75 Ft Diameter Bin

Models: 40–SERIES BIN

Construction Manual

PNEG-4075 Version 1.0

Date: 05-27-13

PNEG-4075 All information, illustrations, photos, and specifications in this manual are based on the latest information available at the time of publication. The right is reserved to make changes at any time without notice.

2 Pneg-4075 75 Ft Diameter 40-Series Bin Table of Contents Contents

Chapter 1 Safety Precautions ...... 7 Safety Guidelines ...... 7 Cautionary Symbols ...... 9 Safety Decals...... 10 Safety Sign-off Sheet...... 13 Chapter 2 Overview ...... 15 General Information...... 15 Anchor Bolt Charts ...... 15 Tools Required for Construction...... 17 Guidelines for Proper Storage of Grain Bin Materials Prior to Construction ...... 17 Overview for a Typical Bin Installation ...... 18 Guidelines for Construction Procedures and Lifting Jack Usage ...... 19 Guidelines for Placement of the Decal Sidewall Sheet ...... 20 Sample Gauge Sheet ...... 20 Chapter 3 Hardware Requirements ...... 23 Bolt and Nut Pairings ...... 23 Hardware for 3–Post Sidewall Sheets on bins that are 18 to 90 Ft in Diameter and 105 Ft Bins that are 27 Rings and Shorter...... 23 Bolt Torque Specifications ...... 24 Identifying Bolt Grades...... 25 Color Chart for Bin Hardware Bucket Lids...... 26 Bolt Identification...... 27 Bolt S-275...... 27 Bolt S-10260...... 27 Bolt S-277...... 27 Bolt S-7485...... 28 Bolt S-7487...... 28 Bolt S-7486...... 28 Bolt S-7488...... 29 Bolt S-10252...... 29 Bolt S-10261...... 30 Chapter 4 Assembling Sidewall Sheets ...... 31 Color Codes for Sidewall Gauge Identification...... 31 Orientation Detail for Top Sidewall Sheets ...... 32 Caulking Detail for Standard (Non-Laminated) Sheets ...... 32 Caulking Detail for Laminated Quad Pattern Sheets ...... 35 Chapter 5 Base Angle Installation...... 37 Installing the Base Angle...... 37 Anchor Bolt Detail...... 39 Installing the Base Angle Shims...... 40 Anchor Bolt Washer Installation ...... 41 Chapter 6 Stiffeners...... 43 Stiffener Part Number Description...... 44 Color Codes for Stiffener Gauge Identification...... 44 Standard Stiffeners...... 45 Top Stiffeners...... 46 Stiffeners Splice ...... 47 Base Stiffeners...... 48 Base Boots ...... 49 Close-Punch Connection for a One-Ring Top Stiffener (16 Ga) and a Two-Ring Stiffener (16 Ga) ...... 50 Two-Ring Top Stiffener to a Two-Ring Stiffener (15–16 Ga) Connection...... 50 Close-Punch Connection for a Two-Ring Top Stiffener to a Two-Ring Stiffener (16 Ga)...... 51

Pneg-4075 75 Ft Diameter 40-Series Bin 3 Table of Contents

Two-Ring Stiffener (15-16 Ga) to a Two-Ring Stiffener (15–16 Ga) Connection...... 51 Close-Punch Connection for a Two-Ring Stiffener (16 Ga) to a Two-Ring Stiffener (16 Ga) ...... 52 Two-Ring Stiffener (0–14 Ga) to a Two-Ring Stiffener (0–14 Ga) Connection...... 52 Close-Punch Connection for a Two-Ring Stiffener (0–14 Ga) to a Two-Ring Stiffener (0–14 Ga) ...... 53 Two-Ring Stiffener (0–14 Ga) to a Close-Punch Base Stiffener (2–8 Ga) Connection ...... 53 Close-Punch Connection for a Two-Ring Stiffener (0–14 Ga) to a Base Stiffener (2–8 Ga) ...... 54 Two-Ring Stiffener (0–14 Ga) to a Base Stiffener (10–16 Ga) Connection ...... 54 Two-Ring Stiffener (2–14 Ga) to a Base Stiffener (10–16 Ga) Connection ...... 55 Two-Ring Stiffener (15–16 Ga) to a Base Stiffener (10–16 Ga) Connection...... 55 Close-Punch Connection for a Two-Ring Stiffener (16 Ga) to a Base Stiffener (10–16 Ga) ...... 56 Close-Punch Two-Ring Stiffener (2–14 Ga) to a Laminated Stiffener (2 Ga) with an Insert (10–14 Ga) ...... 57 Close-Punch Laminated Stiffeners (2 Ga) with Inserts (10–14 Ga)...... 57 Close-Punch Laminated Stiffener (2 Ga) with an Insert (10–14 Ga) to a Laminated Base Stiffener (2–5 Ga) with a Base Insert (2–14 Ga)...... 58 Base Stiffener (10–16 Ga) to a Base Boot Connection...... 59 Close-Punch Connection for a Base Stiffener (10–16 Ga) to a Base Boot...... 59 Close-Punch Connection for a Base Stiffener (2+2 Ga – 8 Ga) to a Base Boot...... 60 Close-Punch Laminated Base Stiffener (2 Ga) with Insert (2+14 to 2+10 Ga) to a Base Boot ...... 61 Close-Punch Standard Stiffener to a 12–Bolt Pattern Laminated Stiffener with Insert...... 61 12–Bolt Pattern Close-Punch Laminated Stiffeners with Insert...... 62 Close-Punch 12–Bolt Pattern Laminated Stiffener to Laminated Base Stiffener with an Inserts to a Base Boot...... 63 Close-Punch 12–Bolt Pattern Laminated Stiffener to Laminated Base Stiffener with an Inserts to a Base Boot...... 64 Chapter 7 Roof Assembly...... 67 Attaching the Inside Stiffener to the Top Outside Stiffener ...... 67 Attaching the Eave Bracket to the Inside Stiffener...... 70 Attaching the Eave Angle to the Sidewall Sheet ...... 71 Connecting the Tension Member to the Eave Bracket ...... 73 Attaching the Center Collar Rafter Clips to the Rafter...... 74 About Temperature Cable Brackets and A-Frame Assemblies...... 75 Assembling the Temperature Cable Bracket ...... 78 Attachment Locations of Purlins to Rafters...... 81 Assembling Purlin Number 4 ...... 82 Assembling Purlin Number 3 ...... 84 Assembling Purlin Number 2 ...... 86 Assembling Purlin Number 1 ...... 88 Assembling a Double A-Frame ...... 91 Assembling the Center Collar ...... 94 Center Collar Placement ...... 97 Guidelines for Assembling and Lifting the A-Frame Rafter Sections ...... 99 Attaching the A-Frames to the Center Collar ...... 101 Attaching the A-Frame to the Eave Bracket...... 102 Assembling the Roof Panel Clips ...... 103 Installing the 6–Hole Intermediate Purlins ...... 106 Installing the 4–Hole Intermediate Purlins ...... 107 Attaching the Roof Panels...... 108 Installing the Roof Flashing ...... 114 Assemble and Install Center Collar Channels and Plates ...... 116 Installing the Conveyor Support Brackets to the Peak Cap ...... 123 Chapter 8 Accessories ...... 125 Installing Roof Ladder Steps...... 126 Roof Ring Placement...... 128 Installing a Roof Ring...... 129

4 Pneg-4075 75 Ft Diameter 40-Series Bin Table of Contents

Installation of Peak–To– Exhauster Ladder Kit ...... 131 Preparation for Roof Exhauster Installation...... 132 Assembling the Roof Exhauster...... 134 Installing Roof Exhauster Assembly ...... 135 Assembling the Auto Roof Vent ...... 138 Assembling Wire Grill Guard Roof Vent ...... 139 Installing the Wire Grill Guard and Auto Roof Vents ...... 141 Installing the Manway Cover...... 142 Ladder Section Assembly...... 144 Inside Ladder Placement...... 144 Installing Inside Ladder Bottom Bracket...... 148 Guidelines for Installing a Sidedraw System...... 149 Installing the Sidedraw Baffle Chute (Two Post Stiffener) ...... 152 Installing the Sidedraw Baffle Chute (Three Post Stiffener)...... 153 Installing the Sidedraw Discharge Chute ...... 155 Wind Ring Requirements ...... 162 Installing Wind Rings ...... 163 Assembling Weather Cover for Roller Valve...... 165 GSI Group, LLC Limited Warranty...... 167

Pneg-4075 75 Ft Diameter 40-Series Bin 5 NOTES

6 Pneg-4075 75 Ft Diameter 40-Series Bin 1 Safety Precautions

Topics Covered in this Chapter ▪ Safety Guidelines ▪ Cautionary Symbols ▪ Safety Decals ▪ Safety Sign-off Sheet

Safety Guidelines Safety guidelines are general-to-specific safety rules that must be respected at all times in the grain stor- age environment. Our foremost concern is your safety and the safety of others associated with grain handling equipment. This manual is to help you understand safe operating procedures and some problems that can be encoun- tered by the operator and other personnel. As owner and/or operator, you are responsible to know what requirements, hazards, and precautions exist and inform all personnel associated with the equipment or in the area. Avoid any alterations to the equip- ment. It can produce a very dangerous situation, where SERIOUS INJURY or DEATH can occur. This equipment shall be installed in accordance with the current installation codes and applicable regula- tions, which should be carefully followed in all cases. Authorities having jurisdiction must be consulted before installations are made. You should consider the location of the bin site relative to power line locations or electrical transmission equipment. Contact your local power company to review your installation plan or for information concerning required equipment clearance. Clearance of portable equipment that can be taken to the bin site must also be reviewed and considered. Any electrical control equipment in contact with the bin must be properly grounded and installed in accordance with National Electric Code provisions and all local codes. This product is intended for the use of grain storage only. Any other use is a misuse of the product.

This product has sharp edges, which may cause serious injury. To avoid injury, handle sharp edges with caution and always use proper protective clothing and CAUTION equipment.

Sidewall bundles or sheets must be stored in a safe manner. The safest method of storing sidewall bundles is laying horizontally with the arch of the sheet upward, like a dome. Sidewall sheets stored on edge must be secured so that they cannot fall over and cause injury. Use care when handling and moving sidewall bundles. Personnel operating or working around equipment must read this manual. This manual must be delivered with equipment to its owner. Failure to read this manual and its safety instructions is a misuse of the equipment.

Pneg-4075 75 Ft Diameter 40-Series Bin 7 Chapter 1: Safety Precautions

Follow Safety Instructions — Read and Understand Manual

• Carefully read all safety messages in this manual and safety signs on your machine. Keep signs in good condition. Replace missing or damaged safety signs. Be sure new equipment components and repair parts include the current safety signs. Replacement safety signs are available from the manufacturer.

• Learn how to operate the machine and how to use controls properly. Do not let anyone operate without instruction.

• Keep your machinery in proper working condition. Unauthor- ized modifications to the machine can impair the function and/or safety and affect machine life.

• If you do not understand any part of this manual or need assistance, contact your dealer.

Practice Safe Maintenance — Maintain Equipment and Work Area

• Understand service procedures before doing work. Keep area clean and dry.

• Never lubricate, service, or adjust machine while it is in oper- ation. Keep hands, feet, and clothing away from rotating parts.

• Keep all parts in good condition and properly installed. Fix damage immediately. Replace worn or broken parts. Remove any built-up grease, oil, and debris.

Prepare for Emergencies — Keep Emergency Equipment Accessible

• Be prepared if fire starts.

• Keep a first aid kit and fire extinguisher handy.

• Keep emergency numbers for doctors, ambulance service, hospital, and fire department near your telephone.

Wear Protective Clothing

• Wear close-fitting clothing and safety equipment appropri- ate to the job.

• Remove all jewelry Eye Protection • Tie long hair up and back.

• Wear safety at all times to protect eyes from debris.

8 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 1: Safety Precautions

• Wear gloves to protect your hands from sharp edges on Gloves plastic or steel parts.

• Wear steel-toed boots to help protect your feet from falling Steel-Toed Boots debris. Tuck in any loose or dangling shoestrings.

• A respirator may be needed to prevent breathing poten- Respirator tially toxic fumes and dust.

• Wear a hard to help protect your head. Hard Hat

• Wear appropriate fall protection equipment when working Fall Protection at elevations greater than 6 ft (1.8 m).

Cautionary Symbols Cautionary symbols appear in the various decals of your product, and alerts the user of potential or immi- nent risk of danger. This manual contains information that is important for you, the owner/operator, to know and understand. This information relates to protecting personal safety and preventing equipment problems. It is the responsibility of the owner/operator to inform anyone operating or working in the area of this equip- ment of these safety guidelines. To help you recognize this information, we use the symbols that are defined below. Please read the manual and pay attention to these sections. Failure to read this manual and its safety instructions is a misuse of the equipment and may lead to serious injury or death.

Make sure to familiarize yourself with these symbols prior to installing, operating, or servicing your grain equipment. Failure to do so may lead to serious injury or death. DANGER

Table 1-1 Description of the different cautionary symbols

Symbol Description

This symbol indicates an imminently hazardous situation which, if not avoided, will result in serious injury or death.

This symbol indicates a potentially hazardous situation which, if not avoided, may result in serious injury or death.

Pneg-4075 75 Ft Diameter 40-Series Bin 9 Chapter 1: Safety Precautions

Table 1-1 Description of the different cautionary symbols (cont'd.)

Symbol Description

This symbol indicates a potentially hazardous situation which, if not avoided, may result in minor or moderate injury.

This symbol indicates a potentially hazardous situation which, if not avoided, may result in property damage.

Safety Decals The safety decals on your grain equipment are safety indicators which must be carefully read and under- stood by all personnel involved in the installation, operation, service, and maintenance of the grain equipment. The manufacturer does not warrant any roof damage caused by excessive vacuum or internal pressure from fans or other air moving systems. Adequate ventilation and/or “makeup air” devices should be pro- vided for all powered air handling systems. The manufacturer does not recommend the use of downward flow systems (suction). Severe roof damage can result from any blockage of air passages. Running fans during high humidity and cold weather conditions can cause air exhaust or intake ports to freeze.

10 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 1: Safety Precautions

ATTENTION: Decal shown below must be present on the outside of the door cover of the two ring, 24 in. (61 cm) porthole door cover and the roof manway cover. If a decal has been damaged or is missing in any of these locations, contact the manufacturer for a free replacement decal. GSI Decals 1004 E. Illinois Street Assumption, IL 62510 Phone: 1–217–226–4421

Pneg-4075 75 Ft Diameter 40-Series Bin 11 Chapter 1: Safety Precautions

ATTENTION: Decal shown below must be present on the outside of the door cover of the two ring, 24 in. (61 cm) porthole door cover and the roof manway cover. If a decal has been damaged or is missing in any of these locations, contact the manufacturer for a free replacement decal. GSI Decals 1004 E. Illinois Street Assumption, IL 62510 Phone: 1–217–226–4421

12 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 1: Safety Precautions Safety Sign-off Sheet Sign-off sheet verifying that all personnel have read and understood the safety instructions. As a requirement of O.S.H.A., it is necessary for the employer to train the employee in the safe operating and safety procedures for this equipment. This sign-off sheet is provided for your convenience and per- sonal record keeping. All unqualified persons must stay out of the work area at all times. It is strongly rec- ommended that another qualified person who knows the shutoff procedure be in the area in the event of an emergency.

Date Employee Name Supervisor Name

Pneg-4075 75 Ft Diameter 40-Series Bin 13 NOTES

14 Pneg-4075 75 Ft Diameter 40-Series Bin 2 General Overview

Topics Covered in this Chapter ▪ General Information ▪ Anchor Bolt Charts ▪ Tools Required for Construction ▪ Guidelines for Proper Storage of Grain Bin Materials Prior to Construction ▪ Overview for a Typical Bin Installation ▪ Guidelines for Construction Procedures and Lifting Jack Usage ▪ Guidelines for Placement of the Decal Sidewall Sheet ▪ Sample Gauge Sheet

General Information General information, overview and instructions needed before performing work. Read this manual carefully. This manual will provide instructions on building the sidewall and stiffeners. You will also need to consult other instructions in building the tank. These include, but may not be limited to: • A stiffener and sidewall gauge layout chart. If such a chart is not included with this manual, contact GSI. • Roof instructions must be followed. Roof instructions are included in this manual. • Ladders, roof stairs, roof handrails and other products are covered by separate instruction manuals. Consult the appropriate accessory manual. Inside ladder instructions are included in this manual. • Aeration systems and transitions are to be installed according to the instructions provided with the system or transition. • It is critical that the anchor bolts are installed and spaced correctly. Anchor Bolt Charts Prior to setting any anchor bolts, you must be sure to have the correct anchor bolt placement. This is very critical for stiffener alignment during bin erection. NOTE: Refer to the proper chart to find the anchor chord dimensions that correspond to the bin that is being built. Start with one anchor bolt and work from it to the left to locate one quarter of the anchor bolts then to the right to locate another quarter of the bolts. Working off of the last anchor bolts in each quarter, locate the remaining anchor bolts in the last two quarters.

Pneg-4075 75 Ft Diameter 40-Series Bin 15 Chapter 2: General Overview

Figure 2-1 Anchor bolt chords for 75 diameter 3–post bin

Bolt Radius (B) Anchor Quantity ft and in m 37 – 8-7/16 11.492 75

Length Length Chord (A) Chord (A) ft and in m ft and in m 1 3 – 1-15/16 0.964 10 30 – 8-1/16 9.349 2 6 – 3-3/4 1.924 11 33 – 6-3/8 10.220 3 9 – 5-7/16 2.881 12 36 – 3-15/16 11.073 4 12 – 6-15/16 3.834 13 39 – 3/4 11.906 5 15 – 8-1/8 4.778 14 41 – 8-3/4 12.719 6 18 – 9-1/16 5.717 15 44 – 3-7/8 13.510 7 21 – 9-9/16 6.644 16 46 – 10-1/16 14.276 8 24 – 9-5/8 7.560 17 49 – 3-1/4 15.018 9 27 – 9-1/8 8.461 18 51 – 7-7/16 15.734

16 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 2: General Overview Tools Required for Construction General tools needed to perform this construction • Combination wrench set 7/16 in. to 1 in. • Alignment punches 12 in. long • 1/2 in. Drive socket set and ratchet • Nail aprons or tool pouches to hold supplies • Gloves for hand protection • Tape measure • 1/2 in. Drive electric or pneumatic torque gun with variable impact capabilities • 1/2 in. Drive impact socket set • Lifting jacks • Center pole roof support • Step ladders • Large C-clamp or welding V-grip for clamping NOTE: Quantities required will depend on the number of workers and size of the bin. Guidelines for Proper Storage of Grain Bin Materials Prior to Construction Storage of the build materials prior to construction is important. Do not to allow moisture to remain between sheets or panels. Wet storage stain (rust) will develop when closely packed bundles of galvanized material, such as sidewall and roof sheets, have moisture present. Inspect roof and sidewall bundles on arrival for any moisture. If moisture is present, it must not be allowed to remain between the sheets. Separate the sheets or panels immediately and wipe them down. Spray with a light oil or diesel fuel If possible, sidewall bundles, roof sheets and other closely packed galvanized materials should be stored in a dry, climate controlled building. If outdoor storage is unavoidable, the materials should be stored so that they are raised above the ground and vegetation. Any stacking and spacing materials should not be corrosive or wet. Be sure to protect materials from the weather, but permit air movement around the bun- dles if possible. Storing roof bundles and sidewall sheets at a slight incline can also help minimize the presence of mois- ture. Storing the bundles with the center of the dome up (like an arch) is one option for minimizing moisture during storage. Sidewall bundles can also be stored on edge but must be secured so that they do not fall over and cause injury. If “white rust” or “wet storage stain” occurs, contact the manufacturer immediately about ways to minimize the adverse effect upon the galvanized coating.

Pneg-4075 75 Ft Diameter 40-Series Bin 17 Chapter 2: General Overview Overview for a Typical Bin Installation These are the typical steps one would perform when constructing a grain bin. Procedures may vary depending different site requirements. Pre-Assembly Activities • Sorting and grouping parts • Assemble A-frames • Assemble center collar • Assemble cap plate Assembly • Build two rings of sidewall sheets for even ringed bins or one ring or three rings for odd ringed bins, making sure to caulk all seams. • Add top outside stiffeners and inside stiffeners at the same time to the two rings of sidewall sheets (Note: These top stiffeners are the lightest gage stiffeners and will get heavier as the bin is raised. Therefore, the heaviest stiffeners are located at the bottom of the bin and are installed last. • Install wind ring to help support the rings • Install the center collar tower support in the center of the bin • Install the eave brackets to the inside stiffeners • Install eave angles to the sidewall sheets (Note how these are aligned.) • Install the tension member to the eave brackets • Lift pre-assembled A-frames, installing them in “opposite pairs” (across from one another) to balance out the load as you install • Install lower roof panels • Install upper roof panels • Cut roof exhauster holes evenly spaced in upper panels • Install upper flashing • Install roof exhauster • Install flat top

18 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 2: General Overview Guidelines for Construction Procedures and Lifting Jack Usage The following procedure is a guideline when using the required lifting jack. Follow this general guideline when lifting the bin as sidewalls are being installed. NOTE: The roof and the top ring for odd ringed bins or the roof and two rings for even ringed bins, will be installed prior to the beginning of bin lifting procedures. Refer to all other procedures on sidewall and stiffener installation prior to the start of construction. IMPORTANT: Begin building with the bin oriented for doors and material handling equipment to be in the correct position when bin construction is complete. 1. Consider the starting location of the bin, relative to the location of doors and other accessories. Proper placement of lifting jacks in relationship to anchor bolts could make a difference in final loca- tions. Note that the sidewall sheets will be staggered. 2. The bin is lifted by the use of lifting jacks. Lifting jacks are used to slowly and evenly lift the bin during construction. Lifting jacks must be properly sized and designed to carry all loads and job site condi- tions associated with the construction of the bin.. The number of lifting jacks required is best determined by personal experience and expertise. Factors such as bin size, jack design, construction conditions, support surface, etc., are all to be considered when deciding how many to use. If in doubt, use one jack on every sheet. The lifting jack must be adequate to carry all loads. Heavy duty jacks, generally hydraulic or electric powered in the case of large bins, should be used for commercial installation. All jacks should be secured with braces or oth- erwise maintained in a stable condition.. Lifting of the bins should not be done under windy conditions Follow the jack manufacturers recommendations on capacity and operations. 3. Lifting brackets should be attached through the stiffener bolt holes. Normally you will need to attach to at least four (4) bolts per stiffener. 4. Raise the bin just high enough to assemble the next ring. When lifting the bin, all jacks must lift at an equal rate. Monitor the lift to ensure even lifting is occurring. 5. To the inside of the first ring, bolt the next ring. Be sure to stagger the sheets and select the proper gauge material. 6. Lower the bin onto the foundation after assembling and tightening bolts on the new ring or rings. 7. Attach stiffeners to the body sheets every two (2) tiers (on the external surface of the bin). You may want to leave sheets loose to make the attachment of the stiffeners easier. 8. Now re-bolt the lifting brackets to the lowest ring in place thus far. Continue ring additions by repeat- ing Step 5 and Step 6. 9. Add inside and outside ladders as you continue to raise the bin. (Refer to the manual supplied with the ladder.) 10.Lower the tank and secure to the foundation before leaving the job site. 11.At the completion of the tank, set stiffeners over the anchor bolts and measure the tank to ensure it is in a round condition. Consult with GSI for questions on tolerances. NOTE: For 2 ring doors or vehicle traffic doors, special placement issues may apply. Consult the special instructions provided with two ring doors or vehicle traffic doors for these options.

Pneg-4075 75 Ft Diameter 40-Series Bin 19 Chapter 2: General Overview Guidelines for Placement of the Decal Sidewall Sheet Use the following as a general guideline the proper decal sheet placement. NOTE: Refer to the stiffener to sidewall attachment detail and specific gauge sheet for the bin. The decal sheets are located in the third ring from the top. They are to be spaced evenly around the diameter of the bin. Figure 2-2 3 Post Bin with three rows of stiffeners used on each sidewall sheet

NOTE: Dashed lines represent stiffener locations. Sample Gauge Sheet A gauge sheet should be supplied with every bin and contains important information specific to your bin. The gauge sheet contains the specific details that are unique to your bin. You must reference this sheet to know the correct order to install the sidewall sheets and stiffeners. The gauge of the sidewall and stiffeners are marked with colors for identification. It is important to use the correct hardware for each type of connection. The gauge sheet will identify what hardware should be used in a vertical seam, horizontal seam, and an overlapping seam for each gauge. The gauge sheet will also identify the sidewall ring where the wind ring must be installed. This is indicated by the word ”Standard” under the wind ring column and in the row of the ring it must be installed. If a side- draw system is used, the word ”Additional” will be located in the row of the ring it must be installed. Doors are to be installed in the ring or rings denoted with (D).

20 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 2: General Overview

Figure 2-3 Sample Gauge Sheet for a 3-Post 75 Diameter Bin

Pneg-4075 75 Ft Diameter 40-Series Bin 21 Chapter 2: General Overview

All information, illustrations, photos, and specifications in this manual are based on the latest information available at the time of publication. The right is reserved to make changes at any time without notice.

22 Pneg-4075 75 Ft Diameter 40-Series Bin 3 Hardware Requirements

Topics Covered in this Chapter ▪ Bolt and Nut Pairings ▪ Hardware for 3–Post Sidewall Sheets on bins that are 18 to 90 Ft in Diameter and 105 Ft Bins that are 27 Rings and Shorter ▪ Bolt Torque Specifications ▪ Identifying Bolt Grades ▪ Color Chart for Bin Hardware Bucket Lids ▪ Bolt Identification

Bolt and Nut Pairings This chart lists the correct nut to use with each size of bolt.

Nut Part Number Nut Size Type Hex or Flanged Bolt Size Bolt Part Number 5/16 x 3/4 S-275 S-396 5/16 YDP Hex 5/16 x 1 1/4 S-277 S-3611 5/16 YDP Flanged 5/16 x 1 S-10260 3/8 x 1 S-7487 S-456 3/8 YDP Hex 3/8 x 1 1/2 S-7488 3/8 x 2 S-10165 3/8 x 1 S-7485 S-9426 3/8 JS Flanged 3/8 x 1 1/2 S-7488 7/16 x 1 1/2 S-10262 S-9281 7/16 JS Hex 7/16 x 2 S-9389 7/16 x 3 1/4 S-10261 S-10253 1/2 YDP Flanged 1/2 x 1 3/4 S-10252 Hardware for 3–Post Sidewall Sheets on bins that are 18 to 90 Ft in Diameter and 105 Ft Bins that are 27 Rings and Shorter Reference this chart for the hardware requirements for 3–post sidewall sheet connections on bins 18 to 90 ft. in diameter. Reference this chart for the hardware requirements for 3–post sidewall sheet connections on bins 105 ft. in diameter that are 27 rings and shorter. Table 3-1 Hardware for 3-Post Sidewall Sheets on 18 to 90 ft. bins and 105 ft Diameter Bins that are 27 Rings and shorter Horizontal Seam Vertical Seam Bolt Stiffener to Sidewall Overlap Seam Bolt Gauge Bolt Size (Quantity) Size (Quantity) Bolt Size (Quantity) Size (Quantity) 20 3/8 x 1 (10) 3/8 x 1 (24) 3/8 x 1 (12) 3/8 x 1 (2) 19 3/8 x 1 (10) 3/8 x 1 (24) 3/8 x 1 (12) 3/8 x 1 (2) 18 3/8 x 1 (10) 3/8 x 1 (24) 3/8 x 1 (12) 3/8 x 1 (2)

Pneg-4075 75 Ft Diameter 40-Series Bin 23 Chapter 3: Hardware Requirements

Table 3-1 Hardware for 3-Post Sidewall Sheets on 18 to 90 ft. bins and 105 ft Diameter Bins that are 27 Rings and shorter (cont'd.) Horizontal Seam Vertical Seam Bolt Stiffener to Sidewall Overlap Seam Bolt Gauge Bolt Size (Quantity) Size (Quantity) Bolt Size (Quantity) Size (Quantity) 17 3/8 x 1 (10) 3/8 x 1 (36) 3/8 x 1 (12) 3/8 x 1 (2) 16 3/8 x 1 (10) 3/8 x 1 (36) 3/8 x 1 (12) 3/8 x 1 (2) 15 3/8 x 1 (22) 3/8 x 1 (48) 3/8 x 1 (12) 3/8 x 1 (2) 14 3/8 x 1 (22) 3/8 x 1 (48) 3/8 x 1 (12) 3/8 x 1 (2) 13 3/8 x 1 (22) 3/8 x 1 (48) 3/8 x 1 (12) 3/8 x 1 (2) 12 3/8 x 1 (22) 3/8 x 1 (48) 3/8 x 1 (12) 3/8 x 1 (2) 11 3/8 x 1 (22) 3/8 x 1 (48) 3/8 x 1 (12) 3/8 x 1 (2) 10 3/8 x 1 (22) 3/8 x 1 (48) 3/8 x 1 (12) 3/8 x 1 (2) 9 3/8 x 1 (22) 3/8 x 1 (48) 3/8 x 1.5 (12) 3/8 x 1.5 (2) 8 3/8 x 1 (22) 3/8 x 1 (48) 3/8 x 1.5 (12) 3/8 x 1.5 (2) 6 3/8 x 1.5 (22) 3/8 x 1.5 (48) 3/8 x 1.5 (12) 3/8 x 1.5 (2) 5 3/8 x 1.5 (22) 3/8 x 1.5 (48) 3/8 x 1.5 (12) 3/8 x 1.5 (2) 11L 3/8 x 1.5 (22) 3/8 x 1.5 (48) 3/8 x 1.5 (12) 3/8 x 1.5 (2) 10L 3/8 x 1.5 (22) 3/8 x 1.5 (48) 3/8 x 1.5 (12) 3/8 x 1.5 (2) 9L 3/8 x 1.5 (24) 7/16 x 1.5 (48) 3/8 x 1.5 (24) 3/8 x 1.5 (6) 8L 3/8 x 1.5 (24) 7/16 x 1.5 (48) 3/8 x 1.5 (24) 3/8 x 1.5 (6) Bolt Torque Specifications The specification torque table below will help the installer determine how tight a specific bolt must be. A bolt that has been over tightened can be just as dangerous as one that hasn't been tightened enough. IMPORTANT: Bolts should not be tightened in excess of the torque specifications chart listed below.

Bolt Minimum Torque Maximum Torque Structural Joints Structural Joints Sealing Joints Sealing Joints (joints without (joints without (joints with seal- (joints with seal- any sealing any sealing ing washers) ing washers) washers) washers) ft-lb N-m ft-lb N-m ft-lb N-m ft-lb N-m 5/16-18 JS Gr 8 with seal 20 27 —— 25 34 —— 3/8 -16 JS Gr 8 with seal 30 41 —— 35 47 —— 7/16-14 JS Gr 8 with seal 50 68 —— 60 81 —— 3/8–16 YDP Gr 8 flanged — — 45 61 —— 55 75 7/16–14 YDP Gr 8 flanged — — 85 115 —— 95 129 1/2-13 YDP Gr 8 flanged — — 125 169 —— 140 189

24 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 3: Hardware Requirements Identifying Bolt Grades Bolts are identified by grade (or hardness), the grade can be identified by the markings on the head of the bolt. These markings will be in the form of slash marks and patterns. Use the following as a guide to deter- mine the correct bolt grade.

Under no condition shall any other bolts be substituted for those supplied by GSI.

CAUTION

Grade 2 Bolts

Grade 2 bolts are designated with a plain head and are not used in GSI grain bins.

Grade 5 Bolts

Grade 5 bolts are designated by three slash marks on the head. All 5/16 inch diameter bolts are to be grade 5 or higher.

Grade 8 Bolts

Grade 8 bolts are designated by six slash marks evenly spaced out around the head of the bolt. All 3/8, 7/16, and 1/2 inch diameter bolts are to be grade 8 or grade 8.2.

Grade 8.2 Bolts

Grade 8.2 bolts are designated by six slash marks on the head in a sunrise pattern. All 3/8, 7/16, and 1/2 inch diameter bolts are to be grade 8 or grade 8.2.

NOTE: Refer to 2.66" commercial tank bolting requirements for complete bolt usage.

Pneg-4075 75 Ft Diameter 40-Series Bin 25 Chapter 3: Hardware Requirements Color Chart for Bin Hardware Bucket Lids For ease of identification, hardware is separated and identified by buckets with color coded lids. Use the following chart to help identify the correct hardware.

Part # Color Bucket Lid Color Description Count

S-275 Dark Blue 1500 5/16 x 3/4 in. YDP bolt pre-assembled with sealing washer

S-10260 Lime Green 1250 5/16 x 1 in. YDP bolt pre-assembled with sealing washer

S-277 Black 1000 5/16 x 1 1/4 in. JS bolt pre-assembled with sealing washer

S-396 Red 5000 5/16 in. JS hex nut

S-3611 NA NA In Box 5/16 in. YDP flange nut

S-7487 Grey 850 3/8 x 1 in. JS bolt pre-assembled with sealing washer

S-7485 Light Green 1000 3/8 x 1 in. flanged JS bolt without sealing washer

S-7488 Orange 650 3/8 x 1 1/2 in. JS bolt pre-assembled with sealing washer

S-7486 Dark Brown 700 3/8 x 1 1/2 in. flanged JS bolt without sealing washer

S-10165 Light Blue 500 3/8 x 2 in. JS bolt pre-assembled with sealing washer

S-7489 Yellow 4000 3/8 in. JS hex nut

S-9426 Dark Purple 2500 3/8 in. JS flanged nut

S-10250 NA NA In Box 7/16 x 1 1/4 in. YDP flanged bolt

7/16 x 1 1/2 in. flanged JS bolt pre-assembled with sealing S-10262 White 500 washer

7/16 x 2 in. full threaded JS bolt pre-assembled with sealing S-9389 Light Purple 350 washer

S-10134 Dark Green 300 7/16 x 2 1/2 in. JS bolt pre-assembled with sealing washer

7/16 x 3 1/4 in. flanged JS bolt pre-assembled with sealing S-10261 Natural (Clear) 200 washer

S-9281 Fire Orange 1500 7/16 in. JS hex nut

S-8479 Light Brown 800 7/16 in. YDP special recessed nut

S-10251 NA NA In Box 7/16 in. YDP un-serrated flange nut

S-10252 NA NA In Box 1/2 x 1 3/4 in. YDP flange bolt

S-10253 NA NA In Box 1/2 in. YDP un-serrated flange nut

26 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 3: Hardware Requirements Bolt Identification Use the following information to identify the bolts and where each must be used during installation. Bolt S-275 An S–275 is a 5/16 x 3/4 in. YDP bolt that is pre-assembled with a sealing washer.

Bolt (S-275) is used in the following locations: • Use in accessories. • Color of bucket lid is dark blue.

A 0.945 in. (2.40 cm) C Grade 5 B 0.750 in. (1.90 cm) D Grade 5

Bolt S-10260 An S–10260 is a 5/16 x 1 in. JS bolt that is pre-assembled with a sealing washer.

Bolt (S-10260) is used in the following locations:

• Use to connect roof panels together where they overlap. • Use when connecting eave angle to sidewall sheet. • The color of the bucket lid is lime green. • Use to connect eave clip to sidewall sheet on bins that are 48 ft diameter and smaller. • Use to attach roof panels to flashing on bins that are 48 ft diame- ter and smaller.

A 1.300 in. (3.30 cm ) C Grade 8 B 1.000 in. (2.54 cm) D Grade 8.2

Bolt S-277 An S–277 is a 5/16 x 1 1/4 in. YDP bolt pre-assembled with a sealing washer.

Bolt (S-277) is used in the following locations: • Use in accessories. • The color of the bucket lid is black.

A 1.445 in. (3.67 cm ) C Grade 5 B 1.250 in. (3.17 cm) D Grade 5

Pneg-4075 75 Ft Diameter 40-Series Bin 27 Chapter 3: Hardware Requirements Bolt S-7485 An S–7485 is a 3/8 x 1 in. JS hex bolt with flanged head and without a sealing washer.

Bolt (S-7485) is used in the following locations:

• Use to splice the stiffeners together on the flanges. (A flange nut is used on the nut side of the connection.) • Use to splice the laminated stiffeners together. (A flange nut is used on the nut side of the connection.) • The color of bucket lid is light green.

A 1.350 in. (3.43 cm) C Grade 8 B 1.000 in. (2.54 cm) D Grade 8.2

Bolt S-7487 An S–7487 is a 3/8 x 1 in. JS bolt that is pre-assembled with a sealing washer.

Bolt (S-7487) is used in the following locations: • Use in all sidewall connections for 20 gauge through 10 gauge sidewall to sidewall sheets. • Use for horizontal and vertical seam connections for 9 gauge through 8 gauge sidewall sheets. • Use when attaching base angle to sidewall sheet on flat bottom bins. • Color of bucket lid is grey.

NOTE: Do not use to splice the stiffeners together on the flanges where they connect to each other or the splice plates.

A 1.350 in. (3.43 cm) C Grade 8 B 1.000 in. (2.54 cm) D Grade 8.2

Bolt S-7486 An S–7486 is a 3/8 x 1 1/2 in. JS hex bolt with a flanged head without a sealing washer.

Bolt (S-7486) is used in the following locations: • Use in special seismic tanks. • The color of the bucket lid is dark brown.

A 1.850 in. (4.70 cm) C Grade 8 B 1.500 in. (3.81 cm) D Grade 8.2

28 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 3: Hardware Requirements Bolt S-7488 An S–7488 is a 3/8 x 1 1/2 in. JS bolt that is pre-assembled with a sealing washer.

Bolt (S-7488) is used in the following locations:

• Use in all stiffener to sidewall and overlap connections where the sidewall is 9 gauge or thicker. • Use in vertical and horizontal seams on sidewall that is 6 gauge or thicker. • The color of the bucket lid is orange.

NOTE: Do not use in flanges where the splice plate bolts to the stiff- eners. Sealing washers should not be used for these connections.

A 1.850 in. (4.70 cm) C Grade 8 B 1.500 in. (3.81 cm) D Grade 8.2

Bolt S-10252 An S–10252 is a 1/2 x 1 3/4 in. YDP flange bolt.

Bolt (S-10252) is used in the following locations: • Use in bins 72 to 135 ft in diameter. • Use in tension plate to eave bracket connection. • Use in rafter clip to rafter connection. • Use in laminated purlins. • Use in purlin clip to rafter and purlin clip to purlin connections. • Use in X-brace to rafter connection. • Use in center collar splice connection. • Use in center collar channel clip to center collar. • Use in rafter to center collar and rafter to eave bracket connections. • Use in center collar channel to clip. • Delivered in a box, not a bucket.

A 1.833 in. (4.66 cm) C Grade 8 B 1.495 in. (3.80 cm) D Grade 8.2

Pneg-4075 75 Ft Diameter 40-Series Bin 29 Chapter 3: Hardware Requirements Bolt S-10261 An S–10261 is a 7/16 x 3 1/4 in. JS bolt that is pre-assembled with a sealing washer.

Bolt (S-10261) is used in the following locations:

• Use in wind ring splice and over pipe connections. • Lid color of bucket is natural (clear).

A 3.645 in. (9.26 cm) C Grade 8 B 3.250 in. (8.26 cm) D Grade 8.2

30 Pneg-4075 75 Ft Diameter 40-Series Bin 4 Assembling Sidewall Sheets

Topics Covered in this Chapter ▪ Color Codes for Sidewall Gauge Identification ▪ Orientation Detail for Top Sidewall Sheets ▪ Caulking Detail for Standard (Non-Laminated) Sheets ▪ Caulking Detail for Laminated Quad Pattern Sheets

Color Codes for Sidewall Gauge Identification Use this chart to interpret the color code painted on the corners of the sidewall sheets. Table 4-1 Color codes for sidewall gauges

Sidewall Gauge Color Code 20 Red 19 Black and Yellow 18 Orange 17 Light Blue and Pink 16 Blue 15 Red and Brown 14 Green 13 Dark Blue and Yellow 12 Black 11 Pink 10 Light Blue 9 Dark Blue and Orange 8 Yellow 6 White 5 Fluorescent Green Table 4-2 Stripe Colors for Special Sidewall Characteristics

Extra Stripe Colors Type of Sidewall Stripe Color BFT Blue Laminated Gold Hex Pattern Ochre Special Galvanized 115 Fluorescent Red and Orange Special Galvanized 140 Florescent Pink

Pneg-4075 75 Ft Diameter 40-Series Bin 31 Chapter 4: Assembling Sidewall Sheets

Table 4-2 Stripe Colors for Special Sidewall Characteristics (cont'd.)

Extra Stripe Colors Type of Sidewall Stripe Color Special Galvanized 160 Florescent Red and Fluorescent Pink NOTE: Stripe colors are located in the middle of each side of the bundle. Orientation Detail for Top Sidewall Sheets To avoid the misalignment of the holes, it is necessary to use the correct orientation of the sidewall sheet during installation. NOTE: Always assemble the top sidewall sheets with the orientation shown. Figure 4-1 3–Post top sidewall sheet orientation

A Top of the top sidewall sheet B Bottom of the top sidewall sheet

Caulking Detail for Standard (Non-Laminated) Sheets To keep out moisture from overlapping the sheets, it is necessary to apply caulk to each sheet prior to installing. NOTE: Always assemble the sidewall sheets with the overlap in the same direction. • Apply a strip of caulk near the outside edge of the outer sheet and between the outer two rows of bolts (A), then apply a strip of caulk 10 in. (25.4 cm) long along the horizontal seams (B), as shown in the figure below.

32 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 4: Assembling Sidewall Sheets

Figure 4-2 Standard and quad punched sidewall sheets as viewed from the outside

A Vertical strip of caulk B 10 in. (25.4 cm) Horizontal strip of caulk

• Before bolting the next ring into place, apply one 10 in. strip of caulk (C) on the front of the under- lapped sheet at each joint. • Also, place a 10 in. (25.4 cm) strip of caulk (D) along the lower horizontal edge of the lapping sheet at every vertical seam. This will fill the space that occurs between the holes caused by the overlapping sheets.

Pneg-4075 75 Ft Diameter 40-Series Bin 33 Chapter 4: Assembling Sidewall Sheets

Figure 4-3 Caulking detail as viewed from inside of the bin

C 10 in. (25.4 cm) Strip of caulk D 10 in. (25.4 cm) Strip of caulk

• Use the supplied tube caulk to fill the larger gaps that occur with heavier gauges and laminated gauges. See Caulking Detail for Laminated Quad Pattern Sheets, page 35 for details about caulk laminated sidewall sheets.

34 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 4: Assembling Sidewall Sheets Caulking Detail for Laminated Quad Pattern Sheets To keep out moisture from overlapping the sheets, it is necessary to apply caulk to each sheet prior to installing. Caulking and Assembling the Individual Sidewall Sheets Each sidewall sheet must be layered and caulked prior to assembling sidewall sheet seams together. Figure 4-4 Laminated quad punched sidewall panel view from outside of the bin

A Strip of caulking B 12 in. (30.4 cm) horizontal strip of caulking

Pneg-4075 75 Ft Diameter 40-Series Bin 35 Chapter 4: Assembling Sidewall Sheets

• When assembling two assembled laminated sheets to each other, apply a strip of caulk (A) near the outside edge of the outer sheet, between the outer two (2) rows of bolts and outside the last row of bolts. • Place a strip of caulk (B) 12 in. (30.4 cm) long to each the horizontal seams. NOTE: Before bolting the next ring into place, apply a strip of caulk 12 in. (30.4 cm) long on the front of the under lapped sheet at each joint. • Also, a 12 in. (30.4 cm) strip of caulk is to be placed along the lower horizontal edge of the lapping sheet at the vertical seam. This will fill the space that occurs between the holes caused by the over- lapping sheets. When assembling two sheets to make a laminated sheet assembly (C), apply a row of caulk all around the vertical seam. Use the supplied tube caulk to fill the larger gaps that occur with heavier gauges and laminated sheets. Figure 4-5 Caulking detail for assembled laminated sidewall sheets

B 12 in. (30.4 cm) horizontal strip of caulk C Laminated sheet detail (caulk not shown)

36 Pneg-4075 75 Ft Diameter 40-Series Bin 5 Base Angle Installation

Topics Covered in this Chapter ▪ Installing the Base Angle ▪ Anchor Bolt Detail ▪ Installing the Base Angle Shims ▪ Anchor Bolt Washer Installation

Installing the Base Angle Installing the base angle ring will help reinforce and seal the final ring. What You Should Know The base angle overlap should be offset two holes from the stiffener. Do not place overlap in line with the stiffener. 1. Place a section of the base angle (B) to the bottom portion of the final ring (A). NOTE: The sidewall sheet will sit on top of the base angle with the vertical portion of the base angle on the inside of the bin. and each end of the base angle will connect to the next base angle section. 2. Install bolts (C) and nuts (D) as shown, but leaving the end holes of each section unfilled until the next section is to be installed. 3. Attach the next base angle section overlapping the end holes (F) and install bolts (C) and nuts (D). 4. Repeat this procedure for the remaining base angle sections (B) over lapping the previously installed base angle section. 5. Before the bolts (C) are tightened, push the base angle tight against the bottom edge of each sheet. 6. Tighten the hardware to the recommended torque specifications, see Bolt Torque Specifications, page 24. 7. Before lowering the bin, apply the optional mastic sealer strip (G) to the entire underneath side of the base angle. NOTE: If optional mastic sealer strip is not used, it is recommended that some other method should be utilized to seal the base ring to the concrete. 8. Lower the bin onto the foundation and check for an adequate seal.

Pneg-4075 75 Ft Diameter 40-Series Bin 37 Chapter 5: Base Angle Installation

Figure 5-1 Exploded view of base angle (view from inside the bin)

A Final ring assembly D 3/8 in. nut (S-9426) B Base angle (B-6753) E Base angle offset example C 3/8 x 1 in. bolt (S-7487) F Optional mastic sealer (or equivalent)

38 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 5: Base Angle Installation Anchor Bolt Detail The following is the minimum requirement for anchorage on standard tanks. Refer to sidedraw instructions for special anchorage details. • 3/4 in. diameter anchor bolt (A) is the minimum allowed. • Exposed anchor bolt thread height (B), 3 in. (7.62 cm) • Overall anchor bolt length (C), 18 in. (45.72 cm) • Hook Length (D), 4-3/4 in. (12.065 cm) Figure 5-2 Anchor bolt example (3/4 in. diameter anchor bolt shown)

Pneg-4075 75 Ft Diameter 40-Series Bin 39 Chapter 5: Base Angle Installation Installing the Base Angle Shims A section of the base boot plate will rest on top of the base angle, therefore causing the base boot to rest unevenly on the foundation. To offset this, base angle shims are required to ensure the base boot sets evenly on the foundation. What You Should Know 1. Place the required base angle shim around the anchor bolt next to the base angle. 2. Place the base stiffener over the anchor bolt onto the required shim. 3. If needed, add standard shims under the required base angle shim. NOTE: If more than one additional shim is required, then the shims must be welded together to the base plate or the base plate must be grouted to provide the proper elevation. Figure 5-3 Base Angle Shims

6 x 9 Base plate (CTS-2121XX or CTS- B-7028 (Required base angle shim for 8 x 10 base A E 2110XX) plate) B-7027 (Required base angle shim for 6 x B F SS-7212 (Standard shim for 8 x 10 base plate) 9 base plate) SS-6953 (Standard shim for 6 x 9 base C G Base angle (B-7025XX or B-7026XX) plate) 8 x 10 Base plate (CTS-2109XX or CTS- D 2131XX)

40 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 5: Base Angle Installation Anchor Bolt Washer Installation Anchor bolt washers help to cover the oversized hole in the base plate. Before You Begin Anchor bolts are secured, and base plates installed. 1. Place a square plate washer (B) onto the anchor bolt (A). NOTE: A square plate washer (provided) must be installed between the base boot (C) and washer (D). 2. Install a washer (D), and secure with a nut (E). 3. Tighten to the recommended torque specification, see Bolt Torque Specifications, page 24.

Figure 5-4 Base stiffener assembly

A 3/4 in. bolt assembly package (B-4161) D 3/4 in. washer (S-866) Square anchor plate washer (3/4 in. HT-635) , B E 3/4 in. nut (S-234) (1 in. B-6756) C Base boot

Pneg-4075 75 Ft Diameter 40-Series Bin 41 NOTES

42 Pneg-4075 75 Ft Diameter 40-Series Bin 6 Stiffeners

Topics Covered in this Chapter ▪ Stiffener Part Number Description ▪ Color Codes for Stiffener Gauge Identification ▪ Standard Stiffeners ▪ Top Stiffeners ▪ Stiffeners Splice ▪ Base Stiffeners ▪ Base Boots ▪ Close-Punch Connection for a One-Ring Top Stiffener (16 Ga) and a Two-Ring Stiffener (16 Ga) ▪ Two-Ring Top Stiffener to a Two-Ring Stiffener (15–16 Ga) Connection ▪ Close-Punch Connection for a Two-Ring Top Stiffener to a Two-Ring Stiffener (16 Ga) ▪ Two-Ring Stiffener (15-16 Ga) to a Two-Ring Stiffener (15–16 Ga) Connection ▪ Close-Punch Connection for a Two-Ring Stiffener (16 Ga) to a Two-Ring Stiffener (16 Ga) ▪ Two-Ring Stiffener (0–14 Ga) to a Two-Ring Stiffener (0–14 Ga) Connection ▪ Close-Punch Connection for a Two-Ring Stiffener (0–14 Ga) to a Two-Ring Stiffener (0–14 Ga) ▪ Two-Ring Stiffener (0–14 Ga) to a Close-Punch Base Stiffener (2–8 Ga) Connection ▪ Close-Punch Connection for a Two-Ring Stiffener (0–14 Ga) to a Base Stiffener (2–8 Ga) ▪ Two-Ring Stiffener (0–14 Ga) to a Base Stiffener (10–16 Ga) Connection ▪ Two-Ring Stiffener (2–14 Ga) to a Base Stiffener (10–16 Ga) Connection ▪ Two-Ring Stiffener (15–16 Ga) to a Base Stiffener (10–16 Ga) Connection ▪ Close-Punch Connection for a Two-Ring Stiffener (16 Ga) to a Base Stiffener (10–16 Ga) ▪ Close-Punch Two-Ring Stiffener (2–14 Ga) to a Laminated Stiffener (2 Ga) with an Insert (10– 14 Ga) ▪ Close-Punch Laminated Stiffeners (2 Ga) with Inserts (10–14 Ga) ▪ Close-Punch Laminated Stiffener (2 Ga) with an Insert (10–14 Ga) to a Laminated Base Stiff- ener (2–5 Ga) with a Base Insert (2–14 Ga) ▪ Base Stiffener (10–16 Ga) to a Base Boot Connection ▪ Close-Punch Connection for a Base Stiffener (10–16 Ga) to a Base Boot ▪ Close-Punch Connection for a Base Stiffener (2+2 Ga – 8 Ga) to a Base Boot ▪ Close-Punch Laminated Base Stiffener (2 Ga) with Insert (2+14 to 2+10 Ga) to a Base Boot ▪ Close-Punch Standard Stiffener to a 12–Bolt Pattern Laminated Stiffener with Insert ▪ 12–Bolt Pattern Close-Punch Laminated Stiffeners with Insert ▪ Close-Punch 12–Bolt Pattern Laminated Stiffener to Laminated Base Stiffener with an Inserts to a Base Boot ▪ Close-Punch 12–Bolt Pattern Laminated Stiffener to Laminated Base Stiffener with an Inserts to a Base Boot

Pneg-4075 75 Ft Diameter 40-Series Bin 43 Chapter 6: Stiffeners Stiffener Part Number Description Part numbers are printed on the end of each stiffener with the last two numbers designating the gauge of the material. Example: CTS-206314 will be printed on a 14 gauge, standard two-ring stiffener. If the stiffener was 8 gauge, it would change the part number to CTS-206308. The part numbers in the following tables use an “XX” at the end of the number to represent the gauge of the material. Color Codes for Stiffener Gauge Identification Use these charts to interpret the color code painted on the ends of the stiffeners.

Table 6-1 Color codes for stiffener gauges Table 6-2 Stripe color codes for stiffener gauges

Sidewall Gauge Color Code Stiffener Type Stripe Color 0 No Color (Zinc) Base Stiffener Red 2 Ochre Back (Laminated) Dark Green 5 Fluorescent Green Insert (Laminated) Gold 6 White Close Punched Light Blue 8 Yellow Special Galvanized 115 Fluorescent Red and 9 Dark Blue and Orange Orange 10 Light Blue Special Galvanized 140 Florescent Pink 11 Pink Special Galvanized 165 Florescent Pink and 12 Black Fluorescent Orange 13 Dark Blue and Yellow 12–Bolt Pattern Brown Stiffener 14 Dark Green NOTE: Extra colored stripes will be centered on 15 Red and Brown the gauge color. If more than one color of stripe is 16 Dark Blue needed, they will be painted next to each other and 17 Light Blue and Pink centered on the gauge color. 18 Orange

44 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 6: Stiffeners Standard Stiffeners Use the following information to determine the differences between the types of standard two-ring stiffeners. Figure 6-1 Standard stiffeners

Call Part Number Description Length Available Out Gauges A CTS-2063XX Two-ring stiffener 63.938 in. (162 cm) 10 – 14 B CTS-2064XX Two-ring stiffener 63.938 in. (162 cm) 15 – 16 C CTS-2073XX Two-ring stiffener (close-punch) 63.938 in. (162 cm) 2–10,12,14 D CTS-2075XX Two-ring stiffener (close-punch) 63.938 in. (162 cm) 16 E CTS-2079XX Two-ring laminated stiffener 63.938 in. (162 cm) 2 – 5 (close-punch) F CTS-2081XX Two-ring insert (close-punch) 63.938 in. (162 cm) 10–14 G CTS-2137XX Two-ring laminate stiffener (close- 63.938 in. (162 cm) 2 punch) H CTS-2138XX Two-ring insert (close-punch) 63.938 in. (162 cm) 2–14

Pneg-4075 75 Ft Diameter 40-Series Bin 45 Chapter 6: Stiffeners Top Stiffeners Use the following information to determine the differences between the three types of top stiffeners. Figure 6-2 Images of the top stiffeners

Call Part Number Description Length Available Out Gauges A CTS-2069XX Inside stiffener (for roof) 23.938 in. (56 cm) 2 – 8, 10, 12, 14 B CTS-2118XX One-ring top stiffener (close 21.938 in. (56 cm) 16 punch) C CTS-2111XX Two-ring top stiffener 53.938 in. (137 cm) 15 – 16 D CTS-2116XX Two-ring top stiffener 53.938 in. (137 cm) 16 (close-punch)

46 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 6: Stiffeners Stiffeners Splice Use the following information to determine the gauge of the splice needed to connect the stiffeners. Figure 6-3 Stiffener splice

Call Out Part Number Description Length Available Gauges A CTS–2091XX Stiffener splice 10 in. (25.4 cm) 8, 10, 12, 14

Use the following chart to determine the gauge of the splice, which is determined by the gauge of the stiff- eners that are being connected. If connecting a heavier gauge to a lighter gauge stiffener, always use the heavier gauge splice for the 13 to 12, 8 to 6, and 2 to 0 gauge connections. For example: If connecting a 13 gauge stiffener to a 12 gauge stiffener, use the 12 gauge splice. If con- necting an 8 gauge stiffener to a 6 gauge stiffener, use the 10 gauge splice. If connecting a 2 gauge stiff- ener to a 0 gauge stiffener, use the 8 gauge splice.

Table 6-3 Splice Usage Splice Gauge Stiffener Gauge 8 Gauge 10 Gauge 12 Gauge 14 Gauge 18 X 17 X 16 X 15 X 14 X 13 X 12 X 11 X 10 X 9 X 8 X 6 X 5 X 2 X 0 X

Pneg-4075 75 Ft Diameter 40-Series Bin 47 Chapter 6: Stiffeners Base Stiffeners Use the following information to determine the differences between the base stiffeners. Figure 6-4 Images of the base stiffeners

Call Out Part Number Description Length Available Gauges A CTS–2119XX Base stiffener 72.094 in. (183 cm) 2 – 8 B CTS-2123XX Base stiffener 72.430 in. (184 cm) 9, 10, 12, 14, 16 C CTS-2115XX Base stiffener 72.094 in. (183 cm) 10, 12, 14, 16 D CTS-2114XX Laminated base stiffener 72.061 in. (183 cm) 2 – 5 E CTS-2113XX Base insert 66.438 in. (169 cm) 2 – 8, 10, 12, 14 F CTS-2133XX Laminated base stiffener 72.088 in. (183 cm) 2 G CTS-2134XX Base insert 71.775 in. (182 cm) 10,12,14 H CTS-2135XX Laminated base stiffener 71.775 in. (182 cm) 2 I CTS-2136XX Base insert 71.775 in. (182 cm) 2 – 8

48 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 6: Stiffeners Base Boots Use the following information to determine the differences between the base boots. Figure 6-5 Images of the base boots

Call Out Part Number Description Height Base Plate Size A CTS–2121XX Base boot weldment for 16 11.391 in. 6 x 9 x 3/8 in. through 9 Ga. base stiffeners (29 cm) (15 x 23 x 0.95 cm) B CTS-2110XX Base boot weldment for 8 through 11.391 in. 6 x 9 x 3/4 in. a laminated 2 Ga. with an 11 Ga. (29 cm) (15 x 23 x 1.90 insert cm) C CTS-2109XX Base boot for 2 Ga. laminated 11.391 in. 8 x 10 x 3/4 in. base stiffeners with inserts from (29 cm) (20 x 25 x 1.90 10 through 2 gauges. cm) D CTS-2131XX Base boot weldment for 2+8 to 2 11.391 in. 8 x 10 x 1–1/2 in. +2 base stiffeners. (29 cm) (20 x 25 x 3.81 cm)

Pneg-4075 75 Ft Diameter 40-Series Bin 49 Chapter 6: Stiffeners Close-Punch Connection for a One-Ring Top Stiffener (16 Ga) and a Two-Ring Stiffener (16 Ga) Reference the following information for a close-punch connection of a one-ring top stiffener (CTS-2118XX) to a two-ring stiffener (CTS-2075XX). Figure 6-6 One-Ring Top Stiffener (16 Ga) and a Two-Ring Stiffener (16 Ga) Close-Punch Connection

A One-ring top stiffener (CTS-2118XX) B Two-ring stiffener (CTS-2075XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Two-Ring Top Stiffener to a Two-Ring Stiffener (15–16 Ga) Connection Reference the following information when connecting a two-ring top stiffener (CTS-2111XX) to a two-ring stiffener (CTS-2064XX). Figure 6-7 Two-Ring Top Stiffener to a Two-Ring Stiffener (15–16 Ga) Connection

A Two-ring top stiffener (CTS-2111XX) B Two-ring stiffener (CTS-2064XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

50 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 6: Stiffeners Close-Punch Connection for a Two-Ring Top Stiffener to a Two-Ring Stiffener (16 Ga) Reference the following information for a close-punch connection of a two-ring top stiffener (CTS-2116XX) to a two-ring stiffener (CTS-2075XX). Figure 6-8 Two-Ring Top Stiffener to a Two-Ring Stiffener (16 Ga) Close-Punch Connection

A Two-ring top stiffener (CTS-2116XX) B Two-ring stiffener (CTS-2075XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Two-Ring Stiffener (15-16 Ga) to a Two-Ring Stiffener (15–16 Ga) Connection Reference the following information when connecting a two-ring stiffener (CTS-2064XX) to a two-ring stiff- ener (CTS-2064XX). Figure 6-9 Two-Ring Stiffener (15-16 Ga) to a Two-Ring Stiffener (15–16 Ga) Connection

A Two-ring stiffener (CTS-2064XX) B Two-ring stiffener (CTS-2064XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Pneg-4075 75 Ft Diameter 40-Series Bin 51 Chapter 6: Stiffeners Close-Punch Connection for a Two-Ring Stiffener (16 Ga) to a Two-Ring Stiffener (16 Ga) Reference the following information for a close-punch connection of a two-ring stiffener (CTS-2075XX) to a two-ring stiffener (CTS-2075XX). Figure 6-10 Two-Ring Stiffener (16 Ga) to a Two-Ring Stiffener (16 Ga) Close-Punch Connection

A Two-ring stiffener (CTS-2075XX) B Two-ring stiffener (CTS-2075XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Two-Ring Stiffener (0–14 Ga) to a Two-Ring Stiffener (0–14 Ga) Connection Reference the following information when connecting a two-ring stiffener (CTS-2063XX) to a two-ring stiff- ener (CTS-2063XX). Figure 6-11 Two-Ring Stiffener (0–14 Ga) to a Two-Ring Stiffener (0–14 Ga) Connection

A Two-ring stiffener (CTS-2063XX) B Two-ring stiffener (CTS-2063XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

52 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 6: Stiffeners Close-Punch Connection for a Two-Ring Stiffener (0–14 Ga) to a Two-Ring Stiffener (0–14 Ga) Reference the following information for a close-punch connection of a two-ring stiffener (CTS-2073XX) to a two-ring stiffener (CTS-2073XX). Figure 6-12 Two-Ring Stiffener (0–14 Ga) to a Two-Ring Stiffener (0–14 Ga) Close-Punch Connection

A Two-ring stiffener (CTS-2073XX) B Two-ring stiffener (CTS-2073XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Two-Ring Stiffener (0–14 Ga) to a Close-Punch Base Stiffener (2–8 Ga) Connection Reference the following information when connecting a two-ring stiffener (CTS-2063XX) to a close-punch two-ring stiffener (CTS-2119XX). Figure 6-13 Two-Ring Stiffener (0–14 Ga) to a Close-Punch Two-Ring Stiffener (2–8 Ga) Connection

A Two-ring stiffener (CTS-2063XX) B Close-punch two-ring stiffener (CTS-2119XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Pneg-4075 75 Ft Diameter 40-Series Bin 53 Chapter 6: Stiffeners Close-Punch Connection for a Two-Ring Stiffener (0–14 Ga) to a Base Stiffener (2–8 Ga) Reference the following information when connecting a two-ring stiffener (CTS-2073XX) to a base stiffener (CTS-2119XX). Figure 6-14 Two-Ring Stiffener (0–14 Ga) to a Two-Ring Stiffener (2–8 Ga) Close-Punch Connection

A Close-punch two-ring stiffener (CTS-2073XX) B Close-punch base stiffener (CTS-2119XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Two-Ring Stiffener (0–14 Ga) to a Base Stiffener (10–16 Ga) Connection Reference the following information when connecting a two-ring stiffener (CTS-2063XX) to a base stiffener (CTS-2123XX). Figure 6-15 Two-Ring Stiffener (0–14 Ga) to a Base Stiffener (10–16 Ga) Connection

A Two-ring stiffener (CTS-2063XX) B Base stiffener (CTS-2123XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

54 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 6: Stiffeners Two-Ring Stiffener (2–14 Ga) to a Base Stiffener (10–16 Ga) Connection Reference the following information for a close-punch connection of a two-ring stiffener (CTS-2073XX) to a base stiffener (CTS-2115XX). Figure 6-16 Two-Ring Stiffener (2–14 Ga) to a Base Stiffener (10–16 Ga) Close-Punch Connection

A Close-punch two-ring stiffener (CTS-2073XX) B Close-punch base stiffener (CTS-2115XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Two-Ring Stiffener (15–16 Ga) to a Base Stiffener (10–16 Ga) Connection Reference the following information when connecting a two-ring stiffener (CTS-2064XX) to a base stiffener (CTS-2123XX). Figure 6-17 Two-Ring Stiffener (15–16 Ga) to a Base Stiffener (10–16 Ga) Connection

A Two-ring stiffener (CTS-2064XX) B Base stiffener (CTS-2123XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Pneg-4075 75 Ft Diameter 40-Series Bin 55 Chapter 6: Stiffeners Close-Punch Connection for a Two-Ring Stiffener (16 Ga) to a Base Stiffener (10–16 Ga) Reference the following information for a close-punch connection of a two-ring stiffener (CTS-2075XX) to a base stiffener (CTS-2115XX). Figure 6-18 Two-Ring Stiffener (16 Ga) to a Base Stiffener (10–16 Ga) Close-Punch Connection

A Close-punch two-ring stiffener (CTS-2075XX) B Close-punch base stiffener (CTS-2115XX) C Splice (CTS-2091XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

56 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 6: Stiffeners Close-Punch Two-Ring Stiffener (2–14 Ga) to a Laminated Stiffener (2 Ga) with an Insert (10–14 Ga) Reference the following information for a close-punch connection with a two-ring stiffener (CTS-2073XX) to a laminated stiffener (CTS-2114XX) and insert (CTS-2113XX). Figure 6-19 Close-Punch Two-Ring Stiffener to a Laminated Stiffener with an Insert

A Close-punch two-ring stiffener (CTS-2073XX) B Close-punch laminated stiffener (CTS-2114XX) C Insert (CTS-2113XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Close-Punch Laminated Stiffeners (2 Ga) with Inserts (10–14 Ga) Reference the following information for a close-punch connection of a laminated stiffener (CTS-2079XX) to a laminated stiffener (CTS-2081XX). Figure 6-20 Close-Punch Laminated Stiffeners with Inserts

A Close-punch laminated stiffener (CTS-2079XX) B Close-punch insert (CTS-2081XX) C 3/8 x 1 Bolt (S-7485) D 3/8 Nut (S-9426) E Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Pneg-4075 75 Ft Diameter 40-Series Bin 57 Chapter 6: Stiffeners Close-Punch Laminated Stiffener (2 Ga) with an Insert (10–14 Ga) to a Laminated Base Stiffener (2–5 Ga) with a Base Insert (2–14 Ga) Reference the following information for a close-punch connection of a two-ring stiffener (CTS-2079XX and CTS-2081XX) to a laminated base stiffener and insert (CTS-2114XX and CTS-2113XX). Figure 6-21 Close-Punch Laminated Stiffener with an Insert to a Laminated Base Stiffener with a Base Insert

A Close-punch laminated stiffener (CTS-2079XX) B Close-punch insert (CTS-2081XX) C Close-punch laminated base stiffener (CTS- 2114XX) D Close-punch base insert (CTS-2113XX) E 3/8 x 1 Bolt (S-7485) F 3/8 Nut (S-9426) G Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

58 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 6: Stiffeners Base Stiffener (10–16 Ga) to a Base Boot Connection Reference the following information when connecting a base stiffener (CTS-2123XX) to a base boot (CTS- 2121XX). Figure 6-22 Base Stiffener (10–16 Ga) to a Base Boot Connection

A Base stiffener (CTS-2123XX) B Base boot (CTS-2121XX) C 3/8 x 1 Bolt (S-7485) D 3/8 Nut (S-9426) E Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Close-Punch Connection for a Base Stiffener (10–16 Ga) to a Base Boot Reference the following information for a close-punch connection for a base stiffener (CTS-2115XX) to a base boot (CTS-2121XX). Figure 6-23 Base Stiffener (10–16 Ga) to a Base Boot Close-Punch Connection

A Close-punch base stiffener (CTS-2115XX) B Close-punch base boot (CTS-2121XX) C 3/8 x 1 Bolt (S-7485) D 3/8 Nut (S-9426) E Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Pneg-4075 75 Ft Diameter 40-Series Bin 59 Chapter 6: Stiffeners Close-Punch Connection for a Base Stiffener (2+2 Ga – 8 Ga) to a Base Boot Reference the following information for a close-punch connection for a base stiffener (CTS-2119XX) to a base boot (CTS-2110XX). Figure 6-24 Base Stiffener (2+2 Ga – 8 Ga) to a Base Boot Close-Punch Connection

A Close-punch base stiffener (CTS-2119XX) B Close-punch base Boot (CTS-2110XX) C 3/8 x 1 Bolt (S-7485) D 3/8 Nut (S-9426) E Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

60 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 6: Stiffeners Close-Punch Laminated Base Stiffener (2 Ga) with Insert (2+14 to 2+10 Ga) to a Base Boot Reference the following information when connecting a close-punch laminated base stiffener (CTS-2114XX) to a base boot (CTS-2109XX or CTS-2110XX). Figure 6-25 Close-Punch Laminated Base Stiffener to a Base Boot

A Close-punch laminated base stiffener (CTS- 2114XX) B Close-punch base Insert (CTS-2113XX) C Close-punch base boot (CTS-2109XX or CTS- 2110XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Close-Punch Standard Stiffener to a 12–Bolt Pattern Laminated Stiffener with Insert Reference the following information for a close-punch connection of a standard stiffener (CTS-2073) to a 12–bolt pattern laminated stiffener (CTS-2137XX) with insert (CTS-2138XX). Figure 6-26 Close-Punch Standard Stiffener to a 12–Bolt Pattern Laminated Stiffener with Insert

A Close punch standard stiffener (CTS-2073XX) B Close-punch laminated stiffener (CTS-2137XX) C Close-punch insert (CTS-2138XX) D 3/8 x 1 Bolt (S-7485) E 3/8 Nut (S-9426) F Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Pneg-4075 75 Ft Diameter 40-Series Bin 61 Chapter 6: Stiffeners 12–Bolt Pattern Close-Punch Laminated Stiffeners with Insert Reference the following information for a close-punch connection of two 12–bolt pattern laminated stiff- eners (CTS-2137XX) with an inserts (CTS-2138XX). Figure 6-27 Close-Punch 12–Bolt Pattern Laminated Stiffeners with Insert

A Close-punch laminated stiffener (CTS-2137XX) B Close-punch Insert (CTS-2138XX) C 3/8 x 1 Bolt (S-7485) D 3/8 Nut (S-9426) E Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

62 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 6: Stiffeners Close-Punch 12–Bolt Pattern Laminated Stiffener to Laminated Base Stiffener with an Inserts to a Base Boot Reference the following information for a close-punch connection of a 12–bolt pattern laminated stiffener (CTS-2137) to a laminated base stiffener (CTS-2135XX) with a inserts (CTS-2138XX and CTS-2135XX) to a base boot (CTS-2131XX). Figure 6-28 Laminated Stiffener to Laminated Base Stiffener with an Inserts to a Base Boot

A Close-punch laminated stiffener (CTS-2137XX) E Base boot (CTS-2131XX) B Close-punch base Insert (CTS-2138XX) F 3/8 x 1 Bolt (S-7485) C Close-punch laminated base stiffener (CTS-2135XX) G 3/8 Nut (S-9426) D Close-punch base Insert (CTS-2136XX) H Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

Pneg-4075 75 Ft Diameter 40-Series Bin 63 Chapter 6: Stiffeners Close-Punch 12–Bolt Pattern Laminated Stiffener to Laminated Base Stiffener with an Inserts to a Base Boot Reference the following information for a close-punch connection of a 12–bolt pattern laminated stiffener (CTS-2137) to a laminated base stiffener (CTS-2133XX) with a inserts (CTS-2138XX and CTS-2134XX) to a base boot (CTS-2109XX or CTS-2110XX). Figure 6-29 Laminated Stiffener to Laminated Base Stiffener with an Inserts to a Base Boot

A Close-punch laminated stiffener (CTS-2137) E Base boot (CTS-2109XX or 2110XX) B Close-punch base Insert (CTS-2138XX) F 3/8 x 1 Bolt (S-7485) C Close-punch laminated base stiffener (CTS- G 3/8 Nut (S-9426) 2133XX) D Close-punch base Insert (CTS-2134XX) H Completed assembly

NOTE: Two-post stiffeners shown. The bolt pattern will vary for three-post. Only place bolts where holes in the stiffeners align with holes in the sidewall sheet.

64 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 6: Stiffeners

Pneg-4075 75 Ft Diameter 40-Series Bin 65 NOTES

66 Pneg-4075 75 Ft Diameter 40-Series Bin 7 Roof Assembly

Topics Covered in this Chapter ▪ Attaching the Inside Stiffener to the Top Outside Stiffener ▪ Attaching the Eave Bracket to the Inside Stiffener ▪ Attaching the Eave Angle to the Sidewall Sheet ▪ Connecting the Tension Member to the Eave Bracket ▪ Attaching the Center Collar Rafter Clips to the Rafter ▪ About Temperature Cable Brackets and A-Frame Assemblies ▪ Assembling the Temperature Cable Bracket ▪ Attachment Locations of Purlins to Rafters ▪ Assembling Purlin Number 4 ▪ Assembling Purlin Number 3 ▪ Assembling Purlin Number 2 ▪ Assembling Purlin Number 1 ▪ Assembling a Double A-Frame ▪ Assembling the Center Collar ▪ Center Collar Placement ▪ Guidelines for Assembling and Lifting the A-Frame Rafter Sections ▪ Attaching the A-Frames to the Center Collar ▪ Attaching the A-Frame to the Eave Bracket ▪ Assembling the Roof Panel Clips ▪ Installing the 6–Hole Intermediate Purlins ▪ Installing the 4–Hole Intermediate Purlins ▪ Attaching the Roof Panels ▪ Installing the Roof Flashing ▪ Assemble and Install Center Collar Channels and Cap Plates ▪ Installing the Conveyor Support Brackets to the Peak Cap

Attaching the Inside Stiffener to the Top Outside Stiffener The inside stiffener supports the eave bracket. It is installed to the inside perimeter of the sidewall sheet at the same time as the top outside stiffener. Two-post sidewall sheets will have two inside stiffeners per sheet and three-post sidewall sheets will have three inside stiffeners per sheet. The inside stiffeners are only located at the eave bracket locations in the sidewall sheet. What You Should Know NOTE: Do not tighten the nuts (C) until all hardware has been installed attaching the inside stiffener (CTS– 2069XX) to the sidewall and the outside stiffener. Bins with an odd number of rings will use the one-ring outside stiffener (CTS-2071XX), and bins with an even number of rings will use the two- ring outside stiffener (CTS-2111XX or CTS-2116XX). 1. From the inside perimeter of the sidewall, place the bolt (B) through the hole located approximately 4 in. down from the top of the sidewall sheet (A).

Pneg-4075 75 Ft Diameter 40-Series Bin 67 Chapter 7: Roof Assembly

NOTE: Install the bolts from the inside to the outside of the bin, passing through the inside stiffener, corrugation spacer, sealing washer, sidewall sheet, and outside stiffener and flange nut. 2. On the inside perimeter, install a sealing washer (F), corrugation spacer (E), and inside stiffener (D). 3. Install a flange nut (C) to the bolt (B) and repeat this process with the remaining hardware. Tighten hardware to the recommended torque specifications, see Bolt Torque Specifications, page 24. Figure 7-1 Inside stiffener to the one-ring top stiffener for bins with an odd number of rings

A Sidewall E Corrugation spacer (S-7041) B 3/8 x 1 in. flange bolt (S-7485) F Sealing washer (S-3558) C 3/8 in. flange nut (S-9426) G One-ring top stiffener (CTS-2071XX) D Inside stiffener (CTS-2069XX) H Assembled view

68 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

Figure 7-2 Inside stiffener to the two-ring top stiffener for bins with an even number of rings

A Sidewall E Corrugation spacer (S-7041) B 3/8 x 1 in. flange bolt (S-7485) F Sealing washer (S-3558) C 3/8 in. flange nut (S-9426) G Two-ring top stiffener (CTS-2111XX or CTS- 2116XX) D Inside stiffener (CTS-2069XX) H Assembled view

After You Finish Repeat this process for the remaining inside stiffeners.

Pneg-4075 75 Ft Diameter 40-Series Bin 69 Chapter 7: Roof Assembly Attaching the Eave Bracket to the Inside Stiffener Eave brackets secure the roof rafter to the sidewall. Before You Begin Install the inside stiffeners to the sidewalls before proceeding. 1. Attach the eave bracket (A) to the inside stiffener (C) and install flange bolts (D). 2. Install flange nuts (B) to the eave bracket and tighten to the recommended torque specifications. See Bolt Torque Specifications, page 24. Figure 7-3 View from inside of the sidewall of a bin

A Eave bracket (CTR-0429) C Inside stiffener (CTS-2069XX) B 3/8 in. flange nut (S-9426) D 3/8 x 1 in. flange bolt (S-7485)

After You Finish Repeat this process for the remaining eave brackets.

70 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly Attaching the Eave Angle to the Sidewall Sheet The eave angle secures each lower portion of the roof panels. What You Should Know Eave angles are bolted to the inside portion of the sidewall and will overlap each section. 1. Install the optional eave seal (F) along the top edge of the eave angle (A). 2. Locate the eave bracket (H) and align the holes of the first eave angle (A) with the holes of the one- ring top stiffener (I). IMPORTANT: For a sidewall sheet that spans four roof panels, the eave angle will align from inside stiffener to inside stiffener. This is very important to ensure the roof panels align prop- erly with the rafters. 3. Install flange bolts (D) and flange nuts (B), leaving the end holes open. NOTE: The quantity of flange bolts (D) and flange nuts (B) may vary, depending on the sidewall punch pattern. 4. Install the second eave angle (C) overlapping the first eave angle (A). 5. Install the flange bolts (D) and flange nuts (B), leaving the last hole open for the next eave angle to be installed. NOTE: The quantity of flange bolts (D) and flange nuts (B) may vary, depending on the sidewall punch pattern. 6. Bend the eave angle tabs (G) upward to conform with each roof panel rib. 7. Tighten all hardware to the recommended torque specification. See Bolt Torque Specifications, page 24.

Pneg-4075 75 Ft Diameter 40-Series Bin 71 Chapter 7: Roof Assembly

Figure 7-4 Exploded view of eave angle (four roof panels)

A First eave angle (CTR-0187) H Eave bracket (CTR-0429) B 5/16 in. flange nut (S-3611) I Outside top stiffener C Second eave angle (CTR-0187) J Inside stiffener (CTS-2069XX) D 5/16 x 1 in. flange bolt (S-10260) K Top of the top sidewall sheet E Upper sidewall L Bottom of the top sidewall sheet G Eave angle tab M Sidewall hole (For the first hole or the last hole of the eave angle and inside stiffener). F Optional eave seal (CRP-4800)

After You Finish Continue this procedure for the remaining eave angles.

72 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly Connecting the Tension Member to the Eave Bracket Tension members connect to the eave brackets and are installed around the inside of the bin eave. Before You Begin Ensure all eave angles, inside stiffeners and eave brackets are installed before proceeding. What You Should Know IMPORTANT: Install bolts as shown, from the backside of the eave bracket. 1. Lift and support the tension member (D) against the outside mating surface of the eave bracket (B). 2. Install flange bolts (C) and flange nuts (A) to each end of the tension member (D). 3. Tighten to the recommended torque specifications. See Bolt Torque Specifications, page 24.

Figure 7-5 View of the tension plate mounting to the bin eave bracket

A 1/2 in. flange nut (S-10253) D Tension member (CTR-0132) B Eave bracket (CTR-0131) E Eave angle (CTR-0187) C 1/2 x 1-3/4 in. flange bolt (S-10252)

After You Finish Repeat this process for the remaining tension members.

Pneg-4075 75 Ft Diameter 40-Series Bin 73 Chapter 7: Roof Assembly Attaching the Center Collar Rafter Clips to the Rafter Center collar rafter clips secure the A-frame rafter sections to the center collar. What You Should Know Each roof rafter receives two center collar rafter clips, identified as the left center collar rafter clip (D) and the right center collar rafter clip (E). 1. Determine the correct orientation of each rafter (A) by identifying the roof panel holes (B) located near the end of each rafter. 2. Install the left center collar rafter clip (D) and right center collar rafter clip (E) to each side of the roof rafter (A). 3. Use flange bolts (F) and flange nuts (C) to secure the center collar rafter clips (D and E) to the rafter (A). Tighten to the recommended torque specification. See Bolt Torque Specifications, page 24. Figure 7-6 Exploded view of center collar rafter clips

A Roof rafter D Left center collar rafter clip (CTR-0003) B Roof panel hole E Right center collar rafter clip (CTR-0004) C 1/2 in. flange nut (S-10253) F 1/2 x 1-3/4 in. flange bolt (S-10252)

After You Finish Repeat this process for the remaining roof rafters.

74 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly About Temperature Cable Brackets and A-Frame Assemblies Temperature cable bracket installation locations must be considered prior to assembling the A-frames. Installation Locations for Temperature Cable Brackets Before assembling the A-frames, you must know the installation locations of the temperature cable brack- ets within the A-frame assemblies. Temperature cable brackets are installed at the same time as the pur- lins are installed. This information is provided solely for the purpose of facilitating proper support bracket placement. It is fully the responsibility of the dealer, customer, contractor, or said agent of such parties to confirm the details of the system to be used. GSI is not responsible for the effectiveness or performance of any tem- perature cable monitoring system or layout. IMPORTANT: Temperature cable brackets must be installed at the specified locations as shown below. Any variation from this pattern or cable quantity shown must be reviewed by GSI engineer- ing. This must be reviewed well in advance of the bin order. Lifting Sequence for the A-Frame Assemblies The layout of the roof structure consists of standard A-frame assemblies and A-frame assemblies with X- bracing that are installed in a specific sequence to evenly distribute the weight as they are being installed. The A-frames with X-bracing are strategically spaced around the diameter of the bin and are the first A- frames to be installed. The A-frame assemblies can be installed in the order as shown in the figure below. A-frames are installed across from each other to keep the weight distributed evenly during installation. Tip Label each A-frame assembly according to the order it is to be installed as it is assembled.

Pneg-4075 75 Ft Diameter 40-Series Bin 75 Chapter 7: Roof Assembly

Figure 7-7 A-frame installation sequence and temperature cable locations for 75 ft diameter bin

A 5 ft radius location (center collar) C 26.3 ft radius location B 11.6 ft radius location

76 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

Table 7-1 A-frame installation sequence and temperature cable locations for 75 ft diameter bin

A-frame number Rafter Number Temp Cable Number Radius Location R1 T3 11.6 ft A1 R2 T8 26.3 ft R16 — 11.6 ft A2 R17 T14 26.3 ft R11 — 11.6 ft A3 R12 T12 26.3 ft R5 — 11.6 ft A4 R6 T10 26.3 ft R20 — 26.3 ft A5 R21 T6 — R24 T7 26.3 ft A6 R25 — — R9 T11 — A7 R10 — — R22 — — A8 R23 — — R7 T4 — A9 R8 — — R18 — — A10 R19 T2 — R3 — 26.3 ft A11 R4 T9 — R13 T5 11.6 ft A12 R14 T13 26.3 ft R15 — — NA Attach to center collar T1 5 ft

NOTE: A-frames labeled “A1” through “A5” have X-bracing and are installed first. A-frames labeled “A6” through “A12” are standard A-frames. The empty spaces that are not labeled must have purlins installed between the rafters after all the A-frames are secured. The numbers reflect the recom- mended installation sequence of the A-frame assemblies. Table 7-2 Starting lengths for temperature cables for 75 ft diameter bins

Length from the center collar 216.1 in. (548.89 cm) Length from 11.6 ft diameter location 148.5 in. (377.19 cm) Length from 26.3 ft diameter location 56.6 in. (143.76 cm)

The temperature cable lengths in the chart above are the distances from where the temperature cable attaches to the rafter or the center collar to the top ring. To calculate the correct temperature cable length, add 32 inches for each bin ring to the starting length. Temperature cables must terminate above any unload equipment and be secured in place with twine. DO NOTallow cables to become tangled in unload equipment.

Pneg-4075 75 Ft Diameter 40-Series Bin 77 Chapter 7: Roof Assembly Assembling the Temperature Cable Bracket The temperature cable brackets are installed to the roof rafters and support the temperature cables. Before You Begin Determine the correct location of the temperature cable brackets within the structure of the A-frame Assembly. See About Temperature Cable Brackets and A-Frame Assemblies, page 75. What You Should Know The A-frame assembly consists of two roof rafters, purlin clips, purlins and possibly X-bracing. The temper- ature cable brackets should be installed when the A-frames are assembled. NOTE: The temperature cable bracket must be installed at specific locations, see About Temperature Cable Brackets and A-Frame Assemblies, page 75. 1. Attach a right purlin clip (C), a left purlin clip (D) and a temperature cable bracket (B) to the roof rafter (A), and install two flange bolts (E) and two flange nuts (F). NOTE: If no X-bracing is installed, install three flange bolts (E) and three flange nuts (F). 2. After all purlins and X-bracing are installed in the A-frame, tighten all hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24.

78 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

Figure 7-8 Installing a temperature cable bracket

A Roof rafter D Left purlin clip (CTR-0099) B 10 in. temperature cable bracket (CTR-0013) E 1/2 x 1-3/4 in. flange bolt (S-10252) C Right purlin clip (CTR-0100) F 1/2 in. flange nut (S-10253)

3. Install a quick link (C) to each cable bracket (B) to support the temperature cables. IMPORTANT: Do not attach weights to the temperature cables; secure the bottom of cables to the floor with light twine. No roof rafter shall support more than one cable.

Pneg-4075 75 Ft Diameter 40-Series Bin 79 Chapter 7: Roof Assembly

Figure 7-9 Supplier quick link

A Purlin C Supplier quick link B Temperature cable bracket (CTR-0013)

4. Locate the center collar temperature cable hole (D), and install a supplier quick link (C), allowing for the installation of a temperature cable at this location.

Figure 7-10 Supplier quick link on the center collar (view from bottom side of center collar)

C Supplier quick link D Center collar temperature cable hole

80 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly Attachment Locations of Purlins to Rafters Purlins are horizontal members between the rafters that give support to the roof structure. The length of the purlin determines its location on the A-frame assembly. The following reference depicts a completely assembled A-frame roof rafter section with X-bracing installed. For more information, see the following sections: Assembling Purlin Number 1, page 88, Assem- bling Purlin Number 2, page 86, Assembling Purlin Number 3, page 84, and Assembling Purlin Number 4, page 82.

Figure 7-11 Location of purlins for a 75 ft (22.86 m) diameter bin

A Location of purlin number 1 (CTR-0210) C Location of purlin number 3 (CTR-0212) B Location of purlin number 2 (CTR-0211) D Location of purlin number 4 (CTR-0213)

Pneg-4075 75 Ft Diameter 40-Series Bin 81 Chapter 7: Roof Assembly Assembling Purlin Number 4 Purlin number 4 is located at the top of the roof rafters nearest to the center collar rafter clips. Before You Begin Place two roof rafters on the ground with roof panel holes facing up. NOTE: Temperature cables may also be installed at this location, to determine if temperature cable brack- ets will be needed, see About Temperature Cable Brackets and A-Frame Assemblies, page 75. What You Should Know The A-frame roof rafter section consists of two roof rafters identified as the left-hand roof rafter (A) and the right-hand roof rafter (C). There are also two different purlin clips, a left purlin clip (E) and a right purlin clip (D). The left purlin clip has an extra hole located in the center as compared to the right, which only has six holes where the purlin and purlin clip are bolted together. NOTE: The seventh hole location in the center of the left purlin clip (E) is for identification purposes only. No hardware is used in this location. 1. Attach a left purlin clip (E) and a right purlin clip (D) to the right-hand roof rafter (C), and install three flange bolts (F) and three flange nuts (I). 2. Attach a left purlin clip (E) and a right purlin clip (D) to the left-hand roof rafter (A), and install three flange bolts (F) and three flange nuts (I). 3. Install the purlin (H) to the right purlin clip (D) and the left purlin clip (E) located between the left-hand roof rafter (A) and the right-hand roof rafter (C). NOTE: Ensure that the orientation of the purlin is correct, the roof panel holes are facing up, and the notch in the purlin is facing the right-hand roof rafter (C). 4. Install twelve flange bolts (B) and twelve flange nuts (G), securing the purlin to the purlin clips. 5. After all purlins are installed in the A-frame, tighten hardware to the recommended torque specifica- tions. See Bolt Torque Specifications, page 24.

82 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

Figure 7-12 Purlin location 4

A Left-hand roof rafter (CTR-0207) F 1/2 x 1-3/4 in. flange bolt (S-10252) B 1/2 x 1-3/4 in. flange bolt (S-10252) G 1/2 in. flange nut (S-10253) C Right-hand roof rafter (CTR-0207) H Purlin (CTR-0213) D Right purlin clip (CTR-0100) I 1/2 in. flange nut (S-10253) E Left purlin clip (CTR-0099)

Pneg-4075 75 Ft Diameter 40-Series Bin 83 Chapter 7: Roof Assembly Assembling Purlin Number 3 Purlin number 3 is located third from the bottom of the rafters. Before You Begin Place two roof rafters on the ground with roof panel holes facing up. Several A-frame assemblies will have X-bracing installed and be placed periodically throughout the perimeter of the roof. Determine if X-bracing is being installed and note those steps in this procedure. NOTE: Temperature cables may also be installed at this location, to determine if temperature cable brack- ets will be needed, see About Temperature Cable Brackets and A-Frame Assemblies, page 75. What You Should Know The A-frame assembly consists of two roof rafters identified as the left-hand roof rafter (A) and the right- hand roof rafter (C). The purlin configuration may not be the same on all A-frames at this location, (number 3), depending if X-bracing is being installed or not. There are also two different purlin clips, a left purlin clip (E) and a right purlin clip (D). The left purlin clip has seven holes, compared to the right, which has six holes along the purlin and purlin clip mating surface. NOTE: The seventh hole location in the center of the left purlin clip (E) is for identification purposes only. No hardware is used in this location. 1. Attach a right purlin clip (D) and a left purlin clip (E) to the right-hand roof rafter (C), and install two flange bolts (F) and two flange nuts (I) into the two top holes. NOTE: If no X-bracing is being installed, install three flange bolts (F) and three flange nuts (I) in this step. 2. Attach a right purlin clip (D) and a left purlin clip (E) to the left-hand roof rafter (A), and install two flange bolts (F) and two flange nuts (I) into the two bottom holes. NOTE: If no X-bracing is being installed, install three flange bolts (F) and three flange nuts (I) in this step. 3. Install the purlin (H) to the right purlin clip (D) and the left purlin clip (E) located between each roof rafter. Install twelve flange bolts (B) and twelve flange nuts (G), securing the purlin to the purlin clips. NOTE: If no X-bracing is being installed, proceed to step 8. 4. Attach the bottom X-brace (K) to the right-hand roof rafter (C), and install a flange bolt (F) and a flange nut (I) into the bottom hole. IMPORTANT: For adjustment purposes, DO NOT tighten the X-brace flange bolts until all X-braces have been installed. 5. Attach the top X-brace (J) to the left-hand roof rafter (A), and install a flange bolt (F) and one flange nut (I) into the top hole. 6. Secure the bottom portion of each X-brace (J and K) with a flange bolt (F) and one flange nut (I). 7. Install a flange bolt (L) and one flange nut (M) securing the X-braces together where they cross. 8. After all purlins are installed, tighten the hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24.

84 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

Figure 7-13 Purlin location 3

A Left-hand roof rafter (CTR-0207) H Purlin (CTR-0212) B 1/2 x 1-3/4 in. flange bolt (S-10252) I 1/2 in. flange nut (S-10253) C Right-hand roof rafter (CTR-0207) J Top X-brace (CTR-0223) D Right purlin clip (CTR-0100) K Bottom X-brace (CTR-0223) E Left purlin clip (CTR-0099) L 1/2 x 1-3/4 in. flange bolt (S-10252)

Pneg-4075 75 Ft Diameter 40-Series Bin 85 Chapter 7: Roof Assembly

F 1/2 x 1-3/4 in. flange bolt (S-10252) M 1/2 in. flange nut (S-10253) G 1/2 in. flange nut (S-10253)

Assembling Purlin Number 2 Purlin number 2 is located second from the bottom of the rafters. Before You Begin Place two roof rafters on the ground with roof panel holes facing up. Several A-frame assemblies will have X-bracing installed and be placed periodically throughout the perimeter of the roof. Determine if X-bracing is being installed and note those steps in this procedure. NOTE: Temperature cables may also be installed at this location, to determine if temperature cable brack- ets will be needed, see About Temperature Cable Brackets and A-Frame Assemblies, page 75. What You Should Know The A-frame assembly consists of two roof rafters identified as the left-hand roof rafter (A) and the right- hand roof rafter (C). The purlin configuration may not be the same on all A-frames at this location (number 2), depending if X-bracing is being installed or not. There are also two different purlin clips, a left purlin clip (E) and a right purlin clip (D). The left purlin clip has seven holes, compared to the right, which has six holes along the purlin and purlin clip mating surface. IMPORTANT: Do not drill additional holes in purlin. Install the flange bolts and nuts as dictated by the number of holes in the purlin. NOTE: The seventh hole location in the center of the left purlin clip (E) is for identification purposes only. No hardware is used in this location. 1. Attach a right purlin clip (D) and a left purlin clip (E) to the right-hand roof rafter (C), and install two flange bolts (F) and two flange nuts (I) into the two top holes. NOTE: If no X-bracing is being installed, install three flange bolts (F) and three flange nuts (I) in this step. 2. Attach a right purlin clip (D), left purlin clip (E), to the left-hand roof rafter (A), and install two flange bolts (F) and two flange nuts (I) into the two bottom holes. NOTE: If no X-bracing is being installed, install three flange bolts (F) and three flange nuts (I) in this step. 3. Install the purlin (H) to the right purlin clip (D) and the left purlin clip (E) located between each roof rafter. Install eight flange bolts (B) and eight flange nuts (G), securing the purlin to the purlin clips. NOTE: If no X-bracing is being installed, proceed to step 8. 4. Attach the bottom X-brace (K) to the right-hand roof rafter (C), and install a flange bolt (F) and flange nut (I) into the bottom hole. IMPORTANT: For adjustment purposes, DO NOT tighten the X-brace flange bolts until all X-braces have been installed.

86 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

5. Attach the top X-brace (J) to the left-hand roof rafter (A), and install a flange bolt (F) and a flange nut (I) into the top hole. 6. Secure the bottom portion of each X-brace (J and K) with a flange bolt (F) and a flange nut (I). 7. Install a flange bolt (L) and a flange nut (M) securing the X-braces (J and K) together. 8. After all purlins are installed, tighten the hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24. Figure 7-14 Purlin location 2

Pneg-4075 75 Ft Diameter 40-Series Bin 87 Chapter 7: Roof Assembly

A Left-hand roof rafter (CTR-0207) H Purlin (CTR-0211) B 1/2 x 1-3/4 in. flange bolt (S-10252) I 1/2 in. flange nut (S-10253) C Right-hand roof rafter (CTR-0207) J Top X-brace (CTR-0222) D Right purlin clip (CTR-0100) K Bottom X-brace (CTR-0222) E Left purlin clip (CTR-0099) L 1/2 x 1-3/4 in. flange bolt (S-10252) F 1/2 x 1-3/4 in. flange bolt (S-10252) M 1/2 in. flange nut (S-10253) G 1/2 in. flange nut (S-10253)

Assembling Purlin Number 1 Purlin number 1 is located closest to the bottom of the rafter. Before You Begin Place two roof rafters on the ground with roof panel holes facing up. Several A-frame assemblies will have X-bracing installed and be placed periodically throughout the perimeter of the roof. Determine if X-bracing is being installed and note those steps in this procedure. NOTE: Temperature cables may also be installed at this location, to determine if temperature cable brack- ets will be needed, see About Temperature Cable Brackets and A-Frame Assemblies, page 75. What You Should Know The A-frame assembly consists of two roof rafters identified as the left-hand roof rafter (A) and the right- hand roof rafter (C). The purlin configuration may not be the same on all A-frames at this location (number 1), depending if X-bracing is being installed or not. There are also two different purlin clips, a left purlin clip (E) and a right purlin clip (D). The left purlin clip has seven holes, compared to the right, which has six holes along the purlin and purlin clip mating surface. IMPORTANT: Do not drill additional holes in purlin. Install the flange bolts and nuts as dictated by the number of holes in the purlin. NOTE: The seventh hole location in the center of the left purlin clip (E) is for identification purposes only. No hardware is used in this location. 1. Attach a right purlin clip (D) and a left purlin clip (E) to the right-hand roof rafter (C), and install two flange bolts (F) and two flange nuts (I) into the two top holes. NOTE: If no X-bracing is being installed, install three flange bolts (F) and three flange nuts (I) in this step. 2. Attach a right purlin clip (D) and a left purlin clip (E) to the left-hand roof rafter (A), and two install flange bolts (F) and two flange nuts (I) into the two bottom holes. NOTE: If no X-bracing is being installed, install three flange bolts (F) and three flange nuts (I) in this step. 3. Install the purlin (H) to the right purlin clip (D) and the left purlin clip (E) located between each roof rafter. Install eight flange bolts (B) and eight flange nuts (G) securing the purlin to the purlin clips. NOTE: If no X-bracing is being installed, proceed to step 8.

88 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

4. Attach the bottom X-brace (K) to the right-hand roof rafter (C), and install a flange bolt (F) and a flange nut (I) into the bottom hole. IMPORTANT: For adjustment purposes, DO NOT tighten the X-brace flange bolts until all X-braces have been installed. 5. Attach the top X-brace (J) to the left-hand roof rafter (A), and install a flange bolt (F) and a flange nut (I) into the top hole. 6. Secure the bottom portion of each X-brace (J and K) with a flange bolt (F) and a flange nut (I). 7. Install a flange bolt (L) and a flange nut (M), securing the X-braces (J and K) together. 8. After all purlins are installed, tighten all hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24.

Pneg-4075 75 Ft Diameter 40-Series Bin 89 Chapter 7: Roof Assembly

Figure 7-15 Purlin location 1

A Left-hand roof rafter (CTR-0207) H Purlin (CTR-0210) B 1/2 x 1-3/4 in. flange bolt (S-10252) I 1/2 in. flange nut (S-10253) C Right-hand roof rafter (CTR-0207) J Top X-brace (CTR-0221) D Right purlin clip (CTR-0100) K Bottom X-brace (CTR-0221) E Left purlin clip (CTR-0099) L 1/2 x 1-3/4 in. flange bolt (S-10252)

90 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

F 1/2 x 1-3/4 in. flange bolt (S-10252) M 1/2 in. flange nut (S-10253) G 1/2 in. flange nut (S-10253)

Assembling a Double A-Frame To achieve the required spacing between each A-frame, a double A-frame will need to be assembled prior to installing and lift into place as one assembly. Before You Begin The double A-frame assembly will consist of three assembled roof rafters, purlin clips, and purlins. There are also two different purlin clips, a left purlin clip (B) and a right purlin clip (C). The left purlin clip has six holes, compared to the right, which has seven holes along the purlin clip mating surface. NOTE: The seventh hole located in the center of the right purlin clip (C) is for identification purposes only. No hardware is used in the location. What You Should Know

The completed assembly is extremely heavy, and all lifting should be performed by a certified crane operator with prior bin construction experience. Never lift during DANGER windy conditions.

When fully assembled the double A-frame becomes very heavy. 1. Place a roof rafter (A) parallel to an assembled A-frame (I). 2. Install left and right purlin clips (B and C) at locations shown, and secure the left and right purlin clips to the roof rafter (A) using flange bolts (D) and nuts (E).Tighten to the recommended torque, see Bolt Torque Specifications, page 24 specifications. 3. Install a purlin (H) at each location shown, and install flange bolts (F) and nuts (G). IMPORTANT: The center rafter in the double A-frame will need to be assembled on blocks raising it above the other rafters. This is necessary to adjust for the difference in rafter eleva- tions due to the conical shape of the roof.

Pneg-4075 75 Ft Diameter 40-Series Bin 91 Chapter 7: Roof Assembly

Figure 7-16 Double A-Frame rafter assembly with blocks

A Rafter D Block at the bottom (below the rafter) B Block at the top (below the roof rafter clip) E Roof rafter clip C Block at the middle (below the rafter)

92 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

Figure 7-17 Double A-frame assembly exploded view

A Roof rafter, (CTR-0207) F 1/2 x 1-3/4 in. flange bolt (S-10252) B Left purlin clip (CTR-0099) G 1/2 in. flange nut (S-10253) C Right purlin clip (CTR-0100) H Purlin

Pneg-4075 75 Ft Diameter 40-Series Bin 93 Chapter 7: Roof Assembly

D 1/2 x 1-3/4 in. flange bolt (S-10252) I Assembled A-frame E 1/2 in. flange nut (S-10253)

Weight of an Assembled Double A-frame

75 ft. Double A-frame Approximate Weight 1020 lb (463 kg) Assembling the Center Collar The center collar assembles each A-frame roof rafter section together at the top. Before You Begin Determine the correct orientation of the center collar in relation to any stairs or conveyor systems. Each half of the center collar (A) has drilled holes for the installation of the cap plate and side plates that will be installed later. For this procedure, each half of the center collar needs to sit securely on stands or suitable blocks, allowing plenty of room to access the bolts on the bottom side of the assembly. 1. Locate each half of the center collar (A), and install the center collar splice plate (D) to the inside por- tion on the center collar. 2. Install flange bolts (E) and flange nuts (B) to the six center holes (H) located on the center collar splice plate (D). NOTE: The remaining open holes along the outside edge of the center collar splice plate (D) will be used when installing the A-frame rafters to the center collar (A). 3. Install the second center collar splice plate (F) to the underside of the center collar (A), and install flange bolts (C) and flange nuts (G).

94 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

Figure 7-18 Center collar assembly

A Center collar (CTR-0217 and CTR-0233) E 1/2 x 1-3/4 in. flange bolt (S-10252) B 1/2 in. flange nut (S-10253) F Center collar splice plate (CTR-0023) C 1/2 x 1-3/4 in. flange bolt (S-10252) G 1/2 in. flange nut (S-10253) D Center collar splice plate (CTR-0208) H Inner holes

4. When assembling the opposite side of the center collar, install another center collar splice plate (D) to the inside portion on the center collar (A). 5. Install flange bolts (E) and flange nuts (B) to the six outer holes (I) of the center collar splice plate (D). NOTE: The configuration will be different on each side due to the odd number of roof rafters. The remaining open holes in the center collar splice plate (D) will be used when installing the A- frame rafters to the center collar (A). 6. Install another center collar splice plate (F) to the underside of the center collar (A), and install flange bolts (C) and flange nuts (G).

Pneg-4075 75 Ft Diameter 40-Series Bin 95 Chapter 7: Roof Assembly

Figure 7-19 Center collar assembly

A Center collar (CTR-0217 and CTR-0233) E 1/2 x 1-3/4 in. flange bolt (S-10252) B 1/2 in. flange nut (S-10253) F Center collar splice plate (CTR-0023) C 1/2 x 1-3/4 in. flange bolt (S-10252) G 1/2 in. flange nut (S-10253) D Center collar splice plate (CTR-0208) I Outer holes

7. Locate the column of three holes (K) that are not paired together on the inside radius of the center collar, and install a center collar channel clip (M). 8. Secure with flange bolts (L) and flange nuts (J). 9. Repeat this procedure for the remaining three center collar channel clips (M).

96 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

Figure 7-20 Installing center collar channel clips

J 1/2 in. flange nut (S-10253) M Center collar channel clip (CTR-0209) K Row of three holes N Center collar channel clip (CTR-0083) L 1/2 x 1-3/4 in. flange bolt (S-10252)

10.Tighten all of the hardware to the recommended torque specifications, see Bolt Torque Specifica- tions, page 24. Center Collar Placement The following figure gives the approximate height needed to install the center collar. With two sidewall rings in place, position the center collar at the height specified, measuring from the bottom of the center collar to the foundation as shown. If additional rings are required for construction pur- poses, add 32 in. for each additional ring. NOTE: It is better to set the center collar a little too high. Do not set the center collar too low.

Pneg-4075 75 Ft Diameter 40-Series Bin 97 Chapter 7: Roof Assembly

Figure 7-21 Center collar placement

A 280.984 (713.70 cm) in. from foundation to bottom of center collar on 75 ft diameter bin

98 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly Guidelines for Assembling and Lifting the A-Frame Rafter Sections The roof is assembled in sections and referred to as A-frame rafter sections. Each A-frame rafter section is assembled on the ground and lifted into place. IMPORTANT: Do not drill additional holes in purlins. Install the flange bolts and nuts as dictated by the number of holes in the purlin. NOTE: Use purlin clips as lifting points, as shown. Figure 7-22 Recommended lifting points for A-frame sections

A Purlin clip

Pneg-4075 75 Ft Diameter 40-Series Bin 99 Chapter 7: Roof Assembly

Figure 7-23 Recommended lifting points for a Double A-frame section

A Purlin clip

The A-frame rafter section has two configurations: with X-bracing and without. The number of A-frame rafter sections with X-bracing depends on which size bin is being constructed.

All lifting should be performed by a certified crane operator with prior bin construction experience. Never lift during windy conditions. DANGER

General Guidelines: • Construct the A-frame sections on flat ground or blocking. • Install the temperature cable brackets at the same time you assemble the A-frame sections. • Always be aware of the orientation of each part prior to assembling. • Use the correct hardware for the part being assembled. Never substitute hardware. • Always ensure hardware is tightened prior to lifting. • Always practice safety when assembling rafter sections. Be aware of others around you when moving long A-frame sections. • Use evenly distributed connection points of support when lifting.

100 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

• Before attempting a lift, adjust each lifting cable to achieve the appropriate angle needed (approxi- mately 30 degrees). • Assemble the A-frames with X-bracing last, so that they can be easily accessed to be lifted into place first. Table 7-3 For standard roof Bin Diameter Peak Capacity Ground Snow Load Approximate A-Frame Weight 75 ft. (22.86 m) 30 K 40 PSF 711 lb (322 kg) 75 ft. (22.86 m) 30 K 40 PSF 1020 lb (463 kg) (three rafter assembly) The part variance multiplier is 4%.

Attaching the A-Frames to the Center Collar The A-frame rafters must be installed to support the center collar and main roof structure. Before You Begin The center collar should be assembled and secured to the support pole, and the A-frame rafters should be assembled. Determine the correct location of each A-frame. For more information, see Center Collar Placement , page 97. Read and understand the safe and proper lifting procedures needed to install the A- frames. For more information, see Guidelines for Assembling and Lifting the A-Frame Rafter Sections, page 99. 1. Carefully lift the A-frame assembly (A) into position, and align with the proper holes on the center collar (B). 2. Install flange bolts (C) and flange nuts (D) as shown. 3. Before continuing with the remaining A-frame rafters, secure the A-frame rafter to the eave clip. See Attaching the A-Frame to the Eave Bracket , page 102.

Pneg-4075 75 Ft Diameter 40-Series Bin 101 Chapter 7: Roof Assembly

Figure 7-24 Exploded view of A-frame to center collar

A A-frame rafter assembly C 1/2 x 1-3/4 in. flange bolt (S-10252) B Center collar (CTR-0217 and CTR-0233) D 1/2 in. flange nut (S-10253)

Attaching the A-Frame to the Eave Bracket Assemble the lower portion of the A-frame rafters to the sidewalls. 1. Lower the A-frame rafter assembly (A) along the side of the eave bracket (C), and align with the proper holes. NOTE: Use the alignment hole (E) in the rafter to help align the holes with a punch tool. 2. Install flange bolts (B) and flange nuts (D), securing one side on the A-frame assembly. 3. Repeat this procedure for the other side of the A-frame. 4. Tighten to the recommended torque specifications. See Bolt Torque Specifications, page 24.

102 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

Figure 7-25 Attaching the rafter to the eave bracket

A A-frame rafter assembly D 1/2 in. flange nut (S-10253) B 1/2 x 1-3/4 in. flange bolt (S-10252) E Hole for alignment tool C Eave bracket (CTR-0429)

After You Finish Continue to the next A-frame installation until all of the A-frame rafter assemblies are installed. See About Temperature Cable Brackets and A-Frame Assemblies, page 75.

Assembling the Roof Panel Clips The roof panel clips are located at the top of the roof rafters nearest to the center collar rafter clips. Before You Begin The A-frame rafters should be fully assembled and installed to the center collar and the eave brackets. What You Should Know The A-frame assembly consists of two roof rafters identified as the left-hand roof rafter (A) and the right- hand roof rafter (C). The roof panel clip is installed between each rafter after the A-frame assemblies are installed. 1. Attach the two roof panel clips (B) to the left-hand roof rafter (A), and install two flange bolts (D) and two flange nuts (E) securing the roof panel clips to the left-hand roof rafter. 2. Attach the third roof panel clip (B) to the right-hand roof rafter (A), and install two flange bolts (D) and two flange nuts (E) securing the roof panel clips to the right-hand roof rafter.

Pneg-4075 75 Ft Diameter 40-Series Bin 103 Chapter 7: Roof Assembly

NOTE: Ensure that the orientation of the roof panel clip is correct, roof panel holes facing the roof and the notch in the roof panel clip is facing the right-hand roof rafter. 3. Tighten all hardware to the recommended torque specifications only after the roof panels are installed. See Bolt Torque Specifications, page 24. Figure 7-26 Roof panel clip

A Left-hand roof rafter (CTR-0207) D 1/2 x 1-3/4 in. flange bolt (S-10252) B Roof panel clip (CTR-0214) E 1/2 in. flange nut (S-10253) C Right-hand roof rafter (CTR-0207)

After You Finish Repeat this procedure for the remaining roof panel clips.

104 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

Pneg-4075 75 Ft Diameter 40-Series Bin 105 Chapter 7: Roof Assembly Installing the 6–Hole Intermediate Purlins Intermediate purlins must be installed to connect each A-frame roof rafter assembly together. The inter- mediate purlins at 11.6 ft radius (near the center collar) and 19.4 ft radius (second from the center collar) connecting each A-frame roof rafter assembly are unique than the other intermediate purlins installed at other diameters of the roof. Before You Begin All A-frame roof rafter assemblies must be installed and secured to both the center collar and the eave brackets. 1. Install the intermediate purlin (A) to the purlin clips (B and D) located outside of each A-frame roof rafter assembly (E). 2. Install six flange bolts (C) and six flange nuts (F) to each end of the purlin (A) securing the intermedi- ate purlin to the purlin clips. 3. Tighten the hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24. Figure 7-27 Exploded view of the 6–hole intermediate purlin

A Purlin (CTR-0213) D Left Purlin clip (CTR-0099) B Right Purlin clip (CTR-0100) E A-frame roof assembly C 1/2 x 1-3/4 in. flange bolt (S-10252) F 1/2 in. flange nut (S-10253)

After You Finish Repeat this procedure only for the remaining 6–hole intermediate purlins (near the center collar) at 11.6 ft radius and 19.4 ft radius of the roof assembly.

106 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly Installing the 4–Hole Intermediate Purlins Intermediate purlins must be installed to connect each A-frame roof rafter assembly together. 4-hole inter- mediate purlins have only four holes on each side to secure them with the purlin clips. Before You Begin All A-frame roof rafter assemblies must be installed and secured to both the center collar and the eave brackets. 1. Install the intermediate purlin (A) to the purlin clips (B and D) located outside of each A-frame roof rafter assembly (E). IMPORTANT: Do not drill additional holes in purlins. Install the flange bolts and nuts as dictated by the number of holes in the purlin. 2. Install four flange bolts (C) and four flange nuts (F) to each end of the purlin (A) securing the inter- mediate purlin to the purlin clips. 3. Tighten the hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24. Figure 7-28 Exploded view of the 4-hole intermediate purlin

A Purlin (CTR-0210 and CTR-0211) D Purlin clip B Purlin clip E A-frame roof assembly C 1/2 x 1-3/4 in. flange bolt (S-10252) F 1/2 in. flange nut (S-10253)

Pneg-4075 75 Ft Diameter 40-Series Bin 107 Chapter 7: Roof Assembly

After You Finish Repeat this procedure only for the remaining 4-hole intermediate purlins.

Attaching the Roof Panels Roof panels overlap the previous roof panel, giving protection from outside elements. Before You Begin Ensure all A-frame roof rafter assemblies are installed, and ensure all intermediate purlins are installed and properly tightened. Predetermine the manway access location. What You Should Know For adjustment purposes, roof panels will be installed to each rafter first, causing exposed gaps between each roof panel group (see figure below). After all roof panels are installed, ensure that all installed hard- ware (flange bolts with sealing washers and flange nuts) are tightened to secure the roof panels. Figure 7-29 Roof panel overview

A Lower roof panel (CTR-0265) C Upper roof panel (CTR-0264) B Exposed gap

108 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

1. With assistance, position a lower roof panel (A) onto the first rafter in any A-frame. 2. Install five flange bolts (D) and five flange nuts (E) into the lower portion of the lower roof panel secur- ing the lower roof panel to the eave angle. 3. With assistance, position another lower roof panel (A) onto the next rafter in the A-frame. NOTE: There should be an exposed gap between the two lower roof panels in the A-frame. 4. Install five flange bolts (D) and five flange nuts (D) into the lower portion of the lower roof panel secur- ing the lower roof panel to the eave angle.

Figure 7-30 Installing the lower roof panels

A Lower roof panel (CTR-0265) E 5/16 in. flange nut (S-3611) D 5/16-18 x 1 flange bolt with sealing washer (S-10260)

5. After installing the two lower roof panels onto the A-frame rafters, with assistance, position an upper roof panel (C) onto a A-frame rafter (F). 6. Install a flange bolt (D) and a flange nut (E) to secure the upper roof panel (C) to the rafter (F). 7. With assistance, position another upper roof panel (C) onto the next rafter in the A-frame.

Pneg-4075 75 Ft Diameter 40-Series Bin 109 Chapter 7: Roof Assembly

NOTE: There should be an exposed gap between the two upper panels in the A-frame. 8. Install a flange bolt (D) and a flange nut (E) to secure the upper roof panel to the rafter.

Figure 7-31 Installing the upper roof panels

B Exposed gap E 5/16 in. flange nut (S-3611) C Upper roof panel (CTR-0264) F A-frame roof rafter D 5/16-18 x 1 flange bolt with sealing washer (S-10260)

9. When the initial two lower panels and two upper panels are installed, fill in the exposed gaps, by installing three additional lower roof panels (A) (as shown) overlapping each lower roof panel on the right, adjusting the lower roof panels as needed. 10.Install flange bolts (D) and flange nuts (E) securing the overlapping lower panels.

110 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

NOTE: To ensure each lower roof panel is overlapping the existing roof panel previously installed, slightly lift the side rib of the previous lower roof panel, allowing the new lower roof panel to be tucked under the previous roof panel. Figure 7-32 Installing the roof panels into exposed gaps

A Lower roof panel (CTR-0265) D 5/16-18 x 1 flange bolt with sealing washer (S- 10260) B Exposed gap E 5/16 in. flange nut (S-3611)

11.When the lower panels are installed, fill in the exposed gaps between the upper panels, by installing three additional upper roof panels (C) overlapping each upper roof panel on the right, adjusting the upper roof panels as needed. 12.Install the flange bolts (D) and the flange nuts (E) along the ribs of each upper panel to secure them. 13.Install the flange bolts (D) and the flange nuts (E) to secure the lower roof panels and the upper roof panels.

Pneg-4075 75 Ft Diameter 40-Series Bin 111 Chapter 7: Roof Assembly

Figure 7-33 Securing the overlapping upper and lower panels

A Lower roof panel (CTR-0265) D 5/16-18 x 1 flange bolt with sealing washer (S- 10260) C Upper roof panel (CTR-0264) E 5/16 in. flange nut (S-3611)

14.Working in a clockwise direction, repeat the procedure to continue installing all the lower roof panels and the upper roof panels onto the A-frames. 15.Field drill holes (B) into the roof panels (A) through holes in the top flange of the purlins (D). Fasten the panels and the purlins securely using 5/16 in. bolts.

112 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

NOTE: Ensure that holes are drilled from inside of the bin. 16.Field drill holes (C) into the roof panels (A) through holes in the top flange of the rafters (E). Fasten the panels and the rafters securely using 5/16 in. bolts. NOTE: Ensure that holes are drilled from inside of the bin. IMPORTANT: Failure to properly secure the roof panel to the purlin and the rafter will constitute a modification to the product not specifically delineated in this manual and will void the limited warranty.

A Roof panel (CTR-0264 and CTR-0265) D Purlin B Roof panel holes (drilled through purlin) E Rafter C Roof panel holes (drilled through rafter)

Pneg-4075 75 Ft Diameter 40-Series Bin 113 Chapter 7: Roof Assembly Installing the Roof Flashing The roof flashing will seal the area between the center collar and the roof panels. What You Should Know Each roof flashing section overlaps and bolts together with the previously installed roof flashing section. 1. Install the first roof flashing section (A) onto the roof panel, and align the holes on the roof flashing with the roof panel. 2. Install flange bolts (B) and flange nuts (C), securing the first roof flashing section (A) to the roof panel ribs. NOTE: Only the first roof flashing section is installed using only six of the required flange bolts and nuts. Any remaining unfilled holes will be filled when the last roof flashing section is installed. Figure 7-34 Installation of the first roof flashing section

A Roof flashing (CTR-0266) C 5/16 in. flange nut (S-3611) B 5/16-18 x 1 flange bolt with sealing washer (S-10260)

114 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

3. Place a strip of rope caulk (D) along the edge of the installed roof flashing (A) where the next roof flashing will overlap. 4. Align the holes along the edge of the next roof flashing (A) with the previously installed roof flashing holes. 5. Install flange bolts (B) and flange nuts (C), securing the two roof flashing sections (A) together. 6. Install flange bolts (B) and flange nuts (C), securing the roof flashing section (A) to the roof panel ribs. 7. Continue installing the remaining flashing until the gap between the center collar and roof panels is covered. NOTE: Remember to place caulk between the overlap of the last two panels. Figure 7-35 Installation of remaining roof flashing sections

A Roof flashing (CTR-0266) C 5/16 in. flange nut (S-3611) B 5/16-18 x 1 flange bolt with sealing washer D Rope caulk (S-10260)

Pneg-4075 75 Ft Diameter 40-Series Bin 115 Chapter 7: Roof Assembly

After You Finish NOTE: If roof exhausters will be installed, see roof accessories, Preparation for Roof Exhauster Installation. Assemble and Install Center Collar Channels and Cap Plates The following procedure is for assembling the center collar channels and cap plates on the ground, and lift- ing the entire assembly as one . 1. Locate a short center collar channel (F), and install a short channel clip (D) to the outer edge of the short center collar channel (F). 2. Install flange bolts (C) and flange nuts (E), and repeat this procedure for the opposite end of this short center collar channel (F). 3. Install one 3/8 in. bolt (B) and nut (A) into the center hole of the short center collar channel (F) to aid with water shedding, NOTE: Installing the 3/8 in. bolt (B) and nut (A) will create a slight pitch when the center cap plate is installed, allowing water to shed from this area. 4. Locate the second short center collar channel (F), and repeat this procedure. 5. Place both assembled short collar channels (F) aside to use later in this procedure.

Figure 7-36 Assembling the short center collar channels

A 3/8 in. nut (S-456) D Short channel clip (CTR-0082) B 3/8 x 1 in. bolt (S-455) E 1/2 in. flange nut (S-10253) C 1/2 x 1-3/4 in. flange bolt (S-10252) F Short center collar channel (CTR-0081)

116 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

6. Locate two long center collar channels (I), and place on stands or suitable blocks. NOTE: Make note of the orientation of each center collar channel prior to assembling. Ensure all cap plate holes are facing in the same direction. 7. Locate the two short center collar channels (F) that were previously assembled, and place between the two long center collar channel (I). 8. Install the short center collar channels (F) to the third set of holes located on each long center collar channel (I). 9. Install flange bolts (G) and flange nuts (H), securing the short center collar channel (F) to the long center collar channel (I). 10.Repeat this procedure for the second short center collar channel (F). 11.Tighten all of the hardware to the recommended torque specifications. See Bolt Torque Specifica- tions, page 24.

Pneg-4075 75 Ft Diameter 40-Series Bin 117 Chapter 7: Roof Assembly

Figure 7-37 Assembling the long center collar channels

F Short center collar channel (CTR-0081) H 1/2 in. flange nut (S-10253) G 1/2 x 1-3/4 in. flange bolt (S-10252) I Long center collar channel (CTR-0080)

12.Place the center cap plate (Q) onto the center collar channel assembly, ensuring the center cap plate is parallel to the long center collar channel (I). 13.Apply a strip of tube caulk (K) along the inside edge row of holes as shown. 14.Install a splice plate (J) over the fresh strip of caulk (K). 15.Align the holes in the splice plate (J) and center cap plate (Q) with the holes in the long center collar channel (I), and loosely install five bolts (M) and nuts (P) into the inner row of holes, working outward from the center of the splice plate. NOTE: Splice plate must remain loose, allowing for side cap plate to be tucked into place. 16.Locate the side cap plate (L), and apply a strip of tube caulk (K) along the row of holes as shown. 17.Lift the splice plate (J) and tuck the side cap plate (L) under the splice plate (J).

118 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

18.Align the holes in the splice plate (J) and side cap plate (L) with the holes in the long center collar channel (I), and install six bolts (N) and nuts (P) into the outer row of holes, working outward from the center of the splice plate. 19.Repeat this procedure for the other side of the center cap plate (Q). 20.Locate the third hole from each end of the spice plates (J), and install four vendor lifting eyebolts (O), NOTsupplied by GSI, and nuts (P). NOTE: Eyebolt will pass through three layers of steel: the splice plate (J), the center cap plate (Q), and the long center collar channel (I). 21.Tighten all hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24.

Pneg-4075 75 Ft Diameter 40-Series Bin 119 Chapter 7: Roof Assembly

Figure 7-38 Installing the cap plates

I Long center collar channel (CTR-0080) N 3/8 x 1 in. bolt with sealing washer (S-7487) J Splice plate (CTR-0020) O Vendor lifting eyebolt K Tube caulk P 3/8 in. nut (S-456) L Side cap plate (CTR-0019), approximately Q Center cap plate (CTR-0017), approximately 304 158 lb (71.6.4 kg) lb (137.89 kg) M 3/8 x 1 in. bolt with sealing washer (S- 7487)

22.Place a continuous bead of tube caulk (V) on the mating surface of the roof flashing. NOTE: Before continuing, read and understand the safe and proper lifting procedures needed to install the A-frames. For more information, see Guidelines for Assembling and Lifting the A- Frame Rafter Sections, page 99. 23.Attach the appropriate lifting chains (R) to the previously installed lifting eyebolts. 24.Attach the appropriate lifting chains (R) to the appropriate lilting device (S). 25.Use the appropriate lifting device (S) and qualified personnel to hoist the cap plate assembly (W) into place.

120 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly

26.Ensure all holes are aligned, and install flange bolts (U) and flange nuts (T) into each collar channel clip. 27.Disconnect the lifting device (S) and remove lifting chains (R) from the cap plate assembly (W). 28.Tighten all hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24.

Figure 7-39 Lifting the center collar channel and cap plates

R Appropriate lifting chains U 1/2 x 1-3/4 in. flange bolt (S-10252) S Appropriate lifting device V Tube caulk T 1/2 in. nut (S-10253) W Cap plate assembly, approximately 912 lb (413.67 kg)

29.Secure the cap plate assembly to the center collar using bolts with sealing washers (X) and nuts (Y), leaving the peak conveyer support bracket holes (Z) unfilled. 30.Replace the four vendor eyebolts with the supplied bolts with sealing washers (X) and nuts (Y). 31.Tighten all hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24.

Pneg-4075 75 Ft Diameter 40-Series Bin 121 Chapter 7: Roof Assembly

Figure 7-40 Cap plate assembly installed

X 3/8 x 1 in. bolt with sealing washer (S- Z Holes for conveyor support brackets 7487) Y 3/8 in. nut (S-456)

122 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 7: Roof Assembly Installing the Conveyor Support Brackets to the Peak Cap Conveyor support brackets are attached to the peak cap and allow support for a conveyor or catwalk system. 1. Place tube caulk around the bolt holes located in the cap plate where the conveyor support brackets (B) will be installed. 2. Position a conveyor support brackets (B) against the cap plate and align the holes. 3. Install flange bolts (A) and secure with flange nuts (C). 4. Tighten to the recommended torque specification. See Bolt Torque Specifications, page 24. Figure 7-41 Conveyor support brackets

A 3/8 x 1-1/2 in. flange bolt, (S-7488) C 3/8 in. flange nut (S-456) B Conveyor support bracket (CTR-0087) D Caulk

After You Finish Repeat this procedure for the remaining conveyor support brackets.

Pneg-4075 75 Ft Diameter 40-Series Bin 123 NOTES

124 Pneg-4075 75 Ft Diameter 40-Series Bin 8 Accessories

Topics Covered in this Chapter ▪ Installing Roof Ladder Steps ▪ Roof Ring Placement ▪ Installing a Roof Ring ▪ Installation of Peak–To– Exhauster Ladder Kit ▪ Preparation for Roof Exhauster Installation ▪ Assembling the Roof Exhauster ▪ Installing Roof Exhauster Assembly ▪ Assembling the Auto Roof Vent ▪ Assembling Wire Grill Guard Roof Vent ▪ Installing the Wire Grill Guard and Auto Roof Vents ▪ Installing the Manway Cover ▪ Ladder Section Assembly ▪ Inside Ladder Placement ▪ Installing Inside Ladder Bottom Bracket ▪ Guidelines for Installing a Sidedraw System ▪ Installing the Sidedraw Baffle Chute (Two Post Stiffener) ▪ Installing the Sidedraw Baffle Chute (Three Post Stiffener) ▪ Installing the Sidedraw Discharge Chute ▪ Wind Ring Requirements ▪ Installing Wind Rings ▪ Assembling Weather Cover for Roller Valve

Pneg-4075 75 Ft Diameter 40-Series Bin 125 Chapter 8: Accessories Installing Roof Ladder Steps Roof ladder steps will allow access to roof and manway access. What You Should Know Each eave-to-peak ladder step package (E) differs with the diameter of each bin. When installing the ladder steps, always start from the eave and work up toward the peak, installing the longest step first and the shortest step last. NOTE: Use the table at the end of this procedure for part listings and the correct placement of each ladder step configuration for various bin sizes. See Table 8-1, page 127. 1. Place the first roof ladder step (B) onto the corresponding roof panel, next to the manway access (G). NOTE: If roof rings will be installed, roof ladder steps (B and F) will not be installed. Proceed to next available ladder step. 2. Install flange bolts (A) and install sealing washers (D) between the ladder step (B) and the roof panel rib. Secure the roof ladder step to the roof panel with two flange nuts (C). Tighten to the recom- mended torque specifications. See Bolt Torque Specifications, page 24. 3. Repeat this procedure for the remaining ladder steps in the eave-to-peak ladder step package (E).

Figure 8-1 Exploded view of a roof ladder step

A 5/16 x 1 in. flange bolt (S-10260) E Eave-to-peak ladder step package (PLS-42496-XX)1 B Roof ladder step (LS-260-X)2 F Roof ladder step (LS-260-X )2 C 5/16 in. flange nut (S-3611) G Manway access D Sealing washer (S-3558)

1. (-XX) denotes the bin diameter. 2. (-X) denotes the ladder step number.

126 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Use the following table as a guide to the location of each ladder step (rung). Table 8-1 Ladder Rung Placement Chart

Bin Diameter Location 72 ft. 75 ft. 78 ft. 90 ft. 105 ft. 135 ft. Bin Peak 37 LS-260-1 36 LS-260-1 35 LS-260-1 34 LS-260-2 33 LS-260-2 32 LS-260-2 31 LS-260-3 30 LS-260-3 29 LS-260-1 LS-260-4 28 LS-260-1 LS-260-4 27 LS-260-1 LS-260-4 26 LS-260-2 LS-260-5 25 LS-260-1 LS-260-2 LS-260-5 24 LS-260-1 LS-260-3 LS-260-5 23 LS-260-2 LS-260-3 LS-260-6 22 LS-260-2 LS-260-4 LS-260-6 21 LS-260-1 LS-260-3 LS-260-4 LS-260-6 Roof Rib Hole 20 LS-260-1 LS-260-2 LS-260-4 LS-260-5 LS-260-7 Number 19 LS-260-1 LS-260-2 LS-260-3 LS-260-4 LS-260-5 LS-260-7 From Bin 18 LS-260-2 LS-260-3 LS-260-3 LS-260-5 LS-260-6 LS-260-8 Eave 17 LS-260-3 LS-260-3 LS-260-4 LS-260-5 LS-260-6 LS-260-8 16 LS-260-3 LS-260-4 LS-260-5 LS-260-6 LS-260-7 LS-260-8 15 LS-260-4 LS-260-5 LS-260-5 LS-260-6 LS-260-7 LS-260-9 14 LS-260-5 LS-260-5 LS-260-6 LS-260-7 LS-260-8 LS-260-9 13 LS-260-6 LS-260-6 LS-260-6 LS-260-7 LS-260-8 LS-260-9 12 LS-260-6 LS-260-7 LS-260-7 LS-260-8 LS-260-9 LS-260-10 11 LS-260-7 LS-260-7 LS-260-7 LS-260-8 LS-260-9 LS-260-10 10 LS-260-8 LS-260-8 LS-260-8 LS-260-9 LS-260-10 LS-260-11 9 LS-260-8 LS-260-9 LS-260-9 LS-260-9 LS-260-10 LS-260-11 8 LS-260-9 LS-260-9 LS-260-9 LS-260-10 LS-260-11 LS-260-11 7 LS-260-10 LS-260-10 LS-260-10 LS-260-11 LS-260-11 LS-260-12 6 LS-260-10 LS-260-11 LS-260-11 LS-260-11 LS-260-12 LS-260-12 5 LS-260-11 LS-260-11 LS-260-12 LS-260-12 LS-260-12 LS-260-13 4 LS-260-12 LS-260-12 LS-260-12 LS-260-12 LS-260-13 LS-260-13 3 LS-260-13 LS-260-13 LS-260-13 LS-260-13 LS-260-13 LS-260-13 2 LS-260-13 LS-260-13 LS-260-13 LS-260-13 LS-260-14 LS-260-14 Bin Eave 1 LS-260-14 LS-260-14 LS-260-14 LS-260-14 LS-260-14 LS-260-14

Pneg-4075 75 Ft Diameter 40-Series Bin 127 Chapter 8: Accessories

NOTE: The table above shows the correct ladder step and part number to be installed in the corresponding hole in the roof rib. Shaded areas also show the correct roof exhauster ladder step and part number with the corresponding hole in the roof rib. Roof Ring Placement The roof ring is a tubular ring bolted to the exterior of the roof. The placement location and quantity of roof ring kits vary with the size of each bin. The exhauster roof ring (A) on the 75 ft bin will be installed in the seventh roof panel rib hole from the top. The eave roof ring (B) will be installed in the last roof panel rib hole located at the eave end of the bin. NOTE: If ladder steps have been installed, and not already omitted, remove the ladder step that is installed in the same roof panel rib hole in which the roof ring will be installed. Figure 8-2 Roof ring location on bin

A Exhauster roof ring kit (CRP-7228-XX)3 B Eave roof ring kit (CRP-5496-XX) 4

3. (-XX) denotes the bin diameter. 4. (-XX) denotes the bin diameter.

128 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories Installing a Roof Ring Quantity and part numbers of roof ring kits vary with the location placement and with the size of each bin. The following procedure will be similar for each kit. What You Should Know The roof ring and threaded stud may become dislocated from each other during high winds or when the inside pressure of the bin is too great. If a threaded stud is dislocated, the entire roof ring will become dis- jointed. To prevent this, drill holes through the roof ring and the threaded stud (after the rings have been installed and expanded to the correct size) and insert a cotter pin or bolt through each hole. See Figure 8- 4, page 130. 1. Determine the quantity of roof ring clips (C) needed for the roof ring section (B) being installed. NOTE: Each roof panel rib must have a roof ring clip installed. 2. Install a flange bolt (A) to the roof ring clip (C), and install a sealing washer (E) to the underside of the roof ring clip (C). 3. Slide each assembled roof ring clip (C) onto a roof ring section (B), and position each roof ring clip (C) over each roof panel rib. 4. Install a flange nut (D) to each roof ring clip (C). NOTE: Do not tighten hardware until all roof ring sections have been installed. Figure 8-3 Exhauster roof ring shown

A 5/16 x 1 in. flange bolt (S-10260) D 5/16 in. flange nut (S-3611) B Exhauster roof ring section (CRP- E Sealing washer (S-3558) 7229-XX)5 C Roof ring clip (R-997)

5. Locate a threaded stud (F) and install stud nuts (G) evenly and to the center of the threaded stud (F).

5. (-XX) denotes the bin diameter.

Pneg-4075 75 Ft Diameter 40-Series Bin 129 Chapter 8: Accessories

6. Install the threaded stud (F) with stud nuts (G) to the end of the roof ring section (B). NOTE: Install the threaded stud (F) to the side where the next roof ring section will be installed. 7. Repeat this process, installing each new roof ring section end onto the preceding threaded stud just installed. 8. When all roof ring sections are installed, tighten each roof ring clip (B) to the recommended torque specifications. See Bolt Torque Specifications, page 24. 9. Adjust each stud nut (G) outward, expanding each roof ring section. Continue this procedure evenly until the roof ring raises the roof, showing a slight .

Figure 8-4 Exploded view of threaded stud

B Exhauster roof ring section (CRP- G Stud nut (S-8926) 7229-XX)6 F Threaded stud (S-8765) H Cotter pin (not supplied)

6. (-XX) denotes the bin diameter.

130 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories Installation of Peak–To– Exhauster Ladder Kit Before installing the roof exhauster, the peak-to-exhauster ladder kit may be installed onto the roof to have access to the roof exhauster. Before You Begin Determine the location of the roof exhauster. What You Should Know This procedure is to install the peak to exhauster ladder kit onto the roof . When the correct location of the roof exhauster has been determined, the peak-to-exhauster ladder kit (A) will be installed next to the roof exhauster on the next available roof rib. IMPORTANT: The peak-to-exhauster ladder kit is an option and it does not come with the standard roof exhauster. 1. Place the appropriate peak-to-exhauster ladder step (B) against the corresponding roof rib hole, using the table listed at the end of this section. NOTE: The contents of each peak-to-exhauster ladder kit (A) differ with bin diameters. 2. Install flange bolts (C) and sealing washers (D) between the peak-to-exhauster ladder step (B), and the roof panel rib. Secure the peak-to-exhauster ladder step to the roof panel with flange nuts (E).

Figure 8-5 Exploded view of peak-to-exhauster ladder kit

A Peak-to-exhauster ladder kit (PLS-42497-XX)7 D Sealing washer (S-3558) B Peak-to-exhauster ladder step (LS-260–X)8 E 5/16 in. flange nut (S-3611) C 5/16 x 1 in. flange bolt (S-10260)

7. (-XX) denotes the bin diameter. 8. (-X) denotes the peak-to-exhauster ladder step number.

Pneg-4075 75 Ft Diameter 40-Series Bin 131 Chapter 8: Accessories

Table 8-2 Peak-to-Exhauster Ladder Rung Kit

Bin Diameter Location 72 ft 75 ft 78 ft 90 ft 105 ft 135 ft ↑ 37 LS-260-1 Bin Peak 36 LS-260-1 35 LS-260-1 34 LS-260-2 33 LS-260-2 32 31 30 29 LS-260-1 28 LS-260-1 27 LS-260-1 Bolt Hole Count 26 LS-260-2 Located on 25 LS-260-1 the Roof Rib 24 LS-260-1 23 LS-260-2 22 LS-260-2 21 LS-260-1 20 LS-260-1 LS-260-2 19 LS-260-1 LS-260-2 LS-260-3 18 LS-260-2 LS-260-3 LS-260-3 17 LS-260-3 LS-260-3 16 LS-260-3 Bin Eave 12 ↓ 11

NOTE: The table above shows the correct ladder step and part number to be installed in the corresponding hole in the roof rib. Shaded areas show the correct roof exhauster ladder step and part number with the corresponding hole in the roof rib. Preparation for Roof Exhauster Installation Before installing the roof exhauster, some preparation is required, utilizing the roof exhauster flashing and roof exhauster mounting plate. Before You Begin Determine the location of the roof exhauster and remove the existing roof flashing panel at this location. Install the peak-to-exhauster ladder kit next to the roof exhauster on the next available rib. What You Should Know This procedure is to temporarily install the roof exhauster flashing. Use the roof exhauster flashing and roof exhauster mounting plate as a template to determine the correct location for field drilling and cutting the roof exhauster hole.

132 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

1. Temporarily install the roof exhauster flashing (E) and ensure all the holes are aligned, and field drill all required holes (H). 2. Temporarily install the roof exhauster mounting plate (F) to the roof using six bolts and six nuts (G). 3. Using the roof exhauster mounting plate (F), mark or scribe the hole (I) to be cut. Tip If tabs are already bent, flip the mounting plate upside down to scribe the hole location. Figure 8-6 Using the roof exhauster flashing and mounting plate as a template

E Exhauster flashing (CTR-0276) H Hole to be field drilled F Exhauster mounting plate (CTR-0277) I Marked or scribed hole to be cut G 5/16 x 1 in hex bolt (S-10260) and 5/16 in. J Field bent inside tab on roof exhauster flange nut (S-3611) mounting plate

4. Bend the tabs (J) downward approximately 90 degrees on the roof exhauster mounting plate (F) to conform with the roof panel. NOTE: Bend the tabs on the ground and adjust as necessary once on the roof. 5. Remove the roof exhauster flashing (E) and roof exhauster mounting plate (F), to make the neces- sary cut along the mark or scribe (I).

Pneg-4075 75 Ft Diameter 40-Series Bin 133 Chapter 8: Accessories

IMPORTANT: The rib of the roof panels should also be cut along the mark shown. Do not cut into any purlins or rafters on the roof panels when making the cut for the roof exhauster. Figure 8-7 Using the roof exhauster flashing and mounting plate as a template

I Marked or scribed hole to be cut

Assembling the Roof Exhauster Assembly of the roof exhauster is done prior to installing onto the roof. 1. Apply a strip of tube caulk (C) along the mating surface of the exhauster standoff weldment (F) and the exhauster mounting plate (E). 2. Install the exhauster standoff weldment (F) to the exhauster mounting plate (E), and align all the holes. 3. Install only seven hex head bolts (A) and flange nuts (D) (as marked), securing the exhauster standoff weldment (F) to the exhauster mounting plate (E). 4. Apply a strip of tube caulk (C) along the mating surface of roof exhauster (B) and the exhauster standoff weldment (F). 5. Install the roof exhauster hood (B) to the exhauster standoff weldment (F), and align all the holes. 6. Install thirty-one hex head bolts (A) and flange nuts (D), securing the roof exhauster hood (B) to the exhauster standoff weldment (F).

134 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Figure 8-8 Roof exhauster assembly

A 5/16 x 1 in. hex bolt (S-10260) D 5/16 in. flange nut (S-3611) B Roof exhauster hood E Exhauster mounting plate (CTR-0277) C Tube Caulk F Exhauster standoff weldment (MIS-7117)

Installing Roof Exhauster Assembly The roof exhauster assembly replaces one of the roof flashing panels and allows for the roof exhauster to be installed. Before You Begin IMPORTANT: The location of the roof exhauster can vary. It should be installed in a location that is free of obstructions, where it does not interfere with any other accessories on the roof. NOTE: The roof exhauster kit is shipped with additional parts. The following part numbers will not be used on 40-series bins: MIS-6703, MIS-6706, MIS-6707, MIS-6805, MIS-6810, MIS-6811, CRP-4793 and CRP-5262.

Pneg-4075 75 Ft Diameter 40-Series Bin 135 Chapter 8: Accessories

1. Before lifting the roof exhauster into place, apply strips of sealing caulk (F) along the ribs of each roof panel and on each roof flashing as shown. 2. Use an appropriate lifting device and qualified personnel to hoist the roof exhauster assembly (D) into place. 3. Install flange bolts (G) and flange nuts (E), securing the roof exhauster assembly (D) to the roof panel. NOTE: Do not tighten flange bolts until all components have been installed. 4. Apply a strip of sealing caulk (C) along the mating surface of the roof exhauster assembly (D) and roof exhauster flashing (A). NOTE: Roof exhauster flashing (A) must be bolted on the top surface of the exhauster mounting plate. 5. Install flange bolts (B) and nuts (E), securing the roof exhauster flashing (A) to the roof exhauster assembly (D). 6. Tighten all hardware to the recommended torque specification. See Bolt Torque Specifications, page 24.

136 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Figure 8-9 Installing roof exhauster

A Roof exhauster flashing (CTR-0276) E 5/16 flange nut (S-3611) 5/16-18 x 1 flange bolt, with sealing washer B F Sealing caulk (S-10260) 5/16-18 x 1 flange bolt with sealing washer C Sealing caulk G (S-10260) D Roof exhauster assembly

7. When the roof exhauster assembly (D) is installed, apply sealing caulk (H) as shown by arrows, seal- ing the roof exhauster assembly (D) to the roof.

Pneg-4075 75 Ft Diameter 40-Series Bin 137 Chapter 8: Accessories

Figure 8-10 Sealing caulk location

D Roof exhauster assembly H Sealing caulk

Assembling the Auto Roof Vent The following instructions are for assembling the auto-vent. First, check the packing list to ensure all com- ponents have been shipped. The unit is easiest assembled in the upside-down position as shown in the instructions. 1. Take all parts out of the shipping box and ensure all parts are present. 2. Turn the roof vent housing assembly (D) upside down. 3. Install a hex bolt(B) through the hole on the side of roof vent housing (D). Install a flange nut (E) to the hex bolt (B) and tighten. 4. With the curvature facing upward, install the flap assembly (F) into the roof vent housing (D), and onto the end of the hex bolt (B). 5. Insert another hex bolt (B) through the other side of the roof vent housing (D), and install a flange nut (E) to the hex bolt (B), between the tab of the flap assembly (F) and the side of roof vent housing (D). 6. Apply a strip of caulking around the three housing sides of the roof vent assembly (D) where it meets the hold-down angle (A). 7. Place the hold-down angle (A) onto the assembled roof vent assembly (D), with the wide end or long end of the hold-down angle (A) facing the vent discharge and the short end facing the rear of the vent. 8. When the hold-down angle (A) is aligned, install #10 self-drilling screws through the roof housing and into the hold-down angle (A).

138 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Figure 8-11 Assembling the flap

A Hold-down angle (MIS-4404) D Roof vent housing assembly (MIS-6778) B 5/16 x 1-1/4 in hex bolt (S-277) E 5/16 in. flange nut (S-3611) C #10 self-drilling screws (S-280) F Flap assembly (MIS-6777)

Assembling Wire Grill Guard Roof Vent The following instructions are for assembling the wire grill guard roof vent. Before beginning assembly, check the packing list to ensure all components have been received. The unit is easiest assembled in the upside-down position as shown in the instructions. 1. Take all parts out of the shipping box and ensure all parts are present. 2. Turn the roof vent housing assembly (D) upside down. 3. Install a hex bolt (B) through the hole on the side of roof vent housing (D). Install a flange nut (E) to the hex bolt (B) and tighten. 4. With the eyelid tabs upward, install the wire grill guard assembly (F) into the roof vent housing (D), and onto the end of the hex bolt (B).

Pneg-4075 75 Ft Diameter 40-Series Bin 139 Chapter 8: Accessories

5. Insert another hex bolt (B) through the other side of the roof vent housing (D), and install a flange nut (E) to the hex bolt (B) , between the tab of the wire grill guard assembly (F) and the side of the roof vent housing (D). 6. Apply a strip of caulking around the three housing sides of the roof vent assembly (D) where it meets the hold-down angle (A). 7. Place the hold-down angle (A) onto the assembled roof vent assembly (D), with the wide end or long end of the hold-down angle (A) facing the vent discharge and the short end facing the rear of the wire grill vent. 8. When the hold-down angle (A) is aligned, install #10 self-drilling screws through the roof vent housing and into the hold-down angle (A).

Figure 8-12 Assembling the grill guard assembly

A Hold-down angle (MIS-4404) D Roof vent housing assembly (MIS-6778) B 5/16 x 1-1/4 in hex bolt (S-277) E 5/16 in. flange nut (S-3611) C #10 self-drilling screw (S-280) F Wire grill guard assembly (MIS-6766)

140 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories Installing the Wire Grill Guard and Auto Roof Vents The following instructions are for installing the wire grill guard roof vent and the auto roof vent. Before You Begin The wire grill guard roof vent and the auto roof vent are assembled prior to installing. 1. If the roof panel (D) does not have a pre-punched hole for the roof vent assembly (A), a hole must be cut. The cut hole should match the roof vent assembly (A). The hole’s inside edge should be approxi- mately 15 ft. (F) from the roof panel eave. 2. Place the three foam strips (C) on the roof panel (D), as shown, and position the roof vent assembly (A) over the foam strips (C). Install bolts (B) and nuts (H), securing the roof vent assembly (A) to the roof panel (D). 3. Instal bolts (G) and nuts (E) from the underside of the roof panel (D) securing the front of the hold- down angle to the roof panel as shown. Tighten the hardware to the recommended torque specifica- tions. See Bolt Torque Specifications, page 24.

Pneg-4075 75 Ft Diameter 40-Series Bin 141 Chapter 8: Accessories

Figure 8-13 Exploded view of vent housing to roof panel

A Roof vent assembly E 5/16 in. flange nut (S-3611) B 5/16 x 3/4 in. flange bolt (S-7482) F Approximately 15 in. (4.5 m) from the roof panel eave C Foam strips (side strips MIS-6781) (top G 5/16 x 3/4 in. flange bolt (S-275) strip MIS-6780) D Roof panel (part number varies) H 5/16 in. flange nut (S-3611)

4. Apply caulk to all holes, ensuring a tight seal. Installing the Manway Cover Installation of a manway cover is necessary if a manway hole is present. 1. Install each hinge base (A) to the manway roof panel (B), and secure with hex bolts (C) and nuts (D). 2. Install the latch bracket (E) to the manway roof panel (B), and secure with hex bolts (C) and nuts (D). 3. Press the manway seal strip (F) onto the lip of the manway sill (G). 4. Install each hinge leaf (H) to the manway cover (I) and secure with hex bolts (C) and nuts (D). 5. Install the latch bracket (J) to the manway cover (I) and secure with hex bolts (C) and nuts (D). 6. Tighten hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24.

142 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

7. Install the manway cover assembly by aligning the hinge leafs (H) with the hinge bases (A), and install a two hex bolts (K) securing each side of the hinges together with nuts (L). NOTE: When securing the hinge leaf (H) to the hinge base (A), double nut each hex bolt (K). 8. Affix suffocation/flighting decals (not shown) to the underside of the manway cover. NOTE: Suffocation/flighting decals replacement part numbers: English, DC-GBC-1A, and Spanish, DC-GBC-1S. Figure 8-14 Manway cover

A Hinge base (MW-291) G Manway sill B Manway roof panel (CTR-0302) H Hinge leaf (MW-272) C 5/16 x 3/4 in. hex bolt (S-275) I Manway cover (MW-008) D 5/16 in. nut (S-396) J Latch (MW-271) E Latch base bracket (MW-289) K 5/16 X 4 in. hex bolt (S-855) F Manway seal strip L 5/16 in. nut (S-396)

Pneg-4075 75 Ft Diameter 40-Series Bin 143 Chapter 8: Accessories Ladder Section Assembly The inside ladder package consists of the ladder, starter brackets, standoff brackets, reinforcement straps, and ending bracket. The ladder should to be assembled before installing it to the bin structure. What You Should Know When assembling ladder sections, ensure all slip resistant ladder rungs are oriented in the same direction. NOTE: A portion of the last ladder section may need to be cut to fit the proper length to the ground or to the intermediate platform. 1. Place two ladder sections (A) together as shown. 2. Install a splice plate (C) to each outside channel, connecting the ladder sections (A). 3. Install flange bolts (D) to each inside channel as shown, connecting the ladder sections (A). 4. Install flange nuts (B) to each outside channel as shown, securing the ladder sections (A). Tighten to the recommended torque specifications. See Bolt Torque Specifications, page 24.

Figure 8-15 Assembling the inside ladder sections

A Ladder section C Splice plate (LDR-4317) B 5/16 in. flange nut (S-3611) D 5/16 x 3/4 in. flange bolt (S-275)

Inside Ladder Placement The inside ladder provides manway access from inside the bin.

144 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

What You Should Know Begin by temporarily positioning the ladder (B) directly under the manway roof panel (A) for the correct placement location. Mark or scribe this location where each side of the ladder’s vertical channels meet the sidewall. Figure 8-16 Positioning the ladder

A Manway access B Ladder assembly

1. Install the right-hand starter bracket (C) to the top hole in the first sidewall ring, located closest to the eave. Install a flange bolt (D), and secure with a flange nut (G). 2. Measure approximately 18-3/4 inches (E) to the left of the RH starter bracket (C), and install the LH starter bracket (K) to the top hole in the first sidewall ring, located closest to the eave. Install a flange bolt (D), and secure with a flange nut (G). 3. Temporarily position the ladder back into place, ensuring that the mating surface of each starter brackets (C and K) are aligned with the inside mating surface of each vertical channel of the ladder (B). 4. Field drill a second 3/8 in. hole (F) using the bottom hole in the starter brackets (C and K) as guides. Install a flange bolt (D), and secure with a flange nut (G). Tighten hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24. 5. Working down from the starter brackets (C and K), and in alignment, install a ladder standoff bracket (H) at every horizontal seam or 32 in. from the previous installed bracket. Install a flange bolt (D) and a flange nut (G), securing each ladder standoff bracket (H) to the sidewall. NOTE: Installing a plumb line to the starter bracket will help keep each bracket aligned evenly.

Pneg-4075 75 Ft Diameter 40-Series Bin 145 Chapter 8: Accessories

6. Install a ladder reinforcing strap (I) to the ladder standoff brackets (H), and install two hex bolts (J) and nuts (G). NOTE: For optimal reinforcement, install the ladder reinforcing straps (I) in a diagonal fashion as shown. 7. Tighten hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24. 8. Install the ladder (B) to the starter brackets (C and K), and install hex bolts (M) and nuts (N), but do not tighten at this time. 9. Install a carriage bolt (Q) to a standoff wedge (O), and insert into the outside channel of the ladder assembly (B). 10.Connect the standoff wedge (O) to the standoff bracket (H), and install a flange nut (P), but do not tighten allowing, for adjustment.

146 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Figure 8-17 Installing ladder brackets

B Ladder assembly J 5/16 in. hex bolt (S-275) C Starter bracket (RH LDR-4347) K Starter bracket (LH LDR-4346) D See sidewall hardware chart. L 3/8 in. field drilled hole location E Approximately 18-3/4 in. (47.62 mm) M 5/16 x 3/4 in. flange bolt (S-275) F 3/8 in. field drilled hole location N 5/16 in. flange nut (S-3611) G 5/16 in. hex nut (S-396) O Standoff wedge (LDR-4198) H Standoff bracket (LDR-4314) P 5/16 in. flange nut (S-3611) I Ladder reinforcing strap (LDR-5132) Q 5/16 x 1 in. carriage bolt (S-3550)

Repeat this process for the remaining standoff brackets. 11.Field drill a 3/8 in. hole (L), and install hex bolts (M) and nuts (N), securing the ladder to the starter brackets (C and K). 12.Tighten all hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24.

Pneg-4075 75 Ft Diameter 40-Series Bin 147 Chapter 8: Accessories Installing Inside Ladder Bottom Bracket The ladder bottom bracket keeps the lower portion of the ladder secure. What You Should Know The lower portion of the ladder may need to be cut to fit properly. Field drilling will be required to complete installation. 1. Ensure the bottom of the ladder (A) is raised 12 in. (38.5 cm) from the floor. NOTE: If the ladder is not 12 in. (38.5 cm) from the floor, cut to specification. 2. Attach the two ladder bottom brackets (B) to the inside portion of the ladder assembly (A). 3. Align the holes in the sidewall with the ladder bottom bracket (B), and install flange bolts (E) and nuts (C). 4. Field drill two 3/8 in. holes (D) as shown, and install the remaining flange bolts (E) and nuts (C), securing the ladder bottom bracket (B) to the sidewall. 5. Field drill six 3/8 in. holes (F) as shown, and install flange bolts (G) and nuts (H). 6. Repeat this procedure for the second ladder bottom bracket (B). 7. Tighten hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24.

148 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Figure 8-18 Bottom ladder bracket

A Ladder assembly E 5/16 x 3/4 in. flange bolt (S-7482) B Ladder bottom bracket (LDR5133) F 3/8 in. field drilled hole location C 5/16 in. flange nut (S-396) G 5/16 x 3/4 in. flange bolt (S-7482) D 3/8 in. field drilled hole location H 5/16 in. flange nut (S-396)

Guidelines for Installing a Sidedraw System A sidedraw system will allow content unloading using gravity, and is done from the side of the bin. General Guidelines to Follow Before Installing A Sidedraw System: NOTE: If a sidedraw system is installed, the standard 3/4 in. anchor bolts must be replaced with 1 in. anchor bolts. • Side discharge is only permitted in GSI commercial bins when a GSI manufactured sidedraw flume system has been installed. No corrugated steel bin must be unloaded through the side wall without installation of such a system and permission of the manufacturer. • A sidedraw should not be the only discharge system available. A standard center discharge and con- veyor must be installed.

Pneg-4075 75 Ft Diameter 40-Series Bin 149 Chapter 8: Accessories

• Installation of multiple systems may require additional wind rings and must be placed a minimum of 90 degrees apart. Installation of multiple systems requires approval of GSI. • Sidedraw systems are intended for use with dry, flowable grain. Sidedraws are not to be used for poorly flowing products. This is not unique to GSI bins and flume systems, but is a general rule for such systems. • In multiple system installations, only one sidedraw may be used at any one time. • Filling must not be occurring at the same time as grain is being withdrawn through the sidedraw flume system. • Prolonged storage of grain in the sloped condition produced by sidedraw discharge may accelerate differential settlement and result in deformations of the bin. After using the sidedraw system, the sloped grain must be returned to a near level condition by use of the center discharge. Leveling of the grain should also allow more even consolidation of foundation and fill soils and produce more even settlement of the bin. • If past experience or geotechnical investigations indicate significant foundation level soil variations or a site propensity toward differential settlement, sidedraw usage may be prohibited or severely restricted. In this situation the use of a flume system should be reviewed with geotechnical consul- tants or the foundation engineer. • Before installing, determine if bin design is a two post stiffener (D) or a three post stiffener (E) configu- ration. See the following figures. • Only install baffle chutes and discharge chute between the post stiffeners (D and E). • Do not install a discharge chute on a vertical seam. • A discharge chute should be installed at the standard height (F).

150 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Figure 8-19 Two and three post stiffener examples

A Typical 24-ring bin D Two post stiffener B Typical 29-ring bin E Three post stiffener C Sidewall sheet F Standard height of discharge chute 16 ft. 4 in. (5 m)

NOTE: Use the following tables as a guide or reference for the proper placement of the sidedraw system.

Pneg-4075 75 Ft Diameter 40-Series Bin 151 Chapter 8: Accessories

Table 8-3 Sidewall Instructions (Two Post Stiffener)

Number of Rings on the Bin Chute Location Horizontal Starting Location Locate 1st chute in 2nd ring from top. All Top bolt holes in chute to be located on 2nd corrugation of body sheet. 11, 12, 15, 17, 19, 21, and 23 Center chute over vertical seam. 10, 12, 14, 16, 18, 20, 22, and 24 Center chute 56-1/4 in. from the 1st horizontal seam bolt in the 2nd ring.

Table 8-4 Sidewall Instructions (Three Post Stiffener)

Number of Rings on the Bin Chute Location Horizontal Starting Location Locate 1st chute in 2nd ring from top. All Top bolt holes in chute to be located on 2nd corrugation of body sheet. 11, 14, 17, 20, 23, 26, 29, 32, and 35 Center chute 75 in. (left to right) from 1st hole in 2nd body sheet. 10, 13, 16, 19, 22, 25, 28, 31, 34, and 37 Center chute 37-1/2 in. (left to right) from 1st hole in 2nd body sheet. 12, 15, 18, 21, 24, 27, 30, 33, and 36 Center chute over vertical seam. Installing the Sidedraw Baffle Chute (Two Post Stiffener) The sidedraw baffle chute helps direct the bin contents to the discharge chute. 1. Determine the sidedraw system location, and ensure the installation of baffle chutes (C) will not inter- fere with stiffeners (A). 2. Starting at the top of the bin, locate the second ring (B), and measure 56-3/4 in. (D) from the edge of sidewall sheet (E), for the proper centering placement of the baffle chute. 3. Locate the horizontal seam connecting the first and second ring, and measure approximately 2-21/32 in. (J) from the center hole in the horizontal seam to the first center hole on the baffle chute. Mark or scribe the hole location. 4. Align the first baffle chute hole with the mark, and ensure the baffle chute is level. Place another mark or scribe at the opposite hole on the baffle chute (C). 5. Field drill a 7/16 in. hole and install flange bolts (H) and flange nuts (I). 6. Repeat the field drilling process for the remaining six holes. 7. Repeat this procedure for the remaining baffle chutes. NOTE: A typical installation has equal spacing (K).

152 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Figure 8-20 First Chute Locations (Two Post Stiffener Only) and Spacing of each baffle chute

A Stiffener’s center line G Field drilled hole location (7/16 in. diameter hole) B Second ring from top of bin H 3/8 x 1-1/2 in. flange bolt (S-7488) C Suitable baffle chute locations I 3/8 in. flange nut (S-456) D Measurement from edge of sidewall sheet J Measurement, approximately 2-21/32 in. (6.77 to center line of baffle chute, 56-3/4 in. cm) (142.9 cm) E Edge of sidewall sheet K Typical spacing, approximately 8 in. (20.32 cm) F Inside of bin

8. Tighten hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24. Installing the Sidedraw Baffle Chute (Three Post Stiffener) The Sidedraw baffle chute helps direct the bin contents to the discharge chute. 1. Determine the sidedraw system location, and ensure the installation of baffle chutes (C) will not inter- fere with stiffeners (A). 2. Starting at the top of the bin, locate the second ring (B), and measure from the edge of sidewall sheet (D or E), for the proper centering placement of the baffle chute.

Pneg-4075 75 Ft Diameter 40-Series Bin 153 Chapter 8: Accessories

NOTE: Depending on the location of the baffle chute (C), the measurement from the sidewall edge will vary (D or E). 3. Locate the horizontal seam connecting the first and second ring, and measure approximately 2-21/32 in. (J) from the center hole in the horizontal seam, to the first center hole on the baffle chute, mark or scribe the hole location. 4. Align and the first baffle chute hole with the mark or scribe, and ensure the baffle chute is level. Place another mark or scribe at the opposite hole on the baffle chute (C). 5. Field drill a 7/16 in. hole and install flange bolts (H) and flange nuts (I). 6. Repeat the field drilling process for the remaining six holes. 7. Repeat this procedure for the remaining baffle chutes. NOTE: A typical installation has equal spacing (K). Figure 8-21 First chute locations (three post stiffener only), and spacing of each baffle chute

A Stiffener’s center line G Field drilled hole location (7/16 in. diameter hole) B Second ring from top of bin H 3/8 x 1-1/2 in. flange bolt (S-7488) C Suitable baffle chute locations I 3/8 in. flange nut (S-456) D Measurement from edge of sidewall sheet J Measurement, approximately 2-21/32 in. (6.77 to center line of baffle chute, 37-1/2 in. cm.) (95.25 cm.)

154 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

E Measurement from edge of sidewall sheet K Typical spacing, approximately 8 in. (20.32 cm) to center line of baffle chute, 75 in. (190.5 cm) F Inside of bin

8. Tighten hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24. Installing the Sidedraw Discharge Chute The following instructions discribe the installation of the sidedraw discharge chute. What You Should Know Field cutting is required to create the opening for the discharge chute. Cutting the opening will require two sidewall panels to be modified. 1. Find the column of bolt holes (A) located on either side of the last baffle chute (B). Measure approxi- mately 11 in. (27.94 cm) (C) inward on the last baffle chute (B), and place a mark or scribe. 2. Repeat this procedure from the opposite column of bolt holes (A), creating the center line (D) on the baffle chute (B), and transfer this center line (D) onto the sidewall panel.

Pneg-4075 75 Ft Diameter 40-Series Bin 155 Chapter 8: Accessories

Figure 8-22 Vertical line location of discharge chute

A Column of bolt holes C Measurement, approximately 11 in. (27.94 cm) B Baffle chute D Vertical center line

3. Measure approximately 4 in. (16.16 cm) upward from the sidewall horizontal seam (E), and place a mark or scribe, creating a horizontal center line (G). 4. Place another mark or scribe where the vertical center line (D) and the horizontal center line (G) meet, creating the center of the discharge chute location (F). 5. Remove the baffle chute from the sidewall panel.

156 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Figure 8-23 Horizontal line location of discharge chute

D Vertical center line F Center of discharge chute location E Sidewall horizontal seam G Horizontal center line

6. Measure approximately 7 in. (17.78 cm) on each side of the vertical center line (D), and place a mark or scribe. 7. Measure approximately 8-1/2 in. (21.59 cm) on each side of the horizontal center line (G), and place a mark or scribe. 8. Using these marks, create an outline of the discharge chute hole to be cut. 9. Field cut the discharge chute hole making a 1-1/2 radius at each corner.

Pneg-4075 75 Ft Diameter 40-Series Bin 157 Chapter 8: Accessories

Figure 8-24 Discharge Chute Hole Outline

D Vertical center line G Horizontal center line

10.Separate the upper sidewall panel (I) from the lower sidewall panel (J). 11.Apply two beads of caulk to seal the discharge chute assembly to the sidewall panels, and insert the discharge chute assembly (H) between the upper sidewall panel (I) and the lower sidewall panel (J). NOTE: To ensure proper watershed, the discharge chute assembly (H) is installed behind the upper sidewall panel (I) and in front of the lower sidewall panel (J).

158 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Figure 8-25 Discharge chute assembly (view form inside the bin)

H Discharge chute assembly J Lower sidewall panel I Upper sidewall panel

12.Using the discharge chute assembly (H) as a guide or template, field drill all necessary holes to secure the discharge chute assembly (H) to the upper sidewall panel (I) and the lower sidewall panel (J). NOTE: When using the discharge chute assembly (H) as a guide or template, field drilling the upper sidewall panel (I) will be done from inside the bin structure, and field drilling the lower sidewall panel (J) will be done from outside the bin structure. 13.Install flange bolts (K) and flange nuts (L), securing the discharge chute assembly (H) to the upper sidewall panel (I) and the lower sidewall panel (J).

Pneg-4075 75 Ft Diameter 40-Series Bin 159 Chapter 8: Accessories

Figure 8-26 Field drilling discharge chute assembly (view from inside the bin)

H Discharge chute assembly K 5/16 x 1-1/4 in. flange bolt (S-10250) I Upper sidewall panel L 5/16 in. flange nut (S-10251) J Lower sidewall panel

14.Place the baffle chute (B) into place and field drill necessary holes, securing with flange bolts and flange nuts.

160 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Figure 8-27 Reinstall baffle chute (view from inside the bin)

B Baffle chute M Field drilled hole location

15.Tighten hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24.

Pneg-4075 75 Ft Diameter 40-Series Bin 161 Chapter 8: Accessories Wind Ring Requirements Wind rings give additional strength against high winds and uneven loads. The quantities and placement of wind rings will depend on the size of bin being constructed. Figure 8-28 Wind ring locations

A Distance (inches) between the center of each wind ring pipe Sidewall ring numbers and location for ring pipe (0.00) = horizontal seam installation. (0.25) = quarter sheet down from top of sidewall ring "R" Value (ex. R10) = Sidewall ring number, (0.50) = half sheet down from top of sidewall ring B "0.XX" (ex. 0.25) = Wind ring pipe center line location (0.75) = three quarter sheet down from top of the within the sidewall ring measured from the top of the sidewall ring each sidewall ring

162 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Figure 8-29 Dimensions for OSHA Compliant Ladder Rung Placement

NOTE: Ensure the wind rings are installed in rela- tion to the ladder rungs as shown to meet O.S.H.A. specifications.

Installing Wind Rings Installation of wind rings is similar for a two and a three post bin design, although hardware quantities may vary. What You Should Know Before installing, determine the bin size, sidewall gauge thickness, and height. Use the hardware chart to match the correct bolt length with the correct sidewall gauge thickness when installing the wind ring brack- ets to the stiffeners (Refer to hardware requirements chapter). To determine the location of the wind rings or if additional wind rings will be needed for sidedraw systems, see Wind Ring Requirements for Sidedraw Systems.

Pneg-4075 75 Ft Diameter 40-Series Bin 163 Chapter 8: Accessories

1. Install a wind ring bracket (B) to each stiffener (C) using flange bolts (A) and flange nuts (D).

Figure 8-30 Wind ring bracket

NOTE: When installing the wind ring bracket to a 2.66" close punched stiffener, use the bolt holes marked 1, 2, 4, and 5 as shown. When installing the wind ring bracket to a 2.66" far punched stiffener, use the bolt holes marked 1 and 5 only. Hole marked 3 will not be used on all 2.66" bins. Flange bolt hardware length may vary with side- wall gauge thickness.

2. Tighten hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24. 3. Place a wind ring section (E) into the channel of the wind ring bracket (B), and install a C-clamp (I), securing with flange bolts (H) and flange nuts (J). Do not tighten until all wind ring sections are installed. 4. Repeat this procedure, inserting each wind ring section (E), over the previously installed wind ring section, securing the wind ring sections together with flange bolts (F) and hex nuts (G). 5. Before installing the last wind ring section (E), slide a wind ring coupling collar (K) over the wind ring section (E). 6. Install the last wind ring section (E) and cut the wind ring section to the proper length. NOTE: The cut needs to be made in a location that allows minimal space between the pipes. 7. Slide the wind ring coupling collar (K), aligning the three pre-drilled holes, and install flange bolts (F) and hex nuts (G). Field drill the remaining three holes (L) using the wind ring coupling collar (K) as a guide or template. 8. Install the remaining flange bolts (F) and hex nuts (G), and tighten all hardware to the recommended torque specifications. See Bolt Torque Specifications, page 24.

164 Pneg-4075 75 Ft Diameter 40-Series Bin Chapter 8: Accessories

Figure 8-31 Exploded view of wind ring installed at upper portion of stiffener

A Flange bolt with sealing washer (part G 7/16 in. hex nut (S-9281) number will vary) B Wind ring bracket (CTS-1005) H 3/8 x 1 in. flange bolt (S-7485) C Stiffener (part number will vary) I C-clamp (SS-7248) D Flange nut (part number will vary) J 3/8 in flange nut (S-9426) E Wind ring section (CTS-1004-XX or CTS- K Wind ring coupling collar (CTS-1006) 1002–XX)9 F 7/16 x 3-1/4 in. flange bolt with sealing L Field drilled hole location washer (S-10261)

Assembling Weather Cover for Roller Valve The following instructions are for assembling the weather cover for the roller valve. 1. Install the weather cover kit after the gate has been installed. 2. Use bead caulking at all seams where the weather cover attaches to the gate. 3. Use hex bolts (C) and flange nuts (D) to plug all holes not in use. 4. Use 1/4 in. self-drilling screw (B) to seal gate end plate corners.

9. (-XX) denotes the bin diameter.

Pneg-4075 75 Ft Diameter 40-Series Bin 165 Chapter 8: Accessories

Figure 8-32 Weather Cover Assembly

A Universal weather cover plate (CHT- D 5/16 in. flange nut (S-3611) 1351) B 1/4 in. self-drilling screw (S-6497) E Universal weather cover plate (CHT-1351) C 5/16 x 3/4 in. hex bolt (S–275) F Chain wheel (typical)

166 Pneg-4075 75 Ft Diameter 40-Series Bin GSI Group, LLC Limited Warranty GSI Group, LLC Limited Warranty The GSI Group, LLC (“GSI”) warrants products which it manufactures to be free of defects in materials and workmanship under normal usage and conditions for a period of 12 months after sale to the original end-user or if a foreign sale, 14 months from arrival at port of discharge, whichever is earlier. The end-user’s sole remedy (and GSI’s only obligation) is to repair or replace, at GSI’s option and expense, products that in GSI’s judgment, contain a material defect in materials or workmanship. Expenses incurred by or on behalf of the end-user without prior written authorization from the GSI Warranty Group shall be the sole responsibility of the end-user. Warranty Extensions: The Limited Warranty period is extended for the following products:

Product Warranty Period * Warranty prorated from list price: Performer Series Direct Drive Fan Motor 3 Years 0 to 3 years - no cost to end-user All Fiberglass Housings AP Fans and Flooring Lifetime 3 to 5 years - end-user pays 25% All Fiberglass Propellers Lifetime 5 to 7 years - end-user pays 50% Feeder System Pan Assemblies 5 Years ** 7 to 10 years - end-user pays 75% Cumberland Feed Tubes (1-3/4" and 2.00") 10 Years * Feeding/Watering ** Warranty prorated from list price: Systems Centerless Augers 10 Years * 0 to 3 years - no cost to end-user Watering Nipples 10 Years * 3 to 5 years - end-user pays 50% Grain Systems Grain Bin Structural Design 5 Years † Motors, burner components and Grain Systems Portable and Tower Dryers 2 Years moving parts not included. Farm Fans Portable and Tower Dryer Frames and Inter- Portable dryer screens included. Zimmerman 5 Years nal Infrastructure † Tower dryer screens not included.

GSI further warrants that the portable and tower dryer frame and basket, excluding all auger and auger drive components, shall be free from defects in materials for a period of time beginning on the twelfth (12th) month from the date of purchase and continuing until the sixtieth (60th) month from the date of purchase (extended warranty period). During the extended warranty period, GSI will replace the frame or basket components that prove to be defective under normal conditions of use without charge, excluding the labor, transportation, and/or shipping costs incurred in the performance of this extended warranty. Conditions and Limitations: THERE ARE NO WARRANTIES THAT EXTEND BEYOND THE LIMITED WARRANTY DESCRIPTION SET FORTH ABOVE. SPECIFICALLY, GSI MAKES NO FURTHER WARRANTY OF ANY KIND, EXPRESS OR IMPLIED, INCLUDING, WITHOUT LIMITATION, WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE OR USE IN CONNECTION WITH: (I) PRODUCT MANUFACTURED OR SOLD BY GSI OR (II) ANY ADVICE, INSTRUCTION, RECOMMENDATION OR SUGGESTION PROVIDED BY AN AGENT, REPRESENTATIVE OR EMPLOYEE OF GSI REGARDING OR RELATED TO THE CONFIGURATION, INSTALLATION, LAYOUT, SUITABILITY FOR A PARTICULAR PURPOSE, OR DESIGN OF SUCH PRODUCTS. GSI shall not be liable for any direct, indirect, incidental or consequential damages, including, without limitation, loss of anticipated profits or benefits. The sole and exclusive remedy is set forth in the Limited Warranty, which shall not exceed the amount paid for the product purchased. This warranty is not transferable and applies only to the original end-user. GSI shall have no obligation or responsibility for any representations or warranties made by or on behalf of any dealer, agent or distributor. GSI assumes no responsibility for claims resulting from construction defects or unauthorized modifications to products which it manufactured. Modifications to products not specifically delineated in the manual accompanying the equipment at initial sale will void the Limited Warranty. This Limited Warranty shall not extend to products or parts which have been damaged by negligent use, misuse, alteration, accident or which have been improperly/inadequately maintained. This Limited Warranty extends solely to products manu- factured by GSI. Prior to installation, the end-user has the responsibility to comply with federal, state and local codes which apply to the loca- tion and installation of products manufactured or sold by GSI. 9101239_1_CR_rev7.xml (revised July 2009)

Pneg-4075 75 Ft Diameter 40-Series Bin 167 This equipment shall be installed in accordance with the current installation codes and applicable regulations which should be carefully followed in all cases. Authorities having jurisdiction should be consulted before installations are made.

GSI Group 1004 E. Illinois St. Assumption, IL 62510-0020 Phone: 1-217-226-4421 Fax: 1-217-226-4420 www.gsiag.com

GSI is a worldwide brand of AGCO Corporation.

Copyright © 2013 by GSI Group Printed in the USA CN #123456