Involuntary Resettlement Due Diligence Report

Document stage: Draft for consultation Project Number: 42486-018 August 2018

INDIA: Urban Services Improvement Program – Additional Financing – Subproject Group Water Supply Scheme of Town Saikheda, Salichauka and Chichli, District

Package No: MPUSIP-5F

Prepared by Urban Development and Environment Department, Bhopal, Madhya Pradesh for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 18 August 2018)

Currency unit = Indian rupee (₹) ₹1.00 = $0.014 1.00 = ₹69.80

ABBREVIATIONS

ADB - Asian Development Bank FGD - Focus group discussion GOI - Government of KL - Kilo Liter GOMP - Government of Madhya Pradesh KM - Kilometer LARR - Land Acquisition, Rehabilitation and Resettlement LPCD - Liter per Capita per Day MDPE - Medium Density Polyethylene pipes MFI - multilateral financial institutions MLD - Million Liter per Day MPUDC - Madhya Pradesh Urban Development Company MPUSIP - Madhya Pradesh Urban Services Improvement NOC - No Objection Certificate OHT - Over Head Tank O&M - operation and maintenance PMU - Program Management Unit PWD - Public works Department R&R - Resettlement and Rehabilitation RF - Resettlement Framework RP - Resettlement Plan ROW - Right of Way RWGM - Raw water gravity main SPS - Safeguard Policy Statement SPU - safeguard policy update ULBs - Urban Local Bodies WRD - Water Resource Department WSS - Water Supply Scheme WTP - Water Treatment Plant

NOTE

In this report, "$" refers to United States dollars.

This draft Involuntary Resettlement Due Diligence Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of the use” section of this website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

CONTENTS Pages

I. INTRODUCTION 1 A. Background 1 B. Project Description 1 C. Scope of this Report 2 II. POLICY FRAMEWORK, AND ENTITLEMENTS 2 III. SUBPROJECT DESCRIPTION 3 A. Description about Subproject Towns 3 B. Existing Water Supply System 3 C. Components of Proposed Group Water Supply Scheme 5 IV. FIELD WORK AND PUBLIC CONSULTATION 6 A. Outline of Fieldwork 6 B. Field work Report 7 C. Public Consultation 7 V. LAND AVAILABILITY AND INVOLUNTARY RESETTLEMENT IMPACTS 14 VI. BUDGET 18 VII. CONCLUSIONS AND RECOMMENDATIONS 18 A. Summary and Conclusions 18

APPENDICES:

1: DETAILS OF LAND OWNERSHIP FOR EACH WATER WORKS COMPONENT TO BE CONSTRUCTED. 28 2: STAKEHOLDER CONSULTATION PHOTOGRAPH AND LIST OF PARTICIPANTS 31 3: INVOLUNTARY RESETTLEMENT SCREENING CHECKLISTS 41 4: LAND RECORDS 44 5: CERTIFICATE OF CHIEF MUNICIPAL OFFICER-SAIKHEDA REGARDING STATUS OF THE LAND PROPOSED FOR SUBPROJECT COMPONENTS 51 6: SITE VISIT REPORT (TOWN SAIKHEDA) OF CDO, PIU- 53 7: NUMBER OF WATER SUPPLY CONNECTION IN THE SUBPROJECT TOWN 56

FIGURES:

Figure 1: Key Plan of Saikheda, Salichauka and Chichli Group Water Supply Scheme 20 Figure 2: Google map Showing Location of Saikheda, Salichauka and Chichli with Transmission alignment 21 Figure 3: Location of proposed components on Google map 22 Figure 4: Photographs of Proposed Transmission main and Distribution Network 26

TABLES:

Table 1: Detail about Existing Water Supply System 3 Table 2: Detail about Existing Water Supply System 4

Table 3: Detail about Existing Water Supply System 4 Table 4: Details of proposed CWFM 5 Table 5: Summary of proposed Distribution Network 6 Table 6: Summary of Consultation with Stakeholders 9 Table 7: Proposed WS Components in subproject towns Saikheda, Salichauka and Chichli and their involuntary resettlement impact 15

I. INTRODUCTION

A. Background

1. Government of Madhya Pradesh (GoMP) with a sector project loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘The Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency (IA) and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project. A project management unit (PMU) created under MPUDC is implementing MPUSIP.

2. The Resettlement Framework (RF) for MPUSIP outlines the objectives, policy principles and procedures for land acquisition, if any, compensation and other assistance measures for Displaced Persons1 (DPs)/Affected Persons (APs), if any.

3. An entitlement matrix, consistent with the existing norms and guidelines of the country and the state government, and ADB’s Safeguard Policy Statement has been prepared to cover losses identified in this Project. The matrix recognizes that the lack of title/customary rights recognized under law will not be a bar to entitlement and has special provisions for non-titled persons.

4. Madhya Pradesh Urban Services Improvement Program (MPUSIP) proposed to be funded by Asian Development Bank (ADB) envisages provision of sustainable water services to 128 tier II towns in the State. Some of these towns will also be provided with comprehensive sewerage and storm water management services. The State Urban Development and Environment Department is the Executing Agency while the Madhya Pradesh Urban Development Company (MPUDC) Limited is the implementing agency for the Program.

B. Project Description

5. MPUSIP. As per revised procurement plan, MPUSIP’s physical components include (a) improvements to water supply scheme in 69 subproject towns, and (b) sewage collection and treatment services proposed in four (4) identified towns namely Saikheda, Sanawad, Anjad and Badwaha under tranche I while in tranche II – water supply scheme in 59 subproject towns and sewage collection and treatment services proposed in seven towns namely Sanchi, Dhamnod, Mandsaur, Jabalpur (part-II), Maihar, Khajuraho and Rajnagar. The project also includes an institutional strengthening component and a project management and administrative support component. The objective of the proposed improvements in subproject towns is to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The project proposals envisage providing 100% coverage of population with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The main objectives of the project are as follows:

(i) Supplying pure drinking water. (ii) Promote sustainable measures to increase potable water supply to the population. (iii) Water supply through future sustainable source developments.

1 In the context of involuntary resettlement, displaced persons are those who are physically displaced (relocation, loss of residential land, or loss of shelter) and/or economically displaced (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas. It covers them whether such losses and involuntary restrictions are full or partial, permanent or temporary. 2

(iv) Water supply through improvements of safe yield of existing water sources. (v) Water supply through improvements to water treatment works. (vi) Drinking water supply contributes towards a sustainable regional development. (vii) To improve the current state of the water cycle of subproject towns through improvements in the separate components of the water supply system in investment program.

C. Scope of this Report

6. This draft involuntary resettlement (IR) due diligence report (DDR) is prepared for the proposed group water supply scheme for the towns of Saikheda, Salichauka and Chichli in district Narsinghpur. The proposed subproject components include: construction of water intakes, water treatment plant (WTP), storage reservoirs (elevated), new pipe laying or pipe replacement (usually along public roads). The proposed subproject will focus on metered water supply for domestic, institutional and commercial users, including water resource identification and treatment, water storage tanks, distribution pipes and metered connections to each household in project towns covering a total population of 39,368 as per Census of India-2011. The estimated population for the design year 2048 is 69,912. All the municipal wards of the subproject towns are covered under the Project.

7. A due diligence process was conducted to examine the land acquisition and resettlement issues in detail, in line with ADB SPS 2009. This report describes the findings and provides copies of relevant documents, resolutions, minutes of meetings and photographs. This land acquisition and resettlement due diligence report needs to be read along with the Resettlement Framework prepared for MPUSIP.

8. Although, IR impacts will be reconfirmed again after completion of detailed design and detailed measurement surveys (DMS) which will be conducted based on the detailed design by Design Build & Operate (DBO) Contractor before initiation of civil works during implementation.2 The final IR report will be reviewed and disclosed on website of urban local body (ULB), IA and ADB. No construction work will commence before the updated social safeguard document for the package is reviewed and approved by ADB and compensation to affected persons, if any, paid. The IA is responsible to hand over the project lands/sites to the contractor which should be free from all encumbrances.

II. POLICY FRAMEWORK, AND ENTITLEMENTS

9. The resettlement framework (RF) set out the objectives, principles, eligibility criteria and entitlement for APs based on ADB SPS, 2009 and LARR, 2013. GoMP adopted LARR 2013 as well as national and state laws for protection of street vendors. Until recently, all activities related to rehabilitation and resettlement in the State of MP had been based on the Madhya Pradesh Resettlement and Rehabilitation Policy, 2002 (MPRR) and National Rehabilitation and

2 Detailed measurement survey will be jointly conducted by safeguards personnel of project implementation unit, consultants and contractors prior to implementation at each site/stretch of alignment. Report (IR DDR / RP for different sites/stretches will be prepared and submitted to ADB for approval; prior payment of compensation to permanent and/or temporarily impacted persons is mandatory before start of civil work at each site/alignment stretch. Social safeguards document for the package will be updated by PMC in coordination with DBO contractor.

3 resettlement Policy, 2007 (NRRP-2007). GoMP adopted LARR 2013 on 3rd October, 2014 with some specifications for operationalizing its implementation in the state. Details of policies are in Resettlement Framework for MPUSIP.

III. SUBPROJECT DESCRIPTION

A. Description about Subproject Towns

10. Subproject Area: The proposed subproject is a group water supply scheme for three towns namely Saikheda, Salichauka and Chichli and description of these towns are as follows:

11. Subproject Town Saikheda: This is a small town in Narsimhapur District of Madhya Pradesh State. It belongs to . It is located 69 KM towards west from District headquarters-Narsimhapur. It is a tehsil headquarter. Saikheda is surrounded by Udaipura Tehsil towards north, Babai Chichli Tehsil towards south, Bankhedi & Pipariya Tehsil towards west and Tendukhera on east. Pipariya, Sohagpur, Raisen, Rehli etc. are some of the nearby towns of Saikheda. The population of Saikheda Nagar Parishad as per 2011 census is 11,327. As per 2011 Census, the sex ratio (Female Population pa 1000 Male Population) of the town is 920 and literate population is 78.3%.

12. Subproject Town Salichauka: Salichauka is newly delineated Nagar Parishad in Tehsil of Narsimhapur District which cover six villages namely, Keshla, Saori, Mohpa, Babai Kalan (also named as Salichauka), Babai khurd and Khairva. The periphery of this Nagar Parishad is 15 km away from Tehsil Headquarter Gadarwara and 69 km away from its District Headquarter Narsimhapur. The economy of the town is based on mainly agricultural products and supporting trade and commerce activities. The Population of Salichauka Nagar Parishad as per 2011 census is 13,816. As per 2011 Census, the sex ratio (Female Population pa 1000 Male Population) of the town is 916 and literacy rate of Salichauka has been 72%.

13. Subproject Town Chichli: Chichli is a Nagar Parishad (NP) in Narsimhapur district of Madhya Pradesh. Chichli is geographically located at 78.42 0C East Longitude and 22.83 0C North Latitude at a height of 349 m above Mean Sea Level (MSL). The Nagar Parishad is spread over 2.5 sq. Km. As per census data of 2011, the total population of the town is 14,225. As per 2011 Census, the sex ratio (Female Population pa 1000 Male Population) of the town is 927 and literate population of Chichli Nagar Parishad is 66%.

B. Existing Water Supply System

14. Subproject Town Saikheda: Presently the main source for drinking water supply in the town is through tube wells located in the various parts of the town. There are total seven tube wells; out of which six are running throughout the year. There is one overhead tank (OHT) of 180 KL capacity in Saikheda. Water from two tube wells is stored in this OHT and then distributed to three wards of the town. An additional nine wards are getting water through direct supply from tube wells. The remaining three wards are getting water from hand pumps.

Table 1: Detail about Existing Water Supply System S. No. Ground Source Particulars Details 1. No. of Intake well No 2. WTP No 3. No. of Tube wells 7 nos. (6 nos. working) 4. No. of Hand pumps 20 nos. working

4

5. No. of tankers 02 nos. working 6. No. of ELSRs 1 no. in working condition 7. No. of Sump No 8. No. of pump 7 nos., 10 HP to 12 HP 9. Per Capita Consumption 49 LPCD Source: Nagar Parishad – Saikheda

15. The water is being supplied to the town after preliminary treatment of chlorination. There is one overhead tank of capacity 180 KL and its condition is structurally good. Water is supplied to three wards (5, 6 & 7) through this OHT. Water is stored in overhead tank through pumping from tube wells. Saikheda Nagar Parishad supplies approximately 0.74 ML of water per day from all sources. The duration and frequency of water supply is one hour per day. The per capita supply of water is 49 LPCD.

16. Subproject Town Salichauka: Water supply system in Salichauka is entirely dependent on ground water source through tube wells. There is absence of dedicated water supply scheme as on today. Water supply to town is served by 11 tube wells located in majority of the wards except in ward no. 13 and ward no. 15. All 11 tube wells are in running condition.

Table 2: Detail about Existing Water Supply System S. No. Ground Source Particulars Details 1. No. of Intake well - 2. No. of Tube wells 11 nos., working 3. No. of Hand pumps 54 nos., 50 nos. working 4. No. of tankers 03 nos. 5. No. of ELSRs 05 nos., working 6. No. of Sump 00 nos. 7. No. of Dug well 00 nos. 7. No. of pump 11 nos. working 8. Per Capita Supply 36 LPCD Source: Nagar Parishad Salichauka

17. Salichauka Nagar Parishad supplies approximately 7.00 lakh litre of water per day. The duration and frequency of water supply is one hour every day. The per capita supply of water is 36 LPCD.

18. Subproject Town Chichli: Chichli is facing a shortage of water. The water problem becomes very acute during the year of scanty rainfall. At present, 0.76 ML per day of water is supplied through tube wells. There are six tube wells that runs throughout the year. Water is stored in overhead tanks of total capacity 550 KL and distributed to the town. In some areas water is distributed directly by pumping from tube wells. Water supply in town is supported by 85 nos. of operational handpumps.

Table 3: Detail about Existing Water Supply System S. No. Ground Source Particulars Details 1. No. of Intake well No 2. No. of Tube wells 6 nos. working 3. No. of Hand pumps 85 nos. working 4. No. of tankers 03 nos. working 5. No. of ELSRs 4nos. 2 nos. working, rest of 2 nos. under Construction but held up last three year by PHE department. 5

S. No. Ground Source Particulars Details 6. No. of Sump No 7. No. of pump 6 nos. 5 HP to 7 HP Source: Nagar Parishad Chichli

C. Components of Proposed Group Water Supply Scheme

19. The primary objectives of the proposed water supply subproject include:

(i) service improvements to achieve safe and sustainable water services both in terms of services to residents and cost recovery (ii) conservation of precious water resources. The project envisages providing 100 percent coverage of population with continuous, pressurized and safe drinking water services and achieving progressively increase cost recovery by expanding the coverage and increasing operating efficiency.

20. Proposed Source of water supply for the group water scheme of three towns is . Proposed components of the group water supply scheme are as follows:

(i) Intake Well: On the bank of Narmada river, R.C.C. intake well of 6m diameter and 17m height is proposed to collect and lift water up to treatment works. (ii) Raw Water Rising Main: The proposed raw water rising main is 3,989 m long, 300 mm dia. pipeline of DI K9 from proposed Intake well to proposed WTP. (iii) Raw Water Pump: Two nos. vertical turbine type pumps with 100% standby are proposed. The discharge of each pump is 4.74 mld or 59.85 LPS and head is 40.12 meter to cater to water supply needs for the intermediate stage up to year 2033. (iv) Water Treatment Plant (WTP): There is no water treatment plant (WTP) in any one of the subproject towns. A common WTP for all three towns having capacity of 5.91 MLD considering 22 Hrs. of pumping has been proposed for the ultimate year of 2048 at Bamhori Khurd under ward number 13 at Saikheda. (v) Clear Water Sump well at new WTP: A 200 KL of sump well with 45 minutes of detention time is proposed at WTP for storing clear water after treatment from WTP. (vi) Clear Water Pump: At WTP and at Sump: Provision of 2 numbers of centrifugal pumps having discharge 4.54 MLD or 57.32 LPS and head of 39.00 m with suitable motor is proposed with 100 percent standby (1 no. working and one stand bye) including suction pipe, control panel, cable and all necessary accessories. (vii) Clear Water Feeder Main (CWFM): CWFM with total length of 57,158m (8767m for Saikheda, 24647m for Salichauka and 23744m for town Chichli) of 100-300 mm dia DI- K9 pipes is proposed to distribute clear water in the towns.

Table 4: Details of proposed CWFM Diameter (mm) Length (m) Pipe Material 100 12930 DI K-9 150 1188 DI K-9 200 20622 DI K-9 250 19432 DI K-9 300 2986 DI K-9 TOTAL 57,158 m Source: DPR (viii) Intermediate Pumping Station (IPS):

6

(a) IPS at junction point (elevation 330.33 m) with a sump well of 70 KL capacity having 45m detention time is proposed to pump water from sump well to different OHTs of Salichauka at Saikheda. (b) IPS at junction point (elevation 355.49 m) a sump well of capacity 40 KL is proposed at Chichli considering 45 minutes detention time.

(ix) Over Head Tanks:

(a) Saikheda: Two OHTs having capacity of 220 KL and 50 KL has been proposed (b) Salichauka: Existing 5 OHTs will be utilized for the proposed project. (c) Chichli: Two OHTs having capacity of 300 KL and 50 KL has been proposed

(x) Distribution Network: The total length of the proposed network is around 93,260 m of diameter 90 mm to 250 mm HDPE PN 10 pipe. The minimum size of pipeline taken is 110 mm as per CPHEEO manual for population less than 50,000.

Table 5: Summary of proposed Distribution Network Diameter (mm) Length (m) Pipe Material 90 24478 HDPE PN10 110 49228 HDPE PN10 140 6228 HDPE PN10 160 2743 HDPE PN10 180 2774 HDPE PN10 200 4200 HDPE PN10 250 3609 HDPE PN10 TOTAL 93,260 m Source: DPR

(xi) Water Supply in litre per capita per day (LPCD): It is proposed to supply 135 LPCD for town Saikheda while remaining two towns namely Salichauka and Chichli will be supplied with 70 LPCD. Town Saikheda NP has been proposed into three water supply zones while town Salichauka and Chichli has been proposed in five water supply zones each.

21. Proposed subproject components are given on Figure 1 while these proposed components on google earth map with coordinates are depicted in Figure 2 & 3.

IV. FIELD WORK AND PUBLIC CONSULTATION

22. This involuntary resettlement document is prepared in consultation with stakeholders including local residents, beneficiaries/consumer, and Urban Local Body (ULB) officials/representatives. Informal consultations and focus group discussions (FGDs) were conducted to seek feedback from local people and other important stakeholders on the proposed development interventions, perceived impacts and mitigation measures and their participation.

A. Outline of Fieldwork 7

23. During the visit, a field inspection of proposed subproject facility locations and pipeline alignments that had been identified was undertaken. These included field visit to the identified sites and alignments and stakeholder consultations. The entire land requirement for the proposed subproject component will be fulfilled by government land. The details of selected lands for subproject components are given in the Appendix-1 and 4.

B. Field work Report

24. We met the concerned ULB officials, public representatives; stakeholders and prominent residents of subproject towns Saikheda, Salichauka and Chichli to collect data / information for proposed subproject during various discussions/meetings (refer to Appendix 2).

(i) During the meeting and discussion, we have gathered the present situation of water supply in the town and the requirement of the stakeholders. Based on present water supply arrangements and gaps arrived are well documented. (ii) With the ULB authorities, we visited all the possible water supply sources and identified locations for all components of proposed water supply scheme. (iii) We have studied all the options of possible water supply source, its dependability, quality assurance of source available and the distance from the town. (iv) Water from the selected source was collected and tested in Bhopal Municipal Corporation Laboratory at Bhopal. Also test report is obtained for designing purpose. (v) We have ensured the water security from the concerned department like WRD etc. such that best-chosen water source is made available to ULB for the purpose of water supply scheme. (vi) We have contacted revenue authorities to ensure the land availability, secured in the ownership of government departments such as ULB or Revenue Department, Govt. of Madhya Pradesh etc. for construction of WTP and service reservoirs. (vii) After getting all the required data for the preparation of DPR, we have mobilized the survey team for the survey work. Focusing road survey for water supply distribution system. Based on elevation differences in individual command areas and required pressure conditions at lines near households.

C. Public Consultation

25. Extensive consultations were undertaken with key stakeholders in line with ADB's requirements pertaining to environment and social considerations. Focus group discussion (FGD) conducted near proposed sites of Intake Well, Water Treatment Plant, Over Head Tank etc. The outcome of focused group discussion with stakeholders in towns and with line departments are presented below. Stakeholders included persons involved in infrastructure provision of basic services like water, wastewater & allied services, other engineers and workers of Local Body, Forest department, Water Resource Department (WRD), PWD, NH, District Administration etc., which are representatives of various departments that can foresee problems pre & post execution of work and hold discussion with public for various matters. (refer to Appendix 2). The following were the outcomes of consultations:

(i) The consultations helped to identify the felt needs /concerns and apprehensions of the communities related to the project and priorities of concerned stakeholders. (ii) Consultations revealed that people are aware of the problems of the existing water supply system in the town and are willing to cooperate in the proposed project.

8

(iii) Consultations with the key stakeholders revealed that existing water supply system is in inadequate and unreliable, so improvement is required, and local inhabitant will definitely and fully accept the project. (iv) The ULB Officials had apprehensions regarding the project whether it will be a financial burden to the Nagar Parishad. The NP does not have capacity or resource to be party in sharing the loan repayment.

26. The major stakeholders targeted during consultations are:

(i) The municipalities, its elected members and staff who will be required to oversee the construction of the distribution networks and WTP as well as be directly responsible for the maintenance of the installations. (ii) Local residents who will take initiative to connect their houses with the water distribution line. (iii) Local business people and traders (iv) The opinion makers are intimately acquainted with and well regarded by the community. They need to be enlisted in spreading environmental awareness within the community as well as in conveying the benefits of the project.

9

Table 6: Summary of Consultation with Stakeholders

Date Location No. of Participants Topics Discussed Issues Participants 30th At Total=08 Elected • Present drinking water supply • Participants welcome the initiative taken by the May Parishad M=05 representatives, source and its condition MPUSIP for the preparation of DPR for Water Supply 2018 Hall, F=03 Chairperson of ULB, • Need of improvement of the of town. and ULB Officials Subprojec present situation • Need for the project was discussed with the participants. t Town • Briefing on project objectives probable implementation • Discussed the problems related to existing water Saikheda procedures supply in the town Saikheda. • Potential positive and negative • Awareness drive in community is utmost required to

impacts due to project get connection and pay the tariff implementation • Socio economic profile of the town was discussed. • Land use and area to be • There is an immediate need of improving the present covered under the project water works infrastructure in the Saikheda area of subproject town. • Operation and maintenance of the facilities developed under the project and community participation; • The official from revenue department gave consent of speedy allotment for required land for project. • Timely road restoration 30th Ward -15 T=17 Local residents • Briefing on project objectives • Participants knew about the proposed project. On May Sardar F=13 probable implementation learning about the project, they expressed that they 2018 Vallabh M=04 procedures were happy that the entire community would be Bhai • Potential positive and negative benefited from the upgraded water supply. Ward, impacts due to project • Slum dwellers showed willingness to take water Subprojec implementation connections but demanded relaxation in user charges. t Town • Experiences sharing on - • People were briefed about the complaint redress Saikheda livelihood activities, mechanism. Resettlement and Rehabilitation, women empowerment, tribal development, health, education, convergence with existing government social security schemes etc. • Grievance Redress procedures 10

Date Location No. of Participants Topics Discussed Issues Participants 30th Local Total= 08, Local Shopkeepers • Knowledge of project • Participants had heard about the proposed project and May Shopkeep F=1, • Present water supply situation: welcomed it. 2018 ers, M=7 only half an hour of supply • Women are facing many problems in fetching water Subprojec alternate day for hours. t Town • Drinking water user charge • Some participants did not have water connections. Saikheda • All households including women were happy to learn about the proposed project. • Possibility of exempting the poor and vulnerable from user charge payment.

30th Mahua Total= 09, Local Residents • Briefed about Subproject • Participants had heard about the proposed project and May Khera, F=3, welcomed it. 2018 Subprojec M=6 t Town Saikheda

30th At Total=08 Elected • Present drinking water supply • Chairman welcomed the initiative taken by the May Parishad M=06 representatives and source and its condition MPUSIP for the preparation of DPR for Water Supply 2018 Hall, F=02 Chairperson of ULB • Need of improvement of the of different towns of Madhya Pradesh. Subprojec present situation • The need for the project was discussed with the Chairman of the Nagar Parishad. t Town • Briefing on project objectives probable implementation • Chairman and CMO discussed the problems in the Salichauk procedures Salichauka related to Drinking Water Supply. a • Potential positive and negative • The socio-economic profile of the both the towns was impacts due to project explained by the Chairman. implementation • There is an immediate need of improving the present • Land use and area to be water works infrastructure in the town. Chairman covered under the project explained the problematic areas (low pressure zones, Electricity supply duration) related to the water supply. • The prime concern and apprehension of the ULB Chairman regarding the project was whether it will be a financial burden on the Nagar Parishad. 11

Date Location No. of Participants Topics Discussed Issues Participants • Operation and maintenance of the facilities developed under the project and community participation; • The official from revenue department gave consent of speedy allotment for required land for project.

30th At Ward Total= 20, Women • Knowledge of project • Women had heard about the proposed project and May No. 1, F=20, • Present water supply situation: welcomed it as women are facing many problems in 2018 Ambedkar M=0 only half an hours of supply fetching water for hours. Ward, alternate day • Some participants did not have water connections. The women were happy to learn about the proposed Subprojec • Drinking water user charge project. t Town • Possibility of exempting the poor and vulnerable from Salichauk user charge payment. a • Slum area must be given relaxation for connection and water use • Timely road restoration 30th At Ward Total= 13, Local Residents • Briefing on project objectives • None of the participants knew about the proposed May No. 6, F=13, probable implementation project. On learning about the project, they 2018 Subprojec M=0 procedures expressed that they were happy that the entire t Town • Potential positive and negative community would be benefited from the upgraded impacts due to project water supply. Salichauk implementation • Slum dwellers showed willingness to take water a • Experiences sharing on - connections but demanded relaxation in user charges. livelihood activities, • People were briefed about the complaint redress

Resettlement and mechanism. Rehabilitation, women empowerment, tribal development, health, education, convergence with existing government social security schemes etc. • Grievance Redress procedures

12

Date Location No. of Participants Topics Discussed Issues Participants 30th At Total=10 Elected • Present drinking water supply • The Chairman of the ULB expressed need for the May Parishad M=07 representatives and source and its condition project and willingness to take it up; 2018 Hall, F=03 Chairperson of ULB • Need of improvement of the • The prime concern and apprehension of the ULB Subprojec present situation Chairman regarding the project was whether it will be a financial burden on the Nagar Parishad. t Town • Briefing on project objectives probable implementation • Operation and maintenance of the facilities developed Chichli procedures under the project and community participation; • Potential positive and negative • Possibility of exempting the poor and vulnerable from

impacts due to project user charge payment. implementation • The prime concern and apprehension of the ULB • Land use and area to be Chairman regarding the project was whether it will be covered under the project a financial burden on the Nagar Parishad. • • Operation and maintenance of the facilities developed under the project and community participation; • The official from revenue department gave consent of speedy allotment for required land for project. 30th At Ward Total= 18, Women • Knowledge of project • Women had heard about the proposed project and May No. 10, F=18, • Present water supply situation: welcomed it as women are facing many problems in 2018 SC Ward, M=0 only half an hours of supply fetching water for hours. Subprojec alternate day • Some participants did not have water connections. The women were happy to learn about the proposed t Town • Drinking water user charge project. Chichli • Possibility of exempting the poor and vulnerable from user charge payment.

30th Subprojec Total= 8, Local Shopkeepers • Briefing on project objectives • None of the participants knew about the proposed May t Town F=03, probable implementation project. On learning about the project, they 2018 Chichli M=05 procedures expressed that they were happy that the entire • Potential positive and negative community would be benefited from the upgraded impacts due to project water supply. implementation • Slum dwellers showed willingness to take water • Experiences sharing on - connections but demanded relaxation in user charges. livelihood activities, • People were briefed about the complaint redress Resettlement and mechanism. Rehabilitation, women empowerment, tribal 13

Date Location No. of Participants Topics Discussed Issues Participants development, health, education, convergence with existing government social security schemes etc. • Grievance Redress procedures

14

V. LAND AVAILABILITY AND INVOLUNTARY RESETTLEMENT IMPACTS

27. No land acquisition or resettlement impacts are anticipated for any of the proposed civil works for group water supply subproject in three towns. Community Development Officer (CDO) of PIU-Jabalpur has visited the proposed sites to study the IR impacts (refer to Appendix 2, 4 and 6).

28. For group water scheme to Saikheda, Salichauka and Chichli towns, raw water abstraction will be undertaken from Narmada River. The Intake well is proposed on Narmada River near village Kelkachh. Land is available for proposed Intake well and belongs to Water Resource Department (WRD). Land is without any settlement/ squatter /cultivation.

29. The identified land at Saikheda for water treatment plant (WTP) (6.50 MLD) has been in the possession of revenue department from many years and was not acquired in anticipation of ADB funded MPUSIP. This was confirmed with the revenue department during visit on 28.03.17. Land proposed for WTP is located at ward number 13, Bamhori Khurd (Khasra number 141) and have total area of 2.77 ha (Appendix 4). It is vacant land free from any encroachments/any type of cultivation and not under any use. The land transfer from revenue department to ULB is under process.

30. 200 KL capacity of clear water sump is proposed at WTP premises for storing clear water after treatment from WTP. The land belongs to revenue department.

31. The proposed raw water rising main is 3,989 m long 300 mm dia. DI K9 pipeline from proposed intake well to proposed WTP and will be laid within the available right of way (RoW) of the existing PWD road. The Clear water feeder main of total length 57,158 m from WTP to Saikheda, from Saikheda to Salichauka, and from Salichauka to Chichli will be laid within existing RoW of PWD road while within the Saikheda, Salichauka and Chichli nagar parishads it will be laid within the available RoW of nagar parishad/ULB roads. The pipelines will not cross any private land along the alignments. Permission/no objection will be required from the PWD for laying of pipelines within their road ROWs.

32. Two OHTs of 220 KL and 50 KL capacities are proposed for Saikheda in ward no.15 and ward no. 2 respectively. Land proposed for these two OHTs are having area of 0.36ha and 0.405ha at Khasra number 158 and Khasra no. 422/1 respectively (refer to page 3 & 4 of 7 of Appendix 4). Two OHTs of 300 KL and 50 KL capacities are proposed for Chichli in ward no.10 and ward no. 12 respectively (refer to Appendix 4). The lands identified for proposed OHTs are vacant, free from any encroachments and are in possession of revenue department. Land transfer from revenue department to ULB is required for the construction of all proposed OHTs.

33. Two intermediate pumping station (IPS) are also proposed under the group water supply scheme. First one is proposed at junction point at Saikheda (elevation 330.33 m) with a sump well of 70 KL capacity having 45m detention time to pump water from sump well to different OHTs of Salichauka. The second IPS is proposed at Chichli at junction point (elevation 355.49 m) with sump well of capacity 40 KL considering 45 minutes detention time. IPS for Salichauka has been proposed at Saikheda. Proposed site for IPS is common with OHT-2 (50 KL) at Saikheda and its Khasra number is 422/1 which belongs to revenue department under government of MP. Khasra number Khasra No. 159/1 is identified for second IPS proposed at Chichli.

15

34. Pipe laying activity on roads in the most congested market areas and densely built-up areas has been carefully planned to avoid IR impacts including temporary economic impacts to hawkers, shops and businesses.

35. Measures will be taken to minimize excavation, disturbance to pedestrians and traffic and avoid income loss to businesses, while minimizing road reconstruction costs. Temporary impacts to traffic/access to shops and residences due to digging of pits for pipe laying are possible during construction; however, these will be mitigated by ensuring access to properties through provision of pedestrian planks, provision of adequate signage, and careful traffic management. Mobile hawkers will be assisted to move to places vacant nearby or to other side of the road, to ensure their earnings are not affected. No income loss is anticipated.

36. House Service connections: It is proposed to provide 100 percent house service connections tapping from a distribution main/sub-main including one tapping saddles, elbows, service pipe from tapping point to the chamber near property boundary or inside the property boundary. The work shall include excavation, road restoration, etc. Currently, there are water connections at subproject towns Saikheda (587), Salichauka (1523) and Chichli (1382) and these three project towns have a total of around 3492 household connections. Projected households’ connections for subproject towns will be 8048. This will account for 2,240, 2,934 and 2,874 house service connections for Saikheda, Salichauka and Chichli respectively.

37. New distribution network includes laying of 93,260 m pipeline. These pipelines are proposed to be laid underground within the existing RoW of public roads belonging to Nagar Parishad. Proposed pipe diameters to be laid range between 90 mm to 250 mm depending on the width of the roads that vary between 3 to 15 m. Distribution lines are proposed on one sides/ centre of the road depending up on availability of space where road widths are small.

38. Civil works in the project include linear excavation for laying pipes within the roads, placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4 m – 0.7 m wide and 0.8 to 1 m depth. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works. Proposed distribution pipe-laying on roads in most part of the town will not have any permanent or temporary IR impact.

39. Laying of transmission mains and distribution network pipelines in the project area has been carefully planned to minimize disturbance to pedestrians and traffic and avoid income loss to businesses. Potential temporary impacts to traffic/access to shops and residences due to digging and excavation for pipe laying are possible during construction; however, these will be mitigated by ensuring access to properties through provision of pedestrian planks, provision of adequate signage, and careful traffic management.

Table 7: Proposed WS Components in subproject towns Saikheda, Salichauka and Chichli and their involuntary resettlement impact Components Capacity Unit Length Land IR Impact (No.) ownership

Water Supply

1 Intake well on 6.50 MLD 1 Water The Intake well proposed on Narmada Narmada River Resource river. Land belongs to WRD. land is without any settlement/ squatter /cultivation or other. Therefore, no IR impact anticipated. refer Appendix -1.

16

Components Capacity Unit Length Land IR Impact (No.) ownership

Department (WRD)

2 Water 6.50 MLD 1 Government WTP of capacity 6.50 MLD Treatment land/ proposed at Saikheda, Bamhori Khurd, Plant (WTP) Revenue Ward no.13. Land belongs to Revenue Department department and is without any settlement/ squatter /cultivation or other. Therefore, no IR impact anticipated. refer Appendix -1 And 4 for khasra details and map.

3 Clear Water 200 KL 1 Government The Proposed Clear Water sump at sump land/ head works is proposed within WTP Revenue complex. Land belonging to revenue Department Department. Therefore, no IR impact anticipated. refer Appendix -1 And 4

4 Overhead 220 KL and 4 Government Proposed OHTs (2 in number) at ward Tanks (OHTs) 50 Kl at land/ no 15 and 2 respectively at town Saikheda Revenue Saikheda and 2 nos OHTs at ward no 10 and 12 at Chichli town. and 300KL Department Land belongs to Revenue and 50KL department. land is without any at Chichli settlement/ squatter /cultivation or others, Therefore, no IR impact anticipated. refer Appendix -1 And 4

5 Guard cum 3 Government The facility will be accommodated operator house land (WRD within the premised of intake well and at Intake well and revenue WTP. It is free of any settlement /

and WTP with department squatter / cultivation or other uses, boundary wall lands) Therefore, no IR impact anticipated. and gate

6 Intermediate 2 At Saikheda- Land has been identified for IPS at Pumping Government Saikheda (Khasra No. 422/1). While Station (IPS) land/ IPS for Chichli (Khasra No. 159/1), Land belongs to Revenue at Saikheda for Revenue Department and land is without any Salichauka Department settlement/ squatter /cultivation or and IPS at others, Therefore, no IR impact

Chichli anticipated. refer Appendix -1 And 4 At Chincli- Revenue Department

7 Transmission Government Rising mains of 3989 m from intake to main (3989 m land/PWD WTP along Kuccha road right of way. +57229 m) Transmission main (feeder main) of 57158 m passes through unused 17

Components Capacity Unit Length Land IR Impact (No.) ownership

/vacant/barren public lands /Road RoW of PWD.

8 Chemical 1 Government Will be accommodated within the WTP Storage and land/Revenue premises. dosing pump Department house

9 Distribution 93260 Road RoW, Pipelines pass through existing road Pipeline m nagar RoWs (government roads). Temporary parishad impacts on traffic/access to properties HDPE pipe - roads of anticipated in some places. Contractor 93260 m project towns to provide signages indicating available (public land) alternate access route to minimize traffic disruptions. Contractor will have to ensure access to shops and residences as per EMP provisions.

10 Household 8048 - During construction period, access to connections properties likely to be temporarily with domestic affected. Contractor will have to ensure metres access as per EMP provisions.

40. Mitigation: The sites or locations for the subproject components have been selected carefully to avoid and minimize involuntary resettlement impacts. The following mitigation measures are proposed to avoid and/or reduce the impacts during linear pipe works:

(i) Provide prior advanced notice (minimum one week) to community along the construction stretch. Distribute information on project and grievance redress mechanism, (ii) Maintain access to avoid disturbance to residents and businesses by providing planks and leaving spaces for businesses and residents to maintain access, (iii) Manage traffic flows as per traffic management plan prepared by the contractor in coordination with local authorities and communities, (iv) Limit the amount of time of open trenches, and complete works quickly where business activities are located, (v) Avoid full street closure to extent possible, (vi) Contractors shall provide employment opportunity to the local residents and particularly woman where possible, and (vii) Contractors shall assist vendors and hawkers in shifting to alternative locations, if required.

41. This subproject does not have any IR impact as there will be no physical or economic displacement. The subproject will have no adverse land acquisition impacts as the subproject components are proposed on public lands belonging to revenue department. Identified sites does not belong to tribal community and no adverse IP impacts are envisaged. Transmission and

18 distribution pipeline carry raw and clear water will traverse only through right of way (RoW) of the government roads. Keeping in view, no IR impacts are likely to be envisaged; an involuntary resettlement screening checklist is prepared and attached in Appendix 3. Accordingly, the subproject is classified under ‘Category C’ for involuntary resettlement under ADB’s SPS-2009.

VI. BUDGET

42. A budgetary provision is made for costs likely to be incurred during implementation of subproject.

Table 8: Budget Sl. Description Target group Estimated cost Source of fund No. 1 Consultation and information persons of INR 450,000 Included in disclosure and awareness drive project subproject cost through IEC tools area 2 Connection drive and GRM Project INR 300,000 Included in area subproject cost 3 Tanker supply for areas where Project area INR 150,000 Included in existing water supply disrupted subproject cost during construction 4 15% contingencies INR 135,000 Included in subproject cost 4 Total INR 10,35,000

VII. CONCLUSIONS AND RECOMMENDATIONS

A. Summary and Conclusions

43. No negative IR impacts are assessed at identified sites for sub-project components, as adequate vacant land is available for the proposed facilities, within the compounds of government lands.

44. For these towns, water will be sourced from Narmada river. The requirement of town is very less in comparison with the dam storage. Office of the CMO has applied to WRD to get NoC and construction of intake well as well as for abstraction of water from the river. The proposed site for WTP is at Bamhori Khurd under Ward no. 13 at Saikheda. Proposed site is owned by Revenue department. Intake well will be constructed on Narmada river near village Kelkachh and NoC for that is under approval from WRD. For linear components (pipe laying) are proposed along government road ROWs. Temporary disruption to road users, pedestrians and community members will be avoided in the most congested zones of subproject towns with proper traffic management with the help of local police and officials. Safety measures are taken during construction time to avoid injuries. Inconveniences to the public are mitigated during construction by the contractor through simple measures such as provision of planks for pedestrian access to shops with effective traffic management. The subproject is classified as “Category C” for Involuntary Resettlement (IR) impact as per ADB’s Safeguard Policy Statement (SPS), 2009.

45. The DDR needs to be updated with the following information:

19

(i) NoC is required from WRD to abstract water from Narmada river (in progress). (ii) Transfer of proposed land WRD, WTP, OHTs and IPSs in the name of respective ULBs (in progress). (iii) NoC is required from PWD to lay the transmission / distribution line. (iv) In addition to the above, in order to improve the quality of consultations, local community organizers will be appointed for Project under package; record of consultations held with local communities and other stakeholders to be included in updated/final DDR. (v) Reflection of design or site changes proposed, if any

20

Figure 1: Key Plan of Saikheda, Salichauka and Chichli Group Water Supply Scheme

21

Figure 2: Google map Showing Location of Saikheda, Salichauka and Chichli with Transmission alignment

22

Figure 3: Location of proposed components on Google map

Site location of Intake well

23

Site location of Intake well and WTP

Site location of proposed OHT-1 for Saikheda at Ward No.15

24

Site location of proposed OHT-2 (50 KL) for Saikheda at Ward No. 2

Site location of proposed OHT-1 for Chichli at Ward No.10

25

Site location of proposed OHT-2 for Chichli at Ward No.12

Site location of proposed Clear water Sump for Chichli at Ward No.13

26

Figure 4: Photographs of Proposed Transmission main and Distribution Network

Raw Water Pumping Main Alignment Photographs

Clear Water Feeder Main from Saikheda to Salichauka

Distriburtion Network 27

28 Appendix 1

Appendix 1: Details of Land Ownership for each Water Works Component to be constructed.

Site Khasra No Ownership of Land Component Location and Area Status of NOC Proposed (Khasra No)

Khasra No. On Narmada ULB has applied for the Intake Well Government /WRD 8/1 / Area River NOC from WRD 2.634 ha

Khasra Govt Of M.P. ULB has applied for the Bamhori Khurd, No. 141 / WTP (Revenue NOC from revenue At Ward No. 13 Area Department) department 2.77 ha

Khasra No. OHT-1 Near Barhata ULB has applied for the Govt Of MP (Revenue 158 / Area (220 KL) at School NOC from revenue Department) 0.36 ha Saikheda At Ward No. 15 department

Appendix 1 29

Near Kherapati Mata Mandir at OHT-2 (50 Ward No. 2, KL) and Saikheda (As per Khasra No. IPS cum ULB has applied for the site visit report of Govt Of MP (Revenue 422/1 / Area sump well NOC from revenue CDO, PIU- Department) 0.405 ha at department Jabalpur, Khasra Saikheda Detail of Ward No. 2 Proposed site to be collected.

OHT (330 Khasra No. ULB has applied for the Ward No. 10 Govt Of MP (Revenue KL) at 246 / Area NOC from revenue Department) Chichli 3.124 ha department

OHT (50 Khasra No. ULB has applied for the Govt Of MP (Revenue KL) at Ward No. 12 369/1 / Area NOC from revenue Department) Chichli 11.328 ha department

30 Appendix 1

At Junction Point IPS with (elevation Clear water Khasra No. ULB has applied for the 355.49m) at Govt Of MP (Revenue Sump well 159/1 / Area NOC from revenue Chichli Department) (40 KL) at 0.91 ha department

Chichli

Appendix 2 31

Appendix 2: Stakeholder Consultation Photograph and List of Participants

Subpoject WSS Town Saikheda: Meeting with ULB and Elected Representatives

32 Appendix 2

Subpoject WSS Town Saikheda: Consultation with Local Residents of Ward No. 15

Appendix 2 33

Subpoject WSS Town Saikheda: Consultation with Local Shopkeepers

Subpoject WSS Town Saikheda: Consultation at WTP enroute habitation Mahua Khera / Kherua

34 Appendix 2

Appendix 2 35

Subpoject WSS Town Salichauka: Meeting with ULB and Elected Representatives

Subpoject WSS Town Salichauka: Meeting with Local Residents Ward No. 1, Ambedkar Ward

36 Appendix 2

Subpoject WSS Town Salichauka: Meeting with Local Residents Ward No. 9 Appendix 2 37

38 Appendix 2

Subpoject WSS Town Chichli: Meeting with ULB and Elected Representatives

Subpoject WSS Town Chichli: Meeting with local residents SC Ward No. 10 Appendix 2 39

40 Appendix 2

Subpoject WSS Town Chichli: Meeting with local Shopkeepers

Appendix 3 41

Appendix 3: Involuntary Resettlement Screening Checklists

A. Introduction

1. Each project/subproject/component needs to be screen for any involuntary resettlement impacts which will occur or already occurred. This screening determines the necessary action to be done by the project team.

B. Information on project/subproject/component:

a. District/ Administrative Name: Narsinghapur b. Location: (i) Saikheda (72 Kms), (ii) Salichauka (70 kms.) and Chichli (62 kms.) away from District headquarter Narsinghpur c. Civil work dates (proposed): Not yet proposed d. Technical Description: Group Water Supply Scheme of three towns namely Saikheda, Salichauka and Chichli. The scheme involves construction of intake well on Narmada River, WTP in Saikheda, Pumping water from intake wells to WTP, laying of Clear water rising main of length 57158 m from WTP to the OHTs, Construction of 2 no of Overhead tank (OHT) of size 220 KL and 50 KL for Saikheda NP, Construction of 2 no of OHT of size 300 KL and 50 KL for Chichli NP and further distribution to end users by various distribution networks through gravitation.

1. Screening Questions for Involuntary Resettlement Impact Below is the initial screening for involuntary resettlement impacts and due diligence exercise. Both permanent and temporary impacts must be considered and reported in the screening process.

Involuntary Resettlement Yes No Not Reason Impacts known Will the project include any physical ✓ Construction of Intake well, WTP, construction work? transmission mains, OHTs and distribution network pipelines proposed

Does the proposed activity include ✓ No upgrading or rehabilitation of existing physical facilities? Will there be permanent land ✓ Only government revenue land sites acquisition? selected for project facilities Will it require temporary land ✓ acquisition? Is the ownership status and current ✓ All identified sites belong to either WRD usage of the land known? or revenue department and free of any structures and encumbrances. Are there any non-titled people who ✓ Lands/corridors identified are vacant live or earn their livelihood at the site and free from any Non-titled people. or within the corridor of impact (COI) / Right of Way (ROW)? Will there be loss of housing? ✓ Will there be loss of agricultural ✓ plots?

42 Appendix 3

Involuntary Resettlement Yes No Not Reason Impacts known Will there be losses of crops, trees, ✓ During laying of distribution lines in and fixed assets (i.e. fences, pumps, congested lanes temporary etc.)? arrangements will be made, pipeline will be located in unused Government lands alongside the existing roads and can be constructed without causing disturbance to houses and commercial establishments. Will there be loss of businesses or ✓ During laying of distribution lines in enterprises? congested lanes temporary arrangements will be made, pipeline will be located in unused government lands alongside the existing roads (within RoW) and can be constructed without causing disturbance to houses and commercial establishments. Will there be loss of incomes and ✓ Any disruption of public facilities or livelihoods? services will be taken care of during excavation. Grievance redress cell will be formed ward wise to settle the grievances early. Will people lose access to facilities, ✓ services, or natural resources? Will any social or economic activities ✓ be affected by land use-related changes? Will people lose access to natural ✓ resources, or common property resources, or communal facilities and/or services? If land use is changed will it have an ✓ adverse impact on social and economic activities? Will access to land and resources ✓ own communally or by the state be restricted? Are any of the affected persons (AP) ✓ from indigenous or ethnic minority groups?

2. Involuntary Resettlement Impact

1. After reviewing the answers above, EA/ Safeguard Team confirms that the proposed subsection/ section/ subproject/component (tick as appropriate): [ N ] Has involuntary resettlement (IR) impact, a resettlement plan (or corrective action plan) is required [✓ ] Has No IR impact, no resettlement plan is required.

Appendix 3 43

Prepared By: LN Malviya Infra Projects Pvt. Verified by: Ltd. Signature: Signature: Name: Position: Name: Vipin Kumar

Position:

Date: Date:

44 Appendix 4

Appendix 4: Land Records

Khasra Map of proposed intake well

(page 1 of 7)

Note: Khasra is land record maintained by the state government, which depicts for each land parcel, the parcel number, ownership, area and landuse. The Khasra/land record is usually accompanied by a scaled map.

The above records depict that the proposed intake site is owned by government and has an area of 2.634 hectares, Khasra No of proposed intake site is 8/1.

Appendix 4 45

Land Records Khasra Details of Proposed WTP of Khasra Number 141 (page 2 of 7)

Note: Khasra is land record maintained by the state government, which depicts for each land parcel, the parcel number, ownership, area and land use. The Khasra/land record is usually accompanied by a scaled map.

The above records depict that the proposed WTP site is owned by government of Madhya Pradesh and has an area of 2.77 hectares. Khasra No of proposed site is 141.

46 Appendix 4

Land Records Proposed OHT-1 at Saikheda (page 3 of 7)

The above records depict that the proposed OHT-1 sites are owned by government of Madhya Pradesh and has an area of 0.036 and 0.040 hectares having Khasra No of 158 and 159 respectively.

Appendix 4 47

Land Records Proposed OHT-2 and IPS cum sump well at same Khasra 422/1, Saikheda (page 4 of 7)

The above records depict that the proposed OHT-2 and IPS cum sump well sites are owned by government of Madhya Pradesh and has an area of 0.405 hectares having Khasra No of 422/1.

48 Appendix 4

Land Records Khasra Details of Proposed OHTs for Chichli OHT-1 (page 5 of 7)

The above

records depict that the proposed OHT site is owned by government and has an area of 3.124 hectares having Khasra number of 246.

Appendix 4 49

Land Records Khasra Details of Proposed OHTs for Chichli OHT-2 (page 6 of 7)

The

above records depict that the proposed OHT site is owned by government and has an area of 11.328 hectares having Khasra number of 369/1

50 Appendix 4

Land Records Clear Water Sump at Chichli

(page 7 of 7)

The above records depict that the proposed Clear water sump site is owned by government and has an area of 0.91 hectares having Khasra number of 159/1.

Appendix 5 51

Appendix 5: Certificate of Chief Municipal Officer-Saikheda regarding Status of the Land Proposed for Subproject Components

52 Appendix 5

Certificate of Chief Municipal Officer-Chichli regarding Status of the Land Proposed for Subproject Components

English Translation:

It is certified by the Chief Municipality Officer-Chichali that land/site proposed for subproject components under WSS- Chichali are under possession of Municipality of town Chichli. Details about land proposed for subproject components is as follows:

1. proposed OHT site is owned by government and has an area of 3.124 hectares having Khasra number of 246. 2. proposed OHT site is owned by government and has an area of 11.328 hectares having Khasra number of 369/1. 3. proposed Clear water sump site is owned by government and has an area of 0.91 hectares having Khasra number of 159/1.

Appendix 6 53

Appendix 6: Site Visit Report (town Saikheda) of CDO, PIU-Jabalpur

English Translation:

On 30.03.2018, CDO at PIU-Jabalpur visited at proposed components of WSS town Saikheda and met local residents and elected ward councilors and briefed about the proposed project funded by ADB. One OHT is being proposed at ward number 15 Barheta. Consultation was conducted with local residents residing in and around of proposed location of OHT. Most of the residents under this belongs to OBC and SC community and they are briefed about proposed water supply project, benefits of safe drinking water and water borne disease. Weekly bazar was organized on each Wednesday at town Saikheda. Shopkeepers are also briefed about project. During visit, CDO met Shri Dwarka Prasad Chaukse, Chairman NP-Saikheda, Mr. RK Sharma, CMO-Saikheda, Mr. Durgesh Avadiya-Elderman, Mr Gaya Prasad Chaudhary Ward Councilor (WC) ward no. 10, Mr Hemant Kumar (WC) ward no. 15 , Shri Ashok Kushwaha (WC) ward no. 12, Shri Sourab Soni (WC) ward no. 11 and briefed about proposed Project.

54 Appendix 6

Site Visit Report (town Salichauka) of CDO, PIU-Jabalpur

English Translation:

CDO at PIU-Jabalpur visited town Salichauka on 30.03.2018. There are 15 wards under munacapility-Salichauka. Apart from distribution line, a clear water sump well is also proposed for WSS-Salichauka which is proposed at Saikhera. Consultation was conducted with local residents of Ambedekar ward of ward no. 1 and briefed about the ADB funded WSS Project. At Salichauka, these inhabitants are getting water directly from tube wells and these tube well dry up in the summer. Ms Chokhi Bai, ward councilor was present during consultation. A meeting was also organized with Shrimati Sangita Mehra, Chairman NP-Salichauka, Baini Singh Shailwar-Dy Chairman, Mr Amar raj patel Ward Councilor (WC) ward no. 7, Manish sharma-WC ward no. 8, Brij sharma-WC ward no. 15, Hiral Lal Ahirwar WC ward no. 9 and CMO-Salichauka.

Appendix 6 55

Site Visit Report (town Chichli) of CDO, PIU-Jabalpur

English Translation:

CDO at PIU-Jabalpur visited town Chichli on 30.03.2018. One OHT is being proposed at ward number 10. Consultation was conducted with local residents residing in and around of proposed location of OHT. Most of the residents under ward number 10 belongs to SC community and they are getting water directly from tube wells. Ward member, Ms Vanskar was present during meeting while Ms Babita Tamrakar, ward member of ward number 3 was also present during consultation. Apart from that a meeting was also conducted with shopkeepers and briefed about the proposed project. A meeting was also organized with Shrimati Sudha, Chairman NP-Chichli, Jitender Kaurav-Dy Chairman, Ram Naresh Ward Councilor (WC), Babita Tamrakar-WC, Sitavi Vanskar-WC, Shrimati Gayatri Dixit-WC and Shrimati Raj kumari Sahu, CMO-Chichli.

56 Appendix 7

Appendix 7: Number of Water Supply Connection in the Subproject Town