Electrical Transmission Systems for Large Offshore Wind Farms

Total Page:16

File Type:pdf, Size:1020Kb

Electrical Transmission Systems for Large Offshore Wind Farms ELECTRICAL TRANSMISSION SYSTEMS FOR LARGE OFFSHORE WIND FARMS A THESIS SUBMITTED TO CARDIFF UNIVERSITY FOR THE DEGREE OF D octor of Philosophy Rosemary Louise King February 2011 UMI Number: U567155 All rights reserved INFORMATION TO ALL USERS The quality of this reproduction is dependent upon the quality of the copy submitted. In the unlikely event that the author did not send a complete manuscript and there are missing pages, these will be noted. Also, if material had to be removed, a note will indicate the deletion. Dissertation Publishing UMI U567155 Published by ProQuest LLC 2013. Copyright in the Dissertation held by the Author. Microform Edition © ProQuest LLC. All rights reserved. This work is protected against unauthorized copying under Title 17, United States Code. ProQuest LLC 789 East Eisenhower Parkway P.O. Box 1346 Ann Arbor, Ml 48106-1346 For Abigail A b s t r a c t The large area required for an offshore wind farm along with its location results in extensive cable systems with a large number of radial feeders and step-up transformers. These transmission systems are very different to traditional onshore networks. Offshore wind farms above around 100MW capacity and over 20km from shore will have either AC or DC transmission, at above 132 kV. The capital costs were compared for AC and DC submarine transmission in order to find a break-even point. Over the lifetime of the wind farm, the cost of losses, maintenance and constrained energy was important. A loss-load factor was determined to enable a quick estimation of the annual cost of losses. Suitable models for the simulation of switching transients in offshore wind farms were identified. Simulations of Nysted offshore wind farm were compared with measurements provided by DONG Energy. A Vacuum Circuit Breaker model was developed and validated against the measurements. It was required in order to represent pre-strikes which caused successive waves and increased the overvoltage. The input data for the cable model was validated by examining the cable charging current and propagation speed of the transients. It was shown that the actual insulation thickness and semiconductor thickness of the cable were each 1mm thicker than that stated in the manufacturer’s data sheets. Simulations of switching transients were carried out in EMTP-RV. Overvoltages in offshore wind farms ranged from temporary over voltages to very fast front transients. Transient Recovery Voltages of the offshore circuit breakers exceeded IEC 62271 requirements in some situations. The disconnection of an array following a single phase fault at a wind turbine produced the most severe overvoltages, exceeding IEC 60071 requirements. The overvoltages in the array remained at a very serious level until the wind turbines stopped generating. D e c l a r a t io n D e c l a r a t io n This work has not previously been accepted in substance for any degree and is not concurrently submitted in candidature for any degree. Signed .....................(candidate) Date: 24/02/2011 S t a t e m e n t 1 This thesis is being submitted in partial fulfilment of the requirements for the degree of PhD. Signed .....................(candidate) Date: 24/02/2011 S t a t e m e n t 2 This thesis is the result of my own independent work/investigation, except where otherwise stated. Other sources are acknowledged by explicit references. S igned A k .....................(candidate) Date: 24/02/2011 S t a t e m e n t 3 I hereby give consent for my thesis, if accepted, to be available for photocopying and for inter-library loan, and for the title and summary to be made available to outside organisations. Signed (candidate) Date: 24/02/2011 4 A cknowledgements First and foremost I would like to express my sincere gratitude to my supervisor, Prof. Nick Jenkins. His guidance, encouragement and advice were essential to this work. I would like to thank Prof. Manu Haddad and Dr. Janaka Ekanayake for their help and advice. I would also like to thank Dr. Bieshoy Awad, Dr. Ahmed Shafiu, Mr. Alvaro Hernandez Manchola, Mr. Ivan Arana and Mr. Fabian Moore for the useful discussions we had. I would like to acknowledge the financial support during my PhD studies from ALSTOM GRID Research and Technology Centre, BP Alternative Energy and Cardiff University. I am very grateful for the support and suggestions from Dr. Angelo Amorelli and Dr. Sandra Eager at BP Alternative Energy. I would also like to acknowledge the advice and support from Dr. Liangzhong Yao, Mr. Harmeet Kang and Dr. Jean-Louis Rasolonjanahary at ALSTOM GRID Research and Technology Centre. I am very grateful to DONG Energy, who kindly supplied data from an offshore wind farm which was used in this thesis. I would like to express my gratitude to Dr. Troels Sorensen at DONG Energy. His feedback was of great importance to this work. I would like to thank all my friends whose advice and encouragement were of great importance to my work. I would like to thank Gnanasambandapillai Ramtharan, Nolan Calio, Yan He, Haziah Hamid and Carlos Ugalde for their support. I am also very grateful to Chidinma Agwu, Shazia Mughal, Sarah Williams, Alison Moses, Kate Herbert, Claudia Stem, Nadia Sebai, Yin Tsang, Sara Brumwell, Rebecca Broadhead, Tracey Rous, Leigh Neilan, Karen Di Piazza, Claire Banford and Helen Shaw for their friendship and encouragement. I would like to thank my family for all their love and encouragement. My parents, Jean and Andrew King, have provided help and support in a myriad of ways, including encouraging my interest in science and engineering and supporting my ideas and study. I would like to thank my sister, Jenny King, for being very supportive. To my fiance Martin Urban, thank you for your encouragement, your patience and for the useful discussions. Finally, I would like to thank my daughter, Abigail, for reminding me that there are more important things in life than a PhD thesis. Her joy was contagious, even during tough times in the PhD pursuit. 5 L is t o f P ublications King, R., Moore, F., Jenkins, N., Haddad, A., Griffiths, H., Osborne, M., “ Switching transients in offshore wind farms - impact on the offshore and onshore networks ”, International Power Systems Transients Conference (IPST2011), Delft, the Netherlands, June 14-17, 2011 Chukaluri, E. K., Barker, C., King, R., “A study on some of the important aspects related to feasibility of HVDC grid ”, CIGRE International Symposium “The Electric Power System of the Future - integrating supergrids and microgrids”, Bologna, Italy, September 13-15, 2011 King, R., Yao, L., Kang, H., Rasolonjanahary, J. L., Jenkins, N., “Transient Recovery Voltages in Offshore Wind Farms ”, 9th International Workshop on Large Scale Integration of Wind Power and on Transmission Networks for Offshore Wind Farms; Quebec City, Quebec, Canada, October 18-19, 2010; ISBN: 978-3-9813870- 2-5; Publisher: Energynautics Gomis-Bellmunt, O., Liang, J., Ekanayake, J., King, R., Jenkins, N., “Topologies of multiterminal HVDC-VSC transmission for large offshore wind farms”, Electrical Power Systems Research; Article in Press; Accepted; 8 Sept 2010, Available online; 27 Oct 2010; DOI: 10.1016/j.epsr.2010.09.006; Publisher: Elsevier Ltd King, R., Ekanayake, J. B., “Harmonic modelling of offshore wind farms”, IEEE PES General Meeting “Power Systems Engineering in Challenging Times”, Minneapolis, Minnesota, USA, July 25-29, 2010; Organiser: IEEE King, R., Jenkins, N., “ Switching Transients in Large Offshore Wind Farms”, 7th International Workshop on Large Scale Integration of Wind Power and on Transmission Networks for Offshore Wind Farms, Madrid, Spain, May 26-27, 2008; ISBN: 978-3-9813870-0-1; Publisher: Energynautics 6 C o n t e n t s C o n t e n t s Abstract........................................................................................................................ 3 Declaration ...................................................................................................................4 Acknowledgements...................................................................................................... 5 List of Publications ...................................................................................................... 6 List of Tables ..............................................................................................................12 List of Figures.............................................................................................................14 1. Introduction ....................................................................................................... 21 1.1. Offshore Wind Energy ................................................................................. 21 1.2. Offshore wind farms ......................................................................................21 1.2.1. Offshore Wind Farms in the UK ........................................................... 22 1.3. Transmission options for large offshore wind farms .................................. 23 1.3.1. Medium Voltage AC Transmission......................................................24 1.3.2. High Voltage AC Transmission .............................................................24 1.3.3. HVDC Transmission ............................................................................. 26 1.4. Research Objective ........................................................................................ 27 1.4.1. Main Objectives of the Thesis .................................................................. 27 1.4.2. The
Recommended publications
  • Modeling and Dynamic Analysis of Offshore Wind Farms in France: Impact on Power System Stability
    04/11/2011 Modeling and dynamic analysis of offshore wind farms in France: Impact on power system stability KTH Master Thesis report number Alexandre Henry Examiner at KTH Dr. Luigi Vanfretti Supervisors at KTH Dr. Luigi Vanfretti and Camille Hamon Supervisor at EDF Dr. Bayram Tounsi Laboratory Electric Power Systems School of Electrical Engineering KTH, Royal Institute of Technology Stockholm, November 2011 Accessibility : .. Front page Page I / III ... Modeling and dynamic analysis of offshore wind farms in France: Impact on KTH EPS power system stability - EDF R&D Abstract Alexandre Henry Page 1 / 90 KTH Master Thesis Modeling and dynamic analysis of offshore wind farms in France: Impact on KTH EPS power system stability - EDF R&D Nomenclature EWEA : European Wind Energy Association UK : United Kingdom EU : European union AC : Alternating current DC : Direct current HVAC : High Voltage Alternating Current HVDC : High Voltage Direct Current PCC : Point of Common Coupling TSO : Transmission System Operator RTE : Réseau de transport d’électricité (French TSO) XLPE : cross linked polythylene insulated VSC : Voltage source converter LCC : Line commutated converter FACTS : Flexible AC Transmission System SVC : Static Var Compensator DFIG : Double Fed Induction Generator MVAC : Medium Voltage Alternating Current ENTSO-E : European Network of Transmission System Operators for Electricity HFF : High Frequency Filter FRT : Fault Ride Through Alexandre Henry Page 2 / 90 KTH Master Thesis Modeling and dynamic analysis of offshore wind farms
    [Show full text]
  • Offshore Wind Power Plant Technology Catalogue Components of Wind Power Plants, AC Collection Systems and HVDC Systems
    Offshore Wind Power Plant Technology Catalogue Components of wind power plants, AC collection systems and HVDC systems Kaushik Das, Nicolaos Antonios Cutululis Department of Wind Energy Technical University of Denmark Denmark October, 2017 ǡ ǡ ǣ ǡ ǡ ǡ Ǥ ǣ ሾሿ ǣ ǣ ǯȀǯ Ȁ Ǥ Ǥ Contents 1 Introduction 1 1.1 Motivation . .3 1.2 Outline of the Report . .3 2 Wind Turbines 4 2.1 Description . .4 2.1.1 Doubly-fed Induction Generator (DFIG) based Wind Turbine4 2.1.2 Fully Rated Converter (FRC) based Wind Turbine . .4 2.2 Technical feasibilities . .5 2.3 Stages of Development . .5 2.4 Cost and Lifetime . .5 3 AC Cables 7 3.1 Cross-linked polyethylene (XLPE) cables . .7 3.1.1 Technical feasibilities . .8 3.1.2 Stages of Development . .9 3.1.3 Cost and Lifetime . .9 3.2 High Temperature Superconducting (HTS) cables . .9 3.2.1 Technical feasibilities . 10 3.2.2 Stages of Development . 10 3.2.3 Cost . 10 4 HVDC Cables 11 4.1 Description . 11 4.1.1 Self-Contained Fluid Filled Cables . 11 4.1.2 Mass Impregnated Cables . 11 4.1.3 Cross-Linked Poly-Ethylene Cables . 13 4.2 Technical feasibilities . 13 4.3 Stages of Development . 14 4.4 Cost and Lifetime . 14 5 AC-DC Converters 16 5.1 Line Commutated Converters . 16 5.1.1 Description . 16 5.1.2 Technical feasibilities . 16 5.1.3 Stages of Development . 18 5.1.4 Cost and Lifetime . 18 5.2 Voltage Source Converters . 18 5.2.1 Description .
    [Show full text]
  • OSPAR Database on Offshore Wind-Farms, 2014 Update
    OSPAR database on offshore wind-farms 2014 UPDATE (revised in 2015) Biodiversity Series 2015 OSPAR Convention Convention OSPAR The Convention for the Protection of the La Convention pour la protection du milieu Marine Environment of the North-East marin de l'Atlantique du Nord-Est, dite Atlantic (the “OSPAR Convention”) was Convention OSPAR, a été ouverte à la opened for signature at the Ministerial signature à la réunion ministérielle des Meeting of the former Oslo and Paris anciennes Commissions d'Oslo et de Paris, Commissions in Paris on 22 September 1992. à Paris le 22 septembre 1992. La Convention The Convention entered into force on 25 est entrée en vigueur le 25 mars 1998. March 1998. The Contracting Parties are Les Parties contractantes sont l'Allemagne, Belgium, Denmark, the European Union, la Belgique, le Danemark, l’Espagne, la Finland, France, Germany, Iceland, Ireland, Finlande, la France, l’Irlande, l’Islande, le Luxembourg, Netherlands, Norway, Portugal, Luxembourg, la Norvège, les Pays-Bas, le Spain, Sweden, Switzerland and the United Portugal, le Royaume-Uni de Grande Bretagne Kingdom. et d’Irlande du Nord, la Suède, la Suisse et l’Union européenne. 2 of 17 OSPAR Commission, 2015 OSPAR Database on Offshore Wind-farms – 2014 Update (revised in 2015) The use of any renewable energy source makes a significant contribution towards climate protection and towards placing our energy supply on a sustainable ecological footing, thereby helping to conserve the natural balance. Nevertheless, the utilisation of renewable sources of energy can also have an adverse impact on the environment and our natural resources. Since 2001, OSPAR and its Biodiversity Committee (BDC) have been noting that the offshore wind energy sector has been rapidly expanding in the OSPAR maritime area.
    [Show full text]
  • Assessment of Vessel Requirements for the U.S. Offshore Wind Sector
    Assessment of Vessel Requirements for the U.S. Offshore Wind Sector Prepared for the Department of Energy as subtopic 5.2 of the U.S. Offshore Wind: Removing Market Barriers Grant Opportunity 24th September 2013 Disclaimer This Report is being disseminated by the Department of Energy. As such, the document was prepared in compliance with Section 515 of the Treasury and General Government Appropriations Act for Fiscal Year 2001 (Public Law 106-554) and information quality guidelines issued by the Department of Energy. Though this Report does not constitute “influential” information, as that term is defined in DOE’s information quality guidelines or the Office of Management and Budget's Information Quality Bulletin for Peer Review (Bulletin), the study was reviewed both internally and externally prior to publication. For purposes of external review, the study and this final Report benefited from the advice and comments of offshore wind industry stakeholders. A series of project-specific workshops at which study findings were presented for critical review included qualified representatives from private corporations, national laboratories, and universities. Acknowledgements Preparing a report of this scope represented a year-long effort with the assistance of many people from government, the consulting sector, the offshore wind industry and our own consortium members. We would like to thank our friends and colleagues at Navigant and Garrad Hassan for their collaboration and input into our thinking and modeling. We would especially like to thank the team at the National Renewable Energy Laboratory (NREL) who prepared many of the detailed, technical analyses which underpinned much of our own subsequent modeling.
    [Show full text]
  • Nummer 30/16 27 Juli 2016 Nummer 30/16 2 27 Juli 2016
    Nummer 30/16 27 juli 2016 Nummer 30/16 2 27 juli 2016 Inleiding Introduction Hoofdblad Patent Bulletin Het Blad de Industriële Eigendom verschijnt The Patent Bulletin appears on the 3rd working op de derde werkdag van een week. Indien day of each week. If the Netherlands Patent Office Octrooicentrum Nederland op deze dag is is closed to the public on the above mentioned gesloten, wordt de verschijningsdag van het blad day, the date of issue of the Bulletin is the first verschoven naar de eerstvolgende werkdag, working day thereafter, on which the Office is waarop Octrooicentrum Nederland is geopend. Het open. Each issue of the Bulletin consists of 14 blad verschijnt alleen in elektronische vorm. Elk headings. nummer van het blad bestaat uit 14 rubrieken. Bijblad Official Journal Verschijnt vier keer per jaar (januari, april, juli, Appears four times a year (January, April, July, oktober) in elektronische vorm via www.rvo.nl/ October) in electronic form on the www.rvo.nl/ octrooien. Het Bijblad bevat officiële mededelingen octrooien. The Official Journal contains en andere wetenswaardigheden waarmee announcements and other things worth knowing Octrooicentrum Nederland en zijn klanten te for the benefit of the Netherlands Patent Office and maken hebben. its customers. Abonnementsprijzen per (kalender)jaar: Subscription rates per calendar year: Hoofdblad en Bijblad: verschijnt gratis Patent Bulletin and Official Journal: free of in elektronische vorm op de website van charge in electronic form on the website of the Octrooicentrum Nederland.
    [Show full text]
  • Offshore Wind Market and Economic Analysis
    Offshore Wind Market and Economic Analysis Annual Market Assessment Prepared for: U.S. Department of Energy Client Contact Michael Hahn, Patrick Gilman Award Number DE-EE0005360 Navigant Consulting, Inc. 77 Bedford Street Suite 400 Burlington, MA 01803-5154 781.270.8314 www.navigant.com February 22, 2013 U.S. Offshore Wind Market and Economic Analysis Annual Market Assessment Document Number DE-EE0005360 Prepared for: U.S. Department of Energy Michael Hahn Patrick Gilman Prepared by: Navigant Consulting, Inc. Lisa Frantzis, Principal Investigator Lindsay Battenberg Mark Bielecki Charlie Bloch Terese Decker Bruce Hamilton Aris Karcanias Birger Madsen Jay Paidipati Andy Wickless Feng Zhao Navigant Consortium Member Organizations Key Contributors American Wind Energy Association Jeff Anthony and Chris Long Great Lakes Wind Collaborative John Hummer and Victoria Pebbles Green Giraffe Energy Bankers Marie DeGraaf, Jérôme Guillet, and Niels Jongste National Renewable Energy Laboratory Eric Lantz Ocean & Coastal Consultants (a COWI company) Brent D. Cooper, P.E., Joe Marrone, P.E., and Stanley M. White, P.E., D.PE, D.CE Tetra Tech EC, Inc. Michael D. Ernst, Esq. Offshore Wind Market and Economic Analysis Page ii Document Number DE-EE0005360 Notice and Disclaimer This report was prepared by Navigant Consulting, Inc. for the exclusive use of the U.S. Department of Energy – who supported this effort under Award Number DE-EE0005360. The work presented in this report represents our best efforts and judgments based on the information available at the time this report was prepared. Navigant Consulting, Inc. is not responsible for the reader’s use of, or reliance upon, the report, nor any decisions based on the report.
    [Show full text]
  • Changing the Scale of Offshore Wind Examining Mega-Projects in the United Kingdom Contents
    Changing the Scale of Offshore Wind Examining Mega-Projects in the United Kingdom Contents 1 Offshore wind ‘mega-projects’ in the 3 United Kingdom 1.1 Market context: Offshore wind in the United Kingdom 5 The Electricity Market Reform white paper 9 The Renewables Obligation (RO) Scheme: Already a billion- 9 pound market 1.2 Costs and timelines for offshore wind projects 11 1.3 Mega-projects as a key driver of competitiveness 13 Leading practices in capital projects management 17 2 Key challenges for offshore wind 19 mega-projects 2.1 Turbine supply chain 21 Case study: Forewind 25 2.2 Vessel contracting 27 Case study: SeaEnergy PLC 29 2.3 Development and HSE: Leveraging the experience 33 of offshore oil and gas Case study: Offshore wind: A perspective from oilfield 35 services companies 2.4 Grid integration of offshore wind 39 Natural gas as the current technology of choice for 42 backup of intermittent generation 2.5 Other considerations and challenges 45 3 Conclusions 47 Implications for key players 50 4 Glossary 53 5 Authors 54 6 Reference 55 1 2 1 Offshore wind ‘mega-projects’ in the United Kingdom 3 4 1.1 Market context: Offshore wind in the United Kingdom Wind is one of the United Kingdom’s The UK government has adopted a Providing financial support for (UK) most plentiful renewable energy series of policy measures to stimulate renewables. In the summer of 2011, resources. Studies show that, as a the progressive deployment of offshore the UK government published the nation, the UK has the most favourable wind which, alongside other renewable Electricity Market Reform (EMR) conditions for offshore wind power energies, is expected to play a crucial white paper9 (see sidebar on page generation in Europe and perhaps role in attaining these challenging 9).
    [Show full text]
  • Development of Next Generation 2MW Class Large Wind Turbines
    Development of Next Generation 2MW Class Large Wind Turbines YOSHINORI UEDA*1 MASAAKI SHIBATA*2 Wind power generation has come to be used widely in the world as a key role for preventing global warming. Accord- ingly, the wind turbines are getting larger rapidly and higher in performance. Mitsubishi Heavy Industries, Ltd. (MHI) is also developing a new type high-performance wind turbine MWT92/2.4. Its rated output is 2400 kW and diameter is 92 m. The new first turbine is expected to start in operation next year in Yokohama. Described below is the new technology applied for MWT92/2.4. The main purpose is to reduce the load exerted on the wind turbine. get larger rapidly mainly in Europe to reduce construc- 1. Introduction tion costs (Fig. 3).3 The rated output increased to double Wind power generation is drawing attention as a key in about 4 years during these ten years. This shows a role to prevent global warming. The wind power in the rapid increase of several times in terms of the conven- world reached to 40.3 GW at the end of 2003 (Fig. 11). tional thermal power generation. The introduction of 2 And wind power in Japan reached to 730 MW with about MW-class wind turbines started in Japan in March 800 units (Fig. 22). 2003, and 15 units of them are already in operation With the increase of wind power, the wind turbines (Table 11). 10 50 400 800 : Single-year : Single-year : Cumulative : Cumulative 8 40 300 600 6 30 200 400 4 20 Cumulative (MW) Cumulative Per-year (MW) Per-year Per year (GW) year Per Cumulative (GW) Cumulative 100 200 2 10 0 0 0 0 '90 '92 '94 '96 '98 '00 '02 '90 '92 '94 '96 '98 '00 '02 Year Ye a r Fig.
    [Show full text]
  • Accelerating South Korean Offshore Wind Through Partnerships, May 2021 3
    ACCELERATING A SCENARIO-BASED SOUTH KOREAN STUDY OF SUPPLY CHAIN, LEVELIZED COST OF ENERGY OFFSHORE WIND AND EMPLOYMENT EFFECTS THROUGH MAY 2021 PARTNERSHIPS Published on behalf of the The sponsors would like to thank Embassy of Denmark in Korea, the following institutions the Danish Energy Agency and the for their review of this study: Netherlands Ministry of Foreign Aff airs. EMBASSY OF DENMARK EMBASSY Seoul OF DENMARK Seoul EMBASSY OF DENMARK EMBASSY Seoul OF DENMARK Seoul EMBASSY OF DENMARK EMBASSY Seoul OF DENMARK Seoul This report is authored by: Aegir Insights helps strategic COWI A/S is a leading Pondera is an international decision-making in the off shore international consulting group renewable energy consultant wind industry through data- within engineering, economics based in the Netherlands. Since driven research and advanced and environmental science. the start of the company in 2007, analytics solutions. Aegir Insights Founded in Denmark in 1930, Pondera advises, develops and is founded by industry experts COWI is dedicated to creating co-invests in renewable energy with leading experience in coherence in tomorrow’s projects. Our in-depth expertise market strategy and investment sustainable societies. We deliver and experience also enable us to decisions, which it applies to help 360° solutions for off shore wind advise policymakers in drawing leading developers, investors and ranging from market advisory to up sustainable energy policies governments maximize value of foundation design. that are in line with daily practice. their off shore wind investments. DISCLAIMER: This publication is for informational purposes only and does not contain or convey legal, fi nancial or engineering advice.
    [Show full text]
  • WIND ENERGY FUTURE in ASIA 2011: Wind Energy Data and Information for 15 Countries
    WIND ENERGY FUTURE IN ASIA 2011: Wind Energy Data and Information for 15 Countries Wind Energy Future in Asia A Compendium of Wind Energy Resource Maps, Project Data and Analysis for 17 Countries in Asia and the Pacific 2 Mongolia Pakistan Philippines Afghanistan Sri Lanka Bangladesh South Korea China Thailand Fiji Timor-Leste Japan Vietnam India Indonesia Kazakhstan Maldives Full Report, August 2012 Wind power has experienced 26% annual growth in cumulative installations worldwide in the past 5 years and is expected to grow at 16% per annum in the next 5 years, despite increasingly turbulent economic conditions in the short term. Since 2010, Asia has been at the forefront of this growth, as wind energy installations in the region have outstripped both North America and Europe. While China and India have been the main drivers of growth, the projected investments in wind projects in the rest of Asia are expected to exceed US$50 billion between 2012 and 2020. Realizing the full potential of wind energy in the region, however, will require long-term, consistent policies and upgraded transmission and grid infrastructure. 1 TABLE OF CONTENTS Acknowledgements .................................................................................................................... 3 Preface ...................................................................................................................................... 4 Executive Summary ..................................................................................................................
    [Show full text]
  • From Feasibility Studies to Rapid Environmental Assessments, We
    Civil Engineering & Eco-Technology Group Civil Engineering & Eco-Technology Group 建設環境研究所 株式会社 建設環境研究所 Civil Engineering & Eco-Technology Consultants Co., Ltd. Civil Engineering & Eco-Technology Consultants Co., Ltd. [ Head Office (Contact) ] +81 3 3988 2643 三洋テクノマリン [email protected] Sanyo Techno Marine Inc. 2-23-2 Higashi Ikebukuro, Toshima-ku, Tokyo 170-0013, Japan Representatives: Mr. Wakamatsu, Mr. Matsuda,and Mr. Kobayashi Branches: Sapporo, Tohoku, Tokyo, Center for Environmental Science From feasibility studies to rapid environmental assessments, and Technology (Omiya), Niigata, Chubu, Osaka, Takamatsu, Kyushu, Okinawa, 25 Sales Offices and 2 Offices [ Center for Environmental Science and Technology ] we provide ‘one-stop’ solutions for the 1-268-1 Kushihiki-cho, Omiya-ku, Saitama 330-0851, Japan Activities: offshore wind power industry Air, soil, water, and sediment quality, noise, vibration, waste, biological, odor, pesticide, asbestos, dioxin, and environmental measurements. [ ISO Certification ] ISO9001 [ KES Certification ] KES Step 1 Holder: Head Office (Tokyo) Center for Environmental Science and Technology(Saitama) Major membership group 三洋テクノマリン 株式会社 Japan Wind Power Association Sanyo Techno Marine Inc. The Japan Civil engineering Consultants Association [ Head Office (Contact) ] +81 3 3666 3149 Japan Association of Environment Assessment The Ports & Harbors Association of Japan [email protected] Japan Environmental Measurement and Chemical Analysis Association 1-3-17 Nihonbashi Horidome-cho, Chuo-ku, Tokyo 103-0012,
    [Show full text]
  • The European Offshore Wind Industry - Key Trends and Statistics 1St Half 2013
    The European offshore wind industry - key trends and statistics 1st half 2013 The European offshore wind industry - key trends and statistics 1st half 2013 1 Mid-Year European offshore wind energy statistics In the first six months of 2013, Europe fully grid connected 277 offshore wind turbines, with a combined capacity totalling over 1 GW. Overall, 18 wind farms were under construction. Once completed these wind farms will have a total capacity of 5,111 MW. New offshore capacity installations during the first half of 2013 doubled compared to the same period the previous year and was just 121 MW less than total 2012 installations. Figure 1: AnnuAl instAlled oFFshore wind cApAcity in europe (Mw) 1400 1200 1000 800 600 400 200 0 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 H1 Full year Source: EWEA The work carried out on these wind farms during the • 254 turbines (43 units or 20% more than during first six months of 2013 is detailed below: the same period last year) were erected in 10 wind farms: Thornton Bank (BE), Gunfleet Sands 3 (UK), • 277 wind turbines were fully grid connected, Lincs (UK), Gwynt y Môr (UK), Teesside (UK), Anholt totalling 1,045 MW (up 522 MW or double (DK), Bard (DE), Riffgat (DE), Kårehamn (SE), Arinaga installations during the same period last year) in Quay (ES). seven wind farms: Thornton Bank (BE), Gunfleet Sands 3 (UK), Lincs (UK), London Array (UK), Teesside • Preparatory work has begun in three further wind (UK), Anholt (DK), BARD Offshore 1 (DE).
    [Show full text]