NO.

SHEET OF 270.0

263.93 /

TS = EB 5042+81.00 /

/

^ ^

/ /

266.0 ^ ^

/

260.97 NW /

/

^ ^ /

5044+00 SC = EB 5044+30.52

/

^ ^ 262.4 / 300 320 340 360 380 240 260 280 400

258.01 CS = EB 5044+93.03 /

N

^ NW ^

/

EB 5045+00 EB /

/

^ ^

/

/ ^ ^

ST = EB 5046+42.55 / NW 5044+00 120 140 160 180 200 220 240 260

^

SOUND TRANSIT DOWNTOWN REDMOND LINK EXTENSION

/ ^ /

258.01 /

^

^

/ / 5045+00

^

^ NW /

SC = EB 5044+30.52 EB 5045+00 255.05 /

^

/ ^

CS = EB 5044+93.03 / /

^

^

/ /

252.10 NW ENGINEERING . PLANNING ENVIRONMENTAL SCIENCES

PVC EB 5046+25.00 ^

/ ^

EL 251.356 / /

^ ^ ST = EB 5046+42.55 / LVC 250.00'

249.00 / /

^ ( / PVI EB 5047+50.00 NW

EL 247.66 /

^ (/

245.42 / /

^ ( TS = EB 5048+07.90 / PVT EB 5048+75.00

^ ( /

EL 242.40

/

241.35 /

/ /

5050+00 / LEGEND:

EB 5050+00 / 235.8 (

237.15 SC = EB 5049+58.38 ^

/

( /

^

/

/

223.7 CS = EB 5050+35.96 (

232.95 /

/

/ /

228.5 /

228.75 / / ST = EB 5051+86.44

/ ^

230.1 / ^

224.55 /

^

/

/ ^

/ ^

216.2 / ^

220.34 / ^

/

/ ^ 5055+00

/ ^ /

229.6 EB 5055+00 ^

216.14 /

/

^

/

^

/ ^

225.1 / ^

211.94 /

TOP OF RAIL AT EB TRACK

/

^

/

^

/ ^

224.8 / ^

207.74 /

/

^

/

^ /

222.7 / ^

^ TS = EB 5057+34.70 /

203.54

/

/

^ /

219.9 / ^ /

PROPOSED DESIGN REFINEMENTS - SEGMENT E 199.34

/

^ /

5060+00 SC = EB 5059+14.70 /

EX GRADE AT EB TRACK ^ EB 5060+00

209.4 / ^

2325.00' -4.20%

195.13 /

/

^

/ ^ / ^

202.6 / ^

190.93 / TRACK PLAN & PROFILE /

^

/ ^ ^

/ TPSS E28 TPSS

^

201.7 / ^

186.73 / /

^

/ ^ /

212.7 / ^ 182.53 / /

^

^

/ /

^

^

181.9 /

178.33 /

/ ^

^ /

5065+00

/ ^ 5065+00 EB

^

180.8 /

174.12 CS = EB 5065+52.83 / / ^ ^

SC = EB 5066+12.83 / /

^

156.6 /

169.92 /

/ ^ /

^ /

^ 175.7 /

165.72 ^ /

/

( ^/

/

171.5 /

^ (

161.52 /

/

( ^/

/

/ 173.0 ^ (

157.32 /

/

^ ( /

EB 5070+00 EB

5070+00 /

/

^ (

164.8 / 153.12 /

REV. NO. DWG NO. ^ SHEET OF

/ ^

/

/

/ ^

152.3 /

148.91 / /

/

/

/

/

124.1 PVC EB 5072+00.00 / LVC 200.00'

/

/ / / / / 144.71 / / EL 144.712 / 5073+00 N 106.0 PVI EB 5073+00.00 120 140 160 180 140.31 EL 140.51 200 220 240 260 5073+00 100 120 140 160 20 40 60 80

/

106.0 PVI EB 5073+00.00 SOUND TRANSIT DOWNTOWN REDMOND LINK EXTENSION LVC 200.00' 140.31 EL 140.51 /

/

/

/

102.4 PVT EB 5074+00.00 / 135.51 EL 135.51 / /

LEGEND: /

5075+00

/

97.6 /

130.51 /

/ EB 5075+00

ENGINEERING . PLANNING ENVIRONMENTAL SCIENCES /

/

/

108.0 /

125.51 /

/

/

/

/

86.5 /

120.51 /

/

/

/

/

82.0 /

115.51 / /

72.7 110.51 5080+00 44.9 EB 5080+00

105.51

1394.31' -5.00% 45.7 100.51 / / / / / / / / / / / / / SB #3 / / / / / / / / / / 26.0 / / / 95.51

CS = EB 5081+57.87 /

/ /

41.0 /

90.51 /

/ /

ST = EB 5083+07.87 /

39.7 /

85.51 / /

EX GRADE AT EB TRACK

/ 5085+00 /

TOP OF RAIL AT EB TRACK /

37.2 EB 5085+00

80.51 /

/

/ /

33.9 /

75.51 / /

TS = EB 5085+93.36 / /

34.0 /

70.51 /

/

SC = EB 5086+83.36 / /

35.3 PVC EB 5087+94.31 /

65.51 EL 65.794 / /

PROPOSED DESIGN REFINEMENTS - SEGMENT E

/ /

36.2 /

60.79 /

/

/

5090+00 / /

35.2 5090+00 EB

56.58 / /

CS = EB 5090+09.13 /

TRACK PLAN & PROFILE /

35.6 / / ^

52.88 ^

/ /

^

^ /

36.0 /

/ ^

49.68 ^

/

/

/ 36.0 ^ (

ST = EB 5092+70.05 /

46.99 /

LVC 1200.00' (

^ /

/

/ 36.0 PVI EB 5093+94.31 ^ (

44.81 EL 35.79 / /

^ ( /

/

5095+00

/ ^ (

35.5 5095+00 EB

43.14 / /

^ ( /

/

/ 36.0 ^ (

41.97 / /

^ ( /

/

/ 36.0 ^ (

41.31 / /

^ ( /

/

/ 36.0 ^ (

41.15 / /

^ ( / /

36.8 /

41.51 /

/

^

^ /

REV. NO. DWG NO.

SHEET OF

5100+00 / /

PVT EB 5099+94.31 ^ ^

36.6 5100+00 EB

42.37 EL 42.31 /

/

^

^ /

/

/ ^ 37.1 ^

43.45 / /

^

^

/

5102+00 /

/ ^

37.5 ^

100 120 140 160 20 60 80 / 40

44.54 N

/

^

^ /

/

/ ^

^ /

SOUND TRANSIT DOWNTOWN REDMOND LINK EXTENSION

LEGEND: /

^ / ^ 5102+00 100 120 -20 20 40 60 80

36.5 0 /

/ ^

44.54 ^

/

/

^ / ^

37.1 /

/ ^

45.62 ^

/

TS = EB 5103+17.06 /

^ / ^

805.48'

1.09% TOP OF RAIL AT EB TRACK ENGINEERING . PLANNING ENVIRONMENTAL SCIENCES

37.6 /

/ ^

46.71 SC = EB 5103+87.01 ^

/

/

^ / ^ 5105+00

36.7 / / ^

^

47.79 5105+00 EB /

/

/

/

^

( 36.9 /

48.88 /

^

(

/

/

/

^

( 37.4 /

CS = EB 5107+00.68

49.96 /

^

( /

/ /

EX GRADE AT EB TRACK /

ST = EB 5107+70.63 ^ /

PVC EB 5107+99.80 ( / 36.9 /

/

51.05 EL 51.046 /

^

( / /

/ /

/

^ /

( / 37.3 /

LVC 320.00' /

51.88 /

100+00 ^

( / /

/ PVI EB 5109+59.80 / 5110+00

/ ^ / EL 52.78 (

/ 38.2 /

EB 5110+00 EB /

52.23 /

^

( / /

/ /

/

/ ^

/

40.2 /

( /

52.07 PVT EB 5111+19.80 / 102+00

^ /

EL 51.98 /

( / /

/

/ ^

/ 40.8 (

51.58 / / /

^ /

/ ( /

/ / ^

/ / 40.8 (

51.08 / /

/ 104+00 ^

/

/

( /

/

2+00 2+00 /

^ / / /

/ ( 40.9 /

50.58 / / ^

/

/

( / TS = EB 5114+64.30 / 5115+00

^ / /

( /

EB 5115+00 EB 42.0 /

/

50.08 /

106+00 ^

/ / (

/

4+00 /

^

/ /

SC = EB 5115+84.30 ( / 40.5 /

/

49.58 / ^

/ / (

/ /

PROPOSED DESIGN REFINEMENTS - SEGMENT E

^

/ /

( / 40.7 /

49.08 /

108+00

^ /

/ / (

/

6+00

/ ^

/

/ 40.9 ( / HIGH RAIL

ACCESS /

48.58 /

1473.40' ^

/

-0.50%

/ ( /

/ /

^

/ /

TRACK PLAN & PROFILE

40.2 ( / /

48.08 110+00 /

^ /

/ ( /

SB #4 8+00

CS = EB 5118+84.19 / / 5120+00

^ / /

EB 5120+00 / / 47.58 / / / /

/

/ /

ST = EB 5120+04.19 /

40.6 / / 112+00

47.08 / / /

10+00

/ / /

/ /

41.4 / / / / 46.58 ^

/

/ / ^ ^

/

43.7 114+00 / ^ 46.08 ^ / 12+00

/ ^

/ ^

/

44.4 /

SEE SHT PP08 ^ FOR STATION 45.58 /

/

AREA ^ / 5125+00 /

EB 5125+00 /

^ / 45.08 14+00

/

^ /

/

PVC EB 5125+93.20 / ^ / 44.58 EL 44.615 /

^ /

TS = EB 5125+79.72 / LVC 230.00'

/

^ 42.2 / PVI EB 5127+08.20 16+00

44.33 / EL 44.04 ( ( ^ /

SC = EB 5126+59.72 / ( ( / ^ / REV. NO. DWG NO. SHEET OF

44.51 PVT EB 5128+23.20 ( ( /

^ / EL 44.62 ( / (

/ ( ^

/

( ( 18+00

^ ( EB 5130+00/ ( (

45.01 ^ /

( ( / ^ (

/

339.28' 5130+00

0.50% ^ /

/ 100 120 -20 0 60 80 20 40 45.51 ^ /

/ N

TPSS E30 / / ^ / /

/ CS = EB 5130+97.93 EB = CS /

SOUND TRANSIT DOWNTOWN REDMOND LINK EXTENSION

/ LEGEND:

/

/

/ / /

/ /

/ / / /

216+00 /

24+00 RAMP REBUILD / / /

/

/

ENGINEERING . PLANNING ENVIRONMENTAL SCIENCES /

/

5130+00 /

100 120 140 -20

20 40 60 80 /

0 /

214+00

45.51 / / CS = EB 5130+97.93 22+00 NEW TRAIL CONNECTION /

/

48.0 SC = EB 5131+57.93

/

46.02 22+72 22+00

/

^ TPSS E30 TPSS /

/

/

/

^

PVC EB 5131+62.48 /

/

20+00 /

EL 46.331 / / ^

(

212+00 ( 44.5 ^ / (

/

46.48 LVC 200.00' ( 5130+00 EB

20+00 ^ ^ /

(

/ (

( (

/

^ ^

PVI EB 5132+62.48 ( (

/

(

EL 46.84 /

18+00

^ ^

43.8 /

(

( /

46.55 / ^

/

(

/

( ^

PVT EB 5133+62.48 /

/ EL 46.33 (

46.9 210+00 (

154.72' 18+00 16+00

46.15 -0.50% ( (

CS = EB 5133+95.28 5135+00 ( 46.3 (

45.64 PVC EB 5135+17.20 EL 45.559 ( ( EB 5135+00

^ ST = EB 5134+87.46

46.1 208+00

16+00 (

45.49 ^

^

^ (

LVC 350.00' ^

^ 0+00 122+00 122+02 ^

(

120+00

/

^ ( 118+00

PVI EB 5136+92.20 / ^ /

43.9 ^ ^ ^ 116+00 / EL 44.68 / ( 46.31 ^ ^ ^ ^ ^

^ ^

/ / ^

/ / / / ^ / /

^ /

^ ^ ^ / /

/ / /

43.5 206+00 / / / /

48.14 14+00 / / ^

^ / / /

/ / / / /

PVT EB 5138+67.20 / / / / / ^ EL 49.93 / ^ / / / 35.0 / / / /

100 YR FLOODPLAIN ELEV. / / / / 50.92 / PC =/ EB 5138+13.00/

/ ^ / / ^

/ / /

/ / / 3'

5140+00

/ / / /

42.2 204+00 / /

53.92 349.69' 12+00 3.00%

/ / / ‡ ‡ / EB 5140+00

‡ ‡ / ‡ / ‡ ‡ ‡ ‡ ‡ ‡

‡ ‡ / ‡ ‡ ‡

‡ ‡ ‡

44.2 ‡ ‡ ‡ ‡ ‡

‡

‡ ‡

‡ ‡ ‡ 56.92 ‡ ‡

‡ ‡

‡ ‡

‡

‡ ‡

‡ ‡ ‡ ‡ ‡

‡

‡ ‡

‡ ‡

‡ ‡ ‡ ‡

‡ ‡ ‡ ‡ ‡ DOWNSTREAM ‡ ‡

‡ ‡ ‡

‡ ‡ ‡ ‡ ‡

‡ ‡

‡ ‡

40.7 202+00 42.7 42.2

PVC EB 5142+16.89 10+00

59.92 ‡ ‡ ‡ ‡

PROPOSED DESIGN REFINEMENTS - SEGMENT E EL 60.423 ‡

‡ ‡ ‡

BEAR CREEK CROSSING CREEK BEAR ‡

40.3 ‡

‡ ‡

‡ ‡

UPSTREAM ‡ ‡ ‡ ‡ ‡

‡

‡ 62.74 ‡ ‡ ‡ ‡ ‡ ‡

‡ ‡ ‡

44.8 43.8 ‡ ‡ ‡

‡ ‡ ‡ ‡

‡ ‡

‡ ‡ ‡ ‡

‡ ‡ ‡ ‡ ‡ ‡ ‡

‡ ‡ ‡ ‡

‡ ‡

‡ ‡ ‡ ‡ PT = EB 5142+84.35 ‡ ‡

‡ 200+00 40.4 ‡ ‡ ‡

‡ ‡

‡ ‡

65.08 LVC 500.00'

‡ ‡ 9' ‡

‡ ‡ ‡

TRACK PLAN & PROFILE ‡

PVI EB 5144+66.89 ‡ ‡ 5145+00

‡ ‡

‡ ‡

‡

EL 67.92 ‡ ‡ ‡ ‡

40.9 ‡ ‡ ‡

66.91 ‡ ‡

‡ ‡ ‡ ‡

‡ ‡ ‡

‡ ‡ 5145+00 EB ‡ ‡ ‡ ‡

EX GRADE AT EB TRACK ‡ ‡ ‡

‡ ‡ ‡ ‡

40.5 ‡ ‡ ‡ 68.25 ‡ ‡

‡

‡ ‡

‡

‡ ‡

‡

‡ ‡

‡ ‡

‡

‡ ‡

‡ ‡

‡ ‡ ‡

‡ ‡

‡ ‡

‡

40.4 ‡ ‡

‡ ‡

‡

‡ •

PVT EB 5147+16.89 • ‡ ‡

‡ 69.08 ‡

• •

‡ •

‡ ‡ • ‡ ‡

‡ ‡ • •

‡ ‡ ‡ EL 69.17 • • ‡ ‡

• •

‡ ‡

‡

‡ • •

‡ ‡ ‡

• ‡

• • ‡ ‡

• •

‡ ‡ ‡ •

• ‡ ‡

• ‡ ‡ ‡

• •

‡ ‡ • • ‡ ‡

• ‡ •

‡ ‡

‡ ‡ • •

‡ ‡ ‡ • •

• ‡

‡ ‡

‡ ‡

‡ • 45.2 • • • ‡ ‡ • •

• ‡

REDMOND WAY

‡ ‡

‡

‡ • • ‡ ‡ ‡

• ‡

• •

‡ 69.59 ‡ • •

‡

‡ ‡ •

• ‡ ‡

• ‡

• •

‡ ‡

• ‡ TOP OF RAIL AT EB TRACK

44.3 ‡ ‡ ‡ ‡ ‡

‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ 170TH AVENUE NE AVENUE 170TH

70.09 NE AVENUE 170TH

• • • • • •

• •

‡ ‡ • •

5150+00

‡ ‡

• •

• • ‡ ‡

‡

• ‡ •

• • ‡ ‡

‡ ‡ • •

41.3 • • ‡ ‡

‡ ‡

• •

70.59 • • ‡ ‡

‡

‡ • •

• • ‡ ‡

‡ ‡ • •

• • ‡ ‡

‡ ‡

• •

• • ‡ ‡ 5150+00 EB

• • ‡ ‡

40.9 ‡

‡

71.09 ‡

‡

‡

958.96' ‡

0.50%

‡ 5151+22 41.6 ‡ BP = 5151+21.81 71.59 ‡

‡

‡

‡ 5153+00

‡

41.5 ‡ 100 120 140 0 80 -20 20 60 40 ‡

72.09 ‡

SR 202 (REDMOND WAY)

‡ REV. NO. DWG NO. SHEET OF ‡

‡

‡ 5153+29

‡ SPEEDBUMP

‡ EP = 5153+29.29

‡

‡

SPEEDBUMP TS = EB 5153+79.29

SC = EB 5154+59.29 EB 5155+00 EB N CS = EB 5155+35.95

SPI = EB 5156+15.95 EB 5150+00 EB

‡ SOUND TRANSIT DOWNTOWN REDMOND LINK EXTENSION LEGEND:

‡

‡

‡

‡

‡

‡ 5151+22

‡ BP = 5151+21.81 ‡

‡

‡

‡

‡

‡

‡

‡

SR 202 (REDMOND WAY) ENGINEERING . PLANNING ENVIRONMENTAL SCIENCES

‡

‡

‡ 5153+00

100 120 140

‡

20 40 60 80 5153+29 0

‡ 41.5 SPEEDBUMP 72.09 ‡ EP = 5153+29.29

‡

‡

SPEEDBUMP TS = EB 5153+79.29 42.1 72.59

SC = EB 5154+59.29 EB 5155+00 EB 5155+00 43.3 CS = EB 5155+35.95 73.09

SPI = EB 5156+15.95 43.4 73.59

SC = EB 5156+95.95 PVC EB 5156+75.85 44.3 EL 73.970 74.08 LVC 200.00' CS = EB 5157+81.11 PVI EB 5157+75.85 43.9 EL 74.47 ST CLEVELAND 74.21 SPEEDBUMP SPEEDBUMP

NE 77TH ST / CLEVELAND ST CLEVELAND / ST 77TH NE ST = EB 5158+61.11 PVT EB 5158+75.85 42.8 EL 73.97

73.85 EB 5160+00 EB

SPEEDBUMP STATION AREA 5160+00 42.7 73.35

SPEEDBUMP 42.8

72.85

‡ ‡

44.0 166TH AVENUE NE 72.35

43.9

914.12' STATION AREA -0.50%

71.85 ‡

166TH AVENUE NE

‡

‡

‡ ‡

44.1 ‡ • ‡ ‡

71.35 •

• EB 5165+00 EB ‡ • ‡ • 5165+00 ‡

‡ 43.3 TOP OF RAIL AT EB TRACK

‡

70.85 ‡ PROPOSED DESIGN REFINEMENTS - SEGMENT E

‡

‡ EX GRADE AT EB TRACK

‡

• ‡

‡ 43.2 • ‡ 70.35 •

43.6 5167+72.43 EB 69.85

TRACK PLAN & PROFILE EP = EB 5167+72.43 PVI 5167+89.97

5168+38 EL 69.40 100 120 140 0 20 60 80 40

CLEVELAND ST

164TH AVENUE NE

164TH AVENUE NE

GILMAN STREET GILMAN GILMAN STREET GILMAN

CLEVELAND ST

LEARY WAY NE WAY LEARY

‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡

‡ ‡ ‡ ‡ ‡ ‡ ‡ LEARY WAY NE WAY LEARY ‡

LEARY WAY NE WAY LEARY

‡ ‡ ‡ ‡ ‡ ‡‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡ ‡

REV. NO. DWG NO.

SHEET OF BROWN STREET BROWN N

CLEVELAND ST

/ / LEGEND: (

/

/

^

/ SOUND TRANSIT DOWNTOWN REDMOND LINK EXTENSION /

( / /

/

108+00

^ /

/ / (

/ 6+00

/ ^

/

/

( / /

/

^ /

/ ( /

/ /

^

/

PARKING FACILITIES PROPOSED LOCATION FOR /

( / /

110+00 / ENGINEERING . PLANNING ENVIRONMENTAL SCIENCES

^ /

/ ( /

SB #4 8+00 CS = EB 5118+84.19 / /

^ / /

EB 5120+00 / /

/ / / /

/

/ /

ST = EB 5120+04.19 /

/ /

112+00

/

/ /

10+00

/ / /

/ /

/ / / / ^

/

/ / ^ ^

/

114+00 / ^ ^

/ 12+00

/ ^

/ ^

/

/

^ /

/

^ /

/

EB 5125+00 /

^ / 14+00

/

^ /

/

/

^ /

/

/ TS = EB 5125+79.72 ^ /

/ ^ / 16+00

/ ( ( ^ /

SC = EB 5126+59.72 / ( ( / ^

/ ( ( /

^ /

( ( /

/ ( ^

/

( ( 18+00

^ ( EB 5130+00/ (

^ / (

( / (

/

^ /

/

^ /

/

TPSS E30 /

^ / /

/

22+00 CS = EB 5130+97.93 EB = CS

PROPOSED DESIGN REFINEMENTS - SEGMENT E 24+00

PARKING FACILITIES PROPOSED LOCATION FOR

TRACK PLAN & PROFILE 25+88

/ / 100 50 REV. NO. DWG NO. SHEET OF SCALE IN FEET 0 N

100 (1" = 100') 200