Quick viewing(Text Mode)

Geotechnical Engineering Study for Lake Lakewood

Geotechnical Engineering Study for Lake Lakewood

GEOTECHNICAL STUDY

FOR

LAKE LAKEWOOD PARK SITE LEANDER, TEXAS Project No. AAA17‐091‐00 Raba Kistner Original Submission February 02, 2018 Consultants, Inc. 8100 Cameron , Suite B-150 Revised, February 23, 2018 Austin, TX 78754 www.rkci.com Mr. Dan Franz, P.E., CFM P 512 :: 339 :: 1745 Halff Associates, Inc. F 512 :: 339 :: 6174 9500 Amberglen Boulevard, Building F, Suite 125 TBPE Firm F-3257 Austin, Texas 78729

RE: Study Lake Lakewood Park Site Leander, Texas

Dear Mr. Franz:

RABA KISTNER Consultants Inc. (RKCI) is pleased to submit the report of our Geotechnical Engineering Study for the above‐referenced project. This study was performed in accordance with RKCI Proposal No. PAA17‐178‐00, dated November 13, 2017. The purpose of this study was to drill 9 borings, to perform laboratory testing to classify and characterize subsurface conditions, and to prepare an engineering report presenting design and recommendations for the proposed Lake Lakewood Park, as as to provide pavement design and construction guidelines. This report has been revised to address concerns associated with foundation and pavements being constructed within the flood plain.

The following report contains our design recommendations and considerations based on our current understanding of information provided to us at the time of this study. There may be alternatives for value engineering of the foundation and pavement systems. RKCI recommends that a meeting be held with the Owner and design team to evaluate if alternatives are available.

We appreciate the opportunity to be of service to you on this project. Should you have any questions about the information presented in this report, or if we may be of additional assistance with value engineering or on the materials testing‐quality control program during construction, please call.

Very truly yours,

RABA KISTNER CONSULTANTS, INC.

Richard T. Shimono, E.I.T. Yvonne Garcia Thomas, P.E. 02/23/2018 Graduate Associate

RTS/YGT: tlc Attachments

Copies Submitted: Above (1‐electronic)

O:\Closed Projects\Austin\2017\AAA17-091-00 Lake Lakewood Park Site\Reporting\AAA17-091-00 Lake Lakewood 2 22 2018 FINAL.docx GEO100 04/09/2014

San Antonio • Austin • Brownsville • Dallas • Houston • McAllen • Mexico • New Braunfels • Salt Lake City

GEOTECHNICAL ENGINEERING STUDY

For

LAKE LAKEWOOD PARK SITE LEANDER, TEXAS

Prepared for

HALFF ASSOCIATES, INC. Austin, Texas

Prepared by

RABA KISTNER CONSULTANTS, INC. Austin, Texas

PROJECT NO. AAA17‐091‐00

Revised, February 23, 2018

Project No. AAA17‐091‐00 i Revised, February 23, 2018

TABLE OF CONTENTS

INTRODUCTION ...... 1 PROJECT DESCRIPTION ...... 1 LIMITATIONS ...... 1 BORINGS AND LABORATORY TESTS ...... 2 GENERAL SITE CONDITIONS ...... 3 SITE DESCRIPTION ...... 3 ...... 3 SEISMIC CONSIDERATIONS ...... 3 STRATIGRAPHY ...... 4 ...... 4 FOUNDATION ANALYSIS ...... 4 EXPANSIVE ‐RELATED MOVEMENTS ...... 4 OVEREXCAVATION AND SELECT FILL REPLACEMENT ...... 5 CONSIDERATIONS ...... 5 FOUNDATION RECOMMENDATIONS ...... 6 FOUNDATION CONSIDERATIONS ...... 6 FOUNDATION OPTIONS ...... 7 Restrooms, Pavilions, Boat/Rental Facility ...... 7 Fishing Pier/Boardwalk...... 7 SITE ...... 7 SPECIAL CONSIDERATIONS ‐ FOUNDATIONS ...... 7 ENGINEERED BEAM AND SLAB FOUNDATION ...... 8 Allowable ...... 8 B.R.A.B. Criteria ...... 8 PTI Design Parameters ...... 9 SHALLOW SPREAD FOOTING FOUNDATIONS ...... 10 Allowable Bearing Capacity ...... 10 AREA FLATWORK ...... 11 DRILLED, STRAIGHT‐SHAFT PIERS ...... 11 Pier Shaft Potential Uplift Forces ...... 12 Allowable Uplift Resistance ...... 12 PIER SPACING ...... 12 RETAINING STRUCTURES ...... 13 LATERAL EARTH PRESSURES ...... 13 BACKFILL COMPACTION ...... 14 DRAINAGE ...... 14

Project No. AAA17‐091‐00 ii Revised, February 23, 2018

TABLE OF CONTENTS

RETAINING FOOTINGS ...... 14 SPECIAL CONSIDERATIONS – RETAINING ...... 15 FOUNDATION CONSTRUCTION CONSIDERATIONS ...... 15 SITE DRAINAGE ...... 15 SITE PREPARATION ...... 16 SELECT FILL ...... 16 CAP ...... 17 EXCAVATIONS ...... 17 DRILLED PIERS ...... 18 Reinforcement and Concrete Placement ...... 18 Casing ...... 18 EXCAVATION SLOPING AND BENCHING ...... 18 EXCAVATION EQUIPMENT ...... 18 UTILITIES ...... 19 PAVEMENT RECOMMENDATIONS ...... 19 CONDITIONS ...... 20 DESIGN INFORMATION ...... 20 FLEXIBLE PAVEMENT (PARKING LOT/ENTRANCE ROADWAY) ...... 20 RIGID PAVEMENT (PARKING LOT/ENTRANCE ROADWAY) ...... 21 MULTI‐USE TRAILS ...... 22 PAVEMENT CONSTRUCTION CONSIDERATIONS ...... 22 SUBGRADE PREPARATION ...... 22 DRAINAGE CONSIDERATIONS ...... 22 ON‐SITE CLAY FILL ...... 23 ALTERNATIVE SELECT FILL ...... 23 LIME TREATMENT OF SUBGRADE9 ...... 23 FLEXIBLE BASE COURSE ...... 24 ASPHALTIC CONCRETE SURFACE COURSE ...... 24 PORTLAND CEMENT CONCRETE ...... 24 CONSTRUCTION RELATED SERVICES ...... 24 CONSTRUCTION MATERIALS TESTING AND OBSERVATION SERVICES ...... 24 BUDGETING FOR CONSTRUCTION TESTING ...... 25

Project No. AAA17‐091‐00 iii Revised, February 23, 2018

ATTACHMENTS

The following figures are attached and complete this report:

Boring Location Map ...... Figure 1 Logs of Borings ...... Figures 2 to 10 Key to Terms and Symbols ...... Figure 11 Results of Soil Analyses ...... Figure 12 Important Information About Your Geotechnical Engineering Report

Project No. AAA17‐091‐00 1 Revised, February 23, 2018

INTRODUCTION

RABA KISTNER Consultants Inc. (RKCI) has completed the authorized subsurface exploration and foundation analysis for the Lake Lakewood Park site to be located in Leander, Texas. This report briefly describes the procedures utilized during this study and presents our findings along with our recommendations for foundation design and construction considerations, as well as for pavement design and construction guidelines.

PROJECT DESCRIPTION

Under consideration in this study is a park surrounding Lake Lakewood in Leander, Texas. Based on email correspondences with the project , we understand almost the entire subject site is located within a 100‐year flood plain. Therefore, consideration should be given to the inundation of flood waters to the foundations and pavements and how this ponding of water could affect the performance of the foundation and pavements. Based on estimates by the civil engineer, we understand inundation of water over the improvements following a 100‐year storm event could last 3 to 5 days.

Proposed improvements to the park include restrooms, a skate park, a fishing pier, a boat rental facility, and pavilions. Additional improvements include public , parking lots, a 10 to 12 ft tall , and concrete paved trails. Relatively light loads are anticipated to be carried by the foundation systems at this site. We understand shallow footings and slabs‐on‐ foundations are preferred for the structures, provided they can withstand soil movements at this site, with the exception of the fishing pier, which is anticipated to be supported on deep foundations to resist the effects of scour.

After conclusion of the field exploration program, the site layout was modified to include the 10 to 12 ft tall retaining wall mentioned above. Additionally, the locations of the fishing pier/boardwalk and boat rental facility have been moved approximately 500 ft west and 150 ft southwest, respectively, and the parking and drive pavement areas have been significantly expanded. We highly recommend additional confirmation borings be drilled at this site prior to construction.

It is our understanding that at the time of this study, site grading plans and proposed structural loads were not yet available. The recommendations presented in this report were prepared with the assumption that final grade for the structures and pavements will be within plus or minus 1 ft of existing grades.

LIMITATIONS

This engineering report has been prepared in accordance with accepted Geotechnical Engineering practices in the region of central Texas and for the use of Halff Associates, Inc. (CLIENT) and its representatives for design purposes. This report may not contain sufficient information for purposes of other parties or other uses. This report is not intended for use in determining construction means and methods. The attachments and report text should not be used separately.

The recommendations submitted in this report are based on the data obtained from 9 borings drilled at this site, our understanding of the project information provided to us, and the assumption that site grading will result in only minor changes in the existing . If the project information described

Project No. AAA17‐091‐00 2 Revised, February 23, 2018

in this report is incorrect, is altered, or if new information is available, we should be retained to review and modify our recommendations.

This report may not reflect the actual variations of the subsurface conditions across the site. The and extent of variations across the site may not become evident until construction commences. The construction process itself may also alter subsurface conditions. If variations appear evident at the time of construction, it may be necessary to reevaluate our recommendations after performing on‐site observations and tests to establish the engineering impact of the variations.

The scope of our Geotechnical Engineering Study does not include an environmental assessment of the air, soil, rock, or water conditions either on or adjacent to the site. No environmental opinions are presented in this report.

If final grade elevations differ from existing grades by more than plus or minus 1 ft, our office should be informed about these changes. If needed and/or if desired, we will reexamine our analyses and make supplemental recommendations.

BORINGS AND LABORATORY TESTS

Subsurface conditions at the site were evaluated by 9 borings drilled at the locations shown on the Boring Location Map, Figure 1. Boring locations were documented in the field utilizing a hand‐held GPS device. The B‐series (building) borings were drilled to approximate depths of 10 ft, the P‐series (pavement) borings were drilled to approximate depths of 5 ft, and the PR‐series (fishing pier) boring was drilled to an approximate depth of 15 ft below the existing ground surface using a track‐mounted drilling rig as presented below.

Depth Boring No. Amenity (ft) B‐1 restroom 10 B‐2, B‐3 pavilions 10 B‐4 restroom/boat rental 10 PR‐1 fishing pier/boardwalk 15 P‐1 roadway 5 P‐2 skate park 5 P‐3 parking lot 5 P‐4 multi‐use trails 5

During drilling operations, 38 split‐spoon samples (with Standard Penetration Test) were collected.

Each sample was visually classified in the laboratory by a member of our geotechnical engineering staff. The geotechnical engineering properties of the strata were evaluated by 38 moisture content and 6 Atterberg Limit tests. The results of all laboratory tests are presented in graphical or numerical form on the boring logs illustrated on Figures 2 through 10. A key to classification terms and symbols used on the logs is presented on Figure 11. The results of the laboratory and field testing are also tabulated on Figure 12 for ease of reference.

Project No. AAA17‐091‐00 3 Revised, February 23, 2018

Standard Penetration Test results (N‐values) are noted as “blows per ft” on the boring logs and Figure 12. The N‐value is the number of blows required to drive a split‐spoon sampler 1 ft into soil/weak rock with a falling, 140‐lb hammer. Where hard or dense materials were encountered, the tests were terminated at 50 blows even if one foot of penetration had not been achieved. When all 50 blows fall within the first 6 in. (seating blows), refusal “ref” for 6 in. or less will be noted on the boring logs and on Figure 12.

Samples will be retained in our laboratory for 30 days after submittal of this report. Other arrangements may be provided at the request of the Client.

GENERAL SITE CONDITIONS

SITE DESCRIPTION

The project site is generally an undeveloped area located north of Lake Lakewood in Leander, Texas. The site is grass‐covered with isolated stands of trees and becomes densely wooded as you travel north away from of the lake. Walking trails border the north perimeter boundary of the lake.

GEOLOGY

A review of the Geologic Atlas of Texas, Austin Sheet, indicates that this site is naturally underlain with the /rock (limestone) of the Fredericksburg Group. The Fredericksburg group varies in hardness and weathering and may be comprised of comprised of Edwards Limestone, Comanche Peak Limestone, Keys Valley Marl, Cedar Park Limestone, and Bee Cave Marl. The limestone of the Fredericksburg group is generally considered hard in induration and typically contains harder zones/seams of chert and dolomite. It can also typically contain karstic features in the form of open and/or clay‐filled vugs, voids, and/or solution cavities that form as a result of solution movement through fractures in the rock mass.

SEISMIC CONSIDERATIONS

On the basis of the soil borings conducted for this investigation, the upper 100 feet of soil may be characterized as rock and a Class B Site Class Definition (Chapter 20 of ASCE 7) has been assigned to this site.

On the basis of the United States Geological Survey (USGS) website1 which utilizes the International (IBC) and U.S. Seismic Design Maps to develop seismic design parameters, the following seismic considerations are associated with this site.

Ss = 0.062g Sms = 0.062g SDS = 0.041g

S1 = 0.034g Sm1 = 0.034g SD1 = 0.023g

Based on the parameters listed above as well as Tables 1613.3.5(1) and 1613.3.5(2) of the 2012 IBC, the Seismic Design Category for both short period and 1 second response accelerations is A. As part of the assumptions required to complete the calculations, a Risk Category of “I or II or III” was selected.

1http://earthquake.usgs.gov/designmaps/us/application.php

Project No. AAA17‐091‐00 4 Revised, February 23, 2018

STRATIGRAPHY

The subsurface conditions encountered at the boring locations are shown on the boring logs, Figures 2 through 10. These boring logs represent our interpretation of the subsurface conditions based on the field logs, visual examination of field samples by our personnel, and test results of selected field samples. Each stratum has been designated by grouping soils that possess similar physical and engineering characteristics. The lines designating the interfaces between strata on the boring logs represent approximate boundaries. Transitions between strata may be gradual.

Stratum I consists of very stiff, dark brown to brown, fat clay (CH). These clays are classified as highly plastic based on measured indices ranging from 41 to 53. Measured moisture contents generally range from 19 to 34 percent. Standard Penetration Test (SPT) N‐values range from 18 to 28 blows per ft.

Stratum II consists of very dense, tan, clayey (SC), which we have classified as decomposed limestone. The fines are classified as moderately plastic based on measured plasticity indices of 13 and 18. Measured moisture contents generally range from 4 to 9 percent. Standard Penetration Test (SPT) N‐values range from 50 blows for 9 to 11 inches of penetration.

Stratum III consists of hard, tan limestone. Measured moisture contents range from 9 to 12 percent. Standard Penetration Test (SPT) N‐values generally range from refusal for 1/2 inch of penetration to refusal for 5 inches of penetration into limestone.

GROUNDWATER

Groundwater was not observed in the borings either during or immediately upon completion of the drilling operations. All borings remained dry during the field exploration phase. However, it is possible for groundwater to exist beneath this site at shallow depths on a transient basis, particularly at the clay/limestone interface, within weathered limestone seams, and following periods of precipitation. Fluctuations in groundwater levels occur due to variation in rainfall and surface water run‐off, as well as water levels of the nearby lake. The construction process itself may also cause variations in the groundwater level.

FOUNDATION ANALYSIS

EXPANSIVE SOIL‐RELATED MOVEMENTS

The anticipated ground movements due to swelling of the underlying soils at the site were estimated for slab‐on‐grade construction using the empirical procedure, Texas Department of Transportation (TxDOT) Tex‐124‐E, Method for Determining the Potential Vertical Rise (PVR). PVR values were estimated for the stratigraphic conditions encountered in our borings as presented below. A surcharge load of 1 psi (concrete slab and sand layer), an active zone extending to the depth of limestone, and dry moisture conditions were assumed in estimating the above PVR values.

Project No. AAA17‐091‐00 5 Revised, February 23, 2018

Estimated PVR Design Condition Boring No. (in.) A B‐1, B‐3, PR‐1, P‐1, P‐2, P‐3 and P‐4 1‐1/2 B B‐2, B‐4 1

The TxDOT method of estimating expansive soil‐related movements is based on empirical correlations utilizing the measured plasticity indices and assuming typical seasonal fluctuations in moisture content. If desired, other methods of estimating expansive soil‐related movements are available, such as estimations based on swell tests and/or soil‐suction analyses. However, the performance of these tests and the detailed analysis of expansive soil‐related movements were beyond the scope of the current study. It should also be noted that actual movements can exceed the calculated PVR values due to isolated changes in moisture content or if water seeps into the soils to greater depths than the assumed active zone depth due to deep trenching or excavations.

OVEREXCAVATION AND SELECT FILL REPLACEMENT

To reduce expansive soil‐related movements in at‐grade construction for design condition A above, a portion of the upper highly expansive subgrade clays can be removed by overexcavating and backfilling with a suitable select fill material. PVR values have been estimated for overexcavation and select fill replacement to various depths below the existing ground surface and are summarized in the table below. Recommendations for the selection and placement of select backfill materials are addressed in a subsequent section of this report.

Depth of Overexcavation and Select Fill Replacement Estimated PVR (ft)* (in.) 0 1‐1/2 1 1 2 3/4 *below the ground surface elevation existing at the time of our study

The Stratum I dark brown clays contribute solely to the PVR values estimated for this site. The shallow, surficial nature of these soils renders their complete removal a viable option for reducing expansive soil‐ related ground movements at this site. To maintain the estimated PVR values above, subsequent fill placed should consist of select fill material in accordance with the Select Fill section of this report.

DRAINAGE CONSIDERATIONS

When overexcavation and select fill replacement is selected as a method to reduce the potential for expansive soil‐related movements at any site, considerations of surface and subsurface drainage may be crucial to construction and adequate foundation performance of the soil‐supported structures. Filling an excavation in relatively impervious plastic clays with relatively pervious select fill material creates a “bathtub” beneath the structure, which can result in ponding or trapped water within the fill unless good surface and subsurface drainage is provided.

Project No. AAA17‐091‐00 6 Revised, February 23, 2018

Water entering the fill surface during construction or entering the fill exposed beyond the building lines after construction may create problems with fill moisture control during compaction and increased access for moisture to the underlying expansive clays both during and after construction.

Several surface and subsurface drainage design features and construction precautions can be used to limit problems associated with fill moisture. These features and precautions may include but are not limited to the following:

 Installing berms or swales on the uphill side of the construction area to divert away from the excavation/fill area during construction;  Sloping of the top of the subgrade with a minimum downward slope of 1.5 percent out to the base of a located beyond the building perimeter;  Sloping the surface of the fill during construction to promote runoff of rain water to drainage features until the final lift is placed;  Sloping of a final, well maintained, impervious clay or pavement surface (downward away from the building) over the select fill material and any perimeter drain extending beyond the building lines, with a minimum gradient of 6 in. in 5 ft;  Constructing final surface drainage patterns to prevent ponding and limit surface water at and around the building perimeter;  Locating the water‐bearing utilities, roof drainage outlets and irrigation spray heads outside of the select fill and perimeter drain boundaries; and  Raising the elevation of the ground level floor slab.

Details relative to the extent and implementation of these considerations must be evaluated on a project‐specific basis by all members of the project design team. Many variables that influence fill drainage considerations may depend on factors that are not fully developed in the early stages of design. For this reason, drainage of the fill should be given consideration at the earliest possible stages of the project.

FOUNDATION RECOMMENDATIONS

FOUNDATION CONSIDERATIONS

Review of the borings and test data indicate that the factors discussed below will affect foundation design and construction at this site.

 The highly expansive nature of the subgrade clays within the active zone.  Lightly‐loaded shallow foundations and pavements will be susceptible to expansive, soil related shrink and swell movements with variation in .  Proposed structures are located within a 100‐year flood plain and will be susceptible to water inundation.

It is our understanding that shallow foundations such as engineered beam and slab foundations are the preferred elements for the proposed skate park, pavilion, and boat/retail structures. Foundation recommendations for the fishing pier/boardwalk will be limited to piers.

Project No. AAA17‐091‐00 7 Revised, February 23, 2018

FOUNDATION OPTIONS

The recommendations provided are based on the data obtained from our field and laboratory studies, our past experience with geotechnical conditions similar to those at this site, and our engineering design analyses. The following alternatives are available to support the park structures at Lakewood Park:

Restrooms, Pavilions, Boat/Rental Facility

 Rigid‐engineered beam and slab foundation;  Post‐tensioned slab‐on grade; and  Shallow footing foundations.

Fishing Pier/Boardwalk

 Drilled, straight‐shaft piers.

The owner may select either one of these foundation systems depending on the performance criteria established for the structures. Cost analyses have not been conducted for any foundation system and are beyond the scope of this study.

SITE GRADING

Site grading plans can result in changes in almost all aspects of foundation recommendations. We have prepared foundation recommendations based on the existing ground surface and the stratigraphic conditions encountered at the time of our study. If site grading plans differ from existing grade by more than plus or minus 1 ft, RKCI must be retained to review the site grading plans prior to bidding the project for construction. This will enable RKCI to provide input for any changes in our original recommendations that may be required as a result of site grading operations or other considerations.

SPECIAL CONSIDERATIONS ‐ FOUNDATIONS

The performance of shallow foundations constructed over soils is contingent upon good drainage and protecting the underlying clay soils from undergoing increases in soil moisture. We understand the areas being considered to construct foundation will lie within the 100‐year flood zone and there is a potential for water to pond against the foundation for several days. To help reduce the occurrence of differential foundation movements due to this condition, the following recommendations are provided:

 Overexcavate and remove all of the expansive, Stratum I clay soils and replace with non‐ expansive select fill materials. Place a clay cap over the select fill overbuild to seal and deter ponding water from seeping into the select fill building pad.

Project No. AAA17‐091‐00 8 Revised, February 23, 2018

ENGINEERED BEAM AND SLAB FOUNDATION

Amenities such as restrooms, pavilions, and the boat rental structures may be founded on engineered beam and slab foundations, provided they are designed to withstand the anticipated soil‐related movements (see Expansive Soil‐Related Movements) without impairing either the structural or their operational performance. When possible, we recommend implementing one of the Overexcavation and Select Fill Replacement options to reduce expansive soil‐related movements.

Allowable Bearing Capacity

Shallow foundations founded on native undisturbed soil or compacted, select fill should be proportioned using the design parameters tabulated below.

Minimum depth below final grade 18 in. Minimum beam width 12 in. Minimum widened beam width 18 in. Maximum allowable bearing pressure for grade beams 2,800 psf Maximum allowable bearing pressure for widened beams 3,500 psf

The above presented maximum allowable bearing pressures will provide a calculated factor of safety of about 3 with respect to the measured , provided that the subgrade is prepared and any fill is selected and placed as recommended in the Site Preparation and Select Fill sections of this report. We also recommend that a vapor barrier be placed between the supporting soils and the concrete floor slab.

B.R.A.B. Criteria

Beam and slab foundations are sometimes designed using criteria developed by the Building Research Advisory Board (B.R.A.B.). Recommended values for the Climatic Rating (Cw) and minimum unconfined compressive strength (qu) are as listed in the table below:

Climatic Rating, Cw 16

Unconfined Compressive Strength, qu 2,800 psf

We recommend the following design plasticity indices (PI) and soil support index (C) values. The design parameters apply to the conditions encountered in our boring and for the grades existing at the time of our field exploration.

Design Condition Effective PI Soil Support Index A 50 0.60 B 20 0.94 Note: If overexcavation and select fill replacement is implemented for design condition A such that all Stratum I dark brown clays are completely then design condition B may be utilized.

Project No. AAA17‐091‐00 9 Revised, February 23, 2018

If site grading operations alter the thickness of the on‐site clays then the criteria above should be reevaluated for the appropriate slab design parameters.

PTI Design Parameters

Post Tensioning Institute (PTI) design parameters were estimated for existing stratigraphic conditions using the procedures and criteria discussed in the Post‐Tensioning Institute Manual entitled “Design of Post‐ Tensioned Slabs‐on‐Ground, Third Edition” dated 2004 with the 2008 supplement.

Differential vertical swell has been estimated for center lift and edge lift conditions for use in designing foundation slabs for the stratigraphy encountered in our borings. These values were determined using a computer program entitled VOLFLO Win 1.5, as recommended by the Post Tensioning Institute. As recommended by PTI, we have evaluated differential swell for both 1) conditions varying from equilibrium and 2) conditions varying between extremes (wet/dry). The values for both of these conditions are presented in the table below. Because soil moisture conditions are likely to vary from wet to dry and dry to wet over many cycles during the lifetime of the structure, we recommend that the conditions varying between the extremes be assumed for design.

Without vertical moisture barrier (Exterior Grade Beam)

Differential Swell (in.) From Equilibrium From Equilibrium Design Condition From Dry to Wet From Wet to Dry to Wet to Dry A 3/4 (EL) ‐1/2 (CL) 2 (EL) ‐1 (CL) B 1/2 (EL) ‐1/2 (CL) 1 (EL) ‐3/4 (CL) Note: If overexcavation and select fill replacement is implemented for design condition A such that all Stratum I dark brown clays are completely removed, then design condition B may be utilized.

With vertical moisture barrier (Exterior Grade Beam)

Conditions were also analyzed with a 30 inch vertical moisture barrier (exterior grade beam). The grade beams may be terminated shallower than 30 inches if they extend 4 inches or more into native, intact limestone.

Differential Swell (in.) From Equilibrium to From Equilibrium Design Condition From Dry to Wet From Wet to Dry Wet to Dry A & B 1/4 (EL) ‐1/4 (CL) 1/4 (EL) ‐1/4 (CL)

Additional design parameters are summarized in the following table:

Project No. AAA17‐091‐00 10 Revised, February 23, 2018

Percent Fine Clay 50(1) Depth to Constant Suction, ft 1.9 Thornthwaite Index, IM ‐13 Constant Soil Suction 3.6 pF Design Condition A B Edge Moisture Variation Distance (center lift) 9.0 ft 9.0 ft Edge Moisture Variation Distance (edge lift) 5.2 ft 4.9 ft 1) Based on our experience with the soils in the region.

SHALLOW SPREAD FOOTING FOUNDATIONS

Consideration may also be given for foundation support on shallow footings for restrooms, pavilions, and the boat rental structures, provided the selected foundation type can be designed to withstand the anticipated soil‐related movements (see Expansive Soil‐Related Movements) without impairing either the structural or the operational performance of these . structures Prior to fill placement, we recommend overexcavation and select fill replacement, as discussed in the Overexcavation and Select Fill Replacement section of this report.

Allowable Bearing Capacity

Shallow, spread foundations founded on native, Stratum II tan clayey sand or Stratum III limestone or compacted, select fill should be proportioned using the design parameters tabulated below.

Select fill or clayey Limestone sand subgrade subgrade Minimum depth below final grade 24 in. Minimum spread footing width 24 in. Maximum allowable bearing pressure for spread footings 3,200 psf 6,000 psf

The above presented maximum allowable bearing pressures will provide a factor of safety of about 3 with respect to the measured shear strength, provided that fill is selected and placed as recommended in the Select Fill section of this report and the subgrade is prepared in accordance with the recommendations outlined in the Site Preparation section of this report.

Resistance to uplift loads generally consists of the structure’s dead load, the weight of the footing itself, and the backfill soil above the footing. If more resistance to these forces is required, the footing may be sized and/or deepened such that the weight of the soils above the footing may be incorporated to help resist the uplift forces. In such a case, select fill directly above the footing may be considered. For purposes of resisting uplift, a unit weight of 120 pcf should be used for fill material compacted on top of the footings. Fill above the footing should be placed in accordance with the Select Fill section of this report.

Project No. AAA17‐091‐00 11 Revised, February 23, 2018

AREA FLATWORK

It should be noted that ground‐supported flatwork such as walkways will be subject to the same magnitude of potential soil‐related movements as discussed previously (see Expansive Soil‐Related Movement section). Thus, where these types of elements abut rigid building foundations or isolated/suspended structures, differential movements should be anticipated.

Based on the anticipated ground movements due to swelling of the underlying soils beneath the sidewalk/flatwork it is our opinion that the design team should consider methods of reducing the anticipated movements through methods discussed in the Overexcavation and Select Fill Replacement section.

As a minimum, we recommend that flexible joints be provided where such elements abut the main structure to allow for differential movement at these locations. Where flatwork abuts the exterior perimeter grade beam of the new building, care must be taken to provide a smooth, vertical construction between the edge of the flatwork and the perimeter grade. beam The flatwork should preferably abut the grade beam at least 4 inches, preferably more, below the bottom of the brick lug (or other exterior veneer material) to avoid damage to the veneer when movements occur in the flatwork. The construction joint should be wide enough to assure that vertical movement in the flatwork will not bind on and subsequently damage the exterior veneer material.

The construction joint should be completed using an appropriate elastomeric expansion joint filler to reduce the amount of water passing through the construction joint. Proper and regular maintenance of the expansion joint will help reduce the water seepage at the flatwork/foundation interface.

A better option, if feasible, is to separate the flatwork away from the building foundation so that movements incurred by the flatwork are totally independent of the building foundation.

DRILLED, STRAIGHT‐SHAFT PIERS

Drilled, straight‐shaft piers may be considered to support the fishing pier/boardwalk. Straight‐shaft piers should be designed as units using an allowable side shear resistance of 2.5 ksf for the portion of the shaft extending into competent Stratum III limestone. Side shear resistance should be neglected within the upper 3 ft of the Stratum III limestone. Based on the 15 ft maximum depth of exploration, pier depths should not exceed a depth of 15 ft below the ground surface existing at the time of our study.

Drilled, straight‐shaft piers socketed a minimum of 2 ft into the StratumI II tan limestone may also be proportioned using a maximum allowable end bearing pressure of 25 ksf. However, we recommend that a minimum of 70 percent of the applied load be carried in side shear.

Final shaft depths will be based on interpretation of conditions in the field at the time of construction. Due to the variable conditions at this site, a representative from RKCI must be present at the time of construction to verify that conditions are similar to those encountered in our borings and that sufficient penetration into the limestone is achieved. If clay seams/and or voids are encountered within the limestone formation during drilled shaft excavations, the shafts must be extended to develop the required side shear resistance. For bid purposes, the owner should anticipate that deeper piers will be required in

Project No. AAA17‐091‐00 12 Revised, February 23, 2018

some areas. Consequently, contractors bidding on the job should include unit costs for various depths of additional pier embedment. Unit costs should include those for both greater and lesser depth in the rock.

Piers for the fishing pier/boardwalk are anticipated to be drilled in the lake. Shallow groundwater conditions may also be encountered in areas outside the lake, depending on seasonal conditions and/or recent precipitation. Casing is expected to be required to facilitate drilled pier construction of the piers and the contractor should include unit costs for casing.

Pier Shaft Potential Uplift Forces

The pier shafts will be subject to potential uplift forces if the surrounding expansive soils within the active zone are subjected to alternate drying and wetting conditions. The maximum potential uplift force acting on the shaft may be estimated by:

Fu = 20*D where:

Fu = uplift force in kips; and D = diameter of the shaft in feet.

Allowable Uplift Resistance

Resistance to uplift forces exerted on the drilled, straight‐shaft piers will be provided by the sustained compressive axial force (dead load) plus the allowable uplift resistance provided by the rock. The allowable uplift resistance provided by the intact limestone rock at this site may be estimated using an allowable side shear resistance of 1.7 ksf for the portion of the shaft extending into competent limestone. This value was evaluated using a factor of safety of 2.

Reinforcing steel will be required in each pier shaft to withstand a net force equal to the uplift force minus the sustained compressive load carried by that pier. We recommend that each pier be reinforced to withstand this net force or an amount equal to 1 percent of the cross‐sectional area of the shaft, whichever is greater.

PIER SPACING

Where possible, we recommend that the piers be spaced at a center to center distance of at least three shaft diameters on‐center for straight‐shaft piers. Such spacing will not require a reduction in the load carrying capacity of the individual piers.

If design and/or construction restraints require that piers be spaced closer than the recommended three shaft diameters, RKCI must re‐evaluate the allowable bearing capacities presented above for the individual piers. Reductions in load carrying capacities may be required depending upon individual loading and spacing conditions.

Project No. AAA17‐091‐00 13 Revised, February 23, 2018

RETAINING STRUCTURES

Based on information provided by the project civil engineer, we understand there is a proposed retaining wall located approximately 900 ft north of Boring B‐2. The retaining wall is expected to be about 12 ft in height and 80 ft long. The wall will act as soil retaining structures and should be designed for lateral earth pressures. Drainage conditions will also need to be considered in design.

Soil borings were not drilled in the vicinity of the proposed retaining wall. If subsurface conditions are not similar to the conditions encountered in our borings, RKCI should be retained to evaluate the conditions and provide supplemental recommendations.

LATERAL EARTH PRESSURES

Equivalent fluid density values for computation of lateral soil pressures acting on retaining walls were evaluated for various types of backfill materials that may be placed behind the retaining walls. These values, as well as corresponding coefficients and estimated unit weights, are presented below in preferential order for use as backfill materials.

Estimated Active Condition At Rest Condition Total Unit Earth Pressure Equivalent Fluid Earth Pressure Equivalent Fluid Weight Back Fill Type Coefficient, ka Density Coefficient, ko Density (pcf) (pcf) (pcf) Washed 135 0.29 40 0.45 60 Crushed Limestone 145 0.24 35 0.38 55 Clean Sand 120 0.33 40 0.5 60 Pit Run Clayey 135 0.32 45 0.48 65 or Clays 120 0.59 70 0.74 90

The values tabulated above under “Active Conditions” pertain to flexible retaining walls free to tilt outward as a result of lateral earth pressures. For rigid, non‐yielding walls the values under “At‐Rest Conditions” should be used.

The values presented above assume the surface of the backfill materials to be level. Sloping the surface of the backfill materials will increase the surcharge load acting on the structures. The above values also do not include the effect of surcharge loads such as construction equipment, vehicular loads, or future storage near the structures. Nor do the values account for possible hydrostatic pressures resulting from groundwater seepage entering and ponding within the retained backfill materials. As discussed later, the walls should be provided with a drain system to allow for the dissipation of water. Surcharge loads and groundwater pressures should be considered in designing any structures subjected to lateral pressures.

The on‐site clays exhibit significant shrink/swell characteristics. The use of clay soils as backfill against the proposed retaining structures is not recommended. These soils generally provide higher design active earthen pressures, as indicated above, but may also exert additional active pressures associated

Project No. AAA17‐091‐00 14 Revised, February 23, 2018

with swelling. Controlling the moisture and density of these materials during placement will help reduce the likelihood and magnitude of future active pressures due to swelling, but this is no guarantee.

BACKFILL COMPACTION

Placement and compaction of backfill behind the retaining walls will be critical, particularly at locations where backfill will support adjacent near‐grade foundations and/or flatwork. If the backfill is not properly compacted in these areas, the adjacent foundations/flatwork can be subject to settlement.

To reduce potential settlement of adjacent foundations/flatwork, the backfill materials should be placed and compacted as recommended in the Select Fill section of this report. Each lift or layer of the backfill should be tested during the backfilling operations to document the degree of compaction. Within at least a 5‐ft zone of the wall backside, we recommend that compaction be accomplished using hand‐ guided compaction equipment capable of achieving the maximum density in a series of 3 to 5 passes.

DRAINAGE

The use of drainage systems is a positive design step toward reducing the possibility of hydrostatic pressure acting against the retaining structures. Drainage may be provided by the use of a drain trench and pipe. The drain pipe should consist of a slotted, heavy duty, corrugated polyethylene pipe and should be installed and bedded according to the manufacturer’s recommendations. The drain trench should be filled with gravel (meeting the requirements of ASTM D 448 coarse concrete aggregate Size No. 57 or 67) and extend from the base of the structure to within 2 ft of the top of the structure. The bottom of the drain trench will provide an envelope of gravel around the pipe with minimum dimensions consistent with the pipe manufacturer’s recommendations. The gravel should be wrapped with a suitable fabric (such as Mirafi 140N or equivalent) to help minimize the intrusion of fine‐grained soil particles into the drain system. The pipe should be sloped and equipped with clean‐out access fittings consistent with state‐of‐the‐practice plumbing procedures.

As an alternative to a full‐height gravel drain trench behind the proposed retaining structures, consideration may be given to utilizing a manufactured geosynthetic material for wall drainage. A number of products are available to control hydrostatic pressures acting on earth retaining structures, including Amerdrain (manufactured by American Wick Drain Corp.), Miradrain (manufactured by Mirafi, Inc.), Enkadrain (manufactured by American Enka Company), and Geotech Insulated Drainage Panel (manufactured by Geotech Systems Corp.). The are placed directly against the retaining structures and are hydraulically connected to the gravel envelope located at the base of the structures.

RETAINING WALL FOOTINGS

The proposed retaining wall may be supported on native Stratum II clayey sand (decomposed limestone) or Stratum III limestone at a minimum depth of 2 ft below final grade. Footings may be designed using maximum allowable bearing pressures of 2,300 psf for Stratum II clayey sand (decomposed limestone) and 5,000 psf for Stratum III limestone. A coefficient of sliding friction of 0.55 may be assumed in evaluation of the factor of safety against sliding.

Project No. AAA17‐091‐00 15 Revised, February 23, 2018

SPECIAL CONSIDERATIONS – RETAINING WALLS

It is understood that retaining walls could be subject to inundation due to the 100 year flood event. As a result, there should be concern of water infiltrating backfill materials behind the wall. Inundation of water could result in migration of fine‐grained soils resulting in voids, thus increased risk of isolated settlements or collapses. Additionally, water entering the fill materials could saturate the fills, inducing additional lateral loads on the retaining walls and causing weakening of the retaining wall fill soils and/or foundation soils and could also result in differential settlement.

Considering these possibilities, it is recommended that the designer consider the following:

 If a cast‐in‐place concrete retaining wall is used, the wall should be designed with water‐tight joints to deter flood waters from seeping into the back of the wall. The wall should have a wall drain embedded with porous gravel to relieve hydrostatic pressures as soon as possible.  If a MSE wall or other walls are used that could allow penetration of flood waters into the back of the wall, we recommend the retaining wall be backfilled with specialized embankment fill materials in conjunction with underdrain and vertical chimney drains. Another recommendation is backfill of the retaining wall with Cement Stabilized backfill, in lieu of select fill gravels as selected and placed per TxDOT item 423. In both cases, special drainage conditions will be required.

FOUNDATION CONSTRUCTION CONSIDERATIONS

SITE DRAINAGE

Drainage is an important key to the successful performance of any foundation. Good surface drainage should be established prior to and maintained after construction to help prevent water from ponding within or adjacent to building foundations or footings and to facilitate rapid drainage away from these structures. Failure to provide positive drainage away from the structures can result in localized differential vertical movements in soil supported foundations and floor slabs, which can in turn result in improper operation of windows and doors.

Current ordinances, in compliance with the Americans with Disabilities Act (ADA), may dictate maximum slopes for walks and drives around and into new buildings. These slope requirements can result in drainage problems for buildings supported on expansive soils. We recommend that the maximum permissible slope be provided away from the building on all sides.

Also to help control drainage in the vicinity of the structure, we recommend that roof/gutter downspouts and landscaping irrigation systems not be located adjacent to the building foundations. Where a select fill overbuild is provided outside of the floor slab/foundation footprint, the surface should be sealed with an impermeable layer (pavement or clay cap) to reduce infiltration of both irrigation and surface waters. Careful consideration should also be given to the location of water bearing utilities, as well as to provisions for drainage in the event of leaks in water bearing utilities. All leaks should be immediately repaired.

Other drainage and subsurface drainage issues are discussed in the Expansive Soil‐Related Movements section of this report and under Pavement Construction Considerations.

Project No. AAA17‐091‐00 16 Revised, February 23, 2018

SITE PREPARATION

Building areas and all areas to support select fill should be stripped of all vegetation and organic . Tree roots greater than 1 inch in diameter should be grubbed and removed. Any voids resulting from removal of tree roots should be backfilled with a suitable, compacted fill material, free of organics, degradable material, and particles exceeding 4 inches in size. On‐site brown to dark brown clay may be utilized to fill in voids in areas outside the building footprints. Furthermore, as discussed in a previous section of this report, we recommend that an Overexcavation and Select Fill Replacement option be utilized to reduce expansive soil‐related movements. Select fill overbuilds should extend at least 3 ft outside the building footprint and the select fill overbuild should be sealed with clay cap to minimize water infiltration into the select fill building pad.

Exposed subgrades should be thoroughly proofrolled in order to locate weak, compressible zones. A minimum of 5 passes of a fully‐loaded dump truck or a similar heavily‐loaded piece of construction equipment should be used for planning purposes. Proofrolling operations should be observed by the Geotechnical Engineer or their representative to document subgrade condition and preparation. Weak or soft areas identified during proofrolling should be removed and replaced with suitable, compacted on‐site clays, free of organics, oversized materials, and degradable or deleterious materials.

Upon completion of the proofrolling operations and just prior to fill placement or slab construction, the exposed subgrade should be moisture conditioned by scarifying to a minimum depth of 6 in. and recompacting to a minimum of 95 percent of the maximum density determined from TxDOT, Tex‐114‐E, Compaction Test. The moisture content of the subgrade should be maintained within the range of optimum moisture content to 3 percentage points above optimum moisture content until permanently covered.

In areas of exposed competent and intact limestone rock subgrade, the subgrade shall be proofrolled in order to locate and densify any weak compressible zones. Scarification and moisture conditioning will not be required on competent and intact limestone rock.

SELECT FILL

Materials used as select fill for building pads preferably should be or gravel aggregate. We recommend that materials specified for use as select fill meet the gradation requirements of 2014 TxDOT Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges, Item 247, Flexible Base, Types A or C, Grades 1‐2 or 3, and have a maximum plasticity index of 20.

Select fill should be placed in loose lifts not exceeding 8 in. in thickness and compacted to at least 95 percent of maximum density as determined by TxDOT, Tex‐113‐E, Compaction Test. The moisture content of the fill should be maintained within the range of 2 percentage points below to 2 percentage points above the optimum moisture content until final compaction.

Alternatively, clayey gravel (GC) or clayey sand (SC) soils, as classified according to the Unified System (USCS), may be considered satisfactory for use as Alternative Select Fill materials at this site. Alternative select fill materials shall have a maximum liquid limit not exceeding 40, a plasticity index between 7 and 20, and a maximum particle size not exceeding 4 in. or one‐half the loose lift

Project No. AAA17‐091‐00 17 Revised, February 23, 2018

thickness, whichever is smaller. In addition, if these materials are utilized, grain size analyses and must be performed during placement at a rate of one test each per 5,000 cubic yards of material due to the high degree of variability associated with pit‐run materials.

If the above listed alternative materials are being considered for bidding purposes, the materials should be submitted to the Geotechnical Engineer for pre‐approval at a minimum of 10 working days or more prior to the bid date. Failure to do so wille be th responsibility of the contractor. The contractor will also be responsible for ensuring that the properties of all delivered alternate select fill materials are similar to those of the pre‐approved submittal. It should also be noted that when using alternative fill materials, difficulties may be experienced with respect to moisture control during and subsequent to fill placement, as well as with erosion, particularly when exposed to inclement weather. This may result in sloughing of beam and/or pumping of the fill materials.

Soils classified as CH, CL, MH, ML, SM, GM, OH, OL and Pt under the USCS aret no considered suitable for use as select fill materials at this site. The native soils are not considered suitable for use as select fill materials.

CLAY CAP

It is anticipated that overexcavation and select fill replacement will be implemented to reduce expansive soil‐related movements in at‐grade construction. In areas where a select fill overbuild is provided outside the building footprint or along the perimeter of the foundations where the fill is exposed, we recommend sealing the exposed surface with a 2 ft minimum impermeable clay layer to reduce infiltration of irrigation and surface water runoff during major rain events.

Materials used as clay cap material should consist of CH soils as classified according to the Unified Soil Classification Systems (USCS) and having a maximum Plasticity Index of 45. We recommend that clay soils be placed in loose lifts not exceeding 8 inches in thickness and compacted to at least 95 percent of the maximum density as determined by TxDOT, TEX 114‐E. The moisture content of the fill should be maintained within the range of optimum to plus 3 percentage points above optimum. We recommend that fill materials be free of roots or other organic or degradable material.

SHALLOW FOUNDATION EXCAVATIONS

Shallow foundation excavations should be observed by the Geotechnical Engineer or their representative prior to placement of reinforcing steel and concrete. This is necessary to observe that the bearing soils at the bottom of the excavations are similar to those encountered in our borings and that excessive loose materials and water are not present in the excavations. If soft pockets of soil are encountered in the foundation excavations, they should be removed and replaced with a compacted non‐expansive fill material or lean concrete up to the design foundation bearing elevations.

Project No. AAA17‐091‐00 18 Revised, February 23, 2018

DRILLED PIERS

Each drilled pier excavation must be examined by an RKCI representative who is familiar with the geotechnical aspects of the soil stratigraphy, the structural configuration, foundation design details and assumptions, prior to placing concrete. This is to observe that:

 The shaft has been excavated to the specified dimensions at the correct depth established by the previously mentioned criteria;  An acceptable portion of the shaft penetrates intact limestone versus weathered and/or clay seams;  The drilled pier excavation remains dry with 1 inch or less standing water prior to concrete placement;  The shaft has been drilled plumb within specified tolerances along its total length; and Excessive cuttings, buildup and soft, compressible materials have been removed from the bottom of the excavation.

Reinforcement and Concrete Placement

Reinforcing steel should be checked for size and placement prior to concrete placement. Placement of concrete should be accomplished as soon as possible after excavation to reduce changes in the moisture content or the state of stress of the foundation materials. No foundation element should be left open overnight without concreting.

Casing

Groundwater seepage and/or side sloughing is expected to be encountered at the time of drilled pier construction. We recommend that the bid documents require the foundation contractor to specify unit costs for different lengths of casing that may be required. Due to the presence of water in the lake, permanent casing may be required, depending on the means and methods of installation.

EXCAVATION SLOPING AND BENCHING

If utility trenches or other excavations extend to or below a depth of 5 ft below construction grade, the contractor or others shall be required to develop a trench safety plan to protect personnel entering the trench or trench vicinity. The collection of specific geotechnical data and the development of such a plan, which could include designs for sloping and benching or various types of temporary shoring, are beyond the scope of the current study. Any such designs and safety plans shall be developed in accordance with current OSHA guidelines and other applicable industry standards.

EXCAVATION EQUIPMENT

Due to the shallow nature of the surficial soils, excavations at this site will require removal of the underlying rock formation. Thus, the need of rock excavation equipment should be anticipated for construction at this site. Our boring logs are not intended for use in determining construction means and methods and may therefore be misleading if used for that purpose. We recommend that earth‐ work and utility contractors interested in bidding on the work perform their own tests in the form of

Project No. AAA17‐091‐00 19 Revised, February 23, 2018

test pits to determine the quantities of the different materials to be excavated, as well as the preferred excavation methods and equipment for this site.

UTILITIES

Utilities which project through slab‐on‐grade, slab‐on‐fill, or any other rigid unit should be designed with either some degree of flexibility or with sleeves. Such design features will help reduce the risk of damage to the utility lines as vertical movements occur.

Our experience indicates that significant settlement of backfill can occur in utility trenches, particularly when trenches are deep, when backfill materials are placed in thick lifts with insufficient compaction, and when water can access and infiltrate the trench backfill materials. The potential for water to access the backfill is increased where water can infiltrate flexible base materials due to insufficient penetration of curbs, and at sites where geological features can influence water migration into utility trenches (such as fractures within a rock mass or at contacts between rock and clay formations). It is our belief that another factor which can significantly impact settlement is the migration of fines within the backfill into the open voids in the underlying free‐draining bedding material.

To reduce the potential for settlement in utility trenches, we recommend that consideration be given to the following:

 All backfill materials should be placed and compacted in controlled lifts appropriate for the type of backfill and the type of compaction equipment being utilized and all backfilling procedures should be tested and documented. Trench backfill materials should be placed in loose lifts not exceeding 8 inches in thickness and compacted to at least 95 percent of maximum density as determined by TxDOT, Tex‐113‐E4 ‐or Tex‐11 E, Compaction Test. The moisture content of the fill should be maintained within the range of 2 percentage points below to 2 percentage points above the optimum moisture content for non‐ cohesive soils and maintained within the range of optimum to 3 percentage points above optimum moisture content for cohesive soils until final compaction.  Curbs should completely penetrate base materials and be installed to a sufficient depth to reduce water infiltration beneath the curbs into the pavement base materials.  Consideration should be given to wrapping free‐draining bedding gravels with a geotextile fabric (similar to Mirafi 140N) to reduce the infiltration and loss of fines from backfill material into the interstitial voids in bedding materials.

PAVEMENT RECOMMENDATIONS

Walking trails are planned to provide connectivity over several miles throughout the park. A central parking lot is also planned. Given the entire Lake Lakewood Park is located within a 100‐year flood plain. Consideration should be given to the inundation of pavements in water.

Recommendations for both flexible and rigid pavements are presented in this report. The Owner and/or design team may select either pavement type depending on the performance criteria established for the project. In general, flexible pavement systems have a lower initial construction cost as compared to rigid pavements. However, maintenance requirements over the life of the pavement are typically much

Project No. AAA17‐091‐00 20 Revised, February 23, 2018

greater for flexible pavements. This typically requires regularly scheduled observation and repair, as well as overlays and/or other pavement rehabilitation at approximately one‐half to two‐thirds of the design life. For flexible pavements that may be susceptible to water infiltration, consideration should be given to protecting the flexible base layer by extending curbs past base material or sealing the exposed flexible base with an impermeable clay cap to reduce water infiltration. Alternatively, consideration may be given to eliminating the flexible base section and designing the asphalt pavements solely with asphaltic materials bearing directly on natural subgrade.

Rigid pavements as compared to flexible are generally more "forgiving", and therefore tend to be more durable and require less maintenance after construction. Additionally, consideration of the erosion of the flexible base layer is eliminated as rigid pavements are typically constructed on natural subgrade.

For either pavement type, drainage conditions will have a significant impact on long term performance, particularly where permeable base materials are utilized in the pavement section. Drainage considerations are discussed in more detail in a subsequent section of this report.

SUBGRADE CONDITIONS

We have assumed the subgrade in pavement areas will consist of the Stratum I clays or recompacted on‐site clays, placed and compacted as recommended in the On‐Site Clay Fill section of this report. Based on our experience with similar subgrade soils, we have assigned a (CBR) value of 3 for use in pavement thickness design analyses.

DESIGN INFORMATION

The following recommendations were prepared based on the 1993 “Guide for the Design of Pavement Structures” by the American Association of State Highway and Transportation Officials (AASHTO). The recommendations for the parking lot and entrance roadway were prepared assuming a 20‐yr design life and Equivalent Single Axle Loads (ESALs) of 20,000 for light duty pavements. This traffic frequency is approximately equivalent to 1 tractor‐trailer truck per day for a design period of 20 years. The recommendations for the multi‐use trails were prepared with the assumption that primary usage would be limited to pedestrian and bicycle traffic.

The Project Civil Engineer should review anticipated traffic loading and frequencies to verify that the assumed traffic loading and frequency is appropriate for the intended use of the facility.

FLEXIBLE PAVEMENT (PARKING LOT/ENTRANCE ROADWAY)

Flexible pavement sections recommended for this site are as listed in the table below:

Project No. AAA17‐091‐00 21 Revised, February 23, 2018

Layer Thickness Layer Description Option 1 1 Option 2 2 Option 3 1 HMAC Surface Course, Type “B” ‐ ‐ 7.0 in. HMAC Surface Course, Type “D” 2.0 in. 2.0 in. ‐ Light Duty Flexible Base 10.0 in. 10.0 in. ‐ (20,000 ESALs) Lime Treated Subgrade _ 8.0 in._ __‐__ _ 8.0 in._ Combined Total 20.0 in. 12.0 in. 15.0 in. 1 The lime treated subgrade section may be eliminated if Stratum II clayey sand (decomposed limestone) or limestone subgrade is exposed after grading. 2 Lime treatment may also be eliminated by overexcavation of the upper 12 to 24 in. of Stratum I dark brown to brown clay and replacement with low PI material meeting the Alternative Select Fill specifications. The pavement section provided in Option 2 is recommended only if this replacement takes place.

RIGID PAVEMENT (PARKING LOT/ENTRANCE ROADWAY)

We recommend that rigid pavement sections at this site consist of the following. Concrete pavements will be less susceptible to damage associated with ponding of water following storm events.

As a performance alternative, the subgrade clay soils beneath the pavements could be lime‐treated beneath the concrete pavements with the treatment extending 3 ft beyond the back of curb. The lime treatment will act as a moisture barrier and help deter ponding water from seeping into the clay soils and causing differential movements of the concrete pavements, especially along the pavement edges.

Traffic Type Portland Cement Concrete Light Duty (20,000 ESALs) 5 in. *Note: A flexible base layer is not required beneath the concrete section.

We recommend that the concrete pavements be reinforced with bar mats. As a minimum, the bar mats should be No. 3 reinforcing bars spaced 18 in. on center in both directions. The concrete reinforcing should be placed approximately 1/3 the slab thickness below the surface of the slab, but not less than 2 in. The reinforcing should not extend across expansion joints.

Joints in concrete pavements aid in the construction and control the location and magnitude of cracks. Where practical, lay out the construction, expansion, control and sawed joints to form square panels, but not to exceed ACI 302.69 Code recommendations. The ratio of slab length‐to‐width should not exceed 1.25. Maximum recommended joint spacings are 12 ft longitudinal and 12 ft transverse.

All control joints should be formed or sawed to a depth of at least 1/4 the thickness of the concrete slab. Sawing of control joints should begin as soon as the concrete will not ravel, generally the day after placement. Control joints may be hand formed or formed by using a premolded filler. We recommend that all longitudinal and transverse construction joints be dowelled to promote load transfer. Expansion joints are needed to separate the concrete slab from fixed objects such as drop inlets, light standards and buildings. Expansion joint spacings are not to exceed a maximum of 75 ft and no expansion or construction joints should be located in a swale or drainage collection locations.

Project No. AAA17‐091‐00 22 Revised, February 23, 2018

If possible, the pavement should develop a minimum slope of 0.015 ft/ft to provide surface drainage. pavement should cure a minimum of 3 and 7 days before allowing automobile and truck traffic, respectively.

MULTI‐USE TRAILS

It should be noted that ground‐supported flatwork such as the proposed multi‐use trails will be subject to the same magnitude of potential expansive, soil‐related movements as discussed previously (see Expansive Soil‐Related Movement). If these movements are objectionable, the performance of the pavements could be improved by lime stabilizing the subgrade beneath the trails and extending the treatment 3 to 5 ft beyond the pavement edges.

The following pavement section is recommended for the trails. However, we recommend the project civil engineer consult with the City of Leander standard sidewalk details and specifications.

Portland Cement Concrete 4 in.

PAVEMENT CONSTRUCTION CONSIDERATIONS

SUBGRADE PREPARATION

Areas to support pavements should be stripped of all vegetation and organic topsoil and the exposed subgrade should be proofrolled in accordance with the recommendations in the Site Preparation section under Foundation Construction Considerations.

After completion of the proofrolling operations and just prior to flexible base placement, the exposed subgrade should be moisture conditioned by scarifying to a minimum depth of 6 in. and recompacting to a minimum of 95 percent of the maximum density determined from the Texas Department of Transportation Compaction Test (TxDOT, Tex‐114‐E). The moisture content of the subgrade should be maintained within the range of optimum moisture content to 3 percentage points above optimum until permanently covered.

DRAINAGE CONSIDERATIONS

As with any soil‐supported structure, the satisfactory performance of a pavement system is contingent on the provision of adequate surface and subsurface drainage. Insufficient drainage which allows saturation of the pavement subgrade and/or the supporting granular pavement materials will greatly reduce the performance and service life of the pavement systems.

Surface and subsurface drainage considerations crucial to the performance of pavements at this site include (but are not limited to) the following:

1) Any known natural or man‐made subsurface seepage at the site which may occur at sufficiently shallow depths as to influence moisture contents within the subgrade should be intercepted by drainage ditches or below grade French drains.

Project No. AAA17‐091‐00 23 Revised, February 23, 2018

2) Final site grading should eliminate isolated depressions adjacent to curbs which may allow surface water to pond and infiltrate into the underlying soils. Curbs should completely penetrate base materials and should be installed to sufficient depth to reduce infiltration of water beneath the curbs. 3) Pavement surfaces should be maintained to help minimize surface ponding and to provide rapid sealing of any developing cracks. These measures will help reduce infiltration of surface water downward through the pavement section.

ON‐SITE CLAY FILL

As discussed previously, the pavement recommendations presented in this report were prepared assuming that on‐site soils will be used for fill grading in proposed pavement areas. If used, we recommend that on‐site soils be placed in loose lifts not exceeding 8 in. in thickness and compacted to at least 95 percent of the maximum density as determined by TxDOT, Tex‐114‐E. The moisture content of the fill should be maintained within the range of optimum water content to 3 percentage points above the optimum water content until permanently covered. We recommend that fill materials be free of roots and other organic or degradable material. We also recommend that the maximum particle size not exceed 4 in. or one half the lift thickness, whichever is smaller.

ALTERNATIVE SELECT FILL

Materials utilized as alternative select fill may be classified as clayey gravel (GC) or clayey sand (SC) soils, as classified according to the Unified Soil Classification System (USCS), may be considered satisfactory for use as Alternative Select Fill materials at this site. Alternative select fill materials shall have a maximum liquid limit not exceeding 40, a plasticity index between 7 and 25, and a maximum particle size not exceeding 4 in. or one‐half the loose lift thickness, whichever is smaller. In addition, if these materials are utilized, grain size analyses and Atterberg Limits must be performed during placement at a rate of one test each per 5,000 cubic yards of material due to the high degree of variability associated with pit‐run materials.

LIME TREATMENT OF SUBGRADE9

Lime treatment of the subgrade soils should be in accordance with the TxDOT Standard Specifications, Item 260. A sufficient quantity of hydrated lime should be mixed with the subgrade soils until either the pH of the soil‐lime mixture is at least 12.4 or higher concentrations of lime do not increasee th pH, as specified in Part III of TxDOT procedure Tex‐121‐E, Soil Lime Testing. For estimating purposes, we recommend that 5 percent lime by weight be assumed for treatment. For construction purposes, we recommend that the optimum lime content of the subgrade soils be determined by laboratory testing.

Lime‐treated subgrade soils should be compacted to a minimum of 95 percent of the maximum density at a moisture content within the range of optimum moisture content to 3 percentage points above the optimum moisture content as determined by Tex‐113‐E. We recommend that lime treatment extend at least 3 ft beyond the curb.

If lime treatment is considered as a method to improve pavement subgrade conditions, it is also recommended to perform additional laboratory testing to determine the concentration of soluble sulfates in the subgrade soils, in order to investigate the potential for a recently reported adverse reaction to lime

Project No. AAA17‐091‐00 24 Revised, February 23, 2018

in certain sulfate‐containing soils. The adverse reaction, referred to as sulfate‐induced heave, has been known to cause cohesive subgrade soils to swell in short periods of time, resulting in pavement heaving and possible failure.

FLEXIBLE BASE COURSE

The flexible base course should be crushed limestone conforming to TxDOT Standard Specifications, Item 247, Type A, Grades 1‐2 or 5. Base course should be placed in lifts with a maximum thickness of 8 in. and compacted to a minimum of 100 percent of the maximum density at a moisture content within the range of 2 percentage points below to 2 percentage points above the optimum moisture content as determined by Tex‐113‐E.

ASPHALTIC CONCRETE SURFACE COURSE

The asphaltic concrete surface course should conform to TxDOT Standard Specifications, Item 340 or 341, Type B or D. The asphaltic concrete should be compacted to a minimum of 92 percent of the maximum theoretical specific gravity (Rice) of the mixture determined according to Test Method Tex‐227‐F. Pavement specimens, which shall be either cores or sections of asphaltic pavement, will be tested according to Test Method Tex‐207‐F. The nuclear‐density gauge or other methods which correlate satisfactorily with results obtained from project roadway specimens may be used when approved by the Engineer. Unless otherwise shown on the plans, the Contractor shall be responsible for obtaining the required roadway specimens at their expense and in a manner and at locations selected by the Engineer.

PORTLAND CEMENT CONCRETE

The Portland cement concrete should be air entrained to result in a 4 percent plus/minus 1 percent air, should have a maximum slump of 5 inches, and should have a minimum 28‐day compressive strength of 4,000 psi. A liquid membrane‐forming curing compound should be applied as soon as practical after broom finishing the concrete surface. The curing compound will help reduce the loss of water from the concrete. The reduction in the rapid loss in water will help reduce shrinkage cracking of the concrete.

CONSTRUCTION RELATED SERVICES

CONSTRUCTION MATERIALS TESTING AND OBSERVATION SERVICES

As presented in the attachment to this report, Important Information About Your Geotechnical Engineering Report, subsurface conditions can vary across a project site. The conditions described in this report are based on interpolations derived from a limited number of data points. Variations will be encountered during construction, and only the geotechnical design engineer will be able to determine if these conditions are different than those assumed for design.

Construction problems resulting from variations or anomalies in subsurface conditions are among the most prevalent on construction projects and often lead to delays, changes, cost overruns, and disputes. These variations and anomalies can best be addressed if the geotechnical engineer of record, RKCI is retained to perform construction observation and testing services during the construction of the project. This is because:

Project No. AAA17‐091‐00 25 Revised, February 23, 2018

 RKCI has an intimate understanding of the geotechnical engineering report’s findings and recommendations. RKCI understands how the report should be interpreted and can provide such interpretations on site, on the client’s behalf.  RKCI knows what subsurface conditions are anticipated at the site.  RKCI is familiar with the goals of the owner and project design professionals, having worked with them in the development of the geotechnical workscope. This enables RKCI to suggest remedial measures (when needed) which help meet the owner’s and the design teams’ requirements.  RKCIs ha a vested interest in client satisfaction, and thus assigns qualified personnel whose principal concern is client satisfaction. This concern is exhibited by the manner in which contractors’ work is tested, evaluated and reported, and in selection of alternative approaches when such may become necessary.  RKCI cannot be held accountable for problems which result due to misinterpretation of our findings or recommendations when we are not on hand to provide the interpretation which is required.

BUDGETING FOR CONSTRUCTION TESTING

Appropriate budgets need to be developed for the required construction testing and observation activities. At the appropriate time before construction, we advise that RKCI and the project designers meet and jointly develop the testing budgets, as well as review the testing specifications as it pertains to this project.

Once the construction testing budget and scope of work are finalized, we encourage a preconstruction meeting with the selected contractor to review the scope of work to make sure it is consistent with the construction means and methods proposed by the contractor. RKCI looks forward to the opportunity to provide continued support on this project, and would welcome the opportunity to meet with the Project Team to develop both a scope and budget for these services.

* * * * * * * * * * * * * * * * * *

ATTACHMENTS

Geeoorrggeettoownn ¤£183 S I T E

Williamson ^_ §¨¦35

Travis

Austin SITE LOCATION MAP

B-1 ?! P-1 P-2 ?! P-3 ?! P-4 ?! ?!

B-4 ?!

PR-1 B-3 ?! ?!

B-2 ?! Legend ?! BORING PROPOSED PLAYGROUND PROPOSED FISHING PIER PROPOSED SKATE PARK PROPOSED BASKETBALL COURT PROPOSED RETAINING WALL PROPOSED PAVEMENT Proposed Structure µ BOAT RENTAL PAVILLION 0 100 200 400 RESTROOM FEET 1 INCH = 400 FEET

PROJECT No.: AAA17-091-00 ISSUE DATE: 02/22/2018 DRAWN BY: KRB 8100 Cameron Road, Suite B-150 CHECKED BY: RTS Austin, Texas 78754 BORING LOCATION MAP REVIEWED BY: YGT (512)339-1745 TEL LAKE LAKEWOOD PARK SITE FIGURE (512)339-6174 FAX LEANDER, TEXAS www.rkci.com WILLIAMSON COUNTY TBPE Firm Number 3257 1 NOTE: This Drawing is Provided for Illustration Only, May Not be to Scale and is Not Suitable for Design or Construction Purposes LOG OF BORING NO. B-1 Lake Lakewood Park Site Leander, Texas TBPE Firm Registration No. F-3257 DRILLING METHOD: Straight Flight Auger LOCATION: N 30.56012; W 97.81305 SHEAR STRENGTH, TONS/FT2

0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 DESCRIPTION OF MATERIAL

PLASTIC WATER LIQUID INDEX % -200 SYMBOL SAMPLES UNIT DRY DEPTH, FT

LIMIT CONTENT LIMIT PLASTICITY WEIGHT, pcf BLOWS PER FT BLOWS PER 10 20 30 40 50 60 70 80 CLAY (CH), Fat, Very Stiff, Dark Brown

24 52 CLAYEY SAND (SC), Very Dense, Tan (decomposed limestone)

50/11"

LIMESTONE, Hard, Tan ref/3" 5

ref/2"

ref/1"

10 Boring Terminated

NOTES: 1. Groundwater not encountered during drilling operations. 2. was backfilled with auger cuttings. NOTE: THESE LOGS SHOULD NOT BE USED SEPARATELY FROM THE PROJECT REPORT

15

DEPTH DRILLED: 10.0 ft DEPTH TO WATER: Dry PROJ. No.: AAA17-091-00 DATE DRILLED: 1/10/2018 DATE MEASURED: 1/10/2018 FIGURE: 2 LOG OF BORING NO. B-2 Lake Lakewood Park Site Leander, Texas TBPE Firm Registration No. F-3257 DRILLING METHOD: Straight Flight Auger LOCATION: N 30.55681; W 97.81237 SHEAR STRENGTH, TONS/FT2

0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 DESCRIPTION OF MATERIAL

PLASTIC WATER LIQUID INDEX % -200 SYMBOL SAMPLES UNIT DRY DEPTH, FT

LIMIT CONTENT LIMIT PLASTICITY WEIGHT, pcf BLOWS PER FT BLOWS PER 10 20 30 40 50 60 70 80 CLAY (CH), Fat, Very Stiff, Dark Brown

CLAYEY SAND (SC), Very Dense, Tan 22 (decomposed limestone)

50/10"

LIMESTONE, Hard, Tan ref/4" 5

ref/1"

ref/1"

10 Boring Terminated

NOTES: 1. Groundwater not encountered during drilling operations. 2. Borehole was backfilled with auger cuttings. NOTE: THESE LOGS SHOULD NOT BE USED SEPARATELY FROM THE PROJECT REPORT

15

DEPTH DRILLED: 10.0 ft DEPTH TO WATER: Dry PROJ. No.: AAA17-091-00 DATE DRILLED: 1/10/2018 DATE MEASURED: 1/10/2018 FIGURE: 3 LOG OF BORING NO. B-3 Lake Lakewood Park Site Leander, Texas TBPE Firm Registration No. F-3257 DRILLING METHOD: Straight Flight Auger LOCATION: N 30.55760; W 97.80958 SHEAR STRENGTH, TONS/FT2

0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 DESCRIPTION OF MATERIAL

PLASTIC WATER LIQUID INDEX % -200 SYMBOL SAMPLES UNIT DRY DEPTH, FT

LIMIT CONTENT LIMIT PLASTICITY WEIGHT, pcf BLOWS PER FT BLOWS PER 10 20 30 40 50 60 70 80 CLAY (CH), Fat, Very Stiff, Dark Brown to Brown, with sand

26

CLAYEY SAND (SC), Very Dense, Tan, with gravel (decomposed limestone) 50/9" 18

LIMESTONE, Chalky, Hard, Tan ref/4" 5

ref/1"

ref/0.5"

10 Boring Terminated

NOTES: 1. Groundwater not encountered during drilling operations. 2. Borehole was backfilled with auger cuttings. NOTE: THESE LOGS SHOULD NOT BE USED SEPARATELY FROM THE PROJECT REPORT

15

DEPTH DRILLED: 10.0 ft DEPTH TO WATER: Dry PROJ. No.: AAA17-091-00 DATE DRILLED: 1/10/2018 DATE MEASURED: 1/10/2018 FIGURE: 4 LOG OF BORING NO. B-4 Lake Lakewood Park Site Leander, Texas TBPE Firm Registration No. F-3257 DRILLING METHOD: Straight Flight Auger LOCATION: N 30.55841; W 97.80788 SHEAR STRENGTH, TONS/FT2

0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 DESCRIPTION OF MATERIAL

PLASTIC WATER LIQUID INDEX % -200 SYMBOL SAMPLES UNIT DRY DEPTH, FT

LIMIT CONTENT LIMIT PLASTICITY WEIGHT, pcf BLOWS PER FT BLOWS PER 10 20 30 40 50 60 70 80 CLAY (CH), Fat, Very Stiff, Dark Brown to Brown

CLAYEY SAND (SC), Very Dense, Tan 28 (decomposed limestone)

50/9.5"

LIMESTONE, Hard, Tan ref/5" 5

ref/2"

ref/1"

10 Boring Terminated

NOTES: 1. Groundwater not encountered during drilling operations. 2. Borehole was backfilled with auger cuttings. NOTE: THESE LOGS SHOULD NOT BE USED SEPARATELY FROM THE PROJECT REPORT

15

DEPTH DRILLED: 10.0 ft DEPTH TO WATER: Dry PROJ. No.: AAA17-091-00 DATE DRILLED: 1/10/2018 DATE MEASURED: 1/10/2018 FIGURE: 5 LOG OF BORING NO. PR-1 Lake Lakewood Park Site Leander, Texas TBPE Firm Registration No. F-3257 DRILLING METHOD: Straight Flight Auger LOCATION: N 30.55770; W 97.81071 SHEAR STRENGTH, TONS/FT2

0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 DESCRIPTION OF MATERIAL

PLASTIC WATER LIQUID INDEX % -200 SYMBOL SAMPLES UNIT DRY DEPTH, FT

LIMIT CONTENT LIMIT PLASTICITY WEIGHT, pcf BLOWS PER FT BLOWS PER 10 20 30 40 50 60 70 80 CLAY (CH), Fat, Very Stiff, Dark Brown

18

CLAY (CL), Lean, Sandy, Hard (decomposed limestone) 50/10" 13

LIMESTONE, Hard, Tan ref/4" 5

ref/2"

ref/1"

10

ref/1" NOTE: THESE LOGS SHOULD NOT BE USED SEPARATELY FROM THE PROJECT REPORT

15 Boring Terminated

NOTES: 1. Groundwater not encountered during drilling operations. 2. Borehole was backfilled with auger cuttings.

DEPTH DRILLED: 15.0 ft DEPTH TO WATER: Dry PROJ. No.: AAA17-091-00 DATE DRILLED: 1/10/2018 DATE MEASURED: 1/10/2018 FIGURE: 6 LOG OF BORING NO. P-1 Lake Lakewood Park Site Leander, Texas TBPE Firm Registration No. F-3257 DRILLING METHOD: Straight Flight Auger LOCATION: N 30.55956; W 97.81413 SHEAR STRENGTH, TONS/FT2

0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 DESCRIPTION OF MATERIAL

PLASTIC WATER LIQUID INDEX % -200 SYMBOL SAMPLES UNIT DRY DEPTH, FT

LIMIT CONTENT LIMIT PLASTICITY WEIGHT, pcf BLOWS PER FT BLOWS PER 10 20 30 40 50 60 70 80 CLAY (CH), Fat, Very Stiff, Dark Brown

24 53 CLAYEY SAND (SC), Very Dense, Tan (decomposed limestone)

50/10"

LIMESTONE, Hard, Tan ref/4"

5 Boring Terminated

NOTES: 1. Groundwater not encountered during drilling operations. 2. Borehole was backfilled with auger cuttings.

10 NOTE: THESE LOGS SHOULD NOT BE USED SEPARATELY FROM THE PROJECT REPORT

15

DEPTH DRILLED: 5.0 ft DEPTH TO WATER: Dry PROJ. No.: AAA17-091-00 DATE DRILLED: 1/10/2018 DATE MEASURED: 1/10/2018 FIGURE: 7 LOG OF BORING NO. P-2 Lake Lakewood Park Site Leander, Texas TBPE Firm Registration No. F-3257 DRILLING METHOD: Straight Flight Auger LOCATION: N 30.55964; W 97.81291 SHEAR STRENGTH, TONS/FT2

0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 DESCRIPTION OF MATERIAL

PLASTIC WATER LIQUID INDEX % -200 SYMBOL SAMPLES UNIT DRY DEPTH, FT

LIMIT CONTENT LIMIT PLASTICITY WEIGHT, pcf BLOWS PER FT BLOWS PER 10 20 30 40 50 60 70 80 CLAY (CH), Fat, Very Stiff, Dark Brown

26 41

CLAYEY SAND (SC), Very Dense, Tan (decomposed limestone)

50/9"

LIMESTONE, Hard, Tan ref/4"

5 Boring Terminated

NOTES: 1. Groundwater not encountered during drilling operations. 2. Borehole was backfilled with auger cuttings.

10 NOTE: THESE LOGS SHOULD NOT BE USED SEPARATELY FROM THE PROJECT REPORT

15

DEPTH DRILLED: 5.0 ft DEPTH TO WATER: Dry PROJ. No.: AAA17-091-00 DATE DRILLED: 1/10/2018 DATE MEASURED: 1/10/2018 FIGURE: 8 LOG OF BORING NO. P-3 Lake Lakewood Park Site Leander, Texas TBPE Firm Registration No. F-3257 DRILLING METHOD: Straight Flight Auger LOCATION: N 30.55930; W 97.81123 SHEAR STRENGTH, TONS/FT2

0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 DESCRIPTION OF MATERIAL

PLASTIC WATER LIQUID INDEX % -200 SYMBOL SAMPLES UNIT DRY DEPTH, FT

LIMIT CONTENT LIMIT PLASTICITY WEIGHT, pcf BLOWS PER FT BLOWS PER 10 20 30 40 50 60 70 80 CLAY (CH), Fat, Very Stiff, Dark Brown

22

CLAYEY SAND (SC), Very Dense, Tan (decomposed limestone)

50/9"

LIMESTONE, Hard, Tan ref/4"

5 Boring Terminated

NOTES: 1. Groundwater not encountered during drilling operations. 2. Borehole was backfilled with auger cuttings.

10 NOTE: THESE LOGS SHOULD NOT BE USED SEPARATELY FROM THE PROJECT REPORT

15

DEPTH DRILLED: 5.0 ft DEPTH TO WATER: Dry PROJ. No.: AAA17-091-00 DATE DRILLED: 1/10/2018 DATE MEASURED: 1/10/2018 FIGURE: 9 LOG OF BORING NO. P-4 Lake Lakewood Park Site Leander, Texas TBPE Firm Registration No. F-3257 DRILLING METHOD: Straight Flight Auger LOCATION: N 30.55918; W 97.80955 SHEAR STRENGTH, TONS/FT2

0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 DESCRIPTION OF MATERIAL

PLASTIC WATER LIQUID INDEX % -200 SYMBOL SAMPLES UNIT DRY DEPTH, FT

LIMIT CONTENT LIMIT PLASTICITY WEIGHT, pcf BLOWS PER FT BLOWS PER 10 20 30 40 50 60 70 80 CLAY (CH), Fat, Very Stiff, Dark Brown

28 50 CLAYEY SAND (SC), Very Dense, Tan (decomposed limestone)

50/9.5"

LIMESTONE, Moderately Hard, Tan 50/4.5" 5 Boring Terminated

NOTES: 1. Groundwater not encountered during drilling operations. 2. Borehole was backfilled with auger cuttings.

10 NOTE: THESE LOGS SHOULD NOT BE USED SEPARATELY FROM THE PROJECT REPORT

15

DEPTH DRILLED: 5.0 ft DEPTH TO WATER: Dry PROJ. No.: AAA17-091-00 DATE DRILLED: 1/10/2018 DATE MEASURED: 1/10/2018 FIGURE: 10 KEY TO TERMS AND SYMBOLS

MATERIAL TYPES

SOIL TERMS ROCK TERMS OTHER

CALCAREOUS CHALK LIMESTONE ASPHALT

CALICHE SAND CLAYSTONE MARL BASE

CLAY SANDY CLAY-SHALE METAMORPHIC CONCRETE/CEMENT

CLAYEY CONGLOMERATE SANDSTONE BRICKS / PAVERS

GRAVEL SILTY DOLOMITE SHALE WASTE

GRAVELLY FILL IGNEOUS SILTSTONE NO INFORMATION

WELL CONSTRUCTION AND PLUGGING MATERIALS

BENTONITE & BLANK PIPE CUTTINGS CUTTINGS SAND

SCREEN CEMENT CONCRETE/CEMENT GRAVEL VOLCLAY

SAMPLE TYPES STRENGTH TEST TYPES

POCKET PENETROMETER

AIR SHELBY TUBE ROTARY ROTARY TORVANE

GRAB NO UNCONFINED COMPRESSION SAMPLE RECOVERY SPLIT BARREL

TRIAXIAL COMPRESSION UNCONSOLIDATED-UNDRAINED CORE NX CORE SPLIT SPOON TRIAXIAL COMPRESSION CONSOLIDATED-UNDRAINED

GEOPROBE PITCHER TEXAS CONE NOTE: VALUES SYMBOLIZED ON BORING LOGS REPRESENT SHEAR SAMPLER PENETROMETER STRENGTHS UNLESS OTHERWISE NOTED

ROTOSONIC ROTOSONIC DISTURBED -DAMAGED -INTACT PROJECT NO. AAA17-091-00 REVISED 04/2012 FIGURE 11a KEY TO TERMS AND SYMBOLS (CONT'D)

TERMINOLOGY Terms used in this report to describe soils with regard to their consistency or conditions are in general accordance with the discussion presented in Article 45 of SOILS MECHANICS IN ENGINEERING PRACTICE, Terzaghi and Peck, John Wiley & Sons, Inc., 1967, using the most reliable information available from the field and laboratory investigations. Terms used for describing soils according to their texture or grain size distribution are in accordance with the UNIFIED SOIL CLASSIFICATION SYSTEM, as described in American Society for Testing and Materials D2487-06 and D2488-00, Volume 04.08, Soil and Rock; Dimension Stone; Geosynthetics; 2005.

The depths shown on the boring logs are not exact, and have been estimated to the nearest half-foot. Depth measurements may be presented in a manner that implies greater precision in depth measurement, i.e 6.71 meters. The reader should understand and interpret this information only within the stated half-foot tolerance on depth measurements. RELATIVE DENSITY COHESIVE STRENGTH PLASTICITY

Penetration Resistance Relative Resistance Plasticity Degree of Blows per ft Density Blows per ft Consistency TSF Index Plasticity

0 - 4 Very Loose 0 - 2 Very Soft 0 - 0.125 0 - 5 None 4 - 10 Loose 2 - 4 Soft 0.125 - 0.25 5 - 10 Low 10 - 30 Medium Dense 4 - 8 Firm 0.25 - 0.5 10 - 20 Moderate 30 - 50 Dense 8 - 15 Stiff 0.5 - 1.0 20 - 40 Plastic > 50 Very Dense 15 - 30 Very Stiff 1.0 - 2.0 > 40 Highly Plastic > 30 Hard > 2.0

ABBREVIATIONS

B = Benzene Qam, Qas, Qal = Quaternary Alluvium Kef = Eagle Ford Shale T = Toluene Qat = Low Deposits Kbu = Buda Limestone E = Ethylbenzene Qbc = Beaumont Formation Kdr = Del Rio Clay X = Total Xylenes Qt = Fluviatile Terrace Deposits Kft = Fort Terrett Member BTEX = Total BTEX Qao = Seymour Formation Kgt = Georgetown Formation TPH = Total Petroleum Hydrocarbons Qle = Leona Formation Kep = Person Formation ND = Not Detected Q-Tu = Uvalde Gravel Kek = Kainer Formation NA = Not Analyzed Ewi = Wilcox Formation Kes = Escondido Formation NR = Not Recorded/No Recovery Emi = Midway Group Kew = Walnut Formation OVA = Organic Vapor Analyzer Mc = Catahoula Formation Kgr = Glen Rose Formation ppm = Parts Per Million EI = Laredo Formation Kgru = Upper Glen Rose Formation Kknm = Navarro Group and Marlbrook Kgrl = Lower Glen Rose Formation Marl Kh = Hensell Sand Kpg = Pecan Gap Chalk Kau = Austin Chalk

PROJECT NO. AAA17-091-00 REVISED 04/2012 FIGURE 11b KEY TO TERMS AND SYMBOLS (CONT'D)

TERMINOLOGY

Slickensided Having planes of weakness that appear slick and glossy. Fissured Containing shrinkage or relief cracks, often filled with fine sand or silt; usually more or less vertical. Pocket Inclusion of material of different texture that is smaller than the diameter of the sample. Parting Inclusion less than 1/8 inch thick extending through the sample. Seam Inclusion 1/8 inch to 3 inches thick extending through the sample. Layer Inclusion greater than 3 inches thick extending through the sample. Laminated Soil sample composed of alternating partings or seams of different . Interlayered Soil sample composed of alternating layers of different soil type. Intermixed Soil sample composed of pockets of different soil type and layered or laminated structure is not evident. Calcareous Having appreciable quantities of carbonate. Carbonate Having more than 50% carbonate content.

SAMPLING METHODS

RELATIVELY UNDISTURBED SAMPLING Cohesive soil samples are to be collected using three-inch thin-walled tubes in general accordance with the Standard Practice for Thin-Walled Tube Sampling of Soils (ASTM D1587) and granular soil samples are to be collected using two-inch split-barrel samplers in general accordance with the Standard Method for Penetration Test and Split-Barrel Sampling of Soils (ASTM D1586). Cohesive soil samples may be extruded on-site when appropriate handling and storage techniques maintain sample integrity and moisture content. STANDARD PENETRATION TEST (SPT) A 2-in.-OD, 1-3/8-in.-ID split spoon sampler is driven 1.5 ft into undisturbed soil with a 140-pound hammer free falling 30 in. After the sampler is seated 6 in. into undisturbed soil, the number of blows required to drive the sampler the last 12 in. is the Standard Penetration Resistance or "N" value, which is recorded as blows per foot as described below.

SPLIT-BARREL SAMPLER DRIVING RECORD Blows Per Foot Description

25 25 blows drove sampler 12 inches, after initial 6 inches of seating. 50/7" 50 blows drove sampler 7 inches, after initial 6 inches of seating. Ref/3" 50 blows drove sampler 3 inches during initial 6-inch seating interval. NOTE: To avoid damage to sampling tools, driving is limited to 50 blows during or after seating interval.

PROJECT NO. AAA17-091-00 REVISED 04/2012 FIGURE 11c RESULTS OF SOIL SAMPLE ANALYSES PROJECT NAME: Lake Lakewood Park Site Leander, Texas

FILE NAME: AAA17-091-00.GPJ 2/22/2018

Sample Water Dry Unit Shear Boring Blows Liquid Plastic Plasticity % -200 Strength Depth Content USCS Weight Strength No. per ft Limit Limit Index Sieve Test (ft) (%) (pcf) (tsf) B-1 0.5 to 2.0 24 34 78 26 52 CH 2.5 to 3.9 50/11" 9 4.5 to 4.8 ref/3" 10 6.5 to 6.7 ref/2" 11 8.5 to 8.6 ref/1" 11 B-2 0.5 to 2.0 22 5 2.0 8 2.5 to 3.8 50/10" 4.0 9 4.5 to 4.8 ref/4" 6.0 9 6.5 to 6.6 ref/1" 8.5 to 8.6 ref/1" 9 B-3 0.5 to 2.0 26 28 CL 2.5 to 3.8 50/9" 19 37 19 18 4.5 to 4.8 ref/4" 10 6.5 to 6.6 ref/1" 11 8.5 to 8.6 ref/0.5" 12 B-4 0.5 to 2.0 28 9 2.5 to 3.8 50/9.5" 4 4.5 to 4.9 ref/5" 9 6.5 to 6.7 ref/2" 10 8.5 to 8.6 ref/1" 11 PR-1 0.5 to 2.0 18 28 2.5 to 3.8 50/10" 8 30 17 13 CL 4.5 to 4.8 ref/4" 9 6.5 to 6.7 ref/2" 9 8.5 to 8.6 ref/1" 9 13.5 to 13.6 ref/1" 9 P-1 0.5 to 2.0 24 12 78 25 53 CH 2.5 to 3.8 50/10" 6 4.0 to 4.3 ref/4" 8 P-2 0.5 to 2.0 26 18 60 19 41 2.5 to 3.7 50/9" 9 CH 4.0 to 4.3 ref/4" 10 P-3 0.5 to 2.0 22 11 2.5 to 3.7 50/9" 8 4.0 to 4.3 ref/4" 10 P-4 0.5 to 2.0 28 23 75 25 50 CH PP = Pocket Penetrometer TV = Torvane UC = Unconfined Compression FV = Field Vane UU = Unconsolidated Undrained Triaxial CU = Consolidated Undrained Triaxial PROJECT NO. AAA17-091-00

FIGURE 12a RESULTS OF SOIL SAMPLE ANALYSES PROJECT NAME: Lake Lakewood Park Site Leander, Texas

FILE NAME: AAA17-091-00.GPJ 2/22/2018

Sample Water Dry Unit Shear Boring Blows Liquid Plastic Plasticity % -200 Strength Depth Content USCS Weight Strength No. per ft Limit Limit Index Sieve Test (ft) (%) (pcf) (tsf) P-4 2.5 to 3.8 50/9.5" 6 4.0 to 4.8 50/4.5" 11

PP = Pocket Penetrometer TV = Torvane UC = Unconfined Compression FV = Field Vane UU = Unconsolidated Undrained Triaxial CU = Consolidated Undrained Triaxial PROJECT NO. AAA17-091-00

FIGURE 12b Important Information about This Geotechnical-Engineering Report

Subsurface problems are a principal cause of construction delays, cost overruns, claims, and disputes.

While you cannot eliminate all such risks, you can manage them. The following information is provided to help.

Geotechnical Services Are Performed for assessment of their impact. Geotechnical cannot Specific Purposes, Persons, and Projects accept responsibility or liability for problems that occur because Geotechnical engineers structure their services to meet the their reports do not consider developments of which they were specific needs of their clients. A geotechnical-engineering not informed. study conducted for a civil engineer may not fulfill the needs of a constructor­ — a construction contractor — or even another Subsurface Conditions Can Change civil engineer. Because each geotechnical- engineering study A geotechnical-engineering report is based on conditions that is unique, each geotechnical-engineering report is unique, existed at the time the geotechnical engineer performed the prepared solely for the client. No one except you should rely on study. Do not rely on a geotechnical-engineering report whose this geotechnical-engineering report without first conferring adequacy may have been affected by: the passage of time; with the geotechnical engineer who prepared it. And no one man-made events, such as construction on or adjacent to the ­— not even you — should apply this report for any purpose or site; or natural events, such as floods, droughts, , project except the one originally contemplated. or groundwater fluctuations.Contact the geotechnical engineer before applying this report to determine if it is still reliable. A Read the Full Report minor amount of additional testing or analysis could prevent Serious problems have occurred because those relying on major problems. a geotechnical-engineering report did not read it all. Do not rely on an executive summary. Do not read selected Most Geotechnical Findings Are Professional elements only. Opinions Site exploration identifies subsurface conditions only at those Geotechnical Engineers Base Each Report on points where subsurface tests are conducted or samples are a Unique Set of Project-Specific Factors taken. Geotechnical engineers review field and laboratory Geotechnical engineers consider many unique, project-specific data and then apply their professional judgment to render factors when establishing the scope of a study. Typical factors an opinion about subsurface conditions throughout the include: the client’s goals, objectives, and risk-management site. Actual subsurface conditions may differ — sometimes preferences; the general nature of the structure involved, its significantly — from those indicated in your report. Retaining size, and configuration; the location of the structure on the the geotechnical engineer who developed your report to site; and other planned or existing site improvements, such as provide geotechnical-construction observation is the most access roads, parking lots, and underground utilities. Unless effective method of managing the risks associated with the geotechnical engineer who conducted the study specifically unanticipated conditions. indicates otherwise, do not rely on a geotechnical-engineering report that was: A Report’s Recommendations Are Not Final • not prepared for you; Do not overrely on the confirmation-dependent • not prepared for your project; recommendations included in your report. Confirmation- • not prepared for the specific site explored; or dependent recommendations are not final, because • completed before important project changes were made. geotechnical engineers develop them principally from judgment and opinion. Geotechnical engineers can finalize Typical changes that can erode the reliability of an existing their recommendations only by observing actual subsurface geotechnical-engineering report include those that affect: conditions revealed during construction. The geotechnical • the function of the proposed structure, as when it’s changed engineer who developed your report cannot assume from a parking garage to an office building, or from a light- responsibility or liability for the report’s confirmation-dependent industrial plant to a refrigerated warehouse; recommendations if that engineer does not perform the • the elevation, configuration, location, orientation, or weight geotechnical-construction observation required to confirm the of the proposed structure; recommendations’ applicability. • the composition of the design team; or • project ownership. A Geotechnical-Engineering Report Is Subject to Misinterpretation As a general rule, always inform your geotechnical engineer Other design-team members’ misinterpretation of of project changes—even minor ones—and request an geotechnical-engineering reports has resulted in costly problems. Confront that risk by having your geo­technical others recognize their own responsibilities and risks. Read engineer confer with appropriate members of the design team these provisions closely. Ask questions. Your geotechnical after submitting the report. Also retain your geotechnical engineer should respond fully and frankly. engineer to review pertinent elements of the design team’s plans and specifications. Constructors can also misinterpret Environmental Concerns Are Not Covered a geotechnical-engineering report. Confront that risk by The equipment, techniques, and personnel used to perform having your geotechnical engineer participate in prebid and an environmental study differ significantly from those used to preconstruction conferences, and by providing geotechnical perform a geotechnical study. For that reason, a geotechnical- construction observation. engineering report does not usually relate any environmental findings, conclusions, or recommendations; e.g., about Do Not Redraw the Engineer’s Logs the likelihood of encountering underground storage tanks Geotechnical engineers prepare final boring and testing logs or regulated contaminants. Unanticipated environmental based upon their interpretation of field logs and laboratory problems have led to numerous project failures. If you have not data. To prevent errors or omissions, the logs included in a yet obtained your own environmental information, geotechnical-engineering report should never be redrawn ask your geotechnical consultant for risk-management for inclusion in architectural or other design drawings. Only guidance. Do not rely on an environmental report prepared for photographic or electronic reproduction is acceptable, but someone else. recognize that separating logs from the report can elevate risk. Obtain Professional Assistance To Deal Give Constructors a Complete Report and with Mold Guidance Diverse strategies can be applied during building design, Some owners and design professionals mistakenly believe they construction, operation, and maintenance to prevent can make constructors liable for unanticipated subsurface significant amounts of mold from growing on indoor surfaces. conditions by limiting what they provide for bid preparation. To be effective, all such strategies should be devised for To help prevent costly problems, give constructors the the express purpose of mold prevention, integrated into a complete geotechnical-engineering report, but preface it with comprehensive plan, and executed with diligent oversight by a a clearly written letter of transmittal. In that letter, advise professional mold-prevention consultant. Because just a small constructors that the report was not prepared for purposes amount of water or moisture can lead to the development of of bid development and that the report’s accuracy is limited; severe mold infestations, many mold- prevention strategies encourage them to confer with the geotechnical engineer focus on keeping building surfaces dry. While groundwater, who prepared the report (a modest fee may be required) and/ water infiltration, and similar issues may have been addressed or to conduct additional study to obtain the specific types of as part of the geotechnical- engineering study whose findings information they need or prefer. A prebid conference can also are conveyed in this report, the geotechnical engineer in be valuable. Be sure constructors have sufficient time to perform charge of this project is not a mold prevention consultant; additional study. Only then might you be in a position to none of the services performed in connection with the give constructors the best information available to you, geotechnical engineer’s study were designed or conducted for while requiring them to at least share some of the financial the purpose of mold prevention. Proper implementation of the responsibilities stemming from unanticipated conditions. recommendations conveyed in this report will not of itself be sufficient to prevent mold from growing in or on the structure Read Responsibility Provisions Closely involved. Some clients, design professionals, and constructors fail to recognize that geotechnical engineering is far less exact than Rely, on Your GBC-Member Geotechnical Engineer other engineering disciplines. This lack of understanding for Additional Assistance has created unrealistic expectations that have led to Membership in the Geotechnical Business Council of the disappointments, claims, and disputes. To help reduce the risk Geoprofessional Business Association exposes geotechnical of such outcomes, geotechnical engineers commonly include engineers to a wide array of risk-confrontation techniques a variety of explanatory provisions in their reports. Sometimes that can be of genuine benefit for everyone involved with labeled “limitations,” many of these provisions indicate where a construction project. Confer with you GBC-Member geotechnical engineers’ responsibilities begin and end, to help geotechnical engineer for more information.

8811 Colesville Road/Suite G106, Silver Spring, MD 20910 Telephone: 301/565-2733 Facsimile: 301/589-2017 e-mail: [email protected] www.geoprofessional.org

Copyright 2015 by Geoprofessional Business Association (GBA). Duplication, reproduction, or copying of this document, or its contents, in whole or in part, by any means whatsoever, is strictly prohibited, except with GBA’s specific written permission. Excerpting, quoting, or otherwise extracting wording from this document is permitted only with the express written permission of GBA, and only for purposes of scholarly research or book review. Only members of GBA may use this document as a complement to or as an element of a geotechnical-engineering report. Any other firm, individual, or other entity that so uses this document without being a GBA member could be commiting negligent or intentional (fraudulent) misrepresentation. ENGINEERING • ENVIRONMENTAL • INFRASTRUCTURE • PROJECT CONTROL

Austin, TX San Antonio, TX Lake Worth, FL

Brownsville, TX Houston, TX Lincoln, NE

Dallas, TX McAllen, TX Salt Lake City, UT

Freeport, TX New Braunfels, TX Mexico

RABA KISTNER