Environmental Monitoring Report

Project No. 39432-013 Semiannual Report June 2018

Participatory Small-Scale Water Resources Sector Project

Prepared by Local Government Engineering Department for the People’s Republic of Bangladesh and the Asian Development Bank.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

LOCAL GOVERNMENT ENGINEERING DEPARTMENT (LGED)

Participatory Small Scale Water Resources Sector Project (PSSWRSP)

SEMI ANNUAL ENVIRONMENTAL MONITORING REPORT

January - June, 2018

TABLE OF CONTENTS

SL. SUBJECT PAGE NO.

1. INTRODUCTION 1

2. STATUS OF PROGRESS OF SUBPROJECT IMPLEMENTATION 1

3. STATUS OF SAFEGUARD COMPLIANCE WITH ADB LOAN COVENANTS 2

4. ENVIRONMENTAL ASSESSMENT OF SUBPROJECTS 3

5. ENVIRONMENTAL IMPACT AND MANAGEMENT 3

6. ENVIRONMENTAL MONITORING 3

7. PROBLEMS ENCOUNTERED IN IMPLEMENTING EMP AND ECP 7

8. LESSONS LEARNT 7

9. CONCLUSION AND RECOMMENDATIONS 8

ANNEXURE:

ANNEX-A: ENVIRONMENTAL MITIGATION PLAN (EMP)

ANNEX-B: FIELD VISIT REPORT

ANNEX-C: WATER QUALITY IMPACT MONITORING REPORT

1

Participatory Small Scale Water Resources Sector Project Environmental Monitoring Report (January-June, 2018)

1. INTRODUCTION Background Participatory Small Scale Water Resources Sector Project (PSSWRSP) is supported by ADB-IFAD and the estimated project cost is $1119.0 million. It is being implemented by LGED within the purview of Local Governments in accordance with the provisions of the National Water Policy. The Project is a follow up of the two previous SSWRD Sector Projects (SSW-I and II) that implemented 580 subprojects from 1995 to 2009. The PSSWRSP will implement 265 new and 147 enhancement Subprojects in 64 districts of the country of Bangladesh, excluding three districts of Hill Tracts and five other districts namely Kurigram, Sherpur, Jamalpur, & Shariatpur from 2010-2018. Both new and enhancement subprojects are spread over 28 districts, whereas, 15 districts cover only new subprojects and 13 districts cover only enhancement subprojects The subproject types are Command Area Development (CAD), Drainage (DR), Flood Management & Drainage (FMD), Water Conservation (Rubber Dam) {WC (RD)} and Water Conservation & Drainage (WCD). The major physical interventions in respect of these four types of subprojects will be re- excavation of khals, rehabilitation/construction of embankments and construction of water management structures like sluices, regulators, water retention structures, rubber dam, weirs, etc. Goal The overall goal of the project is to reduce the poverty level of the country by increasing sustainable agricultural and fishery production. The project’s objective is to develop sustainable stakeholder-driven small-scale water resources management system with special attention to the poorer section of the population. The project will have three outputs: i) institutional strengthening of government agencies at all levels to support PSSWR development; ii) participatory subprojects, which will include poor and vulnerable groups, and which will enable WMCAs to plan, implement, operate, and maintain subprojects; and iii) construction and maintenance of up to 265 new PSSWR subprojects and performance enhancement up to 147 subprojects. As there is no change in subproject scope, no adjustment in the environmental safeguard measures has been considered at this point. The project scope has remained the same as that of the one outlined in the project document, 2. STATUS OF PROGRESS OF SUBPROJECT IMPLEMENTATION Overall physical progress of new and enhancement subprojects has been documented in the Project 30th QPR. As reported, the overall progress of subprojects is estimated at 100% against the elapsed time of 100%. Of the total new 265 subprojects, a total of 265 subprojects have been implemented (handed over 255). 18 subprojects have been dropped from the candidate subproject list of 283 as these are not viable due to social conflict. Of the total 150 performance enhancement subprojects, 147 subprojects have been completed and contract of 3 subprojects have been dropped due to social conflict. However, summarized Batch wise information on physical progresses of all new and enhancement subprojects is given hereunder.

1

New Subprojects Total target of Batch/year Physical Progress (100%) Total no. of Project (dropped) projects Batch-1: FY: 2010-11 2 0 0 Batch-2: FY: 2011-12 20 0 2 Batch-3: FY: 2012-13 51 5 2 Batch-4: FY: 2013-14 70 24 6 Batch-5: FY: 2014-15 70 21 1 Batch-6: FY: 2015-16 70 54 7 Batch-7: FY: 2016-17 84 0 Batch-8: FY: 2017-18 77 0 Total 283 265 18

Enhancement Subprojects Total target. of Batch/year Physical Progress (100%) Total no. of Project (dropped) projects Batch-1: FY: 2010-11 4 0 0 Batch-2: FY: 2011-12 25 13 0 Batch-3: FY: 2012-13 30 19 0 Batch-4: FY: 2013-14 30 23 0 Batch-5: FY: 2014-15 30 21 0 Batch-6: FY: 2015-16 31 19 3 Batch-7: FY: 2016-17 41 0 Batch-8: FY: 2017-18 11 0 Total 150 147 3

3. STATUS OF SAFEGUARD COMPLIANCE WITH ADB LOAN COVENANTS The status of safeguard compliance with ADB Loan Covenants and national safeguard regulations is found to be on track. Detail of status is shown in the following table:

Status of Compliance with ADB Loan Covenant (as of June, 2018): Environment Reference in the Loan Timing for Covenants Status of Compliance Agreement compliances The Borrower, LGED shall ensure that a) the subprojects are designed, constructed, operated,

LA Throughout the and maintained in accordance with Borrower’s Complied Environmental Schedule-5 Project Conservation Rules (1997), ADB’s Safeguard Policy Statements (2009) and EARP Para-14 Implementation

prepared for the project and agreed between the Borrower and ADB; b) the EMP and the mitigation measures included LA Throughout the therein, as specified in the IEEs, are properly Schedule-5 Project Complied implemented; Para-14 Implementation c) any adverse impact on the environment that may arise LA Throughout the from the project implementation is promptly mitigated Schedule-5 Project Complied or minimized in accordance with the EMPs: Para-14 Implementation d) implementation of the EMPs, including any safety LA Throughout the breaches, violation of environmental standards, and Complied Schedule-5 Project corrective measures taken in respect thereof are Para-14 Implementation reported semi-annually to ADB; e) environmental requirements (as set out in the EMP) LA Throughout the Complied are incorporated into the bidding documents and civil Schedule-5 Project

works contracts Para-14 Implementation f) all environmental permits, licenses, and clearances LA Throughout the Complied are obtained in a timely manner prior to Schedule-5 Project

commencement of Works Para-14 Implementation

4. ENVIRONMENTAL ASSESSMENT OF SUBPROJECTS The PSSWRSP has undertaken implementation of 265 New and 147 Enhancement subprojects of different categories having benefited areas of 50-1000 ha each by rehabilitation and/or upgrading of existing water management systems. The policy of ADB is

2 to promote environmentally sustainable economic development in developing countries those use ADB’s assistance/support. The SSWRSP has been classified as Category B. Summary and Initial Environmental Examinations (SIEE and IEEs) and environmental assessment and review procedures are done in accordance with the ADB Environmental Policy (2002) and Environmental Assessment Guidelines (2003), and the Bangladesh Government’s environmental requirements. The Initial Environmental Examination (IEE) is being prepared for each Subproject. The IEE identifies and highlights all beneficial and adverse impacts that may arise due to implementation of the project. 5. ENVIRONMENTAL IMPACT AND MANAGEMENT Considering the impacts as outlined in the IEE report, an Environmental Management and Monitoring Plan (EMMP) is being prepared for each subproject. The EMP defines how mitigation measures suggested in the IEE are being executed and monitored during the design, construction and O&M stages of the subproject. A monitoring program for an important environmental indicator namely water quality of representative sample subprojects will have to be carried out for a minimum period of 5 years. . A set of baseline data will have to be collected before starting operations of the of representative sample subprojects. This monitoring program will be covered by Environmental Lab Technician and Project Implementation Consultant. Also biodiversity impact monitoring for a group of subprojects shall be conducted by a contracted NGO or Consulting Firm. The results of monitoring will then be analyzed and evaluated for designing the required appropriate protective measures against any adverse impacts. Besides water quality monitoring, close supervision and monitoring will be undertaken to ensure that the PSSWRSP is being implemented in an environmentally sound and transparent manner. 6. ENVIRONMENTAL MONITORING Institutional Arrangements: As regards the institutional arrangements, PMU takes overall responsibilities of the monitoring through the PIU at district and upazila levels and subproject WMCA. Project implementation consultants (PICs) support the PMU. Selection of Monitoring Parameters: The Project (PSSWRSP) has been categorized as ‘B’ in accordance with ADB's Safeguard Policy Statement (2009) and as Orange B using GOB criteria (ECR, 1995). These sub-projects are not located in or near any ecologically sensitive area (ECA) and will not have any significant impact. Further REA screening suggests that typical construction related impacts are associated with the civil works of the subprojects. These impacts are of limited intensity and short duration, and can be mitigated by appropriate measures (as proposed in the EMP) including adoption of good construction practices related to protection of community health and safety. However, considering the above fact, qualitative/quantitative monitoring data of only water (surface and ground water) has been considered in the monitoring outcome. Monitoring data of soil, air, noise, biodiversity etc are excluded from monitoring program as these are expected to produce no notable impact due to the implementation of subprojects. Accordingly, the monitoring parameters/indicators considered for water are pH, electrical -3 conductivity (Eh), dissolved oxygen (DO), nitrate-N (NO3-N), phosphate-P (PO4 ), water O hardness (as CaCo3), total dissolved solids (TDS) and Temp ( C), whereas indicators like particulate matters (PM), oxides of sulfur (SOx), oxides of nitrogen (NOx) for air quality has not been considered. Conventional portable water quality test kits are being used for measuring the values of test parameters.

3

Output 1: Subproject IEE Report Finalization with EMP incorporation Up to June, 2018, the IEE of 283 subprojects with their respective EMP template have been finalized. The template, considering all possible impacts due to implementation activities and their mitigation measures, have been prepared to adapt to the specific requirement of the subproject (Annex-A). Status of IEE of New Subprojects (as of June, 2018) Total target of Status of IEE (as of Total no. of Sub- Batch/year subprojects June, 2018) project (dropped) Batch-1: FY: 2010-11 2 Completed 0 Batch-2: FY: 2011-12 20 Completed 2 Batch-3: FY: 2012-13 51 Completed 2 Batch-4: FY: 2013-14 70 Completed 6 Batch-5: FY: 2014-15 70 Completed 1 Batch-6: FY: 2015-16 70 Completed 7 Total 283 Completed 18

Output 2: Environmental Field Monitoring and Supervision Field monitoring during this reporting period is being undertaken to check and verify whether the subproject Contractors/LCS groups has properly complied with EMP and restoration activities for construction and ancillary sites in the implemented subprojects as specified in the Contract Document and Bill of Quantities, and consequently adhered to the underlying principles of ADB’s Environmental Safeguard Policies in relation to the restoration of construction site.

Output 3: Field Visit to verify the Implementation of EMP and Environmental Good Work Practices during Earth Work & Structure Construction As the part of environmental monitoring and supervision of completed subprojects with relation to EMP compliance and restoration of construction and ancillary sites as well, 20 numbers of randomly selected subprojects (4 subprojects/category x 5 categories) from PSSWRSP have been visited at intervals to verify/examine the status of EMP compliance and restoration of construction and ancillary sites as well. However, a summary of noted observations from field visits is presented in Annex-B.

Output 4: Water Quality Impact Monitoring The impacts of project interventions are intended to be determined through monitoring of changes in water quality in sample subprojects. It has been planned to collect water samples on quarterly basis from 2 sites: one for surface water (from river/canal/beel/pond) and one for groundwater (hand tube well/shallow tube well/deep tube well). Data collected during the first year is used for establishing baseline conditions and then follow-up data of the monitoring period are being compared for assessing impact of project interventions.

The water quality parameters for this monitoring are pH, electrical conductivity (Eh), -3 dissolved oxygen (DO), nitrate-N (NO3-N), phosphate-P (PO4 ), water hardness (as CaCo3), total dissolved solids (TDS) and Temp (OC). The water quality test results of target sample subprojects presented in (Annex-C) However, analysis of the water quality test results of sample subprojects has demonstrated basically no remarkable abnormalities with respect to the quality of surface and ground water. Values of all the tested parameters of water quality agree well with the recommended values of the Department of Environment. Only in few instances salinity values of surface

4 water and CaCO3 (Hardness) values demonstrated somewhat irregularities. By and large subproject interventions appear to exert no noticeable adverse impact on water quality in the sample subprojects.

Output 5: Environmental Training/Capacity Building In order to ensure effective and timely implementation of the EMP, in particular, and to enhance the environmental management capacity of Upazila Engineers, Sr. Sociologists, and Socio-economist of project districts, and WMCA members at subproject level, a training program has been developed and undertaken during project period. Once the Upazila Engineers, Sr. Sociologists, and Socio-economist staffs have received appropriate training and have gained adequate experience on environmental related matters, they are expected to train the WMCA members and contractor’s staff, NGOs and other stakeholders. The following aspects are considered in the environmental training programme: • Integrating environmental management in O&M planning by preparing environmental management plan (EMP) for subprojects. • Strengthening the theoretical and practical knowledge of LGED Environmental Lab personnel in order to facilitate smooth operation of lab exercises • Integrating environmental considerations into the effect monitoring environmental issues, impact and management • Strengthening the understanding and environmental knowledge of WMCA members through training In order to achieve the above aspects, a comprehensive environmental training program has been designed. During the current reporting period (January-June, 2018), training of two (2) course events for Environmental Awareness and Local Resource Management has been conducted sixty (60) participated in the training including thirty (30) females (50%). The course events spread over sixty (60) trainee days. Details of the conducted trainings have been outlined in the table below: Details of the conducted training program

Training Total No. Participants Trainee Days Category of Duration Course Course Titles of Training Participants (day) Codes Events Male Female Male Female Total

Environmental WMCA members PSSW-167 Awareness and Local and general 2 1 30 30 30 30 60 Resources Management beneficiaries, including women As regards the status of Environmental Training, already a number of training programs has been conducted under the project during FY 2012-18, and these training details are given in the table below:

Cumulative Achievement as of June, 2016 Course Code, Title & Category of Participants Sl. Participants No. No. of Duration Total Trainee Events (days) Participants days Code Title Category of Participants Male Female

1 66 1 653 213 866 866 PSSW- Implementation & Monitoring XEN,UE,AE,Socio,CO,CA,

5

92 of Environmental Mitigation WMCA members measures

Selected LGED Lab PSSW- Environmental Laboratory 2 Technicians, Lab Asstt. & 8 3,2,1 90 0 90 180 93 and Water Quality Testing Agri/Fish Faci.

Orientation on WMCA members and PSSW- Environmental Awareness 3 general beneficiaries, 304 1 1955 2594 4549 4549 167 and Local Resources including women & Cos Management

AE,UE, SoE,CO, Selected TOT on Environmental PSSW- WMCA 4 Issues, Impact & 15 2 170 34 204 408 168 Chairman/Secretary/Wome Management n members

Total 393 2868 2841 5709 6003

The training programs with respective course code are listed below: Course Code Course Title

PSSW-92: Preparation & Monitoring of Environmental Mitigation Plan (EMP) PSSW-93: Environmental Laboratory & Water Quality Testing PSSW-167: Orientation on Environmental Awareness &l Resources management PSSW-168: TOT Environmental Issues, Impact & Management For the sake of brevity, the above Courses Handouts are not annexed here. However, these will be made available on request. Additionally, in order to enhance the environmental management capacity of contractors and their staff members, training programs at subproject field level /work site are being arranged and undertaken by CM & QCS (Construction Monitoring & Quality Control Supervision) and Environmental Specialist. These training consist of 2 sessions (Session 1: Environmental Awareness Building and Understanding of ECP for Good Work Practices, and Session 2: Contractor’s Self Monitoring and Supervision of subproject environmental works. 7. PROBLEMS ENCOUNTERED IN IMPLEMENTING EMP AND ECP Implementing of Environmental Management Plan (EMP), more specifically environmental mitigation measures in different subprojects were found to be more difficult than it was initially expected. One of the major reasons for this was apparent lack of interest on the part of many Engineers to the Contract and the Contractor in the implementation of EMP. Further most of the contractors had no trained works force to address the environmental issues or to implement the EMP/Environmental Specifications of Tender Document. It was very difficult to convince contractors to recruit trained manpower in order to be able to implement EMP/mitigation measures in subproject. It is worthwhile to point out here that sufficient funds must be allocated for environmental management works of subprojects else contractors will show little interest in the subproject related environmental issues. As the subprojects spread over a vast rural area covering 56 districts, frequent field investigation in relation to environmental supervision and monitoring of subproject works has become difficult. During the contract award, it was decided that contactor’s staff would conduct project environmental works with due diligence. Apparently, this did not work properly due to lack of experience and interest of contractor.

6

8. LESSONS LEARNT One important lesson learnt during implementation of Environmental Management Plan (EMP) and Environmental Code of Practice (ECP) was that that no matter how many environmental consultations are made with contractors and field level staff, unless there is proper institutional setup for Environmental Management all these efforts will produce limited sustainable impact. In order to make the environmental monitoring works more effective and transparent; an institutional set-up for environmental monitoring has been proposed for the project and outlined here below: Institutional set-up for Environmental Monitoring: The environmental monitoring will lead to evaluate the physical performance and impact of the interventions inside and outside of the subproject area and to an understanding how the beneficiaries living in the subproject area responds technically, economically and socially to the environment to be created by flood control, drainage and water retention structures. PMO will take overall responsibilities of the monitoring through the PIU at district and upazila levels and subproject WMCA. Project implementation consultants (PICs) will support the PMO. The monitoring will identify environmental impacts during the construction and operation stages. Subproject operation: The subproject beneficiaries have agreed to form WMCA through which they are managing various subproject activities. These include monitoring of environmental issues which will help the beneficiaries to prepare subproject O&M plan to take advantage of flood control and drainage improvement and water retention and formulate practical recommendations to solve subproject induced and related problems. Following the completion of the construction of infrastructure, the WMCAs undertake the overall responsibilities of environmental monitoring in the subproject area. WMCA O&M, Agriculture and Fisheries subcommittees are supporting the Management Committee in the monitoring. The monitoring contributes to create a basis for water resources management in the subproject area through better understanding of the real impacts of the subproject on agricultural and fisheries resources, environment and economic Majority of contractors involved in implementation of PSSWRSP sub-projects have limited experience of Environmental Management of rural infrastructures. They have not recruited any Environmental Scientists or Environmental Engineers to address the environmental issues. Contractors own environmental monitoring, records of non-compliances, corrective actions taken and reporting of assessment of Environmental Management activates are hardly available as most contractors do not have trained staffs to keep these records. As it appears, contractors, their staff and construction workers are not fully aware of Environmental and Social Safeguards in achieving desired level of Environmental Safeguard objectives of the sub-projects. Because of this, environmental issues figure low in priority and are neglected / ignored during all stages of project works.

9. CONCLUSION AND RECOMMENDATIONS It has been observed that implementation of EMP encountered problem due to inexperienced contractors bidding for projects, some contractors sub-contracting work, quoting low price to win contract, hiring of plants and machinery of low quality at low costs. These contractors gave very little importance to health and safety issues or providing better working conditions, construction of labor camps, stack yards etc. Contractors’ contract labors are mostly from rural areas with almost no experience in construction work and on health and safety issues. These labors have hardly any idea of Environmental Management, especially issues of health and work safety at work sites.

7

In order to incorporate EMP/ECP, Environmental Policy of ADB and Bangladesh Government should be followed by all concerned parties, including Upazila Engineer and XEN. Environmental Management capacity both at field level of LGED and at HQ level needs to be strengthening. Institutional arrangement for Environmental Management of LGED project should be uniform for all the projects and environmental standard should be considered as important as ensuring standard of civil works. Ensuring environmental standard should be considered as important as ensuring standard of civil works. However, this may require a long term planning. Short-term solutions will to encourage XENs/UEs to be more involved in Environmental Management of PSSWRSP sub-projects before they approve payment to contractors. XEN/UE being the Engineer to the contract should ensure proper implementation of EMP/ECP and Environmental Specification of Tender Documents. After completion of civil works, tree plantation and tree caring should be monitored carefully. Trees are part of environmental program and used for slope stabilization and slope protection. Turfing is also an essential component of slope of protection and proper care should be ensured for its maintenance.

8

Annex-A Participatory Small Scale Water Resources Sector Project (PSSWRSP)

ENVIRONMENTAL MITIGATION PLAN (EMP)

A. Subproject Information Name : B. Type : C. Upazilla : District :

D. Proposed Interventions Khal re-excavation/excavation Construction/re-sectioning of embankment ….. km Construction of Regulator/Sluice/ WRS … Construction of Levee km Contruction of Culvert no Irrigation canals: Open (pucca/earthen) ...... km Buried Pipeline ...... km E. Subproject Implementation Schedule Name of the work/activities Date Start Date End 1. Re-excavation of Khal 2. Construction of WRSs F. Design Discussion Meeting including Environmental Mitigation Measures

Place: ...... Date: ...... Number of Project Affected People (PAPs) present: ……………………

G. Signing of Environmental Mitigation Plan (at the time of signing Implementation Agreement)

Place of Signing: …………………... Date of Signing: ………………

LGED WMCA

(……..………………..) (……..………………..)

Executive Engineer, LGED Chairperson ………………… ………………… Subproject WMCA

Steps for Preparing Environmental Mitigation Plan: 1. Finding of potential impacts and identification of adverse impact issues from environmental assessment study report (IEE/EIA). 2. Cross checking of identified adverse impact issues with PRA findings. 3. Identification of PAPs from both IEE/EIA and PRA reports. 4. Presentation of identified impacts and their best possible mitigation options in meeting with PAPs and collection of their opinion in implementing the program. 5. Finalization of EMP after detail discussion with PAPs and incorporation of recommended options in the engineering design. 6. Fixing of implementation schedule for finally accepted Mitigation Plan and endorsement of the document by the concerned LGED Executive Engineer, PAPs, and representatives from WMCAs. 7. Note: All works/activities in the signed mitigation plan should be clearly mentioned in the Implementation Agreement of the concern subproject.

9

Environmental Mitigation Plan Name of the Subproject: Union /Upazila/District: Name of Village/Mouzas: Gross Area of Subproject: SI. Impact of Subproject Activities Mitigation Measures Number Signature of PAP Responsible Entity / on IECs, Resources and Values of PAPs representative(s) Party During design During construction During O&M Physical Environment 1. Regional Flood  Design to ensure no induced   Proper and timely Design : FSDD Firm, PC Regime/Hydrology flooding opening / closing of Constrn. : -  Increase flood intensity  Incorporation of adequate regulator gates, O&M : WMCA, UE  Change in river/khal water flow in design of hydraulic maintaining gates and flow and flooding pattern structures hoisting gears/systems  Enhanced flood risk in  More recharge by in good operable adjacent areas increasing inundation area condition, etc  Fall of ground water table and period  Increase of surface water irrigation facilities 2. Drainage /Water-logging  Design to avoid drainage   Maintaining drainage Design : FSDD Firm, PC  Create/increase drainage congestion : in any lower channels clear of fish Constrn. : - congestion area either inside or outside bundhs, water O&M : WMCA, UE  Cause excessive/unwanted the subproject by draining weeds/hyacinths, drainage (reducing permanent upper / inside areas, inside  Maintain Seal of gates water body/affecting soil subproject area due to property and close gates moisture) inadequate drainage path/ properly/timely to  Water logging in low lying diversion channel during prevent loss of water areas construction; required to be  Hindrance in natural flushing  Design to ensure no conserved, excessive drainage reducing permanent water body significantly;  Design to provide adequate drainage facilities  Design to prevent significant seepage from irrigation canal Instructions to Complete the EMP format:1. Put Tick (✓) in appropriate Box/Measure to confirm the action to be taken. 2. Complete only the IECs that are identified in the IEE to have adverse impacts 3. Any action/measure to be taken other then the mentioned ones should be described against the empty boxes and the box should also be ticked (✓).

10

SI. Impact of Subproject Activities on Mitigation Measures Number Signature of PAP Responsible Entity / Party IECs, Resources and Values of PAPs representative(s) During design During construction During O&M

3. Soil Characteristics / Soil  Design for provision for  Ensure no top soil  Training to farmers on Fertility natural replenishment of removal from fertile IPM / ICM through  Degradation of soil fertility due flood plain soil by flood agricultural land DAE/SRDI support Design : - to: removal of top soil, intensive/ water inundation (top soil to be  Analysis of soil samples diversified agriculture excavated and (base data) of Constrn. : Contractor, (increased use of inorganic kept reserved at subprojects cultivated CS fertilizers, pesticides), one place, take soil land and use fertilizer preventing nutrient rich for construction in application at SRDI/DAE sediment deposition on lands shallow cutting recommended doses O&M : WMCA & Line  Loss of soil fertility due to from the land and  Enhance use of organic Agency DAE hindrance in natural spread the manure by farmers replenishment of flood plain soil preserved top soil by flood water inundation. on land again; 4. Erosion and Siltation  Design to consider existing  Adopt appropriate  Include in the O & M risk and cause no significant construction program special care  Increase sediment deposit on induced impact (provide close management to taking of new earthwork land outside embankment, turf on top and side slopes of minimize erosion of structures under both  Erosion of loose soil from new embankments, set sill levels soil from routine and periodic for earthwork (embankment/spoil) of structures at lower levels or excavations, the initial 2-3 years to and deposit ion on agricultural use other techniques to flush embankments/spoil reduce erosion of soil land out most of sediment load; deposits, etc during during rain and Design : FSDD Firm, PC rains; deposition on nearby  Increased siltation of river/khal crop lands. bed due to construction of Constrn. : - WRS, Weir, Rubber Dam, etc.  Include in the O&M

program removal of deposited silt from the O&M : WMCA, UE channel bed upstream of weirs and elevated sill structures;

11

SI. Impact of Subproject Activities on Mitigation Measures Number Signature of PAP Responsible Entity / Party IECs, Resources and Values of PAPs representative(s) During design During construction During O&M

Biological/ Ecological Environment

5. Terrestrial Habitat:  Design considering minimum  Do not undertake  Include social  Removal /cutting of trees and removal / clearance of trees unnecessary afforestation program on vegetation and vegetation clearance of available land (roadside, vegetation/felling khal bank, structure Design : FSDD Firm, PC trees during site,etc) Constrn. : Contractor, construction CS, IWRMU

O&M : WMCA, CO

6. Wetland Habitat:  Design to avoid complete  Ensure compliance to  Drying up or drastic reduction of drying up of water bodies the timely operation of permanent water bodies/areas  Design to minimize reduction gates of hydraulic  Significant reduction of of seasonal floodplain area structures (meant for Design : FSDD Firm, PC seasonal floodplain area water conservation) Constrn. : -

O&M : WMCA, CO

Instructions to Complete the EMP format:1. Put Tick (✓) in appropriate Box/Measure to confirm the action to be taken. 2. Complete only the IECs that are identified in the IEE to have adverse impacts 3. Any action/measure to be taken other then the mentioned ones should be described against the empty boxes and the box should also be ticked (✓).

12

SI. Impact of Subproject Activities Mitigation Measures Number Signature of PAP Responsible Entity / on IECs, Resources and Values of PAPs representative(s) Party During design During construction During O&M

7. Fisheries:  Consider provision of fish-   Utilization of all Design : FSDD Firm, PC  Decline in natural fisheries pass fish friendly operation subproject wetlands for production to facilitate hatchling fisheries production. Constrn. : -  Reduction of fish habitat migration;  Fish-friendly gate  Reduction of fish biodiversity  Design for provision of fish operation schedule to O&M : WMCA, CO, shelter in khals, fish facilitate in-migration of line agency sanctuary in the Beels and fish for breeding and DoF fixing of fish net at the spawning drainage structure to restrict  Training on improved out-migration of fish fisheries technology, community based culture fisheries in subproject water bodies including hatchery and restocking programme 8. Biodiversity:  Design to consider no drastic   Include social afforestation Design : PC  Loss of biodiversity (due to reduction in permanent water program on available land Constrn. : IWRMU decrease of aquatic and bodies, plant and forest area (roadside, khal bank, O&M : WMCA, CO terrestrial habitat) structure site, etc) Social Environment

9. Land Acquisition:  Consider in the design Design : FSDD Firm, PC  Loss of agricultural avoidance/ minimization of Constrn. : IWRMU land/homestead area land acquisition O&M : -  Dislocation of habitat  Provision for compensation  Economic livelihood disruption and/or resettlement of dislocated persons (PAP's)  Minimize disruption of livelihood and provide for compensation for alternate livelihood  Borrow earth from non- cultivable land

13

SI. Impact of Subproject Activities Mitigation Measures Number Signature of PAP Responsible Entity / on IECs, Resources and Values of PAPs representative(s) Party During design During construction During O&M

10.Unemployment  Identification of affected  Employ local people,  Employ local people, Design : FSDD Firm, PC  Unemployment / reduction of professional group and especially women in especially women in Constrn. : Contractor, CS scope of employment of incorporation of in-kind construction works. O&M activities O&M : WMCA, CO professional community (i.e. compensation for losses in fisher, boat men, etc.) the sub-project planning 11.Navigation / Boat Plying facilities  Consider in the design boat-   Ensure compliance to Design : FSDD Firm, PC  Hindrance/obstruction to boat pass facility in hydraulic operation of hydraulic Constrn. : IWRMU plying structure s, as for as possible. structures for boat pass O&M : WMCA, CO 

Instructions to Complete the EMP format:1. Put Tick (✓) in appropriate Box/Measure to confirm the action to be taken. 2. Complete only the IECs that are identified in the IEE to have adverse impacts 3. Any action/measure to be taken other then the mentioned ones should be described against the empty boxes and the box should also be ticked (✓).

SI. Impact of Subproject Activities Mitigation Measures Numbe Signature of Responsible Entity / on IECs, Resources and r of PAP Party During design During construction During O&M Values PAPs representati ve(s)

Facilities for Workers:   Design : -  Provide adequate Constrn. : Contractor,  Water Supply and Sanitation water supply and CS Facilities for Workers sanitation/toilet O&M : WMCA, CO  Health and Safety Measures facilities for workers For Workers  Adopt appropriate safety measures at work, and provide first

aid services  Make workers aware of health risks and how to avoid these

14

SI. Impact of Subproject Activities Mitigation Measures Numbe Signature of Responsible Entity / on IECs, Resources and r of PAP Party During design During construction During O&M Values PAPs representati ve(s)

Other Environmental Attributes 12.  Air pollution through dust   Spray water regularly  Design : - generation due to subproject on dry work surfaces Constrn. : Contractor, works creating dust CS problems O&M : WMCA,CO 13.  Noise pollution from   Avoid unnecessary  Design : - construction activities noise near the vicinity Constrn. : Contractor,  of homestead areas CS O&M : WMCA,CO 14.  Pollution of water from   Periodic analysis of Design : - application of high doses of representative water Constrn. : inorganic fertilizers/ samples (surface & IWRMU/Dist.XEN pesticides. groundwater) of O&M : -  subproject area 15.  Environmentally sensitive  Avoid archaeological/   area, Archaeological / historical sites, Historical Sites environmentally sensitive Design : FSDD Firm, PC areas (Ramsar Sites:Tanguar Constrn. : IWRMU Haor and Hakaluki Haor; O&M : WMCA, UE National Protected area: Laua Chhara Forest /other national reserve forest areas)

Instructions to Complete the EMP format:1. Put Tick (✓) in appropriate Box/Measure to confirm the action to be taken. 2. Complete only the IECs that are identified in the IEE to have adverse impacts 3. Any action/measure to be taken other then the mentioned ones should be described against the empty boxes and the box should also be ticked (✓).

Executive Engineer, LGED WMCA Chairperson Date of signing:...... Place of signing: ......

15

Annex- B

EMP Compliance and Restoration Status Of Construction and Ancillary Sites of Implemented Subprojects Environmental Sl. Status of EMP Status of Item Location Enhancement No Compliance Restoration (Tree plantation) Restoring of topsoil at site of field office 1. Sundary Khal CAD (SP42015-IFAD-2) Kachua, Chandpur EMP Complied Restoration done yet to take effect 2. Fashiakhali CAD (SP42021-ADB) Chokoria, Cox’s Bazar EMP Complied Restoration done yet to take effect Mohandanga Panna Beel CAD (SP44087- 3. Sadar, Chapai Nawabganj EMP Complied Restoration done yet to take effect ADB) 4. Pashchimj Joar CAD (SP44093-ADB) Mirersarai, Chittagong EMP Complied Restoration done yet to take effect 5. Sapleza DR (SP42022-IFAD-1) Mothbaria, Pirojpur EMP Complied Restoration done yet to take effect 6. Belgapur Julupara DR (SP43031-ADB) Niamatpur, Naogaon EMP Complied Restoration done yet to take effect 7. Badrabati (north) DR (SP43037-IFAD-2) Tarash, EMP Complied Restoration done yet to take effect 8. Arua Kamini DR (SP46253-IFAD-1) Amtoly, Barguna EMP Complied Restoration done yet to take effect 9. Kata Khal FMD (SP42018-ADB) Mujibnagar, Meherpur EMP Complied Restoration done yet to take effect 10. Dholdholia FMD (SP43055-IFAD-2) Saghata, Gaibandha EMP Complied Restoration done yet to take effect 11. Adabaria FMD (SP43057-IFAD-2) Bauphal, Patuakhali EMP Complied Restoration done yet to take effect 12. Dhonkundi Beel FMD (SP44078-ADB) Sherpur, EMP Complied Restoration done yet to take effect Bhelabari Durgapur WC (RD) (SP41006- 13. Aditmari, Lalmonirhat EMP Complied Restoration done yet to take effect ADB) Pashchim Dighulia WC (RD) (SP43047- 14. Ukhia, Cox’s Bazar EMP Complied Restoration done yet to take effect IFAD-2) 15. Hangor Khal WC (RD) (SP46214-ADB) Lohagara, Chittagong EMP Complied Restoration done yet to take effect 16. Chambi Khal WC (RD) (SP46222-ADB) Lohagara, Chittagong EMP Complied Restoration done yet to take effect 17. Purba Sarail Madhai WCD (SP41002-ADB) Kalai, Joypurhat EMP Complied Restoration done yet to take effect Chak Gobindapur Aldadpur WCD 18. Sadullahpur, Gaibandha EMP Complied Restoration done yet to take effect (SP41004-ADB) 19. Noapara Hazirdhara WCD (SP41011-ADB) Puthia, EMP Complied Restoration done yet to take effect 20. Ulushi Khal WCD (SP42020-IFAD-2) Tarash Sirajganj EMP Complied Restoration done yet to take effect Restoring of topsoil at Workers Camp 1. Sundary Khal CAD (SP42015-IFAD-2) Kachua, Chandpur EMP Complied Restoration done yet to take effect 2. Fashiakhali CAD (SP42021-ADB) Chokoria, Cox’s Bazar EMP Complied Restoration done yet to take effect Mohandanga Panna Beel CAD (SP44087- 3. Sadar, Chapai Nawabganj EMP Complied Restoration done yet to take effect ADB) 4. Pashchimj Joar CAD (SP44093-ADB) Mirersarai, Chittagong EMP Complied Restoration done yet to take effect 5. Sapleza DR (SP42022-IFAD-1) Mothbaria, Pirojpur EMP Complied Restoration done yet to take effect 6. Belgapur Julupara DR (SP43031-ADB) Niamatpur, Naogaon EMP Complied Restoration done yet to take effect 7. Badrabati (north) DR (SP43037-IFAD-2) Tarash, Sirajganj EMP Complied Restoration done yet to take effect 8. Arua Kamini DR (SP46253-IFAD-1) Amtoly, Barguna EMP Complied Restoration done yet to take effect

16

Environmental Sl. Status of EMP Status of Item Location Enhancement No Compliance Restoration (Tree plantation) 9. Kata Khal FMD (SP42018-ADB) Mujibnagar, Meherpur EMP Complied Restoration done yet to take effect 10. Dholdholia FMD (SP43055-IFAD-2) Saghata, Gaibandha EMP Complied Restoration done yet to take effect 11. Adabaria FMD (SP43057-IFAD-2) Bauphal, Patuakhali EMP Complied Restoration done yet to take effect 12. Dhonkundi Beel FMD (SP44078-ADB) Sherpur, Bogra EMP Complied Restoration done yet to take effect Bhelabari Durgapur WC (RD) (SP41006- 13. Aditmari, Lalmonirhat EMP Complied Restoration done yet to take effect ADB) Pashchim Dighulia WC (RD) (SP43047- 14. Ukhia, Cox’s Bazar EMP Complied Restoration done yet to take effect IFAD-2) 15. Hangor Khal WC (RD) (SP46214-ADB) Lohagara, Chittagong EMP Complied Restoration done yet to take effect 16. Chambi Khal WC (RD) (SP46222-ADB) Lohagara, Chittagong EMP Complied Restoration done yet to take effect 17. Purba Sarail Madhai WCD (SP41002-ADB) Kalai, Joypurhat EMP Complied Restoration done yet to take effect Chak Gobindapur Aldadpur WCD 18. Sadullahpur, Gaibandha EMP Complied Restoration done yet to take effect (SP41004-ADB) 19. Noapara Hazirdhara WCD (SP41011-ADB) Puthia, Rajshahi EMP Complied Restoration done yet to take effect 20. Ulushi Khal WCD (SP42020-IFAD-2) Tarash Sirajganj EMP Complied Restoration done yet to take effect Restoring of topsoil at site of stock yard 1. Sundary Khal CAD (SP42015-IFAD-2) Kachua, Chandpur EMP Complied Restoration done yet to take effect 2. Fashiakhali CAD (SP42021-ADB) Chokoria, Cox’s Bazar EMP Complied Restoration done yet to take effect Mohandanga Panna Beel CAD (SP44087- 3. Sadar, Chapai Nawabganj EMP Complied Restoration done yet to take effect ADB) 4. Pashchimj Joar CAD (SP44093-ADB) Mirersarai, Chittagong EMP Complied Restoration done yet to take effect 5. Sapleza DR (SP42022-IFAD-1) Mothbaria, Pirojpur EMP Complied Restoration done yet to take effect 6. Belgapur Julupara DR (SP43031-ADB) Niamatpur, Naogaon EMP Complied Restoration done yet to take effect 7. Badrabati (north) DR (SP43037-IFAD-2) Tarash, Sirajganj EMP Complied Restoration done yet to take effect 8. Arua Kamini DR (SP46253-IFAD-1) Amtoly, Barguna EMP Complied Restoration done yet to take effect 9. Kata Khal FMD (SP42018-ADB) Mujibnagar, Meherpur EMP Complied Restoration done yet to take effect 10. Dholdholia FMD (SP43055-IFAD-2) Saghata, Gaibandha EMP Complied Restoration done yet to take effect 11. Adabaria FMD (SP43057-IFAD-2) Bauphal, Patuakhali EMP Complied Restoration done yet to take effect 12. Dhonkundi Beel FMD (SP44078-ADB) Sherpur, Bogra EMP Complied Restoration done yet to take effect Bhelabari Durgapur WC (RD) (SP41006- 13. Aditmari, Lalmonirhat EMP Complied Restoration done yet to take effect ADB) Pashchim Dighulia WC (RD) (SP43047- 14. Ukhia, Cox’s Bazar EMP Complied Restoration done yet to take effect IFAD-2) 15. Hangor Khal WC (RD) (SP46214-ADB) Lohagara, Chittagong EMP Complied Restoration done yet to take effect 16. Chambi Khal WC (RD) (SP46222-ADB) Lohagara, Chittagong EMP Complied Restoration done yet to take effect 17. Purba Sarail Madhai WCD (SP41002-ADB) Kalai, Joypurhat EMP Complied Restoration done yet to take effect Chak Gobindapur Aldadpur WCD 18. Sadullahpur, Gaibandha EMP Complied Restoration done yet to take effect (SP41004-ADB)

17

Environmental Sl. Status of EMP Status of Item Location Enhancement No Compliance Restoration (Tree plantation) 19. Noapara Hazirdhara WCD (SP41011-ADB) Puthia, Rajshahi EMP Complied Restoration done yet to take effect 20. Ulushi Khal WCD (SP42020-IFAD-2) Tarash Sirajganj EMP Complied Restoration done yet to take effect Clearing of un-used construction materials from construction and ancillary sites 1. Sundary Khal CAD (SP42015-IFAD-2) Kachua, Chandpur EMP Complied Restoration done yet to take effect 2. Fashiakhali CAD (SP42021-ADB) Chokoria, Cox’s Bazar EMP Complied Restoration done yet to take effect Mohandanga Panna Beel CAD (SP44087- 3. Sadar, Chapai Nawabganj EMP Complied Restoration done yet to take effect ADB) 4. Pashchimj Joar CAD (SP44093-ADB) Mirersarai, Chittagong EMP Complied Restoration done yet to take effect 5. Sapleza DR (SP42022-IFAD-1) Mothbaria, Pirojpur EMP Complied Restoration done yet to take effect 6. Belgapur Julupara DR (SP43031-ADB) Niamatpur, Naogaon EMP Complied Restoration done yet to take effect 7. Badrabati (north) DR (SP43037-IFAD-2) Tarash, Sirajganj EMP Complied Restoration done yet to take effect 8. Arua Kamini DR (SP46253-IFAD-1) Amtoly, Barguna EMP Complied Restoration done yet to take effect 9. Kata Khal FMD (SP42018-ADB) Mujibnagar, Meherpur EMP Complied Restoration done yet to take effect 10. Dholdholia FMD (SP43055-IFAD-2) Saghata, Gaibandha EMP Complied Restoration done yet to take effect 11. Adabaria FMD (SP43057-IFAD-2) Bauphal, Patuakhali EMP Complied Restoration done yet to take effect 12. Dhonkundi Beel FMD (SP44078-ADB) Sherpur, Bogra EMP Complied Restoration done yet to take effect Bhelabari Durgapur WC (RD) (SP41006- 13. Aditmari, Lalmonirhat EMP Complied Restoration done yet to take effect ADB) Pashchim Dighulia WC (RD) (SP43047- 14. Ukhia, Cox’s Bazar EMP Complied Restoration done yet to take effect IFAD-2) 15. Hangor Khal WC (RD) (SP46214-ADB) Lohagara, Chittagong EMP Complied Restoration done yet to take effect 16. Chambi Khal WC (RD) (SP46222-ADB) Lohagara, Chittagong EMP Complied Restoration done yet to take effect 17. Purba Sarail Madhai WCD (SP41002-ADB) Kalai, Joypurhat EMP Complied Restoration done yet to take effect Chak Gobindapur Aldadpur WCD 18. Sadullahpur, Gaibandha EMP Complied Restoration done yet to take effect (SP41004-ADB) 19. Noapara Hazirdhara WCD (SP41011-ADB) Puthia, Rajshahi EMP Complied Restoration done yet to take effect 20. Ulushi Khal WCD (SP42020-IFAD-2) Tarash Sirajganj EMP Complied Restoration done yet to take effect Clearing path of access for vehicles and pedestrians around construction and ancillary sites 1. Sundary Khal CAD (SP42015-IFAD-2) Kachua, Chandpur EMP Complied Restoration done yet to take effect 2. Fashiakhali CAD (SP42021-ADB) Chokoria, Cox’s Bazar EMP Complied Restoration done yet to take effect Mohandanga Panna Beel CAD (SP44087- 3. Sadar, Chapai Nawabganj EMP Complied Restoration done yet to take effect ADB) 4. Pashchimj Joar CAD (SP44093-ADB) Mirersarai, Chittagong EMP Complied Restoration done yet to take effect 5. Sapleza DR (SP42022-IFAD-1) Mothbaria, Pirojpur EMP Complied Restoration done yet to take effect 6. Belgapur Julupara DR (SP43031-ADB) Niamatpur, Naogaon EMP Complied Restoration done yet to take effect 7. Badrabati (north) DR (SP43037-IFAD-2) Tarash, Sirajganj EMP Complied Restoration done yet to take effect 8. Arua Kamini DR (SP46253-IFAD-1) Amtoly, Barguna EMP Complied Restoration done yet to take effect 9. Kata Khal FMD (SP42018-ADB) Mujibnagar, Meherpur EMP Complied Restoration done yet to take effect

18

Environmental Sl. Status of EMP Status of Item Location Enhancement No Compliance Restoration (Tree plantation) 10. Dholdholia FMD (SP43055-IFAD-2) Saghata, Gaibandha EMP Complied Restoration done yet to take effect 11. Adabaria FMD (SP43057-IFAD-2) Bauphal, Patuakhali EMP Complied Restoration done yet to take effect 12. Dhonkundi Beel FMD (SP44078-ADB) Sherpur, Bogra EMP Complied Restoration done yet to take effect Bhelabari Durgapur WC (RD) (SP41006- 13. Aditmari, Lalmonirhat EMP Complied Restoration done yet to take effect ADB) Pashchim Dighulia WC (RD) (SP43047- 14. Ukhia, Cox’s Bazar EMP Complied Restoration done yet to take effect IFAD-2) 15. Hangor Khal WC (RD) (SP46214-ADB) Lohagara, Chittagong EMP Complied Restoration done yet to take effect 16. Chambi Khal WC (RD) (SP46222-ADB) Lohagara, Chittagong EMP Complied Restoration done yet to take effect 17. Purba Sarail Madhai WCD (SP41002-ADB) Kalai, Joypurhat EMP Complied Restoration done yet to take effect Chak Gobindapur Aldadpur WCD 18. Sadullahpur, Gaibandha EMP Complied Restoration done yet to take effect (SP41004-ADB) 19. Noapara Hazirdhara WCD (SP41011-ADB) Puthia, Rajshahi EMP Complied Restoration done yet to take effect 20. Ulushi Khal WCD (SP42020-IFAD-2) Tarash Sirajganj EMP Complied Restoration done yet to take effect Restoring of borrow areas 1. Sundary Khal CAD (SP42015-IFAD-2) Kachua, Chandpur EMP Complied Restoration done yet to take effect 2. Fashiakhali CAD (SP42021-ADB) Chokoria, Cox’s Bazar EMP Complied Restoration done yet to take effect 3. Mohandanga Panna Beel CAD (SP44087-ADB) Sadar, Chapai Nawabganj EMP Complied Restoration done yet to take effect 4. Pashchimj Joar CAD (SP44093-ADB) Mirersarai, Chittagong EMP Complied Restoration done yet to take effect 5. Sapleza DR (SP42022-IFAD-1) Mothbaria, Pirojpur EMP Complied Restoration done yet to take effect 6. Belgapur Julupara DR (SP43031-ADB) Niamatpur, Naogaon EMP Complied Restoration done yet to take effect 7. Badrabati (north) DR (SP43037-IFAD-2) Tarash, Sirajganj EMP Complied Restoration done yet to take effect 8. Arua Kamini DR (SP46253-IFAD-1) Amtoly, Barguna EMP Complied Restoration done yet to take effect 9. Kata Khal FMD (SP42018-ADB) Mujibnagar, Meherpur EMP Complied Restoration done yet to take effect 10. Dholdholia FMD (SP43055-IFAD-2) Saghata, Gaibandha EMP Complied Restoration done yet to take effect 11. Adabaria FMD (SP43057-IFAD-2) Bauphal, Patuakhali EMP Complied Restoration done yet to take effect 12. Dhonkundi Beel FMD (SP44078-ADB) Sherpur, Bogra EMP Complied Restoration done yet to take effect 13. Bhelabari Durgapur WC (RD) (SP41006-ADB) Aditmari, Lalmonirhat EMP Complied Restoration done yet to take effect Pashchim Dighulia WC (RD) (SP43047- 14. Ukhia, Cox’s Bazar EMP Complied Restoration done yet to take effect IFAD-2) 15. Hangor Khal WC (RD) (SP46214-ADB) Lohagara, Chittagong EMP Complied Restoration done yet to take effect 16. Chambi Khal WC (RD) (SP46222-ADB) Lohagara, Chittagong EMP Complied Restoration done yet to take effect 17. Purba Sarail Madhai WCD (SP41002-ADB) Kalai, Joypurhat EMP Complied Restoration done yet to take effect Chak Gobindapur Aldadpur WCD 18. Sadullahpur, Gaibandha EMP Complied Restoration done yet to take effect (SP41004-ADB) 19. Noapara Hazirdhara WCD (SP41011-ADB) Puthia, Rajshahi EMP Complied Restoration done yet to take effect 20. Ulushi Khal WCD (SP42020-IFAD-2) Tarash Sirajganj EMP Complied Restoration done yet to take effect

19

Annex- C

Water Quality Impact Monitoring Report Water Resources Development Project under LGED

Jan- April- Base / Subproject ID, Name & Water Environment Deptt. Year Parameter March( June( Observed Location Type Standard Q1) Q2) Range 1. SP43056, Latifpur- Etbarpur Khal Subproject , Chandina Total Dissolved solids 147 ~ 2018 Surface 147 210 <2000 (TDS), mg/L 210 Temperature, oC 25 28 25 ~ 28 20~30 Salinity, ppm 106 80 80 ~ 106 300~1000 Phosphate (Ph4), mg/L 1 1 1 ~ 1 <6 pH 7.3 6.7 6.7 ~ 7.3 6.5 ~ 8.5 Nitrate, mg/L <10 <10 10 ~ 10 10 Electrical Conductivity 221 ~ 221 275 400~1000 (EC), µs/cm 275 Dissolved Oxygen, mg/L 6.4 5.2 5.2 ~ 6.4 4~6 105 ~ CaCo3(Hardness), mg/L 105 110 80~120 110 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05 2. SP43059, Kedarpur- Gobindapur Subproject Comilla, Chandina Total Dissolved solids 200 ~ 2018 Surface 205 200 <2000 (TDS), mg/L 205 25.1 ~ Temperature, oC 25.1 28.7 20~30 28.7 140 ~ Salinity, ppm 147 140 300~1000 147 Phosphate (Ph4), mg/L 1 1 1 ~ 1 <6 pH 7.3 7.1 7.1 ~ 7.3 6.5 ~ 8.5 Nitrate, mg/L <10 <10 <10 ~<10 10 Electrical Conductivity 280 ~ 308 280 400~1000 (EC), µs/cm 308 Dissolved Oxygen, mg/L 6.7 6.6 6.6 ~ 6.7 4~6 130 ~ CaCo3(Hardness), mg/L 135 130 80~120 135 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05 3. SP45147, Barkarai-Derpar Kaduti Subproject Comilla, Chandina Total Dissolved solids 310 ~ 2018 Surface 330 310 <2000 (TDS), mg/L 330 25.3 ~ Temperature, oC 25.3 28.2 20~30 28.2 230 ~ Salinity, ppm 237 230 300~1000 237 Phosphate (Ph4), mg/L 1 1 1 ~ 1 <6 pH 7.7 6.7 6.7 ~ 7.7 6.5 ~ 8.5 Nitrate, mg/L <10 <10 <10 ~<10 10 Electrical Conductivity 380 ~ 495 380 400~1000 (EC), µs/cm 495 Dissolved Oxygen, mg/L 4.7 4.9 4.7 ~ 4.9 4~6 147 ~ CaCo3(Hardness), mg/L 150 147 80~120 150 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05 4. SP45154, Harina Changagachia Sub-Project Comilla, Chandina Total Dissolved solids 135 ~ 2018 Surface 140 135 <2000 (TDS), mg/L 140

20

Jan- April- Base / Subproject ID, Name & Water Environment Deptt. Year Parameter March( June( Observed Location Type Standard Q1) Q2) Range 24.8 ~ Temperature, oC 24.8 29.2 20~30 29.2 101 ~ Salinity, ppm 101 110 300~1000 110 Phosphate (Ph4), mg/L 1 1 1 ~ 1 <6 pH 7.8 7.6 7.6 ~ 7.8 6.5 ~ 8.5 Nitrate, mg/L <10 <10 <10 ~<10 10 Electrical Conductivity 211 ~ 211 460 400~1000 (EC), µs/cm 460 Dissolved Oxygen, mg/L 6.5 5.8 5.8 ~ 6.5 4~6 165 ~ CaCo3(Hardness), mg/L 165 1060 80~120 1060 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05 5. SP45156, Orain Golicho Noagaon Subproject Comilla, Chandina Total Dissolved solids 340 ~ 2018 Surface 344 340 <2000 (TDS), mg/L 344 24.9 ~ Temperature, oC 24.9 28.9 20~30 28.9 240 ~ Salinity, ppm 248 240 300~1000 248 Phosphate (Ph4), mg/L 1 1 1 ~ 1 <6 pH 7.5 7.1 7.1 ~ 7.5 6.5 ~ 8.5 Nitrate, mg/L <10 <10 <10 ~<10 10 Electrical Conductivity 517 ~ 517 520 400~1000 (EC), µs/cm 520 Dissolved Oxygen, mg/L 4.4 4.2 4.2 ~ 4.4 4~6 160 ~ CaCo3(Hardness), mg/L 165 160 80~120 165 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05 6. SP45176, Deowra CAD Subproject Comilla, Muradnagar Total Dissolved solids 116 ~ 2018 Surface 116 134 <2000 (TDS), mg/L 134 24.3 ~ Temperature, oC 24.3 28.5 20~30 28.5 Salinity, ppm 83 96 83 ~ 96 300~1000 Phosphate (Ph4), mg/L 1 1 1 ~ 1 <6 pH 7.1 6.9 6.9 ~ 7.1 6.5 ~ 8.5 Nitrate, mg/L <10 <10 <10 ~<10 10 Electrical Conductivity 174 ~ 174 201 400~1000 (EC), µs/cm 201 Dissolved Oxygen, mg/L 3 3.8 3 ~ 3.8 4~6 CaCo3(Hardness), mg/L 75 80 75 ~ 80 80~120 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05 7. SP45177, Dhakshin Trish CAD Subproject Comilla, Muradnagar Total Dissolved solids 108 ~ 2018 Surface 108 136 <2000 (TDS), mg/L 136 23.6 ~ Temperature, oC 23.6 28.7 20~30 28.7 Salinity, ppm 78 97 78 ~ 97 300~1000 Phosphate (Ph4), mg/L 1 1 1 ~ 1 <6 pH 7.2 6.6 6.6 ~ 7.2 6.5 ~ 8.5 Nitrate, mg/L <10 <10 <10 ~<10 10 Electrical Conductivity 164 ~ 164 204 400~1000 (EC), µs/cm 204 Dissolved Oxygen, mg/L 4.7 3.1 3.1 ~ 4.7 4~6 CaCo3(Hardness), mg/L 75 160 75 ~ 160 80~120 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05 8. SP45190, Nababpur-

21

Jan- April- Base / Subproject ID, Name & Water Environment Deptt. Year Parameter March( June( Observed Location Type Standard Q1) Q2) Range Kaliarchar Subproject Comilla, Chandina Total Dissolved solids 190 ~ 2018 Surface 226 190 <2000 (TDS), mg/L 226 Temperature, oC 24.8 29 24.8 ~ 29 20~30 Salinity, ppm 162 98 98 ~ 162 300~1000 Phosphate (Ph4), mg/L 1 1 1 ~ 1 <6 pH 7.4 7.4 7.4 ~ 7.4 6.5 ~ 8.5 Nitrate, mg/L <10 <10 <10 ~<10 10 Electrical Conductivity 240 ~ 340 240 400~1000 (EC), µs/cm 340 Dissolved Oxygen, mg/L 7.1 6.9 6.9 ~ 7.1 4~6 CaCo3(Hardness), mg/L 150 95 95 ~ 150 80~120 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05 9. SP41005, Kanakdia FMD Subproject Patuakhali, Bauphal Total Dissolved solids 292 ~ 2018 Surface 292 <2000 (TDS), mg/L 292 23.2 ~ Temperature, oC 23.2 28.2 20~30 28.2 116 ~ Salinity, ppm 116 116 300~1000 116 Phosphate (Ph4), mg/L 1 1 1 ~ 1 <6 pH 7.2 7.2 7.2 ~ 7.2 6.5 ~ 8.5 Nitrate, mg/L <10 <10 <10 ~<10 10 Electrical Conductivity 262 ~ 262 262 400~1000 (EC), µs/cm 262 Dissolved Oxygen, mg/L 5.1 5.1 5.1 ~ 5.1 4~6 CaCo3(Hardness), mg/L 60 60 60 ~ 60 80~120 23.2 ~ 2018 Ground Temperature, oC 23.2 28.2 20~30 28.2 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05

10. SP43057, Adabaria Subproject Patuakhali, Bauphal Total Dissolved solids 264 ~ 2018 Surface 264 270 <2000 (TDS), mg/L 270 Temperature, oC 23.9 29 23.9 ~ 29 20~30 120 ~ Salinity, ppm 120 120 300~1000 120 Phosphate (Ph4), mg/L 1 1 1 ~ 1 <6 pH 7.7 7.5 7.5 ~ 7.7 6.5 ~ 8.5 Nitrate, mg/L <10 <10 <10 ~<10 10 Electrical Conductivity 255 ~ 278 255 400~1000 (EC), µs/cm 278 Dissolved Oxygen, mg/L 4.6 4.6 4.6 ~ 4.6 4~6 CaCo3(Hardness), mg/L 90 75 75 ~ 90 80~120

2018 Ground Temperature, oC 23.9 27 23.9 ~ 27 20~30 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05

11. SP43058, Shabupura Khal Subproject Patuakhali, Bauphal Total Dissolved solids 275 ~ 2018 Surface 285 275 <2000 (TDS), mg/L 285 Temperature, oC 23.8 28 23.8 ~ 28 20~30 105 ~ Salinity, ppm 108 105 300~1000 108 Phosphate (Ph4), mg/L 1 1 1 ~ 1 <6 pH 7.6 7.6 7.6 ~ 7.6 6.5 ~ 8.5 Nitrate, mg/L <10 <10 <10 ~<10 10 Electrical Conductivity 264 270 264 ~ 400~1000

22

Jan- April- Base / Subproject ID, Name & Water Environment Deptt. Year Parameter March( June( Observed Location Type Standard Q1) Q2) Range (EC), µs/cm 270 Dissolved Oxygen, mg/L 4.9 4.9 4.9 ~ 4.9 4~6 CaCo3(Hardness), mg/L 60 60 60 ~ 60 80~120 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05

2018 Ground Temperature, oC 23.8 28 23.8 ~ 28 20~30 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05

12. SP43060, Ponahura Subproject Patuakhali, Bauphal Total Dissolved solids 260 ~ 2018 Surface 270 260 <2000 (TDS), mg/L 270 24.3 ~ Temperature, oC 24.3 27.3 20~30 27.3 104 ~ Salinity, ppm 104 104 300~1000 104 Phosphate (Ph4), mg/L 1 1 1 ~ 1 <6 pH 7.8 7.7 7.7 ~ 7.8 6.5 ~ 8.5 Nitrate, mg/L <10 <10 <10 ~<10 10 Electrical Conductivity 255 ~ 255 255 400~1000 (EC), µs/cm 255 Dissolved Oxygen, mg/L 5.2 5.2 5.2 ~ 5.2 4~6 CaCo3(Hardness), mg/L 90 90 90 ~ 90 80~120 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05

24.3 ~ 2018 Ground Temperature, oC 24.3 27.3 20~30 27.3 <0.05~ Arsenic, mg/L <0.05 <0.05 0.05 <0.05

23