The Minerva Plan a Rail Strategy for Southeast Queensland Foreword

Total Page:16

File Type:pdf, Size:1020Kb

The Minerva Plan a Rail Strategy for Southeast Queensland Foreword The Minerva Plan a rail strategy for Southeast Queensland Foreword The history of rail in Australia strategy since the Connecting Queensland will be addressed, is dotted with pivotal moments SEQ 2031 regional transport describing the envisioned which have had far-reaching plan was dis-endorsed. It is in development of the network implications. From Bradfield’s this absence of a rail strategy over the coming decades – vision and predominant that Cross River Rail has with a modified Cross River Rail realisation of his railway been allowed to come to its at its core. scheme for Sydney which has current form, with no guiding served our biggest city for framework with which to This document is the Minerva nearly a century, to the pre- measure its suitability in the Plan, a rail strategy for Federation break of gauge long term. Southeast Queensland. The debacle which took almost one Minerva Plan will revisit hundred years to resolve, the Major inner-city rail previous works, including long term implications – both infrastructure has a lifespan Connecting SEQ 2031, to good and bad – of railway extending beyond a century, present a rail strategy that planning decisions are clear with the potential to increase is ‘familiar, yet different’, to see. In 2020, Queensland is the efficiency and liveability and for which considerable facing its own pivotal moment of a city, and it is important investigation has already been with the design of the Cross that the project is designed undertaken. River Rail project. Cross River to deliver on these objectives. Rail has been approved, had Unfortunately, Cross River Rail This plan will set out the contracts signed, and early is not fit for purpose. logical sequencing of projects works have commenced to enhance the capacity and to deliver the second river Fortunately, through minor functionality of the rail network crossing in Brisbane’s CBD by changes to the project, it will into four distinct phases, 2024. be possible to increase capacity without being prescriptive in both the short and long- about specific years. In this However, rather than term, allowing Cross River Rail way, the development of relieve the current capacity to play the role in enhancing the rail network will be able bottleneck and form the the network for which it was to correspond to patronage backbone of a transformation always intended. growth and economic of the rail network as it was conditions. long intended and currently This document will present the promoted as delivering, case of change, demonstrating The Minerva Plan is not Cross River Rail in its current in detail how the current sanctioned by government; iteration will itself become design for Cross River Rail however, we welcome and the bottleneck and prevent is flawed, and how it can be encourage government to almost all future expansion of modified to meet its target adopt the recommendations the Southeast Queensland rail criteria more effectively while listed here. network. improving cost efficiency. Southeast Queensland has Further, the lack of a rail Minerva Transport Planning been without a detailed rail strategy in Southeast Company Limited, June 2020 Caveats and assumptions All information used in the development of the Minerva Plan is publicly available and referenced throughout. In most cases, information has been sought from the Queensland Department of State Development, Tourism and Innovation website through its hosting of track layouts and other information from the various Project Change applications, as well as from Queensland Rail and TransLink’s websites including the Open Data portal. While most of the analysis was conducted using the track arrangements depicted in Project Change 4, the outcomes and findings remain the same with the most recent Project Change 7 revisions from June 2020. Given the last decade has seen multiple variants and business cases developed for Cross River Rail, there is a large amount of detailed rail operational information which has been used as a basis for filling in missing information in the current proposal. On top of this, expert analysis has been conducted to determine the findings presented herein. The Minerva Plan, and the intellectual property contained therein, is copyright of Minerva Transport Planning Company Limited - © Minerva Transport Planning Company Limited 2020. All rights reserved. However, the use of the contents is made freely available to government, government bodies including Government Owned Corporations and Authorities, and community groups on a non-commercial basis. Commercial exploitation of the content is not permitted. Table of Contents Introduction - how to read this document 1 Objectives of this strategy 3 A brief introduction to the Brisbane network, and how it operates 4 Cross River Rail: as it stands 5 What the current version of Cross River Rail will do - understanding the operations 5 A misallocation of new capacity 9 The value equation for the current version of Cross River Rail 16 Phase One: Fixing the current Cross River Rail project 18 Inspired history 18 Modular development and future proofing 27 Phase One peak Hour 28 Phase One Off-Peak Hour 29 Phase Two: The long tunnel 30 Clapham yard, Yeerongpilly, and Sailisbury to Flagstone 34 Phase Two Peak Hour 41 Phase Two Off-Peak Hour 42 Phase Three: The northern expansion 43 A grim forecast 49 Phase Three A Peak Hour 50 Phase Three A Off-Peak Hour 51 Phase Three B Peak Hour 52 Phase Three B Off-Peak Hour 53 Phase Four: Beyond Cross River Rail 55 The “Clevewich” line 57 Phase Four A Peak hour 59 Phase Four A Off-Peak Hour 60 Phase Four B Peak Hour 61 Phase Four B Off-Peak Hour 62 Maintenance and track possessions 63 Improved sectioning 63 Increases track centres 64 Outer network enchancements 65 Signalling 65 Track amplification on Beenleigh line 65 Duplication of Sunshine Coast line 69 Duplication of the Cleveland line 72 Duplication of the Doomben, Airport, and Shorncliffe lines 73 Freight-specific enhancements 74 Ripley Valley extnsion 74 Fourth track electrification between Corinda and Darra 74 Sensitivity testing 75 Are there alternative ways of achieving the vision described here? 75 Cross River Rail 75 Extension of the tunnel to Yeerongpilly 76 The extension to the Trouts Road Corridor 77 The Trouts road Corridor itself 78 Stabling and fleet requirement 79 Underlying timetables 80 The Mains - Kippa-Ring to Springfield Central and Ripley 81 The Suburbans - Ferny Grove and Shorncliffe to Beaudesert 84 The Coastal Line - Maroochydore, Gympie North, and Brisbane Airport to Beenleigh and Collangatta 86 The Clevewich Line - Cleveland to Rosewood and Ipswich 90 The Shuttles - The Dooben Line, and Park Road to Cannon Hill 93 Freight 93 North Coast Line - between Gympie North and Exhibition via Northgate 95 Western Line - between Corinda and the Exhibition loop via Roma Street 96 Conclusion 97 Next Steps and further studies 98 References 100 Appendix One - end state timetables Mains sector Suburbans sector Coastal sector Clevewich sector Freight paths Appendix Two - programme and projects Introduction One of the most important things to understand is that this document is not arguing against a form of Cross River Rail. A significant increase in rail capacity between the north and south of the city is crucial to both cater for near-term patronage growth and to facilitate expansion of the rail network over time. However, the current design of Cross River Rail is fundamentally flawed, meaning it will not achieve its goals in terms of capacity enhancement, nor enable the development of the rail network in decades to come. As such, the early part of this plan describes the current Cross River Rail configuration, and how it will operate, to illustrate the shortcomings of the project. It is acknowledged that in order for the project to change, a strong justification must be given, and this document sets out that justification – this forms the first part of the Minerva Plan. After this, an altered Cross River Rail plan is presented, describing the changes to the project and the levels of additional capacity it then would provide through enhanced operation. Building on this enhanced Cross River Rail, a series of additions and improvements to the network are presented to deliver a comprehensive rail strategy for Southeast Queensland – the Minerva Plan. Traditionally rail strategies have specified exact years for when projects would become operational, yet these are almost never remotely accurate – by way of illustration, Cross River Rail was originally planned to commence operations in 2016. Furthermore, this document has no official status with government or funding bodies, so the idea of specifying introduction years for different projects would be doubly disingenuous. Rather, the Minerva Plan sets out to identify phases of work, noting that some projects are contingent on others and therefore follow a logical sequencing. These phases will contain the different projects that can be completed around the same time, to allow a vision of the network development future to be plotted out. The exact timing of the projects in many cases depends on a range of factors – demand exceeding capacity, political will, State finances – and given these factors are variously unreliable or fickle, the sequencing rather than timing of the projects here is the key focus. There are a further range of projects that are not strictly necessary from a capacity perspective but would overall increase resilience or improve travel time outcomes for passengers. While some projects could conceivably be delivered at any time, this document will attempt to decipher which phase they are best suited to in order to maximise benefits. That being said, they will not strictly be bound to these phases, and are grouped simply to complete the strategic story. As this is not an official document – it is not related to the Queensland Government in any way, and is not the subject of a commission to produce – there is an element of freedom granted to the form of the document that would otherwise not be present.
Recommended publications
  • TTF Smartcard Ticketing on Public Transport 2010
    Tourism & Transport Forum (TTF) Position Paper Smartcard ticketing on public transport July 2010 Tourism & Transport Forum (TTF) is a national, Member‐funded CEO forum, advocating the public policy interests of the 200 most prestigious corporations and institutions in the Australian tourism, transport, aviation & investment sectors. CONTENTS OVERVIEW 2 SMARTCARD TECHNOLOGY 3 ADVANTAGES OF SMARTCARD TICKETING 3 CHALLENGES FOR IMPLEMENTATION 6 SMARTCARD TICKETING IN AUSTRALIA 8 SMARTCARD TICKETING INTERNATIONALLY 10 INNOVATION IN SMARTCARD TECHNOLOGY 12 LOOKING AHEAD 14 CONCLUDING REMARKS 14 FOR FURTHER INFORMATION PLEASE CONTACT: CAROLINE WILKIE NATIONAL MANAGER, AVIATION & TRANSPORT TOURISM & TRANSPORT FORUM (TTF) P | 02 9240 2000 E | [email protected] www.ttf.org.au In short: 1. Smartcard ticketing provides convenience for commuters and efficiency gains for transport service providers. 2. Smartcard systems have been introduced in Australian cities with varying degrees of success. 3. International experience suggests that successful implementation may take many years, and difficulties are commonplace. 4. Overall, the benefits of smartcard ticketing overwhelmingly outweigh the costs and challenges that may arise in implementation. Overview Smartcard technology is being implemented around the world as a substitute for cash transactions in various capacities. When applied to public transport fare collection, smartcards eliminate the need for commuters to queue for tickets and reduce the burden on transport providers to process fare transactions. In recent years, benefits such as decreased travel times and general convenience to commuters have driven a shift towards smartcard ticketing systems on public transport systems in Australia and around the world. As well as providing more efficient transport services to commuters, smartcard ticketing systems enable service providers and transit authorities to collect comprehensive data on the travel behaviour of commuters.
    [Show full text]
  • Tuesday, 18 May 2004
    18 May 2004 Legislative Assembly 1061 TUESDAY, 18 MAY 2004 Legislative Assembly Mr SPEAKER (Hon. R.K. Hollis, Redcliffe) read prayers and took the chair at 9.30 a.m. ASSENT TO BILLS 14 May 2004 The Honourable R.K. Hollis, MP Speaker of the Legislative Assembly Parliament House George Street BRISBANE QLD 4000 Dear Mr Speaker I am pleased to inform the Legislative Assembly that the following Bill, having been passed by the Legislative Assembly and having been presented for the Royal Assent, was assented to in the name of Her Majesty The Queen on 13 May 2004: "A Bill for an Act to repeal the Aurukun Associates Agreement Act 1975, and for related purposes" The Bill is hereby transmitted to the Legislative Assembly, to be numbered and forwarded to the proper Officer for enrolment, in the manner required by law. Yours sincerely (sgd) Quentin Bryce Governor AUDITOR-GENERAL'S REPORT Mr SPEAKER: Order! Honourable members, I have to report that today I received from the Auditor-General a report entitled Audit Report No. 8 of 2003-04: Results of audits performed for 2002-03 as at 31 March 2004. REGISTER OF MEMBERS' INTERESTS Report Mr SPEAKER: Order! Honourable members, I lay upon the table of the House the 16th report on the Register of Members' Interests. STANDING ORDER 114 Mr SPEAKER: Order! Honourable members, in light of the behaviour that has been experienced in the House over the past couple of sitting weeks, I feel it necessary to remind members of standing order 114, which states— A Member shall not interrupt another while addressing the House except by leave of such other Member, and for the purpose of making a personal explanation.
    [Show full text]
  • Smart Cards Contents
    Smart cards Contents 1 Smart card 1 1.1 History ................................................ 1 1.1.1 Invention ........................................... 1 1.1.2 Carte Bleue .......................................... 2 1.1.3 EMV ............................................. 2 1.1.4 Development of contactless systems ............................. 2 1.2 Design ................................................ 2 1.2.1 Contact smart cards ..................................... 3 1.2.2 Contactless smart cards .................................... 3 1.2.3 Hybrids ............................................ 4 1.3 Applications .............................................. 4 1.3.1 Financial ........................................... 4 1.3.2 SIM .............................................. 4 1.3.3 Identification ......................................... 4 1.3.4 Public transit ......................................... 5 1.3.5 Computer security ...................................... 6 1.3.6 Schools ............................................ 6 1.3.7 Healthcare .......................................... 6 1.3.8 Other uses .......................................... 6 1.3.9 Multiple-use systems ..................................... 6 1.4 Security ................................................ 6 1.5 Benefits ................................................ 6 1.6 Problems ............................................... 7 1.7 See also ................................................ 7 1.8 Further reading ...........................................
    [Show full text]
  • Cross River Rail Project Monthly Environmental Report
    Cross River Rail Project Monthly Environmental Report March 2020 Cross River Rail Project Monthly Environmental Report Executive Summary This monthly report has been produced for Project Works undertaken on site for March 2020 for the Rail, Integration and Systems (RIS), and Tunnel, Stations and Development (TSD) packages. This monthly report addresses the obligations outlined in the Coordinator-General’s change report – condition change (hours of works) 2019 (CGCR, October 2019) and the Project’s Outline Environmental Management Plan. The Construction Environmental Management Plans (CEMPs) prepared for the Relevant Project Works being delivered by both Unity Alliance (RIS Contractor) and CBGU JV (TSD Contractor) were endorsed by the Environmental Monitor (EM) and submitted to the Coordinator General in accordance with Condition 4 (a) and 4 (b) respectively. The following Project Works were undertaken in March 2020 – Mayne Area - Surcharge works in a small area of Mayne Yard North using suitable material from the Northern Corridor; and Demolition and removal of redundant infrastructure such as fences, pits, service, OHLE foundations and asbestos drainage culverts completed. Northern Area - Widening of existing access road in Victoria Park and installation of relocated shared user path; Northern Satellite Office facilities were installed and services provided as planned; and Enabling works within the Northern Corridor (removal of unsuitable material). Central Area - Continued site establishment and clearance, fencing and utility works across the central section; Piling preparation and piling across the sites; Shaft Excavation (Roma Street, Woolloongabba and Albert Street); Footbridge demolished and continued demolition works at Roma Street; and Continued demolition of Lot 1 on Albert Street.
    [Show full text]
  • Journal of the Eastern Asia Society for Transportation Studies, Vol.11, 2015
    Effects of Two Fare Policies on Public Transport Travel Behaviour: Evidence from South East Queensland, Australia Author Yen, Barbara, Chen, Wen-Chung, Chiou, Yu-Chiun, Lan, Lawrence W., Mulley, Corinne, Burke, Matthew Published 2015 Journal Title Journal of the Eastern Asia Society for Transportation Studies Version Version of Record (VoR) DOI https://doi.org/10.11175/easts.11.425 Copyright Statement © 2015 Eastern Asia Society for Transportation Studies. The attached file is reproduced here in accordance with the copyright policy of the publisher. Please refer to the journal's website for access to the definitive, published version. Downloaded from http://hdl.handle.net/10072/98986 Griffith Research Online https://research-repository.griffith.edu.au Journal of the Eastern Asia Society for Transportation Studies, Vol.11, 2015 Effects of Two Fare Policies on Public Transport Travel Behaviour: Evidence from South East Queensland, Australia Barbara T.H. YEN a,*, Wen-Chun TSENG b, Yu-Chiun CHIOU c, Lawrence W. LAN d, Corinne MULLEY e, Matthew BURKE f a Urban Research Program, Griffith University, 170 Kessels Road, Nathan, Brisbane, Queensland 4111, Australia; E-mail: [email protected] b School of Aviation, University of New South Wales, Australia; E-mail: [email protected] c Department of Transportation and Logistics Management, National Chiao Tung University, Taiwan, ROC; E-mail: [email protected] d Department of Transportation and Logistics Management, National Chiao Tung University, Taiwan, ROC. E-mail: [email protected] e Institute of Transport and Logistics Studies; The University of Sydney, Australia ; E-mail: [email protected] f Urban Research Program, Griffith University, 170 Kessels Road, Nathan, Brisbane, Queensland 4111, Australia; E-mail: [email protected] Abstract: Congestion and peak loading are key concerns for public transport agencies in Australian cities.
    [Show full text]
  • Appendix C3. Public Engagement Record: December 2019
    Appendix C3 Public Engagement Record: December 10, 2019 to September 16, 2020 Public Engagement Record: December 10, 2019 to September 16, 2020 • Website Screenshots Public Engagement Record: December 10, 2019 to September 16, 2020 • Ask-A-Question Submissions Ask A Question – January 23 to September 16, 2020 Comment title Comment body Response Future Is the western terminus of the line to be built so that it would be able to be We are currently advancing plans for the line between Exhibition/Ontario expansion extended north west at a later date? Thank you Place and the Ontario Science Centre. However, these plans don’t preclude future expansions that may be presented to improve access and meet demand. Thorncliffe Park Where is the station in relation to Overlea Blvd Teams are analyzing the 15 stations identified in the Initial Business Case to Station determine whether or not they should be built, looking at factors like the potential number of users, ease of construction, and cost, to name a few. Findings will be presented in the Preliminary Design Business Case, which we are aiming to complete by summer 2020.By using the GO corridor and building bridges across the Don River instead of tunneling underneath it, a route that is approximately twice the length of the Relief Line South can be built at a similar cost. Also, using the GO corridor will allow people to more easily connect between GO and TTC services that will both be accessible by street level, saving time compared to connections that would lead people into deep underground stations.
    [Show full text]
  • Gold Coast Infill Stations Project Description Report
    Gold Coast Infill Stations Project Description Report April 2021 L\339467772.2 Table of Contents 1. Purpose .......................................................................................................................... 3 2. Project Background and relationship with Cross River Rail ............................................ 3 3. Project Objectives .......................................................................................................... 5 4. Project Scope ................................................................................................................. 5 4.1 Pimpama Station ....................................................................................................... 5 4.2 Helensvale North Station ........................................................................................... 7 4.3 Merrimac Station ....................................................................................................... 8 L\339467772.2 2 1. Purpose The purpose of this document is to describe the background, objectives, and high-level scope of three new infill train stations being planned on the Gold Coast to Brisbane rail line, at Pimpama, Helensvale North and Merrimac. 2. Project Background and relationship with Cross River Rail The rail line connecting the Gold Coast to Brisbane (Gold Coast Line) is located inland with six existing Gold Coast stations at Ormeau, Coomera, Helensvale, Nerang, Robina and Varsity Lakes. As it provides a public transport trunk route north to Brisbane, the Gold
    [Show full text]
  • Referral of Proposed Action
    Referral of proposed action Project title: Cross River Rail 1 Summary of proposed action 1.1 Short description The Cross River Rail project is a proposed new 10.2 kilometre rail link in Brisbane connecting Dutton Park in the south to Bowen Hills in the north. The project will include 5.9 kilometres of twin rail tunnels (one track in each direction) under Brisbane’s inner city and new underground rail stations at Albert Street and Roma Street (in the Brisbane CBD), Woolloongabba, Boggo Road and a new surface station at the Exhibition showgrounds. Upgrades and enhancements to parts of the existing rail network will be delivered where these interface with the project and to support Cross River Rail operations. READING NOTE: The Cross River Rail project has previously (2010) been referred to the then Department of the Environment, Water, Heritage and Arts under reference number 2010/5427. The project was determined to be ‘not a controlled action - if undertaken in a particular manner’. Further planning and design has been undertaken since the original Cross River Rail concept was referred. This has resulted in a modified project of a smaller scale with reduced potential impacts and enhanced affordability. This referral has been prepared as a new referral based on key changes to the project resulting from further planning and design. The referral has been prepared as a stand-alone document that can be assessed without having to reference the previous referral. While the Cross River Rail proponent does not consider the proposed action likely to have a significant impact on a matter protected under the EPBC Act, this referral has also been prepared in light of the CRR 2010 EPBC decision including a number of particular manner conditions that require reassessment.
    [Show full text]
  • FREE OFF-PEAK SENIORS BUS and RAIL TRAVEL Easing the Cost of Living for Seniors
    FREE OFF-PEAK SENIORS BUS AND RAIL TRAVEL Easing the Cost of Living for Seniors A Tim Nicholls-led Liberal National Government will provide free off-peak public transport to passengers with a seniors go card. The Problem A senior go card holder regularly travelling from the Gold Coast to Brisbane saved up to $148 per We understand increases in the cost of living make year, while those regularly travelling from Enoggera, it hard for Queenslanders to make ends meet – Indooroopilly or Newstead to the Brisbane CBD saved especially those on fixed incomes like seniors and $41 per year. pensioners. In regional Queensland, for example, seniors who are Under Annastacia Palaszczuk’s watch, Labor has regular bus passengers travelling in Townsville saved increased car registration by double the inflation up to $66 a year. rate for three years in a row. If you have a 4-cylinder car that’s an increase of over $50! Our Real Plan In recent years the cost of public transport has also risen dramatically – when Annastacia Palaszczuk A Tim Nicholls-led LNP Government will make was the transport minister in the Bligh Labor off-peak bus and rail travel free for senior go card Government, bus and train fares went up 15% year holders. after year after year. A total of 45%. This will mean many of the 20 million senior public While the Palaszczuk Labor Government has transport trips made each year will be free. no plan to tackle the cost of living issues facing The LNP is committed to tackling the rising cost of Queenslanders, the LNP team has been listening and living.
    [Show full text]
  • Cel RFID Digital Lock Application V1.1-021
    Carbine CEL 3in1 Touchscreen Locks CEL-RFID RFIC Application List The CEL locks can accept 25 user codes via the codepad In addition to this, the locks can accept another 25 users via RFID card or Smartphone RFID Chip Compatibility CEL-RFID + ISO Card + Chip:13.56MHz NXP Mifare S50 + Dimensions:86*54*0.8mm CEL-RFID-ST-C + Metal Label + Chip:13.56MHz NXP Mifare S50 + Dimensions: Ø 25mm CEL-RFID-WB + Silicone wristband + Chip:13.56MHz NXP Mifare S50 Dimensions D195 x W16 x T7.5mm Material Silicone Operating Temperature -25~85°C Storage Temperature -25~140°C THE Protection Class NEXT IP68 GENERATION IN LOCKING AUSTRALIA HEAD OFFICE 14 John Hines Avenue Minchinbury NSW 2770 1300 722 311 [email protected] CARBINE IS A DIVISION OF DAVCOR GROUP PTY LTD • ABN. 95 003 562 598 SYDNEY • MELBOURNE • BRISBANE • PERTH • ADELAIDE WWW.CARBINE.COM.AU CEL-RFID Carbine CEL 3in1 Touchscreen Locks RFIC Application List Page 2 Credit Cards & Transport Cards Any RFID cards that are using MIFARE (13.56mHz) chips will be compatible with the lock. The MIFARE chips (ISO14443 Type A) are widely used on transport cards, but not credit cards as most credit cards including VISA PayWave & Mastercard Paypass use EMV chips (ISO14443 Type B) which are not compatible with the lock. However, if the credit card can also be used as a transport card (complying to ISO14443 Type A), it is very likely it can be used to operate the lock. The table below lists the transport cards that are equipped with MIFARE chips in Australia.
    [Show full text]
  • Construction Environmental Management Plan Cross River Rail – Rail, Integration and Systems Alliance
    Construction Environmental Management Plan Cross River Rail – Rail, Integration and Systems Alliance Project number: Document number: RIS-UNA-000-001-MPL-000268 Revision date: 23 August 2019 Revision number: 00 Document Approval Rev Date Prepared Reviewed Approved By Remarks By By A 28/06/19 UNITY IEM IEM comments addressed in Rev B Signature: B 20/08/2019 Unity IEM 21 August 2019 IEM comments addressed in Rev C Signature: C 22/08/2019 Unity IEM Nor further comments from IEM Signature: 00 23/08/2019 Unity IEM IEM Endorsed by IEM with Conditions, inclusive of scope restrictions Signature: Table of Contents 1 Purpose of this Plan .............................................................................................................................. 4 1.1 Background .............................................................................................................................................................. 4 1.2 Project Summary ..................................................................................................................................................... 4 1.3 Project Works - Activities Summary ......................................................................................................................... 5 1.4 Project Works – Areas of Works .............................................................................................................................. 7 1.5 Project Works – Construction Methodologies .........................................................................................................
    [Show full text]
  • Environmental Management Sub-Plans
    Construction Environmental Management Plan Compliance Matrix CRRDA REQUIREMENT ADDRESSED IN SECTION REFERENCE Coordinator-General’s change report – whole of project refinements 2019 Appendix 1 – Part C. – Condition 4 Construction Environmental Management Plan (a) Prior to the commencement of Project Work, a Construction Environmental This Plan Management Plan for those works (Relevant Project Work) must be developed by the Proponent and endorsed by the Environmental Monitor as being consistent with the Outline EMP and these imposed conditions. (b) The endorsed Construction Environmental Management Plan must be submitted to This Plan the Coordinator General at least 20 business days prior to the commencement of Relevant Project Works. (c) The Construction Environmental Management Plan must: (i) describe the Relevant Project Work Section 2 (ii) be based on predictive studies and assessments of construction impacts Relevant sub-plans which have regard to the scale, intensity, location and duration of construction works, and location of Directly Affected Persons (iii) be generally consistent with the Outline EMP and incorporate its This Plan environmental outcomes and performance criteria (iv) incorporate and respond to the Imposed Conditions (Construction) This Plan and associated Sub-plans (v) demonstrate that the Imposed Conditions (Construction) will be complied This Plan and associated Sub-plans with during Relevant Project Work (vi) incorporate the community engagement plan, including the complaints Sections 4.3, 6 and 8 management
    [Show full text]