Resettlement Plan
August 2016
People’s Republic of China: Shaanxi Weinan Luyang Integrated Saline Land Management Project
Prepared by Weinan Municipal Government for the Asian Development Bank. This is an updated version of the resettlement plan originally posted in August 2015 available on http://www.adb.org/sites/default/files/project-document/174073/44037-014-rp-02.pdf.
CURRENCY EQUIVALENTS (as of 24 August 2016)
Currency unit – yuan (CNY) CNY1.00 = $0.1505 $1.00 = CNY6.6435
ABBREVIATIONS
AHH – affected household AP – affected person DMF – Design and Monitoring Framework EA – executing agency FGD – focus group discussion EMDP – ethnic minority development plan GEF – Global Environment Facility HH – household LAR – land acquisition and resettlement LNWP – Luyanghu National Wetland Park LEF – land-expropriated farmer M&E – monitoring and evaluation MIS – management information system PLG – project leading group PMC – project management consultant SGAP – social and gender action and participation plan SPG – Shaanxi provincial government SPS – Safeguard Policy Statement WFB – Weinan finance bureau WLMIDZMC – Weinan Luyanghu Modern Industry Development Zone Management Committee WMG – Weinan municipality government
NOTE In this report, "$" refers to US dollars.
This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
ADB Financed Project
Resettlement Plan Of
Shaanxi Weinan Luyang Integrated Saline Land Management Project
Weinan Project Management Office July 2016
This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
ENDORSEMENT LETTER
Note on this Update
L2980/G0331-PRC: Shaanxi Weinan Luyang Integrated Saline Land Management Project is supporting the WMG to implement environmental and social improvements in the Luyanghu area. The project comprises a five-year $100 million loan (L2980; 2013– 2018), a $2 million grant (G0331) from the Global Environment Facility (GEF), and a $350,000 technical assistance (TA8293) grant for wetland and water bird management.
The RP (2012 version) was formulated in accordance with the data of project feasibility study report (FSR). The updated RP (2015 version) was based in preliminary design, which optimized the design of the original scheme and changed the data of the original feasibility study scheme resulting from insufficient design precision at initial design stage. Meanwhile, as most impacts of land acquisition occur on saltpan and ditches, etc., the definition of land types was not accurately defined in the FSR, and some saline/alkaline lands were also counted as arable land. So in preliminary design change, the design institutes and project implementing agency further checked the types and quantity of acquired land, so as to ensure the accuracy of data, especially in Component 1 Saline Soil Rehabilitation. Moreover, it was found during implementation that there were several incorrect identification on project LAR impacts for several civil works packages under components 1 & 2 in the updated RP (2015 version). Therefore, there are further revisions to the contents and resettlement impact data in this updated RP (2016 version) based on the detailed design particularly in the packages of Component 1. Besides, the land for Tianlu-Tianjiao Connection has been pre-acquired in 2010 and exclude from the impact scope of the updated RP.
Because of the poor communication of information among units before, the RP was not been updated in time. After monitors went to the project sites to recheck and reconfirm, as of January 2016, comparing with the updated edition of August 2015, the permanently occupied land of the project rose from 2,587.8 to 5501.72 mu, and land acquisition types, data of affected population, etc., have changed. Affected cultivated land is increased from 692 mu to 2432.65 mu, whereas non-arable land such as wasteland and saline/alkaline land (salt pan) rose from 1,895.8 mu to 3067.07 mu.
This update mainly covers resettlement impacts, compensation and resettlement policies, restoration measures, organizational structure, resettlement budget, resettlement implementation schedule, etc.
Table 1 Overview of this update
Update Original RP (2012) Former RP(2015) Updated RP (2016) Remarks Identify the LAR impact of Component 1, 854 mu arable land 692 mu arable land 2432.65 mu arable Saline Soil and 1,733.8 mu and 1,895.8 mu land and 3069.07 mu Rehabilitation, non-arable land, non-arable land, non-arable land, Area of land more accurate for 2,587.8 mu land in 2,587.8 mu land in 5501.72 mu land in acquisition (mu) Component 2, total total total Flood Risk Management due to on-site survey
i
Update Original RP (2012) Former RP(2015) Updated RP (2016) Remarks
Impact of land APs increased 1,545 affected 1,455 affected 17,232 affected acquisition 15,777 persons persons in 365 persons in 343 persons in 3,698 Population/hous and AHs increased affected households affected households affected households ehold quantity 3,355 households
4,864.27 mu arable 3,820.17 mu arable 2,042.5 mu arable TLO decreased Area of land and 2,843.33 land and 2,843.33 land and not non- 4621 mu land for temporarily mu non-arable mu non-arable arable land, 2042.5 the Tianlu Lake occupied land land, 7,707.6 mu land, 6,663.5 mu mu land in total excavation doesn’t (mu) land in total land in total occupy land temporarily Demolishment 45 affected persons 45 affected persons 175 affected persons warehouse impacts of and 10 affected and 10 affected and 35 affected building for salt temporarily households with households with households with pan operation buildings 955 m2 temporary 955 m2 temporary 19326 m2 temporary building building building compensation cultivated land cultivated land cultivated land according to the rates compensation CNY compensation CNY compensation CNY local policies and 27000 yuan/mu, 27000 yuan/mu, 28500 yuan/mu in impact area salt pan salt pan Pucheng County, compensation CNY compensation CNY CNY 31063 yuan/mu 5000 yuan/mu 5000 yuan/mu in Fuping County, salt pan compensation CNY 5000 yuan/mu
resettlement CNY 87.963 million CNY 73.646 million CNY 105.281 million increased for the budget yuan yuan yuan physical impact and compensation rate
ii
Executive Summary E1. Project Background
1. Shaanxi Weinan Luyang Integrated Saline Land Management Project is located on the north bank of the Weihe River and within the Pucheng County in the eastern Weinan City of Guanzhong Plain of Shaanxi Province. The Project partially financed by ADB which consists of 4 Components: (1) Saline soils rehabilitation: including Rehabilitation of Luoxi drainage system and improved resilience to climate change of agro-ecosystems; (2) Flood risk management: improve flood storage capacity, prevent flood disaster, and ensure people’s life and property; (3) Wetland ecosystem conservation: improve and protect local wetland ecosystem; (4) Capacity development and project implementation support: institutional strengthening and project management support. The implementation period of the project is five years, that is, from 2013 to 2018. The total investment is 165 million dollars, of which, 100 million dollars is loan from ADB.
E2. Land Acquisition and Resettlement Scope
2. The land acquisition and resettlement (LAR) will affect 60 administrative villages, and 6 town/townships in Pucheng County and Fuping County, including a total of 3,698 households with 17,232 persons affected. Of the affected peoples, 3,663 households with 17,057 persons will be affected by land acquisition only and 35 households with 175 persons will be affected by both land acquisition and temporary building demolition. 3. A total of 5,507.72 mu of rural collective land will be permanently acquired, including 2,432.65 mu of cultivated land and 3,069.07 mu of waste land. 4. The Component will involve 19326.62 m2 of temporary building demolition, structures including brick concrete, brick-wood, earth wood housing, and simple house structures. All the building are non-residential utilized for warehouse or mirabilite production. 5. No enterprises and public institutions or shops are involved in acquisition and demolition. In addition, scattered trees, poles, wires, tombs, enclosures, water wells and other ground ancillary facilities will be affected. In the implementation area of the project, no ethnic minorities will be affected.
E3. Resettlement Principles and Entitlements
6. The resettlement plan (RP) is prepared according to the People’s Republic of China’s Land Administration Law (2004) and the related national, provincial, and municipal policies and regulations, as well as in compliance with ADB’s Safeguard Policy Statement (2009). On the basis of the above-mentioned regulatory and policy requirements and in consultation with local governments, the resettlement principles established for the project are that (i) land acquisition and involuntary resettlement should be avoided or minimized where feasible by developing and comparing a series of design alternatives; (ii) compensation be paid and other resettlement entitlements provided before physical or economic displacement. Compensation and entitlements provided must be adequate to allow those affected to at least maintain their pre-project standard of living, with the prospect of improvement; (iii) land temporarily occupied and the period for disruption are to be kept to a minimum; (iv) all affected persons (APs), titled and non-titled, and renters and/or contractors are to be taken into consideration; (v) RP should be prepared and implemented in accordance with state land rehabilitation policy, national economic and social development plans, and ADB’s SPS; (vi) all those affected will be adequately informed about
iii eligibility, compensation rates and standards, livelihood and income restoration plans, and project timing; (vii) RP should be coordinated with regional development, economic development, and environmental protection; (viii) practical and feasible measures should be formulated to restore the affected items; (ix) a preferential policy and assistance will be provided to vulnerable groups in such things as employment; and (x) close monitoring and timely actions will be carried out to identify and resolve any problems.
7. According to Notice on Average Standard of Unified Annual Output Value and Integrated Land Price on Land Acquisition of Shanxi Province (2010) and Notice on Land Acquisition and Implementation Scheme for Ecological Environment Project, Dredging and Rehabilitation of Main Desalination Drainage Channels in Weinan Luyanghu Modern Industries Development Zone (2014), the compensation rates for the rural collective land compensation and resettlement allowance are: CNY 28,500 yuan (Pucheng County) or CNY 31,063 yuan (Fuping County) per mu for farmland, and CNY 5,000 yuan for waste land with salt pans. The compensation rate for young crops is CNY 1,000 yuan (Pucheng County) or CNY 1,300 yuan (Fuping County) per mu.
8. According to Replacement Cost, the compensation standard of the buildings on the salt pans or along the channel is 500 yuan per square meter. People who work in salt pans can build new temporary buildings with original building materials.
E4. Resettlement and Restoration
9. Based on the socioeconomic survey and public participation on affected groups, APs’ livelihood restoration measures mainly include: (i) with monetary compensation, APs can be engaged in non-farming activities, such as transportation or small businesses or tourism services, etc., (ii) local governments will help APs to adjust agricultural planting structure, and provide planting instruction and technical trainings to expand greenhouse planting area, develop household level animal breeding industry, so as to improve economic incomes; (iii) during the project construction, the PMO will give priority to APs’ employment in the project and to provide nearby enterprises’ employment information, so as to increase their income sources; (iv) during APs’ livelihood restoration process, the PMO will organize APs to accept skill/technical trainings, and ensure all affected laborers receive at least one session of planting and/or non-farming technical training; and(v) local governments will help APs to apply for minimum living guarantee or pension insurance, to make poor families have guarantee on their future income.
E5. Information disclosure and Public participation
10. As a vital social activity for land acquisition, resettlement and compensation, information and consultation should be well-prepared with the aim to make every affected person acquainted with the significance, processes, appropriation, compensation, appeal and the way of settlement and problems existing in the project construction and consultation shall be carried on in advance.
11. From 15 May, 2012 to September 2014, six affected villages held villager representatives meetings to discuss and confirm the resettlement policy and compensation rates in the draft resettlement plan. The final RP will be printed and distributed to affected villages and posted on the website of ADB.
E6. Complaints and Grievances
12. During the preparation of the RP, public participation was encouraged. However,
iv there could be some unforeseen issues happening despite such process. In order to effectively settle the issues and ensure the smooth implementation of the Project construction and land acquisition, an effective and transparent channel for lodging complaints and grievance has been established. The aim is to respond to appeals of the APs timely and transparently. Grievances about the Project may be from collective LA. Correspondingly, the PMO, PIO, resettlement implementing agency, and the affected town governments and village committees will coordinate and handle grievances and appeals arising from resettlement. The APs may file appeals about any aspect of resettlement, including compensation rates. All complaints and their resolution will be recorded by the PMO.
E7. Organization Structure
13. The Executing Agency (EA) of the project is Weinan Municipal Government (WMG). The implementation agency is the Weinan Luyanghu Modern Industrial Development Zone Management Committee and the IA has set up an office, which is in charge of organizing, applying for ADB's loan, coordinating relocation, monitoring and inspecting the payment of usage of the compensation for land acquisition and resettlement. As the stakeholder and counterpart, WMG establish a leading group for land acquisition and resettlement (LAR) and an office to organize and implement the LAR.
E8. Budget for land acquisition and resettlement
14. All the cost incurred during land acquisition, relocation, and resettlement is included in the total budget of the project. In the general budget, direct resettlement costs include compensation for PLA, TLO, the demolition of temporary building and ground attachments, as well as planning and monitoring costs, administrative costs, training costs and contingencies, etc.
15. The general resettlement budget of the Project is CNY105.281 million yuan, including compensation for rural collective land acquisition of 56.777 million yuan or 53.93% of the budget, compensation fees for temporary land occupation of 5.310 million yuan or 5.04% of the budget, land taxes of 33.693 million yuan or 32.0% of the budget, indirect costs of 9.18 million yuan or 8.73% of the budget.
E9. Implementation Schedule
16. The project construction commenced in 2015, in order to properly resettle the affected persons and units, the land acquisition and resettlement activities should be conducted and be finished before the construction of the project. Land acquisition and housing demolition commenced in April 2014 and most of the resettlement activities will be completed by June 2017. However, rehabilitation of livelihoods may take longer to complete. The PMO has agreed to a set of supervision milestones with ADB to ensure timely and effective implementation of the resettlement activities.
E10. Monitoring and Evaluation
17. Details for both the internal and external monitoring and evaluation (M&E) are included in the RP. The PMO will submit an internal progress report semi-annually to ADB. Furthermore, the PMO engaged an independent external resettlement monitoring agency Shaanxi Kexin Consulting Company to undertake external monitoring of the RP implementation. A baseline study conducted before the LAR begins and the first monitoring report submitted in July 2015. After that and until project completion, semi-
v annual monitoring reports will be prepared and submitted for ADB’s review. After completion of the LAR, annual evaluation reports will be submitted to ADB for 2 years or longer if there are any remaining issues.
vi
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
ABBREVIATIONS
ADB Asian Development Bank AP Affected Person AH Affected Household DMF Design and monitoring framework EA Executing Agency FGD Focus group discussion FSR Feasibility Study Report GEF Global Environment Facility HH Household IA Implementation Agency LAR Land Acquisition and Resettlement LNWP Luyanghu National Wetland Park LEF land-expropriated farmer M&E monitoring and evaluation MIS management information system PAM project administration manual PIO project implementation office PLG project leading group PMC project management consultant PMO project management office PPMS project performance monitoring system PRC People’s Republic of China SGAP social and gender action and participation plan SPG Shaanxi provincial government SPS Safeguard Policy Statement TA technical assistance WFB Weinan finance bureau WLMIDZMC Weinan Luyanghu Modern Industry Development Zone Management Committee WMG Weinan municipality government
WEIGHTS AND MEASURES ha hectare km kilometer km2 square kilometer m meter m2 square meter m3 cubic meter m3/d cubic meter per day $(USD) US dollar CNY Renminbi YUAN currency unit
NOTES (i) The fiscal year of the Government of the People’s Republic of China and its agencies ends on 31 December. (ii) In this report, "$" refers to US dollars.
I
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
CONTENTS
Note on this Update ...... i Executive Summary ...... iii 1 PROJECT OVERVIEW ...... 1 1.1 Background and Description of the Project ...... 1 1.1.1 Background of the Project ...... 1 1.1.2 Components and Identification of Resettlement Impacts ...... 1 1.1.3 Summary of Resettlement Impacts ...... 4 1.2 Social and Economic Benefits ...... 4 1.3 Estimated Resettlement Budget and Implementation Plan ...... 5 2 PROJECT IMPACTS ...... 6 2.1 Types of Impacts ...... 6 2.2 Methodology and Procedures ...... 6 2.3 Permanent Land Acquisition ...... 6 2.4 Temporary Land Occupation ...... 14 2.5 Demolition of Rural Temporary Buildings ...... 14 2.6 Affected Vulnerable Groups ...... 15 2.7 Affected Women ...... 15 2.8 Affected Infrastructure and Ground Attachments ...... 16 3 SOCIOECONOMIC ANALYSIS OF AFFECTED AREA ...... 17 3.1 Socioeconomic Profile of the Project Area ...... 17 3.1.1 Socioeconomic Profile of the Affected Counties ...... 17 3.1.2 Socioeconomic Profile of the Affected Towns ...... 17 3.1.3 Socioeconomic Profile of the Affected Villages ...... 17 3.2 Socioeconomic Status of the Affected Population ...... 18 3.2.1 Analysis of Household and Female Population ...... 18 3.2.2 Age Structure ...... 18 3.2.3 Educational Level ...... 19 3.2.4 Housing Conditions ...... 19 3.2.5 Household Income and Expenditure ...... 19 3.3 Social and Gender Analysis ...... 20 4 LEGAL FRAMEWORK AND POLICIES ...... 21 4.1 Laws, Regulations and Policies Applicable to Resettlement ...... 21 4.2 Abstract of ADB Policies ...... 22 4.3 Main Differences between ADB Policy and PRC Laws ...... 24 4.4 Cut-Off Date of Compensation ...... 25 4.5 Compensation Rates ...... 25 4.5.1 Compensation Rates for Acquisition of Collective Land ...... 25 4.5.2 Compensation Rates for Temporary Land Occupation ...... 26 4.5.3 Compensation Rates for Rural Temporary Buildings ...... 26 4.5.4 Compensation Rates for Attachments and Infrastructure ...... 27 4.5.5 Rates of Other Costs ...... 28 4.5.6 Vulnerable Groups ...... 28 4.6 Entitlement Matrix ...... 29 5 RESETTLEMENT AND INCOME RESTORATION ...... 33 5.1 Resettlement Objectives ...... 33 5.2 Principles for Resettlement and Restoration ...... 33 5.3 Restoration Programs of Collective Land Acquisition ...... 33 5.3.1 Cash compensation and distribution ...... 33
II
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
5.3.2 Agricultural improvement ...... 34 5.3.3 Employee Engagement ...... 34 5.3.4 Training ...... 35 5.3.5 Social security system ...... 35 5.4 Restoration Program for Temporarily Occupied Land ...... 35 5.5 Compensation for Temporary Building Demolition ...... 36 5.6 Resettlement Program for Infrastructure and Ground Attachments ...... 36 5.7 Assistance Measures for Vulnerable Groups ...... 36 5.8 Protection of Women’s Rights and Interests ...... 37 6 PUBLIC PARTICIPATION AND GRIEVANCE REDRESS ...... 39 6.1 Public Participation ...... 39 6.1.1 Completed Public Participation Activities at Preparation Stage ...... 39 6.1.2 Participation Plan at the Implementation Stage ...... 41 6.2 Grievances and Appeals ...... 42 6.2.1 Grievance Redress Mechanism ...... 42 6.2.2 Recording, Tracking and Feedback of Grievances and Appeals ...... 43 6.2.3 Contact Information for Grievances and Appeals ...... 43 7 ORGANIZATION STRUCTURE AND RESPONSIBILITY ...... 44 7.1 Resettlement Implementing Agencies ...... 44 7.2 Assignment of Responsibilities ...... 44 7.3 Staffing and Equipment ...... 46 7.3.1 Staffing ...... 46 7.3.2 Equipment ...... 47 7.4 Capacity Enhancing Measures of Resettlement Agencies ...... 47 7.4.1 Resettlement management staff training plan ...... 47 7.4.2 Measures for improving resettlement agencies ...... 47 8 RESETTLEMENT BUDGET ...... 49 8.1 Estimated Budget ...... 49 8.2 Annual Investment Plan ...... 50 8.3 Disbursement and Management of Resettlement Funds ...... 50 8.3.1 Management of Resettlement Funds ...... 50 8.3.2 Disbursement of Resettlement Funds ...... 50 9 RESETTLEMENT IMPLEMENTATION PLAN...... 51 9.1 Principles for Resettlement Implementation ...... 51 9.2 Resettlement Implementation Schedule ...... 51 10 MONITORING AND EVALUATION ...... 53 10.1 Internal Monitoring ...... 53 10.1.1 Scope of Internal Monitoring ...... 53 10.1.2 Methodology of Internal Monitoring ...... 53 10.1.3 Interval and Reporting of Internal Monitoring ...... 54 10.2 External Monitoring ...... 54 10.2.1 Scope and Methodology of External Monitoring ...... 55 10.2.2 External Monitoring Reporting ...... 56 10.3 Post-Resettlement Evaluation ...... 56 APPENDIXES ...... 57
III
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
List of Tables Table 1 Overview of this update ...... i Table 1-1 Basic Information of the Project ...... 2 Table 1-2 Summary of Resettlement Impact ...... 4 Table 2-1 LAR impact breakdown according to packages ...... 7 Table 2-2 Summary of Collective Land Acquired Permanently for the Project ...... 9 Table 2-3 PLA Impact by Land Type and Affected villages ...... 11 Table 2-4 PLA Impact Analysis at Town Level ...... 12 Table 2-5 Land Loss Rate Distribution of Affected Households ...... 14 Table 2-6 Temporary Land Occupation for the Project ...... 14 Table 2-7 Temporary Building Demolition for the Project ...... 14 Table 2-8 Details of affected vulnerable groups ...... 15 Table 2-9 Summary of Affected Ground Attachments ...... 16 Table 3-1 The Social and Economic Situation of the Affected Towns ...... 17 Table 3-2 The Social and Economic Situation of the Affected Villages ...... 18 Table 3-3 Sample Households Income and Expenditure ...... 19 Table 4-1 Compensation rate for acquired collective land ...... 25 Table 4-2 Compensation rate for temporary building ...... 26 Table 4-3 Replacement cost analysis on temporary building ...... 27 Table 4-4 Compensation Standards for the Ground Attachments ...... 27 Table 4-5 Rates of Resettlement Taxes and Fees ...... 28 Table 4-6 Entitlement Matrix ...... 30 Table 5-1 Direct Created Jobs by the Project ...... 34 Table 5-3 Summary of Skill Training Plan ...... 35 Table 6-1 Summary of Public Opinions ...... 40 Table 6-2 Public Participation Plan ...... 41 Table 6-3 Registration Form of Grievance and Appeals ...... 43 Table 6-4 Agencies Accepting Grievances ...... 43 Table 7-1 Staffing of Resettlement Agencies ...... 46 Table 8-1 Resettlement Budget ...... 49 Table 8-2 Annual Resettlement Investment Plan ...... 50 Table 9-1 Resettlement Milestones ...... 51 Table 10-1 Sample Schedule of Resettlement Progress ...... 53 Table 10-2 Sample Monitoring Form ...... 54 Table 10-3 Reporting Schedule of External Monitoring & Evaluation ...... 56
List of Figures Figure 1-1 Construction Sites for the Project ...... 3 Figure 2-1 General Main Channel before rehabilitation ...... 13 Figure 2-2 Linji Branch Channel before rehabilitation ...... 14 Figure 3-1 Age Distribution ...... 18 Figure 3-2 Education Distribution ...... 19 Figure 4-1 LAR information disclosure and cut-off date announcement ...... 25 Figure 4-2 Meeting minute of the establishment of rehabilitation fund for vulnerable groups ...... 28 Figure 6-1 Appeal and Complaint Procedures ...... 43 Figure 7-1 Organization Chart of the Relevant Resettlement Implementation Agencies ...... 44 Figure 8-1 Flowchart of Resettlement Fund Disbursement ...... 50
IV
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
1 PROJECT OVERVIEW 1.1 Background and Description of the Project
1.1.1 Background of the Project
1. In 2009, the State Council of People’s Republic of China (PRC) approved the Guanzhong Tianshui Economic Zone to strengthen the development of the western region. Weinan Municipality, located in the east of Guanzhong Plain, is striving to improve local livelihoods and environment, attract high-tech industrial investment, promote local tourism, and create job opportunities in the Luyanghu area. Shaanxi Weinan Luyang Integrated Saline Land Management Project (L2980/G0331-PRC) will support the Weinan Municipality in implementing natural environment and rural livelihoods improvements for the Luyanghu area. The project area is within the Weinan Municipality, Shaanxi Province. The resident population of Weinan is 5.52 million and the area is 13,100 km2. The transport is convenient with the area, which is called a main cross of Shaanxi connecting with eight provinces. In 2014, the GDP of Weinan is CNY 146.094 billion, an increase of 10.5% over the previous year. The three industries increased 4.9%, 12.1% and 9.7% respectively. The disposable income per capita of the urban citizens in Weinan is CNY 26725, rising CNY 2561. The net income per capita of the rural residents is CNY 8534, rising CNY 969. The two figures are 3% higher than those of Shaanxi Province.
2. Specifically, the Project is constructed in Weinan Luyanghu Modern Industrial Development Zone (WLMIDZ), which is consist of 7 towns in Pucheng County and Fuping County with an area of 124.24 km2. It’s a young development zone approved by Shaanxi Province Government in August 2007, and the population is about 64.3 thousand in 35 villages. WLMIDZ is surrounded by a tableland area, flat and open, with deep soil, sufficient light and heat resources as a traditional agricultural growing area. From the 1960s onwards, in order to solve the irrigation and drainage of the area, the state and local governments have invested in the Longyang pumping irrigation area, Luohui west irrigation area, Qunying pumping irrigation area, Donglei Phase II Yellow River pumping irrigation area, and according to the topographical features and disaster situations, built the Luoxi drainage system for Lubo Shoal and the return water works in irrigation area and other water conservancy facilities, playing an important role in the promotion of regional agricultural production. Low-lying terrain, occlusion, and poor drainage are the main reasons to cause the soil salinization in WLMIDZ, which is the obstacle of the local socioeconomic development and environment protection.
1.1.2 Components and Identification of Resettlement Impacts
3. The project comprises of four outputs: (i) saline soils rehabilitated; (ii) flood risk management implemented; (iii) wetland ecosystem conservation established, comprising (a) support for LNWP development, and (b) promotion of tourism, livelihood, and employment opportunities for local communities; and (iv) capacity development and project implementation support provided. The construction area can be seen in Figure 1-1.
Output 1 Saline soils rehabilitated will reduce soil salinity over approximately 212 km2 and increase productivity and climate resilience of approximately 186 km2 of agricultural land. It has two components: (i) rehabilitation of Luoxi drainage system, and (ii) support for improving resilience to climate change of agro-ecosystems. Output 2 Flood risk management implemented will improve flood storage capacity of Luyanghu area to reduce flood risks to local residents. It includes (i) construction of Tianlu lake (approximately 130 ha), connecting Tianjiao lake in the west, a middle main channel,
1
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project and a central main channel; and (ii) construction of approximately 18.6 km of dike with road around Tianlu lake. The integrated and innovative approach combining flood risk management with drainage system rehabilitation and wetlands ecosystem conservation will contribute to reduced flood risk for the Luyanghu area. Output 3 Wetland ecosystem conservation established has two components: (i) support for LNWP development; and (ii) promotion of tourism, livelihood, and employment opportunities for local communities. The wetlands conservation will reverse ecosystem degradation caused by agricultural encroachment and other pressures associated with the increasing population within the project area. Output 4 Capacity development and project implementation support provided has two components: (i) institutional strengthening, and (ii) project management support during project implementation. The first will support capacity development and training of WMG and WLMIDZMC staff in ADB project management procedures, technical design and implementation, and safeguard supervision and monitoring. The project and the GEF grant were approved on 17 December 2012, which will be implemented in 5 years from 2013 to 2018. The investment cost of the Project is estimated at $165.2 million, of which $100 million is from the ordinary capital resources of ADB. The Weinan Municipal Government also received a $2 million grant from the land degradation focal area of the Global Environment Facility (GEF) to support the work on sustainable land management. A summary profile of the Project is listed in Table 1-1.
Table 1-1 Basic Information of the Project 1 Country People’s Republic of China (PRC) 2 Grant No. 0331-PRC 3 Loan No. 2980-PRC Shaanxi Weinan Luyang Integrated Saline Land Management 4 Project Project 5 Borrower Ministry of Finance of the PRC Weinan Municipal Government (WMG) 6 Executing Agency A PMO formed to act on behalf of the WMG Weinan Luyanghu Modern Industrial Development Zone Implementing 7 Management Committee (WLMIDZMC) Agency A PIO formed to act on behalf of the WLMIDZMC Total Estimated USD 165.2 million 8 Cost 9 ADB Loan USD 100 million Source: ADB website.
4. Based on preliminary identification, the main types of resettlement impacts of the Project are land acquisition, temporary land occupation and the demolition of temporary buildings. All the land acquisition and resettlement (LAR) impacts are induced by the Component 1 Saline Soils Rehabilitation and Component 2 Flood Risk Management.
5. The Project is categorized as A for involuntary resettlement following the criteria laid out in the Safeguard Policy Statement 2009. To mitigate negative impacts of economic and physical displacement, the Project has prepared a draft resettlement plan (RP) during project preparation phase in 2012. Based on the preliminary design and DMS conducted in April 2015, an updated RP has been submitted to ADB for review in August 2015. The updated RP was approved by ADB and uploaded on the website of ADB in September 2015. In March 2016, there is major difference found in the updated RP that the Component 1 incurs 2412mu land acquisition for the rehabilitation of Luoxi drainage system, and the RP updating again in July 2016 based on the detailed design.
2
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
Figure 1-1 Construction Sites for the Project
3
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
1.1.3 Summary of Resettlement Impacts
6. According to the updated RP, the construction of saline land rehabilitation in Component1, Tianlu Lake with a total of 18.6 km dike and road around in Component 2 will incur permanent land acquisition (PLA) of 366.78 hectares (5501.72 mu) land and demolition of 19326 m2 of temporary buildings. The saline land rehabilitation of Component 1 will incur temporary land occupation (TLO) and the total amount of TLO will be 160.13 hectares (2402.5 mu). The wetland ecosystem conservation of Component 3 is not involved in land acquisition and resettlement (LAR). A total of 17,232 persons in 3,698 households will be affected by land acquisition, salt pan acquisition, temporary building demolition. The affected areas include 53 villages in 5 towns of Pucheng County and 7 villages in 1 town of Fuping County, Weinan Municipality. Based on the previous survey, there is no minority affected within the project area.
Table 1-2 Summary of Resettlement Impact County Pucheng Fuping Amount Towns 5 1 6 Villages 53 7 60 Subtotal 5334.72 167 5501.72 Where: cultivated land Collective 2265.65 167 2432.65 land Permanent LA Non-cultivated land (mu) 3069.07 0 3069.07
State-owned land 0 0 0 Total 5334.72 167 5501.72 Temporary Construction and life area 57 0 57 land Construction road occupation 1018.35 0 1018.35 (mu) Site for spoil from main ditch 967.15 0 967.15 Total 2042.5 0 2042.5 2 HD(m ) Temporary building demolition 19326.62 0 19326.62 HHs 3423 275 3698 LA Population 16016 1216 17232 HHs 0 0 0 HD only Population 0 0 0 HHs 35 0 35 Both LA and HD Directly Population 175 0 175 affected HHs population 3423 275 3698 Subtotal Population 16016 1216 17232
Demolition of non- HHs 0 0 0 residential properties Population 0 0 0 HHs 3423 275 3698 Total Population 16016 1216 17232
1.2 Social and Economic Benefits
7. Improvement of soil salinity to increase farmers’ income. After this project is completed, the existing visible water elevation will be reduced a lot, and the groundwater level within the area
4
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project will be significantly reduced, to make the saline soil effectively controlled. More than 50,000 farmers will benefit from the management.
8. Prevention of waterlogging to protect people’s lives and property. The masses in the shoal area and downstream of irrigation area suffered from heavy losses in life and production. Once the project is completed, it will prevent waterlogging, effectively eliminate the hazards of floods in Xihan Railway, Xiyu Expressway, Weipu Expressway and Weiqing Highway and other important transportation routes, so as to ensure the safety of people's lives and property, to promote harmonious development and social stability in economic and social development of the drainage area, and to play its regional resource advantages. The service area of this Project is 418km2, and 144 villages of 10 towns in Pucheng and Fuping County will be benefited from it.
9. Restoring of the wetland ecosystem, and laying the foundation for the development of tourism and other industries. The project is planned, through returning low quality fields or wasteland to lakes, construction of artificial wetlands and recovery measures for wetland ecology, etc., to protect and recover the Luyang Lake wetland ecological system, so that wetlands can effectively bring about a variety of ecological, economic and social benefits in flood storage and alkali removal, water conservation, purification of water quality, landscaping and provision of wetland. Meanwhile, by taking full advantage of existing tourism resources in the project area, Luyang Lake wetland will be built as an important eco-tourist attraction in Shaanxi Province.
10. Complying with the regional development planning. The construction objectives of this project is fully consistent with the Planning for Development of Guanzhong - Tianshui Economic Zone. Luyang Lake is located in the central hinterland of the Eurasian Continental Bridge, a link to connect Guanzhong - Tianshui Economic Zone with the Comprehensive Experimental Zone for Coordinated Development of Shanxi, Shaanxi and Henan Yellow River Golden Triangle Region. After the completion of the project, it will greatly improve the Luyang Lake’s ecological environment, greatly enhance the environment for the development of agriculture, tourism, commerce, services in the project area, and strengthen the Luyang Lake’s tie function and radiation effects in the above regions.
1.3 Estimated Resettlement Budget and Implementation Plan
11. In order to mitigate negative impacts of land acquisition and resettlement (LAR) of this project and guarantee interests and rights of affected persons (APs) and full compensation for APs’ property and income loss, based on detailed design of the project, this resettlement plan (RP) is prepared in accordance with relevant involuntary resettlement policies and regulations of the PRC, Shaanxi Province and Weinan Municipality as well as ADB’s Safeguard Policy Statement (SPS, 2009). The gross investment in the Project is CNY 1.09 billion yuan. Construction funds will be raised from the following three sources, namely ADB loan, GEF grant and Weinan Municipality Governments counterpart fund. The estimated resettlement costs of the Project are CNY 105.28 million yuan, accounting for 9.65% of gross investment, all from domestic counterpart funds.
12. The Project loan takes effective on June 27, 2013, and engaged the project consultation corporation on April 23, 2015. It’s planned to be completed on June 30, 2018, with a construction period of 60 months. Up to July 2016, 1 package of Component 1 and 3 packages of Component 2 are under construction. To meet the schedule of civil works, the LA and HD commenced on April 2014.
5
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
2 PROJECT IMPACTS 2.1 Types of Impacts
13. According to the field survey and analysis, the impact of the project is categorized as: Land acquisition / occupation loss; Temporary building demolition loss; and Other direct and indirect impacts.
2.2 Methodology and Procedures
14. In April 2012, the WLMIDZC appointed Design Institute to prepare the Feasibility Study Report of the Project. During September-October 2012, the survey team of Shaanxi Academy of Social Sciences conducted a survey on the socioeconomic profile of the project area, and resettlement impacts according to the Feasibility Study Report, and a sampling socioeconomic survey covering household population, impacts of LA, household economic status, and expected resettlement modes. The main survey methods are as follows: (i). Door-to-door questionnaire survey: A door-to-door questionnaire survey was conducted in the project area , with the aim of: (1) learning the potential positive and negative impacts of the Subproject; (2) learning local residents’ attitude to, expectations for and suggestions on the Subproject; and (3) learning the public participation and opinions of local residents. (ii). Focus group discussion (FGD): The aim is to: (1) collect the APs’ awareness of, attitude to and expectations for the Subproject; and (2) learn the main modes of information disclosure in the affected towns and villages, and promote public participation. 3 town-level FGDs were held, including one FGD with women and two ordinary FGDs. (iii). In-depth interview: The aim is to further learn the APs’ production and living conditions, positive and negative impacts of the Project on them, potential risks, and their attitude to, expectations for and suggestions on the Project. Women, old people, and staff members of public institutions were interviewed in depth. (iv). Key informant interview: Key informant interviews were conducted with heads of the women’s federation, poverty reduction office, ethnic and religious affairs bureau, land and resources bureau, LA and HD management office, civil affairs bureau, statistics bureau, and labor and social security bureau at the county level, and village heads at the village level, with the aim of learning the stakeholders’ comments and suggestions on the Subproject.
2.3 Permanent Land Acquisition 15. Due to the civil works of Component 1 Saline Soils Rehabilitation and Component 2 Flood Risk Management, the Project will acquire 5501.72 mu land and demolish temporary building in saltpan or along the branch sides. For the construction of excavation of Tianlu-Tianjiao Connection, the land 776.17 mu had been acquired in 2010, and the details can be seen in Due Diligence Report. Other packages are less related to land acquisition without physical impact. The details can be seen in Table 2-1. 16. The land to be acquired is all collective land in Pucheng County and Fuping County, involved 60 villages in 6 towns. Furthermore, 5334.72 mu land in Pucheng County includes 3069.07 mu waste land, most of which is saltpan, the details can be seen in Table 2-2.
6
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
Table 2-1 LAR impact breakdown according to packages
Component/Package Description Sub-package Status Impact PLA(mu) A. Works (13 packages) 5501.72 I. Saline Soils Rehabilitation (8 packages) 2412.15 ADB-SS-CD-01-01 Under Construction PLA 213.4 ADB-SS-CW-01 Rehabilitation of Central Main ADB-SS-CD-01-02 Under detail design PLA 75 ADB-SS-CD-01-03 Under detail design PLA 415 Rehabilitation of Branch and Secondary Branch under ADB-SS-CW-02 Under detail design PLA 220.35 the Central Main ADB-SS-CW-03 Rehabilitation of East Main and its Secondary Branch Under detail design PLA 259 ADB-SS-CW-04 Rehabilitation of Middle Main and its Secondary Branch Under detail design PLA 191 ADB-SS-CW-07 Rehabilitation of West Main and its Secondary Branch Under detail design PLA 377.4 ADB-SS-CW-08-01 Under detail design PLA 82 Rehabilitation of West Main including structures, ADB-SS-CW-08 ADB-SS-CW-08-02 Under detail design PLA 366 management office, and on-farm works ADB-SS-CW-08-03 Under detail design PLA 213 GEF-SS-CW-09 Saline Soil management Ongoing No LAR 0 GEF-SS-CW-10 Shelter belt establishment Ongoing No LAR 0 II. Flood Risk Management (3 packages) 3089.57 ADB-FM-CW-01-01 0 ADB-FM-CW-01 Excavation of Tianlu-Tianjiao Lakes Connection Repackage and Bidding Pre-acquired ADB-FM-CW-01-02 0 ADB-FM-CW-02-01 Ongoing PLA 379 ADB-FM-CW-02-02 Ongoing PLA 395 ADB-FM-CW-02 Excavation of Tianlu Lake ADB-FM-CW-02-03 Ongoing PLA 439 ADB-FM-CW-02-04 Contract award PLA 320 ADB-FM-CW-02-05 Contract award PLA 300 ADB-FM-CW-03 Construction of lake road and dike No started PLA 1256.57 III. Wetland Ecosystem Conservation (2 packages) ADB-WE-CW-01 Construction of Wetland Management Facilities Ongoing No LAR 0 GEF-WE-ME Wetland Management Ongoing No LAR 0 7
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
Component/Package Description Sub-package Status Impact PLA(mu) B. Goods (2 packages) I. Saline Soils Rehabilitation (1 package) ADB-SS-ME-01-01 Shopping No LAR 0 ADB-SS-ME-01 Office equipment for management offices ADB-SS-ME-01-02 No bidding No LAR 0 ADB-SS-ME-01-03 No bidding No LAR 0 II. Wetland Ecosystem Conservation (1 package) ADB-WE-ME-01 Equipment for Public Education Ongoing No LAR 0 C. Consulting Services (8 packages) I. Saline Soils Rehabilitation (5 packages) GEF-SS-CS-01 Soil Management Specialist Ongoing No LAR 0 GEF-SS-CS-02 Rural Business Development Specialist Ongoing No LAR 0 GEF-SS-CS-03 Eco-compensation Specialist Ongoing No LAR 0 GEF-SSTS-01 Field Schools Establishment Ongoing No LAR 0 GEF-SSTS-02 Alternative Livelihoods Ongoing No LAR 0 II. Wetland Ecosystem Conservation (1 package) GEF-WE-CS-01 Wetland Management Specialist Ongoing No LAR 0 III. Capacity Development (2 packages) ADB-CD-CS-04 Project Management Consultants Ongoing No LAR 0 GEF-CD-CS-01 Monitoring and Evaluation Specialist Ongoing No LAR 0 D. Training and Study Tours (6 packages) IV. Capacity Development (6 packages) ADB-TS-TST-01 Training on drainage system management skills Preparation No LAR 0 ADB-TS-TST-02 Training wetland management skills Preparation No LAR 0 ADB-TS-TST-03 Overseas study tour on saline soil improvement Preparation No LAR 0 ADB-TS-TST-04 Overseas study tour on wetland management Preparation No LAR 0 ADB-TS-TST-05 Domestic study tour on saline soil improvement Preparation No LAR 0 ADB-TS-TST-06 Domestic study tour on wetland management Preparation No LAR 0
8
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
Table 2-2 Summary of Collective Land Acquired Permanently for the Project Package Works Town Pucheng County Fuping County PLA cultivated cultivated Village waste land subtotal Village subtotal land land ADB-SS-CW-01 Central Main Dangmu 1 213.4 213.4 213.4 Central Main Dangmu 1 75 75 75 Central Main Dangmu 2 135 135 135 Longchi 4 280 280 280 ADB-SS-CW-02 Dangmu Branch Dangmu 1 46.35 46.35 46.35 Fanjia Branch Dangmu 2 50 50 50 Longyang 2 50 50 50 Linji Branch Dangmu 1 38 38 38 Zhangjia Branch Dangmu 3 36 36 36 ADB-SS-CW-03 Dujia Branch Dangmu 3 20 20 20 East Main Dangmu 1 60 60 60 Dongchen 1 65 65 65 Jiangji Branch Dangmu 1 33 33 33 Mindi Branch Dangmu 1 24 24 24 Longyang 1 25 25 25 Tongyi Branch Longyang 3 32 32 32 ADB-SS-CW-04 Middle Main Dangmu 1 66 66 66 Dongchen 2 70 70 70 Neifu Branch Dongchen 1 31 31 31 Sibu Branch Dongchen 2 24 24 24 ADB-SS-CW-07 West Main Jingyao 1 47.4 47.4 47.4 Longyang 3 245 245 245 Shijia 1 85 85 ADB-SS-CW-08 Guancun Branch Shijia 2 15 15 Jiangjungou Branch Shijia 2 19 19 Shijia Branch Shijia 2 48 48 Donglei Branch Jingyao 2 50 50 50
9
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
Package Works Town Pucheng County Fuping County PLA cultivated cultivated Village waste land subtotal Village subtotal land land Dongzhang Branch Jingyao 2 66 66 66 Jingyao Branch Jingyao 2 59 59 59 Mingde Branch Jingyao 2 58 58 58 Tianshuijing Branch Jingyao 3 73 73 73 Xujiazhuang Branch Jingyao 1 22 22 22 Zhongjia Branch Longyang 2 38 38 38 Dongchen Branch Dongchen 1 38 38 38 Dongxing Branch Dangmu 2 34 34 34 Dongxing 1st Branch Dongchen 4 35 35 35 Dongxing 2nd Branch Dongchen 1 35 35 35 Gaomi Branch Dangmu 1 30 30 30 Wijiazhai Branch Dangmu 1 19 19 19 Xichen Branch Dongchen 2 22 22 22 ADB-FM-CW-02 ADB-FM-CW-02-01 Dangmu 1 20.5 358.5 379 379 ADB-FM-CW-02-02 Dangmu 1 395 395 395 ADB-FM-CW-02-03 Dangmu 1 439 439 439 ADB-FM-CW-02-04 Dangmu 1 320 320 320 ADB-FM-CW-02-05 Dangmu 1 300 300 300 ADB-FM-CW-03 Dangmu 3 1256.57 1256.57 1256.57 Total 71 2265.65 3069.07 5334.72 7 167 5501.72
10
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
17. About 5334.72 mu of collective land will be acquired permanently in Pucheng County, including 2265.65 mu of cultivated land, 3069.07 mu of waste land, affecting 3423 households with 16,016 persons in 53 villages in 5 towns. Only 167 mu of collective land will be acquired permanently in Fuping County, which are all cultivated land, affecting 276 households with 1,216 persons in 7 villages in Shijia Town. See Table 2-3. Table 2-3 PLA Impact by Land Type and Affected villages cultivated waste subtotal County Town Village AHs APs land (mu) land (mu) (mu) Pucheng County 2265.65 3069.07 5334.72 3423 16016 Dangmu Dangbei 46.35 46.35 90 440 Dangnan 70 70 110 520 Dongshe 15 15 25 120 Fanjia 45.5 2247.54 2293.04 78 367 Jiangji 38 38 52 253 Linji 38 38 55 250 Linjia 66 66 98 471 Luyangnan 279.4 593.17 872.57 426 1807 Luyangxin 66 228.36 294.36 105 494 Mindi 33 33 50 234 Nanwang 65 65 90 400 Pailou Zhangjia 12 12 20 96 Wujiazhuang 17 17 25 120 Xiwangjia 9 9 15 71 Yanwang 25 25 35 170 Zhajia 75 75 100 450 Dangmu subtotal 16 900.25 3069.07 3969.32 1374 6263 Dongchen Dongchen 38 38 50 241 Fuxin 9 9 12 57 Jiangji 65 65 100 481 Lijiazhuang 9 9 11 52 Neifu 65 65 135 656 Sanli 9 9 15 74 Sibu 11 11 18 84 Wujiazhai 35 35 50 238 Wujiazhuang 8 8 10 49 Xichen 11 11 15 71 Xinglong 48 48 65 320 Xinli 12 12 15 75 Dongchen subtotal 12 320 320 496 2398 Jingyao Donglei 25 25 40 189 Dongxing 20 20 35 151 Dongyao 47.4 47.4 65 314 Ganquanfang 25 25 40 190 Gaodu 19 19 30 144 Mingde 39 39 60 281 Nanbeibu 33 33 50 237 Tianshuijing 33 33 45 212 Wangjia 39 39 60 286 Xichang 33 33 45 211 11
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
cultivated waste subtotal County Town Village AHs APs land (mu) land (mu) (mu) Xizhang 20 20 30 143 Xujiazhuang 22 22 35 150 Zhaizi 20 20 30 142 Jingyao subtotal 13 375.4 375.4 565 2650 Longchi Chedu 70 70 110 510 Chongquan 70 70 95 450 Longchi 70 70 110 530 Wusi 70 70 100 480 Longchi subtotal 4 280 280 415 1970 Longyang Beihandi 25 25 40 181 Fuwang 100 100 150 717 Hejia 10 10 15 82 Nanhandi 10 10 15 82 Tongyi 12 12 18 91 Zhaojia 115 115 160 750 Zhaojiazhuang 22 22 25 117 Zhongjia 96 96 150 715 Longyang subtotal 8 390 390 573 2735 Fuping County 167 167 275 1216 Shijia Guan 8 8 15 69 Nanping 85 85 150 622 Nanpo Dujia 10 10 15 71 Shangliu 28 28 40 191 Taoyuan 9 9 15 72 Wangjia 20 20 30 143 Zhaojia 7 7 10 48 Shijia subtotal 7 167 167 275 1216 Total 6 60 2432.65 3069.07 5501.72 3698 17232
18. As the land acquisition for branch rehabilitation is linear, the number of affected villages and households is large, but impacts are limited per household. In terms of average land loss of affected households, the highest is 7.6% in Jingyao while the lowest is 5.0 % in Dongchen Town. Table 2-4 PLA Impact Analysis at Town Level before Land Acquisition after Land Acquisition Per Household Per Household Land Farmland The Farmland Acquired Town Farmland Average Acquisition in Villages Number of Farmland (10000 mu) Farmland Households Affected (mu/household) Loss(mu) Loss Rate Loss Rate households Dangmu 11000 9.8 8.9 1374 900.25 0.9% 7.4% Jingyao 17700 15.5 8.76 565 375.4 0.2% 7.6%
Dongchen 3500 4.5 12.86 496 320 0.7% 5.0%
Longyang 5890 5.6 9.51 573 390 0.7% 7.2%
Longchi 7456 7.2 9.66 415 280 0.4% 7.0%
12
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
Shijia 15000 15.7 10.47 275 167 0.1% 5.8%
Figure 2-1 General Main Channel before rehabilitation
13
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
Figure 2-2 Linji Branch Channel before rehabilitation 19. In terms of individual household level land loss rate, among the 3,698 households affected by PLA, 595 AHs (16.0%) will lose 0-6% of their cultivated land, 1649 households (44.7%) will lose 6-7%, 1353 households (36.6%) will loss 7-8%, and only 101 AHs (2.7%) will lose more than 8%. No household will lose land of more than 10%. See Table 2-5. Table 2-5 Land Loss Rate Distribution of Affected Households No Administration The Distribution of the Loss Rate of Farmland of Subtotal Area of Project Households Acquired Land in the Project(Household) ≤6% 6%—7% 7%-8% ﹥8% 1 Dangmu Town 2 861 505 6 1374 2 Jingyao Town 5 85 400 75 565 3 Dongchen Town 395 100 1 0 496 4 Longyang Town 42 271 242 18 573 5 Longchi Town 8 201 204 2 415 6 Shijia Township 143 131 1 0 275 Total 6 595 1649 1353 101 3698 Proportion (%) 16.0% 44.7% 36.6% 2.7% 100.0%
2.4 Temporary Land Occupation 20. About 2042.5 mu of land will be occupied temporarily, which are totally for Component 1 in Pucheng County. The planned period of occupation will be two years. See Table 2-6. 21. S Table 2-6 Temporary Land Occupation for the Project Utilization Current site Amount Occupation time Occupatio reclam situation (mu) n time ation Construction farmland Main and branch 57 During the 2 years Yes and life area ditch construction time Construction farmland Main and branch 1018.35 During the 2 years Yes road ditch construction time Site for spoil farmland Along the main 967.15 During the 2 years Yes from main ditch, east of construction time channels Jingcheng village
2.5 Demolition of Rural Temporary Buildings 22. In the implementation stage, almost all the APs are contractor on salt pans with temporary building demolished. All the non-residential houses were used for salt production, management, and warehouse for the tools. Besides, the main channels rehabilitation will demolish some simple house or mud-wood house used for production tools storage. See Table 2-7. Table 2-7 Temporary Building Demolition for the Project Component Package No. sub-package Amount (m2) I. Saline Soils Rehabilitation ADB-SS-CW-01 500 ADB-SS-CW-02 500 ADB-SS-CW-03 450 ADB-SS-CW-04 350 ADB-SS-CW-07 600 I. Saline Soils Rehabilitation Subtotal 2400 II. Flood Risk Management ADB-FM-CW-02 ADB-FM-CW-02-01 3906.47 ADB-FM-CW-02-02 559.58 ADB-FM-CW-02-03 992.55 ADB-FM-CW-02-04 2483.66 ADB-FM-CW-02-05 4028.79 ADB-FM-CW-03 4955.57 II. Flood Risk Management 16926.62 Total 19326.62 14
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
2.6 Affected Vulnerable Groups
23. Among the affected households, there are 19 vulnerable households (5.38% of all the affected households) are offered subsistence allowances by the government. The 19 vulnerable group households include 5 disabled households, 10 low income households and 4 five- guarantee households. They will be entitled to special support as AHs. And the Project Office confirmed that 0.5% of the total resettlement budget will be used as the special rehabilitation fund for the vulnerable group. Table 2-8 Details of affected vulnerable groups Village/County Name Population(person) category Linjia, Pucheng Cheng Youcang 4 Disabled Linjia, Pucheng Wu Jiyuan 3 Disabled Linjia, Pucheng Song Xiannian 4 ill Linjia, Pucheng Yang Wuxi 2 Old and weak subtotal 4 households 13 persons Donglou, Pucheng, Weinan Wei Baozhu 4 Disabled Donglou, Pucheng, Weinan Cui Jilin 4 Disabled Donglou, Pucheng, Weinan Chang Qingyu 3 Old and weak Subtotal 3 households 11 persons Chitou, Pucheng Li Xiangquan 4 Disabled Chitou, Pucheng Li Zhiming 3 Ill Chitou, Pucheng Li Sanxi 5 old and weak Subtotal 3 households 12 persons Shuinan, Pucheng Wang Xinhong 4 Old and weak Shuinan, Pucheng Liu Jungang 4 ill Shuinan, Pucheng Liu Panxin 4 Disabled Shuinan, Pucheng Liu Heping 3 Old and weak subtotal 4 households 15 Fujia, Pucheng Wang Yali 4 ill Fujia, Pucheng Wang Daimin 4 ill Fujia, Pucheng Wang Haisheng 3 Old and weak Fujia, Pucheng Zhao Wenyuan 3 Old and weak Fujia, Pucheng Li Huamin 5 Disabled subtotal 5 households 19 persons Total 19 households 70 persons
2.7 Affected Women
24. In the population affected by the Project, no widowed, divorced or abandoned woman was found among the respondents. The affected women enjoy the same rights as men, including land contracting, education receiving, family planning and election. Most of the female labor respondents think that they have the same autonomy in production and management as men, and may elect to get employed or do small business independently.
25. The impact of the Project on women’s income is due to the acquisition of cultivated land, while per capita crop cultivation income is 1,000-1,500 yuan, accounting for 8% of household income. Boys and girls have equal opportunities in education, showing no gender-related difference.
26. According to the survey, women have the same concerns as those of men: (a) Compensation rates should comply strictly with the state laws and policies; (b) Compensation fees should be disbursed directly to the AHs. Women have the following needs that are different from those of men: (a) Women expect both cash compensation and land reallocation; (b) Women want skills training in fruits cultivation, stockbreeding and handicrafts; and (c) Women also expect to participate in village-level management. 15
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
2.8 Affected Infrastructure and Ground Attachments
27. The Project will affect 12 types of attachments, namely enclosing walls, fences, cement grounds, telegraph poles, streetlamps, junction boxes, transformers, tombs, wells and trees. See Table 2-9. Table 2-9 Summary of Affected Ground Attachments Item Unit Amount Brick enclosure m 2000 Grown fruit tree tree 1218 Grown tree tree 600 Water closet each 100 Young fruit tree tree 696 Young tree tree 3000 water cellar each 80 well each 70 concrete pole each 300 chimney each 50 transformer each 30 power line m 3000
16
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
3 SOCIOECONOMIC ANALYSIS OF AFFECTED AREA 3.1 Socioeconomic Profile of the Project Area
3.1.1 Socioeconomic Profile of the Affected Counties 28. Pucheng County, located in the northeast of Weihe River Plain, 110 kilometers away from Xi'an, with a total area of 1584 square kilometers and a total population of 760,000, the location of National Time Service Center, has 24 townships and 359 administrative villages. Primary industry is dominated by grain, fruit, animal husbandry and greenhouse facilities at Pucheng County, which has 1.68 million mu of arable land and above 0.65 billion kilograms of grain total output. Besides, Pucheng County is the key county of high-quality fruit industrialization and known as pear. The secondary industry is dominated by energy and chemical industries, agriculture related industries, fireworks, processing etc. The tertiary industry is dominated by tourism, catering and logistics. 29. The county’s regional GDP was more than 15.62 billion yuan in 2014, up 10.1% year on year. Rural residents’ per capita net income was 8,490 yuan, up 11.5% year on year; total retail sales of social consumer goods 5.1 billion yuan, up 14% year on year. 3.1.2 Socioeconomic Profile of the Affected Towns 30. Dangmu Town is located in 15 kilometers south of Pucheng County. The widest span from east to west is 12 kilometers, and the longest span from south to north is 11 kilometers. The total area of this town is 94.73 square kilometers. The town’s jurisdiction includes 25 administrative villages, 162 village groups, 68 villages, 11,000 households, 43,700 persons, the total cultivated land area of 94,900 acres. The industries is dominated by breeding industry, facility agriculture and manufacturing and services in the town. The town’s regional GDP was 0.449 billion yuan in 2014, up 10.9% year on year. Rural residents’ per capita net income was 6986 yuan, up12.4% year on year. Table 3-1 The Social and Economic Situation of the Affected Towns No Town HHs population Farmland Area(ten thousand The Average Number of of People Per Household( Capita Per Farmland(m u/person) Capita Per Net Income of Farmers(yu an) 1 Dangmu 11000 43700 9.8 4 2.24 10086 2 Jingyao 17700 85000 15.5 4.8 1.82 9210
3 Dongchen 3500 17289 4.5 4.9 2.6 13700
4 Longyang 5890 25000 5.6 4.2 2.24 12980
5 Longchi 7456 35000 7.2 4.7 2.06 18000 6 Shijia 15000 75000 15.7 5 2.09 9841
3.1.3 Socioeconomic Profile of the Affected Villages 31. The land acquisition and relocation of this project will affect six administrative villages in Dangmu Town, Weinan City, with a total population of 2,359 households, 10,736 people. 32. According to the survey, as of the end of 2015, there is no scale business enterprise in the 6 villages affected by the project, and the villagers only have some temporary business income, such as the income of nitrate production using local natural conditions. With the development of the project, local farmers' income structure is changing, with the proportion of agricultural income declining, the proportion of income of independent business and service industry and other tertiary industries increasing. Table 3-2 summarizes the social and economic situation of the affected villages.
17
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
Table 3-2 The Social and Economic Situation of the Affected Villages Total The Total Total Poor Per capita Affected Cultivate Industrial Number of Population Male Female Persons/ Income in Villages d Area Structure Households (Persons) Household Rural Area (MU) Go out to work, independent Chitou 657 2796 1425 1371 78/28 5500 7332 management and farming Go out to work, independent Shuinan 364 1494 784 710 51/13 3800 6631 management and farming Go out to work, independent Linjia 574 2595 1326 1269 88/30 5000 8094 management and farming Go out to work, independent Fanjia 254 1317 672 645 46/13 6000 7906 management and farming Go out to work, independent Fujia 243 1241 631 610 42/12 4449 7700 management and farming Go out to work, independent Liujia 267 1320 684 636 50/11 4562 7505 management and farming Go out to work, independent 6 2359 10763 5543 5220 355/107 29311 7528 management and farming
3.2 Socioeconomic Status of the Affected Population
3.2.1 Analysis of Household and Female Population 33. We conducted a sample survey of 1,500 households, accounting for 6% of the total number of households in the 9 sample villages, accounting for 15.5% of all 71 affected villages. 34. In the 1,500 households surveyed, the total number of population is 7,235, the labor 4,842. These people are all Han Nationality, and the number of female is 3,400 accounting for 47% of total respondents. 3.2.2 Age Structure 35. Among the 1,500 households, 7,235 persons, the number of people under the age of 16 accounts for 17.8%, between 16 and 39 34.2%, between 40 and 59 34.6%, over 60 13.4%.
under 16 16‐39 40‐59 over 60
Figure 3-1 Age Distribution
18
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
3.2.3 Educational Level 36. Among the 1,500 households, 7,235 persons, literacy in primary school or below accounts for 21.2%, middle school 32.9%, high school 33.3%, college or above 12.6%. Figure 3-2 illustrated the education background of sample people.
primary school or below middle school high school College or above
Figure 3-2 Education Distribution 3.2.4 Housing Conditions 37. The structure of sample house were major brick-concrete structure and brick-wood structure, with a total housing area of 376,500 m2, or 251 m2 per household on average and 52 m2 per capita. 18.4% households with an area of under 100 m2, 33.4% with an area of 100 -150 m2, 34.6% with an area of 151-300 m2, 10.8% with an area of 301-450 m2, 2.9% with an area of over 451m2.
3.2.5 Household Income and Expenditure 38. The surveyed households have an average annual per household income of CNY 35,000 and an average annual per capita income of CNY 3,125. The income of farmers in the agricultural accounts for a large proportion, and this is consistent with the local industrial structure. Women generally are engaged in farming or handicraft industry, while male labor farming or going out to work. 39. The surveyed households have an average annual household expenditure of CNY 29,000, with household operation expenses CNY 5,000 (17.2%) per household, living consumption expenses CNY 20,000 (69%) per household, other expenses CNY 4,000 (13.8%) per household. The Table 3-3 illustrated the sample households income and expenditure.
Table 3-3 Sample Households Income and Expenditure Item Proportion Per Household Income Per Capita Income % Yuan/Household Yuan/Person Agriculture income 43 15000 3125 Forestry income 0 0 0 Animal husbandry income 0 0 0 Industrial income 0 0 0 Construction industry income 0 0 0 Transportation business 0 0 0 income Service industry income 0 0 0 Other non-agriculture income 3.4 1200 250 Outgoing labor income 51 18000 3750
Annual household income Annual household Collective distribution income 0 0 0 Property income 2.7 800 167 Subtotal 100 35000 7292
19
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
Proportion Per Household Per Capita % Expenditure Expenditure Yuan/Household Yuan/Person Household operation 17.2 5000 1042 expenses Living consumption 69 20000 4167 expenses
Annual Other expenses 13.8 4000 833 Household Expenditure Subtotal 100 29000 6042
3.3 Social and Gender Analysis
40. After the implementation of the project, the affected persons will lose some land, but they can get relevant compensation and improve the living standard through the implementation of the project. In the affected area, the women do most of the housework, so the improvement of the living condition and the environment will lessen their labor. And they can get more job chances because of the improvement of the living condition. Of course, in the socioeconomic survey of the affect to the women, it is shown that both the men and the women concern the just and in-time compensation. 41. Moreover, the income from agriculture is only the 26.51% of the total household income, and the women undertake 72% of the agricultural work, that is, the women earn 3976 yuan every year. After the implementation of the project, the women will lose a small portion of their income but they will get more job chances through more business activities. The villages are formulating rehabilitation plans, which will be renewed in the later reports.
20
Resettlement Plan of Shaanxi Weinan Luyang Integrated Saline Land Management Project
4 LEGAL FRAMEWORK AND POLICIES 4.1 Laws, Regulations and Policies Applicable to Resettlement
42. The resettlement policies of the project have been developed in accordance with the relevant laws, regulations and policies of the PRC, and ADB policies, including:
Policies of ADB