Tendring Life Opportunities District Council Building Services

PRE-TENDER HEALTH AND SAFETY PLAN

Project: Renewal of communal cross door fire doors, flat doors, and internal redecoration.

Location: Groom House, St Annes Road, Clacton-on-Sea, , CO156AY

Prepared By: VG Found Date: 26/09/2019

Checked By: D Williams Date: 26/09/2019

Life Opportunities Development & Building Services District Council Town Hall Station Road Clacton on Sea Essex CO15 1SE

Project Details

Name of Project: Groom House upgrade communal fire doors and areas.

Location: Groom House, St Annes Road, Clacton, Essex CO156AY

Project Description: Replacement of cross corridor fire doors with new fire resistant Door sets . Replacement of Flat and Ancillary Area Doors into existing frames.. Replacement of carpets to communal Areas and internal redecoration.

Key Project dates: October 2019 Construction Phase: November 2019

Client: Damian Williams BSc (Hons) MCIPD MInstLM Life Opportunities Building Services Tendring District Council Town Hall Station Road Clacton on Sea Essex CO15 1SE Contact: ...... Tel 01255 686868

Principle Steve Pearce Designer: Life Opportunities Building Services Tendring District Council Town Hall Station Road Clacton on Sea Essex CO15 1SE Contact: Mr Steve Pearce 01255 686868

Environment

Adjacent Land Uses -- Residential areas, public footpaths Consequent restrictions --

Residential Working Hours – Not weekends or Bank Holidays Commercial Not applicable Health And Safety -- Customer Care Guidelines – see specification

Existing Services Statutory Undertaker Approx Position Above/Below Ground Electricity TBC Various Unknown Gas TBC Various N/A Telecommunications British Telecom Various N/A Surface Water Veolia Water Various Below Ground Foul Water Veolia Water Various Below Ground Note: All excavations are to be preceded by a survey for underground services

Existing Structures

The existing structures comprise the following construction types: Various Locations, therefore Various designs of structure

Main Building(s) approximate date of construction: 1980’s condition: Good

External walls: Brickwork Internal walls: TBC

Ground floor: Concrete Floors Other floors: Suspected Concrete floors

Roofs: Pitched-tiled Major services: All

Existing Drawings and Information

The following documents are attached: Specification of Works, floor plans and site plan.

The following hazardous materials are expected to be found:

Design of the new works

The new works generally comprise the following construction types: Removal of current flat doors and communal corridor doors and replacing them with new fire rated doors. Redecoration of internal walls Re-carpeting communal areas.

Construction risks

The following risks during the construction process have been identified and assessed. The risks have been listed in the three phases of the structure's life: construction, alteration and maintenance and demolition. The list does not presume to be exhaustive and the Principal contractor is requested to identify any further risks and how these will be addressed in the tender submission and subsequently in the construction phase health and safety plan.

RISK PHASE LEVEL PERSONS AT RISK MINIMUM CONTROL MEASURES Dust C Medium Workforce/ Building Follow relevant guidelines for cutting operations take users/ Public precautions to control dust. Workforce to wear personal protective equipment. Inhalation of fibres C Medium Any removed material to be suitably bagged. Masks to be worn Removal of asbestos C Work Workforce IF applicable. Protective clothing to be worn. Prior to force/ starting provide detailed statement as HSE guidance Building RAD survey will be provided before works start. users Potentially hazardous C/D/M Work Workforce Surveys prior to starting seek client's advice on materials due client's force/ control measures. Form contingency plan. Ensure use of rooms/areas Building protective clothing is worn users Use of naked flame C Medium Workforce/ Building NOT permitted. users

RISK PHASE LEVEL PERSONS AT RISK MINIMUM CONTROL MEASURES Connections to existing C/M Medium Workforce Apply relevant health and safety guidelines. Permit to services work procedure Welfare C/D/M Medium Workforce Provide Welfare Facilities Concealed services C/M High Workforce Detect services, training of workforce Trailing leads and hoses C Medium Workforce/ Building Use only 110v equipment Lay leads etc with signs users and protection Access to site C/M Medium Workforce/ Building Agreed positions and routes only to be used when users defined at start of contract Interaction with C Medium Workforce/ building Clear signage and protection of scaffolding. building public users/ public Hoarding and fencing off of work areas Work above occupied C/M medium Building users/ Agreed programme of work. Permit to work areas. Workforce procedure Boarding out or similar Fragile roofs and C/M high Workforce/ Building Barriers around fragile areas use of access equipment. rooflights users Boarding over Access routes C/M High Workforce/ Building Use of scaffold, netting and fencing off work areas users Unprotected edges eg C/M High Workforce/ Building Provide guard-rails roofs users Operation of hoist C High Workforce/ Building Operator training, testing of equipment users Handling and storage of C Medium Workforce Workforce training adequate equipment, secure big components storage, obtain stacking limits Working at height C/D/M High Workforce Scaffold/ access equipment, Safety rails/lines Noise C/D/M High Workforce/Building Limit work hours to 8am-6pm. No Radios. Users/ Public

Other risks that are common on construction projects are listed below. These may be helpful in identifying further issues to be covered in the construction phase health and safety plan:

Demolition and site clearance. Work over or adjacent highways or paths and access routes Buried services. Contact with hazardous materials prior to removal by specialists. Noise and dust. Work adjacent to fume or ventilation terminals Use of mechanical plant. Work on live services. Discovery of asbestos products. Inhalation of insulation fibres. Trailing leads and hoses. Working at high level. Disconnection of lighting. Use of naked flames. Persons occupying areas below or adjacent work area. Stability of partly completed structures Use of hoists or lifts Handling and placement of large components Erection of scaffolds. Fragile roofs or rooflights. Overloading of floors and roofs. Remote connections to services. Storage and handling of glass and hazardous materials. Delivery and unloading of all materials etc especially large items.

This list does not presume to be exhaustive and the principal contractor will be required to identify and analyse any further risks in the construction phase health and safety plan.

Maintenance hazards

The following issues, relating to elements to be designed by the contractor, have been identified as presenting potential hazards during the future maintenance of the structure: None

Co-ordination

It has been identified that at key stages in the project a number of trades or contractors will be working in the same or adjacent areas. It will be the responsibility of the principal contractor to co-ordinate the workforce(s) and a programme of works and method statement will be required to show how this will be achieved.

Construction materials

The following construction materials are prohibited and shall not be incorporated into the work:

Asbestos products. Materials containing loose fibres less than 3 microns in diameter. High Allumina Cement. Calcium chloride. Urea formaldehide Other materials known to be deleterious at the time.

Hazardous materials

Hazardous materials, which cannot be eliminated from the works, have been identified and listed below. This list does not presume to be exhaustive and the principle contractor must identify any further hazardous materials and give detailed method statements in the construction phase health and safety plan.

Welding fumes. Isocyanates (typically in foams and resins). Airborne fibres. Airborne dust especially silica and quartz. Solvents. Paints and the like. Dusts generally. Cement and concrete Acids and alkalis. Resins.

Precautionary measures will typically include: warning signs, personal protective clothing, temporary screening, personnel training, additional ventilation, washing facilities and skin creams. Particular care must be used to identify flammable substances.

Interaction with the client

The contractor will not have sole occupation of the site.

The client will continue to occupy all or part of the site, access routes and emergency routes are to be kept clear at all times.

The principle contractor must take precautions against unauthorised persons being drawn to the works.

Access etc to adjacent land must also be maintained.

All buildings are to be kept secure while work is not in progress.

All adjacent footpaths and rights of way must be protected by suitable fencing or hoarding during the works and supplied with adequate signage and lighting.

Site rules

Health and safety co-ordination

The principle contractor will be responsible for ensuring that health and safety information is made available to every person on site and for induction training for all personnel starting on site. The principal contractor will arrange regular health and safety meetings to be attended by representatives of all organisations present on site. The principal contractor will ensure that all personnel on site are suitably trained in the use of plant and equipment necessary for the works.

The principal contractor is to prepare plans for emergency procedures, first aid, evacuation, including reporting arrangements and liaison with the emergency services as necessary. The principal contractor shall not rely on the facilities provided by the client unless specifically agreed.

Site access/egress

Access to the site is to be via: Public Footpath/Road/ and Private Driveways, Gardens and Paths (with owner’s permission)

Traffic on site is to be restricted to the following routes: Areas belonging to tenants involved in the works

Contractors parking is to be restricted to: Public road only unless permission given by tenant to park on driveway BUT any damage to driveway or garden to be made good by the Contractor at their own expense,

Laydown and storage of materials on site is to be in the following locations: Agreed areas only

Delivery of materials/removal of waste is prohibited during the following times: 18.00pm-08.00am and weekends

The working area will be confined to the following areas only: Areas belonging to tenants involved in the works

Working hours will be restricted to the following:

Monday to Friday: 0800h to 1800h Saturdays: work prohibited unless specifically arranged with client and Building User Sundays: work prohibited unless specifically arranged with client and Building User

Identity badges are to be worn by all construction staff at all times.

Detailed design

The following list indicates those matters that are to be designed in detail by the contractor. As further design information is made available the principal contractor is to further liase with the planning supervisor and update the health and safety plan as required:

Unforeseen events

The principal contractor is to notify the planning supervisor and client immediately if any event occurs which creates or reveals a health and safety hazard or affects the resources necessary to safely complete the work.