Executive Committee Meeting #5/10

Chair: Gerri Lynn O'Connor Vice Chair: Maria Augimeri Members: David Barrow Gay Cowbourne Glenn De Baeremaeker Suzan Hall Jack Heath Colleen Jordan Ron Moeser Anthony Perruzza Maja Prentice Richard Whitehead

July 9, 2010 9:30 A.M. VICTORIA ROOM, PIONEER VILLAGE

AGENDA Pages EX1. MINUTES OF MEETING #4/10, HELD ON JUNE 4, 2010 Minutes Summary Enclosed Herewith on PINK

EX2. BUSINESS ARISING FROM THE MINUTES

EX3. DISCLOSURE OF PECUNIARY INTEREST AND THE GENERAL NATURE THEREOF

EX4. DELEGATIONS

EX5. PRESENTATIONS

EX6. CORRESPONDENCE

1 EX7. SECTION I - ITEMS FOR AUTHORITY ACTION

EX7.1 GREENLANDS ACQUISITION PROJECT FOR 2006-2010 Flood Plain and Conservation Component, Creek Watershed 1672500 Limited CFN 44289 31

EX7.2 CITY OF Request for a Permanent Easement for Two Storm Sewer Outlets Watershed, City of Toronto ( Community Council Area) CFN 42854 34

EX7.3 REQUEST FOR DISPOSAL OF TORONTO AND REGION CONSERVATION AUTHORITY LAND North of King Street East, east of Old King Road (rear of 269 King Street East - Bolton) CFN 42978 38

EX7.4 ASSOCIATION OF MUNICIPALITIES OF ONTARIO POSITION PAPER Joint and Several Liability 42

EX8. SECTION II - ITEMS FOR EXECUTIVE ACTION

EX8.1 SOLARCITY TECHNOLOGY ASSESSMENT PARTNERSHIP Award of Sole Source Contract 44

EX8.2 ONTARIO MUNICIPAL BOARD HEARING 35 Don River Boulevard, City of Toronto 46

EX9. SECTION IV - ITEMS FOR THE INFORMATION OF THE BOARD

EX9.1 GREENLANDS ACQUISITION PROJECT FOR 2006-2010 Flood Plain and Conservation Component, Mimico Creek Watershed Purchase of Land - Toronto District School Board CFN 43339 50

EX9.2 LOWEST BID NOT ACCEPTED Fish Food Glen Haffy Conservation Area 52

EX9.3 LOWEST BID NOT ACCEPTED Vault Toilet and Building Septic Tank Pumping 55

2 EX10. ONTARIO REGULATION 166/06

CITY OF BRAMPTON

EX10.1 BELL To construct, reconstruct, erect or place a building or structure and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on The Gore Road north of Castlemore Road in the City of Brampton, Humber River Watershed as located on the property owned by Region of Peel. The purpose is to install (4)100 mm HDPE ducts under the West Humber River on The Gore Road north of Castlemore Road. The warmwater timing window will apply to works. The proponent will be using the Fisheries and Oceans Canada (DFO) Operational Statement for Horizontal Directional Drilling (HDD). 58

EX10.2 CITY OF BRAMPTON To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on Glidden Road between Heart Lake Road and Rutherford Road in the City of Brampton, Creek Watershed as located on the property owned by City of Brampton. The purpose is to replace a two CSP culverts as well as remove existing gabion baskets and replace them with armour stone on Gildden Road between Heart Lake Road and Rutherford Road. The warmwater fisheries timing window will be applied and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO). 60

EX10.3 CITY OF BRAMPTON To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere, alter a shoreline and alter a watercourse on the west side of the north pond in Chinguacousy Park, City of Brampton, Etobicoke Creek Watershed, as located on property owned by the City of Brampton. The purpose is to construct a park pavilion/boathouse and boat deck on the west side of the north pond in Chinguacousy Park. The warmwater fisheries timing window will be applied to this project and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO). 62

EX10.4 ENBRIDGE GAS DISTRIBUTION INC. To construct, reconstruct, erect or place a building or structure and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on , the south side of Hansen Road, approximately 203 m east of in the City of Brampton, Etobicoke Creek Watershed as located on the property owned by The City of Brampton under Franchise Agreement with Enbridge Gas Distribution Inc. The purpose is to install a gas pipeline under a tributary of Etobicoke Creek on the south side of Hansen Road, approximately 203 m east of Queen Street. TRCA staff will prepare a Letter of Advice on behalf of Fisheries and Oceans Canada (DFO). No in-water works will take place as part of this proposal. 65 3 EX10.5 10 EDGE FOREST DRIVE To construct, reconstruct, erect or place a building or structure on Lot 9, Concession 9, (10 Edge Forest Drive), in the City of Brampton, Humber River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a replacement septic system at the rear of an existing dwelling associated with a municipal building permit. 66

EX10.6 REGIONAL MUNICIPALITY OF PEEL To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units on Part Lot 5, Concession 1 Part 2 Plan 43R-11915, (3, 5, 7, 9 Wellington Street East), in the City of Brampton, Etobicoke Creek Watershed as located on the property owned by Regional Municipality of Peel. The purpose is to undertake works within a TRCA Regulated Area to facilitate the construction of a below ground walkway within the Regional Storm Floodplain. 68

EX10.7 SUNRISE AUTO To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units at 2 Hale Road, in the City of Brampton, Etobicoke Creek Watershed as located on the property owned by Sunrise Auto. The purpose is to undertake works within a TRCA Regulated Area of the Etobicoke Creek Watershed in order to facilitate an addition to the rear of an existing industrial building. 71

CITY OF MISSISSAUGA

EX10.8 CITY OF MISSISSAUGA To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material originating on the site or elsewhere and alter a watercourse at Little Etobicoke Creek near Loreland Avenue, in the City of Mississauga, Etobicoke Creek Watershed, as located on property owned by the City of Mississauga. The purpose is to remove a broken section of storm outlet pipe located within the Little Etobicoke Creek Valley, and repair the area around the outlet with armourstones. Since this was completed as an emergency works, an extension to the warmwater fisheries timing window was granted. A Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO). 72

CITY OF TORONTO [ETOBICOKE YORK COMMUNITY COUNCIL AREA]

EX10.9 65 OAKFIELD DRIVE To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Part Lot 6, 10, Plan 718, (65 Oakfield Drive), in the City of Toronto (Etobicoke York Community Council Area), Mimico Creek Watershed. The purpose is to construct a single family dwelling. 74 4 EX10.10 THE RIVERHOUSE AT THE OLD MILL LIMITED To construct, reconstruct, erect or place a building or structure and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Part Lot 21, 22, 5, 6, 7, 8, Plan M-416, (30 Old Mill Road), in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed as located on the property owned by The Riverhouse at the Old Mill Limited. The purpose is to locate a condominium sales trailer and conduct minor excavation for an archaeological study. 76

EX10.11 WESTON GOLF AND COUNTRY CLUB To construct, reconstruct, erect or place a building or structure on Lot 22, Concession C, (50 St. Philips Road), in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed as located on the property owned by Weston Golf and Country Club. The purpose is to construct an outdoor kitchen and arbour addition to the existing clubhouse building at 50 St. Phillips Road in the City of Toronto (Etobicoke York Community Council Area). 78

CITY OF TORONTO [NORTH YORK COMMUNITY COUNCIL AREA]

EX10.12 CITY OF TORONTO To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on , (Finch Avenue), in the City of Toronto (North York Community Council Area), Don River Watershed as located on the property owned by City of Toronto. The purpose is to decommission an existing storm sewer and construct two new storm sewer outlets. 80

EX10.13 CITY OF TORONTO To construct, reconstruct, erect or place a building or structure, site grade and alter a watercourse on Part Block C, Plan 5544, (11 Valley Woods Road), in the City of Toronto (North York Community Council Area), Don River Watershed as located on the property owned by City of Toronto. The purpose is to develop within a Regulated Area of the Don River watershed to facilitate construction of a new splash-pad, and renovation of an existing playground at Brookbanks Park. 82

EX10.14 14 BRENDAN ROAD To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units on Lot 7, Plan 2566, (14 Brendan Road), in the City of Toronto (North York Community Council Area), Don River Watershed. The purpose is to develop within a Regulated Area of the Don River watershed to facilitate construction of a sunroom addition to the rear of the existing dwelling. 84

5 EX10.15 6 KING MAPLE PLACE To construct, reconstruct, erect or place a building or structure on Lot 248, Plan 66M-677, (6 King Maple Place), in the City of Toronto (North York Community Council Area), Don River Watershed. The purpose is to develop within a Regulated Area of the Don River watershed to facilitate construction of a replacement two-storey dwelling. 85

EX10.16 30 GLENORCY ROAD To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 30, Plan M809, (30 Glenorchy Road), in the City of Toronto (North York Community Council Area), Don River Watershed. The purpose is to develop within a Regulated Area of the Don River watershed to facilitate construction of a replacement two-storey dwelling. 87

EX10.17 84 BRAESIDE ROAD To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units on Part Lot 11, Plan 2473, (84 Braeside Road), in the City of Toronto (North York Community Council Area), Don River Watershed. The purpose is to develop within a Regulated Area of the Don River watershed to facilitate construction of a two-storey addition above, and a three-storey addition to the side of the existing dwelling. 88

CITY OF TORONTO [SCARBOROUGH COMMUNITY COUNCIL AREA]

EX10.18 41 LYNNDALE ROAD To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units on Lot 43, Plan 3227, (41 Lynndale Road), in the City of Toronto (Scarborough Community Council Area), Waterfront Watershed. The purpose is to develop within a Regulated Area of the Lake Ontario waterfront to facilitate construction of a one-storey addition to the rear, and a one-storey addition to the rear and side of the existing dwelling. 90

EX10.19 117 COLONEL DANFORTH TRAIL To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 41, Plan 2546, (117 Colonel Danforth Trail), in the City of Toronto (Scarborough Community Council Area), Highland Creek Watershed. The purpose is to develop within a Regulated Area of the Highland Creek watershed to facilitate construction of a replacement dwelling. 91

6 EX10.20 LE ROSA ESTATES LTD. To construct, reconstruct, erect or place a building or structure on Lot 468, Plan 1566, (117 Chine Drive), in the City of Toronto (Scarborough Community Council Area), Waterfront Watershed as located on the property owned by Le Rosa Estates Ltd.. The purpose is to develop within a Regulated Area of the Lake Ontario waterfront to facilitate construction of a replacement two-storey dwelling. 93

CITY OF TORONTO [TORONTO AND EAST YORK COMMUNITY COUNCIL AREA]

EX10.21 607 RUSHTON ROAD To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 2, Plan 2612, (607 Rushton Road), in the City of Toronto (Toronto and East York Community Council Area), Don River Watershed. The purpose is to construct an at grade dry lay flagstone patio (5.2m x 4.0m) and a water feature in the rear yard of the existing single family detached dwelling at 607 Rushton Road in the City of Toronto (Toronto and East York Community Council Area). 95

EX10.22 108 LANGDEN AVENUE To construct, reconstruct, erect or place a building or structure on Lot 3, Plan 1134, (108 Langden Avenue), in the City of Toronto (Toronto and East York Community Council Area), Humber River Watershed. The purpose is to construct a covered verandah on top of the existing concrete porch to the front of the existing single storey semi-detached dwelling at 108 Langden Avenue in the City of Toronto (Etobicoke York Community Council Area).96

EX10.23 MONTCREST PRIVATE SCHOOL To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 15, 16, Part Block A, Plan 274-E, (658 Broadview Avenue), in the City of Toronto (Toronto and East York Community Council Area), Don River Watershed as located on the property owned by Montcrest Private School. The purpose is to construct a "natural" playground area at Montcrest Private School municipally described 658 Broadview Avenue in the City of Toronto (Toronto and East York Community Council Area). The existing playground area is to be removed. 98

EX10.24 MOUNT PLEASANT GROUP OF CEMETERIES To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Part Lot 19, Concession 3 FTB, (375 Mount Pleasant Road), in the City of Toronto (Toronto and East York Community Council Area), Don River Watershed as located on the property owned by Mount Pleasant Group of Cemeteries. The purpose is to construct a family mausoleum at Mount Pleasant Cemetery on lands municipally described 375 Mount Pleasant Road in the City of Toronto (Toronto and East York Community Council Area). 100 7 CITY OF VAUGHAN

EX10.25 CANADIAN PACIFIC RAILWAY To construct, reconstruct, erect or place a building or structure and site grade on , (60 Burwick Avenue), in the City of Vaughan, Humber River Watershed as located on the property owned by Canadian Pacific Railway. The purpose is to conduct grading works associated with the construction of a replacement headwall / outfall structure within a Regulated Area of the Humber River watershed adjacent to 60 Burwick Avenue in the City of Vaughan. 102

EX10.26 CITY OF VAUGHAN To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere in a Regulated Area on Martin Grove Road (Highway 7 to north of Woodbridge Avenue), in the City of Vaughan, Regional Municipality of York, Humber River Watershed as located on property owned by the City of Vaughan. The purpose is to construct a replacement watermain within a cold water fisheries timing window. The proponent has committed to using the Fisheries and Oceans Canada (DFO) Operational Statement for High-Pressure Directional Drilling for the project. 104 EX10.27 CITY OF VAUGHAN To site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere in a Regulated Area near Glen Shields Avenue, west of Dufferin Street, in the City of Vaughan, Regional Municipality of York, Don River Watershed as located on property owned by the City of Vaughan. The purpose is to remove sediment from a stormwater management pond to mitigate the impacts of sediment on the downstream receiving watercourse within a warm water fisheries timing window. A Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO) for this project. 106

EX10.28 FERNBOOK HOMES (2005) LIMITED To construct, reconstruct, erect or place a building or structure and site grade on Lot 16, Concession 2, (441 Marc Santi Boulevard), in the City of Vaughan, Don River Watershed as located on the property owned by Fernbook Homes (2005) Limited. The purpose is to conduct site grading and construct a rear yard deck associated with the construction of a new dwelling within a Regulated Area of the Don River watershed at 441 Marc Santi Boulevard in the City of Vaughan. 108

EX10.29 290 NASHVILLE ROAD To construct, reconstruct, erect or place a building or structure and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 24, 25, Concession 8, 9, (290 Nashville Road), in the City of Vaughan, Humber River Watershed. The purpose is to construct a cabana within a Regulated Area of the Humber River Watershed at 290 Nashville Road in the City of Vaughan. 109 8 EX10.30 156 RIVERSIDE DRIVE To construct, reconstruct, erect or place a building or structure on Lot 25, Plan M-111, (156 Riverside Drive), in the City of Vaughan, Humber River Watershed. The purpose is to construct a replacement home within a Regulated Area of the Humber River watershed at 156 Riverside Drive in the City of Vaughan. 111

EX10.31 181 RANCH TRAIL ROAD To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 9, Plan M89, (181 Ranch Trail Road), in the City of Vaughan, Humber River Watershed. The purpose is to construct an inground pool, cabana and patio area within a Regulated Area of the Humber River watershed at 181 Ranch Trail Road in the City of Vaughan. 113

EX10.32 9652 KEELE STREET To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on , (9652 Keele Street), in the City of Vaughan, Don River Watershed. The purpose is to construct an inground pool within Regulated Area of the Don River watershed at 9652 Keele Street in the City of Vaughan. 115

EX10.33 YORK REGION DISTRICT SCHOOL BOARD To construct, reconstruct, erect or place a building or structure and site grade on Lot 6, Concession 7, (60 Burwick Avenue), in the City of Vaughan, Humber River Watershed as located on the property owned by York Region District School Board. The purpose is to construct a replacement headwall / outfall structure within a Regulated Area of the Humber River watershed at 60 Burwick Avenue in the City of Vaughan. 117

TOWN OF CALEDON

EX10.34 16358 HUMBER STATION ROAD To construct, reconstruct, erect or place a building or structure and site grade on Lot 22, Concession 4, (16358 Humber Station Road), in the Town of Caledon, Humber River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a replacement septic system at the rear of an existing dwelling associated with a municipal building permit. 119

EX10.35 40 JOHN STREET To construct, reconstruct, erect or place a building or structure on Lot 80, Block 1, Plan BOL-7, (40 John Street), in the Town of Caledon, Humber River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of an in-ground swimming pool at the rear of an existing dwelling associated with a municipal building permit. 121

9 EX10.36 436 KING STREET EAST To construct, reconstruct, erect or place a building or structure and site grade on , (436 King Street East), in the Town of Caledon, Humber River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a replacement septic system adjacent to an existing residential dwelling associated with a municipal building permit. 123

TOWN OF MARKHAM

EX10.37 93 MAIN STREET To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units on Part Lot 2, Plan RP445, (93 Main Street), in the Town of Markham, Rouge River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed to raise the finished flood elevation of an existing dwelling 0.6m and fix the existing foundation. 124

EX10.38 REGIONAL MUNICIPALITY OF YORK To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on , (South West Corner of Major Mackenzie and Warden Avenue), in the Town of Markham, Rouge River Watershed as located on the property owned by Regional Municipality of York. The purpose is to reconstruct an eroded outfall through constructing structures (new storm sewer outfall, armourstone wall, concrete headwall, new rip rap outfall) within a Regional Storm Floodplain; to site grade and place material (for access route, existing rip rap outfall removal, catch basin and corrugated steel pipe removal and rock removal from creek bed) in a Regulated Area; and to temporarily alter a watercourse (Berczy Creek ) during the redside dace timing window to facilitate the outfall reconstruction in the dry and to remove the rocks by hand from the creek. A Letter of Advice will be issued by TRCA staff on behalf of Fisheries and Oceans Canada. 127

TOWN OF WHITCHURCH-STOUFFVILLE

EX10.39 95 CEDAR RIDGE ROAD To construct, reconstruct, erect or place a building or structure on Lot 9, Plan 65M-3909, (95 Cedar Ridge Road), in the Town of Whitchurch-Stouffville, Rouge River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed in order to facilitate the construction of a dwelling on a vacant lot. \129

10 TOWNSHIP OF KING

EX10.40 12855 HIGHWAY 27 SOUTH To construct, reconstruct, erect or place a building or structure on Part Lot 4, 5, Concession 8, (12855 Highway 27 South), in the Township of King, Humber River Watershed. The purpose is to construct a replacement detached garage within a Regulated Area of the Humber River watershed at 12855 Highway 27 in the Township of King. 131

EX10.41 69 LYNWOOD CRESCENT To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Part Lot 28, 29, Plan 457, (69 Lynwood Crescent), in the Township of King, Humber River Watershed. The purpose is to construct a second floor addition and a garage addition to the front of an existing dwelling within a Regulated Area of the Humber River watershed at 69 Lynwood Crescent in the Township of King. 132

EX10.42 KING NORTH DEVELOPMENTS CR INC. To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on Part Lot 6, Concession 3, (north of King Road, west of Dufferin Street), in the Township of King, Humber River Watershed as located on the property owned by King North Developments CR Inc. The purpose is to install a sanitary sewer line under a tributary of the Humber River, in order to provide servicing for a proposed residential subdivision known as King North, located northwest of King Road and Dufferin Street, in the Township of King. 134

EX10.43 141 KINGSCROSS DRIVE To site grade at 141 Kingscross Drive, in the Township of King, Humber River Watershed. The purpose is to construct a replacement septic system within a Regulated Area of the Humber River watershed at 141 Kingscross Drive in the Township of King. 136

PERMIT APPLICATIONS EX10.44 - EX10.65 ARE ERRATA ITEMS:

CITY OF BRAMPTON

EX10.44 CITY OF BRAMPTON To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material originating on the site or elsewhere on McVean Drive approximately 300 metres north of Cottrelle Boulevard in the City of Brampton, Humber River Watershed, as located on property under a permanent easement (location of outlet structure) and temporary easement (drainage area) agreement with the City of Brampton. The purpose is to construct a channel outfall at McVean Drive approximately 300 m north of Cottrelle Boulevard. No in-water works will take place. 138 11 EX10.45 REGIONAL MUNICIPALITY OF PEEL To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on , (The Gore Road from Cottrelle Boulevard to Castlemore Road), in the City of Brampton, Humber River Watershed as located on the property owned by Regional Municipality of Peel. The purpose is to widen The Gore Road from Cottrelle Boulevard to Castlemore Road. A storm sewer system will be constructed as part of the road improvements and the existing Wylie's South and Wylie's North bridges will both be extended on the west side. The warmwater fisheries timing window will be applied to this project and a Letter of Advice written by TRCA on behalf of Fisheries and Oceans Canada (DFO). 140

EX10.46 REGIONAL MUNICIPALITY OF PEEL To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material originating on the site or elsewhere and alter a watercourse along The Gore Road, just north of Castlemore Road, in the City of Brampton, Humber River Watershed, as located on property owned by the Regional Municipality of Peel. The purpose is to widen The Gore Road from the intersection at Castlemore Road to just north of Castlemore Road. A storm sewer system will be constructed as part of the road improvements and the existing Castlemore bridge located along The Gore Road will be extended on either side. The warmwater fisheries timing window will be applied to this project and a Letter of Advice written by TRCA on behalf of Fisheries and Oceans Canada (DFO). 142 CITY OF MISSISSAUGA

EX10.47 REGIONAL MUNICIPALITY OF PEEL To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere approximately 200 m East of Ponytrail Drive on Burnhamthorpe Road in the City of Mississauga, Etobicoke Creek Watershed as located on the property owned by Regional Municipality of Peel. The purpose is to The Region of Peel is proposing the replacement of an existing 150 mm watermain on Burnhamthorpe Road East with a new 300 mm watermain. The warmwater fisheries timing window will be applied to this project and a Letter of Advice will be written by TRCA on behalf of Fisheries and Oceans Canada (DFO). 143

12 CITY OF TORONTO [ETOBICOKE YORK COMMUNITY COUNCIL AREA]

EX10.48 BROADWAY HOMES To construct, reconstruct, erect or place a building or structure, change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 28, Plan 5773, (53 Edenbrook Hill), in the City of Toronto (Etobicoke York Community Council Area), Etobicoke Creek Watershed as located on the property owned by Broadway Homes. The purpose is to construct a new two-storey single family detached dwelling with integral garage and indoor pool at 53 Edenbrook Hill in the City of Toronto (Etobicoke York Community Council Area). The existing dwelling is to be demolished. 145

EX10.49 CITY OF TORONTO To construct, reconstruct, erect or place a building or structure and site grade at 2125 Lawrence Avenue West (Weston Lions Park), in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed as located on the property owned by The City of Toronto. The purpose is to permit the replacement of a natural turf soccer field with an artificial turf soccer field and installation of a sub-grade drainage system and new outfall, within Weston Lions Park, south of Lawrence Avenue West, west of Weston Road, in the City of Toronto. 147

EX10.50 16 DANIELS STREET To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units on Lot 6, Plan 2149, (16 Daniels Street), in the City of Toronto (Etobicoke York Community Council Area), Mimico Creek Watershed. The purpose is to construct a partial second storey addition, a side entrance way, and to reconstruct the existing rear wall and covered front porch to the existing storey single family detached dwelling at 16 Daniels Street in the City of Toronto (Etobicoke York Community Council Area). The existing rear frame addition is to be removed. 148 CITY OF TORONTO [NORTH YORK COMMUNITY COUNCIL AREA]

EX10.51 CITY OF TORONTO To construct, reconstruct, erect or place a building or structure and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere, north of Steeles Avenue, east of Kipling Avenue (2955 Kipling Avenue), in the City of Toronto (North York Community Council Area), Humber River Watershed as located on the property owned by City of Toronto. The purpose is to permit the retrofit of an existing leachate collection system involving excavation around the perimeter of the closed landfill to install pipe and maintenance holes, and a connection to the existing sanitary sewer system. 150

13 CITY OF TORONTO [SCARBOROUGH COMMUNITY COUNCIL AREA]

EX10.52 CITY OF TORONTO To interfere with a wetland and alter a watercourse on , (East Highland Creek- Valley 4/4A), in a regulated area in the City of Toronto (Scarborough Community Council Area), Highland Creek Watershed as located on the property owned by City of Toronto. The purpose is to implement channel restoration works to the East Highland Creek within Valley Segment 4/4A in order to protect the infrastructure located within the valley system from continued erosion and stabilize the channel. The proposal is subject to the warmwater fisheries timing window. 152

CITY OF VAUGHAN

EX10.53 AGC INCORPORATED To site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on Part Lot 13, 14, Concession 10, (8934 Huntington Road), in the City of Vaughan, Humber River Watershed as located on the property owned by AGC Incorporated. The purpose is to undertake restoration works, including the removal of fill, three corrugated steel pipes (CSPs) and a wooden bridge, within a Regulated Area of the Humber River Watershed at 8934 Huntington Road in the City of Vaughan. The fill was originally placed and the culverts/wooden bridge installed without the approval of the TRCA. 154

EX10.54 DOCTOR'S HOUSE DINING CORPORATION To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 41 -43, Plan 9, Part Lot 44, Plan 9, (21 Nashville Road), in the City of Vaughan, Humber River Watershed as located on the property owned by Doctor's House Dining Corporation. The purpose is to construct a 3-storey Inn with an underground parking structure, as an expansion to the existing Doctors House Dining facility, as well as to undertake grading, site alteration and landscaping works that will restore a portion of the existing valley area. 157

EX10.55 89 CLARENCE STREET To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on , (89 Clarence Street), in the City of Vaughan, Humber River Watershed. The purpose is to construct a replacement home and new inground swimming pool within a Regulated Area of the Humber River watershed at 89 Clarence Street in the City of Vaughan. 159

14 EX10.56 30 MODESTO GARDENS To construct, reconstruct, erect or place a building or structure on Lot 14, Plan 65M-2604, (30 Modesto Gardens), in the City of Vaughan, Humber River Watershed. The purpose is to construct a raised concrete deck within a Regulated Area of the Humber River watershed at 30 Modesto Gardens in the City of Vaughan. 160

EX10.57 39 GAMBLE STREET To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 20, Plan M-1106, (39 Gamble Street), in the City of Vaughan, Humber River Watershed. The purpose is to construct a replacement dwelling within a Regulated Area of the Humber River watershed at 39 Gamble Street in the City of Vaughan. 162

EX10.58 THORNHILL GOLF AND COUNTRY CLUB To site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 31, Concession 1 W, (7994 Yonge Street), in the City of Vaughan, Don River Watershed as located on the property owned by Thornhill Golf and Country Club. The purpose is to construct a replacement stormwater management culvert and conduct erosion repair / slope restoration works within a Regulated Area of the Don River watershed at 7994 Yonge Street in the City of Vaughan. 164

TOWN OF AJAX

EX10.59 TOWN OF AJAX To construct, reconstruct, erect or place a building or structure at Greenwood Conservation Area (Taunton and Westney), in the Town of Ajax, Duffins Creek Watershed as located on the property owned by Town of Ajax. The purpose is to permit the reconstruction of the existing pedestrian bridge and installation of a new asphalt trail and staircase within the Duffins Creek valley corridor in Greenwood Conservation Area, north of Taunton Road, east of Westney Road, in the Town of Ajax. 166

TOWN OF CALEDON

EX10.60 74 JAMES STREET To construct, reconstruct, erect or place a building or structure on Lot 41, 42, Block 1, Plan BOL7, (74 James Street), in the Town of Caledon, Humber River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a 8.92 square metre (96 sq. ft.) addition and ancillary deck structure at the rear of an existing residential dwelling associated with a municipal building permit. 168

15 EX10.61 13879 HEART LAKE ROAD To construct, reconstruct, erect or place a building or structure on Lot 27, Concession 3, (13879 Heart Lake Road), in the Town of Caledon, Humber River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a 7.8 square metre (84 sq. ft.) change room and an 7.8 square metre (84 sq. ft.) pool equipment room at the rear of an existing residential dwelling associated with a municipal building permit. 170

TOWN OF MARKHAM

EX10.62 25 RITTER CRESCENT To site grade on Lot 98, Plan M-1971, (25 Ritter Crescent), in the Town of Markham, Rouge River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed in order to facilitate the construction of an in-ground pool and associated landscaping. 171

EX10.63 66 SQUIRE BAKER'S LANE To construct, reconstruct, erect or place a building or structure at 66 Squire Baker's Lane, in the Town of Markham, Rouge River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed in order to facilitate the construction of a new dwelling. 173

TOWN OF RICHMOND HILL

EX10.64 2 MARINUCCI COURT To construct, reconstruct, erect or place a building or structure on Lot 22, Plan 65M-3300, (2 Marinucci Court), in the Town of Richmond Hill, Don River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Don River Watershed in order to facilitate the construction of an in-ground pool and associated landscaping. 174

TOWNSHIP OF KING

EX10.65 156 NORMAN DRIVE To construct, reconstruct, erect or place a building or structure on Lot 24, Plan 573, (156 Norman Drive), in the Township of King, Humber River Watershed. The purpose is to construct a replacement retaining wall and replacement rear yard deck attached to an existing dwelling within a Regulated Area of the Humber River watershed at 156 Norman Drive in the Township of King. 176

16 PERMIT APPLICATIONS EX10.66 - EX10.73 ARE PERMISSION FOR ROUTINE INFRASTRUCTURE WORKS:

Permission for Routine Infrastructure Works Letter of Approval are implemented by Planning and Development Division staff and are received monthly by the Executive Committee. The permission of routine infrastructure works is subject to authorization by the Director, Planning and Development and signed by an appointed enforcement officer. All routine infrastructure works are located within a Regulated Area, generally within or adjacent to the hazard or natural feature and in the opinion of staff do not affect the control of flooding, erosion, dynamic beaches, pollution or the conservation of land.

CITY OF PICKERING

EX10.66 REGIONAL MUNICIPALITY OF DURHAM To undertake borehole investigations east of the unopened portion of Sideline 22 and approximately 150m south of Taunton Road - near Brock Road, in the City of Pickering, Duffins Creek Watershed as located on the property owned by the Regional Municipality of Durham. The purpose is to undertake borehole investigations as part of the detailed design for the Ajax/Pickering Zone 1 Reservoir.

CFN: 44130 - Application #: 0440/10/PICK Report Prepared by: Scott Smith, extension 5758 For information contact: Scott Smith, extension 5758 Date: May 26, 2010

CITY OF TORONTO [ETOBICOKE YORK COMMUNITY COUNCIL AREA]

EX10.67 CITY OF TORONTO To undertake sewer and watermain or utility installation or maintenance within an existing roadway on Haliburton Avenue near Kipling and Rathburn, in the City of Toronto (Etobicoke York Community Council Area), Mimico Creek Watershed as located on the property owned by City of Toronto. The purpose is to permit the installation of a new 150 millimetre watermain by open cut, on Haliburton Avenue, south of Rathburn Road, west of Kipling Avenue.

CFN: 43732 - Application #: 0156/10/TOR Report Prepared by: Brian Storozinski, extension 5744 For information contact: Brian Storozinski, extension 5744 Date: June 11, 2010

17 EX10.68 CITY OF TORONTO To undertake road/pathway resurfacing or reconstruction in Habitant Park (Weston Road and Finch Avenue), in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed as located on the property owned by City of Toronto. The purpose is to permit replacement of the existing asphalt pathway, handrail and swing gate and the repair of an existing culvert within Habitant Park, south of Finch Avenue West, east of Weston Road.

CFN: 43963 - Application #: 0328/10/TOR Report Prepared by: Brian Storozinski, extension 5744 For information contact: Brian Storozinski, extension 5744 Date: June 15, 2010

CITY OF TORONTO [NORTH YORK COMMUNITY COUNCIL AREA]

EX10.69 CITY OF TORONTO To undertake road/pathway resurfacing or reconstruction and structure maintenance in Anewen Park (17 Anewen Drive), in the City of Toronto (North York Community Council Area), Don River Watershed as located on the property owned by City of Toronto. The purpose is to permit resurfacing of the existing asphalt pathway and replacement of the existing chainlink fence in Anewen Park, south of Lawrence Avenue East, west of .

CFN: 44007 - Application #: 0357/10/TOR Report Prepared by: Brian Storozinski, extension 5744 For information contact: Brian Storozinski, extension 5744 Date: June 15, 2010

CITY OF TORONTO [SCARBOROUGH COMMUNITY COUNCIL AREA]

EX10.70 CITY OF TORONTO To undertake borehole investigations on Highland Creek at Morningside Avenue, in the City of Toronto (Scarborough Community Council Area), Highland Creek Watershed as located on the property owned by City of Toronto. The purpose is to permit the drilling of two 150 millimetre diameter boreholes adjacent to Highland Creek at Morningside Drive.

CFN: 44164 - Application #: 0472/10/TOR Report Prepared by: Brian Storozinski, extension 5744 For information contact: Margaret Pak, extension 5714 Date: June 1, 2010

18 TOWN OF RICHMOND HILL

EX10.71 REGIONAL MUNICIPALITY OF YORK To undertake borehole investigations on 19th Avenue, 200 metres west of the CNR tracks to 100 metres east of , in the Town of Richmond Hill, Rouge River Watershed as located on the property owned by Regional Municipality of York. The purpose is to excavate fill in a regulated area to install 13 boreholes in order to investigate the subsoil suitability of the proposed CNR grade separation to be constructed on 19th Avenue, west of Bayview Avenue. No Fisheries and Oceans Canada Letter of Advice will be issued for this project and no timing window restriction will be applied to the works.

CFN: 43110 - Application #: 0832/09/RH Report Prepared by: June Murphy, extension 5304 For information contact: June Murphy, extension 5304 Date: June 25, 2010

TOWN OF WHITCHURCH-STOUFFVILLE

EX10.72 REGIONAL MUNICIPALITY OF YORK To undertake road/pathway resurfacing or reconstruction on the east and west side of Kennedy Road from Bethesda Side Road to approximately 300 metres south of Bethesda Side Road, in the Town of Whitchurch-Stouffville, Rouge River Watershed as located on the property owned by Regional Municipality of York. The purpose is to rehabilitate slope failure locations to maintain roadside stability directly adjacent to a tributary of the Rouge River. The works will be undertaken during the redside dace timing windows and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO) for the timing window restriction.

CFN: 43172 - Application #: 0873/09/WS Report Prepared by: Leah Weller, extension 5785 For information contact: Leah Weller, extension 5785 Date: June 28, 2010

EX10.73 REGIONAL MUNICIPALITY OF YORK To undertake road/pathway resurfacing or reconstruction on the east side of McCowan Road from Approx. 600m N of Bethesda Sideroad to approx. 1100m S of Bethesda, in the Town of Whitchurch-Stouffville, Rouge River Watershed as located on the property owned by Regional Municipality of York. The purpose is to rehabilitate slope failure locations to maintain roadside stability directly adjacent to a tributary of the Rouge River. The works will be undertaken during the redside dace timing windows and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO) for the timing window restriction. 19 CFN: 43173 - Application #: 0874/09/WS Report Prepared by: Leah Weller, extension 5785 For information contact: Leah Weller, extension 5785 Date: June 28, 2010

PERMIT APPLICATIONS EX10.74 - EX10.113 ARE MINOR WORKS LETTER OF APPROVAL:

Permission for Minor Works Letter of Approval are implemented by Planning and Development Division staff and are received monthly by the Executive Committee. The permission of minor works is subject to authorization by the Director, Planning and Development and signed by an appointed enforcement officer. All minor works are located within a Regulated Area, outside of the floodplain and in the opinion of staff do not affect the control of flooding, erosion, dynamic beaches, pollution or the conservation of land.

CITY OF BRAMPTON

EX10.74 3 NEWTON ROAD To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on (3 Newton Road), in the City of Brampton, Etobicoke Creek Watershed.

CFN: 44179 - Application #: 0473/10/BRAM Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: May 31, 2010

EX10.75 44 MERLIN DRIVE To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 22, Plan 43M-1429, (44 Merlin Drive), in the City of Brampton, Humber River Watershed.

CFN: 44211 - Application #: 0503/10/BRAM Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: June 4, 2010

EX10.76 151 HERDWICK STREET To construct a ground floor addition or structure greater than 50 sq. m (538 sq. ft) but less than 150 sq. m (1614 sq. ft) on Lot 120, Plan 14209, (151 Herdwick Street), in the City of Brampton, Humber River Watershed.

CFN: 44249 - Application #: 0533/10/BRAM Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: June 16, 2010

20 EX10.77 118 BLOOMSBURY AVENUE To install a swimming pool on Lot 25, Plan 43M-1738, (118 Bloomsbury Avenue), in the City of Brampton, Humber River Watershed.

CFN: 44250 - Application #: 0534/10/BRAM Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: June 16, 2010

EX10.78 20 SOUTHWELL PLACE To install a swimming pool on Lot 72, Plan 43M-1110, (20 Southwell Place), in the City of Brampton, Etobicoke Creek Watershed.

CFN: 44252 - Application #: 0536/10/BRAM Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: June 16, 2010

CITY OF PICKERING

EX10.79 1800 APPLEVIEW ROAD To construct a ground floor addition or structure greater than 50 sq. m (538 sq. ft) but less than 150 sq. m (1614 sq. ft) on Part Lot 1, Plan 1057, (1800 Appleview Road), in the City of Pickering, Waterfront Watershed.

CFN: 44309 - Application #: 0582/10/PICK Report Prepared by: Lisa Stern, extension 5370 For information contact: Chris Jones, extension 5718 Date: June 28, 2010

EX10.80 686 AMARETTO AVENUE To install a swimming pool on Lot 60, Plan 40M-1312, (686 Amaretto Avenue), in the City of Pickering, Frenchman's Bay Watershed.

CFN: 44235 - Application #: 0520/10/PICK Report Prepared by: Chris Jones, extension 5718 For information contact: Chris Jones, extension 5718 Date: June 16, 2010

EX10.81 861 BAYLAWN SERVICE To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 10, Plan 40M-1671, (861 Baylawn Service), in the City of Pickering, Duffins Creek Watershed.

21 CFN: 44159 - Application #: 0458/10/PICK Report Prepared by: Chris Jones, extension 5718 For information contact: Chris Jones, extension 5718 Date: May 28, 2010

CITY OF TORONTO [ETOBICOKE YORK COMMUNITY COUNCIL AREA]

EX10.82 227 CHURCH STREET To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 13, Plan M411, Part Lot 12, 14, Plan M411, (227 Church Street), in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed.

CFN: 44156 - Application #: 0448/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Steve Heuchert, extension 5311 Date: June 14, 2010

EX10.83 265 ELLIS AVENUE To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 329, Plan M438, (265 Ellis Avenue), in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed.

CFN: 44027 - Application #: 0370/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Steve Heuchert, extension 5311 Date: June 3, 2010

EX10.84 292 RIVERSIDE DRIVE To construct a ground floor addition or structure greater than 50 sq. m (538 sq. ft) but less than 150 sq. m (1614 sq. ft) on Lot 53, Plan M-356, (292 Riverside Drive), in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed.

CFN: 43855 - Application #: 0242/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Mark Rapus, extension 5259 Date: June 14, 2010

EX10.85 37 RIVERCOVE DRIVE To install a swimming pool on Lot 80, Plan M701, (37 Rivercove Drive), in the City of Toronto (Etobicoke York Community Council Area), Mimico Creek Watershed.

22 CFN: 44140 - Application #: 0436/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Mark Rapus, extension 5259 Date: June 14, 2010

CITY OF TORONTO [NORTH YORK COMMUNITY COUNCIL AREA]

EX10.86 20 FENSIDE DRIVE To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) and construct a ground floor addition up to 50 sq. m (538 sq. ft) on Lot 5, Plan 5439, (20 Fenside Drive), in the City of Toronto (North York Community Council Area), Don River Watershed.

CFN: 44158 - Application #: 0451/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: May 28, 2010

EX10.87 2 PARK LANE CIRCLE To undertake minor landscaping involving the placement, removal or regrading of material of less than 30 cubic metres (equivalent to 3 truckloads) and construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Block B, Plan 2578, (2 Park Lane Circle), in the City of Toronto (North York Community Council Area), Don River Watershed.

CFN: 44157 - Application #: 0449/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 29, 2010

EX10.88 161 BAYVIEW HEIGHTS To install a swimming pool on Lot 105, Plan 2694, (161 Bayview Heights), in the City of Toronto (North York Community Council Area), Don River Watershed.

CFN: 43972 - Application #: 0323/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 18, 2010

EX10.89 55 CITATION DRIVE To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 186, Plan M676, (55 Citation Drive), in the City of Toronto (North York Community Council Area), Don River Watershed.

23 CFN: 44152 - Application #: 0464/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: May 26, 2010

CITY OF TORONTO [SCARBOROUGH COMMUNITY COUNCIL AREA]

EX10.90 73 BONNYDON CRESCENT To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 43, Plan 66M-2410, (73 Bonnydon Crescent), in the City of Toronto (Scarborough Community Council Area), Rouge River Watershed.

CFN: 44185 - Application #: 0479/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 16, 2010

EX10.91 49 DOLPHIN DRIVE To change the use, size, or number of dwelling units of a structure, or undertake work that does not change the footprint of the existing structure on Part Lot 6, 7, Plan 1950, (49 Dolphin Drive), in the City of Toronto (Scarborough Community Council Area), Don River Watershed.

CFN: 44146 - Application #: 0442/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 8, 2010

EX10.92 19 FELICITY DRIVE To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 399, Plan M802, (19 Felicity Drive), in the City of Toronto (Scarborough Community Council Area), Highland Creek Watershed.

CFN: 44181 - Application #: 0483/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 18, 2010

EX10.93 71 BONNYDON CRESCENT To install a swimming pool and construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 44, Plan 66M-2410, (71 Bonnydon Crescent), in the City of Toronto (Scarborough Community Council Area), Rouge River Watershed.

24 CFN: 44184 - Application #: 0478/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 16, 2010

EX10.94 75 MOREAU TRAIL To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 118, Plan 66M-2312, (75 Moreau Trail), in the City of Toronto (Scarborough Community Council Area), Don River Watershed.

CFN: 44183 - Application #: 0477/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 16, 2010

EX10.95 110 APPLEFIELD DRIVE To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on , (110 Applefield Drive), in the City of Toronto (Scarborough Community Council Area), Highland Creek Watershed.

CFN: 44068 - Application #: 0400/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: May 28, 2010

EX10.96 UNIVERSITY OF TORONTO SCARBOROUGH To construct a ground floor addition or structure greater than 50 sq. m (538 sq. ft) but less than 150 sq. m (1614 sq. ft) on Part Lot 9, 10, Concession 1, (130 Old Kingston Road), in the City of Toronto (Scarborough Community Council Area), Highland Creek Watershed as located on the property owned by University of Toronto Scarborough.

CFN: 44189 - Application #: 0484/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Michelle Stafford, extension 5250 Date: June 25, 2010

CITY OF TORONTO [TORONTO AND EAST YORK COMMUNITY COUNCIL AREA]

EX10.97 15 CASTLEFRANK CRESCENT To install a swimming pool and undertake minor landscaping involving the placement, removal or regrading of material of less than 30 cubic metres (equivalent to 3 truckloads) on Part Lot 7, Plan 686, (15 Castlefrank Crescent), in the City of Toronto (Toronto and East York Community Council Area), Don River Watershed. 25 CFN: 44147 - Application #: 0443/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Mark Rapus, extension 5259 Date: June 14, 2010

EX10.98 48 DOUGLAS CRESCENT To construct a ground floor addition or structure greater than 50 sq. m (538 sq. ft) but less than 150 sq. m (1614 sq. ft) and change the use, size, or number of dwelling units of a structure, or undertake work that does not change the footprint of the existing structure on Lot 83, 84 & 85, Plan 2398, (48 Douglas Crescent), in the City of Toronto (Toronto and East York Community Council Area), Don River Watershed.

CFN: 44155 - Application #: 0447/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Steve Heuchert, extension 5311 Date: June 14, 2010

CITY OF VAUGHAN

EX10.99 106 BELL HARBOUR PLACE To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 12, Concession 6 Lot 23, Plan 65M-2429, (106 Bell Harbour Place), in the City of Vaughan, Humber River Watershed.

CFN: 44174 - Application #: 0467/10/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 3, 2010

EX10.100 219 RIVERMILL CRESCENT To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on , (219 River Mill Crescent), in the City of Vaughan, Don River Watershed.

CFN: 44264 - Application #: 0544/10/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 18, 2010

EX10.101 74 CHAYA SARA GARDENS To construct a ground floor addition up to 50 sq. m (538 sq. ft) on Lot 71, Plan 65M-3985, (74 Chaya Sara Gardens), in the City of Vaughan, Don River Watershed. 26 CFN: 44122 - Application #: 0429/10/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 3, 2010

TOWN OF AJAX

EX10.102 31 ANGIER CRESCENT To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Part Block 9, Plan 40M-2136, (31 Angier Crescent), in the Town of Ajax, Carruthers Creek Watershed.

CFN: 44263 - Application #: 0545/10/AJAX Report Prepared by: Lisa Stern, extension 5370 For information contact: Chris Jones, extension 5718 Date: June 21, 2010

TOWN OF CALEDON

EX10.103 6415 KING STREET To construct a ground floor addition or structure greater than 50 sq. m (538 sq. ft) but less than 150 sq. m (1614 sq. ft) on Lot 10, Concession 1, (6415 King Street), in the Town of Caledon, Humber River Watershed.

CFN: 44212 - Application #: 0504/10/CAL Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: June 4, 2010

TOWN OF CALEDON

EX10.104 51 NANCY STREET To construct a ground floor addition or structure greater than 50 sq. m (538 sq. ft) but less than 150 sq. m (1614 sq. ft) on Lot A, Plan BOL-7, (51 Nancy Street), in the Town of Caledon, Humber River Watershed.

CFN: 44231 - Application #: 0524/10/CAL Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: June 9, 2010

EX10.105 15805 MOUNT WOLFE ROAD To install a swimming pool on (15805 Mount Wolfe Road), in the Town of Caledon, Humber River Watershed. 27 CFN: 44177 - Application #: 0461/10/CAL Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: May 31, 2010

TOWN OF MARKHAM

EX10.106 9735 WARDEN AVENUE To construct a ground floor addition up to 50 sq. m (538 sq. ft) on Lot 34, Plan 6037Y, (9735 Warden Avenue), in the Town of Markham, Rouge River Watershed.

CFN: 43741 - Application #: 0144/10/MARK Report Prepared by: Lisa Stern, extension 5370 For information contact: Quentin Hanchard, extension 5324 Date: June 7, 2010

EX10.107 21 HERITAGE WOODS MANOR To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on , (21 Heritage Woods Manor), in the Town of Markham, Rouge River Watershed.

CFN: 44310 - Application #: 0583/10/MARK Report Prepared by: Lisa Stern, extension 5370 For information contact: Quentin Hanchard, extension 5324 Date: June 28, 2010

EX10.108 115 FRED VARLEY DRIVE To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 292, Plan 7566, (115 Fred Varley Drive), in the Town of Markham, Rouge River Watershed.

CFN: 44232 - Application #: 0519/10/MARK Report Prepared by: Lisa Stern, extension 5370 For information contact: Lisa Stern, extension 5370 Date: June 11, 2010

EX10.109 15 TREELINE COURT To install a swimming pool on , (15 Treeline Court), in the Town of Markham, Rouge River Watershed.

28 CFN: 44213 - Application #: 0518/10/MARK Report Prepared by: Lisa Stern, extension 5370 For information contact: Lisa Stern, extension 5370 Date: June 11, 2010

TOWN OF RICHMOND HILL

EX10.110 23 CARAT CRESCENT To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Part Lot 11, Plan 65M-3943, (23 Carat Crescent), in the Town of Richmond Hill, Rouge River Watershed.

CFN: 44261 - Application #: 0542/10/RH Report Prepared by: Lisa Stern, extension 5370 For information contact: Lisa Stern, extension 5370 Date: June 21, 2010

EX10.111 22 MOCKINGBIRD DRIVE To install a swimming pool on Lot 91, Plan 65M-3668, (22 Mockingbird Avenue), in the Town of Richmond Hill, Humber River Watershed.

CFN: 44237 - Application #: 0522/10/RH Report Prepared by: Lisa Stern, extension 5370 For information contact: Quentin Hanchard, extension 5324 Date: June 11, 2010

EX10.112 23 RICHVALLEY CRESCENT To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 222, Plan 65M3465, (23 Richvalley Crescent), in the Town of Richmond Hill, Rouge River Watershed.

CFN: 44160 - Application #: 0460/10/RH Report Prepared by: Lisa Stern, extension 5370 For information contact: Lisa Stern, extension 5370 Date: May 28, 2010

TOWNSHIP OF KING

EX10.113 290 KINGSCROSS DRIVE To construct a ground floor addition or structure greater than 50 sq. m (538 sq. ft) but less than 150 sq. m (1614 sq. ft) on Lot 10, PART LOT 9, Block A, Plan 556, (290 Kingscross Drive), in the Township of King, Humber River Watershed.

29 CFN: 44051 - Application #: 0385/10/KING Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: May 31, 2010

SPECIAL BUSINESS

DISCUSSION PAPER - ENCROACHMENTS

EX11. NEW BUSINESS

NEXT MEETING OF THE EXECUTIVE COMMITTEE #6/10, TO BE HELD ON AUGUST 6, 2010, AT 9:30 A.M. IN THE VICTORIA ROOM, BLACK CREEK PIONEER VILLAGE

Brian Denney Chief Administrative Officer

/ks

30 Item EX7.1 TO: Chair and Members of the Executive Committee Meeting #5/10, July 9, 2010

FROM: James W. Dillane, Director, Finance and Business Services

RE: GREENLANDS ACQUISITION PROJECT FOR 2006-2010 Flood Plain and Conservation Component, Mimico Creek Watershed 1672500 Ontario Limited CFN 44289 ______KEY ISSUE Purchase of property located west of Park Lawn Road, south of The Queensway (rear portions of 152, 154 and 156 Park Lawn Road), City of Toronto (Etobicoke York Community Council Area), under the "Greenlands Acquisition Project for 2006-2010", Flood Plain and Conservation Component, Mimico Creek watershed.

RECOMMENDATION

THE EXECUTIVE COMMITTEE RECOMMENDS THAT 0.12 hectares (0.31 acres), more or less, of vacant land being Part of Lots 285, 286, 287 and 288, Plan M-137 and designated as Parts 6, 7 and 8 on Plan 66R-24845, City of Toronto (Etobicoke York Community Council Area), located west of Park Lawn Road, south of The Queensway (rear portions of 152, 154 and 156 Park Lawn Road), be purchased from 1672500 Ontario Limited;

THAT the purchase price be $2.00 and Toronto and Region Conservation Authority (TRCA) will be responsible for survey costs and the vendor's reasonable legal fees;

THAT TRCA receive conveyance of the land free from encumbrance, subject to existing service easements;

THAT the firm of Gardiner Roberts LLP, Barristers & Solicitors, be instructed to complete the transaction at the earliest possible date. All reasonable expenses incurred incidental to the closing for land transfer tax, legal costs, and disbursements are to be paid;

AND FURTHER THAT authorized TRCA officials be directed to take whatever action may be required to give effect thereto, including the obtaining of necessary approvals and the signing and execution of any documents.

BACKGROUND Resolution #A260/05 at Authority Meeting #9/05, held on November 25, 2005, approved the Greenlands Acquisition Project for 2006-2010.

Negotiations have been conducted with Ms. Ida Zan, Vice-President, Development, of 1672500 Ontario Limited.

31 Attached is a plan showing the location of the subject lands.

RATIONALE The subject property falls within TRCA's approved master plan for acquisition for the Mimico Creek watershed as outlined in the approved Greenlands Acquisition Project for 2006-2010. Through the review of Site Plan Application No. 10 101257 WET 05 SA for proposed retail commercial development of this site, TRCA staff established the limits of the open space lands (i.e. Parts 6, 7 and 8 on Plan 66R-24845) which are comprised of a portion of the Regional Storm flood plain and valley corridor of the Mimico Creek at this location.

TAXES AND MAINTENANCE It is proposed that the lands be turned over to the City of Toronto for management.

FINANCIAL DETAILS Funds for the costs related to this purchase are available in the TRCA land acquisition capital account.

Report prepared by: George Leja, extension 5342 Emails: [email protected] For Information contact: George Leja, extension 5342; Ron Dewell, extension 5245 Emails: [email protected]; [email protected] Date: June 21, 2010 Attachments: 1

32 Attachment 1

33 Item EX7.2 TO: Chair and Members of the Executive Committee Meeting #5/10, July 9, 2010

FROM: James W. Dillane, Director, Finance and Business Services

RE: CITY OF TORONTO Request for a Permanent Easement for Two Storm Sewer Outlets Don River Watershed, City of Toronto (North York Community Council Area) CFN 42854 ______KEY ISSUE Receipt of a request from the City of Toronto to provide permanent easements for two storm sewer outlets, north side of Finch Avenue, east of Dufferin Street, Don River watershed, City of Toronto (North York Community Council Area).

RECOMMENDATION

THE EXECUTIVE COMMITTEE RECOMMENDS THAT WHEREAS Toronto and Region Conservation Authority (TRCA) is in receipt of a request from the City of Toronto to provide permanent easements for two storm sewer outlets, north side of Finch Avenue, east of Dufferin Street, Don River watershed, City of Toronto (North York Community Council Area);

AND WHEREAS it is in the best interest of TRCA in furthering its objectives as set out in Section 20 of the Conservation Authorities Act to cooperate with the City of Toronto in this instance;

THEREFORE LET IT BE RESOLVED THAT permanent easements containing a total of 0.15 hectares (0.37 acres), more or less, be granted to the City of Toronto for two storm sewer outlets, said land being Part of Lot 21, Concession 2 WYS, City of Toronto (North York Community Council Area), as shown on a plan entitled: 740 FINCH AVENUE WEST, prepared by City of Toronto - Technical Services, Survey and Mapping, under their Job No. 2009-1052;

THAT consideration be the nominal sum of $2.00, plus all legal, survey and other costs to be paid by the City of Toronto;

THAT the City of Toronto is to fully indemnify TRCA from any and all claims from injuries, damages or costs of any nature resulting in any way, either directly or indirectly, from the granting of these easements or the carrying out of construction;

THAT an archaeological investigation be completed, with any mitigative measures being carried out to the satisfaction of TRCA staff, at the expense of the City of Toronto;

34 THAT all TRCA lands disturbed by the proposed works be revegetated/stabilized following construction and, where deemed appropriate by TRCA staff, a landscape plan be prepared for TRCA staff review and approval in accordance with existing TRCA landscaping guidelines;

THAT a permit pursuant to Ontario Regulation 166/06 be obtained prior to commencement of construction;

THAT said easements be subject to approval of the Minister of Natural Resources in accordance with Section 21(2) of the Conservation Authorities Act, R.S.O. 1990, Chapter C.27, as amended;

AND FURTHER THAT authorized TRCA officials be directed to take whatever action may be required to give effect thereto, including the obtaining of necessary approvals and the signing and execution of any documents.

BACKGROUND The City of Toronto has formally requested permanent easements for two storm sewer outlets located on the north side of Finch Avenue, east of Dufferin Street. In the summer of 2009, a sinkhole resulted in the closure of Finch Avenue between Dufferin Street and Wilmington Avenue due to the collapse of a plugged storm sewer beneath the roadway. The existing storm sewer discharged into a culvert under Finch Avenue which joins the south and north reservoirs of the G. Ross Lord Dam. To prevent the reoccurrence of a sinkhole, storm flows were redirected on either side of the culvert beneath Finch Avenue via two new storm sewer outlets north of the road, discharging directly into the north reservoir instead of on either side of the culvert. Due to the complete closure of Finch Avenue, the sinkhole repair and installation of the new storm sewer outlets were allowed to proceed under the emergency works provision of TRCA's Valley and Stream Corridor Management Program policies for infrastructure projects.

The storm sewer outlets are located within the Regional Storm Flood Plain and Regulated Area of the West Don River. A permit pursuant to Ontario Regulation 166/06 for the as-constructed two outlets is being presented at this Executive Committee Meeting.

The subject TRCA-owned lands were acquired from Summit Holdings Ltd., et al, on May 22, 1963 and Frank Lovett on December 10, 1963, under the Finch Dam and Reservoir Acquisition Project.

Plantings All lands disturbed by construction have been stabilized and, where deemed appropriate by TRCA staff, revegetated with native woody and herbaceous plant material in accordance with existing TRCA landscaping guidelines. A landscape plan has been prepared and will form part of the permit pursuant to Ontario Regulation 166/06.

A plan illustrating the permanent easement location is attached.

35 FINANCIAL DETAILS The City of Toronto has agreed to assume all legal, survey and other costs involved in completing this transaction.

Report prepared by: George Leja, extension 5342 Emails: [email protected] For Information contact: George Leja, extension 5342 or Ron Dewell, extension 5245 Emails: [email protected] or [email protected] Date: June 16, 2010 Attachments: 1

36 Attachment 1

37 Item EX7.3 TO: Chair and Members of the Executive Committee Meeting #5/10, July 9, 2010

FROM: James W. Dillane, Director, Finance and Business Services

RE: REQUEST FOR DISPOSAL OF TORONTO AND REGION CONSERVATION AUTHORITY LAND North of King Street East, east of Old King Road (rear of 269 King Street East - Bolton) CFN 42978 ______KEY ISSUE Declaring surplus a parcel of Toronto and Region Conservation Authority land located north of King Street East, east of Old King Road (rear of 269 King Street East - Bolton, Town of Caledon, Regional Municipality of Peel, Humber River watershed.

RECOMMENDATION

THE EXECUTIVE COMMITTEE RECOMMENDS THAT a parcel of Toronto and Region Conservation Authority (TRCA) land consisting of 0.001 hectares (0.003 acres), more or less, being Part of Lot G, Block 1, Plan BOL-7, shown as a portion of Part 3 on Plan 43R-13764, located north of King Street East, east of Old King Road (rear of 269 King Street East - Bolton), Town of Caledon, Regional Municipality of Peel, Humber River watershed be declared surplus to the requirements of TRCA;

THAT staff enter into negotiations with Bill and Gillian Smillie, owner's of 269 King Street East, Bolton, for the sale of a parcel of TRCA land to resolve the long standing encroachment on TRCA property;

AND FURTHER THAT a report be brought forward to the Executive Committee at a future date with the results of the negotiations.

BACKGROUND At Executive Committee Meeting #8/09, held on October 9, 2009, Resolution #B136/09 was adopted as follows:

THAT the potential disposal of a fragment of land located north of King Street East, east of Old King Road (269 King Street East - Bolton), Town of Caledon, Regional Municipality of Peel, be referred to Toronto and Region Conservation Authority (TRCA) staff for review and discussion in accordance with established TRCA policies;

AND FURTHER THAT a report be brought forward to the Executive Committee at a future date recommending further action.

38 During a routine property inspection by staff in the spring of 2009, it appeared that Mr. and Mrs. Smillie's house was encroaching onto TRCA-owned land. Staff commissioned a survey of the property boundary which confirmed that part of a two-storey addition, wooden deck / platform, as well as a post and wire fence is encroaching on TRCA property. As a result, a letter has been received from Bill and Gillian Smillie, requesting to purchase a fragment of TRCA-owned land to resolve the encroachment. The Smillie's purchased their house at 269 King Street East on April 28, 2000. This private residential property borders on TRCA property to the north and the west.

The subject lands form part of a larger acreage acquired from David and Elizabeth Underhill on September 16, 1986, under the Humber River Flood Plain Lands Acquisition Project.

It would appear that sometime between the original TRCA acquisition of the adjacent property and prior to the Smillie purchase, the house at 269 King Street East was reconstructed and/or expanded onto TRCA property.

In accordance with TRCA policy, the following comments have been received from TRCA, Town of Caledon and Regional Municipality of Peel staff.

TRCA staff Planning and Development staff has confirmed that there are no erosion / slope stability concerns at the potential sale site. The existing house site is located on a raised knoll just above the valley floor; the steeper portion of the valley slope is located immediately north of the dwelling. Therefore, it is recommended that only the minimum area of TRCA property needed to resolve the encroachment be sold so that a full backyard setback is not created behind the existing dwelling. In addition, any proposed works (e.g. new fence) are subject to approval pursuant to Ontario Regulation 166/06.

Town of Caledon staff Town of Caledon staff has no objections to the sale of TRCA land in order to resolve the encroachment.

Region of Peel staff Staff of the Regional Municipality of Peel have no concerns regarding the proposed sale of land to resolve the encroachment on TRCA property behind 269 King Street East and does not require the reservation of any easements at this location.

A map showing the location of the subject property is attached.

RATIONALE Staff has reviewed the subject property and is recommending that a parcel of land be declared surplus and that staff enter into negotiation with Bill and Gillian Smillie to resolve the encroachment on TRCA property.

39 A plan illustrating the location of the subject lands is attached.

Report prepared by: George Leja, extension 5342 Emails: [email protected] For Information contact: George Leja, extension 5342 or Ron Dewell, extension 5245 Emails: [email protected] or [email protected] Date: June 17, 2010 Attachments: 1

40 Attachment 1

41 Item EX7.4 TO: Chair and Members of the Executive Committee Meeting #5/10, July 9, 2010

FROM: James W. Dillane, Director, Finance and Business Services

RE: ASSOCIATION OF MUNICIPALITIES OF ONTARIO POSITION PAPER Joint and Several Liability ______KEY ISSUE Recommends support for Association of Municipalities of Ontario position paper on issue of joint and several liability.

RECOMMENDATION

WHEREAS the Association of Municipalities of Ontario (AMO) has issued a position paper on reform of the legal provisions for joint and several liability as it relates to local government;

AND WHEREAS Conservation Ontario recognizes the value to conservation authorities of reform of joint and several liability in the local government sector which includes conservation authorities and other special purpose bodies;

THEREFORE LET IT BE RESOLVED THAT Toronto and Region Conservation Authority (TRCA) support the Association of Municipalities of Ontario position paper dated April 1, 2010, on reform of joint and several liability, recognizing that the proposed changes would apply to conservation authorities;

AND FURTHER THAT the Province of Ontario, Conservation Ontario, TRCA's participating municipalities and AMO be so advised.

RATIONALE The Association of Municipalities of Ontario has presented its paper dated April 1, 2010, on joint and several liability reform to the Province of Ontario Attorney General's office. The paper highlights how municipalities have become the targets of litigation when other defendants fail to have the means to pay high damage awards. The price communities are paying is steep - municipal insurance premiums and liability claims continue to increase dramatically. This is despite enormous improvements to safety including new standards for roads, playgrounds, pool safety, better risk management practices and the scaling back of some services. Municipalities should not be insurers of last resort. Many other common law jurisdictions have better approaches and others are pursuing liability reform. AMO says it is time for Ontario to do the same. AMO has requested support of municipalities.

42 Conservation Ontario has circulated to conservation authorities the AMO position paper on joint and several liability. The issues raised are relevant to conservation authorities which offer many of the same sort of services that are subject to litigation: recreation facilities, parks, swimming facilities, roads, etc. A number of conservation authorities have approved resolutions of support for the AMO position. Copies of the position paper can be made available to members upon request.

Staff has reviewed the position paper and agrees with the position of AMO requesting that the Province review and reform the provisions of relevant legislation relating to joint and several liability. The foregoing resolution is recommended.

Report prepared by: Jim Dillane, extension 6292 Emails: [email protected] For Information contact: Jim Dillane, extension 6292 Emails: [email protected] Date: June 29, 2010

43 Item EX8.1 TO: Chair and Members of the Executive Committee Meeting #5/10, July 9, 2010

FROM: Adele Freeman, Director, Watershed Management

RE: SOLARCITY TECHNOLOGY ASSESSMENT PARTNERSHIP Award of Sole Source Contract ______KEY ISSUE Award of sole source contract to Thermosol Energy Consulting for completion of monitoring, analysis and reporting in support of the SolarCity Technology Assessment Partnership.

RECOMMENDATION

THAT a contract for monitoring and evaluation of new and existing solar installations in Toronto, to be completed as part of the SolarCity Technology Assessment Partnership, be awarded to Thermosol Energy Consulting, at a cost not to exceed $72,000.00 plus HST;

AND FURTHER THAT authorized officials be directed to take whatever action may be required to give effect thereto, including the obtaining of necessary approvals and the signing and execution of any documents.

BACKGROUND The SolarCity Technology Assessment Partnership (STAP) is a joint project of the Toronto Atmospheric Fund (TAF), the City of Toronto's Energy and Waste Management Office and Toronto and Region Conservation Authority (TRCA). STAP was initiated to develop the tools and resources required to support excellence in site selection, installation and monitoring of solar equipment on City and GTA solar facilities. A variety of solar applications are being monitored and evaluated, including photovoltaic arrays, solar domestic hot water systems, solar air heating and solar pools. Capturing and transferring the knowledge gained from evaluation of the various solar installations will help improve the effectiveness of existing systems and facilitate broader use of solar technologies in urban settings.

Staff from TRCA's Sustainable Technologies Evaluation Program (STEP) has been a key partner in this project since 2008, mainly through the provision of technical expertise, monitoring and installation support. As part of this ongoing effort, it is proposed that Dr. Lucio Mesquita, president of Thermosol Energy Consulting, be retained to conduct solar system inspections, set-up and oversee monitoring activities and prepare case study reports on the performance of solar installations at seven existing sites and seven new installations within the City of Toronto. The consultant would also provide training and written technical guidance on solar best practices, deliver webinars, present at relevant conferences and identify opportunities for further research and/or pilot studies. The total cost of the contract ($72,000 plus HST) is based on a charge out rate of $440 per day up to a maximum of 164 days.

44 Dr. Lucio Mesquita has worked as a consultant in the design and application of solar technology for 17 years, and has a doctoral degree from Queen's University specializing in solar thermal applications. He has published numerous refereed publications and provided academic and professional instruction in applied solar energy. His unique combination of technical expertise in the design, installation and monitoring of solar energy systems, and research experience obtained throughout his career and during the completion of a Ph.D. in Mechanical Engineering, make Dr. Mesquita an ideal candidate to complete the aforementioned STAP deliverables.

RATIONALE Within the solar industry, Dr. Mesquita's particular combination of practical and technical knowledge, and understanding of the key research questions in the field is in short supply. His teaching experience and ability to clearly communicate the function and performance of solar technologies is also a strong asset in sharing insights and monitoring results with facility operators, managers and the general public. As a result, TRCA staff recommend the award of the contract on a sole source as per Sections 1.14.1 and 1.14.5 of TRCA's Purchasing Policy as follows:

1.14.1 A fluctuating market prevents the TRCA from obtaining price protection or owing to market conditions, required goods or services are in short supply. 1.14.5 The required good and services are to be supplied by a particular vendor or supplier having special knowledge, skills, expertise or experience that cannot be provided by any other supplier.

FINANCIAL DETAILS The total cost of the contract services to be provided to Thermosol Energy Consulting is not to exceed $72,000.00 plus HST. Funding will be fully covered by the Toronto Atmospheric Fund in account 416-92.

Report prepared by: Lisa Rocha, extension 5220 Emails: [email protected] For Information contact: Tim Van Seters, extension 5337 Emails: [email protected] Date: June 14, 2010

45 Item EX8.2 TO: Chair and Members of the Executive Committee Meeting #5/10, July 9, 2010

FROM: Carolyn Woodland, Director, Planning and Development

RE: ONTARIO MUNICIPAL BOARD HEARING 35 Don River Boulevard, City of Toronto ______KEY ISSUE Authorization for Toronto and Region Conservation Authority staff to obtain Party Status before the Ontario Municipal Board on referrals related to a Consent and Minor Variance application under the Planning Act, to permit an additional residential development at 35 Don River Boulevard.

RECOMMENDATION

THAT authorization be given for Toronto and Region Conservation Authority (TRCA) staff to obtain Party Status before the Ontario Municipal Board (OMB) regarding proposed consent and minor variance applications, and any other associated applications under the Planning Act, to permit an additional residential development at 35 Don River Boulevard, that is not in conformity with the natural hazard policies of TRCA’s Valley and Stream Corridor Management Program (1994) and the Provincial Policy Statement (2005);

THAT staff continue to work cooperatively with the City of Toronto and the appellants to ensure that the requirements of the Valley and Stream Corridor Management Program are met;

THAT staff be authorized to retain legal counsel to pursue this appeal before the OMB;

AND FURTHER THAT the OMB and all parties and participants to the hearing be so advised.

BACKGROUND The subject lands are located north of Earl Bales Park, and are located fully within the valley feature and within a Regulated Area of the Don River watershed. The existing development on the property is a detached, single-family residential dwelling.

The applicant is proposing to subdivide the existing one lot into two residential building lots, for the purposes of building two new single-family dwellings. Although the subject property is partially located within the Regional Storm floodplain of the Don River, the existing dwelling is sited outside of the floodplain. The additional dwelling is proposed to be located within the floodplain portion of the site.

46 The Planning Act application includes consent to sever the lot, and minor variances associated with the two new resulting residential developments. The application has been appealed to the OMB by the applicant as a result of the City of Toronto Committee of Adjustment's refusal of the consent and minor variance applications.

TRCA staff has submitted comments on the application to the City of Toronto’s Planning Division and to the applicant. Staff comments explain that we do not support the application on the basis that the proposed additional lot and dwelling unit would be located fully within a valley feature, and partially located within the Regional Storm floodplain, inconsistent with the objectives of TRCA’s Valley and Stream Corridor Management Program and the Provincial Policy Statement.

RATIONALE The OMB has scheduled a two-day hearing for August 9, 2010. City of Toronto legal staff has contacted TRCA planning staff and indicated that they have been directed to represent the City of Toronto interests, and as such are working to retain the necessary expert witness to oppose the proposed consent and minor variance at the OMB.

DETAILS OF WORK TO BE DONE Staff is requesting the authorization to represent TRCA interests and provide expert advice to the City of Toronto in order to defend the policies of Valley and Stream Corridor Management Program at the future OMB hearing. Staff will continue to work with the parties and participants to the hearing to resolve the issues, and will represent TRCA interests in advance of and during the hearing. We anticipate that TRCA legal costs will be streamlined in this case.

Report prepared by: Michelle Stafford, extension 5250 Emails: [email protected] For Information contact: Steve Heuchert, extension 5311 Emails: [email protected] Date: June 28, 2010 Attachments: 2

47 Attachment 1

48 Attachment 2

49 Item EX9.1 TO: Chair and Members of the Executive Committee Meeting #5/10, July 9, 2010

FROM: James W. Dillane, Director, Finance and Business Services

RE: GREENLANDS ACQUISITION PROJECT FOR 2006-2010 Flood Plain and Conservation Component, Mimico Creek Watershed Purchase of Land - Toronto District School Board CFN 43339 ______KEY ISSUE Receipt of decision on acquisition of land locally referred to as Heathercrest Park, located on the southeast corner of Storey Crescent and Antioch Drive, City of Toronto, under the "Greenlands Acquisition Project for 2006-2010," Flood Plain and Conservation Component, Rouge River watershed.

RECOMMENDATION

THAT the following Resolution #A32/10 approved at Authority Meeting #2/10, held on March 26, 2010, be received and become part of the public record:

THAT 2.38 hectares (5.89 acres) more or less, consisting of a vacant rectangular shaped parcel of land, being Block A, Plan 5071, Block A, Plan 5057, Etobicoke, City of Toronto, located on the southeast corner of Storey Crescent and Antioch Drive be purchased from the Toronto District School Board;

THAT the purchase price be $3,300,000.00;

THAT the acquisition by Toronto and Region Conservation Authority (TRCA) is conditional on all necessary funding being available;

THAT TRCA receive conveyance of the land required free from encumbrance, subject to existing service easements;

THAT the firm of Gardiner Roberts LLP, Barristers and Solicitors, be instructed to complete the transaction at the earliest possible date. All reasonable expenses incurred incidental to the closing for land transfer tax, legal costs and disbursements are to be paid;

AND FURTHER THAT the authorized TRCA officials be directed to take whatever actions may be required to give effect thereto including the obtaining of necessary approvals, and the signing and execution of any documents.

50 BACKGROUND At Authority Meeting #2/10 held on March 26, 2010, Resolution #A32/10 was approved in camera. Private minutes were retained as a record of this item at the meeting. For transparency, TRCA will report back on in camera items when they can become public so a record of the resolution appears in public minutes.

RATIONALE At the time the report was prepared, the Toronto District School Board (TDSB) had not approved the transaction. TDSB staff requested that TRCA's report be kept confidential until the TDSB had approved the transaction. This approval has now been obtained and the property closing is being completed.

Report prepared by: Mike Fenning, extension 5223 Emails: [email protected] For Information contact: Mike Fenning, extension 5223 or Ron Dewell, extension 5245 Emails: [email protected] or [email protected] Date: June 25, 2010

51 Item EX9.2 TO: Chair and Members of the Executive Committee Meeting #5/10, July 9, 2010

FROM: Derek Edwards, Director, Parks and Culture

RE: LOWEST BID NOT ACCEPTED Fish Food Glen Haffy Conservation Area ______KEY ISSUE Receipt of report approved by the Chief Administrative Officer on award of contract for supply of fish food for Glen Haffy Conservation Area.

RECOMMENDATION

IT IS RECOMMENDED THAT the report from the Chief Administrative Officer on award of contract to Martin Mills Inc., who was not the lowest bidder, be received.

BACKGROUND At Authority Meeting #5/05, held on June 24, 2005, Resolution #A124/05 approved the Purchasing Policy. As per Schedule 'A' of the policy, if the lowest bidder is not selected, a report shall be provided to the Executive Committee for their information at the next available meeting. In this regard, the report outlined in Attachment 1 that was approved by the Chief Administrative Officer on June 2, 2010 is provided for information in Attachment 1.

Report prepared by: Kathy Stranks, extension 5264 Emails: [email protected] For Information contact: Kathy Stranks, extension 5264 Emails: [email protected] Date: June 03, 2010 Attachments: 1

52 Attachment 1 TO: Chair and Members of the Procurement Not Requiring Board Approval Meeting RFQ Lowest Bid Not Accepted ($10,000 up to $25,000) - January 1 to June 30, 2010, June 30, 2010

FROM: Derek Edwards, Director, Parks and Culture

RE: FISH FOOD PURCHASE Glen Haffy Conservation Area ______KEY ISSUE Award of contract for the supply and delivery of fish food for Glen Haffy Conservation Area.

RECOMMENDATION

THAT the contract for supply of fish food for Glen Haffy Conservation Area be awarded to Martin Mills Inc. at a total cost not to exceed $25,000, plus 10% contingency, plus freight, plus applicable taxes.

BACKGROUND Glen Haffy Conservation Area (GHCA) is located in the Region of Peel, Town of Caledon, and features hiking trails, recreational fishing ponds and a rainbow trout fish hatchery program to stock fishing programs at Glen Haffy Headwaters Trout Ponds, Glen Haffy Conservation Area and Heart Lake Conservation Area. Approximately 4,500 fish are stocked at Heart Lake Conservation Area and 5,500 at the Headwaters Trout Ponds each year. The remaining 30,000 are stocked at the main public ponds at GHCA.

RATIONALE Staff researched fish food manufacturers that ship product to Ontario. There are two (2) Canadian manufacturers and several manufacturers and suppliers that operate in Asia, Europe and the United States (U.S.). The fish food manufactured by U.S. companies is available for purchase through the Canadian firms.

Therefore, Request for Quotation (RFQ) documentation was sent to the following two (2) Canadian manufacturers and suppliers of fish food: z Martin Mills Inc. - Elmira, Ontario; z Corey Feeds (Sharpe Farm Supplies Ltd.) - New Brunswick.

The following bids were received and reviewed by Parks and Culture staff (Doug Miller, Ed Patterson and Eric Lemon) on January 22, 2010.

53 Type of Fish Food Suppliers Martin Mills Inc. Corey Feeds (Plus Applicable Taxes) (Plus Applicable Taxes) Floating Feed #3 $32.80 $29.20 (1/8 inch) per 25kg bag (with a 4% discount of $1.31 equaling $31.49) Floating Feed #4 $31.80 $29.20 (1/4 inch) per 20 kg bag (with a 4% discount of $1.27 equaling $30.53) Floating Feed #5 $31.55 $29.20 (3/8 inch) per 20 kg bag (with a 4% discount of $1.26 equaling $30.29)

Staff recommends award of contract for supply of fish food for Glen Haffy Conservation Area to Martin Mills Inc. at a cost not to exceed $25,000, plus 10% contingency, plus freight, plus applicable taxes. Martin Mills Inc. is located in Ontario and guarantees fresh fish food with a maximum 24 hour delivery time. Fresh fish food is vital for the hatchery, as fish food does not have a long shelf life. Corey Feeds ships all product from New Brunswick with shipping times that take up to 6 weeks, therefore leaving a small window of time for the food to be used. Furthermore, a shorter shipping distance guarantees less carbon emissions, driving TRCA's goal of carbon neutrality by 2025.

TRCA staff has an existing 40 year relationship with Martin Mills Inc. and is confident in the quality of their product. Continuing to retain the services of Martin Mills Inc. will enable a guaranteed supply of food for the 2010 season. Martin Mills Inc. has demonstrated ability to work within time lines and produce exceptional service and product.

FINANCIAL DETAILS Estimated funds for 2010 of $25,000, plus 10% contingency, plus freight, plus applicable taxes are available in the Glen Haffy Conservation Area 2010 operating budget within account #322-52.

Report prepared by: Jenifer Moravek, extension 5624 Emails: [email protected] For Information contact: Ed Patterson, 905-584-2922 Emails: [email protected] Date: January 12, 2010

54 Item EX9.3 TO: Chair and Members of the Executive Committee Meeting #5/10, July 9, 2010

FROM: Brian Denney, Chief Administrative Officer

RE: LOWEST BID NOT ACCEPTED Vault Toilet and Building Septic Tank Pumping ______KEY ISSUE Receipt of report approved by the Chief Administrative Officer on award of contract for the supply of pumping septic tanks for Albion Hills Conservation Area, Glen Haffy Conservation Area and Heart Lake Conservation Area for the 2010 season.

RECOMMENDATION

IT IS RECOMMENDED THAT the report from the Chief Administrative Officer on award of contract to Smith Excavating Grading & Septic Services, who was not the lowest bidder, be received.

BACKGROUND At Authority Meeting #5/05, held on June 24, 2005, Resolution #A124/05 approved the Purchasing Policy. As per Schedule 'A' of the policy, if the lowest bidder is not selected, a report shall be provided to the Executive Committee for their information at the next available meeting. In this regard, the report outlined in Attachment 1 that was approved by the Chief Administrative Officer on June 17, 2010 is provided for information in Attachment 1.

Report prepared by: Kathy Stranks, extension 5264 Emails: [email protected] For Information contact: Kathy Stranks, extension 5264 Emails: [email protected] Date: June 14, 2010 Attachments: 1

55 Attachment 1 TO: Chair and Members of the Procurement Not Requiring Board Approval Meeting RFQ Lowest Bid Not Accepted ($10,000 up to $25,000) - January 1 to June 30, 2010, June 30, 2010

FROM: Derek Edwards, Director, Parks and Culture

RE: VAULT TOILET AND BUILDING SEPTIC TANK PUMPING Albion Hills Conservation Area, Glen Haffy Conservation Area and Heart Lake Conservation Area. ______KEY ISSUE Award of contract for the supply of pumping septic tanks for Albion Hills Conservation Area, Glen Haffy Conservation Area and Heart Lake Conservation Area for the 2010 season.

RECOMMENDATION

THAT the contract for supply of pumping the vault toilet septic tanks and building septic systems be awarded to Smith Excavating Grading & Septic Services at a cost not to exceed $20,000.00, plus 10% contingency, plus applicable taxes.

BACKGROUND Toronto and Region Conservation Authority's (TRCA's) Parks and Culture Division strives to exceed customer expectations through delivery of exceptional services. A key component to meeting client's needs at TRCA facilities includes maintaining essential services such as restroom facilities.

Albion Hills Conservation Area (AHCA), Glen Haffy Conservation Area (GHCA) and Heart Lake Conservation Area (HLCA) have numerous restroom facilities for use by the public located within the park areas. These facilities utilize a sealed vault tank containment system for the waste. Throughout the 2010 operating season, the tanks will need emptying as needed depending on their usage.

RATIONALE Staff researched septic tank servicing companies in the local jurisdiction for the supply of tank pumping for AHCA, GHCA and HLCA. Request for Quotation (RFQ) documentation was sent to the following three (3) suppliers: z Smith Excavating Grading & Septic Services; z Swaffield Septic Pumping Service; z Scoles Septic Service Inc.

The following bids were received and reviewed by Parks and Culture staff (Jay Clark, Stephen Lenstra and Sven Pittelkow) on April 27, 2010.

56 Company Bid / Truck Load Including Dumping Fee (plus applicable taxes) Smith Excavating Grading & $400.00/4,000 gal truck Septic Services Swaffield Septic Pumping $600.00/3,600 gal truck Service Scoles Septic Service Inc. $305.50/4,000 gal truck

Staff recommends that the contract be awarded to Smith Excavating Grading & Septic Services, due to the quality of work they provide, as well as superior customer service. Smith Excavating Grading & Septic Services has been servicing TRCA sites for over 10 years and has always provided exceptional technical and customer service. Furthermore, Smith Excavating Grading & Septic Service also provides full maintenance and repairs to septic systems in the case of a sudden malfunction.

The lowest bidder, Scoles Septic Service Inc. had previously discontinued a service contract with minimal notice at Albion Hills Conservation Area part way through the operating season, leaving staff without a septic contractor. In order to avoid such a situation in the future, staff recommends award of contract to Smith Excavating Grading & Septic Services at a maximum cost of $20,000.00, plus 10% contingency, plus applicable taxes.

FINANCIAL DETAILS Estimated cost for 2010, based on projected attendance for AHCA, GHCA and HLCA will be $20,000.00, plus 10% contingency, plus applicable taxes. The 2010 costs for this contract are available in the 2010 conservation areas' operating budget.

Report prepared by: Jenifer Moravek, extension 5624 Emails: [email protected] For Information contact: Jenifer Moravek, extension 5624 Emails: [email protected] Date: May 08, 2010

57 Item EX10 TO: Chair and Members of the Executive Committee Meeting #5/10, July 9, 2010

FROM: Carolyn Woodland, Director, Planning and Development

RE: APPLICATIONS FOR PERMITS PURSUANT TO ONTARIO REGULATION 166/06 Development, Interference with Wetlands and Alterations to Shorelines and Watercourses ______KEY ISSUE Pursuant to Ontario Regulation 166/06, written permission from the Authority is required for: a) straightening, changing, diverting or interfering in any way with the existing channel of a river, creek, stream or watercourse, or for changing or interfering in any way with a wetland; b) development, if in the opinion of the authority, the control of flooding, erosion, dynamic beaches or pollution or the conservation of land may be affected by the development.

A permit may be refused through a Hearing Process, if in the opinion of the Authority, the control of flooding, erosion, dynamic beaches, pollution or the conservation of land is affected.

RECOMMENDATION

THAT permits be granted in accordance with Ontario Regulation 166/06 for the applications which are listed below:

CITY OF BRAMPTON

EX10.1 BELL CANADA To construct, reconstruct, erect or place a building or structure and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on The Gore Road north of Castlemore Road in the City of Brampton, Humber River Watershed as located on the property owned by Region of Peel. The purpose is to install (4)100 mm HDPE ducts under the West Humber River on The Gore Road north of Castlemore Road. The warmwater timing window will apply to works. The proponent will be using the Fisheries and Oceans Canada (DFO) Operational Statement for Horizontal Directional Drilling (HDD).

58 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Plan No. 401; The Gore Rd. and Castlemore Rd.; dated November 30, 2009; received January 14, 2010; red-line revised by TRCA staff June 25, 2010; prepared by Plantec; z Plan No. 701; The Gore Rd. and Castlemore Rd.; dated November 30, 2009; received January 14, 2010; red-line revised by TRCA staff June 25, 2010; prepared by Plantec; z Contingency Plan In The Event of Sedimentation or Frac-out; received January 14, 2010; prepared by Bell.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: Bell Canada is proposing to install (4) 100 mm HDPE ducts under the West Humber River by method of Horizontal Directional Drilling (HDD). The drilling and receiving pits have been located 102 m apart and have been isolated with sediment fencing to minimize the risk of sedimentation to the creek. All work will be conducted within the road-right-of-way.

Control of Flooding: There will be no impact to the control of flooding.

Pollution: Standard sediment and erosion controls (Heavy Duty Silt Fencing) will be in place for the duration of construction, and until the site is restored, to prevent construction generated sediment from entering the watercourse.

Dynamic Beaches: Not applicable

Erosion: There are no geotechnical/slope stability issues associated with the proposal. 59 Conservation of Land: With erosion and sedimentation plans in effect, and the works conducted during the warmwater fisheries (July 1 - March 31) timing window, the potential for a harmful alteration, disruption or destruction (HADD) of fish habitat will be mitigated. The proponent will be using the Fisheries and Oceans Canada (DFO) Operational Statement for Horizontal Directional Drilling (HDD).

Plantings All disturbed areas will be restored with native seed mix following construction.

Policy Guidelines: This proposal complies with Section 4.3, Infrastructure and Servicing, of the TRCA's Valley and Stream Corridor Management Program.

CFN: 43571 - Application #: 0038/10/BRAM Report Prepared by: Ben Krul, extension 5769 For information contact: Ben Krul, extension 5769 Date: June 29, 2010

EX10.2 CITY OF BRAMPTON To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on Glidden Road between Heart Lake Road and Rutherford Road in the City of Brampton, Etobicoke Creek Watershed as located on the property owned by City of Brampton. The purpose is to replace a two CSP culverts as well as remove existing gabion baskets and replace them with armour stone on Gildden Road between Heart Lake Road and Rutherford Road. The warmwater fisheries timing window will be applied and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO).

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit:

60 z Sheet No. 1 of 9; Glidden Road Culvert Replacement - Existing Site Layout Plan, Profile and End Sections; dated October 30, 2008; received January 4, 2010, prepared by Planmac Inc.; z Sheet No. 2 of 9; Glidden Road Culvert Replacement - Proposed Site Layout Plan and End Sections; dated October 30, 2008; received May 31, 2010; red-line revised by TRCA staff June 25, 2010; prepared by Planmac Inc.; z Sheet No. 3 of 9; Glidden Road Culvert Replacement - Structural Details, Cover Slab, Outlet Foundation and Support Beam; dated October 30, 2008; received January 4, 2010, prepared by Planmac Inc.; z Sheet No. 4 of 9; Glidden Road Culvert Replacement - Concrete Parapet Wall Elevation, Sections and Details; dated October 30, 2008; received January 4, 2010, prepared by Planmac Inc.; z Sheet No. 5 of 9; Glidden Road Culvert Replacement - Railing for Parapet Wall Elevation and Details; dated October 30, 2008; received January 4, 2010, prepared by Planmac Inc.; z Sheet No. 6 of 9; Glidden Road Culvert Replacement - Environmental Protection Plan and Section First By-Pass Flow; dated October 30, 2008; received January 4, 2010, prepared by Planmac Inc.; z Sheet No. 7 of 9; Glidden Road Culvert Replacement - Environmental Protection Plan and Section Second By-Pass Flow; dated October 30, 2008; received January 4, 2010, prepared by Planmac Inc.; z Sheet No. 8 of 9; Glidden Road Culvert Replacement - Inlet Retaining Wall Plan, Elevation and Sections; dated May 7, 2008; received January 4, 2010, prepared by Planmac Inc.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The City of Brampton is proposing the removal of two 3.7 m wide x 2.4 m high arch CSP culverts which will be replaced by two 3 m wide x 2.4 m high precast concrete culverts. In addition to these works the City of Brampton is also proposing the construction of new concrete headwalls, parapet walls, steel beam guiderails, curbs, sidewalk, distribution slab and paving Glidden Road at the crossing location. The existing gabion wall on the south side of Glidden Road will be removed and replaced with armour stones. Riverstones will be placed at the outlet locations under the bridge to prevent further scouring.

Control of Flooding: No impacts to flood storage or conveyance are anticipated with this project.

Pollution: Standard erosion and sediment control measures (Heavy Duty Silt Fence, Cofferdam, Jersey Barrier) will be implemented prior to construction and maintained for the duration of construction, and until the site is stabilized and restored, in order to prevent construction generated sediments from entering the watercourses.

61 Dynamic Beaches: Not applicable

Erosion: There are no geotechnical or slope stability concerns associated with the proposed works.

Conservation of Land: With erosion and sedimentation plans in effect, and the works conducted during the warmwater fisheries (July 1 - March 31) timing window, the potential for a harmful alteration, disruption or destruction (HADD) of fish habitat will be mitigated and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO).

Plantings All disturbed areas will be restored with native/non-invasive species following construction.

Policy Guidelines: The proposal complies with Section 4.3 - Infrastructure and Servicing of the Authority's Valley and Stream Corridor Management Program.

CFN: 41525 - Application #: 852/08/BRAM Report Prepared by: Ben Krul, extension 5769 For information contact: Ben Krul, extension 5769 Date: June 29, 2010

EX10.3 CITY OF BRAMPTON To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere, alter a shoreline and alter a watercourse on the west side of the north pond in Chinguacousy Park, City of Brampton, Etobicoke Creek Watershed, as located on property owned by the City of Brampton. The purpose is to construct a park pavilion/boathouse and boat deck on the west side of the north pond in Chinguacousy Park. The warmwater fisheries timing window will be applied to this project and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO).

62 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Letter of Undertaking to provide revisions to the engineering and landscape plans to the satisfaction of TRCA; dated June 15, 2010; received June 17, 2010; prepared by City of Brampton.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: As part of the overall Master Plan for Chinguacousy Park, an existing boathouse and pedalboat area currently located on the east side of the north pond will be removed and replaced with a new two storey boat pavilion on the west side of the north pond in Chinguacousy Park. The pavilion will be a two level structure. The bottom level will consist of an open storage space for pedalboats. The top level will consist of an open deck area, a seating area, and washroom facilities for park visitors. A small office storage space, staff washroom and a staff kitchen will also be located on the second level. The boat deck located off the boat storage space will be constructed as a permanent feature on helical piers along the shoreline of the pond while the boat pavilion will be constructed on caissons on the bank. An armourstone retaining wall will be constructed up to the pavilion as part of the landscaping component for the pedestrian path that leads up to the pavilion from the south pond.

Given the other proposed works on the site including the north and south pond renaturalization (approved at the October 2009 Executive Committee meeting), and future proposed works on the watercourse both north and south of the ponds, a net benefit to this watershed will be generated. The new structure has also been designed to withstand expected flows during a Regional Storm event and the finished floor elevation will be constructed above the floodline.

63 Control of Flooding: There will be no impacts to the control of flooding. The pavilion has also been designed to withstand expected depths and velocities of flow during a Regional Storm event and the finished floor elevation (second storey) will be constructed above the floodline.

Pollution: Standard erosion control measures (silt fence, silt curtain, mud mats) will be implemented for the duration of construction, and until the site is restored, in order to prevent construction generated sediment from entering the watercourse.

Dynamic Beaches: Not applicable

Erosion: There are no slope stability issues related to the works.

Conservation of Land: With erosion and sedimentation plans in effect, the potential for a Harmful, Alteration, Disruption or Destruction (HADD) of fish habitat will be mitigated and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO). This application is subject to the Ministry of Natural Resources (MNR) warmwater fisheries timing window (July 1 to March 31).

Plantings As part of the Master Plan for Chinguacousy Park, naturalization and restoration of the shoreline around both the north and south ponds was previously approved at the October 2009 Executive Committee meeting. Those works have been completed and a net ecological gain has been achieved through that work. In addition, all disturbed areas as a result of the boat pavilion construction will be restored and additional plantings have been included as part of this application (9 trees, 362 shrubs, 462 perennials and ornamental grasses).

Policy Guidelines: This proposal complies with Section 4.2.2 - Development and Redevelopment/Intensification Within Non-Established Communities/Highly Urbanized Areas (D) Replacement Structures - of the Authority's Valley and Stream Corridor Management Program.

CFN: 43572 - Application #: 0039/10/BRAM Report Prepared by: Sharon Lingertat, extension 5717 For information contact: Sharon Lingertat, extension 5717 Date: June 28, 2010

64 EX10.4 ENBRIDGE GAS DISTRIBUTION INC. To construct, reconstruct, erect or place a building or structure and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on , the south side of Hansen Road, approximately 203 m east of Queen Street in the City of Brampton, Etobicoke Creek Watershed as located on the property owned by The City of Brampton under Franchise Agreement with Enbridge Gas Distribution Inc. The purpose is to install a gas pipeline under a tributary of Etobicoke Creek on the south side of Hansen Road, approximately 203 m east of Queen Street. TRCA staff will prepare a Letter of Advice on behalf of Fisheries and Oceans Canada (DFO). No in-water works will take place as part of this proposal.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Page 1 of 1; Typical Horizontal Directional Drill Watercourse Crossing Plan; received September 21, 2009; prepared by Enbridge Gas Distribution Inc.; z Page 4 of 4; Project Hansen Road; dated April 21, 2010, received April 30, 2010; red-line revised by TRCA staff on June 18, 2010; prepared by Enbridge Gas Distribution Inc.; z Contingency Plan for Horizontal Directional Drilling (HDD) of Watercourses in Ontario; dated June 2008; received September 21, 2009; prepared by Enbridge Gas Distribution Inc.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: Enbridge Gas Distribution has proposed the installation of a high pressure gas main under a tributary of the Etobicoke Creek on Hansen Road. The gas main will be installed by method of directional drilling. All work will be contained within the road right-of-way and disturbed areas will be restored to existing conditions following construction.

65 Control of Flooding: There are no geotechncial engineering issues associated with the proposed works.

Pollution: Standard erosion and sediment control measures (Heavy Duty Silt Fence) will be implemented prior to construction and maintained for the duration of construction, and until the site is stabilized and restored, in order to prevent construction generated sediments from entering the watercourses.

Dynamic Beaches: Not applicable

Erosion: There will be no slope stability issues related to the works.

Conservation of Land: With erosion and sedimentation plans in effect, the potential for a harmful alteration, disruption or destruction (HADD) of fish habitat will be mitigated. No in-water works will take place as part of this proposal and a Letter of Advice #2 will be written by TRCA staff on behalf of the Department of Fisheries and Oceans Canada (DFO). The proposed works will impact no significant terrestrial resource features.

Plantings All disturbed areas will be Hydroseeded with a native seed mix consistent with TRCA guidelines following construction.

Policy Guidelines: The proposal complies with Section 4.3 - Infrastructure and Servicing of the Authority's Valley and Stream Corridor Management Program.

CFN: 43027 - Application #: 0768/09/BRAM Report Prepared by: Ben Krul, extension 5769 For information contact: Ben Krul, extension 5769 Date: June 29, 2010

EX10.5 10 EDGE FOREST DRIVE To construct, reconstruct, erect or place a building or structure on Lot 9, Concession 9, (10 Edge Forest Drive), in the City of Brampton, Humber River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a replacement septic system at the rear of an existing dwelling associated with a municipal building permit.

66 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Plan, Redline revised by TRCA Planning staff on June 25, 2010, stamped received by TRCA Planning & Development staff on June 1, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a replacement septic system at the rear of an existing dwelling located at 10 Edge Forest Drive, in the City of Brampton. The rear of the subject property is adjacent to the a valley corridor associated with the Humber River Watershed. The proposed septic system is located on a flat, manicured lawn and is setback sufficiently from the vegetation associated with the valley corridor. In addition, there are no geotechnical concerns anticipated with this proposal. There are also no ecology or flooding related concerns with this proposal.

Control of Flooding: The proposed works are located outside of the Regional Floodplain. As such, no impacts to the storage and/or conveyance of flood waters are anticipated.

Pollution: Appropriate erosion and sediment controls (silt fence) have been proposed with this application, and will be maintained throughout all phases of construction.

Dynamic Beaches: Not applicable.

67 Erosion: There are no geotechnical and/or slope stability concerns anticipated with this project.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings The proposed septic bed is located within an existing manicured lawn. As such, no significant vegetation will be removed as a result of the construction.

Policy Guidelines: This proposal is in conformity with Section 4.2.2 (E) – Property Improvements and Ancillary Structures – of the Authority’s Valley and Stream Corridor Management Program (VSCMP).

CFN: 44210 - Application #: 0501/10/BRAM Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: June 29, 2010

EX10.6 REGIONAL MUNICIPALITY OF PEEL To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units on Part Lot 5, Concession 1 Part 2 Plan 43R-11915, (3, 5, 7, 9 Wellington Street East), in the City of Brampton, Etobicoke Creek Watershed as located on the property owned by Regional Municipality of Peel. The purpose is to undertake works within a TRCA Regulated Area to facilitate the construction of a below ground walkway within the Regional Storm Floodplain.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing A1.6, Proposed Site Plan, prepared by GBCA Architects, dated, June 16, 2010, stamped received by TRCA Planning and Development June 18, 2010; 68 z Drawing AE3.0, Basement Plan 7 & 9 Wellington, prepared by GBCA Architects, dated, June 16, 2010, stamped received by TRCA Planning and Development June 18, 2010; z Drawing AE6.1, Building Sections 7 & 9 Wellington, prepared by GBCA Architects, dated, June 16, 2010, stamped received by TRCA Planning and Development June 18, 2010; z Drawing AE6.2, Building Sections 7 & 9 Wellington, prepared by GBCA Architects, dated, June 16, 2010, stamped received by TRCA Planning and Development June 18, 2010; z Drawing AE6.3, Foundation Sections & Details 7 & 9 Wellington, prepared by GBCA Architects, dated, June 16, 2010, stamped received by TRCA Planning and Development June 18, 2010; z Drawing AE7.8, Tunnel Elevator Plans, Sections and Details, prepared by GBCA Architects, dated, June 16, 2010, stamped received by TRCA Planning and Development June 18, 2010; z Drawing AW3.1, Level 1 (Basement) Plan 3 & 5 Wellington, prepared by GBCA Architects, dated, June 16, 2010, stamped received by TRCA Planning and Development June 18, 2010; z Drawing AW6.5, Tunnel Section, prepared by GBCA Architects, dated, June 16, 2010, stamped received by TRCA Planning and Development June 18, 2010; z Drawing A10.9, Tunnel Details, prepared by GBCA Architects, dated, June 16, 2010, stamped received by TRCA Planning and Development June 18, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of the application is to undertake works within a TRCA Regulated Area to facilitate the construction of an underground pedestrian tunnel within the Regional Storm Floodplain. The subject lands are located in the downtown core of Brampton, which is located within the Regional Storm Floodplain. This area has been designated as a Special Policy Area (SPA), which allows for development (generally of a minor nature) within the floodplain provided that the proposal meets the TRCA's technical requirements for development within SPAs. This modification is being completed in concert with a larger enhancement project associated with the Region of Peel Art Gallery. A topographic survey of the subject lands shows that the lower level of the Art Gallery of Peel at 5 Wellington Street will be inundated by floodwaters during both the Regional and 350-year storm events.

Please note that TRCA Permit C-10053 was approved by the TRCA Executive Committee at its January 15, 2010 meeting to facilitate the construction of a ramp to the north entry of 5 Wellington Street in order to facilitate barrier free access into the site. Through review by TRCA Water Resources staff, it was determined that the ramp would not increase the existing flood risk on the subject lands nor would it impact the flow and/or conveyance of floodwaters. It is TRCA’s understanding that with the issuance of the TRCA permit, the project has received full municipal building permits and a tender was awarded. Since that time, the Region of Peel has revised their redevelopment plan to add an underground walkway to facilitate the barrier free movement of people and artifacts from the Art Gallery of Peel at 5 Wellington Street to the Peel Heritage Museum at 7 Wellington Street.

69 After exploring several alternatives, the preferred proposal involves excavating an area beneath 7 Wellington Street to contain stairs to the main level and an elevator, and connecting the newly excavated vestibule to the lower level of 5 Wellington Street via a tunnel. The finished floor elevation in the new vestibule area below 7 Wellington Street is 211.57 metres above sea level, during a Regional Storm Event floodwaters will flow from 5 Wellington Street into the new vestibule area in 7 Wellington Street. Due to the need to maintain the heritage attributes of the site and construction feasibility issues with raising the tunnel, it was determined that passive flood proofing of the tunnel to the Regional Flood elevation is not practicable. The applicant has committed to passively flood proofing the proposal to the 350-year flood, as consistent with the approach taken for other underground structures in Downtown Brampton. The applicant also has committed to further reducing the risk to these amenity areas during the Regional Storm Event by ensuring that the proposal is passively wet floodproofed to the Regional Event, including ensuring that the tunnel and vestibule will be structurally sound during the Regional Event and installing all electrical services above the Regional floodline. As an additional measure, flood rated doors will be added at either end of the tunnel to provide active dry floodproofing of the tunnel and of 7 Wellington Street to the Regional Storm Elevation.

Control of Flooding: TRCA staff have reviewed this proposal and do not anticipate any significant impacts to the storage and/or conveyance of floodwaters. The applicant has committed to reducing flood risk within the proposed walkway by providing floodproofing measures.

Pollution: Appropriate erosion and sediment controls will be installed and maintained on the subject property throughout all phases of construction.

Dynamic Beaches: Not applicable

Erosion: There are no anticipated geotechnical and/or slope stability concerns related to this application.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings As no vegetation will be removed, no additional plantings are required.

Policy Guidelines: This proposal is consistent with Section 4.2.1 (B) - Development Guidelines for Development/Redevelopment within Designated Two Zone Areas or Special Policy Areas and Section 4.2.2 (E) - Property Improvements and Ancillary Structures - of the Authority's Valley and Stream Corridor Management Program (VSCMP).

CFN: 44182 - Application #: 0485/10/BRAM Report Prepared by: Lisa Stern, extension 5370 For information contact: Quentin Hanchard, extension 5324 Date: June 29, 2010

70 EX10.7 SUNRISE AUTO To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units at 2 Hale Road, in the City of Brampton, Etobicoke Creek Watershed as located on the property owned by Sunrise Auto. The purpose is to undertake works within a TRCA Regulated Area of the Etobicoke Creek Watershed in order to facilitate an addition to the rear of an existing industrial building.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Servicing and Grading, prepared by John Towle Associates Limited Consulting Engineers, dated October 7, 2009, stamped received by TRCA Planning and Development May 21, 2010; z Site Plan, prepared by John Towle Associates Limited Consulting Engineers, dated October 29, 2009, stamped received by TRCA Planning and Development May 21, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to undertake works within a TRCA Regulated Area of the Etobicoke Creek Watershed in order to facilitate an addition to the rear of an existing industrial building. The subject lands are located within a historic industrial subdivision in the City of Brampton. Although the subject lands do not contain any natural features, they are located adjacent to the Regional Storm Floodplain. Based on a topographic survey submitted by the applicant, TRCA Staff confirm that the proposed works are appropriately set back from the Floodplain. The area to which this application applies is currently asphalt parking area, as such no vegetation will be removed as a result of construction.

71 Control of Flooding: The subject site is currently outside of the Regional Storm Flood Plain, as such impacts to the flow and/or conveyance of flood waters is not anticipated.

Pollution: Appropriate erosion and sediment controls will be utilized and maintained throughout all phases of construction.

Dynamic Beaches: Not applicable

Erosion: There are no geotechnical and/or slope stability concerns associated with this application.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings As no significant vegetation will be removed, no additional plantings are required.

Policy Guidelines: The proposal is consistent with Section 4.2.2 (C) - Minor Additions - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44172 - Application #: 0463/10/BRAM Report Prepared by: Lisa Stern, extension 5370 For information contact: Quentin Hanchard, extension 5324 Date: June 29, 2010

CITY OF MISSISSAUGA

EX10.8 CITY OF MISSISSAUGA To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material originating on the site or elsewhere and alter a watercourse at Little Etobicoke Creek near Loreland Avenue, in the City of Mississauga, Etobicoke Creek Watershed, as located on property owned by the City of Mississauga. The purpose is to remove a broken section of storm outlet pipe located within the Little Etobicoke Creek Valley, and repair the area around the outlet with armourstones. Since this was completed as an emergency works, an extension to the warmwater fisheries timing window was granted. A Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO).

72 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z LETO-0100 – Little Etobicoke Creek, Plan Sketch; dated June 14, 2010; received June 14, 2010; prepared by City of Mississauga; red line revised June 16, 2010; z General Notes; received June 14, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: This application involves stabilizing and repairing a broken section of 750 mm diameter storm outlet pipe located in the Little Etobicoke Creek valley. The broken section of outlet pipe will be removed from the valley and the scoured section around the outlet will be repaired with aroumourstones and round gravel/cobble stone. Existing gabions at this outlet will also be removed and replaced with armourstones. The construction access route into the valley will be the same as that used for the work being completed for the CPR interceptor sewer rehabilitation (approved at the January 2010 Executive Committee meeting). This application was identified as Emergency Works and a letter was sent to the City of Mississauga on June 17, 2010 summarizing the authorized works. This permit application seeks to formalize construction that has already taken place through the Emergency Works process.

Control of Flooding: There will be no impacts to the control of flooding.

Pollution: Standard erosion and sediment control measures (cofferdam) will be implemented for the duration of construction, and until the site is restored, in order to prevent construction generated sediment from entering the watercourse.

73 Dynamic Beaches: Not applicable

Erosion: There are no slope stability issues related to the works.

Conservation of Land: With erosion and sedimentation plans in effect, the potential for a Harmful, Alteration, Disruption or Destruction (HADD) of fish habitat will be mitigated and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO). This application is subject to the Ministry of Natural Resources (MNR) warmwater fisheries timing window (July 1 to March 31); however, a fish timing window extension was granted as works needed to be completed immediately under the Emergency Works protocol. The fisheries timing window was granted from June 16, 2010 to July 1, 2010 when the fisheries timing window opens again.

Plantings All disturbed areas will be restored with native, non-invasive vegetation following construction.

Policy Guidelines: This proposal complies with Section 4.3 - Infrastructure and Servicing - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44233 - Application #: 0517/10/MISS Report Prepared by: Sharon Lingertat, extension 5717 For information contact: Sharon Lingertat, extension 5717 Date: June 24, 2010

CITY OF TORONTO [ETOBICOKE YORK COMMUNITY COUNCIL AREA]

EX10.9 65 OAKFIELD DRIVE To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Part Lot 6, 10, Plan 718, (65 Oakfield Drive), in the City of Toronto (Etobicoke York Community Council Area), Mimico Creek Watershed. The purpose is to construct a single family dwelling.

74 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. A1, Site Plan and Zoning Information, prepared by Khalmur Building Productions Inc., Revision No. 4, revised June 1, 2010, received June 18, 2010; z Drawing Un-numbered, Landscape Plan, unknown Authour, on drawing by Taraskic McMillan Kubicki Limited, Revision No. 4, revised June 1, 2010, received June 18, 2010; z Drawing No. T1, Topographical Survey, prepared by Khalmur Building Productions Inc., Revision No. 3, revised June 1, 2010, received June 18, 2010; z Drawing No. TP1, Tree Preservation Plan, prepared by Khalmur Building Productions Inc., Revision No. 3, revised June 1, 2010, received June 18, 2010; z Drawing Un-numbered, Site Grading and Servicing Plan, unknown Authour, on drawing by Taraskic McMillan Kubicki Limited, dated June 11, 2009, received June 18, 2010; z Drawing No. A5, West Elevation, prepared by Khalmur Building Productions Inc., dated June 9, 2009, received June 21, 2010; z Drawing No. A6, East Elevation, prepared by Khalmur Building Productions Inc., dated June 9, 2009, received June 21, 2010; z Drawing No. A7, North Elevation, prepared by Khalmur Building Productions Inc., dated June 9, 2009, received June 21, 2010; z Drawing No. A8, South Elevation, prepared by Khalmur Building Productions Inc., dated June 9, 2009, received June 21, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposal is to construct a single family dwelling on an existing lot of record. The site is located on the south side of Oakfield Drive, east of Royal York Road, north of The Queensway and backs onto the Mimico Creek in the City of Toronto (Etobicoke York Community Council Area). The existing single family dwelling will be demolished.

75 Control of Flooding: The site is not within the Regional Storm Floodplain.

Pollution: Sediment control fencing will be installed to prevent construction related debris from entering the valley.

Dynamic Beaches: Not applicable.

Erosion: The replacement dwelling will have no impact on watercourse erosion. There are no geotechnical concerns with the proposal.

Conservation of Land: The replacement dwelling and accessory structures are located in excess of 10 metres from the top of bank and will have no impact on the conservation of land. Municipal site plan approval limits any future development from being located in the buffer. Existing significant vegetation will be protected with tree protection fencing.

Plantings The buffer will be renaturalized with native trees, shrubs and seed mix.

Policy Guidelines: This proposal is consistent with Section 4.2.2, Development & Redevelopment/Intensification Within Non-Established/Highly Urbanized Areas, of the TRCA's Valley and Stream Corridor Management Program.

CFN: 42555 - Application #: 0426/09/TOR Report Prepared by: Steve Heuchert, extension 5311 For information contact: Steve Heuchert, extension 5311 Date: June 24, 2010

EX10.10 THE RIVERHOUSE AT THE OLD MILL LIMITED To construct, reconstruct, erect or place a building or structure and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Part Lot 21, 22, 5, 6, 7, 8, Plan M-416, (30 Old Mill Road), in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed as located on the property owned by The Riverhouse at the Old Mill Limited. The purpose is to locate a condominium sales trailer and conduct minor excavation for an archaeological study.

76 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. A-002, Trailer Plan (Post Archaeology), prepared by Page + Steele Architects, dated April 22, 2010, Revision No. 2, revised June 24, 2010, received June 25, 2010, redline revised to illustrate archaeological work.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposal is to locate a sales trailer and conduct archaeological investigation work on the upper parking lot on the north side of Old Mill Road across from the Old Mill banquet facility. The site is located north of Bloor Street and backs onto the Humber River. The site is subject to an approved Official Plan Amendment, Zoning Amendment and Site Plan for a condominium building which will be subject to additional TRCA permitting requirements at a later date. The proposed sales trailer is not located within an adjacent restrictive covenant area controlled by TRCA.

Control of Flooding: The site is not located in a regional storm floodplain.

Pollution: The trailer is pre-fabricated and the archaeological work is benign. There will be no impact on the control of pollution.

Dynamic Beaches: Not applicable.

Erosion: The proposed trailer and archaeological work will not impact erosion.

77 Conservation of Land: The site is currently a paved parking lot located above the top of bank of the valley. The proposal will have no impact on the conservation of land.

Plantings No plantings are required.

Policy Guidelines: This proposal is consistent with Section 4.2.2., Development Guidelines within Non-Established Communities/Highly Urbanized Area, of the TRCA's Valley and Stream Corridor Management Program.

CFN: 44314 - Application #: 0588/10/TOR Report Prepared by: Steve Heuchert, extension 5311 For information contact: Steve Heuchert, extension 5311 Date: June 29, 2010

EX10.11 WESTON GOLF AND COUNTRY CLUB To construct, reconstruct, erect or place a building or structure on Lot 22, Concession C, (50 St. Philips Road), in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed as located on the property owned by Weston Golf and Country Club. The purpose is to construct an outdoor kitchen and arbour addition to the existing clubhouse building at 50 St. Phillips Road in the City of Toronto (Etobicoke York Community Council Area).

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. A5.0, Outdoor Kitchen, O.B.C. Matrix and Context Plan, prepared by Hicks Partners, dated April 29, 2010, received on May 28, 2010; z Drawing No. A5.1, Outdoor Kitchen Plans, Elevations and Sections, prepared by Hicks Partners, dated April 29, 2010, received on May 28, 2010. 78 RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to develop within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of an outdoor kitchen area and arbour addition to the existing clubhouse building at Weston Golf and Country Club municipally described 50 St. Phillips Road. The subject site is located north of Dixon Road and west of Weston Road in the City of Toronto (Etobicoke York Community Council Area).

Control of Flooding: The site is not located within a regional storm flood plain and the proposal will have no impact on the storage and/or conveyance of floodwaters.

Pollution: Appropriate erosion and sediment controls will be installed and maintained throughout all phases of construction.

Dynamic Beaches: Not applicable.

Erosion: There are no slope stability/geotechnical concerns associated with this application.

Conservation of Land: The proposed works are located no further than the existing limits of development. There are no other significant natural features on, or adjacent to, the site that would be negatively impacted by the project.

Plantings Native plantings will be provided as per City of Toronto Urban Forestry Ravine Protection Services Guidelines and recommendations pertaining to tree protection and maintenance during construction will be implemented.

Policy Guidelines: This proposal is consistent with Section 4.2.2.(B) - Development Guidelines for Minor Additions within Non-Established/Highly Urbanized Areas of the TRCA's Valley and Stream Corridor Management Program.

CFN: 44190 - Application #: 0486/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Steve Heuchert, extension 5311 Date: June 28, 2010

79 CITY OF TORONTO [NORTH YORK COMMUNITY COUNCIL AREA]

EX10.12 CITY OF TORONTO To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on , (Finch Avenue), in the City of Toronto (North York Community Council Area), Don River Watershed as located on the property owned by City of Toronto. The purpose is to decommission an existing storm sewer and construct two new storm sewer outlets.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. U-1610-005, Emergency Road and Sewer Repairs, prepared by McCormick Rankin, dated September 2009, Revision No. 5, revised November 9, 2009, received May 4, 2010; z Drawing No. U-1610-006, Emergency Road and Sewer Repairs, prepared by McCormick Rankin, dated September 2009, Revision No. 4, revised November 9, 2009, received May 4, 2010; z Drawing No. U-1610-007, Landscape Compensation Plan Culvert 1 and 2 Landscape Notes, prepared by Ecoplans, dated September 2009, received May 4, 2010; z Drawing No. U-1610-008, Planting Details, prepared by Ecoplans, dated September 2009, received May 4, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

80 Proposal: In the summer of 2009 a sinkhole occured on Finch Avenue West between Dufferin Street and Wilmington Avenue, just south of the G. Ross Lord Dam. The sinkhole was caused by the collapse of a plugged stormwater outfall that discharged into a culvert under Finch Avenue. This culvert joins the south and north ponds associated with the Dam. Given that FInch Avenue was closed for an extended period of time, an emergency works permission was granted to the City of Toronto by TRCA staff to repair the damage, and the details of the restoration were deferred to a later date. The solution to the sinkhole was to divert storm flows from either side of the culvert towards the north pond, rather than attempting to fix the storm outfall and culvert due the difficulty of accessing them, and the fact that there was no guarantee that the existing design would not result in a similar issue in the future. The final solution was to construct two new outfalls discharging to rip rap at the base of the road embankment into the north pond. The existing sewers were grouted and abandoned. The project was constructed in the fall of 2009 and the purpose of this application is to regularize the as-built situation. An easement is required over the outfalls as they lie on TRCA-owned land. The granting of the easement is also being considered at this Executive Committee agenda.

Control of Flooding: The proposed outfalls are located above the Regional Storm Flood elevation and there will be no impact on the control of flooding.

Pollution: Sediment and erosion controls were in place during the construction.

Dynamic Beaches: Not applicable.

Erosion: Erosion is addressed through two rip rap channels designed to control the runoff.

Conservation of Land: A small area of the road embankment was disturbed in order to install the outfalls and rip-rap. However, vegetation removals were compensated for at a 3:1 ratio in the general area.

Plantings A total of 55 native trees, 177 native shrubs and native seed mix was installed to compensate for the project.

Policy Guidelines: This proposal is consistent with Section 4.3, Development Guidelines for Infrastructure and Servicing, of the TRCA's Valley and Stream Corridor Management Program.

CFN: 42891 - Application #: 0660/09/TOR Report Prepared by: Steve Heuchert, extension 5311 For information contact: Steve Heuchert, extension 5311 Date: June 14, 2010

81 EX10.13 CITY OF TORONTO To construct, reconstruct, erect or place a building or structure, site grade and alter a watercourse on Part Block C, Plan 5544, (11 Valley Woods Road), in the City of Toronto (North York Community Council Area), Don River Watershed as located on the property owned by City of Toronto. The purpose is to develop within a Regulated Area of the Don River watershed to facilitate construction of a new splash-pad, and renovation of an existing playground at Brookbanks Park.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. L1, Coversheet, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010; z Drawing No. L2, Environmental Protection Plan, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010; z Drawing No. L3, Demolition & Removal Plan, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010; z Drawing No. L4, Site Servicing Plan, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010; z Drawing No. L5, Landscape Construction Plan, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010; z Drawing No. L6, Layout Plan, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010; z Drawing No. L7, Grading Plan Revised April 13, 2010, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010; z Drawing No. L8, Detail Plans, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010; z Drawing No. L9, Planting Plan, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010; z Drawing No. L10, Landscape Details 1, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010. Redlined by TRCA June 29, 2010;

82 z Drawing No. L11, Landscape Details 2, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010; z Drawing No. L12, Landscape Details 3, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010; z Drawing No. L13, Landscape Details 4, prepared by Victor Ford and Associates Inc., dated May 31, 2010, received by TRCA June 2, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposed works include construction of a new splash-pad, replacement of the existing playground structures and equipment, and resurfacing of asphalt trails at Brookbanks Park, in the City of Toronto. The site is located south of Road, east of the Don Valley Parkway.

Control of Flooding: The site is located in an estimated Regional Storm floodplain. The proposed regrading works will not adversely affect the storage or conveyance of floodwaters. Water associated with the operation of the new spash-pad will drain to a sanitary sewer.

Pollution: Sediment control fencing will be installed prior to any regrading or construction activities.

Dynamic Beaches: Not applicable

Erosion: There are no geotechnical concerns associated with this application.

Conservation of Land: Eight tree will be removed as a result of construction.

Plantings Native tree shrub and seed mix will be planted, including 25 trees.

Policy Guidelines: This proposal is consistent with Section 4.2.2(E), Property Improvements and Ancillary Structures, and 4.2.2(H), Existing Resource-based Uses, of TRCA's Valley and Stream Corridor Management Program.

CFN: 43795 - Application #: 0191/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 29, 2010

83 EX10.14 14 BRENDAN ROAD To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units on Lot 7, Plan 2566, (14 Brendan Road), in the City of Toronto (North York Community Council Area), Don River Watershed. The purpose is to develop within a Regulated Area of the Don River watershed to facilitate construction of a sunroom addition to the rear of the existing dwelling.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. A-2, Foundation Plan, Partial First Floor Plan, North Elevation, West Elevation, South Elevation, prepared by Perma-Wood Solariums, dated June 30, 2008, received by TRCA January 28, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposed works include construction of a solarium addition to the rear of the existing dwelling. The solarium will be constructed on piers. The site is located west of Bayview Avenue, south of Moore Avenue, in the City of Toronto.

Control of Flooding: The site is not located in the Regional Storm Floodplain.

Pollution: Sediment control fencing will be installed prior to commencement of any construction or regrading activities, and will remain in place until project completion and stabilization of any exposed soils.

84 Dynamic Beaches: Not applicable

Erosion: TRCA geotechnical engineering staff have reviewed and accepted a geotechnical investigation and the proposed works will be constructed in accordance with the accepted study.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings No plantings are required.

Policy Guidelines: This proposal is consistent with Section 4.2.2(C), Minor Additions, of TRCA's Valley and Stream Corridor Management Program.

CFN: 43655 - Application #: 0094/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 25, 2010

EX10.15 6 KING MAPLE PLACE To construct, reconstruct, erect or place a building or structure on Lot 248, Plan 66M-677, (6 King Maple Place), in the City of Toronto (North York Community Council Area), Don River Watershed. The purpose is to develop within a Regulated Area of the Don River watershed to facilitate construction of a replacement two-storey dwelling.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit:

85 z Drawing No. A1.2, Site Plan, Landscape Plan, Servicing Plan, prepared by Richard Wengle Architect, dated March 31, 2010; z Drawing No. A1.3, Retaining Wall Sections & Details, prepared by Richard Wengle Architect, dated March 31, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposed works include the demolition of the existing dwelling and construction of a new two-storey dwelling at 6 King Maple Place in the City of Toronto. The existing in-ground pool will be renovated, and the existing retaining wall will be reconstructed. The site is located north of Sheppard Avenue East, west of Leslie Street.

Control of Flooding: The site is not located in the Regional Storm floodplain.

Pollution: Sediment control fencing will be erected prior to any construction or regrading works, and will remain in place until construction is complete and any exposed soils have been stabilized.

Dynamic Beaches: Not applicable

Erosion: A geotechnical report is not required as the proposed development is located in the same location as the existing development. TRCA geotechnical engineering staff have reviewed and accepted the proposed retaining wall schematics.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings No plantings are required.

Policy Guidelines: This proposal is consistent with Section 4.2.2(D), Replacement Structures, of TRCA's Valley and Stream Corridor Management Program.

CFN: 43247 - Application #: 0938/09/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 25, 2010

86 EX10.16 30 GLENORCY ROAD To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 30, Plan M809, (30 Glenorchy Road), in the City of Toronto (North York Community Council Area), Don River Watershed. The purpose is to develop within a Regulated Area of the Don River watershed to facilitate construction of a replacement two-storey dwelling.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. A1.1, Site Plan, prepared by Richard Wengle Architect, dated June 11, 2010, received by TRCA June 24, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposed works include the construction of a new two-storey dwelling at 30 Glenorchy Road in the City of Toronto. The site is located south of Lawrence Avenue East, west of Leslie Street. The existing in-ground pool will be retained, and the existing dwelling and cabana will be demolished.

Control of Flooding: The site is not located in the Regional Storm floodplain.

Pollution: Sediment control fencing will be installed prior to commencement of any construction or grading activities, and will remain in place until construction is complete, and any exposed soils have been stabilized.

87 Dynamic Beaches: Not applicable

Erosion: A geotechnical report has been reviewed and accepted by TRCA geotechnical engineering staff, and the proposed works will be constructed in accordance with the report.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings No plantings are required.

Policy Guidelines: The proposal is consistent with Section 4.2.2(D), Replacement Structures, of the TRCA's Valley and Stream Corridor Management Program.

CFN: 43716 - Application #: 0132/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 25, 2010

EX10.17 84 BRAESIDE ROAD To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units on Part Lot 11, Plan 2473, (84 Braeside Road), in the City of Toronto (North York Community Council Area), Don River Watershed. The purpose is to develop within a Regulated Area of the Don River watershed to facilitate construction of a two-storey addition above, and a three-storey addition to the side of the existing dwelling.

88 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. A1, Site Plan, prepared by Trademarked by Design Inc., dated April 2010, received by TRCA May 21, 2010; z Drawing No. A2, Basement Plan, prepared by Trademarked by Design Inc., dated April 2010, received by TRCA May 21, 2010; z Drawing No. A3, Ground Floor Plan, prepared by Trademarked by Design Inc., dated April 2010, received by TRCA May 21, 2010; z Drawing No. A4, Second Floor Plan, prepared by Trademarked by Design Inc., dated April 2010, received by TRCA May 21, 2010; z Drawing No. A5, Third Floor Plan, prepared by Trademarked by Design Inc., dated April 2010, received by TRCA May 21, 2010; z Drawing No. A6, Front/West Elevation, prepared by Trademarked by Design Inc., dated April 2010, received by TRCA May 21, 2010; z Drawing No. A7, Side/North Elevation, prepared by Trademarked by Design Inc., dated April 2010, received by TRCA May 21, 2010; z Drawing No. A8, Side/South Elevation, prepared by Trademarked by Design Inc., dated April 2010, received by TRCA May 21, 2010; z Drawing No. A9, Rear/East Elevation, prepared by Trademarked by Design Inc., dated April 2010, received by TRCA May 21, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposed works include construction of two additional stories above the existing 1.5 storey dwelling at 84 Braeside Road in the City of Toronto. Also proposed is a three-storey addition to the side in the area of an existing patio. The site is located north of Lawrence Avenue East, west of Bayview Avenue.

Control of Flooding: The site is not located in the Regional Storm floodplain.

Pollution: Sediment control fencing is not required as the site is adequately setback from the watercourse.

Dynamic Beaches: Not applicable

Erosion: A geotechnical report is not required as the proposed works do not extend closer to the feature than the existing dwelling, and will be located approximately 7.5 metres from the top-of-slope.

89 Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings No plantings are required.

Policy Guidelines: The proposal is consistent with Section 4.2.2(C), Minor Additions, of the TRCA's Valley and Stream Corridor Management Program.

CFN: 44188 - Application #: 0482/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 25, 2010

CITY OF TORONTO [SCARBOROUGH COMMUNITY COUNCIL AREA]

EX10.18 41 LYNNDALE ROAD To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units on Lot 43, Plan 3227, (41 Lynndale Road), in the City of Toronto (Scarborough Community Council Area), Waterfront Watershed. The purpose is to develop within a Regulated Area of the Lake Ontario waterfront to facilitate construction of a one-storey addition to the rear, and a one-storey addition to the rear and side of the existing dwelling.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. A0.0, Site Plan & OBC & Zoning Info, prepared by Post Architects, dated May 28, 2009, received by TRCA May 6, 2010.

90 RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposed works include construction of a one-storey addition to the rear, a one-storey addition to the rear and side, expansion of the front porch, and installation of second-storey dormer windows at the existing dwelling at 41 Lynndale Road in the City of Toronto. The site is located south of Kingston Road, east of Victoria Park Avenue.

Control of Flooding: The site is not located in the Regional Storm floodplain.

Pollution: Sediment control fencing is not required as the site is manicured and surrounded by a mature hedge-row.

Dynamic Beaches: Not applicable

Erosion: There are no geotechnical concerns associated with this application.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings No plantings are required.

Policy Guidelines: The proposal is consistent with Section 4.2.2(C), Minor Additions, of TRCA's Valley and Stream Corridor Management Program.

CFN: 44142 - Application #: 0438/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 25, 2010

EX10.19 117 COLONEL DANFORTH TRAIL To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 41, Plan 2546, (117 Colonel Danforth Trail), in the City of Toronto (Scarborough Community Council Area), Highland Creek Watershed. The purpose is to develop within a Regulated Area of the Highland Creek watershed to facilitate construction of a replacement dwelling.

91 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. 101, Grading & Servicing Plan, prepared by Politis Engineering Ltd., dated December 2007, revised June 22, 2010, received by TRCA June 24, 2010; z Drawing No. 102, Notes & Details, prepared by Politis Engineering Ltd., dated April 2010, revised June 22, 2010, received by TRCA June 24, 2010; z Drawing No. A1, Site Plan, prepared by AIM Engineering, dated September 1, 2005, revised April 27, 2010, received by TRCA June 24, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: This proposal consists of demolishing an existing single family residential house in order to build a new home. The new home will be located in the same location from the valley as the current house. Therefore, there will be no further encroachment into the valley as the setback will be maintained. A grading plan has been designed to manage storm water on site. Rather than flowing over the valley and potentially causing erosion concerns, the storm water will infiltrate on site.

Control of Flooding: The proposed works are not located within the Regional Storm Floodplain.

Pollution: Sediment fencing will be in place throughout the duration of construction to ensure that sediment will not enter the valley.

Dynamic Beaches: Not applicable

92 Erosion: As the proposed house is located adjacent to a valleyland, TRCA technical staff required a geotechnical report to be complete. TRCA technical staff were satisfied by the findings of the report and ensure that there are no geotechnical concerns.

Conservation of Land: There will be no significant vegetation removed as part of this application. The applicant has agreed to plant the top of bank to increase slope stability.

Plantings All plantings will be consistent with TRCA's Seed Mix Guidelines.

Policy Guidelines: This proposal is consistent with Section 4.2.2(D), Replacement Structures, of TRCA's Valley and Stream Corridor Management Program.

CFN: 44316 - Application #: 0593/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 29, 2010

EX10.20 LE ROSA ESTATES LTD. To construct, reconstruct, erect or place a building or structure on Lot 468, Plan 1566, (117 Chine Drive), in the City of Toronto (Scarborough Community Council Area), Waterfront Watershed as located on the property owned by Le Rosa Estates Ltd.. The purpose is to develop within a Regulated Area of the Lake Ontario waterfront to facilitate construction of a replacement two-storey dwelling.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit:

93 z Drawing No. A1, Site Plan, prepared by Lemcad Consultants, dated May 4, 2010, received by TRCA May 19, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposed works include construction of a new two-storey dwelling with attached garage at 117 Chine Drive in the City of Toronto. The existing dwelling and detached garage will be demolished. The site is located south of Kingston Road, east of Midland Avenue.

Control of Flooding: The site is not located within a Regional Storm floodplain.

Pollution: Sediment control fencing is not required as the site is not located near a watercourse.

Dynamic Beaches: Not applicable

Erosion: There are no geotechnical concerns associated with this application.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings No plantings are required.

Policy Guidelines: The proposal is consistent with Section 4.2.2(D), Replacement Structures, of TRCA's Valley and Stream Corridor Management Program.

CFN: 44186 - Application #: 0480/10/TOR Report Prepared by: Michelle Stafford, extension 5250 For information contact: Steve Heuchert, extension 5311 Date: June 25, 2010

94 CITY OF TORONTO [TORONTO AND EAST YORK COMMUNITY COUNCIL AREA]

EX10.21 607 RUSHTON ROAD To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 2, Plan 2612, (607 Rushton Road), in the City of Toronto (Toronto and East York Community Council Area), Don River Watershed. The purpose is to construct an at grade dry lay flagstone patio (5.2m x 4.0m) and a water feature in the rear yard of the existing single family detached dwelling at 607 Rushton Road in the City of Toronto (Toronto and East York Community Council Area).

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. A01, Site Plan, prepared by Brendan Dolan, undated, received on June 9, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to develop within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of an at grade dry lay flagstone patio (5.2m x 4.0m) and a water feature in the rear yard of the existing single family detached dwelling at 607 Rushton Road. The subject site is located west of Bathurst Street and north of St. Clair Avenue West in the City of Toronto (Toronto and East York Community Council Area).

Control of Flooding: The site is not located within a regional storm flood plain and the proposal will have no impact on the storage and/or conveyance of floodwaters.

95 Pollution: Sediment fencing is not required as the proposed works are adequately set back from the watercourse.

Dynamic Beaches: Not applicable.

Erosion: There are no slope stability/geotechnical concerns associated with this application.

Conservation of Land: No significant vegetation will be removed as a result of construction. There are no other significant natural features on, or adjacent to, the site that would be negatively impacted by the project. The appropriate tree protection fencing will be installed.

Plantings Native plantings will be provided as per City of Toronto Urban Forestry Ravine Protection Services Guidelines and recommendations pertaining to tree protection and maintenance during construction will be implemented.

Policy Guidelines: The proposal is consistent with Section 4.2.2.(E) - Development Guidelines for Property Improvements and Ancillary Structures within Non-Established/Highly Urbanized Areas of the TRCA’s Valley and Stream Corridor Management Program.

CFN: 44253 - Application #: 0537/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Steve Heuchert, extension 5311 Date: June 28, 2010

EX10.22 108 LANGDEN AVENUE To construct, reconstruct, erect or place a building or structure on Lot 3, Plan 1134, (108 Langden Avenue), in the City of Toronto (Toronto and East York Community Council Area), Humber River Watershed. The purpose is to construct a covered verandah on top of the existing concrete porch to the front of the existing single storey semi-detached dwelling at 108 Langden Avenue in the City of Toronto (Etobicoke York Community Council Area).

96 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. 1 of 7, Lot Plan, prepared by Andrew Tiefenbeck, undated, received on June 14, 2010; z Drawing No. 2 of 7, Verandah Plan, prepared by Andrew Tiefenbeck, undated, received on June 14, 2010; z Drawing No. 3 of 7, South Elevation, prepared by Andrew Tiefenbeck, undated, received on June 14, 2010; z Drawing No. 4 of 7, East Elevation, prepared by Andrew Tiefenbeck, undated, received on June 14, 2010; z Drawing No. 5 of 7, West Elevation, prepared by Andrew Tiefenbeck, undated, received on June 14, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to develop within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a covered verandah on top of the existing concrete porch to the front of the existing single storey semi-detached dwelling at 108 Langden Avenue. The subject site is located south of West and west of Weston Road in the City of Toronto (Etobicoke York Community Council Area). The proposed works are to be constructed in the Regulatory Floodplain of the Rockcliffe Special Policy Area.

Control of Flooding: The subject site is located within a Regional Storm Floodplain of the Humber River Watershed and is within the Rockcliffe Special Policy Area (SPA). The SPA recognizes existing commercial and residential development within the floodplain and allows new development/redevelopment subject to new structures meeting the minimum 350-year flood-proofing requirements or the equivalent. TRCA staff have determined the proposed works will not adversely impact the storage and/or conveyance of floodwaters. 97 Pollution: Sediment fencing is not required as the proposed works are adequately set back from the watercourse.

Dynamic Beaches: Not applicable.

Erosion: There are no slope stability/geotechnical concerns associated with this application.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings No plantings are required as part of this project.

Policy Guidelines: The proposal is consistent with Section 4.2.1(B)3.iii. - Development Guidelines for Development/Redevelopment within Designated Two Zone/Special Policy Areas - of the TRCA's Valley and Stream Corridor Management Program.

CFN: 44277 - Application #: 0565/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Steve Heuchert, extension 5311 Date: June 28, 2010

EX10.23 MONTCREST PRIVATE SCHOOL To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 15, 16, Part Block A, Plan 274-E, (658 Broadview Avenue), in the City of Toronto (Toronto and East York Community Council Area), Don River Watershed as located on the property owned by Montcrest Private School. The purpose is to construct a "natural" playground area at Montcrest Private School municipally described 658 Broadview Avenue in the City of Toronto (Toronto and East York Community Council Area). The existing playground area is to be removed.

98 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. 1, Base Plan, prepared by Bienenstock Natural Playgrounds, dated March 27, 2010, received by TRCA staff on June 4, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to develop within a TRCA Regulated Area of the Don River Watershed in order to facilitate the construction of a new "natural" playground area at Montcrest Private School municipally described 658 Broadview Avenue. The existing playground equipment and hard surfacing are to be removed. The proposed works will involve some re-grading, native plantings, and landform creation. The subject site is located on the west side of Broadview Avenue and south of in the City of Toronto (Toronto and East York Community Council Area).

Control of Flooding: The site is not located within a regional storm flood plain and the proposal will have no impact on the storage and/or conveyance of floodwaters.

Pollution: Appropriate erosion and sediment controls will be installed and maintained throughout all phases of construction.

Dynamic Beaches: Not applicable.

Erosion: There are no slope stability/geotechnical concerns associated with this application.

99 Conservation of Land: The proposed works are adequately set back from the top of bank. There are no other significant natural features on, or adjacent to, the site that would be negatively impacted by the project.

Plantings Native plantings will be provided as per City of Toronto Urban Forestry Ravine Protection Services Guidelines and recommendations pertaining to tree protection and maintenance during construction will be implemented.

Policy Guidelines: This proposal is consistent with Section 4.2.2.(D) and (E) - Development Guidelines for Replacement Structures, Property Improvements and Ancillary Structures within Non-Established/Highly Urbanized Areas of the TRCA's Valley and Stream Corridor Management Program.

CFN: 44248 - Application #: 0532/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Steve Heuchert, extension 5311 Date: June 28, 2010

EX10.24 MOUNT PLEASANT GROUP OF CEMETERIES To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Part Lot 19, Concession 3 FTB, (375 Mount Pleasant Road), in the City of Toronto (Toronto and East York Community Council Area), Don River Watershed as located on the property owned by Mount Pleasant Group of Cemeteries. The purpose is to construct a family mausoleum at Mount Pleasant Cemetery on lands municipally described 375 Mount Pleasant Road in the City of Toronto (Toronto and East York Community Council Area).

100 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. A1, Site Plan, prepared by Martin Frenette Architect, dated March 11, 2010, received on June 8, 2010; z Drawing No. G1.0, Elevations, prepared by Picco Engineering, dated January 2010, received on June 8, 2010; z Drawing No. G3.0, Plans, prepared by Picco Engineering, dated January 2010, received on June 8, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to develop within a TRCA Regulated Area of the Don River Watershed in order to facilitate the construction of a family mausoleum at Mount Pleasant Cemetery on lands municipally described 375 Mount Pleasant Road. The subject site is located west of Mount Pleasant Road and north of Moore Avenue in the City of Toronto (Toronto and East York Community Council Area).

Conditional Permit: Due to the City of Toronto strike, this permit will be conditional upon the approval of Urban Forestry Services. Minor revisions to the approved plans required on behalf of Urban Forestry Services will be addressed by TRCA staff through redline revisions.

Control of Flooding: The site is not located within a regional storm flood plain and the proposal will have no impact on the storage and/or conveyance of floodwaters.

Pollution: Sediment and erosion controls are not required as the proposed works are adequately set back from the watercourse.

Dynamic Beaches: Not applicable.

Erosion: There are no slope stability/geotechnical concerns associated with this application.

Conservation of Land: The appropriate tree protection fencing will be installed.

Plantings Native plantings will be provided as per City of Toronto Urban Forestry Ravine Protection Services Guidelines and recommendations pertaining to tree protection and maintenance during construction will be implemented.

101 Policy Guidelines: The proposal is consistent with Section 4.2.2.(E) - Development Guidelines for Property Improvements and Ancillary Structures within Non-Established/Highly Urbanized Areas of the TRCA’s Valley and Stream Corridor Management Program.

CFN: 44244 - Application #: 0528/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Steve Heuchert, extension 5311 Date: June 28, 2010

CITY OF VAUGHAN

EX10.25 CANADIAN PACIFIC RAILWAY To construct, reconstruct, erect or place a building or structure and site grade on , (60 Burwick Avenue), in the City of Vaughan, Humber River Watershed as located on the property owned by Canadian Pacific Railway. The purpose is to conduct grading works associated with the construction of a replacement headwall / outfall structure within a Regulated Area of the Humber River watershed adjacent to 60 Burwick Avenue in the City of Vaughan.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Plan and Cross-Section Drawing, Drawing No. C-1, prepared by Morrison Hershfield, dated January 21, 2010, received by the TRCA April 26, 2010; and z General Notes and Details Drawing, Drawing No. C-2, prepared by Morrison Hershfield, dated January 21, 2010, received by the TRCA April 26, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

102 Proposal: The purpose is to construct grading works associated with the construction of a replacement headwall / outfall structure within a Regulated Area of the Humber River watershed. The current headwall structure (located on the adjacent property at 60 Burwick Avenue) collapsed and the adjacent landowner (York Region District School Board) became aware of the problem sometime in 2009. Based upon a site visit conducted by TRCA staff on September 11, 2009, the headwall is located along an upper tier valley wall of the Main Humber River Valley Corridor. The outfall discharges into a hardened drainage feature which then flows into a culvert that eventually drains towards the Main Humber River.

The proposed works on the subject property consist of minor grading works associated with the reconstruction of the hardened drainage feature. The majority of the overall headwall reconstruction works, which are to be conducted on YRDSB lands, are a part of the associated permit application (CFN: 42929) and has also been included on this Executive Committee Agenda.

TRCA ecology staff are satisfied that the existing drainage feature offers minimal ecological value and have no concerns regarding the proposed replacement of the headwall. TRCA geotechnical staff are satisfied that the design of the replacement headwall will offer an improvement over the failed design and will not result in the destabilization of this portion of the valley wall or cause any erosion issues. TRCA water resources staff are satisfied that the headwall and outfall have been sufficiently designed to handle the drainage area based upon calculations and analysis contained in the Stormwater Management Report Addendum prepared by Morrison Hershfield, dated February 10, 2010, received by the TRCA March 3, 2010.

Control of Flooding: The proposed works are not located within the Regional Storm Flood Plain. There will be no impacts on the storage or conveyance of flood waters.

Pollution: Sediment control fencing will be installed for the duration of construction along with a rock check dam to prevent the transport of sediment down the drainage swale and main valley wall.

Dynamic Beaches: Not applicable

Erosion: TRCA geotechnical staff are satisfied that the proposed works will not destabilize the existing slope.

Conservation of Land: As a watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that may be negatively impacted by the project.

103 Plantings All disturbed areas will be restored to their previous vegetated state and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.3 - Infrastructure and Servicing - of the Authority's Valley and Stream Corridor Management Program

CFN: 44312 - Application #: 0587/10/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 28, 2010

EX10.26 CITY OF VAUGHAN To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere in a Regulated Area on Martin Grove Road (Highway 7 to north of Woodbridge Avenue), in the City of Vaughan, Regional Municipality of York, Humber River Watershed as located on property owned by the City of Vaughan. The purpose is to construct a replacement watermain within a cold water fisheries timing window. The proponent has committed to using the Fisheries and Oceans Canada (DFO) Operational Statement for High-Pressure Directional Drilling for the project.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Dwg. No. 1 of 5, General Notes; dated November, 2009; revised May, 2010; received May 5, 2010; prepared by Chisholm, Fleming and Associates; z Dwg. No. 3 of 5, Martin Grove Road Watermain Replacement, Sta. 10+290 to Sta. 10+610; dated April, 2010; revised April, 2010; received May 5, 2010; prepared by Chisholm, Fleming and Associates;

104 z Dwg. No. 5 of 5, Details; dated April, 2010; revised April, 2010; received May 5, 2010; prepared by Chisholm, Fleming and Associates.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposal is to construct a new 400mm diameter watermain to replace the existing 300mm diameter watermain on Martin Grove Road, from Highway 7 to 60m north of Woodbridge Avenue in the City of Vaughan, Regional Municipality of York. Construction of the new watermain will be undertaken by Horizontal Directional Drilling (HDD) within the road right-of-way of Martin Grove Road and within the Regional Storm Flood Plain of Rainbow Creek, which is a tributary of Humber River. The existing watermain will be abandoned.

Control of Flooding: The proposed project will have no impacts on the storage or conveyance of floodwaters.

Pollution: Standard erosion and sediment control measures (heavy-duty silt fencing) will be implemented prior to construction and maintained for the duration of construction, and until the site is stabilized and restored, in order to prevent construction generated sediments from entering any watercourse or wetland. Erosion and sediment control measures have been provided in accordance with the TRCA Erosion and Sediment Control Guideline for Urban Construction.

Dynamic Beaches: Not applicable

Erosion: Staff has no geotechnical/slope stability issues with the proposal.

Conservation of Land: With the erosion and sediment controls in effect, and the works conducted during the cold water (July 1 to September 15) timing window, the potential for a Harmful Alteration, Disruption or Destruction (HADD) of fish habitat will be mitigated.

Plantings All disturbed areas will be restored with native non-invasive species following construction.

Policy Guidelines: This proposal complies with Section 4.3 - Infrastructure and Servicing - of the Authority's Valley and Stream Corridor Management Program.

105 CFN: 43206 - Application #: 0900/09/VAUG Report Prepared by: Suzanne Bevan, extension 5759 For information contact: Suzanne Bevan, extension 5759 Date: June 28, 2010

EX10.27 CITY OF VAUGHAN To site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere in a Regulated Area near Glen Shields Avenue, west of Dufferin Street, in the City of Vaughan, Regional Municipality of York, Don River Watershed as located on property owned by the City of Vaughan. The purpose is to remove sediment from a stormwater management pond to mitigate the impacts of sediment on the downstream receiving watercourse within a warm water fisheries timing window. A Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO) for this project.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing No. 1 of 2; Storm Pond 15 Rehabilitation; dated March, 2010; revised June 23, 2010; received by TRCA June 23, 2010; red-line revised by TRCA June 23, 2010; prepared by the City of Vaughan Public Works Department; z Drawing No. 2 of 2; Storm Pond 15 Rehabilitation; dated March, 2010; revised June 23, 2010; received by TRCA June 23, 2010; prepared by the City of Vaughan Public Works Department.

RATIONALE The application was reviewed by staff on the basis of the following information:

106 Proposal: The proposal involves the removal of sediment from a stormwater management pond (Pond #15) east of Glen Shields Avenue, west of Dufferin Street, in the City of Vaughan, Regional Municipality of York. The water from the stormwater management pond will be pumped through pipes to an enviro-bag filter system and discharged to a vegetated ditch to the west of the pond. The sediment removal will take approximately one day. The sediment will be temporarily stockpiled on site and then disposed of off site.

Control of Flooding: The proposed work will not have any impacts to the storage or conveyance of flood waters.

Pollution: Standard erosion and sediment control measures (silt fencing and coffer dam) will be implemented prior to construction and maintained for the duration of the works in order to prevent sediment from entering any watercourse. Erosion and sediment control measures have been provided in accordance with the TRCA Erosion and Sediment Control Guideline for Urban Construction.

Dynamic Beaches: Not applicable

Erosion: Staff has no geotechnical/slope stability issues with this proposal.

Conservation of Land: With erosion and sediment control measures in place and the works conducted during the warm water (July 1 to March 31) timing window, the potential for Harmful, Alteration, Disruption or Destruction (HADD) of fish habitat will be mitigated. A Letter of Advice will be prepared by TRCA staff on behalf of Fisheries and Oceans Canada (DFO) for this project.

Plantings All disturbed areas will be restored with native, non-invasive species following construction if required.

Policy Guidelines: The proposal complies with Section 4.3 - Infrastructure and Servicing of the Authority's Valley and Stream Corridor Management Program.

CFN: 43784 - Application #: 0184/10/VAUG Report Prepared by: Louise Monaghan, extension 5756 For information contact: Suzanne Bevan, extension 5759 Date: June 28, 2010

107 EX10.28 FERNBOOK HOMES (2005) LIMITED To construct, reconstruct, erect or place a building or structure and site grade on Lot 16, Concession 2, (441 Marc Santi Boulevard), in the City of Vaughan, Don River Watershed as located on the property owned by Fernbook Homes (2005) Limited. The purpose is to conduct site grading and construct a rear yard deck associated with the construction of a new dwelling within a Regulated Area of the Don River watershed at 441 Marc Santi Boulevard in the City of Vaughan.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Plan, prepared by RN Design, revise dated June 15, 2010, received by the TRCA June 14, 2010, redline revised to indicate the removal excess fill material and location of sediment control fencing.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to conduct site grading and construct a rear yard deck associated with the development of a vacant lot within the Don River watershed. A tributary of the East Don River is in close proximity of the rear of the subject property.

As part of the associated Draft Plan of Subdivision for this property (19T-95066 - Nine-Ten West Ltd.) and the associated Block 11 MESP process, the extent of the feature was defined and an appropriate buffer was created around the feature. The subject property is currently devoid of vegetation and the proposed works are located outside of the buffer which was conveyed to the TRCA as part of the Draft Plan of Subdivision process.

108 Control of Flooding: The proposed works are not located within the Regional Storm Flood Plain, there will be no impacts on the storage or conveyance of flood waters.

Pollution: Sediment control fencing will be erected and maintained for the duration of construction to prevent the transport of sediment into the adjacent buffer area.

Dynamic Beaches: Not applicable.

Erosion: There are no geotechnical issues associated with this application.

Conservation of Land: As a watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that may be negatively impacted by the project.

Plantings All disturbed area will be restored to a sodded condition and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.2.2 E) - Property Improvement and Ancillary Structures - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44283 - Application #: 0559/10/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 23, 2010

EX10.29 290 NASHVILLE ROAD To construct, reconstruct, erect or place a building or structure and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 24, 25, Concession 8, 9, (290 Nashville Road), in the City of Vaughan, Humber River Watershed. The purpose is to construct a cabana within a Regulated Area of the Humber River Watershed at 290 Nashville Road in the City of Vaughan.

109 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Sheet No. A1, Site Plan, prepared by S. Soscia, dated March 20, 2007, received by the TRCA on June 17, 2010, redline revised to correct the address of the site; z Sheet No. A2, Floor Plan, prepared by S. Soscia, dated April 27, 2010, received by the TRCA on June 17, 2010, redline revised to correct the address of the site.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposal involves the construction of a 41.31 square-metre (445 square-foot) cabana. The foundation for the cabana has already been installed, as was noted by TRCA staff during our site visits on April 6, 2010 and May 28, 2010. A violation notice has been issued by TRCA Enforcement staff and all work has stopped on the site. The applicant is awaiting approval from the TRCA and the City of Vaughan before recommencing these works.

The existing residence, pool and ancillary structures are entirely situated within the Humber River valley corridor. The proposed cabana will also be located within the valley corridor within the rear yard of the existing home. No natural features have been altered or removed to facilitate the construction of the cabana.

Fee: As the construction of the cabana was started prior to the issuance of a permit under Ontario Regulation 166/06, an additional administrative fee was charged on this application.

Control of Flooding: The proposed development will not be located within the Regional Storm flood plain. There will be no impact on the storage or conveyance of floodwaters.

110 Pollution: Excavation for the cabana commenced prior to receipt of a permit from the TRCA; however, no sedimentation appeared to have occurred during the excavation activities. The proposed cabana will be approximately 60 metres (197 feet) from the Humber River and will be separated from the watercourse and adjacent vegetation by the existing house, driveway and retaining walls.

Dynamic Beaches: Not applicable.

Erosion: The existing house is located on the valley slope. The cabana will be situated on the terraced rear yard, approximately 1 metre (3 feet) from an existing retaining wall. TRCA staff are satisfied that there will be no geotechnical/slope stability issues associated with the cabana construction and its location.

Conservation of Land: As the watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that may be negatively impacted by the project.

Plantings All disturbed areas will be restored upon completion of the project.

Policy Guidelines: The proposal is consistent with Section 4.2.2 E) - Property Improvements and Ancillary Structures - of the Authority's Valley and Stream Corridor Management Program.

CFN: 43862 - Application #: 0247/10/VAUG Report Prepared by: Coreena Smith, extension 5269 For information contact: Coreena Smith, extension 5269 Date: June 28, 2010

EX10.30 156 RIVERSIDE DRIVE To construct, reconstruct, erect or place a building or structure on Lot 25, Plan M-111, (156 Riverside Drive), in the City of Vaughan, Humber River Watershed. The purpose is to construct a replacement home within a Regulated Area of the Humber River watershed at 156 Riverside Drive in the City of Vaughan.

111 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Plan, Drawing No. A-1, dated April 2010, received by the TRCA April 28, 2010, redline revised to indicate the removal of excess fill material.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct a replacement home within a Regulated Area of the Humber River watershed. The subject property is located on the valley floor of the Main Humber River Valley. The rear portion of the property is located within the Regional Storm Flood Plain and based upon a site visit conducted by TRCA staff on March 30, 2010, contains an approximate 2 H : 1 V steep, but shallow slope. The property is also entirely located within the Woodbridge Special Policy Area.

The property currently contains a dwelling located outside of the flood prone portion of the site (approximately 5 metres from the flood fringe) and a detached garage that is located within the flood plain. The proposed works include the removal of the existing detached garage and the construction of a replacement home that will not encroach further towards the flood plain than the existing home.

Based upon a Slope Stability Assessment prepared by Haddad Geotechnical Inc., dated May 31, 2010, the proposed replacement dwelling will be located approximately 15 metres away from the long-term-stable top-of-slope.

Control of Flooding: The proposed works are located outside of the Regional Storm Flood Plain and an existing garage located within the flood plain will be removed and not replaced. There will be no impacts on the storage and conveyance of flood waters.

112 Pollution: Sediment control fencing will be erected and maintained for the duration of construction to prevent the transport of sediment into the lower tableland area and the Humber River.

Dynamic Beaches: Not applicable.

Erosion: TRCA Geotechnical Staff are satisfied that the proposed works are adequately setback from the long-term-stable top-of-slope and will not affect the stability of the slope feature located on the property.

Conservation of Land: As the watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that may be negatively impacted by the project.

Plantings All disturbed areas will be restored to the existing sodded condition and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.2.1 B) - Development / Redevelopment within Designated Two Zone Areas or Special Policy Areas and 4.2.2 D) - Replacement Structures - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44047 - Application #: 0381/10/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 17, 2010

EX10.31 181 RANCH TRAIL ROAD To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 9, Plan M89, (181 Ranch Trail Road), in the City of Vaughan, Humber River Watershed. The purpose is to construct an inground pool, cabana and patio area within a Regulated Area of the Humber River watershed at 181 Ranch Trail Road in the City of Vaughan.

113 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Plan, prepared by the applicant, received by the TRCA June 3, 2010, redline revised to indicate the removal of excess fill material.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct an inground pool, cabana and patio area within a Regulated Area of the Humber River watershed. Based upon a site visit conducted by TRCA staff May 26, 2008 as part of our previous review for the construction of a new home on the subject property (Ontario Regulation 166/06 Permit No. C-08506), TRCA staff determined that the subject property is located along the edge of a wide, gently sloped valley system and contains a highly altered shallow draw feature. This draw feature is located on the east side of the subject property. The rear of the property backs onto a valley / stream corridor. The subject property does not contain any significant natural vegetation.

The proposed works are located along the edge of the shallow draw feature but will not result in the loss of any vegetation and will not cause any geotechnical issues due to the mild and shallow slope configuration and the lack of any existing significant vegetation across the entire area of the draw feature.

The proposed works are located over 85 metres away from the valley / stream corridor located beyond the rear property line.

Control of Flooding: The proposed works are not located within the Regional Storm Flood Plain. There will be no impacts on the storage or conveyance of flood waters.

114 Pollution: Sediment control fencing will be erected and maintained for the duration of construction to prevent the transport of sediment onto adjacent lands.

Dynamic Beaches: Not applicable.

Erosion: TRCA geotechnical staff are satisfied that due to the shallow and mild inclination of the slope feature, there will be no impacts on the stability of the slope feature.

Conservation of Land: As a watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that may be negatively impacted by the project.

Plantings All disturbed areas will be restored to the existing sodded condition and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.2.2 E) - Property Improvements and Ancillary Structures - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44262 - Application #: 0543/10/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 28, 2010

EX10.32 9652 KEELE STREET To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on , (9652 Keele Street), in the City of Vaughan, Don River Watershed. The purpose is to construct an inground pool within Regulated Area of the Don River watershed at 9652 Keele Street in the City of Vaughan.

115 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Plan, prepared by the applicant, received by the TRCA June 17, 2010, redline revised to indicate the location of sediment control fencing and removal of excess fill material.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct an inground pool within a Regulated Area of the Don River watershed. The subject property is located adjacent to a hardened tributary of the West Don River and is entirely within the Regional Storm Flood Plain. In addition, based upon a site visit conducted by TRCA staff on June 16, 2010, an approximately 1 metre tall municipally constructed retaining wall is located at the property boundary roughly 1 metre away from the edge of the watercourse. The proposed works are located 2 metres inland from the retaining wall and is on flat, sodded tableland devoid of any significant vegetation. No grade changes are proposed as part of this permit.

TRCA geotechnical staff are satisfied with the proposed 2 metre setback from the low retaining wall. TRCA water resources engineer are satisfied that as the proposed works do not include any changes to the existing grades and does not propose any above-ground structures, there will be no impacts on the storage or conveyance of flood waters.

Control of Flooding: The proposed works are located within the Regional Storm Flood Plain. TRCA water resources engineer are satisfied that as the proposed works do not include any changes to the existing grades and does not propose any above-ground structures, there will be no impacts on the storage or conveyance of flood waters.

116 Pollution: Sediment control fencing will be erected to prevent the transport of sediment to the watercourse.

Dynamic Beaches: Not applicable.

Erosion: TRCA geotechnical staff are satisfied that the proposed works are adequately setback from the existing retaining wall.

Conservation of Land: As the watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that may be negatively impacted by the project.

Plantings All disturbed areas will be restored to the existing sodded condition and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.2.2 E) - Property Improvements and Ancillary Structures - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44284 - Application #: 0560/10/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 28, 2010

EX10.33 YORK REGION DISTRICT SCHOOL BOARD To construct, reconstruct, erect or place a building or structure and site grade on Lot 6, Concession 7, (60 Burwick Avenue), in the City of Vaughan, Humber River Watershed as located on the property owned by York Region District School Board. The purpose is to construct a replacement headwall / outfall structure within a Regulated Area of the Humber River watershed at 60 Burwick Avenue in the City of Vaughan.

117 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Plan and Cross-Section Drawing, Drawing No. C-1, prepared by Morrison Hershfield, dated January 21, 2010, received by the TRCA April 26, 2010; z General Notes and Details Drawing, Drawing No. C-2, prepared by Morrison Hershfield, dated January 21, 2010, received by the TRCA April 26, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct a replacement headwall / outfall structure within a Regulated Area of the Humber River watershed. The current headwall structure collapsed and York Region District School Board became aware of the problem sometime in 2009. Based upon a site visit conducted by TRCA staff on September 11, 2009, the headwall is located along an upper tier valley wall of the Main Humber River Valley Corridor. The outfall discharges into a hardened drainage feature which then flows into a culvert that eventually drains towards the Main Humber River.

The proposed works are partially located in lands owned by Canadian Pacific Railway. Accordingly, the associated permit application (CFN: 44312) has also been included on this Executive Committee Agenda.

TRCA ecology staff are satisfied that the existing drainage feature offers minimal ecological value and have no concerns regarding the proposed replacement of the headwall. TRCA geotechnical staff are satisfied that the design of the replacement headwall will offer an improvement over the failed design and will not result in the destabilization of this portion of the valley wall or cause any erosion issues. TRCA water resources staff are satisfied that the headwall and outfall have been sufficiently designed to handle the drainage area based upon calculations and analysis contained in the Stormwater Management Report Addendum prepared by Morrison Hershfield, dated February 10, 2010, received by the TRCA March 3, 2010. 118 Control of Flooding: The proposed works are not located within the Regional Storm Flood Plain. There will be no impacts on the storage or conveyance of flood waters.

Pollution: Sediment control fencing will be installed for the duration of construction along with a rock check dam to prevent the transport of sediment down the drainage swale and main valley wall.

Dynamic Beaches: Not applicable

Erosion: TRCA geotechnical staff are satisfied that the proposed works will not destabilize the existing slope.

Conservation of Land: As a watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that may be negatively impacted by the project.

Plantings All disturbed areas will be restored to their previous vegetated state and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.3 - Infrastructure and Servicing - of the Authority's Valley and Stream Corridor Management Program

CFN: 42929 - Application #: 0686/09/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 28, 2010

TOWN OF CALEDON

EX10.34 16358 HUMBER STATION ROAD To construct, reconstruct, erect or place a building or structure and site grade on Lot 22, Concession 4, (16358 Humber Station Road), in the Town of Caledon, Humber River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a replacement septic system at the rear of an existing dwelling associated with a municipal building permit.

119 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Plan, stamped received by TRCA Planning & Development staff on June 16, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a replacement septic system at the rear of an existing dwelling located at 16358 Humber Station Road, in the Town of Caledon. The subject property is located within a tiered valley corridor. The proposed Waterloo biofilter septic system is located on a tableland portion of the site, on a manicured lawn and is setback sufficiently from the valley slope. As such, no geotechnical concerns are anticipated with this proposal. Additionally, there are no ecology or flooding related concerns with this proposal.

Control of Flooding: The proposed works are located outside of the Regional Floodplain. As such, no impacts to the storage and/or conveyance of flood waters are anticipated.

Pollution: Appropriate erosion and sediment controls (silt fence) have been proposed with this application, and will be maintained throughout all phases of construction.

Dynamic Beaches: Not applicable.

Erosion: There are no geotechnical and/or slope stability concerns anticipated with this project.

120 Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings The proposed septic bed is located within an existing manicured lawn. As such, no significant vegetation will be removed as a result of the construction.

Policy Guidelines: This proposal is in conformity with Section 4.2.2 (E) – Property Improvements and Ancillary Structures – of the Authority’s Valley and Stream Corridor Management Program (VSCMP).

CFN: 44278 - Application #: 0566/10/CAL Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: June 29, 2010

EX10.35 40 JOHN STREET To construct, reconstruct, erect or place a building or structure on Lot 80, Block 1, Plan BOL-7, (40 John Street), in the Town of Caledon, Humber River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of an in-ground swimming pool at the rear of an existing dwelling associated with a municipal building permit.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z SIte Plan, redline revised by TRCA Planning Staff on June 25, 2010, stamped received by TRCA Planning & Development staff on June 18, 2010.

121 RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of an in-ground swimming pool at the rear of an existing dwelling located at 40 John Street, in the Town of Caledon. The subject property is located entirely within the Regional Floodplain adjacent to the Humber River and is also within the Bolton Special Policy Area (SPA). All existing grades surrounding the in-ground swimming pool will be maintained. In addition, all applicable SPA criteria will be met and the proposed pool will be located outside of the EPA portion of the lot adjacent to the Humber River. As such, there are no flooding concerns associated with this proposal. In addition, there are no geotechnical or ecology related concerns anticipated with this proposal.

Control of Flooding: All existing grades are to be maintained. As such, the proposed works will not affect the storage or conveyance of floodwaters.

Pollution: Appropriate erosion and sediment controls (silt fence) have been proposed with this application, and will be maintained throughout all phases of construction.

Dynamic Beaches: Not applicable.

Erosion: There are no geotechnical or erosion concerns anticipated with this project.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings The proposed pool is located within an existing manicured lawn. As such, no significant vegetation will be removed as a result of the construction.

Policy Guidelines: This proposal is in conformity with Section 4.2.2 (E) – Property Improvements and Ancillary Structures – of the Authority’s Valley and Stream Corridor Management Program (VSCMP).

CFN: 44228 - Application #: 0516/10/CAL Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: June 29, 2010

122 EX10.36 436 KING STREET EAST To construct, reconstruct, erect or place a building or structure and site grade on , (436 King Street East), in the Town of Caledon, Humber River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a replacement septic system adjacent to an existing residential dwelling associated with a municipal building permit.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Plan & Section, prepared by Indian Line Excavating & Grading, dated May 30, 2010, Redline revised by TRCA Planning staff on June 28, 2010, stamped received by TRCA Planning & Development staff on June 14, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a replacement septic system adjacent to an existing dwelling located at 436 King Street East, in the Town of Caledon. The rear of the subject property is adjacent to the Humber River and the property is located within the valley corridor. The proposed septic system is located on a manicured lawn on a flat portion of the site and is setback sufficiently from the valley slope. As such, no geotechnical concerns are anticipated with this proposal. Additionally, there are no ecology or flooding related concerns with this proposal.

Control of Flooding: The proposed works are located outside of the Regional Floodplain. As such, no impacts to the storage and/or conveyance of flood waters are anticipated.

123 Pollution: Appropriate erosion and sediment controls (silt fence) have been proposed with this application, and will be maintained throughout all phases of construction.

Dynamic Beaches: Not applicable.

Erosion: There are no geotechnical and/or slope stability concerns anticipated with this project.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings The proposed septic bed is located within an existing manicured lawn. As such, no significant vegetation will be removed as a result of the construction.

Policy Guidelines: This proposal is in conformity with Section 4.2.2 (E) – Property Improvements and Ancillary Structures – of the Authority’s Valley and Stream Corridor Management Program (VSCMP).

CFN: 44280 - Application #: 0563/10/CAL Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: June 29, 2010

TOWN OF MARKHAM

EX10.37 93 MAIN STREET To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units on Part Lot 2, Plan RP445, (93 Main Street), in the Town of Markham, Rouge River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed to raise the finished flood elevation of an existing dwelling 0.6m and fix the existing foundation.

124 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Drawing SD1, Site Plan, prepared by David Johnston Architect, dated June 2010, stamped received by TRCA Planning and Development June 8, 2010; z Drawing A3.1, Exterior Elevations, prepared by David Johnston Architect, dated May 2010, stamped received by TRCA Planning and Development June 8, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed to raise the finished flood elevation of an existing dwelling 0.6m and fix the existing foundation. The subject property is located within an approved residential subdivision. The subject property is entirely located within the Regional Storm Floodplain and is also located within the Unionville Special Policy Area (SPA). The SPA designation recognizes areas within a community such as the Unionville SPA that has historically existed in the floodplain and where strict adherence to Province wide policies concerning new development would result in social or economic hardships for the community. Under the SPA criteria, redevelopment on a small scale may be permitted within the floodplain provided adequate flood proofing measures can be incorporated into the design and construction of all proposed buildings. Based on our review of the plans, the applicant has proposed additional basement windows however the proposed structure will be floodproofed in accordance with TRCA's requirements. The area to which this application applies is void of any significant vegetation. As such, no significant vegetation will be removed as a result of construction.

125 Control of Flooding: TRCA staff has reviewed this proposal and do not anticipate any impacts to the storage and/or conveyance of flood waters. The proposed development is adequately flood protected and has been designed to withstand water flow velocities associated with the Regional Storm event. As well, the proposed development is located outside of the hydraulic floodway. All excavated fill will be removed from the floodplain.

Pollution: Appropriate erosion and sediment controls will be erected and maintained throughout all phases of construction in accordance with TRCA guidelines.

Dynamic Beaches: Not applicable

Erosion: There are no geotechnical and/or slope stability concerns related to this application.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings Since no significant vegetation will be removed, additional plantings are not required.

Policy Guidelines: This proposal is consistent with Section 4.2.1 (B) - Development Guidelines for Development/Redevelopment within Designated Two Zone Areas or Special Policy Areas and Section 4.2.2 (E) - Property Improvements and Ancillary Structures - of the Authority's Valley and Stream Corridor Management Program (VSCMP).

CFN: 44243 - Application #: 0527/10/MARK Report Prepared by: Lisa Stern, extension 5370 For information contact: Quentin Hanchard, extension 5324 Date: June 29, 2010

126 EX10.38 REGIONAL MUNICIPALITY OF YORK To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on , (South West Corner of Major Mackenzie and Warden Avenue), in the Town of Markham, Rouge River Watershed as located on the property owned by Regional Municipality of York. The purpose is to reconstruct an eroded outfall through constructing structures (new storm sewer outfall, armourstone wall, concrete headwall, new rip rap outfall) within a Regional Storm Floodplain; to site grade and place material (for access route, existing rip rap outfall removal, catch basin and corrugated steel pipe removal and rock removal from creek bed) in a Regulated Area; and to temporarily alter a watercourse (Berczy Creek ) during the redside dace timing window to facilitate the outfall reconstruction in the dry and to remove the rocks by hand from the creek. A Letter of Advice will be issued by TRCA staff on behalf of Fisheries and Oceans Canada.

The permit will be issued for the period of July 9, 2010 to July 8, 2012. z Letter of Undertaking (to provide revisions to engineering and landscape drawings); dated June 9, 2010; received June 9, 2010; prepared by The Regional Municipality of York.

RATIONALE The application was reviewed by staff on the basis of the following information:

127 Proposal: The original rip rap outfall on the south side of Major Mackenzie Drive, west of Warden Avenue that was constructed as part of the Major Mackenzie Drive project has failed. It is surmised that the source of the erosion problem rests with the velocity associated with the flows exiting the existing outfall pipe upslope. The proposed storm sewer outfall works were deemed to be an emergency and this file proceeded through the emergency works process. An Emergency Works Authorization letter was issued on June 9, 2010 which enabled the Regional Municipality of York to tender and award the contract prior to the redside dace timing window opening on July 1, 2010. In order to address the erosion issue, the proposal involved removing the existing rip rap outfall, catch basin and corrugated steel pipe outlet, and installing a new storm sewer, concrete headwall, armourstone headwall and rip rap outlet to dissipate energy after exiting the storm sewer and entering Berczy Creek. The outfall restoration component did not involve any in water works other than removing the rocks by hand that were relocated to the Berczy Creek during the erosion. However, the project involved near water works in order to remove the existing rip rap outlet in the dry through a dam and pump around method and to replace with storm sewers. All other exposed slopes were stabilized and seeded.

Control of Flooding: The proposed new outfall will not have any implications to flooding.

Pollution: Standard erosion control measures (dam and pump, silt fences) will be implemented to ensure that the construction-generated sediments do not enter the watercourse.

Dynamic Beaches: Not applicable

Erosion: The current proposal is designed to address the existing erosion situation.

Conservation of Land: There will be in stream works associated with this project. The rock material that has moved down gradient to Berczy Creek as a result of the failure of the existing rip rap outfall will be removed by hand. The works at the site of the existing outfall will be isolated from the Berczy Creek with a dam and pump around method. With erosion and sedimentation plans in effect, the potential for a harmful alteration, disruption or destruction (HADD) of fish habitat will be mitigated and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO) with a redside dace timing window restriction. TRCA staff has noted to the proponent that the watercourse has been identified as redside dace habitat and with the uplisting of this fish under the Ontario Endangered Species Act in February 2009 approvals from the Ministry of Natural Resources may be required for this project. The proponent is working with MNR in this regard. The proposed works will impact no significant terrestrial resource features.

Plantings All disturbed areas will be restored with native/non-invasive seed species following construction.

128 Policy Guidelines: The proposal complies with Section 4.3 - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44191 - Application #: 0523/10/MARK Report Prepared by: June Murphy, extension 5304 For information contact: June Murphy, extension 5304 Date: June 9, 2010

TOWN OF WHITCHURCH-STOUFFVILLE

EX10.39 95 CEDAR RIDGE ROAD To construct, reconstruct, erect or place a building or structure on Lot 9, Plan 65M-3909, (95 Cedar Ridge Road), in the Town of Whitchurch-Stouffville, Rouge River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed in order to facilitate the construction of a dwelling on a vacant lot.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Sketch Showing Elevations, prepared by Rady-Pentex & Edward Surveying Ltd., Dated May 5, 2010, stamped received by TRCA Planning and Development May 26, 2010, redline revised by TRCA Staff; z Site Plan, prepared by Rady-Pentex & Edward Surveying Ltd., Dated May 26, 2010, stamped received by TRCA Planning and Development May 26, 2010; z OPSD 219.130, Heavy Duty Silt Fencing.

RATIONALE The application was reviewed by staff on the basis of the following information:

129 Proposal: The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed in order to facilitate the construction of a dwelling on a vacant lot. The subject lands are located in the Cedar Ridge subdivision in the rural portion of the Town of Whitchurch Stouffville east of Woodbine Road and south of Bloomington Road on the Oak Ridges Moraine in the headwaters of the Rouge River. There is a portion of valley corridor that traverses the subject lands. Based on a site inspection and on a geotechnical report submitted by the applicant, it appears that the proposed dwelling will be appropriately setback from the valley. Although the subject lands are partially vegetated, the area to which this application applies does not contain any significant vegetation, as such no compensation is required.

Control of Flooding: The proposal is located entirely outside of the Regional Storm Flood Plain, as such impacts to the flow and/or conveyance of flood waters is not anticipated.

Pollution: Appropriate erosion and sediment controls will be utilized and maintained throughout all phases of construction.

Dynamic Beaches: Not applicable

Erosion: The applicant has submitted a geotechnical report and TRCA Staff have confirmed are no geotechnical and/or slope stability concerns associated with this application.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings Since no significant vegetation will be removed, additional plantings are not required.

Policy Guidelines: The works are consistent with Section 4.1 - New Development - of the Valley and Stream Corridor Management Program.

CFN: 44198 - Application #: 0489/10/WS Report Prepared by: Lisa Stern, extension 5370 For information contact: Chris Jones, extension 5718 Date: June 28, 2010

130 TOWNSHIP OF KING

EX10.40 12855 HIGHWAY 27 SOUTH To construct, reconstruct, erect or place a building or structure on Part Lot 4, 5, Concession 8, (12855 Highway 27 South), in the Township of King, Humber River Watershed. The purpose is to construct a replacement detached garage within a Regulated Area of the Humber River watershed at 12855 Highway 27 in the Township of King.

The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Plan, prepared by the applicant, received by the TRCA June 1, 2010, redline revised to indicate the removal of excess fill material

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct a replacement detached garage within a Regulated Area of the Humber River watershed. A tributary of the East Humber River traverses the rear of the subject property; however, sometime between 2007 and 2009, this feature was enclosed with a culvert by the property owner (without engineering review and TRCA's or municipal approvals).

The existing tributary is an open channel south of the subject property, however, the tributary enters a municipally constructed culvert approximately 26 metres north of the subject property. As the culvert works on the subject property were completed beyond our statue of limitations, TRCA staff will not be pursuing violation charges for its construction at this time. The approval of the proposed garage is not a concern related to this channel reconstruction.

131 TRCA water resources staff are satisfied that even with the construction of the unauthorized culvert, the proposed garage will have minimal impacts on the storage and conveyance of flood waters as this is a headwater feature with limited drainage area.

The proposed replacement garage will not encroach further towards the existing open portions of the tributary along the northern and southern property boundaries.

Control of Flooding: The proposed works are not located within the Regional Storm Flood Plain. There will be no impacts on the storage or conveyance of flood waters.

Pollution: There are no pollution issues associated with this application as the works are located on a flat, sodded area.

Dynamic Beaches: Not applicable.

Erosion: There are no geotechnical issues associated with this proposal.

Conservation of Land: As a watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural feature on or adjacent to the site that may be negatively impacted by the project.

Plantings All disturbed areas will be restored to the existing sodded condition and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.2.2 D) - Replacement Structures - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44207 - Application #: 0498/10/KING Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 18, 2010

EX10.41 69 LYNWOOD CRESCENT To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Part Lot 28, 29, Plan 457, (69 Lynwood Crescent), in the Township of King, Humber River Watershed. The purpose is to construct a second floor addition and a garage addition to the front of an existing dwelling within a Regulated Area of the Humber River watershed at 69 Lynwood Crescent in the Township of King. 132 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Plan, Drawing No. A1, prepared by Battaglia Architect Inc., dated April 29, 2010, received by the TRCA June 16, 2010, redline revised to indicate the removal of excess fill material; z Basement and Ground Floor Plan, Drawing No. A2, prepared by Battaglia Architect Inc., dated April 29, 2010, received by the TRCA June 16, 2010; z Second Floor Plan, Drawing No. A3, prepared by Battaglia Architect Inc., dated April 29, 2010, received by the TRCA June 16, 2010; and z Elevations Drawing, Drawing No. A4, prepared by Battaglia Architect Inc., dated April 29, 2010, received by the TRCA June 16, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct a second floor addition and a garage addition to an existing dwelling within a Regulated Area of the Humber River watershed. The rear of the subject property is traversed by a tributary of the East Humber River and its associated Regional Storm Flood Plain. The existing dwelling is located approximately 12 metres away from the flood plain.

The proposed second floor addition is located directly above the existing ground floor and will not result in any further encroachment towards the natural features at the rear of the property. The proposed garage addition is located at the front of the existing home and will extend away from the feature towards the roadway. The garage addition is located within an area devoid of vegetation.

TRCA water resources staff are satisfied that the proposed works are adequately setback from the flood plain and will have no impacts on the storage or conveyance of flood waters.

133 Control of Flooding: The proposed works are not located within the Regional Storm Flood Plain. There will be no impacts on the storage or conveyance of flood waters.

Pollution: There are no pollution related issues associated with this project.

Dynamic Beaches: Not applicable

Erosion: There are no geotechnical issues associated with this project.

Conservation of Land: As a watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that may be negatively impacted by the project.

Plantings All disturbed areas will be restore to the existing sodded condition and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.2.2 C) - Minor Additions - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44285 - Application #: 0562/10/KING Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 28, 2010

EX10.42 KING NORTH DEVELOPMENTS CR INC. To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on Part Lot 6, Concession 3, (north of King Road, west of Dufferin Street), in the Township of King, Humber River Watershed as located on the property owned by King North Developments CR Inc. The purpose is to install a sanitary sewer line under a tributary of the Humber River, in order to provide servicing for a proposed residential subdivision known as King North, located northwest of King Road and Dufferin Street, in the Township of King.

134 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Red-Line Revised Plan and Profile - Sanitary Sewer Easement, Drawing No. 206176-P4, prepared by EMC Group, Revision No. 1 (revised June 4, 2010), received June 7, 2010; z Red-Line Revised Plan and Profile - Sanitary Sewer Easement, Drawing No. 206176-P5, prepared by EMC Group, Revision No. 1 (revised April 29, 2010), received April 30, 2010.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposal is to conduct site grading works in order to install a sanitary sewer line under a tributary of the Humber River, in order to facilitate the servicing of a proposed residential subdivision known as King North, in the King City East Community, in the Township of King.

The subject property is located northwest of King Road and Dufferin Street. The proposed sanitary sewer line is oriented in an east-west configuration and will be installed by jack and bore. Two manhole/auger pits will be installed via open cut at each end of the proposed sanitary line. The sanitary sewer line is to be installed a minimum of 2 metres below the invert of the watercourse, in order to minimize any potential disturbance. Dewatering is not expected as part of the installation works, however, if dewatering is necessary, it will be controlled with sump pumps discharging to an enviro-bag at least 30 metres from the watercourse.

Control of Flooding: The proposed line is located under the watercourse while the manholes will be located at grade on the site. As such, TRCA technical staff are satisfied that the works will not negatively impact the storage or conveyance of flood waters.

135 Pollution: Erosion and sediment control fencing will be erected around the work site as part of the overall grading of the subject property. These measures will be maintained for the duration of the works.

Dynamic Beaches: Not applicable.

Erosion: Erosion will be minimized through the implementation of the aforementioned sediment control measures. There are no geotechnical/slope stability issues associated with the proposed works.

Conservation of Land: There will be no in-water works associated with the proposal. Given the installation of the sanitary line under the watercourse, a Letter of Advice will be issued on behalf of Fisheries and Oceans Canada.

Plantings An edge management/restoration plan will be implemented as part of the overall draft approved plan of subdivision. This includes the restoration of the 30 metre buffer established from the valley slope.

Policy Guidelines: This proposal complies with Section 4.3 - Infrastructure and Servicing, of the TRCA's Valley and Stream Corridor Management Program.

CFN: 43721 - Application #: 0138/10/KING Report Prepared by: Kevin Huang, extension 5307 For information contact: Kevin Huang, extension 5307 Date: June 29, 2010

EX10.43 141 KINGSCROSS DRIVE To site grade at 141 Kingscross Drive, in the Township of King, Humber River Watershed. The purpose is to construct a replacement septic system within a Regulated Area of the Humber River watershed at 141 Kingscross Drive in the Township of King.

136 The permit will be issued for the period of July 9, 2010 to July 8, 2012 in accordance with the following documents and plans which form part of this permit: z Site Plan, prepared by Young & Young Surveying Inc., received by the TRCA June 2, 2010, redline revised to indicate the removal of excess fill material.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct a replacement septic system within a Regulated Area of the Humber River watershed. According to our mapping and the site plan provided, the replacement septic system will be re-located near the top-of-slope of the valley corridor of a tributary of the Humber River.

Based upon a site visit conducted by TRCA staff on June 22, 2010, the proposed works are located on a very gentle 5H : 1V slope and located within an already disturbed area that is devoid of significant vegetation. Additionally, the proposed septic system will be located next to an existing tennis court. TRCA geotechnical staff are satisfied that the proposed works will not impact the stability of the slope feature.

Control of Flooding: The proposed works are not located within the Regional Storm Flood Plain. There will be no impacts on the storage or conveyance of flood waters.

Pollution: There are no sediment transport issues associated with this application.

Dynamic Beaches: Not applicable.

137 Erosion: TRCA geotechnical staff are satisfied that the proposed works will not impact the stability of the slope feature.

Conservation of Land: As a watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural feature on or adjacent to the site that may be negatively impacted by the project.

Plantings All disturbed areas will be restored to the existing sodded condition and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.3 - Infrastructure and Servicing - of the Authority's Valley and Stream Corridor Management Program

CFN: 44206 - Application #: 0497/10/KING Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 23, 2010

PERMIT APPLICATIONS EX10.44 - EX10.65 ARE ERRATA ITEMS:

Staff's recommendation for approval is based upon the review and acceptance of additional information from the applicant. The applicant has been informed that the information outstanding must be reviewed and accepted by staff prior to the Executive Committee Meeting. Staff will advise that this application be withdrawn from the Executive Committee Agenda should this information remain outstanding.

CITY OF BRAMPTON

EX10.44 CITY OF BRAMPTON To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material originating on the site or elsewhere on McVean Drive approximately 300 metres north of Cottrelle Boulevard in the City of Brampton, Humber River Watershed, as located on property under a permanent easement (location of outlet structure) and temporary easement (drainage area) agreement with the City of Brampton. The purpose is to construct a channel outfall at McVean Drive approximately 300 m north of Cottrelle Boulevard. No in-water works will take place.

138 The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: This proposal involves the construction of an outfall and overland flow route at McVean Drive, north of Cottrelle Boulevard. The outfall will be constructed on the east side of McVean Drive and will convey overland flow from the McVean Drive right-of-way to the Humber River as sheet flow. The outlet will consist of a turfstone pad that will be filled with topsoil and seeded.

Control of Flooding: There will be no impacts to the control of flooding.

Pollution: Standard erosion and sediment control measures (silt fence) will be implemented for the duration of construction, and until the site is restored, in order to prevent construction generated sediment from entering the watercourse.

Dynamic Beaches: Not applicable

Erosion: There are no slope stability issues related to the works.

Conservation of Land: Works will take place a minimum of 150 metres from the watercourse. No in-water works will take place.

139 Plantings No vegetation removals are anticipated for this work. All disturbed areas will be stabilized and seeded.

Policy Guidelines: This proposal complies with Section 4.3 - Infrastructure and Servicing - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44299 - Application #: 0578/10/BRAM Report Prepared by: Sharon Lingertat, extension 5717 For information contact: Sharon Lingertat, extension 5717 Date: June 28, 2010

EX10.45 REGIONAL MUNICIPALITY OF PEEL To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on , (The Gore Road from Cottrelle Boulevard to Castlemore Road), in the City of Brampton, Humber River Watershed as located on the property owned by Regional Municipality of Peel. The purpose is to widen The Gore Road from Cottrelle Boulevard to Castlemore Road. A storm sewer system will be constructed as part of the road improvements and the existing Wylie's South and Wylie's North bridges will both be extended on the west side. The warmwater fisheries timing window will be applied to this project and a Letter of Advice written by TRCA on behalf of Fisheries and Oceans Canada (DFO).

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

140 RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposal consists of 2 separate applications (CFN 39419 and 43964) for road improvements along The Gore Road from north of Cottrelle Boulevard to north of Castlemore Road. Both of these applications will proceed to the July 9, 2010 Executive Committee Meeting for approval.

This proposal (CFN 39419) is for The Gore Road widening from north of Cottrelle Boulevard to Castlemore Road. The Gore Road will be widened from an existing 2-lane rural roadway to a 4-lane urban section with a central raised median to separate north and southbound traffic. Left and right hand turning lanes will be provided at specific intersections and sidewalks will be constructed on both sides of the road. The road widening will be shifted to the west at Wylie's South and Wylie's North bridges where The Gore Road Tributary parallels the east side of the roadway resulting in extensions to the west for both Wylie's South and Wylie's North bridges.

Control of Flooding: There will be no impacts to the control of flooding.

Pollution: Standard erosion control measures (silt fence, cofferdam, temporary sheet piling) will be implemented for the duration of construction, and until the site is restored, in order to prevent construction generated sediment from entering the watercourse.

Dynamic Beaches: Not applicable

Erosion: There are no slope stability issues related to the works.

Conservation of Land: With erosion and sedimentation plans in effect, the potential for a Harmful, Alteration, Disruption or Destruction (HADD) of fish habitat will be mitigated and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO). This application is subject to the Ministry of Natural Resources (MNR) warmwater fisheries timing window (July 1 to March 31).

Plantings All disturbed areas will be restored and a net ecological gain will be achieved at this site

Policy Guidelines: This proposal complies with Section 4.3 - Infrastructure and Servicing - of the Authority's Valley and Stream Corridor Management Program.

CFN: 39419 - Application #: 425/07/BRAM Report Prepared by: Sharon Lingertat, extension 5717 For information contact: Sharon Lingertat, extension 5717 Date: June 29, 2010

141 EX10.46 REGIONAL MUNICIPALITY OF PEEL To construct, reconstruct, erect or place a building or structure, site grade, temporarily or permanently place, dump or remove any material originating on the site or elsewhere and alter a watercourse along The Gore Road, just north of Castlemore Road, in the City of Brampton, Humber River Watershed, as located on property owned by the Regional Municipality of Peel. The purpose is to widen The Gore Road from the intersection at Castlemore Road to just north of Castlemore Road. A storm sewer system will be constructed as part of the road improvements and the existing Castlemore bridge located along The Gore Road will be extended on either side. The warmwater fisheries timing window will be applied to this project and a Letter of Advice written by TRCA on behalf of Fisheries and Oceans Canada (DFO).

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposal consists of 2 separate applications (CFN 39419 and 43964) for road improvements along The Gore Road from north of Cottrelle Boulevard to north of Castlemore Road. Both of these applications will proceed to the July 9, 2010 Executive Committee Meeting for approval.

This proposal (CFN 43964) is for The Gore Road widening from Castlemore Road to approximately 350 metres north. The Gore Road will be widened from an existing 2-lane rural roadway to a 4-lane urban section with a central raised median to separate north and southbound traffic. Left and right hand turning lanes will be provided at specific intersections and sidewalks will be constructed on both sides of the road. The widening will be shifted equally on both sides at the bridge structure located north of Castlemore Road.

142 Control of Flooding: There will be no impacts to the control of flooding.

Pollution: Standard erosion control measures (silt fence, cofferdam, temporary sheet piling) will be implemented for the duration of construction, and until the site is restored, in order to prevent construction generated sediment from entering the watercourse.

Dynamic Beaches: Not applicable

Erosion: There are no slope stability issues related to the works.

Conservation of Land: With erosion and sedimentation plans in effect, the potential for a Harmful, Alteration, Disruption or Destruction (HADD) of fish habitat will be mitigated and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO). This application is subject to the Ministry of Natural Resources (MNR) warmwater fisheries timing window (July 1 to March 31).

Plantings All disturbed areas will be restored and a net ecological gain will be achieved at this site

Policy Guidelines: This proposal complies with Section 4.3 - Infrastructure and Servicing - of the Authority's Valley and Stream Corridor Management Program.

CFN: 43964 - Application #: 0330/10/BRAM Report Prepared by: Sharon Lingertat, extension 5717 For information contact: Sharon Lingertat, extension 5717 Date: June 29, 2010

CITY OF MISSISSAUGA

EX10.47 REGIONAL MUNICIPALITY OF PEEL To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere approximately 200 m East of Ponytrail Drive on Burnhamthorpe Road in the City of Mississauga, Etobicoke Creek Watershed as located on the property owned by Regional Municipality of Peel. The purpose is to The Region of Peel is proposing the replacement of an existing 150 mm watermain on Burnhamthorpe Road East with a new 300 mm watermain. The warmwater fisheries timing window will be applied to this project and a Letter of Advice will be written by TRCA on behalf of Fisheries and Oceans Canada (DFO).

143 The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The Region of Peel is proposing the removal of a 150 mm diameter watermain which will be replaced with a 300 mm diameter watermain on Burnhamthorpe Road East, approximately 200 m east of Ponytrail Drive. The watermain will be installed by methods of open cut and trenchless tunnelling. All construction access and staging areas will be restricted to the road right-of-way.

Control of Flooding: There will be no impacts to the control of flooding.

Pollution: Standard erosion and sediment control measures (Heavy-Duty Silt Fence, Catch Basin Covers) will be implemented prior to construction and maintained for the duration of construction, and until the site is stabilized and restored, in order to prevent construction generated sediments from entering Etobicoke Creek or municipal drains. Erosion and sediment control measures have been provided in accordance with the TRCA Erosion and Sediment Control Guideline for Urban Construction.

Dynamic Beaches: Not applicable

Erosion: There are no geotechnical/slope stability issues associated with the proposal.

144 Conservation of Land: With erosion and sedimentation plans in effect, the potential for a Harmful, Alteration, Disruption or Destruction (HADD) of fish habitat will be mitigated and a Letter of Advice will be written by TRCA staff on behalf of Fisheries and Oceans Canada (DFO). This application is subject to the Ministry of Natural Resources (MNR) warmwater fisheries timing window of July 1 to March 31.

Plantings There are no tree removals associated with the proposed work. All disturbed areas will be restored with native/non-invasive species following construction.

Policy Guidelines: This proposal complies with Section 4.3, Infrastructure and Servicing, of the TRCA's Valley and Stream Corridor Management Program.

CFN: 44008 - Application #: 0358/10/MISS Report Prepared by: Ben Krul, extension 5769 For information contact: Ben Krul, extension 5769 Date: June 29, 2010

CITY OF TORONTO [ETOBICOKE YORK COMMUNITY COUNCIL AREA]

EX10.48 BROADWAY HOMES To construct, reconstruct, erect or place a building or structure, change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 28, Plan 5773, (53 Edenbrook Hill), in the City of Toronto (Etobicoke York Community Council Area), Etobicoke Creek Watershed as located on the property owned by Broadway Homes. The purpose is to construct a new two-storey single family detached dwelling with integral garage and indoor pool at 53 Edenbrook Hill in the City of Toronto (Etobicoke York Community Council Area). The existing dwelling is to be demolished.

145 The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to develop within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a new two-storey single family detached dwelling with integral garage, integral indoor pool and pool house at 53 Edenbrook Hill. The existing dwelling is to be demolished. The subject site is located west of Royal York Road and south of Eglinton Avenue West in the City of Toronto (Etobicoke York Community Council Area).

Control of Flooding: The site is not located within a regional storm flood plain and the proposal will have no impact on the storage and/or conveyance of floodwaters.

Pollution: Appropriate erosion and sediment controls will be installed and maintained throughout all phases of construction.

Dynamic Beaches: Not applicable.

Erosion: A geotechnical brief has been reviewed and approved by TRCA geotechnical engineering staff. TRCA staff are satisfied that there will be no geotechnical/slope stability issues associated with the completed works.

Conservation of Land: The proposed works are located no further than the existing limits of development and are consistent with existing development along this reach of the ravine. There are no other significant natural features on, or adjacent to, the site that would be negatively impacted by the project.

Plantings Native plantings will be provided as per City of Toronto Urban Forestry Ravine Protection Services Guidelines and recommendations pertaining to tree protection and maintenance during construction will be implemented.

Policy Guidelines: This proposal is consistent with Section 4.2.2.(D) - Development Guidelines for Replacement Structures within Non-Established/Highly Urbanized Areas of the TRCA's Valley and Stream Corridor Management Program.

146 CFN: 44192 - Application #: 0487/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Steve Heuchert, extension 5311 Date: June 29, 2010

EX10.49 CITY OF TORONTO To construct, reconstruct, erect or place a building or structure and site grade at 2125 Lawrence Avenue West (Weston Lions Park), in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed as located on the property owned by The City of Toronto. The purpose is to permit the replacement of a natural turf soccer field with an artificial turf soccer field and installation of a sub-grade drainage system and new outfall, within Weston Lions Park, south of Lawrence Avenue West, west of Weston Road, in the City of Toronto.

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposal involves the replacement of a natural turf soccer field with an artificial turf soccer field and installation of a sub-grade drainage system and new outfall, within Weston Lions Park, south of Lawrence Avenue West, west of Weston Road, within a Regulated area of the Humber River Watershed, in the City of Toronto. The work will include removal of the existing natural turf field, installation of a crushed stone base with 300 millimetre perforated pipe, and replacement lighting and goal posts. A 300 millimetre pipe will connect the field drainage system to an outfall located adjacent to the Humber River.

147 Control of Flooding: The project is located within the Regional Storm Flood Plain. No major grade changes are proposed, and no significant new above ground structures are proposed. Therefore, the project is not anticipated to affect the conveyance or storage of flood waters.

Pollution: Standard erosion and sediment control measures (sediment control fence) will be implemented prior to construction, maintained for the duration, and removed only after the site is stabilized and restored. Erosion and sediment control measures have been provided in accordance with the TRCA Erosion and Sediment Control Guidelines for Urban Construction.

Dynamic Beaches: Not applicable

Erosion: The proposal will have no additional impacts on slope stability or erosion.

Conservation of Land: The work area will be isolated with sediment and erosion control fencing. No vegetation removals are proposed. A Letter of Advice will be provided on behalf of DFO, and the warm water timing window will be applied.

Plantings No plantings are proposed.

Policy Guidelines: This proposal is consistent with Section 4.3 - Infrastructure and Servicing - of the Toronto and Region Conservation Authority's Valley and Stream Corridor Management Program.

CFN: 44223 - Application #: 0512/10/TOR Report Prepared by: Brian Storozinski, extension 5744 For information contact: Brian Storozinski, extension 5744 Date: June 29, 2010

EX10.50 16 DANIELS STREET To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units on Lot 6, Plan 2149, (16 Daniels Street), in the City of Toronto (Etobicoke York Community Council Area), Mimico Creek Watershed. The purpose is to construct a partial second storey addition, a side entrance way, and to reconstruct the existing rear wall and covered front porch to the existing storey single family detached dwelling at 16 Daniels Street in the City of Toronto (Etobicoke York Community Council Area). The existing rear frame addition is to be removed.

148 The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to develop within a TRCA Regulated Area of the Mimico Creek Watershed in order to facilitate the construction of a partial second storey addition, a side entrance way, and to reconstruct the existing rear wall and covered front porch to the existing storey single family detached dwelling at 16 Daniels Street. The subject site is located east of Royal York Road and north of The Queensway in the City of Toronto (Etobicoke York Community Council Area).

Control of Flooding: The site is not located within a regional storm flood plain and the proposal will have no impact on the storage and/or conveyance of floodwaters.

Pollution: Appropriate erosion and sediment controls will be installed and maintained throughout all phases of construction.

Dynamic Beaches: Not applicable.

Erosion: There are no slope stability/geotechnical concerns associated with this application.

149 Conservation of Land: The proposed works are located no further than the existing limits of development. There are no other significant natural features on, or adjacent to, the site that would be negatively impacted by the project.

Plantings Native plantings will be provided as per City of Toronto Urban Forestry Ravine Protection Services Guidelines and recommendations pertaining to tree protection and maintenance during construction will be implemented.

Policy Guidelines: This proposal is consistent with Section 4.2.2.(B) and (D) - Development Guidelines for Minor Additions and Replacement Structures within Non-Established/Highly Urbanized Areas of the TRCA's Valley and Stream Corridor Management Program.

CFN: 44245 - Application #: 0529/10/TOR Report Prepared by: Nicole Moxley, extension 5284 For information contact: Steve Heuchert, extension 5311 Date: June 29, 2010

CITY OF TORONTO [NORTH YORK COMMUNITY COUNCIL AREA]

EX10.51 CITY OF TORONTO To construct, reconstruct, erect or place a building or structure and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere, north of Steeles Avenue, east of Kipling Avenue (2955 Kipling Avenue), in the City of Toronto (North York Community Council Area), Humber River Watershed as located on the property owned by City of Toronto. The purpose is to permit the retrofit of an existing leachate collection system involving excavation around the perimeter of the closed landfill to install pipe and maintenance holes, and a connection to the existing sanitary sewer system.

150 The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposal involves the retrofit of an existing leachate collection system including over two kilometers of 300 millimeter pipe around the closed landfill, 100 metres of 400 millimeter pipe to connect to the sanitary sewer, and 16 precast concrete manholes, north of Steeles Avenue, east of Kipling Avenue, within a Regulated area of the Humber River Watershed, in the City of Toronto. The work will consist of excavation around the perimeter of the landfill site to lay the perforated collection pipe, installation of maintenance holes, and a connection to the existing sanitary sewer. The collection pipe will be connected to the sanitary sewer system to direct the leachate away from the site.

It is our understanding that the City of Toronto is obtaining the required approvals from the Ontario Ministry of the Environment (MOE) for the leachate collection system. TRCA efforts have been focused on the protection of the adjacent natural features during the construction process, and any hydrogeological and geotechnical issues related to the landfill will be addressed through the MOE approvals process.

Control of Flooding: The work is not located within the Regional Storm Flood Plain. Therefore no impacts to the conveyance or storage of flood waters is anticipated.

Pollution: Standard erosion and sediment control measures (sediment and erosion control fencing) will be implemented prior to construction, maintained for the duration, and removed only after the site is stabilized and restored. Erosion and sediment control measures have been provided in accordance with the TRCA Erosion and Sediment Control Guidelines for Urban Construction.

Dynamic Beaches: Not applicable

Erosion: No slope stability or erosion concerns were identified.

Conservation of Land: The work area will be isolated from the creek and adjacent natural areas with sediment and erosion control fencing. No vegetation removals are proposed, and existing vegetation will be protected in accordance with City of Toronto Urban Forestry guidelines. There will be no in-water works associated with the project. The leachate collection system is anticipated to increase the transport of leachate offsite for treatment, resulting in a positive impact to the surrounding vegetation and watercourse.

151 Plantings No plantings are proposed.

Policy Guidelines: This proposal is consistent with Section 4.3 - Infrastructure and Servicing - of the Toronto and Region Conservation Authority's Valley and Stream Corridor Management Program.

CFN: 43594 - Application #: 0049/10/TOR Report Prepared by: Brian Storozinski, extension 5744 For information contact: Brian Storozinski, extension 5744 Date: June 29, 2010

CITY OF TORONTO [SCARBOROUGH COMMUNITY COUNCIL AREA]

EX10.52 CITY OF TORONTO To interfere with a wetland and alter a watercourse on , (East Highland Creek- Valley 4/4A), in a regulated area in the City of Toronto (Scarborough Community Council Area), Highland Creek Watershed as located on the property owned by City of Toronto. The purpose is to implement channel restoration works to the East Highland Creek within Valley Segment 4/4A in order to protect the infrastructure located within the valley system from continued erosion and stabilize the channel. The proposal is subject to the warmwater fisheries timing window.

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

152 Proposal: The proposal involves the implementation for the long-term objectives of the channel restoration works to alter East Highland Creek within Valley Segment 4/4A. Highland Creek was identified as highly impacted channel system to which retrofit stormwater management controls would not be sufficient on their own to stabilize the channel. The channel restoration will protect sanitary sewer crossing and manholes within the East Highland Creek valley; create a positive net gain by creating a more stable fish habitat for spawning activities and development of benthic invertebrate communities; protect valley slopes and private property located along the adjacent table lands; and planform configurations and channel dimensions that minimize maintenance requirements and provide long-term stability. The proposed works were developed from the recommendations of the City of Toronto Wet Weather Flow Management Master Plan (WWFMMP), adopted by the City Council in 1995; the WWFMMP Implementation was adopted by the City Council in 2003.

Control of Flooding: The project is located within the watercourse and flood plain. The channel restoration works will alter Valley Segment 4/4A by providing an energy dissapation pool downstream of Markham Road Bridge. The reconstruction of the armour walls will incorporate bioengineering to protect backfill to help slow velocity on the overbank areas. There will be no impacts to the control of flooding from this project.

Pollution: Standard erosion and sediment control measures (sediment control fencing) will be implemented prior to construction, maintained for the duration and removed only after the site is stabilized and restored. Erosion and sediment control measures have been provided in accordance with TRCA Erosion and Sediment Control Guidelines for Urban Construction.

Dynamic Beaches: Not applicable

Erosion: The proposal will stabilize the slopes and eliminate the majority of erosive forces caused by storm runoff. The proposal will have no additional impacts on slope stability or erosion.

Conservation of Land: As there will be in-water works, there is the potential for Harmful, Alteration, Disruption or Destruction (HADD) to fish habitat. The Department of Fisheries and Oceans Canada (DFO) will provide approval under Section 35(1) of the Fisheries Act for the in-water works. It is noted that the proposed channel restoration will provide a positive net gain of creating more stable fish habitat for spawning activities. This proposal is subject to the warmwater fisheries timing window (July 1 to March 31).

Plantings Details for compensation will be developed in partnership with the City of Toronto's Urban Forestry Division, in consultation with TRCA and DFO staff.

153 Policy Guidelines: This proposal is consistent with Section 4.3 - Infrastructure and Servicing - of the Toronto and Region Conservation Authority's Valley and Stream Corridor Management Program.

CFN: 41145 - Application #: 593/08/TOR Report Prepared by: Margaret Pak, extension 5714 For information contact: Margaret Pak, extension 5714 Date: June 29, 2010

CITY OF VAUGHAN

EX10.53 AGC INCORPORATED To site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on Part Lot 13, 14, Concession 10, (8934 Huntington Road), in the City of Vaughan, Humber River Watershed as located on the property owned by AGC Incorporated. The purpose is to undertake restoration works, including the removal of fill, three corrugated steel pipes (CSPs) and a wooden bridge, within a Regulated Area of the Humber River Watershed at 8934 Huntington Road in the City of Vaughan. The fill was originally placed and the culverts/wooden bridge installed without the approval of the TRCA.

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

154 Proposal: The purpose is to undertake restoration works, including the removal of fill, three corrugated steel pipes (CSPs) and a wooden bridge, within a Regulated Area of the Humber River Watershed at 8934 Huntington Road in the City of Vaughan.

The fill was originally placed and the watercourse crossings installed without the approval of the TRCA. TRCA Enforcement staff became aware of the works in November 2007 and issued a violation notice to the landowner on December 3, 2007 (File No. V2369). The works included the placement of more than 2,400 square metres (25,833 square feet) of fill on the southern valley slope and the installation of two watercourse crossings. One crossing consisted of two CSPs with gravel embankments along West Rainbow Creek and the other crossing consisted of one CSP with gravel embankments along a swale adjoining West Rainbow Creek. Rip-rap had also been placed both upstream and downstream of the larger watercourse crossing. No erosion or sediment controls were evident on the site.

Sediment and erosion control measures were installed shortly after the landowner was first contacted by TRCA staff. These sediment and erosion control measures have not been fully maintained, which has caused some localized erosion and sediment deposition. The embankments of the larger crossing of West Rainbow Creek have also washed out causing further material deposition in the watercourse channel. In an apparent effort to minimize further erosion, the landowner placed additional rip-rap and woody material against the embankments without the approval of the TRCA. A wooden bridge has also been installed over the two CSPs to facilitate foot traffic over the watercourse.

TRCA staff has now obtained and reviewed plans to facilitate the removal of the fill, the three CSPs and the wooden bridge. The plans also include the removal of sediment, rip-rap and woody debris from within the watercourse and along its banks. The site will be stabilized with native trees, shrubs and seed. TRCA staff are supportive of the works as proposed.

Fee: As the fill placement, CSP installation and wooden bridge construction were conducted without a permit from the TRCA, an additional administrative fee was charged on this application.

Control of Flooding: The proposal involves the removal of approximately 2,400 square metres (25,833 square feet) of fill from the flood plain in order to restore the site to its natural contours. The removal of fill will ameliorate any potential flood plain conveyance or storage concerns that would have resulted had the fill been retained in its current position.

Pollution: Sediment and erosion control measures were installed in 2007 shortly after the violation was noted by TRCA staff. However, the sediment and erosion control measures on-site have not been maintained and there has been additional sediment releases to the natural environment.

155 The landowner will install and maintain additional sediment and erosion control measures throughout the restoration and stabilization works to prevent sediment from entering the adjacent natural features, including the watercourse. The sediment deposition in the watercourse and along its banks will be removed. An environmental monitor will complete regular inspections of the work area during the restoration works to ensure the activities comply with the environmental provisions outlined in the permit and the supporting plans. The environmental monitor will also provide advice on the environmental management and construction methods at the site and will submit regular reports to the TRCA.

Dynamic Beaches: Not applicable.

Erosion: The restoration of the site to its natural slope conditions and the stabilization of all disturbed areas will eliminate further erosion issues on the property. TRCA staff are satisfied that there will be no geotechnical/slope stability issues associated with the restoration works as ultimately proposed.

Conservation of Land: The restoration of the slope and watercourse to their natural state is intended to promote the conservation of land.

Plantings A planting plan has been prepared to the satisfaction of TRCA staff. The landowner intends to restore the valley corridor with native plant material and a seed mix. A greater area is proposed to be naturalized than was impacted through the unauthorized works. These enhancement plantings are intended to improve the overall habitat quality along this reach of West Rainbow Creek.

Policy Guidelines: The proposal is consistent with Section 3.2 - Policies and Procedures for Establishing Corridor Boundaries and Alterations - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44204 - Application #: 0495/10/VAUG Report Prepared by: Coreena Smith, extension 5269 For information contact: Coreena Smith, extension 5269 Date: June 29, 2010

156 EX10.54 DOCTOR'S HOUSE DINING CORPORATION To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 41 -43, Plan 9, Part Lot 44, Plan 9, (21 Nashville Road), in the City of Vaughan, Humber River Watershed as located on the property owned by Doctor's House Dining Corporation. The purpose is to construct a 3-storey Inn with an underground parking structure, as an expansion to the existing Doctors House Dining facility, as well as to undertake grading, site alteration and landscaping works that will restore a portion of the existing valley area..

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct a 3-storey Inn with an underground parking garage, as an expansion to the existing Doctors House Dining facility, as well as to undertake grading, site alteration and landscaping works that will restore a portion of the existing valley area. The proposed works will effectively allow the outer limit of the site, along the valley, to be restored to a more natural state.

As part of the associated rezoning and site plan applications an appropriate buffer was applied, which is to be placed into public ownership to ensure its continued long-term protection. The proposal also includes restoration along the edge of the subject site, adjacent to the valley system, wherein the existing surface parking lot will be partially removed and the area replanted.

157 As part of the restoration works to be conducted, an existing storm sewer outfall will be upgraded. TRCA water resources engineering staff are satisfied that the proposed outfall has been properly designed and located.

TRCA ecology staff are satisfied that the proposed landscape restoration plan around the valley system and in the buffer area will result in a net ecological benefit for the subject property over existing conditions.

Control of Flooding: The site is not located within a regional storm floodplain and the proposal will have no impact on the storage and/or conveyance of floodwaters.

Pollution: Appropriate erosion and sediment controls will be installed and maintained throughout all phases of construction.

Dynamic Beaches: Not applicable

Erosion: A Geotechnical Slope Stability report was submitted and reviewed by TRCA geotechnical staff and it was determined there were no geotechnical issues associated with the proposed development. The proposal will be constructed in accordance with the recommendations of the report.

Conservation of Land: No significant vegetation will be removed and the proposal includes replacing and restoring a portion of the parking lot with a vegetated buffer adjacent to the valley system.

Plantings All disturbed areas will be restored with native/ non-evasive species following construction.

Policy Guidelines: This proposal is consistent with Section 4.2.2- Development and Redevelopment/Intensification Within Non-Established Communities/Highly Urbanized Areas and Section 4.3- Infrastructure and Servicing, of TRCA's Valley and Stream Corridor Management Program.

CFN: 44175 - Application #: 0469/10/VAUG Report Prepared by: Bill Kiru, extension 5306 For information contact: Bill Kiru, extension 5306 Date: June 29, 2010

158 EX10.55 89 CLARENCE STREET To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on , (89 Clarence Street), in the City of Vaughan, Humber River Watershed. The purpose is to construct a replacement home and new inground swimming pool within a Regulated Area of the Humber River watershed at 89 Clarence Street in the City of Vaughan.

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct a replacement home and new inground swimming pool within a Regulated Area of the Humber River watershed. The subject property is located within the Woodbridge Special Policy Area (SPA) and is entirely within the Regional Storm Flood Plain but outside of the Hydraulic Floodway. In addition, based upon a topographical survey prepared by Ertl Surveyors, dated April 16, 2010, the subject property is located above the 350 year event flood elevation of 142.49 metres above sea level, which is consistent with development requirement policies within the Woodbridge SPA. The subject property is generally flat and is also devoid of any significant vegetation.

Control of Flooding: The subject property is located within the Regional Storm Flood Plain. TRCA water resources staff are satisfied that the proposed works will have a minimal affect on the storage and conveyance of flood waters.

159 Pollution: Sediment control fencing will be erected and maintained to prevent the transport of sediment into the adjacent property and watercourse.

Dynamic Beaches: Not applicable.

Erosion: There are no geotechnical issues associated with this application.

Conservation of Land: As the watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that may be negatively impacted by the project.

Plantings All disturbed areas will be restored to the existing sodded condition and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.2.1 B) - Development & Redevelopment Within Establish Designated Two Zone Areas and Special Policy Areas - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44234 - Application #: 0507/10/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 24, 2010

EX10.56 30 MODESTO GARDENS To construct, reconstruct, erect or place a building or structure on Lot 14, Plan 65M-2604, (30 Modesto Gardens), in the City of Vaughan, Humber River Watershed. The purpose is to construct a raised concrete deck within a Regulated Area of the Humber River watershed at 30 Modesto Gardens in the City of Vaughan.

160 The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct a raised concrete deck within a Regulated Area of the Humber River watershed. The subject property is located along the edge of the well vegetated valley wall of a tributary of the Main Humber River. As part of the Draft Plan of Subdivision for the subject property (19T-87107 - Constellation Developments), a low retaining wall was constructed at the rear property line which has a maximum height of 0.9 metres. Based upon a Slope Inspection Letter, prepared by SPL Consultants Limited, dated June 9, 2010, received by the TRCA June 17, 2010, the retaining wall can be considered the long-term-stable top-of-slope for the gentle 4H : 1V slope which forms the valley wall.

Based upon a site visit conducted by TRCA staff on May 21, 2010, the proposed works are located within a generally flat, already disturbed sodded area devoid of significant vegetation. The deck will be setback 5 metres from the long-term-stable-of-slope.

Control of Flooding: The proposed works are not located within the Regional Storm Flood Plain, there will be no impacts on the storage or conveyance of flood waters.

Pollution: Sediment control fencing will be erected and maintained for the duration of construction to prevent the transport of sediment into the adjacent valley system.

Dynamic Beaches: Not applicable.

161 Erosion: TRCA Geotechnical staff are satisfied that the proposed works are adequately setback from the stable-top-of-slope and will not impact the stability of the slope feature.

Conservation of Land: As a watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that may be negatively impacted by the project.

Plantings All disturbed areas will be restored to the existing sodded condition and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.2.2 E) - Property Improvements and Ancillary Structures - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44121 - Application #: 0428/10/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 18, 2010

EX10.57 39 GAMBLE STREET To construct, reconstruct, erect or place a building or structure, site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 20, Plan M-1106, (39 Gamble Street), in the City of Vaughan, Humber River Watershed. The purpose is to construct a replacement dwelling within a Regulated Area of the Humber River watershed at 39 Gamble Street in the City of Vaughan.

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

162 The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct a replacement home within the Humber River watershed. The subject property is located within an urbanized and flat portion of the valley floor of the Main Humber River valley corridor. The property is located well over 200 metres away from the Regional Storm Flood Plain and is approximately 10 metres from the toe-of-slope of a very gentle (approximately 4H : 1V) slope feature.

Control of Flooding: The proposed works are not located within the Regional Storm Flood Plain. There will be no impacts on the storage and conveyance of flood waters.

Pollution: There are no pollution related issues associated with this application.

Dynamic Beaches: Not applicable.

Erosion: There are no geotechnical issues associated with this application.

Conservation of Land: As a watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that maybe negatively impacted by the project.

Plantings All disturbed areas will be restored to the existing sodded condition and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.2 - Existing Development - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44282 - Application #: 0558/10/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 24, 2010

163 EX10.58 THORNHILL GOLF AND COUNTRY CLUB To site grade and temporarily or permanently place, dump or remove any material, originating on the site or elsewhere on Lot 31, Concession 1 W, (7994 Yonge Street), in the City of Vaughan, Don River Watershed as located on the property owned by Thornhill Golf and Country Club. The purpose is to construct a replacement stormwater management culvert and conduct erosion repair / slope restoration works within a Regulated Area of the Don River watershed at 7994 Yonge Street in the City of Vaughan.

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct a replacement stormwater management culvert and restore a portion of the valley wall within a Regulated Area of the Don River watershed. The subject property is traversed by the East Don River valley corridor. A portion of the valley wall located near two maintenance buildings experienced a slope failure due to the overtopping of a catchbasin, which is connected to an undersized stormwater management culvert. The valley wall has a 1H : 1V or slightly steeper configuration at this location.

The existing stormwater management culvert conveys overland flow and roof run-off from the maintenance buildings which is directed down the valley wall towards a drainage swale. The culvert and swale empty to the East Don River and has been in existence for many years. Because the current drainage system does not function as intended, the current erosion issues have occurred.

164 The proposal is to replace the failed culvert and catchbasin with sufficiently sized structures based upon engineering calculations and analysis in a report prepared by RJ Burnside & Associates Limited, dated December 2009, received by the TRCA December 23, 2009. The proposed works also include the re-grading, reinforcement and vegetative restoration of the slope face as well as the re-establishment of the drainage swale to the East Don River with improved sediment and erosion control measures over existing conditions. The slope reinforcement works include the installation of soil nails and restoration plantings while the improvements to the drainage swale include the installation of a plunge pool and the lining of the channel with river rock.

The proposed works will take place outside of the migratory birds and warm-water timing windows.

TRCA water resource, ecology and geotechnical staff are satisfied that the proposed works are sufficiently designed to handle anticipated flow amounts and rates and adequately restores the slope and drainage swale to an improved condition.

Control of Flooding: A portion of the works associated with the swale are located within the Regional Storm Flood Plain; however, TRCA water resources staff are satisfied there will be no impacts on the storage or conveyance of flood waters.

Pollution: Appropriate sediment control measures will be implemented including rock check dams and sediment control fencing.

Dynamic Beaches: Not applicable.

Erosion: TRCA geotechnical staff are satisfied that the proposed works will increase the stability of the valley wall.

Conservation of Land: With erosion and sedimentation plans in effect and adherence to the fisheries timing window, the potential for a harmful alteration, disruption or destruction (HADD) of fish habitat will be mitigated and a Letter of Advice will be written by TRCA staff on behalf of the Department of Fisheries and Oceans (DFO).

Plantings All disturbed areas will be restored with native, non-invasive plantings and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.2.2 D) - Replacement Structures and 4.3 - Infrastructure and Servicing - of the Authority's Valley and Stream Corridor Management Program.

165 CFN: 43502 - Application #: 0003/10/VAUG Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 22, 2010

TOWN OF AJAX

EX10.59 TOWN OF AJAX To construct, reconstruct, erect or place a building or structure at Greenwood Conservation Area (Taunton and Westney), in the Town of Ajax, Duffins Creek Watershed as located on the property owned by Town of Ajax. The purpose is to permit the reconstruction of the existing pedestrian bridge and installation of a new asphalt trail and staircase within the Duffins Creek valley corridor in Greenwood Conservation Area, north of Taunton Road, east of Westney Road, in the Town of Ajax.

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The proposal involves the reconstruction of the existing pedestrian bridge and installation of a new asphalt trail and staircase within the Duffins Creek valley corridor in Greenwood Conservation Area, north of Taunton Road, east of Westney Road, within a Regulated area of the Duffins Creek Watershed, in the Town of Ajax. The bridge work will include removal of the existing bridge structure and the installation of a new bridge and abutments. The new bridge will be larger than the current structure, increasing in length from approximately 12 metres to approximately 28 metres. The trail work will include excavation of the slope to accommodate a level trail profile, with a retaining wall to stabilize the slope and support the staircase to allow for safe pedestrian access up and down the slope. 166 The bridge and trail project is associated with a restoration project headed by TRCA Restoration Services. TRCA Restoration Services will be restoring terrestrial and aquatic habitat along the creek bank and repairing damage due to stream erosion. TRCA Restoration Services staff will undertake the initial excavation of the slope to accommodate the passage of heavy equipment down the slope, and will install the temporary bridge west of the pedestrian bridge that will be used by the Town of Ajax to complete their rehabilitation work. As well, the proposed trail will be placed along the same access route created by TRCA staff once the restoration work is completed and equipment is removed from the valley.

Control of Flooding: The project is located within the Regional Storm Flood Plain. The new bridge structure provides greater clearance of the watercourse, positively impacting the conveyance and storage of flood waters, and is located in a remote area where flooding resulting from ice-jamming or debris can be easily contained within the valley corridor. Minimal impacts to grades are also proposed, with the trail work consisting of the removal of fill to accommodate the trail. Therefore, the work will not negatively affect the conveyance or storage of flood waters.

Pollution: Standard erosion and sediment control measures (sediment and erosion control fencing) will be implemented prior to construction, maintained for the duration, and removed only after the site is stabilized and restored. Erosion and sediment control measures have been provided in accordance with the TRCA Erosion and Sediment Control Guidelines for Urban Construction.

Dynamic Beaches: Not applicable

Erosion: The proposal will have no additional impacts on slope stability or erosion.

Conservation of Land: The work area will be isolated from the creek with sediment and erosion control fencing. No vegetation removals are proposed. There will be no in-water works associated with the project. A Letter of Advice will be provided, and the cold-water timing window will be applied. The trail construction and restoration work will control access to the valley and will inhibit the pedestrian and cyclist access routes that currently traverse the existing vegetation causing damage and erosion.

Plantings The Town of Ajax is proposing the planting of 56 shrubs to assist in the naturalization of the disturbed areas and reduce slope erosion.

Policy Guidelines: This proposal is consistent with Section 4.3 - Infrastructure and Servicing - of the Toronto and Region Conservation Authority's Valley and Stream Corridor Management Program.

167 CFN: 43661 - Application #: 0098/10/AJAX Report Prepared by: Brian Storozinski, extension 5744 For information contact: Brian Storozinski, extension 5744 Date: June 29, 2010

TOWN OF CALEDON

EX10.60 74 JAMES STREET To construct, reconstruct, erect or place a building or structure on Lot 41, 42, Block 1, Plan BOL7, (74 James Street), in the Town of Caledon, Humber River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a 8.92 square metre (96 sq. ft.) addition and ancillary deck structure at the rear of an existing residential dwelling associated with a municipal building permit.

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

168 Proposal: The purpose of this application is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a 8.92 square metre (96 sq. ft.) addition and new ancillary deck structure at the rear of an existing residential dwelling located at 74 James Street East, in the Town of Caledon. The subject property is located within the Regional Floodplain in the Bolton Special Policy Area (SPA). The proposed addition will be floodproofed to the Regional Floodplain elevation in accordance with Bolton SPA criteria. In addition, the ancillary deck structure and addition have been designed to withstand water flow velocities and depths anticipated during a Regional Storm event. As such, TRCA staff are satisfied that the proposed addition is appropriately flood protected in accordance with TRCA guidelines. In addition, there are no ecology or geotechnical concerns anticipated with this proposal.

Control of Flooding: The proposed works are located within the Regional Storm Floodplain. The proposed development will be floodproofed in accordance with the Bolton SPA and TRCA guidelines. As well, the proposed works will not have any significant impacts to the storage and/or conveyance of flood waters.

Pollution: Appropriate erosion and sediment controls (i.e., silt fence) have been proposed with this application, and will be maintained throughout all phases of construction.

Dynamic Beaches: Not applicable.

Erosion: There are no geotechnical and/or slope stability concerns anticipated with this project.

Conservation of Land: The subject property is void of any significant vegetation. As such, no significant vegetation will be removed as a result of this project. There are no fisheries related concerns associated with this project.

Plantings As no vegetation is to be removed by the proposed works, plantings have not been required at this time.

Policy Guidelines: This proposal is in conformity with Section 4.2.1. (B) - Development Guidelines for Development/Redevelopment within Designated Two Zone Areas or Special Policy Areas - of the Authority's Valley and Stream Corridor Management Plan (VSCMP).

CFN: 44315 - Application #: 0591/10/CAL Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: June 29, 2010

169 EX10.61 13879 HEART LAKE ROAD To construct, reconstruct, erect or place a building or structure on Lot 27, Concession 3, (13879 Heart Lake Road), in the Town of Caledon, Humber River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a 7.8 square metre (84 sq. ft.) change room and an 7.8 square metre (84 sq. ft.) pool equipment room at the rear of an existing residential dwelling associated with a municipal building permit.

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to undertake works within a TRCA Regulated Area of the Humber River Watershed in order to facilitate the construction of a 7.8 square metre (84 sq. ft.) change room and an 7.8 square metre (84 sq. ft.) pool equipment room at the rear of an existing residential dwelling, adjacent to an existing in-ground swimming pool located at 13879 Heart Lake Road, in the Town of Caledon. The works are located adjacent to a Provincially Significant Wetland (PSW) and are sufficiently setback from the wetland feature. No hydrologic impacts to the wetland are anticipated as a result of the proposed works. In addition, there are no flooding, geotechnical or ecology related concerns anticipated with this proposal. Although there are no ecology related concerns with this proposal, a planting enhancement plan will be provided with this application.

Control of Flooding: The proposed works are located outside of the Regional Floodplain. As such, no impacts to the storage and/or conveyance of flood waters are anticipated.

170 Pollution: Appropriate erosion and sediment controls (silt fence) have been proposed with this application, and will be maintained throughout all phases of construction.

Dynamic Beaches: Not applicable.

Erosion: There are no geotechnical and/or slope stability concerns anticipated with this project.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings All proposed plantings are in accordance with TRCA's guidelines.

Policy Guidelines: This proposal is in conformity with Section 4.2.2 (E) – Property Improvements and Ancillary Structures – of the Authority’s Valley and Stream Corridor Management Program (VSCMP).

CFN: 44273 - Application #: 0553/10/CAL Report Prepared by: Jason Wagler, extension 5743 For information contact: Quentin Hanchard, extension 5324 Date: June 29, 2010

TOWN OF MARKHAM

EX10.62 25 RITTER CRESCENT To site grade on Lot 98, Plan M-1971, (25 Ritter Crescent), in the Town of Markham, Rouge River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed in order to facilitate the construction of an in-ground pool and associated landscaping.

171 The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed in order to facilitate the construction of an in-ground pool and associated landscaping. The subject lands are located within an approved residential subdivision in the Town of Markham and are located adjacent to top of bank. The subject lands currently contain an unapproved retaining wall, which is to be removed as a component of this application, and the effected areas of the property will be re-graded to recreate a more natural slope. Based on a site inspection conducted by TRCA Staff, it appears that the proposed pool will be adequately setback from the top of bank. The area to which the application applies is currently manicured lawn, as such no significant vegetation will be removed as a result of construction.

Control of Flooding: The subject property is located outside of the Regional Storm Floodplain. As such, no impacts to the storage and/or conveyance of floodwaters are anticipated.

Pollution: Appropriate erosion and sediment controls will be installed and maintained on the subject property throughout all phases of construction.

Dynamic Beaches: Not applicable

Erosion: There are no geotechnical and/or slope stability concerns related to this application.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings Since no significant vegetation will be removed, additional plantings are not required.

Policy Guidelines: This proposal is consistent with Section 4.2.2 (E) - Property Improvements and Ancillary Structures - of the Authority's Valley and Stream Corridor Management Program (VSCMP).

CFN: 44303 - Application #: 0573/10/MARK Report Prepared by: Lisa Stern, extension 5370 For information contact: Quentin Hanchard, extension 5324 Date: June 29, 2010

172 EX10.63 66 SQUIRE BAKER'S LANE To construct, reconstruct, erect or place a building or structure at 66 Squire Baker's Lane, in the Town of Markham, Rouge River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed in order to facilitate the construction of a new dwelling.

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed in order to facilitate the construction of a new dwelling. The subject lands are located within an established residential subdivision in the town of Markham located adjacent to the top of bank. There is an existing dwelling on the subject lands to be demolished. Based on TRCA staff's review, it appears that the proposed dwelling is adequately setback from the top of bank and is consistent with setbacks seen in this reach of the valley corridor. The new dwelling will be consistent with the footprint of the existing dwelling as such no significant vegetation will be removed as a result of construction.

Control of Flooding: The subject property is located outside of the Regional Storm Floodplain. As such, no impacts to the storage and/or conveyance of floodwaters are anticipated.

Pollution: Appropriate erosion and sediment controls will be installed and maintained on the subject property throughout all phases of construction.

173 Dynamic Beaches: Not applicable

Erosion: There are no geotechnical and/or slope stability concerns related to this application.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings Since no significant vegetation will be removed, additional plantings are not required.

Policy Guidelines: This proposal is consistent with Section 4.2.2 (D) - Replacement Structures - of the Authority's Valley and Stream Corridor Management Program (VSCMP).

CFN: 44319 - Application #: 0585/10/MARK Report Prepared by: Lisa Stern, extension 5370 For information contact: Quentin Hanchard, extension 5324 Date: June 29, 2010

TOWN OF RICHMOND HILL

EX10.64 2 MARINUCCI COURT To construct, reconstruct, erect or place a building or structure on Lot 22, Plan 65M-3300, (2 Marinucci Court), in the Town of Richmond Hill, Don River Watershed. The purpose is to undertake works within a TRCA Regulated Area of the Don River Watershed in order to facilitate the construction of an in-ground pool and associated landscaping.

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

174 The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to undertake works within a TRCA Regulated Area of the Don River Watershed in order to facilitate the construction of an in-ground pool and associated landscaping. The subject lands are located in an approved residential subdivision in the Town of Richmond Hill located adjacent to top of bank. The subject lands contain an existing retaining wall along the rear property line which separates the subject lands from the valley to the rear which has not received appropriate permits from TRCA. As it is now beyond TRCA's statute of limitations, TRCA Staff are not seeking enforcement action on this wall. TRCA Staff have ensured that the proposed pool and landscaping will be appropriately setback from the top of bank and retaining wall as such, this application is not impacted by the existing retaining wall. The area to which this application applies is currently manicured lawn, as such no significant vegetation will be removed as a result of construction.

Control of Flooding: The subject property is located outside of the Regional Storm Floodplain. As such, no impacts to the storage and/or conveyance of floodwaters are anticipated.

Pollution: Appropriate erosion and sediment controls will be installed and maintained on the subject property throughout all phases of construction.

Dynamic Beaches: Not applicable

Erosion: The applicant has submitted a geotechnical report and such, TRCA Staff are satisfied that there are no geotechnical and/or slope stability concerns related to this application.

Conservation of Land: No significant vegetation will be removed as a result of construction.

Plantings Since no significant vegetation will be removed, additional plantings are not required.

Policy Guidelines: This proposal is consistent with Section 4.2.2 (E) - Property Improvements and Ancillary Structures - of the Authority's Valley and Stream Corridor Management Program (VSCMP).

CFN: 44199 - Application #: 0490/10/RH Report Prepared by: Lisa Stern, extension 5370 For information contact: Quentin Hanchard, extension 5324 Date: June 29, 2010

175 TOWNSHIP OF KING

EX10.65 156 NORMAN DRIVE To construct, reconstruct, erect or place a building or structure on Lot 24, Plan 573, (156 Norman Drive), in the Township of King, Humber River Watershed. The purpose is to construct a replacement retaining wall and replacement rear yard deck attached to an existing dwelling within a Regulated Area of the Humber River watershed at 156 Norman Drive in the Township of King.

The permit will be issued for the period of July 9, 2010 to July 8, 2012.

The documents and plans which form part of this permit will be listed in a separate report

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to construct a replacement retaining wall and replacement rear yard deck within a Regulated Area of the Humber River watershed. The subject property is partially located within the East Humber River valley corridor.

Based upon a site visit conducted by TRCA staff on June 7, 2010, the subject property contains a very shallow and mild slope. The proposed works are to reconstruct an existing approximate 3 foot (0.91 metre) high retaining wall and a construct a replacement deck which is slightly larger than the existing deck. TRCA geotechnical staff have no concerns with these proposed works due to the minor height of the wall and mild inclination of the slope feature. In addition, the proposed works are located within an already disturbed sodded area devoid of any significant vegetation.

176 Control of Flooding: The proposed works are not located within the Regional Storm Flood Plain. There will be no impacts on the storage and conveyance of flood waters.

Pollution: There are no pollution related issues associated with this application given the minor nature of the works and the existing sodded condition of the mild slope feature.

Dynamic Beaches: Not applicable.

Erosion: TRCA geotechnical staff are satisfied that the proposed works will not impact the stability of the slope feature.

Conservation of Land: As a watercourse will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that may be negatively impacted by the project.

Plantings All disturbed areas will be restored to the existing sodded condition and will not affect any significant natural features.

Policy Guidelines: The proposal is consistent with Section 4.2.2 D) - Replacement Structures - of the Authority's Valley and Stream Corridor Management Program.

CFN: 44300 - Application #: 0584/10/KING Report Prepared by: Anthony Sun, extension 5724 For information contact: Bill Kiru, extension 5306 Date: June 28, 2010

177