FDOT Palm Beach County Traffic Report February 19 through February 26, 2021

PALM BEACH COUNTY, Fla. – Palm Beach County traffic will be affected this week by ongoing construction projects and maintenance work, Florida Department of Transportation (FDOT) officials report. Closures will be in effect on I-95 and in other areas throughout Palm Beach County for construction activities.

For around-the-clock, real-time, I-95 traffic information, call 511. To view real-time video of I-95 in Palm Beach County, visit the Florida Department of Transportation’s Palm Beach SMART SunGuide Transportation Management Center (TMC) website at www.smartsunguide.com. FDOT and the SunGuide™ Partners provide these free services. For updated lane closure information, please refer to www.d4fdot.com. Follow us on Twitter and Instagram @MyFDOT_SEFL, and Facebook @MyFDOTSEFL.

SAFETY MESSAGE Stop Speeding Before It Stops You

Speeding is generally defined as driving in excess of the posted speed limit or driving too fast for conditions and can have dangerous consequences, including: Reducing the ability to navigate curves or around obstacles in the roadway; Extending the distance traveled before a vehicle can stop; Increasing the risk of crashes and injuries because other vehicles and pedestrians may not be able to judge distance accurately. Be alert, watch for, and obey speed limit signs. Use extra caution in school zones, residential areas, and on secondary roads. Remember that there is a reason for posted speed limits. Speed limits are designed to protect all – drivers, passengers, and pedestrians. See speeding tip card attached and visit https://www.fdot.gov/safety/speeding-and-aggressive-driving for more information.

CONSTRUCTION PROJECTS

INTERSTATE 95

1. I-95 from south of SW 10th Street in the City of Deerfield Beach to south of in the City of Boca Raton (95 Express Phase 3B-1) Description: Work on this 4.8-mile 95 Express project includes widening and converting the existing I- 95 HOV Lanes to Managed Lanes which will result in two tolled Express Lanes in each direction; the number of General Use lanes will remain the same. Other project improvements include bridge widenings at Palmetto Park Road and Camino Real, complete bridge replacement at the Hillsboro Canal, noise wall construction, portable traffic monitoring sites, toll gantry installation, Intelligent Transportation System (ITS) installation, ramp signaling at the I-95 entrance ramps from Palmetto Park Road, Express Lane markers and landscape relocation. For more information, please contact I- 95Community Outreach Specialist Andrea Pacini at (561) 214-3358 or [email protected]. Cost/Completion: $102 million / Completion is expected in spring 2022. Traffic Impact: I-95 will have three lanes closed in each direction nightly, as needed, Sunday through Thursday nights, with the first lane closing at 9:30 p.m., the second lane closing at 10:30 p.m., and the third lane closing at 11:30 p.m. until 5:30 a.m. I-95 northbound from south of SW 10th Street to south of Glades Road is in final configuration. I-95 Northbound Full Closure Notice: I-95 northbound lanes at Hillsboro Boulevard will be closed to traffic overnight, Tuesday, Feb. 23 and Wednesday, Feb. 24 for overhead sign structure installation. The first lane will close at 9:30 p.m., the second lane will close at 10:30 p.m., and all lanes will be closed by 11:30 p.m., reopening by 5:30 a.m. each morning. Traffic will be detoured via the northbound exit ramp to Hillsboro Boulevard west, and Palmetto Park Road. FHP will be onsite to assist motorists. Thursday, Feb. 25 will be used as a contingency night if needed. Please see detour flyer attached. I-95 Northbound Full Closure Advanced Notice: I-95 northbound lanes at Hillsboro Boulevard will be closed to traffic overnight, Tuesday, March 2 and Wednesday, March 3 for overhead sign structure installation. The first lane will close at 9:30 p.m., the second lane will close at 10:30 p.m., and all lanes will be closed by 11:30 p.m., reopening by 5:30 a.m. each morning. Traffic will be detoured via the northbound exit ramp to Hillsboro Boulevard west, Military Trail and Palmetto Park Road. FHP will be onsite to assist motorists. Thursday, March 4 will be used as a contingency night if needed. Please see detour flyer attached. Arterial Road Traffic Impact: Palmetto Park Road at I-95 will have two lanes closed in each direction nightly, as needed, Sunday through Thursday. The first lane will close at 9 p.m., and the second lane will close at 10:30 p.m. All lanes will be opened by 5:30 a.m. Palmetto Park Road at I-95 will have one lane closed in each direction daily, as needed, 9:30 a.m. until 3:30 p.m., Monday through Friday. Camino Real at I-95 will have one lane closed in each direction daily, as needed, 9:30 a.m. until 4 p.m., Monday through Friday. Ramp Impact: The I-95 southbound exit ramp to Palmetto Park Road will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Motorists will be detoured via I-95 southbound, Hillsboro Boulevard, Military Trail and Palmetto Park Road. FHP will be on site to assist motorists. The I-95 southbound entrance ramp from westbound Palmetto Park Road will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Motorists will be detoured via Military Trail and Hillsboro Boulevard. FHP will be on site to assist motorists. The I-95 southbound entrance ramp from eastbound Palmetto Park Road will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Motorists will be detoured via Military Trail and Hillsboro Boulevard. FHP will be on site to assist motorists. The northbound entrance ramp from eastbound and westbound Palmetto Park Road will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Traffic will be detoured via I-95 southbound to Hillsboro Boulevard to I-95 northbound. The I-95 northbound exit ramp to westbound Hillsboro Boulevard will be closed nightly, 11 p.m. until 5 a.m., Tuesday through Thursday. Motorists will be detoured via I-95, Palmetto Park Roadand Military Trail. FHP will be on site to assist motorists. The I-95 northbound entrance ramp from eastbound Hillsboro Boulevard will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Motorists will be detoured via Military Trail and Palmetto Park Road. FHP will be on site to assist motorists. The I-95 northbound exit ramp to eastbound Hillsboro Boulevard will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Motorists will be detoured via Palmetto Park Road and South . FHP will be on site to assist motorists. The I-95 southbound entrance ramp from westbound Hillsboro Boulevard will be closed nightly, 11 p.m. until 5 a.m. Sunday through Thursday. Motorists will be detoured via Hillsboro Blvd, Military Trail and SW 10th Street. FHP will be on site to assist motorists. The I-95 southbound entrance ramp from eastbound Hillsboro Boulevard will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Motorists will be detoured via Military Trail and SW 10th Street. FHP will be on site to assist motorists. The I-95 southbound exit ramp to SW 10th Street will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Motorists will be detoured via Hillsboro Blvd and Military Trail. FHP will be on site to assist motorists. The I-95 southbound entrance ramp from eastbound and westbound SW 10th Street will be closed nightly, 11 p.m. until 5 a.m., Sunday through Thursday. Motorists will be detoured via SW 10th Street, Military Trail and . FHP will be on site to assist motorists. *Please note that ramp closures will be performed as needed per nighttime construction operations; consecutive ramps will not be closed at the same time.

2. I-95 from south of Glades Road to south of Linton Boulevard and SR 808/Glades Road from NW 22nd Way to West University Drive in the Cities of Boca Raton and Delray Beach (95 Express Phase 3B-2) Description: 95 Express Lanes Phase 3B-2 will extend the existing Express Lanes north from just south of Glades Road to just south of Linton Boulevard in Palm Beach County. One lane will be added and the High Occupancy Vehicle (HOV) lane will be converted to create two Express Lanes in each direction. The number of General Use lanes will remain the same. Access to the Express Lanes will be provided via two designated ingress and egress locations—between Glades Road and and between and Linton Boulevard. The scope of work includes reconfiguration of the SR 808/Glades Road Interchange to a Diverging Diamond Interchange (DDI). Additional project improvements include overhead sign structure installation, Intelligent Transportation System (ITS) and Express Lane markers, new signalization, lighting, signing and pavement markings and ramp signalization at five interchanges from Glades Road to Linton Boulevard. Shoulder-mounted sound barrier walls will be constructed along I-95 northbound between Clint Moore Road and Linton Boulevard, ground-mounted sound walls will be installed on the south side of Yamato Road east of I- 95 adjacent to the University Heights Community and along I-95 northbound south of Linton Boulevard adjacent to the Tierra Verde Community. The Clint Moore Road Bridge over I-95 will be fully reconstructed and the Glades Road bridge over the Regional Transportation Authority (SFRTA) railroad tracks and Military Trail and the I-95 bridge over the C-15 Canal (between Peninsula Drive and Linton Boulevard) will be widened. For more information, please contact I-95 Community Outreach Specialist Andrea Pacini at (561) 214-3358 or [email protected]. Cost/Completion: $148 million. Completion is expected in late 2023. Traffic Impact: I-95 will have up to four lanes closed in each direction nightly as needed for paving, 9 p.m. until 6 a.m. Sunday through Thursday. The first lane will close at 9 p.m., the second lane will close at 9:30 p.m., and the third and fourth lane will close at 10 p.m. I-95 northbound from Yamato Road to Linton Boulevard is in a new traffic pattern with traffic shifted to the outside to allow for median construction. This configuration is anticipated to be in place through summer 2021. I-95 Northbound Full Closure Notice: I-95 northbound at Glades Road will be closed to traffic overnight Thursday, Feb. 25 and Monday, March 1 for overhead sign structure removal. Motorists will be detoured via the I-95 northbound exit ramp to Glades Road, Federal Highway/US-1 and Yamato Road. Thursday, March 4 and Sunday, March 7 will be used as contingency nights if needed. FHP will be on site to assist motorists. Please see detour flyer attached. Glades Road Impact: Advanced Notice: Westbound Glades Road, between NW 22nd Way and West University Drive, will be shifted inside towards the median to allow for outside widening, beginning Monday, March 1. Please see informational flyer attached. Advanced Notice: Westbound Glades Road, between NW 22nd Way and West University Drive, will have one lane closed daily, 9:30 a.m. until 4 p.m., Monday through Friday and from 6 a.m. until 9 p.m. Saturday and Sunday, beginning Monday, March 1. Advanced Notice: Westbound Glades Road, between NW 22nd Way and West University Drive, will have one lane closed nightly at 9 p.m. and two lanes closed at 10 p.m., until 6 a.m., Sunday through Saturday, beginning Monday, March 1. Clint Moore Road Impact: Advanced Notice: The Clint Moore Road bridge over I-95 will be closed completely for reconstruction beginning 5 a.m., Monday morning, March 8, 2021. Crews are permitted to work 7 a.m. until 6 p.m. Monday through Friday and 8 a.m. until 7 p.m. on Saturday. No work is permitted on Sundays or holidays. Emergency access for first responders will be maintained throughout the duration of the closure. Westbound traffic will be detoured via NW 2nd Avenue, Yamato Road and Congress Avenue. Eastbound traffic will be detoured via Park of Commerce Boulevard, Congress Avenue, Yamato Road and NW 2nd Avenue. Local neighborhood access will be maintained; only the approaches and bridge over I-95 will be closed. The reconstruction of this bridge is anticipated to be completed in spring 2022. Please see detour flyer attached. Ramp Impact: The I-95 northbound entrance ramp from westbound Glades Road will be closed nightly as needed for paving, 11 p.m. until 5 a.m., Sunday through Thursday. Traffic will be detoured via Powerline Road and Jog Road. FHP will be on site to assist motorists. The I-95 northbound exit ramp to Spanish River Boulevard will be closed nightly as needed for paving, 11 p.m. until 5 a.m., Sunday and Thursday. Traffic will be detoured via I-95 north, Yamato Road east, US-1 and Spanish River Boulevard. FHP will be onsite to assist motorists. The I-95 northbound entrance ramp from Congress Avenue and Peninsula Corp. Drive will be closed nightly as needed, 11 p.m. until 5 a.m., Sunday and Thursday. Traffic will be detoured via I-95 and Yamato Road. FHP will be on site to assist motorists. The I-95 northbound exit ramp to Congress Avenue will be closed nightly as needed for paving, 11 p.m. until 5 a.m., Sunday and Thursday. Traffic will be detoured via I-95 and Linton Boulevard. FHP will be on site to assist motorists. Consecutive ramps will not be closed at the same time. The I-95 northbound entrance ramp from eastbound Glades Road will be closed nightly as needed,11 p.m. until 5 am., Sunday and Thursday. Traffic will be detoured via Glades Road east, N. Federal Highway and Yamato Road. FHP will be on site to assist motorists. The I-95 southbound entrance ramp from westbound Glades Road will be closed nightly as needed, 11 p.m. until 5 a.m., Sunday and Thursday. Traffic will be detoured via Glades Road west, Powerline Road and Palmetto Park Road. FHP will be on site to assist motorists. The I-95 southbound entrance ramp from eastbound Yamato Road/Spanish River Boulevard will be closed nightly as needed, 11 p.m. until 5 a.m., Sunday through Thursday. Traffic will be detoured via Yamato Road east, Federal Highway/U.S. 1 south and Glades Road. FHP will be on site to assist motorists. The I-95 northbound exit ramp to Yamato Road will be closed nightly as needed, 11 p.m. until 5 a.m., Sunday through Thursday. Traffic will be detoured via Congress Avenue, Peninsula Corp Drive, Congress Avenue and Yamato Road. FHP will be on site to assist motorists.

3. I-95 Interchange Improvements at Atlantic Avenue in the City of Delray Beach Description: Work includes widening the I-95 northbound entrance ramp from Atlantic Avenue, creating a dedicated lane for I-95 northbound and southbound access from westbound Atlantic Avenue, construction of two turn lanes from westbound Atlantic Avenue; one to northbound Congress Avenue and one to southbound Congress Avenue, milling, resurfacing, pavement markings for improved safety and visibility, realigned crosswalks for improved pedestrian safety, internally illuminated and electronic display signs, signalization, pedestrian detectors, and traffic monitoring sites. Pavement markings for bike lanes will be included throughout the project. For more information, please contact I-95 Community Outreach Specialist Andrea Pacini at (561) 214- 3358 [email protected]. Cost/Completion: $5.2 million. Completion is expected in spring 2021. Traffic Impact:

Atlantic Avenue from 13th Avenue to NW 23rd Avenue will have two through lanes closed daily, as needed, 10 a.m. until 2:30 p.m. and nightly, as needed, 9 p.m. until 5 a.m., Sunday through Saturday. Westbound Atlantic Avenue approaching I-95 has a new permanent configuration. The northernmost, or far right lane, of westbound Atlantic Avenue which begins just west of NW 12th Avenue is now designated as I-95 entrance ramp ingress only. Vehicles traveling in this lane will not be able to perform a through movement to continue west on Atlantic Avenue due to the installation of a concrete traffic separator; this lane is exclusively designated for vehicles wishing to access I-95 northbound or southbound. Please note that motorists must decide on their selected movement before they reach NW 12th Avenue. The Atlantic Avenue north sidewalk from 12th Avenue to NW 23 Avenue is closed completely for roadway reconstruction. Pedestrians will be detoured to the south sidewalk via existing crosswalks. Congress Avenue from NW 1st Street to Lowson Boulevard may have one lane closed daily in each direction, as needed, daily, 10 a.m. until 2:30 p.m. and nightly, 9 p.m. until 5 a.m., Sunday through Saturday. NW 12th Avenue will have the westbound turn lane closed, nightly as needed, 9 p.m. to 5 a.m., Sunday through Saturday. The I-95 northbound entrance ramp from Atlantic Avenue will have one lane closed nightly, as needed, 9 p.m. until 5 a.m., Sunday through Saturday.

4. I-95 Milling and Resurfacing from North of Gateway Boulevard to Lantana Road in the City of Boynton Beach and Town of Lantana Description: This 2.35-mile project includes milling and resurfacing I-95 in both directions as well as the entrance and exit ramps at Hypoluxo Road and Lantana Road. This project also includes median lighting upgrades. For more information, please contact Community Outreach Specialist Daniela Silva at (786) 441-3088 or [email protected]. Cost/ Completion: $11.9 million. Completion is expected in spring 2022. I-95 Traffic Impact: I-95 in each direction will have intermittent shoulder closures, daily and nightly, as needed, Sunday through Thursday. I-95 in each direction will have up to four lanes closed nightly, 8:30 p.m. until 6 a.m. Sunday through Thursday. One lane of I-95 may close at 8:30 p.m., two lanes may closeat 10 p.m. until 5:30 a.m. and three lanes may close 12 a.m. until 5 a.m. All lanes will reopen by 6 a.m. Advanced Notice: I-95 in each direction will have up to four lanes closed nightly, 8:30 p.m. until 6 a.m. beginning Sunday night, Feb. 28. One lane may close at 8:30 p.m., two lanes may close at 10 p.m. until 5:30 a.m., three or more lanes may close at 12 a.m. until 5a .m. all lanes will re-open by 6 a.m. Ramp Impact: The I-95 southbound exit ramp to Gateway Boulevard will be closed to traffic nightly as needed, Sunday through Thursday for survey and paving activities. Traffic will be detoured via the I-95 southbound exit ramp to Hypoluxo Road. Motorists can access Gateway Boulevard by traveling eastbound to US-1/Federal Highway or westbound via Congress Avenue then south to Gateway Boulevard. FHP will be onsite to assist motorists. The I-95 southbound exit ramp to Hypoluxo Road will be closed nightly, as needed, 9:30 p.m. until 5 a.m., Sunday through Thursday for survey and paving activities. Traffic will be detoured via the I-95 southbound exit ramp to Gateway Boulevard. Motorists can then access Hypoluxo Road by traveling eastbound to US-1/Federal Highway or westbound to Congress Avenue and north to Hypoluxo Road. FHP will be onsite to assist motorists. The I-95 northbound entrance ramp from Gateway Boulevard will be closed to traffic nightly, as needed, 9:30 p.m. until 5 a.m., Sunday through Thursday for survey and paving activities. Motorists traveling westbound on Gateway Boulevard will be detoured via Congress Avenue and the I-95 northbound entrance ramp from Hypoluxo Road. Eastbound Gateway Boulevard traffic will be detoured via US-1/Federal Highway and the I-95 northbound entrance ramp from Hypoluxo Road. FHP will be onsite to assist motorists. I-95 northbound entrance ramp from Hypoluxo Road will be closed to traffic nightly, as needed, 9:30 p.m. until 5 a.m., Sunday through Thursday for survey and paving activities. Westbound Hypoluxo Road traffic will be detoured via Congress Avenue and the I-95 northbound entrance ramp from Lantana Road. Eastbound Hypoluxo Road traffic will be detoured via Federal Highway/US-1 and the I-95 northbound entrance ramp from Lantana Road. FHP will be onsite to assist motorists. The I-95 northbound exit ramp to Lantana Road will be closed nightly, as needed, 9:30 p.m. until 5 a.m., Sunday through Thursday for survey and paving activities. Traffic will be detoured via the I-95 northbound exit ramp to Hypoluxo Road. Motorists can then access Lantana Road by traveling eastbound to US-1/Federal Highway or westbound to Congress Avenue and north to Lantana Road. FHP will be onsite to assist motorists. Please note that ramp closures will be closed as needed per paving production; consecutive ramps will not be closed at the same time.

5. I-95 Bridge Beam Replacement at 10th Avenue North in the City of Lake Worth Beach

Description: This 0.095-mile project includes removing and replacing the existing damaged bridge beam and replacing the bridge deck and barrier wall on the 10th Avenue North bridge over I-95 northbound. For more information, please contact Community Outreach Specialist Daniela Silva at (786) 441-3088 or [email protected].

Cost/ Completion: $444,903.43. Completion is expected in spring 2021. Arterial Road Impact: 10th Avenue North at I-95 will have one eastbound lane closed nightly, 9 p.m. until 5 a.m., Sunday through Thursday. To ensure pedestrian and cyclist safety, 10th Avenue North at I-95 will have the eastbound bicycle lane and south sidewalk closed for the duration of the project. Pedestrians will be detoured to the north sidewalk and bicyclists will temporarily share the eastbound general traffic lane for a 150-foot section.

6. SR 9/I-95 over Donald Ross Road Bridge Painting Project Description: This project in Palm Beach Gardens and Jupiter began Sept. 9, 2020. Improvements consist of cleaning and painting the steel and concrete portions of the northbound and southbound I- 95 bridges over Donald Ross Road. Cost/Completion: $613,162 / Spring 2021 Traffic Impact: Two eastbound lanes will be closed on Donald Road at the I-95 overpass 8 p.m. to 6:30 a.m. Sunday through Thursday for painting activities. Two westbound lanes will be closed on Donald Road at the I-95 overpass 8 p.m. to 6:30 a.m. Sunday through Thursday for painting activities. Two lanes of the southbound I-95 exit ramp to eastbound Donald Ross Road will be closed 8 p.m. to 6:30 a.m. Sunday through Thursday for painting activities. One lane of the northbound I-95 exit ramp to westbound Donald Ross Road will be closed 8 p.m. to 6:30 a.m. Sunday through Thursday for painting activities. For more information, please contact Community Outreach Specialist Angel Streeter Gardner at (561) 886-8773 [email protected].

7. I-95 Lighting and Roadway Improvements Project from south of State Road 706/ to County Road 708/SE Bridge Road Description: This 11.59-mile I-95 improvements project started September 9, 2020 in Jupiter and Hobe Sound. Work includes installing new roadway lighting with LED luminaires, replacing the high mast lighting system with a conventional LED roadway lighting system, extending the northbound I-95 merge lane just north of Indiantown Road, extending the deceleration distances for the I-95 northbound to westbound Indiantown Road exit ramp and the I-95 southbound to eastbound Indiantown Road exit ramp, and installing wrong way vehicle detection systems at the Indiantown Road and SE Bridge Road I-95 interchanges and new advanced warning signage. Cost/Completion: $12.3 million. Completion is expected in spring 2022. Traffic Impact: The shoulder in both directions of I-95 will be intermittently closed Monday through Friday from 6:30 a.m. to 6 p.m. through Aug. 2021 for temporary asphalt placement, landscaping relocation efforts, and conduit and light pole foundation installations. One lane in either direction of I-95 at the Indiantown Road interchange may be closed Sunday through Thursday night from 10 p.m. to 6 a.m. to facilitate the construction of a minor traffic diversion. For more information, please contact Community Outreach Specialist Kathleen Dempsey at 772-359-5118 or [email protected].

SOUTHERN PALM BEACH COUNTY PROJECTS

8. NE 5th Avenue Sidewalk Improvements on behalf of the City of Boca Raton Description: This 1.1-mile sidewalk improvements project began Monday, January 11, 2021, in the City of Boca Raton. As the Project Sponsor, the City of Boca Raton requested through application to the Palm Beach Transportation Planning Agency, and City Resolution 146-2017, that FDOT District Four design and construct this sidewalk improvement project as part of the Pedestrian Network contained in the City’s Comprehensive Plan. Work includes concrete sidewalk installation on the west side of NE 5th Avenue, driveway and curb & gutter replacement to align with new sidewalk installation, minor signage and pavement marking upgrades, and minor landscaping relocation and irrigation repairs. Cost/Completion: $432,943.86. Completion is expected in fall 2021. Traffic Impact: The southbound lane may be closed, intermittently, 9 a.m. until 4 p.m., Monday through Friday, for construction activities such as concrete pouring for new sidewalk. During this time, a flagging operation will be used to direct traffic northbound and southbound. The contractor is expected to work within one block at a time. Currently, the contractor plans to work between the blocks of NE 6th Street and NE 3rd Street on the south end of the project limits through early March. Please note the contractor may move between these blocks as needed. If the sidewalk needs to be closed within one block, a pedestrian detour will be in place with signage. For more information, please contact Community Outreach Specialist Meredith Cruz at 561-641-6440 or [email protected].

9. US 1 Resurfacing Project from south of Eve Street to south of Harbourside Drive Description: This 0.5-mile roadway improvements project began Monday, June 29, 2020, in the City of Delray Beach. Work includes roadway resurfacing, drainage, signalization and signage improvements, pavement marking upgrades including roadway striping for bike lanes, and sidewalk removal and replacement. Cost/Completion: $1.2 million. Completion is expected in spring 2021. Traffic Impact: One lane may be closed intermittently in each direction, daily, 9 a.m. until 3 p.m., and nightly, 9 p.m. until 6 a.m., Sunday night through Friday. For more information, please contact Community Outreach Specialist Meredith Cruz at 561-641-6440 or [email protected].

10. Swinton Avenue Resurfacing Project Description: This 1.5-mile roadway improvements project began Tuesday, Apr. 14, 2020, from S 10thStreet to 4th Street/Lake Ida Road in the City of Delray Beach. Work includes milling and resurfacing,adding 5-foot wide sidewalk on the west side of the roadway from S 10th Street to S 3rd Street, drainage, signage and pavement marking upgrades including roadway striping for shared use travel lanes, and minor signalization improvements to existing equipment. Cost/Completion: $1.4 million. Completion is expected in early 2021. Traffic Impact: All lanes are open. For more information, please contact Community Outreach Specialist Meredith Cruz at 561-641-6440 or [email protected].

11. Seminole Drive Bridge Replacement Description: This bridge replacement project began Monday, Feb. 3, 2020, between Lantana Road and Tallulah Road in unincorporated Palm Beach County. Work includes full bridge demolition and replacement, and minor widening for bike lane and sidewalk installation. Cost/Completion: $1.3 million. Completion is expected in early 2021. Traffic Impact: Full Bridge Closure: The bridge is closed for reconstruction through early 2021. Motorists may detour via Lawrence Road and Tallulah Road. For more information, please contact Community Outreach Specialist Meredith Cruz at 561-641-6440 or [email protected].

12. State Road 7 Resurfacing Improvements Project from Atlantic Avenue to Boynton Beach Boulevard Description: This 5.09-mile roadway improvements project began Monday, June 24, 2019, in Delray Beach and Boynton Beach. Work includes milling and resurfacing with minor shoulder widening, drainage improvements and lighting upgrades, installation of gravity wall, guardrail, signing and pavement markings, and intersection improvements at Atlantic Avenue and Boynton Beach Boulevard, including traffic monitoring systems and pedestrian detection/signals. Cost/Completion: $7.9 million. Completion is expected in early 2021. Traffic Impact: One lane may be closed in each direction as needed, daily, 7 a.m. until 4 p.m., and nightly, 6 p.m. until 6 a.m., Sunday night through Saturday. For more information, please contact Community Outreach Specialist Meredith Cruz at 561-641-6440 or [email protected].

13. Boynton Beach Boulevard Improvements Project from Congress Avenue to west of Jog Road Description: This 3.7-mile roadway improvements project began Thursday, Aug. 8, 2019, in Boynton Beach. Work included milling and resurfacing, minor widening for bike lane installation, sidewalk, curb and gutter reconstruction, median safety improvements (including partially closing the median opening at Pear Tree Circle), installing directional turn lanes into Lime Tree Condominiums and Bent Tree Villas East, extending the existing turn lane at Bent Tree Drive, drainage, signage, and pavement marking upgrades, minor signalization and lighting improvements, and limited tree removal to allow for median and bike lane safety enhancements. For more information, please contact Community Outreach Specialist Meredith Cruz at 561-641-6440 or [email protected]. Cost/Completion: $8.3 million. This project was final accepted by the Florida Department of Transportation on Tuesday, Feb. 16, 2021.

14. Boynton Beach Boulevard Improvements Project from Lyons Road to Florida’s Turnpike Description: This 1.2-mile roadway improvements project began Sunday, July 12, 2020, in unincorporated Palm Beach County. Work includes milling and resurfacing, minor widening for increased length of the eastbound and westbound turn lanes at the northbound entrance to Florida’s Turnpike, pedestrian pole, guardrail, signage and pavement marking upgrades, including green striping for bike lanes, installation of sidewalk and ADA detectable warning mats, and minor drainage and lighting upgrades. Cost/Completion: $2 million. Completion is expected in spring 2021. Traffic Impact: One lane of Boynton Beach Boulevard may be closed in each direction, 9 a.m. until 4 p.m.,Monday through Friday. One lane of Acme Dairy Road at the Boynton Beach Boulevard intersection may be closed in each direction, 9 a.m. until 4 p.m., Monday through Friday. One lane of Lyons Road at the Boynton Beach Boulevard intersection may be closed in each direction, 9 a.m. until 4 p.m., Monday through Friday. Ramp closures at Florida’s Turnpike: The southbound exit ramp and the northbound entrance and exit ramp at Florida’s Turnpike and Boynton Beach Boulevard, may undergo consecutive full closures, 9 p.m. until 5 a.m., Wednesday night, Feb. 24. The southbound entrance ramp from Boynton Beach Boulevard to Florida’s Turnpike, and outside lane of Boynton Beach Boulevard at Florida’s Turnpike, may be then be closed 9 p.m. until 5 a.m., Thursday night, Feb. 25. Detour Routes: Motorists traveling southbound on Florida’s Turnpike may exit at Lake Worth Road, head west to State Road 7/US 441, and south to Boynton Beach Boulevard. Motorists traveling northbound on Florida’s Turnpike may exit at Atlantic Avenue, west to State Road 7/US 441 and north to Boynton Beach Boulevard and motorists traveling on Boynton Beach Boulevard may detour west to State Road 7/US 441, north to Lake Worth Road, and east to Florida’s Turnpike or south to Atlantic Avenue, and east to Florida’s Turnpike. FHP Troopers will be onsite to monitor traffic during this time. Please note, if there are delays due to weather or other unforeseen impacts, the closures may need to continue the following week, Monday night, Mar. 1, through Thursday night, Mar. 4. Please see detour flyers attached. For more information, please contact Community Outreach Specialist Meredith Cruz at 561-641-6440 [email protected].

15. Fiber Optic Communication Cable Improvements Project Description: This fiber optic communication cable improvements project, which spans over 22 miles in Palm Beach County, began Sunday, July 12, 2020. Work includes the installation of fiber optic cable within existing conduits, and repairs to sections of damaged conduit, at the following locations: Military Trail from Butts Road to Champion Boulevard, Lyons Road from Boynton Beach Boulevard to north of Lantana Road, Lawrence Road from Boynton Beach Boulevard to Hypoluxo Road, and Seminole Pratt Whitney Road from Southern Boulevard to Orange Boulevard. This project also includes the installation of two (2) local hub sites and six (6) closed circuit television (CCTV) cameras to be connected to the Traffic Management Center. Cost/Completion: $1.4 million. Completion is expected in spring 2021. Traffic Impact: Portions of the outside shoulder and sidewalk may be closed in each direction, intermittently, on Lawrence Road from Boynton Beach Boulevard to Hypoluxo Road, 7 a.m. until 7 p.m., Monday through Friday. For more information, please contact Community Outreach Specialist Meredith Cruz at 561-641-6440 or [email protected].

CENTRAL PALM BEACH COUNTY PROJECTS

16. Southern Boulevard (SR 80) Bridges Replacement Project Description This 0.76-mile project includes replacing the existing bascule (draw) bridge and tide relief bridge over the Intracoastal Waterway (ICWW) and Lake Worth Lagoon between the Town of Palm Beach and the City of West Palm Beach. The project limits are between Washington Road in West Palm Beach and State Road A1A/South Ocean Boulevard in Palm Beach. New decorative lighting, pedestrian features, traffic signals, signage and drainage are included. A temporary bridge has been built north of the existing bridge to maintain traffic while the replacement bascule bridge is under construction. Cost/Completion: $95 million. Completion is expected in fall 2021. Traffic Impact: Flagler Drive from Southern Boulevard to Worth Court North is closed as the roadway is reconstructed. Sidewalks also are closed. Access will be maintained for local traffic only. Traffic will be detoured as follows: Traffic going north on Flagler Drive should: Go west on Worth Court North to Washington Road; go north on Washington Road to Southern Boulevard; go east on Southern Boulevard to Flagler Drive. Traffic going south on Flagler Drive should: Go west on Southern Boulevard to Washington Road; go south on Washington Road to Worth Court North; go east on Worth Court North to Flagler Drive. Southern Boulevard’s westbound lane between SR A1A and the tide relief bridge will be closed nightly from 9:30 p.m. to 6 a.m. Sunday, Feb. 21, through Wednesday, Feb. 24, to install drainage. Traffic will be maintained in both directions in the eastbound lane – one direction at a time – with a flagging operation. Marine Impact: The navigable waterway through the Southern Boulevard Bridge is restricted to half channel navigation. Full channel openings will not occur. During half-channel closures, the horizontal clearance through the bridge is 40 feet. The schedule of channel restrictions is published in the U.S. Coast Guard’s Local Notice to Mariners at www.navcen.uscg.gov. The Southern Boulevard Bridge opens for marine traffic twice per hour at 15 minutes and 45 minutes past the hour. For more information, please contact Community Outreach Specialist Angel Streeter Gardner at 561-886-8773 or [email protected].

17. State Road 80/Southern Boulevard at Forest Hill Boulevard/Crestwood Boulevard Description: This 0.46-mile intersection improvement project, located in Wellington and Royal Palm Beach, began on October 24, 2019. Work consists of adding a third westbound to southbound left-turn lane from Southern Boulevard to Forest Hill Boulevard, widening the bridge over the C-51 Canal, converting the Forest Hill Boulevard northbound right-turn lanes to a free-flowing right-turn lane, and widening Southern Boulevard to accommodate an eastbound acceleration lane. Other improvements include milling and resurfacing, drainage, curb and gutter, lighting, guardrails, signalization, sidewalks, landscaping, signage, and pavement markings. Cost/Completion: $5.7 million. Completion is anticipated in spring 2021. Traffic Impact: One westbound lane on Southern Boulevard from Park Central to Forest Hill Boulevard will be closed 9 a.m. to 4 p.m. Monday through Friday to install landscaping and brick pavers. Two lanes may be closed in each direction on Southern Boulevard from Park Central to Forest Hill Boulevard 9 p.m. to 6 a.m. Sunday through Thursday to install traffic detection loops and pavement markings. Two lanes may be closed in each direction on Forest Hill Boulevard/Crestwood Boulevard between Renaissance School Road and Quercus Lane 9 p.m. to 6 a.m. Sunday through Thursday to install pavement markings. Southern Boulevard’s eastbound right-turn lane to southbound Forest Hill Boulevard may be closed 9 a.m. to 4 p.m. Monday through Friday to install guardrail. Southern Boulevard’s north sidewalk from Forest Hill Boulevard to Royal Palm Beach Boulevard is closed until further notice. For more information, please contact Community Outreach Specialist Angel Streeter Gardner at (561) 886-8773 or [email protected].

NORTHERN PALM BEACH COUNTY PROJECTS

18. Vehicle Detection at Traffic Signals Improvements Project Description: This improvements project is upgrading traffic signalization with vehicle video detection systems at 16 locations in Palm Beach County, and began Monday, Aug. 17, 2020. Intersection locations include: Hypoluxo Road and Hagen Ranch Road in Lake Worth; Forest Hill Boulevard and Olympia Boulevard/Via Buena Vida in Wellington; Summit Boulevard and Pine Jog Elementary School, Congress Avenue and Gun Club Road, Pike Road and Florida’s Turnpike, Quadrille Boulevard and Hibiscus Street, 45th Street and Haverhill Road, and 45th Street and Corporate Way in West Palm Beach; Military Trail and Blue Heron Boulevard in Riviera Beach; Congress Avenue and the Lowes/Target Entrance just south of , and Congress Avenue and Silver Beach Road in Lake Park; Military Trail and Hood Road, Military Trail and I-95/Kyoto Gardens Drive, Alternate A1A and Hood Road, and Alternate A1A and Lake Victoria Gardens Avenue in Palm Beach Gardens; and, Indiantown Road and Florida’s Turnpike in Jupiter. Cost/Completion: $845,444. Completion is expected in summer 2021. Traffic Impact: All lanes are open. For more information, please contact Community Outreach Specialist Meredith Cruz at 561-641-6440 or [email protected].

WESTERN PALM BEACH COUNTY PROJECTS

19. State Road 25 Resurfacing Project from the Broward/Palm Beach County Line to Milepost 12.626 Description: Construction on this 12.626-mile resurfacing project began Wednesday, May 13, 2020, in Palm Beach County. Work includes milling and resurfacing the existing travel lanes and shoulders, including shoulder widening, concrete barrier wall installation, guardrail removal and replacement, and signage, pavement marking, and rumble strip installation. Cost/Completion: $21.8 million. Completion is expected in early 2022. Traffic Impact: One lane is closed around-the-clock in each direction from the Broward/Palm Beach County Line to Milepost 12.626. The speed limit is also reduced to 45 mph in the construction zone. For more information, please contact Community Outreach Specialist Meredith Cruz at 561-641-6440 [email protected].

20. State Road 80/Southern Boulevard, from west of Lion Country Safari Road to Forest Hill Boulevard/Crestwood Boulevard Description: Construction on this 7.2-mile widening project began Tuesday, July 31, 2018, in the Village of Royal Palm Beach, Village of Wellington and the Town of Loxahatchee Groves. Work includes widening the existing roadway from four to six lanes, adding a 12-foot shared-use pathway on the north side of the roadway, adding bike lanes, milling and resurfacing, drainage improvements, adding lighting and signalization, installing curb and gutter, guardrails, minor median modifications and signage and pavement markings. Cost/Completion: $33.5 million. Completion is expected in summer 2021. Traffic Impact: Southern Boulevard’s eastbound outside lane between B Road/Binks Forest Drive and Palms West Parkway may be closed 9 a.m. to 3:30 p.m. Sunday through Saturday for work on the outside shoulder. Southern Boulevard’s westbound inside or outside lane between B Road/Binks Forest Drive and Cane Field Trace may be closed 9 a.m. to 3:30 p.m. Sunday through Saturday for work on the shoulder. One lane may be closed in each direction on Southern Boulevard at Lion Country Safari Road, Seminole Pratt Whitney Road, B Road/Binks Forest Drive and F Road/Big Blue Trace from 8:30 p.m. to 6:30 a.m. Monday through Thursday to install traffic signals. Median openings between Cane Field Trace and west of Palms West Parkway may be closed periodically for demolition and reconstruction. Median openings will not be closed consecutively. One lane may be closed periodically in each direction of Southern Boulevard from Palms West Parkway to Cane Field Trace from 9 a.m. to 3:30 p.m. Monday through Saturday. For more information, please contact Community Outreach Specialist Angel Streeter Gardner at (561) 886-8773 or [email protected].

21. Belle Glade Sidewalk Improvements Project Description: Construction on this 2.4-mile sidewalk improvements project began Saturday, Sept. 14, 2019, in the City of Belle Glade. Work includes sidewalk replacement, pavement widening and restoration, driveway reconstruction, drainage structure and pipe replacement, signage and pavement marking upgrades, and installation of detectable warning systems at 13 different locations. Cost/Completion: $1.8 million. Completion is expected in early 2021. Traffic Impact:

SW 6th Street, from W Avenue A to Dr. Martin Luther King, Jr. Boulevard W, may have daily lane closures with a flagging operation, 7:30 a.m. until 6 p.m., Monday through Friday. W Avenue A, from SW 6th Street to SW 5th Street, may have daily lane closures with a flagging operation, 7:30 a.m. until 6 p.m., Monday through Friday. SW 5th St., from B Place to Dr. Martin Luther King, Jr. Boulevard, may have daily lane closures with a flagging operation, 7:30 a.m. until 6 p.m., Monday through Friday. For more information, please contact Community Outreach Specialist Meredith Cruz at 561-641-6440 [email protected].

MAINTENANCE, UTILITY, PERMIT & ADDITIONAL AGENCY PROJECTS

Traffic Impact: The US 1/Parker Bridge, over the Intracoastal Waterway in North Palm Beach, will have one outside lane closed, intermittently, 9 a.m. until 4 p.m., Monday, Feb. 22 through Thursday, Feb. 25, for bridge inspection operations. For more information, please contact Hernan Garcia at 786- 338-5711.

Traffic Impact: The US 1/Jupiter Federal Bridge, over the Intracoastal Waterway in Jupiter, will be closed to traffic overnight, from 9 p.m. on Monday, Feb. 22 to 5 a.m. on Tuesday, Feb. 23, for routine maintenance operations. The bridge may also be closed from 9 p.m. on Tuesday, Feb. 23 to 5 a.m. on Wednesday, Feb. 24 if needed to complete work. Marine traffic will not be affected. Vehicular traffic will be detoured via A1A. A similar closure is planned within the next few weeks; notice will be provided at that time. For media inquiries, please contact FDOT Communications Manager Guillermo Canedo at (954) 777-4090 or by email at [email protected].

Traffic Impact: Brightline, Jupiter – Railroad Crossing at Toney Penna Dr. Full road closure, 7 a.m. to 7 p.m., Monday, February 22. Detour Information: Eastbound Toney Penna Dr. traffic wishing to access Alternate A1A will be directed to travel north on Military Trail to Indiantown Rd., travel east on Indiantown Rd. to Alternate A1A and travel south on Alternate A1A. Alternate A1A traffic wishing to travel west on Toney Penna Dr. will be directed to travel north on Alternate A1A to Indiantown Rd., travel west on Indiantown Rd. to Military Trail and travel south on Military Trail to access Toney Penna Dr. Southbound Old Dixie Hwy. traffic wishing to access Alternate A1A will be directed to travel east on Indiantown Rd. to Alternate A1A. Northbound Old Dixie Hwy. traffic will be directed to travel west on Jupiter Lakes Blvd. to Military Trail, travel north on Military Trail to Indiantown Rd. and travel east on Indiantown Rd. to access Old Dixie Hwy. For more information, please contact Katie Mitzner at 407-502-3587.

Traffic Impact: Brightline, Palm Beach Gardens – Railroad Crossing at RCA Blvd. Full road closure through 7 p.m., Thursday, February 25. Detour Information: Eastbound RCA Blvd. traffic will be directed to travel south on Northcorp Pkwy. to Riverside Dr., travel south on Riverside Dr. to Burns Rd., travel east on Burns Rd. to A1A and travel north on A1A to access RCA Blvd. Westbound RCA Blvd. traffic will be directed to travel south on A1A to Burns Rd., travel west on Burns Rd. to Riverside Dr., travel north on Riverside Dr. to Northcorp Pkwy. and travel west on Northcorp Pkwy. to access RCA Blvd. For more information, please contact Katie Mitzner at 407- 502-3587.

Traffic Impact: Brightline, West Palm Beach – Railroad Crossing at Richard Rd.: Full road closure, 7 a.m., Tuesday, March 2 to 7 p.m., Wednesday, March 10. Detour Information: Eastbound Richard Rd. traffic will be directed to travel south on Old Dixie Hwy. to Northlake Blvd., travel east on Northlake Blvd. to A1A and travel north on A1A to access Richard Rd. Westbound Richard Rd. traffic will be directed to travel south on A1A to Northlake Blvd., travel west on Northlake Blvd. to Old Dixie Hwy. and travel north on Old Dixie Hwy. to access Richard Rd. For more information, please contact Katie Mitzner at 407-502-3587.

Traffic Impact: Northbound Florida’s Turnpike/SR 91 exit ramp to Glades Road/SR 808 (Exit 75). Overnight full ramp closures, 9 p.m. to 5 a.m., Sunday, February 21, and nightly through Thursday, February 25. Detour information:

· Northbound Florida’s Turnpike/SR 91 traffic wishing to access Glades Road/SR 808 (Exit 75) will be directed to exit at Sample Road/SR 834 (Exit 69), travel east on Sample Road to Powerline Road/SR 845 and travel north on Powerline Road to access Glades Road. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Southbound Florida’s Turnpike/SR 91 entrance ramp from Glades Road/SR 808. Overnight full ramp closures, 9 p.m. to 5 a.m., Sunday, February 21, and nightly through Thursday, February 25. Detour information:

· Glades Road/SR 808 traffic wishing to access southbound Florida’s Turnpike/SR 91 will be directed to Powerline Road/SR 845, travel south on Powerline Road to Sample Road/SR 834 and travel west on Sample Road to access southbound Florida’s Turnpike. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Northbound Florida’s Turnpike/SR 91 exit ramp to Boynton Beach Boulevard/SR 804 (Exit 86). Overnight full ramp closures, 9 p.m. to 5 a.m., Sunday, February 21, and nightly through Thursday, February 25. Detour information:

· Northbound Florida’s Turnpike/SR 91 traffic wishing to access Boynton Beach Boulevard/SR 804 (Exit 86) will be directed to exit at Atlantic Avenue/SR 806 (Exit 81), travel west on Atlantic Avenue to US 441/SR 7 and travel north on US 441 to access Boynton Beach Boulevard. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Eastbound and westbound Lantana Road/CR 812 underneath Florida’s Turnpike/SR 91. Daytime full road closures, 9 a.m. to 3 p.m., Thursday, February 25. Detour information:

· Eastbound Lantana Road/CR 812 traffic wishing to continue east will be directed to Lyons Road, travel north on Lyons Road to Lake Worth Road/SR 802, travel east on Lake Worth Road to Jog Road and travel south on Jog Road to access eastbound Lantana Road.

· Westbound Lantana Road/CR 812 traffic wishing to continue west will be directed to Jog Road, travel north on Jog Road to Lake Worth Road/SR 802, travel west on Lake Worth Road to Lyons Road and travel south on Lyons Road to access westbound Lantana Road.

· Northbound Hagen Ranch Road traffic wishing to access westbound Lantana Road/CR 812 will be directed to Lantana Road, travel east on Lantana Road to Jog Road, travel north on Jog Road to Lake Worth Road/SR 802, travel west on Lake Worth Road to Lyons Road and travel south on Lyons Road to access Lantana Road. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Eastbound and westbound Glades Road at Florida’s Turnpike, daytime single lane closure, 9 a.m. to 4 p.m., Monday through Friday. Please note this closure will not affect the entrance or exit ramps. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Eastbound and westbound Atlantic Avenue at Florida’s Turnpike, daytime single lane closure, 9 a.m. to 4 p.m., Monday through Friday. Please note this closure will not affect the entrance or exit ramps. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Eastbound and westbound Boynton Beach Boulevard at Florida’s Turnpike, daytime single lane closure, 9 a.m. to 4 p.m., Monday through Friday. Please note this closure will not affect the entrance or exit ramps. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Ocean Drive at Celestial Way, in Juno Beach, is closed through Wednesday, Feb. 24, for utility work. Traffic is being detoured via Olympus Drive and US 1. For more information, please contact Palm Beach County Traffic & Engineering at 561-684-4000.

Traffic Impact: State Road 15, from south of Morgan Road to south of Shirley Drive, in Pahokee, may have lane closures with a flagging operation, 10:30 a.m. until 3 p.m., Tuesday, Feb. 23, for striping and maintenance operations. For more information, please contact Anthony Debrowski at 561-459-9479.

Traffic Impact: Westbound Lake Worth Road just east of Congress Avenue, in Lake Worth, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 29, 2021, 1 of 2 lanes closed, for force main repairs. For more information, please contact Frank Kendrix 813-299-6320.

Traffic Impact: Eastbound Glades Road at intersection of 95 Avenue, in Boca Raton, 7 p.m. until 5 a.m., Monday through Friday, through Wednesday, Mar. 31, 2021, 2 of 3 lanes closed, for water main installation. For more information, please contact Steven Kopelskopel 954-270-5290.

Traffic Impact: Westbound and eastbound West Indiantown Road, just east of Carver Avenue and just west of Loxahatchee River, in Jupiter, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 26, 2021, 1 of 3 lanes closed, for manholes and conduit system maintenance work. For more information, please contact Sean Linn 772-332-4854.

Traffic Impact: Northbound North Military Trail between Johnson Dairy Road and PGA Boulevard, in Palm Beach Gardens, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 26, 2021, 1 of 3 lanes closed, for manhole and conduit system maintenance. For more information, please contact Sean Linn 772-332-4854.

Traffic Impact: Southbound State Road 7 between North of 92 Place North and South of 72 Place South, in Boynton Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Monday, Apr. 5, 2021, 1 of 3 lanes closed, for wood and concrete poles replacement and installation. For more information, please contact Art Rodriguez 561-475-0064.

Traffic Impact: Eastbound Yamato Road between North West Boca Raton Boulevard and North Dixie Highway, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 29, 1 of 3 lanes closed, for directional boring and conduit installation. For more information, please contact Antonio Seco 954-529-5029 or 305-803-9769.

Traffic Impact: Northbound North Military Trail between Kent Avenue and Purdy Lane, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Apr. 9, 1 of 3 lanes closed, for concrete poles installation. For more information, please contact Maryann Green 561-495-7608.

Traffic Impact: Northbound South Congress Avenue between Kentucky Avenue and Shawnee Road, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Mar. 19, 1 of 3 lanes closed, for wooden pole removal and installation. For more information, please contact Latess Hill 561-631-0663.

Traffic Impact: Westbound Okeechobee Boulevard between South Sapodilla Avenue and South Rosemary Avenue, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Wednesday, Mar. 31, 1 of 4 lanes closed, for directional boring and conduit installation. For more information, please contact Daniel Moura 561-418-0596.

Traffic Impact: Southbound Highway A1A between East Riverside Drive and Center Street, in Jupiter, 9 a.m. until 5 p.m., Monday through Friday, through Friday, Feb. 26, 1 of 3 lanes closed, for maintenance on existing sewer force main. For more information, please contact Joe Jesteeadt 561- 262-0289 and/or Ryan Chernekoff 561-262-3461.

Traffic Impact: Southbound North Ocean Boulevard Boynton Inlet Pier and Seal Lake Drive, in Boynton Beach, 8 p.m. until 5 a.m., Monday through Friday, through Friday, Feb. 26, 1 of 2 lanes closed, for conduit installation. For more information, please contact Daniel Moura 561-418-0596.

Traffic Impact: Southbound South Dixie Highway between Belvedere Road and Monceaux Road, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Mar. 19, 1 of 2 lane closed, for directional boring and conduit installation. For more information, please contact Daniel Moura 561-418-0598.

Traffic Impact: Southbound US Highway A1A between Southeast Village Circle and South Beach Road, in Jupiter, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 26, 1 of 3 lanes closed, for directional boring and conduit installation. For more information, please contact Miguel Arronte 786-479-8190.

Traffic Impact: Westbound East Atlantic Avenue from 375’ ft West of Homewood Boulevard/High Point Boulevard and 170’ ft East of Whatley Road, in Delray Beach, 9 p.m. until 5 a.m., Monday through Friday, through Wednesday Apr. 28, 1 of 3 lanes closed, for wood and concrete pole replacement and installation. For more information, please contact Art Rodriguez 561-475-0064.

Traffic Impact: Northbound Highway A1A between Center Street and the Loxahatchee River bridge, in Jupiter, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 26, 1 of 3 lanes closed, for manhole access for work bridge work. For more information, please contact Sean Linn 772-332- 4854.

Traffic Impact: Northbound and Southbound South Ocean Boulevard from 118’ ft north of Del Haven Drive and 1099’ ft south of Bermuda Gardens Road, in Delray Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Wednesday Apr. 28, 1 of 2 lanes closed, for wood and concrete pole replacement and installation. For more information, please contact Art Rodriguez 561-475-0064.

Traffic Impact: Southbound South Federal Highway between Fladells Lane and Tropic Isle Drive, in Delray Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Wednesday Apr. 28, 1 of 2 lanes closed, for overhead maintenance. For more information, please contact Art Rodriguez 561-475- 0064.

Traffic Impact: Westbound and eastbound Southern Boulevard at the intersection of South Ocean Boulevard, in Palm Beach, 9 p.m. until 4 a.m., Monday through Friday, through Friday, Feb. 26, 1 of 3 lanes closed, for sample point and asphalt patch installation. For more information, please contact Robert Earnst 561-718-4536.

Traffic Impact: Northbound South Federal Highway between Southeast 9 Street and Southeast 7 Street, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 26, 1 of 3 lanes closed, for building material loading delivery. For more information, please contact Carol Judd 786-999-3943.

Traffic Impact: Northbound Highway A1A between Barrow Island Road and Toney Penna Drive, in Jupiter, 9 a.m. until 3:30 p.m., Monday through Friday, through Monday, Mar. 22, 1 of 3 lanes closed, for canal cleaning. For more information, please contact Walter Pfaffendberger 561-723-0638.

Traffic Impact: Westbound PGA Boulevard between Garden Square Boulevard and Hickory Drive, in Palm Beach Gardens, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Mar. 19, 1 of 3 lanes closed, for directional boring and conduit installation. For more information, please contact Miguel Arronte 786-479-8190.

Traffic Impact: Westbound West Atlantic Avenue between High Point Boulevard and Whatley Road, in Delray Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Apr. 30, 1 of 3 lanes closed, for wood poles installation. For more information, please contact Art Rodriguez 561-475-0064.

Traffic Impact: Eastbound Lake Avenue between North Federal Highway and Lakeside Drive, in Lake Worth, 9 a.m. until 3 p.m., Monday through Friday, through Tuesday, Feb. 23, 1 of 3 lanes closed, for setting up utility poles. For more information, please contact Erwin Mosqueda 954-789-7600.

Traffic Impact: Eastbound PGA Boulevard between the I-95 exit ramp and RCA Boulevard, in Palm Beach Gardens, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 26, 1 of 4 lanes closed, for excavate existing sewer main and grout remaining gravity sewer. For more information, please contact Steven Eakins 561-346-1549.

Traffic Impact: Southbound North Quadrille Boulevard between Banyan Boulevard and 3 Street, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Apr. 9, 2 of 2 lanes closed as needed, for directional boring, conduit and pole installation. For more information, please contact Daniel Moura 561-418-0598.

Traffic Impact: Northbound North Military Trail between Westroads Drive and Dyer Boulevard, in Riviera Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Monday, Feb. 22, 1 of 3 lanes closed, for directional boring and conduit installation. For more information, please contact Stephanie Dougherty 954-741-6188.

Traffic Impact: Westbound West Indiantown Road between North Delaware Boulevard and Center Street, in Jupiter, 9 p.m. until 4 a.m., Monday through Friday, through Thursday, Apr. 22, for replacement and pole installation. For more information, please contact Art Rodriguez 561-475-0064.

Traffic Impact: Northbound Alternate A1A between Kyoto Gardens Drive and PGA Boulevard, in Palm Beach Gardens, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Apr. 23, 1 of 3 lanes closed, for gas line installation. For more information, please contact Jonathan Fernandes 786- 375-7839.

Traffic Impact: Westbound East Atlantic Avenue between Northeast 7 Avenue and Northeast 6 Avenue, in Delray Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Mar. 19, 1 of 2 lanes closed, for apply exterior elements. For more information, please contact Alex Bacallao 954- 598-2081.

Traffic Impact: Northbound North Military Trail just north of Blue Heron Boulevard south of Leo Lane, in Riviera Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Wednesday, Mar. 31, 1 of 3 lanes closed, for removal and installation pole and facilities maintenance. For more information, please contact Latess Hill 561-631-0663.

Traffic Impact: Westbound and eastbound West Indiantown Road between Cortona Road to just east of Florida’s Turnpike, in Jupiter, 9 a.m. until 3:30 p.m., Monday through Friday, through Monday, Feb. 22, 1 of 3 lanes closed, for removal and installation of a driveway. For more information, please contact Robert Shaouy 954-275-9700.

Traffic Impact: Westbound Forest Hill Boulevard between Jog Road to Pinehurst Drive, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Wednesday, Mar. 31, 1 of 2 lanes closed, for directional bore installation. For more information, please contact Miguel Arronte 786-479- 8190.

Traffic Impact: Northbound South Ocean Boulevard between Russell Drive and Grand Court, in Highland Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Apr. 9, 1 of 2 lanes closed, for pole installation. For more information, please contact Ted Howard 954-907-4011 or Nick Bucknor 754-303-0396.

Traffic Impact: Westbound Southern Boulevard approximately 1,000’ ft west of Australia Avenue, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, Tuesday, Feb. 23 through Tuesday, Mar. 16, 5 of 5 lanes closed as needed, for directional boring, conduit and hand hole installation. For more information, please contact Lazaro Martinez 305-781-8906.

Traffic Impact: Eastbound Yamato Road between North Dixie Highway and North Federal Highway, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Feb. 22 through Friday, Apr. 2, 1 of 3 lanes closed, for facility maintenance. For more information, please contact Ted Howard 954- 904-7011 or Nick Bucknor 754-303-0396.

Traffic Impact: Westbound Southern Boulevard approximately 150’ ft east of Gem Lake Drive and 356’ ft west, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Feb. 22 through Friday, Mar. 26, 1 of 4 lanes closed as needed, for directional boring installation. For more information, please contact Lazaro Martinez 305-781-8906.

Traffic Impact: Southbound South Federal Highway at Northeast 20 Street, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Apr. 9, 1 of 3 lanes closed, for facility maintenance. For more information, please contact Ted Howard 954-904-7011 or Nick Bucknor 754- 303-0396.

Traffic Impact: Eastbound Okeechobee Boulevard between Florida Avenue and Alabama Avenue, in West Palm Beach, 9 a.m. until 5 p.m., Monday through Friday, Tuesday, Feb. 23 through Friday, Feb. 26, 4 of 5 lanes closed as needed, for crane placing. For more information, please contact Dave Griner 772-834-3778.

Traffic Impact: Northbound South Ocean Boulevard at 350 South Ocean Boulevard, in Boca Raton, 9 a.m. until 3:30 p.m., one night only, Thursday, Feb. 25 through Friday, Feb. 26, 2 of 3 lanes closed as needed, for crane placing. For more information, please contact Dave Griner 772-834-3778.

Traffic Impact: Southbound South Federal Highway between Northeast 2 Avenue and East Palmetto Park Road, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, Thursday, Feb. 25 through Friday, Mar. 5, 1 of 2 lanes closed, for overhead facility maintenance. For more information, please contact Ted Howard 954-904-7011 or Nick Bucknor 754-303-0396.

Traffic Impact: Southbound US 441 South at intersection of Judge Winikoff Road, in Boca Raton, 9 a.m. until 3:30 p.m., one day only, Thursday, Feb. 25, 1 of 4 lanes closed, for sidewalk restoration. For more information, please contact David Beale 561-670-9420.

Traffic Impact: Northbound South Military Trail between Barbridge Road and Line Drive, in West Palm Beach, 8 p.m. until 5 a.m., Monday through Friday, through Friday, Mar. 15, 1 of 3 lanes closed, for facilities maintenance. For more information, please contact Ted Howard 954-904-7011 or Robert Mitchell 305-901-9541.

Traffic Impact: Northbound North Military Trail between Westroads Drive and Dyer Boulevard, in Riviera Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Wednesday, Feb. 24, 1 of 3 lanes closed, for directional boring and conduit installation. For more information, please contact Stephanie Dougherty 954-741-6188.

###

Improve Safety, Enhance Mobility, Inspire Innovation

D4FDOT.com | @MyFDOT_SEFL | Facebook.com/MyFDOTSEFL

The Florida Department of Transportation’s mission is to provide a safe transportation system that ensures the mobility of people and goods, enhances economic prosperity, and preserves the quality of the state’s environment and communities. The department is committed to building a transportation system that not only fits the current needs of Florida’s residents and visitors, but also enhances mobility throughout the state to accommodate its consistent and rapid growth. The unique nature of the Sunshine State and its year-round warm climate provides numerous opportunities to achieve the department’s mission through multiple transportation modes including highways/streets, air, rail, sea, spaceports, transit, and the ever-expanding deployment of bicycle & pedestrian facilities.