Due Diligence Report – Social Safeguards (Land Acquisition and Resettlement)

Project number: 42486-016 August 2016

IND: Urban Services Improvement Program – Water Supply Improvement in Alampur

Package Number: MPUSIP-4A

Prepared by the Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank.

This due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Land Acquisition and Resettlement Due

Diligence Report

Document stage: Draft for consultation Project Number: 42486 Loan and/or Grant Number(s): {LXXXX; GXXXX; TAXXXX} August, 2016

Madhya Pradesh Urban Services Improvement Program

Alampur Water Supply Scheme, District: Bhind

This due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

DDR (IR) ( Alampur, MP )

CURRENCY EQUIVALENTS (As of August 1, 2016)

Currency unit Rupee (INR) INR 1.00 = USD0.0148 USD 1.00 = INR 67.02

List of Abbreviations ADB - Asian Development Bank AP - affected person BPL - below poverty line DDR - Due diligence report DP - displaced person EA - executive agency GOI - Government of GOMP - Government of Madhya Pradesh GRC - grievance redress mechanism HFL - Highest flood level HHs - Households IA - implementing agency IR - involuntary resettlement IP - Indigenous people KM - Kilometer MLD - Million liter per day MPUDC - Madhya Pradesh Urban Development Company MPUSIP - Madhya Pradesh Urban Service Improvement Program NOC - No objection certificate OHT - overhead tank O&M - operation and maintenance PIU - project implementation unit PMC - program monitoring consultant PMU - program management unit PO - project officer PWD - public works department R&R - resettlement and rehabilitation RF - resettlement framework the right to fair compensation and transparency in land acquisition, RFCTLARR - rehabilitation and resettlement act, 2013 RP - resettlement plan RoW - right of way SO - safeguard officer SPS - safeguard policy statement UADD - Urban Administration and Development Directorate UDED - Urban Development and Environment Department ULBs - urban local bodies WRD - water resource department WTP - water treatment plant

Page | 2

DDR (IR) ( Alampur, MP )

CONTENTS

I. INTRODUCTION ...... 4 A. Background ...... 4 B. Scope of this Report ...... 4 II. POLICY FRAMEWORK, AND ENTITLEMENTS ...... 5 III. SUBPROJECT DESCRIPTION ...... 5 A. Existing system ...... 5 B. Proposed Water Supply ...... 6 IV. Field Work and Public Consultation ...... 6 A. Public Consultation ...... 6 V. LAND AVAILABILITY AND INVOLUNTARY RESETTLEMENT IMPACTS ...... 10 VI. CONCLUSIONS ...... 16 A. Summary and Conclusions ...... 16

LIST OF TABLES

Table 1: Summary of Consultation with Stakeholders...... 11 Table 2: Photograph of rising main, clear water rising main & distribution lines ...... 15 Table 3: Proposed sub-project components in Alampur Water Supply Subproject, and their involuntary resettlement impact status...... 17 Table 4: Budgetary Provision...... 20

LIST OF MAP Figure 1: Showing flow of Sindh River from Intake to downstream ...... 13 Figure 2: Google Map showing Transmission main from Intake well at Sindh River to WTP and to OHTs in Alampur ...... 21 Figure 3 : Location of Proposed Intake and WTP on Google Earth map ...... 22 Figure 4: Location of Proposed OHT on Google Earth map ...... 23 Figure 5: Proposed Transmission System for Alampur Water supply ...... 24 Figure 6: Proposed Distribution Network for Alampur Water Supply...... 25

ANNEXURE Annexure 1: Details of Land Ownership for Proposed Water Works Components...... 26 Annexure 2: Stakeholder Consultation Photograph and List of participants ...... 27 Annexure 3: Involuntary Resettlement Screening Checklists ...... 29 Annexure 4: Land Details...... 32 Annexure 5: Certificate of Chief Municipal officer regarding Land Ownership Status...... 34

Page | 3

DDR (IR) ( Alampur, MP )

I. INTRODUCTION A. Background

1. Government of Madhya Pradesh (GoMP) with a sector project loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency (IA) and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project. A project management unit (PMU) created under MPUDC is implementing MPUSIP.

2. MPUSIP’s physical components include (a) improvements to water in 64 project towns; and (b) sewage and storm water collection and treatment services proposed in two (2) identified towns (Khajuraho, and Rajnagar). The project also includes an institutional strengthening component and a project management and administrative support component.

3. MPUSIP will result in improved and sustainable urban services, improved institutional and financial capacity of urban local bodies (ULBs) to deliver sustainable urban services. The Project will also support the development and operationalization of Madhya Pradesh Urban Development Company (MPUDC). The proposed project will be implemented over 10 years (2016-2026).

B. Scope of this Report 4. This land acquisition and resettlement due diligence report is prepared for the proposed water supply subproject for Alampur Municipal Parishad, located in Bhind district, under MPUSIP. Proposed components of the Alampur water supply subproject include construction of water intake, water treatment plant, storage reservoir, transmission mains and distribution system. The proposed subproject will provide metered water supply for domestic, institutional and commercial users, including metered connections to each household in the town. All municipal wards of the town will be covered under the project. The total population of the town is 10686 in Alampur (population as per Census 2011) and the estimated population for which the subproject is designed for the year 2048 is 16203. All the municipal wards of the town are covered in the subproject.

5. A due diligence process was conducted to examine the land acquisition and resettlement issues in detail, in line with ADB SPS 2009. This report describes the findings and provides copies of relevant documents, maps, minutes of meetings and photographs. This land acquisition and resettlement due diligence report needs to be read along with the Resettlement Framework prepared for MPUSIP.

6. Upon project implementation, the social safeguards personnel at PMU (Project Officer – Social Safeguards and Gender), MPUDC will be required to undertake a review of this due diligence report, prepare a confirmation letter or report documenting any modifications for the subproject and submit to ADB; and receive a ‘no objection’ confirmation from ADB prior to start of construction in the subproject.

Page | 4

DDR (IR) ( Alampur, MP )

II. POLICY FRAMEWORK, AND ENTITLEMENTS 7. The Resettlement Framework (RF) prepared for MPUSIP sets out the objectives, principles, eligibility criteria and entitlements for APs, based on ADB SPS, 2009 and LARR 2013 as well as national and state laws for protection of street vendors. Until recently, all activities related to rehabilitation and resettlement in the State of MP had been based on the Madhya Pradesh Resettlement and Rehabilitation Policy, 2002 (MPRR) and National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007). GoMP adopted LARR 2013 on 3rd October, 2014 with some specifications for operationalizing its implementation in the state1. Details of policies are in the Resettlement Framework for MPUSIP.

III. SUBPROJECT DESCRIPTION 8. Project area: Alampur is located at 78.7854180 E and 26.0237530 N. It has an average elevation of 158 m above mean sea level (MSL). Alampur urban region has an areal extent of about 1211 Ha (12.11 sq.km). The town has been divided into 15 wards. Alampur is located in the northern part of MP; and some of its closest towns are Bhind and Lahar in the district. and Datia are at a distance of 93 and 63 kms respectively from Alampur. Bhind city is 83 km away from the town.

A. Existing system 9. Alampur town does not have an organized water supply system. Water supply in Alampur is primarily dependent on sub-surface water sources. Presently Nagar Parishad supplies drinking water by means of 10 tube wells. The daily water supply has been assessed as 0.75MLD for the town.

10. There are 85 hand pumps and 18 open wells which are also used by the residents. The average ground water table depth 65 meters. Only 70% of the population is covered by piped water supply. At present, water is supplied for 2 hours (1 hour in the morning and 1 hour in the evening) daily, at the rate of 50 LPCD through two OHSRs. The present water sources are 10 tube wells located in the town.

11. At present, there are 2 Over Head Tanks (OHTs) for storage with a total capacity of 345 KL and one sump having a capacity of 50 KL. These are located at Narsingh temple and Degree College. Water is supplied from the OHTs as well as direct pumping from bore wells without any storage. This results in uneven pressure across the network and most of the localities across the town have reported low pressure of water supply.

12. The entire town of Alampur is being supplied from ground water source and the water distribution system has a coverage of 70% of town area. At present the town has

1 These GOs issued separately in September 2014 (i) notifies administrative cost of land acquisition; (ii) appoints Divisional Commissioners as Commissioner for Rehabilitation & Resettlement within their respective jurisdictions; (iii) authorizes District Collectors for constituting an Expert Group separately in respect of each project, (iv) notifies the factor which the market value is to be multiplied in case of rural areas, (v) appoints Officer-in charge of Land Acquisition Section in the Office of the Collector as Administrator for Rehabilitation and Resettlement and (vi) limits agricultural land acquisition, as required by the RTFCLARR, 2013.

Page | 5

DDR (IR) ( Alampur, MP )

around 9 Km length of distribution system of AC pipes having 80 mm and 100 mm dia. The city presently has 1934 households with 1108 individual water connections.

B. Proposed Water Supply 13. The primary objectives of the proposed water supply subproject include: (i) service improvements to achieve safe and sustainable water services both in terms of services to residents and cost recovery (ii) Conservation of precious water resources. The project envisages providing 100 percent coverage of population with continuous, pressurized and safe drinking water services and achieving increased cost recovery progressively, by expanding the coverage and increasing operating efficiency.

Proposed components:

14. Proposed subproject components include: (i) Weir across the Sindh River to store the water required for Alampur for 8 months; (ii) intake well to draw raw water from Sindh River at bridge near Ratangarh Mata Temple for the ultimate year water demand; (iii) WTP of 1.43 MLD capacity for ultimate water demand of the project area has been proposed around 600 m from bridge on Sindh River; (iv) Clear Water sump 50 cum capacity at WTP; (v) Proposed OHT of 220 KL capacity near Tehsil office; (vi) laying of rising main of length 19.37 km; (vii) laying of distribution network of length 30 Km. IV. Field Work and Public Consultation

A. Public Consultation 15. Consultations were undertaken with key stakeholders in line with ADB’s requirements pertaining to environment and social considerations. Tools used for consultation were stakeholder meetings and focus group discussions (FGD). Consultant has carried out extensive consultations with affected communities, municipalities and stakeholders, including individual face to face interviews and public consultations.

16. The major stakeholders are: a. The municipality, its elected members and staff who will be required to oversee the construction of the distribution networks and WTP as well as be directly responsible for the maintenance of the installations b. Local residents who will take initiative to connect their houses with the water distribution line. c. Local business persons and traders d. School and college students e. Opinion makers who are intimately acquainted with and well regarded by the community, who need to be enlisted in spreading environmental awareness within the community as well as in conveying the benefits of the project.

17. Field visits were made to all proposed sites and pipeline alignments and the potential impacts and mitigation measures discussed with stakeholders. These consultations

Page | 6

DDR (IR) ( Alampur, MP ) helped identify the felt needs/concerns and apprehensions of the communities related to the project and priorities of concerned stakeholders. Discussions were held with people residing at and/or having businesses at/near the proposed subproject locations. Consultations revealed that people are aware of the problems of the existing water supply system in the city and are willing to cooperate in the proposed project. The field visits and interactions helped ascertain that no further survey and inventories are required. The following Table 2 provides a summary of consultations and discussions held. Appendix 2 provides the picture of stakeholders and community members consulted.

Page | 7

DDR (IR) (Alampur, MP)

Table 1: Summary of Consultation with Stakeholders Date Location No. of Participants Topics Discussed Issues Participants 14th At Total=27 Chairperson of • Briefing on project objectives • The Chairman welcomed the project; and Jan.2016 Community Male-17, ULB, Chief probable implementation given acceptance. hall female=10 Municipal procedures • Expressed concern about the present water Officer, elected • Need of improvement of the supply system and need for augmentation. representatives present situation, Present • Participants expressed concern about the of wards, ULB drinking water supply source and operation and maintenance of the facilities officials its condition developed under the project and community • Potential positive and negative participation. impacts due to project implementation • Land use and area to be covered under the project 14th Jan, Ward-06 Total -16 Local Resident • Briefing on project objectives • Community was glad to hear about the 2016 (Female- 6 probable implementation scheme Male -10) procedures • Assured full support during implementation. • Project effective for Alampur • People were concerned about the hiked of community people monthly water tariff. • Community participation in project implementation • Completion of project on time.

DDR (IR) (Alampur, MP)

14th Jan. Slum Total=12 Female Group • Briefing on project objectives • The women expressed need for the proposed 2016 area F=12,M=0 probable implementation scheme • procedures Grievance Redress • Due to scarcity of water in summer, women procedures have to face more problems. • Women showed willingness to take household connections if they get sufficient water. • Expressed need for subsidy in connection charges.

DDR (IR) ( Alampur, MP )

V. LAND AVAILABILITY AND INVOLUNTARY RESETTLEMENT IMPACTS

18. No land acquisition or resettlement impacts are anticipated for any of the proposed civil works for Alampur water supply subproject. The proposed weir will be constructed on Sindh river; permission for construction from Water Resource Department to be taken.

19. No impact on users downstream of anicut/weir and intake well Sindh River, is anticipated. During site visit it is observed that three natural streams join Sindh River within 5 Km downstream from the proposed annicut/weir and intake location. Out of the three streams, one stream joins from left side and two streams join Sindh River from right side with respect to direction of flow of the river. All these streams are natural drainage channels that carry the runoff generated by the rainfall in this area. There is no industry or town situated in this patch of river, a few agricultural fields are found out, which are dependent on the river for one cropping season only. The top level of the proposed annicut/weir is much lower than the HFL, hence water will continue to overflow and no downstream impacts are anticipated due to construction of Annicut and intake.

Figure 1: Showing flow of Sindh River from Intake to downstream

20. Intake Well and WTP is proposed on Sindh river on the way to Ratanghar Mata Temple. WTP land is now in the state government’s possession /ownership; process of land transfer to ULB is under process. The permission construction of Weir and Intake well to be taken from Water Resource Department, making sure that its conditions for granting of NOC are met.

Page | 10

DDR (IR) ( Alampur, MP )

21. In Alampur town raw water abstraction will be done from Weir through intake well at Sindh River to WTP, then treated and supplied to the town. The proposed water treatment plant (WTP) will be constructed on land belonging to Government of Madhya Pradesh. The land has been in the Revenue Department’s possession for many years and was not acquired in anticipation of ADB funded MPUSIP.

22. The clear water sump of 50 cum has been proposed for storage of treated water and to be constructed within the WTP complex. The ULB shall apply for No Objection Certificate (NOC) from WRD for raw water extraction and construction of intake well at source. The other sites for construction of the proposed water works are revenue land (GoMP). The ULB has to take NOC or transfer of land. 23. The clear water rising mains will be laid underground within the RoW of PWD road from WTP to Clear water sump. The site for the proposed OHT is near tehsil office in Alampur and the land belongs to Nagar Parishad. 24. New distribution pipelines (29296m) are proposed to be laid within existing road ROWs of Nagar parishad road. Proposed pipe diameters range between 75 mm and 250 mm.

25. Pipe laying activity on roads in the most congested market areas and densely builtup areas has been carefully planned to avoid IR impacts including temporary economic impacts to hawkers, shops and businesses.

26.Mobile hawkers will be assisted to move to places vacant nearby or to other side of the road, to ensure their earnings are not affected or the weekly market day will be avoided for construction. Only mobile vendors will be shifted to a nearby location during the period of construction and assistance to shift will be provided by the contactor. No income loss is anticipated.

27. House service connections and domestic water meters: The town has a total of 2123 households. In the initial phase of project 80% of household considered for water connections it is equal to 1700 nos. Contractor will have to ensure access as per EMP provisions, to ensure that there is no temporary income loss. 28. Site inspections and transect walk was carried all along the proposed laying of clear water feeder mains. The proposed pipeline for clear water feeder mains will be laid within the RoW of the existing road. The 38302 m distribution network pipelines in Alampur will be laid within the road RoWs of the Nagar Parishad. Details of land ownership for each water works component proposed to be constructed are given in Appendix 1.

29. Among linear components, laying of Clear Water Feeder Mains for the water supply project is proposed to be laid mostly along the existing government (PWD) roads RoW. The common feeder mains carry clear water from the WTP to the OHTs of the town.

30. New distribution network includes laying of 38302 meter pipeline. These pipelines are proposed to be laid underground along the existing public roads belonging to Nagar

Page | 11

DDR (IR) ( Alampur, MP )

Parishad road RoWs. Proposed pipe diameters to be laid range between 75 mm to 280 mm depending on the width of the roads that vary between 3 to 15 m. Distribution lines are proposed on one sides/ center of the road depending up on availability of space where road widths are small.

31. Civil works in the project include linear excavation for laying pipes along the roads, placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4 m – 0.7 m wide and 0.8 to 1 m depth. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works. Few roads in the core city area are narrow and congested with pedestrians and vehicles, while the roads in outer areas are wide. No necessity for full closure of roads is identified. Proposed distribution pipe-laying on roads in most part of the town will not have any permanent or temporary IR impact.

32. Laying of transmission mains and distribution network pipelines in the project area has been carefully planned to minimize disturbance to pedestrians and traffic and avoid income loss to businesses. Potential temporary impacts to traffic/access to shops and residences due to digging and excavation for pipe laying are possible during construction; however, these will be mitigated by ensuring access to properties through provision of pedestrian planks, provision of adequate signage, and careful traffic management.

33. In case temporary shifting of vendors with temporary structures is necessary, such shifting will be undertaken on a weekly holiday, to avoid income loss on the day(s) of shifting. The vendors will be assisted to shift and will be able to continue plying their trade during the construction period at the alternative location. No income loss is anticipated.

Table 2: Photograph of Rising main, Clear water rising main & distribution lines Rising main

Proposed clear water rising main alignment

Page | 12

DDR (IR) ( Alampur, MP )

Proposed distribution network through congested lanes

Page | 13

DDR (IR) ( Alampur, MP )

Table 3: Proposed sub-project components in Alampur Water Supply Subproject, Bhind District and their involuntary resettlement impact status Sr. Components Capacity Unit Length Land IR Impact IP Impact (No.) ownership Water Supply

1 Weir 1 WRD Weir is proposed on sindh None river. The permission for construction of Weir on Sindh river near at bridge near Ratangarh Mata Temple is to be taken from WRD. It is under process. 2 Intake well on right 1.5 MLD 1 WRD land The Intake well proposed on bank at bridge Sindh river right bank of bridge near Ratangarh mata Temple. near Ratangarh Land belonging to Water Mata Temple Resource Department without any settlement/ squatter /cultivation or other use is available refer Appendix -1. The intake site is vacant and unused. 3 Surface Water 1.5 MLD 1 Government 3.820 ha of total land available Treatment Plant land for WTP only 1.5 ha of land is required. Water Treatment None Plant will be constructed near Abutting road to Ratangarh Mata temple The land is in the government’s possession /ownership. The land has been in the Revenue Department’s possession for many years and was not acquired in anticipation of ADB funded MPUSIP refer khasra details- 85, khasra map refer Appendix -1. Its vacant land. 4 Clear Water 50 cum 1 Government The proposed clear water None sump land sump at main head work with in the WTP complex, land belonging to Revenue Department. Refer Appendix-1. The site is vacant. 5 Over Head Tank 220.00 1 Government OHT of high capacity (OHT) KLL land constructed near existing OHT. Land is vacant the proposed OHT at Zone 2. Land belongs to Revenue Department refer Appendix -1. The land is vacant.

Page | 14

DDR (IR) ( Alampur, MP )

6 Guard cum 3 Government At Intake well and Water None operator house land treatment plant guard cum

and Boundary wall operator house is proposed .At with gate OHT proposed boundary wall. 7 Transmission Government Rising mains of 660m from None main land intake to WTP along PWD road (660+19,370mts) right of way. Transmission main (feeder main )of 19370 mtrs passes through unused/vacant/barren public lands /Road RoW of PWD 8 Chemical Storage 1 Government One chemical storage and None and dosing pump land dosing pump house proposed house at water treatment plant .The land belongs to Revenue Department and is vacant. 9 Distribution 29,296 Road RoW Pipelines pass through existing No Pipeline mtrs (public land) road RoWs (government additional impacts roads). Temporary impacts on on IPs other than HDPE pipe - traffic/access to shops and temporary 29,296mtrs residences anticipated in some access places. Contractor to provide disruptions signages indicating available identified as IR alternate access route to impacts for all minimize traffic disruptions. people in Contractor will have to ensure coverage area. access to shops and residences as per EMP provisions. 10 Household 2123 - During construction period, No additional connections with access to residences and impacts on IPs domestic metres shops likely to be temporarily other than affected. Contractor will have to temporary access ensure access as per EMP disruptions provisions, to ensure that there identified as IR is no temporary Income loss. impacts for all people in coverage area

Page | 15

DDR (IR) ( Alampur, MP )

VI. CONCLUSIONS A. Summary and Conclusions 34. No significant IR impacts are assessed at identified sites for sub-project components, as adequate vacant land is available for the proposed facilities, within the compounds of government lands. The site for new WTP and intake well at Alampur belongs to MP Government. Weir and Intake well is proposed on Sindh River and NOC for that is under approval. The site for a new OHT (proposed near Tehsil office) is government land. Linear components (pipe laying) are proposed within government road ROWs. Temporary disruption to road users, pedestrians and community members will be avoided in the most congested zones of Alampur with proper traffic management, with the help of local police and officials. Safety measures shall be taken during construction to avoid injuries. Inconvenience to the public shall be mitigated during construction by the contractor through simple measures such as provision of planks for pedestrian access to shops, coupled with effective traffic management. A budgetary provision is made for costs likely to be incurred for updating and implementation of this DDR.

Table 4: Budgetary Provision S.no Description Target group Estimated cost Source of fund 1 Consultation Affected persons INR 25,000; Included in of project area subproject cost 2 Communication, Affected persons INR 200,000 Included in awareness generation and of project area subproject cost grievance redress 3 Tanker supply for areas Affected areas INR 100,000 Included in where existing water supply subproject cost disrupted during construction 4 10% contingencies Affected persons INR 32,500 Included in of project area subproject cost Total INR 357,500

Page | 16

DDR (IR) ( Alampur, MP )

Figure 2: Google Map showing Transmission main from Intake well at Sindh River to WTP and to OHTs in Alampur

Page | 17

DDR (IR) ( Alampur, MP )

Figure 3: Location of Proposed Intake and WTP on Google Earth map

Page | 18

DDR (IR) ( Alampur, MP )

Figure 4: Location of Proposed OHT on Google Earth map

Page | 19

DDR (IR) ( Alampur, MP )

Figure 5: Proposed Transmission System for Alampur Water supply

Page | 20

DDR (IR) ( Alampur, MP )

Figure 6: Proposed Distribution Network for Alampur Water Supply

Page | 21

DDR (IR) (Alampur, MP)

Annexure 1: Details of Land Ownership for Proposed Water Works Components

Latitude - Longitude Ownership of Land Plot No.Availability of Site Component Location Status of NOC of components proposed (Khasra No) Land Record 260 05’29.12” N and Near Sindh River on 0 78 38’32.26”E ULB has applied the way to Ratangarh Water Resource for the NOC to Intake Well Mata Temple, 1.5 Yes Department (WRD) WRD MLD

26005’26.24”N and ULB has applied for the NOC to 780 38’53.29”E Revenue near Ratangharh WTP Government 85 Yes Department Mata Temple

Same as above near Ratangharh Clear water sump Government 85 Yes Same as above- Mata Temple

26001’22.59”N and 780 47’35.14”E

near existing Tehsil in possession of OHT Government office Yes ULB

DDR (IR) ( Alampur, MP )

Annexure 2: Stakeholder Consultation Photograph and List of participants

Community Consultation

Site visit for identifying location of components

Page | 23

DDR (IR) ( Alampur, MP )

List of Participants

Page | 24

DDR (IR) ( Alampur, MP )

Annexure 3: Involuntary Resettlement Screening Checklists

A. Introduction 1. Each project/subproject/component needs to be screen for any involuntary resettlement impactsand indigenous people impacts which will occur or already occurred. This screening determines the necessary action to be done by the project team.

B. Information on project/subproject/component: a. District/ Administrative Name: Bhind b. Location: Alampur c. Civil work dates (proposed): Not yet proposed d. Technical Description: Planning and design of Water Supply Scheme for Alampur. The scheme involves construction of intake well and WTP at on Sindh River near Ratan ghar mata Temple in Basai Malak village. Pumping water from intake wells to WTP. Laying of Clear water rising main of length 17 KM from WTP to the sump. Construction of 1 no of Over Head Tanks of size 240 KL with 15 m staging height and further distribution to end users by various distribution networks through gravitation.

C. Screening Questions for Involuntary Resettlement Impact Below is the initial screening for involuntary resettlement impacts and due diligence exercise. Both permanent and temporary impacts must be considered and reported in the screening process.

Involuntary Resettlement Impacts Yes No Not Reason known Will the project include any physical V Alampur Water Supply Scheme proposal will construction work? involve following construction works • Construction of 1 WTP and intake structure at Sindh river and 1 Overhead Tanks of 240 KL with 15 m staging height • Laying of approx. 29 km of distribution network within the town • Laying of Rising Main of approx. 17 km from intake well at Sindh river to Underground Sump Does the proposed activity include V upgrading or rehabilitation of existing physical facilities? Will there be permanent V All components of Water Supply Scheme are being land acquisition? proposed on Government land. The details are as follows – • Construction of weir, WTP, and intake Well near Sindh river on government land • 1 OHT is proposed on government land near Tehsil office. • Laying of the pipe line will be done on the side of the road where sufficiently wide road shoulder is available and through the center/edge of the road where wide road shoulder is not available

Page | 25

DDR (IR) ( Alampur, MP )

Will it require temporary land V • No temporary land acquisition will be there as all acquisition? components are proposed on government land • As per bid document, temporary site for worker camp and the storage of material site will be decided. Vacant land free of use will be taken on rent basis Is the ownership status and current V usage of the land known? Are there any non-titled people who V live or earn their livelihood at the site or within the corridor of impact (COI) / Right of Way (ROW)? Will there be loss of housing? V Will there be loss of agricultural plots? V All sites identified for proposed facilities under the water supply scheme are either under Government ownership or within the jurisdiction of the Nagar Parishad and are vacant and unused. Hence, no loss of agricultural plots envisaged. Will there be losses of crops, trees, and V In the proposed alignment no trees are found. It was fixed assets (i.e. fences, pumps, etc.)? found that all along the internal roads of the ULB, the individual house were built up to the road edge hence the distribution network is proposed to lay at the center or edge of the road where vacant government RoW is available to avoid disturbance to the fixed assets. But care will be taken to ensure that existing trees on road side and fixed assets are not affected during construction and laying of the facilities. Will there be loss of businesses or V Temporary loss of incomes will be avoided through enterprises? provisions of access planks by the contractor. Will there be loss of incomes and V livelihoods? Will people lose access to facilities, V services, or natural resources? Will any social or economic activities V be affected by land use-related changes? Will people lose access to natural V resources, or common property resources, or communal facilities and/or services? If land use is changed will it have an V adverse impact on social and economic activities? Will access to land and resources V owned communally or by the state be restricted? Are any of the affected persons (AP) V from indigenous or ethnic minority groups?

Page | 26

DDR (IR) ( Alampur, MP )

D. Involuntary Resettlement Impact 1. After reviewing the answers above, EA/ Safeguard Team confirms that the proposed subsection/ section/ subproject/component (tick as appropriate): [ ] Has involuntary resettlement (IR) impact, a resettlement plan (or corrective action plan) is required

[V ] Has No IR impact, no resettlement plan is required.

Page | 27

DDR (IR) ( Alampur, MP )

Annexure 4: Land Details Khasra details of WTP land

Note: Khasra is land record maintained by the state government, which depicts for each land parcel, the parcel number, ownership, area and land use. The Khasra/land record is usually accompanied by a scaled map.

The above records depict that the proposed WTP site is owned by government and available area of land is 3.8 hectares

Page | 28

DDR (IR) ( Alampur, MP )

Alampur Khasra map for WTP land

Note: Khasra map is sketch of pocket or location of land on map, land record maintained by the state government, which depicts for each land parcel, the parcel number.

Page | 29

DDR (IR) ( Alampur, MP )

Annexure 5: Certificate of Chief Municipal officer regarding

Land Ownership Status

Page | 30

DDR (IR) ( Alampur, MP )

This is to certify that the Nagar Parishad Alampur, Dist. Bhind (MP) have sufficient own space at Ward No. 08 for OHT and Sump Well.

Page | 31