CLOSING DATE FOR PUBLIC CONSULTATION 19th MAY 2021

Lot 2 – Munster Bridges Term Maintenance Contract No. 3 Culvert Inverts – Group 1 (Knockakip Culvert), Natura Impact Statement Transport Infrastructure Ireland

19/03/2021

Notice

This document and its contents have been prepared and are intended solely as information for Transport Infrastructure Ireland and use in relation to the proposed project. WS Atkins Ireland Limited assumes no responsibility to any other party in respect of or arising out of or in connection with this document and/or its contents. This document has 44 pages including the cover.

Document history Origin- Author- Revision Purpose description ated Checked Reviewed ised Date Rev 0 Draft for Comment NS NS POD MJ 03/06/2020 Rev 1 For Issue NS NS POD MJ 15/07/2020 Rev 2 Minor amendments – NS NS POD MJ 22/10/2020 For Issue Rev 3 For Issue NS NS POD MJ 12/11/2020 Rev 4 Minor amendments – NS NS POD MJ 09/02/2021 For Issue Rev 5 Minor amendments – NS NS POD MJ 19/03/2021 For Issue

Client signoff Client Transport Infrastructure Ireland Project Lot 2 – Munster Bridges Term Maintenance Contract No. 3 Job number 5162555

Client signature / date

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page ii of 44

Contents

Chapter Page 1. Introduction 1 1.1. Project Context 1 1.2. Project Description 2 2. Scope of Study 8 2.1. Legislative Context 8 2.2. Appropriate Assessment Process 8 3. Methods 10 3.1. Legislation & Guidance Documents 10 3.2. Desk Study 10 3.3. Site Visit 11 3.4. Consultation 11 3.5. Statement of Authority 11 4. Existing Environment 12 4.1. Desktop Review 12 4.2. Site Visit 12 5. Screening for Appropriate Assessment 15 5.1. Connectivity of Proposed Project to European Sites 15 5.2. Brief Description of European sites 18 6. Appropriate Assessment 23 6.1. Introduction 23 6.2. Impact Evaluation 23 6.3. Mitigation Measures 29 7. Conclusions 32 References 34

Appendices 35 Appendix A. Design Detail 36 Appendix B. Contractor Method Statement 37 Appendix C. Hydraulic Assessment 38 Appendix D. Section 50 Consent 39

Tables Table 1-1 - Grouping of Structures in Munster 1 Table 5-1 - Qualifying interests of the SAC within the ZoI of the proposed project. 20 Table 6-1 - Site-specific conservation objectives for QIs within ZoI of the proposed project. 25

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page iii of 44

Figures Figure 1-1 – Dam set up for water management 3 Figure 1-2 - Site Location 7 Figure 2-1 - Appropriate Assessment Process (Source: DEHLG, 2009). 9 Figure 5-1 – SACs within potential ZoI of the proposed project. 16 Figure 5-2 - SPAs within the potential ZoI of the proposed project. 17

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page iv of 44

1. Introduction

Atkins have been commissioned by Transport Infrastructure Ireland (TII) to install a concrete invert at Knockakip Culvert (KY-N21-016.00), Co. Kerry. The scope of this Natura Impact Statement (NIS) is for the proposed project at Knockakip Culvert. The proposed project falls under the TII Munster Bridges Term Maintenance Contract No. 3. 1.1. Project Context

The EIRSPAN Bridge Management System covers all aspects of bridge management including routine maintenance. Over the past number of years TII have undertaken routine bridge maintenance contracts under Bridge Term Maintenance Contracts. A TII Bridges Term Maintenance Contract is currently being delivered for all National Road Bridges in Munster.

Under the Munster Bridges Term Maintenance Contract No. 3, Atkins has been appointed as the Consultant to carry out services under the Contract such as bridge inspections and reporting, ecological assessment, production of contract documents, tender assessment, contract administration and site supervision. The Contract involves the annual inspection and undertaking of routine and reactive maintenance works to all National Road Bridges across all counties in the Munster region, namely counties (City & County), Kerry, Waterford, Tipperary, Limerick and Clare. This contract will run until 2021, where it is intended to carry out annual routine maintenance work between circa June and December in each year. All works from each year will be subject to the Appropriate Assessment (AA) process.

It is proposed to install concrete inverts to all existing corrugated steel culverts under National Roads in Munster. These culverts were installed during the 1970s and 80s. The culverts now show signs of significant corrosion and to maintain their structural integrity, a concrete invert liner is to be installed. Under the current Bridges Routine Term Maintenance Contract TII have selected 5 corrugated steel culverts for concrete invert lining. These culverts are presented in Table 1-1 below.

The culverts proposed for concrete invert installation initially underwent Screening for Appropriate Assessment in 2018. TII determined that likely significant effects to European sites, in view of their conservation objectives, could not be ruled out and thus required Appropriate Assessment. Thus, the proposed concrete invert installation at Knockakip Culvert requires further assessment.

For the purposes of assessment, the 5 culverts in Munster have been grouped according to their potential zone of influence and location within Water Framework Directive (WFD) catchments. Using this system, 3 groups were established. These groups are detailed in Table 1-1. Where European sites are located within the potential zone of influence of more than one grouping, the potential for cumulative impacts shall also be considered. Knockakip Culvert is assigned to Group 1, which is in the Bay - Feale WFD catchment.

Table 1-1 - Grouping of Structures in Munster

Group No. Structure Name & No. WFD Catchment

Group 1 Knockakip Culvert (KY-N21-016.00) Tralee Bay - Feale Group 2 Anner Bridge (TS-N24-007.00) Suir

Group 3 Killaha Culvert (KY-N22-024.00) Laune – Maine – Dingle Bay Curraglass Culvert (KY-N22-025.00) Derryreag Culvert (KY-N22-028.00)

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 1 of 44

1.2. Project Description

Transport Infrastructure Ireland undertake routine bridges maintenance works to structures associated with the National Roads Network. This project comprises the provision of a concrete invert lining and associated instream works to Knockakip Culvert (KY-N21-016.00), Co. Kerry. Knockakip Culvert is located on the N21, approximately 6km north-east of town. Knockakip Culvert is situated on the Ballyduff stream, which is a tributary of the River Owveg, located in the Feale subcatchment.

This corrugated steel structure has been identified as having durability and structural issues as a result of the erosion of previous bitumen protection linings and progressive corrosion of the metal particularly in the lower region. The purpose of the concrete invert is to mitigate further corrosion and section loss to the invert of the culvert and to restore and maintain it structural integrity.

It should be noted that the scope of the proposed project is the replacement of the existing concrete lining at the base of the culvert. Given engineering constraints for the structure, it is not feasible to retrofit a ledge for mammal passage within the existing structure. The design and installation of an entirely new structure would be required for this to be achieved, which is outside the scope of the proposed project.

The culvert will be dammed upstream and downstream within 10m of the culvert using double lined sand bags, filled with clean sand, tied and wrapped in heavy gauge polyethene.

There will be three dams erected in the stream; dam 1 upstream of the culvert and dam 2 &3 situated downstream of the culvert (Figure 1-1). Dam 2 and 3 will be erected first, 300mm high on the stream bed. Dam 1 will then be erected, and the stream flow pumped downstream of dam 3. The intake will be fitted with a filter to ensure no fish enter the pipeline. The outfall pipeline will be fitted with a silt sock. This will dissipate flow and prevent scour of the river bed. The stream between dam 1 & 2 will be electro fished and the fish placed in the pool created between dam 2 and 3. On completion of the electro fishing dam 2 will be raised to full height and a silt fence will be erected between dam 2 and dam 3 and a second silt fence will be erected just upstream of dam 3. The water between dam 1 and dam 2 will be pumped into the pooled area between dam 2 and dam 3 in advance of the silt fences. A shallow sump will be excavated (or naturally occurring) in the stream bed upstream of dam 2 to catch surface water and cleaning water from power washing the culvert. The collected water in the sump will be pumped downstream between dam 2 and dam 3 and discharge in advance of the silt fences.

Large boulders will be removed from the riverbed prior to placing a heavy-duty geotextile on the river substrate and stored within the works area for reinstatement on completion of the works. A hardstanding working platform will be placed over the geotextile upstream and downstream of the culvert. The working platform will consist of clean gravel/ crushed rock (typically 250mm thick depending on the riverbed ground conditions). Existing stream bed material within the metal culvert will be captured and stored within the works area for reinstatement on completion of the concrete lining. The corrugated steel culvert will be cleaned by power washing and hand-held mechanical tools such as wire brushing and grinding. The power washing water will be collected in a sump within the works area (i.e. upstream of dam 2) and discharged through the double silt fencing and dam 3 before entering the downstream waters. Arisings from the corrugated metal culvert cleaning will be collected within the culvert and disposed off-site to a licensed waste facility. Prior to placement of the lining, the corrugated steel culvert invert area to be lined will be primed with anti-corrosion primer, prior to placing 150mm thick (nominal) reinforced (stainless steel) concrete to circa one-third of the culvert height. On completion of the culvert lining works the temporary working platform and geotextile will be removed. The culvert bed will be reinstated with stream bed material that was removed from the culvert prior to the works and the stream bed will be regraded locally to the culvert ends with clean natural gravels to realign the culvert and stream bed levels.

The drawing detail of the proposed works is included in Appendix A.

The Contractor’s method statement details how the works will be carried out and the works sequence. The Contractor’s method statement is included in Appendix B and is summarised in the text below along with general specifications of the works from the contract’s Works Requirements Specifications.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 2 of 44

Figure 1-1 – Dam set up for water management

1.2.1. Working Methods

Under the Munster Bridges Term Maintenance Contract No. 3, the works are carried out according to the Works Requirements Specifications. This details the general specifications of the works, which includes the installation of concrete inverts to corrugated structures: -

“The contractor shall remove all silt/debris and deposit build-ups from the structure ensuring appropriate downstream silt containment measures are in place. The existing invert shall be prepared for the installation of the sprayed concrete invert (HTR-DR 1006 & 1007) by cleaning back to bright steel. Removal of all detrimental contamination and corrosion products using handheld tools to produce a generally bright appearance overall. The surfaces shall be free of embedded abrasive particles and corrosion products when viewed through a x10 illuminated magnifying glass. The invert shall then be coated with the corrosion inhibitor Galvafroid manufactured by Fosroc. An anti-corrosion steel primer, Nitoprime Zincrich Plus by Fosroc, will be used to prime the steel”.

Fosroc were contacted regarding the above products proposed to be used during the installation of the concrete invert, as the Safety Data Sheets (SDS) for Galvafroid and Nitoprime Zincrich Plus categorise these products as ‘Aquatic Acute (1-H400) and Aquatic Chronic (1-H410)’. The SDS states that the products ‘contain a substance which is toxic to aquatic organisms and which may cause long-term adverse effects in the aquatic environment’. Fosroc confirmed that the danger to aquatic organisms arises from chlorinated paraffin, which is used as a plasticiser for the product when in a liquid state. These products will be applied during the installation of the concrete culvert in a dry working area. Once cured this material is bound in a polystyrene matrix and no longer mobile. Therefore, it is not regarded as a pollutant in its cured and solid state. These products are not epoxide resin-based coatings, which have been shown to potentially have adverse effects on the aquatic environment (Bell et al., 2020).

As stated in the Contract, existing deposits within the corrugated steel culvert will be removed and disposed of off-site, with the corrugated invert being cleaned back to bare steel using hand held tools. The exposed steel under the proposed concrete lining shall be treated with a corrosion inhibitor followed by an anti-corrosion steel primer. All shotcreting works shall be undertaken in accordance with ‘BS EN 14487: Sprayed Concrete – Execution’.

The installation of the culvert invert lining will be carried out during low water conditions in the months of July to September inclusive.

The Contractor’s method statement details how the works will be carried out in the works sequence. The Contractor’s method statement is included in Appendix B and is summarised in the text below.

The proposed project is anticipated to last approximately 2 weeks. The existing carriageway over the culvert shall always remain in service.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 3 of 44

Typical sequence of works

The sequence of proposed works is sourced from the contractor’s method statement and detailed below: -

• In relation to existing bed gravels immediately upstream and downstream of structure: Existing river bed gravels shall be retained. Lay Terram 2000GT on existing riverbed gravel and construct temporary 300mm thick clean Class 6F granular capping over to form working platform. On completion of the works remove the granular working platform and geotextile. Supplement the existing gravels to IFI requirements local to the culvert ends;

• Excavator to be tracked down the path from the road to the river;

• Existing concrete lining to be broken from culvert using breaker on 1.5T machine;

• Broken out material to be removed using excavator, shovels and wheel barrows. Kango hammer to be used where necessary;

• Material to be disposed of in Conhor Construction Tip in ;

• Power Washing of Culvert Lining:

o The lining will be cleaned using a 25.000PSI Hydro Power Washer removing the loose / decayed material and exposing a clean Sa3 finish on the existing steel lining.

o The washing unit generator will be positioned in the works area on the road with the lance hose running down the bank into the mouth of the culvert.

o The washing will commence on upstream side, washing in the downstream direction.

o It is predicted that the power washing will remove all loose / decayed material but if required small angle grinders and wire brushes will be used to remove any small pockets that remain. This area will then be power washed again to ensure it is completely clean.

o A silt fence will be erected at the outfall of the culvert on the downstream side to ‘filter’ the resultant water from the washing of the steel lining.

o Arisings from the cleaning of the culvert lining will be collected within the culvert and disposed of off-site to a Conhor construction tip.

o A small pump will then be placed on the down – stream side to pump the water into the area between Dam 2 and Dam 3.

o A layer of silt fencing will be wrapped around the intake pipe of the pump as an additional filter layer and the outfall will have a de-watering bag placed around the end of hose.

• Nominal 200mm Thick C25/30 Shotcrete Lining with A393 Stainless Steel Mesh Reinforcement to 1.3 diameter height.

• Existing deposits within the corrugated steel culvert to be removed from the culvert and stored for reuse;

• The invert shall then be coated with the corrosion inhibitor Galvafroid manufactured by Fosroc;

• An anti-corrosion steel primer, Nitoprime Zincrich Plus by Fosroc, will be used to prime the steel;

• Shotcreting: -

o All shotcreting works shall be undertaken in accordance with "BS EN 14487: sprayed concrete - execution";

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 4 of 44

o Nominal 200mm Thick C25/30 Shotcrete Lining with A393 Stainless Steel Mesh Reinforcement to 1/3 diameter height;

o The culvert lining works shall be executed during the low water flow in the months July to September inclusive;

o Set up pump on road within works area;

o Pump hoses will always be located within dry works area so there is no chance of concrete spillage entering the watercourse;

o Care to be taken when working beside live road;

o Direct concrete lorry to pump;

o One man to act as pump operative;

o 2 men required for nozzle and spraying;

o Spotter to stand at mouth of culvert and act as communicator between pump man and nozzle man;

o Googles or glasses to be worn at all times when shotcreting;

o Nominal 200mm to be sprayed on culvert face;

o Pump hoses etc. to be completely cleaned ready for next day’s pour.

• Works will take approximately 2 weeks;

• Excess concrete to be put in skip;

• Upon demobilisation all plant and materials to be taken away in Cumnor hiab truck with hiab crane. Terram to be disposed of in skip.

• Flume to be removed from river and Dam 1 & 2 dismantled;

• Silt fences and dam 3 to be left in place until the sediment upstream of same has dissipated;

• Small step in river bed outside culvert to be reinstated with washed gravel as required;

• All sandbags to be lifted from river and taken to Conhor Construction tip in Ballincollig;

• River bed outside culvert to be reinstated with clean gravels as required.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 5 of 44

1.2.2. Hydraulic Assessment

A hydraulic impact assessment was prepared for the proposed project. The hydraulic assessment report is included in Appendix C. The hydraulic assessment was conducted to analyse the impact of the proposed lining on the culvert’s flow capacity, change in predicted water levels upstream and downstream of the culvert, and changes in the velocities during low flow events. The hydraulic model shows that the proposed works to the existing culvert will not have a significant impact on the hydrological and hydraulic regime of the watercourse. The hydraulic impact assessment supported a Section 50 licence application to the Office of Public Works (OPW). Section 50 consent has been obtained for the proposed project at Knockakip Culvert (Appendix D), granted on 19th March 2021. A recommendation of the consent was that the proposed project should be designed to be resistant to scour and erosion, especially in a flood situation. The design of the proposed project incorporates this recommendation.

The following conclusions, based on the hydrology estimations and further hydraulic model assessment for the baseline and proposed scenarios, were made in the hydraulic assessment for Knockakip culvert: -

• ‘This hydraulic capacity assessment has been prepared in consideration of the requirements under Section 50 of the Arterial Drainage Act 1945.

• IH124 methodology has been used to derive flows for QMED, Q100 and Q100C1 and their magnitudes are 1.639 m3/s, 3.438 m3/s and 4.125 m3/s, respectively.

• The proposed works, due to the reduced flow area and higher invert levels results in increase in water levels upstream of the Knockakip culvert. No changes in the maximum water levels are predicted at the downstream end of the culvert.

• For the three events analysed, the predicted increase in the maximum stage is in the range of 215 mm to 271 mm. The change due to the proposed works is within the OPW limit of 300 mm.

• A minimum freeboard of 1.90 m is available in the culvert under all conditions, and this meets the OPW minimum threshold criteria.

• During low flow conditions, there is sufficient depth of flow, above the recommended 150 mm water depth for fish passage. The proposed works is not expected to cause significant worsening of the present situation with regards to fish passage.

• To aid in smooth fish movement during low flows, placing large rocks and providing transition pools should be considered at the channel immediately downstream of the culvert in discussion with Inland Fisheries Ireland.

• No nearby properties are expected to be affected in the proposed scenario.’

As detailed above, a recommendation of the hydraulic assessment was for the provision of large rocks and pools in the channel immediately downstream of the culvert, in consultation with Inland Fisheries Ireland. Atkins consulted with Inland Fisheries Ireland (IFI) in May 2020. IFI were of the opinion that due to very little channel upstream of the culvert and the fact that the channel is unlikely to be fish bearing, such provisions were not necessary. Prevention of loss of sediment and cementitious material to the watercourse were raised as a concern during the proposed installation of the concrete invert. These concerns will be addressed through the implementation of measures detailed in the working methods, contractor’s method statement (Appendix B) and mitigation measures set out in Section 6.3 of this NIS.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 6 of 44

Legend Knockakip Bridge Rivers

Client: Transport Infrastructure Ireland

Project: Munster Bridges Term Maintenance Title: Knockakip Bridge site location

Drawn: Checked: Authorised: EN NS PO'D Date: Date: 29/05/2020 Date: 29/05/2020 29/05/2020

Drawing No: 1-2 Rev: 1.0

Ordnance Survey Ireland Licence No. AR 0082517 © Ordnance Survey Ireland and Government of Ireland

2. Scope of Study

The proposed project was previously subject to Screening for AA, where TII determined that the proposed project required Appropriate Assessment.

Thus, the aim of this report is to provide supporting information to assist the competent authority to carry out an Appropriate Assessment with respect to the proposed project. 2.1. Legislative Context

Directive 92/43/EEC on the Conservation of Natural Habitats and Wild Fauna and Flora, known as the ‘Habitats Directive’ provides legal protection for habitats and species of European importance. Article 2 of the Directive requires the maintenance or restoration of habitats and species of European Community interest, at a favourable conservation status. Articles 3 – 9 provide the legislative means to protect habitats and species of Community interest through the establishment and conservations of an EU-wide network of sites known as European sites. European sites are Special Areas of Conservation (SACs) designated under the Habitats Directive and Special Protection Areas (SPAs) designated under the Conservation of Wild Birds Directive (79/409/EEC).

Articles 6(3) and 6(4) of the Habitats Directive set out the decision-making tests for plans or projects that could potentially affect European sites. Article 6(3) establishes the requirement for Appropriate Assessment: -

“Any plan or project not directly connected with or necessary to the management of the site but likely to have a significant effect thereon, either individually or in combination with other plans or projects, shall be subject to appropriate assessment of its implications for the site in view of the site's conservation objectives. In the light of the conclusions of the assessment of the implications for the site and subject to the provisions of paragraph 4, the competent national authorities shall agree to the plan or project only after having ascertained that it will not adversely affect the integrity of the site concerned and, if appropriate, after having obtained the opinion of the general public.”

Article 6 (4) deals with the steps that should be taken when it is determined, as a result of Appropriate Assessment, that a plan or project will adversely affect a European site. Alternative solutions, imperative reasons of overriding public interest (IROPI) and compensatory measures need to be addressed in this case. Article 6(4) states: -

“If, in spite of a negative assessment of the implications for the site and in the absence of alternative solutions, a plan or project must nevertheless be carried out for imperative reasons of overriding public interest, including those of a social or economic nature, the Member State shall take all compensatory measures necessary to ensure that the overall coherence of Natura 2000 is protected. It shall inform the Commission of the compensatory measures adopted.

Where the site concerned hosts a priority natural habitat type and/or a priority species, the only considerations which may be raised are those relating to human health or public safety, to beneficial consequences of primary importance for the environment or, further to an opinion from the Commission, to other imperative reasons of overriding public interest.” 2.2. Appropriate Assessment Process

Guidance on the AA process was produced by the European Commission (EC, 2001; 2018), which was subsequently used to develop guidance for Ireland by the Department of Environment, Heritage and Local Government in 2009 (DEHLG, 2009) and also by the National Parks and Wildlife Service in 20181 (NPWS 2018). These guidance documents set out a staged approach to complete the AA process and outlines the issues and tests at each stage. The stages outlined below are taken from the guidance document Appropriate Assessment of Plans and Projects in Ireland – Guidance for Planning Authorities (DEHLG, 2009).

1 https://www.npws.ie/development-consultations

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 8 of 44

Figure 2-1 - Appropriate Assessment Process (Source: DEHLG, 2009).

2.2.1. Screening for Appropriate Assessment

Screening is the process that addresses and records the reasoning and conclusions in relation to the first two tests of Article 6(3): -

i. Whether a plan or project is directly connected to or necessary for the management of the site, and ii. Whether a plan or project, alone or in combination with other plans and projects, is likely to have significant effects on a European site in view of its conservation objectives.

If the effects are deemed to be significant, potentially significant, or uncertain, then the process must proceed to Appropriate Assessment.

2.2.2. Appropriate Assessment

Appropriate Assessment considers whether the plan or project, alone or in combination with other projects or plans, will have adverse effects on the integrity of a European site, and includes any necessary mitigation measures.

The competent authority can only agree to the plan or project after having ascertained that it will not adversely affect the integrity of the site(s) concerned. If this cannot be determined, and where sufficient mitigation cannot be achieved, the alternative solutions need to be considered and the process proceeds to the consideration of alternative solutions.

2.2.3. Alternative Solutions

This examines any alternative solutions or options that could enable the plan or project to proceed without adverse effects on the integrity of a European site. The process must return to AA as alternatives will require assessment in order to proceed. Demonstrating that all reasonable alternatives have been considered and assessed, and that the least damaging option has been selected, it is necessary to examine whether there are imperative reasons of overriding interest (IROPI).

2.2.4. IROPI

This examines whether there are imperative reasons of overriding public interest for allowing a plan or project that will have adverse effects on the integrity of a European site to proceed in cases where it has been established that no less damaging alternative solution exists. Compensatory measures must be proposed and assessed, of which the Commission must be informed.

The AA process only progresses through each of the full process for certain plans and projects. For example, for a project not connected with the management of a European site and where no likely significant effects on a European site in view of its conservation objectives are identified, the process stops at Screening for AA. Throughout the process the precautionary principle must be applied, which requires that the conservation objectives of Natura 2000 should prevail where there is uncertainty (EC, 2001; 2018).

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 9 of 44

3. Methods 3.1. Legislation & Guidance Documents

This report was prepared with reference and due consideration to the following documents and due regard for relevant case law, including but not limited to: -

• Council Directive 92/43/EEC of 21 May 1992 on the conservation of natural habitats and of wild flora and fauna (Habitats Directive);

• Statutory Instrument No. 477/2011 — European Communities (Birds and Natural Habitats) Regulations 2011;

• National Parks and Wildlife Service - Development Consultations2 (NPWS, 2018)

• European Commission (2018). Managing Natura 2000 sites: the provisions of Article 6 of the ‘Habitats’ Directive 92/43/EEC;

• European Commission (2001). Assessment of plans and projects significantly affecting Natura 2000 sites: Methodological guidance on the provisions of Articles 6(3) and (4) of the Habitats Directive 92/43/EEC;

• Department of the Environment, Heritage and Local Government (2009). Appropriate Assessment of Plans and Projects in Ireland. Guidance for Planning Authorities; and,

• Case C-323/17 People Over Wind & anor. V. Coillte. 3.2. Desk Study

A desk study was carried out to collate information available on European sites in the vicinity of the proposed project. These areas were viewed using Google Earth, Google maps3 and Bing maps4 (last accessed on 28/05/2020).

The National Parks and Wildlife Service (NPWS) and National Biodiversity Data Centre (NBDC) online databases were reviewed concerning European sites and their features of interest in the vicinity of the proposed project. The Environmental Protection Agency (EPA) mapping5 system was used to identify any hydrological connection between the proposed project and European sites.

Locations and boundaries of all European sites within 15km of the proposed project were identified and reviewed using the NPWS online map viewer. Boundary shapefiles were also downloaded from this site to facilitate the preparation of project graphics.

Desktop information on relevant European sites were reviewed on the NPWS website, including the site synopsis for each SAC/SPA, the conservation objectives, the site boundaries as shown on the NPWS online map viewer, the standard Natura 2000 Data Form for the SAC/SPA which details conditions and threats of the sites, and published information and unpublished reports on the relevant European sites.

Relevant planning information for the surrounding area was reviewed using the planning enquiry systems of Kerry County Council. Search criteria were implemented to determine whether such projects or plans that would not be relevant to this study. This information was used to determine potential cumulative impacts from other plans / projects with the proposed works.

2 https://www.npws.ie/development-consultations 3 https://www.google.ie/maps 4 http://www.bing.com/maps/ 5 https://gis.epa.ie/EPAMaps/

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 10 of 44

3.2.1. Geographical Information System

Under the Munster Bridges Term Maintenance Contract No. 3, Atkins developed a Geographic Information System (GIS) to store all ecological data relating to the Munster bridges and to facilitate easy interrogation of data both within the dataset and spatially. The GIS was used during the assessment of the 16 structures proposed for the installation of concrete inverts for geospatial analysis of all data using MapInfo V. 16. This included the examination of the locations and boundaries of European sites within 15km of all structures and determination of surface water connectivity between structures and European sites, using the EPA’s river network data.

Under the Munster Bridges Term Maintenance Contract No. 3, Atkins submitted a data request to NPWS regarding freshwater pearl mussel Margaritifera margaritifera. This dataset was also used in the GIS. 3.3. Site Visit

An ecological walkover survey of the site was conducted by an Atkins ecologist during September 2019. The purpose of the survey was to survey the site for invasive plant species and to record the habitats and flora in the vicinity of the proposed project. The survey was chiefly concerned with recording the presence or likely presence of protected species and recording protected habitats or those habitats suitable to support protected species, in particular qualifying interests of European sites. The survey had regard for guidance sources such as NRA (2009) and Smith et al. (2011).

Aerial photos and site maps assisted the ecological walkover survey. Mammals and birds were surveyed based on incidental sightings, signs of activity during the survey and the identification of possible suitable habitats to support these species. Habitats were classified and named according to Fossitt (2000). During the ecological survey the presence of invasive plant species such as Japanese knotweed Reynoutia japonica, Himalayan balsam Impatiens glandulifera and Giant Hogweed Heracleum mantegazzianum were recorded. 3.4. Consultation

Consultation took place with IFI and the OPW regarding the proposed installation of the concrete invert at Knockakip culvert. Concerns raised by IFI were in relation to the loss of sediment and cementitious material to the watercourse during the installation of the proposed concrete invert, which are addressed in the working methods, contractor’s method statement (Appendix B) and mitigation measures set out in Section 6.3 of this report. Consultation with the OPW was with respect to the findings of the hydraulic assessment (Appendix C). Section 50 consent has been obtained for the proposed project at Knockakip Culvert (Appendix D). 3.5. Statement of Authority

This report was prepared by Niamh Sweeney under the direction of Paul O’Donoghue, who also provided peer review support.

Niamh Sweeney (BSc, MSc (Res)) is a freshwater ecologist with over 10 years’ experience in ecological consultancy, with specialisms in macroinvertebrate and diatom taxonomy. Niamh has worked on numerous Screenings for Appropriate Assessment, Natura Impact Statements and Ecological Impact Assessments for private architect firms, waste companies, numerous County Councils, the OPW and Inland Fisheries Ireland. Niamh carried out the site visit and preparation of this report.

Emma Nickelsen has a BSc (Hons) in Environmental Biology and an MSc in Marine Biology. Emma has worked in ecological and environmental consultancy since 2017, working on a wide range of projects including bridge works, road construction, local amenity development and renewable energy. A focus of Emma’s work to date has been on conducting Appropriate Assessment screenings, ecological appraisals and supporting the preparation of Natura Impact Statements and Ecological Impact Statements. Emma assisted in the preparation of this report.

Paul O’Donoghue has a BSc (Zoology), MSc (Behavioural Ecology) and a PhD in avian ecology and genetics. Paul is a chartered member of the Society for the Environment (CEnv) and a full member of the Chartered Institute of Ecology and Environmental Management (MCIEEM). Paul has over 18 years’ experience in ecology; including extensive experience in the preparation of Habitat Directive Assessments / Natura Impact Statements (i.e. Appropriate Assessment under Article 6(3) of the EU Habitats Directive). Paul carried out the technical review of this report.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 11 of 44

4. Existing Environment 4.1. Desktop Review

Knockakip Culvert carries the Ballyduff stream under the N21 road from Castleisland to Abbeyfeale. The Ballyduff stream is a first order stream that originates from Knockakip Hill within the Stack’s Mountain range.

The Ballyduff stream flows for approximately 6km in a north-east direction where it joins the Owveg river. The Owveg River is a tributary of the River Feale. The River Owveg-Feale confluence is located approximately 13km downstream of Knockakip Culvert.

The Ballyduff stream and the Owveg and Feale rivers are categorised as ‘Good’ status under the Water Framework Directive (WFD).

IFI’s Water Framework Directive monitoring of the River Feale and River Owveg have recorded the following species; salmon, brown trout, sea trout, European eel, lamprey sp., and minnow6. O’Connor (2006) has also conducted surveys for juvenile lamprey in the Feale catchment. River/brook lamprey were confirmed from the Owveg catchment. Sea lamprey were only recorded in the downstream reaches of the River Feale and were not recorded in the Owveg catchment. During consultation IFI commented that there is very little channel available upstream of the culvert and it is unlikely that it is fish bearing.

Otter spraints was recorded on the Ballyduff Stream approximately 400m downstream of Knockakip Culvert during the Otter Survey of Ireland (Chapman & Chapman, 1982). It was noted that the stream was small with good cover, however that few aquatic prey items were likely to be available for otter. There are no road kill records for otter in the vicinity of the culvert on the Road Kill Survey 2020 database7. 4.2. Site Visit

Knockakip culvert carries the N21 over the Ballyduff stream. The culvert is located in a rural setting. A small area of broadleaved woodland, which boarders a conifer plantation, is located immediately upstream of the culvert. The broadleaved component is dominated by willow Salix spp. with an understorey of ivy Hedera hibernica, bramble Rubus fructicosus and ferns (Polypodiopsida). A maintenance access track is present upstream of the culvert on the left-hand side, which is lined with bramble, willowherb Epilobium sp. and gorse Ulex sp.. The channel substrate upstream of the culvert was gravel, sand and cobble (in order of dominance).

Downstream of the structure, a significant drop of approximately 1m to the riverbed is present. This drop is a significant barrier to fish passage.

On the left bank Japanese knotweed Reynoutia japonica was recorded. The area of the Japanese knotweed was approximately 5m x 8m in size. Both old stems and new growth was noted. Downstream of the Japanese knotweed, the river bank was dominated by ivy, ferns, herb-robert Geranium robertianum, montbretia and a large Sycamore tree. The vegetation of the right bank downstream of the culvert consisted of herb-robert, ferns, bramble, grasses, rushes and willow. The channel substrate upstream and downstream of the culvert was cobble, gravel and sand (in order of dominance). Mosses were the dominant instream vegetation.

A small stream or spring was present on the right bank, approximately 5m downstream of the culvert.

Otter spraints were present on the downstream side of the culvert. One sprainting site was recorded with 2 spraints present; 1 old and 1 fresh spraint. No otter holts were recorded in the vicinity of the culvert.

6 IFI Interactive GIS Map Viewer - https://ifigis.maps.arcgis.com/apps/webappviewer/index.html?id=9a31fedb077c4fb2991184842b7ef025 7 2020 Road Kill Survey - http://www.biology.ie/mapv.php?m=npws

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 12 of 44

The culvert does not have roosting potential for bats and no bird nesting activity was recorded within the vicinity of the structure.

Plate 4-1 Upstream of Knockakip culvert.

Plate 4-2 Downstream of Knockakip culvert.

Plate 4-3 Japanese knotweed (new and old growth) downstream of culvert.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 13 of 44

Plate 4-4 Fresh otter spraint

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 14 of 44

5. Screening for Appropriate Assessment

5.1. Connectivity of Proposed Project to European Sites

The ‘zone of influence’ (ZoI) for a project is the area over which ecological features may be subject to significant effects as a result of the proposed project and associated activities. This is likely to extend beyond the project site, for example where there are ecological or hydrological links beyond the site boundaries. The zone of influence will vary for different ecological features depending on their sensitivity to an environmental change (CIEEM, 2019).

A distance of 15km is recommended in the case of plans, as a potential zone of influence and this distance is derived from UK guidance (Scott Wilson et al., 2006). However, for projects the distance could be much less, and in some cases less than 100m. National Parks and Wildlife Service guidance8 advises that this must be evaluated on a case-by-case basis with reference to the nature, size and location of the project, the sensitivities of the ecological receptors, and the potential for in-combination effects.

Thus, given the nature, scale and extent of the proposed project, the potential zone of influence will consider European sites with regard to the location of a European site, the QIs of the site and their potential mobility outside that European site, the Cause-Pathway-Effect model and potential environment effects of the proposed project.

5.1.1. Special Areas of Conservation

Knockakip Culvert does not lie within a Special Area of Conservation (SAC).

There is one SAC within 15km of the proposed project; Lower River Shannon SAC (002165). The proposed project is hydrologically connected to the SAC, as its upper boundary lies approximately 2.6km d/s of the culvert on the Ballyduff stream. The Lower River Shannon SAC is a very large site, which is designated for a diverse range of habitats and species, not all of which are relevant to Knockakip Culvert and the Ballyduff stream. Due the surface water connectivity between the proposed project and the SAC, the Lower River Shannon SAC falls within the potential zone of influence of the proposed project.

5.1.2. Special Protection Areas

Knockakip Culvert does lie with a Special Protection Area (SPA); Stack’s to Mullaghareirk Mountains, West Limerick Hills and Mount Eagle SPA (004161). The SPA is designated for Hen Harrier Circus cyaneus.

The proposed project on the N21 will not result in loss or disturbance of supporting habitat regarding nesting sites and hunting ground for Hen Harrier, which is typically open bog, moorland, young conifer plantation and hill farmland (NPWS, 2015). Thus, given the nature and extent of the proposed works and the location of the structure on the N21, likely significant effects to the SPA are not anticipated. Thus, likely significant effects are not anticipated as a result of the proposed project and thus, this SPA is not considered further in this assessment.

8 DoEHLG (2009). Appropriate Assessment of Plans and Projects in Ireland. Guidance for Planning Authorities. Department of Environment, Heritage and Local Government, Dublin, Ireland.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 15 of 44

Legend Knockakip Bridge

15km Buffer

Hydrological Connectivity

Special Area of Conservation Blackwater River (Cork/ Waterford) SAC Lower River Shannon SAC

Client: Transport Infrastructure Ireland

Project: Munster Bridges Term Maintenance Title: SACs within ZoI of Knockakip Bridge Drawn: Checked: Authorised: EN NS PO'D Date: Date: 29/05/2020 Date: 29/05/2020 29/05/2020

Drawing No: 5-1 Rev: 1.0

Ordnance Survey Ireland Licence No. AR 0082517 © Ordnance Survey Ireland and Government of Ireland Legend Knockakip Bridge

15km Buffer

Special Protection Area Stack's to Mullaghareirk Mountains, West Limerick Hills and Mount Eagle SPA

Client: Transport Infrastructure Ireland

Project: Munster Bridges Term Maintenance Title: SPAs within ZoI of Knockakip Bridge Drawn: Checked: Authorised: EN NS PO'D Date: Date: 29/05/2020 Date: 29/05/2020 29/05/2020

Drawing No: 5-2 Rev: 1.0

Ordnance Survey Ireland Licence No. AR 0082517 © Ordnance Survey Ireland and Government of Ireland

5.2. Brief Description of European sites

5.2.1. Lower River Shannon SAC (002165)

NPWS (2013) site synopsis describes the site as follows: -

“This very large site stretches along the Shannon valley from Killaloe in Co. Clare to Loop Head/ Kerry Head, a distance of some 120 km. The site thus encompasses the Shannon, Feale, Mulkear and Fergus estuaries, the freshwater lower reaches of the River Shannon (between Killaloe and Limerick), the freshwater stretches of much of the Feale and Mulkear catchments and the marine area between Loop Head and Kerry Head. Rivers within the sub-catchment of the Feale include the Galey, Smearlagh, Oolagh, Allaughaun, Owveg, Clydagh, Caher, Breanagh and Glenacarney. Rivers within the sub-catchment of the Mulkear include the Killeenagarriff, Annagh, Newport, the Dead River, the Bilboa, Glashacloonaraveela, Gortnageragh and Cahernahallia.

Freshwater rivers have been included in the site, most notably the Feale and Mulkear catchments, the Shannon from Killaloe to Limerick (along with some of its tributaries, including a short stretch of the Kilmastulla River), the Fergus up as far as Ennis, and the Cloon River. These systems are very different in character: the Shannon is broad, generally slow flowing and naturally eutrophic; the Fergus is smaller and alkaline; while the narrow, fast flowing Cloon is acid in nature. The Feale and Mulkear catchments exhibit all the aspects of a river from source to mouth. Semi-natural habitats, such as wet grassland, wet woodland and marsh occur by the rivers, but improved grassland is the most common habitat type. One grassland type of particular conservation significance, Molinia meadows, occurs in several parts of the site and the examples at Worldsend on the River Shannon are especially noteworthy. Here are found areas of wet meadow dominated by rushes (Juncus spp.) and sedges (Carex spp.), and supporting a diverse and species-rich vegetation, including such uncommon species as Blue-eyed Grass (Sisyrinchium bermudiana) and Pale Sedge (C. pallescens). Floating river vegetation characterised by species of water-crowfoot (Ranunculus spp.), pondweeds (Potamogeton spp.) and the moss Fontinalius antipyretica are present throughout the major river systems within the site. The rivers contain an interesting bryoflora with Schistidium alpicola var. alpicola recorded from in- stream boulders on the Bilboa, new to Co. Limerick.

Five species of fish listed on Annex II of the E.U. Habitats Directive are found within the site. These are Sea Lamprey (Petromyzon marinus), Brook Lamprey (Lampetra planeri), River Lamprey (Lampetra fluviatilis), Twaite Shad (Allosa fallax fallax) and Salmon (Salmo salar). The three lampreys and Salmon have all been observed spawning in the lower Shannon or its tributaries. The Fergus is important in its lower reaches for spring salmon, while the Mulkear catchment excels as a grilse fishery, though spring fish are caught on the actual Mulkear River. The Feale is important for both types. Twaite Shad is not thought to spawn within the site. There are few other river systems in Ireland which contain all three species of lamprey. Two additional fish species of note, listed in the Irish Red Data Book, also occur, namely Smelt (Osmerus eperlanus) and Pollan (Coregonus autumnalis pollan). Only the former has been observed spawning in the Shannon.

5.2.1.1. Features of Interest

Due to the size and geographic range of the Lower River Shannon SAC, not all qualifying interests of the SAC are within the zone of influence (ZoI) of the proposed works. Table 5-1 below outlines the qualifying interests of the SAC that are within the ZoI of the proposed project on the Ballyduff stream, Co. Kerry.

Thus, the qualifying interests of the SAC that are within the ZoI of the proposed project are: -

• Water courses of plain to montane levels with the Ranunculion fluitantis and Callitricho-Batrachion vegetation [3260]

• Margaritifera margaritifera (Freshwater Pearl Mussel) [1029]

• Lampetra planeri (Brook Lamprey) [1096]

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 18 of 44

• Lampetra fluviatilis (River Lamprey) [1099]

• Salmo salar (Salmon) [1106]

• Lutra lutra (Otter) [1355]

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 19 of 44

Table 5-1 - Qualifying interests of the SAC within the ZoI of the proposed project.

Within Zone of Qualifying Interest Location Influence Sandbanks which are slightly covered by sea water all the Coastal habitats are restricted to the Shannon estuary and the estuary of the rivers discharging No time [1110] to it, such as the River Feale estuary. These are located a significant distance downstream of Estuaries [1130] the proposed project and given the nature, scale and extent of the works, these habitats are not anticipated to be directly or indirectly impacted by the proposed project. Mudflats and sandflats not covered by seawater at low tide [1140] Coastal lagoons [1150] Large shallow inlets and bays [1160] Reefs [1170] Perennial vegetation of stony banks [1220] Vegetated sea cliffs of the Atlantic and Baltic coasts [1230] Salicornia and other annuals colonising mud and sand [1310] Atlantic salt meadows (Glauco-Puccinellietalia maritimae) [1330] Mediterranean salt meadows (Juncetalia maritimi) [1410] Water courses of plain to montane levels with the This habitat is not present in the immediate vicinity of Knockakip culvert. Floating river Yes Ranunculion fluitantis and Callitricho-Batrachion vegetation may occur in both upland and lowland depositing rivers. Therefore, this habitat vegetation [3260] could be present in the Ballyduff stream and Owveg river. Molinia meadows on calcareous, peaty or clayey-silt-laden Molina meadows of the SAC are predominantly present in the vicinity of the River Shannon, No soils (Molinion caeruleae) [6410] Co. Limerick. The habitats in the vicinity of Knockakip culvert are scrub, conifer plantations and rank grassland with rushes. Alluvial forests with Alnus glutinosa and Fraxinus Alluvial forests are not present in the vicinity of Knockakip culvert. No excelsior (Alno-Padion, Alnion incanae, Salicion albae) The habitats in the vicinity of Knockakip culvert are scrub, conifer plantations and rank [91E0] grassland with rushes.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 20 of 44

Within Zone of Qualifying Interest Location Influence Petromyzon marinus (Sea Lamprey) [1095] Barriers to sea lamprey are present in the River Feale9, therefore they are not anticipated to be No present in the immediate vicinity of the works. Lampetra planeri (Brook Lamprey) [1096] Lamprey sp. were recorded by IFI in the Rivers Feale and Owveg. Therefore, it is possible they Yes Lampetra fluviatilis (River Lamprey) [1099] are present in the watercourses downstream of Knockakip culvert.

Salmo salar (Salmon) [1106] Atlantic Salmon have been recorded by IFI in the Rivers Feale and Owveg. Therefore, it is Yes likely they are present in the Ballyduff stream and/ or the Owveg river downstream of Knockakip culvert. Tursiops truncatus (Common Bottlenose Dolphin) [1349] Common dolphin is a marine species. Given the nature and extent of the works and the No significant distance downstream, direct or indirect impacts resulting from the proposed works are not anticipated. Lutra lutra (Otter) [1355] Otter are present along many lakes, rivers and streams in Ireland. Otter activity signs were Yes recorded at Knockakip culvert during the site visit. Therefore, otter are likely to be present on the Ballyduff stream and Owveg River.

9 Lower River Shannon SAC https://www.npws.ie/sites/default/files/protected-sites/conservation_objectives/CO002165.pdf

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 21 of 44

5.2.1.2. Conservation Objectives

The conservation objectives of the qualifying interests within the ZoI of the proposed works are broadly summarised below: -

• To maintain the favourable conservation condition of Water courses of plain to montane levels with the Ranunculion fluitantis and Callitricho-Batrachion vegetation [3260] in the Lower River Shannon SAC.

• To restore the favourable conservation condition of Freshwater Pearl Mussel in the Lower River Shannon SAC.

• To maintain the favourable conservation condition of Brook Lamprey in the Lower River Shannon SAC.

• To maintain the favourable conservation condition of River Lamprey in the Lower River Shannon SAC.

• To restore the favourable conservation condition of Salmon in the Lower River Shannon SAC.

• To restore the favourable conservation condition of Otter in the Lower River Shannon SAC.

5.2.1.3. Potential Threats to the Lower River Shannon SAC

The site synopsis for the Lower River Shannon SAC describes the land use and management within the site as follows: -

“There is a wide range of land uses within the site. The most common use of the terrestrial parts is grazing by cattle, and some areas have been damaged through over-grazing and poaching. Much of the land adjacent to the rivers and estuaries has been improved or reclaimed and is protected by embankments (especially along the Fergus estuary). Further, reclamation continues to pose a threat, as do flood relief works (e.g. dredging of rivers). Gravel extraction poses a major threat on the Feale.

In the past, cord-grass (Spartina sp.) was planted to assist in land reclamation. This has spread widely and may oust less vigorous colonisers of mud and may also reduce the area of mudflat available to feeding birds.

Domestic and industrial wastes are discharged into the Shannon, but water quality is generally satisfactory, except in the upper estuary where it reflects the sewage load from Limerick City. Analyses for trace metals suggest a relatively clean estuary with no influences of industrial discharges apparent. Further industrial development along the Shannon and water polluting operations are potential threats.

Fishing is a main tourist attraction on the Shannon and there are a large number of angler associations, some with a number of beats. Fishing stands and styles have been erected in places. The River Feale is a designated Salmonid Water under the E.U. Freshwater Fish Directive. Other uses of the site include commercial angling, oyster farming, boating (including dolphin-watching trips) and shooting. Some of these may pose threats to the birds and dolphins through disturbance. Specific threats to the dolphins include underwater acoustic disturbance, entanglement in fishing gear and collisions with fast moving craft.”

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 22 of 44

6. Appropriate Assessment 6.1. Introduction

This section of the report assesses the European site in more detail and examines where likely significant effects may arise. Where these effects are identified that may affect the integrity of the SAC, avoidance and mitigation measures are proposed to offset these effects. These are discussed below in the following sections. 6.2. Impact Evaluation

6.2.1. ‘Do Nothing’ Impact

In the case of the proposed project the ‘do nothing’ approach would be not to repair the existing culvert and not install the concrete invert to its base. In the absence of the proposed project, Knockakip culvert will continue to convey flows under the N21. As the existing culvert is experiencing corrosion, in the absence of repair works, this corrosion will continue and may ultimately result in structural failure of the culvert.

The existing culvert may present an artificial barrier to fish migration, however the length of channel upstream of the culvert is relatively short. During consultation IFI commented that there is very little channel available upstream of the culvert and it is unlikely that it is fish bearing. The ‘do nothing’ approach would result in the status of the culvert regarding fish passage remaining unchanged.

Knockakip culvert is located ca. 2.6km upstream of the Lower River Shannon SAC. Otter from the SAC could travel upstream and travel through the culvert. Given the nature of Knockakip culvert, the sides of the culvert are dry at normal flows. Therefore, otter can freely pass through the culvert during normal flows. It is possible that during high flows, where the sides of the culvert are no longer dry, otter may not be able to travel through the culvert and may access the N22 road as a result. The proposed project is for the installation of a concrete invert at Knockakip culvert. The hydraulic assessment demonstrates that the proposed project will not significantly affect the hydrological regime of the watercourse, nor the capacity of the culvert. Therefore, the installation of the concrete invert will not change the conditions under which Knockakip culvert is passable to otter.

6.2.2. Potential impacts during the works

In summary and as outlined in Section 5 above, the features of interest that are within the zone of influence of the proposed project are: -

• Water courses of plain to montane levels with the Ranunculion fluitantis and Callitricho-Batrachion vegetation [3260]

• Margaritifera margaritifera (Freshwater Pearl Mussel) [1029]

• Lampetra planeri (Brook Lamprey) [1096]

• Lampetra fluviatilis (River Lamprey) [1099]

• Salmo salar (Salmon) [1106]

• Lutra lutra (Otter) [1355]

The attributes and targets for the conservation objectives of the qualifying interests within the zone of influence of the proposed project listed above are set out in Table 6-1. The proposed project is not located within th catchment.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 23 of 44

6.2.2.1. Direct impacts

As the proposed project is located approximately 2.6km upstream of the SAC boundary, given the nature and extent of the proposed project, direct impacts to the qualifying interests of the Lower Shannon River SAC will not occur during the construction phase of the proposed project.

6.2.2.2. Indirect impacts

The site of the proposed project is hydrologically linked to the SAC via surface water pathways. The mobilisation of silts, nutrients, hydrocarbons and concrete materials, could potentially occur during the works. Spillages of products in their liquid state, e.g. primer products, could also potentially occur during the works.

The release and entry of these materials to the Ballyduff stream has the potential to result in localised impacts of sedimentation and increased algal and macrophyte growth in the watercourses downstream, which in turn could impact on the aquatic biota that the river supports and hence, its ecological status.

Qualifying interests such as salmon, lamprey and freshwater pearl mussel may be impacted by the release of sediments as they are sensitive to changes in water quality. Mobilisation of sediments may affect lamprey and salmon spawning beds due to sedimentation of river substrates and the increase of fine sediments to spawning habitats. Fish spawning habitat is generally near suitable freshwater pearl mussel habitat. Freshwater pearl mussel requires very good water quality with cobble and gravel substrate containing very little fine sediment, and algal and plant growth. Floating river vegetation is also sensitive to siltation and changes in substrate composition as this affects the rooted structure of the plants and their ability to photosynthesise.

The potential impacts to species such as salmon and lamprey may also indirectly affect otter and the availability of a food source (fish biomass). Salmon and lamprey are important food sources for otter and a decline in these would have an indirect negative impact on otter.

The potential entry of polluting materials such as hydrocarbons and concrete material into the Ballyduff stream would have a negative impact on all aquatic qualifying interests of the SAC.

Due to the presence of site staff at the culvert for 2 weeks, i.e. the duration of the works, there is potential for temporary disturbance of otter that may travel upstream from the SAC. However, given the scale, extent and duration of the works, this impact is not anticipated to be significant. The dam setup will not cause fragmentation of the riparian corridor and thus, otter will be free to travel through the culvert. However, it is acknowledged that this will most likely be when the work crew is not present at the site, i.e. at the end of each working day until the following morning when works re-commence and at weekends.

Japanese knotweed is present on the downstream left riverbank. It is important that avoidance measures and biosecurity measures are implemented during the works to ensure that the area of Japanese knotweed on the downstream left bank is not disturbed. It is important to note that the area of Japanese knotweed is located on the riverbank, and slightly set back from the channel edge. Therefore, the rhizomes of the Japanese knotweed plants are contained within the soils of the riverbank and not within the instream working area.

6.2.3. Potential impacts post completion of the works

As shown by the hydraulic impact assessment, the proposed repair works to the existing culvert will not impact on the hydrological and hydraulic regime of the watercourse. The installation of the concrete invert at Knockakip Culvert will not alter the conditions under which the culvert is passable to otter, nor will it alter the status of the culvert regarding fish passage. The operation of the proposed project will not generate further emissions to the watercourse.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 24 of 44

Table 6-1 - Site-specific conservation objectives for QIs within ZoI of the proposed project. Qualifying Interest Attribute Measure Target Water courses of plain to montane Habitat area Kilometres Area stable or increasing, subject to natural processes. levels with the Ranunculion fluitantis and Callitricho-Batrachion Habitat distribution Occurrence No decline, subject to natural processes. vegetation Hydrological regime: river flow Metres per second Maintain appropriate hydrological regime. Hydrological regime: tidal Daily water level fluctuations - Maintain natural tidal regime. influence metres Hydrological regime: Metres per second Maintain appropriate freshwater seepage regimes. freshwater seepages Substratum composition: Millimetres The substratum should be dominated by the particle size ranges, particle size range. appropriate to the habitat sub‐type (frequently sands, gravels and cobbles). Water quality: nutrients Milligrammes per litre The concentration of nutrients in the water column should be sufficiently low to prevent changes in species composition or habitat condition. Vegetation composition: Occurrence Typical species of the relevant habitat sub-type should be present typical species and in good condition. Floodplain connectivity: area Area The area of active floodplain at and upstream of the habitat should be maintained. Riparian habitat Area The area of riparian woodland at and upstream of the bryophyte‐rich sub type should be maintained.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 25 of 44

Qualifying Interest Attribute Measure Target Water quality: Ecological quality ratio (EQR) Restore water quality - macroinvertebrates: EQR greater than 0.90 macroinvertebrate and (Q4-5 or Q5); phytobenthos: EQR greater than 0.93. phytobenthos (diatoms) Substratum quality: Percentage Restore substratum quality - filamentous algae: absent or trace (less filamentous algae than 5%); macrophytes: absent or trace (less than 5%). (macroalgae); macrophytes (rooted higher plants) Substratum quality: sediment Occurrence Restore substratum quality - stable cobble and gravel substrate with very little fine material; no artificially elevated levels of fine sediment. Substratum quality: oxygen Redox potential Restore to no more than 20% decline from water column to 5cm availability depth in substrate. Hydrological regime: flow Metres per second Restore appropriate hydrological regime. variability Host fish Number Maintain sufficient juvenile salmonids to host glochidial larvae. Brook and River lamprey Distribution Percentage of river accessible Access to all water courses down to first order streams. Population structure of Number of age/size groups At least three age/size groups of brook/river lamprey present. juveniles Juvenile density in fine Juveniles/m² Mean catchment juvenile density of brook/river lamprey at least 2/m². sediment Extent and distribution of m² and occurrence No decline in extent and distribution of spawning beds. spawning habitat Availability of juvenile habitat Number of positive sites in 2nd More than 50% of sample sites positive. order channels (and greater), downstream of spawning areas Salmon Distribution: extent of Percentage of river accessible 100% of river channels down to second order accessible from anadromy estuary. Adult spawning fish Number Conservation limit (CL) for each system consistently exceeded. Salmon fry abundance Number of fry/5 minutes Maintain or exceed 0+ fry mean catchment-wide abundance electrofishing threshold value. Currently set at 17 salmon fry/5 minutes sampling. Out-migrating smolt Number No significant decline abundance

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 26 of 44

Qualifying Interest Attribute Measure Target Number and distribution of Number and occurrence No decline in number and distribution of spawning redds due to redds anthropogenic causes. Water quality EPA Q value At least Q4 at all sites sampled by EPA Otter Distribution Percentage positive survey No significant decline sites Extent of terrestrial habitat Hectares No significant decline. Area mapped and calculated as 596.8ha above high water mark (HWM); 958.9ha along river banks/ around ponds. Extent of marine habitat Hectares No significant decline. Area mapped and calculated as 4,461.6ha. Extent of freshwater (river) Kilometres No significant decline. Length mapped and calculated as 500.1km. habitat Extent of freshwater Hectares No significant decline. Area mapped and calculated as 125.6ha. (lake/lagoon) habitat Couching sites and holts Number No significant decline. Fish biomass available Kilograms No significant decline. Barriers to connectivity Number No significant increase.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 27 of 44

6.2.4. In-combination Impacts

In-combination impacts with the following plans and projects were considered during the preparation of this report. The search of Kerry County Council was based on a map-based search.

Kerry County Development Plan sets out strategies and objectives to provide sustainable development within Co. Galway. The Plan contains several natural heritage and biodiversity policies, which includes the protection of international and national designated sites, protect existing green infrastructure and provide additional green infrastructure, and the eradication of invasive species. A Natura Impact Report was prepared for the Plan, which assessed the Plan regarding its potential to adversely affect the integrity of European sites. The findings of the AA were integrated into the Plan, ensuring that potential adverse effects have been and will be avoided, reduced or offset. Thus, an AA determination was made by Kerry County Council that the Plan is not foreseen to have any adverse effects on the ecological integrity of any European Site. The current NIS is being prepared to ensure that the proposed project will not have an adverse impact on the integrity of European sites. Given the elements outlined above, the County Development Plan is not anticipated to act in-combination with the proposed project.

Projects that have been granted planning permission in the vicinity of Knockakip culvert, Ballyduff stream and the Owveg River include retention of existing developments, typically extensions to domestic dwellings, or the construction of new domestic dwellings or extensions to such dwellings. Regarding potential impacts to water quality, these projects will have to comply with the EPA’s Code of Practice for Wastewater Treatment Systems for Single Houses (EPA, 2009; 2018).

The 3 Groupings of culverts proposed for repair works in the Munster region (Table 1-1) are in the WFD catchments Tralee Bay – Feale, Suir, and Laune – Maine – Dingle Bay respectively. The proposed project is in the Tralee Bay – Feale catchment that drains to the Lower River Shannon SAC. The culverts in Group 2 and Group 3 are in separate WFD catchments to Group 1 and these WFD catchments do not drain to the Lower River Shannon SAC. Therefore, in-combination effects between the proposed project and other proposed culvert projects will not occur.

The OPW has an arterial drainage scheme in the Feale catchment, however the extent of the drainage scheme is in the lower section of the Feale catchment. The upper extent of the drainage scheme on the River Feale is Listowel town, which is located approximately 20km downstream of Abbeyfeale. Thus, in-combination effects with the OPW drainage programme of the Feale scheme and the proposed project are not anticipated.

Farmers and landowners may also undertake general agricultural operations in areas adjacent to the proposed project and along the river, which could potentially give rise to impacts of a similar nature to those arising from the proposed project. This could potentially result in additional an increased risk to water quality. Many agricultural operations are periodic, not continuous in nature, and qualify as a Notifiable Action that requires consultation with National Parks and Wildlife Service in advance of the works e.g. reclamation, infilling or land drainage within 30m of the river, removal of trees or any aquatic vegetation within 30m of the river, and harvesting or burning of reed or willow (NPWS, 2018). Agricultural operations must also comply with the EC (Environmental Impact Assessment) (Agriculture) Regulations 2011 and amendment 2017 S.I. No. 456/2011 and 407/2017 in relation to activities covered by the regulations;

• restructuring of rural land holdings,

• commencing use of uncultivated land or semi-natural areas for intensive,

• land drainage works on lands used for agriculture.

A Natura Impact Statement is required under Regulation 9 if it is likely to have a significant effect on a European designated site. The drainage or reclamation of wetlands is controlled under the Planning and Development (Amendment) (No. 2) Regulations 2011 and the European Communities (Amendment to Planning and Development) Regulations 2011. Therefore, the in-combination effects of agricultural operations and the proposed project are not likely to be significant.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 28 of 44

6.3. Mitigation Measures

This section describes the mitigation measures required to ensure there are no residual effects on the integrity of the Lower River Shannon SAC. Table 7-1 summaries how these mitigation measures will result in no adverse effect on the integrity of European sites.

6.3.1. General Measures

1. An Ecological Clerk of Works (ECoW) will be appointed and will supervise all aspects of the critical works on site, in particular initial site set up, dam/ silt fence installation, pouring of concrete and use of chemicals. The ECoW will be a suitably qualified and experienced ecologist, which will be appointed by TII. The ECoW will ensure compliance of mitigation measures on site and liaise with IFI and NPWS staff where required.

2. A pre-construction survey for otter will be carried out upstream and downstream of the culvert within one month of commencement of works on site.

3. In accordance with the NRA guidelines, the following guidelines shall be followed: -

• No physical damage or disturbance to an otter holt shall occur.

• No works shall be undertaken within 150m of any holt at which breeding females or cubs are present.

• No wheeled or tracked vehicles should be used within 20m of an active non-breeding holt.

4. If an otter holt is recorded during the pre-construction survey and is likely to be damaged or disturbed by the proposed works, a derogation licence will be applied for from NPWS. Any further mitigation measures required by the derogation licence shall be implemented.

5. The proposed works shall be carried out during July 1st to September 30th inclusive.

6. The site manager shall monitor the 10-day weather forecast. The works shall not take place during high river flows or prior to forecasts of heavy rainfall. High river flows constitute river flows that will top the dams or will be in excess of pumping capabilities. If such conditions are forecast, the works area shall be secured and all materials, including the elements of the dam system (sandbags, silt fences, pumps and associated pipes and silt socks) will removed from the works area and riverbanks. Upon subsidence of flows, the dam system shall be re-instated upstream and downstream of the culvert and the works area de-watered before works can re-commence. This shall be supervised by the ECoW.

7. A Temporary Traffic Management zone will be created within the road corridor. This shall be used for parking and deliveries of materials.

8. All site staff will be informed of best practice methodologies to be employed on site via the dissemination of a tool-box talk. This shall include the requirement for protection of aquatic habitats, the sensitivity of the Lower River Shannon SAC and the presence of Japanese knotweed immediately downstream of the culvert.

9. Works will be carried out during day-time hours, except in the event of an emergency.

10. Any chemical, fuel and oil stores will be located on an impervious base within a secured bund with a storage capacity 110% of the stored volume.

11. Biodegradable oils and fuels will only be used.

12. Drip trays will be placed underneath any standing machinery to prevent pollution by oil/fuel leaks. Where practicable, refuelling of vehicles and machinery will be carried out on an impermeable surface in one designated area well away from any watercourse or drainage (at least 20m).

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 29 of 44

13. Emergency spill kits will be available on site and staff will be trained in their use. A reporting system will be established on site to record accidents and/or spillages on site and the resultant action taken to remedy the incident.

14. Operators will check all equipment, machinery and vehicles on a daily basis before starting work to confirm the absence of leakages. Any leakages should be reported immediately and addressed.

15. Daily checks will be carried out and records kept on a weekly basis and any items that have been repaired/replaced/rejected noted and recorded. Any items of plant machinery found to be defective will be removed from site immediately or positioned in a place of safety until such time that it can be removed. All items of plant will be checked prior to use before each shift for signs of wear/damage.

6.3.2. Specific Measures

16. A dry working area will be achieved by setting up a dam system. There shall be three dams in total; one upstream of the culvert and two downstream of the culvert. Each dam will consist of tightly packed sandbags that are filled with clean sand. The sandbags will be double lined and individually sealed. Only sealed sandbags will be used to create the dams. No clay or soil material is permitted to ‘seal’ the sandbag dams. If needed, a geotextile membrane will be used to enhance the seal of the dams.

17. The integrity of the sandbag dams must be monitored to ensure that the works area is isolated from the live channel. This shall be monitored by the site manager twice daily; in the morning before the commencement of works and at the end of the day prior to leaving site.

18. Two silt fences shall be installed between the two sandbag dams situated downstream of the culvert. Any water pumped into this dammed area shall be in advance of the silt fences. Thus, all water pumped from the work area must pass through both silt fences before re-entering the river.

19. The pipe used to flume flows through the works area will be fitted with a filter to ensure no fish enter the pipe. The outfall of the pipe will be fitted with a silt sock. The silt sock shall be changed and/ or cleaned at regular intervals. The interval for replacing the silt sock will be dependent on the turbidity of the watercourse and therefore this shall be monitored by the site manager twice daily at a minimum; in the morning before the commencement of works and at the end of the day prior to leaving site.

20. The temporary working platform, i.e. terram and 300m thick class 6F granular capping, must be clean and free of any foreign debris before being installed on the existing riverbed gravels.

21. There can be no entry of debris and / or waste material from the works area to the live channel. The debris must be collected within the dry work area, removed from the work area and disposed of appropriately off site at Conhor Construction tip in Ballincollig, Cork.

22. Powerwashing of the culvert will not involve any water abstraction from the river. Water will be brought to site in a bowser by the Contractor. Power washing can only take place when the sandbag dam system and silt fences are in place. The wash unit generator will be positioned on the road and the lance hose will run down the bank into the work area.

23. Any water arising in the work area, as a result of power washing or seepage through the upstream dam, will be pumped from the working area into the area between the two downstream dams in advance of the silt fences. The pump will be located on the temporary working platform and fitted with a drip tray. All associated pipes will be fitted with a silt sock and/ or de-watering bag.

24. Primer products shall be applied to surfaces in the morning of a workday. This is to ensure that the required 6-hour curing time can be achieved before leaving the site at the end of the day. Primer products shall not be applied to surfaces within 48 hours of a heavy rain forecast.

25. Only quantities of primer products required for use in that working day shall be available at the site. These shall be kept is a bunded container located at least 20m from the watercourse until required for use.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 30 of 44

26. The Shotcrete pump will be located on the road above the work area. The integrity of pump hoses must be checked prior to commencing works Pump hoses will be located within the dry work area to ensure no spillage of concrete to the live channel.

27. At no point will any equipment be washed out within the work area or adjacent to a watercourse.

28. Sandbag dam no. 3 and the silt fences shall be left in place until any sediment plume has dissipated.

29. The gravel area on which the temporary working platform was located will be loosened, as it may have been compacted during the works. This area will be reinstated with washed and clean gravel.

30. All material used on site, including the sandbags, silt fences, silt socks, de-watering bags and components of the temporary working platform, will be removed from site and disposed of at Conhor Construction tip in Ballincollig.

6.3.3. Biosecurity protocols

Japanese knotweed is present on the downstream side of Knockakip culvert. Facing downstream, Japanese knotweed is present on the left bank. The area is within 7m of the works area. Therefore, a 7m area will be fenced off, with the river side of the stand fenced-off along the edge of the watercourse. A tarpaulin sheet will be placed over the plant and tied down with rope, which will be attached to stone weights. Care will be taken not to break any parts of the Japanese stand while putting the tarpaulin sheet in place. This area will not be disturbed during the works. After the works, the tarpaulin must be inspected to make sure it is clean and free of any plant material before being removed from the site.

The stands of Japanese knotweed will be cordoned off and signage erected to denote that it is an area where no access is permitted. No access to this area will occur during the proposed project and this riverbank will not be used for the transport of sandbags or any other materials to and from the carriageway and culvert. All access hoses will come down the opposite bank, i.e. the right bank facing downstream.

A pre-construction invasive species survey will be conducted prior to the commencement of works on site. If any further invasive species are recorded, these shall be fenced off using a 7m buffer from the outermost edges of the invasive species plant(s).

Biosecurity protocols shall be implemented during the construction phase of the proposed project to prevent the introduction of invasive species listed on the third schedule of the EC (Birds and Natural Habitats) Regulations 2011 to site and the further spread of diseases.

1. All equipment intended to be used at the site shall be dry, clean and free from debris prior to being brought to site.

2. If drying out of equipment is not feasible, equipment should be either: -

i. power steam washed at a suitably high temperature or at least 65 degrees, or

ii. disinfected with an approved disinfectant, e.g. Virkon or an iodine-based product. It is important that the manufacturer’s instructions are followed and if required, the correct contact times are allowed for during the disinfection process. Items that are difficult to soak should be sprayed or wiped down with disinfectant.

3. During the duration of the proposed project, if equipment is removed off-site to be used elsewhere, the said equipment shall be cleaned and disinfected prior to being brought back to the works area of the proposed project.

4. Appropriate facilities shall be used for the containment, collection and disposal of material and/or water resulting from washing facilities of vehicles, equipment and personnel.

5. Importation of materials shall comply with Regulation 49 of the EC (Birds and Natural Habitats) Regulations 2011.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 31 of 44

7. Conclusions

This NIS provides the competent authority with supporting information to undertake the Appropriate Assessment in relation to the proposed project at Knockakip Culvert and its potential indirect impacts via surface water pathways on the Lower River Shannon SAC.

The NIS has examined the potential impacts of the proposed project on the integrity of the SAC, alone and in combination with other plans and projects, taking into account the site’s structure, function and conservation objectives. Where potential likely significant effects were identified, mitigation measures have been recommended to assist in offsetting these effects.

Following a comprehensive evaluation of the potential direct, indirect and cumulative impacts on the qualifying interests of the SAC, and the implementation of the proposed mitigation measures, it has been concluded by the authors of this report that there will be no residual impacts and the proposed project will not have an adverse effect on the integrity of the Lower River Shannon SAC.

To confirm this conclusion, the following checklist taken from DEHLG (2009) has been completed.

Table 7-1 Checklist of Site Integrity (DEHLG, 2009).

Does the project or plan have the potential to: - Y/N

Cause delays in progress towards achieving the N - Following mitigation, no significant adverse residual impacts conservation objectives of the sites? have been identified that will prevent achievement of the conservation objectives of Lower River Shannon SAC.

Interrupt progress towards achieving the N - Following mitigation, no significant adverse residual impacts conservation objectives of the sites? have been identified that will prevent achievement of the conservation objectives of the SAC.

Disrupt those factors that help to maintain the N - Potential adverse impacts identified during the screening favourable conditions of the site? process, including potential changes to water quality issues and pollution, can be avoided or mitigated against.

Interfere with the balance, distribution and density of N - Potential adverse impacts can be avoided by implementing a key species that are the indicators of the favourable range of measures to maintain water quality and thus protect the condition of the site? surface water dependent species and habitats of the SAC.

Cause changes to the vital defining aspects (e.g. N - Potential adverse impacts from sediment mobilisation and nutrient balance) that determine how the site pollution, which could impact upon ecosystem functioning, can functions as a habitat or ecosystem? be effectively mitigated.

Change the dynamics of the relationships (between, N - Potential adverse impacts relating to changes in water for example, soil and water or plants and animals) quality of the watercourses downstream of the works will not that define the structure and/or function of the site? occur as a result of the project and therefore will not impact on the functioning of the SAC.

Interfere with predicted or expected natural changes N - Potential adverse impacts from changes to the water quality to the site (such as water dynamics or chemical or physical and hydrological regime will not occur and therefore composition)? will not impact upon the functioning of the SAC.

Reduce the area of key habitats? N - There will be no loss of habitat as works will be conducted outside the European site boundary and there will be no changes to the water quality or physical and hydrological regime that could cause habitat loss in the future.

Reduce the population of key species? N - Disturbance impacts to species of the SAC will not occur due to the nature and extent of the proposed project and the physical distance between the proposed works and the SAC. Mitigation measures will ensure that the works will not cause a deterioration in water quality.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 32 of 44

Does the project or plan have the potential to: - Y/N

Change the balance between key species? N - Potential disturbance impacts to species of the SAC will not occur. Mitigation measures will ensure that the works will not cause a deterioration in water quality.

Reduce diversity of the site? N - There shall be no direct impacts to habitats and species of the SAC. The identified mitigation measures to protect water quality will ensure that the current diversity of the SAC is maintained.

Result in disturbance that could affect population N – There shall be no disturbance impacts to species of the SAC size or density or the balance between key species? and therefore, population size and density will not be reduced.

Result in fragmentation? N - The proposed works will not result in the fragmentation of habitats within the SAC or surrounding habitat.

Result in loss or reduction of key features? N – There shall be no loss or reduction of key features within the SAC.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 33 of 44

References

Bell, A.M., Baier, R., Kocher, B., Reifferscheid, G., Buchinger, S. and Ternes, T. (2020) Ecotoxicological characterization of emissions from steel coatings in contact with water. Water Research. 173, 2020, 115525. https://www.sciencedirect.com/science/article/pii/S0043135420300610. Chapman, P.J. and Chapman, L.L. (1982) Otter Survey of Ireland, 1980-81. The Vincent Wildlife Trust, London. CIEEM (2018). Guidelines for Ecological Impact Assessment in the UK and Ireland: Terrestrial, Freshwater, Coastal and Marine. Version 1.1. Chartered Institute of Ecology and Environmental Management, Winchester. Cooper, L. M. (2004). Guidelines for Cumulative Effects Assessment in SEA of Plans, EPMG Occasional Paper 04/LMC/CEA, Imperial College London. DoEHLG (2009). Appropriate Assessment of Plans and Projects in Ireland: Guidance for Planning Authorities. National Parks and Wildlife Service, Department of the Environment, Heritage and Local Government. Dublin. EPA (2009). Code of Practice; Wastewater Treatment Systems and Disposal Systems serving Single Houses (p.e. ≤10). Environmental Protection Agency, Co. Wexford, Ireland. EPA (2018). Code of Practice, Domestic Waste Water Treatment Systems (Population Equivalent ≤10) Draft 26 November 2018. Environmental Protection Agency, Ireland. European Commission (2001). Assessment of Plans and Projects significantly affecting Natura 2000 Sites: Methodological guidance on the provisions of Article 6(3) and (4) of the Habitats Directive 92/43/EEC. European Commission (2017). Managing Natura 2000 Sites: The Provisions of Article 6 of the ‘Habitats’ Directive 92/43/EEC. European Union Habitats Directive, (1992). Council Directives 92/43/EEC of 21 May 1992 on the conservation of natural habitats and of wild fauna and flora. IFI (2016) Guidance on Protection of Fisheries During Construction Works In and Adjacent to Waters. Inland Fisheries Ireland. Dublin, Ireland. Masters-Williams, H., Heap, A. & Kitts, H. (2001) C532 Control of water pollution from construction sites. Guidance for consultants and contractors. Construction Industry Research and Information Association. London, Great Britain. Murnane, E. (2002) SP156 Control of water pollution from construction sites – guide to good practice. Construction Industry Research and Information Association. London, Great Britain. NPWS (2013). Site Synopsis Lower River Shannon SAC Site Code 002165. Version date 16/12/2013, Revision 13. National Parks and Wildlife Service, Department of Arts, Heritage and the Gaeltacht. Dublin, Ireland. NPWS (2015). Site synopsis Stack’s to Mullaghareirk Mountains, West Limerick Hills and Mount Eagle SPA (Version date: 20/01/2015). Department of Arts, Heritage and the Gaeltacht. NPWS (2017). Standard Data Form Lower River Shannon SAC Site Code 002165. National Parks and Wildlife Service, Department of Arts, Heritage and the Gaeltacht. Dublin, Ireland. NRA (2009) Survey Guidelines for National Road Schemes. . Dublin, Ireland. O’Connor W. (2006) A baseline survey of juvenile lamprey populations in the River Feale catchment. Irish Wildlife Manuals, No. 22. National Parks and Wildlife Service, Department of Environment, Heritage and Local Government, Dublin, Ireland. Preene, M., Roberts, T.O.L & Powrie, W. (2016) C750 Groundwater control: design and practice. Construction Industry Research and Information Association. London, Great Britain. Scott Wilson and Levett-Therivel, (2006). Appropriate Assessment of Plans. Scott Wilson, Levett-Therivel Sustainability Consultants, Treweek Environmental Consultants and Land Use Consultants. Smith, G.F, O’Donoghue, P., O’Hora, K. & Delaney, E. (2011) Best Practice Guidance for Habitat Survey and Mapping. The Heritage Council. Kilkenny, Ireland.

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 34 of 44

Appendices

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 35 of 44

Appendix A. Design Detail

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 36 of 44

GENERAL NOTES 100 1. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE

2. ONLY WRITTEN DIMENSIONS SHALL BE USED. NO DIMENSIONS SHALL BE SCALED FROM THE DRAWINGS

3. ALL LEVELS ARE IN METRES AND ARE TO MALIN HEAD DATUM

4. ALL COORDINATES ARE IN METRES AND ARE TO IRISH TRANSVERSE MERCATOR Section 1-01 5. DRAWINGS ARE TO BE READ IN CONJUNCTION WITH THE SPECIFICATION

DRAWING NOTES 231.38

231.44

231.52 231.54 Section 1. FOR RIVER CROSS SECTIONS 1-01 TO 1-17, REFER

231.02 TO TOPOGRAPHICAL SURVEY DRAWINGS 231.64 10

231.74 1-02

231.67 0

231.83

231.67

231.88 231.56 231.86

231.54 231.40

231.96

232.01 To Abbeyfeale232.07 231.99 Section 1-03 232.14

232.02

232.16 231.61 231.85

232.05 A1

231.87 N21 232.25

232.31

232.36

232.40

232.11 Section 1-04

232.39

232.45 232.50

232.39 232.11

232.61

232.59 232.31

232.72

232.71

232.78

232.74 232.85 Flow

232.73

232.59

232.96

232.57 232.99 232.99

233.00 232.98

232.52 232.94

233.07 232.94

233.21

233.13 233.21 233.17 232.86

233.35

233.41

232.84 233.36

233.53

233.50 233.47 233.03

233.59 233.47

233.62 233.66

233.66 233.18

233.56

233.74

Section DO NOT SCALE Section KNOCKAKIP CULVERT 233.64 UNNAMED STREAM

Section 1-13 233.69

229.87 233.27 233.90

Top of Fence 228.45 Bottom of Fence (KY-N21-016.00) Water Level Date of survey=Friday, October 25, 2019 233.94 233.62 228.33228.62 228.37 228.40 228.61 228.70 233.88 1-12 233.87 233.34 228.34 234.07

228.37 228.34 234.06 Pipe Invert 232.83 228.22 231.14 Pipe Soffit 228.60 228.14 233.88 233.82 228.15 228.32 1-14 228.11 234.10 228.16 234.20 228.49 228.54 234.14 234.16 234.23 233.91 228.42 228.14 Water Level Date of survey=Friday, October 25, 2019 234.27 234.16 228.25

228.82 233.90 233.59 228.45 234.27 233.00 228.22 234.13 233.55 228.30 228.53 Top of Wall

229.91 234.29 234.07

229.53 229.00 234.15 234.40 234.39 233.55 228.42 234.13 Water Level Date of survey=Friday, October 25, 2019 234.41 234.05 233.65 234.48 Bottom of Fence Top of Fence

234.39 233.28 234.36 233.18 233.98 233.48 234.36 233.75 234.47 233.41

233.97

233.80 233.91 233.73 234.52 234.26

234.48

Top of Wall 234.65 233.82 Base of crash barrier Section 1-05 Top of crash barrier 233.39 Top of Fence 227.68 Bottom of Fence Circular Opening 227.24

230.79

1-15 Section 227.93 234.57 Pipe Soffit 234.61 Water Level 233.80 Date of survey=Friday, October 25, 2019 234.33 227.87 227.07 227.30 Pipe Invert 234.27 227.21 234.65 226.70 233.89 Water Level Date of survey=Friday, October 25, 2019 226.75 226.57 234.79 234.00 227.81 234.43 Pipe Invert 226.67 233.47 diam=0.11 226.41 Water Level 227.84 Date of survey=Friday, October 25, 2019 226.81 226.56 234.68 234.72 227.46 226.58

Base of crash barrier Top of crash barrier

233.23 Pipe Invert 226.55 diam=0.11 234.04 229.97 226.49 226.51 226.23 234.05 228.86 233.86 233.41 229.48 227.08

233.42

Section 1-11 234.84 226.47 226.29 234.82 227.98 228.31 Pipe Invert 226.87 226.33 234.63 diam=0.15

Bottom ofTop Fence of Fence 226.39 233.17 228.63 Water Level Pipe Invert 228.57 233.57 226.81 Date of survey=Friday, October 25, 2019 233.04 diam=0.37 Pipe Invert diam=0.1

234.92 234.90

227.91

234.01 234.32 234.99 235.01 231.61 234.98 Flow 234.79 234.14 231.26

235.07

235.12

231.32

234.41

235.20 235.16

235.35 234.63 235.28 235.25

235.06

235.35

235.34 234.51

235.22

235.46 1-10 Section 1-06

235.45 235.25

CO-ORDINATES 234.81

234.91

235.54

235.62

235.37 235.25 235.25 235.62

N = 614,681.253 235.64 Section

235.71 1-08 235.72

235.54 E = 503,466.106 234.97 Section 1-09

235.16

235.82

235.89

235.68

235.97 235.92 Section

235.38 UNNAMED STREAM 236.03 236.01 235.82 Section 1-07

236.09

235.41

236.08

235.33

235.93 235.58

236.16 236.14

236.29

236.01

235.98 236.23

236.26

236.35

236.02

236.19

236.14 235.72

236.54 236.45 236.47 235.62

236.20

236.25

235.95

236.56

236.23 236.39 N21

236.67

236.67

236.40

236.81

236.52 Castleisland 236.46

236.76 236.03 236.78

236.51

236.56

236.17 To

236.67

236.29 236.96 236.61

236.89

236.90

236.65

236.21

236.78

236.70

236.34 N21

236.70 236.49

ISSUED FOR REVIEW

© ORDNANCE SURVEY IRELAND LICENSE NR. to 0203.dwg AR 0082518. ORDNANCE SURVEY IRELAND & TRANSPORT INFRASTRUCTURE KNOCKAKIP CULVERT (KY-N21-016.00) GOVERNMENT OF IRELAND IRELAND (TII) REMEDIAL WORKS ATKINS NOT TO BE HELD LIABLE FOR THE USE EXISTING SITE LAYOUT PLAN OF THIS DATA ON ANY PROJECT OTHER THAN THE MUNSTER BRIDGES TERM MAINTENANCE CONTRACT NR.3 PROJECT AOS MG MJ 1:500 18/11/19 18/11/19 18/11/19 A REVIEW COMMENTS INCORPORATED AOS 05/20 MJ MJ MUNSTER BRIDGES TERM May 20, 2020 - 9:09am - ISSUED FOR REVIEW AOS 11/19 MG MJ MAINTENANCE CONTRACT NR.3 Date: File: 5162555-HTR-DR-0200 P 5162555 / HTR / DR / 0200 A

V:\5162555\6 Dwgs-Graphics\61 AutoCad\5162555-HTR-DR-0200 to 0203.dwg 233.14 233.18 GENERAL NOTES 100

233.21 1. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE

233.13 233.27 233.21 233.17 233.17 232.86 2. ONLY WRITTEN DIMENSIONS SHALL BE USED. NO DIMENSIONS SHALL BE SCALED FROM THE DRAWINGS

233.35 3. ALL LEVELS ARE IN METRES AND ARE TO MALIN 233.34 HEAD DATUM 232.62 233.41

233.41 233.44 4. ALL COORDINATES ARE IN METRES AND ARE TO IRISH TRANSVERSE MERCATOR 232.84 233.36 5. DRAWINGS ARE TO BE READ IN CONJUNCTION WITH 233.31 THE SPECIFICATION 233.53 232.41 233.42 233.55

233.50 233.47 233.59 233.03 231.38 233.59 233.47

233.68

10 EXISTING FENCING 232.26 233.71 233.62 233.66 233.69 233.33 233.66

0 233.78 C 233.18 233.56

0203 233.74

233.72 232.06

233.64 229.74

A1 229.85 233.96233.97 233.69 229.87 233.27 A 233.90 232.65 229.26 231.46 0202 230.64 Top of Fence 228.45 Bottom of Fence Water Level 233.97 EXISTING CONCRETE APRON Date of survey=Friday, October 25, 2019 233.94 233.62 228.33228.62 228.37 231.80 SLAB ON SIDE SLOPE 228.40 228.63 228.61 233.88 228.70228.71228.80 232.88 233.87 233.34 228.36228.55 231.80 233.69 231.22 230.79 228.34 228.34 234.07 234.12 233.96 228.37 228.33228.34 234.06 EXISTING MASONRY PARAPET WALL Pipe Invert 232.83 228.22 231.14 EXISTING ROAD Pipe Soffit 228.60 228.14 228.34 232.69 231.91 233.88 233.82 SAFETY BARRIER 228.15 228.32228.54 234.15 232.79 232.16 228.11 232.99 234.10 231.80 228.16 234.21 230.61 234.20 228.49 228.54 234.14 234.16 233.30 229.62 234.22 234.23 233.91 228.42 228.14 231.63 Water Level 229.24228.84 Date of survey=Friday, October 25, 2019 228.47 228.68 234.27 228.22 234.16 231.79 228.25228.22228.64 230.57 228.82 233.90 233.88 228.34 232.74 233.59 234.27 233.00 228.45 228.56 234.13 228.22 EXISTING FENCING 230.39 228.85 233.55 228.30 234.29 228.53 Top of Wall

DO NOT SCALE 228.90228.91 229.89229.82 229.70 229.91 234.36 228.96 229.09 234.29 234.07 234.10 228.71 231.72 229.53 230.65 UNNAMED STREAM 228.68228.65 229.00 234.15 234.40 228.28 234.39 228.42 233.55 228.28 231.12 234.13 234.25 KNOCKAKIP CULVERT 228.38Water Level 232.91 Date228.77 of survey=Friday, October 25, 2019 228.82 231.80 234.41 234.05 (KY-N21-016.00) 228.88 234.40 233.65 230.56 234.48 233.80 Bottom of Fence 229.17 232.47 Top of Fence 229.96 229.44 232.65 234.36 234.39 233.28 232.15 229.50 230.21 233.48 233.18231.97 233.80 233.98 229.16 233.48 231.25 230.75 234.36 233.75 234.47 233.41 231.78

233.97 233.96 234.44 233.80 230.12 Flow 233.91 234.06 231.58 234.53 233.73 232.59 234.58 234.52 234.50 229.38 229.16 234.26

234.48 234.58 234.13 230.92 234.08 230.39

Top of Wall 228.86 234.65 233.82 228.34 Base of crash barrier 234.23 Top of crash barrier 234.28 233.39 Top of Fence 227.78227.68 Bottom of234.28 Fence Circular Opening 234.67 227.24 230.79 EXISTING RAISED 227.93227.28 EXISTING MASONRY PARAPET WALL 234.57 Pipe Soffit 227.99 228.85 234.61 Water Level 233.80 Date of survey=Friday, October 25, 2019 227.83 CONCRETE VERGE 234.70 227.26 227.07 227.56 234.33 227.87 228.76 227.30 Pipe Invert 228.57 234.27 234.43 227.21 234.65 226.70 233.89 227.27 227.09 229.07 228.59 234.07 Water Level 227.33 226.53Date of survey=Friday, October 25, 2019 229.11 228.87 226.75 226.57 226.57 234.79 234.00 227.81 226.53 229.14 234.43 227.62 227.58Pipe Invert 226.67 233.47 diam=0.11 226.41 Water Level 227.84 228.60 Date226.45 of survey=Friday, October 25, 2019 226.81 227.05 229.21 EXISTING ROAD 226.56 234.68 226.59 234.72 228.49 227.46 226.94 229.42 SAFETY BARRIER 234.33 226.56226.50 226.58 Base of crash barrier 227.81 Top of crash barrier 229.23 226.51 226.54 226.45 228.01 229.62 226.51 227.02 233.23 226.75 227.78 229.28 Pipe Invert 226.74 227.34 226.55 226.74 diam=0.11 234.04 226.49 B 230.45229.97 227.69 226.51 226.62 229.64 234.78 226.23 234.05 228.86 226.27 227.79 233.86 226.40 0202 233.41 229.48 228.19 227.08 226.21 231.57 230.02 233.42 226.34226.14 226.73 234.84 226.47 226.29 234.82 232.17 227.98 228.31 226.29 Pipe Invert 226.87 226.33 226.55226.34 234.72 234.63 diam=0.15 230.52 229.87 226.53 Bottom ofTop233.17 Fence of Fence 226.39 233.17 228.63 Water Level Pipe Invert 228.57 234.31 233.57 226.81 Date of survey=Friday, October 25, 2019 233.04 230.51 diam=0.37 Pipe Invert 233.47 diam=0.1 226.69 226.02226.43 230.95 234.92 234.90 227.14 225.92 227.91 227.55 234.66 226.07 231.24 231.76 226.52 Flow

234.01 226.74 234.32 227.83 231.62 234.99 235.01 227.10 231.61 228.02 234.98 233.87 234.79 228.75 234.14 231.26 227.44 234.64 D 230.08 228.18 233.02 0203 230.91 228.28 233.31 235.07 228.52 235.12 232.47 228.66

231.32 229.09 233.31 235.13 UNNAMED STREAM 234.41 233.24 234.58 229.63 233.80 230.75 235.20 235.16

233.59 235.08 232.17

235.35 234.63 231.83 231.20 235.28 235.25 235.06 231.40 235.03 234.06

235.35

235.34 234.51 234.97 ISSUED FOR REVIEW

© ORDNANCE SURVEY IRELAND LICENSE NR. to 0203.dwg AR 0082518. ORDNANCE SURVEY IRELAND & TRANSPORT INFRASTRUCTURE KNOCKAKIP CULVERT (KY-N21-016.00) GOVERNMENT OF IRELAND IRELAND (TII) REMEDIAL WORKS ATKINS NOT TO BE HELD LIABLE FOR THE USE EXISTING STRUCTURE LAYOUT PLAN OF THIS DATA ON ANY PROJECT OTHER THAN THE MUNSTER BRIDGES TERM MAINTENANCE CONTRACT NR.3 PROJECT AOS MG MJ 1:125 18/11/19 18/11/19 18/11/19 A REVIEW COMMENTS INCORPORATED AOS 05/20 MJ MJ MUNSTER BRIDGES TERM May 20, 2020 - 9:15am - ISSUED FOR REVIEW AOS 11/19 MG MJ MAINTENANCE CONTRACT NR.3 Date: File: 5162555-HTR-DR-0200 P 5162555 / HTR / DR / 0201 A

V:\5162555\6 Dwgs-Graphics\61 AutoCad\5162555-HTR-DR-0200 to 0203.dwg GENERAL NOTES 100

Carriageway CL 1. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE 13320 2. ONLY WRITTEN DIMENSIONS SHALL BE USED. NO ROAD SAFETY BARRIER ROAD SAFETY BARRIER 1519 3701 944 6069 1087 DIMENSIONS SHALL BE SCALED FROM THE MASONRY PARAPET WALL H/S NORTHBOUND ISLAND SOUTHBOUND H/S DRAWINGS MASONRY PARAPET WALL 3. ALL LEVELS ARE IN METRES AND ARE TO MALIN HEAD DATUM

4. ALL COORDINATES ARE IN METRES AND ARE TO IRISH TRANSVERSE MERCATOR CONCRETE APRON SLAB ON SIDE SLOPE 5. DRAWINGS ARE TO BE READ IN CONJUNCTION WITH THE SPECIFICATION

231.137m 230.778m 10 0

BED LEVEL

227.657m 228.330m A1

25550

SECTION A SCALE 1:100 0201 DO NOT SCALE

CARRIAGEWAY CENTRELINE

230.930m

SURVEYED WATER LEVEL 228.020m

227.820m

SECTION B SCALE 1:100 0201

ISSUED FOR REVIEW

© ORDNANCE SURVEY IRELAND LICENSE NR. to 0203.dwg AR 0082518. ORDNANCE SURVEY IRELAND & TRANSPORT INFRASTRUCTURE KNOCKAKIP CULVERT (KY-N21-016.00) GOVERNMENT OF IRELAND IRELAND (TII) REMEDIAL WORKS ATKINS NOT TO BE HELD LIABLE FOR THE USE EXISTING SECTIONS A AND B OF THIS DATA ON ANY PROJECT OTHER THAN THE MUNSTER BRIDGES TERM MAINTENANCE CONTRACT NR.3 PROJECT AOS MG MJ 1:100 18/11/19 18/11/19 18/11/19 A REVIEW COMMENTS INCORPORATED AOS 05/20 MJ MJ MUNSTER BRIDGES TERM May 20, 2020 - 9:20am - ISSUED FOR REVIEW AOS 11/19 MG MJ MAINTENANCE CONTRACT NR.3 Date: File: 5162555-HTR-DR-0200 P 5162555 / HTR / DR / 0202 A

V:\5162555\6 Dwgs-Graphics\61 AutoCad\5162555-HTR-DR-0200 to 0203.dwg File: 5162555-HTR-DR-0200 to 0203.dwg DO NOT SCALE 0 10 100 Date: May 20, 2020 - 9:22am A1 V:\5162555\6 Dwgs-Graphics\61 AutoCad\5162555-HTR-DR-0200 OF THISDATA GOVERNMENT THE CONTRACT NR.3PROJECT ATKINS NOT AR 0082518. © ORDNANCE MUNSTER ORDNANCE TO SURVEY ON OF IRELAND BRIDGES BE

ANY PROJECTOTHERTHAN HELD LIABLE IRELAND LICENSENR.

SURVEY IRELAND& TERM DATUM = MAINTENANCE FOR Level (mOD)

THE USE Offset (m) 226.000mOD DATUM =

232.397 -27.923 Level (mOD) Offset (m) 226.000mOD to0203.dwg

232.121 -25.167

233.175 -27.599

233.168 -24.154 232.204 -20.271 EDGE OFCARRIAGEWAY

232.789 -17.927

232.626 -20.449 EDGE OFCARRIAGEWAY

232.668 -13.322

231.435 -14.346

232.613 -10.059 EXISTING FENCELINE GRAVEL TRACK

231.973 -8.278 231.245 -7.729

230.117 -6.143 SCALE 1:100 SECTION SCALE 1:100 SECTION A -

ISSUED FORREVIEW REVIEW COMMENTSINCORPORATED

228.336 -3.491 229.935 -6.686 EXISTING FENCELINE 227.277 -1.284 0201 D 0201 C 230.768m

227.169 0.000

228.978 -2.376

227.325 1.214 BRIDGE PARAPET

227.582 2.099

228.359 -0.727 231.139m AOS AOS

228.486 3.289 228.341 0.000 11/19 05/20

228.341 4.522 MG MJ

BRIDGE PARAPET 228.342 2.285 MJ MJ

230.453 6.096 IL PIPE 110mmØ SURVEYED WATER 228.540 3.261 CONCRETE 227.810m 231.568 7.398 CONCRETE IL PIPE 233.230m

110mmØ 228.681 6.176

233.174 9.820 LEVEL 227.930m

233.466 10.961 228.966 8.364 SURVEYED WATER EXISTING

233.829 15.134 FENCELINE 228.884 11.992 LEVEL 229.450m EXISTING

229.159 14.093 FENCELINE

233.805 18.608 229.160 15.876

233.782 22.081 MAINTENANCE CONTRACT TRANSPORT INFRASTRUCTURE MUNSTER BRIDGES TERM IRELAND (TII) NR.3 EXISTING SECTIONAL 1. GENERAL NOTES 5. 3. 2. 4. P KNOCKAKIP IRISH TRANSVERSEMERCATOR DRAWINGS ARETOBEREADINCONJUNCTIONWITH HEAD DATUM DRAWINGS DIMENSIONS SHALL NOTED OTHERWISE ONLY WRITTENDIMENSIONSSHALL THE SPECIFICATION ALL ALL ALL COORDINATES AREINMETRESANDTO LEVELS AREINMETRESANDTOMALIN DIMENSIONS AREINMILLIMETRESUNLESS 1:100 5162555 / REMEDIAL ISSUED FORREVIEW CULVERT (KY-N21-016.00) 18/11/19 BESCALEDFROM HTR/ AOS

ELEVATIONS C WORKS DR 18/11/19 / 0203 BEUSED.NO MG THE AND D 18/11/19 A MJ GENERAL NOTES 100

233.21 1. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE

233.13 233.21 233.17 232.86 2. ONLY WRITTEN DIMENSIONS SHALL BE USED. NO DIMENSIONS SHALL BE SCALED FROM THE DRAWINGS

233.35 3. ALL LEVELS ARE IN METRES AND ARE TO MALIN HEAD DATUM

233.41 4. ALL COORDINATES ARE IN METRES AND ARE TO IRISH TRANSVERSE MERCATOR 232.84 233.36 5. DRAWINGS ARE TO BE READ IN CONJUNCTION WITH THE SPECIFICATION 233.53

233.50 233.47 233.03 SEQUENCE OF WORKS 233.59 233.47 A · REMOVE ANY LARGE STONES WITHIN THE WORKING

10 EXISTING FENCING 233.62 233.66 PLATFORM AREAS AND STORE ON SITE FOR REINSTATEMENT. 233.66 0 233.18 · PLACE HEAVY DUTY TERRAM 2000 GT OR

233.56 EQUIVALENT APPROVED GEOTEXTILE ON THE 233.74 EXISTING STREAM BED OVER THE EXTENT OF THE WORKING PLATFORM AREA. · PLACE WORKING PLATFORM ON THE GEOTEXTILE A 233.64 CONSISTING NOMINAL 250mm THICK CLEAN GRAVEL. · EXCAVATE THE EXISTING STREAM BED MATERIAL A1 0206 233.69 229.87 233.27 WITHIN THE CULVERT. THIS MATERIAL SHALL BE 233.90 STORED WITHIN THE WORKS AREA FOR

Top of Fence REINSTATEMENT. Bottom of Fence · ON COMPLETION OF THE CONCRETE LINING WORKS, EXISTING CONCRETE APRON 233.94 233.62 REMOVE THE WORKING PLATFORM AND SLAB ON SIDE SLOPE GEOTEXTILE. 233.88 228.70 233.87 233.34 · REINSTATE THE EXCAVATED STREAM BED MATERIAL WITHIN THE CULVERT AND THE LARGE STONES IN 234.07 THE STREAM BED · ALIGN THE STREAM BED LEVEL LOCAL TO THE EXISTING MASONRY PARAPET WALL EXTENTPLATFORM OF 234.06 232.83 CULVERT ENDS WITH WASHED GRAVEL 231.14 EXISTING ROAD Pipe Soffit 10000 233.88 SAFETY BARRIER

WORKING 234.10

234.20 228.54 234.14 234.16 A 234.23 233.91 TEMPORARY DAM Nr.1 UPSTREAM 234.27 228.82 233.59 234.27 233.00 234.13 EXISTING FENCING 233.55 Top of Wall DO NOT SCALE

229.91 234.29 234.07

229.53 UNNAMED STREAM 229.00 234.15 234.40 234.39 233.55 234.13 KNOCKAKIP CULVERT

234.41 234.05 (KY-N21-016.00) 233.65 234.48 Bottom of Fence Top of Fence

234.36 234.39 233.28

233.98 EXISTING MASONRY PARAPET WALL 234.36 233.75 234.47

233.80 233.91 Flow 233.73 234.52 234.26

234.48

Top of Wall 234.65 233.82 Base of crash barrier Top of crash barrier

Top of Fence Bottom of Fence Circular Opening TEMPORARY DAM Nr.2 EXISTING RAISED 230.79 DOWNSTREAM 234.57 Pipe Soffit 234.61 CONCRETE VERGE 233.80 234.33 234.27 TEMPORARY DAM Nr.3 234.65 233.89 DOWNSTREAM 234.79 234.00 234.43 EXISTING ROAD 234.68 SAFETY BARRIER 234.72 Base of crash barrier Top of crash barrier A 10000 234.04 WORKING PLATFORM B 229.97 234.05 228.86 EXTENT 233.86 0206 229.48 233.42 OF

234.84 234.82 228.31

234.63

Bottom ofTop Fence of Fence

233.57 233.04

234.92 234.90

227.91 Flow

234.01 234.32 234.99 235.01

234.98

234.79 234.14

235.07

235.12 UNNAMED STREAM 234.41

235.20 235.16

235.35 234.63

235.28 235.25

235.06

235.35

235.34 234.51 ISSUED FOR REVIEW

© ORDNANCE SURVEY IRELAND LICENSE NR. to 0206.dwg AR 0082518. ORDNANCE SURVEY IRELAND & TRANSPORT INFRASTRUCTURE KNOCKAKIP CULVERT (KY-N21-016.00) GOVERNMENT OF IRELAND IRELAND (TII) PROPOSED REMEDIAL WORKS ATKINS NOT TO BE HELD LIABLE FOR THE USE SHEET 1 OF 2 - 10:04am OF THIS DATA ON ANY PROJECT OTHER THAN THE MUNSTER BRIDGES TERM MAINTENANCE CONTRACT NR.3 PROJECT AOS MG MJ 1:125 09, 2020 14/05/20 14/05/20 14/05/20 A NOTES ADDED AOS 07/20 MJ MJ MUNSTER BRIDGES TERM Jul - ISSUED FOR REVIEW AOS 05/20 MJ MJ MAINTENANCE CONTRACT NR.3 Date: File: 5162555-HTR-DR-0205 P 5162555 / HTR / DR / 0205 A

V:\5162555\6 Dwgs-Graphics\61 AutoCad\5162555-HTR-DR-0205 to 0206.dwg Carriageway CL GENERAL NOTES 100

13320 1. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE ROAD SAFETY BARRIER ROAD SAFETY BARRIER 1519 3701 944 6069 1087 MASONRY PARAPET WALL H/S NORTHBOUND ISLAND SOUTHBOUND H/S 2. ONLY WRITTEN DIMENSIONS SHALL BE USED. NO REMOVE, AND STORE FOR REINSTATEMENT, ANY MASONRY PARAPET WALL DIMENSIONS SHALL BE SCALED FROM THE EXISTING MATERIAL WITHIN THE CULVERT. DRAWINGS OVER THE EXTENT OF THE PROPOSED LINING, CLEAN CONCRETE APRON SLAB ON SIDE SLOPE CULVERT TO ST3 QUALITY BY MECHANICAL MEANS AND 3. ALL LEVELS ARE IN METRES AND ARE TO MALIN COAT INSIDE OF CULVERT SURFACE TO BE LINED WITH HEAD DATUM NOMINAL 250mm TEMPORARY WORKING NITROPRIME ZINCRICH PLUS OR EQUIVALENT APPROVED PLATFORM CONSISTING CLEAN GRAVEL A PROPOSED 4. ALL COORDINATES ARE IN METRES AND ARE TO ON HEAVY DUTY TERRAM 2000 GT OR CONCRETE LINING IRISH TRANSVERSE MERCATOR EQUIVALENT APPROVED GEOTEXTILE NOMINAL 250mm TEMPORARY WORKING ON EXISTING STREAM BED PLATFORM CONSISTING CLEAN GRAVEL ON HEAVY DUTY TERRAM 2000 GT OR 5. DRAWINGS ARE TO BE READ IN CONJUNCTION WITH EQUIVALENT APPROVED GEOTEXTILE THE SPECIFICATION ON EXISTING STREAM BED 231.137m TEMPORARY DAM A 230.778m SEQUENCE OF WORKS Nr.1 UPSTREAM TEMPORARY DAM A 24700 Nr.2 DOWNSTREAM · REMOVE ANY LARGE STONES WITHIN THE WORKING

10 PLATFORM AREAS AND STORE ON SITE FOR TEMPORARY DAM REINSTATEMENT. BED LEVEL Nr.3 DOWNSTREAM 0 · PLACE HEAVY DUTY TERRAM 2000 GT OR 228.330m EQUIVALENT APPROVED GEOTEXTILE ON THE 227.657m EXISTING STREAM BED OVER THE EXTENT OF THE WORKING PLATFORM AREA. · PLACE WORKING PLATFORM ON THE GEOTEXTILE CONSISTING NOMINAL 250mm THICK CLEAN GRAVEL. · EXCAVATE THE EXISTING STREAM BED MATERIAL A1 WITHIN THE CULVERT. THIS MATERIAL SHALL BE STORED WITHIN THE WORKS AREA FOR 10000 25550 REINSTATEMENT. · ON COMPLETION OF THE CONCRETE LINING WORKS, REMOVE THE WORKING PLATFORM AND SECTION A GEOTEXTILE. SCALE 1:100 0205 · REINSTATE THE EXCAVATED STREAM BED MATERIAL REMOVE, AND STORE FOR REINSTATEMENT, ANY EXISTING MATERIAL WITHIN THE CULVERT. WITHIN THE CULVERT AND THE LARGE STONES IN THE STREAM BED OVER THE EXTENT OF THE PROPOSED LINING, CLEAN CULVERT TO ST3 QUALITY BY MECHANICAL MEANS AND COAT INSIDE OF CULVERT SURFACE TO BE LINED WITH NITROPRIME · ALIGN THE STREAM BED LEVEL LOCAL TO THE CULVERT ENDS WITH WASHED GRAVEL ZINCRICH PLUS OR EQUIVALENT APPROVED CARRIAGEWAY CENTRELINE DO NOT SCALE 1050

PROPOSED CONCRETE LINING SECTION B SCALE 1:100 0205

Culvert CL

EXISTING CORRUGATED CULVERT CULVERT ON COMPLETION OF THE WORKS AND REMOVAL OF CONCRETE HARDSTAND AND GEOTEXTILE, ALIGN EXISTING STREAM BED INSIDE FACE OF CULVERT LINING WITH CONCRETE LINING / REINSTATED BED MATERIAL USING CULVERT CORRUGATIONS WASHED GRAVEL CORRUGATION DEPTH (VARIES) CONCRETE GRADE C40/50 STAINLESS STEEL A393 EXISTING STREAM BED LEVEL 50 VARIES VARIES 50 STAINLESS STEEL A393 MESH NOMINAL THICKNESS 150mm REINFORCEMENT MESH WITH 100 ABOVE CORRUGATIONS 65mm CONCRETE COVER LEVEL VARIES 100 A 100

F2 NOMINAL 150mm THICK 150 VARIES (TO BE DETERMINED ON SITE) NOM 150 1050 CONCRETE GRADE C40/50 STAINLESS STEEL GRADE 316

NOMINAL ABOVE CORRUGATIONS A393 REINFORCEMENT MESH WITH 65mm CONCRETE COVER VARIES

VARIES DETAIL AT ENTRY / EXIT OF CULVERT

CORRUGATED CULVERT Scale at A1 1:50 Scale at A3 1:100 TYPICAL CULVERT CROSS SECTION TOP OF LINING DETAIL CULVERT LINING DETAIL Scale at A1 1:50 Scale at A1 1:10 Scale at A1 1:10 Scale at A3 1:100 Scale at A3 1:20 Scale at A3 1:20

ISSUED FOR REVIEW

© ORDNANCE SURVEY IRELAND LICENSE NR. to 0206.dwg AR 0082518. ORDNANCE SURVEY IRELAND & TRANSPORT INFRASTRUCTURE KNOCKAKIP CULVERT (KY-N21-016.00) GOVERNMENT OF IRELAND IRELAND (TII) PROPOSED REMEDIAL WORKS ATKINS NOT TO BE HELD LIABLE FOR THE USE SHEET 2 OF 2 - 1:50pm OF THIS DATA ON ANY PROJECT OTHER THAN THE MUNSTER BRIDGES TERM MAINTENANCE CONTRACT NR.3 PROJECT AOS MG MJ 1:100 15, 2020 14/05/20 14/05/20 14/05/20 A NOTES ADDED, DETAILS UPDATED AOS 07/20 MJ MJ MUNSTER BRIDGES TERM Jul - ISSUED FOR REVIEW AOS 05/20 MJ MJ MAINTENANCE CONTRACT NR.3 Date: File: 5162555-HTR-DR-0205 P 5162555 / HTR / DR / 0206 A

V:\5162555\6 Dwgs-Graphics\61 AutoCad\5162555-HTR-DR-0205 to 0206.dwg

Appendix B. Contractor Method Statement

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 37 of 44

RISK ASSESSMENT METHOD STATEMENT – RAMS 26 REV07

Title: Masonry Repair

Project Name: Munster Bridges

Locations: Knockakip Culvert - KY-N21-016.00

Safety Notes / Site Safety Rules:

a) All operatives will be Site Inducted on their first day on site and have a minimum of a valid Safe Pass card, as standard b) All works to be carried out within the agreed site boundary and/or Traffic Management plan c) All operatives will be required to wear the minimum P.P.E as follows:- - hard hats, hi-vis vests, safety boots (see below for task specific PPE) d) Working hours to be strictly within specified site hours. e) All plant operators to have relative and valid CSCS cards f) All persons on site to follow the instructions of site management g) If an operative feels work conditions are unsafe, then they are to stop works immediately and inform Site Management h) GA1 certs to be kept on file for inspection in the Mobile Safety File i) All plant to be weekly inspected and details recorded on GA2 j) GA3 to be completed weekly or as conditions dictate for all work at height k) Harnesses to be recorded in the harness log book l) No works to be carried out in extreme weather conditions m) Where required (adverse weather) work to be protected with hessian material n) Traffic management to be set up as per temporary traffic mgmt. plan set No.1. o) The existing carriageway over the culvert shall remain in service at all times p) Cumnor shall liaise with the inland fisheries Ireland environmental officer regarding works

Ecological Notes

• No re-fuelling can take place within 20m of the stream and can only take place using bowsers of delivery trucks. • Spill trays to be used when refueling • All refueling to take place within the site set up on the hard shoulder and not anywhere near the watercourse • Spill kits will be readily available on site • When entering the stream, and when leaving the, all operatives must wash down their wellingtons / waders and any tools that come into contact with the water with active Virkon

Page 1 of 21 CCF800/23 Rev 0 Aquatic. This will avoid the risk of any cross contamination when working on other bridges in other areas. • Operatives to be made familiar with Inland Fisheries Ireland Biosecurity Protocol 2010 prior to commencing the works to ensure all guidelines are followed • Sandbags to be placed as bund to dry area below area of impact to prevent any lime mortar entering the watercourse • All birds’ nests are protected by law. Nests which might be encountered under bridges include dipper and grey wagtail. The Dipper nests in closed / domed nests often located on supports under bridges. Kingfisher may also nest in sand banks close to bridges. Our ecologist will advise on general ecological questions as works progress. If a nest is discovered, the area is to be left undisturbed and the ecologist advice should be sought. If a known nesting site would be impacted be proposed repair works, mitigation in the form of artificial nest boxes must be provided. • There is Japanese knotweed on the d/s left bank. No works to be carried out within 7m of this. All access hoses to come down the opposite bank. This area is not to be disturbed and will be fenced off from the works area. This work will be carried under guidance from Cumnor’s Ecologist. •

Site Set Up

• TTMP set up No1 to be set up as per diagram below

• Site vehicles will park within the temporary traffic management set up on the hard shoulder • All materials will be stored within the TM set up

Page 2 of 21 CCF800/23 Rev 0

Water Management

1) The stream will be over-pumped through a flume that will be attached roof of the culvert at a high level. 2) The pump will be located in a shelf that will be dug into the slope above the culvert. 3) Life ring to be placed in full view on pole at edge of river 4) Sand to be brought to site in 1T Bags from Roadstone Classis. Sand to be clean building sand. 5) Approximately 60 no. hessian sand bags to be filled with sand and handed down to the river bed at upstream side of culvert 6) Sand bags should only be half filled with sand and tied & sealed to ensure no sand enters the watercourse 7) Bottom layer of sandbags should be “walked in” to riverbed to create good seal between sand bags and river bed 8) Sand bags to be built up in stretcher bond to desired height 9) There will be three dams erected in the stream; a. Dam 1 upstream of the culvert and dam 2 &3 situated downstream of the culvert (See above). b. Dam 2 and 3 will be erected first, 300mm high on the stream bed. c. Dam 1 will then be erected and the stream flow pumped downstream of dam 3. The intake will be fitted with a filter to ensure no fish enter the pipeline. d. The outfall pipeline will be fitted with a silt sock. This will dissipate flow and prevent scour of the river bed. e. The stream between dam 1 & 2 will be electro fished and the fish placed in the pool created between dam 2 and 3. f. On completion of the electro fishing dam 2 will be raised to full height and a silt fence will be erected between dam 2 and dam 3 and a second silt fence will be erected just upstream of dam 3. g. The water between dam 1 and dam 2 will be pumped into the pooled area between dam 2 and dam 3 in advance of the silt fences. h. A shallow sump will be excavated (or naturally occurring) in the stream bed upstream of dam 2 to catch surface water and cleaning water from power washing the culvert. i. The collected water in the sump will be pumped downstream between dam 2 and dam 3 and discharge in advance of the silt fences

Page 3 of 21 CCF800/23 Rev 0 10) The outlet pipe will be placed into a 225mm non perforated pipe installed through the culvert at high level. It will be secured by a temporary bracket that will be fixed to at high level along the culvert. 11) The bracket will consist of a threaded bar arrangement with unit strut drilled through the steel lining with an expanding anchor bolt fitting at the end to hold it in place. The threaded rod arrangement will allow for height adjustment to accommodate for a gravity fall on the pipe. 12) Sump and 2 inch pump to be set up on down stream side of culvert to pump away any excess water that has managed to get through the sandbag dam. This water is to be pumped into the area between dam 1 and dam 2 13) Cumnor will arrange consultation with IFI prior to mobilisation. Electrofishing requirement will be agreed upon at this consultation.

Fig i – Upstream of Culvert

Fig ii – Downstream of culvert

Typical sequence of works:

Page 4 of 21 CCF800/23 Rev 0 1. In relation to existing bed gravels upstream and downstream of structure : Existing river bed gravels shall be retained. Lay Terram 2000GT on existing riverbed gravel and construct temporary 300mm thick clean Class 6F granular capping over to form working platform. On completion of the works remove the granular working platform and geotextile. Supplement the existing gravels to IFI requirements local to the culvert ends.’ 2. Excavator to be tracked down path from road to river bed 3. Existing concrete lining to be broken from culvert using breaker on 1.5T machine 4. Broken out material to be removed using excavator, shovels and wheel barrows. Kango hammer to be used where necessary 5. Material to be disposed of in Conhor Construction Tip in Ballincollig 6. Power Washing of Culvert Lining: • The lining will be cleaned using a 25.000PSI Hydro Power Washer removing the loose / decayed material and exposing a clean Sa3 finish on the existing steel lining. • The washing unit generator will be positioned in the works area on the road with the lance hose running down the bank into the mouth of the culvert. • The washing will commence on upstream side, washing in the downstream direction. • It is predicted that the power washing will remove all loose / decayed material but if required small angle grinders and wire brushes will be used to remove any small pockets that remain. This area will then be power washed again to ensure it is completely clean. • A silt fence will be erected at the outfall of the culvert on the downstream side to ‘filter’ the resultant water from the washing of the steel lining. • Arisings from the cleaning of the culvert lining will be collected within the culvert and disposed of off site to a Conhor construction tip. • A small pump will then be placed on the down – stream side to pump the water into the area between Dam 2 and Dam 3. • A layer of silt fencing will be wrapped around the intake pipe of the pump as an additional filter layer and the outfall will have a de-watering bag placed around the end of hose. 7. Nominal 200mm Thick C25/30 Shotcrete Lining with A393 Stainless Steel Mesh Reinforcement to 1/3 diameter height

Fig iii

8. Existing deposits within the corrugated steel culvert to be removed from Culvert and stored for reuse. Material to be cleaned in washout area in field adjacent to culvert. 9. The invert shall then be coated with a corrosion inhibitor such as Galvafroid manufactured by Fosroc or equivalent approved. 10. An anti-corrosion steel primer such as Nitoprime Zincrich Plus by Fosroc or equivalent to be used to prime the steel. 11. Shotcreting o All shot-creting works shall be undertaken in accordance with "BS EN 14487 : sprayed concrete - execution" o Nominal 200mm Thick C25/30 Shotcrete Lining With A393 Stainless Steel Mesh Reinforcement to 1/3 diameter height

Page 5 of 21 CCF800/23 Rev 0 o The culvert lining works shall be executed during the low water flow in the months July to September inclusive o Set up pump on road within works area o Pump hoses will always be located within dry works area so there is no chance of concrete spillage entering the watercourse o Care to be taken when working beside live road o Direct concrete lorry to pump o One man to act as pump operative

o 2 men required for nozzle and spraying o Spotter to stand at mouth of culvert and act as communicator between pump man and nozzle man o Googles or glasses to be worn at all times when shotcreting o Nominal 200mm to be sprayed on culvert face o Pump hoses etc to be completely cleaned ready for next days pour. 12. Works will take approximately 2 weeks. 13. Excess concrete to be put in skip. 14. Upon demobilisation all plant and materials to be taken away in Cumnor hiab truck 15. Material used for working platform to be put into 1 T bags and removed from works area with hiab crane. Terram to be disposed of in skip 16. Flume to be removed from river and Dam 1 & 2 dismantled 17. Silt fences and dam 3 to be left in place until the sediment upstream of same has disapated. 18. Small step in river bed outside culvert to be reinstated with washed gravel as required 19. All sandbags to be lifted from river and taken to Conhor construction tip. 20. River bed outside culvert to be reinstated with clean gravel as required.

Fig iv – Reed B50 Shotcrete Pump

Page 6 of 21 CCF800/23 Rev 0

Fig v – Pathway to Culvert from Road

Key Personnel Involved:

Name: Role / Trade: Contracts Manager Project Engineer Quality & Safety Manager Contract Ecologist Foreman / SLG

P.P.E required

Other:

1. Hi-Vis vest / jacket - double banded EN ISO 20471

2. Trousers – double banded Safety Boots Hard Hats Safety EN ISO 20471:2013 To include EN397 Gloves 3. PVC rain trousers / jackets EN50365 Ankle EN 388 levels EN 471:2003 support 4-1-2-1 or 4. Safety harness (where no edge protection) EN ISO 2-1-2-1 EN 361:2002 20345:2011 CE 5. Lanyard S3 SRC EN 355:2002

Note: EN 795 for any anchor point used

All work is to be undertaken by qualified competent persons with experience of the type of work described above

Prepared by: Date: March 2020

Page 7 of 21 CCF800/23 Rev 0

Position: Contract Manager Issue no: Rev 00

Page 8 of 21 CCF800/23 Rev 0

Project / Location Munster Bridges Job No: J1938

Assessment Review Assessment Date: Assessed By: COM 12/05/20 Period: Scope of Works:

Evaluation Matrix Severity of Consequence (S) Likelihood (L) Risk Level (R)

1 Insignificant/minor first aid, no time off, no loss 1 Improbable Low 1 - 4 5 5 10 15 20 25 Severity of Lost time, recoverable, (strain, sprain, laceration, dermatitis) 2 2 Low Moderate 5 - 9 Consequence 4 4 8 12 16 20 3 3 6 9 12 15 Temporary disability, recoverable (minor fracture, asthma, 3 3 Medium Considerable 10 - 14 deafness, concussion) 2 2 4 6 8 10

Permanent disability, survivable (major fractures, amputation, 1 1 2 3 4 5 4 4 High head injuries, eye injuries, poisoning) High 15 – 19 1 2 3 4 5 5 Causing death to one or more people (fatal injuries, Likelihood occupational cancer, fatal disease/fire) 5 Almost certain Critical 20-25

Notes on completing the Risk Assessment below:

• A number of Hazards have been identified on the above mentioned site. Please confirm which may be applicable to your specific works on site. Each hazard is to be completed by entering Y/N in the end column and initial that you have read and understood. If specific relevant hazards have not been noted, the Sub-Contractor is obliged to ensure those hazards, including detailed risk assessment are included in the blank sections below. Additional space has been left if addition controls are required.

• If issues arise on site causing unforeseen and additional risks to those completing the works, that job or task will need to be PAUSED until such

time that the Risk has been assessed and additional control measures are put in place and documented below reducing the risk associated with said

works

Page 9 of 21 CCF800/23 Rev 0

Existing and Additional Risk Control Measures Risk Applic Ref: Individual Hazards Identified Persons / Groups at Risk Remaining able on Activity Risk Before After site Description Controls Controls Y / N S L R S L R (Initial) 1. • Use of Abrasive • Eye / bodily • All Operators 3 3 9 • Ensure guards and safety devices are working & in place 1 3 3 Wheels injuries • Members of the • Certified operatives only to change abrasive wheels / discs • Injury to other Public • Safety goggles / glasses (correct EN rating – min BS2092) and person suitable ear protection to be worn at all times • Nosie induced • Work area to be free of debris and obstructions & item to be cut is hearing loss securely positioned • Damage to • Check operations will not affect others in the immediate area either Materials / by flying debris or excessive noise services • Ensure protection of adjacent materials and services are in place (Water, Gas, ESB)

2. • Access, egress • Trip hazards, • All Operators 4 2 8 • All access ways into site to be kept clear at all times 4 2 2 to site and work slipping causing • Members of the • Site housekeeping to be enforced to ensure the site is safe and areas a limb injury Public organised • All cables to be hung or moved out of access paths

3. • Use of a • Incompetence • All Operators 4 2 8 • Use only authorised nominated and certified persons to sling loads 2 2 4 Banksman on • Trapped hands / • Members of the & bank plant Site feet public • Understanding of hand signals is required • Injury to • Incorrect use of • Hands and feet are clear of load before any signal is given persons in lifting gear • Only approved and certified lifting gear may be used public • Overloading • Banksman must wear an orange, named hi vis top spaces Little or no • Radio communication must be used where visibility is restricted • Damage to Communication • Strong gloves and steel toe capped boots are a must adjacent buildings / materials

Page 10 of 21 CCF800/23 Rev 0 4. • Using Cement • Severe skin • All operators 2 2 4 • A MSDS (Material Safety Data Sheet) sheet must be available for 1 2 2 and / or concrete burns involved in the materials used on site • Falls of operation • Appropriate PPE to be worn, including glasses for splashing, PVC materials into gloves and wellingtons excavations • Washing facilities and first aid station to be provided for operatives • Manual • Restrict time exposed to concrete handling • Barriers / stop blocks to all excavations • Suitable discharge area for concrete lorries • Safe system of work in place documented and signed by all involved in the works

5. • Any Demolition • Sudden collapse • All operators 2 4 8 • All glass, projecting parts & loose objects will be removed first 2 2 4 works on site of structure involved in the • All service to be made redundant / safe • Hazardous works • No other work will be carried out within the area of demolition substances • Public adjacent to • Demolition will start at the top of the roof and work downwards works areas • Continuous monitoring of the structure will be carried out to ensure stability of the structure • Dust suppression to be used, if conditions dictate • Shoring and bracing will be erected as required to prevent collapse • All openings to be protected • PPE to be worn at all times • Safe system of work in place documented and signed by all involved in the works

Page 11 of 21 CCF800/23 Rev 0 6. • Dust on Site • Visibility • Injury to 4 2 8 • Use equipment that produces minimal dust 2 1 2 • Silicosis impairment for operators on • Use water to dampen when cutting • Dust drivers causing site • Restricted hours on site explosion collision • Injury to members • Seal off areas to prevent the spread of dust • • Personal injury of the public • Issue PPE - dust masks, safety respirators

7. • Use of Electrics • Electrocution • All operators 2 4 8 • All temporary routes for cabling must be set out beforehand and 2 2 4 on Site • Damage to • Members of the duct where possible cables public that me be • All portable equipment must be P.A.T tested as per the Gen • Overload in close proximity Application Regs 2007, part 3: Electricity – Reg 81 (as required) causing a fire of the site and certs kept on file • All electrical appliances / tools must be visually checked by a competent person before each use • Trailing cables must be tied overhead where possible and not interfere with access routes • All electrical cabinets / boxes must be locked • C02 temporary fire points must be strategically setup around site / buildings • All electrical tools must be a maximum of 110volts • Safe system of work in place documented and signed by all involved in the works

8. Fires • Bodily injury • All operators 2 4 8 • No burning of materials anywhere on or around site permitted 2 2 4 • Spread of fire • Member of public • All gas bottles must be securely tied and have a Fire point • Property in close proximity (extinguisher) close at hand damage of the site • Any explosives are to be protected by close board sheeting • Potential death • Strategic fire points to be setup around site & through buildings • Temporary fire escape layout plan & evacuation plan to be setup

Page 12 of 21 CCF800/23 Rev 0 9. • Lifting • Dangers to • All operators 4 2 8 • All lifting equipment must be certified (GA1) and copies of certs 1 4 4 Equipment operatives on • Public in close kept onsite site proximity of • Only certified operators to use lifting plant, e.g. cranes, MEWP’s • Fall of materials site etc • Lifting equipment to be checked and recorded in GA2 weekly • Any damaged or worn slings / chains must not be used and disposed of • Temporary barriers must be placed around lifting / sluing areas • Safe system of work in place documented and signed by all involved in the works

10. • Manual • Injury to back • All operators 4 2 8 • All operatives are trained in manual handling. 4 1 4 Handling of • Lower limb • Use of mechanical aids to lift items where possible, e.g. cable block materials on site injury / teleporter/ Hi-ab • Arm & Hand • Use of two employees to lift awkward or heavy items injuries • Frequent stretching of the back is encouraged to all employees who are constantly bending.

Page 13 of 21 CCF800/23 Rev 0 11. • Noise • Damage to • All operators 4 2 8 • PPE must be worn when there is a noise level is above 80dBA 2 2 4 hearing • Members of • Earplugs to be worn at low level noises • Affecting the public in • Ear muffs to be worn when operators are using tool/plant that have members of the close a high noise level public proximity to • Operators are not to be exposed to excessively loud noises for the ongoing extended periods works • If possible use other plant and tools that do not have a loud noise level

12. • Operating Plant • Dangers to other • Operator 4 4 12 • Area to be excavated to be CAT scanned for services by ticketed 1 4 4 on Site operatives on • Operatives on operator. Drawing and plans to be checked also. Dial before you dig (Excavator) site site to be consulted. • Overturning of • Members of • Operators must be CSCS certified and trained to use plant excavator the public • Safety signage to be in place • Overhead • No unauthorised passengers permitted on plant. Services • All plant must have flashing beacons and audible sirens • Underground • Care to be taken when reversing and sluing Services • Unattended excavator must have the engine switched off and keys • Injury to driver out and others • Extra care to be taken where sloping surfaces are being driven including death • Do not overload machinery to their stated capacity • All other operatives to remain outside the exclusion zone. 13. • Operating Tools • Cuts / • All operators 4 2 8 • Wear appropriate PPE to include ear defenders and safety glasses / 2 1 2 • Operator must track on the designated access route as required on site Lacerations using tools on goggles • Spotter to be in place at all times • Long term site • Only 110volt (max) permitted on site • Safe system of work in place documented and signed by all deafness • Erect sound barriers as required involved in the works • Nerve injuries • Restrict length of time for use, e.g. mainly vibrating / oscillating

tools (check tool specs)

• Do not leave tools running

Page 14 of 21 CCF800/23 Rev 0 14. • Refuelling plant • Fire / • All operators 2 2 4 • All fuels to be kept in correct containers and clearly labelled & 1 2 2 on site environmental involved in the identified pollution refuelling task • No refuelling to take place in the vicinity of ignition points • Engines must be switched off before any refuelling takes place • Fuel tanks must be double skinned and bunded with lockable valves • Spillage kits must be in close proximity of all tanks and within waste lorries • Storage areas of fuels must have appropriate fire extinguishers • Any spillages must be reported immediately to the Site Supervisor / Safety Manager

15. • Setting out of • Injury to • All operators 2 4 8 • Install traffic management as per plan issued 1 3 3 Traffic operator on site • Members of • Ensure signage and cones are as per approved plan Management by moving the public • Operators with CSCS cards to setup traffic management system and vehicles inspect on a weekly basis or as required • Injury to • Safe system of work in place documented and signed by all members of the involved in the works public that may • be in close 16. • Preventing • proximityInjury to of • All operators 2 3 6 • All site visitors are inducted prior to being in work areas 2 2 4 unauthorised worksunauthorised on site • Operators to notify site management of any unauthorised access to access to area of person on site • Unauthorised site immediately works • Damage to plant person on site • Site gates to be closed at all times and locked and checked at close / equipment and of business materials All required signage in place notifying public of works in the area

Page 15 of 21 CCF800/23 Rev 0 17. • Vibration on • Numbness & • All operators 2 2 4 • Allow only competent persons to use tools 1 2 2 site tingling of involved in the • Refer to individual vibration / exposure limits fingers / hands works • Wear full PPE to include anti-vibration gloves as required • Nerve & muscle • Reduce length of times using tool damage to • Use tools with low vibration fingers / hands • Safe system of work in place documented and signed by all • White finger involved in the works (VWF) • Arm vibration • (AV)

18. • Working in bad • Operators being • All operators 3 3 9 • When there are poor weather conditions all work to stop 3 1 3 weather injured as a immediately, foreman to make call if carrying out work is unsafe conditions result of the bad weather

19. • Working over • Drowning • All operators 3 4 12 • PPE to include life vests, flotation devices and drag lines as 2 3 6 water • Upper body conditions dictate or where no edge protection in place injuries • AF4 to be completed weekly • Death of fish • Temporary decks with heavy gauge polythene and catch nets to be life used where working under bridges • All plant and tools to be placed in water course to be steam cleaned prior to use • Safe system of work in place documented and signed by all involved in the works

Page 16 of 21 CCF800/23 Rev 0 20. • Vermin and bird • Contact with • All operators 3 3 9 • Suitable PPE to be worn at all times. including full disposable 2 2 4 droppings droppings may involved in overalls. Gloves to be disposed of after each use – do not re-use cause illness and works gloves / dust masks / disposable suits. irritations to • Hands to be washed before eating food, or touching your face as operative bird droppings may contain ‘Salmonella’ (a bacterial infection causing severe diarrhea). • All breaks are to be taken away from the areas contaminated by bird droppings to avoid cross contamination. • Dampen down the bird droppings with water to prevent the creation of dust from the droppings. • Excessive bird droppings can cause a build-up of insects, which can transmit diseases and other infections, so the use of insect repellent is required if this is the case. • Operatives who have pre-existing respiratory conditions are to wear suitable dust masks such as the 3m 6000 series as required. • Operatives with weakened immune systems should not directly do tasks involving bird droppings. • all works involved with areas containing excessive bird droppings are to be supervised sufficiently ensuring controls are in place at all times. 21. • Virus / infection • Contraction • Operatives 3 5 15 • Cum nor Construction ltd has introduced a detailed 3 1 3

Control (Covi- of virus, • Other Covid-19 policy which will become part of everyday 19 / Influenza) illness contractors action to inhibit the spread of Covid-19 throughout our • Hospitalisatio • Members of the community or communities which we are involved with. n public • This policy has been created and approved under direct • Epidemic / • Family discussion with senior management and must be applied pandemic members throughout each site and each working day. effects • Prior to attending site, all operatives are required to • Serious complete a screening questionnaire’ & ‘CIF-C19 online illness to the induction’ and issue digitally to site management for elderly and review. Those failing the questionnaire will not be those with permitted on site. underlying • Each site will have a C19 Compliance Officer appointed conditions to ensure social distancing guidelines, rules and policies • Possible death are maintained at all times • Each site has been issued a revised Site Attendance Register which includes Covd-19 Screening Assessment questions to be carried out by the ‘Designated Person’ ‘C19 Compliance Officer. • Site start times are to be staggered to reduce the number of personnel entering and exiting the site at any one time Page 17 of 21 CCF800/23• Wash Rev 0hands using soap and warm water following the 20 second rule and drying sufficiently using disposable 22. • • • • Avoid eating outside of cleaned areas such as canteens. • Ensure that sites are not flooded with personnel, only the necessary amount of personnel are to be on site at any one time. Social distancing protocols as set out by the department of health are to be followed at all times. • Use hand sanitizing gel as required, but hand washing regularly is the best form of defence. 23. • Close Contact • Contraction • Operatives 3 5 15 • All site personnel are to be screened prior to enteringThe 3 2 6 working of virus, • Other ‘sitedesignated on a daily person’ basis / ‘C19 Compliance Officer’ will illness contractors • ensureAll personnel that all personnel are to be briefedwill abide daily by on social their distancing work • Transmission • Members of the ppracticesrotocols beingkeeping carried at a minimum out. 2m from other people at of Virus, public • allAny times. clos e contact working that is to be envisaged is to Illness • Family • be added into the daily briefing. Keep • Hospitalisatio members • workElimination areas clean, of close and contactwipe down working surface is tos such be preferred as door n handles,at all times hand rails and any surface that is touched by • Epidemic / • operatives,Engineerin withg controls a disinfectant where appropriate cleaner regularly are to be put in pandemic throughoutplace where the possible, day. and each action where close effects • Canteencontact si sand envisaged toilets to is beto cleanedhave a separate before and RA afterfor that • Serious breakstask. . All food waste to be placed in bins provided. illness to the •• BreakWhere time possible,s are to if be close staggered contact in working order to cannotminimize be the elderly and numberavoided, of pe personnelrsonnel are within to be the put canteen in pairs at with any tonehose time, pairs those with ensuringremaining all for personnel all close are contact 2m apart activities when sitting or underlying • staExclnding.usion zones including signage are to be put in place conditions • aroundRead anythe H&Sclose Newsletterscontact working that areareas issued to ensure on a regularother • Possible death basisoperatives which are will not give able current to enter informa the artionea, while on the ongoing virusmain outbreak.taining social distancing for all others on site at all • times,Cough illuminating / sneeze into Compliance a tissue or by your other elbow site members.and dispose • ofExclusion the tissue zones immediately including and signag washe your are tohands be put in place immediatelaround anyy closeafterward contacts. working areas to ensure other • operativesIf you feel are unwell not able and to have ente rany the ofarea, the whilefollowing, notifymaintaining your site social supervisor distancing immediately: for all others Coug onh, site Elevated at all Temtimes,perature, illuminating shortness Compliance of breath, by runny other nose. site members. •• AddPeopleitional who PP haveE such mild as Dustsymptoms masks, must safety stay glasses, at home andwhite self suits-isolate. and gloves are mandatory for close contact • workingEnsure and that must sites baree w nornot flooded at all times. with personnel, only • theUpon necessary completion amoun oft ofthe personnel task the white are to suits, be on dust site masks at any oneand time. gloves Social are to d istancingbe disposed proto of colsin a asseparate set out bin by clearlythe Page 18 of 21 CCF800/23 departmen labelled Rev 0 ont ofsite health for contaminated are to be followed materials at all times.

• Operatives are to wash their hands prior to commencing 24. • • • • All tools used are to be cleaned and disinfected after use, and at any other times where tools may be shared between personnel on site. If possible, tools are not to be shared on site, but must be cleaned at the end of each day and prior to commencing work the following days • Site start times are to be staggered to reduce the number of personnel entering and exiting the site at any one time

25. • Using Alcohol • Burns to • Operatives 4 3 12 • Safety Data sheets for Hand Sanitisers to be retained on 4 1 4 Based Hand hands and using the site detailing the concentration of alcohol in the HS Sanitiser skin hand • Dedicated Hand Sanitising (HS) Stations are to be set

• sanitiser and up at each site and works area operatives • HS Stations are to be out of direct sunlight. adjacent to • HS Stations are not to be placed in corridors or areas where entrances that form fire escape routes hand sanitiser is • Detailed instructions on the application and use of HS to be displayed at each HS station applied • Small amount of HS to be placed in the palm of hand and rubbed in sufficiently without stopping until hands are dry and the vapours disperse

• Hand sanitisers to be rubbed in and dry before leaving the HS Station ‘once dry, your hands are safe’

• Alcohol-based HS should be stored and used away from all heat and ignition sources, including (but not limited to) sparks; open flames; any types of electrical outlets, switches or equipment; and extreme heat.

• Hand sanitisers not to be stored or used within site working areas where possible sources of ignition are applicable

• Fire Blanket / extinguisher to be in place at HS stations

• Any HS with an alcohol content over 50% is to be treated as above

• Suitable first aid measures are to be in place on sites for • burns applicable from the misuse of the HS.

Page 19 of 21 CCF800/23 Rev 0 Specific Training Required:

Safe Pass CSCS card for plant Manual Handling CSCS card for scaffolding CSCS card for MEWPs CSCS card for cranes

Prepared by: Date: May 2020

Position: Engineer Issue no: Rev 00

Page 20 of 21 CCF800/23 Rev 0

We (the undersigned) have read and understood the attached Site Specific Method Statement and will comply with the specified requirements and control measures. If the work activity changes or deviates from that originally envisaged, we will seek further advice and request an amended method statement.

METHOD STATEMENT BRIEFING

Consultation, comment, A.O.B.

Name (print): Signature: Date:

Page 21 of 21 CCF800/23 Rev 0

Appendix C. Hydraulic Assessment

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 38 of 44

Culvert Lining Hydraulic Impact Assessment Knockakip Culvert: KY-N21-016 Transport Infrastructure Ireland

March 2020

Notice

This document and its contents have been prepared and are intended solely as information for Transport Infrastructure Ireland and use in relation to Knockakip culvert (KY-N21-016) WS Atkins Ireland Limited assumes no responsibility to any other party in respect of or arising out of or in connection with this document and/or its contents. This document has 26 pages including the cover.

Document history Document title: Knockakip Culvert: KY-N21-01616 Document reference: 5162160DG0005 Revision Purpose description Originated Checked Reviewed Authorised Date Rev 0.0 Issued for Review PA KC PC MJ March 2020

Client signoff Client Transport Infrastructure Ireland Project Culvert Lining Hydraulic Impact Assessment Job number 5162160

Client signature / date

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 2 of 26

Contents

Chapter Page 1. Introduction 5 2. Site Location 5 3. Existing Culvert Description 5 4. Proposed Works 6 5. Catchment Description 8 5.1. Flow Assessment 9 6. Development of Hydraulic Model 12 6.1. Hydraulic Model Selection 12 6.2. Hydraulic Modelling Assumptions 12 6.3. Topographical Survey Data 12 6.4. Channel & Associated Bank Roughness Values 12 6.5. Boundary Conditions 13 6.6. Hydraulic Model Development 13 7. Analysis of Model Simulations 16 7.1. Impact of Proposed Works 16 7.2. Impact of Climate Change 17 7.3. Impact on the Low Flows 17 8. Conclusions 17

Appendices 24 Appendix A. Survey Data 25

Tables Table 5-1 - Physical catchment descriptors from FSU portal 8 Table 5-2 - Design flows for Knockakip culvert – FSU method (rural estimates) 9 Table 5-3 - Catchments parameters (for use in IoH 124 and FSR 3) 10 Table 5-4 – Design flow estimates - IoH 124 method 10 Table 5-5 – Design flow estimates – FSR3 method 10 Table 5-6 - Comparison of Q100 estimates 11 Table 5-7 - Design flow estimates for hydraulic modelling - derived by IH124 method 11 Table 6-1 - Roughness values for the watercourse and Knockakip culvert 13 Table 6-2 - Cross section locations 14 Table 6-3 - Culvert details 15 Table 8-1 - Hydraulic model results (maximum stage) 19 Table 8-2 - Hydraulic model results (maximum depth) 21 Table 8-3 - Hydraulic model results for QMED (max. velocity) 23

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 3 of 26

Figures Figure 2-1 - Knockakip culvert location 5 Figure 3-1 - Knockakip culvert entrance (left) and inside view of the culvert (right) 6 Figure 3-2 - Plan showing the Knockakip culvert at right angles (approx.) to the upstream reach6 Figure 4-1 - Typical proposed culvert cross-sectional view 7 Figure 5-1 - Catchment upstream of Knockakip culvert 8 Figure 5-2 - Growth factors from FSU Portal 9 Figure 6-1 - Location of cross-sections 13 Figure 7-1 - Long section plot -Q100 16

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 4 of 26

1. Introduction

Atkins has been commissioned by Transport Infrastructure Ireland (TII) in respect of National Roads bridges maintenance for Munster and North West regions of Ireland. As a part of this,45 corrugated steel culverts are proposed to be lined with concrete. This assessment is being done for the Knockakip culvert (Structure Ref ID: KY-N21-016) to analyse the impact of proposed lining on the culvert’s flow capacity and its impacts on the flood levels upstream and downstream of the culvert.

2. Site Location

The Knockakip culvert (Structure Ref ID: KY-N21-016) is located at the national primary road N21 near Castleisland in the County of Kerry, approximately 5.5 km north of Castleisland town as indicated in Figure 2-1 below.

Figure 2-1 - Knockakip culvert location

3. Existing Culvert Description

The Knockakip culvert is circular in shape and made up of corrugated steel metal. The upstream face of the culvert has a diameter 2.80 m, and the downstream face has diameter of 2.96 m. The cross sections upstream and downstream of the culvert have the river wider than the width of the culvert. The banks are mostly covered with grass and forest trees. The current condition of the culvert is shown in Figure 3-1. No significant silt deposition is evident from the figure. Figure 3-2 shows that the watercourse takes approximately a 90-degree bend to enter the Knockakip culvert.

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 5 of 26

Figure 3-1 - Knockakip culvert entrance (left) and inside view of the culvert (right)

Figure 3-2 - Plan showing the Knockakip culvert at right angles (approx.) to the upstream reach

4. Proposed Works

The proposed works consist of cleaning out the silt from the existing culvert and lining the culvert with 150mm thick reinforced concrete for the bottom-third of the culvert, as detailed in Figure 4-1. However, for the purpose of hydraulic assessment, the culvert has been assumed to be lined at the top as well, as discussed further in Section 6.2.

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 6 of 26

Figure 4-1 - Typical proposed culvert cross-sectional view

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 7 of 26

5. Catchment Description

The Knockakip culvert lies on an unnamed tributary to River Owveg, approximately 5 km upstream of its confluence with River Owveg. The catchment is small with area < 1 km2 and is completely rural. The outlet node of the ungauged catchment as taken from the FSU portal is about 100 m downstream of the Knockakip culvert (Location number: 23_2047_1). The Knockakip culvert drainage catchment and the culvert location are shown in Figure 5-1. The catchment descriptors from the FSU Portal for the subject site are tabulated in Table 5-1. The main stream is steep as can be noted from a high value of main stream slope (S1085 = 39.7263 m/km). The catchment is flashy and has low permeability (BFISOIL = 0.3389), and there is no attenuation due to lakes/reservoirs (FARL = 1). This indicates that the catchment has a quick response to the rainfall events. There is one property identified at the edge of the catchment. The N21 which is a primary road lies within the catchment. However, there is no historical flooding reported in the area (floodmaps.ie web portal)

Approx. Culvert location property location Catchment area

FSU outlet node

Figure 5-1 - Catchment upstream of Knockakip culvert

Table 5-1 - Physical catchment descriptors from FSU portal Location Number 23_2047_1 Contributing Catchment Area 1.016 km2 BFISOIL 0.3389 SAAR 1410.03 mm FARL 1 DRAIND 0.979 km/km2 S1085 39.7263 m/km ARTDRAIN2 0 URBEXT 0 Centroid Distance 6.26 km

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 8 of 26

5.1. Flow Assessment For the assessment of inflows to the hydraulic model, three different methods for flow estimation viz. Flood Studies Update (FSU), FSR3 and IH124 were used. Since the catchment area is small (<25 km2), the FSU method is not applicable. However, to obtain the catchment parameters and for comparative purposes, the FSU method was also considered.

Flood Studies Update (FSU) Programme Method The catchment that drains to the Knockakip culvert is smaller than the catchment used in the FSU Portal to compute QMED, with the latter having an additional area of 0.11 km2 downstream of the N21 road. To reduce the flow pro-rata by area, a multiplying factor has been applied to the QMED estimate, which is computed as below: 푐푎푡푐ℎ푚푒푛푡 푎푟푒푎 표푓 푡ℎ푒 푐푢푙푣푒푟푡 0.906 퐹푙표푤 푟푒푑푢푐푡𝑖표푛 푓푎푐푡표푟 = = = 0.892 푐푎푡푐ℎ푚푒푛푡 푓푟표푚 퐹푆푈 푃표푟푡푎푙 1.016

The PCD (physical catchment descriptors) rural estimate of QMED for the downstream ungauged outlet from the FSU Portal is 0.8664 m3/s, hence for the culvert upstream, QMED is calculated as 0.772 m3/s (0.8664 x 0.892). As the catchment is completely rural, only the rural estimates were taken for computation.

FSU QMED Estimation As the subject site is ungauged, pivot catchments were reviewed for hydrological similarity. However, all the pivot catchments were very big (>100 km2), and the closest hydrological similarity value computed was 5.1262 (recommended value is 1), hence all pivot catchments were rejected. Thus, the PCD (physical catchment descriptors) QMED estimate was applied with the standard factorial error of 1.37 (for 68% confidence interval - upper limit) to ensure that the flows are not underestimated, and the final QMED values was calculated to be 1.058 m3/s (0.772 x 1.37).

FSU 100yr Design Flow Estimation Pooled flood frequency analysis was performed for the subject site in the FSU Portal, and the growth factor for various flood frequencies was estimated as shown in the Figure 5-2 below.

Figure 5-2 - Growth factors from FSU Portal

The growth factor of 1.92 for 100-year design flood was used for the assessment. The upper limit of the standard error associated with growth factor in pooling analysis for EV1 distribution is 2%, and hence the error adjusted growth factor is 1.958. Finally, the 100-year flood (Q100) is calculated as 2.072 m3/s. A 20% uplift for climate change was applied to obtain 100-year flood with 20% climate change (Q100C1) as 2.486 m3/s. Table 5-2 summarizes the design flows for Knockakip culvert from the FSU analysis.

Table 5-2 - Design flows for Knockakip culvert – FSU method (rural estimates) Event Design flood (m3/s) QMED 1.058 Q100 2.072 Q100C1 2.486

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 9 of 26

Institute of Hydrology Report No. 124 Method The Institute of Hydrology (IoH) Report 124 method was used for comparative purposes to determine the mean annual flow (QBAR), hence Q100 and Q100C1 were estimated for Knockakip culvert catchment. The Institute of Hydrology Report No.124 (IH 124) 3 parameter equation to determine mean annual flow (QBAR) is shown below: 0.89 1.17 2.17 푄퐵퐴푅푟푢푟푎푙 = 0.00108 퐴푟푒푎 푆퐴퐴푅 푆푂퐼퐿

A desktop study was carried out to determine the values of the parameters for the Knockakip culvert catchment. The soil for both the catchments was classified into Class 5 based on maps from the UKSUDS website. The description of parameters of the IoH 3-variable equation and the determined values for the catchment are listed in Table 5-3.

Table 5-3 - Catchments parameters (for use in IoH 124 and FSR 3) Parameter Description Values Area Catchment area (km2) 0.906 SAAR Standard Average Annual Rainfall (mm) 1410.03 SOIL Soil index (no units) 0.5

The values listed above were applied to the calculations, and the QBAR was calculated. Further, the standard factorial error of 1.65 (for 68% confidence interval) was applied and the estimate is shown in Table 5-4. For IoH 124 method, the growth factor for 1 in 100-year flood is 1.96 (Flood Studies Report). Thus, Q100 and Q100C1 are estimated and listed in Table 5-4.

Table 5-4 – Design flow estimates - IoH 124 method Event Flow (m3/s) QBAR 1.754 Q100 3.439 Q100C1 4.125

FSR3 Analysis The FSR 3-variable equation for estimating mean annual flood (QBAR) for an ungauged rural catchment is: 푄퐵퐴푅 (푟푢푟푎푙) = 0.00066 퐴푟푒푎0.92푆퐴퐴푅1.22 푆푂퐼퐿2.0

The catchment parameters listed in Table 5-3 were used and the QBAR was calculated with a factorial error of 1.58 for 68% confidence interval) applied to the estimate and is listed in Table 5-5. For FSR3 method, the growth factor for 1 in 100-year flood is 1.96 (Flood Studies Report). Thus, Q100 and Q100C1 are estimated and listed in Table 5-5.

Table 5-5 – Design flow estimates – FSR3 method Event Flow (m3/s) QBAR 1.654 Q100 3.243 Q100C1 3.891

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 10 of 26

The flows determined using the three methods discussed in Sections 5.1.1, 5.1.2 and 5.1.3 were reviewed. The FSU analysis was carried out just for comparative purposes as it is applicable on catchment areas greater than 25 km2. The comparison of Q100 estimates (Table 5-6) from the other two different methods are comparable, thereby indicating the robustness and reliability of estimates for the study area. The FSR3 and IH124 methods are better suited for catchment sizes greater than 0.4 km2.

Table 5-6 - Comparison of Q100 estimates Event Flow (m3/s)

FSU 2.072

IH124 3.438

FSR3 3.243

IH124 method gives the conservative estimate for Q100 and is also relevant for the Knockakip catchment which has an area of 0.9 km2. Therefore, the flows computed using IH124 methodology was taken forward for hydraulic modelling. The QMED event corresponds to the median flood flow (1 in 2-year return period) and is a reasonable estimate for low flows as there is 50% exceedance probability. The QMED flow for IH124 method is estimated as: 푄퐵퐴푅 푄푀퐸퐷 = ⁄1.07 Thus, QMED is computed as (1.754/1.07) = 1.639 m3/s. The summary of flows taken forward for hydraulic modelling is listed in Table 5-7.

Table 5-7 - Design flow estimates for hydraulic modelling - derived by IH124 method Event Flow (m3/s)

QMED 1.639

Q100 3.438 Q100C1 4.125

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 11 of 26

6. Development of Hydraulic Model

A 1D hydraulic model was developed for the tributary with the Knockakip culvert added. The purpose was to estimate the impact of the proposed lining on the culvert capacity, change in predicted water levels upstream and downstream, and changes in the velocities during the low flow events. Due to the uncertainty and limitations in hydrologic and hydraulic modelling along assumptions as listed in Section 6.2, the reader is advised to exercise caution and interpret the results as indicative changes in river channels levels due to the proposed works. The results should not be used for any direct assessment of flood risk in the region. 6.1. Hydraulic Model Selection Flood Modeller v4.5 was selected to construct the 1D hydraulic model for the study area. 6.2. Hydraulic Modelling Assumptions The following are the main assumptions in the hydraulic model development: 1. The channel roughness has been defined based on land use information provided in survey drawings 2. The shape of the culvert is assumed to be circular based on the survey information provided 3. Based on the information from survey, the culvert inlet unit was assumed to be a square headwall type (i.e. with no wingwalls), corresponding to circular corrugated metal conduits. 4. For model simplification, lining is assumed to be done all round inside the culvert 5. No silt deposition and no significant blockage at all conditions has been assumed for the modelled scenarios 6. A 90-degree bend with a head loss coefficient of 0.5 has been assumed at the upstream face of the culvert, based on the survey information. 6.3. Topographical Survey Data Topographical survey data from Murphy Surveys (2019) has been used to develop the hydraulic model. The data includes river cross sections and culvert and deck details. The survey covers the watercourse for a length of 241m upstream of the culvert, and 220 m downstream of the culvert. The extent of the survey and the survey data received are shown in Appendix A of the report. 6.4. Channel & Associated Bank Roughness Values No roughness values were provided with the survey data. Therefore, based on the survey information on the land use type, the roughness values were assigned. The channel consisted mostly of stones/ gravel and hence a Manning’s ‘n’ of 0.04 was used. For the banks, ‘n’ value of 0.055 and 0.06 was assigned to land use classes corresponding to grass/bog and forestry respectively. In the proposed scenario, the culvert is assumed to be lined entirely with reinforced concrete. Table 6-1 below lists the assigned Manning’s roughness values in the hydraulic models.

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 12 of 26

Table 6-1 - Roughness values for the watercourse and Knockakip culvert Watercourse Features Manning’s Roughness River bed 0.040 River banks 0.055 and 0.060 Culvert bottom (existing) 0.028 Culvert top (existing) 0.028 Culvert bottom (proposed) 0.012 Culvert top (proposed) 0.012

6.5. Boundary Conditions A constant flow boundary was applied at the upstream and a normal depth boundary was applied as the downstream boundary conditions. 6.6. Hydraulic Model Development A total channel length of 486 m along the unnamed tributary to the River Owveg was modelled. This includes river cross sections, the Knockakip culvert and the boundaries. Interpolated sections were added to the hydraulic model so that spacing between the cross-sections follows the rule of thumb, suggested by the software guidance notes for a given slope and typical depth (Samuels P.G, 1990). Also, Section KNK_11 provided in the survey data was removed as the section was not representative of the typical channel and banks in the watercourse. The location of cross sections used for hydraulic model development is shown in Figure 6-1. The cross sections and their relative positions to the culvert is tabulated in Table 6-2.

Culvert location

Figure 6-1 - Location of cross-sections

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 13 of 26

Table 6-2 - Cross section locations Cross section label Relative distance to Knockakip culvert KNK_17 241 m from upstream face of culvert KNK_17In1 222 m from upstream face of culvert KNK_17In2 203 m from upstream face of culvert KNK_16 184 m from upstream face of culvert KNK_15 136 m from upstream face of culvert KNK_15In1 119 m from upstream face of culvert KNK_15In2 102 m from upstream face of culvert KNK_15In3 85 m from upstream face of culvert KNK_15In4 68 m from upstream face of culvert KNK_15In5 51 m from upstream face of culvert KNK_14 34 m from upstream face of culvert KNK_13 13 m from upstream face of culvert KNK_12 9 m from upstream face of culvert KNK_12c upstream face of culvert KNK_10 downstream face of culvert KNK_09 4 m from downstream face of culvert KNK_08 12 m from downstream face of culvert KNK_07 18 m from downstream face of culvert KNK_06 42 m from downstream face of culvert KNK_05 58 m from downstream face of culvert KNK_05In1 72 m from downstream face of culvert KNK_05In2 87 m from downstream face of culvert KNK_04 101 m from downstream face of culvert KNK_03 115 m from downstream face of culvert KNK_03In1 132 m from downstream face of culvert KNK_03In2 150 m from downstream face of culvert KNK_02 167 m from downstream face of culvert KNK_02In1 185 m from downstream face of culvert KNK_02In2 202 m from downstream face of culvert KNK_01 220 m from downstream face of culvert

The survey data was used to develop a ‘baseline’ model representing the existing situation. The ‘baseline’ hydraulic model was further used to create a ‘proposed’ scenario model, where lining is provided in the culvert. Below are the changes in the ‘proposed’ scenario model. • Manning’s roughness value was updated to 0.012 for the bottom and top of the culvert to represent the concrete liner, considering that no silt will be deposited (also see assumption-5 under Section 6.2.) • The invert levels at the entry and exit, and diameter of the culvert were updated to reflect the 150mm thick concrete lining.

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 14 of 26

Culvert details before and after the lining are shown in Table 6-3.

Table 6-3 - Culvert details Before lining After lining 150mm concrete Invert level Soffit level Diameter Invert level Soffit level Diameter (mAD) (mAD) (m) (mAD) (mAD) (m) Culvert 228.337 231.139 2.802 228.487 230.989 2.502 entrance Culvert exit 227.81 230.768 2.958 227.960 230.618 2.658 Culvert length 25 m 25 m

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 15 of 26

7. Analysis of Model Simulations

The baseline and proposed models were simulated under steady state mode for the following scenarios: • Impact of proposed works (Q100) • Impact of climate change (Q100C1) • Low flow condition (QMED) 7.1. Impact of Proposed Works The baseline and proposed hydraulic models were simulated for 1 in 100-year event to predict the impacts of proposed works. The maximum stage and depth results from hydraulic modelling for Q100 are presented in Table 8-1 and Table 8-2 respectively. A long section plot indicating the maximum stages along the watercourse for 1 in 100-year event is also shown in Figure 7-1.

Figure 7-1 - Long section plot -Q100

The results demonstrate that the impact due to lining is predicted only in the reach upstream of the culvert. For the 1 in 100-year event, the maximum increase in the water level is 258 mm. Of this 258 mm increase in water levels, 150 mm increase is due to raising the culvert invert levels by 150mm by installing the proposed lining. There is enough freeboard available (minimum 2.03m) in the proposed scenario, and the proposed works do not affect the water levels in the reach beyond 68 m upstream of the culvert. The N21 road is also not overtopped due to the lining works. There is one property identified at the edge of the catchment. As the flows are remaining in the channel, the property is not affected due to lining.

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 16 of 26

Hence, the proposed works to the Knockakip culvert will not have a significant hydraulic impact on the tributary and its main watercourse.

7.2. Impact of Climate Change The baseline and proposed hydraulic models were simulated for 1 in 100-year plus 20% climate change event. The purpose of these simulations was to assess whether the proposed lining works to the Knockakip culvert will have any hydraulic impacts under a climate change scenario. The maximum stage and depth results from hydraulic modelling for Q100C1 are presented in Table 8-1 and Table 8-2 respectively. The results of the simulation indicate that the maximum increase in the water level is 271 mm, of which 150 mm of the increase is due to raised invert levels of the culvert in the proposed scenario. There are no changes predicted downstream of the culvert. For the climate change scenario, which models the worst-case scenario for the catchment, there is enough freeboard available (1.98 m) for the proposed scenario. The maximum water level within the culvert remains at less than one-third of its opening height. Hence, the results indicate that no extra allowances are needed during proposed works to account for a climate change event. Therefore, the assumption of an all-round lining to the culvert does not impact the hydraulic results. There is one property identified at the edge of the catchment. As the flows are remaining in the channel, the property is not affected due to lining. 7.3. Impact on the Low Flows To assess the availability of water for fish passage during low flows, the hydraulic model was assessed for the QMED event. The flow depth is summarised in Table 8-2 and the velocity in Table 8-3. The modelling results in Table 8-2 suggest that for the baseline scenario, the depth of flow is 482 mm at the upstream and 280 mm at the downstream end of the culvert. The corresponding flow velocities are in the range of 2.32 m/s to 4.96 m/s for the upstream and downstream ends respectively (Table 8-3). From Table 8-2, it can be noted that the proposed works causes the flow depth at the upstream end of the culvert to reduce by 151 mm, to 331 mm. The corresponding increase in velocity is from 2.32 m/s to 4.25 m/s. At the downstream, the flow depth remains unchanged at 280 mm, with a small increase in velocity from 4.96 to 5.25 m/s. From the above analysis, the proposed works is not expected to cause significant worsening of the present situation. However, measures to reduce the exit velocity and increase the water levels at the channel immediately downstream of the culvert should be considered in discussion with Fisheries Ireland. This could be achieved by placing large rocks and providing transition pools at the downstream to drown the culvert inlet.

8. Conclusions

Based on the hydrology estimations, and further hydraulic model assessment for the baseline and proposed scenarios, following conclusions are made: • This hydraulic capacity assessment has been prepared in consideration of the requirements under Section 50 of the Arterial Drainage Act 1945. • IH124 methodology has been used to derive flows for QMED, Q100 and Q100C1 and their magnitudes are 1.639 m3/s, 3.438 m3/s and 4.125 m3/s respectively. • The proposed works, due to the reduced flow area and higher invert levels results in increase in water levels at upstream of the Knockakip culvert. No changes in the maximum water levels are predicted at the downstream. • For the three events analysed, the predicted increase in the maximum stage is in the range of 215 mm to 271 mm. The change due to the proposed works is within the OPW limit of 300 mm. • A minimum freeboard of 1.90 m is available in the culvert under all conditions, and this meets the OPW minimum threshold criteria

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 17 of 26

• During low flow conditions, there is sufficient depth of flow, above the recommended 150 mm water depth for fish passage. The proposed works is not expected to cause significant worsening of the present situation with regards to fish passage. • To aid in smooth fish movement during low flows, placing large rocks and providing transition pools should be considered at the channel immediately downstream of the culvert in discussion with Fisheries Ireland. • No nearby properties are expected to be affected in the proposed scenario.

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 18 of 26

Table 8-1 - Hydraulic model results (maximum stage) Maximum stage for different return periods (in mAD) Node Label Chainage QMED event 1 in 100-year event 1 in 100-year plus 20% climate change (upstream to (m) event downstream) Baseline Proposed Difference Baseline Proposed Difference Baseline Proposed Difference KNK_17 0 234.265 234.265 0.000 234.430 234.430 0.000 234.486 234.486 0.000 KNK_17In1 19 233.553 233.553 0.000 233.759 233.759 0.000 233.826 233.826 0.000 KNK_17In2 38 232.944 232.944 0.000 233.192 233.192 0.000 233.262 233.262 0.000 KNK_16 57 232.475 232.475 0.000 232.675 232.675 0.000 232.728 232.728 0.000 KNK_15 105 231.340 231.340 0.000 231.489 231.489 0.000 231.531 231.531 0.000 KNK_15In1 122 230.966 230.966 0.000 231.126 231.126 0.000 231.162 231.160 -0.002 KNK_15In2 139 230.580 230.580 0.000 230.747 230.747 0.000 230.793 230.793 0.000 KNK_15In3 156 230.202 230.202 0.000 230.377 230.377 0.000 230.423 230.423 0.000 KNK_15In4 173 229.824 229.824 0.000 230.006 230.007 0.001 230.052 230.062 0.010 KNK_15In5 190 229.451 229.467 0.016 229.691 229.812 0.120 229.789 229.930 0.141 KNK_14 207 229.288 229.388 0.100 229.633 229.787 0.154 229.740 229.915 0.175 KNK_13 228 229.168 229.324 0.156 229.520 229.728 0.208 229.632 229.857 0.224 KNK_12 232 229.154 229.318 0.164 229.506 229.722 0.216 229.619 229.851 0.231 KNK_12c 241 229.075 229.291 0.215 229.436 229.693 0.258 229.551 229.821 0.271 KNK_Cu* 241 228.819 228.818 -0.001 229.028 228.962 -0.066 229.093 229.006 -0.087 KNK_Cd* 266 228.090 228.240 0.150 228.233 228.388 0.154 228.279 228.434 0.156 KNK_10 266 227.428 227.428 0.000 227.527 227.527 0.000 227.559 227.559 0.000 KNK_09 270 226.822 226.822 0.000 227.001 227.001 0.000 227.053 227.053 0.000 KNK_08 278 226.683 226.683 0.000 226.921 226.921 0.000 226.982 226.982 0.000 KNK_07 284 226.541 226.541 0.000 226.793 226.793 0.000 226.849 226.849 0.000 KNK_06 308 225.954 225.954 0.000 226.231 226.231 0.000 226.289 226.289 0.000 KNK_05 324 225.675 225.675 0.000 225.899 225.899 0.000 225.978 225.978 0.000

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 19 of 26

Table 8- 1 (continued) -Hydraulic modelling results (maximum stage) Maximum stage for different return periods (in mAD) Node Label Chainage QMED event 1 in 100-year event 1 in 100-year plus 20% climate (upstream to (m) change event downstream) Baseline Proposed Difference Baseline Proposed Difference Baseline Proposed Difference KNK_05In1 338.33 225.262 225.262 0.000 225.505 225.505 0.000 225.597 225.597 0.000 KNK_05In2 352.66 224.855 224.855 0.000 225.114 225.114 0.000 225.213 225.213 0.000 KNK_04 366.99 224.510 224.510 0.000 224.756 224.756 0.000 224.825 224.825 0.000 KNK_03 380.99 224.331 224.331 0.000 224.430 224.430 0.000 224.460 224.460 0.000 KNK_03In1 398.32 223.908 223.908 0.000 224.035 224.035 0.000 224.079 224.079 0.000 KNK_03In2 415.65 223.492 223.492 0.000 223.704 223.704 0.000 223.771 223.771 0.000 KNK_02 432.98 222.901 222.901 0.000 223.222 223.222 0.000 223.295 223.295 0.000 KNK_02In1 450.65 222.212 222.212 0.000 222.449 222.449 0.000 222.530 222.530 0.000 KNK_02In2 468.32 221.633 221.633 0.000 221.828 221.828 0.000 221.889 221.889 0.000 KNK_01 485.99 221.109 221.109 0.000 221.282 221.282 0.000 221.338 221.338 0.000

*Corresponds to culvert nodes in hydraulic model

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 20 of 26

Table 8-2 - Hydraulic model results (maximum depth) Maximum depth for different return periods (m) Node Label Chainage QMED event 1 in 100-year event 1 in 100-year plus 20% climate change (upstream to (m) event downstream) Baseline Proposed Difference Baseline Proposed Difference Baseline Proposed Difference KNK_17 0 0.338 0.338 0.000 0.503 0.503 0.000 0.559 0.559 0.000 KNK_17In1 19 0.425 0.425 0.000 0.631 0.631 0.000 0.698 0.698 0.000 KNK_17In2 38 0.615 0.615 0.000 0.863 0.863 0.000 0.933 0.933 0.000 KNK_16 57 0.945 0.945 0.000 1.145 1.145 0.000 1.198 1.198 0.000 KNK_15 105 0.605 0.605 0.000 0.754 0.754 0.000 0.796 0.796 0.000 KNK_15In1 122 0.592 0.592 0.000 0.752 0.752 0.000 0.788 0.786 -0.002 KNK_15In2 139 0.565 0.565 0.000 0.733 0.733 0.000 0.778 0.778 0.000 KNK_15In3 156 0.548 0.548 0.000 0.723 0.723 0.000 0.769 0.769 0.000 KNK_15In4 173 0.531 0.531 0.000 0.713 0.714 0.001 0.759 0.768 0.010 KNK_15In5 190 0.518 0.534 0.016 0.758 0.878 0.120 0.856 0.997 0.141 KNK_14 207 0.715 0.815 0.100 1.060 1.214 0.154 1.167 1.342 0.175 KNK_13 228 0.891 1.047 0.156 1.243 1.451 0.208 1.355 1.580 0.224 KNK_12 232 0.939 1.103 0.164 1.291 1.507 0.216 1.404 1.636 0.231 KNK_12c 241 0.748 0.964 0.215 1.109 1.366 0.258 1.224 1.494 0.271 KNK_Cu* 241 0.482 0.331 -0.151 0.691 0.475 -0.216 0.756 0.519 -0.237 KNK_Cd* 266 0.280 0.280 0.000 0.423 0.428 0.004 0.469 0.474 0.006 KNK_10 266 0.259 0.259 0.000 0.358 0.358 0.000 0.390 0.390 0.000 KNK_09 270 0.406 0.406 0.000 0.585 0.585 0.000 0.637 0.637 0.000 KNK_08 278 0.475 0.475 0.000 0.713 0.713 0.000 0.774 0.774 0.000 KNK_07 284 0.621 0.621 0.000 0.873 0.873 0.000 0.929 0.929 0.000 KNK_06 308 0.855 0.855 0.000 1.132 1.132 0.000 1.190 1.190 0.000

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 21 of 26

Table 8-2 (continued)- Hydraulic model results (maximum depth)

Node Label Maximum depth for different return periods (m) (upstream to Chainage QMED event 1 in 100-year event 1 in 100-year plus 20% climate change downstream) (m) event

Baseline Proposed Difference Baseline Proposed Difference Baseline Proposed Difference KNK_05 324 0.589 0.589 0.000 0.813 0.813 0.000 0.892 0.892 0.000 KNK_05In1 338.33 0.557 0.557 0.000 0.799 0.799 0.000 0.891 0.891 0.000 KNK_05In2 352.66 0.531 0.531 0.000 0.790 0.790 0.000 0.888 0.888 0.000 KNK_04 366.99 0.566 0.566 0.000 0.812 0.812 0.000 0.881 0.881 0.000 KNK_03 380.99 0.803 0.803 0.000 0.902 0.902 0.000 0.932 0.932 0.000 KNK_03In1 398.32 0.810 0.810 0.000 0.938 0.938 0.000 0.982 0.982 0.000 KNK_03In2 415.65 0.825 0.825 0.000 1.038 1.038 0.000 1.104 1.104 0.000 KNK_02 432.98 0.665 0.665 0.000 0.986 0.986 0.000 1.059 1.059 0.000 KNK_02In1 450.65 0.458 0.458 0.000 0.695 0.695 0.000 0.776 0.776 0.000 KNK_02In2 468.32 0.361 0.361 0.000 0.556 0.556 0.000 0.617 0.617 0.000 KNK_01 485.99 0.320 0.320 0.000 0.493 0.493 0.000 0.549 0.549 0.000

*Corresponds to culvert nodes in hydraulic model

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 22 of 26

Table 8-3 - Hydraulic model results for QMED (max. velocity)

Chainage Maximum velocity in m/s Node Label (upstream to (m)

downstream) Baseline Proposed Difference

KNK_17 0 1.977 1.977 0.000

KNK_17In1 19 2.104 2.104 0.000

KNK_17In2 38 2.044 2.044 0.000

KNK_16 57 1.483 1.483 0.000 KNK_15 105 1.239 1.239 0.000 KNK_15In1 122 1.233 1.233 0.000 KNK_15In2 139 1.296 1.296 0.000 KNK_15In3 156 1.307 1.307 0.000 KNK_15In4 173 1.299 1.299 0.000

KNK_15In5 190 1.275 1.203 -0.072

KNK_14 207 0.656 0.506 -0.150

KNK_13 228 0.978 0.726 -0.251

KNK_12 232 0.856 0.645 -0.212

KNK_12c 241 1.060 0.696 -0.363 KNK_Cu* 241 2.317 4.248 1.931 KNK_Cd* 266 4.959 5.247 0.288 KNK_10 266 3.405 3.405 0.000 KNK_09 270 1.245 1.245 0.000 KNK_08 278 1.406 1.406 0.000 KNK_07 284 1.607 1.607 0.000

KNK_06 308 1.629 1.629 0.000

KNK_05 324 1.972 1.972 0.000

KNK_05In1 338.33 1.977 1.977 0.000

KNK_05In2 352.66 1.960 1.960 0.000

KNK_04 366.99 1.673 1.673 0.000 KNK_03 380.99 0.853 0.853 0.000 KNK_03In1 398.32 0.992 0.992 0.000 KNK_03In2 415.65 1.184 1.184 0.000 KNK_02 432.98 2.429 2.429 0.000 KNK_02In1 450.65 2.168 2.168 0.000 KNK_02In2 468.32 1.932 1.932 0.000

KNK_01 485.99 1.670 1.670 0.000

*Corresponds to culvert nodes in hydraulic model

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 23 of 26

Appendices

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 24 of 26

Appendix A. Survey Data

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 25 of 26

GENERAL NOTES 100 1. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE

2. ONLY WRITTEN DIMENSIONS SHALL BE USED. NO DIMENSIONS SHALL BE SCALED FROM THE DRAWINGS

3. ALL LEVELS ARE IN METRES AND ARE TO MALIN HEAD DATUM

4. ALL COORDINATES ARE IN METRES AND ARE TO IRISH TRANSVERSE MERCATOR Section 1-01 5. DRAWINGS ARE TO BE READ IN CONJUNCTION WITH THE SPECIFICATION

DRAWING NOTES 231.38

231.44

231.52 231.54 Section 1. FOR RIVER CROSS SECTIONS 1-01 TO 1-17, REFER

231.02 TO iO GEOMATICS DRAWING 231.64 10 1675_CS_Knoc_Rev1.DWG

231.74 1-02

231.67 0

231.83

231.67

231.88 231.56 231.86

231.54 231.40 Abbeyfeale 231.96

232.01

232.07

To 231.99 Section 1-03 232.14

232.02

232.16 231.61 231.85

232.05 A1

231.87 232.25

232.31

232.36

232.40

232.11 Section 1-04

232.39

232.45 232.50

232.39 232.11

232.61

232.59 232.31

232.72

232.71

232.78

232.74 232.85 Flow

232.73

232.59

232.96

232.57 232.99 232.99

233.00 232.98

232.52 232.94

233.07 232.94

233.21

233.13 233.21 233.17 232.86

233.35

233.41

232.84 233.36

233.53

233.50 233.47 233.03

233.59 233.47

233.62 233.66

233.66 233.18

233.56

233.74

Section DO NOT SCALE Section KNOCKAKIP CULVERT 233.64 UNNAMED STREAM

Section 1-13 233.69

229.87 233.27 233.90

Top of Fence 228.45 Bottom of Fence (KY-N21-016.00) Water Level Date of survey=Friday, October 25, 2019 233.94 233.62 228.33228.62 228.37 228.40 228.61 228.70 233.88 1-12 233.87 233.34 228.34 234.07

228.37 228.34 234.06 Pipe Invert 232.83 228.22 231.14 Pipe Soffit 228.60 228.14 233.88 233.82 228.15 228.32 1-14 228.11 234.10 228.16 234.20 228.49 228.54 234.14 234.16 234.23 233.91 228.42 228.14 Water Level Date of survey=Friday, October 25, 2019 234.27 234.16 228.25

228.82 233.90 233.59 228.45 234.27 233.00 228.22 234.13 233.55 228.30 228.53 Top of Wall

229.91 234.29 234.07

229.53 229.00 234.15 234.40 234.39 233.55 228.42 234.13 Water Level Date of survey=Friday, October 25, 2019 234.41 234.05 233.65 234.48 Bottom of Fence Top of Fence

234.39 233.28 234.36 233.18 233.98 233.48 234.36 233.75 234.47 233.41

233.97

233.80 233.91 233.73 234.52 234.26

234.48

Top of Wall 234.65 233.82 Base of crash barrier Section 1-05 Top of crash barrier 233.39 Top of Fence 227.68 Bottom of Fence Circular Opening 227.24

230.79

1-15 Section 227.93 234.57 Pipe Soffit 234.61 Water Level 233.80 Date of survey=Friday, October 25, 2019 234.33 227.87 227.07 227.30 Pipe Invert 234.27 227.21 234.65 226.70 233.89 Water Level Date of survey=Friday, October 25, 2019 226.75 226.57 234.79 234.00 227.81 234.43 Pipe Invert 226.67 233.47 diam=0.11 226.41 Water Level 227.84 Date of survey=Friday, October 25, 2019 226.81 226.56 234.68 234.72 227.46 226.58

Base of crash barrier Top of crash barrier

233.23 Pipe Invert 226.55 diam=0.11 234.04 229.97 226.49 226.51 226.23 234.05 228.86 233.86 233.41 229.48 227.08

233.42

Section 1-11 234.84 226.47 226.29 234.82 227.98 228.31 Pipe Invert 226.87 226.33 234.63 diam=0.15

Bottom ofTop Fence of Fence 226.39 233.17 228.63 Water Level Pipe Invert 228.57 233.57 226.81 Date of survey=Friday, October 25, 2019 233.04 diam=0.37 Pipe Invert diam=0.1

234.92 234.90

227.91

234.01 234.32 234.99 235.01 231.61 234.98 Flow 234.79 234.14 231.26

235.07

235.12

231.32

234.41

235.20 235.16

235.35 234.63 235.28 235.25

235.06

235.35

235.34 234.51

235.22

235.46 1-10 Section 1-06

235.45 235.25

234.81

234.91

235.54

235.62

235.37 235.25 235.25 235.62

235.64 Section

235.71 1-08 235.72

235.54 UNNAMED STREAM 234.97 Section 1-09

235.16

235.82

235.89

235.68

235.97 235.92 Section

235.38

236.03

236.01 235.82 Section 1-07

236.09

235.41

236.08

235.33

235.93 235.58

236.16 236.14

236.29

236.01

235.98 236.23

236.26

236.35

236.02

236.19

236.14 235.72

236.54 236.45 236.47 235.62

236.20

236.25

235.95

236.56

236.23 236.39 N21 NATIONAL PRIMARY ROAD

236.67

236.67

236.40

236.81

236.52

236.46

236.76 236.03 236.78

236.51

236.56

236.17

236.67

236.29 236.96 236.61

236.89

236.90

236.65

236.21

236.78

236.70

236.34 To Castleisland

236.70 236.49

ISSUED FOR REVIEW

© ORDNANCE SURVEY IRELAND LICENSE NR. to 0203.dwg AR 0082518. ORDNANCE SURVEY IRELAND & TRANSPORT INFRASTRUCTURE KNOCKAKIP CULVERT (KY-N21-016.00) GOVERNMENT OF IRELAND IRELAND (TII) REMEDIAL WORKS ATKINS NOT TO BE HELD LIABLE FOR THE USE - 3:49pm EXISTING SITE LAYOUT PLAN OF THIS DATA ON ANY PROJECT OTHER THAN THE MUNSTER BRIDGES TERM MAINTENANCE CONTRACT NR.3 PROJECT AOS MG MJ

29, 2019 1:500 MUNSTER BRIDGES TERM 18/11/19 18/11/19 18/11/19 Nov - ISSUED FOR REVIEW AOS 11/19 MG MJ MAINTENANCE CONTRACT NR.3 Date: File: 5162555-HTR-DR-0200 P 5162555 / HTR / DR / 0200 -

V:\5162555\6 Dwgs-Graphics\61 AutoCad\5162555-HTR-DR-0200 to 0203.dwg 233.14 233.18 GENERAL NOTES 100

233.21 1. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE

233.13 233.27 233.21 233.17 233.17 232.86 2. ONLY WRITTEN DIMENSIONS SHALL BE USED. NO DIMENSIONS SHALL BE SCALED FROM THE DRAWINGS

233.35 3. ALL LEVELS ARE IN METRES AND ARE TO MALIN 233.34 HEAD DATUM 232.62 233.41

233.41 233.44 4. ALL COORDINATES ARE IN METRES AND ARE TO IRISH TRANSVERSE MERCATOR 232.84 233.36 5. DRAWINGS ARE TO BE READ IN CONJUNCTION WITH 233.31 THE SPECIFICATION 233.53 232.41 233.42 233.55

233.50 233.47 233.59 233.03 231.38 233.59 233.47

233.68

10 EXISTING FENCING 232.26 233.71 233.62 233.66 233.69 233.33 233.66

0 233.78 C 233.18 233.56

0203 233.74

233.72 232.06

233.64 229.74

A1 229.85 233.96233.97 233.69 229.87 233.27 A 233.90 232.65 229.26 231.46 0202 230.64 Top of Fence 228.45 Bottom of Fence Water Level 233.97 EXISTING CONCRETE APRON Date of survey=Friday, October 25, 2019 233.94 233.62 228.33228.62 228.37 231.80 SLAB ON SIDE SLOPE 228.40 228.63 228.61 233.88 228.70228.71228.80 232.88 233.87 233.34 228.36228.55 231.80 233.69 231.22 230.79 228.34 228.34 234.07 234.12 233.96 228.37 228.33228.34 234.06 EXISTING MASONRY PARAPET WALL Pipe Invert 232.83 228.22 231.14 EXISTING ROAD Pipe Soffit 228.60 228.14 228.34 232.69 231.91 233.88 233.82 SAFETY BARRIER 228.15 228.32228.54 234.15 232.79 232.16 228.11 232.99 234.10 231.80 228.16 234.21 230.61 234.20 228.49 228.54 234.14 234.16 233.30 229.62 234.22 234.23 233.91 228.42 228.14 231.63 Water Level 229.24228.84 Date of survey=Friday, October 25, 2019 228.47 228.68 234.27 228.22 234.16 231.79 228.25228.22228.64 230.57 228.82 233.90 233.88 228.34 232.74 233.59 234.27 233.00 228.45 228.56 234.13 228.22 EXISTING FENCING 230.39 228.85 233.55 228.30 234.29 228.53 Top of Wall

DO NOT SCALE 228.90228.91 229.89229.82 229.70 229.91 234.36 228.96 229.09 234.29 234.07 234.10 228.71 231.72 229.53 230.65 UNNAMED STREAM 228.68228.65 229.00 234.15 234.40 228.28 234.39 228.42 233.55 228.28 231.12 234.13 234.25 KNOCKAKIP CULVERT 228.38Water Level 232.91 Date228.77 of survey=Friday, October 25, 2019 228.82 231.80 234.41 234.05 (KY-N21-016.00) 228.88 234.40 233.65 230.56 234.48 233.80 Bottom of Fence 229.17 232.47 Top of Fence 229.96 229.44 232.65 234.36 234.39 233.28 232.15 229.50 230.21 233.48 233.18231.97 233.80 233.98 229.16 233.48 231.25 230.75 234.36 233.75 234.47 233.41 231.78

233.97 233.96 234.44 233.80 230.12 Flow 233.91 234.06 231.58 234.53 233.73 232.59 234.58 234.52 234.50 229.38 229.16 234.26

234.48 234.58 234.13 230.92 234.08 230.39

Top of Wall 228.86 234.65 233.82 228.34 Base of crash barrier 234.23 Top of crash barrier 234.28 233.39 Top of Fence 227.78227.68 Bottom of234.28 Fence Circular Opening 234.67 227.24 230.79 EXISTING RAISED 227.93227.28 EXISTING MASONRY PARAPET WALL 234.57 Pipe Soffit 227.99 228.85 234.61 Water Level 233.80 Date of survey=Friday, October 25, 2019 227.83 CONCRETE VERGE 234.70 227.26 227.07 227.56 234.33 227.87 228.76 227.30 Pipe Invert 228.57 234.27 234.43 227.21 234.65 226.70 233.89 227.27 227.09 229.07 228.59 234.07 Water Level 227.33 226.53Date of survey=Friday, October 25, 2019 229.11 228.87 226.75 226.57 226.57 234.79 234.00 227.81 226.53 229.14 234.43 227.62 227.58Pipe Invert 226.67 233.47 diam=0.11 226.41 Water Level 227.84 228.60 Date226.45 of survey=Friday, October 25, 2019 226.81 227.05 229.21 EXISTING ROAD 226.56 234.68 226.59 234.72 228.49 227.46 226.94 229.42 SAFETY BARRIER 234.33 226.56226.50 226.58 Base of crash barrier 227.81 Top of crash barrier 229.23 226.51 226.54 226.45 228.01 229.62 226.51 227.02 233.23 226.75 227.78 229.28 Pipe Invert 226.74 227.34 226.55 226.74 diam=0.11 234.04 226.49 B 230.45229.97 227.69 226.51 226.62 229.64 234.78 226.23 234.05 228.86 226.27 227.79 233.86 226.40 0202 233.41 229.48 228.19 227.08 226.21 231.57 230.02 233.42 226.34226.14 226.73 234.84 226.47 226.29 234.82 232.17 227.98 228.31 226.29 Pipe Invert 226.87 226.33 226.55226.34 234.72 234.63 diam=0.15 230.52 229.87 226.53 Bottom ofTop233.17 Fence of Fence 226.39 233.17 228.63 Water Level Pipe Invert 228.57 234.31 233.57 226.81 Date of survey=Friday, October 25, 2019 233.04 230.51 diam=0.37 Pipe Invert 233.47 diam=0.1 226.69 226.02226.43 230.95 234.92 234.90 227.14 225.92 227.91 227.55 234.66 226.07 231.24 231.76 226.52 Flow

234.01 226.74 234.32 227.83 231.62 234.99 235.01 227.10 231.61 228.02 234.98 233.87 234.79 228.75 234.14 231.26 227.44 234.64 D 230.08 228.18 233.02 0203 230.91 228.28 233.31 235.07 228.52 235.12 232.47 228.66

231.32 229.09 233.31 235.13 UNNAMED STREAM 234.41 233.24 234.58 229.63 233.80 230.75 235.20 235.16

233.59 235.08 232.17

235.35 234.63 231.83 231.20 235.28 235.25 235.06 231.40 235.03 234.06

235.35

235.34 234.51 234.97 ISSUED FOR REVIEW

© ORDNANCE SURVEY IRELAND LICENSE NR. to 0203.dwg AR 0082518. ORDNANCE SURVEY IRELAND & TRANSPORT INFRASTRUCTURE KNOCKAKIP CULVERT (KY-N21-016.00) GOVERNMENT OF IRELAND IRELAND (TII) REMEDIAL WORKS ATKINS NOT TO BE HELD LIABLE FOR THE USE - 3:50pm EXISTING STRUCTURE LAYOUT PLAN OF THIS DATA ON ANY PROJECT OTHER THAN THE MUNSTER BRIDGES TERM MAINTENANCE CONTRACT NR.3 PROJECT AOS MG MJ

29, 2019 1:125 MUNSTER BRIDGES TERM 18/11/19 18/11/19 18/11/19 Nov - ISSUED FOR REVIEW AOS 11/19 MG MJ MAINTENANCE CONTRACT NR.3 Date: File: 5162555-HTR-DR-0200 P 5162555 / HTR / DR / 0201 -

V:\5162555\6 Dwgs-Graphics\61 AutoCad\5162555-HTR-DR-0200 to 0203.dwg GENERAL NOTES 100

Carriageway CL 1. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE 13320 2. ONLY WRITTEN DIMENSIONS SHALL BE USED. NO ROAD SAFETY BARRIER ROAD SAFETY BARRIER 1519 3701 944 6069 1087 DIMENSIONS SHALL BE SCALED FROM THE MASONRY PARAPET WALL H/S NORTHBOUND ISLAND SOUTHBOUND H/S DRAWINGS MASONRY PARAPET WALL 3. ALL LEVELS ARE IN METRES AND ARE TO MALIN HEAD DATUM

4. ALL COORDINATES ARE IN METRES AND ARE TO IRISH TRANSVERSE MERCATOR CONCRETE APRON SLAB ON SIDE SLOPE 5. DRAWINGS ARE TO BE READ IN CONJUNCTION WITH THE SPECIFICATION

231.137m 230.778m 10 0

BED LEVEL

227.657m 228.330m A1

25550

SECTION A SCALE 1:100 0201 DO NOT SCALE

CARRIAGEWAY CENTRELINE

230.930m

SURVEYED WATER LEVEL 228.020m

227.820m

SECTION B SCALE 1:100 0201

ISSUED FOR REVIEW

© ORDNANCE SURVEY IRELAND LICENSE NR. to 0203.dwg AR 0082518. ORDNANCE SURVEY IRELAND & TRANSPORT INFRASTRUCTURE KNOCKAKIP CULVERT (KY-N21-016.00) GOVERNMENT OF IRELAND IRELAND (TII) REMEDIAL WORKS ATKINS NOT TO BE HELD LIABLE FOR THE USE - 3:50pm SECTIONS A AND B OF THIS DATA ON ANY PROJECT OTHER THAN THE MUNSTER BRIDGES TERM MAINTENANCE CONTRACT NR.3 PROJECT AOS MG MJ

29, 2019 1:100 MUNSTER BRIDGES TERM 18/11/19 18/11/19 18/11/19 Nov - ISSUED FOR REVIEW AOS 11/19 MG MJ MAINTENANCE CONTRACT NR.3 Date: File: 5162555-HTR-DR-0200 P 5162555 / HTR / DR / 0202 -

V:\5162555\6 Dwgs-Graphics\61 AutoCad\5162555-HTR-DR-0200 to 0203.dwg File: 5162555-HTR-DR-0200 to 0203.dwg DO NOT SCALE 0 10 100 Date: Nov 29, 2019 - 3:51pm A1 V:\5162555\6 Dwgs-Graphics\61 AutoCad\5162555-HTR-DR-0200 OF THISDATA GOVERNMENT THE CONTRACT NR.3PROJECT ATKINS NOT AR 0082518. © ORDNANCE MUNSTER ORDNANCE TO SURVEY ON OF IRELAND BRIDGES BE

ANY PROJECTOTHERTHAN HELD LIABLE IRELAND LICENSENR.

SURVEY IRELAND& TERM DATUM = MAINTENANCE FOR Level (mOD)

THE USE Offset (m) 226.000mOD DATUM =

232.397 -27.923 Level (mOD) Offset (m) 226.000mOD to0203.dwg

232.121 -25.167

233.175 -27.599

233.168 -24.154 232.204 -20.271 EDGE OFCARRIAGEWAY

232.789 -17.927

232.626 -20.449 EDGE OFCARRIAGEWAY

232.668 -13.322

231.435 -14.346

232.613 -10.059 EXISTING FENCELINE GRAVEL TRACK

231.973 -8.278 231.245 -7.729

230.117 -6.143 SCALE 1:100 SECTION SCALE 1:100 SECTION -

ISSUED FORREVIEW

228.336 -3.491 229.935 -6.686 EXISTING FENCELINE 227.277 -1.284 0201 D 0201 C 230.768m

227.169 0.000

228.978 -2.376

227.325 1.214 BRIDGE PARAPET

227.582 2.099

228.359 -0.727 231.139m AOS

228.486 3.289 228.341 0.000 11/19

228.341 4.522 MG

BRIDGE PARAPET 228.342 2.285 MJ

230.453 6.096 IL PIPE 110mmØ SURVEYED WATER 228.540 3.261 CONCRETE 227.810m 231.568 7.398 CONCRETE IL PIPE 233.230m

110mmØ 228.681 6.176

233.174 9.820 LEVEL 227.930m

233.466 10.961 228.966 8.364 SURVEYED WATER EXISTING

233.829 15.134 FENCELINE 228.884 11.992 LEVEL 229.450m EXISTING

229.159 14.093 FENCELINE

233.805 18.608 229.160 15.876

233.782 22.081 MAINTENANCE CONTRACT TRANSPORT INFRASTRUCTURE MUNSTER BRIDGES TERM IRELAND (TII) NR.3 1. GENERAL NOTES 5. 3. 2. 4. P KNOCKAKIP IRISH TRANSVERSEMERCATOR DRAWINGS ARETOBEREADINCONJUNCTIONWITH HEAD DATUM DRAWINGS DIMENSIONS SHALL NOTED OTHERWISE ONLY WRITTENDIMENSIONSSHALL THE SPECIFICATION ALL ALL ALL COORDINATES AREINMETRESANDTO LEVELS AREINMETRESANDTOMALIN DIMENSIONS AREINMILLIMETRESUNLESS 1:100 5162555 / SECTIONS REMEDIAL ISSUED FORREVIEW CULVERT (KY-N21-016.00) 18/11/19 BESCALEDFROM HTR/ AOS

C ANDD WORKS DR 18/11/19 / 0203 BEUSED.NO MG THE 18/11/19 - MJ NEW Northing NEW Easting NEW Elevation Chainage No VerticalExageration Datum 228.000m NEW Northing NEW Easting NEW Elevation Chainage No VerticalExageration Datum 230.000m NEW Northing NEW Easting NEW Elevation Chainage No VerticalExageration Datum 231.000m NEW Northing NEW Easting NEW Elevation Chainage No VerticalExageration Datum 233.000m Vt. Vt. Vt. Vt. Chainage:258 Chainage:381 Chainage:429 Chainage:486 ID:Sect ID:Sect ID:Sect ID:Sect Hz. Scale1:250 Hz. Scale1:250 Hz. Scale1:250 Hz. Scale1:250 Type:Open Type:Open Type:Open Type:Open Scale: Scale: Scale: Scale: 1-13 1-15 1-16 1-17 1:250 1:250 1:250 1:250 (Remains Flat) (Levels (Rises slowly) (Rises slowly) off) 614687.967 503439.164 233.298 0.000 614662.290 503335.701 236.740 0.000 614653.214 503291.960 236.888 0.000 614662.776 503249.726 239.534 0.000 Forestry Forestry

614686.720 503440.575 231.787 1.883 Forestry Forestry 614686.688 503440.612 231.737 1.932 614659.224 503335.266 235.964 3.097 614650.225 503292.213 236.088 3.000 614659.253 503250.030 239.500 3.536

614685.809 503441.607 230.387 3.259 WATER LEVEL228.42m 614659.148 503335.255 235.945 3.174 614650.218 503292.214 236.087 3.007 614684.967 503442.560 229.724 4.531 614649.233 503292.297 235.934 3.995 614657.944 503250.143 239.529 4.850 Stone/Gravel 614657.227 503334.983 233.146 5.113 2019-10-25 Grass/Bog 614684.938 503442.592 229.701 4.574 614657.104 503334.965 232.965 5.238 614649.022 503292.315 233.737 4.207 614657.743 503250.160 239.534 5.052 614684.931 503442.600 229.677 4.585 614656.811 503334.924 232.648 5.534 614648.867 503292.328 233.405 4.363 WATER LEVEL232.00m 614657.429 503250.187 239.672 5.367

614684.713 503442.847 228.958 4.915 Grass/Bog 614656.816 503250.240 239.706 5.982 614656.793 503334.921 232.629 5.552 614648.821 503292.332 233.307 4.409 2019-10-25 Stone/Gravel 614684.356 503443.252 228.712 5.455 614656.433 503334.870 232.199 5.915 614647.992 503292.402 233.065 5.240 614656.255 503250.289 239.738 6.545 Grass/Bog 614684.345 503443.263 228.705 5.470 Grass/Bog 614656.410 503334.867 232.171 5.939 614644.487 503292.699 232.043 8.758 614655.497 503250.354 239.404 7.306 WATER LEVEL

614684.338 503443.272 228.704 5.481 614655.635 503334.757 232.071 6.722 614644.485 503292.700 232.042 8.760 614655.492 503250.355 239.402 7.311 WATER LEVEL 2019-10-25 614684.083 503443.560 228.675 5.866 Stone/Gravel 614644.310 503292.714 231.922 8.936 614655.475 503250.356 239.380 7.328

614655.590 503334.751 232.065 6.767 2019-10-25 Stone/Gravel 614684.074 503443.571 228.646 5.880 Grass/Bog 614644.307 503292.715 231.918 8.939 614652.404 503250.621 235.465 10.411

614654.983 503334.665 231.535 7.380 Grass/Bog

614683.906 503443.761 228.286 6.134 230.80m 614652.336 503250.627 235.379 10.479 614654.945 503334.659 231.502 7.418 614644.034 503292.738 231.530 9.213 234.42m 614683.902 503443.765 228.278 6.139 614653.898 503334.511 231.342 8.476 614643.972 503292.743 231.877 9.275 614651.946 503250.660 235.106 10.870 614683.896 503443.772 228.278 6.149 614653.832 503334.502 231.332 8.542 614643.969 503292.743 231.878 9.278 614650.986 503250.743 234.096 11.834 614683.599 503444.108 228.277 6.597 614652.801 503334.355 231.174 9.584 614643.685 503292.767 231.941 9.563 614650.983 503250.744 234.093 11.837 Grass/Bog 614683.595 503444.112 228.279 6.603 614652.737 503334.346 231.164 9.648 Grass/Bog 614643.683 503292.768 231.945 9.565 614650.099 503250.820 234.021 12.724 614683.407 503444.325 228.377 6.887 Fence 614643.443 503292.788 232.433 9.806 614648.934 503250.920 233.927 13.893

(Remains Flat) 614651.873 503334.224 231.281 10.521 614683.403 503444.330 228.385 6.894 614651.822 503334.216 231.288 10.573 614643.370 503292.794 232.453 9.879 614648.932 503250.921 233.927 13.896 614683.177 503444.586 228.771 7.235 614650.623 503334.046 230.993 11.784 614643.360 503292.795 232.451 9.889 614648.372 503250.969 233.941 14.457 Grass/Bog 614682.951 503444.841 228.824 7.576 614650.555 503334.037 230.976 11.853 614642.445 503292.873 232.235 10.808 614647.982 503251.003 234.141 14.849 614682.950 503444.843 228.825 7.577 614650.517 503334.031 230.955 11.890 614642.436 503292.873 232.238 10.816 614647.978 503251.003 234.143 14.853 Forestry 614682.500 503445.352 229.172 8.257 614649.826 503333.933 231.043 12.589 614641.156 503292.982 232.720 12.102 614646.994 503251.088 235.124 15.840 614682.497 503445.355 229.173 8.261 614641.144 503292.983 232.726 12.113 614646.992 503251.088 235.126 15.842 (Remains Flat)

614649.787 503333.928 231.040 12.628 (Rises slowly) 614682.048 503445.864 229.415 8.940 614649.430 503333.877 230.777 12.989 614640.392 503293.047 233.098 12.868 614646.989 503251.088 235.128 15.846 614682.010 503445.906 229.435 8.997 614649.330 503333.863 230.740 13.090 614640.385 503293.047 233.098 12.875 614645.464 503251.220 236.328 17.376 614681.509 503446.474 230.183 9.754 614649.192 503333.844 230.735 13.229 614639.428 503293.128 233.082 13.835 614644.546 503251.299 236.920 18.298

614681.503 503446.481 230.214 9.763 614648.962 503333.811 230.742 13.461 614639.418 503293.129 233.089 13.846 614644.245 503251.325 237.114 18.600 Grass/Bog 614681.498 503446.486 230.219 9.770 614648.922 503333.805 230.744 13.502 614638.585 503293.200 233.643 14.681 614644.095 503251.338 237.238 18.750 614680.972 503447.082 230.754 10.565 614648.754 503333.781 231.194 13.672 614638.292 503293.224 233.838 14.975 614643.146 503251.420 238.026 19.703 614680.958 503447.097 230.770 10.586 614648.746 503333.780 231.214 13.679 614638.289 503293.225 233.840 14.979 614642.073 503251.512 238.707 20.780 614679.433 503448.824 232.594 12.890 614647.039 503333.538 231.440 15.403 614638.001 503293.249 233.827 15.268 614642.071 503251.513 238.708 20.782 614679.422 503448.836 232.607 12.906 614646.975 503333.529 231.449 15.468 614637.744 503293.271 233.815 15.525 614642.069 503251.513 238.710 20.784 614678.252 503450.160 234.077 14.673 614646.301 503333.434 231.940 16.149 614637.740 503293.271 233.818 15.529 614640.975 503251.607 239.841 21.882 614678.244 503450.169 234.078 14.685 614646.278 503333.430 231.957 16.173 614636.422 503293.383 234.912 16.852 614640.675 503251.633 239.859 22.183 614677.299 503451.239 234.231 16.113 614645.173 503333.273 232.764 17.288 614636.421 503293.383 234.912 16.853 614639.300 503251.752 239.943 23.564 614639.298 503251.752 239.943 23.565 614677.034 503451.538 234.278 16.512 614645.139 503333.269 232.789 17.322 614635.958 503293.422 234.846 17.318 (Remains Flat) 614677.033 503451.540 234.278 16.514 614644.553 503333.186 233.037 17.914 614635.948 503293.423 234.854 17.328 614638.886 503251.787 240.010 23.979 614677.032 503451.542 234.278 16.516 614644.540 503333.184 233.042 17.927 614634.981 503293.505 235.611 18.298 614637.351 503251.920 240.262 25.519 614676.650 503451.973 234.277 17.092 614643.449 503333.029 233.863 19.029 614634.980 503293.505 235.611 18.299 614636.901 503251.959 240.301 25.971 614676.643 503451.981 234.284 17.103 614643.425 503333.026 233.881 19.053 614634.295 503293.563 235.984 18.986 614635.425 503252.086 240.430 27.453 614676.258 503452.418 234.668 17.685 614642.543 503332.900 234.814 19.945 614634.289 503293.564 235.990 18.993 614633.512 503252.251 240.464 29.373 614676.241 503452.437 234.668 17.710 614642.523 503332.898 234.834 19.965 614632.781 503293.691 237.410 20.506 614632.535 503252.336 240.482 30.354 614675.313 503453.487 234.696 19.112 614641.816 503332.797 235.313 20.679 614632.778 503293.692 237.412 20.509 614632.511 503252.338 240.482 30.378 614641.804 503332.796 235.321 20.691 614631.558 503293.795 238.210 21.733 614628.909 503252.648 240.511 33.993 614641.074 503332.692 236.354 21.428 614631.557 503293.795 238.210 21.734 614628.901 503252.649 240.511 34.001 614641.065 503332.691 236.367 21.437 614630.752 503293.863 238.371 22.542 614625.472 503252.945 240.630 37.443 614640.323 503332.586 236.963 22.187 614630.749 503293.864 238.372 22.546 614640.312 503332.584 236.972 22.198 614628.491 503294.055 239.003 24.812 614639.547 503332.476 237.123 22.970 614639.543 503332.475 237.124 22.975 614638.639 503332.347 237.126 23.888 614638.630 503332.346 237.126 23.897 614637.829 503332.232 237.207 24.706 NEW Northing NEW Easting NEW Elevation Chainage No Datum 228.000m NEW Northing NEW Easting NEW Elevation Chainage No Datum 228.000m Vt. Scale:1:250 Chainage:279 ID:Sect 1-14 Hz. Scale1:250 Vt. Scale:1:250 Chainage:254 ID:Sect 1-12 Hz. Scale1:250 Type:Open Type:Open Vertical Vertical Exageration Exageration (Rises slowly) (Levels off)

614689.718 503442.836 232.685 0.000 614684.531 503424.198 234.101 0.000 614689.143 503443.525 232.155 0.897 Forestry 614689.139 503443.530 232.151 0.904 Forestry 614682.573 503424.450 230.573 1.974 614688.792 503443.945 231.802 1.445 WATER LEVEL228.42m 614682.568 503424.451 230.564 1.979 Stone/Gravel

614688.791 503443.947 231.798 1.447 2019-10-25 614682.174 503424.501 229.964 2.376 Grass/Bog 614688.526 503444.264 231.184 1.860 614682.170 503424.502 229.958 2.380 614687.855 503445.069 229.627 2.908 614681.515 503424.586 229.503 3.041 614687.850 503445.074 229.617 2.915 614681.512 503424.587 229.500 3.044 Bank WATER LEVEL228.81m 614687.537 503445.450 229.240 3.404 Grass/Bog 614679.216 503424.882 229.385 5.359 Stone/Gravel 614687.374 503445.645 228.843 3.659 614679.196 503424.885 229.384 5.379 2019-10-25 614687.069 503446.010 228.485 4.135 614677.916 503425.049 228.924 6.669

614687.055 503446.027 228.469 4.156 Grass/Bog 614677.741 503425.072 228.861 6.846

614686.851 503446.271 228.229 4.474 614677.738 503425.072 228.861 6.849 614686.840 503446.285 228.215 4.493 614677.490 503425.104 228.859 7.099 0486 1-17_Ch Section Grass/Bog 614686.642 503446.522 228.221 4.801 614675.607 503425.346 228.846 8.998 614686.630 503446.537 228.221 4.820 614675.588 503425.349 228.846 9.017

614686.340 503446.884 228.330 5.273 Fence 614674.835 503425.446 228.575 9.776 614686.324 503446.903 228.336 5.297 614674.829 503425.447 228.573 9.782 (Remains Flat)

614686.309 503446.922 228.378 5.321 614674.374 503425.505 228.589 10.241 614686.063 503447.216 228.595 5.705 614674.368 503425.506 228.589 10.247 0429 1-16_Ch Section 614685.987 503447.307 228.928 5.823 614673.766 503425.583 228.867 10.854 614685.775 503447.561 228.863 6.153 614673.761 503425.584 228.869 10.859 614685.758 503447.581 228.848 6.181 614673.492 503425.619 229.135 11.130 614685.404 503448.005 228.898 6.733 614673.490 503425.619 229.137 11.132 614685.386 503448.027 228.911 6.761 614672.659 503425.726 229.213 11.970

Grass/Bog 614685.334 503448.089 228.924 6.842 614672.653 503425.727 229.214 11.976 0381 1-15_Ch Section 614685.172 503448.284 229.844 7.096 614672.108 503425.797 229.423 12.525 614685.159 503448.299 229.886 7.115 614672.105 503425.797 229.424 12.529 614685.010 503448.478 229.821 7.348 614670.708 503425.977 229.285 13.937 614685.002 503448.487 229.817 7.360 614670.702 503425.978 229.284 13.943 (Rises slowly)

614684.989 503448.503 229.779 7.382 614669.919 503426.078 229.640 14.733 614684.683 503448.870 228.918 7.859 614669.914 503426.079 229.642 14.738 0279 1-14_Ch Section

614684.244 503449.396 230.613 8.544 614668.699 503426.235 230.014 15.963 NO ACCESS

NO ACCESS

614684.230 503449.412 230.654 8.565 614668.693 503426.236 230.016 15.968 0258 1-13_Ch Section 614683.710 503450.035 231.108 9.376 614667.676 503426.367 230.407 16.994 0254 1-12_Ch Section 614683.696 503450.052 231.120 9.399 614667.383 503426.405 230.520 17.290 614683.048 503450.829 231.781 10.411 614667.381 503426.405 230.521 17.291 614683.029 503450.852 231.800 10.440 614666.793 503426.481 230.706 17.884

614682.383 503451.626 232.442 11.449 614666.011 503426.581 230.952 18.672 Section 1-10_Ch 0220 614682.359 503451.655 232.466 11.486 614666.009 503426.582 230.953 18.675 0245 1-11_Ch Section 614681.624 503452.536 233.458 12.633 614664.851 503426.731 231.240 19.843 Section 1-09_Ch 0216 614681.606 503452.557 233.482 12.661 614664.848 503426.731 231.241 19.845 Section 1-08_Ch 0208 614663.655 503426.885 231.617 21.048 614681.260 503452.972 233.793 13.201 Section 1-07_Ch 0202 614681.250 503452.984 233.802 13.217 614663.654 503426.885 231.617 21.049 614680.461 503453.929 233.937 14.449 614660.914 503427.237 233.020 23.811 614680.319 503454.099 233.961 14.670 614660.909 503427.238 233.023 23.817 614680.316 503454.103 233.962 14.674 614660.284 503427.318 233.305 24.447

614679.773 503454.754 234.060 15.522 614660.244 503427.324 233.305 24.488 0119 1-04_Ch Section 614679.642 503454.911 234.253 15.727 614658.605 503427.534 233.309 26.139 0105 1-03_Ch Section 614679.462 503455.126 234.517 16.007 614658.592 503427.536 233.308 26.153 614679.457 503455.133 234.525 16.016 614657.677 503427.654 233.241 27.076 614678.581 503456.182 234.579 17.382 614657.640 503427.659 233.248 27.113

614655.912 503427.881 233.593 28.855 Section 1-02_Ch 0053 1-02_Ch Section Section 1-06_Ch 0178 1-06_Ch Section

Section 1-05_Ch 0162 Section 1-01_Ch 0000 1-01_Ch Section 0 CHAINAGE C A B 1675 Original 1:250 Height Datum:OSGM15/Malin Grid System:ITM N21 KnockakipCulvert Knockakip CrossSections Atkins Cork REV 1/FOR Draft. 1675_CS_Knoc_Rev1 18/11/19 APPROVAL Head SK SK 1 of4 CM 18/11/19 NEW NEW NEW Chainage No VerticalExageration Datum NEW NEW NEW Chainage No VerticalExageration Datum NEW NEW NEW Chainage No VerticalExageration Datum NEW NEW NEW Chainage No VerticalExageration Datum Vt. Scale:1:250 Vt. Scale:1:250 Vt. Scale:1:250 Vt. Scale:1:250 Chainage:202 Chainage:216 Chainage:220 Chainage:245 ID:Sect ID:Sect ID:Sect ID:Sect Hz. Scale1:250 Hz. Scale1:250 Hz. Scale1:250 Hz. Scale1:250 Type:Open Type:Open Type:Bridge Type:Bridge Northing Easting Elevation Northing Easting Elevation Northing Easting Elevation Northing Easting Elevation 225.000m 226.000m 227.000m 228.000m 1-07 1-09 1-10 1-11 (Remains Flat) (Remains Flat) (Rises (No access) (Levels off) slowly)

614675.388 503493.416 227.830 0.000 614697.280 503494.514 232.056 0.000 614703.151 503495.498 232.412 0.000 614711.780503472.559 233.175 0.000 Road Edge Vegetation 614694.833 503492.712 231.463 3.039 614700.640 503493.545 232.271 3.181 614709.250503470.220 233.168 3.445 614694.817 503492.701 231.461 3.059 614671.731 503491.452 227.808 4.151 614700.498 503493.435 232.263 3.360 614709.207503470.180 233.168 3.505 614671.730 503491.452 227.808 4.152 Vegetation 614693.889 503492.018 231.374 4.210 614700.454 503493.400 232.257 3.417 614670.826 503490.967 227.781 5.178 614692.228 503490.795 231.225 6.273 614699.936 503492.998 232.184 4.072 614670.825 503490.966 227.781 5.180 614692.222 503490.790 231.217 6.281 614706.530503467.705 232.626 7.150 614669.841 503490.438 227.793 6.296 614696.707 503490.487 232.416 8.164 614706.479503467.657 232.616 7.220

WATER LEVEL 614692.197 503490.772 231.225 6.312 Vegetation 614669.828 503490.430 227.793 6.311 614690.706 503489.675 231.703 8.163 614695.759 503489.750 232.196 9.364 2019-10-25 614668.800 503489.879 226.757 7.477 Stone/Gravel 614695.303 503489.395 232.584 9.941 614668.778 503489.867 226.734 7.503 614695.231 503489.339 232.646 10.033 226.15m 614667.555 503489.210 226.580 8.891 614695.173 503489.294 232.575 10.106 Vegetation

614666.379 503488.579 226.433 10.225 Gravel track 614686.389 503486.496 231.958 13.524 614694.802 503489.005 232.121 10.577 614702.049503463.562 231.435 13.253 614666.376 503488.577 226.424 10.229 614701.833503463.362 231.377 13.547 614685.413 503485.778 231.796 14.736 614666.224 503488.495 226.019 10.402

614690.937 503486.000 232.204 15.473 Base 614665.667 503488.196 225.939 11.034 of Fence Vegetation 614665.537 503488.126 225.920 11.181 614689.381 503484.790 232.696 17.443 614664.960 503487.817 226.066 11.836 614682.663 503483.753 232.078 18.150 614689.086 503484.561 232.789 17.817 Top ofFence 614664.928 503487.799 226.074 11.873 614688.761 503484.308 232.737 18.229 614664.624 503487.636 226.519 12.218 614680.721 503482.324 231.782 20.562 614664.429 503487.531 226.634 12.439 614696.425503458.362 229.935 20.913 614680.666 503482.283WATER LEVEL 231.770 20.631 614664.255 503487.438 226.736 12.636 614696.118503458.078 229.853 21.330 Concrete

614679.763 503481.618Stone/Gravel 231.581 21.752 2019-10-25

614664.033 503487.319 226.845 12.888 Base 614679.717 503481.584 231.556 21.809 of Fence

614663.517 503487.042 227.098 13.474 Top ofFence

614678.863 503480.955 228.81m 231.105 22.870 614663.476 503487.020 227.110 13.521 Vegetation 614678.505 503480.692 230.916 23.314 614693.260503455.436 228.978 25.223 Top ofWall

614662.286 503486.381 227.442 14.871 614692.661503454.883 228.795 26.038 WATER LEVEL228.45m 614678.463 503480.661 230.871 23.367 614682.141 503479.160 232.598 26.614 2019-10-25 Concrete 614662.285 503486.380 227.443 14.873 614692.661503454.882 228.794 26.039 Stone/Gravel 614675.743 503478.659 227.989 26.743 614682.096 503479.125 232.654 26.672

614661.050 503485.717 228.183 16.275 WATER LEVEL 614692.627503454.851 228.705 26.084

614675.736 503478.654 227.982 26.753 614681.711 503478.826 232.229 27.159 Concrete 614661.048 503485.716 228.184 16.277 614692.619503454.843 228.702 26.096 Grass/Bog

614675.313 503478.342 227.564 27.278 2019-10-25

Stone/Gravel 614681.638 503478.769 232.147 27.252 614660.766 503485.565 228.280 16.596 614692.118503454.380 228.547 26.778 614674.813 503477.974 227.285 27.899 614681.610 503478.747 232.119 27.287 614660.057 503485.184 228.503 17.401 614692.054503454.321 228.359 26.865 Concrete Concrete 614674.459 503477.714 227.087 28.338 226.67m 614681.469 503478.638 231.973 27.466 614660.005 503485.156 228.519 17.461 614692.049503454.317 228.359 26.872 614674.450 503477.707 227.074 28.349 614681.107 503478.356 231.365 27.924 614659.515 503484.893 228.656 18.017 614691.515503453.823 228.341 27.599 614674.066 503477.424 226.534 28.826 614681.036 503478.301 231.245 28.015

614659.507 503484.888 228.658 18.026 WATER LEVEL 614691.288503453.612 228.332 27.909 614674.038 503477.404 226.534 28.860 614679.990 503477.487 230.302 29.340 Top Concrete 2019-10-25

614659.105 503484.673 228.965 18.482 Stone/Gravel 614691.181503453.514 228.330 28.055 of

614673.613 503477.091 226.528 29.389 614679.784 503477.327 230.117 29.601 Wall

614658.945 503484.587 229.087 18.664 227.93m 614690.784503453.147 228.327 28.595

614673.585 503477.070 226.525 29.423 614677.996 503475.937 228.596 31.865 Top

614658.938 503484.583 229.091 18.672 614690.769503453.133 228.327 28.615 of Pipe diam

Invert level227.81 Grass/Bog Fence 614672.946 503476.600 226.456 30.217 614677.690 503475.699 228.336 32.253 Base ofFence 614657.864 503484.006 229.632 19.890 614689.837503452.272 228.342 29.884 614672.897 503476.564 226.451 30.278 Concrete 614676.881 503475.070 227.856 33.278 Bank 614657.861 503484.005 229.638 19.894 0.11 614689.830503452.264 228.344 29.895 614672.896 503476.563 226.451 30.279 614676.753 503474.970 227.780 33.440 614657.258 503483.681 230.747 20.578 614689.156503451.642 228.538 30.812 614672.824 503476.510 226.416 30.369 614676.039 503474.415 227.334 34.344 614656.588 503483.321 230.847 21.339 (Remains 614689.121503451.609 228.540 30.860

614671.968 503475.880 226.498 31.431 614675.948 503474.344 227.277 34.460 Concrete Pipe diam 614654.248 503482.065 231.198 23.995 Invert level233.23 614687.089503449.730 228.674 33.628 614671.967 503475.879 226.498 31.433 614675.346 503473.875 227.262 35.223 614653.066 503481.430 231.385 25.337 Flat) 614686.981503449.630 228.681 33.775 0.11 614671.336 503475.415 226.511 32.216 614675.259 503473.809 227.260 35.332 Road Top 614652.948 503481.367 231.404 25.470 614686.976503449.626 228.682 33.781 Edge

614671.269 503475.365 226.509 32.299 614675.065 503473.658 227.199 35.578 of (Remains

Fence 614649.225 503479.367 231.704 29.696 Base ofFence 614686.097503448.814 229.405 34.978 614671.245 503475.348 226.508 32.329 614674.934 503473.556 227.169 35.744 614648.710 503479.091 231.746 30.281 614685.432503448.198 228.989 35.884

614671.240 503475.344 226.511 32.335 614674.670 503473.350 227.208 36.080 Flat) 614648.693 503479.082 231.746 30.300 614685.374503448.145 228.966 35.963 614670.807 503475.025 226.745 32.873 614674.399 503473.139 227.272 36.423 614647.367 503478.370 231.726 31.805 614684.680503447.503 229.110 36.909 614670.799 503475.019 226.762 32.883 614674.020 503472.845 227.319 36.902 614647.352 503478.362 231.726 31.822 614684.662503447.487 229.104 36.932 614670.519 503474.813 227.341 33.231 614673.976 503472.810 227.325 36.958 614645.158 503477.184 231.764 34.312 614684.651503447.476 229.036 36.948 614670.509 503474.806 227.349 33.243 614673.572 503472.496 227.595 37.470 614645.069 503477.136 231.765 34.414 614684.620503447.448 228.900 36.990 614670.141 503474.535 227.668 33.700 Grass/Bog 614673.537 503472.469 227.618 37.514 614639.646 503474.224 231.810 40.569 614684.482503447.320 228.927 37.177 614670.118 503474.518 227.688 33.729 614673.297 503472.283 227.585 37.818 614683.174503446.111 229.223 38.959 614670.086 503474.494 227.718 33.768 614673.278 503472.267 227.582 37.843 614682.720503445.691 228.885 39.578 614669.583 503474.124 228.188 34.392 614672.412 503471.594 228.415 38.940 614682.710503445.682 228.884 39.591 614669.532 503474.087 228.227 34.456 614672.338 503471.537 228.486 39.033

Grass/Bog 614682.438503445.430 229.207 39.962 614667.398 503472.516 229.869 37.106 614671.440 503470.839 229.172 40.170 614682.334503445.335 229.207 40.102 614667.387 503472.507 229.879 37.120 614671.365 503470.780 229.230 40.266 614681.658503444.709 229.202 41.024 614666.661 503471.973 230.512 38.022 614671.067 503470.548 229.588 40.643 614681.197503444.283 229.164 41.651 614666.557 503471.896 230.581 38.150 614671.043 503470.530 229.617 40.673 614681.189503444.276 229.159 41.662 614664.811 503470.611 231.748 40.318 (Remains 614670.197 503469.872 230.385 41.745 614681.167503444.255 229.159 41.692 614664.801 503470.604 231.755 40.331 614670.122 503469.813 230.453 41.840

Flat) 614679.249503442.482 229.161 44.305 614664.651 503470.493 231.775 40.517 614669.169 503469.072 231.487 43.047 Road

614659.519 503466.715 232.472 46.890 614669.094 503469.014 231.568 43.142 Edge

614659.471 503466.680 232.469 46.950 614668.342 503468.429 232.131 44.096 (Remains 614658.274 503465.799 232.392 48.436 614668.289 503468.388 232.171 44.163

614654.853 503463.280 232.173 52.684 614667.266 503467.593 233.098 45.458 Flat) 614649.016 503458.983 232.242 59.932 614667.183 503467.528 233.174 45.564 614666.348 503466.879 233.445 46.621 614666.282 503466.827 233.466 46.705 614663.279 503464.492 233.833 50.509 614663.013 503464.285 233.866 50.846 614662.987 503464.265 233.829 50.878 614657.295 503459.839 233.780 58.089 614657.221 503459.781 233.801 58.183

614652.536 503456.138 234.063 64.118 Section 1-17_Ch 0486 1-17_Ch Section

NEW NEW NEW Chainage No VerticalExageration Datum 225.000m NEW NEW NEW Chainage No VerticalExageration Datum 226.000m Vt. Scale:1:250 Chainage:178 ID:Sect 1-06 Hz. Type:Open Vt. Scale:1:250 Chainage:208 ID:Sect 1-08 Hz. Type:Open Section 1-16_Ch 0429 1-16_Ch Section Scale Scale Northing Easting Elevation Northing Easting Elevation

1:250 1:250 (Rises Sharply) 0381 1-15_Ch Section (Rises slowly)

614674.485 503503.641 229.065 0.000 614675.214 503488.225 228.757 0.000

614673.933 503487.365 229.113 1.543 614672.948 503504.900 227.054 1.987

614673.907 503487.347 229.098 1.575

Vegetation 614672.346 503505.394 226.943 2.765 0279 1-14_Ch Section 614673.039 503486.765 228.603 2.620 614672.340 503505.398 226.942 2.773 NO ACCESS

614673.027 503486.757 228.599 2.634 NO ACCESS

614670.722 503506.724 226.744 4.865 WATER LEVEL226.39m

614672.763 503486.579 228.502 2.952 0258 1-13_Ch Section 614670.698 503506.744 226.741 4.896 0254 1-12_Ch Section Vegetation 2019-10-25

614671.479 503485.718 228.035 4.498 Stone/Gravel 614670.231 503507.126 226.524 5.500 614671.420 503485.678 228.013 4.570 614669.362 503507.838 226.460 6.622 614671.009 503485.402 227.069 5.065 614669.343 503507.854 226.456 6.648 614670.987 503485.387 227.018 5.091 614669.328 503507.866 226.458 6.667

WATER LEVEL225.35m 614670.531 503485.081 226.755 5.640 Section 1-10_Ch 0220 614668.453 503508.583 226.271 7.798 0245 1-11_Ch Section 614670.503 503485.062 226.739 5.674 614667.945 503508.998 226.187 8.454 2019-10-25 Section 1-09_Ch 0216

Stone/Gravel 614670.126 503484.809 226.627 6.129 614667.927 503509.013 226.180 8.477 Section 1-08_Ch 0208 614670.105 503484.795 226.621 6.153 614667.331 503509.502 226.101 9.248

614669.809 503484.596 226.285 6.511 Vegetation 614667.328 503509.504 226.101 9.251 Section 1-07_Ch 0202 614669.792 503484.585 226.266 6.531 614666.766 503509.965 226.074 9.979 Grass/Bog 614669.478 503484.374 226.211 6.909 614666.763 503509.967 226.074 9.983 614669.462 503484.363 226.208 6.928

614666.047 503510.554 226.026 10.908 614669.386 503484.312 226.217 7.020 0119 1-04_Ch Section 614665.699 503510.839 226.002 11.358

614668.676 503483.835 226.333 7.875 614665.555 503510.956 225.976 11.543 0105 1-03_Ch Section 614668.228 503483.535 226.291 8.414 614664.932 503511.467 225.862 12.349 614668.133 503483.471 226.292 8.529 614664.706 503511.652 225.378 12.641 614667.939 503483.341 226.533 8.763 614664.629 503511.715 225.213 12.741 614667.925 503483.331 226.551 8.780

614664.628 503511.716 225.213 12.742 614667.566 503483.090 226.529 9.212 0053 1-02_Ch Section 614664.295 503511.989 225.262 13.172

Grass/Bog 614667.544 503483.075 226.528 9.239

614664.266 503512.013 225.234 13.211 614666.221 503482.187 226.684 10.832 0178 1-06_Ch Section 614664.124 503512.129 225.099 13.394

614666.134 503482.129 226.694 10.936 Grass/Bog 614663.991 503512.238 225.100 13.566

Section 1-05_Ch 0162 614665.824 503481.920 227.128 11.311 0000 1-01_Ch Section 614663.978 503512.249 225.100 13.583 614665.813 503481.913 227.143 11.324 614663.959 503512.264 225.154 13.607 614665.374 503481.618 227.427 11.853 614663.693 503512.482 225.922 13.950 614665.182 503481.489 227.551 12.083 614663.263 503512.834 226.008 14.507 614665.167 503481.479 227.555 12.102 614663.259 503512.838 226.010 14.512 614664.067 503480.740 227.832 13.427 614663.071 503512.991 226.128 14.754 (Levels off) 614664.054 503480.732 227.835 13.443 614662.620 503513.361 226.519 15.338 614663.340 503480.252 228.018 14.302 614662.612 503513.367 226.525 15.348 614663.325 503480.242 228.035 14.320 614662.599 503513.378 226.533 15.365 614662.711 503479.830 228.745 15.060 614661.806 503514.028 227.029 16.390 614662.690 503479.816 228.767 15.085 614660.739 503514.902 228.491 17.770 614661.438 503478.975 230.080 16.594 (Remains Flat) 614660.366 503515.207 229.002 18.251 614661.416 503478.961 230.106 16.619 614660.195 503515.347 229.295 18.473 614660.768 503478.526 230.913 17.400 614660.122 503515.407 229.420 18.567 614660.509 503478.352 230.949 17.712 614659.971 503515.531 229.626 18.763 614655.816 503475.201 231.594 23.365 614659.864 503515.619 229.771 18.901 614654.179 503474.101 231.819 25.337 614659.732 503515.727 229.775 19.071 614654.086 503474.039 231.832 25.448 614657.603 503517.471 229.847 21.823 614648.850 503470.524 231.966 31.755 614655.794 503518.953 229.923 24.162 614648.844 503470.520 231.966 31.762 614655.765 503518.977 229.924 24.200 614643.091 503466.657 232.297 38.692 0 CHAINAGE 614655.743 503518.994 229.919 24.228 614654.367 503520.122 229.580 26.007 614654.316 503520.163 229.584 26.072 614651.881 503522.158 229.770 29.220 614648.660 503524.797 228.995 33.384 C A B 1675 Original 1:250 Height Datum:OSGM15/Malin Grid System:ITM N21 KnockakipCulvert Knockakip CrossSections Atkins Cork REV 1/FOR Draft. 1675_CS_Knoc_Rev1 18/11/19 APPROVAL Head SK SK 2 of4 CM 18/11/19 NEW Northing NEW Easting NEW Elevation Chainage No VerticalExageration Datum 220.000m NEW Northing NEW Easting NEW Elevation Chainage No VerticalExageration Datum 223.000m NEW Northing NEW Easting NEW Elevation Chainage No VerticalExageration Datum 223.000m NEW Northing NEW Easting NEW Elevation Chainage No VerticalExageration Datum 225.000m Vt. Vt. Vt. Vt. Chainage:000 Chainage:105 Chainage:119 Chainage:162 ID:Sect ID:Sect ID:Sect ID:Sect Hz. Scale1:250 Hz. Scale1:250 Hz. Scale1:250 Hz. Scale1:250 Type:Open Type:Open Type:Open Type:Open Scale: Scale: Scale: Scale: 1-02 1-03 1-04 1-05 1:250 1:250 1:250 1:250 (Rises slowly) (Rises slowly) (Rises slowly) (Rises slowly)

614770.598 503610.253 225.053 0.000 614737.373 503540.855 229.140 0.000 614731.190 503527.374 230.587 0.000 614669.356 503507.854 226.458 0.000 614770.355 503610.988 225.091 0.774 614669.627 503508.507 226.354 0.707 614770.354 503610.990 225.091 0.776 614669.755 503508.819 226.408 1.044 614770.165 503611.564 225.033 1.381 614670.394 503510.360 226.240 2.713 Grass/Bog

614769.994 503612.081 224.980 1.925 Grass/Bog Forestry Grass/Bog 614671.056 503511.959 226.205 4.443 614769.967 503612.163 224.979 2.012 614733.070 503543.574 229.019 5.090 614671.058 503511.965 226.205 4.449 614769.778 503612.735 224.968 2.614 614732.939 503543.657 229.016 5.245 614769.537 503613.464 224.942 3.382 614769.535 503613.469 224.942 3.387 614724.610 503531.794 230.061 7.927 614672.481 503515.399 225.995 8.166 614769.413 503613.838 224.886 3.775 614672.486 503515.413 225.994 8.181 Vegetation 614769.413 503613.840 224.886 3.778 WATER LEVEL 614768.903 503615.382 224.808 5.401

614673.798 503518.579 225.784 11.608 2019-10-25 614768.897 503615.399 224.807 5.419 614727.464 503547.116 228.887 11.722 614673.804 503518.595 225.783 11.626 Stone/Gravel 614768.695 503616.011 224.820 6.065 614727.371 503547.174 228.883 11.831

614725.762 503548.191 228.822 13.734 614673.806 503518.598 225.781 11.629 225.22m 614768.692 503616.021 224.820 6.075 614719.419 503535.280 229.561 14.179 614674.069 503519.234 225.303 12.317 614768.435 503616.798 224.663 6.894 614719.413 503535.284 229.560 14.187 614674.075 503519.248 225.299 12.333 614768.432 503616.808 224.661 6.904 614719.156 503535.457 229.532 14.497 614674.407 503520.050 225.089 13.200 614767.981 503618.171 224.693 8.339 614717.525 503536.553 229.357 16.462 614722.717 503550.115 228.611 17.336 614674.446 503520.144 225.086 13.302

614767.973 503618.195 224.694 8.364 614716.717 503537.096 229.201 17.435 Grass/Bog 614722.509 503550.247 228.597 17.582 614674.446 503520.145 225.086 13.304 614767.721 503618.960 224.595 9.170 Grass/Bog 614714.904 503538.313 228.852 19.619 614674.512 503520.303 225.119 13.474 614767.716 503618.974 224.593 9.185 Grass/Bog 614714.878 503538.330 228.846 19.650 614674.514 503520.309 225.125 13.480 614767.393 503619.950 224.599 10.213 614719.717 503552.010 228.137 20.885 614713.244 503539.428 228.453 21.618 614674.798 503520.993 225.889 14.221 614767.386 503619.972 224.599 10.236 614719.547 503552.118 228.109 21.086 614713.233 503539.435 228.450 21.631 614675.033 503521.563 225.677 14.838 614764.578 503628.467 223.905 19.183 614717.886 503553.168 226.401 23.051 614712.348 503540.030 228.191 22.698 614675.037 503521.572 225.674 14.848 614764.471 503628.793 223.878 19.527 614717.803 503553.220 226.316 23.149 614711.941 503540.303 228.000 23.189 614675.043 503521.586 225.694 14.863 Forestry 614764.168 503629.708 223.766 20.490 614717.776 503553.237 226.298 23.181 (Remains Flat) 614711.927 503540.312 227.994 23.205 614675.387 503522.418 226.912 15.763 614764.154 503629.752 223.761 20.537 614717.237 503553.578 225.939 23.819 614711.890 503540.337 227.975 23.250 614675.475 503522.628 227.473 15.991 614764.153 503629.753 223.763 20.538 WATER LEVEL 614717.153 503553.631 225.269 23.918 614675.478 503522.637 227.495 16.000 Grass/Bog 614711.257 503540.762 227.654 24.011 614764.148 503629.769 223.814 20.554 614717.148 503553.634 225.235 23.923 2019-10-25 614711.055 503540.899 227.290 24.256 614675.595 503522.919 227.650 16.306 614763.290 503632.366 223.274 23.289 614715.957 503554.386 225.081 25.333 Stone/Gravel WATER LEVEL223.94m 614710.932 503540.981 227.069 24.404 Grass/Bog 614675.597 503522.924 227.653 16.311 614763.250 503632.485 223.249 23.415 614715.903 503554.421 225.074 25.397

221.16m 614710.727 503541.118 226.718 24.650 614675.772 503523.346 228.178 16.768

614763.240 503632.518 223.241 23.449 614715.872 503554.440 225.053 25.433 2019-10-25 614710.322 503541.391 226.021 25.139 614675.775 503523.353 228.186 16.775 Stone/Gravel 614763.006 503633.223 223.068 24.192 614715.190 503554.871 224.593 26.239 WATER 614710.306 503541.401 226.014 25.158 614676.107 503524.154 228.013 17.643 614762.851 503633.692 222.962 24.686 614713.417 503555.991 224.625 28.337 614708.721 503542.466 225.265 27.068 2019-10-25 614676.118 503524.183 228.007 17.674 LEVEL 224.14m

614762.842 503633.721 222.956 24.716 614713.348 503556.035 224.626 28.419 Stone/Gravel

Trees/Vegetation 614708.674 503542.498 225.263 27.124 614676.126 503524.202 228.004 17.694 614762.417 503635.005 222.842 26.069 614711.481 503557.215 224.542 30.628 614705.672 503544.514 225.139 30.740 614676.864 503525.983 227.728 19.622

614762.390 503635.088 222.835 26.156 614711.420 503557.253 224.539 30.699 WATER 614705.662 503544.521 225.136 30.753 614677.683 503527.961 227.596 21.763 614762.251 503635.509 222.747 26.600 614711.390 503557.272 224.526 30.735

614704.973 503544.9832019-10-25 224.950 31.582 614677.689 503527.976 227.595 21.779 LEVEL 224.14m

614762.242 503635.537 222.741 26.629 Stone/Gravel 614710.441 503557.872 224.111 31.858 Vegetation 614703.562 503545.931 224.796 33.282 614677.697 503527.995 227.595 21.800 614761.862 503636.685 222.657 27.838 614710.432 503557.877 224.095 31.868 (Remains Flat) Road 614703.465 503545.997 224.655 33.399 614678.258 503529.349 227.627 23.265 614761.836 503636.764 222.651 27.921 614710.162 503558.048 223.598 32.187

614702.976 503546.325 223.944 33.988 Vegetation 614678.755 503530.549 227.615 24.564 614761.691 503637.204 220.975 28.385 614709.997 503558.152 223.574 32.382 614702.680 503546.523 224.038 34.344 614761.680 503637.236 220.857 28.418 614709.695 503558.343 223.528 32.740 614702.618 503546.565 224.029 34.418 614761.470 503637.873 220.851 29.089 614709.445 503558.501 223.585 33.036 614702.273 503546.797 223.980 34.834 614761.455 503637.919 220.851 29.138 614709.332 503558.572 223.610 33.169 (Remains Flat) (No access) 614702.272 503546.798 223.980 34.836 614761.212 503638.652 220.793 29.910 614709.160 503558.681 224.145 33.373 614701.638 503547.224 224.061 35.600 614761.194 503638.707 220.789 29.967 614709.156 503558.684 224.158 33.378 614701.636 503547.225 224.068 35.602

614760.949 503639.449 220.789 30.749 614708.800 503558.908 224.239 33.798 (Rises 614701.479 503547.331 224.586 35.791 614760.930 503639.506 220.789 30.810 614708.792 503558.913 224.241 33.808 614700.680 503547.867 225.030 36.753 slowly) 614760.671 503640.289 220.832 31.634 614706.716 503560.225 224.261 36.264 614700.320 503548.109 225.230 37.188 614760.651 503640.351 220.835 31.699 614706.677 503560.250 224.261 36.309 614699.627 503548.574 225.309 38.022 614760.311 503641.379 223.837 32.782 614706.644 503560.271 224.259 36.349 614698.653 503549.228 225.421 39.195 614760.283 503641.463 224.082 32.870 614704.839 503561.411 224.174 38.484 614697.587 503549.944 225.642 40.479 614759.878 503642.688 224.137 34.160 614703.356 503562.348 224.241 40.238 614697.308 503550.132 225.730 40.815 614759.842 503642.799 224.142 34.278 614702.310 503563.009 224.289 41.476 614695.268 503551.502 226.375 43.273 614759.516 503643.786 224.327 35.317 614700.327 503564.262 224.350 43.821 614692.362 503553.454 227.775 46.774 614759.484 503643.881 224.345 35.417 614758.989 503645.378 224.408 36.993 614758.970 503645.437 224.410 37.055 614758.405 503647.146 224.375 38.856 NEW Northing NEW Easting NEW Elevation Chainage No Datum 222.000m Vt. Scale:1:250 Chainage:53 ID:Sect 1-02 Hz. Type:Open Vertical Scale 1:250

Exageration (Rises slowly)

614753.740 503575.840 226.920 0.000

614751.870 503578.153 226.810 2.974 614751.869 503578.154 226.810 2.976 614750.819 503579.453 226.751 4.646

614750.818 503579.453 226.751 4.647 614750.013 503580.449 226.920 5.927 0486 1-17_Ch Section 614750.003 503580.461 226.918 5.943 614749.655 503580.891 226.854 6.496 614749.654 503580.894 226.854 6.499 Grass/Bog 614748.015 503582.920 226.674 9.105

614747.794 503583.193 226.650 9.456 614747.721 503583.284 226.638 9.573 0429 1-16_Ch Section 614746.970 503584.212 226.510 10.767 614746.969 503584.214 226.510 10.769 614746.067 503585.329 226.274 12.203 614746.017 503585.390 226.258 12.282

614745.151 503586.462 225.984 13.660 614744.680 503587.044 225.758 14.408 0381 1-15_Ch Section 614744.669 503587.058 225.753 14.427 614744.211 503587.625 225.527 15.155

614744.210 503587.625 225.527 15.156 Grass/Bog 614744.110 503587.749 225.480 15.316

614743.796 503588.137 225.334 15.814

WATER LEVEL222.35m 614743.617 503588.358 225.245 16.099 0279 1-14_Ch Section 2019-10-25 614743.243 503588.821 225.058 16.694 NO ACCESS NO ACCESS

614743.242 503588.823 225.058 16.696 Stone/Gravel Section 1-13_Ch 0258 1-13_Ch Section 614742.779 503589.395 224.923 17.432 0254 1-12_Ch Section 614742.541 503589.689 224.726 17.810 614742.376 503589.893 224.589 18.073 614741.849 503590.545 224.429 18.911 Grass/Bog 614741.383 503591.122 224.177 19.653

Section 1-10_Ch 0220 614741.195 503591.354 224.075 19.951 0245 1-11_Ch Section 614741.195 503591.354 224.075 19.952 Section 1-09_Ch 0216 614740.352 503592.397 223.879 21.293 Section 1-08_Ch 0208 614740.351 503592.398 223.879 21.294 Section 1-07_Ch 0202 614739.711 503593.190 223.810 22.312 614739.710 503593.191 223.810 22.314 614738.120 503595.157 223.510 24.842 Grass/Bog 614738.119 503595.158 223.509 24.844

614737.622 503595.773 223.176 25.634 0119 1-04_Ch Section 614737.243 503596.242 223.009 26.237 0105 1-03_Ch Section 614737.242 503596.242 223.009 26.238 614736.820 503596.765 222.886 26.910 614736.622 503597.009 222.515 27.223

614736.622 503597.009 222.515 27.224 Stone Wall

614736.539 503597.112 222.252 27.357 Road 0053 1-02_Ch Section

614736.256 503597.462 222.236 27.807 614736.072 503597.690 222.353 28.099 0178 1-06_Ch Section (Remains Flat) 614736.071 503597.690 222.354 28.100 Section 1-05_Ch 0162

614735.566 503598.315 224.236 28.903 0000 1-01_Ch Section 614735.566 503598.315 224.236 28.904 614735.110 503598.879 224.555 29.628 614735.110 503598.879 224.555 29.630 614734.076 503600.158 224.936 31.273 614734.073 503600.162 224.937 31.279 614733.162 503601.288 225.070 32.727 614732.495 503602.113 225.080 33.788 614731.558 503603.271 225.114 35.278 614731.556 503603.274 225.114 35.281 614729.440 503605.891 225.100 38.647 614727.104 503608.780 225.273 42.362 614727.102 503608.782 225.273 42.364 614726.121 503609.995 225.591 43.925 614725.728 503610.481 226.619 44.550 614725.343 503610.957 226.337 45.162 614725.187 503611.151 225.904 45.411 614725.185 503611.152 225.904 45.413 614724.517 503611.979 226.083 46.476 0 CHAINAGE C A B 1675 Original 1:250 Height Datum:OSGM15/Malin Grid System:ITM N21 KnockakipCulvert Knockakip CrossSections Atkins Cork REV 1/FOR Draft. 1675_CS_Knoc_Rev1 18/11/19 APPROVAL Head SK SK 3 of4 CM 18/11/19 0 SCALE BAR 20 50 1:1000 100 NEW Northing NEW Easting NEW Elevation Chainage No Datum 220.000m Vertical

Exageration

614761.129 503638.684 220.789 0.000

614756.142 503634.334 220.937 6.617

614751.439 503630.231 221.077 12.859

614750.239 503627.804 221.141 15.566

614749.084 503625.468 221.203 18.172

614748.799 503622.897 221.280 20.759

614748.602 503621.114 221.333 22.553

614748.359 503618.924 221.399 24.757

614747.938 503615.120 221.503 28.584

614747.057 503607.161 221.720 36.591

614746.407 503603.848 221.814 39.968

614746.012 503601.835 221.871 42.019

614744.320 503600.772 221.938 44.017

614741.807 503599.193 222.041 46.985 614741.674 503599.110 222.041 47.142 614739.947 503598.482 222.113 48.979

614738.010 503597.778 222.188 51.040 614737.800 503597.702 222.188 51.263

614735.479 503597.334 222.405 53.613

614733.220 503596.976 222.591 55.901 614733.003 503596.942 222.591 56.120 614732.066 503596.126 222.503 57.363 614731.473 503595.320 222.635 58.363 614730.746 503594.475 222.579 59.478 614730.319 503593.680 222.553 60.381 614729.718 503592.682 222.722 61.546 614729.345 503591.074 222.544 63.196

614729.046 503589.700 222.604 64.602

614728.852 503588.007 222.599 66.306

614727.618 503585.036 222.735 69.524 614727.269 503584.213 222.778 70.417

614726.446 503582.690 222.886 72.149 614725.907 503581.811 222.915 73.179 614725.384 503580.958 222.943 74.180 614724.990 503580.080 222.921 75.143

614724.260 503578.292 222.982 77.074 614724.288 503577.174 222.935 78.192

614723.545 503575.282 223.034 80.225 614723.354 503574.715 223.050 80.823 614722.991 503574.508 223.030 81.241 614721.997 503573.241 223.094 82.852 614721.043 503572.023 223.154 84.399

614718.903 503570.651 223.224 86.941

614716.886 503569.358 223.290 89.337 200

614714.155 503568.684 223.369 92.149

614711.645 503568.065 223.440 94.735

614710.995 503564.075 223.516 98.777

614710.317 503559.915 223.595 102.992 614710.364 503559.397 223.513 103.512 614709.664 503558.295 223.529 104.818

614705.342 503550.560 223.797 113.678

614701.209 503543.164 224.053 122.151

614698.130 503537.717 224.214 128.408

614695.188 503532.512 224.367 134.387 614695.174 503532.489 224.367 134.414

614691.332 503526.349 224.562 141.657 614691.237 503526.248 224.562 141.795

614688.141 503522.963 224.680 146.309

614685.328 503519.978 224.790 150.411 614685.284 503519.955 224.790 150.461

614683.006 503518.771 224.867 153.028 614682.051 503518.275 224.900 154.104 614681.915 503518.046 224.908 154.370 614681.720 503517.718 224.917 154.752 614680.798 503517.970 224.944 155.708 614680.775 503517.980 224.944 155.732 614679.807 503518.397 224.968 156.787 614678.526 503518.948 224.997 158.181 614678.509 503518.955 224.997 158.200 614676.537 503519.481 225.047 160.241 614674.409 503520.049 225.089 162.443 614673.082 503520.472 225.114 163.836 614672.632 503520.615 225.131 164.308 614672.604 503520.636 225.131 164.343 614672.387 503520.803 225.148 164.617 614672.115 503521.011 225.164 164.959 614671.451 503520.891 225.188 165.634 614669.719 503520.577 225.242 167.394 614668.483 503518.932 225.179 169.452 614667.834 503518.202 225.149 170.429 614666.753 503516.988 225.103 172.054 614666.328 503516.670 225.179 172.586 614665.910 503516.357 225.250 173.107 614665.332 503514.946 225.254 174.632 614664.888 503513.468 225.230 176.175

614663.686 503510.475 225.295 179.401

614663.502 503507.774 225.377 182.108

614663.310 503504.960 225.461 184.928

614663.328 503502.886 225.521 187.002

614663.347 503500.726 225.582 189.163

614663.479 503497.956 225.666 191.936

614663.617 503495.080 225.753 194.815

614664.563 503491.651 225.836 198.373

614665.534 503488.132 225.920 202.023 614665.916 503487.429 226.044 202.823 614666.314 503486.697 226.170 203.656 614667.426 503485.462 226.229 205.317

614668.551 503484.213 226.287 206.999

614669.438 503482.764 226.386 208.698

614670.343 503481.285 226.486 210.432

614671.247 503479.446 226.531 212.480

614672.173 503477.563 226.577 214.579

614672.482 503477.073 226.492 215.158 WATER LEVEL227.930m 614672.807 503476.557 226.406 215.768 614673.027 503475.931 226.532 216.432

614673.438 503475.354 226.643 217.140 TOW:234.517 614673.866 503474.751 226.755 217.880 614674.599 503473.904 226.989 219.000 614674.848 503473.617 227.151 219.380 614675.153 503473.401 227.213 219.754 COMPACTED MUD/GRAVEL ROAD 614675.312 503473.205 227.660 220.006 EDGE 614675.424 503473.067 227.660 220.183 614676.296 503471.994 227.683 221.566 614676.742 503471.445 227.691 222.274 614678.360 503469.453 227.744 224.840 ROAD CULVERT OPE

614683.350 503463.311 227.996 232.753 KERB TOP CHANNEL TOW:234.991 WATER LEVEL 614691.292 503453.536 228.331 245.348

614691.363 503453.448 228.331 245.461 228.450m 614691.079 503452.831 228.282 246.140 614690.731 503452.181 228.144 246.878 614689.832 503450.368 228.140 248.901 614689.103 503449.401 228.109 250.112 614688.317 503448.269 228.127 251.491 614687.559 503447.176 228.144 252.821 614686.905 503446.677 228.219 253.643

614684.551 503444.381 228.288 256.931

614682.318 503442.203 228.353 260.051

614680.814 503439.661 228.416 263.004

614679.373 503437.226 228.476 265.834

614678.644 503435.852 228.508 267.389

614677.940 503434.526 228.539 268.891

614676.255 503431.341 228.614 272.494

614674.639 503428.288 228.686 275.948 614674.413 503427.782 228.703 276.502 614674.616 503426.635 228.639 277.668 614674.828 503425.439 228.573 278.882 614674.684 503424.506 228.629 279.826 614674.488 503423.062 228.650 281.283

614673.714 503421.540 228.712 282.991

614672.967 503420.071 228.772 284.639

614671.278 503418.741 228.909 286.789

614669.676 503417.480 229.038 288.827

614670.081 503415.904 229.049 290.454

614670.500 503414.271 229.060 292.140

614671.507 503409.594 229.093 296.924

614672.542 503404.783 229.126 301.846

614673.424 503399.141 229.165 307.556

614674.333 503393.329 229.205 313.439 614674.436 503392.152 229.226 314.620 Section 1-17_Ch 0486 1-17_Ch Section

614673.965 503385.606 229.359 321.183

614673.477 503378.823 229.497 327.984 614673.296 503377.628 229.520 329.192 614672.855 503376.648 229.543 330.267

614668.206 503370.353 229.713 338.093 Section 1-16_Ch 0429 1-16_Ch Section

614663.785 503364.367 229.874 345.534

614660.091 503360.184 229.996 351.115

614656.583 503356.210 230.111 356.416 Section 1-15_Ch 0381 1-15_Ch Section

614650.659 503345.459 230.379 368.691

614649.738 503343.789 230.420 370.598

614648.685 503339.289 230.518 375.219 614648.680 503339.249 230.518 375.259 614648.586 503338.561 230.542 375.954 614648.240 503336.025 230.633 378.514 614648.332 503335.397 230.692 379.148 614648.420 503335.199 230.706 379.365 614648.728 503334.512 230.750 380.118 614649.044 503334.057 230.742 380.671 614649.514 503333.379 230.723 381.497 614649.548 503333.331 230.723 381.556 614650.071 503333.206 230.659 382.093 614650.418 503332.784 230.710 382.639 614652.190 503330.630 230.896 385.429

614653.795 503328.786 230.940 387.873 614655.409 503326.932 230.983 390.332 0279 1-14_Ch Section

614656.300 503325.765 231.009 391.800 NO ACCESS

614657.208 503324.574 231.035 393.298

614657.410 503322.884 231.070 395.000 NO ACCESS

614657.620 503321.126 231.106 396.770

614657.529 503319.211 231.142 398.687 0258 1-13_Ch Section 614657.435 503317.211 231.179 400.689 0254 1-12_Ch Section

614657.110 503314.411 231.237 403.509

614656.770 503311.488 231.298 406.451

614655.885 503309.644 231.333 408.496

614653.410 503306.297 231.403 412.659

614651.051 503303.107 231.469 416.627 Section 1-10_Ch 0220 614649.347 503301.041 231.515 419.304 614647.719 503299.068 231.559 421.863 0245 1-11_Ch Section 614647.243 503298.590 231.613 422.537 614646.779 503298.124 231.665 423.195 Section 1-09_Ch 0216 614645.561 503295.865 231.535 425.762

614644.391 503293.696 231.412 428.226 Section 1-08_Ch 0208

614642.850 503289.523 231.927 432.674 614642.834 503289.480 231.927 432.720 614643.073 503287.266 232.190 434.947 Section 1-07_Ch 0202 614643.734 503285.757 232.203 436.594 614644.046 503285.345 232.196 437.111 614644.468 503284.259 232.210 438.276 614644.906 503283.809 232.199 438.904 614645.157 503283.671 232.199 439.190 614645.600 503283.428 232.232 439.696 614645.821 503283.306 232.258 439.948 614645.947 503283.208 232.258 440.108 614646.502 503282.776 232.299 440.811 614646.717 503282.608 232.331 441.084 614646.997 503282.468 232.331 441.397

614647.444 503282.245 232.345 441.897

614648.330 503281.803 232.366 442.887 614648.934 503281.496 232.392 443.564 0119 1-04_Ch Section 614649.210 503281.355 232.430 443.874 614650.125 503281.084 232.419 444.829 614650.728 503280.905 232.411 445.458 614650.944 503280.865 232.411 445.677 614651.821 503280.703 232.503 446.569

614652.839 503280.515 232.574 447.604

614655.097 503280.178 232.641 449.887 614656.790 503279.925 232.707 451.599 0105 1-03_Ch Section 614656.821 503279.895 232.707 451.642 614658.778 503278.041 232.785 454.338 614658.852 503277.932 232.785 454.470 614659.384 503277.150 232.810 455.416 614660.008 503276.232 232.836 456.526 614660.113 503275.117 232.862 457.645 614660.166 503273.690 232.905 459.073 614660.222 503272.202 232.950 460.562 614659.872 503269.022 233.035 463.762 614659.497 503267.511 233.115 465.319 614659.263 503266.636 233.150 466.224 614659.061 503266.020 233.232 466.873 614658.527 503265.162 233.203 467.883 614658.010 503264.329 233.175 468.864 614657.072 503262.455 233.192 470.959

614655.497 503260.891 233.477 473.179 614653.995 503259.399 233.746 475.296 0053 1-02_Ch Section 614653.479 503258.764 233.619 476.114 614653.106 503258.612 233.633 476.517 614652.736 503258.460 233.646 476.917 614652.047 503258.058 233.815 477.714

614651.385 503257.672 233.973 478.481

614650.925 503257.284 234.001 479.083 614650.475 503256.904 234.027 479.672 0178 1-06_Ch Section 614649.433 503253.283 233.939 483.440 614649.589 503252.684 233.955 484.059

614648.934 503250.916 233.927 485.944

Section 1-05_Ch 0162 Section 1-01_Ch 0000 1-01_Ch Section 0 CHAINAGE C A B 1675 1:1000 Original Height Datum:OSGM15/Malin Grid System:ITM N21 KnockakipCulvert Knockakip LongitudinalSection Atkins Cork REV 1/FOR Draft. 1675_CS_Derryb_Rev1 18/11/19 APPROVAL Head SK SK 4 of CM 18/11/19 N Bottom of Bank 0 10 20 50 100 Building outline SCALE BAR 1:500 Wall Line

Breakline 18.87

19.22 19.23

231.38 Drainage Channel

231.44

231.51

231.52 231.54 Vegetation Line Vegetation Line

231.02 231.63

231.64

231.63

231.74 Shed Shed

231.67

231.83 231.62 231.67 Positive Index Contour 231.88 231.56 231.86 231.90 231.54 231.40

231.96

231.99

232.01 Positive Normal Contour

232.07

231.99

232.03

232.14

232.02 LP 232.16 Lamp Post 231.61 231.85 232.18

232.05 231.99

231.87 232.25 232.27 Fence Wood or Conc 232.31 FENCE

232.36

232.32 232.40 232.11 Bollard or Post Boll.

232.39

232.45 232.50

232.29

232.39 232.11 Gate Gate

232.61

232.59 232.31

232.68 232.72 G 232.71 Gully 19.21

232.78 232.81 232.74

232.85

232.81 Covered outdoor area

232.73

232.59

232.96

232.57 232.99 232.99 232.74 233.00 232.98 IC 232.52 232.94 Inspection Cover

233.00

233.07 19.21 232.94

233.14

233.21 Top of kerb 19.22

233.13 233.27 233.21 233.17 232.86

233.35

233.34 233.41 Sign Sign 233.41 233.44 U2 503478.885 232.84 233.36 614706.365 233.432 233.31

233.53 233.42 233.55 MH 233.50 233.47 233.59 233.03 233.59 233.47 Manhole Cover CL:19.17 233.68

233.71 233.62 233.66 233.69 233.33 233.66 233.78 233.18

233.56 233.74 19.24 233.72 Path

233.64 229.74

233.96233.97 233.69 229.87 233.27 233.90

229.26 230.64 Top of Fence 228.45 Bottom of Fence Water Level 233.97 Date of survey=Friday, October 25, 2019 233.94 233.62 228.33228.62 228.37 231.80 228.40 228.63 228.61 233.88 Top of wall height 228.70 TW: 20.80 232.88 233.87 233.34 231.80 233.69 230.79 228.34 234.07 234.12 233.96 228.37 228.34 234.06 Pipe Invert 232.83 228.22 231.14 Pipe Soffit 228.60 228.14 231.91 233.88 233.82 228.15 228.32 234.15 228.11 232.99 234.10 228.16 234.21 19.20 230.61 234.20 228.49 228.54 234.16 Road edge 234.14 234.22 234.23 233.91 228.42 228.14 231.63 Water Level Date of survey=Friday, October 25, 2019 234.27 234.16 228.25 228.64 230.57 228.82 233.90 233.88 232.74 234.27 233.59 228.45 233.00 228.22 234.13 233.55 228.30 234.29 228.53 Top of Wall

229.91 234.36 234.29 234.07 231.72 229.53 229.00 234.15 234.40 234.39 233.55 228.42 234.13 Spot Level 234.25 Water Level 232.91 19.16 Date of survey=Friday, October 25, 2019 234.41 234.05 234.40 233.65 234.48 Bottom of Fence 233.80 Top of Fence

234.36 234.39 233.28 233.18

233.98 233.48 234.36 233.75 234.47 233.41 E 719654.517 S2A 233.97 234.44 233.80 233.91 233.73 234.58 234.50 N 736848.270 234.52 234.26 Survey Station 234.48 234.13 El 19.185

Top of Wall 234.65 D1 233.82 Base of crash barrier Top of crash barrier 503471.669 233.39 Top of Fence 227.68 Bottom of Fence 614677.290 Circular Opening 233.868 227.24 230.79 227.93 234.57 Pipe Soffit 234.61 Water Level 233.80 Date of survey=Friday, October 25, 2019 234.33 227.87 227.07 234.43 227.30 Pipe Invert 234.27 227.21 Top of Bank 234.65 226.70 233.89 234.07 Water Level Date of survey=Friday, October 25, 2019 226.75 226.57 226.57 234.79 234.00 227.81 234.43 Pipe Invert 226.67 233.47 diam=0.11 226.41 Water Level 227.84 Date of survey=Friday, October 25, 2019 226.81 226.56 234.68 226.59 234.72 227.46 234.33 226.56 226.58 Base of crash barrier Top of crash barrier 226.54 226.45 233.23 Pipe Invert 226.55 diam=0.11 234.04 226.49 234.78 229.97 226.51 Roof Level 226.23 RL: 26.08 234.05 228.86 233.86 226.40 233.41 229.48 227.08

233.42 226.14

234.84 226.47 226.29 234.82 227.98 228.31 Pipe Invert 226.87 226.33 226.34 234.72 234.63 diam=0.15 U1 Bottom ofTop Fence of Fence 226.39 503448.522 233.17 228.63 Water Level Pipe Invert 228.57 234.31 233.57 226.81 Date of survey=Friday, October 25, 2019 614668.327 233.04 diam=0.37 Pipe Invert 234.879 diam=0.1 234.92 PUMP 234.90 Tank or Pump House 227.91 234.66 D2 234.01 503460.228234.32 234.99 614662.840 235.01 231.61 234.98 234.315

234.79 234.14 231.26 234.64 Tree (Trunk,Canopy)

235.07

235.12

231.32 235.13 234.41

234.58

235.20 235.16 Water Mains cover WMS 235.08

235.35 234.63

235.28 235.25

235.06

235.03

235.35

235.34 234.51

234.97

235.22

235.46 234.94

235.45 235.25 Sheet Layout

234.81

234.91

235.54

235.62

234.94

235.37 235.25 235.25 235.62

235.64

235.71 235.69 231.38

231.44

231.51

231.52 231.54

231.02 231.63

231.64

231.63

231.74

231.67

231.83 231.62 231.67

231.88 231.56 231.86 231.90 231.54 231.40 235.72 231.96

231.99

232.01

235.54 232.07 234.97

231.99

232.03

232.14

232.02

232.16 231.61 235.62 231.85 232.18

232.05 231.99

231.87 232.25

232.27

235.16 232.31

232.36

232.32 232.40

232.11

232.39

232.45 232.50

232.29

232.39 232.11

232.61

232.59 232.31

232.68

232.72

232.71 235.82 232.78 232.81 232.74

232.85

232.81

232.73

232.59 235.58 232.96 232.57 232.99 232.99 232.74 233.00 232.98

232.52 232.94

233.00

235.89 233.07 232.94

233.14

233.21

233.13 233.27 233.21 233.17 232.86 235.68

233.35

233.34 233.41

233.41 233.44 U2 503478.885 232.84 233.36 614706.365 233.432 233.31

233.53 233.42 233.55

233.50 233.47 233.59 233.03

233.59 233.47

233.68

233.71 233.62 233.66 233.69 233.33 233.66 233.78 233.18

233.56

233.74

233.72

233.64 229.74

233.97 235.92 233.96 233.69 235.97 229.87 233.27 235.51 233.90 229.26 230.64 Top of Fence 228.45 Bottom of Fence Water Level 233.97 Date of survey=Friday, October 25, 2019 233.94 233.62 228.33228.62 228.37 231.80 228.40 228.63 228.61 233.88 228.70 232.88 233.87 233.34 231.80 233.69 235.83 230.79 228.34 234.07 234.12 233.96 228.37 228.34 234.06 Pipe Invert 232.83 228.22 231.14 228.14 Pipe Soffit 228.60 231.91 233.82 233.88 228.15 228.32 234.15 228.11 232.99 234.10 228.16 234.21 230.61 234.20 228.49 228.54 234.14 234.16 FS2 234.22 234.23 233.91 228.42 228.14 231.63 Water Level Date of survey=Friday, October 25, 2019 234.27 234.16 228.25 228.64 230.57 228.82 233.90 233.88 232.74 234.27 233.59 228.45 233.00 228.22 234.13

233.55 228.30 234.29 228.53 Top of Wall

229.91 234.36 234.29 234.07 231.72

503421.154 229.53 234.15 234.40 229.00 234.39 233.55 228.42 234.13 Water Level 232.91 234.25 Date of survey=Friday, October 25, 2019 234.41 234.05 234.40 233.65 234.48 Bottom of Fence 233.80 Top of Fence

234.36 234.39 233.28 233.18

233.98 233.48 234.36 233.75 614630.951 235.38 234.47 233.41 233.97 234.44 233.80 233.91 233.73 234.58 234.52 234.50 234.26

234.48 235.37 234.13

Top of Wall 234.65 233.82 Base of crash barrier D1 Top of crash barrier 236.144 233.39 503471.669 Top of Fence 227.68 Bottom of Fence 614677.290 Circular Opening 227.24 233.868 230.79 236.03 227.93 234.57 Pipe Soffit 234.61 Water Level 233.80 Date of survey=Friday, October 25, 2019 234.33 227.87 227.07 227.30 Pipe Invert 234.27 234.43 227.21

234.65 233.89 226.70 234.07 Water Level Date of survey=Friday, October 25, 2019 235.45 226.75 226.57 226.57 234.79 234.00 227.81 234.43 Pipe Invert 226.67 233.47 diam=0.11 226.41 Water Level 227.84 Date of survey=Friday, October 25, 2019 226.56 226.81 234.68 226.59 234.72 227.46 234.33 226.56 226.58 Base of crash barrier Top of crash barrier 226.54 226.45 233.23 Pipe Invert 226.55 diam=0.11 234.04 229.97 226.49 234.78 226.51 226.23 234.05 228.86 233.86 226.40 233.41 229.48 227.08 236.01 233.42 226.14 234.84 226.47 226.29 234.82 227.98 228.31 Pipe Invert 226.87 226.33 226.34 234.72 diam=0.15 U1 234.63 Bottom ofTop Fence of Fence 226.39 233.17 228.63 Water Level 503448.522 Pipe Invert 228.57 234.31 233.57 226.81 Date of survey=Friday, October 25, 2019 235.82 614668.327 233.04 diam=0.37 Pipe Invert 234.879 diam=0.1 234.92 234.90

227.91 235.76 234.66 D2 234.01 503460.228234.32 234.99 614662.840 235.01 231.61 234.98 234.315

234.79 234.14 231.26 234.64

235.07

235.12

231.32 235.13 234.41

234.58

235.20 235.16 235.95 235.08 236.09 235.35 234.63 235.28 235.25

235.06

235.03

235.41 235.35

235.34 234.51 234.97

235.22

235.46 234.94

235.45 235.25

236.08 234.81 234.91

235.54

235.62

234.94 235.37 235.25 235.25 235.62

235.33 235.64

235.71 235.69

235.72

235.54 234.97 235.62

235.16

235.82

235.58

235.89

235.68

235.72 235.97 235.92 235.51 235.83 FS2 503421.154

614630.951 235.38 236.144 235.37 236.03 235.45

236.01

235.82 235.76

235.95 236.09

235.41

236.08

235.93 235.33

235.58 235.72

235.93 235.58

236.16 236.14 235.65

235.91 236.29 236.16 236.08

236.01

236.14 235.98 236.23 235.65 236.26 236.04

236.35

236.02 235.88

236.19

236.14 235.72

236.54 236.45 236.47 235.62 236.36 235.91 236.20

236.25

236.29 236.27 235.95

236.56

236.23 236.08 236.39 236.12

236.52

236.67

236.67 236.42 236.40

236.81

236.52

236.46

236.76 236.03 236.01 236.78 236.51 236.28 KN2 236.56 503402.685 614601.179 236.17 236.821 236.73

236.67

236.96 236.29 236.61

236.89

236.90 236.62

236.65

235.98 236.21 236.78 236.47 236.23 236.70

236.34 236.26 236.70 236.49

236.04

236.35

236.02 235.88

236.19

236.14 235.72

236.54 236.45 236.47 235.62 236.36 236.20

236.25

236.27 235.95

236.56

236.23

236.39

236.12

236.52

236.67

236.67 236.42 236.40 1

236.81

236.52

236.46

236.76 236.03 236.78 236.51 236.28 KN2 236.56 503402.685 614601.179 236.17 236.821 236.73

236.67

236.29 236.96 236.61

236.89 236.90 236.62 C

236.65

236.21

236.78 236.47 236.70 B 236.34

236.70 236.49 A Original Draft. SK 02/11/2019

REV 1/FOR APPROVAL

Atkins Cork

Topographical Survey

N21 Knockakip Culvert

Grid System: ITM

Height Datum: OSGM15/Malin Head

1:500 19/11/19 SK CM

1675 1675_T_Knoc_Rev1 1 of 1

© WS Atkins Ireland Limited except where stated otherwise

Contains sensitive information Culvert Lining Hydraulic Impact Assessment | 0.0 | March 2020 Atkins | Knockakip Culvert Capacity Assessment.docx Page 26 of 26

Appendix D. Section 50 Consent

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 39 of 44

I refer to the above Section 50 applications.

This application was received from Atkins Ireland Ltd on behalf of Transport Infrastructure Ireland and arises due to the proposed works for the Knockakip culvert on the N21 National Road.

The documentation submitted has been examined and I am to confirm that the consent of the Commissioners of Public Works under Section 50 of the Arterial Drainage Act, 1945 is given to the proposed culvert/bridge with the following recommendations:

Recommendation

1) The proposed works should be designed to be resistant to scour. This is the applicants/designers responsibility. 2) Detail design for the proposed scheme is the responsibility of the applicant. 3) It is the applicant’s responsibility to satisfy themselves that all works planned and undertaken are in compliance with all current environmental and ecological legislation.

It should be noted that consent is given only for the purpose of Section 50 and does not absolve the recipient of responsibility for any adverse effects caused by this installation to any third party.

The Commissioners of Public Works are not responsible and accept no liability for any loss or damage whatsoever caused as a result of this development.

Yours sincerely,

______

Engineering Services Administration Unit 19th March 2021

Ceann Oifig, Sráid Jonathan Swift, Baile Átha Troim, Co. na Mí, C15 NX36 Head Office, Jonathan Swift Street, Trim, Co. Meath, C15 NX36 T +353 46 942 6000 | [email protected] www.opw.ie

© WS Atkins Ireland Limited except where stated otherwise

5162555DG023 | 5 | 19/03/2021 Atkins | 5162555DG0023 rev 5 - Knockakip NIS.docx Page 40 of 44