Tendring Life Opportunities District Council Building Services PRE-TENDER HEALTH AND SAFETY PLAN Project: Renewal of communal cross door fire doors, flat doors, and internal redecoration. Location: Groom House, St Annes Road, Clacton-on-Sea, Essex, CO156AY Prepared By: VG Found Date: 26/09/2019 Checked By: D Williams Date: 26/09/2019 Life Opportunities Development & Building Services Tendring District Council Town Hall Station Road Clacton on Sea Essex CO15 1SE Project Details Name of Project: Groom House upgrade communal fire doors and areas. Location: Groom House, St Annes Road, Clacton, Essex CO156AY Project Description: Replacement of cross corridor fire doors with new fire resistant Door sets . Replacement of Flat and Ancillary Area Doors into existing frames.. Replacement of carpets to communal Areas and internal redecoration. Key Project dates: October 2019 Construction Phase: November 2019 Client: Damian Williams BSc (Hons) MCIPD MInstLM Life Opportunities Building Services Tendring District Council Town Hall Station Road Clacton on Sea Essex CO15 1SE Contact: ........................ Tel 01255 686868 Principle Steve Pearce Designer: Life Opportunities Building Services Tendring District Council Town Hall Station Road Clacton on Sea Essex CO15 1SE Contact: Mr Steve Pearce 01255 686868 Environment Adjacent Land Uses -- Residential areas, public footpaths Consequent restrictions -- Residential Working Hours – Not weekends or Bank Holidays Commercial Not applicable Health And Safety -- Customer Care Guidelines – see specification Existing Services Statutory Undertaker Approx Position Above/Below Ground Electricity TBC Various Unknown Gas TBC Various N/A Telecommunications British Telecom Various N/A Surface Water Veolia Water Various Below Ground Foul Water Veolia Water Various Below Ground Note: All excavations are to be preceded by a survey for underground services Existing Structures The existing structures comprise the following construction types: Various Locations, therefore Various designs of structure Main Building(s) approximate date of construction: 1980’s condition: Good External walls: Brickwork Internal walls: TBC Ground floor: Concrete Floors Other floors: Suspected Concrete floors Roofs: Pitched-tiled Major services: All Existing Drawings and Information The following documents are attached: Specification of Works, floor plans and site plan. The following hazardous materials are expected to be found: Design of the new works The new works generally comprise the following construction types: Removal of current flat doors and communal corridor doors and replacing them with new fire rated doors. Redecoration of internal walls Re-carpeting communal areas. Construction risks The following risks during the construction process have been identified and assessed. The risks have been listed in the three phases of the structure's life: construction, alteration and maintenance and demolition. The list does not presume to be exhaustive and the Principal contractor is requested to identify any further risks and how these will be addressed in the tender submission and subsequently in the construction phase health and safety plan. RISK PHASE LEVEL PERSONS AT RISK MINIMUM CONTROL MEASURES Dust C Medium Workforce/ Building Follow relevant guidelines for cutting operations take users/ Public precautions to control dust. Workforce to wear personal protective equipment. Inhalation of fibres C Medium Any removed material to be suitably bagged. Masks to be worn Removal of asbestos C Work Workforce IF applicable. Protective clothing to be worn. Prior to force/ starting provide detailed statement as HSE guidance Building RAD survey will be provided before works start. users Potentially hazardous C/D/M Work Workforce Surveys prior to starting seek client's advice on materials due client's force/ control measures. Form contingency plan. Ensure use of rooms/areas Building protective clothing is worn users Use of naked flame C Medium Workforce/ Building NOT permitted. users RISK PHASE LEVEL PERSONS AT RISK MINIMUM CONTROL MEASURES Connections to existing C/M Medium Workforce Apply relevant health and safety guidelines. Permit to services work procedure Welfare C/D/M Medium Workforce Provide Welfare Facilities Concealed services C/M High Workforce Detect services, training of workforce Trailing leads and hoses C Medium Workforce/ Building Use only 110v equipment Lay leads etc with signs users and protection Access to site C/M Medium Workforce/ Building Agreed positions and routes only to be used when users defined at start of contract Interaction with C Medium Workforce/ building Clear signage and protection of scaffolding. building public users/ public Hoarding and fencing off of work areas Work above occupied C/M medium Building users/ Agreed programme of work. Permit to work areas. Workforce procedure Boarding out or similar Fragile roofs and C/M high Workforce/ Building Barriers around fragile areas use of access equipment. rooflights users Boarding over Access routes C/M High Workforce/ Building Use of scaffold, netting and fencing off work areas users Unprotected edges eg C/M High Workforce/ Building Provide guard-rails roofs users Operation of hoist C High Workforce/ Building Operator training, testing of equipment users Handling and storage of C Medium Workforce Workforce training adequate equipment, secure big components storage, obtain stacking limits Working at height C/D/M High Workforce Scaffold/ access equipment, Safety rails/lines Noise C/D/M High Workforce/Building Limit work hours to 8am-6pm. No Radios. Users/ Public Other risks that are common on construction projects are listed below. These may be helpful in identifying further issues to be covered in the construction phase health and safety plan: Demolition and site clearance. Work over or adjacent highways or paths and access routes Buried services. Contact with hazardous materials prior to removal by specialists. Noise and dust. Work adjacent to fume or ventilation terminals Use of mechanical plant. Work on live services. Discovery of asbestos products. Inhalation of insulation fibres. Trailing leads and hoses. Working at high level. Disconnection of lighting. Use of naked flames. Persons occupying areas below or adjacent work area. Stability of partly completed structures Use of hoists or lifts Handling and placement of large components Erection of scaffolds. Fragile roofs or rooflights. Overloading of floors and roofs. Remote connections to services. Storage and handling of glass and hazardous materials. Delivery and unloading of all materials etc especially large items. This list does not presume to be exhaustive and the principal contractor will be required to identify and analyse any further risks in the construction phase health and safety plan. Maintenance hazards The following issues, relating to elements to be designed by the contractor, have been identified as presenting potential hazards during the future maintenance of the structure: None Co-ordination It has been identified that at key stages in the project a number of trades or contractors will be working in the same or adjacent areas. It will be the responsibility of the principal contractor to co-ordinate the workforce(s) and a programme of works and method statement will be required to show how this will be achieved. Construction materials The following construction materials are prohibited and shall not be incorporated into the work: Asbestos products. Materials containing loose fibres less than 3 microns in diameter. High Allumina Cement. Calcium chloride. Urea formaldehide Other materials known to be deleterious at the time. Hazardous materials Hazardous materials, which cannot be eliminated from the works, have been identified and listed below. This list does not presume to be exhaustive and the principle contractor must identify any further hazardous materials and give detailed method statements in the construction phase health and safety plan. Welding fumes. Isocyanates (typically in foams and resins). Airborne fibres. Airborne dust especially silica and quartz. Solvents. Paints and the like. Dusts generally. Cement and concrete Acids and alkalis. Resins. Precautionary measures will typically include: warning signs, personal protective clothing, temporary screening, personnel training, additional ventilation, washing facilities and skin creams. Particular care must be used to identify flammable substances. Interaction with the client The contractor will not have sole occupation of the site. The client will continue to occupy all or part of the site, access routes and emergency routes are to be kept clear at all times. The principle contractor must take precautions against unauthorised persons being drawn to the works. Access etc to adjacent land must also be maintained. All buildings are to be kept secure while work is not in progress. All adjacent footpaths and rights of way must be protected by suitable fencing or hoarding during the works and supplied with adequate signage and lighting. Site rules Health and safety co-ordination The principle contractor will be responsible for ensuring that health and safety information is made available to every person on site and for induction training for all personnel starting on site. The principal contractor will arrange regular health and safety meetings to be attended by representatives of all organisations present on site. The principal contractor will ensure that all personnel on site are suitably trained in the use of plant and equipment
Details
-
File Typepdf
-
Upload Time-
-
Content LanguagesEnglish
-
Upload UserAnonymous/Not logged-in
-
File Pages6 Page
-
File Size-