Engineering Design Evolution of the JT-60SA Project
P. Barabaschi, Y. Kamada, S. Ishida for the JT-60SA Integrated Project Team
EU: F4E-CEA-ENEA-CNR/RFX-KIT-CRPP-CIEMAT-SCKCEN
JA: JAEA
1
JT-60SA Objectives
•A combined project of the ITER Satellite Tokamak Program of JA-EU
(Broader Approach) and National Centralized Tokamak Program in Japan.
•Contribute to the early realization of fusion energy by its exploitation to support the exploitation of ITER and research towards DEMO.
ITER
DEMO
Complement ITER towards DEMO
Support ITER
JT-60SA
2
The New Load Assembly
••
JT60-U: Copper Coils (1600 T), Ip=4MA, Vp=80m3 JT60-SA: SC Coils (400 T), Ip=5.5MA, Vp=135m3
JT-60U JT-60SA
JT-60SA(A≥2.5,Ip=5.5 MA)
ITER (A=3.1,15 MA)
3.0m
6.2m
~4m
~2.5m
1.8m
KSTAR (A=3.6, 2 MA)
1.7m
EAST (A=4.25,1 MA)
1.1m
3
SST-1 (A=5.5, 0.22 MA)
3
High Beta and Long Pulse
• JT-60SA is a fully superconducting tokamak capable of confining break-
max
even equivalent class high-temperature deuterium plasmas (Ip =5.5 MA) lasting for a duration (typically 100s) longer than the timescales characterizing the key plasma processes, such as current diffusion and particle recycling.
• JT-60SA should pursue full non-inductive steady-state operations with high βN (> no-wall ideal MHD stability limits).
4
4
Plasma Shaping
• JT-60SA will explore the plasma configuration optimization for ITER and DEMO with a wide range of the plasma shape including the shape of ITER, with the capability to produce both single and double null configurations.
5
5
- Ip=5.5MA, Lower Single Null
- Ip=5.5MA, Double Null
- Ip=4.6 MA ITER like
Phased Research Plan
• Exploitation within the BA period will aim at the initial research phase:
- HH operation for plasma full commissioning - DD operation for identification of the issues in preparation for full DD operation
• Principles of “Joint Exploitation” later phases agreed between EU and JA • Detailed “Research Plan” jointly prepared
Annual Neutron
Limit
Expected Duration
Remote Handling
Max Power
- Phase
- Divertor
- P-NB N-NB ECRF
1.5MW
Power x Time
1-2 y 2-3y 2-3y >2y
- -
- 10MW
x100s
23MW 33MW
phase I phase II phase I phase II
HDDDD
Initial
Research Phase
LSN partial monoblock
+
1.5MW x5s
NB: 20MW x 100s
30MW x 60s duty = 1/30
4E19 4E20 1E21
R&D
Perp.
13MW
10MW
Tang. 7MW
Integrated Research Phase
LSN full-
ECRF: 100s
37MW
41MW monoblock
7MW
Use
Extended
Research
Phase
- >5y
- 1.5E21
- DN
- 24MW
- 41MW x 100s
6
Baseline Schedule
-Start of Tokamak Assembly:
Early 2012
-Completion of Tokamak Assembly: October 2015
-First Plasma: Mid 2016.
7
Device re-baselining
• In late 2007, cost concerns prompted the Parties to request a re-design of the device.
• Several ways to reduce costs were found in “old” design:
• Issues found:
ꢀ
Maximum field in TF conductor rather large for cost effective [email protected] design (Operation point : 6.5T at 5K, with 1K temperature margin). Conductor hot spot temp was unnecessarily low Structures rather heavy and complex to fabricate – multiple coil types Nuclear heating too conservatively estimated
ꢀꢀꢀꢀ
…
• Solution:
ꢀꢀꢀ
Reduce TF field, decrease SC strands volume (segregation), decrease Cu section Optimise structural design Recover plasma performance lost by field reduction by plasma volume increase made possible by reduction of magnet size Rationalise requirements and ports
ꢀ
• In parallel some other problems were addressed:
ꢀꢀꢀ
Seismic Loads to be managed by supports Peak TF Ripple in Plasma to be reduced to 0.5% Inductive flux for plasma operation to be increased to reach 100s flattop
8
Design at >6T costly for NbTi (when Tcs~6K)
T=6K
T=5K
9
Aspect Ratio Optimised
•
R/a is the real only free parameter in the design of a Tokamak for a given
nTτ
••
Trade-off between volume and power density R/a determines important engineering factors
ꢀꢀꢀꢀꢀ
Access to In-Vessel Components Wall power density Field and technology of magnets Mechanical loads Controllability of plasma shape
•
Optimum A is largely a function of technology, machine size, and scaling laws
- The Toroidal Field, and the density
- increase with Aspect Ratio
- decrease with Aspect Ratio
- The Plasma volume the Plasma Current, and
τ
E
10
Main Results of re-Design on TF Magnet
2007 Design
NEW
IDR
CDR 2007
2008
TF Total TF Energy [GJ] TF coils #
1.51
1.06
18
TF Tension [MN]
Number of turns in 1 coil
Peak Field [T]
6.80
90
4.70
72
6.43 30.0
5.65
- 24.4
- Total length of conductor [km]
Total Structure Mass [ton]
Strand type
~650
~280
NbTi
Conductor current [kA] Cable space dimensions [mm] N SC Strands
25.3
25.7
18x22
324
25.1x25.1
720
-
- N Cu Strands
- 162
Tmarg (after burn) [K]
~1.1
~1.4
SC Strand mass in windings of 18
New Design
- 92
- 34
coils [ton]
Segregated copper mass in 18 coils [ton]
-
14
11
Main Results of re-Design
Additional Design Changes: •Cryoplant: heat load re-assessed based on new operation scenarios with reduced neutron yield and reduction of magnet cold structure. From 16kW to ~10kW and much improved dynamics •Cryostat: Single Wall with simplified geometry •Vacuum Vessel: Better distribute VV ports to provide a simpler out of plane support to the TF magnet structure. Reduction of shells
•PF system:
•Balance the distribution of turns in the EF system, •6 Coils (Vs 7), •Broader betap-li range, •28% less conductor •4 Independent CS coils (Vs 3)
•TF Ripple Lowered: with Ferritic Insert will be <0.5%
•Inductive Flux Increased: to ensure 100s flattop
12
Machine Parameters
• After successful completion of the re-baselining in late 2008, the JT-60SA project was launched with the new design with the following parameters.
Cryostat
Basic machine parameters
P-NBI
P-NBI
Plasma Current Toroidal Field, Bt Major Radius, Rp Minor Radius, a Elongation, κX Triangularity, δX Aspect Ratio, A
Shape Parameter, S Safety Factor, q95 Flattop Duration
Heating & CD Power
N-NBI
5.5 MA 2.25 T
2.96
ECH
1.18 1.95 0.53
N-NBI
2.5 6.7 ~3
100 s
41 MW 10 MW 24 MW
7 MW
15 MW/m2
P-NBI ECRF
Divertor wall load
13
13
Heating and CD Systems
Variety of heating/current-drive/ momentum-input combinations
NB: 34MWx100s
Positive-ion-source NB 85keV 12units x 2MW=24MW
COx2u, 4MW CTRx2u, 4MW
Perpx8u, 16MW
Negative-ion-source NB 500keV, 10MW for off-axis NBCD
ECRF: 110GHz, 7MW x 100s
9 Gyrotrons, 4 Launchers with movable mirror
14
14
Magnet
•
All SC Magnet
ꢀ
Nb3Sn for CS
ꢀ
NbTi for TF, EF
•••
18 TF Coils 6 EF Coils 4 CS independent modules
15
Conductors
Coil
Type of strands
TF
NbTi
CS
Nb3Sn 20 ~9
Operating current (kA) Nominal peak field (T) Operating temperature (K) Number of SC strands/Cu strands Local void fraction (%) Cable dimensions (mm) Central hole (id x od) (mm) Conductor ext. dimensions (mm)
25.7 5.65 <5K 324 / 162 32
<5.1K 216 / 108 34
TFC conductor
18.0 x 22.0 -22.0 x 26.0
Φ21.0 7 x 9 27.9 x 27.9
Conductor type
No. of coils Type of strand
EF-H
EF3, 4
NbTi
20.0 6.2
EF-L
EF1, 2, 5, 6
←
CS conductor
Operating current (kA) Nominal peak field (T) Operating temperature (K) Number of SC/Cu strands Local void fraction (%) Cable dimensions (mm) Central hole (id x od) (mm) Conductor ex. dimensions (mm)
←
4.8
- 4.8
- 5.0
450 / 0 34
216 / 108 34
21.8 7 x 9 27.7
19.1
←
EF-L&H conductor
16
25.0
16
TF Magnet features
TF winding pack
Connections area
• Cable in Conduit Conductor , 72 turns, 25.7kA each
OIS
• 6 double pancakes, 6 turns/pancake. Helium inlets in high field side – joints in external low field side
EF1 hanging support arm
• Windings enclosed in Steel Casings • Steel casings supported to ground vertically and toroidally - connected in inboard curved regions by “Inner Intercoil Structure”
• Steel casings guided toroidally by “Outer Intercoil
Structure” to support out of plane loads.
EF support pedestals
Gravity support
Reinforcement ribs
17
View of Magnet - assembly
18
TFC Cold Tests
•••
All TFC will be cold tested at full current before shipping to Japan Test Facility will be in CEA-Saclay PA prepared with test facility specifications and cold testing specifications
ꢀ HV Tests ꢀ Leak Tests ꢀ Flow, Pressure Drop ꢀ Dimensional Stability during and after cooldown ꢀ Resistance, Joints ꢀ Tmargin, Quench tests (2 coils)
••
Cryostat and jigs being fabricated. Cryostat to be delivered in Saclay in first half 2011
19
Power Supplies
•
Largely a full new set of Power Supplies compatible with long pulse operation have been designed and will be procured. These will include:
•
TFC, grouped in 3 units of 6 coils
ꢀ 6 pulse unidirectional, 26kA, 80V ꢀ 3 Fast Discharge QPC Units (1.5KV to ground)
•
PFC, each coil with:
ꢀ 12 pulse, 20kA, ~1KV ꢀ Booster (old units) or new Switching Network Unit ꢀ Fast Discharge QPC Unit
•
In-vessel Coils
••
QPC Units: Under final tendering phase SCM-PS:
ꢀ Technical Specs completed, ꢀ Procurement Arrangement in final stage
20