<<

D.P.R. of The IWMP-I (2009-10) Block-, Distt.-

Department of Land Development and Water Resources, Bhoomi Sanrakshan Adhikari, L.D.W.R., Auraiya at Ajeetmal Division Kanpur

1

CERTIFICATE

This is certified that the proposed Project (IWMP-I) having Eleven Micro-Watersheds of Block-Bidhuna, District Auraiya, (U.P.) has been selected for its sustainable development of manageemnt of natural resources on watershed basis under Integrated Watershed Management Programme. The treatable rainfed area is physically available for proposed interventions and is not overlapping with any other schemes. It will be developed and managed by as per Common Guidelines for Watershed Development Project-2008, GOI, New . The significant results will be achieved through proposed interventions on soil and water conservation, ground water recharge, availability of drinking and irrigation water, agricultural production systems, live stock, fodder availability, livelihoods of asset less peoples, capacity building, etc. The proposed Detailed Project Report of IWMP-I, 2009-10 is submitted for its approval.

Soil Conservation Officer Deputy Director Land Development and Water Resource Land Development and Water Resource Auraiya at Ajeetmal (U.P.) , Kanpur (U.P.)

Project Director Chief Development Officer DRDA, Auraiya (U.P.) Distt.-Auraiya (U.P.)

2 EXECUTIVE SUMMARY

All the micro-watersheds of IWMP-I, 2009-10 are situated in Bidhuna Block of District Auraiya, Uttar Pradesh. The project consists of eleven micro-watersheds namely Sabhad (2C4B5a4d), Mau (2C4B5a4c), Marha Macchi Jhil (2C4B5a4b), Belpur Bela (2C4B5a4a), Banthara (2C4B5a2d), Dondapur (2C4B5a2c), Babina Sukhchenpur (2C4B5a1d), Bhadasiya (2C4B5a1c), Indpamau (2C4B5a1b), Asjana (2C4B5a1c (L)) and Sarai Pratham (2C4C2c1d (L)) . All these microwatersheds spread over in 45 villages of 31 Gram Panchayat. The total geographical area of the IWMP-I is 8269.851 ha, out of which 6177.00 ha is treatable under Integrated Watershed Management Programme IWMP-I. All micro-watershed falls in agro-climatic zone of Central Plain Zone representing semi-arid ecological sub-region. The microwatersheds of IWMP-I is situated at an elevation of some 135m to 152m above mean sea level and has relief from 11m. to 16m. The watershed has a general slope is about 1.00 per cent. General topography of the watershed is mild to gentle. Elevation range and relief are given in Table 2.3.

Spatial distribution of different slope classes was prepared using Arc GIS. Slope was divided into five classes’ viz. 0-0.5, 0.5- 1.0, 1-3, 3-5, and more than 5 per cent. Per cent areal extent of different slope classes in IWMP-I micro-watershed is shown in Table 2.4. The dominant slope category in the micro-watershed were 1-3 per cent (39%) followed by 3-5 per cent (28%). on an average 17 per cent of the population is scheduled caste. Population details of the IWMP-I are depited in Table 3.1. In general 7 per cent opulation migrate from the project area due to drought and earn more money, however, migration was more than 50 per cent during 2007-08 due to continuous drought from 2004 to 2007 in the region.

Major crops of the watershed are Urd, Moong, Sorghum, Paddy and Arhar during kharif and Pea, , , Massor and mustard during rabi. The productivity of these crops is significantly lower than the national and state average. The cropping intensity during kharif is significantly lower than the rabi . The pre-dominant tree species are Neem (Azadirachta indica), Babool (Acacia nilotica) , Palas and Ber ( Zizyphus spp.) etc .

3

Participatory Rural Appraisal (PRA) exercise was conducted to understand the people’s needs and problems. The exercise brought out pressing needs and preferences of people for water harvesting structures through pucca checkdams on ephemeral streams, earthen bunding to protect soil erosion from agricultural fields along with field drainage structure, crop varieties with improved package of practices, agroforestry interventions and improved cultivation of fodder production, etc.

The Watershed Committee (WC) and SHGs have been constituted according to IWMP Guideline-2008. Active participation and co-operation of community will be ensured by building their capacities through exposures and trainings. The overall BC ratio of the project is estimated to be more than 2.00 as compared to the 1.55 in pre project scenario .

4

CONTENTS

No. Particulars Page Nos. 1. INTRODUCTION AND PROJECT BACKGROUND 1.1 Project Background 9 1.2 Need and scope for Watershed Development Programme 13 1.3 Weightage for the selection of the proposed watershed 13 1.4 Details of ongoing watershed development programme 15 2. GENERAL DESCRIPTION OF THE PROPOSED PROJECT AREA 2.1 Location 16 2.2 Area and Land use 21 2.3 Physiography 25 2.4 Climate 27 3. BASELINE SURVEY AND PARTICIPATORY RURAL APPRAISAL 3.1 Socio-Economic Analysis 29 3.2 Soil Texture 64 3.3 Major Crops and its productivity 65 3.4 Agroforestry nad Horticulture 77 3.5 Livestock and Fisheries 80 3.6 Foresh and Grass Land 88 3.7 Livelihood Status 91 4. INSTITUTIONAL BUILDING AND PROJECT MANAGEMENT 4.1 Project Implementing Agency 112 4.2 Details of formation of SHGs and User Groups 113-174 4.3 Convergence in IWMP-I, Auraiya 175 5. MANAGEMENT / ACTION PLAN 176 5.1 Entry Point Activity (EPA) 177 5.2 Work Phase 180 6. CAPACITY BUILDING PLAN 181-208 7. PHASING OF PROGRAMME AND BUDGETING 209-211 7.1 Monitoring and Evalution 212 7.2 Annual Action Plan 213 7.3 Details of Convergence 214 8. CONSOLIDATION AND WITHDRAWAL STRATEGY 215

5

No. Particulars Page Nos. 9. EXPECTED OUTCOME 9.1 Employment generation and checking migration 216 9.2 Other expected outcome 216 10. MAPS (Satellite Image of the Project Area, Cadastral Map, Contour Map, Drainage map, MWSs Map & Action plan map) 11. ANNEXURE-I PARAMETERS 218 12. ANNEXURE-II CONTRIBUTION TO WATERSHED DEVELOPMENT FUND (WDF) 219-220 13. ANNEXURE-III LIVELIHOOD ACTION PLAN FOR LANDLESS/ASSETLESS 221-223

6 LIST OF TABLES

S.No. Particulars Page Nos. 1 Table 1.1: Basic Project Information 9 2 Table 1.2: Approved plan Preliminary Project Report (PPR) by Steering Committee (SC), Govt. of 10 3 Table 1.3: Details of Micro Watersheds 10-13 4 Table 1.4: Weigthage Criteria (for score) 13-14 5 Table 2.1: General Description of the Project Area 16-20 6 Table 2.2: Details of land resources in IWMP-I of Auraiya 21-24 7 Table 2.3: Slope range in the project area for IWMP-I in Auraiya 25 8 Table. 2.4 : Areal extent of various slope classes in the micro-watershed of IWMP-I 26 9 Table 2.5: Average monthly rainfall of the last 05 years 27 10 Table 2.6: Flood and Drought Area 28 11 Table 3.1: Demographic Features in Project Area 29-32 12 Table 3.2: Details of land holding pattern 33-43 13 Table 3.3: Details of Migration: from project area (IWMP-I Auraiya) 44-46 14 Table 3.4: Details of Village Infrastructure 47-57 15 Table. 3.5 Details of Common Property Resources In IWMP-I, Auraiya 58-63 16 Table 3.6: Soil Texture 64 17 Table 3.7: Microwatershed wise details of crops, their productivity and production 65-75 18 Table 3.8: Food, Fodder and fuel production in the proejct area (IWMP-I District, Auraiya) 76 19 Table 3.9: Horticulture Status 77-79 20 Table 3.10: Live Stock Population 80-83 21 Table 3.11: Productivity of Live Stock 84-87 22 Table 3.12: Forest, Vegetative Cover/Grass Land 88-91 23 Table 3.13: Livelihood status of landless people IWMP-I Auraiya 92-95 24 Table 3.14: Details of Live Stock status of the farmers 96-99 25 Table 3.15: Present Livelihood status 100-103 26 Table 3.16: Ground Water Status 104-106 27 Table 3.17: Irrigation Status 106-109 28 Table 3.18: Source-wise irrigated area 109-112 29 Table 4.1: Details of Project Implementing Agency (PIA) 112 30 Table 4.2: Details of Staff of PIA 113 31 Table 4.3: Details of Watershed Development Team (WDT) 114 32 Table 4.4: Details of Watershed Committee (WC) 115-145

7 S.No. Particulars Page Nos. 34 Table 4.5 Villagewise details of SHG 146-158 35 Table 4.6: Details of Self Help Groups 159-162 36 Table 4.7: Village wise details of UGs 163-174 37 Table. 4.8 : List of Central/State sponsored schemes 175 38 Table. 4.9 : Details Convergence wtih MNREGA 176 39 Table 5.1: Detail of EPA Activities and their expenditure 177-179 40 Table 5.2: Runoff and soil erosion in the project area 181-182 41 Table 5.3 Microwatershed wise detail of Proposed activities 183-186 42 Table. 5.4 : Village/Gram Panchayat/Watershed Committee wise detail of Proposed activities 187- 43 Table 6.1: List of identified training institutes for capacity building 209 44 Table 6.2: Training to stakeholders on participatory watershed management 210 45 Table 6.3: Capacity Building Annual Action Plan 211 46 Table 7.1: Physical, financial targets, outlays and their year wise breakups 213 47 Table 7.2: Details of proposed watershed wise Convergence in the project 214 48 Table 9.1 Expected Benefits 216

8 CHAPTER-1 INTRODUCTION AND PROJECT BACKGROUND

1.1: Project Background: IWMP-1 project is located in Bidhuna Block of Auraiya District, U.P. The project is a cluster of 11 Micro watersheds with 2C4B5a4d, 2C4B5a4c, 2C4B5a4b, 2C4B5a4a, 2C4B5a2d, 2C4B5a2c, 2C4B5a1d, 2C4B5a1c, 2C4B5a1b, 2C4B5a1c and 2C4B5a1d being their respective codes. The total project (geographical) area of the watershed cluster is about 8269.851 ha out of this 6177.00 ha has been undertaken to be treated under Integrated Watershed Management Program (IWMP-I) with starting year 2009-10.

Table 1.1: Basic Project Informations :

Sl.No. Details No. Area (ha.) 1 2 3 4 1 Total Geographical area and micro watersheds in the project (Before start of IWMP in district) 257 128342.00 2 Workable Micro Watersheds and Geographical/treatable area 11 8269.85/ 6177.00 3 Micro Watersheds already treated by LDWR & other agencies 101 50550.00 4 Balance Micro Watersheds/ Geographical area for treatment (After IWMP-Ist) 145 69523.00

9 Table 1.2: Approved plan Preliminary Project Report (PPR) by Steering Committee (SC), Govt. of India:

Year Name of Project MWS Geographical Project PIA S.C. /Treatable Area Cost Meeting (ha) Rs. lakh Date 1 2 4 5 6 7 8 2009-10 IWMP-I Auraiya 11 8269.85 /6177.00 741.24 B S A Auraiya at Ajeetmal 25.02.2009

Table 1.3: Details of Micro Watersheds:

Name of the Name of the Microwat Name of the Treatable watershed in which S.No. Micro ersheds Gram Panchayat Village proejct Aera (ha) Proposed MWS is Watersheds Code situated 1 2 3 4 5 6 7 1. IWMP-I, 1. Badin (E.K.) 1. Bhatura (E.K.) 14.012 Arind River Auraiya 2. Gura 2. Gura 54.731 Sabhad 2C4B5a4d 3. Sabhad 3. Sabhad 422.009

Total 490.752 2. " " Badin (E.K.) 4. Badin (E.K.) 50.131 " " 4. Bhatoli 5. Bhatoli Bidhuna 11.231 5. Marha Macchi Jhil 6. Chakarpur 20.073 Gura Gura 40.643 6. Harchandpur (E.K.) 7. Jagatpur, (E.K.) 40.362 Mau 2C4B5a4c Marha Macchi Jhil 8. Marha Machhi Jhil 9.622 7. Mau 9. Mau 377.094 Mau 10. Narayanpur Sahar 17.243 Gura 11. Rajpur Bidhuna 130.562 Sahbad Sabhad 200.543 Total 897.504 3. " " Marha Macchi Jhil Chakarpur 25.147 " " Mau 12. Khizarpur 32.253 Marha Macchi Jhil Marha Machhi Jhil 132.199 Marha Macchi Mau Mau 17.217 2C4B5a4b Jhil Mau Narayanpur Sahar 140.115 Gura Rajpur Bidhuna 8.324 8. Rathgaon (E.K.) 13. Rathgaon (E.K.) 80.586 9. Sanwaliya 14. Sanwaliya 80.643 Total 516.484

10

S.No. Name of the Name of the Village Treatable Name of the watershed Microwaters proejct Micro Aera (ha) in which Proposed heds Code Watersheds MWS is situated 1 2 3 4 5 6 7 4. " " 10. Banthara 15. Banthara 30.651 Arind River 11. Belpur Bela 16. Belpur Bela 30.013 Belpur Bela 2C4B5a4a Rathgoan (EK) Rathgaon (E.K.) 180.154 Sanwaliya Sanwaliya 49.453 Total 290.271 5. " " Banthara Banthara 251.541 " " 12. Bashai 17. Bashai 20.023 Belpur Bela Belpur Bela 155.845 Marha Machhi Jhil Marha Machhi Jhil 50.458 Banthara 2C4B5a2d 13. Pusauli 18. Narainpur Bhanu 60.543 Rathgaon (E.K.) Rathgaon (E.K.) 8.413 Sanwaliya Sanwaliya 25.031 14. Tajpur Bidhuna 19. Tajpur Bidhuna 60.683 Belpur Bela 20. Kiratpur 60.751 Total 693.288 6. " " Bashai Bashai 12.831 " " 15. Dondapur 21. Dondapur 150.128 Pusauli Narainpur Bhanu 17.031 Dondapur 2C4B5a2c 16. Alipur 22. Palia 15.355 Pusauli 23. Pusauli 116.641 Tajpur Bidhuna Tajpur Bidhuna 150.865 Total 462.851 7. " " 17. Babina Sukhchenpur 24. Babina Sukhchenpur 123.801 " " Belpur Bela Belpur Bela 8.500 Babina 2C4B5a1d 18. Pasua 25. Pasua 32.213 Sukhchenpur Rathgaon (E.K.) Rathgaon (E.K.) 75.951 19. Sarai Pratham 26. Sarai Pratham 70.438 Total 310.903

11 S.No Name of Name of the Village Treatable Name of the watershed Microwater- Name of Gram . the proejct Micro Aera (ha) in which Proposed sheds Code Panchayat Watersheds MWS is situated 1 2 3 4 5 6 7 8. " " Babinapur Sukchenpur Babina Sukhchenpur 20.203 Arind River Babinapur Sukchenpur27. Bampur Rampur 35.513 20. Bamrauliya 28. Bamrauliya 150.408 21. Bhadsiya 29. Bhadsiya 150.544 22. Bhikhra 30. Bhikhra 131.453 Dondapur Dondapur 4.522 23. Indpamau 31. Indapamau 10.910 Bhadhasiya 2C4B5a1c 24. Mahrokh Mit 32. Marhokh Hariram 41.054 Marhokh Mit 33. Marhokh Mit 21.224 Pusauli Narayanpur Bhanu 5.361 Bhadsiya Pusauli 34. Nawada Malkhan 66.301 25. Rooppur Sahar Pusauli 21.842 35. Roopur Sahar 86.511

Total 745.846 9. " " 26. Asjana 36. Asjana 55.412 " " Asjana 37. Barka 38.500 Bhikhra Bhikhra 26.910 Indpamau Indapamau 178.030 Indpamau 2C4B5a1b 27. Rawatpur (ALD) 38. Rawatpur ALD) 111.84 Roopur Sahar Rooppur Sahar 102.415 Rooppur Sahar 39. Vimtamau 135.432 Bhadasiya Nawada Malkhan 5.344 Total 653.883 " " Asjana Asjana 170.046 " " 10. Asjana 2C4B5a1c (L) Asjana 40. Hathnapur 100.642 Rooppur Sahar Vimatamau 75.913 Total 346.601

12

Name of the Name of the Name of Gram Panchayat Village Treatable Name of the watershed in S.No Microwater- proejct Micro Aera (ha) which Proposed MWS is . sheds Code Watersheds situated 1 2 3 4 5 6 7 11 . " " Pasua Pasua 53.801 " " 28. Udelapur (ALD) 41. Purwa Bhadauria Ruru (ALD) 25.543 Sarai Pratham Sarai Pratham 60.841 Saray 2C4B5a1d (L) 29. Shahoopur (ALD) 42. Malikpur Mishripur (ALD) 35.00 Pratham 30. Ruru Kala (ALD) 43 Kariapur Ruru (ALD) 20.363 31. Shivpur (ALD) 44. Shivpur (ALD) 452.856 Udelapur (ALD) 45. Udelapur (ALD) 120.213 Total 768.617 Grand Total 6177.00

1.2: Need and scope for Watershed development programme:

Watershed Development Programme is prioritized on the basis of thirteen parameters namely Poverty index, Percentage of SC/ST population, Actual wages, Percentage of small and marginal farmers, Ground water status, Moisture Index, Area under rainfed agriculture, Drinking water situation, Percentage of the degraded land, Productivity potential of the land, Continuity of another watershed that has already been treated, and Cluster approach for the area. Cluster approach was followed taken into consideration for micro-watersheds covering a total geographical area of 8269.85 ha with a cumulative score of 90. (Reference Table given below)

1.3: Weightage for the selection of the watershed:

Project Project Weightage under the criteria name type I II III IV V VI VII VIII IX X XI XII XIII Total 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 IWMP-1 Drought 7.5 5.0 5.0 10.0 5.0 0.0 5.0 7.5 10.0 10.0 10.0 15.0 0.0 90.0

13 Table 1.4: Weigthage Criteria (for score): S. Maximu Criteria Ranges & scores No. m score i Poverty index (% of poor to 10 Above 80 % (10) 80 to 50 % (7.5) 50 to 20 % (5) Below 20 % population) (2.5) ii % of SC/ ST population 10 More than 40 % (10) 20 to 40 % (5) Less than 20 % (3) iii Actual wages 5 Actual wages are significantly Actual wages are equal to lower than minimum wages or higher than minimum (5) wages (0) iv % of small and marginal farmers 10 More than 80 % (10) 50 to 80 % (5) Less than 50 % (3)

v Ground water status 5 Over exploited (5) Critical (3) Sub critical (2) Safe (0) vi Moisture index/ 15 -66.7 & below (15) -33.3 to -66.6 (10) 0 to -33.2 (0) DPAP/ DDP Block DDP Block DPAP Block Non DPAP/ DDP Block vii Area under rain-fed agriculture 15 More than 90 % (15) 80 to 90 % (10) 70 to 80% (5) Above 70 % (Reject) viii Drinking water 10 No source (10) Problematic village (7.5) Partially covered (5) Fully covered (0) ix Degraded land 15 High – above 20 % (15) Medium – 10 to 20 % (10) Low- less than 10 % of TGA (5) x Productivity potential of the land 15 Lands with low production & Lands with moderate Lands with high where productivity can be production & where production & where significantly enhanced with productivity can be productivity can be reasonable efforts (15) enhanced with reasonable marginally enhanced with efforts (10) reasonable efforts (5) xi Contiguity to another watershed 10 Contiguous to previously Contiguity within the Neither contiguous to that has already been developed/ treated watershed & microwatersheds in the previously treated treated contiguity within the project but non contiguous watershed nor contiguity microwatersheds in the project to previously treated within the (10) watershed (5) microwatersheds in the project (0) xii Cluster approach in the plains 15 Above 6 micro-watersheds in 4 to 6 microwatersheds in 2 to 4 microwatersheds in (more than one contiguous cluster (15) cluster (10) cluster (5) micro-watersheds in the project) Cluster approach in the hills Above 5 micro-watersheds in 3 to 5 microwatersheds in 2 to 3 microwatersheds in (more than one contiguous cluster (15) cluster (10) cluster (5) micro-watersheds in the project)

14 • The total no. of families under BPL is 3439 out of 6719 household family which is 51.18% of the total households of the Watershed. • The percentage of schedule caste in the watershed is about 30% to the total population. • Rainfed agriculture forms the primary occupation of the watershed due to scant irrigation and ground water availability. • More than 90 percent of the farmers are small and marginal by nature and the actual wages earned by the labour is less than the minimum wages hence a score of 10 is given. • Since the rainfall received is erratic and irregular, the Moisture index is low and the area is classified under IWMP block. • Drinking water is problematic in the watershed. • Some part of land is degraded. The soil is very permeable and production of the land can be significantly enriched with the availability of timely irrigation.

1.4 Details of ongoing watershed programme

Presently there is no watershed development programme is going on in this selected micro-watersheds.

15 CHAPTER – 2

GENERAL DESCRIPTION OF PROJECT AREA

2.1 Location : The micro-watersheds of IWMP-I is located in Bidhuna block of Araiya district. It is about 40 km. from Auraiya on Auraiya to Bidhuna road. Location (lat/long), Gram Panchayat, villages and its geographical area for each micro-watershed are depicted in Table 2.1. Total area of the project is 8269.85 ha, out of which treatable area is 6177 ha. The geographical area of micro-watershed varied in the range of 322.172 ha to 1272.106 ha.

Table 2.1 : Micro-watershed wise details of location, Gram Panchayat, Village and Geographical area of IWMP-I

Area of Name of village Details of important/ Sl. Name of Micro- included in Latitude/ Longitude Name of GP Name of Villages approach road with No. Block watershed MWS distance Km. with Code (Geographica l) 1 6 2 3 4 5 7 8 29 0 51' 30"N to 29 0 52' 45" N 1. Badin (E.K.) 1. Bhatura 24.038 Auraiya to Sabhad Sabhad 1 Bidhuna 79 0 30'15'' E to 79 0 32 ' 30'' E 2. Gura 2. Gura 54.889 road 41km. from (2C4B5a4d) 3. Sahbad 3. Sabhad 522.009 auraiya TOTAL 600.937 26 0 51' 0"N to 26 0 51' 45" N Badin (E.K.) 4. Badin 52.876 79 0 30' 0'' E to 79 0 -30 ' 45'' E 4. Bhatoli Bidhuna 5. Bhatoli Bidhuna, 12.156 Badin (E.K.) Bhatura, 0.136 5. Marha Machhi jhil 6. Chakarpur, 26.801 Gura Gura, 44.025 6. Harichandpur (EK) 7. Jagatpur, 47.757 Auraiya to Madamajhi Mau 2 Bidhuna 7. Har Chandapur (E.K.) 8. Karmoopur, 1.688 Jheel road 39km. from (2C4B5a4c) 8. Bidhuna (NP) 9. Khan Jahanpur Sahar 16.653 auraiya Marha Machhi Jhil 10. Marha Machhi Jhil 10.165 9. Mau 11. Mau 409.721 Mau 12. Narayanpur Sahar 17.992 Gura 13. Rajpur Bidhuna 147.152 Sabhad Sabhad 230.075 TOTAL 1017.197

16 Area of Name of village Details of important/ Sl. Name of Micro- included in Latitude/ Longitude Name of GP Name of Villages approach road with No. Block watershed MWS distance Km. with Code (Geographica l) 1 6 2 3 4 5 7 8 Marha Machhi Jhil Chakarpur 30.119 Khan Jahanpur Sahar Khan Jahanpur Sahar 0.177 Mau 14. Khizarpur 38.565 Marha Machhi Jhil Marha Machhi Jhil 142.041 Marha Machhi 26 0 50' 0"N to 26 0 51' 0" N Auraiya to Narayanpur Mau Mau 19.801 3 Bidhuna Jhil 79 0 29' 45''E to 79 0 32' 0'' E Sahar road 40km. from Mau Narayanpur Sahar 150.287 (2C4B5a4b) auraiya Gura Rajpur Bidhuna 10.991 10. Rathgaon (E.K.) 15. Rathgaon 87.886 Sabhad Sabhad 0.135 11. Sanwaliya 16. Sanwaliya 87.452 TOTAL 567.454 12. Banthara 17. Banthara 34.996 26 0 48' 45"N to 26 0 50' 15" N Auraiya to Belpur Bela Belpur Bela 13. Belpur Bela 18. Belpur Bela 35.341 4 Bidhuna 79 0 29' 15''E to 79 0 31 ' 30'' E road 33km. from (2C4B5a4a) Rathgaon (E.K.) Rathgaon 192.903 auraiya Sanwaliya Sanwaliya 58.932 TOTAL 322.172 Banthara Banthara 272.136 Sanwaliya 19. Bashai 23.332 Belpur Bela Belpur Bela 175.968 Bidhuna (NP) 20. Bidhuna (NP) 11.839 26 0 48' 0"N to 26 0 50' 30" N Marha Machhi Jhil Marcha Machhi Jhil 58.269 Auraiya to Banthara Banthara 5 Bidhuna 79 0 30' 0''E to 79 0 31 ' 45'' E 14. Pusauli 21. Narainpur Bhanu 69.735 road 36km. from (2C4B5a2d) Rathgaon (E.K.) Rathgaon 10.710 auraiya Sabhad Sabhabd 3.380 Sanwaliya Sanwaliya 35.831 15. Tajpur Bidhuna 22. Tajpur Bidhuna 65.746 Belpur Bela 23. Kiratpur 70.831 TOTAL 797.778

17 Name of Area of village Details of Sl. Name of Micro- included in important/ approach Latitude/ Longitude Name of GP Name of Villages No. Block watershed MWS road with distance with Code (Geographical) Km. 1 6 2 3 4 5 7 8 16. Alipur 24. Alipur 5.742 17. Bamrauliya 25. Bamrauliya 0.998 Sanwaliya Bashai 14.266 Auraiya to 26 0 48' 0"N to 26 0 49' 30" N Dondapur 18. Dondapur 26. Dondapur 177.749 Narayanpur Bhanu 6 Bidhuna 79 0 32' 15''E to 79 0 33 ' 0'' E (2C4B5a2c) Pusauli Narainpur Bhanu 23.673 road 34km. from

Alipur 27. Palia 22.509 auraiya Pusauli 28. Pusauli 129.038 Tajpur Bidhuna Tajpur Bidhuna 198.197 TOTAL 572.173 19. Babina Sukhchenpur 29. Babina Sukhchenpur 155.636 Belpur Bela Belpur Bela 11.506 20. Bhikhra 30. Bhikhra 0.141 Bidhuna (N.P.) Bidhuna N.P. 305.923 Babina 260 48' 0"N to 260 48' 45" N Bidhuna (NP) 31. Chandarpur 0.488 Auraiya to Shivpur 7. Bidhuna Sukhchenpur 390 30' 0''E to 790 -30' 45'' E Pusauli Narayanpur Bhanu 1.157 road 37km. from (2C4B5a1d) 21. Pasua 32. Pasua 40.395 auraiya Rathgaon (EK) Rathgaon 95.584 22. Sarai Pratham 33. Sarai Pratham 78.792 23. Shivpur (ALD) 34. Shivpur 0.472 Belpur Bela Kiratpur 2.083 TOTAL 692.178

18 Area of village Name of Micro- Details of important/ Sl. Name of included in watershed with Latitude/ Longitude Name of GP Name of Villages approach road with No. Block MWS Code distance Km. (Geographical)

1 6 2 3 4 5 7 8

Babina Sukhchenpur Babina Sukhchenpur 25.992 Babina Sukhchenpur 35. Bampur Rampur 41.197 Bamrauliya Bamrauliya 183.351 24. Bhadasiya 36. Bhadsiya 177.669 Bhikhra Bhikhra 153.477 Bidhuna (NP) Bidhuna (NP) 5.676 Bidhuna (NP) Chandarpur 180.955 Dondapur Dondapur 6.522 25. Indpamau 37. Indapamau 12.923 0 0 Auraiya to Bhadhasiya Bhadasiya 26 46' 0"N to 26 48 0" N Bidhuna (NP) 38. Maharajpur Bidhuna 50.690 8 Bidhuna 0 0 ' road 32km. from (2C4B5a1c) 79 30' 0''E to 79 33 15'' E 26. Marhokh Mit 39. Marhokh Hariram 47.310 auraiya Marhokh Mit 40. Marokh Mit 25.770 Pusauli Narainpur Bhanu 5.361 Bhadhasiya 41. Nawada Mal Khan 83.380 Alipur Palia 0.288 Pusauli Pusauli 28.293 27. Rawatpur (ALD) 42. Rawatpur 12.270 28. Rooppur Sahar 43. Roopur Sahar 100.946 Shivpur (ALD) Shivpur 34.728

TOTAL 1176.796 29. Asjana 44. Asjana 65.608 Asjana 45. Barka Purwa 44.714 Rawatpur (ALD) 46. Bhaipur 33.428 Bhikhra Bhikhra 33.673 0 0 Bidhuna (N.P.) Chandarpur 6.681 26 45 0"N to 26 46' 30" N Auraiya to Vimtamau Indapamau Indapamau Indapamau 198.002 9 Bidhuna 79 0 30' 0''E to 79 0 33 ' 45'' E road 36km. from (2C4B5a1b) Marhok Mit Marokh Mit 0.911 auraiya Bhadasiya Nawada Mal Khan 5.391 Rawatpur (ALD) Rawatpur 133.155 Rooppur Sahar Rooppur Sahar 119.508 Shivpur (ALD) Shivpur 8.374 Rooppur Sahar 47. Vimtamau 152.370 TOTAL 801.817

19 Details of Name of Area of village important/ Sl. Name of Micro- Latitude/ Longitude Name of GP Name of Villages included in MWS approach road No. Block watershed (Geographical) with distance with Code Km. 1 6 2 3 4 5 7 8 Asjana Asjana 216.412 Asjana Barkapurwa 0.048 Rawatpur (ALD) Bhaipur 2.194 Auraiya to Asjana 26 0 43' 30 "N to 26 0 46' 0" N Asjana 48. Hathnapur 115.827 Asjana road 10 Bidhuna (2C4B5a1c) 79 0 30' 30''E to 79 0 33 ' 0'' E 30. Jagupur (ALD) 49. Jagupur 32.765 29km. from (L) 31. Kaliyanpur Jagoo 50. Kaliyanpur Jagoo 2.777 auraiya 32. Purwa Patti (ALD) 51. Purwa Patti 0.036 Rawatpur (ALD) Rawatpur 0.289 Roopur Sahar Vimatamau 78.897 TOTAL 449.245 33. Barua 52. Barua 17.838 Rawatpur (ALD) Bhaipur 82.146 Barua 53. Bijaura 23.259 34. Chandaia (ALD) 54. Chandaia 39.984 Bidhuna (N.P.) 55. Kariapur Ruru 59.377 35. Shahoopur (ALD ) 56. Malikpur Mishripur 55.853 36. Purwa Pitaram 57. Muggpur 12.152 Saray Alipur Palia 7.907 Auraiya to Saray 260 44' 30"N to 260 47' 15" N Pratham Pasua Pasua 63.662 Pratham road 11 Bidhuna 790 27' 0''E to 790 30' 15'' E (2C4B5a1d) 37. Udelapur (ALD) 58. Purwa Bhadauria Ruru 33.615 34km. from

(L) Chandaia 59. Purwa Bhara Mal 10.488 auraiya Udelapur 60. Purwa Jhabra 34.870 Rawatpur (ALD ) Rawatpur 0.075 38. Ruru Kala 61. Ruru Kala 74.310 Sarai Pratham Sarai Pratham 65.946 Shahoopur (ALD) 62. Shahoopur 33.849 Shivpur (ALD) Shivpur 506.331 Udelapur (ALD) 63. Udelapur 150.446 TOTAL 1272.108 GRAND 8269.851 TOTAL

20 2.2: Area and Land use:

Village wise detailed information on type of land is depicted in Table 2.2. The total culturable land of the project is 6587.348 ha, out of which 207.50 (3.15%) ha land is under assured irrigation mainly by means of open shallow dug wells. The cultivable rainfed, temporary and permanent wastelands are about 88, 7 and 1.7 per cent, respectively, of culturable land of the project.

Table 2.2: Details of land resources in IWMP-I of Auraiya district

Area Detailed Villages Cultivated and Wasteland area of the within G.P. villages (ha) (Falling within the project) Sr. Name of the G.P./ Uncultivated No. W.C. Cultivated Cultivated Pvt. Agri. Land Commu wasteland/ fallow Forest Total rainfed irrigated - nity Others Perm Land area (ha) area area Temp. Gen Sc ST OBC Total land anent 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 1. Badin (E.K.) Bhatura 14.012 6.800 0.000 0.000 0.000 10.406 24.174 8.325 2.081 20.812 0.000 1.203 2.159 Badin 50.131 1.600 1.680 1.240 20.196 5.049 0.000 26.486 51.731 0.000 1.210 0.935 53.876 Total 64.143 8.400 1.680 1.240 28.521 7.130 0.000 36.892 72.543 0.000 2.413 3.094 78.050 2. Gura Gura 95.374 3.041 0.710 1.740 0.000 50.078 98.914 38.670 9.668 98.415 0.000 0.416 0.083 Rajpur Bidhuna 138.886 2.560 6.620 2.710 55.494 13.874 0.000 72.078 141.446 0.000 1.131 15.566 158.143 Total 234.260 5.601 7.330 4.450 94.164 23.541 0.000 122.156 239.861 0.000 1.547 15.649 257.057 3. Sabhad Sabhad 622.552 13.210 14.230 5.770 0.000 320.766 715.599 251.997 62.999 635.762 0.000 10.410 69.427 Total 622.552 13.210 14.230 5.770 251.997 62.999 0.000 320.766 635.762 0.000 10.410 69.427 715.599 4. Bhatoli Bhatoli 11.231 0.500 0.000 0.000 0.000 5.866 12.156 4.692 1.173 11.731 0.000 0.000 0.425 Total 11.231 0.500 0.000 0.000 4.692 1.173 0.000 5.866 11.731 0.000 0.000 0.425 12.156 5. Marha Macchi Jhil Marha Macchi Jhil 192.279 3.030 5.640 1.430 0.000 98.369 257.785 77.552 19.388 195.309 0.000 2.110 60.366 Chakarpur 45.220 0.560 1.640 0.890 17.956 4.489 0.000 23.335 45.780 1.640 1.100 8.400 56.920 Total 237.499 3.590 7.280 2.320 95.508 23.877 0.000 121.704 241.089 1.640 3.210 68.766 314.705 6. Harchandpur (E.K.) Jagatpur 40.362 3.700 1.420 0.840 0.000 22.451 47.757 17.289 4.322 44.062 0.000 0.641 3.054 Total 40.362 3.700 1.420 0.840 17.289 4.322 0.000 22.451 44.062 0.000 0.641 3.054 47.757

21 Area Detailed Villages Cultivated and Wasteland area of the within G.P. villages (ha) (Falling within the project) Sr. Name of the G.P./ Uncultivated No. W.C. Cultivate Cultivated Pvt. Agri. Land Commu wasteland/ fallow Forest Total d rainfed irrigated - nity Others Perm Land area (ha) area area Temp. Gen Sc ST OBC Total land anent 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 7. Mau Mau 394.311 5.840 7.840 1.640 159.404 39.851 0.000 200.896 400.151 2.013 5.013 22.345 429.522

Narayanpur Sahar 157.358 3.400 4.100 1.030 63.891 15.973 0.000 80.894 160.758 0.000 1.513 6.008 168.279 Khizarpur 32.253 1.950 1.140 0.000 13.681 3.420 0.000 17.102 34.203 0.000 0.811 3.551 38.565 Total 583.922 11.190 13.080 2.670 236.976 59.244 0.000 298.892 595.112 2.013 7.337 31.904 636.366 8. Rathgaon (E.K.) Rathgaon 345.104 3.500 9.410 4.410 137.678 34.419 0.000 176.507 348.604 0.000 4.813 33.666 387.083

Total 345.104 3.500 9.410 4.410 137.678 34.419 0.000 176.507 348.604 0.000 4.813 33.666 387.083 9. Sanwaliya Sanwaliya 155.217 4.050 3.120 1.940 62.931 15.733 0.000 80.603 159.267 0.000 1.518 21.430 182.215

Total 155.217 4.050 3.120 1.940 62.931 15.733 0.000 80.603 159.267 0.000 1.518 21.430 182.215 10. Banthara Banthara 282.192 3.010 3.843 1.043 113.664 28.416 0.000 143.122 285.202 0.000 2.413 19.517 307.132

Total 282.192 3.010 3.843 1.043 113.664 28.416 0.000 143.122 285.202 0.000 2.413 19.517 307.132 11. Belpur Bela Belpur Bela 194.358 2.700 3.201 1.009 78.420 19.605 0.000 99.033 197.058 0.000 4.041 21.716 222.815

Kiratpur 60.751 2.400 1.013 0.987 24.866 6.216 0.000 32.069 63.151 0.000 0.643 9.120 72.914 Total 255.109 5.100 4.214 1.996 103.286 25.821 0.000 131.102 260.209 0.000 4.684 30.836 295.729 12. Bashai Bashai 32.854 2.520 1.030 0.130 14.098 3.524 0.000 17.752 35.374 0.000 0.713 21.511 57.598

Total 32.854 2.520 1.030 0.130 14.098 3.524 0.000 17.752 35.374 0.000 0.713 21.511 57.598 13. Pusauli Pusauli 138.483 5.800 3.107 1.610 57.069 14.267 0.000 72.947 144.283 0.000 2.419 10.629 157.331

Narayanpur Bhanu 82.935 2.960 2.101 1.034 33.944 8.486 0.000 43.465 85.895 0.000 1.518 30.505 117.918 Total 221.418 8.760 5.208 2.644 91.013 22.753 0.000 116.412 230.178 0.000 3.937 41.134 275.249 14. Tajpur Bidhuna Tajpur Bidhuna 211.548 4.120 3.204 1.900 85.507 21.377 0.000 108.784 215.668 6.403 4.416 37.456 263.943

Total 211.548 4.120 3.204 1.900 85.507 21.377 0.000 108.784 215.668 6.403 4.416 37.456 263.943 15. Dondapur Dondapur 154.650 2.243 2.840 1.231 62.265 15.566 0.000 79.062 156.893 0.000 3.713 23.665 184.271

Total 154.650 2.243 2.840 1.231 62.265 15.566 0.000 79.062 156.893 0.000 3.713 23.665 184.271

22 Area Detailed Villages Cultivated and Wasteland area of the within G.P. villages (ha) (Falling within the project) Sr. Name of the G.P./ Cultivate Uncultivated No. W.C. Cultivate Pvt. Agri. Land Commu d wasteland/ fallow Forest Total d rainfed - nity Others irrigated Perm Land area (ha) area Temp. Gen Sc ST OBC Total land area anent 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 16. Alipur Palia 15.355 2.290 0.000 0.000 7.058 1.765 0.000 8.823 17.645 0.000 1.500 0.118 19.263

Total 15.355 2.290 0.000 0.000 7.058 1.765 0.000 8.823 17.645 0.000 1.500 0.118 19.263 17. Babina Babina 144.004 9.500 2.810 1.947 60.623 15.156 0.000 77.725 153.504 0.000 2.814 25.310 181.628 Sukhchenpur Sukhchenpur Bampur Rampur 35.513 0.794 0.980 0.000 14.523 3.631 0.000 18.153 36.307 0.000 0.817 4.073 41.197 Total 179.517 10.294 3.790 1.947 75.146 18.786 0.000 95.879 189.811 0.000 3.631 29.383 222.825 18. Pasua Pasua 86.014 4.642 1.920 0.940 35.886 8.972 0.000 45.798 90.656 4.013 1.641 7.747 104.057

Total 86.014 4.642 1.920 0.940 35.886 8.972 0.000 45.798 90.656 4.013 1.641 7.747 104.057 19. Sarai Pratham Sarai Pratham 131.279 7.540 2.013 1.341 54.991 13.748 0.000 70.080 138.819 0.000 2.613 3.306 144.738

Total 131.279 7.540 2.013 1.341 54.991 13.748 0.000 70.080 138.819 0.000 2.613 3.306 144.738 20. Bamrauliya Bamrauliya 150.408 4.600 2.341 1.610 61.359 15.340 0.000 78.309 155.008 0.000 2.517 26.824 184.349

Total 150.408 4.600 2.341 1.610 61.359 15.340 0.000 78.309 155.008 0.000 2.517 26.824 184.349 21. Bhadasiya Bhadasiya 150.544 3.900 2.613 1.241 61.281 15.320 0.000 77.843 154.444 1.246 2.314 19.665 177.669

Newada Malkhan 71.645 8.100 1.093 0.940 31.522 7.881 0.000 40.343 79.745 0.000 1.814 7.212 88.771 Total 222.189 12.000 3.706 2.181 92.803 23.201 0.000 118.185 234.189 1.246 4.128 26.877 266.440 22. Bhikhra Bhikhra 158.363 5.890 2.013 1.093 65.264 16.316 0.000 82.673 164.253 0.000 2.490 20.548 187.291

Total 158.363 5.890 2.013 1.093 65.264 16.316 0.000 82.673 164.253 0.000 2.490 20.548 187.291 23. Indpamau Indpamau 188.940 4.300 36.520 5.640 75.040 18.760 0.000 99.440 193.240 0.000 3.570 14.115 210.925

Total 188.940 4.300 36.520 5.640 75.040 18.760 0.000 99.440 193.240 0.000 3.570 14.115 210.925 24. Marhokh Mit Marhokh Mit 21.224 4.920 0.930 0.000 10.458 2.614 0.000 13.072 26.144 0.000 0.413 0.124 26.681

Marhokh Hariram 41.054 1.650 2.400 1.640 16.426 4.106 0.000 22.172 42.704 0.000 0.971 3.635 47.310 Total 62.278 6.570 3.330 1.640 26.884 6.721 0.000 35.243 68.848 0.000 1.384 3.759 73.991

23

Area Detailed Villages Cultivated and Wasteland area of the within G.P. villages (ha) (Falling within the project) Sr. Name of the G.P./ Uncultivated No. W.C. Cultivate Cultivated Pvt. Agri. Land Commu wasteland/ fallow Forest Total d rainfed irrigated - nity Others Perm Land area (ha) area area Temp. Gen Sc ST OBC Total land anent 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 25. Rooppur Sahar Rooppur Sahar 188.926 5.900 4.342 3.120 76.682 19.171 0.000 98.973 194.826 0.000 3.614 22.014 220.454

Vimtamau 211.345 5.100 7.400 3.800 85.058 21.265 0.000 110.123 216.445 0.000 3.874 10.948 231.267 Total 400.271 11.000 11.742 6.920 161.740 40.435 0.000 209.096 411.271 0.000 7.488 32.962 451.721 26. Asjana Asjana 225.458 12.440 4.600 3.750 93.659 23.415 0.000 120.824 237.898 0.000 1.024 43.098 282.020

Barkapurwa 38.500 1.950 1.540 0.540 15.964 3.991 0.000 20.495 40.450 0.000 0.982 3.330 44.762 Hathnapur 100.552 3.400 4.070 3.800 40.061 10.015 0.000 53.876 103.952 1.310 1.603 8.962 115.827 Total 364.510 17.790 10.210 8.090 149.684 37.421 0.000 195.195 382.300 1.310 3.609 55.390 442.609 27. Rawatpur Rawatpur 111.840 3.450 3.860 4.210 44.432 11.108 0.000 59.750 115.290 0.000 1.431 29.068 145.789

Total 111.840 3.450 3.860 4.210 44.432 11.108 0.000 59.750 115.290 0.000 1.431 29.068 145.789 28. Udelapur (ALD) Udelapur 120.213 4.010 2.700 1.870 48.941 12.235 0.000 63.047 124.223 0.000 1.481 24.742 150.446

Purwa Bhadauriya 25.543 1.540 1.350 0.980 10.441 2.610 0.000 14.032 27.083 0.000 0.879 5.653 33.615 Ruru Total 145.756 5.550 4.050 2.850 59.382 14.846 0.000 77.078 151.306 0.000 2.360 30.395 184.061 29. Shahoopur (ALD) Malikpur Mishripur 35.000 1.490 0.230 0.600 14.356 3.589 0.000 18.545 36.490 0.000 1.031 18.332 55.853

Total 35.000 1.490 0.230 0.600 14.356 3.589 0.000 18.545 36.490 0.000 1.031 18.332 55.853 30. Ruru Kala (ALD) Kariapur Ruru 20.363 1.321 0.890 0.000 8.674 2.168 0.000 10.842 21.684 0.000 1.131 36.562 59.377

Total 20.363 1.321 0.890 0.000 8.674 2.168 0.000 10.842 21.684 0.000 1.131 36.562 59.377 31. Shivpur (ALD) Shivpur 452.856 24.340 3.640 5.380 188.726 47.182 0.000 241.288 477.196 0.000 6.843 65.866 549.905

Total 452.856 24.340 3.640 5.380 188.726 47.182 0.000 241.288 477.196 0.000 6.843 65.866 549.905 Grand Total 6177.000 202.561 168.144 77.026 2521.014 630.254 0.000 3228.294 6379.561 16.625 99.132 822.786 7318.104

24 2.3 Physiography

The micro-watersheds of IWMP-I is situated at an elevation of some 135 to 152 m above mean sea level and has relief from 11 to 16 m. The watershed has a general slope of less than 1 per cent. General topography of the watershed is mild to gentle. Elevation range and relief are given in Table 2.3.

Table 2.3: Micro-watershed wise elevation range and relief

S.N o. Name of MWS Minimum Maximum Relief 1 2 3 4 5 1. Sabhad (2C4B5a4d) 137 151 14 2. Mau (2C4B5a4c) 139 151 12 3. Marha Macchi Jhil (2C4B5a4b) 138 150 12 4. Belpur Bela (2C4B5a4a) 139 151 12 5. Banthara (2C4B5a2d) 139 152 13 6. Dondapur (2C4B5a2c) 139 150 11 7. Babina Sukhchenpur (2C4B5a1d) 139 151 12 8. Bhadasiya (2C4B5a1c) 138 150 12 9. Indpamau (2C4B5a1b) 136 150 14 10. Asjana (2C4B5a1c) (L) 135 151 16

11. Sarai Pratham (2C4B5a1d) L 138 150 12

25 Slope : Spatial distribution of different slope classes was prepared using Arc GIS. Slope was divided into five classes’ viz. 0-0.5, 0.5- 1.0, 1-3, 3-5, and more than 5 per cent. Per cent areal extent of different slope classes in IWMP-I micro-watershed is shown in Table 2.4. The dominant slope category in the micro-watershed were 1-3 per cent (31%) followed by 3-5 per cent (10%).

Table 2.4: Areal extent of various slope classes in the micro-watershed of IWMP-I

Slope range wise area (ha) S.No. Name of MWS & Code >5% Total Project 0-0.5% 0.5-1.00% 1.00-3.00% 3.00-5.00% Undulating Terraced Area (ha) 1 2 3 4 5 6 7 8 9

1 Sabhad (2C4B5a4d) 122.688 220.961 95.304 31.776 20.023 - 490.752 2 Mau (2C4B5a4c) 224.376 404.101 174.295 58.113 36.618 - 897.504 3 Marha Macchi Jhil (2C4B5a4b) 129.121 232.547 100.301 33.442 21.073 - 516.484 4 Belpur Bela (2C4B5a4a) 72.568 130.695 56.371 18.795 11.843 - 290.271 5 Banthara (2C4B5a2d) 173.322 312.153 134.637 44.890 28.286 - 693.288 6 Dondapur (2C4B5a2c) 115.713 208.399 89.886 29.970 18.884 - 462.851 7 Babina Sukhchenpur (2C4B5a1d) 77.726 139.984 60.377 20.131 12.685 - 310.903 8 Bhadasiya (2C4B5a1c) 186.462 335.817 144.843 48.294 30.431 - 745.846 9 Indpamau (2C4B5a1b) 163.471 294.411 126.984 42.339 26.678 - 653.883 10 Asjana (2C4B5a1c) L 86.650 156.057 67.310 22.442 14.141 - 346.601 11 Sarai Pratham (2C4B5a1d) L 192.154 346.070 149.265 49.768 31.360 - 768.617 Total 1544.250 2781.194 1199.573 399.961 252.022 0.000 6177.000

26 2.4 Climate

The annual average rainfall of the West region in about 800 mm, rainfall about 90% of which is received during South-West monsoon period (Singh et al . 2002). The major part of the rainfall is received during the month of July to August. The winter rains are erratic, occasional, meager and uncertain. The total rainy days/year vary from 32-48 in the region with an average of 40. The distribution of rainfall is very erratic. Low rainfall and drought are common features. Long dry spells during rainy season are also experienced often, which adversely affect the crops. It has been observed that in a cycle of 5 years, 2 are normal, 2 drought years and 1 is excessive rainfall year (Tiwari et al . 1998). The climate of Auraiya is characterized by a hot dry summer and cold winter and is marked for high variability of rainfall year to year. There are primarily four seasons: – Dry Summer season – from March to May i.e. before advent of monsoon, moist summer season – from June to September (Monsoon) transition period - in October and November, which is the post monsoon period, and winter season – from December to February The coldest months in the year are December and January. Average monthly rainfall and temperature are shown in Table 2.5.

Table 2.5 : Average monthly rainfall and temperature of IWMP-I, Auraiya

Rainfall in mm Month 2004 2005 2006 2007 2008 2009 2010 Average 1 2 3 4 5 6 7 8 9 January 12.1 4.5 0 0.80 0.00 8.1 3.40 4.13 February 0 0.3 0 31.30 0.00 1.00 24.60 8.17 March 0 1.5 30.10 17.8 0.00 0.00 0.00 8.98 April 10.30 1.3 0 0.10 2.80 2.1 1.90 2.64 May 3.2 6.5 22.35 13.1 18.3 12.1 1.50 11.01 June 95.3 40.40 55.45 70.50 584.20 8.00 26.80 125.81 July 135.20 198.30 178.00 82.30 250.00 190.70 215.60 178.58 August 286.80 132.20 170.10 100.9 206.1 182.90 148.60 175.37 September 59.1 110.20 81.9 36.51 100.1 71.50 155.1 87.77 October 46.5 0 30.5 0 0.00 58.60 0.2 19.40 November 0 0 0 0 25.3 10.40 32.00 9.67 December 0 1.3 0.10 1.0 00 4.50 2.21 1.31 Source: Data site of Agro-meteorological Deptt.

The open pan evaporation varied in the range of 0.3 to 18 mm/day during the year with average of about 5 mm/day. Average relative humidity varied in the range of 38 to 98 per cent, however the range of wind speed of 0.9 to 16 km/hr. The details of flood and drought in the project area are showed in Table 2.6.

27

Table 2.6 : Details of flood and drought in the project area (IWMP-I, Auraiya)

Periodicity Particula Not Name of Micro-watershed Villages Any other rs Annual affected (Please specify)

1 2 3 4 5 6

No. of Microwatershed : 11 Flood Name of Villages - - - Name of Microwatershed : Name(s) of Villages - - - Sabhad (2C4B5a4d) Mau (2C4B5a4c) Draught No. of Villages : 41 Marha Macchi Jhil (2C4B5a4b) Name of Villages: Belpur Bela (2C4B5a4a) Bhatura, Badin, Gura , Rajpur Bidhuna Banthara (2C4B5a2d) Sabhad , Bhatoli , Marha Macchi Jhil , Twice in 5 years however, the region Dondapur (2C4B5a2c) Chakarpur, Jagatpur, Mau , Narayanpur experienced severe drought during 2004- Babina Sukhchenpur (2C4B5a1d) Sahar, Khizarpur, Rathgaon, Sanwaliya , Banthara , Belpur Bela , Kiratpur, Bashai , 2007 and 2009-2010 were deficit by about Bhadasiya (2C4B5a1c) 17 to 20 per cent Indpamau (2C4B5a1b) Pusauli , Narayanpur Bhanu, Tajpur Asjana (2C4B5a1c) L Bidhuna , Dondapur , Palia, Babina - Sukhchenpur , Bampur Rampur, Pasua , Sarai Pratham (2C4B5a1d) L Sarai Pratham , Bamrauliya, Bhadasiya , Newada Malkhan , Bhikhra, Indpamau , Marhokh Mit , Marhokh Hariram, Rooppur Sahar , Vimtamau, Asjana , Barkapurwa, Hathnapur, Rawatpur , Udelapur , Purwa Bhadauriya Ruru, Malikpur Mishripur, Kariapur Ruru , Shivpur

28 CHAPTER – 3 BASELINE SURVEY AND PARTICIPATORY RURAL APPRAISAL

Table 3.1 :Demographic Features in the project area (IWMP-I, Auraiya) Villages Total Population Population of SC/ST S.No. Name of the G.P./ W.C. within G.P. Total Male Female Total Male Female 1 2 3 4 5 6 7 8 9 1. Badin (E.K.) Bhatura 286 152 134 114 63 51 Badin 4094 2277 1817 2456 1351 1105 Total 4384 2434 1957 2577 1422 1165 2. Gura Gura 807 418 289 322 177 145 Rajpur Bidhuna 411 219 192 82 46 36 Total 1218 637 481 404 223 181 3. Sabhad Sabhad 6133 3255 2878 3802 2091 1711 Total 6133 3255 2878 3802 2091 1711 4. Bhatoli Bhatoli 2598 1373 1225 1039 572 467 Total 2598 1373 1225 1039 572 467 5. Marha Macchi Jhil Marha Macchi Jhil 1029 547 479 153 83 70 Chakarpur 176 95 81 11 7 4 Total 1205 642 560 164 90 74 6. Harchandpur (E.K.) Jagatpur 417 220 197 125 69 56 Total 417 220 197 125 69 56 7. Mau Mau 4380 2234 2146 672 342 330 Narayanpur Sahar 227 125 102 17 10 7 Khizarpur 226 123 103 9 6 3 Total 4833 2482 2351 698 358 340

29 Villages Total Population Population of SC/ST S.No. Name of the G.P./ W.C. within G.P. Total Male Female Total Male Female 1 2 3 4 5 6 7 8 9 8. Rathgaon (E.K.) Rathgaon 6355 3503 2852 1906 1319 857 Total 6355 3503 2852 1906 1319 857 9. Sanwaliya Sanwaliya 1269 668 601 507 279 128 Total 1269 668 601 507 279 128 10. Banthara Banthara 3793 2045 1748 948 522 426 Total 3793 2045 1748 948 522 426 11. Belpur Bela Belpur Bela 1401 748 653 630 347 283 Kiratpur 716 368 348 429 236 193 Total 2117 1116 1001 1059 583 476 12. Bashai Bashai 1068 576 492 213 117 96 Total 1068 576 492 213 117 96 13. Pusauli Pusauli 608 323 285 395 218 177 Narayanpur Bhanu 827 432 395 289 159 130 Total 1435 755 680 684 377 307 14. Tajpur Bidhuna Tajpur Bidhuna 2206 1134 1072 1213 668 545 Total 2206 1134 1072 1213 668 545 15. Dondapur Dondapur 1761 931 830 880 484 396 Total 1761 931 830 880 484 396 16. Alipur Palia 700 382 318 245 135 110 Total 700 382 318 245 135 110 17. Babina Sukhchenpur Babina Sukhchenpur 641 329 312 128 70 58 Bampur Rampur 593 318 275 207 114 93 Total 1234 647 587 335 184 151

30 Villages Total Population Population of SC/ST S.No. Name of the G.P./ W.C. within G.P. Total Male Female Total Male Female 1 2 3 4 5 6 7 8 9 18. Pasua Pasua 1866 1005 861 280 154 126 Total 1866 1005 861 280 154 126 19. Sarai Pratham Sarai Pratham 968 517 451 338 186 152 Total 968 517 451 338 186 152 20. Bamrauliya Bamrauliya 1224 639 585 122 68 54 Total 1224 639 585 122 68 54 21. Bhadasiya Bhadasiya 1169 650 519 455 250 205 Newada Malkhan 1142 604 538 445 245 200 Total 2311 1254 1057 900 495 405 22. Bhikhra Bhikhra 1626 864 772 325 179 146 Total 1626 864 772 325 179 146 23. Indpamau Indpamau 1307 715 592 653 359 294 Total 1307 715 592 653 359 294 24. Marhokh Mit Marhokh Mit 1335 880 784 400 215 185 Marhokh Hariram 800 281 190 240 137 103 Total 2135 1161 974 640 352 288 25. Rooppur Sahar Rooppur Sahar 1444 760 684 433 239 194 Vimtamau 919 500 419 367 202 165 Total 2363 1260 1103 800 441 359 26. Asjana Asjana 2772 1458 1314 831 457 374 Barkapurwa 494 270 224 17 12 5 Hathnapur 525 277 248 157 87 70 Total 3791 2005 1786 1005 556 449

31 Villages Total Population Population of SC/ST S.No. Name of the G.P./ W.C. within G.P. Total Male Female Total Male Female 1 2 3 4 5 6 7 8 9 27. Rawatpur() Rawatpur 1538 826 712 461 249 212 Total 1538 826 712 461 249 212 28. Udelapur (ALD) Udelapur 865 484 381 346 191 155 Purwa Bhadauriya Ruru 308 161 174 77 43 34 Total 1173 645 555 423 234 189 29. Shahoopur (ALD) Malikpur Mishripur 554 295 259 110 61 49 Total 554 295 259 110 61 49 30. Ruru Kala (ALD) Kariapur Ruru 767 408 359 230 132 98 Total 767 408 359 230 132 98 31. Shivpur (ALD) Shivpur 2809 1468 1341 1460 789 671 Total 2809 1468 1341 1460 789 671 Grand Total 64349 34394 29896 23086 12959 10307

32 Table 3.2 : Details of land holding pattern n IWMP-I, Auraiya

Sr. No. of No. of BPL Land holding ha. No. Name of G.P./W.C. Village with G.P. Type of Farmer households households Irrigated Rainfed Total 1 2 3 4 5 6 7 8 9 (i) Big (above 4 ha.) 1 - 2.685 5.604 8.289 (ii) Medium (2-4 ha.) 2 - 1.375 2.802 4.177 (iii) Small (1-2 ha.) 4 - 1.510 3.082 4.592 (iv) Marginal (0-1 ha.) 6 5 1.230 2.524 3.754 1 Badin (E.K.) Bhatura (v) Landless 10 10 0.000 0.000 0.000 Total 23 15 6.800 14.012 20.812 (i) Big (above 4 ha.) 4 - 1.312 18.884 20.196 (ii) Medium (2-4 ha.) 2 - 0.656 9.443 10.099 (iii) Small (1-2 ha.) 7 - 0.722 10.386 11.108 (iv) Marginal (0-1 ha.) 18 15 0.590 8.498 9.088 Badin (v) Landless 12 12 0.000 0.000 0.000 Total 44 27 3.280 47.211 50.491 Grand Total 67 42.768 10.080 61.223 71.303 (i) Big (above 4 ha.) 9 - 1.500 37.170 38.670 (ii) Medium (2-4 ha.) 8 - 0.750 18.585 19.335 (iii) Small (1-2 ha.) 14 - 0.825 20.443 21.269 (iv) Marginal (0-1 ha.) 22 18 0.675 16.726 17.402 2 Gura Gura (v) Landless 14 14 0.000 0.000 0.000 Total 66 32 3.751 92.924 96.675 (i) Big (above 4 ha.) 12 - 3.672 51.822 55.494 (ii) Medium (2-4 ha.) 10 - 1.836 25.911 27.747 (iii) Small (1-2 ha.) 25 - 2.020 28.502 30.522 (iv) Marginal (0-1 ha.) 28 24 1.652 23.320 24.972 Rajpur Bidhuna (v) Landless 13 13 0.000 0.000 0.000 Total 88 37 9.180 129.556 138.736 Grand Total 154 69 12.931 222.480 235.411

33 Sr. No. of No. of BPL Land holding ha. No. Name of G.P./W.C. Village with G.P. Type of Farmer households households Irrigated Rainfed Total 1 2 3 4 5 6 7 8 9 (i) Big (above 4 ha.) 51 - 10.976 241.021 251.997 (ii) Medium (2-4 ha.) 42 - 5.488 120.510 125.998 (iii) Small (1-2 ha.) 77 - 6.037 132.561 138.598 (iv) Marginal (0-1 ha.) 126 107 4.939 108.459 113.399 3 Sabhad Sabhad (v) Landless 17 17 0.000 0.000 0.000 Total 313 124 27.440 602.552 629.992 (i) Big (above 4 ha.) 1 - 0.200 4.492 4.692 (ii) Medium (2-4 ha.) 1 - 0.100 2.246 2.346 (iii) Small (1-2 ha.) 2 - 0.110 2.471 2.581 (iv) Marginal (0-1 ha.) 4 4 0.090 2.022 2.112 4 Bhatoli Bhatoli (v) Landless 12 12 0.000 0.000 0.000 Total 21 16 0.500 11.231 11.731 (i) Big (above 4 ha.) 19 - 3.468 74.084 77.552 (ii) Medium (2-4 ha.) 14 - 1.734 37.042 38.776 (iii) Small (1-2 ha.) 28 - 1.907 40.746 42.653 (iv) Marginal (0-1 ha.) 44 37 1.561 33.338 34.898 5 Marha Macchi Jhil Marha Macchi Jhil (v) Landless 19 19 0.000 0.000 0.000 Total 124 56 8.670 185.209 193.879 (i) Big (above 4 ha.) 2 - 0.880 17.076 17.956 (ii) Medium (2-4 ha.) 3 - 0.440 8.538 8.978 (iii) Small (1-2 ha.) 5 - 0.484 9.392 9.876 (iv) Marginal (0-1 ha.) 9 7 0.396 7.684 8.080 Chakarpur (v) Landless 11 11 0.000 0.000 0.000 Total 30 18 2.200 42.690 44.890 Grand Total 154 74 10.870 227.899 238.769 (i) Big (above 4 ha.) 2 - 2.048 15.241 17.289 (ii) Medium (2-4 ha.) 2 - 1.024 7.620 8.644 (iii) Small (1-2 ha.) 5 - 1.126 8.382 9.509 (iv) Marginal (0-1 ha.) 8 7 0.922 6.858 7.780 6 Harchandpur (E.K.) Jagatpur (v) Landless 14 14 0.000 0.000 0.000 Total 32 21 5.120 38.102 43.222

34 Sr. No. of No. of BPL Land holding ha. No. Name of G.P./W.C. Village with G.P. Type of Farmer households households Irrigated Rainfed Total 1 2 3 4 5 6 7 8 9 (i) Big (above 4 ha.) 20 - 5.472 153.932 159.404 (ii) Medium (2-4 ha.) 23 - 2.736 76.966 79.702 (iii) Small (1-2 ha.) 49 - 3.010 84.663 87.672 (iv) Marginal (0-1 ha.) 76 64 2.462 69.270 71.732 7 Mau Mau (v) Landless 23 23 0.000 0.000 0.000 Total 190 87 13.680 384.831 398.511 (i) Big (above 4 ha.) 8 - 2.820 60.891 63.711 (ii) Medium (2-4 ha.) 9 - 1.410 30.446 31.856 (iii) Small (1-2 ha.) 19 - 1.551 33.490 35.041 (iv) Marginal (0-1 ha.) 30 26 1.269 27.401 28.670 Narayanpur Sahar (v) Landless 13 13 0.000 0.000 0.000 Total 80 39 7.050 152.228 159.728 (i) Big (above 4 ha.) 3 - 1.204 12.445 13.649 (ii) Medium (2-4 ha.) 3 - 0.602 6.223 6.824 (iii) Small (1-2 ha.) 6 - 0.662 6.845 7.507 (iv) Marginal (0-1 ha.) 10 9 0.542 5.600 6.142 Khizarpur (v) Landless 11 11 0.000 0.000 0.000 Total 33 20 3.009 31.113 34.203 Grand Total 303 146 23.739 568.172 592.442 (i) Big (above 4 ha.) 17 - 5.164 132.514 137.678 (ii) Medium (2-4 ha.) 20 - 2.582 66.257 68.839 (iii) Small (1-2 ha.) 42 - 2.840 72.882 75.723 (iv) Marginal (0-1 ha.) 65 55 2.324 59.631 61.955 8 Rathgaon (E.K.) Rathgaon (v) Landless 21 21 0.000 0.000 0.000 Total 165 76 12.910 331.284 344.194 (i) Big (above 4 ha.) 8 - 2.788 60.143 62.931 (ii) Medium (2-4 ha.) 9 - 1.394 30.071 31.465 (iii) Small (1-2 ha.) 19 - 1.533 33.079 34.612 (iv) Marginal (0-1 ha.) 30 25 1.255 27.064 28.319 9 Sanwaliya Sanwaliya (v) Landless 18 18 0.000 0.000 0.000 Total 84 43 6.970 150.357 157.327

35 Sr. No. of No. of BPL Land holding ha. No. Name of G.P./W.C. Village with G.P. Type of Farmer households households Irrigated Rainfed Total 1 2 3 4 5 6 7 8 9 (i) Big (above 4 ha.) 14 - 2.741 110.922 113.664 (ii) Medium (2-4 ha.) 16 - 1.371 55.461 56.832 (iii) Small (1-2 ha.) 35 - 1.508 61.007 62.515 (iv) Marginal (0-1 ha.) 54 46 1.234 49.915 51.149 10 Banthara Banthara (v) Landless 19 19 0.000 0.000 0.000 Total 138 65 6.853 277.306 284.159 Belpur Bela (i) Big (above 4 ha.) 10 - 2.360 76.019 78.380 11 Belpur Bela (ii) Medium (2-4 ha.) 11 - 1.180 38.010 39.190 (iii) Small (1-2 ha.) 24 - 1.298 41.811 43.109

(iv) Marginal (0-1 ha.) 37 32 1.062 34.209 35.271

(v) Landless 13 13 0.000 0.000 0.000

Total 95 45 5.901 190.048 196.049

Kiratpur (i) Big (above 4 ha.) 5 - 1.365 23.500 24.866 (ii) Medium (2-4 ha.) 5 - 0.683 11.750 12.433 (iii) Small (1-2 ha.) 11 - 0.751 12.925 13.676

(iv) Marginal (0-1 ha.) 19 16 0.614 10.575 11.190

(v) Landless 16 15 0.000 0.000 0.000

Total 56 31 3.413 58.751 62.164 Grand Total 151 75 9.314 248.799 258.213 12 Bashai Bashai (i) Big (above 4 ha.) 3 - 1.420 12.678 14.098 (ii) Medium (2-4 ha.) 3 - 0.710 6.339 7.049 (iii) Small (1-2 ha.) 6 - 0.781 6.973 7.754

(iv) Marginal (0-1 ha.) 11 9 0.639 5.705 6.344

(v) Landless 4 4 0.000 0.000 0.000 Total 27 13 3.550 31.694 35.244

36 Sr. No. of No. of BPL Land holding ha. No. Name of G.P./W.C. Village with G.P. Type of Farmer households households Irrigated Rainfed Total 1 2 3 4 5 6 7 8 9 Pasauli (i) Big (above 4 ha.) 7 - 3.563 53.506 57.069

13 Pasauli (ii) Medium (2-4 ha.) 8 - 1.781 26.753 28.535

(iii) Small (1-2 ha.) 17 - 1.960 29.429 31.388

(iv) Marginal (0-1 ha.) 27 23 1.603 24.078 25.681

(v) Landless 19 19 0.000 0.000 0.000

Total 79 42 8.907 133.766 142.673

Narayanpur Bhanu (i) Big (above 4 ha.) 6 - 1.184 31.920 33.104

(ii) Medium (2-4 ha.) 7 - 0.592 15.960 16.552

(iii) Small (1-2 ha.) 15 - 0.651 17.556 18.207

(iv) Marginal (0-1 ha.) 25 21 0.533 14.364 14.897

(v) Landless 12 12 0.000 0.000 0.000

Total 65 33 2.960 79.800 84.861 Grand Total 143 75 11.867 213.566 227.534 14 Tajpur Bidhuna Tajpur Bidhuna (i) Big (above 4 ha.) 11 - 2.930 82.578 85.507 (ii) Medium (2-4 ha.) 12 - 1.465 41.289 42.754 (iii) Small (1-2 ha.) 26 - 1.611 45.418 47.029 (iv) Marginal (0-1 ha.) 41 34 1.318 37.160 38.478

(v) Landless 17 17 0.000 0.000 0.000 Total 107 51 7.324 206.444 213.768 15 Dondapur Dondapur (i) Big (above 4 ha.) 8 - 2.033 60.232 62.265 (ii) Medium (2-4 ha.) 9 - 1.017 30.116 31.132 (iii) Small (1-2 ha.) 19 - 1.118 33.127 34.246

(iv) Marginal (0-1 ha.) 29 25 0.915 27.104 28.019

(v) Landless 16 16 0.000 0.000 0.000 Total 81 41 5.083 150.579 155.662

37 Sr. No. of No. of BPL Land holding ha No. Name of G.P./W.C. Village with G.P. Type of Farmer households households Irrigated Rainfed Total 1 2 3 4 5 6 7 8 9 16 Alipur Palia (i) Big (above 4 ha.) 1 - 0.916 6.142 7.058 (ii) Medium (2-4 ha.) 1 - 0.458 3.071 3.529 (iii) Small (1-2 ha.) 3 - 0.504 3.378 3.882

(iv) Marginal (0-1 ha.) 5 4 0.412 2.764 3.176

(v) Landless 2 2 0.000 0.000 0.000 Total 13 6 2.290 15.355 17.645 Babina Sukhchenpur (i) Big (above 4 ha.) 14 - 4.924 55.699 60.623 (ii) Medium (2-4 ha.) 17 Babina Sukhchenpur 12 - 2.462 27.849 30.311

(iii) Small (1-2 ha.) 28 - 2.708 30.634 33.343

(iv) Marginal (0-1 ha.) 45 39 2.216 25.064 27.280

(v) Landless 11 11 0.000 0.000 0.000

Total 110 50 12.310 139.247 151.557

Bampur Rampur (i) Big (above 4 ha.) 3 - 0.630 13.813 14.443 (ii) Medium (2-4 ha.) 3 - 0.315 6.907 7.221 (iii) Small (1-2 ha.) 7 - 0.346 7.597 7.944

(iv) Marginal (0-1 ha.) 11 9 0.283 6.216 6.499

(v) Landless 12 12 0.000 0.000 0.000 Total 35 21 1.574 34.533 36.307 Grand Total 146 71 13.884 173.780 187.864 18 Pasua Pasua (i) Big (above 4 ha.) 7 - 2.625 33.262 35.886 (ii) Medium (2-4 ha.) 7 - 1.312 16.631 17.943 (iii) Small (1-2 ha.) 16 - 1.444 18.294 19.738

(iv) Marginal (0-1 ha.) 27 23 1.181 14.968 16.149

(v) Landless 18 18 0.000 0.000 0.000 Total 76 41 6.562 83.154 89.716

38 Sr. No. of No. of BPL Land holding ha. No. Name of G.P./W.C. Village with G.P. Type of Farmer households households Irrigated Rainfed Total 1 2 3 4 5 6 7 8 9 (i) Big (above 4 ha.) - 3.821 51.170 54.991 19 Sarai Pratham Sarai Pratham 10 (ii) Medium (2-4 ha.) 11 - 1.911 25.585 27.496

(iii) Small (1-2 ha.) 25 - 2.102 28.144 30.245

(iv) Marginal (0-1 ha.) 41 35 1.720 23.027 24.746

(v) Landless 17 17 0.000 0.000 0.000 Total 104 52 9.553 127.925 137.478 (i) Big (above 4 ha.) - 2.776 58.583 61.359 20 Bamrauliya Bamrauliya 12 (ii) Medium (2-4 ha.) 12 - 1.388 29.291 30.680

(iii) Small (1-2 ha.) 28 - 1.527 32.221 33.748

(iv) Marginal (0-1 ha.) 46 39 1.249 26.362 27.612

(v) Landless 9 9 0.000 0.000 0.000 Total 107 48 6.941 146.457 153.398 Bhadasiya (i) Big (above 4 ha.) 10 - 2.605 58.676 61.281 (ii) Medium (2-4 ha.) 11 - 1.303 29.338 30.641

21 Bhadasiya (iii) Small (1-2 ha.) 19 - 1.433 32.272 33.705

(iv) Marginal (0-1 ha.) 31 26 1.172 26.404 27.577

(v) Landless 16 16 0.000 0.000 0.000 Total 86 42 6.513 146.690 153.203

Newada Malkhan (i) Big (above 4 ha.) 6 - 3.677 27.845 31.522

(ii) Medium (2-4 ha.) 6 - 1.839 13.922 15.761

(iii) Small (1-2 ha.) 14 - 2.022 15.315 17.337

(iv) Marginal (0-1 ha.) 24 20 1.655 12.530 14.185

(v) Landless 14 14 0.000 0.000 0.000

Total 64 34 9.193 69.612 78.805 Grand Total 150 76 15.706 216.302 232.008 (i) Big (above 4 ha.) - 3.161 62.103 65.264 22 Bhikhra Bhikhra 8 (ii) Medium (2-4 ha.) 9 - 1.581 31.051 32.632

(iii) Small (1-2 ha.) 20 - 1.739 34.157 35.895

(iv) Marginal (0-1 ha.) 31 26 1.423 27.946 29.369

(v) Landless 15 15 0.000 0.000 0.000 Total 83 41 7.903 155.257 163.160

39 Sr. No. of No. of BPL Land holding ha. No. Name of G.P./W.C. Village with G.P. Type of Farmer households households Irrigated Rainfed Total 1 2 3 4 5 6 7 8 9 (i) Big (above 4 ha.) - 16.328 58.712 75.040 23 Indpamau Indpamau 20 (ii) Medium (2-4 ha.) 15 - 8.164 29.356 37.520

(iii) Small (1-2 ha.) 34 - 8.980 32.292 41.272

(iv) Marginal (0-1 ha.) 56 48 7.348 26.420 33.768

(v) Landless 21 21 0.000 0.000 0.000 Total 147 69 40.820 146.780 187.600 Marhokh Mit (i) Big (above 4 ha.) 2 - 2.340 8.118 10.458 (ii) Medium (2-4 ha.) 2 - 1.170 4.059 5.229

24 Marhokh Mit (iii) Small (1-2 ha.) 5 - 1.287 4.465 5.752

(iv) Marginal (0-1 ha.) 8 7 1.053 3.653 4.706

(v) Landless 12 12 0.000 0.000 0.000 Total 29 19 5.850 20.294 26.144 Marhokh Hariram (i) Big (above 4 ha.) 5 - 1.620 14.806 16.426

(ii) Medium (2-4 ha.) 3 - 0.810 7.403 8.213

(iii) Small (1-2 ha.) 8 - 0.891 8.143 9.034

(iv) Marginal (0-1 ha.) 12 10 0.729 6.663 7.392

(v) Landless 9 9 0.000 0.000 0.000

Total 37 19 4.050 37.014 41.064 Grand Total 66 38 9.900 57.308 67.208 Rooppur Sahar (i) Big (above 4 ha.) 10 - 4.097 72.586 76.682 (ii) Medium (2-4 ha.) 11 - 2.048 36.293 38.341

25 Rooppur Sahar (iii) Small (1-2 ha.) 23 - 2.253 39.922 42.175

(iv) Marginal (0-1 ha.) 36 31 1.844 32.664 34.507

(v) Landless 12 12 0.000 0.000 0.000 Total 92 43 10.242 181.464 191.706 Vimtamau (i) Big (above 4 ha.) 20 - 5.000 80.058 85.058

(ii) Medium (2-4 ha.) 17 - 2.500 40.029 42.529

(iii) Small (1-2 ha.) 39 - 2.750 44.032 46.782

(iv) Marginal (0-1 ha.) 64 54 2.250 36.026 38.276

(v) Landless 13 13 0.000 0.000 0.000

Total 153 67 12.500 200.145 212.645 Grand Total 245 110 22.742 381.609 404.351

40

Sr. No. of No. of BPL Land holding ha No. Name of G.P./W.C. Village with G.P. Type of Farmer households households Irrigated Rainfed Total 1 2 3 4 5 6 7 8 9 Asjana (i) Big (above 4 ha.) 22 - 6.816 86.843 93.659 (ii) Medium (2-4 ha.) 19 - 3.408 43.422 46.830 (iii) Small (1-2 ha.) 43 - 3.749 47.764 51.513 26 Asjana (iv) Marginal (0-1 ha.) 70 60 3.067 39.079 42.147

(v) Landless 23 23 0.000 0.000 0.000 Total 177 83 17.040 217.108 234.148

Barkapurwa (i) Big (above 4 ha.) - 1.396 14.568 15.964

(ii) Medium (2-4 ha.) 3 - 0.698 7.284 7.982

(iii) Small (1-2 ha.) 13 - 0.768 8.012 8.780

(iv) Marginal (0-1 ha.) 18 6 0.628 6.556 7.184

(v) Landless 12 12 0.000 0.000 0.000

Total 46 18 3.490 36.420 39.910

Hathnapur (i) Big (above 4 ha.) - 2.988 37.073 40.061 (ii) Medium (2-4 ha.) 7 - 1.494 18.536 20.030 (iii) Small (1-2 ha.) 25 - 1.643 20.390 22.033

(iv) Marginal (0-1 ha.) 35 23 1.345 16.683 18.027

(v) Landless 13 12 0.000 0.000 0.000

Total 80 35 7.470 92.682 100.152 Grand Total 303 136 28.00 346.21 374.21 27 Rawatpur (ALD) Rawatpur (i) Big (above 4 ha.) 1 - 2.924 41.508 44.432 (ii) Medium (2-4 ha.) 9 - 1.462 20.754 22.216 (iii) Small (1-2 ha.) 20 - 1.608 22.829 24.438

(iv) Marginal (0-1 ha.) 33 28 1.316 18.679 19.994

(v) Landless 2 2 0.000 0.000 0.000 Total 66 30 7.310 103.770 111.080

41 Sr. No. of No. of BPL Land holding ha No. Name of G.P./W.C. Village with G.P. Type of Farmer households households Irrigated Rainfed Total 1 2 3 4 5 6 7 8 9 Udelapur (i) Big (above 4 ha.) 6 - 2.684 46.257 48.941 28 Udelapur (ALD) (ii) Medium (2-4 ha.) 7 - 1.342 23.129 24.471

(iii) Small (1-2 ha.) 15 - 1.476 25.441 26.918

(iv) Marginal (0-1 ha.) 23 20 1.208 20.816 22.024

(v) Landless 14 14 0.000 0.000 0.000

Total 65 34 6.710 115.643 122.353

Purwa Bhadauria Ruru (i) Big (above 4 ha.) 2 - 1.156 9.285 10.441 (ii) Medium (2-4 ha.) 2 - 0.578 4.643 5.221 (iii) Small (1-2 ha.) 5 - 0.636 5.107 5.743

(iv) Marginal (0-1 ha.) 8 7 0.520 4.178 4.699

(v) Landless 13 13 0.000 0.000 0.000

Total 30 20 2.890 23.213 26.103 Grand Total 95 53 9.600 138.856 148.456 29 Shahoopur (ALD) Malikpur Mishripur (i) Big (above 4 ha.) 3 - 0.688 13.668 14.356 (ii) Medium (2-4 ha.) 3 - 0.344 6.834 7.178 (iii) Small (1-2 ha.) 7 - 0.378 7.517 7.896

(iv) Marginal (0-1 ha.) 11 9 0.310 6.151 6.460

(v) Landless 6 6 0.000 0.000 0.000 Total 29 15 1.720 34.170 35.890 30 Ruru Kala (ALD) Kariapur Ruru (i) Big (above 4 ha.) 1 - 0.884 7.789 8.674 (ii) Medium (2-4 ha.) 2 - 0.442 3.895 4.337 (iii) Small (1-2 ha.) 4 - 0.486 4.284 4.770

(iv) Marginal (0-1 ha.) 7 6 0.398 3.505 3.903

(v) Landless 4 4 0.000 0.000 0.000 Total 17 10 2.211 19.473 21.684

42

Sr. No. of No. of BPL Land holding ha No. Name of G.P./W.C. Village with G.P. Type of Farmer households households Irrigated Rainfed Total 1 2 3 4 5 6 7 8 9 31 Shivpur (ALD) Shivpur (i) Big (above 4 ha.) 24 - 11.192 177.534 188.726 (ii) Medium (2-4 ha.) 27 - 5.596 88.767 94.363 (iii) Small (1-2 ha.) 58 - 6.156 97.644 103.800

(iv) Marginal (0-1 ha.) 89 76 5.036 79.890 84.927

(v) Landless 14 14 0.000 0.000 0.000 Total 212 90 27.980 443.836 471.816 Grand Total 3798.57 1819.81 367.67 5931.93 6302.535

43 Table 3.3 : Details of migration from Project area (IWMP-I, Auraiya) : Pre-Project Status

Distance of Income from No. of No. of days Major destination of Occupation Name of such S. No. Name of village person per year of reason(s) for migration during Watershed occupation migrating migration migrating from the migration (Rs. in lakh) village (km) 1 2 3 4 5 6 7 8 9 1. Badin (E.K.) Bhatura 20 150 Earn Money 150 to 460 Labour 0.30 to 0.47

Badin 15 150 Earn Money 150 to 450 Labour 0.30 to 0.48 Total 35 150 - - - - 2. Gura Gura 25 150 Earn Money 150 to 510 Labour 0.30 to 0.48 Rajpur Bidhuna 12 150 Earn Money 150 to 580 Labour 0.28 to 0.44 Total 37 150 - - - - 3. Sabhad Sabhad 34 150 Earn Money 150 to 490 Labour 0.27 to 0.4 Total 34 150 - - - - 4. Bhatoli Bhatoli 25 150 Earn Money 150 to 500 Labour 0.28 to 0.47 Total 25 150 - - - - 5. Marha Macchi Jhil Marha Macchi Jhil 24 150 Earn Money 150 to 490 Labour 0.30 to 0.48 Chakarpur 7 150 Earn Money 150 to 500 Labour 0.29 to 0.49 Total 31 150 - - - - 6. Harchandpur (E.K.) Jagatpur 12 150 Earn Money 150 to 510 Labour 0.30 to 0.45 Total 12 150 - - - - 7. Mau Mau 23 150 Earn Money 150 to 500 Labour 0.30 to 0.47 Narayanpur Sahar 13 150 Earn Money 150 to 48 Labour 0.30 to 0.45 Khizarpur 8 150 Earn Money 150 to 500 Labour 0.28 to 0.49 Total 44 150 - - - - 8. Rath gaon (E.K.) Rath gaon 19 150 Earn Money 150 to 400 Labour 0.27 to 0.49 Total 19 150 - - - - 9. Sanwaliya Sanwaliya 14 150 Earn Money 150 to 500 Labour 0.29 to 0.48 Total 14 150 - - - - 10. Banthara Banthara 15 150 Earn Money 150 to 560 Labour 0.29 to 0.48

Total 15 150 - - - -

44 Distance of Income from No. of No. of days Major destination of Occupation such S. No. Name of Watershed Name of village person per year of reason(s) for migration during occupation migrating migration migrating from the migration (Rs. in lakh) village (km) 1 2 3 4 5 6 7 8 9 11. Belpur Bela Belpur Bela 15 150 Earn Money 150-500 Labour 0.30 to 0.45 Kiratpur 7 150 Earn Money 150-490 Labour 0.27 to 0.40 Total 22 150 - - - - 12. Bashai Bashai 5 150 Earn Money 150-510 Labour 0.30 to 0.45 Total 5 150 - - - - 13. Pusauli Pusauli 6 150 Earn Money 150-400 Labour 0.28 to 0.42 Narayanpur Bhanu 8 150 Earn Money 150-500 Labour 0.30 to 0.42 Total 14 150 - - - - 14. Tajpur Bidhuna Tajpur Bidhuna 18 150 Earn Money 150-400 Labour 0.35 to 0.48 Total 18 150 - - - - 15. Dondapur Dondapur 10 150 Earn Money 150-500 Labour 0.30 to 0.45 Total 10 150 - - - - 16. Alipur Palia 4 150 Earn Money 150-400 Labour 0.28 to 0.42 Total 4 150 - - - - 17. Babina Sukhchenpur Babina Sukhchenpur 2 150 Earn Money 150-400 Labour 0.30 to 0.45 Bampur Rampur 3 150 Earn Money 150-500 Labour 0.27 to 0.40 Total 5 150 - - - - 18. Pasua Pasua 7 150 Earn Money 150-460 Labour 0.30 to 0.45 Total 7 150 - - - - 19. Sarai Pratham Sarai Pratham 5 150 Earn Money 150-490 Labour 0.28 to 0.42 Total 5 150 - - - - 20. Bamrauliya Bamrauliya 4 150 Earn Money 150-500 Labour 0.30 to 0.45 Total 4 150 - - - - 21. Bhadasiya Bhadasiya 8 150 Earn Money 150-500 Labour 0.30 to 0.45 Newada Malkhan 7 150 Earn Money 150-500 Labour 0.28 to 0.42 Total 15 150 - - - - 22. Bhikhra Bhikhra 10 150 Earn Money 150-500 Labour 0.30 to 0.45 Total 10 150 - - - - 23. Indpamau Indpamau 12 150 Earn Money 150-400 Labour 0.25 to 0.45 Total 15 150 - - - -

45

Distance of Income from No. of No. of days Major destination of Occupation Name of such person per year of reason(s) for migration during S. No. Name of village occupation Watershed migrating migration migrating from the migration (Rs. in lakh) village (km) 1 2 3 4 5 6 7 8 9 24. Marhokh Mit Marhokh Mit 14 150 Earn Money 150-550 Labour 0.30 to 0.45

Marhokh Hariram 12 150 Earn Money 150-550 Labour 0.30 to 0.48 Total 26 150 - - - - 25. Rooppur Sahar Rooppur Sahar 11 150 Earn Money 150-600 Labour 0.28 to 0.45 Vimtamau 18 150 Earn Money 150-600 Labour 0.28 to 0.43 Total 29 150 - - - - 26. Asjana Asjana 35 150 Earn Money 150-500 Labour 0.29 to 0.48 Barkapurwa 10 150 Earn Money 150-550 Labour 0.29 to 0.48 Hathnapur 12 150 Earn Money 150-500 Labour 0.30 to 0.49 Total 57 150 - - - - 27. Rawatpur(AL D) Rawatpur 10 150 Earn Money 150-450 Labour 0.30 to 0.46 Total 10 150 - - - - 28. Udelapur (ALD) Udelapur 8 150 Earn Money 150-500 Labour 0.30 to 0.42 Purwa Bhadauriya Ruru 9 150 Earn Money 150-550 Labour 0.30 to 0.45 Total 17 150 - - - - 29. Shahoopur (ALD) Malikpur Mishripur 6 150 Earn Money 150-600 Labour 0.29 to 0.48 Total 6 150 - - - - 30. Ruru Kala (ALD) Kariapur Ruru 7 150 Earn Money 150-450 Labour 0.30 to 0.45 Total 7 150 - - - - 31. Shivpu r (ALD) Shivpur 6 150 Earn Money 150-500 Labour 0.30 to 0.48 Total 6 150 - - - - Grand Total 558 150 - - - -

46 Table 3.4 : Details of Village infrastructure in IWMP-I, Auraiya

Name of Micro- Sr. No. Parameters Status Watershed

1 2 3 4

Name of village connected to the main road by an all-weather road Bidhuan and Sabhad Road (i) Bidhuna Sabhad

(ii) Village's Name provided with electricity Shabhand

(iii) No. of households without access to drinking water 6732 again 4375

No. of educational institutions : (P) (S) (HS) (VI) (iv) Primary (P)/Secondary(S)/Higher Secondary (HS)/ Vocational Institution 01 01 - - (VI)

(v) Name of villages with access to Primary Health Centre NIl

(vi) Names of villages with access to Veterinary Dispensary Nil Sabhad 1. (vii) Name of villages with access for Post Office 01 (2C4B5a4d) (viii) Name of villages with access to Banks Nil

(ix) Name of villages with access to Markets/mandis Nil

(x) Name of villages with access to Agro-industries Nil

(xi) Total quantity of surplus deficit Nil

No. of milk collection centers (xii) PA-01 (e-g- Union ()U)/Society (S)/Private agency (PA)/ others (O)

(xiii) Name of villages with access to Anganwadi center Nil

(xiv) Cummunity centre, Panchayat Ghar Nil

47 Name of Micro- Sr. No. Parameters Status Watershed

1 2 3 4

Name of village connected to the main road by an all-weather road Bidhuan & Mau Road (i) Bidhuna to Mau

(ii) Village's Name provided with electricity Mau

(iii) No. of households without access to drinking water 7799 again 4932

No. of educational institutions : (P) (S) (HS) (VI) (iv) Primary (P)/Secondary(S)/Higher Secondary (HS)/ Vocational Institution 01 01 01 - (VI)

(v) Name of villages with access to Primary Health Centre Nil

(vi) Names of villages with access to Veterinary Dispensary Nil Mau 2. (vii) Name of villages with access for Post Office 01 (2C4B5a4c) (viii) Name of villages with access to Banks Nil

(ix) Name of villages with access to Markets/mandis Nil

(x) Name of villages with access to Agro-industries Nil

(xi) Total quantity of surplus milk deficit Nil

No. of milk collection centers (xii) Nil (e-g- Union ()U)/Society (S)/Private agency (PA)/ others (O)

(xiii) Name of villages with access to Anganwadi center 03

(xiv) Cummunity centre, Panchayat Ghar 01

48 Name of Micro- Sr. No. Parameters Status Watershed

1 2 3 4

Name of village connected to the main road by an all-weather road Bidhuna and Sabhad Road (i) between Marha Macchi Jhil

(ii) Village's Name provided with electricity Marha Macchi Jhil

(iii) No. of households without access to drinking water 7065 again 6572

No. of educational institutions : (P) (S) (HS) (VI) (iv) Primary (P)/Secondary(S)/Higher Secondary (HS)/ Vocational Institution 01 01 - - (VI)

(v) Name of villages with access to Primary Health Centre Nil

(vi) Names of villages with access to Veterinary Dispensary Nil 3. Marha Macchi Jhil (vii) Name of villages with access for Post Office 01 (2C4B5a4b) (viii) Name of villages with access to Banks Nil

(ix) Name of villages with access to Markets/mandis Nil

(x) Name of villages with access to Agro-industries Nil

(xi) Total quantity of surplus milk deficit Nil

No. of milk collection centers (xii) PA-01 (e-g- Union ()U)/Society (S)/Private agency (PA)/ others (O)

(xiii) Name of villages with access to Anganwadi center 01

(xiv) Cummunity centre, Panchayat Ghar 01

49 Name of Micro- Sr. No. Parameters Status Watershed 1 2 3 4 Name of village connected to the main road by an all-weather road Bidhuna & BelpurBeal Road (i) between Belpur Bela (ii) Village's Name provided with electricity Belpur Bela (iii) No. of households without access to drinking water 5161 against 3097 No. of educational institutions : Belpur Bela (P) (S) (HS) (VI) 4. (iv) Primary (P)/Secondary(S)/Higher Secondary (HS)/ Vocational Institution 02 01 - - (2C4B5a4a) (VI) (v) Name of villages with access to Primary Health Centre Nil (vi) Names of villages with access to Veterinary Dispensary Nil (vii) Name of villages with access for Post Office 01 (viii) Name of villages with access to Banks Nil (ix) Name of villages with access to Markets/mandis Nil (x) Name of villages with access to Agro-industries Nil (xi) Total quantity of surplus milk deficit Nil No. of milk collection centers (xii) Nil (e-g- Union ()U)/Society (S)/Private agency (PA)/ others (O) (xiii) Name of villages with access to Anganwadi center Nil (xiv) Cummunity centre, Panchayat Ghar Nil

50 Name of Micro- Sr. No. Parameters Status Watershed

1 2 3 4

Name of village connected to the main road by an all-weather road Bidhuna to Sahbad Road between (i) Banthra

(ii) Village's Name provided with electricity Banthra

(iii) No. of households without access to drinking water 7562 against 4205

No. of educational institutions : (P) (S) (HS) (O) (iv) Primary (P)/Secondary(S)/Higher Secondary (HS)/ Vocational Institution 01 01 - 01 (VI)

(v) Name of villages with access to Primary Health Centre Nil

(vi) Names of villages with access to Veterinary Dispensary Nil Banthara 5. (vii) Name of villages with access for Post Office Nil (2C4B5a2d) (viii) Name of villages with access to Banks Nil

(ix) Name of villages with access to Markets/mandis Nil

(x) Name of villages with access to Agro-industries Nil

(xi) Total quantity of surplus milk deficit Nil

No. of milk collection centers (xii) PA-01 (e-g- Union ()U)/Society (S)/Private agency (PA)/ others (O)

(xiii) Name of villages with access to Anganwadi center Nil

(xiv) Cummunity centre, Panchayat Ghar Nil

51 Name of Micro- Sr. No. Parameters Status Watershed

1 2 3 4

Name of village connected to the main road by an all-weather road Bela Road Bidhuna to Bela (i) bewteen Basai, Dodnapur Pusauli, alipur, Tajpur Bidhuna

(ii) Village's Name provided with electricity Dodnapur

(iii) No. of households without access to drinking water 7171 against 3475

No. of educational institutions : (P) (S) (HS) (O) (iv) Primary (P)/Secondary(S)/Higher Secondary (HS)/ Vocational Institution 02 01 - 01 (VI)

(v) Name of villages with access to Primary Health Centre Nil

(vi) Names of villages with access to Veterinary Dispensary Nil Dondapur 6. (2C4B5a2c) (vii) Name of villages with access for Post Office 01

(viii) Name of villages with access to Banks Nil

(ix) Name of villages with access to Markets/mandis Nil

(x) Name of villages with access to Agro-industries Nil

(xi) Total quantity of surplus milk deficit Nil

No. of milk collection centers (xii) Nil (e-g- Union ()U)/Society (S)/Private agency (PA)/ others (O)

(xiii) Name of villages with access to Anganwadi center 01

(xiv) Cummunity centre, Panchayat Ghar 01

52

Name of Micro- Sr. No. Parameters Status Watershed

1 2 3 4

Name of village connected to the main road by an all-weather road Bidhuan to Achalda Road bewten (i) Babina Sukchenpur, Saraya Pratham

(ii) Village's Name provided with electricity Babina Sukhchenpur

(iii) No. of households without access to drinking water 5472 against 3879

No. of educational institutions : (P) (S) (HS) (O) (iv) Primary (P)/Secondary(S)/Higher Secondary (HS)/ Vocational Institution 01 01 - 01 (VI)

(v) Name of villages with access to Primary Health Centre 01

Babina (vi) Names of villages with access to Veterinary Dispensary 01 7. Sukhchenpur (vii) Name of villages with access for Post Office 01 (2C4B5a1d) (viii) Name of villages with access to Banks Nil

(ix) Name of villages with access to Markets/mandis Nil

(x) Name of villages with access to Agro-industries Nil

(xi) Total quantity of surplus milk deficit Nil

No. of milk collection centers (xii) Nil (e-g- Union ()U)/Society (S)/Private agency (PA)/ others (O)

(xiii) Name of villages with access to Anganwadi center 01

(xiv) Cummunity centre, Panchayat Ghar 01

53

Name of Micro- Sr. No. Parameters Status Watershed

1 2 3 4

Name of village connected to the main road by an all-weather road Bidhuna to Road (i) bewteen Bhadasiya & Bhikhra

(ii) Village's Name provided with electricity Bhadasiya

(iii) No. of households without access to drinking water 5423 Against 3241

No. of educational institutions : (P) (S) (HS) (VI) (iv) Primary (P)/Secondary(S)/Higher Secondary (HS)/ Vocational Institution 02 01 - - (VI)

(v) Name of villages with access to Primary Health Centre Nil

(vi) Names of villages with access to Veterinary Dispensary Nil Bhadasiya 8. (vii) Name of villages with access for Post Office 01 (2C4B5a1c) (viii) Name of villages with access to Banks Nil

(ix) Name of villages with access to Markets/mandis Nil

(x) Name of villages with access to Agro-industries Nil

(xi) Total quantity of surplus milk deficit Nil

No. of milk collection centers (xii) Nil (e-g- Union ()U)/Society (S)/Private agency (PA)/ others (O)

(xiii) Name of villages with access to Anganwadi center 01

(xiv) Cummunity centre, Panchayat Ghar 01

54 Name of Micro- Sr. No. Parameters Status Watershed

1 2 3 4

Name of village connected to the main road by an all-weather road Bidhuna to Sahar Road bewteen (i) Indpamau

(ii) Village's Name provided with electricity Indpamau

(iii) No. of households without access to drinking water 3889 against 2785

No. of educational institutions : (P) (S) (HS) (VI) (iv) Primary (P)/Secondary(S)/Higher Secondary (HS)/ Vocational Institution 02 01 - - (VI)

(v) Name of villages with access to Primary Health Centre Nil

(vi) Names of villages with access to Veterinary Dispensary Nil Indpamau 9. (vii) Name of villages with access for Post Office Nil (2C4B5a1b) (viii) Name of villages with access to Banks Nil

(ix) Name of villages with access to Markets/mandis Nil

(x) Name of villages with access to Agro-industries Nil

(xi) Total quantity of surplus milk deficit Nil

No. of milk collection centers (xii) Nil (e-g- Union ()U)/Society (S)/Private agency (PA)/ others (O)

(xiii) Name of villages with access to Anganwadi center 01

(xiv) Cummunity centre, Panchayat Ghar Nil

55 Name of Micro- Sr. No. Parameters Status Watershed

1 2 3 4

Name of village connected to the main road by an all-weather road Bidhuna to Chandarpur bewteen (i) Indpamau

(ii) Village's Name provided with electricity Indpamau

(iii) No. of households without access to drinking water 4075 against 3430

No. of educational institutions : (P) (S) (HS) (O) (iv) Primary (P)/Secondary(S)/Higher Secondary (HS)/ Vocational Institution 02 01 - 01 (VI)

(v) Name of villages with access to Primary Health Centre Nil

(vi) Names of villages with access to Veterinary Dispensary 01 Asjana 10. (vii) Name of villages with access for Post Office 01 (2C4B5a1c) (L) (viii) Name of villages with access to Banks 01

(ix) Name of villages with access to Markets/mandis Nil

(x) Name of villages with access to Agro-industries Nil

(xi) Total quantity of surplus milk deficit 01

No. of milk collection centers (xii) PA-01 (e-g- Union ()U)/Society (S)/Private agency (PA)/ others (O)

(xiii) Name of villages with access to Anganwadi center 01

(xiv) Cummunity centre, Panchayat Ghar 01

56 Name of Micro- Sr. No. Parameters Status Watershed

1 2 3 4

(i) Name of village connected to the main road by an all-weather road Bidhuna to Achalda Road

(ii) Village's Name provided with electricity Saraiay Pratham

(iii) No. of households without access to drinking water 4000 agaginst 3275

No. of educational institutions : (P) (S) (HS) (VI) (iv) Primary (P)/Secondary(S)/Higher Secondary (HS)/ Vocational Institution 02 01 - - (VI)

(v) Name of villages with access to Primary Health Centre Nil

(vi) Names of villages with access to Veterinary Dispensary Nil Sarai Pratham 11. (vii) Name of villages with access for Post Office Nil (2C4B5a1d) L (viii) Name of villages with access to Banks Nil

(ix) Name of villages with access to Markets/mandis Nil

(x) Name of villages with access to Agro-industries Nil

(xi) Total quantity of surplus milk deficit Nil

No. of milk collection centers (xii) PA-01 (e-g- Union ()U)/Society (S)/Private agency (PA)/ others (O)

(xiii) Name of villages with access to Anganwadi center 01

(xiv) Cummunity centre, Panchayat Ghar 01

57 Table 3.5 : Details of Common Property Resources In IWMP-I, Auraiya

Total Area (ha) Area available for treatment ha Area owned/In possession of Sr. Name of MWS CPR Particulars Govt. No. with Code Pvt. Govt. Pvt. PRI Other (specify PRI Other Person Revanue Persons Dept.) 1 2 3 4 5 6 7 8 9 10 11 Wasteland/degraded land 96.00 - 25.18 - 96.00 - 25.18 - Pastures - 8.8 ------Orchards ------Village Woodlot ------Forest ------Sabhad Village Ponds/Tanks - - 10.120 - - 10.120 - - 1. (2C4B5a4d) Community Buildings - - 2.00 - - - - - Weekly Markets ------Permanent Markets ------Temples/Places of worship 0.245 ------Habitat, Chakmark, Sector, Road etc. - - 12.132 - - - - - Total 96.245 8.80 49.432 - 96 10.12 25.18 - Wasteland/degraded land 22.80 - 18.25 - 22.80 - 18.25 - Pastures - 17.20 ------Orchards ------Village Woodlot ------Forest - 1.640 ------Village Ponds/Tanks - - 8.30 - - 8.30 - - 2 Mau (2C4B5a4c) Community Buildings - - 12.27 - - - - - Weekly Markets 0.500 ------Permanent Markets ------Temples/Places of worship 0.250 ------Habitat, Chakmark, Sector, Road etc. - - 20.122 - - - - - Total 23.55 18.84 58.942 - 22.80 8.30 18.25

58 Total Area (ha) Area available for treatment ha Area owned/In possession of Sr. Name of MWS CPR Particulars Govt. No. with Code Pvt. Govt. Pvt. PRI Other (specify PRI Other Person Revanue Persons Dept.) 1 2 3 4 5 6 7 8 9 10 11 Wasteland/degraded land 1.600 - 20.00 - 1.600 - 20.000 - Pastures - 7.600 ------Orchards ------Village Woodlot 4.00 ------Forest 2.013 ------Village Ponds/Tanks 4.00 ------3 Marha Macchi Community Buildings - - 10.112 - - - - - Jhil (2C4B5a4b) Weekly Markets ------Permanent Markets ------Temples/Places of worship 0.500 ------Habitat, Chakmark, Sector, Road etc. - 8.400 ------Total 10.100 18.013 30.112 - 1.600 - 20.000 - Wasteland/degraded land 5.600 - 18.600 - 5.600 - 18.600 - Pastures - 2.000 ------Orchards ------Village Woodlot ------Forest - 6.403 ------

Village Ponds/Tanks 4.715 - 12.785 - - - - - 4 Belpur Bela Community Buildings ------(2C4B5a4a) Weekly Markets ------Permanent Markets ------Temples/Places of worship 0.800 - 10.704 - - - - - Habitat, Chakmark, Sector, Road etc. ------Total 11.115 8.403 42.089 - 5.600 - 18.600 -

59 Total Area (ha) Area available for treatment ha Area owned/In possession of Sr. Name of MWS CPR Particulars Govt. No. with Code Pvt. Govt. Pvt. PRI Other (specify PRI Other Person Revanue Persons Dept.) 1 2 3 4 5 6 7 8 9 10 11 Wasteland/degraded land 2.415 - 1.827 - 2.415 - - - Pastures - 24.085 ------Orchards ------Village Woodlot ------Forest - 6.403 ------Banthara Village Ponds/Tanks - - 6.425 - - - - - 5 (2C4B5a2d) Community Buildings - - 2.874 - - - - - Weekly Markets ------Permanent Markets ------Temples/Places of worship 0.675 ------Habitat, Chakmark, Sector, Road etc. - - 16.703 - - - - - Total 3.090 30.488 27.829 - 2.415 - - - Wasteland/degraded land 8.210 - 9.237 - 8.210 - 9.237 - Pastures - 13.667 ------Orchards 1.219 ------Village Woodlot ------Forest ------Dondapur Village Ponds/Tanks - - 2.115 - - - - - 6 (2C4B5a2c) Community Buildings - - 7.750 - - - - - Weekly Markets ------Permanent Markets ------Temples/Places of worship 0.715 - 2.716 - - - - - Habitat, Chakmark, Sector, Road etc. ------Total 10.144 13.667 21.818 - 8.210 - 9.237 -

60

Total Area (ha) Area available for treatment ha Area owned/In possession of Sr. Name of MWS CPR Particulars Govt. No. with Code Pvt. Govt. Pvt. PRI Other (specify PRI Other Person Revanue Persons Dept.) 1 2 3 4 5 6 7 8 9 10 11 Wasteland/degraded land - - 0.467 - - - 0.467 - Pastures ------Orchards ------Village Woodlot ------Forest - 4.134 ------Babina Village Ponds/Tanks - - 1.728 - - - - - 7 Sukhchenpur Community Buildings - - 6.244 - - - - - (2C4B5a1d) Weekly Markets ------Permanent Markets ------Temples/Places of worship 0.815 ------Habitat, Chakmark, Sector, Road etc. - - 2.815 - - - - - Total 0.815 4.134 11.254 - - - 0.467 - Wasteland/degraded land 6.128 - 23.218 - 6.128 - 23.218 - Pastures - 52.405 ------Orchards 4.080 ------Village Woodlot ------Forest - 1.246 ------Bhadasiya Village Ponds/Tanks - - 3.067 - - - - - 8 (2C4B5a1c) Community Buildings - - 18.920 - - - - - Weekly Markets ------Permanent Markets ------Temples/Places of worship 0.627 ------Habitat, Chakmark, Sector, Road etc. - - 20.312 - - - - - Total 10.835 53.651 65.517 - 6.128 - 23.218 -

61 Total Area (ha) Area available for treatment ha Area owned/In possession of Sr. Name of MWS CPR Particulars Govt. No. with Code Pvt. Govt. Pvt. PRI Other (specify PRI Other Person Revanue Persons Dept.) 1 2 3 4 5 6 7 8 9 10 11 Wasteland/degraded land 10.427 - 4.713 - 10.427 - 4.713 - Pastures - 0.478 ------Orchards 1.288 ------Village Woodlot ------Forest ------Indpamau Village Ponds/Tanks - - 6.113 - - - - - 9 (2C4B5a1b) Community Buildings - - 2.494 - - - - - Weekly Markets - 0.428 ------Permanent Markets ------Temples/Places of worship 0.975 ------Habitat, Chakmark, Sector, Road etc. - - 10.239 - - - - - Total 12.690 0.906 23.559 - 10.427 - 4.713 - Wasteland/degraded land ------Pastures ------Orchards ------Village Woodlot ------Forest - 1.310 ------Asjana Village Ponds/Tanks - - 8.317 - - - - - 10 (2C4B5a1c) (L) Community Buildings - - 1.603 - - - - - Weekly Markets - 0.428 ------Permanent Markets ------Temples/Places of worship 0.774 ------Habitat, Chakmark, Sector, Road etc. - - 5.623 - - - - - Total 0.774 1.738 15.543 - - - - -

62

Total Area (ha) Area available for treatment ha Area owned/In possession of Sr. Name of MWS CPR Particulars Govt. No. with Code Pvt. Govt. Pvt. PRI Other (specify PRI Other Person Revanue Persons Dept.) 1 2 3 4 5 6 7 8 9 10 11 Wasteland/degraded land 2.615 - 6.428 - 2.615 - 6.428 - Pastures ------Orchards ------Village Woodlot ------Forest ------Sarai Pratham Village Ponds/Tanks - - 8.402 - - - - - 11 (2C4B5a1d) L Community Buildings - - 3.735 - - - - - Weekly Markets ------Permanent Markets ------Temples/Places of worship 0.718 ------Habitat, Chakmark, Sector, Road etc. - - 14.635 - - - - - Total 3.333 - 33.200 - 2.615 - 6.428 - Grand Ttoal 182.691 158.640 379.295 0.000 155.795 18.420 126.093 -

63 3.2 Soil Texture

Majority of the land of the project is mainly medium textured soil. Category wise details of farmer and their irrigated area are described in Table 3.6.

Table 3.6: Details of Soil texture in IWMP-I, Auraiya

Area in different Soil Group (ha)

Sr. No. Name of the Project/MWS Light textured Medium textured soil Heavy textured soil Remarks soil (sand, loamy (Sandy loam, loam, silt (Clayey) sand) loam)

1 2 3 4 5 6 1 - Sabhad (2C4B5a4d) 147.226 318.989 24.538 2 - Mau (2C4B5a4c) 269.251 583.378 44.875 3 - Marha Macchi Jhil (2C4B5a4b) 154.945 335.715 25.824 4 - Belpur Bela (2C4B5a4a) 87.081 188.676 14.514 5 - Banthara (2C4B5a2d) 207.986 450.637 34.664 6 - Dondapur (2C4B5a2c) 138.855 300.853 23.143 7 - Babina Sukhchenpur (2C4B5a1d) 93.271 202.087 15.545 8 - Bhadasiya (2C4B5a1c) 223.754 484.800 37.292 9 - Indpamau (2C4B5a1b) 196.165 425.024 32.694 10 - Asjana (2C4B5a1c) (L) 103.980 225.291 17.330 11 Sarai Pratham (2C4B5a1d) L - 230.585 499.601 38.431 Total IWMP -I - 1853.100 4015.050 308.850

64 3.3 Major Crops, its Productivity and Production

Micro-watershed wise grown crops, their productivity and production under irrigated and rainfed condition is given in Table 3.7. As far as productivity of cereals is concerned, it is significantly lower than the state and national average. Micro-watershed wise cropping intensity varied from 132 to 135 per cent with average 134 per cent for the project.

Table 3.7: Micro-watershed wise details of Crops, their Productivity and Production in IWMP-I, Auraiya

Name of MWS – Sabhad (2C4B5a4d)

Area in Productivity Production (q) (ha.) q/ha. S.No. Crop. Fodder/Fuel/ Grain/Main product Irrigated Rainfed Irrigated Rainfed. Other Product. Irrigated Rainfed Irrigated Rainfed 1 2 3 4 5 6 7 8 9 10 Kharif A 1 Urd 0.000 35.880 0.000 5.500 0.000 197.340 0.000 39.468 2 Moong 0.000 59.800 0.000 5.700 0.000 340.860 0.000 68.172 3 Arhar 0.000 11.960 0.000 6.400 0.000 76.544 0.000 137.779 4 Sorghum 0.000 131.560 0.000 4.000 0.000 526.240 0.000 499.928 5 Paddy 6.871 0.000 21.500 0.000 147.716 0.000 59.087 23.635 Total 6.871 245.376 147.716 1140.984 59.087 768.982 B Rabi 1 Wheat 9.324 186.592 20.500 12.500 191.148 2332.400 99.397 1212.848 2 Barley 0.000 88.631 0.000 12.400 0.000 1099.027 0.000 549.513 3 Masoor 0.000 23.324 0.000 4.200 0.000 97.961 0.000 9.796 4 Gram 0.000 97.961 0.000 6.000 0.000 587.765 0.000 117.553 5 Pea 0.000 23.324 0.000 7.200 0.000 167.933 0.000 33.587 6 Mustured 0.000 46.648 0.000 7.800 363.854 0.000 145.542 Total 9.324 392.602 209.000 4555.177 99.397 2014.027 C Zaid Nil ------Cultivable Area 490.752 - Cropping 133 - - - -

intensity

65 Name of MWS – Mau (2C4B5a4c)

Area in Productivity Production (q) (ha.) q/ha. S.No. Crop. Fodder/Fuel/ Grain/Main product Irrigated Rainfed Irrigated Rainfed. Other Product. Irrigated Rainfed Irrigated Rainfed 1 2 3 4 5 6 7 8 9 10 A Kharif 1 Urd 0.000 67.313 0.000 5.500 0.000 370.220 0.000 74.044 2 Moong 0.000 112.188 0.000 5.000 0.000 560.940 0.000 112.188 3 Arhar 0.000 22.438 0.000 5.800 0.000 130.138 0.000 234.249 4 Sorghum 0.000 246.814 0.000 4.000 0.000 987.254 0.000 937.892 5 Paddy 12.565 0.000 21.400 0.000 268.892 0.000 107.557 0.000 Total 12. 565 448.752 268.892 2048.553 107.557 1358.372 B Rabi 1 Wheat 16.155 283.611 19.800 12.000 319.870 3403.335 166.333 1769.734 2 Barley 134.715 0.000 12.500 0.000 1683.942 0.000 841.971 3 Masoor 35.451 0.000 4.800 0.000 170.167 0.0 00 17.017 4 Gram 148.896 0.000 6.000 0.000 893.375 0.000 178.675 5 Pea 35.451 0.000 7.500 0.000 265.886 0.000 53.177 6 Mustured 70.903 0.000 7.000 496.320 0.000 198.528 Total 16.155 709.028 319.870 6913.025 166.333 3059.102 C Zaid Nil ------Cultivable Area 897.504 - Cropping 132 - - - - intensity

66 Name of MWS – Marha Macchi Jhil (2C4B5a4b)

Area in Productivity Production (q) (ha.) q/ha. S.No. Crop. Fodder/Fuel/ Grain/Main product Irrigated Rainfed Irrigated Rainfed. Other Product. Irrigated Rainfed Irrigated Rainfed 1 2 3 4 5 6 7 8 9 10 A Kharif 1 Urd 0.000 38.736 0.000 4.800 0.000 185.934 0.000 37.187 2 Moong 0.000 64.561 0.000 5.200 0.000 335.715 0.000 67.143 3 Arhar 0.000 12.912 0.00 0 6.400 0.000 82.637 0.000 148.747 4 Sorghum 0.000 142.033 0.000 3.500 0.000 497.116 0.000 472.260 5 Paddy 7.747 0.000 20.900 0.000 161.918 0.000 64.767 0.000 Total 7.747 258.242 161.918 1101.402 64.767 725.337 B Rabi 1 Wheat 10.3 30 167.341 19.800 12.600 204.528 2108.494 106.354 1096.417 2 Barley 0.000 79.487 0.000 12.000 0.000 953.843 0.000 476.921 3 Masoor 0.000 20.918 0.000 4.500 0.000 94.129 0.000 9.413 4 Gram 0.000 87.854 0.000 6.400 0.000 562.265 0.000 112.453 5 Pea 0.000 20.918 0.000 7.500 0.000 156.882 0.000 31.376 6 Mustured 0.000 41.835 0.000 6.800 284.479 0.000 113.792 Total 10.330 418.352 204.528 4160.093 106.354 1840.372 C Zaid Nil ------Cultivable Area 516.484 - Cropping 135 - - - - intensity

67 Name of MWS – Belpur Bela (2C4B5a4a)

Area in Productivity Production (q) (ha.) q/ha. S.No. Crop. Fodder/Fuel/ Grain/Main product Irrigated Rainfed Irrigated Rainfed. Other Product. Irrigated Rainfed Irrigated Rainfed 1 2 3 4 5 6 7 8 9 10 A Kharif 1 Urd 0.000 21.770 0.000 4.800 0.000 104.498 0.000 20.900 2 Moong 0.000 36.284 0.000 5.500 0.000 199.561 0.000 39.912 3 Arhar 0.000 7.257 0.000 6.000 0.000 43.541 0.000 78.373 4 Sorghum 0.000 79.825 0.000 4.500 0.000 359 .210 0.000 341.250 5 Paddy 4.935 0.000 21.500 0.000 106.094 0.000 42.438 0.000 Total 4.935 145.136 106.094 706.810 42.438 480.435 B Rabi 1 Wheat 5.486 91.726 19.800 12.400 108.625 1137.398 56.485 591.447 2 Barley 0.000 43.570 0.00 0 11.500 0.000 501.051 0.000 250.526 3 Masoor 0.000 11.466 0.000 4.800 0.000 55.035 0.000 5.504 4 Gram 0.000 48.156 0.000 6.000 0.000 288.936 0.000 57.787 5 Pea 0.000 11.466 0.000 7.500 0.000 85.993 0.000 17.199 6 Mustured 0.000 22.931 0.000 6.800 15 5.934 0.000 62.373 Total 5.486 229.314 108.625 2224.347 56.485 984.835 C Zaid Nil ------Cultivable Area 290.271 - Cropping 133 - - - - intensity

68 Name of MWS – Banthara (2C4B5a2d)

Area in Productivity Production (q) (ha.) q/ha. S.No. Crop. Fodder/Fuel/ Grain/Main product Irrigated Rainfed Irrigated Rainfed. Other Product. Irrigated Rainfed Irrigated Rainfed 1 2 3 4 5 6 7 8 9 10 A Kharif 1 Urd 0.000 53.037 0.000 4.600 0.000 243.968 0.000 48.794 2 Moong 0.000 88.394 0.000 5.200 0.000 459.650 0.000 91.930 3 Arhar 0.000 17.679 0.000 6.500 0.000 114.912 0.000 206.842 4 Sorghum 0.000 194.467 0.000 3.500 0.000 680.635 0.000 646.604 5 Paddy 9.706 0.000 21.800 0.000 211.591 0.000 84.637 0.000 Total 9.7 06 353.577 211.591 1499.166 84.637 994.170 B Rabi 1 Wheat 12.479 219.079 19.500 11.800 243.344 2585.132 126.539 1344.269 2 Barley 0.000 104.063 0.000 12.500 0.000 1300.782 0.000 650.391 3 Masoor 0.000 27.385 0.000 4.500 0.000 123.23 2 0.000 12.323 4 Gram 0.000 115.016 0.000 6.500 0.000 747.607 0.000 149.521 5 Pea 0.000 27.385 0.000 7.400 0.000 202.648 0.000 40.530 6 Mustured 0.000 54.770 0.000 6.500 356.003 0.000 142.401 Total 12.479 547.698 243.344 5315.404 126.539 2339.43 5 C Zaid Nil ------Cultivable Area 693.288 - Cropping 133 - - - - intensity

69 Name of MWS – Dondapur (2C4B5a2c)

Area in Productivity Production (q) (ha.) q/ha. S.No. Crop. Fodder/Fuel/ Grain/Main product Irrigated Rainfed Irrigated Rainfed. Other Product. Irrigated Rainfed Irrigated Rainfed 1 2 3 4 5 6 7 8 9 10 A Kharif 1 Urd 0.000 34.714 0.000 5.400 0.000 187.455 0.000 37.491 2 Moong 0.000 57.856 0.000 4.800 0.000 277.711 0.000 55.542 3 Arhar 0.000 11. 571 0.000 6.500 0.000 75.213 0.000 135.384 4 Sorghum 0.000 127.284 0.000 4.000 0.000 509.136 0.000 483.679 5 Paddy 6.480 0.000 21.000 0.000 136.078 0.000 54.431 0.000 Total 6.480 231.426 136.078 1049.515 54.431 712.096 B Rabi 1 Wh eat 8.331 148.112 19.500 11.500 162.461 1703.292 84.480 885.712 2 Barley 0.000 70.353 0.000 12.000 0.000 844.240 0.000 422.120 3 Masoor 0.000 18.514 0.000 4.500 0.000 83.313 0.000 8.331 4 Gram 0.000 77.759 0.000 5.800 0.000 451.002 0.000 90.200 5 Pea 0.000 18.514 0.000 7.500 0.000 138.855 0.000 27.771 6 Mustured 0.000 37.028 0.000 6.600 244.385 0.000 97.754 Total 8.331 370.281 162.461 3465.088 84.480 1531.889 C Zaid Nil ------Cultivable Area 462.851 - Cropping 133 - - - - intensity

70 Name of MWS – Babina Sukhchenpur (2C4B5a1d)

Area in Productivity Production (q) (ha.) q/ha. S.No. Crop. Fodder/Fuel/ Grain/Main product Irrigated Rainfed Irrigated Rainfed. Other Product. Irrigated Rainfed Irrigated Rainfed 1 2 3 4 5 6 7 8 9 10 A Kharif 1 Urd 0.000 21.418 0.000 4.600 0.000 98.522 0.000 19.704 2 Moong 0.000 35.697 0.000 5.000 0.000 178.483 0.000 35.697 3 Arhar 0.000 7.139 0.000 5.400 0.000 38.552 0.000 69.394 4 Sorghum 0.000 78.532 0.000 4.500 0. 000 353.395 0.000 335.726 5 Paddy 4.371 0.000 20.800 0.000 90.917 0.000 36.367 0.000 Total 4.371 142.786 90.917 668.952 36.367 460.521 B Rabi 1 Wheat 5.537 94.414 19.500 11.500 107.964 1085.756 56.141 564.593 2 Barley 0.000 44.846 0.000 12.000 0.000 538.158 0.000 269.079 3 Masoor 0.000 11.802 0.000 4.500 0.000 53.108 0.000 5.311 4 Gram 0.000 49.567 0.000 5.500 0.000 272.619 0.000 54.524 5 Pea 0.000 11.802 0.000 7.500 0.000 88.513 0.000 17.703 6 Mustured 0.000 23.603 0.000 6.500 153.422 0.000 61.369 Total 5.537 236.034 107.964 2191.576 56.141 972.578 C Zaid Nil ------Cultivable Area 291.4 - Cropping 133 - - - - intensity

71 Name of MWS – Bhadasiya (2C4B5a1c)

Area in Productivity Production (q) (ha.) q/ha. S.No. Crop. Fodder/Fuel/ Grain/Main product Irrigated Rainfed Irrigated Rainfed. Other Product. Irrigated Rainfed Irrigated Rainfed 1 2 3 4 5 6 7 8 9 10 A Kharif 1 Urd 0.000 55.938 0.000 4.600 0.000 257.317 0.000 51.463 2 Moong 0.000 93.231 0.000 4.800 0.000 447.508 0.000 89.502 3 Arhar 0.000 18.646 0.000 5.500 0.000 102.554 0.000 184.597 4 Sorghum 0.000 205.108 0.000 4.000 0.000 820.431 0.000 779.409 5 Paddy 10.442 0.000 20.400 0.000 213.014 0.000 85.205 0.000 Tota l 10.442 372.923 213.014 1627.809 85.205 1104.971 B Rabi 1 Wheat 14.171 241.654 20.500 11.500 290.507 2779.022 151.064 1445.092 2 Barley 0.000 114.786 0.000 12.000 0.000 1377.428 0.000 688.714 3 Masoor 0.000 30.207 0.000 4.500 0.000 135.930 0.000 13.593 4 Gram 0.000 126.868 0.000 5.600 0.000 710.463 0.000 142.093 5 Pea 0.000 30.207 0.000 7.600 0.000 229.571 0.000 45.914 6 Mustured 0.000 60.414 0.000 6.500 392.688 0.000 157.075 Total 14.171 604.135 290.507 5625.103 151.064 2492.481 C Zaid Nil ------Cultivable Area 745.846 - Cropping 134 - - - - intensity

72 Name of MWS – Indpamau (2C4B5a1b)

Area in Productivity Production (q) (ha.) q/ha. S.No. Crop. Fodder/Fuel/ Grain/Main product Irrigated Rainfed Irrigated Rainfed. Other Product. Irrigated Rainfed Irrigated Rainfed 1 2 3 4 5 6 7 8 9 10 A Kharif 1 Urd 0.000 50.022 0.000 4.800 0.000 240.106 0.000 48.021 2 Moong 0.000 83.370 0.000 4.500 0.000 375.165 0.000 75.033 3 Arhar 0. 000 16.674 0.000 5.600 0.000 93.374 0.000 168.074 4 Sorghum 0.000 183.414 0.000 3.800 0.000 696.974 0.000 662.125 5 Paddy 9.808 0.000 20.400 0.000 200.088 0.000 80.035 0.000 Total 9.808 333.480 200.088 1405.620 80.035 953.254 B Rabi 1 Wheat 11.770 206.627 20.500 11.500 241.283 2376.211 125.467 1235.630 2 Barley 0.000 98.148 0.000 12.400 0.000 1217.033 0.000 608.517 3 Masoor 0.000 25.828 0.000 4.500 0.000 116.228 0.000 11.623 4 Gram 0.000 108.479 0.000 6.000 0.000 650.875 0.000 130.175 5 Pea 0.000 25.828 0.000 7.600 0.000 196.296 0.000 39.259 6 Mustured 0.000 51.657 0.000 6.500 335.769 0.000 134.308 Total 11.770 516.568 241.283 4892.411 125.467 2159.511 C Zaid Nil ------Cultivable Area 653. 883 - Cropping 133 - - - - intensity

73 Name of MWS – Asjana (2C4B5a1c) L

Area in Productivity Production (q) (ha.) q/ha. S.No. Crop. Fodder/Fuel/ Grain/Main product Irrigated Rainfed Irrigated Rainfed. Other Product. Irrigated Rainfed Irrigated Rainfed 1 2 3 4 5 6 7 8 9 10 A Kharif 1 Urd 0.000 26.515 0.000 4.500 0.000 119.317 0.000 23.863 2 Moong 0.000 44.192 0.000 5.500 0.000 243.054 0.000 48.611 3 Arhar 0.000 8.838 0.000 6.400 0.000 56.565 0.000 101.818 4 Sorghum 0.000 97.222 0.00 0 3.600 0.000 349.998 0.000 332.498 5 Paddy 5.199 0.000 20.800 0.000 108.140 0.000 43.256 0.000 Total 5.199 176.767 108.140 768.934 43.256 506.790 B Rabi 1 Wheat 6.239 110.912 20.000 11.800 124.776 1308.765 64.884 680.558 2 Barley 0.000 52.683 0.000 12.000 0.000 632.200 0.000 316.100 3 Masoor 0.000 13.864 0.000 4.500 0.000 62.388 0.000 6.239 4 Gram 0.000 58.229 0.000 5.500 0.000 320.259 0.000 64.052 5 Pea 0.000 13.864 0.000 7.600 0.000 105.367 0.000 21.073 6 Mustured 0.000 27.7 28 0.000 6.500 180.233 0.000 72.093 Total 6.239 277.281 124.776 2609.212 64.884 1160.115 C Zaid Nil ------Cultivable Area 346.601 - Cropping 134 - - - - intensity

74 Name of MWS – Sarai Pratham (2C4B5a1d) L

Area in Productivity Production (q) (ha.) q/ha. S.No. Crop. Fodder/Fuel/ Grain/Main product Irrigated Rainfed Irrigated Rainfed. Other Product. Irrigated Rainfed Irrigated Rainfed 1 2 3 4 5 6 7 8 9 10 A Kharif 1 Urd 0.000 58.799 0.000 4.800 0.00 0 282.236 0.000 56.447 2 Moong 0.000 97.999 0.000 5.000 0.000 489.993 0.000 97.999 3 Arhar 0.000 19.600 0.000 5.500 0.000 107.799 0.000 194.037 4 Sorghum 0.000 215.597 0.000 4.200 0.000 905.508 0.000 860.232 5 Paddy 11.550 0.000 20.600 0.000 237.930 0. 000 95.172 0.000 Total 11.550 391.995 237.930 1785.536 95.172 1208.716 B Rabi 1 Wheat 13.066 245.957 20.400 11.600 266.556 2853.106 138.609 1483.615 2 Barley 0.000 116.830 0.000 12.000 0.000 1401.957 0.000 700.979 3 Masoor 0.000 30.745 0.000 4.500 0.000 138.351 0.000 13.835 4 Gram 0.000 129.128 0.000 5.600 0.000 723.115 0.000 144.623 5 Pea 0.000 30.745 0.000 7.500 0.000 230.585 0.000 46.117 6 Mustured 0.000 61.489 0.000 6.800 418.128 0.000 167.251 Total 13.066 614.894 26 6.556 5765.242 138.609 2556.420 C Zaid Nil ------Cultivable Area 768.617 - Cropping 134 - - - - intensity

75 It was observed that the productivity of wheat, gram, mustard, arhar and linseed was about 66, 37, 33,49 and 26 per cent, respectively, less than the average (last 10 years- Source: Directorate of Economics and Statistics, Department of Agriculture and Cooperation ) productivity of the state of Uttar Pradesh.

Table 3.8: Food, fodder and fuel production in the project area (IWMP-I, District- Auraiya)

Summary Production Production Unit Total Production Remarks During Kharif during Rabi

Food Production (Atlas.)

Cereals Quintal 1791.528 3057.026 4848. 554 -

Pulses Quintal 1392.427 1546.920 2939.347 -

Oilseed Quintal 499.0 06 0.000 499.006 -

Grand Total - - 8286.907 -

Fodder Production (Atlas.)

Dry Fodder Quintal 27372.629 - - -

Green Fodder Quintal 0.00 - - -

Fuel Production

Arhar+Mustard Quintal 3011.780 - - -

Over all Cropping Intensity 134

76 3.4 Agroforestry and Horticulture There is no systematic agroforestry and orchard in the project area, however, few scattered trees of desi ber, aonla, guava, etc. was found in the micro-watersheds which is consumed locally (Table 3.7). Table 3.9: Horticulture Status

Name of Important horticultural crop Orchard Scattered Fruit Crop S. Name of micro watershed Name of Product N. with code village Productivity Production Production Name Area ha. No. ivity qtl/ha qtls (q) (q/No.) 1 2 3 4 5 6 7 8 9 10 Bhatura (E.K.) 1 Sabhad (2C4B5a4d) Gura NIL 0.00 0.00 0.00 5 0.80 4.00 Sabhad Badin (E.K.) Bhatoli Bidhuna Chakarpur Gura Jagatpur, (E.K.) 2. Mau (2C4B5a4c) Marha Machhi Jhil NIL 0.00 0.00 0.00 3 0.75 2.25 Mau Narayanpur Sahar Rajpur Bidhuna Sabhad Chakarpur Khizarpur Marha Machhi Jhil Mau 3. Marha Macchi Jhil (2C4B5a4b) NIL 0.00 0.00 0.00 7 0.60 4.20 Narayanpur Sahar Rajpur Bidhuna Rathgaon (E.K.) Sanwaliya Banthara Belpur Bela 4. Belpur Bela (2C4B5a4a) Rathgaon (E.K.) NIL 0.00 0.00 0.00 4 0.70 2.80 Sanwaliya

77 Name of Important horticultural crop Orchard Scattered Fruit Crop S. Name of micro watershed Name of Product Productio N. with code village Productivity Production Name Area ha. No. ivity n qtl/ha qtls (q/No.) (q) 1 2 3 4 5 6 7 8 9 10 Banthara Bashai Belpur Bela Marha Machhi Jhil 5. Banthara (2C4B5a2d) Narainpur Bhanu NIL 0.00 0.00 0.00 6 0.75 4.50 Rathgaon (E.K.) Sanwaliya Tajpur Bidhuna Kiratpur Bashai Dondapur Narainpur Bhanu 6. Dondapur (2C4B5a2c) Palia NIL 0.00 0.00 0.00 5 0.80 4.00 Pusauli Tajpur Bidhuna Babina Sukhchenpur Belpur Bela 7. Babina Sukhchenpur (2C4B5a1d) Pasua 0.00 0.00 0.00 2 0.85 1.70 Rathgaon (E.K.) Sarai Pratham Babina Sukhchenpur Bampur Rampur Bamrauliya Bhadsiya Bhikhra Dondapur 8 Bhadasiya (2C4B5a1c) Indapamau NIL 0.00 0.00 0.00 7 0.80 5.60 Marhokh Hariram Marhokh Mit Narayanpur Bhanu Nawada Malkhan Pusauli Roopur Sahar

78 Name of Important horticultural crop Orchard Scattered Fruit Crop S. Name of micro watershed Name of Product N. with code village Productivity Production Production Name Area ha. No. ivity qtl/ha qtls (q) (q/No.) 1 2 3 4 5 6 7 8 9 10 Asjana Barka Purwa Bhikhra Indapamau 9. Indpamau (2C4B5a1b) Rawatpur ALD) NIL 0.00 0.00 0.00 6 0.85 5.10 Rooppur Sahar Vimtamau Nawada Malkhan Asjana 10. Asjana (2C4B5a1c) (L) Hathnapur NIL 0.00 0.00 0.00 9 0.70 6.30 Vimatamau Pasua Purwa Bhadauria Ruru (ALD) Sarai Pratham Purwa 11. Sarai Pratham (2C4B5a1d) L Malikpur Mishripur 6.00 0.99 kg/ha 5940 5 0.84 4.20 (ALD) Bhadauriya Kariapur Ruru (ALD) Shivpur (ALD) Udelapur (ALD)

Total 6.00 0.99 kg/ha 5940 59 8.44 44.65 ( Scattered fruit plant of Papaya, Ber, Aonla, Guava, Karonda etc)

79 3.5 Livestock and Fisheries In the name of cattle mainly desi cow are found in the project which productivity is significantly lower than the average productivity of the state. The Details of livestock and its productivity are available in Table 3.8 and 3.9, respectively. Table 3.10: Livestock Population in IWMP- I, Auraiya (All Figures are in No.) Sr. Name of Name of Cow Buffalo Poultry Other No. Micro Village Ox/ watershed Goat Sheep Piggeries Desi Crossed Desi Murrah Bull Broiler Layers Total specify with code 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Bhatura (E.K.) 15 6 5 2 1 95 - - 7 10 141 - Sabhad Gura 10 2 4 2 1 73 - - 10 25 127 - 1 (2C4B5a4d) Sabhad 21 4 6 3 2 64 30 20 40 190 - Total 46 12 15 7 4 232 30 0 37 75 458 - Badin (E.K.) 14 3 5 2 1 60 15 14 30 70 214 - Bhatoli Bidhuna 21 5 7 4 2 69 12 18 30 80 248 - Chakarpur 7 2 4 2 1 73 - - - - 89 - Gura ------0 - Jagatpur, (E.K.) 9 2 30 12 1 75 - - - - 129 - Marha Machhi Jhil ------0 - Mau 20 2 85 15 2 81 30 - 10 30 275 - Narayanpur Sahar 5 1 20 5 1 69 - - - - 101 - Mau Rajpur Bidhuna 10 2 40 15 1 58 - 8 65 130 329 - 2 (2C4B5a4c) Sabhad ------0 - Total 86 17 191 55 9 485 57 40 135 310 1385 - Chakarpur 5 1 20 4 2 70 - - - - 102 - Khizarpur 20 4 18 5 2 93 - - - - 142 - Marha Machhi Jhil 50 6 160 40 2 74 125 - 10 20 487 - Mau ------0 - Narayanpur Sahar ------0 - Rajpur Bidhuna 15 3 31 16 1 48 11 4 20 30 179 - Marha Macchi Jhil Rathgaon (E.K.) 30 5 125 30 2 85 3 21 18 120 439 - 3 (2C4B5a4b) Sanwaliya 27 12 35 15 2 76 20 21 208 - Total 147 31 389 110 11 446 159 46 48 170 1557 -

80 Sr. Name of Name of Cow Buffalo Poultry Other No. Micro Village Ox/ watershed Goat Sheep Piggeries Desi Crossed Desi Murrah Bull Broiler Layers Total specify with code 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Banthara 24 5 40 12 2 62 27 13 185 - Belpur Bela 12 6 31 6 1 49 37 31 7 16 196 - Belpur Bela Rathgaon (E.K.) ------4 (2C4B5a4a) Sanwaliya ------Total 36 11 71 18 3 111 64 44 7 16 381 - Banthara ------Bashai 8 3 24 20 1 54 - - 5 20 135 - Belpur Bela ------Marha Machhi Jhil ------Narainpur Bhanu 14 7 30 16 1 75 - - 20 30 193 - Rathgaon (E.K.) ------Sanwaliya ------Banthara Tajpur Bidhuna 9 7 22 14 1 83 11 10 25 182 - 5 (2C4B5a2d) Kiratpur 7 4 20 16 1 40 11 20 91 210 - Total 38 21 96 66 4 252 11 11 55 166 720 - Bashai ------Dondapur 9 7 30 17 1 92 - 16 13 21 206 - Narainpur Bhanu ------Palia 6 6 21 17 1 87 - - 5 11 154 - Dondapur Pusauli 8 3 34 16 1 86 - 14 21 41 224 - 6 (2C4B5a2c) Tajpur Bidhuna ------Total 23 16 85 50 3 265 0 30 39 73 584 - Babina Sukhchenpur 6 5 36 15 1 93 - - - - 156 - Belpur Bela ------0 - Pasua 14 7 57 18 0 88 - - - - 184 - Babina Sukhchenpur Rathgaon (E.K.) ------0 - 7 (2C4B5a1d) Sarai Pratham 20 5 65 20 1 94 - - 2 11 218 - Total 40 17 158 53 2 275 - - 2 11 558 -

81 Sr. Name of Name of Cow Buffalo Poultry Other No. Micro Village Ox/ watershed Goat Sheep Piggeries Desi Crossed Desi Murrah Bull Broiler Layers Total specify with code 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Babina Sukhchenpur ------Bampur Rampur 8 6 41 17 0 77 - - - - 149 - Bamrauliya 9 3 36 13 1 82 - - - - 144 - Bhadsiya 6 7 31 13 1 69 - - 9 21 157 - Bhikhra ------Dondapur ------Indapamau 11 4 35 136 0 91 11 9 11 23 331 - Marhokh Hariram 4 1 16 5 0 78 - - - - 104 - Marhokh Mit 7 3 37 14 1 86 - - 9 24 181 - Narayanpur Bhanu ------Nawada Malkhan 6 3 39 15 1 79 - - - - 143 - Bhadasiya Pusauli 23 7 65 35 0 81 13 - 160 20 404 - 8 (2C4B5a1c) Roopur Sahar 6 3 20 16 1 84 - - - 130 - Total 80 37 320 264 5 727 24 9 189 88 1743 - Asjana 25 10 150 30 0 87 50 150 300 802 - Barka Purwa 8 4 17 13 1 34 13 3 10 4 107 - Bhikhra ------Indapamau ------Rawatpur ALD) 9 3 30 15 1 92 - - 15 41 206 - Rooppur Sahar ------Indpamau Vimtamau 10 4 56 12 0 85 - 27 - - 194 - 9 (2C4B5a1b) Nawada Malkhan ------Total 52 21 253 70 2 298 13 80 175 345 1309 - Asjana ------Asjana (2C4B5a1c) Hathnapur 18 9 37 18 1 67 43 23 16 26 258 - 10 (L) Vimatamau ------Total 18 9 37 18 1 67 43 23 16 26 258 -

82 Sr. Name of Name of Cow Buffalo Poultry Other No. Micro Village Ox/ watershed Goat Sheep Piggeries Desi Crossed Desi Murrah Bull Broiler Layers Total specify with code 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Pasua ------Purwa Bhadauria Ruru (ALD) 7 3 31 17 1 90 - - - - 149 - Sarai Pratham ------Malikpur Mishripur (ALD) 5 2 27 14 1 45 - - - - 94 - Sarai Kariapur Ruru (ALD) 9 14 29 14 2 59 - - - - 127 - Pratham (2C4B5a1d) Shivpur (ALD) 17 8 57 18 2 89 27 26 17 62 323 - 11 L Udelapur (ALD) 8 3 31 13 1 65 - - - - 121 - Total 46 30 175 76 7 348 27 26 17 62 814 - Grand Total 612 222 1790 787 51 3506 428 309 720 1342 9767 -

83 Table 3.11: Productivity of livestock in IWMP-I, Auraiya

Milk Production (Liter Per day) per Animal Goatry Poultry Piggeries Name of Micro Sr. Name of Broiler weight watershed with Weight in Layers No. of No. Village Cow Buffalo Weight Kg/Pig code Kg/goat eggs/day in Kg/ Brl Desi Crosse Desi Murrah 1 2 3 4 5d 6 7 8 9 10 11 Bhatura (E.K.) 1.50 2.60 2.70 3.50 8.00 0.90 9 - Sabhad 1. Gura 1.70 2.50 2.80 3.80 7.50 0.70 25 - (2C4B5a4d) Sabhad 1.40 2.40 2.50 3.70 6.50 0.80 37 - Badin (E.K.) 1.50 2.10 2.40 3.80 6.40 0.70 51 16 Bhatoli Bidhuna 1.50 2.00 2.70 4.00 7.80 1.00 65 15 Chakarpur 1.60 2.60 2.90 3.40 8.00 - - -- Gura ------Jagatpur, (E.K.) 1.40 2.00 3.00 3.60 6.50 - - - 2. Mau (2C4B5a4c) Marha Machhi Jhil ------Mau 1.30 2.40 2.50 3.70 6.40 0.70 25 Narayanpur Sahar 1.30 2.40 2.40 3.70 6.90 - - - Rajpur Bidhuna 1.40 2.00 2.80 3.90 7.00 0.80 10 15 Sabhad ------Chakarpur ------Khizarpur 1.20 2.50 2.70 3.70 7.50 - - - Marha Machhi Jhil 1.40 2.70 2.80 4.00 6.40 1.00 16 - Marha Macchi Mau ------3. Jhil (2C4B5a4b) Narayanpur Sahar ------Rajpur Bidhuna ------Rathgaon (E.K.) 1.50 2.50 2.50 3.80 7.90 0.90 17 13 Sanwaliya 1.50 2.40 2.70 3.90 6.80 - - 17 Banthara 1.40 2.00 2.90 3.40 6.50 - - 16 Belpur Bela Belpur Bela 1.00 2.50 2.50 3.50 7.50 0.80 11 17 4. (2C4B5a4a) Rathgaon (E.K.) ------Sanwaliya ------

84 Milk Production (Liter Per day) per Animal Goatry Poultry Piggeries Name of Micro Sr. Name of Broiler weight watershed with Weight in Layers No. of No. Village Cow Buffalo Weight Kg/Pig code Kg/goat eggs/day in Kg/ Brl

Desi Crosse Desi Murrah 1 2 3 4 5 6 7 8 9 10 11 Banthara ------Bashai 1.50 2.80 2.70 3.60 7.80 0.80 15 Belpur Bela ------Marha Machhi Jhil ------Banthara 5. (2C4B5a2d) Narainpur Bhanu 1.40 2.40 2.80 3.90 7.00 0.80 25 Rathgaon (E.K.) ------Sanwaliya ------Tajpur Bidhuna 1.50 2.00 2.80 4.00 6.80 0.80 25 17 Kiratpur 1.60 2.50 2.70 3.80 8.00 0.90 Bas hai ------Dondapur 1.20 2.80 2.50 3.50 7.50 1.00 15 18 Dondapur Narainpur Bhanu ------6. (2C4B5a2c) Palia 1.40 2.00 3.00 3.50 7.00 0.80 8 Pusauli 1.50 2.40 2.80 3.70 6.70 0.90 35 17 Tajpur Bidhuna ------Babina Sukhchenpur 1.00 2.50 2.50 4.00 7.80 - - - Babina Belpur Bela ------7. Sukhchenpur Pasua 1.20 2.00 2.40 3.50 8.00 - (2C4B5a1d) Rathgaon (E.K.) ------Sarai Pratham 1.50 2.40 2.80 3.80 7.50 0.80 9 -

85

Milk Production (Liter Per day) per Animal Goatry Poultry Piggeries Name of Micro Sr. Name of Broiler weight watershed with Weight in Layers No. of No. Village Cow Buffalo Weight Kg/Pig code Kg/goat eggs/day in Kg/ Brl

Desi Crosse Desi Murrah 1 2 3 4 5 6 7 8 9 10 11 Babina Sukhchenpur ------Bampur Rampur 1.50 3.00 2.50 3.70 6.80 - Bamrauliya 1.00 2.80 2.90 3.50 8.00 - - - Bhadsiya 1.50 2.50 2.50 4.00 7.80 0.80 17 - Bhikhra ------Dondapur ------Bhadasiya 8. (2C4B5a1c) Indapamau 1.40 2.00 2.80 3.40 7.90 0.90 20 16 Marhokh Hariram 1.30 2.00 2.90 3.50 9.00 - - - Marhokh Mit 1.50 2.50 2.40 3.80 6.50 0.90 18 - Narayanpur Bhanu ------Nawada Malkhan 1.60 2.80 3.00 4.00 7.50 - - - Pusauli 1.50 2.50 2.80 3.80 6.90 1.00 130 - Roopur Sahar 1.40 2.00 2.40 3.50 6.50 - - - Asjana 1.70 2.60 2.50 3.40 6.70 0.90 250 18 Barka Purwa 1.40 2.70 2.50 3.80 7.40 0.80 10 14 Bhikhra ------Indpamau Indapamau ------9. (2C4B5a1b) Rawatpur ALD) 1.50 2.00 2.70 3.90 7.50 0.80 35 - Rooppur Sahar ------Vimtamau 1.50 2.00 2.60 3.70 8.00 - - 16 Nawada Malkhan ------Asjana ------Asjana 10. (2C4B5a1c) (L) Hathnapur 1.60 2.80 2.50 4.00 7.40 0.9 0 33 18 Vimatamau ------

86

Milk Production (Liter Per day) per Animal Goatry Poultry Piggeries Name of Micro Sr. Name of Broiler weight watershed with Weight in Layers No. of No. Village Cow Buffalo Weight Kg/Pig code Kg/goat eggs/day in Kg/ Brl

Desi Crosse Desi Murrah 1 2 3 4 5 6 7 8 9 10 11 Pasua ------Purwa Bhadauria Ruru (ALD) 1.80 2.50 2.50 4.00 6.90 - - - Sarai Pratham ------Sarai Pratham Malikpur Mishripur (ALD) 1.40 2.50 3.00 3.70 7.50 - - - 11. (2C4B5a1d) L Kariapur Ruru (ALD) 1.00 2.00 2.70 3.90 8.00 - - - Shivpur (ALD) 1.80 2.00 2.50 3.50 6.90 - - - Udelapur (ALD) 1.50 2.80 2.80 3.40 7.50 - - - Average for IWMP -I 1.43 2.39 2.67 3.72 7.30 0.85 36.44 17.36

87 3.6 Forest and Grassland Degraded forest planted by Gram Panchayat and Grass land available in project area is given below in Table 3.12. Table 3.12: Forest, vegetative cover/grassland in IWMP-I, Auraiya Other vegetative cover Forest (Area ha) Grassland (Area ha) (Area ha.) Name of Micro Gram Sr. Name of watershed with Samaj Gram No. Village code Reserve (Natural Total Samaj Private Gram Private /Planted Samaj

1 2 3 4 5 6 7 8 9 10 Bhatura (E.K.) 0.000 0.000 0.000 1.150 0.000 0.000 1.350 1 Sabhad (2C4B5a4d) Gura 0.000 0.000 0.000 0.300 0.000 0.000 2.260 Sabhad 0.000 0.000 0.000 5.212 0.000 0.000 0.800 Total 4.000 5.000 6.000 13.662 8.000 9.000 14.410 Badin (E.K.) 0.000 0.000 0.000 1.600 0.000 0.000 0.320 Bhatoli Bidhuna 0.000 0.000 0.000 0.000 0.000 0.000 0.210 Chakarpur 0.000 1.640 1.640 1.100 0.000 0.000 2.320 Gura 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Jagatpur, (E.K.) 0.000 0.000 0.000 0.641 0.000 0.000 1.700 2 Mau (2C4B5a4c) Marha Machhi Jhil 0.000 0.000 0.000 2.110 0.000 0.000 4.200 Mau 0.000 2.013 2.013 5.013 0.000 0.000 3.400 Narayanpur Sahar 0.000 0.000 0.000 1.513 0.000 0.000 3.600 Rajpur Bidhuna 0.000 0.000 0.000 1.131 0.000 0.000 6.200 Sabhad 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Total 0.000 3.653 3.653 13.108 0.000 0.000 21.950 Chakarpur 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Khizarpur 0.000 0.000 0.000 0.610 0.000 0.000 2.400 Marha Machhi Jhil 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Marha Macchi Jhil Mau 0.000 0.000 0.000 0.000 0.000 0.000 0.000 3 (2C4B5a4b) Narayanpur Sahar 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Rajpur Bidhuna 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Rathgaon (E.K.) 0.000 0.000 0.000 3.400 0.000 0.000 8.400 Sanwaliya 0.000 0.000 0.000 1.200 0.000 0.000 4.320 Total 0.000 0.000 0.000 5.210 0.000 0.000 15.120

88 Name of Micro Other vegetative cover Sr. Name of Forest (Area ha) Grassland (Area ha) No. watershed with Village (Area ha.) code Gram Samaj Gram Reserve (Natural Total Samaj Private Gram Private /Planted Samaj

1 2 3 4 5 6 7 8 9 10 Banthara 0.000 0.000 0.000 1.300 0.000 0.000 5.400 Belpur Bela 0.000 0.000 0.000 2.500 0.000 0.000 4.700 4 Belpur Bela (2C4B5a4a) Rathgaon (E.K.) 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Sanwaliya 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Total 0.000 0.000 0.000 3.800 0.000 0.000 10.100 Banthara 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Bashai 0.000 0.000 0.000 0.510 0.000 0.000 2.600 Belpur Bela 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Marha Machhi Jhil 0.000 0.000 0.000 0.000 0.000 0.000 0.000 5 Banthara (2C4B5a2d) Narainpur Bhanu 0.000 0.000 0.000 1.250 0.000 0.000 3.600 Rathgaon (E.K.) 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Sanwaliya 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Tajpur Bidhuna 0.000 0.000 0.000 2.400 0.000 0.000 8.700 Kiratpur 0.000 0.000 0.000 0.410 0.000 0.000 4.690 Total 0.000 0.000 0.000 4.570 0.000 0.000 19.590 Bashai 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Dondapur 0.000 0.000 0.000 2.400 0.000 0.000 3.800 Narainpur Bhanu 0.000 0.000 0.000 0.000 0.000 0.000 0.000 6 Dondapur (2C4B5a2c) Palia 0.000 0.000 0.000 1.300 0.000 0.000 0.118 Pusauli 0.000 0.000 0.000 1.300 0.000 0.000 3.200 Tajpur Bidhuna 0.000 6.403 6.403 0.000 0.000 0.000 0.000 Total 0.000 6.403 6.403 5.000 0.000 0.000 7.118 Babina Sukhchenpur 0.000 0.000 0.000 1.600 0.000 0.000 5.700 Belpur Bela 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Babina Sukhchenpur 7 Pasua 0.000 4.013 4.013 1.200 0.000 0.000 2.780 (2C4B5a1d) Rathgaon (E.K.) 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Sarai Pratham 0.000 0.000 0.000 1.800 0.000 0.000 2.400 Total 0.000 4.013 4.013 4.600 0.000 0.000 10.880

89 Name of Micro Other vegetative cover Sr. Name of Forest (Area ha) Grassland (Area ha) No. watershed with Village (Area ha.) code Gram Samaj Gram Reserve (Natural Total Samaj Private Gram Private /Planted Samaj

1 2 3 4 5 6 7 8 9 10 Babina Sukhchenpur 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Bampur Rampur 0.000 0.000 0.000 0.600 0.000 0.000 1.700 Bamrauliya 0.000 0.000 0.000 1.800 0.000 0.000 6.400 Bhadsiya 0.000 1.246 1.246 1.700 0.000 0.000 7.320 Bhikhra 0.000 0.000 0.000 2.100 0.000 0.000 2.100 Dondapur 0.000 0.000 0.000 0.000 0.000 0.000 0.000 8 Bhadasiya (2C4B5a1c) Indapamau 0.000 0.000 0.000 2.500 0.000 0.000 3.800 Marhokh Hariram 0.000 0.000 0.000 0.520 0.000 0.000 1.700 Marhokh Mit 0.000 0.000 0.000 0.320 0.000 0.000 0.040 Narayanpur Bhanu 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Nawada Malkhan 0.000 0.000 0.000 1.210 0.000 0.000 2.700 Pusauli 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Roopur Sahar 0.000 0.000 0.000 3.200 0.000 0.000 9.700 Total 0.000 1.246 1.246 13.950 0.000 0.000 35.460 Asjana 0.000 0.000 0.000 0.850 0.000 0.000 1.320 Barka Purwa 0.000 0.000 0.000 0.600 0.000 0.000 1.600 Bhikhra 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Indapamau 0.000 0.000 0.000 0.000 0.000 0.000 0.000 9 Indpamau (2C4B5a1b) Rawatpur ALD) 0.000 0.000 0.000 1.200 0.000 0.000 11.200 Rooppur Sahar 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Vimtamau 0.000 0.000 0.000 3.100 0.000 0.000 6.950 Nawada Malkhan 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Total 0.000 0.000 0.000 5.750 0.000 0.000 21.070 Asjana 0.000 0.000 0.000 0.000 0.000 0.000 0.000 10 Asjana (2C4B5a1c) (L) Hathnapur 0.000 1.310 1.310 1.200 0.000 0.000 6.500 Vimatamau 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Total 0.000 1.310 1.310 1.200 0.000 0.000 6.500

90 Name of Micro Other vegetative cover Sr. Name of Forest (Area ha) Grassland (Area ha) No. watershed with Village (Area ha.) code Gram Samaj Gram Reserve (Natural Total Samaj Private Gram Private /Planted Samaj

1 2 3 4 5 6 7 8 9 10 Pasua 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Purwa Bhadauria Ruru (ALD) 0.000 0.000 0.000 1.200 0.000 0.000 2.450 Sarai Pratham 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Sarai Pratham 11 Malikpur Mishripur (AL D) 0.000 0.000 0.000 0.850 0.000 0.000 4.850 (2C4B5a1d) L Kariapur Ruru (ALD) 0.000 0.000 0.000 0.920 0.000 0.000 3.700 Shivpur (ALD) 0.000 0.000 0.000 3.400 0.000 0.000 8.900 Udelapur (ALD) 0.000 0.000 0.000 0.820 0.000 0.000 7.200 Total 0.000 0.000 0.000 7.190 0.000 0.000 27.100 Grand Total 4.000 21.625 22.625 78.040 8.000 9.000 189.298

3.7 Livelihood Status

Assestless/landless people earn their livelihood mainly from labour and batai. They were earning about Rs. 3000/per month. It is expected that their income will enhance due to watershed management as it will generate sustained employment opportunity. Intervention based on piggeries, fisheries, black smithy and carpentery was not in practice. Livelihood status of landless, farmers and interventions based livelihood status are shown in Table 3.11, 3.12 and 3.13, respectively.

91 Table 3.13: Livelihood Status of Landless People IWMP-I Auraiya

No. of house hold engaged Pre Expected Desired project Income Name of Name of Activities Name of Average from micro village S. N. livelihood Income/ desired Remarks Sc St Other Women Total watershed activities Activity with code Year Rs/Year

1 2 3 4 5 6 7 8 9 10 11 12 13 Bhatura (E.K.) 4 - 5 3 12 With Goatery investment Sabhad Gura Labour/ 3 - 7 4 14 38012 70524 1 Dairy work i.e. (2C4B5a4d) Sabhad Batai 8 - 6 3 17 extra income Total 15 - 18 10 43 in SHG Badin (E.K.) 6 - 4 2 12 Bhatoli Bidhuna 6 - 2 4 12 Chakarpur 4 - 5 2 11 Gura - - - - With Goatery investment Mau Jagatpur, (E.K.) Labour/ 4 - 6 4 14 2 35144 Dairy 69360 work i.e. (2C4B5a4c) Marha Machhi Jhil Batai 8 - 5 4 17 Mau 7 - 10 6 23 extra income Narayanpur Sahar 3 - 7 3 13 in SHG Rajpur Bidhuna - - - - Sabhad - 0 Total 38 - 39 25 102 Chakarpur - - - - Khizarpur 4 - 5 2 11 Marha Machhi Jhil - - - - With Marha Macchi Goatery investment Mau Labour/ - - - - 3 Jhil 32288 Dairy 68160 work i.e. Narayanpur Sahar Batai - - - - (2C4B5a4b) Rajpur Bidhuna 4 - 7 2 13 extra income Rathgaon (E.K.) - - - - in SHG Sanwaliya - - - - Total 8 - 12 4 24

92 No. of house hold engaged Pre Expected Desired project Income Name of Name of Activities Name of Average from micro village S. N. livelihood Income/ desired Remarks Sc St Other Women Total watershed activities Activity with code Year Rs/Year

1 2 3 4 5 6 7 8 9 10 11 12 13 Banthara 7 - 8 4 19 With Goatery investment Belpur Bela Belpur Bela Labour/ 5 - 8 2 15 4 44750 Dairy 73500 work i.e. extra (2C4B5a4a) Rathgaon (E.K.) Batai - - - - Sanwaliya 5 - 7 6 18 income in Total 17 - 23 12 52 SHG Banthara - - - - Bashai 1 - 2 1 4 Belpur Bela - - - - Marha Machhi Jhil - - - - With Goatery investment Banthara Narainpur Bhanu Labour/ 4 - 5 3 12 52682 80857 5 Dairy work i.e. extra (2C4B5a2d) Rathgaon (E.K.) Batai 7 - 8 6 21 Sanwaliya - - - - income in Tajpur Bidhuna - - - - SHG Kiratpur 5 - 6 5 16 village - - - - Total 17 - 21 15 53 Bashai - - - - Dondapur 6 - 7 3 16 With Goatery investment Dondapur Narainpur Bhanu Labour/ - - - - 6 53730 Dairy 85488 work i.e. extra (2C4B5a2c) Palia Batai 2 - - - 2 Pusauli 6 - 8 5 19 income in Tajpur Bidhuna 5 - 6 5 16 SHG Total 19 - 21 13 53

93 No. of house hold engaged Pre Expected Desired project Income Name of Name of Activities Name of Average from micro village S. N. livelihood Income/ desired Remarks Sc St Other Women Total watershed activities Activity with code Year Rs/Year

1 2 3 4 5 6 7 8 9 10 11 12 13 Babina Sukhchenpur 3 - 5 2 10 With Belpur Bela - - - - Babina Goatery investment Pasua Labour/ 6 - 9 3 18 7 Sukhchenpur 41124 Dairy 82436 work i.e. extra Rathgaon (E.K.) Batai - - - - (2C4B5a1d) income in Sarai Pratham 5 - 8 3 16 SHG Total 14 - 22 8 44 Babina Sukhchenpur - - - - Bampur Rampur 4 - 5 2 11 Bamrauliya - 7 2 9 Bhadsiya 5 - 6 5 16 Bhikhra 5 - 6 4 15 With Dondapur - - - - Goatery investment Bhadasiya Labour/ 8 Indapamau 9 - 10 2 21 39195 Dairy 77280 work i.e. extra (2C4B5a1c) Batai Marhokh Hariram 3 - 4 2 9 income in Marhokh Mit 4 - 5 3 12 SHG Narayanpur Bhanu - - - - Nawada Malkhan 4 - 7 3 14 Pusauli - - - - Roopur Sahar - - - - Total 34 - 50 23 107 Asjana - - - - Barka Purwa 2 - 8 2 12 Bhikhra - - - - With Goatery investment Indpamau Indapamau Labour/ - - - - 9 32893 Dairy 78279 work i.e. extra (2C4B5a1b) Rawatpur ALD) Batai - - - - Rooppur Sahar 4 - 5 3 12 income in Vimtamau 5 - 6 2 13 SHG Nawada Malkhan - - - - Total 11 - 19 - 30

94

No. of house hold engaged Pre Expected Desired project Income Name of Name of Activities Name of Average from micro village S. N. livelihood Income/ desired Remarks Sc St Other Women Total watershed activities Activity with code Year Rs/Year

1 2 3 4 5 6 7 8 9 10 11 12 13 Asjana 8 - 9 6 23 With Asjana Goatery investment Hathnapur Labour/ 4 - 8 1 13 10 (2C4B5a1c) 35748 Dairy 79100 work i.e. extra Vimatamau Batai - - - - (L) income in Total 12 - 17 7 36 SHG Pasua - - - - Purwa Bhadauria Ruru 13 - - - 13 (ALD) With Sarai Pratham Goatery investment 11 Sarai Pratham - - - - (2C4B5a1d) L Malikpur Mishripur (ALD) Labour/ 1 - 4 1 6 46232 Goatery 81448 work i.e. extra income in Kariapur Ruru (ALD) Batai 1 - 2 1 4 SHG Shivpur (ALD) 3 - 7 4 14 Udelapur (ALD) 4 - 8 2 14 Total 22 21 8 51 Grand Total 207 - 263 125 595 4107 2 Average 76948 -

95 Table 3.14: Details of Livelihood Status of the Farmers No. of house hold engaged Pre Remark project Expected s Name of Micro Name of Desired Sr. Name of Average Income from watershed with livelihood Activities No. Village Sc St Other Women Total Income/ desired code Activity Year activities

1 2 3 4 5 6 7 8 9 10 11 12 Bhatura (E.K.) 44 - 60 11 115 Improveemnt of agri. Agriculture + prod. Improvement of Gura 31 - 42 9 82 Sabhad A.H., Labour, 35000-45000 animal husbandry 55000-60000 1. Sabhad Batai NRM Livelihood (2C4B5a4d) 29 - 145 17 191 activities Total 104 - 247 37 388 Badin (E.K.) 43 - 171 18 232 Bhatoli Bidhuna 37 - 143 14 194 Chakarpur - - 31 7 38

Gura - - - - - Improveemnt of agri. Jagatpur, (E.K.) Agriculture + 23 - 39 10 72 prod. Improvement of A.H., Labour, 35000-45000 animal husbandry 50000-65000 2. Mau (2C4B5a4c) Marha Machhi Jhil Batai 31 - 52 13 96 NRM Livelihood Mau 48 - 59 9 116 activities Narayanpur Sahar 13 - 24 5 42 Rajpur Bidhuna 32 - 62 13 107 Sabhad - - - - - Total 227 - 581 89 897 Chakarpur - - - - - Khizarpur 22 - 26 7 55

Marha Machhi Jhil - - - - - Improveemnt of agri. Mau Agriculture + - - - - - prod. Improvement of Marha Macchi A.H., Labour, 35000-45000 animal husbandry 55000-65000 3. Narayanpur Sahar - - - - - Jhil (2C4B5a4b) Batai NRM Livelihood Rajpur Bidhuna - - - - - activities Rathgaon (E.K.) 48 - 81 21 150 Sanwaliya 30 - 61 11 102 Total 100 - 168 39 307

96 No. of house hold engaged Pre Remark project Expected s Name of Micro Name of Desired Sr. Name of Average Income from watershed with livelihood Activities No. Village Sc St Other Women Total Income/ desired code Activity Year activities

1 2 3 4 5 6 7 8 9 10 11 12 Banthara 41 - 102 21 164 Improveemnt of agri. Belpur Bela Agriculture + 43 - 89 17 149 prod. Improvement of Belpur Bela A.H., Labour, 35000-45000 animal husbandry 50000-65000 4. Rathgaon (E.K.) - - - - - (2C4B5a4a) Batai NRM Livelihood Sanwaliya - - - - - activities Total 84 - 191 38 313 Banthara - - - - - Bashai 27 - 61 9 97 Belpur Bela - - - - - Improveemnt of agri. Marha Machhi Jhil - - - - - Agriculture + prod. Improvement of Banthara Narainpur Bhanu A.H., Labour, 31 - 58 7 96 35000-45000 animal husbandry 55000-60000 5. Batai NRM Livelihood (2C4B5a2d) Rathgaon (E.K.) - - - - - activities Sanwaliya - - - - - Tajpur Bidhuna 39 - 82 11 132 Kiratpur 19 - 35 6 60 Total 116 - 236 33 385 Bashai - - - - -

Dondapur 23 - 36 7 66 Improveemnt of agri. Narainpur Bhanu Agriculture + - - - - - prod. Improvement of Dondapur A.H., Labour, 35000-45000 animal husbandry 50000-65000 6. Palia 30 - 41 5 76 (2C4B5a2c) Batai NRM Livelihood Pusauli 26 - 43 9 78 activities Tajpur Bidhuna - - - - - Total 79 - 120 21 220

97

No. of house hold engaged Pre Remark project Expected s Name of Micro Name of Desired Sr. Name of Average Income from watershed with livelihood Activities No. Village Sc St Other Women Total Income/ desired code Activity Year activities

1 2 3 4 5 6 7 8 9 10 11 12 Babina Sukhchenpur 21 - 34 8 63 Improveemnt of agri. Belpur Bela - - - - - Agriculture + prod. Improvement of Babina Pasua A.H., Labour, 28 - 53 11 92 35000-45000 animal husbandry 55000-65000 7. Sukhchenpur Batai NRM Livelihood Rathgaon (E.K.) - - - - - (2C4B5a1d) activities Sarai Pratham 38 - 61 7 106 Total 87 0 148 26 261 Babina Sukhchenpur - - - - - Bampur Rampur 39 - 54 9 102 Bamrauliya 31 - 59 11 101 Bhadsiya 38 - 64 7 109 Bhikhra 34 - 74 13 121 Improveemnt of agri. Dondapur 41 - 78 13 132 Agriculture + prod. Improvement of Bhadasiya Indapamau A.H., Labour, 24 - 47 7 78 35000-45000 animal husbandry 55000-60000 8. Batai NRM Livelihood (2C4B5a1c) Marhokh Hariram 14 - 23 5 42 activities Marhokh Mit 28 - 59 9 96 Narayanpur Bhanu - - - - - Nawada Malkhan 21 - 47 8 76 Pusauli - - - - - Roopur Sahar 17 - 41 7 65 Total 287 0 546 89 922

98

No. of house hold engaged Pre Remark project Expected s Name of Micro Name of Desired Sr. Name of Average Income from watershed with livelihood Activities No. Village Sc St Other Women Total Income/ desired code Activity Year activities

1 2 3 4 5 6 7 8 9 10 11 12 Asjana 32 - 141 11 184 Barka Purwa 21 - 43 5 69

Bhikhra - - - - - Improveemnt of agri. Indapamau Agriculture + - - - - - prod. Improvement of Indpamau A.H., Labour, 35000-45000 animal husbandry 55000-65000 9. Rawatpur ALD) 27 - 56 9 92 (2C4B5a1b) Batai NRM Livelihood Rooppur Sahar - - - - - activities Vimtamau 24 - 51 7 82 Nawada Malkhan 21 - 47 5 73 Total 125 0 338 37 500 Asjana - - - - - Improveemnt of agri. Agriculture + prod. Improvement of Hathnapur 21 - 46 9 76 Asjana A.H., Labour, 35000-45000 animal husbandry 50000-65000 10. Vimatamau Batai NRM Livelihood (2C4B5a1c) (L) - - - - - activities Total 21 - 46 9 76 Pasua - - - - - Purwa Bhadauria Ruru (ALD) 13 - 27 5 45 Improveemnt of agri. Sarai Pratham 22 - 47 7 76 Agriculture + prod. Improvement of Sarai Pratham Malikpur Mishripur (ALD) A.H., Labour, 20 - 23 3 4635000-45000 animal husbandry 50000-60000 11. Batai NRM Livelihood (2C4B5a1d) L Kariapur Ruru (ALD) 19 - 41 6 66 activities Shivpur (ALD) 39 - 121 13 173 Udelapur (ALD) 14 29 7 50 Total 127 0 288 41 456 - - - - Grand Total 1357 0 2909 459 4725 - - - -

99 Table 3.15: Present Livelihood Status (No. of households/Income per year) in IWMP-I Auraiya Income in Rs Activities Name of Black Carpentry Stitching Wages Agriculture Micro Dairy Poultry Goatry Piggeries FisheriesSmithy / Sr. Name of watershed knitting No. Village with Av. Av. Av. Av. Av. Av. Av. Av. Av. Av. code No No No No No incom No No No incom No No income income income income income income income income e e 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Bhatura (E.K.) 115 10500 3 10500 32 24500 ------16 11500 115 25500 Sabhad Gura 82 10300 - - 17 24400 ------14 12000 82 23200 1. (2C4B5a4d) Sabhad 191 10200 8 10600 70 23300 ------22 12500 191 21000 Total 388 - 11 - 119 ------52 - 388 - Badin (E.K.) 232 10400 9 12600 72 23200 2 18500 ------27 11000 232 18500 Bhatoli Bidhuna 194 10300 11 12600 71 21600 4 18300 ------24 12000 194 20000 Chakarpur 38 10100 - - 9 21200 ------4 12500 38 22000 Gura ------Jagatpur, (E.K.) 72 10400 - - 18 21700 ------14 11500 72 23200 Mau 2. Marha Machhi Jhil 96 10300 - - 36 21200 ------16 12000 96 25000 (2C4B5a4c) Mau 116 10500 5 11400 22 21800 ------5 12500 116 23000 Narayanpur Sahar 42 10100 11700 17 21600 ------6 11500 42 22500 Rajpur Bidhuna 107 10400 13 15700 21 21500 2 18400 15 12000 107 24500 Sabhad ------Total 897 - 38 - 266 - 8 55200 ------111 - 897 - Chakarpur ------Khizarpur 55 10500 - - 10 21500 ------55 23600 Marha Machhi Jhil ------Marha Macchi Mau ------3. Jhil Narayanpur Sahar ------(2C4B5a4b) Rajpur Bidhuna ------Rathgaon (E.K.) 150 10400 9 12300 44 21700 3 18500 ------26 12500 150 24000 Sanwaliya 102 10300 17 21800 3 18400 ------23 11500 102 23500 Total 307 - 9 - 71 - 6 ------49 - 307 - Banthara 164 10200 - - 13 24500 4 18600 ------21 11000 164 23700 Belpur Bela 149 10300 - - 7 24600 5 18200 ------18 11500 149 19200 Belpur Bela 4. Rathgaon (E.K.) ------(2C4B5a4a) Sanwaliya ------Total 313 - - - 20 - 9 ------0 - 39 - 313 -

100 Activities Name of Black Carpentry Stitching Wages Agriculture Micro Dairy Poultry Goatry Piggeries FisheriesSmithy / Sr. Name of watershed knitting No. Village with Av. Av. Av. Av. Av. Av. Av. Av. Av. Av. code No No No No No incom No No No incom No No income income income income income income income income e e 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Banthara ------Bashai 97 10500 - - 4 24600 ------11 12500 97 18500 Belpur Bela ------Marha Machhi Jhil ------Banthara 5. Narainpur Bhanu 96 104 00 2 3880 8 23500 ------21 11000 96 20500 (2C4B5a2d) Rathgaon (E.K.) ------Sanwaliya ------Tajpur Bidhuna 132 10200 2 3600 16 22400 ------21 11500 132 21200 Kiratpur 60 10300 4 3700 7 23300 3 18200 ------14 11500 60 23500 Total 385 - 8 - 35 - 3 ------67 - 385 - Bashai ------Dondapur 66 10500 2 3400 24 23800 5 18200 ------19 10500 66 24200 Narainpur Bhanu ------Dondapur 6. Palia 76 10200 2 2100 18 24200 17 12500 76 20500 (2C4B5a2c) Pusauli 78 10300 7 9800 24 24300 4 18600 19 12500 78 21200 Tajpur Bidhuna ------Total 220 - 11 - 66 - 9 ------55 - 220 - Babina Sukhchenpur 63 10200 - 30 24200 ------13 11000 63 19000 Belpur Bela ------Babina Pasua 92 10400 - - 27 24500 ------18 12000 92 23000 7. Sukhchenpur Rathgaon (E.K.) ------(2C4B5a1d) Sarai Pratham 106 10200 2 2200 50 24300 14 12500 106 23500 Total 261 - 2 - 107 ------61 - 261 -

101

Activities Name of Black Carpentry Stitching Wages Agriculture Micro Dairy Poultry Goatry Piggeries FisheriesSmithy / Sr. Name of watershed knitting No. Village with Av. Av. Av. Av. Av. Av. Av. Av. Av. Av. code No No No No No incom No No No incom No No income income income income income income income income e e 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Babina Sukhchenpur ------Bampur Rampur 102 10100 - - 18 24800 ------4 11000 102 24500 Bamrauliya 101 10500 17 24200 ------5 115 00 101 25000 Bhadsiya 109 10200 3 3600 20 24300 ------16 12000 109 23300 Bhikhra 121 10100 ------11 12500 121 24500 Dondapur 132 10200 ------132 24500 Bhadasiya Indapamau 78 10300 2 3600 18 24 400 2 18100 ------16 12000 78 23300 8. (2C4B5a1c) Marhokh Hariram 42 10400 18 24300 ------5 11500 42 24300 Marhokh Mit 96 10200 3 3400 22 24600 ------17 12500 96 25200 Narayanpur Bhanu ------Nawada Malkhan 76 10400 21 2400 ------13 11000 76 24500 Pusauli - - 10 8500 41 24400 ------16 11500 - - Roopur Sahar 65 10300 - - 16 24300 ------9 12500 65 22200 Total 922 - 18 - 191 - 2 ------112 - 922 - Asjana 184 10200 12 8400 41 24800 5 18700 ------22 11500 184 24500 Barka Purwa 69 10300 1 2300 6 24100 1 18100 ------6 12000 69 25300 Bhikhra ------Indpamau Indapamau ------9. (2C4B5a1b) Rawatpur ALD) 92 10200 4 3100 18 24300 ------13 12500 92 24200 Rooppur Sahar ------Vimtamau 82 10400 21 24600 3 18500 ------9 11500 82 24200 Nawada Malkhan 73 10300 ------Total 500 - 17 - 86 - 9 ------50 - 427 - Asjana ------Asjana Hathnapur 76 10200 2 3200 16 24200 2 18200 ------11 11500 76 25500 10. (2C4B5a1c) Vimatamau ------(L) Total 76 - 2 - 16 - 2 ------11 - 76 -

102

Activities Name of Black Carpentry Stitching Wages Agriculture Micro Dairy Poultry Goatry Piggeries FisheriesSmithy / Sr. Name of watershed knitting No. Village with Av. Av. Av. Av. Av. Av. Av. Av. Av. Av. code No No No No No incom No No No incom No No income income income income income income income income e e 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Pasua ------Purwa Bhadauria 45 10400 - - 19 24500 ------6 120005 22500 4 Ruru (ALD) Sarai Pratham 76 10100 ------Sarai Pratham Malikpur Mishripur 11. 46 10300 - - 15 24300 ------17 1250046 24500 (2C4B5a1d) L (ALD) Kariapur Ruru (ALD) 66 10400 20 24400 ------10 11500 66 25000 Shivpur (ALD) 173 10300 5 2400 31 24700 7 18600 24 11000 173 25500 Udelapur (ALD) 50 10400 - - 14 24600 ------11 10500 50 23500 Total 456 - 5 - 99 - 7 ------68 - 380 - 12 Grand Total 4725 10100 7500 1076 23150 55 18400 ------675 118004576 22600 1

103 Table 3.16: Ground Water Status in IWMP-I, Auraiya

Name of micro Depth of Ground Water Table S. Name of No. of watershed (GBL in Meter) Remark N. village Observation well with code Before Monsoon After Monsoon 1 2 3 4 5 6 7 Bhatura (E.K.) 1 Sabhad (2C4B5a4d) Gura 10.50 13.30 14 - Sabhad Badin (E.K.) Bhatoli Bidhuna Chakarpur Gura 2. Mau (2C4B5a4c) Jagatpur, (E.K.) 10.55 13.10 13 - Marha Machhi Jhil Mau Narayanpur Sahar Rajpur Bidhuna Sabhad Chakarpur Khizarpur Marha Machhi Jhil Marha Macchi Jhil Mau 3. 10.52 12.70 15 - (2C4B5a4b) Narayanpur Sahar Rajpur Bidhuna Rathgaon (E.K.) Sanwaliya Banthara Belpur Bela Belpur Bela 4. 10.53 12.95 12 - (2C4B5a4a) Rathgaon (E.K.) Sanwaliya Banthara Bashai Belpur Bela Marha Machhi Jhil Banthara 5. Narainpur Bhanu 10.55 12.05 13 - (2C4B5a2d) Rathgaon (E.K.) Sanwaliya Tajpur Bidhuna Kiratpur

104 Name of micro Depth of Ground Water Table S. Name of No. of watershed (GBL in Meter) Remark N. village Observation well with code Before Monsoon After Monsoon 1 2 3 4 5 6 7 Bashai Dondapur Dondapur Narainpur Bhanu 6. 10.54 12.95 14 - (2C4B5a2c) Palia Pusauli Tajpur Bidhuna Babina Sukhchenpur Babina Belpur Bela 7. Sukhchenpur Pasua 10.50 13.00 11 - (2C4B5a1d) Rathgaon (E.K.) Sarai Pratham Babina Sukhchenpur Bampur Rampur Bamrauliya Bhadsiya Bhikhra Bhadasiya Dondapur 8 Indapamau 10.52 12.90 16 - (2C4B5a1c) Marhokh Hariram Marhokh Mit Narayanpur Bhanu Nawada Malkhan Pusauli Roopur Sahar Asjana Barka Purwa Bhikhra Indpamau Indapamau 9. 10.54 12.95 15 - (2C4B5a1b) Rawatpur ALD) Rooppur Sahar Vimtamau Nawada Malkhan Asjana Asjana (2C4B5a1c) 10. Hathnapur 10.50 13.05 10 - (L) Vimatamau

105 Name of micro Depth of Ground Water Table S. Name of No. of watershed (GBL in Meter) Remark N. village Observation well with code Before Monsoon After Monsoon 1 2 3 4 5 6 7 Pasua Purwa Bhadauria Ruru (ALD) Sarai Pratham Sarai Pratham 11. 10.5 12.95 16 - (2C4B5a1d) L Malikpur Mishripur (ALD) Kariapur Ruru (ALD) Shivpur (ALD) Udelapur (ALD)

10.52 12.90 - - Average of IWMP-I

Depth of water table in open shallow dug wells in the project area was about 10 to 11 during pre monsoon, however it was in the range of 12-13 m. during post monsoon season.

Table 3.17: Irrigation Status in IWMP-I Auraiya

Name of micro Name of Net Net Gross Cultivated Area Gross Irrigated Area S. watershed village Cultivated Irrigated Rainfed N. Area with code Area Area Kharif Rabi Zaid Total Kharif Rabi Zaid Total 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Bhatura (E.K.) Sabhad 1 Gura 245.376 392.602 - 637.978 506.947 6.871 9.324 - 16.195 16.195 490.752 (2C4B5a4d) Sabhad Badin (E.K.) Bhatoli Bidhuna Chakarpur Gura Mau 2 Jagatpur, (E.K.) 448.752 709.028 - 1157.78 886.26 12.565 16.155 - 28.72 28.72 897.504 (2C4B5a4c) Marha Machhi Jhil Mau Narayanpur Sahar Rajpur Bidhuna Sabhad

106 Name of micro Name of Net Net Gross Cultivated Area Gross Irrigated Area S. watershed village Cultivated Irrigated Rainfed N. Area with code Area Area Kharif Rabi Zaid Total Kharif Rabi Zaid Total 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Chakarpur Khizarpur Marha Machhi Jhil Marha Macchi Mau 3 Jhil Narayanpur Sahar 258.242 418.352 - 676.594 534.561 7.747 10.33 - 18.077 18.077 516.484 (2C4B5a4b) Rajpur Bidhuna Rathgaon (E.K.) Sanwaliya Banthara Belpur Bela Belpur Bela 4 145.136 229.314 - 374.45 300.692 4.935 5.486 - 10.421 10.421 290.271 (2C4B5a4a) Rathgaon (E.K.) Sanwaliya Banthara Bashai Belpur Bela Marha Machhi Jhil Banthara 5 Narainpur Bhanu 353.577 547.698 - 901.275 715.473 9.706 12.479 - 22.185 22.185 693.288 (2C4B5a2d) Rathgaon (E.K.) Sanwaliya Tajpur Bidhuna Kiratpur Bashai Dondapur Dondapur Narainpur Bhanu 6 213.426 370.281 - 583.707 477.662 6.48 8.331 - 14.811 14.811 462.851 (2C4B5a2c) Palia Pusauli Tajpur Bidhuna

107 Name of micro Name of Net Net Gross Cultivated Area Gross Irrigated Area S. watershed village Cultivated Irrigated Rainfed N. Area with code Area Area Kharif Rabi Zaid Total Kharif Rabi Zaid Total 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Babina Sukhchenpur Babina Belpur Bela 7 Sukhchenpur Pasua 142.786 236.034 - 378.82 320.811 4.371 5.537 - 9.908 9.908 310.903 (2C4B5a1d) Rathgaon (E.K.) Sarai Pratham Babina Sukhchenpur Bampur Rampur Bamrauliya Bhadsiya Bhikhra Dondapur Bhadasiya 8 Indapamau 372.923 604.935 - 977.858 770.459 10.442 14.171 - 24.613 24.613 745.846 (2C4B5a1c) Marhokh Hariram Marhokh Mit Narayanpur Bhanu Nawada Malkhan Pusauli Roopur Sahar Asjana Barka Purwa Bhikhra Indpamau Indapamau 9 333.48 516.568 - 850.048 675.461 9.808 11.77 - 21.578 21.578 653.883 (2C4B5a1b) Rawatpur ALD) Rooppur Sahar Vimtamau Nawada Malkhan Asjana Asjana 10 (2C4B5a1c) Hathnapur 176.767 277.281 - 454.048 358.039 5.199 6.239 - 11.438 11.438 346.601 (L) Vimatamau

108 Name of micro Name of Net Net Gross Cultivated Area Gross Irrigated Area S. watershed village Cultivated Irrigated Rainfed N. Area with code Area Area Kharif Rabi Zaid Total Kharif Rabi Zaid Total 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Pasua Purwa Bhadauria Ruru (ALD) Sarai Sarai Pratham Pratham 11 Malikpur Mishripur (ALD) 391.995 614.894 - 1006.889 793.233 11.5 13.066 - 24.616 24.616 768.617 (2C4B5a1d) Kariapur Ruru (ALD) L Shivpur (ALD) Udelapur (ALD) Total 3082.46 4916.987 0 7999.447 6339.598 89.6 73 112.888 0 202.56 1 202.56 1 6177.00

Table 3.18: Source wise Area Irrigated in IWMP-I, Auraiya (area in ha) Total Name of State Tube Lift Others Tanks Open well Bore wells Irrigated S. micro Name of Canal wells irrigation (Specify) Area Rem N. watershed village Area with code No. Area No. Area No. Area No. Area No. Area No. Area

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Bhatura (E.K.) Sabhad 1 Gura ------14 20.612 ------(2C4B5a4d) Sabhad Badin (E.K.) Bhatoli Bidhuna Chakarpur Gura Mau Jagatpur, (E.K.) 2 ------13 37.695 ------(2C4B5a4c) Marha Machhi Jhil Mau Narayanpur Sahar Rajpur Bidhuna Sabhad

109

Total Name of State Tube Lift Others Tanks Open well Bore wells Irrigated S. micro Name of Canal wells irrigation (Specify) Area Rem N. watershed village Area with code No. Area No. Area No. Area No. Area No. Area No. Area

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Chakarpur Khizarpur Marha Machhi Jhil Marha Macchi Mau ------15 21.693 - - - - - Jhil Narayanpur Sahar - (2C4B5a4b) Rajpur Bidhuna Rathgaon (E.K.) Sanwaliya Banthara Belpur Bela Belpur Bela ------12 12.188 ------(2C4B5a4a) Rathgaon (E.K.) Sanwaliya Banthara Bashai Belpur Bela Marha Machhi Jhil Banthara Narainpur Bhanu ------13 29.118 ------(2C4B5a2d) Rathgaon (E.K.) Sanwaliya Tajpur Bidhuna Kiratpur Bashai Dondapur Dondapur Narainpur Bhanu ------14 19.44 ------(2C4B5a2c) Palia Pusauli Tajpur Bidhuna Babina Sukhchenpur Babina Belpur Bela 7 Sukhchenpur Pasua ------11 12.239 ------(2C4B5a1d) Rathgaon (E.K.) Sarai Pratham

110 Total Name of State Tube Lift Others Tanks Open well Bore wells Irrigated S. micro Name of Canal wells irrigation (Specify) Area Rem N. watershed village Area with code No. Area No. Area No. Area No. Area No. Area No. Area

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Babina Sukhchenpur Bampur Rampur Bamrauliya Bhadsiya Bhikhra Dondapur Bhadasiya 8 Indapamau ------16 31.326 ------(2C4B5a1c) Marhokh Hariram Marhokh Mit Narayanpur Bhanu Nawada Malkhan Pusauli Roopur Sahar Asjana Barka Purwa Bhikhra Indpamau Indapamau 9 ------15 27.463 ------(2C4B5a1b) Rawatpur ALD) Rooppur Sahar Vimtamau Nawada Malkhan Asjana Asjana 10 (2C4B5a1c) Hathnapur ------10 14.557 ------(L) Vimatamau Pasua Purwa Bhadauria Ruru (ALD) Sarai Pratham Sarai Pratham 11 Malikpur Mishripur ------16 32.282 ------(2C4B5a1d) L (ALD) Kariapur Ruru (ALD) Shivpur (ALD) Udelapur (ALD)

Total 149 258.613

111

CHAPTER – 4

INSTITUTIONAL BUILDING AND PROJECT MANAGEMENT

4.1 Project Implementing Agency

The Project Implementing Agency (PIA) is Soil Conservation Officer, Department of Land Development and Water Resources, IWMP-I, Auraiya Uttar Pradesh. The PIA was given responsibility to develop the micro-watershed by District Watershed Development Unit (DWDU) and State Level Nodal Agency (SLNA) considering its vast experiences in handling land and water management issues in the region. The PIA has well experienced trained and sufficient staff to handle the watershed management programme efficiently. Most of the staff of PIA has exposure of several watershed projects. In addition the PIA has access for technical backstopping from the CSA Kanpur and KVK located at Auraiya. Details of PIA are presented in subsequent section.

Table 4.1: Details of Project Implementing Agency (PIA), IWMP-I, Auraiya

Sr. No. Particulars of PIA 1 Date of selection of PIA 16-03-2010

2 Type of organization State Govt. Agency

(i) Name of organization Department of Land Development and Water Resources, Uttar Pradesh Bhoomi Sanrakshan Adhikari, Land Development and Water Resources Ajad Nagar Gadiya Road , Ajeetmal (ii) Designation & Address District –Auraiya Pin- (206121) 3 Telephone BSA - 9412898776

(i) Fax 05683-292301

(ii) E-mail [email protected]

112 Table 4.2 : Details of Staff of PIA, IWMP-I, Auraiya

Field of Sr. Designation Name M/F Qualification Experience & Remarks No. Period 1 2 3 4 5 6 7 Bhoomi Sanrakshan Adhikari 1. Shri Sudarshan Yadav M B.Sc. Ag. Engineering 31 year /Deputy Director

2. J.E./T.O. Shri Suresh Chandra Katiyar M Diploma in Civil Engg.

3. Junior Engineer " Shivgopal Goswami M Diploma in Ag. Engg. 28 year 4. Accountant " B.N.singh M M.Com. 26 year 5. Accountant " Vibhuti Prasad M M.Com. 26 year 6. Draughtsman " Chandra Shekhar Kushwah M Diploma in (Civil) 7 year 7. Trecer " Anil Kumar Shrivastav M Intermediate 24 year 8. Jr. Clerk " Anil Kumar M B.Sc. (Math.) 1 year 9. A.S.C.I. " Balkishun Ram M M.Sc. (Ag) Agronomy 7 year 10. A.S.C.I. " Rohit Pratap Singh M B.Sc. (Ag.) - 11. A.S.C.I. Km. Akanksha F B.Sc. (Ag) - 12. A.S.C.I. Km. Kumudini singh F M.Sc. (Ag) Agronomy - 13. Irrigation Sup. Shri Bateshwar Pandey M B.A. 22 year 14. Munshi " Vijay Bahadur Yadav M Intermediate(Ag) 19 year 15. Irrigation Sup. " Divjendra Nath Pandey M Intermediate 28 year 16. Irrigation Sup. " Sukhveer Singh M Intermediate 22 year 17. Irrigation Sup. " Ramsuchit Vishwakarma M Intermediate 20 year 18. Irrigation Sup. " Chandresh Kumar M M.A. 8 year 19. IVth Class " Narmeshwar Upadhyay M Intermediate 22 year 20. IVth Class " Jameer Ahamad Rijvee M High School 22 year 21. IVth Class " Ramvilas M High School 28 year 22. Dak Rannar " Ram Achal Yadav M High School 20 year

113 Table 4.3 : Details of Watershed Development Team (WDT) in the project area

Project : IWMP-I PIA-BSA, LDWR, Auraiya District : Auraiya

Date of Sr. Name of WDT Description of M/F Age Qualification/ Experience Role/ Function Appointment of No. member Professional Training WDT member

1 2 3 4 5 6 7 8

1. Shri Birbal singh M 25 M.Sc. (Ag.) Horticulture Soil science Soil Science Expert 19-10-2011

2. Km. Vinita Shahu F 21 B.A. M.S.W. Social work 16-11-2011

M.Sc. (Ag.) Shri Kailash Naraya 3. M 65 Agronomy Agriculture 01.08.2011 Saxen Plant Production

Shri Ram Lakhan 4. M 64 B.Sc. (Ag.) Soil Conservation Water Management 01.08.2011 Verma

114

Table 4.4 : Details of Watershed Committee (WC)

Wateshed Committee/Gram Panchayat-Badin (EK) Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F √ - - - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - - √ - 8 of Watershed

th Member M √ - - √ - - - √ - 8 programme

Member M - - √ √ - - - √ - 8th under the 1. Badin (EK) Under Process Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ - - - - - √ - - - 5th common guide

Member F - - √ ------5th lines)

Member F √ ------B.sc. Agg.

115 Wateshed Committee/Gram Panchayat-Gura Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M - - √ √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 2. Gura Under Process Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

116 Wateshed Committee/Gram Panchayat- Sabhad Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M - - √ √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 3. Sabhad 12.01.11 Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M - - √ - - - - - √ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

117 Wateshed Committee/Gram Panchayat- Bhatoli Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 4. Bhatoli Under Process Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M √ ------B.A. (Eco.)

118

Wateshed Committee/Gram Panchayat- Marha Macchi Jhil Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

th Marha Member M - - √ √ - - √ - - 8 under the 5. 29.07.11 Macchi Jhil Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

119 Wateshed Committee/Gram Panchayat- Harchandpur(EK) Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the Harchandpur 6. Under Process (EK) th Member M - - √ √ - - √ - - 8 supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

120 Wateshed Committee/Gram Panchayat- Mau Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President M - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M - - √ √ - - √ - - 8 of Watershed

th Member M √ - - √ - - √ - - 8 programme

Member M √ - - √ - - √ - - 8th under the 7. Mau Under Process Member M √ - - √ - - √ - - 8th supervision of

Member M √ ------√ - 8th PIA (as per

Member F √ - - - - - √ - √ - 5th common guide

Member F - - √ ------5th lines)

Member M - √ ------B.A. (Eco.)

121 Wateshed Committee/Gram Panchayat- Rathgaon Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M √ - - √ ------12 Implementation

th Member M - - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

th Rathgaon Member M - - √ √ - - √ - - 8 under the 8 Under Process (E.K.) Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------√ - 5th lines)

Member M - - √ ------B.sc. Agg.

122 Wateshed Committee/Gram Panchayat- Sanwaliya Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President M - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 9 Sanwaliya Under Process Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member F √ ------5th lines)

Member F - - √ ------B.sc. Agg.

123 Wateshed Committee/Gram Panchayat- Banthara Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President M - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M - - √ √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 10 Banthara 12.01.11 Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member F √ ------√ - 5th common guide

Member F √ ------5th lines)

Member F - - √ ------B.sc. Agg.

124 Wateshed Committee/Gram Panchayat- Belpur Bela Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F √ - - - - √ - √ - - 10 th

th Secretary M √ - - √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M √ - - √ - - √ - - 8 programme

Member M √ - - √ - - √ - - 8th under the 11 Belpur Bela 11.01.11 Member M √ - - √ - - √ - - 8th supervision of

Member M √ ------√ - 8th PIA (as per

Member F √ ------√ - 5th common guide

Member F √ ------5th lines)

Member F - - √ ------B.sc. Agg.

125 Wateshed Committee/Gram Panchayat- Bashai Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President M - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 12 Bashai Under Process Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

126 Wateshed Committee/Gram Panchayat- Pusauli Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President M √ - - - - √ - √ - - 10 th

Secretary M √ - - √ ------12 th Implementation Member M √ - - √ - - √ - - 8th of Watershed Member F √ - - √ - - √ - - 8th programme Member M - - √ √ - - √ - - 8th under the 13 Under Process th Pusauli Member M - - √ √ - - √ - - 8 supervision of Member F √ ------√ - 8th PIA (as per

th Member F - - √ - - - - - √ - 5 common guide

th Member F √ ------5 lines)

Member B.sc. M √ ------(Eco.)

127 Wateshed Committee/Gram Panchayat- Tajpur Bidhuna Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President M √ - - - - √ - √ - - 10 th

Secretary M √ - - √ ------12 th Implementation Member M - - √ √ - - √ - - 8th of Watershed Member M - - √ √ - - √ - - 8th programme Member M - - √ √ - - √ - - 8th Tajpur under the 14 Under Process th Member M - - √ √ - - √ - - 8 Bidhuna supervision of Member M √ ------√ - 8th PIA (as per

th Member M - - √ - - - - - √ - 5 common guide

th Member M - - √ ------5 lines)

Member B.A. M √ ------(Eco.).

128 Wateshed Committee/Gram Panchayat- Dondapur Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President M - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M - - √ √ - - √ - - 8 of Watershed

th Member M √ - - √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 15 Dondapur Under Process Member M √ - - √ - - √ - - 8th supervision of

Member F - - √ - - - - - √ - 8th PIA (as per

Member M - - √ - - - - - √ - 5th common guide

Member M - - √ ------5th lines)

Member M √ ------B.A. (Eco.)

129 Wateshed Committee/Gram Panchayat- Alipur Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President M - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 16 Alipur Under Process Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member F √ - - - - - √ - √ - 5th common guide

Member M √ ------5th lines)

Member M √ ------B.A. (Eco.)

130 Wateshed Committee/Gram Panchayat- Babina Sukhchenpur Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the Babina 17 Under Process Sukhchenpur th Member M - - √ √ - - √ - - 8 supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

131

Wateshed Committee/Gram Panchayat- Pasua Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M - - √ √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 18 Pasua 15.12.2011 Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M - - √ - - - - - √ - 5th common guide

Member M √ ------5th lines)

Member M √ ------B.sc. Agg.

132 Wateshed Committee/Gram Panchayat- Sarai Pratham Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

th Sarai Member M - - √ √ - - √ - - 8 under the 19 27-01-11 Pratham Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

133 Wateshed Committee/Gram Panchayat- Bamrauliya Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 20 Bamrauliya Under Process Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

134 Wateshed Committee/Gram Panchayat- Bhadsiya Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M - - √ √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 21 Bhadsiya 20.12.11 Member M - - √ √ - - - √ - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M √ ------B.sc. Agg.

135 Wateshed Committee/Gram Panchayat- Bhikhra Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President M - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M - - √ √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 22 Bhikhra 24.12.11 Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M - - √ - - - - - √ - 5th common guide

Member M - √ ------5th lines)

Member M √ ------B.sc. Agg.

136 Wateshed Committee/Gram Panchayat- Indpamau Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 23 Indpamau Under Process Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

137 Wateshed Committee/Gram Panchayat- Marhokh Mit Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

th Marhokh Member M - - √ √ - - √ - - 8 under the 24 Under Process Mit Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

138

Wateshed Committee/Gram Panchayat- Rooppur Sahar Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

th Rooppur Member M - - √ √ - - √ - - 8 under the 25 Under Process Sahar Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

139 Wateshed Committee/Gram Panchayat- Asjana Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 26 Asjana 12.01.11 Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

140 Wateshed Committee/Gram Panchayat- Rawatpur Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

Member M - - √ √ - - √ - - 8th under the 27 Rawatpur Under Process Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M - - √ ------B.sc. Agg.

141 Wateshed Committee/Gram Panchayat- Udelapur (ALD) Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President M - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

th Udelapur Member M - - √ √ - - √ - - 8 under the 28 19.12.11 (ALD) Member M - - √ √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M √ ------B.sc. Agg.

142

Wateshed Committee/Gram Panchayat- Shahoopur (ALD) Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President M - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M - - √ √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

th Shahoopur Member M - - √ √ - - √ - - 8 under the 29 14.12.11 (ALD) Member M √ - - √ - - √ - - 8th supervision of

Member M √ ------√ - 8th PIA (as per

Member M - √ - - - - - √ - 5th common guide

Member M √ ------5th lines)

Member M √ ------B.sc. Agg.

143 Wateshed Committee/Gram Panchayat- Ruru Kala (ALD) Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President F - - √ - - √ - √ - - 10 th

th Secretary M - - √ √ ------12 Implementation

th Member M √ - - √ - - √ - - 8 of Watershed

th Member M - - √ √ - - √ - - 8 programme

th Ruru Kala Member M - - √ √ - - √ - - 8 under the 30 17.12.11 (ALD) Member M √ - - √ - - √ - - 8th supervision of

Member M - - √ - - - - - √ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member M √ ------5th lines)

Member M √ ------B.sc. Agg.

144

Wateshed Committee/Gram Panchayat- Shivpur (ALD) Name of Project – IWMP- I District : Auraiya

Date of constitution/ Educat- Name of S. Registration as a OBC/ Land ional Function(s) Gram Designation M/F SC ST SF MF LF UG SHG GP No. Society (dd/mm/ Gen. less Qualifi- assigned Panchayat yyyy) cation

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

President M - - √ - - √ - √ - - 10 th

th Secretary F - - √ √ ------12 Implementation

th Member F - - √ √ - - √ - - 8 of Watershed

th Member F - - √ √ - - √ - - 8 programme

th Shivpur Member M √ - - √ - - √ - - 8 under the 31. 28.11.10 (ALD) Member M - - √ √ - - √ - - 8th supervision of

Member M √ ------√ - 8th PIA (as per

Member M √ ------√ - 5th common guide

Member F √ ------5th lines)

Member M √ ------B.sc. Agg.

The project IWMP-I spread over in 45 villages of 31 gram panchayat. Gram panchayat wise watershed committee was constituted, except Gata and Sujwan, and detailes are given in above Table. The watershed committee for remaining two gram panchyats will be constituted by Dec., 2011.

145 Table : 4.5 Village wise details of Self Help Groups (SHGs) in the project Area IWMP-I

Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both No. Men Women Total Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless 8 2 10 2 1 3 6 1 7 (ii) SF 9 9 18 4 1 5 8 7 15 14.12.10 1 Sabhad (2C4B5a4d) Bhatura (E.K.) 1 - 1 2 (iii) MF 1 1 2 - - - 2 1 3 (iv) LF ------

Total 18 12 30 6 2 8 16 9 25 (i) Landless 11 3 14 3 2 5 8 2 10 (ii) SF 10 6 16 1 1 2 5 3 8 11.01. 11 Gura 1 1 - 2 (iii) MF 3 1 4 ------(iv) LF ------

Total 24 10 34 4 3 7 13 5 18 (i) Landless 11 6 17 6 2 3 6 3 9 (ii) SF 16 4 20 3 1 4 10 2 12 28.12.10 Sabhad 3 1 1 5 (iii) MF - - - 1 1 2 - - - (iv) LF ------Total 27 10 37 10 4 14 16 5 21 (i) Landless 8 4 12 3 2 5 8 4 12 (ii) SF 12 5 17 6 1 7 12 5 17 14.12.10 Badin (E.K.) 1 1 1 3 (iii) MF 2 1 3 1 - 1 2 - 2 (iv) LF ------Total 22 10 32 10 3 13 22 9 31 2. Mau (2C4B5a4c) (i) Landless 7 5 12 3 7 5 5 4 9 (ii) SF 16 4 18 12 1 13 10 2 12 16.01.11 Bhatoli Bidhuna 1 1 1 3 (iii) MF 1 1 2 1 1 2 - - (iv) LF ------Total 24 10 34 16 9 25 15 6 21

146 Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both Tota No. Men Women l Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless 8 3 11 3 1 4 6 1 7 (ii) SF 10 6 16 4 2 6 5 1 6 Chakarpur 1 - 1 2 (iii) MF 3 1 4 ------18.01.11 (iv) LF ------Total 21 10 31 7 3 10 11 2 13 (i) Landless ------(ii) SF ------Gura - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless 10 4 14 3 2 5 8 2 10 (ii) SF 13 4 17 4 1 5 10 2 12 Jagatpur, (E.K.) 1 - 1 2 (iii) MF 2 1 3 10.1.11 (iv) LF ------Total 25 9 34 7 3 10 18 4 22 Mau (2C4B5a4c) (i) Landless ------(ii) SF ------Marha Machhi 1 1 - 2 (iii) MF ------Jhil (iv) LF ------Total ------(i) Landless 11 2 13 5 1 6 10 1 11 (ii) SF 12 6 18 3 4 7 11 3 14

Mau 1 1 - 2 (iii) MF 1 1 2 1 1 2 1 1 2 25.12.10 (iv) LF ------Total 24 9 33 9 6 15 22 5 27 (i) Landless 10 3 13 4 1 5 10 1 11 (ii) SF 14 2 16 3 1 4 6 7 13 Narayanpur 1 1 1 3 (iii) MF 3 1 4 1 1 1 1 3 14.11.10 Sahar (iv) LF ------Total 27 6 33 8 2 10 17 9 27

147 Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both Tota No. Men Women l Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless 11 2 13 4 1 5 10 1 11 (ii) SF 8 8 16 3 1 4 6 7 13 16.01.11 Rajpur Bidhuna 1 - 1 2 (iii) MF 2 2 4 1 1 1 1 2 (iv) LF ------Total 21 12 33 8 2 10 17 9 26 Mau (2C4B5a4c) (i) Landless ------(ii) SF ------Sabhad - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Chakarpur - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless 9 2 11 5 1 8 2 10 12 (ii) SF 12 4 16 7 1 1 3 3 29.12.10 Khizarpur 2 - 1 3 (iii) MF 3 1 4 1 1 2 - (iv) LF ------Total 24 7 31 13 3 16 5 10 15 3. Marha Macchi Jhil (2C4B5a4b) (i) Landless 12 7 19 6 2 8 7 3 10 (ii) SF 16 2 18 6 1 7 8 4 12 26.12.10 Marha Machhi 1 1 - 2 (iii) MF 1 1 2 - - - 9 1 10 Jhil (iv) LF ------Total 29 10 39 12 3 15 24 8 32 (i) Landless ------(ii) SF ------

Mau - - - - (iii) MF ------(iv) LF ------Total ------

148 Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both Tota No. Men Women l Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless ------(ii) SF ------Narayanpur - - - - (iii) MF ------Sahar (iv) LF ------Total ------(i) Landless ------(ii) SF ------Rajpur Bidhuna - - - - (iii) MF ------(iv) LF ------Total ------Marha Macchi Jhil (2C4B5a4b) (i) Landless 14 7 21 6 2 8 9 1 10 (ii) SF 16 2 18 5 1 6 11 3 14 Rathgaon (E.K.) 1 1 1 3 (iii) MF 1 1 2 - - - - - 15.11.11 (iv) LF ------Total 31 10 41 11 3 14 20 4 24 (i) Landless 12 6 18 5 2 7 7 3 10 (ii) SF 13 3 16 6 1 7 9 1 10 Sanwaliya 1 1 1 3 (iii) MF 3 1 4 1 - 1 2 - 2 16.12.11 (iv) LF ------Total 28 10 38 12 3 15 18 4 22 (i) Landless 10 3 13 - - - 5 2 7 (ii) SF 5 8 13 - - - 2 3 5 Banthara 1 1 1 3 (iii) MF 5 2 7 - - - 2 1 3 11.01.2011 (iv) LF - - - Total 20 13 13 - - - 9 6 15 4. Belpur Bela (2C4B5a4a) (i) Landless 10 2 12 10 2 12 8 1 9 (ii) SF 14 02 26 8 1 9 6 - 6 Belpur Bela - - - - (iii) MF 4 1 5 1 1 2 - - - 15.06.11 (iv) LF ------Total 28 5 33 19 4 23 14 1 15

149

Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both Tota No. Men Women l Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless ------Rathgaon (E.K.) (ii) SF ------(iii) MF ------(iv) LF ------Total ------Belpur Bela (2C4B5a4a) (i) Landless ------(ii) SF ------Sanwaliya - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Banthara - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Banthara - 5. Bashai - - - - (iii) MF ------(2C4B5a2d) (iv) LF ------Total ------(i) Landless ------(ii) SF ------Belpur Bela 1 2 - 3 (iii) MF ------(iv) LF ------Total ------

150 Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both Tota No. Men Women l Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless ------(ii) SF ------Marha Machhi - - - - (iii) MF ------Jhil (iv) LF ------Total ------(i) Landless ------(ii) SF ------Narainpur - - - - (iii) MF ------Bhanu (iv) LF ------Total ------(i) Landless ------(ii) SF ------Rathgaon - - - - (iii) MF ------(E.K.) (iv) LF ------Banthara Total ------

(2C4B5a2d) (i) Landless ------(ii) SF ------Sanwaliya - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Tajpur Bidhuna - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless 12 4 16 7 2 9 7 2 9 (ii) SF 12 5 17 5 3 8 5 2 7 Kiratpur 1 1 1 3 (iii) MF 2 1 3 1 1 2 1 1 20.11.11 (iv) LF Total 26 10 36 13 6 19 13 4 17

151 Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both Tota No. Men Women l Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless 9 2 11 4 1 5 4 1 5 (ii) SF 10 7 17 6 3 9 5 3 8 18.11.11 Bashai 1 - 1 2 (iii) MF 2 1 3 1 1 (iv) LF Total 21 10 31 10 4 14 10 4 14 (i) Landless 13 3 16 7 1 8 7 2 9 (ii) SF 11 5 16 5 2 7 6 3 9 16.11.10

Dondapur 1 - 1 2 (iii) MF 2 2 4 1 1 2 - - -

(iv) LF Total 26 10 36 13 4 17 13 5 18 (i) Landless 8 4 12 3 2 5 4 2 6 (ii) SF 13 5 18 6 2 8 7 3 10 14.10.11 Narainpur 1 1 - 2 (iii) MF 2 1 3 1 1 12 1 1 2 Bhanu (iv) LF Total 23 10 33 10 5 15 12 6 18 6. Dondapur (2C4B5a2c) (i) Landless 15 4 19 7 2 9 13 3 16 (ii) SF 12 6 18 6 1 7 11 4 15 01.01.12 Palia 1 1 - 2 (iii) MF 2 2 1 1 2 2 2 4 (iv) LF Total 29 10 39 14 4 18 26 9 35 (i) Landless 13 6 19 10 5 15 13 6 19 (ii) SF 17 4 21 16 3 19 17 4 21 16.12.10 Pusauli 1 1 1 3 (iii) MF 1 1 1 1 2 1 1 (iv) LF Total 31 10 41 27 9 36 31 10 41 (i) Landless 13 4 17 12 2 14 12 3 15 (ii) SF 13 5 18 11 5 16 12 4 16 10.11.11 Tajpur Bidhuna 2 1 - 3 (iii) MF 1 1 2 1 1 2 1 1 2 (iv) LF 27 Total 27 10 37 24 8 32 25 8 33

152 Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both Tota No. Men Women l Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless 2 3 5 2 2 4 1 1 2 (ii) SF 4 1 5 1 2 3 1 1 2 04.03.11 Babina 1 1 1 3 (iii) MF 3 2 5 1 2 3 - - - Sukhchenpur (iv) LF ------Total 9 6 15 4 6 10 2 2 4 (i) Landless ------(ii) SF ------Belpur Bela - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless 12 6 18 10 3 13 11 5 16 (ii) SF 14 4 18 6 1 7 12 3 15 Babina Sukhchenpur 02.02.12 7. Pasua 1 1 1 3 (iii) MF 2 - 2 10 1 11 - 1 2 (2C4B5a1d) (iv) LF ------Total 28 10 38 26 5 31 23 9 33 (i) Landless ------(ii) SF ------Rathgaon (E.K.) - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless 14 3 17 10 2 12 13 3 16 (ii) SF 10 6 16 8 3 11 10 6 16 27.11.10 Sarai Pratham 3 1 - 4 (iii) MF 3 1 4 1 1 2 3 1 4 (iv) LF ------Total 27 10 37 19 6 25 26 10 36

153 Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both Tota No. Men Women l Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless ------(ii) SF ------Babina - - - - (iii) MF ------Sukhchenpur (iv) LF ------Total ------(i) Landless 9 3 12 4 2 6 5 2 7 (ii) SF 10 6 16 5 2 7 7 2 9 16.11.11 Bampur Rampur 1 1 1 3 (iii) MF 2 1 3 1 1 2 (iv) LF ------Total 21 10 31 10 5 15 12 4 16 (i) Landless 5 4 9 3 2 5 3 2 5 (ii) SF 13 6 19 6 3 9 7 2 9 18.11.11 Bamrauliya 1 1 1 3 (iii) MF 1 1 (iv) LF ------Total 19 10 29 9 5 14 10 4 14 8. Bhadasiya (2C4B5a1c) (i) Landless 10 6 16 4 1 5 5 3 8 (ii) SF 15 3 18 7 3 10 9 2 11 10.01.2011 Bhadsiya 1 1 1 3 (iii) MF 1 1 2 ------(iv) LF ------Total 26 10 36 11 4 15 14 5 19 (i) Landless 2 6 8 0 3 3 1 2 3 (ii) SF 1 10 11 - - - - 2 2 12.01.11 Bhikhra 1 1 1 3 (iii) MF 3 4 7 - - - - 1 1 (iv) LF ------Total 6 20 26 0 3 3 1 5 6 (i) Landless ------(ii) SF ------Dondapur - - - - (iii) MF ------(iv) LF ------Total ------

154 Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both No. Men Women Total Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless ------(ii) SF ------Indapamau - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless 9 3 12 6 2 8 8 2 10 (ii) SF 6 7 13 4 3 7 5 3 8 22.11.11 Marhokh 1 1 1 3 (iii) MF 4 2 6 2 2 4 1 1 2 Hariram (iv) LF Total 19 12 31 12 7 19 14 6 20 (i) Landless 7 3 10 10 10 4 4 (ii) SF 6 1 7 4 1 5 3 1 4 24.11.2011 Marhokh Mit 1 1 1 3 (iii) MF 7 6 13 3 2 5 4 2 6 (iv) LF Total 20 10 30 7 13 20 7 7 14 Bhadasiya (2C4B5a1c) (i) Landless ------(ii) SF ------Narayanpur - - - - (iii) MF ------Bhanu (iv) LF ------Total ------(i) Landless 10 4 14 6 2 8 6 2 8 (ii) SF 6 6 12 3 3 6 3 3 6 28.11.11 Nawada 1 1 1 3 (iii) MF 5 3 8 2 1 3 3 2 5 Malkhan (iv) LF Total 21 13 34 11 6 17 12 7 19 (i) Landless ------(ii) SF ------Pusauli - - - - (iii) MF ------(iv) LF ------Total ------

155 Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both Tota No. Men Women l Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless 10 2 12 6 1 7 5 1 6 (ii) SF 9 9 18 5 3 8 4 4 8 Bhadasiya 18.11.11 Roopur Sahar 1 1 1 3 (iii) MF 1 1 2 ------(2C4B5a1c) (iv) LF ------Total 20 12 32 11 4 15 9 5 14 (i) Landless 10 - 10 - - 10 - 10 - (ii) SF 10 - 10 - - 10 - - - Asjana 1 1 - 2 (iii) MF ------09.11.11 (iv) LF ------Total 20 - 20 - - 20 - - - (i) Landless 20 20 10 10 10 10 20 (ii) SF 4 2 6 ------Barka Purwa 1 1 - 2 (iii) MF 1 1 2 ------28.12.2011 (iv) LF ------Total 25 3 28 10 10 10 10 20 (i) Landless 11 4 15 ------(ii) SF 6 7 14 4 3 7 4 3 7 Indpamau 9. Bhikhra 1 1 1 3 (iii) MF 4 2 6 2 2 4 2 2 4 21.11.2011 (2C4B5a1b) (iv) LF ------Total 21 13 34 6 5 11 6 5 11 (i) Landless 7 3 10 10 10 4 4 (ii) SF 6 1 7 4 1 5 3 1 4 Indapamau 1 1 1 3 (iii) MF 7 6 13 3 2 5 4 2 6 24.11.2011 (iv) LF ------Total 20 10 30 7 13 20 7 7 14 (i) Landless 2 2 1 1 2 1 1 2 (ii) SF 9 9 18 4 3 7 3 1 4 Rawatpur ALD) 1 1 - 2 (iii) MF 1 1 2 1 1 2 - - - 26.11.201 (iv) LF ------Total 12 10 22 6 5 11 4 2 6

156 Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both Tota No. Men Women l Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless ------(ii) SF ------Rooppur Sahar - - - (iii) MF ------(iv) LF ------Total ------(i) Landless 10 3 13 6 3 9 5 2 7 (ii) SF 2 10 12 1 5 6 1 6 7 Indpamau Vimtamau 1 1 1 3 (iii) MF 4 4 8 2 2 4 2 2 4 16.11.2011 (2C4B5a1b) (iv) LF ------Total 16 16 33 9 10 19 8 10 18 (i) Landless ------(ii) SF ------Nawada - - - - (iii) MF ------Malkhan (iv) LF ------Total ------(i) Landless ------(ii) SF ------Asjana - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless 10 4 14 6 3 9 6 2 8 (ii) SF 7 2 9 6 2 8 5 1 6 Asjana (2C4B5a1c) 10. Hathnapur 1 - 1 2 (iii) MF 3 1 4 2 1 3 1 1 2 19.11.2011 (L) (iv) LF ------Total 20 7 27 14 6 20 12 4 16 (i) Landless ------(ii) SF ------Vimatamau - - - - (iii) MF ------(iv) LF ------Total ------

157 Name of Names of Total no. of No. of SC/ST in No. of BPL in Date of MWS villages Constituted/registered SHGs No. of members each category each category formation With With With of SHGs S. only only both No. Men Women Total Categories M F Total M F Total M F Total 1 2 3 4 5 6 7 8 9 10 11 12 12 13 14 15 16 17 (i) Landless ------(ii) SF ------Pasua - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless 12 1 13 7 1 8 7 1 8 Purwa (ii) SF 7 11 18 3 4 7 4 2 6 Bhadauria Ruru 1 1 1 3 (iii) MF 1 1 2 1 1 2 12.11.11 (ALD) (iv) LF ------Total 20 13 33 11 6 17 11 3 14 (i) Landless ------(ii) SF ------Sarai Pratham - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless 4 2 6 2 1 3 2 1 3 (ii) SF 10 5 15 6 3 9 6 3 9 11. Sarai Pratham Malikpur 1 1 1 3 (iii) MF 2 3 5 1 1 2 14.11.11 (2C4B5a1d) L Mishripur (ALD) (iv) LF ------Total 16 10 26 9 5 14 8 4 12 (i) Landless 5 1 6 3 1 4 4 1 5 (ii) SF 2 1 3 1 1 2 1 1 2 Kariapur Ruru 1 1 1 3 (iii) MF 7 10 17 2 4 6 3 6 9 15.11.11 (ALD) (iv) LF ------Total 14 12 26 6 6 12 8 8 16 (i) Landless 10 4 14 6 2 8 6 2 8 (ii) SF 6 6 12 2 2 4 3 3 6 16.11.2011 Shivpur (ALD) 1 1 1 3 (iii) MF 5 3 8 3 1 4 2 1 3 (iv) LF ------Total 21 13 34 11 5 16 11 6 17 (i) Landless 9 5 14 5 2 7 4 3 7 (ii) SF 2 1 3 1 1 2 1 1 2 18.11.11 Udelapur (ALD) 1 1 1 3 (iii) MF 8 9 17 5 4 9 5 4 9 (iv) LF ------Total 19 15 34 11 7 18 10 8 18 Grand Total 53 40 35 128 - 1001 465 1465 473 235 516 612 273 580

158 Table 4.6: Details of Self Help Groups (SHGs) in the project area Project- IWMP I District- Auraiya Total No. of Members Name of Bank and Up to Name of self Date of S. Name of Names of Name of Name of Address date Group Help constitutio No. MWS villages Adhyaksh Sachiv Account Saving activities group n Women Sc/St Other Total No. & Rs. Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Bhatura (E.K.) Jai Durga 11 -01 -2011 Nirmla Devi Jahar Singh Dairy Jai Maa Kali 12.01.2011 Lalmani Veer Pratap Singh 12 8 10 30 Under Prosess 1200 Goatry Rani Laxmi Bai 16.01.2011 Ramkrishna Katheria Veer Bahadur Poultry Gura Jai Santosh 11 -01 -2011 Bada Devi Monu Singh Dairy Sabhad 1 Jai Bhole 18.01.2011 Dashrath Singh Hargovind Tiwari 10 7 17 34 Under Prosess 1100 Goatry (2C4B5a4d) Jai Maa Durgey 20.01.2011 Sanjeet Kumar Suresh Kumar Poultry Jai Durga 11 -01 -2011 Urmila Devi Nagar Singh Goatry Sabhad S.B. Patel SHG 28.12.2011 Gajendra Singh Ram Kumar 10 14 13 37 Under Prosess 1000 Dairy Jai Kashi 28.12.2011 Nahar Singh Ram Awatar Poultry Poultry Badin (E.K.) Jai Santoshi 14-12-2011 Deer Singh Lutvar Singh 5 - 5 10 Under Prosess 1100 Dairy Goatry Rope Making Bhatoli Bidhuna Under Process Under Process 3SHG Under Process 10 10 20 20 Under Prosess Nill Goatry Chakarpur Unde r Prosess Under Prosess 3SHG Under Prosess 10 10 - 10 Under Prosess Nill Goatry Gura ------Jagatpur, (E.K.) Under Prosess Under Prosess 3SHG Under Prosess 10 10 10 30 Under Prosess nill Dair y 2. Mau (2C4B5a4c) Marha Machhi Jhil Under Prosess 3SHG 10 5 25 30 Under Prosess nill Dairey Ambedker Nagar 26 -12 -11 Mehu lal Sanautar Dairy Mau Jai Santoshi Maa 28.12.11 Shyam Sunder Rakesh Kumar 9 15 9 33 Under Prosess 1100 Goatry Jai Maa Kali 30.12.11 Deena Nath Shiv Charan Poultry Maa Durga 10 -04 -11 Smt. Sonam Smt. Sunita Devi UNDER Rope Making Narayanpur Sahar 30.12.11 Suresh Kumar Rajesh Singh 8 10 12 30 1100 Jai Maa Kali PROSESS Goatry Ja Maa Saraswati 01.01.12 Jai Singh Har Voding Rajpur Bidhuna Under Prosess Under Prosess 3SHG Unde r Prosess 10 10 10 30 Under Prosess 1000 Poultry Sabhad ------Chakarpur ------Jai Durga 14.11.2010 Prabhu Dayal Puttu Dayal Dairy Khizarpur Jai Maa Kali 16.11.2010 Mahesh Chandra Govind 8 8 14 30 Under Prosess 1100 Goatry Jai Maa Saraswati 16.11.2010 Ajay Kumar Prakash Narayan Poultry Marha Machhi Jhil ------Mau ------Narayanpur Sahar Marha Macchi Jhil ------3 (2C4B5a4b) Rajpur Bidhuna ------Dr. Bhima Rao 15.11.2010 Subendar Kumar Jitendra Kumar Dairy Ambedakar Rathgaon (E.K.) 17.11.2010 Prem Chandra Suresh Kumar 10 15 13 38 Under Prosess 1100 Goatry Rani Laxmi Bai 19.11.2010 Saurabh Dilip Poultry Jai Bhole Ja i Bajrang 18.11.2010 Ram Kumar Ayudhya Prasad Dairy Sanwaliya Jai Bhole 20.11.2010 Deeraj Kumar Neeraj Kumar 10 10 10 30 Under Prosess 1100 Goatry Jai Maa Kali 24.11.2010 Raju Om Prakash Poultry

159 Total No. of Members Name of Bank and Up to Name of self Date of S. Name of Names of Name of Name of Address date Group Help constitutio Wo No. MWS villages Adhyaksh Sachiv Sc/St Other Total Account Saving activities group n men No. & Rs. Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Jai Krishna 12.01.2011 Bhoore singh Rampal Singh Banthara Under Dairy Jai Bajrang 12.01.2011 Brijendra Pratap Singh Vijay pal 11 11 10 32 1800 Goatry Prosess Jai Maa Ambe 15.01.2011 Smt. Shanti Devi Rekha Devi Poultry Belpur Bela Belpur Bela Dr.Ambedker 10.12.2011 Usa Devi Jai Devi 4 Under Dairy (2C4B5a4a) S.B. Patel SHG 12.12.2011 Santosh Kumari Madhuri 10 10 10 30 1100 Goatry Prosess Mahamaya 16.12.2011 Sheela Devi Premwati Poultry Rathgaon (E.K.) ------Sanwaliya ------Banthara ------Bashai ------Belpur Bela ------Marha Machhi Jhil ------Narainpur Bhanu ------Rathgaon (E.K.) ------Banthara 5 Sanwaliya ------(2C4B5a2d) Mahamaya SHG 18.01.2011 Rihana Begum Kajal Bano Under Dairy Tajpur Bidhuna Dr. Ambedkar 20.01.2011 Amit Kumar Subh Nath 10 10 10 30 1100 Fisheries Prosess Jai Maa Kali 20.01.2011 Surendra Kumar Jaslin Piggary Aanand 11.01.2011 Jitendra Singh Munna Lal Under Poultry Kiratpur Pragtisheel SHG 26.12.2011 Nanhi Devi Uma Devi 12 12 6 30 1200 Dairy prosess Dr. Ambedkar 29.12.2011 Usha Devi Smt. Jay Devi Goatry Under Bashai Under Prosess 3SHG 12 6 12 30 nill Poultry prosess Jai Bajrang 24.01.2011 Subash Chandra Krishna Kumar Under Dairy Dondapur 10 5 5 20 nill Jai Maa Ambe 29.01.2011 Kushuma Devi Sangeeta Devi prosess Goatry Under Narainpur Bhanu Jai Durga 3SHG 18.07.2011 Shri Ram Sevak Genda Lal 2 11 - 13 1100 Dairy Prosess Jai Maa 01.01.2012 Pankaj Kumar Saurabh Gupta Under Dondapur Palia Saraswati 10 5 5 20 Nill Goatry 6 01.01.2012 Annapurna Sunita Prosess (2C4B5a2c) Jai Maa Sharda 19.07.2011 Ram vilas Vidhya ram Jai Ambe SHG Goatry 19.07.2011 Vedvati Ganga sahaye Dairey Janvi Under 20.07.2011 Maan singh Santosh kumar 35 42 10 87 1700 Poultry Pusauli Jai Shri Ram 18.12.2011 Premvti Meera devi Prosess Goatrey Jai Vira Devi Dairy

Tajpur Bidhuna ------

160 Total No. of Members Name of Bank and Up to Name of self Date of S. Name of Names of Name of Name of Address date Group Help constitutio No. MWS villages Adhyaksh Sachiv Women Sc/St Other Total Account Saving activities group n No. & Rs. Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Jai Shri Ram 15 -11 -2010 Raj Narayan Shiv Ram Under Babina Sukhchenpur 10 10 - 20 1100 Goatry Jai Maa 16.10.2010 Jawahar Lal Ram Prakash Prosess Belpur Bela ------Babina Under Pasua Jai Maa Santoshi 16.10.2010 Ramkesh Ram Pal - 12 12 24 1800 Dairy 7 Sukhchenpur Process (2C4B5a1d) Rathgaon (E.K.) ------Jai Maa Durge 10.10.2010 Ram Kumar Rohit Goatry Under Sarai Pratham Dr. Ambedkar 11.10.2010 Pati Ram Pyare Lal 10 10 10 30 1100 Poultry Process Jai Maa Kali 15.10.2010 Khan Durjan Lal Dairy Babina Sukhchenpur ------

Bampur Rampur Shitla SHG 17.11.2010 Pratap Singh Ram Prakash Under 13 18 8 39 1100 Goatry Jai Maa Kali 16-11-2010 Jawahar Lal Ram Ratan prosess Poultry Aanand 30.01.2012 Virnedra Ram Awtar Under Goatry Bamrauliya 10 - 10 20 1100 Pragtisheel SHG 15.01.2011 Devi Dayal Surya Kumar Prosess Poultry Jai Maa Laxmi 1-12 -201 1 Mithlesh Devi Meeta Devi Goatry Under Bhadsiya Jai Pahari Baba 01.01.2012 Diensh Singh Chandra Bhan 10 10 10 30 2200 Poultry Prosess Baba Bhauraj 30.01.2012 Saroj Devi Vidhya Devi Dairy Jai Shank Baba 10 -10 -2010 Rakesh Babu Raghvendra under Poultry Bhikhra 10 10 - 20 1100 Jai Kali 14.10.2010 Pushpa Devi Aarti Devi prosess Dairy Dondapur ------Bhadasiya Jai Maa Kali 13 -01 -2011 Arvind Dev Dutt 8 under Poultry (2C4B5a1c) Indapamau Jai Maa Annpurna 15.01.2011 Roop Chand Chandra Pal 10 15 5 30 1000 prosess Dairy Jai Maa Santoshi 11.12.2011 Satyawati Bindeshwari Jan hvi 09 -09 -2010 Chandra Bali Vinod Kumar under Dairy Marhokh Hariram 12 19 1 32 1000 Jai Shri Ram 14.09.2010 Babu Ram Virendra Kumar prosess Poultry Jai Maa Annpurna 13 -01 -2011 Vijay Kumar Pintoo Goatr y under Marhokh Mit Jai Durga 15.01.2011 Devendra Satish Chandra 10 20 - 30 1100 Poulatrey prosess Jai Maa Sheetla 18.01.2011 Radhey Shyam Ram Sewak Dairy Narayanpur Bhanu ------under Nawada Malkhan Under Process - under prosess - - 10 10 nill Poultry prosess Pusauli ------Jai Maa Laxmi 12.01.11 Satya Narayan Sone Lal Poultry under Roopur Sahar Jai Pahari Baba 14.01.11 Har Dayal Awadesh Kumar 10 10 10 30 1100 Dairy prosess Baba Bhauraj 25.01.11 Prasad Urmila Devi Fisheries

161 Total No. of Members Name of Up to S. Name of self Bank and Name of Names of Date of Name of Name of date Group No Help Address MWS villages constitution Adhyaksh Sachiv Women Sc/St Other Total Saving activities . group Account Rs. No. & Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Jai Maa Kalika 27.01.12 Ram Ratan Manoj Kumar under Poultry Asjana 10 10 10 30 1100 Ambedkar 30.01.12 Salik Ram Ishrar Ali prosess Dairy Jai Bajrang 18.11.11 Raja Ram Amar Signh Dairy Barka Purwa 14 9 10 33 do 1100 Jai Maa Ambe 29.11.11 Ativir Amrikh Gotary Bhikhra ------Indpamau 9 Indapamau ------(2C4B5a1b) Ram ji -Shyam ji 14 -11 -11 Ram Kishan Guru Dyal under Goatrey Rawatpur ALD) 10 6 6 22 1100 Shri Krishan 15.11.11 Prem Chandra Chhote Lal prosess Dairy Rooppur Sahar ------Vimtamau ------Nawada Malkhan ------Asjana ------Jai Maa Vaisno 19 -11 -2011 Vijay Pratap Madan Lal Goatry Asjana Under 10 Hathnapur Jai Maa Durga 21.11.2011 Ignesh Kumar Munni Lal 7 20 - 27 1400 Poultry (2C4B5a1c) (L) Prosess Jai Maa Ambey 23.11.2011 Gyan Pratap Suresh Kumar Dairy Vimatamau ------Pa sua ------Goatr y Purwa Bhadauria Jai Maa Kali 5-10-2010 Chhotel Lal Ram Pratap Under 9 11 3 23 1200 Poulatrey Ruru (ALD) Jai Maa Durge 07.10.2010 Narendra Anand Kumar Prosess Dairy Jai Maa Durge 10 -10 -2010 Ramkumar Ro hit Under Goatry Dr. Ambedker 11-10-2010 Pati ram Vade Lal 10 10 10 30 prosess 1400 Dairy Sarai Pratham Sarai Pratham Jai maa kali 15-10-2010 Islam khan Durjan Lal Poultry 11 (2C4B5a1d) L Devi Dayal Under Malikpur Mishripur Dr. Ambedkar 16-12-2010 Ram Kishore 1100 Goatry Parashu Ram 10 14 2 26 prosess (ALD) Ja Maa Saraswati 18.12.2010 Nathu Ram Poultry Rakesh Kumar Under Ali 15-12-2010 Ashok Kumar 1100 Goatry Kariapur Ruru (ALD) Jeevan Lal 12 12 2 26 prosess Ram Janki 18.12.2010 Rita Devi Poultry Jai maa Santoshi 16 -11 -2010 Ram Singh Suresh Kumar Under Dairy Jai Maa Durge 16-11-2010 Ajay Veer Mahesh Chandra Goatry 15 18 1 34 prosess 1700 Shivpur (ALD) Jai Maa Ambe 16-11-2010 Ajad Ali Noor Jahan Poultry Sarai Pratham Jai Maa Laxmi 05-02-2011 Anand Priya Guddi Silayi

(2C4B5a1d) L Under Dairy Sahani 11-12-2010 Manoj Kumar Ashok Kumar 1400 Udelapur (ALD) 11 16 4 31 Goatry Jai Baba 15.12.2010 Ram Bahadur Ram Sewak prosess Poultry (M-Male, F-Female)

162 4.2 Details of formation of User Grups (UGs) User Groups were formed on the basis of beneficiaries of different natural resource conservation activities to be constructed in the watershed. The location of the activities/group mentioned in Table 4.7. Table 4.7: Village wise details of User Groups (UGs) in the project area IWMP- I Project- IWMP- I District – Auraiya Total no. of No. of SC/ST in No. of BPL in Date of S. Name of Names of No. of members UGs . each category each category formation No. MWS villages Men Women Both Total Categories M F Total M F Total M F Total of Ugs 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 (i) Landless ------(ii) SF 8 2 10 ------18.01.11 Bhatura (E.K.) 2 - 1 3 (iii) MF 1 1 2 2 - 2 5 - (iv) LF 1 - 1 1 - 1 - 5 Total 10 3 13 3 - - - - - (i) Landless ------(ii) SF 6 2 8 2 2 4 5 1 Sabhad (2C4B5a4d) Gura 1 - 1 2 (iii) MF 38 2 40 10 1 11 25 1 25 10.01.11 (iv) LF 1 1 2 ------Total 45 5 50 12 1 1 29 1 1 (i) Landless ------(ii) SF 17 1 18 13 - - - - - 14.01.11 Sabhad 3 - 1 4 (iii) MF 96 2 98 80 - - - - - (iv) LF 3 1 4 - - - - - Total 116 4 120 93 - 93 106 2 108 (i) Landless ------(ii) SF 8 2 10 4 - 4 6 1 7 12.01.11 Badin (E.K.) 1 - 1 2 (iii) MF 19 1 20 15 2 17 17 17 (iv) LF 2 - 2 - - - 1 - 1 Total 29 3 32 19 21 24 1 25 (i) Landless ------(ii) SF 5 2 7 3 1 4 4 2 6 19.12.10 Bhatoli Bidhuna 1 - 1 2 (iii) MF 1 1 2 - - - 1 1 2 (iv) LF ------Total 6 3 9 3 1 4 5 3 8 2. Mau (2C4B5a4c) (i) Landless ------(ii) SF 15 1 16 4 1 5 13 1 14 14.12.11 Chakarpur 1 - 1 2 (iii) MF 2 1 3 - - - 1 1 2 (iv) LF ------Total 17 2 19 4 1 5 14 2 16 (i) Landless ------(ii) SF ------Gura - (iii) MF ------(iv) LF ------Total

163 Total no. of No. of SC/ST in No. of BPL in Date of No. of members Name of Names of UGs. each category each category formation S. MWS villages of Ugs No. Men Women Both Total Categories M F Total M F Total M F Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 (i) Landless ------(ii) SF 12 2 14 4 2 6 10 1 11 Jagatpur, (E.K.) 1 - 1 (iii) MF 3 1 4 1 1 2 1 1 2 10.11.2010 (iv) LF ------Total 15 3 18 5 3 8 11 2 13 (i) Landless ------(ii) SF 80 10 90 18 2 20 70 8 78 14.11.2011 Marha Machhi Jhil 1 - 1 2 (iii) MF 12 1 13 4 1 5 10 10 (iv) LF 1 1 2 Total 93 12 105 22 3 25 80 8 88 (i) Landless ------(ii) SF 35 5 40 8 1 9 32 4 36 Mau 2 - 2 (iii) MF 23 2 25 22 1 23 10.11.2010 (iv) LF 5 ------Total 63 7 70 8 1 9 54 5 59 Mau (2C4B5a4c) (i) Landless ------(ii) SF ------Narayanpur Sahar - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF 42 3 45 10 1 11 40 1 41 12.11.10 Rajpur Bidhuna 1 - 1 2 (iii) MF 8 2 10 2 1 3 (iv) LF 2 2 Total 52 5 57 10 1 11 42 2 44 (i) Landless ------(ii) SF ------Sabhad - - - - (iii) MF ------(iv) LF ------Total ------

164 Total no. of No. of SC/ST in No. of BPL in Date of No. of members Name of Names of UGs. each category each category formation S. MWS villages of Ugs No. Men Women Both Total Categories M F Total M F Total M F Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 (i) Landless ------(ii) SF 18 2 20 2 1 3 14 1 15 18.11.11 Chakarpur 1 - 1 2 (iii) MF 1 1 2 1 1 2 (iv) LF ------Total 19 3 22 3 2 5 14 1 15 (i) Landless ------(ii) SF ------Khizarpur - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Marha Machhi Jhil - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Mau - - - - (iii) MF ------(iv) LF ------Marha Macchi Jhil Total ------3. (2C4B5a4b) (i) Landless ------(ii) SF ------Narayanpur Sahar - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Rajpur Bidhuna - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF 114 6 120 15 2 17 110 2 112 16.11.11 Rathgaon (E.K.) 1 - 1 2 (iii) M F 20 2 22 10 1 11 14 1 15 (iv) LF 1 1 2 Total 135 9 144 25 3 28 124 3 127 (i) Landless ------(ii) SF 45 5 50 25 1 26 40 40 15.11.11 Sanwaliya 1 - 1 2 (iii) MF 14 1 15 10 10 10 10 (iv) LF 1 1 Total 60 6 66 35 1 36 50 50

165 Total no. of No. of SC/ST in No. of BPL in Date of No. of members Name of Names of UGs. each category each category formation S. MWS villages of Ugs No. Men Women Both Total Categories M F Total M F Total M F Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 (i) Landless ------(ii) SF 94 6 100 19 7 25 70 1 71 12.10.11 Banthara 2 - - 2 (iii) MF 15 2 17 2 1 3 10 1 11 (iv) LF 1 1 2 Total 110 9 119 21 8 29 80 2 82

(i) Landless ------(ii) SF 60 10 70 10 2 12 50 2 52 18.10.11 Belpur Bela 1 - 1 2 (iii) MF 8 2 10 2 1 3 6 1 7 (iv) LF 1 1 2 Total 69 13 82 12 3 15 56 3 59 4. Belpur Bela (2C4B5a4a) (i) Landless ------(ii) SF ------Rathgaon (E.K.) - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Sanwaliya - - - - - (iii) MF ------(iv) LF ------Total ------

166

Total no. of No. of SC/ST in No. of BPL in Date of No. of members Name of Names of UGs. each category each category formation S. MWS villages of Ugs No. Men Women Both Total Categories M F Total M F Total M F Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 (i) Landless ------(ii) SF ------Banthara - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF 13 2 15 10 1 11 11 1 12 14.10.11 Bashai 1 - - 1 (iii) MF 1 1 2 1 1 2 (iv) LF ------Total 14 3 17 10 1 11 12 2 14 (i) Landless ------(ii) SF ------Belpur Bela - - - - (iii) MF ------(iv) LF ------Total ------5. Banthara (2C4B5a2d) (i) Landless ------(ii) SF ------Marha Machhi Jhil - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF 38 2 40 27 2 29 27 1 28 25.12.11 Narainpur Bhanu 1 - - 1 (iii) MF 9 1 10 7 1 8 8 1 9 (iv) LF 2 1 3 1 1 2 1 1 2 Total 49 4 53 35 4 36 36 3 39 (i) Landless ------(ii) SF ------Rathgaon (E.K.) - - - - (iii) MF ------(iv) LF ------Total ------

167 Total no. of No. of SC/ST in No. of BPL in Date of No. of members Name of Names of UGs. each category each category formation S. MWS villages of Ugs No. Men Women Both Total Categories M F Total M F Total M F Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 (i) Landless ------(ii) SF ------Sanwaliya - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF 65 5 70 17 2 19 50 5 55 16.11.11 Banthara (2C4B5a2d) Tajpur Bidhuna - - 1 1 (iii) MF 6 2 8 5 1 6 2 1 3 (iv) LF 1 1 2 Total 72 8 80 22 3 25 22 6 58 (i) Landless ------(ii) SF 30 6 36 25 1 26 28 3 31 18.11.11

Kiratpur - - - - (iii) MF 3 1 4 12 1 13 2 1 3

(iv) LF 1 1 2 Total 34 8 42 37 2 39 30 4 34 (i) Landless ------(ii) SF ------Bashai - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii ) SF 85 5 90 18 2 20 80 2 82 Dondapur - - 1 1 (iii) MF 18 2 20 2 1 3 4 1 5 19.11.11 (iv) LF 9 1 10 Total 112 8 120 20 3 23 84 3 87 (i) Landless ------(ii) SF ------6. Dondapur (2C4B5a2c) Narainpur Bhanu (iii) M F ------(iv) LF ------Total ------(i) Landless ------(ii) SF 8 1 9 3 2 5 6 1 7 06.11.11 Palia 1 - - 1 (iii) MF 1 1 2 1 1 2

(iv) LF ------Total 9 2 11 3 2 5 7 2 9 (i) Landless ------(ii) SF 45 5 50 14 2 16 35 2 37 15.11.11 Pusauli 1 - - 1 (iii) MF 6 2 8 4 1 5 4 1 5 (iv) LF 1 1 2 1 1 2 Total 52 8 60 18 2 21 40 4 44

168 Total no. of No. of SC/ST in No. of BPL in Date of No. of members Name of Names of UGs. each category each category formation S. MWS villages of Ugs No. Men Women Both Total Categories M F Total M F Total M F Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 (i) Landless ------(ii) SF 54 6 60 18 2 20 48 2 50 18.11.11 Tajpur Bidhuna 2 - - 2 (iii) MF 14 2 16 2 1 3 10 2 12 (iv) LF 3 1 4 Total 71 9 80 20 3 23 58 4 62 (i) Landless ------(ii) SF 55 7 62 22 3 25 14 2 16 20.12.11 Babina Sukhchenpur 2 - 1 3 (iii) MF 22 4 26 11 2 13 5 1 6 (iv) LF 1 1 2 1 Total 78 12 90 34 5 39 19 3 22 (i) Landless ------(ii) SF ------Belpur Bela - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF 28 8 36 17 3 20 9 2 11 Babina Sukhchenpur 16.10.11 7. Pasua 1 - 1 2 (iii) MF 16 5 21 9 2 11 4 1 5 (2C4B5a1d) (iv) LF 2 1 3 1 1 2 1 1 Total 46 14 60 27 6 33 14 3 17 (i) Landless ------(ii) SF ------Rathgaon (E.K.) - - - - (iii) MF ------(iv) LF ------Total (i) Landless ------(ii) SF ------Sarai Pratham - - - - (ii i) MF ------(iv) LF ------Total ------

169

Total no. of No. of SC/ST in No. of BPL in Date of No. of members Name of Names of UGs. each category each category formation S. MWS villages of Ugs No. Men Women Both Total Categories M F Total M F Total M F Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 (i) Landless ------(ii) SF ------Babina Sukhchenpur - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Bampur Rampur - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Bamrauliya - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------8. Bhadasiya (2C4B5a1c) Bhadsiya - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Bhikhra - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Dondapur - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Indapamau - - - - (iii) MF ------(iv) LF ------Total ------

170 Total no. of No. of SC/ST in No. of BPL in Date of No. of members Name of Names of UGs. each category each category formation S. MWS villages of Ugs No. Men Women Both Total Categories M F Total M F Total M F Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 (i) Landless ------(ii) SF 12 3 15 3 3 1 1 2 14.10.11 Marhokh Hariram - - 1 1 (iii) MF 10 2 12 2 2 4 1 1 2 (iv) LF 1 1 Total 23 5 28 5 2 (i) Landless ------(ii) SF 9 2 11 2 2 1 1 2 15.10.11 Marhokh Mit - - 1 1 (iii) MF 5 1 6 3 3 1 1 2 (iv) LF ------Total 14 3 17 5 5 2 2 4 (i) Landless ------(ii) SF ------Narayanpur Bhanu - - - - (iii) MF ------(iv) LF ------Total ------Bhadasiya (2C4B5a1c) (i) Landless ------(ii) SF ------Nawada Malkhan - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Pusauli - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Roopur Sahar - - - - (iii) MF ------(iv) LF ------Total ------

171

Total no. of No. of SC/ST in No. of BPL in Date of No. of members Name of Names of UGs. each category each category formation S. MWS villages of Ugs No. Men Women Both Total Categories M F Total M F Total M F Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 (i) Landless ------(ii) SF 75 6 81 13 2 15 3 1 4 10.10.11 Asjana - - 1 1 (iii) MF 61 4 65 7 1 8 2 1 3 (iv) LF 6 2 8 1 1 Total 142 12 154 21 3 24 5 2 7 (i) Landless ------(ii) SF 15 3 18 2 1 3 2 5 7 18.10.11 Barka Purwa - - 1 1 (iii) MF 12 3 15 1 2 1 3 4 (iv) LF 1 1 Total 28 6 34 3 1 5 3 8 11 (i) Landless ------(ii) SF ------Bhikhra (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF 67 7 74 8 3 11 3 2 5 16.10.11 Indapamau 1 - 1 2 (iii) MF 42 5 47 3 2 5 2 1 3 (iv) LF 4 1 5 1 1 5 3 8 Total 113 13 126 12 5 17 9. Indpamau (2C4B5a1b) (i) Landless ------(ii) SF 35 2 37 7 2 95 3 1 4 Rawatpur ALD) 2 - 1 3 (iii) MF 23 1 24 3 1 4 2 1 14.12.11 (iv) LF 3 3 3 Total 61 3 64 10 3 13 5 2 7 (i) Landless ------(ii) SF 43 5 48 15 3 18 6 1 7 Rooppur Sahar 1 1 1 3 (iii) MF 27 4 31 9 2 11 2 1 3 15.10.11 (iv) LF 1 1 Total 71 9 80 24 5 29 8 2 10 (i) Landless ------(ii) SF 76 11 87 15 5 20 7 4 11 Vimtamau 1 2 - 3 (iii) MF 47 4 51 6 3 9 3 1 4 16.11.11 (iv) LF 2 2 Total 125 15 140 21 8 29 10 5 15 (i) Landless ------(ii) SF 23 5 28 5 2 7 4 2 6 Nawada Malkhan 1 - 1 2 (iii) MF 17 2 19 4 1 5 3 1 3 18.11.11 (iv) LF 2 1 3 Total 42 8 50 9 3 12 7 3 9

172 Total no. of No. of SC/ST in No. of BPL in Date of No. of members Name of Names of UGs. each category each category formation S. MWS villages of Ugs No. Men Women Both Total Categories M F Total M F Total M F Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 (i) Landless ------(ii) SF ------Asjana - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF 33 7 40 8 3 11 4 2 6 10. Asjana (2C4B5a1c) (L) Hathnapur 1 - 1 2 (iii) MF 19 2 21 5 1 6 2 1 3 17.12.11 (iv) LF 4 2 6 Total 56 11 67 13 4 17 6 3 9 (i) Landless ------(ii) SF ------Vimatamau - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF ------Pasua - - - - (iii) MF ------(iv) LF ------Total ------(i) Landless ------(ii) SF 9 2 11 2 1 3 2 1 3 Purwa Bhadauria Ruru (ALD) 1 - 1 2 (iii) MF 5 1 6 1 1 2 1 1 5 16.10.11 (iv) LF ------Total 14 3 17 3 2 5 3 2 8 (i) Landless ------(ii) SF 45 5 50 7 2 9 3 1 4 Sarai Pratham 11. Sarai Pratham 1 1 1 3 (iii) MF 27 3 30 3 2 5 2 1 3 14.10.11 (2C4B5a1d) L (iv) LF 6 1 7 Total 78 9 87 10 4 14 5 2 7 (i) Landless ------(ii) SF 11 3 14 3 1 4 1 1 2 Malikpur Mishripur (ALD) - 1 1 2 (iii) MF 5 3 8 2 1 3 1 1 2 08.12.11 (iv) LF 1 1 Total 17 6 23 5 2 7 2 2 4 (i) Landless ------(ii) SF 7 1 8 2 2 1 1 Kariapur Ruru (ALD) 1 - 1 2 (iii) MF 4 1 5 1 1 1 1 16.12.11 (iv) LF ------Total 11 2 13 3 3 2 2

173 Total no. of No. of SC/ST in No. of BPL in Date of No. of members Name of Names of UGs. each category each category formation S. MWS villages of Ugs No. Men Women Both Total Categories M F Total M F Total M F Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 (i) Landless ------(ii) SF 89 17 106 21 5 26 5 3 8 Shivpur (ALD) 1 1 4 6 (iii) MF 63 18 81 13 1 14 2 1 3 14.10.11 (iv) LF 7 4 11 Sarai Pratham Total 159 39 198 34 6 40 7 4 11

(2C4B5a1d) L (i) Landless ------(ii) SF 32 6 38 11 3 14 7 1 8 Udelapur (ALD) 1 - 1 2 (iii) MF 7 2 9 2 1 3 18.12.11 (iv) LF 3 1 4 2 1 3 Total 42 9 51 15 5 20 7 1 8 Grand Total 40 6 34 80 2237 307 2544 669 109 760 964 104 1016

174 4.3 Convergence in IWMP-I, Auraiya

Several programmes are running in the area which are sponsored by Central and State Govt. and could be converged with watershed programmes. The details of the activities to be carried out under convergence in the project are mentioned in Chapter 5. However, micro- watershed wise amount of convergence is mentioned in Table 4.9.

Table 4.8: List of Central/State sponsored schemes

S.No. Name of Programme Implementing Agency Objectives of the Programme To increase seed replacement Seed Distribution Programme (Pulse 1 U.P. Agriculture Deptt. ratio for higher Development & ISOPAM) productivity 2 Pump set Distribution (Food Security Mission) Agriculture Deptt. Providing irrigation Agriculture Deptt., 3 Training Programme Capacity building of the farmers KVK 4 HDPE pipe Agriculture Deptt. Increasing the area under fruits 5 National Horticulture Mission (NHM) Horticulture Deptt. and vegetables To make hygienic condition in 6 Sanitation Programme Gram Vikash the rural areas To provide work to the all village personnel 7 MGNERGA (Watershed development, forestry etc.) Gram Panchayat under the rojgar guarantee yojana To improve the productivity of 8 Dept. of Animal Husbandry U.P. Animal Husbandry livestock 9 Afforestation Deptt. of Forest U.P. To improve the vegetative cover 10 NABARD (Agriculture & SMC) Deptt. Of Agriculture Watershed development etc.

175 Table 4.9 Details of Convergence of IWMp with other Schemes in IWMP-I, Auraiya (Rs. Lakh)

Names of Was this fund Fund made Name of Departments included in Rs. Reference no. of Level at which Name of available to activity/task/structure S. with Schemes 12, 000/ 15,000 per activity/ task/ decision for Micro convergence undertaken with No. converging ha. structure in convergence Watershed (Rs. converged with DPR@ was taken$ in lakh) Yes No funds IWMP 1 2 3 4 5 6 7 8 9 1. Sabhad (2C4B5a4d) MGNREGA 7.1320 2. Mau (2C4B5a4c) - do - 6.7440 3. Marha Macchi Jhil (2C4B5a4b) - do - 1.8710 4. Belpur Bela (2C4B5a4a) - do - 3.8210 5. Banthara (2C4B5a2d) - do - 0.5460

6. Dondapur (2C4B5a2c) - do - 0.8540 Additional to the Water Resource Included in DPR Distrct Level 7. Babina Sukhchenpur (2C4B5a1d) - do - 0.5910 cost of Rs. 12000/ha Development 8. Bhadasiya (2C4B5a1c) - do - 1.4550 9. Indpamau (2C4B5a1b) - do - 1.3080 10. Asjana (2C4B5a1c) (L) - do - 0.6640 11. Sarai Pratham (2C4B5a1d) L - do - 2.1770 Total 27.1630

176 CHAPTER – 5

MANAGEMENT/ACTION PLAN

The details of Preparatory Phase, Works Phase and Convergence planning are described in subsequent section

5.1 Entry Point Activities (EPA)

Entry point activities were executed with the consent of stake holders and it helped in winning the confidence of the villagers for moving ahead the other programmes of watershed. In total 27 EPA activities were executed in the project area which costed Rs. 2965000.00 Photographs of entry point activities done in the project are given below in Table No. 5.1:

Table. 5.1 : Detail of EPA Activities and their expenditure Name of Name of Name of Name of Code of E.P.A cost Cost in Year project/ Location Rem. PIA Project Block project in lakh Lacs Name of village 1 2 3 4 5 6 7 8 9 10 Sabhad (2C4B5a4d) 2.80 construction for drainage from village Sabhad 2.8 0 - mau road to pond, Out of Village kachpura to big Mau (2C4B5a4c) 2.67 2.67 - drainage construction for drainage from village khijarpur to pond, A kisan manch construction on Gram Marha Macchi (2C4B5a4b) 2.47 sabha land near tempe, A handpum platform 2.47 - Jhil repairing near ramnath house Mau sampark marg to vill. nibajpur Gram sabha land on near suresh house, Gram Belpur Bela (2C4B5a4a) 3.01 sabha land on near suresh house, Near Village 3.01 - raundapur road Banthara (2C4B5a2d) 2.79 Village ratanpur primary school to old drainage 2.79 - LDWR IWMP-I 2009-10 Bidhuna Village Pusauli near suresh house to pond, gram Auraiya-I Dondapur (2C4B5a2c) 2.49 sabha land near suresh house, Village Pusauli 2.49 - road to ramratan house Babina A kisan manch construction on Gram sabha land, (2C4B5a1d) 2.15 2.15 - Sukhchenpur Nahar to vill. ludhpura Village bhikhara road to hanuman tempale, Bhadasiya (2C4B5a1c) 3.12 3.12 - Village bhaunrajpur road from drainage drainage from Coprativ com metie to Indpamau (2C4B5a1b) 2.88 basantapurwa, Coprativ commetie to 2.88 - basantapurwa Diwlipurwa to asjana Asjana (2C4B5a1c) L 2.72 2.72 -

Sarai Pratham (2C4B5a1d) L 2.55 Village chapora jasbant singh house to pond 2.55 - total 29.65 29.65 -

177 Year 2009-10 Year 2009-10 Entry Point Activities Entry Point Activities LDWR- Auraiya-I, IWMP-I LDWR- Auraiya-I, IWMP-I MWS- Village- Pusauli MWS- Village- Pusauli Block- Distt.-Auraiya Block- Distt.-Auraiya

Village - Pusauli Village - Pusauli

178

Year 2009-10 Year 2009-10 Entry Point Activities Entry Point Activities LDWR- Auraiya-I, IWMP-I LDWR- Auraiya-I, IWMP-I MWS- Village- Kiratpur MWS- Village- Kiratpur Block- Distt.-Auraiya Block- Distt.-Auraiya

Village –Vimtamau Village – Vimtamau

179 5.2 Works Phase

Following are the major problems of the watersheds • Excess runoff and soil loss • Poor water holding capacity of the soil • Low productivity of crops • Low fertility of soil • Low cropping intensity • Lack of technical knowledge • Poor vegetative cover • Poor/low productive breeds of miltch animals • Lack of feed & fodder availability • Non availability of wood/fuel • Lack of proper market facilities • Low income of the households • Lack of employment opportunity.

Estimation of Runoff from the Watershed Approximately it is estimated that runoff potential of the project area is 308.64 mm, equivalent to 48.37 per cent of average annual rainfall. Expected runoff and soil loss from the project area are depicted Table 5.1.

180 Table 5.2: Runoff and soil erosion in the project area (IWMP-I, Auraiya)

Name of Micro Run off Average Soil Loss Sr. No. Cause Type of erosion Area affected (ha) Watershed (mm/ year) (Tonnes/ ha/ year) 1 2 3 4 5 6 7 Water erosion Sabhad a Sheet 206.302 1 b Rill 279.728 302 18-19 (2C4B5a4d) c Gully 4.722 Total 490.752 Water erosion Mau a Sheet 367.977 2 b Rill 514.213 312 21-22 (2C4B5a4c) c Gully 15.314 Total 897.504 Water erosion Marha Macchi Jhil a Sheet 211.758 3 b Rill 299.561 305 19-20 (2C4B5a4b) c Gully 5.165 Total 516.484 Water erosion Belpur Bela a Sheet 116.108 4 b Rill 150.163 314 22-23 (2C4B5a4a) c Gully 24.000 Total 290.271 Water erosion Banthara a Sheet 285.635 5 b Rill 402.800 308 19-20 (2C4B5a2d) c Gully 4.853 Total 693.288 Water erosion Dondapur a Sheet 192.083 6 b Rill 250.533 312 22-23 (2C4B5a2c) c Gully 20.235 Total 462.851

181 Name of M icro Run off Average Soil Loss Sr. No. Cause Type of erosion Area affected (ha) Watershed (mm/ year) (Tonnes/ ha/ year) 1 2 3 4 5 6 7 Water erosion Babina Sukhchenpur a Sheet 127.470 7 b Rill 160.324 306 20-21 (2C4B5a1d) c Gully 23.109 Total 310.903 Water erosion Bhadasiya a Sheet 294.609 8 b Rill 447.508 305 17-18 (2C4B5a1c) c Gully 3.729 Total 745.846 Water erosion Indpamau a Sheet 272.669 9 b Rill 351.112 312 19-20 (2C4B5a1b) c Gully 30.102 Total 653.883 Water erosion Asjana a Sheet 138.640 10 b Rill 187.563 314 20-21 (2C4B5a1c) (L) c Gully 20.398 Total 346.601 Water erosion a Sheet 315.133 Sarai Pratham 305 18-19 11 b Rill 441.352 (2C4B5a1d) L c Gully 12.132 Total 768.617 Water erosion a Sheet 2528.384 Total for IWMP-I b Rill 3484.857 308.64 20.00 c Gully 163.759 Total 6177.00

182 Watershed Development Activities Proposed : The detail of microwatershed wise proposed activities are shown below Table 5.3 Microwatershed wise detail of Watershed development activites proposed in IWMP-1, Auraiya

(Rs. in Lac) Name of Microwatershed Unit Mau (2) Name of Head Sabhad (1) Marha Macchi Jhil (3) Belpur Bela (4) Banthara (5) Dondapur (6) (2C4B5a4d) (2C4B5a4c) (2C4B5a4b) (2C4B5a4a) (2C4B5a2d) (2C4B5a2c) Qty. Cost Qty. Cost Qty. Cost Qty. Cost Qty. Cost Qty. Cost 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1.Watershed Development Works 1.1 Land Development (Productive use) 1.1.1 Afforestation ha. 3.430 0.6950 6.280 1.2730 3.600 0.7320 2.000 0.4050 4.850 0.9830 3.230 0.6560 1.1.2 Horticulture ha. 7.500 1.9140 13.720 3.5050 7.890 2.0160 4.430 1.1330 10.600 2.7070 7.000 1.8050 1.1.3 Agriculture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 1.1.4 Pasture ha. 1.470 0.3670 2.690 0.6710 1.500 0.3860 1.000 0.2170 2.000 0.5180 1.300 0.3460 1.1.5 Others Sq.mt. 8250.00 0.4800 15145 0.8780 8710.00 0.5050 4890.00 0.2840 11700.00 0.6790 7800.00 0.4520 Total 3.4560 6.3270 3.639 2.0390 4.8870 3.2590 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 245.00 14.700 448.50 26.910 258.00 15.480 145.00 8.700 346.00 20.760 231.00 13.860 1.2.2 Peripheral & Marginal Bunding 98.28 9.828 179.75 17.975 103.80 10.380 58.86 5.886 138.94 13.894 92.86 9.286 (with sodding) meter/ha 1.2.3 Others meter/ha 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Total 343.28 24.528 628.25 44.885 361.80 25.860 203.86 14.586 484.94 34.654 323.86 23.146 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 1.3.2 Gully plugs No. 6 4.628 10 7.690 5 3.850 13 4.884 7 5.128 4 2.873 1.3.3 Others No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 Total 6 4.628 10 7.690 5 3.850 13 4.884 7 5.128 4 2.873 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 1.4.2 Check dams No. 10 7.500 12 9.058 4 3.230 2 1.818 3 2.466 3 2.680 1.4.3 Nallah Bunds No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 1.4.4 Others No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 Total 10 7.500 12 9.058 4 3.230 2 1.818 3 2.466 3 2.680

183

1 2 3 4 5 6 7 8 9 10 11 12 13 14 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 1.5.2 Check dams No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 1.5.3 Nallah Bunds No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 Total 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 Grand Total 40.112 67.056 36.579 23.327 47.135 31.958 2. Administrative Cost ha. 490.752 5.889 897.504 10.770 516.484 6.198 290.271 3.483 693.288 8.320 462.851 5.554 3. Monitoring 0.589 1.077 0.620 0.348 0.832 0.555 4.Institution & Capacity Building 4.1 SHG Formation 0.000 0.000 0.000 0.000 0.000 0.000 4.2 UG Formation 0.000 0.000 0.000 0.000 0.000 0.000 4.3 Formation of Federation 0.000 0.000 0.000 0.000 0.000 0.000 4.4 Capacity building No. of person 507 2.945 924 5.385 532 3.099 299 1.742 714 4.160 476 2.777 5.DPR 0.589 1.077 0.620 0.348 0.832 0.555 Total 490.752 10.012 897.504 18.309 516.484 10.537 290.271 5.921 693.288 14.143 462.851 9.441 6.Livelihood activities for the asset -less persons

No. of SHG/ 7/45 5.302 12/70 9.690 7/45 5.573 5/35 3.132 11/65 7.488 7/45 4.995 6.1 Plan for Livelihood activities Person Total 5.302 9.690 5.573 3.132 7.488 4.995 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 Person No. of SHG/ 1/7 0.560 3/12 0.983 1/7 0.566 1/5 0.318 2/10 0.759 1/5 0.506 7.2 Beekeeping Person No. of SHG/ 4/19 0.799 7/35 1.430 4/20 0.824 2/10 0.463 5/25 1.106 3/18 0.738 7.3 Poultry Person No. of SHG/ 1/5 0.383 1/5 0.680 1/5 0.396 1/5 0.222 1/5 0.531 1/5 0.354 7.4 Fisheries Person No. of SHG/ 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 7.5 Bio-fuel Plantation Person No. of SHG/ 3/30 2.221 7/60 4.052 3/30 2.331 2/17 1.310 4/40 3.130 3/30 2.087 7.6 Dairy Person 7.7 Others (Green Manuring) ha. 184.00 1.9260 337.00 3.625 194.00 2.081 108.00 1.170 260.00 2.794 173.00 1.869 Total 5.889 10.770 6.198 3.483 8.320 5.554 Grand Total (1+2+3+4+5+6+7) 61.315 105.825 58.887 35.863 77.086 51.948

184

Name of Microwatershed Babina Bhadasiya (8) Indpamau (9) Asjana (10) Sarai Pratham (11) Unit Sukhchenpur (7) Total (2C4B5a1c) (2C4B5a1b) (2C4B5a1c) L (2C4B5a1d) L Name of Head (2C4B5a1d) Target Target Target Target Target Target Qty. Cost Qty. Cost Qty. Cost Qty. Cost Qty. Cost Qty. Cost 1 2 15 16 17 18 19 20 21 22 23 24 25 26 1.Watershed Development Works 1.1 Land Development (Productive use) 1.1.1 Afforestation ha. 2.00 0.405 5.20 1.057 4.50 0.927 2.40 0.490 7.41 2.682 45.90 9.305 1.1.2 Horticulture ha. 4.74 1.211 11.40 2.910 10.00 2.551 5.30 1.352 11.97 3.043 94.55 24.147 1.1.3 Agriculture ha. 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 1.1.4 Pasture ha. 1.00 0.232 2.23 0.558 2.00 0.518 1.00 0.259 2.81 0.668 19.00 4.740 1.1.5 Others Sq.mt. 5230.00 0.303 12580.00 0.729 11025.00 0.640 5840.00 0.339 11130.00 0.762 104300.00 6.0510 Total 2.151 5.254 4.636 2.440 7.155 44.243 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 155.00 9.300 372.50 22.350 326.50 19.590 173.00 10.380 386.00 23.275 3086.50 185.305 1.2.2 Peripheral & Marg inal Bunding 62.41 6.241 149.81 14.981 130.21 13.021 69.79 6.979 150.61 15.131 (with sodding) meter/ha 1235.32 123.602 1.2.3 Others meter/ha 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 Total 217.41 15.541 522.31 37.331 456.71 32.611 242.79 17.359 536.61 38.406 4321.82 308.907 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 1.3.2 Gully plugs No. 3 2.100 5 3.996 5 3.855 3 2.318 5 3.867 66 45.384 1.3.3 Others No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 Total 3 2.100 5 3.996 5 3.855 3 2.318 5 3.867 66 50.40 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 1.4.2 Check dams No. 2 1.692 6 4.995 5 4.146 2 1.839 5 4.400 54 43.824 1.4.3 Nallah Bunds No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 1.4.4 Others No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 Total 2 1.692 6 4.995 5 4.146 2 1.839 5 4.400 54 43.824

185 1 2 15 16 17 18 19 20 21 22 23 24 25 26 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0.00 0.000 1.5.2 Check dams No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0.00 0.000 1.5.3 Nallah Bunds No. 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0.00 0.000 Total 0 0.000 Grand Total 21.483 51.576 45.248 23.956 53.828 442.268 2. Administrative Cost ha. 310.903 3.731 745.846 8.950 653.883 7.847 346.601 4.159 768.617 9.223 6177.00 74.124 3. Monitoring 0.373 0.895 0.785 0.416 0.922 7.412 4.Institution & Capacity Building 4.1 SHG Formation 0.000 0.000 0.000 0.000 0.000 0.000 4.2 UG Formation 0.000 0.000 0.000 0.000 0.000 0.000 4.3 Formation of Federation 0.000 0.000 0.000 0.000 0.000 0.000 4.4 Capacity building No. of person 319 1.865 767 4.475 672 3.923 356 2.080 796 4.612 6360 37.062 5.DPR 0.373 0.895 0.785 0.416 0.922 7.412 Total 310.903 6.342 745.846 15.215 653.883 13.340 346.601 7.071 768.617 15.679 6177.00 126.010 6.Livelihood activities for the asset -less persons

No. of SHG/ 5/30 3.352 11/65 8.051 10/60 7.063 5/30 3.742 12/65 8.321 92/555 66.711 6.1 Plan for Livelihood activities Person Total 3.352 8.051 7.063 3.742 8.321 66.711 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ Person No. of SHG/ 1/5 0.340 2/10 0.816 2/10 0.716 1/5 0.379 2/9 0.870 17/85 6.800 7.2 Beekeeping Person No. of SHG/ 2/12 0.495 6/30 1.190 5/25 1.043 3/15 0.553 6/26 1.236 47/235 9.879 7.3 Poultry Person No. of SHG/ 1/5 0.237 1/5 0.572 1/5 0.500 1/5 0.265 1/5 0.644 11/55 4.793 7.4 Fisheries Person No. of SHG/ 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 0 0.000 7.5 Bio-fuel Plantation Person No. of S HG/ 2/20 1.400 5/50 3.366 4/40 2.950 2/20 1.563 4/38 3.422 39/375 28.235 7.6 Dairy Person 7.7 Others (Green Manuring) ha. 116.00 1.259 280.00 3.006 245.00 2.638 130.00 1.399 293.00 3.051 2320.00 24.818 Total 3.731 8.950 7.847 4.159 9.223 74.124 Grand Total (1+2+3+4+5+6+7) 34.908 83.792 73.498 38.928 87.051 709.1144

186 Table 5.4 Village/Gram Panchayat/ Watershed Committee wise detail of Watershed development activites proposed in IWMP-1, Auraiya (Rs. in Lac)

Badin (E.K.) (1) Gura (2) Unit No./ Bhatura Badin Total Gura Rajpur Bidhuna Total Name of Head Length/ area ha Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost

1 2 3 4 5 6 7 8 9 10 11 12 13 14 1.Watershed Deve lopment Works 1.1 Land Development (Productive use) 1.1.1 Afforestation ha. 0.000 0.0000 1.000 0.0900 1.000 0.0900 1.500 0.1500 1.200 0.2550 2.700 0.4050 1.1.2 Horticulture ha. 0.600 0.2400 1.000 0.2320 1.600 0.4720 1.500 0.3120 2.300 0.5700 3.800 0.8820 1.1.3 Agriculture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 1.1.4 Pasture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.500 0.1250 0.500 0.1250 1.1.5 Others Sq.mt.- 0.000 0.0000 500.00 0.0300 500.00 0.0300 1000.00 0.0690 3000.00 0.1770 4000.00 0.2460 Total 0.2400 0.3520 0.5920 0.5310 1.1270 1.6580 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 7.006 0.4204 25.065 1.5040 32.071 1.9244 45.687 2.8610 69.4430 4.1660 115.130 7.0270 1.2.2 Peripheral & Marginal Bunding meter/ha 2.802 0.2820 10.026 1.0030 12.828 1.2850 19.075 1.9075 27.7790 2.7780 46.854 4.6855 (with sodding) 1.2.3 Others 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.0000 0.0000 0.000 0.0000 Total 9.808 0.7024 35.091 2.5070 44.899 3.2094 64.762 4.7685 97.2220 6.9440 161.984 11.7125 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.3.2 Gully plugs No. 0 0.0000 1 0.7636 1 0.7636 1 0.7631 2 1.5272 3 2.2908 1.3.3 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 0 0.0000 1 0.7636 1 0.7636 1 0.7631 2 1.5272 3 2.2908 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.2 Check dams No. 0 0.0000 1 0.8115 1 0.8115 1 0.8115 2 1.6230 3 2.4345 1.4.3 Nallah Bunds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.4 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 0 0.0000 1 0.8115 1 0.8115 1 0.8115 2 1.6230 3 2.4345

187

1 2 3 4 5 6 7 8 9 10 11 12 13 14 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.2 Check dams No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.3 Nallah Bunds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Total 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Grand Total 0.9424 4.4341 5.3765 6.8741 11.2212 18.0953 2. Administrative Cost ha. 14.012 0.1681 50.131 0.6016 64.143 0.7697 95.374 1.1445 138.886 1.6666 234.26 2.8111 3. Monitoring 0.0168 0.0602 0.0770 0.1145 0.1667 0.2812 4.Institution & Capacity Building 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.1 SHG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.2 UG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.3 Formation of Federation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.4 Capacity building No. of Person 15 0.0840 52 0.3007 67 0.3847 96 0.5722 139 0.8332 235 1.4054 5.DPR 0.0168 0.0602 0.0770 0.1144 0.1667 0.2811 Total 0.2857 1.0227 1.3084 1.9456 2.8332 4.7788 6.Livelihood activities for the asset-less persons No. of SHG/ 6.1 Plan for Livelihood activities Person 1/10 0.1513 1/12 0.5414 2/22 0.6927 2/14 1.0300 2/13 1.4999 4/27 2.5299 Total 1/10 0.1513 1/12 0.5414 2/22 0.6927 2/14 1.0300 2/13 1.4999 4/27 2.5299 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.2 Beekeeping Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.3 Poultry Person 0 0.0000 1/10 0.2000 1/10 0.2000 1/5 0.2000 1/5 0.2000 2/10 0.4000 No. of SHG/ 7.4 Fisheries Person 0 0.0000 0 0.0000 0 0.0000 1/5 0.3925 1/5 0.4000 2/10 0.7925 No. of SHG/ 7.5 Bio-fuel Plantation Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.6 Dairy Person 1/10 0.1581 1/10 0.2016 2/20 0.3597 1/10 0.2020 1/10 0.5166 2/20 0.7186 7.7 Others (Green Manuring) ha. 1.00 0.0100 20.00 0.2000 21.00 0.2100 35.00 0.3500 55.00 0.5500 90.00 0.9000 Total 0.1681 0.6016 0.7697 1.1445 1.6666 2.8111 Grand Total (1+2+3+4+5+6+7) 1.5475 6.5998 8.1473 10.9942 17.2209 28.2151

188 Harchandpur(EK) Sabhad (3) Bhatoli (4) Marha Macchi Jhil (5) Unit (6) No./ Name of Head Length/ area Sabhad Bhatoli Marha Macchi Jhil Chakarpur Total Jagatpur ha Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost

1 2 15 16 17 18 19 20 21 22 23 24 25 26 1.Watershed Development Works 1.1 Land Development (Productive use) 1.1.1 Afforestation ha. 2.250 0.7000 0.000 0.0000 1.250 0.3000 0.700 0.0750 1.950 0.3750 0.500 0.0600 1.1.2 Horticulture ha. 3.750 0.9500 0.600 1.6900 2.250 0.5580 1.300 0.2700 3.550 0.8280 1.200 0.2650 1.1.3 Agriculture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 1.1.4 Pasture ha. 2.000 0.5000 0.000 0.0000 0.500 0.1250 0.000 0.0000 0.500 0.1250 0.000 0.0000 1.1.5 Others Sq.mt.- 11000.00 0.6000 0.000 0.0000 4500.00 0.2400 500.00 0.0300 5000.00 0.2700 500.00 0.0300 Total 2.7500 1.6900 1.2230 0.3750 1.5980 0.3550 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 311.276 18.6766 5.6155 0.3370 96.139 5.7684 22.610 1.3565 118.749 7.1249 20.181 1.2110 1.2.2 Peripheral & Margin al Bunding meter/ha 124.510 12.451 2.2462 0.2250 38.456 3.8460 9.004 0.9000 47.460 4.7460 8.072 0.8720 (with sodding)) 1.2.4 Others 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 Total 435.786 31.1276 7.8617 0.5620 134.595 9.6144 31.614 2.2565 166.209 11.8709 28.253 2.0830 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.3.2 Gully plugs No. 5 3.8182 0 0.0000 2 1.5272 1 0.7636 3 2.2908 1 0.7636 1.3.3 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 5 3.8182 0 0.0000 2 1.5272 1 0.7636 3 2.2909 1 0.7636 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.2 Check dams No. 6 4.8720 0 0.0000 2 1.6230 0 0.0000 2 1.6230 0 0.0000 1.4.3 Nallah Bunds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.4 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 6 4.8720 0.00 0.0000 2 1.6230 0.00 0.0000 2 1.6230 0 0.0000

189

1 2 15 16 17 18 19 20 21 22 23 24 25 26 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.2 Check dams No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.3 Nallah Bunds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Total 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.000 0 0.0000 0.0000 Grand Total 42.5678 2.2520 13. 9876 3. 3951 17.3827 3.2016 2. Administrative Cost ha. 622.552 7.4706 11.231 0.1348 192.279 2.3074 45.220 0.5426 237.499 2.8500 40.362 0.4843 3. Monitoring 0.7471 0.0135 0.2307 0.0543 0.2850 0.0484 4.Institution & Capacity Building 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.1 SHG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.2 UG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.3 Formation of Federation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.4 Capacity building No. of Person 625 3.7351 11 0.0674 193 1.1536 46 0.2712 239 1.4248 40 0.2422 5.DPR 0.7471 0.0135 0.2307 0.0543 0.2850 0.0484 Total 12.6999 0.2292 3.9224 0.9224 4.8448 0.8233 6.Livelihood activities for the asset-less persons No. of SHG/ 6.1 Plan for Livelihood activities 3/17 6.7235 2/12 0.1213 3/19 2.076 2/11 0.4884 5/30 2.5644 2/14 0.4359 Person Total 3/17 6.7235 2/12 0.1213 3/19 2.076 2/11 0.4884 5/30 2.5644 2/14 0.4359 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.2 Beekeeping Person 1/5 0.4000 0 0.0000 1/5 0.4000 0 0.0000 1/5 0.4000 0 0.0000 No. of SHG/ 7.3 Poultry Person 1/5 0.2000 1/5 0.0948 1/5 0.2000 0 0.0000 1/5 0.2000 0 0.0000 No. of SHG/ 7.4 Fisheries Person 1/5 0.4000 0 0.0000 1/5 0.4000 0 0.0000 1/5 0.4000 0 0.0000 No. of SHG/ 7.5 Bio-fuel Plantation Person 0 0.0000 0 0.0000 0 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.6 Dairy Person 4/40 3.9706 0 0.0000 1/5 0.5574 1/5 0.3926 2/10 0.9500 1/5 0.3343 7.7 Others (Green Manuring) ha. 250.00 2.500 4.00 0.0400 75.00 0.7500 15.00 0.1500 90.00 0.9000 15.00 0.1500 Total 7.4706 0.1348 2.3074 0.5426 2.8500 0.4843 Grand Total (1+2+3+4+5+6+7) 69.8841 2.7373 22.2934 5.3485 27.6419 4.9451

190

Mau (7) Rathgaon (EK) (8) Sanwaliya (9) Unit No./ Mau Narayanpur Sahar Khizarpur Total Rathgaon Sanwaliya Name of Head Length/ area ha Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost

1 2 27 28 29 30 31 32 33 34 35 36 37 38 1.Watershed Development Works 1.1 Land Development (Productive use) 1.1.1 Afforestation ha. 2.000 0.3750 1.500 0.3300 0.300 0.0450 3.800 0.7500 1.750 0.3750 1.600 0.3300 1.1.2 Horticulture ha. 4.500 1.1000 3.500 0.8700 0.750 0.1400 8.750 2.1100 4.500 1.1000 3.500 0.8700 1.1.3 Agriculture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 1.1.4 Pasture ha. 1.000 0.2500 0.500 0.1250 0.000 0.0000 1.500 0.3750 1.000 0.2500 0.500 0.1250 1.1.5 Others Sq.mt.- 5000.00 0.2700 3000.00 0.1770 500.00 0.0300 8500.00 0.4770 5000.00 0.2700 3000.00 0.1770 Total 1.9950 1.5020 0.2150 3.7120 1.9950 1.5020 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 197.155 11.829 78.679 4.7210 16.126 0.9680 291.960 17.5180 172.550 10.3530 77.609 4.6570 1.2.2 Peripheral & Marginal Bunding meter/ha 78.862 7.8860 31.472 3.1470 6.451 0.6450 69.021 6.9020 31.043 3.1040 (with sodding)) 116.785 11.6780 1.2.4 Others 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 Total 276.017 19.715 110.151 7.8680 22.577 1.6130 408.745 29.1960 241.571 17.2550 108.652 7.7610 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.3.2 Gully plugs No. 5 3.8182 1 0.7636 0 0.0000 6 4.5818 5 3.8182 4 3.0545 1.3.3 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 5 3.8182 1 0.7636 0 0.0000 6 4.5818 5 3.8182 4 3.0545 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.000 0 0.0000 1.4.2 Check dams No. 3 2.4345 1 0.8115 0 0.0000 4 3.2460 2 1.6230 2 1.6230 1.4.3 Nallah Bunds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.4 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 3 2.4345 1 0.8115 0 0.0000 4 3.2460 2 1.6230 2 1.6230

191

2 3 27 28 29 30 31 32 33 34 35 36 37 38 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.2 Check d ams No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.3 Nallah Bunds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Total 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0 000 0.0000 0.0000 0.0000 0.0000 0.0000 Grand Total 27. 9627 10.9451 1.8280 40.7358 24.6912 13.9405 2. Administrative Cost ha. 394.311 4.7317 157.358 1.8883 32.253 0.3870 583.922 7.0070 345.104 4.1412 155.217 1.8626 3. Monitoring 0.4732 0.1888 0.0387 0.7007 0.4141 0.1863 4.Institution & Capacity Building 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.1 SHG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.2 UG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.3 Formation of Federation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.4 Capacity building No. of Person 395 2.3658 160 0.9442 32 0.1935 587 3.5035 347 2.0706 157 0.9312 5.DPR 0.4732 0.1888 0.0387 0.7007 0.4141 0.1863 Total 8.0439 3.2101 0.6579 11.9119 7.0400 3.1664 6.Livelihood activities for the asset-less persons No. of SHG/ 6.1 Plan for Livelihood activities Person 2/13 4.2586 2/13 1.6995 1/11 0.3483 5/37 6.3064 4/21 3.7271 3/18 1.6763 Total 2/13 4.2586 2/13 1.6995 1/11 0.3483 5/37 6.3064 4/21 3.7271 3/18 1.6763 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.2 Beekeeping Person 1/5 0.4000 1/5 0.4000 0 0.0000 2/10 0.8000 1/5 0.4000 0 0.0000 No. of SHG/ 7.3 Poultry Person 2/10 0.4000 1/5 0.2000 2/10 0.2870 5/25 0.8870 2/10 0.4000 1/5 0.2000 No. of SHG/ 7.4 Fisheries Person 1/5 0.4000 0 0.0000 0 0.0000 1/5 0.4000 1/5 0.4000 1/5 0.4000 No. of SHG/ 7.5 Bio-fuel Plantation Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.6 Dairy Person 2/20 1.9817 1/10 0.6883 0 0.0000 3/30 2.6700 2/20 1.5412 1/10 0.6626 7.7 Others (Green Manuring) ha. 155.00 1.5500 60.00 0.6000 10.00 0.1000 225.00 2.2500 140.00 1.4000 60.00 0.6000 Total 4.7317 1.8883 0.3870 7.0070 4.1412 1.8626 Grand Total (1+2+3+4+5+6+7) 44.9969 17.743 3.2212 65.9611 39.5965 20.6458

192 Banthara (10) Belpur Bela (11) Bashai (12) Unit No./ Name of Head Banthara Belpur Bela Kiratpur Total Bashai Length/ area ha Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost 1 2 39 40 41 42 43 44 45 46 47 48 1.Watershed Development Works 1.1 Land Development (Productive use) 1.1.1 Afforestation ha. 1.250 0.3000 1.250 0.3000 1.000 0.0850 2.250 0.3850 0.500 0.0600 1.1.2 Horticulture ha. 3.500 0.8350 2.250 0.5580 1.250 0.2420 3.500 0.8000 0.700 0.1400 1.1.3 Agriculture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 1.1.4 Pasture ha. 1.000 0.2400 0.500 0.1250 0.000 0.0000 0.500 0.1250 0.000 0.0000 1.1.5 Others Sq.mt.- 4500.00 0.2400 4500.00 0.2400 500.00 0.0300 5000.00 0.2700 500.00 0.0300 Total 1.6150 1.2230 0.3570 1.5800 0.2300 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 141.096 8.4650 97.179 5.8300 30.3760 1.8230 127.555 7.6530 16.427 0.9860 1.2.2 Peripheral & Marginal Bunding meter/ha 56.438 5.6440 38.872 3.8870 12.1500 1.2150 51.022 5.1020 6.5708 0.6570 (with sodding)) 1.2.3 Others 0.000 0.0000 0.000 0.0000 0.0000 0.0000 0.000 0.0000 0.000 0.0000 Total 197.534 14.1090 136.051 9.7170 42.5260 3.0380 178.577 12.7550 22.9978 1.6430 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.3.2 Gully plugs No. 5 3.8182 3 2.2909 1 0.7634 4 3.0545 0 0.0000 1.3.3 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 5 3.8182 3 2.2909 1 0.7634 4 3.0545 0 0.0000 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.2 Check dams No. 3 2.4345 2 1.6230 1 0.8115 3 2.4345 0 0.0000 1.4.3 Nallah Bunds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.4 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 3 2.4345 2 1.6230 1 0.8115 3 2.4345 0 0.0000

193 1 2 39 40 41 42 43 44 45 46 47 48 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.2 Check dams No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.3 Nallah Bunds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Total 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Grand Total 21.9767 14.8539 4.9701 19.8244 1.8730 2. Administrative Cost ha. 282.192 3.3863 194.358 2.3323 60.751 0.7290 255.109 3.0613 32.854 0.3943 3. Monitoring 0.3386 0.2332 0.0729 0.3061 0.0394 4.Institution & Capacity Building 0.0000 0.0000 0.0000 0.0000 0.0 000 4.1 SHG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 4.2 UG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 4.3 Formation of Federation 0.0000 0.0000 0.0000 0.0000 0.0000 4.4 Capacity building No. of Person 284 1.6932 196 1.1662 60 0.3645 256 1.5307 33 0.1970 5.DPR 0.3386 0.2332 0.0729 0.3061 0.0394 Total 5.7567 3.9649 1.2393 5.2042 0.6701 6.Livelihood activities for the asset-less persons No. of SHG/ 2/13 3.0477 2/12 2.0990 3/16 0.6561 7/41 2.7551 2/11 0.3548 6.1 Plan for Livelihood activities Person Total 2/13 3.0477 2/12 2.0990 3/16 0.6561 7/41 2.7551 2/11 0.3548 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Person No. of SHG/ 1/5 0.4000 1/5 0.4000 0 0.0000 1/5 0.4000 0 0.0000 7.2 Beekeeping Person No. of SHG/ 1/5 0.2000 1/5 0.2000 1/5 0.2000 2/10 0.4000 1/5 0.2943 7.3 Poultry Person No. of SHG/ 1/5 0.4000 1/5 0.4000 0 0.0000 1/5 0.4000 0 0.0000 7.4 Fisheries Person No. of SHG/ 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 7.5 Bio-fuel Plantation Person No. of SHG/ 2/20 1.2363 1/ 10 0.5323 1/10 0.2790 2/20 0.8113 0 0.0000 7.6 Dairy Person 7.7 Others (Green Manuring) ha. 115.00 1.1500 80.00 0.8000 25.00 0.2500 105.00 1.0500 10.00 0.100 Total 3.3863 2.3323 0.7290 3.0613 0.3943 Grand Total (1+2+3+4+5+6+7) 34.1674 23.2467 7.5945 30.8448 3.2922

194 Pusauli (13) Tajpur Bidhuna(14) Dondapur (15) Alipur (16) Unit Narayanpur No./ Pusauli Total Tajpur Bidhuna Dondapur Palia Name of Head Length/ area Bhanu ha Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost

1 2 49 50 51 52 53 54 55 56 57 58 59 60 1.Watershed Development Works 1.1 Land Development (Productive use)

1.1.1 Afforestation ha. 1.200 0.2550 1.000 0.1500 2.200 0.4050 1.200 0.3000 1.250 0.3300 0.000 0.0000 1.1.2 Horticulture ha. 2.250 0.5700 1.500 0.3120 3.750 0.8820 3.300 0.8380 3.500 0.8700 0.650 0.1630 1.1.3 Agriculture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 1.1.4 Pasture ha. 0.500 0.1250 0.000 0.0000 0.500 0.1250 1.000 0.2500 0.500 0.1250 0.000 0.0000 1.1.5 Others Sq.mt.- 3000.00 0.1770 1000.00 0.0690 4000.00 0.2460 4500.00 0.2400 3000.00 0.1770 0.00 0.0000 Total 1.1270 0.5310 1.6580 1.6280 1.5020 0.1630 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 69.242 4.1540 41.468 2.4880 110.710 6.6420 105.774 6.3460 77.325 4.6390 7.678 0.4610 1.2.2 Peripheral & Marginal Bunding meter/ha 27.697 2.7690 16.587 1.6580 44.284 4.4270 42.309 4.2310 30.930 3.0930 3.071 0.3070 (with sodding)) 1.2.3 Others 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 Total 96.939 6.9230 58.055 4.1460 154.994 11.0690 148.083 10.5770 108.255 7.7320 10.749 0.7680 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.3.2 Gully plugs No. 1 0.7636 1 0.7636 2 1.5272 3 2.2909 1 0.7636 0 0.0000 1.3.3 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 1 0.7636 1 0.7636 2 1.5272 3 2.2909 1 0.7636 0 0.0000 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.2 Check dams No. 1 0.8115 1 0.8115 2 1.6230 2 1.6230 2 1.6230 0 0.0000 1.4.3 Nallah Bunds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.4 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 1 0.8115 1 0.8115 2 1.6230 2 1.6230 2 1.6230 0.00 0.0000

195 1 2 49 50 51 52 53 54 55 56 57 58 59 60 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.2 Check dams No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.3 Nallah Bunds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.4 Others No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Total 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Grand Total 9.6251 6.2521 15.8772 16.1189 11.6206 0.9310 2. Administrative Cost ha. 138.483 1.6618 82.935 0.9952 221.418 2.6570 211.548 2.5386 154.650 1.8558 15.355 0.1843 3. Monitoring 0.1662 0.0995 0.2657 0.2539 0.1856 0.0184 4.Institution & Capacity Building 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.1 SHG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.2 UG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.3 Formation of Federation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.4 Capacity building No. of Person 140 0.8309 85 0.4976 225 1.3285 214 1.2692 155 0.9279 15 0.0922 5.DPR 0.1662 0.0995 0.2657 0.2539 0.1856 0.0184 Total 2.8251 1.6918 4.5169 4.3156 3.1549 0.3133 6.Livelihood activities for the asset-less persons No. of SHG/ 6.1 Plan for Livelihood activities Person 3/19 1.4956 2/12 0.8957 5/31 2.3913 3/17 2.2847 3/16 1.6702 3/19 0.1658 Total 3/19 1.4956 2/12 0.8957 5/31 2.3913 3/17 2.2847 3/16 1.6702 3/19 0.1658 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.2 Beekeeping Person 1/5 0.4000 0 0.0000 1/5 0.4000 1/5 0.4000 0 0.0000 0 0.0000 No. of SHG/ 7.3 Poultry Person 1/5 0.2000 1/5 0.2000 2/10 0.4000 1/5 0.2000 1/5 0.2000 1/5 0.1343 No. of SHG/ 7.4 Fisheries Person 0 0.0000 0 0.0000 0 0.0000 1/5 0.4000 0 0.0000 0 0.0000 No. of SHG/ 7.5 Bio-fuel Plantation Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.6 Dairy Person 1/10 0.5118 1/10 0.4952 2/20 1.0070 1/10 0.6886 1/10 1.0558 0 0.0000 7.7 Others (Green Manuring) ha. 55.00 0.5500 30.00 0.3000 85.00 0.8500 85.00 0.8500 60.00 0.6000 5.00 0.0500 Total 1.6618 0.9952 2.6570 2.5386 1.8558 0.1843 Grand Total (1+2+3+4+5+6+7) 15.6076 9.8348 25.4424 25.2578 18.3015 1.5944

196 Sarai Pratham Unit Babina Sukhchenpur (17) Pasua (18) Bamrauliya (20) No./ (19) Name of Head Length/ area Babina Sukhchenpur Bampur Rampur Total Pasua Sarai Pratham Bamrauliya ha Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost

1 2 61 62 63 64 65 66 67 68 69 70 71 72 1.Watershed Development Works 1.1 Land Development (Productive use)

1.1.1 Afforestation ha. 1.200 0.2550 0.500 0.0600 1.700 0.3150 1.100 0.1500 1.200 0.2550 1.200 0.3300 1.1.2 Horticulture ha. 2.300 0.5700 0.750 0.1400 3.050 0.7100 1.500 0.3120 2.300 0.5700 3.500 0.8700 1.1.3 Agriculture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 1.1.4 Pasture ha. 1.000 0.2500 0.000 0.0000 1.000 0.2500 0.500 0.1250 0.500 0.1250 0.500 0.1250 1.1.5 Others Sq.mt.- 300.00 0.1770 500.00 0.0300 800.00 0.2070 1000.00 0.0690 3000.00 0.1770 3000.00 0.1770 Total 1.2520 0.2300 1.4820 0.6560 1.1270 1.5020 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 72.000 4.3200 17.757 1.0650 89.757 5.3850 43.007 2.5800 65.639 3.9380 75.204 4.5120 1.2.2 Peripheral & Marginal Bunding meter/ha 28.800 2.8800 7.103 0.7100 35.903 3.5900 17.202 1.7200 26.256 2.6260 30.082 3.0080 (with sodding)) 1.2.3 Others 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 Total 100.800 7.2000 24.860 1.7750 125.660 8.9750 60.209 4.3000 91.895 6.5640 105.286 7.5200 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.3.2 Gully plugs No. 2 1.5272 0 0.0000 2 1.5272 1 0.7636 1 0.7636 1 0.7636 1.3.3 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 2 1.5272 0 0.0000 2 1.5272 1 0.7636 1 0.7636 1 0.7636 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.2 Check dams No. 2 1.6230 0 0.0000 2 1.6230 1 0.8115 1 0.8115 1 0.8115 1.4.3 Nallah Bunds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.4 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 2 1.6230 0 0.0000 2 1.6230 1 0.8115 1 0.8115 1 0.8115

197

2 3 61 62 63 64 65 66 67 68 69 70 71 72 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.2 Check dams No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.3 Nallah Bunds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Total 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Grand Total 11.6022 2.0050 13.6072 6.5311 9.2621 10.5971 2. Administrative Cost ha. 144.004 1.7281 35.313 0.4262 179.317 2.1543 86.014 1.0322 131.279 1.5753 150.408 1.8049 3. Monitoring 0.1728 0.0426 0.2154 0.1032 0.1575 0.1805 4.Institution & Capacity Building 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.1 SHG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.2 UG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.3 Formation of Federation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.4 Capacity building No. of Person 145 0.8639 35 0.2131 180 1.0770 87 0.5161 133 0.7877 152 0.9024 5.DPR 0.1728 0.0426 0.2154 0.1032 0.1575 0.1805 Total 2.9376 0.7245 3.6621 1.7547 2.6780 3.0683 6.Livelihood activities for the asset-less persons No. of SHG/ 1.9387 6.1 Plan for Livelihood activities Person 1/5 1.5552 2/12 0.3835 3/17 3/18 0.9290 3/17 1.4178 1/9 1.6244 Total 1/5 1.5552 2/12 0.3835 3/17 1.9387 3/18 0.9290 3/17 1.4178 1/9 1.6244 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.2 Beekeeping Person 1/5 0.4000 0 0.0000 1/5 0.4000 0 0.0000 1/5 0.4000 0 0.0000 No. of SHG/ 7.3 Poultry Person 1/5 0.2000 1/5 0.2000 2/10 0.4000 1/5 0.2000 1/5 0.2000 1/5 0.2000 No. of SHG/ 7.4 Fisheries Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1/5 0.4000 No. of SHG/ 7.5 Bio-fuel Plantation Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.6 Dairy Person 1/10 0.5781 0 0.0000 1/10 0.5781 1/10 0.4822 1/10 0.4753 1/10 0.6049 7.7 Others (Green Manuring) ha. 55.00 0.5500 22.00 0.2262 77.00 0.7762 35.00 0.3500 50.00 0.5000 60.00 0.6000 Total 1.7281 0.4262 2.1543 1.0322 1.5753 1.8049 Grand Total (1+2+3+4+5+6+7) 17.8231 3.5392 21.3623 10.2470 14.9332 17.0947

198

Bhadasiya (21) Bhikhra (22) Indpamau (23) Unit No./ Bhadasiya Newada Malkhan Total Bhikhra Indpamau Name of Head Length/ area ha Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost

1 2 73 74 75 76 77 78 79 80 81 82 1.Watershed Development Works 1.1 Land Development (Productive use) 1.1.1 Afforestation ha. 1.400 0.3300 0.750 0.0750 2.150 0.4050 1.300 0.3300 1.100 0.3000 1.1.2 Horticulture ha. 3.500 0.8700 1.250 0.2420 4.750 1.1120 3.500 0.8700 2.250 0.5580 1.1.3 Agriculture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 1.1.4 Pasture ha. 0.500 0.1250 0.500 0.1250 1.000 0.2500 0.500 0.1250 0.500 0.1250 1.1.5 Others Sq.mt.- 3000.00 0.1770 1000.00 0.0690 4000.00 0.2460 3000.00 0.1770 4500.00 0.2400 Total 1.5020 0.5110 2.0130 1.5020 1.2230 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 75.272 4.5160 35.823 2.1490 111.095 6.6650 79.182 4.7510 94.470 5.6680 1.2.2 Peripheral & Marginal Bunding meter/ha 30.109 3.0110 14.329 1.4330 44.438 4.4440 31.673 3.1670 37.788 3.7790 (with sodding)) 1.2.3 Others 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 Total 105.381 7.5270 50.152 3.5820 155.533 11.1090 110.855 7.9180 132.258 9.4470 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.3.2 Gully plugs No. 1 0.7636 1 0.7636 2 1.5272 1 0.7636 2 1.5272 1.3.3 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 1 0.7636 1 0.7636 2 1.5272 1 0.7636 2 1.5272 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.2 Check dams No. 1 0.8115 1 0.8115 2 1.6230 1 0.8115 2 1.6230 1.4.3 Nallah Bunds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.4 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 1 0.8115 1 0.8115 2 1.6230 1 0.8115 2 1.6230

199 1 2 73 74 75 76 77 78 79 80 81 82 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.2 Check dams No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.3 Nallah Bunds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Total 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Grand Total 10.6041 5.6681 16.2722 10.9951 13.8202 2. Administrative Cost ha. 150.544 1.8065 71.645 0.8597 222.189 2.6662 158.363 1.9004 188.94 2.2673 3. Monitoring 0.1807 0.0860 0.2667 0.1900 0.2267 4.Institution & Capacity Building 0.0000 0.0000 0.0000 0.0000 0.0000 4.1 SHG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 4.2 UG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 4.3 Formation of Federation 0.0000 0.0000 0.0000 0.0000 0.0000 4.4 Capacity building No. of Person 152 0.9032 73 0.4298 225 1.3330 160 0.9503 190 1.1337 5.DPR 0.1807 0.0860 0.2667 0.1900 0.2267 Total 3.0711 1.4615 4.5326 3.2307 3.8544 6.Livelihood activities for the asset-less persons No. of SHG/ 6.1 Plan for Livelihood activities Person 3/16 1.6259 2/14 0.7738 5/30 2.3997 1/8 1.7103 2/10 2.0406 Total 3/16 1.6259 2/14 0.7738 5/30 2.3997 1/8 1.7103 2/10 2.0406 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.2 Beekeeping Person 0 0.0000 0 0.0000 0 0.0000 1/5 0.4000 1/5 0.4000 No. of SHG/ 7.3 Poultry Person 1/5 0.2000 1/5 0.2000 2/10 0.4000 2/10 0.4000 2/10 0.4000 No. of SHG/ 7.4 Fisheries Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.5 Bio-fuel Plantation Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.6 Dairy Person 1/10 1.0065 1/10 0.3797 2/20 1.3862 1/10 0.5004 1/10 0.7173 7.7 Others (Green Manuring) ha. 60.00 0.6000 28.00 0.2800 88.00 0.8800 60.00 0.6000 75.00 0.7500 Total 1.8065 0.8597 2.6662 1.9004 2.2673 Grand Total (1+2+3+4+5+6+7) 17.1076 8.7631 25.8707 17.8365 21.9825

200

Unit Marhokh Mit (24) Roppur S ahar (25) No./ Marhokh Mit Marhokh Hariram Total Roppur Sahar Vimtamau Total Name of Head Length/ area ha Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost

1 2 83 84 85 86 87 88 89 90 91 92 93 94 1.Watershed Development Works 1.1 Land Development (Productive use)

1.1.1 Afforestation ha. 0.200 0.0300 0.600 0.0750 0.800 0.1050 1.150 0.3000 1.150 0.3000 2.300 0.6000 1.1.2 Horticulture ha. 0.600 0.1350 1.300 0.2700 1.900 0.4050 2.250 0.5580 3.400 0.8380 5.650 1.3960 1.1.3 Agriculture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 1.1.4 Pasture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.500 0.1250 1.000 0.2500 1.500 0.3750 1.1.5 Others Sq.mt.- 500.00 0.0300 500.00 0.0300 1000.00 0.0600 4500.00 0.2400 4500.00 0.2400 9000.00 0.4800 Total 0.1950 0.3750 0.5700 1.2230 1.6280 2.8510 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 10.612 0.6367 20.527 1.2320 31.139 1.8687 94.463 5.6670 105.673 6.3400 200.136 12.0070 1.2.2 Peripheral & Marginal Bunding meter/ha 4.245 0.4250 8.211 0.8210 12.456 1.2460 37.785 3.7790 42.269 4.2270 80.054 8.0060 (with sodding)) 1.2.3 Others meter/ha 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 Total 14.857 1.0617 28.738 2.0530 43.595 3.1147 132.248 9.4460 147.942 10.5670 280.190 20.0130 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.3.2 Gully plugs No. 0 0.0000 0 0.0000 0 0.0000 2 1.5272 2 1.5272 4 3.0544 1.3.3 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 0 0.0000 0 0.0000 0 0.0000 2 1.5272 2 1.5272 4 3.0544 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.2 Check dams No. 0 0.0000 0 0.0000 0 0.0000 2 1.6230 2 1.6230 4 3.2460 1.4.3 Nallah Bunds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.4 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 0 0.0000 0 0.0000 0 0.0000 2 1.6230 2 1.6230 4 3.2460

201

1 2 83 84 85 86 87 88 89 90 91 92 93 94 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.2 Check dams No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.3 Nallah Bunds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Total 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Grand Total 1.2567 2.4280 3.6847 13.8192 15.3452 29.1644 2. Administrative Cost ha. 21.224 0.2547 41.054 0.4926 62.278 0.7473 188.926 2.2670 211.345 2.5361 400.271 4.8031 3. Monitoring 0.0255 0.0493 0.0748 0.2267 0.2536 0.4803 4.Institution & Capacity Building 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.1 SHG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.2 UG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.3 Formation of Federation 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 4.4 Capacity building No. of Person 22 0.1273 42 0.2462 64 0.3735 190 1.1336 214 1.2681 404 2.4017 5.DPR 0.0255 0.0493 0.0748 0.2267 0.2536 0.4803 Total 0.4330 0.8374 1.2704 3.8540 4.3114 8.1654 6.Livelihood activities for the asset-less persons No. of SHG/ 6.1 Plan for Livelihood activities Person 2/10 0.2292 2/12 0.4434 4/22 0.6726 2/12 2.0400 2/13 2.2825 4/25 4.3225 Total 2/10 0.2292 2/12 0.4434 4/22 0.6726 2/12 2.0400 2/13 2.2825 4/25 4.3225 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.2 Beekeeping Person 0 0.0000 0 0.0000 0 0.0000 1/5 0.4000 0 0.0000 1/5 0.4000 No. of SHG/ 7.3 Poultry Person 1/5 0.1747 2/10 0.3426 3/15 0.5173 1/5 0.2000 1/5 0.2000 2/10 0.4000 No. of SHG/ 7.4 Fisheries Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.5 Bio-fuel Plantation Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.6 Dairy Person 0 0.0000 0 0.0000 0 0.0000 1/10 0.9170 1/10 1.4861 2/20 2.4031 7.7 Others (Green Manuring) ha. 8.00 0.0800 15.00 0.1500 23.00 0.2300 75.00 0.7500 85.00 0.8500 160.00 1.6000 Total 0.2547 0.4926 0.7473 2.2670 2.5361 4.8031 Grand Total (1+2+3+4+5+6+7) 2.1736 4.2014 6.3750 21.9802 24.4752 46.4554

202 Asjana (26) Rawatp ur (27) Unit No./ Asjana Barkapurwa Hathnapur Total Rawatpur Name of Head Length/ area ha Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost

1 2 95 96 97 98 99 100 101 102 103 104 1.Watershed Development Works 1.1 Land Development (Productive use)

1.1.1 Afforestation ha. 1.250 0.3000 0.600 0.0750 1.200 0.1500 3.050 0.5250 1.100 0.1500 1.1.2 Horticulture ha. 3.750 0.9000 0.750 0.1450 1.400 0.3120 5.900 1.3570 1.900 0.6720 1.1.3 Agriculture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 1.1.4 Pasture ha. 1.000 0.2500 0.000 0.0000 0.000 0.0000 1.000 0.2500 0.000 0.0000 1.1.5 Others Sq.mt.- 4500.00 0.2400 500.00 0.0300 1000.00 0.0690 6000.00 0.3390 1000.00 0.0690 Total 1.6900 0.2500 0.5310 2.4710 0.8910 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 112.729 6.7640 19.250 1.1550 50.276 3.0165 182.255 10.9355 55.920 3.3550 1.2.2 Peripheral & Marginal Bunding meter/ha 45.092 4.5090 7.700 0.7700 20.110 2.0110 72.902 7.2900 22.268 2.2370 (with sodding)) 1.2.3 Others 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 Total 157.821 11.2730 26.950 1.9250 70.386 5.0275 255.157 18.2255 78.188 5.5920 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.3.2 Gully plugs No. 2 1.5272 0 0.0000 1 0.7636 3 2.2908 1 0.7636 1.3.3 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 2 1.5272 0 0.0000 1 0.7636 3 2.2908 1 0.7636 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.2 Check dams No. 2 1.6230 0 0.0000 1 0.8115 3 2.4345 1 0.8115 1.4.3 Nallah Bunds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.4 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 2 1.6230 0.00 0.0000 1 0.8115 3 2.4345 1 0.8115

203

1 2 95 96 97 98 99 100 101 102 103 104 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.2 Check dams No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.3 Nallah Bunds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Total 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Grand Total 16.1132 2.1750 7.1336 25.4218 8.0581 2. Administrative Cost ha. 225.458 2.7050 38.500 0.4620 100.552 1.2066 364.510 4.3736 111.840 1.3421 3. Monitoring 0.2710 0.0462 0.1207 0.4379 0.1342 4.Institution & Capacity Building 0.0000 0.0000 0.0000 0.0000 0.0000 4.1 SHG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 4.2 UG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 4.3 Formation of Federation 0.0000 0.0000 0.0000 0.0000 0.0000 4.4 Capacity building No. of Person 227 1.3524 38 0.2310 100 0.6032 365 2.1866 112 0.6710 5.DPR 0.2710 0.0462 0.1207 0.4379 0.1342 Total 4.5994 0.7854 2.0512 7.4360 2.2815 6.Livelihood activities for the asset-less persons No. of SHG/ 6.1 Plan for Livelihood activities Person 2/10 2.4350 4/20 0.4158 2/14 1.0860 8/44 3.9368 1/15 1.2079 Total 2/10 2.4350 4/20 0.4158 2/14 1.0860 8/44 3.9368 1/15 1.2079 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.2 Beekeeping Person 1/5 0.4000 0 0.0000 0 0.0000 1/5 0.4000 0 0.0000 No. of SHG/ 7.3 Poultry Person 1/5 0.2000 1/5 0.3100 1/5 0.2000 3/15 0.7100 1/5 0.2000 No. of SHG/ 7.4 Fisheries Person 1/5 0.4000 0 0.0000 0 0.0000 1/5 0.4000 0 0.0000 No. of SHG/ 7.5 Bio-fuel Plantation Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.6 Dairy Person 1/10 0.8050 0 0.0000 1/10 0.6066 2/20 1.4116 1/10 0.6921 7.7 Others (Green Manuring) ha. 90.00 0.9000 15.00 0.1520 40.00 0.4000 145.00 1.4520 45.00 0.4500 Total 2.7050 0.4620 1.2066 4.3736 1.3421 Grand Total (1+2+3+4+5+6+7) 25.8526 3.8382 11.4774 41.1682 12.8166

204 Shahoopur |(ALD) Ruru Kala (ALD) Udelapur (ALD) (28) Unit (29) (30) No./ Purwa Bhadauriya Udelapur Total Malikpur Mishripur Kariapur Ruru Name of Head Length/ area Ruru ha Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost Qanty. Cost

1 2 105 106 107 108 109 110 111 112 113 114 1.Watershed Development Works 1.1 Land Development (Productive use) 1.1.1 Afforestation ha. 1.200 0.2550 0.250 0.0300 1.450 0.2850 0.500 0.0600 0.250 0.0300 1.1.2 Horticulture ha. 2.500 0.6150 0.550 0.1300 3.050 0.7450 0.750 0.1400 0.650 0.1350 1.1.3 Agriculture ha. 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 1.1.4 Pasture ha. 0.500 0.1250 0.000 0.0000 0.500 0.1250 0.000 0.0000 0.000 0.0000 1.1.5 Others Sq.mt.- 3000.00 0.1770 500.00 0.0300 3500.00 0.2070 500.00 0.0300 500.00 0.0300 Total 1.1720 0.1900 1.3620 0.2300 0.1950 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 60.107 3.6060 12.772 0.7660 72.879 4.3720 17.500 1.0500 10.182 0.6110 1.2.2 Peripheral & Marginal Bunding meter/ha 24.063 2.4040 5.109 0.5110 29.172 2.9150 7.00 0.7000 4.073 0.4070 (with sodding)) 1.2.3 Others 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 0.000 0.0000 Total 84.170 6.0100 17.881 1.2770 102.051 7.2870 24.50 1.7500 14.255 1.0180 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.3.2 Gully plugs No. 1 0.7636 0 0.0000 1 0.7636 0 0.0000 0 0.0000 1.3.3 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 1 0.7636 0 0.0000 1 0.7636 0 0.0000 0 0.0000 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.2 Check dams No. 1 0.8115 0 0.0000 1 0.8115 0 0.0000 0 0.0000 1.4.3 Nallah Bunds No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 1.4.4 Others No. 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 Total 1 0.8115 0 0.0000 1 0.8115 0 0.0000 0 0.0000

205 1 2 105 106 107 108 109 110 111 112 113 114 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.2 Check dams No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.5.3 Nallah Bunds No. 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Total 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Grand Total 8.7571 1.4670 10.1511 1.9800 1.2130 2. Administrative Cost ha. 120.213 1.4425 25.543 0.3065 145.756 1.7490 35.00 0.4200 20.363 0.2444 3. Monitoring 0.1443 0.0307 0.1750 0.0420 0.0244 4.Institution & Capacity Building 0.0000 0.0000 0.0000 0.0000 0.0000 4.1 SHG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 4.2 UG Formation 0.0000 0.0000 0.0000 0.0000 0.0000 4.3 Formation of Federation 0.0000 0.0000 0.0000 0.0000 0.0000 4.4 Capacity building No. of Person 122 0.7213 25 0.1532 147 0.8745 35 0.2100 20 0.1222 5.DPR 0.1443 0.0307 0.1750 0.0420 0.0244 Total 2.4524 0.5211 2.9735 0.7140 0.4154 6.Livelihood activities for the asset-less persons No. of SHG/ 6.1 Plan for Livelihood activities Person 2/14 1.2983 2/13 0.2759 4/27 1.5742 1/6 0.3780 1/6 0.2199 Total 2/14 1.2983 2/13 0.2759 4/27 1.5742 1/6 0.3780 1/6 0.2199 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.2 Beekeeping Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.3 Poultry Person 1/5 0.2000 1/5 0.2065 2/10 0.4065 1/5 0.2700 1/5 0.1644 No. of SHG/ 7.4 Fisheries Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.5 Bio-fuel Plantation Person 0 0.0000 0 0.0000 0 0.0000 0 0.0000 0 0.0000 No. of SHG/ 7.6 Dairy Person 1/10 0.7425 0 0.0000 1/10 0.7425 0 0.0000 0 0.0000 7.7 Others (Green Manuring) ha. 50.00 0.5000 10.00 0.1000 60.00 0.6000 15.00 0.1500 8.00 0.0800 Total 1.4425 0.3065 1.7490 0.4200 0.2444 Grand Total (1+2+3+4+5+6+7) 13.9503 2.5705 16.4478 3.4920 2.0927

206

Unit Shivpur (ALD) (31) No./ Total Name of Head Shivpur Length/ area ha Qanty. Cost Qanty. Cost 1 2 115 116 11 7 118 1.Watershed Development Works 1.1 Land Development (Productive use)

1.1.1 Afforestation ha. 2.500 0.6000 45.900 9.3050 1.1.2 Horticulture ha. 3.750 0.6000 94.550 24.1470 1.1.3 Agriculture ha. 0.000 0.0000 0.000 0.0 000 1.1.4 Pasture ha. 2.000 0.5000 19.000 4.7400 1.1.5 Others Sq.mt.- 4500.00 0.2400 104300.00 6.0510 Total 1.94 00 44.2430 1.2 Soil & Moisture Conservation 1.2.1 Countour Bunding (with sodding) meter/ha 226.428 13.5860 3086.500 185.3050 1.2.2 Peripheral & Marginal Bunding (with sodding)) meter/ha 90.571 9.0570 1235.282 123.6020 1.2.3 Others 0.000 0.0000 0.000 0.0000 Total 316.999 22.6430 4321.782 308.9070 1.3 Vegetative and Engineering Structure 1.3.1 Earthen Checks No. 0 0.0000 0 0.0000

1.3.2 Gully plugs No. 4 3.0545 66 50.4000 1.3.3 Others No. 0 0.0000 0 0.0000 Total 4 3.0557 66 50.4000 1.4 Water Harvesting Structure (New Created) 1.4.1 Farm ponds No. 0 0.0000 0 0.0000

1.4.2 Check dams No. 3 2.4345 54 43.8240 1.4.3 Nallah Bunds No. 0 0.0000 0 0.0000 1.4.4 Others No. 0 0.0000 0 0.0000

Total 3 2.4345 54 43.8240

207

1 2 115 116 117 118 1.5 Water Harvesting Structure (Renovated) 1.5.1 Farm ponds No. 0.0000 0.0000 0.0000 0.0000 1.5.2 Check dams No. 0.0000 0.0000 0.0000 0.0000 1.5.3 Nallah Bunds No. 0.0000 0.0000 0.0000 0.0000 Total 0.0000 0.0000 0.0000 0.0000 Grand Total 30.084 442.268 2. Administrative Cost ha. 452.856 5.4350 6177.00 74.1240 3. Monitoring 0.5428 7.4124 4.Institution & Capacity Building 0.0000 0.0000 4.1 SHG Formation 0.0000 0.0000 4.2 UG Formation 0.0000 0.0000 4.3 Formation of Federation 0.0000 0.0000 4.4 Capacity building No. of Person 606 2.7187 6360 37.0620 5.DPR 0.5429 7.4124 Total 9.2394 126.0108 6.Livelihood activities for the asset-less persons 6.1 Plan for Livelihood activities No. of SHG/ Person 2/14 4.8921 92/555 66.7116 Total 2/14 4.8921 92/555 66.7116 7.Production system & micro-enterprises 7.1 Sericulture No. of SHG/ Person 0 0.0000 0 0.0000 7.2 Beekeeping No. of SHG/ Person 2/10 0.8000 17/85 6.8000 7.3 Poultry No. of SHG/ Person 3/15 0.6000 47/235 9.8786 7.4 Fisheries No. of SHG/ Person 0 0.0000 10/50 4.7925 7.5 Bio-fuel Plantation No. of SHG/ Person 0 0.0000 0 0.0000 7.6 Dairy No. of SHG/ Person 4/40 2.2350 39/375 28.2347 7.7 Others (Green Manuring) ha. 180.00 1.8000 2320.00 24.8182 Total 5.4350 74.1240 Grand Total (1+2+3+4+5+6+7) 49. 63 97 709.1144

208 CHAPTER-6 CAPACITY BUILDING PLAN

The capacity building of various stack holders will be given very high priority as the watershed is to be developed in participatory mode. Capacity building itiative plays very imporatnt role in human resource development of watershed.

Table 6.1 : List of identified training institutes for capacity building S. Name of Address Designation Type of Area(s) of No. of No. of Allocation to No. Training of the Head institute specialization Training persons to be be made to Institute of Institute assigned trained the institute 1 2 3 4 5 6 7 8 9

1. SIRD/ B.K.T. & Director State Watershed 6 200 B.K.T. development & Concerning District General / Level / Lucknow DIRD management, Principal WCDC/ improved production PIA system, microenterprises, 2. UPLDWR Bhumi Vikas & Jala Principal WCDC/ Livelihood 4 400 Beli Kalan Sansadhan Training Secretary, activities for Lucknow PIA institute, Belikala, LDWR landless peoples Lucknow

3. Agri. & C.S.A. & Tech. Vice WCDC/ 10 1000 Kanpur Tech. University, Kanpur Chancellor PIA University & Concening K.V.K.

Note-Other all institution as identify by S.L.N.A. for Livelihood / Micro Enterprises and other Activities accroding to need in Selected Project Areas.

209 Table 6.2 : Training to stakeholders on participatory watershed management

Sl. Client Title of the programme/ Objectives Coverage/topics Training Training No. Group duration/ time methadology Institute

1 2 3 4 5 6 7

1. WDT Orentation, Planning and To Strengthen and Natural Resource Lectures, videos SIRD /DIRD Member Implementation of IWMP update the skill of Management and visits to /RIRD Project (3 day) WDT member for Livelihood option for successful better planning landless and marginal wateshed management and farmers, Improved executing the project Agriculture production system

2. WC Member Orentation, Planning and Orentation and NRM Production Lectures, videos SIRD / CSA implementation of IWMP strengthening of system, livelihood and and visits to /UPLDWR Project (3day) Maintaining knowledge and skills Account/ledger successful the record of expenditure and of rural peoples keeping and its wateshed preparing budget. maintenance

3. UGs / SHGs Orentation of Agriculture livelihood & micro Integrated crop Lectures, videos CSA, Kanpur & Member Production system and enterprises managemnt in pulses, and field visits of other institutions specialized training for SHGs improvement in Project crereals, oilseeds, specifis subject as identified by (3day) Areas vegetables, orchards require S.L.N.A. and small scale projects.

4. PIA Member Orentation, Planning, design To Strengthening and Natural Resource Lectures, videos SIRD / CSA and implementation of updating the skill and Management and field visits watershed development knowledge Livelihood option for works, Natural Resource landless and marginal Management, Maintenance of farmers, Improved account records and prearing Agriculture budget, production system

210 Table. 6.3 : Capacity Building Annual Action Plan

Physical & Financial Planning Total Total No. S. Stake of Ist Year IInd Year IIIrd Year IVth Year No. Holders persons/ No. of Phy. Amt. member No. of No. of No. of No. of Trgs. Phy. Amt. Phy. Amt. Phy. Amt. Phy. Amt. Trgs Trg. Trgs. Trgs.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

SLNA - - - 1.582 - - 0.741 ------2.323

WCDC 9 - - 3.705 - - 1.853 - - 1.112 - - - - - 6.670

1. PIA 22 22 1 0.20 88 4 0.80 22 1 0.20 22 1 0.20 154 7 1.400

2. WDT 4 4 1 0.04 20 5 0.20 4 1 0.04 4 1 0.04 32 8 0.320

3. WC 310 310 1 1.60 620 2 3.20 300 1 1.55 300 1 1.55 1530 5 7.900

4. SHG 800 800 - 0.00 400 1 2.00 400 1 2.00 400 1 2.00 2000 3 6.000

5. UG 500 500 - 0.00 300 1 1.50 300 1 1.50 300 1 1.50 1400 3 4.500

6. Other Specify 250 250 1 2.50 400 1 2.00 400 1 2.00 280 1 1.447 1330 4 7.947

Total 1986 1986 4 4.34 1828 14 9.70 1426 6 7.29 1306 6 6.737 6546 30 28.067

Grand Total 1986 1986 4 4.34 1828 14 9.70 1426 6 7.29 1306 6 6.737 6546 30 37.06

211

CHAPTER-7 PHASING OF PROGRAMME AND BUDGETING

7. 1 Monitoring and Evaluation Monitoring of the project will be done at each stage and it will be carried out for both, process and outcome. Some community members will be trained and will be involved in participatory monitoring of various parameters and processes and the crop yields. The interventions, expenditure and other information will be displayed in the micro-watershed through wall writings. Besides trained community members, PIA/DWDU will also monitor the physical and financial progress of watershed development programme. Frontier technologies viz. GIS and Remote Sensing techniques will be used by the PIA/DWDU for monitoring and evaluation. The PIA shall submit quarterly progress reports (countersigned by the Watershed Committee (WC) President) to the DWDU for further submission to the SLNA. Sustainable and unbiased monitoring will be ensured by involving an independent agency. About 1 per cent of the total budget will be used on this activity.

Plan for Evaluation Watershed development activities bring about both tangible and intangible benefits. In order to quantify the benefits, impact analysis has been proposed.

Theme It is presumed that as a consequence of watershed development activities there will be noticeable change in socio-economic status of inhabitants, cropping intensity, ground water recharge, crop diversification, fuel, fodder and small timber availability, livestock composition and milk production, etc. These indicators can be gauged over bench mark data both at the beginning and at the end of the project within the watershed.

Observations The following indicators will be taken into account for quantitative and qualitative assessment. For the purpose, detailed questionnaires will be prepared and field observations will be carried out. • Duration of availability of drinking water/irrigation and groundwater recharge • Irrigation frequency and area under irrigation • Changes in cropping pattern and cropping systems in the farmers fields along with productivity and incomes • Soil health • Satellite monitoring for vegetation cover and other parameters • Fuel, fodder and small timber availability • Livestock composition and productivity • Periodic pest and disease monitoring will be done in major crops

212 • Socio-economic aspects including resource inventory • Following indices will also be worked out as qualitative indicators of the watershed development: • Land Improvement Index (LII) • Crop Diversification Index (CDI) • Cultivated Land Utilization Index (CLUI) • Crop Fertilization Index (CFI) • Induced Watershed Eco-Index (IWEI) The concurrent and post-project monitoring and evaluation would be conducted to assess the status of watershed related interventions. It will be done by an independent agency having similar experiences. About 1 per cent of the total budget will also be used on evaluation.

7.2 Annual Action Plan (AAP)

Physical and financial targets and outlays and their year wise break ups are given Table 7.1. Year wise financial phasing for the budget available (Rs. 741.240 lakh) with IWMP-I, district Auraiya is given in Table 7.2.

Table 7.1: Physical, financial targets, outlays and their year wise breakups of IWMP-I, Auraiya S. Name of Items Unit First Year Seecond year Third Year Fourtth Year Total No. 2010-11 2011-12 2012-13 2013-14 Phy. Finc. Phy. Finc. Phy. Finc. Phy. Finc. Phy. Finc. 1 2 3 4 5 6 7 8 9 10 11 12 13 1. Admin. 0.000 14.820 0.000 40.014 0.000 19.290 0.000 0.000 0.000 74.124 2. Monitoring 0.000 1.482 0.000 2.964 0.000 2.964 0.000 0.000 0.000 7.410 3. Evaluation 0.000 2.223 0.000 2.594 0.000 2.593 0.000 0.000 0.000 7.410 4. E.P.A No. 27 29.640 0.000 0.000 0.000 0.000 0.000 0.000 27 29.640 5. I. & C.B. No. 1986 22.230 1828 11.115 2732 3.705 0.000 0.000 6546 37.050 6. D.P.R. Preparation No. 1 7.410 0.000 0.000 0.000 0.000 0.000 0.000 1 7.410 7. W.D.W. ha. 827.000 55.784 3347.000 224.894 2003.000 134.498 6177.00 415.176 8. Livelihood Activities No. 18 7.410 90 37.050 48 22.230 156 66.690 9. Prod. System & M.E. ha. 0.000 0.000 16.700 7.410 116.90 51.870 33.400 14.820 167.00 74.100 10. Consolidation & withdrawal 0.000 0.000 0.000 0.000 0.000 0.000 0.000 22.230 0.000 22.230 - 133.589 - 296.401 - 251.970 - 59.280 - 741.240

213 Table 7.2: Details of proposed watershed wise convergence in project : Rs. in Lac.

S.No. Name of Microwatershed and Treatable Project From Convergence %age of code Area Cost IWMP from Covergence in ha. (WDW) MNREGA Fund

1 2 3 4 5 6 7

1 Sabhad (2C4B5a4d) 490.752 40.1120 32.9800 7.1320 21.63

2 Mau (2C4B5a4c) 897.504 67.0560 60.3120 6.7440 11.18 3 MarhaMacchiJhil (2C4B5a4b) 516.484 36.5790 34.7080 1.8710 5.39 4 Belpur Bela (2C4B5a4a) 290.271 23.3270 19.5060 3.8210 19.59 5 Banthara (2C4B5a2d) 693.288 47.1350 46.5890 0.5460 1.17 6 Dondapur (2C4B5a2c) 462.851 31.9580 31.1040 0.8540 2.75 7 BabinaSukhchenpur (2C4B5a1d) 310.903 21.4830 20.8920 0.5910 2.83 8 Bhadasiya (2C4B5a1c) 745.846 51.5760 50.1210 1.4550 2.90 9 Indpamau (2C4B5a1b) 653.883 45.2480 43.9400 1.3080 2.98 10 Asjana (2C4B5a1c) L 346.601 23.9560 23.2920 0.6640 2.85 11 SaraiPratham (2C4B5a1d) L 768.617 53.8280 51.6510 2.1770 4.21 Total 6177.00 442.258 415.095 27.1630 6.54

214

CHAPTER ‐8

CONSOLIDATION AND WITHDRAWAL STRATEGY

8. Consolidation and Withdrawal Strategy

Success of the programme depends on various watershed interventions and sustainability can only be achieved through active participation of community. It will be on capacity building and empowerment of stakeholders. The WC, SHGs, UGs etc. will be on established, trained and strengthened to continiue development after withdrawal of PIA. By building economic activities through CBOs community participation will be sustained. The PR&D approach alongwith demand driven interventions will reduce dependency on subsidies. Contribution from the community will be ensured for the entire acitivities to develop sense of belongingness and the contributions will be deposited to the account of watershed development fund (W.D.F.). It will also be strengthening through donations from the individuals and institutions and the CBOs will be trained to run watershed as business model on sustainable basis. The tangible economic benefits alongwith empowerment by PIA will empower the CBOs to develop and sustain the watershed acitivities after withdrawal of the PIA. Community organization will withdraw the money from the WDF to maintain the assets created during the implementation phase.

The consolidation phase will also include: ‐‐‐

1. To prepare the project completion report. 2. Documentation of success stories. 3. Making films, leaflets, bulletins and the lessons learnt. 4. The expenditure will be done as per the common guidelines for watershed development projects-2008. 5. The completion report will reflect the development on following aspects: - a. Productivity enhancement (increased in total productivity, seed replacement, farm mechanization, resources use and opertional efficiency) b. Nutritional Security (Production of diverse food commodities). c. Risk minimization (Integrated farming system, water harvesting and protected cultivation, value addition and improved marketing). d. State of Environment (Improvement in vegetative cover, hydrology and adoption of IPNM). d. Profitability (Loss preventing and cost reducing measures, value addition and agro-processing) e. Livelihood security (skill enhancement capacity building, increased employment in agriculture and allied enterprises, reduction in drudgery of farm women and aout migration).

215 CHAPTER ‐9

EXPECTED PROJECT OUTCOME

9.1 Employment Generation and Checking Migration

Employment has always been a problem in the village. The principal occupations of the people are dry land agriculture, animal husbandry and casual labor work. However, rain fall being very limited and erratic, agriculture suffers, i.e. at best they can take only a single crop, which keeps them partially engaged for about 4 months a year. Lack of fodder makes animal husbandry very difficult too. So, animal husbandry does not keep them engaged full time. Thus the people mainly depend upon casual labor, either in the village itself or outside it.

The project plans for creation of both wage employment and self employment opportunities. Wage employment would be created by engaging people in watershed development works. Self employment would be created by providing the people with cash support in the form of direct livelihood activities like agro based activities and microenterprises. It will be very effective for checking the migration of rural peoples.

9.2: Other expected outcome

Table 9.1: Expected Benefits:

S.No. Particulars of Items Unit Pre Execution Post Execution

1 2 3 4 5

1. Improvement of Ground water table GBL/M 12.50 11.50

2. Availability of Quality Drinking Water Month/Year 10 Month 12 Month

3. Increase in Cultivated Area ha. +20%

4. Increase in irrigated area ha. 730.00

5. Increase in cropping intensity % 134 157 (Approximate)

6. Increase in production q/ha. 11.25 14.75

7. Increase in area under horticulture ha. 135.20 285.20

216

S.No. Particulars of Items Unit Pre Execution Post Execution

1 2 3 4 5

8. Increase in vegetative cover ha. 198.30 735.20

9. Increase in fuel wood % - +15-20%

10. Increase in area under fodder ha. - +15-20%

11. Increase in milk production Ltr/year 584000 700800

12. Employment Generation M days/year 105 130 (Approximately)

13. Detension of Run off cumec/ha./year 48 25

14. Reduction in Soil loss t/ha./year 20 11

15. Income % +30%

217

ANNEXURE-I (PARAMETERS)

Sr. No. Name of Soil Conservation measures & code Specification Remarks

Top Width (m) Base(m) Height(m) Cross Section

1 2 3 4 5 6 7

1- Countour Bund CB 0.50 2.30 0.60

2- Marginal Bund MB 1.00 4.75 1.25

3- Peripheral Bund PB 1.00 4.75 1.25

4- Earthen Check Dam ECD 3.00 15.00 3.00

5- Check Dam CD 3.00 15.00 3.00

6- Gully plugs GP 3.00 15.00 3.00

7- Afforestation AFF Escatered and block plantation

8- Drop spill way DSW As per Design

9- Chute outlet CHT As per Design

10- Hume pipe outlet HMP As per Design

218

ANNEXURE-II Table : Contribution to watershed Development Fund (WDF)

(Rs. in Lac)

S.No. Name of W.C. Area Total Amount WDW (56%) Contribution to WDF Remarks 1 2 3 4 5 6 7 1. Badin (E.K.) 64.143 7.697 4.310 0.237 2. Gura 234.260 28.111 15.742 0.866 3. Sabhad 622.552 74.706 41.835 2.301 4. Bhatoli 11.231 1.347 0.7547 0.042 5. Marha Macchi Jhil 237.499 28.500 15.960 0.878 6. Harchandpur (E.K.) 40.362 4.843 2.7123 0.149 7. Mau 583.922 70.070 39.240 2.158 8. Rathgaon (E.K.) 345.104 41.412 23.191 1.276 9. Sanwaliya 155.217 18.626 10.431 0.574 10. Banthara 282.192 33.863 18.963 1.043 11. Belpur Bela 255.109 30.613 17.143 0.943 12. Bashai 32.854 3.942 2.208 0.121 13. Pusauli 221.418 26.570 14.879 0.818 14. Tajpur Bidhuna 211.548 25.386 14.216 0.782 15. Dondapur 154.650 18.558 10.392 0.572 16. Alipur 15.355 1.1843 1.032 0.057 17. Babina Sukhchenpur 179.517 21.542 12.064 0.664 18. Pasua 86.014 10.322 5.780 0.318 19. Sarai Pratham 131.279 15.753 8.822 0.485 20. Bamrauliya 150.408 18.049 10.107 0.556 contd.....

219 1 2 3 4 5 6 7 21. Bhadasiya 222.189 26.662 14.931 0.821 22. Bhikhra 158.363 19.004 10.642 0.585 23. Indpamau 188.940 22.673 12.697 0.698 24 Marhokh Mit 62.278 7.473 4.185 0.230 25 Rooppur Sahar 400.271 48.033 26.898 1.479 26. Asjana 364.510 43.741 24.495 1.347 27. Rawatpur 111.840 13.420 7.516 0.413 28. Udelapur (ALD) 145.756 17.490 9.795 0.539 29. Shahoopur (ALD) 35.000 4-200 2.352 0.129 30. Ruru Kala (ALD) 20.363 2-444 1.368 0.075 31 Shivpur (ALD) 452.856 54.343 30.433 1.674 Total 6177.000 741-240 415.094 22.830

220 ANNEXURE-III

Table. Livelihood Action Plan for Landless/Assetless

(Rs. in Lac)

S. Name & Code MWS No. of Activity Proposed Cost per Total SHG Share Release Amt. Proposed date for Remarks N0. Unit unit Cost from Project activity (start) Fund 1 2 3 4 5 6 7 8 9 1 Sabhad (2C4B5a4d) 8 Dairy 0.500 4.000 1.098 2.902 April 2012 10 Gotary 0. 200 2.000 1.000 1.000 April 2012 4 Tailoring 0. 200 0.800 0.400 0.400 April 2012 2 Carpentry 0. 300 0.600 0.300 0.300 April 2012 10 Rop e Making 0. 100 1.000 0.500 0.500 April 2012 4 General Merchant Shop 0.100 0.400 0.200 0.200 April 2012 Total 38 3.498 5.302 2 Mau (2C4B5a4c) 16 Dairy 0.500 8.000 3.000 5.000 April 2012 20 Gotary 0.200 4.000 1.760 2.240 April 2012 8 Tailoring 0.200 1.600 0.800 0.800 April 2012 2 Carpentry 0.300 0.600 0.300 0.300 April 2012 16 Rope Making 0.100 1.600 0.800 0.800 April 2012 11 General Merchant Shop 0.100 1.100 0.550 0.550 April 2012 Total 73 7.21 0 9.690 3 MarhaMacchiJhil (2C4B5a4b) 8 Dairy 0.500 4.000 1.098 2.902 April 2012 10 Gotary 0.200 2.000 0.727 1.273 April 2012 4 Tailoring 0.200 0.800 0.400 0.400 April 2012 2 Carpentry 0.300 0.600 0.300 0.300 April 2012 10 Rope Making 0.100 1.000 0.500 0.500 April 2012 4 General Merchant Shop 0.100 0.400 0.200 0.200 April 2012 Total 38 3.225 5.573 4 Belp ur Bela (2C4B5a4a) 4 Dairy 0.500 2.000 0.568 1.432 April 2012 15 Gotary 0.200 3.000 1.500 1.500 April 2012 2 Rope Making 0.100 0.200 0.100 0.100 April 2012 2 General Merchant Shop 0.100 0.200 0.100 0.100 April 2012 Total 23 2.268 3.132

221

S. Name & Code MWS No. of Activity Proposed Cost per Total SHG Share Release Amt. Proposed date for Remarks N0 Unit unit Cost from Project activity (start) . Fund 1 2 3 4 5 6 7 8 9 5 Banthara (2C4B5a2d) 10 Dairy 0.500 5.000 1.800 3.200 April 2012 20 Gotary 0.200 4.000 1.000 3.000 April 2012 2 Tailoring 0.200 0.400 0.200 0.200 April 2012 2 Carpentry 0.300 0.600 0.300 0.300 April 2012 10 Rope Making 0.100 1.000 0.462 0.538 April 2012 5 Gene ral Merchant Shop 0.100 0.500 0.250 0.250 April 2012 Total 49 4.012 7.488 6 Dondapur (2C4B5a2c) 5 Dairy 0.500 2.500 0.700 1.800 April 2012 20 Gotary 0.200 4.000 1.025 2.795 April 2012 4 Rope Making 0.100 0.400 0.100 0.300 April 2012 2 General Merchant Shop 0.100 0.200 0.100 0.100 April 2012 Total 31 1.925 4.995 7 BabinaSukhchenpur (2C4B5a1d) 4 Dairy 0.500 2.000 0.568 1.432 April 2012 15 Gotary 0.200 3.000 1.478 1.522 Ap ril 2012 2 Rope Making 0.100 0.200 0.100 0.100 April 2012 2 General Merchant Shop 0.100 0.200 0.100 0.100 April 2012 Total 23 2.246 3.352 8 Bhadasiya (2C4B5a1c) 10 Dairy 0.500 5.000 1.237 3.763 April 2012 20 Gotary 0.200 4.000 1.000 3.000 April 2012 2 Tailoring 0.200 0.400 0.200 0.200 April 2012 2 Carpentry 0.300 0.600 0.300 0.300 April 2012 10 Rope Making 0.100 1.000 0.462 0.538 April 2012 5 General Merchant Shop 0.100 0.500 0.250 0.250 April 2012 Total 49 3.449 8.051

222

S. Name & Code MWS No. of Activity Proposed Cost per Total SHG Share Release Amt. Proposed date for Remarks N0 Unit unit Cost from Project activity (start) . Fund 1 2 3 4 5 6 7 8 9 Indpamau (2C4B5a1b) 10 Dairy 0.500 5.000 1.800 3.200 April 2012 9 20 Gotary 0.200 4.000 1.425 2.575 April 2012

2 Tailoring 0.200 0.400 0.200 0.200 April 2012

2 Carpentry 0.300 0.600 0.300 0.300 April 2012

10 Rope Making 0.100 1.000 0.462 0.538 April 2012

5 General Merchant Shop 0.100 0.500 0.250 0. 250 April 2012

Total 49 4.437 ` 7.063

Asjana (2C4B5a1c) L 4 Dairy 0.500 2.000 0.568 1.432 April 2012 10 15 Gotary 0.200 3.000 1.088 1.912 April 2012

2 Rope Making 0.100 0.200 0.100 0.100 April 2012

2 General Merchant Shop 0.100 0.200 0.100 0.100 April 2012

Total 23 1.856 3.742

SaraiPratham (2C4B5a1d) L 10 Dairy 0.500 5.000 0.967 4.033 April 2012 11 20 Gotary 0.200 4.000 1.000 3.000 April 2012

2 Tailo ring 0.200 0.400 0.200 0.200 April 2012

2 Carpentry 0.300 0.600 0.300 0.300 April 2012

10 Rope Making 0.100 1.000 0.462 0.538 April 2012

5 General Merchant Shop 0.100 0.500 0.250 0.250 April 2012

Total 49 3.179 8.321

Grand Total 445 37.395 66.709

223

MAPS

224 225

226

227 228

229

230

231

232 233

234

235 236

237

238

239 240 241 242 243

244

245

246

247

248 249 250 251

252 253 254

255

256

257 258

259 260

261 262 263 264

265 266

267 268 269

270

271 272

273 274 275

276

277

278

279

280

281

282

283