SINGARENI COLLIERIES COMPANY LIMITED (A Government Company) MANDAMARRI- AREA K.K.1 Incline

HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS UP TO 30th SEPTEMBER, 2013

A. SALIENT FEATURES OF THE PROJECT: 1 Name of the Project : KALYAN KHANI – 1 (KK-1) Incline Underground Coal mine. 2 Organization : The Singareni Collieries Company Limited 3 Coalfield : Godavari Valley Coal Field 4 Type of Mine : Underground 5 Technology : Board & Pillar with SDL's 6 Environmental Clearance : A Letter No & date : J-11015/383/2007-IA.II (M), GoI, MoEF, Dated:27 -10 - 2008 B Sanction capacity : Normative: 0.30 MTPA Peak: 0.50 MTPA C Mining Lease Area : 424.49 Ha D Date of Public Hearing : 13-02-2008 7 Location of the Project A Village : Mandamarri B Tehasil : Revenue Mandal of Mandamarri C District : D State : Andhra Pradesh E Latitude : NORTH: 18 0 58 ’ 59’’ TO 19 0 00 ’ 00’’ F Longitude : EAST: 79 0 28’ 23’’ TO 79 0 29’ 10’’ G Topo Sheet : 56M/8 H Nearest railway station : Mandamarri I Nearest Airport : Hyderabad J Nearest town : Mandamarri 8 Address for Correspondence : A Name : J. KUMARASWAMY B Designation : AGENT C Address THE AGENT,KK GROUP; THE SCCo. LTD., D Pin Code : 504 231 F E-mail ID : [email protected] G Telephone No. : 08736 -256633 H Fax No. : 08736-257033 9 Life of the Project A Date of Opening : 12-02-1956 B Total Life of the project as : 16 Years per EMP C Balance Life : 8 ½ Years 10 Seams : A Total Seams Present : IB, IA, I, IIB, IIA, II, III & IV B Seams being worked : III & IV 11 Depth A Minimum Depth (m) : 31 m B Maximum Depth (m) : 364 m C Present working depth (m) : 240 m

1 12 Reserves A Total Geological Reserves : 29.509 MT B Total Extractable Reserves : 12.120 MT C Reserves already Extracted : 8.187 MT D Balance Reserves : 3.933 MT E Coal production during last : 0.097MT six months 13 Land Requirement A Total Requirement (Mine Take 424.49 ha Area) B Forest land Involved 237.01 ha C Non-forestland 124.18 ha D Land acquired so far 63.30 ha (Surface rights) 14 Statutory Clearances A Ground Water Clearance : Lr.No.441/T/2007, Dated:25.10.2007 B Consent for Establishment : C Consent for Operation : APPCB/RCP/ADB/102/KK-1/HO/CFO/2012/3298, Dated: 23 -10 -2012 and valid up to 30.09.2014. D Forest Clearance : 8-5/88-FC, Dated: September 15 th ,1999 E Minin g Lease : Procgs.No.1538/M/2003, Dated: 13 -08 -2003 F Others (Specify) : 15 R & R Involved : No R&R is involved in the project

2

Part – 1:

Status of Implementation of MoEF conditions as on 30-09-2013 Sl. Special Condition Compliance Status No. i) Mining shall not be carried in forest land Forestry clearance under the provisions of for which forestry clearance has not FC Act, 1980 accorded for the forestland been obtained under the provisions of involved North Godavari mining lease vide FC Act, 1980. MoEF lr.no . 8-5/88-FC, dated 15.09.1999 for underground mining activities. ii) Sufficient coal pillars shall be left un- The Air shaft is located from surface to 12 extracted around the Air shaft (Within level of 4 seam and its dia and depth of the subsidence influence area) to protect sinking is 5.5 and 40 m respectively. 60 from any damage from subsidence, if meters of barrier from the centre of the any. shaft all along the perimeter of the shaft is left as un-extracted. iii) Solid barriers shall be left below the A WBM road of 1.75 KM length leading to roads falling within the blocks to avoid Jangupalli village over the mine take area any damage to the roads. and 40 meters of safety solid barrier is left against the road. iv) Depression due to subsidence resulting There is no subsidence is observed in the in water accumulating within low lying present working Panels 38T & 38B of areas shall be filled up or drained out by No .3&4 seams where depillaring is in cutting drains. progress at a depth of 146 m and also there is no accumulation of water is observed. Accumulation of water if any, due precautions will be taken as per stipulated condition. v) While extracting the panels in the lower Complied the condition. seam, all the water bodies in the subsidence area shall be drained. Dewatering of upper seam (3-seam) is Dewatering of old goaves of the upper done while working in lower seam (4– seams shall be continued as long as the seam). There is no subsidence found in lower seam is worked to prevent the the present workings in 3 & 4 seams. accumulation of large water bodies over Besides the given stipulations, further more working area. precautions have been taken as mentioned in the provisions of Regulation 126 &127 of CMR 1957 and also the permission given by the DGMS to the panel no 38T &38Bof 3&4 seams vide letter no:HR-2(SCZ)/ PERM /2012/419-21, Dated 07-02-2012

3 vi Regular monitoring of Subsidence survey is being carried out during extraction of subsidence movement on the caving panel once in every month and after completion the surface over and of the extraction, once in every 6 months (till the movement around the working area ceases completely). The system of frequency and recording and impact on natural of observations is as per the provisions of DGMS Technical drainage pattern, water circular No. 4 of 1988. The depressions/Cracks were bodies, vegetation, effectively plugged with red earth from nearby areas and structure, roads and plantation is being raised after stabilization. surroundings should be continued till movement There is no subsidence movement observed in present ceases completely. In working panel i.e., 38T&38B panel of 3&4 seams. The case of observation of details of panel is as follow: any high rate of 1 Date of subsidence occurred: Nil subsidence movement, 1 Size of the panel: 140m( b)X244m(l) appropriate effective 2 Area of extraction as on 19200 m2 corrective measures 30/09/2013: should be taken to avoid 3 Total area of the panel: 34000 m2 the loss of life and 4 depth from surface: 132 m material. Cracks should 3-seam: be effectively plugged 5 depth from surface: 146 m with ballast and clay soil/ 4-seam: suitable material. 6 Height of extraction: 2.6 m 3-seam: 4 - seam 3.6 m As per subsidence prediction report, the anticipated max subsidence is: 0.01 m (NIRM formula) Actual observed: Nil Since inception of the mine so far the maximum subsidence observed is 2.40m in Panel No. R of No. 3 & 4 Seams and the details are as follow 1 Date of subsidence occurred: 14-12-2000 1 Size of the panel: 220 (l)m X 139(w) m 2 Area of extraction: 18959 Sq.m 3 Total area of the panel: 30580 Sq.m 4 depth from surface: 44.3 m 3-seam: 5 depth from surface: 57 m 4-seam: 6 Height of extraction: 2.90 m 3-seam: 4 - seam 3.50 m 7 Total subsidence area 2.40 ha 8 Max Crack width observed m 0.60 m 9 Max subsidence observed so far 2.40 m

Course of Action taken: All micro level cracks including the original subsidence were dozed of effectively with tractor dozer and filled with red earth for compact sealing. Presently the area is raised with plantation.

4

Sl. Special Condition Compliance Status No. vii) Garland/surface drains (size gradient The pit entries such as airshaft and main incline and and length) around the safety areas man way dip was designed minimum 3 m above the such as mine shaft and low lying areas HFL of the area. The sumps are designed keeping the and sump capacity should be designed highest seepage calculations and retention time to keeping 50% safety margin over an settle the silt material. Adequate numbers of the above the peak sudden rainfall and pumps were already provided to pump out mine water maximum discharge in the area during peak rainfall. 240 hp pumps (3 no) and 190 hp adjoining the mine sites. Sump (1 no) working to cater the needs of adequate capacity should also provide adequate retention capacity of make up of water. The details of retention period to allow proper settling the sumps are as follow: of silt material. Sufficient number of Location of Calculations of Actual pumps of adequate capacity shall be sump 4Seam sump cap KL Capacity in deployed to pump out mine water Kilo liter during peak rainfall. 1 3 Dip/16 L 685.26 1458 2 12dip/38 level 1192.32 2592 3 14 dip/54 level 1114.56 2592 4 24Clevel/7 dip 874.80 1944

viii) Crushers at the CHP should be There is no CHP especially for this mine. However, operated with high efficiency bag mobile water sprinklers are being used for sprinkling filters, water sprinkling system should on unpaved roads. Coal transportation roads and be provided to check fugitive permanent internal roads were black topped. Besides emissions from crushing operations, the above, mist spray system is effectively working to conveyor system, haulage roads, and suppress the fugitive dust at CHP. In addition to the transfer points, etc. above all internal roads and coal transporting roads in mine premises are effectively made water sprinkling and thus suppressing the fugitive dust. ix) Drills should be wet operated. There is no drill is deployed on surface as it is an underground mine. The water spraying on the working face as per the provisions of 123 of Coal Mines Regulation, 1957 is implemented to avoid the dust generation in the working places. x) A progressive afforestation plan shall A progressive afforestation plan has been prepared be prepared and implemented for the and envisaged in the EIA/EMP. The Company has undisturbed area and shall include separate Forestry department under the control of IFS area brought under greenbelt officer deputed from GoI /AP Forest Department to development, areas along the roads, implement afforestation plan into the action. The infrastructure, over surface where details of progressive plantation are being furnished in mining is being done below, along ML the half yearly monitoring reports submitted to boundary an township outside the Regional Office, MoEF, Bangalore and Regional lease areas, etc., by planting native Office, AP Pollution Control Board. As on date species in consultation with the local plantation in 35 ha in KK-1 Incline within the mine take DFO/Agriculture Department. The area was carried out apart from the vacant areas density of the trees should be around within the office complex. Block plantation in 835.00 2500 plants per Ha. Ha was carried out in the area out side, within the mining lease and in townships. Capital expenditure of Rs. 24.57 lakh incurred in KK-1 Incline.

5 xi) Conservation plan for endangered The project is an expansion of existing old mine workings species found in and around the and is restricted to underground only and also there is no project area shall be formulated in endangered species found in core and buffer zones as consultation with the State Forest per declaration (EMP) of Scientific study carried on flora and Wildlife Departments. and fauna in the area by ENVIS centre of Eastern Ghats of EPTRI, Hyderabad.

The precise details of the report is as follow: Flora Core Zone Buffer Zone Agricultural Crops Paddy,Jowar,maize Commercial Crops Cotton, chilli Plantation Pongamia, Pongamia, Jatropa Bambusa Natural vegetation / Dry Dry deciduous forest type deciduous forest forest Grass lands -- -- Endangered -- -- species Endemic species -- -- Other (specify) -- -- Fauna Core Zone Buffer Zone Total listing of 22 25 faunal elements Endangered -- -- species Endemic species -- -- Migratory species -- -- Details of aquatic -- -- fauna if applicable

Since there is no endangered and endemic flora and fauna is observed in core zone as well as buffer zone, the Conservation plan is not being prepared. xii) Regular monitoring of groundwater Complied and data enclosed in Annexure-5 (Quality) & level and quality should be carried Anexure-7 (Ground water levels). out by establishing a network of exiting wells and construction of new peizometers. The monitoring for quantity shall be done four times a year in pre-monsoon (May), monsoon (August), post-monsoon (November) and winter (January) seasons and for quality in May. Data thus collected shall be submitted to the Ministry of Environment & Forests and to the Control Pollution Board quarterly within one month of monitoring. xiii) The Company shall put up artificial 2550 KLD of excess mine discharge water is being groundwater recharge measures diverted to nearby nallah i.e., Orregaddavagu for for augmentation of groundwater augmentation of ground water and also agriculture resource. The project authorities purpose of the near by agricultural fields at Mandamarri should meet water requirement of beside Cinema hall area and Narlapur village. The nearby village(s) in case the village Company will supply drinking and domestic water to the wells go dry due to dewatering of nearby villages in case of the village wells dried due to mine. dewatering of mine.

6

Sl. Special Condition Compliance Status No. xiv) The company shall obtain approval of Ground water clearance from Ground Water CGWA/CGWB Regional Office for use of Department, Government of Andhra Pradesh ground water if any, for mining operations. was accorded vide lr.no . 441/T/2007, Dated 25.10.2007. xv) Sewage treatment plant should be installed in Sewage treatments in existing colony being the existing colony. ETP should also be treated through septic tanks followed by soak provided for workshop and CHP wastewater. pits. ETP is provided and operating in the Area workshop.

Further more, it is proposed to take up a small Sewage Treatment Plant at Pranahitha Colony, Mandamarri. xvi) For monitoring land use pattern and for post Complied. mining land use, a time series of land use The land use / land cover classifications have maps, based on satellite imagery (on a scale taken with satellite Imageries and the details of 1:5000) on the core zone and buffer zone, are being furnished with reference to the from the start of the project until end of mine base line studies as fallows: life shall be prepared once in 3 years (for any one particular season which is consistent in the time series.) and the report submitted to MOEF and its Regional office at Bangalore.

Buffer Zone: Details of Land. Study area as per Study area as per Variance BLD (2006) In Ha imageries 2010 report % Built up land 1908 3390.56 77.70 Double Crop area Single Crop area 13209 19044.02 44.17 Agricultural Plantations Dense Forest 15157 15378.38 1.46 Scrub Forest Mining Area 3 156.84 5128.00 Forest Plantation 150 2320.47 1446.98 Land with/without scrubs 8260 3309.05 -59. 94 River/Canals 948 846.93 -10.66 Water bodies 638 700.89 9.86

xvii) A Final Mine Closure Plan along with details of It will be sent as per the stipulated condition Corpus Fund should be submitted to the since the project will be closed after 9 Years. Ministry of Environment & Forests 5 years in advance of final mine closure for approval.

7

B. GENERAL CONDITIONS Sl. Condition Compliance Status No. i) No change in mining technology and scope of Complied working shall be made without prior approval of the Ministry of Environment and Forests. ii) No change in the calendar plan including Complied excavation, quantum of mineral coal and waste shall be made. The production achieved during the year 2012-13 is 1.985 Lakh tons as against 3.50 Lakh tons as envisaged in approved EMP. iii) Four ambient air quality monitoring stations Complied and details are enclosed in shall be established in the core zone as well Annexure-1, Point-5 of Part II as in the buffer zone for SPM, RPM, SO2 and NOx, Hg and other heavy metals such as Pb, Cr, As etc. Location of the stations shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets in consultation with the State Pollution Control Board. iv) Fugitive dust emissions (SPM and RSPM, Hg Fugitive dust emissions are being monitored and other heavy metals) from all the sources regularly at mines (KK 1 Incline) allied shall be controlled regularly monitored and activities (RKP CHP). data recorded properly. Water spraying arrangement on haul roads, wagon loading Effective water spraying arrangement is and dump trucks (loading and unloading) being provided as suggested above. points shall be provided and properly Monitoring details are enclosed in maintained. Annexure-1, Point-5 of Part II v) Data on ambient air quality (SPM, RSPM, SO2 Complied and analysis reports furnished in and NOx, Hg and other heavy metals) shall be Annexure-1, Point-5 of Part II regularly submitted to the Ministry including its Regional Office at Bangalore and to the State Pollution Control Board and the Central Pollution Control Board once in six months. vi) Adequate measures shall be taken for control Noise control measures such as plantation of noise levels below 85 dB (A) in the work around the fan house & mine take area, environment. Workers engaged in blasting and Provision of evasee to main mechanical drilling operation, operation of HEMM, etc shall ventilator, reduction of height of fall in the be provided with ear plugs/muffs. bunkers, maintenance of machinery, etc., are being taken up. All the active work force engaged on drilling, blasting, operation of machinery and noise prone areas are being provided with earplugs. Monitoring details are enclosed in Annexure-3, Point-10 of Part II vii) Industrial wastewater (workshop and Complied and analysis reports are furnished wastewater from the mine) shall be properly as Annexure-2, Point-8 of Part II collected, treated so as to conform to the standards prescribed under GSR 422(E) dated 19 th May 1993 and 31 st December 1993 or as amended from time to time before discharge. Oil and grease trap shall be installed before discharge of workshop effluents. viii) Vehicular emissions shall be kept under Vehicles are being tuned regularly for control control and regularly monitored. Vehicles used of emissions and ensured coal is loaded for transporting the mineral shall be covered optimally and covered with tarpaulin. with tarpaulins and optimally loaded. 8

Sl. Condition Compliance Status No. ix) Environmental laboratory shall be established Post project environmental quality monitoring with adequate number and type of pollution is being carried out through an external monitoring and analysis equipment in agency i.e., M/s EPTRI, Hyderabad. Suitable consultation with the State Pollution Control Environmental lab is established in Board. Mandamarri area. x) Personnel working in dusty areas shall wear Personnel working in dusty areas are being protective respiratory devices and they shall provided with dust masks, Training and also be provided with adequate training and information on safety and health aspects are information on safety and health aspects. being given through Internal Safety Occupational health surveillance programme Organization and Mine Vocational Training of the workers shall be undertaken periodically Centers. to observe any contractions due to exposure to dust and to take corrective measures, if Occupational health surveillance is being needed. carried out periodically through Periodical Medical Examinations (PME) once in every 5 years. Every year 1/5 of the total manpower will be covered under PME. PME held during the last six month period is for 174 persons. xi) A separate environmental management cell Area and Company Level Environmental Cell with suitable qualified personnel shall be set is established separately with qualified up under the control of a Senior Executive, personnel, which will serve the purpose and who will report directly to the Head of the full fill the condition. However, the project Company. has constituted separate environmental management cell with the following officers: Sl. Designation No 1 DGM Chairman 2 Manager, KK 1 inc Member 3 Project Engineer Member 4 Safety Officer Member 5 Survey Officer Member 6 Area Env. Officer Convener 7 Area Forest Officer Member

xii) The funds earmarked for environmental As per the progress of the project protection measures shall be kept in separate constructional activities etc, A separate account and shall not be diverted for other account will be maintained for the funds purpose. Year-wise expenditure shall be earmarked for environmental protection reported to this Ministry and its Regional Office measures and year wise expenditure will be at Bangalore. reported to the Ministry and its regional office at Bangalore. Details are furnished below:

The details of for the period from April, 2013 to September, 2013 Sl. Expenditure Description No in Rs. 1 Air Pollution Prevention & Control measures (Free Gas supply of workers) 2789118.00 2 Air & Water monitoring cost 11021374.00 3 Plantatation (Block & Avenue) 2457916.00 4 Water spraying arrangements 122299.00 5 Water cess 12641.00 6 CFO fee 22500.00 7 filter bed maintenance 102300.00 Total 1,65,28,148.00

9

Sl. Condition Compliance Status No. x) The Regional Office of this Ministry located at Bangalore Complied shall monitor compliance of the stipulated conditions. The Project authorities shall extend full cooperation to the office(s) of the Regional Office by furnishing the requisite data/ information/ monitoring reports. xiv) A copy of the EC will be marked to concerned Panchayat Complied / local NGO, if any, from whom any suggestion/ representation has been received while processing the proposal. xv) State Pollution Control Board shall display a copy of the Complied clearance letter at the Regional Office, District Industry Centre and Collector’s Office/ Tahsildar‘s Office for 30 days. xvi) The Project authorities shall advertise at least in two local The advertisement was given on newspapers widely circulated around the project, one of 18.11.2008 in Deccan chronicle which shall be in the vernacular language of the locality (English Daily) and Vartha (Telugu concerned within seven days of the clearance letter Daily) widely circulated around the informing that the project has been accorded project. environmental clearance and a copy of the clearance letter is available with the State Pollution Control Board and may also be seen at the website of the ministry of Environment & Forests at http://envfor.nic.in 3 The Ministry or any other competent authority may All conditions mentioned are stipulate any further condition for environmental complied. protection. 4 Failure to comply with any of the conditions mentioned All conditions mentioned are above may result in withdrawal of this clearance and complied. attract the provisions of the Environment (Protection) Act, 1986. 5 The above conditions will be enforced inter-alia, under the All conditions mentioned are provisions of the Water (Prevention & Control of Pollution) complied. Act, 1974, the Air (Prevention & Control of pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act, 1991 along with their amendments and Rules.

10 A PERIODIC PROGRESS REPORT REGARDING ENVIRONMENTAL PROTECTION MEASURES TILL 30.09.2013 IS ENCLOSED AS PART - II.

PART – II 1. Production Details Sl. Year Coal (in MT) No As per EC Mt Actual Mt 1 2008-09 0.300 0.245 2009-10 0.300 0.232 2010 -11 0.300 0. 190 2011-12 0.300 0.181 2012-13 0.350 0.196

2. Plantation: 1 No of plants planted during last six months / last Nil year 2 Area covered in Ha Nil 3 Expenditure incurred in Rs. lakhs Nil 4 Total area brought under plantation so far in Ha 35 Ha 5 Total no of plants planted so far since inception 27332 6 Species of plants planted Clones and mixed with native species 7 Seeds sown so far Nil 8 Small plants planted so far 230 9 Total expenditure in Rs. lakhs 24.57 Note: Plan along with details of year wise plantation furnished.

3. Water Balance Statement: Sl Description Quantity in KLD 1 Average quantity of water pumped out of the mine 7500 2 Water used for drinking/bathing and other industrial 1100 requirement 3 Water used for washing of HEMM ----- 4 Water used for plantation 100 5 Water supplied for nearest township/village for 3500 domestic purpose 6 Excess water let out 2550 7 Point of discharge (as per CFO) On land for irrigation/dust suppression 8 Discharge Consent from APPCB Mine discharge water after treatment: 544 KLD Domestic Wastewater: 560 KLD

4. Micro-meteorological Monitoring: Micro-meteorological station was installed at Guest House, Mandamarri. The summary of the monitoring from 01.04.2013 to 30.09.2013 as follows: Sl. Parameter Min. Max. Mean No. 1. Temperature (0C) 24 44.9 25

2. Wind Speed (Km/hr) 0 11.7 1.43

3. Relative Humidity (%) 10.7 99.9 60.23 Predominant Wind direction for the 4 0 360 177.21 entire study period Total rainfall (mm):1033 mm 5 0 210 5.60 (From 01-04-2013 to 30-09-2014)

11 Annexure-1

5. Ambient Air Quality Monitoring:

Monitoring data: The summary of the monitoring from 01.04.2013 to 30.09.2013 as follows:

Direction & PM 10 Location Distance Min. Max. 98%tile STD

CORE ZONE KK-2 Incline N 28 o W & 1.4 KM 92 169 165 250 KK-1 Incline -- 105 194 192 250 KK-5 Pit Office S 47 o E & 2.7 KM 123 254 248 250 RKP –CSP S 2 o E & 6.4 KM 121 284 282 300 BUFFER ZONE GM Office, Mandamarri N 53 o W & 0.8 KM 71 124 122 100 Chopparapalli Village Due North & 2.4 KM 68 112 111 100 Mandamarri Colony S 24 o E & 1.5 KM 63 118 117 100 Shankarapalli Village S 66 o E & 4.5 KM 52 90 90 100 Pranahitha colony S 22º E & 3 KM 63 118 116 100

Direction & PM Location 2.5 Distance Min. Max. 98%tile STD CORE ZONE KK-2 Incline N 28 o W & 1.4 KM 31.4 67.2 66.8 60 KK-1 Incline -- 38.4 74.3 73.6 60 KK-5 Pit Office S 47 o E & 2.7 KM 45.2 94.8 94.5 60 RKP –CSP S 2 o E & 6.4 KM 42.6 98.4 98.3 60 BUFFER ZONE GM Office, Mandamarri N 53 o W & 0.8 KM 36.7 63.5 63.2 60 Chopparapalli Village Due North & 2.4 KM 31.6 66.2 65.9 60 Mandamarri Colony S 24 o E & 1.5 KM 32.1 67.4 67.0 60 Shankarapalli Village S 66 o E & 4.5 KM 26.7 44.4 44.2 60 Pranahitha colony S 22º E & 3 KM 31.2 60.4 60.0 60

12

SO Location Direction & Distance 2 Min. Max. 98%tile STD CORE ZONE KK-2 Incline N 28 o W & 1.4 KM 8.2 20.4 19.3 120 KK-1 Incline -- 7.3 15.5 15.3 120 KK-5 Pit Office S 47 o E & 2.7 KM 9.9 14.8 14.7 120 RKP –CSP S 2 o E & 6.4 KM 11.1 14.4 14.3 120 BUFFER ZONE GM Office, Mandamarri N 53 o W & 0.8 KM 9.7 12.3 12.3 80 Chopparapalli Village Due North & 2.4 KM 10.2 15.8 15.3 80 Mandamarri Colony S 24 o E & 1.5 KM 10.0 14.0 13.8 80 Shankarapalli Village S 66 o E & 4.5 KM 10.3 12.9 12.9 80 Pranahitha colony S 22º E & 3 KM 9.7 13.3 13.3 80

NO Location Direction & Distance x Min. Max. 98%tile STD CORE ZONE KK-2 Incline N 28 o W & 1.4 KM 18.8 29.4 29.0 120 KK-1 Incline -- 15.0 27.9 27.5 120 KK-5 Pit Office S 47 o E & 2.7 KM 15.3 31.5 31.0 120 RKP –CSP S 2 o E & 6.4 KM 19.6 26.9 26.9 120 BUFFER ZONE GM Office, Mandamarri N 53 o W & 0.8 KM 17.5 23.5 23.5 80 Chopparapalli Village Due North & 2.4 KM 19.0 28.3 28.3 80 Mandamarri Colony S 24 o E & 1.5 KM 17.6 27.3 26.3 80 Shankarapalli Village S 66 o E & 4.5 KM 15.5 29.5 29.5 80 Pranahitha colony S 22º E & 3 KM 13.8 26.9 26.7 80

13

Air Pollution Control Measures: Already practiced, if applicable Measures Taken (1) Effective water spraying arrangements in Adequate water spraying arrangements have underground working places as well as at been made at all working coal faces and coal loading bunkers at pithead on surface galleries. Water spraying is regularly done at loading and unloading places of tipplers and bunkers at pit head on surface (2) Water spraying arrangement along coal Water spraying is regularly done by tractor transport route within the mine premises mounted water tanker exclusively engaged to serve the purpose. (3) Plantation within the mine premises and As on date 35 ha of Block plantation is done. also along coal transport route Avenue plantation is also done along the coal transport route. Further it is planned to take up during 2014 monsoons. (4) Coal trucks are being covered with Insisting regularly all lorry owners and followed tarpaulins for preventing spillage. tarpaulin covers over coal. (5) The underground workings of the mine The underground workings of the mine are well are being well ventilated by adequate ventilated by adequate ventilation ventilation arrangements. arrangements. The requirements and standards specified in this regard by Director General of Mines Safety (DGMS)

6. Surface Water Quality Monitoring: Monitoring Data: The summary of the monitoring from 01.04.2013 to 30.09.2013 is enclosed as Annexure-4

7. Groundwater Quality Monitoring: Monitoring Data: The summary of the monitoring from 01.04.2013 to 30.09.2013 is enclosed as Annexure-5 8. Phreatic Surface Ground water table: Monitoring Data: The summary of the monitoring from 01.04.2013 to 30.09.2013 is enclosed as Annexure-6 Direction & COD (mg/l) Location Distance Min. Max. 98%tile STD KK 1 Mine discharge -- 10.0 20.0 20.0 250 Area work shop ETP outlet S 30 o E & 0.1 KM 10.0 50.0 47.8 250 Bharath Colony Effluent N 4 o E & 3.1 KM 20.0 38.0 38.0 250 Mandamarri Colony o S 24 E & 1.5 KM 20.0 40.0 39.8 250 Effluent

Annexure-2 9. Effluent Quality Monitoring: PH Direction & Location Distance Min. Max. 98% tile STD KK 1 Mine discharge -- 7.2 8.2 8.1 5.5 to 9.0 o Area work shop ETP outlet S 30 E & 0.1 KM 6.4 8.0 8.0 5.5 to 9.0 o Bharath Colony Effluent N 4 E & 3.1 KM 7.0 8.2 8.1 5.5 to 9.0 Mandamarri Colony S 24 o E & 1.5 KM 5.5 to 9.0 Effluent 7.0 7.9 7.9

14

Direction & TSS (mg/l) Location Distance Min. Max. 98%tile STD KK 1 Mine discharge -- 4.0 14.0 13.8 100 Area work shop ETP outlet S 30 o E & 0.1 KM 8.0 23.5 23.0 100 Bharath Colony Effluent N 4 o E & 3.1 KM 8.0 37.0 35.7 100 Mandamarri Colony o S 24 E & 1.5 KM 8.0 33.0 30.1 100 Effluent

Direction & Oil & Grease (mg/l) Location Distance Min. Max. 98%tile STD KK 1 Mine discharge -- <1 <1 <1 10 Area work shop ETP outlet S 30 o E & 0.1 KM <1 2 1.9 10 Bharath Colony Effluent N 4 o E & 3.1 KM <1 2 2.0 10 Mandamarri Colony o S 24 E & 1.5 KM <1 2 2.0 10 Effluent

Water Pollution Control Measures:

1 Mine discharge water is being An average of 7500 Kilo liters/day of water is being treated in slow sand filters and regularly treated in sand bed filter beds and 2550 Kilo settling tank for removal of coal liters/day excess water is being discharged in to the fines and suspended solids. near by natural water courses and out side fields after removal of suspended solids to augment the ground water table in and surrounding of mine premises. 3500 KLD of water is supplied regularly for domestic usage and it is being supplied after sedimentation, filtration and disinfected by adequate chlorination. 2 Colony effluent is being treated in Domestic sewage will be treated in septic tank septic tanks and soak pits followed by soak pits

15

Annexure-4

Physico-Chemical and Bacteriological Characteristics of Surface Water at Selected Locations in the Study Area

S.N Parameters Unit Test Tolerance CPCB Water quality RESULT o. Method Limits IS : Criteria SW-3 SW-4 SW-5 2296-1982 (Ralla (Ralla (Palla Class C Class Class Class vagu vagu vagu A B C U/S) D/S) U/S) 1 pH - 4500-H+B 6.5-8.5 6.5 - 6.5 - 6.5 - 8.2 8.3 8.3 8.5 8.5 9 2 Temperature ºC 2550. B ------25.7 25.1 25.6 3 Electrical µmhos/cm 2510-B ------536 528 604 Conductivity 4 Turbidity NTU 2130. B ------2.4 1.7 1.8 5 Chlorides as Cl - mg/L 4500-Cl -.B 600 ------23 20 33 6 Colour Pt-co- 2120. B 300 ------20 20 20 7 Nitrates as NO 3 mg/L PDA 50 ------0.07 0.079 0.271 8 Nitrites as NO mg/L 4500-NO ------2 2 BDL BDL BDL .B 9 Total Coliform MPN/100mL 9221A & B 5000 50 or 500 or 5000 less less or less 70 70 240 10 Faecal Coliform MPN/100mL 9221 E ------17 22 130 11 E. Coli Presence or 9221 F ------<1.8 <1.8 Prese Absence nt 12 Pesticides: α–BHC, µg/L 6630. D ------ND ND ND β-BHC, γ-BHC, δ- BHC, o,p-DDT, p,p’ – DDT, α - Endosulfan, β- Endosulfan, Aldrin, Dieldrin 2,4-D, Carboryl Qualitative 6630. D ND ND ND (Carbonate) analysis Malathion Methyl Parathion Anilophos, Chloropyriphos 13 Boron as B mg/L 3120-B 1.0 ------0.08 0.06 0.08 14 Total Chromium as ------mg/L 3120. B 0.05 0.10 BDL BDL Cr 15 Lead as Pb mg/L 3120. B 0.01 ------BDL BDL BDL 16 Nickel as Ni mg/L 3120. B 0.02 ------BDL BDL BDL 17 Cadmium as Cd mg/L 3120. B 0.003 ------BDL BDL BDL 18 Zinc as Zn mg/L 3120. B 5 ------0.09 0.07 0.08 19 Arsenic as As mg/L 3120. B 0.01 ------BDL BDL BDL

16

S.No. Parameters Unit Test Toleranc CPCB Water quality Criteria RESULT Method e Limits SW-3 SW-4 SW-5 (Ralla (Ralla (Palla vagu vagu vagu Class C Class Class B Class C U/S) D/S) U/S) A 20 Odour TON 2150. B ------No No No odour is odour is odour is observed observed observed 21 Dissolved Oxygen mg/L 4500-O.C 4 6 mg/l 5 mg/l or 4 mg/l or more or more 5.8 6.0 5.9 more 22 Bio chemical mg/L IS: 3025 3 2 mg/l 3 mg/l or 3 mg/l Oxygen Demand or less or less 3 BDL 3 for 3 days 27 o C less 23 Ammonical mg/L 4500-NH ------3 BDL BDL BDL Nitrogen as NH 3-N -C 24 Total Suspended mg/L 2540. D 1500 ------o 16 14 16 Solids at 105 C 25 Total Phosphates mg/L 4500-P-D ------BDL BDL BDL 26 Chemical Oxygen mg/L 5220. D ------12 10 12 Demand 27 Oil & Grease mg/L 5520. B ------<1 <1 <1 28 Polyaromatic µg/L 6440.C ------ND ND ND Hydrocarbons (PAH’s): Acenaphthene, Acenaphthylene, Anthracene, B(a)A, B(a)P, B(b)F, B(k)F, Pyrene, Dibenz(a,h) anthracene, Fluoranthene, Fluorene, Indeno(1,2,3-(d) Pyrene, Naphthalene, Phenanthrene, Pyrene, Methyl Naphthalene

17 Annexure-5 Physico-Chemical, Bacteriological Characteristics of Groundwater Collected within the Study Area S.N Parameters Unit Test Method IS: 10500 IS: 10500 RESULT o. Desirable Permissible GW-4 GW-5 GW-6 Limits Limits (MMR (RKP (Sarangapa colony) colony) lli) 1. pH - 4500-H+B 6.5 to 8.5 No relaxation 7.2 7.0 7.0 2. Temperature ºC 2550. B -- -- 25.1 25.2 25.4 3. Electrical Conductivity µmhos/cm 2510-B -- -- 1030 1780 1110 4. Colour Pt-co- 2120. B 5 15 <5 <5 <5 5. Total Hardness as mg/L 2340. C 200 600 392 704 427 CaCO 3 6. Turbidity NTU 2130. B 1 5 0.4 0.6 0.3 - - 7. Chlorides as Cl mg/L 4500-Cl .B 250 1000 91 317 107 - - 8. Fluoride as F mg/L 4500-F .C 1.0 1.5 0.817 0.814 1.25 9. Total Dissolved Solids at mg/L 2540.C 500 2000 o 520 947 546 180 C 10. Calcium as Ca mg/L 3500-Ca.B 75 200 87 125 101 11. Magnesium as Mg mg/L 3500-Mg.B 30 100 43 95 43 2- 2- 12. Sulphates as SO 4 mg/L 4500-SO 4 .E 200 400 129 263 51 - 13. Nitrates as NO 3 mg/L 4500-NO 3 .B 45 No relaxation 25 33 15 - 14. Nitrites as NO 2 mg/L 4500-NO 2 .B -- -- BDL BDL BDL 15. Cyanide as CN- mg/L 4500-CN -.F 0.05 No relaxation BDL BDL BDL 16. Total Alkalinity as mg/L 2320. B 200 600 298 408 423 CaCO 3 17. Hexavalent Chromium mg/L 3500-Cr +6 .B ------BDL BDL BDL as Cr +6

S.No. Parameters Unit Test IS: IS: 10500 RESULT Method 10500 Permissible Desirabl Limits GW -4 GW -5 GW -6 e Limits (MMR (RKP (Saranga colony) colony) palli) 18 Boron as B mg/L 3120-B 0.5 1.0 0.06 0.13 0.06 19 Copper as Cu mg/L 3120-B 0.05 1.5 BDL BDL BDL 20 Manganese as Mn mg/L 3120-B 0.1 0.3 0.08 0.16 0.17 21 Cadmium as Cd mg/L 3120-B 0.003 No relaxation BDL BDL BDL 22 Selenium as Se mg/L 3120-B 0.01 No relaxation BDL BDL BDL 23 Arsenic as As mg/L 3120-B 0.01 0.05 BDL BDL BDL 24 Lead as Pb mg/L 3120-B 0.01 No relaxation BDL BDL BDL 25 Zinc as Zn mg/L 3120-B 5 15 0.09 0.09 0.28 26 Chromium as Cr mg/L 3120-B 0.05 No relaxation BDL BDL BDL 27 Nickel as Ni mg/L 3120-B 0.02 No relaxation BDL BDL BDL 28 Barium as Ba mg/L 3120. B 0.7 No relaxation BDL BDL BDL 29 Silver as Ag mg/L 3120. B 0.1 No relaxation BDL BDL BDL 30 Molybdenum as Mo mg/L 3120. B 0.07 No relaxation BDL BDL BDL 31 Total Coliform MPN/100 ml 9221A & B -- -- <1.8 <1.8 <1.8 32 Faecal Coliform MPN/100 ml 9221 E -- -- <1.8 <1.8 <1.8 33 E. Coli Presence / 9221 F -- -- <1.8 <1.8 <1.8 Absence 34 Pesticides: α–BHC, β-BHC, µg/L 6630. D Absent 0.001 ND ND ND γ-BHC, δ-BHC, o,p-DDT, p,p’ –DDT, α - Endosulfan, β- Endosulfan, Aldrin, Dieldrin 2,4-D, Carboryl (Carbonate) Qualitative 6630. D Absent 0.001 ND ND ND Malathion Methyl Parathion analysis Anilophos, Chloropyriphos

18

S.No Parameters Unit Test Method IS: 10500 IS: 10500 RESULT . Desirable Permissibl GW-4 GW-5 GW-6 Limits e Limits (MMR (RKP (Saranga colony) colony) palli) 35 Odour TON 2150. B Agreeable Agreeable No Odour No No observed Odour Odour observed observed 36 Taste FTN 2160. B Agreeable Agreeable No flavour No No observed flavour flavour observed observed 37 Residual free chlorine mg/L 4500-Cl -.B 0.2 1.0 BDL BDL BDL 38 Orthophosphates mg/L 4500-P-D -- -- BDL BDL BDL 39 Anionic Detergents ( as mg/L IS:13428 : 0.2 1.0 MBAS) 2005 K <0.2 <0.2 <0.2 40 Total Ammonia mg/L - - - 41 Chloramines mg/L - - - BDL BDL BDL 2- 2 42 Sulfide as S mg/L 4500. S - G - - BDL BDL BDL 43 Mineral Oil mg/L IS:3025 0.5 No Absent Absent Absent (part 39) relaxation 44 Chemical Oxygen mg/L 5220. D -- -- 8 8 6 Demand 45 Polyaromatic µg/L 6440.C -- -- ND ND ND Hydrocarbons (PAH’s): Acenaphthene, Acenaphthylene, Anthracene, B(a)A, B(a)P, B(b)F, B(k)F, Pyrene, Dibenz(a,h) anthracene, Fluoranthene, Fluorene, Indeno(1,2,3-(d) Pyrene, Naphthalene, Phenanthrene, Pyrene, Methyl Naphthalene

NTU – Nephelometric Turbidity Unit; TON – Threshold Odour Number; FTN – Flavor Threshold Number; BDL – Below Detection Limit, Detection Limit –Cyanide – 0.05 mg/L ; Hex. Chromium – 0.05 mg/L; Copper – 0.02 mg/L; Manganese – 0.01 mg/L; Cadmium – 0.01 mg/L; Selenium – 0.04 mg/L; Arsenic – 0.02 mg/L; Lead – 0.04 mg/L; Aluminum – 0.03 mg/L; Chromium – 0.02 mg/L; Nickel – 0.02 mg/L; Residual free chlorine – 1 mg/L; Nitrites – 0.02 mg/L; Orthophosphates – 0.05 mg/L; ND-Not Detected; Detection Limit : Pesticides– 0.1 ppm; PAHs – 1 ppm. *Not Performed –PCBs, Trihalomethanes, NP: (Not Performed): Radioactive materials,Alachlor, Atrazine, Butachlor, Ethion, Monocrotophos.

19

Water Conservation Measures: 1 Mine discharge water is being Excess mine discharge water 2550 KLD is letting in to reused for mine requirement and the near by natural water courses and out side fields colony needs and remaining after consuming the water for drinking, dust water is let off in to nearby tanks suppression, plantation and township. The requirement for use by villagers for irrigation of water for all the above is 7500 KLD. 2 Rain water harvesting structures 34 no Rain Water Harvesting structures were are being constructed in and constructed in Mandamarri area. These have been not around the project area for effectively functioning since; they were constructed augmenting groundwater during the period 2004-05. It is therefore, fresh recharge. proposals are being prepared for construction of new Rain Water Harvesting Structures / pits. 3 Phreatic surface levels are being Season – wise phreatic surface levels have been monitored throughout the life of monitored. It is observed that, during the monsoon the mine. period, the levels are found as 1.85 m (mango garden, sandronpalli) where the mine was situated at the distance of 1.3 Km which reveals no effect on the depletion of water table as compare to its original measuring depth.

Noise Pollution Control Measures:

Sl. Description Control Measures taken up No. 1 In the high noise intensity working 65 Nos of Ear plugs have been provided to areas / zones earmuffs or earplugs employees exposed to higher noise levels viz or any other suitable personal Coal cutters; Hauler Operators, Pump Operators, protective equipment have been trammers and SDL operators etc., and also provided to the workmen Vehicles are regularly maintained to control engine noise. 2 The main mechanical ventilators The effective functioning of MV fan and its fittings (MV Fans) have been provided with have been regularly checked for rectify the evasee which dampens the noise. defects to control the noise. 3 Green belt developed all around the 35 ha of Green belt of rich canopy is maintained main mechanical ventilator and around lease area to attenuate noise levels. mine premises to dampen the noise.

8. Capital and Revenue Expenditure incurred on Environment Management and Pollution Control Measures:

Capital expenditure already incurred towards Environmental protection measures

SL VALUE ACTIVITY NO Rs. Lakhs 1 Pollution control (a) Air Pollution Control 0.85 Pumping arrangements (b) Water pollution control i) Construction of Filter bed 18.69 (including pumping arrangement) ii) Construction of Septic tank at mine premises 4.02 iii) Black topping of roads within mine premises 0.30 2 Expenditure on plantation 2.06 3 Fan evassee (10% cost of fan mechanicals) 2.58 Total 28.50

20

Additional Capital expenditure already incurred towards Environmental protection measures (Direct Cost)

SL ACTIVITY VALUE Rs. NO Lakhs 1 Pollution control equipment 5.00 (Mist spray arrangements at coal loading bunkers) 2 Greenbelt development within mine boundary 41.62 3 Scientific study to be conducted i. Generation of BLD and preparation of EMP 7.66 ii) Subsidence prediction study 3.00 iii) Expenditure for public hearing 1.00 iv) Ground water clearance charges 0.10 4 Phreatic surface monitoring bore holes 1.40 5 Flow meters 0.24 6 Rain water Harvesting structures 1.20 7 Construction of settling pond 1.00 TOTAL 62.22

Revenue expenditure incurred towards Environmental protection Measures for the reporting period April, 2013 to Sept, 2013

Sl. Description Expenditure in Rs. No Air Pollution Prevention & Control measures (Free Gas supply 1 2789118.00 of workers) 2 Air & Water monitoring cost 11021374.00 3 Plantatation (Block & Avenue) 2457916.00 4 Water spraying arrangements 122299.00 5 Water cess 12641.00 6 CFO fee 22500.00 7 filter bed maintenance 102300.00 Total 1,65,28,148.00

9. Socio-economic Measures:

i. A common central township is provided on a non coal bearing area and it is maintained with such facilities like dispensary, schools, drinking water supply, market place, recreation clubs, Parks, well lighted approach roads, dust bins etc., at various places in the colony and it is away from mining activity. Sulabh Complexes are constructed in and around mining colonies in addition to individual toilets provided in quarters.

ii. Existing no of quarters for this mine : 608

iii. Workers were educated about the importance of family planning and an incentive of Rupees 1000/- along with 6 days leave is being given as encouragement.

21 iv. Arrangements were made for giving vaccination to children and adults to protect from diseases and steps are taken to eliminate / control Malaria under effective supervision of Health Officer. v. All necessary steps are being taken for improving general sanitation of Township/Colony under effective supervision of Health Officer. 6324 m3 of garbage was removed from the colonies during this six months period. vi. Sports and games are conducted regularly for workmen. vii. Greenery is developed in the existing colonies. viii. SCCL, Mandamarri area had been encouraging the employees to plant saplings of different varieties including fruit bearing and shady trees by distributing saplings free of cost during monsoon season of every year. ix. Various training programmes have conducted for unemployed surrounding village people and the details as follow: Name of the Vocational Training Programme Total no of persons trained Computer Hardware 100 Fashion Designing 210 Motor Vehicle Driving 210 Tailoring 80 Multi media 724 Paper Carry Bags 60 Beautician 93 Juki machine training 232 Saree rolling 102 Spoken English 40 Dress making 552 Screen printing 61 Photo lamination 40 Electrician 26 Photo & Videography 66 Agarbatti making 20 Gas stove repairs / tent house 2 Literacy Programme for illiterate spouses of 4037 work persons Soft Toys 4 AP Police Training 1442

22 x. 5200 Fruit bearing plants of Mango, Sapota, Guava, Orange, Pomegranate, Lemon etc to the villagers. xi. To encourage unemployed youth on Entrepreneurs Development Programme for establishment of Ancillary units and from which the products will be utilized in mines and departments and the details are as follow: Presently, 14 new entrepreneurs were selected for establish new ancillary units ie BPA-3, MM-5 and SRP- 6 Entrepreneur Development Programme was conducted to these 14 candidates from 4th June to 14th June 2012 at Yellandu Club, Mandamarri jointly by the Centurion University, Khadi Gramodyog Vidyalay and Officials from Singareni collieries Co Ltd., The units proposed are: Roof bolts – 4 persons, motor winding works – 1, House wiring – 3, GI Canisters – 1, Dog nails, bolts & nuts – 1, Fish plates – 1, Fabrication – 2, GI Wire items – 1 Out of these 14 persons, 13 have applied for loan through Prime Minister’s Employment Generation Programme as detailed Below: For Rs 25 lakh: 4 persons For Rs 20 lakh: 1 person For Rs 10 lakh: 2 persons For Rs 7 lakh: 1 person For Rs 1 lakh: 5 person All the above 13 candidates obtained Vendor codes from SCCo Ltd. and got their proposed firms registration. Development activities (CSR) under SHAPe Programme in the surrounding villages from 2003-04 to 2008-09:

a).Towards school building and compound : 21.80 lakhs b).Towards drinking water in the surrounding villages (namely Mandamarri, Amaravadi, Kurmapalli, Kasipet and Muthyam palli etc) for bore holes, overhead tanks and pipe lines : 24.50 Lakhs

c).Towards BT, CC roads, drainages, bridges & street lighting : 498.25 Lakhs

Total : 544.55 Lakhs

xii. Mobile medical camps conducted in near by villages and the details are as follow: (for the period April, 2013 to Sept, 2013 : six-months period—25 camps)

Sl. Date of Place / Villages covered No. of persons No. conducting benefited 1 03/04/2013 Dubbapalli & Sandronpalli 77 2 10/04/2013 Subhash Nagar (RKP) 32 3 17/04/2013 Adilpet 74 4 24/04/2013 Ponnaram 66 23 5 08/05/2013 Subhash Nagar (RKP) 91 6 15/05/2013 Sarnangapalli 55 7 22/05/2013 Venkatapur 53 8 29/05/2013 Gudipalli - MLA Colony 64 9 05/06/2013 Mamidigattu 58 10 12/06/2013 Subhash Nagar 55 11 19/06/2013 Turkapalli 62 12 26/06/2013 Sonapur 64 13 03/07/2013 Dubbapalli & Sandronpalli 59 14 10/07/2013 Subhash Nagar 67 15 17/07/2013 Kankur & Mudigunta 243 16 24/07/2013 Adilpet 104 17 31/07/2013 Ponnaram 42 18 7/08/2013 Venkatapur 87 19 14/08/2013 Subhash Nagar (RKP) 31 20 21/08/2013 Sarangapalli 42 21 28/08/2013 Gudipalli - MLA Colony 69 22 04/09/2013 Mamidigattu 95 23 11/09/2013 Subhash Nagar 89 24 18/09/2013 Turkapalli 57 25 25/09/2013 Dubbapalli & Sandronpalli 60 Total 1796

10. The minutes of EMC is as Follow:

MINUTES OF THE ENVIRONMENTAL COMMITTEE MEETING HELD ON 18.09.2013

Area level Environmental committee meeting of KK-5 Incline, KK-1 Incline and RK-1A Incline held on 18.09.2013 under the Chairmanship of Shri J.Kumara Swamy, Agent, KK Group of mines and the following executives were attended.

Sl. Name Designation No Shri 1 J. Kumara Swamy Agent , KK Group Acted as Chairman Convener / Co- 2 D.Sanjeeva Reddy SE(ENV), MM coordinator 3 P Veera Bhadra Rao Colliery Manager Member 4 P Narasimha Rao Safety Officer, KK1 Incline Member 5 P Bala Krishna EE(E&M), KK-1 Incline Member 6 K Rajanna Dy.SSO, KK-1 Incline. Member 7 K.Rajasekhar DGM(Civil) Member 8 K.Nagaraju Group Engineer, KK Group Member 9 Hari Narayana Sr. Forest Officer Member

At outset, SE (ENV) briefed about each condition imposed in Env. Clearance and for every condition present status reviewed and the ATR vs responsibility of the executive is being furnished as under.

Sl. Action to be taken Responsibility No. 1 Land use pattern, present status including plan. Dy.SSO, KK-1 Incline. 2 Plantation Proposal during the year 2014 DySSO, KK-1 incline. 3 Construction of rain water harvesting structures DGM(Civil), MM 4 Construction of STP, at Bharath Colony DGM (Civil), MM 5 Construction of ETP at CHP DGM (Civil), MM 7 Information of PME for last six months Sr. Personnel Officer, KK-1 8 Adequate measures to be taken for control of Air pollution and Safety Officer, KK – 1 inc 24 Noise levels below standards. 9 Details of dust respiratory to be given to the workmen for the Safety Offiece, KK-1 inc period of 1 st April 2013 to 30 th Sept, 2013 10 Condition wise compliance status for earlier EPH minutes and Manager, KK-1 incline ATR 11 PO, KK 1 incline reviewed the ground water level monitoring Manager, KK 1 incline reports and advised Manager, KK 1 to frame a course of action to be taken for free supply of water to the near by villages. If they ask for supply of water in summer season. 12 PO, KK 1 incline advised DGM (Civil) to make necessary DGM(C) , MM proposals for construction of Rain water harvesting structures and also STP at Vorregadda area 13 PO, KK 1 incline advised Manager to construct a Vermi Manager, KK 1 incline Compost Pit beside of the Canteen

The above meeting was concluded by expressing thanks to the participants.

PROJECT OFFICER, KK GROUP

25 The Condition Vs Compliance of Groundwater clearance: Sl. Condition Compliance No. 1 Periodical monitoring of Ground water Complied and the report of the same submitted levels and quality (every month) should be to Dy Director, AP Ground water dept., Nirmal taken and report must be submitted to the on half yearly basis vide lr.no. Deputy Director, Ground water Department, MMR/ENV/GW01/432, Dated 13-04-2013 Nirmal, regularly. 2. Rain water harvesting structures should be For construction of Fresh Rain water harvesting taken up in all the villages with in the radius structures, initiated new proposals. of 10 km of the project area. 3. Afforestation in surrounding areas should As on date, plantation in 35 ha in KK 1 incline be taken up. mine take area has been taken up besides the total Block plantation of 835.00 ha was carried out in the area out side, within the mining lease and in townships etc., 4. Dewatering from mine if any, may cause to The excess mine water of 2550 KLD is being be planned considering needs of the regularly discharging in Vorregadda vagu (After farming community. treated) and thus the neary by villages Narlapur and Mandamarri village people are benefitted by utilizing the water for their Agricultural activities. Environmental Public Hearing Minutes Vs Response/Commitment of Project Proponents And Present Status Date of Public Hearing Conducted: 13-02-2008 (11.00 AM) Venue: Zilla Parishad Girls High School, Mandamarri (Village & Mandal), Adilabad (D) Sl. Response/Commitment of Project Issue raised by the public Present status No. proponents 1 Transportation of coal by It was informed that Water spraying Tarpaulins are covering Lorries through villages is at RK-1A Incline Weigh Bridge is while transporting of causing air pollution and being carried out to curb with air Coal. complained that coal pollution. Air pollution control transport lorries are not measures such as covering the coal Laying of WBM road covered with tarpaulin and trucks with tarpaulins will be from Pakistan Camp to requested for providing road ensured. Mandamarri Rly. Stn is dividers. made. After settling of He informed that from Pakistan road with WBM cement Requested for taking steps Camp at RKP, coal is being road will be laid. to redress air pollution transported by private Washeries problem from Pakistan and not by SCCL; however he Camp to Mandamarri Rly would take up the matter with the stn. and requested for laying owners of the Washeries to resolve of cement road. the pollution problem of this area. 2 Informed that the General Manager, Mandamarri It is agreed to supply surrounding villagers are explained that due to opening of the water through tankers facing drinking water and mines by SCCL, development has and by drilling additional requested to solve the water taken place in surrounding villages bore wells if any village supply problem of such as transportation, and well goes dry due to Chirrakunta Village due to establishment of other ancillary mine activities. KK-5 incline SCCL should industries. supply mine water to the As on date, Village Gram nearby villages He assured that he would examine Panchayat made Water the possibility of supply of water and supply system from clarified that Chirrakunta Village is Open well and found no not falling in the mine plan of KK-5 noticeable complaints. Incline and stated that water However it is to decide to problem is not due to mining drill additional Bore Wells 26 activities. by the company. Drilling of 40 bore wells in the surrounding villages work tender floated and to be awarded. 3 Informed that few villages Regarding water problems, General Presently, the problem is are lying over the mine Manager, Mandamarri assured that resolved. Since excess workings of KK-5, RK-1A he would visit the villages and will mine water is being and MK-4 Inclines and due examine the possibility of diversion diverted through to underground mining of excess mine water from mine. Palavagu and near by operations, it is becoming villages are utilizing the difficult to locate drains for He further requested villagers to water. agricultural purpose and consult SCCL before digging new they area compelled to rely bore well for identification of proper on bore wells and requested place and also informed that the SCCL for diversion of management will depute its Hydro- excess mine discharge geologist to identify suitable location water to these villages for for making bore wells. cultivation. 4 Stated that due to mining General Manager, Mandamarri Compensation paid to operations in KK-5 Incline, informed that there will be no harm the Mango garden owner the bore wells may dry up to said bore well as the working of and the area is under and the mango gardens may KK-5 Incline will not reach up to that possession of the be damaged, rendering the place. In case of any problem the Company. dependents into distress same will be looked into. and requested that the company should provide livelihood or compensation for the loss. 5 Requested SCCL to allocate General Manager informed that in Some of the SHAPE SHAPE funds to their village SHAPE-I, II & III programme funds also provided to for supply of drinking water majority of the funds were utilized the affected villages of from mine as well as for Kasipet and Muthyampalli and the mine. Godavari River Water and other nearby villages and informed electricity and further that allocation of the funds are made requested for lying of by the Hon’ble MLA and not made cement roads and by the SCCL. He assured that be construction of drains in would take up the matter with the nearby villages. concerned for allocating SHAPE funds for the development of nearby villages of the mine. 6 Requested for construction He clarified that due to out-sourcing The issue is complied by of drains and septic tanks at of sanitation work, sanitation has Construction of Sulabh various places and improved in Mandamarri Area. GM Complex in III zone, MM. maintenance of sulabh informed the construction of Sulabh complex in III Zone, MM complex may be undertaken but Area by SCCL maintenance of the same should be done by the concerned Government Authority. 7 Requested to extend the It was informed that training This is being provided vocational training facility in programmes are being undertaken regularly under SSS Tailoring and Dress making, for the unemployed youth by activities. Motor Vehicle Driving etc., to Singareni Sewa Samithi (SSS). the unemployed youth of nearby villages.

27

28 Annexure -6 ATTITUDE OF PHREATIC SURFACE IN GODAVARI VALLEY COAL FIELD Area:Mandamarri Nearest Total Well Type of Dimensions Measuring mine & Name of village Location depth Geology Period No. well (m) point (m) 2011 2012 2013 dist. (m) (km) Winter 5.98 6.96 5.35 Pre- KK-2 inc. 7.40 7.14 7.21 Bharat Barakar monsoon 1 Somagudem Domestic 1.0 10.5 0.70 colony Sst Monsoon 5.16 3.00 4.91 Post- 1.5 6.25 4.38 monsoon Winter 3.70 4.76 4.55 Pre- KK-2 inc. 5.35 6.27 AB Teak Barakar monsoon 2 Choprapalli Domestic 4.5 6.0 0.3 plantation Fm. Monsoon 3.25 4.65 AB Post- 1.5 2.73 2.85 monsoon Winter 10.65 12.16 11.55 Near Pre- KK-2 inc. 12.90 14.67 12.62 rly.gate Talchir monsoon 3 Buradagudem Domestic 1.4 14.8 0.60 towards Fm. Monsoon 8.30 8.42 9.18 mncl. Post- 1.5 11.50 11.86 monsoon Winter 3.50 4.10 4.49 KK-5&5A Pre- 4.53 5.12 4.55 inc. Talchir monsoon 4 Mandamarri Bus stand Domestic 1.3 6.6 0.80 Fm. Monsoon 1.50 4.18 2.17 Post- 1.7 3.55 3.62 monsoon Winter 6.43 7.20 6.90 KK-5&5A Pre- Barren 7.44 9.33 7.55 inc. Hanuman monsoon 5 Sandronipalli Domestic 3.0 8.5 Measures 0.5 Temple Monsoon 7.10 7.76 4.98 Fm. Post- 1.3 6.92 6.85 monsoon

29

Winter 2.77 4.25 2.90 KK-5&5A Mango Pre- Barren 4.70 5.12 5.57 inc. garden monsoon 6 Sandronipalli Agriculture 6.0 6.0 Measures 0.50 towards Monsoon 3.10 1.85 1.95 Fm. Adilpet Post- 1.3 3.48 3.55 monsoon Winter 9.60 10.20 9.52 KK-5&5A Pre- Barren 10.72 11.12 10.77 inc. monsoon 7 Dubbapali In village Domestic 2.0 14.0 Measures 0.40 Monsoon *9.65 10.50 8.45 Fm. Post- 2.5 11.55 10.20 monsoon Winter 1.00 1.60 NR KK-5&5A Pre- Palachettu 1.02 1.92 2.95 inc. Barakar monsoon 8 Mandamarri area, Zone Domestic 1.0 4.6 0.30 Fm. Monsoon 1.30 1.45 1.38 III Post- 1.3 1.00 NR monsoon Winter 4.82 8.77 8.65 Near Rly Pre- RK-1A *9.02 Dry 6.65 Gate Sullavai monsoon 9 Ketanpalli Domestic 3.0 9.3 0.20 towards Fm. Monsoon 3.60 6.55 5.51 RKP Post- 2.5 6.30 3.53 monsoon Winter 5.48 6.50 6.75 Pre- KK-5 6.86 6.89 6.78 Near rice Kamthi monsoon 10 Adilpet Domestic 1.8 11/7.0 0.50 mill Fm. Monsoon 5.80 6.20 3.82 Post- 6.5 6.75 6.55 monsoon Winter 8.90 11.30 9.45 kk5&mk4 Pre- 10.80 10.85 10.78 inc. Centre of Kamthi monsoon 11 Adilpet Domestic 3.0 11.0/12.0 0.50 the village Fm. Monsoon 10.70 11.27 8.12 Post- 6.5 10.60 10.45 monsoon

30 Winter 5.05 6.52 3.00 KK-5&5A Pre- 6.85 6.89 6.65 inc. In the Kamthi monsoon 12 Avudam Domestic 3.0 7.5 G.L village Fm. Monsoon 3.35 4.10 2.82 Post- 11.8 5.20 5.25 monsoon Winter 3.10 4.60 4.49 KK-5&5A Pre- Road side 4.58 4.62 4.03 inc. Kamthi monsoon 13 Avudam towards Agriculture 4.5 6.0 G.L Fm. Monsoon 3.20 4.32 1.71 village Post- 11.00 4.25 NR monsoon Winter *8.46 Dry 3.83 RK 1A Pre- Dry NR 5.55 INC monsoon Barren Monsoon 7.75 7.30 1.26 14 Sarangapalli Main road Domestic 1.3 1 0.0 Measures 0.50 Post- 1.80 Fm. 9.35 NR monsoon Post-

monsoon

Note: * indicates new well started adjacent to the previous existing well NA : Not approachable NR : Not Recorded

31