NYC Department of Environmental Protection Bureau of Engineering Design and Cost Estimating Manual

Issued June 2008

Table of Contents

Cost Estimating Manual - Issued June 2008 Table of Contents

Chapter 1 – Introduction Introduction...... 1-1 Estimating Framework...... 1-2 Manual Organization...... 1-4 Compliance with Cost Estimating Manual...... 1-4

Chapter 2 – Inputs to Estimating Process Introduction...... 2-1 Estimate Preparation Services...... 2-1 Estimate Work Breakdown Structure (WBS)...... 2-2 Project Scope...... 2-7 Project Risks...... 2-10 Project Schedule...... 2-11 Pre-Estimate Meeting...... 2-11

Chapter 3 – Estimate Preparation Estimating System Requirements...... 3-1 Estimating Methodology...... 3-2 Estimate Structure and Definitions...... 3-4 Estimating System Rates and Supporting Calculations...... 3-10 Estimate Inputs...... 3-12 Escalation of Construction Cost Inputs...... 3-13 Estimate Sections...... 3-14

Chapter 4 – Estimate Output Basic Estimate Reports...... 4-1 Basis of Estimate Report...... 4-3

Chapter 5 – Contingency Introduction...... 5-1 Contingency Definitions...... 5-2 Key Source of Risk and Variability...... 5-3 Methods for Setting Contingency...... 5-8

Chapter 6 – Estimate Review and Approval Introduction...... 6-1 Cost Estimating Team Review...... 6-1 Project Management and Design Team Review...... 6-3 Design Consultant Senior Management Endorsement...... 6-5

i Cost Estimating Manual June 2008

Cost Estimating Manual - Issued June 2008 Table of Contents

List of Attachments Attachment 1-1 AACE 18R-97

Attachment 2-1 BEDC Work Packages by CSI Division

Attachment 2-2 Design Content by Estimate Class

Attachment 3-1 Sample Wage Rate Calculation

Attachment 3-2 Sample Work Week Differential Calculations

Attachment 3-3 Estimator Inputs 3-3A Equipment 3-3B Earthwork 3-3C Structural Concrete 3-3D Electrical 3-3E Process Piping 3-3F Indirect Project Cost

Attachment 3-4 Indirect Project Costs Checklist

Attachment 4-1 Estimating Reports 4-1A WBS Level 1 Summary Report 4-1B WBS Level 2 Summary Report 4-1C Scope Review Report Summarized to Assembly 4-1D Scope Review Report Detailed 4-1E Labor Productivity Detail Report (Assembly) 4-1F Labor Productivity Detail Report (Item)

Attachment 4-2 AACE 34R-05

Attachment 5-1 Guidance on Contingency Levels for Primary Construction Inputs

ii Introduction Chapter 1

Chapter 1 Introduction

Chapter 1 Introduction

Chapter 1 – Introduction

Introduction

Accurate cost estimating is essential for the effective management of the New York City, Department of Environmental Protection’s Capital Program. To ensure consistency across all projects and to facilitate review and approval of all cost estimates prepared for the Capital Program, the Bureau of Engineering Design and Construction (BEDC) has developed this Cost Estimating Manual. Key objectives of Manual include the following:

• Standardization in engineering inputs (scope) at all estimating milestones to drive consistency in the expected accuracy range of cost estimates • Standardization of estimating format to facilitate development, review, and historical data capture • Guidance on development of appropriate contingency levels to facilitate better transparency and decision-making in Capital Program budgeting • Standardization in the submittal of estimate supporting documentation including sources of information and assumptions used to develop the estimate • Minimum quality requirements for estimate review prior to submittal to BEDC

The Manual identifies requirements of the entire estimating process covering the following eight major steps in cost estimating:

E i g h t M a j o r 1 Communicate Project Scope to Estimating Team S t e p s i n C o s t (Scope Input from Engineer to Estimator) Estimating 2 Plan the Estimate Preparation (Work Breakdown Structure and Estimate Structure) 3 Develop Estimate

4 Risk Analysis and Contingency Development

5 Output Estimate

6 Document Basis of Estimate

7 Quality Review (Estimating Team and Engineering Team) 8 Submit Estimate to BEDC

1-1 Cost Estimating Manual June 2008

Estimating Framework

The estimating framework described in this Manual is largely based on the Association for the Advance- ment of Cost Engineering (AACE) Recommended Practice No. 18R-97: Cost Estimate Classification Sys- tem – As Applied in Engineering, Procurement and Construction for the Process Industries. This AACE Recommended Practice has been adapted and expanded to the specific needs and characteristics of the BEDC Capital Program. A copy of this Practice can be obtained from the AACE website at www.aacei.org/ technical/rp.shtml and is included as Attachment 1-1 to this Manual.

AACE Practice 18R-97 utilizes a five level Class System (5, 4, 3, 2, and 1) which corresponds to estimate types prepared at various stages of project development. Type 5 cost estimates are developed a project conception when little project information or scope has been developed. Type 1 estimates are complete detailed unit cost and take off estimates with complete or near complete scope definition. For planning and budgeting purposes, BEDC requires development of project cost estimates at the various milestones within the project life cycle. The correlation between the estimates produced at each of the key BEDC project life cycle milestones and AACE estimate classes is shown in Figure 1.1. For each delivery milestone, the generally accepted estimating methods, expected level of accuracy, level of scope definition, and the key scope content requirements necessary to develop the estimate are identified.

1-2 Chapter 1 Introduction

90/100% Milestone

95 to 100% Complete Annotated Drawings Complete Specifications Class 1* Detailed Unit Cost with Detailed Take-off -10% to +15% P E D C n y Design: 60% Milestone 40 to 70% Preliminary to Advanced Drawings Major Specifications Class 2 Detailed Unit Cost Detailed with Forced Take-off -15% to +20% d t o e

p p l i A

30% s Milestone 10 to 40% Final Equipment Lists Site Layout (Earthwork) Plans Building/Facility Major Sections Concrete Quantities Final P&IDs Electrical Single Lines Class 3 Semi-Detailed Unit Costs with Assembly Level Line Items -20% to +30%

a t i o n c i f i ss Facility Planning Facility Design Criteria General Site Layout Pipeline Corridors Prelim. Equipment Lists Prelim. Electrical Loads Class 4 Equipment Factored Equipment Factored or Parametric -30% to +50% 1 to 15% Process Flow Diagram C l a e a t m t i s Initiation t E Class 5 Parametric or Parametric Capacity Factored -50% to +100% 0 to 2% Hydraulic Capacity s s c C o

f r i s t i

e t c h a r a a r y o C e mm Life Cycle Phase s t i m a t Per AACE 18R-97, Class 1 estimates are generally prepared only for discrete parts or sections of the total project when preparing owner’s estimates, AACE 18R-97, Class 1 estimates are generally prepared only for discrete parts or sections of the total project when preparing owner’s Per E AACE Estimate Class Estimate Methodology Expected Level of Accuracy Expected Level Key Content Requirements Key (Scope Content Examples) * might be prepared to Class 1 standards, the while sections of an estimate used by DEP Accordingly, or prepared by subcontractors for bidding purposes. overall estimate is only considered a Class 2 estimate. Figur e 1-1 S u P roj ec t s o f Engin ee ring Des ign and Con s tru c tion Capital Bur e au

1-3 Cost Estimating Manual June 2008

Manual Organization

This Manual describes standardized procedures used in the development of Capital Project cost estimates in support of delivery of BEDC’s Capital Program. The Manual is organized into the following Chapters and associated main subject areas: Chapter 2 – Inputs to the Estimating Process • Estimate Preparation Services • Establish Work Breakdown Structure (WBS) • Project Scope • Project Risks • Project Schedule • Pre-Estimate Preparation Meeting Chapter 3 – Estimate Preparation • Estimating System Requirements (Software) • Estimating Methodology • Estimate Structure and Definitions • Estimating System Rates and Supporting Calculations • Estimate Inputs • Escalation of Construction Inputs • Estimate Sections Chapter 4 – Estimate Output • Basic Estimate Reports • Basis of Estimate Report Chapter 5 – Contingency • Contingency Definitions • Key Sources of Risk and Variability • Methods for Analyzing Risk and Setting Contingency Chapter 6 – Estimate Review and Approval • Cost Estimating Team Review • Project Team Review • Consultant Senior Management Review And Endorsement

Compliance with Cost Estimating Manual

All cost estimates prepared for BEDC during facility planning and design efforts shall adhere to the require- ments of this Manual. Exception to compliance with this Manual must be received in writing from the Con- sultant and submitted to the BEDC Project Manager at the initiation of design. Waivers will be reviewed on a case by case basis weighing project size, complexity, and reasons for variance request.

1-4 Chapter 1 Attachments

Attachment 1-1 AACE 18R-97

Attachment 1-1 AACE 18R-97

AACE International Recommended Practice No. 18R-97

COST ESTIMATE CLASSIFICATION SYSTEM – AS APPLIED IN ENGINEERING, PROCUREMENT, AND CONSTRUCTION FOR THE PROCESS INDUSTRIES

Copyright 2000 AACE, Inc. AACE International Recommended Practices and Standards

1 Attachment 1-1 AACE 18R-97

Recommended Practice No. 18R-97 Cost Estimate Classification System – As Applied in Engineering, Procurement, and Construction for the Process Industries

June 15, 1998

PURPOSE

As a recommended practice of AACE International, the Cost Estimate Classification System provides guidelines for applying the general principles of estimate classification to project cost estimates (i.e., cost estimates that are used to evaluate, approve, and/or fund projects). The Cost Estimate Classification System maps the phases and stages of project cost estimating together with a generic maturity and quality matrix, which can be applied across a wide variety of industries. This addendum to the generic recommended practice provides guidelines for applying the principles of estimate classification specifically to project estimates for engineering, procurement, and construction (EPC) work for the process industries. This addendum supplements the generic recommended practice (17R-97) by providing:

• a section that further defines classification concepts as they apply to the process industries; • charts that compare existing estimate classification practices in the process industry; and • a chart that maps the extent and maturity of estimate input information (project definition deliverables) against the class of estimate.

As with the generic standard, an intent of this addendum is to improve communications among all of the stakeholders involved with preparing, evaluating, and using project cost estimates specifically for the process industries. It is understood that each enterprise may have its own project and estimating processes and terminology, and may classify estimates in particular ways. This guideline provides a generic and generally acceptable classification system for process industries that can be used as a basis to compare against. It is hoped that this addendum will allow each user to better assess, define, and communicate their own processes and standards in the light of generally-accepted cost engineering practice.

INTRODUCTION

For the purposes of this addendum, the term process industries is assumed to include firms involved with the manufacturing and production of chemicals, petrochemicals, and hydrocarbon processing. The common thread among these industries (for the purpose of estimate classification) is their reliance on process flow diagrams (PFDs) and piping and instrument diagrams (P&IDs) as primary scope defining documents. These documents are key deliverables in determining the level of project definition, and thus the extent and maturity of estimate input information. Estimates for process facilities center on mechanical and chemical process equipment, and they have significant amounts of piping, instrumentation, and process controls involved. As such, this addendum may apply to portions of other industries, such as pharmaceutical, utility, metallurgical, converting, and similar industries. Specific addendums addressing these industries may be developed over time. This addendum specifically does not address cost estimate classification in nonprocess industries such as commercial building construction, environmental remediation, transportation infrastructure, “dry” processes such as assembly and manufacturing, “soft asset” production such as software development, and similar industries. It also does not specifically address estimates for the exploration, production, or transportation of mining or hydrocarbon materials, although it may apply to some of the intermediate processing steps in these systems. The cost estimates covered by this addendum are for engineering, procurement, and construction (EPC) work only. It does not cover estimates for the products manufactured by the process facilities, or for research and development work in support of the process industries. This guideline does not cover the significant building construction that may be a part of process plants. Building construction will be covered in a separate addendum.

Copyright 2000 AACE, Inc. AACE International Recommended Practices and Standards

2 Attachment 1-1 AACE 18R-97

Cost Estimate Classification System – As Applied in Engineering 2 of 8 Procurement, and Construction for the Process Industries

June 15, 1998 This guideline reflects generally-accepted cost engineering practices. This addendum was based upon the practices of a wide range of companies in the process industries from around the world, as well as published references and standards. Company and public standards were solicited and reviewed by the AACE International Cost Estimating Committee. The practices were found to have significant commonalities that are conveyed in this addendum.

COST ESTIMATE CLASSIFICATION MATRIX FOR THE PROCESS INDUSTRIES

The five estimate classes are presented in figure 1 in relationship to the identified characteristics. Only the level of project definition determines the estimate class. The other four characteristics are secondary characteristics that are generally correlated with the level of project definition, as discussed in the generic standard. The characteristics are typical for the process industries but may vary from application to application. This matrix and guideline provide an estimate classification system that is specific to the process industries. Refer to the generic standard for a general matrix that is nonindustry specific, or to other addendums for guidelines that will provide more detailed information for application in other specific industries. These will typically provide additional information, such as input deliverable checklists to allow meaningful categorization in those particular industries.

Primary Secondary Characteristic Characteristic

EXPECTED PREPARATION LEVEL OF ACCURACY EFFORT PROJECT END USAGE METHODOLOGY RANGE Typical degree of DEFINITION Typical purpose of Typical estimating ESTIMATE Typical variation in effort relative to Expressed as % of estimate method CLASS low and high least cost index of complete definition ranges [a] 1 [b] Capacity Factored, Parametric Models, L: -20% to -50% Class 5 0% to 2% Concept Screening 1 Judgment, or H: +30% to +100% Analogy

Equipment L: -15% to -30% Class 4 1% to 15% Study or Feasibility Factored or 2 to 4 H: +20% to +50% Parametric Models

Semi-Detailed Unit Budget, Costs with L: -10% to -20% Class 3 10% to 40% Authorization, or 3 to 10 Assembly Level H: +10% to +30% Control Line Items

Detailed Unit Cost Control or Bid/ L: -5% to -15% Class 2 30% to 70% with Forced 4 to 20 Tender H: +5% to +20% Detailed Take-Off

Detailed Unit Cost Check Estimate or L: -3% to -10% Class 1 50% to 100% with Detailed Take- 5 to 100 Bid/Tender H: +3% to +15% Off

Notes: [a] The state of process technology and availability of applicable reference cost data affect the range markedly. The +/- value represents typical percentage variation of actual costs from the cost estimate after application of contingency (typically at a 50% level of confidence) for given scope. [b] If the range index value of “1” represents 0.005% of project costs, then an index value of 100 represents 0.5%. Estimate preparation effort is highly dependent upon the size of the project and the quality of estimating data and tools.

Figure 1. – Cost Estimate Classification Matrix for Process Industries

Copyright 2000 AACE, Inc. AACE International Recommended Practices and Standards

3 Attachment 1-1 AACE 18R-97

Cost Estimate Classification System – As Applied in Engineering 3 of 8 Procurement, and Construction for the Process Industries

June 15, 1998 CHARACTERISTICS OF THE ESTIMATE CLASSES

The following charts (figures 2a through 2e) provide detailed descriptions of the five estimate classifications as applied in the process industries. They are presented in the order of least-defined estimates to the most-defined estimates. These descriptions include brief discussions of each of the estimate characteristics that define an estimate class. For each chart, the following information is provided.

• ANSI Standard Reference (1972) Name: this is a reference to the equivalent estimate class in the existing ANSI standards. • Alternate Estimate Names, Terms, Expressions, Synonyms: this section provides other commonly used names that an estimate of this class might be known by. These alternate names are not endorsed by this Recommended Practice. The user is cautioned that an alternative name may not always be correlated with the class of estimate as identified in the chart. • Description: a short description of the class of estimate, including a brief listing of the expected estimate inputs based on the level of project definition. • Level of Project Definition Required: expressed as a percent of full definition. For the process industries, this correlates with the percent of engineering and design complete. • End Usage: a short discussion of the possible end usage of this class of estimate. • Estimating Methods Used: a listing of the possible estimating methods that may be employed to develop an estimate of this class. • Expected Accuracy Range: typical variation in low and high ranges after the application of contingency (determined at a 50% level of confidence). Typically, this results in a 90% confidence that the actual cost will fall within the bounds of the low and high ranges. • Effort to Prepare: this section provides a typical level of effort (in hours) to produce a complete estimate for a US$20,000,000 plant. Estimate preparation effort is highly dependent on project size, project complexity, estimator skills and knowledge, and on the availability of appropriate estimating cost data and tools.

CLASS 5 ESTIMATE ANSI Standard Reference Z94.2-1989 Name: End Usage: Order of magnitude estimate (typically -30% to +50%). Class 5 estimates are prepared for any number of strategic business planning purposes, such as but not limited to Alternate Estimate Names, Terms, Expressions, market studies, assessment of initial viability, evaluation of Synonyms: alternate schemes, project screening, project location Ratio, ballpark, blue sky, seat-of-pants, ROM, idea study, studies, evaluation of resource needs and budgeting, long- prospect estimate, concession license estimate, range capital planning, etc. guesstimate, rule-of-thumb. Estimating Methods Used: Description: Class 5 estimates virtually always use stochastic Class 5 estimates are generally prepared based on very estimating methods such as cost/capacity curves and limited information, and subsequently have wide accuracy factors, scale of operations factors, Lang factors, Hand ranges. As such, some companies and organizations have factors, Chilton factors, Peters-Timmerhaus factors, elected to determine that due to the inherent inaccuracies, Guthrie factors, and other parametric and modeling such estimates cannot be classified in a conventional and techniques. systemic manner. Class 5 estimates, due to the requirements of end use, may be prepared within a very Expected Accuracy Range: limited amount of time and with little effort expended— Typical accuracy ranges for Class 5 estimates are - 20% to sometimes requiring less than an hour to prepare. Often, -50% on the low side, and +30% to +100% on the high little more than proposed plant type, location, and capacity side, depending on the technological complexity of the are known at the time of estimate preparation. project, appropriate reference information, and the inclusion of an appropriate contingency determination. Level of Project Definition Required: Ranges could exceed those shown in unusual 0% to 2% of full project definition. circumstances.

Effort to Prepare (for US$20MM project): As little as 1 hour or less to perhaps more than 200 hours, depending on the project and the estimating methodology used. Figure 2a. – Class 5 Estimate

Copyright 2000 AACE, Inc. AACE International Recommended Practices and Standards

4 Attachment 1-1 AACE 18R-97

Cost Estimate Classification System – As Applied in Engineering 4 of 8 Procurement, and Construction for the Process Industries

June 15, 1998 CLASS 4 ESTIMATE ANSI Standard Reference Z94.2-1989 Name: End Usage: Budget estimate (typically -15% to + 30%). Class 4 estimates are prepared for a number of purposes, such as but not limited to, detailed strategic planning, Alternate Estimate Names, Terms, Expressions, business development, project screening at more Synonyms: developed stages, alternative scheme analysis, Screening, top-down, feasibility, authorization, factored, confirmation of economic and/or technical feasibility, and pre-design, pre-study. preliminary budget approval or approval to proceed to next stage. Description: Class 4 estimates are generally prepared based on limited Estimating Methods Used: information and subsequently have fairly wide accuracy Class 4 estimates virtually always use stochastic ranges. They are typically used for project screening, estimating methods such as equipment factors, Lang determination of feasibility, concept evaluation, and factors, Hand factors, Chilton factors, Peters-Timmerhaus preliminary budget approval. Typically, engineering is from factors, Guthrie factors, the Miller method, gross unit 1% to 5% complete, and would comprise at a minimum the costs/ratios, and other parametric and modeling following: plant capacity, block schematics, indicated techniques. layout, process flow diagrams (PFDs) for main process systems, and Expected Accuracy Range: preliminary engineered process and utility equipment lists. Typical accuracy ranges for Class 4 estimates are -15% to -30% on the low side, and +20% to +50% on the high side, Level of Project Definition Required: depending on the technological complexity of the project, 1% to 15% of full project definition. appropriate reference information, and the inclusion of an appropriate contingency determination. Ranges could exceed those shown in unusual circumstances.

Effort to Prepare (for US$20MM project): Typically, as little as 20 hours or less to perhaps more than 300 hours, depending on the project and the estimating methodology used. Figure 2b. – Class 4 Estimate

CLASS 3 ESTIMATE ANSI Standard Reference Z94.2-1989 Name: End Usage: Budget estimate (typically -15% to + 30%). Class 3 estimates are typically prepared to support full project funding requests, and become the first of the Alternate Estimate Names, Terms, Expressions, project phase “control estimates” against which all actual Synonyms: costs and resources will be monitored for variations to the Budget, scope, sanction, semi-detailed, authorization, budget. They are used as the project budget until replaced preliminary control, concept study, development, basic by more detailed estimates. In many owner organizations, engineering phase estimate, target estimate. a Class 3 estimate may be the last estimate required and could well form the only basis for cost/schedule control. Description: Class 3 estimates are generally prepared to form the basis Estimating Methods Used: for budget authorization, appropriation, and/or funding. As Class 3 estimates usually involve more deterministic such, they typically form the initial control estimate against estimating methods than stochastic methods. They usually which all actual costs and resources will be monitored. involve a high degree of unit cost line items, although these Typically, engineering is from 10% to 40% complete, and may be at an assembly level of detail rather than individual would comprise at a minimum the following: process flow components. Factoring and other stochastic methods may diagrams, utility flow be used to estimate less-significant areas of the project. diagrams, preliminary piping and instrument diagrams, plot plan, developed layout drawings, and essentially complete Expected Accuracy Range: engineered process and utility equipment lists. Typical accuracy ranges for Class 3 estimates are -10% to -20% on the low side, and +10% to +30% on the high side, Level of Project Definition Required: depending on the technological complexity of the project, 10% to 40% of full project definition. appropriate reference information, and the inclusion of an appropriate contingency determination. Ranges could exceed those shown in unusual circumstances.

Effort to Prepare (for US$20MM project): Typically, as little as 150 hours or less to perhaps more than 1,500 hours, depending on the project and the estimating methodology used. Figure 2c. – Class 3 Estimate

Copyright 2000 AACE, Inc. AACE International Recommended Practices and Standards

5 Attachment 1-1 AACE 18R-97

Cost Estimate Classification System – As Applied in Engineering 5 of 8 Procurement, and Construction for the Process Industries

June 15, 1998 CLASS 2 ESTIMATE ANSI Standard Reference Z94.2-1989 Name: End Usage: Definitive estimate (typically -5% to + 15%). Class 2 estimates are typically prepared as the detailed control baseline against which all actual costs and Alternate Estimate Names, Terms, Expressions, resources will now be monitored for variations to the Synonyms: budget, and form a part of the change/variation control Detailed control, forced detail, execution phase, master program. control, engineering, bid, tender, change order estimate. Estimating Methods Used: Description: Class 2 estimates always involve a high degree of Class 2 estimates are generally prepared to form a detailed deterministic estimating methods. Class 2 estimates are control baseline against which all project work is monitored prepared in great detail, and often involve tens of in terms of cost and progress control. For contractors, this thousands of unit cost line items. For those areas of the class of estimate is often used as the “bid” estimate to project still undefined, an assumed level of detail takeoff establish contract value. Typically, engineering is from 30% (forced detail) may be developed to use as line items in the to 70% complete, and would comprise at a minimum the estimate instead of relying on factoring methods. following: process flow diagrams, utility flow diagrams, piping and instrument diagrams, heat and material Expected Accuracy Range: balances, final plot plan, final layout drawings, complete Typical accuracy ranges for Class 2 estimates are -5% to engineered process and utility equipment lists, single line -15% on the low side, and +5% to +20% on the high side, diagrams for electrical, electrical equipment and motor depending on the technological complexity of the project, schedules, vendor quotations, detailed project execution appropriate reference information, and the inclusion of an plans, resourcing and work force plans, etc. appropriate contingency determination. Ranges could exceed those shown in unusual circumstances. Level of Project Definition Required: 30% to 70% of full project definition. Effort to Prepare (for US$20MM project): Typically, as little as 300 hours or less to perhaps more than 3,000 hours, depending on the project and the estimating methodology used. Bid estimates typically require more effort than estimates used for funding or control purposes. Figure 2d. – Class 2 Estimate

CLASS 1 ESTIMATE ANSI Standard Reference Z94.2 Name: End Usage: Definitive estimate (typically -5% to + 15%). Class 1 estimates are typically prepared to form a current control estimate to be used as the final control baseline Alternate Estimate Names, Terms, Expressions, against which all actual costs and resources will now be Synonyms: monitored for variations to the budget, and form a part of Full detail, release, fall-out, tender, firm price, bottoms-up, the change/variation control program. They may be used to final, detailed control, forced detail, execution phase, evaluate bid checking, to support vendor/contractor master control, fair price, definitive, change order estimate. negotiations, or for claim evaluations and dispute resolution. Description: Class 1 estimates are generally prepared for discrete parts Estimating Methods Used: or sections of the total project rather than generating this Class 1 estimates involve the highest degree of level of detail for the entire project. The parts of the project deterministic estimating methods, and require a great estimated at this level of detail will typically be used by amount of effort. Class 1 estimates are prepared in great subcontractors for bids, or by owners for check estimates. detail, and thus are usually performed on only the most The updated estimate is often referred to as the current important or critical areas of the project. All items in the control estimate and becomes the new baseline for estimate are usually unit cost line items based on actual cost/schedule control of the project. Class 1 estimates may design quantities. be prepared for parts of the project to comprise a fair price estimate or bid check estimate to compare against a Expected Accuracy Range: contractor’s bid estimate, or to evaluate/dispute claims. Typical accuracy ranges for Class 1 estimates are -3% to Typically, engineering is from 50% to 100% complete, and -10% on the low side, and +3% to +15% on the high side, would comprise virtually all engineering and design depending on the technological complexity of the project, documentation of the project, and complete project appropriate reference information, and the inclusion of an execution and commissioning plans. appropriate contingency determination. Ranges could exceed those shown in unusual circumstances. Level of Project Definition Required: 50% to 100% of full project definition. Effort to Prepare (for US$20MM project): Class 1 estimates require the most effort to create, and as such are generally developed for only selected areas of the project, or for bidding purposes. A complete Class 1 estimate may involve as little as 600 hours or less, to perhaps more than 6,000 hours, depending on the project and the estimating methodology used. Bid estimates typically require more effort than estimates used for funding or control purposes. Figure 2e. – Class 1 Estimate

Copyright 2000 AACE, Inc. AACE International Recommended Practices and Standards

6 Attachment 1-1 AACE 18R-97

Cost Estimate Classification System – As Applied in Engineering 6 of 8 Procurement, and Construction for the Process Industries

June 15, 1998 COMPARISON OF CLASSIFICATION PRACTICES

Figures 3a through 3c provide a comparison of the estimate classification practices of various firms, organizations, and published sources against one another and against the guideline classifications. These tables permits users to benchmark their own classification practices.

Association of Cost Norwegian Project American Society AACE Classification ANSI Standard AACE Pre-1972 Engineers (UK) Management of Professional Standard Z94.0 ACostE Association (NFP) Estimators (ASPE)

Concession Estimate

Order of Magnitude Order of Magnitude Order of Magnitude Exploration Estimate Class 5 Estimate Estimate Estimate -30/+50 Class IV -30/+30 Level 1 Feasibility Estimate

Authorization Class 4 Study Estimate Study Estimate Class III -20/+20 Estimate Level 2 Budget Estimate -15/+30 Master Control Class 3 Preliminary Estimate Budget Estimate Level 3 Class II -10/+10 Estimate

Class 2 Definitive Estimate Level 4 INCREASING PROJECT DEFINITION Definitive Estimate Definitive Estimate Current Control -5/+15 Class I -5/+5 Estimate Level 5 Class 1 Detailed Estimate Level 6

Figure 3a. – Comparison of Classification Practices

Copyright 2000 AACE, Inc. AACE International Recommended Practices and Standards

7 Attachment 1-1 AACE 18R-97

Cost Estimate Classification System – As Applied in Engineering 7 of 8 Procurement, and Construction for the Process Industries

June 15, 1998

Major Consumer AACE Classification Major Oil Company Major Oil Company Major Oil Company Products Company Standard (Confidential) (Confidential) (Confidential) (Confidential)

Class A Class V Prospect Estimate Class S Class 5 Order of Magnitude Class V Strategic Estimate Estimate Class B Evaluation Estimate

Class C Class 1 Class IV Feasibility Estimate Class 4 Class IV Conceptual Estimate Screening Estimate Class D Development Class III Estimate Class 2 Primary Control Class III Class 3 Semi-Detailed Estimate Class E Estimate Preliminary Estimate Class II Class F Master Control Class II Class 2 Master Control INCREASING PROJECT DEFINITION Estimate Class 3 Estimate Detailed Estimate Class I Current Control Class 1 Current Control Class I Estimate Estimate Figure 3b. – Comparison of Classification Practices

J.R. Heizelman, K.T. Yeo, Stevens & Davis, P. Behrenbruck, AACE Classification 1988 AACE The Cost Engineer, 1988 AACE Journal of Petroleum Standard Transactions [1] 1989 [2] Transactions [3] Technology, 1993 [4]

Class V Class 5 Class V Class III* Order of Magnitude Order of Magnitude

Class IV Class 4 Class IV Factor Estimate Study Estimate

Class III Class II Class 3 Class III Office Estimate

Budget Estimate Class II Class 2 Class II INCREASING PROJECT DEFINITION Definitive Estimate

Class I Class 1 Class I Class I Control Estimate Final Estimate

[1] John R. Heizelman, ARCO Oil & Gas Co., 1988 AACE Transactions, Paper V3.7 [2] K.T. Yeo, The Cost Engineer, Vol. 27, No. 6, 1989 [3] Stevens & Davis, BP International Ltd., 1988 AACE Transactions, Paper B4.1 (* Class III is inferred) [4] Peter Behrenbruck, BHP Petroleum Pty., Ltd., article in Petroleum Technology, August 1993

Figure 3c. – Comparison of Classification Practices

Copyright 2000 AACE, Inc. AACE International Recommended Practices and Standards

8 Attachment 1-1 AACE 18R-97

Cost Estimate Classification System – As Applied in Engineering 8 of 8 Procurement, and Construction for the Process Industries

June 15, 1998 ESTIMATE INPUT CHECKLIST AND MATURITY MATRIX

Figure 4 maps the extent and maturity of estimate input information (deliverables) against the five estimate classification levels. This is a checklist of basic deliverables found in common practice in the process industries. The maturity level is an approximation of the degree of completion of the deliverable. The degree of completion is indicated by the following letters.

• None (blank): development of the deliverable has not begun. • Started (S): work on the deliverable has begun. Development is typically limited to sketches, rough outlines, or similar levels of early completion. • Preliminary (P): work on the deliverable is advanced. Interim, cross-functional reviews have usually been conducted. Development may be near completion except for final reviews and approvals. • Complete (C): the deliverable has been reviewed and approved as appropriate.

ESTIMATE CLASSIFICATION General Project Data: CLASS 5 CLASS 4 CLASS 3 CLASS 2 CLASS 1 Project Scope Description General Preliminary Defined Defined Defined Plant Production/Facility Capacity Assumed Preliminary Defined Defined Defined Plant Location General Approximate Specific Specific Specific Soils & Hydrology None Preliminary Defined Defined Defined Integrated Project Plan None Preliminary Defined Defined Defined Project Master Schedule None Preliminary Defined Defined Defined Escalation Strategy None Preliminary Defined Defined Defined Work Breakdown Structure None Preliminary Defined Defined Defined Project Code of Accounts None Preliminary Defined Defined Defined Contracting Strategy Assumed Assumed Preliminary Defined Defined Engineering Deliverables: Block Flow Diagrams S/P P/C C CC Plot Plans S P/C C C Process Flow Diagrams (PFDs) S/P P/CCC Utility Flow Diagrams (UFDs) S/P P/C C C Piping & Instrument Diagrams (P&IDs) S P/CCC Heat & Material Balances S P/CCC Process Equipment List S/P P/CCC Utility Equipment List S/P P/C C C Electrical One-Line Drawings S/P P/CCC Specifications & Datasheets S P/CCC General Equipment Arrangement Drawings S P/CCC Spare Parts Listings S/P P C Mechanical Discipline Drawings S PP/C Electrical Discipline Drawings S PP/C Instrumentation/Control System Discipline Drawings S PP/C Civil/Structural/Site Discipline Drawings S PP/C

Figure 4. – Estimate Input Checklist and Maturity Matrix

REFERENCES

ANSI Standard Z94.2-1989. Industrial Engineering Terminology: Cost Engineering. AACE International Recommended Practice No.17R-97, Cost Estimate Classification System.

Copyright 2000 AACE, Inc. AACE International Recommended Practices and Standards

9 Attachment 1-1 AACE 18R-97

10 Chapter 2 Inputs to the Estimating Process Inputs to the Estimating Process Chapter 2

Chapter 2 Inputs to Estimating Process

Chapter 2 – Inputs to Estimating Process

Introduction

This Chapter describes the key inputs to the cost estimating process and focuses primarily on the transmit- tal of project scope definition to the estimating team. Scope definition is consistently identified as the most important factor in estimating accuracy. Scope communication between the engineering and estimating teams is particularly critical in the early stages of project development when little scope is physically shown in the documents. The engineer is expected to work closely with the estimating team throughout the plan- ning and design phases of the project to ensure effective communication of the scope including both what is shown and not shown in the documents. An integrated design and estimating team will help facilitate the scope transfer and cost estimate development process.

The primary cost estimating inputs covered in this chapter are: • General Estimate Preparation • Estimate Work Breakdown Structure • Project Scope (Reports, Drawings, Specifications, etc.) – Scope Definition – Gap Analysis – Scope Change Log • Project Risks • Project Schedule • Pre-Estimate Preparation Meeting

Estimate Preparation Services

In some instances, the engineer is rushed to make a deliverable date and the estimating team may not be given sufficient time to prepare a quality estimate. In other cases, the estimating team may be stretched with workload and not apply adequate time to develop a proper estimate. Independent of cause, a hasty estimate can obviously result in greater estimating error.

The estimating team is encouraged to develop a cost estimating model that can be used to quickly deter- mine the level of effort and cost to provide adequate cost estimating services, meeting all of the require- ments outlined in this Manual. Factors that should be considered in the model include but are not limited to the following:

• Cost estimate class (5, 4, 3, 2, or 1) • Estimated total construction cost • Project complexity • Estimated No. of Drawings

2-1 Cost Estimating Manual June 2008

• Availability of effective parametric cost models (for early estimates) • Effectiveness of coordination and communication of design team with estimating team • Average hourly rates of estimating staff

The AACE has an example cost estimating services model that can be downloaded from the website and calibrated based on each estimating team’s historical estimating experience. This model only includes cost and time for the cost estimating function. It does not include the level of effort required of the engineering team to develop the deliverables and coordinate with the estimating team.

To ensure adequate management of the schedule and budget of all estimating services, the consultant engineer shall provide the following information:

• At the beginning of both the facility planning and the design phase of all BEDC projects, the design and estimating team must identify the amount of time required, the number of estimators required, and the schedule for preparation of all estimates. This information must be summarized in the Project Manage- ment Plan and incorporated into the Engineer’s baseline project schedule. Any projected schedule variation or any significant change in the overall project scope should be reported to the estimating team so that the estimating services plan can be adjusted as necessary to ensure adequate time and budget for preparation of a sound cost estimate at all submittal milestones. • In the cover letter for all cost estimates submitted to BEDC, the engineer of record must document the date that the scope package was delivered to the estimating team, the date the project team met with the estimating team to review the information, the date the estimate was returned to the engineer for review, and the date the estimate was submitted to BEDC. The lead estimator should be copied on the correspondence to BEDC. • The consultant’s monthly invoice should include a separate task for cost estimating support and ser- vices. The invoice must include an itemized list of the name and corresponding number of hours devoted to cost estimating services during the billing period.

Estimate Work Breakdown Structure (WBS)

The WBS is a hierarchal listing of elements that organizes and defines the scope of the project into man- ageable and definable areas and packages of work. A standard WBS must be created prior to initiating any cost estimating services. The WBS provides the structure in which to produce the estimate and must remain constant throughout each of the project estimating phases. An established WBS provides the fol- lowing benefits:

1. Drives consistency in the elements and line items included in the cost estimates. 2. Acts as a checklist to ensure all required elements are included in the estimate. 3. Provides a communication tool between the designer and estimator for scope definition at each esti- mating interval. 4. Provides a framework for allocating costs to scope items not shown at various cost estimating intervals. 5. Facilitates cost reconciliation from one estimate to the next by isolating areas of cost increase. 6. Facilitates review and comparison of cost estimates at both a gross level and detailed level across multiple capital projects.

2-2 Chapter 2 Inputs to Estimating Process

A standard six-level WBS structure has been established for BEDC Capital Projects and is as shown below: Level 1 – Area Level 2 – Process Level 3 – System Level 4 – Group/Division Level 5 – Work Package Level 6 – Assembly

Level 1 – Area Area is the highest level of the WBS and represents a geographical area of the site with a defined boundary that may include one or more process units. Areas may also included non-process parts of a plant includ- ing roads, walkways, landscaping, buildings, etc. Examples of typical areas include Headworks, Solids Handling, Primary Clarification, or Effluent Pump Station. The boundaries for an area are generally defined as the footprint of all the process elements that are co-located in the same discrete area. Interconnecting piping and other utilities (between process units) should be assigned to the “General/Site” area.

Level 2 - Process A process unit typically changes the physical properties of whatever enters it or it can be a utility process that enhances or improves the efficiency of the process function. Examples of processes include Primary Clarification, Screening, or Thickening. Depending on the facility, a process under an Area can be one in the same. For example, the Filtration process can be located in the Filtration area along with other processes such as the Filtration Backwash Waste Basin. In other cases the processes can be different from the area. For example, the Screening process is typically located in the Headworks area, along with other processes such as Coarse Solids Reduction, Grit Processing, etc. Many of the elements within any given area are required to complete the facility, but are not necessarily part of any given process. For consistency, items not shown on the P&ID’s (Process and Instrumentation Diagrams) or not directly attributable to systems shown on the P&ID’s, should be assigned to the “General/Building” designation at WBS Level 2. Support elements, such as electrical service, instrumentation, SCADA, that can be attributed to a process and/or system should be assigned to that process/system. To make this distinction, determine if the element would be eliminated if the process/system was eliminated.

Level 3 – System A system is a component of a process that is required in order to achieve the process objective. Examples of systems include Grit Cyclone for the grit removal process, Backwash Pump System for the filtration process, or Chlorine Contact Tank for the Disinfection Process. Capacity and/or sizing information for each system is also provided by the design team. The distinction between a “process” and a “system” can also be explained by the following:

• A process is what is being done to the material in the process stream. • Systems are the physical components that enable the process.

2-3 Cost Estimating Manual June 2008

Since some systems may be optional, depending on process design, and the different types of systems may also accomplish the same purpose with the process, it is essential that the design team define all systems required for a given process.

For items assigned to the “General/Buildings” designation at WBS Level 2, system designations at WBS Level 3 should follow Uniformat II for Major Group Items as defined by ASTM E1557-05 designations. These include:

A – Substructure B – Shell C – Interiors D – Services E – Equipment and Furnishings F – Special Construction and G – Sitework

For incorporation into the overall WBS for a treatment plant project, the code should be linked together to include the abbreviation for the General/Buildings process as shown below:

G/B-A – Substructure G/B-B – Shell etc.

Level 4 – Group/Division Level 4 organizes project elements into groups (Group Elements in ASTM E1557) and/or CSI major divi- sions (Divisions 1 through 17).

Level 5 – Work Package The Work Package level is largely where the work packages are broken down based on the discipline, trade, or crew. Work packages are generally the scope of work within each system that would be performed by a specialty subcontractor to the general contractor or by a separate trade discipline/crew within the general contactor’s forces. (In ASTM E 1557 Work Packages are identified as Individual Elements). Examples of Work Packages include Mass Excavation, Structural Excavation, Equipment, Process Piping, Yard Piping, Plumbing, Structural Concrete, Structural Steel, Miscellaneous Metal, Masonry, Electrical, Painting and Coating, etc. A standard list of Work Packages organized by CSI division is included as Attachment 2-1 to this Manual.

Level 6 – Assembly Assembly is the lowest level of the WBS and is where the detailed quantity take-off is performed. Assemblies are used to convert the dimensional information available on the plan to detailed line item quantities in order to calculate the cost of labor, materials, equipment, subcontracts, etc. for the elements shown on the design

2-4 Chapter 2 Inputs to Estimating Process drawings. For example, given the dimensions and rebar sizing/spacing for a slab on grade, the estimator can determine quantities for the detailed line items such as:

• Fine grading/subgrade preparation • Volume of aggregate base (if required) • Vapor barrier (if required) • Formwork area • Concrete volume to buy and place • Surface area of concrete requiring finishing • Quantity of reinforcing steel to buy and install

A partial sample of a WBS for a portion of a wastewater treatment plant is shown below: Level 1(Area) – Headworks Level 2 (Process) - General Level 2 (Process) - Screening Level 2 (Process) – Coarse Solids Reduction Level 2 (Process) – Odor Collection Level 2 (Process) – General/Buildings Level 2 (Process) – Grit/Debris Processing Level 3 (System) – Grit Classifications/Separation and Washing Level 3 (System) - Grit Conveyance Level 3 (System - Grit Receptacle Level 3 (System) – Grit Removal Level 4 (Group/Discipline) – Equipment/Division 11 Level 4 (Group/Discipline) – Piping/Division 15 Level 4 (Group/Discipline) – Electrical/Division 16 Level 5 (Work Package) – Electrical Service and Distribution Level 6 (Assembly) – Equipment Connection Detail Estimate Line Items (included in the assembly): Conduit Wire/Cable Flex Motor Connection Local VFD/Control Station Disconnects Heat Trace

In the example above, multiple processes exist within the same area. Accordingly, systems that are a child of the area (building substructure, building services, building superstructure), but are common to and sup-

2-5 Cost Estimating Manual June 2008 port multiple processes would be assigned to “General/Buildings” at Level 2 as shown below:

Level 1 (Area) – Headworks Level 2 (Process) – Screening Level 2 (Process) – Coarse Solids Reduction Level 2 (Process) – Grit/Debris Processing Level 2 – General/Buildings Level 3 – G/B-A; Substructure Level 4 (Work Package) – Structure Excavation Level 4 (Work Package) – Foundation Level 3 – G/B- Services Level 4 – (Group/Division) – Electrical/Division 17 Level 4 – (Group/Division) – Plumbing/Division 15 Level 4 – (Group/Division) – HVAC/Division 15 Level 4 – (Group/Division) – Fire Protection/Division 15 Level 3 – G/B - Shell Level 4 - (Group/Division) – Exterior Enclosure/Division 3 Level 5 – Exterior Walls Level 6 – (Assembly) – CIP Concrete Walls Assembly includes these detail items: Concrete Construction Joints Waterstop Formwork Placement Reinforcing Embedded Items Strip Forms Finish Cure

In the example above, the Level 3 items do not support any given process and therefore they are assigned to “General” at Level 2. This same rationale applies whenever a WBS value at any level is not specific to any given WBS element at the higher (parent) level. If the element cannot be specifically assigned to a unique element at the higher level, it is assigned to the “General” value at the higher level. Another way to determine whether an element belongs to a specific element at a higher level is to evaluate whether or not the lower level element is required if the higher level element is deleted. If the lower level element is still required (even though it may be downsized), it should be assigned to the “General” WBS value at the higher

2-6 Chapter 2 Inputs to Estimating Process level. Conversely, if the lower level element is no longer required if the higher level element is eliminated, it should be assigned specifically to the corresponding higher element.

An example WBS for typical wastewater facilities can be discerned in the Example Cost Estimating Output Reports included as Attachments 4-1 and referenced in Chapter 4 of this Manual. Level 5 (Work Package) and Level 6 (Assembly) WBS values, organized by CSI specification division for use on all types of DEP projects are included in Attachment 2-1 of this Manual.

WBS Development by Deliverable Milestone and Estimate Class Table 2-1 provides a summary of the minimum and desirable level of the WBS that must be developed for each cost estimate at each delivery milestone. The minimum and desirable levels of the WBS reflect the range of scope definition that may be available at each estimating interval. Levels 1 through 3 of the WBS should be defined by the engineer of record while levels 4 and 5 can be developed jointly by the engineer and the estimating team with the engineer likely providing the initial definition and the estimating team verifying this information. Level 6, and the detailed estimate line items below Level 6, are defined and generated by the estimating team.

Table 2-1 WBS Requirements for Each Estimate Deliverable

Li f e Cy cl e Mi l e s t o n e Es t i m a t e Cl a s s Mi n i m u m WBS Le v e l De s i r a bl e WBS Le v e l Project Initiation 5 None Level 2 - Process Facility Planning 4 Level 2 - Process Level 3 - System Preliminary Design – 30% 3 Level 5 – Work Package Level 6 – Assembly Final Design – 60% 2 Level 5 – Work Package Level 6 – Assembly Final Design – 90/100% 1, 2 Level 5 – Work Package Level 6 – Assembly

Project Scope

To ensure that the estimate accurately includes all elements of the approved project scope, the design team shall transmit a project scope definition package to the estimating team at each estimating milestone. The project scope definition package shall include, at a minimum, the following documents:

• WBS • Scope Documents (Reports, Memos, Drawings, Specifications, etc.) • Gap Analysis • Scope Change Log Work Breakdown Structure The WBS will be used by the engineering team to communicate a detailed itemized scope of the overall project to the estimating team. This is a particularly valuable tool to communicate scope shown and scope not shown. Often the engineer has an understanding of the scope of the project beyond what has been

2-7 Cost Estimating Manual June 2008 documented to date via the planning documents or the design drawings and specifications. On the other hand, the estimator’s understanding of the scope is somewhat limited to what is shown in the physical documents.

The estimating team will use the WBS transmitted by the engineer to structure the development and pre- sentation of the cost estimate. The estimating team will develop line item costs at the lowest level available in the WBS for each area. Depending on what level this is, the line item estimate could be based on results of parametric modeling (e.g. Level 2), estimated allocations (Level 1, 2, 3, or 4), or quantities shown or as- sumed (e.g. Level 6). The WBS should be as detailed as possible based on the engineer’s understanding of the ultimate project scope. The more detailed the WBS can be developed, the more powerful a tool it will be to the estimating team to allocate costs to the project, and the more valuable to the engineer in reviewing the estimate. As estimates are developed through the life cycle and additional scope is shown, costs associated with unquantified items will shift from allocations to more detailed (and correspondingly more accurate) take-offs.

Scope Definition Project scope definition is the most critical element in successful cost estimating. A minimum level of scope definition is required for each AACE Estimating Class. If the necessary scope definition is not provided at each milestone, the estimating team can not develop the associated class of estimate with the expected range of accuracy. The BEDC has developed a summary of the scope requirements for each deliverable milestone and associated AACE Estimating Class (See Attachment 2-2). The table is a significant expan- sion of Figure 4 in the AACE Recommended Practice No. 18R-97 (see page 8 of Attachment 1-1) tailored largely to the municipal water and wastewater industries. The engineer is required to review the content table and ensure that as many items as possible are included with each associated deliverable. Areas that could not be developed due to lack of information shall be flagged to the estimating team and should be a focus of the Gap Analysis described in the next section.

In any project, certain elements of the project will have the most significant effect on the final construction cost. As a rule of thumb, about 20% of the elements of a project can comprise 80% of the total cost. These elements or “cost drivers” should be identified as early in the project life cycle as possible and the design team should focus progress on design development based on the key cost drivers. This will improve the expected accuracy of the cost estimates at early stages of project development. In general, the content requirements for each class of estimate shown in Attachment 2-2 of this Manual are intended to capture the key cost drivers at early stages of project development.

2-8 Chapter 2 Inputs to Estimating Process

Cost drivers vary depending on the type of project and the project-specific scope. For water and waste- water treatment plant work, key cost drivers in early stages of project development typically include the following:

Table 2-2 Key Cost Drivers in Early Project Development Es t i m a t e Cl a s s Ke y Co s t Dr i v e r s Class 5 Capacity Site Selection Process Selection Class 4 Major Process Design Criteria Preliminary Site Plan Preliminary Geotechnical Information Preliminary Hydraulic Profile Preliminary Equipment List Preliminary Electrical Loads Preliminary Building, Structure, and Process Area Elevations, Plans and Major Sections (Archi- tectural and Mechanical Disciplines with approximately structural dimensions) Class 3 Final Geotechnical Plan Site Hazard Assessment Final Site Plan and Hydraulic Profile (Site Civil Works) Building and Process Area Plans and Major Sections Preliminary Concrete and Reinforcing Steel Quantities Mechanical Equipment and Valves Large Piping Electrical Equipment and Distribution (Single Line Drawings) Architectural Elevations Process and Instrumentation Drawings Construction Duration (General Conditions)

Gap Analysis A Gap Analysis is a systematic review and evaluation of the design documents against the approved scope. In performing the Gap Analysis, the current design deliverables are reviewed to assess the elements of the design scope that are and are not illustrated. The “gap” items convey scope elements known by the engineer to ultimately be required to complete the project but are not yet shown in the unfinished contract documents. The estimators use the Gap Analysis to develop as complete a price as possible by including unshown items identified in the Analysis. In general, the more comprehensive the Gap Analysis, the less uncertainty in the cost estimate.

The Gap Analysis is performed by the project design team. The lead designers should identify areas of the design that require further development, as well as elements that will be required, but have yet to be designed. As part of the Gap Analysis, the engineer should provide guidance on how to close the scope gap in the estimating process. Where possible, one or more of the following strategies should be used to close the identified scope gaps and communicate information to the estimating team:

2-9 Cost Estimating Manual June 2008

• Itemized list (with reference to drawing number) of scope items needed but not shown (e.g. structural footing drain pipe, pea gravel, geotextile, and observation manhole). • Hand mark-up on the documents delivered to the engineer with either sketches or notes of items that will be added in subsequent deliverable milestones and include a list of these items in the Gap Analysis narrative. • Hand mark-ups of existing facility drawings describing the change or elements to be replaced/ repaired. • Hand mark-ups of drawings of similar scope items from other projects showing modified dimensions and notes communicating the differences between the “go-by” design and the current project. (e.g. modify clarifier diameter from 50 to 70 feet and influent/effluent pipe diameter from 12 to 18-inch) • Provide cut sheets or other manufacturer’s information for major equipment and supplies and when available, vendor phone quotes.

Regardless of the estimate class being performed, the estimators should use the most detailed design information available at the time the estimate is being prepared. Prioritization of available design data to be used for input into the estimate (in descending order) is:

• Quantities from detailed engineering design documents for the current project including hand mark- ups where possible • Quantities from “Go-by” detail designs from a similar project • Cost estimating relationships (capacity factors, equipment factors, etc.) Scope Change Log Each project team is required to maintain a scope change log throughout the design phase of the project. The scope change log is a tool to record all changes to the defined project scope. During the Design Phase, the Scope Change Log should maintain a record of any changes to the project that were either not defined or not anticipated at the initiation of the Design phase. Typically, the scope of a project during the Facility Planning Phase is captured in a Basis of Design Report (BODR). It is particularly important to document all scope items that were not accounted for in the previous estimate to help direct the estimating team to the new scope items. The most recent version of the Scope Change Log shall be submitted to the estimating team with each project scope definition package to assist in quickly identifying areas of change since the previous estimate was developed.

Project Risks

Each project team is required to maintain a Risk Register throughout the life cycle of the project. The Risk Register is a tool to record all identified project risks that could impact the budget or schedule of the project. The Register includes an estimate of the probability of occurrence and quantification of the potential schedule and/or budget impact of each identified risk. Additional detail on how the Risk Register should be incorporated into the cost estimate is included in Chapter 5 – Contingency.

2-10 Chapter 2 Inputs to Estimating Process

Project Schedule

Accurate, realistic construction schedules are a critical element for developing accurate cost estimates. In addition to facilitating calculation of time-related costs, an accurate schedule validates the time allotted for construction of the project in the bid documents. At a minimum, the project design team must provide the es- timating team with significant milestones, anticipated contract dates, constraints, and phasing requirements for the project. The level of detail required in the project schedule to prepare a proper estimate increases with estimate class. A basic schedule of construction start, substantial completion and final completion is sufficient for preparation of a Class 5 estimate while a detailed critical path method Gantt schedule aligned to at least level 3 of the WBS is necessary to prepare a Class 1 estimate. The estimating and design team should work together to validate the durations and logic shown.

Pre-Estimate Meeting

Prior to development of a project estimate, a meeting shall be held with the key project stakeholders includ- ing the design team (Project Manager and technical leads, key subconsultants as appropriate), BEDC (Project Manager and a representative of the Cost Estimating Division), and the estimating team (lead estimators). The meeting should be held within approximately one week of the estimator’s receipt of the Scope Package from the engineer. The main purpose of the meeting is to ensure that the estimating team has a thorough understanding of the project scope. Key discussion items of the meeting shall include but not be limited to the following areas:

Design Team: • Review overall project scope • Review WBS • Review project scope not physically shown but necessary for the project (Gap Analysis) • Review specific areas of change since the previous estimate (recorded on Scope Change Log) • Review identified project risks (Risk Register) • Provide any historical cost data that may be relevant to project

Estimating Team: • Describe proposed estimating methodology and related assumptions • Describe proposed estimate WBS • Describe sources of data (labor, materials, escalations, etc.)

The meeting shall be documented in a set of meeting minutes highlighting key decisions and action items. All action items shall have an assigned responsible party and due date. The minutes shall be distributed to key project stakeholders.

2-11 Cost Estimating Manual June 2008

2-12 Chapter 2 Attachments

Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 2

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

HAZMAT ABATEMENT Type of Asbestos Product, Type of Asbestos Product, Area of Structure Includes Items for Glove Bag Removal, Testing, Asbestos Removal sf Method of Removal, SF of Method of Removal, SF of Disposal, Containment Structure, Negative Air, & Surface Surface Filtration. Type of Product (Paint, or Type of Product (Paint, or Area of Structure Includes Items for Containment Structure, Lead Abatement sf Metallic), SF of Surface Metallic), SF of Surface Sandblasting, Testing & Disposal. EARTHWORK Area for Clear & Grub, Density Area for Clear & Grub, Density Area of Clear & Grub Include Equipment for Clearing and Grubbing, Clear and Grub acre of Vegetation of Vegetation Chipping & Disposal. Area for Clear & Grub, Density Area for Clear & Grub, Density Area of Clear & Grub Include Equipment and Labor for Felling Trees, Logging acre of Vegetation of Vegetation Tree Handling, & Transport. Lf of Silt Fence, Area for Re- Lf of Silt Fence, Area for Re- Area of Erosion Control Include silt fence, re-seeding, tire washes, check Erosion Control ls seeding, # Tire Washes, # of seeding, # Tire Washes, # of dams, & Swales. Check Dams, lf of Swales Check Dams, lf of Swales Area of Rip Rap, Size of Rip Include Placement & Grouting of Rip Rap. Rip Rap cy Rap, Grouted Y/N Area of Stabilization, Depth of Area of Stabilization Area of Site Include Lime/Cement Delivery, Spreading, Mixing, Soil Stabilization (lime or cement) cy Stabilization, % Stabilization by and Compaction of Soil to be Stabilized. Vol Area of Jute Mat, Area of Area of Stabilization Area of Stabilization Include Items for Jute Mat, Seeding, and Slope Stabilization sy Seeding, lf of Drainage Swales Drainage Swales.

Depth of Shoring, Shoring Area of Shoring Area of Shoring Includes Shoring Material & Installation, Bracing, Excavation Support sf Type, Length of Shoring. Type & Support Specialities. of Support Specialities Vol of Material, Haul Distance, Vol of Material Vol of Material Includes Loading, & Hauling of Material. Trucking cy (or tons) # of Trucks Vol of Material, Haul Distance, Vol of Material Vol of Material Includes Loading, & Hauling of Material. Disposal cy (or tons) # of Trucks Vol of Cut & Fill, Haul Distance Vol of Cut & Fill Vol of Cut (Assume Site Includes Equipment and Labor to Complete Mass Excavation & Backfill cy Balance) Excavation & Backfill. Structure Dimensions, Structure Vol of Cut & Fill Vol of Cut (Assume Site Includes Equipment and Labor to Complete Structural Excavation & Backfill cy Depth, Excavation Slope Angle, Balance) Excavation & Backfill.

Lf of Drainage Piping, Size of LF of Drainage Piping Area of Site Include Excavation, Bedding, Backfill, Pipe Piping,Type of Piping # of Laying, Utility Crossing, & Restoration. Storm Drainage lf Manholes, # of Culverts, Ave Invert Depth Lf of Drainage Piping, Size of LF of Drainage Piping Area of Structure Include Excavation, Bedding, Backfill, Pipe Structure Underdrains lf Piping,Type of Piping, Ave Laying, Utility Crossing, & Restoration. Invert Depth SURVEYING Task Type ( Set Control, Duration of Survey Crew Approximate Value of Inlcudes Survey Crew Hours Based on Task. Surveying ls Building Layout, Grade Earthwork Package Checking, As-Built Surveys) SOIL STERILIZING Soil Sterilizing sy Area Area Area of Structure Includes Application of Sterilant. Pump Type, Pump Duration, Duration of Pumping Approximate Value of Includes Sump, Gravel Barrel, Pump & Hose Surface Dewatering ls Pump Qty Earthwork Package Operation. DEWATERING Well Point Spacing, Length of Length of Well Point System Approximate Value of Includes Well Installation, Wells System Lines, & Well Point System ls Line, Number of Header Lines, Earthwork Package Pump Operation. Days of Operation

ATTACHMENT 2-1 DIVISION 2 JUNE 2008 1 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 2

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

MEMBRANE LINER Liner Type, Liner Thickness, Liner Area Liner Area Includes Liner Installation as Sub Number based Membrane Liners sy Liner Area on Job Size (Small, Med, & Large) and Material Type. CAISSON DRILLING Caisson Diameter, Depth, Caisson Diameter, Depth, Area of Structure Includes Drilling of Caissons by Size and Soil Caisson Drilling vlf (or ea) Count, Soil or Rock Count, Soil or Rock Conditions. TRAFFIC CONTROL Required Elements (Traffic Duration of Traffic Control, Area Area of Site Includes Traffic Control Elements ( Permits, Control Plan, # of Flaggers, # of of Traffic Control Flaggers, Cones, Barrels, Barricades, & Signs). Traffic Control ls Cones, # of Barrels, # of Barricades, # of Signs, Duration of Work) RAILROAD WORK Required Improvement # of Crossings # of Crossings Includes Railroad Improvement Elements Elements ( # of Crossing Gates, (Permits, Crossing Gates, Signs, Signals). Rail Road Work ls # of Signs, # of Signals)

FOUNDATION SUPPORT Depth of Shoring, Length of Depth of Shoring, Length of Area of Shoring Includes Sheet Piling and Special Shoring Sheetpiling sf Shoring, Shoring Supports Shoring, Shoring Supports Elements such as Deadmen, Tie-Backs, Rakers, and Walers. Depth of Shoring, Length of Depth of Shoring, Length of Area of Shoring Includes H Piles and Lagging and Special Shoring H Pile & Lagging sf Shoring, Shoring Supports Shoring, Shoring Supports Elements such as Deadmen, Tie-Backs, Rakers, and Walers. Diameter, Depth, Count, Soil or Diameter, Depth, Count, Soil or Area of Shoring Includes Subcontractor Price for Secant Piles. Secant Walls vlf (or ea) Rock Rock Diameter, Depth, Count, Soil or Diameter, Depth, Count, Soil or Area of Shoring Includes Subcontractor Price for Tangent Piles. Tangent Walls vlf (or ea) Rock Rock Wall Length, Width, and Depth. Wall Length, Width, and Depth. Area of Shoring Includes Subcontractor Price for Slurry Walls. Slurry Walls sf Diameter, Depth, Count, Soil or Area of Shoring Area of Shoring Includes Subcontractor Price for Soil Mixing. Soil Mixing vlf (or ea) Rock No. of Slant Piles, Depth of Area of Shoring Area of Shoring Includes Subcontractor Price for Slant Piles. Underpinning vlf (or ea) Slant Piles, Diameter of Slant Piles. Diameter, Depth, Count, Soil or Diameter, Depth, Count, Soil or Area of Shoring Includes Subcontractor Price for Jet Grout Jet Grouting vlf (or ea) Rock Rock Columns. Diameter, Depth, Count, Soil or Diameter, Depth, Count, Soil or Area of Shoring Includes Subcontractor Price for Stone Columns. Stone Columns vlf (or ea) Rock Rock

2ATTACHMENT 2-1 DIVISION 2 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 2

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

SITE CONCRETE Length of Straight Section, Length of Curb Area of Site Includes Curb and/or Gutter. Curb & Gutter lf Length of Curved Section, Curb only? Area of Paving, Thickness of Area of Paving, Thickness of Area of Site Includes Concrete Paving Elements and Paving, Perimeter of Paving, Paving Pavement Markings. Concrete Paving sy Pavement Markings (y/n), # of Parking Stalls, Lf of Striping. Length of Sidewalk, Width of Length of Sidewalk Area of Site Includes Installation of Sidewalk Installation. Sidewalks sf Sidewalk, Thickness of Sidewalk. Length of Drain Pan, Width of Length of Drain Pan Area of Site Includes Concrete Paving Elements for Drain Drain Pans sf Drain Pan, Thickness of Drain Pan. Pan Length of Wall, Thickness of Area of Wall # of Walls Includes Concrete Construction Elements, Wall Height of Wall, Width of Coatings, & Exterior Finishes on Wall Face. Retaining Walls cy Base, Thickness of Base, Rebar #/CY, Face Finish AC PAVING lf of Striping, # of Parking Stalls, LF of Striping Area of Site Includes Subcontractor Price for Pavement Pavement Markings ls # of Handicap Stalls Markings. Area of Paving, Thickness of Area of Paving, Thickness of Area of Site Includes AC Paving Elements and Pavement Paving, Perimeter of Paving, Paving Markings. Paving sy Pavement Markings (y/n), # of Parking Stalls, Lf of Striping. Wheel Stops ea # of Wheel Stops # of Wheel Stops Area of Site Includes # of Wheel Stops DEMOLITION # of Crew Days, Volume of # of Crew Days, Volume of Area of Site Includes Hours for a Standard Demolition Crew Demolition ls Disposal Disposal and Disposal Costs. FENCING Fence Height, Fence Length, # Fence Height, Fence Length, # Area of Site Includes Fence Elements and Gates. Chain Link Fencing lf of Man Gates, # of Vehicle of Man Gates, # of Vehicle Gates, Barbed Wire (y/n) Gates, Barbed Wire (y/n)

ATTACHMENT 2-1 DIVISION 2 JUNE 2008 3 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 2

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

LANDSCAOPE & IRRIGATION Type of Pavers, Area of Pavers, Area of Pavers Area of Site Includes Installation of Pavers, Weed Barrier, Pavers sf Perimeter of Pavers, Base Sand, and Soil Preparation. Sand Depth Shrub Type, Shrub Size, Tree # of Shrubs, # of Trees Area of Site Inlcudes Plant Materials by Size and Type, Plant Materials ea Type, Tree Size, # of Plant Staking, Guying, Mulch, and Maintenance. Relocations Grass Area, Grass Type, Grass Area Area of Site Includes Grass Planting, Fertilizer, Loam Grasses sf or acre Fertilizer (y/n), Mulch Type, Spreading, and Mulching. Loam Thickness # of Controllers, # of Backflow Sprinkler System Area Area of Site Includes Installation of Sprinkler System Preventers, LF of 3" PVC Pipe, Components by Type and Quantity. LF of 2.5" PVC Pipe, LF of 2" PVC Pipe, LF of 1.5" PVC Pipe, LF of 1" PVC Pipe, LF of 3/4" Sprinkler Systems sf PVC Pipe, # of 3" Ftgs, # of 2.5" Ftgs, # of 2" Ftgs, # of 1.5" Ftgs, # of 1" Ftgs, # of 3/4" Ftgs, # of Rotary Heads, # of Pop-Up Heads, # of Control Valves # of Ground Cover Plants, Area of Ground Cover Area of Site Includes Ground Cover Plants, Planting Bed Ground Cover sf Planting Bed Area, Weed Preparation, Weed Barrier, and Mulch. Barrier (y/n), Mulch Type # of Architectural Boulders Area of Boulders Area of Site Includes Delivery and Machine Placement of Architectural Boulders ea Boulders. Wetlands Mitigation Plan (y/n), Wetlands Mitigation Plan (y/n), Area of Site Inlcudes Wetlands Mitigation Plan, Safety Fence, Wetland Mitigation ls lf of Safety Fence, lf of Silt lf of Safety Fence, lf of Silt and Silt Fence. Fence Fence MONITORING WELLS # of Monitoring Wells, Depth of # of Monitoring Wells Area of Site Includes Monitoring Well Drilling, Well Monitoring Wells, Monitoring Construction including Casing, Screens, Sand, & Well Dia., PVC or Stainless Bentonite, Access Structure (Flush or Stick-up), Well Materials, Depth of Soil, Well Development, Decon Station, Water Monitoring Wells vlf (ea) Depth of Rock, Handling, Clean-up and Soil Disposal. Decontamination Station (y/n), Contain Water (y/n), Flush Mount or Stick Up WELL DRILLING # of Monitoring Wells, Depth of # of Wells Area of Site Includes Well Drilling, Well Construction including Monitoring Wells, Monitoring Casing, Screens, Sand, & Bentonite, Access Well Drilling vlf (ea) Well Dia., PVC or Stainless Structure (Flush or Stick-up), and Well Well Materials, Depth of Soil, Development. Depth of Rock SIGNAGE # of Building ID Signs, # of # of Signs Area of Site Includes Building ID Signs, Traffic Signs, Room Traffic Signs, # of Room Signs, Signs, Pipe ID Signs, Hazard Signs, Restrictive # of Pipe ID Signs, # of Hazard Signs, and Equipment Tags. Signage ls Signs, # of Restrictive Signs, # of Equipment Tags

4ATTACHMENT 2-1 DIVISION 2 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 2

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

SITE PIPING Pipe Dia, Pipe Material, Invert Pipe Dia, LF of Pipe, Ftg Area of Site Includes Pipe Installation, Manholes, Flared Ends, Depth, # of Manholes, Manhole Density and Bedding. Sanitary Sewer lf Dia, # of Flared Ends, Bedding Depth Pipe Dia, Pipe Material, Pipe Pipe Dia, LF of Pipe, Ftg Area of Site Includes Pipe Installation, Bedding, Hydrants, Depth, # of 90s, # or Tees, Density PIVs, and Testing. Fire Protection lf Bedding Depth, # of Hydrants, # of PIVs Pipe Dia, Pipe Material, Pipe Pipe Dia, LF of Pipe, Ftg Area of Site Includes Pipe Installation, Bedding, Meters and Gas Piping lf Depth, # of 90s, # or Tees, # of Density Testing. Meters, Bedding Depth Pipe Dia, Pipe Material, Pipe Pipe Dia, LF of Pipe, Ftg Area of Site Includes Pipe Installation, Bedding, and Testing. Domestic / Utility Water lf Depth, # of 90s, # or Tees, Density Bedding Depth # of Manholes, Manhole Depth, # of Manholes Area of Site Includes Manhole Base, Precast Risers, Precast Manholes / Vaults ea Manhole Dia, Type of Cover, Conical Section, Ladder, Damproofing, and Damproofing (y/n) Castings. Cathodic Protection lf DEFER TO ELECTRICAL # of Potholing Locations, Depth # of Potholes Area of Site Includes Backhoe and Laborer Time, Shoring, Potholing ls of Exploration, Area of and Restoration. Restoration, Restoration Type Support Crossing Utility (y/n), # of Crossings Area of Site Includes Timber & Sling Supports, Hand Crossing Span, Hand Excavation, and Concrete Encasement. Utility Protection ls Excavate(y/n), Hand Excavation Vol, Encase Utiltity (y/n), Ecasement Vol PROCESS YARD PIPING *See Div 15 PIPING REHAB *See Div 15 PIPE BURSTING Existing Pipe Dia, Replacement Pipe Dia, LF of Pipe LF of Pipe Includes Subcontractor Price for Pipe Bursting Pipe Dia, Length of Pipe based on Length and Diameter, and Restoration. Bursting, Surface Restoration Pipe Bursting lf (y/n), Area of Restoration, Type of Restoration

JACKING & TUNNELING Depth of Launch/Receiving Pipe Dia, LF of Pipe LF of Pipe Includes Subcontractor Price for Pits, Diameter of Pipe, Length Jacking/Tunneling based on Length and Jacking & Tunneling lf of Pipe Run Diameter, Launch and Receiving Pit Construction and Backfill, and Restoration.

ATTACHMENT 2-1 DIVISION 2 JUNE 2008 5 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 3

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

FORM/REINFORCE/PLACE/FINISH CONCRETE Slab Length, Slab Width, Slab Slab Length, Slab Width, Slab Slab Length, Slab Width, Slab Includes Concrete Formwork, Construction Joints, Thickness, LF of CJ, Waterstop Thickness, LF of CJ, Waterstop Thickness, Reinforcing. Waterstop, Placement, Reinforcing, Strip Forms, Type, Thickened Edge (y/n), Type, Thickened Edge (y/n), Finish, and Cure. Reinforcing, Finish Reinforcing, Finish Slab on Grade cy Wall Length, Wall Height, Wall Wall Length, Wall Height, Wall Wall Length, Wall Height, Wall Includes Concrete Formwork, Construction Joints, Thickness, CJ Spacing, Thickness, CJ Spacing, Thickness, Reinforcing. Waterstop, Formwork, Placement, Reinforcing, Waterstop Type, Reinforcing, Waterstop Type, Reinforcing, Embedded Items, Strip Forms, Finish, and Cure. Form Type, Embedded Items, Form Type, Embedded Items, Walls cy Finish Finish Slab Length, Slab Width, Slab Slab Length, Slab Width, Slab Slab Length, Slab Width, Slab Includes Concrete Formwork, Shoring, Thickness, LF of CJ, Waterstop Thickness, LF of CJ, Waterstop Thickness, Shoring Height, Construction Joints, Waterstop, Placement, Type, Reinforcing, Shoring Type, Reinforcing, Shoring Reinforcing. Reinforcing, Strip Forms, Finish, and Cure. Volume, Embedded Items, Volume, Embedded Items, Elevated Slabs cy Finish Finish # of Beams, Length of Beam, # of Beams, Length of Beam, # of Beams, Length of Beam, Includes Concrete Formwork, Shoring, Width of Beam, Height of Width of Beam, Height of Width of Beam, Height of Placement, Reinforcing, Strip Forms, Finish, and Beams AFF, Depth of Beams, Beams AFF, Depth of Beams, Beams AFF, Depth of Beams Cure. Beams cy Reinforcing Reinforcing # of Columns, Length of # of Columns, Length of Includes Concrete Formwork, Placement, Column, Width of Column, Column, Width of Column Reinforcing, Strip Forms, Finish, and Cure. Columns cy Reinforcing, Finish # of Footings, Footing Width, # of Footings, Footing Width, # of Footings, Footing Width, Includes Concrete Formwork, Placement, Footing Length, Footing Footing Length, Footing Footing Length, Footing Reinforcing, Strip Forms, Finish, and Cure. Column Footings cy Thickness, Reinforcing Thickness, Reinforcing Thickness # of Footings, Footing Width, # of Footings, Footing Width, # of Footings, Footing Width, Includes Concrete Formwork, Placement, Footing Length, Footing Footing Length, Footing Footing Length, Footing Reinforcing, Strip Forms, Finish, and Cure. Continuous Footings cy Thickness, Reinforcing Thickness, Reinforcing Thickness # of Treads, Width of Stairs, # # of Treads, Width of Stairs, # # of Treads Includes Concrete Formwork, Placement, of Landings, Length of of Landings, Length of Reinforcing, Strip Forms, Finish, and Cure. Landings, Width of Landings, Landings, Width of Landings, Stairs cy Reinforcing Reinforcing # of Supports, Pipe Diameter, # of Supports, Pipe Diameter, # of Pipe Supports Includes Concrete Formwork, Placement, Support Type, Support Width, Support Type, Support Width, Reinforcing, Strip Forms, Finish, and Cure. Support Height, Support Support Height, Support Pipe Supports cy Length, Reinforcing Length, Reinforcing # of Equipment Pads, Pad # of Equipment Pads, Pad # of Equipment Pads Includes Concrete Formwork, Placement, Length , Pad Width, Pad Length , Pad Width, Pad Reinforcing, Strip Forms, Finish, Cure, and Thickness, Anchor Bolts (y/n), # Thickness, Anchor Bolts (y/n), # Anchor Bolts. of Anchor Bolts, Reinforcing of Anchor Bolts, Reinforcing Equipment Pads cy

6ATTACHMENT 2-1 DIVISION 3 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 3

PRECAST CONCRETE # of Panels, Area of Panels, # of Panels, Area of Panels, Area of Panels Includes Subcontractor Price to Furnish & Erect Wall Panels sf Thickness of Panels Thickness of Panels Precast Panels. # of Panels, Area of Panels, # of Panels, Area of Panels, Area of Panels Includes Subcontractor Price to Furnish & Erect Roof Tees sf Thickness of Panels Thickness of Panels Precast Panels. # of Panels, Area of Panels, # of Panels, Area of Panels, Area of Panels Includes Subcontractor Price to Furnish & Erect Thickness of Panels, Surface Thickness of Panels, Surface Precast Panels. Architectural Wall Panels sf Type Type

CONCRETE REHABILITATION LF of Joint Repair LF of Joint Repair LF of Joint Repair Includes Saw Cutting, Formwork, Placement, Joint Repair lf Finish, and Sealants. Type of Resurfacing, Area of Type of Resurfacing, Area of Area of Resurfacing Includes Milling, and Replacement of Concrete. Re-Surfacing sf Resurfacing Resurfacing

ATTACHMENT 2-1 DIVISION 3 JUNE 2008 7 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 4

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

MASONRY SUB Length, Width, size/thickness; Wall Area Structure Perimeter Includes scaffolding, layout, height; bond;openings;cmu block/mortar/rebar/grout, cleaning, sealer Concrete Block- CMU type;reinf;grout sf Length, Width, size/thickness; Wall Area Structure Perimeter Includes scaffolding, layout, height; bond;openings;brick block/mortar/rebar/grout, cleaning, sealer Brick Masonry type;reinf;grout sf Length, Width, Wall Area Structure Perimeter Includes scaffolding, layout, Special Masonry-Glass, Stone, size/thickness;height; matl/installation,cleaning, sealer Veneers openings;type matl;attachment sf

8ATTACHMENT 2-1 DIVISION 4 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 5

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

STRUCTURAL ERECTION Number levels, member Bldg Area, Bldg Height Area of Structure, # of Floors Includes detailing,fab/delivery, hoisting/erecting, Structural Steel Framing ton sizes/count, steel/conn types all conn's/welding, safety provisions

Count, Length, Member Count, Length Area of Structure Includes detailing,fab/delivery, hoisting/erecting, Joists lf size/count, mat'l/conn types, all conn's/welding, safety provisions finish Area, Material type/finish, Bldg Area Area of Structure Includes detailing,fab/delivery, hoisting/erecting, Deck sf openings, conn details welding, safety provisions MISCELLANEOUS METALS Length of Railing, Railing mat'l Length of Railing Area of Structure Includes detailing, fab/delivery, shop finishes, Handrail lf /type, conn's, finish installation Count,Mat'l type, height, conn's, Count Area of Structure Includes detailing, fab/delivery, shop finishes, Stairs & Ladders ea finish installation Area, Mat'l type, openings, Area Area of Structure Includes detailing, fab/delivery, shop finishes, Grating sf support/fastening, finish installation Area, Mat'l type, openings, Area Area of Structure Includes detailing, fab/delivery, shop finishes, Plate sf support/fastening, finish installation Length, Mat'l type/sizes, post Length Area of Structure Includes detailing, fab/delivery, shop finishes, Guard Rail lf spacing, anchorage installation Count, Mat'l type/sizes, finish Count Area of Structure Includes detailing, fab/delivery, shop finishes, Embedded Items ls installation Pipe Sleeves ea Count, Mat'l type/sizes Count Area of Structure Includes detailing, fab/delivery, installation Count, Bolt dia/length, mat'l Count Area of Structure Includes detailing, fab/delivery, installation Anchor Bolts set type, patterns if poss Length, Mat'l type/size, conn's Length Area of Structure Includes detailing,fab/delivery, hoisting/erection, Crane Rail lf conn's Area, Mat'l type, Area Area of Structure Includes detailing, fab/delivery, installation Aluminum Covers sf support/anchorage, special finish

ATTACHMENT 2-1 DIVISION 5 JUNE 2008 9 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 6

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

CARPENTRY Area, Mat'l sizes/types, location, Area Area of Structure Includes all labor, materials, fasteners, Rough ls fastening stock/scrap Area, Mat'l sizes/types, location, Area Area of Structure Includes all labor, materials, fasteners, Finish Carpentry ls fastening, prefinishes stock/scrap

Area, Mat'l sizes/types, quantity Area Area of Structure Includes all labor, materials incl tops, fasteners, Casework ls uppers/lowers, prefinishes stock/scrap

Area, Mat'l dimensions, Area Area of Structure Includes detailing fab/delivery, installation FRP Products (Weir plates) ls connection

10ATTACHMENT 2-1 DIVISION 6 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 7

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

WATERPROOFING/MOISTURE PROTECTION Area, Mat'l type, thickness Area Area of Structure Includes surface prep, application, protection Waterproofing/Moisture Protection sf

EXTERIOR INSULATION FINISH SYSTEM (EIFS) Area, Mat'l system type, Area, Mat'l system type, Area of Structure Includes integral color/finish, surface prep, EIFS sf thickness thickness application, protection FIREPROOFING Fireproofing sf Area, Mat'l type/hour rating Area Area of Structure Includes surface prep, application, patching ROOFING Area, Mat'l/system type, Area Area of Structure Includes safety,surface prep, hoisting, installation, Membrane Roofing sq substrate/ballast stock/scap,protection Area, Mat'l/system type, Area Area of Structure Includes safety,surface prep,hoisting, installation, Built-Up Roofing sq substrate/ballast stock/scap protection Area, Mat'l/system type, Area Area of Structure Includes safety,surface prep,hoisting, Bituminous Roofing sq substrate/ballast installation,stock/scrap, protection Shingle Roofing sq Area, Mat'l type, style Area Area of Structure Includes safety, installation, stock/scrap Tile Roofing sq Area, Mat'l type, style Area Area of Structure Includes safety, installation, stock/scrap METAL SIDING & ROOFING Area, Mat'l/ system type, Area Perimeter, Area of Structure Includes detailing, fab/delivery, shop finish, Metal Siding & Roofing sf support, openings hoisting, install, stock/scrap FLASHING & SHEET METAL Area, Mat'l type/sizes/profiles, Area Area of Structure Includes fab/deliver, shop finish, installation, Flashing & Sheet Metal sf attachment stock/scrap

ROOFING ACCESSORIES Count, Item sizes/types, Count Area of Structure Includes shop finishes, hoisting, installation, Roofing Accessories ls anchorage, finish stock, cleanup SEALANTS & CAULKING Length, Mat'l types, bead Length Area of Structure Includes surface prep, priming, application, Sealants & Caulking ls thicknesses protection/cleanup

ATTACHMENT 2-1 DIVISION 7 JUNE 2008 11 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 8

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

DOORS FRAMES & HARDWARE Count, Mat'l types, sizes, fire Count Area of Structure Includes setting/grouting frames, install/adjusting Doors & Hardware ea rating, special hdwre doors and hdwre OVERHEAD DOORS Count, Mat'l type/sizes, Count Area of Structure Includes inst rails, door, operator-framing/trims by Overhead Doors ea manual/electric, shop finishes others ALUMINUM ENTRANCES / STOREFRONTS Count, Mat'l type/sizes, Count Area of Structure Includes frame inst, doors, glazing, hdwre Aluminum Entrances & Storefronts ls manual/auto operators, hdwre WINDOWS Count, Mat'l type/sizes, conn's, Count Area of Structure Includes frame inst, hoisting-glazing usually Windows ea shop finishes separate GLASS & GLAZING Glass & Glazing sf Area, Mat'l type/sizes Area Area of Structure Includes glass inst, hoisting, cleanup

12ATTACHMENT 2-1 DIVISION 8 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 9

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

LATHE & PLASTER Area, Mat'l type/system, Area Area of Structure Includes scaffold, surface prep, application, Lathe & Plaster sy substrate, integral finish cleanup DRYWALL & METAL STUDS Area, Mat'l type,framing Area Area of Structure Includes layout, framing,backing, gwb, Drywall & Metal Studs sf height/spacing, firewalls stock/scrap-verify taping w/painting CERAMIC FLOOR & WALL TILE Area, Mat'l type, perimeter, Area Area of Structure Includes inst/mortar bed, grout, cleanup Ceramic Floor & Wall Tile sf thinset/thickset, special finishes

ACOUSTICAL CEILING Area, Mat'l type, grid/support Area Area of Structure Includes wires, grid, dropping tile, stock/scap Acoustical Ceiling sf type CARPET & RESILIENT FLOORS Area, Mat'l type/substrate, Area Area of Structure Includes minor surface prep, installation, Carpet & Resilient Floor sf special designs/layouts stock/scrap,cleanup/ first wax SEAMLESS FLOORS Area, Mat'l Area Area of Structure Includes minor surface prep/underlayment if Seamless Floors sf type/substrate,underlayment,sp spec'd, stock/scrap, cleanup ecial layout WOOD FLOORS Area, Mat'l type/substrate, Area Area of Structure Includes minor surface prep/underlayment if Wood Floors sf underlayment spec'd, stock/scrap, cleanup TERAZZO FLOORS Area, Mat'l type/finish, location Area Area of Structure Includes minor surface prep, inst, stock/scrap, Terazzo Floors sf quantities cleanup PROTECTIVE COATINGS Area, Mat'l type/thicknesses, Area Area of Structure Includes surface prep,application in/outside, Protective/Cementitious Coatings sf locations cleanup, touchup CEMENTITOUS COATINGS Area, Mat'l type/thicknesses, Area Area of Structure Includes surface prep,application in/outside, Cementitious Coatings sf locations cleanup, touchup PAINTING & VINYL WALL COVERINGS Area, Mat'l type/mil Area Area of Structure Includes surface prep, application in/outside, Painting & Vinyl Wall Coverings sf thicknesses, locations cleanup, touchup

ATTACHMENT 2-1 DIVISION 9 JUNE 2008 13 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 10

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

MISCELLANOUS SPECIALTIES Count, Mat'l type/sizes, conn's Count Area of Structure Includes mat'l, installation Marker / Tack Boards ea Area, Mat'l type/sizes, conn's, Area Area of Structure Includes detailing/fab/delivery, hoisting, inst, shop Architectural Louvers sf shop finishes finishes,sealant Count, Mat'l type, size, base Count Area of Structure Includes mat'l, hoisting, installation-verify Flag Poles ea reqm't conc/steel base elsewhere Count, Mat'l type/sizes, lighting Count Area of Structure Includes detailing/fab/delivery, hoisting, conn's, Signage ls in exterior units installation Count, Mat'l type/rating, Count Area of Structure Includes cabinet/mounting bracket installation Fire Protection Specialties ls cabinet/mounting reqm'ts Count, Mat'l type/sizes, shop Count Area of Structure Includes assembly installation and connection to Shelving ls finishes, conn's substrate Count, Mat'l type/sizes/finishes, Count Area of Structure Includes inventory/stocking, installation/anchoring, Toilet & Bath Accessories ls anchoring, schedule cleanup

TOILET PARTITONS Count, Mat'l type/size/finishes, Count Area of Structure Includes layout, installation, shop finishes, Toilet Partitions ls anchoring cleanup ACCESS FLOORING Area, Mat'l Area Area of Structure Includes minor substrate prep, support Access Flooring sf type/size/finish,support grid/grounding, floor inst structure,grounding LOCKERS Count, Mat'l Count Area of Structure Includes installation, anchoring, cleanup Lockers ea type/size/support/conn's, shop finish PARTITIONS Area, Mat'l size/types,support, Count Area of Structure Includes support tracks, installation, operators, Operable Partitions sf manual/auto operation cleanup

Area, Mat'l Count Area of Structure Includes, installation, hdwre,cleanup Wire Mesh Partitions sf size/types,support/conn's, shop finish

14ATTACHMENT 2-1 DIVISION 10 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 12

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

WINDOW TREATMENT Area of Structure Drapes sf Area, Mat'l type/sizes, support Count Includes hdwre, installation, cleanup Area of Structure Blinds sf Area, Mat'l type/sizes, support Count Includes hdwre, installation, cleanup PROJECTION SCREENS Count, Mat'l type/sizes, support, Area of Structure Projection Screens ea Count Includes mounting hdwre, auto operator manual/motor oper LABORATORY CASEWORK Count, Mat'l type/sizes, quantity Area of Structure Includes installation/adjutment, stock/scrap, Laboratory Casework ls Count uppers/lowers, finish cleanup FURNITURE Count, Mat'l type/sizes, special Area of Structure Interior Plants & Planters ls Count Includes planter/plant materials items Area, Mat'l type/sizes, frame Area of Structure Entry Mats sf Count Includes installation of frame and mats support

ATTACHMENT 2-1 DIVISION 12 JUNE 2008 15 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 15

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

PLUMBING FIXTURES Qty, fixture type, pipe material, pipe length, pipe diameter, # of Qty, fixture type, Pipe Length, Assembly includes providing and installing pipe, Water Closets ea Qty. elbow, tees, caps, traps, Valve ftg density. fittings, and plumbing fixtures. Type, Valve Qty.

Qty, fixture type, pipe material, pipe length, pipe diameter, # of Qty, fixture type, Pipe Length, Assembly includes providing and installing pipe, Urinals ea Qty. elbow, tees, caps, traps, Valve ftg density. fittings, and plumbing fixtures. Type, Valve Qty. Qty, lavatory type, lavatory Qty, lavatory type, lavatory Assembly includes providing and installing pipe, Lavatories ea Qty. material. material. fittings, and plumbing fixtures. Qty, sink type, sink material, pipe material, pipe length, pipe Qty, sink type, sink material, Assembly includes providing and installing pipe, Sinks ea diameter, # of elbow, tees, Qty. Pipe Length, ftg density. fittings, and plumbing fixtures. caps, traps, Valve Type, Valve Qty. Qty, shower/tub type, material, pipe material, pipe length, pipe Qty, shower/tub type, material, Assembly includes providing and installing pipe, Showers/tubs ea diameter, # of elbow, tees, Qty. Pipe Length, ftg density. fittings, and plumbing fixtures. caps, traps, Valve Type, Valve Qty. Qty, fountain type, pipe material, pipe length, pipe Qty, fountain type, Pipe Length, Assembly includes providing and installing pipe, Drinking Fountains and Coolers ea diameter, # of elbow, tees, Qty. ftg density. fittings, and plumbing fixtures. caps, traps, Valve Type, Valve Qty. Qty, fixture type, pipe material, pipe length, pipe diameter, # of Qty, fixture type, Pipe Length, Assembly includes providing and installing pipe, Bidets ea Qty. elbow, tees, caps, traps, Valve ftg density. fittings, and plumbing fixtures. Type, Valve Qty.

Qty, fixture type, pipe material, pipe length, pipe diameter, # of Qty, fixture type, Pipe Length, Assembly includes providing and installing pipe, Emergency Fixtures ea Qty. elbow, tees, caps, traps, Valve ftg density. fittings, and plumbing fixtures. Type, Valve Qty.

16ATTACHMENT 2-1 DIVISION 15 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 15

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

DOMESTIC WATER DISTRIBUTION Assemblies include all pipe, fittings, and Pipe Material, Diameter, # of Pipe Material, Diameter, ftg associated work with regard to domestic water Pipes & Fittings ea elbows, tees, caps, pipe length, density, pipe length, hanger Pipe length, diameter, material. supply. The unit of measure at the assembly level hanger type/spacing type/spacing is number of fixtures. Assemblies include all valves and hydrants. Hose Valve Qty, material, size, and Valve Qty, size, and type. Valve size & qty. Hydrant size bibbs are included in this assembly. The unit of Valves & Hydrants ea type. Hydrant Qty, material, Hydrant Qty, size, and type. & qty. measure at the assembly level is number of size, and type. valves and hydrants. This assembly includes equipment associated with the domestic water supply, including fittings, Water heater size, water and specialties required for hookup. Assemblies sofener size, filter qty, filter Water heater size, water include hot water heaters, water treatment plant, Qty of domestic water Domestic Water Equipment ea size, water supply pump size, sofener size, filter qty, water i.e., water softeners, filters, distillers, etc.; pumps equipment items. water supply pump type, tank supply pump size, tank size. directly associated with domestic water supply; size, tank type. and tanks for the potable hot or cold water system. The unit of measure at the assembly level is pieces of equipment.

Assemblies include insulation used in association Pipe length, diameter, insulation Insulation and Identification ea Pipe length, diameter Pipe length with domestic water supply. The unit of measure type, sign type. at the assembly level is number of fixtures. Any other special items associated with domestic water supply. All associated work items, including pipes, fittings, valves, insulation, and hookup Specialties ea Specialty qty, size, type. Specialty qty, size, type. Specialty qty, size, type. should be included in this assembly. The unit of measure at the assembly level is pieces of special equipment. Other Domestic Water Supply ea

ATTACHMENT 2-1 DIVISION 15 JUNE 2008 17 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 15

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

SANITARY WASTE Pipe Material, Diameter, # of Assemblies include all pipe, fittings, and Pipe Material, Diameter, fitting bends, tees, caps, pipe length, associated work with regard to sanitary waste Waste Pipe & Fittings lf density, pipe length, trench Pipe length, diameter, material. trench depth, bedding depth, pipe and fittings. The unit of measure at the depth surface type. assembly level is number of fixtures. Assemblies include all pipe, fittings, and Pipe Material, Diameter, # of Pipe Material, Diameter, fitting associated work with regard to sanitary vent pipe Vent Pipe & Fittings lf bends, tees, caps, pipe length, Pipe length density, pipe length and fittings. The unit of measure at the assembly hanger type, hanger spacing. level is number of fixtures. Assemblies include all floor drains. Hub drains Pipe Material, Diameter, # of Pipe Material, Diameter, fitting are considered to be pipe and are not included in Floor Drains lf Pipe length bends, tees, caps, pipe length. density, pipe length. this category. The unit of measure at the assembly level is number of drains. This is equipment associated with the sanitary waste system, including fittings and specialties required for hook-up. Assemblies include waste Pipe Material, Diameter, # of Pipe Material, Diameter, fitting treatment equipment, i.e., sluice gates, Sanitary Vent and Equipment ea bends, tees, caps, pipe length, Pipe length density, pipe length incinerators, etc.; pumps for sewage injection; hanger type, hanger spacing. and holding tanks for the domestic water system. The unit of measure at the assembly level is pieces of equipment. Assemblies include insulation used in association Pipe length, diameter, insulation with sanitary waste and vent system. The unit of Insulation and Identification lf Pipe length, diameter Pipe length type, sign type. measure at the assembly level is number of fixtures. Sanitary waste and vent not described by the Other Sanitary Waste ea assembly categories listed above. RAIN WATER DRAINAGE Pipe Material, Diameter, # of Assemblies include pipe and fittings from the roof Pipe Material, Diameter, fitting Pipe & Fittings lf bends, tees, caps, pipe length, Pipe length drains to the discharge points, including supports density, pipe length hanger type, hanger spacing. and other associated work.

Pipe Material, Diameter, # of Assemblies include roof drains. The unit of Pipe Material, Diameter, fitting Roof Drains ea bends, tees, caps, pipe length, Pipe length measure at the assembly level is number of density, pipe length hanger type, hanger spacing. drains. This is equipment associated with the rain water drainage, including fittings and specialties Rain water supply pump size, Rainwater Drainage Equipment ea Rain water supply pump size. Rain water supply pump size. required for hook-up. Assemblies include pumps rain water supply pump type. and other associated items for drainage of rain water. Pipe length, diameter, insulation Assemblies include insulation used in association Insulation and Identification lf Pipe length, diameter Pipe length type, sign type. with rain water drainage system. Rain water drainage system not described by the Other Rainwater Drainage ea assembly categories

18ATTACHMENT 2-1 DIVISION 15 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 15

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

OTHER PLUMBING SYSTEMS Assemblies include all special pipe and fittings, excluding acid waste pipe and work with regard to Pipe Material, Diameter, # of special pipe. Medical gas and vacuum fittings, Pipe Material, Diameter, fitting Special Piping Systems ea bends, tees, caps, pipe length, Pipe length and associated systems piping are included in density, pipe length hanger type, hanger spacing. this category. The unit of measure at the assembly level is the number of special fixtures, interceptors, outlets, or systems. Pipe Material, Diameter, # of Assemblies include all pipe, fittings, special acid bends, tees, caps, pipe length, Pipe Material, Diameter, fitting waste equipment, and other associated work hanger type, hanger spacing, Acid Waste Systems ea density, pipe length, specialy Pipe length items with regard to acid waste systems. The unit special fixture qty, special qty. of measure at the assembly level is the number of fixture type, interceptor qty, special fixtures, interceptors, outlets, or systems. outlet qty. Assemblies include all interceptors. The unit of Interceptors ea Interceptor qty, interceptor size Interceptor qty Interceptor qty measure at the assembly level is number of interceptors. Pipe Material, Diameter, # of Pipe Material, Diameter, # of Assemblies include pumps and associated bends, tees, caps, pipe length, bends, tees, caps, pipe length, Pipe Length, equipment equipment with pools, including specialties Pool Piping & Equipment gpm trench depth, bedding depth, surface type, pump size, allowance. required for hook-up. The unit of measure at the surface type, pump type, pump vacuum system size. assembly level is each. size, vacuum system size.

Pipe Material, Diameter, # of Compressted Air System (Non- Pipe Material, Diameter, fitting psi bends, tees, caps, pipe length, Pipe length Breathing) density, pipe length hanger type, hanger spacing.

Pipe Material, Diameter, # of This system includes special plumbing systems Pipe Material, Diameter, fitting bends, tees, caps, pipe length, not described by the assembly categories listed Other Plumbing Systems ea density, pipe length, device Pipe length, device qty hanger type, hanger spacing, above, such as fountain piping systems and type, device qty. device type, device qty. devices.

ATTACHMENT 2-1 DIVISION 15 JUNE 2008 19 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 15

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

ENERGY SUPPLY Pipe Material, Diameter, # of bends, tees, caps, pipe length, Pipe Material, Diameter, fitting Assemblies include storage equipment, transfer Pipe length, tank size, pump Oil Supply System mbh hanger type, hanger spacing, density, pipe length, tank type, equipment, and distribution piping. The unit of size. tank type, tank size, pump size, tank size, pump size. measure at the assembly level is each system. pump type. Pipe Material, Diameter, # of This category includes both natural gas and LPG. Pipe Material, Diameter, ftg bends, tees, caps, pipe length, Assemblies include metering and regulation density, pipe length, tank type, Pipe length, tank size, pump Gas Supply System mbh hanger type, hanger spacing, equipment, storage equipment, transfer tank size, regulator type, pump size. tank type, tank size, regulator equipment, and distribution piping. The unit of size. type, pump size, pump type. measure at the assembly level is each system. This category includes storage equipment, Conveyor length, hopper size, Conveyor length, hopper size, Conveyor length, equipment transfer equipment, processing equipment, and Coal Supply System mbh scale type scale type allowance distribution piping. The unit of measure at the assembly level is each system. Assemblies include meters, valves, heat Pipe Material, Diameter, # of Pipe Material, Diameter, fitting exchangers, fittings, and specialties required for Steam supply system (from central bends, tees, caps, pipe length, mbh density, pipe length, device Pipe length, device qty hook-up and distribution piping, including plant) hanger type, hanger spacing, type, device qty. supports, sleeves, and insulation. The unit of device type, device qty. measure at the assembly level is each system.

Assemblies include meters, valves, heat Pipe Material, Diameter, # of Pipe Material, Diameter, fitting exchangers, fittings, and specialties required for Hot Water Supply System (from bends, tees, caps, pipe length, mbh density, pipe length, device Pipe length, device qty hook-up and distribution piping, including central plant) hanger type, hanger spacing, type, device qty. supports, sleeves, and insulation. The unit of device type, device qty. measure at the assembly level is each system.

Pipe Material, Diameter, # of bends, tees, caps, pipe length, Pipe Material, Diameter, ftg Assemblies include collector panels, heat hanger type, hanger spacing, density, pipe length, tank size, Pipe Length, equipment exchangers, storage tanks, pumps, etc., including Solar Energy Supply Systems mbh tank type, tank size, pump size, pump size, pump type, heat allowance. pipe and fittings required for hookup. The unit of pump type, heat exchanger exchanger size, collector panel measure at the assembly level is each system. size, collector panel size, size, collector panel qty. collector panel qty.

Wind is used to turn a generator which generates Windmill size, Windmill height, electricity. This energy is either stored in a battery Windmill size, Windmill height, Foundation depth, boiler size, or used to generate hot water in an electric boiler. Foundation depth, boiler size, Pipe Length, equipment Wind Energy Supply System mbh pipe length, # of bends, tees, Assemblies would include the required devices to pipe length, ftg density, battery allowance. caps, insulation type, battery make this a total electromechanical system. The size, battery qty. size, battery qty. unit of measure at the assembly level is each system. Other Energy Supply xx

20ATTACHMENT 2-1 DIVISION 15 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 15

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

HEAT GENERATING SYSTEMS Boiler Size, Boiler Fuel Type, Assemblies include boilers, expansion tanks, Expansion Tank Size, Heat Boiler Size, Boiler Fuel Type, chemical feeders, air separators, pumps, heat Exchanger Size, Heat Expansion Tank Size, Heat exchangers, boiler feed units, etc. This assembly Steam Boilers mbh Exchanger Type, Steam Piping Boiler Size Exchanger Size, Steam Piping would also include fittings and specialties and the Length, Dia, # of Elbows, Tees, Length, Dia, ftg density. flue stack. The unit of measure at the assembly Valves, Valve Type, Expansion level is each system. Joints, Insulation type. Boiler Size, Boiler Fuel Type, Assemblies include boilers, expansion tanks, Expansion Tank Size, Heat Boiler Size, Boiler Fuel Type, chemical feeders, air separators, pumps, heat Exchanger Size, Heat Expansion Tank Size, Heat exchangers, boiler feed units, etc. This assembly Hot Water Boilers mbh Exchanger Type, Steam Piping Boiler Size Exchanger Size, Steam Piping would also include fittings and specialties and the Length, Dia, # of Elbows, Tees, Length, Dia, ftg density. flue stack. The unit of measure at the assembly Valves, Valve Type, Expansion level is each system. Joints. Furnace Size, Furnace Type, This is a system that heats air. Assemblies would Furnace Size, Furnace Type, Fuel Type, Fuel Piping Length, include furnace and necessary fittings and Fuel Type, Fuel Piping Length, Furnaces mbh diameter, # of elbow, tees, caps Furnace Size. specialties required for hookup, including flue and diameter, transition density, Duct size, Duct Length, Hanger stack. The unit of measure at the assembly level Duct size, Duct Length. Spacing. is each. Assemblies would include unit heaters and the Heater Size, heater Type, Fuel energy supply system hookup (other than Heater Size, heater Type, Fuel Type, Fuel Piping Length, electrical), including all necessary pipe, fittings, Type, Fuel Piping Length, Fuel-Fired Unit Heaters mbh diameter, # of elbow, tees, Heater Size. and specialties required for hook-up. Flue and diameter, transition density, caps, Duct size, Duct Length, stack, if required, are included in this assembly. Duct size, Duct Length. Hanger Spacing. The unit of measure at the assembly level is each. Auxiliary Equipment Type, Size, Auxiliary Equipment Type, Size, Assemblies would include any other equipment Auxiliary Equipment mbh Piping Length, diameter, # of Piping Length, diameter,ftg Auxiliary Equipment Allowance associated with heat generating systems. The elbow, tees, cap density unit of measure at the assembly level is each. Insulation Type, Insulation R- Assemblies would include insulation of any Equipment Thermal Insulation sf Value, Insulation Location, Insulation Type, Insulation Qty Insulation Qty component in this subsystem. The unit of Insulation Qty measure at the assembly level is each. Other Heat Generating Systems xx

ATTACHMENT 2-1 DIVISION 15 JUNE 2008 21 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 15

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

COOLING GENERATING SYSTEMS Condenser Size, Condenser Type, Compressor Size, Condensor Size, , Compressor Assemblies include condensers, compressors, Compressor Type, Pump Size, Size, Compressor Type, Pump chillers, pumps, cooling towers, etc., including Chilled Water Systems ton Pump Type, Cooling Tower Size, Cooling Tower Size, Equipment Allowance fittings and specialties required for hook-up. The Size, Cooling Tower Type, Cooling, Piping Length, ftg unit of measure at the assembly level is each. Piping Length, diameter, # of density elbow, tees, caps Condenser Size, Condenser Type, Compressor Size, Compressor Type, Heat Pump Condenser Size, Compressor Assemblies include condensers, compressors, Size, Heat Pump Type, Size, Heat Pump Size, Direct Expansion Systems ton Equipment Allowance heat pumps, and refrigerant piping. The unit of Refrigerant Pump Size, Refrigerant Pump Size, Piping measure at the assembly level is each. Refrigerant Pump Type, Piping Length, diameter, ftg density Length, diameter, # of elbow, tees, caps Other Cooling Generating Systems xx

22ATTACHMENT 2-1 DIVISION 15 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 15

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

DISTRIBUTION SYSTEMS Heating Coil Size, Cooling Coil Assemblies include heating coils, cooling coils, Size, Heating/Cooling Water and fittings and specialties required for water Piping Length, dia, # of elbow, Heating Coil Size, Cooling Coil hook-up. This assembly also includes duct tees, caps, Duct Heater qty, Size, Heating/Cooling Water heaters, filters, humidifiers, supply and return Duct Heater size, Humidifier Piping Length, dia,ftg density, Air Distribution, Heating & Cooling cf/m Bldg Area ductwork, dampers, fire dampers, supply and Size, Duct Length, Duct Size, Duct Heater qty, Humidifier return grilles, registers and diffusers, turning Damper Qty, Fire Damper Qty, Size, Duct Length, Duct Size, vanes, sound traps, and all associated insulation. Grill Qty, Diffuser Qty, Register Device Count, Insulation Area. The unit of measure at the assembly level is Qty, Turning Vane Qty, CF/M. Insulation Type, Insulation Area. Pipe length, diameter, insulation Assemblies include pipe and fittings, supports, Pipe Length, diameter, ftg Steam Distribution Systems mbh type, # of elbows, tees, caps, Bldg Area wall and floor sleeves, and pipe insulation. The density. sleeves. unit of measure at the assembly level is MBH. Pipe length, diameter, insulation Assemblies include pipe and fittings, supports, Pipe Length, diameter, ftg Hot Water Distribution Systems mbh type, # of elbows, tees, caps, Bldg Area wall and floor sleeves, and pipe insulation. The density. sleeves. unit of measure at the assembly level is MBH. Change Over Distribution Systems mbh Pipe length, diameter, insulation Assemblies include pipe and fittings, supports, Pipe Length, diameter, ftg Glycol Distribution Systems mbh type, # of elbows, tees, caps, Bldg Area wall and floor sleeves, and pipe insulation. The density. sleeves. unit of measure at the assembly level is MBH. Pipe length, diameter, insulation Assemblies include pipe and fittings, supports, Pipe Length, diameter, ftg Chilled Water Distribution Systems ton type, # of elbows, tees, caps, Bldg Area wall and floor sleeves, and pipe insulation. The density. sleeves. unit of measure at the assembly level is tons. Duct Length, Duct Material, Assemblies include ductwork grilles, registers, Duct Size, # of bends, tees, Duct Length, Duct Material, Ftg Exhaust Systems cf/m Bldg Area diffusers, fans, and all associated work. The unit caps, sleeves, Fan Type, Fan Density of measure at the assembly level is each system. Qty, Grille qty, Register Qty Air Handling Unit Size, Air Handling Unit Type, Duct Air Handling Unit Size, Air Assemblies include AHU, ductwork grilles, Length, Duct Material, Duct Handling Unit Type, Duct registers, diffusers, fans, and all associated work. Air Handling Units cf/m Bldg Area Size, # of bends, tees, caps, Length, Duct Size, ftg density, The unit of measure at the assembly level is each sleeves, Fan Type, Fan Qty, Fan Qty, Grille qty, Register Qty system. Grille qty, Register Qty Other Distribution Systems xx

ATTACHMENT 2-1 DIVISION 15 JUNE 2008 23 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 15

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

TERMINAL & PACKAGE UNITS Unit Size, Unit Type, Unit Qty, pipe length, pipe material, # of Unit Size, Unit Type, Unit Qty, Assemblies include the complete terminal unit and Unit Ventilators ea Bldg Area elbows, tees, caps, valves, pipe length, ftg density wall sleeve with all controls. insulation length.

Unit Size, Unit Type, Unit Qty, pipe length, pipe material, # of Unit Size, Unit Type, Unit Qty, Assemblies include the complete terminal unit and Unit Heaters ea Bldg Area elbows, tees, caps, valves, pipe length, ftg density wall sleeve with all controls. insulation length.

Unit Size, Unit Type, Unit Qty, pipe length, pipe material, # of Unit Size, Unit Type, Unit Qty, Assemblies include the complete terminal unit and Fan Coil Units ea Bldg Area elbows, tees, caps, valves, pipe length, ftg density wall sleeve with all controls. insulation length.

Unit Size, Unit Type, Unit Qty, pipe length, pipe material, # of Unit Size, Unit Type, Unit Qty, Assemblies include the complete terminal unit and Fin Tube Radiation ea Bldg Area elbows, tees, caps, valves, pipe length, ftg density wall sleeve with all controls. insulation length. Assemblies include the complete terminal unit and Electric Heating ea Unit Size, Unit Type, Unit Qty Count Bldg Area wall sleeve with all controls. CONTROLS & INSTRUMENTATION Thermostat Type, Thermostat Includes devices such as thermostats, timers, Qty, Sensor Type, Sensor Qty, Thermostat Qty, Sensor Qty, sensors, control valves, etc., necessary to HVAC Controls ea Equipment Allowance Control Valve Type, Control Control Valve Qty operate the total system. The unit of measure at Valve Qty. the assembly level is each system. Electronic Controls ea Valve Qty, Valve Size, Valve Type, High Pressure Choke Valve Qty, High Pressure Assemblies includes ball and butterfly valves, Pneumatic Controls ea Qty, High Pressure Choke Size, Choke Qty, Sensor Qty, Equipment Allowance actuators, high pressure chokes, valve Sensor Qty, Sensor Type, Regulator Qty positioners, sensors, regulators, etc. Regulator Qty, Regulator Size.

Air Compressor Size, Air Air Compressor Size, Air Compressor Type, Air Compressor Type, Air Assemblies include air compressors, dryers, and Compressor Qty, Compressed Air Compressor Size, Air Compressor Qty, Compressed distribution tubing, (only used with pneumatic Instrument Air Compressors ea Air Piping Size, Compressed Compressor Type, Air Air Piping Size, Compressed control systems). The unit of measure at the Air Piping Material, dia, # of Compressor Qty Air Piping Material, dia, ftg assembly level is each. elbows, tees, caps, connections density. to instruments. Fan Qty, Fan Size, Fan Type, Fan Qty, Fan Size, Duct Duct Length, Duct Size, Duct Assemblies include the removal of contaminated Gas Purging Systems ea Length, Duct Size, Duct Equipment and Duct Allowance Material, # of Duct Bends and or unwanted gases from a structure or pipe. Material, ftg density Transitions, caps, sleeves. Controls and instrumentation not described by the Other Controls Instrumentation ea assembly categories listed above.

24ATTACHMENT 2-1 DIVISION 15 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 15

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

SYSTEMS TESTING & BALANCING Includes operating and testing of pumps, setting of all control valves, and determining system Water Side Testing & Balancing - # of Units to be tested, Type of ea # of Units to be Tested Testing Allowance capacity. The unit of measure at the assembly Heating & Cooling Units to be tested. level is each device, i.e., boiler, chiller, fan coil,and unit heater. Includes operating and testing of all air handling devices, adjusting of all fans to set rate of air flow, setting all fan motorsat desired operation, setting Air Side Testing & Balancing - # of Units to be tested, Type of of air flow at all registers, grilles, diffusers, and ea # of Units to be Tested Testing Allowance Heating, Cooling & Exhaust Units to be tested. louvers to deliver design CFM, and testing and calibrating of thermostats to achieve desired space temperature. The unit of measure at the assembly level is each device. # of Units to be tested, Type of HVAC Commissioning ls # of Units to be Tested Testing Allowance Final testing of operational system. Units to be tested. Other Systems Testing & # of Units to be tested, Type of Systems testing and balancing not described by ea # of Units to be Tested Testing Allowance Balancing Units to be tested. the assembly categories listed above. OTHER HVAC SYSTEMS AND EQUIPMENT Includes construction work other than mechanical Labor hours, Equipment Hours, which must be performed in conjunction with the General Construction Items sf Crew hours Allowance Material Cost. special mechanical system to make the system complete. Condenser Size, Condenser Type, Compressor Size, Includes equipment for refrigeration in a cold Compressor Type, Evaporative storage facility. Both low and medium Condenser Size, Compressor Blower Size, Evaporative temperature equipment are included. Assemblies Size, Evaporative Blower Size,, Blower Type, Heat Recovery Equipment Allowance, Piping include: condensing and compressor units, Refrigeration Systems ton Heat Recovery System Size, , System Size, Heat Recovery Allowance evaporator blowers, refrigerant piping, and Piping Length, Piping Material, System Type, Piping Length, specialties, heat recovery systems (liquid or gas), Piping Dia, ftg density. Piping Material, Piping Dia, # of heat recovery distribution systems (liquid or gas), elbow, tees, caps, Insulation and system testing and balancing. Length, Insulation Type. Any other mechanical system not defined in other categories. Assemblies would include special Labor hours, Equipment Hours, Other Special Mechanical Systems ea Crew hours Allowance systems and special devices. The unit of Material Cost. measure at the assembly level is each system or device. SPRINKLERS The fixture, device, or sprinkler head that Sprinkler Head Type, Sprinkler releases the water to suppress the fire. The unit Sprinklers And Releasing Devices ea Sprinkler Head Qty Building Area Head Qty of measure at the assembly level is each sprinkler head. Assemblies include alarm valves, flow control valves, pipe and fittings from equipment to Sprinkler System Type, Sprinkler System Type, sprinkler heads, including all supports and wall or Manifold Piping Dia, Piping Sprinkler Water Supply Equipment Manifold Piping Dia, Piping floor sleeves. All equipment including tanks, ea Material, Piping Length, # of Building Area And Piping Material, Piping Length, ftg pumps, and other associated equipment, fittings, elbows, tees, caps, couplings, density, Valve Qty and specialties required for hook-up are in this Valve Qty, Valve Type. assembly. The unit of measure at the assembly level is each sprinkler head.

ATTACHMENT 2-1 DIVISION 15 JUNE 2008 25 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 15

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

STANDPIPE SYSTEMS Assemblies include standpipe risers and all other Piping Dia, Piping Material, piping, fittings, and supports associated with this Piping Length, # of elbows, Piping Dia, Piping Material, category. Siamese connections, roof manifolds, tees, caps, couplings, Valve Piping Length, ftg density, cabinets, hoses, racks, and other fire department Standpipe Equipment & Piping ea Building Area Qty, Valve Type, Roof Manifold Valve Qty, Valve Type, connections are included in this assembly. All Qty, Cabinet Qty, Cabinet Size, Accessories Qty equipment including pumps, tanks, etc., with all Cabinet Type, Hose Rack Qty. required fittings and specialties for hook-up are included in this assembly. FIRE PROTECTION SPECIALTIES Assemblies include all types of fire extinguishers, Extinguisher Type, Extinguisher i.e., water, dry chemical, carbon dioxide, soda Fire Extinguishing Devices ea Size, Extinguisher Qty, Extinguisher Qty Building Area acid, etc. The brackets, sleeves, and supporting Extinguisher Cabinet Type. devices are included in this assembly.

OTHER FIRE PROTECTION SYSTEMS Carbon Dioxide Systems ea Carbon Dioxide System Size Carbon Dioxide System Size Building Area Foam Fire Suppression System Foam Fire Suppression System Foam Generating Equipment ea Building Area Size Size Clean Agent Systems ea Clean Agent System Size Clean Agent System Size Building Area Hood & Duct Fire Protection Hood & Duct Fire Protection Hood & Duct Fire Protection ea Building Area System Size System Size Assemblies includes other fire protection systems Other Special Fire Protection Special Fire System Type, Special Fire System Type, ea Building Area such as halon systems, exhaust hood systems, Systems Special Fire System Size Special Fire System Size and special chemical suppression systems.

26ATTACHMENT 2-1 DIVISION 15 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 16

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

ELECTRICAL SERVICE & DISTRIBUTION Duct bank Layout, Pad Overhead or underground transformers used or requirements, Conduit feeder Conduit feeder and wire size, primary electrical service. Assemblies include Location of equipment, size of Main Transformers KVA and wire size, Location of Location of equipment, size of transformers, pad, trenching, and backfill. Transformers equipment, size of Transformers Transformers Duct bank Layout, Pad Transformers fed from protection equipment on Conduit feeder and wire sizes, requirements, Conduit feeder Location of equipment, size of the building side of primary transformer. Secondary KVA Location of equipment, size of and wire size, Location of Equipment Assemblies include transformers, conduit, conduit equipment equipment, size of Equipment support, and wire. Elevation drawing, Breaker size This includes the protection equipment and Conduit feeder and wire sizes, and layout, Conduit feeder and Single one line drawing, metering devices for main distribution. Single one line drawing, Main Switchboards KVA wire sizes, Single one line Location of equipment, size of Assemblies include main distribution panel, Location of equipment, size of drawing, Location of equipment, Equipment breaker, fuses, and meters. equipment size of equipment Single one line drawing, This includes the interior step-down or back boost Conduit feeder and wire sizes, Conduit feeder and wire sizes, Location of equipment, size of transformers. Interior Distribution Transformers KVA Location of equipment, size of Location of equipment, size of Equipment equipment equipment Branch circuit panelboards. Assemblies include Breaker size and layout, Conduit feeder and wire sizes, Single one line drawing, panelboards, breakers ,conduit, and wire. Conduit feeder and wire sizes, Panels AMP Location of panels, size of Location of panels, size of Panel Schedule, Location of panels Panel panels, size of panels Breaker size and layout, Conduit feeder and wire sizes, Over-current protection device enclosed in its Location of equipment, size of Enclosed Circuit Breakers AMP Conduit feeder and wire sizes, Location of equipment, size of own housing. Assemblies include enclosed circuit breaker Location of equipment breaker breaker, conduit, and wire. Elevation drawing, MCC This is a cabinet in which motor starters and Buckets size and layout, Conduit feeder and wire sizes, operation devices are contained. Assemblies Single one line drawing, Conduit feeder and wire sizes, Single one line drawing, include the motor control center cabinet, motor Motor Control Centers AMP Location of equipment, size of Single one line drawing, Location of equipment, size of starters, contacts, switches, conduit, wire, and all Equipment Location of equipment, size of equipment associated items. equipment Elevation drawing, Conduit Conduit feeder and wire sizes, Service and distribution not described by the feeder and wire sizes, Single Single one line drawing, Location of equipment, size of assembly categories listed above. Other Service And Distribution XX one line drawing, Location of Location of equipment, size of Equipment equipment, size of equipment equipment LIGHTING & BRANCH WIRING Fixture description, Fixture Fixture description, Reflective This assembly includes fixtures, conduit, wire, Lighting requirements, Size of location, receptacle location, ceiling plan, Lighting and switching devices. Lighting Equipment SF area requiring lighting and switch location, Classification of requirements, Classification of power, Classification of area area, and circuitry area Lighting and general power This assembly includes switches, receptacles, Device description, Device Device description, Device requirements, Size of area equipment connections, conduit, and wire. Other Lighting And Branch Wiring SF location, Classification of area, location, Classification of area requiring lighting, Classification and circuitry required of area Classification of emergency This assembly includes fixtures, conduit, wire, Conduit and Cable Location of areas requiring lighting system, Conduit and and switching devices for an emergency lighting requirements, fixture and emergency lighting systems, Emergency Lighting & Power XX Cable requirements, fixture and power system. device location, Classification of Size of area, Classification of and device location, area, area Classification of area,

ATTACHMENT 2-1 DIVISION 16 JUNE 2008 27 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 16

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

COMMUNICATIONS & SECURITY Assemblies include wire, conduit, conduit support Classification of Fire alarm or fastening systems, fire alarm devices, fire system, ladder diagram, panel Conduit and cable Fire Alarm requirements, Size detection devices, panels, safety switches, all Fire Alarm Systems EA size, Conduit and cable requirements, Fire alarm device of area requiring Fire Alarm, electrical connections, and other associated requirements, Fire alarm device location, Classification of area, Classification of area items. location, Classification of area, Assemblies include wire, conduit, conduit support Classification of Nurse call or fastening systems, Nurse call devices, Panels, system, ladder diagram, Conduit and Cable Location of areas requiring safety switches, all electrical connections, and Nurse Call Systems EA Conduit and Cable requirements, Nurse call device Nurse Call, Size of area, other associated items. requirements, Nurse call device location, Classification of area, Classification of area location, Classification of area, Classification of Public address Assemblies include wire, conduit, speakers, system, ladder diagram, Conduit and Cable monitoring devices, amplifiers, switches, power Location of areas requiring Conduit and Cable requirements, Public address system tie-in devices, and detection devices. Public Address Systems EA Public address, Size of area, requirements, Public address device location, Classification of Classification of area device location, Classification of area, area, This system would include central switchboards, Classification of telephone sets, underground ducts, and Intercommunication system, Conduit and Cable Location of areas requiring an manholes. Assemblies include wire, conduit, ladder diagram, Conduit and requirements, Intercommunication System, Intercommunications Systems EA backboards, cabinets, outlets, and power supply Cable requirements, Intercommunication device Size of area, Classification of connections. Intercommunication device location, Classification of area, area location, Classification of area, Assemblies include wire, conduit, power systems Classification of Clock system, Location of areas requiring tie-in, safety switches, control panels, battery ladder diagram, Conduit and Conduit and Cable Clock and Program system, back-up devices, clocks and outlets. Clock & Program Systems SF Cable requirements, Clock requirements, Clock device Size of area, Classification of device location, Classification of location, Classification of area, area area, Assemblies include wire, conduit, grounding Classification of television amplifiers, receivers, video equipment, and system, ladder diagram, Conduit and Cable Location of areas requiring outlets grouped according to use. Television Systems SF Conduit and Cable requirements, television device Television system, Size of area, requirements, television device location, Classification of area, Classification of area location, Classification of area, Classification of security Assemblies include wire, conduit, conduit support system, ladder diagram, Conduit and Cable or fastening systems, security alarm devices, all Location of areas requiring Conduit and Cable requirements, Security system electrical connections, and other associated Security Systems EA Security System, Size of area, requirements, Security system device location, Classification of items. Intrusion Detection Systems (IDS) are Classification of area device location, Classification of area, included in this category. area,

28ATTACHMENT 2-1 DIVISION 16 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 16

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

Communication and alarm systems not described Classification of other by the assembly categories listed above. communication system, ladder Conduit and Cable Location of areas requiring Other Communications & Alarm diagram, Conduit and Cable requirements, other Other Communication System, EA Systems requirements, other communication device location, Size of area, Classification of communication device location, Classification of area, area Classification of area, Classification of Detection Detection systems not described by the assembly System, ladder diagram, Conduit and Cable categories listed above. Location of areas requiring General Construction Items Conduit and Cable requirements, detection system EA Detection System, Size of area, (Electrical) requirements, detection system device location, Classification of Classification of area device location, Classification of area, area, OTHER ELECTRICAL SERVICES Assemblies include lightning protection devices Lightning protection system Description of Lightning (air terminals, mounting devices), clamps, ground layout, Description of Lightning Location of areas requiring protection system, Cable rods, cadwells, conductors, trenching, backfill, Lightning Protection SF protection system, Cable Lightning Protection, Size of requirements, quantity of down and any other items used to ground metal requirements, quantity of down area leads, quantity of lightning rods structural frames with conduit and wire. leads, quantity of lightning rods Electric heating control location, Items could include baseboard heaters and wall power requirements, Electrical Electrical Heating requirements, and ceiling heaters. Assemblies include safety Heating requirements, Conduit Conduit and wire requirements, Location of areas requiring switches, control devices, heaters, conduit, and Electric Heating SF and wire requirements, Location of Electric Heating Electric Heating, Size of area, wire. Location of Electric Heating equipment, classification of classification of area equipment, classification of area area Assemblies include wire, conduit, conduit support Single one line drawing or Energy Management or fastening systems, sensor devices, and all schematic drawings, Energy requirements, Conduit and wire Location of areas requiring an electrical connections. Management requirements, Energy Management Control requirements, Location of Energy Management system, EA Conduit and wire requirements, System Energy Management Size of area, classification of Location of Energy equipment, classification of area Management equipment, area classification of area Single one line, schematic, or Special systems and devices not described by the Conduit and wire requirements, ladder drawings, Conduit and Location of area for other assembly categories. Other Special Systems And Location of other special SF wire requirements, Location of special systems, Size of area, Devices systems devices, Classification other special systems devices, Classification of area of area Classification of area

ATTACHMENT 2-1 DIVISION 16 JUNE 2008 29 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 16

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

ELECTRICAL DISTRIBUTION Classification of Substation, This system includes substation equipment and elevation drawing of substation, materials required from the primary power source. Conduit and Cable Breaker layout and size, requirements, Single one line Location of area for Substation, Substations SF Conduit and Cable drawing, Substation location single one line drawing requirements, Single one line and size. drawing, Substation location and size. Classification of Transformer, Electrical power transformers used in conjunction Conduit and Cable Conduit and Cable Location of area for with electrical substations. May include pole/tower requirements, Single one line Transformers EA requirements, Single one line transformer, single one line or pad-mounted transformers. drawing, transformer location drawing, Transformer location drawing and size. and size Classification of switches and Includes all components of switchgear, voltage control devices, elevation regulators and bus bars used with electrical Switches and control device drawing of substation, switches substations. layout and size, Conduit and Switches, Controls & Devices XX and control device layout and Single one line drawing, Cable requirements, Single one size, Conduit and Cable line drawing, requirements, Single one line drawing, Includes all components of switchgear, for Elevation drawing of substation, Metering requirements, Conduit metering used with electrical substations. Metering requirements, Conduit and Cable requirements, Single Location of area for Substation, Metering EA and Cable requirements, Single one line drawing, Substation single one line drawing one line drawing, Substation location and size. location and size. Pole/Tower layout, Roadway or Roadway or people crossing Separation of poles/towers Towers, poles, crossarms, and insulators used in people crossing layouts, Cable layouts, Cable and wire size, requirements, height of conjunction with substations. and wire size, Cross arm, Cross arm, insulator poles/towers, cable sag Towers, Poles, Crossarms & insulator requirements, requirements, Separation of requirements KVA Insulators Separation of poles/towers poles/towers requirements, requirements, height of height of poles/towers, cable poles/towers, cable sag sag requirements requirements Duct bank layouts, Cable and Cable and wire description in Number of conduits in duct Includes conductors used in conjunction with wire description in duct bank duct bank conduits, Duct bank bank, concrete and substations. conduits, Duct bank location, location, Number of conduits in reinforcement requirements. Underground Electric Conductors KVA Number of conduits in duct duct bank, concrete and bank, concrete and reinforcement requirements. reinforcement requirements. Manhole/Handhole size and Manhole/Handhole size and Includes manholes and handholes and excavation Manholes, and Handholes EA description, Manhole/Handhole description, Manhole/Handhole Manhole/Handhole location for use in conjunction with substations. location location

30ATTACHMENT 2-1 DIVISION 16 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 16

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

Pole/Tower layout, Roadway or Roadway or people crossing Separation of poles/towers Includes conductors used in conjunction with people crossing layouts, Cable layouts, Cable and wire size, requirements, height of substations. and wire size, Cross arm, Cross arm, insulator poles/towers, cable sag insulator requirements, requirements, Separation of requirements Overhead Electric Conductors EA Separation of poles/towers poles/towers requirements, requirements, height of height of poles/towers, cable poles/towers, cable sag sag requirements requirements Grounding systems used in conjunction with Size of grounding electrode, Size of grounding electrode, substations. Grounding systems for buildings, location of test wells, Grounding location of test wells, Grounding Grounding requirements, Grounding Systems LF power distribution, and other electrical systems requirements, Substation requirements, Substation Substation location and subsystems are included with those other location location systems. Elevation drawing, Size of Includes conductors for underground electrical Size of Transmission & Transmission & Distribution distribution. Distribution equipment, Conduit equipment, Conduit and cable Location of Transmission & Other Electric Transmission & and cable requirements, LF requirements, Location of Distribution equipment, Single Distribution Location of Transmission & Transmission & Distribution one line drawing Distribution equipment, Single equipment, Single one line one line drawing drawing SITE LIGHTING Fixture description, Fixture Includes fixtures, controls, and all components Fixture description, roadway Lighting requirements, Size of Exterior Lighting Fixtures & location, receptacle location, used in conjunction with exterior lighting. KVA layout, Lighting requirements, area requiring lighting and Controls switch location, Classification of Classification of area power, Classification of area area, and circuitry Fixture location, Grounding Lighting requirements, Size of Grounding systems used in conjunction with Grounding requirements, size Grounding Systems LF requirements, size of grounding area requiring lighting and exterior lighting. of grounding electrode electrode power, Classification of area Special security lighting Includes all components used for special security Fixture description, Fixture Fixture description, Conduit and requirements, Size of area lighting. location, receptacle location, Cable requirements, fixture Special Security Lighting Systems EA requiring special security switch location, Classification of and device location, lighting and power, area, and circuitry Classification of area, Classification of area Fixture description, Fixture Conduit and Cable Includes components and equipment used for Lighting requirements, Size of location, receptacle location, requirements, fixture and area lighting not described above. Other Area Lighting LF area requiring lighting and switch location, Classification of device location, Classification of power, Classification of area area, and circuitry area, SITE COMMUNICATION AND SECURITY Includes all components, cables, and equipment Classification of used in conjunction with exterior telephone Telecommunication system, Conduit and Cable Location of areas requiring a systems. ladder diagram, Conduit and requirements, telecommunication System, Telecommunications Systems EA Cable requirements, Telecommunication device Size of area, Classification of Telecommunication device location, Classification of area, area location, Classification of area, Includes all components, cables, and equipment Classification of Sound system, Conduit and Cable used in conjunction with exterior sound systems. ladder diagram, Conduit and Location of areas requiring a requirements, Sound system Sound Systems EA Cable requirements, sound sound system, Size of area, device location, Classification of system device location, Classification of area area, Classification of area,

ATTACHMENT 2-1 DIVISION 16 JUNE 2008 31 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 16

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

Includes all components, cables, and equipment Classification of Fire alarm used in conjunction with exterior fire alarm system, ladder diagram, panel Conduit and cable Fire Alarm requirements, Size systems. Fire Alarm Systems EA size, Conduit and cable requirements, Fire alarm device of area requiring Fire Alarm, requirements, Fire alarm device location, Classification of area, Classification of area location, Classification of area, Includes all components, cables, and equipment Classification of CATV system, used in conjunction with exterior cable TV ladder diagram, Conduit and Conduit and Cable Location of areas requiring systems. Cable TV Systems (CATV) EA Cable requirements, television requirements, CATV device CATV system, Size of area, device location, Classification of location, Classification of area, Classification of area area, Classification of security Includes cables, wiring, and equipment used in system, ladder diagram, Conduit and Cable conjunction with exterior security systems. Location of areas requiring Conduit and Cable requirements, Security system Security Systems XX Security System, Size of area, requirements, Security system device location, Classification of Classification of area device location, Classification of area, area, Includes cameras, monitors, and components Classification of TV Camera used in conjunction with exterior security and monitor system, ladder Conduit and Cable Location of areas requiring TV systems. diagram, Conduit and Cable requirements, TV Camera and Camera and monitor system, TV Cameras & Monitors LF requirements, TV Camera and monitor system device location, Size of area, Classification of monitor system device location, Classification of area, area Classification of area, Grounding requirements, size Grounding requirements, size Grounding systems used in conjunction with Grounding requirements, Duct Grounding Systems LF of grounding electrode Duct of grounding electrode Duct exterior electrical distribution. Bank location Bank location Bank location Includes all components, cables, and equipment Classification of other used in conjunction with other special Communication/Alarm System, Conduit and Cable Location of areas requiring communication and alarm systems not defined ladder diagram, Conduit and requirements, other other Communication/Alarm above. Other Communication & Alarm LF Cable requirements, other Communication/Alarm System System, Size of area, Communication/Alarm System device location, Classification of Classification of area device location, Classification of area, area, Classification of other security Includes all components and equipment used in system, ladder diagram, Conduit and Cable conjunction with special security systems not Location of areas requiring Conduit and Cable requirements, other Security defined above. Other Security Systems LF other Security System, Size of requirements, Security system system device location, area, Classification of area device location, Classification of Classification of area, area, Classification of Emergency Electric power transformers used in conjunction Power Generation System, Conduit and Cable with exterior electrical distribution. May include Conduit and Cable requirements, Single one line Location of areas requiring pole/tower or pad-mounted transformers and requirements, Single one line drawing, Emergency Power Emergency Power Generation generators. Emergency Power Generation EA drawing, Emergency Power Generation System equipment System, Size of area, Generation System equipment location and size, Classification Classification of area location and size, Classification of area. of area.

32ATTACHMENT 2-1 DIVISION 16 JUNE 2008 Attachment 2-1 BEDC Work Packages by CSI Divisions

ATTACHMENT 2-1 Attachment 2-1 BEDC Work PackagesBEDC WORK byPACKAGES CSI BY DivisionCSI DIVISION - DIVISION 16

WORK PACKAGE ASSEMBLY UNIT CLASS 2 CLASS 3 CLASS 4 SCOPE OF ASSEMBLY

OTHER SITE ELECTRICAL UTILITIES Details of cathodic protection Includes all components required in conjunction connection, Location of test with sacrificial anode system. Type of Sacrificial required, Sacrificial Anode Cathodic sites, Type of Sacrificial Location of areas requiring EA conduit and wire requirements, Protection System required, conduit and wire cathodic Protection yard piping layout. requirements, yard piping layout. Includes conductors and termination required for Details of cathodic protection cathodic protection. connection, Location of test Induced current cathodic Induced Current Cathodic sites, Induced current cathodic protection requirements, Location of areas requiring LF Protection System protection requirements, conduit and wire requirements, cathodic Protection conduit and wire requirements, yard piping layout. yard piping layout. Details of cathodic protection Includes components and equipment used in connection, Location of test cathodic protection conjunction with other cathodic protection sites, cathodic protection requirements, conduit and wire Location of areas requiring systems not defined above. Other Cathodic Protection XX requirements, conduit and wire requirements, yard piping cathodic Protection requirements, yard piping layout. layout.

ATTACHMENT 2-1 DIVISION 16 JUNE 2008 33 Attachment 2-1 BEDC Work Packages by CSI Divisions

34 Attachment 2-2 Design Content by Estimate Class

Attachment 2-2 Design Content by EstimateATTACHMENT Class 2-2 DESIGN CONTENT BY ESTIMATE CLASS

Estimate Class Description Class 5 Class 4 Class 3 Class 2 Class 1 Initiation Planning 30% Design 60% Design 90/100% Design

GENERAL PROJECT INFORMATION Project Scope Description Preliminary Advanced Final Final Final Plant Capacity Assumed Advanced Final Final Final Site Location Assumed Specific Specific Specific Specific Site Layout None Preliminary Final Final Final Earthwork Quantities None Preliminary Final Final Final Process Selection and Criteria None Preliminary Final Final Final Design Discipline Criteria and Standards None Preliminary Final Final Final Equipment Lists (Criteria, Hp, size, etc.) None Preliminary Final Final Final Electrical Load Lists None Preliminary Advanced Final Final Geotechnical Information None Preliminary Final Final Final Permitting Requirements Assumed Preliminary Final Final Final Site Environmental Survey None Preliminary Final Final Final Site Hazards Survey None Preliminary Final Final Final Aerial Photography None Preliminary Final Final Final Site Survey None Preliminary Final Final Final Building Programming None Advanced Final Final Final Architectural Material Boards None None Preliminary Final Final Traffic Plan None None Preliminary Final Final Accoustical Study None None Preliminary Final Final Contracting (Packaging) Strategy None Advanced Final Final Final Equipment Procurement Approach None Preliminary Final Final Final Calculations None Preliminary Advanced Final Final Surge Analysis None None Preliminary Final Final Project Schedule Assumed Preliminary Advanced Final Final Project Risk Log Assumed Updated Updated Updated Updated

1

ATTACHMENT 2-2 Site Projects JUNE 2008 Attachment 2-2 Design Content by Estimate Class ATTACHMENT 2-2 DESIGN CONTENT BY ESTIMATE CLASS

Estimate Class Description Class 5 Class 4 Class 3 Class 2 Class 1 Initiation Planning 30% Design 60% Design 90/100% Design

SPECIFICATIONS Table of Contents Draft Final Final Final Major Mechanical Equipment (>~$100k) Draft Final Final Major Pipe (>~48 to 60-in) Draft Final Final Major Electrical Equipment (generators, switchgear, VFDs) Draft Final Final Process Control Strategies Draft Final Final Concrete Draft Final Final Trenchless Technology Draft Final Final Remaining Specifications Draft Final

DRAWINGS

GENERAL Location and Vicinity Map Finished List of Drawings Preliminary Advanced Finished Building/Location Area Designation Key Preliminary Finished Pipeline Key Plan Preliminary Finished List of Symbols Finished List of Abbreviations Finished Liquids Process Flow Schematic Advanced Finished Solids Process Flow Schematic Advanced Finished Design Criteria Advanced Finished Hydraulic Profile (Plants) Preliminary Finished Hydraulic Gradeline (Pipelines) Preliminary Finished Piping Schedule Preliminary Finished

2 ATTACHMENT 2-2 Site Projects JUNE 2008 ATTACHMENT 2-2 Attachment 2-2 Design Content by Estimate Class DESIGN CONTENT BY ESTIMATE CLASS

Estimate Class Description Class 5 Class 4 Class 3 Class 2 Class 1 Initiation Planning 30% Design 60% Design 90/100% Design

CIVIL Civil Notes and Symbols Preliminary Advanced Finished List of Abbreviations Advanced Finished Civil Standard Details Preliminary Advanced Finished Existing Site Plan Preliminary Finished Site Key Plan Finished Demolition Preliminary Advanced Finished Construction Staging Area Plan and Notes Preliminary Advanced Finished Horizontal Control and Paving Plan Preliminary Finished Grading and Drainage Plan Preliminary Finished Site Plan Preliminary Preliminary Finished Large Yard Piping Plan Preliminary Preliminary Advanced Finished Small Piping Plan Preliminary Preliminary Finished Site Sections Preliminary Finished Road Profiles Preliminary Advanced Finished Yard Piping Profiles Preliminary Advanced Finished Civil Structure Plans Preliminary Finished Civil Structure Sections and Details Preliminary Advanced Finished

CORROSION CONTROL Corrosion Control Notes Preliminary Advanced Finished Corrosion Control Symbols and Abbreviations Preliminary Finished Corrosion Control Standard Details Preliminary Advanced Finished Corrosion Control Plans Advanced Finished Corrosion Control Sections and Details Preliminary Finished

3 ATTACHMENT 2-2 Site Projects JUNE 2008 Attachment 2-2 Design Content by Estimate Class ATTACHMENT 2-2 DESIGN CONTENT BY ESTIMATE CLASS

Estimate Class Description Class 5 Class 4 Class 3 Class 2 Class 1 Initiation Planning 30% Design 60% Design 90/100% Design

PIPING PLANS Existing topographic features Preliminary Finished Existing sub-surface piping and structures Preliminary Advanced Finished Existing utility data Advanced Finished Street, physical feature names (creeks, rivers etc.) Preliminary Finished Survey control points located on plan view Advanced Finished Geotechnical bore hole/test pipe locations shown on Finished plan view Pipeline bend and fitting coordinates shown on plan Finished view New improvements Advanced Finished New piping showing coordinates, sizes, material Advanced Finished Pipe stationing and tick marks Advanced Finished Pipe bend information to angle point callouts Advanced Finished Invert elevations on small gravity lines Advanced Finished Corrosion Control Details Advanced Finished

PIPING PROFILES Existing ground line Preliminary Finished New finish grade Advanced Finished New pipe showing invert, crown and manholes Preliminary Advanced Finished Stations at all pipe angle points, appurtenances, inlets, outlets, and any other items necessary for Advanced Finished fabrication and installation (pressure piping). Appurtenances such as meters, couplings, valves, etc Preliminary Advanced Finished (pressure pipeline). Pipe crossings both new and existing. Advanced Finished Pipe slopes on the profile. Advanced Finished Define special bedding conditions. Advanced Finished Pipe material classifications including size, service Preliminary Advanced Finished and material callouts.

4 ATTACHMENT 2-2 Site Projects JUNE 2008 ATTACHMENT 2-2 Attachment 2-2 Design Content by Estimate Class DESIGN CONTENT BY ESTIMATE CLASS

Estimate Class Description Class 5 Class 4 Class 3 Class 2 Class 1 Initiation Planning 30% Design 60% Design 90/100% Design

Storm drain hydraulic grades Advanced Finished Casings where needed including casing data. Advanced Finished Special pipe supports where needed. Advanced Finished All underground interferences. Advanced Finished Detail references specific to the construction of the Advanced Finished pipe. Match line and match line data. Advanced Finished Surface restoration requirements Advanced Finished

LANDSCAPE/ IRRIGATION General Landscaping Notes Preliminary Advanced Finished General Landscaping Symbols and Abbreviations Preliminary Advanced Finished Planting Demolition/ Plant Salvage Plan Preliminary Advanced Finished Planting Plan Preliminary Preliminary Advanced Finished Plant Legend Preliminary Advanced Finished Planting Details Preliminary Finished Irrigation Legend Preliminary Preliminary Finished Irrigation Plans Preliminary Preliminary Finished Irrigation Details Preliminary Finished

EROSION CONTROL Erosion Control Notes and Symbols Preliminary Preliminary Finished Erosion Control Standard Details Advanced Finished Erosion Control Plan Preliminary Advanced Finished Erosion Control Details Preliminary Finished

5 ATTACHMENT 2-2 Site Projects JUNE 2008 Attachment 2-2 Design Content by Estimate Class ATTACHMENT 2-2 DESIGN CONTENT BY ESTIMATE CLASS

Estimate Class Description Class 5 Class 4 Class 3 Class 2 Class 1 Initiation Planning 30% Design 60% Design 90/100% Design

ARCHITECTURAL Architectural General Notes & Symbols Advanced Finished Architectural Standard Details Preliminary Advanced Finished Summary Preliminary Finished Life Safety Plans & Notes Preliminary Finished ADA Standards (NA where projects are exempt) Preliminary Finished Wall & Partition Types Preliminary Finished Door & Finish Schedules, Window Types Preliminary Finished Laboratory Equipment Schedule (if applicable) Preliminary Finished Toilet Accessories Schedule Preliminary Finished Furnishings Plan & Schedule (if applicable) Preliminary Advanced Finished Demolition Plans, Sections & Details Preliminary Advanced Finished Architectural Key Plan Preliminary Finished Floor Plan(s) Preliminary Advanced Advanced Finished Reflected Ceiling Plan(s) Preliminary Advanced Finished Roof Plan Preliminary Advanced Finished Exterior Building Elevations Preliminary Advanced Finished Elevation Details Preliminary Finished Building Sections Preliminary Advanced Finished Interior Elevations Advanced Finished Wall Sections Preliminary Finished Project Specific Details & Sections Advanced Finished

6 ATTACHMENT 2-2 Site Projects JUNE 2008 ATTACHMENT 2-2 Attachment 2-2 Design Content by Estimate Class DESIGN CONTENT BY ESTIMATE CLASS

Estimate Class Description Class 5 Class 4 Class 3 Class 2 Class 1 Initiation Planning 30% Design 60% Design 90/100% Design

STRUCTURAL Assumed = Approximate Wall and Slab Thickness; Preliminary = + Rebar; Advanced = + Accessories (e.g. stairs, hatches); Finished = Fully Annotated

General Structural Notes Preliminary Finished General Standard Structural Details Preliminary Advanced Finished General Project Specific Details Preliminary Finished Demolition Plans, Sections & Details Preliminary Advanced Finished Pile Plan Assumed Preliminary Advanced Finished Foundation Plan Assumed Preliminary Advanced Finished Floor Plan Assumed Preliminary Advanced Finished Top Deck or Intermediate Plan Assumed Preliminary Advanced Finished Partial Plans Preliminary Finished Roof Framing Plans Preliminary Advanced Finished Main Sections Assumed Preliminary Advanced Finished Partial Sections Preliminary Finished Structural Steel Frame Elevations and Details Preliminary Advanced Finished Minor Structure Plans, Sections & Details Preliminary Preliminary Finished

MECHANICAL Started = Overall Dimensions; Preliminary = + Major Equipment and Piping (>8"); Advanced = + Accessories (e.g. small piping, supports); Finished = Fully Annotated

Mechanical Standard General Notes Preliminary Advanced Finished Mechanical Standard Details Preliminary Finished Mechanical Equipment Schedules Preliminary Advanced Finished Mechanical Demolition Preliminary Advanced Finished Mechanical Floor Plans Preliminary Advanced Finished Mechanical Sections Preliminary Advanced Finished Mechanical Details Preliminary Advanced Finished

7 ATTACHMENT 2-2 Site Projects JUNE 2008 Attachment 2-2 Design Content by Estimate Class ATTACHMENT 2-2 DESIGN CONTENT BY ESTIMATE CLASS

Estimate Class Description Class 5 Class 4 Class 3 Class 2 Class 1 Initiation Planning 30% Design 60% Design 90/100% Design

PLUMBING Plumbing Standard Details Advanced Finished Plumbing Schedules Preliminary Advanced Finished Domestic Riser Diagrams Preliminary Advanced Finished Sanitary Riser Diagrams Preliminary Advanced Finished Natural Gas Riser Diagrams Preliminary Advanced Finished Plumbing Floor Plans Preliminary Advanced Finished Plumbing Sections Advanced Finished Plumbing Details Finished

HVAC HVAC Standard General Notes Preliminary Finished HVAC Standard Details Preliminary Advanced Finished HVAC Equipment Schedules Preliminary Finished HVAC Demolition Preliminary Advanced Finished HVAC Floor Plans Preliminary Advanced Finished HVAC Sections Preliminary Finished HVAC Details Preliminary Finished

FIRE PROTECTION Fire Protection Standard Details Advanced Finished Fire Protection Floor Plans Preliminary Advanced Finished Fire Protection Details Preliminary Finished

8 ATTACHMENT 2-2 Site Projects JUNE 2008 ATTACHMENT 2-2 Attachment 2-2 Design Content by Estimate Class DESIGN CONTENT BY ESTIMATE CLASS

Estimate Class Description Class 5 Class 4 Class 3 Class 2 Class 1 Initiation Planning 30% Design 60% Design 90/100% Design

INSTRUMENTATION Instrumentation Notes Finished Instrumentation Symbols and Abbreviations Advanced Finished Instrumentation Standard Details Advanced Finished Control System Block Diagram Advanced Finished Communication System Diagram Advanced Finished Security System Diagram Advanced Finished Logic Diagrams Preliminary Advanced Finished Panel Layout Drawings Preliminary Advanced Finished Loop Drawings (if required) Advanced Finished Control Room Plan and Elevations Preliminary Finished Process and Instrumentation Diagrams (P&IDs) Advanced Finished Instrument and I/O Lists Advanced Finished

ELECTRICAL Electrical Standard Symbols Finished Electrical Standard Details Advanced Finished Site Plan Advanced Finished Duct Bank Schedule Advanced Finished Manhole, Hand hole and Pull Box Schedule Advanced Finished Single Line Diagrams Advanced Finished Electrical Equipment Elevations Preliminary Finished Schematic Diagrams Preliminary Finished Lighting Fixture Schedule Advanced Finished Panelboards/Transformers Advanced Finished Riser Diagrams for Telephone Systems Preliminary Finished Riser Diagrams for Fire Alarm Systems Preliminary Finished Conduit Development Preliminary Advanced Finished Conduit Schedule Advanced Finished Demolition Preliminary Finished Electrical Equipment Location Plans Advanced Finished Lighting and Receptacle Plans Preliminary Finished Lightning and Grounding Plans Preliminary Finished Miscellaneous Systems Plans Preliminary Finished

ATTACHMENT 2-2 Site Projects JUNE 2008 9 Attachment 2-2 Design Content by Estimate Class

10 Chapter 3 Estimate Preparation Estimate Preparation Chapter 3

Chapter 3 Estimate Preparation

Chapter 3 – Estimate Preparation This chapter describes the general approach to estimate preparation to be used for all BEDC cost estimat- ing and includes subsections on the following subjects: • Estimating System Requirements • Estimating Methodology • Estimate Structure and Definitions • Estimating System Rates and Supporting Calculations • Estimate Inputs • Escalation of Construction Cost Inputs • Estimate Sections

Estimating System Requirements

All Class 4, 3, 2 and 1 estimates prepared for BEDC projects with an estimated construction cost of $25M or greater shall be produced using an estimating system with the minimum features listed below: • Multiple standard and custom reports using filter, sort, and subtotal features • Resource reports (labor, equipment, materials, etc.) • Variance reports able to compare estimates prepared at various stages of project development • On-screen review capability, including summary/drill-down features • Multiple resource rate tables • Update the entire estimate by changing a resource price or rate • Apply adjustment factors to portions of the estimate based on a selection criteria

Spreadsheet software may be used for Class 5 and 4 estimates and for supporting calculations of Class 3, 2, and 1 estimates. However, the body of Class 3, 2, and 1 estimates must be prepared using an estimating system with the capabilities listed above, as well as the capability of producing the reports listed in Chapter 4 of this Manual. Estimating systems used to prepare BEDC Class 3, 2 and 1 estimates shall be one of the following, or an approved equal: • Sage; Timberline Estimating Extended • MC2 (Management Computer Controls); ICE • Heavy Construction Systems Specialists (HCSS); Heavy Bid • Bid2Win Software • Hard Dollar • WinEstimator; WinEst

Approval to use any estimating system other than those listed above must be obtained in writing from the BEDC Cost Estimating Division.

3-1 Cost Estimating Manual June 2008

Estimates shall be submitted to the BEDC in hard-copy and electronic format. Electronic copies must pro- vide BEDC Cost Estimating Division staff the ability to manipulate the estimate (sort, summarize, drill-down) as well as produce custom reports, but not necessarily revise the estimate.

Estimating Methodology

When submitting an estimate to BEDC, the estimator must identify the type of estimating methodology that will be used for the various components of the estimate and provide back-up material as required to support the accuracy of the method. There are a variety of industry standard techniques to develop estimates. The choice of technique is dictated largely by the level of scope definition and the end use of the estimate. In most estimates, multiple methodologies are used to account for the varying degrees of scope definition for different project elements. In general, top-down estimates are used in early stages of project development when less than about 15 to 20% of the total scope is defined and are typically limited in application to Class 5 and 4 estimates. Top-down estimates use rules of thumb, parametric models, analogies, or other cost estimating relationships (CERs) to estimate the total cost. These types of estimating methodologies can be highly inaccurate and proper levels of contingency must be applied to account for this estimating risk. Bottoms-up methods are characterized by a thorough, detailed analysis of scope and task components which can be “rolled-up” to produce an estimate of the entire project. This requires a detailed work break- down structure and pricing of each work package that comprises the project. This method requires a higher level of scope definition and is typically reserved for Class 3, 2 and 1 estimates.

Definitions of the various estimating methods typically used in projects is listed below. Where available, definitions were quoted from the AACE Recommended Practice No. 10S-90 Cost Engineering Terminol- ogy. The methodologies are listed in the order of acceptable use based on scope definition. For example, Judgment, Gross Capacity-factored, and Parametric Models should only be used in early estimates (Class 5 or 4) while Detailed Unit Cost with Detailed Quantity Take-Offs are reserved for later estimates (Class 3, 2, and 1):

Judgment – Judgment is an estimating method based on historical experience with similar type facilities adjusted for known project complexities and size or capacity differences.

Gross Capacity-Factored – “A cost estimating method in which the cost of a new facility or facility com- ponent is derived from the cost of a similar item or facility of a known, but usually different capacity. In this method, the ratio of costs between two similar facilities is equal to the ration of the capacities taken to an exponential factor.” Capacity-factored estimating methods are typically based on a very limited amount of high level project definition such as average dry weather and peak wet weather flow (ADWF or PWWF) for a secondary wastewater treatment facility. A gross capacity-factored estimate could be based on a unit cost per capacity developed based on historical cost data of similar facilities adjusted for location and time.

3-2 Chapter 3 Estimate Preparation

Discipline-Factored – In early estimates, the various major trades of a project are sometimes calculated as a percentage of the total project costs. Discipline costs such as site civil works, electrical, instrumentation, and landscaping generally fall within a percent range of the total project. For example, instrumentation is typically in the range of 4 to 8% of the total project cost of a typical water treatment plant project while electrical systems are generally in the range of 8 to 15% of the total project costs.

Parametric Model – “In estimating practice, describes estimating algorithms or cost estimating relation- ships that are highly probabilistic in nature. Typical parametric algorithms include, but are not limited to, factoring techniques, gross unit costs, and cost models. Parametric estimates can be as accurate as defini- tive estimates.” Example inputs of a parametric model for a secondary clarifier cost model might include PWWF, maximum surface loading rate, and allowable water depth. Based on these high level inputs, the general dimensions of the facility can be estimated and when combined with unit costs of the elements, a parametric-based cost estimate can be developed.

Parametric models can also be used to price components of the project based on the output of preliminary design information. For example, after equipment requirements have been defined, power distribution can be estimated based on the total connected horsepower of the equipment; building lighting and receptacle/ branch wiring costs can be estimated based of the square footage of floor area of buildings.

Semi-Detailed Unit Costs with Assembly-Level Line Items – Both the takeoff and the estimate is done at the “assembly level” vs. the “line-item level”. This practice is typical of Class 4 estimates and for some elements of Class 3 estimates. In cases where portions of the design documents have not progressed to a point to allow detailed takeoff, and a “go-by” design from a similar project is not available, it may be neces- sary to use composite unit costs for certain elements of the projects. For example, if the only information available for a building is the square footage and the use of the building, it may be appropriate to use a “unit price factor”, which in the case of a building would be $/square foot of building. Factors such as this are known as “composite” prices as they include all the cost for the elements at the lower WBS levels. In this case, the composite square foot price for a building ($/square foot), includes the cost for all of the ele- ments that make up a complete building (structural, architectural, plumbing, HVAC, electrical, etc.), and the estimate is done at WBS Level 2 only. As the design progresses, and more detail becomes available, it will be possible to include more detail in the estimate for WBS Levels 3 through 6, but by pricing at WBS Level 2 only, it is understood that the cost for all elements below this level are included in the composite price.

Detailed (Line Item) Unit Cost with Forced (Line Item) Quantity Take-Offs – If the class of estimate requires more detail than a capacity factor or composite price, “forced” takeoff, using cost estimating re- lationships, can be used to estimate the quantities at the lower WBS levels. For instance, cost estimating relationships for the average square feet of interior partition per square foot of building or the number of sprinkler heads per square foot of building can be used to estimate quantities for these elements, as well the remaining building elements. Another example of forced takeoff is pricing for a concrete wall - if the wall

3-3 Cost Estimating Manual June 2008 dimensions are available but the rebar details are not available, the formwork and concrete volume could be determined using line item detail and the rebar quantity could be determined using an average lbs/cy factor (pounds of rebar per cubic yard of concrete).

Detailed (Line Item) Unit Cost with Detailed (Line Item) Quantity Take-Offs – Complete detailed takeoff and line item estimating with 100% design drawings and documents.

Definition Assembly-Level and Detailed (Line-Item) Quantity Take-Offs –The difference between as- sembly-level and line-item detail as referenced in the discussion of estimating methodology above can be demonstrated by the example of cast-in-place concrete. At the assembly level, the takeoff quantity would be cubic yards, and the estimate detail would be manhours/labor per cubic yard, material per cubic yard, equipment cost per cubic yard, etc. At the detailed line level, takeoff quantities would include formwork, construction joints, waterstop, buy/place concrete, buy place reinforcing steel, embedded items, cure, etc.

The design and estimating team must work together to select the most appropriate estimating methodolo- gies based on the scope definition and availability of historical cost data and parametric models, again keeping in mind that various methodologies can be used for various project elements or components. The team should strive to use the most advanced methodologies where possible to reduce estimating error. The estimating team is required to report on the estimating methodologies used in developing the estimate as part of the Basis of Estimate Report (See Chapter 4 –Estimate Outputs).

Estimate Structure and Definitions

In order to ensure consistency and to facilitate review and capture of historical cost data, all cost estimates prepared for BEDC Capital Projects must be prepared using a consistent format. This section describes the general organization of the estimate including required Cost Types, Fields (or Columns), Estimate Sections, and Line Item Coding. Cost Types Standard cost types/categories to be used in all estimates are: • Labor • Material • Equipment (Construction ) • Subcontracts • Other

3-4 Chapter 3 Estimate Preparation

These cost categories are typically the major column headings in all estimates, and all costs in the estimate must fall into one of these categories. Each cost type/category is defined below:

Labor – All craft and staff labor (both hourly and salaried employees) required to complete the project. Man-hours is the basic unit of measure for labor and regardless of how labor costs are estimated (by crew hours, man-months, man-weeks, etc.), total man-hours should also be calculated and included in the estimate.

Equipment – The cost for construction equipment utilized for construction of the project. Costs include: • Rental/depreciation • Maintenance/repair costs • Operating costs (fuel, oil, grease)

Labor to operate the equipment is not included in the equipment cost type. Labor for major maintenance/ repair of the equipment is included in the equipment cost. Labor for daily servicing should be included in the labor category, but as an indirect cost.

Material – All permanent and temporary material used in the project. Material is further subdivided into the following categories: • Permanent material – all material that becomes part of the completed facility other than process equipment • Process equipment – all equipment that becomes part of the completed facility and is shown on the equipment list • Temporary material – all material used and/or consumed during construction of the project that does not become part of the completed facility. Examples include plywood for concrete formwork, lumber for temporary scaffolding or walkways, and materials for temporary roadways.

Subcontracts – The cost of specialty work performed by subcontractors to the prime contractor. For all estimates prepared for BEDC, only subcontract items performed on an hourly or true unit-price basis should be included in the subcontract category. Prices in the subcontract column should be “all-in” prices, including subcontractor overhead and profit. All other costs (not procured on a true unit-price basis), even if performed by a subcontractor, should be estimated with the typical cost categories (labor, equipment, material, and other), but identified as a subcontracted item. This allows better analysis of on-site manpower levels, risk, escalation, markup, and other factors that may affect the total price of the project. Prices in the labor, equipment, material, and other cost type columns should not include subcontractor overhead and profit. Subcontractor overhead and profit can be added in the markup section of the estimate as described later in this chapter.

Other – All other costs that do not fit into one of the other cost categories (labor, equipment, materials, subcontracts).

3-5 Cost Estimating Manual June 2008

Fields/Columns in Estimates In addition to separate columns for the dollar amount for each of the cost types/categories noted in the previous section, the estimating system must contain additional fields (columns) to provide additional data to each line item estimate including quantities, how the line item is priced, and codes to allow the estimate to be sorted and summarized in various combinations. Not all columns will be used in any given report. Chapter 4 describes the standard estimate reports and which columns are included in each report. The fields and their functions are described below. The actual names of any given field may vary depending on the estimating system being used as long as the field performs the same function and provides the information listed. Field names in italics in the list below are “unit of measure” descriptions associated with a specific value field. The header for these fields may be combined with the header with the associated value field. For example the header for the “Estimated Productivity” value may be combined with the header for the “Productivity Unit” as long as the “Productivity Unit” is shown for each line item (e.g 250 cy/day or 0.15 mh/sf).

Item Level 1/Item Level 2/Item Level 3 – These (labor and equipment) assigned to the work. three fields make up a unique identifier for like Resources are time-related (e.g. manhours, crew- items in the estimating database. The actual field hours, crew-days, man-days, etc.). Productivity is names may vary depending on the estimating sys- quantified as resources per unit (e.g. manhours tem being used. The fields are hierarchal. Level per lineal foot) or units per resource (e.g. cubic 1 is the highest level and is generally organized yards per crew-day). “Base” Productivity is the by CSI division or section within the estimating productivity from the estimating organization’s database. Each line item in the estimate must be historical cost library, reference, or experience, assigned a value for each of these fields in order and represents the productivity expected under to allow grouping of similar items for comparison ideal conditions. In cases where the historical cost during the estimate review process. is tracked as a range, the base productivity should represent the average or most likely productivity Description – Description of the work included in under ideal conditions, before adjustments for the estimate line item. project-specific factors. Take-off Quantity – Physical quantity of the Productivity Adjustment – The value in this col- estimate line item determined from the design umn represents any adjustment (by percentage) documents. to the base productivity (see above) to determine Unit – Unit of measure (UOM) for the takeoff quan- the estimated productivity used for the line item. A tity (e.g. lineal feet, cubic yard, square feet, etc.). positive percentage calculates a higher productiv- ity (lower cost), and a negative percentage results Waste – Percentage waste applied to the takeoff in a lower productivity (higher cost). Different line quantity to determine the order (buy) quantity for items within the estimate including line items for the material for the estimate line item. similar work, may have different adjustment fac- Crew – Composition of the crew (labor and equip- tors applied to them. ment resources) used to perform the work de- Estimated Productivity – The productivity used scribed by the estimate line item. Crews can con- to calculate the cost for a given estimate line sist of multiple craft personnel, and multiple pieces item. With the recommended procedure above, of equipment, or may be a single resource. “Estimated Productivity” is “Base Productivity” Base Productivity (value) – Productivity is the rate adjusted by the percentage shown in the “Produc- at which the work is performed by the resources tivity Adjustment column.

3-6 Chapter 3 Estimate Preparation

Productivity Units – Units associated with the pro- Material Quantity Unit – Unit of measure for “Ma- ductivity rates (e.g. mh/lf, cubic yards/crew-hour, terial Quantity”. sf/mh, etc.) Material Price – Price per unit to purchase the Labor Quantity – Quantity of labor units (man- material. This represents the price per unit that hours, crew-hours, man-day, crew-days) used to will actually be paid to the supplier of the mate- perform the work. rial, not the material amount divided by the takeoff quantity. Labor Quantity Unit – Unit of measure for “Labor Quantity”. Material Price Unit – Unit of measure for “Material Price”. Labor Price – Price of the labor in the crew per unit of time, expressed as $/manhours, $/crew- Material Amount – “Material Quantity” multiplied day, etc. by “Material Price” Labor Price Unit – Unit of measure for “Labor Material Cost/Unit – “Material Amount” divided Price” (manhours, crew-day, etc.). by “Takeoff Quantity”. Labor Manhours – Quantity of manhours required Material Cost Unit – Unit of measure for Material to perform the work on the estimate line item, Cost/Unit calculated as “Labor Quantity” multiplied by crew Material Tax – Check mark or yes/no to indicate size (number of personnel on the crew). whether tax is applicable to the material in the line Labor Amount – “Labor Quantity” multiplied by item. “Labor Price”. Material Subcategory – Code to indicate if the Labor Cost/Unit – Labor amount (dollars) per material is permanent material, process equip- takeoff unit. ment, or temporary material/supplies. Labor Cost Unit – Unit of measure for “Labor Subcontract Price – Cost per takeoff unit of Cost/Unit”. subcontractors work required for the estimate line item. Labor Rate Table – Code to identify the labor rate table used to price the line item. Subcontract Price Unit – Unit of measure for “Subcontract Price”. Material Conversion Factor – The “Material Conversion Factor” is used when the material is Subcontract Amount – “Subcontract Price” multi- quantified with a unit of measure but priced with plied by “Takeoff Quantity”. another unit of measure. For example, aggregate Equipment Price – Cost per unit (hour, day, etc.) base might be quantified by the cubic yard, but of the equipment in the crew used to perform the purchased by the ton. In this case, the “Material work. Conversion Factor” would be expressed as tons per cubic yard (tons/cy). Equipment Price Unit – Unit of measure for “Equipment Price”. Material Unit/Unit – Unit of measure for “Material Conversion Factor” (tons/cy, etc.). Equipment Amount – “Equipment Price” multi- plied by “Takeoff Quantity”. Material Waste (yes/no) – Indicates if the “Waste” percentage (see above) is applied to the “Takeoff Equipment Rate Table – Code to indicate the Quantity” to calculate the “Material Quantity” used equipment rate table used to price the equipment to determine the cost of the material for the esti- in the line item. mate line item. Other Price – Cost per takeoff unit of “Other” Material Quantity – “Takeoff Quantity” multiplied costs. by “Material Conversion Factor” multiplied by (1 plus “Waste” factor). This is also known as the Other Price Unit – Unit of measure for “Other “order” quantity. Price”.

3-7 Cost Estimating Manual June 2008

Other Amount – “Other Price” multiplied by Source codes for Quantity and Material Pricing are “Takeoff Quantity”. used for reporting purposes to rate the accuracy Other Tax – Check mark or “yes/no” to indicate of the estimate. These codes are defined below. whether tax is applicable to the “other” cost in the line item. Quantity Source Codes: Total Cost/Unit – Sum of the unit cost (cost per 1) Detailed takeoff off design drawings takeoff unit) for Labor, Material, Equipment, Sub- 2) “Forced” takeoff from partially complete de- contracts, and Other costs. sign drawings Total Unit – Unit of measure for “Total Cost/Unit”. 3) Takeoff from a “go-by” design (design draw- ings from a previously-designed facility similar Total Amount – Total dollar amount for the esti- in size in nature) mate line item. Total Amount is equal to the total amounts of Labor, Material, Equipment, Subcon- 4) Factored using a cost estimating relationship tracts, and Other. 5) Assumed by estimator (no drawings or cost Percent of Total (optional) - Percent of the total estimating relationship available) cost in the estimate represented by a given line Material Pricing Source Codes: or subtotal within the estimate. Typically used 1) Firm quote (written) for review purposes to identify cost drivers in the estimate. Although a value can be assigned to 2) Budget quote (written) each line item in the estimate, typically only the 3) Telephone quote percentage values on the subtotal line items are useful. 4) Estimated price (using current invoices or published data) Estimate Line Item Coding 5) Database prices Each line in the detailed estimate (at the item level) 6) Plug numbers should be assigned the appropriate values for the Material Classes: following item codes: All materials in the database should be assigned • WBS Level 1; Area Name to a Bill of Materials Description. Bill of Materials • WBS Level 2; Process Name Descriptions should be grouped into product cat- • WBS Level 3; System Name egories of similar material items. Material Classes • WBS Level 4; Group/Division Name should be structured to group materials that would • WBS Level 5; Work Package Name generally be subject to the same supply/demand • WBS Level 6; Assembly Name fluctuation and escalation rates and have readily- • Subcontract Package (to identify work to be performed by subcontractors and assign available escalation forecast data available, such work to individual subcontract packages) as Producer Price Index (PPI) data. Producer Price • Material Class (for assigning escalation val- Index classifications are maintained by the U.S. ues – see below) Department of Labor, Bureau of Labor Statistics • Work Week (average hours per week for over- and are available on the Bureau’s website, http:// time calculations) www.bls.gov/ppi/. • Quantity Source (see below) • Material Pricing Source (see below) • Estimator’s Initials • Drawing Reference

3-8 Chapter 3 Estimate Preparation

A partial list of PPI classifications applicable to Line Item Coding for Composite BEDC capital projects is listed below: Material Prices • Asphalt paving mixes and blocks To produce several of the required reports, line • Roofing asphalts and pitches, items must be coded to a material class and ma- coatings, and cements terial source code in order to calculate escalation • Concrete products or contingency or other factors associated with • Concrete pipe the line item. When composite prices are used • Ready-mixed concrete that contain materials that belong to more than • Sand, gravel, and crushed stone one material class or code, the line item can either • Gypsum products be assigned to the predominant material code, • Lumber or a material class that reflects the composition • Plywood of the unit price can be used. For instance, for • Plastic construction products and pipe reinforced concrete, the concrete and the reinforc- • Hot rolled bars, plates, and structural shapes ing steel would normally be assigned to two dif- • Concrete reinforcing bar ferent material classes for calculating escalation • Fabricated structural metal and contingency. The line item can be coded to • Iron and steel pipe a material class for “reinforced concrete” and the • Fabricated pipe and fittings approximate quantity of reinforcing steel can be • Valves and fittings calculated using an average lb/cy factor. • Pumps and pumping equipment • Fans and blowers • Industrial material handling equipment • Other special industry equipment • Power, distribution and spe- cialty transformers • Switchgear and switchboard apparatus • Panelboards • Motors and generators • Electrical lighting equipment • Building wire and cable • Power wire and cable • Commercial lighting fixtures • Current carrying wiring devices • Noncurrent-carrying wiring devices • Communications systems and equipment

3-9 Cost Estimating Manual June 2008

Estimating System Rates and Supporting Calculations

This section describes the requirements of the various rate tables and supporting calculations that are part of the estimating system. Labor Productivity There are three basic methods for estimating labor costs: 1. Unit Price – Labor cost (dollar amount) per unit, not based on manhours and a labor rate. For ex- ample, the unit-price method for labor would use an historical price of $2.50/sf for an item, vs. using an historical production rate of 0.05 manhours per square foot, extended by a labor rate of $50.00 per manhour. The unit-price method for pricing labor shall not be used in estimates prepared for BEDC. 2. Manhour Pricing – Manhours per unit or unit per manhour; for example 5 manhours/each or 8 sf per manhour. 3. Crew Pricing – In this method, a crew is built up using multiple resources (labor and equipment), and extended against a production rate (example; cubic yards per hour, square feet per day, days per each, etc.).

Manhour pricing is typically used for labor-intensive work such as mechanical, electrical, concrete form- work, etc. Manhour pricing can performed the same way as crew pricing; by using a single labor resource as the crew. However, when using manhour pricing, a crew should still be used to account for a working foreman. This can be done by either adding a fraction foreman to a crew with a single journeyman or by composing the crew for the anticipated foreman ration. For example, with a journeyman-to-working foreman ratio of four-to-one, the crew could either consist of one journeyman and 0.25 foreman or four journeymen and one foreman.

Crew pricing is typically used for civil work and other equipment-intensive work because equipment re- sources can be assigned to the crew. In addition, crew pricing allows for the possibility of the need to augment the basic crew with additional resources. For example, it may be necessary to add a flagger to an excavation crew to account for traffic conditions around the excavation. In this case, the production rate can stay the same, but the manhours per unit and labor cost will go up since the crew is larger.

Another example is trucking associated with an excavation operation. The production rate is typically con- trolled by the capacity of the equipment performing the excavation, but the haul distance to the disposal affects the number of trucks required to support the operation (as the haul distance increases, more trucks are required). Labor Rates Manhour labor rates should be established by craft in the estimating system. Bare wages rates and fringe benefits should be obtained from published prevailing wages rates as covered by the New York State Labor Law Statutes 220 & 230. Prevailing Wage Rate tables are published for New York City and on a county-by- county basis in the remainder of the state. Labor rates should be fully-burdened to include payroll taxes and payroll-based insurance such as workers compensation. Craft-specific workers compensation rates should

3-10 Chapter 3 Estimate Preparation be used. For payroll tax and insurance rates that are employer-specific (based on experience factors), the default published rate should be used. An example labor rate calculations table is included as Attachment 3-1 to this Manual. Overtime Calculations Labor costs must be increased to account for planned and/or incidental overtime. Planned overtime occurs when the contractor plans to work other than a 40-hour work-week, (such as five 10-hour days per week, six 8-hour days per week, etc.) for some or all work activities. Incidental overtime occurs when crews must work past regularly scheduled work hours to finish a critical activity, such as a concrete pour. Overtime should be included in the estimate using add-on factors. (See the section titled “Estimate Sections” later in this chapter for instructions on using add-on factors.) The add-on calculation for overtime keys off the “Work Week” code assigned to each line item in the estimate.

Possible factors include: 42 hours/week – 5% incidental overtime 44 hours/week – 10% incidental overtime 48 hours/week – schedule six 8-hour days per week 50 hours/week – scheduled five 10-hour days per week 60 hours/week – scheduled six 10-hour days per week

Other overtime possibilities to consider would be 12-hour days. This situation might occur when supporting a 24-hr per day operation and changing crews twice per day (three, 8-hour shifts) is not feasible. Overtime factors should also take into account shift premiums such as 8-hours pay for 7 hours of work for swing or night shifts, or other premiums not included in the normal straight-time rates. These rules are normally identified in the union labor agreements. An example work week differential table for various overtime options is included as Attachment 3-2 to this Manual. Material Pricing Most construction materials may be grouped into three general categories: 1. Commercially-Available Commodities. Off-the-shelf items that are commercially available and not subject to significant regional variation in price such as: – Electrical commodities – Mechanical commodities – Building commodities 2. Location-Specific Commodities. Materials required in substantial quantities that are manufactured locally or regionally and subject to regional pricing/availability such as: – Concrete – Aggregates – Earthwork fill material – Rebar – Fabricated structural steel

3-11 Cost Estimating Manual June 2008

3. Project-Specific Equipment/Materials. Commonly large or custom (not “off-the-shelf”) items that are not manufactured locally and are subject to national or international availability such as: – Large fabricated pipe – Major Equipment – Large and specialty valves

The cost estimator is required to obtain telephone quotes or have in possession current invoices for all commercially available commodities. For location-specific and project-specific commodities, budgetary quotes from vendors are required. Decomposition of Composite Prices When composite unit prices are used, there should be a detailed estimate that calculates that unit price. The detailed estimate should document the assumptions for cost estimating relationships (for example lbs/ cy of rebar, sf of partitions per sf of floor area, etc.), as well as labor productivity, labor rates, material pricing, etc. In addition, when using composite unit prices, the price should still be broken into the basic cost types (labor, equipment, materials, subcontracts, and other) as well as manhours. This allows the unit prices in the assembly to be adjusted for escalation, wage rates, and productivity. Equipment Rates (Construction) If actual equipment rental rates and operating costs are not available, rates should be established using the most current data from the Associated Equipment Distributors (AED) Green Book. When using hourly rates for equipment that will be assigned to a work activity continuously, the hourly rates should be calculated as the monthly rental rate divided by 173 hours per month (40 hours per week times 52 weeks per year divided by 12 months per year). Blue Book weekly, daily, and hourly rental rates should only be used when the equipment will be used for durations consistent with such rates. Equipment rate tables should be set up with separate categories for ownership and operating costs to allow adjustments and/or escalation for operating costs due the potential volatility of fuel costs.

Estimate Inputs

Attachment 3-3 summarizes estimator inputs for each class of estimate for the typical cost drivers in mu- nicipal water and wastewater work. These key cost drivers include the following: • Equipment (Attachment 3-3A) • Earthwork (Attachment 3-3B) • Structural Concrete (Attachment 3-3C) • Electrical (Attachment 3-3D) • Process Piping (Attachment 3-3E) • Indirect Costs (Attachment 3-3F)

3-12 Chapter 3 Estimate Preparation

The tables in Attachment 2-1 show the description of each assembly, the unit of measure, and the required input for estimate Classes 2, 3, and 4. For Class 5 estimates, assembly level detail is not typically used. Class 1 estimates will typically use line item level of detail. The “required input” column is based on the design information that is typically available at the stage of the project development that corresponds with that estimate class. Where the required input is less than what is required for complete detailed takeoff using the assembly, the estimator may either use a composite price as described above, or generate the required input using forced takeoffs.

Escalation of Construction Cost Inputs

Escalation of construction cost inputs shall be included in all estimates. The assumed escalation is con- sidered an element of the base cost estimate and not contingency. Escalation contingency is added to account for the possibility that the amount of escalation included in the base estimate will be exceeded.

Due to the volatility of various key construction materials, labor and material escalation should be calculated independently. Base cost estimates should included current labor and material prices with escalation cal- culated and shown separately as outlined below. Escalation calculations are to be included in the Basis of Estimate Report (See Chapter 4 – Estimate Outputs). Material Escalation The base estimate should be prepared using current prices for all materials and supplies included in the estimate. As noted earlier in this chapter, all material items in the estimate shall be assigned to a material class that corresponds to its associated PPI (Producer Price Index) escalation index. Producer Price Index classifications are maintained by the U.S. Department of Labor, Bureau of Labor Statistics and are available on the Bureau’s website, http://www.bls.gov/ppi/.

Different classes of material that represent a significant portion of the estimate may be subject to different market volatility and should be escalated using different rates. As part of this analysis, a material resource report by material class should be prepared and included with the estimate backup. Materials for which a specific escalation index is not available and are not a significant portion of the total material cost, may be assigned to a general escalation index, as long as a minimum of 80% of the total material cost in the estimate is assigned to a specific escalation index. Escalation for materials shall be based on data from a recognized provider of pricing data, such as Global Insight, or a similar service acceptable to the BEDC Cost Estimating Division. Forecast data must be updated at least annually but preferably quarterly, especially for critical materials. Updates shall be obtained to correspond with the anticipated duration of the project or for the period in which the materials are expected to be purchased by the contractor.

Material escalation shall also be analyzed using the proposed construction schedule. Different material and equipment items may require different escalation factors, depending on the anticipated purchase date. For instance, long-lead time specialty equipment will typically be purchased by the contractor shortly after

3-13 Cost Estimating Manual June 2008 receiving a Notice to Proceed. In this case, the estimated cost for the equipment does not need to be escalated past this date. Other materials may be subject to escalation throughout the duration of the project. For example, ready-mix concrete prices are typically subject to escalation at least annually, even if the contractor has committed to the entire concrete required for the work at the beginning of the project.

Material escalation shall be shown as separate line items on the estimate summary sheet, one line per escalation percentage, and the supporting calculations shall be included in the Basis of Estimate Report (see Chapter 4 – Estimate Outputs). Labor Escalation If available, labor rates should be escalated based on future increases included in the appropriate union labor agreements. If this information is not available or if contracts will expire prior to the scheduled end of the project, forecasts of labor rate increases prepared by a recognized industry forecast service (e.g Global Insight) should be used. Escalation should be based on an estimate of the number of manhours that will be expended during each wage period, typically annually.

Labor escalation shall be shown as a separate line item on the estimate summary sheet and the supporting calculations shall be included in the Basis of Estimate document (see Chapter 4 – Estimate Outputs). Escalating Composite Prices Where the estimate, or portions of the estimate, are not prepared at the line item detail level (for early estimates based on factoring or composite unit prices only), escalation should be calculated by decompos- ing the price to the same labor and material components that correspond to the escalation factors used in detail line item estimates. Completed estimates from historical projects should be used to facilitate the decomposition of the prices. A similar method should be used for escalating historical composite prices to current pricing.

Estimate Sections

All estimates should be structured with separate sections for each of the following major cost classifications: 1. Direct Costs 2. Indirect Project Costs 3. Add-ons 4. Contractor Markup 5. Contractor Bonds/Insurance 6. Project Contingency

3-14 Chapter 3 Estimate Preparation

Definitions for each of these cost classifications are shown below. Direct Costs Per AACE Recommended Practice 10S-90, direct costs are: “Costs of completing work that are directly attributable to its performance and are necessary for its completion. 1) In construction: the cost of installed equipment, material, labor and supervision directly or immediately involved in the physical construction of the permanent facility.”

Direct costs include all craft labor extending from the working foreman level down, that are directly as- sociated with the physical work activity. Non-working craft supervision above the working foreman level (general foreman, master mechanics, shop stewards, superintendents, etc.) and all other staff supervision should be included in indirect project costs.

All permanent materials (materials that become part of the completed facility/project) are included in direct costs. In addition, temporary materials/supplies that are directly associated with a physical work item are in- cluded in direct costs. Examples of temporary materials/supplies that are included in direct costs include: • Materials/supplies for concrete formwork • Concrete curing compound • Lumber and structural steel used for temporary supports and falsework • Shoring for a structure excavation and recovered when no longer needed

Temporary materials and supplies that are not directly associated with a physical work item are included in indirect project costs. Examples include: • Scaffolding/walkways used by all crafts for various work items • Temporary enclosures and heating for all crafts for various work items • Materials for a temporary bridge constructed for access to the site

Construction equipment that can be directly attributed to the physical work and assigned to the crew is considered a direct cost. Examples of equipment that should be in included in direct costs include: • Excavating equipment • Cranes assigned directly to a specific crew and used for a specific work activity • Compressors assigned to an individual crew

Examples of equipment that should be included in indirect project costs are: • Forklifts at a common staging facility that supports all work activities • Cranes (fixed and mobile) that support multiples crafts and work activities • Flatbed trucks used for general purposes • Centralized compressed air systems • Centralized temporary power facilities

3-15 Cost Estimating Manual June 2008

Indirect Project Costs AACE Recommended Practice 10S-90 defines indirect costs as; “Cost not directly attributable to the comple- tion of an activity.” In construction, all cost which do not become a final part of the installation, but which are required for the orderly completion of the installation and may include, but are not limited to, field adminis- tration, direct supervision, capital tools, startup costs, etc.” Indirect project costs are sometimes referred to as “general conditions costs”, “general expense costs”, “field overhead costs”, etc. For consistency, these costs should always be identified as “indirect project costs” in estimates prepared for BEDC.

Indirect project costs cannot be allocated to physical work items as they are either not related to the overall volume of work or cannot logically be allocated to any one physical work item. Essentially they are all project-related costs (other than bonds and insurance) that cannot be attributed directly to a physical work activity and generally include: • Mobilization/demobilization • Job-site staff (management, engineering, supervision, quality control, safety, support, etc.) • Temporary facilities and structures (offices, warehouses, safety/first-aid, tool sheds, fuel/repair facilities, etc.) • Temporary support facilities and utilities (barricades/fencing, parking/roadways, storage yards, signs, scaffolding, enclosures, etc.) • Temporary utilities (telephone, water, power, compressed air) • Job office expenses • Finance expenses

Not all indirect project costs will be incurred/expended at the project site. Depending on the size of the project and the contractor’s organization, some project-related functions may be performed at the contrac- tor’s home office (e.g. project controls, change order estimating, project accounting, etc.). Even though these functions are performed at the home office, since they are directly related to the project, they are still considered project-related costs and should be included in the estimate as indirect project costs.

Many indirect costs are one-time costs (mobilization/demobilization) or strictly time-related costs (e.g. rent of office trailers or security guards) and are independent of the volume of work performed during any given period. A comprehensive checklist of all potential indirect project costs to be included in the estimate can be found in Attachment 3-4 of this Manual.

Some indirect costs are very easily calculated as percentages of other costs and are therefore included in the “Add-ons” section of the estimate summary.

3-16 Chapter 3 Estimate Preparation

Add-Ons Add-ons are used in estimates to calculate costs of items that are typically a percentage of other costs. Sales tax as a percentage of materials in an example. Other examples include: • Small tools and supplies as a % of labor or as a dollar per manhour rate • Overtime as a percentage of labor cost • Subcontractor markup • Escalation

Add-ons are useful because they automatically recalculate the amount of the add-on if the cost on which it was based changed. They also allow quick recalculation of an estimate if the rate associated with the add-on changes (escalation increased from 6% to 8% for instance).

Add-ons can also be used to calculate contractor markup/profit, as well as bond, and revenue-related insurance costs. However, these costs should be shown in their respective sections and not in the add-ons section of the estimate summary. Contractor Markup An amount included in the contractor’s bid price in addition to all project-related direct and indirect costs to account for profit/fee and to cover a portion of the company’s home office overhead. Contractor Bonds/Insurance This estimate section includes the cost to provide payment and performance bonds as well as the revenue- based insurance (typically builders risk and general liability insurance). Worker’s compensation insurance should be included in the labor rates. Contingency Estimating contingency is included as a separate chapter to this Manual (Chapter 5 – Contingency).

3-17 Cost Estimating Manual June 2008

3-18 Chapter 3 Attachments

Attachment 3-1 Sample Wage Rate Calculation

ATTACHMENT 3-1 Attachment 3-1 Sample Wage RateSAMPLE Calculation WAGE RATE CALCULATION

Craft: United Brotherhood of Carpenters and Joiners Local: District Council of New York City and Vicinity Classification: Carpenter-Building Commercial Effective Dates: 10/1/2007 through 6/30/2008

Normal Work Hours per Day (A) 7 Average Weeks/Yr 52 Days per Week ( C ) 5 Hours per Year (A X B X C) 1820

ST Shift 1.5 OT 2.0 OT Hourly Wage $ 41.710 53.63 62.57 83.43 Taxable Wage $ 48.120 60.04 68.98 89.93

Fringe Benefits Fringe Calc. Method Percentage Welfare Fund Dollars per hour worked N/A $ 10.00 $ 10.00 10.00$ 10.00$ Pension Fund Dollars per hour worked N/A $ 9.81 $ 9.81 9.81$ 9.81$ Annuity Fund Dollars per hour worked N/A $ 6.60 $ 6.60 6.60$ 6.60$ A.J.R.E.I.F. Dollars per hour worked N/A $ 0.70 $ 0.70 0.70$ 0.70$ Vacation Dollars per hour worked N/A $ 6.41 $ 6.41 6.41$ 6.41$ Supplemental Dollars per hour worked N/A $ 0.04 $ 0.04 0.04$ 0.04$ Supplemental Pension Dollars per hour worked N/A $ 1.00 $ 1.00 1.00$ 1.00$ Int'l Brotherhood of Carpenters Dollars per hour worked N/A $ 0.06 $ 0.06 0.06$ 0.06$ NY DCC Labor/Management Dollars per hour worked N/A $ 0.20 $ 0.20 0.20$ 0.20$

Total Fringe $ 34.82 $ 34.82 34.82$ 34.82$

Wage Plus Fringe $ 76.53 $ 88.45 97.39$ 118.25$

Taxes & Insurance Taxable Wage Cap FICA/S.S. 6.200% Note 1 $ 2.98 $ 3.72 4.28$ 5.58$ FICA/Med 1.450% N/A $ 0.70 $ 0.87 1.00$ 1.30$ State U.I. 9.500% $ 8,500 /Year $ 0.44 $ 0.44 0.44$ 0.44$ Fed U.I. 0.800% $ 7,000 /Year $ 0.03 $ 0.03 0.03$ 0.03$ Workers Compensation 12.670% $ 750 /Week $ 2.72 $ 2.72 2.72$ 2.72$ WC Classification 5403 Total Taxes and Insurance $ 6.87 $ 7.78 8.47$ 10.07$

Total Hourly Rate $ 83.40 $ 96.23 105.86$ 128.32$

NOTES: 1) FICA cap not used in calculations. 2) Shift work (2nd and 3rd shift) rate based on 9 hours pay for 7 hours work. 3) 1.5 OT for weekday hours over 7 and all day Saturdays 4) 2.0 OT for Sundays and Holidays 1

ATTACHMENT 3-1 JUNE 2008 Attachment 3-1 Sample Wage Rate Calculation

2 Attachment 3-2 Sample Work Week Differential Calculations Attachment 3-2 Sample Work Week Differential Calculations

ATTACHMENT 3-2 SAMPLE WORK WEEK DIFFERENTIAL CALCULATIONS

Base Week Alt Week 1 Alt Week 2 Alt Week 3 Alt Week 4 Alt Week 5 Incidental overtime, 1- Single shift; 7-hrs/day; 5 hr/day; 7-hrs/day; 5 Single shift; 10-hrs/day; 5 2 shifts; 7-hrs/day; 5 3 shifts; 7-hrs/day; 5 2 shifts; 10-hrs/day; 5 days/wk days/wk days/wk days/wk days/wk days/wk Hrs/Wk Amt/Wk Hrs/Wk Amt/Wk Hrs/Wk Amt/Wk Hrs/Wk Amt/Wk Hrs/Wk Amt/Wk Hrs/Wk Amt/Wk Rate Description Ave Rate/Hr

Straight Time 83.4 35 2919 35 2919 35 2919 35 2919 35 2919 35 2919 Overtime-Day Shift 105.86 0 0 5 529.3 15 1587.9 0 0 0 0 15 1587.9 Straight Time-Middle Shift 96.23 0 0 0 0 0 0 35 3368.05 35 3368.05 35 3368.05 Overtime-Middle Shift 105.86 0 0 0 0 0 0 0 0 0 0 15 1587.9 Straight Time-Night Shift 96.23 0 0 0 0 0 35 3368.05 0 Overtime-Night Shift 105.86 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Total per Week 35 2,919.00 40 3,448.30 50 4,506.90 70 6,287.05 105 9,655.10 100 9,462.85

Average $/HR 83.4 86.21 90.14 89.82 91.95 94.63 Premium $/HR vs Base N/A 2.81 6.74 6.42 8.55 11.23 % premium vs. Base N/A 3.37% 8.08% 7.70% 10.25% 13.47%

1

ATTACHMENT 3-2 JUNE 2008 Attachment 3-2 Sample Work Week Differential Calculations

2 Attachment 3-3 Estimator Inputs

Attachment 3-3A Equipment In process plants, equipment is one of the most significant cost drivers and must therefore be identified and defined early in the design phase. In addition to being identified on the drawings, equipment must be defined using the followings: • Equipment List • Equipment Specifications

Equipment List

The equipment list should be started no later than the Class 4 estimate phase and updated as required throughout the remainder of design. At a minimum, the following equipment must be included on the equipment list: • All equipment shown on the Process Flow Diagrams and Process and Instrumentation Diagrams • All valves of >6-inches in diameter, gates, and meters • All equipment shown on the electrical Single-Line Diagrams • All equipment shown on HVAC schematics

The equipment list should include the item title, type of equipment, installation location, equipment number (from P&ID) drive type (rotating equipment), actuator type (for valves and gates) power requirements, key design criteria (size, dimensions, capacity, etc.), specification section, and P&ID Reference Sheet.

Minimum requirements for the Equipment List and Specifications for all equipment by estimate class are shown in the table below:

Es t i m a t e Eq u i p m e n t Li s t Co n t e n t s So u r ce o f Specifications Cl a s s (i n c l u d e a l l e q u i p m e n t s h o w n o n ) Pricing Da t a 5 Not started Not Started Historical data Budget quotes for major process Process Flow Diagrams Not Started 4 equipment; Historical data for others Completed P&ID’s Vendor budget quotes for all equip- Preliminary Electrical Single-Line Diagrams Draft 3 ment Partially- completed HVAC Schematics Completed P&ID’s Written quotations for major process Completed Electrical Single-Line Diagrams Final equipment; vendor budget quotes 2 Completed HVAC Schematics for all other Additional minor equipment Additional minor equipment (e.g. small sump Final 1 pumps)

1 Attachment 3-3 Estimator Inputs

Attachment 3-3B Earthwork

General

Depending on the particular scope of the project, earthwork can be a major cost driver in construction. Be- cause of the wide range of existing site conditions, soil types, groundwater, staging/phasing requirements, and construction methods/equipment, earthwork is also a major source of variability in estimates. In ad- dition, due to the potential for encountering unknown or unanticipated conditions, even after geotechnical investigations have been completed, earthwork represents a major risk factor.

Major Earthwork Work Packages

Work packages within the general “earthwork” classification can be grouped into three categories: • Mass Excavation & Fill/Site Preparation/Overlot Grading • Major Structure Excavation and Backfill (per structure) • Other (roadways, sitework finishes, etc.)

As the majority of the cost will typically be in the first two categories for treatment plant work, this section focuses on those categories only.

The “Mass Excavation/Site Preparation” work package includes all work required to adjust the site eleva- tions to approximate final grade (or lower if structure excavation will be wasted on site). “Major Structure Excavation and Backfill” includes the excavation/backfill specific to a given structure or area after the mass excavation has been performed. Excavation and backfill specific to other project elements (pipe, ductbank, small structures, etc) is included with each structure or element.

Excavation Production Table

To facilitate estimate review, an Excavation Production Table should be completed and included in the Basis of Estimate document for all major excavation estimates. The Excavation Production Table summarizes the quantities determined by the detailed excavation takeoff and documents the assumptions (method, crew, and productivity) for the major elements of the excavation estimate: • Excavate • Load and Haul • Place and Compact

Line items in the Excavation Production Table should be structured to allow the reviewer to determine where the excavation occurs, where the material is transported, excavation methods, placement/compac- tion methods, and associated production rates. Total quantity should be based on the amount to be excavated and/or fill required. Individual line item within the table represent quantities for separate areas or

2 Attachment 3-3 Estimator Inputs structures that will use the same methods, crew, production rates, haul distances, disposal methods, etc. For example, material that will be moved to a temporary stockpile location should be on a separate line item than material that will go straight to a permanent fill location, or be hauled to an offsite disposal area. Only quantities that use the same method, crew, disposition, and production rates should be on the same line.

The combination of the various methods for these elements will depend on a number of factors, including: • Distance between excavation site and spoil/stockpile site • Timing of excavation vs. backfill • Material type • Equipment availability

If material must disposed off-site, any required disposal/tipping fee per cubic yard or ton should be shown for each affected line. If the fee is on a per ton basis, the conversion from cubic yards should also be shown in this column.

Depending on the conditions, not all of the elements may be applicable to a given operation. For example, if the excavation for a small structure is performed by a backhoe that is able to simply sidecast the material which is later used for backfill at the same location, there may not be a load/haul component. In other cases, the excavator may be able to place the material directly in the hauler such that a separate loading operation is not required.

In cases where all three elements (excavate, load/haul, place/compact) are performed simultaneously and at the same rate, this could theoretically be considered as a single crew. In this case, individual crew members and equipment should still be assigned to each element to facilitate production analysis and review. Only in cases where the same piece of equipment performs multiple elements (such as a scraper operation) should the crews be combined.

Site conditions may require additional processing of the material in addition to the three typical operations (excavate, load/haul, place/compact). Additional operations may include: • Screening • Drill/Blast • Soil Conditioning • Disking/Drying • Mixing • Shoring / Soil Stabilization

These additional operations should be shown as separate line items in the Excavation Production Table, and since they represent “double handling” of the material, the quantities will be in addition to typical excavation quantities.

3 Attachment 3-3 Estimator Inputs

Support Operations

Many other items that are not necessarily driven by the excavation quantities must also be included in the earthwork estimate. These include: • Erosion Control • Haul road development • Haul road maintenance • Dust control • Stockpile maintenance • Weed control • Dewatering

Since these items may not be “quantity-driven” (not proportional to the excavation quantities) they will typically not be included in a unit price for excavation, and are not included in the Excavation Production Table.

Structure Excavation Table

A Structure Excavation Table should be created for all major structure excavation and backfill to document the assumptions made for quantity takeoffs (excavation depth, side slopes, side clearance, etc.), and to serve as a checklist to ensure all required elements have been included. For simply-shaped excavations, the table may also be used to perform the quantity takeoff. Quantities and assumptions generated by the Structure Excavation Table should be posted to the Excavation Production Table.

Quantity Determination for Each Estimate Class

Since earthwork represents a major cost driver, estimates should be prepared using the most detailed in- formation available. The minimum level of detail that should be used for each estimate class is summarized below.

Class 5 – Earthwork quantities can be assumed using a “go-by” design, historical data, or may be included in the capacity factor used to price the work.

Class 4 – Major earthwork quantities may be determined using the preliminary site grading and facility layout plans coupled with the hydraulic profile.

Class 3 – Major earthwork quantities can typically be finalized at this point. Preliminary quantities for other earthwork packages (roads, finishes) should be estimated at least at the assembly level.

Class 1/2 – All earthwork quantities should be finalized in the Class 2 estimate.

4 Attachment 3-3 Estimator Inputs

Attachment 3-3C Structural Concrete Structural concrete typically represents a significant cost driver for water and wastewater facilities. The percentage of the total cost associated with concrete will vary depending on the particular project scope. Where concrete will be a significant cost driver, the estimate should be based on the most detailed informa- tion available. Whenever possible, estimates for structural concrete should be based on detailed takeoffs, either from the design documents from the actual project, or documents from a similar facility (“go-by” design) adjusted to approximate the actual project.

Forced Takeoff for Structural Concrete

If details are not available, either from the design documents or “go-by” design documents, it may be necessary to use “forced takeoff” (cost estimating relationships) to calculate concrete quantities. Typically, there are two levels of forced takeoff: • Volume of concrete based on a project design parameter • Quantity of concrete-related components based on concrete volume

Components for Structural Concrete

Estimates done at line-item detail level should contain at a minimum the following components: • Concrete volume (cy) • Formwork (sf) • Shoring (cf) • Finishing (sf) • Reinforcing (tons) • Accessories – Waterstop (lf) – Embedded misc. metal, including anchor bolts (lbs) – Expansion/contraction joints (lf) – Vapor Barrier (sf) – Hardner / Sealer (sf) – Formliners – Admixtures – Keyways – Blockouts In addition to the components listed above, line items should be identified by the following categories: • Concrete by : – Strength/mix design – Placement method

5 Attachment 3-3 Estimator Inputs

• Buggy • Truck • Crane • Pumped – Assembly • Walls – Straight – Circular – Battered • Slab on Grade • Elevated Slabs – Suspended Formed – Slab on Metal Deck • Beams (if not integral with slabs) • Columns – Square – Round • Footings – Continuous – Pad • Equipment Pads • Stairs (cast in place concrete) • Curbs and Miscellaneous • Formwork by type – Walls • Gang • Handset • Straight • Circular • Battered – Elevated slabs – Slab on Grade • <12” • 12” to 24” • >24” (Raft Type) – Columns • Square • Round

6 Attachment 3-3 Estimator Inputs

– Beams (integral or non-integral) – Footings • Continuous • Pad – Stairs – Equipment pads – Curbs • Finishing by type – Horizontal • Float • Trowel – Vertical • Point and Patch • Sack Rub

Composite Prices

When details are not available to perform takeoff at the assembly or component level, composite prices may be generated. Composite prices per cubic yard of concrete are generated by using an average quantity for the various components, and pricing the average quantities with current labor and material rates. This composite cost is then extended against the concrete quantity to obtain the total cost.

Typical composite prices include: • Cost per cubic yard for all structural concrete, when quantities by assembly are not available. • Cost per cubic yard by assembly type.

Composite prices should be generated to allow calculation of all cost types (labor, permanent material, equipment, supplies, etc.) and man-hours. Also, because of the possibility of large swings in material prices, concrete and reinforcing steel should be itemized separately for all estimates (i.e., even though a composite price is used to generate costs, the quantity and cost of reinforcing steel should be broken out separately). If composite prices are used, the supporting calculations and pricing should be included in the Basis of Estimate documents.

Assemblies

In order to facilitate scope and pricing reviews, concrete takeoffs and estimates should be performed and summarized by the following assemblies (WBS Level 4). Small/insignificant quantities may be summarized in the “other” assembly category. Large/significant quantities may require an additional designation. Total and unit costs should be shown at the assembly level, with cubic yards as the unit.

7 Attachment 3-3 Estimator Inputs

Takeoff/Estimating Requirements by Estimate Class

Target requirements for concrete takeoff and pricing are listed below for each estimate class. These are the targeted requirements and whenever possible, revert to the following preferences: • Detailed takeoff of all components (DTO) • Detailed takeoff of volume and formwork; forced takeoff (FTO) of remaining components based on concrete volume

Es t i m a t e Ta r g e t Li n e It e m De t a i l Ta k e o f f m e t h o d Pricing Me t h o d Cl a s s 5 Total CY of Concrete Forced takeoff of total volume Composite cost/cy 4 CY of Concrete by Assembly Force takeoff of volume by assembly Composite cost/cy by assembly 3 See table below See table below See table below

1 a n d 2 Complete line item detail for Detailed takeoff of all components Line item pricing for all all components components

Class 3 Vo l u m e / Re i n f o r c i n g Acce s s o r i e s / As s e m b ly Pl a ce m e n t Fo r m w o r k Fi n i s h i n g St ee l De t a i l s Quantity Pricing Quantity Pricing Quantity Pricing Quantity Pricing Quantity Pricing Slab on Grade DTO DTO DTO lbs/CY FTO/CY Walls DTO DTO DTO lbs/CY FTO/CY Elevated Slabs DTO DTO DTO lbs/CY FTO/CY Beams DTO DTO DTO lbs/CY FTO/CY Columns DTO DTO DTO lbs/CY FTO/CY Column Footings DTO DTO DTO lbs/CY FTO/CY Continuous Footings DTO DTO DTO lbs/CY FTO/CY Stairs FTO Comp In Comp In Comp In Comp In Comp In Comp In Comp In Comp In Comp Pipe Supports FTO Comp In Comp In Comp In Comp In Comp In Comp In Comp In Comp In Comp Equipment Pads FTO Comp In Comp In Comp In Comp In Comp In Comp In Comp In Comp In Comp Other/Miscellaneous FTO Comp In Comp In Comp In Comp In Comp In Comp In Comp In Comp In Comp

8 Attachment 3-3 Estimator Inputs

Attachment 3-3D Electrical Electrical systems typically represent a significant cost in treatment plant construction. Because the electri- cal design is highly dependent on the process design and especially the equipment selection, the input available for estimating the electrical systems typically lags behind other disciplines. Accordingly, early estimates must rely more heavily on cost estimating relationships and/or “go-by” designs. Electrical work in treatment plants generally falls into three major categories: • Process-related systems that supply power to the major process equipment • Building and site services (lighting, receptacle power, etc.) • Communication and security systems

Horsepower of the process equipment is the cost driver for the process-related systems while the square footage of the buildings and facilities drives the other systems. Minimum required input and the associated estimating methodology for each class of estimate are listed below. See Appendix 2-1 for the input require- ments for electrical assemblies. Class 5 If “go-by” design information is not available for the Class 5 estimate, electrical systems may either be included in the capacity factor, or based on a cost estimating relationship (typically equipment-factored based on the anticipated horsepower of the equipment) and the square footage of the facilities. Class 4 At Class 4, the P&ID drawings are “advanced” and should show all process equipment and the preliminary equipment list should be available including all horsepower requirements. From this information, the total power requirements for each process area may be determined and cost estimating relationships or “go-by” design of electrical systems can be used for estimating purposes. In addition, the preliminary site plan and architectural floor plans are available for forced takeoffs of building and site electrical services (e.g. sight lighting). Class 3 At Class 3, the electrical single-line diagrams are advanced and any electrical systems not shown on the single-line diagrams should be noted in the Gap Analysis provided by the design team. Together with the mechanical, structural, and architectural floor plans, all of the process-related electrical systems and the majority of the remaining electrical systems can be estimated at line item detail by using assemblies (see Appendix for a list of assemblies). For the building/site services, and communications/security systems, forced takeoff on a square foot basis may be required to generate quantities for the assemblies. Class 2 and 1 At Class 2, all systems have at least a preliminary design available and all electrical should be estimated at a line-item level of detail with only minor adjustments required for the class 1 estimate.

9 Attachment 3-3 Estimator Inputs

Attachment 3-3E Process Piping Process piping is normally a significant cost item in treatment plant work and includes all piping shown on the P&ID drawings. It does not include plumbing (domestic water and sanitary waste piping). The majority of the cost for process piping will be around the process equipment as this is where the majority of the valves, fittings, and in-line devices are located. Complete P&ID (Process and Instrumentation Diagram) drawings are essential for accurate piping estimates.

Piping takeoffs should be organized and identified by system, service, and size within each process area. Process piping outside the battery limits of a given process area (typically identified as “yard piping”) should be included in the “General Site” area in the WBS.

Assemblies for process piping should include all valves and in-line devices as well as hangers, supports, and other ancillary items (nut/bolt sets, gaskets, fittings, etc.). Minimum required input and the associated estimating methodology for each class of estimate are listed below. Class 5 If “go-by” design information is not available for the Class 5 estimate, process piping may either be included in the capacity factor or based on a cost estimating relationship (typically equipment-factored based on the value or capacity of the equipment) in each process area. Class 4 At Class 4, the P&ID drawings are “advanced” and should show all process piping so takeoffs may be done from the P&ID drawings with estimated lengths and assumed fitting densities (number of elbows, tees, etc., per lineal foot of pipe). Any piping not shown on the P&ID drawings should be noted in the Gap Analysis provided by the design team. Class 3 P&ID drawings are complete at this point, so all process piping will be shown. In addition, most large diameter pipe will be shown on the mechanical plans and sections. Pipe not shown on the mechanical plans/sections may be estimated from the P&I drawings using the same methodology as for the Class 4 estimate. Class 2 AND 1 At Class 2, all large-bore process piping (4” diameter and greater) is shown on the mechanical drawings and complete takeoffs can be included in the estimate. Small-bore pipe (less than 4” diameter) may not be shown on the mechanical drawings so takeoff is performed using assumed routing, lengths, and fitting densities.

10 Attachment 3-3 Estimator Inputs

Attachment 3-3F Indirect Project Costs Indirect cost may be estimated as a percentage of direct cost for all projects with an estimated construction of less than $50M for all estimate classes and for all project greater than $50M for class 5 and 4 estimates. For projects greater than $50M or with construction schedules that exceed 24 months, a detailed estimate of Indirect Project Cost should be performed using the checklist included in Attachment 3-4.

Since many of the Indirect Project Costs are time-related, the anticipated construction schedule should be used when estimating these costs. Personnel costs represent a major portion of the time-related Indirect Project Cost, and the average and peak staff manpower on site also drives other costs such as office space requirements, relocation and per-diem cost, etc. On all projects over $50M, a personnel schedule should be included as part of the Basis of Estimate document. For each individual, the schedule should indicate: • Anticipated start date • Anticipated completion date • Relocation required (yes/no) • Per diem required (yes/no) • Vehicle (yes/no) • Cell phone (yes/no) • Personal computer (yes/no)

The personnel may be done in a spreadsheet or by other means, but should be capable of calculating the total months or weeks for each individual, and the average and peak manpower.

11 Attachment 3-3 Estimator Inputs

12 Attachment 3-4 Indirect Project Costs Checklist

Attachment 3-4 Indirect ProjectATTACHMENT Costs 3 - Checklist4 INDIRECT PROJECT COSTS CHECKLIST Phase Item Description Unit 100.100 Project Management 20 PROJECT MANAGEMENT (RECURRING) wk 21 Project Executive wk 22 Project Manager wk 23 Assistant Project Manager wk 24 Construction Manager wk 25 Assistant Construction Manager wk 29 Risk Manager wk 100.110 Field Engineering 20 FIELD ENGINEERING (RECURRING) ls 21 Senior Project Engineer wk 22 Project Engineer wk 23 Field Engineer wk 24 Detailer/Draftsman wk 25 Geotechnical Engineer wk 26 wk 27 wk 28 Mechanical Engineer wk 29 Electrical - I & C Engineer wk 100.115 Surveying 20 SURVEYING (RECURRING) wk 21 Survey Crew Chief wk 22 Survey Crew wk 100.120 Field Supervisory Staff 20 FIELD SUPERVISORY STAFF (RECURRING) wk 21 General Superintendent wk 22 Project (or Area) Superintendent wk 23 Assistant Project Superintendent wk 24 Civil Superintendent wk 25 Concrete Superintendent wk 26 Mechanical Superintendent wk 27 Electrical - I & C Superintendent wk 100.125 Operations 30 OPERATIONS (STARTUP) wk 31 Lead Operator wk 32 Operator wk 100.130 Project Controls 20 PROJECT CONTROLS (RECURRING) wk 21 Project Controls Engineer wk 22 Project Scheduler wk 23 Document Control Engineer wk 100.135 Project Accounting Staff 20 PROJECT ACCOUNTING STAFF (RECURRING) wk 21 Project Accounting wk 100.140 Project Safety Personnel 20 PROJECT SAFETY PERSONNEL (RECURRING) wk 21 Safety Manager wk 22 Assistant Safety Manager wk

1 Attachment 3-4 June 2008 Attachment 3-4 Indirect Project Costs Checklist ATTACHMENT 3 - 4 INDIRECT PROJECT COSTS CHECKLIST 100.150 Project Admin Staff 20 PROJECT ADMIN STAFF (RECURRING) wk 21 Office Manager wk 22 Project Coordinator wk 23 Project Secretary wk 24 Time Keeper wk 25 Runner wk 100.160 Quality Control Staff 20 QUALITY CONTROL STAFF (RECURRING) wk 21 QA Manager wk 22 QA Inspector wk 23 Civil Inspector wk 24 Mechanical Inspector wk 25 Concrete Inspector wk 26 Building Inspector wk 27 Electrical Inspector wk 29 Construction Materials Technician wk 100.170 Estimating 20 ESTIMATING (RECURRING) wk 21 Chief Estimator wk 22 Lead Estimator wk 23 Civil Estimator wk 24 Mechanical Estimator wk 25 Concrete Estimator wk 26 wk 27 Electrical Estimator wk 100.180 Procurement 20 PROCUREMENT (RECURRING) wk 21 Procurement Manager wk 22 Purchasing Agent wk 100.190 Laborers 20 LABORERS (RECURRING) wk 21 General Purpose Laborers wk 22 Carpenters wk 23 Pipefitters wk 24 Operators wk 25 wk 100.195 Other Project Staff 20 OTHER PROJECT STAFF (RECURRING) wk 21 Security wk 22 Traffice Control wk 23 Interns wk 100.200 Community Service 10 COMMUNITY SERVICE (SETUP) ls 11 Community Service Programs ls 12 Community Outreach ls

Attachment 3-4 June 2008

2 Attachment 3-4 Indirect Project Costs Checklist ATTACHMENT 3 - 4 INDIRECT PROJECT COSTS CHECKLIST 100.400 Travel & Living Expense 10 "ONE TIME" TRAVEL & LIVING EXPENSE (SETUP) ls 11 Relocation Expenses (Billable) ls 12 Moving Expense (Billable) ls 13 En route Expense (Billable) ls 14 Other One Time Expenses (Billable) ls 20 TRAVEL & LIVING EXPENSE (RECURRING) ls 21 Living Allowance mo 22 Auto Rental mo 23 Motel & Hotel mo 24 Airline trip 25 Travel Expenses mo 29 Management Travel mo 60 TRAVEL & LIVING EXPENSE (NON-BILLABLE) ls 61 Relocation (Non-Billable) ls 62 Moving Expenses (Non-Billable) ls 63 En route Expenses (Non-Billable) ls 64 Other One Time Expenses (Non-Billable) ls 65 Living Allowance(Non-Billable) mo 66 Auto Rental(Non-Billable) mo 67 Motel & Hotel(Non-Billable) mo 68 Airline(Non-Billable) trip 69 Travel Expenses(Non-Billable) mo 100.600 Bonds 10 PERFORMANCE & PAYMENT BONDS (SETUP) ls 11 Performance Bonds ls 12 Payment Bonds ls 100.700 Insurance Charges 10 MONTHLY LIABILITY INSURANCE CHARGE (SETUP) ls 11 Professional Liability (E & O) Insurance ls 12 Construction Liability Insurance ls 13 Owner's Protective Liability Insurance ls 14 Railroad Protective Insurance ls 15 Pollution Insurance ls 16 Marine/Offshore Insurance ls 17 Builder's Risk Insurance ls 60 MISC CHARGES (NON-BILLABLE) ls 61 Monthly Liability Insurance Charge (Non-Billable) ls 62 Temp Living ls 63 Project Differential ls 64 Recruiting ls 100.800 Taxes 70 TAXES (MISC COST) ls 71 Gross Receipts Tax ls 72 Owner Tax ls 73 Wage Tax ls

Attachment 3-4 June 2008

3 Attachment 3-4 Indirect Project Costs Checklist ATTACHMENT 3 - 4 INDIRECT PROJECT COSTS CHECKLIST 101.060 Regulatory Requirements 10 REGULATORY REQUIREMENTS (SETUP) ls 11 Building Permits ls 12 Electric Permits ls 13 Plumbing Permits ls 14 Temporary Dewatering Permit ls 15 Sprinkler System Permit ls 16 Fire Alarm Hook up Permit ls 17 Street Cut Permits ls 18 Other Project Specific Permits ls 19 Other Project Specific Permits ls 101.065 Health & Safety 10 HEALTH & SAFETY (SETUP) ls 11 Health & Safety Plan ls 40 HEALTH & SAFETY (FIELD COST) ls 41 Safety Awards ls 42 Safety Equipment & Materials mo 46 First Aid Kit ea 48 Fall Protection Harness ea 49 Confined Space Rescue System ea 101.066 Temporary Protection 40 TEMPORARY PROTECTION (FIELD COST) ls 41 Temporary Partitions lf 42 Guard Rails lf 56 23 Temporary Barricades 43 Debris & Personnel Nets sf 44 Temporary Stairs/Ladders/Covers ea 56 29 Temporary Protective Walkways 45 Portable Ventilation Blowers (explosion proof) ea 46 Fire Extinguishers ea 47 Safety Signs/Barracades ea 56 33 Temporary Security Barriers Temporary Security Enclosures 48 54 23 Scaffolding & Platforms sf 101.400 Quality Control 40 QUALITY CONTROL (FIELD COST) ls 41 Soil Testing ls 42 Material Testing ls 43 Concrete Testing ls 44 Project Specific Testing (non-start up) ls 45 Project Specific Testing (non-start up) ls 46 Project Specific Testing (non-start up) ls 47 Project Specific Testing (non-start up) ls 48 Project Specific Testing (non-start up) ls 49 Project Specific Testing (non-start up) ls 101.450 Start Up Testing 30 START UP TESTING (STARTUP) ls 31 Water Quality Testing ls

Attachment 3-4 June 2008

4 Attachment 3-4 Indirect Project Costs Checklist ATTACHMENT 3 - 4 INDIRECT PROJECT COSTS CHECKLIST 101.505 Mobilization 10 MOBILIZATION (SETUP) ls 11 Site Trailers Set Up ls 12 Phone System Set Up ls 13 LAN Set Up ls 50 DEMOBILIZATION (CLOSEOUT) ls 51 Site Trailers Tear Down ls 52 Phone System Tear Down ls 53 LAN System Tear Down ls 54 Access Roads Removal ls 101.510 Temporary Utilities 10 TEMPORARY UTILITIES (SETUP) ls 11 Telephone Line Installation ls 12 Cell Phone Set Up ls 13 Cable Installation ls 14 51 13 Electric Power Supply Line Installation ls 15 Gas Line Installation ls 16 Drinking Water Line Installation ls 17 Construction Water Line Installation ls 18 Sanitary Line Installation ls 19 51 16 Fire Protection Installation ls 19.1 51 23 Temporary HVAC Installation 20 TEMPORARY UTILITIES (RECURRING) mo 21 Telephone Monthly Charge mo 22 Cell Phone/Pager Monthly Charge mo 23 Cable Monthly Charge mo 24 Electrical Monthly Power Charge mo 25 Gas Monthly Charge mo 26 Drinking Water/Ice Monthly Charges mo 27 Construction Water Monthly Charges mo 28 Fuel Oil Monthly Charge mo 29 Heat/Cooling Monthly Charge mo 50 TEMPORARY UTILITIES (CLOSEOUT) ls 51 51 33 Telephone Line Disconnect & Remove ls 52 Cell Phone Disconnect ls 53 Cable Disconnect & Remove ls 54 Electric Power Supply Line Disconnect & Remove ls 55 51 29 Gas Line Disconnect & Remove ls 56 Drinking Water Line Disconnect & Remove ls 57 Construction Water Line Disconnect & Remove ls 58 Sanitary Line Disconnect & Remove ls 59 Fire Protection Disconnect & Remove ls 101.520 Security 20 SECURITY (RECURRING) wk 101.530 Protect Exist Facilities 10 PROTECTION OF EXISTING FACILITIES (SETUP) ls 11 56 39 Protection of Trees ls 20 PROTECTION OF EXISTING FACILITIES (RECURRING) ls

Attachment 3-4 June 2008

5 Attachment 3-4 Indirect Project Costs Checklist ATTACHMENT 3 - 4 INDIRECT PROJECT COSTS CHECKLIST 101.532 Site Condition Surveys 10 SITE CONDITION SURVEYS (SETUP) ls 11 Survey ls 12 Video Survey ls 13 Photographs ls 20 SITE CONDITION SURVEYS (RECURRING) mo 21 Monthly Surveys mo 40 SURVEYS (FIELD COST) ls 50 SITE CONDITION SURVEYS (CLOSEOUT) ls 51 Survey ls 52 Video Survey ls 53 Photographs ls 101.535 Settlement Monitoring 20 SETTLEMENT MONITORING (RECURRING) wk 101.540 Progress Documentation 20 MONTHLY PROGRESS DOCUMENTATION (RECURRING) wk 21 Progress Photos wk 22 Progress Videos wk 40 SPECIAL INSPECTIONS (FIELD COST) ls 101.550 Site Access & Storage 10 SITE ACCESS AND STORAGE (SETUP) ls 11 55 13 Access Roads Construct ls 55 16 Haul Routes 55 19 Temporary Parking 55 23 Temporary Roads 55 26 Traffic Control 55 29 Staging Areas 53 13 Temporary Bridges 53 16 Temporary Decking 53 19 Temporary Overpasses 53 23 Temporary Ramps 53 26 Temporary Ramps (check description) 40 SITE ACCESS AND STORAGE (FIELD COST) ls 41 Road Maintenance ls 42 Snow Removal ls 43 Street Sweeping ls 101.560 Temp Environ Controls 10 TEMPORARY ENVIRONMENTAL CONTROLS (SETUP) ls 11 Waste Management Plan ls 20 TEMPORARY ENVIRONMENTAL CONTROLS (RECURRING) mo 21 Dumpster Pickups mo 22 Recycle Pickups mo 40 TEMPORARY ENVIRONMENTAL CONTROLS (FIELD COST) ls 41 56 26 Temporary Chain Link Fence lf 56 13 Temporary Air Barriers 42 56 16 Dust Barriers sf 43 56 19 Noise Barriers sf 44 Pollution Control ls 45 51 26 Lighting System ls

Attachment 3-4 June 2008

6 Attachment 3-4 Indirect Project Costs Checklist ATTACHMENT 3 - 4 INDIRECT PROJECT COSTS CHECKLIST 101.565 Weather Protection 40 WEATHER PROTECTION (FIELD COST) mo 41 Winter Conditions mo 42 Heating Equipment mo 43 Winter Heat Fuel mo 44 Temp Enclosures ls 45 Ground Covers ls 101.570 SWPPP 10 STORM WATER POLLUTION PREVENTION PLAN (SET UP) ls 20 STORM WATER POLLUTION PREVENTION PLAN (RECURRING) mo 57 13 Temporary Erosion and Sediment Control 57 16 Temporary Pest Control 57 19 Temporary Environmental Controls 57 23 Temporary Storm Water Pollution Controls 101.575 Hoisting / Staging 40 HOISTING/STAGING (FIELD COST) mo 41 54 16 Hoisting Costs mo 42 Staging Costs mo 54 13 Temporary Elevators 101.580 Project Sign 10 PROJECT SIGN (SETUP) ls 58 13 Temporary Project Signage 58 16 Temporary Interior Signage 101.585 Construction Equipment 40 CONSTRUCTION EQUIPMENT (FIELD COST) mo 41 Small tools mo 42 Truck & Tools mo 43 Fork Lift (Rough Terrain) mo 44 Crane mo 45 Loader mo 46 Compressor mo 47 Generator mo 49 Survey Equipment mo 101.586 Fuels & Maintenance 40 FUELS & MAINTENANCE (FIELD COST) mo 41 Fuels - Gas mo 42 Fuels - Diesel mo 43 Maintenance of Equipment mo 101.590 Field Offices 20 FIELD OFFICES (RECURRING) mo 21 51 13 MWH Constructors Office Trailer mo 22 Owners Office Trailer mo 23 Oversight Office Trailer mo 24 Change Room/Lunch Room Trailer mo 25 Supply Trailer/Container mo 26 51 13 Tool Shed mo 27 Decon Trailer mo 28 51 19 Chemical Toilet mo

Attachment 3-4 June 2008

7 Attachment 3-4 Indirect Project Costs Checklist ATTACHMENT 3 - 4 INDIRECT PROJECT COSTS CHECKLIST 101.591 Field Office Equipment 10 FIELD OFFICE EQUIPMENT (SETUP) ls 11 Copy Machine purchase ea 12 Fax Machine Purchase ea 13 Personal Computer purchase ea 14 Printers purchase ea 15 Software Licenses purchase ls 16 Furniture purchase ls 20 FIELD OFFICE EQUIPMENT (RECURRING) mo 21 Copy Machine Lease/Rental mo 22 Fax Machine Lease/Rental mo 23 Personal Computer Lease/Rental mo 24 Printers Lease/Rental mo 25 Software Charges ls 26 Furniture Lease/Rental mo 101.592 Field Office Services 20 FIELD OFFICE SERVICES (RECURRING) mo 21 Office Supply mo 22 Janitorial Service mo 23 Printing & Photocopies Service mo 24 Postage & Fed Ex mo 25 Courier mo 101.595 Project Vehicles 20 PROJECT VEHICLES (RECURRING) mo 21 Pick-Up Truck: Supervision mo 22 Pick-Up Truck: Job mo 25 Golf Cart mo 29 Automobile mo 101.600 Prod/Matl/Equip/Subst's 40 PRODUCTS, MATERIALS, EQUIPMENT AND SUBSTITUTIONS (FIELD COST) ls 41 Equipment Unloading ls 42 Equipment Storage ls 43 Off Load Misc Deliveries ls 101.610 Owner-Furnished Equipment 40 OWNER-FURNISHED EQUIPMENT (FIELD COST) ls 101.650 Test/Disinfect Structures 30 TEST & DISINFECT CONCRETE AND STEEL WATER STRUCTURES (STARTUP) ls 101.655 Gravity Pipeline Testing 30 GRAVITY PIPELINE TESTING (STARTUP) ls 101.656 Pressure Pipe Test/Disinf 30 PRESSURE PIPE TESTING AND DISINFECTION (STARTUP) ls 101.657 Pneumatic Struct Testing 30 PNEUMATIC STRUCTURE TESTING (STARTUP) ls 101.658 TV Inspect Sewers 30 TELEVISION INSPECTION OF SEWERS (STARTUP) ls

Attachment 3-4 June 2008

8 Attachment 3-4 Indirect Project Costs Checklist ATTACHMENT 3 - 4 INDIRECT PROJECT COSTS CHECKLIST 101.660 Equip Test/Plant Startup 30 EQUIPMENT TESTING AND PLANT STARTUP (STARTUP) ls 31 Chemicals for Start-Up ls 32 Utilities for Start-Up ls 33 Temporary Process Facilites ls 34 Solids Handling & Disposal ls 101.670 Owner Staff Training 30 OWNER STAFF TRAINING (STARTUP) ls 101.700 Project Closeout 50 PROJECT CLOSEOUT (CLOSEOUT) ls 51 Record Drawings ls 52 Punchlists ls 53 Final Cleaning ls 54 Closeout Submittals ls 101.800 Maintenance 50 MAINTENANCE (CLOSEOUT) ls 51 Operations & Maintenance Manual ls

Attachment 3-4 June 2008

9 Attachment 3-4 Indirect Project Costs Checklist

10 Estimate Output Chapter 4

Chapter 4 Estimate Output

Chapter 4 Estimate Output

Chapter 4 – Estimate Output

Basic Estimate Reports

It is imperative that estimating reports be delivered to BEDC in a consistent format to facilitate review by the BEDC Cost Estimating Division. This section describes the desired format of estimate submittals to BEDC. Each of the estimating reports to be submitted by the estimating team at each estimating interval is described below and examples of each are contained in Attachment 4-1 of this Manual.

1. Summary Reports – summarized to the following WBS Levels (one line per summary level): 1a. WBS Level 1 Summary Report (Attachment 4-1A) 1b. WBS Level 2 Summary Report (Attachment 4-1B) Summary reports should include the following columns: • WBS Level • Labor Manhours • ”Amount” columns for: – Labor – Equipment – Material – Subcontracts – Other – Total • Percentage of Total (optional)

2. Scope Review Reports 2a. Scope Review Report - organized by Assembly showing all cost types, summarized to WBS Level 5 (Work Package), sorted by Area/Process/System/Work Package/Assembly and with the following columns (See Attachment 4-1C):

• Sort Level (to delineate • Labor Cost/Unit • Subcontract Cost/Unit sort/subtotal levels) • Labor Amount • Subcontract Amount • Notes • Equipment Cost/Unit • Other Cost/Unit • Takeoff Quantity • Equipment Amount • Other Amount • Unit Of Measure • Material Cost/Unit • Total Cost/Unit • Labor Manhours • Material Amount • Total Amount

4-1 Estimate Output June 2008

2b. Scope Review Report - with Line Item Detail using same format as above with estimate line (See Attachment 4-1D). NOTE: this is an optional report to BEDC and only required if requested by the Cost Estimating Division. This report can be submitted as part of the estimate review package, or a single copy can be available at the scope review meeting with the project team. Alternately, this level of detail may be reviewed during the review meeting with a live copy of the estimate “on-screen” using a laptop computer and screened projection.

3. Labor/Productivity and Pricing Reports 3a. Labor/Productivity Detail Report Organized by Assembly. This report is used for review of con- tent and labor productivity/pricing within assemblies (See Attachment 4-1E). The report is sorted by assembly with line item detail for the items within the assembly. Like assemblies are combined in this report (quantities and amounts for like assemblies are combined into a single assembly). Columns as shown below:

• Assembly/ • Estimated Productivity • Material Cost/Unit Database Level 2 • Labor Cost/Unit • Material Amount • Item Description • Labor Amount • Subcontract Cost/Unit • Database Level 3 • Equipment Cost/Unit • Subcontract Amount • Takeoff Quantity • Equipment Amount • Other Price • Unit Of Measure • Material Conversion Factor • Other Cost/Unit • Crew • Material Waste (yes/no) • Other Amount • Labor Manhours • Material Waste % • Total Cost/Unit • Base Productivity • Material Quantity • Total Amount • Productivity Adjustment • Material Price

3b. Labor/Productivity Detail Report (Item). This report is used for review of labor pricing, labor productivity, and material pricing of individual estimate line items (See Attachment 4-1F). The report is sorted by Database Level 3/Database Level 2 with like items combined (items of the same work scope and same production rate combined into a single line item; quantities and amounts represent the total of all like items). Columns as shown below:

• Database Level 2/3 • Labor Rate Table • Material Tax (yes/no) • Item Description • Labor Amount • Subcontract Cost/Unit • Takeoff Quantity • Equipment Cost/Unit • Subcontract Amount • Unit Of Measure • Equipment Amount • Other Price • Crew • Material Conversion Factor • Other Cost/Unit • Labor Manhours • Material Waste (yes/no) • Other Amount • Base Productivity • Material Waste % • Other Tax (yes/no) • Productivity Adjustment • Material Quantity • Total Cost/Unit • Estimated Productivity • Material Price • Total Amount

• Labor Cost/Unit • Material Cost/Unit • Labor Price • Material Amount

4-2 Chapter 4 Estimate Output

4. Labor and Equipment Resource Reports 4a. Labor Resource Report organized by labor classification (See Attachment 4-1G). One line per labor classification with columns for: • Description of Labor Classification • Manhours • Labor Amount ($) • Average $/Manhour Total labor amount for the report should be equal to the total labor amount on the summary sec- tion of the various estimate reports noted previously. Average $/Manhour for each labor classification should be compared to the labor rate listing in the basis of estimate report to make sure the rates are consistent.

4b. Equipment Resource Report organized by piece of equipment (See Attachment 4-1H). One line per piece of equipment with columns for: • Description of equipment • Total equipment hours • Equipment Amount ($) • Average $/Equipment-Hour The total equipment amount for the report should be equal to the total equipment amount on the summary section of the various estimate reports noted above. Average $/Equipment-Hour Manhour should be compared to the labor rate listing in the basis of estimate report to make sure the rates are consistent. In addition, this report may be used to make an “equipment adjustment”. This may be necessary when certain pieces of equipment may be required on the site, but not fully utilized. The hours for the piece of equipment may need to be adjusted to a “time-phased” basis in lieu of the total hours utilized in the estimate.

Basis of Estimate Report

In addition to the estimate reports noted above, all estimates prepared at each stage in the project develop- ment with a value over $25M shall include a comprehensive Basis of Estimate Report (BOE) Report. The Report must be prepared in accordance with AACE Recommend Practice 34R-05 Basis of Estimate as modified herein. A copy of the document is included as Attachment 4-2 of this Manual or may be obtained at http://www.aacei.org/tcm/. Specific requirements for BOE Reports prepared for BEDC are detailed below. In some cases, the recommendations in AACE 34R-05 have been adopted and quoted in whole.

The BOE Report communicates the rationale, assumptions, pricing sources, and other inputs to the estimat- ing process used by the team in development of the cost estimate. This document consolidates information prepared from multiple sources which are used to establish the basis of the cost forecast. Each BOE Report shall address the topics, as applicable, described in this section. If there are no applicable items for the section, of if for any reason the section does not apply, the section heading should still be included in the document, and the text should read “NONE”, or “N/A” (not applicable).

4-3 Estimate Output June 2008

Project Scope Description Provide a brief narrative describing the major project components. The section should generally be limited to no more than one page.

Estimating Methodology Indicate the primary estimating methodology used to prepare the cost estimate. Where different method- ologies were used for major elements of the estimate or different work packages, give a brief description of each, organized by WBS. Identify the percentages of the total direct cost wherein the quantities were determined by the various estimating methods. These percentages can be determined by running an estimate report sorted by the Quantity Source Code as defined in Chapter 3.

1) Detailed takeoff off design drawings 2) “Forced” takeoff from partially complete design drawings 3) Takeoff from a “go-by” design (design drawings from a previously-designed facility similar in size in nature) 4) Factored using a cost estimating relationship 5) Assumed by estimator (no drawings or cost estimating relationship available)

Estimate Classification Identify the AACE estimate classification for the entire estimate based on the quality of the design documents used to prepare the estimate and the estimating methods used. Where different elements of the estimate fall within different AACE classifications, the estimate should only be assigned to a given classification if at least 75% of the estimated cost is supported by scope definition and estimating methodologies falling within that classification. If the completed estimate does not meet the criteria for the AACE estimate class as further defined in this Manual required by the corresponding life-cycle stage, identify the reasons and/or justification why the estimate does not meet the specified class.

Design Basis Reference all documents provided to the estimating team to convey the scope of the project. As a minimum, the following documents should be referenced in the BOE and attachments provided where noted:

• Updated log of all reports, design drawings, specifications, equipments lists, and other design informa- tion used in preparing the estimate. Typically this list should be prepared and kept up to date by the design team. • Compare the required design content summarized in Attachment 2-2 (see Chapter 2) to the actual design content delivered to the estimating team. Include comments of the completeness and adequacy of the documents for the class of estimate proposed. • If material take-off’s (MTO’s) are provided to the estimating team, identify specifically who developed the MTO’s and the methodology used. Also a summary of these quantities as an attachment to the BOE. • Gap Analysis including disposition of the items by the estimating team (Attachment).

4-4 Chapter 4 Estimate Output

• Meeting minutes of the Pre-Estimate Preparation Meeting and any additional meetings held with the project team during estimate preparation and review. Planning Basis Include a brief description of the contracting and procurement plan/strategy provided to the estimating team by the project team. The plan should include any provisions for pre-purchase of equipment or materials by the Owner or Owner’s agent, use of specialized construction equipment, modularization, etc.

Identify key project milestones, both those supplied to the estimating team by other members of the project team and those assumed by the project team. If multiple contracts are to be awarded, the dates for all contracts should be included. At a minimum, key milestones should include the anticipated dates for:

• Advertisement • Bid Date • Notice of Award • Begin Mobilization • Specified Contractual Interim Milestones • Substantial Completion Date • Final Completion Date • Start and completion of major phases of the work • Startup/commissioning of major systems • Other significant milestones in the construction schedule

Document and discuss scheduling assumptions used in preparing the schedule and estimate including but not limited to:

• Work-week schedule (hour worked per day, days worked per week, shifts worked per day, etc.) • Planned use of overtime • Provision for “incidental” overtime • Constraints on “seasonal” work due to temperature, inclement weather, assumptions for lost work days due to inclement weather, etc. • Identify which key work activities will be affected by the above

Reference and attach a copy of the construction schedule used to estimate the work. The schedule pro- vided to the estimating team with the project definition package for each estimate should be validated for logic and durations by the estimating team. List any recommended changes to the engineer’s proposed schedule based on the estimating effort.

4-5 Estimate Output June 2008

Cost Basis Identify and describe the cost basis, factors, and pricing sources for the following:

Material Pricing. Pricing sources for all major equipment and significant commodities shall be identi- fied. Include a Bill of Material report sorted by the Material Source Code and Material Class. Include any quotes for major equipment and significant commodities in the attachments. Discuss calculation of freight costs for any materials where freight is not included in the base price. If desired, freight may be included as an add-on cost (see Chapter 3). Labor and Equipment Rates. Calculation sheet documenting all wage and equipment rates used in- cluding craft rates, crew mix, equipment rates, etc. Include a crew detail report to identify the crew mix and a rate table report. Include all items included in the rates. For labor include the base rate, fringes, payroll taxes, workers compensation and other insurance. For equipment, include rental/depreciation rate and hourly operating cost). Labor Productivity. Discuss source of labor productivity rates used in the estimate (source of data- base, historical data, etc.) and source and rationale for any adjustment factors applied for each major Work Package. Include an estimate report sorted by Work Package (WBS Level 5) and Productivity Table to identify and quantify productivity adjustments included in the estimate. Indirect Cost. Pricing source and methodology for estimating project indirect costs. If the indirect costs are calculated by percentage, provide the rationale and identify the source Taxes and Duties. Identify all taxes and duties, including their rate and basis, included in the estimate. Escalation. Describe indices used, basis for application, to what items they were applied and the method of calculation (including duration). Contractor Markup/Profit. Discuss the basis for the contractor markup/profit used in the estimate, including the influence of local market conditions. Other Factors. Identify any unusual pricing factors or external influence that may have a significant impact on the project that are not described elsewhere in the report. Examples include: • Currency exchange rate for equipment/materials purchased outside the country. If currency ex- change rates were used to calculate portions of the estimate, list currency exchange fluctuations as a potential in the risk log. • Temporary surcharges • Price and productivity factors for an unusual location, restricted access, restricted work hours, etc.

Allowances Describe any allowances (per the definition below) included in the estimate, the amount of those allow- ances, and where they are included in the estimate. The definition of allowances from AACE 10S-90 and adopted by BEDC is as follows:

“Resources included in estimates to cover the cost of known but undefined requirements for an individual activity, work item, account or sub account. (6/07)” (emphasis added)

Do not include other items referenced in the allowance section of AACE RP 34-05 (material take-off allow- ance, overbuy allowances, congestion allowances, working allowances) as these do not fit the definition of allowances. These types of costs should be detailed in the cost section of the BOE document.

4-6 Chapter 4 Estimate Output

Assumptions Any assumptions made by the estimator but not documented elsewhere in the estimate basis should be included in this section. Assumptions should be grouped into two basic categories:

1. Scope. Assumptions made by the estimator where the design documents did not provide adequate detail to do a proper quantity take-off, site conditions not defined, etc. 2. Pricing. Assumptions that would affect pricing of materials, availability of labor, etc. Examples include adequate source of fill material located within 50 miles of the project site or adequate supply of labor without supplementing with resources from other areas. Add-Ons Include a report to show how all add-ons (see Chapter 3) have been applied (basis, range, etc.).

Exclusions In this section, the estimator should document all potential items of cost which a reviewer might associate with the project, but for which no costs have been included in the estimate. Asbestos abatement, removal of hazardous wastes, acquisition of land, taxes, financing costs, licensing costs, etc., are examples of potential items that need to be identified.

Exceptions The estimator should identify any anomalies or variances to the BEDC’s standard estimating practices.

Risks and Opportunities Any areas of the estimate containing significant risk or opportunity should be identified and itemized in this section. As a minimum, the project risk log should be attached to the BOE. For projects that require a complete risk analysis, the summary report should be attached to the BOE. See Chapter 5 – Contingency for additional details on estimating project risks.

Contingencies The methods used to determine the contingency amount should be described.

Reconciliation All BOE documents should reference and include as an attachment a reconciliation report WBS 2 level showing the previous estimate (estimate prepared at the previous stage of the project life cycle), the current estimate and the difference by cost type (labor, equipment, material, other, total). Additional reports at a lower WBS level may be necessary to highlight certain changes. Provide an overview of the major differ- ence between the current estimate and the last-published estimate.

If there are major differences between the current estimate, and the previous estimate, a detailed reconcilia- tion may be necessary. Detailed reconciliations should be organized by WBS and cover all aspects of proj- ect documentation (cost estimate, basis of estimate, schedule, and risks). In general, reconciliation should

4-7 Estimate Output June 2008 recognize or highlight specific changes in scope, basis of estimate, schedule, and risks. Identify the cost impact due to scope changes, pricing updates, labor productivity adjustments, estimate refinements, etc.

Estimate Quality Assurance Identify all estimate reviews that have taken place to date and any additional reviews that are proposed to take place subsequent to delivery to BEDC.

Estimating Team Include a list of the estimator responsible for each Work Package (WBS Level 5) in the estimate.

4-8 Chapter 4 Attachments

Attachment 4-1 Estimating Reports Attachment 4-1A WBS Level 1 Summary Report Sample Project Page 1 WBS Level 1 Summary Report 5/16/2008 12:25 AM

Spreadsheet Level Labor Man Hrs Labor Amount Material Amount Sub Amount Equip Amount Other Amount Total Amount Direct Costs 01 HW/OC Head Works / Odor Control 31,794 2,675,856 6,026,033 313,298 332,028 13,684 9,360,899 02 A Basin Aeration Basins 33,041 2,571,705 1,159,369 163,312 46,783 3,941,169 03 Memb/WAS Membrane System And WAS Piping 65,132 5,671,492 14,764,135 245,570 510,425 1,176,980 22,368,602 05 UV UV System 3,201 294,830 881,632 120,165 6,679 3,200 1,306,507 06 Recl. Pump Reclaimed Pumping And Storage 17,470 1,330,471 2,393,653 2,592,438 929,660 100 7,246,322 07 Rej Pump Reject Pumping and Storage 10,031 687,293 421,434 1,787,617 828,256 3,724,600 10 Gen. Struct. General Site Structures 1,830 168,832 347,583 293,295 9,913 819,623 11 Elect. Bldg Electrical / Generator Building and Fuel System 7,387 707,564 1,357,473 5,348 2,070,385 12 Ops Bldg Operations and Maintenance Building 32,277 2,671,006 2,527,829 11,855 39,022 5,249,711 13 Blowers Blower Systems 27,817 2,389,273 5,716,757 247,265 12,731 3,542 8,369,568 14 Chem Storage Chemical Storage and Feed Systems 959 88,604 61,101 45 149,750 Direct Costs 230,939 19,256,926 35,656,998 5,616,850 2,832,072 1,244,289 64,607,135 Indirect Costs * unassigned * 163,200 11,692,249 185,685 72,740 2,015,840 13,966,514 Indirect Costs 163,200 11,692,249Sample Project 185,685 72,740 2,015,840 13,966,514 Page 2A WBS Level 1 Summary Report 5/16/2008 12:25 AM

Estimate Totals

Description Amount Totals Hours Rate Basis Percent of Total Labor 30,949,175 394,139 hrs 21.67% Material 35,656,998 24.97% Subcontract 5,802,535 4.06% Equipment 2,904,813 84,108 hrs 2.03% Other 3,260,129 2.28% 78,573,650 78,573,650 55.02 Small Tools & Supplies 1,547,459 5.00 % C 1.08% Incidental Overtime Allowance 1,547,459 5.00 % C 1.08% Overtime Allowance - 48 hr/wk 2,321,188 7.50 % C 1.63% Overtime Allowance - 60 hr/wk 3,094,918 10.00 % C 2.17% Overtime Allowance - 70 hr/wk 4,642,376 15.00 % C 3.25% Subcontractor OH&P 8,643,101 11.00 % C 6.05% Contractor Profit 15,714,730 20.00 % T 11.00% Contractor Bond & Insurance 3,142,946 4.00 % T 2.20% Project Contingency 23,572,095 30.00 % T 16.51% Total 142,799,922

THIS IS A SAMPLE REPORT TO ILLUSTRATE REPORT LAYOUT ONLY. QUANTITIES, RATES, MARKUPS, ETC. SHOULD NOT BE USED FOR ESTIMATING PURPOSES. NOT ALL PAGES OF THE REPORT ARE INCLUDED IN THIS SAMPLE.

1 Attachment 4-1 Estimating Reports

2 Attachment 4-1 Estimating Reports

Sample Project PagePage 1A 1 Attachment 4-1B WBS Level 2 SummaryWBS Level 2Report Summary Report 5/16/2008 12:26 AM

Spreadsheet Level Labor Man Hrs Labor Amount Material Amount Sub Amount Equip Amount Other Amount Total Amount Direct Costs 01 HW/OC Head Works / Odor Control Coarse Screening Coarse Screening 477 43,921 115,107 260 159,288 Common Systems 929 89,146 134,693 223,839 Fine Screening 310 29,027 67,892 220 97,140 Flow Measurement Flow Measurement 561 51,911 3,557,483 190 300 3,609,884 General/Buildings 19,769 1,571,803 804,285 312,998 329,893 12,712 3,031,690 Grit Removal 2,218 205,275 682,404 470 19 888,167 Odor Control Odor Control 7,530 684,773 664,170 300 995 653 1,350,891 01 HW/OC Head Works / Odor Control 31,794 2,675,856 6,026,033 313,298 332,028 13,684 9,360,899 02 A Basin Aeration Basins Activated Sludge 33,041 2,571,705 1,159,369 163,312 46,783 3,941,169 02 A Basin Aeration Basins 33,041 2,571,705 1,159,369 163,312 46,783 3,941,169 03 Memb/WAS Membrane System And WAS Piping Activated Sludge 2,084 189,166 319,908 85 509,159 General/Buildings 22,689 1,801,843 1,119,436 368,963 15,980 3,306,221 MBR Filtration 4,819 454,286 989,871 214,070 211 1,658,438 * unassigned * 35,541 3,226,198 12,334,920 31,500 141,165 1,161,000 16,894,783 03 Memb/WAS Membrane System And WAS Piping 65,132 5,671,492 14,764,135 245,570 510,425 1,176,980 22,368,602 05 UV UV System Disinfection 2,138 198,329 305,884 165 3,910 508,289 * unassigned * 1,063 96,501 575,748 120,000 2,769 3,200 798,218 05 UV UV System 3,201 294,830 881,632 120,165 6,679 3,200 1,306,507 06 Recl. Pump Reclaimed Pumping And Storage Reclaimed Pumping 17,470 1,330,471 2,393,653 2,592,438 929,660 100 7,246,322 06 Recl. Pump Reclaimed Pumping And Storage 17,470 1,330,471 2,393,653 2,592,438 929,660 100 7,246,322 07 Rej Pump Reject Pumping and Storage Reject Water 10,031 687,293 421,434 1,787,617 828,256 3,724,600 07 Rej Pump Reject Pumping and Storage 10,031 687,293 421,434 1,787,617 828,256 3,724,600 10 Gen. Struct. General Site Structures General/Buildings 296 21,766 180,556 291,274 9,913 503,509 Lift Station 199 18,981 11,104 205 30,290 Sitework 1,334 128,085 155,924 1,815 285,824 10 Gen. Struct. General Site Structures 1,830 168,832 347,583 293,295 9,913 819,623 11 Elect. Bldg Electrical / Generator Building and Fuel System Elect. Distribution 925 88,476 130,602 3,465 222,544 General/Buildings 6,462 619,087 1,226,871 1,883 1,847,841 11 Elect. Bldg Electrical / Generator Building and Fuel System 7,387 707,564 1,357,473 5,348 2,070,385 12 Ops Bldg Operations and Maintenance Building General/Buildings 32,277 2,671,006 2,527,829 11,855 39,022 5,249,711 12 Ops Bldg Operations and Maintenance Building 32,277 2,671,006 2,527,829 11,855 39,022 5,249,711 13 Blowers Blower Systems Activated Sludge 8,713 822,190 1,991,154 3,433 3,478 2,820,254 General/Buildings 15,888 1,275,209 1,290,769 182,833 600 3,542 2,752,953 * unassigned * 3,215 291,874 2,434,833 61,000 8,653 2,796,361 13 Blowers Blower Systems 27,817 2,389,273 5,716,757 247,265 12,731 3,542 8,369,568 14 Chem Storage Chemical Storage and Feed Systems Chemical Systems 959 88,604 61,101 45 149,750 14 Chem Storage Chemical Storage and Feed Systems 959 88,604 61,101 45 149,750 Direct Costs 230,939 19,256,926 35,656,998 5,616,850 2,832,072 1,244,289 64,607,135 Indirect Costs * unassigned * * unassigned * 163,200 11,692,249 185,685 72,740 2,015,840 13,966,514 * unassigned * 163,200 11,692,249 185,685 72,740 2,015,840 13,966,514 Indirect Costs 163,200 11,692,249 185,685 72,740 2,015,840 13,966,514

Estimate Totals 3 Attachment 4-1 Estimating Reports Sample Project Page 2A WBS Level 2 Summary Report 5/16/2008 12:26 AM

Estimate Totals

Labor 30,949,175 394,139 hrs 21.67% Material 35,656,998 24.97% Subcontract 5,802,535 4.06% Equipment 2,904,813 84,108 hrs 2.03% Other 3,260,129 2.28% 78,573,650 78,573,650 55.02 Small Tools & Supplies 1,547,459 5.00 % C 1.08% Incidental Overtime Allowance 1,547,459 5.00 % C 1.08% Overtime Allowance - 48 hr/wk 2,321,188 7.50 % C 1.63% Overtime Allowance - 60 hr/wk 3,094,918 10.00 % C 2.17% Overtime Allowance - 70 hr/wk 4,642,376 15.00 % C 3.25% Subcontractor OH&P 8,643,101 11.00 % C 6.05% Contractor Profit 15,714,730 20.00 % T 11.00% Contractor Bond & Insurance 3,142,946 4.00 % T 2.20% Project Contingency 23,572,095 30.00 % T 16.51% Total 142,799,922

THIS IS A SAMPLE REPORT TO ILLUSTRATE REPORT LAYOUT ONLY. QUANTITIES, RATES, MARKUPS, ETC. SHOULD NOT BE USED FOR ESTIMATING PURPOSES. NOT ALL PAGES OF THE REPORT ARE INCLUDED IN THIS SAMPLE.

4 Attachment 4-1 Estimating Reports

Sample Project Page 1 Attachment 4-1C Scope Review Report Summarized to AssemblyScope Review Report Summarized to Assembly 5/15/2008 7:46 PM

Takeoff Labor Man Labor Labor Equip Material Material Sub Other Other Total Spreadsheet Level Notes Equip Cost/Unit Sub Cost/Unit Total Cost/Unit Quantity Hrs Cost/Unit Amount Amount Cost/Unit Amount Amount Cost/Unit Amount Amount Direct Costs 01 HW/OC Head Works / Odor Control Coarse Screening Coarse Screening Bar Screen Division 11 Equipment Equipment Vendor 11A-e Equipment 1.00 ea 128.000 11,619.20 /ea 11,619 40.00 /ea 40 /ea /ea /ea 11,659.20 /ea 11,659 Equipment Vendor 128.000 11,619 40 11,659 Division 11 Equipment 128.000 11,619 40 11,659 Division 17 Instrumentation Instrumentation 16130-001 Conduit and Copper Wire Bar Screen 1 Instrum 180.00 lf 21.836 11.65 /lf 2,096 /lf 7.20 /lf 1,296 /lf /lf 18.85 /lf 3,392 16130-001 Conduit and Copper Wire Bar Screen 1 Instrum 180.00 lf 16.381 8.74 /lf 1,573 /lf 6.72 /lf 1,210 /lf /lf 15.46 /lf 2,783 16130-001 Conduit and Copper Wire Bar Screen 1 Instrum 90.00 lf 11.754 12.54 /lf 1,128 /lf 7.59 /lf 683 /lf /lf 20.12 /lf 1,811 17000-01 Transmitter 3/4" Transmitter Connection Bar Screen 1 Instrum 2.00 ea 25.890 1,242.72 /ea 2,485 /ea 3,819.65 /ea 7,639 /ea /ea 5,062.37 /ea 10,125 17000-10 Discrete 3/4" Instrument Connection Bar Screen 1 Instrum 2.00 ea 36.608 1,757.19 /ea 3,514 /ea 2,247.70 /ea 4,495 /ea /ea 4,004.89 /ea 8,010 17000-10 Discrete 3/4" Instrument Connection Bar Screen 1 Instrum 1.00 ea 12.204 1,171.58 /ea 1,172 /ea 1,383.71 /ea 1,384 /ea /ea 2,555.29 /ea 2,555 Instrumentation 124.673 11,969 16,707 28,676 Division 17 Instrumentation 124.673 11,969 16,707 28,676 Bar Screen 252.673 23,588 40 16,707 40,335 Flow Control Division 11 Equipment Process Mechanical 11A-e Equipment 1.00 ea 224.000 20,333.60 /ea 20,334 220.00 /ea 220 98,400.00 /ea 98,400 /ea /ea 118,953.60 /ea 118,954 Process Mechanical 224.000 20,334 220 98,400 118,954 Division 11 Equipment 224.000 20,334 220 98,400 118,954 Flow Control 224.000 20,334 220 98,400 118,954 Coarse Screening Coarse Screening 476.673 43,921 260 115,107 159,288 Common Systems Control System Division 17 Instrumentation Instrumentation 16001-011a Duct Bank - PVC Sch 40 or Sch 80 Conduit Fiber Optic 450.00 lf 41.110 8.77 /lf 3,947 /lf 1.70 /lf 765 /lf /lf 10.47 /lf 4,711 17000-20 - Cabinets Cabinets for instrumentation PLC-1 1.00 ea 154.130 14,796.48 /ea 14,796 /ea 19,422.11 /ea 19,422 /ea /ea 34,218.59 /ea 34,219 17000-20 - Cabinets Cabinets for instrumentation PLC-10V,11V 2.00 ea 178.660 8,575.68 /ea 17,151 /ea 8,019.62 /ea 16,039 /ea /ea 16,595.29 /ea 33,191 17000-20 - Cabinets Cabinets for instrumentation PLC-12V 1.00 ea 263.130 25,260.48 /ea 25,260 /ea 44,529.61 /ea 44,530 /ea /ea 69,790.09 /ea 69,790 Instrumentation 637.030 61,155 80,756 141,911 Division 17 Instrumentation 637.030 61,155 80,756 141,911 Control System 637.030 61,155 80,756 141,911 Eye Wash Division 17 Instrumentation Instrumentation 17000-10 Discrete 3/4" Instrument Connection Eye Wash 2.00 ea 16.048 770.31 /ea 1,541 /ea 1,388.24 /ea 2,776 /ea /ea 2,158.55 /ea 4,317 Instrumentation 16.048 1,541 2,776 4,317 Division 17 Instrumentation 16.048 1,541 2,776 4,317 Eye Wash 16.048 1,541 2,776 4,317 Gas Detection Division 17 Instrumentation Instrumentation 16130-001 Conduit and Copper Wire Gas Detection Instrumentation 170.00 lf 17.396 9.82 /lf 1,670 /lf 5.02 /lf 854 /lf /lf 14.85 /lf 2,524 16130-001 Conduit and Copper Wire Gas Detection Instrumentation 630.00 lf 72.600 11.06 /lf 6,970 /lf 6.65 /lf 4,190 /lf /lf 17.71 /lf 11,160 17000-01 Transmitter 3/4" Transmitter Connection Gas Detection Instru 7.00 ea 84.595 1,160.16 /ea 8,121 /ea 3,102.29 /ea 21,716 /ea /ea 4,262.45 /ea 29,837 17000-01 Transmitter 3/4" Transmitter Connection Odor Control II Inst 1.00 ea 18.000 1,728.00 /ea 1,728 /ea 4,675.00 /ea 4,675 /ea /ea 6,403.00 /ea 6,403 17000-10 Discrete 3/4" Instrument Connection Gas Detection Instru 7.00 ea 78.106 1,071.17 /ea 7,498 /ea 2,766.61 /ea 19,366 /ea /ea 3,837.78 /ea 26,864 17000-20 - Cabinets Cabinets for instrumentation Gas Detection Instrumentation 2.00 ea 4.830 231.84 /ea 464 /ea 179.61 /ea 359 /ea /ea 411.45 /ea 823 Instrumentation 275.527 26,451 51,160 77,611 Division 17 Instrumentation 275.527 26,451 51,160 77,611 Gas Detection 275.527 26,451 51,160 77,611 Common Systems 928.605 89,146 134,693 223,839 Fine Screening Fine Screen Drum Division 11 Equipment Process Mechanical 11A-e Equipment 1.00 ea 20.000 1,815.50 /ea 1,816 100.00 /ea 100 /ea /ea /ea 1,915.50 /ea 1,916 Process Mechanical 20.000 1,816 100 1,916 Division 11 Equipment 20.000 1,816 100 1,916 Division 17 Instrumentation Instrumentation 16130-001 Conduit and Copper Wire Fine Drum Screen Instruments 180.00 lf 24.366 13.00 /lf 2,339 /lf 8.00 /lf 1,441 /lf /lf 21.00 /lf 3,780 16130-001 Conduit and Copper Wire Fine Drum Screen Instruments 360.00 lf 41.825 11.15 /lf 4,015 /lf 7.63 /lf 2,746 /lf /lf 18.78 /lf 6,761

5 Sample Project Page 2 Attachment 4-1 Estimating Reports Scope Review Report Summarized to Assembly 5/15/2008 7:46 PM

Takeoff Labor Man Labor Labor Equip Material Material Sub Other Other Total Spreadsheet Level Notes Equip Cost/Unit Sub Cost/Unit Total Cost/Unit Quantity Hrs Cost/Unit Amount Amount Cost/Unit Amount Amount Cost/Unit Amount Amount

16130-001 Conduit and Copper Wire Fine Drum Screen Instruments 180.00 lf 19.784 10.55 /lf 1,899 /lf 6.68 /lf 1,203 /lf /lf 17.24 /lf 3,102 16130-001 Conduit and Copper Wire Fine Drum Screen Instruments 80.00 lf 10.284 12.34 /lf 987 /lf 2.77 /lf 221 /lf /lf 15.11 /lf 1,209 17000-01 Transmitter 3/4" Transmitter Connection Fine drum scr Instru 2.00 ea 26.130 1,254.24 /ea 2,508 /ea 3,907.62 /ea 7,815 /ea /ea 5,161.86 /ea 10,324 17000-10 Discrete 3/4" Instrument Connection Fine drum scr Instru 2.00 ea 35.108 1,685.19 /ea 3,370 /ea 1,960.46 /ea 3,921 /ea /ea 3,645.65 /ea 7,291 17000-10 Discrete 3/4" Instrument Connection Fine drum scr Instru 2.00 ea 3.048 146.31 /ea 293 /ea 68.24 /ea 136 /ea /ea 214.55 /ea 429 17000-10 Discrete 3/4" Instrument Connection Fine drum scr Instru 1.00 ea 2.024 194.30 /ea 194 /ea 1,113.24 /ea 1,113 /ea /ea 1,307.54 /ea 1,308 17000-10 Discrete 3/4" Instrument Connection Fine drum scr Instru 1.00 ea 1.954 187.58 /ea 188 /ea 1,389.42 /ea 1,389 /ea /ea 1,577.00 /ea 1,577 17000-10 Discrete 3/4" Instrument Connection Fine drum scr Instru 2.00 ea 9.248 443.91 /ea 888 /ea 352.96 /ea 706 /ea /ea 796.87 /ea 1,594 Instrumentation 173.771 16,682 20,692 37,374 Division 17 Instrumentation 173.771 16,682 20,692 37,374 Fine Screen Drum 193.771 18,498 100 20,692 39,290 Flow Control Division 11 Equipment Process Mechanical 11A-e Equipment 1.00 ea 116.000 10,529.90 /ea 10,530 120.00 /ea 120 47,200.00 /ea 47,200 /ea /ea 57,849.90 /ea 57,850 Process Mechanical 116.000 10,530 120 47,200 57,850 Division 11 Equipment 116.000 10,530 120 47,200 57,850 Flow Control 116.000 10,530 120 47,200 57,850 Fine Screening 309.771 29,027 220 67,892 97,140 Flow Measurement Flow Measurement Flow Control Division 15 Mechanical Process Mechanical 15A-e DI Mech Joint Pipe by LF - JSW Flow Measurement Piping 100.00 lf 183.000 166.12 /lf 16,612 0.45 /lf 45 278.08 /lf 27,808 /lf /lf 444.65 /lf 44,465 Process Mechanical 183.000 16,612 45 27,808 44,465 Division 15 Mechanical 183.000 16,612 45 27,808 44,465 Division 17 Instrumentation Instrumentation 16130-001 Conduit and Copper Wire Influent Channel Ins 360.00 lf 39.692 10.59 /lf 3,810 /lf 6.16 /lf 2,219 /lf /lf 16.75 /lf 6,029 16130-001 Conduit and Copper Wire Influent Channel Ins 360.00 lf 32.785 8.74 /lf 3,147 /lf 5.79 /lf 2,083 /lf /lf 14.53 /lf 5,230 17000-01 Transmitter 3/4" Transmitter Connection Influent Channel Ins 1.00 ea 23.345 2,241.12 /ea 2,241 /ea 5,503.57 /ea 5,504 /ea /ea 7,744.69 /ea 7,745 17000-01 Transmitter 3/4" Transmitter Connection Influent Channel Ins 1.00 ea 15.345 1,473.12 /ea 1,473 /ea 3,853.57 /ea 3,854 /ea /ea 5,326.69 /ea 5,327 Instrumentation 111.167 10,672 13,659 24,331 Division 17 Instrumentation 111.167 10,672 13,659 24,331 Flow Control 294.167 27,284 45 41,467 68,796 Sampling Division 11 Equipment Equipment Vendor 11A-e Equipment 1.00 ea 152.000 13,797.80 /ea 13,798 120.00 /ea 120 3,507,500.00 /ea 3,507,500 /ea 300.00 /ea 300 3,521,717.80 /ea 3,521,718 Equipment Vendor 152.000 13,798 120 3,507,500 300 3,521,718 Division 11 Equipment 152.000 13,798 120 3,507,500 300 3,521,718 Division 15 Mechanical Process Mechanical 15A-h Sample Piping Sample Piping 120.00 lf 45.040 34.07 /lf 4,089 0.21 /lf 25 5.62 /lf 674 /lf /lf 39.90 /lf 4,788 Process Mechanical 45.040 4,089 25 674 4,788 Division 15 Mechanical 45.040 4,089 25 674 4,788 Division 17 Instrumentation Instrumentation 17000-10 Discrete 3/4" Instrument Connection Influent Channel Ins 4.00 ea 70.216 1,685.19 /ea 6,741 /ea 1,960.46 /ea 7,842 /ea /ea 3,645.64 /ea 14,583 Instrumentation 70.216 6,741 7,842 14,583 Division 17 Instrumentation 70.216 6,741 7,842 14,583 Sampling 267.256 24,627 145 3,516,016 300 3,541,088 Flow Measurement Flow Measurement 561.423 51,911 190 3,557,483 300 3,609,884 General/Buildings Common Systems Division 03 Concrete FRP Concrete 0301- Headworks Concrete Equipment Headworks Concrete Equipment 1.00 ls 640.000 61,100.80 /ls 61,101 145,081.60 /ls 145,082 /ls /ls /ls 206,182.40 /ls 206,182 FRP Concrete 640.000 61,101 145,082 206,182 Division 03 Concrete 640.000 61,101 145,082 206,182 Common Systems 640.000 61,101 145,082 206,182 G/B-A-Substructure Division 03 Concrete FRP Concrete 0322- Wall Concrete (Dimensional Takeoff) Headworks Intermediate Channel & Drum 61.67 cy 1,163.787 1,542.44 /cy 95,117 /cy 324.46 /cy 20,009 /cy 10.00 /cy 617 1,876.90 /cy 115,743 Screen Area 0330- S-O-G Concrete (Rectangular) Headworks Lower Level Floors 433.46 cy 1,568.258 262.89 /cy 113,951 /cy 186.35 /cy 80,776 /cy 10.00 /cy 4,335 459.24 /cy 199,062 0330- S-O-G Concrete (Rectangular) Headworks Odor Control Exterior Slab 175.00 cy 623.650 261.68 /cy 45,794 /cy 175.09 /cy 30,641 /cy 10.00 /cy 1,750 446.77 /cy 78,185 0330- S-O-G Concrete (Rectangular) Headworks Odor Control BioScrubber & 39.85 cy 211.952 399.42 /cy 15,918 /cy 180.07 /cy 7,176 /cy 10.00 /cy 399 589.49 /cy 23,492 Carbon Absorber Pads

6 Sample Project Page 3 Scope Review Report Summarized to Assembly Attachment 4-1 Estimating5/15/2008 7:46 Reports PM

Takeoff Labor Man Labor Labor Equip Material Material Sub Other Other Total Spreadsheet Level Notes Equip Cost/Unit Sub Cost/Unit Total Cost/Unit Quantity Hrs Cost/Unit Amount Amount Cost/Unit Amount Amount Cost/Unit Amount Amount

0334- Suspended Slab Concrete (Dimensional Take-Off) Headworks Influent Channel Floors 51.39 cy 562.302 900.81 /cy 46,292 /cy 359.26 /cy 18,462 /cy /cy 1,260.06 /cy 64,753 0334- Suspended Slab Concrete (Dimensional Take-Off) Headworks Intermediate Channel and Drum 217.78 cy 1,974.375 736.55 /cy 160,404 /cy 323.87 /cy 70,531 /cy /cy 1,060.42 /cy 230,935 Screen Area Channel Floor FRP Concrete 6,104.326 477,476 227,594 7,100 712,170 Division 03 Concrete 6,104.326 477,476 227,594 7,100 712,170 G/B-A-Substructure 6,104.326 477,476 227,594 7,100 712,170 G/B-B-Shell Division 03 Concrete FRP Concrete 0322- Wall Concrete (Dimensional Takeoff) Headworks Grit Tanks Walls 228.89 cy 2,544.657 877.83 /cy 200,926 /cy 271.64 /cy 62,175 /cy 10.00 /cy 2,289 1,159.47 /cy 265,389 0322- Wall Concrete (Dimensional Takeoff) Headworks Wall in Mechanical Bar Screen 131.93 cy 2,788.718 1,733.89 /cy 228,746 /cy 316.37 /cy 41,738 /cy 10.00 /cy 1,319 2,060.26 /cy 271,804 Area 0326- Rectangle Column Concrete Headworks Columns 106.67 cy 1,706.873 1,309.92 /cy 139,724 /cy 269.89 /cy 28,788 /cy 10.00 /cy 1,067 1,589.81 /cy 169,578 0334- Suspended Slab Concrete (Dimensional Take-Off) Headworks Upper Level Grit Classifier Floor 93.75 cy 1,021.505 897.02 /cy 84,096 /cy 356.51 /cy 33,423 /cy 10.00 /cy 938 1,263.54 /cy 118,456 0334- Suspended Slab Concrete (Dimensional Take-Off) Headworks Elevated Slabs Near Mechanical 60.69 cy 641.764 868.38 /cy 52,698 /cy 353.26 /cy 21,437 /cy /cy 1,221.63 /cy 74,135 Screens and Influent Channels FRP Concrete 8,703.517 706,189 187,561 5,612 899,363 Division 03 Concrete 8,703.517 706,189 187,561 5,612 899,363 Division 04 Masonry Masonry 0412- 12" Block 12" CMU Infill 4,500.00 sf 913.500 15.85 /sf 71,342 /sf 11.69 /sf 52,625 /sf /sf 27.55 /sf 123,967 Masonry 913.500 71,342 52,625 123,967 Division 04 Masonry 913.500 71,342 52,625 123,967 Division 08 Doors and Windows Doors, Frames, & Hdw 0800- Hollow Metal Doors Basic Doors/Frames/Hardware 5.00 ea 56.000 945.39 /ea 4,727 /ea 1,620.00 /ea 8,100 /ea /ea 2,565.39 /ea 12,827 Doors, Frames, & Hdw 56.000 4,727 8,100 12,827 Division 08 Doors and Windows 56.000 4,727 8,100 12,827 G/B-B-Shell 9,673.017 782,258 248,286 5,612 1,036,157 G/B-C-Interiors Division 05 Metals Misc Metals 0532- Misc Metals Headworks Upper Level Metals 273.760 /lf 24,010 /lf /lf 174,939 /lf /lf /lf 198,949 0545- Headworks Exterior Metal Stairs Headworks Exterior Metal Stairs 2.00 ea 94.800 4,157.12 /ea 8,314 /ea 6,600.00 /ea 13,200 /ea /ea 10,757.12 /ea 21,514 Misc Metals 368.560 32,324 188,139 220,463 Division 05 Metals 368.560 32,324 188,139 220,463 Division 08 Doors and Windows Doors, Frames, & Hdw 0800- Hollow Metal Doors Basic Doors/Frames/Hardware 5.00 ea 32.000 540.22 /ea 2,701 /ea 800.00 /ea 4,000 /ea /ea 1,340.22 /ea 6,701 Doors, Frames, & Hdw 32.000 2,701 4,000 6,701 Division 08 Doors and Windows 32.000 2,701 4,000 6,701 Division 09 Finishes Protective Coatings 099 0- Headworks Interior Coatings Allowance 1.00 ls /ls /ls /ls 250,000.00 /ls 250,000 /ls 250,000.00 /ls 250,000 Protective Coatings 250,000 250,000 Division 09 Finishes 250,000 250,000 G/B-C-Interiors 400.560 35,025 192,139 250,000 477,164 G/B-D-Services Division 15 Mechanical Distribution Systems 15B-b HVAC Budget /lf /lf /lf /lf 60,000 /lf /lf 60,000 Distribution Systems 60,000 60,000 Domestic Water Dist. 15A-h UW System Utility Water System 320.00 lf 386.670 109.69 /lf 35,100 0.31 /lf 100 63.97 /lf 20,471 /lf /lf 173.97 /lf 55,671 Domestic Water Dist. 386.670 35,100 100 20,471 55,671 Energy Supply 15A-f Compressed Air Piping Compressed Air Piping 100.000 /lf 9,078 /lf 500 /lf 60,000 /lf /lf /lf 69,578 Energy Supply 100.000 9,078 500 60,000 69,578 Other Plumbing Sys. 15B-b HVAC Budget 200.000 /lf 18,155 /lf 1,000 /lf 20,000 /lf /lf /lf 39,155 Other Plumbing Sys. 200.000 18,155 1,000 20,000 39,155 Other Plumbing Syst. 15A-c PD System PD System 65.10 lf 89.000 124.10 /lf 8,079 /lf 138.94 /lf 9,045 /lf /lf 263.04 /lf 17,124 Other Plumbing Syst. 89.000 8,079 9,045 17,124 Sanitary Waste 15A-h Floor Drainage Floor Drainage 140.00 lf 63.960 41.47 /lf 5,806 0.07 /lf 10 32.57 /lf 4,560 /lf /lf 74.11 /lf 10,376 Sanitary Waste 63.960 5,806 10 4,560 10,376 Division 15 Mechanical 839.630 76,217 1,610 114,076 60,000 251,903 Division 16 Electrical Elect - Other Other Electrical Services

7 Attachment 4-1 Estimating Reports

Sample Project Page 28 Scope Review Report Summarized to Assembly 5/15/2008 7:46 PM

Estimate Totals

Description Amount Totals Hours Rate Basis Percent of Total Labor 30,949,175 394,139 hrs 21.67% Material 35,656,998 24.97% Subcontract 5,802,535 4.06% Equipment 2,904,813 84,108 hrs 2.03% Other 3,260,129 2.28% 78,573,650 78,573,650 55.02 Small Tools & Supplies 1,547,459 5.00 % C 1.08% Incidental Overtime Allowance 1,547,459 5.00 % C 1.08% Overtime Allowance - 48 hr/wk 2,321,188 7.50 % C 1.63% Overtime Allowance - 60 hr/wk 3,094,918 10.00 % C 2.17% Overtime Allowance - 70 hr/wk 4,642,376 15.00 % C 3.25% Subcontractor OH&P 8,643,101 11.00 % C 6.05% Contractor Profit 15,714,730 20.00 % T 11.00% Contractor Bond & Insurance 3,142,946 4.00 % T 2.20% Project Contingency 23,572,095 30.00 % T 16.51% Total 142,799,922

THIS IS A SAMPLE REPORT TO ILLUSTRATE REPORT LAYOUT ONLY. QUANTITIES, RATES, MARKUPS, ETC. SHOULD NOT BE USED FOR ESTIMATING PURPOSES. NOT ALL PAGES OF THE REPORT ARE INCLUDED IN THIS SAMPLE.

8 Attachment 4-1 Estimating Reports

Sample Project Page 1 Attachment 4-1D Scope Review Report Detailed Scope Review Report - Detailed 5/15/2008 7:53 PM

Takeoff Labor Man Labor Labor Equip Material Material Sub Other Other Total Spreadsheet Level Notes Equip Cost/Unit Sub Cost/Unit Total Cost/Unit Quantity Hrs Cost/Unit Amount Amount Cost/Unit Amount Amount Cost/Unit Amount Amount Direct Costs 01 HW/OC Head Works / Odor Control Coarse Screening Coarse Screening Bar Screen Division 11 Equipment Equipment Vendor 11A-e Equipment Barscreen System 16' Inc in 3.5MM Budget 2.00 ea 128.000 5,809.60 /ea 11,619 20.00 /ea 40 - - - - 5,829.60 /ea 11,659 Equipment 1.00 ea 128.000 11,619.20 /ea 11,619 40.00 /ea 40 /ea /ea /ea 11,659.20 /ea 11,659 Equipment Vendor 128.000 11,619 40 11,659 Division 11 Equipment 128.000 11,619 40 11,659 Division 17 Instrumentation Instrumentation 16130-001 Conduit and Copper Wire GRC 3/4" 180.00 lf 7.200 3.84 /lf 691 - - 1.13 /lf 203 - - - - 4.97 /lf 894 Rigid Conduit Hub 3/4" 4.00 E 1.000 24.00 /E 96 - - 4.87 /E 19 - - - - 28.87 /E 115 3/4" Cut & Thread 4.00 ea 0.600 14.40 /ea 58 - - 0.08 /ea 0 - - - - 14.48 /ea 58 Hole Punching For Enclosures-Gutter-Panels & Switchboards 3/4" 4.00 ea 1.200 28.80 /ea 115 ------28.80 /ea 115 GRC Elbow 3/4" 6.00 E 1.500 24.00 /E 144 - - 5.28 /E 32 - - - - 29.28 /E 176 GRC U-Channel Rigid Conduit Clamp 3/4" 23.00 E 0.920 3.84 /E 88 - - 0.61 /E 14 - - - - 4.45 /E 102 ThruWall Seal 3/4" 2.00 E 1.800 86.40 /E 173 - - 298.84 /E 598 - - - - 385.24 /E 770 Explosion Proof Male Sealoff 3/4" 4.00 E 1.800 43.20 /E 173 - - 18.68 /E 75 - - - - 61.88 /E 248 Explosion Proof Sealing Cement 1 Lb 4.00 E - - - - 15.29 /E 61 - - - - 15.29 /E 61 Explosion Proof Sealing Fibre 1 Oz 4.00 E - - - - 9.75 /E 39 - - - - 9.75 /E 39 Copper Wire XHHW Stranded #14 1,242.00 lf 3.726 0.29 /lf 358 - - 0.19 /lf 240 - - - - 0.48 /lf 598 Explosion Proof Female Union 3/4" 1.00 E 0.170 16.32 /E 16 - - 11.31 /E 11 - - - - 27.63 /E 28 #20 - #14 Wire termination 24.00 E 1.680 6.72 /E 161 ------6.72 /E 161 Wire Markers 24.00 E 0.240 0.96 /E 23 0.16 /E 4 1.12 /E 27 Conduit and Copper Wire Bar Screen 1 Instrum 180.00 lf 21.836 11.65 /lf 2,096 /lf 7.20 /lf 1,296 /lf /lf 18.85 /lf 3,392 16130-001 Conduit and Copper Wire GRC 3/4" 180.00 lf 7.200 3.84 /lf 691 - - 1.13 /lf 203 - - - - 4.97 /lf 894 Rigid Conduit Hub 3/4" 4.00 E 1.000 24.00 /E 96 - - 4.87 /E 19 - - - - 28.87 /E 115 3/4" Cut & Thread 4.00 ea 0.600 14.40 /ea 58 - - 0.08 /ea 0 - - - - 14.48 /ea 58 Hole Punching For Enclosures-Gutter-Panels & Switchboards 3/4" 4.00 ea 1.200 28.80 /ea 115 ------28.80 /ea 115 GRC Elbow 3/4" 3.00 E 0.750 24.00 /E 72 - - 5.28 /E 16 - - - - 29.28 /E 88 GRC U-Channel Rigid Conduit Clamp 3/4" 23.00 E 0.920 3.84 /E 88 - - 0.61 /E 14 - - - - 4.45 /E 102 ThruWall Seal 3/4" 2.00 E 1.800 86.40 /E 173 - - 298.84 /E 598 - - - - 385.24 /E 770 Explosion Proof Male Sealoff 3/4" 4.00 E 1.800 43.20 /E 173 - - 18.68 /E 75 - - - - 61.88 /E 248 Explosion Proof Sealing Cement 1 Lb 4.00 E - - - - 15.29 /E 61 - - - - 15.29 /E 61 Explosion Proof Sealing Fibre 1 Oz 4.00 E - - - - 9.75 /E 39 - - - - 9.75 /E 39 Computer Cable Individually Shielded 2-C #16 207.00 lf 0.621 0.29 /lf 60 - - 0.84 /lf 173 - - - - 1.13 /lf 233 Explosion Proof Female Union 3/4" 1.00 E 0.170 16.32 /E 16 - - 11.31 /E 11 - - - - 27.63 /E 28 #20 - #14 Wire termination 4.00 E 0.280 6.72 /E 27 ------6.72 /E 27 Wire Markers 4.00 E 0.040 0.96 /E 4 0.16 /E 1 1.12 /E 4 Conduit and Copper Wire Bar Screen 1 Instrum 180.00 lf 16.381 8.74 /lf 1,573 /lf 6.72 /lf 1,210 /lf /lf 15.46 /lf 2,783 16130-001 Conduit and Copper Wire GRC 3/4" 90.00 lf 3.600 3.84 /lf 346 - - 1.13 /lf 101 - - - - 4.97 /lf 447 Rigid Conduit Hub 3/4" 2.00 E 0.500 24.00 /E 48 - - 4.87 /E 10 - - - - 28.87 /E 58 3/4" Cut & Thread 2.00 ea 0.300 14.40 /ea 29 - - 0.09 /ea 0 - - - - 14.49 /ea 29 Hole Punching For Enclosures-Gutter-Panels & Switchboards 3/4" 2.00 ea 0.600 28.80 /ea 58 ------28.80 /ea 58 GRC Elbow 3/4" 3.00 E 0.750 24.00 /E 72 - - 5.28 /E 16 - - - - 29.28 /E 88 GRC U-Channel Rigid Conduit Clamp 3/4" 11.00 E 0.440 3.84 /E 42 - - 0.61 /E 7 - - - - 4.45 /E 49 ThruWall Seal 3/4" 1.00 E 0.900 86.40 /E 86 - - 298.84 /E 299 - - - - 385.24 /E 385 Explosion Proof Male Sealoff 3/4" 2.00 E 0.900 43.20 /E 86 - - 18.68 /E 37 - - - - 61.88 /E 124 Explosion Proof Sealing Cement 1 Lb 2.00 E - - - - 15.29 /E 31 - - - - 15.29 /E 31 Explosion Proof Sealing Fibre 1 Oz 2.00 E - - - - 9.75 /E 19 - - - - 9.75 /E 19 Copper Wire XHHW Stranded #14 828.00 lf 2.484 0.29 /lf 238 - - 0.19 /lf 160 - - - - 0.48 /lf 399 #20 - #14 Wire termination 16.00 E 1.120 6.72 /E 108 ------6.72 /E 108 Wire Markers 16.00 E 0.160 0.96 /E 15 0.16 /E 3 1.12 /E 18 Conduit and Copper Wire Bar Screen 1 Instrum 90.00 lf 11.754 12.54 /lf 1,128 /lf 7.59 /lf 683 /lf /lf 20.12 /lf 1,811 17000-01 Transmitter 3/4" Transmitter Connection Equipment "LIT" 2.00 E 2.000 96.00 /E 192 - - 1,650.00 /E 3,300 - - - - 1,746.00 /E 3,492 3/4" Explosionproof Flexible Conduit 4.00 E 3.000 72.00 /E 288 - - 287.24 /E 1,149 - - - - 359.24 /E 1,437 FSC Box 3/4" 2.00 E 0.600 28.80 /E 58 - - 11.10 /E 22 - - - - 39.90 /E 80 Weatherproof Plate for FS Box Single Receptacle 2.00 ea 0.160 7.68 /ea 15 - - 15.18 /ea 30 - - - - 22.86 /ea 46 Specification Grade Switch SP Gray 20a 2.00 E 0.300 14.40 /E 29 - - 16.99 /E 34 - - - - 31.39 /E 63 #12 Pigtail 2.00 E 0.040 1.92 /E 4 - - 0.74 /E 1 - - - - 2.66 /E 5 Copper Wire XHHW Stranded #12 40.00 lf 0.160 0.38 /lf 15 - - 0.28 /lf 11 - - - - 0.67 /lf 27 #12 - #10 Wire termination 12.00 E 0.840 6.72 /E 81 ------6.72 /E 81 Wire Markers 12.00 E 0.120 0.96 /E 12 0.16 /E 2 1.12 /E 13 Computer Cable Individually Shielded 2-C #16 10.00 lf 0.030 0.29 /lf 3 - - 0.84 /lf 8 - - - - 1.13 /lf 11 #20 - #14 Wire termination 8.00 E 0.560 6.72 /E 54 ------6.72 /E 54 Cable Markers 4.00 E 0.080 1.92 /E 8 0.18 /E 1 2.10 /E 8 SS Instrument stand List termination points 2.00 ea 12.000 576.00 /ea 1,152 - - 275.00 /ea 550 - - - - 851.00 /ea 1,702 Equipment "LE" 2.00 E 2.000 96.00 /E 192 - - 1,100.00 /E 2,200 - - - - 1,196.00 /E 2,392 Manufacture Cable (Furnished by Others) 2.00 ea 2.000 96.00 /ea 192 ------96.00 /ea 192 Equipment "YS" (Motion Switch) 2.00 E 2.000 96.00 /E 192 - - 165.00 /E 330 - - - - 261.00 /E 522 3/4" Transmitter Connection Bar Screen 1 Instrum 2.00 ea 25.890 1,242.72 /ea 2,485 /ea 3,819.65 /ea 7,639 /ea /ea 5,062.37 /ea 10,125 17000-10 Discrete 3/4" Instrument Connection Equipment "MV" (Motorized Valve "FBO & IBO") 2.00 E 2.000 96.00 /E 192 - - 55.00 /E 110 - - - - 151.00 /E 302 9 Sample Project Page 8 Attachment 4-1 Estimating Reports Scope Review Report - Detailed 5/15/2008 7:53 PM

Takeoff Labor Man Labor Labor Equip Material Material Sub Other Other Total Spreadsheet Level Notes Equip Cost/Unit Sub Cost/Unit Total Cost/Unit Quantity Hrs Cost/Unit Amount Amount Cost/Unit Amount Amount Cost/Unit Amount Amount

Instrumentation 17000-10 Discrete 3/4" Instrument Connection Equipment "MV" (Motorized Valve "FBO & IBO") 4.00 E 4.000 96.00 /E 384 - - 55.00 /E 220 - - - - 151.00 /E 604 3/4" Explosionproof Flexible Conduit 4.00 E 3.000 72.00 /E 288 - - 287.24 /E 1,149 - - - - 359.24 /E 1,437 Copper Wire XHHW Stranded #14 32.00 lf 0.096 0.29 /lf 9 - - 0.19 /lf 6 - - - - 0.48 /lf 15 Wire Markers 16.00 E 0.160 0.96 /E 15 0.16 /E 3 1.12 /E 18 #20 - #14 Wire termination 8.00 E 0.560 6.72 /E 54 ------6.72 /E 54 SS Instrument stand List termination points 4.00 ea 24.000 576.00 /ea 2,304 - - 275.00 /ea 1,100 - - - - 851.00 /ea 3,404 Equipment "ZS" (Postions Switch "FBO" & "IBO") 8.00 E 12.000 144.00 /E 1,152 - - 55.00 /E 440 - - - - 199.00 /E 1,592 Equipment "HS" (Hand Switch/Control Switch) 12.00 E 12.000 96.00 /E 1,152 - - 275.00 /E 3,300 - - - - 371.00 /E 4,452 Equipment "ZL" 8.00 ea 4.000 48.00 /ea 384 - - 55.00 /ea 440 - - - - 103.00 /ea 824 Heavy Duty One Unit Control Station NEMA 4 Open 4.00 ea 3.200 76.80 /ea 307 - - 85.80 /ea 343 - - - - 162.60 /ea 650 Heavy Duty One Unit Control Station NEMA 4 Close 4.00 ea 3.200 76.80 /ea 307 - - 103.38 /ea 414 - - - - 180.18 /ea 721 Heavy Duty One Unit Control Station NEMA 4 LOR 4.00 ea 4.000 96.00 /ea 384 - - 106.86 /ea 427 - - - - 202.86 /ea 811 3/4" Instrument Connection Influent Channel Ins 4.00 ea 70.216 1,685.19 /ea 6,741 /ea 1,960.46 /ea 7,842 /ea /ea 3,645.64 /ea 14,583 Instrumentation 70.216 6,741 7,842 14,583 Division 17 Instrumentation 70.216 6,741 7,842 14,583 Sampling 267.256 24,627 145 3,516,016 300 3,541,088 Flow Measurement Flow Measurement 561.423 51,911 190 3,557,483 300 3,609,884 General/Buildings Common Systems Division 03 Concrete FRP Concrete 0301- Headworks Concrete Equipment 100-Ton Crawler Crane 16.00 wk 640.000 3,818.80 /wk 61,101 7,450.80 /wk 119,213 ------11,269.60 /wk 180,314 Concrete Vibrators 32.00 wk - - 150.00 /wk 4,800 ------150.00 /wk 4,800 Air Compressors 16.00 wk - - 566.00 /wk 9,056 ------566.00 /wk 9,056 Generators 16.00 wk - - 750.80 /wk 12,013 ------750.80 /wk 12,013 Headworks Concrete Equipment Headworks Concrete Equipment 1.00 ls 640.000 61,100.80 /ls 61,101 145,081.60 /ls 145,082 /ls /ls /ls 206,182.40 /ls 206,182 FRP Concrete 640.000 61,101 145,082 206,182 Division 03 Concrete 640.000 61,101 145,082 206,182 Common Systems 640.000 61,101 145,082 206,182 G/B-A-Substructure Division 03 Concrete FRP Concrete 0322- Wall Concrete (Dimensional Takeoff) 4000 psi Concrete 61.67 cy - - - - 105.00 /cy 6,475 - - - - 105.00 /cy 6,475 Pump Place Walls 61.67 cy 50.690 53.93 /cy 3,325 ------10.00 /cy 617 63.93 /cy 3,942 Job Built with Plyform 4-8' 2,664.00 sf 793.872 26.17 /sf 69,716 1.79 /sf 4,755 - - - - 27.96 /sf 74,471 Strip & Oil Wall Forms 2,664.00 sf 45.288 1.07 /sf 2,845 ------1.07 /sf 2,845 Wall Bulkhead Forms 15.00 sf 6.450 37.76 /sf 566 2.10 /sf 32 - - - - 39.86 /sf 598 Horizontal Wall Keyway 4" 397.00 lf 9.925 2.20 /lf 872 0.42 /lf 167 - - - - 2.62 /lf 1,038 Vertical Wall Keyway 4" 345.00 lf 10.350 2.64 /lf 909 0.42 /lf 145 - - - - 3.06 /lf 1,054 Waterstop 9" Bulb 409.00 lf 12.270 1.89 /lf 771 - - 7.88 /lf 3,221 - - - - 9.76 /lf 3,992 Grind/Patch Walls 2,664.00 sf 66.600 1.57 /sf 4,184 - - 0.02 /sf 53 - - - - 1.59 /sf 4,238 Liquid Curing Compounds 2,664.00 sf 7.992 0.19 /sf 502 - - 0.03 /sf 70 - - - - 0.22 /sf 572 Finish- Top of Wall & Curb 277.50 sf 2.775 0.78 /sf 215 ------0.78 /sf 215 Wall Rebar 5.71 tn 114.100 1,356.60 /tn 7,739 - - 818.97 /tn 4,672 - - - - 2,175.57 /tn 12,412 Sandblast CJ's 277.50 sf 13.875 3.14 /sf 872 0.25 /sf 69 - - - - 3.39 /sf 941 Labor to Install Embedded Angle @ Top of Wall 222.00 lf 29.600 11.71 /lf 2,599 - - 1.58 /lf 350 - - - - 13.28 /lf 2,949 Wall Concrete (Dimensional Takeoff) Headworks Intermediate Channel & Drum 61.67 cy 1,163.787 1,542.44 /cy 95,117 /cy 324.46 /cy 20,009 /cy 10.00 /cy 617 1,876.90 /cy 115,743 Screen Area 0330- S-O-G Concrete (Rectangular) 4000 psi Concrete 433.46 cy - - - - 105.00 /cy 45,513 - - - - 105.00 /cy 45,513 Pump Place Slab on Grade 433.46 cy 270.911 41.00 /cy 17,773 ------10.00 /cy 4,335 51.00 /cy 22,107 Fine Grade SOG 7,802.25 sf 187.254 1.51 /sf 11,765 ------1.51 /sf 11,765 S.O.G. Edge Form > 1' 534.75 sf 117.645 19.32 /sf 10,331 1.31 /sf 702 - - - - 20.63 /sf 11,033 S-O-G Const Joints > 1' 975.00 sf 282.750 25.47 /sf 24,831 1.31 /sf 1,280 - - - - 26.78 /sf 26,110 Zip Strips 1/2" 650.00 lf 65.000 6.28 /lf 4,084 0.15 /lf 96 - - - - 6.43 /lf 4,180 Sealant At Sealant Grooves 650.00 lf 8.125 1.10 /lf 714 - - 1.05 /lf 683 - - - - 2.15 /lf 1,396 Strip & Oil SOG Form 1,509.75 sf 21.137 0.88 /sf 1,328 ------0.88 /sf 1,328 Waterstop 9" Bulb 650.00 lf 19.500 1.89 /lf 1,225 - - 7.88 /lf 5,119 - - - - 9.76 /lf 6,344 Rebar/Mesh Support - Bricks 928.00 ea 2.320 0.17 /ea 157 - - 0.26 /ea 244 - - - - 0.43 /ea 401 SOG Rebar 32.51 tn 406.363 847.88 /tn 27,564 - - 818.99 /tn 26,625 - - - - 1,666.86 /tn 54,188 Finish- Hard Trowel 7,802.25 sf 163.847 1.63 /sf 12,709 - - 0.04 /sf 312 - - - - 1.67 /sf 13,021 Liquid Curing Compounds 7,802.25 sf 23.407 0.19 /sf 1,471 - - 0.03 /sf 205 - - - - 0.22 /sf 1,675 S-O-G Concrete (Rectangular) Headworks Lower Level Floors 433.46 cy 1,568.258 262.89 /cy 113,951 /cy 186.35 /cy 80,776 /cy 10.00 /cy 4,335 459.24 /cy 199,062 0330- S-O-G Concrete (Rectangular) 4000 psi Concrete 175.00 cy - - - - 105.00 /cy 18,375 - - - - 105.00 /cy 18,375 Pump Place Slab on Grade 175.00 cy 102.942 38.59 /cy 6,753 ------10.00 /cy 1,750 48.59 /cy 8,503 Fine Grade SOG 3,150.00 sf 75.600 1.51 /sf 4,750 ------1.51 /sf 4,750 S.O.G. Edge Form > 1' 375.00 sf 82.500 19.32 /sf 7,245 1.31 /sf 492 - - - - 20.63 /sf 7,737 S-O-G Const Joints > 1' 337.50 sf 97.875 25.47 /sf 8,595 1.31 /sf 443 - - - - 26.78 /sf 9,038 Zip Strips 1/2" 225.00 lf 21.177 5.91 /lf 1,331 0.15 /lf 33 - - - - 6.06 /lf 1,364 Sealant At Sealant Grooves 225.00 lf 2.646 1.03 /lf 232 - - 1.05 /lf 236 - - - - 2.08 /lf 469 Strip & Oil SOG Form 712.50 sf 9.975 0.88 /sf 627 ------0.88 /sf 627 Rebar/Mesh Support - Bricks 393.00 ea 0.924 0.16 /ea 63 - - 0.26 /ea 103 - - - - 0.42 /ea 166 SOG Rebar 13.13 tn 154.412 798.00 /tn 10,474 - - 818.99 /tn 10,749 - - - - 1,616.99 /tn 21,223 Finish- Hard Trowel 3,150.00 sf 66.150 1.63 /sf 5,131 - - 0.04 /sf 126 - - - - 1.67 /sf 5,257

10 Sample Project Page 12 Scope Review Report - Detailed Attachment 4-1 Estimating5/15/2008 7:53 Reports PM

Takeoff Labor Man Labor Labor Equip Material Material Sub Other Other Total Spreadsheet Level Notes Equip Cost/Unit Sub Cost/Unit Total Cost/Unit Quantity Hrs Cost/Unit Amount Amount Cost/Unit Amount Amount Cost/Unit Amount Amount

PD System PD System 65.10 lf 89.000 124.10 /lf 8,079 /lf 138.94 /lf 9,045 /lf /lf 263.04 /lf 17,124 Other Plumbing Syst. 89.000 8,079 9,045 17,124 Sanitary Waste 15A-h Floor Drainage SWgt Pipe Single Hub 6" 80.00 lf 20.000 22.69 /lf 1,816 - - 25.85 /lf 2,068 - - - - 48.55 /lf 3,884 SWgt Pipe Single Hub 4" 60.00 lf 12.000 18.16 /lf 1,089 - - 13.69 /lf 821 - - - - 31.84 /lf 1,910 SWgt 90 Ell 4 5.00 ea 3.000 54.47 /ea 272 - - 26.25 /ea 131 - - - - 80.72 /ea 404 SWgt 90 Ell 6 4.00 ea 2.800 63.54 /ea 254 - - 45.70 /ea 183 - - - - 109.24 /ea 437 SWgt 45 Ell 4 4.00 ea 2.560 58.10 /ea 232 - - 20.50 /ea 82 - - - - 78.60 /ea 314 SWgt Wye 6 1.00 ea 1.400 127.09 /ea 127 - - 91.40 /ea 91 - - - - 218.49 /ea 218 SWgt Wye 6x4 6.00 ea 8.400 127.09 /ea 763 - - 61.75 /ea 371 - - - - 188.84 /ea 1,133 SWgt P Trap 4 4.00 ea 2.800 63.54 /ea 254 - - 43.15 /ea 173 - - - - 106.69 /ea 427 Floor Drain 4" 4.00 ea 9.000 204.25 /ea 817 - - 125.00 /ea 500 - - - - 329.25 /ea 1,317 6" Clean Outs 2.00 ea 2.000 90.78 /ea 182 5.00 /ea 10 70.00 /ea 140 - - - - 165.78 /ea 332 Floor Drainage Floor Drainage 140.00 lf 63.960 41.47 /lf 5,806 0.07 /lf 10 32.57 /lf 4,560 /lf /lf 74.11 /lf 10,376 Sanitary Waste 63.960 5,806 10 4,560 10,376 Division 15 Mechanical 839.630 76,217 1,610 114,076 60,000 251,903 Division 16 Electrical Elect - Other Other Electrical Services 16670-000 Lightning protection assembly Copper Air Terminal 8.00 E 8.000 96.00 /E 768 - - 99.46 /E 796 - - - - 195.46 /E 1,564 Copper Lightning protection cable 350.00 lf 12.250 3.36 /lf 1,176 - - 1.95 /lf 682 - - - - 5.31 /lf 1,858 Lightning protection arrester 1.00 E 1.200 115.20 /E 115 - - 99.46 /E 99 - - - - 214.66 /E 215 12" x 12" Rubber pad 124.67 E 12.467 9.60 /E 1,197 - - 0.99 /E 123 - - - - 10.59 /E 1,320 12" x 12" Cement paver 8.00 E 8.000 96.00 /E 768 - - 99.46 /E 796 - - - - 195.46 /E 1,564 GRC One Hole Steel Straps 1/2" 116.67 E 3.500 2.88 /E 336 - - 0.23 /E 27 - - - - 3.11 /E 363 Sch 80 PVC Conduit 1" Overhead/Surface 210.00 lf 7.350 3.36 /lf 706 - - 0.77 /lf 161 - - - - 4.13 /lf 867 GRC One Hole Steel Straps 1" 30.00 E 0.900 2.88 /E 86 - - 0.58 /E 17 - - - - 3.46 /E 104 Cadwelds 6.00 ea 3.000 48.00 /ea 288 - - 12.17 /ea 73 - - - - 60.17 /ea 361 Copper Lightning protection cable 252.00 lf 8.820 3.36 /lf 847 - - 1.95 /lf 491 - - - - 5.31 /lf 1,338 Roof penetration and Roof Jack 6.00 ea 13.200 211.20 /ea 1,267 - - 16.50 /ea 99 - - - - 227.70 /ea 1,366 Lightning Protection Certification 1.00 ls 4.000 384.00 /ls 384 - - - - 2,750.00 /ls 2,750 - - 3,134.00 /ls 3,134 Lightning protection assembly Lightning Protection 1.00 ea 82.687 7,937.92 /ea 7,938 /ea 3,365.21 /ea 3,365 2,750.00 /ea 2,750 /ea 14,053.13 /ea 14,053 Elect - Other Other Electrical Services 82.687 7,938 3,365 2,750 14,053 Electrical 16151-110 Ground loop Copper Wire Bare Stranded #4/0 450.00 lf 9.900 2.11 /lf 950 - - 4.56 /lf 2,054 - - - - 6.68 /lf 3,004 Site Ditching 6" x 36" 450.00 lf 4.500 0.96 /lf 432 - - 1.93 /lf 866 - - - - 2.89 /lf 1,298 Backfill per Cu/Yard 25.00 cy 12.500 48.00 /cy 1,200 - - 9.90 /cy 248 - - 57.90 /cy 1,448 Detectable Warning Tape 450.00 lf - - - - 0.17 /lf 77 - - - - 0.17 /lf 77 Ground Rod 3/4" x10' 8.00 E 6.400 76.80 /E 614 - - 9.50 /E 76 - - - - 86.30 /E 690 Driving Stud 3/4" 8.00 E 0.400 4.80 /E 38 - - 4.93 /E 39 - - - - 9.73 /E 78 Cadwelds 8.00 ea 4.000 48.00 /ea 384 - - 12.17 /ea 97 - - - - 60.17 /ea 481 Sch 80 PVC Conduit 1" 200.00 lf 6.000 2.88 /lf 576 - - 0.77 /lf 154 - - - - 3.65 /lf 730 Sch 80 PVC 90 Degree Elbow 1" 20.00 E 3.000 14.40 /E 288 - - 3.28 /E 66 - - - - 17.68 /E 354 PVC Terminal Adaptor 1" 20.00 E 1.600 7.68 /E 154 - - 0.29 /E 6 - - - - 7.97 /E 159 1 Pint PVC Cement 2.00 E 1.000 48.00 /E 96 - - 6.31 /E 13 - - - - 54.31 /E 109 Ground loop Building Ground 450.00 lf 49.300 10.52 /lf 4,733 /lf 7.66 /lf 3,447 0.55 /lf 248 /lf 18.73 /lf 8,428 Electrical 49.300 4,733 3,447 248 8,428 Division 16 Electrical 131.987 12,671 6,813 2,998 22,481 Division 17 Instrumentation Instrumentation 16001-011a Duct Bank - PVC Sch 40 or Sch 80 Conduit Sch 40 PVC Conduit 1" 250.00 lf 7.500 2.88 /lf 720 - - 0.39 /lf 98 - - - - 3.27 /lf 818 Plastic Coated Rigid Steel 90 Elbow 1" 2.00 E 0.700 33.60 /E 67 - - 10.86 /E 22 - - - - 44.46 /E 89 PVC Female Adaptor 1" 2.00 E 0.160 7.68 /E 15 - - 0.33 /E 1 - - - - 8.01 /E 16 Plastic Coated Rigid Steel Conduit 1" 20.00 lf 1.200 5.76 /lf 115 - - 3.36 /lf 67 - - - - 9.12 /lf 182 Plastic Coated Rigid Steel Coupling 1" 4.00 E 0.280 6.72 /E 27 - - 3.47 /E 14 - - - - 10.19 /E 41 1" Cutting & Threading PVC Coated 2.00 ea 0.600 28.80 /ea 58 - - 0.22 /ea 0 - - - - 29.02 /ea 58 1 Pint PVC Cement 2.50 E 1.250 48.00 /E 120 - - 6.30 /E 16 - - - - 54.30 /E 136 Tie Wire (50' roll) 2.50 ea 2.500 96.00 /ea 240 - - 8.80 /ea 22 - - - - 104.80 /ea 262 #3 Re-bar 200.00 ea 2.000 0.96 /ea 192 - - 0.20 /ea 40 - - - - 1.16 /ea 232 Copper Wire XHHW Stranded #14 500.00 lf 1.500 0.29 /lf 144 - - 0.19 /lf 97 - - - - 0.48 /lf 241 #20 - #14 Wire termination 4.00 E 0.280 6.72 /E 27 ------6.72 /E 27 Wire Markers 4.00 E 0.040 0.96 /E 4 0.16 /E 1 1.12 /E 4 Duct Bank - PVC Sch 40 or Sch 80 Conduit Eye Wash 250.00 lf 18.010 6.92 /lf 1,729 /lf 1.51 /lf 377 /lf /lf 8.42 /lf 2,106 Instrumentation 18.010 1,729 377 2,106 Division 17 Instrumentation 18.010 1,729 377 2,106 G/B-D-Services 989.627 90,617 1,610 121,265 62,998 276,489 G/B-G-Sitework Division 02 Earthwork 02B-200 Headworks Site Preparation Caterpillar CP-323C Vibratory Soil Compactor w/ Operator 8.00 hr 8.000 84.69 /hr 678 29.32 /hr 235 ------114.01 /hr 912 Caterpillar 938G Wheel Loader & Operator 16.00 hr 16.000 90.08 /hr 1,441 47.70 /hr 763 ------137.78 /hr 2,204 Dump Truck 14 cy 16.00 hr 16.000 74.72 /hr 1,196 48.53 /hr 776 ------123.25 /hr 1,972 Caterpillar 236 Skid Steer Loader w/ Operator 16.00 hr 16.000 84.69 /hr 1,355 26.31 /hr 421 ------111.00 /hr 1,776 General Laborer 32.00 hr 32.000 62.83 /hr 2,011 62.83 /hr 2,011 Site Foreman 16.00 hr 16.000 95.47 /hr 1,528 14.64 /hr 234 ------110.11 /hr 1,762

11 Attachment 4-1 Estimating Reports

Sample Project Page 109 Scope Review Report - Detailed 5/15/2008 7:53 PM

Estimate Totals

Description Amount Totals Hours Rate Basis Percent of Total Labor 30,949,175 394,139 hrs 21.67% Material 35,656,998 24.97% Subcontract 5,802,535 4.06% Equipment 2,904,813 84,108 hrs 2.03% Other 3,260,129 2.28% 78,573,650 78,573,650 55.02 Small Tools & Supplies 1,547,459 5.00 % C 1.08% Incidental Overtime Allowance 1,547,459 5.00 % C 1.08% Overtime Allowance - 48 hr/wk 2,321,188 7.50 % C 1.63% Overtime Allowance - 60 hr/wk 3,094,918 10.00 % C 2.17% Overtime Allowance - 70 hr/wk 4,642,376 15.00 % C 3.25% Subcontractor OH&P 8,643,101 11.00 % C 6.05% Contractor Profit 15,714,730 20.00 % T 11.00% Contractor Bond & Insurance 3,142,946 4.00 % T 2.20% Project Contingency 23,572,095 30.00 % T 16.51% Total 142,799,922

THIS IS A SAMPLE REPORT TO ILLUSTRATE REPORT LAYOUT ONLY. QUANTITIES, RATES, MARKUPS, ETC. SHOULD NOT BE USED FOR ESTIMATING PURPOSES. NOT ALL PAGES OF THE REPORT ARE INCLUDED IN THIS SAMPLE.

12 Attachment 4-1 Estimating Reports

Sample Project Page 1 Attachment 4-1E Labor Productivity Detail Report (Assembly) Labor Productivity Detail Report (Assembly) 5/15/2008 7:05 PM

DB Base Produc- Assembly/ Labor Estimated Labor Labor Equip Equip Material Conv Matl Material Material Sub Other Other Spreadsheet Level Level Takeoff Quantity Crew Produc- tivity % Material Quantity Material Price Sub Cost/Unit Total Cost/Unit Total Amount DB Level 2 Man Hrs Productivity Cost/Unit Amount Cost/Unit Amount Factor Waste Cost/Unit Amount Amount Cost/Unit Amount 3 tivity Adj 02B-020 Chain Link Fencing 2820.006 6' Chain Link Fence 2 2,000.00 lf - - - - No - - - - 13.00 26,000 - - 13.00 26,000 2820.006 6' Fence Man Gate 4 4.00 ea - - - - No - - - - 175.00 700 - - 175.00 700 2820.006 6' Fence Vehicle Gate 20' 20 1.00 ea - - - - No - - - - 880.00 880 - - 880.00 880 2820.006 3 Strand Barb Wire @ Top Add 100 2,000.00 lf - - - - No - - - - 6.00 12,000 - - 6.00 12,000 Chain Link Fencing 2,000.00 lf 19.79 39,580 19.79 39,580 02B-030 Traffic Control (Signs, Rails, Signals) 2892.100 Allowance for Site Signage (Traffic Control, Bldg ID, Etc.) 10 1.00 ls - - - - No - - - - 10,000.00 10,000 - - 10,000.00 10,000 Traffic Control (Signs, Rails, Signals) 1.00 ls 10,000.00 10,000 10,000.00 10,000 02B-040 Grassed Areas 2900.990 Landscaping Allowance -sub 1.00 ls - - - - No - - - - 75,000.00 75,000 - - 75,000.00 75,000 Grassed Areas 75,000 75,000 02B-120 Bituminous Paving-Small Areas 2310.110 Rough Grade Areas 60 11,111.11 sy 02-Site Grade Rough 89 1,000.00 1,000.00 sy/cd 0.72 8,007 0.60 6,707 No ------1.32 14,714 2310.120 Fine Grade Small Pads 60 11,111.11 sy 02-Site Grade Fine 178 1,000.00 1,000.00 sy/cd 1.01 11,170 No 1.01 11,170 2320.010 Gravel Base - Small Paving 70 3,703.70 cy 02-Site Fl Base 30 2,000.00 2,000.00 cy/cd 0.70 2,589 0.87 3,207 1.50 ton/cy Yes 30 7,222.22 ton 25.00 /ton 48.75 180,556 - - - - 50.32 186,351 2740.120 Bituminous Base Course 3" 30 11,111.11 sy - - - - No - - - - 8.00 88,889 - - 8.00 88,889 2740.120 Bituminous Binder Course 1" 110 11,111.11 sy - - - - No - - - - 5.00 55,556 - - 5.00 55,556 2760.100 Painted Lines 6" Wide 6 5,000.00 lf - - - - No - - - - 0.45 2,250 - - 0.45 2,250 Bituminous Paving-Small Areas 11,111.11 sy 296 1.96 21,766 0.89 9,913 16.25 180,556 13.20 146,694 32.30 358,929 02B-130 Concrete Sidewalks 2895.100 Allowance for Misc Site Concrete 22 1.00 ls 06-Laborer ls/ch - - Yes 7 1.07 ls /ls 20,000.00 20,000 - - 20,000.00 20,000 Concrete Sidewalks 1.00 ls 20,000.00 20,000 20,000.00 20,000 02B-200 Aeration Basins / MBR Excavation 1900.120 Cat Dozer D-8 d8 40.00 hr 01-Dozer D8 40 90.08 3,603 153.71 6,148 No ------243.79 9,752 1900.136 Cat Excavator 325 w/ Operator 325 80.00 hr 01-Excavator Cat 325 80 95.47 7,638 105.02 8,402 No ------200.49 16,039 2010.100 General Laborer 10 240.00 hr 02- General Laborer 240 62.83 15,079 No 62.83 15,079 2010.100 Site Foreman 20 60.00 hr 02- General Foreman 60 95.47 5,728 14.64 878 No ------110.11 6,607 2010.100 Mechanic 30 60.00 hr 02- General Mechanic 60 89.83 5,390 No 89.83 5,390 Aeration Basins / MBR Excavation 3,500.00 bcy 480 10.70 37,438 4.41 15,428 15.11 52,866 02B-200 Aeration Basins / MBR Backfill 1900.120 Cat Dozer D-8 w/ Operator d8 80.00 hr 01-Dozer D8 80 90.08 7,206 153.71 12,297 No ------243.79 19,503 1900.160 Caterpillar 825H Double Drum Soil Compactor w/ Operator 012 80.00 hr 01-Soil Comp 825H 80 84.69 6,775 142.02 11,362 No ------226.71 18,137 1900.210 Dump Truck 14 cy td14 160.00 hr 01-Truck Dump 14 160 74.72 11,955 48.53 7,765 No ------123.25 19,720 1900.220 Caterpillar 966G Wheel Loader & Operator 966G 80.00 hr 01-Wheel Loader 966G 80 90.08 7,206 80.62 6,450 No ------170.70 13,656 1900.240 Caterpillar 236 Skid Steer Loader w/ Operator 236 40.00 hr 01-Skid Steers 236 40 84.69 3,388 26.31 1,052 No ------111.00 4,440 2010.100 General Laborer 10 160.00 hr 02- General Laborer 160 62.83 10,053 No 62.83 10,053 2010.100 Site Foreman 20 40.00 hr 02- General Foreman 40 95.47 3,819 14.64 586 No ------110.11 4,404 2010.100 Heavy Equipment Mechanic 30 40.00 hr 02- General Mechanic 40 89.83 3,593 No 89.83 3,593 Aeration Basins / MBR Backfill 3,500.00 ccy 680 15.43 53,996 11.29 39,511 26.72 93,506 02B-200 Aeration Basins / MBR Subgrade Preparation 1900.170 Caterpillar CP-663E Vibratory Soil Compactor w/ Operator 016 60.00 hr 01-Vib Roller 663E 60 84.69 5,081 63.70 3,822 No ------148.39 8,903 1900.220 Caterpillar 966G Wheel Loader & Operator 966G 30.00 hr 01-Wheel Loader 966G 30 90.08 2,702 80.62 2,419 No ------170.70 5,121 2010.100 General Laborer 10 120.00 hr 02- General Laborer 120 62.83 7,540 No 62.83 7,540 2010.100 Site Foreman 20 60.00 hr 02- General Foreman 60 95.47 5,728 14.64 878 No ------110.11 6,607 2301.100 Purchase Type A: 3/4" Minus Granular Rock 05 1,450.00 CY - - - - 1.50 ton/CY No 2,175.00 ton 25.00 /ton 37.50 54,375 - - - - 37.50 54,375 Aeration Basins / MBR Subgrade Preparation 1,125.00 ccy 270 18.71 21,052 6.33 7,119 48.33 54,375 73.37 82,546 02B-200 Headworks Site Preparation 1900.170 Caterpillar CP-323C Vibratory Soil Compactor w/ Operator 010 8.00 hr 01-Vib Roller 323C 8 84.69 678 29.32 235 No ------114.01 912 1900.210 Dump Truck 14 cy td14 16.00 hr 01-Truck Dump 14 16 74.72 1,196 48.53 776 No ------123.25 1,972 1900.220 Caterpillar 938G Wheel Loader & Operator 938G 16.00 hr 01-Wheel Loader 938G 16 90.08 1,441 47.70 763 No ------137.78 2,204 1900.240 Caterpillar 236 Skid Steer Loader w/ Operator 236 16.00 hr 01-Skid Steers 236 16 84.69 1,355 26.31 421 No ------111.00 1,776 2010.100 General Laborer 10 32.00 hr 02- General Laborer 32 62.83 2,011 No 62.83 2,011 2010.100 Site Foreman 20 16.00 hr 02- General Foreman 16 95.47 1,528 14.64 234 No ------110.11 1,762 2240.110 Maintenance of Pumps 60 350.00 day NYC Drilling Crew 1,051 0.33 0.33 day/ch 188.68 66,038 300.30 105,105 Yes 350.00 day 25.00 /day 25.00 8,750 - - - - 513.98 179,893 Headworks Site Preparation 1.00 ls 1,155 74,244.98 74,245 107,534.55 107,535 8,750.00 8,750 190,529.53 190,530 02B-200 Headworks Odor Control Exterior Slab Site Preparation 1900.220 Caterpillar 938G Wheel Loader & Operator 938G 8.00 hr 01-Wheel Loader 938G 8 90.08 721 47.70 382 No ------137.78 1,102 1900.240 Caterpillar 236 Skid Steer Loader w/ Operator 236 8.00 hr 01-Skid Steers 236 8 84.69 678 26.31 210 No ------111.00 888 2010.100 General Laborer *10 40.00 hr 02- General Laborer 40 62.83 2,513 No 62.83 2,513 2240.110 Maintenance of Pumps 60 250.00 day NYC Drilling Crew 751 0.33 0.33 day/ch 188.68 47,170 300.30 75,075 Yes 250.00 day 25.00 /day 25.00 6,250 - - - - 513.98 128,495 Headworks Odor Control Exterior Slab Site 1.00 ls 807 51,081.03 51,081 75,667.16 75,667 6,250.00 6,250 132,998.19 132,998 Preparation 02B-200 Reclaimed Water Pump Station Earthwork 1900.210 Dump Truck 14 cy td14 8.00 hr 01-Truck Dump 14 8 74.72 598 48.53 388 No ------123.25 986 1900.220 Caterpillar 966G Wheel Loader & Operator 966G 8.00 hr 01-Wheel Loader 966G 8 90.08 721 80.62 645 No ------170.70 1,366 1900.240 Caterpillar 236 Skid Steer Loader w/ Operator 236 8.00 hr 01-Skid Steers 236 8 84.69 678 26.31 210 No ------111.00 888 2010.100 General Laborer 10 32.00 hr 02- General Laborer 32 62.83 2,011 No 62.83 2,011 2010.100 Site Foreman 20 16.00 hr 02- General Foreman 16 95.47 1,528 14.64 234 No ------110.11 1,762 2240.110 Maintenance of Pumps 60 25.00 day NYC Drilling Crew 75 0.33 0.33 day/ch 188.68 4,717 300.30 7,508 Yes 25.00 day 25.00 /day 25.00 625 - - - - 513.98 12,849 Reclaimed Water Pump Station Earthwork 1.00 ls 147 10,250.97 10,251 8,985.43 8,985 625.00 625 19,861.40 19,861 02B-200 Duration Earthwork Equipment 1900.120 Cat Dozer D-8 w/ Operator *d8 80.00 hr 01-Dozer D8 80 90.08 7,206 153.71 12,297 No ------243.79 19,503 1900.136 Cat Excavator 320 w/ Operator *320 80.00 hr 01-Excavator Cat 320 80 95.47 7,638 77.06 6,165 No ------172.53 13,802 1900.160 Caterpillar 815F Double Drum Soil Compactor w/ Operator *010 80.00 hr 01-Soil Comp 815F 80 84.69 6,775 106.54 8,523 No ------191.23 15,298 1900.210 Dump Truck 14 cy td14 40.00 hr 01-Truck Dump 14 40 74.72 2,989 48.53 1,941 No ------123.25 4,930 1900.220 Caterpillar 966G Wheel Loader & Operator *966G 80.00 hr 01-Wheel Loader 966G 80 90.08 7,206 80.62 6,450 No ------170.70 13,656 2010.100 General Laborer *10 160.00 hr 02- General Laborer 160 62.83 10,053 No 62.83 10,053 2010.100 Site Foreman *20 80.00 hr 02- General Foreman 80 95.47 7,638 14.64 1,171 No ------110.11 8,809 2240.110 Maintenance of Pumps *60 5,700.00 day NYC Drilling Crew 17,117 0.33 0.33 day/ch 188.68 1,075,468 300.30 1,711,712 Yes 5,700.00 day 25.00 /day 25.00 142,500 - - - - 513.98 2,929,680 13 Sample Project Page 2 Attachment 4-1 Estimating Reports Labor Productivity Detail Report (Assembly) 5/15/2008 7:05 PM

DB Base Produc- Assembly/ Labor Estimated Labor Labor Equip Equip Material Conv Matl Material Material Sub Other Other Spreadsheet Level Level Takeoff Quantity Crew Produc- tivity % Material Quantity Material Price Sub Cost/Unit Total Cost/Unit Total Amount DB Level 2 Man Hrs Productivity Cost/Unit Amount Cost/Unit Amount Factor Waste Cost/Unit Amount Amount Cost/Unit Amount 3 tivity Adj Duration Earthwork Equipment 5,700.00 bcy 17,717 197.36 1,124,973 306.71 1,748,259 25.00 142,500 529.08 3,015,732 02B-240 Aeration Basins / MBR Well Point Dewatering System 2240.110 Set Well Points 10 74.00 ea NYC Drilling Crew 148 0.50 0.50 ea/ch 125.66 9,299 200.00 14,800 Yes 74.00 ea 350.00 /ea 350.00 25,900 675.66 49,999 2240.110 Header Lines 12 1,100.00 lf - - No ------5.00 5,500 5.00 5,500 2240.110 Pumps and Equipment 50 180.00 day 02-Dewater Pumps - - 180.00 32,400 No ------180.00 32,400 2240.110 Maintenance of Pumps 60 180.00 day NYC Drilling Crew 541 0.33 0.33 day/ch 188.68 33,962 300.30 54,054 Yes 180.00 day 25.00 /day 25.00 4,500 513.98 92,516 Aeration Basins / MBR Well Point Dewatering 1.00 ls 689 43,261.00 43,261 101,254.05 101,254 30,400.00 30,400 5,500.00 5,500 180,415.05 180,415 System 0301- MBR / AerationConcrete Equipment 3995.100 100-Ton Crawler Crane 6 12.00 wk 01-Crane Crawl 100 480 40.00 40.00 hr/wk 3,818.80 45,826 7,450.80 89,410 No ------11,269.60 135,235 3995.100 40-Ton Hyrdaulic Crane 10 40.00 wk 01-Crane Hydro 40 1,600 40.00 40.00 hr/wk 3,818.80 152,752 4,618.00 184,720 No ------8,436.80 337,472 3995.100 Concrete Buggies 50 52.00 wk 01-Concr Eqp-Buggies - - 200.00 10,400 No ------200.00 10,400 3995.100 Concrete Vibrators 52 104.00 wk 01-Concr Eqp-Vibr - - 150.00 15,600 No ------150.00 15,600 3995.100 Air Compressors 54 52.00 wk 01-Air Comp 185 - - 566.00 29,432 No ------566.00 29,432 3995.100 Generators 56 52.00 wk 01-Generator 45 - - 750.80 39,042 No ------750.80 39,042 MBR / AerationConcrete Equipment 12.00 mo 2,080 16,548.13 198,578 30,716.93 368,603 47,265.07 567,181 n 0301- Headworks Concrete Equipment 3995.100 100-Ton Crawler Crane 6 16.00 wk 01-Crane Crawl 100 640 40.00 40.00 hr/wk 3,818.80 61,101 7,450.80 119,213 No ------11,269.60 180,314 3995.100 Concrete Vibrators 52 32.00 wk 01-Concr Eqp-Vibr - - 150.00 4,800 No ------150.00 4,800 3995.100 Air Compressors 54 16.00 wk 01-Air Comp 185 - - 566.00 9,056 No ------566.00 9,056 3995.100 Generators 56 16.00 wk 01-Generator 45 - - 750.80 12,013 No ------750.80 12,013 Headworks Concrete Equipment 1.00 ls 640 61,100.80 61,101 145,081.60 145,082 206,182.40 206,182 0301- Reject Water Storage Tank (7MG) 3000.990 Reject Water Storage Tank (7MG) -sub 1.00 ls - - - - No - - - - 1,736,000.00 1,736,000 - - 1,736,000.00 1,736,000 Reject Water Storage Tank (7MG) 1.00 ls 1,736,000.00 1,736,000 1,736,000.00 1,736,000 0301- Reclaimed Water Tank (10MG) 3000.990 Reclaimed Water Tank (10MG) -sub 1.00 ls - - - - No - - - - 2,540,000.00 2,540,000 - - 2,540,000.00 2,540,000 Reclaimed Water Tank (10MG) 1.00 ls 2,540,000.00 2,540,000 2,540,000.00 2,540,000 0302- Continuous Footings 2310.120 Hand Trim Footings 37 1,350.00 sf 02-Site Grade Fine 34 0.03 0.03 mh/sf 1.57 2,121 - - No ------1.57 2,121 3100.102 Continuous Footing Forms < 12" 2 900.00 sf 03-Conc Forming 126 0.14 0.14 mh/sf 12.30 11,065 Yes 900.00 sf 0.40 /sf 0.40 360 - - - - 12.70 11,425 3100.310 Strip & Oil Footing Forms 14 900.00 sf 06-Laborer 9 0.01 0.01 mh/sf 0.63 565 - - No ------0.63 565 3210.104 Footing Rebar 202 3.75 tn 03-Conc Rebar 38 10.00 10.00 mh/tn 678.30 2,544 - - Yes 5 3.94 tn 780.00 /tn 819.10 3,072 - - - - 1,497.41 5,615 3310.100 4000 psi Concrete 40 50.00 cy - - - - Yes 5 52.50 cy 100.00 /cy 105.00 5,250 - - - - 105.00 5,250 3310.150 Truck Place Wall Footings 1 50.00 cy 03-Conc Placement 20 0.40 0.40 mh/cy 26.24 1,312 - - No ------26.24 1,312 3350.110 Finish- Float 4 1,350.00 sf 03-Conc Finishing 14 0.01 0.01 mh/sf 0.78 1,047 - - Yes 1,350.00 sf 0.01 /sf 0.01 14 - - - - 0.79 1,061 Continuous Footings 50.00 cy 240 373.08 18,654 173.90 8,695 546.98 27,349 0303-1 Continuous Footings with Pier Footings 3000.110 Form/Place/Finish Footings, incl rebar/cmu dowels 3 150.00 cy 03-Conc Forming 900 6.00 6.00 mh/cy 526.91 79,036 No 3 150.00 cy 250.00 /cy 250.00 37,500 7.00 1,050 - - 783.91 117,586 Continuous Footings with Pier Footings 150.00 cy 900 526.91 79,036 250.00 37,500 7.00 1,050 783.91 117,586 0322- Wall Concrete (Dimensional Takeoff) 3100.180 Panel Form System 16'-> *b 17 46,834.00 sf 03-Conc Forming 8,196 0.18 0.18 mh/sf 15.37 719,752 Yes 5 49,175.70 sf 1.80 /sf 1.89 88,516 - - - - 17.26 808,268 3100.180 Job Built with Plyform 0-4' *c 4 6,830.00 sf 03-Conc Forming 1,694 0.25 0.25 mh/sf 21.78 148,750 Yes 5 7,171.50 sf 1.60 /sf 1.68 11,474 - - - - 23.46 160,224 3100.180 Job Built with Plyform 4-8' *c 8 10,548.00 sf 03-Conc Forming 3,143 0.30 0.30 mh/sf 26.17 276,039 Yes 5 11,075.40 sf 1.70 /sf 1.79 18,828 - - - - 27.96 294,867 3100.180 Job Built with Plyform 8-12' *c 12 9,666.00 sf 03-Conc Forming 1,924 0.20 0.20 mh/sf 17.48 168,921 Yes 5 10,149.30 sf 1.80 /sf 1.89 18,269 - - - - 19.37 187,190 3100.180 Job Built with Plyform 16'-> *c 17 38,188.00 sf 03-Conc Forming 6,683 0.18 0.18 mh/sf 15.37 586,879 Yes 5 40,097.40 sf 2.00 /sf 2.10 80,195 - - - - 17.47 667,074 3100.310 Strip & Oil Wall Forms *22 112,066.00 sf 06-Laborer 1,905 0.02 0.02 mh/sf 1.07 119,699 - - No ------1.07 119,699 3150.192 Wall Bulkhead Forms *2 3,572.00 sf 03-Conc Forming 1,536 0.43 0.43 mh/sf 37.76 134,885 Yes 5 3,750.60 sf 2.00 /sf 2.10 7,501 - - - - 39.86 142,386 3150.198 Labor to Install Embedded Angle @ Top of Wall *12 1,049.00 lf 03-Conc Forming 140 7.50 7.50 lf/mh 11.71 12,283 - - Yes 5 1,101.45 lf 1.50 /lf 1.58 1,652 - - - - 13.28 13,935 3150.620 Keyway 4" *4 2,619.00 lf 03-Conc Forming 52 0.02 0.02 mh/lf 1.76 4,600 Yes 5 2,749.95 lf 0.40 /lf 0.42 1,100 - - - - 2.18 5,700 3150.620 Horizontal Wall Keyway 4" *24 4,495.00 lf 03-Conc Forming 112 0.03 0.03 mh/lf 2.20 9,869 Yes 5 4,719.75 lf 0.40 /lf 0.42 1,888 - - - - 2.62 11,756 3150.620 Vertical Wall Keyway 4" *34 1,625.00 lf 03-Conc Forming 49 0.03 0.03 mh/lf 2.64 4,281 Yes 5 1,706.25 lf 0.40 /lf 0.42 683 - - - - 3.06 4,964 3210.104 Wall Rebar *210 343.78 tn 03-Conc Rebar 6,876 20.00 20.00 mh/tn 1,356.60 466,372 - - Yes 5 360.97 tn 780.00 /tn 819.00 281,555 - - - - 2,175.60 747,927 3310.100 4000 psi Concrete *40 3,744.82 cy - - - - Yes 5 3,932.06 cy 100.00 /cy 105.00 393,206 - - - - 105.00 393,206 3310.260 Truck Place Walls 1 33.33 cy 03-Conc Placement 20 0.60 0.60 mh/cy 39.36 1,312 - - No ------39.36 1,312 3310.260 Pump Place Walls *3 3,711.48 cy 03-Conc Placement 3,051 0.82 0.82 mh/cy 53.93 200,144 - - No ------10.00 37,115 63.93 237,259 3350.110 Finish- Top of Wall & Curb *20 6,692.50 sf 03-Conc Finishing 67 0.01 0.01 mh/sf 0.78 5,191 - - No ------0.78 5,191 3350.130 Grind/Patch Walls *2 112,066.00 sf 06-Laborer 2,802 0.03 0.03 mh/sf 1.57 176,028 - - Yes 112,066.00 sf 0.02 /sf 0.02 2,241 - - - - 1.59 178,269 3350.140 Rub Walls 2 3,393.00 sf 06-Laborer 254 0.08 0.08 mh/sf 4.71 15,989 - - Yes 3,393.00 sf 0.20 /sf 0.20 679 - - - - 4.91 16,667 3350.150 Sandblast CJ's *3 6,692.50 sf 06-Laborer 335 0.05 0.05 mh/sf 3.14 21,024 Yes 6,692.50 sf 0.25 /sf 0.25 1,673 - - - - 3.39 22,698 3390.170 Liquid Curing Compounds *2 112,066.00 sf 06-Laborer 336 0.00 0.00 mh/sf 0.19 21,123 - - Yes 5 117,669.30 sf 0.03 /sf 0.03 2,942 - - - - 0.22 24,065 3510.610 Waterstop 6" Bulb *106 4,529.00 lf 06-Laborer 91 0.02 0.02 mh/lf 1.26 5,691 - - Yes 5 4,755.45 lf 6.25 /lf 6.56 29,722 - - - - 7.82 35,413 3510.610 Waterstop 9" Bulb *109 1,209.00 lf 06-Laborer 36 0.03 0.03 mh/lf 1.89 2,279 - - Yes 5 1,269.45 lf 7.50 /lf 7.88 9,521 - - - - 9.76 11,800 Wall Concrete (Dimensional Takeoff) 3,744.82 cy 39,301 828.11 3,101,110 254.12 951,644 9.91 37,115 1,092.14 4,089,868 0322- Wall Concrete (Dimensional Takeoff) 7110.100 Sprayed On Bituminous Damproofing 15 15,000.00 sf 07-Insul\Waterprof 225 0.02 0.02 mh/sf 1.08 16,252 - - Yes 7 16,050.00 sf 0.60 /sf 0.64 9,630 - - - - 1.73 25,882 Wall Concrete (Dimensional Takeoff) 15,000.00 sf 225 1.08 16,252 0.64 9,630 1.73 25,882 0326- Rectangle Column Concrete 3100.110 Form Rectangle Columns 16 -20' 20 5,760.00 sf 03-Conc Forming 1,220 0.21 0.21 mh/sf 18.60 107,115 Yes 5 6,048.00 sf 1.50 /sf 1.58 9,072 - - - - 20.17 116,187 3100.310 Strip & Oil Column Forms 4 5,760.00 sf 06-Laborer 68 0.01 0.01 mh/sf 0.74 4,256 - - No ------0.74 4,256 3150.625 Chamfer 1" 10 2,880.00 lf 03-Conc Forming 50 0.02 0.02 mh/lf 1.54 4,434 Yes 5 3,024.00 lf 0.20 /lf 0.21 605 - - - - 1.75 5,038 3210.104 Column Rebar 206 9.33 tn 03-Conc Rebar 110 11.76 11.76 mh/tn 798.00 7,449 - - Yes 5 9.80 tn 780.00 /tn 819.03 7,645 - - - - 1,617.03 15,093 3310.100 4000 psi Concrete 40 106.67 cy - - - - Yes 5 112.00 cy 100.00 /cy 105.00 11,200 - - - - 105.00 11,200 3310.270 Pump Place Piers & Columns 3 106.67 cy 03-Conc Placement 69 0.65 0.65 mh/cy 42.45 4,528 - - No ------10.00 1,067 52.45 5,595 3350.130 Grind/Patch Columns 4 5,760.00 sf 06-Laborer 173 0.03 0.03 mh/sf 1.89 10,857 - - Yes 5,760.00 sf 0.02 /sf 0.02 115 - - - - 1.91 10,972 3390.170 Liquid Curing Compounds 2 5,760.00 sf 06-Laborer 17 0.00 0.00 mh/sf 0.19 1,086 - - Yes 5 6,048.00 sf 0.03 /sf 0.03 151 - - - - 0.22 1,237 Rectangle Column Concrete 106.67 cy 1,707 1,309.92 139,724 269.89 28,788 10.00 1,067 1,589.81 169,578 0330- Upper Floor Structural 3000.135 Topping Slab, 2" thick 4 110.00 cy 03-Conc Forming 1,100 10.00 10.00 mh/cy 878.18 96,600 - - No 110.00 cy 250.00 /cy 250.00 27,500 20.00 2,200 - - 1,148.18 126,300 3410.130 PC Hollow Core Planks 8", grouted, w/embeds 80 14,000.00 sf 03-Conc Precast 350 0.03 0.03 mh/sf 2.39 33,411 0.98 13,691 Yes 14,000.00 sf 11.00 /sf 11.00 154,000 - - - - 14.36 201,102

14 Sample Project Page 8 Labor Productivity Detail Report (Assembly) Attachment 4-1 Estimating5/15/2008 Reports 7:05 PM

DB Base Produc- Assembly/ Labor Estimated Labor Labor Equip Equip Material Conv Matl Material Material Sub Other Other Spreadsheet Level Level Takeoff Quantity Crew Produc- tivity % Material Quantity Material Price Sub Cost/Unit Total Cost/Unit Total Amount DB Level 2 Man Hrs Productivity Cost/Unit Amount Cost/Unit Amount Factor Waste Cost/Unit Amount Amount Cost/Unit Amount 3 tivity Adj 15A-c Grit System 15203.002 DI Flg x Flg Pipe 4" x 15' CL-53 415 2.00 ea 15-PipeCrew 8 4.00 4.00 mh/ea 363.10 726 - - 233.00 lb/ea No 466.00 lb 2.60 /lb 605.80 1,212 - - - - 968.90 1,938 15203.002 DI Flg x Flg Pipe 4" x 18' CL-53 418 2.00 ea 15-PipeCrew 8 4.00 4.00 mh/ea 363.10 726 - - 274.40 lb/ea No 548.80 lb 2.60 /lb 713.44 1,427 - - - - 1,076.54 2,153 15203.002 DI Flg x Flg Pipe 6" x 1' CL-53 601 8.00 ea 15-PipeCrew 24 3.00 3.00 mh/ea 272.33 2,179 - - 55.40 lb/ea No 443.20 lb 2.60 /lb 144.04 1,152 - - - - 416.37 3,331 15203.002 DI Flg x Flg Pipe 6" x 3' CL-53 603 4.00 ea 15-PipeCrew 12 3.00 3.00 mh/ea 272.33 1,089 - - 98.20 lb/ea No 392.80 lb 2.60 /lb 255.32 1,021 - - - - 527.65 2,111 15203.002 DI Flg x Flg Pipe 6" x 4' CL-53 604 4.00 ea 15-PipeCrew 12 3.00 3.00 mh/ea 272.33 1,089 - - 119.60 lb/ea No 478.40 lb 2.60 /lb 310.96 1,244 - - - - 583.29 2,333 15203.002 DI Flg x Flg Pipe 6" x 7' CL-53 607 2.00 ea 15-PipeCrew 14 7.00 7.00 mh/ea 635.43 1,271 - - 183.80 lb/ea No 367.60 lb 2.60 /lb 477.88 956 - - - - 1,113.31 2,227 15203.002 DI Flg x Flg Pipe 6" x 18' CL-53 618 2.00 ea 15-PipeCrew 14 7.00 7.00 mh/ea 635.43 1,271 - - 419.20 lb/ea No 838.40 lb 2.60 /lb 1,089.92 2,180 - - - - 1,725.35 3,451 15203.014 DI Flanged 90 SR ell 4" 4 5.00 ea 15-PipeCrew 13 2.50 2.50 mh/ea 226.94 1,135 - - 50.00 lb/ea No 250.00 lb 2.90 /lb 145.00 725 - - - - 371.94 1,860 15203.014 DI Flanged 90 SR ell 6" 6 6.00 ea 15-PipeCrew 18 3.00 3.00 mh/ea 272.33 1,634 - - 80.00 lb/ea No 480.00 lb 2.90 /lb 232.00 1,392 - - - - 504.33 3,026 15203.030 DI Flanged Con Red 6x4" 604 2.00 ea 15-PipeCrew 6 3.00 3.00 mh/ea 272.33 545 - - 45.00 lb/ea No 90.00 lb 2.60 /lb 117.00 234 - - - - 389.33 779 15203.065 DI Flg x Flg Wall Pipe 4" x 2' CL53 582 2.00 ea 15-PipeCrew 8 4.00 4.00 mh/ea 363.10 726 - - No 2.00 ea 348.40 /ea 348.40 697 - - - - 711.50 1,423 15203.065 DI Flg x Flg Wall Pipe 6" x 2' CL53 1136 3.00 ea 15-PipeCrew 15 5.00 5.00 mh/ea 453.88 1,362 - - No 3.00 ea 403.00 /ea 403.00 1,209 - - - - 856.88 2,571 15203.091 DI Flat Blind Flange 4" 4 2.00 ea 15-PipeCrew 5 2.50 2.50 mh/ea 226.94 454 - - 10.00 lb/ea No 20.00 lb 2.60 /lb 26.00 52 - - - - 252.94 506 15241.211 Dresser Flanged Coupling Adapter 4" 20 3.00 ea 15-PipeCrew 4 1.20 1.20 mh/ea 108.93 327 - - No 3.00 ea 67.00 /ea 67.00 201 - - - - 175.93 528 15241.211 Dresser Flanged Coupling Adapter 6" 25 3.00 ea 15-PipeCrew 5 1.50 1.50 mh/ea 136.16 408 - - No 3.00 ea 85.00 /ea 85.00 255 - - - - 221.16 663 Grit System 217.35 lf 322 134.65 29,266 0.41 90 117.70 25,582 252.76 54,938 15A-c PD System 15120.002 Bolt, Nut & Gasket Set ANSI C110/AWWA A21.10-150# 8 a 80 15.00 ea 15-PipeCrew 15 1.00 1.00 mh/ea 90.78 1,362 - - No 15.00 ea 49.40 /ea 49.40 741 - - - - 140.18 2,103 15203.002 DI Flg x Flg Pipe 8" x 4' CL-53 804 2.00 ea 15-PipeCrew 8 4.00 4.00 mh/ea 363.10 726 - - 174.40 lb/ea No 348.80 lb 2.60 /lb 453.44 907 - - - - 816.54 1,633 15203.002 DI Flg x Flg Pipe 8" x 6' CL-53 806 2.00 ea 15-PipeCrew 8 4.00 4.00 mh/ea 363.10 726 - - 234.60 lb/ea No 469.20 lb 2.60 /lb 609.96 1,220 - - - - 973.06 1,946 15203.002 DI Flg x Flg Pipe 8" x 8' CL-53 808 3.00 ea 15-PipeCrew 24 8.00 8.00 mh/ea 726.20 2,179 - - 294.80 lb/ea No 884.40 lb 2.60 /lb 766.48 2,299 - - - - 1,492.68 4,478 15203.002 DI Flg x Flg Pipe 8" x 18' CL-53 818 1.00 ea 15-PipeCrew 8 8.00 8.00 mh/ea 726.20 726 - - 595.80 lb/ea No 595.80 lb 2.60 /lb 1,549.08 1,549 - - - - 2,275.28 2,275 15203.014 DI Flanged 90 SR ell 8" 8 4.00 ea 15-PipeCrew 16 4.00 4.00 mh/ea 363.10 1,452 - - 140.00 lb/ea No 560.00 lb 2.90 /lb 406.00 1,624 - - - - 769.10 3,076 15203.065 DI Flg x Flg Wall Pipe 8" x 2' CL53 1690 1.00 ea 15-PipeCrew 6 6.00 6.00 mh/ea 544.65 545 - - No 1.00 ea 496.60 /ea 496.60 497 - - - - 1,041.25 1,041 15203.091 DI Flat Blind Flange 8" 8 1.00 ea 15-PipeCrew 4 4.00 4.00 mh/ea 363.10 363 - - 80.00 lb/ea No 80.00 lb 2.60 /lb 208.00 208 - - - - 571.10 571 PD System 65.10 lf 89 124.10 8,079 138.94 9,045 263.04 17,124 15A-c Scum System-Glass Lined 11295.110 Flg Plug Valve 6", V-30-852,862,854,864,865 +3 6 8.00 ea 15-PipeCrew 40 5.00 5.00 mh/ea 453.88 3,631 7.50 60 No 8.00 ea 500.00 /ea 500.00 4,000 - - - - 961.38 7,691 11295.120 Swing Check Valve 6",V-30-813/853 06 2.00 ea 15-PipeCrew 10 5.00 5.00 mh/ea 453.88 908 5.00 10 No 2.00 ea 1,800.00 /ea 1,800.00 3,600 - - - - 2,258.88 4,518 15000.001 Pressure Gauge & Switch Assembly 005 3.00 ea 15-PipeCrew 24 7.96 7.96 mh/ea 722.57 2,168 - - No 3.00 ea 235.87 /ea 235.87 708 - - 958.44 2,875 15000.001 Air/Vacuum Release Assembly- 3" & Smaller 010 2.00 ea 15-PipeCrew 40 20.19 20.19 mh/ea 1,832.75 3,665 - - No 2.00 ea 1,427.94 /ea 1,427.94 2,856 - - - - 3,260.69 6,521 15120.002 Bolt, Nut & Gasket Set ANSI C110/AWWA A21.10-150# 4 a 40 3.00 ea 15-PipeCrew 3 0.85 0.85 mh/ea 77.16 231 - - No 3.00 ea 27.84 /ea 27.84 84 - - - - 105.00 315 15120.002 Bolt, Nut & Gasket Set ANSI C110/AWWA A21.10-150# 6 a 60 30.00 ea 15-PipeCrew 30 1.00 1.00 mh/ea 90.78 2,723 - - No 30.00 ea 35.69 /ea 35.69 1,071 - - - - 126.47 3,794 15203.002 DI Flg x Flg Pipe 4" x 2' CL-53 402 7.00 ea 15-PipeCrew 18 2.50 2.50 mh/ea 226.94 1,589 - - 53.60 lb/ea No 375.20 lb 2.60 /lb 139.36 976 - - - - 366.30 2,564 15203.002 DI Flg x Flg Pipe 6" x 2' CL-53 602 2.00 ea 15-PipeCrew 6 3.00 3.00 mh/ea 272.33 545 - - 76.80 lb/ea No 153.60 lb 2.60 /lb 199.68 399 - - - - 472.01 944 15203.002 DI Flg x Flg Pipe 6" x 4' CL-53 604 2.00 ea 15-PipeCrew 6 3.00 3.00 mh/ea 272.33 545 - - 119.60 lb/ea No 239.20 lb 2.60 /lb 310.96 622 - - - - 583.29 1,167 15203.002 DI Flg x Flg Pipe 6" x 6' CL-53 606 2.00 ea 15-PipeCrew 6 3.00 3.00 mh/ea 272.33 545 - - 162.40 lb/ea No 324.80 lb 2.60 /lb 422.24 844 - - - - 694.57 1,389 15203.002 DI Flg x Flg Pipe 6" x 8' CL-53 608 2.00 ea 15-PipeCrew 14 7.00 7.00 mh/ea 635.43 1,271 - - 205.20 lb/ea No 410.40 lb 2.60 /lb 533.52 1,067 - - - - 1,168.95 2,338 15203.002 DI Flg x Flg Pipe 6" x 12' CL-53 612 2.00 ea 15-PipeCrew 14 7.00 7.00 mh/ea 635.43 1,271 - - 290.80 lb/ea No 581.60 lb 2.60 /lb 756.08 1,512 - - - - 1,391.51 2,783 15203.014 DI Flanged 90 SR ell 6" 6 9.00 ea 15-PipeCrew 27 3.00 3.00 mh/ea 272.33 2,451 - - 80.00 lb/ea No 720.00 lb 2.90 /lb 232.00 2,088 - - - - 504.33 4,539 15203.030 DI Flanged Con Red 6x4" 604 2.00 ea 15-PipeCrew 6 3.00 3.00 mh/ea 272.33 545 - - 45.00 lb/ea No 90.00 lb 2.60 /lb 117.00 234 - - - - 389.33 779 15203.065 DI Flg x Flg Wall Pipe 6" x 2' CL53 1136 5.00 ea 15-PipeCrew 25 5.00 5.00 mh/ea 453.88 2,269 - - No 5.00 ea 403.00 /ea 403.00 2,015 - - - - 856.88 4,284 15241.211 Dresser Flanged Coupling Adapter 4" 20 2.00 ea 15-PipeCrew 2 1.20 1.20 mh/ea 108.93 218 - - No 2.00 ea 67.00 /ea 67.00 134 - - - - 175.93 352 Scum System-Glass Lined 71.40 lf 271 344.17 24,574 0.98 70 311.05 22,209 656.20 46,853 15A-c Activate Sludge Basins 1 & 2 11295.120 Swing Check Valve 20", CSRWRF-V-40-132,133,232 , 233 20 4.00 ea 15-PipeCrew 64 16.00 16.00 mh/ea 1,452.40 5,810 7.50 30 No 4.00 ea 9,500.00 /ea 9,500.00 38,000 - - - - 10,959.90 43,840 11295.120 Swing Check Valve 24", CSRWRF-V-40-151,152,251,252 24 4.00 ea 15-PipeCrew 76 19.00 19.00 mh/ea 1,724.73 6,899 7.50 30 No 4.00 ea 14,500.00 /ea 14,500.00 58,000 - - - - 16,232.23 64,929 15060.036 Floor Stand Assembly-Galv with U-bolt 20 x 2' 607 16.00 ea 15-PipeCrew 144 9.00 9.00 mh/ea 816.98 13,072 2.50 40 No 16.00 ea 635.00 /ea 635.00 10,160 - - - - 1,454.48 23,272 15060.036 Floor Stand Assembly-Galv with U-bolt 24 x 2' 623 40.00 ea 15-PipeCrew 440 11.00 11.00 mh/ea 998.53 39,941 2.50 100 No 40.00 ea 700.00 /ea 700.00 28,000 - - - - 1,701.03 68,041 15120.002 Bolt, Nut & Gasket Set ANSI C110/AWWA A21.10-150# 20 a200 31.00 ea 15-PipeCrew 127 4.10 4.10 mh/ea 372.18 11,538 - - No 31.00 ea 251.74 /ea 251.74 7,804 - - - - 623.92 19,341 15120.002 Bolt, Nut & Gasket Set ANSI C110/AWWA A21.10-150# 24 a201 43.00 ea 15-PipeCrew 200 4.65 4.65 mh/ea 422.10 18,150 - - No 43.00 ea 350.55 /ea 350.55 15,074 - - - - 772.65 33,224 15203.002 DI Flg x Flg Pipe 20" x 4' CL-53 2004 8.00 ea 15-PipeCrew 80 10.00 10.00 mh/ea 907.75 7,262 - - 590.00 lb/ea No 4,720.00 lb 2.60 /lb 1,534.00 12,272 - - - - 2,441.75 19,534 15203.002 DI Flg x Flg Pipe 20" x 8' CL-53 2008 2.00 ea 15-PipeCrew 30 15.00 15.00 mh/ea 1,361.63 2,723 - - 956.00 lb/ea No 1,912.00 lb 2.60 /lb 2,485.60 4,971 - - - - 3,847.23 7,694 15203.002 DI Flg x Flg Pipe 20" x 18' CL-53 2018 8.00 ea 15-PipeCrew 120 15.00 15.00 mh/ea 1,361.63 10,893 - - 1,871.00 lb/ea No 14,968.00 lb 2.60 /lb 4,864.60 38,917 - - - - 6,226.23 49,810 15203.002 DI Flg x Flg Pipe 24" x 4' CL-53 2404 8.00 ea 15-PipeCrew 88 11.00 11.00 mh/ea 998.53 7,988 - - 767.60 lb/ea No 6,140.80 lb 2.60 /lb 1,995.76 15,966 - - - - 2,994.29 23,954 15203.002 DI Flg x Flg Pipe 24" x 8' CL-53 2408 2.00 ea 15-PipeCrew 32 16.00 16.00 mh/ea 1,452.40 2,905 - - 1,225.20 lb/ea No 2,450.40 lb 2.60 /lb 3,185.52 6,371 - - - - 4,637.92 9,276 15203.002 DI Flg x Flg Pipe 24" x 18' CL-53 2418 20.00 ea 15-PipeCrew 320 16.00 16.00 mh/ea 1,452.40 29,048 - - 2,369.20 lb/ea No 47,384.00 lb 2.60 /lb 6,159.92 123,198 - - - - 7,612.32 152,246 15203.014 DI Flanged 90 SR ell 20" 20 4.00 ea 15-PipeCrew 44 11.00 11.00 mh/ea 998.53 3,994 - - 810.00 lb/ea No 3,240.00 lb 2.90 /lb 2,349.00 9,396 - - - - 3,347.53 13,390 15203.014 DI Flanged 90 SR ell 24" 24 4.00 ea 15-PipeCrew 48 12.00 12.00 mh/ea 1,089.30 4,357 - - 1,240.00 lb/ea No 4,960.00 lb 2.90 /lb 3,596.00 14,384 - - - - 4,685.30 18,741 15203.065 DI Flg x Flg Wall Pipe 20" x 2' CL53 5014 2.00 ea 15-PipeCrew 22 11.00 11.00 mh/ea 998.53 1,997 - - No 2.00 ea 1,267.50 /ea 1,267.50 2,535 - - - - 2,266.03 4,532 15203.065 DI Flg x Flg Wall Pipe 24" x 2' CL53 5568 2.00 ea 15-PipeCrew 24 12.00 12.00 mh/ea 1,089.30 2,179 - - No 2.00 ea 1,652.30 /ea 1,652.30 3,305 - - - - 2,741.60 5,483 Activate Sludge Basins 1 & 2 630.00 lf 1,859 267.87 168,755 0.32 200 616.43 388,353 884.62 557,308 15A-c Sub Pmps Alternate B 11210.150 Submersible Pump w/ Rails & Ell Ftg 76-100 hp 55 6.00 ea 15-PipeCrew 336 56.00 56.00 mh/ea 5,083.40 30,500 15.00 90 Yes 6.00 ea 11,000.00 /ea 11,000.00 66,000 - - - - 16,098.40 96,590 11286.001 Gate Valve - Lvr/HW - 10" 25 6.00 ea 15-PipeCrew 48 8.00 8.00 mh/ea 726.20 4,357 5.00 30 No 6.00 ea 2,100.00 /ea 2,100.00 12,600 - - - - 2,831.20 16,987 11295.120 Swing Check Valve 10" 10 6.00 ea 15-PipeCrew 48 8.00 8.00 mh/ea 726.20 4,357 5.00 30 No 6.00 ea 2,800.00 /ea 2,800.00 16,800 - - - - 3,531.20 21,187 15060.036 Floor Stand Assembly-Galv with U-bolt 10 x 2' 527 42.00 ea 15-PipeCrew 294 7.00 7.00 mh/ea 635.43 26,688 5.00 210 No 42.00 ea 412.00 /ea 412.00 17,304 - - - - 1,052.43 44,202 15120.002 Bolt, Nut & Gasket Set ANSI C110/AWWA A21.10-150# 10 a100 97.00 ea 15-PipeCrew 175 1.80 1.80 mh/ea 163.40 15,849 - - No 97.00 ea 78.68 /ea 78.68 7,632 - - - - 242.08 23,481 15203.002 DI Flg x Flg Pipe 10" x 2' CL-53 1002 20.00 ea 15-PipeCrew 80 4.00 4.00 mh/ea 363.10 7,262 - - 154.40 lb/ea No 3,088.00 lb 2.60 /lb 401.44 8,029 - - - - 764.54 15,291 15203.002 DI Flg x Flg Pipe 10" x 5' CL-53 1005 12.00 ea 15-PipeCrew 48 4.00 4.00 mh/ea 363.10 4,357 - - 272.00 lb/ea No 3,264.00 lb 2.60 /lb 707.20 8,486 - - - - 1,070.30 12,844 15203.002 DI Flg x Flg Pipe 10" x 8' CL-53 1008 4.00 ea 15-PipeCrew 36 9.00 9.00 mh/ea 816.98 3,268 - - 389.60 lb/ea No 1,558.40 lb 2.60 /lb 1,012.96 4,052 - - - - 1,829.94 7,320 15203.002 DI Flg x Flg Pipe 10" x 18' CL-53 1018 24.00 ea 15-PipeCrew 216 9.00 9.00 mh/ea 816.98 19,607 - - 781.60 lb/ea No 18,758.40 lb 2.60 /lb 2,032.16 48,772 - - - - 2,849.14 68,379 15203.014 DI Flanged 90 SR ell 10" 10 6.00 ea 15-PipeCrew 30 5.00 5.00 mh/ea 453.88 2,723 - - 215.00 lb/ea No 1,290.00 lb 2.90 /lb 623.50 3,741 - - - - 1,077.38 6,464 15203.065 DI Flg x Flg Wall Pipe 10" x 2' CL53 2244 6.00 ea 15-PipeCrew 48 8.00 8.00 mh/ea 726.20 4,357 - - No 6.00 ea 604.50 /ea 604.50 3,627 - - - - 1,330.70 7,984 Sub Pmps Alternate B 592.20 lf 1,359 208.25 123,327 0.61 360 332.73 197,043 541.59 320,730 15A-c Final Eff Piping 11286.003 Butterfly Valve - Lvr/HW - 8" 20 3.00 ea 15-PipeCrew 18 6.00 6.00 mh/ea 544.65 1,634 5.00 15 No 3.00 ea 850.00 /ea 850.00 2,550 - - - - 1,399.65 4,199 11295.120 Swing Check Valve 8" 08 3.00 ea 15-PipeCrew 18 6.00 6.00 mh/ea 544.65 1,634 5.00 15 No 3.00 ea 2,100.00 /ea 2,100.00 6,300 - - - - 2,649.65 7,949 15000.001 Pressure Gauge & Switch Assembly 005 3.00 ea 15-PipeCrew 24 7.96 7.96 mh/ea 722.57 2,168 - - No 3.00 ea 235.87 /ea 235.87 708 - - 958.44 2,875 15000.001 8" Mag Meters FE-150/160 ---- 2.00 ea 15-PipeCrew 8 4.00 4.00 mh/ea 363.10 726 20.00 40 Yes 2.00 ea 8,000.00 /ea 8,000.00 16,000 - - - - 8,383.10 16,766 15120.002 Bolt, Nut & Gasket Set ANSI C110/AWWA A21.10-150# 8 a 80 22.00 ea 15-PipeCrew 22 1.00 1.00 mh/ea 90.78 1,997 - - No 22.00 ea 49.40 /ea 49.40 1,087 - - - - 140.18 3,084 15120.202 54" Mag Meter Flgd, FE-101 60 1.00 ea 15-PipeCrew 40 40.00 40.00 mh/ea 3,631.00 3,631 30.00 30 No 1.00 ea 55,565.00 /ea 55,565.00 55,565 - - - - 59,226.00 59,226 15203.002 DI Flg x Flg Pipe 8" x 1' CL-53 801 6.00 ea 15-PipeCrew 24 4.00 4.00 mh/ea 363.10 2,179 - - 84.10 lb/ea No 504.60 lb 2.60 /lb 218.66 1,312 - - - - 581.76 3,491

15 Attachment 4-1 Estimating Reports

Sample Project Page 27 Labor Productivity Detail Report (Assembly) 5/15/2008 7:05 PM

Estimate Totals

Description Amount Totals Hours Rate Basis Percent of Total Labor 30,949,175 394,139 hrs 21.67% Material 35,656,998 24.97% Subcontract 5,802,535 4.06% Equipment 2,904,813 84,108 hrs 2.03% Other 3,260,129 2.28% 78,573,650 78,573,650 55.02 Small Tools & Supplies 1,547,459 5.00 % C 1.08% Incidental Overtime Allowance 1,547,459 5.00 % C 1.08% Overtime Allowance - 48 hr/wk 2,321,188 7.50 % C 1.63% Overtime Allowance - 60 hr/wk 3,094,918 10.00 % C 2.17% Overtime Allowance - 70 hr/wk 4,642,376 15.00 % C 3.25% Subcontractor OH&P 8,643,101 11.00 % C 6.05% Contractor Profit 15,714,730 20.00 % T 11.00% Contractor Bond & Insurance 3,142,946 4.00 % T 2.20% Project Contingency 23,572,095 30.00 % T 16.51% Total 142,799,922

THIS IS A SAMPLE REPORT TO ILLUSTRATE REPORT LAYOUT ONLY. QUANTITIES, RATES, MARKUPS, ETC. SHOULD NOT BE USED FOR ESTIMATING PURPOSES. NOT ALL PAGES OF THE REPORT ARE INCLUDED IN THIS SAMPLE.

16 Attachment 4-1 Estimating Reports

Sample Project Page 1 Attachment 4-1F Labor Productivity Detail Report (Item) Labor Productivity Detail Report (Item) 5/15/2008 7:03 PM

DB Base Labor Produc- Estimated Labor Labor Rate Labor Material Conv Material Matl Matl Material Sub Equip Equip Other Oth Other Level Spreadsheet Level Takeoff Quantity % Crew Produc- Labor Price Material Quantity Material Price Sub Cost/Unit Total Cost/Unit Total Amount Man Hrs tivity Adj Productivity Cost/Unit Table Amount Factor Cost/Unit Waste Tax Amount Amount Cost/Unit Amount Cost/Unit Tax Amount 3 tivity 100.100 Project Management 21 Project Executive 104.00 wk NYC-01-Proj Exec 4,160 4,625.20 4,625.20 /wk CD-NYC1 481,021 - - - No No ------No - 4,625.20 481,021 22 Project Manager 104.00 wk NYC-01-Proj Manager 4,160 4,500.00 4,500.00 /wk CD-NYC1 468,000 - - - No No ------No - 4,500.00 468,000 23 Assistant Project Manager 104.00 wk NYC-01-Assistant PM 4,160 4,000.00 4,000.00 /wk CD-NYC1 416,000 - - - No No ------No - 4,000.00 416,000 24 Construction Manager 104.00 wk NYC-01-Const Mgr 4,160 4,000.00 4,000.00 /wk CD-NYC1 416,000 - - - No No ------No - 4,000.00 416,000 25 Assistant Construction Manager 104.00 wk NYC-01-Assistant CM 4,160 3,800.00 3,800.00 /wk CD-NYC1 395,200 - - - No No ------No - 3,800.00 395,200 29 Risk Manager 52.00 wk NYC-01-Risk Manager 2,080 3,600.00 3,600.00 /wk CD-NYC1 187,200 - - - No No ------No - 3,600.00 187,200 Project Management 22,880 2,363,421 2,363,421 100.110 Field Engineering 21 Senior Project Engineer 104.00 wk NYC-01-Senior PE 4,160 2,887.60 2,887.60 /wk CD-NYC1 300,310 - - - No No ------No - 2,887.60 300,310 22 Project Engineer 104.00 wk NYC-01-Project Eng 4,160 3,150.00 3,150.00 /wk CD-NYC1 327,600 - - - No No ------No - 3,150.00 327,600 23 Field Engineer 104.00 wk NYC-01-Field Eng 4,160 2,100.00 2,100.00 /wk CD-NYC1 218,400 - - - No No ------No - 2,100.00 218,400 24 Detailer/Draftsman 52.00 wk NYC-01-Draftsman 2,080 2,450.00 2,450.00 /wk CD-NYC1 127,400 - - - No No ------No - 2,450.00 127,400 25 Geotechnical Engineer 26.00 wk NYC-01-Geotech Eng 1,040 3,360.00 3,360.00 /wk CD-NYC1 87,360 - - - No No ------No - 3,360.00 87,360 26 Civil Engineer 78.00 wk NYC-01-Civil Eng 3,120 3,360.00 3,360.00 /wk CD-NYC1 262,080 - - - No No ------No - 3,360.00 262,080 27 Structural Engineer 52.00 wk NYC-01-Struct Eng 2,080 3,360.00 3,360.00 /wk CD-NYC1 174,720 - - - No No ------No - 3,360.00 174,720 28 Mechanical Engineer 104.00 wk NYC-01-Mech 4,160 3,360.00 3,360.00 /wk CD-NYC1 349,440 - - - No No ------No - 3,360.00 349,440 Engineer 29 Electrical - I & C Engineer 52.00 wk NYC-01-Elect I&C Eng 2,080 3,360.00 3,360.00 /wk CD-NYC1 174,720 - - - No No ------No - 3,360.00 174,720 Field Engineering 27,040 2,022,030 2,022,030 100.115 Surveying 21 Survey Crew Chief 32.00 wk NYC-01-Survey Chief 1,280 3,150.00 3,150.00 /wk CD-NYC1 100,800 - - - No No ------No - 3,150.00 100,800 22 Survey Crew 32.00 wk NYC-01-Survey Crew 1,280 4,200.00 4,200.00 /wk CD-NYC1 134,400 - - - No No ------No - 4,200.00 134,400 Surveying 2,560 235,200 235,200 100.120 Field Supervisory Staff 21 General Superintendent 104.00 wk NYC-01-General Super 4,160 3,430.00 3,430.00 /wk CD-NYC1 356,720 - - - No No ------No - 3,430.00 356,720 22 Project (or Area) Superintendent 104.00 wk NYC-01-Project Super 4,160 3,280.00 3,280.00 /wk CD-NYC1 341,120 - - - No No ------No - 3,280.00 341,120 23 Assistant Project Superintendent 104.00 wk NYC-01-Asst Proj Sup 4,160 3,115.20 3,115.20 /wk CD-NYC1 323,981 - - - No No ------No - 3,115.20 323,981 24 Civil Superintendent 96.00 wk NYC-01-Civil Super 3,840 2,975.20 2,975.20 /wk CD-NYC1 285,619 - - - No No ------No - 2,975.20 285,619 25 Concrete Superintendent 78.00 wk NYC-01-Conc Super 3,120 2,975.20 2,975.20 /wk CD-NYC1 232,066 - - - No No ------No - 2,975.20 232,066 26 Mechanical Superintendent 96.00 wk NYC-01-Mech Super 3,840 3,237.60 3,237.60 /wk CD-NYC1 310,810 - - - No No ------No - 3,237.60 310,810 27 Electrical - I & C Superintendent 52.00 wk NYC-01-Elect Super 2,080 3,237.60 3,237.60 /wk CD-NYC1 168,355 - - - No No ------No - 3,237.60 168,355 Field Supervisory Staff 25,360 2,018,670 2,018,670 100.125 Operations 31 Lead Operator 16.00 wk NYC-01-Lead Operator 640 2,800.00 2,800.00 /wk CD-NYC1 44,800 - - - No No ------No - 2,800.00 44,800 32 Operator 16.00 wk NYC-01-Operator 640 2,450.00 2,450.00 /wk CD-NYC1 39,200 - - - No No ------No - 2,450.00 39,200 Operations 1,280 84,000 84,000 100.130 Project Controls 21 Project Controls Engineer 104.00 wk NYC-01-Proj Cntl Eng 4,160 2,450.00 2,450.00 /wk CD-NYC1 254,800 - - - No No ------No - 2,450.00 254,800 22 Project Scheduler 104.00 wk NYC-01-Proj Sched 4,160 2,450.00 2,450.00 /wk CD-NYC1 254,800 - - - No No ------No - 2,450.00 254,800 23 Document Control Engineer 104.00 wk NYC-01-Doc Cntrl Eng 4,160 2,362.40 2,362.40 /wk CD-NYC1 245,690 - - - No No ------No - 2,362.40 245,690 Project Controls 12,480 755,290 755,290 100.135 Project Accounting Staff 21 Project Accounting 104.00 wk NYC-01-Proj Account 4,160 2,257.60 2,257.60 /wk CD-NYC1 234,790 - - - No No ------No - 2,257.60 234,790 Project Accounting Staff 4,160 234,790 234,790 100.140 Project Safety Personnel 21 Safety Manager 104.00 wk NYC-01-Safety Mgr 4,160 3,325.20 3,325.20 /wk CD-NYC1 345,821 - - - No No ------No - 3,325.20 345,821 22 Assistant Safety Manager 104.00 wk NYC-01-Asst Safety 4,160 2,625.20 2,625.20 /wk CD-NYC1 273,021 - - - No No ------No - 2,625.20 273,021 Project Safety Personnel 8,320 618,842 618,842 100.150 Project Admin Staff 21 Office Manager 104.00 wk NYC-01-Office Mgr 4,160 2,625.20 2,625.20 /wk CD-NYC1 273,021 - - - No No ------No - 2,625.20 273,021 22 Project Coordinator 104.00 wk NYC-01-Proj Coord 4,160 2,625.20 2,625.20 /wk CD-NYC1 273,021 - - - No No ------No - 2,625.20 273,021 23 Project Secretary 104.00 wk NYC-01-Proj Sec 4,160 1,750.00 1,750.00 /wk CD-NYC1 182,000 - - - No No ------No - 1,750.00 182,000 24 Time Keeper 104.00 wk NYC-01-Time Keeper 4,160 1,137.60 1,137.60 /wk CD-NYC1 118,310 - - - No No ------No - 1,137.60 118,310 25 Runner 104.00 wk NYC-01-Runner 4,160 1,400.00 1,400.00 /wk CD-NYC1 145,600 - - - No No ------No - 1,400.00 145,600 Project Admin Staff 20,800 991,952 991,952 100.160 Quality Control Staff 21 QA Manager 96.00 wk NYC-01-QA Manager 3,840 3,062.40 3,062.40 /wk CD-NYC1 293,990 - - - No No ------No - 3,062.40 293,990 22 QA Inspector 96.00 wk NYC-01-QA Inspector 3,840 2,712.80 2,712.80 /wk CD-NYC1 260,429 - - - No No ------No - 2,712.80 260,429 23 Civil Inspector 96.00 wk NYC-01-Civil Inspect 3,840 2,450.00 2,450.00 /wk CD-NYC1 235,200 - - - No No ------No - 2,450.00 235,200 24 Mechanical Inspector 96.00 wk NYC-01-Mech Inspect 3,840 2,800.00 2,800.00 /wk CD-NYC1 268,800 - - - No No ------No - 2,800.00 268,800 25 Concrete Inspector 78.00 wk NYC-01-Conc Inspect 3,120 2,450.00 2,450.00 /wk CD-NYC1 191,100 - - - No No ------No - 2,450.00 191,100 26 Building Inspector 52.00 wk NYC-01-Building Insp 2,080 2,450.00 2,450.00 /wk CD-NYC1 127,400 - - - No No ------No - 2,450.00 127,400 27 Electrical Inspector 52.00 wk NYC-01-Elect Inspect 2,080 2,800.00 2,800.00 /wk CD-NYC1 145,600 - - - No No ------No - 2,800.00 145,600 29 Construction Materials Technician 78.00 wk NYC-01-Materials Tec 3,120 1,750.00 1,750.00 /wk CD-NYC1 136,500 - - - No No ------No - 1,750.00 136,500 Quality Control Staff 25,760 1,659,019 1,659,019 100.170 Estimating 21 Chief Estimator 10.00 wk NYC-01-Chief Est 400 4,025.20 4,025.20 /wk CD-NYC1 40,252 - - - No No ------No - 4,025.20 40,252 22 Lead Estimator 10.00 wk NYC-01-Lead Est 400 3,675.20 3,675.20 /wk CD-NYC1 36,752 - - - No No ------No - 3,675.20 36,752 23 Civil Estimator 6.00 wk NYC-01-Civil Est 240 2,975.20 2,975.20 /wk CD-NYC1 17,851 - - - No No ------No - 2,975.20 17,851 24 Mechanical Estimator 6.00 wk NYC-01-Mech Est 240 2,975.20 2,975.20 /wk CD-NYC1 17,851 - - - No No ------No - 2,975.20 17,851 25 Concrete Estimator 6.00 wk NYC-01-Concrete Est 240 2,975.20 2,975.20 /wk CD-NYC1 17,851 - - - No No ------No - 2,975.20 17,851 26 Building Estimator 6.00 wk NYC-01-Building Est 240 2,975.20 2,975.20 /wk CD-NYC1 17,851 - - - No No ------No - 2,975.20 17,851 27 Electrical Estimator 6.00 wk NYC-01-Elect Est 240 2,975.20 2,975.20 /wk CD-NYC1 17,851 - - - No No ------No - 2,975.20 17,851 Estimating 2,000 166,260 166,260 100.180 Procurement 21 Procurement Manager 16.00 wk NYC-01-Procure Mgr 640 3,675.20 3,675.20 /wk CD-NYC1 58,803 - - - No No ------No - 3,675.20 58,803 22 Purchasing Agent 16.00 wk NYC-01-Purch Agent 640 2,712.40 2,712.40 /wk CD-NYC1 43,398 - - - No No ------No - 2,712.40 43,398 Procurement 1,280 102,202 102,202 100.190 Laborers 21 General Purpose Laborers 104.00 wk 02- General Laborer 4,160 40.00 40.00 ch/wk 2,513.20 62.83 /ch CD-NYC1 261,373 No No No 2,513.20 261,373 Laborers 4,160 261,373 261,373 100.195 Other Project Staff 21 Security 80.00 wk NYC-01-Security 3,200 1,400.00 1,400.00 /wk CD-NYC1 112,000 - - - No No ------No - 1,400.00 112,000 22 Traffice Control 24.00 wk NYC-01-Traffic Cntrl 960 1,400.00 1,400.00 /wk CD-NYC1 33,600 - - - No No ------No - 1,400.00 33,600 23 Interns 24.00 wk NYC-01-Interns 960 1,400.00 1,400.00 /wk CD-NYC1 33,600 - - - No No ------No - 1,400.00 33,600 Other Project Staff 5,120 179,200 179,200 100.200 Community Service 11 Community Service Programs 1.00 ls - - CD-NYC1 - - - - No No - - - - - 50,000.00 No 50,000 50,000.00 50,000 12 Community Outreach 1.00 ls - - CD-NYC1 - - - - No No - - - - - 50,000.00 No 50,000 50,000.00 50,000 Community Service 100,000 100,000

17 Attachment 4-1 Estimating Reports Sample Project Page 4 Labor Productivity Detail Report (Item) 5/15/2008 7:03 PM

DB Base Labor Produc- Estimated Labor Labor Rate Labor Material Conv Material Matl Matl Material Sub Equip Equip Other Oth Other Level Spreadsheet Level Takeoff Quantity % Crew Produc- Labor Price Material Quantity Material Price Sub Cost/Unit Total Cost/Unit Total Amount Man Hrs tivity Adj Productivity Cost/Unit Table Amount Factor Cost/Unit Waste Tax Amount Amount Cost/Unit Amount Cost/Unit Tax Amount 3 tivity Grading- Rough 89 8,007 6,707 14,714 2310.120 Grading- Fine *35 Fine Grade SOG 52,182.25 sf 02-Site Grade Fine 1,252 0.02 0.02 mh/sf 1.51 62.83 /mh CD-NYC1 78,687 - - - No No ------No - 1.51 78,687 37 Hand Trim Footings 1,350.00 sf 02-Site Grade Fine 34 0.03 0.03 mh/sf 1.57 62.83 /mh CD-NYC1 2,121 - - - No No ------No - 1.57 2,121 60 Fine Grade Small Pads 11,111.11 sy 02-Site Grade Fine 178 1,000.00 1,000.00 sy/cd 1.01 1,005.28 /cd CD-NYC1 11,170 No No No 1.01 11,170 Grading- Fine 1,464 91,977 91,977 2320.010 Base- Gravel 70 Gravel Base - Small Paving 3,703.70 cy 30 02-Site Fl Base 30 2,000.00 2,000.00 cy/cd 0.70 1,398.16 /cd CD-NYC1 2,589 1.50 ton/cy 48.75 7,222.2 ton 25.00 /ton Yes Yes 180,556 - - 0.87 3,207 - No - 50.32 186,351 Base- Gravel 30 2,589 180,556 3,207 186,351 2740.120 Asphalt Paving - SY 30 Bituminous Base Course 3" 11,111.11 sy - - CD-NYC1 - - - - No No - 8.00 88,889 - - - No - 8.00 88,889 110 Bituminous Binder Course 1" 11,111.11 sy - - CD-NYC1 - - - - No No - 5.00 55,556 - - - No - 5.00 55,556 Asphalt Paving - SY 144,444 144,444 2760.100 Pavement Marking 6 Painted Lines 6" Wide 5,000.00 lf - - CD-NYC1 - - - - No No - 0.45 2,250 - - - No - 0.45 2,250 Pavement Marking 2,250 2,250 2820.006 Chain Link Fence- 6' 2 6' Chain Link Fence 2,000.00 lf - - CD-NYC1 - - - - No No - 13.00 26,000 - - - No - 13.00 26,000 4 6' Fence Man Gate 4.00 ea - - CD-NYC1 - - - - No No - 175.00 700 - - - No - 175.00 700 20 6' Fence Vehicle Gate 20' 1.00 ea - - CD-NYC1 - - - - No No - 880.00 880 - - - No - 880.00 880 100 3 Strand Barb Wire @ Top Add 2,000.00 lf - - CD-NYC1 - - - - No No - 6.00 12,000 - - - No - 6.00 12,000 Chain Link Fence- 6' 39,580 39,580 2892.100 Traffic Signal Systems 10 Allowance for Site Signage (Traffic Control, Bldg ID, Etc.) 1.00 ls - - CD-NYC1 - - - - No No - 10,000.00 10,000 - - - No - 10,000.00 10,000 Traffic Signal Systems 10,000 10,000 2895.100 Site Bounds 22 Allowance for Misc Site Concrete 1.00 ls 7 06-Laborer ls/ch 62.83 /ch CD-NYC1 1.1 ls /ls Yes Yes 20,000.00 20,000 - - - No - 20,000.00 20,000 Site Bounds 20,000 20,000 2900.990 Landscaping Sub -sub Landscaping Allowance 1.00 ls - - CD-NYC1 - - - - No No - 75,000.00 75,000 - - - No - 75,000.00 75,000 Landscaping Sub 75,000 75,000 3000.110 Conc Budget- Footings 3 Form/Place/Finish Footings, incl rebar/cmu dowels 150.00 cy 3 03-Conc Forming 900 6.00 6.00 mh/cy 526.91 87.82 /mh CD-NYC1 79,036 250.00 150.0 cy 250.00 /cy No No 37,500 7.00 1,050 - No - 783.91 117,586 Conc Budget- Footings 900 79,036 37,500 1,050 117,586 3000.130 Conc Budget- SOG 10 Form Place/Finish/Cure Int Slabs, incl rebar,10" typ 525.00 cy 3 03-Conc Forming 3,150 6.00 6.00 mh/cy 526.91 87.82 /mh CD-NYC1 276,627 300.00 525.0 cy 300.00 /cy No No 157,500 10.00 5,250 - No - 836.91 439,377 Conc Budget- SOG 3,150 276,627 157,500 5,250 439,377 3000.135 Conc Budget- SOMD 4 Topping Slab, 2" thick 110.00 cy 03-Conc Forming 1,100 10.00 10.00 mh/cy 878.18 87.82 /mh CD-NYC1 96,600 250.00 110.0 cy 250.00 /cy No No 27,500 20.00 2,200 - - - No - 1,148.18 126,300 Conc Budget- SOMD 1,100 96,600 27,500 2,200 126,300 3000.160 Conc Budget- Pipe Spprts *24 Form, Reinforce & Pour 18-24" Dia Conc Pipe Supports 20.00 ea 03-Conc Forming 480 24.00 24.00 mh/ea 2,107.63 87.82 /mh CD-NYC1 42,153 ea/EA 250.00 20.0 ea 250.00 /ea No No 5,000 50.00 1,000 - No - 2,407.63 48,153 3' high, 12"thick 48 Form, Reinforce & Pour 42-48" Dia Conc Pipe Supports 4.00 ea 03-Conc Forming 192 48.00 48.00 mh/ea 4,215.27 87.82 /mh CD-NYC1 16,861 ea/EA 450.00 4.0 ea 450.00 /ea No No 1,800 75.00 300 - No - 4,740.27 18,961 3' high, 18"thick 72 Form, Reinforce & Pour 66-72" Dia Conc Pipe Supports 2.00 ea 03-Conc Forming 160 80.00 80.00 mh/ea 7,025.44 87.82 /mh CD-NYC1 14,051 ea/EA 650.00 2.0 ea 650.00 /ea No No 1,300 100.00 200 - No - 7,775.44 15,551 3' high, 18"thick Conc Budget- Pipe Spprts 832 73,065 8,100 1,500 82,665 3000.990 Conc Subs- Concrete -sub Reject Water Storage Tank (7MG) 1.00 ls - - CD-NYC1 - - - - No No - 1,736,000.00 1,736,000 - - - No - 1,736,000.00 1,736,000 -sub Reclaimed Water Tank (10MG) 1.00 ls - - CD-NYC1 - - - - No No - 2,540,000.00 2,540,000 - - - No - 2,540,000.00 2,540,000 -sub Reject Water Pump Station Concrete (Same as 1.00 ls - - CD-NYC1 - - - - No No - 50,000.00 50,000 - - - No - 50,000.00 50,000 Reclaimed Water PS) -sub Deep Injection Well Slab & Pipe Supports (Same as 1.00 ls - - CD-NYC1 - - - - No No - 50,000.00 50,000 - - - No - 50,000.00 50,000 Reclaimed Water PS) Conc Subs- Concrete 4,376,000 4,376,000 3100.102 Forms- Footing 2 Continuous Footing Forms < 12" 900.00 sf 03-Conc Forming 126 0.14 0.14 mh/sf 12.30 87.82 /mh CD-NYC1 11,065 0.40 900.0 sf 0.40 /sf Yes Yes 360 - - - No - 12.70 11,425 Forms- Footing 126 11,065 360 11,425 3100.110 Forms- Column 20 Form Rectangle Columns 16 -20' 5,760.00 sf 5 03-Conc Forming 1,220 0.21 0.21 mh/sf 18.60 87.82 /mh CD-NYC1 107,115 1.58 6,048.0 sf 1.50 /sf Yes Yes 9,072 - - - No - 20.17 116,187 Forms- Column 1,220 107,115 9,072 116,187 3100.120 Forms- S-O-G 10 S.O.G. Edge Form < 1' 144.00 lf 5 03-Conc Forming 29 0.20 0.20 mh/lf 17.56 87.82 /mh CD-NYC1 2,529 1.00 sf/lf 1.16 151.2 sf 1.10 /sf Yes Yes 166 - - - No - 18.72 2,695 *12 S.O.G. Edge Form > 1' 6,156.75 sf 5 03-Conc Forming 1,354 0.22 0.22 mh/sf 19.32 87.82 /mh CD-NYC1 118,948 1.31 6,464.6 sf 1.25 /sf Yes Yes 8,081 - - - No - 20.63 127,029 14 S-O-G Const Joints < 1' 28.00 lf 5 03-Conc Forming 8 0.27 0.27 mh/lf 23.71 87.82 /mh CD-NYC1 664 1.00 sf/lf 1.16 29.4 sf 1.10 /sf Yes Yes 32 - - - No - 24.87 696 *16 S-O-G Const Joints > 1' 6,535.00 sf 5 03-Conc Forming 1,895 0.29 0.29 mh/sf 25.47 87.82 /mh CD-NYC1 166,428 1.31 6,861.8 sf 1.25 /sf Yes Yes 8,577 - - - No - 26.78 175,005 Forms- S-O-G 3,286 288,570 16,857 305,426 3100.124 Forms- Suspended Slab *2 Form Suspended Slab 0-15' 2,489.00 sf 5 03-Conc Forming 132 0.05 0.05 mh/sf 4.65 87.82 /mh CD-NYC1 11,585 1.84 2,613.5 sf 1.75 /sf Yes Yes 4,574 - - - No - 6.49 16,158 *4 Form Suspended Slab 15-up 13,126.00 sf 5 03-Conc Forming 1,050 0.08 0.08 mh/sf 7.03 87.82 /mh CD-NYC1 92,216 1.94 13,782.3 sf 1.85 /sf Yes Yes 25,497 - - - No - 8.97 117,713 *8 Suspended Slab Const Joint 327.00 lf 5 03-Conc Forming 39 0.12 0.12 mh/lf 10.54 87.82 /mh CD-NYC1 3,446 0.84 343.4 lf 0.80 /lf Yes Yes 275 - - - No - 11.38 3,721 30 Slab Edge Form < 1' 186.00 sf 5 03-Conc Forming 17 0.09 0.09 mh/sf 8.08 87.82 /mh CD-NYC1 1,503 2.36 195.3 sf 2.25 /sf Yes Yes 439 - - - No - 10.44 1,942 *32 Slab Edge Form > 1' 3,888.75 sf 03-Conc Forming 358 0.09 0.09 mh/sf 8.08 87.82 /mh CD-NYC1 31,418 2.75 3,888.8 sf 2.75 /sf Yes Yes 10,694 - - - No - 10.83 42,112 Forms- Suspended Slab 1,596 140,168 41,479 181,647 3100.130 Forms- Shoring *6 Shore Suspended Slabs 277,454.00 cf 03-Conc Forming 3,698 **** **** mh/cf 1.17 87.82 /mh CD-NYC1 324,711 0.27 277,454.0 cf 0.27 /cf Yes Yes 74,913 - - - No - 1.44 399,623 Forms- Shoring 3,698 324,711 74,913 399,623 3100.164 Forms- Equipment Pad 6 Equipment Pad Form 6" 174.00 sf 5 03-Conc Forming 152 0.88 0.88 mh/sf 76.84 87.82 /mh CD-NYC1 13,370 1.26 182.7 sf 1.20 /sf Yes Yes 219 - - - No - 78.10 13,590 *10 Equipment Pad Form > 8" 1,326.40 sf 5 03-Conc Forming 1,194 0.90 0.90 mh/sf 79.04 87.82 /mh CD-NYC1 104,834 1.26 1,392.7 sf 1.20 /sf Yes Yes 1,671 - - - No - 80.30 106,505 Forms- Equipment Pad 1,346 118,204 1,890 120,094 3100.180 Forms- Wall Forms *b 17 Panel Form System 16'-> 46,834.00 sf 5 03-Conc Forming 8,196 0.18 0.18 mh/sf 15.37 87.82 /mh CD-NYC1 719,752 1.89 49,175.7 sf 1.80 /sf Yes Yes 88,516 - - - No - 17.26 808,268 *c 4 Job Built with Plyform 0-4' 6,830.00 sf 5 03-Conc Forming 1,694 0.25 0.25 mh/sf 21.78 87.82 /mh CD-NYC1 148,750 1.68 7,171.5 sf 1.60 /sf Yes Yes 11,474 - - - No - 23.46 160,224 *c 8 Job Built with Plyform 4-8' 10,548.00 sf 5 03-Conc Forming 3,143 0.30 0.30 mh/sf 26.17 87.82 /mh CD-NYC1 276,039 1.79 11,075.4 sf 1.70 /sf Yes Yes 18,828 - - - No - 27.96 294,867 *c 12 Job Built with Plyform 8-12' 9,666.00 sf 5 03-Conc Forming 1,924 0.20 0.20 mh/sf 17.48 87.82 /mh CD-NYC1 168,921 1.89 10,149.3 sf 1.80 /sf Yes Yes 18,269 - - - No - 19.37 187,190 *c 17 Job Built with Plyform 16'-> 38,188.00 sf 5 03-Conc Forming 6,683 0.18 0.18 mh/sf 15.37 87.82 /mh CD-NYC1 586,879 2.10 40,097.4 sf 2.00 /sf Yes Yes 80,195 - - - No - 17.47 667,074

18 Sample Project Attachment 4-1 EstimatingPage 14 Reports Labor Productivity Detail Report (Item) 5/15/2008 7:03 PM

DB Base Labor Produc- Estimated Labor Labor Rate Labor Material Conv Material Matl Matl Material Sub Equip Equip Other Oth Other Level Spreadsheet Level Takeoff Quantity % Crew Produc- Labor Price Material Quantity Material Price Sub Cost/Unit Total Cost/Unit Total Amount Man Hrs tivity Adj Productivity Cost/Unit Table Amount Factor Cost/Unit Waste Tax Amount Amount Cost/Unit Amount Cost/Unit Tax Amount 3 tivity 15203.014 DI Flanged 90 ell 24 DI Flanged 90 SR ell 24" 4.00 ea 15-PipeCrew 48 12.00 12.00 mh/ea 1,089.30 90.78 /mh CD-NYC1 4,357 ###### lb/ea 3,596.00 4,960.0 lb 2.90 /lb No Yes 14,384 - - - - - No - 4,685.30 18,741 36 DI Flanged 90 SR ell 36" 2.00 ea 15-PipeCrew 36 18.00 18.00 mh/ea 1,633.95 90.78 /mh CD-NYC1 3,268 ###### lb/ea 21,460.00 14,800.0 lb 2.90 /lb No Yes 42,920 - - - - - No - 23,093.95 46,188 42 DI Flanged 90 SR ell 42" 2.00 ea 15-PipeCrew 40 20.00 20.00 mh/ea 1,815.50 90.78 /mh CD-NYC1 3,631 ###### lb/ea 29,000.00 20,000.0 lb 2.90 /lb No Yes 58,000 - - - - - No - 30,815.50 61,631 DI Flanged 90 ell 449 40,713 163,386 204,099 15203.024 DI Flanged Wye 8 DI Flanged Wye 8" 2.00 ea 15-PipeCrew 8 4.00 4.00 mh/ea 363.10 90.78 /mh CD-NYC1 726 478.40 2.0 ea 478.40 /ea No Yes 957 - - - - - No - 841.50 1,683 DI Flanged Wye 8 726 957 1,683 15203.030 DI Flanged Con Red *604 DI Flanged Con Red 6x4" 6.00 ea 15-PipeCrew 18 3.00 3.00 mh/ea 272.33 90.78 /mh CD-NYC1 1,634 45.00 lb/ea 117.00 270.0 lb 2.60 /lb No Yes 702 - - - - - No - 389.33 2,336 *1816 DI Flanged Con Red 18x16" 13.00 ea 15-PipeCrew 130 10.00 10.00 mh/ea 907.75 90.78 /mh CD-NYC1 11,801 335.00 lb/ea 670.00 4,355.0 lb 2.00 /lb No Yes 8,710 - - - - - No - 1,577.75 20,511 DI Flanged Con Red 148 13,435 9,412 22,847 15203.065 DI Flanged Wall Pipe 582 DI Flg x Flg Wall Pipe 4" x 2' CL53 2.00 ea 15-PipeCrew 8 4.00 4.00 mh/ea 363.10 90.78 /mh CD-NYC1 726 348.40 2.0 ea 348.40 /ea No Yes 697 - - - - - No - 711.50 1,423 *1136 DI Flg x Flg Wall Pipe 6" x 2' CL53 10.00 ea 15-PipeCrew 50 5.00 5.00 mh/ea 453.88 90.78 /mh CD-NYC1 4,539 403.00 10.0 ea 403.00 /ea No Yes 4,030 - - - - - No - 856.88 8,569 *1690 DI Flg x Flg Wall Pipe 8" x 2' CL53 4.00 ea 15-PipeCrew 24 6.00 6.00 mh/ea 544.65 90.78 /mh CD-NYC1 2,179 496.60 4.0 ea 496.60 /ea No Yes 1,986 - - - - - No - 1,041.25 4,165 2244 DI Flg x Flg Wall Pipe 10" x 2' CL53 6.00 ea 15-PipeCrew 48 8.00 8.00 mh/ea 726.20 90.78 /mh CD-NYC1 4,357 604.50 6.0 ea 604.50 /ea No Yes 3,627 - - - - - No - 1,330.70 7,984 5014 DI Flg x Flg Wall Pipe 20" x 2' CL53 2.00 ea 15-PipeCrew 22 11.00 11.00 mh/ea 998.53 90.78 /mh CD-NYC1 1,997 1,267.50 2.0 ea 1,267.50 /ea No Yes 2,535 - - - - - No - 2,266.03 4,532 5567 DI Flg x Flg Wall Pipe 24" x 1' CL53 5.00 ea 15-PipeCrew 60 12.00 12.00 mh/ea 1,089.30 90.78 /mh CD-NYC1 5,447 1,207.00 5.0 ea 1,207.00 /ea No Yes 6,035 - - - - - No - 2,296.30 11,482 5568 DI Flg x Flg Wall Pipe 24" x 2' CL53 2.00 ea 15-PipeCrew 24 12.00 12.00 mh/ea 1,089.30 90.78 /mh CD-NYC1 2,179 1,652.30 2.0 ea 1,652.30 /ea No Yes 3,305 - - - - - No - 2,741.60 5,483 DI Flanged Wall Pipe 236 21,423 22,215 43,638 15203.091 DI Blind Flange 4 DI Flat Blind Flange 4" 2.00 ea 15-PipeCrew 5 2.50 2.50 mh/ea 226.94 90.78 /mh CD-NYC1 454 10.00 lb/ea 26.00 20.0 lb 2.60 /lb No Yes 52 - - - - - No - 252.94 506 8 DI Flat Blind Flange 8" 1.00 ea 15-PipeCrew 4 4.00 4.00 mh/ea 363.10 90.78 /mh CD-NYC1 363 80.00 lb/ea 208.00 80.0 lb 2.60 /lb No Yes 208 - - - - - No - 571.10 571 18 DI Flat Blind Flange 18" 3.00 ea 15-PipeCrew 30 10.00 10.00 mh/ea 907.75 90.78 /mh CD-NYC1 2,723 175.00 lb/ea 350.00 525.0 lb 2.00 /lb No Yes 1,050 - - - - - No - 1,257.75 3,773 DI Blind Flange 39 3,540 1,310 4,850 15204.001 DI Mech-Joint Pipe by LF 15 DI Mech-Joint Pipe 8" 400.00 lf 7 15-PipeCrew 52 0.13 0.13 mh/lf 11.80 90.78 /mh CD-NYC1 4,720 31.10 lb/lf 66.55 13,310.8 lb 2.00 /lb Yes Yes 26,622 - - - - - No - 78.36 31,342 55 DI Mech-Joint Pipe 30" 100.00 lf 7 15-PipeCrew 26 0.26 0.26 mh/lf 23.60 90.78 /mh CD-NYC1 2,360 162.60 lb/lf 186.16 17,398.2 lb 1.07 /lb Yes Yes 18,616 - - - - - No - 209.76 20,976 DI Mech-Joint Pipe by LF 78 7,080 45,238 52,318 15204.013 DI Mech-Joint 45 ell 9 DI Mech-Joint 45 ell 8" 10.00 ea 15-PipeCrew 40 4.00 4.00 mh/ea 363.10 90.78 /mh CD-NYC1 3,631 124.20 10.0 ea 124.20 /ea No Yes 1,242 - - - - - No - 487.30 4,873 DI Mech-Joint 45 ell 40 3,631 1,242 4,873 15204.014 DI Mech-Joint 90 ell 12 DI Mech-Joint 90 ell 8" 4.00 ea 15-PipeCrew 16 4.00 4.00 mh/ea 363.10 90.78 /mh CD-NYC1 1,452 137.70 4.0 ea 137.70 /ea No Yes 551 - - - - - No - 500.80 2,003 DI Mech-Joint 90 ell 16 1,452 551 2,003 15204.024 DI Mech-Joint Wye 5 DI Mech-Joint Wye 8" 8.00 ea 15-PipeCrew 32 4.00 4.00 mh/ea 363.10 90.78 /mh CD-NYC1 2,905 305.10 8.0 ea 305.10 /ea No Yes 2,441 - - - - - No - 668.20 5,346 DI Mech-Joint Wye 32 2,905 2,441 5,346 15204.065 DI Mech-Joint Wall Pipe 17 DI MJ x MJ Wall Pipe 8" x 2' CL53 8.00 ea 15-PipeCrew 48 6.00 6.00 mh/ea 544.65 90.78 /mh CD-NYC1 4,357 330.75 8.0 ea 330.75 /ea No Yes 2,646 - - - - - No - 875.40 7,003 57 DI MJ x MJ Wall Pipe 30" x 2½' CL53 1.00 ea 15-PipeCrew 16 16.00 16.00 mh/ea 1,452.40 90.78 /mh CD-NYC1 1,452 2,880.00 1.0 ea 2,880.00 /ea No Yes 2,880 - - - - - No - 4,332.40 4,332 DI Mech-Joint Wall Pipe 64 5,810 5,526 11,336 15204.080 DI Restraining Joint Ftg 55 DI Restraining Joint (RJ) Ftg 30" 12.00 ea 15-PipeCrew 66 5.50 5.50 mh/ea 499.26 90.78 /mh CD-NYC1 5,991 526.00 12.0 ea 526.00 /ea No Yes 6,312 - - - - - No - 1,025.26 12,303 DI Restraining Joint Ftg 66 5,991 6,312 12,303 15211.101 Copper "L" Pipe 25 Copper Pipe - Soldered - Type "L" - 2 200.00 lf 7 15-PipeCrew 52 0.26 0.26 mh/lf 23.60 90.78 /mh CD-NYC1 4,720 4.14 214.0 lf 3.87 /lf Yes Yes 828 - - - - - No - 27.74 5,548 ---- H20 Pipe Budget 1.00 ls 15-PipeCrew 40 40.00 40.00 mh/ls 3,631.00 90.78 /mh CD-NYC1 3,631 6,000.00 1.0 ls 6,000.00 /ls Yes Yes 6,000 - - - - - No - 9,631.00 9,631 Copper "L" Pipe 92 8,351 6,828 15,179 15211.114 Copper 90 Ell 116 Copper Pipe 90 Ell - Type "L" - 2 32.00 ea 15-PipeCrew 0 0.01 0.01 mh/ea 0.91 90.78 /mh CD-NYC1 29 12.42 32.0 ea 12.42 /ea No Yes 397 - - - - - No - 13.33 426 Copper 90 Ell 0 29 397 426 15211.120 Copper Tee 116 Copper Pipe Tee - Type "L" - 2 6.00 ea 15-PipeCrew 0 0.01 0.01 mh/ea 0.91 90.78 /mh CD-NYC1 5 23.20 6.0 ea 23.20 /ea No Yes 139 - - - - - No - 24.11 145 Copper Tee 0 5 139 145 15211.143 Copper Union 50 Copper Pipe Union - Type "L" - 2 19.00 ea 15-PipeCrew 15 0.80 0.80 mh/ea 72.62 90.78 /mh CD-NYC1 1,380 34.00 19.0 ea 34.00 /ea No Yes 646 - - - - - No - 106.62 2,026 Copper Union 15 1,380 646 2,026 15215.102 PVC Pipe Sch 80 10 PVC Pipe Sch 80 1 440.00 lf 7 15-PipeCrew 119 0.27 0.27 mh/lf 24.51 90.78 /mh CD-NYC1 10,784 1.00 LF/lf 1.91 470.8 LF 1.78 /LF Yes Yes 839 - - - - - No - 26.42 11,623 *10 PVC Pipe Sch 80 1 300.00 lf 7 15-PipeCrew 81 0.27 0.27 mh/lf 24.51 90.78 /mh CD-NYC1 7,353 1.00 LF/lf 1.41 321.0 LF 1.32 /LF Yes Yes 424 - - - - - No - 25.92 7,777 15 PVC Pipe Sch 80 1-½ 440.00 lf 7 15-PipeCrew 119 0.27 0.27 mh/lf 24.51 90.78 /mh CD-NYC1 10,784 1.00 LF/lf 3.19 470.8 LF 2.98 /LF Yes Yes 1,405 - - - - - No - 27.70 12,189 20 PVC Pipe Sch 80 2 200.00 lf 7 15-PipeCrew 54 0.27 0.27 mh/lf 24.51 90.78 /mh CD-NYC1 4,902 1.00 LF/lf 4.37 214.0 LF 4.08 /LF Yes Yes 873 - - - - - No - 28.88 5,775 20 PVC Pipe Sch 80 2 440.00 lf 7 15-PipeCrew 119 0.27 0.27 mh/lf 24.51 90.78 /mh CD-NYC1 10,784 1.00 LF/lf 5.89 470.8 LF 5.51 /LF Yes Yes 2,593 - - - - - No - 30.40 13,377 *20 PVC Pipe Sch 80 2 1,620.00 lf 7 15-PipeCrew 437 0.27 0.27 mh/lf 24.51 90.78 /mh CD-NYC1 39,705 1.00 LF/lf 4.37 1,733.4 LF 4.08 /LF Yes Yes 7,072 - - - - - No - 28.88 46,777 *40 PVC Pipe Sch 80 4 360.00 lf 7 15-PipeCrew 97 0.27 0.27 mh/lf 24.51 90.78 /mh CD-NYC1 8,823 1.00 LF/lf 9.75 385.2 LF 9.11 /LF Yes Yes 3,509 - - - - - No - 34.26 12,333 *60 PVC Pipe Sch 80 6 560.00 lf 7 15-PipeCrew 151 0.27 0.27 mh/lf 24.51 90.78 /mh CD-NYC1 13,725 1.00 LF/lf 18.61 599.2 LF 17.39 /LF Yes Yes 10,420 - - - - - No - 43.12 24,145 PVC Pipe Sch 80 1,177 106,860 27,135 133,995 15215.313 PVC 80 Soc 45 Ell 40 PVC 80 45 Ell SxS 4 6.00 ea 15-PipeCrew 9 1.50 1.50 mh/ea 136.16 90.78 /mh CD-NYC1 817 125.00 6.0 ea 125.00 /ea No Yes 750 - - - - - No - 261.16 1,567 60 PVC 80 45 Ell SxS 6 3.00 ea 15-PipeCrew 6 2.00 2.00 mh/ea 181.55 90.78 /mh CD-NYC1 545 104.00 3.0 ea 104.00 /ea No Yes 312 - - - - - No - 285.55 857 PVC 80 Soc 45 Ell 15 1,362 1,062 2,424 15215.314 PVC 80 Soc 90 Ell 10 PVC 80 90 Ell SxS 1 35.00 ea 15-PipeCrew 13 0.37 0.37 mh/ea 33.59 90.78 /mh CD-NYC1 1,176 5.35 35.0 ea 5.35 /ea No Yes 187 - - - - - No - 38.93 1,363 *10 PVC 80 90 Ell SxS 1 36.00 ea 15-PipeCrew 13 0.37 0.37 mh/ea 33.59 90.78 /mh CD-NYC1 1,209 3.96 36.0 ea 3.96 /ea No Yes 143 - - - - - No - 37.55 1,352 15 PVC 80 90 Ell SxS 1-½ 35.00 ea 15-PipeCrew 15 0.42 0.42 mh/ea 38.13 90.78 /mh CD-NYC1 1,334 7.66 35.0 ea 7.65 /ea No Yes 268 - - - - - No - 45.78 1,602 20 PVC 80 90 Ell SxS 2 10.00 ea 15-PipeCrew 5 0.45 0.45 mh/ea 40.85 90.78 /mh CD-NYC1 408 6.86 10.0 ea 6.86 /ea No Yes 69 - - - - - No - 47.71 477 20 PVC 80 90 Ell SxS 2 35.00 ea 15-PipeCrew 16 0.45 0.45 mh/ea 40.85 90.78 /mh CD-NYC1 1,430 9.26 35.0 ea 9.26 /ea No Yes 324 - - - - - No - 50.11 1,754 *20 PVC 80 90 Ell SxS 2 100.00 ea 15-PipeCrew 45 0.45 0.45 mh/ea 40.85 90.78 /mh CD-NYC1 4,085 6.86 100.0 ea 6.86 /ea No Yes 686 - - - - - No - 47.71 4,771 40 PVC 80 90 Ell SxS 4 16.00 ea 15-PipeCrew 24 1.50 1.50 mh/ea 136.16 90.78 /mh CD-NYC1 2,179 27.42 16.0 ea 27.42 /ea No Yes 439 - - - - - No - 163.58 2,617 60 PVC 80 90 Ell SxS 6 8.00 ea 15-PipeCrew 16 2.00 2.00 mh/ea 181.55 90.78 /mh CD-NYC1 1,452 78.01 8.0 ea 78.01 /ea No Yes 624 - - - - - No - 259.56 2,076 PVC 80 Soc 90 Ell 146 13,273 2,739 16,012 15215.320 PVC 80 Soc Tee 10 PVC 80 Tee SxSxS 1 12.00 ea 15-PipeCrew 6 0.54 0.54 mh/ea 49.02 90.78 /mh CD-NYC1 588 20.78 12.0 ea 20.78 /ea No Yes 249 - - - - - No - 69.80 838 10 PVC 80 Tee SxSxS 1 2.00 ea 15-PipeCrew 1 0.54 0.54 mh/ea 49.02 90.78 /mh CD-NYC1 98 15.39 2.0 ea 15.39 /ea No Yes 31 - - - - - No - 64.41 129 15 PVC 80 Tee SxSxS 1-½ 12.00 ea 15-PipeCrew 7 0.61 0.61 mh/ea 55.37 90.78 /mh CD-NYC1 664 26.69 12.0 ea 26.69 /ea No Yes 320 - - - - - No - 82.06 985 20 PVC 80 Tee SxSxS 2 3.00 ea 15-PipeCrew 2 0.67 0.67 mh/ea 60.82 90.78 /mh CD-NYC1 182 21.27 3.0 ea 21.27 /ea No Yes 64 - - - - - No - 82.09 246 20 PVC 80 Tee SxSxS 2 12.00 ea 15-PipeCrew 8 0.67 0.67 mh/ea 60.82 90.78 /mh CD-NYC1 730 28.71 12.0 ea 28.71 /ea No Yes 345 - - - - - No - 89.53 1,074 *20 PVC 80 Tee SxSxS 2 50.00 ea 15-PipeCrew 34 0.67 0.67 mh/ea 60.82 90.78 /mh CD-NYC1 3,041 21.27 50.0 ea 21.27 /ea No Yes 1,064 - - - - - No - 82.09 4,104

19 Attachment 4-1 Estimating Reports

Sample Project Page 27 Labor Productivity Detail Report (Item) 5/15/2008 7:03 PM

Estimate Totals

Description Amount Totals Hours Rate Basis Percent of Total Labor 30,949,175 394,139 hrs 21.67% Material 35,656,998 24.97% Subcontract 5,802,535 4.06% Equipment 2,904,813 84,108 hrs 2.03% Other 3,260,129 2.28% 78,573,650 78,573,650 55.02 Small Tools & Supplies 1,547,459 5.00 % C 1.08% Incidental Overtime Allowance 1,547,459 5.00 % C 1.08% Overtime Allowance - 48 hr/wk 2,321,188 7.50 % C 1.63% Overtime Allowance - 60 hr/wk 3,094,918 10.00 % C 2.17% Overtime Allowance - 70 hr/wk 4,642,376 15.00 % C 3.25% Subcontractor OH&P 8,643,101 11.00 % C 6.05% Contractor Profit 15,714,730 20.00 % T 11.00% Contractor Bond & Insurance 3,142,946 4.00 % T 2.20% Project Contingency 23,572,095 30.00 % T 16.51% Total 142,799,922

THIS IS A SAMPLE REPORT TO ILLUSTRATE REPORT LAYOUT ONLY. QUANTITIES, RATES, MARKUPS, ETC. SHOULD NOT BE USED FOR ESTIMATING PURPOSES. NOT ALL PAGES OF THE REPORT ARE INCLUDED IN THIS SAMPLE.

20 Attachment 4-2 AACE 34R-05

Attachment 4-2 AACE 34R-05

AACE International Recommended Practice No. 34R-05

BASIS OF ESTIMATE TCM Framework: 7.3 – Cost Estimating and Budgeting

Acknowledgments: Todd Pickett, CCC (Author) Stephen M. Jacobson CCC Peter R. Bredehoeft, Jr. Carlton W. Karlik, PE Ted A. Downen Christopher L. Kinney Larry R. Dysert, CCC Donald F. McDonald, Jr. PE CCE PSP Bruce G. Elliott, CCC Bernard A. Pietlock CCC John K. Hollmann, PE CCE Richard A. Selg, CCE

Copyright 2007 AACE, Inc. AACE International Recommended Practices

1 Attachment 4-2 AACE 34R-05

AACE International Recommended Practice No. 34R-05 BASIS OF ESTIMATE TCM Framework: 7.3 – Cost Estimating and Budgeting

May 2, 2007

PURPOSE

AACE International’s Total Cost Management (TCM) Framework identifies a basis of estimate (BOE) document as a required component of a cost estimate. As a Recommended Practice (RP) of AACE International, the template outlined in the following sections provides guidelines for the structure and content of a cost basis of estimate.

In the TCM Framework, the BOE is characterized as the one deliverable that defines the scope of the project, and ultimately becomes the basis for change management. When prepared correctly, any person with capital project experience can use the BOE to understand and assess the estimate, independent of any other supporting documentation. A well-written BOE achieves those goals by clearly and concisely stating the purpose of the estimate being prepared (i.e. cost study, project options, funding, etc.), the project scope, pricing basis, allowances, assumptions, exclusions, cost risks and opportunities, and any deviations from standard practices. In addition the BOE is a documented record of pertinent communications that have occurred and agreements that have been made between the estimator and other project stakeholders.

A well prepared basis of estimate will:

• Document the overall project scope. • Communicate the estimator’s knowledge of the project by demonstrating an understanding of scope and schedule as it relates to cost. • Alert the project team to potential cost risks and opportunities. • Provide a record of key communications made during estimate preparation. • Provide a record of all documents used to prepare the estimate. • Act as a source of support during dispute resolutions. • Establish the initial baseline for scope, quantities and cost for use in cost trending throughout the project. • Provide the historical relationships between estimates throughout the project lifecycle. • Facilitate the review and validation of the cost estimate. This RP is intended to be a guideline, not a standard. It is understood that not all organizations that prepare estimates employ the same processes and practices, and therefore, may opt to use this information either in part or in its entirety.

RECOMMENDED PRACTICE

The primary intent of this RP is to provide a guideline for the topics and contents to be included in typical BOE. However, before describing the template contents there are a few points of significance worth noting:

• Be factually complete, but be concise. • Be able to support your facts and findings. • Identify estimating team members and their roles. • Describe the tools, techniques, estimating methodology, and data used to develop the cost estimate. • Identify other projects that were referenced or benchmarked during estimate preparation. • Develop the cost estimate and the BOE concurrently. • The BOE establishes the context of the estimate, and supports review and validation.

Copyright 2007 AACE International, Inc. AACE International Recommended Practices

2 Attachment 4-2 AACE 34R-05

Basis of Estimate 2 of 6

May 2, 2007 • Qualify any rates or factors that are referenced either in the estimate or BOE; e.g. productivity can be expressed as either units/time (linear feet/hour) or time/units (hours/linear foot). The following describes the suggested topics and contents included in a typical BOE.

Purpose In this initial section of a basis of estimate, the estimator should provide a brief and concise description for the total project. The type of project should be identified (i.e., new facilities, addition to existing, revamp of existing, etc.), as well as the type and capacity of the process units, the location of the facility, and the overall timing of the project.

Project Scope Description This section of the estimate basis should be organized to correspond with the project’s work breakdown structure (i.e., plant, building, floor, etc.). A semi-detailed description of the scope of work should be provided for each major segment of the project. Identify any major pieces of process equipment or components. It’s also good practice to indicate the primary trades that will be involved with the project. Be as thorough as necessary, without being overly descriptive, so as to adequately explain the scope of work being estimated.

Methodology The BOE should indicate the primary estimating methodology used to prepare the cost estimate. This should include documentation of the use of cost resources, historical data and project benchmarking. Documenting the level of effort or man-hours used in preparation of the estimate may also be helpful.

Estimate Classification The AACE International estimate classification should be identified, along with reasons or justification used in the selection of the estimate classification.

Design Basis Company standards will typically specify the technical and project information required for the classification of the estimate that is being prepared. In this section, the estimator will identify the types and status of engineering and design deliverables that were provided to prepare the estimate including any design basis assumptions. Two attachments to the estimate basis should be referenced: 1) an estimate deliverables checklist that is aligned with the company’s standard project process; and 2) a listing of all engineering drawings (including revision number and date), a well as other design information, such as specifications, equipment lists, units of measure (imperial vs. metric), etc.

In addition it may be useful to document specific quantity metrics for particular projects, such as overall excavation and backfill quantities, overall concrete volumes, overall piping quantities, etc. These may be organized by facilities, process train or manufacturing unit.

If material take-off’s (MTO’s) are provided to the estimator, identify specifically who developed the MTO’s and the methodology used.

Planning Basis This section documents the project management, engineering, design, procurement, fabrication, and construction approaches to the project. The contracting and resource strategies should be identified, as well as any assumptions that were made with regard to the workweek schedule (hours worked per day, days worked per week, shifts worked per day, etc.) and planned use of overtime. Any assumptions made regarding constructability, modularization, use of specialized construction equipment should also be noted here.

The overall project schedule and key milestones should be identified.

Copyright 2007 AACE International, Inc. AACE International Recommended Practices

3 Attachment 4-2 AACE 34R-05

Basis of Estimate 3 of 6

May 2, 2007 Cost Basis Describe the methods and sources used for determining all material, labor and subcontract pricing. Identify the following:

• Pricing sources for all major equipment (vendor quotes, historical data, etc,). • Bulk material and commodity pricing sources, including any discount strategies. • The pricing source for all labor hours, and all labor productivity adjustments. Provide appropriate detail if productivities vary by trade and/or location within the project (plant, etc.). • All wage rates used (including crew/craft rates, craft mix, etc.). Identify all items included in all-in rates (if used). • Pricing source and methodology for construction indirects. • Pricing source for all start-up costs. • Pricing source and methodology for all home office costs (project management, engineering, design, etc.). Document the basis for any contractor fee costs. • Pricing source and methodology for costs such as freight, taxes, duties, etc. • Pricing source for any owner’s costs included in the estimate. • Currency exchange rates if applicable, as well as the stability and/or volatility of rates. • Escalation indices used, and the method of calculation (including duration). • Contingency development and basis. • Location factors used and the basis for these factors. • Influence of local market conditions. • Capital costs vs. expense costs, or other categorization as necessary. • Any other pricing factors or external influences that may have a significant impact on project cost should be identified. Allowances In this section, identify the level and types of allowances used in the estimate. Describe the basis for the common estimating allowances such as material take-off allowances, overbuy allowances, design allowances for engineered equipment, congestion allowances, working height allowances, etc.

This section should also describe any other costs that have not been detailed in the body of the estimate, such as lump-sum allowances for specific areas of scope or any other factored costs not described elsewhere in the estimate basis.

Assumptions Any other assumptions made by the estimator but not documented elsewhere in the estimate basis should be included in this section. This may include such assumptions as an adequate labor supply being available, adequate funding available, site conditions, etc. Small assumptions can change into major assumptions throughout the life of the project. Therefore, it is better to document assumptions then not to document at all.

Exclusions In this section, the estimator should document all potential items of cost which a reviewer might associate with the project, but for which no costs have been included in the estimate. Asbestos abatement, removal of hazardous wastes, acquisition of land, taxes, financing costs, licensing costs, etc. are examples of potential items that may need to be identified.

Exceptions The estimator should identify any anomalies or variances to your organization’s standard estimating practices. This section should document any significant deviations from the project and/or engineering deliverables normally required for the applicable class of estimate. A good practice is to provide a checklist as an attachment to the BOE that will document any exceptions that are identified. This checklist should correspond to the company’s standard estimating practices.

Copyright 2007 AACE International, Inc. AACE International Recommended Practices

4 Attachment 4-2 AACE 34R-05

Basis of Estimate 4 of 6

May 2, 2007 Risks and Opportunities Any areas of the estimate containing significant risk or opportunity should be identified. If a formal risk analysis study has been prepared then it should be described (e.g. methodology, technique, etc.). In particular, this section should identify those cost elements that have been identified with high or very high risk or opportunity values. The risk analysis report (or summary) should be provided as an attachment to the BOE.

Contingencies Contingency is a cost element of the estimate used to cover the uncertainty and variability associated with a cost estimate, and unforeseeable elements of cost within the defined project scope. Contingency covers inadequacies in complete project scope definition, estimating methods, and estimating data. Contingency specifically excludes changes in project scope, and unforeseen major events such as earthquakes, prolonged labor strikes, etc. The amount of contingency included in the estimate should be identified, as well as the methods used to determine the contingency amount. If risk analysis techniques were utilized to develop the contingency amount, the associated confidence level should also be identified.

Management Reserve Contingency is not intended to cover the costs associated with changes in project scope. If the project needs to provide an allowance for anticipated changes in scope, or to cover the costs for items that may be required but have not yet been specifically identified as being included in the current project scope, then that amount of cost, typically referred to as management reserve, should be identified here.

The intended purpose and use of management reserve should be clearly identified. The approval process, management and tracking of the management reserve should also be clearly identified.

Reconciliation Provide an overview of the major differences between the current estimate and the last published estimate prepared for this project. Identify the cost impacts due to scope changes, pricing updates, labor productivity adjustments, estimate refinement, etc. A more detailed reconciliation or cost trending report can be provided as an additional attachment if necessary.

Benchmarking This section should document any comparisons of overall estimate metrics, ratios, and factors with similar projects, historical data, and industry data. Projects used in the benchmark comparisons should be similar in process type and overall value. If significant variations of the estimated project costs versus the benchmarks exist, those inconsistencies should be identified and commented upon. A more detailed benchmark analysis report may be included as an attachment to the BOE.

Estimate Quality Assurance Since estimate reviews are the means for testing the quality of the estimate, this section of the BOE should identify all estimate reviews that have taken place to date, and any additional reviews that are proposed to take place. All review comments or analysis should be included as an attachment to the BOE.

Estimating Team In this final section, all members of the estimating team should be identified, including roles and responsibilities.

Attachments Several supporting documents will generally be included with the basis of estimate. 1) Attachment A: Estimate Deliverables Checklist Attachment A: Estimate Deliverables Checklist

Copyright 2007 AACE International, Inc. AACE International Recommended Practices

5 Attachment 4-2 AACE 34R-05

Basis of Estimate 5 of 6

May 2, 2007 Attach a completed estimate deliverables checklist indicating the project and engineering deliverables that should be provided to support preparation of the estimate for the associated estimate classification, and whether they were in fact available during preparation of the estimate. 2) Attachment B: Reference Documents Attachment B: Reference Documents Document the drawings, manuals, texts, notes, specifications, and other references used in developing the estimate. Identify the revisions and date of issue for key documents.

Additional Attachments Include any other attachments that may be necessary or required (reconciliation report, benchmarking report, risk analysis report, escalation calculations, etc.).

LEVEL OF DEATIL IN THE BASIS OF ESTIMATE

It is often not a simple matter to determine just how much detail should be provided in a BOE. Several factors may come into play during the preparation of the cost estimate that will help determine that answer but, it is the estimator’s best judgment that will ultimately decide the appropriate level of detail in the BOE.

Level of Project Definition Estimates are prepared at various stages of a project. A more detailed estimate will generally require a more detailed BOE, however that is not always the case. A conceptual estimate will probably be based on a limited amount of scope but may require a more detailed basis of estimate. It's not uncommon for a BOE for a conceptual estimate to be more thorough than one prepared for a more detailed estimate because there are often more assumptions made at the conceptual stage of a project that require greater documentation.

Conversely, there may be times when the project definition is so complete or simplistic that a BOE does not require a great amount of detail. A three or four page document may be sufficient to convey the BOE.

Cost Value of the Project Typically, a more expensive a project will require a more detailed BOE. However, projects of lesser cost can require an extensive BOE to fully communicate major assumptions that constrain or reduce the cost.

Type of Project The type of project can also affect the BOE. For example, the BOE for a direct purchase (e.g., single piece of large equipment) may be less detailed than for a construction project

Other Factors Other factors that affect the level of detail in a BOE are: work breakdown structure (WBS), consideration for new technologies, contracting strategy, etc.

The BOE should contain a concise level of detail to fully support the review of the estimate by those that have not been a part of the preparation of the estimate. The BOE provides a definition of the scope of the project as estimated, and should establish the basis for change management subsequent to publication of the estimate.

REFERENCES

1. Hollmann, John K., Editor. Total Cost Management Framework: A Process for Applying the Skills and Knowledge of Cost Engineering, Morgantown, WV: AACE International, 2006.

Copyright 2007 AACE International, Inc. AACE International Recommended Practices

6 Attachment 4-2 AACE 34R-05

Basis of Estimate 6 of 6

May 2, 2007 CONTRIBUTORS

Todd Pickett, CCC (Author) Peter R. Bredehoeft, Jr. Ted A. Downen Larry R. Dysert, CCC Bruce G. Elliott, CCC John K. Hollmann, PE CCE Stephen M. Jacobson CCC Carlton W. Karlik, PE Christopher L. Kinney Donald F. McDonald, Jr. PE CCE PSP Bernard A. Pietlock CCC Richard A. Selg, CCE

Copyright 2007 AACE International, Inc. AACE International Recommended Practices

7 Attachment 4-2 AACE 34R-05

8 Chapter 5 Contingency Contingency Chapter 5

Chapter 5 Contingency

Chapter 5 – Contingency

Introduction

The cost of constructing large capital projects can be subject to significant risks and variability that if not prop- erly managed and addressed, can result in significant estimating errors. This risk must be managed through the proper use of allowances, contingencies, and management reserve to help minimize variations in cost estimates as the project advances through the different stages of development. While applying contingency to cost estimates cannot guarantee that a budget established at some milestone during project development will not be exceeded when the project is bid, properly applied contingency can decrease this probability.

Allocation of contingency at every phase of cost estimating should be based on sound cost estimating practices and must be allocated based on established risk factors. The amount of contingency needed and the risk factors that this contingency addresses shifts throughout project development and the estimate must reflect these shifts. For example, in the early stages of estimating, project definition level is the most important factor in cost estimating risk and a significant amount of contingency must be applied to offset this risk. In later stages of project development, project definition is often well-established and other risk factors such as market conditions or material escalation rise in importance. Fixed contingency allocations at various stages of project development often lead to substantial estimating error and do not necessarily reflect the measurable project risks.

Industry best practice dictates that all cost estimates, regardless of the phase in the project development cycle, carry some level of funding for unknown project conditions. This funding is typically termed contin- gency, and may affect the ultimate cost of the project. When evaluating contingency, impacts of delays to the project schedule must also be considered as they may significantly affect the final cost of a project.

Levels of contingency may vary as project development progresses, and the methods for determining con- tingency amounts may differ Figure 5-1 E x a m p l e o f E s t i m a t e from project to project, but a Distribution at E a c h E s t i m a t e C l a s s structured approach for de- in the Project Life Cycle termining contingency must What is Shown be followed and documented What is Know but Not Shown during estimate preparation. 250 Contingency As the design progresses, the 200 required contingency should 150 normally decrease reflecting 100 the increased certainty in the 50 project scope and the oppor- ENGINEER’S ESTIMATE ($M) ENGINEER’S ESTIMATE 0 tunity to mitigate risks. 5 4 3 2 1 ESTIMATE CLASS

5-1 Estimate Review and Approval June 2008

F i g u r e 5 - 2 Probability Distribution Curve of Engineer’s Estimate of the Bid Price 100% 90% 80% 70% 60% 50% 40% 30% 20% 10%

PROBABILITY OF BID BELOW ENGINEER’S ESTIMATE PROBABILITY OF BID BELOW 0% $500 $600 $700 $800 $900 $1,000 ENGINEER’S ESTIMATE ($M)

Adding contingency to cost estimates does not guarantee that the budget established during the estimating process will not be exceeded by bid prices. Contingency amounts are inversely proportional to the probabil- ity of a budget being exceeded (i.e. the more contingency included, the lower the chance of exceeding the budget). Through statistical analysis of bidding history coupled with specific information about the project at hand and current market conditions; a probability curve of the expected bid price can be developed (See Figure 5-2). It becomes a management function to decide on an acceptable probability of a budget overrun and thus the level of contingency to be included in the budget.

Contingency Definitions

Many industries, agencies, and companies define the amount carried for project unknowns differently. Common terms include contingency, allowances, and reserves. To avoid confusion over the terminology used to define these elements in the estimate, the following standard industry terms and their definitions (AACE International Recommended Practice 10S-90, June 2007) and shall be used in all estimate-related documents and correspondence.

Allowances: “Resources included in estimates to cover the cost of known but undefined requirements for an individual activity, work item, account or sub account.”

Contingency: “An amount added to an estimate to allow for items, conditions, or events for which the state, occurrence, and/or effect is uncertain and that experience shows will likely result, in aggregate, in additional costs. Typically estimated using statistical analysis or judgment based on past asset or project experience. Contingency usually excludes:

5-2 Chapter 5 Contingency

1) Major scope changes such as changes in end product specification, capacities, building sizes, and locations of the asset or project; 2) Extraordinary events such as major strikes and natural disasters; 3) Management reserves; and 4) Escalation and currency effects.

Some of the items, conditions, or events for which the state, occurrence and/or effect is uncertain include, but are not limited to, planning and estimating errors and omissions, minor price fluctuations (other than general escalation), design developments and changes within the scope, and variations in market and environment conditions. Contingency must be included in all estimates and the expectation is that this contingency will be expended.”

Management Reserve: “An amount added to an estimate to allow for discretionary management purposes outside of the defined scope of the project, as otherwise estimated. Use of Management Reserve requires a change to the project scope and the cost baseline, while the use of contingency funds is within the project’s approved budget and schedule baseline.” The responsibility for assigning management reserves resides with the BEDC Management and therefore is not covered in this Manual.

Key Sources of Risk and Variability

There are five key factors that contribute most significantly to variability in cost estimating. These five fac- tors include: 1. Project Definition Level 2. Estimating Methodology 3. Project-Related Risks 4. Escalation of Construction Cost Inputs 5. Construction Market Conditions

It should be noted that “scope creep” (the addition of scope items to a project) can be a significant con- tributor to escalating cost estimates through the project phases but this factor is not included in the list. Management of scope creep is the responsibility of the project management team and the allocation of funds to address scope creep is through a management reserve. The amount of management reserve needed must be assigned by the project management team and dictated to the estimating team. The cost estimator has no information to assess this source of variability and therefore can not be held accountable for the cost implications of unforeseen scope additions.

Each of these five main sources of estimating risk and variability have different levels of emphasis at differ- ent phases of a project and thus the amount of contingency allocation to each of the items will shift as the estimate is advanced. While the relevance of each major source of risk will vary due to the nature a given project, the matrix below summarizes the general visibility of each of these factors aligned to each of the five AACE estimating classes.

5-3 Estimate Review and Approval June 2008

T a b l e 5 . 1 T e m p o r a l I n f l u e n c e o f K e y R i s k Factors in Cost Estimating

Es t i m a t e Cl a s s So u r ce o f Ri s k a n d Va r i a b i l i t y 5 4 3 2 2 Pr o j ec t Definition Leve l + + o - - Es t i m a t i n g Me t h o d o l o g y + + o - - Pr o j ec t -Specific Ri s k s o + + + + Es c a l a t i o n o f Co n s t r u c t i o n Co s t In p u t s - - o + + Co n s t r u c t i o n Ma r k e t Co n d i t i o n s - - o + +

+ highly visible risk o moderately visible risk - less visible risk

The influence of the various key risk factors is largely based on the ability to predict and quantify each risk at the various stages of project development. For example, in the early stages of a project when construc- tion may be years out, project definition risk may be high and construction market conditions risk may be relatively unknown or unpredictable. As the project progresses, scope definition risk declines while the potential impacts of market conditions become more visible.

Further details on the nature of each of these sources risk and variability are discussed below. Methods for setting contingency are defined in the section following the risk source discussion. Project Definition Level and Estimating Methodology Industry research consistently recognizes project definition as the key factor in the ability to accurately forecast construction costs, particularly in the early phases of project development. Accordingly, the proj- ect team must collectively ensure that the project definition level is appropriate for the size, complexity and importance of the project, as well as phase of project development.

Project definition and estimating methodology are intrinsically linked since the level of project definition dictates the appropriate estimating methodology, and therefore, these two factors should be evaluated together when assigning contingency to the estimate. Both project definition and estimating methodology are controlled by the collective project team. By utilizing consistent, structured procedures, the variability of these two controlling elements can be minimized. Project-Specific Risks Project-specific risks refer to conditions or situations specific to a particular project that lack proper defini- tion at any given time during the project development. Project-related risks are present during all stages of project of development, but become better defined and more significant in the later stages of the project.

5-4 Chapter 5 Contingency

Examples of project specific risks include: • Possibility that the selected site may not be available, which could potentially increase the costs for property acquisition, site development costs, conveyance facilities, permit costs, and the associated schedule delays. • Unusual and/or unknown site soil conditions • Other unusual site conditions that could increase costs; proximity to existing facilities, restricted site access, potential environmental mitigation requirements, etc. • Unknown process risks; the possibility that the results a required pilot study may significantly affect the process design, require additional systems, etc. • Permitting risks associated with complicated or lengthy permit processes • Scope risks from public involvement processes that may require implementation of undetermined miti- gation measures

Project-related risks should be identified in the risk register on a line item basis and have a contingency amount assigned for each potential risk. In the risk register, the project team should estimate the full cost of the risk (what is the full cost the project would experience) if the risk event did occur, and an associated occurrence probability expressed as a percentage. Risks that have a relatively high probability of occurring should typically be included in the base estimate and not added as a risk factor. Such risks can be listed in the risk register and noted as potential savings, but the cost should be included the base estimate.

The following risks should always be considered and calculated in order to determine the estimate variability. • Material Quantities; the risk that the material quantities have been underestimated due to poor scope definition and/or the method used to determine the quantities. • Material Price; risk associated with material unit prices used in the estimate are inaccurate. • Labor Productivity; risk that labor productivity anticipated by the bidders is less than that included used in the estimate. • Labor Price; risk that labor rates used in the estimate are lower than what will be anticipated by the bidders.

NOTE: Risk for labor and material prices is NOT to account for anticipated escalation. Anticipated escala- tion should be calculated and included in the base estimate (see Chapter 3). Labor/material price risk is calculated to account for the possibility that the base rates in the estimate are inadequate and abnormal escalation caused by market factors (shortages, etc.).

Amounts to be used as the cost basis for calculating material and labor risk can be extracted from the estimate using the estimate line item codes defined in Chapter 3. Suggested percentages to be used in the analysis are shown in Attachment 5-1. In these tables the (+) percentages should be used to determine risk amounts to be added to the estimate. The (+) and ( – ) percentages should only be used for Monte- Carlo type simulations where range estimating is employed.

When using the above risk factors, the following points must be considered:

5-5 Estimate Review and Approval June 2008

1) Material and labor factors will compound as additional material quantities will require additional instal- lation labor. 2) Factors must be applied before contractor markups (overhead, insurance, profit, etc.). 3) If using these factors for range estimating or Monte-Carlo type analyses, both plus and minus factors should be used. Escalation Risk for Construction Inputs As noted in Chapter 3, “anticipated escalation” is to be included in the base cost of the estimate. “Escalation risk” is the risk that the anticipated escalation included in the base bid will be exceeded due to unforeseen market conditions for a particular resource. For example, if steel prices are projected to increase 4 % per year over the length of the project, this amount of escalation should be included in the base bid. Escalation risk is the risk that steel prices will escalate beyond the 4% per year included in the base estimate.

It is also important to distinguish between “escalation of construction inputs” and “construction market con- ditions”. Construction inputs include the labor, materials, process equipment, supplies, fuel, etc., that are required to complete the project. Construction market conditions (see below) are reflective of the volume of work available to contractors and affect the overall bid price in addition to the pricing of construction inputs. Construction Market Conditions At later stages in the project development, the construction market is the principal factor leading to varia- tions between cost estimates and bid prices. The “construction service” performed by the general contac- tor and subcontractors must be viewed as a commodity in itself and analyzed for market conditions that may affect the overall bid price for the project. Current construction market activity and future trends of total construction volume in the local and national market need to be monitored and taken into account when forecasting bid prices. For the local market, DEP can network with other large public agencies in the area (Ports Authority, DDC, etc.), labor unions, trade associations (AGC of New York, General Contractors Association), etc. to gauge the level of upcoming construction activity. In addition, commercially-available local and national forecasts can be used which include McGraw-Hill Construction Research and Analytics and Global Insight.

A variety of factors may lead to market conditions that result in above-normal bid prices. These factors include: • Number of bidders • Bidders perception of risk associated with the project • Length of time between bid and anticipated Notice to Proceed (increases escalation risk to bidders) • Ability to obtain performance bonds • Level of construction activity in the national and local market

Due to the variability and significant impact construction market conditions may have on bid prices, base cost estimates should be priced with standard (typical) contractor markups for risk, profit, and overhead.

5-6 Chapter 5 Contingency

Any adjustments to the standard markup should be carried as a separate item in the estimate for visibility and should be referenced to and explained in the Basis of Estimate document. The estimating team should recommend an adjustment based on their experience with the local market, but BEDC Management should make the final determination on the amount of any adjustment to the standard markups. A detailed discus- sion of various methods for monitoring market conditions is included at the end of this chapter.

As standard markups for subcontractor profit/overhead, contractor overhead/profit, insurance/bonds, and normal escalation may vary according to economic and market conditions, they should be obtained from the BEDC Cost Estimating Division prior to finalizing an estimate. See estimate procedures and formats in Chapters 3 and 4 for instructions on calculating and summarizing adjustments to the standard markups.

Other than research on the number of bidders vs. bid prices (discussed below), little published research ex- ists that can be used to predict variances in bid results due to “construction market” conditions, particularly at the local level. The estimating team and other members of the project team must analyze both the global and local market conditions to determine recommended general contractor and subcontractor markup percentages to be used in cost estimates. Analysis methods that can be employed by the estimating team include: • “Feels like” surveys of other owners and entities receiving bid prices • Re-pricing historical bids from different time frames • Statistical analysis of bid results

“Feels like” Surveys “Feels like” surveys are non-technical and simply involve gathering the opinion of a number of owners, con- tractors, estimating professionals, and others involved in receiving bid prices, to formulate an intuitive sense “gut feel” for how bid prices compare to “normal” market conditions. While this is a relatively inexpensive method, it is obviously highly subjective.

Re-pricing of Historical Data Use of this method involves several distinct steps as listed below: 1) Identify two similar projects, one that is a historical project bid prior to the onset of the current market conditions. 2) Extract fully-burdened unit prices (unit prices with all contractor markups included) from an historical internal estimate that used “typical” markups and that has been reconciled to the actual received bid. 3) Adjust these extracted, fully burdened unit prices for the known escalation of construction inputs (labor, materials, etc.). 4) Use these adjusted prices to estimate a recently bid project similar in nature to the historical project. 5) By comparing the estimate of the recently bid project (using the adjusted prices from the historical project), to the actual bid of the recent project gives a qualitative indication of the change in the con- struction market.

Obviously this method requires identification of projects with enough similarity that the comparison is valid. It is important to note that this process of evaluating construction market conditions is very labor intensive.

5-7 Estimate Review and Approval June 2008

Bid Prices vs. Number of Bidders One of the factors to consider when establishing adjustments to estimated contractor markups is the num- ber of anticipated bidders. Numerous studies have documented the tendency for an increase in bid prices as the number of bidder’s decreases. Many factors affect the number of bidders that will ultimately propose on a given project. Among these, project size, potential risk, and complexity of the project are typically the most influential.

Comparison of the data from the various studies suggests that although the effect of the number of bidders on bid prices is “universal”, the data sets do not support a single mathematical model. Variance between the studies is likely due to factors associated with the construction type, location, and other owner-specific variables. Even with the variance between the studies, they can be used to formulate suggested guidelines on the potential effect on bid prices of a lower than normal number of bidders. When evaluating construc- tion market conditions, the following guidelines should be considered when less than four bidders are anticipated: 3 bidders – up to 15% of the total estimated bid price 2 bidders – 20 to 30% of the total estimated bid price 1 bidder – 25 to 40% of the total estimated bid price

The above percentages should be considered approximate guidelines only, as results from individual proj- ects may vary significantly above or below these ranges.

Methods for Setting Contingency

There are a variety of methods for establishing contingency for construction projects. Most methods can be grouped into three main categories as shown in the table below: Table 5-2 S u m m a r y o f T y p i c a l C o n t i n g e n c y Estimating Methodologies Ca t e g o r y Me t h o d Pre-Determined Percentages Qualitative Expert Opinion Standard Risk Model Risk Analysis Simplified Monte Carlo Risk Model Integrated Cost/Model Risk Model

Which method, or combination of methods, used will depend on the available historical data and the nature of the project, (size, complexity, significance). This decision must be agreed upon by the project team and documented in the Basis of Estimate Report. Each method for setting contingency is described later in this chapter.

5-8 Chapter 5 Contingency

The table below summarizes the minimum requirements for contingency setting methods to be for all esti- mates prepared for BEDC based on the estimated project value and estimate class. Methods are described in detail in the following section.

Table 5-2 S u m m a r y o f C ontingency M e t h o d o l o g i e s R e q u i r e d Based on Project Size and Estimate Class Co n t i n g e n c y Me t h o d o l o g y Cl a s s 5 Cl a s s 4 Cl a s s 3 Cl a s s 2 Cl a s s 1 Pre-Determined Percentages Required Required Required Required Required (AACE Guidelines) Required if Required if Required if Required if Standard Risk Model Optional >$10M >$10M >$10M >$10M Simplified Monte Carlo Risk Required if Required if Required if Required if Optional Model >$25M >$25M >$25M >$25M Optional if Integrated Cost/Schedule Optional if >$50M; Update of Class Update of Class Not Applicable Risk Model >$50M Required if 3 Analysis 2 Analysis >$100M

Notes: 1) Regardless of the method(s) used to analyze contingency, pre-determined percentages shall also be established by the estimating team. The amount of contingency included in the estimate shall not be less than that calculated by the pre-determined percentages ap- propriate for the class of estimate unless approved by the BEDC project manager. 2) Where a formal risk analysis is performed, the risk register shall also be prepared and used as input for a portion of the risk analysis.

Pre-Determined Percentages One commonly used practice is to add contingency to the base Es t i m a t e AACE Rec o m m e n d e d cost estimate using pre-determined percentages such as those Cl a s s Co n t i n g e n c y recommended in AACE Recommended Practice 18R-97. Us- L: -20% to -50% 5 ing pre-determined percentages is the minimum requirement for H: +30% to +100% L: -15% to -30% determining contingency amounts. Pre-determined percentages 4 H: +20% to +50% may need to be supplemented with other methods depending on L: -10% to -20% 3 the nature of the job. H: +10% to +30% L: -5% to -15% Recommend percentages in AACE 18R-97 were determined from 2 H: +5% to +20% industry research, including regression analysis of historical proj- L: -3% to -10% 1 ect data. However, since they represent average results, simply H: +3% to +15% applying them to base cost estimates without further analysis may not provide an adequate picture of project risk. The expected accuracy ranges listed in AACE 18R-97 are defined as the “… typical variation in low and high range after the application of contingency (determined at a 50% level of confidence). Typically, this results in a 90% confidence that the actual cost will fall within the bound of the low and high ranges.”

5-9 Estimate Review and Approval June 2008

The AACE recommended contingency percentages are a range for each estimate class. Determination of the value included in the estimate should be done by evaluating a number of factors, including: • Level of project definition; poorly-defined projects require higher contingency • Complexity of the project; more complex projects require higher contingency • State of the technology involved with the project; new technology represents higher risk • Experience of the estimating team with the particular type of project • Time allowed to prepare the estimate • Quality of the cost data available • Overall quality of the estimate

In addition to the project team evaluating the above factors and recommending a contingency percentage to be included in the estimate, the significance of the project in terms of impact to the overall DEP capital program. Projects that cannot be delayed due to consent decrees or other obligations or considerations, should carry a higher contingency (closer to the high end of the recommended range), even if the other factors would justify a contingency at the lower end of the range. Expert Opinion Contingency may be set based on the experience of the estimators and other members of the project team. This method takes the nature of the project and specific risk factors into account, and therefore may provide a more realistic projection than pre-determined percentages. However, it is very subjective and heavily reliant on the availability of experts with a background relevant to the particular project. The level of detail and structure when using the expert opinion approach can vary widely, from assigning an overall project contingency, to assigning a contingent amount to discrete WBS elements and additional risk drivers. This method should only be used when experts with specific, relevant experience with all aspects of the project are available, and only with specific approval from the BEDC project manager. Risk Analysis Risk analysis can be used to evaluate appropriate levels of contingency for a project. In addition, risk analysis sessions add value to the project development process since they require the project team to identify risks and analyze options to mitigate these risks to reduce the overall project impact. In addition to generating a recommended value for contingency, risk analysis sessions provide feedback on: 1) Areas of the design that might require additional development 2) Risk mitigation strategies 3) Identified risk items that may require involvement by management

Risk analysis methods vary in complexity and effort required to employ them. Common methods include: • Standard Risk Model • Simplified Monte Carlo Risk Model • Integrated Cost/Schedule Risk Analysis

5-10 Chapter 5 Contingency

Standard Risk Model One of the simplest risk analysis methods, sometimes referred to as the “standard risk model”, consists of the following steps: 1) Assemble a risk register by identifying and listing each risk elements associated with project completion. 2) Assign an estimated cost and schedule impact to each risk element (cost to the project should the risk element occur). 3) Assign a probability (percent chance) that the risk element will occur. 4) Calculate the expected net risk by multiplying the cost and schedule impact of each risk element times the associated probability. 5) Sum the expected net risk of each risk element to calculate the total risk for the project.

This method is also known as Expected Value and Expected Net Risk. One disadvantage of this method is that it produces a “single point” contingency that does not provide a probability of the calculated contin- gency being exceeded. Use of the risk register to support risk identification and management is detailed in the BEDC Project Delivery Manual and a copy of the latest standard risk register template should be obtained from your BEDC PM at the initiation of every project.

Simplified Monte Carlo Risk Model The standard risk model can be enhanced to generate probabilities on whether a given contingency amount will be exceeded. For each line item in the risk register, minimum, most likely, and maximum values of budget and schedule impact are determined to create a triangular distribution for each line item. Using the triangular distributions and associated probability of occurrence for each line item as input, a simple Excel- based Monte Carlo simulation generates an estimated project cost (base estimate cost plus contingency) for a range of probability values (50%, 60%, 70% 80%, 90%, etc.). The results can be presented as a probability distribution curve or in a table format.

As an example of this method, the base estimate for a project may be $100M. By adding a contingency of $30M, the probability of not exceeding the total projected cost of $130M might be increased to 80%. By adding contingency of $50M (total projected cost of $150M) the chance of not exceeding the total projected amount might be increased to 90%.

In general, the required input consists of: • Base estimate amount (cost and schedule) • Estimate certainty (base estimated cost and schedule) • Assignment of a probability that the risk will happen. • Assignment of individual line items in the risk log with separate minimum amounts, most likely amounts, and maximum amounts. • Schedule impact in months (minimum, maximum, most likely)

Detailed instructions for using the Simplified Monte Carlo Risk Model, along with a template and sample, should be obtained from your BEDC Project Manager at the initiation of a project.

5-11 Estimate Review and Approval June 2008

Integrated Cost/Schedule Risk Model The Integrated Cost/Schedule Risk Model uses Monte Carlo simulation techniques to generate the most likely outcome of the combination of all the risk items (both cost and schedule) associated with a project. Commercial off-the-shelf software is available to perform Monte Carlo simulations. A complete Monte Carlo simulation requires extensive involvement from the project team and should be facilitated by an individual experienced with the process.

One common approach is to use Monte Carlo simulation in conjunction with range estimating. Under this approach, line items at a certain WBS level in the estimate are assigned ranges as opposed to a single cost amount. This requires the estimator to assign a minimum cost, a most likely cost, and a maximum cost for each line in the WBS. Based on the theory that neither the “best case” nor the “worst case” will happen for all line items, the simulation runs multiple iterations of possible cost combinations and possible final values for each line item, and calculates a probability distribution. From this probability distribution, the project team can select a required contingency amount based on the desired confidence level. The desired confidence level translates into the probability that the contingency amount will not be exceeded.

Recent studies have indicated that Monte Carlo-type simulations are not effective in calculating realis- tic probability distributions on poorly-defined jobs. Without realistic probability distributions, selecting a reasonable contingency becomes impossible. These studies point to several factors that lead to poor simulation results: • Failure to recognize the dependencies between risk items and account for this in the simulation.. • At the early stages of project development, project-specific risk drivers are not readily definable. • Lack of project definition (especially at the early stages of project development) typically leads to over optimistic estimates of project cost and risk. Because of the shortfalls of simulation techniques, they should be used only under the following conditions: • Project definition has progressed to the point where risks are readily definable, and valid range esti- mates can be performed. • Personnel experienced in Monte Carlo methods are available to facilitate a risk session. • Project size and significance justify the effort required to complete the evaluation.

5-12 Chapter 5 Attachments

Attachment 5-1 Guidance on Contingency Levels for Primary Construction Inputs ATTACHMENT 5 - 1 Attachment 5-1 GUIDANCE Guidance ON CONTINGENCYon Contingency LEVELS Levels FOR PRIMARY for Primary CONSTRUCTION Construction INPUTS Inputs

Code Description (+) % Remarks

Material Quantity 0 Major process equipment from equipment lists 0 1 Detailed takeoff from completed design drawings 0-10 Includes miscellaneous equipment, instruments, (other than major process equipment), etc. for other than Class 1 and 2 estimates. 2 Takeoff from a “go-by” design (design drawings from a 5 - 20 previously-designed facility similar in nature) 3 Factored using a cost estimating relationship 10 - 25 4 Assumed by estimator 20-50 Material Price 0 Agreed contract price 0 1 Firm quote (written) 0-2 2% to account for contract finalization 2 Budget quote (written) 5 - 15 3 Estimated price (using current invoices or published data) 10 - 20 Includes estimating database prices updated by pricing 4 Database prices (not updated by pricing service) 15-25 5 Plug prices 20-30 Labor Productivity 0 Actual (measured) productivity on same jobsite 0-5 1 Actual (measured) productivity from another jobsite 5 - 10 2 Database with historical data 5 - 20 3 Published data (Means, etc.) 10 - 20 4 Estimated (no backup) 15-50 Labor Price 0 Site agreement currently in place 0 1 Union agreement 0-5 Possible adjustment for crew assignment and jurisdictional 2 Published labor rates 5 - 10 3 Published data (Means, etc.) 10 - 15 4 Estimated (no backup) 15-20

1

Attachment 5-1 June 2008 Attachment 5-1 Guidance on Contingency Levels for Primary Construction Inputs

2 Chapter 6 Estimate Review and Approval Estimate Review and Approval Estimate Review Chapter 6

Chapter 6 Estimate Review and Approval

Chapter 6 – Estimate Review and Approval

Introduction

Three levels of review are required for each cost estimate prepared for BEDC Capital Projects prior to submittal to the BEDC Project Manager. These three levels include:

• Cost estimating team review • Project management and design team review • Consultant senior management review and endorsement

The scope and purpose of these reviews is described in this section.

All reviews shall be performed using the Basis of Estimate (BOE) Report as the reference document and the primary basis for the agenda (see Chapter 5 for details on the BOE Report). In addition to the BOE Report, a complete copy of the project definition package (drawings, specifications, gap analysis, and other related information) should be made available for each review team and shall be available during every review session.

The meeting minutes and notes addressing the disposition of items identified shall be included in the Estimating Quality Assurance section of the BOE document.

The remainder of this chapter describes the quality reviews of the cost estimate

Cost Estimating Team Review Purpose An independent lead estimator that was not involved in preparing the estimate should perform a peer review of the estimate. This review should be performed before the estimate is submitted to the project manage- ment and design team.

Areas of Focus The estimate should include a detailed scope review and a detailed pricing review using the following reports:

• Scope Review Report organized by Assembly • Scope Review Report with Line Item Detail • Labor/Productivity Detail Report (Assembly) • Labor/Productivity Detail Report (Item) Labor and Equipment Resource Reports See Chapter 4 – Estimate Outputs for descriptions and samples of these reports.

6-1 Estimate Review and Approval June 2008

Participants This peer review should be performed by the independent lead estimator with the project lead estimator and each discipline estimators that were involved in preparing the estimate.

Review Materials A hard copy of the drawings and specifications, gap analysis, BOE Report and either a hard or electronic copy of the estimate.

Specific Review Topics: Estimate Classification • Concurrence with the estimate classification indicated by the estimating team. Design Basis • Estimating team used and priced the most current version of all: – Design documents – Correspondence – Gap Analysis – Any other information that might affect the estimate. Estimating Methodology • Estimating methodologies appropriate for the status of the design documents provided. • Any parametric models or cost estimating relationships used in the estimate have been applied properly. Cost Basis • Check the estimate against the project definition documents including the detailed WBS to ensure that all required elements have been included in the estimate as either quantity take-offs or allocations. • Ensure the Gap Analysis has been properly priced in the estimate • Spot check major takeoff quantities • Review all line item pricing in the estimate for productivity, proper crew assignments, etc. • Review all labor rates and crew compositions • Check that the total amounts on the labor and equipment resource reports match the corresponding amounts on the estimate summary reports. • Review pricing of all items included in the equipment list. If quotes were received, check for compli- ance to the design requirements. • Review pricing of all major commodities • Review all indirect costs and markups Planning Basis • The project schedule meets all regulatory requirements, project milestones, interfaces with existing plant, etc. • Review duration of major schedule activities • Review schedule logic

6-2 Chapter 6 Estimate Review and Approval

Allowances • Review all allowances included in the estimate Assumptions • Verify the assumptions made by the estimating team Exclusions • Review exclusions taken by the estimating team Exceptions • Indicate concurrence with any exceptions from an estimating standpoint Risk and Opportunities • Verify that all known risks have been captured in the risk log • Indicate concurrence with the magnitude and probability of all risk items Contingencies • Review and concur with contingency allocations Reconciliation • Review overall reconciliation to previous estimate Benchmarking • Review all metrics produced by the estimating team • Compare estimate to any other applicable metrics Outputs The independent estimator should review the material and host a meeting with the lead estimators that prepared the cost estimate and go through areas of justification as requested by the independent estimator. Meeting minutes with an attendee list shall be produced and distributed to each attendee after the review.

Project Management and Design Team Review Purpose A detailed scope review performed with the design team to confirm compliance with the design documents and design intent.

Areas of Focus The review shall verify that the estimate accurately reflects the approved scope of the project as repre- sented by the project definition package including the gap analysis to cover scope items not shown in the documents.

Participants This peer review should be performed with the lead estimator, the design Consultant Project Manager and key design discipline leads, and the BEDC Project Manager.

6-3 Estimate Review and Approval June 2008

Review Materials The Scope Review Report by Assembly should be used to facilitate this review. A hard copy of the Basis of Estimate document shall be provided to each reviewer. The estimate may be reviewed in hard copy or electronically. Copies should be provided to all reviewers several days before the review.

Specific Review Topics Estimate Classification • General concurrence with the estimate classification indicated by the estimating team. Design Basis • Estimating team received the most current version of all: – Design documents – Correspondence – Any other information that might affect the estimate • Review gap analysis for effectiveness in conveying scope not shown Estimating Methodology • Estimating methodologies appropriate for the status of the design documents provided. • Any parametric models or cost estimating relationships used in the estimate have been applied properly. Cost Basis -• Check the estimate against the project definition documents, including the detailed WBS to ensure that all required elements have been included in the estimate as either quantity take-offs or allocations. • Ensure the Gap Analysis has been properly priced in the estimate. • Review pricing of items included in the equipment list. If quotes were received, check for compliance to the design requirements. • Review pricing and escalation of all major commodities. • For any unusual requirements in the plans or specifications, verify that the estimating team understood the requirements and priced them accordingly. • For any unique design elements that represent a first-time application, or an application not normally included in the type of project, review the pricing with the estimating team. • Check indirect costs for concurrence on testing, quality control/assurance, and startup requirements. Planning Basis • The project schedule meets all regulatory requirements, project milestones, interfaces with existing plant, etc. Allowances • Indicate concurrence with all allowances included in the estimate. Assumptions • Verify the assumptions made by the estimating are correct relative to the design. Exclusions • Indicate concurrence with the exclusions taken by the estimating team (the exclusions are not in the project scope)

6-4 Chapter 6 Estimate Review and Approval

Exceptions • Indicate concurrence with any exceptions from a design standpoint. Risk and Opportunities • Verify that all known risks have been captured in the risk log. • Indicate concurrence with the magnitude and probability of all risk items. Contingencies • Review itemized list of contingency items focused on scope, estimating methodology, materials escala- tion, market conditions, and other project specific risks. • Indicate concurrence Management Reserve • Provide recommendation for Management Reserve funds based on professional judgment of the po- tential changes that could occur in the future prior to bid and award. Reconciliation • Review reconciliation to previous estimate • Indicate concurrence with scope changes or other factors contributing to change in estimate. Outputs The review participants must convene a meeting to review the topics listed above. As part of the review meeting, it is often helpful to review a copy of the live estimate with a screen and projector in the room. Meeting minutes with an attendee list shall be produced and distributed to each attendee after the review. The Project Manager shall verify that all review comments are incorporated into the estimate.

Design Consultant Senior Management Endorsement Purpose Assure that all quality reviews have occurred and to provide final review and approval of the Basis of Esti- mate Report.

Areas of Focus The main area of review is the established contingency and recommendations for Management Review.

Participants This review should be performed with the lead estimator, the DEP project manager, and the Consultant Project Manager.

Review Materials The estimate report sorted by Area/Process/System should be used to facilitate this review. A hard copy of the Basis of Estimate document shall be provided to each reviewer but the estimate may be reviewed by using hard copies or reviewing a copy of the live estimate with a screen and projector. Copies should be provided to all reviewers several days before the review.

6-5 Estimate Review and Approval June 2008

Specific Review Topics Estimating Methodology • Estimating methodologies appropriate for the status of the design documents provided. Risks • Verify that all known risks have been captured in the risk ledger. • Review magnitude and probability of all risk items. Contingencies • Itemized list of contingency items focused on scope, estimating methodology, materials escalation, market conditions, and other project specific risks. Management Reserve • Provide recommendation for Management Reserve funds based on professional judgment of the po- tential for unpredicted changes that could occur in the future prior to bid and award Reconciliation • Review reconciliation to previous estimate

Outputs The Management Team prepares a cover letter for transmittal of the estimate to BEDC. The cover letter must include the following language:

“We have reviewed the attached project cost estimate. We believe that the estimate conforms to the ac- cepted standard of care for professional practice, that it is complete in terms of scope, schedule, cost of materials, and labor. It is based on current market conditions and an anticipate level of competition and reasonably expected future trends, assuming no outside adverse project impacts or delays. This cost estimate has been escalated on a straight line extrapolation to the midpoint of construction based on the projected start year of construction. The goal was to develop an estimate that would be the second lowest bid if submitted by a contractor in a competitive bid.”

The letter must be signed by the Project Director for all estimates under $200 million in construction value and by the president of the firm (or of each joint venture) for all estimates over $200 million in construction value.

6-6