ILLINOIS TOLLWAY

Lane Closure Reference Guide

Illinois Tollway 2700 Ogden Avenue Downers Grove, IL 60515-1703 Telephone (630) 241-6800

September 2018 Revision 11.1 Table of Contents

Purpose ...... 3

Contract Information Page ...... 4

Lane Closure Requests & Revisions Due ...... 7 Ask for a Read Receipt ...... 7 Breakdown of Daytime & Overnight Hours when filling out Lane Closure Requests ....7 Published Lane Closure Report ...... 7

Reporting Lane Closure Status Procedure ...... 8

Standard Lane/Shoulder Closure Requests ...... 9

Revisions to Lane Closure Requests ...... 12

Cancellation of Lane Closure Request ...... 15

10 Day Advance Lane/Shoulder Closure Request ...... 18

Long Term Request ...... 21

Standard Lane/Shoulder Closure Requests with Trooper Assistance ...... 24

State Trooper Assistance Form ...... 27 Submittals Due ...... 27

Emergency Closure/Holiday or After Business Hours Requests 3PM - 7AM ...... 30

Tollway/CM/Contractor PCMS Deployment and Maintenance Guide ...... 31

Other Lane Closure Details ...... 34 Published Lane Closure Report ...... 34 Breakdown of Daytime & Overnight Hours when filling out Lane Closure Requests ..34 Subject Line When Emailing Closures ...... 34 Ask for a Read Receipt ...... 34 Entering Milepost Numbers ...... 34 List of Lanes Closed & Opened ...... 34

Appendix ...... 35

List A - Systemwide Milepost Numbers ...... 36 List B - Type of Work ...... 42 List C – List of Lanes to Close ...... 43 List D - Ramp Designations ...... 44 List F - Emergency Lane Closure Request/or After Hours Lane Closure Changes ...... 51

- 2 - 8/28/2018 Purpose Information on construction activity, traffic shifts, stage changes, variances or any other activity that will impact traffic on the Tollway and/or local roads and nearby communities must be reported in advance to the Construction Corridor Manager (CCM), Construction Manager (CM), Design Engineering (DSE). Lane Closures at [email protected] (x4822 & 4821), Elyse Morgan (x1703), Construction Communications Coordinators (CCC) Vacant (x6381) and Maria Burnham (x6389).

In addition to lane closure information, any other activity or issues that may impact Tollway customers should be communicated to the CCC as soon as possible.

The information in this Lane Closure Reference Guide provides directions for filling out any form that must be submitted to the Tollway when requesting any lane/shoulder closure(s).

DO NOT REFORMAT ANY FORM FOR ANY REASON UNLESS INSTRUCTED IN THIS DOCUMENT. WHEN THE DIRECTIONS ARE FOLLOWED THERE IS NO REASON TO REFORMAT A FORM.

Also included are procedures that have been sent via email and additional information that will help along the way.

- 3 - 9/19/2018 Contract Information Page When the Notice to Proceed (NTP) or Authorization Letter has been issued for a new contract, the Resident Engineer/Contractor must fill out a Contract Information Page and then email it to Lane Closures - [email protected] & Elyse Morgan - [email protected] before the first request has been submitted. A Standard Lane/Shoulder Closure or Long Term Lane/Shoulder Closure request CAN NOT be approved and processed without the Contract Information Page and a signed NTP/Authorization Letter.

Below are detailed directions for filling out the Contract Information Page. Page 6 is a sample of what the page should look like after all the information has been input. Make sure that every section is filled in and is correct before submitting to the Tollway. Again, submit the Contract Information Page to [email protected] & [email protected] before the first request has been submitted. Only one (1) phone number per section can be processed.

ALL PHONE NUMBERS THAT ARE PROVIDED ARE TO BE 24/7 NUMBERS. NO CALL SHOULD GO TO VOICE MAIL.

1) Contract/Permit Number: Type the contract/permit number listed on the NTP/Authorization Letter (i.e. I-12-1234/TS 16-1234)

2) Location: Type the location of the project listed on the NTP/Authorization Letter (i.e. IL 56 to Maple Av)

3) Type of Work: Type the type of work listed on the NTP/Authorization Letter (Pavement Resurfacing, Bridge Widening, etc.)

4) Milepost(s): Type the starting milepost of the project and the ending milepost of the project listed on the NTP/Authorization Letter (see pages 7 & 34 for entering milepost numbers),

5) Maint. Sect.: Type the Maintenance Section the project is in (M1, M2, M3, etc.) List A

6) M.O.T. Company: Type the Maintenance of Traffic Company (company setting up closures)

7) Office Phone: Type the MOT office phone number

8) Cell Phone: Type the cell number of the MOT (MUST be a 24/7 number)

9) CM/DSE: Type the CM or DSE (Construction Manager or Design Engineering company name)

10) Office Phone: Type the office number of the CM or DSE

11) Resident Engineer: Type the Resident Engineer’s name (CM or DSE point of contact person)

12) Cell Phone: Type the cell phone number of the RE (MUST be a 24/7 number)

13) Home Phone: Type the home phone number of the RE (MUST be a 24/7 number)

14) Field Phone: Type the phone number of the field office

15) Contractor: Type the name of the contractor (company doing the work on the Tollway). It should NOT be blank.

16) Office Phone: Type the office number of the contractor

17) Tollway Project Manager: Type the name of the Tollway Project Manager

18) Ext: Type the Tollway extension of the Tollway PM

19) Cell Phone: Type the cell phone number of the Tollway PM

20) Home Phone: Type the home phone number of the Tollway PM

- 4 - 8/28/2018 CONTRACT INFORMATION PAGE ALL PHONE NUMBERS SHOULD BE 24/7 NUMBERS ALL CALLS MUST BE ANSWERED BY A PERSON NOT VOICE MAIL Date: ______

CONTRACT # TYPE OF WORK M.O.T. COMPANY CM/DSE RESIDENT ENGINEER (1) (3) (6) (9) (11)

LOCATION MILEPOST(S) MAINT. OFFICE PHONE OFFICE PHONE CELL PHONE SECT. (2) (4) (7) (10) (12) (5) CELL PHONE HOME PHONE (8) (13)

FIELD PHONE CONTRACTOR TOLLWAY PROJECT MANAGER EXT. CELL PHONE (14) (15) (17) (18) (19)

OFFICE PHONE HOME PHONE (16) (20)

Please return to Lane Closures- [email protected] & Elyse Morgan - [email protected] as soon as possible

rev. 2/6/15 mlk - 5 - CONTRACT INFORMATION PAGE ALL PHONE NUMBERS SHOULD BE 24/7 NUMBERS ALL CALLS MUST BE ANSWERED BY A PERSON NOT VOICE MAIL

Date: ______

CONTRACT # TYPE OF WORK M.O.T. COMPANY CM/DSE RESIDENT ENGINEER

I-05-1234 Roadway Widening Traffic Control Co. LPT Jennifer Brown & Reconstruction

LOCATION MILEPOST(S) OFFICE PHONE OFFICE PHONE CELL PHONE MAINT. I-294 60.0 to 100.0 SECT. 222-333-4444 666-777-8888 111-222-4444

M15 CELL PHONE HOME PHONE

400-500-6000 600-700-8000

FIELD PHONE CONTRACTOR TOLLWAY PROJECT MANAGER EXT. CELL PHONE

777-888-9999 The Pavers, Inc. Bob Jones 999 200-300-4000

OFFICE PHONE HOME PHONE

999-000-1111 900-100-2000

Please return to Lane Closures- [email protected] & Elyse Morgan - [email protected] as soon as possible

rev. 2/6/15 mlk - 6 - Lane Closure Requests & Revisions Due It is a requirement that Daily Lane Closure Requests & Revisions for daytime and overnight work are due to the Tollway BEFORE 9:00 AM as follows:

Tuesday work is due Monday BEFORE 9:00 AM

Wednesday work is due Tuesday BEFORE 9:00 AM

Thursday work is due Wednesday BEFORE 9:00 AM

Friday work is due Thursday BEFORE 9:00 AM

Saturday, Sunday & Monday work is due Friday BEFORE 9:00 AM

If requests are not in BEFORE 9:00 AM or submitted earlier (unless instructed by Lane Closures) on day specified above they will not be approved and published on the Lane Closure Report.

Emergency closures will be taken on a case by case basis (see page 30 of this document).

ANY AND ALL CONFLICTS MUST BE RESOLVED BEFORE 9:00 AM. IF CONFLICTS ARE NOT RESOLVED BOTH LANE CLOSURES WILL BE DENIED.

Your email subject line MUST include Contract/Permit Number and Date of Closure.

Make sure that the form is filled out correctly: Contract/Permit number or Local Road name MUST be in the Contract # column. Type of Work MUST be filled in. Mileposts MUST be listed little to big regardless of direction.

The information at the bottom MUST be filled in correctly before submitting: Approved for submittal Name, Title, Company Name, Phone Number Submitted by (person who is sending the request), Title, Company Name, Phone Number Date and Time request is being submitted to Tollway.

Ask for a Read Receipt Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified.

Breakdown of Daytime & Overnight Hours when filling out Lane Closure Requests Daytime Hours 7:00 am to 7:00 pm Overnight Hours 7:00 pm to 7:00 am

WHEN SUBMITTING A REVISION, MAKE SURE THAT WHAT HAS BEEN CHANGED IS IN RED.

Published Lane Closure Report The published lane closure report is emailed out at approximately 2:00 PM Monday through Friday. Take a moment to review the daily Lane Closure Report once you receive it to make sure that your closure is on the report and that it is correct.

This way everyone can be notified if a closure did not make the report or if there is a correction that needs to be made before Maintenance leaves at 3:00 PM.

- 7 - 8/28/2018 Reporting Lane Closure Status Procedure The Construction Manager/ Design Engineer (CM/DSE) must contact the Traffic Center when the contractor starts to take each lane(s)/shoulder out of service, then when each lane is put back into service regardless if they are on the Mainline, ramp or at a Plaza (i.e. call when you start taking out your single lane, then call again when you start taking out your double lane closure and then again when you start taking out your triple lane closure), when the 1st vehicle occupies the lane/shoulder and if/when a lane configuration changes (i.e. the mile posts that are on the report have changed, multiple stops for a moving closure).

All shoulder closures in the SMART corridor on I-90 & I-294 Central Tri-State MUST be called in.

For lane & SMART/I-294 Central Tri-State corridor notifications (twenty-four hours a day), the CM/DSE shall notify: The Tollway Traffic Center can be reached at 331-238-1772.

The CM/DSE shall provide the Traffic Center the following information when they make all calls: Contract/Permit Number Corridor (road), Direction, start & end milepost Lane(s)/shoulder taking out of service Contact Information (name & call back phone number)

For overnight closures that cause a back-up of five (5) miles or greater, the CM/DSE shall notify: The Tollway Traffic Center can be reached at 331-238-1772.

The CM/DSE shall provide the Traffic Center the following information when they make all calls: Contract/Permit Number Corridor (road), Direction, start & end milepost Approximate length of the backup and/or the location of where the traffic is backed up to.

 After the CM/DSE contacts Traffic Center, they shall call their PM and inform them of the back- up and that they have contacted Traffic Center.

Closures not being picked up on time prior to their scheduled removal, Emergency extension approval are needed if the closure is being delayed in removal. Follow Emergency Lane Closure Request Procedure on page 30.

If hours for scheduled closure (what is on the published report) change a revision must be submitted the next day. Example: If closure was to begin at 7:00 PM until 5:00 AM (what is on the published Lane Closure Report) and the CM/DSE calls in that they are closing the lane at 8:00 PM, then a revision needs to be submitted the following day. The same applies for putting the lane back into service.

* For overnight lane closures that cause a back-up of 5 miles or greater Dispatch will send a Critical Page.

- 8 - 9/18/2018 Standard Lane/Shoulder Closure Requests Information on start of construction, traffic shifts, stage changes, variances or any other activity that will impact traffic on the Tollway and/or local roads, as well as nearby communities, must be reported in advance. This includes closures on any local roads in addition to ramp/plaza and mainline lane closures. A scheduled or contract closure typically includes a MOT plan that has been previously submitted, reviewed and approved. Notification shall state when lane closure will start, where the lane closure is located, direction of travel, lane(s) involved, and description of the closure and the duration of the closure.

Below are directions for filling out a Standard Lane/Shoulder Closure Request (daily lane closure). Page 11 is what the request should look like after all the information has been input. Make sure that every section is filled out correctly before submitting to the Tollway. Submit requests to CCC, Elyse Morgan and Lane Closures.

1) Daytime or Overnight Day: Type the day of closure (i.e. Monday, Tuesday, Wednesday, etc.)

2) Date of Closure: Type the date of the closure (i.e. 1/21/14)

3) Tollway #: Type the Tollway number/Local Road name (i.e. I-90, I-94, Maple Av, etc.)

4) Contract/Permit or Maint. Bldg. Number: Type the contract/permit or maintenance number (i.e. I-12-1234)

5) Mileposts: Type the starting milepost number and the ending milepost number (little to big regardless of which direction, i.e. 96.8 to 97.9). List A

6) Direction: Type the direction of closure (i.e. EB, WB, SB, NB)

7) Nearest Underpass/Overpass: Type the starting nearest underpass/overpass to ending nearest underpass/overpass (i.e. Single Rd to Triple Rd). List A

8) Type of Work: Type the type of work listed (i.e. Pavement Striping). List B

9) Lane(s)/Shoulder Closed: Type the lane(s)/shoulder that will be closed (i.e. Left Lane). List C

10) Lane(s)/Shoulder Open: Type the lane(s)/shoulder that will be open (i.e. 2 Right Lanes). List C

11) Times of Closure: Type the start time to the end time of closure (i.e. 7:00 pm -6:00 am)

12) Approved for submittal by: Type the Resident Engineer’s name that will be approving the request

13) Title: Type the Resident Engineer’s title

14) Company: Type the Resident Engineer’s company

15) Phone #: Type the Resident Engineer’s phone number (24/7)

16) Emailed by: Type your name

17) Title: Type your title

18) Company: Type your company

19) Phone #: Type your phone number (24/7)

20) Date submitted to Tollway: Type the date request is submitted to the Tollway

21) Time submitted to Tollway: Type the time request is submitted to the Tollway

22) If this is a revision,: Leave blank

- 9 - 8/28/2018 STANDARD LANE/SHOULDER CLOSURE REQUEST

DAYTIME: (1) OVERNIGHT: (1) DATE: (2) Sun, Mon, Tues, Wed, etc. Sun, Mon, Tues, Wed, etc. Date of Closure(s)

LANE(S) Tollw'y Contract # or CLOSURE from Nearest underpass/overpass LANE(S) TIMES of DIR. or SHLD TYPE OF WORK OPEN CLOSURE # Maint. bldg. M.P. to M.P. X-RD to X-RD CLOSED (3) (4) (5) (6) (7) (8) (9) (10) (11)

I-

I-

I-

I-

I-

I-

I-

I-

Cancellation notices must be received ASAP with copies also sent to the Traffic Center Staff at [email protected]..

All closure requests must be submitted to Lane Closures by e-mail (or by fax if computers down), no later than 9am of the working day preceding the requested closure(s). Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified. A copy of this request should also go to Maria Burnham in Communications and Elyse Morgan in the Traffic Center.

e-mail: [email protected] Fax#: (630) 241-6112 Phone#: (630) 241-6800 ext. 4822 & 4821 [email protected] (630) 795-2627 (630) 241-6800 ext. 6389 [email protected] (630) 241-6800 ext. 1703 [email protected] (331) 238-1772

Fill out following information:

Approved for submittal by: (12) Title (13) Co: (14) Phone#: (15)

Emailed by: (16) Title: (17) Co: (18) Phone#: (19)

Date submitted to Tollway: (20) Time submitted to Tollway: (21) If this is a revision, REVISION # (22)

rev 9/21/18 mlk

- 10 - STANDARD LANE/SHOULDER CLOSURE REQUEST

DAYTIME: OVERNIGHT: Monday DATE: 1/21/14 Sun, Mon, Tues, Wed, etc. Sun, Mon, Tues, Wed, etc. Date of Closure(s)

LANE(S) Tollw'y Contract # or CLOSURE from Nearest underpass/overpass LANE(S) TIMES of DIR. or SHLD TYPE OF WORK OPEN CLOSURE # Maint. bldg. M.P. to M.P. X-RD to X-RD CLOSED I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping Left lane 3 Right lanes 7 pm to 8 pm

I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping 2 Left lanes 2 Right lane 8 pm to 11 pm

I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping 3 Left lanes Right lane 11 pm to 6 am Single Rd to Triple Rd (left lane I-294 I-12-1234 96.8 to 97.9 NB Pavement Striping Left lane Right lane 7 pm to 11 pm CD/Aux lane closed) Left cash Right cash I-294 I-12-1234 70.0 NB Extra Plaza Pavement Reconstruction 10 pm to 11 pm approach approach ORT 2, Right ORT 1 & Left I-294 I-12-1234 70.0 NB Extra Plaza Pavement Reconstruction & Center 7 pm to 11 pm cash cash, IPO Entrance ramp from That St to Right side Left side I-90 I-12-1234 3.5 EB Pavement Striping 8 pm to 7 am EB I-90 (Ramp A) ramp ramp I-88 I-12-5678 166.5 to 167.8 WB Right Rd to Left Rd Barrier Wall Relocate Right lane Left lane 9 pm to 4 am

Old Rd I-12-5678 167.9 (off system) NB Old Rd Barrier Wall Relocate Right lane Left lane 9 pm to 4 am

Cancellation notices must be received ASAP with copies also sent to the Traffic Center Staff at [email protected].

All closure requests must be submitted to Lane Closures by e-mail (or by fax if computers down), no later than 9pm of the working day preceding the requested closure(s). Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified. A copy of this request should also go to Maria Burnham in Communications and Elyse Morgan in the Traffic Center.

e-mail: [email protected] Fax#: (630) 241-6112 Phone#: (630) 241-6800 ext. 4822 & 4821 [email protected] (630) 795-2627 (630) 241-6800 ext. 6389 [email protected] (630) 241-6800 ext. 1703 [email protected] (331) 238-1772

Fill out following information:

Approved for submittal by: John Doe Title Resident Engineer Co: Pretend Inc. Phone#: 111-222-4444

Emailed by: Nancy Jones Title: Asst. Resident Engineer Co: Pretend Inc. Phone#: 555-666-7777

Date submitted to Tollway: 02/03/14 Time submitted to Tollway: 7:30 PM If this is a revision, REVISION #

rev 9/21/18 mlk

- 11 - Revisions to Lane Closure Requests Below are directions for filling out a revision to a Standard Lane/Shoulder Closure Request that has been submitted to the Tollway. Page 14 is the Standard Lane/Shoulder Closure Request that has been submitted to the Tollway. Page 13 is what the revision should look like after making changes. Make sure that every section is filled out correctly before submitting to the Tollway. Submit revisions to CCC, TIMS, Elyse Morgan and Lane Closures.

1) Open original lane closure request that was submitted

2) Save a copy

3) Check to make sure that the Save in section lists the location of where the new form will be filed

4) Rename document (make sure that revision is in the title)

5) Make changes to the request in red

6) Down at the bottom of the page change the following information: Date submitted: Type the date revision is submitted to the Tollway Time submitted: Type the time revision is submitted to the Tollway If this is a revision, Type 1 after the # sign

- 12 - 8/28/2018 STANDARD LANE/SHOULDER CLOSURE REQUEST

DAYTIME: OVERNIGHT: Monday DATE: 1/21/14 Sun, Mon, Tues, Wed, etc. Sun, Mon, Tues, Wed, etc. Date of Closure(s)

LANE(S) Tollw'y Contract # or CLOSURE from Nearest underpass/overpass LANE(S) TIMES of DIR. or SHLD TYPE OF WORK OPEN CLOSURE # Maint. bldg. M.P. to M.P. X-RD to X-RD CLOSED I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping Left lane 3 Right lanes 7 pm to 8 pm

I-294 I-12-1234 96.8 to 99.0 NB/SB Single Rd to Triple Rd Pavement Striping 2 Left lanes 2 Right lane 8 pm to 11 pm

I-294 I-12-1234 96.8 to 99.0 NB/SB Single Rd to Triple Rd Pavement Striping 3 Right lanes Left lane 11 pm to 6 am Single Rd to Triple Rd (right lane I-294 I-12-1234 96.8 to 97.9 NB Pavement Striping Right lane Right lane 7 pm to 11 pm CD/Aux lane closed) Left cash Right cash I-294 I-12-1234 70.0 NB Extra Plaza Pavement Reconstruction 10 pm to 11 pm approach approach ORT 1, Right ORT 2 & Left I-294 I-12-1234 70.0 NB Extra Plaza Pavement Reconstruction & Center 7 pm to 11 pm cash cash, IPO Entrance ramp from That St to Right side Left side I-90 I-12-1234 3.5 EB Pavement Marking Removal 8 pm to 7 am EB I-90 (Ramp A) ramp ramp I-88 I-12-5678 166.5 to 167.8 WB Right Rd to Left Rd Barrier Wall Relocate Right lane Left lane 9 pm to 4 am

Old Rd I-12-5678 167.9 (off system) NB Old Rd Barrier Wall Relocate Right lane Left lane 9 pm to 4 am

Cancellation notices must be received ASAP with copies also sent to the Traffic Center Staff at [email protected].

All closure requests must be submitted to Lane Closures by e-mail (or by fax if computers down), no later than 9pm of the working day preceding the requested closure(s). Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified. A copy of this request should also go to Maria Burnham in Communications and Elyse Morgan in the Traffic Center.

e-mail: [email protected] Fax#: (630) 241-6112 Phone#: (630) 241-6800 ext. 4822 & 4821 [email protected] (630) 795-2627 (630) 241-6800 ext. 6389 [email protected] (630) 241-6800 ext. 1703 [email protected] (331) 238-1772

Fill out following information:

Approved for submittal by: John Doe Title Resident Engineer Co: Pretend Inc. Phone#: 111-222-4444

Emailed by: Nancy Jones Title: Asst. Resident Engineer Co: Pretend Inc. Phone#: 555-666-7777

Date submitted to Tollway: 02/03/14 Time submitted to Tollway: 8:00 PM If this is a revision, REVISION # 1

rev 9/21/18 mlk

- 13 - STANDARD LANE/SHOULDER CLOSURE REQUEST

DAYTIME: OVERNIGHT: Monday DATE: 1/21/14 Sun, Mon, Tues, Wed, etc. Sun, Mon, Tues, Wed, etc. Date of Closure(s)

LANE(S) Tollw'y Contract # or CLOSURE from Nearest underpass/overpass LANE(S) TIMES of DIR. or SHLD TYPE OF WORK OPEN CLOSURE # Maint. bldg. M.P. to M.P. X-RD to X-RD CLOSED I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping Left lane 3 Right lanes 7 pm to 8 pm

I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping 2 Left lanes 2 Right lane 8 pm to 11 pm

I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping 3 Left lanes Right lane 11 pm to 6 am Single Rd to Triple Rd (left lane I-294 I-12-1234 96.8 to 97.9 NB Pavement Striping Left lane Right lane 7 pm to 11 pm CD/Aux lane closed) Left cash Right cash I-294 I-12-1234 70.0 NB Extra Plaza Pavement Reconstruction 10 pm to 11 pm approach approach ORT 2, Right ORT 1 & Left I-294 I-12-1234 70.0 NB Extra Plaza Pavement Reconstruction & Center 7 pm to 11 pm cash cash, IPO Entrance ramp from That St to Right side Left side I-90 I-12-1234 3.5 EB Pavement Striping 8 pm to 7 am EB I-90 (Ramp A) ramp ramp I-88 I-12-5678 166.5 to 167.8 WB Right Rd to Left Rd Barrier Wall Relocate Right lane Left lane 9 pm to 4 am

Old Rd I-12-5678 167.9 (off system) NB Old Rd Barrier Wall Relocate Right lane Left lane 9 pm to 4 am

Cancellation notices must be received ASAP with copies also sent to the Traffic Center Staff at [email protected].

All closure requests must be submitted to Lane Closures by e-mail (or by fax if computers down), no later than 9pm of the working day preceding the requested closure(s). Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified. A copy of this request should also go to Maria Burnham in Communications and Elyse Morgan in the Traffic Center.

e-mail: [email protected] Fax#: (630) 241-6112 Phone#: (630) 241-6800 ext. 4822 & 4821 [email protected] (630) 795-2627 (630) 241-6800 ext. 6389 [email protected] (630) 241-6800 ext. 1703 [email protected] (331) 238-1772

Fill out following information:

Approved for submittal by: John Doe Title Resident Engineer Co: Pretend Inc. Phone#: 111-222-4444

Emailed by: Nancy Jones Title: Asst. Resident Engineer Co: Pretend Inc. Phone#: 555-666-7777

Date submitted to Tollway: 02/03/14 Time submitted to Tollway: 8:00 PM If this is a revision, REVISION # rev 9/21/18 mlk

- 14 - Cancellation of Lane Closure Request The cancellation of a lane closure(s) should be sent to Tollway immediately (before 1:00 PM if possible). Cancellations must be communicated immediately to the Incident Manager, CCC, TIMS, Elyse Morgan and Lane Closures as outlined on the lane closure form. This DOES NOT mean that you can cancel part of a lane closure request and ADD a closure. That is a REVISION (refer to page 7 of this document).

During business hours, Monday through Friday, 7 am to 3 pm, the CM/DSE shall email the CCC, TIMS (x1772), Elyse Morgan and Lane Closures.

During after-hours/holiday, from 3 pm to 7 am, weekends and holidays, all lane closures that have been changed (with prior approval by the Tollway)/cancelled should be directed to the Tollway Traffic Center at 630-241-6800 x1772 with a follow up email to CCC, Incident Manager, Elyse Morgan and Lane Closures.

Below are directions for filling out a cancellation to a Standard Lane/Shoulder Closure Request that has already been submitted to the Tollway. Page 17 is the Standard Lane/Shoulder Closure Request that has been submitted to the Tollway. Page 16 is what the cancellation should look like after the changes.

1) Open original lane closure request that you submitted

2) Save a copy

3) Check to make sure that the Save in section lists the location of where the new form will be filed

4) Rename document (make sure that cancellation is in the title)

5) Select all of the information that has been cancelled

6) Go to Home tab then font section and change the color to red

7) In the font dialog box check single strikethrough

8) Down at the bottom of the page change the following information: Date submitted: Type the date cancellation is submitted to the Tollway Time submitted: Type the time cancellation is submitted to the Tollway If this is a revision, Type Cancellation after the # sign

- 15 - 9/19/2018 STANDARD LANE/SHOULDER CLOSURE REQUEST

DAYTIME: OVERNIGHT: Monday DATE: 1/21/14 Sun, Mon, Tues, Wed, etc. Sun, Mon, Tues, Wed, etc. Date of Closure(s)

LANE(S) Tollw'y Contract # or CLOSURE from Nearest underpass/overpass LANE(S) TIMES of DIR. or SHLD TYPE OF WORK OPEN CLOSURE # Maint. bldg. M.P. to M.P. X-RD to X-RD CLOSED I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping Left lane 3 Right lanes 7 pm to 8 pm

I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping 2 Left lanes 2 Right lane 8 pm to 11 pm

I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping 3 Left lanes Right lane 11 pm to 6 am Single Rd to Triple Rd (left lane I-294 I-12-1234 96.8 to 97.9 NB Pavement Striping Left lane Right lane 7 pm to 11 pm CD/Aux lane closed) Left cash Right cash I-294 I-12-1234 70.0 NB Extra Plaza Pavement Reconstruction 10 pm to 11 pm approach approach ORT 2, Right ORT 1 & Left I-294 I-12-1234 70.0 NB Extra Plaza Pavement Reconstruction & Center 7 pm to 11 pm cash cash, IPO Entrance ramp from That St to Right side Left side I-90 I-12-1234 3.5 EB Pavement Striping 8 pm to 7 am EB I-90 (Ramp A) ramp ramp I-88 I-12-5678 166.5 to 167.8 WB Right Rd to Left Rd Barrier Wall Relocate Right lane Left lane 9 pm to 4 am

Old Rd I-12-5678 167.9 (off system) NB Old Rd Barrier Wall Relocate Right lane Left lane 9 pm to 4 am

Cancellation notices must be received ASAP with copies also sent to the Traffic Center Staff at [email protected].

All closure requests must be submitted to Lane Closures by e-mail (or by fax if computers down), no later than 9pm of the working day preceding the requested closure(s). Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified. A copy of this request should also go to Maria Burnham in Communications and Elyse Morgan in the Traffic Center.

e-mail: [email protected] Fax#: (630) 241-6112 Phone#: (630) 241-6800 ext. 4822 & 4821 [email protected] (630) 795-2627 (630) 241-6800 ext. 6389 [email protected] (630) 241-6800 ext. 1703 [email protected] (331) 238-1772

Fill out following information:

Approved for submittal by: John Doe Title Resident Engineer Co: Pretend Inc. Phone#: 111-222-4444

Emailed by: Nancy Jones Title: Asst. Resident Engineer Co: Pretend Inc. Phone#: 555-666-7777

Date submitted to Tollway: 02/03/14 Time submitted to Tollway: 8:30 PM If this is a revision, REVISION # Cancellation rev 9/21/18 mlk

- 16 - STANDARD LANE/SHOULDER CLOSURE REQUEST

DAYTIME: OVERNIGHT: Monday DATE: 1/21/14 Sun, Mon, Tues, Wed, etc. Sun, Mon, Tues, Wed, etc. Date of Closure(s)

LANE(S) Tollw'y Contract # or CLOSURE from Nearest underpass/overpass LANE(S) TIMES of DIR. or SHLD TYPE OF WORK OPEN CLOSURE # Maint. bldg. M.P. to M.P. X-RD to X-RD CLOSED I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping Left lane 3 Right lanes 7 pm to 8 pm

I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping 2 Left lanes 2 Right lane 8 pm to 11 pm

I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping 3 Left lanes Right lane 11 pm to 6 am Single Rd to Triple Rd (left lane I-294 I-12-1234 96.8 to 97.9 NB Pavement Striping Left lane Right lane 7 pm to 11 pm CD/Aux lane closed) Left cash Right cash I-294 I-12-1234 70.0 NB Extra Plaza Pavement Reconstruction 10 pm to 11 pm approach approach ORT 2, Right ORT 1 & Left I-294 I-12-1234 70.0 NB Extra Plaza Pavement Reconstruction & Center 7 pm to 11 pm cash cash, IPO Entrance ramp from That St to Right side Left side I-90 I-12-1234 3.5 EB Pavement Striping 8 pm to 7 am EB I-90 (Ramp A) ramp ramp I-88 I-12-5678 166.5 to 167.8 WB Right Rd to Left Rd Barrier Wall Relocate Right lane Left lane 9 pm to 4 am

Old Rd I-12-5678 167.9 (off system) NB Old Rd Barrier Wall Relocate Right lane Left lane 9 pm to 4 am

Cancellation notices must be received ASAP with copies also sent to the Traffic Center Staff at [email protected].

All closure requests must be submitted to Lane Closures by e-mail (or by fax if computers down), no later than 9pm of the working day preceding the requested closure(s). Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified. A copy of this request should also go to Maria Burnham in Communications and Elyse Morgan in the Traffic Center.

e-mail: [email protected] Fax#: (630) 241-6112 Phone#: (630) 241-6800 ext. 4822 & 4821 [email protected] (630) 795-2627 (630) 241-6800 ext. 6389 [email protected] (630) 241-6800 ext. 1703 [email protected] (331) 238-1772

Fill out following information:

Approved for submittal by: John Doe Title Resident Engineer Co: Pretend Inc. Phone#: 111-222-4444

Emailed by: Nancy Jones Title: Asst. Resident Engineer Co: Pretend Inc. Phone#: 555-666-7777

Date submitted to Tollway: 02/03/14 Time submitted to Tollway: 7:30 PM If this is a revision, REVISION # rev 9/21/18 mlk

- 17 - 10 Day Advance Lane/Shoulder Closure Request For any project with major disruption of traffic, especially for medium or long term duration, start of new construction, major traffic shift, stage change, closing ramps, closing mainline or local roads for any time duration (includes intermittent Full Closures) or whenever construction activity will have a new and/or significant impact to traffic movements and flow, a 10 Day Advance Lane/Shoulder Closure Request must be submitted. This information is for Media-Alert purposes only; no closures are “Permitted” with this request. The information will give the Tollway time to notify the weekday and weekend drivers, issue accurate and timely press releases/construction alerts to the media and draft content of Portable Changeable Message Sign (PCMS)/Dynamic Message Sign (DMS) messages.

Below are directions on how to fill out a 10 Day Advanced Lane/Shoulder Closure Request. Page 20 is a sample of what the request should look like after all the information has been input. Make sure that every section is filled out correctly before submitting to the Tollway. Submit requests to CCC, TIMS, Elyse Morgan and Lane Closures.

NOTE: A Standard Lane/Shoulder Request still needs to be submitted. When the 10 Day Advance Lane/Shoulder Closure Request is submitted to the Tollway, the start date for the work to begin should be no less than 10 DAYS FROM THE DATE REQUEST WAS SUBMITTED NO EXCEPTIONS. If the date on a 10 Day Advance Lane/Shoulder Closure Request is delayed, a revised 10 Day Advance Lane/Shoulder Closure Request must be sent in.

1) Daytime or Overnight Day: Type the day of closure (i.e. Monday, Tuesday, Wednesday, etc.)

2) Date of Closure: Type the date of the closure (i.e. 1/21/14)

3) Tollway Number: Type the Tollway number/Local Road name (i.e. I-90, I-94, Maple Av, etc.)

4) Contract/Permit or Maintenance Number: Type the contract/permit or maintenance number (i.e. I-12-1234)

5) Mileposts: Type the starting milepost number and the ending milepost number (little to big regardless of which direction, i.e. 96.8 to 97.9). List A

6) Direction: Type the direction of closure (i.e. EB, WB, SB, NB)

7) Nearest Underpass/Overpass: Type the starting nearest underpass/overpass to ending nearest underpass/overpass (i.e. Single Rd to Triple Rd) List A

8) Type of Work: Type in the type of work (i.e. Pavement Striping) List B

9) Lane(s)/Shoulder Closed: Type the lane(s)/shoulder that will be closed (i.e. Left Lane) List C

10) Lane(s)/Shoulder Open: Type the lane(s)/shoulder that will be open (i.e. 2 Right Lanes) List C

11) Times of Closure: Type the start date & time to the end date & time of the closure (i.e. 1/21/14 @ 5am to 3/23/14 @ 5am)

12) Why Necessary? Type why significant lane closure is required/necessary (see sample)

13) How Reducing Impact?: Type how the contractor is minimizing the disruption of traffic flow for this closure (see sample)

14) Date submitted: Type the date request is submitted to the Tollway

15) Time submitted: Type the time request is submitted to the Tollway

16) Project#: Type the project (contract/permit) number

17) Name: Type the Resident Engineer’s name

18) Co: Type the Resident Engineer’s company

19) Title: Type the Resident Engineer’s title

20) Phone #: Type the Resident Engineer’s phone number

- 18 - 8/28/2018

10 DAY ADVANCE LANE/SHOULDER CLOSURE REQUEST

DAY: (1) NIGHT: (1) DATE: (2) Sun, Mon, Tues, Wed, etc. Sun, Mon, Tues, Wed, etc. Date of Closure(s)

CLOSURE LANE(S) Tollw'y Nearest underpass/overpass LANE(S) TIMES of Contract # or from or SHLD DIR. TYPE OF WORK OPEN CLOSURE # Maint. bldg. M.P. to M.P. X-RD to X-RD CLOSED

I- (3) (4) (5) (6) (7) (8) (9) (10) (11) I- I- I-

I-

Cancellation notices must be received ASAP with copies also sent to the Traffic Center Staff at [email protected]. Why Necessary? (12)

How Reducing Impact? (13)

All closure requests must be submitted to Lane Closures by e-mail, no later than 9pm 10 days in advance of the start of new construction or any major change in traffic. Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified. A copy of this request should also go to Maria Burnham in Communications, Elyse Morgan in the Traffic Center and to the Traffic Center Staff.

e-mail: [email protected] Phone#: (630) 241-6800 ext. 4822 & 4821 [email protected] (630) 241-6800 ext. 6389 [email protected] (630) 241-6800 ext. 1703 [email protected] (331) 238-1772

Date submitted to Tollway: (14) Time submitted to Tollway: (15) Project # (16)

NPME: (17) Co: (18) Title: (19) Phone#: (20)

rev 9/21/18 mlk

- 19 -

10 DAY ADVANCE LANE/SHOULDER CLOSURE REQUEST

DAY: Tuesday NIGHT: DATE: 1/21/14 Sun, Mon, Tues, Wed, etc. Sun, Mon, Tues, Wed, etc. Date of Closure(s)

CLOSURE LANE(S) Tollw'y Nearest underpass/overpass LANE(S) TIMES of Contract # or from or SHLD DIR. TYPE OF WORK OPEN CLOSURE # Maint. bldg. M.P. to M.P. X-RD to X-RD CLOSED

Detour 1/21/14 @ 5pm to I-294 I-12-1234 40.9 NB Entrance rpmp from EB I-88 Rpmp Replacement Rpmp Closed Posted 3/23/14 @ 5pm

I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Striping Left lane 2 Right lanes 5 pm to 8 pm

I-294 I-12-1234 96.8 to 98.0 NB/SB Single Rd to Triple Rd Pavement Striping 2 Right lanes Left Lane 8 pm to 10 pm

Cancellation notices must be received ASAP with copies also sent to the Traffic Center Staff at [email protected]. Closing entrance rpmp to convert rpmp from one lane to two lanes. Rpmp will close at 5 pm on Monday, February 6th and reopen Why Necessary? at 8 pm on Friday, March 23rd This will eliminate traffic backing up on EB-I88 to enter NB I-294. Closing both NB & SB lanes for pavement re-striping.

How Reducing Impact? Traffic will be detoured Car Rd for access to NB I-294. Closing both NB & SB lanes for pavement re-striping is to help the public with traffic flow. Pavement markings are confusing son of the public.

All closure requests must be submitted to Lane Closures by e-mail, no later than 9pm 10 days in advance of the start of new construction or any major change in traffic. Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified. A copy of this request should also go to Maria Burnham in Communications, Elyse Morgan in the Traffic Center and to the Traffic Center Staff.

e-mail: [email protected] Phone#: (630) 241-6800 ext. 4822 & 4821 [email protected] (630) 241-6800 ext. 6389 [email protected] (630) 241-6800 ext. 1703 [email protected] (331) 238-1772

Date submitted to Tollway: 01/06/14 Time submitted to Tollway: 8:44 pm Project # I-12-1234

NPME: Nancy Jones Co: Pretend, Inc. Title: Asst. RE Phone#: 555-666-7777

rev 9/21/18 mlk

- 20 - Long Term Request The information provided for a Long Term closure is for lane/shoulder closures that will be closed for 24 hours over three (3) or more consecutive days such as Monday, Tuesday & Wednesday (72 hours or more). Weekend closures are not considered a Long Term closure.

Below are directions for filling out a Long Term Lane/Shoulder Closure Request. Page 23 is a sample of what the request should look like after all the information has been input. Make sure that every section is filled out correctly before submitting to the Tollway. Submit requests to CCC, TIMS, Elyse Morgan and Lane Closures.

1) Daytime or Overnight Day: Type the day of closure (i.e. Monday, Tuesday, Wednesday, etc.)

2) Date of Closure: Type the date of the closure (i.e. 1/21/14 to 3/23/14)

3) Tollway Number: Type the Tollway number/Local Road name (i.e. I-90, I-94, Maple Av, etc.)

4) Contract/Permit or Maintenance Number: Type the contract/permit or maintenance number (i.e. I-12-1234)

5) Mileposts: Type the starting milepost number and the ending milepost number (little to big regardless of which direction, i.e. 96.8 to 97.9). List A

6) Direction: Type the direction of closure (i.e. EB, WB, SB, NB)

7) Nearest Underpass/Overpass: Type the starting nearest underpass/overpass to ending nearest underpass/overpass (Single Rd to Triple Rd) List A

8) Type of Work: Type in the type of work listed Pavement Reconstruction. List B

9) Lane(s)/Shoulder Closed: Type the lane(s)/shoulder that will be (i.e. Left Lane). List C

10) Lane(s) or Shoulder Open: Type the lane(s) that will be open (i.e. 2 Right Lanes). List C

11) Times of Closure: Type the start date & time to the end date & time of the closure (i.e. 1/21/14 @ 5am to 3/23/14 @ 5am)

12) Approved for submittal by: Type the Resident Engineer’s name that will be approving the lane closure request

13) Title: Type the Resident Engineer’s title

14) Company: Type the Resident Engineer’s company

15) Phone #: Type the Resident Engineer’s phone number (27/7)

16) Emailed by: Type your name

17) Title: Type your title

18) Company: Type your company

19) Phone #: Type your phone number (24/7)

20) Date submitted: Type the date request is submitted to the Tollway

21) Time submitted: Type the time request is submitted to the Tollway

22) If this is a revision,: Leave blank

- 21 - 8/28/2018

LONG TERM STANDARD LANE/SHOULDER CLOSURE REQUEST DAYTIME: (1) OVERNIGHT: (1) DATE: (2) Sun, Mon, Tues, Wed, etc. Sun, Mon, Tues, Wed, etc. Date of Closure(s)

LANE(S) Tollw'y CLOSURE from Nearest underpass/overpass LANE(S) TIMES of Contract # or or SHLD DIR. TYPE OF WORK OPEN CLOSURE # Maint. bldg. M.P. to M.P. X-RD to X-RD CLOSED

(3) (4) (5) (6) (7) (8) (9) (10) (11)

I-

I-

I-

I-

I-

I-

I-

I-

Cancellation notices must be received ASAP with copies also sent to the Traffic Center Staff at [email protected].

All closure requests must be submitted to Lane Closures by e-mail (or by fax if computers down), no later than 9pm of the working day preceding the requested closure(s). Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified. A copy of this request should also go to Maria Burnham in Communications and Elyse Morgan in the Traffic Center.

e-mail: [email protected] Fax#: (630) 241-6112 Phone#: (630) 241-6800 ext. 4822 & 4821 [email protected] (630) 795-2627 (630) 241-6800 ext. 6389 [email protected] (630) 241-6800 ext. 1703 [email protected] (331) 238-1772

Fill out following information:

Approved for submittal by: (12) Title: (13) Co: (14) Phone#: (15)

Emailed by: (16) Title: (17) Co: (18) Phone#: (19)

Date submitted to Tollway: (20) Time submitted to Tollway: (21) If this is a revision, REVISION # (22)

rev 9/21/18 mlk

- 22 - LONG TERM STANDARD LANE/SHOULDER CLOSURE REQUEST

DAYTIME: Tuesday OVERNIGHT: DATE: 1/21/14 to 3/23/14 Sun, Mon, Tues, Wed, etc. Sun, Mon, Tues, Wed, etc. Date of Closure(s)

LANE(S) Tollw'y Contract # or CLOSURE from Nearest underpass/overpass LANE(S) TIMES of DIR. or SHLD TYPE OF WORK OPEN CLOSURE # Maint. bldg. M.P. to M.P. X-RD to X-RD CLOSED 1/21/14 @ 5pm to I-294 I-12-1234 96.8 to 97.9 NB/SB Single Rd to Triple Rd Pavement Reconstruction Left lane 2 Right lanes 3/23/14 @ 5pm I- Both All lanes 1/21/14 @ 5pm to I-294 I-12-1234 100.1 to 102.0 NB Double Rd to Always Rd Pavement Reconstruction Shoulders shifted right 3/23/14 @ 5pm I-

I-

I-

I-

I-

Cancellation notices must be received ASAP with copies also sent to the Traffic Center Staff at [email protected].

All closure requests must be submitted to Lane Closures by e-mail (or by fax if computers down), no later than 9pm of the working day preceding the requested closure(s). Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified. A copy of this request should also go to Maria Burnham in Communications and Elyse Morgan in the Traffic Center.

e-mail: [email protected] Fax#: (630) 241-6112 Phone#: (630) 241-6800 ext. 4822 & 4821 [email protected] (630) 795-2627 (630) 241-6800 ext. 6389 [email protected] (630) 241-6800 ext. 1703 [email protected] (331) 238-1772

Fill out following information:

Approved for submittal by: John Doe Title: Resident Engineer Co: Pretend Inc. Phone#: 111-222-4444

Emailed by: Nancy Jones Title: Asst. Resident Engineer Co: Pretend Inc. Phone#: 555-666-777

Date submitted to Tollway: 2/3/14 Time submitted to Tollway: 7:30 PM If this is a revision, REVISION #

rev 9/21/18 mlk

- 23 - Standard Lane/Shoulder Closure Requests with Trooper Assistance A scheduled or contract closure typically includes a MOT plan that has been previously submitted, reviewed and approved. Notification shall state when closure will start, where the closure is located, direction of travel, lanes involved, description of the closure and the duration of the closure.

Below are directions for filling out a Standard Lane/Shoulder Closure Request with Trooper Assistance. Page 26 is a sample of what the request should look like after all the information has been input. Make sure that every section is filled out correctly before submitting to the Tollway. Submit requests to CCC, TIMS, Elyse Morgan and Lane Closures.

1) Daytime or Overnight Day: Type the day of closure (i.e. Monday, Tuesday, Wednesday, etc.)

2) Date of Closure: Type the date of the closure (i.e. 1/21/14)

3) Tollway #: Type the Tollway number/Local Road name (i.e. I-90, I-94, Maple Av, etc.)

4) Contract/Permit or Maint. Bldg. Number: Type the contract/permit or maintenance number (i.e. I-12-1234)

5) Mileposts: Type the starting milepost number and the ending milepost number (little to big regardless of which direction, i.e. 96.8 to 97.9). List A

6) Direction: Type the direction of closure (i.e. EB, WB, SB, NB)

7) Nearest Underpass/Overpass: Type the starting nearest underpass/overpass to ending nearest underpass/overpass (i.e. Single Rd to Triple Rd). List A

8) Type of Work: Type the type of work listed (i.e. Pavement Striping). List B

9) Lane(s)/Shoulder Closed: Type the lane(s)/shoulder that will be closed (i.e. 2 Left Lanes). List C

10) Lane(s)/Shoulder Open: Type the lane(s)/shoulder that will be open (i.e. Right Lane). List C

11) Times of Closure: Type the start time to the end time of closure (i.e. 8:00 pm - 5:00 am)

12) Skip a row or 2.

13) Select the entire row. Right mouse click and select merge cells. On the paragraph toolbar click on center then type information for full closure (i.e. SIX (6) 15 SB minute FULL CLOSURES with Trooper Assistance at 12:01 am, 1:00 am, 1:30 am, 2:00 am, 2:30 am & 3:00 am)

14) Approved for submittal by: Type the Resident Engineer’s name that will be approving the lane closure request

15) Title: Type the Resident Engineer’s title

16) Company: Type the Resident Engineer’s company

17) Phone #: Type the Resident Engineer’s phone number (24/7)

18) Emailed by: Type your name

19) Title: Type your title

20) Company: Type your company

21) Phone #: Type your phone number (24/7)

22) Date submitted: Type the date request is submitted to the Tollway

23) Time submitted: Type the time request is submitted to the Tollway

24) If this is not a revision,: Leave blank

- 24 - 8/28/2018 STANDARD LANE/SHOULDER CLOSURE REQUEST

DAYTIME: (1) OVERNIGHT: (1) DATE: (2) Sun, Mon, Tues, Wed, etc. Sun, Mon, Tues, Wed, etc. Date of Closure(s)

LANE(S) Tollw'y Contract # or CLOSURE from Nearest underpass/overpass LANE(S) TIMES of DIR. or SHLD TYPE OF WORK OPEN CLOSURE # Maint. bldg. M.P. to M.P. X-RD to X-RD CLOSED (3) (4) (5) (6) (7) (8) (9) (10) (11)

I-

(12)

I-

I-

I-

I-

I-

I-

Cancellation notices must be received ASAP with copies also sent to the Traffic Center Staff at [email protected].

All closure requests must be submitted to Lane Closures by e-mail (or by fax if computers down), no later than 9pm of the working day preceding the requested closure(s). Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified. A copy of this request should also go to Maria Burnham in Communications and Elyse Morgan in the Traffic Center.

e-mail: [email protected] Fax#: (630) 241-6112 Phone#: (630) 241-6800 ext. 4822 & 4821 [email protected] (630) 795-2627 (630) 241-6800 ext. 6389 [email protected] (630) 241-6800 ext. 1703 [email protected] (331) 238-1772

Fill out following information:

Approved for submittal by: (13) Title: (14) Co: (15) Phone#: (16)

Submitted by: (17) Title: (18) Co: (19) Phone#: (20)

Date submitted to Tollway: (21) Time submitted to Tollway: (22) If this is a revision, REVISION # (23)

rev 9/21/18 mlk

- 25 - STANDARD LANE/SHOULDER CLOSURE REQUEST

DAYTIME: OVERNIGHT: Monday DATE: 1/21/14 Sun, Mon, Tues, Wed, etc. Sun, Mon, Tues, Wed, etc. Date of Closure(s)

LANE(S) Tollw'y Contract # or CLOSURE from Nearest underpass/overpass LANE(S) TIMES of DIR. or SHLD TYPE OF WORK OPEN CLOSURE # Maint. bldg. M.P. to M.P. X-RD to X-RD CLOSED I-294 I-12-1234 96.8 to 97.9 NB Single Rd to Triple Rd Pavement Striping Left lane 2 Right lanes 6 pm to 8 pm

I-294 I-12-1234 96.8 to 97.9 NB Single Rd to Triple Rd Pavement Striping 2 left lanes Right lane 8 pm to 5 pm

SIX (6) NB FULL CLOSURES with Trooper Assistance at 12:01 pm, 1:00 pm, 1:30 pm, 2:00 pm, 2:30 pm, 3:00 pm

I-

I-

I-

I-

I-

I-

Cancellation notices must be received ASAP with copies also sent to the Traffic Center Staff at [email protected].

All closure requests must be submitted to Lane Closures by e-mail (or by fax if computers down), no later than 9pm of the working day preceding the requested closure(s). Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified. A copy of this request should also go to Maria Burnham in Communications and Elyse Morgan in the Traffic Center.

e-mail: [email protected] Fax#: (630) 241-6112 Phone#: (630) 241-6800 ext. 4822 & 4821 [email protected] (630) 795-2627 (630) 241-6800 ext. 6389 [email protected] (630) 241-6800 ext. 1703 [email protected] (331) 238-1772

Fill out following information:

Approved for submittal by: John Doe Title Resident Engineer Co: Pretend Inc. Phone#: 111-222-4444

Emailed by: Nancy Jones Title: Asst. Resident Engineer Co: Pretend Inc. Phone#: 555-666-7777

Date submitted to Tollway: 2/3/14 Time submitted to Tollway: 7:30 PM If this is a revision, REVISION #

rev 9/21/18 mlk

- 26 - State Trooper Assistance Form District 15 State Police require a 48 hour advanced notice for their assistance with FULL CLOSURES. Make sure the proper paperwork is submitted in a timely manner. If contractor needs to cancel the Trooper Assistance, the PROJECT MANAGER must make sure that the State Police are notified as soon as possible. The State Police can be reached at: 630-241-6800, option “7”. Speak directly to the Shift Commander and explain the reason for cancelling the closure, then ask that an email be sent from the Traffic Center to radio noting the cancellation of the closure. Radio will then issue a “Tollway Critical” page alerting management that the closure has been cancelled. If the closure was a day-time closure which would have impacted traffic, Tollway Communications will alert the appropriate Media outlets.

Submittals Due Wednesday - must be submitted by Monday before 9:00 AM. Thursday - must be submitted by Tuesday before 9:00 AM. Friday - must be submitted by Wednesday before 9:00 AM. Saturday - must be submitted by Thursday before 9:00 AM. Sunday, Monday or Tuesday - must be submitted by Friday before 9:00 AM.

There are 16 places on the form that require information and/or signature by Requestor:

1) Assistance Date Date for which you are requesting State Police assistance. 2) Assistance Start Time Starting time(s) of the full closure(s) (Note: For closures starting at Midnight, indicate 12:01 a.m. and the proper calendar date). 3) Requestor Project Manager Name. 4) Requestor’s Title Project Manager Name. 5) Contract/Permit Number Contract/Permit number. 6) Date Submitted Date submitted to the Tollway. 7) Time Submitted Time the request is submitted to the Tollway. 8) Tollway The Tollway Interstate numerical identification. (i.e., I-294, I-90, I-88, etc.) needed. 9) Direction Travel direction for affected traffic. (i.e., EB, WB, NB, SB) 10) Milepost Milepost location for closure (limits of lanes affected). 11) Activity Work being performed requiring the full closure. 12) Lane(s) Closed List each lane(s) closed and each start time. (sample shown on request) Time of Closure(s) 13) PM Project Manager Name & 24/7 cell phone number. 14) CM Construction Manager Name & 24/7 cell phone number. 15) Contractor Name of contractor & 24/7 cell phone number. 16) Chief of Toll Operations Leave Blank - The Chief of Toll Operations will sign ONLY if Mainline plaza lanes are being closed. 17) Shift Commander Leave Blank - The District 15 Shift Commander receiving the closure request Receiving Request must sign and date the closure request when received on the lines below the signature line.

PHONE NUMBERS GIVEN MUST NOT GO TO VOICE MAIL.

- 27 - 8/28/2018 THE ILLINOIS STATE TOLL HIGHWAY AUTHORITY District 15 Assistance Form 48 HOUR ADVANCE NOTICE REQUIRED

TO: LT. Chiappini, LT. Bradley 1 Assistance Date: LT. Hodgdon, ALT. Hasan ALT. Swanson District 15 Shift Commander 2 Assistance Start Time:

3 REQUESTOR: 6 Date Submitted: 4 (Project Manager) 5 CONTRACT #: 7 Time Submitted:

8 TOLLWAY: (i.e., I-294, I-94, I-90, I-88, I-355)

9 DIRECTION: (i.e., EB, WB, NB, SB) 10 M.P. to M.P.

11 This closure is required for :

The Maintenance of Traffic (MOT) contractor will have lane closures fully erected at least 15 minutes before the start time for first closure.

12 Engineering is requesting State Police assistance for traffic control and/or temporary lane shutdown as outlined below:

Lane(s) Closed Start Time of Closure(s) End Time of Closure(s)

Phone Numbers: 24/7 required Chief of Toll Operations (When Mainline Toll Plazas are involved) 13 Project Manager: 14 Construction Manager: 15 Contractor: Date: Time:

Requestor – Must obtain Shift Commander’s D-15 Shift Commander Receiving Request Signature then “cc” those below:

cc: Maint District Manager; M-Section Manager 16 ID: Incident Manager; Maria Burnham Elyse Morgan, TIMS / TOC; Lane Closures Date: Time:

cc: Operations Lieutenant, Zone M/Sergeant, Zone Sergeant, Radio

*** District 1 - Joe Dragovich: M-1, M-2, M-8, M-11, M-12, M-14 *** District 2 – Rohan Gayle: M-3, M-4, M-5, M-6, M-7, M-16 August 2018 - 28 - THE ILLINOIS STATE TOLL HIGHWAY AUTHORITY District 15 Assistance Form 48 HOUR ADVANCE NOTICE REQUIRED

TO: LT. Chiappini, LT. Bradley Assistance Date: 01/21/15 LT. Hodgdon, ALT. Hasan ALT. Swanson District 15 Shift Commander Assistance Start Time: 12:01 AM

REQUESTOR: John Doe Date Submitted: 01/18/15 (Project Manager) CONTRACT #: I-12-1234 Time Submitted 7:30 AM

TOLLWAY: I-294 (i.e., I-294, I-94, I-90, I-88, I-355)

DIRECTION: NB (i.e., EB, WB, NB, SB) M.P. 96.8 to M.P. 97.9

This closure is required for: Installation of barrier wall to restripe pavement for the next stage.

The Maintenance of Traffic (MOT) contractor will have lane closures fully erected at least 15 minutes before the start time for first closure.

Engineering is requesting State Police assistance for traffic control and/or temporary lane shutdown as outlined below:

Lane(s) Closed Start Time of Closure(s) End Time of Closure(s)

1, 2, 3 12:01 AM 12:16 AM 1, 2, 3 1:00 AM 1:15 AM 1, 2, 3 1:30 AM 1:45 AM 1, 2, 3 2:00 AM 2:15 AM 1, 2, 3 2:30 AM 2:45 AM 1, 2, 3 3:00 AM 3:15 AM

Phone Numbers: 24/7 required Chief of Toll Operations (When Mainline Toll Plazas are involved) Project Manager: John Doe (630) 222-2222 Construction Manager: James Smith (630) 333-3333 Contractor: The Contractor Name (630) 444-4444 Date: Time:

Requestor – Must obtain Shift Commander’s D-15 Shift Commander Receiving Request Signature then “cc” those below:

cc: Maint District Manager; M-Section Manager ID: Incident Manager; Maria Burnham Elyse Morgan, TIMS / TOC; Lane Closures Date: Time:

cc: Operations Lieutenant, Zone M/Sergeant, Zone Sergeant, Radio *** District 1 - Joe Dragovich: M-1, M-2, M-8, M-11, M-12, M-14 *** District 2 – Rohan Gayle: M-3, M-4, M-5, M-6, M-7, M-16 August 2018 - 29 - Emergency Closure/Holiday or After Business Hours Requests 3PM - 7AM Below states what an emergency lane closure is and the directions to get a request approved and processed. Fill out a Standard Lane/Shoulder Closure Request. Email request to the Tollway for approval. In the BODY OF THE EMAIL, type the reason for the emergency lane closure request. Include the mileposts, direction, crossroads, lanes closed and open and the hours of the request. Email to everyone you normally do and include the Incident Manager asking for approval for the request.

SUBJECT: EMERGENCY LANE CLOSURE/HOLIDAY REQUESTS/OR AFTER BUSINESS HOURS REQUEST 3PM-7AM

1. When an emergency repair/action is needed the standard lane/shoulder closure request form still must be completed, even though the approval process can occur verbally.

2. The Construction Manager and Project Manager must approve the request and forward the request to Lane Closures.

3. The CCM and/or the CM and/or the Project Manager must obtain the Tollway’s approval through direct verbal contact with the Incident Manager or in his absence the Roadway Maintenance Manager.

4. Incident Manager’s approval of Emergency Lane Closures shall be limited to a bona fide Emergency Condition that effect safe and efficient performance of the Toll road. Failure to meet established deadlines for daily lane closures alone will not qualify for approval by the Incident Manager. These requests will be denied.

5. After receiving Tollway approval, the CCM and/or CM must directly notify Communications Vacant x6381, Lane Closures via email, Traffic Center x1772, Maintenance Section Manager and Plaza Manager (if applicable). The Incident Manager / Roadway Maintenance District Manager / Roadway Maintenance Manager will advise Traffic Center/Dispatch and ISP Operations that the Emergency Closure has been approved and the Dispatch will send out a critical page with the closure information, further signifying Tollway approval of the Emergency Closure.

6. Late requests for lane closures as a rule will not be allowed unless approval is received from the Incident Manager.

Your assistance in notifying the Construction Team Managers is requested.

INCIDENT MANAGER 630-241-6800, extension 4904 630-201-6209 (CELL)

ROADWAY MAINTENANCE MANAGER 630-241-6800, extension 4913 331-251-4578 (CELL)

- 30 - 9/19/2018 Tollway/CM/Contractor PCMS Deployment and Maintenance Guide The information herein is intended as a reference guide regarding the use of TIMS-compatible Portable Changeable Message Signs (PCMS) when deployed on Tollway construction sites. When a construction contract requires the use of TIMS-compatible signs, the placement of the signs will be spelled out in the Maintenance and Traffic standards required in the construction contract document. It is important to note that the construction contract may allow non-TIMS- compatible signs. However, when a contract requires the use of TIMS-compatible signs the contractor must use these signs; no alternates are allowed.

The TIMS-compatible signs outlined and listed in the construction contract documents are designed to communicate with the Tollway’s Traffic and Incident Management System (TIMS). This communication uses specialized software developed for this purpose. The construction contracts identify signs by make and model, which are TIMS pre-qualified and can be used on Tollway construction projects.

Due to the programming of messages by TIMS, knowing the exact location of all signs is critical. The Traffic Center is to be notified immediately before signs are moved to new locations or taken off the job. If a sign loses communication with TIMS for any reason (i.e. struck by vehicle, equipment failure, etc.), it is responsibility of the contractor to ensure replacement within 24 hours.

The following is information to answer many questions on the use of PCMS’s on Tollway construction projects.

1. When Full Matrix or TIMS-compatible PCMS’s are required to be used on Tollway construction sites, the signs to be used on the sites are to be delivered to the Tollway’s Central Shop (3460 S. Finley Rd Downers Grove IL) before placement at the job site. This applies to all signs going onto a Tollway job for the first time, as well as signs that have not been on a Tollway project for more than 90 days.

2. All correspondence regarding PCMS signs with the Tollway’s Traffic Center and Communications Department is to include the Tollway PCMS sign identifier number placed on the sign by the Tollway.

3. Full Matrix PCMS’s are to be programmable by the Tollway’s TIMS system. The quantity of TIMS-compatible PCMS’s per direction of work zone will be spelled out in the Maintenance of traffic portion of the contract specifications.

4. The CM is responsible for formulating messages for approval by the Tollway’s Incident Manager for preconstruction messages.

5. The CM is to submit a weekly report of all PCMS’s used in his/her construction zone. That report will contain Owner, Tollway Sign Number, Location, currently displayed message and contact information to be used to report malfunctions or for sign status inquiries. This report will uploaded to e-builder every Monday.

6. The weekly report will be revised and submitted each time a move occurs to any TIMS-programmable PCMS.

7. Automated Vehicle Location systems (AVL) on all TIMS compatible signs are to remain on/powered and correctly reporting while on a Tollway project. - 31 - 9/19/2018

8. AVL is to be turned off or disabled if a TIMS compatible PCMS is removed from a Tollway project.

9. The age and sign quality is of importance and signs that do not meet the standards of the Tollway will not be allowed on projects. Signs that are in poor physical appearance or that have more than three failures in a 12 month period must be removed and not returned.

10. Any sign replacing a TIMS-compatible sign for maintenance or repairs must be a Tollway approved sign marked with a Tollway identifying number and be TIMS compatible.

11. As construction contracts close and PCMS’s are ready to be taken off the site, the Traffic Center is to be notified of the move. The CM is to verify with the Tollway Project Manager the status of the TIMS-compatible signs.

The following are the Tollway Contacts:

Incident Manager Steve Mednis [email protected] 630-241-6800 ext 4904

Traffic Operations Department Elyse Morgan [email protected] 630-241-6800 ext 1703 TIMS Center [email protected] 630-241-6800 ext 1772

Tollway Communications Department Joelle McGinnis [email protected] 630-241-6800 ext 6380 Vacant 630-241-6800 ext 6381 Maria Burnham [email protected] 630-241-6800 ext 6389

Tollway Fleet unit Tom Deldin [email protected] 630-241-6800 ext 4919

Central Shop 630-241-6800 ext 4551

- 32 - 9/19/2018 PCMS APPROVAL FORM

Project # Sign Number Location

Phase 1

Phase 2

Project # Sign Number Location

Phase 1

Phase 2

Project # Sign Number Location

Phase 1

Phase 2

[email protected] [email protected]

- 33 - Other Lane Closure Details

Published Lane Closure Report The published lane closure report is emailed out at approximately 2:00 PM Monday through Friday. Take a moment to review the daily Lane Closure Report once you receive it to make sure that your closure is on the report and that it is correct.

This way everyone can be notified if a closure did not make the report or if there is a correction that needs to be made before Maintance leaves at 3:00 PM.

Breakdown of Daytime & Overnight Hours when filling out Lane Closure Requests Daytime Hours 7:00 am to 7:00 pm Overnight Hours 7:00 pm to 7:00 am

Subject Line When Emailing Closures When emailing your lane closure to the Tollway you need to add in the subject line, the contract number, date of closure and if the closure is a day or night closure (i.e. 1234-10242006-Night).

Ask for a Read Receipt Designate a read and/or delivery receipt within the e-mail to assure delivery. Follow up with a phone call ONLY if the e-mail read/delivery receipt is not verified.

Entering Milepost Numbers Type the lowest number first, then the largest number (i.e. 96.8 to 97.9) Regardless which corridor or direction.

Type ONE (1) milepost number for ramp & plaza closures.

List A is a list of all the milepost numbers for the crossroads for each corridor. List D is a list all of the milepost numbers for the ramps for each corridor.

List of Lanes Closed & Opened List C is a list of wording to use when stating which lanes will be closed and which lanes will be open.

 When you close a right or left lane you are also closing the shoulder. You DO NOT need to list shoulder.

 When closing a shoulder use right shoulder or left shoulder NOT inside shoulder or outside shoulder.

DO NOT USE LANE NUMBERS.

- 34 - 8/28/2018

Appendix

- 35 - 8/28/2018 CROSSROAD, PLAZA & OASIS MILE POSTS TRI-STATE TOLLWAY (I-294/I-80) M.P. CROSSING PLAZA # M-Sect. M.P. CROSSING PLAZA # M-Sect. 0.0 Ford/Calumet Expy (I-94/IL 394) [SOUTH TERMINUS] 1 26.6 Burlington Northern Santa Fe RR (BNSF RR) 2 0.2 Canadian National RR (CN RR) " 27.1 Pedestrian Bridge (Maple Av) " 0.6 Thorn Creek " 27.4 Ogden Avenue (US 34) " 0.8 Southland Lincoln Oasis " 28.2 Salt Creek " 1.2 Chicago Road " 28.5 31st Street " 1.5 Union Pacific RR (UP RR) " 28.9 NB I-294 ramp to WB I-88 (Ramp Mary) " 1.6 Vincennes Rd/Williams Street " 29.1 EB I-88 ramp to SB I-294 (Ramp Nora) " 1.8 Thornton Quarry Bridge " 29.5 Cermak Road (22nd St) " 2.1 CSX RR " 29.9 Cermak Plaza {35} " 2.7 (Rt 1) [Plaza 47]* " 30.5 Roosevelt Road (IL 38) " 3.2 Center Street " 30.9 Roosevelt Road to EB I-290 Bridge " 3.7 Ashland Avenue " 31.1 I-88 Tri-Level Bridge " 3.8 Markham Yard " 31.3 Butterfield Road (IL 56) " 4.0 Wood Street " 31.5 Canadian National RR (CN RR) " 4.2 Dixie Highway " 31.6 I-290 (Eisenhower/Lake St Extension) " 4.9 Western Av/171st " 31.8 SB exit ramp to EB I-290 (Ramp H to I-290) " 5.1 I-80 Plazas {43} (WB) & {45} (EB) " 31.9 Electric Avenue " 5.3 167th Street " 32.4 St. Charles Road " 5.6 163rd Street Plaza {41} " 32.9 Union Pacific RR (UP RR) " 6.3 (US 6) [Plaza 40]* " 33.0 Union Pacific RR (UP RR) " 7.6 I-57 [Plaza 42]* " 33.6 Lake Street (US 20) / North Avenue (IL 64) " 8.2 147th Street (IL 83) [Plaza 42]* " 35.3 Grand Avenue " 8.8 Kedzie Avenue " 35.8 Union Pacific RR (UP RR) " 9.1 Rock Island RR (RI RR) " 9.5 Rexford Avenue " 36.3 Wolf Road 3 10.0 Crawford Avenue " 36.9 Franklin Street " 10.3 Midlothian Turnpike " 36.9-37.5 Bensenville Railroad Yard Bridge " 10.6 135th Street " 37.4 Mannheim Road " 10.9 Cal-Sag Channel " 37.8 O'Hare Oasis " 11.1 131st Street " 38.3 Irving Park Road (IL 19) " 12.0 (IL 50)/127th St " 38.9 Irving Park Plaza {33} (SB only) " 14.6 Ridgeland Avenue/115th St " 39.0 Lawrence Avenue " 15.1 111th Street " 39.2 Canadian Pacific RR (CP RR) " 15.6 107th Street " 39.8 Balmoral Avenue " 15.7 Norfolk Southern RR (NS RR) " 40.2 O'Hare [Plaza 31]* (SB only) " 16.1 Southwest Highway " 40.5 O'Hare Interchange [Plaza 32]* (NB only) " 16.8 Harlem Avenue (IL 43) " 40.7 I-90 Tri-Level Bridge " 17.5 (US 12, 20) [Plaza 38]* " 40.9 I-90 Ramps " 18.7 87th Street " 41.0 Higgins Road (IL 72) " 18.7 Roberts Road " 41.1 Devon Avenue " 19.3 83rd Street Plaza {39} (NB only) " 41.6 Touhy Plaza {29} (NB only) " 19.7 82nd Street Plaza {36} (SB only) " 42.0 River Road (Des Plaines) " 20.0 88th Avenue " 42.1 Touhy Avenue " 20.3 IL 171 (Archer Av) " 42.7 Des Plaines River " 20.8 La Grange Road " 43.2 Oakton Street (IL 62) " 20.9-22.0 Mile-Long Bridge " 43.3 Algonquin Road " 22.0 75th Street/Willow Springs Road (UPS) [Plaza 34]* " 43.5 Union Pacific RR (UP RR) " 22.5 5th Avenue " 43.5 Busse Highway " 22.7 Willow Springs Road " 44.0 Rand Road " 23.1 I-55 (Stevenson Expy) " 44.2 Dempster Street (US 14) " 23.3 Wolf Road " 44.5 Ballard Road " 23.5 Joliet Road " 45.2 Golf Road (IL 58) [Plaza 28]* " 45.9 Union Pacific RR (UP RR) " 23.7 Flagg Creek South 2 46.0 Central Road " 24.1 I-55 Ramps (to NB I-294) [Plaza 37]* " 47.3 Avenue (IL 21) " 24.4 Plainfield Road " 47.5 West Lake Avenue " 25.0 Hinsdale Oasis " 48.9 Willow Road [Plaza 27]* " 25.4 55th Street " 49.8 Sanders Road Underpass " 26.4 47th Street " 51.5 Dundee Road (IL 68) " 26.5 Flagg Creek North " 52.0 Sanders Road Overpass " 52.8 End of I-294 [North Terminus] "

Version 18.1 Effective 03-01-2018 - 36 - * unattended plaza CROSSROAD, PLAZA & OASIS MILE POSTS TRI-STATE TOLLWAY (I-94) AND EDENS SPUR (I-94) M.P. CROSSING PLAZA # M-Sect. M.P. CROSSING PLAZA # M-Sect. 0.0 State Line EDENS SPUR 25.4 I-294 NB Overpass 4 0.5 Russell Road [NORTH TERMINUS] 4 25.5 Lake Cook Road Ramp " 1.2 Old US 41 " 26.4 Edens Spur Plaza {24} " 2.4 IL 173 (Rosecrans Rd) " 26.8 Pfingsten Road " 4.8 Waukegan Plaza {21} " 27.0 West Fork Chicago River " 5.0 Wadsworth Road " 27.3 Metra RR/Canadian Pacific RR " 5.8 Mill Creek " 27.7 Waukegan Road (IL 43) " 7.5 Stearns School Road " 28.6 East Fork Chicago River " 8.4 IL 132 (Grand Av) " 29.3 Union Pacific RR (UP RR) " 9.7 Washington Street " 29.5 Skokie Blvd " 10.1 Milwaukee Avenue (IL 21) " 30.0 Edens Expressway " 10.5 Des Plaines River " 11.2 IL 120 (Belvidere Rd) " 12.0 O'Plaine Road " 13.8 Buckley Road (IL 137) [Plaza 20]* " 15.2 Atkinson Road " 15.7 Metra RR " 16.0 IL 176 (Rockland Rd) " 16.6 Canadian National RR (CN RR) " 17.2 Bradley Road " 18.1 Lake Forest Oasis " 18.9 IL 60 (Town Line Rd) [Plaza 22]* " 20.3 Everett Road " 21.8 Half Day Road (IL 22) [Plaza 23]* " 22.7 Duffy Lane " 24.2 Deerfield Road " 25.2 Lake-Cook Road [Plaza 26]* " 25.3 Edens Spur Ramp "

Version 18.1 Effective 03-01-2018 - 37 - * unattended plaza CROSSROAD, PLAZA & OASIS MILE POSTS JANE ADDAMS MEMORIAL TOLLWAY (I-90) M.P. CROSSING PLAZA # M-Sect. M.P. CROSSING PLAZA # M-Sect. STATE MILEPOSTS 0.00 Illinois/Wisconsin State Line TOLLWAY MILEPOSTS 0.3 IL 75 (Gardner Av) 43.7 Brier Hill Road 6 0.8 Manchester Road 44.4 Hennig Road " 1.0 Turtle Creek Rest Area 45.0 Sandwald Road " 1.4 Dry Run Creek 46.4 IL 47 [Plaza 6]* " 1.7 Prairie Hill Road 47.5 Kishwaukee River " 2.2 Rockton Road 47.8 Powers Road " 49.4 IL Route 72 " 2.7 Rockton Road [West Terminus] 7 50.1 Union Pacific RR (UP RR) " 3.5 South Beloit Plaza {1} " 52.1 Randall Road [Plaza 8]* " 3.7 McCurry Road " 53.2 Sleepy Hollow Road " 4.8 Elevator Road " 53.8 Elgin Plaza {9} " 5.4 Burr Oak Road " 54.6 IL Route 31 [Plaza 11]* " 5.9 Stone Bridge Trail " 6.3 Belvidere Road " 55.7 Fox River 5 7.5 Swanson Road " 55.8 Duncan Avenue " 8.9 IL 173 (West Lane Rd) [Plaza 4]* " 56.1 IL 25 (Dundee Rd) " 10.4 Rock Cut State Park " 56.3 IL 25 Ramp Bridge [Plaza 13]* " 10.8 Harlem Road " 58.1 Beverly Road [Plaza 16B]* " 12.5 E. Riverside Blvd [Plaza 2]* " 59.1 Canadian National RR (CN RR) " 13.4 Spring Creek Road " 59.7 IL 59 [Plaza 14 & 16A]* " 14.4 Rote Road " 60.4 Bartlett Road " 15.2 Business US 20 Ramp " 61.3 Higgins Road " 15.8 Business US 20 (State St) " 62.2 Barrington Road [Plaza 10]* " 16.9 Newburg Road " 63.9 East Branch Poplar Creek " 17.4 Cherry Valley (I-39, US 20) " 65.6 Roselle Road [Plaza 12]* " 17.6 Mill Road " 67.3 Meacham Road [Plaza 12A]* " 18.3 Kishwaukee River " 68.2 I-290/IL 53 overpass " 19.5 Union Pacific RR (UP RR) " 69.3 Salt Creek " 19.8 Bypass US 20 " 69.4 Golf Road (IL 58) " 20.8 Irene Road [Plaza 5A]* " 70.8 Arlington Heights Road [Plaza 18]* " 21.8 Town Hall Road " 72.4 Busse Road " 22.8 Stone Quarry Road " 72.7 IL 83 (Oakton St) " 23.3 Belvidere Plaza {5} (WB only) " 73.5 Elmhurst Road [Plaza 18A]* " 23.8 Pearl Street " 74.0 Higgins Creek " 24.2 Belvidere Oasis " 74.4 Des Plaines Oasis " 24.5 Tripp Road " 74.6 Mt. Prospect Road " 25.0 Genoa Road [Plaza 3]* " 74.8 Union Pacific RR (UP RR) " 26.5 Johnson Road " 75.0 Union Pacific RR (UP RR) " 27.4 Mosquito Creek " 75.3 Wolf Road " 27.9 Spring Center Road " 75.5 Touhy Avenue 28.8 Shattuck Road " 76.1 Higgins Rd (IL 72) 3 30.3 Garden Prairie Road 6 76.7 Mannheim Road (US 12-45) " 31.2 County Line Road " 76.9 Canadian Pacific RR (CP RR) " 33.3 Anthony Road " 77.1 Devon Plaza {17} (WB only) " 34.8 Coon Creek " 77.3 Devon Av/Higgins Rd " 35.3 Harmony-Riley Road " 77.8 I-294 Tri-level Bridge " 36.1 IL 23 " 78.1 Willow Creek " 37.5 Getty Road " 78.3 Des Plaines River Rd " 37.8 Marengo-Hampshire Plaza {7} (EB only) " 78.5 River Road Plaza {19} (EB only) " 40.8 Harmony Road " 78.6 Des Plaines River (E Terminus at MP 78.59 at Kennedy Expy) " 41.9 US 20 Ramps " STATE MILEPOSTS 42.3 US 20 Marengo-Hampshire " 78.6 I-190 WB Overpass

Version 18.1 Effective 03-01-2018 - 38 - * unattended plaza CROSSROAD, PLAZA & OASIS MILE POSTS VETERANS MEMORIAL TOLLWAY (I-355) M.P. CROSSING PLAZA # M-Sect.

0.1 I-80 [SOUTH TERMINUS] 14 0.4 Cedar Road " 0.8 US 6 [Plaza 101]* " 1.8 Spring Creek " 2.6 Bruce Road " 3.3 Spring Creek Plaza {99} " 3.3 Fraction Run Creek " 3.8 167th Street " 4.1 Gougar Road " 4.3 163rd Street " 4.8 159th Street (IL 7) [Plaza 97]* " 5.3 Fiddyment Creek " 5.8 151st Street " 6.8 143rd Street " 7.3 Archer Avenue (IL 171) [Plaza 95]* " 7.8 135th Street " 8.9 127th Street [Plaza 93]* " 9.7 New Avenue " 10.2 Des Plaines River " 10.7 Bluff Road " 11.4 Internationale Parkway " 11.8 Burlington Northern Santa Fe RR (BNSF RR) " 12.3 I-55 " 13.8 Boughton Road [Plaza 90]* " 14.4 Boughton Plaza {89} " 14.5 83rd Street " 15.5 75th Street [Plaza 87]* " 16.1 71st Street " 17.2 63rd Street/Hobson Road [Plaza 85]* " 17.5 Jackson Avenue " 18.3 Maple Avenue [Plaza 83]* " 18.8 Hitchcock Avenue " 19.1 Burlington Northern Santa Fe RR (BNSF RR) " 19.5 Ogden Avenue (IL 34) [Plaza 81]* " 19.8 Warrenville Road " 20.1 I-88 " 20.8 Finley Road Underpass " 21.7 Finley Road Overpass " 21.9 I-88 Ramps (Ramps SE & SW) " 22.6 Butterfield Road (IL 56) [Plaza 79]* " 23.4 22nd Street " 23.5 Foxworth Boulevard " 24.0 Oak Creek Drive " 24.6 Roosevelt Road (IL 38) [Plaza 77]* " 25.1 IL 53 " 26.3 Prairie Path " 26.4 Hill Avenue/Union Pacific RR (UP RR)/Crescent Blvd " 26.8 St. Charles Road " 27.1 Great Western Trail " 27.4 Pleasant Lane " 27.9 North Avenue (IL 64) [Plaza 75]* " 28.9 Fullerton Avenue " 29.2 Army Trail Plaza {73} " 29.8 Army Trail Road [NORTH TERMINUS] "

Version 18.1 Effective 03-01-2018 - 39 - * unattended plaza CROSSROAD, PLAZA & OASIS MILE POSTS REAGAN MEMORIAL TOLLWAY (I-88) M.P. CROSSING PLAZA # M-Sect. M.P. CROSSING PLAZA # M-Sect.

44.2 Rock Falls (US 30) [WEST TERMINUS] 12 105.0 Dauberman Road 11 44.5 Howland Creek " 107.2 Main Street " 45.7 Union Pacific RR (UP RR) " 108.7 Blackberry Creek " 46.3 Nelson Road " 109.3 IL 47 " 47.3 Bollman Road " 111.6 Bliss Road " 48.9 Harmon Road " 113.3 IL 56 Ramp " 50.0 Atkinson Road " 51.4 Hoyle Road " 113.8 IL 56 (Sugar Grove) 8 51.6 Three Mile Creek " 114.2 Deerpath Road " 52.4 Pump Factory Road " 114.4 Orchard Road [Plaza 64]* " 53.8 Canadian National RR (CN RR) " 115.7 Randall Road " 53.9 IL 26 " 116.8 IL 31 Ramp " 54.4 Dixon Ramps " 117.0 IL 31 [Plaza 63]* " 55.1 Chicago Avenue (US 52) " 117.2 Fox River " 56.0 Burkett Road " 117.4 IL 25 " 56.4 Dixon Plaza {69} " 117.8 Aurora Plaza {61} " 56.8 Red Brick Road " 118.3 Mitchell Road " 58.3 Nachusa Road " 118.8 Church Road " 59.8 Robbins Road " 119.2 Farnsworth Avenue [Plaza 59]* " 60.8 Rocky Ford Road " 121.4 Eola Road [Plaza 60]* " 60.8 Rocky Ford Road " 121.9 Union Pacific RR (UP RR) " 63.1 Whitney Road " 122.6 Prairie Path " 64.5 Reynolds Road " 123.3 IL 59 " 67.3 Midway Road " 124.1 Raymond Drive " 68.4 Ashton Road " 124.8 West Branch DuPage River " 70.5 Meridian Road " 125.2 Winfield Road [Plaza 58]* " 71.5 Brooklyn Road " 125.7 Mill Street " 72.6 Thorpe Road " 126.5 Washington Street " 73.1 Beach Creek " 127.4 Freedom Drive [Plaza 57]* " 73.6 Brush Grove Road " 127.6 Naperville Road " 74.2 Rickelson Creek " 129.1 Yackley Road " 76.1 IL 251 " 129.6 East Branch DuPage River " 129.8 Warrenville Road " 76.8 Steward Road (Main St) 11 130.0 IL 53 " 77.3 Burlington Northern Santa Fe RR (BNSF RR) " 131.0 I-355 NB Underpass to WB I-88 ( Ramp NW) " 78.5 I-39/US 51 " 131.3 I-355 " 79.7 Mulford Road " 132.0 Finley Road " 80.7 Locust Road " 132.4 I-355 NB Overpass to EB I-88 (Ramp EN) " 81.7 Woodlawn Road " 133.2 I-355 SB Overpass to EB I-88 (Ramp SE) " 83.6 Tower Road " 133.7 Highland Avenue (Downers Dr) [Plaza 56A WB]* " 84.6 Willrett Road " 134.3 Highland Avenue [Plaza 56B EB]* " 85.6 Shabbona Road " 135.1 Meyers Road Plaza {52} (EB only) " 86.2 DeKalb Plaza {66} " 135.4 Meyers Road " 87.6 University Road " 136.4 Midwest Road (EB only) [Plaza 55]* " 91.4 Annie Glidden Road [Plaza 67]* " 137.1 IL 83 (Kingery Hwy) [Plaza 54]* " 91.6 Kishwaukee River " 137.8 Spring Road (WB only) [Plaza 53]* " 91.7 South First Street " 138.0 Cermak Road " 92.5 IL 23 (4th St) " 138.1 York Road Plaza {51} (WB only) " 92.6 Union Pacific RR (UP RR) " 93.1 Oasis Ramp Bridge " 138.6 EB I-88 ramp to SB I-294 (Ramp Nora) 2 93.3 DeKalb Oasis " 138.5 Salt Creek " 94.0 Peace Road [Plaza 65]* " 138.7 NB I-294 ramp to WB I-88 (Ramp Mary) " 95.8 Somonauk Road " 138.9 York Road (Harger Rd) " 98.5 Hinckley Road " 138.9 Bike Path " 100.0 Keslinger Road " 139.3 Roosevelt Road (IL 38) " 101.0 County Line Road " 140.0 I-294 Tri-Level Bridge " 103.2 Watson Road " 140.4 Eisenhower Expy (I-290) [EAST TERMINUS] "

Version 18.1 Effective 03-01-2018 - 40 - * unattended plaza CROSSROAD, PLAZA & OASIS MILE POSTS ELGIN O'HARE WESTERN ACCESS (IL 390) M.P. CROSSING PLAZA # M-Sect. 5.9 Lake Street (IL 20) 16 6.3 Lake Street Plaza {330} " 6.4 W Branch DuPage River " 6.8 Metra RR " 7.2 Gary Avenue " 7.4 Springinsguth Road " 7.6 Irving Park Road (IL19) " 7.9 Rodenburg Road " 8.3 Wright Boulevard " 8.8 Mitchell Boulevard " 8.9 CN RR " 9.0 Mitchell Boulevard Plaza {328} " 9.4 Roselle Road " 10.5 Plum Grove Road " 10.6 Plum Grove Road Plaza {326} " 11.2 Meacham Road " 12.1 Rohlwing Road (IL 53) " 12.4 I-290 Ramps (to WB and EB IL 390) " 12.5 Eisenhower Expressway (I-290) " 13.1 Park Boulevard " 13.3 Hamilton Lakes Drive Plaza {324} " 13.4 Ketter Drive* [Plaza 325]* " 13.5 Arlington Heights Road " 13.8 Prospect Avenue " 14.2 Salt Creek " 14.4 Mittel Drive {322} " 14.8 Wood Dale Road " 15.3 Lively Boulevard {320} " 15.8 Busse Road (IL 83) " 16.1 CTM Railroad " 16.2 Supreme Drive " 16.9 York Road " 16.9 Western By-Pass "

Version 18.1 Effective 03-01-2018 - 41 - * unattended plaza List B

Type of Work

Accident Clean Up ETC Work Pier Construction Accident Investigation Fence Work Plowable Marker Maint Aerial Cable Work Fiber Optic Work Pothole Repair Animal Control Flood Work Pressure Relief Joint Antenna Work Gantry Work Grinding Asphalt Paving Girder Delivery Protective Shielding Attenuator Work Girder Installation Punch List Work Backfilling Girder Removal Pylon Cap Barrier Wall Installation Guardrail Installation Ramp Construction Barrier Wall Relocate Guardrail Repair Reflector Installation/Repair Barrier Wall Removal Guardrail Replacement Re‐lamping Barrier Wall Repair HAZMAT Clean Up Replace Toll Booth Bearing Work Install Bird Netting Retaining Wall Construction Bridge Beam Erection Intermittent Pavement Roadside Emissions Bridge Beam Removal Repair Roadway Lighting Repairs Bridge Deck Form I‐PASS Conversion Rumble Strip Work Bridge Deck Repair Island Work Sawcutting Bridge Demolition Landscaping Scupper Cleaning Bridge Girder Erection Light Pole Work Setting Girders Bridge Inspection Load and Unloading Dump Sewer Work Bridge Joint Repair Trucks Shoulder Grinding Bridge pier removal Loop Installation Shoulder Reconstruction Bridge Reconstruction Maint. Facility Work Shoulder Removal Bridge Widening Material Delivery Shoulder Widening Bridge Work Material Storage Shoulder Work Cable Guardrail Median Work Sign Installation/Repair Repair/Replacement Message Sign Work Sign Relocation Caisson Drilling Monotube Work Sign Removal Camera Work Mudjacking Sign Replacement Canopy Work Nicor Line Work Sign Structure Foundation Concrete Pour Noise Wall Construction Sign Truss Work/Inspection Conduit Work Oasis Work Slab Jacking Construct Pullout ORT Maintenance Slope Removal Construction Site Clean Up Overhead Sign Work Slope Stabilization Crack Sealing Painting Snow Removal Crossover Work Parapet Removal Soil Borings Culvert Work Pavement and Bridge Survey Crew Delineator Work Widening Sweeping Dig Test Holes Pavement and Shoulder Toll Plaza Maintenance Directional Drilling Replacement Toll Plaza Modifications Ditch Excavation Pavement Coring Traffic Control Ditch Line Cleaning Pavement Grinding Traffic Sensor Drain Repair/Cleaning Pavement Marking Removal Traffic Shift Drainage System Repair Pavement Reconstruction Treadle Work Electrical Installation Pavement Removal Tunnel Tile Cleaning Electrical Removal Pavement Repair Underdrain Installation Electrical Repair Pavement Striping Utility Work Equipment Move Pavement Testing Warranty Work Erosion Control Pavement Widening Window Replacement - 42 - 8/17/2018 List C

List of Lanes to Close

# of Lanes LANES CLOSED LANES OPEN # of Lanes LANES CLOSED LANES OPEN Both shoulders All lanes shifted left Both shoulders All lanes shifted left Both shoulders All lanes shifted right Both shoulders All lanes shifted right Left Lane Right Lane Left Lane 4 Right Lanes Right Lane Left Lane Left Center Lane Left Lane & 3 Right Lanes 2 Both shoulders All Lanes Open Center Lane 2 Left Lane & 2 Right Lanes Left shoulder All Lanes Open Right Lane 4 Left Lanes Right shoulder All Lanes Open Right Center Lane Right Lane & 3 Left Lanes Various Shoulders (Moving) Various Shoulders (Moving) Two Left Lanes 3 Right Lanes 5 Various Lanes (Moving) Various Lanes (Moving) Two Right Lanes 3 Left Lanes Three Left Lanes 2 Right Lanes Three Right Lanes 2 Left Lanes # of Lanes LANES CLOSED LANES OPEN Both shoulders All Lanes Open Both shoulders All lanes shifted left Left shoulder All Lanes Open Both shoulders All lanes shifted right Right shoulder All Lanes Open Center Lane Left & Right Lanes Various Shoulders (Moving) Various Shoulders (Moving) Left Lane Two Right Lanes Various Lanes (Moving) Various Lanes (Moving) Right Lane Two Left Lanes Two Left Lanes Right Lane 3 Two Right Lanes Left Lane # of Lanes LANES CLOSED LANES OPEN Both shoulders All Lanes Open Both shoulders All lanes shifted left Left shoulder All Lanes Open Both shoulders All lanes shifted right Right shoulder All Lanes Open Left Lane 5 Right Lanes Various Shoulders (Moving) Various Shoulders (Moving) 2 Left Lanes 4 Right Lanes Various Lanes (Moving) Various Lanes (Moving) 3 Left Lanes 3 Right Lanes 4 Left Lanes 2 Right Lanes 5 Left Lanes Right Lane # of Lanes LANES CLOSED LANES OPEN Left Center Lane Left Lane & 4 Right Lanes Both shoulders All lanes shifted left Left Right Lane 2 Left Lanes & 3 Right Lanes Both shoulders All lanes shifted right Right Lane 5 Left Lanes Left Lane Three Right Lanes 2 Right Lanes 4 Left Lanes 6 Left Center Lane Left Lane & 2 Right Lanes 3 Right Lanes 3 Left Lanes Right Lane Three Left Lanes 4 Right Lanes 2 Left Lanes Right Center Lane Right Lane & 2 Left Lanes 5 Right Lanes Left Lane Two Left Lanes Two Right Lanes Right Left Lane 3 Left Lanes & 2 Right Lanes Two Center Lanes Left & Right Lanes Right Center Lane 4 Left Lanes & Right Lane 4 Two Right Lanes Two Left Lanes 2 Center Lanes 2 Right Lanes & 2 Left Lanes Three Left Lanes Right Lane Both shoulders All Lanes Open Three Right Lanes Left Lane Left shoulder All Lanes Open Both shoulders All Lanes Open Right shoulder All Lanes Open Left shoulder All Lanes Open Various Shoulders (Moving) Various Shoulders (Moving) Right shoulder All Lanes Open Various Lanes (Moving) Various Lanes (Moving) Various Shoulders (Moving) Various Shoulders (Moving) Various Lanes (Moving) Various Lanes (Moving) Ramp Lanes LANES CLOSED LANES OPEN Ramps Both shoulders All Lanes Open # of Lanes LANES CLOSED LANES OPEN Left shoulder All Lanes Open

When closing plaza lanes you need to state which plaza lanes Right shoulder All Lanes Open Plaza you will be closing and which plaza lanes will be open (i.e. 12, Left Side Ramp Right Side Ramp 13 & 14). Right Side Ramp Left Side Ramp Entrance Ramp Closed Detour Posted Exit Ramp Closed Detour Posted

DO NOT USE NUMBERS (execpt for plaza lanes)

- 43 - 8/17/2018 RAMP DESIGNATION TRI-STATE I-294/I-80 TRI-STATE I-294/I-80 (cont'd)

Exit Exit MP Number RAMP INTERCHANGE MOVEMENT MP Number RAMP INTERCHANGE MOVEMENT 0.0 IDOT-H Calumet Expy (Rt 394) NB Calumet to NB I-294 12.0 12A A Cicero Av/127th St (Rt 50) SB I-294 to SB Cicero Av 0 B " SB I-294 to SB Calumet C " SB Cicero Av to NB I-294 C Bishop Ford (I-94) SB Ford to NB I-294 12C D " NB I-294 to SB Cicero Av 0 J " SB I-294 to WB Ford 12B E " NB I-294 to NB Cicero Av IDOT-K Calumet Expy (Rt 394) NB Calumet to EB I-80/I-94 F " NB Cicero Av to NB I-294 IDOT-G " EB I-80/I-94 to SB Calumet 12B H " SB I-294 to 127th St IDOT Bishop Ford Expy SB Ford to EB I-80/I-94 J " 127th St to SB I-294 IDOT " WB I-80/I-94 to WB Ford 12A K " NB I-294 to 127th St

0.8 A Lincoln Oasis NB I-294 to Lincoln Oasis 17.5 A 95th Street (US 12-20) EB 95th St to NB I-294 B " Lincoln Oasis to NB I-294 B " WB 95th St to NB I-294 C " SB I-294 to Lincoln Oasis 17B C " SB I-294 to WB 95th St D " Lincoln Oasis to SB I-294 17A D " SB I-294 to EB 95th St 17 N " Plaza 38* NB I-294 to 95th St 2.7 2A A Halsted Street (Rt 1) SB I-294 to NB Halsted St S " Plaza 38* 95th St to SB I-294 B " NB Halsted St to NB I-294 C"Plaza 47BC* SB Halsted St to SB I-294 20.3 E Archer Avenue (Rt 171) EB Archer Av to SB I-294 2B D " Plaza 47A* NB I-294 to SB Halsted St C LaGrange Road (US 12-20-45) SB LaGrange to SB I-294 E"Plaza 47BC* NB Halsted St to SB I-294 B Archer Avenue (Rt 171) WB Archer Av to SB I-294 2A F " Plaza 47A* NB I-294 to NB Halsted St 2B G " SB I-294 to SB Halsted St 22.0 22 A 75th St/Willow Springs Rd Plaza 34* SB I-294 to 75th/Willow Springs H " SB Halsted St to NB I-294 B " 75th/Willow Springs to SB I-294 22 C " NB I-294 to 75th/Willow Springs 4.0 A Wood Street Wood St to NB I-294 D " Plaza 34* 75th/Willow Springs to NB I-294

4.2 4 B Dixie Highway SB I-294 to Dixie Hwy 22.5 23A A I-55 (Stevenson Expy) NB I-294 to NB I-55

5.1 A EB I-80 to NB I-294 23.3 E Wolf Road Wolf Rd to SB I-294 5 B " SB I-294 to WB I-80 23B N " NB I-294 to Wolf Rd C"Plaza 45 EB I-80 to EB I-80/SB I-294 23B J I-55 (Stevenson Expy) NB I-294 to SB I-55 5D " Plaza 43 WB I-80/NB I-294 to WB I-80 K " NB I-55 to SB I-294

6.3 A 159th Street (US 6) WB 159th St to SB I-294 23.5 C I-55 (Stevenson Expy) Plaza 37 to SB I-55 6B B " NB I-294 to WB 159th St D I-55/Joliet Road Joliet Rd to Plaza 37 6A C " NB I-294 to EB 159th St IDOT-E " Plaza 37 to EB Joliet Rd D " EB 159th St to SB I-294 IDOT-G I-55 (Stevenson Expy) Plaza 37 to NB I-55 6B E " Plaza 40* SB I-294 to WB 159th St AB " NB I-55 to Plaza 37 F"Plaza 40* WB 159th St to NB I-294 IDOT-F " SB I-55 to Plaza 37 G"Plaza 40* EB 159th St to NB I-294 6A H " Plaza 40* SB I-294 to EB 159th St 23.8 A I-55 Plaza 37 Plaza 37* Plaza 37 to NB I-294 B"Plaza 37* SB I-294 to Plaza 37 7.6 B Plaza 42* NB I-57 to NB I-294 7B M " Plaza 42* SB I-294 to SB I-57 25.0 A Hinsdale Oasis NB I-294 to Hinsdale Oasis A** " NB I-57 to SB I-294 (2024) B " Hinsdale Oasis to NB I-294 C** " SB I-57 to SB I-294 (2024) C " SB I-294 to Hinsdale Oasis D** " Plaza 42** SB I-57 to NB I-294 (2024) D " Hinsdale Oasis to SB I-294 7** H** " NB I-294 to NB I-57 (2024) E " I-55 Ramp A to Oasis 7A** L** " Plaza 42** SB I-294 to NB I-57 (2024)

N Interstate 57 - 147th Street (IL 83) Plaza 42* 147th St to NB I-294 8S " Plaza 42* SB I-294 to 147th St

(continued on next page) *unattended plaza ** Future Work Revision 18.2 09/21/2018 - 44 - To be Replaced RAMP DESIGNATION (cont'd) TRI-STATE I-294/I-80 (cont'd) TRI-STATE I-294/I-80 (cont'd)

Exit Exit MP Number RAMP INTERCHANGE MOVEMENT MP Number RAMP INTERCHANGE MOVEMENT 27.4 A Ogden Avenue (US 34) EB Ogden Av to NB I-294 40.2 I O'Hare Interchange EB I-190 O'Hare to SB I-294 27B B " NB I-294 to WB Ogden Av N " EB I-190 O'Hare to NB I-294/WB I-90 C " WB Ogden Av to SB I-294 J " WB I-190 Kennedy to SB I-294 27A D " SB I-294 to EB Ogden Av E " EB I-90 to Ramp F - Plaza 31 27A E " NB I-294 to EB Ogden Av 40A F Plaza 31 - O'Hare West* SB I-294 to WB I-190-O'Hare F " WB Ogden Av to NB I-294 40.5 40 P Plaza 32 - O'Hare East* NB I-294 to WB I-190-O'Hare 27B G " SB I-294 to WB Ogden Av Q " Plaza 32 to River Rd H " EB Ogden Av to SB I-294 40.9 A I-90 WB (Kennedy Expy) WB I-90 Kennedy to NB I-294 28.9 29 M I-88 (Regan Tollway) NB I-294 to WB I-88 40B B I-90 EB (Kennedy Expy) SB I-294 to EB I-90 Kennedy 29.1 N " EB I-88 to SB I-294 40 L " NB I-294 to EB I-90 Kennedy 40B C I-90 WB (Jane Addams Tollway) SB I-294 to WB I-90 29.5 29 A Cermak Road (22nd St.) SB I-294 to Cermak Rd 40 D " NB I-294 to WB I-90 B " Cermak Rd to NB I-294 G " EB I-90 to SB I-294 H " EB I-90 to NB I-294 30.5 30A A Roosevelt Road (Rt 38) NB I-294 to EB Roosevelt Rd M " EB I-190 to WB I-90 (to Ramp D) 30B B " NB I-294 to WB Roosevelt Rd C " WB Roosevelt Rd to SB I-294 42.1 A Touhy Avenue/River Road SB River Rd to SB I-294 D " EB Roosevelt Rd to SB I-294 42A B " NB I-294 to EB Touhy Av C " NB River Rd to SB I-294 31.1 32 B I-294/I-290 (Eisenhower Expy) NB I-294 to EB I-290 42B D " NB I-294 to WB Touhy Av 32 J " NB I-294 to WB I-290 D " WB I-290 to SB I-294 44.2 A Dempster Street (US 14) SB Rand Rd to SB I-294 L I-88/I-290 (Eisenhower Expy) EB I-88 to WB I-290 44A B " NB I-294 to EB Dempster St (ramp E to ramp J) C " WB Dempster St to SB I-294 E I-88/I-294 EB I-88 to NB I-294 44B D " NB I-294 to WB Dempster St 32 F " SB I-294 to WB I-88 45.2 A Golf Road (Rt 58) Plaza 28* EB Golf Rd to NB I-294 31.8 G I-290 (Eisenhower Expy) EB I-290 to SB I-294 45 B " Plaza 28* SB I-294 to Golf Rd (via N East River Rd) 32 H " SB I-294 to EB I-290 C " Plaza 28* WB Golf Rd to NB I-294 K " WB I-290 to NB I-294 48.9 48 A Willow Road NB I-294 to Willow Rd 33.6 33 F I-290 WB SB I-294 to WB I-290 B " Plaza 27* Willow Rd to NB I-294 (US 20-Lake St & Rt 64-North Av) 48 C " Plaza 27* SB I-294 to Willow Rd J " Lake/North/I-290 to NB I-294 D " Willow Rd to SB I-294

37.8 A O'Hare Oasis NB I-294 to O’Hare Oasis 52.8 Q I-94 NB I-294 to WB I-94 B " O’Hare Oasis to NB I-294 A Lake-Cook Road Lake-Cook Rd to SB I-294 C " SB I-294 to O’Hare Oasis 52 B " NB I-294 to Lake-Cook Rd D " O’Hare Oasis to SB I-294 ~~~~~~~~~~~~~~~~~~~~~~~~~~ 38.3 38B A Irving Park Road (Rt 19) SB I-294 to WB Irving Park Rd B " WB Irving Park Rd to NB I-294 EDENS SPUR I-94 C " EB Irving Park Rd to NB I-294 Exit 38A D " SB I-294 to EB Irving Park Rd MP Number RAMP INTERCHANGE MOVEMENT 27.8 A Spur - Waukegan Road (Rt 43) Waukegan Rd to WB Edens Spur 39.8 A Balmoral Avenue Balmoral Ave to SB I-294 27 B " EB Edens Spur to Waukegan Rd 39 B " Plaza 30* NB I-294 to Balmoral Ave 24.2 24 F WB Edens Spur to Deerfield Rd

(continued on next page)

*unattended plaza ** Future Work Revision 18.2 09/21/2018 - 45 - To be Replaced RAMP DESIGNATION (cont'd) TRI-STATE I-94 TRI-STATE I-94 (cont'd)

Exit Exit MP Number RAMP INTERCHANGE MOVEMENT MP Number RAMP INTERCHANGE MOVEMENT 0.5 1 B Russell Road WB I-94 to Russell Rd 25.2 25A C Edens Spur (I‑94) Plaza 26* EB I-94 to Lake-Cook Rd C " Russell Rd to WB I-94 D " Plaza 26* Lake-Cook Rd to WB I-94 D " EB I-94 to Russell Rd 25.4 25B P " EB I-94 to SB I-294 ~~~~~~~~~~~~~~~~~~~~~~~~~~ 1.4 A Edwards Road Edwards Rd to EB I-94 JANE ADDAMS MEMORIAL I-90 2.4 A Route 173 (Rosecrans Road) Rt 173 to EB I-94 Exit 2 B " WB I-94 to Rt 173 MP Number RAMP INTERCHANGE MOVEMENT 2.7 A Rockton Road Rockton Rd to EB I-90 8.4 F Route 132 (Grand Av) (cont’d) WB Rt 132 to WB I-94 3 B " WB I-90 to Rockton Rd 8A G " EB I-94 to WB Rt 132 IDOT-2 " Rockton Rd to WB I-90 H " EB Rt 132 to EB I-94 3 IDOT-1 " EB I-90 to Rockton Rd

8.4 A Route 132 (Grand Avenue) EB Rt 132 to WB I-94 8.9 8 A IL 173 (West Lane Rd) EB I-90 to Rt 173 8A B " WB I-94 to WB Rt 132 B “ Plaza 4* Rt 173 to EB I-90 C " WB Rt 132 to EB I-94 C “ Rt 173 to WB I-90 8B D " EB I-94 to EB Rt 132 8 D “ Plaza 4* WB I-90 to Rt 173 8B E " WB I-94 to EB Rt 132 12.3 A E. Riverside Blvd Plaza 2* E Riverside Blvd to EB I-90 10.1 10 A Milwaukee Avenue (Rt 21) EB I-94 to Milwaukee Av 12 B " Plaza 2* WB I-90 to E Riverside Blvd B " Milwaukee Av to WB I-94 C " E Riverside Blvd to WB I-90 12 D " EB I-90 to E Riverside Blvd 11.2 11A A Route 120 (Belvidere Road) WB I-94 to EB Rt 120 11B B " WB I-94 to WB Rt 120 15.8 A Bus. US 20 (Rockford) Bus US 20 to EB I-90 C " WB Rt 120 to EB I-94 15 B " EB I-90 to Bus US 20 D " EB Rt 120 to EB I-94 15 C " WB I-90 to Bus US 20 D " Bus US 20 to WB I-90 13.8 A Route 137 (Buckley Road) Buckley Rd to EB I-94 13 B " WB I-94 to Buckley Rd 17.4 17 F US 20/I-39 (Cherry Valley) WB I-90 to US 20 C"Plaza 20* Buckley Rd to WB I-94 G " US 20 to WB I-90 13 D " Plaza 20* EB I-94 to Buckley Rd H " US 20 to EB I-90 17 I " EB I-90 to US 20 16.0 A Route 176 (Rockland Road) Rt 176 to EB I-94 16 B " WB I-94 to Rt 176 20.8 20 A Irene Road WB I-90 to Irene Road D " Irene Road to EB I-90 18.1 A Lake Forest Oasis WB I-94 to Lake Forest Oasis 20 B " Plaza 5A* EB I-90 to Irene Road B " Lake Forest Oasis to WB I-94 C " Plaza 5A* Irene Road to WB I-90 C " EB I-94 to Lake Forest Oasis D " Lake Forest Oasis to EB I-94 24.2 A Belvidere Oasis EB I-90 to Belvidere Oasis B " Belvidere Oasis to EB I-90 18.9 A Route 60 (Town Line Road) Town Line Rd to EB I-94 C " WB I-90 to Belvidere Oasis 19 B " WB I-94 to Town Line Rd D " Belvidere Oasis to WB I-90 C"Plaza 22* Town Line Rd to WB I-94 19 D " Plaza 22* EB I-94 to Town Line Rd 25.0 25 A Genoa Road Plaza 3* EB I-90 to Genoa Rd B " Genoa Rd to EB I-90 21.8 21 A Route 22 (Half Day Road) WB I-94 to Half Day Rd C " Genoa Rd to WB I-90 B"Plaza 23* Half Day Rd to WB I-94 25 D " Plaza 3* WB I-90 to Genoa Rd 21 C " Plaza 23* EB I-94 to Half Day Rd D " Half Day Rd to EB I-94 42.3 42 A US 20 (Marengo-Hampshire) EB I-90 to US 20 B " US 20 to EB I-90 24.2 24 A Deerfield Road WB I-94 to Deerfield Rd 42 C " WB I-90 to US 20 B " Deerfield Rd to EB I-94 D " US 20 to WB I-90

*unattended plaza (continued on next page) ** Future Work Revision 18.2 09/21/2018 - 46 - To be Replaced RAMP DESIGNATION (cont'd) JANE ADDAMS MEMORIAL I-90 (cont'd) JANE ADDAMS MEMORIAL I-90 (cont'd)

Exit Exit MP Number RAMP INTERCHANGE MOVEMENT MP Number RAMP INTERCHANGE MOVEMENT 46.4 46 A IL 47 WB I-90 to NB Rt 47 2013 Plaza 65.5 65 A Roselle Road Plaza 12* WB I-90 to Roselle Rd B"Plaza 6* NB Rt 47 to EB I-90 Plaza B " Plaza 12* Roselle Rd to EB I-90 C " SB Rt. 47 to EB I-90 Ramp C** " Central Rd to WB I-90 (2018) D"Plaza 6* EB I-90 to Rt. 47 Plaza 65 D"Plaza 12* EB I-90 to Roselle Rd E " WB I-90 to SB Rt 47 Ramp F " N&S Rt. 47 to WB I-90 Ramp 67.3 67 A Meacham Road Plaza 12A* WB I-90 to Meacham Rd C " Plaza 12A* Meacham Rd to WB I-90 52.1 52 A Randall Road WB I-90 to Randall Rd B " Randall Rd to EB I-90 68.2 A I-290/Route 53 SB Rt 53 to EB I-90 52 C " Plaza 8* EB I-90 to Randall Rd 68B IDOT-B " Plaza 15* EB I-90 to NB Rt 53 D"Plaza 8* Randall Rd to WB I-90 IDOT-C " NB I-290/Rt 53 to WB I-90 68A D " WB I-90 to SB I-290/Rt 53 54.6 A Route 31 NB Rt 31 to WB I-90 68A E " Plaza 15* EB I-90 to SB I-290/Rt 53 54B B " EB I-90 to NB Rt 31 IDOT-F " NB I-290/Rt 53 to EB I-90 C"Plaza 11* SB Rt 31 to EB I-90 68B IDOT-G " WB I-90 to NB Rt 53 54A D " Plaza 11* WB I-90 to SB Rt 31 H " SB Rt 53 to WB I-90 54B E " Plaza 11* WB I-90 to NB Rt 31 F"Plaza 11* NB Rt 31 to EB I-90 70.7 A Arlington Heights Road SB Arlington Hts Rd to EB I-90 54A G " EB I-90 to SB Rt 31 B " NB Arlington Hts Rd to EB I-90 H " SB Rt 31 to WB I-90 70 C " WB I-90 to Arlington Hts Rd D"Plaza 18* SB Arlington Hts Rd to WB I-90 56.3 A Route 25 Rt 25 to WB I-90 70 E " Plaza 18* EB I-90 to Arlington Hts Rd 56 B " Plaza 13* WB I-90 to Rt 25 F " Plaza 18* NB Arlington Hts Rd to WB I-90 56 C " EB I-90 to Rt 25 D"Plaza 13* Rt 25 to EB I-90 73.5 73** A Elmhurst Road (Rt 83) Plaza 18A* WB I-90 to Elmhurst Rd 73** B " Plaza 18A* EB I-90 to Elmhurst Rd 58.1 58 A Beverly Road Plaza 16B* WB I-90 to Beverly Rd C " Plaza 18A* Elmhurst Rd to WB I-90 B " Beverly Rd to EB I-90 D " Plaza 18A* Elmhurst Rd to EB I-90

59.7 59 A Route 59 Plaza 14* EB I-90 to Rt 59 74.4 D Des Plaines Oasis EB I-90 to Des Plaines Oasis B " SB Rt 59 to WB I-90 E " Des Plaines Oasis to WB I-90 59 C " Plaza 16A* WB I-90 to Rt 59 F " Des Plaines Oasis to EB I-90 D " NB Rt 59 to EB I-90 G " WB I-90 to Des Plaines Oasis E " SB Rt 59 to EB I-90 F " NB Rt 59 to WB I-90 76.1 76 C Lee Street (Rt 72) WB I-90 to Lee St B " Lee St to EB I-90 62.2 62 A Barrington Road Plaza 10* WB I-90 to SB Barrington Rd 62 B " Plaza 10* WB I-90 to NB Barrington Rd 77.3 R Devon Avenue/Higgins Road Devon Av to WB I-90 62 C " Plaza 10* EB I-90 to NB Barr Rd 62 D " Plaza 10* EB I-90 to SB Barr Rd 77.9 77A B I-90 to I-294 I-90 EB to I-294 SB/IL-190 (O'Hare) 62 E " Plaza 10* NB Barrington Rd to WB I-90 77B D " I-90 EB to I-294 NB 62 F " Plaza 10* SB Barrington Rd to WB I-90 77 A " I-90 WB to I-294 NB 62 G " Plaza 10* SB Barrington Rd to EB I-90 62 H " Plaza 10* NB Barrington Rd to EB I-90 78.6 CF Cumberland Av I-90 EB to Cumberland Av

~~~~~~~~~~~~~~~~~~~~~~~~~~ (continued on next page)

*unattended plaza ** Future Work Revision 18.2 09/21/2018 - 47 - To be Replaced RAMP DESIGNATION (cont'd) REAGAN MEMORIAL I-88 REAGAN MEMORIAL I-88 (cont'd)

Exit Exit MP Number RAMP INTERCHANGE MOVEMENT MP Number RAMP INTERCHANGE MOVEMENT 44.2 44 B US 30 (West Terminus) WB I-88 to US 30 119.2 A Farnsworth Av Plaza 59* SB Farnsworth Av to EB I-88 C " US 30 to EB I-88 119A D " Plaza 59* WB I-88 to SB Farnsworth Av 119A E " EB I-88 to Farnsworth Av 54.4 54 A Route 26 (Dixon) EB I-88 to Rt 26 F " Plaza 59* NB Farnsworth Av to EB I-88 C " Rt 26 to WB I-88 119B G " Plaza 59* WB I-88 to NB Farnsworth Av B " Rt 26 to EB I-88 H " Farnsworth Av to WB I-88 54 D " WB I-88 to Rt 26 121.4 121 A Eola Rd Plaza 60* WB I-88 to Eola Rd (via Bilter Rd) 76.1 76 A Route 251 (Rochelle) EB I-88 to Rt 251 B " Plaza 60* Eola Rd to EB I-88 (via Diehl Rd) B " Rt 251 to EB I-88 121 C " EB I-88 to Eola Rd (via Diehl Rd) 76 C " WB I-88 to Rt 251 D " Eola Rd to WB I-88 (via Bilter Rd) D " Rt 251 to WB I-88 123.3 A Route 59 Rt 59 to EB I-88 78.5 IDOT-E I-39/US 51 SB I-39 to EB I-88 123 B " WB I-88 to Rt 59 78B IDOT-C " EB I-88 to NB I-39 C " Rt 59 to WB I-88 IDOT-A " NB I-39 to WB I-88 123 D " EB I-88 to Rt 59 78A IDOT-G " WB I-88 to SB I-39 78A IDOT-F " EB I-88 to SB I-39 125.2 125 A Winfield Road WB I-88 to Winfield Rd IDOT-D " NB I-39 to EB I-88 B " Winfield Rd to EB I-88 78B IDOT-B " WB I-88 to NB I-39 125 C " Plaza 58* EB I-88 to Winfield Rd IDOT-H " SB I-39 to WB I-88 D " Plaza 58* Winfield Rd to WB I-88

91.4 91 A Annie Glidden Rd Annie Glidden Rd to WB I-88 127.4 127 B Naperville Road (via Freedom Dr) Plaza 57* EB I-88 to Naperville Rd B"Plaza 67 WB I-88 to Annie Glidden Rd C " Plaza 57* Naperville Rd to WB I-88 C"Plaza 67 Annie Glidden Rd to EB I-88 127 D " WB I-88 to Naperville Rd 91 D " EB I-88 to Annie Glidden Rd 127.6 A Naperville Road SB Naperville Rd to EB I-88 93.25 E DeKalb Oasis DeKalb Oasis to WB I-88 F " NB Naperville Rd to EB I-88 F " WB I-88 to DeKalb Oasis G " DeKalb Oasis to EB I-88 130.0 A Route 53 SB Rt 53 to EB I-88 H " EB I-88 to DeKalb Oasis 130 B " WB I-88 to Rt 53 D " NB Rt 53 to EB I-88 94.0 94 J Peace Road Plaza 65* WB I-88 to Peace Rd K"Plaza 65* Peace Rd to EB I-88 130.8 131 G-ES I-355 (Veterans Tollway) EB I-88 to SB I-355 L " Peace Rd to WB I-88 131 N-EO Ogden Av (US 34) Plaza 81* EB I-88 to Ogden Av 94 M " EB I-88 to Peace Rd K-OW " Plaza 81* Ogden Av to WB I-88

109.3 A Route 47 Rt 47 to WB I-88 132.4 132 E-EN I-355 (Veterans Tollway) EB I-88 to NB I-355 109 B " EB I-88 to Rt 47 133.2 131A C-WS " WB I-88 to SB I-355 113.3 113 A Route 56, US 30 WB I-88 to SB Rt 56 B " NB Rt 56 to EB I-88 133.4 131B A-WN " WB I-88 to NB I-355

114.4 114 A Orchard Road WB I-88 to Orchard Rd 133.7 D Downers Drive Plaza 56* Downers Dr to WB I-88 B " Orchard Rd to EB I-88 114 C " Plaza 64* EB I-88 to Orchard Rd 134.25 134 A Highland Avenue WB I-88 to Highland Av D"Plaza 64* Orchard Rd to WB I-88 B " Highland Av to EB I-88 134 C " Plaza 56* EB I-88 to Highland Av 117 A Route 31 Plaza 63* Rt 31 to WB I-88 117 B " WB I-88 to Rt 31 136.5 136 R Midwest Road EB I-88 to Midwest Rd 117 C " Plaza 63* EB I-88 to Rt 31 S " Plaza 55* Midwest Rd to EB I-88 D " Rt 31 to EB I-88

(continued on next page) *unattended plaza ** Future Work Revision 18.2 09/21/2018 - 48 - To be Replaced RAMP DESIGNATION (cont'd) REAGAN MEMORIAL I-88 (cont'd) VETERANS MEMORIAL I-355 (cont'd)

Exit Exit MP Number RAMP INTERCHANGE MOVEMENT MP Number RAMP INTERCHANGE MOVEMENT 137.1 A Route 83 Plaza 54* SB Rt 83 to EB I-88 13.8 A Boughton Road Boughton Rd to NB I-355 B"Plaza 54* NB Rt 83 to EB I-88 13 B " Plaza 90* NB I-355 to Boughton Rd 137 C " WB I-88 to SB Rt 83 C " Plaza 90* Boughton Rd to SB I-355 13 D " SB I-355 to Boughton Rd 137.8 A Spring Rd (22nd St) Plaza 53* Cermak/Spring to WB I-88 138 B " WB I-88 to Cermak; NB Rt 83 15.5 15 A 75th Street Plaza 87* SB I-355 to 75th St 15 B " NB I-355 to 75th St 138.9 138 A York Road EB I-88 to York Rd C " 75th St to SB I-355 B Harger Road (York) Harger Rd to WB I-88 D " Plaza 87* 75th St to NB I-355

~~~~~~~~~~~~~~~~~~~~~~~~~~ 17.2 17 A 63rd Street Plaza 85* SB I-355 to 63rd St 17 B " NB I-355 to 63rd St VETERANS MEMORIAL I-355 C " 63rd St to SB I-355 D"Plaza 85* 63rd St to NB I-355 Exit MP Number RAMP INTERCHANGE MOVEMENT 0.0 0A IDOT - A-EN Interstate 80 EB I-80 to NB I-355 18.3 18 A Maple Avenue Plaza 83* SB I-355 to Maple Av 0B IDOT - B-WN " WB I-80 to NB I-355 18 B " NB I-355 to Maple Av C-SW " SB I-355 to WB I-80 C " Maple Av to SB I-355 D-SE " SB I-355 to EB I-80 D " Plaza 83* Maple Av to NB I-355

0.8 1 A US Route 6 SB I-355 to US 6 19.5 20B I-NO Ogden Avenue (US 34) NB I-355 to Ogden Av 1B " Plaza 101 NB I-355 to US 6 J-OS " Ogden Av to SB I-355 C"Plaza 101 US 6 to SB I-355 19 L-SO " SB I-355 to Ogden Av D " US 6 to NB I-355 M-ON " Ogden Av to NB I-355

4.8 4 A 159th Street (IL 7) Plaza 97 SB I-355 to 159th St 20.1 20A F-NE I-88 (Reagan Tollway) NB I-355 to EB I-88 4 B " NB I-355 to 159th St C-CA " ISTHA CA to EB I-88 C " 159th St to SB I-355 20A H-NW " NB I-355 to WB I-88 D"Plaza 97 159th St to NB I-355 21.5 20 B-SE I-88 (Reagan Tollway) SB I-355 to EB I-88 6.8 B 143rd Street 143rd St to SB I-355 20 D-SW " SB I-355 to WB I-88 7 C " NB I-355 to 143rd St 22.6 22 A Route 56 (Butterfield Road) SB I-355 to Butterfield Rd 7.3 7 A Archer Avenue Plaza 95 SB I-355 to Archer Av 22 B " Plaza 79* NB I-355 to Butterfield Rd D"Plaza 95 Archer Av to NB I-355 C " Plaza 79* Butterfield Rd to SB I-355 D " Butterfield Rd to NB I-355

8.9 A 127th Street 127th St to SB I-355 24.6 24 A Route 38 (Roosevelt Road) SB I-355 to Roosevelt Rd 8B " Plaza 93 SB I-355 to 127th St 24 B " Plaza 77* NB I-355 to Roosevelt Rd C"Plaza 93 127th St to NB I-355 C " Plaza 77* Roosevelt Rd to SB I-355 8 D " NB I-355 to 127th St D " Roosevelt Rd to NB I-355

12.3 IDOT - C-IN NB I-55 to NB I-355 27.9 27 A Route 64 (North Avenue) SB I-355 to North Av IDOT - E-IS " NB I-55 to SB I-355 27 B " Plaza 75* NB I-355 to North Av IDOT - F-OS " SB I-55 to SB I-355 C " Plaza 75* North Av to SB I-355 IDOT - A-ON " SB I-55 to NB I-355 D " North Av to NB I-355 12A B-SO " SB I-355 to SB I-55 12B D-SI " SB I-355 to NB I-55 29.8 29 IDOT-A Army Trail Road SB I-355 to Army Trail Rd 12A G-NI " NB I-355 to NB I-55 29 B " NB I-355 to Army Trail Rd 12B H-NO " NB I-355 to SB I-55 C " EB Army Trail Rd to SB I-355 IDOT-D " WB Army Trail Rd to NB I-355 N " EB Army Trail Rd to NB I-355 IDOT-S " WB Army Trail Rd to SB I-355

*unattended plaza (continued on next page) ** Future Work Revision 18.2 09/21/2018 - 49 - To be Replaced RAMP DESIGNATION (cont'd) IL 390 WESTERN ACCESS (IL 390) IL 390 WESTERN ACCESS (IL 390) (cont'd)

Exit Exit MP Number RAMP INTERCHANGE MOVEMENT MP Number RAMP INTERCHANGE MOVEMENT 6.0 6 A Lake St (US 20) WB IL 390 to Lake St 13 A Prospect Ave** WB IL 390 to Prospect Ave B " EB Lake St to EB IL 390 13.6 13 B " EB IL 390 to Prospect Ave D " WB Lake St to EB IL 390 13 C " Prospect Ave to EB IL 390 13 D " Prospect Ave to WB IL 390 7.1 7A A Gary Ave WB IL 390 to SB Gary Ave D " NB Gary Ave to EB IL 390 14.8 14 A Wood Dale Rd** WB IL 390 to Wood Dale Rd EB IL 390 to Irving Park Rd and 7.4 B Springinsguth Rd 7 Springinsguth Rd 14 B " EB IL 390 to Wood Dale Rd C Springinsguth Rd Springinsguth Rd to WB IL 390 14 C " Wood Dale Rd to WB IL 390 14 D " Wood Dale Rd to EB IL 390 7.6 7B A IL 19 (Irving Park Road) WB IL 390 to Irving Park Rd D " Irving Park Rd to EB IL 390 15.8 15 B Busse Rd (IL 83) EB IL 390 to Busse Rd 8.3 8 A Wright Blvd WB IL 390 to Wright Blvd 15 C " Busse Rd to WB IL 390 D " Wright Blvd to EB IL 390 D " Busse Rd to EB IL 390 (2019)

9.4 9 A Roselle Rd WB IL 390 to Roselle Rd 9 B " EB IL 390 to Roselle Rd 16.9 A I-490** SB I-490 to WB IL 390 (2020) C " Roselle Rd to WB IL 390 F " SB I-490 to Supreme Dr (2020) D " Roselle Rd to EB IL 390 D " NB I-490 to WB IL 390 (2020) C " NB I-490 to Supreme Dr (2020) 11.2 11 A Meacham Rd WB IL 390 to Meacham Rd 16A B " EB IL 390 to NB I-490 (2020) EB IL 390 to Meacham Rd & 11 B " Rohlwing Rd (IL 53) 16B E " EB IL 390 to SB I-490 (2020) C " Meacham Rd to WB IL 390 D " Meacham Rd to EB I-290

12.1 12A A IL 53 (Rohlwing Road) WB IL 390 to Rohlwing Rd D " Rohlwing Rd to EB IL 390

12.5 C I-290 (Eisenhower Expressway) WB IL 390 to EB I-290 12B D " EB IL 390 to WB I-290 12 E " WB IL 390 to WB I-290 12C F " EB IL 390 to EB I-290 12 IDOT " EB I-290 to EB IL 390 IDOT EB I-290 to WB IL 390 IDOT " EB I-290 to Park Blvd. IDOT " WB I-290 to EB IL 390 IDOT " WB I-290 to WB IL 390 IDOT " WB I-290 to Park Blvd. "

Arlington Heights Rd to WB Ketter 13.3 C Arlington Heights Road Plaza 325* Dr, to WB Ramp C, to WB I390

*unattended plaza ** Future Work Revision 18.2 09/21/2018 - 50 - To be Replaced List F

Emergency Lane Closure Request/or After Hour Lane Closure Changes

REGULAR BUSINESS HOURS Monday – Friday 7 AM to 3 PM

Notification to Tollway CM/PM/PCL is CCC Notified of Lane Closures Change Traffic Technician TOC Incident Manager

Tollway Acknowledges/Approves

Lane Closure Document Change sent to DMS Signing Plan Amended/Submit by media by TOC Altered by TOC Lane Closures

AFTER HOURS + Weekends, Holidays, or 3 PM to 7 AM Monday/Friday

CM Requests approval of lane closure request through PM

PM Approves/Submits Request to Incident •Notify Maintenance Section Manager CCC Notifies Manager •Notify Maintenance Manager E903 Lane Closures TOC/Dispatch Approves •Notify ISP Operations Desk Traffic Technician TOC Incident Manager

DMS Plan Altered Accordingly

- 51-