<<

Note: kV is the abbreviation for kilovolt, which is equal to 1,000 volts.

120/25-kV Gracefield Substation and 120-kV Lines

INFORMATION ON THE SOLUTION SELECTED • November 2015

To meet growing demand for electricity, Hydro-Québec conducted draft-design studies in winter 2013-2014 to build a 120/25-kV* transformer substation in Gracefield and rebuild the 120-kV transmission line between Paugan substation, in Low, and substation, in Egan-Sud. The 65-km line will be rebuilt in the middle of the corridor occupied by the current line. Since the plan calls for adding a circuit, a new 5-km line must be built that follows the existing line from Déléage to the entry to Maniwaki substation. In addition, a 120-kV line about 5.3 km long must be built to supply the new Gracefield substation. This bulletin describes the lowest-impact solution selected by Hydro-Québec. 76°0'

Egan-Sud, M Aumond, CT !  107 PROJECT TO DATE Maniwaki, V Maniwaki ComposantesProject components du projet #substation In the previous steps of this project, TracéSelected retenu route pour for l’alimentation Gracefield Hydro-Québec carried out an inventory dusubstation poste de supply Gracefield line ! TracéSelected retenu route Mont-Laurier of the natural and human environments Maniwaki, V tap LigneLine to à bereconstruire rebuilt to better understand the host environment Lac Kichi-gàngwenindam for the planned equipment. LimiteBoundary Lac Lac Pitòbìg Bois Franc 46°20' MunicipalityMunicipalité Grand lac 46°20' Based on its studies and technical, economic des Cèdres and environmental criteria, Hydro-Québec InfrastructuresInfrastructure Zibi, R ! Déléage, M Sainte-Thérèse- 105 ProvincialRoute nationale highway proposed two routes for the Gracefield Petit lac Maniwaki, V de-la- Route régionale des Cèdres , M substation supply line and two variants 301 Secondary road for the transmission line’s entry at TertiaryRoute locale road 

Maniwaki substation. PostesExisting et substations lignes de transportand transmission existants lines 105 # 69 kV Gatineau Hydro-Québec then held information Messines, M  # 120 kV and consultation sessions with various Blue Sea, M Messines # # 230 kV stakeholders. The company gathered substation Grand lac the comments of representatives of local Rond organizations, government departments, 120-KV LINES AND Lac Blue Sea Lac affected landowners and the general GRACEFIELD SUBSTATION Cameron population. , M 46°10' 46°10'

The outcomes of these discussions, combined with the technical, economic and environmental studies, contributed to Gracefield determining the lowest-impact solution. substation (to be rebuilt) # La Vallée-de-la- Gatineau (MRC)

Lac Heney Gracefield, V Lac-Sainte-Marie, M

Rivière Rivière 46°0' 46°0'

301 Kazabazua # substation

Kazabazua, M Low, CT Denholm, M 105 Ruisseau

Venosta Lac Sainte-Marie 45°50' 45°50' 0 3 6 km Paugan # UTM, zone 18, NAD83 substation 7339_bu_tet_041_traceretenu_151015.mxd

2 76°0' Paugan–Maniwaki transmission line

Line segment between Paugan substation and the Mont-Laurier tap This segment will be rebuilt over 65 km in the middle of the existing corridor. The current line on wooden H-frames will be dismantled before construction begins. The line will be supported by guyed steel lattice towers in forested areas and reduced-footprint towers in farmland. To accommodate an additional circuit, the right-of-way must be widened by 4.3 m on either side of the line, for a total width of 39 m.

LINE SEGMENT FROM PAUGAN SUBSTATION TO THE MONT-LAURIER SUBSTATION TAP

Guyed tower selected for the 120-kV Maniwaki # double-circuit line to be rebuilt  substation Mont-Laurier tap 105

Messines # substation

Gracefield New right-of-way boundary New right-of-way boundary

# Current right-of-way boundary Current right-of-way boundary substation (to be rebuilt) 22 to 38 m

# Kazabazua 301 substation

15.2 m 15.2 m

Paugan # 5.0 m 19.5 m 19.5 m 5.0 m substation Clearing easement 39.0 m Clearing easement

105 7339_buf3_tet_018_ligneRecons_150505.fh9 7339_bu_tet_043_pylonePaug_151015.mxd # 366

Paugan substation

3 Paugan–Maniwaki transmission line

Line segment between Mont-Laurier tap and Maniwaki substation At Déléage, after the Mont-Laurier substation tap, the new line will run side-by-side with the existing line to the Route 105 crossing. For the entry to Maniwaki substation, Hydro-Québec has selected Variant A, which routes the new line south of the current line, passing between existing buildings. The company optimized this variant based on concerns expressed by local representatives and affected landowners. The line segment will be supported by four-legged lattice towers as well as reduced-footprint lattice towers.

This 4.5-km segment will be built to the west of the existing line ComposantesProject components du projet

and require widening the right-of-way by 26.3 m. TracéSelected retenu route LigneLine to à bereconstruire rebuilt LigneLine to à bedémanteler dismantled

PostesExisting et substations lignes de transport and transmission existants lines

EXPANSION OF THE ENTRY TO MANIWAKI SUBSTATION 200 69 kV # 120 kV 190 75°58' 75°56' 700 180 Lac de la # Lac Maniwaki Barbotte A Grier

substation n 180 180 i Crique l

u 190

190  o

P

e des u Hall 200 R

190

210 Quatre 105 180 des 190

Rivière Gatineau 220 180 Fourches

200 46°23'15"

Crique 46°23'15"

Maniwaki e A n g substation Rue Lafrance ta 107 n  o M Rue Mo ntreuil la e

Rue Éthier d

x in u m re e ou h m C A Ch 190 e mi s 180 n de

180 190

Mont-Laurier tap !

190

r

e

i

r

u

a

L 200 46°22'30" e 46°22'30" u R 190 0 290 580 m Rue King 180 Lac MTM, zone 9, NAD83 Godin 210 200 Rue McDougall 7339_bu_tet_021_Maniwaki_151015.mxd 220 75°58' Lac Scott 75°56'

Maniwaki substation

4 LINE SEGMENT FROM THE MONT-LAURIER SUBSTATION TAP TO MANIWAKI SUBSTATION

Planned 120-kV Existing 120-kV Maniwaki # double-circuit line double-circuit line  substation (Déléage area) Mont-Laurier tap 105

Messines # substation

Gracefield # New right-of-way boundary

substation Current right-of-way boundary Current right-of-way boundary (to be rebuilt) d x 32 to 35 m 22 to 38 m m . 5 1 0 1 5

# 1

Kazabazua i _ n 301 substation a M e n l o y p _

4 5.0 m 26.3 m widening 15.2 m 15.2 m

# 4

Paugan 0 _ t Clearing substation e 19.5 m 22.0 m t

_ easement u b _ 9

105 3 7339_buf1_tet_016_ligneMani_150505.fh9 3 7 # 366

5 Gracefield substation and supply line

Selected substation site Planned Gracefield substation The new 120/25-kV Gracefield substation will  be adjacent to the existing substation, near Route 105. This site is close to the load centre Gracefield substation and 25-kV distribution system and uses the existing access road and ditches. It minimizes environmental and social impacts by limiting

  modifications to the landscape.

 The fenced area of the planned substation will be about 100 m by 75 m, not including drainage ditches on its periphery. While the

 planned substation will be built primarily on a   lot belonging to Hydro-Québec, the company must acquire part of the adjacent property to accommodate all equipment.

 The substation will be supplied by two 120-kV circuits from the main line. A prefabricated 105 building will house the control, protection and telecommunications equipment. 0 50 100 m Related work will be required at Paugan and UTM, zone 18, NAD83 Maniwaki substations to add or modify 120-kV 7339_bu_tet_045_poste_151015.mxd outgoing line structures. This work will take place entirely on Hydro-Québec property.

Gracefield substation supply line Based on the draft-design studies and the public consultation process, Hydro-Québec selected Route A. This 5.3-km route runs along property boundaries for about 1.8 km, then crosses Chemin Henri and 800 m further turns to follow the relief for better landscape integration and reduced visibility from Route 105. This route also limits the impact on farmland and some wetlands. The substation supply line will be supported by guyed steel lattice towers in forested areas and reduced-footprint towers in farmland. The planned right-of-way is 39 m wide.

6 GRACEFIELD SUBSTATION SUPPLY LINE Chemin

15 15A Lac 76°2' 15 76°0' Paquin 15 220

C C h h e 160 e 40 39 38 37 36 35 34 33 32 31 m 30A 29 28 27 26 26 m i

n

i n 16 230 200

200 H d u 220 210 e n 46°7'30"

r D 46°7'30" i

o

m

a 

i 17

n e 105 150

210 18

200

19 200 route Ch em 30B in 180 220 La ch ap el 20 le 25

Selected 200 190 21

200 200 46°6'45" 190 46°6'45" 190 180 35 44A 43A 42 41 190 33A 33B 34

170

h ep os Project components 160 -J 170 nt ai 170 S Planned Gracefield substation 180 e Rivière-Gatineau u 180 R la Selected route Gatineau 200 de Transmission line to be rebuilt Planned Gracefield substation 30 32 33 34 35 32A31 32B 200 160 d Current Gracefield substation an Chemin 200 # rtr # Existing 69-kV substation and Be hemin transmission line 210 C Rivière031 330 660 m

180 30 The property boundaries shown on this map are MTM, zone 9, NAD83 76°2' 7339_bu_tet_020_derivation_151015.mxd approximate76°0' and provided for reference only. 6°6' 46°6' 4 150

230

Planned 120-kV Maniwaki # double-circuit line  substation Mont-Laurier tap 105

Messines # substation Right-of-way boundary Right-of-way boundary Gracefield # substation (to be rebuilt) 22 to 38 m

# Kazabazua 301 substation

5.0 m 19.5 m 19.5 m 5.0 m Paugan # substation Clearing easement 39.0 m Clearing easement

105 7339_buf2_tet_017_ligneDeri_150505.fh9 # 7339_bu_tet_042_pyloneGrace_151015.mxd 366

7 Tangible support for About the construction work community development Hydro-Québec has planned two phases of construction work. The first phase involves Hydro-Québec sees its projects as an opportunity to building Gracefield substation and its supply participate in the development of host communities line and rebuilding the transmission line through the Integrated Enhancement Program (IEP). between Paugan substation and the Once the work has begun, the company grants Gracefield substation tap. eligible organizations funding equivalent to 1% of the initially authorized value of the new facilities The second phase consists of rebuilding covered by the IEP. the transmission line to the Mont-Laurier tap and building the new line segment from the tap to Maniwaki substation.

To minimize the project’s impacts, Schedule Hydro-Québec will implement a range of mitigation measures, ensure environmental Permitting 2016 compliance monitoring of the worksite and Land clearing, rehabilitate the sites after construction. dismantling of line and construction of Public participation substation and new lines Fall 2016–Fall 2018 Starting in 2014, Hydro-Québec informed Dismantling of existing substation 2018-2020 and consulted with the various groups affected by the project: official representatives of the communities, local organizations, members of the business community, ministries, affected landowners and citizens. For more information This process made it possible to develop mitigation measures to adapt the project to Julie Léonard local realities, taking into account the results Advisor – Community Relations – Laurentides of the technical, economic and environmental Direction – Affaires régionales et collectivités studies carried out for the project. E-mail: [email protected] Once the necessary government permits Info-project Line – Laurentides have been obtained, Hydro-Québec will contact the groups affected to present 1 8 0 0 4 6 5-1 5 2 1, ext. 6 0 2 2 the planned construction schedule.

www.hydroquebec.com/projects/gracefield.html

Ce document est également publié en français. This is a translation of the original French text. 2015E1395-A

100 %