COUNCIL

LOCAL DEVELOPMENT PLAN (2011-2026)

EXAMINATION IN PUBLIC:

Matter 8: Infrastructure & Welsh Language

Action Point 1

Council to amend Table 6.1 [Implementation Plan Summary] to include up to date information on infrastructure proposals and to incorporate information to strengthen the link between allocated sites and infrastructure provision.

Council’s Response

If deemed acceptable and appropriate by the Inspectors, the Council would propose the revised Table 6.1 (as appended) to be addressed via a Matters Arising Change.

1 . Implementation and Monitoring

Revised Table 6.1 Implementation Plan Summary

Implementation Location Lead Organisation & Funding Status 2013 Phasing Amount of Policy Reference Settlement 2015 Development 2011-14 2014-17 2017-20 2020-23 2023-26

Policy SP5 - Coastal Corridor Strategy Area & Monitoring SP 5 Science & Innovation Campus, Fabian Way University, St Modwen Commenced

Policy H1 - Housing Sites V8

H1/ 1 Gorffwysfa Care Home Bryncoch 15 NPT & Private Sector

H1/ 2 Leiros Park Extension Bryncoch 200 Private Sector

H1/ 3 Groves Road (Phase 2) Cimla 42 Private Sector

H1/ 4 Ocean View Jersey Marine 81 David Wilson Homes Commenced

H1/ 5 Dwr Y Felin Lower School Longford 100 NPT & Private Sector

H1/ 6 Hafod House Care Home Neath 12 NPT & Private Sector

H1/ 7 Neath Town Centre Redevelopment Neath 50 NPT & Private Sector

Approved H1/ 8 Crymlyn Grove (Phase 2) 75 Barratt Homes Commenced

H1/ 9 Crymlyn Grove (Phase 3) Skewen 150 Private Sector

H1/10 Wern Goch Skewen 50 Private Sector Hale Homes Commenced

H1/11 Neath Road / Fairyland Road Tonna 300 Private Sector

H1/LB/1 Waunceirch Bryncoch 13 Waterstone Homes Complete

H1/LB/2 Groves Road (Phase1) Cimla 34 Coastal Group Commenced

H1/LB/3 Elba Crescent Crymlyn Burrows 50 Private Sector

H1/LB/4 Area 1, Coed Darcy Urban Village 157 Atlantic Developments Commenced

H1/LB/5 Coed Darcy Urban Village Llandarcy 2,150 2,400 St Modwen Commenced

TR1/2 Coed Darcy Southern Access Road St Modwen & Private Sector. Funding and delivery secured as part of the S.106 agreement with completion scheduled before the occupation of the 501st unit or by July 2017 whichever is the sooner

Funded through WG, ERDF & St Modwen & supported through NPT. Scheme completed in early 2013 TR1/3 Ffordd Amazon (Stage 2)

TR1/4 Junction 43, M4 Improvements Phased programme of improvements to be funded and delivered in line with the S.106 agreement

2 H1/LB/6 Eaglesbush, Melincryddan Neath 50 Private Sector

H1/LB/7 Garthmor (Phase 2), Melincryddan Neath 34 Ballard Homes Commenced

H1/LB/8 Briton Ferry Road Neath 28 Coastal Group Commenced

Commenced H1/LB/9 The Ropewalk Neath 12 Coastal Group Complete 1 . Implementation and Monitoring

Location Lead Organisation & Funding Status 2013 Phasing V8 Amount of Policy Reference Settlement 2015 Development 2011-14 2014-17 2017-20 2020-23 2023-26

H1/LB/10 Barrons Court Neath Abbey 15 Private Sector Commenced Monitoring & Private Sector Gwalia Housing Approved H1/LB/11 Cardonnel Road Skewen 16 Association Commenced

H1/LB/12 Crymlyn Grove (Phase 1) Skewen 81 Barratt Homes Commenced

H1/12 Blaenbaglan School (land to the r/o) Baglan 141 Private Sector Implementation

H1/13 Hawthorn Close Cwmafan 100 Private Sector Revised H1/14 Western Logs Cwmafan 130 Private Sector

H1/15 Neath Port Talbot College (Margam Campus) Margam 70 NPT College

H1/16 Glanafan Comprehensive School Port Talbot 50 NPT & Private Sector

H1/17 Harbourside Port Talbot 520 385 NPT, Private Sector & RSLs Commenced

TR1/5 Harbour Way (PDR) Approx. £108m scheme,WG & Convergence funded and completed in late 2013

Funded by RTP / JTP and National Stations Improvement Programme which includes WG and Convergence funding. Port Talbot Parkway station under construction and due to be completed during 2016, with the Integrated TR1/6 Integrated Transport Hub (Port Talbot) Transport Hub fully implemented by 2018

H1/18 Afan Lido & Land r/o Tywyn School Sandfields 150 NPT & Private Sector

H1/19 Bay View Social Club Sandfields 23 Private Sector

H1/20 Purcell Avenue Sandfields 115 St Modwen

H1/21 Morfa Afan Care Home Sandfields 10 NPT & Private Sector

H1/22 Tir Morfa Road Sandfields 75 NPT & Private Sector

H1/LB/13 Blaenbaglan Farm Baglan 260 160 Private Sector Approved

H1/LB/14 Thorney Road Baglan 10 Private Sector Commenced

H1/LB/15 Stycyllwen Baglan 24 Private Sector Commenced

Commenced H1/LB/16 Abbottsmoor Baglan Moors 42 Barratt Homes Complete

H1/LB/17 Farteg Fawr Bryn 25 Private Sector Commenced

H1/LB/18 Copperminers Cwmafan 90 Barratt Homes Commenced

H1/LB/19 Forest Lodge Lane Cwmafan 12 Private Sector Commenced

Commenced H1/LB/20 Groeswen Margam 39 Taylor Wimpey Complete 3 H1/LB/21 Station Road Port Talbot 14 Coastal Group Complete

Commenced H1/LB/22 Royal Buildings, Talbot Road Port Talbot 46 Coastal Group Complete

H1/LB/23 Dyffryn Road Taibach 14 Private Sector Complete

H1/LB/24 Maes Marchog Banwen 16 NPT Complete 1 . Implementation and Monitoring

Revised Location Lead Organisation & Funding Status 2013 Phasing Amount of Policy Reference Settlement 2015 Development 2011-14 2014-17 2017-20 2020-23 2023-26 Implementation

H1/LB/25 Glyn Dulais Care Home Crynant 21 NPT & Private Sector Approved

H1/LB/26 Heol Y Waun Seven Sisters 68 Private Sector Approved

& H1/23 Park Avenue Glynneath 150 NPT & Private Sector Monitoring H1/LB/27 Heol Y Glyn Glynneath 81 Private Sector Approved

H1/LB/28 Welfare Hall Glynneath 17 Private Sector Approved V8 H1/LB/29 Ynys Y Nos Avenue Glynneath 16 WDL Homes Commenced

H1/24 Bryn Morgrug (Phase 2) Alltwen 52 Private Sector Redrow Homes Commenced

H1/25 Ynysymond Road Alltwen 50 Private Sector

H1/26 Cwmtawe School (Phase 2) Pontardawe 32 Private Sector

H1/27 Waun Sterw / Waun Penlan, Rhydyfro Pontardawe 115 NPT & Private Sector

H1/28 Bryn Brych Farm Rhos 150 Private Sector

H1/LB/30 Bryn Morgrug (Phase 1) Alltwen 56 Redrow Homes Commenced

H1/LB/31 Cwmtawe School (Phase 1) Pontardawe 80 Coastal Group Commenced

H1/LB/32 Holly Street Pontardawe 45 Private Sector

H1/LB/33 Waun Penlan, Rhydyfro Pontardawe 19 Private Sector

H1/LB/34 Glan Yr Afon (Phase 2) Pontardawe 15 Coastal Group Complete

H1/29 Compair / GMF Ystalyfera 120 Private Sector

Commenced H1/LB/35 Golwg Y Mynydd Godre'r Graig 64 Taylor Wimpey Homes Complete

H1/LB/36 Graig Newydd (Phase 1) Godre'r Graig 42 Barratt Homes Complete

Approved H1/LB/37 Graig Newydd (Phase 2) Godre'r Graig 66 Taylor Wimpey Homes Commenced

Policy GT 1 - Gypsy & Traveller Site

Cae Garw (Phase 1) Margam 4 Pitches NPT Approved

GT1 Cae Garw (Phase 2) Margam 7 Pitches NPT Approved

An appropriate site / Cae Garw 9 Pitches NPT 4 Policy EC 1 - Employment Allocations

EC1/1 Baglan Bay Port Talbot 11 15 Hectares St.Modwen, Private Sector

TR1/1 Baglan Energy Park Link Road £7.3 m scheme, funded by RTP / JTP, NPT and developer. Scheme completed in March 2015

EC1/2 Junction 38 (M4), Margam Port Talbot 6 Hectares Welsh Government, Private Sector 1 . Implementation and Monitoring

Location Lead Organisation & Funding Status 2013 Phasing V8 Amount of Policy Reference Settlement 2015 Development 2011-14 2014-17 2017-20 2020-23 2023-26

TR1/5 Harbour Way (PDR) Approx. £108m scheme,WG & Convergence funded and completed in late 2013 Monitoring &

EC1/3 Land within Coed Darcy SRA Neath 4 Hectares St.Modwen, Private Sector

TR1/2 Coed Darcy Southern Access Road St Modwen & Private Sector. Funding and delivery secured as part of the S.106 agreement with completion scheduled before the occupation of the 501st unit or by July 2017 whichever is the sooner

Funded through WG, ERDF & St Modwen & supported through NPT. Scheme completed in early 2013 Implementation TR1/3 Ffordd Amazon (Stage 2) Revised TR1/4 Junction 43, M4 Improvements Phased programme of improvements to be funded and delivered in line with the S.106 agreement

Phase 1 Nearing EC1/4 Land within Harbourside SRA 11 7 Hectares Port Talbot Private Sector, Deryn Properties Completion 40,000 sq ft (Phase 1) Complete TR1/5 Harbour Way (PDR) Approx. £108m scheme,WG & Convergence funded and completed in late 2013 TR1/6 Integrated Transport Hub Funded by RTP / JTP and National Stations Improvement Programme which includes WG and Convergence funding. Port Talbot Parkway station under construction and due to be completed during 2016, with the Integrated Transport Hub fully implemented by 2018

Policy R 1 - Retail Allocations

Planning Application in R1/1 Neath Town Centre Regeneration Scheme Neath To be determined NPT & Private Sector preparation Phase 1 Commenced

R1/2 Glanafan Comprehensive School Port Talbot To be determined NPT & Private Sector

Supplementary Planning R1/3 Harbourside Port Talbot To be determined Private Sector Guidance prepared

R1/4 Park Avenue, Glynneath Neath Valley To be determined NPT & Private Sector

Policy TO 3 - Tourism Led Regeneration

Planning application TO3/1 Rheola Estate, Glynneath Neath Valley Private Sector submitted Outline Planning Permission

Policy TO 4 - Walking & Cycling Routes 5 Funded through NPT, NRW & Completed May TO4/1 Coastal Path WEFO 2012

Funded through Convergence Commenced TO4/2 Cognation Mountain Bike Trails ERDF, WG and Western Valleys Complete Strategic regeneration area with 1 . Implementation and Monitoring

Revised Location Lead Organisation & Funding Status 2013 Phasing Amount of Policy Reference Settlement 2015 Development 2011-14 2014-17 2017-20 2020-23 2023-26 Implementation

Blade element funded by Vatenfall as part of the Pen y Cymoedd Wind farm project

Funded through ROWIP grant Completed May & TO4/3 Great Dragon Ride Route

Monitoring administered by NRW 2012

Policy TR 1 - Transport Proposals V8 Planning £7.3 m scheme, funded by RTP / application JTP, NPT and developer TR1/1 Baglan Energy Park Link Road Baglan submitted contributions, due for completion Complete March 2015 2015

Planning permission approved. The Coed Darcy Southern Access Road is St Modwen & Private Sector. scheduled for TR1/2 Coed Darcy Southern Access Road Llandarcy Funding and delivery secured as completion part of the S.106 agreement before the occupation of the 501st unit or by July 2017 whichever is the sooner

Funded through WG, ERDF & St Complete early TR1/3 Ffordd Amazon (Stage 2) Llandarcy Modwen, supported through NPT 2013

Commenced Site Phased programme of preparation works improvements to be funded and TR1/4 Junction 43, M4 Improvements Llandarcy complete and delivered in line with the S.106 highway works agreement commenced

Approx. £108m scheme,WG & Completion late TR1/5 Harbour Way (PDR) Port Talbot Convergence funded due for 2013 Complete completion late 2013 late 2013

Planning permission approved for Parkway element, design stage on-going for remaining Funded by RTP / JTP and elements National Stations Improvement TR1/6 Integrated Transport Hub (Port Talbot) Port Talbot 6 Programme which includes WG New Port Talbot and Convergence funding Parkway station scheme commenced & due to be completed during 2016 1 . Implementation and Monitoring

Location Lead Organisation & Funding Status 2013 Phasing V8 Amount of Policy Reference Settlement 2015 Development 2011-14 2014-17 2017-20 2020-23 2023-26

TR1/7 Monitoring Amman Valley Cycle Way Amman Valley Funded through RTP / JTP Commenced &

VRP, All Wales Coastal Footpath, Tidy Towns, BBC Breathing Completed March TR1/8 Afan Valley Trail (Port Talbot to Afan Valley) Port Talbot Spaces, NPT Capital, Forestry 2013 Commission, Welsh Water, Barratts S.106 Implementation

Masterplan for area to include Revised TR1/9 Park & Share, Junction 38 (M4) Margam Port Talbot NPT & WG scheme being prepared

7