Environment and Social Safeguards Monitoring Report 2009 - 2017

Project Number: 37749-013 Loan 2465/Loan 8238(OFID) May 2019

Philippines: Agrarian Reform Communities Project II

Prepared by ARCP II – NPCO for the Asian Development Bank

This report does not necessarily reflect the views of ADB or the Government concerned, and neither the ADB nor the Government shall be held liable for its contents.

ABBREVIATIONS/GLOSSARY

ARC Agrarian Reform Communities ARC Clusters Agrarian Reform Community Clusters ARCP II Second Agrarian Reform Communities Project CNC Certificate of Non-Coverage CNO Certificate of Non-Overlap CP Certification Precondition DAR Department of Agrarian Reform ECC Environmental Clearance Certificate EMB Environmental Management Bureau GOP Government of the IP Indigenous Peoples LGU Unit NCIP National Commission on Indigenous Peoples NSAC National Subproject Approval Committee (composed of representatives (Assistant Secretary/Director level) from Department of Agriculture(DA)/National Irrigation Administration(NIA); NCIP, Department of Environment & Natural Resources (DENR)/Environment & Management Bureau (EMB); Department of Public Works & Highways (DPWH); Dept of Budget & Management (DBM) , Department of Interior and Local Government (DILG) ; Department of Finance (DOF)/Bureau of Local Government Funds(BLGF) and Municipal Development Funds Office (MDFO) and National Economic Development Authority (NEDA) NGALGU National Government Assistance to Local Government Unit PAPs Project Affected Persons RSAC Regional Subproject Approval Committee (composed of Regional representatives of the DAR, DA, DPWH, DENR, NCIP and NEDA)

This environmental and social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any program or strategy, financing any project, or by making any designation of or reference to a particular or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

2

CONTENTS

Executive Summary

Introduction and Project Overview

Safeguards Monitoring and Evaluation

Social Safeguards Performance Monitoring

Occupation and Health Safety

Grievance Redress Mechanism

Conclusion

Attachments

3

ATTACHMENTS

Annex I: List of /ARCs/ARC Clusters covered by ARCP II Annex II: Project Organizational Structure Annex III: ARCP II Safeguards Manual Annex IV: List of Approved Subprojects Annex V: ARCP II ESS Monitoring Form Annex VI. Sample ESS Monitoring Form Submitted by LGU (FMR; Irrigation) Annex VII. Photo documentation Please add Photos of consultation, training, etc.

4

EXECUTIVE SUMMARY

The Agrarian Reform Communities Project II or ARCP II is designed to enable agrarian reform beneficiaries (ARBs) to reduce poverty and sustain improved incomes and quality of life. It aims at enhancing the capabilities and well-being of the poor and marginalized groups in 152 ARCs and 11ARC Clusters spread in 6 covering 19 eligible provinces and about 168 LGUs in the southern part of the country. It is an integrated and complementary package of assistance involving (a) community-driven development; (b) agriculture and enterprise development; (c) rural infrastructure; and (d) project implementation and management.

ARCP II is funded from loans from the Asian Development Bank (ADB) and the OPEC Fund for International Development (OFID) amounting to US$70 million and US$30 million, respectively. Loan effectivity is 2009, with the original project completion date of December 2014 and loan closure of 31 December 2013 for OFID loan and 30 June 2015 for ADB loan. However, due to the significant delays encountered by the Project, the physical completion and loan closing dates for both the ADB and OFID loans were extended first to 31 December 2015 and June 2016, respectively. It was again extended to 31 December 2017 for its physical completion, while financial closure is 30 June 2018 for ADB and June 2017 for OFID loans.

As part of the Loan covenant, the DAR as the executing agency, together with ARCP II- National Project Coordination Office put in place the Environment and Social Safeguards of the Project. ESS Point Persons at the DAR national, regional and provincial levels were provided training and orientation by the ESS Consultant engaged by the Project. Thus, setting up the ESS system at the ARCP II. LGU partners were also oriented and provided with ESS Safeguard Manual and guidance in the preparation of safeguard documents. ESS Point Persons at the field level together with the MPDCs of the LGUs are part of the project team together with the Project Economist and Rural Infra Engineers, to ensure that ESS are not left out from project validation, preparation and implementation.

Under the rural infrastructure component, there are 475 approved subprojects of which 333 are physically completed, with 142 still ongoing. These subprojects complied with the ESS documentary requirements from securing of CNC/ECC, CNO/CP and ROW acquisition. Though it was disclosed to the community and project affected persons their right to be compensated for their affected lands and improvements, most of the PAPs have donated the affected lands or executed quit claim in favor of the LGUs. It is their way of helping the LGU to meet the cost sharing requirement under the ARCP II. But there are also PAPs that asked for payments for affected lands and crops, especially those affected by new or road opening. The LGUs of Daram and Almagro in West compensated the PAPs affected by their farm-to-market roads.

Overall, the LGUs complied with environment and social safeguards in the implementation of their subprojects, especially in securing safeguards documents. The weakness is in the monitoring and reporting of safeguards implementation. The revised ARCP II ESS Monitoring Form was downloaded to the field almost third quarter of 2016, and was left out by the LGUs in lieu of ARCP II-related technical and financial documents and concerns.

5

I. Introduction and Project Overview

Project Number L2465/8238-PHI: AGRARIAN REFORM COMMUNITIES PROJECT II and Title: Safeguards Environment B Category Involuntary B Resettlement Indigenous Peoples A Reporting period: March 2009 – Dec 2017 Last report date: First Reporting Project  On 27 October 2008, Asian Development Bank (ADB) and the Background and OPEC Fund for International Development (OFID) approved two loans key sub-project worth US$70 million and US$30 million (equivalent to P3.15 billion and activities: P1.35 billion, for a total of P4.50 billion), respectively, to the Republic of the Philippines to finance Agrarian Reform Communities Project II (ARCP II). The loan took effect on 4 March 2009 and is expected to be completed by December 2014. The Project was officially launched on 20 March 2009. Original project completion date was December 2014, while the loan closure dates were 31 December 2013 and 30 June 2015 for the OFID and ADB loans, respectively.

 The Department of Agrarian Reform (DAR) is the executing agency (EA) with the assistance from different national government agencies (NGAs), local government units (LGUs), and non-governmental organizations (NGOs) and people organizations (POs) in the covered Agrarian Reform Communities (ARCs). The government agencies include all participating municipal LGUs and DAR offices at the regional and provincial levels, DAR-ARMM, the CARP implementing partner agencies such as the Department of Agriculture (DA), Department of Environment and Natural Resources (DENR), Department of Public Works and Highways (DPWH) and specialized agencies such as the National Irrigation Administration (NIA) and the NCIP.

3. ARCP II is designed to enable the agrarian reform beneficiaries (ARBs) to reduce poverty and sustain improved incomes and quality of life. The Project aims at enhancing the capabilities and well-being of poor and marginalized groups in 152 Agrarian Reform Communities (ARCs) and 11 ARC clusters spread across six regions, covering 19 eligible provinces and approximately 168 LGUs in the southern part of the country (Annex 1 List of Provinces covered by ARCP II).

4. The Project goal will be achieved through the implementation of an integrated and complementary package of assistance involving; (i) community driven development (CDD); (ii) agriculture and enterprise development (AED); (iii) sustainable rural infrastructure (SRI); and (iv) project implementation and management (PIM).

5. In 2009, the following key activities were carried out:

6

 Organized project offices, i.e., the National Project Coordination Office (NPCO) at the DAR Central Office, the Regional Project Management Office (RPMO) in 6 DAR Regional Offices (DARRO), and Provincial Project Management Office (PPMO) in the 19 DAR Provincial Offices (DARPO). Hiring of project consultants and staff, taking on board regular staff from DAR, and procurement of office furniture and equipment.  Project Executive Committee (PEC) and the National Subproject Approval Committee (NSAC) and Regional Subproject Approval Committee (RSAC) were organized. These committees are composed of official representatives from the oversight agencies and CARP implementing partner agencies at the national and regional levels. The PEC approves the Project’s annual work & financial plan. The NSAC review, evaluate and approve rural infrastructure subprojects costing more than US$75,000 (or its peso equivalent while the RSAC deals with the rural infrastructure subprojects below US$75,000. The NSAC deliberated on 18 rural infra subprojects but approved only 17 SPs (Annex IV- List of Approved Subprojects).  At the municipal level, a Local Project Office (LPO) is created through an Executive Order issued by the Local Chief Executive, to oversee the implementation of the approved rural infrastructure subprojects, and other ARCP II-related activities in the LGU. It is headed by the Municipal , and composed of the Municipal Planning & Development Coordinator (MPDC), Municipal Engineer (ME), Municipal Agriculture Officer (MAO), Municipal Accountant and other municipal officials involved in the project.  ADB Special Mission on Sept 23-24, 2009 participated in the Project’s regional/provincial orientation workshop while First Project Review Mission on October 19 -30, 2009 assessed ARCP II’s physical and financial progress for 2009.  ARCP II Project Operation Manuals for CDD, for AED, for Rural Infrastructure and for Environment and Social Safeguards was approved by ADB.  Orientation workshops on Rural Infrastructure and Environment and Social Safeguards for concerned DAR officials and partner LGUs for VIII, IX and ARMM.

6. In 2010, a total of 18 subprojects were approved by the NSAC (9) and RSAC (9). Orientation and training on FS/DE/ESS was conducted simultaneously for the DAR personnel assigned as Economist, Rural

7

Infra Engineers and ESS Point Persons in the covered DARROs and DARPOs. Other key activities include:

 A Special Loan Administration Review Mission dispatched by the ADB on June 21-23, 2010 to work on (i) LGU Ganassi and United Nation World Food Programme (UNWFP) collaboration; (ii) updating procurement packages of FMR as the template for other FMR SPs; and (iii) finalizing the TOR for the consultant team to assist the overall management of the Project.  The Mission obtained assurance that the UNWFP committed to finance unskilled labor to help the Ganassi, comply with the NG-LGU cost sharing mechanism; gathered justification to support the request of LGU to include the force account as an option and a template for RI component; and finalized the draft TOR for the consultant team to support project overall management.  For ESS, the NPCO and other project team members observed the safeguards requirements provided for in the ARCP II Environment and Social Safeguards Manual (Annex III), for subprojects presented to the NSAC for deliberation and approval.

7. In 2011, about 77 subprojects) were approved by the NSAC and RSAC. These SPs have varying degree of ESS compliance. During the year, the ADB conducted two (2) Loan Review Missions, one in July and in November. Among the recommendations of the Mission was to conduct a short (4-day) gender and social safeguards mission in the 2nd week of January 2012 to agree with revised Gender Action Plan’s (GAP) implementation milestone, resources and knowledge products; and address issues of marginal groups and microfinance and discuss reporting complaint mechanism for IP. Other major events/activities under the Project:

 Under the RI component, the GOP has approved the inclusion of costs for environmental and social safeguards such as permit fees, application fees, and cost of right of way as part of the LGU equity contribution.  In July 1, 2011, the DAR engaged two joint venture (J/V) partners namely Orient Integrated Development Consultants Inc (OIDCI) and Hineleban Foundation Inc (HFI) as Special Management Team (SMT) to support the implementation of ARCP II in the Autonomous Region of Muslim (ARMM). SMT’s engagement is for 36 months, and started July 2011. The SMT assisted the ARMM LGUs in project proposal preparation and in securing the document required by the

8

ARCP and the NSAC including environment and social safeguards documents.  The DAR - ARCP II also engaged the services of the Engineering and Development Corporation of the Philippines (EDCOP), for quality assurance services for rural infrastructures.

8. In 2012, the Loan Review Mission (intermittently from November 23 to December 19, 2012) aimed to review the project implementation and the projected contract awards and disbursements from 2013-2015. Environment and social safeguards was not discussed in the review. The recommended conduct of a short (4-day) gender and social safeguards mission in the 2nd week of January 2012 did not materialize.

About 252 subprojects were approved both by NSAC and RSAC. During the period the National Government Assistance to LGU (NGALGU) was approved. Such was a big support to the LGU, as NGALGU provides the 25% of the LGU counterpart funds for every approved subproject of the LGU. It was also in 2012 when:

 In 5 January, ADB approved the request of the ARCP II- NPCO to make use of a Pro-forma Resolution expressing the commitment of Barangay to ensure Environment and Social Safeguards in the implementation of Social Infrastructure Subproject under the ARCP II, in lieu of the identified project safeguards requirements for Rural Infrastructure. The Pro- forma SB Resolution on Social Infrastructures/ for Social Infrastructure subprojects, is a Resolution ensuring that the barangay shall take care of the environmental and social safeguards concerns, including right of way sans the safeguards documents required by ARCP II per its Safeguards Manual. Social infrastructures subprojects are health station, day care centers, multi-purpose building, tribal centers and school buildings.  A back to back M & E and ESS Training Workshop for ARCP II’s M & E and ESS Point Persons, respectively of the 19 provinces and 6 regions was conducted in August, wherein sharing of experiences and good practices in ensuring safeguards compliance was done. The proposed MOA among IA/PO, LGU and ARCPII was crafted for irrigation subprojects.

9. In 2013, a total of 84 subprojects were approved by both NSAC and RSAC. However, in September, the NGALGU was stopped due to

9

issues raised on the constitutionality of the Disbursement Acceleration Program (DAP) which is the source of NGALGU funds. Other major project-related events that somehow impacted ARCP II implementation.

 Changes in Project Management, with a new NPCO Coordinator. Implementation of the DAR Rationalization brought changes at the field level as most of the ESS Point Persons either availed of the early retirement packages, promoted or transferred to other assignments in the DARPOs/DARROs. Also, for LGUs as the local election brought changes in MPDCs as well in some LGUs.  Joint (OFID and ADB) Loan Review Mission conducted September 12 -17, 2013, aimed to (i) assess project physical progress, issues and mitigation measures; (ii) review financial progress including disbursement, contract awards and discuss strategies to improve the Project physical and financial performance; (iii) conduct project site visits and interact with project stakeholders; (iv) review the Project’s compliance with loan covenants; and (v) review and explore mitigation measures to overcome outstanding issues and improve the overall project performance and loan utilization. Per Mission’s MOU, as most of the subprojects are for rehabilitation, there are no issues raised on environmental and social safeguards.

10. In 2014, as the ADB loan period is to expire in 31 December, DAR requested for one (1) year extension to NEDA and DOF to bring project completion date to 31 Dec 2015. OFID and ADB approved the loan extension on 6 Oct and 29 Oct, respectively. During the year, there are 18 approved subprojects approved by NSAC.

 Mid Term Review Mission was conducted June 24 – July 8, 2014 and recommended major ”actions” in project implementation. Among those with reference/impact to environment and social safeguards implementation are: a. EDCOP and NPCO to make available knowledge (in the form of simple manual) on what the ARBOs could do to maintain rural infrastructure subprojects—such as the types of trees, planting distances and other techniques -- and to provide support to enhance their roles in rural infra operations and maintenance (O&M); LGUs and ARBOs to put in place measures in concerned areas to reduce the risk of heavy vehicles to damage RI SPs.

10

o NPCO/EA to identify subprojects to be delisted, with “as not yet started” as basis by DAR cut-off date of 30 June 2014.  In the same Mission, a social safeguards review team from ADB was fielded July 1, 2014 to discuss social safeguards issues with relevant DAR and NPCO staff, review available safeguards documentation and reports and discuss observed gaps with NPCO staff. The special safeguards mission’s objective was to clarify the following: i) whether the conduct of social safeguards is fully understood by the project team and whether training at the beginning of the project has been conducted; ii) if project screening and categorization of subprojects as per RF and IPPF is identified and included in the feasibility report; iii) whether LARR (short and long version and SDLAR) and IPP has been prepared as part of the FS for every SP prior to approval of SPs; and iv) whether M & E system and progress report, annual reports should capture progress of IPPF/RF. The TOR can also include verification whether the staff are: i) sensitive to gender differences in agricultural enterprise responsibilities and resource access; ii) sensitive to ethnic group differences in land use and decision making processes for CDD, infrastructure and other project components; and iii) adaptable to different community absorption rates based ability to speak or read or write Philippine languages; and iv) skill in dealing with multi IP and intercultural communication, and in applying inclusive approach. Recommendation of the Special Safeguard Mission:

Agreed Action Status

 NPCO/EA to provide ADB  NPCO submitted said with a consolidated report on report as scheduled due diligence by 15 Aug  ADB to strengthen oversight  ADB issued NOL for the guidance safeguards issues engagement of an ESS for remaining project consultant implementation period  NPCO to strengthen its  NPCO ensure inclusion of safeguards - related safeguards in its quarterly documentation, monitoring reports and reporting  EA to hire a social  Engaged the services of an safeguards consultant with ESS Consultant in October the following Terms of 2017 Reference: i) advise the

11

project team in completing the documentations related to requirements for RF/IPPF; ii) facilitate refresher training for Project staff on LFR and IPPF requirements and how to fulfill them in the on-going projects; iii) provide a template for due diligence for some completed small infra subproject and prepare or complete the Project valuation form; iv) advise on how to report progress on social safeguards; v) advise on how to improve inclusion of IPs and vulnerable people in the on-going project and avoid elite capture, strengthening group dynamics and organization from various starting points; and vi) undertake due diligence for any other outstanding issues related to RF/IPPF.  ADB to provide NPCO with  ADB provided NPCO with the required template for the GAP monitoring GAP monitoring/reporting template used by ARCP II in the GAP report submitted to ADB

 About 123 subprojects were delisted  In In response to the recommendation of the Mid-Term Review Mission, ARCP II in close collaboration with EDCOP, extended capacity building with regional and provincial engineers on construction management supervision and materials testing supervision as well as capacity building on O & M of completed subprojects such as access infrastructure, potable water system irrigation system and post-harvest facilities and social infrastructure for RI engineers and CDD coordinators.

12

11. In 2015- Considering the significant delays encountered by the Project, the physical completion and loan closing dates for both the ADB and OFID loans were extended to 31 December 2016 and June 2017, respectively. In the Aide Memoire for the October 26-30, 2015 ADB Mission, Social Safeguards staff of SEER joined the said mission to meet with NPCO staff responsible with ESS and to follow up on the status of agreements/recommendations made during the Midterm Review Mission held in 2014. Based on her findings, the Mission recommends that the:

 NPCO to prepare a summary per identifying the subprojects that still have pending safeguards documents and specifying which safeguards documents are lacking, and the status of implementation of these subprojects. For subprojects with pending safeguards documents, NPCO to prepare an action plan for obtaining these documents including target dates and specific persons responsible for following up in obtaining documents.  NPCO to carry out an in-depth analysis of the project impacts to IPs with reference to the measures described in the IP development framework (IPDF). ADB and NPCO to discuss and agree on the schedule of preparation and submission of this report. The analysis to be submitted to ADB prior to the next review mission.  DARPO to send reports to NPCO that clearly indicate the results of the monitoring and mitigation activities on the ground.  NPCO to check whether there is compliance to EMMP, and  To check the plausibility of the monitoring reports sent by DARPO. Such reports have to state that the impacts during construction, and during operation are mitigated as per IEE and that the EMMP follow the requirements of the IEE.

12. In 2016, a Safeguards Review Mission for ARCP II was fielded on February 1 to 5 and analyzed whether (i) environment and social safeguards requirements are met; (ii) monitoring, evaluation and mitigation of impacts are carried out; (iii) monitoring reports reflect content of EMMP and Indigenous Peoples Development Framework (IPDF); (iv) communication and documentation of results is functioning. Though the Mission found deficits of the current environmental and social safeguards system, it was noted that the inspected subprojects are all appreciated by the community and in general have low environmental and social impacts. The following actions were agreed between the Mission and NPCO for improving compliance with safeguards requirements:

13

o Templates for more comprehensive monitoring updated, in terms of environmental safeguards, the Project monitoring template should be used to check whether (a) IEE/EMMP was done and its content is in accordance with overall IEE; (b) IEE/EMMP is implemented; (c) stating main problems and mitigation. Prior to distribution to DARPOs, the updated template should be sent to ADB for review and approval. o Quarterly reports need to monitor, not only compliance in terms of submission of documents, but also safeguard implementation. o ESS staff capacity needs to be strengthened by assigning dedicated ESS Specialist at provincial level and additional capacity development for staff at provincial and local level or LGUs. No training should be conducted after June 2016. o Since the Project will be completed in December 2016, the focus should be on institutionalizing O & M after project completion. Therefore an O & M Plan is needed for each SP, which captures ESS for O & M as well as the responsibilities. NPCO analyses the quality (deadline for plans is March 2016), and will send final version of one example to ADB for review and approval. o NPCO to carry out inventory of safeguards status. This should cover not just whether all required documents have been submitted , but also inventory of ESS staff and include due diligence on whether or not the actions mention in mitigation plans pending safeguard issues have been addressed. If not, then corrective actions prior to project completion must be implemented.

 The NPCO together with ADB finalized the new ARCP II Safeguards Monitoring Form, and was downloaded to the field offices. Orientation on the new form was done through one on one with LGU alongside PBGS Performance Measure Assessment, as the DAR Undersecretary for Finance disapproved almost all project-related activities including hiring of consultants and renewal of Project staff, claiming that the Project extension was just time extension with no budget.  With the change in Administration in July, the ARCP II was again back to its full swing, including the resubmission of proposal for engaging of ESS Consultant and capacity building for the new ESS Point Persons, and the DAR’s request for another one (1) year extension of implementation period and validity of loans. The said request was approved by the Investment Coordination Committee (ICC)/NEDA Board and was forwarded to Department of Finance on 21 December 2016 for endorsement to ADB.

13. In 2017 - The DOF officially endorsed the request for extension to of ARCP II to ADB and OFID on January 9, 2017. The ADB and OFID approved the extension on April 5, 2017 and May 4, 2017, respectively. Hence, the physical completion of the Project is 31 December 2017, while financial closure is 30 June 2018.

14

 In October 13 – November 3, intermittent, ADB dispatched a Review Mission to (i) to assess the project implementation programs; (ii) visit project sites; (iii) examine the government’s request for partial loan cancellations; (iv) review consultants recruitment, contract awards and disbursements; (v) ;

 Status of Project Implementation as of 31 December 2017, physical performance: Component Global Accomplishment Accomplishment Weight (Based on (Based on Original Targets) Revised Targets)

Community Driven 3.00 3.00 3.00 Development Agriculture & 15.00 13.03 13.03 Enterprise Development Rural Infrastructure 77.00 55.42 66.66

Project Management & 5.00 5.00 5.00 Implementation Total 100.00 76.61 87.85

On financial, for the same period: ADB OFID Total

Net Commitment (US$ M) 67 21.609 88.609

Scheduled Availment (US$ M) 67 21.609 88.609

Actual Availment (US$ M) 38.78 7.40 46.18

Utilization Rate (%) 57.87 34.25 52.11

Availment Rate (%) 57.87 34.25 52.11

Time Elapsed 100 100

 The Project has approved 598 rural infra subprojects but with 123 delisted/withdrawn subprojects, the total number of SPs approved and were implemented now stands at 475 summed up as follows: : o 267 access infrastructure with a total length of 947.67 km o 13 communal irrigation facilities with a total service area of 5,022.75 hectares o 15 units of potable water system o 39 SPs of post-harvest facilities

15

o 141 social infrastructure such as 60 classrooms and 54 units of multi-purpose centers, day care centers, tribal halls and 27 health centers Table 1: No of SPs by type of infrastructure and status by Region Region Status FMR Irrigation PWS PHF Social Infra

IV-B Completed 13 3 2 0 13

On going 5 0 0 0 0

V Completed 63 2 4 12 45

On going 18 1 0 0 12

VI Completed 7 0 0 3 3

On going 3 0 0 0 0

VIII Completed 46 2 1 1 0

On going 23 0 1 1 0

IX Completed 35 3 3 11 48

On going 15 2 0 0 0

ARMM Completed 10 0 1 0 14

On going 29 1 3 11 5

TOTAL Completed 174 10 11 27 123

On going 93 4 4 12

 Of the 475 subprojects, 333 were reported completed, with 142 rural infrastructure SPs still with ongoing civil works (Annex IV).

Report prepared by: Rosario R. Regalado, DAR Point Person for ESS, ARCP II

II. Safeguards Monitoring and Evaluation

1. Although the most desired scheme for this development project is to have none or have the least number of people that will be negatively affected by its project activities, it is virtually impossible to only have positive impacts on all its possible stakeholders. Therefore,

16

a set of guidelines was prepared for implementers to guarantee that appropriate measures are applied in terms of ensuring integration of environmental and social concerns during planning, design, implementation and operation of projects funded under ARCP II. These guidelines were discussed in the ARCP II Safeguards Manual approved by ADB in 2009.

2. The Safeguards Manual covers the following: i) Land Acquisition, Resettlement and Rehabilitation (LARR) Framework and Guidelines; ii) Guidelines on Environment Safeguards; and iii) Guidelines on Indigenous Peoples. It was prepared consistent with the relevant ARCP II Project Documents: Report and Recommendation to the President (RRP), Project Administration Memorandum (PAM) and the ARCP II Main Report, ADB Policy on Involuntary Resettlement, Guidelines on Environment Safeguards and Indigenous Peoples.

3. The ADB approved the revised ARCP II Environment and Social Safeguards Monitoring Form (Annex V). This addresses the needed improvement in monitoring safeguards implementation for rural infrastructure subprojects. Said form was discussed with the PBD Chief Agrarian Reform Program Officers (CARPOs) of the DARPOs in 2016 to ensure that the work will be undertaken by the ESS Point Person in the provinces, in the ARCP II year end assessment.

II. a Summary of Compliance on Environmental Safeguards

4. Of the 475 approved rural infrastructure subprojects, 59 subprojects were issued with Environmental Compliance Certificates and 254 issued with Certificate of Non Coverage. Others are social infrastructures with SB Resolution. Of those with ECC, 38 subprojects were already completed while those with CNC, 175 SPs are completed (Annex IV-A: List of Subprojects issued with ECC; Annex IV-B: List of SPs issued with CNC).

5. Among the subprojects issued with ECC are five (5) irrigation subprojects with a total service area of 2,400 hectares. These are rehabilitation of existing irrigation system and there are no environmental issues encountered during the subproject implementation. The LGU of and the farmers are grateful for the ARCP II assistance. Both Tagbawto CIS and Tabuunok CIS were badly damaged by typhoon hence, the rehabilitation of the dam prevented both irrigation system from being totally damaged and unoperational. Farm-to-market roads were also implemented with no environmental concerns as necessary permits and clearances were secured. It also helped that the EMMP as well as the conditions in the ECC were discussed with the contractor and the community during pre-construction.

6. Implementation problems, technical in nature were addressed and remedied with variation orders approved by the LGU and ARCP II. The engagement of an engineering firm that looked into quality control and monitoring of subprojects is a big factor in ensuring environmental soundness and technical problems during implementation are avoided.

7. As for the safeguards monitoring report, a number of LGUs from , , , West Samar, E. Samar, , , del Norte and Sur submitted their safeguards monitoring form for 62 subprojects. The DARPOs continually remind the LGUs that suitable mitigation measures stated in the EMMPs and the conditions in the ECC should be implemented (Annex VI – Sample ESS Monitoring Form submitted by LGUs).

8. Review of the environmental compliance monitoring report of subprojects submitted by the LGUs showed mitigation measures implemented such as provisions of access thru the

17

road rehabilitation site implementing proper scheduling of rehabilitation works along the road and/or assigning a “Barangay ” to handle traffic management of pedestrians and vehicles. In some subproject sites, there were no waste disposal facilities, but during the site inspection, the contractor was urged to provide waste bins in compliance with the RA 9003. In controlling the increase of suspended dust particulates along the unpaved roads and gas emission from vehicles and equipment, the contractor of Gen. Malvar Pontevedra FMR had particularly complied to the mitigation measures. One most common ECC condition that was not done by the LGUs was to submit report to the EMB-DENR. The LGUs were reminded of their compliance to this requirement.

III. Social Safeguards Performance Monitoring

9. ESS compliance monitoring report per subproject reflected that the LGUs had given full attention to consultative meetings with equal representation of men and women, on PAPs. The subprojects were fully discussed to them, and LGUs had given prior coordination and consultation with women's groups, with Barangay Development Councils, with Irrigators Service Association, School Board/Officials, and peoples organizations. Welfare, and Multi- Purpose Cooperatives. People were oriented about the project descriptions and given awareness of ARCP II environment and social safeguards guidelines and requirements.

III.a. Summary of Compliance with IR/IP Requirements

Table of SP with RP

Reg No. Deed of Deed of Joint of Donation Conveyance Quit SPs with Quit Claim Claim IV-B 11 9

10. On Land Acquisition and Resettlement, there are 171 subprojects with Project Affected Persons (PAPs). These PAPs have either portion of their lands affected, or improvements in their lands such as crops, trees and structures. Only 66 subprojects have prepared a short resettlement plan, wherein an inventory of PAPs, affected lands and improvements were discussed including the arrangement with the PAP. (Annex IV- C list of SPs with PAPs) Table 1: Subprojects with Project Affected Persons (PAPs) Region/Province No. of SPs Region IV-B () 11 3 Palawan 1 7 Region V 20 7 8 5 Region VI 10 Iloilo 5 Negros Occidental 5

18

Region VIII 47 Leyte 16 Northern Samar 6 14 West Samar 11 Region IX 67 28 31 8 ARMM 21 Lanaodel Norte 18 1 2

11. The Resettlement Plan (RP) contains the ROW acquisition, which in most cases are donated to the LGU. Only 66 subprojects have RP, other SPs were supported only by masterlist of PAPs and legal documents for the right of way documentation. Legal documents executed by the PAPs are deed of donation, deed of conveyance with quit claim, joint quit claim, permit to enter, and usufruct as the proposed infrastructure subprojects have been the clamor of the beneficiaries, hence the PAPs are very much willing to help the LGUs raise the needed equity by donating portions of their lands and assets just to ensure that the project will be implemented. Table 2: No of Subprojects with RP and Type of ROW document Region No of SPs RP Deed of Deed of Joint/Quit Permit to Donation Conveyance Claim Enter; SB with Quit Claim Resolution, etc IV-B 11 8 9 2 2 V 15 6 7 3 4 VI 10 4 4 8 VIII 47 29 29 12 4 13 IX 67 18 36 2 19 14 ARMM 21 1 13 5 5

12. As the right to be compensated and their entitlement was disclosed during barangay consultations, there are also PAPs that asks for payment especially for subprojects that involved relatively big portions of affected land and improvements like opening or new farm- to-market road construction. Like the four ( 4 ) farm-to-market road subprojects in Samar Province, the LGUs provided compensation to the Project Affected Persons: Daram, Samar i) Construction of Mabini – Mayahay – San Roque FMR ii) Construction of Pob 02 – Talisay FMR iii) Construction of Mabini – Astorga – San Vicente – Bono-anan FMR Almagro, Samar i) Construction of – Costa Rica I FMR

13. There are also 298 subprojects that have no PAPs as certified by the LGUs. These subprojects are mostly rehabilitation or improvement of an existing farm-to-market road, with

19

the Right of Way (ROW) already secured by the LGU before ARCP II or social infrastructure subprojects.

III. b Indigenous People 14. On Indigenous Peoples (IPs), though the ARCP II was not specifically designed for the IPs as it aims to benefit the agrarian reform beneficiaries and farmers in the Agrarian Reform Communities, these ARCs may be in areas inhabited by the indigenous peoples, hence the IPs, in the ARCs and ARC Clusters were not left out by the project.

15. Rural infrastructure subprojects are required to secure Certificate of Non Overlap/Certification Precondition (CNO/CP) from the NCIP. A total of 225 subprojects were issued CNO and 40 subprojects were issued and Certification Precondition (Annex IV-D: List of Subprojects issued with CNO; Annex IV-E: List of SPs issued with CPs).

Table 3: No of SPs issued with Certification Precondition and Certificate of Non Overlap Region NO of subprojects with CP No, of subprojects with CNO IV-B (MIMAROPA) 0 21 V 2 85 VI 2 7 VIII 0 30 IX 36 21 ARMM 0 43

16. Most of the subprojects issued with CPs are in the Zamboanga Provinces. The IPs, mostly Subanen in Leon Postigo and Siayan, Zamboanga del Norte shared that they were consulted during the planning of their proposed subproject, in fact, they were the ones who requested said subprojects from their LGUs. In Bgy. Mangop Elementary School, Leon Postigo, the Project provided 2 school rooms. About 70% of the 244 enrollees in school year 2017 - 2018 are IPs. The facilities are not only used as classroom for the Grade VI pupils but as computer room as well. It also served as meeting venue for Parent Teachers Associations (PTAs) and other activities that requires a bigger area. While the Bgy Health Station in Sta. Maria, Leon Postigo provides for the immediate health services of the community from consultation, immunization, pre-natal, birthing and family planning. About 75% of the 242 households are Subanen. The FMR in Bgy Moyo, Siayan is highly appreciated by the all Subanen community. They are thankful that it is now easier for them to transport their products to and from the market. It also helped them in emergencies, as the LGU’s ambulance can now respond to them in bringing their sick family member to the doctor, whereas before they use to carry patient in a hammock, and walk thru to the proper to avail of health services.

17. In Zamboanga del Sur, there are six (6) units of tribal centers provided by the Project. These subprojects directly benefits the IPs. Of the tribal centers visited this year, those in the of , Josefina and San Miguel are already being used by the indigenous peoples and their council. It serves as a regular meeting place of the tribes where they conduct rituals in celebration of the IP Day, in settling conflicts, as storage of their costumes, musical instruments and other common properties the tribe uses in their rituals. In Kumalarang, the tribal center also serves as temporary shelter for the Subanen students, where they eat their lunch and spend their break time. It also serves as a venue for their school of living traditions (SLT). The Subanens in Kumalarang have already applied their CADC.

20

18. The tribal centers in is not yet turned over to the IPs, as the IP community found defects in the building. The LGU of Labangan promised that the defects will be repaired and the tribal center will be completed and turn over for use of the Subanen in December 2017. The Subanens in Binayan have been longing to have a more permanent place where they can meet as a tribe. At present, they request the use of or the church building if the Timoay’s call for a meeting.

19. Though there are also IPs or Subanens member of the SACASIG Irrigators Association, in Sagrada Familia Irrigation Project being rehabilitated by the ARCP II, these IPs are very much mainstreamed due to inter-marriages. Not much is known on their beliefs and traditions, even their children hardly speak the dialect, as most of them use the Visayan language. They said the children does not want to be identified as IPs. However, they also said that there are efforts now from the Timoays to strengthen and to practice their traditions.

IV. Occupational, Health and Safety (OHS) Performance Monitoring

20. Part of the Project’s commitments to social safeguard is to promote safety and health to workers, personnel and visitors in the construction project site. Moreso,, that the Project requires the contractor gave hiring preference to qualified local community residents, and when there is lack of skilled work force in the affected barangays, some hired workers were from the outside community.

21. As the LGUs and the Contractor involved in the implementation of subprojects take care of the occupational health and safety of the workers in the construction site and the possible health impacts of the subproject in the community and the environment. These are frequently asked during subproject monitoring, whether OHS is observed, such as use of protective equipment (PPE) among others. There is a Contractor that provided not only PPEs but medicines/antidotes to help the workers overcome waterborne parasites.

22. ECCs issued to ARCP II subprojects also stipulated the Regulatory Conditions such as, compliance to the PD 442 or the Labor Code of the Philippines including occupational safety and health. Cited in their respective ECCs that close monitoring of the project be undertaken by the proponent to maintain a high level of safety and efficiency at all stages of the operation, provisions of PPEs to workers for safety, and immediately address to any environmental hazard/change that may occur.

V. Grievance and Redress Mechanism

23. As discussed in the Safeguards Manual, complaints and grievances will be managed through a Complaints and Grievance Committee (CGC) at the barangay level. It shall be established to hear the complaints and grievances of the PAPs regarding the acquisition of land and other assets, compensation, resettlement, rehabilitation and other entitlements. Through a Sangguniang Barangay Resolution, a Complaints and Grievance Committee shall be created and will form part of the Barangay CARP Implementing Team (BCIT) as one of its committees. Members of the CGC shall include the (BIT Chairman), a member of the Barangay Justice (Lupong Tagapamayapa), committee heads of the BCIT as well as formal and informal representatives of the affected community. The complaint, grievance and appeal shall have the following levels:  LEVEL 1 PAP addresses complaints and grievances to the Barangay CGC. The Committee will have to document its investigation to the facts presented and provide

21

a written response to the PAP, within fifteen (15) calendar days of receiving the complaint.  LEVEL 2 If the PAP is not satisfied with the decision of the Committee; the PAP may appeal the case to the Project Local Office thru the MPDO within fifteen (15) calendar days of receiving the written decision/s from the Barangay Committee. The decision of the MPDO shall be rendered within thirty (30) calendar days of receipt of the PAP's appeal after validating the facts of the complaint. Through a Resolution, a Complaints and Grievance Committee at the municipal level shall be created and will form part of the Project Local Office (PLO) designating the MPDO as Grievance Officer for the LGU. Members of the municipal CGC shall include a member of Sangguniang Bayan, committee heads of the PLO and representative from the barangay CGC. The MPDO shall be responsible in providing regular reports to the Office of the Mayor on grievance related matters.  LEVEL 3 If the PAP is not satisfied with the decision of the MPDO; the PAP may appeal the case to the PARO/Provincial Project Manager (PPM) within fifteen (15) calendar days of receiving the written decisions from the MPDO. The decision of the PARO shall be rendered within thirty (30) calendar days of receipt of the PAP's appeal after validating the facts of the complaint.  LEVEL 4 If the PAP is not satisfied with the decision of the PARO/PPM; the PAP may appeal the case to the DAR Regional Director/Regional Project Manager (RPM) within fifteen (15) calendar days of receiving the written decisions from the PARO. The decision of the DAR Regional Director shall be rendered within thirty (30) calendar days of receipt of the PAP's appeal after validating the facts of the complaint

o If the PAP is not satisfied with the decision of the PARO, the case may be submitted to the ARCP 2 NPCO through the National Project Coordinator (NPC) and Environment and Social Safeguards Specialist (ESS) for consideration. The decision of the NPCO shall be rendered within thirty (30) calendar days of receipt of the PAP's appeal.

o PAPs will be exempted from all administrative and legal fees. o Unresolved grievance can be elevated to the proper courts. However, resorting to courts prior to availment of this complaint and grievance process will make the appellantior to availment of this complaint and grievance process will make theop remedies.

24. There were no reported grievances related to subproject construction raised to NPCO. During monitoring, the LGUs claimed that complaints or queries were immediately addressed or settled at the local project office and that there are no formal complaints that are elevated. Issues cited were more on request of PAPs to have a family member be hired or provided with job in the construction, and were accommodated or immediately acted upon by LGUs, as this is also in the project policy to involve the community residents in labor in the subproject implementation. Most of the complaints, were on the delays of project implementation or delays in payments of contractors due to late releases and slow liquidation.

VI. Information Disclosure, Socialization including Capacity Building

22

25. In 2009, during ARCP II launching and orientation of Project partners like the Local Government Units, Environment and Social Safeguards policies were among the topics discussed with the LGUs. The activity was carried through in the ARCs, as the community, including the project affected persons were informed of environment and social safeguard policies of the ADB, especially their right to be compensated.

26. DARRO/PO ESS Point Persons together with Regional ESS Consultants conducted more ESS-focused orientation with the LGUs particularly with the Municipal Planning and Development Coordinators (MPDCs).

27. Aside from the training provided by ARCP II to the ESS Point Persons of the DAR Provincial and Regional Offices covered by the Project, FS/DED/ESS writeshop were conducted with the LGUs for provinces that requested assistance from the NPCO like, Samar, Mindoro Oriental, Lanao del Sur and Sosrogon. Results and agreements from the training were incorporated in the quarterly progress reports submitted to ADB.

Table 4: List of Safeguards Training and Workshops Number of Region Training Date Participants Participants Trained DARRO & Orientation/Workshop on DARPO VI & VIII August 5-6, 2009 24 Infrastructure & ESS assigned to ARCP II DARRO & IVB & Orientation/Workshop on DARPO Aug 13-14, 2009 28 V Infrastructure & ESS assigned to ARCP II DARRO & IX & Orientation/Workshop on DARPO Sept 23-24, 2009 36 ARMM Infrastructure & ESS assigned to ARCP II ESS point Persons, IV-B FS/DE-POW/ESS Training May 25-27, 2010 4 ESS Economist & Engineers ESS point Persons, V FS/DE-POW/ESS Training March 17-19, 2010 4 ESS Economist & Engineers ESS point Persons, VI FS/DE-POW/ESS Training May 25-27, 2010 3 ESS Economist & Engineers ESS point Persons, VIII FS/DE-POW/ESS Training March 17-19, 2010 5 ESS Economist & Engineers ESS point Persons, IX FS/DE-POW/ESS Training March 17-19, 2010 4 ESS Economist & Engineers ESS point ARMM FS/DE-POW/ESS Training May 25-27, 2010 4 ESS Persons,

23

Economist & Engineers FS/DE-POW/ESS Training for MPDCs & Mun VIII Sept 27-30, 2010 8 LGUs Northern Samar Engineers FS/DE-POW/ESS Training for MPDCs & Mun VI & VIII October 5-7,2010 10 LGUs Irrigation Subprojects Engineers M & E and ESS 26 ESS All M&E - ESS Training August 7-9,2012 Point Persons Point regions (Region & Prov) Persons Workshop on the ARCP II DARRO & All safeguards monitoring form Sept 27 – 29, 2016 DARPO 26 regions (during the ARCP II ssessment) CARPOs

VII. Conclusion

28. The ARCP II is dubbed as the most challenging Foreign-Assisted Project implemented by the DAR either seriously or just in jest, such can be attributed to the following: national policy on cost-sharing when the Project was approved was not affordable for the LGUs; cancelation of the NGALGU that helps address cost-sharing difficulties; extreme natural and man-made calamities such as earthquake, typhoons especially Typhoon Yolanda, the Zamboanga siege, and the siege; changes in administration brought about by three (3) local elections and two (2) national elections; and changes in ARCP II point persons and staff from NPCO to PPMOs.

29. With such backdrop, overall environment and social safeguards implementation in ARCP II subprojects was observed by the LGUs and contractors. ESS documentary requirements, from tree cutting permits, ECC/CNC, CNO/CP and ROW documentations were painstakingly complied with by the LGUs. It is in the monitoring and reporting of the mitigation measures where the Project was lacking, as efforts was focused on the LGUs compliance to the documentary requirements.

30. Among the challenges encountered in ESS implementation where we can learn from and to better improve safeguards implementation in succeeding projects are:

 Capacity and consistency of the implementing agency to oversee the overall safeguards performance of the project and monitor the same at the project level. Such oversight responsibility includes provision of timely advice and support to the proponents;

 Hiring of full time qualified environmental and social safeguards specialists at the Project Management Office and at Provincial Project Offices throughout project duration;

 Integration of the Environment and Social Safeguard Management Plan in the bidding documents, design and reporting on the actual delivery of safeguards on a regular basis during subproject implementation, to avoid ESS as just an add-on to the many concerns in project implementation.

 On Right of Way acquisition, particularly for donated lands, more thorough review of documents should be done and ensure that annotation on the title of area donated to the project is documented.

24

 Capacity building on environmental and social safeguards for the subproject proponent is integral to the project and should not be taken for granted. Hence, orientation and training of subproject proponents should always be provided.

Monitoring of ongoing projects will be taken up in the next reporting period.

25

ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 1 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered dated 07/29/08 Brgys.

IV-B 1 Oriental Mindoro Pinamalayan 2nd 1st MAROPA 6 Quinabigan Del Razon Malaya Marfrancisco Rosario Papandayan Bansud 2nd 2nd Salcedo 6 Salcedo Conrazon Rosacarra Proper Tiguisan Villa Pag-asa Pag-asa Bongabong 2nd 1st Bongabong East 5 Sagana San Isidro Anilao Orcunoma Mina De Oro Roxas 2nd 2nd Roxas 9 San Mariano Happy Valley San Vicente Little Tanauan Mabuhay Libtong Cantil Victoria San Aquilino Mansalay 2nd 2nd MARBRIBA 3 Sta. Maria Balugo Sta. Brigida Bulalacao 2nd 2nd Bulalacao 4 Cambunang Nasukob San Juan Balatasan sub total 6 6 33 2 Palawan Coron 1st 1st Santulupe ARC 3 San Nicolas Taytay 1st 1st Pujalte Estate 1 Poblacion Aborlan 2nd 1st Plaridel/Jose ARC 2 Plaridel Jose Rizal Iraan/Isaub ARC 2 Iraan Isaub Brooke's Point 2nd 1st Mambalaot--Calasaguen 3 Maasin Mambalot Calasaguen sub total 4 5 11

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 2 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

3 Romblon Sta. Fe Lone 5th Magsaysay 3 Magsaysay Mat-I Pandan Calatrava Lone 5th Balogo 1 Balogo Magdiwang Lone 5th Tampayan - Jao-asan 5 Jao-Asan Tampayan Ipil Dulangan Ambulong San Fernando Lone 4th Taclobo ARC 3 Taclobo Espana Pili sub total 4 4 12 0 total region IV-B 14 15 56

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 3 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

V 4 Camarines Norte 1st 3rd Batobalani 4 Batobalani Tawig Dagang Capacuan Labo 1st 1st Daguit 4 Daguit Malangcao- Macogon Talobatib 1st 3rd Magsaysay 3 Magsaysay Old Camp Tanauan Jose Panganiban 1st 2nd San Pedro 4 San Pedro San Martin San Rafael Tamisan Vinzon 2nd 3rd Aguit-it expanded 4 Aguit-it Manlucugan Matango Singi sub total 5 5 19 0

Camarines Sur 1st 1st Mantila 3 Mantila San Isidro Serranzana 2nd 4th Cabugao 2 Cabugao San Antonio 2nd 1st Bahay 6 Bahay Aslong Potot San Pablo Malinao San Isidro 4th 4th Del Pilar 3 Del Pilar Ason Salvacion 5th 3rd Agdangan-San Rafael 5 Agdangan San Rafael Sta. Teresita San Isidro Buluang Buhi 5th 1st -Divino Rostro 5 Antipolo Divino Rostro San Isidro San Francisco San Rafael sub total 6 6 24 0

VI 6 Sorsogon 2nd 2nd Irosin Municipal 24 Bagsangan Batang Bolos Buenavista Carriedo * Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: Casini List updated as of CawayanJanuary 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 4 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

Cogon Gabao Gulang-gulang Gumapia Liang Macawayan Mapaso Monbon Patag Salvacion San Isidro San Pedro Sto.Domingo Bulawan Tabon-tabon Tinampo Tongdol

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 5 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

Juban 2nd 4th Lahong 1 Lajong Juban 2 Sipaya Calateo Bulan 2nd 1st Bulan 4 Lahong Fabrica A. Bonifacio Gregorio del Pilar 2nd 3rd Matnog 2 Hidhid Bolo 2nd 2nd Gubat ARC Cluster 6 Beriran Carriedo Cabiguhan Jupi Dita Payawin sub total 5 6 39 0 total region V 16 17 82 0

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 6 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

7 Negros Occidental Calatrava 1st 1st MADO 2 Maaslob Dolis Valladolid 4th 4th ALBAPA 3 Alijis Bayabas Pacol Pontevedra 4th 3rd Gen. Malvar 1 Gen. Malvar Hinoba-an 6th 1st Pagbana-ag ARC 2 Alim Asia Candoni 6th 4th Caningay 1 Caningay sub total 5 5 9 0 8 Iloilo Bingawan 3rd 5th Guintapangin 4 Guihulacan Tapacon Agba-o Inamyungan Anilao 3rd 4th Cag-an 1 Cag-an Lambunao 3rd 1st AGSIBAGO 2 Agsirab Bagongbong Dumangas 4th 1st Dumangas 6 Balabag Maquina Pagdugue Patiao Pulao Sulangan Batad 4th 5th Bulak 2 Bulak Norte Bulak Sur Barotac Viejo 5th 3rd LIPATA SARC 1 Lipata San Rafael 5th 5th San Andres-Florentino 2 San Andres Florentino sub total 7 7 18 0 total region VI 12 12 27 0

VIII 9 Northern Samar San Jose 1st 5th Uswag Caraingan 5 Bagong Sabang Bonglas Da-o Gengarog San Lorenzo San Isidro 1st 4th San Isidro 5 Alegria Mabuhay Palanit Salvacion San Juan 2nd 3rd Palapag 6 Sangay Napo Capacujan Magsaysay Matambag Osemeña Gamay 2nd 4th Gamay 3 Bangon G. M. Osias Cagamutan del Norte sub total 4 4 19 0 * Additional LGU included in ARC Cluster **10 Additional Eastern Samar ARC included in ARC Cluster Lone 5th Balangkayan 13Note: Balogo List updated as of January 11, 2012 Bangon ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 7 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

Cabay Caisawan Cantubi Guinpoliran Brgy. (Poblacion) 1 Brgy. (Poblacion) 2 Brgy. (Poblacion) 3 Brgy. (Poblacion) 4 Brgy. (Poblacion) 5 Maramag Julag Salcedo Lone 5th SALCEDO 13 Naparaan Carapdapan Camanga Cantomoja Cagaut Sta. Cruz Tacla-on Tagbacan Casili-on Caridad Seguinon Talangdawan

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 8 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

San Policarpo Lone 5th ESSP 3 Bangon Tan-awan Sta. Cruz Arateche Lone 3rd ESSP 12 Tawagan Cagsalay MacArthur Inayawan Tebalawon Aguinaldo Bato Tangbo Casidman Concepcion Bigo Campacion Lawa-an Lone 5th Lawa-an 4 Taguite San Isidro Brgy. Poblacion 08 Lone 5th Giporlos 9 Barangay 05 Barangay 07 Coticot Parina Paya Pres. Roxas San Isidro San Miguel Sta. Cruz

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 9 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

Balangiga Lone 4th 7 Barangay Poblacion 1 San Miguel Cansumangcay Sta. Rosa Cag-olango Guinmaayohan Bacjao San Julian Lone 5th San Julian 5 Brgy 6 Poblacion Campidhan Casoroy Libas Nena sub total 8 7 66 0

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 10 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

11 Western Samar 1st 4th St. Francis ARC 9 Balonga-as Bangon-gote Binalayan Cabungaan Catan-agan Dapdap Lahong Talinga Pajo Sta. Margarita 1st 4th -Ilo 2 Balud Ilo Almagro 1st 5th Almagro 23 San Jose Poblacion Veloso Lunang I Lunang II Malobago Rono Panjobjoban I Panjobjoban II Tongatunga Costa Rica I Costa Rica II San Isidro Talanid Bacjao Kerikite Magsaysay Biasong I Biasong II Imelda Guinausan Mabuhay Marabaras 2nd 5th Macaparican 4 Camarobo-an Parina Cantongtong Macabetas Daram 2nd 3rd West Daram ARC 11 Mayabay Poblacion 1 Poblacion 2 Real San Roque Mabini Birawan Bagacay Saugan Mandoyocan

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 11 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

Pagsanghan 1st 5th SARA 13 Libertad Viejo Sto. Nino Canlapwas Bangon Pange Buenos Aires Calanyugan Cambaye Caloloma San Luis Villahermosa Or. Villahermosa Occ. sub total 6 6 62 0

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 12 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

12 Leyte Tolosa 1st 5th Tolosa 5 Canmogsay Capangihan Malbog Opong San Vicente Alang-alang 1st 2nd 3 San Antonio Salvacion Langit Palo 1st 3rd Palo 2 3 San Agustin Cabarasan Daku Capirawan 2nd 4th Capoocan 6 Sto. Niño Visares Lemon Cabul-an San Joaquin Balugo 3rd 4th Calubian I 2 Labtic Enage San Isidro 3rd 4th San Isidro 12 Hda. Maria Paril Daja Diot Daja Dacu Bawod Matungao Tinago San Miguel Bunacan Taglawigan San Jose Crossing

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 13 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

Villaba 3rd 3rd ARC (Casilion) 1 Casilion Matag-ob 4th 4th Matag-ob 2 Balagtas San Vicente Merida 4th 5th Merida II 5 Poblacion Cambalong Lundag Mat-e Calunasan Kananga 4th 1st Kananga 5 Libongao Masarayao Naghalin Aguiting Lim-ao Hilongos 5th 2nd Hilongos (regular) 8 Tejero Liberty Concepcion Baas Campina Lunang Tabunok Taguipa Javier 5th 4th Javier Settlement 20 Binulho Talisayan Manlilisid Laray Comatin Malitbogay Naliwatan Inayupan San Sotero Poblacion Zone I Poblacion Zone II Magsaysay Odiong Ulhay A. Bonifacio Cancayang Guindapunan Manarug Pinocawan Sta. Cruz 5th 4th Inopacan ARC 4 Cabulisan Can-angay Hinabay Mara-o 5th 3rd Matalom 4 Elevado Esperanza Calumpang San VIcente sub total 14 14 80 0 * Additionaltotal LGU region included VIII in ARC Cluster 32 31 227 0 ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 14 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

IX 13 Zamboanga del Norte Piñan 1st 4th VILLACITA 6 Villacita Desin Calican Obay Upper Gumay Tinaytayan POSSADELBA 6 Poblacion North Poblacion South Sigabe Adante Del Pilar Bacuyong LUZSITE Expanded 6 Luzvilla Sikitan Teresita Bagong Silang Santa Fe Dilawa 3rd 4th Panabutan Expanded 6 Panabutan Doña Cecilia San Nicolas Sipakit Catuyan San Vicente Siayan 2nd 2nd Siayan West 5 Siayan Proper Paranglumba Moyo Polayo Dumpilas Siayan East 6 Muñoz Litolet Gunyan Gonayen Datagan Soguilon Manukan 2nd 3rd Manukan East 6 Linay Gupot Dipane Lingatongan Jose Aguirre Saluyong 2nd 1st MNSR 3 Motibot Nipaan Sto. Rosario 3rd 3rd GBL 3 Gabu Balas Lawigan 3rd 1st JOLAMIPAMAN 5 Jose Brilantes

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 15 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

AL Micubo Lituban Manaol Pangian 3rd 2nd GUMBUEBAS 4 Upper Gumay Bagong Silang Buenavista Map 3rd 3rd Kauswagan Baliguian 5 1. Kauswagan (expanded) 2. Lumay 3. Mamad 4. Nonoyan 5. Poblacion (Baliguian) sub total 9 12 61 0

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 16 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

14 Zamboanga del Sur 1st 3rd Balamban Expanded 7 Balamban Kabuhi Daniel C. Mantos Tumapic Upper Sto. Niño Lower Sto. Niño San Jose Josefina 1st 5th Josefina Highland Cluster 14 Bogo Calabat Sebucang Nopulan Lo. Bag-ong Tudela Leonardo Gumahan Up. Bag-ong Tudela Mansanas Nemeño Litapan Ebarlie Moradje Dawa Tagaytay Hill 1st 4th LUCCAT-LBP 10 Luy-a Upper Bayao Camanga Curvada Alindahaw Tabuan Tinotongan Lower Bayao Baclay Panduma Sr. 1st 4th Tambulig Highland B 5 Bag-ong Tabogon Limamaan Libato Upper Lodiong Tuluan 1st 2nd MANTELIBA 6 New Basag Libertad Manlabay Maralag Lower Timonan Upper Timonan

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 17 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

Labangan 1st 3rd Labangan C 3 Bokong Dipaya Binayan 1st 2nd TAGUMA Upland 3 Tagolalo Gubaan Mahayahay 1st 4th Midsalip Cluster 12 Poblacion B Timbaboy Canipay Sur Canipay Norte Tuluan Guma Poblacion A Bacahan Bibilop Dumalianao Boloron Lumpunid Molave 1st 1st Culo 1 Culo Miligan 1 Miligan Rizal 1 Rizal 2nd 4th MACASETIBA 5 Malasik Camanga Sebucao Tickwas Baloboan Tigbao 2nd 5th BeGCalLi 5 Begong Guinlin Caluma Longmot Limas Kumalarang 2nd 4th Kumalarang 1 Poblacion (Kumalarang) sub total 12 14 74 0

15 Zamboanga Sibugay Payao 1st 3rd Don Alfonso 11 Bulawan Guiwan Kima Kulasian Calape Fatima La Fortuna Lower Sumilong Upper Sumilong Balongisan San Isidro Mabuhay 1st 4th Mabuhay A 7 Poblacion Malinao Kauswagan Ligaya Catipan Punawan * Additional LGU included in ARC Cluster Sioton ** Additional ARC included in ARC Cluster Note: List updated as of Mabuhay B 11 CaliranJanuary 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 18 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

Bangkaw Bangkaw Pamansaan Abunda Bagong Silang Pinalim (San Roque) Sto. Nino (Caliran) Tandu-Comot (Katipunan) Look-Barlac Sawa Taguisian 2nd 2nd Culasian-Supit 2 Culasian Supit

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 19 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

Naga 2nd 3rd Sulo 1 Sulo Tambanan 1 Tambanan 2nd 2nd Lower Sibuguey 8 Labasan Kimos Balucanan Salinding Sibuguey Lagting Mirangan Coloran sub total 5 7 41 0 total region IX 26 33 176 0

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 20 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

ARMM 16 Maguindanao 1st 5th Matilak 4 Matilak Liong Pened Maitong 1st 1st MRP 3 2 Labungan Kibucay Datu Saudi 2nd 4th Salbu 1 Salbu 2nd 4th Muslim 4 Tulunan Linamunan Damablac Bo. Muslim 2nd Tukanalogong 2 Tukanalocong Kaya-kaya 5 5 13 0

17 Lanao del Sur Poona-bayabao 1st 4th Ragayan 16 Bangon -Dimunda Bugaran Bualan Cadayonan Calilangan-Dicala Calupaan Dimayon Dilausan Dongcoan Gadungan Poblacion Liangan Lumbac Lumbacalngud Madanling Tagoloan 1st 4th Malinao-Cadayonan 10 Kingan Little Marawi Inodaran Mimbaguiang Cadayonan Sigayan Tagoloan Poblacion Malinao Baguaingud Kianibong 1st 5th Marantao 9 CamaligBubong CamaligPoblacion Bandar Ingud Tacub BangaPantar CawayanLinuk CawayanKalaw

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 21 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

InudaranLoway Ganassi 2nd 4th Taliogon 10 Barorao Taganonok Barit Panggawalupa Taliogon Proper Sogod Madaya Tabuan Para-aba Masolun Campongaraya sub total 4 4 45 0

18 Tipo-tipo Lone 3rd TARBADECO 1 Tipo-tipo Proper TIPARBECO 2 Kabangalan Bohe Pahuh Lone 6th SCARBIDIC 9 Sta. Clara Tumakid Baungos Maloong Canal Maloong San Jose Balagtasan Bohenange Baugos Panunsulan LARBECO Lone 1st TARBIDC 1 Tumahubong CATARBEDECO MARBEDCO Lone 4th CARBADECO 1 Canas Calang TARBAMC 1 Cahas sub total 6 9 14 0

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX I: LIST OF PROVINCES COVERED BY ARCP II Page 22 of 22 Agrarian Reform Communties Project 2 (ARCP 2) Covered Local Government Units (LGUs) and Agararian Reform Communties (ARCs) with Barangays

No. of Cong. Income Class (as per Region Province LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

19 Sulu Maimbong 1st 5th 7 TubigSamin Matatal RatagLimbun Kandang Gulangan Patao Ipil 2nd 4th Pandami 4 ParianDakula Lahi Malanta Sibaud Proper 2nd 4th Sultan Jamalul Kiram 3 Kan-ukol Su-uh Kan-Dayok Tongkil 2nd 4th Calaycay 3 Kahikukuk Tambun-bun Danao 2nd 2nd Tulling 5 Tulling Siundoh Manta North Manta Minapan sub total 5 5 22 0

20 Tawi-tawi Lone Ungus ungus Tungehat 4 Ungus-Ungus Tongehat Mochtar Ligayan Tanduowak Tandubanak 4 Tongsibalo Sheik makdum Tandubanak Taunguh Lone 2nd Lakit-lakit Mandulan 3 Bohe Basag Lakit lakit Mandulan Lone 3rd Buan-Karaha 2 Boan Karaha Lone Tubig Dakulah - Basnunuk-Sikullis Sitankai Lone sub total 5 6 13 0 total ARMM 25 29 107 0 GRAND TOTAL 125 137 675 0

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 Page 1 of 12 Agrarian Reform Communties Project 2 (ARCP 2) List of ARC Clusters with Barangay

Income Class (as per No. of Cong. RegProvince ARC Cluster LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

IVB 1 Romblon SALOF ARC Cluster Looc Lone 4th ** Liliput 4 Limon Norte Limon Sur Punta Tuguis **Agojo 1 Agojo San Andres Lone 5th Agpudlos 3 Agpudlos Calunacon Linawan Ferrol Lone 6th Claro M. Recto 2 C.M. Recto Ginag-uman sub total 3 4 10 10 total region IV-B 3 4 10 10 V Camarines Norte Basud - San Lorenzo Ruiz ARC Cluster San Lorenzo Ruiz 2nd 5th San Isidro 3 San Isidro Matacong San Ramon *Basud 2nd 3rd Caayunan 4 Caayunan San Felipe Plaridel San Pascual Matnog 5 Matnog Bactas Mampili Laniton Langa sub total 2 3 12 12 5 Camarines Sur Baao-Bula Cluster 1st 4th Danawin 4 Comadaycaday Comadogcadog Pinagdapian San Juan

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 Page 2 of 12 Agrarian Reform Communties Project 2 (ARCP 2) List of ARC Clusters with Barangay

Income Class (as per No. of Cong. RegProvince ARC Cluster LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

*Pili 3rd 1st **Bagong Sirang 3 Bagong Sirang Binanwaanan Del Rosario **Binobong-Tagbong 3 Binobong Tagbong New San Roque *Ocampo 3rd 3rd **May-ogob 6 May-ogob San Roque Commonal New Moriones Old Moriones Hanawan Sta. Cruz **Ayugan 3 Ayugan Cabarowan San Antonio **Pinit 4 Pinit Hibago San Francisco San Vicente Tigaon 4th 3rd Tinawagan-Coyaoyao 3 Cayaoyao Tinawagan Cabalinadan *Bula 5th 2nd **Sto. Niño 4 Sto. Nino Ombao Heights Ombao Popog San Roque **BIAD II 3 San Agustin San Ramon San Isidro **Lanipga 2 Lanipga Pawili sub total 5 10 35 35

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 Page 3 of 12 Agrarian Reform Communties Project 2 (ARCP 2) List of ARC Clusters with Barangay

Income Class (as per No. of Cong. RegProvince ARC Cluster LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

VI 6 Sorsogon Casiguran ARC Connectivity Casiguran 1st 4th Casiguran ARC "A" 3 Sta Cruz Burgos Trece Martirez Casiguran Cluster "B" 4 Escuala Tigbao San Juan Inlagadian Castilla 1st 3rd San Rafael Expanded ARC 3 San Rafael San Isidro Poblacion Expanded ARC 3 Mayon San Vicente Miluya sub total 2 4 13 13 total region V 9 17 60 60

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 Page 4 of 12 Agrarian Reform Communties Project 2 (ARCP 2) List of ARC Clusters with Barangay

Income Class (as per No. of Cong. RegProvince ARC Cluster LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

VIII 9 Northern Samar Mondragon - San Roque- Catarman 1st 1st Catarman 8 Galutan ARC Cluster Hinatad Mckinley Dona Pulgueria Washington Macagtas Libjo Imelda 1st 4th Bobon 2 Arellano Balat-balud Mondragon 1st 3rd Mondragon 3 Nenita Mirador San Antonio *Lope de Vega 1st 4th **Lope de Vega 4 Poblacion Bayho Lower Caynaga Bonifacio 2nd 3rd Catubig 2 13 San Jose Sulitan Magtuad Nahulid Nabulo Bonifacio CM Recto San Antonio Anongo Roxas San Vicente Hitapi-an Sta. Fe

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 Page 5 of 12 Agrarian Reform Communties Project 2 (ARCP 2) List of ARC Clusters with Barangay

Income Class (as per No. of Cong. RegProvince ARC Cluster LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

Laoang 2nd 2nd 11 Abaton Simora La Perla Oleras Cabagngan Cabulaloan Cangcahipos Catigbian Gibatangan Sibunot Yabyaban yu76 4th Las Navas 10 Balugo Bugay Bukid Geracdo (F. Robis) Lomala-og Matelarag Rebong San Fernando San Jorge Sto. Tomas *San Roque 2nd 4th **San Roque 5 Bantayan Poblacion Zone III Balnasan Coroconog Balud *Pambujan 2nd 4th **Pambujan 4 Cabari-an Canjumadal Manahao San Ramon sub total 9 9 60 60

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 Page 6 of 12 Agrarian Reform Communties Project 2 (ARCP 2) List of ARC Clusters with Barangay

Income Class (as per No. of Cong. RegProvince ARC Cluster LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

10 Eastern Samar Sinirangan ARC Cluster Dolores Lone 4th Jicontol Valley 7 Buenavista Mangogbong Cabago-an Gap-ang Hinolaso Jicontol Osmeña **PARIK 5 Malaintos Bonghon Sto. Niño San Isidro Caglao-an Taft Lone 4th Taft 6 Del Remedios Malinao Mabuhay Lomatud Danao San Pablo *Can-avid Lone 4th **Can-avid 10 Baruk Caghalong Camantang Can-ilay Jepaco Mabuhay Guibuangan Malogo Obong Solong * Lone 4th **Sulat 5 A-et Mabini San Juan San Mateo Del Remedio sub total 4 5 33 33 Western Samar Western Samar ARC Cluster 2nd 4th CALPINSET 12 Borong (renamed to SOWSEED ARC Cluster) Majancao Hubasan Literon Lubang Minata Sinalangtan San Mauricio Bulao Canbagtic Otoc Antol

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 Page 7 of 12 Agrarian Reform Communties Project 2 (ARCP 2) List of ARC Clusters with Barangay

Income Class (as per No. of Cong. RegProvince ARC Cluster LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

Pinabacdao 2nd 4th CALPINSET 6 Loctob Madalunot Catigawan Bugho Pelaon **Pahug 5 Pahug Lale Laygayon Mambog Parasanon Villareal 2nd 4th Villareal 6 Igot Macopa Conant Nagcaduha Canmucat Tomabe Marabut 2nd 5th Marabut 11 Canyoyo Osmeña Tinabanan Caluwayan Legaspi San Roque Mabuhay Panan-awan Roño Tagalag Veloso * 2nd 1st **Samar Settlement 4 Cancaiyas Bulao Baloog Malilinab *Sta. Rita 2nd 3rd **San Juanico 5 Caticugan Sta. Elena San Juan San Pedro Pagsulhogon **Samar Settlement 4 Maligaya Union Tominamos 4. San Eduardo sub total 6 6 53 53 total region VIII 19 20 146 146 IX 13 Zamboanga del Norte Settlement ARCs Cluster * 3rd 4th ZN Resettlement 4 Poblacion Godod Delocot Mausawagon Baluno SBLP 4 Sianan Bunawan Lomogom San Pedro Chrismusu 9 Raba Rambon Sarawagan Guisapong Limbonga Banuangan Miampic Dipopor Sioran * 3rd 4th **Rubber Stump 9 Banbanan Balacbaan Cabong Poblacion (Tampilisan) Sandayong Tilubog Tininggaan Tubod Znac **ZN Resettlement 9 Camul (Tampilisan) Lawaan Barili Sto. Niño Molos New Farmington Situbo Galingon

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 Page 8 of 12 Agrarian Reform Communties Project 2 (ARCP 2) List of ARC Clusters with Barangay

Income Class (as per No. of Cong. RegProvince ARC Cluster LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

*Leon Postigo 3rd 4th **Triple MS 7 Manil Mangop Morob Sta. Maria Palandok (Rizon) Bogabongan Delusom * 3rd 3rd **Hillside 4 Dinoan Balakan Danao Tambalang sub total 4 6 46 46 14 Zamboanga del Sur Bagandian-Peninsula ARC Cluster Dinas 2nd 4th LEGANGUIMI 8 Legarda Uno Legarda Dos Legarda Tres Ig. Garrata Old Mirapao Nangka West Mirapao Guinicolalay San Miguel 2nd 4th San Miguel Cluster 5 Betinan Dao-an Libuganana Limonan Mati

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 Page 9 of 12 Agrarian Reform Communties Project 2 (ARCP 2) List of ARC Clusters with Barangay

Income Class (as per No. of Cong. RegProvince ARC Cluster LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

San Pablo 2nd 4th San Pablo Cluster 10 Mabuhay Payag Culasian Sagasan Teniapan Kapamanok Mulansong Pantad Pongapong Marcos 2nd 4th Tabina Cluster 3 Poblacion Lumbia Mabuhay 2nd 4th Dimataling Lowland 9 Tiniguangan Sugbay Uno Bacayawan Poblacion Buburay Sumpot Tinggabulong Balanagan Kagawasan * 2nd 3rd **Maruing Cluster 11 Mandeg Carpoc Linokmadalum Pantad Luanan Mahalingeb Maruing Tiguha Tabon Pingalay **Bulawan 1 Bulawan * 2nd 3rd **Kalian (Expanded) 3 Kalian Sagua Tulapoc 2nd Balongating 5 Balongating Guling** Canunan** Baguitan** Dagohoy** Pitogo 2nd Pitogo 5 Colojo Liguac** Balongbalong** Sugbay Dos** San Isidro** Vicenzo Sagun 2nd Vicenzo Sagun 14 Bui-os Cogon Danan Kabatan Kapatagan Limason Linoguayan Lumbal Lunib Maculay Maraya Sagucan Waling-waling Ambulon sub total 10 11 74 74

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 Page 10 of 12 Agrarian Reform Communties Project 2 (ARCP 2) List of ARC Clusters with Barangay

Income Class (as per No. of Cong. RegProvince ARC Cluster LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

15 Zamboanga Sibugay Ipil 2nd 1st SWIZS (forml. ) 5 Buluan Makilas Caparan Tiayon Magdaup **Greenhills 6 Bacalan Domandan Guituan Logan Tenan Upper Pangi

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 Page 11 of 12 Agrarian Reform Communties Project 2 (ARCP 2) List of ARC Clusters with Barangay

Income Class (as per No. of Cong. RegProvince ARC Cluster LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

Kabasalan 2nd 2nd Good Year 1 Good year **Greenfield 7 Buayan Concepcion Dipala Nazareth Sayao Tamin+ **Cainglet Cluster 7 Cainglet Sininan Calubihan Lumbayao Timuay Danda (Mangahas) Bolo Batallion Riverside Titay 2nd 2nd Palomoc Titay Valley 9 Palomok Achasol Asuzano Bangco Dalangin Namnama Poblacion Mabini Tugop **Highlander 7 Santa Fe Pulidan Kipit Dalisay San Antonio Longilog Mate Naga 2nd 3rd **Golden Valley 9 Baga Baluno Bangkaw-bangkaw Crossing Sta. Clara Kaliantana LA Paz Mamagon Santa Clara Upper Sulitan

Tungawan 2nd 2nd Tri-People () 8 Sisay Langon Libertad Masao Baluran Gaycon Timbabawan Tigbanuang **SALLAM 5 Taglibas Looc-labuan Linguisan Tigbucay San Vicente *R.T. Lim 2nd 3rd **West Sibugay Bay 10 Gango Silingan Calula Pres. Roxas Mabini Kulambugan Katipunan Casacon Magsaysay Tupilac sub total 6 11 74 74 total region IX 20 28 194 194

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 Page 12 of 12 Agrarian Reform Communties Project 2 (ARCP 2) List of ARC Clusters with Barangay

Income Class (as per No. of Cong. RegProvince ARC Cluster LGU DOF Order No. 23-08 ARC ARC Barangays Covered District dated 07/29/08 Brgys.

ARMM 16 Maguindanao SLAM Alliance * 2nd new Kadayunan 1 Ramcor 2nd 4th Bunawan 3 Bunawan Kalumenga Napok * 2nd 2nd **Mileb 5 Mileb Barurao Sampao Kulambog Panadtaban Inrandum Alliance Parang 1st 1st Macarimbang 4 GT Biruar Gadungan Samberen Orandang 1st 4th Langkong 2 Langkong Bayanga Norte * 1st 4th MRP #1 ARC 4 Nuyo Dinganen Edcor Batatawan * 1st 4th MRP #1 ARC 9 Tugaig Nabalawag Barira Liong Lipa Marang Gadung Bualan Ruminimbang 7 7 27 28 Lanao del Sur Wao-Bumbaran Alliance Bumbaran 1st 3rd Bumbaran 7 Sumugot Franfort Lambanogan Punud Comara Apartfort Mansilao *Wao 1st 2nd Milaya 6 Milaya Amoyong Katutungan Kadingilan Bout Cebuano 2 2 6 6 total ARMM 9 9 33 34 GRAND TOTAL 60 78 443 444

* Additional LGU included in ARC Cluster ** Additional ARC included in ARC Cluster Note: List updated as of January 11, 2012 ANNEX IV: LIST OF APPROVED SUBPROJECTS, with physical status DAR-ADB Agrarian Reform Communities Project II NSAC and RSAC Approved Subprojects As of December 2017

NSAC/RSAC SUBPROJECT TITLE PROVINCE ARC Barangay Physical Status DATE REGION

1 Rehab w/ Spot Concreting of Pag-Asa-Conrazon FMR NSAC 27 16-Nov-12 4-B Oriental Mindoro Bansud SALCEDO ARC Pag-Asa; Conrazon completed

2 Const & Rehab w/ Spot Concreting of Laway I-Kantong Putol FMR NSAC 27 16-Nov-12 4-B Oriental Mindoro Bansud SALCEDO ARC Salcedo completed 3 Const of Sagana Health Building NSAC 26 30-Oct-12 4-B Oriental Mindoro Bongabong Bongabong Central ARC Sagana completed 4 Rehabilitation of Anilorcu CIS NSAC 34 06-Sep-13 4-B Oriental Mindoro Bongabong Bongabong Central ARC Anilao; Orcunoma completed 5 Construction of Anilao FMR NSAC 34 06-Sep-13 4-B Oriental Mindoro Bongabong Bongabong Central ARC Anilao completed 6 Concreting of Orcunoma-Mina de Oro FMR NSAC 34 06-Sep-13 4-B Oriental Mindoro Bongabong Bongabong Central ARC Mina de Oro; Orcunoma completed 7 Rehab with Spot Concreting of San Roque-Tafarma FMR NSAC 25 19-Oct-12 4-B Oriental Mindoro Bulalacao Bulalacao ARC San Roque completed

8 Rehab with Spot Concreting of Dancalan-San Roque-Libtong FMR NSAC 26 30-Oct-12 4-B Oriental Mindoro Bulalacao Bulalacao ARC San Roque completed 9 Concreting of Cambunang-Napisian-Cogon Malapad FMR NSAC 29 19-Dec-12 4-B Oriental Mindoro Bulalacao Bulalacao ARC Cambunang on going 10 Concreting of Sta. Maria-Villarosa FMR NSAC 28 29-Nov-12 4-B Oriental Mindoro Mansalay MARBRIDA ARC Sta. Maria on going 11 Concreting of Balugo-Maliwanag FMR NSAC 28 29-Nov-12 4-B Oriental Mindoro Mansalay MARBRIDA ARC Balugo on going 12 Construction with Spot Concreting of Sta. Brigida-Alegria FMR NSAC 28 29-Nov-12 4-B Oriental Mindoro Mansalay MARBRIDA ARC Sta. Brigida on going 13 Construction/Rehabilitation of Tagpit-Titibawan FMR NSAC 31 26-Apr-13 4-B Palawan Aborlan Iraan-Isaub ARC Isaub; San Juan completed 14 Rehabilitation of Apurawan CIS NSAC 32 07-Jun-13 4-B Palawan Aborlan Iraan-Isaub ARC Apurawan completed 15 Rehabilitation of Talakaigan CIS NSAC 32 07-Jun-13 4-B Palawan Aborlan Iraan-Isaub ARC Apoc-apoc completed 16 Rehab of Balogo PWS NSAC 18 18-May-12 4-B Romblon Calatrava Balogo ARC Balogo completed 17 Concreting of Hinag-oman-Culasi-Guin-awayan FMR NSAC 23 14-Sep-12 4-B Romblon Ferrol C.M. Recto ARC Hinag-oman completed 18 Concreting of CM Recto-Lupog FMR NSAC 23 14-Sep-12 4-B Romblon Ferrol C.M. Recto ARC C.M. Recto; Lupog on going 19 Construction of C.M. Recto Barangay Health Center NSAC 29 19-Dec-12 4-B Romblon Ferrol C.M. Recto ARC C.M. Recto; Lupog completed 20 Const of Limon Norte Barangay Health Center NSAC 20 05-Jul-12 4-B Romblon Looc Liliput ARC Limon Norte completed 21 Const of Limon Sur Barangay Health Center NSAC 20 05-Jul-12 4-B Romblon Looc Liliput ARC Limon Sur completed 22 Const of Tampayan Proper Health Center NSAC 7 30-Mar-11 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Tampayan completed 23 Const of Two (2) Classrooms School Building for Tomas and Maria MaglayaNSAC Memorial 7 School 30-Mar-11 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Tampayan completed 24 Const of Franco Day Care Center NSAC 18 18-May-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Dulangan completed Tampayan; Jao-Asan; 25 Const of Tampayan/Jao-Asan PWS Level II NSAC 19 07-Jun-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Poblacion completed 26 Rehab of Binaliwan FMR NSAC 19 07-Jun-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Tampayan completed 27 Rehab of Cataja FMR NSAC 19 07-Jun-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Jao-Asan completed 28 Const of Two (2) Classrooms School Building for Ambulong ElementaryNSAC School 20 05-Jul-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Ambulong completed 29 Const of Two (2) Classrooms School Building for Jao-asan ElementaryNSAC School 20 05-Jul-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Jao-asan completed 30 Const of Jao-Asan Two (2) Unit Classroom Building with Comfort RoomsNSAC for Tomas 21 and Maglaya 31-Jul-12 Memorial School 4-B Romblon (Phase II) Magdiwang Tampayan/Jao-asan ARC Tampayan completed 31 Const of Two (2) Classroom School Building with Comfort Room NSAC 26 30-Oct-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Ipil completed 32 Const of Sanghiran-Campo-Agpudlos Proper FMR NSAC 9 25-Aug-11 4-B Romblon San Andres Agpudlos ARC Agpudlos completed 33 Const of España MPB NSAC 25 19-Oct-12 4-B Romblon San Fernando Taclobo ARC España completed NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

34 Const of Taclobo MPB NSAC 25 19-Oct-12 4-B Romblon San Fernando Taclobo ARC Taclobo completed 35 Rehab of Palate FMR NSAC 9 25-Aug-11 4-B Romblon Sta. Fe Magsaysay ARC Magsaysay completed 36 Rehab w/ Spot Concreting of Magsaysay-Pandan FMR NSAC 21 31-Jul-12 4-B Romblon Sta. Fe Magsaysay ARC Magsaysay; Pandan completed 37 Concreting of Tuaca-San Pascual FMR NSAC 11 4-Nov-11 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCTuaca; San Pascual completed 38 Concreting of Caayunan FMR NSAC 11 4-Nov-11 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCCaayunan completed 39 Concreting of San Felipe FMR NSAC 21 31-Jul-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCSan Felipe completed 40 Concreting of Matnog FMR NSAC 24 27-Sep-12 5 Camarines Norte Basud MATLAMALABAC ARC Matnog completed 41 Const of Laniton FMR NSAC 26 30-Oct-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterLaniton ongoing 42 Concreting of Tuaca-San Pascual FMR (Phase II) NSAC 27 16-Nov-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterTuaca; San Pascual completed 43 Concreting of San Felipe-Caayunan FMR NSAC 28 29-Nov-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterSan Felipe completed 44 Concreting of San Felipe-Mantugawe FMR NSAC 28 29-Nov-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterSan Felipe completed 45 Construction of One (1) Unit Warehouse with Office (Brgy. Laniton) NSAC 34 06-Sep-13 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterLaniton completed 46 Construction of Multipurppose Pavement (Brgy. Laniton) RSAC 5 29-Nov-11 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCLaniton completed 47 Rehabilitation of Mampili Level II Potable Water System RSAC 5 29-Nov-11 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCMampili completed 48 Construction of Access Road for ARCCESS RSAC 7 30-Mar-12 5 Camarines Norte Basud Matnog ARC Laniton completed 49 Construction of Multipurpose Pavement/Solar Dryer in Barangay LanitonRSAC 7 30-Mar-12 5 Camarines Norte Basud Matnog ARC Laniton completed 50 Concreting of Brgy. San Martin FMR NSAC 17 20-Apr-12 5 Camarines Norte Jose Panganiban San Pedro ARC San Martin completed 51 Concreting of Brgy. San Pedro FMR NSAC 17 20-Apr-12 5 Camarines Norte Jose Panganiban San Pedro ARC San Pedro ongoing 52 Concreting of Brgy. Tamisan FMR NSAC 17 20-Apr-12 5 Camarines Norte Jose Panganiban San Pedro ARC Tamisan completed 53 Concreting of Brgy. San Rafael-Sta. Rosa Norte FMR NSAC 17 20-Apr-12 5 Camarines Norte Jose Panganiban San Pedro ARC San Rafael completed 54 Concreting of San Pedro-Bagong Silang II FMR NSAC 31 26-Apr-13 5 Camarines Norte Jose Panganiban San Pedro ARC San Pedro ongoing 55 Concreting of Brgy. Tamisan FMR Phase II NSAC 35 18-Oct-13 5 Camarines Norte Jose Panganiban San Pedro ARC Tamisan ongoing 56 Concreting of Macogon Barangay Road NSAC 11 4-Nov-11 5 Camarines Norte Labo Daguit ARC Macogon completed 57 Concreting of Naboongan-Igang FMR NSAC 13 19-Dec-11 5 Camarines Norte Labo Daguit ARC Daguit completed 58 Construction of 1 FMR NSAC 13 19-Dec-11 5 Camarines Norte Labo Daguit ARC Talobatib completed 59 Concreting of Purok 7 FMR NSAC 13 19-Dec-11 5 Camarines Norte Labo Daguit ARC Talobatib completed 60 Concreting of Malangcao Basud Purok 6-Purok 7 FMR NSAC 13 19-Dec-11 5 Camarines Norte Labo Daguit ARC Malangcao completed 61 Concreting of Lugui FMR NSAC 35 18-Oct-13 5 Camarines Norte Labo Lugui ARC Lugui completed 62 Concreting of Iberica FMR NSAC 35 18-Oct-13 5 Camarines Norte Labo Lugui ARC Iberica completed 63 Concreting of San Antonio FMR NSAC 35 18-Oct-13 5 Camarines Norte Labo Lugui ARC San Antonio ongoing 64 Concreting of Mabilo I FMR NSAC 35 18-Oct-13 5 Camarines Norte Labo Lugui ARC Mabilo I completed 65 Construction of Solar Dryer (Brgy. Daguit) RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Daguit completed 66 Construction of DARBO Multi-Purpose Building (Brgy. Daguit) RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Daguit completed 67 Construction of Day Care Center (Brgy. Daguit) RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Daguit completed 68 Construction of Solar Dryer (Brgy. Malangcao Basud) RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Malangcao Basud completed 69 Construction of Malangcao Basud Health Station RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Malangcao Basud completed 70 Rehabilitaion of Macogon Level II Potable Water System RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Macogon completed 71 Construction of PHF/Warehouse RSAC 7 30-Mar-12 5 Camarines Norte Labo Daguit ARC Daguit completed 72 Rehab of Matanlang-Casalugan FMR NSAC 11 4-Nov-11 5 Camarines Norte Paracale Batobalani ARC Tawig completed 73 Concreting of Capacuan (Purok 1-5) FMR NSAC 11 4-Nov-11 5 Camarines Norte Paracale Batobalani ARC Capacuan completed 74 Concreting of Batobalani-Igang FMR NSAC 14 19-Jan-12 5 Camarines Norte Paracale Batobalani ARC Batobalani completed 75 Concreting of Sitio Submakin FMR NSAC 19 07-Jun-12 5 Camarines Norte Paracale Batobalani ARC Batobalani completed NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

76 Const of Sitio Potot FMR NSAC 19 07-Jun-12 5 Camarines Norte Paracale Batobalani ARC Batobalani completed 77 Concreting of Batobalani-Igang FMR (Phase II) NSAC 19 07-Jun-12 5 Camarines Norte Paracale Batobalani ARC Batobalani completed 78 Concreting of Dagang-Tabas FMR NSAC 22 24-Aug-12 5 Camarines Norte Paracale Batobalani ARC Dagang completed 79 Const of Day Care Center (Brgy. Dagang) RSAC 5 29-Nov-11 5 Camarines Norte Paracale Batobalani ARC Dagang completed 80 Const of MPB (Brgy. Batobalani) RSAC 5 29-Nov-11 5 Camarines Norte Paracale Batobalani ARC Batobalani completed 81 Const of Balumbon Spring Level II Water System RSAC 5 29-Nov-11 5 Camarines Norte Paracale Batobalani ARC Dagang completed 82 Improv/Expansion of Level II Water System (Brgy. Tawig) RSAC 5 29-Nov-11 5 Camarines Norte Paracale Batobalani ARC Tawig completed 83 Const of San Isidro-Sitio Too FMR NSAC 13 19-Dec-11 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Isidro completed 84 Concreting of Matacong-San Isidro FMR NSAC 13 19-Dec-11 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC Matacong completed 85 Concreting of Matacong-San Isidro FMR (Extension) NSAC 20 05-Jul-12 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Isidro completed 86 Concreting of Purok 2 Matacong FMR NSAC 27 16-Nov-12 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC Matacong completed 87 Concreting of Brgy. San Ramon FMR NSAC 40 29-Apr-15 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Ramon completed 88 Const of San Ramon Day Care Center RSAC 3 15-Oct-10 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Ramon completed 89 Const of San Isidro Day Care Center RSAC 3 15-Oct-10 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Isidro completed 90 Const of Matacong Day Care Center RSAC 3 15-Oct-10 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC Matacong completed 91 Const of San Ramon MPP RSAC 3 15-Oct-10 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Ramon completed 92 Concreting of San Ramon, Purok 1-Purok 2 FMR RSAC 5 29-Nov-11 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Ramon completed 93 Const of SIARBECO MPB and Warehouse RSAC 5 29-Nov-11 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Isidro completed Const of Buluang-San Isidro-Sta. Teresita-Agdangan Service Buluang; San Isidro; Sta. 94 Road NSAC 24 27-Sep-12 5 Camarines Sur Baao Agdangan-San Rafael ARC Teresita; Agdangan completed 95 Concreting of Iyagan-Cristo Rey FMR NSAC 32 07-Jun-13 5 Camarines Sur Baao Agdangan-San Rafael ARC Agdangan; San Rafael completed 96 Concreting of Agdangan-San Rafael Circumferential Road RSAC 4 15-Jun-11 5 Camarines Sur Baao Agdangan-San Rafael ARC Agdangan completed 97 Rehab of Caranday-Cristo Rey FMR RSAC 4 15-Jun-11 5 Camarines Sur Baao Agdangan-San Rafael ARC completed 98 Rehab of Caranday-Del Pilar FMR RSAC 4 15-Jun-11 5 Camarines Sur Baao Agdangan-San Rafael ARC completed 99 Concreting of Antipolo-Divino Rostro FMR NSAC 18 18-May-12 5 Camarines Sur Buhi Antipolo-Divino Rostro ARC Antipolo; Divino Rostro completed 100 Concreting of San Rafael FMR NSAC 24 27-Sep-12 5 Camarines Sur Buhi Antipolo-Divino Rostro ARC San Rafael completed 101 Concreting of Mariyokriyok FMR NSAC 28 29-Nov-12 5 Camarines Sur Buhi Antipolo-Divino Rostro ARC San Francisco completed 102 Rehab of Maligaw-ligaw FMR RSAC 3 15-Oct-10 5 Camarines Sur Buhi Antipolo-Divino Rostro ARC completed 103 Concreting of Sto. Domingo-San Isidro-San Agustin-San Ramon FMRNSAC 20 05-Jul-12 5 Camarines Sur Bula BIAD II Bula Side ARC Sto. Domingo; San Isidro; San Agustin;completed San Ramon 104 Concreting of Highway-Lanipga FMR NSAC 24 27-Sep-12 5 Camarines Sur Bula Lanipga ARC Lanipga ongoing 105 Construction of 2-Storey MultiPurpose Building of Lanipga RSAC 7 30-Mar-12 5 Camarines Sur Bula Lanipga ARC Lanipga completed 106 Construction of Lanipga Solar Dryer RSAC 7 30-Mar-12 5 Camarines Sur Bula Lanipga ARC Lanipga completed 107 Construction of Day Care Center in Barangay Lanipga RSAC 7 30-Mar-12 5 Camarines Sur Bula Lanipga ARC Lanipga completed 108 Construction of Solar Dryer San Isidro ARC RSAC 7 30-Mar-12 5 Camarines Sur Bula Lanipga ARC completed 109 Concreting of Pinagdapian FMR NSAC 21 31-Jul-12 5 Camarines Sur Del Gallego Danawin ARC Pinagdapian completed 110 Rehab/Concreting of San Juan FMR NSAC 23 14-Sep-12 5 Camarines Sur Del Gallego Danawin ARC San Juan completed 111 Concreting of Peñafrancia FMR NSAC 26 30-Oct-12 5 Camarines Sur Del Gallego Danawin ARC Peñafrancia completed 112 Concreting of Tomagoktok FMR NSAC 26 30-Oct-12 5 Camarines Sur Del Gallego Danawin ARC Tomagoktok completed 113 Construction of Tabion FMR NSAC 31 26-Apr-13 5 Camarines Sur Del Gallego Danawin ARC Tabion completed 114 Concreting of Mansalaya FMR NSAC 31 26-Apr-13 5 Camarines Sur Del Gallego Danawin ARC Mansalaya completed 115 Construction of Health Center RSAC 4 15-Jun-11 5 Camarines Sur Del Gallego Danawin ARC Comadaycaday completed 116 Rehab of Ason-Poblacion FMR NSAC 1 2-Sep-09 5 Camarines Sur Garchitorena Del Pilar ARC Ason; Del Pilar ongoing 117 Concreting of Bahi-Ason FMR NSAC 18 18-May-12 5 Camarines Sur Garchitorena Del Pilar ARC Bahi; Ason ongoing NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

118 Construction of Flood Control NSAC 24 27-Sep-12 5 Camarines Sur Garchitorena Del Pilar ARC Ason ongoing 119 Const of Del Pilar Multi-Purpose Pavement RSAC 3 15-Oct-10 5 Camarines Sur Garchitorena Del Pilar ARC Del Pilar completed 120 Const of Ason Multi-Purpose Pavement RSAC 3 15-Oct-10 5 Camarines Sur Garchitorena Del Pilar ARC Ason completed 121 Const of Ason 2-Classroom Building RSAC 3 15-Oct-10 5 Camarines Sur Garchitorena Del Pilar ARC Ason completed 122 Const of del Pilar Classroom Building RSAC 3 15-Oct-10 5 Camarines Sur Garchitorena Del Pilar ARC Del Pilar completed 123 Construction of Health Station in Barangay Salvacion RSAC 7 30-Mar-12 5 Camarines Sur Garchitorena Del Pilar ARC Salvacion ongoing 124 Construction of Health Station in Barangay Del Pilar RSAC 7 30-Mar-12 5 Camarines Sur Garchitorena Del Pilar ARC Del Pilar ongoing 125 Construction of 2-Classroom School Building in Barangay SalvacionRSAC 7 30-Mar-12 5 Camarines Sur Garchitorena Del Pilar ARC Salvacion ongoing 126 Flood Control Structure (Revetment) Del Pilar RSAC 8 31-Jul-13 5 Camarines Sur Garchitorena Del Pilar ARC Del Pilar completed 127 Concreting of Bahay FMR NSAC 21 31-Jul-12 5 Camarines Sur Libmanan Bahay ARC Bahay completed 128 Concreting of Potot FMR NSAC 21 31-Jul-12 5 Camarines Sur Libmanan Bahay ARC Potot ongoing 129 Concreting of Sitio Hamorawon FMR NSAC 21 31-Jul-12 5 Camarines Sur Libmanan Bahay ARC San Pablo ongoing 130 Improvement of Aslong FMR RSAC 3 15-Oct-10 5 Camarines Sur Libmanan Bahay ARC completed 131 Construction of MultiPurpose Building in Barangay Bahay RSAC 7 30-Mar-12 5 Camarines Sur Libmanan Bahay ARC Bahay completed 132 Construction of MultiPurpose Building in Barangay Potot RSAC 7 30-Mar-12 5 Camarines Sur Libmanan Bahay ARC Potot completed 133 Construction of MultiPurpose Building in Barangay Malinao RSAC 7 30-Mar-12 5 Camarines Sur Libmanan Bahay ARC Malinao completed 134 Const of Cabugao FMR NSAC 5 12-Jul-10 5 Camarines Sur Milaor Milaor ARC Cabugao ongoing 135 Const and Concreting of Cabugao-Maydaso FMR NSAC 20 05-Jul-12 5 Camarines Sur Milaor Cabugao ARC Cabugao; Maydaso completed 136 Concreting of Cabugao-Mayaopayawan-San Antonio FMR NSAC 20 05-Jul-12 5 Camarines Sur Milaor Cabugao ARC Cabugao; Mayaopayawan; San Antoniocompleted 137 Construction of 2-Storey MultiPurpose Building in Barangay CabugaoRSAC 7 30-Mar-12 5 Camarines Sur Milaor Cabugao ARC Cabugao completed 138 Construction of 2-Storey MultiPurpose Building in Barangay San AntonioRSAC 7 30-Mar-12 5 Camarines Sur Milaor Cabugao ARC San Antonio completed 139 Concreting of Hanawan-Dinurog FMR NSAC 25 19-Oct-12 5 Camarines Sur Ocampo May-ogob ARC Hanawan completed 140 Concreting of Old Moriones-San Roque Communal FMR NSAC 34 06-Sep-13 5 Camarines Sur Ocampo Old Moriones-San Roque Communal ARCOld Moriones completed 141 Construction of One-Unit-Two (2) Classroom School Building (Bgy. DelNSAC Rosario) 31 26-Apr-13 5 Camarines Sur Pili Bagong Sirang ARC Del Rosario completed 142 Construction of One-Unit-Two (2) Classroom School Building (Bgy. BagongNSAC Sirang) 31 26-Apr-13 5 Camarines Sur Pili Bagong Sirang ARC Bagong Sirang completed 143 Construction of Solar Dryer for Bagong Sirang ARC RSAC 7 30-Mar-12 5 Camarines Sur Pili Bagong Sirang ARC completed 144 Construction of Solar Dryer for Binobong ARC RSAC 7 30-Mar-12 5 Camarines Sur Pili Binobong ARC completed 145 Improvement of Binobong ARC Farm to Market Road RSAC 7 30-Mar-12 5 Camarines Sur Pili Binobong ARC completed 146 Construction of 2-CL School Building for Binobong ARC RSAC 7 30-Mar-12 5 Camarines Sur Pili Binobong ARC completed 147 Construction of 2-CL School Building for Sagrada ARC RSAC 7 30-Mar-12 5 Camarines Sur Pili Binobong ARC completed 148 Concreting of Tinawagan-Coyaoyao FMR NSAC 27 16-Nov-12 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC Tinawagan; Coyaoyao ongoing 149 Concreting of Tinawagan-Barobaroti-Caraycayon FMR NSAC 27 16-Nov-12 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC Tinawagan; Barobaroti; Caraycayon ongoing 150 Construction of Day Care Center (Brgy. Gubat) RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC Gubat completed 151 Construction of Day Care Center (Brgy. San Francisco) RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC San Francisco completed 152 Construction of Day Care Center (Brgy. Coyaoyao) RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC Coyaoyao completed 153 Construction of Day Care Center (Brgy. Talojongon) RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC Talojongon completed 154 Construction of 2-classroom Huyon-huyon School Building RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC completed 155 Construction of 2-classroom Panagan School Building RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC completed 156 Construction of Cabalinadan School Building (Package I) RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC completed 157 Construction of Cabalinadan School Building (Package II) RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC completed 158 Construction of Tinawagan School Building (Package I) RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC Tinawagan completed 159 Construction of Tinawagan School Building (Package II) RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC Tinawagan completed 160 Construction of Gubat School Building RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC Gubat completed NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

161 Construction of Mabalodbalod School Building (Package I) RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC completed 162 Construction of Mabalodbalod School Building (Package II) RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC completed 163 Construction of San Francisco School Building RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC San Francisco completed 164 Construction of Vinagre School Building RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC completed 165 Construction of Salvacion School Building RSAC 6 27-Dec-11 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC completed 166 Concreting of Lajong FMR NSAC 19 07-Jun-12 5 Sorsogon Bulan Bulan ARC Lajong completed 167 Concreting of Fabrica-G. del Pilar FMR NSAC 19 07-Jun-12 5 Sorsogon Bulan Bulan ARC Fabrica; G. del Pilar completed 168 Rehabilitation/Improvement of A. Bonifacio SWIP NSAC 31 26-Apr-13 5 Sorsogon Bulan Bulan ARC A. Bonifacio completed

169 Const of Boton Flood Control Structure (Flood Protection Works) NSAC 16 30-Mar-12 5 Sorsogon Casiguran Casiguran ARC Boton completed 170 Concreting Trese Martires-Boton FMR NSAC 18 18-May-12 5 Sorsogon Casiguran Casiguran ARC Boton; Trese Martires ongoing

ongoing 171 Const of Boton Flood Control Structure (Phase II) NSAC 22 24-Aug-12 5 Sorsogon Casiguran Casiguran ARC Boton

172 Construction of 2 Storey Multi-Purpose Building RSAC 2 17-Aug-10 5 Sorsogon Casiguran Casiguran ARC A completed

173 Rehab/Improv of San Isidro-Nalup-an FMR NSAC 5 12-Jul-10 5 Sorsogon Castilla San Rafael Expanded ARC San Isidro completed 174 Rehabilitation of Pili CIS NSAC 31 26-Apr-13 5 Sorsogon Castilla San Rafael Expanded ARC San Isidro; San Rafael; Mayon; Maracabaccompleted 175 Construction of 2-Classroom School Building (Quirapi) RSAC 8 31-Jul-13 5 Sorsogon Castilla Castilla NCI Quirapi ongoing 176 Construction of 2-Classroom School Building (Pandan) RSAC 8 31-Jul-13 5 Sorsogon Castilla Castilla NCI Pandan ongoing 177 Construction of 2-Classroom School Building (Amomonting) RSAC 8 31-Jul-13 5 Sorsogon Castilla Castilla NCI Amomonting ongoing 178 Construction of 2-Classroom School Building (Buenavista) RSAC 8 31-Jul-13 5 Sorsogon Castilla Castilla NCI Buenavista ongoing 179 Construction of 2-Classroom School Building (Cumadcad/Rosal E/S)RSAC 8 31-Jul-13 5 Sorsogon Castilla Castilla NCI Cumadcad/Rosal ongoing 180 Construction of 2-Classroom School Building (Dinapa) RSAC 8 31-Jul-13 5 Sorsogon Castilla Castilla NCI Dinapa ongoing 181 Construction of 2-Classroom School Building (Cogon) RSAC 8 31-Jul-13 5 Sorsogon Castilla Castilla NCI Cogon ongoing 182 Construction of 2-Classroom School Building (Dancalan) RSAC 8 31-Jul-13 5 Sorsogon Castilla Castilla NCI Dancalan ongoing 183 Construction of 2-Classroom School Building (Sogoy) RSAC 8 31-Jul-13 5 Sorsogon Castilla Castilla NCI Sogoy ongoing 184 Concreting of Jupi-Dita FMR NSAC 29 19-Dec-12 5 Sorsogon Gubat Gubat ARC Dita; Jupi completed 185 Concreting of Bagsangan-Monbon FMR NSAC 17 20-Apr-12 5 Sorsogon Irosin Irosin ARC Bagsangan; Monbon ongoing 186 Rehabilitation of Burabod-San Julian CIS NSAC 32 07-Jun-13 5 Sorsogon Irosin Irosin ARC ongoing 187 Const of 600 sq.m. Solar Drier RSAC 4 15-Jun-11 5 Sorsogon Irosin Irosin Municipal ARC Bagsangan completed 188 Rehab of Sipaya-Calateo FMR NSAC 9 25-Aug-11 5 Sorsogon Juban Juban ARC Sipaya; Calateo completed 189 Const of Sipaya-Taboc FMR NSAC 18 18-May-12 5 Sorsogon Juban Juban ARC Sipaya; Taboc ongoing

190 Roadway Construction and Concreting of Hidhid-Banogao FMR NSAC 23 14-Sep-12 5 Sorsogon Matnog Matnog ARC Hihid; Banogao completed 191 Construction of Health Center (Bolos) * RSAC 4 15-Jun-11 5 Sorsogon Matnog Matnog ARC Bolo completed 192 Construction of 2-Classroom School Building (Brgy. Hidhid) RSAC 8 31-Jul-13 5 Sorsogon Matnog Matnog ARC Hidhid completed 193 Construction of 2-Classroom School Building (Brgy. Bolo) RSAC 8 31-Jul-13 5 Sorsogon Matnog Matnog ARC Bolo completed Concreting of Sitio Nagpana to Sitio Proper, Lipata to San 194 Geronimo FMR NSAC 34 06-Sep-13 6 Iloilo Barotac Viejo Lipata Special ARC Lipata completed NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

Concreting/Rehabilitation of Junction Tapacon-Inamyugan-Agbao- Tapacon; Agba-o; ongoing 195 Guinhulagan FMR w/ Bridge NSAC 37 18-Feb-14 6 Iloilo Bingawan GUINTAPAGIN ARC Guinhulacan; Inamyugan 196 Concreting of Pulao-Bulod-Sulangan FMR NSAC 34 06-Sep-13 6 Iloilo Dumangas Dumangas ARC Pulao; Sulangan ongoing 197 Concreting of JNR-Agsirab-Bagongbong-Sitio Agdalusan FMR NSAC 35 18-Oct-13 6 Iloilo Lambunao AGSIBAGO ARC Agsirab; Bagongbong completed

ongoing 198 Concreting of San Andres – San Florentino FMR with Bridge NSAC 37 18-Feb-14 6 Iloilo San Rafael San Andres-San Florentino ARC San Andres; San Florentino 199 Rehab/Const of Sitio Cantacson-Hag-ik FMR NSAC 21 31-Jul-12 6 Negros Occidental Candoni Caningay ARC Caningay completed 200 Rehab of Junction National Highway-Purok 5 FMR NSAC 19 07-Jun-12 6 Negros Occidental Hinoba-an Pagbana-ag ARC Asia completed 201 Construction of Brgy. Asia Health Station RSAC 2 31-Jul-12 6 Negros Occidental Hinoba-an Pagbana-ag ARC Asia completed 202 Construction of 2-Classroom School Building with Hallway in Brgy. AlimRSAC 2 31-Jul-12 6 Negros Occidental Hinoba-an Pagbana-ag ARC Alim completed

203 Concreting of Brgy. Gen. Malvar Proper to Purok 1 Road NSAC 23 14-Sep-12 6 Negros Occidental Pontevedra Gen. Malvar ARC General Malvar completed

204 Const/Rehab of Brgy Proper to Purok 4 (Tamsik) Road RSAC 1 14-Dec-10 6 Negros Occidental Pontevedra General Malvar ARC General Malvar completed 205 Construction of 2-Classroom School Building with Comfort Rooms RSAC 2 31-Jul-12 6 Negros Occidental Pontevedra General Malvar ARC General Malvar completed 206 Construction of Multi-Purpose Pavement in Purok 1 RSAC 2 31-Jul-12 6 Negros Occidental Pontevedra General Malvar ARC General Malvar completed 207 Construction of Multi-Purpose Pavement in Purok 5 RSAC 2 31-Jul-12 6 Negros Occidental Pontevedra General Malvar ARC General Malvar completed 208 Construction of Agricultural Warehouse RSAC 2 31-Jul-12 6 Negros Occidental Pontevedra General Malvar ARC General Malvar completed

209 Rehab of ALBAPA FMR NSAC 7 30-Mar-11 6 Negros Occidental Valladolid ALBAPA ARC Bayabas; Alijis; Pacol completed

210 Const of Salvacion-Langit FMR NSAC 4 16-Mar-10 8 Leyte Alangalang Alangalang 1 ARC Salvacion; Langit completed

Petrolio; Malobago; Kawayanan; ongoing Tuburan;Kawayanan; Tuburan; 211 Rehabilitation of Petrolio-Villanueva FMR NSAC 30 22-Mar-13 8 Leyte Calubian Calubian II ARC ; Bugtongang, Villanueva 212 Rehab of Visares-Balugo FMR NSAC 2 16-Oct-09 8 Leyte Capoocan Capoocan ARC Visares; Balugo ongoing 213 Rehabilitation of Tabunok CIS NSAC 33 17-Jul-13 8 Leyte Hilongos Hilongos ARC Tabunok completed 214 Rehabilitation of Tagbawto CIS NSAC 33 17-Jul-13 8 Leyte Hilongos Hilongos ARC Tagbawto completed 215 Rehab of Marao-Macagoco FMR NSAC 25 19-Oct-12 8 Leyte Inopacan Inopacan ARC Marao; Macagoco completed 216 Rehabilitation of Guinsangaan-Can-angay FMR NSAC 29 19-Dec-12 8 Leyte Inopacan Inopacan ARC Can-angay; Marao completed 217 Const of Manlilisid-San Sotero FMR NSAC 6 27-Jan-11 8 Leyte Javier Javier Settlement ARC Manlilisid; San Sotero completed 218 Concreting of San Sotero-Ulhay FMR NSAC 18 18-May-12 8 Leyte Javier Javier Settlement ARC San Sotero; Ulhay completed Zone 1; Pinocawan; A. ongoing 219 Concreting of Zone 1-Pinocawan-Bonifacio-Talisayan FMR NSAC 18 18-May-12 8 Leyte Javier Javier Settlement ARC Bonifacio; Talisayan 220 Concreting of Odiong-Guindapunan FMR NSAC 19 07-Jun-12 8 Leyte Javier Javier Settlement ARC Odiong; Guindapunan completed

221 Concreting of San Sotero-Caraye FMR NSAC 20 05-Jul-12 8 Leyte Javier Javier Settlement ARC Caraye; San Sotero ongoing

Laray; Magsaysay; ongoing 222 Concreting of Laray-Magsaysay-Malitbogay FMR NSAC 23 14-Sep-12 8 Leyte Javier Javier Settlement ARC Malitbogay 223 Concreting of Sitio Km. 14-Sitio Torrel, Brgy. Masarayao FMR NSAC 21 31-Jul-12 8 Leyte Kananga Kananga ARC Masarayao completed 224 Rehab of Brgy. Esperanza-San Vicente FMR NSAC 15 01-Mar-12 8 Leyte Matalom Matalom II ARC Esperanza; San Vicente completed NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

225 Rehab of Elevado-Pres. Garcia FMR NSAC 27 16-Nov-12 8 Leyte Matalom Matalom II ARC Elevado; Pres. Garcia completed 226 Const of Cambalong Warehouse & Solar Dryer NSAC 27 16-Nov-12 8 Leyte Merida Merida II ARC Cambalong on going San Agustin; Capirawan; 227 Const of San Agustin-Capirawan-Cangubang FMR NSAC 2 16-Oct-09 8 Leyte Palo Palo 2 ARC Cangumbang completed Capirawan; Canhidoc; 228 Construction of Capirawan-Gacao-Canhidoc-Arado FMR NSAC 33 17-Jul-13 8 Leyte Palo Palo 2 ARC Gacao; Arado completed 229 Const/Improv of Brgy. Crossing-Brgy. Biasong FMR NSAC 3 19-Nov-09 8 Leyte San Isidro San Isidro ARC Brgy. Crossing; Biasong completed 230 Rehabilitation of Bawod-Paril FMR NSAC 33 17-Jul-13 8 Leyte San Isidro San Isidro ARC Bawod; Paril completed

231 Canmogsay-Capangihan PWS LII NSAC 28 29-Nov-12 8 Leyte Tolosa Tolosa ARC Capangihan; Canmogsay completed

232 Rehab of Casili-on-Sambulawan FMR NSAC 6 27-Jan-11 8 Leyte Villaba Villaba ARC Casili-on; Sambulawan completed

233 Const of Sitio Balukawe-Balat Balud FMR NSAC 6 27-Jan-11 8 Northern Samar Bobon Bobon ARC Salvacion; Balat Balud completed

234 Const of Brgy. Salvacion-Sitio Balukawe FMR NSAC 22 24-Aug-12 8 Northern Samar Bobon Bobon ARC Salvacion completed

235 Concreting of Trojillo-Calantiao FMR NSAC 32 07-Jun-13 8 Northern Samar Bobon Bobon ARC Calantiao; Trojillo completed

Calingnan; San Francisco; Const of Calingnan-San Francisco-Cagugubngan-Osmeña-Nabulo- Cagugubngan; Osmeña; 236 Nahulid-San Jose FMR NSAC 12 18-Nov-11 8 Northern Samar Catubig Catubig 2 ARC Nabulo; Nahulid; San Jose completed

237 Const of Brgy. Cagamutan-Bato-Bangon FMR with Bridge NSAC 6 27-Jan-11 8 Northern Samar Gamay Gamay ARC Cagamutan; Bato; Bangon completed

238 Concreting of Cagamutan-Bato-Bangon FMR NSAC 28 29-Nov-12 8 Northern Samar Gamay Gamay ARC Cagamutan; Bato; Bangon completed 239 Concreting of Bangon-G.M. Osias FMR NSAC 40 29-Apr-15 8 Northern Samar Gamay Gamay ARC Bangon; G.M. Osias completed

240 Concreting of Catigbian-Cabulaloan-Sibunot FMR NSAC 25 19-Oct-12 8 Northern Samar Laoang Laoang ARC Catigbian; Cabulaloan; Sibunot completed

241 Concreting of Catigbian-Cabulaloan-Sibunot FMR (Phase II) NSAC 35 18-Oct-13 8 Northern Samar Laoang Laoang ARC Catigbian; Cabulaloan; Sibunot completed

ongoing 242 Concreting of Matambag-Osmeña-Bangon FMR NSAC 30 22-Mar-13 8 Northern Samar Palapag Palapag ARC Matambag; Osmeña; Bangon

243 Concreting of San Juan to Entapatan FMR NSAC 27 16-Nov-12 8 Northern Samar San Isidro San Juan ARC San Juan completed

244 Improvement of Bonglas (Junction-Brgy. Proper) FMR NSAC 21 31-Jul-12 8 Northern Samar San Jose San Jose ARC Bonglas completed Bagong Sabang; Dao; 245 Concreting of Dao-Bagong Sabang-Tubigdanao FMR NSAC 32 07-Jun-13 8 Northern Samar San Jose San Jose ARC Tubigdanao completed Balud; Coroconog; 246 Const of Inilian-Galutan-Burac-Coroconog-Himabug-at FMR NSAC 17 20-Apr-12 8 Northern Samar San Roque San Roque ARC Balnasan completed

247 Const of Brgy. 3 to Brgy. 1 FMR NSAC 4 16-Mar-10 8 Eastern Samar Balangiga Balangiga ARC Brgy. 1; Brgy. 3 completed NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

248 Const of Brgy. San Miguel FMR NSAC 18 18-May-12 8 Eastern Samar Balangiga Balangiga ARC San Miguel ongoing Guinpoliran; Bangon; 249 Rehab and Const of Guinpoliran-Bangon-Cantubi FMR (Section 1) NSAC 16 30-Mar-12 8 Eastern Samar Balangkayan Balangkayan ARC Cantubi ongoing 250 Concreting of Jumalag-Magsaysay FMR (Section 2) NSAC 16 30-Mar-12 8 Eastern Samar Balangkayan Balangkayan ARC Jumalag; Magsaysay completed Brgy. 8 Poblacion; San 251 Rehab/Const of Barangay 8-San Isidro FMR NSAC 3 19-Nov-09 8 Eastern Samar Lawaan Lawaan ARC Isidro ongoing 252 Concreting of Barangay Taguite FMR NSAC 26 30-Oct-12 8 Eastern Samar Lawaan Lawaan ARC Taguite ongoing Construction with Spot Concreting of San Miguel-Babanikhon- Babanikhon; Macaanga; 253 Macaanga FMR NSAC 29 19-Dec-12 8 Eastern Samar Llorente Llorente ARC San Miguel ongoing

Concreting of San Pedro-Palactad FMR with 6.65 LM Flat Slab 254 Bridge NSAC 28 29-Nov-12 8 Eastern Samar Quinapondan ARC San Pedro; Rizal; Palactad completed Casilion; Tagbacan; 255 Rehab of Casilion-Tagbacan-Taclaon-Sta. Cruz FMR NSAC 6 27-Jan-11 8 Eastern Samar Salcedo Salcedo ARC Taclaon; Sta. Cruz ongoing Cagaut; Cantomoja;Camanga;Cara 256 Concreting of Cagaut-Cantomoja-Camanga-Carapdapan FMR NSAC 33 17-Jul-13 8 Eastern Samar Salcedo Salcedo ARC pdapan ongoing

257 Const of Casoroy-Layog FMR NSAC 3 19-Nov-09 8 Eastern Samar San Julian San Julian ARC Casoroy completed 258 Const of Agricultural Warehouse NSAC 13 19-Dec-11 8 Eastern Samar San Julian San Julian ARC Libas completed

259 Const of Panaw-nawan-Magti-aw FMR NSAC 15 01-Mar-12 8 Eastern Samar San Julian San Julian ARC Campidhan; Nena; Libas ongoing

260 Rehab of Sta. Cruz-Bangon FMR NSAC 5 12-Jul-10 8 Eastern Samar San Policarpo ESSP ARC Sta. Cruz; Bangon ongoing Lumatod; Danao; Del 261 Const of Lumatod-Danao FMR with 20 LM RCDG Bridge NSAC 6 27-Jan-11 8 Eastern Samar Taft Taft ARC Remedios ongoing Poblacion; Malobago; Rono; Tonga-Tonga; Lunang; Talahid; Costa 262 Const of Poblacion-Costa Rica II FMR NSAC 25 19-Oct-12 8 Western Samar Almagro Almagro Strategic ARC Rica completed

263 Const of Cogon-Cancaiyas-Villa Aurora FMR NSAC 15 01-Mar-12 8 Western Samar Basey Samar Settlement Project ARC Cogon; Cancaiyas, Villa Aurora completed Bacyaran; Bulao; 264 Const of Bacyaran-Bulao-Canbagtic-San Mauricio FMR NSAC 5 12-Jul-10 8 Western Samar Calbiga Calpinset ARC Canbagtic; San Mauricio completed 265 Concreting of Barobaybay-Pasigay FMR NSAC 23 14-Sep-12 8 Western Samar Calbiga SOWSEED ARC Cluster Barobaybay; Pasigay completed 266 Concreting of Brgy. 7-Tinago FMR NSAC 23 14-Sep-12 8 Western Samar Calbiga SOWSEED ARC Cluster Brgy. 7; Tinago completed 267 Concreting of Panayuran FMR NSAC 23 14-Sep-12 8 Western Samar Calbiga SOWSEED ARC Cluster Polangi; Panayuran completed Borong; Hubasan; Mahangcao; Macaalan; 268 Construction of Calbiga Upland Barangay PWS NSAC 30 22-Mar-13 8 Western Samar Calbiga SOWSEED ARC Cluster Panayuran ongoing Mabini; Mayabay; San 269 Const of Mabini-Mayahay-San Roque FMR NSAC 1 2-Sep-09 8 Western Samar Daram West Daram ARC Roque completed

270 Const of Poblacion 02-Talisay FMR NSAC 11 4-Nov-11 8 Western Samar Daram West Daram ARC Talisay; Poblacion 02 completed NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

Mabini; Ubo; Birawan; Astorga; Marupangdan; 271 Const of Mabini-Astorga-San Vicente-Bono-anan FMR NSAC 26 30-Oct-12 8 Western Samar Daram West Daram ARC San Vicente; Bono-anon completed 272 Concreting of Macaparican ARC FMR NSAC 20 05-Jul-12 8 Western Samar Jiabong Macaparican ARC Cantongtong completed Sta. Rita; Malobago; 273 Const of Sta. Rita FMR NSAC 15 01-Mar-12 8 Western Samar Marabut SOWSEED ARC Pinamitinan ongoing 274 Improv of Pagsangan-San Agustin FMR NSAC 2 16-Oct-09 8 Western Samar Pagsanghan Pagsangahan Strategic ARC Canlapwas; Villahermosa Occidental;completed Villahermosa Oriental; Pange; San Luis; Buenos Aires Pagsanghan ARC (Pagsanghan). Hinogacan; San Agustin; Gandara; Dapdap (Tarangnan) 275 Concreting of Pagsanghan-Caloloma FMR NSAC 21 31-Jul-12 8 Western Samar Pagsanghan Pagsanghan ARC Poblacion; Caloloma completed

Nabong; Loctob; 276 Const of Nabong-Loctob-Catigawan-Lawaan-Pahug FMR NSAC 3 19-Nov-09 8 Western Samar CALPINSET ARC Catigawan; Lawaan; Pahug ongoing

Quezon; San Isidro; Rawis; 277 Concreting of -Cantaguic FMR NSAC 30 22-Mar-13 8 Western Samar San Jorge San Jorge ARC Cantaguic ongoing

278 Const of Ilo-Balud Circumferential ARC FMR NSAC 24 27-Sep-12 8 Western Samar Sta. Margarita Balud-Ilo ARC Balud; Ilo ongoing Tulay; Camayse; Anibongon; Gumamela; Rosal; Bougainvilla; Santan; Bokinggan; 279 Spot Concreting of Poblacion-Tulay FMR NSAC 13 19-Dec-11 8 Western Samar Sta. Rita SOWSEED ARC Cluster Hinangutnan; Salvacion ongoing 280 Concreting of Poblacion-Hinangutdan FMR NSAC 27 16-Nov-12 8 Western Samar Sta. Rita SOWSEED ARC Cluster Poblacion; Hinangutdan ongoing

Dapdap; Talinga; 281 Rehab of Barangay Dapdap-Lahong FMR NSAC 2 16-Oct-09 8 Western Samar Tarangnan St. Francis ARC Binalayan; Lahong completed Balugo; Bahay; Pajo; Gallego; Balongaas; 282 Spot Concreting of Balugo-Imelda FMR NSAC 19 07-Jun-12 8 Western Samar Tarangnan St. Francis and Cambatutay ARC Canunghan; Imelda completed

Canmucat; Nagcaduha; 283 Const/Rehab of Villareal ARC FMR NSAC 4 16-Mar-10 8 Western Samar Villareal Villareal ARC Macopa; Conant completed

San Fernando; Malonoy; 284 Concreting of Villareal ARC FMR NSAC 16 30-Mar-12 8 Western Samar Villareal SOWSEED ARC Sto. Niño; Igot; Macopa ongoing 285 Construction of Nonoyan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Balaguian Kauswagan Expanded ARC completed 286 Construction of Mamad Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Balaguian Kauswagan Expanded ARC completed 287 Construction of Lumay Solar Dryer RSAC 8 6-Jul-12 9 Zamboanga del Norte Balaguian Kauswagan Expanded ARC completed 288 Construction of Poblacion Multi-Purpose Center RSAC 8 6-Jul-12 9 Zamboanga del Norte Balaguian Kauswagan Expanded ARC completed 289 Construction of Kauswagan Multi-Purpose Center RSAC 8 6-Jul-12 9 Zamboanga del Norte Balaguian Kauswagan Expanded ARC completed

Dapdap; Anastacio; Punta; Galas; Gulayan; Tumo; Sinaman; Bandera; 3 290 Rehabilitation of CIS NSAC 33 17-Jul-13 9 Zamboanga del Norte Dipolog City DCS Expanded ARC Olingan; Sta. Filomena completed NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

Construction of Barangay Buenavista One Unit-2 CL School 291 Building RSAC 9 27-Dec-12 9 Zamboanga del Norte Gutalac GUMBUEBAS Buenavista completed

292 Construction of Barangay Silang One Unit-2 CL School Building RSAC 9 27-Dec-12 9 Zamboanga del Norte Gutalac GUMBUEBAS Silang One completed 293 Construction of Barangay Map One Unit-2 CL School Building RSAC 9 27-Dec-12 9 Zamboanga del Norte Gutalac GUMBUEBAS Map One completed

294 Construction of Barangay Gutalac One Unit-2 CL School Building RSAC 9 27-Dec-12 9 Zamboanga del Norte Gutalac GUMBUEBAS Gutalac One completed 295 Construction of Barangay Upper Gutalac Day Care Center RSAC 10 28-Dec-12 9 Zamboanga del Norte Gutalac GUMBUEBAS Upper Gutalac completed 296 Construction of Barangay Bagong Silang Day Care Center RSAC 10 28-Dec-12 9 Zamboanga del Norte Gutalac GUMBUEBAS Bagong Silang completed 297 Concreting of Sitio Jiay-Sitio Sibulan Bgy. Balas FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Labason GBL ARC Balas ongoing

298 Construction of Upper Gabu PWS 2 RSAC 1 18-Jun-10 9 Zamboanga del Norte Labason GBL ARC completed 299 Construction of Upper Gabu Early Child Care Development Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed 300 Construction of Balas Early Child Care Development Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed 301 Construction of Lawigan Early Child Care Development Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed

302 Construction of Sitio Sawi Early Child Care Development Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed

303 Construction of Sitio Jaivy Early Child Care Development Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed Construction of Sitio Sibulan Early Child Care Development 304 Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed 305 Construction of Balas Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed 306 Construction of Sibulan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed 307 Construction of Lawigan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed 308 Construction of Lawigan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed 309 Construction of Balas Barangay Health Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed 310 Construction of Sibulan Barangay Health Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed 311 Construction of Lawigan Barangay Health Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed 312 Construction of Balas Multi-purpose Pavement RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason GBL ARC completed 313 Construction of Delusom Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Leon Postigo Triple MS ARC completed 314 Construction of Palandok Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Leon Postigo Triple MS ARC completed 315 Construction of Bogabongan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Leon Postigo Triple MS ARC completed 316 Construction of Mangop Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Leon Postigo Triple MS ARC completed 317 Construction of Sta. Maria Barangay Health Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Leon Postigo Triple MS ARC completed

318 Concreting of Lingatongan-Meses FMR NSAC 22 24-Aug-12 9 Zamboanga del Norte Manukan Manukan East ARC Lingatongan; Meses completed

319 Concreting of Gupot FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Manukan Manukan East ARC Gupot ongoing 320 Rehab with Concreting of Polayo-Denuyan FMR NSAC 19 07-Jun-12 9 Zamboanga del Norte Siayan Siayan West ARC Polayo completed 321 Rehab with 0.75 km Concreting of Paranglumba FMR NSAC 20 05-Jul-12 9 Zamboanga del Norte Siayan Siayan West ARC Paranglumba completed 322 Rehab with 2 km. Concreting of Sitio Bolanao-Litolet FMR NSAC 21 31-Jul-12 9 Zamboanga del Norte Siayan Siayan East ARC Litolet ongoing 323 Rehab with 0.7 km. Concreting of Moyo-Sitio Pase FMR NSAC 21 31-Jul-12 9 Zamboanga del Norte Siayan Siayan West ARC Moyo ongoing 324 Rehab with 0.9 km. Concreting of Gonayen-Sayaw FMR NSAC 21 31-Jul-12 9 Zamboanga del Norte Siayan Siayan East ARC Gonayen completed NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

325 Rehabilitation/Concreting of Junction Muñoz-Litolet FMR NSAC 32 07-Jun-13 9 Zamboanga del Norte Siayan Siayan East ARC Litolet completed

326 Rehabilitation/Concreting of Poblacion-Moyo FMR NSAC 33 17-Jul-13 9 Zamboanga del Norte Siayan Siayan West ARC Poblacion; Moyo ongoing 327 Concreting of Motibot-Sto. Rosario FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Sindangan MNSR ARC Sto. Rosario ongoing 328 Construction of Motibot Solar Dryer RSAC 3 16-Sep-11 9 Zamboanga del Norte Sindangan MNSR ARC completed 329 Construction of Nipaan Solar Dryer RSAC 8 6-Jul-12 9 Zamboanga del Norte Sindangan MNSR ARC completed 330 Construction of Sto. Rosario Solar Dryer RSAC 8 6-Jul-12 9 Zamboanga del Norte Sindangan MNSR ARC completed 331 Rehabilitation of Lituban CIS NSAC 34 06-Sep-13 9 Zamboanga del Norte Siocon Jolamipaman ARC completed

332 Concreting of JNR Pangian-Greenridge FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Siocon Jolamipaman ARC Pangian completed 333 Construction of Panabutan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Sirawai Panabutan Expanded ARC completed 334 Construction of Catuyan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Sirawai Panabutan Expanded ARC completed 335 Construction of Sipakit FMR RSAC 8 6-Jul-12 9 Zamboanga del Norte Sirawai Panabutan Expanded ARC completed 336 Upgrading/Rehab of Poblacion-New Dapitan FMR NSAC 24 27-Sep-12 9 Zamboanga del Norte Tampilisan Rubber Stump ARC Poblacion ongoing 337 Concreting of Poblacion-ZNAC FMR NSAC 27 16-Nov-12 9 Zamboanga del Norte Tampilisan Rubber Stump ARC ZNAC completed 338 Rehabilitation of Sagrada Familia CIS NSAC 31 26-Apr-13 9 Zamboanga del Sur Aurora TaGuMa ARC ongoing 339 Construction of Mahayahay Waterworks System RSAC 8 6-Jul-12 9 Zamboanga del Sur Aurora TaGuMa ARC completed 340 Construction of Legarda Uno Farmers Multi-purpose Center RSAC 8 6-Jul-12 9 Zamboanga del Sur Dinas LEGANGUIMI ARC Legarda Uno completed

341 Const of Maralag-Libertad FMR NSAC 3 19-Nov-09 9 Zamboanga del Sur Dumingag Mantilba ARC Maralag; Libertad completed

342 Construction of New Basak Multi-purpose Center with Solar Dryer RSAC 2 10-Nov-10 9 Zamboanga del Sur Dumingag Mantilba ARC completed

343 Construction of Maralag Multi-purpose Center with Solar Dryer RSAC 2 10-Nov-10 9 Zamboanga del Sur Dumingag Mantilba ARC Maralag completed

344 Construction of Libertad Multi-purpose Center with Solar Dryer RSAC 2 10-Nov-10 9 Zamboanga del Sur Dumingag Mantilba ARC Libertad completed

345 Construction of Manlabay Multi-purpose Center with Solar Dryer RSAC 2 10-Nov-10 9 Zamboanga del Sur Dumingag Mantilba ARC completed

346 Construction of Upper Timonan Multi-purpose Center with Solar DryerRSAC 2 10-Nov-10 9 Zamboanga del Sur Dumingag Mantilba ARC completed

347 Construction of Lower Timonan Multi-purpose Center with Solar DryerRSAC 2 10-Nov-10 9 Zamboanga del Sur Dumingag Mantilba ARC completed

348 Rehab of Nopulan-Bogo-Calabat FMR NSAC 2 16-Oct-09 9 Zamboanga del Sur Josefina Josefina Highland Cluster ARC Nopulan; Bogo Calabat completed

349 Rehab of Brgy. Moradje-Ebarle FMR NSAC 18 18-May-12 9 Zamboanga del Sur Josefina Josefina Highland Cluster ARC Moradje; Ebarle completed 350 Rehab/Concreting of Brgy. Moradje-Tagaytay-Dawa FMR NSAC 24 27-Sep-12 9 Zamboanga del Sur Josefina Josefina Highland Cluster ARC Dawa; Moradje; Tagaytay completed 351 Construction of Josefina Cluster ARC Tribal Center RSAC 9 9-Jul-12 9 Zamboanga del Sur Josefina Josefina Highland Cluster ARC completed 352 Rehabilitation of Guipos CIS NSAC 34 06-Sep-13 9 Zamboanga del Sur Guipos Balongating Expanded ARC Balangating, Poblacion ongoing

353 Const of Junction Poblacion Kumalarang-Bualan FMR NSAC 11 4-Nov-11 9 Zamboanga del Sur Kumalarang Baganian Peninsula ARC Cluster Poblacion; Bualan completed 354 Construction of 1 Unit Tribal Hall Building RSAC 9 4-Feb-13 9 Zamboanga del Sur Kumalarang Baganian Peninsula ARC Cluster completed NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

355 Construction of Dipaya Day Center RSAC 8 6-Jul-12 9 Zamboanga del Sur Labangan Labangan Cluster C ARC completed 356 Construction of Bokong Tribal Center RSAC 9 9-Jul-12 9 Zamboanga del Sur Labangan Labangan Cluster C ARC completed 357 Construction of Binayan Tribal Center RSAC 9 9-Jul-12 9 Zamboanga del Sur Labangan Labangan Cluster C ARC completed Pingalay; Maruing; Pantad; Const/Improv of Bualan-Maruing-Pampang-Poblacion Lapuyan Pampang; Poblacion; 358 FMR NSAC 12 18-Nov-11 9 Zamboanga del Sur Lapuyan Baganian Peninsula ARC Cluster Tipasan completed Tumapic; San Jose; 359 Const of Balamban-San Jose-Tumapic FMR with RCDG Bridge NSAC 2 16-Oct-09 9 Zamboanga del Sur Mahayag Balamban Expanded ARC Balamban completed Concreting of Bgy. Lower Salug Dako-Balamban-San Jose DCM Balamban; DCM; Lower 360 FMR NSAC 24 27-Sep-12 9 Zamboanga del Sur Mahayag Balamban Expanded ARC Salug; San Jose completed 361 Construction-Rehabilitation-Concreting of Bgy. DCM FMR NSAC 24 27-Sep-12 9 Zamboanga del Sur Mahayag Balamban Expanded ARC DCM ongoing 362 Const of Bgy. Lower Sto. Niño FMR NSAC 26 30-Oct-12 9 Zamboanga del Sur Mahayag Balamban Expanded ARC Lower Sto. Niño ongoing

363 Const of Tipasan-Tulapok-Poblacion FMR NSAC 11 4-Nov-11 9 Zamboanga del Sur Margosatubig Baganian Peninsula ARC Cluster Tulapok; Tiguian; Poblacion completed

364 Const of Brgy. Buloron-Dumalinao FMR NSAC 16 30-Mar-12 9 Zamboanga del Sur Midsalip Midsalip ARC Cluster Buloron; Dumalinao completed

365 Concreting of Buloron-Lumponid FMR NSAC 17 20-Apr-12 9 Zamboanga del Sur Midsalip Midsalip ARC Cluster Buloron; Lumponid completed 366 Construction of Midsalip Cluster ARC Tribal Center RSAC 9 9-Jul-12 9 Zamboanga del Sur Midsalip Midsalip ARC Cluster completed

367 Const of Culo FMR NSAC 18 18-May-12 9 Zamboanga del Sur Molave Culo ARC Culo completed

368 Concreting of Purok Jupiter (Basay)-Purok Venus FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Molave Rizal ARC Rizal completed

369 Concreting of Purok Ferry-Purok Happy Valley FMR NSAC 21 31-Jul-12 9 Zamboanga del Sur Molave Miligan ARC Miligan completed 370 Concreting of Limonan-Kabogkabog FMR NSAC 33 17-Jul-13 9 Zamboanga del Sur San Miguel San Miguel Cluster ARC Limonan; Kabogkabog ongoing 371 Construction of San Miguel Cluster ARC Tribal Center RSAC 9 9-Jul-12 9 Zamboanga del Sur San Miguel San Miguel Cluster ARC completed

372 Concreting of Tanducan-Tambunan FMR NSAC 18 18-May-12 9 Zamboanga del Sur Tabina Tabina Cluster ARC Poblacion; Malim ongoing

373 Rehab of Gabunon-Bag-ong Tabugon FMR NSAC 5 12-Jul-10 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster B ARC Gabunon;Tuluan; Libato; Bag-ong Tabugoncompleted

374 Concreting of Lower Lodiong-Limamaan FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster B ARC Lower Lodiong; Limamaan completed

375 Concreting of Junction Limamaan-Upper Lodiong FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster B ARC Upper Lodiong; Limamaan; Tuluan completed 376 Rehab w/ Spot Concreting of Limamaan FMR NSAC 22 24-Aug-12 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster B ARC Limamaan completed

377 Construction of Tuluan Barangay Health Station RSAC 4 16-Mar-12 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster ARC Tuluan completed 378 Construction of Limamaan Multi-purpose Center RSAC 5 18-Apr-12 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster ARC Limamaan completed

379 Rehab/Improv of Guinlin-Limas FMR NSAC 1 2-Sep-09 9 Zamboanga del Sur Tigbao BegCaLLi ARC Guinlin; Limas completed 380 Const of BegCaLLi ARC Health Station NSAC 2 16-Oct-09 9 Zamboanga del Sur Tigbao BegCaLLi ARC Begong completed NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

381 Concreting of Begong-Limas FMR NSAC 25 19-Oct-12 9 Zamboanga del Sur Tigbao BegCaLLi ARC Begong; Limas ongoing Const with 1.248 Concreting of Alindahaw-Panduma Sr.-Camanga Alindahaw; Panduma Sr.; 382 FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Tukuran LUCATT-LBP ARC Camanga completed 383 Construction of Upper Bayao Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Sur Tukuran LUCATT-LBP ARC completed 384 Construction of Baclay Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Sur Tukuran LUCATT-LBP ARC completed 385 Construction of Brgy. Camanga Health Station RSAC 8 6-Jul-12 9 Zamboanga del Sur Tukuran LUCATT-LBP ARC completed 386 Construction of Luy-a 1 CL Elem. School Building RSAC 8 6-Jul-12 9 Zamboanga del Sur Tukuran LUCATT-LBP ARC completed 387 Construction of Tabuan 1 CL Elem. School Building RSAC 8 6-Jul-12 9 Zamboanga del Sur Tukuran LUCATT-LBP ARC completed 388 Construction of Tinutungan 1 CL Elem. School Building RSAC 8 6-Jul-12 9 Zamboanga del Sur Tukuran LUCATT-LBP ARC Tinutungan completed 389 Const of Maasin & Tiayon PWS Level II NSAC 25 19-Oct-12 9 Zamboanga Sibugay Ipil SWIZS ARC Maasin; Tiayon completed 390 Construction of Goodyear Day Care Center RSAC 3 16-Sep-11 9 Zamboanga Sibugay Goodyear ARC Goodyear completed

391 Concreting of Poblacion-Ligaya FMR NSAC 25 19-Oct-12 9 Zamboanga Sibugay Mabuhay Placeres ARC Ligaya; Poblacion completed 392 Const of Sitio Tuburan-Malinao FMR NSAC 25 19-Oct-12 9 Zamboanga Sibugay Mabuhay Placeres ARC Malinao; Poblacion ongoing 393 Concreting of Poblacion-Malinao FMR NSAC 37 18-Feb-14 9 Zamboanga Sibugay Mabuhay Placeres ARC Poblacion; Malinao completed 394 Rehab of Tambanan-Sulo FMR NSAC 18 18-May-12 9 Zamboanga Sibugay Naga Tambanan and Sulo ARC Tambanan; Sulo completed Balungisan; La Fortuna; Calape; Kulasian; Bulawan; 395 Rehab with Spot Concreting of Balungisan-Guiwan FMR NSAC 6 27-Jan-11 9 Zamboanga Sibugay Payao Don Alfonso ARC Guiwan completed Balungisan; Upper 396 Concreting of Balungisan-Upper Sumilong FMR NSAC 35 18-Oct-13 9 Zamboanga Sibugay Payao Don Alfonso ARC Sumilong completed 397 Rehabilitation of Bulawan CIS NSAC 32 07-Jun-13 9 Zamboanga Sibugay Payao Don Alfonso ARC Bulawan; Guiwan completed 398 Const of Flood Control Protection Dike cum FMR NSAC 21 31-Jul-12 9 Zamboanga Sibugay Siay Lower Sibuguey ARC Lagting ongoing 399 Rehab of Culasian-Supit FMR NSAC 1 2-Sep-09 9 Zamboanga Sibugay Titay Supit ARC Culasian; Supit completed 400 Rehab w/ Spot Concreting of Kitabog-Mabini FMR NSAC 20 05-Jul-12 9 Zamboanga Sibugay Titay Titay Valley ARC Kitabog; Mabini completed 401 Concreting of Brgy. Libertad FMR NSAC 19 07-Jun-12 9 Zamboanga Sibugay Tungawan TRI-People ARC Libertad ongoing 402 Concreting of Tumahubong ARC FMR NSAC 16 30-Mar-12 14 Basilan Sumisip TARBIDC ARC Tumahubong ongoing 403 Const of Tumahobong PWS LII NSAC 18 18-May-12 14 Basilan Sumisip TARBIDC ARC Tumahubong ongoing

404 Rehab of Tumahubong ARC FMR NSAC 21 31-Jul-12 14 Basilan Sumisip TARBIDC ARC Tumahubong ongoing

Tipo-Tipo Proper; Magkawa; Limbu-pas; 405 Concreting of TARBADECO ARC Road Network NSAC 18 18-May-12 14 Basilan Tipo-Tipo TARBADECO ARC Guinanta completed 406 Concreting of Phil-Am-Buhe Pahu FMR NSAC 18 18-May-12 14 Basilan Ungkaya Pukan TIPARBECO ARC Cabangalan; Buhe Pahu completed Concreting of Brgy. Dado Poblacion-Sitio Matampay Bagoaingud 407 FMR NSAC 37 18-Feb-14 14 Lanao del Sur Dado ARC Dado completed 408 Construction of Dado ARC PWS LII NSAC 37 18-Feb-14 14 Lanao del Sur Balindong Dado ARC Dado completed 409 Construction of Health Center Building (Brgy. Polayagan) NSAC 37 18-Feb-14 14 Lanao del Sur Bubong Bubong ARC Polayagan ongoing Construction of Multi-Purpose Building with Solar Dryer (Brgy. 410 Salipongan) NSAC 37 18-Feb-14 14 Lanao del Sur Bubong Bubong ARC Salipongan ongoing 411 Concreting of Sumogot FMR NSAC 18 18-May-12 14 Lanao del Sur Bumbaran Bumbaran ARC Sumogot ongoing

412 Const of Barit-Taliogon-Tabuan FMR NSAC 4 16-Mar-10 14 Lanao del Sur Ganassi Taliogon ARC Taliogon; Tabuan completed NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

Campongaraya; Taganonok;Taliogon; 413 Concreting and Rehab of Taganonok-Taliogon-Paraaba FMR NSAC 18 18-May-12 14 Lanao del Sur Ganassi Taliogon ARC Paraaba ongoing Masolun; Taganonok; 414 Construction of Masolun-Taganonok-Taliogon FMR NSAC 35 18-Oct-13 14 Lanao del Sur Ganassi Taliogon ARC Taliogon ongoing Masolun; Taganonok; 415 Construction of Campongraya PWS - Level II NSAC 35 18-Oct-13 14 Lanao del Sur Ganassi Taliogon ARC Taliogon ongoing 416 Construction of Barit PWS NSAC 36 06-Dec-13 14 Lanao del Sur Ganassi Taliogon ARC Barit ongoing Campongaraya; Barorao; 417 Concreting of Campongaraya-Barorao-Panggawalupa-Barit FMR NSAC 36 06-Dec-13 14 Lanao del Sur Ganassi Taliogon ARC Panggawalupa; Barit ongoing Construction of Panggawalupa Pre-Stress Concrete Girder 418 (PSCG) Bridge NSAC 36 06-Dec-13 14 Lanao del Sur Ganassi Taliogon ARC Panggawalupa ongoing

419 Construction of Barangay Health Center @ Brgy. Campongraya RSAC 3 18-Oct-12 14 Lanao del Sur Ganassi Campongraya ongoing 420 Construction of Multi-Purpose Building @ Brgy. Barorao RSAC 3 18-Oct-12 14 Lanao del Sur Ganassi Barorao ongoing 421 Construction of Multi-Purpose Building @ Brgy. Taliogon RSAC 3 18-Oct-12 14 Lanao del Sur Ganassi Taliogon ongoing 422 Construction of Warehouse Solar Dryer @ Brgy. Barit RSAC 3 18-Oct-12 14 Lanao del Sur Ganassi Barit ongoing Pindolonan; Pantao; 423 Concreting of Pindolonan-Pantao-Macadar FMR NSAC 35 18-Oct-13 14 Lanao del Sur Pindolonan ARC Macadar ongoing 424 Concreting of Sultan Barudi Bansil FMR NSAC 35 18-Oct-13 14 Lanao del Sur Kapatagan SBB ARC Kapatagan; Bongabon ongoing Construction of Multi-Purpose Building with Solar Dryer (Proper 425 Kapatagan) NSAC 37 18-Feb-14 14 Lanao del Sur Kapatagan SBB ARC Proper Kapatagan ongoing

426 Construction of Multi-Purpose Building with Solar Dryer (Daguan) NSAC 37 18-Feb-14 14 Lanao del Sur Kapatagan SBB ARC Daguan ongoing

427 Concreting of Bangon-Lumbac & Dimapok FMR NSAC 36 06-Dec-13 14 Lanao del Sur Lumbaca Unayan Dilausan ARC Bangon; Lumbac; Dimapok ongoing Pitatanglan; Wago; 428 Concreting of Pitatanglan-Wago Kabasaran & Wago-Miniros FMR NSAC 36 06-Dec-13 14 Lanao del Sur Cabasaran ARC Kabasaran; Miniros ongoing Bandaraingud; Loway Inodaran 429 Concreting of Camalig Bandaraingud-Loway Inodaran FMR NSAC 21 31-Jul-12 14 Lanao del Sur Marantao Bubong Camalig ARC Bubong Dimunda; Pantao; ongoing Ragayan; Bansayan; 430 Concreting and Rehab of Bubong-Ragayan-Gadongan FMR NSAC 18 18-May-12 14 Lanao del Sur Ragayan ARC Gadongan ongoing

431 Construction of Multi-Purpose Building with Solar Dryer (Lumbac) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong ARC Lumbac ongoing Construction of Multi-Purpose Building with Solar Dryer 432 (Bacayawan) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Bacayawan ongoing Construction of Multi-Purpose Building with Solar Dryer 433 (Tagoranao) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Tagoranao ongoing Construction of Multi-Purpose Building with Solar Dryer 434 (Pagalongan) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Pagalongan ongoing Construction of Multi-Purpose Building with Solar Dryer 435 (Dinganun) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Dinganum ongoing NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

436 Construction of Multi-Purpose Building with Solar Dryer (Malalis) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Malalis ongoing Construction of Multi-Purpose Building with Solar Dryer (Buta- 437 Sumalindao) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Buta-Sumalindao ongoing

Dinganun; Pagalongan; 438 Concreting of Dinganun-Pagalongan-Bacayawan-Lumbac FMR NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Bacayawan; Lumbac ongoing

439 Concreting of Kinggan-Tagoloan Poblacion FMR NSAC 13 19-Dec-11 14 Lanao del Sur Tagoloan Malinao-Cadayonan ARC Malinao; Cadayonan ongoing

Buadi Diamangga; Buadi 440 Concreting of Buadi Diamangga-Buadi Ongcalo FMR (Section 1) NSAC 35 18-Oct-13 14 Lanao del Sur Taraka Sigayan ARC Ongcalo; Cadayonan completed Buadi Diamangga; Buadi 441 Concreting of Cadayonan FMR (Section 2) NSAC 35 18-Oct-13 14 Lanao del Sur Taraka Sigayan ARC Ongcalo; Cadayonan ongoing 442 Construction of MPB (Bgy. Buadi Amunud) NSAC 36 06-Dec-13 14 Lanao del Sur Taraka Sigayan ARC Buadi Amunod completed

443 Construction of MPB (Bgy. Sundig) NSAC 36 06-Dec-13 14 Lanao del Sur Taraka Sigayan ARC Sundig completed

444 Construction of MPB (Bgy. Moriatao Luksadato) NSAC 36 06-Dec-13 14 Lanao del Sur Taraka Sigayan ARC Moriato Luksadato ongoing 445 Taraka Pump Irrigation Communal Irrigation Project NSAC 36 06-Dec-13 14 Lanao del Sur Taraka Sigayan ARC ongoing 446 Concreting of 8 km Dinganen-Nuyo FMR I NSAC 35 18-Oct-13 14 Maguindanao Buldon Buldon ARC Dinganen-Nuyo ongoing 447 Concreting of Tamborong-Bunawan FMR NSAC 13 19-Dec-11 14 Maguindanao Datu Paglas Bunawan ARC Tamborong; Bunawan completed Ganta; ; 448 Const of Ganta-Gambar FMR NSAC 14 19-Jan-12 14 Maguindanao Kabuntalan Matilak ARC Gambar completed 449 Concreting of Langkong-Bayanga Norte Road NSAC 21 31-Jul-12 14 Maguindanao Matanog Langkong ARC Langkong; Bayanga Norte ongoing 450 Concreting of Pasil-Langpas Farm to Market Road NSAC 39 26-Aug-14 14 Sulu Pasil ARC Pasil; Langpas ongoing 451 Concreting of Kuppong-Kagay Farm to Market Road NSAC 39 26-Aug-14 14 Sulu Indanan Pasil ARC Kuppong;Tubig Samin; Kaga Matatal;y ongoing Datag Limbun; Gulangan; 452 Concreting of Patao Junction-Ipil FMR NSAC 13 19-Dec-11 14 Sulu Maimbung Maimbung ARC TubigKandang; Samin; Patao; Matatal; Ipil completed Concreting of Pantao Junction-Kandang Gulangan-Ratag Limbun Datag Limbun; Gulangan; 453 FMR NSAC 13 19-Dec-11 14 Sulu Maimbung Maimbung ARC Kandang; Patao; Ipil completed Tubig Samin; Matatal; Datag Limbun; Gulangan; 454 Concreting of Tubig Samin Junction-Tambuan FMR NSAC 13 19-Dec-11 14 Sulu Maimbung Maimbung ARC Kandang; Patao; Ipil completed

Kan-dayuk; Kan-ukul; 455 Rehab of Su'uh-Kan-dayuk-Kan-ukul FMR NSAC 7 30-Mar-11 14 Sulu Panamao Sultan Jamalul Kiram ARC Su'uh completed

Parian Dakula; Lahi; 456 Concreting of Parian-Dakula-Lahi-Malanta FMR NSAC 13 19-Dec-11 14 Sulu Pandami Pandami ARC Malanta ongoing Buan; Ratag; Siowing; 457 Concreting of Buan, Ratag, Siowing Sipanding and Duggo FMR NSAC 21 31-Jul-12 14 Sulu Siasi Ratag-Gantaan ARC Sipanding; Duggo ongoing 458 Concreting of Barangay Kanmindus - Tando Bato FMR NSAC 37 18-Feb-14 14 Sulu Luuk Tando Bato ARC Kanmindus, Tando Bato ongoing 459 Concreting of Bgy. Tando Bato FMR NSAC 37 18-Feb-14 14 Sulu Luuk Tando Bato ARC Tando Bato ongoing NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE REGION

460 Concreting of Kahawa - Tampakan FMR NSAC 37 18-Feb-14 14 Sulu ongoing 461 Concreting of Tandubanak ARC FMR (Section 1) NSAC 14 19-Jan-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak ongoing 462 Concreting of Tandubanak ARC FMR (Section 2) NSAC 14 19-Jan-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak ongoing 463 Concreting of Tandubanak ARC FMR (Section 3) NSAC 14 19-Jan-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak ongoing 464 Concreting of Tongehat ARC FMR NSAC 14 19-Jan-12 14 Tawi-Tawi Sibutu Ungus-Ungus-Tongehat ARC Tongehat ongoing Construction of 3-Unit Classroom School Building (Brgy. Tawi-Tawi Sibutu 465 Tandubanak) RSAC 2 24-May-12 14 Tandubanak ARC Tandubanak completed Construction of 3-Unit Classroom School Building MSU-CHS Tawi-Tawi Sibutu 466 (Brgy. Ungus-Ungus) RSAC 2 24-May-12 14 Ungus Ungus Tongehat ARC Ungus-Ungus completed Construction of 3-Unit Classroom School Building (Brgy. Taungoh) Tawi-Tawi Sibutu 467 RSAC 2 24-May-12 14 Tandubanak ARC Taungoh completed Construction of 3-Unit Classroom School Building (Brgy. Tawi-Tawi Sibutu 468 Tongehat) RSAC 2 24-May-12 14 Ungus Ungus Tongehat ARC Tongehat completed Construction of 3-Unit Classroom School Building (Brgy. Tawi-Tawi Sibutu 469 Tongsibalo) RSAC 2 24-May-12 14 Ungus Ungus Tongehat ARC Tongsibalo completed Construction of 3-Unit Classroom School Building (Brgy. Ungus- Tawi-Tawi Sibutu 470 Ungus) RSAC 2 24-May-12 14 Ungus Ungus Tongehat ARC Ungus-Ungus completed 471 Construction of Barangay Ungus-Ungus Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Ungus-Ungus completed 472 Construction of Barangay Tongsibalo Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Tongsibalo completed 473 Construction of Barangay Tongehat Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Tongehat completed 474 Construction of Barangay Taungoh Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Taungoh completed 475 Construction of Barangay Tandubanak Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak completed

475 DAR-ADB Agrarian Reform Communities Project II List of Subprojects Issued with ECC As of December 2017 STATUS OF LGU COMPLIANCE WITH ESS REQUIREMENTS ENVIRONMENTAL SAFEGUARDS NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE ECC/CNC

REGION EMMP IEE APPLICATION ECC/CNC

completed 1 Construction/Rehabilitation of Tagpit-Titibawan FMR NSAC 31 26-Apr-13 4-B Palawan Aborlan Iraan-Isaub ARC Isaub; San Juan CNC/ECC 09-Jan-13 ECC 24-Jan-14 PP 2 Const of Sanghiran-Campo-Agpudlos Proper FMR NSAC 9 25-Aug-11 4-B Romblon San Andres Agpudlos ARC Agpudlos CNC/ECC 28-Jun-11 ECC 16-Dec-11 PP completed 3 Rehab of Palate FMR NSAC 9 25-Aug-11 4-B Romblon Sta. Fe Magsaysay ARC Magsaysay ECC 11-Mar-11 PP completed 4 Concreting of Sitio Submakin FMR NSAC 19 07-Jun-12 5 Camarines Norte Paracale Batobalani ARC Batobalani CNC 16-Jan-12 ECC 04-Jul-12 P 5 Const of Sitio Potot FMR NSAC 19 07-Jun-12 5 Camarines Norte Paracale Batobalani ARC Batobalani CNC 16-Jan-12 ECC 04-Jul-12 P completed 6 Const of San Isidro-Sitio Too FMR NSAC 13 19-Dec-11 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Isidro CNC/ECC 09-Nov-11 ECC 04-Jul-12 completed

7 Const of Cabugao FMR NSAC 5 12-Jul-10 5 Camarines Sur Milaor Milaor ARC Cabugao ECC 16-Feb-10 PP 8 Concreting of Tinawagan-Coyaoyao FMR NSAC 27 16-Nov-12 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC Tinawagan; Coyaoyao CNC/ECC 08-Dec-11 ECC 06-Feb-15 9 Concreting of Tinawagan-Barobaroti-Caraycayon FMR NSAC 27 16-Nov-12 5 Camarines Sur Tigaon Tinawagan-Coyaoyao ARC Tinawagan; Barobaroti; Caraycayon CNC/ECC 08-Dec-11 ECC 06-Feb-15 10 Concreting/Rehabilitation of Junction Tapacon-Inamyugan-Agbao-GuinhulaganNSAC FMR 37 w/ Bridge 18-Feb-14 6 Iloilo Bingawan GUINTAPAGIN ARC Tapacon; Agba-o; Guinhulacan; InamyuganCNC/ECC 16-Aug-13 ECC 26-Dec-16 P 11 Concreting of JNR-Agsirab-Bagongbong-Sitio Agdalusan FMR NSAC 35 18-Oct-13 6 Iloilo Lambunao AGSIBAGO ARC Agsirab; Bagongbong CNC 26-Nov-13 ECC 24-Jul-16 P completed 12 Concreting of San Andres – San Florentino FMR with Bridge NSAC 37 18-Feb-14 6 Iloilo San Rafael San Andres-San Florentino ARC San Andres; San Florentino CNC/ECC 27-Mar-14 ECC 08-Apr-15 P

13 Const of Salvacion-Langit FMR NSAC 4 16-Mar-10 8 Leyte Alangalang Alangalang 1 ARC Salvacion; Langit CNC/ECC 12-Nov-09 ECC 03-Mar-10 P completed 14 Rehabilitation of Tabunok CIS NSAC 33 17-Jul-13 8 Leyte Hilongos Hilongos ARC Tabunok CNC/ECC 11-Jul-13 ECC 11-Nov-14 PP completed 15 Rehabilitation of Tagbawto CIS NSAC 33 17-Jul-13 8 Leyte Hilongos Hilongos ARC Tagbawto CNC/ECC 11-Jul-13 ECC 11-Nov-14 PP completed

16 Construction of Capirawan-Gacao-Canhidoc-Arado FMR NSAC 33 17-Jul-13 8 Leyte Palo Palo 2 ARC Capirawan; Canhidoc; Gacao; Arado ECC 17-Apr-13

17 Concreting of San Juan to Entapatan FMR NSAC 27 16-Nov-12 8 Northern Samar San Isidro San Juan ARC San Juan CNC 13-Mar-12 ECC 02-Aug-16 PP completed 18 Concreting of Dao-Bagong Sabang-Tubigdanao FMR NSAC 32 07-Jun-13 8 Northern Samar San Jose San Jose ARC Bagong Sabang; Dao; Tubigdanao CNC 13-Mar-12 ECC 06-Nov-14 PP completed

19 Const of Inilian-Galutan-Burac-Coroconog-Himabug-at FMR NSAC 17 20-Apr-12 8 Northern Samar San Roque San Roque ARC Balud; Coroconog; Balnasan ECC 02-Jan-12 ECC 29-Jun-12 PP completed

20 Const of Brgy. 3 to Brgy. 1 FMR NSAC 4 16-Mar-10 8 Eastern Samar Balangiga Balangiga ARC Brgy. 1; Brgy. 3 ECC 04-Oct-06 PP completed

21 Rehab/Const of Barangay 8-San Isidro FMR NSAC 3 19-Nov-09 8 Eastern Samar Lawaan Lawaan ARC Brgy. 8 Poblacion; San Isidro ECC 07-Apr-10 PP 22 Construction with Spot Concreting of San Miguel-Babanikhon-Macaanga FMRNSAC29 19-Dec-12 8 Eastern Samar Llorente Llorente ARC Babanikhon; Macaanga; San Miguel CNC 06-Sep-12 ECC 03-Dec-14

23 Const of Poblacion-Costa Rica II FMR NSAC 25 19-Oct-12 8 Western Samar Almagro Almagro Strategic ARC Poblacion; Malobago; Rono; Tonga-Tonga;ECC Lunang; Talahid; 01-Aug-12 Costa Rica ECC 22-Aug-13 PP completed

24 Const of Cogon-Cancaiyas-Villa Aurora FMR NSAC 15 01-Mar-12 8 Western Samar Basey Samar Settlement Project ARC Cogon; Cancaiyas, Villa Aurora CNC 09-Nov-11 ECC 31-Jan-12 PP completed

25 Const of Bacyaran-Bulao-Canbagtic-San Mauricio FMR NSAC 5 12-Jul-10 8 Western Samar Calbiga Calpinset ARC Bacyaran; Bulao; Canbagtic; San Mauricio ECC 24-Feb-10 PP completed STATUS OF LGU COMPLIANCE WITH ESS REQUIREMENTS ENVIRONMENTAL SAFEGUARDS NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE ECC/CNC

REGION EMMP IEE APPLICATION ECC/CNC

26 Const of Mabini-Mayahay-San Roque FMR NSAC 1 2-Sep-09 8 Western Samar Daram West Daram ARC Mabini; Mayabay; San Roque ECC 02-Oct-09 PP completed

27 Const of Poblacion 02-Talisay FMR NSAC 11 4-Nov-11 8 Western Samar Daram West Daram ARC Talisay; Poblacion 02 ECC 07-Oct-11 ECC 25-Nov-11 PP completed

28 Const of Mabini-Astorga-San Vicente-Bono-anan FMR NSAC 26 30-Oct-12 8 Western Samar Daram West Daram ARC Mabini; Ubo; Birawan; Astorga; Marupangdan;CNC/ECC San Vicente;17-Oct-12 Bono-anon ECC 31-Oct-12 P completed

29 Const of Sta. Rita FMR NSAC 15 01-Mar-12 8 Western Samar Marabut SOWSEED ARC Sta. Rita; Malobago; Pinamitinan ECC 08-Dec-11 ECC 29-Dec-11 PP

30 Const of Nabong-Loctob-Catigawan-Lawaan-Pahug FMR NSAC 3 19-Nov-09 8 Western Samar Pinabacdao CALPINSET ARC Nabong; Loctob; Catigawan; Lawaan; Pahug ECC 27-Oct-09 P

31 Const of Ilo-Balud Circumferential ARC FMR NSAC 24 27-Sep-12 8 Western Samar Sta. Margarita Balud-Ilo ARC Balud; Ilo ECC/CNC 18-Jul-12 ECC 24-Apr-13 PP 3 32 Rehabilitation of Dipolog CIS NSAC 33 17-Jul-13 9 Zamboanga del Norte Dipolog City DCS Expanded ARC Dapdap; Anastacio; Punta; Galas; Gulayan;CNC/ECC Tumo; Sinaman; 10-Jul-13 Bandera; ECC Olingan; Sta. Filomena PP completed 33 Construction of Barangay Buenavista One Unit-2 CL School Building RSAC 9 27-Dec-12 9 Zamboanga del Norte Gutalac GUMBUEBAS Buenavista completed 34 Concreting of Sitio Jiay-Sitio Sibulan Bgy. Balas FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Labason GBL ARC Balas CNC 14-Aug-12 ECC 10-Jul-14

35 Concreting of Lingatongan-Meses FMR NSAC 22 24-Aug-12 9 Zamboanga del Norte Manukan Manukan East ARC Lingatongan; Meses CNC 12-Jul-12 ECC 13-Jul-12 PP completed

36 Concreting of Gupot FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Manukan Manukan East ARC Gupot ECC 11-Dec-13 ECC 20-Mar-14 PP

37 Rehabilitation/Concreting of Junction Muñoz-Litolet FMR NSAC 32 07-Jun-13 9 Zamboanga del Norte Siayan Siayan East ARC Litolet CNC no date ECC 23-Apr-15 completed

38 Rehabilitation/Concreting of Poblacion-Moyo FMR NSAC 33 17-Jul-13 9 Zamboanga del Norte Siayan Siayan West ARC Poblacion; Moyo CNC no date ECC 23-Apr-15 39 Rehabilitation of Lituban CIS NSAC 34 06-Sep-13 9 Zamboanga del Norte Siocon Jolamipaman ARC ECC 07-Dec-16 P completed

40 Concreting of JNR Pangian-Greenridge FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Siocon Jolamipaman ARC Pangian ECC 25-May-16 P completed

41 Rehab of Nopulan-Bogo-Calabat FMR NSAC 2 16-Oct-09 9 Zamboanga del Sur Josefina Josefina Highland Cluster ARC Nopulan; Bogo Calabat CNC 04-Sep-09 ECC 08-Jul-10 PP completed

42 Rehab of Brgy. Moradje-Ebarle FMR NSAC 18 18-May-12 9 Zamboanga del Sur Josefina Josefina Highland Cluster ARC Moradje; Ebarle CNC/ECC 10-May-12 ECC 14-Feb-17 PP completed

43 Const of Junction Poblacion Kumalarang-Bualan FMR NSAC 11 4-Nov-11 9 Zamboanga del Sur Kumalarang Baganian Peninsula ARC Cluster Poblacion; Bualan CNC 01-Sep-11 ECC 09-Jan-11 PP completed

44 Const/Improv of Bualan-Maruing-Pampang-Poblacion Lapuyan FMR NSAC 12 18-Nov-11 9 Zamboanga del Sur Lapuyan Baganian Peninsula ARC Cluster Pingalay; Maruing; Pantad; Pampang; Poblacion;ECC Tipasan 14-Jun-11 ECC 21-Feb-12 PP completed

45 Const of Balamban-San Jose-Tumapic FMR with RCDG Bridge NSAC 2 16-Oct-09 9 Zamboanga del Sur Mahayag Balamban Expanded ARC Tumapic; San Jose; Balamban ECC 29-Sep-09 ECC 26-Mar-10 PP completed

46 Concreting of Bgy. Lower Salug Dako-Balamban-San Jose DCM FMR NSAC 24 27-Sep-12 9 Zamboanga del Sur Mahayag Balamban Expanded ARC Balamban; DCM; Lower Salug; San JoseCNC/ECC 07-May-12 ECC 06-Jan-14 PP completed 47 Construction-Rehabilitation-Concreting of Bgy. DCM FMR NSAC 24 27-Sep-12 9 Zamboanga del Sur Mahayag Balamban Expanded ARC DCM CNC/ECC 07-May-12 ECC 06-Jan-14 P 48 Const of Bgy. Lower Sto. Niño FMR NSAC 26 30-Oct-12 9 Zamboanga del Sur Mahayag Balamban Expanded ARC Lower Sto. Niño CNC/ECC 07-May-12 ECC 06-Jan-14 P

49 Const of Tipasan-Tulapok-Poblacion FMR NSAC 11 4-Nov-11 9 Zamboanga del Sur Margosatubig Baganian Peninsula ARC Cluster Tulapok; Tiguian; Poblacion ECC 23-Jun-11 ECC 05-Mar-12 PP completed STATUS OF LGU COMPLIANCE WITH ESS REQUIREMENTS ENVIRONMENTAL SAFEGUARDS NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE ECC/CNC

REGION EMMP IEE APPLICATION ECC/CNC

50 Concreting of Buloron-Lumponid FMR NSAC 17 20-Apr-12 9 Zamboanga del Sur Midsalip Midsalip ARC Cluster Buloron; Lumponid CNC 14-May-10 ECC 15-Feb-13 P completed 51 Concreting of Limonan-Kabogkabog FMR NSAC 33 17-Jul-13 9 Zamboanga del Sur San Miguel San Miguel Cluster ARC Limonan; Kabogkabog ECC 09-Jul-13 ECC 21-Jan-13 PP

52 Concreting of Tanducan-Tambunan FMR NSAC 18 18-May-12 9 Zamboanga del Sur Tabina Tabina Cluster ARC Poblacion; Malim CNC 11-Feb-11 ECC 05-Feb-13 PP

53 Rehab of Gabunon-Bag-ong Tabugon FMR NSAC 5 12-Jul-10 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster B ARC Gabunon;Tuluan; Libato; Bag-ong TabugonCNC 21-Oct-09 ECC 03-May-12 P completed

54 Const with 1.248 Concreting of Alindahaw-Panduma Sr.-Camanga FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Tukuran LUCATT-LBP ARC Alindahaw; Panduma Sr.; Camanga ECC 15-Mar-12 ECC 30-Aug-12 PP completed

55 Rehab with Spot Concreting of Balungisan-Guiwan FMR NSAC 6 27-Jan-11 9 Zamboanga Sibugay Payao Don Alfonso ARC Balungisan; La Fortuna; Calape; Kulasian;ECC Bulawan; Guiwan 23-Aug-10 ECC 12-Apr-11 PP completed 56 Rehabilitation of Bulawan CIS NSAC 32 07-Jun-13 9 Zamboanga Sibugay Payao Don Alfonso ARC Bulawan; Guiwan ECC 02-Aug-13 completed 57 Rehab of Culasian-Supit FMR NSAC 1 2-Sep-09 9 Zamboanga Sibugay Titay Supit ARC Culasian; Supit CNC 08-Jul-09 ECC 20-Mar-12 P completed 58 Concreting of Tumahubong ARC FMR NSAC 16 30-Mar-12 14 Basilan Sumisip TARBIDC ARC Tumahubong ECC 08-Sep-11 PP

59 Rehab of Tumahubong ARC FMR NSAC 21 31-Jul-12 14 Basilan Sumisip TARBIDC ARC Tumahubong CNC 03-Apr-12 ECC 08-Sep-11 PP

Notes: ECC/CNC Application shows the date when the LGU applied for ECC wiith the Environment and Management Bureau (EMB), the ECC/CNC column shows the date when the ECC was issued EMMP column, the check ( / ) mark means the LGU prepared and submitted Environment Management and Monitoring Plan (EMMP) for the subproject. IEE column, per ARCP 2 Safeguards Manual, IEE Checklist will be prepared per ARC; the check ( / ) mark means the LGU submitted an IEE checklist for the subproject DAR-ADB Agrarian Reform Communities Project II List of Subprojects issued with Certificate of Non Coverage (CNC) As of December 2017 STATUS OF LGU COMPLIANCE WITH ESS REQUIREMENTS ENVIRONMENTAL SAFEGUARDS NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE ECC/CNC

REGION EMMP IEE APPLICATION ECC/CNC

1 Construction of Anilao FMR NSAC 34 06-Sep-13 4-B Oriental Mindoro Bongabong Bongabong Central ARC Anilao CNC/ECC 22-Mar-12 CNC 20-Nov-13 P completed 2 Concreting of Orcunoma-Mina de Oro FMR NSAC 34 06-Sep-13 4-B Oriental Mindoro Bongabong Bongabong Central ARC Mina de Oro; Orcunoma CNC/ECC 22-Mar-12 CNC 25-Nov-13 P completed 3 Rehabilitation of Apurawan CIS NSAC 32 07-Jun-13 4-B Palawan Aborlan Iraan-Isaub ARC Apurawan CNC 22-Sep-14 PP completed 4 Rehabilitation of Talakaigan CIS NSAC 32 07-Jun-13 4-B Palawan Aborlan Iraan-Isaub ARC Apoc-apoc CNC 22-Sep-14 PP completed

completed 5 Rehab of Balogo PWS NSAC 18 18-May-12 4-B Romblon Calatrava Balogo ARC Balogo CNC 20-Mar-12 P 6 Concreting of Hinag-oman-Culasi-Guin-awayan FMR NSAC 23 14-Sep-12 4-B Romblon Ferrol C.M. Recto ARC Hinag-oman CNC 23-Jul-12 CNC 02-Oct-12 completed 7 Const of Tampayan Proper Health Center NSAC 7 30-Mar-11 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Tampayan CNC 10-Mar-11 CNC 06-Apr-11 PP completed 8 Const of Two (2) Classrooms School Building for Tomas and Maria MaglayaNSAC Memorial 7 School 30-Mar-11 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Tampayan CNC 10-Mar-11 CNC 06-Apr-11 PP completed 9 Const of Sitio Franco Day Care Center NSAC 18 18-May-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Dulangan CNC 17-Apr-12 NA NA completed

completed

10 Const of Tampayan/Jao-Asan PWS Level II NSAC 19 07-Jun-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Tampayan; Jao-Asan; Poblacion CNC 17-Apr-12 PP 11 Rehab of Binaliwan FMR NSAC 19 07-Jun-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Tampayan CNC 17-Apr-12 P completed 12 Rehab of Cataja FMR NSAC 19 07-Jun-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Jao-Asan CNC 17-Apr-12 P completed 13 Rehab w/ Spot Concreting of Magsaysay-Pandan FMR NSAC 21 31-Jul-12 4-B Romblon Sta. Fe Magsaysay ARC Magsaysay; Pandan CNC 04-Jul-12 CNC 24-May-13 P completed 14 Concreting of Tuaca-San Pascual FMR NSAC 11 4-Nov-11 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCTuaca; San Pascual CNC 29-Sep-11 CNC 09-Dec-11 P completed 15 Concreting of Caayunan FMR NSAC 11 4-Nov-11 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCCaayunan CNC 29-Sep-11 CNC 09-Dec-11 PP completed 16 Concreting of San Felipe FMR NSAC 21 31-Jul-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCSan Felipe CNC 26-Mar-12 CNC 04-Jun-12 100 17 Concreting of Matnog FMR NSAC 24 27-Sep-12 5 Camarines Norte Basud MATLAMALABAC ARC Matnog CNC 23-Mar-12 CNC 04-Jun-12 PP completed 18 Const of Laniton FMR NSAC 26 30-Oct-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterLaniton CNC 29-Mar-12 PP 90 19 Concreting of Tuaca-San Pascual FMR (Phase II) NSAC 27 16-Nov-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterTuaca; San Pascual CNC/ECC 10-Jul-12 CNC 19-Nov-12 PP completed 20 Concreting of San Felipe-Caayunan FMR NSAC 28 29-Nov-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterSan Felipe CNC 10-Jul-12 CNC 19-Nov-12 PP completed 21 Concreting of San Felipe-Mantugawe FMR NSAC 28 29-Nov-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterSan Felipe CNC 10-Jul-12 CNC 19-Nov-12 PP completed 22 Construction of One (1) Unit Warehouse with Office (Brgy. Laniton) NSAC 34 06-Sep-13 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterLaniton CNC 28-Feb-12 CNC 29-Mar-12 completed 23 Construction of Multipurppose Pavement (Brgy. Laniton) RSAC 5 29-Nov-11 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCLaniton CNC 21-Nov-11 CNC 21-Dec-11 P √ completed 24 Rehabilitation of Mampili Level II Potable Water System RSAC 5 29-Nov-11 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCMampili CNC 21-Nov-11 CNC 21-Dec-11 P √ completed 25 Construction of Access Road for ARCCESS RSAC 7 30-Mar-12 5 Camarines Norte Basud Matnog ARC Laniton CNC 29-Mar-12 P √ completed 26 Construction of Multipurpose Pavement/Solar Dryer in Barangay LanitonRSAC 7 30-Mar-12 5 Camarines Norte Basud Matnog ARC Laniton CNC 29-Mar-12 P √ completed 27 Concreting of Brgy. San Martin FMR NSAC 17 20-Apr-12 5 Camarines Norte Jose Panganiban San Pedro ARC San Martin CNC/ECC 11-Jan-12 CNC 10-Feb-12 PP completed 28 Concreting of Brgy. San Pedro FMR NSAC 17 20-Apr-12 5 Camarines Norte Jose Panganiban San Pedro ARC San Pedro CNC/ECC 11-Jan-12 CNC 10-Feb-12 PP 90 29 Concreting of Brgy. Tamisan FMR NSAC 17 20-Apr-12 5 Camarines Norte Jose Panganiban San Pedro ARC Tamisan CNC/ECC 16-Jan-12 CNC 10-Feb-12 PP 100 30 Concreting of Brgy. San Rafael-Sta. Rosa Norte FMR NSAC 17 20-Apr-12 5 Camarines Norte Jose Panganiban San Pedro ARC San Rafael CNC/ECC 16-Jan-12 CNC 10-Feb-12 PP 100 31 Concreting of San Pedro-Bagong Silang II FMR NSAC 31 26-Apr-13 5 Camarines Norte Jose Panganiban San Pedro ARC San Pedro CNC/ECC 10-Jul-12 CNC 19-Nov-12 PP 90 32 Concreting of Brgy. Tamisan FMR Phase II NSAC 35 18-Oct-13 5 Camarines Norte Jose Panganiban San Pedro ARC Tamisan CNC/ECC 10-Jul-12 CNC 19-Nov-12 PP 60 33 Concreting of Macogon Barangay Road NSAC 11 4-Nov-11 5 Camarines Norte Labo Daguit ARC Macogon CNC/ECC 29-Sep-11 CNC 09-Dec-11 P completed 34 Concreting of Naboongan-Igang FMR NSAC 13 19-Dec-11 5 Camarines Norte Labo Daguit ARC Daguit CNC/ECC 09-Nov-11 CNC 03-Jan-12 P 100 35 Construction of Purok 1 FMR NSAC 13 19-Dec-11 5 Camarines Norte Labo Daguit ARC Talobatib CNC/ECC 09-Nov-11 CNC 10-Feb-12 P completed 36 Concreting of Purok 7 FMR NSAC 13 19-Dec-11 5 Camarines Norte Labo Daguit ARC Talobatib CNC/ECC 09-Nov-11 CNC 10-Feb-12 P 100 37 Concreting of Malangcao Basud Purok 6-Purok 7 FMR NSAC 13 19-Dec-11 5 Camarines Norte Labo Daguit ARC Malangcao CNC/ECC 09-Nov-11 CNC 03-Jan-12 P completed 38 Concreting of Lugui FMR NSAC 35 18-Oct-13 5 Camarines Norte Labo Lugui ARC Lugui CNC/ECC 25-Oct-12 CNC 21-Feb-13 PP completed 39 Concreting of Iberica FMR NSAC 35 18-Oct-13 5 Camarines Norte Labo Lugui ARC Iberica CNC/ECC 25-Oct-12 CNC 04-Mar-13 PP completed 40 Concreting of San Antonio FMR NSAC 35 18-Oct-13 5 Camarines Norte Labo Lugui ARC San Antonio CNC 29-Oct-12 CNC 07-Mar-13 PP 75 41 Concreting of Mabilo I FMR NSAC 35 18-Oct-13 5 Camarines Norte Labo Lugui ARC Mabilo I CNC 29-Oct-12 CNC 04-Mar-13 PP completed 42 Construction of Solar Dryer (Brgy. Daguit) RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Daguit CNC 21-Nov-11 CNC 21-Dec-11 P √ completed 43 Construction of DARBO Multi-Purpose Building (Brgy. Daguit) RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Daguit CNC 21-Nov-11 CNC 21-Dec-11 P √ completed STATUS OF LGU COMPLIANCE WITH ESS REQUIREMENTS ENVIRONMENTAL SAFEGUARDS NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE ECC/CNC

REGION EMMP IEE APPLICATION ECC/CNC

44 Construction of Day Care Center (Brgy. Daguit) RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Daguit CNC 21-Nov-11 CNC 21-Dec-11 P √ completed 45 Construction of Solar Dryer (Brgy. Malangcao Basud) RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Malangcao Basud CNC 21-Nov-11 CNC 21-Dec-11 P √ completed 46 Construction of Malangcao Basud Health Station RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Malangcao Basud CNC 21-Nov-11 CNC 21-Dec-11 P √ completed 47 Rehabilitaion of Macogon Level II Potable Water System RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Macogon CNC 21-Nov-11 CNC 21-Dec-11 P √ completed 48 Construction of PHF/Warehouse RSAC 7 30-Mar-12 5 Camarines Norte Labo Daguit ARC Daguit CNC 29-Mar-12 P √ completed 49 Rehab of Matanlang-Casalugan FMR NSAC 11 4-Nov-11 5 Camarines Norte Paracale Batobalani ARC Tawig CNC/ECC 29-Sep-11 CNC 09-Dec-11 PP completed 50 Concreting of Capacuan (Purok 1-5) FMR NSAC 11 4-Nov-11 5 Camarines Norte Paracale Batobalani ARC Capacuan CNC/ECC 27-Sep-11 CNC 09-Dec-11 PP completed 51 Concreting of Batobalani-Igang FMR NSAC 14 19-Jan-12 5 Camarines Norte Paracale Batobalani ARC Batobalani CNC/ECC 09-Nov-11 CNC 10-Feb-12 PP 100 52 Concreting of Batobalani-Igang FMR (Phase II) NSAC 19 07-Jun-12 5 Camarines Norte Paracale Batobalani ARC Batobalani CNC 17-Feb-12 CNC 06-Mar-12 P 100 53 Concreting of Dagang-Tabas FMR NSAC 22 24-Aug-12 5 Camarines Norte Paracale Batobalani ARC Dagang CNC 28-Feb-12 CNC 29-Mar-12 PP 100 54 Const of Day Care Center (Brgy. Dagang) RSAC 5 29-Nov-11 5 Camarines Norte Paracale Batobalani ARC Dagang CNC 21-Nov-11 CNC 21-Dec-11 P √ completed

55 Const of MPB (Brgy. Batobalani) RSAC 5 29-Nov-11 5 Camarines Norte Paracale Batobalani ARC Batobalani CNC 21-Nov-11 CNC 21-Dec-11 P completed 56 Const of Balumbon Spring Level II Water System RSAC 5 29-Nov-11 5 Camarines Norte Paracale Batobalani ARC Dagang CNC 21-Nov-11 CNC 21-Dec-11 P √ completed 57 Improv/Expansion of Level II Water System (Brgy. Tawig) RSAC 5 29-Nov-11 5 Camarines Norte Paracale Batobalani ARC Tawig CNC 21-Nov-11 CNC 21-Dec-11 P √ completed 58 Concreting of Matacong-San Isidro FMR NSAC 13 19-Dec-11 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC Matacong CNC/ECC 09-Nov-11 CNC 06-Mar-12 100 59 Concreting of Matacong-San Isidro FMR (Extension) NSAC 20 05-Jul-12 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Isidro CNC/ECC 05-Mar-12 CNC 29-Mar-12 PP completed 60 Concreting of Purok 2 Matacong FMR NSAC 27 16-Nov-12 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC Matacong CNC/ECC 17-Feb-12 CNC 24-Jun-13 PP completed 61 Concreting of Brgy. San Ramon FMR NSAC 40 29-Apr-15 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Ramon CNC 20-Mar-15 CNC 26-Aug-16 PP completed 62 Const of San Ramon Day Care Center RSAC 3 15-Oct-10 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Ramon CNC 08-Oct-10 P √ completed 63 Const of San Isidro Day Care Center RSAC 3 15-Oct-10 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Isidro CNC 08-Oct-10 P √ completed 64 Const of Matacong Day Care Center RSAC 3 15-Oct-10 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC Matacong CNC 08-Oct-10 P √ completed 65 Const of San Ramon MPP RSAC 3 15-Oct-10 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Ramon CNC 08-Oct-10 P √ completed 66 Concreting of San Ramon, Purok 1-Purok 2 FMR RSAC 5 29-Nov-11 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Ramon CNC 21-Nov-11 CNC 21-Dec-12 P √ completed 67 Const of SIARBECO MPB and Warehouse RSAC 5 29-Nov-11 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Isidro CNC 21-Nov-11 CNC 21-Dec-12 P √ completed 68 Concreting of Antipolo-Divino Rostro FMR NSAC 18 18-May-12 5 Camarines Sur Buhi Antipolo-Divino Rostro ARC Antipolo; Divino Rostro CNC/ECC 14-May-12 CNC 07-Jan-13 completed 69 Rehab of Maligaw-ligaw FMR RSAC 3 15-Oct-10 5 Camarines Sur Buhi Antipolo-Divino Rostro ARC CNC 12-Aug-09 P √ completed 70 Concreting of Sto. Domingo-San Isidro-San Agustin-San Ramon FMR NSAC 20 05-Jul-12 5 Camarines Sur Bula BIAD II Bula Side ARC Sto. Domingo; San Isidro; San Agustin; SanCNC Ramon 09-May-12 CNC 06-Dec-12 completed 71 Concreting of Highway-Lanipga FMR NSAC 24 27-Sep-12 5 Camarines Sur Bula Lanipga ARC Lanipga CNC/ECC no date CNC 29-Oct-12 60 72 Concreting of Pinagdapian FMR NSAC 21 31-Jul-12 5 Camarines Sur Del Gallego Danawin ARC Pinagdapian CNC 27-Mar-12 CNC 11-Jul-12 completed 73 Rehab/Concreting of San Juan FMR NSAC 23 14-Sep-12 5 Camarines Sur Del Gallego Danawin ARC San Juan CNC 27-Mar-12 CNC 11-Jul-12 completed 74 Concreting of Peñafrancia FMR NSAC 26 30-Oct-12 5 Camarines Sur Del Gallego Danawin ARC Peñafrancia CNC/ECC 27-Mar-12 CNC 25-Nov-11 completed 75 Concreting of Tomagoktok FMR NSAC 26 30-Oct-12 5 Camarines Sur Del Gallego Danawin ARC Tomagoktok CNC/ECC 27-Mar-12 CNC 08-Oct-12 completed 76 Construction of Tabion FMR NSAC 31 26-Apr-13 5 Camarines Sur Del Gallego Danawin ARC Tabion CNC/ECC 27-Mar-12 CNC 09-Nov-13 completed 77 Concreting of Mansalaya FMR NSAC 31 26-Apr-13 5 Camarines Sur Del Gallego Danawin ARC Mansalaya CNC/ECC 27-Mar-12 CNC 07-May-13 completed 78 Rehab of Ason-Poblacion FMR NSAC 1 2-Sep-09 5 Camarines Sur Garchitorena Del Pilar ARC Ason; Del Pilar CNC 27-Jul-09 P 70

79 Const of Del Pilar Multi-Purpose Pavement RSAC 3 15-Oct-10 5 Camarines Sur Garchitorena Del Pilar ARC Del Pilar CNC with CNC application CNC 10-Aug-12 completed

80 Const of Ason Multi-Purpose Pavement RSAC 3 15-Oct-10 5 Camarines Sur Garchitorena Del Pilar ARC Ason CNC with CNC application CNC 10-Aug-12 completed

81 Const of Ason 2-Classroom Building RSAC 3 15-Oct-10 5 Camarines Sur Garchitorena Del Pilar ARC Ason CNC with CNC application CNC 10-Aug-12 completed

82 Const of del Pilar Classroom Building RSAC 3 15-Oct-10 5 Camarines Sur Garchitorena Del Pilar ARC Del Pilar CNC with CNC application CNC 10-Aug-12 completed 83 Construction of Health Station in Barangay Salvacion RSAC 7 30-Mar-12 5 Camarines Sur Garchitorena Del Pilar ARC Salvacion CNC 19-Mar-12 CNC 10-Aug-12 80 84 Concreting of Bahay FMR NSAC 21 31-Jul-12 5 Camarines Sur Libmanan Bahay ARC Bahay CNC/ECC 16-Mar-12 CNC 02-May-12 PP completed 85 Concreting of Potot FMR NSAC 21 31-Jul-12 5 Camarines Sur Libmanan Bahay ARC Potot CNC/ECC 16-Mar-12 CNC 02-May-12 PP 80 86 Concreting of Sitio Hamorawon FMR NSAC 21 31-Jul-12 5 Camarines Sur Libmanan Bahay ARC San Pablo CNC/ECC 16-Mar-12 CNC 02-May-12 PP 80 87 Improvement of Aslong FMR RSAC 3 15-Oct-10 5 Camarines Sur Libmanan Bahay ARC CNC 12-Oct-10 P √ completed 88 Construction of MultiPurpose Building in Barangay Bahay RSAC 7 30-Mar-12 5 Camarines Sur Libmanan Bahay ARC Bahay CNC 21-Mar-12 CNC 02-May-12 completed 89 Construction of MultiPurpose Building in Barangay Potot RSAC 7 30-Mar-12 5 Camarines Sur Libmanan Bahay ARC Potot CNC 21-Mar-12 CNC 02-May-12 completed STATUS OF LGU COMPLIANCE WITH ESS REQUIREMENTS ENVIRONMENTAL SAFEGUARDS NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE ECC/CNC

REGION EMMP IEE APPLICATION ECC/CNC

90 Construction of MultiPurpose Building in Barangay Malinao RSAC 7 30-Mar-12 5 Camarines Sur Libmanan Bahay ARC Malinao CNC 21-Mar-12 CNC 02-May-12 completed

91 Const and Concreting of Cabugao-Maydaso FMR NSAC 20 05-Jul-12 5 Camarines Sur Milaor Cabugao ARC Cabugao; Maydaso CNC 27-Mar-12 completed 92 Concreting of Cabugao-Mayaopayawan-San Antonio FMR NSAC 20 05-Jul-12 5 Camarines Sur Milaor Cabugao ARC Cabugao; Mayaopayawan; San Antonio CNC 27-Mar-12 completed 93 Construction of 2-Storey MultiPurpose Building in Barangay Cabugao RSAC 7 30-Mar-12 5 Camarines Sur Milaor Cabugao ARC Cabugao CNC 15-Nov-11 CNC 27-Mar-12 completed 94 Construction of 2-Storey MultiPurpose Building in Barangay San AntonioRSAC 7 30-Mar-12 5 Camarines Sur Milaor Cabugao ARC San Antonio CNC 15-Nov-11 CNC 27-Mar-12 completed 95 Construction of Solar Dryer for Bagong Sirang ARC RSAC 7 30-Mar-12 5 Camarines Sur Pili Bagong Sirang ARC CNC 20-Mar-12 CNC 04-Jun-12 completed 96 Construction of Solar Dryer for Binobong ARC RSAC 7 30-Mar-12 5 Camarines Sur Pili Binobong ARC CNC 27-Mar-12 CNC 04-Jun-12 completed 97 Improvement of Binobong ARC Farm to Market Road RSAC 7 30-Mar-12 5 Camarines Sur Pili Binobong ARC CNC 20-Mar-12 CNC 04-Jun-12 P √ completed 98 Construction of 2-CL School Building for Binobong ARC RSAC 7 30-Mar-12 5 Camarines Sur Pili Binobong ARC CNC 27-Mar-12 CNC 04-Jun-12 completed 99 Construction of 2-CL School Building for Sagrada ARC RSAC 7 30-Mar-12 5 Camarines Sur Pili Binobong ARC CNC 27-Mar-12 CNC 04-Jun-12 completed 100 Concreting of Lajong FMR NSAC 19 07-Jun-12 5 Sorsogon Bulan Bulan ARC Lajong CNC 10-May-12 CNC 08-Nov-12 PP completed 101 Concreting of Fabrica-G. del Pilar FMR NSAC 19 07-Jun-12 5 Sorsogon Bulan Bulan ARC Fabrica; G. del Pilar CNC 10-Apr-12 CNC 08-Nov-12 PP completed

102 Const of Boton Flood Control Structure (Flood Protection Works) NSAC 16 30-Mar-12 5 Sorsogon Casiguran Casiguran ARC Boton CNC 13-Jan-12 PP completed 103 Concreting Trese Martires-Boton FMR NSAC 18 18-May-12 5 Sorsogon Casiguran Casiguran ARC Boton; Trese Martires CNC 19-Feb-12 PP 40

104 Const of Boton Flood Control Structure (Phase II) NSAC 22 24-Aug-12 5 Sorsogon Casiguran Casiguran ARC Boton CNC 27-Mar-12 PP 35

105 Construction of 2 Storey Multi-Purpose Building RSAC 2 17-Aug-10 5 Sorsogon Casiguran Casiguran ARC A Trece Martires CNC 25-Aug-10 P √ completed

106 Rehab/Improv of San Isidro-Nalup-an FMR NSAC 5 12-Jul-10 5 Sorsogon Castilla San Rafael Expanded ARC San Isidro CNC 08-Dec-09 submitted; for NPC signature P completed 107 Rehabilitation of Pili CIS NSAC 31 26-Apr-13 5 Sorsogon Castilla San Rafael Expanded ARC San Isidro; San Rafael; Mayon; MaracabacCNC 24-Apr-13 CNC 26-Apr-13 PP completed 108 Concreting of Jupi-Dita FMR NSAC 29 19-Dec-12 5 Sorsogon Gubat Gubat ARC Dita; Jupi CNC 12-Oct-12 CNC 06-Dec-12 PP completed 109 Concreting of Bagsangan-Monbon FMR NSAC 17 20-Apr-12 5 Sorsogon Irosin Irosin ARC Bagsangan; Monbon CNC 16-Mar-12 CNC 19-Mar-12 PP 73 110 Rehabilitation of Burabod-San Julian CIS NSAC 32 07-Jun-13 5 Sorsogon Irosin Irosin ARC CNC 14-Jul-14 15 111 Const of 600 sq.m. Solar Drier RSAC 4 15-Jun-11 5 Sorsogon Irosin Irosin Municipal ARC Bagsangan CNC CNC 15-Mar-13 completed 112 Rehab of Sipaya-Calateo FMR NSAC 9 25-Aug-11 5 Sorsogon Juban Juban ARC Sipaya; Calateo CNC 09-Feb-11 PP completed 113 Concreting of Sitio Nagpana to Sitio Proper, Lipata to San Geronimo FMRNSAC 34 06-Sep-13 6 Iloilo Barotac Viejo Lipata Special ARC Lipata CNC 07-Nov-13 P completed 114 Concreting of Pulao-Bulod-Sulangan FMR NSAC 34 06-Sep-13 6 Iloilo Dumangas Dumangas ARC Pulao; Sulangan CNC 21-Oct-13 CNC 24-Sep-14 P 38 115 Rehab/Const of Sitio Cantacson-Hag-ik FMR NSAC 21 31-Jul-12 6 Negros Occidental Candoni Caningay ARC Caningay CNC 11-Jun-12 CNC 08-May-14 completed 116 Rehab of Junction National Highway-Purok 5 FMR NSAC 19 07-Jun-12 6 Negros Occidental Hinoba-an Pagbana-ag ARC Asia CNC 10-May-12 CNC 22-Nov-16 PP completed

117 Concreting of Brgy. Gen. Malvar Proper to Purok 1 Road NSAC 23 14-Sep-12 6 Negros Occidental Pontevedra Gen. Malvar ARC General Malvar CNC 23-Aug-12 CNC 13-Sep-12 PP completed

118 Const/Rehab of Brgy Proper to Purok 4 (Tamsik) Road RSAC 1 14-Dec-10 6 Negros Occidental Pontevedra General Malvar ARC General Malvar CNC 02-Sep-10 P NA completed

119 Rehab of ALBAPA FMR NSAC 7 30-Mar-11 6 Negros Occidental Valladolid ALBAPA ARC Bayabas; Alijis; Pacol CNC 08-Sep-10 CNC 19-Sep-12 PP completed Petrolio; Malobago; Kawayanan; Tuburan;Kawayanan; Tuburan; Kawayan; 120 Rehabilitation of Petrolio-Villanueva FMR NSAC 30 22-Mar-13 8 Leyte Calubian Calubian II ARC Bugtongang, Villanueva CNC 14-Oct-14 60 121 Rehab of Marao-Macagoco FMR NSAC 25 19-Oct-12 8 Leyte Inopacan Inopacan ARC Marao; Macagoco CNC 12-Apr-12 PP completed 122 Rehabilitation of Guinsangaan-Can-angay FMR NSAC 29 19-Dec-12 8 Leyte Inopacan Inopacan ARC Can-angay; Marao CNC 12-Apr-12 completed 123 Const of Manlilisid-San Sotero FMR NSAC 6 27-Jan-11 8 Leyte Javier Javier Settlement ARC Manlilisid; San Sotero CNC 17-May-10 P completed 124 Concreting of San Sotero-Ulhay FMR NSAC 18 18-May-12 8 Leyte Javier Javier Settlement ARC San Sotero; Ulhay CNC/ECC 21-Mar-12 CNC 12-Apr-12 P completed 125 Concreting of Zone 1-Pinocawan-Bonifacio-Talisayan FMR NSAC 18 18-May-12 8 Leyte Javier Javier Settlement ARC Zone 1; Pinocawan; A. Bonifacio; TalisayanCNC/ECC 21-Mar-12 CNC 12-Apr-12 P 59.96 126 Concreting of Odiong-Guindapunan FMR NSAC 19 07-Jun-12 8 Leyte Javier Javier Settlement ARC Odiong; Guindapunan CNC/ECC 01-Mar-12 CNC 12-Apr-12 completed STATUS OF LGU COMPLIANCE WITH ESS REQUIREMENTS ENVIRONMENTAL SAFEGUARDS NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE ECC/CNC

REGION EMMP IEE APPLICATION ECC/CNC

127 Concreting of San Sotero-Caraye FMR NSAC 20 05-Jul-12 8 Leyte Javier Javier Settlement ARC Caraye; San Sotero CNC/ECC 21-Mar-12 CNC 12-Apr-12 P 50.85

128 Concreting of Laray-Magsaysay-Malitbogay FMR NSAC 23 14-Sep-12 8 Leyte Javier Javier Settlement ARC Laray; Magsaysay; Malitbogay CNC 12-Apr-12 50 129 Concreting of Sitio Km. 14-Sitio Torrel, Brgy. Masarayao FMR NSAC 21 31-Jul-12 8 Leyte Kananga Kananga ARC Masarayao CNC/ECC 08-May-12 CNC 29-Apr-13 P completed 130 Rehab of Brgy. Esperanza-San Vicente FMR NSAC 15 01-Mar-12 8 Leyte Matalom Matalom II ARC Esperanza; San Vicente CNC 14-Feb-12 CNC 14-Feb-12 PP completed 131 Rehab of Elevado-Pres. Garcia FMR NSAC 27 16-Nov-12 8 Leyte Matalom Matalom II ARC Elevado; Pres. Garcia CNC 14-Jun-12 completed 132 Const of Cambalong Warehouse & Solar Dryer NSAC 27 16-Nov-12 8 Leyte Merida Merida II ARC Cambalong CNC 04-Aug-11 NA NA 95

133 Const of San Agustin-Capirawan-Cangubang FMR NSAC 2 16-Oct-09 8 Leyte Palo Palo 2 ARC San Agustin; Capirawan; Cangumbang CNC 14-Oct-09 P completed 134 Const/Improv of Brgy. Crossing-Brgy. Biasong FMR NSAC 3 19-Nov-09 8 Leyte San Isidro San Isidro ARC Brgy. Crossing; Biasong ECC 07-Oct-09 CNC 14-Sep-12 submitted; for RD signature completed 135 Rehabilitation of Bawod-Paril FMR NSAC 33 17-Jul-13 8 Leyte San Isidro San Isidro ARC Bawod; Paril CNC 15-Feb-13 completed 136 Canmogsay-Capangihan PWS LII NSAC 28 29-Nov-12 8 Leyte Tolosa Tolosa ARC Capangihan; Canmogsay CNC 23-Mar-12 P completed 137 Rehab of Casili-on-Sambulawan FMR NSAC 6 27-Jan-11 8 Leyte Villaba Villaba ARC Casili-on; Sambulawan CNC 17-Nov-09 submitted; for RD signature completed

138 Const of Sitio Balukawe-Balat Balud FMR NSAC 6 27-Jan-11 8 Northern Samar Bobon Bobon ARC Salvacion; Balat Balud CNC 04-Oct-10 CNC 18-May-12 submitted; for RD signature P completed

139 Const of Brgy. Salvacion-Sitio Balukawe FMR NSAC 22 24-Aug-12 8 Northern Samar Bobon Bobon ARC Salvacion CNC 19-Mar-12 CNC 09-Jan-13 PP completed

140 Concreting of Trojillo-Calantiao FMR NSAC 32 07-Jun-13 8 Northern Samar Bobon Bobon ARC Calantiao; Trojillo CNC/ECC 19-Mar-12 CNC 03-Mar-15 PP completed

141 Const of Calingnan-San Francisco-Cagugubngan-Osmeña-Nabulo-Nahulid-SanNSAC Jose 12 FMR 18-Nov-11 8 Northern Samar Catubig Catubig 2 ARC Calingnan; San Francisco; Cagugubngan;CNC Osmeña; Nab 03-Nov-11ulo; Nahulid; CNCSan Jose 27-Mar-12 PP 74

142 Const of Brgy. Cagamutan-Bato-Bangon FMR with Bridge NSAC 6 27-Jan-11 8 Northern Samar Gamay Gamay ARC Cagamutan; Bato; Bangon ECC 05-Nov-09 CNC 10-Jul-12 PP completed

143 Concreting of Cagamutan-Bato-Bangon FMR NSAC 28 29-Nov-12 8 Northern Samar Gamay Gamay ARC Cagamutan; Bato; Bangon CNC/ECC 12-Nov-12 CNC 23-Nov-12 PP completed 144 Concreting of Bangon-G.M. Osias FMR NSAC 40 29-Apr-15 8 Northern Samar Gamay Gamay ARC Bangon; G.M. Osias CNC 06-Mar-15 PP completed

145 Concreting of Catigbian-Cabulaloan-Sibunot FMR NSAC 25 19-Oct-12 8 Northern Samar Laoang Laoang ARC Catigbian; Cabulaloan; Sibunot CNC/ECC 12-Mar-10 CNC 02-Sep-13 P completed

146 Concreting of Catigbian-Cabulaloan-Sibunot FMR (Phase II) NSAC 35 18-Oct-13 8 Northern Samar Laoang Laoang ARC Catigbian; Cabulaloan; Sibunot CNC 12-Mar-13 CNC 09-Oct-14 completed

147 Concreting of Matambag-Osmeña-Bangon FMR NSAC 30 22-Mar-13 8 Northern Samar Palapag Palapag ARC Matambag; Osmeña; Bangon CNC/ECC 17-Feb-12 CNC 31-Mar-14 PP 37

148 Improvement of Bonglas (Junction-Brgy. Proper) FMR NSAC 21 31-Jul-12 8 Northern Samar San Jose San Jose ARC Bonglas CNC 03-Apr-12 CNC 03-Feb-15 PP completed

149 Const of Brgy. San Miguel FMR NSAC 18 18-May-12 8 Eastern Samar Balangiga Balangiga ARC San Miguel ECC 04-May-12 CNC 08-Aug-12 PP 80 150 Rehab and Const of Guinpoliran-Bangon-Cantubi FMR (Section 1) NSAC 16 30-Mar-12 8 Eastern Samar Balangkayan Balangkayan ARC Guinpoliran; Bangon; Cantubi ECC 20-Jan-12 CNC 09-Feb-12 PP 85 151 Concreting of Jumalag-Magsaysay FMR (Section 2) NSAC 16 30-Mar-12 8 Eastern Samar Balangkayan Balangkayan ARC Jumalag; Magsaysay ECC 20-Jan-12 CNC 09-Feb-12 PP completed STATUS OF LGU COMPLIANCE WITH ESS REQUIREMENTS ENVIRONMENTAL SAFEGUARDS NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE ECC/CNC

REGION EMMP IEE APPLICATION ECC/CNC

152 Concreting of Barangay Taguite FMR NSAC 26 30-Oct-12 8 Eastern Samar Lawaan Lawaan ARC Taguite CNC 02-Aug-12 33

153 Concreting of San Pedro-Palactad FMR with 6.65 LM Flat Slab Bridge NSAC 28 29-Nov-12 8 Eastern Samar Quinapondan Quinapondan ARC San Pedro; Rizal; Palactad CNC 10-Aug-12 P completed

154 Rehab of Casilion-Tagbacan-Taclaon-Sta. Cruz FMR NSAC 6 27-Jan-11 8 Eastern Samar Salcedo Salcedo ARC Casilion; Tagbacan; Taclaon; Sta. Cruz CNC 10-Nov-11 P 70 155 Concreting of Cagaut-Cantomoja-Camanga-Carapdapan FMR NSAC 33 17-Jul-13 8 Eastern Samar Salcedo Salcedo ARC Cagaut; Cantomoja;Camanga;Carapdapan CNC 12-Apr-12 P 19

156 Const of Casoroy-Layog FMR NSAC 3 19-Nov-09 8 Eastern Samar San Julian San Julian ARC Casoroy CNC 21-Oct-09 CNC 21-Oct-09 P completed

157 Const of Agricultural Warehouse NSAC 13 19-Dec-11 8 Eastern Samar San Julian San Julian ARC Libas CNC 28-Nov-11 P completed

158 Const of Panaw-nawan-Magti-aw FMR NSAC 15 01-Mar-12 8 Eastern Samar San Julian San Julian ARC Campidhan; Nena; Libas CNC 28-Nov-11 PP 80

159 Rehab of Sta. Cruz-Bangon FMR NSAC 5 12-Jul-10 8 Eastern Samar San Policarpo ESSP ARC Sta. Cruz; Bangon ECC 22-Oct-09 CNC 03-Mar-11 submitted; for NPC signature P 55

160 Const of Lumatod-Danao FMR with 20 LM RCDG Bridge NSAC 6 27-Jan-11 8 Eastern Samar Taft Taft ARC Lumatod; Danao; Del Remedios CNC 20-Oct-09 CNC 28-Oct-11 P 67.27 161 Concreting of Barobaybay-Pasigay FMR NSAC 23 14-Sep-12 8 Western Samar Calbiga SOWSEED ARC Cluster Barobaybay; Pasigay CNC 13-Jun-12 CNC 05-Dec-12 PP completed 162 Concreting of Brgy. 7-Tinago FMR NSAC 23 14-Sep-12 8 Western Samar Calbiga SOWSEED ARC Cluster Brgy. 7; Tinago CNC 13-Jun-12 CNC 05-Dec-12 PP completed 163 Concreting of Panayuran FMR NSAC 23 14-Sep-12 8 Western Samar Calbiga SOWSEED ARC Cluster Polangi; Panayuran CNC 13-Jun-12 CNC 05-Dec-12 PP completed 164 Construction of Calbiga Upland Barangay PWS NSAC 30 22-Mar-13 8 Western Samar Calbiga SOWSEED ARC Cluster Borong; Hubasan; Mahangcao; Macaalan;CNC Panayuran 11-Apr-12 CNC 07-May-13 P 165 Concreting of Macaparican ARC FMR NSAC 20 05-Jul-12 8 Western Samar Jiabong Macaparican ARC Cantongtong CNC 17-Apr-12 P completed 166 Improv of Pagsangan-San Agustin FMR NSAC 2 16-Oct-09 8 Western Samar Pagsanghan Pagsangahan Strategic ARC Canlapwas; Villahermosa Occidental; VillahermosaECC/CNC Oriental; 24-Aug-09 Pange; San CNC Luis; 30-Sep-09Buenos Aires Pagsanghan ARC (Pagsanghan). Hinogacan; San Agustin;completed Gandara; Dapdap (Tarangnan) 167 Concreting of Pagsanghan-Caloloma FMR NSAC 21 31-Jul-12 8 Western Samar Pagsanghan Pagsanghan ARC Poblacion; Caloloma CNC 29-May-12 P completed 168 Concreting of Quezon-Cantaguic FMR NSAC 30 22-Mar-13 8 Western Samar San Jorge San Jorge ARC Quezon; San Isidro; Rawis; Cantaguic CNC 16-Jan-13 PP 50.98 169 Spot Concreting of Poblacion-Tulay FMR NSAC 13 19-Dec-11 8 Western Samar Sta. Rita SOWSEED ARC Cluster Tulay; Camayse; Anibongon; Gumamela; Rosal; Bougainvilla; Santan;CNC Bokinggan; 01-Dec-11 Hinangutnan; SalvacionP and San Roque 85 170 Concreting of Poblacion-Hinangutdan FMR NSAC 27 16-Nov-12 8 Western Samar Sta. Rita SOWSEED ARC Cluster Poblacion; Hinangutdan CNC 08-Oct-12 P 50 171 Rehab of Barangay Dapdap-Lahong FMR NSAC 2 16-Oct-09 8 Western Samar Tarangnan St. Francis ARC Dapdap; Talinga; Binalayan; Lahong CNC 16-Sep-09 CNC 17-Sep-09 PP completed 172 Spot Concreting of Balugo-Imelda FMR NSAC 19 07-Jun-12 8 Western Samar Tarangnan St. Francis and Cambatutay ARC Balugo; Bahay; Pajo; Gallego; Balongaas; Canunghan; Imelda CNC 27-Mar-12 completed submitted; for RD signature; original copy with Region 8 173 Const/Rehab of Villareal ARC FMR NSAC 4 16-Mar-10 8 Western Samar Villareal Villareal ARC Canmucat; Nagcaduha; Macopa; Conant CNC 09-Nov-09 counterpart completed 174 Concreting of Villareal ARC FMR NSAC 16 30-Mar-12 8 Western Samar Villareal SOWSEED ARC San Fernando; Malonoy; Sto. Niño; Igot; Macopa CNC 29-Mar-12 67 175 Rehab with Concreting of Polayo-Denuyan FMR NSAC 19 07-Jun-12 9 Zamboanga del Norte Siayan Siayan West ARC Polayo CNC 29-Mar-12 CNC 27-Feb-15 PP completed 176 Rehab with 0.75 km Concreting of Paranglumba FMR NSAC 20 05-Jul-12 9 Zamboanga del Norte Siayan Siayan West ARC Paranglumba CNC 29-Mar-12 CNC 25-Feb-15 PP completed 177 Rehab with 2 km. Concreting of Sitio Bolanao-Litolet FMR NSAC 21 31-Jul-12 9 Zamboanga del Norte Siayan Siayan East ARC Litolet CNC 29-Mar-12 CNC 27-Feb-15 PP 30 178 Rehab with 0.7 km. Concreting of Moyo-Sitio Pase FMR NSAC 21 31-Jul-12 9 Zamboanga del Norte Siayan Siayan West ARC Moyo CNC 29-Mar-12 CNC 25-Feb-15 PP 10 179 Rehab with 0.9 km. Concreting of Gonayen-Sayaw FMR NSAC 21 31-Jul-12 9 Zamboanga del Norte Siayan Siayan East ARC Gonayen CNC 29-Mar-12 CNC 25-Feb-15 PP completed 180 Construction of Panabutan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Sirawai Panabutan Expanded ARC CNC 04-Apr-12 completed 181 Construction of Catuyan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Sirawai Panabutan Expanded ARC CNC 04-Apr-12 completed 182 Construction of Sipakit FMR RSAC 8 6-Jul-12 9 Zamboanga del Norte Sirawai Panabutan Expanded ARC CNC 04-Apr-12 completed 183 Upgrading/Rehab of Poblacion-New Dapitan FMR NSAC 24 27-Sep-12 9 Zamboanga del Norte Tampilisan Rubber Stump ARC Poblacion CNC 22-Apr-12 CNC 26-Sep-13 65 STATUS OF LGU COMPLIANCE WITH ESS REQUIREMENTS ENVIRONMENTAL SAFEGUARDS NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE ECC/CNC

REGION EMMP IEE APPLICATION ECC/CNC

184 Concreting of Poblacion-ZNAC FMR NSAC 27 16-Nov-12 9 Zamboanga del Norte Tampilisan Rubber Stump ARC ZNAC CNC 27-Mar-12 CNC 26-Sep-13 PP completed 185 Rehabilitation of Sagrada Familia CIS NSAC 31 26-Apr-13 9 Zamboanga del Sur Aurora TaGuMa ARC CNC 12-Sep-14 20

186 Const of Maralag-Libertad FMR NSAC 3 19-Nov-09 9 Zamboanga del Sur Dumingag Mantilba ARC Maralag; Libertad CNC 28-Aug-09 P completed 187 Rehabilitation of Guipos CIS NSAC 34 06-Sep-13 9 Zamboanga del Sur Guipos Balongating Expanded ARC Balangating, Poblacion CNC 26-Sep-13 CNC 22-Oct-13 PP

188 Const of Brgy. Buloron-Dumalinao FMR NSAC 16 30-Mar-12 9 Zamboanga del Sur Midsalip Midsalip ARC Cluster Buloron; Dumalinao CNC/ECC 12-May-10 CNC 26-Dec-12 PP completed

189 Concreting of Purok Jupiter (Basay)-Purok Venus FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Molave Rizal ARC Rizal CNC/ECC 15-May-12 CNC 12-Jul-12 PP completed

190 Concreting of Purok Ferry-Purok Happy Valley FMR NSAC 21 31-Jul-12 9 Zamboanga del Sur Molave Miligan ARC Miligan CNC/ECC 15-May-12 CNC 12-Jul-12 PP completed

191 Concreting of Lower Lodiong-Limamaan FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster B ARC Lower Lodiong; Limamaan CNC 30-Apr-12 PP completed

192 Concreting of Junction Limamaan-Upper Lodiong FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster B ARC Upper Lodiong; Limamaan; Tuluan CNC 30-Apr-12 PP completed 193 Rehab w/ Spot Concreting of Limamaan FMR NSAC 22 24-Aug-12 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster B ARC Limamaan CNC 30-Apr-12 PP completed

194 Rehab/Improv of Guinlin-Limas FMR NSAC 1 2-Sep-09 9 Zamboanga del Sur Tigbao BegCaLLi ARC Guinlin; Limas CNC 24-Nov-09 P completed

195 Const of Maasin & Tiayon PWS Level II NSAC 25 19-Oct-12 9 Zamboanga Sibugay Ipil SWIZS ARC Maasin; Tiayon CNC 27-Jun-12 PP completed

196 Concreting of Poblacion-Ligaya FMR NSAC 25 19-Oct-12 9 Zamboanga Sibugay Mabuhay Placeres ARC Ligaya; Poblacion CNC 08-Jun-12 completed

197 Const of Sitio Tuburan-Malinao FMR NSAC 25 19-Oct-12 9 Zamboanga Sibugay Mabuhay Placeres ARC Malinao; Poblacion CNC 08-Jun-12 86.64

198 Concreting of Poblacion-Malinao FMR NSAC 37 18-Feb-14 9 Zamboanga Sibugay Mabuhay Placeres ARC Poblacion; Malinao CNC 08-Jun-12 completed

199 Rehab of Tambanan-Sulo FMR NSAC 18 18-May-12 9 Zamboanga Sibugay Naga Tambanan and Sulo ARC Tambanan; Sulo ECC 24-Apr-12 CNC 10-May-12 PP completed

200 Concreting of Balungisan-Upper Sumilong FMR NSAC 35 18-Oct-13 9 Zamboanga Sibugay Payao Don Alfonso ARC Balungisan; Upper Sumilong CNC 07-Jun-12 CNC 07-Jun-12 P completed 201 Rehab w/ Spot Concreting of Kitabog-Mabini FMR NSAC 20 05-Jul-12 9 Zamboanga Sibugay Titay Titay Valley ARC Kitabog; Mabini CNC 08-Jun-12 P completed 202 Concreting of Brgy. Libertad FMR NSAC 19 07-Jun-12 9 Zamboanga Sibugay Tungawan TRI-People ARC Libertad CNC 02-Apr-12 CNC 10-Jun-13 PP 70 203 Concreting of Tumahubong ARC FMR NSAC 16 30-Mar-12 14 Basilan Sumisip TARBIDC ARC Tumahubong ECC 08-Sep-11 PP 50 204 Const of Tumahobong PWS LII NSAC 18 18-May-12 14 Basilan Sumisip TARBIDC ARC Tumahubong CNC 08-Sep-11 PP 10

205 Rehab of Tumahubong ARC FMR NSAC 21 31-Jul-12 14 Basilan Sumisip TARBIDC ARC Tumahubong CNC 03-Apr-12 ECC 08-Sep-11 PP 64.36 206 Concreting of TARBADECO ARC Road Network NSAC 18 18-May-12 14 Basilan Tipo-Tipo TARBADECO ARC Tipo-Tipo Proper; Magkawa; Limbu-pas; CNCGuinanta 03-Apr-12 CNC 28-Sep-12 PP completed 207 Concreting of Phil-Am-Buhe Pahu FMR NSAC 18 18-May-12 14 Basilan Ungkaya Pukan TIPARBECO ARC Cabangalan; Buhe Pahu CNC 12-Feb-12 CNC 28-Sep-12 PP completed 208 Concreting of Brgy. Dado Poblacion-Sitio Matampay Bagoaingud FMR NSAC 37 18-Feb-14 14 Lanao del Sur Balindong Dado ARC Dado CNC 16-Jun-14 completed 209 Construction of Dado ARC PWS LII NSAC 37 18-Feb-14 14 Lanao del Sur Balindong Dado ARC Dado CNC 16-Jun-14 completed 210 Concreting of Sumogot FMR NSAC 18 18-May-12 14 Lanao del Sur Bumbaran Bumbaran ARC Sumogot CNC 03-Apr-12 CNC 15-May-12 42.49

211 Const of Barit-Taliogon-Tabuan FMR NSAC 4 16-Mar-10 14 Lanao del Sur Ganassi Taliogon ARC Taliogon; Tabuan ECC 12-Nov-09 CNC 09-Jun-10 completed 212 Concreting and Rehab of Taganonok-Taliogon-Paraaba FMR NSAC 18 18-May-12 14 Lanao del Sur Ganassi Taliogon ARC Campongaraya; Taganonok;Taliogon; ParaabaCNC 03-Apr-12 CNC 15-May-12 213 Construction of Masolun-Taganonok-Taliogon FMR NSAC 35 18-Oct-13 14 Lanao del Sur Ganassi Taliogon ARC Masolun; Taganonok; Taliogon CNC 18-Nov-14 CNC 22-Apr-15 PP 214 Concreting of Campongaraya-Barorao-Panggawalupa-Barit FMR NSAC 36 06-Dec-13 14 Lanao del Sur Ganassi Taliogon ARC Campongaraya; Barorao; Panggawalupa; BaritCNC 18-Nov-14 CNC 22-Apr-15 PP 215 Concreting of Pindolonan-Pantao-Macadar FMR NSAC 35 18-Oct-13 14 Lanao del Sur Kapai Pindolonan ARC Pindolonan; Pantao; Macadar CNC 12-Sep-14 P 216 Concreting of Bangon-Lumbac & Dimapok FMR NSAC 36 06-Dec-13 14 Lanao del Sur Lumbaca Unayan Dilausan ARC Bangon; Lumbac; Dimapok CNC 30-Jul-14 CNC 15-Jan-15 217 Concreting of Pitatanglan-Wago Kabasaran & Wago-Miniros FMR NSAC 36 06-Dec-13 14 Lanao del Sur Lumbayanague Cabasaran ARC Pitatanglan; Wago; Kabasaran; Miniros CNC 16-Mar-15 218 Concreting of Camalig Bandaraingud-Loway Inodaran FMR NSAC 21 31-Jul-12 14 Lanao del Sur Marantao Bubong Camalig ARC Camalig Bandaraingud; Loway Inodaran CNC 03-Apr-12 CNC 04-Mar-13 PP 219 Concreting and Rehab of Bubong-Ragayan-Gadongan FMR NSAC 18 18-May-12 14 Lanao del Sur Poona Bayabao Ragayan ARC Bubong Dimunda; Pantao; Ragayan; Bansayan;CNC Gadongan 03-Apr-12 CNC 15-May-12 PP STATUS OF LGU COMPLIANCE WITH ESS REQUIREMENTS ENVIRONMENTAL SAFEGUARDS NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE ECC/CNC

REGION EMMP IEE APPLICATION ECC/CNC

220 Concreting of Dinganun-Pagalongan-Bacayawan-Lumbac FMR NSAC 35 18-Oct-13 14 Lanao del Sur Sultan DumalondongSultan Dumalondong ARC Dinganun; Pagalongan; Bacayawan; Lumbac CNC 22-Jan-15 P

221 Concreting of Kinggan-Tagoloan Poblacion FMR NSAC 13 19-Dec-11 14 Lanao del Sur Tagoloan Malinao-Cadayonan ARC Malinao; Cadayonan ECC 05-Sep-11 CNC 28-Sep-12 PP 222 Concreting of Buadi Diamangga-Buadi Ongcalo FMR (Section 1) NSAC 35 18-Oct-13 14 Lanao del Sur Taraka Sigayan ARC Buadi Diamangga; Buadi Ongcalo; CadayonanECC 18-Aug-14 CNC 27-Feb-15 P completed

223 Concreting of Cadayonan FMR (Section 2) NSAC 35 18-Oct-13 14 Lanao del Sur Taraka Sigayan ARC Buadi Diamangga; Buadi Ongcalo; CadayonanECC 18-Aug-14 CNC 27-Feb-15 P 224 Construction of MPB (Bgy. Buadi Amunud) NSAC 36 06-Dec-13 14 Lanao del Sur Taraka Sigayan ARC Buadi Amunod CNC 27-Feb-15 completed

225 Construction of MPB (Bgy. Sundig) NSAC 36 06-Dec-13 14 Lanao del Sur Taraka Sigayan ARC Sundig CNC 27-Feb-15 completed

226 Construction of MPB (Bgy. Moriatao Luksadato) NSAC 36 06-Dec-13 14 Lanao del Sur Taraka Sigayan ARC Moriato Luksadato CNC 27-Feb-15 227 Taraka Pump Irrigation Communal Irrigation Project NSAC 36 06-Dec-13 14 Lanao del Sur Taraka Sigayan ARC ECC 18-Aug-14 CNC 27-Feb-15 P 228 Concreting of 8 km Dinganen-Nuyo FMR I NSAC 35 18-Oct-13 14 Maguindanao Buldon Buldon ARC Dinganen-Nuyo CNC 09-Dec-14 229 Concreting of Tamborong-Bunawan FMR NSAC 13 19-Dec-11 14 Maguindanao Datu Paglas Bunawan ARC Tamborong; Bunawan CNC 11-Jan-10 CNC 23-Mar-12 PP completed 230 Const of Ganta-Gambar FMR NSAC 14 19-Jan-12 14 Maguindanao Kabuntalan Matilak ARC Ganta; Pagalungan; Gambar CNC 28-Mar-11 CNC 15-May-12 PP completed 231 Concreting of Pasil-Langpas Farm to Market Road NSAC 39 26-Aug-14 14 Sulu Indanan Pasil ARC Pasil; Langpas CNC 27-Apr-15 232 Concreting of Kuppong-Kagay Farm to Market Road NSAC 39 26-Aug-14 14 Sulu Indanan Pasil ARCTubig Kuppong; Samin; Kaga Matatal;y Datag CNC 27-Apr-15 Limbun; Gulangan; Kandang; 233 Concreting of Patao Junction-Ipil FMR NSAC 13 19-Dec-11 14 Sulu Maimbung Maimbung ARC TubigPatao; Samin; Ipil Matatal; Datag CNC 04-Nov-11 CNC 28-Sep-12 P completed Limbun; Gulangan; Kandang; 234 Concreting of Pantao Junction-Kandang Gulangan-Ratag Limbun FMR NSAC 13 19-Dec-11 14 Sulu Maimbung Maimbung ARC Patao; Ipil CNC 04-Nov-11 CNC 28-Sep-12 P completed Limbun; Gulangan; Kandang; 235 Concreting of Tubig Samin Junction-Tambuan FMR NSAC 13 19-Dec-11 14 Sulu Maimbung Maimbung ARC Patao; Ipil CNC 04-Nov-11 CNC 28-Sep-12 P completed 236 Rehab of Su'uh-Kan-dayuk-Kan-ukul FMR NSAC 7 30-Mar-11 14 Sulu Panamao Sultan Jamalul Kiram ARC Kan-dayuk; Kan-ukul; Su'uh CNC 28-Sep-12 P completed 237 Concreting of Parian-Dakula-Lahi-Malanta FMR NSAC 13 19-Dec-11 14 Sulu Pandami Pandami ARC Parian Dakula; Lahi; Malanta CNC 04-Nov-11 CNC 28-Sep-12 PP 238 Concreting of Bgy. Tando Bato FMR NSAC 37 18-Feb-14 14 Sulu Luuk Tando Bato ARC Tando Bato CNC 27-Nov-14 239 Concreting of Kahawa - Tampakan FMR NSAC 37 18-Feb-14 14 Sulu Talipao CNC 09-Oct-14 240 Concreting of Tandubanak ARC FMR (Section 1) NSAC 14 19-Jan-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak CNC/ECC 28-Nov-11 CNC 28-Sep-12 PP 241 Concreting of Tandubanak ARC FMR (Section 2) NSAC 14 19-Jan-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak CNC/ECC 28-Nov-11 CNC 28-Sep-12 PP 242 Concreting of Tandubanak ARC FMR (Section 3) NSAC 14 19-Jan-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak CNC/ECC 28-Nov-11 CNC 28-Sep-12 PP 243 Concreting of Tongehat ARC FMR NSAC 14 19-Jan-12 14 Tawi-Tawi Sibutu Ungus-Ungus-Tongehat ARC Tongehat CNC/ECC 28-Nov-11 CNC 28-Sep-12 PP 244 Construction of 3-Unit Classroom School Building (Brgy. Tandubanak) RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak CNC 28-Sep-12 completed 245 Construction of 3-Unit Classroom School Building MSU-CHS (Brgy. Ungus-Ungus)RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Ungus-Ungus CNC 28-Sep-12 completed 246 Construction of 3-Unit Classroom School Building (Brgy. Taungoh) RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Tandubanak ARC Taungoh CNC 28-Sep-12 completed 247 Construction of 3-Unit Classroom School Building (Brgy. Tongehat) RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Tongehat CNC 28-Sep-12 completed 248 Construction of 3-Unit Classroom School Building (Brgy. Tongsibalo) RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Tongsibalo CNC 28-Sep-12 completed 249 Construction of 3-Unit Classroom School Building (Brgy. Ungus-Ungus) RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Ungus-Ungus CNC 28-Sep-12 completed 250 Construction of Barangay Ungus-Ungus Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Ungus-Ungus CNC 28-Sep-12 completed 251 Construction of Barangay Tongsibalo Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Tongsibalo CNC 28-Sep-12 completed 252 Construction of Barangay Tongehat Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Tongehat CNC 28-Sep-12 completed 253 Construction of Barangay Taungoh Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Taungoh CNC 28-Sep-12 completed 254 Construction of Barangay Tandubanak Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak CNC 28-Sep-12 completed

Notes: ECC/CNC Application shows the date when the LGU applied for CNC wiith the Environment and Management Bureau (EMB), the ECC/CNC column shows the date when the CNC was issued EMMP column, the check ( / ) mark means the LGU prepared and submitted Environment Management and Monitoring Plan (EMMP) for the subproject. IEE column, per ARCP 2 Safeguards Manual, IEE Checklist will be prepared per ARC; the check ( / ) mark means the LGU submitted an IEE checklist for the subproject ANNEX IV - C: LIST OF SUBPROJECTS WITH PROJECT-AFFECTED PERSONS (PAPs) DAR-ADB Agrarian Reform Communities Project II As of December 2017

INVOLUNTARY RESETTLEMENT NSAC/RSAC SUBPROJECT TITLE PROVINCEMUNICIPALITY Barangay Physical Status DATE MASTERLIST Summary of Affected Land and PAPs MINUTES OF MEETING (W/ RIGHT OF WAY DOCUMENTATION

REGION LEGAL DOCS LEGAL DOC(S) EXECUTED RP/SDR OF PAPS Improvements/Livelihood ATTENDANCE SHEET) MALE FEMALE TOTAL LAND IMPROVEMENTS TOTAL PROOF OF VALUATION

1 Const & Rehab w/ Spot Concreting of Laway I-Kantong Putol FMR NSAC 27 16-Nov-12 4-B Oriental Mindoro Bansud Salcedo 100% completed Deed of Donation 4 0 4 P 136,130.00 0.00 136,130.00 completed 2 Construction of Anilao FMR NSAC 34 06-Sep-13 4-B Oriental Mindoro Bongabong Anilao PP 100% completed Affidavit 7 5 12 RP 121,500.00 0.00 121,500.00 completed 3 Construction with Spot Concreting of Sta. Brigida-Alegria FMR NSAC 28 29-Nov-12 4-B Oriental Mindoro Mansalay Sta. Brigida 100% completed Deed of Donation 5 3 8 RP 50,000.00 Schedule of Market Values for Agricultural lands, cluster of Mainland Municipalities, completed 4 Construction/Rehabilitation of Tagpit-Titibawan FMR NSAC 31 26-Apr-13 4-B Palawan Aborlan Isaub; San Juan PP 100% completed Deed of Donation 1 2 3 49,239.20 0.00 49,239.20 Palawan Permit to Enter, Construct and Operate; DOD; Affidavit of Possession with Quit completed 5 Rehab of Balogo PWS NSAC 18 18-May-12 4-B Romblon Calatrava Balogo PP 100% completed Claim 8 3 11 P 0.00 0.00 0.00 6 Const of Tampayan Proper Health Center NSAC 7 30-Mar-11 4-B Romblon Magdiwang Tampayan PP 100% completed Deed of Donation 0 1 1 SDR P completed 7 Const of Two (2) Classrooms School Building for Tomas and Maria MaglayaNSAC Memorial 7 School 30-Mar-11 4-B Romblon Magdiwang Tampayan PP 100% completed Deed of Donation 0 1 1 SDR P completed Written Consent for Right of Way (ROW) - Permit to Enter Construct and completed Operate; Affidavit of Possession with 8 Const of Tampayan/Jao-Asan PWS Level II NSAC 19 07-Jun-12 4-B Romblon Magdiwang Tampayan; Jao-Asan; Poblacion PP 100% completed Quit Claim 48 RP P 0.00 0.00 0.00 9 Rehab of Binaliwan FMR NSAC 19 07-Jun-12 4-B Romblon Magdiwang Tampayan 100% completed Deed of Donation with Quit Claim 7 5 12 RP P 27,230.00 0.00 27,230.00 completed 10 Rehab of Cataja FMR NSAC 19 07-Jun-12 4-B Romblon Magdiwang Jao-Asan PP 100% completed Deed of Donation with Quit Claim 3 9 12 RP P 67,800.00 2,500.00 70,300.00 completed 11 Const of Sanghiran-Campo-Agpudlos Proper FMR NSAC 9 25-Aug-11 4-B Romblon San Andres Agpudlos PP 100% completed Deed of Donation 28 19 47 RP P 566,080.00 66,000.00 632,080.00 Certification completed 12 Const of Laniton FMR NSAC 26 30-Oct-12 5 Camarines Norte Basud Laniton PP 100% completed Joint Undertaking 11 P 50,000.00 13 Rehabilitation of Mampili Level II Potable Water System RSAC 5 29-Nov-11 5 Camarines Norte Basud Mampili 100% completed Permit to Enter completed 14 Rehabilitaion of Macogon Level II Potable Water System RSAC 5 29-Nov-11 5 Camarines Norte Labo Macogon 100% completed Permit to Enter completed Joint Undertaking/ Waiver of Right/Quit 15 Const of Sitio Potot FMR NSAC 19 07-Jun-12 5 Camarines Norte Paracale Batobalani 100% completed Claim 3 4 7 RP 0.00 0.00 0.00 completed 16 Improv/Expansion of Level II Water System (Brgy. Tawig) RSAC 5 29-Nov-11 5 Camarines Norte Paracale Tawig 100% completed Permit to Enter completed 17 Const of San Isidro-Sitio Too FMR NSAC 13 19-Dec-11 5 Camarines Norte San Lorenzo Ruiz San Isidro P 100% completed Joint Undertaking 18 1 19 43,994.00 0.00 43,994.00 BIR Zonal Valuation completed 18 Rehab/Concreting of San Juan FMR NSAC 23 14-Sep-12 5 Camarines Sur Del Gallego San Juan 100% completed Deed of Donation 7 1 8 250,350.00 0.00 250,350.00 completed 19 Construction of Tabion FMR NSAC 31 26-Apr-13 5 Camarines Sur Del Gallego Tabion PP 100% completed Deed of Donation 4 2 6 0.00 0.00 0.00 completed BIR Zonal; Bureau of Agricultural Statistics 20 Const of Cabugao FMR NSAC 5 12-Jul-10 5 Camarines Sur Milaor Cabugao PP 100% completed Deed of Sale 24 6 30 RP P 216,401.72 234,290.78 450,692.50 Certification Municipal Assessor's Valuation; 21 Const and Concreting of Cabugao-Maydaso FMR NSAC 20 05-Jul-12 5 Camarines Sur Milaor Cabugao; Maydaso 100% completed Deed of Donation with Quit Claim 4 2 6 90,079.32 6,890.00 96,969.32 Bill of Materials completed Provincial Assessor's Valuation; 22 Const of Boton Flood Control Structure (Flood Protection Works) NSAC 16 30-Mar-12 5 Sorsogon Casiguran Boton PP 100% completed Deed of Donation with Quit Claim 24 RP P 151,761.48 129,320.00 281,081.48 Bill of Materials completed 23 Concreting Trese Martires-Boton FMR NSAC 18 18-May-12 5 Sorsogon Casiguran Boton; Trese Martires PP 100% completed Deed of Donation with Quit Claim 11 3 14 RP 44,236.22 150,500.00 194,736.22 Provincial Assessor's Valuation Provincial Assessor's Valuation; 24 Const of Boton Flood Control Structure (Phase II) NSAC 22 24-Aug-12 5 Sorsogon Casiguran Boton P 100% completed Deed of Donation with Quit Claim 9 4 13 RP P 6,595.45 16,090.00 22,685.45 MENRO

Deed of Donation with Quit Claim; Affidavit of Possession with Easement of Schedule of Fair Market Values 25 Rehab/Improv of San Isidro-Nalup-an FMR NSAC 5 12-Jul-10 5 Sorsogon Castilla San Isidro PP 100% completed Right of Way and Quit Claim 8 3 11 RP P 542,301.40 65,800.00 608,101.40 of Real Properties completed Reso. No. 050a-2008; Municipal Agriculturist and Municipal Assessor's 26 Roadway Construction and Concreting of Hidhid-Banogao FMR NSAC 23 14-Sep-12 5 Sorsogon Matnog Hihid; Banogao 4 out of 16 PAPs with legal documents (25%) Deed of Donation 16 342,489.20 71,915.00 414,404.20 Certification completed 27 Concreting of Sitio Nagpana to Sitio Proper, Lipata to San Geronimo FMRNSAC 34 06-Sep-13 6 Iloilo Barotac Viejo Lipata PP 100% completed Joint Quit Claim 10 7 17 P 0.00 0.00 0.00 MAO Certification completed 28 Concreting/Rehabilitation of Junction Tapacon-Inamyugan-Agbao-GuinhulaganNSAC FMR 37 w/ Bridge 18-Feb-14 6 Iloilo Bingawan Tapacon; Agba-o; Guinhulacan; Inamyugan PP 100% completed Joint Quit Claim 24 20 44 P 0.00 0.00 0.00 MAO Certification 29 Concreting of Pulao-Bulod-Sulangan FMR NSAC 34 06-Sep-13 6 Iloilo Dumangas Pulao; Sulangan PP 100% completed Joint Quit Claim 21 9 30 P 0.00 0.00 0.00 30 Concreting of JNR-Agsirab-Bagongbong-Sitio Agdalusan FMR NSAC 35 18-Oct-13 6 Iloilo Lambunao Agsirab; Bagongbong PP 100% completed Joint Quit Claim 20 13 33 P 0.00 0.00 0.00 MAO Certification completed Joint Quit Claim; Deed of Donation with 31 Concreting of San Andres – San Florentino FMR with Bridge NSAC 37 18-Feb-14 6 Iloilo San Rafael San Andres; San Florentino PP 100% completed Quit Claim 14 10 24 P 0.00 0.00 0.00 MAO Certification Joint Quit Claim; Affidavit of Possession Municipal Agriculturist 32 Rehab/Const of Sitio Cantacson-Hag-ik FMR NSAC 21 31-Jul-12 6 Negros Occidental Candoni Caningay PP 100% completed with Quit Claim 19 4 23 P 0.00 76,751.20 76,751.20 Valuation completed 33 Rehab of Junction National Highway-Purok 5 FMR NSAC 19 07-Jun-12 6 Negros Occidental Hinoba-an Asia PP 100% completed Joint Quit Claim 6 4 10 RP P 10,000.00 11,900.00 21,900.00 completed Affidavit of Possession with Quit Claim; Municipal Agriculturist 34 Concreting of Brgy. Gen. Malvar Proper to Purok 1 Road NSAC 23 14-Sep-12 6 Negros Occidental Pontevedra General Malvar PP 100% completed Deed of Donation with Quit Claim 6 2 8 RP P 2,600.00 13,560.00 16,160.00 Valuation; Bill of Materials completed Deed of Donation with Quit Claim; 35 Const/Rehab of Brgy Proper to Purok 4 (Tamsik) Road RSAC 1 14-Dec-10 6 Negros Occidental Pontevedra General Malvar PP 100% completed Waiver of Rights 11 3 14 RP √ completed Deed of Donation with Quit Claim; Joint Municipal Assessor; MENRO 36 Rehab of ALBAPA FMR NSAC 7 30-Mar-11 6 Negros Occidental Valladolid Bayabas; Alijis; Pacol PP 100% completed Quit Claim 3 3 6 RP P 540.00 5,500.00 6,040.00 Certificate completed Deed of Conveyance/Quit Claim with BIR Zonal Valuation; MAO 37 Const of Salvacion-Langit FMR NSAC 4 16-Mar-10 8 Leyte Alangalang Salvacion; Langit PP 100% completed Deed of Donation/ Deed of Donation 6 4 10 RP P 56,727.00 130,779.60 187,506.60 Certification completed Petrolio; Malobago; Kawayanan; Tuburan;Kawayanan; Tuburan; Kawayan; Affidavit of Claimant with Deed of 38 Rehabilitation of Petrolio-Villanueva FMR NSAC 30 22-Mar-13 8 Leyte Calubian Bugtongang, Villanueva 100% completed Conveyance 1 1 2 P 30,000.00 0.00 30,000.00

NAPOCOR; Provincial 39 Rehab of Visares-Balugo FMR NSAC 2 16-Oct-09 8 Leyte Capoocan Visares; Balugo 100% completed Joint Affidavit of Joint Claim 5 4 9 RP P 0.00 12,368.11 12,368.11 Assessor's Valuation Deed of Conveyance/Quit Claim with 40 Const of Manlilisid-San Sotero FMR NSAC 6 27-Jan-11 8 Leyte Javier Manlilisid; San Sotero PP 100% completed Deed of Donation 4 4 8 P 22,909.29 0.00 22,909.29 Assessor's Market Value completed Deed of Conveyance/Quit Claim with 41 Concreting of San Sotero-Ulhay FMR NSAC 18 18-May-12 8 Leyte Javier San Sotero; Ulhay PP 100% completed Deed of Donation 7 2 9 P 0.00 25,200.00 25,200.00 MAO and PCA Certification completed Deed of Conveyance/Quit Claim with 42 Concreting of Zone 1-Pinocawan-Bonifacio-Talisayan FMR NSAC 18 18-May-12 8 Leyte Javier Zone 1; Pinocawan; A. Bonifacio; Talisayan PP 100% completed Deed of Donation 24 P 0.00 89,300.00 89,300.00 PCA Certification Deed of Conveyance/Quit Claim with 43 Concreting of Odiong-Guindapunan FMR NSAC 19 07-Jun-12 8 Leyte Javier Odiong; Guindapunan PP 100% completed Deed of Donation 8 3 11 0.00 14,000.00 14,000.00 MAO and PCA Certification completed Deed of Conveyance/Quit Claim with 44 Concreting of San Sotero-Caraye FMR NSAC 20 05-Jul-12 8 Leyte Javier Caraye; San Sotero P 100% completed Deed of Donation 12 6 18 0.00 27,600.00 27,600.00 MAO and PCA Certification Deed of Conveyance/Quit Claim with 45 Concreting of Laray-Magsaysay-Malitbogay FMR NSAC 23 14-Sep-12 8 Leyte Javier Laray; Magsaysay; Malitbogay 100% completed Deed of Donation 10 7 17 0.00 94,000.00 94,000.00 MAO and PCA Certification

Schedule of Base Unit Market 46 Concreting of Sitio Km. 14-Sitio Torrel, Brgy. Masarayao FMR NSAC 21 31-Jul-12 8 Leyte Kananga Masarayao PP 100% completed Deed of Donation 7 4 11 RP P 86,081.74 120,336.00 206,417.74 Values completed Deed of Reconveyance/Quit Claim with 47 Const of San Agustin-Capirawan-Cangubang FMR NSAC 2 16-Oct-09 8 Leyte Palo San Agustin; Capirawan; Cangumbang PP 100% completed Deed of Donation; Deed of 17 7 24 RP P 571,600.00 123,464.80 695,064.80 BIRProvincial/Municipal Zonal; MAO Certification Assessor's completed Deed of Conveyance/Quit Claim with valuation, MAO valuation and 48 Construction of Capirawan-Gacao-Canhidoc-Arado FMR NSAC 33 17-Jul-13 8 Leyte Palo Capirawan; Canhidoc; Gacao; Arado PP 100% completed Deed of Donation 11 9 20 6,326.10 130,309.60 136,635.70 BIR Zonal valuation 49 Const/Improv of Brgy. Crossing-Brgy. Biasong FMR NSAC 3 19-Nov-09 8 Leyte San Isidro Brgy. Crossing; Biasong PP 100% completed Deed of Conveyance with Quit Claim 28 8 36 RP P 225,866.45 26,226.60 252,093.05 BIR Zonal; MAO Certification completed Declaration of Ownership and Voluntary Undertaking of Commitment with Deed Municipal Assessor, MAO and 50 Rehabilitation of Bawod-Paril FMR NSAC 33 17-Jul-13 8 Leyte San Isidro Bawod; Paril PP 100% completed of Donation 7 2 9 8,400.00 15,400.00 23,800.00 MPDC completed INVOLUNTARY RESETTLEMENT NSAC/RSAC SUBPROJECT TITLE PROVINCEMUNICIPALITY Barangay Physical Status DATE MASTERLIST Summary of Affected Land and PAPs MINUTES OF MEETING (W/ RIGHT OF WAY DOCUMENTATION

REGION LEGAL DOCS LEGAL DOC(S) EXECUTED RP/SDR OF PAPS Improvements/Livelihood ATTENDANCE SHEET) MALE FEMALE TOTAL LAND IMPROVEMENTS TOTAL PROOF OF VALUATION

(ROW) - Permit to Enter Construct and 51 Canmogsay-Capangihan PWS LII NSAC 28 29-Nov-12 8 Leyte Tolosa Capangihan; Canmogsay PP 100% completed Operate 2 2 4 P 0.00 0.00 0.00 completed

Deed of Conveyance/Quit Claim with Schedule of Base Unit Market 52 Rehab of Casili-on-Sambulawan FMR NSAC 6 27-Jan-11 8 Leyte Villaba Casili-on; Sambulawan PP 100% completed DeedAffidavit of ofDonation Possession with Quit Claim; 9 5 14 RP P 3,981.09 6,550.18 10,531.27 Values completed Deed of Donation with Quit Claim; 53 Const of Sitio Balukawe-Balat Balud FMR NSAC 6 27-Jan-11 8 Northern Samar Bobon Salvacion; Balat Balud PP 100% completed DeclarationAffidavit of Claimant; of Ownership Deed and of AbsoluteVoluntary 6 3 9 RP P 4,821.60 36,532.80 41,354.40 Provincial Assessor's Valuation completed Undertaking of Commitment; Deed of 54 Const of Brgy. Cagamutan-Bato-Bangon FMR with Bridge NSAC 6 27-Jan-11 8 Northern Samar Gamay Cagamutan; Bato; Bangon PP 100% completed Conveyance with Sale and Deed of 15 4 19 RP P 48,156.96 32,830.00 80,986.96 Provincial Assessor's Valuation completed Deed of Conveyance with Sale and Value of Real Property; 55 Concreting of Bangon-G.M. Osias FMR NSAC 40 29-Apr-15 8 Northern Samar Gamay Bangon; G.M. Osias PP 100% completed Deed of Donation 12 2 14 RP P 61,300.08 10,400.00 71,700.08 Declaration of Ownership and completed Deed of Donation with Quit Claim; Schedule of Base Unit Market 56 Concreting of Matambag-Osmeña-Bangon FMR NSAC 30 22-Mar-13 8 Northern Samar Palapag Matambag; Osmeña; Bangon P 100% completed Affidavit of Possession with Quit ClaimClaim; 37 RP P 103,892.79 171,200.00 275,092.79 Values Declaration of Ownership and Voluntary Schedule of Base Unit Market 57 Concreting of San Juan to Entapatan FMR NSAC 27 16-Nov-12 8 Northern Samar San Isidro San Juan 100% completed Undertaking of Commitment; Deed of 30 RP P 100,414.55 323,175.00 423,589.55 Values completed Deed of Donation with Quit Claim; Provincial/Municipal Assessor's 58 Const of Inilian-Galutan-Burac-Coroconog-Himabug-at FMR NSAC 17 20-Apr-12 8 Northern Samar San Roque Balud; Coroconog; Balnasan PP 100% completed AffidavitDeclaration of Possession of Ownership with and Quit Voluntary Claim 13 6 19 RP P 8,646.85 83,485.00 92,131.85 Valuation completed Undertaking of Commitment; Deed of 59 Const of Brgy. 3 to Brgy. 1 FMR NSAC 4 16-Mar-10 8 Eastern Samar Balangiga Brgy. 1; Brgy. 3 PP 100% completed Conveyance with Deed of Donation 10 7 17 RP P 47,919.08 58,888.00 106,807.08 Provincial Assessor's Valuation completed Deed of Donation; Declaration of Ownership and Voluntary Undertaking Municipal Assessor's 60 Const of Brgy. San Miguel FMR NSAC 18 18-May-12 8 Eastern Samar Balangiga San Miguel PP 100% completed of Commitment 12 4 16 RP P 100,756.00 97,844.00 198,600.00 Certification 61 Rehab and Const of Guinpoliran-Bangon-Cantubi FMR (Section 1) NSAC 16 30-Mar-12 8 Eastern Samar Balangkayan Guinpoliran; Bangon; Cantubi PP 100% completed Deed of Donation with Quit Claim 2 3 5 RP P 21,045.42 31,166.00 52,211.42 Provincial Assessor's Valuation PP Deed of Donation with Quit Claim P Provincial Assessor's Valuation 62 Concreting of Jumalag-Magsaysay FMR (Section 2) NSAC 16 30-Mar-12 8 Eastern Samar Balangkayan Jumalag; Magsaysay 100% completed 2 3 5 RP Provincial Assessor's Valuation; completed Deed of Donation with Quit Claim; Deed Municipal Agriculturist of Conveyance with Sale; Declaration of Certification; MPDC 63 Rehab/Const of Barangay 8-San Isidro FMR NSAC 3 19-Nov-09 8 Eastern Samar Lawaan Brgy. 8 Poblacion; San Isidro PP 100% completed Heirship with Special Power of Attorney 29 10 39 RP P 0.00 109,300.20 109,300.20 Certification Schedule of Market Value for all Agricultural Lands for Deed of Donation with Quit Claim; Deed Eastern Samar; Municipal 64 Concreting of Barangay Taguite FMR NSAC 26 30-Oct-12 8 Eastern Samar Lawaan Taguite 100% completed of Conveyance with Sale 11 4,452.10 24,302.00 28,754.10 Assessor's Valuation 65 Construction with Spot Concreting of San Miguel-Babanikhon-Macaanga FMRNSAC 29 19-Dec-12 8 Eastern Samar Llorente Babanikhon; Macaanga; San Miguel P 100% completed Deed of Donation with Quit Claim 19 10 29 P 0.00 96,576.00 96,576.00 Assessor's Market Value Schedule of Market Value for all Agricultural Lands for 66 Concreting of San Pedro-Palactad FMR with 6.65 LM Flat Slab Bridge NSAC 28 29-Nov-12 8 Eastern Samar Quinapondan San Pedro; Rizal; Palactad 100% completed Deed of Conveyance with Sale 25 0.00 37,284.00 37,284.00 Eastern Samar completed Deed of Conveyance with Sale and Deed of Donation; Waiver of Right/Quit Office of the Municipal 67 Rehab of Casilion-Tagbacan-Taclaon-Sta. Cruz FMR NSAC 6 27-Jan-11 8 Eastern Samar Salcedo Casilion; Tagbacan; Taclaon; Sta. Cruz PP 100% completed Claim 44 18 62 RP P 0.00 69,818.00 69,818.00 Agriculturist Deed of Conveyance with Sale and 68 Concreting of Cagaut-Cantomoja-Camanga-Carapdapan FMR NSAC 33 17-Jul-13 8 Eastern Samar Salcedo Cagaut; Cantomoja;Camanga;Carapdapan 100% completed Deed of Donation 7 5 12 6,594.00 9,500.00 16,094.00

Provincial Valuation; Municipal 69 Const of Casoroy-Layog FMR NSAC 3 19-Nov-09 8 Eastern Samar San Julian Casoroy PP 100% completed Deed of Donation with Quit Claim 15 5 20 RP P 72,902.15 52,258.00 125,160.15 Assessor's Certificate completed

70 Const of Panaw-nawan-Magti-aw FMR NSAC 15 01-Mar-12 8 Eastern Samar San Julian Campidhan; Nena; Libas PP 100% completed Deed of Donation with Quit Claim 12 4 16 RP P 21,101.00 5,316.00 26,417.00 Provincial Assessor's Valuation Deed of Conveyance with Deed of Donation; Deed of Conveyance with Municipal Assessor's 71 Rehab of Sta. Cruz-Bangon FMR NSAC 5 12-Jul-10 8 Eastern Samar San Policarpo Sta. Cruz; Bangon PP 100% completed Sale 1 10 11 RP 84,713.86 106,970.00 191,683.86 Certification

Joint Quit Claim; Deed of Conveyance 72 Const of Lumatod-Danao FMR with 20 LM RCDG Bridge NSAC 6 27-Jan-11 8 Eastern Samar Taft Lumatod; Danao; Del Remedios 100% completed with Donation; Deed of Donation 4 4 8 RP P 13,024.00 10,680.00 23,704.00 Provincial Assessor's Valuation Municipal Assessor's Valuation; Municipal Agricultural Officer 73 Const of Poblacion-Costa Rica II FMR NSAC 25 19-Oct-12 8 Western Samar Almagro Poblacion; Malobago; Rono; Tonga-Tonga; Lunang;P Talahid; Costa Rica 100% completed Joint Quit Claim with compensation 13 RP P 206,910.44 1,551,440.00 1,758,350.44 Valuation completed Deed of Donation of Real Property and Municipal Assessor's 74 Const of Cogon-Cancaiyas-Villa Aurora FMR NSAC 15 01-Mar-12 8 Western Samar Basey Cogon; Cancaiyas, Villa Aurora PP 100% completed Land Improvements 70 RP P 0.00 214,270.00 214,270.00 Certification; Bill of Materials completed

Deed of Conveyance with Sale and Provincial Assessor's Valuation; 75 Const of Bacyaran-Bulao-Canbagtic-San Mauricio FMR NSAC 5 12-Jul-10 8 Western Samar Calbiga Bacyaran; Bulao; Canbagtic; San Mauricio PP 100% completed Deed of Donation 40 19 59 attendance sheet only 0.00 486,690.00 486,690.00 CENRO Certification completed 76 Construction of Calbiga Upland Barangay PWS NSAC 30 22-Mar-13 8 Western Samar Calbiga Borong; Hubasan; Mahangcao; Macaalan; Panayuran 100% completed Permit to Enter, Construct and Operate 1 0 1 0.00 0.00 0.00 Deed of Absolute Sale; Extrajudicial Settlement of Estate with Absolute Sale of a Portion of Registered Land; 77 Const of Mabini-Mayahay-San Roque FMR NSAC 1 2-Sep-09 8 Western Samar Daram Mabini; Mayabay; San Roque PP 100% completed Affidavit of Claimant 12 8 20 RP P 478,895.00 47,190.00 526,085.00 Provincial Assessor's Valuation completed Affidavit of Possession; Affidavit of 78 Const of Poblacion 02-Talisay FMR NSAC 11 4-Nov-11 8 Western Samar Daram Talisay; Poblacion 02 PP 100% completed Claimant 18 P 243,124.00 131,921.00 375,045.00 Provincial Assessor's Valuation completed Affidavit of Claimant; Affidavit of Possession; Deed of Donation with Quit 79 Const of Mabini-Astorga-San Vicente-Bono-anan FMR NSAC 26 30-Oct-12 8 Western Samar Daram Mabini; Ubo; Birawan; Astorga; Marupangdan; San Vicente; Bono-anon 100% completed Claim 36 506,448.00 439,394.00 945,842.00 completed Provincial Assessor's Valuation; Municipal Assessor's 80 Const of Sta. Rita FMR NSAC 15 01-Mar-12 8 Western Samar Marabut Sta. Rita; Malobago; Pinamitinan PP 100% completed Joint Quit Claim 19 1 20 RP P 157,282.00 265,258.10 422,540.10 Certification; Bill of Materials

Affidavit of Possession and Easement of ROW, Affidavit of Claimant (for 81 Const of Nabong-Loctob-Catigawan-Lawaan-Pahug FMR NSAC 3 19-Nov-09 8 Western Samar Pinabacdao Nabong; Loctob; Catigawan; Lawaan; PahugPP 100% completed improvements) 31 RP P 0.00 57,742.00 57,742.00 Provincial Assessor's Valuation Municipal Assessor's 82 Const of Ilo-Balud Circumferential ARC FMR NSAC 24 27-Sep-12 8 Western Samar Sta. Margarita Balud; Ilo P 100% completed Joint Quit Claim 21 8 29 RP P Certification; Bill of Materials Deed of Covenyance/Declaration of Ownership and Voluntary Undertaking 83 Const/Rehab of Villareal ARC FMR NSAC 4 16-Mar-10 8 Western Samar Villareal Canmucat; Nagcaduha; Macopa; Conant 100% completed of Commitment 7 5 12 RP submitted; no attendance sheet 32,694.20 28,710.00 61,404.20 Provincial Assessor's Valuation completed 84 Construction of Nonoyan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Balaguian 100% completed Deed of Donation 3 0 3 completed 85 Construction of Mamad Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Balaguian 100% completed Deed of Donation 3 0 3 completed 86 Construction of Lumay Solar Dryer RSAC 8 6-Jul-12 9 Zamboanga del Norte Balaguian 100% completed Deed of Sale of a Parcel of Land 0 1 1 completed 87 Construction of Poblacion Multi-Purpose Center RSAC 8 6-Jul-12 9 Zamboanga del Norte Balaguian 100% completed Deed of Sale of a Portion of a Registered Parcel0 of Land 1 1 completed 88 Construction of Kauswagan Multi-Purpose Center RSAC 8 6-Jul-12 9 Zamboanga del Norte Balaguian 100% completed Deed of Absolute Sale 1 0 1 completed 89 Concreting of Sitio Jiay-Sitio Sibulan Bgy. Balas FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Labason Balas P 100% completed Joint Quit Claim 13 7 20 0.00 0.00 0.00 legal doc- 100%; Affidavit Executed by ISF beneficiaries (3 PAPs) allowing use of reservoir and intake, Written Cosent 90 Construction of Upper Gabu PWS 2 RSAC 1 18-Jun-10 9 Zamboanga del Norte Labason of ROW signed by all PAPs (33) 36 P completed INVOLUNTARY RESETTLEMENT NSAC/RSAC SUBPROJECT TITLE PROVINCEMUNICIPALITY Barangay Physical Status DATE MASTERLIST Summary of Affected Land and PAPs MINUTES OF MEETING (W/ RIGHT OF WAY DOCUMENTATION

REGION LEGAL DOCS LEGAL DOC(S) EXECUTED RP/SDR OF PAPS Improvements/Livelihood ATTENDANCE SHEET) MALE FEMALE TOTAL LAND IMPROVEMENTS TOTAL PROOF OF VALUATION

91 Construction of Upper Gabu Early Child Care Development Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason NA NA 100% completed Deed of Donation 1 0 1 completed 92 Construction of Balas Early Child Care Development Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason NA NA 100% completed Deed of Sale 1 0 1 completed 93 Construction of Sitio Sawi Early Child Care Development Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason 100% completed Deed of Donation 0 1 1 completed 94 Construction of Sitio Jaivy Early Child Care Development Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason NA NA 100% completed Deed of Donation with Quit Claim 0 1 1 completed 95 Construction of Sitio Sibulan Early Child Care Development Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason NA NA 100% completed Deed of Donation with Quit Claim 0 1 1 completed 96 Construction of Balas Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason NA NA 100% completed SB Res. No. 139 S 1992; Ordinance No. 98-00340 0 0 completed 97 Construction of Sibulan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason NA NA 100% completed DENR FMB No. 24-1 0 0 0 completed 98 Construction of Lawigan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason 100% completed 1992 completed 99 Construction of Lawigan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason 100% completed 1992 completed 100 Construction of Balas Barangay Health Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason NA NA 100% completed Deed of Sale 1 0 1 completed 101 Construction of Sibulan Barangay Health Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason NA NA 100% completed Deed of Donation with Quit Claim 0 1 1 completed 102 Construction of Lawigan Barangay Health Center RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason NA NA 100% completed Deed of Donation 1 0 1 completed 103 Construction of Balas Multi-purpose Pavement RSAC 5 18-Apr-12 9 Zamboanga del Norte Labason 100% completed Deed of Donation with Quit Claim 0 1 1 completed 104 Concreting of Motibot-Sto. Rosario FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Sindangan Sto. Rosario P 100% completed Joint Quit Claim 18 10 28 0.00 0.00 0.00 105 Construction of Motibot Solar Dryer RSAC 3 16-Sep-11 9 Zamboanga del Norte Sindangan 100% completed Deed of Donation with Acceptance 1 0 1 completed 106 Construction of Nipaan Solar Dryer RSAC 8 6-Jul-12 9 Zamboanga del Norte Sindangan 100% completed Deed of Donation 0 1 1 completed 107 Rehabilitation of Lituban CIS NSAC 34 06-Sep-13 9 Zamboanga del Norte Siocon P 100% completed Joint Quit Claim 31 8 39 0.00 0.00 0.00 completed

108 Concreting of JNR Pangian-Greenridge FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Siocon Pangian P 100% completed Joint Quit Claim 22 6 28 0.00 0.00 0.00 completed 109 Construction of Panabutan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Sirawai 100% completed Deed of Donation completed 110 Construction of Catuyan Elementary School Building RSAC 5 18-Apr-12 9 Zamboanga del Norte Sirawai 100% completed Deed of Donation completed 111 Construction of Sipakit FMR RSAC 8 6-Jul-12 9 Zamboanga del Norte Sirawai completed 112 Rehabilitation of Sagrada Familia CIS NSAC 31 26-Apr-13 9 Zamboanga del Sur Aurora 100% completed Permit to Enter 7 2 9 113 Construction of Mahayahay Waterworks System RSAC 8 6-Jul-12 9 Zamboanga del Sur Aurora Deed of Donation of Real Property completed 114 Construction of Legarda Uno Farmers Multi-purpose Center RSAC 8 6-Jul-12 9 Zamboanga del Sur Dinas Legarda Uno completed Municipal Assessor's 115 Const of Maralag-Libertad FMR NSAC 3 19-Nov-09 9 Zamboanga del Sur Dumingag Maralag; Libertad PP 100% completed Joint Quit Claim 9 2 11 PRP P 0.00 36,324.00 36,324.00 Certification completed Municipal Assessor's 116 Rehab of Nopulan-Bogo-Calabat FMR NSAC 2 16-Oct-09 9 Zamboanga del Sur Josefina Nopulan; Bogo Calabat PP 100% completed Joint Quit Claim 1 0 1 SDR P 0.00 1,200.00 1,200.00 Certification completed Deed of Conveyance/ Quit Claim with Municipal Agriculturist and 117 Rehab of Brgy. Moradje-Ebarle FMR NSAC 18 18-May-12 9 Zamboanga del Sur Josefina Moradje; Ebarle PP 100% completed Deed of Donation 5 2 7 RP P 0.00 103,400.00 103,400.00 Municipal Assessor's valuation completed 118 Rehab/Concreting of Brgy. Moradje-Tagaytay-Dawa FMR NSAC 24 27-Sep-12 9 Zamboanga del Sur Josefina Dawa; Moradje; Tagaytay P 100% completed Joint Quit Claim 31 RP P 0.00 63,054.00 63,054.00 completed 119 Rehabilitation of Guipos CIS NSAC 34 06-Sep-13 9 Zamboanga del Sur Guipos Balangating, Poblacion PP 100% completed Deed of Donation with Quit Claim 8 10 18 RP P 74,450.00 0.00 74,450.00 Waiver of Rights/Quit Claim; Deed of Donation;Declaration of Heirship with Schedule of Fair Market 120 Const of Junction Poblacion Kumalarang-Bualan FMR NSAC 11 4-Nov-11 9 Zamboanga del Sur Kumalarang Poblacion; Bualan PP 100% completed Special Power of Attorney 15 3 18 P 89,455.68 135,141.36 224,597.04 Values; MAO Certification completed 121 Construction of 1 Unit Tribal Hall Building RSAC 9 4-Feb-13 9 Zamboanga del Sur Kumalarang completed

Municipal Assessor's Valuation; 122 Const/Improv of Bualan-Maruing-Pampang-Poblacion Lapuyan FMR NSAC 12 18-Nov-11 9 Zamboanga del Sur Lapuyan Pingalay; Maruing; Pantad; Pampang; Poblacion;PP Tipasan 100% completed Joint Quit Claim 73 28 101 P 0.00 473,654.00 473,654.00 MAO Certification completed MAO Certification; Municipal 123 Const of Balamban-San Jose-Tumapic FMR with RCDG Bridge NSAC 2 16-Oct-09 9 Zamboanga del Sur Mahayag Tumapic; San Jose; Balamban PP 100% completed Joint Quit Claim 32 14 46 RP 0.00 366,710.00 366,710.00 Assessor's Certification completed Municipal Assessor's 124 Concreting of Bgy. Lower Salug Dako-Balamban-San Jose DCM FMR NSAC 24 27-Sep-12 9 Zamboanga del Sur Mahayag Balamban; DCM; Lower Salug; San Jose PP 100% completed Joint Quit Claim 20 0.00 9,824.00 9,824.00 Certification; Bill of Materials completed 125 Construction-Rehabilitation-Concreting of Bgy. DCM FMR NSAC 24 27-Sep-12 9 Zamboanga del Sur Mahayag DCM PP 100% completed Joint Quit Claim 5 1 6 0.00 91,728.00 91,728.00 Municipal Assessor's Valuation 126 Const of Bgy. Lower Sto. Niño FMR NSAC 26 30-Oct-12 9 Zamboanga del Sur Mahayag Lower Sto. Niño PP 100% completed Joint Quit Claim 33 432,941.04 348,301.11 781,242.15 Municipal Assessor's Valuation; 127 Const of Tipasan-Tulapok-Poblacion FMR NSAC 11 4-Nov-11 9 Zamboanga del Sur Margosatubig Tulapok; Tiguian; Poblacion PP 100% completed Deed of Donation 9 2 11 RP P 37,209.12 40,664.00 77,873.12 Schedule of Fair Market Values completed Deed of Donation; Affidavit of Municipal Assessor's Valuation; 128 Const of Brgy. Buloron-Dumalinao FMR NSAC 16 30-Mar-12 9 Zamboanga del Sur Midsalip Buloron; Dumalinao PP 100% completed Possession and Joint Quit Claim 15 3 18 RP P 235,962.30 92,306.00 328,268.30 Bill of Materials completed Provincial Assessor's Valuation; Municipal Assessor's 129 Concreting of Buloron-Lumponid FMR NSAC 17 20-Apr-12 9 Zamboanga del Sur Midsalip Buloron; Lumponid PP 100% completed Deed of Donation; Waiver 53 RP P 74,528.85 236,741.40 311,270.25 Certification; Bill of Materials completed

130 Const of Culo FMR NSAC 18 18-May-12 9 Zamboanga del Sur Molave Culo PP 100% completed Deed of Donation with Quit Claim 7 1 8 RP 44,437.25 17,195.47 61,632.72 Land Bank Valuation completed Municipal Assessor's Valuation; 131 Concreting of Purok Jupiter (Basay)-Purok Venus FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Molave Rizal P 100% completed Joint Quit Claim 11 P 0.00 33,570.00 33,570.00 Bill of Materials completed Municipal Assessor's Valuation; 132 Concreting of Purok Ferry-Purok Happy Valley FMR NSAC 21 31-Jul-12 9 Zamboanga del Sur Molave Miligan 100% completed Joint Quit Claim 10 0.00 14,016.00 14,016.00 Bill of Materials completed

133 Concreting of Limonan-Kabogkabog FMR NSAC 33 17-Jul-13 9 Zamboanga del Sur San Miguel Limonan; Kabogkabog PP 100% completed Joint Quit Claim 14 5 19 RP P 0.00 76,638.00 76,638.00 Municipal Assessor's valuation Municipal/ Provincial Assessor's 134 Concreting of Tanducan-Tambunan FMR NSAC 18 18-May-12 9 Zamboanga del Sur Tabina Poblacion; Malim PP 100% completed Joint Quit Claim 8 RP P 0.00 5,212.00 5,212.00 Valuation Provincial Assessor's Valuation; Deed of Donation; Deed of Donation Municipal Assessor's 135 Rehab of Gabunon-Bag-ong Tabugon FMR NSAC 5 12-Jul-10 9 Zamboanga del Sur Tambulig Gabunon;Tuluan; Libato; Bag-ong Tabugon PP 100% completed with Quit Claim 45 31 76 RP P 48,317.09 147,850.00 196,167.09 Certification; MAO Certification completed Municipal/ Provincial Assessor's 136 Concreting of Lower Lodiong-Limamaan FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Tambulig Lower Lodiong; Limamaan 100% completed Deed of Donation with Quit Claim 12 6 18 4,272.00 6,000.00 10,272.00 Valuation completed Municipal/ Provincial Assessor's 137 Concreting of Junction Limamaan-Upper Lodiong FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Tambulig Upper Lodiong; Limamaan; Tuluan P 100% completed Deed of Donation with Quit Claim 18 11 29 5,137.08 38,000.00 43,137.08 Valuation completed 138 Rehab w/ Spot Concreting of Limamaan FMR NSAC 22 24-Aug-12 9 Zamboanga del Sur Tambulig Limamaan 100% completed Deed of Donation with Quit Claim 9 3 12 2,563.20 40,155.50 42,718.70 Provincial Assessor's Valuation completed Deed of Sale; Municipal 139 Rehab/Improv of Guinlin-Limas FMR NSAC 1 2-Sep-09 9 Zamboanga del Sur Tigbao Guinlin; Limas PP 100% completed Deed of Donation; Deed of Sale 11 0 11 RP P 13,560.00 33,426.00 46,986.00 Assessor's Valuation completed Sangguniang Barangay Resolution No. 44, Series of 2009 140 Const of BegCaLLi ARC Health Station NSAC 2 16-Oct-09 9 Zamboanga del Sur Tigbao Begong allocating 200 sq.m. of land for the subproject. Sangguniang Barangay Resolution 0 0 0 16,000.00 0.00 16,000.00 BIR Zonal Valuation completed Municipal Assessor Certification following Schedule of Market Values for all Agricultural Lands for 141 Concreting of Begong-Limas FMR NSAC 25 19-Oct-12 9 Zamboanga del Sur Tigbao Begong; Limas PP 100% completed Deed of Donation 18 6 24 237,462.00 17,957.00 255,419.00 Zamboanga del Sur

142 Const with 1.248 Concreting of Alindahaw-Panduma Sr.-Camanga FMRNSAC 20 05-Jul-12 9 Zamboanga del Sur Tukuran Alindahaw; Panduma Sr.; Camanga 100% completed Deed of Donation 24 82,517.76 15,540.00 97,967.76 completed 143 Const of Maasin & Tiayon PWS Level II NSAC 25 19-Oct-12 9 Zamboanga Sibugay Ipil Maasin; Tiayon PP 100% completed Deed of Donation with Quit Claim 6 2 8 RP 16.12 0.00 16.12 Municipal Assessor's Valuation completed Sole Declaration of Heirship with Quit P Claim and/or Waiver of Right and Provincial Assessor's Valuation 144 Concreting of Poblacion-Ligaya FMR NSAC 25 19-Oct-12 9 Zamboanga Sibugay Mabuhay Ligaya; Poblacion 100% completed Declaration of Ownership with Quit 9 6 15 RP 52,402.40 790.00 53,192.40 completed Claim and Waiver of Rights and/or 145 Const of Sitio Tuburan-Malinao FMR NSAC 25 19-Oct-12 9 Zamboanga Sibugay Mabuhay Malinao; Poblacion P 100% completed Interest of a Portion of Unregistered 6 7 13 RP 58,128.00 28,440.00 86,568.00 Provincial Assessor's Valuation

146 Rehab of Tambanan-Sulo FMR NSAC 18 18-May-12 9 Zamboanga Sibugay Naga Tambanan; Sulo 100% completed Affidavit of Quit Claim/ Waiver of Rights 1 0 1 0.00 0.00 0.00 completed INVOLUNTARY RESETTLEMENT NSAC/RSAC SUBPROJECT TITLE PROVINCEMUNICIPALITY Barangay Physical Status DATE MASTERLIST Summary of Affected Land and PAPs MINUTES OF MEETING (W/ RIGHT OF WAY DOCUMENTATION

REGION LEGAL DOCS LEGAL DOC(S) EXECUTED RP/SDR OF PAPS Improvements/Livelihood ATTENDANCE SHEET) MALE FEMALE TOTAL LAND IMPROVEMENTS TOTAL PROOF OF VALUATION

Bill of Materials; Provincial 147 Rehab with Spot Concreting of Balungisan-Guiwan FMR NSAC 6 27-Jan-11 9 Zamboanga Sibugay Payao Balungisan; La Fortuna; Calape; Kulasian; Bulawan;PP Guiwan 100% completed Deed of Donation with Quit Claim 150 RP P 0.00 560,352.00 560,352.00 Assessor completed Municipal/ Provincial Assessor's 148 Concreting of Balungisan-Upper Sumilong FMR NSAC 35 18-Oct-13 9 Zamboanga Sibugay Payao Balungisan; Upper Sumilong 100% completed Deed of Donation with Quit Claim 15 174,090.00 179,356.00 353,446.00 Valuation completed 149 Const of Flood Control Protection Dike cum FMR NSAC 21 31-Jul-12 9 Zamboanga Sibugay Siay Lagting P 100% completed Deed of Donation 21 P 127,392.00 0.00 127,392.00 BIR Zonal Valuation 150 Rehab of Culasian-Supit FMR NSAC 1 2-Sep-09 9 Zamboanga Sibugay Titay Culasian; Supit 100% completed Quit Claim 20 8 28 0.00 33,748.00 33,748.00 Quit Claim completed 151 Concreting of Brgy. Dado Poblacion-Sitio Matampay Bagoaingud FMR NSAC 37 18-Feb-14 14 Lanao del Sur Balindong Dado 100% completed Joint Quit Claim; Deed of Donation 23 5 28 0.00 358,000.00 358,000.00 FMV completed 152 Construction of Dado ARC PWS LII NSAC 37 18-Feb-14 14 Lanao del Sur Balindong Dado 100% completed, w/ SB Reso Joint Quit Claim; Deed of Donation 16 3 19 0.00 241,000.00 241,000.00 FMV completed 153 Construction of Health Center Building (Brgy. Polayagan) NSAC 37 18-Feb-14 14 Lanao del Sur Bubong Polayagan 100% completed, w/ SB Reso Deed of Transfer of Rights and Quit Claim 1 0 1 154 Construction of Multi-Purpose Building with Solar Dryer (Brgy. Salipongan)NSAC 37 18-Feb-14 14 Lanao del Sur Bubong Salipongan 100% completed Deed of Transfer of Rights and Quit Claim 1 0 1 155 Concreting of Sumogot FMR NSAC 18 18-May-12 14 Lanao del Sur Bumbaran Sumogot P 100% completed Joint Deed of Donation with Quit Claim 9 0 9 59,342.00 0.00 59,342.00 Declaration of Real Property Joint Quit Claim; Affidavit of Possession 156 Const of Barit-Taliogon-Tabuan FMR NSAC 4 16-Mar-10 14 Lanao del Sur Ganassi Taliogon; Tabuan 100% completed with Quit Claim 24 4 28 0.00 581,115.00 581,115.00 Provincial Assessor's Valuation completed Affidavit of Possession with Easement of Schedule of Base Unit Market 157 Concreting and Rehab of Taganonok-Taliogon-Paraaba FMR NSAC 18 18-May-12 14 Lanao del Sur Ganassi Campongaraya; Taganonok;Taliogon; ParaabaPP 100% completed Road ROW 27 2 29 231,780.00 279,820.00 511,600.00 Value

158 Construction of Masolun-Taganonok-Taliogon FMR NSAC 35 18-Oct-13 14 Lanao del Sur Ganassi Masolun; Taganonok; Taliogon PP 100% completed Deed of Donation 2 1 3 8,640.00 33,960.00 42,600.00 Municipal Assessor's Valuation

159 Construction of Campongraya PWS - Level II NSAC 35 18-Oct-13 14 Lanao del Sur Ganassi Masolun; Taganonok; Taliogon PP 100% completed Deed of Donation 3 1 4 16,460.00 31,640.00 48,100.00 Municipal Assessor's Valuation

160 Construction of Barit PWS NSAC 36 06-Dec-13 14 Lanao del Sur Ganassi Barit PP 100% completed Deed of Donation 5 0 5 22,400.00 0.00 22,400.00 Municipal Assessor's Valuation

161 Concreting of Campongaraya-Barorao-Panggawalupa-Barit FMR NSAC 36 06-Dec-13 14 Lanao del Sur Ganassi Campongaraya; Barorao; Panggawalupa; BaritPP 100% completed Deed of Donation 11 0 11 20,590.00 0.00 20,590.00 Municipal Assessor's Valuation

162 Construction of Panggawalupa Pre-Stress Concrete Girder (PSCG) BridgeNSAC 36 06-Dec-13 14 Lanao del Sur Ganassi Panggawalupa PP 100% completed Deed of Donation 2 0 2 2,580.00 0.00 2,580.00 Municipal Assessor's Valuation

163 Concreting of Pindolonan-Pantao-Macadar FMR NSAC 35 18-Oct-13 14 Lanao del Sur Kapai Pindolonan; Pantao; Macadar P 100% completed Joint Quit Claim 23 16 39 RP 0.00 296,000.00 296,000.00 Local Market Value 164 Concreting of Pitatanglan-Wago Kabasaran & Wago-Miniros FMR NSAC 36 06-Dec-13 14 Lanao del Sur Lumbayanague Pitatanglan; Wago; Kabasaran; Miniros PP 100% completed Deed of Donation 3 0 3 0.00 0.00 0.00

Municipal Assessor Valuation; 165 Concreting of Camalig Bandaraingud-Loway Inodaran FMR NSAC 21 31-Jul-12 14 Lanao del Sur Marantao Camalig Bandaraingud; Loway Inodaran PP 100% completed Joint Deed of Donation with Quit Claim 10 2 12 165,000.00 152,300.00 317,300.00 Municipal Agriculturist 166 Concreting and Rehab of Bubong-Ragayan-Gadongan FMR NSAC 18 18-May-12 14 Lanao del Sur Poona Bayabao Bubong Dimunda; Pantao; Ragayan; Bansayan;PP Gadongan 100% completed Deed of Donation 7 0 7 0.00 0.00 0.00 167 Concreting of Dinganun-Pagalongan-Bacayawan-Lumbac FMR NSAC 35 18-Oct-13 14 Lanao del Sur Sultan DumalondongDinganun; Pagalongan; Bacayawan; LumbacP 100% completed Deed of Donation 13 2 15 0.00 0.00 0.00

Affidavit of Possession with Easement of 168 Concreting of Kinggan-Tagoloan Poblacion FMR NSAC 13 19-Dec-11 14 Lanao del Sur Tagoloan Malinao; Cadayonan 100% completed Road ROW and Quit Claim 32 0.00 156,200.00 156,200.00 Municipal Assessor Valuation 169 Const of Ganta-Gambar FMR NSAC 14 19-Jan-12 14 Maguindanao Kabuntalan Ganta; Pagalungan; Gambar P 100% completed Deed of Donation with Quit Claim 24 8 32 0.00 0.00 0.00 completed 170 Rehab of Su'uh-Kan-dayuk-Kan-ukul FMR NSAC 7 30-Mar-11 14 Sulu Panamao Kan-dayuk; Kan-ukul; Su'uh PP 100% completed Joint Quit Claim 6 0 6 0.00 6,700.00 6,700.00 Municipal Treasurer Certification completed 171 Concreting of Parian-Dakula-Lahi-Malanta FMR NSAC 13 19-Dec-11 14 Sulu Pandami Parian Dakula; Lahi; Malanta 100% completed Affidavit of Waiver of Rights 7 0.00 0.00 0.00

Notes: 66 Masterlist of PAPs column refers to the inventory of Project Affected Persons (PAPs), the check ( / ) mark means there is a masterlist of PAPs for said project Summary of Affected Land and Improvements/Livelihood refers to a matrix of affected land and improvements per PAPs, the check ( / ) mark means the LGU submittted the matrix Legal documents executed column refers to the kind of ROW legal documents signed by the PAPs, PAPs column is the summary of PAPs per subproject, gender seggregated. RP/SDR column refers to Resettlement Plan and Summary Discussion on Resettlement per subproject., those with RP means the LGU submitted said resettlement plan Minutes of Meeting with Attendance refers to minutes of meeting during consultations with the PAPs and community, the check ( / ) mark shows that the LGU submitted copy of said minutes ROW documentation column refers to the ROW cost per SP, such could either be compensated or valued only to account said ROW cost as part of the LGUs equity Proof of Valuation column refers to the basis of valuation of ROW cost computation for affected lands, improvements and livelihood ANNEX IV - D: LIST OF SUBPROJECTS ISSUED WITH CNO DAR-ADB Agrarian Reform Communities Project II As of December 2017

INDIGENOUS PEOPLE NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE CP/CNO REGION APPLICATION CP/CNO

completed 1 Rehab w/ Spot Concreting of Pag-Asa-Conrazon FMR NSAC 27 16-Nov-12 4-B Oriental Mindoro Bansud SALCEDO ARC Pag-Asa; Conrazon CNO 21-Mar-12 CNO 18-Oct-12 2 Const & Rehab w/ Spot Concreting of Laway I-Kantong Putol FMR NSAC 27 16-Nov-12 4-B Oriental Mindoro Bansud SALCEDO ARC Salcedo CNO 21-Mar-12 CNO 18-Oct-12 completed 3 Const of Sagana Health Building NSAC 26 30-Oct-12 4-B Oriental Mindoro Bongabong Bongabong Central ARC Sagana NA CNO 18-Oct-12 completed 4 Rehabilitation of Anilorcu CIS NSAC 34 06-Sep-13 4-B Oriental Mindoro Bongabong Bongabong Central ARC Anilao; Orcunoma CNO/CP 29-Apr-14 CNO 17-Oct-14 completed 5 Construction of Anilao FMR NSAC 34 06-Sep-13 4-B Oriental Mindoro Bongabong Bongabong Central ARC Anilao CNO 22-Mar-12 CNO 18-Oct-12 completed 6 Concreting of Orcunoma-Mina de Oro FMR NSAC 34 06-Sep-13 4-B Oriental Mindoro Bongabong Bongabong Central ARC Mina de Oro; Orcunoma CNO 22-Mar-12 CNO 18-Oct-12 completed 7 Rehab with Spot Concreting of San Roque-Tafarma FMR NSAC 25 19-Oct-12 4-B Oriental Mindoro Bulalacao Bulalacao ARC San Roque CNO/CP 26-Mar-12 CNO 18-Oct-12 completed 8 Rehab with Spot Concreting of Dancalan-San Roque-Libtong FMR NSAC 26 30-Oct-12 4-B Oriental Mindoro Bulalacao Bulalacao ARC San Roque CNO/CP 22-Oct-12 CNO 18-Oct-12 completed 9 Concreting of Sta. Maria-Villarosa FMR NSAC 28 29-Nov-12 4-B Oriental Mindoro Mansalay MARBRIDA ARC Sta. Maria CNO 31-Mar-12 CNO 05-Oct-12 10 Concreting of Balugo-Maliwanag FMR NSAC 28 29-Nov-12 4-B Oriental Mindoro Mansalay MARBRIDA ARC Balugo CNO 31-Mar-12 CNO 05-Oct-12 11 Construction with Spot Concreting of Sta. Brigida-Alegria FMR NSAC 28 29-Nov-12 4-B Oriental Mindoro Mansalay MARBRIDA ARC Sta. Brigida CNO 31-Mar-12 CNO 05-Oct-12

completed 12 Rehab of Balogo PWS NSAC 18 18-May-12 4-B Romblon Calatrava Balogo ARC Balogo CNO 21-Dec-11 CNO 28-Nov-12 13 Concreting of Hinag-oman-Culasi-Guin-awayan FMR NSAC 23 14-Sep-12 4-B Romblon Ferrol C.M. Recto ARC Hinag-oman CNO 27-Jun-12 CNO 23-Dec-12 completed 14 Const of Tampayan Proper Health Center NSAC 7 30-Mar-11 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Tampayan CNO 06-Dec-10 CNO 01-Jun-11 completed 15 Const of Two (2) Classrooms School Building for Tomas and Maria MaglayaNSAC Memorial 7 School 30-Mar-11 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Tampayan CNO 06-Dec-10 CNO 01-Jun-11 completed 16 Const of Tampayan/Jao-Asan PWS Level II NSAC 19 07-Jun-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Tampayan; Jao-Asan; Poblacion CNO/CP 23-Nov-11 CNO 04-Nov-13 completed 17 Rehab of Binaliwan FMR NSAC 19 07-Jun-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Tampayan CNO/CP 23-May-12 CNO 04-Nov-13 completed 18 Rehab of Cataja FMR NSAC 19 07-Jun-12 4-B Romblon Magdiwang Tampayan/Jao-asan ARC Jao-Asan CNO/CP 23-May-12 CNO 04-Nov-13 completed 19 Const of Taclobo MPB NSAC 25 19-Oct-12 4-B Romblon San Fernando Taclobo ARC Taclobo NA CNO 01-Sep-14 completed 20 Rehab of Palate FMR NSAC 9 25-Aug-11 4-B Romblon Sta. Fe Magsaysay ARC Magsaysay CNO 30-May-11 CNO 06-Aug-13 completed 21 Rehab w/ Spot Concreting of Magsaysay-Pandan FMR NSAC 21 31-Jul-12 4-B Romblon Sta. Fe Magsaysay ARC Magsaysay; Pandan CNO/CP 11-Jun-12 CNO 06-Aug-13 completed 22 Concreting of Tuaca-San Pascual FMR NSAC 11 4-Nov-11 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCTuaca; San Pascual CNO 29-Sep-11 CNO 01-Feb-13 completed 23 Concreting of Caayunan FMR NSAC 11 4-Nov-11 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCCaayunan CNO 29-Sep-11 CNO 16-Aug-12 completed 24 Concreting of San Felipe FMR NSAC 21 31-Jul-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCSan Felipe CNO/CP 26-Mar-12 CNO 08-May-13 25 Concreting of Matnog FMR NSAC 24 27-Sep-12 5 Camarines Norte Basud MATLAMALABAC ARC Matnog CNO/CP 23-Mar-12 CNO 01-Feb-13 completed 26 Const of Laniton FMR NSAC 26 30-Oct-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterLaniton CNO/CP 16-Jan-12 CNO 16-Aug-12 27 Concreting of Tuaca-San Pascual FMR (Phase II) NSAC 27 16-Nov-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterTuaca; San Pascual CNO/CP 10-Jul-12 CNO 01-Feb-13 completed 28 Concreting of San Felipe-Caayunan FMR NSAC 28 29-Nov-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterSan Felipe CNO/CP 10-Jul-12 CNO 08-May-13 completed 29 Concreting of San Felipe-Mantugawe FMR NSAC 28 29-Nov-12 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterSan Felipe CNO/CP 10-Jul-12 CNO 08-May-13 completed 30 Construction of One (1) Unit Warehouse with Office (Brgy. Laniton) NSAC 34 06-Sep-13 5 Camarines Norte Basud Basud-San Lorenzo Ruiz ARC ClusterLaniton CNO/CP 28-Feb-12 CNO 16-Aug-12 completed 31 Construction of Multipurppose Pavement (Brgy. Laniton) RSAC 5 29-Nov-11 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCLaniton CNO 15-Nov-11 CNO 16-Aug-12 completed 32 Rehabilitation of Mampili Level II Potable Water System RSAC 5 29-Nov-11 5 Camarines Norte Basud Basud-San Lorenzo Ruiz Cluster ARCMampili CNO 21-Dec-11 CNO 16-Aug-12 completed 33 Construction of Access Road for ARCCESS RSAC 7 30-Mar-12 5 Camarines Norte Basud Matnog ARC Laniton CNO 05-Mar-12 CNO 16-Aug-12 completed 34 Construction of Multipurpose Pavement/Solar Dryer in Barangay Laniton RSAC 7 30-Mar-12 5 Camarines Norte Basud Matnog ARC Laniton CNO 04-Mar-12 CNO 16-Aug-12 completed 35 Concreting of Brgy. San Martin FMR NSAC 17 20-Apr-12 5 Camarines Norte Jose Panganiban San Pedro ARC San Martin CNO 11-Jan-12 CNO 16-Aug-12 completed 36 Concreting of Brgy. San Pedro FMR NSAC 17 20-Apr-12 5 Camarines Norte Jose Panganiban San Pedro ARC San Pedro CNO 11-Jan-12 CNO 01-Feb-13 INDIGENOUS PEOPLE NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE CP/CNO REGION APPLICATION CP/CNO

37 Concreting of Brgy. Tamisan FMR NSAC 17 20-Apr-12 5 Camarines Norte Jose Panganiban San Pedro ARC Tamisan CNO 16-Jan-12 CNO 01-Feb-13 38 Concreting of Brgy. San Rafael-Sta. Rosa Norte FMR NSAC 17 20-Apr-12 5 Camarines Norte Jose Panganiban San Pedro ARC San Rafael CNO 16-Jan-12 CNO 01-Feb-13 39 Concreting of San Pedro-Bagong Silang II FMR NSAC 31 26-Apr-13 5 Camarines Norte Jose Panganiban San Pedro ARC San Pedro CNO 10-Jul-12 CNO 01-Feb-13 40 Concreting of Brgy. Tamisan FMR Phase II NSAC 35 18-Oct-13 5 Camarines Norte Jose Panganiban San Pedro ARC Tamisan CNO 01-Feb-13 41 Concreting of Macogon Barangay Road NSAC 11 4-Nov-11 5 Camarines Norte Labo Daguit ARC Macogon CNO 29-Sep-11 CNO 01-Feb-13 completed 42 Concreting of Naboongan-Igang FMR NSAC 13 19-Dec-11 5 Camarines Norte Labo Daguit ARC Daguit CNO 09-Nov-11 CNO 16-Aug-12 43 Construction of Purok 1 FMR NSAC 13 19-Dec-11 5 Camarines Norte Labo Daguit ARC Talobatib CNO 09-Nov-11 CNO 16-Aug-12 completed 44 Concreting of Purok 7 FMR NSAC 13 19-Dec-11 5 Camarines Norte Labo Daguit ARC Talobatib CNO 09-Nov-11 CNO 16-Aug-12 45 Concreting of Malangcao Basud Purok 6-Purok 7 FMR NSAC 13 19-Dec-11 5 Camarines Norte Labo Daguit ARC Malangcao CNO 09-Nov-11 CNO 16-Aug-12 completed 46 Concreting of Lugui FMR NSAC 35 18-Oct-13 5 Camarines Norte Labo Lugui ARC Lugui CNO 25-Oct-12 CNO 19-Mar-13 completed 47 Concreting of Iberica FMR NSAC 35 18-Oct-13 5 Camarines Norte Labo Lugui ARC Iberica CNO 25-Oct-12 CNO 07-Oct-13 completed 48 Concreting of San Antonio FMR NSAC 35 18-Oct-13 5 Camarines Norte Labo Lugui ARC San Antonio CNO 29-Oct-12 CNO 07-Oct-13 49 Concreting of Mabilo I FMR NSAC 35 18-Oct-13 5 Camarines Norte Labo Lugui ARC Mabilo I CNO 29-Oct-12 CNO 12-Mar-13 completed 50 Construction of Solar Dryer (Brgy. Daguit) RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Daguit CNO 15-Nov-11 CNO 01-Feb-13 completed 51 Construction of DARBO Multi-Purpose Building (Brgy. Daguit) RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Daguit CNO 15-Nov-11 CNO 16-Aug-12 completed 52 Construction of Day Care Center (Brgy. Daguit) RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Daguit CNO 15-Nov-11 CNO 16-Aug-12 completed 53 Construction of Solar Dryer (Brgy. Malangcao Basud) RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Malangcao Basud CNO 15-Nov-11 CNO 16-Aug-12 completed 54 Construction of Malangcao Basud Health Station RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Malangcao Basud CNO 15-Nov-11 CNO 16-Aug-12 completed 55 Rehabilitaion of Macogon Level II Potable Water System RSAC 5 29-Nov-11 5 Camarines Norte Labo Daguit ARC Macogon CNO 15-Nov-11 CNO 01-Feb-13 completed 56 Construction of PHF/Warehouse RSAC 7 30-Mar-12 5 Camarines Norte Labo Daguit ARC Daguit CNO 05-Mar-12 CNO 01-Feb-13 completed 57 Rehab of Matanlang-Casalugan FMR NSAC 11 4-Nov-11 5 Camarines Norte Paracale Batobalani ARC Tawig CNO/CP 29-Sep-11 CNO 16-Aug-12 completed 58 Concreting of Capacuan (Purok 1-5) FMR NSAC 11 4-Nov-11 5 Camarines Norte Paracale Batobalani ARC Capacuan CNO/CP 27-Sep-11 CNO 16-Aug-12 completed 59 Concreting of Batobalani-Igang FMR NSAC 14 19-Jan-12 5 Camarines Norte Paracale Batobalani ARC Batobalani CNO 09-Nov-11 CNO 01-Feb-13 60 Concreting of Sitio Submakin FMR NSAC 19 07-Jun-12 5 Camarines Norte Paracale Batobalani ARC Batobalani CNO 16-Jan-12 CNO 16-Aug-12 61 Const of Sitio Potot FMR NSAC 19 07-Jun-12 5 Camarines Norte Paracale Batobalani ARC Batobalani CNO 16-Jan-12 CNO 16-Aug-12 completed 62 Concreting of Batobalani-Igang FMR (Phase II) NSAC 19 07-Jun-12 5 Camarines Norte Paracale Batobalani ARC Batobalani CNO/CP 17-Feb-12 CNO 01-Feb-13 63 Concreting of Dagang-Tabas FMR NSAC 22 24-Aug-12 5 Camarines Norte Paracale Batobalani ARC Dagang CNO/CP 05-Mar-12 CNO 16-Aug-12 64 Const of Day Care Center (Brgy. Dagang) RSAC 5 29-Nov-11 5 Camarines Norte Paracale Batobalani ARC Dagang CNO 15-Nov-11 CNO 16-Aug-12 completed 65 Const of MPB (Brgy. Batobalani) RSAC 5 29-Nov-11 5 Camarines Norte Paracale Batobalani ARC Batobalani CNO 15-Nov-11 CNO 16-Aug-12 completed 66 Const of Balumbon Spring Level II Water System RSAC 5 29-Nov-11 5 Camarines Norte Paracale Batobalani ARC Dagang CNO 15-Nov-11 CNO 16-Aug-12 completed 67 Improv/Expansion of Level II Water System (Brgy. Tawig) RSAC 5 29-Nov-11 5 Camarines Norte Paracale Batobalani ARC Tawig CNO 15-Nov-11 CNO 16-Aug-12 completed 68 Const of San Isidro-Sitio Too FMR NSAC 13 19-Dec-11 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Isidro CNO 09-Nov-11 CNO 16-Aug-12 completed 69 Concreting of Matacong-San Isidro FMR NSAC 13 19-Dec-11 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC Matacong CNO 09-Nov-11 CNO 16-Aug-12 70 Concreting of Matacong-San Isidro FMR (Extension) NSAC 20 05-Jul-12 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Isidro CNO/CP 05-Mar-12 CNO 16-Aug-12 completed 71 Concreting of Purok 2 Matacong FMR NSAC 27 16-Nov-12 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC Matacong CNO/CP 17-Feb-12 CNO 16-Aug-12 completed 72 Concreting of Brgy. San Ramon FMR NSAC 40 29-Apr-15 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Ramon CNO/CP 20-Mar-15 CNO 16-Aug-12 completed 73 Const of San Ramon Day Care Center RSAC 3 15-Oct-10 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Ramon CNO 05-Oct-10 CNO 17-Sep-12 completed 74 Const of San Isidro Day Care Center RSAC 3 15-Oct-10 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Isidro CNO 05-Oct-10 CNO 17-Sep-12 completed 75 Const of Matacong Day Care Center RSAC 3 15-Oct-10 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC Matacong CNO 05-Oct-10 CNO 17-Sep-12 completed 76 Const of San Ramon MPP RSAC 3 15-Oct-10 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Ramon CNO 05-Oct-10 CNO 17-Sep-12 completed INDIGENOUS PEOPLE NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE CP/CNO REGION APPLICATION CP/CNO

77 Concreting of San Ramon, Purok 1-Purok 2 FMR RSAC 5 29-Nov-11 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Ramon CNO 15-Nov-11 CNO 16-Aug-12 completed 78 Const of SIARBECO MPB and Warehouse RSAC 5 29-Nov-11 5 Camarines Norte San Lorenzo Ruiz San Isidro ARC San Isidro CNO 15-Nov-11 CNO 16-Aug-12 completed 79 Concreting of Pinagdapian FMR NSAC 21 31-Jul-12 5 Camarines Sur Del Gallego Danawin ARC Pinagdapian CNO/CP 27-Mar-12 CNO 06-Nov-14 completed 80 Rehab/Concreting of San Juan FMR NSAC 23 14-Sep-12 5 Camarines Sur Del Gallego Danawin ARC San Juan CNO/CP 27-Mar-12 CNO 06-Nov-14 completed 81 Concreting of Peñafrancia FMR NSAC 26 30-Oct-12 5 Camarines Sur Del Gallego Danawin ARC Peñafrancia CNO/CP 28-Sep-12 CNO 06-Nov-14 completed 82 Concreting of Tomagoktok FMR NSAC 26 30-Oct-12 5 Camarines Sur Del Gallego Danawin ARC Tomagoktok CNO/CP 28-Sep-12 CNO 06-Nov-14 completed 83 Construction of Tabion FMR NSAC 31 26-Apr-13 5 Camarines Sur Del Gallego Danawin ARC Tabion CNO/CP 27-Mar-12 CNO 06-Nov-14 completed 84 Concreting of Mansalaya FMR NSAC 31 26-Apr-13 5 Camarines Sur Del Gallego Danawin ARC Mansalaya CNO/CP 27-Mar-12 CNO 06-Nov-14 completed 85 Construction of Health Center RSAC 4 15-Jun-11 5 Camarines Sur Del Gallego Danawin ARC Comadaycaday CNO 19-Jul-11 completed 86 Rehab of Ason-Poblacion FMR NSAC 1 2-Sep-09 5 Camarines Sur Garchitorena Del Pilar ARC Ason; Del Pilar CNO 05-Aug-09 87 Concreting of Bahi-Ason FMR NSAC 18 18-May-12 5 Camarines Sur Garchitorena Del Pilar ARC Bahi; Ason CNO 19-Mar-12 CNO 05-Aug-09 88 Construction of Flood Control NSAC 24 27-Sep-12 5 Camarines Sur Garchitorena Del Pilar ARC Ason CNO 19-Mar-12 CNO 05-Aug-09 89 Const of Del Pilar Multi-Purpose Pavement RSAC 3 15-Oct-10 5 Camarines Sur Garchitorena Del Pilar ARC Del Pilar CNO 10-Aug-09 completed 90 Const of Ason Multi-Purpose Pavement RSAC 3 15-Oct-10 5 Camarines Sur Garchitorena Del Pilar ARC Ason CNO 10-Aug-09 completed 91 Const of Ason 2-Classroom Building RSAC 3 15-Oct-10 5 Camarines Sur Garchitorena Del Pilar ARC Ason CNO 05-Aug-09 completed 92 Const of del Pilar Classroom Building RSAC 3 15-Oct-10 5 Camarines Sur Garchitorena Del Pilar ARC Del Pilar CNO 05-Aug-09 completed 93 Improvement of Aslong FMR RSAC 3 15-Oct-10 5 Camarines Sur Libmanan Bahay ARC CNO 03-Feb-11 completed

94 Const of Cabugao FMR NSAC 5 12-Jul-10 5 Camarines Sur Milaor Milaor ARC Cabugao CNO 26-Jan-10 CNO 04-Mar-10

95 Const and Concreting of Cabugao-Maydaso FMR NSAC 20 05-Jul-12 5 Camarines Sur Milaor Cabugao ARC Cabugao; Maydaso CNO 04-Mar-10 completed 96 Concreting of Cabugao-Mayaopayawan-San Antonio FMR NSAC 20 05-Jul-12 5 Camarines Sur Milaor Cabugao ARC Cabugao; Mayaopayawan; San Antonio CNO 04-Mar-10 completed 97 Construction of 2-Storey MultiPurpose Building in Barangay Cabugao RSAC 7 30-Mar-12 5 Camarines Sur Milaor Cabugao ARC Cabugao CNO 11-Nov-11 CNO 04-Mar-10 completed 98 Construction of 2-Storey MultiPurpose Building in Barangay San Antonio RSAC 7 30-Mar-12 5 Camarines Sur Milaor Cabugao ARC San Antonio CNO 11-Nov-11 CNO 04-Mar-10 completed 99 Construction of Solar Dryer for Bagong Sirang ARC RSAC 7 30-Mar-12 5 Camarines Sur Pili Bagong Sirang ARC CNO 20-Mar-12 CNO 01-Feb-13 completed 100 Improvement of Binobong ARC Farm to Market Road RSAC 7 30-Mar-12 5 Camarines Sur Pili Binobong ARC CNO 20-Mar-12 CNO 01-Feb-13 completed

101 Construction of 2 Storey Multi-Purpose Building RSAC 2 17-Aug-10 5 Sorsogon Casiguran Casiguran ARC A Trece Martires CNO 13-Jan-11 completed

102 Rehab/Improv of San Isidro-Nalup-an FMR NSAC 5 12-Jul-10 5 Sorsogon Castilla San Rafael Expanded ARC San Isidro CNO 07-Dec-09 CNO 13-Dec-10 completed 103 Rehabilitation of Pili CIS NSAC 31 26-Apr-13 5 Sorsogon Castilla San Rafael Expanded ARC San Isidro; San Rafael; Mayon; MaracabacCNO/CP 16-Apr-13 CNO 13-Dec-10 completed 104 Concreting of Bagsangan-Monbon FMR NSAC 17 20-Apr-12 5 Sorsogon Irosin Irosin ARC Bagsangan; Monbon CNO 19-Mar-12 CNO 24-Sep-14 105 Rehabilitation of Burabod-San Julian CIS NSAC 32 07-Jun-13 5 Sorsogon Irosin Irosin ARC CNO 24-Sep-14 106 Rehab of Sipaya-Calateo FMR NSAC 9 25-Aug-11 5 Sorsogon Juban Juban ARC Sipaya; Calateo CNO 18-Feb-11 CNO 13-Jun-11 completed 107 Concreting/Rehabilitation of Junction Tapacon-Inamyugan-Agbao-GuinhulaganNSAC FMR 37 w/ Bridge 18-Feb-14 6 Iloilo Bingawan GUINTAPAGIN ARC Tapacon; Agba-o; Guinhulacan; InamyuganCNO 16-Aug-13 CNO 28-May-15 108 Concreting of Pulao-Bulod-Sulangan FMR NSAC 34 06-Sep-13 6 Iloilo Dumangas Dumangas ARC Pulao; Sulangan CNO/CP 21-Oct-13 CNO 04-Jun-15 109 Concreting of San Andres – San Florentino FMR with Bridge NSAC 37 18-Feb-14 6 Iloilo San Rafael San Andres-San Florentino ARC San Andres; San Florentino CNO/CP 27-Mar-14 CNO 01-Jun-15 110 Rehab of Junction National Highway-Purok 5 FMR NSAC 19 07-Jun-12 6 Negros Occidental Hinoba-an Pagbana-ag ARC Asia CP 07-May-12 CNO 29-Jul-13 completed INDIGENOUS PEOPLE NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE CP/CNO REGION APPLICATION CP/CNO

111 Concreting of Brgy. Gen. Malvar Proper to Purok 1 Road NSAC 23 14-Sep-12 6 Negros Occidental Pontevedra Gen. Malvar ARC General Malvar CNO 20-Sep-10 completed

112 Const/Rehab of Brgy Proper to Purok 4 (Tamsik) Road RSAC 1 14-Dec-10 6 Negros Occidental Pontevedra General Malvar ARC General Malvar CNO 20-Sep-10 completed 113 Construction of 2-Classroom School Building with Comfort Rooms RSAC 2 31-Jul-12 6 Negros Occidental Pontevedra General Malvar ARC General Malvar NA NA completed 114 Construction of Multi-Purpose Pavement in Purok 1 RSAC 2 31-Jul-12 6 Negros Occidental Pontevedra General Malvar ARC General Malvar NA NA completed 115 Construction of Multi-Purpose Pavement in Purok 5 RSAC 2 31-Jul-12 6 Negros Occidental Pontevedra General Malvar ARC General Malvar NA NA completed 116 Construction of Agricultural Warehouse RSAC 2 31-Jul-12 6 Negros Occidental Pontevedra General Malvar ARC General Malvar NA NA completed

117 Rehab of ALBAPA FMR NSAC 7 30-Mar-11 6 Negros Occidental Valladolid ALBAPA ARC Bayabas; Alijis; Pacol CNO 22-Sep-09 CNO 25-Apr-11 completed

118 Const of Salvacion-Langit FMR NSAC 4 16-Mar-10 8 Leyte Alangalang Alangalang 1 ARC Salvacion; Langit CNO 06-Oct-09 CNO 26-Jul-11 completed 119 Const of Manlilisid-San Sotero FMR NSAC 6 27-Jan-11 8 Leyte Javier Javier Settlement ARC Manlilisid; San Sotero CNO 12-Apr-10 CNO 09-Jan-12 completed 120 Concreting of San Sotero-Ulhay FMR NSAC 18 18-May-12 8 Leyte Javier Javier Settlement ARC San Sotero; Ulhay CNO 09-Jan-12 completed

121 Concreting of Zone 1-Pinocawan-Bonifacio-Talisayan FMR NSAC 18 18-May-12 8 Leyte Javier Javier Settlement ARC Zone 1; Pinocawan; A. Bonifacio; Talisayan CNO 09-Jan-12 122 Concreting of Odiong-Guindapunan FMR NSAC 19 07-Jun-12 8 Leyte Javier Javier Settlement ARC Odiong; Guindapunan CNO 09-Jan-12 completed

123 Concreting of San Sotero-Caraye FMR NSAC 20 05-Jul-12 8 Leyte Javier Javier Settlement ARC Caraye; San Sotero CNO 09-Jan-12

124 Concreting of Laray-Magsaysay-Malitbogay FMR NSAC 23 14-Sep-12 8 Leyte Javier Javier Settlement ARC Laray; Magsaysay; Malitbogay CNO 09-Jan-12 125 Concreting of Sitio Km. 14-Sitio Torrel, Brgy. Masarayao FMR NSAC 21 31-Jul-12 8 Leyte Kananga Kananga ARC Masarayao CNO/CP 08-May-12 CNO 21-Jun-13 completed

126 Const of San Agustin-Capirawan-Cangubang FMR NSAC 2 16-Oct-09 8 Leyte Palo Palo 2 ARC San Agustin; Capirawan; Cangumbang CNO 06-Oct-09 completed 127 Const/Improv of Brgy. Crossing-Brgy. Biasong FMR NSAC 3 19-Nov-09 8 Leyte San Isidro San Isidro ARC Brgy. Crossing; Biasong CNO 08-Oct-09 CNO 12-Mar-10 completed 128 Rehabilitation of Bawod-Paril FMR NSAC 33 17-Jul-13 8 Leyte San Isidro San Isidro ARC Bawod; Paril CNO 12-Mar-10 completed

129 Const of Brgy. Cagamutan-Bato-Bangon FMR with Bridge NSAC 6 27-Jan-11 8 Northern Samar Gamay Gamay ARC Cagamutan; Bato; Bangon CNO 05-Nov-09 CNO 04-Feb-13 completed

130 Concreting of Cagamutan-Bato-Bangon FMR NSAC 28 29-Nov-12 8 Northern Samar Gamay Gamay ARC Cagamutan; Bato; Bangon CNO no date CNO 04-Feb-13 completed

131 Const of Brgy. 3 to Brgy. 1 FMR NSAC 4 16-Mar-10 8 Eastern Samar Balangiga Balangiga ARC Brgy. 1; Brgy. 3 CNO 06-Nov-09 CNO 15-Apr-10 completed

132 Const of Brgy. San Miguel FMR NSAC 18 18-May-12 8 Eastern Samar Balangiga Balangiga ARC San Miguel CNO 05-Mar-12 CNO 31-May-12

133 Rehab/Const of Barangay 8-San Isidro FMR NSAC 3 19-Nov-09 8 Eastern Samar Lawaan Lawaan ARC Brgy. 8 Poblacion; San Isidro CNO 07-Oct-09 CNO 15-Apr-10 INDIGENOUS PEOPLE NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE CP/CNO REGION APPLICATION CP/CNO

134 Rehab of Casilion-Tagbacan-Taclaon-Sta. Cruz FMR NSAC 6 27-Jan-11 8 Eastern Samar Salcedo Salcedo ARC Casilion; Tagbacan; Taclaon; Sta. Cruz CNO 07-Oct-09 CNO 15-Apr-10

135 Const of Casoroy-Layog FMR NSAC 3 19-Nov-09 8 Eastern Samar San Julian San Julian ARC Casoroy CNO 14-Jun-11 completed

136 Const of Agricultural Warehouse NSAC 13 19-Dec-11 8 Eastern Samar San Julian San Julian ARC Libas CNO 13-Jul-12 completed

137 Const of Panaw-nawan-Magti-aw FMR NSAC 15 01-Mar-12 8 Eastern Samar San Julian San Julian ARC Campidhan; Nena; Libas CNO 24-Jan-12 CNO 13-Jul-12

138 Rehab of Sta. Cruz-Bangon FMR NSAC 5 12-Jul-10 8 Eastern Samar San Policarpo ESSP ARC Sta. Cruz; Bangon CNO 22-Oct-09 CNO 09-Feb-10

139 Const of Lumatod-Danao FMR with 20 LM RCDG Bridge NSAC 6 27-Jan-11 8 Eastern Samar Taft Taft ARC Lumatod; Danao; Del Remedios CNO 26-Oct-09 CNO 27-Jan-12

140 Const of Cogon-Cancaiyas-Villa Aurora FMR NSAC 15 01-Mar-12 8 Western Samar Basey Samar Settlement Project ARC Cogon; Cancaiyas, Villa Aurora CNO 16-Nov-11 CNO 26-Apr-12 completed

141 Const of Bacyaran-Bulao-Canbagtic-San Mauricio FMR NSAC 5 12-Jul-10 8 Western Samar Calbiga Calpinset ARC Bacyaran; Bulao; Canbagtic; San MauricioCNO 15-Sep-09 CNO 15-Oct-10 completed

142 Const of Mabini-Mayahay-San Roque FMR NSAC 1 2-Sep-09 8 Western Samar Daram West Daram ARC Mabini; Mayabay; San Roque CNO 12-Aug-09 CNO 13-Jul-12 completed

143 Const of Poblacion 02-Talisay FMR NSAC 11 4-Nov-11 8 Western Samar Daram West Daram ARC Talisay; Poblacion 02 CNO 07-Oct-11 CNO 13-Jul-12 completed

144 Const of Mabini-Astorga-San Vicente-Bono-anan FMR NSAC 26 30-Oct-12 8 Western Samar Daram West Daram ARC Mabini; Ubo; Birawan; Astorga; Marupangdan; San Vicente; Bono-anonCNO 13-Jul-12 completed 145 Concreting of Macaparican ARC FMR NSAC 20 05-Jul-12 8 Western Samar Jiabong Macaparican ARC Cantongtong CNO 13-Apr-12 CNO 13-Jul-12 completed

146 Const of Sta. Rita FMR NSAC 15 01-Mar-12 8 Western Samar Marabut SOWSEED ARC Sta. Rita; Malobago; Pinamitinan CNO 01-Dec-11 CNO 26-Apr-12

147 Const of Nabong-Loctob-Catigawan-Lawaan-Pahug FMR NSAC 3 19-Nov-09 8 Western Samar Pinabacdao CALPINSET ARC Nabong; Loctob; Catigawan; Lawaan; PahugCNO 01-Sep-09 CNO 20-Dec-09

148 Const of Maralag-Libertad FMR NSAC 3 19-Nov-09 9 Zamboanga del Sur Dumingag Mantilba ARC Maralag; Libertad CNO 12-Aug-09 CNO 15-Dec-09 completed INDIGENOUS PEOPLE NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE CP/CNO REGION APPLICATION CP/CNO

149 Construction of New Basak Multi-purpose Center with Solar Dryer RSAC 2 10-Nov-10 9 Zamboanga del Sur Dumingag Mantilba ARC CNO 15-Dec-09 completed

150 Construction of Maralag Multi-purpose Center with Solar Dryer RSAC 2 10-Nov-10 9 Zamboanga del Sur Dumingag Mantilba ARC Maralag CNO 15-Dec-09 completed

151 Construction of Libertad Multi-purpose Center with Solar Dryer RSAC 2 10-Nov-10 9 Zamboanga del Sur Dumingag Mantilba ARC Libertad CNO 15-Dec-09 completed

152 Construction of Manlabay Multi-purpose Center with Solar Dryer RSAC 2 10-Nov-10 9 Zamboanga del Sur Dumingag Mantilba ARC CNO 15-Dec-09 completed

153 Construction of Upper Timonan Multi-purpose Center with Solar Dryer RSAC 2 10-Nov-10 9 Zamboanga del Sur Dumingag Mantilba ARC CNO 15-Dec-09 completed

154 Construction of Lower Timonan Multi-purpose Center with Solar Dryer RSAC 2 10-Nov-10 9 Zamboanga del Sur Dumingag Mantilba ARC CNO 15-Dec-09 completed

155 Rehab of Nopulan-Bogo-Calabat FMR NSAC 2 16-Oct-09 9 Zamboanga del Sur Josefina Josefina Highland Cluster ARC Nopulan; Bogo Calabat CNO 23-Sep-09 CNO 20-Nov-09 completed 156 Construction of Dipaya Day Center RSAC 8 6-Jul-12 9 Zamboanga del Sur Labangan Labangan Cluster C ARC CNO 02-Nov-10 completed 157 Construction of Bokong Tribal Center RSAC 9 9-Jul-12 9 Zamboanga del Sur Labangan Labangan Cluster C ARC CNO 02-Nov-10 completed 158 Construction of Binayan Tribal Center RSAC 9 9-Jul-12 9 Zamboanga del Sur Labangan Labangan Cluster C ARC CNO 02-Nov-10 completed

159 Const of Balamban-San Jose-Tumapic FMR with RCDG Bridge NSAC 2 16-Oct-09 9 Zamboanga del Sur Mahayag Balamban Expanded ARC Tumapic; San Jose; Balamban CNO 12-Aug-09 CNO 14-Dec-09 completed

160 Const of Brgy. Buloron-Dumalinao FMR NSAC 16 30-Mar-12 9 Zamboanga del Sur Midsalip Midsalip ARC Cluster Buloron; Dumalinao CNO 16-Jun-10 completed

161 Concreting of Buloron-Lumponid FMR NSAC 17 20-Apr-12 9 Zamboanga del Sur Midsalip Midsalip ARC Cluster Buloron; Lumponid CNO 16-Jun-10 completed 162 Construction of Midsalip Cluster ARC Tribal Center RSAC 9 9-Jul-12 9 Zamboanga del Sur Midsalip Midsalip ARC Cluster CNO 05-Jul-12 CNO 19-Dec-12 completed

163 Rehab of Gabunon-Bag-ong Tabugon FMR NSAC 5 12-Jul-10 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster B ARC Gabunon;Tuluan; Libato; Bag-ong TabugonCNO 13-Aug-09 CNO 08-Dec-09 completed

164 Rehab/Improv of Guinlin-Limas FMR NSAC 1 2-Sep-09 9 Zamboanga del Sur Tigbao BegCaLLi ARC Guinlin; Limas CNO 08-Dec-09 completed 165 Const of BegCaLLi ARC Health Station NSAC 2 16-Oct-09 9 Zamboanga del Sur Tigbao BegCaLLi ARC Begong CNO 08-Dec-09 completed

166 Concreting of Begong-Limas FMR NSAC 25 19-Oct-12 9 Zamboanga del Sur Tigbao BegCaLLi ARC Begong; Limas CNO/CP 20-Aug-12 CNO 08-Dec-09

167 Rehab with Spot Concreting of Balungisan-Guiwan FMR NSAC 6 27-Jan-11 9 Zamboanga Sibugay Payao Don Alfonso ARC Balungisan; La Fortuna; Calape; Kulasian;CNO Bulawan; 28-Oct-09 Guiwan CNO 26-Jan-10 completed 168 Concreting of Tumahubong ARC FMR NSAC 16 30-Mar-12 14 Basilan Sumisip TARBIDC ARC Tumahubong CNO 14-Oct-11 CNO 03-May-12 169 Const of Tumahobong PWS LII NSAC 18 18-May-12 14 Basilan Sumisip TARBIDC ARC Tumahubong CNO 14-Oct-11 CNO 03-May-12

170 Rehab of Tumahubong ARC FMR NSAC 21 31-Jul-12 14 Basilan Sumisip TARBIDC ARC Tumahubong ` CNO 03-May-12 171 Concreting of TARBADECO ARC Road Network NSAC 18 18-May-12 14 Basilan Tipo-Tipo TARBADECO ARC Tipo-Tipo Proper; Magkawa; Limbu-pas;CNO Guinanta 06-Feb-12 CNO 03-May-12 completed INDIGENOUS PEOPLE NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE CP/CNO REGION APPLICATION CP/CNO

172 Concreting of Phil-Am-Buhe Pahu FMR NSAC 18 18-May-12 14 Basilan Ungkaya Pukan TIPARBECO ARC Cabangalan; Buhe Pahu CNO 03-May-12 completed 173 Concreting of Brgy. Dado Poblacion-Sitio Matampay Bagoaingud FMR NSAC 37 18-Feb-14 14 Lanao del Sur Balindong Dado ARC Dado CNO 15-Jan-15 completed 174 Construction of Dado ARC PWS LII NSAC 37 18-Feb-14 14 Lanao del Sur Balindong Dado ARC Dado CNO 15-Jan-15 completed 175 Concreting of Sumogot FMR NSAC 18 18-May-12 14 Lanao del Sur Bumbaran Bumbaran ARC Sumogot CNO 03-May-12

176 Const of Barit-Taliogon-Tabuan FMR NSAC 4 16-Mar-10 14 Lanao del Sur Ganassi Taliogon ARC Taliogon; Tabuan CNO 25-Nov-09 completed 177 Concreting and Rehab of Taganonok-Taliogon-Paraaba FMR NSAC 18 18-May-12 14 Lanao del Sur Ganassi Taliogon ARC Campongaraya; Taganonok;Taliogon; Paraaba CNO 03-May-12 178 Construction of Masolun-Taganonok-Taliogon FMR NSAC 35 18-Oct-13 14 Lanao del Sur Ganassi Taliogon ARC Masolun; Taganonok; Taliogon CNO 03-May-12 179 Construction of Campongraya PWS - Level II NSAC 35 18-Oct-13 14 Lanao del Sur Ganassi Taliogon ARC Masolun; Taganonok; Taliogon CNO 03-May-12 180 Construction of Barit PWS NSAC 36 06-Dec-13 14 Lanao del Sur Ganassi Taliogon ARC Barit CNO 03-May-12 181 Concreting of Campongaraya-Barorao-Panggawalupa-Barit FMR NSAC 36 06-Dec-13 14 Lanao del Sur Ganassi Taliogon ARC Campongaraya; Barorao; Panggawalupa; Barit CNO 03-May-12 182 Construction of Panggawalupa Pre-Stress Concrete Girder (PSCG) BridgeNSAC 36 06-Dec-13 14 Lanao del Sur Ganassi Taliogon ARC Panggawalupa CNO 03-May-12 183 Construction of Barangay Health Center @ Brgy. Campongraya RSAC 3 18-Oct-12 14 Lanao del Sur Ganassi Campongraya CNO 03-May-12 184 Construction of Multi-Purpose Building @ Brgy. Barorao RSAC 3 18-Oct-12 14 Lanao del Sur Ganassi Barorao CNO 03-May-12 185 Construction of Multi-Purpose Building @ Brgy. Taliogon RSAC 3 18-Oct-12 14 Lanao del Sur Ganassi Taliogon CNO 03-May-12 186 Construction of Warehouse Solar Dryer @ Brgy. Barit RSAC 3 18-Oct-12 14 Lanao del Sur Ganassi Barit CNO 03-May-12 187 Concreting of Bangon-Lumbac & Dimapok FMR NSAC 36 06-Dec-13 14 Lanao del Sur Lumbaca Unayan Dilausan ARC Bangon; Lumbac; Dimapok CNO/CP 08-Jul-14 CNO 27-Aug-14 188 Concreting of Pitatanglan-Wago Kabasaran & Wago-Miniros FMR NSAC 36 06-Dec-13 14 Lanao del Sur Lumbayanague Cabasaran ARC Pitatanglan; Wago; Kabasaran; Miniros CNO 12-Mar-15 189 Concreting of Camalig Bandaraingud-Loway Inodaran FMR NSAC 21 31-Jul-12 14 Lanao del Sur Marantao Bubong Camalig ARC Camalig Bandaraingud; Loway Inodaran CNO 03-May-12 190 Concreting and Rehab of Bubong-Ragayan-Gadongan FMR NSAC 18 18-May-12 14 Lanao del Sur Poona Bayabao Ragayan ARC Bubong Dimunda; Pantao; Ragayan; Bansayan; Gadongan CNO 03-May-12 191 Construction of Multi-Purpose Building with Solar Dryer (Lumbac) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Lumbac CNO 26-Jan-15 192 Construction of Multi-Purpose Building with Solar Dryer (Bacayawan) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Bacayawan CNO 26-Jan-15 193 Construction of Multi-Purpose Building with Solar Dryer (Tagoranao) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Tagoranao CNO 26-Jan-15 194 Construction of Multi-Purpose Building with Solar Dryer (Pagalongan) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Pagalongan CNO 26-Jan-15 195 Construction of Multi-Purpose Building with Solar Dryer (Dinganun) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Dinganum CNO 26-Jan-15 196 Construction of Multi-Purpose Building with Solar Dryer (Malalis) NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Malalis CNO 26-Jan-15 197 Construction of Multi-Purpose Building with Solar Dryer (Buta-Sumalindao)NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Buta-Sumalindao CNO 26-Jan-15 198 Concreting of Dinganun-Pagalongan-Bacayawan-Lumbac FMR NSAC 35 18-Oct-13 14 Lanao del Sur Sultan Dumalondong Sultan Dumalondong ARC Dinganun; Pagalongan; Bacayawan; Lumbac CNO 26-Jan-15

199 Concreting of Kinggan-Tagoloan Poblacion FMR NSAC 13 19-Dec-11 14 Lanao del Sur Tagoloan Malinao-Cadayonan ARC Malinao; Cadayonan CNO 03-May-12 200 Concreting of 8 km Dinganen-Nuyo FMR I NSAC 35 18-Oct-13 14 Maguindanao Buldon Buldon ARC Dinganen-Nuyo CNO 11-Nov-14 201 Concreting of Tamborong-Bunawan FMR NSAC 13 19-Dec-11 14 Maguindanao Datu Paglas Bunawan ARC Tamborong; Bunawan CNO 22-Dec-09 completed 202 Const of Ganta-Gambar FMR NSAC 14 19-Jan-12 14 Maguindanao Kabuntalan Matilak ARC Ganta; Pagalungan; Gambar CNO 28-Feb-11 CNO 16-Dec-11 completed CNO 203 Concreting of Langkong-Bayanga Norte Road NSAC 21 31-Jul-12 14 Maguindanao Matanog Langkong ARCTubig Langkong; Samin; Bayanga Matatal; Norte Datag 03-May-12 Limbun; Gulangan; Kandang; 204 Concreting of Patao Junction-Ipil FMR NSAC 13 19-Dec-11 14 Sulu Maimbung Maimbung ARC TubigPatao; Samin; Ipil Matatal; Datag CNO/CP 04-Nov-11 CNO 03-May-12 completed Limbun; Gulangan; Kandang; 205 Concreting of Pantao Junction-Kandang Gulangan-Ratag Limbun FMR NSAC 13 19-Dec-11 14 Sulu Maimbung Maimbung ARC Patao; Ipil CNO/CP 04-Nov-11 CNO 03-May-12 completed Limbun; Gulangan; Kandang; 206 Concreting of Tubig Samin Junction-Tambuan FMR NSAC 13 19-Dec-11 14 Sulu Maimbung Maimbung ARC Patao; Ipil CNO/CP 04-Nov-11 CNO 03-May-12 completed 207 Rehab of Su'uh-Kan-dayuk-Kan-ukul FMR NSAC 7 30-Mar-11 14 Sulu Panamao Sultan Jamalul Kiram ARC Kan-dayuk; Kan-ukul; Su'uh CNO 15-Dec-09 CNO 03-May-12 completed INDIGENOUS PEOPLE NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE CP/CNO REGION APPLICATION CP/CNO

208 Concreting of Parian-Dakula-Lahi-Malanta FMR NSAC 13 19-Dec-11 14 Sulu Pandami Pandami ARC Parian Dakula; Lahi; Malanta CNO 04-Nov-11 CNO 03-May-12 Buan; Ratag; Siowing; Sipanding; 209 Concreting of Buan, Ratag, Siowing Sipanding and Duggo FMR NSAC 21 31-Jul-12 14 Sulu Siasi Ratag-Gantaan ARC Duggo CNO 03-May-12 210 Concreting of Kahawa - Tampakan FMR NSAC 37 18-Feb-14 14 Sulu Talipao CNO 30-Oct-17 211 Concreting of Tandubanak ARC FMR (Section 1) NSAC 14 19-Jan-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak CNO 28-Nov-11 CNO 03-May-12 212 Concreting of Tandubanak ARC FMR (Section 2) NSAC 14 19-Jan-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak CNO 28-Nov-11 CNO 03-May-12 213 Concreting of Tandubanak ARC FMR (Section 3) NSAC 14 19-Jan-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak CNO 28-Nov-11 CNO 03-May-12 214 Concreting of Tongehat ARC FMR NSAC 14 19-Jan-12 14 Tawi-Tawi Sibutu Ungus-Ungus-Tongehat ARC Tongehat CNO 28-Nov-11 CNO 03-May-12 215 Construction of 3-Unit Classroom School Building (Brgy. Tandubanak) RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak CNO 03-May-12 completed 216 Construction of 3-Unit Classroom School Building MSU-CHS (Brgy. Ungus-Ungus)RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Ungus-Ungus CNO 03-May-12 completed 217 Construction of 3-Unit Classroom School Building (Brgy. Taungoh) RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Tandubanak ARC Taungoh CNO 03-May-12 completed 218 Construction of 3-Unit Classroom School Building (Brgy. Tongehat) RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Tongehat CNO 03-May-12 completed 219 Construction of 3-Unit Classroom School Building (Brgy. Tongsibalo) RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Tongsibalo CNO 03-May-12 completed 220 Construction of 3-Unit Classroom School Building (Brgy. Ungus-Ungus) RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Ungus-Ungus CNO 03-May-12 completed 221 Construction of Barangay Ungus-Ungus Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Ungus-Ungus CNO 03-May-12 completed 222 Construction of Barangay Tongsibalo Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Tongsibalo CNO 03-May-12 completed 223 Construction of Barangay Tongehat Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Ungus Ungus Tongehat ARC Tongehat CNO 03-May-12 completed 224 Construction of Barangay Taungoh Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Taungoh CNO 03-May-12 completed 225 Construction of Barangay Tandubanak Health Station RSAC 2 24-May-12 14 Tawi-Tawi Sibutu Tandubanak ARC Tandubanak CNO 03-May-12 completed

Note: CP/CNO Application column refers to the date when the LGU applied for CP/CNO with the National Commission on Indigenous Peoples (NCIP) CP/CNO column refers to the date when tNCIP issued the Certificate of Non Overlap for the subproject ANNEX IV - E: LIST OF SUBPROJECTS ISSUED WITH CPs DAR-ADB Agrarian Reform Communities Project II As of December 2017

INDIGENOUS PEOPLE NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE CP/CNO REGION APPLICATION CP/CNO

1 Concreting of Antipolo-Divino Rostro FMR NSAC 18 18-May-12 5 Camarines Sur Buhi Antipolo-Divino Rostro ARC Antipolo; Divino Rostro CP 12-Aug-09 completed 2 Rehab of Maligaw-ligaw FMR RSAC 3 15-Oct-10 5 Camarines Sur Buhi Antipolo-Divino Rostro ARC CP 12-Aug-09 completed 3 Concreting of Sitio Nagpana to Sitio Proper, Lipata to San Geronimo FMRNSAC 34 06-Sep-13 6 Iloilo Barotac Viejo Lipata Special ARC Lipata CNO/CP 02-Sep-13 CP 01-Jun-15 completed 4 Concreting of JNR-Agsirab-Bagongbong-Sitio Agdalusan FMR NSAC 35 18-Oct-13 6 Iloilo Lambunao AGSIBAGO ARC Agsirab; Bagongbong CNO/CP 26-Nov-13 CP 09-Mar-15 completed 3 5 Rehabilitation of Dipolog CIS NSAC 33 17-Jul-13 9 Zamboanga del Norte Dipolog City DCS Expanded ARC Dapdap; Anastacio; Punta; Galas; Gulayan;CNO/CP Tumo; Sinaman;10-Jul-13 Bandera;CP Olingan;13-Feb-14 Sta. Filomena completed 6 Concreting of Sitio Jiay-Sitio Sibulan Bgy. Balas FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Labason GBL ARC Balas CNO 05-Oct-12 CP 22-Jul-14

7 Concreting of Lingatongan-Meses FMR NSAC 22 24-Aug-12 9 Zamboanga del Norte Manukan Manukan East ARC Lingatongan; Meses CNO/CP 02-Apr-12 CP 13-Feb-14 completed

8 Concreting of Gupot FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Manukan Manukan East ARC Gupot CNO 09-Oct-13 CP 13-Feb-14 9 Rehab with Concreting of Polayo-Denuyan FMR NSAC 19 07-Jun-12 9 Zamboanga del Norte Siayan Siayan West ARC Polayo CNO/CP 28-Mar-12 CP 17-Sep-14 completed 10 Rehab with 0.75 km Concreting of Paranglumba FMR NSAC 20 05-Jul-12 9 Zamboanga del Norte Siayan Siayan West ARC Paranglumba CP 28-Mar-12 CP 17-Sep-14 completed 11 Rehab with 2 km. Concreting of Sitio Bolanao-Litolet FMR NSAC 21 31-Jul-12 9 Zamboanga del Norte Siayan Siayan East ARC Litolet CP 28-Mar-12 CP 17-Sep-14 12 Rehab with 0.7 km. Concreting of Moyo-Sitio Pase FMR NSAC 21 31-Jul-12 9 Zamboanga del Norte Siayan Siayan West ARC Moyo CP 28-Mar-12 CP 17-Sep-14 13 Rehab with 0.9 km. Concreting of Gonayen-Sayaw FMR NSAC 21 31-Jul-12 9 Zamboanga del Norte Siayan Siayan East ARC Gonayen CP 28-Mar-12 CP 17-Sep-14 completed

14 Rehabilitation/Concreting of Junction Muñoz-Litolet FMR NSAC 32 07-Jun-13 9 Zamboanga del Norte Siayan Siayan East ARC Litolet CNO/CP 21-May-13 CP 17-Sep-14 completed

15 Rehabilitation/Concreting of Poblacion-Moyo FMR NSAC 33 17-Jul-13 9 Zamboanga del Norte Siayan Siayan West ARC Poblacion; Moyo CNO/CP 21-May-13 CP 17-Sep-14 16 Rehabilitation of Lituban CIS NSAC 34 06-Sep-13 9 Zamboanga del Norte Siocon Jolamipaman ARC CP 17-Oct-16 completed

17 Concreting of JNR Pangian-Greenridge FMR NSAC 37 18-Feb-14 9 Zamboanga del Norte Siocon Jolamipaman ARC Pangian CP 13-Oct-16 completed 18 Upgrading/Rehab of Poblacion-New Dapitan FMR NSAC 24 27-Sep-12 9 Zamboanga del Norte Tampilisan Rubber Stump ARC Poblacion CP 28-Mar-12 CP 13-Feb-14 19 Concreting of Poblacion-ZNAC FMR NSAC 27 16-Nov-12 9 Zamboanga del Norte Tampilisan Rubber Stump ARC ZNAC CNO/CP 27-Mar-12 CP 13-Feb-14 completed

20 Rehab of Brgy. Moradje-Ebarle FMR NSAC 18 18-May-12 9 Zamboanga del Sur Josefina Josefina Highland Cluster ARC Moradje; Ebarle CNO/CP 10-May-12 CP 03-Jan-14 completed 21 Rehab/Concreting of Brgy. Moradje-Tagaytay-Dawa FMR NSAC 24 27-Sep-12 9 Zamboanga del Sur Josefina Josefina Highland Cluster ARC Dawa; Moradje; Tagaytay CNO 10-May-12 CP 03-Jan-14 completed 22 Construction of Josefina Cluster ARC Tribal Center RSAC 9 9-Jul-12 9 Zamboanga del Sur Josefina Josefina Highland Cluster ARC CP 03-Jan-14 completed 23 Rehabilitation of Guipos CIS NSAC 34 06-Sep-13 9 Zamboanga del Sur Guipos Balongating Expanded ARC Balangating, Poblacion CNO/CP no date CP 13-Feb-14

24 Const of Junction Poblacion Kumalarang-Bualan FMR NSAC 11 4-Nov-11 9 Zamboanga del Sur Kumalarang Baganian Peninsula ARC Cluster Poblacion; Bualan CNO/CP 01-Sep-11 CP 30-Aug-12 completed

25 Const/Improv of Bualan-Maruing-Pampang-Poblacion Lapuyan FMR NSAC 12 18-Nov-11 9 Zamboanga del Sur Lapuyan Baganian Peninsula ARC Cluster Pingalay; Maruing; Pantad; Pampang; Poblacion;CP Tipasan14-Jun-11 CP 30-Aug-12 completed

26 Concreting of Bgy. Lower Salug Dako-Balamban-San Jose DCM FMR NSAC 24 27-Sep-12 9 Zamboanga del Sur Mahayag Balamban Expanded ARC Balamban; DCM; Lower Salug; San JoseCNO 08-May-12 CP 12-Oct-12 completed 27 Construction-Rehabilitation-Concreting of Bgy. DCM FMR NSAC 24 27-Sep-12 9 Zamboanga del Sur Mahayag Balamban Expanded ARC DCM CNO 08-May-12 CP 12-Oct-12 28 Const of Bgy. Lower Sto. Niño FMR NSAC 26 30-Oct-12 9 Zamboanga del Sur Mahayag Balamban Expanded ARC Lower Sto. Niño CNO 08-May-12 CP 12-Oct-12 INDIGENOUS PEOPLE NSAC/RSAC SUBPROJECT TITLE PROVINCE MUNICIPALITY ARC Barangay Physical Status DATE CP/CNO REGION APPLICATION CP/CNO

29 Const of Tipasan-Tulapok-Poblacion FMR NSAC 11 4-Nov-11 9 Zamboanga del Sur Margosatubig Baganian Peninsula ARC Cluster Tulapok; Tiguian; Poblacion CNO 23-Jun-11 CP 30-Aug-12 completed

30 Const of Culo FMR NSAC 18 18-May-12 9 Zamboanga del Sur Molave Culo ARC Culo CNO/CP 27-Feb-12 CP 30-Aug-12 completed

31 Concreting of Purok Jupiter (Basay)-Purok Venus FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Molave Rizal ARC Rizal CNO 16-May-12 CP 05-Oct-12 completed

32 Concreting of Purok Ferry-Purok Happy Valley FMR NSAC 21 31-Jul-12 9 Zamboanga del Sur Molave Miligan ARC Miligan CNO 16-May-12 CP 05-Oct-12 completed

33 Concreting of Tanducan-Tambunan FMR NSAC 18 18-May-12 9 Zamboanga del Sur Tabina Tabina Cluster ARC Poblacion; Malim CP 10-Feb-11 CP 12-Nov-12

34 Concreting of Lower Lodiong-Limamaan FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster B ARC Lower Lodiong; Limamaan CNO/CP 23-Mar-12 CP 04-Feb-13 completed

35 Concreting of Junction Limamaan-Upper Lodiong FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster B ARC Upper Lodiong; Limamaan; Tuluan CNO/CP 23-Mar-12 CP 04-Feb-13 completed 36 Rehab w/ Spot Concreting of Limamaan FMR NSAC 22 24-Aug-12 9 Zamboanga del Sur Tambulig Tambulig Highland Cluster B ARC Limamaan CNO/CP 23-Mar-12 CP 04-Feb-13 completed

37 Const with 1.248 Concreting of Alindahaw-Panduma Sr.-Camanga FMR NSAC 20 05-Jul-12 9 Zamboanga del Sur Tukuran LUCATT-LBP ARC Alindahaw; Panduma Sr.; Camanga CNO 15-Mar-12 CP 24-Sep-12 completed

38 Concreting of Balungisan-Upper Sumilong FMR NSAC 35 18-Oct-13 9 Zamboanga Sibugay Payao Don Alfonso ARC Balungisan; Upper Sumilong CNO 05-Jun-12 CP 29-Jan-13 completed 39 Rehab of Culasian-Supit FMR NSAC 1 2-Sep-09 9 Zamboanga Sibugay Titay Supit ARC Culasian; Supit CNO 24-Aug-09 CP 28-Aug-13 completed 40 Rehab w/ Spot Concreting of Kitabog-Mabini FMR NSAC 20 05-Jul-12 9 Zamboanga Sibugay Titay Titay Valley ARC Kitabog; Mabini CNO/CP 04-May-12 CP 28-Aug-13 completed

Note: CP/CNO Application column refers to the date when the LGU applied for CP/CNO with the National Commission on Indigenous Peoples (NCIP) CP/CNO column refers to the date when tNCIP issued the Certification Precondition for the subproject ANNEX V: ARCP II Safeguards Monitoring Form

DEPARTMENT OF AGRARIAN REFORM Second Agrarian Reform Communities Project (ARCP2)

ENVIRONMENTAL MANAGEMENT & MONITORING PLAN (EMMP) AND ENVIRONMENTAL COMPLIANCE CERTIFICATE (ECC) & SOCIAL SAFEGUARDS COMPLIANCE MONITORING REPORT

______NAME OF SUBPROJECT

PRIMARY PURPOSE: To ensure that all activities related to the subproject are environmentally sound, socially acceptable and sustainable.

OBJECTIVES:

1. Monitor compliance of the subproject vis-à-vis the Environmental Management& Monitoring Plan (EMMP), Environmental Compliance Certificate and other applicable laws, rules and regulations; 2. Monitor action/s taken based on the Environmental Assessment during pre-implementation phase; 3. Monitor action/s taken based on the conditions and required social safeguards documents; and 4. Provide bases for timely decision-making with regard to mitigation, monitoring and institutional measures to be taken during implementation and operation to eliminate adverse environmental and social impacts.

MONITORING PERIOD COVERED: ______

I. BASIC INFORMATION: Subproject Type: ______Name of ARC: ______Location: ______Project Stage/Phase: ______(i.e. Implementation phase: mid or end) Contact Person: ______Designation/Contact No: ______

II. PROJECT OFFICE ENVIRONMENTAL ASSESSMENT REVIEW FINDINGS ANDRECOMMENDATIONS

Environmental Assessment Proposed Measures for: Action Taken by: Findings Remarks ARCP2 Proponent ARCP2 Proponent

COMPLIANCE TO EMMP Monitoring Cost ofMitigation Institutional Plan Schedule Guarantees Remarks Mitigation/Enhancem parameter, or Enhancement (Frequency) (explainati ent Measure (status location Planned Actual Planned Actual Planned Actual Planned Actual on of of implementation) discrepan cies bet planned & actual

*Explain reason in Remarks column and the plan/action (including timeline) of DARPO to address this concern

III. COMPLIANCE TO ECC CONDITIONS

STATUS OF COMPLIANCE ECC CONDITIONS REMARKS YES NO Others

*Explain reason in Remarks column and the plan/action (including timeline) of DARPO to address this concern

VII. SOCIAL SAFEGUARDS

Land acquisition and resettlement impacts of the sub-project (include number of AHs and APs per type of impact1): ______Affected vulnerable households:______Resettlement Plan prepared? (Y/N): ______

1 E.g. impacts on main structures (house, independent shop), secondary structures, land, crops, trees Resettlement Plan fully implemented? (Y/N): ______

Status of Compliance INVOLUNTARY RESETTLEMENT Yes No Remarks (Completed) (Not Completed)* 1) Consultation with the community (Pre- implementation phase) 2) Orientation and disclosure of Social Safeguards policy e.g. rights of PAPs to be compensated 3) Grievance Redress Mechanism 4) Compensation of PAPs land, improvements 5) Legal documents (for donated lands,ROW)

Status of Compliance INDIGENOUS PEOPLES Yes No Remarks (Complying) (Not Complying) 1) For ARCs/ ARC Clusters with IPs: IP Chapter in the ARCDP/ IP Development Plan 2) Secured CNO/ Certification Precondition 3) Impact of the Subproject to the IPs

*Explain reason in Remarks column and the plan/action (including timeline)of DARPO to address this concern

IV. RECOMMENDATIONS

______.

V. ATTACHMENTS Photographs (Annex 1)

PREPARED BY:

LPO: ______

REVIEWED AND APPROVED BY:

______Provincial ESS Coordinator

ANNEX VI : PHOTO DOCUMENTATION

Meeting with the community and PAPs in Tigbao, Zamboanga del Sur “ Rehabilitation/Improvement of Guinlin – Limas FMR”

ESS writeshop with LGUs in Samar: preparation of safeguards documents

LGUs of Samar: ESS writeshop

Pre-Construction Meeting: ‘Construction of Mabini-Mayabay-San Roque FMR’, Daram, Samar

Meeting with LGU Dumingag, Zamboanga del Sur discussing ARCP II including Environment & social safeguards

Validation of proposed subproject (team of engineer, economist, ESS point person) in Mahayag, Zamboanga del Sur

Meeting with community and PAPs in Tigaon, Camarines Sur (ESS, CDD Consultant and RIE)

Dialogue with Ati tribe, Bgy, Lipata Special ARC, Barotac Nuevo, Iloilo

ESS ORIENTATION IN PALAWAN WITH DAR & LGU REPRESENTATIVES

FS/DE-POW/ESS DISCUSSION IN PALAWAN WITH DAR POINT PERSONS & LGU REPRESENTATIVES