Wissahickon School District

Design Competition for the Wissahickon High School

March 18, 2014 Project Design Team

Wissahickon School District

Danielle V. Hoffer Brian K. Good, AIA Rod Frey, Jr., AIA Kenneth R. Johnson AIA, REFP, LEED GA Senior Project Manager Senior Project Manager Senior Project Manager Vice President Project Architect Project Designer Director of Quality Control

Renew Design Group Snyder Hoffman & Baker, Ingram & 7group Associates, Inc. LEED Consultant Associates

Glenn Harris Lee Snyder

Site/Civil Engineering and Mechanical, Electrical, Structural Engineering Metropolitan Acoustics Landscape Design Plumbing and Fire Acoustical Consultant Protection Engineering About Gilbert Architects . Established in 1988

. Full-service architectural firm

. Focused exclusively on designing educational facilities in , Maryland, Delaware and Virginia

Founder and President of Gilbert Architects Inc. About Gilbert Architects . $2 billion in school construction costs since 1988

. School experience: 88 elementary schools 69 secondary schools - 5 new high schools; 30 renovations and additions - 8 new middle schools (2 with 9th grade centers); 25 renovations and additions 103 PlanCon projects 30 Green/Sustainable/LEED projects

. 95% of projects awarded by repeat clients

School District of Cheltenham Township

Glenside Elementary Cheltenham Elementary

Wyncote Elementary Lower Merion School District

Gladwyne ElementarySchool Penn Valley Elementary School

Welsh Valley Middle School Bala Cynwyd Middle School Radnor Township School District

Radnor Senior High School Renovations and Additions School District of Upper Dublin

Upper Dublin High School New Construction West Chester Area School District

Bayard Rustin High School

East High School

B. Reed Henderson High School

Review the program with the Administration

Review existing data

Find solutions that address the issues Existing Program Organization

Upper Auditorium Upper Round Gym

Art Upper Cafeteria Fitness Room & Kitchen

Square Gym & Audion Locker Rooms

Existing Main Floor Level Circulation and Courtyard Views

7 6

The “Knuckle” 5 8

1 2 3 4

Existing Main Floor Level

Existing Auditorium and Stage

Existing Lower Cafeteria

Existing High School Library

Solution A

Proposed Renovations and Additions to the Wissahickon High School

Renovations and Additions – Phase 1

Begin Construction Summer of 2015

Construct pool – Complete Summer of Renovate blocks 2016 of classrooms in phases

Construct Performing Arts Wing – Complete Add temporary Dec. 2016 classrooms – Summer of 2015

Proposed Main Floor Level Renovations and Additions – Phase 1

Construct Cafeteria / Kitchen addition – Complete December 2016

Proposed Lower Level Renovations and Additions – Phase 2

Demolish the Auditorium; construct new Gym; convert classrooms to Fitness and Wrestling Rooms – Complete Summer 2017

Proposed Lower Level Renovations and Additions – Phase 2

Convert Cafeteria & Kitchen to Tech Ed; new TV Studio – Complete Summer 2017

Proposed Main Floor Level Renovations and Additions – Phase 3

Complete Jan. 2018

Convert Square Gym to new Library/Media Center and SGIs; Convert 2-story Locker Room to tiered LGI Renovate to new LGI

Proposed Main Floor Level

East High School Conversion of

Competition Gym to Library Renovations and Additions – Phase 4

Complete June 2018 Renovate Library to new LGI and SGI space

Proposed Main Floor Level Renovations and Additions – Advantages

Athletics

Performing and Allied Arts

Library / Media Center Accessible to Community

Proposed Main Floor Level Renovations and Additions – Disadvantages

 

 

   

Proposed Main Floor Level

Renovations and Additions – Site Planning

Renovations and Additions – Site Planning

Proposed New High School Auditorium

Entrance from Dager Road

Entrance at Cafeteria and New Gymnasium

View from Dager Road

Entrance at Cafeteria and New Gymnasium

Cafeteria Expansion / Bus Drop-off Area

Construction Costs . Site work $ 4,165,800 . Selective demolition 200,000 . Renovations (total) 39,324,480 . New construction (additions) 22,028,850 . Asbestos & environ. abatement 415,000 . Construction phasing premium 1,500,000 . Subtotal: $67,634,130

. Design contingency @ 7% 4,734,389 . Inflation @ 3% 2,029,024

Total Construction Cost: $74,397,543

Renovations and Additions Cost Estimate

Construction Costs: $74,397,543

Soft Costs: (Low) (High)

(w/ modular classrooms) + $13,448,187 +$15,358,644

Total Project Costs: $87,845,730 $89,756,187

Solution B

Proposed New Construction of the Wissahickon High School

New Construction – Phase 1 Begin Construction Summer of 2015

Construct new 3-story Renovate Construction Zone classroom wing Round Gym and Auditorium; summer of 2016 complete summer 2017

Construct new natatorium; complete summer of 2016 Existing mechanical School Zone room remains operational New Construction – Phase 2

Summer of 2017

School Zone

Construction Zone Demolish existing building New Construction – Phase 2 Complete Construction Summer of 2018

Construct new Gym

Construct Art Classrooms

Complete Sitework New Construction

Proposed Lower Level New Aquatic Facility

New Construction

Proposed First Floor Plan Technology Enhanced Instructional Areas

New Construction

W N

E

Proposed Second Floor Plan New Construction

Proposed Third Floor Plan New Construction - Advantages

Program Organization

Academic Core Student Zone Athletics Wing

Performing Arts Wing

Public Zone New Construction - Advantages

Safety and Security

New Construction - Advantages

W N Environmentally Conscious Design

E New Construction – Proposed Site Plan

W N

E New Construction – Proposed Site Plan

Proposed New High School Campus

Public Zone - Main Entrance Plaza View from Houston Road Design Aspects

South exposure for Identifiable solar panels at standing main entrance seam metal roof

Art rooms reduce scale of the higher Auditorium Controlled Classroom Daylighting

Material Selection

Sand finish masonry units

Manufactured stone veneer

Cast stone trim Student Zone

Cafeteria pavilion 3-story academic building

Music rooms reduce scale of higher auditorium along street

View from Dager Road Library / Media Center

North window exposure ideal for indirect natural light New Construction Costs . Site work $ 5,900,000 . Demolition (total) 1,500,000 . New construction 59,088,631 . Renovations (existing round gym) 2,313,870 . Asbestos & environ. abatement 415,000 . Construction phasing premium 500,000 . Subtotal: $69,717,501

. Design contingency @ 4% 2,788,700 . Inflation @ 3% 2,091,525

Total Construction Cost: $74,597,726

Solution B – New Construction Cost Estimate

Construction Costs: $74,597,726

Soft Costs: (Low) (High)

(w/o modular classrooms) +$12,275,260 +$13,952,720

Total Project Costs: $86,872,986 $88,550,446

Solution B.1

New High School for a Total Project Budget of $74,500,000 Solution B.1 - Program Reductions Total Project Budget of $74,500,000 Reduced costs = reduction in square footage

Option B New Construction = 318,299 s.f.

. Eliminate Natatorium - 26,204 s.f. . Combined Auditorium & LGI - 6,000 s.f. . Eliminate (1) full sized court - 6,500 s.f. . Additional s.f. reductions - 23,500 s.f.

Total Square Foot 256,095 s.f.

20% reduction in square footage 600 Seat Auditorium

(2) LGIs / Additional Seating Capacity

Additional 300 Seat Capacity Multi-functional Space Design

Solution B.1 – Construction Costs . Site work w/o Natatorium $ 5,750,000 . Demolition (total) 1,500,000 . Renovations (existing round gym) 2,313,870 . Building less s.f. reductions 46,513,219 . Asbestos & environ. abatement 415,000 . Construction phasing premium 500,000 Subtotal: $56,992,089

. Design Contingency @ 4% $ 2,279,684 . Inflation @ 3% $ 1,709,763

Total Construction Cost: $60,981,536

Solution B.1 – New Modified Cost Estimate

Construction Costs: $60,981,536

Soft Costs: (Low) (High)

+ $12,139,196 + $13,898,373

Total Project Costs: $73,120,732 $74,879,909

Cost Comparison between Options

Renovations & Additions: $74,397,543 With temporary classrooms: Total Project Cost $87.8 - 89.8M

New Construction: $74,597,726 No temporary classrooms: Total Project Cost $86.9 - $88.5M

New Construction for a Total Project Cost of $74,500,000: $60,981,536 No temporary classrooms: Total Project Cost $73 – 74.9M

Creative Design Solutions for the 21st Century High School 21st Century Classroom

Interactive Learning - Problem Solving

Interactive Learning Environment

Technology Enhanced Instructional Areas

User Friendly

Plymouth-Whitemarsh Senior High School Library/Media Center Renovations Spaces Designed to Facilitate Learning

Promote Fitness & Wellness

Thank you for considering Gilbert Architects Inc. to be part of the Wissahickon High School design team

Stand Alone Pool Allowed if part of the high school educational program

Stand alone project . Subject to Act 34 Act 34 capacity of 40 = maximum allowable building expenditure of $1,121,864 . Referendum required

Part of the high school project . Schedule - Phased bidding - Land Development . Cost

Stand Alone Pool

Building expenditure calculations Act 34 capacity of 40 = maximum allowable building expenditure of $1,121,864

9th grade: 10 x $23,984 = $230,984 10-12th grade: 30 x $29,696 = $890,880

Aggregate Allowable Building Expenditure $1,121,864