A45 Development Link Road Due for completion spring 2018 Highways Newsletter 4 - March 2017

Simon Levell Rebecca Miller Site liaison manager Communication [email protected] manager [email protected]

Welcome to the fourth edition of the Daventry Development Link Road Newsletter. The scheme

The last three months, since the last Newsletter No. 3 in December 2016, has seen The A45 Daventry Development Link Road (formerly Weedon, Flore & Upper Heyford Bypass) will be steady progress on site. We had our planned two-week Christmas/New Year a new 3.5 mile (5.7 km) single carriageway. shutdown, the generally short daylight hours and often difficult weather conditions in terms of temperatures, rainfall and sometimes high winds means that certain activities – notably earthworks and concreting – can be constrained or not take place The road will start at a new roundabout on the existing A45 between the villages of Dodford and at all. Weedon. It will then pass to the north of the communities of Weedon, Flore and Upper Heyford before re-joining the A45 at a new roundabout between Upper Heyford and the at That said, the contractors – Balfour Beatty – and their sub-contractors have been junction 16. progressing well. We had to adjust some of the programme and implemented imaginative and pro-active efforts to keep on programme and advance a number of The scheme features extensive earthworks (cuttings and embankments) and includes the work activities. construction of eight structures as follows: The main construction works (phase 2 contract) continues as planned, and in • A major combined bridge crossing of the Railway & Grand conjunction with Northamptonshire Highways issues are being communicated to Union Canal affected parties and the local community. Since it was agreed that the Daventry link • A bridge spanning the ( Branch) Road would be constructed we have been liaising, and co-existing, with land • Bridges carrying Brockhall Road, Brington Road, a bridleway and a byway over the owners, the local population, local businesses, statutory agencies (such as new road Network Rail and Canal & River Trust) and the travelling public. Although our works are weather dependant we remain on schedule to complete Spring 2018. • A stream culvert (a structure that allows water to flow under the road) and farm access bridge We aim to minimise disruption for our neighbours during construction. Local access to residential properties on the north side of Flore is from the A45 High We will do this by: Street, whilst Brockhall and nearby farms are accessed from the A5 north of Weedon or the Daventry – Duston road via from the north – suitable diversions are in place for local traffic and the local communities are being kept fully informed through • Carrying out as much of the construction work during the day time as we can various communication channels. This closure is necessary to enable the efficient and • Using clear diversion route signs when roads are closed timely completion of the bridge which will eventually carry the Brockhall Road over the • Ensuring that site vehicles only use approved routes link road. We did consider a temporary diversion to allow the road to remain open. How- • Closely monitoring the impact of site operations ever, this would actually have been impractical and a rather costly addition to the scheme • Using techniques and machines designed to minimise noise and vibration budget. • Keeping in regular contact with our neighbours so they are informed as works progress One challenge we have faced is the planned or unscheduled closure between junctions 16 & 18 on the M1. We liaise with Highways all the time but, as we all know, For road users we will ensure their safety by: if anything happens on the M1 the A45 and A5 take the strain and become congested, often having a detrimental effect on our deliveries and construction too.

• Operating a reduced speed limit through the road works; this makes it safer for The temporary diversion alignment for the A5 trunk road has now been operational for the workforce and drivers, and gives drivers more time to react to the road around 4 months. The switchover went well and the road is working for all roadusers. conditions ahead In recent weeks we had a short night closure to replace road markings to ensure safety. • Keeping road closures to a minimum and avoiding peak hours where possible The temporary road enabled a start to be made during the autumn on reconstructing the existing by placing layers of stone and fill in order to bring it up to its final level (new roundabout connection with the link road). Works on this will start again once the site becomes more dry and earthworks can resume. Construction Progress – what have we done so far and what are we doing next? Earthworks Temporary Works & Traffic Management Whilst most of the stripping of topsoil was complete by December (around 75%) some additional areas have now been stripped, bringing this total to around 85%. Bulk The stone haul roads that were established within the site perimeter along much of the earthworks have slowed down in recent weeks purely due to how wet it has been. length of the new road corridor (to ensure efficient movements of heavy construction plant and essential material deliveries as well as general site access) have required some Another area of earthworks progress has been the re-aligned route of Brockhall Road, in routine maintenance. Although winter has been reasonably kind to us rainfall and our readiness for diverting this local road over the new bridge once complete. Works are also ground conditions have still proved challenging and created no go areas at times. These continuing to take place associated with constructing the major railway and canal bridge muddy conditions means roads on the area suffer and we have ensured they are regularly over the West Coast Main Line and . The main construction work is cleaned and swept. We are committed to road user safety and mitigating the impact on due to start in the spring. local communities Drainage Traffic management remains an important consideration, ensuring construction-related Drainage works – placing manholes, pipe runs and gullies to drain surface water from vehicle movements do not take place on local roads as far as is practicable. Advance the new road – have progressed particularly well at the new western A45 (Cavalry Hill) warning signs and related traffic management signage – such as safety-related speed roundabout on the Dodford side of Weedon. Stone layers and kerbing have also been limits – continue to be in force on all public road approaches and interfaces with the main placed in readiness for tarmacking. The plan is to complete one side of the roundabout works, notably on the A45 (both ends of scheme), A5 trunk road, Brockhall and Brington and allow traffic to use it, whilst completing the other side of the roundabout. Roads. At the eastern end of the scheme, preparatory works have taken place to install drainage A notable change in the last quarter is the temporary closure of Brockhall Road, Flore, to across the fields. The new road also benefits from five balancing ponds. which will through traffic, which came into force in the second week of January and is expected to collect water to ensure that local watercourses are not overloaded during heavy rainfall. last for between 6 and 8 months. Although it has been wet on site we have been using pumps in order to keep earthworks and For more information about the scheme you can visit the website at bridge excavations as free of water as possible. www.northamptonshire.gov.uk Bridges and Structures As indicated above, the Brockhall Road north of Flore is currently closed to enable construction Please advise people that they can join this mailing list and receive regular of the new overbridge. A large excavation has been made and works are now proceeding on the progress updates by emailing [email protected] and registering new bridge. The abutment front and wingwalls on both sides of the bridge are starting to emerge their email address. They will be added to the mailing list and this from the ground. The design uses reinforced earth technology which ‘locks’ together bands of information will remain confidential and will not be shared with any third compacted fill material between reinforcing layers which are then anchored to interlocking concrete retaining walls. This system is cost-effective and efficient to construct, and is to be parties. used on all the side road structures along the route (the others being at Brington Road and Upper Heyford). We will also be using this method on the green bridge at Hillside Road, Flore. This If you have any questions relating to these activities please do not hesitate ecological structure will not only take pedestrians over the link road but also allow wild animals to contact Simon Levell at [email protected] who will be your to safely make the crossing. site-based contact on day-to-day issues specifically relating to the road The excavation for the Green Bridge is complete, with work starting on the abutments for that construction phase and its impacts. structure. Further west again is the site of Whilton Brook Bridge (over a key branch of the River Nene) Excavation and rock fill has already taken place in readiness for the abutments to be For all general highway issues that are not specific to the Daventry constructed for this key river crossing. Development Link Road works you should contact the Street Doctor

Archaeology, Ecology & Environment service in Northamptonshire. At the site of Upper Heyford Bridge, archaeological investigation work has taken place in connection with residual planning requirements to investigate the presence and extent of Roman Remember, you can also report highway faults online with our road remains. Our ecologists have been on site to mitigate any impact and species-rich Street Doctor service. northamptonshire.gov.uk/streetdoctor hedgerow has been translocated to ensure its preservation for the future.

Fencing Works & Utility Diversions Follow us on Twitter @nnhighways for all the latest transport and A great deal of the fencing work has been completed, particularly where there are farming needs. highways updates and news. Meanwhile, work continues on utility diversions (water, gas, electricity, telecoms etc.) and connections to water troughs serving land owners’ fields used for grazing as part of A45 Daventry Development Link Road funded by: accommodation works obligations. Northamptonshire County Council, SEMLEP and Community Liaison & Communications Daventry District Council Throughout these works, close liaison continues to be maintained with the local land owners, in order to ensure that their farming operations are not compromised or delayed. Our priority is to let everyone affected know what is going on and we welcome you contacting us to find out more or if you have any questions or concerns.

Balfour Beatty have registered the project with the Considerate Constructors Scheme, a nationally-recognised initiative which rewards contractors and projects based on being good neighbours with the local residential, business and road-using communities with whom they have to co-exist: Indeed, to date Balfour Beatty have contributed to a summer bank holiday event in Weedon and the playing field facilities in Flore. A 5

Pond Rights of Way - Key A M 1 5 Brooks's Plantation Pond FB FB 98.1m 89.6m FB

97.2m Flore Fields Spinney Vicarage Farm DW Pond

Drain 96.3m 92.4m MP 71 94.5m Track 93.9m Targets BM 95.02m Existing Bridleway Tank BM 98.86m Cattle Grid

87.2m Vicarage Farm

Canal Lower Belt 103.9m Spring 100.3m Existing Footway Weir T rack Dundas Covert

ck BM 93.40m Tra Greenway Spinney  Issues Diverted Footway

Lower Glassthorpe Lodge

Towing Path Issues New Covert n 92.0m Def Drai GP Pond BM 104.47m Pond Skewbridge Dra Spinney in

89.6m ok BM 97.28m

ilton Bro h W

W a 96.3m 93.9m ROMANtli RO n g Stree

Pond

t AD 96.3m Pond

G ui d e Post

Pond 102.7m

Sinks Drain

Posts 93.3m

Spring 91.4m Skew Bridge Pond PTP 99.1m

GP BM 95.01m Broamenthill Spinney MP 70.75 Pond

EU2 95.7m PTP 99.1m Track Grand Union Canal The newPond road EU6

Trac Cloverlea

k

ETL Landing Spinney M 1 101.8m Pond EU14 Pond Pond

Sand Pit 93.3m 95.4m Track

Drain Sinks 93.3m

Issues

Pond BM 92.26m 97.2m

BM 97.91m

Area of Archaeological Drain Interest

Issues

Issues Green Bridge Issues 94.8m Track

Pond SL 86.9m Ford BM 101.10m

Wagoners Cottage Track Issues

Willow Track 96.3m 97.2m Issues

Def CS Pond BM 87.02m EU2 Pond

Spring

Track Pond

Ponds Issues FB Pond Pond Lay-by Oxhouse Farm

MP 70.5 95.4m

Pond 98.1m Sinks Pond 95.7m

Dra

in PET CEMETERY Pump Flagstaff Brockhall Road Oxhouse Farm Cottages Issues Sinks 100.3m EU15 118.9m

Bridge Issues

107.0m Pond 101.8m

Collects

Drain Pond GP

EU14 127.4m Hobhill Spinney FB Def 108.5m

A 5

M 1

A 5 Track Drai

n 94.8m 99.4m Stone Hobhill Spinney Drain Track 135.0m 97.2m Collinshill Farm Track EU15 Tr Drain ack

Pond SL Stone Hobhill Barn

84.4m

MP 1 MP 8 Pond Spring 122.5m

Dodmoor Farm Grounds Mast

Pond EU6 BM 118.99m

Dodmoor Farm 122.5m 93.3m BM 99.02m EU18

Pond EN9 99.4m

140.8m Track Pond Riding Stables Glassthorpehill Pond

Willow End 2 Foot Bridge Issues

Spring 1

Track Pillar BM 141.45m Issues MP .25 EU1 Flag Staff Pond Track M 1

The White House 86.3m GP Hadland House Farm 95.4m Dodmoor Farm M 82.3m 1 Bungalow GP BM 93.74m BM 82.02m

BM 100.04m 98.5m FB BM 82.12m 92.0m BM 108.36m

2 Honeymoon Cottage 8 97.8m 104.5m 109.4m Hadland House

OTT CL 31 MUSC Brington Road 101.8m HI

SEARS CLOSE

L

LSIDE BM

1 12 14

3 95.1m 29 104.94m 3 Tanks 2

ROA Bridge

D

Smallholding

9

1

6 20 103.9m 14 EU5

Reservoir 12

20

1

7 26

2 2

5 1 1

1 0 ETL BR 2 82.0m OC

12 E CRESCENT KH TH 31

ALL EL Water Tower Path 90.2m

22 RO

Towing Path FLORE AD El Sub Sta 14

8 33kV

COLLINS HILL 1

11

7

2

3

1

11 1 5

Watling Street 15 ROMAN ROAD 6a 11 100.3m EL 6 Drain EU7 Pond Police House Pond 2

n 14 n SE 3 Drai EL Drai CAPELL RI 2

26 Garage 100.6m

11kV

1 EU18

23 15 11 Shelter EU7 EU7 EL 95.7m 93.6m EU5 33kV 2 KT5 1 Memorial HIGH STREET BM 94.24m 88.7m EL 82.0m Pond LB

43

44 44a

6a

4

56

41 46 White Hart 50

a 48

6 5

New A5 52 (PH) 1

53 PO

4 9 0 Whilton Brook 27 4 Hall

EL Pond 2

3 6

MP 70 Flore Hill Farm Pond 4 Works 58

10 a Track

6 2 34

Dismantled Railway Bridge 58 a

A 45 5

Pond BM 100.79m 96.6m

12 60 28 32 EL LB 101.2m 10

14 62 T

r Roy BM 97.12m ack

al Oak Grand Union Canal 16 LB (PH) 64 El Sub Sta 1 The Firs NS EU7 FLOR GARDE

EL BM 107 106.1m YEW TREE 4 El 25 1 E

H 3 68 Sub IL 11 .95m L 119 Sta Pp 15

2

1 EU1 3

11kV 18 4 19 20

MP .25 106.4m 6 14 TCB 72 Roundabout 21 El Sub

Flore 1a 87.2m Sta EL 1 Pond 1 2

94.2m 2 116.4m SUTTON ACRE 3 2 1 3

Russell EL 7

118.6m Surgery 1 10 a

24 1 7 2 3 1 1 Hollandstone 4

11kV R 125 11kV 12 i EL EL se 7 A 5 BM 102.72m 5

Grange Farm 1 2

11 87.8m 4 1a E

87.8m 3 Farm Culvert Pond Dodmoor Canal N

FLORE HILL STREET 1b

18

2 15 30 5 EL 2 5

25 9

Globe Farm 102.1m THE GREEN 11kV 11 4

BLISS LA

2 2a 24 8 5a

Mile Stone and Rail Bridge 8 SUTTON Globe Farm

122.5m 11

27 11 0 19 1 13 NE

Stone Track 29 Hollandstone

1 15 MEADOW LA

12

LANE 31 KING'S LANE 14 1 Approximate Location of 2b 6 Lilac FARM

Cottage BM 123.01 SPRINGFIELD 6 42 Farm Crossing SPRING Highgrove Flore CL A 2 1 House A 45

45 1 BRICKETTS 19

Proposed Office Blocks BM The Lilacs Farm 76

m Grove 5

16

5

87.79m 1

House 20

4 15

Cattle Grid 14 23

96.9m 2 12

T 4

9 1 Tennis 3 HE A 85.3m Court 2 84.7m

V 3 ENU 6

122.5m 5 47

E

24 11 0

6 6

LANE 1 4 1

86.9m Green 15 1 BM 85.07m Issues Ch 0W Pond Hotel M 1 Country 9 Meadow Rosea 29 WATLI 2 3 THE ORCHARD

CHAPEL Farm

ROMAN ROAD 6 THORNTON CLOSE 8

O 32

Dodford Wharf N 34 8

R Flore 10

G STREET 2 51 DNANCE ROAD Gas Cylinder

Ashlawn Cott 15 SL Farm Filling Depot 66

3

Oaklands LB

4

4

1 3 8

The Conyngham 12 2 5

16 Nene View

Living Stones Glebe The Vicarage 35

Ashley 12 Hollandstone Farm 2

89.3m 17 House 1 Spring

MP .75 Weedon Lay-by 4 Spring Junction The Bungalow Bungalows Pond House 23 Church

The 55 119.8m 1 A 45 37 77.1m ck Tra

12

41 83.8m

Tel Ex Flore C of E NETHER L 41

9 ANE EU10 4

1 Pond 45

1 4

A 45 Primary School 72 Greyleys Pond

43 SPRING LANE SUTTON 43 1 59

Dodford A 5 Pond 46

e 46 A 45 M 1 Th galows Flore C of E Pond NETHER LANE

Wharf un B B B

74

RI RI

6 6 48

Tel Controlled 48

C

Farm C 54 WATLING 54 92.1m 84.3m

61 K K 15

Ex STREET

ETTS LANE ETTS

ETTS LANE ETTS Issues 42 42

44 School 11 44

Grand Union Canal 9

47 Weedon 47 Towing 76 EU9 Hollandstone Farm Junction Langhley Lay-by s THE AVENU Track D Pa 85.7m

STREET E rain 1 Post 1 Posts R LANE t NETHE BM h 91.55m New PH ILL The House Posts Pond Lodge on House 77.3m FLORE H 117.9m 119.2m Weed Works 97.1m Issues Gas Governor 103.1m Lake Little Nearton HIGH STREET A 45 BM 109.65m Flore House Track

29 25 35

112.4m Foot 35 82.2m

68 23 17

66a

b 66a

ridge 66

Gas 66 HIGH Globe Hotel

St STREET

at Lake 60

Governor 60

3 ion House

5 5

5 Issues Path 2

El CLOSE Bank 2 81.8m 0 0 4

SOR 4

Strawberry 12 36 Depot Sub ND 36

Depot Fields 10 WI

6 6 2

Sta 5 PH 2 Gas Gov Pond

6 3 Path

14 PO

2 1 28 22

30 30 20 Magpie 20 Road Weedon Police House 15 47 18 Tennis House 1 16 THE 7 44 1 to 6 Court

1 6 3 Red House

2

5

GRE Wharf 5 6 6 Brodie Lodge

8 8

1

1

Depot 1 1

6 6

1 1 Y Playing Field

S 19 1

5

45 0 5

22 8 1 8 4 Trelawny 12 York Crossroads

4 12

Depot 12 Track

38 Hotel All Saints' Church 8 8

0

3 2 2

4 2

4 Rid 15 4

2 HARMANS WAY 14 BM 84.67m

21 e

2 12 2

5 2 Flore Park 80.3m 10 30 A 45

4 REGENC 6 2 28 TCB 10 12 16 SE 0

Y CLO 1 EU12 26 5 1 19 10 CLOSE

16 9

7 FB

7

EQUESTRIAN WAY 10 3 8

12 18 3 3

26 26

1

17 ETON 1 to to

t 15 t o o 20

11 20

4

34 1 34 o o

1 7 Issues 8 t 8 8 t 8 Upper Heyford

5 The Croft

2 Boat 2

CAVALRY HILL 19 Track 11 11

4 York Ride SE Yard

3 2 5 6

ORDNANCE ROAD 6 38 38

3 4 3 BM

CLO

8 8

4 4

o 1 o

2 21 82.59m

0 t t 0 0

47 47 4 4 1 1 MP Drain Farm Bridge

9 Path

18 81.3m

CESTER EU11

36 20 8

2 27

o o 45 8 45

38 18

18a 14 GLOU 31

35 t t 35 35

33 33

24 24

23 to to 23 23 25 6 HARMANS WAY Garage

2

40

15 11

15 1

9 77.2m

19 Ordnance 77.1m 7 25

0 IEL ROAD 42 R

1 House LITTLE P

25

2

1 2

1 1 1 1

1 1

2 5 5

3 to to The existing A45 8 18 12 16 2 20 CAVALRY FIELDS 10 35 85.3m 4 Redlynch CAMPBELL CLOSE LANCERS WAY Manor

2 M 1

8 Farm 18 1

12 24 81.3m A 45

53 45 TCB

2 FB Piers LB

15 9 FB

The Mill Farm BM 81.50m 11 rack

T 83.4m 80.5m EU9 Pond Fir Lea Foot Bridge 82.2m MAIN ROAD Chy 79.2m Water Bollards Foxwood El Sub Sta 75 (Units 1 to 11) Path (um) 88.6m BM 88.21m 15 Works 77 79 86 87 Ebenezer House

78 Gantry 88.8m 75.3m 3

1 9 5 14 FG10 Watl KT4 The Old Depot ing S FUSILIER WAY 1 WB 81.8m 3 The East Lodge treet Grand Union Canal A 45 70 5 To BM Depot 7 BM 85.65m wi ROMAN ROA Issues n 79.21m g Pa Dovecote Water 87.1m 77.3m t El Sub Sta h Farm D Water STREET Park View Water Hill Farm 2 BRIDGE Issues 79.5m 4 Home Water Pond 79.2m 6 Farm BRIDGE ST BM 81.11m 8 86.0m River Nene Tip 6 3 (dis) 1 4 4a Tip The White (disused) FB Gates Issues The Flats

ETL Issues Flats The Close BRIDGE STREET Issues River Nene

8 6 16 Issues 30 20 17

32 18 8 3 14 12 2 Upper Heyford The Stables A 45 24 81.1m 77.6m

26 Foot Bridge 42 36

Pond

RIVERSIDE DRIVE 1

Pond 23

4 52

54 The

46 Path (um)

4 Lay-by

19 11 Pond FB

15 17 27 Barn

Drain WEEDON

Track

58 25

8

56 50

Weedon Bec 4 21 Pond

EU12

River Nene 19 Coach House

18 60 33 Weir 80.2m Heyford Mill BRI Pump House Hipwells D GE

in 22

16 STREET a BROOKSIDE 70

r The 8

D

Allotment Bungalow

2

20 12 Riverside Brooklyn NENESIDE CLOSE Gardens Track

Court KT2 7

11 15 Allotment Gardens FG16 5 FB Weir

3

Church A

75 bat 2 t oir 103 Plume of Track Issues

1 Feathers Well Ho Middle 91 (PH) 1

FG5 KS5 43a 89 5 2 85 67 Issues ORDNANCE ROAD 6 1b 1a 1 Path (um) FG16 71 4 (Track) 51 13b 13a 11b 11a 9 12

63 3 TCB 8

83.6m 59 80.2m

4

53 33 7 4 SL KS5 41 6 6

1

15 1 83.1m

3 3

WEST STREET 43 10 GP 14 FG10 1

37 14 a

5

10 5

16

WAY

80.4m 17

14

7 7

20

22

24 L

BM 80.99m 30 ay-b

5 5

36

40

54

9 9

48 80.6m 80.7m y

38a 38 WEST 42

4 18

1

2 2 2 PH

PO KT1

4 6 56

12 KS5 River 54

2

15 6 15 15 BM 82.37m 6a 20 1 Works

4 Path (um)

17 17 46 FG4 CHURCH St Peter's Church 2 17 CLOSE 21 22 42

Community 11 15 3

9 Weedon 40 Nene 5 55

21 KINGS PARK 55 KS12

KT6 41 Centre U Ref Ch 41 BUSWELL 24 Drain

Primary School 30

1 21

10 10 7

15 6 2 11 2 FG15

39

STREET 39 1 19

19 82.5m

29 29

25 25

31

25 31 23 23

2

8 FG14

28 WAY 90.2m

21a 21a

21 11 21 6 22 29 82.4m

STREET Grand

12 12 'S Union Spring 12 3 15 1 EW Canal YN 1 N 1 1 T FG11 1 CR R KS11 Tr 11 5 Path (Um) A BILLING 80.8m

ac OFT 3 1 M 30

k Club SCHOOL PL

MANOR ST ST MARY'S

WA 35 3a Issues

2 12 2 12 14 WAY 1 12 Y 5

2 Pond Jetties

2 m) 8 8

12

5a 12 Pond 7

Recreation Ground 7 u

20 2 5d

3 3

12 Stanton's Barn 14

SOUTH STREET14

8

18 18 7

7 Camping Site FG5 Garage

WAY ROA Path ( 2 PETER'S 14 41 ST Cemetery Pond 14 2 The 5 FG8

BM KS5

D Hollies

30 30

15

27 79.77m

15 El

11

19 QUEEN'S PARK 1 Sub 80.0m

17 90.1m 91.5m Sta Ponds

ack 1 86.6m r

Path Drain 27 36

36 The Path (um) T

15

14

7 Vicarage Spring 11 110 FG9 118 78 100 20 76 Whitehall KT3

Towing FG8 46 FG1 Cottage Path (um) 28 Pine Reach Hillside KT4 View T rack

146 High-house Wharf Pump BM 72.50m 16 56 83.4m Pond House 71.9m 12 38 86 BM 90.75m FG4 36 66 92 5 156 10 Track 95.3m Upper Weedon 140 Flore Lane CES CLOSE 6 86.0m 2 134 Wharf

N NEW CROFT 132 KS11 Whitehall Farm 24 39

PRI

2 2 4 25 Wharf TITHE ROAD 37 Sluice Simon's

Upper Weedon 6 House 49 23 Weedon Wharf

4 BM 93.09m Overflow Cottage

Tk Grand Union Canal Ponds 59

The Firs Track 7

LB 15

1 11a Surgery MP Ingledell 14 11 55 81 GP

Sinks 12 Cottage TCB 1 69 A 5 Stowehill Wharf 90.6m Pond

1 Track STREET 69 Sewage Works 72.1m BM Kingfishers 22 O River Nene DUKELANDS QUEEN 99.3m Stowehill Pond KT1 98.75m AK S The Grange 3

ft Path (um)

3 House Foot Bridge

4 2 7 cro Track

l NEW STREET T l 2a Spring 9 River Nene

Hi Tk 8

6 FG11

The Bungalow A 5

9 The Old Priory 90.3m Water Spring Pond FB Track 11

15 Lower Weedon

Track 15 17 11 98.0m Builder's FG1 The Grange KT6 Path (um)

Yard 16

Tra

1 Water KS3 8

ET 39 72 OSE 24 c Track L 5 k 9 Spring

C Pond TITHE STRE Pond ROAD LM 1 The 43 River Nene 2 8 Canal HO

NEW

Firs 28 26 Priory 17 BM 90.69m 16 KS10 8 FG13 38 Court 97.4m Sewage Works Union

Issues FG18 FG2 BM 73.07m 72.8m 102.6m

1 OAK STREET Towing Path 9 22 25

4 Grand

Track 50 BM 105.04m Chapmans Close KS14 Porch 41 Stowehill

52 83.4m House 76 58b 58a QUEEN STREET 35 97.1m Sluice

78 56 104.9m 37 Towing Path Wharf

15

39 Stowehill Home 27

0

70 2 31 4 Farm House 68 21 Cottage

The Narrow Boat 64 60

Grand Union Canal (PH) 38 75 Sinks

102.4m 12 Tank I 01/09/15/ SMT Earthworks Amended Ch1500-Ch2500 MFH SL

GP 36

1

QUEEN STREET 67 Butterfields 59

49

b

47 57

67 OAKLANDS 24

55 Dairy 51 Upper Weedon LB RK 30 H 29/04/15 SMT Access Tracks Amended. Other Minor Amendments MFH SL

Farm A 48

Upper Weedon 63 7 Stowehill NOR P Pit SL Swingbridge House 22 MA

(disused) 97.1m 1 G 10/03/15 SMT Access Tracks Removed. Green Bridge Widened MFH SL

Greenacres 6 KS2

Pit 75 Issues

(disused) The Bungalow MP

71

16 12 Track 18 Fernhollow KS5 F 19/12/14 SMT Various Scheme Amendments MFH SL Farm

FG11

Heyford Lodge Bridge E 03/11/14 SMT A5 Roundabout and Carriageway Amended MFH SL

102.9m MANOR PARK 1 FG2 5 Lodge

MP .75 9 D 21/08/14 SMT A5 to A45 Link Route Amended

112.5m 2 1

1 Pump

22 1 House 12 KS14 23 Earthworks amended Ch1600 to Ch2500 MFH SL 2 15 85.5m Issues

ROMAN ROAD 27

5

KS21 2 C 24/07/14 SMT Balancing Ponds Added MFH SL

31

21

Hall The Rectory 8 17

KS19 43

Spring 19

21 CHURCH LANE

11 1

15

23 53 B 01/05/14 SMT Vertical Alignment Amended Ch1700 - Ch2600 MFH MH 49 White 16 9 House 1

BM 106.69m 55 St Peter and Allotment Gardens St Paul's Church White A 29/01/14 SMT Original MFH SL Benns

Hall 5 Orchard Sinks 6 2 7 Sports Field 8 1 102.8m 5 4 7

4 KS19

Tennis Path (um) 14

39 CHUR 3 LK Court 4 Path 15 REV DATE BY DESCRIPTION CHK APD 26

WA Pavilion

2

Cemetery CH 0 12a 14

STREET a ANOR 15

41 Tennis 1 KS18 110.3m

8 M

73.9m

35 Court

24 2 1 2

126.6m 1

1

3

3 1 10

1

c

FB 0

7 22 d

2 11 T

22 16 1

4

EE 10b 29 25 11 1

Drain 5 DRAWING STATUS:

TR 19 Issues S Track 9 BROOKSIDE PLACE

9 Spring 3

10

1

2

10a 2 2 Spring 3 MIDDLE KS1 7 WEEDON RO 1

Posts 12 FOR INFORMATION ONLY The Issues 16 PARSONS CL Spring

5 Old Sun 5a

KS16 1 BM 75.50m 2 4 (PH) AD WATERY LANE

5 10

12 4 5 8

132.4m 5

CHURCH STREET 3a KS6 6

74.1m 16 106.8m 15 8

1

8 11 6 3

Issues 30 Club 27 3 8 9 Bliss 2 Charity Aided

Reservoir School 6 Pond

(covered) 25

1a 4 a 1 24 PH SL 28 122.8m PO

War Meml 4 26 1 Heyford

24 20 18

16 2 14 Cottage a

Spring 10 8

2 1 2 KD14 TCB KS6 Denbrook KS7 GP 5 5 76.7m 1 2

11

29 6 BM 76.66m 6 WAY 14

LD 139.2m 8 27 IE

0 1 73.7m Track FG11 GP KS17 The Green 2 6 WAKEF 10 1 Baptist Church 12 9 14

Pond 15 1 1 ETL The Green

24 3 ROAD

28

17 2

2

1 Mile Stone 2 6 PROJECT:

Lay-by

BM 112.89m 9 Halls 4

0 11 75.5m 134.8m Hall RO

BE

3

8

1 8 RT 3

S 2

FIELD 3

5

FARTHINGSTONE ROAD 7 52

36 1

1a 9 Pond

Towing Path 11 KS10 Grand Union Canal The Pound 15 Foot Bridge 1

FE1 Nether b

FG3 16

1

1 A45 Daventry Development Link 2 41

BM 138.74m El Sub Sta 5 1

3 9 4 Stowehill Tunnel 3

Heyford Posts 5

HILL 7 36 141.9m 42 SIDE ROAD 7 6 35 HILLSIDE ROAD The Hillcrest Cottage 48

Pound 2

22

4 1 2

148.0m 4 7 25 20

15

39 21

151.7m 19 29

1 14 60

3 2 73.7m

3 12

9 OAD

2 43 R

9 Foot Bridge 117.9m 2 10

5 1 2

152.3m T 38 LOSE 6 Weedon Hill 2 HE TITLE: 7 C a 2 7 6

PEAK

Track 5

1

7 4 Pond 23 2 11

WINSTON 7

8 1

2

15

11 59 2 Base Plan This map is reproduced from Ordnance Survey material with CLO 1 154.0m SE 78

Weedon Hill 6

3

0 1 15 HILLSIDE CRESCENT 1 Tanborough 2 1

Path 1

GP 11 15

Oaktreehill Barn 1

9 12

6 17 the permission of Ordnance Survey on behalf of the Controller FURNACE LANE 14

86

AVENUE

71 N 2

6 4

BM 154.37m 2

Weedon Hill Farm 11 1 ESTER 26a W

NT of Her Majesty's Stationery Office Crown copyright. 2 1 © 4 59 5 6 Spring CE S

Pillar 30

RE 17

18 3 1 FE C 4 BM 162.32m 2

Track 88

7

5 ROL T 158.5m 81 N Unauthorised reproduction infringes Crown copyright and may 8 5 E

28 5 24

C BM 76.60m 1

9 FB RES 28a

30 16 FE C Sewage SCALE @ A0 CHECKED: APPROVED:

14

ROL Works lead to prosecution or civil proceedings. SL 2 22 KS8 SOUTH VIEW

18 36 19

MP 68

15 1/5000 MFH SL

11

2

1

2

9

53 51

41 79.7m DESIGN/DRAWN: DATE: Spring Cattle Grid ROAD Northamptonshire County Council: Licence No. 100019331. Posts 39 SMT 29/01/14 L:\GROWTH\HIGHWAY DESIGN\2015-16\A45 DAVENTRY DEVELOPMENT LINK\AUTOCAD\BASE PLAN AND LONG SECTIONS DWG NO 03I & 04I.DWG L:\GROWTH\HIGHWAY DESIGN\2015-16\A45 DAVENTRY DEVELOPMENT LINK\AUTOCAD\BASE PLAN AND LONG SECTIONS DWG NO 03I & 04I.DWG Track Pond

Published 2014. Greena Track cre KD12 PROJECT No: DRAWING No: REV: s

156.5m 114.4m Burnham Fern Hollow Cottage 77.2m Spring Coal Yard S1265 R1999/03 I CAD File: CAD File: