Challenges and Possible Solutions for the Power System of the Future

A Research Perspective

Deepak Ramasubramanian [email protected]

CIGRE NGN Webinar November 8, 2019

www.epri.com © 2019 Research Institute, Inc. All rights reserved. Renewable & Battery Cost Trend: Unlocked Potential by 2025

Universal Solar PV: ~$0.02/kWh in high solar 4100 region but still almost half the cost of rooftop Solar Wind Battery solar ($/kWac) ($/kW) ($/kWh) Wind LCOE: ~ $0.03/kWh in high wind region

Electric vehicle (~300miles): ~$7,000 decrease Commercial building batteries: 2-year payback

2100 Solar/wind + 4-6 hour storage cost = power plant 1650 1350 1400 1000 850 No breakthrough technology needed! 200 100 2010 2017 2025 2010 2017 2025 2010 2017 2025

2 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Renewables are increasing…

3 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Not just wind and solar PV

Electric Vehicles Batteries

700,000 9 650,000 600,000 8 550,000 500,000 7 450,000 400,000 6 350,000 300,000 5

250,000 NumberVehicles of 200,000 4 150,000

100,000 Installed Capacity(GW) 3 50,000

0 2

Apr-11 Apr-12 Apr-13 Apr-14 Apr-15 Apr-16 Apr-17

Dec-10 Dec-11 Dec-12 Dec-13 Dec-14 Dec-15 Dec-16

Aug-12 Aug-13 Aug-14 Aug-15 Aug-16 Aug-11 1 Nissan GM Toyota - Ford BMW Tesla 2012 2013 2014 2015 2016e 2017e 2018e 2019e 2020e 2021e 2022e 2023e 2024e 2025e OTHER PHEV TOTAL BEV TOTAL Small-Scale Batteries Utility-Scale Batteries

Source: EPRI Program on Electric Transportation Source: Bloomberg New Energy Finance, illustrated by EPRI

4 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Inverter Based Resources and Low Short Circuit Systems

5 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. What is short circuit ratio (SCR)…? ▪ SCR – Ratio of short circuit MVA at a source bus to the MW rating of generator – High value of SCR implies that the source is ‘small’ relative to the rest of the network. ▪ If source moves around a lot, network is minimally impacted. – Lower values of SCR implies that source can be ‘comparable’ size with network. ▪ Movement of source will impact network

Source: “Integrating Inverter-Based Resources into Weak Power Power Systems”, Andrew Issacs, Electranix Corporation, EPRI-NERC-NATF-ESIG Webinar Series, 2018

6 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Weak grids…

▪ How does a weak grid arise? – There is limited fault current available in the system -> resulting in lower voltages – There is large impedance between the source and rest of the network -> resulting in lower voltages

▪ Why may this be an issue? – An inverter uses measured voltage to decide the magnitude and angle of injected current – Small variation in current injection can cause large variation in voltages – An inverter tries to detect angle and magnitude of phase voltage, and react to this detection in a very fast manner. – This can results in an unstable operation. – In order to deliver a specific value of P and Q, both magnitude and angle of V should be known in order to decide the value and angle of current 푃 − 푗푄 퐼∠휙 = 푉∠ − 휓

7 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Inverters and Weak Grids ▪Wind/Solar interconnections in weak systems are becoming more common –Connected farther away from transmission –Reduction of available short circuit current

▪Contingencies or scheduled outages (e.g. lines under maintenance) may reduce system strength below typical levels expected under normal operating conditions. –Changes impedance of system

▪Additionally, if such a network situation coincides with ramping up of the plant, the location can become even weaker –Injection of higher current through an already weak network Source: “Deploying Utility-Scale PV Power Plants in Weak Grids”, First Solar, 2017 PES General Meeting, Chicago, IL, July 2017

▪Converter controller instabilities might occur under weak grid conditions –Inherent fast controllers may not be stable

8 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Present Industry Practices to Ascertain Inverter Impact in Low Short Circuit

▪ No clear industry standard on metrics & associated thresholds to identify a weak area of the system

▪ Low SCR doesn’t necessarily imply converter control instability – May re-tune (slowdown) inverter controls

▪ Other options to deal with low SCR – System reinforcement (, new transmission) – Curtail plant output Source: “Integrating Variable Energy Resources into Weak Power Systems”, NERC, June 2017

9 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. But SCR Does Not Provide The Entire Picture…

▪ For an inverter plant, a low or high value of SCR may not provide the entire picture about control instability

▪ Controller instability due to extended MW output duration of a fault can be because of: – Increased controller effort to maintain respective references during the fault Factors – Post contingency system does not provide sufficient damping Affecting Controller SCR Inverter Plant gains – Saturation of controllers due to large values of gain Instability ▪ New “Advanced Short-Circuit Strength” metric has been developed – For a fault at the POI of an inverter based plant, provides Plant estimate on fault clearing time threshold to prevent Layout controller instability.

10 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Limitations of Present Converter Positive Sequence Dynamic Models Generic Positive Sequence Models Limitations • Models not suitable for capturing fast controller dynamics/interactions • Models not accurate for studying unbalanced conditions near the converters • Models not suitable for interconnection studies of a wind/ plant to a weak transmission system • Models not suitable for detailed studies related to phenomena such as sub-synchronous resonance and ferro-resonance

11 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Proposed REGC_C (Positive Sequence Model)

▪Representation of PLL and inner current control loop ▪Small timestep required (1ms) ▪Improves numerical stability ▪Suggested to be used for weak grid studies before conducting detailed three-phase EMT studies ▪Update: ▪PSS®E model implementation almost complete ▪Model testing in collaboration with EPRI members

12 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Inverter Based Resource Impact on Protection Relays

13 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Motivation, Challenges & Needs

• Continuously increasing penetration level of inverter interfaced resources, predominantly renewables (Type III, Type IV WTGs & PVs)

Challenge

• Complex fault response • Differs significantly from synchronous short-circuit current contribution (SCC)

Impact on System Protection • Accurate short-circuit models for protection/planning studies • Performance of legacy protection schemes (distance protection etc)

14 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Inverter Based Resources Fault Response Characteristics

Synchronous Generator

•SCC magnitude close to nominal load current (typically 1.1-1.5 pu) •Initial transient (typical duration 0.5 -1.5 cycles) – uncontrolled response – controller “reaction time” •Fault current can be capacitive, inductive or resistive •Typically low negative sequence current contribution

Type IV WTG •No zero sequence current

15 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. IBR Short Circuit Models Synchronous generator classical short circuit model (voltage source behind an impedance) is not applicable

PSS®CAPE

• Voltage controlled current source • Iterative solution (nonlinear behavior) • considers the impact of controls on the short circuit response • respects inverter current limits ASPEN OneLiner v14 IEEE PSRC C24 WG Time frame 1 (seconds or cycles) Fault Type: Positive sequence voltage Positive sequence Positive sequence current (pu) current (pu) angle with respect to positive sequence voltage (deg) 0.9 0.7 0.5 0.3 0.1

16 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Protection System Performance Evaluation

Negative Sequence Based Protection • Investigate relays response & identify potential misoperation scenarios • Provide recommendations and study practices Line Differential Protection to protection engineers when conducting protection studies to prevent relay misoperation & miscoordination Communication Assisted Protection • Related Industry Efforts: • IEEE PES - NERC Technical Report “Impact of Inverter Based Generation on Bulk Power System Line Distance Protection Dynamics and Short-Circuit Performance” • DOE Project “Inverter Based Resource (IBR) Negative Sequence Current (I2) Injection Study” Power Swings Protection

17 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Next Generation Tools for Distribution Planning

18 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Distribution System Analysis Tools

Present day tools Requirements for future tools

• Snap shot simulation • Accelerate advanced analysis

• Extreme values • Varying operational conditions

• Simple and efficient • Big data processing

• Seemed to have everything • The evolution is happening

19 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. The Next Generation of Distribution Analysis Tools

20 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. The Next Generation of Distribution Analysis Tools

▪ Accelerating simulations

21 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. The Next Generation of Distribution Analysis Tools

▪ Simplifying Complex Processes and Data

High level interface, describes the simulation process and global considerations of the planning study

Medium level interface, describes customized equipment using pre-existing functions

Low level interface, describes customized functionalities as new components for the simulation

22 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Conclusions

23 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Distributed Energy Resources (DER) Impact on Bulk Power System

24 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Why should DER be modeled explicitly…?

Block tripping of DERs can be a concern to system stability

How does a transmission planner get this visibility?

25 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. A solution for DER to be modeled for bulk power system planning studies…

• Represents pumps, fans, lighting, HVAC systems, Substation residential AC. • Recently updated to represent behind the meter DER (R-DER) • Also represents dedicated load serving DER resources not netted with load

• Is this representation perfectly accurate? • No. It is only reasonably accurate • Does it need to be perfectly accurate? • No.

Focus of this presentation Step – down Aggregate dynamics of all loads/generation served by the substation If the decision to be made from studies does not change whether one uses detailed models or aggregated models, then aggregate models are sufficient

26 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. The modeling challenge still persists though…

Vsub0

VtDER_A0 Entire load on a substation modeled as a single equivalent

1.05pu

Complete three phase 0.95pu voltage profile represented by single RMS profile

27 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Aggregated model to represent the dynamic behavior of DER…

Proportional voltage control Vt_filt 1 _ Verr Iqv Vt 1 + s Trv Kqv

+ Iqh1 s0 Iql1 Vref0 (user defined) dbd1, dbd2 pfaref tan Iqmax 1 + Iq Pgen + (Pord) 1 1 1 Iqcmd 1 + s Tp Qref 1 + s Tiq 1 + s Tg s1 0 s2 Iqmin s3

Reference: Pflag 0.01 Q priority Vt_filt Xe The New Aggregated Distributed (s0)

Iqmax = Imax Vtqo Eq= id + control Vrfrac 1 Vtdo Ed= Energy Resources (der_a) Model Iqmin = -Imax + ~ Pqflag Current Vtripflag for Transmission Planning Ipmax = sqrt( Imax2 – Iqcmd2) 0 j V – Q priority Limit 1 + 1 Studies. 2019 Update. White P priority – P priority Logic 0 1 + s Tv Ipmax = Imax vl0 vl1 vh1 vh0 1 -

Paper. 3002015320. Electric Iqmax = sqrt( Imax2 – Ipcmd2) iq

s4 X

Power Research Institute (EPRI). Vt_filt X e Iqmin = -Iqmax Vt_filt (s0) e Palo Alto, CA (s0) Frequency Tripping Pmax Logic See Details in Id ( = Ip)

Freq_flag 0.01 Pmax Model Description rrpwr 0 dPmax Pref Pref Ipmax Voltage source interface femax s7 1 1 + 1 + s Tpord 1 + s Tg 1 _ Kpg + Kig Pord IpcmdVoltage and Ip Pgen 1 + s Tp + s 1 dPmin s8 s9 Frequency control (Pord) Ipmin femin s6 Pmin frequency -rrpwr 0 Pmin fdbd1,fdbd2 Frq_filt Ddn + Freq _ trip 1 1 + s Trf Post fault P recovery + + s5 Dup Frq_filt Freq_ref 0 _ Freq 1 To controls 0 1 + s Trf To frequency relay model + 1 s5 1 Freq_ref If Vt (terminal voltage) Vpr then 0 to position 1, else position 0 1 To frequency relay model 1 If Vt (terminal voltage) Vpr then switch to position 1, else position 0

How to find parameter values for the model? Present focus is on voltage thresholds.

28 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Partial trip of DER based on voltage magnitude…

Individual DER Vtrip = 0.88pu Individual DER Vtrip = 0.5pu

Reference: Deepak Ramasubramanian, Inalvis Alvarez-Fernandez, Parag Mitra, Anish Gaikwad and Jens C. Boemer, “Ability of Positive Sequence Aggregated Distributed Energy Resource Model to Represent Unbalanced Tripping of Distribution Inverters,” 2019 IEEE Power & Energy Society General Meeting (PES), Atlanta, GA, 2019

29 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Impact on bulk power system… ▪ Simulation premise – System generation is 69 GW, gross load is 81 GW, DER is 14 GW – Fault applied in the middle of transmission line, and subsequently line is cleared in 6 cycles – Load dynamics are considered along with DER dynamics

Without the parallel trip characteristic, there could be a huge misrepresentation of amount of DER that ride through a single phase fault

30 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Flexibility and Resource Uncertainty

31 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. German Hourly Net Load Range – August Workdays, 2019

60,000

50,000

40,000 27 GW RANGE 30,000 Maximum

Average NET LOAD (MW) LOAD NET 20,000 Minimum Data Source: 10,000 ENTSOe Transparency Platform Data

0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 HOUR

32 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Carbon Reduction Necessitates Enabling Flexiblity

33 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Long-Term Planning Needs –What “Type” of Capacity is Needed?

Traditional "Generic Capacity" Metrics New "Flexible Capacity" Metrics

LOLEGENERIC-CAPACITY LOLEMULTI-HOUR Traditional metric to capture events that occur due to New metric to capture events due to system ramping capacity shortfalls in peak conditions deficiencies of longer than one hour in duration

Load Generation 50,000 60,000 40,000

50,000 30,000

20,000 40,000 1 5 9 13 17 21

LOLEINTRA-HOUR 30,000 MW New metric to capture events due to system ramping deficiencies inside a single hour 20,000 45,500 10,000 44,500 43,500 More Information: 42,500 0 California Energy Systems for the 21st 1 3 5 7 9 11 13 15 17 19 21 23 41,500 Century Flexibility Metrics Project (2017) 10:00 10:10 10:20 10:30 10:40 10:50 11:00 Hours New need to ensure flexibility adequacy in long-term planning?

34 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Flexibility Will Become More Valuable

▪ Increasing variability and uncertainty will require flexibility on all time scales and at different spatial scales

▪ Different resources may contribute – DER, storage and inverter based resources may provide some of the needed flexibility services – Retrofits and altered operational More Information: Metrics for Quantifying Flexibility in Power practices System Planning, 3002004243, 2014 (EPRI)

EPRI working on flexibility tools and metrics to assess long term resource adequacy impacts

35 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Short-term Operational Needs – Impact on

Instantaneous events Primary Stabilize frequency

Contingency Return frequency to nominal Secondary Reserve and/or ACE to zero

Tertiary Return system to secure state (replace other reserves) Event Longer duration events Return frequency to nominal Secondary and/or ACE to zero Ramping Reserve Operating Return system to secure state Tertiary Reserve (replace other reserves)

Flexibility Correct the anticipated ACE Reserve Manual (Part of Optimal Dispatch) Non-Event Regulating Correct the current ACE Reserve Automatic (Within Optimal Dispatch) *Terminology not universal

36 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Few industry working groups in relation to these topics…

▪ CIGRE JWG C2/C4.41 Impact of high penetration of inverter-based generation on system inertia of networks ▪ CIGRE WG C4.56 on Electromagnetic transient simulation models for large-scale system impact studies in power systems having a high penetration of inverter-based resources ▪ CIGRE WG B5.65 Enhancing Protection System Performance by Optimizing the Response of Inverter-Based Sources ▪ IEEE/CIGRE B4.82 Working Group on Use of Real Code in EMT Models for Power System Analysis ▪ IEEE PSDP Task Force on Modeling and Simulation of Large Power Systems with High Penetration of Inverter-Based Generation ▪ IEEE PSRC C32 WG Protection Challenges and Practices for the Interconnection of Inverter Based Generation to Utility Transmission Systems. ▪ WECC Modeling and Validation Work Group (MVWG) – WECC Load Modeling Task Force (LMTF) – WECC Modeling Task Force (REMTF) ▪ NERC Inverter Based Resource Performance Task Force (IRPTF) ▪ NERC Load Modeling Task Force (LMTF) ▪ NERC System Planning Impacts from Distributed Energy Resources Working Group (SPIDERWG)

37 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Questions, comments, and suggestions..?

38 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved. Together…Shaping the Future of Electricity

39 www.epri.com © 2019 Electric Power Research Institute, Inc. All rights reserved.