PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

FORM I

I. BASIC INFORMATION

S. Item Details No 1. Name of the project/s Proposed construction of Panimalar Medical College and Research Institute at Survey Numbers 11 & 12 etc., of Nazarathpettai village, Taluk, district by M/s. Jaisakthi Educational Trust. 2. S.No. in the schedule The project is categorized under Schedule 8 (a) “Building and Large Construction projects” of EIA Notification 2006 and its subsequent amendment 3. Proposed capacity / Proposed Built-up area is 77,057.85 area/length/tonnage to be Sq.m. handled/command area/lease Building wise area details are given in area/number of wells to be drilled the Conceptual Plan 4. New/Expansion/Modernization New 5. Existing Capacity/ Area etc. Nil 6. Category of Project i.e. ‘A’ or ‘B’ Category B2 7. Dose it attract the general condition? No If yes, please specify. 8. Dose it attract the specific condition? Not Applicable If yes, please specify. 9. Location Plot/Survey/ Khasra. No 11, 12, 13, 21, 22, 23, 24pt, 25pt, 26, 27/1(pt), 27/2(pt), 28/1(pt), 28/2(pt), 29/1(pt), 29/2(pt), 38/1(pt), 39/1(pt), 39/2(pt), 41/1, 41/2(pt), 42, 43, 44, 98, 100, 101, 102, 103, 106 and 108 Village Taluk Poonamallee District Thiruvallur State 10. Nearest railway station/airport along Railway Station with distance in Km. - 7 km (NNW) Tiruninravur - 9.1 km (NW) Airport International Airport - 10.3 km (SW) 11. Nearest town, city, district - 1.4 km (SW),

1 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

headquarters along with distance in Poonamallee- 3.3 km (SE) Km. Nazarathpet - 1.1 km (S) 12. Village Panchayats, Zilla parished, Poonamallee Panchayat Union municipal corporation, local Panchayat Union Office, 1, New body(complete postal address with Building, Trunk Road, Poonamallee, telephone nos. to be given) Chennai, 600056 Telephone No: 044-26495686 13. Name of the applicant M/s. Jaisakthi Educational Trust 14. Registered address 23, 2nd Street, Railway Colony, Nelson Manickam Road, , Chennai, Tamil Nadu 600029 15. Address for correspondence Name Mr.C. Sakthi Kumar Designation (Owner/Partner/CEO) Trustee Address Bangalore Trunk Road, Varadharajapuram, Nazarethpettai, Poonamallee, Chennai Pin Code 600123 E-Mail [email protected] Telephone/ Mobile No 044-26490202, 044-23741289 Fax No 044-26490101, 044-23742744 16. Details of Alternative Sites Examined, No alternative sites examined if any, location of these sites should be shown on a Topo sheet. 17. Interlinked Projects Not Applicable 18. Whether separate application of Not Applicable interlinked project has been submitted? 19. If yes, date of submission Not Applicable 20. If no, reason Not Applicable 21. Whether the proposal involves No approval / Clearance under the following acts: if yes, details of the same and their status to be given. (a)The Forest (Conservation) Act, 1980? (b)The Wildlife (Protection) Act, 1972? (c)The C.R.Z Notification, 1991? 22. Whether there is any government No order/ Police relevant/ relating to the site? 23. Forest land involved (hectares) No 24. Whether there is any litigation No pending against the land/ or land in

2 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

which the Project is proposed to be set up? (a) Name of the Court (b) Case No. (c) Order/ directions of the Court, if any And its relevance with the proposed Project

(II) ACTIVITY 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, and the like) Details thereof (with Information/Checklist approximate quantities /rates, S.No. Yes/No confirmation wherever possible) with source of information data 1.1 Permanent or temporary No There will not be any change in the change in land use, land land use, land cover or topography cover or topography as the site is categorized as including increase intensity Institutional & Primary Residential of land use (with respect to Use Zone as per the Development local land use plan) control rules of CMDA. 1.2 Clearance of existing land, No The proposed expansion activities vegetation and Buildings? will be carried out in the vacant land. So there will not be any major clearance activities, no cutting of trees & vegetation except those minor shrubs & weeds clearing. 1.3 Creation of new land uses? No Land use of the proposed site comes under Primary Residential Use Zone and is permitted at the proposed site as per the regulations of CMDA (Refer Annexure I) 1.4 Pre-construction Yes Geo technical investigation has investigations e.g. Bore been done to find the suitability of Houses, Soil testing? soil for providing for adequate foundations for the proposed structure (Refer Annexure V) 1.5 Construction works? Yes Construction of various buildings will be done systematically, with economy of materials and with due

3 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

care on environmental protection. 1.6 Demolition works? No No demolition works will be carried out as the land is vacant. 1.7 Temporary sites used for Yes Inside the proposed site, a small construction works or area will be utilized temporarily for housing of construction construction of sheds for the workers? workers and materials. Water supply and sanitation facilities will be provided for them. Mostly workers will be deployed from local area only. 1.8 Above ground buildings, Yes Excavation works will be carried structures or earthworks out for foundation of the including linear structures, structures. Later on, the cut and cut and fill or excavations fill process will be required to the minimum extent for leveling. 1.9 Underground works mining No No underground works will be or tunneling? required. 1.10 Reclamation works? No Only levelling of ground if required. 1.11 Dredging? No No need for dredging 1.12 Off shore structures? No Not required 1.13 Production and No It’s a construction project. Hence manufacturing processes? not applicable 1.14 Facilities for storage of No Temporary sheds will be goods or materials? constructed for the storage of cement, sand and other materials during construction phase. 1.15 Facilities for treatment or Yes Sewage generated shall be treated disposal of solid waste or in STP of capacity 550 KLD. The liquid effluents? treated wastewater will be reused for toilet flushing, HVAC and greenbelt development. There will be no excess treated sewage. Municipal Solid Waste will be collected, Segregated, treated and disposed to authorized recyclers. 1.16 Facilities for long term No There is no residential facility for housing of operational operational workers as they will be workers? deployed from local area. 1.17 New road, rail or sea traffic No The existing road network is during Construction or sufficient for connectivity of the operation? site. 1.18 New road, rail, air, No The existing infrastructure will be waterborne or other made use during construction and

4 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

transport infrastructure operation phase. including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of No As construction works will be existing transport routes or within a specified area, there is no infrastructure leading to need for closure or diversion of changes in Traffic existing transport routes. The movements? existing transport infrastructure will be made use. 1.20 New or diverted No No new or diversion transmission transmission lines or lines & pipelines are required for pipelines? this project. 1.21 Impoundment, damming, No There will not be any alteration in culverting, realignment or the hydrology of the watercourses other changes to the or aquifers due to the proposed hydrology of watercourses or project. aquifers? 1.22 Stream crossings? No No Stream crossings 1.23 Abstraction or transfers of No No Ground water shall be water form ground or abstracted. Additional quantity of surface waters? water will be sourced from Local body (Poonamallee Panchayat Union) 1.24 Changes in water bodies or No There shall be no change in water land surface affecting bodies or the land surface which drainage or runoff? affect the drainage or runoff. 1.25 Transport of personnel or No Transport of personnel or materials for construction, construction materials during operation or construction phase and operation decommissioning? phase will be through existing roads. 1.26 Long-term dismantling or No No long term works involved in the decommissioning or proposed activity restoration works? 1.27 Ongoing activity during No Only temporary thatched sheds decommissioning which will be built for storing cement and could have an impact on the other materials. So there will be no environment? decommissioning works. 1.28 Influx of people to an area No During construction period either temporarily or workers will be deployed locally. permanently? 1.29 Introduction of alien No No such alien species are species? envisaged

5 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

1.30 Loss of native species or No No loss of native species will occur genetic diversity? as the site is plain 1.31 Any other actions? No Only eco-friendly activities like tree plantation will be undertaken

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non- renewable or in short supply) Details thereof (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 2.1 Land especially undeveloped No There is no agricultural land. or agricultural land (ha) 2.2 Water (expected source & Yes Total water Requirement 601 KLD competing users) unit: KLD of which recycled water for flushing (210 KLD), HVAC (261 KLD) and Green belt development (45 KLD) will be made available through in-house STP. Fresh water requirement of 391 KLD shall be met by local body. 2.3 Minerals (MT) No No usage of minerals is envisaged. 2.4 Construction material - Yes Cement - 6,000 Bags stone, aggregates, sand/soil Steel - 8,770 MT (expected source - MT) Sand - 12,000 cum Brick - 45,323 sq.m 2.5 Forests and timber (source - No Usage of timber will be minimal MT) 2.6 Energy including electricity Yes Electricity will be availed from and fuels (source, competing TANGEDCO. Total Electric load users) Unit: fuel (MT), energy for the proposed project is 3560 (MW) KVA. (Refer section 3.9)

2.7 Any other natural resources No There is no need for other natural (use appropriate standard resources units)

6 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health Details there of (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 3.1 Use of substances or No No such materials will be required materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of No There will not be any occurrence disease or affect disease of diseases as our activities are vectors (e.g. insect or water confined to construction areas borne diseases) only 3.3 Affect the welfare of people No Employment will be given to local e.g. by changing living people thus the living standards conditions? of the people will get improved. 3.4 Vulnerable groups of people No There is no vulnerable group of who could be affected by the people who could be affected by project e.g. hospital patients, the project. children, the elderly etc., 3.5 Any other causes No Nil

4. Production of solid wastes during construction or operation or decommissioning (MT/month) Details thereof (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 4.1 Spoil, overburden or mine No No Spoil, overburden or mine wastes wastes 4.2 Municipal waste (domestic Yes The quantity of municipal solid and or commercial wastes) waste generated from the proposed project will be 1944 kg/day (Refer section 3.7) 4.3 Hazardous wastes (as per Yes The quantity of Hazardous waste Hazardous Waste generated from the proposed Management Rules) project (Refer section 3.7)  DG Filters & filter material - 0.2 TPA (Disposal through TSDF

7 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

facility Gummudipoondi)  Used oil - 0.15 TPA (Disposed to TNPCB/CPCB authorized re- processors) 4.4 Other industrial process No Not envisaged wastes 4.5 Surplus product No Not applicable since this is construction project 4.6 Sewage sludge or other Yes STP sludge of 74 kg/day will be sludge from effluent used as manure for greenbelt treatment development ETP sludge of 1.2 ton/annum will be collected and disposed to TSDF Authorized Recyclers 4.7 Construction or demolition Yes Construction and demolition wastes wastes will be used in land filling and in road pavements in the surrounding low lying areas. Wood and paper waste will be disposed through recyclers 4.8 Redundant machinery or No Most of the equipments used equipment during construction phase will be hired 4.9 Contaminated soils or other No There is no source for materials contamination of soils or other materials. 4.10 Agricultural wastes No Does not arise 4.11 Other solid wastes Yes The quantity of Bio Medical waste generated from the proposed project will be 469 kg/day (Refer section 3.7)

8 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Details thereof (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 5.1 Emissions from combustion Yes The gaseous emissions are of fossil fuels from stationary expected from transport vehicles or mobile sources moving inside the project site. The emissions are expected from Diesel Generator during operation phase. 5.2 Emissions from production No Does not arise since the proposed processes project is a Residential Development 5.3 Emissions from materials Yes Emissions like dust will arise handling including storage or during the transportation of transport materials and the dust will be controlled by slow movement of vehicles, covering the materials properly and by water spraying 5.4 Emissions from construction No Maximum construction works will activities including plant and be done with well-maintained equipment equipments. 5.5 Dust or odours from Yes Dust emission will be arrested by handling of materials water spraying and covering the including construction stored materials with tarpaulin materials, sewage and waste cover. Septic tanks & soak pit will be provided for laborers during construction phase 5.6 Emissions from incineration No There are no incineration of waste activities 5.7 Emissions from burning of No No such activities will be waste in open air (e.g. slash permitted materials, construction debris) 5.8 Emissions from any other No No emissions from any other sources sources

9 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

6. Generation of Noise and Vibration, and Emissions of Light and Heat: Details thereof (with Information/Checklist Yes/ approximate quantities /rates, S. No. confirmation No wherever possible) with source of information data 6.1 From operation of equipment Yes Workers will be given ear plugs in e.g. engines, ventilation plant, noisy area. Acoustic enclosures crushers will be provided for the D.G. set 6.2 From industrial or similar No Not Applicable processes 6.3 From construction or Yes Noise levels in the range of 75-85 demolition dB (A) will be generated occasionally during the construction activities. Workers in the noisy areas will be provided with earmuffs and earplugs. 6.4 From blasting or piling No Not applicable 6.5 From construction or Yes During construction phase operational traffic construction materials will be transported by road, through well maintained vehicles to control noise, vibration and emissions. During operational phase traffic noise and emissions will be increased slightly that will be minimized by paving roads with asphalt/concrete, well maintained vehicles, slow movement of vehicles and by planting trees 6.6 From lighting or cooling No Adequate enclosures, tree systems plantations will be provided 6.7 From any other sources No Not Applicable

10 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: Details thereof (with Information/Checklist Yes/ approximate quantities /rates, S. No. confirmation No wherever possible) with source of information data 7.1 From handling, storage, use No There will be no handling of or spillage of hazardous hazardous materials. materials 7.2 From discharge of sewage or Yes Sewage will be treated in the STP other effluents to water or the of capacity 550 KLD within the land (expected mode and project site. The treated waste place of discharge) water will be reused for green belt development; toilet flushing and HVAC Effluent will be treated in the ETP of capacity 100 KLD and treated effluent will be connected to STP 7.3 By deposition of pollutants No Emissions from operation of DG emitted to air into the land or Sets will be within the prescribed into water limits and negligible. 7.4 From any other sources No No other polluting sources exist 7.5 Is there a risk of long term No There will not be any long term build up of pollutants in the build up of pollutants in the environment from these environment from these sources sources?

11 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment Details thereof (with Information/Checklist Yes/ approximate quantities /rates, S. No. confirmation No wherever possible) with source of information data 8.1 From explosions, spillages, No No hazardous substances will be fires etc from storage, required either during handling, use or production of construction or operation phases. hazardous substances However adequate safety measures to mitigate all risks anticipated out of fire in diesel will be taken care of by installing suitable fire fighting system. 8.2 From any other causes No No risks from any other sources 8.3 Could the project be affected The area under study falls in by natural disasters causing Zone-III according to the Indian environmental damage (e.g., Standard Seismic Zoning Map. The floods, earthquakes, structure was designed to be landslides, cloudburst etc)? earthquake resistant. There will not be any long term build up of pollutants in the environment from these sources.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality Details thereof (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 9.1 Lead to development of Yes Supporting and ancillary supporting. Utilities, ancillary development will take place which development or development in turn will improve environment. stimulated by the project (e.g.,) Plantation of trees, which could have impact on rainwater harvesting, and Storm the environment e.g. water drains etc., Basic Supporting infrastructure infrastructure will be developed in (roads, power supply, waste the proposed area. or waste water treatment, etc.) Housing development Yes There would be housing development with hospital

12 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

Extractive industry No No Extraction Supply industry No No Industrial activity 9.2 Lead to after-use of the site, No Not Applicable which could have an impact on the environment 9.3 Set a precedent for later No Developmental activity may take developments place complying statutory requirements. 9.4 Have cumulative effects due No Does not arise to proximity to other existing or planned projects with similar effects

(III) Environmental Sensitivity

Aerial distance S. Name/ (within 15 km.) Areas No. Identity Proposed project location boundary 1. Areas protected under NIL - international conventions, national or local legislation for their ecological, landscape, cultural or other related value 2. Areas which are important or Chembarambakkam 2.8 km (s) sensitive for ecological Lake reasons - Wetlands, Coovum River 4.1 km (NE) watercourses or other water Lake 7.8 km (ESE) bodies, coastal zone, Tinnanur Lake 8.4 km (NW) biospheres, mountains, 9.3 km (SE) forests Palavedu Eri 9.8 km (NNW) Kovilpadagai 9.8 km (NNE) 3. Areas used by protected, NIL - important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4. Inland, coastal, marine or Chembarambakkam 2.8 km (s) underground waters Lake 7.8 km (ESE) 5. State, National boundaries No Not Applicable 6. Routes or facilities used by No Not Applicable the public for access to recreation or other tourist, pilgrim areas

13 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

7. Defense installations No NIL within 15 km radius 8. Densely populated or built-up Thirumazhisai 1.4 km (SW) area Poonamallee 3.3 km (SE) Nazarathpet 1.1 km (S) 9. Areas occupied by sensitive St.Joseph's 1.7 km (E) man-made land uses Matriculation Higher 0.5 km (SSW) (hospitals, schools, places of Secondary School worship, community) 10. Areas containing important, Not applicable - high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11. Areas already subjected to Not applicable --- pollution or environmental damage. (those where existing legal environmental standards are exceeded) 12. Areas susceptible to natural The area under study --- hazard which could cause the falls in Zone III, project to present according to the Indian environmental problems Standard Seismic (earthquakes, subsidence, Zoning Map. landslides, erosion, flooding or extreme or adverse climatic conditions)

14 NOVEMBER 2016

PROPOSED CONSTRUCTION OF HOSPITAL WITH RESIDENTIAL QUARTERS BY M/s. JAISAKTHI EDUCATIONAL TRUST FORM I

16 NOVEMBER 2016