Initial Environmental Examination

Document Stage: Final Project Number: 38254

December 2009

India: North Urban Sector Investment Program (Tranche 2)—Gangavathi CMC

Prepared by Karnataka Urban Infrastructure Development Finance Corporation

For the Government of Karnataka North Karnataka Urban Sector Investment Program

The initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Karnataka Urban Infrastructure Development and Finance Corporation, Government of Karnataka

North Karnataka Urban Sector Investment Program

Package IV - Bellary

Tranche II Sub-Projects in Gangavathi CMC

Initial Environmental Examination (IEE)

December 2009

Span Consultants Pvt. Ltd

Association with

Voyants Solutions Pvt. Ltd

(formerly M/s. Ramky Infra Consulting Pvt. Ltd).

NKUSIP (Package IV – Bellary) Tranche II Sub Projects in GangavathiTown

Currency Equivalent

Currency Unit - Indian Rupee/s Re. 1.00 = US$ 0.022 US$ 1.00 = Rs. 45

Abbreviations

ADB : Asian Development Bank ASP : Activated Sludge Process BM : Bituminous Macadam DoEEF : Department of Ecology, Environment EIA : Environmental Impact Assessment EMP : Environmental Management Plan EP Act : Environment (Protection) Act, 1986 GoI : Government of GoK : Government of Karnataka GSB : Granular Sub-base IEE : Initial Environmental Examination KSPCB : Karnataka State Pollution Control Board MLD : Million Litre per Day MoEF : Ministry of Environment and Forests MSL : Mean Sea Level MSS : Mix Seal Surface NKUSIP : North Karnataka Urban Sector Project NOC : No Objection Certificate NOx : Oxides of Nitrogen OM : Operations Manual PCC : Profile Concrete Course PWD : Public Works Department SOx : Oxides of Sulphur STP : Sewage Treatment Plant RSPM : Respirable Suspended Particulate Matter TSPM : Total Suspended Particulate Matter WMM : Wet Mix Macadam WRDO : Water Resource Development Organization

KUIDFC 3 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

CONTENTS

CHAPTER –I: INTRDUCTION

1.1 Overview 6 1.2 Environmental Regulatory Compliance 6 1.3 Purpose of Initial Environmental Examination 8 1.4 Scope pf IEE 8 1.5 Report Structure 8

CHAPTER – II: DISCRIPTION OF THE INVESTMENT PROGRAM COMPONENTS

2.1 NKUSIP Goal 9 2.2 Project Location 10 2.3 Need for Infrastructure improvement IN Gangavathi 13 2.3.1 Karnataka- Health Status 13 2.3.2 Drainage System 14 2.3.3 Need of project 18 2.3.4Slum Improvement 19

2.3.5 Infrastructure in Slum 25 2.3.6 Need of project 29 2.3.7 Proposed Drain 32 2.3.8Slum Improvement 35 2.4 Investment Program Implementation Schedule 42 2.5 Investment Program Benefits 42 2.6 Investment program Alternatives 43

CHAPTER – III DISCRIPTION OF THE ENVIRONMENT 3.1 Environnent profile of Gangavathi 45 3.1.1 Introduction 45 3.1.2 Physiography 45 3.1.3 Seismology 45 3.1.4 Climate condition 45 3.1.5 Surface Water 45 3.1.6 Air quality 46 3.1.7 Socio economic Characteristics 46 3.1.8 Household Size and Sex Ration 47 3.1.9 Literacy 47 3.2 Environment setting of Investment Program Component sites 47 3.2.1 Urban Drainage Up gradation 48 3.2.2 Slum Up gradation 48

CHAPTER – IV: SCREENING OF POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURE 48

KUIDFC 4 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

CHAPTER – V: INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL MONITORING PLAN

5.1. Institutional Requirements 70 5.2 Institutional strengthening 71 5.2.1 Organisation & Staffing 71 5.2.2 Monitoring & Reporting Procedure 72 5.2.3 Record keeping 72 5.3 Environmental Monitoring Program 72 5.3.1 Rehabilitation & Resettlement Program 73 5.3.2 Afforestation 73 5.3.3 Soil conservation 73 5.3.4 Borrow area conservation 73 5.3 Training Needs 75 5.4 Environmental Monitoring Plans 76

CHAPTER – VI: PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

6.1. Overview 83

CHAPTER – VII Finding and Recommendation 7.1. Findings 86 7.2. Recommendations 86

CHAPTER – VIII: CONCLUSIONS 88

KUIDFC 5 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

TABLES

Table: 1 Water Borne / Related Diseases in Karnataka Table: 2 Existing Drainage System in Gangavathi Table: 3 Slums In Gangavathi Table: 4 Percentage distribution of SlumHoseholds by access to various services Table: 5 Existing details of road and drain Table 6 Investment Program Alternatives Table: 7 Percentage Distribution of Slum Households by access to basic services Table: 8 Screening Of Impacts Table: 9 Environmental Impacts & Mitigation Measures of water supply system Table 10: Environ mental Impacts & Mitigation Measures of sewerage and sanitation work Table: 11 Environmental Impacts & Mitigation Measures of road up gradation Table: 12 Environmental Impacts & Mitigation Measures of drainage up gradation Table: 13 Institutional Roles & Responsibilities Table: 14 Training Needs Table: 15 Environmental Monitoring Plan for water supply rehabilitation Table: 16 Environmental Monitoring Plan for drainage Up gradation Table: 17 Environmental Monitoring Plan for road up gradation Table: 18 Sample estimated environmental cost Table: 19 Public Comments & Mitigation Measures Table 20 environmental Issues of Proposed Infrastructure Components.

MAPS Map: 1 location Map of Gangavathi Town Fig: 1 Photos of Existing Condition of Drain in Gangavathi Fig: 2 Photos of Public Consultation.

KUIDFC 6 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

CHAPTER - I

INTRODUCTION 1.1. Overview

1. The North Karnataka Urban Sector Investment Program (NKUSIP) proposes to improve the environmental quality of the urban areas through better urban infrastructure facilities and thus improve living conditions of the urban people. In the wake of poor infrastructure facilities and services such as water supply, sewerage and sanitation and solid waste management, the risk of infectious diseases through exposure to unhealthy environment runs high, particularly in the case of urban poor. Hence, the proposed Investment Program aims at minimizing or mitigating the risk and ensures the well-being of people.

2 . Though the Investment Program aims to improve the environmental condition of urban areas, the proposed improvements of infrastructure facilities may exert certain adverse impacts on the natural environment. While developing urban infrastructure facilities, impacts during the construction stage are expected to be more severe than impacts during the operation phase, though for a short duration. Exceptions being some facilities such as solid waste landfill, sewage treatment plant, which may also exert adverse impacts during the operation phase also, if due care is not taken. Again, most of the impacts are activity- specific. However, if due care is taken during the construction phase, investment Program negative impacts will be far outweighed by positive impacts

1.2 Environmental Regulatory Compliance

3 The components of NKUSIP includes Urban drains and slum improvement works infrastructure such as water supply, sewerage and sanitation, solid waste management and road. Sub-components, which fall under the ambit of environmental regulations and mandatory requirement, are indicated in the following Table

KUIDFC 7 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

Table 1.1 : Environmental Regulatory Compliance of NKUSIP Components

Sub- Applicability of Compliance Criteria Component Acts/Guidelines

All sub- The Environment Policy and • Categorization of sub-project components Operations Manual (OM) 20: components into A, B or C and Environmental Assessment developing required level of Guidelines 2003 environmental assessment for Environmental Considerations in each component ADB Operation

4 The above table indicates that as far as GoI and GoK Acts/Guidelines are concerned, the proposed Investment Programs do not need to go through environmental assessment process;. The ADB guidelines, on the other hand, stipulate addressing environmental concerns, if any, of a proposed activity in the initial stages of Investment Program preparation. For this, the ADB Guidelines categorizes the proposed components into varies categories (A, B or C) to determine the level of environmental assessment required to address the potential impacts. Level of environmental assessment required for each category of Investment Program, as per ADB’s Environmental Assessment Guidelines 2003 is presented below.

(i) Category A. Sub-project components with potential for significant adverse environmental impacts. An environmental impact assessment (EIA) is required to address significant impacts.

(ii) Category B. Sub-project components judged to have some adverse environmental impacts, but of lesser degree and/or significance than those for Category A projects. An initial environmental examination (IEE) is required to determine whether significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report.

(iii) Category C. Sub-components unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are still reviewed.

KUIDFC 8 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

1.3 Purpose of Initial Environmental Examination

5 The NKUIDFC Package IV – Bellary covers 25 sub-project towns. To fulfil the ADB’s environmental assessment requirement for sector loans, the environmental assessment of sample sub-project was carried out. Owing to the scale and nature of the proposed infrastructure components and environmental profile of the NKUSIP area in general and the sample sub-project towns in particular, prima facie almost all Investment Program components are unlikely to have adverse environmental impacts.

6 Therefore, as per the ADB’s Environmental Assessment Guidelines, the sub-project components proposed in Gangavathi under NKUSIP are categorized as ‘B’ and an initial environmental examination (IEE) have been carried out.

1.4 Scope of IEE

7 The IEE was based mainly on secondary sources of information and field reconnaissance surveys; no field monitoring (environmental) survey was conducted. Stakeholder consultation was an integral part of the IEE.

1.5 Report Structure

1 This Report is framed with 8 Sections including this Introduction Chapter: 1. Introduction 2. Project Description 3. Environmental Description 4. Screening of Environmental Impacts and Mitigation Measures 5. Institutional requirements and Environmental Monitoring Plans 6. Public consultation and Information Disclosure 7. Findings and Recommendations 8. Conclusions

KUIDFC 9 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

CHAPTER – II

DESCRIPTION OF THE INVESTMENT PROGRAM COMPONENTS

2.1 NKUSIP Investment Program Goal

8 The North Karnataka Urban Sector Investment Program (NKUSIP) will finance investment for (i) Environmental Sanitation Infrastructure; (ii) Water supply Infrastructure; (iii) Urban Roads Improvement; (iv) Poverty Alleviation; (v) Non- Municipal Infrastructure; (vi) Institutional Development; and (vii) Investment Program Assistance. The overall development goal of the NKUSIP is to facilitate economic growth in the towns of North Karnataka and bring about urban development through equitable distribution of urban basic services to the citizens that are environmentally sound and operationally sustainable. The development purpose is designed to assist Urban Local Bodies (ULBs) to “promote good urban management, and develop and expand urban infrastructure to increase economic opportunities and to reduce vulnerability to environmental degradation and urban poverty”.

9 Thus the Investment Program goal is to facilitate economic growth in the towns/cities of North Karnataka and bring about urban development though equitable distribution of urban basic services to the citizens that is environmentally sound and operationally sustainable. The following are the urban infrastructure components proposed under the NKUSIP.

(i) Urban Drainage; and (ii) Poverty Alleviation; and,

2.2 Project location

10 GANGAVATHI, the second largest urban centre in District is located at a distance of 360 km northwest from the State Capital Bangalore and 45 km from Koppal. The town is the Taluk Headquarters of the Gangavathi Taluk in . The City Municipal Council jurisdiction extends up to an area of 16.53 Sq.km with 31 wards. The Gangavathi is the centre for development activities in agricultural sector and rightly called as the “Rice Bowl of Karnataka”. It is an important commercial and marketing centre well known for trade in paddy, jaggery, jowar and other food grains.

KUIDFC 10 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

11 The town is located on a gentle ground slope towards the south. Durgamma nalla runs across the town from southwest to southeast there by dividing the town into two parts. A hillock abuts the town on the west and stretches for considerable length along its border. The highest plane of town is at + 398.17 m above MSL and the lowest part of the town is at + 381.09 m above MSL. : The surface stratum is composed of murrum soil mixed with granite boulder out cropping at several places. The town comes under Central Karnataka Plateau, with the region representing the transitional surface between Deccan trap and relatively higher surface. Largely, this region represents the Tungabhadra River basin. The location map of the Gangavathi is presented in Maps 2.1 & 2.2.

KUIDFC 11 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

Maps 2.1 : Aerial view of Gangavathi Town

KUIDFC 12 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report Index Map – ULBS Package – IV, Bellary

List of ULBs

 Bellary  Hospet  Raichur  Sindanur  Koppal  Gangavathi  Chamarajnagar

KUIDFC 13 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

2.3 Need for Infrastructure Improvement in Area Gangavathi, the second largest town and taluk headquarters of Koppal District is one of the twenty-five towns being considered under the North Karnataka Urban Sector Improvement Programme (NKUSIP) with loan assistance from Asian Development Bank (ADB). The programme envisages the development of urban infrastructures in the selected towns. The main emphasis is on water supply, urban sanitation (sewerage, solid waste disposal and storm water disposal) and poverty alleviation in addition to urban roads and non municipal components like fire services, tourism information centers and lake development. In Gangavathi, the two main components of water supply and sewerage have been taken up by the line departments, while the urban drains and slum improvements are being taken up under NKUSIP. Hence while the urban infrastructure improvements to the town are being taken up in general it is necessary to provide more emphasis in the improvements of the slums in order to have a comprehensive development of the town. Hence, the formulation of specific projects for the slums. The project will improve the environmental services in the slums by providing water supply, sewerage, drainage, pavements and street lighting facilities. In addition public conveniences facilities will be provided where very much needed.

2.4 Karnataka – Health Status Lack of safe and adequate water supply and sanitation facilities leads unhealthy environment which results in the risk of infectious diseases particularly in urban areas. Report which was generated by The State of Environment Report (SOER), 2003, Karnataka, brings out the fact that the lack of safe water supply and sanitation facilities is essentially leading to the health related consequences. The following are important observations of the report.

Table 2.1: Water borne/related Diseases in Karnataka Yea Gastroe C Leptos Viral Typhoid 199 1 6 7 1 - - 61 - - 199 1 6 4 1 - - 21 - - 199 1 8 4 1 - - 6 7 26 1 199 1 3 3 1 - - 3 0 20 0 199 1 3 5 3 - - 7 1 10 0 199 2 3 6 6 - - 1 6 22 1

KUIDFC 14 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report 199 2 3 7 1 6 2 1 4 3 5 199 2 5 4 2 1 0 3 2 2 0 199 1 1 1 3 5 2 4 2 24 1 200 3 2 3 3 3 1 3127 0 200 2 1 3 1 6 7 5233 6 200 2 1 3 0 2 0 4142 2 Source: SOER 2003

Hence, it is evident that the lack of safe water supply and sanitation facilities in the State adversely affects health condition of the Population. The following section details the status of water supply, sanitation and other basic infrastructure facilities in Gangavathi.

(i.)Urban Drainage (ii.) Slum Improvement

Table 2.2: Sub projects components under Tranche – II

SI. No. Infrastructure Description Location Components to be built under Tranche II 1 Urban Drainage Construction of Main drain, street Gangavathi CMC drain including culverts. 2 Slums Improvements in water supply GangavathiCMC line, Sewerage system, Roads, Drains, etc.

2.5 Drainage System

EXISTING DRAINAGE SYSTEM:

12 The drainage system in Gangavathi town consists of a single major nallah, Durgamma nallah which runs from North West to South East direction, and network of secondary and tertiary drains built around this main channel. Length of the primary drain channel is 4.0 Km in the CMC limits and the width of the nallah is 20-30 m variation in different places, while the length of secondary and tertiary drains is 110 Km. the salient features of gangavathi CMC with respect to existing drain are presented in Table 2.3.

KUIDFC 15 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report Table: 2.3 Existing drainage system in gangavathi

A Total Area of Gangavathi City 16.53sq km

Total population as on 2001 93249

Total House hold 31263

Drain area covered of road length 47% of the town

Length of Drainage Network including all 110.00 Km types

Condition of the Existing Sewerage Poor system

Type of Drainage System Primary ,Secondary & Tertiary

Primary drain (Durgamma nala) 4 kms

Total length of drain of various 114 KM categories

Source : DPR ( detail project report)

A) PRIMARY DRAINS:

15. There is a single principal natural drain, which flow through the town, the Durgamma Nala flows from North West to South East direction of the town and eventually joins the Tungabhadra River. It is a natural stream, irregular in shape, full of vegetation and trees, and with average width varying from 20 to 30m. It carries the rain water and also wastewater, which is used by the farmers for agricultural purpose.

B) SECONDARY DRAINS: The following drains have been identified by the CMC of Gangavathi for the improvement under this project.

Table 2.4: Details of existing sewerage drain

Sl. No Name of Work A CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM BANNIKATTI CAMP TO DURGAMMA NALA OF DRAIN NO -1 OF SIZE (0.5MX 1.0M )OF LENGTH 13OM B CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM ERANNA GUDDA TO CANAL ON DRAIN NO -2A OF SIZE (3.0M X 1.0M) OF LENGTH 24OM

KUIDFC 16 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report Sl. No Name of Work C CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM ERANNA GUDDA TO CANAL ON DRAIN NO -2B OF SIZE (2.0MX 1.0M) OF LENGTH 140M

D CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM ERANNA GUDDA TO CANAL ON DRAIN NO -2C OF SIZE (1.0MX 1.0M) OF LENGTH 2OOM

E CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM KANAKADAS CIRCLE TO LBS NAGAR OF DRIAN NO 3 SIZE (2.5MX1.5M) OF LENGTH 570M

F CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM KANAKADAS CIRCLE TO CHILDREN PARK OF DRAIN NO 3A OF SIZE (1.5MX1.5M) OF LENGTH 670M

G CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM VALMIKI CIRCLE TO CHILDREN PARK OF DRAIN NO 3B of size (1.25Mx1.5M)OF LENGTH 850M

H CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM RAMAPURA DRAIN NO -3C OF SIZE (4.00 X 1.25)MTS OF LENGTH 26OM

I CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM KILLA AREA TO DURGAMMA NALA NO -4 OF SIZE (1.0M X 1.0M) OF LENGTH 3OOM

J CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM APMC TO DURGAMMA NALA NO -5 OF SIZE (4.00 X 1.25)MTS OF LENGTH 31OM

K CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM APMC TO DURGAMMA NALA NO -5A OF SIZE (4.00 X 1.25)MTS.OF LENGTH 750M

L CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM APMC TO DURGAMMA NALA NO -5B OF SIZE (4.00 X 1.25)MTS.OF LENGTH 500M

M CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM MARUTHINAGAR TO DURGAMMA NALA NO -6 OF SIZE (4.00 X 1.25)MTS.OF LENGTH 860M

N CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM MARUTHINAGAR TO DURGAMMA NALA NO -6A OF SIZE (4.00 X 1.25)MTS.OF LENGTH 300M

O CONSTRUCTION OF SIDE WALL OF SECONDARY STORM WATER DRAIN NO 6B OF LENGTH 270 MTS

P CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM L B S NAGAR TO CANAL NO -7 OF SIZE 1.5 X 1.25MTS. OF LENGTH 195M

Q CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM LAKSHMI CAMP TO LBS NAGAR NO -7A OF SIZE 1.0 X 1.0MTS.OF LENGTH 360M

R CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM RELIANCE PETROL BANK TO DURGAMMA NALA ON DRAIN NO-8 OF SIZE (1.50MX1.25M) OF LENGTH 5OOM

KUIDFC 17 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report Sl. No Name of Work S CONSTRUCTION OF SECONDARY STORM WATER DRAIN FROM RELIANCE PETROL BANK TO DURGAMMA NALA ON DRAIN NO-8A OF SIZE (1.00MX1.25M) OF LENGTH 82OM

The total length of the drain to be improved is 9.00km

 Bannikatti camp: This drain flows towards Durgamma nala located on the centre part of the town near Bamboo bazaar. Covered areas are Bannikatti camp area, some part of APMC yard and market area.

 Eranna Gudda to canal: This drain flows in northwest to east direction and is located on the southern part of the town. Covered areas of town are hillock area, some part of Virpapur area, Basavanna temple area and Yellamma katti extension area.

 Valmiki circle to kanakdas circle: This drain flows in northwest to east direction and is located in the central part of the town. Covered areas of town are hillock area, Jayanagar, Basavaswara bad wane, Kuvempu nagar, Market, Bus stand, Police quarters, and Bus Depot area. Replacement of existing drain with bigger size to increase the capacity of the drain to avoid the flood during rainy season.

 Killa Area to Durgamma nallah: This drain flows in north to south direction and reaches Durgamma nallah and is located in the most densely populated area of the town. Covered areas of the town are slum area Killa Area slum, Gandhi circle, Commercial area near HMS theatre, Pinjar oni.

 Taluk stadium to Durgamma nallah: This drain flows in north to south direction reaches Durgamma nallah and is located in the Commercial area and densely populated area of the town. Covered areas of the town are APMC, Vegetable Market, thickly populated slum areas. This drain is loaded not only with the sewage water but also with solid waste like vegetable waste, plastic paper etc dumped inside the nallah,

 Maruthinagar to Durgamma nallah: This drain flows in northwest to south direction reaches Durgamma nallah and is located on the northern side of the town. Covered area of Maruthinagar, Marutheswaranagar, Lingaraj camp, Vinayakanagar, Manjuvara camp.

KUIDFC 18 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

 Lakshmi camp to Krishnadevaraya canal: This drain flows in north – south direction and reaches Krishnadevaraya canal and is located on the Eastern side of the town. Covered areas are Lakshmi camp, Gowri nagar, Jia Bheemanagar, Chalavadi oni L B S nagar.

C) TERTIARY DRAINS:

15. The roadside drains are provided on both sides of the roads. Most of the built up drains are rectangular in shape and are constructed in stone masonry with concrete at the bottom. The katcha drains are in the form of excavated shallow trenches, with no protection to the sides and are prone to damage by the traffic

16. Drains serve the dual purpose of carrying storm water in rainy season and waste water in other seasons. It is, therefore, necessary to provide drains on both sides of the roads. The total length of the roads in the town is 234.00 kms. Actual length of built up drains is 110 km. Thus, covers a mere 47 percent of the roads. The coverage thus appears extremely poor. Most of the road network appears yet to be covered either by pucca drains or katcha drains.

2.3.3 Need of the project

17. Killa Area slum, Lakshmi camp, LBS nagar, Chalavadi oni, Jia Bheemanagar, Manjuvara camp and pinjar oni get flooded in heavy rainy season. Areas near M G circle, M G road and road also are affected. A drain network is required to carry the flood water in this area.

18. The field inspection reveals that the most of the drains are choked up due to dumping of garbage and debris in secondary and tertiary drains. Practically the above drains are used by households as a dumping yard. In addition due to long neglect of O&M operation of the system most of the drains are in choked condition. In particular during rainy season the drains overflow onto the surface of roads. Also the sullage water flowing in surrounding area cause pollution. In addition on account of damaged drains in the surrounding area, the ground water is also polluted due to seepage of sullage and sewerage from the above drains. In spite of fair slope due to illicit dumping of solid waste and neglect of O&M operation the whole system has practically collapsed. It is of prime importance that there is an urgent need for strengthening the drain system, particularly in the low lying areas. Also most of the roads are damaged on account of the over flow of storm water drain.

Inadequate coverage of drain: Only 47 percent of the roads appear to have been covered / served by built up drains. Secondary Drain Links: many low lying areas in the town get flooded as they cannot be effectively drained for want of proper drain network and proper outlets in the form of Secondary drains connecting to the primary channels.

Unhygienic Condition: There is an existing sewerage system in the town but most of the sewer lines are choked due to dumping of solid waste. Most of the area still dependent on the road side drains for carriage of waste water. In the absence of well constructed drains in many areas, waste water flows along the streets and accumulates in low lying areas. Still trunk sewer works not complete hence raw sewage water allow into storm water drains. Use of the

KUIDFC 19 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report open channels for dumping the garbage and debris affects the draining capacity of these channels. The open cess pools formed in the low lying areas pose a serious threat to the health of the citizen, besides polluting the ground water and presenting very ugly sights.

Durgamma nallah is the only main natural drain now passing through the city. The entire drain network is at present working as feeders to this nallah which leads the excess waters to the river. There had been a very old system of drain network (Krishnadevaraya canal) which was to work as an irrigation canal to the fields on both its banks and as a storm water canal during floods/rains. During non-rainy period it was fed from the river. The excess water during rainy season, excess water let into Durgamma Nala. This system has been neglected and at present has been turned into a drain leading the waste water to Durgamma nallah. It is also used for irrigation purpose. It has been proposed to improve the secondary drains now leading to the Durgamma nala so as to improve the drainage of the side drains and thus provide a solution to the flooding problem.

 STORM WATER DRAINAGE NETWORK:

For many of the low lying areas in the city there are no proper outlets or secondary drains connecting them to the primary channels. The drains are blocked due to debris and waste and are not effective. Entire city is still dependent on the roadside drains for carriage of wastewater. In the absence of well constructed drains in many areas, waste water flows along the streets and accumulates in low lying areas. Use of the open channels for dumping the garbage and plastic bags affects the draining capacity of these channels. The open cess pools formed in the low lying areas pose a serious threat to the health of the citizen, besides polluting the ground water In the absence of a sewerage system and inadequate sanitation facilities, a large amount of the domestic sewage is let into storm water drains. This is resulting in pollution of the public water bodies such as river, as the waste runoff leads to these watercourses.

2.6 Slum Improvement

The study of slums in Gangavathi is made to assess the extent of their access to basic services. It includes identification of the level of services in slums, opportunity cost incurred by households, mechanisms to overcome the shortfall in service and affordability and determination /willingness to pay for improved services. The study was made to assess the socio-economic profile, access to basic services and identification of the priority for providing for basic services. In Gangavathi there are 26 declared slums and 1 undeclared slum. The total population in declared slums is 34,658 and 468 (2001) in the undeclared slum, accounting for about 37.37 % of the total population. Details of declared and undeclared

KUIDFC 20 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report slums along with the area and resident population are given in the table below:

Table 2.4: Slums in Gangavathi

Sl No. of Area in Name of Slum Population No Households acres

A Declared

1 Angadi Veeranna camp 393 6.32 2152

2 Erannagudda camp 164 2.83 936

3 H R S camp 177 2.31 895

4 Gajananna sawmill 372 4 1836

5 Annur Gowramma camp 154 4.28 954

6 Gallamma camp 74 1.39 474

7 Old Trench near Killa 174 8.29 895

8 Rampurpet 48 0.14 288

9 Basaveswara camp 74 2.09 252

Near Neelakanteshwara 10 2.28 582 Temple 97

11 Veerapura Waddar Oni 94 3.25 234

12 Gundamma camp 600 22.17 4460

13 Indiranagar 182 1.3 1044

Near housing board 14 30.03 2015 colony 250

15 Mehboobnagar 450 5.24 2352

KUIDFC 21 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report 16 Lambani Thanda 480 8 2632

17 Bhagatsingh Nagar 275 6.12 1670

18 Chelluvadiwada 480 9 2800

19 Ambedkar colony 258 9.2 2200

Basheer Ahmed 20 1.17 749 compound 145

21 Majawardiggi 127 5 529

22 Uppinamali camp 122 1.16 555

23 Herur Kishan Rao 140 1.29 690

24 Lakshmi camp 264 4.25 1326

25 Lingaraj camp 346 6 1730

26 New weekly market 99 1.22 408

Total 6039 148.33 34,658

B Undeclared

1 Siddikere 468

I) Socio-Economic Profile of the town slums

Poverty alleviation efforts through special plans, programs and policy measures by the Government of India have been initiated since 1970s. It has been promoted as one of the most important goals of the Government throughout the last three decades. The Government of Karnataka to initiated since then, a program for alleviation of poverty in both urban and rural areas.

In the context of environmental conditions of the informal and formal low-income settlements,

KUIDFC 22 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report NKUSIP proposes to improve the environmental services in these settlements by providing water supply, sewerage, drainage, roads and pavements. The Project will provide for public conveniences catering to the environmental sanitation needs of dwellers. This component will also include a social sub-component, which shall provide for activities that will be dovetailed along with centrally sponsored schemes for poverty alleviation. This component will be addressed through the Karnataka Slum Clearance Board (KSCB), a State Line Department.

27. The phenomenal growth of Urban Karnataka has lead to mushrooming of slums in and around the urban areas. The vulnerable places for slum development are mostly environmentally fragile areas namely marshy and swampy areas, low lying areas, vacant government lands, and its agencies, lands under high tension lines etc. The inhabitants of these slums are basically the urban poor, who are a legitimate part of the town. They contribute to its growth and deserve a share of the benefits of that growth. In Karnataka there are 2603 slums, out of which Bangalore alone accounts for 543, with Gangavathi having 26 declared slums. The improvements proposed in this scheme are in areas which are declared as slums by Karnataka Slum Clearance Board. These slums are located within a radius of 2.5 kms of Gangavathi Town. These slum dwellers are residing in these slums for the past 20 -25 years. Percentage Distribution of slum households to access to basic service is presented in Table 2.5.

Table 2.5. Percentage Distribution of Slum households by access to basic services

Service Description Access to Households

HSC 22

Stand post 43 Water Supply Open well/ Bore well 9

Stand post + open well/ 26 bore well

Public Convenience 9 Sanitation None 91

Solid Dustbins available 8

KUIDFC 23 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report waste Dustbins not present 92 disposal

R.C.C 4

Housing Tiled pucca - Type Tiles katcha 30

Thatched 66

The physical environment in terms of housing conditions, availability of basic services etc determines the productivity and consequently the quality of life in urban areas. Majority of the people living in slums do suffer from deprivation especially in basic services and amenities.

II) Household size and sex ratio: Survey of the Gangavathi town slums indicated an average household size of 5.3 in slums; with a standard deviation of 0.70. For the sample household this is higher than the KSCB figure for average slum household size of 4.32 in Gangavathi. Only 4 percent of the surveyed households were recorded as woman headed households while 48 percent of the households were recorded belong to SC/ST community. The average sex ratio for sample households is 877 females per 1000 males in Gangavathi slums, with a standard deviation of 70.06, showing some variation among sample households. The sample average is lower than the 2001 Census figure of 976, for the town as a whole.

III) Literacy: Literacy levels in Gangavathi slums are low, with 30 percent female literacy among the sample slum population, which is very much lower than the male literacy at 58 percent. The survey indicates a total literacy of 45 percent, which is very much below the 2001 Census figure of 67 percent for Gangavathi town as whole.

IV) Penetration of house holds service connection by income level; Primary data suggests that individual connectivity is related to the income level (Chart 2.8), where more number of households in income category Rs. 1,500 – 2,500 is connected to HSC.

KUIDFC 24 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

V) Housing. Housing condition in Gangavathi slums were found very poor. Large proportions (96 percent) of households were found staying in katcha houses (30 percent in tiled katcha and 66 percent in thatched houses). Remaining 4 percent of households stay in R.C.C. houses, provided under government schemes. A large proportion of households (65 percent) reside in built up area between 100-200 Sq. ft. while, remaining occupy the houses with built up area less than100sq

KUIDFC 25 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

VI) Income Distribution. Income levels of households serve as a proxy for their affordability to pay for existing / improved services. Survey results indicate that 57 percent of sample households fall in the below poverty line (BPL) income category. Forty-three percent of the sample households fall in the Rs. 1,500-2,500 monthly income bracket. It is evident that from the Chart 2.6 that lower income group is predominant among the slum population of Gangavathi. An inference can be drawn that very small percentage of migrants in income category of < Rs. 1,500 are rural poor, who come to the town in search of work.

2.6.1 Infrastructure in Slums

A.Water Supply

Most of the population in the slums depend more on stand post supply in Gangavathi i.e. 43% of the house holds have stand post connectivity and only 22% of slum households are served by house service connection while additional 9% have access to bore well/ open well All the households with HSC supply have unmetered connections. Households indicating multiple sources of water use both the sources for drinking and washing purposes and there is no selective use of different sources. Reliability of stand post /HSC in terms supply duration was found satisfactory in Gangavathi slums.

KUIDFC 26 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report Key Issues.

 Unreliable water supply in terms of supply, duration and quantity supplied.  Defunct water supply network in some slums,  Problems of water pressure and quality.  Lack of access or less secure access to alternate sources during water shortage periods and

 Unmetered supply of water, which renders determination of actual water consumption (and thereby demand) and cost recovery for water supplied, by the CMC is difficult.

B. Sewerage and Sanitation

In the Gangavathi town, UGD system is under execution and 80% of the town slums have been covered with sewer network but yet to be connected to households or connections. Only 9% of the slum households have indicated access to safe sanitation and have individual low cost sanitation facility. Without septic tanks the remaining 91% households practice open defecation in the absence of any sanitation facilities. KSCB has constructed 2 nos of community toilets under VAMAAY scheme and in 7 slums community toilet works are under progress by CMC, Wastewater is generally disposed into roadside drains by all slum households. The condition of roadside drains is very bad; as a result the wastewater overflows on roads. None of the households indicated satisfaction with the current levels of service. Stagnation of wastewater and prevalence of mosquitoes are common problems in many slums.

Key Issues

 Inadequate sanitation facilities leading to the practice of open defecation,  Blocking of roadside/storm drains due to disposal of night soil in the drains,  Health, hygiene and environmental implications due to the absence of safe disposal system, and  Inability of the poorest households to bear capital costs, which will have implications for tariff and subsidy design.

KUIDFC 27 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report

C. Solid Waste Management

There is no regular clearing of disposed waste by CMC, creating an unhygienic environment. Seventy four percent of the surveyed households indicated irregular collection of waste from the disposal site with frequency ranging from once a week to once in two weeks. It indicates very poor coverage of solid waste management system in Gangavathi slums. Only 8% of households have access to dustbin facilities. Remaining households were found to have lack of access to dustbins for waste disposal

Key Issues.

 Inadequate dustbin facility in slums,  No regular collection of disposed waste, and  Blocking of roadside drains, improper disposal and irregular collection,  Health and hygiene implications, animal nuisance, and implications on the surrounding environment.  D. Roads and Drainage

31. Majority of the slums are located along the roads. Consequently, slums along main roads have black topped road access while others have earthen/macadam road access. For about 80 % of the approach roads width is less than 3.5m, while for the remaining 20% road width is between 3.5 - 5m. The drains are generally unlined and open, clogged with kitchen waste and solid waste. It results in flooding of the slums during monsoons.

Key Issues.

 Poor condition of approach roads due to lack of regular maintenance,  Lack of roadside drains, and if present, improper management, and  Blocking of roadside drains due to disposal of solid waste and night soil.

KUIDFC 28 Span & Voyants NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Fig: 2.3 photo shows existing condition of drain, nalla and road at slum area in Gangavathi.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 29 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

2.6.2 Need of Project

32. The existing condition of the slums in the town of Gangavathi is poor and an urgent need is there to fulfill the following basic infrastructure in these slums. The basic needs are

 Cement Concrete Roads  Cement Concrete Drains  Water supply distribution pipe line  Street lights

 Public stand post

 Community toilet

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 30 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table: 2.6 Existing details of road and drain

Sr.no. Area of Slum Area in Existing Width Roads and Culverts

Mud Metal B.T CC Pavings Total mts

3. to 1 Angadi Veeranna camp 25570.72 492.28 494.39 85.08 - 917.58 - 1497.05 3.5

2 Erannagudda camp 11450.18 - 4.5 175.00 22.00 - 161.00 - 358.00

3 H R S camp 9346.26 311.79 2.00 54.00 - 77.35 364.80 - 496.15

4 Gajananna saw mill 16184.00 189.00 2.50 - - 90.15 896.90 - 987.05

5 Annur gowramma camp 17316.88 34.96 3.50 - - - 366.62 - 366.62

6 Gallamma camp 5623.94 - 3.00 - - - 286.71 - 286.71

236.5 7 Old Trench near Killa 33541.34 2180.84 3.50 673.52 - 650.00 - 1560.02 0

8 Rampurpet 566.44 - 2.00 ------

9 Basaveswara camp 8456.14 586.62 3.00 - - - 618.88 - 618.88

Near Neelakanteshwara 10 9224.88 - 3.50 - - - 535.65 - 535.65 temple

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 31 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 289.2 11 Veerapura waddar oni 13149.5 - 4.00 - 88.58 271.80 - 649.63 5

322.0 12 Gundamma camp 89699.82 5961.01 3.00 - 498.12 2584.32 - 3308.54 0

13 Indiranagar 5259.8 - 3.50 92.00 - - 347.60 - 439.60

14 Near housing board colony 121501.38 ------

15 Mehboobnagar 21241.50 90.33 3.00 671.00- - 816.41 - 938.14

16 Lambani Thanda 32368.00 395.63 3.50 - 34.10 - 1543.78 - 1577.88

1117.0 17 Bhagatsingh nagar 24761.52 503.88 3.50 - - 530.57 - 1582.95 0

18 Chelluvadiwada 36414.00 - 3.00 100.00 - 154.49 1150.36 - 1387.20

1820.0 19 Ambedkar colony 37223.2 4476.84 3.00 106.44 140.32 32.26 - 1843.09 0

20 Basheer ahmed compound 4733.82 - 3.00 ------

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 32 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 21 Majawardiggi 20230.00 457.05 3.50 522.82- - 499.60 - 1022.42

22 Uppinamali camp 4693.36 - 3.00 - - - 269.34 - 269.34

23 Herur Kishan rao 5219.34 280.18 3.00 145.85- - 67.39 - 213.24

1204.0 24 Lakshmi camp 17195.5 539.88 3.50 - - 411.99 - 616.92 0

25 Lingaraj camp 24276.00 524.13 - 286.75- - 740.42 - 1027.17

26 New weekly market area 4936.12 ------

Total 16500.2 8638.5 1285.5 14063.9 >>> 273922.12 9 8 247.62 1 8 - 24235.69

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 33 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Proposed Improvement in Basic Infrastructures Of Gangavathi Town

Sub-project Component Description

2.6.3 Proposed Drain 33. It was proposed in clip to improve the condition of the existing nallah and provide a proper outlet for the storm water drain in the low lying areas. The total estimated cost for the improvement of drains is Rs 200.00 lakhs. 34 It is proposed to improve the condition of the existing nallah and provide a proper outlet for the storm water drain in the low-lying areas. The total estimated investment required for the improvement is Rs. 998.00 Lakh. Based on the detailed topographical survey, the following secondary storm water drains of about 8.40 Kms will be taken up for Gangavathi town under this project.  Bannikatti camp: This drain flows towards Durgamma nala located on the centre part of the town near Bamboo bazaar. Covered areas are Bannikatti camp area. Proposed drain for a length of 130m of size (0.5mx 1.0m)  Eranna Gudda to Krishnadevaraya canal: This drain flows from northwest to east direction and is located on the southern part of the town. Covered areas are the Hillock areas of town some part of Virpapur area, Basavanna temple area and Yellamma katti extension area. The total length of the drain is about 880m with varying width from 2m to 3m. Hence proposed RCC drain of size (1.0M x1.0M)of length 200M, (2.0M x1.0M) of length140 and (3.0Mx 1.0M) for a length of 240M.The existing drain of length 320M is in good condition hence these section are retained .  Valmiki circle to Kanakadas circle: This drain flows from northwest to East direction and is located on the central part of the town. Covered areas of town are Hillock area, Jayanagar, Basavawara bad wane, Kuvempu nagar, Market, Bus stand, Police quarters, and Bus depot area. The total length of the drain is about 3390m with varying width from 0.5m to 1.5m. Hence proposed RCC drain of size (1.25M x1.5M) for a length of 850M and (1.50Mx 1.50M) for a length of 670m and also considered repair works from Ramapura area to children park for a length of 300m. The existing drain of length 1000M is constructed recently, which is in good condition, hence this section of the drains are retained  Killa Area to Durgamma nallah: This Drain flows from north to south direction reaches Durgamma nallah and is located on the most densely populated area of the town. Covered areas of the town are slum area Killa Aria slum, Gandhi circle, Commercial area near HMS

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 34 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

theater, Pin jar oni. The total length of the drain is about 1000m with varying width from 2m to 1.0m. Hence proposed RCC drain of size (1.5.0M x1.5M) for a length of 300M. About 700m of drains are constructed by stone masonry which can be retained and the remaining 200m of existing drain are to be dismantled because the drain size is less. During rainy season water overflows hence this drains is replaced with new drain of size (1.0Mx1.00M).

 Taluk stadium to Durgamma nallah: This Drain flows from north to south direction reaches Durgamma nallah and is located on the Commercial area and densely populated area of the town. Covered area of the town are APMC, some par of Maruthinagar,Vegetable Market, thick slum areas these drain loaded not only with the sewage water also solid waste like vegetable waste, plastic paper etc are dumped inside the nallah, The total length of the drain is about 1450m with varying width from 4.0 m to 5.0m. Hence proposed RCC drain of size (4.0M x1.25M) for a length of 310M and also included proposed repair works from taluk stadium to APMC yard for a length of about 1450m. The existing drain of length 700M is in good condition hence these section of the drain are retained.

 Maruthinagar to Durgamma nallah: This Drain flows in northwest to south direction reaches Durgamma nallah and is located on the Northern side of the town. Covered areas are Maruthianagar, Marutheswaranagar, Lingaraj camp, Vinayakanagar, Manjuvara camp. The existing drain are bad condition, Hence proposed bed concrete for a length of 860m and also proposed with only side wall for a length of 300m.

 Lakshmi camp to LBS Nagar: This drain flows from north to south direction reaches Krishnadevaraya canal and is located on the eastern side of the town. Covered areas are Lakshmi camp, Gowri nagar and Jia Bheemanagar. The total length of the drain is about 730m with varying width from (1.5.0 m to 3.0m). Hence proposed RCC drain of size (1.0M x1.0M) for a length of 510M.

 LBS Nagar to canal: This drain flows from north to south direction reaches Krishnadevaraya canal and is located on the eastern side of the town. Covered areas are Chalavadi oni and L B S Nagar. The total length of the drain is about 850m with varying width from (1.5.0 m to 3.0m). At present area not covered by residential area. Hence proposed only RCC drain of size (1.50M x1.25M) for a length of 195M

 Reliance petrol bank to Durgamma nallah via road: This drain flows from north to south direction reaches Durgamma nallah and is located on the Eastern side of the town. Covers areas are July Nagar and Amarbhagat Singh Nagar. The total length of the drain is about 1320m with varying width from 1.0 m to 2.0m. Hence proposed RCC drain of size (1.0M x1.0M) for a length of 820M and (1.0mx 1.25m) for a length of 500m.

 There is no land acquisition is involved since the drain is passing along the govt. Land (ie. Adjacent to road). No resettlement impacts will be involved.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 35 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

2.6.4 Improvement in Slum : 35. KSCB has identified 9 slums for up-gradation of basic infrastructure such as water supply, sewerage system, roads storm water drains, street lights, and community toilet etc, under this NKUSIP.

I) Mujawardigi slum 32. This slum is situated in western side of the of town, having population of 529 nos spreads over an area of 6.50 acres. In order to improve the infrastructure in addition to the existing facilities the following co mponents have been considered in the preparation of DPR.

 Concrete roads; cement concrete roads are proposed where mud roads exist with varying width from 3.5m to 4.5mts for a length of 568 mts so as to maintain uniformity over entire slum.  Storm water drains; two different sections of CC drains are proposed on both sides of the road, based on catchments and road width in order to drain storm water effectively from low lying areas through the drain and finally connecting to the main storm channel passing near by. It is proposed to construct drains for a length of 500 mts.  Under ground drainage system ; since under ground drainage system is being executed by KUWS&DB covering all the slums in town the same has not been taken up under this project Recently one community toilet with 10 seater has been constructed by KSCB and is being utilized by the dwellers.  Water supply; there is piped water supply system covering part of the slum area by CMC. Most of the dwellers fetch water from stand posts with single tap without proper platform. Pipe line is not covering the entire slum area, so it proposed to lay distribution pipes for a length of 250mts in this area including replacement of old and damaged lines along with 5 nos of public stand posts.

 Street lights; as there is no proper illumination in the interior portion of the slum, it is proposed to fix up 15 nos solar lamps with mounting structure and pole

II) Mehaboobnagar 33. This slum is also situated in western side of the town, having population of 2,352 spreading over an area of 5.24 acres. In order to improve the infrastructure in addition to the existing, following components have been considered in the preparation of DPR.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 36 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

 Concrete roads; Cement concrete roads are proposed where ever mud roads exist of varying width from 3.5m to 4.5mts for a length of 1890 mts so as to improve accessibility & hygiene.

 Storm water drains,; Two different sections of CC drains are proposed on both sides of road, based on catchments and in order to drain storm water effectively from low lying area through the drain and finally connecting to the main storm channel passing near by. It is proposed to construct drains for a length of 3780 mts

 Under ground drainage system; since under ground drainage system is being executed by KUWS&BD for the slums also the same has not been taken up under this project.

 Water supply; there is piped water supply existing in part of the slum but pipe line is not covering the entire area. So it proposed to lay pipe for a length of 300mts in the area including replacement of old and damaged ones along with 10 nos of public stand posts.

 Street lights; as there is no proper illumination in the interior of the slum, it is proposed to fix 20 nos solar lamps with mounting structure and pole

III) Laxmi camp- (Ambedkarnagar) 34. This slum is situated in eastern side of the of town having population of 1326 spreading over an area of 13.45 acres including Ambedkarnagar. In order to improve the infrastructure in addition to the existing the following components have been considered in the preparation of DPR.

 Concrete roads; cement concrete roads are proposed where ever mud roads exists with varying width from 3.5m to 4.5mts for a length of 2442 mts so as to improve accessibility & hygiene.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 37 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

 Storm water drains; two different sections of CC drains are proposed on both sides of road, based on catchments and in order to drain storm water effectively from low lying area and finally connecting to the main storm channel passing near by. It is proposed to construct drains for a length of 4390mts.

 Under ground drainage system; since the under ground drainage system is being executed by KUWS&DB the same has not been taken up under this project. Most of the dwellers in this area practicing open defecation due to absence public conveniences so

 Water supply; there is piped water supply existing in part of the slum but the pipe line is not covering the entire area. It is proposed to lay pipes for a length of 850 mts in the area, including replacement of old and damaged pipes. 10 nos of public stand posts are proposed.

 Street lights; Inorder to provide proper illumination in the interior of slums, it is proposed to fix 22 nos solar lamps with mounting structure and pole

IV) Gundamma camp;

35. This slum is situated in heart of the town having population of 2514 spreading over an area of 6.32acres. In order to improve the infrastructure in addition to the existing, the following components have been considered in the preparation of DPR.

 Concrete roads; cement concrete roads are proposed, where ever mud roads exist with varying width from 3.5m to 4.5mts, for a length of 2000 mts so as to improve accessibility & hygiene.

 Storm water drains; two different sections of CC drains are proposed on both sides of road, based on catchments and in order to drain storm water effectively from low lying area and finally connect to the main storm channel passing near by. So it is proposed to construct drains for a length of 4300 mts.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 38 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

 Under ground drainage system; since under ground drainage system is being executed by KUWS&DB the component has not been taken up under this project,

 Water supply; There is piped water supply existing in parts of the slum but the pipe line is not covering the entire area, and hence it is proposed to lay pipe for a length of 300 mts in the area, including replacement of old and damaged pipes and provide 3 nos of public stand posts.

 Street lights; as there is no proper illumination in the interior of the slum, it is proposed to fix 25 nos solar lamps with mounting structure and pole v) Killa area

36. This slum is situated in south west of town having population of 895 spreading over an area of 8.29acres. In order to improve the infrastructure in addition to the existing the following components have been considered in the preparation of DPR.

 Concrete roads; cement concrete roads are proposed where ever mud roads exist, with varying width from 3.5 m to 4.5 mts, for a length of 400 mts so as to improve accessibility & hygiene.

 Storm water drains,; two different sections of CC drains are proposed on both sides of road, based on catchments and in order to drain of storm water effectively from low lying area through the drains and finally connect to the main storm channel passing near by. It is proposed to construct drains for a length of 800 mts.

 Under ground drainage system; since under ground drainage system is being executed by KUWS&DB the component has not been taken up under this project.

 Water supply; there is piped water supply existing in parts of the slum but the pipe lines are not covering the entire area and so it proposed to lay pipes for a length of 500 mts in

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 39 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

the slum area including replacement of old and damaged pipes. 4 nos of public stand posts are proposed based on the population.  15 nos solar lamps with mounting structure and pole

V1) H R S camp;

This slum is situated in southern side of town having a population of 895 spreading over an area of 2.31acres. In order to improve the infrastructure in addition to the existing the following components have been considered in the preparation of the DPR.

 Concrete roads; cement concrete roads are proposed where ever mud roads exist, with varying width from 3.5m to 4.5mts, for a length of 1300 mts so as to improve accessibility & hygiene.

 Storm water drains,; two different sections of CC drains are proposed on both sides of road, based on catchments and in order to drain storm water effectively from low lying area through the drains and finally connect to the main storm channel passing near by. It is proposed to construct drains for a length of 800 mts.

 Under ground drainage system; since under ground drainage system is being executed by KUWS&DB covering all the town slums, the component has not been taken up under this project.

 Water supply; there is piped water supply existing in parts of the slum but the pipe line is not covering the entire slum area, and so it proposed to lay pipe for a length of 250 mts in the area including replacement of old and damaged pipes, and providing 3 nos of public stand posts.

 Street lights; as there is no proper illumination in the interior parts of the slum, it is proposed to fix up15 nos solar lamps with mounting structure and pole

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 40 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

VII) Chelluvadiwada;

36. This slum is situated in , south of town having population of 2800 spreading over an area of 9.02acres. In order to improve infrastructure in addition to the existing, the following components have been considered in the preparation of the DPR.

 Concrete roads; cement concrete roads are proposed where ever mud roads presently exist, with varying width from 3.5m to 4.5mts for a length of 200 mts.

 Storm water drains; two different sections of CC drains are proposed on both sides of road, based on catchments and road width in order to drain the storm water effectively from low lying area through lead drain and finally connecting to the main storm channel passing near by. It is proposed to construct drains for a length of 400mts.

 Under ground drainage system; since under ground drainage system is being executed by KUWS&DB the component has not been taken up under this project.

 Water supply; There is piped water supply existing in parts of the slum the pipe line is not covering the entire area. Hence it is proposed to lay pipeline for a length of 300 mts in the slum including replacement of old and damaged pipes, and installing 3 nos of public stand posts.

 Street lights; as there is no proper illumination in parts of the slum, it is proposed to fix up up15 nos solar lamps with mounting structure and pole

V111) Bhagatsingh nagar; 37. This slum is situated in north of town having population of 1670 and spreading over an area of 6.12acres. In order to improve the infrastructure in addition to the existing facilities the following components have been considered in the preparation of the DPR.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 41 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

 Concrete roads; cement concrete roads are proposed where mud roads exist, with varying width from 3.5 m to 4.5 mts, for a length of 1115 mts.

 Storm water drains; two different sections of CC drains are proposed on both sides of road, based on catchments and the road width, in order to drain storm water effectively from low lying area and finally draining to the main storm channel. It is proposed to construct drains for a length of 2234 mts.

 Under ground drainage system; since under ground drainage system is being executed by KUWS&DB the component has not been taken upunder this project.

 Water supply; there is piped water supply in parts, but the pipe line is not covering the entire area. It is proposed to lay pipes for a length of 250 mts in the area, including replacing old and damaged pipes. 8 nos of public stand posts are proposed based on the population.

 Street lights; as there is no proper illumination in parts of the slum, it is proposed to fix up up22 nos solar lamps with mounting structure and pole

1X) Angadi veeranna camp;

38. This slum is situated in west side of the town having population of 2152, over an area of 6.32 acres. In order to improve the infrastructure the following components have been considered

Concrete roads; Cement concrete roads are proposed where ever mud roads exist, with varying width from 3.5m to 4.5mts, for a length of 100mts.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 42 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Storm water drains; CC drains are proposed on both sides of the road for a length of 750 mts in order to drain storm water effectively from low lying area and finally connecting to the main storm channel near by.

Under ground drainage system; since under ground drainage system is being executed by KUWS&DB the same has not been taken up under this project.

Water supply; there is piped water supply existing in parts but the pipe line is not covering the entire area. It is proposed to lay pipes for a length of 500 mts in the area including replacement of old and damaged pipes along with 5 nos of public stand posts.

 Street lights; as there is no proper illumination the slum, it is proposed to fix up 15 nos solar lamps with mounting structure and pole

2.7 Investment Program Implementation Schedule

40. The Investment Program is to be implemented over an six-year period, commencing in FY 2009-10 and civil works construction starting in FY 2009-10. Completion is scheduled by end FY 2015-16

2.8 Investment Program Benefits 41. Urbanisation in India was the main driving force behind the rapid economic growth experienced in the country. However rapid urbanisation combined with the gross under- investment in urban infrastructures has resulted in serious environmental and health problems in urban areas. Urban households across India, particularly the poor and disenfranchised, continue to have limited access to potable water, sanitation, drainage and solid waste disposal facilities. While from the onset of the 8th Plan, the priority is to develop urban infrastructure and provide essential municipal services to reduce urban poverty incidence and to prevent further environmental degradation, the sector shows large inefficiencies in service delivery, inadequate investments to expand service coverage and lack of asset maintenance.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 43 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

42. The present project proposed under NKUSIP is intended to make up for these shortcomings in the selected slums. The proposals are intended to deliver and improve the delivery of water supply, drains, and paved roads in the slums selected. This in tandem with the general improvements under taken by the KUWS&DB and Slum Clearance Board would definitely improve the environment, health and sense of satisfaction in the slums where works are proposed.

2.9 Investment Program Alternatives

39. The environmental suitability of the proposed components are judged through the selected location and proposed process/technology during both the construction and operation phases. The interaction and the level of interference with the surrounding land use determine the environmental sustainability of the Investment Program components. However, the components proposed under NKUSIP are basic urban infrastructure services, most of which are location fixed providing scope for alternatives only in terms of technology, which again are limited. The following table shows environmental suitability of the selected alternatives.

Table 2.7 Investment Program Alternatives

Sub- Suitability of Selected Alternative Component Storm water Proposed RCC drain of length 5000m for Area town drain drainage which runs at various locations within the CMC limit of the town. However, the best alternative of gravity flow system is retained. No acquisition of land/structure is involved in the road improvement. It involves no tree cutting. Slum in Area there has 26 declared and one undeclared slum. out of which Improvements these slum only 9 slum has to be selected for improvement based on urgent need and execute works so as to attain maximum utility. Source: DPR (Detail project Report)

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 44 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

CHAPTER - III DESCRIPTION OF THE ENVIRONMENT

3.1 Environmental Profile of Area 3.1.1 Introduction

40. GANGAVATHI, the second largest urban centre in Koppal District is located at a distance of 360 km northwest from the State Capital Bangalore and 45 km from Koppal. The town is the Taluk Headquarters of the Gangavathi Taluk in Koppal District. The City Municipal Council jurisdiction extends up to an area of 16.53 Sq.km with 31 wards. The Gangavathi is the centre for development activities in agricultural sector and rightly called as the “Rice Bowl of Karnataka”. It is an important commercial and marketing centre well known for trade in paddy, jaggery, jowar and other food grains. 3.1.2 Physiography 41. The town is located on a gentle ground slope towards the south. Durgamma nalla runs across the town from southwest to southeast there by dividing the town into two parts. A hillock abuts the town on the west and stretches for considerable length along its border. The highest plane of town is at 398.17 m above MSL and the lowest part of the town is at 381.09 m above MSL. : The surface stratum is composed of murrum soil mixed with granite boulder out cropping at several places. The town comes under Central Karnataka Plateau, with the region representing the transitional surface between Deccan trap and relatively higher surface. Largely, this region represents the Tungabhadra River basin. 3.1.3 Seismology 42. As per the seismic zoning map of India, the Area town falls under the Zone II, which is the lowest earth quake risk zone in India. This zone is termed as “low damage risk zone”.

3.1.4 Climatic Conditions

43. The climate of the Gangavathi Town is characterized by dry weather during the major parts of the year and very hot summer temperatures are experienced during the periods of March to May. The town receives Southwest monsoon during the period of June to September while the months of October and November can be termed as post monsoon months. The average annual rainfall for the town is 509 mm. During the months of April and May the temperatures goes as high as 41oC and during the months of December and January the temperature will be around minimum of 15oC. Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 45 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

3.1.5 Surface Water 44. The River Tungabhadra is one of the important rivers in the north India that flows in a direction south to north along the northern side of Areaat around 30 km from the town. The river rises in the hills of Kerala and flows through the states of Karnataka and tamil nadufor a length of about 500km, before joining the Bay of Bengal sea.

3.1.6 Air Quality 45.Area is known for commercial and trade business and rich in agriculture farms there is very few small scale industries located near by areas. Pollution because of industries and vehicular movement is observed well with in the limit stipulated by Central Pollution Control Board.

3.1.7 Socio Economic Characteristics

46. The phenomenal growth of Urban Karnataka has lead to mushrooming of slums in and around the urban areas. The vulnerable places for slum development are mostly environmentally fragile areas namely marshy and swampy areas, low lying areas, vacant government lands, and its agencies, lands under high tension lines etc. The inhabitants of these slums are basically the urban poor, who are a legitimate part of the town. They contribute to its growth and deserve a share of the benefits of that growth. In Karnataka there are 2603 slums, out of which Bangalore alone accounts for 543, with Gangavathi having 26 declared slums. The improvements proposed in this scheme are in areas which are declared as slums by Karnataka Slum Clearance Board. These slums are located within a radius of 2.5 kms of Gangavathi Town. These slum dwellers are residing in these slums for the past 20 -25 years.

Table 3.1. Percentage Distribution of Slum households by access to basic services

Service Description Access to Households

HSC 22 Water Stand post 43 Supply Open well/ Bore 9

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 46 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

well

Stand post + open 26 well/ bore well

Public Convenience 9 Sanitation None 91

Solid Dustbins available 8

waste Dustbins not 92 disposal present

R.C.C 4

Housing Tiled pucca -

Type Tiles katcha 30

Thatched 66

The physical environment in terms of housing conditions, availability of basic services etc determines the productivity and consequently the quality of life in urban areas. Majority of the people living in slums do suffer from deprivation especially in basic services and amenities.

3.1.8 Household size and sex ratio

47. Survey of the Gangavathi town slums indicated an average household size of 5.3 in slums; with a standard deviation of 0.70. For the sample household this is higher than the KSCB figure for average slum household size of 4.32 in Gangavathi. Only 4 percent of the surveyed households were recorded as woman headed households while 48 percent of the households were recorded belong to SC/ST community. The average sex ratio for sample households is 877 females per 1000 males in Gangavathi slums, with a standard deviation of 70.06, showing some variation among sample households. The sample average is lower than the 2001 Census figure of 976, for the town as a whole.

3.1.9 Literacy

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 47 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

48 Literacy levels in Gangavathi slums are low, with 30 percent female literacy among the sample slum population, which is very much lower than the male literacy at 58 percent. The survey indicates a total literacy of 45 percent, which is very much below the 2001 Census figure of 67 percent for Gangavathi town as whole.

3.2 Environmental Settings of Investment Program Component Sites 49.The town is located on gentle ground sloping towards the south . the main natural grain Durgamma nallah starts near Waddarahatti tank and flows from North west to South east dividing the city into two parts.. The highest plane of the town is at 443m above mean sea level and

3.2.1 Urban Drainage Up gradation 50.It is proposed to improve the condition of the existing nallah and provide a proper outlet for the storm water drain in the low-lying areas. The total estimated investment required for the improvement is Rs. 646.00 Lakh. Based on the detailed topographical survey, secondary storm water drains of about 5 Kms will be taken up for Area town.

3.2.2 Slum Up gradation 51.Total of 9 slum have been selected to execute the works. the works include extending 3750 meters of water supply lines with about 14 public stand posts,. Laying 1000 mtrs of sewer lines, construction of concrete drains, providing 7,708 mtrs. Concrete roads with necessary culverts in place of katcha muds roads, seven ten seater community toilets and about 180 street lights. The estimated project cost for these improvements id Rs. 702 Lakhs.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 48 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

CHAPTER - IV SCREENING OF POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

5 2 . Potential environmental impacts of the proposed infrastructure components are presented in this section. Mitigation measures to minimize/mitigate negative impacts, if any, are recommended along with the agency responsible for implementation. Monitoring actions to be conducted during the implementation phase is also recommended to reduce the impact.

53. Screening of potential environmental impacts is categorized into four categories considering Investment Program phases: location impacts and design impacts (pre construction phase), construction phase impacts and operations and maintenance phase impacts.

(i) Location impacts include impacts associated with site selection, and include loss of on-site biophysical array and encroachment either directly or indirectly on adjacent environments. It also includes impacts on people who will lose their livelihood or any other structures by the development of that site.

(ii) Design impacts include impacts arising from project design, including technology used, scale of operation/throughput, waste production, discharge specifications, pollution sources and ancillary services.

(iii) Construction impacts include impacts caused by site clearing, earthworks, machinery, vehicles and workers. Construction site impacts include erosion, dust, noise, traffic congestion and waste production.

(iv) O & M impacts include impacts arising from the operation and maintenance activities of the infrastructure facility. These include routine management of operational waste streams, and occupational health and safety issues.

Screening of environmental impacts has been based on the impact magnitude (negligible/moderate/ severe in the order of increasing degree) and impact duration

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 49 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

(temporary/permanent). The following table shows the screening of impacts; N/T represents the lowest impact while S/P represents the highest impact. Numerator represents the Degree of Impact and denominator represents the Duration of impact.

Table 11 Screening of Impacts - Duration of Magnitude (Degree of Impact) Negligib Modera Severe(S) Temporary(T) N/T M/T S/T Permanent (P) N/P M/P S/P

The following tables shows the potential environmental impacts of the sub-project Components proposed for Area.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 50 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table 4.1: Environmental Impacts and Mitigation Measures of Drainage Upgradation Impact Description Significance of the Impact Mitigation Measures Implementati Preliminary

Location Impacts C ti No location impacts are N/a. N/a. N/a. N/a. envisaged as the proposed activities are carried out within the existing set-up.

Design Impacts N/a. N/a. No loss or encroachment of N/a. N/a. ULB N/a. cultural or historical properties is envisaged.

Construction Impacts

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 51 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Impacts to livelihood M/T Will compensate any business ULB Part of The Construction of Storm Waterloses as per the Resettlement construction drain will disturb the day to day activitiesFramework and Maintain costs of public such as shops, residence andassess to business (shops) also leads to un safety condition to them.people by providing planks / makeshifts pathway, etc. Exposure of workers to M/T contaminated soil during disilting It is highly unlikely that the soil Occupational Safety Plan shall and excavations contains any heavy metals; however, be prepared. This includes: (i) considering the entering of domestic provision of personal wastewater including sewage enters protection equipment such as the open drains, this impact may be gloves, boots, (ii) Manual considerable. handling of waste shall be avoided as far as possible; and (iii) Training of workers on safe handling of sludge. Disturbance to traffic due to M/T Construction material shall be Head N/a. storage of construction Stockpiled to minimize contractor material/waste and material traffic blockages. transport vehicles and other equipment. Excavation of trenches will MT Find beneficial uses for waste Contractor. produce large amount of waste soil in construction, land soil. raising and infilling of

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 52 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Trees may be removed along MP Only remove trees if it cant be Contractor drain routes avoided Plant and maintained two trees for every one removed

Business may lose income if MT *compensate business for lost KUIDFC customers access is impeded income as per the Resettlement Framework.

Leave spaces for access between mounds of soil and Contraqctor provide planks for continued

access across trenches. Provide bridges to allow people Contractor & vehicles to cross trench

Excavation could damage other SP Determine location of water Design infrastructure pipes, electrical pylons, etc. consultant and design scheme to avoid damage

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 53 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Traffic may be disrupted by soil MT Keep soil vehicles machinery and vehicles ion roads off road when possible. If work will affect road, conduct when traffic is light. Ensure police provide warning signs / diversion if needed Contractor.

Traffic in town could be MT Plan routes to avoid narrow disrupted by vehicles en route to streets, congested routes, and from site, delivering material important / fragile buildings, contractor or removing waste key religious & tourism sites

Ground disturbance could SP Request state and local ULB/ damage archaeological and archaeological authorities to contractor. historical remains assess archaeological potential of proposed STP site. Include state and town historical authorities as a project stake holders to benefit from their expertise. Develop and apply protocol to protect chance find (excavation observed by archaeologist stop work if find are suspected: state authority to plan appropriate

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 54 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Workers and the public are at MT Prepare and implement a site Contractor risk from accidents on site health and safety plan that includes measures to : - Exclude the public from site - Ensure that workers use Personnel Protective Equipment - Provide Health & Safety training for all personnel’s. Economic benefit if local people MT Contractor should employ at are employed in contractor force least 50% of workforce from Contractor communities in vicinity of construction sites

Dust nuisance. M/T Dust suppression activities Head Part of Due to dry weather conditions of the such as water sprinkling contractor construction Gangavathi, the dust generated due shall be employed. costs to the construction activity may be significant.

Impacts due to disposal of N/T N/a. N/a. N/a. contaminated silt.

Pollution and silt loading of water N/T N/a. N/a. N/a. bodies

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 55 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Public and worker safety N/T N/a. N/a. N/a.

Operation Impacts Silting and pollution of water M/T Ensure clearing of ULB N/a. bodies due to non-clearance debris/waste and material of construction work site from the drainage bed and from the banks before

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 56 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table 4.2: Environmental Impacts and Mitigation Measures of Slums – Water Supply system Impact Description Significance of the Impact Mitigation Measures Implementation Preliminary

Location and Design impacts MP Identify and consult all R ULBibili t CPart tiof O & M Water use conflict may occur downstream users’ sufficient water cost. with downstream users. for them to continue existing water

Particularly in dry season dependent activities. Negotiate month. agreements with user and the appropriate regulatory agencies and establish controls to ensure that water is not abstracted of agreed volumes. Also, road side water tank (syntax tank) shall be provided to have continuous water supply.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 57 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

The increase in water supply MP Improved sanitation facilities to Part of O & M will increase waste water levels. accommodate increase in water cost. ULB use including twin latrines, public

toilets etc.,

Improved sanitation system to Increased waste water caused accommodate increased water Part of O & M by the increased in water supply MP ULB supply including new toilets, septic cost. Since the location of tank, cleaning services and sludge

rehabilitation drying beds. N/a work will be at existing facilities, N/a and the existing environment is N/a N/a a built environment, no design-

Construction Impacts

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 58 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Impacts to livelihood M/T Will compensate any business Head Contractor/ULB Preparation The laying of water line will loses as per the Resettlement and disturb the day to day activities Framewor. implementatio of public such as shops, While laying water line through n of site residence and also leads to un narrow streets and thick management safety condition to them. commercial establishments, the plan. work will be planned to complete in short duration and care will be taken to avoid excavation of the entire road stretch in these areas. Road blocking due to laying of N/T Head Part of water supply network and Proposed network will be laid Construction material shall be Contractor/ULB construction increased traffic flow due to in the presently un-served stockpiled to minimize traffic costs vehicle movement for fringe and extension areas. blockages. construction activities; As these areas are not inconvenience densely populated impacts Poor performance of the contractor to the local community. due to construction activities may potentially exacerbate these may not be significant. impacts and therefore qualified contractors to be appointed. The contracted ork incl des the

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 59 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Dust and noise from M/T Frequent water sprinkling Head Part of construction Due to dry climatic condition program will undertake to Contractor/CMC construction Activities. the dust generation may be suppress the dust. costs Considerable. No major

noise generating

activities envisaged.

Part of N/T Head Waste soil and imported sand Contractor/ULB construction Remove waste quickly, cover spray costs stock piles, sprinkling of water to may create dust impacting air avoid dust pollution, only bring sand quality ( for backfill) to site when needed N/T Part of Plan work program to keep Head contractor / People will be inconvenienced construction shutdown to minimum, provide CMC costs and their health may be at risk if alternative water to affected water supply system is shut residents inform communities to down for long period

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 60 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Impact Description Significance of the Mitigation Measures Implementation Preliminary Loss of forest trees and MT Avoid tree cutting to extend possible Contractor Part of vegetation and plant 25 sampling for every tree construction

cut. cost.

Contractor Construction activities to avoid steep .Part of Impact on topography and slope slopes and landside prone areas. Contractor construction stability cost. MT Excessive excavated materials to be Disposal of excavated material disposed at designated place. Part of construction cost.

Environmental impacts from MT Where sites/camps are set up, the Contractor Part of construction workers camp contractor will see that proper construction

sanitation ( toilets, solid waste cost.

management) systems are in place:

potable drinking water provided:

kerosene to be provided at reduced rate for cooking: gambling, liquor and illicit relationship banned, contractor will be required ( as per his contract) to ensure clean up of site back to original

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 61 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Trenching could damage otherMT Confirm location of infrastructure to Contractor Part of infrastructure avoid these sites. construction cost.

Shops may lose income if Compensate business for lost income customers access is impeded MT Contractor (as per Resettlement framework). Part of

Leave spaces for access between construction mounds of soil. Private bridges to allow cost.

people & vehicles to cross trench.

Increase workforce in these areas to finish work quickly, inform shopkeepers

of work in advance.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 62 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Sites of social / culturalMT dentify building at risk from vibration Contractor Part of importance (school, hospitals, damage and avoid using pneumatic construction

temples, tourism sites) may be drills or heavy vehicles nearby, remove cost.

disturbed by noise, dust waste quickly , cover / spray stockpiles, vibration and impeded access import sand only when needed, cover

soil sand on trucks, increase workforce

to finish work quickly. Use bridges to

allow access ( peoples/ vehicles).

Consult relevant authorities, custodians

of buildings, local people to address

issues and avoid work at sensitive

times. No construction at night and

early morning hours. Public to be

notified of any loud noise and vibration.

Prepare and implement a site Health Contractor MT Part of Workers and the public are at and Safety plan that include measures construction risk from accidents on site . to : Exclude the public from all cost. construction sites. Ensure that workers

use personal protective equipment.

Provide Health & Safety training for all

personnel: follow documented

procedures for all site activities: and Head keep accident reports and records. Economic benefits if local MP Contractor/ULB people are employed in Provide employment to local Part of Span Consultantstt Pvt. kf Ltd. In association with Ramky Infrastructure Pvt. Ltd tti 63 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

O& M Impacts Occupational health and safety M/T Provide provision for safety measures contractor Part on of workers and locals in design stage. Training of workers construction Risk of contaminated water M/S Prepare and operate H & S plan with Contractor Part of in the distribution system. same measures in design stage. construction Training of workers on safety Costs measures to be taken. Inadequate disposal of M/P Safe sludge handling methods shall Contractor Part of sludge treatment plants will be employed – personnel protection construction cause nuisance to public equipment such as gloves, boots Costs

health shall be provided. Any sludge

produced will be delivered to the sludge drying beds via open bed

trucks covered with tarpaulin. Testing

of sludge for contaminants will be done by government laboratories. If

sludge found to contain alum other or

other contaminates after testing, it can be land filled.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 64 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table 4.3: Environmental Impacts and Mitigation Measures of Slums - Sewerage & Sanitation works Impact Description Significance of the Impact Mitigation Measures Implementatio Preliminary

Pollution and health M/P Safe sludge handling methods ULB PartC tiof O & hazards due to improper sludge shall be employed - Personal M costs disposal Quantity of sludge generation will be protection equipment such as methods considerable. Contaminated work area gloves, boots, shall be provided. may cause health hazards. Sludge shall be dried in drying beds before its disposal. This sludge may be used as manure for non- food crops or land filled. Mixing of non-municipal N/P Wastewater from industries KSPCB N/a. wastewater may interfere with Possibility of mixing of industrial shall not be allowed to enter the the treatment process. effluent is very low as there are no sewers. In case of discharges industries in the sewerage zones with into sewers the effluent shall problematic discharges. confirm to the CPCB/KSPCB standards:

• BOD < 350 mg/l • pH – 5.5 – 9.0 • Suspended solids < 600 mg/l • Arsenic(as As). <0.2 • Mercury (As Hg), mg/l, max.0.01 • Lead (as Pb) mg/l, max 1.0 • Cadmium (as Cd) mg/l, max 1.0 • Copper (as Cu)mg/l, max. 3.0

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 65 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Impacts due to illegal M/P Illegal tapping of sewage ULB Part of O & tapping of sewage for irrigation Trunk sewers traverse agricultural from the sewer lines shall M costs purpose from trunk sewers: fields. Illegal tapping was observed. not be allowed. Regular . Probable contamination of agricultural maintenance and constant lands and groundwater; potential check would reduce the hazards due to entering of problem. contaminants into food chain. Impact on the working condition of the STP due to reduced inflow Nuisance and pollution of M/P Regular maintenance will nullify ULB Part of O & ground/surface water due Irrigation canals traverse the town and the impact. M costs to over flowing/choking of the groundwater depth is shallow in sewers. the northern part of the town

Human health risks and MT Sewer leaks shall be detected ULB Part of O & M contamination of soil and and repaired rapidly and costs groundwater due to leaking effectively sewers

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 66 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Impact on business income if MP Spaces shall be left for accessULB Part of O & M customer’s access is impeded between mounds of soil. costs by • Planks shall be provided to network repair works ST allow people & vehicles to cross Discharge of hazardous trench. materials into sewers, resulting • Workforce shall be increased in damage to sewer system in these areas to finish work and danger to Workers. Mixing quickly. of Industrial Waste water with • Shopkeepers will be informed sewage. of work in advance M/P KSPCB & ULB Part of O & M Treatment process in the Septic tank will costs Wherever level permits, sewer be significantly affected Health risk to The rules and regulation will be

line proposed in slum area shall the sewer workers due to toxic effluent strictly implemented to avoid be connected to the proposed and gases. mixing of industrial waste sewer line for city and if the level stream/hazardous waste with is not permitted, those areas sewage in sewer system. ULB Part of O & M shall be connected to the costs proposed community toilets Sludge will be dried and tested

which will be connected to the for absence of bacteria and septic tank. The sludge settled pathogens Dried sludge will be in Septic tank shall be sold to farmers to fertilize land periodically removed. along with the STP sludge.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 67 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Economic benefits to local MP Periodic monitoring of treated ULB Part of people by Project effluent will be carried out. A Construction

water quality-testing laboratory and operation

will be provided. Cost Discharge of insufficiently M/T Part of O &M treated H&S Plan shall be prepared and ULB costs wastewater to water operated with same measures as used in construction phase

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 68 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table 4.4 Environmental Impacts and Mitigation Measures of Slums - Roads Up gradation Impact Description Significance of the Impact Mitigation Measures Implementation Preliminary

Location Impacts Ribilit C ti No location impacts are envisaged as N/a. N/a. N/a. N/a. the Proposed activities do not encroach into any sensitive land uses nor does

Desiit ig ln Impactsl d i iti Acquisition of land/structure is not N/a. N/a. N/a. N/a. envisaged. No trees will be cut as part of the Investment Program. Construction Impacts Disturbance to informal commercial N/T Temporary relocation of ULB As part of activities during construction. No Hawkers and vendors were hawkers RP observed. A detailed survey will be and vendors; followed by costs conducted at the design stage to reinstatement of original identify hawkers and vendors premises when the work is completed. Disturbance due to construction N/T N/a N/a N/a activities Low levels of traffic was Road block and increase in traffic on observed in the slums on the

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 69 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Nuisance due to noise. M/T Noise limits for construction Head Contractor N/a. Proposed roads pass through slum equipments such as areas (residential area). compactors, rollers shall not exceed 75 dB(A), as specified by CPCB. High noise generating activities, if any, shall not be carried out during the nights.

Dust nuisance. M/T Dust suppression activities Head Contractor Part of Proposed roads pass through such as water sprinkling constructi residential areas. Due to dry shall be employed. on costs weather condition dust nuisance may be considerable. Public and worker safety N/T Provide caution and Head Contractor Part of signboards. /CMC constructi on costs Personal protection equipment such as gloves, boots, shall be provided to

the workers

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 70 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table 4.5 Environmental Impacts and Mitigation Measures of Drainage Upgradation Impact Description Significance of Mitigation Measures Implementatio Preliminary the Impact n Costing Location Impacts No location impacts are N/a. N/a. N/a. N/a. envisaged asthe proposed activities are carried out within the existing set-up.

Design Impacts N/a. N/a. No loss or encroachment of N/a. N/a. CMC Area N/a. cultural or historical properties is envisaged.

Construction Impacts

Impact to “ livelihoods due to will compensate any business losses as per the disruption during construction” resettlement framework.

“ the laying of distribution lines And maintain assess to business (shops) people by will disturb the day to day providing planks/ makeshifts pathways etc. while lying activities of public such as shops, sewers through narrow street and thick commercial residence and also lead to un establishment the work will be planned to complete in safety condition to them short duration and care will be taken to avoid excavation of the entire road stretch in these areas. Construction Head contractor Part of M/T material shall be stockpiled. Adequate arrangement for construction traffic diversion including erection of proper sign boards. costs Exposure of workers to Dust shall be suppressed by frequently sprinkling water. contaminated Reputed standard make equipment shall be used soil during desilting and exactions complied with standard stipulated by PCB to ensure noise well within the limit. High noise making activity will be restricted in day time only. Poor performance of the contractor may potentially exacerbate these impacts and therefore qualified contractors to be appointed. The contracted work includes the implementation of construction site management plan.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 71 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Disturbance to traffic due to M/T Construction material shall be Head contractor N/a. storage of construction Stockpiled to minimize traffic blockages. material/waste and material transport vehicles and other equipment. Nuisance due to noise N/T N/a. N/a. N/a. Dust nuisance. M/T Dust suppression activities such as water sprinkling Head contractor Partof shall be employed. Frequent vehicle maintaince shall constructio Due to dry undertake to ensure smooth movement of vehicles to n costs weather avoid any noise, smoke pollution. conditions of no soil spill during transportation of soil at construction site to curb to curb the increased dust emission due to the Area, the vehicular movement. Daily inspection at construction dust generated site shall be carried out to ensure removal of due to the construction debris. construction dust sealed truck shall be used for transportation of activity may be earth. significant.

Excavation of trenches will MP Contractor Part of Find beneficial uses for waste soil in construction, land produce large amounts of waste construction raising and infilling of excavated areas. soil cost. Keep soil, vehicles, machinery off road when possible Traffic may be disrupted by soil and vehicle on road MT If work will affect road, conduct when traffic is light. Contractor Part of construction Ensure police provide warning sign / diversion if needed. cost. Impacts due to disposal of N/T N/a. N/a. N/a. contaminated silt

Pollution and silt loading of water N/T N/a. N/a. N/a. bodies Public and worker safety N/T N/a. N/a. N/a.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 72 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Excavation could damage other S/P Determine location of water pipes, electricity pylons etc Design infrastructure and design scheme to avoid damage. consultant Locate different infrastructure on opposite site of road. Design consultancy Economic benefit if local people are employed in contractors MT Contractor should employs at least 50 % of workforce Contractor workforce from communities in vicinity of construction sites

Operation Impacts Silting and pollution of water M/T Ensure clearing of debris/waste and CMC Area N/a. bodies material from the drainage bed and from the banks due to non-clearance of before pressing into operation. construction work site

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 73 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL MONITORING PLAN

5.1 Institutional Requirements

54. Nodal Executing Agency (EA). Karnataka Urban Infrastructure Development & Finance Corporation (KUIDFC) is the nodal executing agency (EA) responsible for implementing NKUSIP. Investment Program implementation activities will be monitored by KUIDFC through a separate Investment Program Management Unit (IPMU), which will be set-up within KUIDFC. The Managing Director/KUIDFC will head the IPMU and will be assisted by an Executive Director to oversee the Investment Program progress. A team of senior technical, administrative and financial officials will assist the Executive Director in controlling and monitoring project implementation activities. KUIDFC will establish IPMU offices at two locations (in Bellary and Gulbarga) in the Investment Program area. All Investment Program decisions will be made by the Executive Director who shall operate from the IPMU, Dharwad; only interactions with GoK, GoI and ADB shall be conducted through the KUIDFC office at Bangalore.

55. Implementing Agency (IA). Implementation Agencies (IA) will oversee sub-project component implementation at the sub-project towns, where the Investment Program ULB will implement sub-project components. The responsibilities of the IA shall include (i) carrying out detailed surveys, investigations and engineering designs of individual infrastructure components; (ii) tendering, evaluating bids and awarding works, contract administration, supervision and quality control; (iii) measuring works carried out by the contractors and certifying payments; (iv) conducting public awareness campaigns and participation programs, (v) carrying out environmental assessments; and (vi) preparing monthly reports. The Investment Program Consultants (PC) will assist the Investment Program ULB in all the aforesaid activities; in the case of other IAs, the PC shall proof check designs and quality check construction quality.

56 Thus, the responsibility fulfilling environmental requirements of GoI/GoK (for the project- components of STP, solid waste processing and disposal and construction of barrage) and conducting required level of environmental assessment as per ADB guidelines lies with the borrowing ULB. The Investment Program Consultants will assist the ULB in this regard. The IEE/EIA reports prepared by ULB will be reviewed by the

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 74 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

IPMU as per the ADB’s Environmental Guidelines and forwarded to ADB for review and approval. In case of IEE reports, the ADB could delegate approval of IEE reports fully to the IPMU after reviewing the first two reports. However, all the EIA reports shall be sent to ADB for approval.

57. The mitigation measures identified through IEE/EIA are incorporated into the project cycle. Mitigation measures, which are implemented by the Contractor, shall form part of the Contract Documents. The other mitigation measures are undertaken by the ULB (itself or in assistance with Investment Program Consultants) as specified in the IEE.

5.2 INSTITUTIONAL STRENGTHENING

Institutional strengthening will be undertaken to achieve the goals of the project including sound environmental management. Steps to be taken are discussed under the following sub-headings:  Organisation and Staffing;  Environmental Training;  Monitoring and Reporting; and  Record-keeping.

5.2.1 Organisation and Staffing

58. The implementation of mitigation measures requires supervision by adequately trained staff within the Project Implementation Unit (PIU). The PIU will nominate one of its officers to act as Environmental Officer (EO), to formally address environmental issues on a routine basis, who will have an oversight of environmental aspects of the construction contracts, including the enforcement of all monitoring provisions, the locations of construction and labour camps, etc. Before the commencement of construction, the EO will receive training in the environmental issues associated with STP construction and maintenance projects. The EO will also organize the training programs. Main duties of the EO will include:

 Review of bids to ensure their adherence to the environmental specifications and the requirements of the Environmental Management Plan (EMP).

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 75 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

 Collection and dissemination of relevant environmental documents including amendments to environmental protection acts issued by various agencies such as the Asian Development Bank (ADB), World Bank and other concerned organisations.  Co-ordination with government departments on environmental issues and obtaining the necessary clearances from the regulatory authorities.

 Monitoring the environmental aspects during construction to ensure that the environmental requirements of the contract and the mitigation measures proposed in the EMP are implemented.  Supervising contractors and preparation of environmental input to the quarterly progress report.

5.2.2 Monitoring and Reporting Procedures

59. The EO shall ensure monitoring of various environmental parameters during the implementation of the project. The EO will visually assess contractor’s practices. Observations of EO and compliance thereupon shall be documented as part of normal contract monitoring. Regular monitoring of dust control, soil conservation practices, management of borrow/quarry area will also be carried out as provided in the contract document.

5.2.3 Record Keeping

60. Monitoring form should be devised for use. The form should focus attention on environmental issues and provide feedback for the future stages of the work. Mitigation and enhancement measures will explicitly make part of the construction contracts documents so that the compliance is measurable and readily documented. Daily project diaries would record environmental problems (spills, dust etc.) as well as safety related incidents and will be retained as part of contract management documents. These reports would be included in Quarterly Progress Reports provided to the funding agency (ADB) as well.

5.3 ENVIRONMENTAL MONITORING PROGRAM

61 Environmental Monitoring Program is a vital process of any management plan of the development project. This helps in signalling the potential problems resulting from the Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 76 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

proposed project and will allow for prompt implementation of corrective measures. The environmental monitoring will be required during construction and operational phases. The following parameters need to be monitored:

- Rehabilitation and Resettlement Program,

- Afforestation,

- Soil conservation,

- Borrow Area Conservation, and - Sanitation and Waste Disposal.

5.3.1 Rehabilitation and Resettlement Program 62 The Rehabilitation and Resettlement Program needs to be monitored during the project construction phase. The entire program is supposed to be completed before operation phase. Sufficient care needs to be taken to ensure that money reaches the project-affected people. The quality of life of rehabilitated people should not fall below their present status. Details of such program have been presented in separate Social Impact Assessment report.

5.3.2 Afforestation

63 Afforestation for the proposed project will commence before the start of the project cycle. The Forest Department of Government of Karnataka will implement the afforestation program. Trees shall be planted along the railway line inside the right of way (ROW) as soon as construction work is over.

5.3.3 Soil Conservation

64 Soil erosion rates, water sediment load, effectiveness of soil conservation measures, changes in soil texture and structure should be monitored at frequent intervals, during construction and operation phase..

5.3.4 Borrow area Conservation 65. Restoration of borrow areas will be monitored from time to time by construction supervision engineer with the progress of works in full compliance with the contractual obligations. The excavation and restoration of borrow areas and their surroundings, in an

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 77 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

environmentally sound manner to the satisfaction of the supervising engineer, is required to be done by the contractor before final acceptance and payment under the terms of contract.

Table 5.1 Institutional Roles and Responsibilities Investment Activity Details Responsible Program Phase Agency

Pre construction Investment Program Conduct Rapid ULB phase Categorization Environmental Assessment (REA) for Reviewing the REA and IPMU assigning project category (Ea/Eb/Ec) Conducting EA Conducting IEE/EIA Investment based on the project Program categorization Consultants

Conducting Public Consultation and Investment Program Fulfilling GoK/GoI ULB clearances requirement such as clearances from other Review of EIA/IEE ReviewingGovernme ntthe EIA/IEE IPMU and SEIA/SIEE Reports Disclosure of Information disclosure - ULB SEIA/SIEE SIEE/SEIA reports Incorporation of Incorporation of Investment mitigation measures necessary mitigation Program into Investment measures identified in Consultants Review of design Review of design and IPMU documents contractual documents Construction Implementation of Implementation of Contractor Phas mitigation measures necessary mitigation Monitoring Environmental Investment monitoring as specified Program in monitoring plan during Consultants Preparation of progress Preparation of monthly ULB in assistance reports progress reports to be of PC submitted to IPMU including a section on implementation of the mitigation measures Review of progress IPMU to review the IPMU

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 78 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Investment Activity Details Responsible Program Agency Phase Operation Environment Conducting environmental ULB Stage al Monitoring monitoring, as specified in the environmental Compliance Compliance monitoring to KSPCB Monitoring review the environmental

5.3.5 Training Needs 66 As described in the above table the IPMU will involve in monitoring the Investment Program implementation while the ULB will implement the Investment Program. It is therefore important that these agencies and particularly the officials involved in the Investment Program to have understanding of the ADBs environmental assessment procedures and also of environmental issues of various urban infrastructure components. As far as implementation of mitigation measures on site is concerned the Contractor will be involved. Hence, it is important to orient the contractors and supervisory staff towards the implementation of mitigation measures and their consequences. Hence, considering the existing capabilities of the agencies involved in NKUSIP, the following training program is suggested. The following table presents the suggested training program.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 79 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table 5.2. Training Needs (2007 – 2015) Description Contents Schedule Participants Program 1 Module 1 – Orientation 2 days • PMU officials Orientation Program • Investment Program Cycle of involved in / Workshop for NKUSIP the project and Implementing • ADBs Environmental • ULB officials Agency and Assessment Executing Agency involved in Guidelines project • EA requirements of NKUSIP implementation • Indian Environmental Laws & Regulations relating to urban infrastructure project • Environmental impacts of urban infrastructure projects

Module 2 Environmental Assessment Process • Project categorization as per ADB • IEE/EIA process, Formats and Reports • Identification of Environmental Impacts • Identification Mitigation Measures • Formulation of Environmental Management Plan • Implementation and Monitoring • Summary EIA/IEEs • Review of EIA/IEE reports to l ih ADB Program - Module 1 Implementation of 1 day • Contractors 2 Mitigation Measures involved in Orientation • Environmental issues related NKUSIP Program urban infrastructure projects • Supervisory / Workshop for during construction staff of ULB Contractors and • Implementation of Supervisory mitigation measures staff • Monitoring of implementation Program - 3 Module – Experiences and Best 1 day (every • IPMU Experience Sharing Practices alternative officials • Experiences on implementation year from the • ULB officials in terms of environmental start concerns of implemented of project, i.e. • Local NGOs projects 2007)

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 80 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

5.3.6 Environmental Monitoring Plans

Monitoring is an essential and an integral part of the implementation of the proposed Environmental mitigation measures. Environmental monitoring generates useful Information and improves the quality of implementation of mitigation measures. This IEE and EMP are updated as per detailed design and any design changes. Environmental monitoring plans for sub project components in Gangavathi are presented in Table – 5.3 to 5.9 and annual environmental cost estimate is provided in Table 5.10.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 81 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table 5.3 : Environmental Monitoring Plan for Drainage Up gradation Mitigation Parameters to be Location Measurement Frequency Responsibility Preliminary Measures Monitored Costing Construction Stage Check for dust Incorporation of N/a. Inspection of contract One-off IPMU IPMU staff nuisance mitigation documents inspection time as measures in the before signing required contract the contract documents Dust nuisance Constructi Ensure the Weekly CMC Area with Part of on work implementation of the construction sites mitigation measures assistance of costs of such as spraying of Investment prima water; assess the Program ry situation through visual Consultants drain inspection and s; interviews with local people Operation stage Checking of Waste water Ensure the drains are not One time before ULB Part of O & M drains nuisance clogged and free of solid the rain. cost. waste and other debris.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 82 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table 5.4: Environmental Monitoring Plan for Slums - Water Supply Rehabilitation Mitigation Measures Location Measurement Frequency Responsibilit Preliminary Design Stage Monitoring C ti Water quality (all parameters, particularlyKabini river at One time before faecal colliform ) the intake final design stage. point MoU between ULBS and other Signed One time before downstream communities agreement final design stage. Safe intake sites with minimum risk of Proposed One time before pollution adequate source and intake intake sites final design stage . protection measures. Paid compensation and rehabilitation Survey of APS At the time of civil measures for land acquisition before civil contract award. contract award. All design of component include proper Proposed One time before consideration of environment ( i.e. water design of final design phase. and air quality, noise pollution sludge DSC. management ) Avoiding / minimising tree cutting. Proposed One time before designs of final design phase. Design of occupational safety measures. Proposed One time before design of DSC final design phase. Training program for staff by consultants. -- As needed before and during

Construction Stage Monitoring il tti

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 83 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Construction Stage Incorporation of mitigation One-off inspectionPMU Part of All construction related Mitigation measures in the contract of contract construction Measures: documents document. costs N/a Construction site management plan to Verification of Contract control the dust and noise nuisance, and Documents before signing road blocks. the contract. Implementation of Construction site Pipe LayingMonitoring of air quality is Weekly Contractor management plan providing access to sites and not required. Ensure the and ULB with businesses during pipe lying, etc. surroundings. implementation of the assistance mitigation measures such of Investment (i) Noise & dust nuisance at site, as spraying of water; Program (ii) Traffic Maintain ace assess the situation Consultant. (iii) Impact to Livelihood through visual inspection and interviews with local people, usage of standard equipment complying with CPCB Noise standard for Operation stage Check for blockage and leakage Distribution Percentage of water Yearly twice (once ULB Part of O & M problems; reducing the water losses. line & losses during normal costs Transmission season and once line. during lean season)

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 84 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Implementation of the Sludge N/a Health check for WTP staff Yearly once ULB Part of O & M Management Plan - Check for health Costs. hazards due to sludge handling. Regular O & M water treatment facilities Inspection of facilities By annual Water quality ( TSS, pH, Temperature, Drinking water at taps andParameters BOD5, COD , E- coli) reservoirs. location and frequency according to the national drinking water quality standards and implementation

Residual chlorine is sufficient to assure Measured throughout thegBi- idelines annually the potability of water supply at the distribution network household tap as well as to assure no particularly at point furthest over chlorination. from the chlorination point..

Training and operation supervision of Survey of staff Bi- annually

Handlingsystem staff and dosages of chlorine and Treatment plant inspection Quarterly

li

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 85 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table 5.5 Environmental Monitoring Plan for Slums - Sewerage System Mitigation Measures Location Measurement Frequency Responsibilit Preliminary y Costing Design/Location Stage Monitoring N.A Verification of contractOne-off inspection PMU Check for Construction related impacts documents before signing of and mitigation measures. the contract Incorporation of mitigation measures into the bidding and civil contract documents All designs of components include proper --- Proposed designs ofOne time before PC consideration of environment (i.e., water DSC final design phase. and air quality, noise pollution ,sludge management) Design of occupational safety measures Proposed designs ofOne time before PC DSC final design phase. Training programs for staff by ------As needed before PC consultants. and during implementation. Gas monitoring for sewage pipes –Sewer pipes Gas monitoring in the Monthly once as ULB with the Adequate monitoring of gas may not beand sewerage network part of Plant assistance of possible due to distant manholeManholes Operation. Program spacing. Manhole shall be designed consultants considering worker/s safety

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 86 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

All location and design related mitigation N/a Incorporation of One off PMU/ULB/PC measures to mitigate loss of amenity and mitigation measures in inspection of nuisance; and sludge disposal. the design including air designs Appropriate design of process and layout dispersion modeling for is required. STP site. Checking/Verification of Investment program Design documents Disposal of treated waste water – Sale Site observation; farmer Monthly ULB of treated wastewater to farmers for survey irrigation and usage of treated waste water for ponding systems for Construction Stage All construction related mitigation N/a. Incorporation of One-off IPMU measures such as construction site mitigation measures in inspection of management plan to control the dust and the contract documents. Contract noise nuisance and road blocks. Document Verification of Contract Documents before signing the contract

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 87 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Implementation of construction site Sewer Monitoring of air quality Weekly Contractor and Part of management plan, providing access to laying sites and noise is not ULB with consultancy businesses during pipe laying etc. (i) and required. Ensure the the cost noise and dust nuisance at site (ii) traffic surrounding implementation of assistance maintenance. s mitigation measures of (usage of standard Investment equipment complying Program with CPCB Noise Consultants standard for construction equipment) and assessment of the situation through visual inspection and interviews with local

Beneficial usage of waste soil All sites Sitepeople observations; shall CC be Monthly Contractor/ (construction, land raising, infill) records PMU/ULB/PC

Waste soil removal as soon as it is All sites Site observations Weekly Contractor/ excavated. PMU/ULB/PC

Usage of tarpaulins to cover soil when All sites Site observations Weekly Contractor/ transported on trucks. PMU/ULB/PC Avoidance of narrow local roads when From STP Observations off site; CC Weekly Contractor/ transporting soil. record PMU/ULB/PC

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 88 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Avoidance of transporting soil during From STP Observations on and off Weekly Contractor/ peak traffic periods site PMU/ULB/PC Coverage or damping down Stockpiled Inhabited Site observation Weekly Contractor/ soil in dry weather. areas PMU/ULB/PC Conduction of all excavation work in the All sites Site observation Monthly Contractor/ dry season. PMU/ULB/PC Pumping groundwater from excavated STP site Site observations; farmer Monthly Contractor/ areas and provide to farmers. survey PMU/ULB/PC Leaving spaces for access between Network Site observation Weekly Contractor/ mounds of soil. sites PMU/ULB/PC Provision for planks/walkways to allow Network Site observation Weekly Contractor/ people & vehicles to cross open. sites PMU/ULB/PC trenches Removal of trees only if it cannot be All sites Site observation Weekly Contractor/ avoided. PMU/ULB/PC Plantation and maintenance of two trees All sites Observations on/off site; Monthly Contractor/ for every one removed. CC records PMU/ULB/PC * Compensation of businesses for lost Where Shopkeeper survey; As required. Contractor/ income required LSGD record. PMU/ULB/PC Increase of workforce in inhabited areas Network Site observations; CC Monthly Contractor/ to finish work quickly. sites records PMU/ULB/PC Advance information to shop keepers and Network Resident surveys; CC Monthly Contractor/ residents of work. sites records PMU/ULB/PC

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 89 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Confirmation of location of Infrastructure Network Site observation; design Monthly Contractor/ and avoid these sites. sites reports PMU/ULB/PC Location of water and sewer pipes on Network Site observation; design Monthly Contractor/ opposite sides of roads. sites reports PMU/ULB/PC Integration of subprojects to conduct Network Site observation; design Monthly Contractor/ trenching at same time. sites reports PMU/ULB/PC Work conduction during light traffic. Network Site observations; CC Monthly Contractor/ sites records PMU/ULB/PC Ensuring that police provide traffic Network Site observations; CC Monthly Contractor/ diversions when required. sites records PMU/ULB/PC Proper planning for transport routes to Network Observations off site: CC weekly Contractor/ avoid narrow streets, important or fragile sites record PMU/ULB/PC buildings, and religious and tourism sites. Proper planning of work to avoid peak Network Observations off site: CC Monthly Contractor/ traffic and main festival/tourism season. sites record PMU/ULB/PC Avoidance of using pneumatic drills near Network Observations off site: CC Weekly Contractor/ buildings at risk from vibration. sites record PMU/ULB/PC Usage of modern vehicles and machinery All sites Site observations; CC Monthly Contractor/ and proper maintenance as specified. records PMU/ULB/PC Consultation with authorities, custodians Network Site observations; CC Monthly Contractor/ of buildings, communities to address key sites records; resident PMU/ULB/PC issues and avoid working at sensitive surveys Preparation and implementation of a site All sites Site observations; CC Monthly Contractor/ H&S Plan (safety of workers/public) records PMU/ULB/PC

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 90 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Exclusion of public from the site. All sites Site observations; CC Monthly Contractor/ records PMU/ULB/PC Ensuring that workers wear Personal All sites Site observations; CC Monthly Contractor/ Protective Equipment. records PMU/ULB/PC Provision for Health and Safety training All sites CC records; worker Monthly Contractor/ for all personnel. interviews PMU/ULB/PC Following of documented procedures for All sites Site observations; CC Monthly Contractor/ all site activities. records PMU/ULB/PC Maintenance of accident reports and All sites CC records Monthly Contractor/ records PMU/ULB/PC Employ at least 50% of workforce from All sites CC records; worker Monthly Contractor/ communities near sites. interviews PMU/ULB/PC

Mitigation Measures Location Measurement Frequency Responsibility Preliminary Operation Stage C ti Baseline water quality Nallah Water quality testing for Monthly once as part ULB parameters such as pH, of Plant operation. BOD, COD, TSS, TDS, coliforms, etc. Clogging of drains Sewer Proper maintenance with Monthly once as part ULB network periodical cleaning or of Plant operation. sites scrapping of drains or desilting/ de-weeding, etc. Potential for gas explosion in Pipes – gas Sewer pipes Gas monitoring in the Monthly once as part ULB monitoring. sewerage of Plant operation. network

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 91 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Odor emission control at STP and STP and Proper operation and Sewerage System. Sewer Maintenance of the network Sewerage and STP system. • Frequent flushing or scraping.  Solid separation; keeping solid Stockpiles dry and preferably covered or compost them. • Lagoon type; aerobic lagoons produce less odor than anaerobic lagoons. • Lagoon covers. • Windbreaks to reduce airflow across lagoons. Buffer zone in the form of landscaping and earthwork shall be

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 92 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Check for contamination of groundwater/ Inlet of Analyze the wastewater Monthly as part ULB Part of O & M agricultural fields due to discharge of STP characteristics including of cost. untreated/partially treated STP effluent. heavy metals such as plant operation

Mercury (As Hg), Lead (i) Influent wastewater quality (as Pb), Cadmium (as Cd), Total chromium, (as Cr), Copper (as Cu), Zinc (as Zn) and Nickel

(ii) Treated wastewater quality at outlet Outlet of (AnalyzeNi) the Seasonal (four ULB Part of O & M discharge point of STP. STP characteristics to seasons) as cost. comply with the third party PCB disposal monitoring. standards. These include: • BOD < 30 mg/l • pH – 6.5 – 8.0 • SS < 100 mg/l Implementation of the Sludge N/a Health check up for STPYearly once ULB Part O & M Management Plan - Check for health staff cost. hazards due to sludge handling.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 93 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Emergency plan for Power supplyPumping Under emergency Whenever there is ULB Management to minimize risks on theStation and situations such as power Power (regular receiving waters. STP. failure in the pumping supply) failure. stations, diesel operated generators of suitable capacity have been proposed. In case of failure of generators, the sewage collected in the well will be pumped using diesel pump sets, conveyed by truck and properly disposed into the STP. In case of failure of screens, the sewage will be bypassed to the wet well. In STP also, generator has been provided to tackle the Detection and repairing of sewer leaks STP Site observation; farmer Monthly ULB rapidly and effectively Sale of dried inert survey sludge to farmers to fertilize land. Advance information of work to Network Resident surveys Monthly ULB shopkeepers and residents. sites

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 94 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Provision of walkways/planks for publicNetwork Site observation; resident Monthly ULB and vehicles. sites survey Requesting police to divert traffic if Network Site observations Monthly ULB necessary. sites Avoidance of usage of drills or heavy Network Site observations Monthly ULB vehicles near fragile buildings sites Completion of work quickly in sensitive Network Site observations; OMC Monthly ULB areas. sites records Consultation with communities to avoid Network Site observation; resident Monthly ULB working during sensitive periods. sites survey Preparation and operation of H&S plan to All sites. Site observations; OMC Monthly ULB Part of O & M protect workers and citizens. records cost. Economic benefits to local people- STP STP Employer record; worker Monthly ULB Part of O & M workers should be residents of survey cost. neighboring areas. Survey of chemical and bacteriological STP Water quality Monthly for ULB Part of O & M quality of STP effluent. sampling/analysis 5 years cost. Bacteriological surveys of dried STP STP Bacterial Monthly for ULB Part of O & M sludge sampling/analysis 5 years cost. Survey of public health and incidence of Gangavathi Hospital records; Annual for 6 years. ULB Part of O & M water borne disease. town. Resident survey. cost.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 95 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table 5.6: Environmental Monitoring Plan for Slums - Drainage Up gradation Mitigation Location Measurement Frequency Responsibilit Preliminary ConstructionM Stage C ti Check for dust nuisance N/a. Inspection of contract One-off IPMU documents inspection before signing the

Impact to livelihood Construction Ensure the implementation of Weeklyt t ULB with the Part of work sites mitigation measures such as assistance of construction of drains; spraying of water; assess the Investment costs situation through visual Program inspection and interviews with Consultants local people, will compensate any business losses as per the resettlement framework

Operation stage No significant Impacts envisaged. N/a. N/a. N/a. N/a. N/a.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 96 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table 5.7: Environmental Monitoring Plan for Slums - Roads Up gradation Mitigation Location Measurement Frequency Responsibility Preliminary ConstructionM C i Work sites of Incorporation of mitigation One-off IPMU IPMU staff Check for dust road measures in the contract inspection of before time as nuisance improvements documents. signing required with in the town the contract

Dust and noise Work sites of Monitoring of air quality and Weekly ULB with the assistancePart of nuisance Road noise is not required. Ensure of construction improvements the implementation of Investment Program Costs with in the town mitigation measures (usage Consultants. of standard equipment complying to Noise levels of CPCB, spraying of water to arrest dust);assess the situation through visual inspection and interviews Operation stage N/a. N/a. N/a. N/a. N/a. No significant impacts envisaged

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 97 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table: 5.8 Sample Estimated Environmental Costs

No. Item Cost ( Rs) A. Monitoring during Operation Period

I. Air monitoring 32000

II. Noise monitoring 8000

III. Water sampling , Waste water quality 60000 testing

B. Training Cost.

Program 1 4000

Program 2 4000

Program 3 4000

C. Other 1. Group discussion 5000 60000 2) Health check up for workers 177000 Total

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 98 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

CHAPTER - VI

PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

6.1 Overview

68. Public consultation is a process in which public get freedom to express their own view over a project. Public consultation is a vital in early stage of project which helps strengthening preventive measures to ensure environment sustainability and preserving public interest by taking in account their anticipated questions and introducing measures for mitigating the same.

69 public consultation hold almost in all declared slum area to overview opinion of the public and their anticipated problem enhancing mitigation measure during implementation of project to safe guard environment. It is seen that publics are most awaited for a project what NKUSIP proposed in help of ADB. During public consultation public has brought in light existing scenario of infrastructure facilities like drainage system and problem involved in system which turns in worth condition in rainy season due to bad condition. Peoples are experiences adverse effect of blocked drains in terms of generating bad smell and encouraging to increase infectious diseases due to disposal of household thinks and night soils.

70. peoples also expressed their concern on water supply scheme as many part of the slum areas has not yet covered with existing pipelines and they more depends on bore well or hand pumps to meet daily water requirement. Peoples are expressed their dissatisfaction over water supply scheme because most of the time they received sewage contaminated water which was not fit for drinking purpose, there is no consistency in pressure of water made people to keep option of bore well as well as hand pumps. Peoples demanded for surface water from Tungabhadra river which has been already supplied to other part of the town.

71 People expressed their concern over road and demanded for up gradation with RCC road as these roads put these people in trouble during rainy season. Overflow of drain on to the roads pollutes entire environment and creates unhygienic condition for residing people. Peoples living in the extension areas of town demanded for both storm water drains and roads and sanitation facility. Detailed discussion with public and reply for the same is presented in Table 6.1.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 99 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Fig: 6.1: Photos during public consultation at slum area in Gangavathi town.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 100 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Table 6.1 Public Comments & Mitigation measures SI Date Location Comments from local Proposed mitigation No. public (A) Drain works 03.11.08 Near Bus I) Construction of drains.  Dust generation shall be arrested by stand area. water spraying. Public brought in notice of  Ensure usage of standard equipment to SPAN consultant and CMC reduce the noise nuisance. Equipment Gangavathi about generation of shall comply with the noise levels of dust and noise during construction equipment laid out by the construction of drains and CPCB. High noise generating activities disturbance of daily normal including material unloading shall be traffic and demanded for proper avoided during nights. The surrounding mitigation measure minimising people shall be informed, especially in the same. densely populated area, of nature and schedule of the high noise generating

activities, if any.

 Adequate arrangements for traffic diversions including erection of proper sign boards.

 Highly Qualified contractor will be engaged to execute the work in proper way and specific conditions shall be imposed in the contract to take safety measures.

(B) Construction of Road & Street lights improvement in slum area. 04.11.08 Chelluvadiwa Public express their concern  Due care will be taken to suppress dust da slum about generation of dust and maximum extend by sprinkling of water in affect of noise by using high frequent base at work side. volume making equipment  Noise level will be in limit because of during road construction, uses of standard reputed make disturbance in normal traffic. equipments comply with all standards stipulated by Pollution Control Board Public also concern their which itself takes care of noise. concern over safety of the  Proper adequate personnel protective workers during road equipments will be provided to workers construction and providing like ear muffler, nose mask, hand gloves, lampas on poles. safety shoes etc. to ensure safety of workers.  Persons working on providing lamps on poles will made aware with dangers involves in their works and precautionary measures by providing them proper training.  Personnel protective equipment like electric resistant shoes with gloves and safety belt will be provided to avoid any kind of accidents.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 101 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

6.2 Grievance Redress Committee (GRC)

72 Grievances will first be brought to the attention of the implementing NGO. Grievances not redressed by the NGO will be brought to the grievance redress committee (GRC) established in each Investment Program district. The GRC process is designed to be transparent, gender responsive, culturally appropriate and commensurate to the risks and adverse impacts of the project, as well as readily accessible to all segments of the affected people. Affected people are to be appropriately informed about the mechanism through media and public outlets. This participatory process shall ensure that all views of the people are adequately reviewed and suitably incorporated in the design and Implementation process. 73. A District Level Project Steering Committee (DLPSC) headed by the Concerned District Commissioner (DC) has been established under the NKUSIP project vide GO: No N. A.E. 45 PRJ 04 dated 18/06/04 for 21 towns. In addition to the functions of the committee, Grievance redress was included as additional functions vide GO: No. N. A. E. 167 PRJ05 dated 22/09/05 for the same towns . Later the DLPSC was established along the function of grievance redress vide GO: No. N. A. E124 PRJ 2007, dated29/11/07, hence a grievance redress mechanism is in place for the project.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 102 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

CHAPTER - VII FINDING AND RECOMMENDATION 7.1 Findings 74. Based on the screening of environmental impacts, all the proposed sub-project components in Area are found to be environmentally acceptable and therefore able to proceed to the implementation phase. In most cases, particular environmental issues identified are those that are typical for the type of component, and a range of proven mitigation strategies exist to address them. Table 33 indicates the environmental consideration of the proposed infrastructure components. Table 7.1: Environmental Issues of Proposed Infrastructure Components Infrastructure Environmental Impact Environmental Component Issue Mitigations Drainage Appropriate upgradation • Construction impacts mitigation measures as suggested

Slum • No significant issues Appropriate Improvements • Construction and mitigation measures

75. As described above, most impacts are relevant to typical construction and operation. The Important sets of mitigation measures, which are relevant to most of the components, include preparation of activity plans using appropriate mitigation measures identified in the earlier sections. These activity plans include:

• Construction Site Management Plan (to address construction impacts); • Occupational Safety Plan (to address the health related impacts)

76. These activity plans should be prepared by the Investment Program Consultants as compendium of the relevant mitigation measures identified in earlier section. They should form part of the contractual arrangements with construction contractors, or directly implemented by the CMC as facility operator, as required ‘Work Practices’.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 103 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

7.2 Recommendations 80. It is recommended that the IPMU should be involved in monitoring the implementation of those components that are critical to acceptable environmental performance of the component. Owing to the location of proposed facilities and geographical setting of the town/region as a whole, no major impacts envisaged from any of the proposed sub- components projects in Gangavathi. In addition to the construction stage impacts, most of the impacts are typical of operation of sub-component project, i.e. impacts due to inadequate sewage treatment, toxic gas emissions from landfill site etc. These impacts could be mitigated with sound design and therefore the design stage becomes crucial. In view of this importance, the PMO is delegated with the monitoring responsibility of the design stage to ensure the environmental sustainability of the NKUSIP. Monitoring parameters have been identified for ensuring the environmental benign operation of the Investment Program.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 104 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

CHAPTER - VIII

CONCLUSIONS

The proposed Investment Program is beneficial to the environment and the society. The projects fall under the Category B of ADB's Guidelines. From this IEE, it can be understood that this Investment Program is of small-scale and does not cause any significant adverse environmental impacts and so a full scale EIA is not required. It is recommended that project can be implemented with proper mitigation measures to protect the environment. This IEE with the recommended institutional requirement and environmental monitoring plan becomes the completed EIA. This IEE for the proposed Investment Program meets all the required environmental criteria. Present status of the project study recommends only IEE for proposed project components. Therefore, no separate EIA is required.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 105 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

AAPENDIX 1: Rapid Environmental Assessment (REA) Checklist

SEWAGE TREATMENT

Instructions:

. This checklist is to be prepared to support the environmental classification of project. it to be attached to the environmental categorization from that it is to be prepared and submitted to the Chief Compliance officer of the Regional and sustainable Development Department. . This checklist id to be completed with the assistance of an Environment Specialist in a

Regional Department . This checklist focuses on environmental issue and concerns. To ensure that the social dimensions are adequately considered. Refer also to ADB checklist and handbooks on (i) involuntary resettlement (ii) indigenous peoples planning (iii) poverty reduction (iv) participation and (v() gender and development. . Answer the questions assuming the “without mitigation” case. The purpose is to identify potential impacts. Use the “remark” section to discuss any anticipated mitigation measures.

Country / project Title: India / North Karnataka Urban Sector Investment Program.

Sector Division Urban Development

………………………………………………………………………………………………

Screening Questions Yes No Remarks

B. Project Siting

Is the project area

. Densely populated √

. Heavy with development activities √

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 106 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

. Adjacent to or within any environmentally sensitive area . Cultural heritage site √

. Protected area √

. Wetland √

. Mangrove √

. Estuarine √

. Buffer zone of protected area √

. Special area for protecting biodiversity √

. Bay √

A. Potential Environmental Impact ` Will the project cause…..

. Impairment of historical / cultural √ monuments / areas and loss/ damage to the sites? . Interference with other utilities and √ During construction stage traffic blockage of access to buildings and human activities may nuisance to neighbouring areas due to affected temporarily due to noise, smell and influx of insects generation of dust and noise rodents etc? from mechanical equipments. Adequate measure will be taken by skirling of water to minimize dust and traffic management plan with sign board. Machinery with standard reputed make adopted that will itself taker care of noise.

. Dislocation or involuntary resettlement √ No any dislocation or involuntary

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 107 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

of people? resettlement envisaged in a project.

. Impairment of downstream water quality √ The proposed Facultative sludge due to in adequate sewage treatment or process system is designed to release of untreated sewage? meet the discharge norms of inland surface water as suggested by Central Pollution Control Board. It is suggested that proposed system will be properly maintained to ensure efficiency of treatment.

. Overflows and flooding of neighbouring √ Periodic maintenance of sewer properties with raw sewage. ? lines has been suggested in the EMP to avoid overflowing and flooding of neighbouring properties.

. Environmental pollution due to √ Sludge disposal will be carried inadequate sludge disposal or industrial out in frequently say once in a 2 waste discharge illegally disposed in to 3 days. Sludge disposal will sewer.? be restricted in a confined space to avoid surface and soil pollution.

. Noise and vibration due to blasting and √ Construction machineries other civil works? used in a construction will be standard reputed made comply with noise level standard prescribed by pollution control board.

. Discharge of hazardous material into √ It is suggested in EMP that sewers, resulting in damage to sewer Gangavathi CMC has to ensure system and danger to workers ? that no hazardous waste will be

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 108 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

illegally discharged in to sewer lines.

. Inadequate buffer zone around pumping √ Buffer zone with screen and and treatment plats to alleviate noise landscaping is suggested to and other possible nuisances, and provide proper shielding such protect facilities? that operation of STP will not have nuisance to surrounding.

. Social conflicts between construction √ The local labour force will be workers from other areas and utilized by the contractor for community workers? construction activities and hence there are no possibilities for social conflict regarding employment opportunities during construction phase.

. Road blocking and temporary flooding √ Road blocking and traffic re due to land excavation during the rainy routing has been envisaged season? during construction stage of sewer lines. Temporary flooding is not anticipated as there is no deep excavation or filling of low laying area envisaged in the project.

. Noise and dust construction activities? √ Construction machineries will be reputed make which will itself take care of noise moreover these machineries will be comply with standards stipulated by Central pollution Control board. Water sprinkling program will be suggested to ensure minimize of dust

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 109 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

generated.

. Traffic disturbances due to construction √ Traffic management with re material transport and waste? routine of traffic during construction period is required to avoid conflict of public transport with construction material.

. Temporary silt runoff due to √ The construction waste water construction? will be channelled such that it will have sufficient time to settle the solid and do not deteriorate water quality of discharging courses.

. Hazards to public health due to overflow √ Regular maintenance of sewer flooding and ground water pollution due line has been suggested to to failure of sewage system? avoid overflow of sewer line and related impact on public health due to pollution.

Chances of failure sewage system will be less and in extreme case care will be taken by diverting sewage in nearby nalas and rectified defects quickly to take system in working.

. Deterioration of water quality due to √ Sludge from sludge drying bed inadequate sludge disposal or direct will be removed at regular discharge of untreated sewage water? interval to avoid re – suspension in the treated water and there by deteriorating treated water

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 110 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

quality. Direct discharge of untreated sewage water is not anticipated.

. Contamination of surface and ground √ Sludge will be disposed of in a water due to sludge disposal on land? confined area the sludge disposal area should be properly lined with geosynthetic lining such that it will not leach to the nearby water courses / and pollute environment.

. Health and safety hazards to workers √ Mixing of hazardous / industrial from toxic gases and hazardous effluent with sewage may result material which may be contained in in sewer and STP which should sewage flow and exposures to be avoided through proper law pathogens in sewage and sludge? and enforcement.

The sewer cleaning and STP workers should be provided protective measures such as boots masks etc. to avoid exposure to pathogens in sewage and sludge.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 111 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

AAPENDIX 2: Rapid Environmental Assessment (REA) Checklist WATER SUPPLY

Instructions:

. This checklist is to be prepared to support the environmental classification of project. It to be attached to the environmental categorization from that it is to be prepared and submitted to the Chief Compliance officer of the Regional and sustainable Development Department. . This checklist is to be completed with the assistance of an Environment Specialist in a Regional Department . This checklist focuses on environmental issue and concerns. To ensure that the social dimensions are adequately considered, refer also to ADB checklist and handbooks on (i) involuntary resettlement (ii) indigenous peoples planning (iii) poverty reduction (iv) participation and (v() gender and development.

. Answer the questions assuming the “without mitigation” case. The purpose is to identify potential impacts. Use the “remark” section to discuss any anticipated mitigation measures.

Country / project Title: India / North Karnataka Urban Sector Investment Program.

Sector Division Urban Development

………………………………………………………………………………………………

Screening Questions Yes No Remarks

B. Project Siting

Is the project area

. Densely populated √

. Heavy with development activities √

. Adjacent to or within any environmentally sensitive area . Cultural heritage site √

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 112 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

. Protected area √

. Wetland √

. Mangrove √

. Estuarine √

. Buffer zone of protected area √

. Special area for protecting √ biodiversity . Bay √

B. Potential Environmental Impact ` Will the project cause…..

. Pollution of raw water supply from √ No such communities, industries upstream waste water discharge discharge envisage since the intake from communities, industries, point comes nearer to the suvarnavathi agriculture and soil erosion runoff. reservoir.

. Impairment of historical / cultural √ monuments / areas and loss / damage to the site . Hazard of land subsidence √ There is no ground water exploitation caused by excessive ground for proposed water supply water pumping improvements for Gangavathi CMC

. Social conflict arising from √ displacement of communities . Conflicts in abstraction of raw √ Since the water is drawing from Kabini water for water supply with other ( Kaveri) river basin, there will not be beneficial water uses for surface any water scarcity at any point of time. and ground waters? . Unsatisfactory raw water sup[ply ( √ Because of river is perennial no such e.g. excessive pathogens or pathogens and mineral constituents mineral constituents ?

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 113 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

problem envisaged.

. Delivery of unsafe water to √ distribution system . Inadequate protection of intake √ The exiting intake exist at kabini river is works or wells leading to pollution in good condition, so there are no of water supply? possibilities of pollution due to inadequate protection of intake works or wells.

. Over pumping of ground water, √ There is no ground water exploitation leading to Stalinization and required for the proposed ground subsidence? improvements in water supply.

. Excessive algal growth in storage √ Gangavathi CMC has to ensure that reservoir? the storage reservoir will be cleaned regularly to avoid excessive algal growth.

. Increase in production of sewage √ The proposal involves ensuring regular beyond capabilities of community supply of 135 lpcd excluding losses for facilities? the public which neither will nor result in excess sewage production. The proposed STP for the city is designed to meet the sewage generated with 108 lpcd.

. Inadequate disposal of sludge √ There is no such proposal of altering from water treatment plants? design and facilities in water treatment plant. It is prime duty of Gangavathi CMC to ensure that the sludge is removed from water treatment plants regularly to meet standard of treated water.

. Inadequate buffer zone around √ Sufficient buffer zone / noise barrier is pumping and treatment plants to to be developed around pumping

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 114 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

alleviate noise and other possible station to alleviate noise. nuisance and protect facilities . Impairments associated with √ Temporary impairments are anticipated transmission lines and access along the new transmission lines roads? routes during construction stage .No new access is proposed.

. Health Hazard arising from √ Proposed project seen to be not have inadequate design of facilitate for any proposal for altering design / receiving , storing, and handling facilities in water treatment plant. of chlorine and other hazardous chemicals . Health and safety hazards to √ Gangavathi CMC has to ensure that workers from the management of proper safety practices are ensured for chlorine used for disinfection and workers in water treatment plant. other contaminants? . Dislocation or involuntary √ There is no resettlement of people for resettlement of people project implementation.

. Social conflict between √ Local labour will be utilized in construction workers from other maximum number by contractor so areas and community workers? possibility of social conflict regarding employment opportunities will be less during construction stage

. Noise and dust from construction √ Measures will be taken in initial stage activities of project by deploying standard reputed make machinery with comply of stipulated noise standard to ensure noise with in limit and practice of frequent water spraying will be adopted to minimize dust.

. Increased road traffic due to √ The construction material transport will interference of construction increase traffic within city. Proper traffic activities? management will have to be

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 115 NKUSIP (Package IV – Bellary) Tranche II Sub Projects in Gangavathi Town IEE Report ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

implemented to avoid conflict between public transport and construction material transport.

. Continuing soil erosion / silt runoff √ Construction debris and excess soil from construction operation generated at construction site should be properly disposed to avoid erosion.

. Delivery of unsafe water due to √ Gangavathi CMC has to ensure poor o & m treatment process ( efficiency of operation of water especially mud accumulation in treatment plant. filter ) and inadequate chlorination due to lack of adequate monitoring of chlorine residual in distribution system . Accidental leakage of chlorine √ gas? . Excess abstraction of water √ affecting downstream water users . Competing uses of water √

. Increased sewage flow due to √ The proposal is for ensuring regular increased water supply water supply of 100 lpcd for the public which will result in increased sewage generation. The propose STP for the city is designed too meet the sewage generated with 100 lpcd.

. Increased volume of sullage ( √ The proposed STP for the city is wastewater from cooking and designed to meet the sullage washing ) and sludge from waste generated due to project. Gangavathi water treatment plant CMC has to ensure that the sludge generated in STP is disposed off with safe disposal practices.

Span Consultants Pvt. Ltd. In association with Ramky Infrastructure Pvt. Ltd 116