<<

ACTION MEMO

AC TRANSIT DISTRICT GM Memo No. 07-209 Board of Directors Executive Summary Meeting Date: September 19, 2007

Committees: Planning Committee Finance Committee External Affairs Committee Operations Committee Rider Complaint Committee Paratransit Committee

Board of Directors Financing Corporation

SUBJECT:

Consider receiving semi-annual report and update on the Transbay Terminal Project

RECOMMENDED ACTION:

Information Only Briefing Item Recommended Motion

1. Receive update on progress of Transbay Terminal project i. Consider designs for ii. Consider designs for Bus Storage Facility iii. Consider designs for Temporary Terminal

2. Review Transbay Joint Powers Authority (TJPA) Competition Jury Report recommending selection of Pelli/Hines team as Designer/Developer for Transbay Transit Center, consider supporting said recommendation and have the Board President send letter to TJPA.

Fiscal Impact:

BOARD ACTION: Approved as Recommended [ ] Other [ ] Approved with Modification(s) [ ]

[To be filled in by District Secretary after Board/Committee Meeting]

The above order was passed on ______, 2007.

Linda Nemeroff, District Secretary By

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 2 of 18

There is likely to be an increase in annual operating costs of an unknown amount resulting from increased rental charges, starting in 2014. The net deficit in Transbay services could be offset by a large but unknown increase in fare revenue. There will be a Capital contribution of about $50 to 60 million, net present value based on a 25 cent Passenger Facility Charge (PFC) paid over 35 years.

Background/Discussion:

Schedule:

• The project continues to proceed on schedule with construction on the new Transbay Transit Center starting in late 2009 and completion of the bus components in late 2013 or early 2014.

• The Temporary Terminal will begin construction in mid-2008 with completion and occupancy in 2009. Bus Storage may lag about six to 12 months behind Temporary Terminal occupancy.

Substantial progress continues to be made on delivering the Transbay Terminal project by the TJPA, of which AC Transit is a member agency.

As of July 2007, the TJPA has expended about $97 million for project delivery, of which about $59 million is for property purchases, $19 million for project engineering, $17 million for program management and $3 million for TJPA administration.

Next phase expenditures are estimated at about $13 million for the Temporary Terminal construction, $31 million for Bus Storage and an additional amount for required property purchases.

Project Description

As detailed in previous communications to the Board, the Transbay Terminal / Downtown Extension / Redevelopment Project consists of three key components:

ƒ A new, multimodal transportation terminal that will provide convenient and efficient connections among AC Transit, Muni, Caltrain, BART, , Samtrans, Greyhound, other transit operators, and the proposed high speed rail system;

ƒ An extension of Caltrain service from its current terminus at Fourth and Townsend Streets to a new underground terminal at the Transbay Terminal site; and

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 3 of 18

ƒ Establishment of a Redevelopment Area Plan designed to revitalize the Transbay Terminal area and alleviate blight by supporting transit-oriented development.

Funding status is as follows:

• Terminal – Including AC Transit facilities and Muni, Samtrans and Golden Gate areas, and bus ramps and bus storage. Also includes Temporary Terminal.

o Cost: $1 billion Status: Fully Funded

• Rail Extension – Including underground rail facilities, Transbay rail platforms, permanent bus depot, new 4th and Townsend rail station.

o Cost: $2.4 billion Status: Partially Funded

• Redevelopment Project – All development expenses and infrastructure improvements in 40 acre redevelopment area.

o Cost: $TBD billion Status: Internally Funded

The total updated project cost for the terminal and the Caltrain extension is about $3.4 billion (Year of Expenditure dollars). Cost of the terminal building (included in the $3.4 billion total) is about $1 billion (Year of Expenditure dollars).

The location of the facility is First and Mission, present site of the Transbay Terminal, pursuant to the interests of AC Transit and consistent with state law (AB 812; SB 916). The new, multimodal terminal will produce significant improvements in both the aesthetics and the comfort of transit, and it will be convenient, efficient and safe for passengers. Passengers will be able to quickly and easily transfer among all transit operators serving in a single location.

Pursuant to Legislative mandate, the facility will be designed to include the proposed California high speed rail system. It will provide shops, restaurants, and other uses designed to appeal to passengers, and contribute to the vibrancy of the area. The existing facility does not meet current seismic safety or space utilization standards; these deficiencies have been documented in the adopted Final Environmental Impact Statement (FEIS)/Final Environmental Impact Report (FEIR). The proposed project, which has been under development for more than ten years, is the result of strong public involvement, technical analysis, and political support.

AC Transit Facilities and Bus Operations

The adopted Terminal design provides for the expansion of Bay Bridge bus service to meet estimated year 2030 demand. This demand results in the operation of about 150

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 4 of 18 peak hour bus trips (up from about 100 currently). The project accommodates these vehicles in a single level, center platform facility where buses operate clockwise and passengers wait in an enclosed, conditioned waiting area. The design provides 30 stop locations on a 1,300 foot platform, an increase from the 23 stops that are currently used by AC, Muni and Westcat buses. Articulated buses will be accommodated at 26 of the 30 stop locations. Intercity buses will be located one level below street level on the mezzanine, adjacent to the rail waiting area. In phase 2 of the project, Caltrain and ultimately intercity high speed rail trains will be located in the lowest levels of the terminal in a six track facility.

Buses will access the terminal on a dedicated ramp structure leading directly into both bus levels, looping inside the terminal. Traffic simulations have demonstrated the ability of the ramps and terminal structure to accommodate post-2030 bus service demand levels. AC Transit also performed a full-scale demonstration of the terminal configuration in August 2005 at Alameda Point, testing the ability of the design to accommodate 145 bus departures in a one hour period. The test demonstrated successful functioning of the design.

The terminal building is intended to be a signature project for San Francisco and for the entire Bay Area. Three competing visions of the project ensure that the region and the transit operators will provide service in an attractive storefront for transit which would also have superior operational functionality.

Dedicated bus storage will be provided to AC Transit in the area under the I-80 freeway in San Francisco, between Second and Third Streets. Up to 70 AC Transit buses could be stored at this site between the morning and afternoon peaks, thus reducing the number of required deadhead trips to and from the .

Funding Scenarios

The Transbay Project has more than a billion dollars in committed funding, as follows:

Source Amount (in million $)

Bridge Tolls Regional Measure 1 $54 Regional Measure 2 $150

MTC Discretionary RTIP $28 AB 1171 $150

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 5 of 18

Local Sales Tax San Mateo Sales Tax $31 San Francisco Sales Tax $148

Land and Tax Increment Land Sales $360

Loans TIFIA (secured with tax increment, etc) $512

Federal SAFETEA-LU $56 FTA Section 1601 (TEA-21) $11

Total Committed Revenues $1500

There are also other revenues that have been identified but not committed:

High Speed Rail Bonds $475.0 Passenger Facility Charges $873.0 Prop 1B, 1C Infrastructure Bonds $TBD

These revenues are neither discounted nor escalated, and would allow the TJPA to obtain a loan to bridge the funding gap and also bring future funding (such as land sales and tax increment revenues) forward. A portion of the PFCs are proposed to be derived from AC Transit passengers.

Land Sales and Tax Increment

In July 2003, the TJPA entered into a Cooperative Agreement with Caltrans and the City and County of San Francisco that will transfer right-of-way in the Transbay Terminal area from state ownership to City and TJPA ownership. Redevelopment of this right-of-way is expected to help achieve the goals of the Project, including improving the area’s economic vitality and providing funding for the Project. Pursuant to the Agreement, all sales proceeds from the property transfer will be dedicated to the terminal project, as will all tax increments generated by the new land uses. The California Transportation Commission is expected to consider approval of the land transfer agreement later this year.

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 6 of 18

Ridership Study

Under a contract with the Water Transit Authority (funded by TJPA, AC Transit and MTC), Cambridge Systematics has been revising ridership forecasts for the Bay Bridge Corridor covering BART, AC Transit and ferry services, as well as automobile trips. In addition, under a separate contract with the TJPA, Cambridge Systematics has been providing updated information on ridership in the Peninsula Corridor, both for Caltrain and for BART, as well as bus services.

The model improves on the existing MTC models in several ways:

• It provides a peak hour estimate, which the current MTC model does not provide.

• It provides an interactive feature allowing diversion from crowded modes to less crowded modes.

For many years, AC Transit staff has requested MTC to revise its model to recognize inherent capacity limits on BART. The effort undertaken by Cambridge Systematics adds another layer on the MTC model that recognizes crowding and changes the overall estimates accordingly.

Under federal New Starts regulations, all ridership forecasts must be based on the adopted regional population and employment forecasts. In the Bay Area, the Association of Bay Area Governments (ABAG) creates the population and employment forecasts (which are adopted by the ABAG Board) , and MTC then creates its travel model using the ABAG forecasts. ABAG’s Projections 2005 is the current basis for Bay Area travel demand. Under the Projections 2005 scenario, San Francisco employment is projected to increase by about 230,000 jobs by 2030, or about 10,000 jobs per year. Housing production is not expected to increase as quickly, leading to an increase in “commuters” – those employees who live outside of San Francisco but work in the City. Under the ABAG forecasts, virtually all the increase in out-of-county employees is from the East Bay. It should be noted that San Francisco employment increased by about 50 percent during the 1960 to 1990 period – and ABAG’s growth projections from 2005 to 2030 forecast a 40 percent growth over this 25 year period.

Using these baselines, Cambridge Systematics provided 2030 and 2015 ridership forecasts, both for daily trips and for one-hour, peak direction afternoon trips. (2030 is the design year for the Transbay Transit Center). Design year means the facility is designed to meet demand in a designated year.

Bay Bridge Corridor – This corridor is currently the region’s most robust transit corridor with afternoon transit use approaching 18,000 passengers in the peak hour, eastbound direction. While there is capacity on the transit system, the Bay Bridge is at capacity. As can be surmised, by 2030 the corridor will be in crisis, as the available transit capacity will

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 7 of 18 be used. The ridership forecasts predict a doubling of transit demand in the afternoon peak hour.

Bay Bridge Corridor Year 2005 - Observed Year 2030 Mode Peak Hour All Day Peak Hour All Day

BART 14,000 150,800 26,800 227,200 AC Transit 2,980 11,000 7,800 24,000 Ferries 460 3,300 2,000 11,000

Total Transit 17,440 165,100 36,600 262,200 Auto Demand 9,700 267,950 10,900 284,000

Total peak hour transit demand in the afternoon peak hour is expected to approach 37,000 passengers – critically challenging the current system. BART is expected to deliver 27,000 to 28,000 East Bay bound afternoon peak hour passengers, and AC Transit is expected to provide 7,100 to 7,800 trips. Ferries are limited to about 2,000 afternoon peak hour trips. BART ridership doubles in the peak hour and AC Transit ridership almost triples.

Cambridge Systematics, working with BART and AC Transit staff, developed estimates of high and low capacities for BART and AC Transit. BART was assumed to have a capacity of at least 28,000 one way trips in 2030 and a high capacity of about 32,000. AC Transit was assumed to operate 120 to 175 bus trips in a comparable period. For 2015 BART was assumed to have capacity of at least 24,000 (about the same as today), and a high capacity of about 28,000.

Since the model takes the perception of “crowdedness” into consideration, the 2030 model assumes that BART never exceeds 28,000 passengers, even with a capacity of 32,000. As trains become more crowded, passengers perceive more discomfort and they move onto buses and ferries. In any case, even with the higher BART capacity of 32,000, bus ridership only declines by about 700 passengers in the peak hour. It should also be noted that the model continues to add some afternoon peak hour vehicle trips to the Bay Bridge, which the bridge cannot accommodate, so the model is likely underestimating transit use.

Cambridge Systematics also developed estimates of total BART activity at Embarcadero and Montgomery Stations. In the afternoon peak hour, both stations together are forecast to exceed 31,000 boardings and alightings in all directions – or about 15,000 per hour at each station. Only 14 BART stations today exceed the forecast hourly weekday number all day long.

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 8 of 18

The consultants also forecast patronage in 2015, as follows:

Bay Bridge Corridor Year 2005 - Observed Year 2015 Mode Peak Hour All Day Peak Hour All Day

BART 14,000 150,800 19,200 172,300 AC Transit 2,980 11,000 6,000 18,400 Ferries 460 3,300 1,500 9,400

Total Transit 17,400 165,100 26,700 200,100 Auto Demand 9,700 267,950 10,900 275,000

These 2015 forecasts will be used to establish an estimated revenue stream for the Transportation Infrastructure Finance and Innovation Act (TIFIA) passenger facility charges analysis.

All of the Bay Bridge Corridor forecasts were thoroughly vetted with AC Transit, BART, WTA and MTC, and the parties agree on the appropriateness of the results. It should also be noted that the overall forecast increase in BART patronage (about 1.5 to 2.0 percent annually) mirrors BART’s passenger growth over the last 15 to 20 years.

Peninsula Corridor and High Speed Rail – TJPA also commissioned Cambridge Systematics to develop new estimates of Caltrain ridership into Transbay Terminal, and separately the consultants also developed forecasts for the proposed statewide high- speed rail system into San Francisco.

By extending Caltrain, that system would increase downtown San Francisco ridership by about 74 percent. In addition, should a high speed rail system be built, Cambridge Systematics estimated that about 24,000 passengers daily would use it from Transbay Terminal.

Peninsula/Caltrain Corridor Year 2030 Year 2005 TTC/DTX Year 2030 Observed Project No Project Mode All Day All Day All Day

Caltrain DTX Transbay 30,700 4th & King 14,200 6.500 21,100

Total 14,200 36,750 21,100

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 9 of 18

Total Transbay Transit Center Use – The following chart lists the total activity at the Transbay Transit Center forecast for year 2030. These forecasts include the work performed by Cambridge Systematics for both the Bay Bridge Corridor and Caltrain extension, and independently for the California High Speed Rail Authority. Also included are estimates of intercity bus use and Muni’s Treasure Island bus service from other sources.

Daily and Peak Hour Usage of the Transbay Terminal

Mode Daily Peak Source Hour

AC Transit 23,100 7,800 Ridership Analysis Muni – Treasure Island 6,400 580 Treasure Island Transportation Plan Intercity 1,450 200 Transbay EIS/EIR Caltrain 30,700 4,200 Ridership Analysis HSR 24,000 3,400 CAHSR Study

Total 85,650 16,180

Analysis – These passenger forecasts demonstrate the clear need to increase transit capacity into downtown San Francisco to support the region’s most dense job location and the economic growth associated with the central business district. The Transbay Transit Center provides the only reasonable short-term capacity increase through an expanded bus terminal for East Bay – San Francisco trips. By 2030 BART capacity will be severely taxed. A new Transbay Transit Center will provide crucial transportation capacity by providing a larger and more efficient terminal for East Bay buses.

With more than 8,000 passengers hourly (AC Transit, Westcat and Muni Treasure Island), about 160-175 bus trips will use the terminal in a one hour period – a 75 percent increase from the present. The ridership forecasts indicate that the Transbay Transit Center bus program is a high priority and that the rail components of the Transbay project will be required as a further step in expanded regional transit capacity.

Progress Since Last Update

In September 2006, staff reported on the project’s progress. At that time, TJPA staff had just been authorized to phase the project after a six month delay by TJPA Board inaction. Substantial progress has been made since then as follows:

Temporary Terminal – During construction of the permanent facility, AC Transit buses must be operated from a temporary facility. This project is on the “critical path,” meaning

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 10 of 18 that it must proceed prior to construction of the new permanent terminal, and that any delay to the Temporary Terminal will delay the permanent facility.

In April 2007, the TJPA awarded a design contract to Carter-Burgess of Oakland to design the new Temporary Terminal. The design period is extremely short and the final design must be completed and ready for bid by March 2008. Construction bids would be awarded by November, with construction starting immediately, and completion in August 2008.

The Temporary Terminal will be located a block to the southeast of the current terminal (on the block of Howard, Main, Beale and Folsom). TJPA program management staff developed an initial site plan with Greyhound occupying the southern third of the block and AC Transit (with Westcat) in the upper two-thirds. Carter-Burgess revised and improved this plan –under the revised plan, a total of 17 boarding positions are provided and AC Transit would have 16 boarding locations; Westcat would have one. This contrasts with the current 22 boarding locations that are used by AC and Westcat. In addition, there is one drop-off location versus the multiple alighting locations currently provided in the terminal.

In addition to the reduction of five positions, eight of the boarding locations are provided on a center island, requiring passengers to cross an active bus roadway. Finally, access to the Temporary Terminal is via city streets requiring transit priority measures and active enforcement. Bus staging is also limited.

The current design was simulated at Alameda Point (former Alameda Naval Air Station) on Wednesday, June 27, 2007. While the simulation demonstrated that the facility would be able to accommodate the current Transbay schedule, it also revealed that there would be little excess capacity. The simulation also determined that to ensure reliable service would require at least 15 supervisors, which represents an increase of eight from the current schedule. The large number of supervisors is required because of multiple and conflicting turning movements, limited capacity inside the terminal, and movements on city streets, as well as duties associated with the off-site storage facility. By contrast, the permanent terminal is extremely efficient and would likely require fewer supervisors than the District currently uses. These positions have not yet been budgeted but staff will request authorization from the Board at the appropriate time. In addition, with the reduction of five bus boarding locations, staff has estimated that dwell times within the terminal must not exceed four minutes. Should the dwell times become longer, theoretical delays (schedule failures, i.e., two buses are trying to load at the same location) would increase. The analysis indicates that when seven or eight trips use one bus stop in an hour and dwells exceed four minutes, that stop will have a 40 percent failure rate. At least one-third of the locations would have this level of activity and would fail if dwell times exceed four minutes.

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 11 of 18

Fare collection represents the largest component of dwell time. Studies indicated that MCI coaches require eight seconds per passenger to load – or about eight minutes. Staff tested a “Translink-only” option, where passengers would tag and then sit down. This option requires four seconds per passenger and would meet the dwell time requirements. In addition, it should be noted that a “platform-prepaid” option, where passengers are required to have a valid paid ticket before entering platform and then enter the bus freely, would require about three seconds per passenger for an MCI bus.

Under no scenario can staff recommend allowing cash fares in the Temporary Terminal. Accordingly, staff recommends that in the Temporary Terminal cash fares be prohibited and that Translink or a vended ticket be the only payment options. Under this scenario, ticket vending machines would be located at several locations prior to entering the terminal.

Bus Storage – Another major component of the new Transbay Terminal is the permanent bus storage facility. This facility would provide not only midday storage of up to 70 buses, it would also provide a reservoir for afternoon buses arriving from the East Bay prior to departure.

The bus storage facility will be located under the I-80 freeway structure in San Francisco between 2nd and 3rd Streets; Golden Gate Transit will have a slightly larger facility between 3rd and 4th Streets. The basic concept provides for both storage and a staging and recirculation area as buses return in the afternoon from the East Bay. Staff anticipates that with a dedicated Transbay Fleet (as proposed in GM Memo 07-0140a), Transbay buses would still provide some supplemental services as necessary. As these buses return from the East Bay in the afternoon, their arrival times in San Francisco will vary depending on Bay Bridge traffic, which is random and erratic. When the bridge is operating well, buses can arrive up to 30 minutes early, and there needs to be an area to store them. In addition, should the terminal need to be closed due to an emergency or threat, the buses need to be diverted into a safe and operational area.

The design effort is complicated by the need to work extensively with the surrounding community, as the impacted party, and with Caltrans, as the property owner. To that end, the various options considered include the option to use the area for other uses and events when buses are not stored or staged there – generally after 6:30 pm on weekdays and all day on weekends. Automobile parking, community services and other uses that are neighborhood-compatible and that are allowed under Caltrans right-of-way standards are being considered. Many of these uses could generate additional operating revenue for the Terminal.

Permanent Terminal – In June 2006 (seven months after the staff proposed the phasing plan and the selection process), the TJPA Board approved the criteria for a design/development competition (D/D) to select a team to design the new Transbay Transit Center and the associated ramps and plazas.

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 12 of 18

On November 1, 2006, TJPA solicited internationally for qualified Design/Development teams. The selection process consists of two stages. In Stage 1, consolidated design and development teams, consisting of the architectural and engineering team with a qualified and experienced developer, submitted statements of qualifications to the TJPA for consideration. A jury of seven professionals reviewed five submittals, and recommended four teams to proceed to Stage 2, the formal design competition. It is important to note that the intent of the process is not to select a design, but to select a designer. The design represents the designers’ opportunity to showcase ideas and concepts, and to demonstrate their ability to deliver a world-class project.

As the four teams proceeded to the design competition, one team (Boston Properties- Calatrava) withdrew, leaving three teams.

The three final teams are:

• Pelli Clarke Pelli Architects and Hines • Richard Rogers Partnership and Forest City Enterprises with MacFarlane Partners • Skidmore Owings and Merrill and Rockefeller Group Development Corporation

The three finalists presented their design concepts for the million square foot transit center and adjacent transit tower to the TJPA Board of Directors on August 6, 2007. In addition, the public was able to view the proposals on August 7 and August 8, 2007 at City Hall in San Francisco, and then again from August 27 through September 16th 2007 in the Grand Lobby of the Yerba Buena Center for the Arts at 3rd and Mission Streets.

As part of the competition process, the TJPA issued a set of scoping documents that provided guidance to the teams as to program and functional requirements. AC Transit’s interest was in the bus components, and the scoping documents provided for the previously noted program, i.e. a single level 1300 foot bus deck for use by AC Transit and other regional operators. This deck provides for 30 bus bays and includes internal recirculation.

Each team proposed slightly different approaches to the project.

Pelli Clarke Pelli Architects and Hines summarized their concept as follows (edited for length):

Our Transbay Transit Center architecture is open, full of light and clean air, and environmentally sustainable. It is also functional, a pleasure to use, and adaptable to future needs. It is designed to be the centerpiece of a new neighborhood. As such, we propose transforming the roof of the Transit Center into a public park––City Park. The 5.4 acre City Park is accessible and inviting, complete with the attractions

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 13 of 18

and activities that characterize great urban green spaces. The park also actively improves the environment around the Transit Center, absorbing pollution from bus exhaust, treating and recycling water, and providing a habitat for local wildlife. Sustainability is at the heart of our proposal.

Our Transbay Tower is a slender, graceful and beautiful icon. It is a simple and eternal form, like an obelisk, marking the location of the Transit Center against the San Francisco sky. At its base is Mission Square, a grand public space sheltered under a flowing glass and steel canopy, that forms the ceremonial entrance to the Transit Center. The Tower balances the richness of design of the Transit Center. The perimeter structure of the Center is sculpted like branches of a tree, covered with glass that waves like the petals of a flower. The Transit Center is infused with natural light coming through Light Columns that also open views of the sky and the trees of City Park to all users.

The Pelli Clarke Pelli Architects and Hines proposal generally conforms to the scoping documents pertaining to bus operations. The developer, Hines, offered $350 million to the TJPA for the rights to build the signature tower. The jury gave a score of 90, and a first place ranking, to the Pelli-Hines team.

Richard Rogers/Forest City/MacFarlane summarized their concept as follows (edited for length):

Designed by world-renown 2007 Pritzker Prize winning architect Richard Rogers, the open, light-drenched transit center will be a natural gateway, welcoming visitors and daily commuters into the city. With its irresistible blend of local and destination retail, fresh food markets, and cafes and restaurants, the Transit Center will create a new public realm, bringing a 24-hour vitality and cohesiveness to an emerging neighborhood in our great city. Chairs, benches, natural light, trees and continuous movement and bustle will all serve to animate and humanize this grand public space and reflect the city's inclusiveness.

The transparent, multi-use, 82-story Transbay Tower will define the city's skyline for decades. While the elegant tower will rise 1,000 feet into the sky, it will be dramatically set back at street level to create a large, welcoming public plaza. Crowned with a visually striking, working wind turbine that will create useable energy, the progressive green-design will be a model of environmentally sound, energy efficient sustainability. The Transbay Tower will be as practical as it is beautiful. Combining destination and local retail, office space, hotel rooms, condominiums, and affordable housing, the Tower, with its community spaces devoted to education and culture will be a microcosm of the city and bay region itself.

The Richard Rogers/Forest City/MacFarlane proposal generally conforms to the scoping documents pertaining to bus operations. The developer, Forest City, offered $145 million

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 14 of 18 to the TJPA for the rights to build the signature tower. The jury gave a score of 72, and a second place ranking, to the Rogers/Forest City team.

The Skidmore Owings and Merrill and Rockefeller Group Development Corporation summarized their concept as follows:

The SOM|RGDC proposal will improve transit operations, reduce annual operating costs and radically reduce the emission of climate-changing carbon dioxide. This is achieved by creating a double deck bus platform; effectively reducing its length by two city blocks. SOM has used this opportunity to create two dramatic civic gestures: a light-filled Transbay Hall, equal in scale to the central Vanderbilt Hall of Grand Central Station, and a full block Performing Arts Park. SOM’s Transbay Tower, a mixed-use tower 1200 feet to the top floor, is equally bold. The first full floor is lifted 100 feet above a full block urban plaza at , creating a civic portal to the Transbay Hall. The Tower includes retail, cultural uses, office space, boutique hotel, condominiums and a publicly accessible sky room. The Tower’s unique form tapers as it reaches the sky, accommodating the uses held within. Atop the Tower are state-of-the-art wind turbines which, combined with its photovoltaic crown, reduces annual energy consumption by 74%. The project includes a partnership with SFMOMA for a major digital arts program and with the California State Library to house the Sutro Collection.

SOM’s Transbay Transit Terminal and Tower represent the highest level of environmental stewardship ever achieved in a major urban mixed-use project. The project’s combined reduction in emissions, over a conventional design, will be over 176,000,000 pounds of carbon dioxide over a ten-year period. The Transit Center will achieve LEED Platinum and the Tower LEED Gold and possibly Platinum. Both are designed to the highest levels of safety and security which will allow it to withstand a “2500 year” earthquake and other security concerns. The project harvests rainwater, reducing the burden on the city’s infrastructure. The project makes extensive use of natural ventilation and natural light contributing to dramatic reductions in energy by harvesting solar and wind power.

The developer, Rockefeller, offered $128 million to the TJPA for the rights to build the signature tower. The jury gave a score of 61, and a ranking of third, to the SOM/Rockefeller team.

AC Transit staff believes the Skidmore Owings and Merrill and Rockefeller Group Development Corporation proposal does not conform to the scoping documents pertaining to bus operations. The SOM proposal to create a split-level bus operation results in substandard bus operations and inevitable inconvenience to passengers. Staff disagrees with the SOM assertions that operations would improve – in fact, operations would be compromised as management and supervision of the terminal would be on two levels, operations would be constrained through narrower bus circulation areas, internal

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 15 of 18 ramps would limit movement and create blind turns, passenger flows would be compromised and the transfer to Muni buses would be substantially degraded.

Jury Recommendation – On September 10, 2007 the TJPA issued the Jury Recommendations. As noted, the Competition Jury recommended the team of Pelli Clarke Pelli Architects and Hines. The vote was unanimous. AC Transit staff concurs with this selection for the following reasons:

• The Pelli/Hines proposal offers far and away the greatest compensation for the Tower site, significantly strengthening the TJPA’s financial position. The total amount of compensation that Hines has offered to the TJPA for the right to develop a signature tower is $350 million – more than twice as much as the next highest ranked team.

• The Pelli/Hines proposal offers a developer that is experienced in San Francisco and has unequaled national experience and financial resources.

• The Pelli/Hines proposal creates a significant and important architectural statement and provides important amenities for San Francisco and San Francisco commuters.

• The Pelli/Hines proposal creates an efficient and well-designed bus transit operational area, and comfortable and clear passenger waiting areas, wayfinding and circulation.

Should the TJPA Board approve the jury recommendation, the TJPA would enter into two sets of negotiations with the Pelli-Hines team: One contract would award a design contract for the transit terminal to Pelli Clarke Pelli Architects, and the TJPA would be the owner and responsible for the delivery of that project. The other contract would be between Hines and the TJPA with Pelli Clarke Pelli Architects as the listed designer for the signature Transit Tower. It is expected that negotiations with both entities will require about five months, although the tower negotiations are dependent upon the City rezoning process, which is an 18 month effort. In the meantime, Hines and the TJPA would agree on a term sheet.

At a minimum, for the right to develop the tower Hines will be required to provide funding to the project, as well as the proposed Winter Garden linking the Tower with the Transit Center, retail and concession uses on the first two floors and other related considerations.

It should be noted that the City & County of San Francisco is engaging in separate but interrelated study of heights in the terminal area. The current height limit at the Transit Tower site is 550 feet, and a tower that size was certified in the FEIS/EIR. The Redevelopment Agency Design for Development suggested a larger tower, up to 850 feet, and a tower that size requires a new environmental process, as well as studies of

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 16 of 18 wind and shadows. Since this work needs to be performed anyway, the City will also study taller towers, and all the competition submittals featured towers of about 1200 feet. It is anticipated that the tower will exceed 1000 feet after all the studies are performed.

Permanent Terminal Operating Costs/Capital Contribution – Unlike Caltrans, the TJPA has no independent funding sources for terminal operations other than a specified statutory allocation from bridge tolls. That allocation is about $3 million annually, with annual inflationary adjustments. In addition, concession revenues will generate some funding, although that amount is unknown at this point. It is likely that the bridge tolls and concession revenues will be inadequate to fund the Terminal operating expenses. The TJPA has engaged a consultant to estimate these expenses and the associated revenues. Once that study is finalized staff will have a better understanding of what the shortfall may be.

Staff also notes that the FEIS/EIR assumes a “passenger facility charge” of about 25 cents per passenger (year 2000 dollars) to provide a capital contribution to the terminal project. AC Transit did not object to this charge in our comments on the FEIS/EIR. The net present value of this charge would be about $50 to $60 million (year 2010 dollars).

Policy decisions concerning increased rentals and capital contributions will be forwarded to the Board for consideration as more information becomes available. Staff expects the TJPA to begin outlining a “Lease and Use Agreement” in the next few months, to memorialize all aspects of the tenant-landlord relationship that will exist with the construction of the Temporary Terminal and change in ownership from Caltrans to the TJPA. The agreement will likely be modeled on similar agreements between airports and airlines, but the staff position is that in any agreement AC Transit will be the primary tenant of the upper deck bus facilities, and should control and manage that portion of the facility.

Rail Elements – Preliminary engineering work continues to proceed on the Caltrain Downtown Extension project. The TJPA engaged in a “value management” process, using a panel of independent experts in train operations and tunneling construction methods. The purpose of the process was to identify and evaluate at a conceptual level potential design, construction or program scope changes in the rail program that could reduce construction cost while maintaining operational and quality standards. After review by the TJPA staff, a follow-up report determined that there were opportunities to significantly reduce the construction costs for the rail extension. The major recommendation was the elimination of the non-revenue “tail tracks” which extend east of the station. The panel instead recommended that the rail system be reconfigured as a “loop” system to allow through movements of trains, greatly increasing the capacity of the rail facility. Since the loop was not studied in the FEIS/EIR, the TJPA Board authorized the staff to proceed into a supplemental environmental analysis on the loop plan. As noted before, the rail extension is not fully funded.

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 17 of 18

Finally, progress continues to be made on the possible alignment of an underground connection to the BART stations on Market Street. Several possible alignments are under consideration, but the two most promising are from the far east end of the Transit Center under Beale Street to , or a tunnel that cuts diagonally from the Transit Tower under First and Mission, then directly under the proposed Renzo Piano designed building at First and Mission, then via Ecker Street alley to Montgomery Station. Studies with BART are continuing on these alternatives.

Fremont Street Ramp

GC Memo 07-103 summarized a March 2007 meeting between AC staff and Caltrans staff concerning the transition from the existing Caltrans facilities into new TJPA facilities, and coordination issues with the Caltrans West Approach project. That memo said:

Caltrans also inquired about the desirability of demolishing the temporary Fremont off-ramp, which is located on the right of way for the removed block-and-a-half of bus ramp. Caltrans has scheduled the demolition of this structure for March 2008, at their cost, unless advised otherwise by April 30, 2007. AC Transit staff is investigating using this temporary structure to re-circulate buses during the afternoon peak period;– that analysis is on-going with the SF MTA traffic engineers with a resolution expected by the end of April. Should it be feasible and desirable to use this facility, then the demolition costs would be borne by the Transbay Terminal project at the appropriate time.”

In April 2007, AC Transit staff tested the use of the temporary Fremont Street ramp as a means to re-circulate buses. The demonstration indicated that with small physical modifications including some re-striping, the new routing could work and save as much as five to ten minutes as buses re-circulate in the afternoon. In late August, 2007 SF MTA traffic planning staff responded that they would not re-stripe the lanes, but would allow AC to use the ramp at our responsibility and with Caltrans concurrence. This is an effective “no,” and since the ramp would only be used until AC moves into the Temporary Terminal in two years, staff will inform Caltrans that we do not intend to proceed with using the temporary Fremont Street ramp.

Next Steps

The next steps for the project include continued oversight of the Temporary Terminal and Bus Storage design process, as well as participation in the design of the permanent facility. In addition, staff expects to begin negotiations with the TJPA on elements of the Lease and Use Agreement in the near future.

Recommendation

GM Memo No. 07-209 Subject: Update on Transbay Terminal Project Date: September 19, 2007 Page 18 of 18

Staff recommends that the Board authorize the Board President to send a letter to the TJPA Board supporting the jury recommendation of the Pelli Clarke Pelli Architects and Hines design/development team.

Prior Relevant Board Actions/Policies:

GC Memo 07-103, April 18, 2007: Update on Transbay Terminal – Caltrans Mtg GM Memo 06-178, Sept 6, 2006: Semi Annual Transbay Terminal Report GM Memo 05-243, Dec. 7, 2005: Semi Annual Transbay Terminal Report GM Memo 04-120, April 7, 2004: Transbay Terminal Project Resolution 984C: A Resolution Identifying the Needs of AC Transit Regarding Various Issues Associated with a New Transit Terminal and a Temporary Transbay Transit Terminal Resolution 984D: A Resolution Approving in Concept a Joint Exercise of Powers Agreement, Bylaws, Design and Construction Agreement and Legislation Related to a New Transbay Transit Terminal and a Temporary Transbay Transit Terminal Resolution 1150: A Resolution Supporting the Phase II Study of Great Expectations Alternative for a Multi-Modal Transit Facility at the Site of the Transbay Transit Terminal

Attachments:

Attachment A: TJPA Jury Recommendation Attachment B: Recommended Letter to TJPA Board Attachment C: Terminal plans from Competing D/D Teams

Approved by: Rick Fernandez, General Manager Nancy Skowbo, Deputy General Manager, Service Development

Prepared by: Anthony Bruzzone, Manager Service and Operations Planning

Date Prepared: September 13, 2007

GM Memo 07-209 Attachment B Page 1 of 2 September 19, 2007

The Honorable Chair, Transbay Joint Powers Authority 210 Mission Street, Suite 1960 San Francisco, California

Dear Chair Hill:

This letter is in reference to Item Number 8 on the TJPA Board of Directors calendar for September 20, 2007 concerning the selection of a Design and Development team for the Transbay Transit Center project.

The Alameda-Contra Costa Transit District Board of Directors has reviewed and considered the recommendation of the expert jury that was appointed by the TJPA Board to assist in selecting the winning team. We have carefully reviewed the jury’s detailed and thorough report.

The AC Transit Board of Directors fully supports the jury’s recommendation that the Pelli Clarke Pelli/Hines team be selected to enter into exclusive negotiations with the TJPA and urges the TJPA Board to adopt the jury’s recommendation.

We believe the jury’s recommendation is sound because:

• The Pelli/Hines proposal and concept creates an efficient and well-designed bus transit operational area, and comfortable and clear passenger waiting areas, wayfinding and circulation.

• The Pelli/Hines proposal offers by far the greatest compensation for the Tower site, significantly strengthening the TJPA’s financial position.

• The Pelli/Hines proposal offers a developer that is experienced in San Francisco and has unequaled national experience and financial resources.

• The Pelli/Hines proposal creates a significant and important architectural statement and provides important amenities for San Francisco and San Francisco commuters.

In addition, we understand that the Pelli/Hines team has a long history of working together and creating important structures in many major cities. We are also appreciative of Pelli Clarke Pelli’s reputation of delivering major projects on schedule and within budget. GM Memo 07-209 Attachment A

FINAL REPORT Process Summary & Jury’s Recommendation

TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition

10 SEPTEMBER 2007 STASTNYBRUN

BOARD OF DIRECTORS Dear Directors: TRANSBAY JOINT POWERS AUTHORITY As Competition Manager for the Transbay Transit Center & Tower Design & Development 201 MISSION STREET, SUITE 1960 Competition, I am pleased to report that the Jury has completed its tasks in accordance with SAN FRANCISCO, CA the rules and procedures in the Competition Manual adopted by this Board’s Resolution 94105-1858 06-013.

10 SEPTEMBER 2007 Through their individual and collective analysis, the Jurors evaluated and scored each Proposal by applying the Stage II Evaluation Criteria. The Jury’s ranking of the Proposals was unanimous, as follows:

1. Pelli Clarke Pelli Architects and Hines 2. Rogers Stirk Harbour & Partners and Forest City Enterprises with MacFarlane Partners 3. Skidmore, Owings & Merrill and Rockefeller Group Development Corporation

Therefore, the recommendation of the Jury to the TJPA Board is to invite Pelli Clarke Pelli Architects and Hines to enter exclusive negotiations with the TJPA for contracts to design the Transit Center and design and develop the Transit Tower.

The attached report entitled “Transbay Transit Center & Tower Design & Development Competition Final Report” summarizes the overall Competition process and provides a synopsis of the Jury’s analysis of the Proposals leading to their recommendation.

It is with extreme confidence in the work of this extraordinary Jury that I forward their recommendation to you for your consideration and action.

Sincerely,

STASTNYBRUN ARCHITECTS INC.

DONALD J. STASTNY FAIA FAICP COMPETITION MANAGER

ARCHITECTURE URBAN DESIGN PLANNING • INTERIORS COMMUNITY DESIGN PROCESS/COMPETITION MANAGEMENT STASTNYBRUN ARCHITECTS, INC. • 813 SW ALDER STREET, SUITE 200 • PORTLAND, OREGON 97205 USA TEL 503. 222. 5533 • FAX 503. 227. 5019 00 TABLEOFCONTENTS 1 1 1 0 0 " 0 0 0 0 03 02 01 2 1 0 9 8 7 6 5 4 DESIGN&DEVELOPMENT STAGEIIEVALUATIONCRITERIA STAGEII COMPETITIONS JURY’S APPENDIX COMPETITION MANAGER COMPETITION JURY SCORES, RANKING&RECOMMENDATION TECHNICAL REVIEWOFPROPOSALS MATERIALS &INFORMATIONPROVIDEDTOTEAMS OVERVIEW OFTHE INTRODUCTION Question &Answers Request forProposals Competition Man Pelli ClarkeArchitectsandHines Skidmore Owings&Merrill Rogers StirkHarbour&PartnersandForestCityEnterprises Pelli ClarkeArchitectsandHines Skidmore Owings&Merrill Rogers StirkHarbour&PartnersandForestCityEnterprises Rockefeller GroupDevelopmentCorporation with MacFarlanePartners Rockefeller GroupDevelopmentCorporation with MacFarlanePartners STASTNYBRUN ARCHITECTS, INC. REPORT PREPAREDBY EVALUATION OFP SUMMARY

ual

CHEDULE

D

and and

/ D COMPETITION

ROPOSALS PROPOSALS Transbay Transit Center & Tower Design & Development Competition

52 49 43 42 24 21 11 24 12 36 30 1 15 3 8 6 4 2 1 8

TABLE OF CONTENTS 7 0 0 2 10 3

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition FINAL REPORT • Table of Contents

n Dvlpet em “/ Team”) (“D/D Team Design Development a and select to Competition tional interna an launched (“TJPA”) Authority Powers Joint Transbay the 2006, June In INTRODUCTION 00 Jury impaneledbytheTJPABoard. the analysis and recommendation of the TJPA’s Request for by Proposals (“RFP”), and the submitted to response in Teams D/D three the Proposals the Competition the process, describes report This Bay Area,andtheStateofCalifornia. the Francisco, San for transit rail and bus of focus the and Area Redevelopment Transbay the of centerpiece the as tion posi their of worthy be would cellence ex technical whose and functional, Tower aesthetic, and Center Transit class D/D Team that would create a unique, world a sought TJPA The Center. Transit the to adjacent Tower a develop and design to and California, Francisco, San be developed by the TJPA in downtown to design a multi-modal Transit Center to - - - design for the Transit Center and Tower and Center Transit the for design Pelli/Hines The two. other the to superior sion that one Proposal, from Pelli/Hines, is (“SOM/ The Jury is unanimous, however, in its conclu exceptional. were Corporation – Rockefeller”) Development Skidmore, Group Rockefeller and Merrill & andOwings City”), “(Rogers/Forest (“Pelli/Hines”), City Enterprises with MacFarlane Partners Hines Rogers Stirk Harbour and & Partners and Pelli Forest Clarke PelliArchitects – Stage Competition RFP the of the in three participating the Teams by submitted Proposals The Transbay Transit Center & Tower Proposals. the Jury’s complete analysis of the three Please refer to section 08 of this report for than theoffersofotherTeams. higher significantly was Property Tower the for price purchase a of offer Hines’ and requirements, aesthetic and tional, func operational, TJPA’s the met best Design & Development Competition - - 7 0 0 2 10 1

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 00 • Introduction

signed in tandem. The site of the Transit the of site The tandem. in signed de be buildings the that required TJPA will Tower be large and complex structures, the and Center Transit the Because OVERVIEW OFTHED/DCOMPETITION 01 services for the Transit Center and Tower and Center Transit the for services architectural/engineering of scope The processes. teams selected by the TJPA though other other by constructed and designed be to are listed elements additional other The Competition. this through selected ramps will be the designed by the D/D Team only elements, facilities. additional these storage Of bus permanent and Center, Transit the to Bridge Bay the ing King, temporary bus terminals, and ramps connect Fourth at station surface ing exist the to modifications Station, Street Townsend and Fourth underground new a Center, Transit the to Streets King and Fourth from Caltrain extend to systems rail and tunnel rail the elements: ditional ad several includes which (“Program”), a larger Transbay Transit Center Program of part are Tower and Center Transit The and CountyofSanFrancisco. City the of authority the under process with the TJPA and during the entitlement Agreement Option Tower ne a of gotiation through determined be will Tower the in uses of mix The Center. Transit the retail, andcultural,thatwillcomplement office, hotel, residential, as such uses, of mix a contain could Tower The space. future administrative TJPA and space, the mercial trains, com leased Rail, High-Speed California commuter buses, accommodate will Center Transit new The Streets. Mission and First at Terminal Center and Tower is the existing Transbay ------“optto Mngr) Te process The Manager”). (“Competition by the TJPA to manage the Competition retained also was which Inc., Architects, StastnyBrun by TJPA the with tandem in designed was process Competition The the TJPAandselectedTeam. between negotiated be to Option Agreement the by and Team D/D winning the by submitted Proposal the by mined deter be shall development Tower the services. The financial and other terms administration of construction and ments, will include all design, construction docu Transbay Transitthe TJPABoard D/D Teams and ranked the Proposals for the by presentations oral and submittals Centerwritten the evaluated and reviewed als the of Transit Tower. development The same Jury and of profession design Center and Transit the of design the for als &propos submitted and prepared Teams D/D invited four Towerthe of three II, Stage In II four – RequestforProposals(“RFP”). Stage in approved, participation for Board Teams D/D TJPA the and recommended, Jury The Teams. D/D the qualifications submittals and interviewed the reviewed professionals, velopment de estate real and transportation, sign, de recognized of comprised Jury, The professionals. engineer development and design other and ing, architectural, of team full a and Tower, the for Entity Development a Tower, and Center Transit the design to Designer pack Lead a identified that ages qualifications submitted Teams – RequestforQualifications(“RFQ”),D/D I Stage In stages. two in conducted was Design & Development Competition ------

OVERVIEW OF THE COMPETITION 7 0 0 2 10 2

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 01 • Competition Overview

COMPETITION SCHEDULE 02 • • AGREEMENT AWARD • • • • • • • • • • STAGE II:REQUESTFORPROPOSALS(“RFP”) • • • • • • • • • STAGE I:REQUESTFORQUALIFICATIONS(“RFQ”) Transmitted toTJPA Final ReportwiththeJury’sRecommendation 8/06/07 Teams PresentedDesignstoBoardatPublicMeeting Jury PresentationsandEvaluations Submission ofProposals End ofQuestion&AnswerPeriod 2nd Mid-courseReview 1st Mid-courseReview Start ofQuestion&AnswerPeriod Stage IIBriefing 2/23/07 TJPA IssuedRFPandUpdatedCompetitionManual Announcement ofStageIResults Recommendation ofFourRespondents TJPA BoardApprovedtheJury’s Jury InterviewsandEvaluation Submission ofQualifications End ofQuestion&AnswerPeriod End ofRegistration Pre-Submittal Briefing 11/01/06 Start ofQuestion&AnswerPeriod RFQ Announcement&OpeningofRegistration for ExclusiveNegotiations 9/20/07 Announcement ofSelectedD/DTeam and SelectsaD/DTeamforExclusiveNegotiations TJPA BoardReviewsJury’sRecommendation

Transbay Transit Center & Tower Design & Development Competition 8/30/07 7/31/07-8/03/07 7/10/07 6/26/07 5/22-25/07 4/17, 18,20,23/07 3/01/07 3/01/07 2/15/07 2/15/07 1/29/07 –1/31/07 1/11/07 12/21/06 12/21/06 11/15/06, 12/7/06 11/01/06 9/20/07 7 0 0 2 10 3

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 02 • Competition Schedule

with the Stage I Evaluation Criteria and Criteria Evaluation the I Stage the with evaluated Jury The submittals and interviews in accordance RFQ. the responded Teams to D/D five I, Stage In STAGE II 03 rni Cne, n ohr requirements other and the Center, for Transit budget the Center, Transit for the requirements TJPA’s the describing Report Definition Scope the with Teams D/D the provided TJPA the time which at Teams, participating the for Francisco San in Briefing II Stage the hosted TJPA Property”). the II, Stage (“Tower of commencement the Tower At the the of for lease site ground or purchase for the terms financial proposed including development of and the Tower (“Proposals”), design Transit for Proposal the a a and of Center prepare design the to for Proposal required were Teams Manual. Competition updated and RFP 2007 23, the of Teams the February to distribution the with on began II Stage • • • • D/D TeamstoparticipateinStageII: four following the inviting ommendation, The TJPA Board approved the Jury’s rec (“RFP”). Proposals for Request – II Stage D/D Teams for invitation to participate in four Board TJPA the to recommended Corporation (“SOM/Rockefeller”) Rockefeller GroupDevelopment Skidmore, Owings&Merrilland City”) MacFarlane Partners“(Rogers/Forest and ForestCityEnterpriseswith Rogers StirkHarbour&Partners (“Pelli/Hines”) Pelli ClarkeArchitectsandHines Properties”) Properties (“Calatrava/Boston Santiago CalatravaandBoston SUMMARY - Technical Advisory Committee (TAC) in (TAC) Committee Advisory Technical the with reviews mid-course confidential had an opportunity to participate in two Team each time, that During Proposals. prepare to months 1/2 4 had Teams The Property. Tower the of lease ground or purchase the for proposals financial Teams’ the of comparison Jury’s the ease to proposals Forma Templates to present their financial Pro and Sheet Term Model a with Teams Competition Manager furnished the D/D the 2007, 12, April On Proposals. the for Transbayreview technical The site. Tower the for proposed terms and financial the Criteria Transitanalyzed Minimum TJPA’s the with compliance determine to Center Transit the for designs the of review technical a conducted Staff TJPA the and Manager Centerview. At the re same time, the its Competition for Jury the to Proposals the ted 2007 Manual, Competition the in & compliance for with the check Mandatory Requirements stated initial Tower an After the Competition Schedule. with accordance in Proposals ted Rogers/ Pelli/Hines, 2007, Forest City, and SOM/Rockefeller submit 10, July On the from Calatrava/Boston withdrew Competition. the Team 2007, Properties May In ality, andfinancialterms. function technical design, of discussion included Reviews The Proposal. each of functionality and feasibility the maximize to Teams the to feedback constructive provided reviews The consultants. TJPA and staff, Agency Redevelopment and staff, San Francisco Planning Department TJPA Manager, Competition the cluding Design & Development Competition the Competition Manager transmit n uy 12, July on - - - - -

COMPETITION SCHEDULE 7 0 0 2 10 4

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 03 • Stage II Summary

ie n wr bsd n h Scope Pro FormaTemplates. the on based Definition Report, Model Term Sheet and were and tive subjec not were analysis financial and h TP wbie uut 6-September 17, 2007. August website TJPA the on and 2007, 16, 27-September August Center Buena Yerba in 2007, 7-8, August Hall City on in comment were public for designs display The designs. the on comments public heard and Teams the in a public meeting. Directors questioned and Center Tower to the TJPA Board Transit of Directors the for design its sented pre also Team each 2007, 6, August On ranking oftheTeams. scores overall the determine Jurors’ to summed II were The Stage Criteria. the on Evaluation based Proposals the scored individually and Jurors presentations the all analysis, Following tion. ques Jury’s the to responded and the Jury to Proposals Each their presented discussion. Team analyzed group through and them individually submittals the studied Jurors The Proposals. the of analysis financial and review theirtechnical Proposals and Report theDefinition Scope and summarized staff and TJPA Manager 3, Competition August The through 2007. 2007 Francisco 31, San July in from convened Jury The - - -

Transbay Transit Center & Tower Design & Development Competition 7 0 0 2 10 5

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 03 • Stage II Summary

on thisCriteria.TheCriteriaisasfollows: Manual. The Jury Competition based were its evaluation and the ranking Criteria in Evaluation published II Stage The EVALUATION CRITERIA 0 h Tast etr te dniy f the of identity the Center, Transit the for design the develop to consultants its how of and TJPA the with work would Team the description a design, of final the completion for milestones detailed the Transit Center, a schedule containing for design completed the for to Team the pay would monetary TJPA the total compensation the including Center, Transit the for Agreement Design the for terms key propose should Respondents estimate ofdirectconstructioncost. should also concept be responsive to design the TJPA preliminary Center Transit The requirements. other and technical, operational, TJPA’s the satisfy to ability Scope the demonstrate design TJPA and Report, Definition the and in contained requirements criteria the meet The Transit Center design concept should and seismicstructuralsafety. user flow and accessibility, green design, context, transit community operational requirements, excellence, design image, architectural and Center; Transit the the to throughout uses its and Tower the of relationship the to given flowcare particular with complex, resident user requirements; and operational transit address should Proposal Center Transit The vibrant, neighborhood. a pedestrian-oriented promote will that uses level street the on emphasis particular place form of San urban Francisco. the The of part Proposal as should Tower and Center an understanding of the role of the Transit The Transit Center Proposal should reflect TRANSIT CENTERPROPOSAL(40%) 4 structural innovation, and demonstrate constructability. and seismic should design, green of integration concept design Tower Transit The Francisco. San of form urban the in plays Tower the role the of Center Transit design. It the should reflect an understanding to complimentary a and presentcompatible is that concept design should Proposal Tower The TOWER PROPOSAL(40%) individual their of responsibilities. description a and involved, be would that members Team Transbay be can that the a program demonstrates development forma submit that pro Transitdocumentation and financial should appropriate Respondents proposal. Center Tower the of feasibility financial partnership. overall and timing the the and TJPA the to public/private revenue of amount on focus will Jury the the The of of construction &years for initial the during primarily financial Program capital Towerfor proposed responsive to the Program’s requirement be should Program the Team’s to contribution The Report. Center, criteria contained in the Scope Definition Transit design and the requirements the meet and to access enhance the Center, public Transit should of the to concept relationship Tower the design demonstrate Tower The iconic an architectural image. create and neighborhood and Tower should be the Center focus of an evolving Transit The neighborhood. pedestrian-oriented vibrant, a promote will that uses and design level street the on emphasis particular place should It Design & Development Competition 7 0 0 2 10 6

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 04 • Evaluation Criteria

o te ein n Development and Design the for terms key the propose should Respondents finance to development oftheTower. resources sufficient capital has Team detailed the that include evidence should Tower Transit Respondent’s the of development the finance to plan The built. and financed in integratingthetwostructures. consideration fundamental a be should and the public Tower functions of the Transit Center the of functions public the conflict, Symbolic and and flow relationships between functions. ancillary and flows support all and pedestrian vehicular requirements, and massing and program the to adherence movement, Tower including user accessibility, people and functional technical issues of the Transit the Center and of understanding The Proposals should illustrate a thorough ISSUES (20%) FUNCTIONALITY ANDTECHNICAL their of description individual responsibilities. a and be would involved, that members identity Team the the of construction, final and the design of completion for milestones including a schedule containing detailed Tower, Transit the for Agreement Option

Transbay Transit Center & Tower Design & Development Competition 7 0 0 2 10 7

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 04 • Evaluation Criteria

ah em ih h sm sucs of sources information necessary to understand the same provided the with Team Manager each below, Competition detail the greater in discussed As PROVIDED TOTHED/DTEAMS MATERIALS &INFORMATION 0 h sxvlm Soe Definition Transit and Scope the for technical requirements operational the with containing six-volume Report Teams the the provided Manager Competition the briefing, that At 2007. 1, March on session briefing public a at of II Proposals) for (Request Competition Stage the in participating Teams the brief would Manager Competition the that provided Manual Competition The Stage IIBriefing Program other documents. and (EIS/EIR), Center Program Transit Transbay the for Report Impact Statement/Environmental Impact Environmental the posted TJPA already had the where website, Competition TJPA TJPA’s the The on documents these Criteria. posted Evaluation II Stage the included Manual Competition The Competition. the govern to Proposals for Request a and Manual Competition a developed Manager Competition The Website Competition Manual, RFP, & TJPA 8. 7. 6. 5. 4. 3. 2. 1. Tower, includingthe: and Center Transit the for criteria TJPA’s 5 Questions andAnswers Two Mid-CourseReviews templates Model TermSheetandPro-Forma Scope DefinitionReport Stage IIBriefing website Public documentsontheTJPA Request forProposals Competition Manual lrfcto o ad ute detail further and for requirements of TJPA’s the concerning sought of questions source The clarification the questions. the identifying website Competition and without the questions on the answers posted Manager Competition Manager. The Competition the to questions written submit to Teams The Competition Manual also allowed the Questions andAnswers illustrating theserequirements. presentation PowerPoint a and reports, geotechnical below), (discussed Center Transbay Transit3. Center2. & Tower1. Definition Report: Scope The operators. transit public and stakeholders among consensus by oped years, the EIS/EIR; and information devel pers prepared over the course of several Transbay Terminal Improvement Study working pa Commission’s Transportation nition Report drew from the Metropolitan sign of the Transit Center. The Scope six-volume Defi a Scope Definition Report to guide the de prepared (PMPC), team consultant Controls Program and ment Manage Program its through TJPA, The Scope DefinitionReport questions 62 and answers. of posting the in resulted the Transit Center and Tower. This process

Design & Developmentbaseline constructioncost estimate. sufficient detailtoestablisha Develops adesignconceptof the projectsite;and elements could be configured within Demonstrates thattheprogram CompetitionTransit Center; and functionalrequirementsforthe design standards,andoperational Establishes theprogramelements, - - - - - 7 0 0 2 10 8

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 05 • Materials & Info Provided to Teams

• • • • • The sixvolumesinclude: osrit ipsd y h transit the by imposed physical and constraints standards design the of most includes 2 Volume Center. Transit of Report design quality and performance Definition for the explains the TJPA’s general Scope expectations the Criteria, Minimum the establishing to addition In 7. 6. 5. 4. 3. 2. 1. are: Criteria Minimum The Criteria). (Minimum the minimum criteria for the Transit Center established Report Definition Scope The • Opportunities Volume 5:SustainableDesign Volume 4:SiteDesignGuidelines Standards Volume 3:DesignCriteriaand and Constraints Volume 2:DesignRequirements Volume 1:ExecutiveSummary and schedule. TJPA’s constructioncostestimate General conformancewiththe requirements; and the TJPA’sspaceneedsand General conformancewith Mission StreetattheTowersite; to theTransitCenterbuildingfrom A visualandphysicalconnection Beale StreetandFremontStreet; The easternbusplazabetween required bythevariousoperators; The numberandsizeofbusbays Passenger PlatformLevel; of thetracksonTrainStation The TJPA’sprescribedgeometry two-phase plan; Phase II,consistentwiththeTJPA’s construction ofthetrainstationin train stationinPhaseI,andthelater the foundationandboxfor portion oftheTransitCenterand completion oftheabove-ground A constructionplanthatallows Drawings Volume 6:ScopeDefinition o dcae pcfc architectural Criteria, Minimum the than to other specific respect issues does with Rather, Report dictate requirements. Definition not Scope The baseline a establish construction costestimate. to and Center Transit the of feasibility operational and TJPA consultants to validate the financial by prepared Building Center Transit the for configurations of drawings contains 6 Volume elements. design sustainable and design, site materials, construction Report describe the TJPA’s guidelines for operational design. Volumes 3, Center and 4, Transit and the 5 of of the demands Scope functional Definition critical Sections 2.0 and 3.0 of Volume 2 describe site. Center Transit the by and operators Transbay TransitReport. the exceeded guidelines laid or out in the Scope met Definition Proposal each Jury The Proposal. the carefully Centerconsidered the extent to which its of demonstrate aesthetic advantages and to operational, functional, required was however, Team, had Each Concourse. Teams the Terminal, & the significant latitude to the modify or even of omit Tower along length pedestrians the of addressed proposal movement a as long As alongthe longitudinal axis of the Transit Center. movement would pedestrian Report facilitate Definition Scope the of 2.1.4 Section 2, Volume in shown Level Concourse the example, that intended For TJPA the appeal. aesthetic and greatest efficiency, safety, convenience, that manner a the achieve would believed Team each in operations bus out lay the to also but interior envelope, building select exterior an to design and onlyfinishes building not free were and design layout guidelines. to The Teams latitude the organization, standards, the from depart had Team each and Teams that these guidelines were flexible the informed Manager Competition the Design & Development Competition 7 0 0 2 10 9

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 05 • Materials & Info Provided to Teams

he tu poie a eea lvl of level general a provided thus Sheet Term Model The Property. Tower the of to execute for purchase or ground lease exclusive negotiations for would selected Team be the expected that Agreement the Disposition and of Development Option terms the set Sheet Term Model The Templates Model TermSheet&Pro-Forma oslat. uig h Mid-Course the During consultants. and TJPA Department and staff, Agency Redevelopment Planning Francisco Committee (TAC) Advisory Technical a each and confidential Reviews, and meetings with the Competition Manager closed in Mid-Course met Team the In the MinimumCriteria. met Proposal Team’s each that ensure to Team each with Reviews Mid-Course that the Competition Manager hold two The Competition Manual further directed Mid-Course Reviews the financialproposals. of merit the analyzing of task Jury’s the easing considerably terms, financial of comparisons like-to-like make could Jury using uniform templates ensured that the proposals financial of submission Teams’ The Property. Tower the of lease ground or purchase a the for proposals financial prescribed framework for presentation Templates of the Teams’ The Pro-Forma Team. selected the and TJPA the between Project Tower the for contract the of terms material the to as certainty ossig f JA tf, San staff, TJPA of consisting xlie te hne o l Teams all to change the explained Manager Competition the requirements, resulted in a change to the Competition Competition Report. question specific a to answer Definition an the Where Scope and in Manual information on expanding or clarifying Teams the from also TAC questions to theanswers objective provided and Reviews, Manager Mid-Course Competition the During designing theTransitCenter. in discretion wide allowed were Teams Criteria. Minimum the the Criteria, Minimum the satisfying After meet to that failed Proposals the of aspects those to proposals design specific on Manager comments Competition strictly enforced a the policy limiting the TAC’s Reviews, Transbay Transit Center & Tower satisfied theMinimumCriteria. successful were insofar as the Proposals of all three Reviews Teams Mid-Course The Criteria. Minimum the met design a particular any design, validate, beyond commenting with on whether or preferences to, regard or opinions express not did TAC and Manager Competition In responding to questions, however, the through the Question and Answer process. Design & Development Competition 7 0 0 2 10 10

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 05 • Materials & Info Provided to Teams

borhood, provide a symbolic marker symbolic a provide borhood, neigh evolving an of point focal the as serve will that Tower and Center Transit Transbay a envisions TJPA The DESIGN &DEVELOPMENTPROPOSALS THE TRANSITCENTER&TOWER 0 y ah em n dsrb their describe respective proposal. and Team each by The following statements are provided of buildingsforSanFrancisco. its contribution to the next generation Competition. The Jury the applauds each D/D Team for to expertise class world and passion their commit fully to promise Teams’ the fulfilled ments interpretation of the Program require creative and unique Proposal’s Each public. the and Francisco San of City the high expectations of the TJPA, the meet to rose Teams D/D The City. the for for development private and excellence public design of standard for San Francisco, and establish a new 6 Rogers/Forest City SOM/Rockefeller top tobottom: Pelli/Hines - -

Transbay Transit Center & Tower Design & Development Competition 7 0 0 2 10 11

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 06 • Design & Development Proposals

xrse te er o 2s century tremendous 21st with Tower city of Francisco--a San heart and the Center the expresses for Transit vision uplifting Transbay and bold Our WITH MACFARLANEPARTNERS AND FORESTCITYENTERPRISES ROGERS STIRKHARBOUR&PARTNERS city’s inclusiveness. the reflect and space public grand this humanize and animate to serve all will bustle and movement continuous and trees light, natural benches, Chairs, city. to great our in neighborhood emerging an cohesiveness and vitality 24-hour a bringing realm, public new a create will Center Transit the restaurants, and cafes destination retail, fresh food markets, the and into city. With commuters its irresistible blend of local and daily and welcoming visitors gateway, natural a be will center transit light-drenched open, the Rogers, Richard architect winning Prize Pritzker 2007 world-renown by Designed San Francisco as the Golden Gate Bridge. transit center will be as glorious a portal to its emphasis on transparency, the regional exuberant waves of glass and steel, and its With solutions. conventional question to willingness a and creativity, diversity, sound, energy efficient sustainability. The sustainability. efficient energy sound, design will be a create model green- of environmentally progressive will the energy, useable that turbine wind striking, working visually a with Crowned plaza. level to create a large, welcoming public sky, it will be dramatically set the into feet back 1,000 rise will tower elegant at street the While decades. for skyline city’s the define will Tower multi- Transbay 82-story use, transparent, the meticulous reputation and craftsmanship, buildings international visionary his on who built Rogers, has Richard by designed As Transbay Transit Center & Tower fluid, a as forward collaborative effort. move will it -and imagination- the vision--a of leap extraordinary transformative an with begins Tower and Center Transit Transbay the bay architecture, great all and Like city itself. region the of microcosm a be will culture and education spaces to community devoted its with Tower, the housing, rooms, affordable and condominiums, hotel space, office retail, local and destination Combining beautiful. is it as practical as be will Tower Transbay Design & Development Competition 7 0 0 2 10 12

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 06 • Design & Development Proposals

Forest CityEnterpriseswithMacFarlanePartners Rogers StirkHarbour&Partnersand

Transbay Transit Center & Tower Design & Development Competition 7 0 0 2 10 13

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 06 • Design & Development Proposals

Forest City EnterpriseswithMacFarlane Partners Rogers Stirk Harbour&Partners and

Transbay Transit Center & Tower Design & Development Competition 7 0 0 2 10 14

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 06 • Design & Development Proposals

dul dc bs ltom which platform, bus deck creating by double achieved a is This carbon dioxide. annual climate-changing of emission reduce operating operations, costs and radically reduce the transit improve will proposal SOM|RGDC The DEVELOPMENT CORPORATION AND ROCKEFELLERGROUP SKIDMORE, OWINGS&MERRILL energy consumption by 74%. The project annual reduces crown, photovoltaic its with combined which, turbines wind art state-of-the- are Tower the Atop within. held uses the accommodating sky, the reaches it as tapers form unique Tower’s The room. sky accessible publicly a condominiums and hotel, boutique space, office uses, cultural retail, includes Tower The Hall. Transbay the to portal civic a creating Street, Mission at plaza urban block full a above feet 100 lifted is floor full first The bold. equally is floor, top the to feet 1200 tower mixed-use Transbay a SOM’s Tower, Park. Arts Performing block full a in and Station, of Central Grand Hall equal Vanderbilt central Hall, the to scale Transbay light-filled a gestures: civic dramatic two create to opportunity this used has SOM blocks. city two by length its reduces effectively osby ltnm Bt ae designed are Both Platinum. LEED possibly achieve and Gold LEED will Tower the and Platinum Center of Transit pounds The period. 176,000,000 ten-year a over dioxide over carbon be will design, conventional in a reduction over project. emissions, combined mixed-use project’s urban The major a of in level highest environmental and the stewardship ever represent Terminal achieved Tower Transit Transbay SOM’s Sutro Collection. the house with to Library State California and the program arts digital major a for SFMOMA with partnership a includes Transbay Transit Center & Tower and windpower. dramatic solar harvesting by energy in to reductions contributing light natural and ventilation natural of use makes extensive project The infrastructure. city’s the on burden the reducing rainwater, harvests project The other concerns. and security earthquake and year” “2,500 safety a of withstand to it levels allow will which security, highest the to Design & Development Competition 7 0 0 2 10 15

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 06 • Design & Development Proposals

Rockefeller GroupDevelopmentCorporation Skidmore, Owings&Merrilland

Transbay Transit Center & Tower Design & Development Competition 7 0 0 2 10 16

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 06 • Design & Development Proposals

Rockefeller GroupDevelopmentCorporation Skidmore, Owings&Merrilland

Transbay Transit Center & Tower Design & Development Competition 7 0 0 2 10 17

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 06 • Design & Development Proposals

It is designed to be the centerpiece of a needs. future to adaptable and use, to sustainable. It is also functional, a environmentally and air, clean pleasure and light great civic places. Francisco’s Its San architecture of is open, to one full of become aspires Center Transit Transbay Our AND HINES PELLI CLARKEARCHITECTS our proposal. of heart the at is Sustainability recycling wildlife. and local for habitat a providing treating and water, exhaust, bus from pollution absorbing Center, the Transit around environment actively the also improves park The and spaces. green attractions urban great characterize the that activities with complete inviting, and accessible is 5.4- Park City acre The Park. park––City public a into transforming the roof of the Transit Center new neighborhood. As such, we propose ih cmn truh ih Columns Light the and sky the of views open also through that coming light natural flower. with infused is a Center Transit The of petals the like waves that glass with covered tree, a like of branches perimeter sculpted is The Center the of structure Center. Transit the of the Tower balances the of richness form of timeless The design Center. Transit the to entrance ceremonial the forms that canopy steel and glass flowing a under sheltered space public grand a Square, Mission is base its At sky. Francisco San location of the Transit Center against the and simple a the marking obelisk, an like form, eternal is It icon. beautiful and Our Transbay Tower is a slender, graceful Transbay Transit Center & Tower City andtheRegion. the neighborhood, their for assets new extraordinary are Park City and Center Transit The users. all to Park City of trees Design & Development Competition 7 0 0 2 10 18

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 06 • Design & Development Proposals

Pelli Clarke PelliArchitectsand Hines

Transbay Transit Center & Tower Design & Development Competition 7 0 0 2 10 19

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 06 • Design & Development Proposals

Pelli ClarkeArchitects andHines

Transbay Transit Center & Tower Design & Development Competition 7 0 0 2 10 20

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 06 • Design & Development Proposals

the TJPA staff and Project Management/ Following submission of the final Proposals, Report Variances fromtheScopeDefinition TECHNICAL REVIEWOFPROPOSALS 0 • Visual andphysicalconnectionto SOM/ROCKEFELLER • Open air • Tower parking/loadingaccesson • Retail pavilionsinMarketHallat • Elimination ofConcourseLevel • Visual andphysicalconnectionto ROGERS/FOREST CITY benefits variances: the by represented functional challenges and/or and and risks, operational feasibility, the the assess allow to to Jury Report Definition Scope the attention from variances Jury’s major following PM/PC the the or and to any brought staff team of TJPA approval the element Proposal, any of expressing disapproval Without Report. Definition Scope the of Criteria Minimum review that all of the Teams have met the the TJPA staff determined in its technical Elements presented in Program the Scope Definition Report, the and of interpretation organization unique a presents Minimum Proposals the of each Although Criteria. the with the complied whether Proposals to as determination limited a was to review was the review subjective; technical not The the of Proposals. review technical a conducted team (“PM/PC”) team Controls Program Transit Tower Mission Streetatmid-block through ground levels Minna Street ground level Mission StreetalongFirst 7 environment atbusand • Did notprovideacostanalysisfor • • Abovegradeencroachmentsinto • Parkroof • Visualandphysicalconnectionto PELLI/HINES • Proposed publicparkorcommercial • Intercity“Greyhound”busstationon • Stacking ofbusdecks n oue o te cp Definition Scope the of 6 Volume in Drawings Definition Scope the on based of the cost Transit to construct the Transit Center the estimate preliminary a for prepared Center consultant PM/PC The Construction CostEstimate development oftheTransitTower. for schedule acceptable an submitted of the Master Schedule, and each Team of the Transit Center within the deadlines design final the of completion projects that schedule a submitted Team Each development oftheTransitTower. for schedule a propose Team each that The Competition Manual further required in accordance with the Master Schedule. milestones for designing the Transit Center detailed containing schedule a propose Team D/D each that required Manual Master design and construction. a The Center Competition Transit 1 Phase the contains for Schedule Report Scope the Definition of 2, Volume C, Appendix Project ScheduleReview Minna &Natomarights-of-way Mission StreetalongFremont Beale overgroundlevelbusplaza development betweenFremontand Minna Street Transbay Transit Center & Tower construction phase IIoftheterminalbuilding Design & Development Competition

7 0 0 2 10 21

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 07 • Technical Review of Proposals

h Cmeiin aul required Center Transit Manual a submit to Team each Competition The the preliminary estimate. of this 4.18 summarizes Report Table Definition Scope 2, Volume Definition Report. Scope the of volumes other the in requirements, described standards and project criteria, the and Report from thePelli/Hinesestimate. park garden roof the of costs the identified exceeds payment earmarked the of Definition value the Moreover, estimate. Report Scope the exceeded Direct Costs Total of estimate Pelli/Hines the which by $24,000,000 the than greater is however, payment, earmarked that of (Jury’s Evaluation of report Proposals). this of The 8 value section in detail greater in discussed are proposal financial the of terms The park. the of development includes the for amount payment earmarked an proposal financial Pelli/Hines the Center However, Proposal. Transit their in the Building for proposed park garden roof the for $37,866,000 of cost a includes estimate Team Pelli/Hines the because $24,000,000 roughly by figure TJPA’s the exceeds estimate Pelli/Hines cost from the Scope Definition Report. construction of estimate The preliminary the The Teams.and Rogers/Forest City are consistent three those with SOM/Rockefeller by provided theestimates with by Report submitted the Definition from Scope Estimate Cost Construction the compares Center Transit estimated follows TJPA’s that table The constructed be construction cost. could of estimate preliminary TJPA’s the within that design hs 1 Phase

tf ue a otdfeeta approach cost-differential a used Staff estimates the conceptual, were and detail lacked Teams’ the Because design. cost to construct each Team’s proposed did not prepare detailed estimates of the As part of the technical review, TJPA Staff estimate the with prepared bythePM/PCteam. consistent Phase were for cost 2 estimated and scope the that advised Pelli/Hines estimate, 2 Phase a for question Jury a to response In estimate. an submit not did Pelli/Hines estimates; submitted and City SOM/Rockefeller Rogers/Forest Program the 2 of Phase in Center Transit the train in station underground the of for construction requested estimate an submit Teams Manual the that Competition The Transbay Transit Center & Towercost intheScopeDefinitionReport. construction of concepts estimate preliminary the design within three achievable reasonably be would the of that each concluded ultimately Staff 5-10%. by Proposal each of costs construction the understate likely each Teams three the of by submitted estimates the 1 that Phase determined Staff the review, this conducting In changes. those with associated cost reduced or added the Definition of estimated and volume etc.) Scope steel, area, architectural concept glazed the (e.g., the Report in from portrayed three construction the or reviewed scope in departures Staff major for proposals TJPA The Report. Definition Scope the in construction estimate Teams’ preliminary the to relative the estimates cost validate to Design & Development Competition 7 0 0 2 10 22

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 07 • Technical Review of Proposals

2 overhead &profit. 1 TOTAL DIRECTCOSTS G50 G40 G30 G20 G15 G10 G F20 F10 F E20 E10 E D50 D15 D10 D C30 C10 C B20 B10 B A20 A10 A Costs Construction of Estimates Submitted Transbay TransitCenter-Phase1

Note: Refertoexplanation oftheroofgardenparkonpreviouspage. Note: DirectConstruction Costsonly,excludingdesigncontingencies,general conditions, 1 OTHER SITECONSTRUCTION SITE ELECTRICALUTILITIES SITE/MECHANICAL UTILITIES SITE IMPROVEMENT ROOF GARDENPARK SITE PREPARATION BUILDING SITEWORK DEMOLITION SELECTIVE CONSTRUCTION/ SPECIAL CONSTRUCTION DEMOLITION SPECIAL FURNISHING EQUIPMENT EQUIPMENT &FURNISHING ELECTRICAL MECHANICAL CONVEYING SYSTEMS SERVICES INTERIOR FINISHES INTERIOR CONSTRUCTION INTERIORS EXTERIOR ENCLOSURE SUPERSTRUCTURE SHELL BASEMENT CONSTRUCTION FOUNDATIONS SUBSTRUCTURE 1 2 BUILDING $255,656,000 (by others) (by others) (by others) Definition ESTIMATED CONSTRUCTIONCOST 17,043,000 12,347,000 29,390,000 14,164,000 69,262,000 83,426,000 58,657,000 13,159,000 71,816,000 15,843,000 16,627,000 25,503,000 17,606,000 11,288,000 54,397,000 Report Scope included 784,000

Transbay Transit Center & Towernot -0- -0- -0- -0- -0- -0-

Design & Development Competition 145,399,000 $254,697,000 Forest City (by others) 10,261,000 13,055,000 78,778,000 66,621,000 32,621,000 11,700,000 44,321,000 24,266,000 10,550,000 43,848,000 Rogers/ 2,794,000 7,174,000 8,074,000 9,032,000 included 500,000 400,000 above In G30 not -0- -0- -0- -0- -0- -0- With below $255,399,000 Rockefeller (by others) (by others) (by others) 26,986,000 26,986,000 45,996,526 70,976,071 51,145,000 51,145,000 13,738,000 13,738,000 12,506,186 18,483,595 15,566,985 46,557,000 In above In above included SOM/ not -0- -0- -0- -0- -0- -0-

$279,881,200 Pelli/Hines 37,866,000 (by others) (by others) (by others) 33,532,300 33,532,300 45,002,400 46,604,500 91,606,900 15,053,000 55,706,900 70,759,900 41,018,600 21,117,600 16,020,300 42,963,500 In above 2,644,600 5,825,600 508,000 -0- -0- -0- -0- -0- -0- 2 2 7 0 0 2 10 23

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 07 • Technical Review of Proposals

new urban building type. Jury The The design a must for calling is client the that Teams recognizes work. their D/D of quality the the on commends Jury The OF PROPOSALS EVALUATION JURY’S 0 xed te tetcps Te Transit The Center design works with the urban form streetscapes. that the canopy a extends with curve has graceful design a The typology. place urban market an the as using transit of It role City. the beyond thedestination new a to creates scale, open human and is Hall” that accessible, idea “Market strong open a is Its fabric. urban the to well connects Center Transit The form ofSanFrancisco. urban the of part as Tower and Center an understanding of the role of the Transit The Transit Center Proposal should reflect Forest CityEnterprises Rogers StirkHarbour&Partnersand the in listed Stage Criteria the Competition Manual,asfollows: Evaluation satisfied II Proposal each which to extent the analyzed Jury The evolve inthenewcentury. to continues it as development urban of useful contributions to our understanding are Proposals three all that believes Jury these among Proposals Choosing has not been an easy task. The innovation. creative through value add to needs of has reached beyond the given program Team each that, than More available. time the in accomplish to easy not this feat a well, it taken solved and has seriously program Team and Every aesthetic symbolic. to financial practical, and from social range that needs site, set of needs at a large scale on a difficult demanding and complex a coordinate 8 with MacFarlanePartners and durability. permanence of sense a without flexible too be may form the however, district; market is appropriate for the developing open, is It inviting, and level. does not cut off the street City. The at has connection It building. strong very a a and spaces people good in the than in rather arrives one City – Francisco San of by bus in the arrive open air provides a to panorama because Francisco San of • • • • ArchitectureCriticoftheBostonGlobe • The Jury: Transbay Transit Center & Tower • • • • KPFF ConsultingEngineers Arthur JohnsonPESE Turner AssociatesArchitectsandPlanners,Inc. Oscar HarrisFAIA University ofCaliforniaatDavis Department ofEnvironmentalScienceandPolicy, Susan L.Handy Hodgetts +FungDesignandArchitecture Hsin-Ming FungAIA Robert CampbellFAIA Design & Development Competition San Dean Ma TJPA Maria AyerdiJD Perkins+Will Allison G.WilliamsFAIA Keyser MarstonAssociates A. JerryKeyser Francisco DepartmentofPlanning(ex-officio) ( e x-o fficio) cri s FAICP

7 0 0 2 10 24

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation of Proposals

f h Mre Hl ad h pavilions the and Hall Market the informality The of the city. as the to plane link cultural ground the at domain public the treats It openness. and scale The design prop neighborhood. pedestrian-oriented vibrant, a promote particular place emphasis on the street level uses that should will Proposal The the structure creates an awkward space of angle the but City, the to connection and transparency its in pleasing is form arched glassy The problematic. is area waiting the and circulation passenger requirements, bus operational transit meets design the Fremont While Streets. First and on effect and tunnel the operations reduces transit compromising benefits. It opens up the structure without potential removal offers Level Concourse and the of simplification not is The entry clear. the good, is level ground at permeability and flexibility the While transit operationalrequirements. The Transit Center Proposal should address Streets. First and Fremont on level ground the at traffic vehicle with conflicts creates also it but vibrancy, level street the create to floor ground the on everyone collects It cons. and pros has Level Concourse the of removal The use. its limit may elements,which the to the open Hall Market the leaving However, enclosure to itself lend or close Center. to difficult appear it makes permeability Transit the throughout traffic pedestrian distributes connections with the neighborhood enables and Hall. permeability ground-level Market This oriented community the provides for easy flow in and out through ground level. The design is permeable and pedestrians. There is for good use of friendly paving treatments be at vibrancy would and promotes design level street an be The community. surrounding the serve to to potential The important destination in and of itself and has scale. Hall human Market the to contribute oses a wonderful human f h Tast etr eg ticketing, (e.g. Center Transit the of functions core the but wayfinding, helps building the of transparency The below. at bringing daylight down into effective the is spaces element skylight central The Center. Transit movement the throughout easy patterns provides design The to theTransitCenter. uses its and Tower the of relationship the to given care particular the with complex, throughout flow resident and user The Transit Center Proposal should address not convincing. was development design in resolved be The Team’s explanation of how this would exposed to the elements when boarding. restricts pedestrian flow. Also bus riders would be and clearance head low with Transbay and light is structure the of that shape The transparent. structure Transitsimple exciting, an is design Center Transit The and structuralsafety. seismic and design, green accessibility, and flow user requirements, operational Center design transit should context, community image, Proposal excellence, architectural Center address Transit The & bus level. upper the of expense ground Tower the the at level on much too focused be Transit Center. Overall, the scheme could weak. may compromise level security is requirements for ground the at Street permeability The Mission on presence Center’s Transit the addition, In entry. of sense and hierarchy clear no but level, street the at articulation positive is There and vehicles on First and Fremont Streets. the circulation conflicts between pedestrians congregating creates level However, ground at people keeping level. ground while at pedestrians light and openness creates removal Its cons. and bold and daring move that presents pros a is Level Concourse the of elimination The core. this to users transit lead or on focus not does design The find. to hard potentially are schedules) information, Design & Development Competition 7 0 0 2 10 25

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: Rogers/Forest City

users. At the street level, it is a community- disabled hinder may structure the inside bus passengers, but low head clearance for space exciting potentially a creates interior the materials is of a positive. The nave warmth at the top humanistic The design. airport Madrid the of design the unique or fresh. Indeed, it not is is very it similar but to gesture, bold dramatic, a is rga ws hruh Te greatest The departure thorough. the from the of was Scope analysis Definition program Report technical Team’s The technical, andotherrequirements. operational, TJPA’s the satisfy to ability Scope the demonstrate design TJPA and Report, the Definition and in contained requirements criteria the meet The Transit Center design concept should an “essentialfacility.” seismic and as designed is Center Transit The events. blast about defensively thought Team The development. design during be susceptible addressed and could analyzed further be but collapse could progressive to It level. below best street be might isolation the but isolated, base is design the Structurally structural model that flexible, can accommodate change. efficient, thought an is well It out. extremely also is are system features structural The analyzed. design well and superb sustainable The secure. and clean keeping in difficulty of drawbacks potential plus elements, the to exposure the suffers structure air open- the However, control. climate need for the eliminating throughout, light natural and air fresh permits structure air open- The unconvincing. but theatrical is level bus at proposal landscape The questionable. is cantilever the of edge the at and planted trees the design of viability the the into integrated landscape not The is raceway. or roadway elevated an like perspective aerial an from appears and inviting not is roof the and looking down from surrounding buildings, openness However, vibrancy. create The permeability design. oriented oncin f h Tast etr to Center Transit the of The connection convincing. not was resolved would be this how of the explanation Team’s However, development. design in Jury a question that this to issue could be rectified response in indicated Team The above. discussed as buses boarding passengers for problematic open-air is level the bus Also, security maintenance. for and concerns raises however, level, ground at environment open-air meet but approach, program and operational objectives. The different a also are pavilions retail The operations. transit compromise not does and design the of above; most important, discussed it works to disadvantages the advantage advantages and several has change That is the elimination of the Concourse Level. Transbay They Schedule. Master the in forth set Transitof the Transit Center within the deadlines design final that the of schedule completion projects a submitted Team individual The their of responsibilities. description a and Center the of involved, be would that identity members Team the Center, Transit the for design the develop to consultants its how of and TJPA the with work would Team the description a & design, of final the completion for Tower milestones detailed the Transit Center, a schedule containing for design completed the for to Team the pay would monetary TJPA the total compensation the including Center, Transit the for Agreement Design the for terms key propose should Respondents the preliminary in cost reasonably Scope DefinitionReport. the construction of be estimate within would achievable design The estimate ofdirectconstructioncost. also be responsive to the TJPA preliminary The Transit Center design concept should and securityconcerns. through the train mezzanine poses safety crosses that parking Tower the to Street Minna on Access weak. is Street Mission Design & Development Competition 7 0 0 2 10 26

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: Rogers/Forest City

em ebr se t hv an about concerns have had Jury the However, to together. The well work and seem dialogue Team. open the members of Team supportive very is and leaders strong have a strong partnership. The developer very are mixed- Partners team McFarlane and developing City Forest projects. use development experience strong with a have ground plane. and massing are not resolved well at the compliment form Tower’s the and Center than Transit the rather dominate to under continually construction. is The Tower it aggressively seeks that impression the create would and elegance It lacks context. Francisco San the fit not do that its structural expression and imagery felt Jury The Francisco. San of ornamentalbuildings colored light the with well marry not does that and structure aggressive, industrial burly, a is it gesture. However, dramatic bold, a is Tower The San Francisco. role theTowerplaysinurbanformof the of understanding an reflect should It Center Transit the presents safetyandsecurityconcerns. through parking Tower the to Access projects. separate two be to appear They them. between complimentary) or similarity to respect there is no clear design relationship (with repetition of structural modules. However, the by driven both are but different, are Center Transit and Tower of design The Center Transit design. the to complimentary a and compatible present is that concept should design Proposal Tower The design. the to changes toward inflexibility and Jury the of by raised concerns to response lack apparent Designer’s Lead the etrs r spr ad h green the and design intentionsareimpressive. superb are features design sustainable the However, idiom. design the within inherent opportunities explored further have could innovative. Team very The not and is design the elements that structural redundancy. felt Jury the clear, are uses of expression the and elements, While use in” “plug- expression, structural exoskeletal its to due constructable highly The is design theory. architecture” “plug-in and “Archigram” in founded approach an is It through. thought well is structure The and constructability. innovation, structural and seismic demonstrate integration of green design, should concept design Tower Transit The Transbay The skyline. the not does aesthetic warehouse industrial, of fabric existing Transitthe is jarring and too great a departure from image. image The icon. wrong the is it However, iconic an be would architectural Tower The iconic an image. Center create and neighborhood evolving an of focus the be should Tower and Center Transit The &at thegroundlevel. Towerand the Tower is subservient to that idea idea big the is Center Transit the of Hall pedestrian space. Overall, it a appears unresolved that the creates Market but and permeable footprint smaller a for to allows arrangement uncomfortable This pedestrian. the be to appear underneath that spaces create of Tower pieces the overhanging the However, and memorable pedestrian interchange. could create a plaza The lively level. neighborhood street at center neighborhood use. It is well planned to promote the new pedestrian strong a promotes Tower the of base the at footprint small The level. street at potential strong has design The neighborhood. pedestrian-oriented vibrant, a promote will that uses and design level street the on emphasis particular place should It Design & Development Competition 7 0 0 2 10 27

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: Rogers/Forest City

ulc ces o h Tast Center, Transit design and the requirements the meet and to access enhance the Center, public Transit should of the to concept relationship Tower the design demonstrate Tower The too robust,muscularandunresolved. is It City. this for inappropriate is design of heaviness The Francisco. San reflect Report. However,FC/MPdidnotdefine thisterm. 2 imposed, if would notaffectthepurchaseprice. expense, such that committed affirmatively team No Tower. the on tax special would Roos Mello a City impose the that possibility the acknowledged team and Each proposed. as price building the develop and finance to purchase the pay to capability financial the has it that demonstrated Team Each potential. revenue incorporated reasonable assumptions regarding sales and Jury the of the convince financial feasibility to of its sufficient Proposal. information Each Proposal backup provided any bonus payment offered in each Proposal. Each team on focused Jury The the amount of the purchase price (not ground lease) and Property. Tower the of transfer on full in paid only, cash be will Price Purchase Base the that commitment a including Sheet, Term the to agreed Team proposals contained the following terms in common: each 1 offer. Purchase FC/MP’s on their focused Jury in the FC/MP” by Ground Lease offer. owned Given this condition, be component must Condominium Residential the with associated rights development and Partners fee “the that MacFarlane proposed (“FC/MP”) and City Forest and timing the amount ofrevenuetotheTJPA. on focus will Jury The connection toMissionStreet. weak a creates it but positive, a is First on Center Transit the to entry the create to site the of side east the to Tower the the into Tower Market Hall of the Transit Center. Moving the past move would separate People plaza. a by two connected projects as essentially designed are Tower Tower and the Center Transit in The base. use retail interfaces no or there limited but is plaza Center, Transit the open with well Tower’s The Report. criteria contained in the Scope Definition CM ue Znn Sur Fe a i qoe i this in quoted is as Feet Square Zoning uses FC/MP While different in purchase price offers, the three financial 1 rc cnit o “ Priiain Rent Participation “a of consists Price Purchase Additional proposed FC/MP’s ZSF.” 1,230,000 of development for available area total the Dollars on based Million ($145,000,000) Five Forty and One Hundred be will offer price purchase total the Program, Preferred the For Property. rights and fee associated with the Tower Square Foot Zoning per ($117.89) Cents and Eighty-Nine Dollars Seventeen Hundred “One of Price Purchase Base a offers FC/MP Price. Purchase Additional and Price Purchase Base a of of consists timing) and (amount revenue offer financial FC/MP The Transbay includes uses of mix The Sheet. Term FC/MP’s per as (ZSF) TransitFeet Square Zoning million 1.2 and document Vision the of 164 1.5 page of per feet Tower square the gross a million that for is considered proposal Jury FC/MP The offer. Center business their of viability the support to documentation forma pro and financial be FC/MP submitted the requested program can that financed andbuilt. a & program demonstrates development Tower that Towerdocumentation the submit forma pro and financial appropriate the should of Respondents proposal. feasibility overall the on financial focus also will Jury The by quantified FC/MP. not Additional was Price the Purchase nature, speculative its given and such, As projections. FC/MP’s current of excess in profits in TJPA share to the allows that provision windfall a is Price Purchase Additional the that FC/MC question, Jury a to response in clarified, project.” the of components costs Retail and development Office the a on of land total including the receives return on 10% cumulative FC/MP Gross compounded, after Modified the of Revenue 2.5% to equal Design & Development Competition 2 (ZSF) for the development 7 0 0 2 10 28

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: Rogers/Forest City

ht atr i htl evcs being services hotel in factors that $1,600 per net SF, a sales price projection over slightly at sales gross condominium more than $100 per net SF, and Annual residential gross ZSF. office rents are projected at slightly 640,000 of amount the in and space programmed is office The space. office hotel, facility units, retail/community condominium residential s mjr eeoe wt extensive mixed use projects. MacFarlane Partners with developer and urban on experience development major a is results from operations. Forest City (“FC”) as asset such value, liquidity factors and history asset of positive of consideration financial specific account into taking credentials, impressive very have FC/MP development securing capitalfortheTower. of record projects, performance, and their financial plan for past track in their capital securing of record track their including credentials financial presented FC/MP Tower, the of development the finance to resources As evidence that the Team has the the finance thedevelopmentofTower. capital that to resources capital sufficient has evidence Team detailed include the should Tower Transit the of development finance to plan Respondent’s The offered. Price Purchase the sustain to sufficient is developer the by assumed factor profit views. the that persuaded its was Jury the Finally, and strength, strong further gain very to its Tower, anticipated market office an in location the iconic of the nature feet), square to gross space 640,000 office the keeps (which use were mixed building’s the given feasible likely prices sales and rents projected entitlement andthat persuaded was Jury The feasibility. market financial, factor to of plus strong a nature be to use building the mixed the considered Jury The building. same the in available ein n cntuto, h identity the construction, final and the design of completion for milestones key including a schedule containing detailed Tower, Transit the for propose Agreement Option Development and Design the for should terms Respondents capital fortheTower. comfortable is secure to capacity Jury the has FC/MP The that TJPA. the to assurances behind stand would FC that the lender. Further, the Jury understands to guarantees competitive provide will standards. Also, per the finance plan, FC at 25% of total cost, which meets industry the equity provide for will they indicates plan Tower financial FC/MP’s CalPERS to funds. relationship advisor special institutional a major with a is (“MP”) Transbay Transit Center & Tower Tower. acceptable an Transit the of development for schedule submitted Team their The of description individual responsibilities. a be and would involved, that members Team the of Design & Development Competition 7 0 0 2 10 29

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: Rogers/Forest City

form ofSanFrancisco. urban the of part as Tower and Center an understanding of the role of the Transit The Transit Center Proposal should reflect Rockefeller GroupDevelopmentCorporation Skidmore Owings&Merrill h wsen n o te ulig Other building. the of end western the isolates Street First of west level ground Mission at permeability the limited The entry. on Street emphasis much there too and is level street at connectivity pedestrian strong a not is there Overall, travelers. by bypassed easily is area the but Street Natoma to well relates retail The Street. Mission of off concept entry than focused on Natoma to enable the great rather concept relating to the neighborhood. entry The retail is and Hall Transit the on much too is focus the and exciting potential. Uses are not balanced The street level uses are modest and lack neighborhood. pedestrian-oriented vibrant, a promote particular place emphasis on the street level uses that should will Proposal The in spatialexperience. the design is strong in imagery, but weak Overall, form. in Tower the to similar too is Center Transit the Also, site. the of end west the across circulation barrier off cuts a and of somewhat is it time, same the At Street. Fremont daylighting and freeing up space east of Fremont Street the overall footprint of the Transit Center, stacking of the bus operations condenses The presented. is it way the appreciated or seen self-focused be really never would rather it object; a is design overall excessive and could be intimidating. The is Hall Transit the of scale region. the However, the for hub transit the as scale grand a on gateway new a and room, a civic City, the in transit for of presence reminiscent and traditional rail stations. It creates a strong dramatic is Hall, Transit the design, the of point focal The and to a place to pass through rather than rather through pass to place a to Hall Transit the relegate Street, Natoma on retail the from as separation its Hall, as well Transit the of uses limited scale and excessive The Center. of Transit accessibility the pedestrian not the does to that add street a oriented remains Minna service Hall. Transit the and Greyhound between relationship Street First no across is There Streets. Minna neighborhood and especially south to First and and surrounding the to poorly relates Center Transit north the Hall, Transit the the of entrances through than Transbay An functions. separating by bus operations Bay transit other and East Muni from Transit isolates passengers Hall Transit The exiting. emergency for problematic be could entrance which Hall, Transit west the through or the to is either buses Bay directed Center East from and to Access grades could steeper have greater The noise impacts. inconvenient. is circulation for problematic maneuvering is buses. The roadways bus &climbing decreased and of width The efficiency. Towerdecreases from and pattern routing The deck. to bus upper the ramps the in of traffic vicinity the diverging and merging with problems creates It or transit. of efficiency park but at too great a performance cost to and the operational Street, Fremont of east site developable Hall potential the Transit creates a the decks for bus opportunity of Stacking transit operationalrequirements. The Transit Center Proposal should address the of design. element guaranteed a not is it Center, Transit the for estimate cost their Team’s financial proposal nor included the in within funded program, not is the it because but to addition park positive a performance is The destination. a Design & Development Competition 7 0 0 2 10 30

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: SOM/Rockefeller

not improve upon operations and would and would Street operationsMinna to Greyhound move bus stack to the proposal Overall, edge. street negativethe on Center potentially effect Transit a creating the taller, make also decks would bus the Stacking difficult. more generally wayfinding passenger make would riders for buses of floor additional tis rm h tan eznn, thus at thatlocation. experience mezzanine, pedestrian any train eliminating the from stairs exit are Street First onto Hall Transit the from shown doors only The access north. the to pedestrian from Center the Transit isolate Street Minna on operations dock loading and bus Greyhound Hall. to the East Bay bus deck from the Transit go to concourse transit the at elevators transfer must who passengers disabled for especially inconvenient, is distance travel rider passenger The clear. area, not is bus once wayfinding two-story space Also, the one bottlenecks. in through create users may transit all wayfinding easier for makes visitors, accessed but are funneling services transit all which from hall central a an Having issue. becomes security if problematic Tower is the of floor ground the Hall through Transit the to access on emphasis the and paths circulation of restricting However, and controlled too is Street. plane ground the Fremont potential daylight the flow and to user Hall Transit of the are elements strongest The to theTransitCenter. uses its and Tower the of relationship the to given care particular the with complex, throughout flow resident and user The Transit Center Proposal should address compromise userflow. ht h Tast al s pae o pass to place a is Hall Transit the that on Natoma retail Street from of the Transit separation Hall the means addition, In time. the of much empty be could Hall the so visitors, other and users transit for space comfortable a create not does of It excessive. scale is however, Hall, The Transit the integral. are and features numerous design Sustainable side the walls. along areas rail enter to light and enables structure the and areas bus into light is light brings roof transparent The minimal. structure innovative The and structuralsafety. seismic and design, green accessibility, and flow user requirements, operational design transit should context, community image, Proposal excellence, architectural Center address Transit The Transbaythe TransitCenter. of efficiency operational the diminish to accumulate operations of area each in enabling Transitthe and Transit Hall -- the compromises made level bus the stacking – for basis Team’s varying the from the Scope Definition Report form that issues appreciates Centerthe sustainability and Jury design the While Report. Definition the Scope in elements these of the configuration to compared as operations transit the of bus efficiency different the two- reduces and ramping a platform, & bus grade, level at Greyhound Tower that design shows the that believes Jury The technical, andotherrequirements. operational, TJPA’s the satisfy to ability Scope the demonstrate design TJPA and Report, the Definition and in contained requirements criteria the meet The Transit Center design concept should considered design progressive collapse. structural the and isolated base is excellent It out. thought well is and However, engineering the structural justification. to the similar without too is Tower It tiresome. and overwhelming is structure of complexity park, The assure. not does proposal the which performance potential other the limited than quite is provided space through rather than a destination. Green Design & Development Competition 7 0 0 2 10 31

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: SOM/Rockefeller

epnet sol pooe e terms key propose should Respondents the preliminary in cost reasonably Scope DefinitionReport. the construction of be estimate within would achievable design The estimate ofdirectconstructioncost. also be responsive to the TJPA preliminary The Transit Center design concept should r a iia ashtc o to different two for aesthetic similar a are and and visually differentiated not are Tower Center Transit the overwhelming; visually is Center Transit and Tower both in elements structural lacy of from are repetition benefit Center would more variety and different aesthetic. The Transit but and compatible Tower The Center Transit design. the to complimentary a and compatible present is that concept should design Proposal Tower The challenge. continuous a be would it that appears It Team’s the flexibility to adapt their design efficiency, is in doubt. operational of expense the at elements design for grand push to decision Team’s design. the the Given afford to ability TJPA’s the developer and the the overwhelm TJPA and might compromise team design the design side of the Team. The Jury sensed The Schedule. Master Team appeared the to be dominated by in the forth set of the Transit Center within the deadlines design final that the of schedule completion projects a submitted Team individual The their of responsibilities. description a and the of involved, be would that identity members Team the Center, Transit the for design the develop to consultants its how of and TJPA the with work would Team the description a design, of final the completion for milestones detailed the Transit Center, a schedule containing for design completed the for to Team the pay would monetary TJPA the total compensation the including Center, Transit the for Agreement Design the for enclosure, of the building is elegant. The elegant. is building the of enclosure, expresses its program of uses. The skin, or San fits lightness shape narrowing and rising Its Francisco. Tower’s The houses. Ladies” “Painted old ornamental the of the woodwork recalls “laciness” The designed. over being without other any The Tower is simple, yet memorable, unlike San Francisco. role theTowerplaysinurbanformof the of understanding an reflect should It traffic throughthelobbyofTower. pedestrian all herds the and crowds Center Transit base its at footprint major large a two the Tower’s the Also, unresolved. is structures is between joint the buildings weakness; the between connection physical The types. building Transbay Transitdesign elements. innovative much attention to innovative sustainable through paid Team The techniques. construction Center schedule the the TJPA’s meet to ability but its reiterated elements, Team exterior repetitive non- to due construct to slower be may &within. The complex and twisting structure Towerskin as an expression building’s of the of the resolution beautiful uses a is contained The Tower is very innovative structurally. It and constructability. innovation, structural and seismic demonstrate integration of green design, should concept design Tower Transit The at thetopthanitsbase. the stronger is Francisco to San of form makes urban Tower the The contribution upward. moves it as line sky the in elegant and slender more becomes it but site, the dominates Tower the base, bulky profile from the north or south. At its the than appealing more much is west Also, or east the from profile slender more the overpowering. and too is monumental effect the but idea, exciting an is entry great the with art of integration Design & Development Competition 7 0 0 2 10 32

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: SOM/Rockefeller

pedestrian amenities. base. few provide its would it artwork, with entry at bulky very Although the Tower would have a grand is Tower The neighborhood. pedestrian-oriented vibrant, a promote will that uses and design level street the on emphasis particular place should It poses security risks. Moreover, the public entry Tower the through Also, Center Transit the to monumental. too be may However, the entry hall, at 100 feet high, scale. large a on art public for potential a with transit to door front the is It entry. grand Center’s Transit the is Tower The Report. Center, criteria contained in the Scope Definition Transit design and the requirements the meet and to access enhance the Center, public Transit should of the to concept relationship Tower the design demonstrate Tower The amenities atgroundlevel. or connections pedestrian lacks It level. ground at surroundings its to connection an of focus evolving neighborhood due to its lack theof as convincing is as Tower entitlements not the Also, obtain height. current its to at unable were destroying the overall design if the Team Tower without height in reduced the be not could that however, concerned, was Jury The elegant. and it beautiful overall is but base, its at bulky too is it and profile slimmer its as proportionally manner. The wider side is not as resolved elegant soft, a in achieved is elements much has up structural it of prominence The rises potential. twisting it as façade’s evolving and The of skyline Francisco. the to San addition great a be beautiful and without seeming too over done. It would memorable is is It Tower superb. the icon, architectural architectural an As iconic an image. create and neighborhood evolving an of focus the be should Tower and Center Transit The offer. Purchase focused Rockefeller’s on evaluation Jury its a the of offer, absence Lease the Ground In supportable is market.” the size in all-office similar an of that building believe it does nor that is held under a 99 year ground lease site a on units such believe develop can it not that does and units ownership Rockefeller “intends to include and residential timing the amount ofrevenuetotheTJPA. on focus will Jury The which ultimatelyisverydivisive. entry, grand the create to forfeited are Transit neighborhood surrounding the and Center to connections important as the Tower lobby remains open. Other long so only Terminal the access could Transbay Transitfollows: various as the Tower proposed of the of components pricing market the on based is price land This $118,440,700.” Center of payment a for land the “acquire to Price Purchase Base a offers Rockefeller Additional Purchase Price. and Price & Purchase Base a Towerof consists offer financial Rockefeller The TJPA. for the to deliver would proposal property Tower the Rockefeller’s revenue of amount and timing the on focused Jury the however, Manual, Competition the to and in contained Criteria Evaluation the with Library accordance In Art. State Public to contribute California the house to Tower the in space donate to a public park. Rockefeller also proposed of the Transit Center if it forpossible were not used for the east the to site price a of value development including site, purchase Tower in the the TJPA the to to addition Jury, value provide the would to Proposal its that presentation suggested Rockefeller oral its In Design & Development Competition 7 0 0 2 10 33

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: SOM/Rockefeller

• • • • • • rs sur fe o ofc sae The space. 720,000 office of feet proposed square gross and Rockefeller retail residential office. hotel, includes units, that condominium uses a of with feet mix square gross million 1.7 of Tower a for is proposal Rockefeller’s that forma considered pro Jury The offer. business their and documentation to support the viability of financial requested the program submitted be Rockefeller can that financed andbuilt. a program demonstrates development Tower that documentation the submit forma pro and financial appropriate the should of Respondents Proposal. feasibility overall the on financial focus also will Jury The major adjustmentinprice. change was not likely to be a basis for a consideration, Rockefeller persuaded under the Jury that such now is as codes, performance-based adopt to were City Jury the a if impact possible the to as question to response In codes. building 2007 on based is Price Purchase its that stated Rockefeller that noted Jury The Price tobe$10.2million. present value of the Additional Purchase the estimated It million. $23 totals Price the nominal value of Additional Purchase every five of years.” Rockefeller stated that payments This additional payment will increase 10% additional $1,000,000 per annum make (payable monthly). will Respondent . . . Completion Substantial of 20 years, commencing on the date of Purchase Price to be paid over a “period Additional an proposed also Rockefeller $0 pergrosssq.ft.ofculturalspace $0 perparkingspace $35,000 perhotelroom unit forsale residential housing affordable per $0 unit forsale residential rate market per $100,00 and retail office off ft. sq. gross per $100 eet eieta cnoiim sales condominium residential ferent dif and errors typographical contained also forma pro The rent. gross with tent consis not – expenses operating of net stated that gross scheduled income was Rockefeller income, rental gross provide units. condominium Where the template asked for Rockefeller to price sales tial residen gross and feet square net per rent office gross projected the derstand un to Jury the for difficult it made that information inconsistent internally tained con template forma pro Rockefeller’s and marketspaceinthebuilding. development, the finance entitlements, obtain to position strong a in Rockefeller place would building the for proposed uses of mixture the that considered Jury Transbaythe that Jury the persuaded Rockefeller Transitstrength, and the building’s views. Finally, office market anticipated to gain further an of in location strong nature very its Tower, iconic the the space) office of feet square gross 700,000 over (just use Center were mixed building’s the given feasible likely prices sales and rents projected its that Jury the persuaded Rockefeller &nancial feasibilityoftheProposal.) Towerfi the substantiate to information ficient suf included proposal the that believed Notwithstanding the above-cited inconsistencies, the Jury price. purchase the purchase condition or amend to offered not and – price the for verification and backup provide to designed was template forma pro the that noted be should it regard, this (In feet square net per $1300 nearly of proceeds sales gross residential projecting and Teams, two er oth the from proposals the of range the within was which $100, approximately at feet square net per rents office gross ing project proposal, the in presented tion informa the of all on based assumption reasonable most the it be to what considered adopted Jury the information sup a port table. In evaluating this inconsistent and table summary a in prices Design & Development Competition ------7 0 0 2 10 34

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: SOM/Rockefeller

nld dtie eiec ta the finance thedevelopmentofTower. that to resources capital sufficient has evidence Team detailed include the should Tower Transit the of development finance to plan Respondent’s The offered. price purchase the sustain was to sufficient assumed Rockefeller factor profit to developtheTower. capacity to secure the capital necessary the Jury is comfortable with Rockefeller’s and Center however, Overall, Center Embarcadero Rockefeller e.g. of past, projects the famous Rockefeller’s than in-process exception, and quite different that been are projects unlike the development Tower project, land has with in one primarily experience development was concerned that Rockefeller’s recent necessary capital was excellent, the Jury raising of record track Rockefeller’s that industry standards. While the Jury found equity to meet 25% of total cost, meeting financial plan Their for the Tower indicates they will raise operations. from results positive of history a and liquidity, value, financial credentials, including high asset Rockefeller and RGII have very impressive to besound. securing capital for the Tower appeared Jury the found that Rockefeller’s financial plan for performance, development of record track its and projects, past in excellent track record Rockefeller’s of Given securing capital RGII, of own. commitments the its as well financial as statements RGII’s submitted Rockefeller TJPA. the to performance Rockefeller’s of assurances behind stand also would RGII that understood Jury The provide lenders. and construction to guarantees capital completion company, necessary Rockefeller behind with Inc. parent stand will International, (“RGII”), its Group Rockefeller that noted capital resources the to has finance it the that demonstrate Tower, To Rockefeller

Transbay Transit Center & Tower Tower. acceptable an Transit the of development for schedule submitted Team their The of description individual responsibilities. a be and would involved, that members identity Team the the of construction, final and the design of completion for milestones key including a schedule containing detailed Tower, Transit the for propose Agreement Option Development and Design the for should terms Respondents Design & Development Competition 7 0 0 2 10 35

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: SOM/Rockefeller

form ofSanFrancisco. urban the of part as Tower and Center an understanding of the role of the Transit The Transit Center Proposal should reflect Pelli ClarkeArchitectsandHines the City. The sidewalks are retained and retained are sidewalks The City. the of shape the reinforces edge street at the around activity entire Transit Center and vibrant Tower. The detail with uses level street excellent has proposal The neighborhood. pedestrian-oriented vibrant, a promote particular place emphasis on the street level uses that should will Proposal The neighborhood. vibrant and street life as focus of a mixed use, dense space open usable new providing city, and neighborhood in role Streets. its about is it as building single a as itself Fremont and Overall, the First design is not as much about on effect “tunnel” the lessens and addresses also design The Park. City and Center Transit the to entry grand and hall space civic a as or “Mission room great spirit. a provides Francisco Square” San the with keeping in wholly environment, the for and concern a also but heartedness, structure light of sense a only Center not conveys park Transit rooftop the of Design form. urban the defining further proceeds, redevelopment adjacent has as new buildings to park link to the for potential catalyst the itself, a in As development Park.” “City urban wonderful a through value add to hub transportation a beyond The Center the Transit inviting. of program and the expands visible proposal is retail scaled welland is edge Center Transit The below. Center Transit the of on skyline marker the a as works Tower The level. from an aerial perspective and at ground both Francisco San of form urban the of part as beautifully fits Center Transit The and activity of all sidewalks, particularly sidewalks, all of activity and dimension the to contributes design The from a service street to a pedestrian area. area. The design surrounding calls for an upgrade of theMinna to links provides block western the through level ground for the neighborhood. The permeability at center pedestrian a create to effort the to contributes Natoma on The center retail vibrant. more become streets the helps and environment pedestrian more a for makes openness The lively inviting. and is which overhang, floor 2nd the under Center Transit the into extended Transbay hall from access ticketing clear with information, and central for location The clear a Transitprovides areas. areas boarding ticketing to from movement easy and clear enables design The light. and circulation of terms was in Flow out thought passengers. well Center rail and bus circulation for clear is There directions. all from flow excellent provides design The to theTransitCenter. &uses its and Tower the of relationship the to given care Tower particular the with complex, throughout flow resident and user The Transit Center Proposal should address the reducing efficiency ofoperations. without contained are fumes and noise bus and elements the and vertically. People are sheltered from horizontally movements user simplifying Report, yet enhances it by Center clarifying and Transit Definition Scope TJPA the follows design The operations. transit The design proposal provides for excellent transit operationalrequirements. The Transit Center Proposal should address proposed amountofretail. the Center, than more require may building the the surrounding streets the all Natoma and Minna. However, to activate Design & Development Competition 7 0 0 2 10 36

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: Pelli/Hines

h Tast etr rpsl should Proposal Center Transit The reach it. to ride escalator or elevator funicular, a clear, the park is four stories up, requiring are paths circulation the although that concern a is There platforms. unloading and loading from separated are areas waiting Bus Street. Mission on plaza the hnmn, h atok ik the links artwork the phenomena, environmental with deals who artist an the Transit Center and park. Designed by throughout integrated is Art sustainable. noise from the bus area is innovative and and fumes treat and remove to solution Team’s The Center. and Transit the of length repetitiveness the decrease help and landmark park) (and internal good a provide wells light The Center. Transit compromising the transit functions of the without development, neighborhood in physical activity. It is a risky, daring move needed much get can residents where place a and activities, educational and events civic for opportunities offers also unique new destination within the City. It and exciting an be would and residents of number growing a for neighborhood the to space green needed much add growing trees of on the feasibility roof. The the park would assure to park rooftop construction methodology for creating a the demonstrated has Team The Center. Transit the of design sustainable overall the to contribute would and community rooftop park would be a great asset to an the important part of the urban fabric. The Team committed The to landscape architecture as organism. urban living, breathing, a to it transforms it contrary, fifth the the ignore To roof. of expanse great not the elevation, does design The fabric urban and the the context of into the community. well extremely fit Tower iconic and Center Transit landmark The and structuralsafety. seismic and design, green accessibility, and flow user requirements, operational design transit context, community image, excellence, architectural address oee, ute dsg development design further However, condition. and codes building local of reflective not is it but scheme, good a developed has Team The isolated. base not be required if the structure is should properly joints These leaking. potential to due concern serious a are structure roof design is not worked out yet. Joints in the could be less fussy. Overall, the structural the sidewalk area. The system is sound but move the columns inward and increases Center. The basket structural system helps Transit and Tower the between link a as the as and Center Transit the to gateway main development further and needs exploration design its but potential, great has Square” with “Mission Tower. park and Center the using Transit community greater the the of functions Transbay Transitthe developer. by contribution additional dedicated a through accommodated is park the of strongest cost added the the and proposal is financial Center preliminary This Report. reasonably Definition the be estimate within of construction cost would in the Scope achievable design The &estimate ofdirectconstructioncost. Toweralso be responsive to the TJPA preliminary The Transit Center design concept should enhances theprogram. rather operational but requirements, circulation on and infringe not does circulation park scope the verical efficiency. (from definition report) and the addition of the improved been and improve has that Horizontal changes considered have seriously to the design seems criteria and team suggested The technical, andotherrequirements. operational, TJPA’s the satisfy to ability Scope the demonstrate design TJPA and Report, the Definition and in contained requirements criteria the meet The Transit Center design concept should should addresstheseconcerns. Design & Development Competition 7 0 0 2 10 37

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: Pelli/Hines

h fnl ein a ecito o how of and TJPA the with work would Team the description a design, of final the completion for milestones detailed the Transit Center, a schedule containing for design completed the for to Team the pay would monetary TJPA the total compensation the including Center, Transit the for Agreement Design the for terms key propose should Respondents park. and Center Transit the the of spaces on public focus puts simplicity Its Center. Transit the marks Tower The other. each vocabularies and relate without copying and Center compatible Transit but contrasting have Tower The Tower. the to and park. The park is an excellent contrast and compatibility at two levels – ground The proposal has very good Center connections Transit design. the to complimentary a and compatible present is that concept should design Proposal Tower The internationally. team with a strong track record nationally and development a including collaborative/integrated team, very a backed by leadership up design have together. They relationship long-standing a with developer strong strong a a projects and have architect They Francisco. successful San in and completed including together, working experience and synergy great has Team The in TJPA. work a is progress and they need to work with the this that acknowledged seemed architect Team The design. the enriching to open the and changes flexible and responsive to potential design seemed Team overall The space. providing public to commitment developer’s Team The the schedule. The Jury was impressed by the meet to Schedule. TJPA the with work Master would the of of the Transit Center within the deadlines design final that the of schedule completion projects a submitted Team individual The their of responsibilities. description a and the of involved, be would that identity members Team the Center, Transit the for design the develop to consultants its elements oftheexteriorwall. spandrel and mullions of heaviness the against cautions Jury the area, glass of Francisco. However, San with the of minimization atmosphere and sunlight the of understanding an showing Francisco precedents, San with keeping in is tower fabric. urban the of texture surface “pearlescent” The the to detractors versus an as contributors strong are together and form urban woven well very are huge a be amenity could programmed, and Francisco and the park, if properly built, managed, San for appropriate is tower the of design light slender, elegant, The San Francisco. role theTowerplaysinurbanformof the of understanding an reflect should It Transbay Transit Center its to current symmetryonallsides. opposed as orientation, respond solar could to Tower design. the addition, sustainable In the & to floor to contribute floor air fresh of Tower use and glass of scale and sense viability. The minimization of better a it give to more uses varied of needs expression and/or design exploration structural The circulation. impede and use functional no provide to appear base the to added columns at large big additional the Also, too floors. top are the diameter in feet 11 at Columns Tower. the of form and image and could contribute more to the overall However, is the structure is straightforward. not It necessarily innovative true. and and well simple tried is and system out thought structural Tower’s The and constructability. innovation, structural and seismic demonstrate integration of green design, should concept design Tower Transit The Design & Development Competition . Both the tower and the terminal 7 0 0 2 10 38

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: Pelli/Hines

entry to the Transit Center and the park the and Center Transit the to entry space (Mission Square) public that serves for as the block the of side east the of Square, but weaker on First Street. The use Mission on strong are uses proposed The neighborhood. pedestrian-oriented vibrant, a promote will that uses and design level street the on emphasis particular place should It Francisco. central place. It is timeless and fits in San the Tower is a whole, elegant identifier of in the Tower’s variety façade and massing. establish Overall, to driver functional and authentic an provide would Tower analyze mixed-use a that acknowledged further and explore Team The uses. hotel and/or residential to flexibility its indicated Team the but neighborhood, new a of vibrancy the to contribute not the may program all-office the as weakness at a is scale Tower the of use singular the The base. of program, refinement use and mixed through orientation, design the solar slight enrich to a need is a creating There simple, too being it iconic. of danger be driven still functionally and and more operationally be could Tower the felt Jury The development. for catalyst a as park the using area the in redevelopment future addresses and considers also design The street level, park level, and view from afar. and icon of the area. It works well at the Center Transit the of marker a the as Tower to contributing blows, wind the as light of presence the change Tower the Its playful sculpture/turbines at the top design. of the to integral is Art image. soften the texture “pearlescent” and curved form Its solution. elegant simple, a is It image. architectural iconic an creates architectural The Tower, paired with the Transit iconic Center, an image. create and neighborhood evolving an of focus the be should Tower and Center Transit The them inasecureway. sorting also but mix to people allowing through Mission Square is well organized, is a positive feature. Also, pedestrian flow multiple levels. at linked are Center Transit and the Tower to relation Tower and Transit Center. more The retail in the needs the canopy develop Square to Mission The need architecturally. links a is there linked, are but spaces private and public the Transit Center. Programmatically, the mark to landmark a as serves Tower strong The very structures. two a the between relationship provides proposal The Report. Center, criteria contained in the Scope Definition Transit design and the requirements the meet and to access enhance the Center, public Transit should of the to concept relationship Tower the design demonstrate Tower The Transbay the with accordance pay in to a Program amount propose this We in $350,000,000. Program results of Preferred the to formula Contribution TransitFinancial this the scenario, “Under all floorsfromthe51stFloorupwards.” Centerfor $250/FAR at constant remains pricing the whereupon Floor, 50th the through up sequence in (SF floor per $2/FAR adding Tower, $150/FAR Transit the of base Floor the at Area”) “Gross of 102.9 & Sec. have Code value Planning We a Towerassigned rights. development FAR Tower’s Transit the valuing to approach formulaic “a on based Base is offer Hines The a of solely Purchase Price. Preferred consists its on Program offer financial Hines’ the Hines’ Purchaseoffer. of nature on focused Jury the offer, Lease Ground conditional the Given for developer to purchase the Property.” option an to agree mutually would TJPA and “developer and condition” good in to keep and surrender the improvements expectation that . . “the . includes offer Lease a Ground Hines’ customary covenant and timing the amount ofrevenuetotheTJPA. on focus will Jury The Design & Development Competition 7 0 0 2 10 39

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: Pelli/Hines

an opportunity to meet the City of San of City the meet to opportunity an City provides of Park City of creation The be Park. construction will the to Contribution allocated Financial the of 15% that assumes formula pricing “Our Transit Tower property.” the of transfer full upon sum cash lump in a as sheet, term disposition h sae n h Twr e eoe to all devoted be virtually Tower the in that space the is preference its that proposal its in stated Hines feet. square Hine’s that proposal is for a Tower of 1.8 million gross considered Jury The offer. business their of viability the support to documentation forma pro and financial program requested the submitted be Hines can that financed andbuilt. a program demonstrates development Tower that documentation the submit forma pro and financial appropriate the should of Respondents Proposal. feasibility overall the on financial focus also will Jury The definitive statement. a hear not did Jury the but Park, the for O&M for responsibility financial greater question, interview an that Hines might consider assuming even to response in said, also Hines scheme. financing O&M an of component one least at as district that basis, Hines proposed an assessment the Park’s presence, including Hines. On from financially benefit will who owners property of number a be asserted will there Hines that However, place. in be would Park the of (O&M) maintenance and operations for necessary dollars the specific proposal to assure how and no when made Hines that noted also Jury The construction ofCityPark. capital to restricted the as offer their of 15% consider to Hines understood the Jury K question, interview an Prop to response potential the shadow impacts of the Transit Tower.” In to mitigation requirement critical a as well as Tower, Transit space the for open Francisco’s defend its ability to finance and market and finance to ability its defend When Hines was asked in the interview to by theothertwoTeams. more is than double that allocated proposedto office use of Hines amount space The office space. office square of million feet 1.8 nearly market or for entitlements secure to unable be may Hines that risk the on focused Jury The condominiums. did not provide sales but prices for SF, residential net per residential $83 at rents office gross to might annual projected Tower instead Hines condominiums. the allocated of be floors upper of number substantial a for that possibility the allowed Hines although use; office Transbay response Hines’ and identified Jury the Transitrisks the both account into took Jury The Center & Tower2. 1. the following: say to Hines understood Jury the office, a Tower with so much space devoted to

Design & Developmentoffice. the not of as well as residential included use Tower would ultimate the if offer change Price Purchase their that indicated Hines interview question, an to response In Competition office. be devoted to residential rather the than for could 50 above floors allow that potential does that proposal Jury their the reminded also Hines such believe success would berealizedwithallofficeuse. and entitlement/development success, of record outstanding an with market entitlement/development Francisco San the in active very reminder are they that a expressed proposal written reasons They the in the to TJPA.” added the soundest for a the with opportunity presents tower base office the retail an “that repeated i.e. effect, proposal— written their in language in Hines, 7 0 0 2 10 40

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: Pelli/Hines

a sfiin t ssan t purchase its very its run had it indicated sustain Hines offer. to sufficient was factor Hines’ that affirm to and Proposal written to its in factor profit approach a of projection its clarify to Jury Hines the asked process, interview the During of the TowercomponentofProposal. evaluation its in inquiry Jury’s the to h Jr i cmotbe ht ie has Hines that comfortable is Jury The development. office is suit strongest its Hines’ while development track record that was excellent, concluded also Jury The excellent. be to capital necessary raising of record track Hines the found costs, total thus meeting the industry standards. of The Jury 25% meet to equity the raise to plans support, MetLife from with results positive Hines, Tower, the finance To of operations. history financial a and impressive liquidity, values, asset very high credentials: has Hines MetLife a by representative presentattheinterview. confirmed was MetLife, had this with it and that agreement Jury an the reached to stated Hines interview the In project.” Tower Transit the for agreement an documenting on working currently is] [Hines and Proposal interest written its stated that “MetLife in has expressed strong and financial resources substantial own Hines its Tower, described the finance to capital resources the has it that demonstrate To the developmentofTower. has sufficient capital resources to finance include detailed evidence that the Team the should Tower Transit the of development finance to plan Respondent’s The offer. price purchase its in reduction a request residential rather than office, it would not the above space 50th floor were to be devoted to for-sale the if that Jury, the also Hines indicated, in response to a question from qualification. without Price and model Purchase its offering in comfortable was forma pro sophisticated

Transbay Transit Center & Tower Tower. acceptable an Transit the of development for schedule submitted Team their The of description individual responsibilities. a be and would involved, that members identity Team the the of construction, final and the design of completion for milestones key including a schedule containing detailed Tower, Transit the for propose Agreement Option Development and Design the for should terms Respondents the Tower. for capital secure to capacity the Design & Development Competition 7 0 0 2 10 41

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 08 • Jury’s Evaluation: Pelli/Hines

h Pooas Smig h individual the Summing Proposals. the scored individually Jurors the interviews, and presentations Team D/D including Following the evaluation of the Proposals, RECOMMENDATION SCORES, RANKING& 09 Jury’s recommendation is unanimous. Agreement for the Transit Tower site. The Option Development and and Disposition a Center Transit the for Design Agreement a for negotiations exclusive for the Board of Directors approve this Team Pelli and Hines first and recommends that The Jury ranked the D/D Team of Pelli Clarke Recommendation oftheJury by aletterfromA-G. represented is Jurors voting seven the of each below, table the In unanimous. is ranking. The Jury’s ranking of the overall the derived Proposals teams the of scores Pelli/Hines Rockefeller SOM/ Forest City Rogers/ FIRM 90 65 70 A 85 66 77 B 90 60 70 C JUROR 90 60 70 D Transbay Transit Center & Tower

Design & Development Competition 92 50 67 E 90 50 70 F 94 73 77 G TOTAL 631 424 501 AVE. 90 61 72 RANK 1 3 2 7 0 0 2 10 42

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 09 • Scores, Ranking & Recommendation

rhtcue rtc f h Bso Globe. Boston the of critic architecture as work his for the Criticism for of Prize Pulitzer recipient a is Campbell Robert ROBERT CAMPBELL, COMPETITION JURY 10 t ouba nvriy H lvs and lives He works inCambridge,Massachusetts. University. Columbia at Program Journalism Arts National the in Michigan. In 2003 he was a Senior Fellow at Professor Visiting Fisher Max 2002 the as recently most universities, several urbanism, at architecture taught has and architecture, Times, York New the for poetry onand culture, popular reviewed has books He Rome. in Academy American the at architect-in-residence was he 1997 In publications. numerous and Monthly Atlantic the poems in appeared Traveling His have Prize. Appleton Kelley where and the Fellowship Design, received of he School Graduate Harvard the and Journalism; Graduate of School Columbia the Kappa; Phi Beta to elected was he where College, Harvard of graduate a is Campbell Mr. profession.” the to and architecture to contributions outstanding of recognition “in Architects, of Society Boston the of is He the recipient of the 2004 Award of Honor Sciences. and Arts of Academy American the and Architects of American Institute the of Fellow a is and cities, and institutions cultural to consultant a as 1975, since architect an as practice private in been has He city.” of American bookshelf the on anyone who cares about the fate of the wrote “belongs Tribune it Chicago that the which of Time, Through of City American An Cityscapes Boston: book, a and of the author the for Record, is columnist Architectural bimonthly magazine a is He elsewhere and i poorps in photographs his

FAIA ois Se s nentoal kon for known internationally is She topics. she these on and publications 30 than more has behavior, travel development on development patterns land transportation land of impact the of and on impact investments the relationships the use, both land and on transportation between focus interests the of University the of California at Director Davis. Center Her research the Transportation University and Policy and the Science in Environmental Professor of a Department is Handy Susan Dr. SUSAN L.HANDY, Transbay Transit Center the from Planning University ofCaliforniaatBerkeley. Regional and City in Ph.D. a Engineering and University, Civil Stanford from in M.S. an University, &a B.S.E. in Civil Engineering from Princeton Tower has of the World Health Organization. and She has the Council participated in the Health Cities program and Research Medicine of National Institute the of committees on served has She journals. boards editorial of several the international academic and Foundation, Wood Johnson Robert the by funded program Committee of Advisory the Active Living National by Design the Board, Transportation Research the Issues of Transportation Women’s in and Behavior, Travel and Telecommunications Development, Land and Transportation on Committees the of member a is Handy Dr. practice. and policy to research link to ability for her in planning transportation respected walking of field widely the is and and behavior design neighborhood her research on the connection between Design & Development Competition P h D

COMPETITION JURY 7 0 0 2 10 43

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 10 • Competition Jury

ein. hs nvra apoc allows approach universal This designs. a unique perspective to Hodgetts adds + Fung’s environments urban Architecture. various in her and countries, several comprehension of the Design in human experience lived Having Fung Hodgetts + of principal/co-founder and Hsin-Ming Fung is an architect, educator, HSIN-MING FUNG, itnuse Vstn Poesrhp at Professorship Ohio StateUniversity. Visiting Distinguished Baumer Herbert the to appointed were they 1996, in of and Design, Professors Architectural Visiting Saarinen Eero as University Yale to invited were Fung Ms. in and Hodgetts Mr. 2000, as well as Design 1995, Environmental In 2002. to 1985 from California Pomona, of School the at California professor State Polytechnic a University also was She Programs. Graduate of Los Director the currently is she Southern California, at California Institute of taughtArchitecture, of where has and University Angeles, the at Architecture of Master her earned Fung Ms. Architects. of Institute American the of chapter Angeles Los the In from Medal Arts. the 2006, Hodgetts+ Fung received the Gold for Endowment National the for Council the on serve in to Clinton Academy President by American nominated was and Rome, the Fellowship through Advanced Prize Rome addition, NEA the of In recipient 1991 the Art. was Fung Ms. Modern of Francisco Museum San the and Angeles, Los in Art Contemporary of Museum The Aires, Industry, the Museum of Fine Arts in Buenos the Museum of Science and Hollywood Boulevard. on Her work Theater has been Egyptian exhibited renovation the at the of and Tokyo, in Gakuen Yamano for tower glass 35- mixed-use story the Bowl, Hollywood famed the of design new the UCLA, at Library ‘Towell’ temporary award-winning the including the execution of all of the firm’s projects, in engaged been has Fung Ms. Fung, + compromising vitality. As Director of Design for Hodgetts without accessibility for AIA raiain ad let t fr a form community to with clients work and to organizations ability integration. His development and design commercial planning, transit on focus a with Florida, and Louisiana Alabama, Ohio, Georgia, in projects planned and in constructed projects. He has designed Harris has completed more than $3 billion areas. urban major other and Atlanta of fabric urban the of transforming years, multiplicity projects, a 30 designed has over firm the For Associates. Turner name the bearing work design the of all oversees and vision strategic firm’s the for responsible is He Georgia. Atlanta, in Inc Planners, and Architects Turner Associates of Director Creative and Board the of Chairman Founder, is Harris Oscar OSCAR HARRIS, Transbay Transitprofession. the to contributions his for Architects of Bronze Medal from the American Institute the awarded was he 2004, serves In trustee. as Center also he where University Carnegie Mellon from Architecture of Master a and Pennsylvania in career. University Lincoln from Arts of entire Bachelor a holds and Harris his Mr. design & issues specialized facility connectivity has transportation Tower He in Authority. Rapid Atlanta Transit Metro the for contract Consultant Engineering General the Principal in a is he Additionally, Georgia. Hartsfield Atlanta, of in Airport International Jackson expansion airport billion $5.4 the of management program the for Consultants) IAC Aviation in (International Principal a is He Orleans”. of New Rebuilding “The for for member Conference panel ULI Around a was Development and Transit, Successful for contributing author of ULI’s Ten Principles Urban Land Institute, Mr. Harris was also a community for and civic visioning. As Past Trustee of the Definition” “Project in expert premier a become to Associates “visioning workshops” has allowed Turner interactive through vision of consensus Design & Development Competition FAIA

COMPETITION JURY 7 0 0 2 10 44

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 10 • Competition Jury

sae n rdvlpet community. redevelopment and estate real the in authority recognized a is and Marston Keyser of principal founding is projects a He development. estate on real consulting evaluating and of in Marston’s feasibility life the Keyser professional his spent entire has Keyser, Board, the of Chairman Jerry A. A. JERRYKEYSER aba lh, n nentoa land international economics society. an of Alpha, president Lambda past as well as initiatives, government and planning promote to Francisco leadership organization formed San a SPUR, of member board past also is Keyser Mr. growth. region’s the in assist in to government leaders and education business, of an composed Forum, organization Economic Area Partnership Bay the of member Public/Private board former a is He Council. the Council Use Mixed and ULI a chaired has Institute, Land Urban the of is member a Keyser Mr. University. Columbia from of Cornell University and earned his MBA graduate a is He implemented. be can downtown develop that strategies revitalization and/or retail to efforts their in towns and cities assisting in experience extensive had multi- also has He on projects. use consultation and of analysis in involved extensively been has Keyser the Mr. career, throughout his Throughout States. United and community development what financial the trends, with contacts estate and development, estate unique real real in works Keyser in Mr. insight give groups to professional combine and work industry and with knowledge experience, Portland. in His Place San Pioneer in and Plaza Diego, Horton Francisco, San in Ballpark AT&T impactincluding developments high and distinguished West’s the of many of center the at been has Keyser Mr. years, thirty than more the For ein eiw omte, n o the on and Committee, Review Planning Design Capital Berkeley’s California, of University the on serves She Design. of Loeb School Graduate a Harvard the at Fellow was and Berkeley, California, of of University the Master’s from both a Architecture and art of in practice degree the Bachelor’s a Ms. Francisco. holds San Williams in Merrill Skidmore, & with Owings partner associate that was to prior and 2004, to 1997 from was Ai for design Williams of director and principal Ms. the developments. mixed- Francisco’s civic use and high-rise corporate urban, and San including headquarters facilities, projects cultural institutions, Perkins+Will major for strategy design the sets Williams Allison ALLISON G.WILLIAMS, Transbay Transit CenterAwards Programs. Design Architects various of for Institute American and Record/Business Awards Design Architecture Week the for &juror for design award programs recently Towerinvited an schools as serves and architecture of at Ms. frequently Magazine. lectures Williams Ebony and Magazine Enterprise Black Report, World and News US Journal, Street Wall Times, York New The in appeared recently have Williams about articles Featured Francisco. San in Women of Museum International the Center for African American Culture and Terminal, and Airport currently the August Wilson International Francisco Complex, San Center the Civic the Francisco including San projects winning award several of design the in roles leadership in advisory Fellow design are credit her To 1997. in AIA the to elevated Magazine was the and board to Design appointed Harvard recently was She Exploratorium. The and Diaspora African board of directors for the Museum of the Design & Development Competition FAIA

COMPETITION JURY 7 0 0 2 10 45

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 10 • Competition Jury

n h aayi ad ein f complex of design and and analysis structures the of in design seismic and design experience in the seismic analysis over 35 years of professional has engineering Johnson Mr. 1974. in office Oregon the opening a since held has office, he position Portland KPFF’s of in-charge Art Johnson is vice president and partner- ARTHUR JOHNSON, n sabl Tre. e evs s chair as serves He Doernbecher Turkey. Istanbul, in Center, Childrens Hospital, and the US Consulate Convention most Oregon the including firm’s projects, complex the of many on structural engineer” “design the as acts Johnson Mr. engineering, structural for in-charge principal- As systems. framing structural PE, SE states. 27 in Engineer Professional registered a is He Berkeley. at California of University degree in Structural Engineering from the in Civil Engineering and Master of Science received his Bachelor of Science degree Johnson professor Mr. Oregon. of University adjunct the at an is He Oregon. of Council Engineers Consulting the of and Council of American Structural Engineers of Oregon. Mr. Johnson is past chair of board the a member of the Architectural Foundation as and the Oregon, at of University Arts Allied and School Architecture the for of Visitors of secretary Board the University, of State Portland at Board Advisory College Maseeh the of Transbay Transit Center & Tower Fung, to left: Susan Handy; FAIA Robert Campbell, Competition Jury

Design & Development Competition ; Dean Macris, AIA. Arthur Not picture Johnson, A. JerryKeyser. :

B FAIA; ack row,righttoleft: FAICP; d: MariaAyerdi. PE, SE; Allison G.Williams,

Oscar Harris, Frontrow,right

Hsin-Ming FAIA ; 7 0 0 2 10 46

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 10 • Competition Jury

ein cntuto ad prto of Terminal/ Transbay dollar multi-billion the operation and construction design, of Board Directors, Ms. Ayerdi is responsible for three-county the member, five Authority Powers Joint Director Executive As MARIA AYERDI, NON-VOTING Center Project. the advancement of the Transbay Transit courage and determination have been crucial to experience, skill, Ayerdi’s Ms. tax that sales transfer recognized generally is It extension. Francisco San land and increase the toll Bridge voter-approved a proceeds, including Project in funds, billion $1 Transit over Transbay aggregated has Ayerdi Ms. the total, In towards Project. of Center applied funding be the this will from result transaction will that revenues The Transportation. of Department California San prime Francisco landbelongingtotheStateof of of acres 19 transfer approximately the negotiated effort Ayerdi this Ms. personally TJPA, of the of part behalf As on and Project. the of Phase first the construct and design to necessary funding of the developed and Record federal identified She issued. been has Decision A requirements. (CEQA) California and (NEPA) Federal under cleared been now has EIS/EIR The the managed She Project’s environmental (EIS/EIR) process. (TJPA). Authority Powers Joint Transbay the formed Ayerdi which Ms. Project, Agreement Powers Joint the the developed of behalf On professionals. other and architects engineers, 200 over includes now team delivery Her Project. Center the Transit Transbay the of elements manages and all of development Ayerdi and design ongoing directs Ms Center). currently Project Transit Extension (Transbay Downtown Caltrain EX OFFICIO JD

f h Transbay the of eotn t a to reporting MEMBERS a Facso oorws nug Hero with Unsung Tomorrow’s honored Francisco was San Ayerdi Ms. 2002, In she department. work, service public worked with United Parcel Service’s legal her to Prior Roundtable. Airport the of member and the Association of Bay Area Governments of Committee Executive the District, of member Management Quality Bay Air the Area of Director Deputy (Caltrain), the Peninsula Corridor Joint Powers Board Director and has been the Vice-Chair of Transportation Policy Advisor and Project Francisco’s San previously of Mayor the She as served California. of Bar Hastings State and the of member a is She Law. Berkeley of College California, of Ms. AyerdiisagraduateoftheUniversity Transbay Avenue, Ness Van as locations Transitsuch in housing more many enable to zoning plans and the districts, for all retail/commercial of City’s plans rezoning a neighborhoods, plan, downtown Centerrecognized Department nationally a including efforts planning the significant several direction completed his Under &1992, andfrom2004tothepresent. Towerthree occasions: In 1975 to 1976, 1980 to Director. He has served that capacity on Planning Francisco’s San is Macris Dean DEAN MACRIS, Area Bay Influential Latinos. Most 2006 the of Chamber of Commerce named her one Hispanic the year, same That Area. Bay Influential Women in Public Service in the Times named Ms. Ayerdi One of The Most Project. In 2006, the San Francisco Business for her success in advancing the Year, Transbay the of Woman Francisco Chapter, Area Bay San Seminar, Women’s Transportation the named was she 2004, In Francisco’s San contributions environment of and Bay betterment special Area transportation. the her to for Award, Design & Development Competition FAICP 7 0 0 2 10 47

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 10 • Competition Jury

Consultant to the San Francisco Giants on in planning. He has several also served national received and as state awards Planning for excellence has Department the leadership his Under architecture. and advancing The design skyline, urban preservation, of cause the city’s the in Hill. shaping instrumental been Rincon has Department and Mid-Market American InstituteofCertifiedPlanners. Planning Association. He leadership is a Fellow of the American of the and Administration Society Public personal American the from awards received and Mayors Francisco San four under served has He Development. and Planning of Department Commissioner, Assistant him In 1965 Mayor Richard J. Daley appointed Chicago. in career his began Macris Mr. Gate Park. Golden in program rebuilding Sciences’ of Academy California the to and park baseball team’s the of construction the

Transbay Transit Center & Tower Design & Development Competition 7 0 0 2 10 48

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 10 • Competition Jury

nldn dsg, einbid A/E design/build, design, including competitions, 50 over run has Architects StastnyBrun years, twenty past the Over STASTNYBRUN ARCHITECTS,INC. COMPETITION MANAGER 11 h poes a bcm a oe for model a become has process The process. competition equitable and fair a maintaining while builder/contractors the and teams, architect/engineer the that client, the between process interaction allowed selection design/build a created StastnyBrun Lindquist, Kling with into program construction in ten months. from Collaborating embassies moved two process the The 1998. in Salaam, es Tanzania Dar and Kenya Nairobi, in had been torn apart by that embassies terrorist two bombings the for competition Berlin. design/build a in managed and created embassy StastnyBrun U.S. association, this Continuing new the for their competition design the of management with began State U.S. of the Department with relationship StastnyBrun’s (GSA). Administration Services General the U.S. Department of State and the U.S. design run competitions and selection processes for has Architects StastnyBrun Recognized for their superb qualifications, raise communities’expectations. and work best their do to designers for environment an create that processes author and icon. designers the promote They the beyond far reaching effects catalytic have that fabric urban the in they interventions creating on focused competitions, have design managing and authoring initiating, of years twenty create StastnyBrun’s to in but icons, used architectural been historically has process competition design The experts. competition premier nation’s the of one the firm and Don Stastny’s recognition as in resulted has experience of depth This selection, and other innovative processes. and used the processes and outcomes and processes in the used and courthouses GSA the for U.S. Massachusetts and Oregon for competitions design concurrent Legacy”. two undertook a They Building – Excellence Guide Architects Design Program StastnyBrun “The the GSA, authored the For rebuild. Nation’s to ourTanzania and Kenya to met commitment and and time budget, record within in completed were U.S. embassies two The State. of Department the for projects design/build other Transbay team collaborative the members survivors, family and including force, Transittask volunteer 350-member a bombing. with the Working of survivors and victims the to dedicated memorial a to develop process design a facilitated Stastny Centerfor the Oklahoma City National Memorial. lead an international design competition selected through a nationwide search to collaborating a team of with Helene Fried and &Paul Stastny, Morris, was Donald Towerthe GSAprocess. of guidelines general the within realized be could requirements, issues critical embassy these how security and of and understanding programs their on based process this undertake to asked China Projects portfolio. StastnyBrun was the in those particularly embassies, U.S. protocols to apply to design selection for GSA the modify to State of Department U.S. the publication, assist to its asked and was After StastnyBrun federal agencies. other state for methodology selection state-of-the-art as GSA’s adopted be for to begun basis has and program the acclaimed be to continued on has GSA, by guidebook published guidebook, The the processes. selection for Excellence Design basis the as Design & Development Competition 7 0 0 2 10 49

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 11 • Competition Manager

enyvna at er Wrig in Working year. conjunction with the Families of Flight 93, last International Pennsylvania Memorial County, Somerset in Competition Design National Flight the 93 for advisors competition as Architects served also Associates Fried Helene with StastnyBrun administration. competition and development program was responsible for community outreach, n panr h hs en honored been has he architect planner, award-winning and An models. national become have which of plans, many and commissions, competitions, for processes he international and 50 national over addition designed and In developed has renovations, centers. cultural historic and buildings, office housing, multi-family museums, and regions, cities the neighborhoods, including of projects planning of taken range has a and on Stastny Mr. nationally, of internationally. locally, expectations architecture and understanding public’s the elevating toward works he tool, strategic design and communities, comprehensive a as Using for culturally. rebuilding and facilitator physically years and thirty designer, architect, practicing Architects, urban a been StastnyBrun has Inc. Portland’s CEO of and founder a Stastny, J. Donald Competition Manager DONALD J.STASTNY, Center Community (RJKCCC) forTheSalvationArmy. Corps Kroc and Ray Joan Chicago the for and Alaska Juneau, in Capitol Competition Designer/Design State competition Alaska the for processes international facilitated and authored recently also StastnyBrun two-stage competition. a design a through created park national first the to managed leading process competition advisors competition the Service, Park National the and Commission, Advisory 93 Flight Force, Task Memorial National 93 Flight FAIA, FAICP f oo “n eonto a a member a as recognition “in Honor of Medal Region’s Architects Pacific of and Northwest Institute American 2006 the awarded was He Greece. Athens, in and Ekistics of Center the at Fellow Research Pennsylvania, of continued his post-graduate studies as a University at Architecture Design) (Urban the in Planning City degrees and Masters received his the He and Washington. from of Architecture University, Administration University of State Bachelor Business a Oregon in from degree Science of Bachelor his received Stastny Mr. Planners. of Institute Canadian the of of Urban Institute Design. the Additionally, and he is Planners, a Certified member of Institute American the Architects, of Institute American the in Fellowship with Transbay Competition and for the Chicago Ray and Joan Kroc Designer/Design State Transit Alaska Capitol the for the manager as project served Mannhard Ms. development projects. and planning, visioning, and Centerparticipated in numerous community coordinated also has she outreach, and processes public about Knowledgeable sustainable design and business practices. advance and integrate to entities profit non- and private & with worked has She Towerwhile remaining cognizant of finer details. picture big the considering perspective, from both environment a comprehensive and built focused the understands development. She estate real and and design, experience urban planning, architecture, in has training She Architects. StastnyBrun with manager project and Jennifer Mannhard is a professional planner Project JENNIFER MANNHARD, Northwest andPacificRegion”. AIA the to unique contributions notable made has who and Architecture, and Architects of understanding public the in consistently excellence design, and the has practice of long Architecture, who life demonstrated Region the of Design & Development Competition Manager AICP, LEED ® AP 7 0 0 2 10 50

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 11 • Competition Manager

n oese te ulcto and publication materials, competition the all of distribution oversees and between competitors and information clients, Memorial of creates exchange She the National manages Competition. 93 Design Flight International the on assistance facilitation and provided coordination also She Army. Salvation The for (RJKCCC) Center Community Corps etfe b te ainl Charrette National the Institute. Planner by Charrette certified and Professional, LEED of a Institute Planners, Certified American a the is She of member University. State Portland at Development Estate Real in Certificate Urban & Regional Planning and of Graduate Master her completed and University A&M Texas from Design Environmental of Bachelor her received Mannhard Ms. processes. competition the of execution and ensures successful coordination and For moreinformationpleasecontact: STASTNYBRUN ARCHITECTS,INC. Or visittheCompetitionwebsite: ® [email protected] Accredited www.transbaycenter.org [email protected] (503) 222-5533 ®

Transbay Transit Center & Tower Design & Development Competition 7 0 0 2 10 51

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 11 • Competition Manager

Competition Man APPENDIX 1 Question &Answers Request forProposals 2 ual

Transbay Transit Center & Tower Design & Development Competition 7 0 0 2 10 52

SEPT TRANSBAY TRANSIT CENTER & TOWER Design & Development Competition 12 • Appendix

Competition Manual **UPDATED FOR STAGE II**

Transbay Transit Center & Tower Design & Development

DESIGN & DEVELOPMENT COMPETITION Competition

To select the Design and Development Team most qualified to design a world class Transit Center to be developed by the TJPA in downtown San Francisco, California, as well as design and develop a world class mixed-use Tower adjacent to the Transit Center.

Stage II: Request for Proposals (RFP) RFP and Updated Competition Manual Released - February 23, 2007 Stage II Briefing - March 1, 2007 1st Mid-Course Review - Week of April 16, 2007 2nd Mid-Course Review - Week of May 21, 2007 Proposals Due - July 10, 2007 (Revised Addendum #2 - 5/17/07) Transbay Transit Center & Tower 05/17/07 02/23/07 APPENDIX ...... CONTACT INFORMATION COMPETITION MANAGER ...... COMPETITION JURY ...... COMPETITION SCHEDULE COMPETITION REGULATIONS ...... COMPETITION SPACEPROGRAM ...... FINANCING THEPROGRAM THE TRANSBAYTRANSITCENTERPROGRAM ...... OVERVIEW OFTHEDESIGN&DEVELOPMENTCOMPETITION EVALUATION OFSTAGEII – DESIGN ANDDEVELOPMENTPROPOSALS EVALUATION OFSTAGEI – RESPONDENT QUALIFICATIONS ...... J. I. H. G. F. E. D. C. B. A. 16. 15. 14. 13. 12. 11. 10. 9. 8. 7. 6. 5. 4. 3. 2. 1. Site Map ...... TJPA ...... Funding ...... Timeline ...... Program Elements ......

Summary Report ...... Competition Schedule ...... Competition Address ...... City Code Contract Disadvantaged BusinessEnterprise(DBE)Participation Exhibition ofCompetitionSubmittals Honorarium &OwnershipofCompetitionSubmittals ...... Competition Manager ...... Jury ...... Disqualification ...... Eligibility toCompete ...... Mandatory RequirementsforStageIID/DProposalSubmittal Mandatory RequirementsForStageIQualificationsSubmittal Communications Competition Procedure Quality Management SystemManual Transbay Transit CenterBuildingScopeDefinition Report Protest Procedures Licensing Requirements Certification RegardingLobbying Certification RegardingDebarment, Suspension,andOtherResponsibilityMatters Levine Act Disadvantaged BusinessEnterprise ProgramRequirements Disadvantaged BusinessEnterpriseProgramRequirements Disadvantaged BusinessEnterpriseProgramRequirements Award ...... Provisions ApplicabletoAgreementswithTJPA (Updated)

(Updated) (Updated) (Updated) (Updated) TABLE OFCONTENTS ...... (Inserted) ...... (Updated) ...... (Updated) ...... (Updated) (Inserted)

...... (Updated) ...... (Updated) ...... (Updated)

31 30 28 25 23 21 20 16 16 14 10 10 19 19 19 19 18 17 17 17 17 16 8 7 6 4 2 8 5 5 5 4 4 COMPETITION FOR STAGEII UPDATED MANUAL 1

Transbay Transit Center & Tower - Design & Development Competition TABLE OF CONTENTS 02/23/07 listed Respondents toparticipateinStage II. short- the of part or all invite will Board TJPA The II. of Stage in list participate to short invited be a to Respondents Board”) (“TJPA Directors of Board TJPA the to recommend will Jury the evaluation, the of completion Upon Respondents. the of interviews and submissions written the evaluate will Jury The and managementapproach. Respondent’s the expertise, of breadth members, team Respondent all of credentials experience, consider relevant organization, will Jury the Finally, success. financial and design exceptional combines that project development mixed-use high-rise, a deliver to capacity Respondent’s the evaluate also will the Jury The profile. evaluate individual and will performance, philosophy, design Jury work, of I portfolio The Designer’s Lead qualifications. Stage Designer’s in Lead Accordingly, the on emphasis Tower. heavy and place will Center Jury Transit the the for quality design superior expects TJPA The Transit the Center andTower. for consultants special and engineers, architects, executive a separate retain to Tower, elect may and Designer Lead the Center functions, distinct RFQ have Transit will buildings two the the the Because professionals. development both to design responding to Teams Designer and design other and engineering, architectural, of team full a and Tower, the for Entity Development Lead D/D a excellence. identify design must (“Respondents”) maintaining while project development complex high-profile, this execute to creativity recommend and will expertise, experience, professionals the development possessing estate Teams D/D real and design recognized of Jury a I, Stage In STAGE I:REQUESTFORQUALIFICATIONS(“RFQ”) as theCompetitionManager.Theprocesswillbeconductedfollows: The Competition will be managed by StastnyBrun Architects, Inc., which has been retained by the TJPA The TJPAstronglyencouragestheD/DTeamstoreflectdiversityofSanFranciscoBayArea. the OptionAgreementtobenegotiatedbetweenTJPAandselectedTeam. by and Team D/D winning the by submitted Proposal the by determined be shall development Tower construction documents, and construction administration services. The financial and other terms of the The scope of architectural/engineering services for the Transit Center and Tower will include all design, processes. elements listed are to be designed and constructed by other teams selected by additional the other TJPA The though other Competition. this through selected Team D/D the by designed be will ramps the only elements, additional these Of facilities. storage bus permanent and Center, Transit the to Bridge Bay the connecting ramps terminals, bus temporary King, and Fourth at station surface existing the to King Streets to the Transit Center, a new underground Fourth and Townsend Street Station, modifications includes several additional elements: the rail tunnel and rail systems to extend Caltrain from Fourth and which (“Program”), Program Center Transit Transbay larger a of part are Tower and Center Transit The development proposalandforsecuringallentitlements. Act Quality Environmental (“CEQA”) California is complete. The selected D/D the Team will be responsible for under environmental review of its Tower Center Transit the for review Environmental (“City”). Francisco San of County and City the of authority the under process entitlement the during and TJPA mix of uses in the Tower is to be determined through negotiation of a Tower Option Agreement with the of uses, such as residential, hotel, office, retail, and cultural, that will complement the Transit Center. The High-Speed Rail, leased commercial space, and TJPA administrative space. The Tower will contain a mix California future the trains, commuter buses, accommodate will Center Transit new The Streets. Mission be should buildings designed the in structures, tandem. complex The and site large of be the Transit will Center Tower and and Tower is Center the Transit existing the Transbay Because Terminal at First and Area, andtheStateofCalifornia. Bay the Francisco, San for transit rail and bus of focus the and Area Redevelopment Transbay the of centerpiece the as position their of worthy are excellence technical and functional, aesthetic, whose Transit Center. The TJPA seeks a the D/D to Team adjacent Tower that mixed-use will a in create develop a and TJPA design unique, the to world and by class California, Francisco, Transit developed San Center downtown be and Tower to Center Transit a design to Team (“D/D”) a Development select and to Design Competition international an conducting is (“TJPA”) Authority Powers Joint Transbay The OVERVIEW OFTHEDESIGN&DEVELOPMENTCOMPETITION COMPETITION FOR STAGEII UPDATED MANUAL 2

Transbay Transit Center & Tower - Design & Development Competition OVERVIEW OF THE COMPETITION 02/23/07 akn Rsodns o peetto t te or i Sae I Te uy il lo e epnil for responsible be stage donotmeetthestandardssetbyTJPA. also either will in submitted proposals Jury the that The determines it if II. Competition the Stage of termination in recommending Board and the II Stage to to presentation advance for to Respondents I Stage ranking in Respondents recommending for responsible be will Jury The THE COMPETITIONJURY the TJPA. design of the two structures and define the financial and legal relationship between the D/D Team and terminate theselectionprocessatanypoint.TheAgreementsshallcontaindetailedstandardsfor to right the reserves also TJPA The Team. ranked second the with negotiations commence and team top-ranked the with negotiations terminate to right the reserve Board and Staff TJPA the then Board, fails to agree to terms for the Agreements that the TJPA Staff can Team recommend the for If approval Directors. by of the Board TJPA TJPA the by approval for recommend to willing is and Program the of Design a and Tower Transit the interests best the for in be to considers Staff TJPA the that (Agreements) Center Transit the for Agreement Agreement Option Development and the with Design negotiate a shall Team staff TJPA selected Team. a with negotiations exclusive in engage to staff may authorize discretion, sole its in and, report staff TJPA the and Report Jury the consider will Board TJPA The CONTRACT and TJPA’sstaffreportselectaRespondenttobeinvitednegotiate. The Jury will rank the Proposals for the TJPA Board. The TJPA Board will review the the TJPA’s Jury’s requirements, recommendation and the potential revenue to the Program from the development of the Tower. will Jury evaluate The the Respondent. quality each of of the presentation proposed oral design, and functionality submission of written the the Transit consider Center will and Jury Tower, The adherence to will presenttheirProposalstotheJury. technical review and the Respondents’ this responses Following clarification. request to or Respondents question questions to and criteria and minimum with compliance requests for clarification, Respondents The Competition Manager and TJPA staff will review the technical aspects of the Proposals to determine of theProgramManagement/ProgramControl(“PMPC”)Team. members and staff, TJPA the Manager, Competition the with reviews mid-course two in participate to have a minimum of 120 calendar days to prepare Proposals. Each Respondent will have an opportunity two structures, the budget for the Transit Center, and other requirements for Proposals. Respondents will Stage II, the TJPA will provide the Respondents with an information packet describing the scope of the of commencement the At Property”). (“Tower Tower the for site the of lease ground or purchase the for terms financial proposed including Tower, the of development and design the for Proposal a and Respondents invited to participate in Stage II will prepare a Proposal for the design of the Transit Center, STAGE II:REQUESTFORPROPOSALS(“RFP”) (Updated) AWARD COMPETITION FOR STAGEII UPDATED MANUAL 3

Transbay Transit Center & Tower - Design & Development Competition OVERVIEW OF THE COMPETITION 05/17/07 was constructed in 1939 and no longer meets current or current meets longer no and 1939 in constructed was Terminal Transbay current The Angeles. Los to Francisco Transit, AC MUNI, San from Rail High-Speed California future and SamTrans, systems: Greyhound, Transit, transit Gate Golden state Caltrain, BART, connecting and hub transit regional modern eight a with in Francisco streets Mission San the and replace First at will Terminal Transbay Program current Center Transit Transbay The (Focus ofDesignandDevelopmentCompetition) Transbay TransitCenterandTower offices, parks,andshopssurroundingthenewTransitCenter. accommodations for future California High-Speed Rail; and creating a new neighborhood with homes, its current terminus at Fourth and King streets to the new downtown Transit Center and development of Mission streets in San Francisco with a new modern Transit Center; extending Caltrain underground from The Program consists of three interconnected parts: replacing the outdated Transbay Terminal at First and PROGRAM ELEMENTS THE TRANSBAYTRANSITCENTERPROGRAM Bay, cafes, andmarkets. and neighborhood will feature widened sidewalks, new views of the San Francisco this of centerpiece Street the Folsom be will Center. Transit the in retail including not retail, of hotel feet square 60,000 and office, space, commercial and new of feet square million 1.2 affordable), thriving, a Redevelopment Plan includes 3,400 into new homes (with 35% The Street development. sustainable for Market model transit-oriented of south Francisco San will transform a currently 2005, underutilized in Agency section Redevelopment of Francisco downtown San the and City the by adopted Plan, Redevelopment Transbay The New Neighborhood Rail High-Speed and railconnectionstotheEastBay. future accommodate to designed be will Center Transit and line rail The streets. Townsend and Second under alignment an through Center Transit the new into Caltrain extend and streets King and Fourth at available, the TJPA will modify the existing Caltrain station becomes funding as the or 2012, of in begin phase to slated project, second from the miles In 1.3 Francisco. San however, downtown ends, currently Caltrain San connecting and Jose. Valley, by Silicon Peninsula, link the to regional Francisco vital San a as serves Caltrain (Not partoftheCompetition) Caltrain DowntownExtensionandFutureHigh-SpeedRail provide additionalfinancingfortheProgram. and skyline an City’s the be redefine to will that expected presence iconic is Tower Transit the The to Center. adjacent Transit built be will Tower Transit mixed-use A below-grade trainstation. address the entire Transit Center, including ramps and the should design The Bridge. Bay Francisco-Oakland San the ramps that will connect to new a new off-site bus storage facility with includes I Phase future Rail. High-Speed and California Caltrain serving levels below-grade two for foundations and retail concourse-level and floor ground level, bus above-grade one with construction Center Transit new a include of will Program the of phase first The future capacityneedsfortheregionorstate. (Not partoftheCompetition) (Revised) COMPETITION FOR STAGEII UPDATED MANUAL 4

Transbay Transit Center & Tower - Design & Development Competition THE TRANSBAY TRANSIT CENTER PROGRAM 05/17/07 Board-Caltrain, andtheCaliforniaDepartmentofTransportation(exofficio). County of San Francisco, the Alameda-Contra Costa Transit District, the Peninsula Corridor Joint Powers the of current Transbay site Terminal. The TJPA is led the by a six-member Board on of Directors representing the facilities City and associated and center transportation new a maintain and design, operate to build, 2001 in formed was TJPA The TJPA. the by headed is Program Center Transit Transbay The TJPA funded bylocal,regional,andfederalsources.FundingfortheRailExtensionisnotcomplete. billion, escalated to the year of expenditure (YOE). Phase I is funded at $983 million (YOE). The project is The TJPA estimates that the cost of the Transit Center and Caltrain will be $3.4 FUNDING in 2018,orasfundingbecomesavailable. 2014. in completed be and 2010 April in completed be and 2012 in begin to expected is Extension Rail Downtown Caltrain the of Construction begin will building Center Transit new the of Construction Phase I of the Program is scheduled to begin in 2008 with the construction of a temporary bus terminal. TIMELINE KEY COMPONENTS AND PROJECT AREA (Revised) COMPETITION FOR STAGEII UPDATED MANUAL 5

Transbay Transit Center & Tower - Design & Development Competition THE TRANSBAY TRANSIT CENTER PROGRAM 02/23/07 as independent buildings. a seamless connection at the ground level and concourse first level above grade, but should function constructed be should buildings with lobby main single a share should buildings two The necessary. if construction sequential for allow two The Tower. Transit and line simultaneously asseparate projects,butthedesignforTransitCenterandTower shouldalso match building project Center a shows Transit complex. Drawings, the Definition Center Scope between Transit Report, one Definition Scope as the appear of to Six Volume and excellence, design compatibility, architectural for designed jointly be must that projects separate are Tower Transit the and building Center Transit The CONSTRUCTABILITY OFTRANSITCENTERAND TOWERPROJECTS development entitywillprovidecapitalforconstruction oftheTransitCenter. In Competition. the consideration in for selected acquiring an entity interest in development the the Tower site by and the entirely right funded to develop be the Tower, will the Tower selected Transit The Constraints. and Requirements Design Two: Volume of Report, Definition 4.18 Scope Program Table Center Transit in Transbay the contained dollars current in estimate preliminary the is building Center Transit the of construction for limit budget fixed TJPA the Competition, purposes Development and For Design the of building. II Center Stage of Transit the of construction for limit budget fixed TJPA the exceed not does that analysis cost a II Stage in submit Team Development and Design each that require Manual Competition the in contained regulations Competition building The Center TJPA. Transit the by The funded be will projects. construction separate are Tower Transit the and building Center Transit The TRANSIT CENTERBUILDINGANDTOWERPROJECTSCONSTRUCTIONCOSTS website: The Transbay Financial Plan is described in a March 2006 report. This report can be viewed at the TJPA’s Tower (theProperty)isexpectedtoprovidesubstantialfundingfortheProgram. to theTJPA. funds allocating and programming, planning, for responsible are that agencies following the include partners funding TJPA’s The sources. local and regional, state, federal, from funding receives TJPA The Definition Reportandislessthan$983million.)PhaseTwofundedinpart. Scope the of 2 Volume of 4.18 section in identified is responsibility design have will Team the which for building Center Transit the of Two and One Phases of cost construction direct $983 (The of funded. One is Phase million for estimate cost Program total The Center. Transit the into underground Streets level rail below-ground the of design and component of storage; the Transit Center. bus Phase Two extends and the Caltrain rail ramps, line 1.3 miles bus from Fourth and foundation, King rail the Center, Transit Center is under construction; design and construction of the above-ground portion of the Transit new the while passengers serve to terminal bus temporary a of construction and design includes One Phase Program. billion $3.4 the build to plan two-phased a approved Board TJPA the 2006, 2, June On FINANCING THEPROGRAM to these sources of funding, the sale or long-term groundlease of the property underlying the Transit the underlying property the of groundlease long-term or sale the funding, of sources these to transit operators using the Transit Center, and net operating income from the Transit Center. In addition the Transbay Redevelopment Project Area, passenger facility charges and/or other commitments from in parcels state-owned the from funds increment tax include loan construction the repay to used be will that sources revenue Long-term loan. period construction a includes Plan Financial Transbay revenue the long-term identifies Plan Financial Transbay Program, the of portion a completes TJPA the until available be not will funds these Because the streams. revenue, of sources these supplement To term. near the in available opportunities generating revenue one-time other acquired and parcels, right-of-way from income lease proceeds, sales land grants, with costs capital its fund will Program The • • • • Caltrans California TransportationCommission(CTC) Federal HighwayAdministration(FHWA) Federal TransitAdministration(FTA) http://www.transbaycenter.org/TransBay/content.aspx?id=311. • • • (Inserted) San MateoCountyTransportationAuthority(SMCTA) (SFCTA) San FranciscoCountyTransportationAuthority Metropolitan TransportationCommission(MTC) COMPETITION FOR STAGEII UPDATED MANUAL 6

Transbay Transit Center & Tower - Design & Development Competition 02/23/07 intended to set a standard for design excellence. They excellence. design for standard a set to intended are reports the Program other or in Report Definition contained Scope renderings Architectural complex. establish the two buildings as a landmark transportation a however, creative architectural and engineering design that will Report, for the Transit Center or Definition the Transit Tower. The TJPA seeks Scope intentionally does not The propose an architectural character buildings. both for objective paramount a is excellence Design for useinpreparing Proposals. help to Manual Competition this six-volume report will be to provided to Respondents selected to Appendix participate in Stage II of the the Competition in provided Respondents to is understand the standards and Summary requirements for the Transit Executive Center and Tower. The entire – 1 Volume six of comprised is Report Definition volumes: Scope The are notspecificarchitecturalrequirements. to construct, economical be will that Center Transit a design to and levels optimal their at with operate to agencies transit comply must Center various the allow to requirements Transit and standards these quality the of design technical the The define and that standards, and other requirements for functional, sections the Transit Center. and organizational, plans floor building Definition Report includes narrative reports, conceptual Scope The Center. Transit the for requirements design and program space building TJPA the detailing Report Definition Scope six-volume a prepared has TJPA The COMPETITION SPACEPROGRAM quality oftheproject Volume 6 – Scope Definition Drawings: into theTransitCenter identifies the Program’s commitment to sustain Opportunities: Design Sustainable - 5 Volume velopment Area Guidelines: Design Site - 4 Volume must satisfy Standards: & Criteria Design - 3 Volume and siteconstraints of the work, design process requirements, regu provides general project background, summary Constraints: & Requirements Design - 2 Volume Volume 1-ExecutiveSummary noprtn ssanbe ein opportunities design sustainable incorporating for ideas level concept offers and design, able Rede Transbay the for plans and requirements Francisco San of County and City with sistent team design the standards and criteria nical tech the defines and design of basis the vides requirements, deliverable requirements, latory site development controls and guidelines con guidelines and controls development site the required scope, content, organization, and organization, content, scope, required the establish to areas streetscape surrounding and Center Transit the for drawings level concept operate andmaintain. provides includes pro ------ELEVATED BUSPASSENGERWAITING AREA TRAIN PASSENGERBOARDINGPLATFORM CONCOURSE ANDGROUNDLEVEL TRAIN PASSENGER MEZZANINE COMPETITION FOR STAGEII UPDATED MANUAL 7

Transbay Transit Center & Tower - Design & Development Competition COMPETITION SPACE PROGRAM 02/23/07 . COMPETITIONPROCEDURE 1. The followingregulationsgovernthisCompetition. COMPETITION REGULATIONS .. StageII: 1.2. StageI: 1.1. 1.2.1. Notification: Participant II Stage 1.1.9. Stage I Evaluation and Selection: 1.1.8. Interviews: I Stage 1.1.7. Compliance Check: 1.1.6. Qualifications: Respondent I Stage of Submission 1.1.5. Period: Answer and Question 1.1.4. Pre-Submittal Meeting: 1.1.3. Distribution of RFQ Packets: 1.1.2. RFQ Announcement and Registration: 1.1.1. participate in the Competition. The announcement will contain a description of the Transit Center of and Transit description Tower Project a (“Project”), the contain Competition process, will and other announcement The Competition. the in participate to Website Competition the on electronically register must Entities Development and Designers Lead Individual Website. Competition the on and publications, association trade media, minority-focused publications, professional newspapers, trade in appear Jury will evaluate all complying Stage I submittals and recommend the most qualified most the recommend and submittals I Stage complying all evaluate will Jury Designer and a representative of the Developer are required to attend one of the two Lead the of representative A mandatory. is Meetings Pre-Submittal two the of one at Attendance Website. Competition the to them post and tour site and briefing the of the briefing and tour to answer questions. The Competition briefing a Manager and tour attend of will the to Project prepare site. opportunity Representatives of minutes the the TJPA participants will be registered available during allowing meeting each at same Competition Manual containing information on the Project and the Competition can Competition the and Project the on information containing Manual Competition uoaial dsulf te umta, eoe h sbitl rm h Competition, the from submittal the remove submittal, the disqualify automatically will Manager Competition the Regulations, Competition these with noncompliance in with the Mandatory Requirements for Stage I Submittals. Should any submittal be found the questions will be posted to the Competition Website. The source of questions shall to answers Manager’s Competition the and questions The Address. Competition the registered participants may submit questions by e-mail to the Competition Manager at after this deadline will be late, will not be considered in the Competition, and will be will and Competition, the in considered be not will late, be will deadline this after (Pacific Time) on the date indicated on the p.m. Competition 3:00 Schedule. by Submittals Address received Competition the at received be must submittals All Regulations. Competition these in forth set Submittals I Stage for Requirements Mandatory the to RFP Distribution: participate inStageIItothe CompetitionWebsite. Respondents totheTJPABoard tobeinvitedparticipateinStageII. dates setforthintheCompetitionSchedule. notify thesender,andreturnnoncompliantsubmittal tothesender. returned unopenedtothesender. remain anonymous. Pre-Submittal Meetings. be downloadedfromtheCompetitionWebsite. pertinent information. of the TJPA Board’s decision and post the short-list of Respondents to be invited to invited be to Respondents of short-list the post and decision Board’s TJPA the of equally and without prejudice. The interviews will take place in San Francisco on the on Francisco San in place take will interviews The prejudice. without and equally evaluated be to Respondent each allows that format a in conducted be and criteria evaluation I Stage the on focus will interview The Submittals. I Stage for Requirements Request forQualifications Request forProposals Respondents invited toparticipateinStage IIwillreceiveanRFP. The Jury will interview Respondents complying with the Mandatory the with complying Respondents interview will Jury The The Competition Manager will check each submittal for compliance Two Pre-Submittal Meetings will be held. The program will be the

In response to registration on the Competition Website, the uig h shdld usin n Ase period, Answer and Question scheduled the During The Competition Manager will notify all Respondents all notify will Manager Competition The Based on the written submittal and the interview, the Announcement of the RFQ and advertisements will Responses to the RFQ must conform must RFQ the to Responses COMPETITION FOR STAGEII UPDATED MANUAL 8

Transbay Transit Center & Tower - Design & Development Competition COMPETITION REGULATIONS 05/17/07 1.2.8. Stage II Presentations: II Stage 1.2.8. ... i-ore Reviews: Mid-course 1.2.4. Period: Answer and Question 1.2.3. Briefing: Competition II Stage 1.2.2. ..2 rsnain o h TP Board: TJPA the to Presentation 1.2.12. Jury: the of Report 1.2.11. 1.2.10. Public: the to Presentations 1.2.9. Proposals: of Review Technical 1.2.7. Check: Compliance 1.2.6. Submission of Stage II Proposals: 1.2.5.

a checklist to the Jury for each Proposal indicating whether the Proposal complies with the written Proposals to the Jury, the Competition Manager and TJPA staff will provide the letter dated May 14, 2007 (“Minimum Requirements”). Simultaneous with delivery of by amended as Templates, Forma Pro and Sheet Term Model the and 2007, 1, March Report, Definition Competition Manual, Scope materials provided to the Respondents the at the Stage II of Briefing on criteria minimum the with compliance determine to Tower, the for documentation financial the and Center Transit the of enhancements operational and functionality as such Proposals, the of aspects technical the review Competition Briefing in San Francisco with the Competition Manager and representatives n wtot rjdc. olwn te rsnain te uy a ak usin and questions ask may Jury the presentation, the Following prejudice. without and conducted in a uniform format that allows each Respondent to be evaluated equally be will presentations The Schedule. Competition the in forth set dates the on Jury the to the questions will the be sent simultaneously to at the Respondents. The source of Manager questions Competition the to Competition Address. Copies e-mail of the questions and by the Competition Manager’s questions answers submit may Respondents disqualify the submittal, notify the Respondent of the decision, and return the submittal comply with the Competition Regulations, the Competition Manager will automatically for Stage II Submittals. Should the Competition Manager find that any submittal receipt does and examine not each Proposal for compliance with the Mandatory Requirements that bestmeetstheevaluationcriteria. Selection: and Evaluation II Stage presentations totheJury. discuss theProposalwithRespondent. each MinimumRequirement(“TJPAstaffreport”). to thesender. (Updated) Period. shall remainanonymous. of theTJPAtoreviewSchedule,Procedures,andStageIIsubmittalrequirements. recommendation totheTJPABoardaccompanied bytheTJPAstaff report. without selectingaD/DTeam. n h Cmeiin ceue Sbisos eevd fe ti tm wl b lt, will late, be sender. will the to unopened returned be time will and Competition, the in this considered be not after received Submissions Schedule. Competition the on received at the Competition Address by 3:00 pm (Pacific Time) on the date indicated for Stage II Submittals set forth in these Competition Regulations. All submittals must be in the same manner as answers to questions submitted during the Question and Answer Respondents the to comments the distribute and Respondents all affect that Reviews during arising issues on comment will Manager Competition The terms. financial and provide functionality, technical design, of discussion include may will Reviews The Proposal. each Reviews The consultants. of functionality Respondent, and feasibility the TJPA maximize to Respondents to the feedback constructive and among staff, session working TJPA day-long Manager, a Competition is Review The Proposal. its of Jury the will rank presentations, the Proposals and and recommend that Proposals the TJPA the Board approve of the Proposal evaluation Upon criteria. evaluation II Stage evaluation criteria, it shall recommend to the TJPA that the Competition be terminated the fulfills Proposal no that find Jury the Should Proposals. the of ranking its for reasons ocps o te rni Cne ad oe a a ulc etn floig their following meeting public a at Tower and Center Transit the for concepts The Jury will prepare a written report to the TJPA Board stating the stating Board TJPA the to report written a prepare will Jury The Upon receipt of Proposals, the Competition Manager will confirm will Manager Competition the Proposals, of receipt Upon Each Each Respondent will be invited to present its Proposal orally to orally Proposal its present to invited be will Respondent Each

epnet il e nie t to i-ore Reviews Mid-Course two to invited be will Respondent h Rsodns il e nie t peet hi design their present to invited be will Respondents The epnet wl b rqie t atn te tg II Stage the attend to required be will Respondents uig h shdld usin n Ase period, Answer and Question scheduled the During Proposals shall conform to the Mandatory Requirements

h Cmeiin aae ad h TP saf will staff TJPA the and Manager Competition The h TP saf il owr te uy eot and report Jury the forward will staff TJPA The The Jury will evaluate the Proposals based on the on based Proposals the evaluate will Jury The (Revised) (Revised) COMPETITION FOR STAGEII UPDATED MANUAL 9

Transbay Transit Center & Tower - Design & Development Competition COMPETITION REGULATIONS 05/17/07 . COMMUNICATIONS 2. . MANDATORYREQUIREMENTS FORSTAGEIQUALIFICATIONSSUBMITTAL 3. .. Contract Award: 1.3. .. omt n Copies: and Format 3.2. 3.1. Questions and Answers: 2.4. Reporting and Disqualification: 2.3. Duration: 2.2. Protocol: Communications 2.1. design of the two structures and define the financial and legal relationship between the D/D the between relationship legal and financial the define and structures two the of design terminate to right the the for standards detailed contain reserves shall Agreements The also point. any at TJPA process selection the The Team. ranked second the with negotiations commence and team top-ranked the with negotiations terminate to right the reserve Board and Staff TJPA the then Board, TJPA the by approval for recommend can Staff TJPA the that approval by the TJPA Board of Directors. If the Team fails to agree to terms for the the Agreements that TJPA (Agreements) Staff considers to be in the best interests of the Program and is willing to recommend for Center Transit the for Agreement Design a and Tower Transit the for Agreement Option Development and Design a Team selected the with negotiate shall staff TJPA Team. a with negotiations exclusive in engage to staff authorize may discretion, sole its ulfctos on i 85 1 ic fra ad n eetoi cp i PF omt n a on format PDF in copy electronic two equals double-sided printing paper; of one side single a considered is page A disc. compact and format inch 11 x 8.5 in bound Qualifications organizational and management structure, and capability to complete the Transit Center and the Lead Designer’s design philosophy and experience, the Respondent Team’s composition, The individuals. of Respondent’s collaboration written submittal a and interview or should provide individual the Jury an with an be understanding of could Designer Lead The Tower. and for Center Transit the for Entity consultants special and engineers, architects, executive and Tower, the Development a Tower, and Center Transit the both design to Designer Lead a to, highly of development. team Respondents and must a design identify each engineering member propose and of architectural their must representing Team, including, individuals but innovative RFQ not and limited qualified the to Respondents excellence. design while Tower maintaining and Center Transit the of complexity and cost the of program development a Manager. The Competition Manager will automatically disqualify Respondents who engage in and members of the Jury shall report any communications from Respondents to the Competition pages. Tower. Definitions: and Purpose decision toterminatetheCompetitionwithoutselectingaTeam. Question andAnswerPeriodsineachStage. Team andtheTJPA. Questions andAnswerswillbecomepartoftheCompetitionProgram. unauthorized communications. usin sal ean nnmu. pn ulcto b te optto Mngr the Manager, Competition the by publication Upon the anonymous. of authorship remain The Regulations. shall Competition questions the with accordance in answered be will information by e-mail to the Competition Manager at the Competition Address during the during Address Competition the at Manager Competition the to e-mail by information this Competition request shall Respondent the these Program, the or Project, in the Regulations, Competition the provided Competition, the to regard as with information desires Participant any If except Competition. the from Respondent Competition, the disqualify automatically this will communication unauthorized Any to Regulations. pertaining matters on Manager Competition or Jury, consultants, TJPA staff, TJPA Board, TJPA the of member any to depart from this communications protocol; or (3) final announcement of the TJPA Board’s TJPA the of announcement final (3) or protocol; communications this from depart seeking to Team the with negotiations begin and Team selected initially the with negotiations abandon to decision Board’s TJPA the of announcement final final (2) the negotiations; exclusive for of date the (1) of: later the announcement to of distributed the decision is of the RFP TJPA this Board to date approve contracts the with from the Team Competition selected hs omnctos rtcl hl rmi i efc truhu Sae I f the of II Stage throughout effect in remain shall protocol communications This The TJPA Board will consider the Jury Report and the TJPA staff report and, in epnet ms sbi tn rne cpe o te Respondent the of copies printed ten submit must Respondents All questions received in accordance with the Competition Schedule n tg I te uy il eet epnet qaiid o undertake to qualified Respondents select will Jury the I, Stage In o epnet r epnets gn sal omnct with communicate shall agent Respondent’s or Respondent No Employees of the TJPA, TJPA Board members, TJPA consultants, COMPETITION FOR STAGEII UPDATED MANUAL 10

Transbay Transit Center & Tower - Design & Development Competition COMPETITION REGULATIONS 02/23/07 .. Contents: 3.3. be accepted. ... ed einrs rjc Documentation: Project Designer’s Lead 3.3.7. Profile: Biographical Designer’s Lead 3.3.6. Lead Designer’s Statement of Design Intent: 3.3.5. Profiles: Firm 3.3.4. Chart: Organization Respondent 3.3.3. Team: D/D Proposed of Description Narrative 3.3.2. Letter: Cover 3.3.1. with TJPA’s Quality Management System (the Quality Management System Manual is comply to commitment a demonstrate should narrative The selected. was members team of combination specific the why explain should narrative The Team. D/D the of members key the of responsibilities Respondent and roles specific the the and names the of and Team composition the describes that pages) six (maximum narrative the content of the submittal (maximum two pages). The Lead Designer and Developer ) 1) of theLeadDesigner,butmustinclude: excellence (maximumtwopages). CommitmentoftheLeadDesignertoProject. 4) Understandingofthevision,values,andmissionProgram. 3) the by presented challenges and opportunities design the of Understanding 2) to philosophy that apply would Designer the how and philosophy design Overall 1) (maximum threepages)addressing: (maximum sixpages) Respondent Teamstructure(maximumtwopages). provided intheAppendixtothisCompetitionManual). may signasinglecoverletterorseparateletters. information describing education, professional experience, and recognition for design public sector projects. The project documentation may be organized at the discretion the within completed be must projects the of two Designer least At project). per pages six (maximum years ten past Lead the by projects five to up of documentation number of employees, annual revenue for the past five years, and office locations. office and years, five past established, the for revenue year annual employees, subsidiaries, of number or companies parent venture management, joint senior significant interests, partners, limited and general ownership, percentage and owners organization, of form legal firm’s each describe shall Respondents Architects, The submittal shall contain only the following information. No other information will information other No information. following the only contain shall submittal The • A client reference who may be contacted, with telephone number, mailing number, telephone with contacted, be may who reference client A • Designexcellence. • Howthedesigncontributed tourbanfabric. • the enhanced and user the of importance the celebrated design the How • How the project incorporated green design, such as energy efficiency, use of • objectives quality and schedule, budgetary, operational, client’s the How • Howtheprojectissimilarinscope,program, and/orcomplexitytotheTransit • Designobjectives,approach,results,project significance,andkeyfeatures. • A narrativedescriptionofeachproject(maximumtwo pages)thatincludes: Project. the Project.

address, and e-mail address. user experience. renewable buildingmaterials,etc. were achieved. Center andTower. With respect to the Development Entity, Lead Designer, and Executive and Designer, Lead Entity, Development the to respect With The cover letter shall briefly introduce the Respondent and summarize and Respondent the introduce briefly shall letter cover The Respondents shall submit a graphic depiction of the of depiction graphic a submit shall Respondents h La Dsge sal rvd biographical provide shall Designer Lead The

The Lead Designer shall submit a statement

h La Dsge sol submit should Designer Lead The epnet sal umt written a submit shall Respondents COMPETITION FOR STAGEII UPDATED MANUAL 11

Transbay Transit Center & Tower - Design & Development Competition COMPETITION REGULATIONS 02/23/07 ... eeomn Eprec Documentation: Experience Development 3.3.9. Developer Profiles: 3.3.8. ..0 Dvlpet niys iaca Cpct Documentation: Capacity Financial Entity’s Development 3.3.10. ) Evidence from established financial source(s) of the Respondent’s ability to 3) finance 4) A description of the expected types and amounts of financing needed for the for needed financing of amounts and types expected the of description A 4) Balance sheets, income statements and changes in net asset statements (and any 2) years fiscal or calendar recent most four the for statements financial Audited 1) ) A list of awards, publications, 3) notices, peer recognition, or any other documentation inch 10 x 8 two of minimum a including project, each of examples Illustrative 2) partner isinvolved.Thestatementshouldincludeallofthefollowing: name, project including years, ten last the within completed projects of list A community 5) creating and outreach public with experience of description A 4) Identification of specific experience, if any, with public-private joint development 3) Anindicationwhethertheprojectswerecompletedontimeandbudget. 2) Adescriptionofexperiencewithmixed-useandhigh-risedevelopments. 1) pages), including: pages) similar to the Transit Center and Tower completed in the last 10 years. (maximum ten (maximum years. projects 10 last the in completed Tower and Center Transit the to and similar projects complex large, of development the with experience current of the key individuals to be involved in the development of the project. (maximum six more of the joint venture partners, the statement should indicate which joint venture joint which indicate should statement the partners, venture joint the of more or one to pertains that statement the in presented is information and venture joint a is Respondent the Where Project. the for the costs development fund and predevelopment to capacity financial Respondent’s demonstrate to information sufficient eal h dvlprs xeine n pa fr euig iacn fo grants, from financing charitable contributions, or other securing comparable funding sources, if for such funds would plan and experience developer’s the detail in describe should Respondent sources. funding uncertain other or contributions, grants, or loans contingent on reliance minimize should Respondents so, doing In should demonstrate beyond a reasonable doubt their ability to Respondents Project. finance the the for financing project. debt and equity necessary attract and/or Project. Respondents should identify recent projects (including private-public joint be proposedfortheProject. other guarantees toenablefundingoftheProject. or equity the contribute and Project the behind stand will credit and faith good the respondent may include this information for those partners or members whose Principles. If Respondent is a joint venture or new financial entity without the condition of the financial respondent in presenting accordance with Generally statements, Accepted Accounting accurately as statements financial the certify must firm accounting reputable A respondent. the of position financial current overall the and debt, recourse Respondent’s the flows, cash negative with projects current flows, cash positive with projects current loans, non-performing any showing and status, financial current and worth net project) the for created be will that entities purpose special any not entity, enduring major the (i.e. Respondent’s the showing lutain/mgs f ah rjc ad diinl igas iae, r other or explanatory information. images, diagrams, additional and project each of illustrations/images opein rl o fr, ecnae f wesi a cmlto, current completion, at ownership of percentage upon firm, ownership percentage,andreasonforanytransfer. rate of absorption role date, completion, completion date, commencement description, consensus. projects Include property. owned involving long-termgroundleasesandsaleoftheproperty. publicly involve that projects i.e., projects, of designexcellence(maximumonepage). appropriate Respondents should provide resumes and at least three references statements) intableformatforthelastfouryears. epnet sal xli peiu and previous explain shall Respondents epnet sal submit shall Respondents COMPETITION FOR STAGEII UPDATED MANUAL 12

Transbay Transit Center & Tower - Design & Development Competition COMPETITION REGULATIONS 02/23/07 ..2 Standard Form 330: 3.3.12. References: Financial Entity’s Development 3.3.11. 2 A current Dunn 12) and Bradstreet Comprehensive Report or comparable rating report An explanation, 11) including dates and circumstances and outcome, of any insurance An explanation, including dates 10) and circumstances, of any bankruptcy filing of the legal potential or judgments, litigation, threatened or pending of description A 9) size, type, project describing: portfolio estate real current Respondent’s of list A 8) or completed yet not but underway currently projects Respondent’s all of list A 7) equity predevelopment of amount and nature, source, the of identification An 6) An identification of specific relationships (and contact information) with sources of 5) information regarding the Respondent team’s organization, qualifications, and past and qualifications, organization, team’s Respondent the regarding information provides which Administration, Services General U.S. the by published Qualifications” ) epnet sol icue n h S30 l ncsay icpie and disciplines necessary all SF330 the in include should Respondents 1) projects. the natureandlengthofbusinessrelationshipwith thebanksandinsurers. by submitting signed letters on Respondent’s letterhead to TJPA with copies to the references authorizing the TJPA to check these references. Respondents shall identify to copies with TJPA to letterhead Respondent’s on letters signed submitting by references from a bank and three financial references from a bond insurance agency against the Respondent by any funding source or financial institution during the during institution financial or source funding any by Respondent the against taken actions adverse any of discussion a include Also committed. amounts and source, financing project, of type detailing commitments, financing obtaining in a Include years) funders. 2-3 last the within (preferably history recent equity Respondent’s the of statement and debt from references appropriate provide and development projects, if any) where Respondent made a similar level of investment for Respondent. claims filedbytheRespondentoranyjointventurepartner. or private saleofadeedtrustforpropertyownedbyRespondentoranypartner. on foreclosure the or Respondent in partner venture joint any or Respondent timely a in manner. Property Tower the lease ground or purchase to option the exercise or entitlements use land contemplated the obtain to ability Respondent’s affect could that or business development or construction the to team relates that or members partners venture joint individual its or Respondent the involving actions Respondent’s the and ownership interest. amounts; rate, and sources, occupancy methods, financing project’s etc.), the manager, property (developer, absorption rate, and financial role commitment required on the part value, of the Respondent; location, the in Project. role integral an play will individuals these whether and projects, these on working personnel lead the of names methods, and amounts financing schedule, occupied, including a brief description of the status of each project, development equity willbemadeavailableforeachphaseoftheProject. predevelopment how Describe Project. the of development the funds affect may these that of availability the on limitations any and costs, predevelopment for available to the Respondent to fund the Project. Identify the process to secure equity Project isconsistentwiththeirinvestmentcriteriaforaprojectofthissize. the that sources these from acknowledgements with funds, grant governmental or funds charitable private of sources applicable) (if or capital, debt and equity past fiveyearsandexplainwhatstepsweretakentocorrecttheproblem. rnprain pdsra cruain tne vniain fr sprsin cost suppression, fire threat), and vulnerability for (design systems surveillance and security estimation, ventilation, tunnel circulation, electrical, pedestrian mechanical, transportation, vertical signage/graphics, ramps), acoustics/vibration, Bridge sustainability, public lighting, Bay safety, design, e.g. life resistant design, bridge blast and seismic, highway (including structural rail, civil, design), geotechnical, facilities rail and transportation (including architectural following: the to limited not but including Tower, and Center Transit the for subconsultants Respondents shall submit a Standard Form 330 “Architect Engineer Respondents shall provide three financial three provide shall Respondents

COMPETITION FOR STAGEII UPDATED MANUAL 13

Transbay Transit Center & Tower - Design & Development Competition COMPETITION REGULATIONS 07/05/07 . MANDATORYREQUIREMENTSFORSTAGEIID/DPROPOSALSUBMITTAL 4. .. omt n Copies: and Format 4.2. Definitions: and Purpose 4.1. Presentation: PowerPoint I Stage 3.4 .. Contents: 4.3. ... Transit Center Proposal: 4.3.2. ... ein ocp Boards: Concept Design 4.3.1. ..3 San Francisco Human Rights Commission (HRC) Forms: 3.3.13. requirements distributed at the Stage II composition presentation and Briefing mediums, scales, drawing and uniform to adhere as and TJPA the detailed by in the Presentation Requirements of theTransitCenteranddevelopmentTower. electronic copyofaPowerPointpresentationoncompactdiscpreparedfortheInterview. Memo dated6/21/07. shall submitanarchitecturalmodelatthetimeofStageIIpresentation. presentation board and a compact each disc of with copy PDF printed format one copies submit of also the shall submittal. Respondents Respondents document. bound separate each of copies 14 submit shall respondents and tabs, and contents of table a have to required is document bound each documents, bound multiple in are proposals If format. inch 11 x 8.5 shall also propose the legal and financial terms of an agreement with the TJPA for the design submittal II Stage The Project. the for desires TJPA the image iconic class, world the befitting design compelling a present should Proposal The Report. Definition Scope the in forth set as Proposal demonstrating an understanding of the requirements of the Transit Center and Tower artvs n darm ta epan h dsg a dpce o te “Required the on depicted as design the explain that diagrams and perspectives, narratives elevations, sections, plans, including Tower, and Center Transit the of vertically oriented boards (maximum of 1/2” thickness) illustrating the design concept ) epnet sol edao t peet h ifrain n h S30 n a in SF330 the in information the present to endeavor should Respondents 3) Respondents should also include in the SF330 other consultants that will work with 2) explosive anddangerousmaterialsdetectors,voice/datasystems. ) CertificationRegardingLobbying. 4) Certification Regarding Debarment, Suspension, and Other Responsibility Matters.3) Bidders/Proposers – Requirements Program Enterprise Business Disadvantaged 2) A copy of the firm’s Nondiscrimination Program or Equal Opportunity Employment 1) Information andtheformsarelocatedinappendixtothisCompetitionManual. ) A narrative description of the design concept and an explanation as to how the 2) Atableofcontentsandtabs identifyingthepartsofProposal. 1) safety. TheProposalshallinclude: Drawings andDrawingScales”distributedon6/21/07. eurmns ue fo ad cesblt, re dsg, n simc n structural and seismic and design, green operational accessibility, and transit flow context, user community requirements, image, architectural Center; Transit the to uses its and Tower the of relationship the to given care throughout particular with complex, flow the resident and will user requirements; that operational uses transit Proposal address level Center should Transit street The the neighborhood. pedestrian-oriented on vibrant, a emphasis promote particular place should Proposal The the role of the Transit Center and Tower as a part of the urban form of San Francisco. niy ad xctv Aciet ms sbi te olwn saeet ad forms. and statements following the submit must Architects Executive and Entity, To ensureafaircomparisonoftheProposals,eachProposalwilluseformsprovided concise and understandable manner. Limit resumes and project examples to key environmental consultants,andretailspecialists. attorneys, consultants, financial including Project, the on Entity Development the Information RequestForm. Policy Statement(ifany). individuals andrelevantprojects. Definition Report. concept meets the requirements and design criteria contained in the TJPA Scope epnet sal umt 4 rne cpe o te rpsl on in bound Proposal the of copies printed 14 submit shall Respondents (Revised) Each Respondent selected to participate in Stage II shall submit a submit shall II Stage in participate to selected Respondent Each The Transit Center Proposal should reflect an understanding of At the time of the interview, Respondents should submit one submit should Respondents interview, the of time the At epnet sal rpr a aiu o tn 6 x 48”, x 36” ten of maximum a prepare shall Respondents The Lead Designer, Development (Revised) (Revised) COMPETITION FOR STAGEII UPDATED MANUAL 14

Transbay Transit Center & Tower - Design & Development Competition COMPETITION REGULATIONS 05/21/07 4.3.3. Tower Proposal: Tower 4.3.3. ob ad lz fr h Twr hl poie sals cneto t te Transit the to connection Proposal Tower The character. seamless neighborhood evolving the to a contribute and Center provide shall Tower the for plaza and lobby public The Program. the for advantageous financially as well as design in green and 6) Design renderings and a printed color copy of each presentation board scaled board presentation each of copy color printed a and renderings Design 6) 4) A cost analysis comparing the proposed design concept to the TJPA preliminary TJPA the to concept design proposed the comparing analysis cost A 4) functional and planning uses, program all that confirmation and listing tabular A 3) ) n xlnto o te oe’ fnnil otiuin o h Porm that Program the to contribution financial Tower’s the of explanation An 5) Afinancialmodel(proformatemplatetobeprovidedattheStageIIBriefing). 4) and quantities, uses, including program development proposed of description A 3) the to relationship its including concept design the of description narrative A 2) AtableofcontentsandtabsidentifyingthepartsProposal. 1) shall alsoinclude: identify shall proposers FEE”, “PROPOSED marked envelope sealed separate, a In including Center, Transit the for Agreement Design the for terms key Proposed 5) ) A ln o iac te eeomn o te rni Twr otiig detailed containing Tower Transit the of development the finance to plan A 6) .8 f oue w o te cp Dfnto Rpr. h cs aayi o direct of analysis cost The construction cost of the Transit Report. Center design must fall within the TJPA preliminary Definition Scope the of Two Section Volume in of established 4.18 as dollars current in cost construction direct of estimate requirements areprovided. construction of the program primarily during he initial years of the public/private the of years initial he during primarily program the of construction to the Program should be responsive to the Program’s requirements for capital for Page 2 of the Model Term Sheet as amended. The proposed financial Tower contribution Property under the “preferred” and “base program” scenarios a identified on propose the shall of purchase and lease Respondents ground a on based Property Tower the of 2007. disposition 14, May dated letter the by amended as conforms to the Model Term Sheet and Pro Forma Templates dated April 12, 2007, synergy ofuses. Scope the in contained Definition Report. criteria design and requirements the the meets how to concept as explanation an and features, building green and Center Transit to 8.5”x11”size. the proposal. of section other any in the included be not for shall information fee Team Proposed Center. the to pay Transit the for would services phase administration construction and TJPA design completed the compensation monetary total the would beinvolved,andadescriptionoftheirindividualresponsibilities. develop the design for the Transit Center, the identity of the Team members that to consultants its and TJPA the design, with work final would Team the the how of of description a completion for milestones detailed containing schedule a estimate. financial strength ofthedevelopmententity. 10-K and the 10-Q; and (5) any other information that would further illuminate the an explanation of any material changes in financial position since the filing of the the if (4) position; development entity financial is a public entity’s company, the its most development recent 10-K and and the 10-Q filings division and affect could or that subsidiary parent the a against (3) pending parent; lawsuits the any of of obligations also description are subsidiary the of obligations the that documentation supporting with commitment a division, or subsidiary a is entity development the if (2) issued; were sheets balance and statements income the company, and an explanation of any material changes in financial position since company’s, the most recent income statement and balance sheet for the parent if the income statements and balance sheets are not consolidated with a parent and, entity development the for sheets balance and statements income recent of the Tower. To support the financing plan, the Team should submit: (1) the most evidence that the Team has sufficient capital resources to finance the development partnership. The TJPA envisions a landmark Transit Tower that will be innovative be will that Tower Transit landmark a envisions TJPA The (Revised)

COMPETITION FOR STAGEII UPDATED MANUAL 15

Transbay Transit Center & Tower - Design & Development Competition COMPETITION REGULATIONS 02/23/07 . JURY 7. DISQUALIFICATION 6. ELIGIBILITYTOCOMPETE 5. are: selected by the Competition Manager and approved by the TJPA Board. The members of the Jury selection meetings. The and tasks of evaluation the all Jury at are defined present by be the will Competition Regulations. members All Jury Jurors were All professionals. development and design of The Jurywillconsistofsevenvotingandtwoex-officio non-votingmembersandwillbecomprised will bedisqualified. Any Respondent committing an act (or acts) that conflict with or violate the Competition Regulations or respondtoeitherstageofthisCompetition. team, TJPA Board, Jury, or Jury members’ firms, are eligible to participate on any Respondent team shall comply with the State of California licensing requirements. No member of the TJPA staff, PMPC Record” of Engineers and “Architect The teams. or individuals all to open be will Competition This 4.3.5. San Francisco Human Rights Commission (HRC) Forms: 4.3.4. • • • •

Oscar HarrisFAIA, TurnerAssociatesArchitects andPlanners,Inc. of CaliforniaatDavis Susan L.Handy,Professor,Department ofEnvironmentalScienceandPolicy,University Hsin-Ming FungAIA,Hodgetts +FungDesignandArchitecture Robert CampbellFAIA,Architecture CriticoftheBostonGlobe niy ad xctv Aciet ms sbi te olwn saeet ad forms. and Manual. statements Competition this to appendix following the in located the are forms the and submit Information must Architects Executive and Entity, lcrnc Files Electronic 8) Proposed key terms for the Design and Development Option Agreement for the for Agreement Option Development and Design the for terms key Proposed 8) 7 board inPDFformatatreso including the Proposal and an electronic copy of each design concept presentation 5) Responsibility CertificationRegardingLobbying. Other 4) and Suspension, Debarment, Regarding Certification 3) Bidders/Proposers – Requirements Program Enterprise Business Disadvantaged 2) A copy of the firm’s Nondiscrimination Program or Equal Opportunity Employment 1) (Inserted) 9 A akoldeet ht a te oe Poet i wti te Transbay the within is Property Tower the (a) that acknowledgement An ) ) Design renderings and a printed color copy of each presentation board scaled board presentation each of copy color printed a and renderings Design ) of the final design and construction, the identity of the Team members that would Transit Tower, including a schedule containing detailed milestones for completion developer oftheTransitTowercontributespecialtaxestoProgram. the that require may approved, if that, District Facilities Community Mello-Roos a be will Property assigned to the Program; and the (b) the City is investigating the from feasibility of forming increment tax net all and Area Plan Redevelopment Disclosures requiredbythe Matters. Information RequestForm. Policy Statement(ifany). to 8.5”x11”size. be involved,andadescriptionoftheirindividualresponsibilities. : epnet sal umt C o DD otiig h submi the containing DVD or CD a submit shall Respondents lutions appropriateforwebpostingandprinting. Levine Act.

The Lead Designer, Development (Inserted) ttal , COMPETITION FOR STAGEII UPDATED MANUAL 16

Transbay Transit Center & Tower - Design & Development Competition COMPETITION REGULATIONS 02/23/07 11. DISADVANTAGED BUSINESSENTERPRISE (DBE)PARTICIPATION 10. EXHIBITION OFCOMPETITION SUBMITTALS HONORARIUM&OWNERSHIP OFCOMPETITIONSUBMITTALS 9. COMPETITIONMANAGER 8. On May 1, 2006, Caltrans announced major changes to the statewide DBE Program. The policies The Program. DBE statewide the to changes major announced Caltrans 2006, 1, May On TJPA The 2006-07. (FY) year fiscal the TJPA’swebsiteathttp://www.transbaycenter.org/TransBay/content.aspx?id=311. for Program of DBE page Documents the on the available is which Program, DBE adopted the review Teams that recommends TJPA the 2006, 20, July On the in result may which contract, this of breach material termination ofthiscontract orsuchotherremedy,astheTJPAdeemsappropriate. a is requirements these out carry to 49 CFR Part 26 in the award and administration of DOT-assisted contracts. Failure by the contractor of requirements applicable out carry shall contractor The contract. this of performance the in sex The contractor or subcontractor shall not discriminate on the basis of race, color, national origin, or assisted contractandsubcontract: Pursuant to 49 CFR Section 26.13, the TJPA is required to make the following assurance in every DOT- activities. Policy: 11.1. credit totheauthor(s)ofanymaterialused. reserves t further right TJPA the The submittals. II Stage and I Stage all exhibit to right the reserves TJPA The Ownership andintellectualpropertyrights,however,shallremainwiththeLeadDesigner. Competition. the during TJPA the to submitted has Designer Lead the materials all advertise and Should any Lead Designer decline the honorarium, the TJPA shall have the right to publish, display, all of materials andmaypublish,advertiseorusetheforpromotionalmarketingpurposes. copies retain may Designer Lead The ideas. and concepts, design materials, any use may the during TJPA the honorarium to Competition, including submitted the intellectual materials property, shall of all become the that exclusive acceptance property agreement of the binding Designer’s TJPA, legally which Lead a constitute The shall excellence. design of recognition in importance $100,000, of the Board amount the TJPA of in the honorarium by an offered approved be and will II Jury Stage the to advance by to selected Teams D/D the of Designers Lead The meetings asrequiredfortheorderlyexecutionofCompetition. facilitate shall Manager Competition The process. selection transparent and equitable an ensure to Competition the of activities all Project coordinate shall Manager Competition Competition The the Competition. the is AICP Mannhard Jennifer Manager; Manager. The Competition Manager shall be Respondents’ sole contact with the TJPA throughout Competition the is FAICP FAIA Stastny J. Donald Competition. the manage to Inc. Architects, StastnyBrun retained has TJPA The contracts and subcontracts relating to TJPA’s construction, procurement and professional services professional and procurement construction, TJPA’s to relating subcontracts and contracts for fairly compete can DBEs which on (DOT)-assisted field playing level Transportation a create of to is intention Department TJPA’s contracts. of administration and award the in origin national purposes, publication, documents, videos, or fund-raising at its discretion. TJPA shall give appropriate • • • • • o publish, advertise, publish, Dean Ma Maria AyerdiJ.D.,TJPA Allison G.WilliamsFAIA,Perkins+Will A. JerryKeyser,KeyserMarstonAssociates Arthur JohnsonPESE,KPFFConsultingEngineers h TP’ plc i t esr nniciiain n h bss f ae clr sx or sex color, race, of basis the on nondiscrimination ensure to is policy TJPA’s The cri s FAICP,San use or display any and all material for educational or promotional or educational for material all and any display or use ( e Francisco DepartmentofPlanning(ex-officio) x-o fficio) (Updated) (Updated) COMPETITION FOR STAGEII UPDATED MANUAL 17

Transbay Transit Center & Tower - Design & Development Competition COMPETITION REGULATIONS 05/17/07 12. CONTRACT AWARD women fortheirrespectiveworkforces. 11.2. Equal Employment Opportunity: request. upon electronically obtained be also can and Manual this to Appendix the in included are forms non-DBE and subcontrators and DBE the Final of Expenditure Report payment with the completion of of the proof contract. These as Declaration Payment Subcontractor the (2) and invoice; every Bidders/Proposers of award TJPA’s Upon the participation. submit DBE contracts, the winning Team and will of be required to submit (1) the TJPA’s Progress Payment Report with regardless complete Proposals, their to with required Form Request be Information will Teams 26.37), CFR (49 Pursuant to the monitoring requirements outlined in Section XIII of the TJPA’s FY 2006-07 DBE Program the to addition in policies these review TJPA’s FY2006-07DBEProgram.TheseexhibitsareincludedintheAppendixtothisManual. should Teams changes. those of part are Participation, Enterprise Business Enterprise Subcontractor/Disadvantaged for Business Agreement Standard Disadvantaged 10-J, and Bidders/Proposers Information, to Notice 10-I, Exhibits Caltrans in outlined 1) A conceptual design for the Tower and the Transit Center, including height, bulk, and shape, and bulk, height, including Center, Transit the and Tower the for design conceptual A 1) contracts The shall include: Center. Transit the for Development Agreement Design and a Design and Tower, a the contracts: for Agreement two Option ultimately, and, sheet term a on to faith agreement good reach in negotiate will parties the Period, Negotiating the During Period”). (“Negotiating TJPA the with Agreements the negotiate to period negotiating exclusive an into enter be to will invited Team D/D selected the II, Stage in Respondent a of selection Board’s TJPA the Following contract. 11.3. DBE Availability Advisory Percentage: 2) A schedule for planning and funding, at the D/D Team’s sole cost, all aspects of design and design of aspects all cost, sole Team’s D/D the at funding, and planning for schedule A 2) 9) As to any ground lease: A) a provision that TJPA’S fee ownership and minimum base rent base minimum and ownership fee TJPA’S that provision a A) lease: ground any to As 9) D/D the by exercised be to Property Tower the of lease ground or purchase for option An 8) financial the and Property Tower the of disposition the involving partnership public/private A 6) in placed is Tower the once covenants operating and construction quality first for Provisions 5) Completionguaranteeandperformanceorpaymentbonds. 4) Timeandperformancebenchmarkswithterminationprovisionsfornon-performance. 3) percentage for this contract. However, Teams are encouraged to obtain DBE participation for this for participation DBE obtain to encouraged are Teams However, contract. this for percentage 7) Financial benefits to the TJPA that include both up front consideration for the Tower Property Tower the for consideration front up both include that TJPA the to benefits Financial 7) general plan amendments, rezoning, subdivision, required testing, environmental review, and review, environmental testing, required subdivision, rezoning, amendments, plan general plans, financing services, consulting other and legal A/E, including Tower, the of construction to constitutethebasisforformalapplicationsentitlements. market conditions; C) base rent; D) periodic adjustments and re-appraisals of base rent; E) rent; base participation or percentagerentbased ongrossincomeand/orparticipation innetprofits of re-appraisals and adjustments periodic D) rent; base C) conditions; market upon based and use proposed the to appropriate term lease a B) subordinated; be not will Team uponobtainingentitlements todeveloptheTower. and specificallocationsofrentsorsalesproceeds. dated April12,2007,asamendedbytheletter May14,2007. Templates Forma Pro and Sheet Term Model the in contained terms the include will Property Tower the for Agreement Option lease ground or purchase a of terms the that expects TJPA The participation. Program and payment(s) up-front with Property Tower the of lease ground (2) return; of rate specified some earned has capital invested after revenues for surplus sharing mechanism a or rent percentage as such Program, the to revenue surplus of allocation arrangements: (1) cash purchase of the Tower Property plus participation that includes specific contribution of the Tower development to the Program based on one of the following financial service. all otheraspectsofsecuringentitlementsfortheTower. The TJPA encourages Teams to actively recruit minorities and The TJPA has not established a DBE availability advisory (Revised)

COMPETITION FOR STAGEII UPDATED MANUAL 18

Transbay Transit Center & Tower - Design & Development Competition COMPETITION REGULATIONS 02/23/07 16. SUMMARY REPORT 15. COMPETITION SCHEDULE 14. COMPETITION ADDRESS 13. CITY CODEPROVISIONSAPPLICABLE TOAGREEMENTSWITHTJPA eetd / Ta, h Cmeiin aae wl ise rpr smaiig h Competition the summarizing report a process andresults. issue will Manager Competition the Team, D/D selected the with Period Negotiating the of start the and Team D/D selected the of announcement Upon posted ontheCompetitionWebsite. and addenda as issued be will they required, are clarifications or changes other or schedule the to modifications If Schedule. Competition the events modify to right the reserves TJPA The deadlines. of and sequence the lists It Regulations. Competition the of part is Schedule Competition The The addressfordeliveryofsubmittalsis: 5533 at Manager, Project Mannhard, Jennifer via Stastny J. All communications in the course of the Competition shall be to the Competition Manager, Donald olse_index.asp. Additional http://www.sfgov.org/site/ at web the on available chapter. is HCAO and this MCO the regarding under information obligations compliance their determine to Code Administrative Francisco San the consult should Contractors thereof. lieu in to amounts pay coverage or employees care certain health provide to contractors requires 12Q, Chapter Code Administrative S.F. in forth set as HCAO, The 2006. 1, January of for as $10.77 is compensation entities for-profit for hourly employees covered gross the that Note requirements. minimum certain meet that off time who do work funded under the Agreements with hourly gross compensation, and paid and unpaid ordinance the by covered employees provide to TJPA the with contractors Code requires 12P, Chapter Administrative Francisco San in forth set as MCO, The (HCAO). Ordinance Accountability to the requirements of the City Minimum Compensation Ordinance (MCO) and the City With Health Care respect to the Design Agreement for the Transit Center, Teams are urged to pay special attention Project atanytime. the terminate or suspend to right the reserves TJPA The documentation. construction and design detailed of preparation Team’s D/D the to prior design or program the in modification request to right the reserves TJPA the available, become funds as phased be may construction and design Because the Competition results will be used to solicit and allocate capital improvement funds, and financial andlegalrelationshipbetweentheD/DTeamTJPA. the define and structures two the of design the for standards detailed contain shall Agreements ranked Team. The TJPA also reserves the right to second terminate the selection process at any point. the The with negotiations commence and team top-ranked the to with right negotiations the terminate reserve Board and Staff TJPA the then Board, TJPA the TJPA by approval the for recommend by approval for recommend can Staff to TJPA the that Agreements the willing for terms to agree to is fails Team to the If and Directors. of Board considers Program Staff the TJPA of interests the Tower best that Transit the (Agreements) the in Center be for Transit the Agreement for Option Agreement Development Design and a and Design a Team selected negotiate shall the staff TJPA with Team. a with negotiations exclusive in discretion, engage sole to its staff in authorize and, may report staff TJPA the and Report Jury the consider will Board TJPA The Nopaymentofbroker’scommissions. 10) . G) TJPA’srighttoapproveanyassignmentofthelease. from refinancing and sale; F) the lessee will pay a possessory interest tax in lieu of property tax; (Updated) T San Francisco,CA94105 201 MissionSt.,Suite1960 Attn: DesignandDevelopmentCompetitionManager ransbay JointPowersAuthority TRANSBAY (Updated) @stastnybrun .com or (Inserted) (503) 222- (503) COMPETITION FOR STAGEII UPDATED MANUAL 19

Transbay Transit Center & Tower - Design & Development Competition 05/17/07 Announcement ofStageIIresults TJPA BoardApprovesselectionofRespondents Interviews andEvaluation Respondent QualificationSubmittalsDue Question &AnswerPeriodEnds Registration Ends Pre-Submittal Meeting Pre-Submittal Meeting Question &AnswerPeriodBegins RFQ Announcement&RegistrationOpens STAGE I:REQUESTFORQUALIFICATIONS(“RFQ”) (Revised 2perAddendum#2-5/17/07) (Revised 1perAddendum#1-3/13/07) COMPETITION SCHEDULE Announcement ofSelectedD/DTeamforExclusiveNegotiations TJPA BoardReviewsJury’sRecommendationand AGREEMENT AWARD Summary ReportofProcessandJury’s Public MeetingtoPresenttheDesignConcepts Presentations totheJuryandEvaluation Proposals Due Question &AnswerPeriodEnds 2nd Mid-courseReview 1st Mid-courseReview Question &AnswerPeriodBegins Stage IIBriefing Issue RFPandUpdatedCompetitionManual STAGE II:REQUESTFORPROPOSALS(“RFP”) SelectsaD/DTeam Recommendation TransmittedtotheTJPA (Revised 1) (Revised 1)

(Revised 2)

(Revised 1)

(Revised 1)

(Revised 2) (Revised 2)

(Revised 2) 9/20/07 8/06/07 8/30/07 week of7/30/07 6/26/07 9/20/07 week of5/21/07 7/10/07 2/15/07 2/15/07 1/29/07 –1/31/07 1/11/07 12/21/06 12/21/06 12/7/06 11/15/06 11/01/06 11/01/06 week of4/16/07 3/01/07 3/01/07 2/23/07 COMPETITION FOR STAGEII UPDATED MANUAL 20

Transbay Transit Center & Tower - Design & Development Competition COMPETITION SCHEDULE 02/23/07 hud ecie ah opnn o te epnet em daig la dsicin between distinctions clear drawing Team, Respondent the responsibilities forspecificphasesoftheProject. of component each describe should plan for coordinating the work of local consultants with consultants working in remote offices. Proposals the describe and work, production and design major of should conduct the of They location physical the identify resources. Respondent’s manage and plan to method the and plans control cost and and the process for incorporating client and community input. Respondents should explain their quality vision for the Project. Proposals should describe Respondent’s the implementing roles for of responsible key members Team Team members, principal lines the of identify communication, should Respondents on successfully together worked have previous projects. and Project, the to complexity and size in similar projects on regarding designing in San Francisco. The principal Respondent team members should have experience engineering challenges of the exhibited and projects architectural and the how met Respondent lessons the learned how would demonstrate inform should the Respondents form, Respondent 330 SF the In Francisco, theprojectsite,andusesincludedinjointTransitCenterTowerproject. San to specific requirements and issues of knowledge describe also should It schedules. performance agencies and private industry with respect to cost control, quality control of work, and compliance with efficient manner. The Proposal should describe past performance on contracts with both government and expeditious an in work the accomplish to capacity demonstrate should Respondents team. the Team members that would design and develop the Tower, and the organization and management of TJPA’s Quality Management System, the composition of the team, the professional qualifications of the the with comply to commitment team’s the Center, Transit the design would that members team the standards for design and development. The narrative should describe the professional TJPA’s qualifications of the exceed or meet to necessary qualifications professional the possess should Team D/D The OVERALL RESPONDENTTEAMCOMPOSITIONANDORGANIZATION(20%) addressing Examples magnitude. adjacencies andlinkstotransportationshouldbeincluded. this of project a undertake to capacity financial the demonstrate shall Entity Development The partnerships. public/private forming in Entity Development the of success urban, mixed-use projects that excel in high-rise, design excellence deliver and green to design. Of capacity particular interest financial is the the have and experienced be should Entity Development The DEVELOPMENT ENTITY(30%) of range a indicate should educational andworkexperiencetheabilitytodelivercomplex,largeprojects. profile/resume The excellence. design designer’s to the commitment and of leadership level design personal demonstrate clearly should exhibits The Project. the by raised issues design and requirements project of understanding an demonstrate that exhibits of comprised be should documentation project The challenges, ideas. communicate to and designer the opportunities, of ability requirements, the reflect Project’s and the of understanding her or his demonstrate design, toward attitude designer’s the express should intent design of statement The profile. individual and performance, experience, relevant philosophy, design work, of portfolio by evidenced as design The Lead Designer should have the capability and commitment to achieve design excellence and green LEAD DESIGNER(50%) EVALUATION OFSTAGEI–RESPONDENTQUALIFICATIONS COMPETITION FOR STAGEII UPDATED MANUAL 21

Transbay Transit Center & Tower - Design & Development Competition EVALUATION OF STAGE I 02/23/07 Note: Maximum pointtotalis100andscores areusedonlytodetermine rank POINTS JUROR: RESPONDENT TEAM: STAGE I–RESPONDENTQUALIFICATIONS- 50 20 30 10 10 10 10 10 15 15 10 5 5

ulfe i ter ils ad h Ta mmes ae xeine working experience have members Team the and fields, highly their are members in Team the qualified Team, D/D the on represented are Tower the develop and design and Center Transit the design to necessary disciplines All Demonstrates an understanding of how the political and cultural climate in San Center Transit the to for scale financing innovative Demonstrates and profitable. were and complexity Project Tower and in similar are examples Project involvement personal and excellence design to commitment Demonstrates to approaches innovative and exploration of level high a demonstrate Designs complex solve to solutions design creative unique employs recognizes Project, design, the toward of aspects attitude imaginative and flexible Exhibits h DD ems raiain ln lal ietfe ky oe ad ie of lines and roles key identifies clearly plan input, community and client receive to mechanism a provides communication, organization Team’s D/D The and providesforcost quality control. together successfully. OVERALL RESPONDENTCOMPOSITIONAND ORGANIZATION Francisco willaffecttheProject,includingacommitment togreendesign. complex projects.Demonstrateslongevityofownership. Financial capacityfortheTransitCenterandTowerProject. THE DEVELOPMENTENTITY history showaconsistentcommitmenttodesignexcellence. Project. throughout thelifeofproject. solving programrequirementsoflarge,complex,urbanprojects. design challenges. THE LEADDESIGNER CATEGORY Professional credentials are appropriate and educational background and work Tower and Center Transit the to complexity in similar are examples Project JURY EVALUATIONSHEET DATE: LEAD DESIGNER: Total Score

SCORE COMPETITION FOR STAGEII UPDATED MANUAL 22

Transbay Transit Center & Tower - Design & Development Competition EVALUATION OF STAGE I 02/23/07 public functions of the Transit Center should be a fundamental consideration in integrating the two the integrating structures. in consideration fundamental a be should Center Transit the of functions public issues the and Tower the of functions public the between relationships flow and Symbolic functions. ancillary the technical to and adherence movement, functional and support people all and conflict, and flows accessibility, pedestrian and the vehicular requirements, massing user and program including of Tower understanding and Center thorough Transit the a of illustrate should Proposals The FUNCTIONALITY AND TECHNICALISSUES(20%) individual responsibilities. and construction, the identity of the Team design members that would be involved, and final a description of their the of completion for milestones detailed containing schedule a the including for Tower, Transit Agreement Option Development and Design the for terms key propose should Respondents the finance to plan resources tofinancethedevelopmentofTower. Respondent’s The built. and financed development be of the Transit Tower should can include detailed evidence that that the Team has sufficient program capital development a Respondents should submit the appropriate financial and pro forma documentation that demonstrates financial feasibilityoftheTowerproposal. private partnership. The Jury will focus Program’s on the timing the and public/ amount the of of revenue to years to initial the the TJPA responsive during and primarily the Program overall the be of construction for should capital for requirement Program the to contribution financial proposed Team’s The in theScopeDefinitionReport. Center, Transit the to Tower the of enhance relationship public access to the the Transit Center demonstrate should concept design Tower The Tower shouldbethefocusofanevolvingneighborhoodandcreateiconicarchitecturalimage. design and uses that will promote a vibrant, pedestrian-oriented neighborhood. The Transit Center and level street the on emphasis particular place should It constructability. and innovation, structural and San Francisco. The Transit Tower design concept should demonstrate the integration of to green complimentary design, and seismic Transit Center compatible design. It should reflect is an understanding of the that role the Tower concept plays in the urban design form of a present should Proposal Tower The THE TOWERPROPOSAL(40%) responsibilities. Transit the for design the Center, the identity of the Team develop members that would be involved, and a to description of their individual consultants its and TJPA the with description work a would Team design, the final how of the of completion for milestones detailed containing schedule a Center, total monetary compensation the TJPA would pay to the Team for the completed design for the Transit the including Center, Transit the for Agreement Design the for terms key propose should Respondents TJPA the to responsive be also should concept preliminary estimateofdirectconstructioncost. design Center Transit The requirements. other and technical, operational, TJPA’s the satisfy to ability the demonstrate and Report, Definition Scope TJPA the in contained criteria design and requirements the meet should concept design Center Transit The and Center; Transit the to and accessibility,greendesign,seismicstructuralsafety. uses its complex, and Tower the the throughout of architectural image, relationship flow the resident to given and care user particular with requirements; operational transit address should Proposal Center Transit The neighborhood. pedestrian-oriented vibrant, a promote will that uses level as part of the urban form of San Francisco. The Proposal should place particular emphasis on the street The Transit Center Proposal should reflect an understanding of the role of the Transit Center and Tower THE TRANSITCENTERPROPOSAL(40%) PROPOSALS EVALUATION OFSTAGEII–DESIGNANDDEVELOPMENT design excellence (Updated) , community context, transit operational requirements, user flow , and meet the requirements and design criteria contained (Updated) COMPETITION FOR STAGEII UPDATED MANUAL 23

Transbay Transit Center & Tower - Design & Development Competition EVALUATION OF STAGE II 02/23/07 Note: Maximum pointtotalis100andscores areusedonlytodetermine rank The Team’s proposed financial contribution to the Program should be responsive to the Program’s requirement for capital for capital for requirement Program’s construction of the the Program primarily to during the responsive initial years be of the should public/private partnership. The Program Jury will the focus on to the timing contribution and financial proposed Team’s The Tower andthepublicfunctionsofTransitCentershouldbeafundamental considerationinintegratingthetwostructures. the of functions public the between relationships flow and Symbolic functions. ancillary and support all and conflict, and flows pedestrian and vehicular requirements, massing and program the to adherence movement, people accessibility, user including Tower and Center Transit the of issues technical and functional the of understanding thorough a illustrate should Proposals The that wouldbeinvolved,andadescriptionoftheirindividualresponsibilities. members Team the a of identity the including construction, and design final Tower, the of completion Transit for milestones detailed containing the schedule for Agreement Option Development and Design the for terms key propose should Respondents evidence thattheTeamhassufficientcapitalresourcestofinance developmentoftheTower. that can be financed and built. The Respondent’s plan to finance the development of the Transit Tower should include detailed Respondents should submit the appropriate financial and pro forma documentation that demonstrates a development program amount ofrevenuetotheTJPAandoverallfinancialfeasibilityTowerproposal. Transit Center The Tower design concept should demonstrate the relationship of the Tower to the Transit Center, enhance public access to the and Towershouldbethefocusofanevolvingneighborhoodcreateiconicarchitecturalimage. Center Transit The neighborhood. pedestrian-oriented vibrant, a promote will that uses and design level street the on emphasis It design. Center should demonstrate integration of green design, seismic and structural innovation, and constructability. It should Transit place particular the to complimentary and compatible is that should reflect an understanding of the role the Tower plays in the urban form of San Francisco. The Transit Tower design concept concept design a present should Proposal Tower The individual their of description a and involved, be would responsibilities. that members Team the of identity the Center, Transit the for design the develop to consultants its and milestones TJPA the detailed with work containing would Team schedule the how of a description a Center, design, final Transit the of the completion for for design completed the for Team the to pay would TJPA the Respondents should propose key terms for the Design Agreement for the Transit Center, including the total monetary compensation concept shouldalsoberesponsivetotheTJPApreliminaryestimateofdirectconstructioncost. Definition Scope TJPA the in contained criteria design Report, and and demonstrate the ability requirements to satisfy the the TJPA’s operational, technical, meet and other should requirements. The Transit concept Center design design Center Transit The and Center; Transit the to uses design, andseismicstructuralsafety. its and Tower the flow of relationship resident the and image, architectural to user given requirements; care particular operational with transit complex, address the should throughout Proposal Center Transit The neighborhood. oriented pedestrian- vibrant, a promote will that uses level street the on emphasis particular place should Proposal The Francisco. San of The Transit Center Proposal should reflect an understanding of the role of the Transit Center and Tower as part of the urban form POINTS JUROR: RESPONDENT TEAM: STAGE II - DESIGN AND DEVELOPMENT PROPOSALS - 40 40 20

TRANSIT CENTERPROPOSAL CATEGORY FUNCTIONALITY ANDTECHNICALISSUES TOWER PROPOSAL , and meettherequirementsdesigncriteriacontainedinScopeDefinitionReport. design excellence design , community context, transit operational requirements, user flow and accessibility, green accessibility, and flow user requirements, operational transit context, community (Updated) (Updated) DATE: LEAD DESIGNER: JURY EVALUATION SHEET Total Score SCORE COMPETITION FOR STAGEII UPDATED MANUAL 24

Transbay Transit Center & Tower - Design & Development Competition EVALUATION OF STAGE II 02/23/07 Baumer Distinguished VisitingProfessorship atOhioStateUniversity. Herbert the to appointed were they 1996, in and Design, Architectural of Professors Visiting Saarinen 1985 to 2002. In 1995, as well as 2000, Mr. Hodgetts and Ms. Fung were invited to Yale University as Eero from California Pomona, in Design Environmental of School University Polytechnic State California the at professor a also was She Programs. Graduate of Director the currently is she where Architecture, of Institute California Southern at taught has and of Angeles, Los California, of University the Master at Architecture her earned Fung Ms. Architects. of Institute American the of chapter Medal Angeles Gold Los the the from received Fung Hodgetts+ 2006, In Arts. the for Endowment National the the for on Council serve to Clinton President by nominated was and Rome, in Academy American the through Fellowship Advanced Prize Rome NEA the of recipient 1991 the was Fung Ms. addition, In Art. Modern of Museum Francisco San the and Angeles, Los in Art Contemporary of Museum The Aires, Buenos in work hasbeenexhibitedattheLosAngelesMuseum ofScienceandIndustry,theMuseumFineArts for Yamano Gakuen in Tokyo, and the renovation of the Egyptian Theater on Hollywood Boulevard. Her ‘Towell’ Library at UCLA, the new design of the famed Hollywood Bowl, has been the engaged in 35-story the execution of mixed-use all of glass the firm’s tower projects, including the award-winning temporary allows for accessibility without compromising vitality. As Director of Design for Hodgetts + Fung, Ms. Fung approach universal This designs. Fung’s + Hodgetts to perspective unique a adds environments urban and Design Fung + various in experience human the of comprehension her countries, several in lived Having Architecture. Hodgetts of principal/co-founder and educator, architect, an is Fung Hsin-Ming HSIN-MING FUNG,AIA University ofCaliforniaatBerkeley. an M.S. in Civil Engineering from , and a Ph.D. in City and Regional Planning from the program of the World Health Organization. She has a B.S.E. in Civil Engineering from Princeton University, Cities Health the in participated has and Council Research National the and Medicine of Institute the of committees on served has She journals. academic international several of boards editorial the and Advisory National the Board, Foundation, Johnson Wood Research Robert the by funded program Design by Transportation Living Active the of Committee the of Transportation in Issues Women’s and Behavior, Travel and Telecommunications Development, Land and Transportation on Committees the transportation planning for her ability to link research to policy and practice. Dr. Handy is a member of the on research her for connection known between she internationally neighborhood design is and and She walking behavior behavior, and topics. is travel these widely respected on in on publications the field 30 patterns of than development more has land of impact the and development land on on the relationships between transportation and land use, both the impact of transportation investments focus interests research Her Davis. California of University the at Center Transportation University the of Dr. Susan Handy is a Professor in the Department of Environmental Science and Policy and the Director SUSAN L.HANDY,P He livesandworksinCambridge,Massachusetts. and and Monthly Fellowship Atlantic the in Traveling appeared have poems Appleton His Prize. Kelley the received he where Design, of School Graduate Harvard the and Journalism; of School Graduate Columbia the Kappa; Beta Phi to elected was he where College, of outstanding recognition contributions “in to Architects, architecture of and Society to Boston the the profession.” of Honor Mr. of Campbell Award is 2004 a the graduate of of recipient Harvard the is He Sciences. and Arts of Academy American the and Architects of and Institute cities, American the and of institutions Fellow a cultural is to consultant a as 1975, since architect an as practice private in been has He city.” American the of fate the about cares who anyone of bookshelf the on “belongs it a book, Cityscapes of Boston: An American City Through Time, of which the Chicago Tribune wrote that Boston Globe. He is a bimonthly columnist for the magazine Architectural Record, and is the author of the of critic architecture as work his for Criticism for Prize Pulitzer the of recipient a is Campbell Robert ROBERT CAMPBELL, COMPETITION JURY Michigan. In 2003 he was a Senior Fellow in the National Arts Journalism Program at Columbia University. has taught architecture at several universities, most recently as the 2002 Max Fisher Visiting Professor at has reviewed books on architecture, urbanism, popular culture, and poetry for the New York Times, and numerous publications. In 1997 he was architect-in-residence at the American Academy in Rome. He FAIA h D elsewhere and his photographs in photographs his and COMPETITION FOR STAGEII UPDATED MANUAL 25

Transbay Transit Center & Tower - Design & Development Competition COMPETITION JURY 02/23/07 Programs. Awards Design Architects of Institute Architecture American various the for for and Awards recently Design Week programs Record/Business award design for juror invited an as serves and architecture of schools at frequently lectures Williams Ms. Magazine. Ebony and Magazine Enterprise Black Report, about Williams have recently appeared in The New York Times, Wall Street Journal, US News and World articles Featured Francisco. San in Women of Museum International the and Culture American African Wilson August the currently and Terminal, Airport International Francisco San the Complex, design are credit her To 1997. in AIA leadership the roles in in the Fellow design Design of to several Harvard elevated award winning the was projects to including and the board appointed San Francisco advisory recently Civic Magazine Center was She Exploratorium. The and Diaspora African the of California, of Museum University the for directors of board the the on and Committee, Review on Design Planning Capital Berkeley’s serves She Design. of School Graduate Harvard the at Fellow Loeb a practice of art and a Master’s of Architecture both from the University of California, Berkeley, and was the in degree Bachelor’s a holds Williams Ms. Francisco. San in Merrill & Owings Skidmore, with partner Williams was the principal and director of design for Ai from 1997 to 2004, and prior Ms. developments. mixed-use civic and high-rise to urban, and institutions, cultural facilities, headquarters that was associate Allison Williams sets the design strategy for Perkins+Will San Francisco’s major projects including corporate ALLISON G.WILLIAMS,FAIA past presidentofLambdaAlpha,aninternationallandeconomicssociety. as well as initiatives, government and planning promote to formed organization leadership Francisco San a SPUR, of member board past also is Keyser Mr. growth. region’s the in assist to government and member of Institute, the Bay Land Area Economic Forum, Urban an organization the composed of board former leaders of a in is He business, Council. member Partnership education Public/Private the and a Council Use Mixed ULI is a chaired has Keyser Mr. University. Columbia from MBA his earned and University Cornell of graduate a is He implemented. be can that strategies revitalization and/or retail He has also had extensive experience in assisting cities and towns in their efforts to develop downtown his career, Mr. Keyser has been extensively involved in analysis of and consultation on multi-use projects. and contacts with the development and financial community throughout the United States. Throughout combine to give Mr. Keyser unique insight in real estate trends, what works in real estate development, groups professional and industry with work and knowledge experience, His Portland. in Place Pioneer and Diego, San in Plaza Horton Francisco, San in Ballpark AT&T including developments impact high and distinguished West’s the of many of For center the at been has Keyser community. Mr. years, thirty than more redevelopment the and of estate real principal the founding in authority a recognized is a is He and development. Marston Keyser on consulting and projects estate real of feasibility the A. Jerry Keyser, Keyser Marston’s Chairman of the Board, has spent his entire professional life in evaluating A. JERRYKEYSER American InstituteofArchitectsforhiscontributionstotheprofession. Around Development Successful for Principles Ten ULI’s of author contributing a also was Harris Mr. Institute, Land Urban the of Trustee Past As visioning. civic and community for Definition” “Project in expert premier a become to Associates Turner allowed has workshops” “visioning interactive through vision of consensus a form to clients and organizations community with work to ability His integration. Alabama, Louisiana and Florida, with a focus on transit planning, design and commercial development Ohio, Georgia, in projects planned and designed has He projects. constructed in billion $3 than more of projects, transforming the urban fabric of Atlanta and other major urban areas. Harris has completed design work bearing the name Turner Associates. For over 30 years, the firm has designed a multiplicity the of all oversees and vision strategic firm’s the for responsible is He Georgia. Atlanta, in Inc Planners, Oscar Harris is Founder, Chairman of the Board and Creative Director of Turner Associates Architects and OSCAR HARRIS,FAIA Mellon University where he also serves as trustee. In 2004, he was awarded the Bronze Medal from the from Medal Bronze Carnegie the awarded was he 2004, In from trustee. as serves also he where Architecture University Mellon of Master a and Pennsylvania in University Lincoln from Arts of Bachelor a holds Harris Mr. career. entire his issues connectivity and design facility transportation in specialized has He Authority. Transit Rapid Atlanta Metro the for contract Consultant Engineering General the airport in billion $5.4 the Principal a of is he Additionally, Georgia. management Atlanta, in Airport International Jackson program Hartsfield of expansion the for Consultants) Aviation (International Principal a IAC is He in Orleans”. New of Rebuilding “The for Conference ULI for member panel a was and Center for Center

Transit, COMPETITION FOR STAGEII UPDATED MANUAL 26

Transbay Transit Center & Tower - Design & Development Competition COMPETITION JURY 02/23/07 he againrejoined thePlanningDepartment asitsDirector. serve to request, Newsom’s Mayor at him 2004, late In appointed 1992. until held Feinstein he position a Planning, Mayor of Director as again when 1980 in Francisco San Macris to returned Mr. He Director. Governments. Area Planning Bay of as Association the of 1975 Director Associate Executive in become to and 1976 in government Development City left Community of Director as 1972 in him appointed Alioto Joseph Mayor Director. Assistant as Department Planning Francisco San the joined he 1968 In Development. and Planning of Department Chicago the of Commissioner Assistant Daley, J. Richard Mayor by appointed was he 1965 In Chicago. in career planning his began Macris Dean DEAN MACRIS,FAICP the HispanicChamberofCommercenamedherone ofthe2006MostInfluentialBayAreaLatinos. named Ms. Ayerdi One of The Most Influential Women in Public Times Service Business in Francisco the San Bay the Area. That 2006, of same In year, Project. Transbay Woman the advancing Chapter, in success her Area for Year, the Bay Francisco San Seminar, Transportation Women’s the named was she 2004, In transportation. Area Bay and environment special Francisco’s San her of for betterment the Award, to contributions Hero Unsung Tomorrow’s Francisco San with honored was Ayerdi Ms. 2002, In legal Service’s Parcel United with worked she work, department. service public her to Prior Roundtable. Airport Peninsula the of member Vice-Chair of the Executive Committee of the Association of Bay Area the Governments and member of the been Francisco’s has San and of Corridor Director Mayor Joint Powers the Board Project (Caltrain), Deputy as Director of and the served Bay Area previously Advisor Air Quality Management She District, Policy She California. Law. Transportation of of Bar College State Hastings the and of Berkeley member California, a of is University the of graduate a is Ayerdi Ms. and determinationhavebeencrucialtotheadvancementofTransbayTransitCenterProject. courage experience, skill, Ayerdi’s Ms. that recognized generally is It extension. tax sales Francisco San billion in Project funds, including the land transfer proceeds, a voter-approved Bridge toll increase and towards the funding of the Transbay Transit Center Project. In total, Ms. Ayerdi has aggregated over $1 California Department of Transportation. personally Ayerdi The revenues Ms. that TJPA, will the result of from behalf this transaction on will and negotiated be effort the applied transfer this of of approximately 19 part acres of As prime San Francisco Project. land the belonging to of the Phase State of first the Decision has been issued. She identified and developed the funding necessary to design and construct has now been cleared under Federal (NEPA) and California (CEQA) requirements. A federal Record of EIS/EIR The process. (EIS/EIR) environmental Project’s the managed She (TJPA). Authority Powers Joint On behalf of the Project, Ms. Ayerdi developed the Joint Powers Agreement which formed the Transbay other professionals. Director Executive As MARIA AYERDI,JD Non-Voting Berkeley. HeisaregisteredProfessionalEngineerin27states. Civil in degree Science of Bachelor his Engineering received and Master of Science degree in Structural Engineering from the University of California at Johnson Mr. Oregon. of University adjunct the an at is He professor Oregon. of Council Engineers Consulting the of and Engineers Structural American of Council a the of chair as past is Johnson and Mr. Oregon. of Oregon, Foundation Architectural the of of member board University the at Arts Allied and Architecture of School the for Visitors of Board the of secretary University, State Portland at Board Advisory College Maseeh the of chair as serves He the including Turkey. Istanbul, in projects, Consulate US the and Hospital, Childrens complex Doernbecher Center, Convention Oregon most firm’s the of many on engineer” Johnson structural “design Mr. the engineering, as structural acts for principal-in-charge As systems. framing structural complex of engineering professional of years 35 design experience over in the has seismic analysis Johnson and seismic Mr. design of 1974. structures in and in office the analysis Oregon and held design the has opening he since position a office, Portland KPFF’s of partner-in-charge and president vice is Johnson Art ARTHUR JOHNSON,PE,SE Transbay Transit Center Project. Her delivery team now includes over 200 engineers, architects and architects engineers, 200 over includes now team delivery Her the of Project. elements Ms Center all Transit of Transbay Center). development and Transit design ongoing (Transbay the manages Project and directs Extension currently Ayerdi Downtown Terminal/Caltrain multi- the Transbay of operation dollar and construction billion design, the for responsible is Ayerdi Ms. Directors, of Board Ex Officio of the Transbay Joint Powers Authority Powers Joint Transbay the of Members

reporting to a five member, three-county member, five a to reporting COMPETITION FOR STAGEII UPDATED MANUAL 27

Transbay Transit Center & Tower - Design & Development Competition COMPETITION JURY 02/23/07 and designed over 50 national and international processes for competitions, commissions, and plans, and commissions, competitions, for processes international and national 50 over designed and family housing, office buildings, historic renovations, and cultural centers. In addition he has developed and taken on physically a range communities, of projects including rebuilding the has Stastny Mr. planning internationally. and nationally, locally, architecture of of expectations years and understanding neighborhoods, cities and thirty regions, museums, multi- for public’s facilitator the elevating toward works he tool, strategic and comprehensive a as design Using culturally. and designer, urban architect, practicing a been has Inc. Architects, StastnyBrun Portland’s of CEO and founder a Stastny, J. Donald Competition Manager DONALD J.STASTNY,FAIA,FAICP Corps CommunityCenter(RJKCCC)forTheSalvation Army. State Capitol Designer/Design Competition in Juneau, Alaska and for the Chicago Ray and Joan Kroc Alaska the for processes competition international facilitated and authored recently also StastnyBrun interpret theMemorial’sMissionStatementinform ofamemorialexpression. competition the Service, advisors created and facilitated a two-stage open competition process that challenged individuals to Park National the and Commission, Advisory 93 Flight Force, Task Memorial National 93 Flight 93, Flight of Families the with conjunction in Working year. last Pennsylvania County, a competition advisor for the Flight 93 National Memorial International Design Competition in Somerset this experience and the experience with the Department of State, StastnyBrun Architects also served on as Drawing administration. competition and development program for responsible was team project bombing. Working with a 350-member volunteer task facilitated force, the including family of members StastnyBrun survivors and and survivors, the victims Memorial. the to dedicated National memorial a develop to City process design international Oklahoma an the for competition a lead to managers competition design for search nationwide a through selected was Architects StasntyBrun addition, In could berealizedwithinthegeneralguidelinesofGSAprocess. issues critical these how and requirements, security and programs embassy of understanding their on particularly those in the China Projects portfolio. StastnyBrun was asked to undertake this process based the U.S. Department of State to modify the GSA protocols to apply to design selection for U.S. selection embassies, state-of-the-art as methodology for adopted other federal be and state agencies. to After begun its publication, StastnyBrun has was asked to and assist be program to acclaimed continued GSA’s for has basis GSA, the by guidebook published the guidebook, for The basis the processes. selection as Excellence outcomes Design and on processes the used and GSA and the Oregon in for courthouses Massachusetts U.S. for competitions design concurrent two Building undertook – They Guide Legacy”. Program a Excellence Design “The the authored Architects StastnyBrun GSA, the For Kenya andTanzaniatorebuild. to commitment Nation’s our met and budget, within and time record in completed were embassies two The State. The of Department U.S. the for projects design/build other for model a become has process process. competition equitable and fair a maintaining while builder/contractors the and teams, architect/engineer the client, the between interaction allowed that process selection design/build a created StastnyBrun Lindquist, Kling with Collaborating months. ten in construction into program from terrorist by apart torn been had that bombings embassies in Nairobi, two Kenya and the Dar es Salaam, for Tanzania in competition 1998. The and design/build process created moved a the StastnyBrun two embassies association, managed this Continuing Berlin. in embassy U.S. new the for competition StastnyBrun’s relationship with the and U.S. Department of State competitions began with their design management of the design run has selection Architects processes for the U.S. Department of State and StastnyBrun the U.S. General Services Administration (GSA). qualifications, superb their for Recognized raise communities’expectations. creating on the designers and focused author processes that create an environment for have designers to do their best work they and competitions, design interventions managing in the urban fabric and that have catalytic authoring effects reaching far initiating, beyond the icon. of They promote years competition process has historically been used to create architectural icons, but in StastnyBrun’s twenty design The experts. competition premier nation’s the of one as recognition Stastny’s Don and in firm the resulted design, has experience including of depth competitions, This processes. 50 innovati COMPETITION FOR STAGEII UPDATED MANUAL 28

Transbay Transit Center & Tower - Design & Development Competition COMPETITION MANAGER 02/23/07 • • • • • • • • • • • • • • • • • • • • StastnyBrun ArchitectsProcessDesignandManagement Charrette Institute. of LEED Institute a American Planners, the Certified of member a is She University. State Portland at Development Estate Real in Certificate Graduate and Planning Regional & Urban of Master her completed and University A&M of Design the competition processes. Ms. Mannhard received her Bachelor of International Environmental Design from Texas Memorial National execution and coordination successful ensures and materials, competition all of creation the oversees 93 Flight the or creates clients, and competitors between information on of exchange the manages She Competition. assistance provided also facilitation She Army. Chicago and Salvation The the coordination for for (RJKCCC) Center and Community Competition Corps Kroc Designer/Design Joan Capitol and Ray State Alaska the for manager project the as served Mannhard Ms. projects. development participated and and planning, visioning, coordinated community numerous also in has she outreach, and processes public practices. about business Knowledgeable and design sustainable advance and integrate to entities non-profit and private focused and perspective, considering the comprehensive big picture while remaining a cognizant of finer details. both She has worked from with development and development. environment estate built the real understands and She design, urban She planning, Architects. architecture, StastnyBrun in training with and manager experience project has and planner professional a is Mannhard Jennifer Project JENNIFER MANNHARD,AICP,LEED and PacificRegion’sMedalofHonorforhiscontributionstothearchitecturalprofession. Northwest AIA 2006 the awarded recently was He Greece. Athens, in Ekistics of Center the at Fellow City Planning and at the University of Pennsylvania, and continued his post-graduate studies as a Research Architecture in degrees Masters his received He Washington. of University the from Architecture his received Stastny Mr. Planners. of Institute Bachelor of Science degree in Business Administration from Oregon State Canadian University, and a Bachelor of the of member a is he Additionally, Design. the Urban of Institute the and Planners, Certified of in Institute American the Architects, of Institute American Fellowship with honored been has he planner, and architect award-winning An associations. neighborhood and governments, tribal departments, city agencies, state governments, international many of which have become national models. He is a masterful facilitator as well, having worked with California Jewish MuseumArchitect Selection–SanFrancisco, California Villa MontalvoArtistResidencyInvitational –Saratoga, California Exploratorium DesignCharretteand Atelier–SanFrancisco, Study /StationDesignCharrette– Washington, D.C. Washington MetroAreaTransitAuthority CoreCapacity Design Competition–Boise,Idaho Capital CityDevelopmentCorporation PioneerCorridor California Ontario EducationalVillageDesignCompetition–Ontario, SE MorrisonCharrette–Portland,Oregon – Juneau,Alaska Alaska StateCapitolDesigner/DesignCompetition Center A/ESelectionCompetition–Chicago,Illinois The SalvationArmyRayandJoanKrocCorpsCommunity Francisco, California Transbay TerminalDesign/DevelopmentCompetition–San U.S. EmbassyDesignCompetition–Berlin,Germany Tanzania U.S. EmbassyDesign/BuildCompetition–DaresSalaam, U.S. EmbassyDesign/BuildCompetition–Nairobi,Kenya Program, ChinaProjects U.S. OverseasBuildingOperationsDesignExcellence City, Oklahoma Oklahoma CityMemorialDesignCompetition– Competition –Shanksville,Pennsylvania Flight 93NationalMemorialInternationalDesign Francisco, California San FranciscoPrize/GSAPlazaDesignCompetition– Competition –Springfield,Massachusetts General ServicesAdministrationU.S.CourthouseDesign Competition –Eugene,Oregon General ServicesAdministrationU.S.CourthouseDesign Handbook General ServicesAdministrationDesignExcellenceProgram Manager ® Accredited Professional, and Charrette Planner Charrette and Professional, Accredited ® AP • • • • • • • • • • • • • • • • • • • • • Oregon Pioneer Courthouse SquareDesignCompetition–Portland, California Beverly HillsCivic Center DesignCompetition–Beverly Hills, California Domaine ClosPegaseDesignCompetition –NapaValley, – Portland,Oregon State ofOregonOfficeBuildingDesign Competition Seattle CityHallDevelopmentStrategy –Seattle,Washington California Walt DisneyConcertHallDesignCompetition –LosAngeles, South WaterfrontDevelopmentProgram–Portland,Oregon Competition –SanDiego,California San DiegoCivicandGovernmentCenterDesign/Build Labor &IndustriesBuildings)–Olympia,Washington and Departmentof East CampusPlusDesign/BuildProgram(NaturalResources – LosAngeles,California Center, NaturalHistoryMuseum,PerformanceGlen&Grove) ArtsPark Center,PerformingArtsChildren’s ARTSPARK LADesignCompetitions(MasterPlanCharrette, Townsend, Washington Port TownsendGatewayCommunityDesignCharrette– Perris CivicCenterDesignCompetition–Perris,California Vegas, Nevada Clark CountyGovernmentCenterDesignCompetition–Las – Portland,Oregon Lewis &ClarkCollegeSignatureProjectDesignCommission Competition –LosAngeles,California South CentralLAMixed-UseDesign/Develop/Build Lawrence Island,Alaska Gambell SchoolDesign/BuildCompetitionProcess–St. Manteca BusinessSummit–Manteca,California Waverly ParkDesignCompetition–Kirkland,Washington – Oakland,California Oakland AdministrationBuildingsDesign/BuildCompetition – Berkeley,California Berkeley PublicSafetyBuildingDesignCompetition ® certified by the National the by certified COMPETITION FOR STAGEII UPDATED MANUAL 29

Transbay Transit Center & Tower - Design & Development Competition COMPETITION MANAGER 02/23/07 CONTACT INFORMATION DONALD J.STASTNYFAIAFAICP For moreinformationpleasecontact: JENNIFER MANNHARDAICP www.transbaycenter.org Or visittheCompetitionwebsite: Competition ProjectManager [email protected] [email protected] StastnyBrun Architects,Inc. Competition Manager (503) 222-5533 COMPETITION FOR STAGEII UPDATED MANUAL 30

Transbay Transit Center & Tower - Design & Development Competition CONTACT INFORMATION 02/23/07 TransbayJointPowersAuthority C. DISADVANTAGED BUSINESSENTERPRISEPROGRAMREQUIREMENTS DISADVANTAGED BUSINESSENTERPRISEPROGRAMREQUIREMENTS B. DISADVANTAGEDBUSINESSENTERPRISEPROGRAMREQUIREMENTS A. APPENDIX QUALITY MANAGEMENTSYSTEMMANUAL J. TRANSBAYTRANSITCENTERBUILDINGSCOPEDEFINITIONREPORT I. H. PROTEST PROCEDURES LICENSING REQUIREMENTS G. CERTIFICATION REGARDINGLOBBYING F. CERTIFICATION REGARDINGDEBARMENT,SUSPENSION,ANDOTHER E. D. LEVINE ACT ) FinalExpenditureReport D) SubcontractorPaymentDeclaration C) ProgressPaymentReport (Part 1&PartII) B) Bidders/ProposersInformationRequestForm A) Standard AgreementForSubcontractor/DBEParticipation Caltrans Exhibit10-J Notice ToBidders/ProposersDisadvantagedBusinessEnterpriseInformation May 5,2006 Caltrans Exhibit10-I Volume One:ExecutiveSummary RESPONSIBILITY MATTERS (Updated) The CompetitionManualAppendix Final Report:ProcessSummary& has beenomittedfromthis Jury’s Recommendation

(Updated) COMPETITION FOR STAGEII UPDATED MANUAL 31

Transbay Transit Center & Tower - Design & Development Competition APPENDIX 02/23/07 negotiation. The TJPA shall have no obligation unless and until the parties enter into final agreements further final into to enter parties the subject until and be unless obligation may no have shall terms TJPA The submittal; negotiation. Team’s the of terms all accepts TJPA the that mean not Design Agreement for the Transit Center. The TJPA’s selection of a Team for exclusive negotiations shall a and Tower Transit the for Agreement Option Development and Design a in for negotiations engage exclusive to Team D/D a select and report Board staff TJPA’s TJPA and The recommendation TJPA. Jury’s the the review to will recommendation its submit and Proposals the rank will Jury The Tower. the of development the from Program the to revenue potential the and requirements, TJPA’s the to adherence Tower, and Center Transit the of functionality design, proposed the of quality the evaluate The Jury will consider the written submission and oral presentation of each of presentation oral and submission written the consider will Jury The h cmoiin f h Jr wl b te ae hogot h Cmeiin Te ae uy who Jury Proposals received donotmeetthestandards setbytheTJPA. same The Competition. the Jury will also be responsible for recommending termination of the Competition if it determines that the throughout same the be The Respondents. II Stage rank will II Stage to advance to I will Stage from Teams D/D the recommended Jury the of composition The The CompetitionJury Team D/D and theTJPA. the between relationship legal and financial the define and structures two the of design terminate theselectionprocessatanypoint.TheAgreements shallcontaindetailedstandardsforthe to right the reserves also TJPA The Team. ranked second the with negotiations commence and team top-ranked the with negotiations terminate to right the reserve Board and Staff TJPA the then Board, fails to agree to terms for the Agreements that the TJPA Staff can recommend for approval Team the by If the Directors. TJPA of Board TJPA the by approval for recommend to willing is and Program the of Design a and Tower Transit the interests best the in be to considers Staff TJPA the that (Agreements) Center for Transit the for Agreement Agreement Option Development and the Design with a negotiate shall Team staff selected TJPA Team. a with negotiations exclusive in engage to staff authorize may discretion, sole its in and, report staff TJPA the and Report Jury the consider will Board TJPA TThe Contract Award following approvalbyformalresolutionoftheTJPABoardDirectors. and requestsforclarifications, aspects of the Proposals to determine compliance with minimum criteria and to question Upon submission of the Proposals, the Competition Manager and TJPA staff will evaluate the technical with theCompetitionManager,TJPAstaff,andconsultants. will provide the TJPA the II, Stage of commencement the At Property”). (“Tower Tower the for site the of lease ground or purchase the for terms financial proposed design including (“Proposals”), for Tower Proposal the of a development and and Center, Transit the of design the for Proposal a prepare will Respondents meets theTJPA’sstandardsfordesignexcellenceandfinancialfeasibility. in Stage II of the Competition have expertise Design/ to (“RFP”) Proposals for Stage I of the Request Competition (“Respondents”). The Jury in this Directors determined of that Board TJPA the the by Teams issues approved selected and Jury to the participate by selected (“TJPA”) were that Teams Development Authority Powers Joint Transbay The INTRODUCTION ANDOVERVIEWOFSTAGEIITHESELECTIONPROCESS REQUEST FORPROPOSALS(RFP) DESIGN ANDDEVELOPMENTCOMPETITION TRANSBAY TRANSITCENTERANDTOWER in designing and building world-class high rise buildings or request clarification. Following this technical review and the Respondents’ responses to questions to responses Respondents’ the and review technical this Following clarification. request or and Answer Period budget for the Transit Center, and other requirements for Proposals. Respondents , e ach Respondent will have an opportunity to participate in two mid-course reviews with an information packet describing the scope of the two structures, the Respondents will presenttheirProposalstotheJury. in designing prominent and complex public projects ,

#07- and are capable of producing a proposal that 04 In addition to an ongoing Question Respondent. The Jury will Jury The Respondent. Respondents and RF

1 Transbay Transit Center & Tower Design & Development Competition REQUEST FOR PROPOSALS P 02/23/07 with the TJPA Staff, TJPA Board, TJPA consultants, PMPC team, or Jurors. Any such communication will communication such Any Jurors. or team, PMPC consultants, TJPA Board, TJPA Staff, TJPA the with It is against the Competition Regulations for Participants to communicate with respect to this Competition eadn sbitl otn ad omt shdl ad vns ad vlain rtra o the for criteria evaluation and events, Competition the and in forth set Regulations Competition schedule the to conform must Proposals format, All Competition. rules and and information content pertinent all submittal contains regarding It Regulations. and Process Competition the describes THIS ISAREQUEST FORPROPOSALS FROMINVITEDD/D TEAMS. automatically disqualifyParticipants. at Mannhard Jennifer Manager, Project or FAICP FAIA TRANSBAY Stastny J. Donald. the to Manager, sent be Competition should Competition Development and Design the or RFP this regarding questions All INQUIRIES with alladdenda.Teamsshouldthereforecheckthe website beforesubmittingtheirProposals. compliance for responsible solely are Teams (www.TransbayCenter.org). website TJPA’s the on posted The TJPA may modify the RFP prior to the Proposal due date by issuing written addenda. Addenda will be ADDENDA and forquestionsanswers. Report, Definition Scope six-volume and deliverables, and process Competition Project, the discuss to be will meeting the for agenda basic The I. Stage during held were Meetings Pre-Submittal the where Theater Herbst the from upstairs is Room Green The 94102. CA Francisco, San floor, 2nd Avenue, Ness The Stage II Briefing will be held on March 1, 2007 from 9:00 a.m. – noon in the Green Room at 401 Van Proposal requirements,thebudgetforTransitCenter,andScopeDefinitionReport. Manager and representatives of the TJPA to review the Competition schedule, Competition procedures, D/D Teams are required to attend the Stage II Competition Briefing in San Francisco with the Competition STAGE IIBRIEFING TJPA BoardSelectD/DTeam Jury RecommendationtoTJPA Public MeetingtoPresenttheDesignConcepts Presentations totheJuryandEvaluation Proposals Due Question &AnswerPeriodEnds 2nd Mid-courseReviewweekof 1st Mid-courseReviewweekof Question &AnswerPeriodBegins Stage IIBriefing Issue RFPandUpdatedCompetitionManual The officialandcompletescheduleisintheCompetitionManual.Keydatesare: SCHEDULE ANDKEYDATES Manual. from be documents to the forms downloading the by including Proposal, Manual, the Competition in the submitted and RFP this of copies obtain may Teams D/D SUBMITTAL INFORMATION February 23, developmentcompetition @stastnybrun.com 200 7

r y otcig h Cmeiin aae. h Cmeiin Manual Competition The Manager. Competition the contacting by or or

(503) 222-5533 . 8/15/07 8/01/07 6/11/07 4/16/07 10/18/07 10/11/07 9/21/07 9/18/07 –9/21/07 3/01/07 3/01/07 2/23/07 www.TransbayCenter.org/design-

RF

2 Transbay Transit Center & Tower Design & Development Competition REQUEST FOR PROPOSALS P 6/29/07 1 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS 1 The guidelines for the competition don’t provide enough opportunity for the design teams to meet Q1: DISTRIBUTED 3/13/07 STAGE IIQUESTIONS&ANSWERS 3 h Tast etr a aray en tde i a ERES ne te aiona Environmental California the under EIR/EIS an in studied been already has Center Transit The A3: it is or EIR, own its have it Will tower? the for process entitlement specific the to speak you Can Q3: originally the to return to elected and schedule the reviewed have City the and TJPA The A2: schedule. holiday European account into take not does 15 August proposals, for date new The Q2: The requirements are to ensure fairness of evaluation and not designed to restrict your creativity. drawings the include that boards oriented vertically 48” x 36” ten is requirement submittal The The requirements stated in the Competition Manual (02/23/07) and the ‘Draft Required Drawings A1: h rqie daig ad cls n em o yu dsg s ta w my ae corrections/ make may we consideration into that take will requirements the so to made refinements Any necessary. design if refinements your of terms in scales and drawings required the with the Jury, or enough freedom to present our designs. The size and quantity requirements for requirements quantity and size The designs. our present to freedom enough or Jury, the with current 550 feet and establish new design controls for the District, as well as lay the foundation the lay as well as District, the for controls design new establish and feet 550 current expected to increase the allowable heights of buildings in the Transbay Terminal area above the the additional environmental review for the Tower will be minor. that The Transbay District rezoning is anticipates Department the Tower, Transit the of impacts potential the of many cover will Francisco rezoning San District the Transbay new Because the of review review. environmental that that expects in Department studied Planning be to issues the and Tower Transit the for review environmental of level the determine will Team Development and Design selected the by proposed project Tower specific the of Study Initial Department’s Planning the CEQA, Under (based onaspecificmixofuses)theTowerwillrequire additionalenvironmentalreview. review. environmental additional require will Tower the impacts traffic and shadow, wind, bulk, specific the that contemplated always was it Moreover, of height additional The feet. 550 of review for the Transit Center is complete. The EIR/EIS studied a Transit Tower of a maximum height in April 2004. The TJPA Board also approved an Addendum to that EIR/EIS in 2006. Environmental Quality Act (CEQA) and the National Environmental Policy Act (NEPA). That EIR/EIS was certified included withthetransitcenter? established submissionandevaluationdates.SeeAddendum#1datedMarch13,2007. Can itbechanged? See Addendum#1datedMarch13,2007. (public meeting)inperson. The D/D Teams will present their proposal to the both the Jury and to the TJPA Board of Directors at thepresentationtoJuryandisnotarequiredpartofinitialProposalsubmittal. enable both Jury and public understanding of to the design concept. The model is boards to be delivered the on scales drawing the with commonality have to needs model the of scale The an architectural model of the Transit Center, Tower and immediate environs at a scale of 1”=40’. In addition, contrary to the direction given at the Briefing, D/D Teams will be required to provide of yourchoosing. etc. diagrams, images, model photos, text, through design your of explanations and expressions individual/team for room you allows boards of amount the drawings, required the to addition In all TeamsdesignsandtheneedtopresentthemequallyJury. 1 The 2007. 1, March on Briefing II Stage the at distributed Scales’ Drawing and Drawings Required ‘Draft the on indicated scales the at will beabletofairlyassessthedifferentproposals. to Jury established the scales, specific at were drawings specific mandating By 2007 Jury. the by evaluation 1, fair a ensure March on Briefing II Stage the at distributed Scales’ Drawing and the boardsarerestrictive. st Mid-course Review is your opportunity to respond to respond to opportunity your is Review Mid-course NOTE: A60HASBEENMODIFIED 6/29/07 6/29/07 2 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS 7 What is the protocol for community outreach? Are Q7: we permitted to contact or meet with community Attached are a PDF and a CAD file of the most recent redevelopment plan area map (from the A6: Isitpossible to obtainalarge-scaleplanoftheTransbayNeighborhood RedevelopmentArea? Q6: DISTRIBUTED 3/22/07 Francisco San the for speak not does and over control or jurisdiction have not does TJPA The A5: Isthe Cityhiringoneofthecompetingfirmsforsitestudies? Q5: In the initial investigation of urban form A4: for the Transbay Area, the Planning Department conducted WhataboutPropK? Q4: review for the Tower will be determined in the Initial Study following the definition of a specific a of definition the following Study Initial the in determined be will Tower the for review additional traffic analysis, or any further environmental review. Again, the level of environmental that from different substantially assumed in not the Transbay District rezoning EIR, it is is possible that the Tower will not proposed require a full EIR, ultimately design Tower the of impacts traffic the height, of probable reasonably bulk, wind, and traffic assuming impacts using most the best information available. If the height, bulk, wind and Tower Transit study the of impacts will the review to EIR attempt will District Department The Transbay District. Transbay new the the in development high-rise of that impacts environmental anticipates Department Planning The Program andotherpublicbenefitsfortheTransbayDistrict. a certain height. The revenues of the Mello-Roos tax will used to fund the Transbay Transit Center above extend that projects building from payments require will that tax special Mello-Roos a for and neighborhood groupstodiscusstheir desireswithregardstopublic amenitiesorfacilities? Streetscape andOpenSpace Plan)providedbytheRedevelopmentAgency. competition. site of the Project to San any consultant the or that subconsultant the to relating however, participating contract any award to intend currently not in does Department understands, Planning Francisco the TJPA TJPA Design The Development Department. Planning or Commission Planning area. the for standards performance and controls new the into findings relevant any incorporate will Department The spaces. open public protected on shadow of quality and and creation the on like, diffusion, diffraction, the distance; and materials; building and source sizes, floorplate orientation, building timing; siting, building reflectance; and duration shadow like issues technical current the evaluate however, will, procedures for Department determining shadow Planning impacts to The see if they might be Francisco. refined. San It will of also investigate voters the by initiative by passed legislation shadow K Proposition the to changes seeking of intention no has In developing urban form policies and controls for the Transbay District, the Planning Department This preliminaryanalysisdidnotincludearobustexistingshadowfan. year. the of times certain at time of periods short for Square, Portsmouth and Square, Mary’s St. Transbay Tower site have the potential to cast shadows on public parks, including Union Square, the for proposed heights building greater the that suggested that analysis shadow preliminary a for responsibility no have will for It responsible only. Center Transit be the environmental reviewordiscretionarygovernmentalapprovalsfortheTransitCenter. of will design the Competition for responsible Development be will Team and The Tower. Transit Design the for approvals discretionary all the securing and review environmental in selected Team The use permitfortheTowerprojectisappealedtoBoardofSupervisors. other or permit use conditional a or review environmental to regard with decision Commission’s Roos District, the Board of Supervisors will not review the Transit Tower project unless the Planning Mello- a and rezoning District Transbay the establishing ordinances approve must Supervisors of approval of the Tower project from the San Francisco City Planning Commission. While the Board In addition to environmental review, the Transit Tower project will be required to obtain discretionary Tower project. 6/29/07 3 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS 7 Tee a be etnie omnt otec truh h Tasa Tria Improvement Terminal Transbay the through outreach community extensive been has There A7: 1: Areddashedlineontheattachedplanmarkspropertyline.Thebelowgroundtrainstation A11: WhereisthesouthwestpropertylineofTransbayprojectsite? Q11: DISTRIBUTED 4/16/07 ThecorrectTable3.5isattached. A10: Space Lease 3.5 ‘Table that Constraints, and Requirements Design 2: Volume in that appears It Q10: AutoCAD with (CD 6 Volume Documents Scope the in included were drawings survey site The A9: Couldwegetamoredetailedtopographicdrawingshowingallgradesandburiedutilities? Q9: 6, April than later no Teams the to distributed be will and development under is template The the for template a providing A8: be would TJPA that suggested was it meeting 1 March the In Q8: Reference Drawing:A/103Volume6,ScopeDefinitionReport SW PROPERTYBOUNDARYLINE TRANSBAY PROPERTYBOUNDARYCLARIFICATION•Q11 Representatives of the San Francisco Redevelopment Agency, Planning Department, and TJPA and Department, Planning Agency, Redevelopment Francisco San the of Representatives life the team. selected the with outreach community be throughout to continue will There date. to Program the and of process, Environmental work, Development for Design the study, Plan below groundeasementfortheDTXtraintunnel. a to subject be will 3721047, Parcel Assessor’s is and Natoma 90 addressed is which project, the of corner southwest the at parcel private small The project. Transbay the of part a not are that properties private adjoins line property southwestern The Street. Natoma and Street Minna both for right-of-ways the into lines property the beyond extends Building Center Transit the of portion Space Program Facilities Support Central 3.4 ‘Table of repeat Requirements.’ PleaseprovidecurrentTable3.5. a is Requirements’ Program is Area, Center Transit the attached. in utilities existing all of drawings containing Util.zip, TC_All C3.01 file the Also, available. data survey electronic the all contains 102 & C101 No. Drawings drawings). 2007. development proposal.Isthistemplateavailable? will beinattendanceattheMid-courseReviewstoansweryourquestions. 90 NatomaStreet North Minna Street Natoma Street 6/29/07 4 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS A12b: Yes, transit center building site is zoned as a ‘P’ district; however, the tower site will be rezoned be will site tower the however, district; ‘P’ a as zoned is site building center transit Yes, A12b: Q12b: Isthesitedesignateda‘P’district? terminal the for use land ‘P’ the in limits parking permitted for requirement definitive a there Is Q12a: Transbay the for zoning use land ‘P’ the and parking regarding below questions three of Consists Q12: 1: No. Caltrans Parcel T, which includes the central portion of the Transbay Terminal and the plaza A15: Is there a parcel Q15: map that shows the legal boundaries and dimensions of the two sites (development Tower Transit the between line” “match projects’ the that indicates Report Definition Scope The A14: Istherea legal propertylinebetweentheterminalsiteandtowersite? Q14: The allocation of costs to build and maintain the reciprocal easement areas in the Transit Center A13: an have will Terminal the where areas of costs development allocating for anticipated is What Q13: DISTRIBUTED 5/3/07 IntheC-3districts(towhichtowersitewillberezoned) the followingapplies: the because but districts, C-3 the in use any for requirements parking minimum no are There A12c: joint & site terminal the for permitted office) hotel, (housing, use by ratios parking the are What Q12c: in apply Code Planning Francisco San the of 151 Section of requirements parking same the No, A12a: project site. area between theTerminalandMission Street, iscurrentlyasingle parcel. parcel andtransitcenter)? Center andtheTowerprior tothetransferofTowersiteTenant/Buyer. of North 2.5’ be will site Center Transit column line A. Caltrans Parcel T will be subdivided the to create a property line between the Transit and site Tower the between line property the that assume should Teams Competition, the of purposes For A701). drawing to (refer building Center the precise location of which will probably be determined during schematic design A, of the line Transit column of north distance a at located be to is building Center Transit Transbay the and Transbay TransitCenterProgram. pro to Team each to up is It Proposal. Team’s each of part as presented be should and areas these for design Team’s the on depends TJPA the and Tenant/Buyer the between as Tower and of gridlineA,isthataTerminalcost? on how to treat these costs. For example, if the main direction clear gathering a have area Teams the for that the sure make Terminal to is crossed intent The north Site? Tower the over easement parking downtown major stand-alone a considered be will limits these beyond parking Any 4. Conditional with and right, by permitted is units four per space 1 to up uses, residential For office,retail,hotel)of7%theGrossFloor Areaofsuchuses. 3. Thereisafirmmaximumparkingallowancefornon-residentialuses(e.g. 2. Therearenominimumparkingrequirementsforanyuse. 1. there arenorequirementsforpublictransportationfacilities. terminal itself will remain ‘P’, it technically would have minimum parking requirements. However, development program? to C-3-O(SD). P districts. site? both in terms of net present value and in providing capital to the TJPA in the initial years of the of years initial the in TJPA the to capital providing in and value present net of terms in both TJPA, the to proposal business attractive an in result will that arrangement sharing cost a pose garage andwouldrequirePlanningCommissionapprovalassuch. bedroom orsmallerandupto1spaceperunitforunitsthatare2bedroomslarger. one are that units for unit per spaces .75 to up Commission Planning the from approval Use - 6/29/07 5 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS Q17b: Are there any requirements for setbacks from the property line or streets for the Tower at base/ at Tower the for streets or line property the from setbacks for Q17b: requirements any there Are A17a: No,thePlanningCodedoesnotrequireanysetbacksforTransit Center. Q17a: Are thereanyrequirementsforsetbacksfromtheproperty lineorstreetsfortheTransitCenter? Twobuildings. A16: WilltheCityconsiderthistobeonebuildingortwo? Q16: 2: Vol. 2, Section 2.1.5 of the Scope Definition Report, Page 19, describes the A20: use of the Elevated Bus The Scope Documents say that Greyhound “may” operate Q20: on the elevated bus level during Phase for requirements operational and technical minimum the contains Report Definition Scope The A19: WhatflexibilitydoRespondentshaveindepartingfromtheScope DefinitionReport? Q19: The fees for affordable housing are set forth in Planning Code section 313.6. The Mayor’s Office of the of development to applicable fees impact City’s the lists 8, Page Sheet, Term Model The A18: WhattypeandamountofdevelopmentfeeswilltherebefortheTower Property? Q18: Departments Planning the of part as change may requirements these that noted be should It adjacent the of center from setback 15’ a requires Code Planning Existing Level: Mid/upper 103’ i.e. height, wall street the below setbacks any require not A17b: do Codes Planning Existing Base: hour bus operations by the bus transit agencies.” For the purpose of the Competition, assume that Greyhoundwilloperate ontheelevatedbuslevel. Competition, the of purpose the For agencies.” transit bus the by operations bus hour to the west end of the train mezzanine, freeing space to allow for growth in the number of peak relocate will operations bus intercity the 2, Phase In level. bus elevated the on space share also Level, and states: “During Phase 1 operations, Greyhound and other intercity bus operations may 1. CommentsbyD.GillespieindicatedthatGreyhound “will”operatethere.Pleaseclarify. Mid-Course Reviewprocesses. require minimum the meet must Center Transit the for design the provided, configurations and TJPA expects the creative process to result in some the departure from While the sample layouts, locations, reference. for provided are and requirements minimum such meet Report Definition the Transit Center and bus ramps. The layouts, locations, and configurations set forth in the Scope square footofnewofficeorhoteldevelopment. per $1.00 at fixed is 314.4 section Code Planning under fee Childcare The development. office The Downtown Park fee under Planning Code section 139 is fixed at $2.00 per square foot of new law. current under option an not is fee a of payment onsite; 15% at fixed is 249.28 section Code forth in Administrative Code section 38.4. The requirement for inclusionary housing under Planning Housing can provide information as to the current adjusted fee. The fees for public transit are set http://www.municode.com/Resources/ClientCode_List.asp?cn=San%20Francisco&sid=5&cid=4201 requirements oftheCity’simpactfeeordinancescanbeaccessedonwebsiteat: de and development, of feet square new on based formula by imposed are fees The Tower. pending TransitDistrictPlanforbuildingsofthenewtallerheights. tallest buildingheightlimitcurrentlyineffectSanFranciscoof550’. the at setback 35’ to linearly increasing ground, above 103’ i.e. height, wall street the at street above ground. mid/upper? it is incumbent upon the Team to raise the issue through either the Question and Answer or the or Answer and Question the either through issue the raise to Team the upon incumbent is it Report, Definition Scope the in contained elements design specific of flexibility the to as doubt any harbors Team a Where construction. of phasing the and operation transit to relating ments pend on the type of space added; e.g., residential, office, hotel, or retail. The formulas and other - - 6/29/07 6 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS 2: The Tower may be placed anywhere on the Tower site. Vol. 2, section 2.2 of the Scope Definition A21: Is the Tower placement on the Tower site required to be Q21: on the western half bordering Mission and 2: Please use the ridership numbers provided in the “Transbay Transit Center Program Scope Defini A24: Arenewprojectedridershipstudiesavailable? Q24: Please be advised that these are the dynamic vehicular envelopes and not the established struc track and clearances lateral the used, be to are tracks curved If tracks. tangent for are These envelope, dynamic train the showing format PDF and CAD both in diagrams two are Attached A23: Whatisthedynamicclearanceenvelopeoftrains? Q23: during established be will width Required platforms. rail the for width minimum set no is There A22: Whatistherequiredminimumwidthofrailplatforms? Q22: originally proposed by the Metropolitan Transportation Commission Transbay Terminal Improve Terminal Transbay Commission Transportation Metropolitan the by proposed originally Report, Pages 22-23, indicates that the TJPA has studied two locations: The east half of the site as First streets? tion. train equipmentselectedinthefuture. spacing shallbeincreasedby2inchesperdegreeof curvature. rule FRA anticipated and stock rolling selected on based adjustment height Platform 5. Adjustments basedonanticipatedFRArulechanges the on Commission 4. Utilities Public California the with confirmation on and based Caltrain Adjustments by stock rolling of selection 3. final on based are envelopes clearance Final 2. Vehiclein-orout-swingasaresultofhorizontalcurves 1. diagram donotinclude: assumed in the current preliminary planning for the Transit Center Train Station facilities. The com wide. feet 32 approximately of sections tangent the on platforms showing drawings Definition Scope the with date, to followed been has circulation passenger facilitate permanent to platform the on structure nearest the to edge platform the from clearance 8-foot an and sections platform tangent for width minimum feet 30 of criterion planning A volumes. passenger on based design defined underPropositionK.”(SeePage22). tion Report, Volume Two: Design Requirements and Constraints” for the purpose of the Competi the on based established be will heights platform final the although 6, Vol. in Drawings Report Definition Scope the on shown as platforms) (high rail of top the than higher inches 6 ft. 3 be to assumed are platforms passenger the that note please addition, In clearance. for gauge tural be used with caution. Users should be should aware that and the vehicle clearance only envelopes shown engineering in the conceptual for developed was (VC0247) diagram vehicle posite Street; and the potential impact of shadows from the Tower being cast onto public open space lobby hotel separate and porte-cochere; a vehicular to access to access parking and vehicular service Tower; functions for and the Center Tower from Transit Fremont the both for lobby civic combined a of connection seamless Street; Mission and Streets Fremont and First of corners both the from lobby civic the to access pedestrian of ease Street; Mission on Center Transit the of level of the Transit Center. Important issues to be addressed include clear visibility and the identity concourse and level ground the at desired connection seamless the in results Center Transit the with Tower the of integration the that provided site, Tower Transit the on anywhere Tower the of states: “The TJPA will, however, allow the design and development teams to propose the location however, Report, Definition Scope The Mission. and First of corner the at site the on of half west the located tower the show drawings Report Definition Scope the Accordingly, site. the of half two locations, the TJPA concurs with the Redevelopment Agency-proposed location on the west ment Plan Study and the west half of the site as proposed by the Redevelopment Agency. Of the changes clearance requirementsspecifiedinGO26 California HighSpeedRail - - - - - 6/29/07 7 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS 2: The concourse is intended to serve three primary functions. First, it will provide a pedestrian circu A26: Whatarethefunctionalobjectivesofconcourse? Q26: Please use the AC Transit Program Space Requirements provided in the “Transbay Transit Center A25: WhataretherequirementsofACTransit? Q25: Q31: Are members of D/D Teams allowed to participate in Citizens Advisory Committees (CAC) that (CAC) Committees Advisory Citizens in participate to allowed Teams D/D of members Are Q31: A Jury will consider the written submission and oral presentation of each Respondent and report (“TJPA”) Authority Powers Joint Transbay “The 2: Page on Manual Competition the in stated As A30: Whatisthespecificpurposeofcompetition? Q30: Report, Definition Scope the of 2 Volume in Summary, Space Program Architectural 3.2 Table A28: Whataretheretailexpectationsforproject? Q28: All mandatory requirements for Stage II D/D proposal submittal as A27: listed in the Competition Manu can we items there are or 10th July on due be to need materials presentation competition all Do Q27: petition. Program Scope Definition Report, Volume Two: Design Requirements for the purpose of the Com relate totheprojectarea? design oftheTransitCenter. its recommendation to the TJPA Board of Directors. The TJPA Board will consider the Jury’s recom the StateofCalifornia.” D/D Team that will create a unique, world class Transit Center and Tower whose aesthetic, func a seeks TJPA The Center. Transit the to adjacent Tower mixed-use a develop and design to and California, Francisco, San downtown in TJPA the by developed be to Center Transit a design to Team (“D/D”) Development and Design a select to Competition international an conducting is a propose to however, flexibility, different locationandlayout,providedthatthethreerequirementsaremet. the has Team D/D Each 3.2. Table in requested space lease retail of amount the propose to requested is Team D/D each Competition, the of purpose the gsf 2,000 of (shown on plans at station ground level at column intersection storage 2-3 and C-D); for bicycle a total of 60,000 gsf. 3) For and, gsf; 24,000 of space gsf; lease 34,000 retail of level space concourse 2) lease retail level ground 1) requirements: three indicates 121, of 28 Page model maybeincludedinyourJuly10thsubmittal. complete aftertheJuly10thdeadline? site, providedthattherequiredprogramspacesareprovided. Team for a Design and Development Option Agreement for the design and development of development the for Team selected the of and Designer Lead the with Agreement Design a and Tower design Transit the the for Agreement Option Development and Design a selected for a Team with negotiations exclusive in engage to Staff TJPA authorize may and mendation and Area, Bay the Francisco, San for transit rail and bus of focus the and Area Redevelopment Transbay the of centerpiece the as position their of worthy are excellence technical and tional, be submitted but this is not to be delivered until your presentation to the Jury. Photographs of the al are to be submitted by the July 10th deadline. TJPA has also requested that a physical model the on elsewhere or concourse the on either accommodated be can space other and office TJPA of function third The accommodated. are functions circulation passenger second and first space program commercial flexible the the that provided concourse, the of layout in flexibility have teams D/D The plans. the on shown for and space, support building back-of-house and offices TJPA for location a provides concourse the Third, streets. Fremont and First over crossing pedestrian safe a provides concourse the Second, level. bus elevated the of area waiting the in congestion reduce to desired is This above. level bus elevated the to access for point desired the to length its along circulate and concourse, the to up go entries, level ground the of any at building the enter may pedestrians that so Center Transit the of length the along corridor lation - - - - - 6/29/07 8 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS 3: To avoid the appearance of or an actual conflict of interest, a member of a D/D Team shall not A31: The City is concerned not just with minimizing the width and bulk of the Tower as it projects above It is anticipated that the City will rezone the Transit Tower site as part of the Planning Department’s Minimizing the bulk of the Transit Tower is of utmost concern to the City (i.e. Planning Department A34: WhatareconcernsregardingBulk? Q34: As previously stated, the City Planning Department has no intention at this time of bringing to the A33: WhataboutPropM? Q33: As previously stated in the Stage II Questions and Answers, the City Planning Department has no A32: Tower Transit the impact will it how and K Prop regarding clarification further provide Please Q32: not attempt to influence the communications of the CAC with any of these agencies concerning Transit CenterProgram.MembersofTeamsmayattendmeetingsCACs,however,butshould Francisco, AC Transit, or the Peninsula Corridor Joint Powers Board on any aspect of the Transbay or that advises the TJPA, the San Francisco Redevelopment Agency, the City advise and County of San to formed was that (CAC) Committee Advisory Citizens any of member a as serve also they winthecompetition). sun the impacts levels lower and mid Tower’s the of bulk the way the in but skyline, existing the of approximately100’. devel be not will controls These Hill. Rincon for adopted was as such bulk, in reductions overall examine reducing the need for graduated setbacks (as in the “S” bulk controls) in exchange for also will Department The possible. as little the as modified and upward extended be will controls “S” Plan, District Transbay the Under feasibility. economic and structural maintaining still while possible dimensions slender most the to towers restrict to seek will controls bulk new The heights. pending Transit District Plan, including new bulk controls appropriate for buildings of the new taller buildings tallerthan550’asnoarecurrentlypermittedabovethisheight. also building horizontal and diagonal dimensions. The Planning Code includes no bulk controls for limits for the lower and upper portions of the tower; the controls limit not only floor plate size, but diminishing and Street), Mission of width the times 1.25 or 103’, (i.e. height wall street the below Bulk in District described “S” (see are Planning limitations Code bulk Section corresponding 270(d)). its The 550’; current is bulk Francisco controls San contain in no currently limitations limit height building tallest The skyline. the on landmark a be will which Tower, the of reception political and and Redevelopment Agency) in regards both to the City’s form as well as future potential public 320-324. voters a revision of Proposition M, the Annual Office Limit, as regulated in Planning Code Section development goalswhileminimizingshadowimpacts. revi any bringing or 295) Section Code (Planning K Prop of revision recommending of intention Proposal. the Program. bulky (in floor plate and/or dimension) are unlikely to gain final approval (regardless of whether of (regardless approval final gain to unlikely are dimension) and/or plate floor (in bulky excessively are that designs Tower surroundings. immediate the of pattern built and views light, concerns and strive to minimize the bulk of the building, particularly above the street wall height oped in time to advise teams in the Competition. However, the Teams must be conscious of these and design urban achieve to ways consider and Plaza), Herman Park/Justin Embarcadero and on impacts shadow any Recreation of and Parks conscious open be spaces (including should Union Teams Square, St rare. Mary’s Square, is Portsmouth this Square, although benefit, public of joint a through hearing, have the ability to raise the Commissions, tolerances for any particular open space based The on findings Commissions. Parks and Recreation and Planning the of tion resolu joint a by 1989 in policies as adopted were but themselves, ordinance K Prop the or 295 established shadow tolerances for downtown open space are specifically not current included in the the text that of Section Note Teams. the advise to time in developed be not will proposals the current methods of analyzing shadow and determine if they might be refined. Any refinement sions to the voters. In its Transit Center District Plan studies, the Planning Department will examine - - - - 6/29/07 9 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS 3: Rental car fleet parking facilities are not included in A35: the Scope Definition Report as a requirement. HowisRentalCarParkingaccommodatedintheScopeDefinitionReport? Q35: A38: Section 2.2 of Volume 2 of the Scope Definition Report provides planning background as to the to as background planning provides Report Definition Scope the of 2 Volume of 2.2 Section A38: Isatower of1200’acceptabletotheCitySanFrancisco? Q38: DISTRIBUTED 5/15/07 A Proposal should demonstrate that the Team will cooperate with A37: the TJPA on construction of the that but Center, Transit the design will Team selected the that provides Manual Competition The Q37: including compliance, code building and ADA for designed be will building Center Transit The A36: WhataretheADArequirementsfortactilestripsonfloorof train platforms? Q36: parking accessory as Code Planning the in allowed limits the beyond and above parking Any oee “ae r etl f e o ue atmbls we cnutd niey ihn n en an within entirely conducted when automobiles, used or new of rental or “sale However trols. the discretionary review of the City Planning Commission under the Transbay District zoning con through and zoning, District Transbay new this by controlled be will tower the of height final The of new buildings to be constructed to heights ranging from 850 feet to approximately 1,200 feet. Transbay Transit Center, including the Tower site, with the objective of allowing a limited number to establish new planning controls for building height and bulk requirements in the vicinity of the effort planning a undertaking be will Planning City feet. San 1,000 of excess in height in a at Francisco, building tallest the be should tower the that Group Working Interagency Francisco San of County and City the of recommendation the including Tower, Transit the of height potential the constructionofTransitCenteronTJPA’sbehalf. would be no competitive advantage to proposing to serve as the developer for the Transit Cen there Center, Transit and Tower the of construction efficient enable to contractors its and TJPA schedule. Beyond demonstrating the capacity and commitment to work cooperatively with the Tower and the Transit Center to insure that the Transit Center is completed within budget and on also developer build theTransitCenterunderacontractwithTJPA? the that proposal a consider Jury the Will Center. Transit the build will TJPA the use of“tactileflooringstrips”attheedgealltrainplatforms. high amountofstudyandscrutiny. Sections 223(m)-(p). The Planning Code Code and General Plan Planning strongly discourage long-term on or com based merits its on Commission Planning the by evaluated be and will considered Center, Transit the serves it whether of regardless uses), such of Area Floor Gross of (7% required pricingofsuchparking. a proposal from the selected Team that the Team build the Transit Center or manage aspects of for the Transit Tower and the Design Agreement for the Transit Center. The TJPA will not entertain two the of construction structures the will be during determined in TJPA negotiations for the the Design and with Development Option coordinating Agreement in Team the of role precise the ter. The Jury will not consider any such proposal. If a Team is selected for exclusive negotiations, a without Center Transit the with connected or in parking commuter or long-term for proposal a of approval recommend to unlikely is Department Planning the and C-3, the in parking muter and arrangement the as well as parking of amount -- controls relevant all includes This stated. passengers, will be limited and regulated by the parking controls of the C-3 district, as previously train for parking long-term including site, Tower Transit the on parking other Any vehicles. senger itself. Parking for rental car vehicles may not be used for general private or public parking of pas they are not regulated as parking garages. A rental as desk facility, car need rental not a in be stored vehicles located of in number the the on Transit restrictions no Tower are There 223(m)-(p)). (Sections vehicles passenger for facilities parking from distinguished separately are and 223(a) closed building” is a permitted use in all C-3 zoning districts according to Planning Code Section - - - - - 6/29/07 10 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS A39: Section 4.11 of Volume 2 of the Scope Definition Report states that the design of both the Tran the both of design the that states Report Definition Scope the of 2 Volume of 4.11 Section A39: WillthetowerstructuraldesigncriteriabePerformanceBasedDesign? Q39: A42: This acknowledgement shall be part of the Set Terms of the Team’s Proposal as required by the by required as Proposal Team’s the of Terms Set the of part be shall acknowledgement This Manual Competition A42: the in requested acknowledgement the of form required the is What Q42: DISTRIBUTED 6/1/07 concourse and level ground the on space public the of portion the to service mechanical The A43: North space public center transit (the space public shared the in system mechanical the Will Q43: See response to Question 13 distributed 5/3/07. See also response to Question 43 A42: below. All public Is the developer responsible for building and maintaining the transit center public space North of Q42: to use will jury the which submittals, required the on be should presentation your of focus The A41: physical and boards 10 the beyond material supplemental present to allowed Teams D/D Are Q41: See response to Questions 28 and 37 distributed 5/3/07. The Lead Designer of each Team will be A40: retail all manage and develop to strategy retail unified a propose Developer Tower the Can Q40: Model TermSheet“Special Tax”(Page8)and“Taxincrementfinancing” 9). referenced insection4.3.3.7? mechanical rational and efficient an propose system toservethisarea. to flexibility the the has by team maintained and Each operated project. constructed, Tower designed, be should A line grid of north level space beservedbyathird,independentmechanical system? this should Or system? tower or systems mechanical center transit the of part be A) Line Grid of the TJPA,oracombinationofabove. con be will Tower Transit and Center Transit that between line property the of north space Grid LineAoristhissharedbutadistinctlydividedeasement? present to however, additional materials. latitude, the have You criteria. the with complied have you if determine model duringthejurypresentation? space intheTransitCenteralongwithretailTower. Ac Center. Transit the of components all manage and develop will TJPA The TJPA. the with agreement separate a in component, retail the including Center, Transit the design to required space ontheTowerandTransitCentersites? Center andTower. developer and the TJPA, or terms of the development agreement between the developer and developer the between agreement development the of terms or TJPA, the and developer of approval of the Tower by the Planning Commission, reciprocal easements between the Tower conditions by governed be will line property the of north space public this of maintenance and structed, owned, and maintained by the owner of the Tower. The design, construction, operation retail the manage Tenant/Buyer the that proposal a consider may TJPA the Agreement, Option retail in the Transit Center. The Jury will not consider any such proposal. During negotiation of the cordingly, there would be no competitive advantage to proposing to develop and manage the Transit the both for approach design performance-based a allow, will Francisco San of City the that anticipated reasonably be can it and supports, TJPA The design. performance-based ports sup IBC The (IBC). Code Building International the on based is which Code, Building California of City The design. of time San Francisco is currently the developing amendments to the code in order to comply with at the new effect in code building City the by governed be buildings’ will design The approach. design performance-based a on based be will Tower and Center sit - - - - 6/29/07 11 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS A43: Yes, firms may reuse the existing forms submitted during Stage I (Competition Manual Section Manual (Competition I Stage during submitted forms existing the reuse may firms Yes, A43: I Stage in provided already were that 4.3.4, section in required forms, existing the re-use we Can Q43: A47: The concept for the Transit Center assumes that all trains entering the train tunnel and serving and tunnel train the entering trains all that assumes Center Transit the for concept The A47: Whatisthe assumptionregardinguseofdieseltrainsintheTransitCenterTrainStation? Q47: Center Transit other and offices TJPA all provide Competition, D/D the of purpose the for No, A46: MaytheTJPA officesbeprovidedwithintheTower? Q46: http://www.samtrans.org/schedules.html SamTrans: SamTrans will terminate most of its downtown buses traveling on Mission St. at the Transit http://goldengatetransit.org/schedules/pages/Bus-Schedules.php Mission on traveling buses service day all its for Plaza Bus the use will GGT Transit: Gate Golden Plaza Bus the use will minutes) (6 41-Union and minutes) (4 1-California lines MUNI addition In 6-Parnassus:10minutes • 5-Fulton:5minutes • 38L(orBRT):6minutes • 38-Geary:3minutes • MUNI: The MUNI lines and current peak headways that will be using the route stopping on Mission sum a is following The available. not are lines bus individual on volumes passenger Projected A45: WhatBusLineswillusethefuturePlazaatTransitCenter? Q45: To meet the TJPA’s schedule for the start of construction of the Transit Center, the agreement for A44: between Center Transit the of design the for agreement an negotiating for schedule the is What Q44: For example, the Bidders/Proposers Information Request Form must be updated to reflect the reflect to updated be must Form Request Information Bidders/Proposers the example, For 4.3.4) but must submit new forms for any revised or new information such as new team members. of thecompetition? Definition Report assumes electric powered trains and is appropriate for both electric and /or and dual modelocomotives. electric both for appropriate is and trains powered electric assumes Report Definition Scope the of Two Volume of 4.18 Table in presented estimate cost preliminary The ). Ventilation requirements need to allow for the presence of diesel laden locomotives (dual mode power. electric under operating For be will trains trains. all that assume powered Competition, D/D the dual-mode of purposes operate to capability the preserve to required is Competition D/D the for developed design Center Transit The power. electric under be will Station Train the program requirementswithintheTransitCenterbuilding. SamTrans schedulemaybefoundatthefollowinglink: Golden Gate Transit; buses would stage at the Bus Plaza, and then board outbound passengers. and Muni with shared stop bus curb St. Mission the on off dropped be would Passengers Center. Plaza schedule maybefoundatthefollowinglink: Bus the use may Transit’s Transit Gate Golden lines. Gate commute period peak Golden during northbound departures addition, afternoon for In lines. 80 and 70 the primarily Street, they willcomestraightdownBealeStreettotheBusPlaza. between BealeandFremontstreets,butwon’tusetheroutingthatstopsonMissionStreet,since between BealeandFremontstreetsforpassengerpickuparethefollowing: Plaza Bus the to proceeding then and unloading, passenger for Center Transit the of front in St. streets. before March31,2008. or on signed be should Designer Lead the and TJPA the between Center Transit the of design the TJPAandLeadDesigner? current make-upofateamorfirmcomposition. and Fremont streets, and the Bus Plaza at the new Transit Center between Fremont and Beale and Fremont between Center Transit new the at Plaza Bus the and streets, Fremont and First between Street Mission along curbside on stop bus the use to intended service bus of mary - 6/29/07 12 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS h oiia cnet ln o te rni Cne peae b te erpltn Transportation Metropolitan the by prepared Center Transit the for plan concept original The en partially plaza, open an provides Report Definition Scope the within concept planning The A48: Transit the and Tower the between Connection” “Seamless the for requirements the are What Q48: A51: Any permanent extension of a building below grade and up to ten feet above grade into the into grade above feet ten to up and grade below building a of extension permanent Any A51: without right-of-way public adjacent the into project Structure Center Transit the can far How Q51: The TJPA expects that while the emphasis of the Teams’ presentations will be on the architecture A50: cost or Tower the for proposals financial their present teams the that recommend TJPA the Does Q50: other or proposals any release not will TJPA the 6, August on meeting Board the of advance In A49: August on Board TJPA the to presentations the at public made be will information financial What Q49: of issues the of discussion additional for 5/03/07 distributed 21 Answer and 21 Question also See the as Plan Redevelopment the followed TJPA the by prepared Report Definition Scope The the on Tower the placing Plaza, and Tower the of location the reverse to proposed plan That Transbay the for plan a developed subsequently Agency Redevelopment Francisco San The the Tower on the east half of the site. See the “Transbay Terminal Improvement Plan” available Plan” Improvement Terminal “Transbay the See site. the of half east the on Tower the of placement the and site, Tower the of half west the on plaza open an proposed Commission closed/sheltered plaza,orapartiallyenclosed/naturallyventilatedciviclobby. Center lobbiesatthegroundlevel? with varying maximum widths described in Section 136. In the C-3 districts, decorative features decorative districts, C-3 the In 136. Section in described widths maximum varying with line property the beyond feet (3) three of projection maximum a to limited are balconies and windows bay general, In courses). belt cornices, (e.g. building a of envelope usable the expand not do which elements decorative and balconies, windows, bay for allowances includes which projections, limitations on building projections into streets and alleys are described in Section Planning 136, the Regarding permit. encroachment Code, an aside from require signage (Article 6), not awnings, canopies would and marquees and (Section 136.1) and Plan, similar General and Department and Department of Building Inspection, subject to the Planning and Building Codes Planning the by review for matter a strictly is grade above feet 10 above right-of-way the into Bureau of Street Use and Mapping. Any building projection that extends beyond the property line Works Public of Department the from permit Encroachment Major a requires right-of-way public grade trainboxaswelltheabove-gradebusstructure? requiring an encroachment permit? Would encroachment permits be required for both the below- Property andcostestimatesfortheTransitCenter. Prop Tower the of lease purchase/ground the for proposal financial its of summary a include to and functionality of the proposed designs for the Transit Center and Tower, a Team may choose estimates fortheTransitCentertoBoardonAugust6? documents submittedbytheTeamsinDesignDevelopmentCompetition. 6? and concourselevels. concern related to the combined civic space linking the Tower and Transit Center at the ground each D/D Team. of proposal concept design overall the compliments and users Center Transit the serves provide flexibility for each D/D team to propose a layout for a combined “civic space” that best Volume Six of the Scope Definition Report illustrate an enclosed combined lobby, the intent is to in drawings the While lobby. main Center Transit the and lobby Tower the between connection base, and further developed concept plans for a combined “civic space” providing a seamless and TransitCenterbuilding. a glass-covered partially enclosed public plaza due to its location on the north side of the Tower as proposed was plaza The site. the of half eastern the on plaza the and site the of half western velopment Agencywebsite:http://sfgov.org/site/sfra_page.asp?id=5583#D4D Rede the on available Development,” for “Design report a in described Area, Redevelopment on theMTCwebsite:http://www.mtc.ca.gov/library/transbay/index.htm prepared to answer questions from the Board regarding their financial proposals for the Tower the for proposals financial their regarding Board the from questions answer to prepared be nevertheless should Teams presentation. its in Center Transit the for estimate cost its and erty - - - 6/29/07 13 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS The preliminary estimate is based on the scope of work defined in the Scope Definition Report, Definition Scope the in defined work of scope the on based is estimate preliminary The construction of estimate preliminary TJPA the underlying assumptions the clarifies following The constructed be to entirety, its in presented as Building, Center Transit the for possible be must It The cost analysis to be submitted by the Design Development Teams will be provided separately of estimate preliminary TJPA the to concept design proposed the comparing analysis cost “A Center Transit the that require 4, subparagraph 4.3.2, paragraph Regulations, Competition The “The Transit Center building and the Transit Tower are separate projects. The Transit Center building Tower and Building Center Transit of discussion under Manual Competition the of 6 page On A53: the of scope the to regards in construction of estimate preliminary TJPA the clarify you Can Q53: DISTRIBUTED 6/05/07 No. The Teams are not required to enter into labor agreements to respond to the RFP. All agree A52: AretheTeamsrequiredtoenterintolaboragreementsaspartoftheirProposals? Q52: granting of a Variance from the Planning Code by the Zoning Administrator, based on an as an on based Administrator, Zoning the by Code Planning the from Variance a of granting height of four (4) feet. Any projections beyond these limitations could be approved through the maximum a with feet (2) two project may level roof below features decorative and feet, (6) six of height maximum a with right-of-way a into feet (4) four project to permitted are level roof at be atPre-Schematic Design(Concept) level ofcompletion. at be to considered to considered is are drawings Report Definition Scope the and, prices; completion; of level Programming unit 2007 January assuming prepared the within was drawings estimate the The on report. illustrated and report the in established standards quality the and cost presentedinTable4.18 ofVolumeTwotheScopeDefinitionReport. eral ContractorsGeneralConditions,Overhead&Profit isnotincludedintheTotalDirectCost. at the in defined as $2007 in Cost” (construction) Direct “Total the for service into placed and for PhasesI&II. must fallwithintheTJPApreliminaryestimate.” the of Two Volume of design Center Transit the of cost construction direct of analysis cost The Report. Definition Scope 4.18 Section in established as dollars current in cost construction direct Proposal include: Definition Report,VolumeTwo:DesignRequirementsandConstraints.” construction will be funded by the TJPA. The Competition regulations contained in the Competi Projects ConstructionCoststhefollowingstatementismade: estimate inphaseoneandtwo? was attachedtotheApril12,2007ModelTermSheet. right-of-way abovegradewouldbeweighedagainsttheseprinciplesandpolicies. elements at this stage of project development. The allowance in the Estimate Total for the Gen the for Total Estimate the in allowance The development. project of stage this at elements Team with TJPA approval during the design phase of the project to cover reasonably unforeseen Design A/E the to available be will Contingencies Design The Summary. Estimate Detail tached Scope Program Center Transit Transbay the of 4.18 Table in contained dollars, current in construction cost, direct of estimate preliminary the is building Center Transit the of construction for For purposes of Stage II of the Design and Development Competition, the TJPA fixed budget limit building. Center Transit the of construction for limit budget fixed TJPA the exceed not does that analysis cost a II Stage in submit Team Development and Design each that require Manual tion 011 Policy Board TJPA of copy A agreements. check card regarding 011, No. Policy Board TJPA ever, shall require the hotel or restaurant operator to apply the TJPA Labor Representation Policy, how Tower, Transit the in tenants restaurant and hotel its and Tenant/Buyer the between ments public the into extend to proposal a Variance, a of granting the considering In space. street on impinges that development discourages Element) Design Urban the (particularly Plan General the pattern, air city the and surroundings their and to people orient to light serve and buildings, adjacent to provide corridors, view public important are right-of-ways public As policies. Plan sessment of the proposal’s public benefits, necessity, unique conditions or hardship, and General ------6/29/07 14 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS Attached is a Detailed Estimate Summary in UNIFORMAT of the preliminary estimate of construc The Construction Contracting Method is assumed to be publicly competitively bid with more than “Ten provide to construction assuming estimated are spaces lease Commercial and Retail All lower the at covers column with durable, be to assumed are spaces public all for finishes Wall Ceilings for all public spaces are assumed to contain a suspended ceiling system, except in toilets special for allowance an with terrazzo, thin-set be to assumed is spaces public all for Flooring The Transit Center building is assumed to be largely naturally ventilated, with mechanical ventila roof the of 50% that assumes building Center Transit the of roof the of estimate preliminary The capa the preserve to required is Competition D/D the for developed design Center Transit The The preliminary estimate DOES NOT include any cost for systems or equipment related to train op Cost (construction) Direct Total the in included NOT ARE that items following the note Please designphase,ConstructionManagement,Owner’sProfessionalServices ConstructionContingencies,Owner’sContingenciesandother Program 10. ProfessionalFeesincludingA/EDesign, ManagingContractorsservicesduringthe PermitsandFees 9. LandAcquisition 8. HazardousMaterialsRemediation 7. TheconstructioncostoftheBusRamps 6. 5. ElementF20Demolition&AbatementoftheexistingTransbayTerminalBuildingand ElementG40SiteElectricalUtilities 4. 3. ElementG30SiteMechanicalUtilities(relocationofutilitiesinthepublicRightWays ElementEEquipmentandFurnishings 2. 1. tractors’ costs, includingallsubcontractors’ overheadandprofit. subcon all of summation the be will Cost Direct Total The construction. of cost total guaranteed the within construction managing for and Contractors Sub the by construction of coordination three qualified bidders. A General Contractor (or Managing Contractor) will be responsible for all including installationofmechanical heatingandcoolingequipmentwouldbe at tenantcost. seven feetofcolumn. or otherspaceswherehardceilingsarerequiredfor performance. carpet, andforsupportspacestileorcarpetasappropriate. be to assumed are offices TJPA for Flooring locations. selected in systems paving other or stone and supportspaces,enclosedtenantspaces. A703-A706. surface area is glazed, and 50% is solid surfaced. The roof extent is assumed as shown in Drawings trains andisappropriateforbothelectric/ordualmodelocomotives. Project atalaterdate. estimate: Report. ant-ready Shell space” with building services brought to each tenant space. All interior fit-out interior All space. tenant each to brought services building with space” Shell ant-ready offices TJPA enclosed be to assumed are spaces conditioned only The required. as support tion estimate presented in Table 4.18 of Volume Two of cost the Scope Definition Report assumes electric powered preliminary The locomotives). mode (dual locomotives laden diesel of presence the for allow to need requirements Ventilation power. electric under operating be will trains all that assume Competition, D/D the of purposes For trains. powered dual-mode operate to bility Extension Downtown the by incurred be will items such of cost The systems. operational other or systems communications equipment, signal power, traction track, way, track including erations, Definition Scope the in shown as system building each to related are costs construction building understand how the TJPA preliminary estimate has been developed, and how the TJPA assumes to Team D/D each assist to provided is information this rather, but Report, Definition Scope the with consistent not is estimate preliminary TJPA the that demonstrate to attempting information construction of allocation cost the within each cost element in Table regarding 4.18. The D/D Teams ARE specificity NOT to present any argument or of level additional an provides It cost. tion Costs BusRamps tofacilitateconstructionofthebuilding) ------6/29/07 15 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS 5: eadn te ups o te 5’ cee rpsl Prgah 3 f h Mdl em Sheet Term Model the of #3 Paragraph proposal; scheme 550’ the of purpose the Regarding Q54: DISTRIBUTED 6/13/07 5: On-site inclusionary housing must be comparable to market units. A57: Planning Code Section 315.4(c) the scheme, tower our in residential incorporate to elect we should that emphasized been has It Q57: for terms financial and designs lease ground and purchase the present should Teams The No. A56: Due to the requirement to submit proposals for both land purchase and ground lease for both the Q56: Prop Tower the of lease ground and purchase a both propose Teams the that requirement The A55: and purchase land a both on based proposals development our submit to asked been have We Q55: The TJPA does not intend to dictate to the A54: Teams particular uses or floor areas for either the “base accurate base line would be established if all three proposers were basing their proposals on the in fact to establish a baseline cost utilizing this as-allowed scheme as the basis, a tighter and more Forma is to maximize “apples to Pro apples” comparisons and of Sheet respondents’ Term proposals. Model If the the of purpose purpose is primary a that states 2007, 12, April dated document unwritten policy that this “comparability” extends to the distribution of units throughout the proj the throughout units of distribution the to extends “comparability” this that policy unwritten an enforced consistently has Department project.” Planning the principal Code, Planning the the in written in not While units rate market to construction of quality overall and appearance exterior bedrooms, of number in comparable be “shall units such that states Housing”) of (“Type document Procedures or Policy the with source ofthislanguage. us provide Please criteria. language code “scattered” any find the to requiring unable are We site. on located being housing the of requirement the to refer Plan Redevelopment the and Code Planning the Both floors. contiguous on be nor together located not and units residential the throughout” “scattered be to required are units of affordable housing component would need to be located “on site” and that the required number ing the“preferreddesigns”). questions from the Jury regarding their “base program” proposals (as well as questions concern the “base progam” proposals to the Jury. The Teams should nevertheless be prepared to answer for terms financial or designs present not should Teams The Jury. the to designs” “preferred the (4 total)tothejury? schemes alternate the for proposals development and/or design the present we that intent your it Is scheme. as-allowed the “design” to required been not have we that understood further is It reflecting the different program uses favored by each of the differing methods of land possession. tower the of design the in differences be likely will there schemes, preferred the and as-allowed Competition Manual§4.3.3(5);TJPABoardofDirectorsmeetingDec.19,2005). reference? this of us advise and discussed, was this meeting which a at and time what at is specifically identify lease) ground vs. (fee proposal dual this product ofconcernsexpressedbyonetheTJPABoardmembersataMeeting.Willyou for requirement the that understanding our is It scheme. preferred the for and scheme, as-allowed 550’, the both for approach lease ground a the understand to Jury the enabling components ofthefinancialoffers. thus format, transparent same the in assumptions present net value and revenues, costs, present to required is Team the each of that sense comparisons the apples” in Proposals to “apples maximize to attempt Templates Forma Pro and Sheet based on realistic assumptions regarding cost, revenue, and market absorption. The Model Term program” or “preferred design” Tower. Rather, it is up to each Team to select a mix of land uses same land-useandprogram.Willyouconsideraninstructiontoallproposersonthisbasis? ect. The inclusionary units shall be integrated throughout the building in a unit type mix that is that mix type unit a in building the throughout integrated be shall units inclusionary The ect. e.g., (see, settings and sources of variety a in TJPA the of constituents other and staff, Board, maximum flexibility to meet these objectives. Teams These objectives the have been allow expressed by to the TJPA is proposals lease ground and purchase develop to Teams the requiring of purpose The Program. the for Property Tower the for value present net maximum the obtain to (4) and sound; economically is that project Tower a produce to (3) loans; federal and bonds of the in construction for initial capital years of obtain the Program; to (2) to use (1) the proceeds from the Tower concerns: Property to TJPA secure repayment longstanding four from arises erty - - - 6/29/07 16 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS Q58: Paragraph 4, page 1 of the “Model Term Sheet and Pro Forma Templates for Disposition of the of Disposition for Templates Forma Pro and Sheet Term “Model the of 1 page 4, Paragraph Q58: DISTRIBUTED 6/22/07 6: h Po om tmlt sae a te edr f ot iaca pgs “ttd n 07 Dollars 2007 in “Stated pages: financial most of header the at states template Forma Pro The Q61: bound not and separately submitted be may Proposal Tower and Proposal Center Transit The A60: 4.2 of the Competition Manual states that each team Q60: is to submit 10 printed copies of the proposal DISTRIBUTED 6/29/07 330 and HRC new submit must Teams 2007. 1, June on distributed 43 Question to response See A59: HRC the just or forms 330 new submit to need we do added been have members team new If Q59: pe (ENA) Agreement Negotiating Exclusive six-month the that indicates Sheet Term Model The A58: Scope definition Report, 2, Appendix Volume C schedule Agreement. indicates Developer in this the row execute 181 to that 2007 the date Developer the Agreement 20, as 2008 September 20, March of as date a established defines date selection the With Tenant/Buyer. the of selection the following period ENA month 6 a be will there that states 2007 12, April dated Tower”, Transit penthouse floors, but must at least be spread throughout the rest of the building. The interior fea in the project. In a high-rise project, inclusionary units need not be located on the uppermost or units desirable least the as designated or way, any in units rate market the from distinguishable be not may units Inclusionary clustered. confined to than the lowest few stories of a building, clustered in rather a part or certain floors of the project units, rate market the of representative really asking us todo? are you what this Is numbers. meaningless be will they levels 2007 to deflated then are amounts dollar these If flows. cash discounted using value land the for solving and returns calculating amount over time and thereby the stabilized year is reached with escalated dollars. We are then – Stabilized Year”. Each element of the cost and expense in the pro forma is escalated by some Requirements Memodated6/21/07. con of table a have to required is each bindings, multiple in are proposals If one. as together that containstwoindividuallytabbedsections-Transit CenterProposalandTowerProposal? and book one separately as bound be to proposals two the want you do or presentation for together bound packaged proposals the want you Do 4.2 but singular. the separately, in bound proposal proposals the of two speaks the only want you that appears it contents 4.3 of on table a Based with tabs. (4.3.3) and Proposal Tower a and tabs and contents of table a with (4.3.2) proposal Center Transit a be will there that state 4.3 in outlined contents The format. 11.5 x 8 in forms fornewTeammembers. forms listedin4.3.4ofthecompetitionmanual? superseded. is tobesignedonJanuary31,2008.Whichofthesecorrect? for inclusionaryhousingareapplicabletotheTransitTower. tents and tabs. The required number of copies of proposals is 14 as listed in the Presentation the in listed as 14 is proposals of copies of number required The tabs. and tents been has Report Definition Scope the of C Exhibit 2, Volume in stated Agreement Developer a of execution the for 2008 31, January of date the Accordingly, 2008. 20, March after occur will Sheet Term a a of execution for selects date six-month Directors the 2007, 20, of September after or Board on Tenant/Buyer TJPA the that Assuming Sheet. Term a of execution the following Sheet Term Model The Agreement Option Development and Disposition a execute will parties the that period. provides further ENA the of commencement the after months six within occur will Sheet Term a of execution for date the that provides further Sheet Term Model The ENA. an of execution parties’ the upon commence will Tenant/Buyer the of selection the following riod standards above the that assume to are Teams Competition, the of purposes For housing. new for standards then-current the with consistent are and quality good of are they as long as units, tures of affordable units need not be the same as or equivalent to those in market rate dwelling - - - 6/29/07 17 Transbay Transit Center & Tower Design & Development Competition STAGE II QUESTIONS & ANSWERS Q62: A portion of our development program includes condominiums. In our ground lease offer to the to offer lease ground our In condominiums. includes program development our of portion A Q62: ie current, in completed be should They year. multi not and static are requested Formas Pro The A61: 6: The ground must either be sold or leased, and the TJPA will not consider a vertical subdivision on A62: Does this structure conform with the technical requirements of the RFP under section 2 ‘Responses fee interest in that portion, assuming there is a legal structure to accommodate this arrangement. TJPA, we would like to carve out the residential condos from the ground lease structure and retain requested sincethetemplateisstatic. being not is that flows; cash discount or inflate to need no is There year. stabilized by meant is what is That operations. stabilized assume should projections expense and Income dollars. 2007 On thisbasis,aproposerwillnotbedisqualifiedforfailingtosubmitgroundleaseproposal. accom could that structure legal a is there that believe not do we Accordingly, term). lease ground the beyond extend that rights have will owners residential (where lease ground a of top Required ForGroundLeaseOnly’oftheModelTermSheet? it should state this in its proposal and decline to offer a proposal under the ground lease option. lease ground the under proposal a offer to decline and proposal its in this state should it then lease, ground year 99 a under held is that site a on units such develop can it that believe not does and units ownership residential include to intends proposer a If request. the modate - GM Memo 07-209 Attachment B Page 1 of 2 September 19, 2007

The Honorable Jerry Hill Chair, Transbay Joint Powers Authority 210 Mission Street, Suite 1960 San Francisco, California

Dear Chair Hill:

This letter is in reference to Item Number 8 on the TJPA Board of Directors calendar for September 20, 2007 concerning the selection of a Design and Development team for the Transbay Transit Center project.

The Alameda-Contra Costa Transit District Board of Directors has reviewed and considered the recommendation of the expert jury that was appointed by the TJPA Board to assist in selecting the winning team. We have carefully reviewed the jury’s detailed and thorough report.

The AC Transit Board of Directors fully supports the jury’s recommendation that the Pelli Clarke Pelli/Hines team be selected to enter into exclusive negotiations with the TJPA and urges the TJPA Board to adopt the jury’s recommendation.

We believe the jury’s recommendation is sound because:

• The Pelli/Hines proposal and concept creates an efficient and well-designed bus transit operational area, and comfortable and clear passenger waiting areas, wayfinding and circulation.

• The Pelli/Hines proposal offers by far the greatest compensation for the Tower site, significantly strengthening the TJPA’s financial position.

• The Pelli/Hines proposal offers a developer that is experienced in San Francisco and has unequaled national experience and financial resources.

• The Pelli/Hines proposal creates a significant and important architectural statement and provides important amenities for San Francisco and San Francisco commuters.

In addition, we understand that the Pelli/Hines team has a long history of working together and creating important structures in many major cities. We are also appreciative of Pelli Clarke Pelli’s reputation of delivering major projects on schedule and within budget. GM Memo 07-209 Attachment B Page 2 of 2 The Honorable Jerry Hill September 19, 2007

The Board also wishes to acknowledge the interest and excitement that the Transbay Transit Center design competition generated. More than 500 people attended the unveiling of these proposals on a Monday night last month creating a very positive atmosphere.

The process has been clear, fair, impartial and professional; it also attracted extraordinary designs and a significant financial offer to the TJPA. The entire TJPA staff, including the URS PMPC team, are to be recognized for this extraordinary achievement, but special thanks are in order to Executive Director Maria Ayerdi and Competition Manager Don Stastny. To have teams of the caliber that participated in the design competition is a testament to Ms Ayerdi’s and Mr. Stastny’s professionalism and capabilities and their passion for this project.

Very truly yours,

Greg Harper President