Involuntary Resettlement Assessment and Measures

Resettlement Plan for AEP 8: 31A and 31B (–Tavaragere––Gangawathi) Document Stage: Draft for Consultation Project Number: 42513 August 2010

IND: State Highway Improvement Project

Prepared by Public Works Department, Government of Karnataka.

The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

i

TABLE OF CONTENTS ABBREVIATIONS ……………………………………..iv EXECUTIVE SUMMARY ……………………………...... vi 1 PROJECT DESCRIPTION ...... 1 1.1 BACKGROUND ...... 1 1.2 OBJECTIVES...... 1 1.3 PHYSICAL CHARACTERISTICS OF THE PROJECT AREA...... 4 1.4 PROJECT COMPONENTS ...... 4 1.5 ROAD CONFIGURATION:...... 4 1.6 REALIGNMENT / BYPASSES: ...... 4 1.7 BRIDGES AND OTHER CROSS DRAINAGE STRUCTURES:...... 4 1.8 ROAD SIDE DRAINAGE:...... 5 1.9 RAILWAY OVER BRIDGES (ROBS): ...... 5 1.10 JUNCTIONS / INTERSECTION IMPROVEMENTS: ...... 5 1.11 SERVICE ROADS AND UNDERPASSES:...... 5 1.12 WAY SIDE AMENITIES / TOLL PLAZA / TRUCK PARKING, ETC.: ...... 5 1.13 MAGNITUDE OF IMPACTS...... 5 1.14 MINIMIZING IMPACTS...... 6 1.15 DESIGN CROSS SECTIONS...... 6 1.16 MITIGATION THROUGH DESIGN CROSS SECTION...... 7 1.17 ROAD SAFETY AND TRAFFIC MANAGEMENT MEASURES ...... 7 1.18 MAGNITUDE OF IMPACTS CULTURAL PROPERTIES AND CPRS ...... 8 1.19 IMPACT OF THE PROJECT ...... 8 1.20 RIGHT OF WAY AND CORRIDOR OF IMPACT...... 9 2 METHODOLOGY FOR IMPACT ASSESSMENT ...... 10 2.1 SOCIAL IMPACT ASSESSMENT ...... 10 2.2 APPROACH TO RESETTLEMENT PLANNING...... 10 2.3 CENSUS SOCIOECONOMIC SURVEY...... 11 2.4 METHODOLOGY AND DATABASE...... 11 2.5 SOURCES OF DATA...... 12 3 SOCIOECONOMIC INFORMATION AND PROFILE...... 13 3.1 SOCIO ECONOMIC PROFILE OF THE PROJECT AREA ...... 13 3.2 SOCIO ECONOMIC PROFILE OF DISPLACED POPULATION...... 13 3.3 VULNERABLE GROUPS...... 16 3.4 GENDER ISSUES...... 16 3.5 INDIGENOUS PEOPLE...... 17 4 SCOPE OF LAND ACQUISITION AND RESETTLEMENT...... 18 4.1 PROPOSED LAND ACQUISITION ...... 18 4.2 ESTIMATED TIME FOR LA ...... 19 4.3 MANAGING LAND ACQUISITION...... 19 4.4 STAFFING FOR LAND ACQUISITION WORK...... 19 4.5 NEGOTIATIONS COMMITTEE FOR LAND PRICE FIXATION AND DETERMINATION OF REPLACEMENT COST ...... 20 4.6 NEGOTIATION COMMITTEE ...... 20 4.7 METHOD OF PRICE FIXATION...... 20 4.8 FAILURE OF KHA AND APPELLATE COMMITTEE...... 21 4.9 VALUATION OF ASSETS...... 21 4.10 CUT-OFF DATE ...... 21 4.11 ESTIMATION OF LAND REQUIREMENT AND PREPARATION OF LAND ACQUISITION PLANS22 4.12 COMPENSATION PAYMENT PROCESS ...... 22 4.13 ADMINISTERING THE PAYMENT OF R & R ASSISTANCE ...... 22 5 STAKEHOLDERS CONSULTATION, PARTICIPATION AND DISCLOSURE ...... 24 5.1 CONSULTATION AND COMMUNITY PARTICIPATION...... 24 5.2 METHODOLOGY...... 24

ii

5.3 KEY FINDINGS OF THE CONSULTATIONS ...... 24 5.4 LEVELS OF CONSULTATION ...... 27 5.5 CONSULTATIONS DURING IMPLEMENTATION...... 27 5.6 DISCLOSURE ...... 28 6 LEGAL FRAMEWORK ...... 30 6.1 THE NATIONAL POLICY ON RESETTLEMENT AND REHABILITATION FOR PROJECT AFFECTED HOUSEHOLDS, 2007 ...... 30 6.2 THE LAND ACQUISITION (LA) ACT OF 1894 ...... 31 6.3 ASIAN DEVELOPMENT BANK’S SAFEGUARD POLICY ...... 31 6.4 INDIGENOUS PEOPLES...... 33 6.5 KARNATAKA HIGHWAY ACT 1964 ...... 33 6.6 COMPARISON OF NATIONAL AND STATE POLICIES WITH ASIAN DEVELOPMENT BANKS SPS -2009...... 33 7 ENTITLEMENTS, ASSISTANCE AND BENEFITS ...... 35 7.1 KSHIP POLICY...... 35 7.2 IMPACTS AND ENTITLEMENTS...... 35 7.3 CORRIDOR OF IMPACT ...... 35 7.4 TARGETED SUPPORT TO VULNERABLE GROUPS ...... 36 7.5 OPTION AND CHOICES ...... 36 7.6 PRINCIPLES...... 36 7.7 DEFINITIONS...... 36 7.8 ENTITLEMENTS...... 38 7.9 ENTITLEMENT MATRIX ...... 42 8 RELOCATION OF HOUSING AND SETTLEMENTS ...... 48 8.1 BASIC PROVISION FOR RELOCATION ...... 48 8.2 NEED FOR RELOCATION...... 48 8.3 DEVELOPMENT OF VENDOR MARKETS ...... 48 8.4 ENVIRONMENTAL ASPECTS...... 48 8.5 SOCIAL ASPECTS ...... 48 8.6 RECONSTRUCTION OF AFFECTED COMMUNITY STRUCTURES ...... 49 9 INCOME RESTORATION AND REHABILITATION...... 50 9.1 INCOME RESTORATION MEASURES ...... 50 9.2 IMPACT CATEGORIES AND IR SCHEMES ...... 50 9.3 IR ACTIVITIES...... 50 10 RESETTLEMENT BUDGET AND FINANCING...... 52 10.1 BUDGET AND COSTS ...... 52 11 GRIEVANCE REDRESSAL MECHANISM...... 55 11.1 GRIEVANCE REDRESSAL COMMITTEE...... 55 FIGURE 11-1: GRIEVANCE REDRESSAL ...... 56 12 INSTITUTIONAL MECHANISMS...... 57 12.1 INSTITUTIONAL ARRANGEMENTS ...... 57 12.2 SOCIAL DEVELOPMENT AND RESETTLEMENT CELL (SDRC...... 57 12.3 SDRC AND STAFF DEPLOYMENT ...... 57 12.4 PROTECTION OF ROW...... 60 12.5 VALUATION OF OTHER STRUCTURES/ASSETS ...... 60 12.6 ROLES AND RESPONSIBILITIES OF OFFICIALS FOR RP IMPLEMENTATION...... 60 12.7 COMPETENT AUTHORITY FOR VARIOUS APPROVAL ...... 65 12.8 IMPLEMENTATION SUPPORT BY NGOS...... 65 12.9 DATABASE MANAGEMENT ...... 66 13 IMPLEMENTATION SCHEDULE ...... 68 13.1 COORDINATION WITH CIVIL WORKS AND CERTIFICATION ...... 68 13.2 IMPLEMENTATION SCHEDULE AND TIMING OF RESETTLEMENT...... 68 13.3 CAPACITY BUILDING AND TRAINING ...... 70 14 MONITORING AND REPORTING ...... 71 14.1 MONITORING ...... 71 iii

14.2 INTERNAL MONITORING ...... 71 14.3 EXTERNAL MONITORING...... 71 15 TYPE OF GATE ...... 86 16 PART-III...... 93 17 FOR TENANTS ...... 94 18 EXTENT OF LOSS...... 98 18.1 COMMUNITY ASSET SCHEDULE...... 100 III. CONDITION OF SERVICES ...... 138 3. Data, Services and Facilities to be provided by the Client ...... 140 BANK GUARANTEE OF 10% CONTRACT VALUE SHALL BE VALID UP TO TIME PERIOD SPECIFIED IN C 1.2.3 OF SPECIAL CONDITIONS OF CONTRACT...... 141 6. TEAM FOR THE ASSIGNMENT ...... 141

LIST OF TABLES Table 1-1: Summary Tables on Impacts ...... 5 Table 2-1: Distribution of DHs...... Table 3-2: Religion...... 13 Table 3-3: Occupation Distribution...... 13 Table 3-4: Income Distribution ...... 14 Table 3-5: Age Classification ...... 14 Table 3-6: Literacy ...... 15 Table 3-7: Type of Structure ...... 15 Table 3-8: Affected Households by Gender...... 16 Table 4-1: Land Acquisition Details ...... 20 Table 5-1: Key Issues: T13 – Jagalur – NH 13 ...... 25 Table 6-1: Comparison of gaps in various Acts and Policies with ADBs SPS ...... 34 Table 7-1: Entitlement Matrix ...... 42 Table 9-1: Categories for Income restoration ...... 50 Table 10-1: Budget ...... 52 Table 10-2: Unit Costs for R & R ...... 53 Table 10-3: R & R Unit Costs...... 53 Table 12-1: Administrative and Financial Responsibilities of officials and Agencies for RP Implementation ...... 60 Table 12-2: Competent Authority for Approvals...... 65 Table 13-1: R & R Implementation Schedule...... 69 Table 13-2: In house Training programme...... 70 Table 14-1: Monitoring Indicators for Physical Progress ...... 72 Table 14-2: Financial Indicators for Progress ...... 73 Table 14-3: Monitoring Of GRC ...... 73

LIST OF FIGURES Figure 1-1: KSHIP Roads ...... 3

ANNEXURE ANNEX 1: Typical Road Cross Section ANNEX 2: Details of Community Assets ANNEX 3: Census and Community Asset Survey Schedules ANNEX 4: Details of Land Acquisition ANNEX 5: Structure Details ANNEX 6: List of Participants For Meeting and Photographs ANNEX 7: NGO ToR ANNEX 8: Monitoring and Evaluation Consultants ToR

iv

ACRONYMS ADB Asian Development Bank AC Assistant Commissioner ADSW Assistant Director Social Welfare APL Above Poverty Line BP Bank Policy BPL Below Poverty Line CAO Chief Administrative Officer CPO Chief Project Officer CPR Common Property Resources COI Corridor of Impact DC Deputy Commissioner DH displaced household DP displaced person DPR Detail Project Report EWS economically weaker section FGD focus group discussion GOI Government of GOK Government of Karnataka GRC Grievance Redressal Cell HPCFRRI High Power Committee for Redressal of Regional Imbalances HDM Highway Design Module ID Identity Card IPDP Indigenous People Development Plan IR Income Restoration ITI Industrial Training Institute KHA Karnataka Highways Act KSHIP Karnataka State Highways Improvement Project LAA Land Acquisition Act LAO Land Acquisition Officer LAP Land Acquisition Plan MRR Manager Rehabilitation andResettlement NH National Highway NGO Non-Governmental Organization NRRP National Resettlement and Rehabilitation Policy PSA Poverty and Social Assessment PA Project Authority PIU Project Implementation Unit PGB Project Governing Body PHC Primary Health Center PWD Public Works Department PU Pre University PGB Project Governing Body RTC Record of Rights R & R rehabilitation and resettlement RP resettlement plan ROW right of way SIA social impact assessment SDO Social Development Officer SDRC Social Development Resettlement Cell v

SWI Social Welfare Inspector SC Scheduled Caste SR Schedule of Rates ST Scheduled Tribes ToR Terms of Reference UR Upgrading ZP Zilla Panchayat

vi

E. EXECUTIVE SUMMARY E1. Project Description 1. The Public Works Department, Government of Karnataka is implementing Karnataka State Highways Improvement Project (KSHIP). Under this Project, 613.03 km of State Highways roads have been identified for project assistance under Asian Development Bank. The 615.03 km of roads has been divided into nine packages. The aim of the project is to improve the performance of the State’s road transport network by improving road conditions and capacity, and to improve the State’s capacity to plan, develop and maintain the Karnataka roads network. This project is Package AEP 8 comprising of two links: 31A (Mudgal to Tavaragere) is 31.21 km in and districts and 31B (Tavaragere to Gangawathi) is 42.89 km in . 2. The scope of work involves upgrading works of existing single-lane and intermediate- lane roads to 12 m roadway with standard two-lane seven-meter carriageway and alignment improvements to relevant IRC standards and other associated road and bridge works including improvement of major and minor bridges, culverts, road intersections, drains, road geometrics and road furniture. 3. The proposed project can be viewed as boosting economic growth and poverty reduction which will bring substantial social and economic development in the region. The social benefits arising due to the project will be triggered off due to improved accessibility to various services such as easy access to markets, health facilities, schools, workplace which in turn increases the income of the region, and ultimately elevating their standard of living. Although various positive project impacts and benefits are expected from the proposed project as mentioned above, there will be some negative impacts on the people living in the immediate project area. 4. The aim of this Resettlement Plan (RP) is to mitigate negative impacts caused due to the project and resettle the displaced persons and restore their livelihoods. This Resettlement Plan has been prepared on the basis of census survey findings and consultation with various stakeholders. The plan complies with ADB Safeguard Policy Statement-2009. E2. Socioeconomic Information and Profile 5. Scheduled Caste and Scheduled tribe households each account for 10% of the total population; the remaining are from the general category. Among religious groups, Hindus dominate with 86%, the remaining account for Muslims. Distribution of displaced persons (DPs) by occupation reveals that agriculture accounts for 43.81%; the other sector, which supports a large section of DHs, is represented by trade/commerce accounting for 43.81%. Agriculture labour accounts for 6.68%. In spite of difficulties in getting reliable data on household income, efforts were made to persuade the respondents to report as accurate data as possible. 13.86% of the population has income less than Rs.26,000. Scheduled Tribes (ST) households earning less than Rs.26,000 account for 12.5% of the ST population. The income information has been segregated for ST, SC and general category. Age classification shows 72.99% of the total DPs fall in the age group of 18-59. Since this happens to be the working age-group, the mitigation measures as given in the entitlement matrix need to be carefully implemented with reference to vii

18-59 age groups. Illiterate population accounts for 21.47% of the surveyed population. Just literate population accounts for 18.28% of the total population, while primary accounts for 16.75% of the total population; those with Middle school education account for 12.36% of the total population; those with education up to secondary level accounts for 16.35% of the total population. Graduates account for 3.39%. Of the residential structure getting affected, 29.49% are pucca. Amongst commercial structures getting affected, only 2.40% of the structures are pucca. Majority (63) of the commercial structures getting affected are pan/cigarette shops, followed by 39 tea stalls. Of the total residential structures getting affected, 88.46% have electricity, while 13% have access to piped water. Among household assets, 11.50% of the households have television, 3.77% own two/four wheelers, 3.03% having cooking gas, 6.37% have telephones, and only 1.30% have refrigerators. Amongst agricultural equipment, 11.76% own tractors, 7.35% own harvesters, and 10.29% have their own sprayers. 6. The vulnerable group includes persons who are physically challenged, widows, or above sixty years of age who are not provided or cannot immediately be provided with alternative livelihood and who are not otherwise covered as part of a household. These persons are entitled to assistance to include in government pension schemes, if not yet included and if eligible as per Government criteria, (OR) lump-sum amount of Rs. 25,000. There are some DPs that are in more than one vulnerable category. These DPs will be paid only once. There are 48 widows, 13 physically challenged persons and 149 persons over 60 years. There are 48 women-headed household identified. E3. Scope of Land Acquisition and Resettlement 7. Census socioeconomic surveys were conducted for a Corridor of Impact between 16 m and 22 m keeping in view the design requirements. Land acquisition for the project is estimated at 5.21 acres of private land which needs to be acquired. No government land is getting affected. According to the census survey, there are 526 displaced households (DHs) and 1,618 DPs. The project will impact 161 community structures. There is no impact on archaeological sites. All community structures will be relocated by the project authorities before demolition. 8. The summary project impacts are presented below. Table E-1: Summary of Project Impacts Impacts No. 1 Land Acquisition 5.21 Acres 2 Total no. of owners losing land 148 3 Total no. of private structure affected 350 4 Total No. of CPRs 161 5 Total no. of DPs 1618 Source: Census Survey, KSHIP Project, 2009-10

viii

E4. Stakeholders Consultation, Participation and Consultation 9. Consultations with various stakeholders were carried out during various phases of project preparation. During consultations people said that they have not been compensated for the land acquisition done earlierfor the existing road. Project Authority should also give the compensation for the acquisition done earlier, they are still paying tax for land which has already been acquired; they wanted to know the compensation for the loss of bore well, they did not want their bore well to be affected; people wanted to know how nontitleholders with shops will be compensated; people said government rate given for land is low, they wanted market rate to be given for the land; bore wells are a major issue - their bore well, is yielding good water, is getting affected. Similar water yield will not be found in other bore wells. If the bore well is affected, the farmers will suffer; in a flour mill which is getting affected there are 4 workers, they should also be compensated; people said even if 2-3 houses are affected, the PA should develop the new houses like a Resettlement colony and and not only in the case of 20 houses; people asked for equal assistance for all those who are losing their shops; people said that compensation should be paid before the start of construction ; some said the project should maintain the road as it is. In reposnse it was explained for any issue regarding land it can be taken up with DCs office. For all issues regarding compensation the entitlement matrix was explained. 10. To keep transparency in planning and for further active involvement of stakeholders the project information will be disseminated through disclosure of resettlement planning documents. The project authority (PA) will submit the resettlement plan (RP) to ADB for disclosure on ADB’s website. 11. The PA will provide relevant resettlement information, in a timely manner, in an accessible place in , to the affected persons and other stakeholders. A Resettlement and Land Acquisition information leaflet containing information on compensation, entitlement and resettlement management adopted for the project will be made available in Kannada and distributed to DPs. E5. Legal Framework 12. The Government of Karnataka (GOK) will adopt a Resettlement and Rehabilitation (R & R) Policy for KSHIP to address the adverse impacts arising out of this project in the line with the National Resettlement and Rehabilitation Policy 2007. The policy adopted for the project is consistent with ADB’s Safeguard Policy Statement. This RP is prepared in accordance with the stipulations and guidelines provided in Public Works Departmental Code Government of Karnataka , and the project specific Resettlement and Rehabilitation: - Principles and Policy Framework for the Karnataka State Highways Improvement Project, The National Resettlement and Resettlement Policy 2007 and ADB’s Safeguard Policy Statement SPS -2009. In addition to the above measures, realizing the need of infrastructure development like roads in timely manner, the Public Works Department (PWD)-GoK has decided to acquire the land through the legislation called “The Karnataka Highways Act 1964”(KHA,1964). The KHA, 1964 provides the opportunity to acquire the land through consent award. It is expected that land acquisition under this Act will help the DPs to receive the market price/replacement cost of land as compensation. ix

The GOK has already initiated the process of establishing the Negotiation Committee. The role of the committee will be to negotiate the price of land with the beneficiary. The guidance value of the land will be considered for negotiation. Minimum negotiated price for the Districts of Urban, Bangalore Rural, Chikkaballapur, , Ramnagaram, , Davangere, Belgaum and Dakshin Kannada will be one and half times the Guidance Value. For all the other districts other than those mentioned the minimum price will be twice the guidance value.

E6. Entitlements, Assistance and Benefits 13. The Project Entitlement policy addresses the direct and indirect impacts of project construction and operation on displaced persons, households and communities. The most direct and immediate impacts are those associated with project construction, mainly land acquisition. Other losses include loss of shelter, and other assets within the project’s corridor of impact, as well as roadside structure, business establishments, and public facilities. Mitigation is provided through compensation and assistance to project displaced persons, households, and groups. These social units are entitled to compensation and assistance on the basis of this policy framework adopted by the project. The policy provides mitigation for: • loss of assets, including land and house or workplace; • loss of livelihood or income opportunities; and • Collective impacts on groups, such as loss of community assets, common property resources, and others. 14. Compensation eligibility is limited by a cut-off date. The cut-off date for non- titleholders, is the date of the start of the census survey on a particular link. The cut-off date for the Link 31A is 1 August 2009 and Link 31B is 12 January 2009. The project Entitlement Matrix (Table E-2) identifies and lists various types of losses resulting out of the project and specific compensation and resettlement packages for each category.

Table E-2 Entitlement Matrix No. Impact Entitlements Remarks Category I. Title Holders (a) Loss of land 1. Compensation as per the • Stamp duty and registration principle of replacement cost charges are applicable to through direct negotiation as those who accept negotiation provided for in the Karnataka price. State Highway Act, 1964 + stamp duty and registration charges; • Minimum negotiated price for

2. Compensation offered is cash the Districts of Bangalore Urban, for land; Bangalore Rural,

3 As per the NRRP-2007 the acquiring body has to provide rehabilitation grant equivalent to 750 days minimum agricultural wages. At present the minimum agricultural wages is Rs. 100/day. The NGO will ascertain the actual needs of the displaced persons and assist in creating assets.

x

No. Impact Entitlements Remarks Category Chikkaballapur, Ramnagaram, and Corporation / Municipal limits of other district HQs will be 1.5 times the Guidance Value. For all other areas other than those mentioned above the minimum negotiated price will be 2 times the Guidance Value.1 OR average sales statistics, which ever is higher.2

3. In case of severance of land an additional 25% compensation will be paid to the land loser if he retains the remaining plot OR if the remaining land is not viable and the land owner opts to surrender the entire plot to the project, compensation as given in No. 1 will be applicable;

4. Loss of perennial crops and non-perennial crops will be compensated in accordance with Horticulture department valuation process, which is the replacement cost;

5. A grant of Rs. 15,000 for replacement of Cattle shed;

6. Water yielding bores will be replaced in the location identified by the affected person in the remaining land holding subject to availability of water. In case water is not available replacement cost of the borewell at current PWD

4 Bagar Hukum lands are government lands which are unauthorizedly cultivated by persons without legal documents. Applications for regularization that are pending before the regularization committee. 1 Revised Guidance Value of the properties in Bangalore Urban, Bangalore Rural, Chikkaballpur, Ramanagaram and Corporation/Municipal limits is 2-3 times higher than the earlier Guidance Value. Hence 1.5 times the Guidance Value is proposed as minimum negotiated price. In other areas ratio of revision is reasonably low, hence 2 times the Guidance Value is proposed as minimum price. 2 The average Sales Statistics is in line with LA Amendment Bill. In the LA Amendment Bill there are different modalities in determining and assessing the market value, any one among them would be adopted wherein the land loser gets the maximum market value. xi

No. Impact Entitlements Remarks Category SR rates without depreciation charges and 30% solatium will be given; • Marginal farmer is defined as those left with 1 hectare of 7. In case of land owners who non-irrigated or 0.50 hectare become landless or marginal of irrigation or combination of farmers, the following both; additional entitlements will be offered: (a) subsistence allowance of Rs. 30,000 for land less and marginal; and, (b) assistance for creating Income generation asset valued up to Rs.75,0003; • Narrow stretch of land is defined as persons losing an 8. Additional amount of Rs. area that is up to 5 guntas of 20,000 will be restricted to land. those who lose narrow stretch of land as ex gratia compensation in lieu of all other benefits; • The NGO engaged for the RP implementation will 9. For those becoming landless ensure linkages of the and all marginal farmers trained persons to ongoing training assistance will be programs, to facilitate provided for income generating employment and marketing vocational training and skills opportunities. upgrade options as per affected the displaced persons' choice;

10. Employment opportunity for affected the displaced persons as per his/her skills and the availability of suitable work in road construction work; • Any Government land which 11. In case of Bagar Hukum lands4 is unauthorizedly occupied - 50% of compensation and by a person and such person other benefits are available for has applied for regularization land owners which is of the same under the equivalent to replacement Karnataka Land Revenue value for this category. Rules under 108 C(1) is called Bagar Hukum land. Under Rule 108C section 94A, of the Karnataka Land Revenue Act,1966, the Tahsildar is the custodian of the records and he will issue the certification whether the application is pending before the Committee or not. Tahsildar is the Secretary of

xii

No. Impact Entitlements Remarks Category the Committee for regularization of unauthorized occupation of government land.

(b) Loss of 1. Compensation at current PWD • In case more than 25% of a Residential scheduled rates without house is affected and structures depreciation and 30% solatium unviable for retaining, full at replacement cost; compensation will be paid. 2. Alternative houses in • Resettlement colonies will be resettlement colony or developed if more than 20 developed plot and households are displaced in construction cost of Rs. 40,000 2 km continuous stretch. linked to construction progress; • Plot size will be equivalent to 3. Additional 25% of current PWD size lost subject to a SR rates without depreciation + maximum of 369 sq 30% solatium for the affected m/1200sq ft in rural area and portion as compensation for 184 sq m /600 sq ft in urban partially affected structures areas. towards reconstruction; • Displaced persons have a 4. Shifting assistance of Rs. right to salvage the affected 10,000; materials. 5. Subsistence allowance of Rs. 30,000. (c) Loss of 1. Compensation at current PWD • Shopping units with 100-150 commercial scheduled rates without sq ft will be constructed if structures depreciation and 30% solatium more than 20 shops are at replacement cost; affected in a continuous 2. Alternative shop or assistance stretch of 2 km and the for income generating asset owners opt for a shop. valuated up to Rs. 75,000; • Displaced persons have a 3. Additional 25% compensation right to salvage the affected for partially affected structures; materials. 4. Shifting assistance of Rs. • Training for self-employment 10,000; will be provided to one adult 5. Subsistence allowance of Rs. per household as needed. 30,000.

(d) Loss of 1. Compensation at current PWD • In case more than 25% of residential scheduled rates without house is affected and cum depreciation and 30% solatium unviable for retaining, full commercial at replacement cost; compensation will be paid. structures 2. Alternative shop or assistance • Resettlement colonies will be for income generation asset developed if more than 20 valuated up to Rs. 75,000; households are displaced in 3. Additional 25% compensation 2 km continuous stretch. for partially affected structures; • Plot size will be equivalent to 4. Shifting assistance of Rs. size lost subject to a 10,000; maximum of 369 sq 5. Subsistence allowance of Rs. m/1200sq ft in rural areas 30,000; and 184 sq m. /600 sq ft in 6. Additional amount of Rs. urban areas. 25,000 as grant. • Shopping units with 100-150 xiii

No. Impact Entitlements Remarks Category sq ft will be constructed if more than 20 shops are affected in a continuous stretch of 2 km and the owners opt for a shop. • Displaced persons have a right to salvage the affected materials. • Training for self-employment will be provided to one adult per household as needed.

II. Tenants (a) Residential 1. Rental allowance for 6 months at Rs. 500 per month in rural and Rs. 1,000 in urban areas; 2. Shifting assistance of Rs. 10,000. (b) Commercial 1. Rental allowance for 6 months at Rs. 1,000 per month in rural and Rs. 1,500 in urban areas; 2. Shifting assistance of Rs. 10,000; 3. Assistance for income generation asset up to Rs. 75,000. (c) Loss of 1. Rental allowance for 6 months residential at Rs. 1,000 per month in rural cum and Rs. 1,500 in urban areas; commercial 2. Shifting assistance of Rs. structures 10,000; 3. Assistance for income generation asset up to Rs. 75,000. III. Non-Title holders (a) Residential 1. House in resettlement colony 1. House plot size in Squatters or developed plot and resettlement colony to be construction cost of Rs. 40,000 minimum of 25 sq m/270 sq linked to construction progress; ft. Resettlement colony will 2. Subsistence allowance of be constructed if more than Rs.15,000; 20 residential squatters are 3. Shifting Allowance of Rs.5,000. getting affected in a continuous stretch of 2 km and opted for same. As per NRRP 2007. 2. Developed plot size will be allotted of 25 sq m/ 270 sq ft in urban area and 33 sq m /350 sq ft in rural area as per NRRP 2007.

(b) Commercial 1. Alternative shop of 100 sq ft or 3. Shopping units will be

xiv

No. Impact Entitlements Remarks Category Squatters assistance for income constructed if more than 20 generatinon asset valuated up shops are affected in a to Rs. 30,000; continuous stretch of 2 km 2. Subsistence allowance of and opted for shop. Rs.15,000; 3. Shifting Allowance of Rs.5,000. (c) Encroachers 1. Replacement cost of affected structure calculated at current PWD scheduled rates without depreciation; 2. Compensation of crop loss or advance notice for harvesting crops. IV. Loss of livelihood (a) Loss of 1. Subsistence allowance of Rs. • Training for self-employment primary 15,000; will be provided to one adult source of 2. Training assistance will be per household as needed. income provided for income generating vocational training and skills upgrade options as per the displaced persons' choice; 3. Employment opportunity for the displaced persons as per his/her skills and availability of suitable work in the road construction. V. Vulnerable People (a) Widows 1. Assistance to include in • This will be restricted to Physically government pension schemes if those who have no or cannot challenged not included , if eligible as per be provided with alterative and those Government criteria; (OR) livelihood sources. aged above 2. Lumpsum amount of Rs. 25,000 • Training for those above 60 60 years 3.Training assistance will be years is not mandatory and provided for income generating will be provided for if the vocational training and skills person opts for it and after upgrade options as per the the need is assessed. displaced persons' choice.

VI. Community Assets (a) Community 1. Reconstruction of affected Assets assets; 2. Transfer to Local authorities for maintenance. VII. Unidentified Impacts (a) Unidentified 1. Unforeseen impacts shall be Impacts documented and mitigated based on the principles provided in this policy.

Note: All amounts in this entitlement matrix are fixed as of April 01, 2010. These will increased 10% annually on first day of April every year. The same will hold good for guidance value also if not revised by the GoK.

xv

E7. Relocation of Housing and Settlements 15. Wherever there is a loss of residential structure, the PA will provide for alternative house. The alternative house will be provided in consultation with the displaced person. The Project Authority (PA) will provide compensation for the affected structure without depreciation, adequate compensation for partially damaged structures, and relocation assistance, according to the Entitlement Matrix. The entitlements to the non-titleholders will be given only if they occupied the land or structures in the project area prior to the cut-off date. There are 16 houses, 102 commercial structure and 2 residential cum commercial structure which have to be relocated. The identification of land for relocation will be done by the PIU in consultation with the DP. People prefer resettlement within the village to avoid disruption of community life and problem with host community. E8. Income Restoration and Rehabilitation 16. The DPs losing their livelihoods includes titleholders losing land, DPs having commercial structures, and employees of the affected structures. In the case of economically displaced persons, the PA will compensate for the loss of income or livelihood sources. The PA will also provide assistance such as, training, and employment opportunities so that they can improve, or at least restore, their income-earning capacity, production levels, and standards of living to pre- displacement levels. 17. The entitlement proposed for the project has adequate provisions for restoration of livelihood of the affected communities. The focus of restoration of livelihoods is to ensure that the DPs are able to at least regain their previous living standards. To restore and enhance the economic conditions of the DPs, certain income generation and income restoration programs are incorporated in the RP. To begin with providing employment to the local people during the construction phase will enable them to benefit from the project and keep more of the resources spent on the project in the local economy. It will also give the local communities a greater stake and sense of ownership in the project. The implementing NGO will carry out need assessment and micro plan with training or linking to ongoing income generation training programs and assist in rehabilitation of DPs. E9. Resettlement Budget and Financing Plan 18. The costs used for the budget estimates are based on information collected during the census socioeconomic surveys of DPs. The estimated total budget for the implementation of RP is Rs. 61.76 million. The resettlement cost estimate for this project includes eligible compensation and resettlement assistance. It does not include Operating Costs, NGO and Monitoring Consultant Costs as these costs are for the overall project( this has been estimated Rs. 20 million for the total project). The unit cost for land and other assets in this budget has been derived through consultation with Social Development Resettlement Cell (SDRC/PIU).. Contingency provisions have also been made to take into account variations from this estimate. A summary R & R cost is given in Table E-3.

xvi

Table E-3 R & R Budget Item (in Rs) 1 Compensation for land 5210000.00 2 Alternative site cost 6810000.00 3 Compensation for private structure 14755549.00 4 R & R Assistance 229376500.00 5 Contingency (10%) 5615205.00 6 Total 61,767,254.00

E10. Grievance Redress Mechanisms 19. The project will establish a Grievance Redressal process, with district-level committees. Each District Grievance Redressal Committee (GRC) will have representation from the local affected population and the NGOs involved in RP implementation. These committees will hear complaints and facilitate solutions; and the process, as a whole, will promote dispute settlement through mediation to reduce unnecessary litigation. The Deputy Commissioner will be the Chairman of the Grievance Redressal Committe; an Academician (to be selected by DC) will be Member; (iii) A representative of DP (to be selected by DC) will be Member and (iv) Executive Engineer of the concerned Division will be Convener. The GRC will be established at the district level with the primary objective of providing a mechanism to mediate conflict and cut down on lengthy litigation. It will also provide people, who might have objections or concerns about their assistance, a public forum to raise their objections and through conflict resolution, address these issues adequately. The GRCs will continue to function, for the benefit of the displaced persons, during the entire life of the project including the defects liability periods. 20. The Grievance Committees will meet regularly during the implementation of the RP, at least once a month. The committees will suggest corrective measures at the field level itself and fix responsibilities for the implementation of its decisions. However, the NGOs will form the first level of intervention in resolving DP-related grievances and attempt to motivate the DP to facilitate implementation of the R & R program. The option of contacting the project authorities is available to DPs at any time. The Deputy Commissioner will be the Appellate Authority. At the first level intervention, the NGO will attempt to resolve the grievance; Next, the CAO will attempt to address land-related grievance and the Assistant Director Social Welfare (ADSW) will address the non land-related grievances; the next option will be to approach the Grievance Redressal Committee; followed by the Regional Commissioner who is the Appellate Authority; If all of the above fails, the DPs can approach the court. It is the responsibility of the SDRC/NGO to inform the affected persons of the GRC, to make it effective. Taking grievances to the Judiciary should be avoided as much as possible and the NGO should make utmost efforts on reconciliation at the level of GRC.

E11. Institutional Arrangements 21. KSHIP has a dedicated unit called the Social Development and Resettlement Cell (SDRC) within the Project Implementation Unit for the implementation of the RP. All aspects of xvii

resettlement and rehabilitation and the delivery of entitlements are managed by Social Development/Resettlement Cell (SDRC). The SDRC facilitates land acquisition and compensation, relocation and resettlement, distribution of assistance for the DPs. The SDRC is responsible for monitoring the implementation of all resettlement and rehabilitation activities, including land acquisition. The RP will be implemented by the (Hospet) division of PIU. Staffing is complete for the proposed institutional set up. The key SDRC officials are: 22. Special DC Land Acquisition - Special Deputy Commissioner will be the one in charge of the overall land acquisition. He will be assisted by two Assistant Commissioners for Land Acquisition who are responsible for all activities related to land acquisition. One Assistant Commissioner will be stationed at the zonal office of North Karnataka (Hospet) and the other one will be stationed at the PIU Office (South Zonal Office) in Bangalore. 23. Chief Administrative Officer –The CAO will be responsible for all resettlement and rehabilitation activities. The CAO will also be assisted by the Assistant Director Social Welfare (ADSW) who will be responsible for R & R work. On the land acquisition side, the CAO and the Assistant Commissioners will be responsible for fixing the negotiated price of the land along with the affected persons according to the Karnataka Highways Act, 1964, and for disbursing the compensation. 24. The Assistant Director Social Welfare is responsible for shifting of project affected persons, coordination of disbursement of assistance such as shifting allowance disbursement of funds for income generating programmes, relief assistance, etc. 25. The Resettlement and Rehabilitation Manager will assist the ADSW and coordinate all the rehabilitation work of the SDO’s. 26. The ADSW and the Resettlement and Rehabilitation Manager will be assisted by the Social Development Officer (SDO).The SDOs will be assisted by the Social Welfare Inspectors (SWI). The SWI’s are supporting staff to SDOs to carry out the functions as per the directions of SDOs. 27. The SDRC will have a Data Management Specialist. The responsibility of this person will be to monitor and update the data of all the project affected persons; to highlight any discrepancy in compensation and paid disbursed; and coordinate the inputs of information from the North and South Divisions to the Central database at the PIU in Bangalore. The PIU has already appointed the Consultants for database management. Information is ready to be transferred to the PIU for use in implementation. 28. Involuntary resettlement is a sensitive issue and strong experience in R & R matters along with community-related skills will be required by the PIU in order to build a good rapport with the affected community and facilitate satisfactory R & R of the DPs. To overcome this deficiency, two experienced and well-qualified NGO in this field will be engaged to assist the PIUs in the implementation of the RP. The NGO would play the role of a facilitator and will work as a link between the PIU and the affected community. NGO will assist DP in income restoration by preparing micro plan and guiding to access into various ongoing government development schemes and agencies providing financial assistance and loan. Taking into account the

xviii significant role of the NGO in RP implementation, it is important to select NGO that are capable, genuine and committed to the tasks assigned in order to ensure the success of the Plan. E12. Implementation Schedule 29. Implementation of RP mainly consists of compensation to be paid for affected structures and rehabilitation and resettlement activities. The time for implementation of resettlement plan will be scheduled as per the overall project implementation. All activities related to the land acquisition and resettlement must be planned to ensure that compensation is paid prior to displacement and commencement of civil works. Public consultation, internal monitoring and grievance redress will be undertaken intermittently throughout the project duration. However, the schedule is subject to modification depending on the progress of the project activities. The civil works contract for each project will only be awarded after all compensation and relocation has been completed for project and rehabilitation measures are in place. The RP preparation and implementation schedule is presented below.

Table E-4: R & R Implementation Schedule

Activity Progress (Year/Quarter) 2009 2010 2011 Q4 Q1 | Q2 | Q3 | Q4 Q1 | Q2 | Q3 | Q4 Project Preparation Stage Screen project impact ------Public Consultation on alignment ------Prepare Land Acquisition Plan ------Carry out Census Survey ------Prepare Resettlement Plan (RP) ------RP Implementation Stage Hiring of NGOs for RP Implementation ------Obtaining approval of RP from ADB ------Disclosure of RP ------Public consultation ------Preparation LAP ------Declaration of cut-off date (KHA Notification) ------Payment of compensation ------Taking possession of acquired land ------Handing over the acquired land to contractor ------Rehabilitation of DPs ------Monitoring and Reporting Period Internal monitoring and reporting ------External monitoring and reporting ------E13. Monitoring and Reporting 30. Monitoring involves periodic checking to ascertain whether activities are going according to the plan. It provides the feedback necessary for project management to keep the programmes on schedule. Monitoring provides both working system for project managers and a channel for the resettles to make known their needs and their reactions to resettlement execution. Monitoring exercise will be undertaken both internally and externally. xix

31. While SDRC/PIU on monthly basis will carry out the project’s internal monitoring, external agency will be appointed for third party monitoring. Monitoring is essentially an exercise in strategic learning that can and should be used for enhancing the quality of RP implementation. There are two types of monitoring being undertaken namely: (a) Internal, which is normally carried out by the project authority itself; and (b) external or independent monitoring by an external agency. 32. The internal monitoring is a conventional monitoring of government-related to physical factors such as, number of households affected, resettled, assistance extended, infrastructure facilities provided, etc. and other financial aspects, such as compensation paid, grant extended, etc. The internal monitoring must be simultaneous with the implementation of the Rehabilitation Plan (RP).The objectives of the internal monitoring are: (i) Daily Operations Planning; (ii) Management and Implementation; and (iii) Operational Troubleshooting and Feedback. The frequency of internal monitoring could be daily or weekly depending on the issues and level. 33. An external monitoring agency will be appointed to monitor R & R programmes on semi- annual basis. It should also bring the difficulties faced by the DPs to the notice of PIU so as to help in formulating corrective measures. As a feedback to the PIU and other concerned, the external agency should submit semi-annual report on progress made relating to different aspect of R & R. The reports will be disclosed on ADBs websiteThe agency will also certify the completion of LA and R & R activities for issuing bid documents and award from LA and R & R point of view.

1

1 PROJECT DESCRIPTION

1.1 Background 1. This package has been selected, for upgrading with a 7-meter carriage way. Upgrading will have direct /indirect impact on the population along the project corridor. Common property resources, residential structures, commercial structures are likely to be affected. Non-titleholders within the ROW are likely to be displaced. This RP includes the baseline socioeconomic survey characteristics of the displaced persons, the R & R Policy provisions and entitlements and outcome of the consultation held with displaced persons and communities. 2. This project is Package AEP 8 comprising of two links: 31A ( Mudga to Tavaragere) is 31.21 km in Koppal and Raichur districts and crosses two Taluks Lingsugur and and 31B ( Tavaragere to Gangawathi) is 42.89 km in Koppal district and crosses the taluks of Gangavathi and Kushtagi . According to the categorization of taluks given in the High Power Committee for Redressal of Regional Imbalances Report of 2002, package covers: (i) two most backward taluks3 (Lingsugur and Kushtagi); and (ii) one backward taluk (Gangavathi). The location Map of the Project is given in Map 1.

1.2 Objectives 3. This Resettlement Plan (RP) is project specific, which outlines the extent of impacts due to road improvements on communities and the mitigation of the potential impacts. It details necessary implementation procedures for resettlement and rehabilitation. This RP is prepared in accordance with the stipulations and guidelines provided in Public Works Departmental Code Government of Karnataka4, and the project specific Resettlement and Rehabilitation: - Principles and Policy Framework for the Karnataka State Highways Improvement Project –II, The National Resettlement and Rehabilitation Policy 2007 and ADB’s Safeguard Policy Statement of 2009. Within this given background the objective of RP is: a. To Identify adverse impacts and determine how they could be overcome or substantially mitigated with the implementation of Karnataka State Highways Improvement Project; b. To present the entitlements for the affected persons for payment of compensation and assistance for establishing the livelihoods and; c. To present an action plan for the delivery of compensation and assistance in accordance with the policy adopted for the project;

3 The HPCFRRI report classified taluks in four categories on the basis of the Composite Development Index namely: i) Most backward taluka; ii) More backward taluka; iii) Backward Taluka; and iv) Relatively Developed Taluk A total of 35 relevant indicators covering 5 sectors viz., agriculture and allied; industry, trade and finance; infrastructure (economic); infrastructure (social) and population characteristics were considered for analysis in the report. This indicator was used to compute a Comprehensive Composite Development Index (CCDI) for each taluk. The Committee also attempted a study of imbalances from the deprivation end in respect of six important basic minimum needs to gain a qualitative understanding of the problem. Those six basic minimum needs are: 1. Income deprivation - Percentage of households (rural) below poverty line.2.Unsafe deliveries - Percentage of deliveries not attended by trained health personnel. 3. Unsafe Drinking water - Percentage of habitations not fully covered by safe drinking water facility.4. Malnourished Children below age group 5 - Percentage of moderately and severely malnourished children. 5. Children out of school in the age group of 6-14 years- Percentage of children out of school in the age group of 6-14 years. 6. Gender Gaps in literacy- Literacy rate (Male-female)

4 PWD Departmental Code is in the process of being finalized.

2

d. To prepare an action plan for the project affected people for improving or at least retaining the living standards in the post resettlement period.

3

Figure 1-1: KSHIP Roads

4

1.3 Physical Characteristics of the project area 4. This link passes through the Central Karnataka Plateau. The Central Karnataka Plateau covers the districts of Bellary, Chikkamagalur, , Davanagere, Dharwad, Gadag, , Raichur, Koppal and . The region represents the transitional surface between the Northern Karnataka Plateau with relatively higher surface. By and large, this region represents the area of Tungabhadra basin. The general elevation varies between 450 and 700 meters. However, this transitional ground is broken by several sets of parallel ridges mainly made up of Dharwar system of rocks. The height of such residual hills is about 900 meters above mean sea level. The general slope of this region is towards the east. The major crops growing in these places are Sunflower, Paddy, Maize, Groundnut, Cotton, Flowers, Wheat, Ragi, Bajra, Chillies, Coconut and Arecanut.

1.4 Project Components 5. As the existing ROW is not uniform the additional requirement varies for a minimum of 12 m up to 30 m COI. Key activities for road improvement involves (i) widening/strengthening of the road up to two lane divided carriageway configuration, (ii) improving road geometry, (iii) laying of embankment, (iv) rehabilitation and construction of new bridges and other cross drainage structures, (v) construction of side drains, (vi) construction of railway over bridges (ROB), (vii) junctions/intersections improvement, (viii) provision of service roads, underpasses and way side amenities, etc. The project activities are described below.

1.5 Road Configuration: 6. Link 31A is designed at 23 million standard axle (msa) and 66 msa for Bituminous and Granular respectively. Rural Cross Section with Earthern Shoulders (RCSES) is proposed for 29.42 km and Urban Cross Section ( UCS) 1 – for 1.79 km length. 7. Link 31B is designed at three million standard axle (msa) and six msa for Bituminous and Granular respectively. Cross Section with Paved Shoulders is proposed for 38.69 km, Urban Cross Section 1 for 3.58 km, and Urban Cross Section 2 for 0.64 km length.

1.6 Realignment / Bypasses: 8. Link 31 A: There are no major realignments / bypasses proposed. 9. Link 31 B: There are no major realignments / bypasses proposed.

1.7 Bridges and other Cross Drainage structures: 10. Link 31A: One major bridge, five minor bridges and 50 culverts are proposed for reconstruction. 11. Link 31B: One major bridge, five minor bridges and 50 culverts are proposed for reconstruction 5

1.8 Road Side Drainage: 12. Link 31 A: Unlined drain is proposed in rural section and both covered / uncovered drains are provided in town and village sections. 13. Link 31 B: Unlined drain is proposed in rural section and both covered / uncovered drains are provided in town and village sections.

1.9 Railway over Bridges (ROBs): 14. Link 31A: There are no ROBs proposed. 15. Link 31B: There are no ROBs proposed.

1.10 Junctions / Intersection improvements: 16. Link 31A: There are two major and eight minor junctions proposed for improvement. 17. Link 31B: There are three major and 11 minor junctions proposed for improvement.

1.11 Service roads and underpasses: 18. Link 31 A: There are no service roads and underpasses proposed. 19. Link 31 B: There are no service roads and underpasses proposed.

1.12 Way side amenities / Toll plaza / Truck parking, etc.: 20. Link 31A: There are 14 bus bays with passenger shelter proposed.

21. Link 31B: There are 16 bus bays with passenger shelter proposed.

1.13 Magnitude of impacts 22. The project will impact 1618 DPs and 526 DHs. The total private land acquisition for the project is 5.21 Acres. Table 1-1: Summary Tables on Impacts Land Land Acquisition- Transfer – Displaced Displaced Community Link List of villages Private Govt households Persons Assets (Nos) (Ac) ( Ac) 31A Chattara, Killarahatti, 4.16 0.00 145 527 52 Konapura, Mudgal, Mullura, Nagalapura, Tavaragere, Todaki, Ulamgere, Ulimeshwara, Vyakaranala

31B Aralihalli, Aralihalli 1.05 0.00 381 1091 109 Cross, Galemma Camp, Gangavathi, Gonahalli, Gonala, , Hulihydara, Kanakagiri, ,

6

Kesarahatti, Menadal, Sulekal, Tavaragere, Tippanal Cross, Tippanala

TOT 5.21 0.00 526 1618 161 AL

Table 1-2: Categories of DHs and losses

Sl. Extent of Loss Titleholders Tenant Squatter Encroacher No. 1 Losing Total House 4 0 12 0 2 Losing Total Com. Struc. 4 0 196 2 3 Losing Total House and Com. Struc. 00 2 0 4 Tenants Losing Total Livelihood 046 0 0 5 Losing Total Land 00 0 0 1 Losing only Part of House 57 1 3 0 2 Losing Part of Com. Struc. 40 1 0 Losing Part of House and Com. 3 30 1 0 Struc. 4 Patrial Plot 10 0 0 5 Total Boundary Wall 15 0 0 0 6 Partial Boundary Wall 40 0 0 7 Cattleshed 10 2 0 8 Losing Partial Land 148 0 0 0 9 Others 18 0 1 0 Total 259 47 218 2

1.14 Minimizing impacts 23. Design and planning measure has helped to reduce the negative impact on structures and livelihood of the people.

1.15 Design Cross Sections 24. There are 11 types of typical road cross sections proposed for upgrading roads. Distinct design approaches have been followed to minimize negative impacts on the people. The Typical road cross section for upgrading roads is given in Annex 1. For this package 5 cross sections have been used. (i) UR 1 A Rural Cross section: This has a 7.0 mts paved carriage way, with 1.5 mts paved shoulder and 1.0 mts unpaved shoulder on either side. (ii) UR 1 B Rural Cross section: This has a 7.0 mts paved carriage way, with 2.5 mts unpaved shoulder on either side. (iii) UR 2 Rural Cross section (through village): This has a 7.0 mts paved carriage way, with minimum 2.5 mts to a maximum of 4.5 mts paved shoulder and 1.0 mts uncovered drains on each side. (iv) UR 3 Urban Cross section in Built up area (with covered drain): This has a 7.0 mts paved carriage way, with minimum 2.5 mts to a maximum of 4.5 mts paved shoulder and 2.0 mts footpath on either side, with the drains below the foot path. 7

(v) UR 4 Urban Dual Lane Cross section in Built up area (with covered drain): This has 1.2 mts median with a 7.5 mts carriageway on either side and 2.00 mts footpath on either side, with the drains below the foot path .

1.16 Mitigation through Design Cross Section 25. The changes that have been considered in the project through good designs to mitigate social impacts include: - Avoiding unnecessary displacement by modifying project alignments, reducing the width of the corridor of impact, or modifying design based on rural and urban cross sections. At built-up/ village sections where the road width is insufficient for expansion, design alternatives include reduction of COI; - Smoothening of curves and bends for better geometric design. In case where it affects settlements, alignment changes were done; - Minimal impact on residential and commercial structures thus minimizing resettlement and loss of livelihood; - Paved shoulders to be maintained as far as possible to facilitate movement of non-motorized traffic; - Reducing design speed in built up areas; - Reducing impacts on existing shrines and worship places; - Providing suitable safety measures, such as speed reductions near schools and hospitals; - Minimizing the raising of roads in urban areas to prevent water seepage to the houses adjoining the roads; and - Providing access to businesses and residential units that would be otherwise impacted by construction; and minimizing losses of public and private property, such as tube wells, tree plantations and other common property resources within the ROW, by minimizing the width to be cleared.

1.17 Road safety and Traffic Management measures 26. During the consultations, safety of the roadside communities has been found to be a major concern. A number of measures have been proposed to reduce the risk of traffic accidents. Traffic safety measures include: Conducting “Road Safety Audits” has become a key responsibility as part of the Highway Designs. Various road safety appurtenances, which should be adopted as a part of improving the safety in the road design, are adopted in the project road designs. 27. Road Furniture details include: Road Markings; Cautionary, Mandatory and Informatory signs; KM stones and 200m stones; Delineators and Object Markers; Guard Posts and Crash Barriers; Road Humps and Rumble Strips; Reflective Pavement Markers (RPM) and Chevron signs and Median and Footpath Barriers. In addition, bus bays, parking bays, truck lay byes with rest areas and detailed improvements to major and minor intersections on the project road coupled with identification of black spots are being dealt with.

8

1.18 Magnitude of Impacts Cultural properties and CPRs 28. There are no sites of archaeological importance or sacred groves within the COI for this link. The project authorities would relocate cultural properties in alternative site such as places of worship which are getting totally affected. The identification of alternative site will be done by the NGO/ support agency in consultation with the local user population of that particular cultural property. The alternative site for construction will be provided by the GOK. In case government land is not available, the project authorities will have to buy land to replace the cultural property. If the cultural properties are partially affected the project authorities will compensate only the affected portion. 29. The project will impact 161 community structures. There are: 3 primary schools, 12 temples, two mosques, 11 aralikatte, 16 bus shelters, 25 hand pumps, 12 mini water supply tanks, 21 bore wells, 10 water tanks etc. There are some structures which are getting partially affected. 30. All community assets getting affected need to be relocated before commencement of civil works. The broad timetable for relocation of community assets is given in the Implementation Schedule. The relocation of the community assets needs to be undertaken concurrently in all the contract packages. The project authority will be responsible for the construction of the affected community assets. The relocated community assets would be handed over to the local community/trust for maintenance. 31. All hand pumps getting affected will be located depending on availability and depth of water table. Water points, public taps and wells getting affected will also be similarly relocated. All affected aralikattes, will be built by the project authorities, and in sites identified by the project-affected groups and the co-ordinating NGO/ support agency for implementation. The project authorities will relocate all the bus shelters getting affected by widening of the road. The location of the bus shelter were decided on the basis of the frequency of usage arrived through the consultative process of the users and design requirements.

1.19 Impact of the project 32. The proposed project can be viewed as boosting economic growth and poverty reduction which will bring substantial social and economic development in the region. The social benefits arising due to the project will be triggered off due to improved accessibility to various services such as easy access to markets, health facilities, schools, workplace which in turn increases the income of the locals, and ultimately elevating their standard of living. The outcome of the project will include: (i) The project will serve villages with better access and enhanced mobility. Improved backward taluk connectivity will facilitate travel to taluk head quarters and other local government/development agencies. In places where the connectivity is poor the project will provide better access to amenities such as health, education, town/market and improved social networking; (ii) The project will improve the accessibility of the population along the project corridor to education, health, employment, trading opportunities and in the long run help towards poverty alleviation; 9

(iii) The project will help to increase new economic and employment opportunities by providing improved linkages to markets, production centers and other areas of economic opportunities. Better and quicker transportation would help the rural population to transport their produce faster and get more profit margins instead of depending solely on local ‘markets’ and middlemen; (iv) Women will benefit, as their mobility will be facilitated both in terms of access to social services, as well as access to higher levels of schooling. Women’s access to higher levels of health care outside the village will also improve considerably; (v) Targeted assistance will be provided to vulnerable groups including below poverty line households, women-headed households, and physically challenged persons, through the Resettlement Policy. 33. The likely adverse impacts of the project are: Potential adverse impacts associated with the project are (i) land acquisition, and (ii) loss of livelihood and overall the proposed project will bring in economic and social changes, which in turn would bring economic prosperity and would lead to poverty alleviation.

1.20 Right of Way and Corridor of Impact 34. The Right of Way is the lawfully acquired corridor of public land owned by the State Government and administered by the PWD for the transit of the existing road. Using available records with the PWD and the Revenue Department, the social team verified the boundaries of private properties within and in the vicinity of likely corridor of impact. The preparation of the Land Acquisition Plan is being facilitated through the verification of land records, updated records for the ownership of land. 35. For this project, preparation of RP associated with displacement is limited to the corridor of impact. The corridor of impact is the width required for the actual construction of the road, including carriageway, shoulder, embankments and longitudinal drainage. Within this corridor there should be no structures or hindrances. The objective of social input to project design is to ensure that the corridor of impact is reduced, within acceptable design principles and standards, to minimize displacement and other project impacts. Those affected between the Corridor of Impact and Right of Way during the lifetime of the project will be assisted in line with this project Entitlement Policy, if they are required to be affected for any additional work required for this project.

10

2 METHODOLOGY FOR IMPACT ASSESSMENT

2.1 Social Impact Assessment 36. Poverty and Social Assessment (PSA) was carried out for the project road. The PSA study looked into the likely impacts of road improvement on the communities, and the likely mitigation aspects of the impacts. It also looked into the impact of the project especially on the backward taluks through which the project road passes, and how the road project is likely to affect the impacted population. The study was based on extensive public consultations and stakeholders view. 37. The negative social impact identified by community members was the potential for loss of land to project interventions. However, according to a majority of stakeholders consulted, the benefits of the project outweigh impacts from minor losses of land. There was broad consensus in all these communities that dry land acquired by the project would not be a problem, people were reluctant to part with irrigated or garden lands. To overcome any resistance it was informed that according to the entitlement policy land losers will be given market value of land after negotiation under the KHA.1964. Recommendations for impact mitigation and enhancement entitlements were given by the stakeholders. The suggestions as feasible have been incorporated into the design.

2.2 Approach to Resettlement Planning 38. During the census survey it was seen that road widening and improvement will have some impact on residences, businesses, shrines, places of worship, agricultural land, community assets. Most of the infrastructure work planned for the project as far as possible will take place within the established ROW. In most cases, the land required for the project is immediately adjacent to the current carriageway. The additional land required by the project falls under several classifications: (i) Public land owned by the State Government and administered by other Departments such as Revenue; (ii) Public land owned by villages or other local governments; and (iii) Private land. 39. The RP is prepared to ensure that: a. The displaced persons are: (i) informed about their options and rights pertaining to resettlement; (ii) consulted on, offered choices among, and provided with technically and economically feasible resettlement alternatives; and (iii) provided prompt and effective compensation at full replacement cost for losses of assets attributable directly to the project; b. Displaced persons are: (i) provided assistance (such as shifting allowance, transition allowance, economic rehabilitation grant etc.) during relocation; and (ii) provided with residential housing, or housing sites, or as required, compensated for agricultural sites; c. To ensure that displaced persons are : i) offered support after displacement, for a transition period, to restore their livelihood and standards of living; (ii) provide with development assistance in addition to compensation measures, such as credit facilities, training, or job opportunities; and (iii) at least improving or retaining the living standards in the post resettlement period. 11

2.3 Census Socioeconomic Survey 40. As a part of the project, a census survey of Displaced households\Persons (DHs and DPs) was carried out. The findings of the census survey provided the magnitude of social impacts on the DHs and DPs. In this section, the survey outcomes are analyzed. The census information helped to generate necessary data/input for the preparation of this Resettlement Plan. The Census Survey Schedule is given in Annex 2. The surveys provide a baseline measurement of potential impacts on displaced households/persons that form the eligibility criteria for entitlement as given in the R & R Policy of KSHIP. The objectives of the census verification were: (i) Provide information regarding project impacts in order to facilitate designing of various components of the RP, especially R & R entitlement; (ii) Minimize the influx of outsiders to the affected area; (iii) Identification of DPs by effect categories; and (iv) Enumeration of DPs assets and land holdings. 41. The project will impact the following households: Table 2-1: Categories of DHs and losses

Sl. Extent of Loss Titleholders Tenant Squatter Encroacher No. 1 Losing Total House 4 0 12 0 2 Losing Total Com. Struc. 4 0 196 2 3 Losing Total House and Com. Struc. 00 2 0 4 Tenants Losing Total Livelihood 046 0 0 5 Losing Total Land 00 0 0 1 Losing only Part of House 57 1 3 0 2 Losing Part of Com. Struc. 40 1 0 Losing Part of House and Com. 3 30 1 0 Struc. 4 Patrial Plot 10 0 0 5 Total Boundary Wall 15 0 0 0 6 Partial Boundary Wall 40 0 0 7 Cattleshed 10 2 0 8 Losing Partial Land 148 0 0 0 9 Others 18 0 1 0 Total 259 47 218 2

2.4 Methodology and Database 42. Census covers 100% of the potentially affected population within the likely COI. It provides a demographic overview of the population served by the RP and profiles household assets and main sources of livelihood. During census survey, legal boundaries of affected properties were verified. The census registered all household members and individuals within the potential COI their assets and income, and demographic and social information to determine whether project affected persons were to be categorized as vulnerable groups with special entitlements under the project. Private land owners, tenants, squatters and encroachers within the COI were covered. Structures, trees, and other assets were also recorded. 43. Data was collected at the following levels: (i) Household level interviews with each affected household were undertaken. Each of the households surveyed and the

12 structure/agricultural land likely to be affected by the project has been numbered, documented and photographed; and (ii) Village level public consultations were conducted. 44. A database has been created for the census information. The information has been stored and analyzed using Visual Basic and MS-Access. This program is easily convertible to Oracle platform. The superimposition of the survey data on the final engineering designs will provide the actual number of DPs. Only these DPs within the final COI will be considered eligible for support under the project.

2.5 Sources of Data 45. Data was collected was collected from the following secondary sources: (i) Revenue records at local/village level - with regard to land particulars for acquisition of properties; (ii) Census records for demographic information; (iii) PWD for ROW/COI, estimates of the cost of infrastructure development etc.; (iv) Development agencies to get information on various developmental programs for specific sections of population like landless, marginal and small farmers etc. tribal, SCs etc.; and (v) Local organizations including NGOs in order to involve them and integrate their activities in the economic development programs of the displaced population. 13

3 SOCIOECONOMIC INFORMATION AND PROFILE

3.1 Socio Economic profile of the project Area 46. This project has two links 31 A is 31.21 km in Koppal and Raichur district and 31 B with a length of 42.89 km in Koppal district. The female population varies from 48.70% in Link 31 A to 49.37% in Link 22 B. Gangawathi town, accounts for 73% of the total population of Link 31 B. The Schedule Caste population varies from 13.52% in Link 31 B to 20.93% in Link 31 A. The Scheduled tribe population is at 6.82% for both the links. The literacy level in this area is low. The overall literacy level varies from 44.44% in Link 31 A to 52.41% in Link 31 B. The female literacy rate varies from 32.03% in Link 31 A to 42.54% in Link 31 B. This corridor passes through Koppal and Raichur district where the literacy rates are 55.02 and 58.04% respectively. The work force participation rate varies from 42.65% in Link 31 A to 35.90% in Link 31 B. The total female work force rate varies from 19.09% in Link 31 B to 35.33% in Link 31A. These two links are predominantly paddy cultivation areas. The area around Gangawathi town is referred to as the ‘rice bowl of Karnataka. The access to amenities in the area is average. The nearest towns in Link 31 A are Mudgal, Kushtagi, and Sindhanur; in Link 31 B the nearest towns are Kushtagi and Gangawathi.

3.2 Socio Economic profile of Displaced Population 47. The key socioeconomic characteristics of the displaced population are discussed below. 48. Social Stratification: Scheduled Caste and Scheduled tribe households each account for 10% of the total population; the remaining are from the general category. Table 3-1: Social Stratification Link SC ST General Total No. No. % No. % No. % No. 31 A 13 0.00 27 24.32 71 63.96 111 31B 23 0.00 12 4.86 212 85.83 247 Total 36 10.056 39 10.894 283 79.05 358 49. Religious Group: Among religious groups, Hindus dominate with 86%, the remaining account for Muslims. Table 3-2: Religion Link Hindu Muslim Christian Jain Total No. No. % No. % No. % No. % No. 31A 99 89.19 12 10.81 0 0.00 0 0.00 111 31B 210 85.02 37 14.98 0 0.00 0 0.00 247 Total 309 86.31 49 13.69 0 0 0 0 358 50. Occupation: Distribution of DPs by occupation reveals that agriculture accounts for 43.81%; the other sector, which supports a large section of DHs, is represented by trade/commerce accounting for 43.8 %. Agriculture labour accounts for 6.68%. Table 3-3: Occupation Distribution Agricult Allied HH Link No. Agriculture % ure % Agri. % Service % Industri % Labour Activities es

14

31 A 109 57.67 9 4.76 0 0.00 2 1.06 0 0.00 31 B 160 37.65 32 7.53 0 0.00 7 1.65 0 0.00 Total 269 43.81 41 6.68 0 0 9 1.47 0 0.00

Cont.. Comme Link Profess Skilled Other rce/ % % % Artisans % % Total No. ional Labour s Trade 31A 61 32.28 1 0.53 0 0.00 0 0.00 7 3.70 189 31B 203 47.76 5 1.18 2 0.47 0 0.00 16 3.76 425 Total 264 43.00 6 0.98 2 0.33 0 0.00 23 3.75 614 51. Income level: In spite of difficulties in getting reliable data on household income, efforts were made to persuade the respondents to report as accurate data as possible. 40.11% of the general population has income less than Rs.26,000. ST households earning less than Rs.26,000 account for 50.00% of the ST population. The income information has been segregated for ST, SC and general category. Table 3-4: Income Distribution Schedule Caste

Link 5000 - 11501 - 16001 - 26001 - 40001 - 75001 - Above Total No. % % % % % % % 11500 16000 26000 40000 75000 100000 100000 SC

31A 4 25.00 0 0.00 5 31.25 5 31.25 2 12.50 0 0.00 0 0.00 16 31B 2 8.33 2 8.33 13 54.17 5 20.83 1 4.17 1 4.17 0 0.00 24 Total 6 15.00 2 5.00 18 45.00 10 25.00 3 7.50 1 2.50 0 0 40

Cont… Schedule Tribe 5000 1150 Link 16001 26001 - 1 - 40001 - 75001 - Above Tot_ No. % % - % - % % % % 1150 1600 75000 100000 100000 ST 26000 40000 0 0 31A 1 3.70 0 0.00 9 33.33 7 25.93 9 33.33 1 3.70 0 0.00 27 31B 2 15.38 2 15.38 6 46.15 2 15.38 0 0.00 1 7.69 0 0.00 13 Total 3 7.50 2 5.00 15 37.50 9 22.50 9 22.50 2 5.00 0 0.00 40

Cont… General

Abov Link 11501 16001 26001 40001 5000 - 75001 - e Tot_ No. % - % - % - % - % % % 11500 100000 1000 O 16000 26000 40000 75000 00

31A 6 7.79 3 3.90 25 32.47 17 22.08 17 22.08 2 2.60 7 9.09 77 31B 30 11.45 8 3.05 64 24.43 96 36.64 45 17.18 4 1.53 15 5.73 262 Total 36 10.62 11 3.24 89 26.25 113 33.33 62 18.29 6 1.77 22 6.49 339 52. Age Classification: 72.99% of the total DPs fall in the age group of 18-59. Since this happens to be the working age-group the mitigation measures as given in the entitlement matrix need to be carefully implemented with reference to 18-59 age groups. Table 3-5: Age Classification Link Below 18 18-60 Above 60 Total No. No. % No. % No. % No. 31A 92 17.46 376 71.35 59 11.20 527 15

31B 196 17.97 805 73.79 90 8.25 1091 Total 288 17.80 1181 72.99 149 9.21 1618 53. Literacy: Illiterate population accounts for 21.47% of the surveyed population. Just literate population accounts for 18.28% of the total population; while primary accounts for 16.75% of the total population; those with Middle school education account for 12.36% of the total population; those with education up to secondary level accounts for 16.35% of the total population. The detail education table with gender wise break up is given below. Graduates account for 3.39%. Table 3-6: Literacy Illiterate Just Literate Primary Middle Link To To Tot Tot No. M % F % t_I M % F % M % F % t_ M % F % _JL _M ll P 34.6 65. 12 51.6 48.3 62. 37.3 54.2 45.7 31A 44 83 32 30 62 57 34 91 32 27 59 5 35 7 1 9 64 6 4 6 42.3 11 57. 19 43.6 12 56.3 56. 43.2 16 50.3 49.6 31B 83 93 213 93 71 64 63 127 5 3 65 6 6 0 4 71 9 4 9 1 12 39.3 19 60. 32 12 45.4 15 54.5 15 58. 10 41.1 25 51.6 48.3 Total 275 96 90 186 7 2 6 68 3 5 5 0 5 0 82 5 8 5 1 9 Cont… Secondary Intermediate Graduate Post Graduate Link To To Tot No. Tot M % F % t_ M % F % M % F % t_ M % F % _P _IM S G G 10 63.6 2 36.3 76.9 23.0 87. 31A 49 77 30 9 39 13 0.0 0 0.00 13 7 1 12.5 8 4 8 6 2 8 5 0 60.9 6 39.0 16 71.1 28.8 68. 1 31.5 81. 18.1 31B 103 64 26 90 26 38 18 4 22 5 6 5 9 1 9 42 2 8 8 8 61.7 9 38.2 24 72.8 27.1 76. 1 23.5 83. 16.6 Total 152 94 35 129 39 51 25 5 30 9 4 1 6 7 3 47 2 3 3 7

Cont… Link ITI/Diploma Engineer/Doctor Others Total No. M % F % Tot_I/D M % F % Tot_E/D M % F % Tot_O M % F % Tot 31 A 0 0 0 0 0 1 100 0 0.00 1 0 0 0 0 0 265 55.56 212 44.44 477 31 B 1 100 0 0 1 5 71 2 28.57 7 0 0 0 0 0 550 53.55 477 46.45 1027 Total 1 100 0 0 1 6 75 2 25.00 8 0 0 0 0 0 815 54.19 689 45.81 1504 54. Structure Type: Of the residential structure, 29.49% are pucca. Amongst commercial structures getting affected, only 2.40% of the structures are pucca.

Table 3-7: Type of Structure Residential Link Semi No. Pucca % % Kutcha % Tot_Residential % Pucca 31A 7 31.82 6 27.27 9 40.91 22 43.14 31B 16 28.57 12 21.43 28 50.00 56 35.90 Total 23 29.49 18 23.08 37 47.44 78 37.68 Cont… Commercial Link Semi No. Pucca % % Kutcha % Tot_Commercial % Pucca 31A 3 5.00 6 10.00 51 85.00 60 100

16

31B 3 1.58 31 16.32 156 82.11 190 100 Total 6 2.40 37 14.80 207 82.80 250 200 55. Loss of Commercial structures: Majority (63) of the commercial structures is pan/cigarette shops; followed by 39 tea stalls. 56. Access to utilities: Of the total residential structures getting affected, 88.46% have electricity, while 13% have access to piped water. 57. Household Assets: Among household assets 11.50% of the households have television; 3.77% own two/four wheelers; 3.03% having cooking gas; 6.37% have telephones and only 1.30% have refrigerators. Amongst agricultural equipment 11.76% own tractors; 7.35% own harvesters and 10.29% own Sprayers.

3.3 Vulnerable Groups 58. Those falling within this category include persons such as physically challenged, widows, or persons above sixty years of age, who are not provided or cannot immediately be provided with alternative livelihood and who are not otherwise covered as part of a household. These persons are entitled to Assistance to include in government pension schemes if not included, if eligible as per Government criteria (OR) Lump-sum amount of Rs. 25,000. There are some DPs that are in more than one vulnerable category. These DPs will be paid only once. There are 48 widows, 13 physically challenged persons and 149 DPs over 60 years. Households by Gender are given below. Table 3-8: Affected Households by Gender Link Male Female Total Category No. No. % No. % No. Head of HH 101 89.38 12 10.62 113 31A DPs 468 88.80 59 11.20 527 Head of HH 209 85.31 36 14.69 245 31B DPs 923 84.60 168 15.40 1091

3.4 Gender Issues 59. There 48 women-headed household. The proposed upgrading of roads under KSHIP is expected to open up new economic opportunities for women to upgrade their skills and also better accessibility to educational and health facilities. The improved road was perceived to help reduce travel time, as an immediate benefit. Women as a segregated class are not involved in any economic activity, which demands attention to their special needs. However, in the village level consultations, the women said that improved roads were a danger especially in the built-up area. Increased speed of traffic makes it difficult for women and children to cross the roads. It also leads to increased accidents as children in villages areas tend to play near the roads. In some links, the improved road will lead to the movement of heavy vehicles carrying ore and goods; this was not welcome in the village limits. To ensure that women are secure in receiving payments, all benefits will be provided in joint account where the woman will be the primary beneficiary. Wherever title is provided, it should be provided with joint title with women as the primary beneficiary. 17

3.5 Indigenous People 60. In Karnataka, Schedule Tribes (ST) account for 6.55% (3.46 million) of the total State population. Bellary district has the highest concentration of STs in Karnataka. There are 50 major tribes with 109 sub-tribes in the State (as of March 2005), according to the notified Schedule under Article 342 of the Constitution of India. In Karnataka there are 4 Districts which fall under the Integrated Tribal Development Project. These are Mysore, Kodagu, Dakshin Kannada and Chikmagalur. Integrated Tribal Development Projects (ITDPs) are contiguous large areas of the size of one or more Development Block in which the ST population is 50% or more of the total population. Primitive Tribal Groups are found in Chamarajnagar District. The Government of Karnataka has identified (i) Jenu Kuruba; and (ii) Koraga tribes as primitive groups (PTGs). Primitive Tribal Groups (PTGs) are identified isolated communities among the STs characterized by a low rate of population, a pre- agricultural level of technology and extremely low levels of literacy. 61. Jenu Kuruba tribes are originally from Mysore, Chamarajanagar and Kodagu districts, and Koraba tribes are from and Dakshin Kannada districts. In , only Kollegala Taluk has PTG areas. PTGs constitute the most vulnerable among the all notified tribes. 62. None of the ITDP districts or the PTG district fell within this project road. The Director of Tribal Welfare GoK, has indicated through a letter No: DSTW : TSP:OSCR 12/2010-11 dated 26 April 2010, that no village in the State of Karnataka has been designated as tribal village; and that the project roads are not passing through any ITDP areas. Tribal are living in the villages along the project roads along with other communities. Based on the information provided by the Tribal Department and the Census surveys IPDP will not be required 63. There are 39 Scheduled Tribe households getting affected in this package, who are dispersed over the package. The Tribal households found in the project area no longer maintain any of the distinctive characteristic mentioned above. During the consultations held there were no specific issues raised by tribal persons/groups. According to the detailed socio economic survey carried out for the poverty and social assessment and the census survey carried out for the preparation of the RPs, the STs identified in the links do not exhibit any of the following characteristics (i) self-identification as members of a distinct indigenous cultural group and recognition of this identity by others; (ii) collective attachment to geographically distinct habitats or ancestral territories in the project area and to the natural resources in these habitats and territories; (iii) customary cultural, economic, social, or political institutions that are separate from those of the dominant society and culture; and (iv) a distinct language, often different from the official language of the country or region. Besides all the STs are predominantly maintaining the similar standards of living which is comparable to the other sections of the community

18

4 SCOPE OF LAND ACQUISITION AND RESETTLEMENT

4.1 Proposed Land Acquisition 64. Land acquisition will be done under the Karnataka Highways Act (KHA), 1964. Under KHA, land acquisition will be entrusted to a designated “Highway Authority” with delegated powers, so that the entire acquisition proceedings will be carried out under centralized agency i.e., Highway Authority with dedicated officials for the purpose of land acquisition, instead of involving many officials of the revenue department. Acquisition under consent award as given under Section 27 of KHA, 1964 will be applicable. This will help in arriving at a mutually agreed rate of compensation with the land owners, which will eliminate resentment from the land owners regarding rate of compensation thus reduce the scope for approaching the civil courts for higher compensation. Section 27 read with Section 26 provides payment of compensation to individuals who are losing land. No other section in the Act deals with payment of compensation determined by way of agreement. Under the KHA in this project the Negotiation Committee after negotiation with the land losers in clusters arrive at a price agreeable to the land losers. Once the price is agreed for individual survey numbers accordingly an agreement will be executed with the land losers. Subsequently the land will be taken possession of. In this process no award is passed. Generally, this process is termed consent award. 65. The summary and main features on comparison between LAA and KHA are: 1. Time taken under ideal situation for land acquisition under KHA,1964 is 63 weeks as against 94 weeks for LA Act 1894; 2. The Project Director is designated as “Highway Authority” and in charge of LA. However, the land acquisition under LA Act, 1894 needs to pass through a set of departmental procedure and officials who are often busy with their primary departmental duties; 3. The proposal of land acquisitions under LAA 1894 needs to pass through six offices, i.e. the acquiring body, the Tahlisdar, the Assistant Commissioner, the Deputy Commissioner, the survey department and finally, the Government which is not only time consuming but also a tedious process. It is also relevant to mention here that even for small clarifications the file has to go through all these offices which cause unavoidable delay in file processing. Under KHA, 1964 the Project will have dedicated officers designated solely for this task, as a result of which the LA process will be faster and better streamlined. The land acquisition under KHA, 1964 would involve two agencies namely the Highway Authority and Government. 66. The process of Land Acquisition under KHA, 1964 is as follows: a. On the recommendations of the “Highway Authority”, the “State Government” will issue a notification for acquisition of the required land, which will be published in the Gazette (Section 15). b. After publication of notification Under Section 15 of KHA, 1964, the Highway Authority will cause the land to be measured (Section 16). 19

c. Under Section 17 of KHA, 1964, public notice will be issued to all the interested persons to file their claim for compensation within 15 days from the date of receipt of notice. d. At any time after the publication of notification under section 15(on receiving report from the Highway Authority), the State Government. may direct that the lands specified in the notification shall be taken possession of, from such date as may be specified in the direction. From such date, the said land vest absolutely in the State Government. free from all encumbrances (Section 19). This process would take place only after completion of awards in every case. e. Consequent to notification under section 15 and after obtaining documents from the land losers the “Highway Authority” will proceed to pass award on consent basis if there is consensus for a mutually agreed rate for consent award (section 27). f. In default of consensus the “Highway Authority” will proceed to fix the compensation on general award basis (Section 28). g. There is also provision for making reference against the award of the “Highway Authority” before the court of law (Section 35).

4.2 Estimated time for LA 67. From the issue of Section 15 the time taken to complete the land acquisition process is 6 months. Anticipated time to be taken for each stage of acquisition proceedings under KHA 1964 is as follows: a. Section 15: After issue of section 15 notification, 45 days is given for filing claims. b. Section 17: public notice and notice to individual land losers to file his claims within a specific date mentioned therein the notice. c. Framing of award: Framing of award under section 27, 28 and taking possession of land -12 weeks d. Section 19: From section 15 notification to issue of direction under section 19 for taking possession of the land – 24 weeks

4.3 Managing Land Acquisition 68. The GOK has designated the Project Director (PD) as Highway Authority under Section 6 of KHA, as per GO Order No.PWD 49 EAP 2008 dated 02 December 2008. 69. The Special DC Land Acquisition and the Project Director are the award approving authorities. Sp DC LA can approve award up to Rs.50 Lakhs. Above Rs.50 Lakhs and up to Rs.1 Crore the authority rests with the Project Director.

4.4 Staffing for Land Acquisition Work 70. The Special DC Land Acquisition will be in charge of Land Acquisition. To execute the LA work efficiently the GoK has issued orders for the appointment of supporting staff for LA. 71. The Sp DC LA will be assisted by two Assistant Commissioners.

20

4.5 Negotiations Committee for Land Price Fixation and determination of Replacement Cost 72. Under the KHA, 1964 the negotiation of compensation is the most important task. The determination of replacement cost is the foundation for the purpose of compensation by agreement or consent award. Replacement Cost of land for consent award will be determined through negotiations between the land losers and the Negotiation Committee. The price of land has generally been seen more than the market value derived adopting the procedure land down in the LA Act 1894. Since land acquisition proceedings are quasi judicial proceedings offering a minimum price before the award can be passed will not be a fair act for the proceedings. The composition of the committee is given below.

4.6 Negotiation Committee • Assistant Commissioner of the concerned Sub Division Chairman • Assistant Commissioner of KSHIP Secretary • Jurisdictional Executive Engineer Member • Zilla Panchayat Member of the concerned jurisdiction Member 73. The Guidance Value as per the Department of Stamps and Registration for the different categories of land, for the villages along the project road will be obtained from concerned District Registrars. This guidance value will be referred to by the Negotiation Committee. 74. The Zilla Panchayat member of the area is the member of the Committee. Proceedings of the Committee are documented by the AC (LA) of PIU KSHIP who is the member secretary. The public representative, that is the Zilla Panchayat, member on the Committee will be considered as an independent external party for the negotiation and settlement purpose. If needed proceedings can be videographed 75. At this stage, it is not possible to identify the exact owner of the land getting affected. This will be known after Section 19, Notification under KHA, is complete. the details of those losing their lands is given in Annex 4. Table 4-1: Land Acquisition Details Private land Govt Land Total Land Link Details (Acres) (Acres) (Acres) 31A Mudgal- Tavaragere 163.17 0.00 163.17 31B Tavaragere - Gangavathi 216.29 0.00 216.29 TOTAL 380.06 0.00 380.06

4.7 Method of Price fixation a. The concerned Land Acquisition officer who is the member secretary of the Negotiation Committee will call for a meeting; b. Dates for price negotiation will be given village wise. Negotiation will be conducted village wise calling all the land losers together for negotiation. This is to ensure transparency; 21

c. The PIU will provide information on the guidance value of the land to land losers before negotiations; d. For the Districts of Bangalore Urban, Bangalore Rural, Chikkaballapur, Kolar, Ramnagaram, Mysore, Davangere, Belgaum and Dakshin Kannada, the minimum negotiation price will be one and half times the Guidance Value. For all the other districts, other than those mentioned, the minimum price will be twice the guidance value; e. The Negotiation Committee will negotiate the price with the landlord; f. Based on the decision of the Negotiation Committee the Special Land Acquisition Officer will give the compensation; g. Compensation will be given within 30 days of taking possession and receiving all the necessary documents5 by the Special LA officer. In case of delay, a 9% interest will be given to the beneficiary up to a period of one year, after which it will be increased to15% thereafter. (This is as per the provisions of the LA Act); h. On approval of the award by the Special DC or PD, the Special Land Acquisition Officers will make the payments accordingly; and i. Possession of Land will be taken vide Section 19, which will be only after the payment of compensation.

4.8 Failure of KHA and Appellate Committee 76. In the event the landlord does not agree with the rate negotiated by the Negotiation Committee, the award will be passed in the traditional general LA method and the amount will be deposited with the court. The provisions of the Amendment Bill will be followed as necessary.

4.9 Valuation of Assets 77. The valuation of structures and other assets will be carried out by Government approved valuators appointed by the PIU. Valuation will be done on the basis of current PWD Schedule of Rates, without depreciation at replacement cost. Based on the valuation, another 30% will be given. Trees will be valued by the Horticulture/Forest department.

4.10 Cut-Off Date 78. The cut-off date for those who have legal title is the date of Notification under Section 15 of Karnataka Highway Act 1964. The date of census is the cut-off date for those who do not have legal standing for eligibility of assistance under the project. People moving into the COI after this cut-off date will not be entitled to support. It is the responsibility of the PWD to ensure that the COI is maintained free of squatters and encroachers. 79. It is recognized that there will be a margin of error in the census, and any person who was not enumerated but can show documentation or evidence that he/she is rightfully an entitled person will also be included. The Project Implementation Unit is responsible for such verification. A cut-off date slip was issued to the non titled people surveyed. The cut-off date

5 Documents to be furnished include Phani (RTC), Mutation Extract, Vamsha Ruksha (Geneological Tree) and if the interest of land holder is subject to a court decree, a certified copy of such a decree.

22 for non- titleholders, is the date of the start of the census survey on a particular link. The cut- off date for link 31A is 1 August 2009 and for 31B is 12 January 2009. Given below are the details of displaced persons whose structure/assets are getting as on the cut-off date:

4.11 Estimation of land requirement and Preparation of Land Acquisition Plans 80. The Land Acquisition Plan (LAP) for the link road is under preparation. Coordination with revenue department is in progress. The likely timetable for procurement for land acquisition is placed in the implementation schedule. 81. The preparation process of LAP includes: a. From the Land Record office Village map, tippany, hissa tippany, akar band is collected; b. RTC records is collected from the Taluk Office; c. Based on the above documents and spot inspection sketches for LA are made; d. Calculation of land acquisition requirement in a particular survey number is arrived based on the Akarband; e. Field verification of RoW is done from PWD notifications; f. Identify and Stakeout on ground of the areas beyond RoW where private land needs to be acquired as per approved proposed alignment designs; g. Measurement of land proposed to be acquired to be done along with the Revenue Department. This is done in coordination with Project Consultants, PIU staff and revenue officials; h. After field verification land particulars are transferred to each survey sketch; and i. The LA plans have to be finally signed by the Surveyor, Supervisor, Tahsildar, KSHIP AE, KSHIP AEE and Project Consultants.

4.12 Compensation Payment Process 82. The compensation payment process includes: • Compensation to be finalized by the Negotiation Committee with the consent of beneficiary; • The award will be approved by the Special DC LA or Project Director depending on the award amount; and • Cheque payment will be done. The SDRC will assist beneficiaries to open a Bank account incase they do not have an existing bank account. • Consent will be taken in written form.

4.13 Administering the payment of R & R Assistance • All Entitlements to be provided will be verified against losses incurred by the NGO; • Information will be updated in the database; • Bank accounts are to be opened for all beneficiaries; • The CAO will authorize payment of R & R assistance; 23

• All payments will be made through Cheque, directly to the DPs; and • DPs who are in more than one vulnerable category will be paid only once.

24

5 STAKEHOLDERS CONSULTATION, PARTICIPATION AND DISCLOSURE

5.1 Consultation and Community Participation 83. Public consultations were held in Nagalapur in 31A and Herur in 31B, focusing on areas of impact due to widening, at places where congestion has impacts on buildings and where major common property resources are getting affected- such as any religious structures etc. The outcome of the consultations were used for analysis of alternatives and minimizing negative impact of the project.

5.2 Methodology 84. The methodology followed for public consultations was: 1) Group meetings and one to one consultations were held with the displaced persons. 2) Informing all the likely affected persons regarding the meeting including DPs and at village level. Panchayat leaders, gram sabha members, officers from PWD sub- divisions and any local NGOs were also informed about the meetings; and 3) The minutes of the meetings have been recorded, list of participants for each of the meeting along with the signature have been obtained and the photographs of consultations have also been taken. The list of participants and photographs has been provided in Annex 6. 85. During the consultation the people were informed about: (i) KSHIP, including a background on KSHIP Phase A project; (ii) The rural and urban design cross sections of the roads; (iii) The people were informed about KSHIP Resettlement policy and the compensation and assistance provided therein and asked suggestion for improvement so that their suggestions can be incorporated by the project authority for KSHIP; (iv) Proposed safety measures for the road; and (v) The likely impacts of the road, both positive and negative. The Consultations elicited from the people: (i) Their views on the project especially the likely adverse impacts; (ii) Possible mitigation measures in case of adverse impacts; (iii) Means of better delivery of compensation and assistance; (iv) The assurance from the project authority not to marginalize people by depriving them from their livelihood; and (v) Provision of infrastructure such as drinking water and toilets. 86. As a part of the public empowerment through public consultations the stakeholders have written to the Project authority regarding their views on the impact of the project, and the anticipated adverse impacts. These issues have been addressed and responses have been provided. 87. As meaningful consultations in the project is a regular and continuous process, more in-depth consultations will be organized by the implementation NGOs throughout the project cycle.

5.3 Key Findings of the Consultations 88. The consultations have helped in not only achieving the social assessment objectives, but also assisted in gathering suggestions for mitigation of adverse impacts, improvement in designs and facilitating inputs for the resettlement plan preparation and 25 implementation. The consultations for the links were held at Nagalapur on 5 July 2010 for link 31A and Herur on 5 July 2010 for 31B. There were 39 participants for link 31A meeting and 72 participants for link 31B meeting. 89. The issues discussed and the outcome has been given below:

Table 5-1: Key Issues: 31 A

Name Sex Profession Issues discussed Response Sharanapp M Barber How do you compensate for It was explained that the PA a Maski, the loss of bore well? will replace the bore well by Nagalapura digging a bore well in place . identified by the person losing the bore well. In case there is no water found then the project will compensate by giving the replace cost of the bore well. Shivagena M Farmer He said that they have not It was explained for the earlier ppa been compensated for the project the matter has to be Kurubaru, land acquisition done for the looked into by PWD/DC office. Nagalapura existing road. Project However, for this project . Authority should also give compensation will be paid the compensation for the according to the project policy. acquisition done earlier. Sangappa M Farmer Two road alignments have It was explained for the earlier Hugar, already been done on our 3- project the matter has to be Nagalapura acre agricultural land without looked into by PWD/DC office. . any compensation paid and However, for this project now the road is being again compensation will be paid by widened and we will lose the according to the project policy. remaining land also. Please give us the land at some other location or give the The project will try and save compensation for land the bore well as far as acquired earlier. possible. However, if it was not He said he will lose the possible to retain, the PA will existing bore well which is dig another bore well. yielding water. We have tried It was reassured that further bore well at other location consultations will be held. but without yield. So please widen the existing road itself without realigning the road. You should conduct one more separate meeting and discuss. Somashek M Grama He said they are still paying It was explained for the earlier ara, Panchayat the tax for the land already project the matter has to be Nagalapura h member acquired for the existing looked into by PWD/DC office. . road. You should arrange to However, for this project compensate for the land lost compensation will be paid earlier. according to the project policy. It was explained that those having shops in government land will be provided with For businessmen having alternative site and assistance their shop in Government. for rehabilitation so that their

26

Name Sex Profession Issues discussed Response land. How are they going to livelihood is not affected. be compensated? Mudukana M Farmer He said they are earning It was explained that those gowda their livelihood by the Pan having shops in government. Shiragumpi shop on the road side. They land will be provided with , will be affected. He asked for alternative site and assistance Nagalapura compensation so that their for rehabilitation so that their . lives are not affected. livelihood is not affected.

Table 5-2: Key Issues: 31 B

Name Sex Profession Issues discussed Response Laxmi M Business – He said that the government It was explained that Reddy Herur Flour Mill rate given for land is low. compensation for land will be The people want market rate based on negotiation as per the to be given for the land. KHA. A Negotiation committee will be set up. 1.5 to 2 times the guidance value will be taken as the minimum price for Their bore well, which is negotiation. yielding good water, is It was explained that the PA will getting affected. Similar replace the bore well by digging a water yield will not be found bore well in place identified by in other bore wells. If the the person losing the bore well. bore well is affected, the In case there is no water found farmers will suffer. then the project will compensate by giving the replace cost of the He said they have a flour mill bore well. which is getting affected. It was explained the project will There are 4 workers who are provide assistance to employees working in the mill, they whose livelihood is getting should also be affected. PA will provide compensated. subsistence allowance of Rs. 15,000; Training assistance will be provided for income generating vocational training and skills upgrading options as per affected persons choice; and Employment opportunity for affected persons as per his skills and availability of suitable work in road construction work. Ganesh M Contractor He said that even if 2-3 It was explained that only if 20 Herur houses are affected, the PA houses were getting affected, it should develop the new was feasible to provide a houses like a Resettlement resettlement colony with all the colony and and not only in amenities. the case of 20 houses. Chinnappa M Un Last year in Kanakagiri, It was explained that it was held Nayak Herur employed there was a similar meeting for the KSHIP Project but under held. different funding source. Uday Kumar M Hotel He has taken a private It was explained that commercial Herur Business property on lease and is tenants will be provided with running a hotel. Now the rental assistance, including land is being acquired – he shifting assistance and an wanted to know what income generating asset up to compensation will be given. Rs.75000. 27

Name Sex Profession Issues discussed Response Manjunatha M Pan shop He said that he is running a It was explained that all those Herur pan shop. However, he is who are losing shops will be from the middle class provided with alternative site and household. He said that the assistance for rehabilitation so project will give more that their livelihood is not assistance to BPL affected. The project does not households. He said equal give entitlements based on BPL assistance should be given category but on the basis of loss. top all those who are losing their shops. Nagraj Herur M Farmer He said that all those who It was explained that all those are losing shops in the area who are losing shops will be should not be distinguished provided with alternative site and on the basis of APL and assistance for rehabilitation so BPL. All should be that their livelihood is not compensated equally. affected. The project does not give entitlements based on BPL category but on the basis of loss. Virupaksha M Labour He said that they are It was explained that if a house Herur working as labour. If their was affected by the project, the houses are affected, they PA will provide for alternative have no resources to rebuild house or a site and construction their houses. They asked the assistance up to Rs40,000. If government to provide for more than 20 houses are getting alternate houses. affected in 2 km stretch, then a resettlement colony will be constructed. Siddengowd M Farmer He said that compensation He said according to the project a Hiregowda should be paid before the principles compensation and start of construction or the assistance has to be paid before people will stop the work. the start of civil work. Virupaksha M Lawyer He said the project should It was explained that the design Gowda maintain the road as it is. of the road will be looked into by Herur The PA can also explore the the technical team. possibility of a bypass, as it will be less hazardous for the people of the village. If during project implementation PIU KSHIP or implementation NGO come across any case where affected persons have not been timely paid during previous land acquisition (for the same road) such cases will be dealt on the case to case basis and PIU KSHIP will facilitate the acquiring body to make payment to the affected persons through GRC and this will be documented.

5.4 Levels of Consultation 90. The consultation program is tiered and conducted at several levels that included, among others: (i) Heads of households/members likely to be impacted; (ii) Villagers and Village Panchayats; and (iii) and Implementing Agency and line Departments.

5.5 Consultations during implementation 91. Several additional DP consultations will be conducted during RP implementation. As a follow-up of the local-level DP consultations held during project preparation, further consultations will be conducted by the NGO during implementation. In the first round of consultations, information on RP and entitlement policy and options will be disseminated. This will involve explaining the Entitlement Framework and resettlement options to the DPs and soliciting their support and cooperation. This will help finalize agreement on the various

28 entitlements provided in the entitlement framework. Next round of consultation involves agreements on compensation and assistance options and entitlements with DPs and completion of DP identity card indicating the accepted entitlement package. The next round of DP consultations will occur when compensation and assistance are provided and actual resettlement begins and the NGO has to facilitate relocation.

5.6 Disclosure 92. In order to make the RP implementation process transparent, a series of FGDs/ meetings etc will be held with all stakeholders for dissemination of information regarding rehabilitation process and entitlement framework. The RP and entitlements will be disclosed in public meeting. The salient features of RP and the R & R policy will be translated in Kannada and disclosed through public consultations to be held in taluka head quarter of each districts through which the particular link pass through. It will also be disclosed through the PWD, Government of Karnataka website. In addition brochure of the Land Acquisition and the R & R Policy will also be provided. All copies will be kept in: (i) State Government Library at Bangalore; (ii) District libraries of the Project; and (iii) in the Panchayat offices along the project roads. The RP document will also be disclosed on ADBs website as per the disclosure requirements. 93. A Public Consultation and Disclosure Plan will be prepared by PIU/NGO for each of the project roads as per the format below: 94. Table 5-3: Public Consultation and Disclosure Plan Timing Agencies Activity Task (Date/ Remarks

Period) Stakeholder Mapping of the identification project area Project information Distribution of dissemination information leaflets to dispalced persons (DPs) Consultative Discuss potential meetings with APs impacts of the during scoping project phase Public Notification Publish list of affected lands/sites in a local newspaper; establish eligibility cut-off date Socio-economic Collect socioeconomic survey information on DP’s perception on the project Consultative Discuss meetings on entitlements, resettlement compensation mitigation rates, grievance measures redress mechanisms Publicize the Distribute leaflets 29 resettlement plan or booklets in local (RP) language

Full disclosure of Distribute RP in the RP to APs local language to DPs Internet disclosure of RP posted on ADB the RP and/or EA website

Consultative Face to face meetings during meetings with DPs detailed measurement survey(DMS) Disclosure after Disclose updated DMS RP to DPs

Internet disclosure of Updated RP the updated RP posted on ADB and/or EA website

30

6 LEGAL FRAMEWORK 95. This chapter provides an overview of the applicable policy and Acts for the Project.

6.1 The National Policy on Resettlement and Rehabilitation for Project Affected Households, 2007 96. Until recent time, in India, there were no safeguard policy to deal with resettlement and rehabilitation of displaced persons. There was no uniform approach adopted by states towards the displaced persons. In the absence of central policies, ad hoc administrative instructions, in conformity with the Land Acquisition Act was in practice. In 2007, the GOI developed a National Social Safeguard Policy. This was developed taking into the consideration the safeguard policies of international development bodies like the World Bank, Asian Development Bank etc. The National Policy on Resettlement and Rehabilitation for Project Affected Households, 2007 (NRRP) came into effect in October 2007. The salient feature and the statements of the NRRP policy are as follows: (i) SIA shall be mandatory for all projects involving displacement of four hundred or more households’ en masses in plain areas, or two hundred or more households en masses in tribal or hilly areas etc. Coordination with EIA in the context of the public hearing done in the project affected area for EIA shall also cover issues related to SIA; (ii) Consultations with affected people and disclosure of relevant information to them at various stages of resettlement planning; (iii) Affected people without legal rights also need to be assisted (affected people categorized landless agricultural workers, forest dwellers, tenants and artisans who are critically dependent on the acquired assets for their subsistence/ livelihoods); (iv) Prepare resettlement plans that are disclosed to the affected people in draft form, and reviewed and approved by competent authorities; (v) Collection of socioeconomic baseline for project affected households; (vi) Project displaced persons (whose entire land is taken) will receive land in lieu of his loss. In addition, cash assistance will be paid for regaining livelihood; (vii) Vulnerable project affected people will get extra cash/kind assistance; (viii) Purchase of land from any project affected persons would be through consent award (negotiation of rate between land owner and project authority); (ix) The Grievance Redressal Cell shall have representatives of women, Schedule Castes, Scheduled Tribes residing in the affected zone. The Cell shall have the power to consider and dispose of all complaints relating to resettlement and rehabilitation against the decision of the Administrator/R & R Committee at Project level; (x) A monitoring cell should be constituted under the project; and (xi) Each project affected household comprising of rural artisan/small trader and self- employed person shall get one-time financial assistance for construction of working shed/shop for livelihood support. 31

6.2 The Land Acquisition (LA) Act of 1894 97. The Land Acquisition (LA) Act of 1984 is commonly used for acquisition of land for any public purpose. It is used at the State level with State amendments made to suit local requirements. Expropriation of and compensation for land, houses and other immovable assets are carried out under the Land Acquisition (Amendment) Act, 1984. The Act deals with compulsory acquisition of private land for public purpose. The procedures set out include: (i)Preliminary notification(Section 4); (ii) Declaration of Notification (Section 6); (iii) Notice to persons interested (Section 9); (iv) Enquiry and award (Section 11); and (v) Possession (Section 16). 98. The 1984 amendments to the LA Act addressed the matter of compensation and delays in payment. As regards to the level of compensation, the rate of solatium was increased from 15% to 30%. For delays, the amendment requires that: (i) A time of one year was fixed for completing all formalities between the issuance of Section 4 and Section 6; and (ii) The compensation award must be determined within two years of the issuing of section 6 notification. Interest is payable at a rate of 12% per year from the date of preliminary notification to the date of dispossession. These changes apply to cases before the Civil Courts even for awards made before the enactment of the amendments.

6.3 Asian Development Bank’s Safeguard Policy 99. The ADB’s Safeguard Policy Statement 2009, recognizes and addresses the R & R impacts of all the affected persons, irrespective of their titles, and requires the preparation of RP in every instance where involuntary resettlement occurs. The ADB policy requirements are: (a) avoid or minimize impacts where possible; (b) consultation with the affected people in project planning and implementation; (c) payments of compensation for acquired assets at the replacement cost; (d) ensure that no one is worse off as a result of resettlement and would maintain at least their original standard of living; (e) resettlement assistance to affected persons, including non-titled persons; and (f) special attention to vulnerable people/groups. 100. The three important elements of the Involuntary Resettlement policy of ADB are (i) compensation to replace lost assets, livelihood, and income; (ii) assistance for relocation, including provision of relocation sites with appropriate facilities and services; and (iii) assistance for rehabilitation to achieve at least the same level of well-being with the project as without it. Some or all of these elements may be present in a project involving involuntary resettlement. For any ADB operation requiring involuntary resettlement, resettlement planning is an integral part of project design, to be dealt with from the earliest stages of the project cycle. The main policy principles of the SPS are : • Screen the project early on to identify past, present, and future involuntary resettlement impacts and risks. Determine the scope of resettlement planning

32

through a survey and/or census of displaced persons, including a gender analysis, specifically related to resettlement impacts and risks. • Carry out meaningful consultations with affected persons, host communities, and concerned non-government organizations. Inform all displaced persons of their entitlements and resettlement options. Ensure their participation in planning, implementation, and monitoring and reporting of resettlement programs. Pay particular attention to the needs of vulnerable groups, especially those below the poverty line, the landless, the elderly, women and children, and Indigenous Peoples, and those without legal title to land, and ensure their participation in consultations. Establish a grievance redress mechanism to receive and facilitate resolution of the affected persons’ concerns. Support the social and cultural institutions of displaced persons and their host population. Where involuntary resettlement impacts and risks are highly complex and sensitive, compensation and resettlement decisions should be preceded by a social preparation phase. • Improve, or at least restore, the livelihoods of all displaced persons through (i) land-based resettlement strategies when affected livelihoods are land based where possible or cash compensation at replacement value for land when the loss of land does not undermine livelihoods, (ii) prompt replacement of assets with access to assets of equal or higher value, (iii) prompt compensation at full replacement cost for assets that cannot be restored, and (iv) additional revenues and services through benefit sharing schemes where possible. • Provide physically and economically displaced persons with needed assistance, including the following: (i) if there is relocation, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, integration of resettled persons economically and socially into their host communities, and extension of project benefits to host communities; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) civic infrastructure and community services, as required. • Improve the standards of living of the displaced poor and other vulnerable groups, including women, to at least national minimum standards. In rural areas provide them with legal and affordable access to land and resources, and in urban areas provide them with appropriate income sources and legal and affordable access to adequate housing. • Develop procedures in a transparent, consistent, and equitable manner if land acquisition is through negotiated settlement to ensure that those people who enter into negotiated settlements will maintain the same or better income and livelihood status. • Ensure that displaced persons without titles to land or any recognizable legal rights to land are eligible for resettlement assistance and compensation for loss of non-land assets. • Prepare a resettlement plan elaborating on displaced persons’ entitlements, the income and livelihood restoration strategy, institutional arrangements, 33

monitoring and reporting framework, budget, and time-bound implementation schedule. • Disclose a draft resettlement plan, including documentation of the consultation process in a timely manner, before project appraisal, in an accessible place and a form and language(s) understandable to affected persons and other stakeholders. Disclose the final resettlement plan and its updates to affected persons and other stakeholders. • Conceive and execute involuntary resettlement as part of a development project or program. Include the full costs of resettlement in the presentation of project’s costs and benefits. For a project with significant involuntary resettlement impacts, consider implementing the involuntary resettlement component of the project as a stand-alone operation. • Pay compensation and provide other resettlement entitlements before physical or economic displacement. Implement the resettlement plan under close supervision throughout project implementation. • Monitor and assess resettlement outcomes, their impacts on the standards of living of displaced persons, and whether the objectives of the resettlement plan have been achieved by taking into account the baseline conditions and the results of resettlement monitoring. Disclose monitoring reports.

6.4 Indigenous Peoples 101. Indigenous Peoples (IP) are defined by ADB’S Indigenous Peoples Policy are those having distinct social, cultural, economic, and political traditions and institutions compared with the mainstream or dominant society. IP generally share the following characteristics: (i) descent from a population living in an area before current national territories were defined; (ii) maintenance of cultural and social identities separate from those of dominant societies; (iii) self-identification and identification by others as being part of a distinct cultural group; (iv) linguistic identity different from that of dominant society; (v) political traditions and institutions distinct from dominant culture; (vi) economic systems oriented more toward traditional production systems; and (vii) unique ties and attachments to traditional habitats and ancestral territories.

6.5 Karnataka Highway Act 1964 102. In addition to the above measures, realizing the need of infrastructure development like roads in timely manner, the PWD GOK has decided to acquire the land in KSHIP through the “The Karnataka Highways Act 1964”(KHA,1964) instead of using the Land Acquisition Act of 1894.

6.6 Comparison of National and State Policies with Asian Development Banks SPS -2009 103. The National Rehabilitation and Resettlement Policy of 2007 (NRRP-2007), represents a significant milestone in the development of a systematic approach to address resettlement issues in India and closes significantly the gap between Indian national policies and those of ADBs. The Land Acquisition Act (LAA) of 1894 (as amended in 1984) gives

34 directives for the acquisition of land in the public interest and provides benefits only to titleholders. The LAA also does not provide replacement cost for the loss of land and assets. By contrast, the NRRP recognizes non-titleholders, although the basic requirement is for the non-titleholder to have been in the project-affected area at least three years prior to the declaration of the area as an affected area. In Karnataka there are various project level R & R Policies. The KSHIP policy tries to address any gaps in the existing policies which are relevant for the project. Table 6-1: Comparison of gaps in various Acts and Policies with ADBs SPS LA NRRP-2007 ADB KSHIP Policy Cut-off Date 3 years prior to Date of survey will Date of survey will be for date of survey for be considered as considered as cut-off for Assistance non-titleholders cut-off for non- non-titleholders and the and the date of titleholders and the date of section 15 section 15 date of section 15 notification for titleholder. notification for notification for titleholders. titleholder. Social Impact Mandates SIA Requires a Poverty A Poverty and Social Assessment survey for 400 or and Social Assessment study has more getting Assessment study. been done for this displaced en No minimum project. masse in plain threshold area or more than prescribed. 200 households in hilly area Replacement No Provides for Provides for Provides for replacement Cost of land replaceme alternative lands; replacement cost cost (compensation) of nt cost of where not of land. land through negotiations land possible, as per KHA. monetary compensation Assistance to No direct mention This is covered. Provides assistance to tenants of assistance to tenants losing losing tenants losing commercial and commercial commercial and residential structures. and residential residential structures. structures 35

7 ENTITLEMENTS, ASSISTANCE AND BENEFITS

7.1 KSHIP Policy 104. The National, State and Departmental Code provides for the framework for resettlement and rehabilitation activities. However, within the context of the above mentioned policy frameworks, a project specific Resettlement Policy has been prepared. The project policy has been evolved through a number of discussions by PIU. Good practices of the other States have also been taken into consideration in addition to considering the relevant policy provisions and entitlements under each category of loss mentioned in National Policy for Resettlement and Rehabilitation 2007.

7.2 Impacts and Entitlements 105. This policy addresses the direct and indirect impacts of project construction and operation on displaced persons, households, and communities. The most direct and immediate impacts are those associated with project construction, mainly land acquisition. Other losses include loss of shelter, and other assets within the project’s corridor of impact, as well as roadside structure, business establishments, and public facilities. Mitigation is provided through compensation and assistance to project displaced persons, households, and groups. These social units are entitled to compensation and assistance on the basis of this policy framework adopted by the project. The policy provides mitigation for: • loss of assets, including land and house or work place; • loss of livelihood or income opportunities; and • Collective impacts on groups, such as loss of community assets, common property resources, and others. 106. Loss of assets and livelihood are impact categories that represent direct project impacts on an identified population. The people likely to be affected will be surveyed and registered, and project monitoring and evaluation will compare long-term impact against baseline socioeconomic data. Collective impacts on groups represent direct and indirect impacts, where group members need not be individually registered. Group-oriented gains and losses in this category are less quantifiable in terms of impacts on the individual. Mitigation and support mechanisms are collectively oriented, and the monitoring of these efforts will examine the impact and benefits for the groups involved. The GOK from time to time will make amendments in this policy as and when required.

7.3 Corridor of Impact 107. Right of Way is the lawfully acquired corridor of public land owned by the State Government and administered by the PWD for the transit of the existing road. Using available records with the PWD and the Revenue Department, the project will verify the boundaries of the legal right of way, as well as boundaries of private properties within and in the vicinity of the likely Corridor of Impact. Displacement under the project will be limited to the corridor required for the road and its safety zone. This corridor is referred to as the Corridor of Impact. Within this corridor, there should be no structures or other hindrances. The advantage of this approach is that such a corridor is easier to maintain free of

36 encumbrances than the full Right of Way. Where the COI is beyond the RoW land acquisition will be required.

7.4 Targeted support to vulnerable groups 108. The project will develop target assistance for groups such as women-headed households, physically challenged, widow and persons above the age of 60 years. Attention will be given on a case by case basis, with regard to their rehabilitation, livelihood, educational opportunities, vocational training, etc.

7.5 Option and Choices 109. The project will provide options and choices among different entitlements to the affected population. As part of the project consultation and participation mechanisms, people will be informed and consulted about the project and its impacts, and their entitlements and options. The affected population will be counselled so that they are able to make informed choices among the options provided.

7.6 Principles 110. This policy is based on the principle that the population affected by the project will be assisted to improve their former living standards. The policy emphasizes that involuntary resettlement will be avoided or minimized where possible by exploring other alternative project designs. Where displacement is unavoidable, people losing assets, livelihood or other resources shall be assisted in improving their former living standards. The policy document describes the details of entitlements and type of assistance to be extended to the affected persons, which will become the basis for preparing a detailed and time bound Resettlement Plan (RP). The RP will contain the implementation details on how to ensure that principles and provisions of this policy can be implemented. The Resettlement Plan will describe the approach to be followed in minimizing and mitigating negative social and economic impacts caused by the project, including displacement. 111. This policy identifies categories of expected project impacts, including loss of property and assets, loss of livelihood, and other social and economic impacts on groups and roadside communities. All people, households and groups adversely affected by the project would be registered and support will be given in accordance with these policy provisions. All assistance will be given as one time payment.

7.7 Definitions a. Agricultural land means lands being used for the purpose of: (i) agriculture or horticulture; (ii) raising of crops, grass or garden produce; and (iii) land used by an agriculturist for the grazing of cattle, but does not include land used for cutting of wood only. b. Assistance refers to the support provided to displaced persons in the form of ex-gratia payments, loans, asset services, etc. in order to improve the standard of living and reduce the negative impacts of the project. c. Bagar Hukum land is any government land which is unauthorizedly occupied by a person and such person has applied for regularization of the same under 37

the Karnataka Land Revenue Rules under 108 C(1) is called Bagar Hukum land. d. Below poverty line or BPL Household means below poverty line households as defined by the Planning Commission of India, from time to time, and those included in the State BPL list in force. e. Compensation refers to the amount paid under The Karnataka Highways Act, 1964 and The Karnataka Highways Rules, 1965, for private property, structures and other assets acquired for the project. It refers to the amount as given in the Entitlement Matrix for the project. f. Cut-off Date is the date of Notification under Section 15 of Karnataka Highways Act, 1964 will be the cutoff date where the land acquisition will be required. For Non-titleholders the date of socioeconomic survey will be considered as the cut-off date. g. Displaced households (DHs) means- (i) a household whose primary place of residence or other property or source of livelihood is adversely affected by the acquisition of land for a project or involuntary displacement due to any other reason; (ii) any tenure holder, tenant, lessee or owner of other property, who on account of acquisition of land (including Bagar Hukum or other property) in the affected area of otherwise, has been involuntary displaced from such land or other property; (iii) any agricultural or non-agricultural laborer, landless person (not having homestead land or agricultural land) rural artisan, small trader or self-employed person; who has been residing or has engaged in any trade, business, occupation or vocation in the affected area, and who has been deprived of earning his livelihood or alienated wholly or substantially from the main source of his trade, business, occupation or vocation because of the acquisition of land in the affected area or being involuntarily displaced for any other reason; h. Displaced Persons (DPs) any person who has economic interests or residence within the project impact corridor and who may be adversely affected directly by the project. Project displaced persons include those displaced, those losing commercial or residential structures in whole or part, those losing agricultural land or homesteads in whole or part, and those losing income sources as a result of project action. i. Encroachers are those persons who have extended their building, business premises or work places into government lands. Assistance will be provided to these persons, based on their loss. j. Household includes a person, his or her spouse, minor sons, unmarried daughters, minor brothers, unmarried sisters, father, mother and other relatives residing with him or her and dependent on him or her for their livelihood, and includes “nuclear household” consisting of a person, his or her spouse, and minor children; k. Government refers to the Government of Karnataka l. Land acquisition or acquisition land means acquisition of land under the Karnataka Highways Act, 1964;

38

m. Marginal farmer means a cultivator with an unirrigated land holding up to one hectare or irrigated land holding up to half hectare; n. Minimum Wages The minimum wage of a person for his/her services/labour is Rs. 100 per day as per Government Notification NoLD96 LMW 2005 dated 30.07.2007. o. Non-Perennial Crop: Any plant species, either grown naturally or through cultivation that lives for a season and perishes with harvesting of its yields has been considered as a non-perennial crop in the project. For example, paddy, sugarcane, groundnut, etc. p. Notification means a notification published in the Gazette of India, or as the case may be, the Gazette of State. q. Perennial Crop: Any plant species that live for years and yields its products after a certain age of maturity is a perennial crop. Generally trees, either grown naturally or by horticultural and yield fruits or timber have been considered as perennial crop in the project. For example, tamarind, coconut, mango, teak, neem etc. are perennial crops. r. Replacement Cost of the acquired assets and property is the amount required for the affected house hold to replace/reconstruct the lost assets through purchase in the open market. Replacement cost will be calculated at PWDs current Schedule of Rates without depreciation. Replacement cost will be in line with the provisos of the Entitlement Matrix of the project. s. Severance of Land can be defined of a land holding divided into two or more pieces due to acquisition of land mainly for laying new project alignment, such as a bypass or a realignment. t. Small farmer means a cultivator with an unirrigated land holding up to two hectares or with an irrigated land holding up to one hectare, but more than the holding of a marginal farmer. u. Squatter means those persons who have illegally occupied government lands for residential, business and/or other purposes. v. Tenants are those persons having bonafide tenancy agreements, written or unwritten, with a private property owner with clear property titles, to occupy a structure or land for residence, business or other purposes. w. Vulnerable groups persons such as physically challenged, widows, or persons above sixty years of age. x. Women-headed Household is headed by a woman and does not have a male earning member. This woman may be a widowed, separated or deserted person.

7.8 Entitlements 112. The DPs will be provided with the benefits described in the succeeding paragraphs. 113. Loss of Land: This includes all those who have legal title to land. They will be provided with Compensation as per Replacement Cost through direct negotiation as per Karnataka State Highway Act, 1964 + stamp duty and registration charges. Stamp duty and 39 registration charges are applicable for those who accept negotiation price. Minimum negotiated price for the Districts of Bangalore Urban, Bangalore Rural, Chikkaballapur, Ramnagaram, and Corporation / Municipal limits of other district HQs will be one and half times the Guidance Value. For all other areas other than those mentioned above the minimum negotiated price will be twice the Guidance Value.6 OR average sales statistics, whichever is higher7. In case of severance of land an additional 25% compensation will be paid to the land loser if he retains the remaining plot OR if the remaining land is not viable and the land owner opts to surrender the entire plot to the project, compensation as given earlier will be applicable; Loss of perennial crops and non-perennial crops will be compensated in accordance with Horticulture department valuation process; A grant of Rs. 15,000 for replacement of Cattle shed; Water yielding bores will be replaced in the location identified by the affected person in the remaining land holding subject to availability of water. In case water is not available, replacement cost of the borewell at current PWD SR rates and 30% solatium will be given. In case of land owners who become landless or marginal farmers, the following additional entitlements will be offered: (a) subsistence allowance of Rs.30,000 for land less and marginal; and, (b) assistance for creating Income generation asset valued up to Rs.75,000; Additional amount of Rs.20,000 will be restricted to those who loose narrow stretch of land as ex gratia compensation in lieu of all other benefits(Narrow stretch of land is defined as persons losing up to five guntas of land). For those becoming landless and all marginal farmers training assistance will be provided for income generating vocational training and skill upgrading options as per affected persons choice .The NGO will ensure linkages of the trained persons to ongoing programmes, to facilitate employment and marketing opportunities; Employment opportunity for affected persons as per his skills and availability of suitable work in road construction work; In case of Bagar hukum lands - 50% of compensation and other benefits as available for land owners. Any Government land which is unauthorizedly occupied by a person and such person has applied for regularization of the same under the Karnataka Land Revenue Rules under 108 C(1) is called Bagar Hukum land. Under Rule 108C section 94A, of the Karnataka Land Revenue Act,1966, the Tahsildar is the custodian of the records and he will issue the certification whether the application is pending before the Committee or not. Tahsildar is the Secretary of the Committee for regularization of unauthorized occupation of government land. 114. Loss of residential structures: These persons with legal titles losing their residential structures. They will get compensation at current PWD scheduled rates without depreciation and 30% solatium at replacement cost; Alternative houses in resettlement colony or developed plot and construction cost of Rs. 40,000 linked to construction progress; Additional 25% compensation for partially affected structures towards reconstruction; Shifting assistance of Rs. 10,000; Subsistence allowance of Rs. 30,000. In case more than 25% of house is affected and unviable for retaining, full compensation will be paid;

6 Revised Guidance Value of the properties in Bangalore Urban, Bangalore Rural, Chikkaballpur, Ramanagaram and Corporation/Municipal limits is two - three times higher than the earlier Guidance Value. Hence one and half times the Guidance Value is proposed as minimum negotiated price. In other areas ratio of revision is reasonably low, hence twice the Guidance Value is proposed as minimum price. 7 The average Sales Statistics is in line with LA Amendment Bill. In the LA Amendment Bill there are different modalities in determining and assessing the market value, any one among them would be adopted wherein the land loser gets the maximum market value.

40

Resettlement colonies will be developed if more than 20 households are displaced in 2 Km continuous stretch; Plot size will be equivalent to size lost subject to a maximum of 369 sq m/1200sq ft in rural area and 184 sq m /600 sq ft in urban areas; People have right to salvage the affected materials. 115. Loss of commercial structures: These are persons with legal titles who will loose their commercial structures. They will get compensation at current PWD scheduled rates without depreciation and 30% solatium at replacement cost; Alternative shop or assistance for income generation asset valuated up to Rs. 75,000; Additional 25% compensation for partially affected structures; Shifting assistance of Rs. 10,000; Subsistence allowance of Rs. 30,000; Shopping units with 100-150 sq ft will be constructed if more than 20 shops are affected in a continuous stretch of two km and opt for shop. People have right to salvage the affected materials; Training for self-employment will be provided to one adult per household as needed. 116. Loss of residential cum commercial structures: These are persons who loose their commercial cum residential structures. They will get the following entitlements: Compensation at current PWD scheduled rates without depreciation and 30% solatium at replacement cost; Alternative shop or assistance for income generation asset valuated up to Rs. 75,000 or Alternative houses in resettlement colony or developed plot and construction cost of Rs. 40,000 linked to construction progress ; Additional 25% compensation for partially affected structures; Shifting assistance of Rs. 10,000 ; Subsistence allowance of Rs. 30,000 ;Additional amount of Rs. 25,000 as grant. In case more than 25 of house is affected and unviable for retaining, full compensation will be paid ; Resettlement colonies will be developed if more than 20 households are displaced in 2 Km continuous stretch;Plot size will be equivalent to size lost subject to a maximum of 369 sq m/1200sq ft in rural area and 184 sq m /600 sq ft in urban areas; Shopping units with 100-150 sq ft will be constructed if more than 20 shops are affected in a continuous stretch of 2 km and opt for shop ; People have right to salvage the affected materials ; Training for self-employment will be provided to one adult per household as needed. 117. Tenants losing residential structure: These are persons who are residing as tenants. They will be eligible for Rental allowance for 6 months at Rs. 500 per month in rural and Rs. 1,000 in urban areas; Shifting assistance of Rs. 10,000. 118. Tenants losing commercial structure: These are persons who are carrying out commercial activities as tenats. They will be eligible for Rental allowance for 6 months at Rs. 1000 per month in rural and Rs. 1500 in urban areas; Shifting assistance of Rs. 10,000; Assistance for income generation asset up to Rs. 75,000. 119. Tenants losing residential cum commercial structure; These are tenants who reside and carry out commercial activity in the same structure. These persons will be entitled to Rental allowance for 6 months at Rs. 1,000 per month in rural and Rs. 1,500 in urban areas; Shifting assistance of Rs. 10,000; Assistance for income generation asset up to Rs. 75,000. 120. Non-titleholders – residential squatters: These are persons without legal title who are residing on government property. These persons will be asiisted with House in resettlement colony or developed plot and construction cost of Rs. 40,000 linked to construction progress; Subsistence allowance of Rs.15,000 ; Shifting Allowance of Rs.5,000. 41

House size in resettlement colony to be minimum of 25 sqm/270 sq ft Resettlement colony will be constructed if more than 20 residential squatters are getting affected in a continuous stretch of 2 km and opted for same; Developed plot size will be allotted of 25 sq m/ 270 sq ft in urban area and 33 sq m /350 sq ft in rural area. 121. Non-titleholders – commercial squatters: These are persons without legal title who are carrying out commercial activity on government property. These persons will be asiisted with 122. Alternative shop of 100 sq ft or assistance for income generation asset valuated up to Rs. 30,000; Subsistence allowance of Rs.15,000; Shifting Allowance of Rs.5000. Shopping units will be constructed if more than 20 shops are affected in a continuous stretch of two km and opted for shop. 123. Encroachers: These are persons whose structures have encroached on government land. These persons will be provided Replacement cost of affected structure calculated at current PWD scheduled rates without depreciation and compensation of Crop loss or advance notice for harvesting crops 124. Loss of primary source of income: Those persons who are working as employees or agricultural labours who depend upon an existing activity getting affected. These persons will be entitled to Subsistence allowance of Rs. 15,000. Training assistance will be provided for income generating vocational training and skill upgrading options as per affected person’s choice; Employment opportunity for affected persons as per his skills and availability of suitable work in road construction work will be provided. Training for self- employment will be provided to one adult per household as needed 125. Vulnerable groups: Widows, the physically challenged and those aged above 60 years: These persons will be entitled to Assistance to include in government pension schemes if not included, if eligible as per Government criteria (OR) Lump-sum amount of Rs. 25,000 ; Training assistance will be provided for income generating vocational training and skill upgrading options as per choice; This will be restricted to those who have no or cannot be provided with alterative livelihood sources. 126. Community Assets getting affected will be reconstructed and be transferred to Local authorities for maintenance 127. Unidentified Impacts : Unforeseen impacts shall be documented and mitigated based on the principles provided in this policy 128. All amounts in this entitlement matrix are fixed as of April 01, 2010. These will increased 10 % annually on first day of April every year. The same will hold good for guidance value also if not revised by the GoK.

42

7.9 Entitlement Matrix 129. The entitlement matrix will guide to offer compensation and assistance to those persons affected by the project. The detailed entitlement matrix for the project is given in Table 7-1. Table 7-1: Entitlement Matrix

No. Impact Entitlements Remarks Category I. Title Holders (a) Loss of land 1. Compensation as per the • Stamp duty and registration principle of replacement cost charges are applicable for through direct negotiation as those who accept negotiation provided for in the Karnataka price. State Highway Act, 1964 + stamp duty and registration charges; • Minimum negotiated price for 2. Compensation offered is cash the Districts of Bangalore for land Urban, Bangalore Rural,

Chikkaballapur, Ramnagaram, and Corporation / Municipal limits of other district HQs will be 1.5 times the Guidance Value. For all other areas

other than those mentioned

above the minimum negotiated price will be 2 times the Guidance Value.1 OR average sales statistics, which ever is higher.2

3. In case of severance of land an additional 25% compensation will be paid to the land loser if he retains the remaining plot OR if the remaining land is not viable and the land owner opts

3 As per the NRRP-2007 the acquiring body has to provide rehabilitation grant equivalent to 750 days minimum agricultural wages. At present the minimum agricultural wages is Rs. 100/day. The NGO will ascertain the actual needs of the displaced persons and assist in creating assets. 4 Bagar Hukum lands are government lands which are unauthorizedly cultivated by persons without legal documents. Applications for regularization that are pending before the regularization committee. 1 Revised Guidance Value of the properties in Bangalore Urban, Bangalore Rural, Chikkaballpur, Ramanagaram and Corporation/Municipal limits is 2-3 times higher than the earlier Guidance Value. Hence 1.5 times the Guidance Value is proposed as minimum negotiated price. In other areas ratio of revision is reasonably low, hence 2 times the Guidance Value is proposed as minimum price. 2 The average Sales Statistics is in line with LA Amendment Bill. In the LA Amendment Bill there are different modalities in determining and assessing the market value, any one among them would be adopted wherein the land loser gets the maximum market value. 43

No. Impact Entitlements Remarks Category to surrender the entire plot to the project, compensation as given in No. 1 will be applicable;

4. Loss of perennial crops and non-perennial crops will be compensated in accordance with Horticulture department valuation process, which is the replacement cost.

5. A grant of Rs. 15,000 for replacement of Cattle shed;

6. Water yielding bores will be replaced in the location identified by the affected person in the remaining land holding subject to availability of water. In case water is not available replacement cost of the borewell at current PWD SR rates without depreciation charges and 30% solatium will be given. • Marginal farmer is defined as those left with 1 hectare of 7. In case of land owners who non-irrigated or 0.50 hectare become landless or marginal of irrigation or combination of farmers, the following both additional entitlements will be offered: (a) subsistence allowance of Rs. 30,000 for land less and marginal; and, (b) assistance for creating Income generation asset valued up to Rs.75,0003; • Narrow stretch of land is defined as persons losing an 8. Additional amount of Rs. area that is up to 5 guntas of 20,000 will be restricted to land. those who lose narrow stretch of land as ex gratia compensation in lieu of all other benefits. • The NGO engaged for the RP implementation will 9. For those becoming landless ensure linkages of the and all marginal farmers trained persons to ongoing training assistance will be programs, to facilitate provided for income generating employment and marketing vocational training and skills opportunities. upgrade options as per affected the displaced persons' choice;

10. Employment opportunity for affected the displaced persons as per his/her skills and the availability of suitable work in

44

No. Impact Entitlements Remarks Category road construction work. • Any Government land which is unauthorizedly occupied by a person and such person 11. In case of Bagar hukum lands4 has applied for regularization - 50% of compensation and of the same under the other benefits as available for Karnataka Land Revenue land owners which is Rules under 108 C(1) is equivalent to replacement called Bagar Hukum land. value for this category.. Under Rule 108C section 94A, of the Karnataka Land Revenue Act,1966, the Tahsildar is the custodian of the records and he will issue the certification whether the application is pending before the Committee or not. Tahsildar is the Secretary of the Committee for regularization of unauthorized occupation of government land. (b) Loss of 1. Compensation at current PWD • In case more than 25% of a Residential scheduled rates without house is affected and structures depreciation and 30% solatium unviable for retaining, full at replacement cost. compensation will be paid 2. Alternative houses in • Resettlement colonies will be resettlement colony or developed if more than 20 developed plot and households are displaced in construction cost of Rs. 40,000 2 km continuous stretch linked to construction progress. • Plot size will be equivalent to 3. Additional 25% of current PWD size lost subject to a SR rates without depreciation + maximum of 369 sq 30% solatium for the affected m/1200sq ft in rural area and portion as compensation for 184 sq m /600 sq ft in urban partially affected structures areas. towards reconstruction • Displaced persons have a 4. Shifting assistance of Rs. right to salvage the affected 10,000 materials. 5. Subsistence allowance of Rs. 30,000

(c) Loss of 1. Compensation at current PWD • Shopping units with 100-150 commercial scheduled rates without sq ft will be constructed if structures depreciation and 30% solatium more than 20 shops are at replacement cost. affected in a continuous 2. Alternative shop or assistance stretch of 2 km and the for income generation asset owners opt for a shop. valuated up to Rs. 75,000 • Displaced persons have a 3. Additional 25% compensation right to salvage the affected for partially affected structures materials 4. Shifting assistance of Rs. • Training for self-employment 10,000 will be provided to one adult 5. Subsistence allowance of Rs. per household as needed 30,000 • Displaced persons have a right to salvage the affected materials

45

No. Impact Entitlements Remarks Category (d) Loss of 1. Compensation at current PWD • In case more than 25% of residential scheduled rates without house is affected and cum depreciation and 30% solatium unviable for retaining, full commercial at replacement cost. compensation will be paid structures 2. Alternative shop or assistance • Resettlement colonies will be for income generation asset developed if more than 20 valuated up to Rs. 75,000 households are displaced in 3. Additional 25% compensation 2 km continuous stretch for partially affected structures • Plot size will be equivalent to 4. Shifting assistance of Rs. size lost subject to a 10,000 maximum of 369 sq 5. Subsistence allowance of Rs. m/1200sq ft in rural area and 30,000 184 sq m. /600 sq ft in urban 6. Additional amount of Rs. areas. 25,000 as grant. • Shopping units with 100-150 sq ft will be constructed if more than 20 shops are affected in a continuous stretch of 2 km and the owners opt for a shop. • Displaced persons have a right to salvage the affected materials • Training for self-employment will be provided to one adult per household as needed II. Tenants (a) Residential 1. Rental allowance for 6 months at Rs. 500 per month in rural and Rs. 1000 in urban areas 2. Shifting assistance of Rs. 10,000 (b) Commercial 1. Rental allowance for 6 months at Rs. 1,000 per month in rural and Rs. 1,500 in urban areas 2. Shifting assistance of Rs. 10,000 3. Assistance for income generation asset up to Rs. 75,000 (c) Loss of 1. Rental allowance for 6 months residential at Rs. 1,000 per month in rural cum and Rs. 1,500 in urban areas commercial 2. Shifting assistance of Rs. structures 10,000 3. Assistance for income generation asset up to Rs. 75,000 III. Non-Title holders

46

No. Impact Entitlements Remarks Category (a) Residential 1. House in resettlement colony • House plot size in Squatters or developed plot and resettlement colony to be construction cost of Rs. 40,000 minimum of 25 sq m/270 sq ft linked to construction progress. Resettlement colony will be 2. Subsistence allowance of constructed if more than 20 Rs.15,000. residential squatters are 3. Shifting Allowance of Rs.5000. getting affected in a continuous stretch of 2 km and opted for same. As per NRRP 2007. • Developed plot size will be allotted of 25 sq m/ 270 sq ft in urban area and 33 sq m /350 sq ft in rural area as per NRRP 2007.

(b) Commercial 1. Alternative shop of 100 sq ft or • Shopping units will be Squatters assistance for income constructed if more than 20 generation asset valuated up shops are affected in a to Rs. 30,000; continuous stretch of 2 km 2. Subsistence allowance of and opted for shop. Rs.15,000; 3. Shifting Allowance of Rs.5000. (c) Encroachers 1. Replacement cost of affected structure calculated at current PWD scheduled rates without depreciation 2. Compensation of crop loss or advance notice for harvesting crops IV. Loss of livelihood (a) Loss of 1. Subsistence allowance of Rs. • Training for self-employment primary 15,000. will be provided to one adult source of 2. Training assistance will be per household as needed income provided for income generating vocational training and skills upgrade options as per the displaced persons' choice; 3. Employment opportunity for the displaced persons as per his/her skills and availability of suitable work in the road construction. V. Vulnerable People (a) Widows 1. Assistance to include in • This will be restricted to Physically government pension schemes if those who have no or cannot challenged not included , if eligible as per be provided with alterative and those Government criteria (OR) livelihood sources. aged above 2. Lump-sum amount of Rs. 25,000 • Training for those above 60 60 years 3. Training assistance will be years is not mandatory and provided for income generating will be provided for if the vocational training and skills person opts for it and after upgrade options as per the the need is assessed. displaced persons' choice

VI. Community Assets (a) Community 1. Reconstruction of affected Assets assets 47

No. Impact Entitlements Remarks Category 2. Transfer to Local authorities for maintenance VII. Unidentified Impacts (a) Unidentified 1. Unforeseen impacts shall be Impacts documented and mitigated based on the principles provided in this policy Note: All amounts in this entitlement matrix are fixed as of April 01, 2010. These will increased 10% annually on first day of April every year. The same will hold good for guidance value also if not revised by the GoK.

48

8 RELOCATION OF HOUSING AND SETTLEMENTS

8.1 Basic Provision for Relocation 130. The PA will provide adequate and appropriate replacement land and structures or cash compensation for lost land and structures, adequate compensation for partially damaged structures, and relocation assistance, according to the Entitlement Matrix. The PA will compensate to the non-title holders for the loss of assets other than land, such as dwellings, and also for other improvements to the land. The entitlements to the non- titleholders will be given only if they occupied the land or structures in the project area prior to the cut-off date.

8.2 Need for Relocation 131. Efforts have been made to minimize the resettlement. There are four houses (titleholder) and 12 non-titleholder houses that are likely to be affected. Majority of the structures (149) getting affected are nontitleholder commercial structures. All efforts are made through various provisions in this RP to mitigate negative social impacts on displaced persons and communities by supporting relocation of affected households and by restoration of pre-project levels of income.

8.3 Development of Vendor markets 132. Shopping units with 100-150 sq ft will be constructed if more than 20 shops are affected in a continuous stretch of two km and opt for shop. In this package there is no requirement for vendor markets

8.4 Environmental Aspects 133. Some of the criteria to be considered are: (i) Lands notified, as water body should be avoided; (ii) Irrigated agriculture lands should be avoided; (iii) Lands notified, as forest should be avoided including forests coming under Panchayat; (iv) Resettlement sites nearer to the water bodies (including ponds and canals) are to be avoided to prevent water borne diseases;(v) Lands under plantation are to be avoided; and (vi) the resettlement sites should be at least 10 km away from ecologically sensitive areas.

8.5 Social Aspects 134. (i) Lands owned by the vulnerable communities should be avoided for resettlement sites. This includes SC/ST, women-headed households and households below poverty line, lands owned by small and marginal farmers should not be acquired for resettlement sites; (ii) DPs and host community should be consulted for mutual acceptance of the presence of each other. 135. Preference will be given to land-based resettlement strategies for displaced persons whose livelihoods are land-based. These strategies may include resettlement on public land, or on private land acquired or purchased for resettlement. Whenever replacement land is offered, displaced persons are provided with land for which a combination of productive potential, locational advantages, and other factors is at least equivalent to the advantages of the land taken. If land is not the preferred option of the displaced persons, or sufficient land 49 is not available at a reasonable price, non land-based options built around opportunities for employment or self-employment should be provided in addition to cash compensation for land and other assets lost.

8.6 Reconstruction of affected community structures The project authorities will replace and reconstruct all community assets before demolition. For shifting of community assets, the NGO will: (i) consult with the community along with the SDO and identify alternative land- the land identified has to be government land wherever possible, or given as donation in some cases; (ii) owner consent letter has to be signed by the donor /owner in the prescribed format prepared by the NGO (name, place, survey nos., site measurement); (iii) the reconstruction will be carried out by the local contractors; (iv) the KSHIP Assistant Executive Engineer of the division will be responsible for monitoring the work; and (v) the cost for the relocation and reconstruction will be paid by the project.

50

9 INCOME RESTORATION AND REHABILITATION

9.1 Income restoration measures 136. The basic objective of income restoration activities is that no project-affected person shall be worse off than before the project. Restoration of pre-project levels of income is an important part of rehabilitating individuals, households, and socioeconomic and cultural systems in affected communities. Income restoration schemes will be designed in consultation with affected persons so as to benefit them. Based on the information collected on IR activities from the census socioeconomic surveys, the implementing NGO will identify suitable IR programme for the affected persons.

9.2 Impact Categories and IR Schemes 137. Project-induced displacement may lead to loss or diminished income for Displaced Person (DPs). The main categories of impacts expected as a result of project land and property acquisition include: (a) Loss of agriculture land in part or full; (b) Loss of commercial establishments (c) Loss of livelihood as employees and (d) tenants losing their livelihood. Table 9-1: Categories for Income restoration Loss No. DPs/ DHs 1 Partial loss of agriculture 148 2 Loss of commercial structures 202 3 Loss of livelihood as employees 1 4 Tenants losing livelihood 46 138. The economic rehabilitation assistance money will be deposited in bank accounts to be released only for the purchase of income generating assets. Women-headed households will be assisted in identifying alternative space in adjacent areas for continuing their trade or vocations. These households will have to be given preference in disbursement of assistance. The SDRC will use its good offices with local authorities to facilitate early rehabilitation of these women-headed households. DPs losing their livelihood as employees will be provided only relief assistance.

9.3 IR Activities 139. There are two types of IR activities, i.e. short-term and long-term. Short-term IR activities mean restoring DPs’ income during periods immediately before and after relocation. For this, the support NGO shall ensure that: compensation and R & R assistance as provided in the entitlement matrix is provided. Other works include work in the project construction activities and other allied activities such as work on resettlement sites etc. Long term IR activities include provision of shops for those losing their total livelihood, to re- establish their commercial activities. Shopping units with 100-150 sq ft will be constructed if more than 20 shops are affected in a continuous stretch of two km and opt for shop. It also includes purchase of income generating assets up to Rs. 75,000. In case the amount used is less than this, the beneficiary will get the remaining amount after one year of successful completion of the activity, which will be monitored by the NGO. 140. The steps to be followed for income restoration include: 51

Step 1: Identification of Target Groups – NGOs need to identify the affected persons; Step 2: Identification of IR Activities - Prepare a list of possible and feasible income restoration options. While identifying IR options, the following factors shall also be considered: (i) Education level of DPs; (ii) Skill possession;(iii)Likely economic activities in the post displacement period; (iv) Extent of land left; (v) Suitability of economic activity to supplement the income; and (vi) Market potential and marketing facilities. Based on socioeconomic characteristics and options preferred by DPs, the NGO may have to re- assign trades to DPs. Options include (i) petty trade, and (ii) skill-related schemes and loans for pumps, bore wells, bullock carts etc to increase productivity. The NGO will assist DPs in identifying appropriate alternative economic rehabilitation schemes through counselling and consultation. Step 3: Training: Option for training for skill enhancement for those losing their livelihood has been provided in the Entitlement Matrix for owners losing commercial structure and employees losing their livelihood. Step 4: Identification of Trainers / Training Institutes: Based on trades selected, NGO shall have to identify master trainer and/or training institute for different trades / activities who can provide on the job training. Step 5: Training Arrangement: NGO shall make different groups of DPs as per trades selected and make all the arrangements such as fixing the venue etc. Step 6: Monitoring of DPs: After training the NGO shall monitor the DPs in order to take mid-term correction measures, if required.

52

10 RESETTLEMENT BUDGET AND FINANCING

10.1 Budget and Costs 141. The costs used for the budget estimates are based on information collected during the census socioeconomic surveys of DPs. The estimated total budget for the implementation of RP is Rs. 61.76 million. This does not include Operating Costs, NGO and Monitoring Consultant Costs as these costs are for the overall project, which is estimated at Rs. 20 million. The unit costs and detailed budget are given below: Table 10-1: Budget Sl. Cost per Category Total Unit Total cost No. Unit LAND ACQUISITION 1 Agriculture land 5.21 1,000,000 5,210,000 Sub Total 5,210,000 ALTERNATIVE SITE COST 2 Residential site (owner) 4 30,000 120,000 3 Commercial site (owner) 3 50,000 150,000 4 Commercial site (squatter) 198 30,000 5,940,000 5 Residential site (squatter) 12 50,000 600,000 Sub Total 6,810,000 STRUCTURE COST 6 RCC - Pucca housing (Sq ft) 4,406.03 800 3,524,824 7 Dry stone masonary (Sq ft) 6,799.08 600 4,079,448 8 Mud mortar (Sq ft) 20,432.22 350 7,151,277 Sub total 14,755,549 R & R ASSISTANCE 9 EWS House construction(Non Titleholder) 12 40,000 480,000 10 House construction (owners) 4 40,000 160,000

11 Shifting Allowance(Non-titleholders) 210 10,000 2,100,000

12 Subsistence Allowance (Non-titleholders) 210 15,000 3,150,000

13 Subsistence Allowance (Owners) 8 30,000 240,000 14 Additional assistance for land losers 148 20,000 2,960,000 15 Shifting Allowance(Titleholders) 8 10,000 80,000

17 Economic generating asset(owner/tenant) 50 75,000 3,750,000 18 Economic generating asset (squatter) 198 30,000 5,940,000 19 Rental Value Commercial 46 9,000 414,000 20 Rental Value Residential 1 6,000 6,000 21 Relief Assistance 1 15,000 15,000 22 Training for DP 245 15,000 3,675,000 23 Vulnerable groups 210 25,000 5,250,000 53

Sl. Cost per Category Total Unit Total cost No. Unit 24 Cattle shed 3 15,000 45,000 25 Group Entitlement 74.10 15,000 1,111,500 Sub Total 29,376,500 Total 56,152,049 10% Contingency 5,615,205 OVERALL TOTAL 61,767,254 Table 10-2: Unit Costs for R & R Sl. Category Estimates (in Rs) No. 1 Agricultural Land per ha Rs.2,470,000 2 Non Agricultural Land per ha Rs.3,705,000 3 Pucca house 800 per sq ft 4 Semi pucca house 600 per sq ft 5 Kutcha house 350 per sq ft 6 Construction cost for house in Resettlement site 40,000 per structure 7 EWS Housing 40,000 per unit Training for DP for income generation schemes and 15,000 (Rs.5000 per month for 3 8 vocational training months) 9 NGO assistance for implementation 85,00,000 10 Evaluation Consultants 30,00,000 11 SDRC and associated staff training 15,00,000 lump sum 12 Group entitlements 15,000 per km Office equipment (including Rs. 5,00,000 each for 20,00,000 lump sum 13 setting up office of LAO in North and South Karnataka 14 Vehicle cost ( Rs.8,00,000 per vehicle) 8 vehicles 56,00,000 142. In accordance with the policy provisions, all grants and benefits shall be indexed annually at 10 % on the first of April. These include subsistence allowance, shifting allowance, relief assistance, amounts for income generating asset, cost for the provision of sites to squatters and rental allowance. Table 10-3: R & R Unit Costs Sl. Category Proposed Amount No. 1 Purchase Commercial site for Rs.30,000 (10’x10’) Urban Rs 15000 Rural area squatters 2 Purchase Commercial site for Rs.50,000 (10’x15’) Urban Rs 25000 Rural area Titleholders 3 Purchase Residential site for Rs. 30,000 Urban Rs 20000 Rural area squatter 4 Purchase Residential site for Rs. 70,000 Urban Rs 30000 Rural area Titleholders 5 Shifting allowance for Titleholders Rs.10,000 as one time payment 6 Subsistence allowance for Rs. 30,000 Titleholders 7 Subsistence allowance for squatters Rs.15,000 as one time payment 8 Shifting assistance for squatters Rs.5,000 as one time payment 9 construction cost for Residential Rs.40,000 squatters 10 IGA assistance to commercial Rs.30,000 for income generating asset squatter 11 Shifting allowance for Bagar Hukum Rs.5,000 as onetime Payment

54

Sl. Category Proposed Amount No. House holders 12 Subsistence allowance for those Rs.15,000 as onetime payment who are losing Bagar Hukum Lands 13 Additional assistance for those Rs.20,000 as onetime payment. losing land 14 Income generating Grant for Title Rs.75,000 as onetime payment holder who loose entire land /Business 15 Rental allowance for commercial Rs. 1,500 for urban and Rs. 1,000 for rural per Tenant month for 6 months. 16 Rental allowance for residential Rs.1,000 for urban and Rs. 500 for rural per Tenant month for 6 months 17 Relief assistance for loss of Rs.15,000 lump sum payment employment of agriculture and Non agriculture. 18 Assistance to Vulnerable groups Rs. 25,000 lump sum payment In the R & R budget, allocation has not been made for replacement of affected community structures. Any community assets that are getting impacted and which need to be replaced or relocated, is being undertaken separately by PIU KSHIP field division offices. 55

11 GRIEVANCE REDRESSAL MECHANISM

11.1 Grievance Redressal Committee 143. The project will establish a Grievance Redressal process, with district-level committees. Each District Grievance Redressal Committee will have representation from the local affected population and the NGOs involved in RP implementation. These committees will hear complaints and facilitate solutions; and the process, as a whole, will promote dispute settlement through mediation to reduce unnecessary litigation. 144. The following persons will constitute the District Level Grievance Redressal Cell : • Deputy Commissioner Chairman • Academician (To be selected by DC) Member • Representative of DP (To be selected by DC) Member • Executive Engineer of Concerned Division Convener 145. The main functions of the GRC will be: a. to provide support to DPs on problems arising out of eligibility for RP-provided entitlements and assistance provided; b. to record the grievances of the DPs, and categorize, prioritize and solve them within one month; c. to inform PIU of serious cases within one week; and d. to report to the aggrieved parties about the developments regarding their grievance and decisions of the PIU, within one month. 146. The Grievance Committees will meet regularly during implementation of the RP, at least once a month. The committees will suggest corrective measures at the field level itself and fix responsibilities for implementation of its decisions. However the NGOs will form the first level of intervention in resolving DP related grievances and attempt to motivate the DP to facilitate implementation of the R & R program. The option of contacting the project authorities is available to DPs at any time. The Deputy Commissioner will be the Appellate Authority. The steps in the GRC are: a. At the first level intervention the NGO will attempt to resolve the grievance; b. Next the CAO will attempt to address land related grievance and the ADSW will address the non-land related grievances; c. The third step will be to approach the Grievance Redressal Committee; d. Next they can Approach the Regional Commissioner who is the Appellate Authority; e. If all the above fails, the DPs can approach the court. 147. It is the responsibility of the SDRC/NGO to inform the affected persons of the GRC, to make it effective. The NGO shall make DPs aware of the grievance mechanism set out in the RP and shall assist PDPs who have grievances to pursue a suitable remedy. The NGO shall help the DPs to file a grievance application. 148. The NGO shall record the grievance and bring the same to the notice of the Grievance Redressal Committees (GRC) within seven days of receipt of the grievance from the DPs. It shall submit a draft resolution with respect to the particular grievance of the DP,

56 suggesting solutions, if possible, and deliberate on the same in the GRC meeting through the NGO representative in the GRC. 149. The NGO shall assist in the GRC process whenever necessary. Figure 11-1: Grievance Redressal

57

12 INSTITUTIONAL MECHANISMS

12.1 Institutional Arrangements 150. KSHIP has a dedicated unit called the Social Development and Resettlement Cell (SDRC) within the Project Implementation Unit for the implementation of the RP. All aspects of resettlement and rehabilitation and the delivery of entitlements are managed by Social Development/Resettlement Cell (SDRC).

12.2 Social development and Resettlement Cell (SDRC 151. The SDRC facilitates land acquisition and compensation, relocation and resettlement, distribution of assistance for the DPs. The SDRC is responsible for monitoring the implementation of all resettlement and rehabilitation activities, including land acquisition. The responsibilities of SDRC include: i. responsible for all land acquisition activities; ii. liaison with State and District levels Departments to facilitate DP access and take advantage of services and programs already in place; iii. evolve mechanisms for coordinating the delivery of the compensation and assistance to entitled persons; iv. review and provide social development perspectives and inputs to on-going project design and implementation by working closely with project planners, contractors, and construction supervision consultants; v. link the project with state government agencies, provide liaison with PWD field units and impacted communities, coordinate with district-level committees regarding social development and resettlement operations in the field, mobilize assisting NGO partners, and support the organisation of local community representing DPs; and vi. engage required training services, oversee a grievance redressal process, actively monitor RP implementation, and cooperate with planned project evaluations.

12.3 SDRC and Staff Deployment 152. The RP will be implemented by the North Karnataka (Hospet) division of PIU; Staffing is complete for the proposed institutional set up.The institutional setup is given in Figure 12.1 The key SDRC officials are: • Special DC Land Acquisition - Special Deputy Commissioner in the cadre of KAS will be the in charge of the overall land acquisition. He will be assisted by two Assistant Commissioners for Land Acquisition who is responsible for all activities related to land acquisition. One Assistant Commissioner will be stationed in the zonal office of North Karnataka(Hospet) and the other one would be stationed at PIU Office (South Zonal Office) in Bangalore. • Chief Administrative Officer –The CAO in the cadre of KAS will be responsible for all resettlement and rehabilitation activities. The CAO will also be assisted by The Assistant Director Social Welfare (ADSW) who will be responsible for R & R work. On

58

the land acquisition side CAO and the Assistant Commissioners will be responsible for fixing the negotiated price of the land along with the affected persons according to the Karnataka Highways Act, 1964, and disbursing the compensation. • The Assistant Director Social Welfare is responsible for shifting of project affected persons, coordination of disbursement of assistance such as shifting allowance etc., disbursement of funds for income generating programmes, relief assistance, etc. The ADSW needs to have relevant experience of at least five years in resettlement projects, with a minimum educational qualification of Masters in Social Science. • The Resettlement and Rehabilitation Manager will assist the ADSW and coordinate all the rehabilitation work of the SDO’s. The R & R Manager has to have experience in resettlement projects with minimum experience of three years, with a minimum educational qualification of Masters Degree in Social Sciences. • The ADSW and the Resettlement and Rehabilitation Manager will be assisted by the Social Development Officer (SDO). It is suggested that four SDOs be stationed in the Assistant Commissioners Office to be located on North zone and PIU –South in Bangalore (already appointed). The responsibility of SDO includes: support to resettlement and rehabilitation related work pertaining to RP implementation, like issue and the verification of ID cards, identification of local income generation potential, monitoring rehabilitation works, providing assistance to vulnerable groups, co-ordinating with NGOs etc. The SDO has to have a Masters degree in Social Sciences. • The SDOs will be assisted by the Social Welfare Inspectors (SWI). The SWI’s are supporting staff to SDOs to carry out the functions as per the directions of SDOs. • The SDRC will have a Data Management Specialist. The responsibility of this person will be to monitor and update the data of all the project affected persons; to highlight any discrepancy in compensation and paid disbursed; and coordinate the inputs of information from the North and South Divisions to the Central database at PIU at Bangalore. The Data Management Specialist is to be supported by additional staff. The PIU has already appointed the Consultants for database management. Information is ready to be transferred to the PIU for use in implementation. 59

Figure 12.1: Institutional Set up

CHIEF PROJECT OFFICER

PROJECT CAO (SPECIAL SPECIAL DIRECTOR DC) AT PIU HQsc DC(LA)

AC-LAO-GRP I NORTH KARNATAKA ASSISTANT DIRECTOR (Office at Dharwad - AC-LAO-GRP I SOUTH (SOCIAL WELFARE) tentatively KARNATAKA AT HQ s

DEPUTY TAHSILDAR R &R MANAGER DEPUTY

SOCIAL SDO - SOUTH FIRST DIV REVENUE COMPUTER SDO - NORTH KARNATAKA SURVEYOR (4) FIRST DIV REVENUE COMPUTER DEVELOPMENT ASSISTANT INSPECTOR (4) OPERATOR/STENO 1 SURVEYOR (4) (2) KARNATAKA (2) ASSISTANT (2) INSPECTOR (4) OPERATOR/STENO 2 OFFICER (1) PIU

GROUP D (4) GROUP D (4)

SOCIAL WELFARE INSPECTOR (1) SOCIAL WELFARE INSPECTOR (6)SOCIAL WELFARE VEHICLE 1 INSPECTOR (6) VEHICLE 1 DRIVER 1

COMPUTER OPERATOR 1; STENO 1

VEHICLE 4, DRIVER 4 MONITORING DBMS NGO NORTH NGO SOUTH CONSULTANTS SPECIALIST GROUP D (2)

60

12.4 Protection of RoW 153. Section 5 of the KHA mentions the Highway Authority will exercise power and discharge duties in accordance with provisions of the KHA for restriction of ribbon development along the highways and for prevention and removal of encroachments. The Highway Authority under Section 7 has power to fix boundary of building and control lines of highways. Section 21 mentions prevention of unauthorized occupation of highway. Thus the onus of protecting the COI/RoW lies with the Project Authority. Once the COI/Row has been identified and frozen, the COI/RoW has to be clearly marked with boundary stones. Any new encroachment into the area will be monitored the Division PWD, this has to be done through bi-monthly site inspection by the Divisional Engineer in charge. Those Non-titleholders already identified by the project will be provided by Identity Cards issued by the PIU. The bi- monthly site inspection will help to prevent further encroachments.

12.5 Valuation of other structures/assets 154. The valuation of structures and other assets, which have not been covered by the LAPs will be carried out by Government approved valuators appointed by the PIU. Valuation will be done on the basis of current PWD Schedule of Rates, without depreciation at replacement cost. Based on the valuation another 30 % will be given.. However, this will be approved and verified by the concerned Executive Engineer. It will be forwarded to the PD for approval. Trees will be valued by the Horticulture/Forest department.

12.6 Roles and responsibilities of officials for RP implementation 155. The Administrative roles and responsibilities and financial powers - existing and to be delegated of the SDRC officials are given below. Delegations of financial powers have to done through a Government Order. Table 12-1: Administrative and Financial Responsibilities of officials and Agencies for RP Implementation Personnel/ Administrative Roles and Financial Powers Agency Responsibilities PIU Chief Project • In charge of the overall project • Will be authorized to make Officer activities. any additional changes • To decide on all policy matters without having to refer to regarding LA and R & R. the Steering committee, • Participate as a member secretary provided the amount is in the State level Committees to within the budget facilitate land acquisition, pre- construction activities, and implementation of R & R activities. • Authorized to take decision in financial matters within the provided budget. 61

Personnel/ Administrative Roles and Financial Powers Agency Responsibilities Project • Overall in charge of day to day • To approve awards above Director activities of LA and R & R. Rs.50 Lakhs to Rs. One • Participate in State and District Crore. level meetings to facilitate LA and • To approve of Rand R R & R activities. assistance above One • Responsible for contracting NGOs lakh. and Monitoring consultants. • Periodic appraisal of progress and reporting to the Asian Development Bank and the Government on monthly basis. SDRC Chief • Responsible for all R & R activities • To approve payments for R Administrative • Coordinate the implementation of & R assistance up to Rs. Officer R & R activities with PIU, field staff, One lakh per individual. engineering and revenue officials. • Approve of micro plans prepared by the NGOs for implementing RP. • Monitor the progress of R & R activities and LA carried out by the NGO and Monitoring Consultants. • Hold periodic meetings on R & R implementation and report to the PD and CPO. • Provide advisory support to PIU for monitoring of RP implementation. Assistant • Assist CAO in the implementation • No financial powers Director of R & R activities. Social Welfare • Coordinate training for PIU and NGOs for capacity building to implement R & R. • Facilitate development of resettlement sites and agriculture land. • Participate in the allotment of residential and commercial plots to the DPs. • Liaison with district administration and line departments for dovetailing government schemes for income generating activities to DPs. • Participate in the meetings of Grievance Redressal Committee. Manager • Coordinate implementation of R & • No financial powers R & R R activities with PIU and field staff. • Facilitate the appointment of external agency for monitoring activities to be taken up by the implementing NGO. • Assist CAO to perform R & R activities.

• Review the work in finalization of

resettlement site development.

• Prepare monthly progress report for the SDRC and Land

62

Personnel/ Administrative Roles and Financial Powers Agency Responsibilities Acquisition. • Monitor the R & R report and submit to CAO and PD. LAND Special DC • Coordinate Land acquisition • To approve awards up to ACQUISITION Land process with Tahsildar at field. Rs.50 Lakhs, Acquisition • Prepare guidelines and procedures to be adopted for land acquisition. • Interact with District officials and other stakeholders to speed up the land acquisition process. • Monitor land acquisition and report progress to CPO and PD. Assistant • Assist CAO and Sp. DC LA to • No financial powers Commissioner perform R & R and Land -LAO Acquisition activities. • Make budgetary provisions Tahsildar • Overall responsible for land • No financial powers acquisition as land acquisition officer. • Coordinate the preparation of Land Plan Schedules with Consultants and monitor the same. • Facilitate the preparation and submission of Section 15 notification under KHA for land acquisition. • Prepare progress report on physical and financial monitoring of LA and submit to DC LA. FIELD UNIT Executive • Participate in District level • No financial powers Engineer meetings. • Oversee the process of implementation of RP in the field. • Ensure the preconstruction work is done before handing over site to contractor. • Oversee the process of land acquisition, shifting of CPRs and other assets in the field. • Scrutinize and certify the structures valuation report submitted by the valuators. • Coordinate selection of resettlement site. • Conduct periodic review with staff • Submit monthly progress reports to PD on R & R activities. 63

Personnel/ Administrative Roles and Financial Powers Agency Responsibilities Assistant • Responsible for pre construction • No financial powers Executive work in his jurisdiction. Engineer • Finalization and demarcation of COI. • Coordinate with NGO/Monitoring consultants and SDO to carry out R & R activities.

• Coordinate with valuers for preparations of estimates. • Support SDO/NGO for selection of resettlement site. Social • Overall responsible for R & R • No financial powers Development activities in the field Officer • Liaison with District administration and line departments for dovetailing government schemes. • Make budget provision for R & R activities • Participate in allotment of sites to DPs. • Coordinate with NGO/Monitoring consultants for implementation of R & R. • Facilitate opening of Joint Accounts for DPs for transfer of R & R assistance through cheque. • Coordinate to disseminate the R & R policy in local language. • Facilitate public consultation on R & R Policy with NGO/ Revenue/ PWD officials. • Organize meetings with NGOs to review progress at district level and submit to R & R Manager and CAO at PIU. Social Welfare • Responsible for maintaining the R • No financial powers Inspectors & R work at division wise. • Assist NGO for selection of resettlement site. • Assist Monitoring Consultants /NGO to conduct training for DP on IGA • Coordinate with SDO/EE at field level for disbursement of R & R assistance. • Ensure all eligible DPs are awarded compensation. • Attend monthly meeting at district level and submit monthly progress report to R & R Manager and ADSW. DATABASE Data • Responsible for maintaining the • No financial powers Management database of the DPs. Specialist • Responsible for maintaining the database of overall physical and

64

Personnel/ Administrative Roles and Financial Powers Agency Responsibilities financial progress. • Coordination of the database for SDRC. • The implementation of R & R activities by NGOs to be maintained. • Provide necessary formats for collection of field information. • Coordinate with SDRC to prepare and maintain the progress report. • Maintain the records of grievance redressal committee. • Coordinate the inputs of data from North and South Divisions. • Identify discrepancies in disbursement. EXTERNAL NGO (2) • Responsible for providing PIU • No financial powers AGENCIES support for implementation of RP. • Verification of DPs. • Distribution of ID cards. • Preparation of micro plans. • Dissemination of information. • Assist to DPs to avail R & R assistance and compensation. • Identify site for relocation for CPRs. • Identify resettlement /vendor market sites. • Identify training needs and provide the same. • Facilitate in opening joint accounts. • Enable DPs to identify alternate sites for house/shop • Assist DPs to relocate. • Provide monthly progress reports on implementation Monitoring • Conduct monitoring of RP • No financial powers Consultants implementation activities. • Conduct internal, external and concurrent monitoring. • Provide early alert to PIU to redress any potential problems. • Monitor target achievements and slippages. • Certification of readiness from LA and R & R view at the time of issuing bid documents and award of contract. Grievance • Support DPs in resolving issues • No financial powers Redressal related to R & R and LA. Committee. • Record grievance and resolve them within stipulated time. • Inform PIU about any serious cases. 65

Personnel/ Administrative Roles and Financial Powers Agency Responsibilities • Report to the aggrieved parties about the decisions of the PIU. Negotiation • Negotiate the consent price of land • No financial powers Committee.

12.7 Competent Authority for various Approval 156. The table below identifies the competent Authority for various approvals during implementation.

Table 12-2: Competent Authority for Approvals Approvals Required Competent Authority Approval for LA awards Special DC LA and PD, PIU; Notification by Government Approval for Roles and Responsibilities for SDRC Steering Committee officials and staff R & R Policy/ Entitlements and amendments to Government Policy RP and Budget Steering Committee Changes in R & R Policy/RP implementation and Government entitlements Consultants/NGOs output CAO Fixing compensation rate Price Negotiation Committee – District level Approval for issue of ID cards CAO PIU jointly by Engineers/ Revenue /NGO. Approval of disbursement of Assistance CAO; PD Approval for structure valuation with land Preparation By Divisional EE/ valuators and approval by PD and Special DC LA Approval for structure valuation without land Preparation By Divisional EE/ valuators and approval PD Approval for shifting and relocation of community Estimate preparation by Divisional EE and assets approval by PD Approval for requirement of Resettlement site , CAO, PD vendor market for AFs Approval for any grievance related to R & R Grievance Redressal Committee

12.8 Implementation support by NGOs 157. The work of the NGO will include consultations and counseling of DPs, encouraging DPs for productive utilization of compensation and rehabilitation grants, facilitating DP access to income generating assets, increasing the social acceptability, ensuring effectiveness of training programs organized for DPs electing participation in self- employment schemes etc., The SDRC has to ensure that the NGO has sufficient experience in implementation of resettlement project, especially in Karnataka and it has to have adequate manpower. Two NGOs will be hired. One for North Karnataka and one for South Karnataka. 158. The NGO will work as a link between the PIU - SDR Cell and the affected community. They will educate the DPs on the need to implement the Project, on aspects relating to LA and R & R measures and ensures proper utilization of various compensations

66 extended to the DPs under the R & R entitlement package. The tasks of the NGO will be to facilitate the resettlement process. Its broad objectives will be: a. Identification, verification and updating of DP Census, Includes verification of properties of DPs and estimation of their type and level of losses for the preparation micro plans and ID Cards. b. Develop micro plans in consultation with the DPs and PIU staff. . c. Educate DPs on their rights, entitlements, and obligations under the RP; Assist the DPs to identify suitable alternate land for resettlement purposes; d. Preparation and Distribution of Entitlement cum Identity Card. All eligible project displaced households will be issued Identity Cards, giving details of the type of losses and type of entitlements. e. Ensure that DPs receive their full entitlements; Where options are available, the NGO will provide advice to DPs on benefits of each option; Assist the DPs in getting benefits from various government development programs; f. Rehabilitation of Affected Households and restoration of Income and Livelihood. The NGO will help the communities derive maximum benefits out of the project without loosing their livelihoods and the least impact on socio-cultural aspects of their lives. g. Assist DPs on grievance redressal through the established system; and h. Will relocate DPs. Assist PIU in making arrangements for the smooth relocation of the DPs; No Physical relocation from agriculture land, residential units, commercial establishments or other immovable properties will begin before alternate arrangements are made. i. Any other responsibility that may be assigned by the PIU for the welfare of the affected communities. 159. In order to carry out the above tasks, NGO staff will be stationed in the site offices. Besides contacting the DPs on an individual basis to regularly update the baseline information, group meetings and village-level meetings will be conducted by the support agency on a regular basis. The frequencies of such meetings will depend on the requirements of the DPs but should occur at least once a month. The support agency will have to encourage participation of individual DPs in such meeting by discussing their problems regarding LA, R & R and other aspects relating to their socioeconomic lives. Such participation will make it easier to find a solution acceptable to all involved

12.9 Database Management 160. A census Database has been created by the consultants. This database will be transferred to the SDRC, for upgrading and further use. The main purpose of the database and use will be to (i) track progress of R & R implementation (ii) for determining the entitlements to be paid; (iii) track pending entitlements and amounts; (iv)organizing outputs for periodical reports and other project requirements; and (v) establishing input formats . The Database consultants will be responsible for (i) modifying the input/ output formats to the project requirements; (ii) Training of SDRC staffs and other field level staffs ;(iii) aid the NGO in finalizing the entitlements of each DPs and DHs ; (iv) provide for decision making at the PIU;(v) Monitor and regulate the land acquisition, distribution of compensation and assistance, grievance redressal and financial progress. In which the SDRC will hire 67 database management consultants for the management, monitoring and updating of the data. The database consultants will need to depute data entry operators in the offices of the Assistant Commissioner. The data in the HQ will be updated based on the information sent by the division office. The database will be developed to suit the requirements of implementation and monitoring payments. The database Information will be made web- enabled (based on consultation with SDRC).

68

13 IMPLEMENTATION SCHEDULE

13.1 Coordination with civil works and certification 161. The resettlement program will be co-coordinated with the timing of civil works. The required coordination has contractual implications, and will be considered in procurement and bidding schedules, award of contracts, and release of cleared COI sections to project contractors. The project will provide adequate notification, counseling and assistance to affected people so that they are able to move or give up their assets without undue hardship before commencement of civil works and after receiving the compensation. The implementation schedule provides the key benchmarks of implementing the RP. All other activities related to implementation and land acquisition will be undertaken simultaneously. 162. Actions to be completed before prior to bid and award of contract include: (i) Resettlement Plan should have been approved by the GoK and Bank for respective roads; (ii) the RP should have been disclosed in the web site and other public places accessible to the local people; (iii) the first notification for private land acquisition should have been issued; (iv) the issue of identity cards to eligible project affected households should have been completed. The actions to be completed prior to handing over of the first milestone stretches to the contractor includes: (i) The private land acquisition should have been completed and compensation offered to the land owners for Section 1; (ii) The Government land should have been transferred or no objection should have been obtained from the land owning agency for Section I; (iii) The community assets should have been replaced in Section 1; and (iv) the remaining land acquisition, R & R assistance and relocation of community assets for second milestone should be completed within 6 months of award of contract and prior to handing of the site to the contractor. 163. It is the responsibility of the PIU to ensure that the RP is successfully implemented in a timely manner. The implementation schedule needs to be updated periodically and monitored judiciously. The completion of R & R activities will be certified by the MandE consultants. Resettlement and Rehabilitation is complete only when the following criteria are met: a. All legal compensation both for land and structure must be paid; b. 100 % must have received compensation; c. All eligible DPs must have alternative house and economic rehabilitation must be complete; d. At least 80 % of all eligible DPs must have started their new economic activity; e. All project affected common property resources must be replaced and re- established. f. Implementation of the remedial measures arising out of impact evaluations must be complete.

13.2 Implementation Schedule and Timing of Resettlement 164. During project implementation, the resettlement program will be co-coordinated with the timing of civil works. The required coordination has contractual implications, and will be considered in procurement and bidding schedules, award of contracts, and release of 69 cleared COI sections to project contractors. The project will provide adequate notification, counseling and assistance to affected people so that they are able to move or give up their assets without undue hardship before commencement of civil works and after receiving the compensation. This provides the key benchmarks of implementing the RP. All other activities related to implementation and land acquisition will be undertaken simultaneously. After signing of contract the contractor will start his works in Section I, followed by Section II. 165. The proposed consideration of time to be taken for Land Acquisition under the KHA, after the issue of Section 15 notification is 6 months. 166. The time taken for the implementation for the RP will be two years. Resettlement planning and updating of studies will be a continuous process throughout the project. The PIU will coordinate these efforts to assure that RP implementation and phasing is appropriately sequenced with designs and civil works. 167. The resettlement process must be completed before the start of civil works. PIU has clear the COI and resettle DPs located within the COI, before the civil work starts on any section of the project road. DPs will be given at least three months notice to vacate their property before civil works starts. The civil works schedule needs to be dovetailed into the land acquisition and resettlement implementation schedule. The LA and R andR Implementation schedule is given below: Table 13-1: R & R Implementation Schedule

Activity Progress (Year/Quarter) 2009 2010 2011 Q4 Q1 | Q2 | Q3 | Q4 Q1 | Q2 | Q3 | Q4 Project Preparation Stage Screen project impact ------Public Consultation on alignment ------Prepare Land Acquisition Plan ------Carry out Census Survey ------Prepare Resettlement Plan (RP) ------RP Implementation Stage Hiring of NGOs for RP Implementation ------Obtaining approval of RP from ADB ------Disclosure of RP ------Public consultation ------Preparation LAP ------Declaration of cut-off date (KHA Notification) ------Payment of compensation ------Taking possession of acquired land ------Handing over the acquired land to contractor ------Rehabilitation of DPs ------Monitoring and Reporting Period Internal monitoring and reporting ------External monitoring and reporting ------

70

13.3 Capacity Building and Training 168. The capacity building and training of the PIU/SDRC is important for successful and timely implementation of RP. To enhance capabilities, the SDRC staff will be given in house training periodically (once in six months at least). All SDRC officers and staff have to attend training programmes. Training will cover techniques in conducting participatory rural appraisal for micro-planning, conducting census socioeconomic surveys, dissemination of information, community consultation and progress monitoring and evaluation. In house training will be carried out by professional identified by the PIU. Local institutes such as the Indian Institute of Management, Institute for Social and Economic Change and private consultants can be identified for training. Table 13-2: In house Training programme Staff Training Module PIU CAO ; DC LA; ADSW ; R & R Policy, National State, Asian Development Banks; R & R Manager; SDO ; Socio Economic and Census Survey ; Checklist for R & SWI R; Implementation Schedule ; Training Needs Assessment ;Monitoring indicators; Dissemination of information ; Preparation of RP, LAP, Disbursement method, disclosure of documents; Best practices of other R & R projects FIELD EE ; AEE ; Revenue Measurement of structures; Valuation procedures; Resettlement site selection; Minimizing resettlement; preparation of LAPs, Disbursement method.; Shifting of CPRs EXTERNAL NGOs ; Monitoring Government schemes; Disbursement methods; public Consultants consultation; income generating activities.

71

14 MONITORING AND REPORTING

14.1 Monitoring 169. Monitoring involves periodic checking to ascertain whether activities are going according to the plan. It provides the feedback necessary for project management to keep the programmes on schedule. Monitoring provides both working system for project managers and a channel for the resettles to make known their needs and their reactions to resettlement execution. Monitoring exercise will be undertaken both internally and externally. 170. While SDRC/PIU on monthly basis will carry out the project’s internal monitoring and external agency will be appointed for third party monitoring. Indicators, which will be monitored during the project, may be divided into two categories. • Process and output indicators or internal monitoring • Outcome/impact indicators or external monitoring 171. Monitoring is essentially an exercise in strategic learning that can and should be used for enhancing the quality of RP implementation. There are two types of monitoring being undertaken namely (a) Internal, which is normally carried out by the project authority itself and (b) external or independent monitoring by an external agency.

14.2 Internal monitoring 172. The internal monitoring is a conventional monitoring of government related to physical factors such as, number of households affected, resettled, assistance extended infrastructure facilities provided, etc. and other financial aspects, such as compensation paid, grant extended, etc. the internal monitoring must be simultaneous with the implementation of the Rehabilitation Plan (RP). 173. The objectives of the internal monitoring are: (i) Daily Operations Planning; (ii) Management and Implementation and (iii) Operational Trouble shooting and Feedback. The periodicity of internal monitoring could be daily or weekly depending on the issues and level.

14.3 External monitoring 174. An external monitoring agency will be appointed to monitor R & R programmes on semi-annual basis. It should also bring the difficulties faced by the DPs to the notice of PIU so as to help in formulating corrective measures. As a feedback to the PIU and other concerned, the external agency should submit semi-annual report on progress made relating to different aspect of R & R. The reports will be disclosed on ADB website. The agency will also certify the completion of LA and R & R activities for issuing bid documents and award from LA and R & R point of view. 175. The objectives of the external monitoring are: • To track resettled and host population over time in order to document the restoration of incomes and standard of living. • Determine remedial action if required. • If income and standard of living of the DPs has at least been restored and has not declined.

72

• In case of host population, whether income and standard of living of host population have not declined due to influence of resettlers. • Whether resettlers and host population has re-integrated with each other. Table 14-1: Monitoring Indicators for Physical Progress % against Implement Revised Monitoring Progress Cumulati Revised Sl. ation Impleme Indicators for This ve Implement No. Target ntation Physical Progress Month Progress ation (Nos) Target Target Land Acquired- 1 5.21 private Land transferred – 2 0.00 Government Compensation for loss of Commercial 3 4 structure to title holder. Shifting assistance 4 to Title holder for 4 commercial Subsistence allowance for 5 commercial 4 structures for titleholder. Alternative shop/or 6 IGA for commercial 4 structure (owner) Commercial tenants 8 to be paid rental 46 allowance Shifting assistance 9 46 for tenants Income generating 10 Assets for 46 Commercial tenants. Commercial 11 Structure for 198 squatters Shifting allowance 12 for commercial 198 squatters Commercial squatter 13 198 for shop or IGA Subsistence allowance for 14 198 commercial squatters 15 Vulnerable groups 210 16 Cattle Shed 3

73

Table 14-2: Financial Indicators for Progress Total Monitoring Indicators for Implementa Progress Sl. No. Unit Cost Cost Physical Progress tion Target This Month (in Rs.) Rs. 1 Land Acquired- private 5.21 2470000.00 per ha. Land transferred – 2 0.00 Government Allowance for those losing 3 148 20000.00 land 4 Commercial site (owner) 4 50000 Pucca housing (Area in Sq 5 4406.03 800 ft) 6 Semi Pucca (Area in Sq ft) 6799.08 600 7 Kutcha (Area in Sq ft) 20432.22 350 8 Commercial site (squatter) 198 30000 EWS House 9 construction(Non 12 40000 Titleholder) House construction 10 4 40000 (owners) Shifting Allowance(Non- 11 210 10000 titleholders) Subsistence Allowance 12 210 11000 (Non-titleholders) Subsistence Allowance 13 8 30000 (Owners) Shifting 14 8 10000 Allowance(Titleholders) Economic generating 15 50 75000 asset(owner/tenant) Economic generating asset 16 198 30000 (squatter) Rental Value for 17 46 9000 Commercial tenant Rental Value for Residential 18 1 6000 tenant. Training for DP(commercial 19 245 15000 owner tenant, employee) 20 Vulnerable groups 210 25000 21 Group Entitlement (km) 74.10 15000 Table 14-3: Monitoring Of GRC Sl. 1st 2nd 3rd 4th Particulars No. Quarter Quarter Quarter Quarter 1 No. of cases referred to GRC 2 No. of cases settled by GRC 3 No. of cases pending with GRC 4 Average time taken for settlement of cases 5 No. of GRC meetings 6 Number of DPs moved to court 7 No. of pending cases with the court 8 No. of cases settled by the court 9 No. of GRC meetings

74

Annex 1: Typical Road Cross Section 75

76 77

78

Annex 2 : Details of Community Assets

Community Asset Details of link 31A (Mudgal-Tavaragere)

Total Affected Sl. Typeof Other Owner Chainage Side Village Structure Structure No. Asset Asset Type (Sq m) (Sq m) 1 1.125 RHS Mudgal Aralikatte Community 11.70 6.76 1.575 LHS Compound 212.50 12.50 2 Mudgal Others Government Wall 3 1.770 RHS Mudgal Temple Community 18.00 8.00 4 1.786 LHS Mudgal Others Water Tap Panchayat 6.00 2.25 6.750 LHS Mini 24.00 3.00 Water 5 Pikalihala Panchayat Supply Tank 6.752 LHS Hand 7.50 2.25 6 Pikalihala Panchayat Pump 6.755 LHS Water 30.00 12.50 7 Pikalihala Others Panchayat Tank 6.755 LHS Hand 9.00 2.25 8 Pikalihala Panchayat Pump 6.944 LHS Mini 9.75 2.25 Water 9 Pikalihala Panchayat Supply Tank 7.510 LHS Hand 12.75 2.25 10 Pikalihala Panchayat Pump 8.525 RHS Mini 12.75 2.25 Water 11 Ulmagere Panchayat Supply Tank 8.545 RHS Bus 51.00 24.00 12 Ulmagere Panchayat Stand 8.550 LHS Mini 17.25 2.25 Water 13 Ulamgere Panchayat Supply Tank 8.555 LHS Hand 9.00 2.25 14 Ulamgere Panchayat Pump 15 9.410 RHS Nagalapura Temple Community 14.00 4.00 11.257 LHS Water 27.50 10.00 16 Nagalapura Others Panchayat Tank 17 11.260 LHS Nagalapura Well Panchayat 17.50 6.25 18 11.318 RHS Nagalapura Aralikatte Community 25.00 15.00 11.42 LHS Mini 14.10 2.25 Water 19 Nagalapura Panchayat Supply Tank 11.855 LHS Hand 12.00 2.25 20 Nagalapura Panchayat Pump 14.148 RHS Pump 10.50 2.25 Chattara 21 Others House & Panchayat Tanda Bore Well 14.320 LHS Chattara Hand 9.00 2.25 22 Panchayat Tanda Pump 14.390 RHS Mini 32.00 8.00 Chattara 23 Water Panchayat Tanda Supply

79

Total Affected Sl. Typeof Other Owner Chainage Side Village Structure Structure No. Asset Asset Type (Sq m) (Sq m) Tank 14.44 RHS Chattara Hand 10.95 2.25 24 Panchayat Tanda Pump 14.585 RHS Chattara 20.00 16.00 25 Temple Community Tanda 26 15.915 RHS Chattara Mosque Community 12.00 4.00 16.008 LHS Chattara 95.00 5.00 27 Others Arch Community Tanda 16.015 RHS Bus 64.00 8.00 28 Chattara Panchayat Stand 16.018 LHS Chattara 76.00 12.00 29 Aralikatte Community Tanda 30 16.052 RHS Chattara Aralikatte Community 15.00 9.00 16.275 LHS Hand 13.50 2.25 31 Chattara Panchayat Pump 16.527 RHS Hand 8.25 2.25 32 Chattara Panchayat Pump 17.42 RHS Bus 55.00 15.00 33 Kalamalli Panchayat Stand 17.598 RHS Hand 8.25 2.25 34 Kalamalli Panchayat Pump 18.11 RHS Bus 55.00 7.50 35 Gollarahatti Panchayat Stand 19.353 LHS Water 25.00 2.00 36 Tadakigrama Others Panchayat Tank 37 20.985 RHS Killarahatti Others Bore Well Panchayat 9.75 2.25 21.648 LHS Hand 15.00 2.25 38 Killarahatti Panchayat Pump 21.652 LHS Water 32.00 8.00 39 Killarahatti Others Panchayat Tank 21.76 RHS Bus 60.00 24.00 40 Killarahatti Panchayat Stand 24.750 LHS Pump 7.50 2.25 41 Garjnal Others House & Panchayat Bore Well 24.860 LHS Pump 10.50 2.25 42 Garjnal Others House & Panchayat Bore Well 25.140 LHS Pump 8.25 2.25 43 Garjnal Others House & Panchayat Bore Well 26.485 RHS Bus 54.00 24.00 44 Mallur Panchayat Stand 26.495 RHS Hand 16.50 2.25 45 Mallur Cross Panchayat Pump 29.840 LHS Hand 15.00 2.25 46 Panchayat Pump 47 30.088 LHS Tavaragera Others Bore Well Panchayat 9.00 2.25 48 30.57 RHS Tavaragera Others Circle Community 12.00 9.00 30.765 LHS Primaty 65.00 5.00 49 Tavaragera Government School 50 30.860 LHS Tavaragera Aralikatte Community 21.00 3.00 51 30.895 RHS Tavaragera Temple Community 22.00 12.00 52 31.225 RHS Tavaragera Mosque Community 15.00 6.00

80

Community Asset Details of link 31B (Tavaragere-Kanakageri-Gangawathi)

Total Affected Sl. Typeof Owner Chainage Side Village Other Asset Structure Structure No. Asset Type (Sq m) (Sq m) 1 0.287 RHS Tavaragera Hand Pump Panchayat 6.00 2.25 0.480 RHS Electrician Room 20.00 16.00 2 Tavaragera Others Panchayat (KEB) 3 0.495 RHS Tavaragera Others Circle Community 9.00 2.25 4 0.497 RHS Tavaragera Others Flag Pole Community 9.00 2.25 5 0.552 RHS Tavaragera Others Bore Well Panchayat 7.50 2.25 6 0.686 LHS Tavaragera Hand Pump Panchayat 18.00 2.25 7 0.712 RHS Tavaragera Others Compound Wall Community 420.00 21.00 8 0.767 RHS Tavaragera Others Bore Well Panchayat 18.00 2.25 9 1.180 RHS Tavaragera Others Bore Well Panchayat 9.00 2.25 10 1.478 LHS Tavaragera Others Bore Well Panchayat 13.50 2.25 11 1.690 RHS Tavaragera Well Community 40.00 16.00 12 2.097 RHS Tavaragera Aralikatte Community 18.00 9.00 13 2.110 RHS Tavaragera Others Compound Wall Community 25.50 1.50 14 2.113 RHS Tavaragera Shrine Community 5.00 1.00 15 4.566 RHS Menadal Others Water Tank Panchayat 54.00 12.00 16 4.600 RHS Menadal Aralikatte Community 29.60 24.00 17 4.620 RHS Menadal Temple Community 50.00 60.00 18 4.660 RHS Menadal Others Pump House Panchayat 39.00 9.00 19 4.710 RHS Menadal Others Water Tank Panchayat 57.00 15.00 20 4.882 RHS Menadal Hand Pump Panchayat 16.50 2.25 21 4.915 RHS Menadal Others Compound Wall Government 1128.00 47.00 5.000 RHS Gramapanchayath 80.00 16.00 22 Menadal Others Panchayat Building 23 5.015 RHS Menadal Bus Stand Panchayat 54.00 18.00 6.863 RHS Ganganala 45.00 20.00 24 Bus Stand Panchayat Cross 6.868 LHS Ganganala 10.50 2.25 25 Hand Pump Panchayat Cross 26 9.895 RHS Huliyad Hand Pump Panchayat 10.50 2.25 27 11.590 RHS Huliyad Samadhi Private 12.70 4.00 28 11.740 RHS Huliyad Samadhi Private 16.50 2.25 29 11.840 RHS Hulihydura Others Gowdown Government 172.50 150.00 30 11.880 RHS Hulihydura Others Library Government 57.50 25.00 31 11.925 RHS Hulihydura Others Water Tank Panchayat 20.00 8.00 11.982 LHS Primaty 42.00 7.00 32 Hulihydura Government School 33 12.087 LHS Hulihydura Bus Stand Panchayat 67.50 7.50 34 12.092 RHS Hulihydura Others Statue Pvt. Trust 6.00 1.00 35 12.278 LHS Hulihydura Others Name Plate Pvt. Trust 7.50 1.50 36 12.390 RHS Hulihydura Hand Pump Panchayat 16.50 2.25 37 12.426 RHS Hulihydura Others Compound Wall Community 357.00 17.00 38 13.008 RHS Hulihydura Hand Pump Panchayat 9.00 2.25 39 13.010 RHS Hulihydura Temple Community 105.00 97.50 16.72 LHS Kanakapura Pump House & 13.50 2.25 40 Others Panchayat Cross Bore Well 16.75 LHS Kanakapura 7.50 2.25 41 Others Pump House Panchayat Cross 16.755 RHS Kanakapura 8.25 2.25 42 Others Bore Well Panchayat Cross 16.832 RHS Kanakapura 72.00 32.00 43 Bus Stand Panchayat Cross 16.840 RHS Kanakapura 24.00 16.00 44 Aralikatte Community Cross 81

Total Affected Sl. Typeof Owner Chainage Side Village Other Asset Structure Structure No. Asset Type (Sq m) (Sq m) 16.875 RHS Kanakapura 12.00 2.25 45 Hand Pump Panchayat Cross 21.165 LHS Water Tank & 54.00 15.00 46 Kanakagiri Others Panchayat Water Tap 47 22 LHS Kanakagiri Others Bore Hole Panchayat 12.00 2.25 48 22.095 RHS Kanakagiri Others Bore Hole Panchayat 19.50 1.50 22.14 RHS Driver's 80.00 40.00 49 Kanakagiri Others Association Pvt. Trust Foundation 50 22.485 LHS Kanakagiri Others Circle Pvt. Trust 4.00 1.00 22.7 LHS Mini Water 10.20 0.60 51 Kanakagiri Supply Panchayat Tank 22.895 LHS Mini Water 10.50 2.25 52 Kanakagiri Supply Panchayat Tank 22.999 RHS Mini Water 9.00 2.25 53 Kanakagiri Supply Panchayat Tank 23.04 RHS Primaty 59.50 3.50 54 Kanakagiri Government School 55 23.188 RHS Kanakagiri Others Water Tap Panchayat 6.00 1.00 56 23.29 LHS Kanakagiri Others Ambedkar Circle Pvt. Trust 9.75 2.25 57 23.3 RHS Kanakagiri Bus Stand Panchayat 52.00 12.00 58 23.47 LHS Kanakagiri Others Compound Wall Community 35.75 3.25 59 23.597 RHS Kanakagiri Hand Pump Panchayat 15.00 2.25 60 23.72 LHS Kanakagiri Others Bore Well Panchayat 10.50 2.25 61 23.758 LHS Kanakagiri Others Bore Well Panchayat 11.25 2.25 62 23.92 LHS Kanakagiri Others Bore Well Panchayat 13.50 2.25 63 24.915 RHS Kanakagiri Aralikatte Community 18.00 15.00 26.045 RHS MWS & Water 28.00 6.00 64 Tippenahalli Others Panchayat Tank 26.094 RHS Tippenahalli 10.00 4.00 65 Aralikatte Community Cross 26.098 RHS Tippenahalli 16.00 4.00 66 Others Mata Private Cross 26.1 RHS Tippenahalli 22.00 2.00 67 Others Water Tank Private Cross 26.312 RHS Tippenahalli 96.00 8.00 68 Bus Stand Panchayat Cross 26.822 RHS Tippenahalli Pump House & 10.50 2.25 69 Others Panchayat Cross Bore Well 70 29.832 LHS Kesarahatti Others Bore Well Panchayat 7.50 2.25 71 31.788 RHS Aralahalli Bus Stand Panchayat 48.00 24.00 72 32.63 LHS Aralahalli Others Bore Well Panchayat 10.50 2.25 33.02 LHS Pump House & 8.25 2.25 73 Kesarahatti Others Panchayat Bore Well 33.866 LHS Pump House & 6.75 2.25 74 Kesarahatti Others Panchayat Bore Well 75 33.93 LHS Kesarahatti Temple Community 12.00 4.00 34.055 LHS Mini Water 6.75 2.25 76 Kesarahatti Supply Panchayat Tank 77 34.18 LHS Kesarahatti Others Water Tap Panchayat 9.75 0.75 78 34.192 RHS Kesarahatti Bus Stand Panchayat 53.20 2.80 79 34.195 RHS Kesarahatti Others Compound Wall Panchayat 195.00 15.00

82

Total Affected Sl. Typeof Owner Chainage Side Village Other Asset Structure Structure No. Asset Type (Sq m) (Sq m) 80 34.508 RHS Kesarahatti Others Water Tap Panchayat 6.00 1.00 81 34.531 RHS Kesarahatti Hand Pump Panchayat 7.50 2.25 82 34.545 RHS Kesarahatti Anganavadi Anganawadi Panchayat 46.00 8.00 83 34.65 LHS Kesarahatti Hand Pump Panchayat 10.50 2.25 84 34.653 LHS Kesarahatti Temple Community 280.00 175.00 85 34.958 RHS Kesarahatti Others Water Tap Panchayat 6.00 1.00 86 35 RHS Kesarahatti Aralikatte Community 24.00 16.00 87 35.11 LHS Kesarahatti Shrine Community 10.00 4.00 88 35.692 RHS Herur Others Pump House Panchayat 9.00 2.25 35.78 LHS Pump House & 9.75 2.25 89 Herur Others Panchayat Bore Well 90 35.835 LHS Herur Others Arch Community 42.50 2.50 91 36.26 LHS Herur Temple Community 63.00 28.00 92 36.265 RHS Herur Others Arch Community 56.00 8.00 93 36.353 RHS Herur Others Water Tap Panchayat 8.00 0.50 36.415 RHS Old 25.00 7.50 94 Herur Others Gramapanchyath Panchayat Office 95 36.71 LHS Herur Others Ambedkar Circle Pvt. Trust 8.25 1.50 96 36.755 LHS Herur Others Water Tap Panchayat 7.50 2.25 97 36.79 LHS Herur Others Circle Pvt. Trust 11.00 2.00 38.895 LHS Galemma 16.00 8.00 98 Temple Community Camp 99 39.055 LHS Gonal Temple Community 22.00 10.00 100 39.546 LHS Gonal Bus Stand Panchayat 49.00 28.00 39.93 RHS Galemma 13.50 2.25 101 Hand Pump Panchayat Camp 39.94 RHS Galemma 112.00 84.00 102 Temple Community Camp 40.118 LHS Galemma MWS & Water 14.25 2.25 103 Others Panchayat Camp Tap 40.285 LHS Mini Water 17.25 0.75 Galemma 104 Supply Panchayat Camp Tank 40.31 LHS Galemma 36.00 12.00 105 Shrine Community Camp 40.555 LHS Basavanna 28.00 16.00 106 Shrine Community Camp 40.587 LHS Mini Water 14.25 2.25 Basavanna 107 Supply Panchayat Camp Tank 108 41.93 RHS Gangavathi Others Check Post Government 24.00 16.00 109 42.909 RHS Gangavathi Bus Stand Panchayat 85.50 27.00 83

Annex 3: Census and Community Asset Survey Schedules

Census Survey Schedules

PART 1

ASSET INFORMATION

Q.No. ______

Name of the Investigator: ______Date: ______

1.0 GENERAL IDENTIFICATION

1.1 Corridor Name 1.2 Corridor No

1.3 Link Name

1.4 Link No

1.5 Chainage

1.6 Side (LHS/RHS)

1.7 i) District

ii) Taluk

iii) Village/Town

1.8 Name of the owner

1.9 Name of the Respondent

1.10 Type of likely loss

1. Residential 2. Commercial 3. Residential cum Commercial

4. Office 5. Cattle Shed 6. Agricultural land 7. Farm House 8. Boundary Walls 9. Water bodies 10. Institutions 11. Livelihood / Income 12. Others (sp.)

Location: 1.Rural 2.Semi Urban 3.Town 4.City 5. Industrial

84

2.0 STRUCTURE IDENTIFICATION

2.1 Sl.No. of the Structure : ______

2.2 Address of the Structure : ______

2.3 Status of Occupier (Tick in the appropriate box)

Owner Legal Non-title holders Vacant Tenant Squatte Encroacher r

2.4 Ownership (Tick under appropriate type and enter the no. of households under the same)

Governmen Communit Private Trust t y

Type of ownership

2.5 Do you have legal document of

Structure 1. Yes 2. No RTC No. Sub No.

Agricultural land 1. Yes 2. No RTC No. Sub No.

(to be asked only to the owner) (If yes, ask for the legal document and check it with the Village Accountant)

3.0 PROOF OF RESIDENCE

3.1 Do you own a ration card? 1. Yes 2. No

Green Red Yellow (Please verify the category of card: APL/BPL/ Others ______) 3.2 If yes, Card No. ______

3.3 If Yes, since how long (only year) ______

85

4.0 TYPE OF CONSTRUCTION

4.1 MEASUREMENT OF THE STRUCTURE

(In Sq m)

OFFSET FROM EXISTING OFFSET FROM EDGE OF ASSET UP

CENTRAL LINE TO AREA GETTING AFFECTED

LAND STRUCTURE LAND STRUCTURE Starting Metre Ending Metre Width Total Area (in sq m)

4.2 STRUCTURE DETAILS Plinth Area Total Area being Sl.No Type of structure Length Width affected (in Sq m)

1 Type A (With RCC roof/ Stone/Brick work in Cement Mortar and plastered with cement mortar, Class II woodwork with fixtures, Mosaic/Polished slab flooring with water supply, sanitary and electrical works. 2 Type B (With RCC roof, Stone/Brick work in Cement Mortar and plastered with cement mortar/ Class II wood work with fixtures, cement concrete flooring with water supply, sanitary and electrical works. 3 Type C with tile roof, Stone/Country Brick work in Cement Mortar and plastered with cement mortar, ordinary woodwork fixtures. Flooring …………..(specify) with water supply sanitary and electrical work. 4 Type D with AC/GI sheet roof, Stone/Country Brick work in Mud Mortar and plastered with Cement Mortar, ordinary wood work fixtures flooring……………….(specify) with water supply sanitary and electrical work. Type E with Stone/Country Brick/Mud 5 walls ordinary slab flooring with ordinary wood work doors, roofing with slab/sheets 6 Type F with stone slab/GI sheet for walls with Mud flooring, Thatched roof

86

Plinth Area Total Area being Sl.No Type of structure Length Width affected (in Sq m)

7 Type G with Tatti walls with thatched roof mud flooring 8 Type I Wooden Box 9 Type J only Basement 10 Type K Up to lintel level

4.3 SITE MEASUREMENT

Sl. Width Total Area Area Length No. (in Sq m) 1 Built up area 2 Open Space 3 Total Area

4.4 BOUNDARY WALL DETAILS

Sl. Boundary/Compound wall Width Total Area No. Length (in Sq m) 1 Barbed wire fencing 2 Stone Masonry 3 Brick/Stone Masonry 4 Mud Wall 5 Others (Specify)

4.5 GATE DETAILS

Sl. Length (in m) Height (in m) No. 15 Type of Gate 1 M.S 2 Wooden 3 Others

4.6 Diagram of the Structure (Rough diagram with dimension – Not to Scale)

4.7 No. of Floors

Ground Ground+1 Others Total Floor Area (all floors) (Sq m)

4.8 DETAILS OF STRUCTURE IN ROW Give the following details

Sl.No. TYPE OF STRUCTURES IN ROW*

87

* 1. Pucca 2. Semi-Pucca 3. Kutcha

5.0 WATER SOURCES GETTING AFFECTED

Sources (in No.) User (use code)* Units to be acquired Dug Wells Tube Wells LI Points *[1. Domestic 2. Agriculture 3. Industrial 4. Others (to be specified)]

6.0 TREES COMING WITHIN LAND AREA TO BE ACQUIRED

Trees to be acquired Species - Type (In nos.) Fruit bearing Fodder Fuel wood

176. (PHOTOGRAPH TO BE ATTACHED – STRUCTURE ALONG WITH HEAD OF HOUSEHOLD/ RESPONDENT)

88

PART – II

HOUSE HOLD SCHEDULE (FOR OWNERS, SQUATTERS, ENCROACHERS)

1.0 HOUSEHOLD IDENTIFICATION

1.1 Name of the head of the HH: ______1.2 Name of the Respondent: ______

2.0 SOCIAL GROUP PARTICULARS

2.1 Religious Group

1. Hindu 2. Muslim 3. Sikh

4. Christian 5. Jain 6.Others (specify)______

2.2 Social Stratification:

1.SC 2.ST 3.Others (General)

2.3 Caste ______

3.0 Indebtedness Please indicate your borrowings during last one year

Source Reason for Amount Borrowed Borrowing (in Rs.) Bank Private Money Lender

Friends/Relatives

Others (Specify)

4.0 DETAILS OF HOUSEHOLD ASSETS OWNED Do you own any of the following?

1. Colour TV 1.Yes 2. No.

2. Refrigerator 1.Yes 2. No.

3. 2-Wheeler/4-Wheeler 1.Yes 2. No.

4. Cooking gas (LPG) 1.Yes 2. No.

5.Telephone 1.Yes 2. No.

89

5.0 DETAILS OF AGRICULTURAL EQUIPMENTS OWNED

Do you own any of the following?

1. Tractor 1.Yes 2. No.

2. Bullock carts 1.Yes 2. No.

3. Harversters 1.Yes 2. No.

4. Sprayer 1.Yes 2. No.

5. Others (Specify) 1.Yes 2. No.

6.0 DETAILS OF HOUSEHOLD MEMBER(S) WITH DISABILITY

Name of the household Sl.No. Sex Age Nature of Disability member

90

7.0 HOUSEHOLD PARTICULARS

7.1 Kindly provide the following details.

Sex Relation Total Income (Rs.) Income (Rs.) Sl. Name of the household (Male/ Marital Educatio Occupation with Head of Age No. members Femal Status n Subsidiar Subsidiar Within Outside HH Main Main e) y y COI* COI* 1 2 3 4 5 6 7 8 9 10 11 12 * Corridor of Impact (COI) (Please ensure that the respondent is above 18 yrs

91

Code for Relation with Head of Household

1. Self 2. Son 3. Brother 4. Son-in-law 5. Brother-in-law 6. Cousin 7. Daughter 8. Wife 9. Daughter-in-law 10. Sister 11. Sister-in-law 12. Mother 13. Mother-in-law 14. Grand Son 15. Grand Daughter 16. Grand Daughter-in-law 17. Grand Son-in-law 18. Niece

19. Nephew 20. Father 21. Others

Code for Marital Status

1. Married 2. Unmarried 3. Divorced 4. Separated 5. Widow 6. Widower 7. Deserted

Code for Education

1. Illiterate 2. Just literate 3. Primary (up to 4th) 4. Middle (5th, 6th, 7th) 5. Secondary (8th, 9th, 10th 6. Intermediate (12th pass) pass) 7. Graduate 8. Post Graduate 9. ITI/ Diploma

10. Engineer 11. Doctor 12. Others (specify)

Code for Occupation

1. Agriculture 2. Agriculture labour Allied agriculture activities (e.g. dairy, poultry, goatery, piggery, sheep rearing etc.) Service HH industries (specify) Commerce/Trade Professional (doctor, engineer, etc.) Skilled labor (welders, fitters, turner, plumber, electrician, mechanic, mason, etc.) Artisans (cobbler, etc.) Others (Specify)

8.0 LAND UTILISATION

8.1 Kindly give the details of landholding (applicable in case of acquisition of land) Kindly check up the ownership of land with the land records available with the respondents.

92

(Unit in Sq m) Wet Type Dry Land Garden Land Total Land 1. Total land owned

2. Land Proposed to be acquired

3. Remaining land

8.2 AFFECTED CATEGORY (Tick the appropriate category)

1 Title Land 2 Tenancy Land 3 Encroached Land 4 Bagar Hukum

8.3 LAND UTILISATION FOR AGRICULTURAL ENCROACHERS

Total area of encroached land

Type of crop grown

8.4 MARKET VALUE

Please provide the current market value of the land likely to be affected.

8.5 CROPPING PATTERN (Only in Case of Bypasses and Realignments) Kindly give the following details Area Cultivated Income from Yield Crop Rate (in land which Season Sl.No. Irrigate (Qtls/Acr Name Dry Rs./Qtls) is likely to d e) be acquired Kharif 1

2

3 Rabi 1

2

3 Summer 1

2

3 93

16 PART-III

FOR OWNERS and SQUATTERS (Only in case of the total loss of the structure)

1.0 STRUCTURE

RESIDENTIAL

1.1 Is your house electrified 1. Yes 2. No

1.2 Do you have piped water connection? 1. Yes 2. No

1.3 If no, what is your source of drinking water?

a) Open Well b) Bore Well c) Piped Water d) Others (Specify) ______

COMMERCIAL

1.4 What type of business you are doing?

1. Tea Stall 2. Grocery 3. Garments 4. Cloth Shop 5. Medical Store 6. Auto repair 7. Auto spare parts 8. Sweet Stall 9. Eatery (Dhaba) 10. Fruits and 11. Only fruits 12. Only vegetable Vegetable 13. Snacks 14. Pan/Cigarette 15. Bicycle repair 16. Tyre repairing 17. Tailoring 18. General Merchant 19. Clinic 20. School/College 21.Motel/Hotel 22. Electrical goods 23. Barber 24. Bakery 25. Others (specify)

1.5 Do you have any assistants/employees to help in the business? 1. Yes 2. No

1.6 If yes, how many? (in nos.) ______

1.7 What is your net income/year ? Rs. ______

94

PART IV

17 FOR TENANTS

1.0 RESIDENTIAL

1.1 Name and Address of the Owner ______

1.2 Name and Address of the Tenant ______

1.3 How long are you residing in this place (in years)? ______

1.4 How much rent you pay (in Rs.)? ______

1.5 Do you have a Rental Agreement ? 1. Yes 2. No

COMMERCIAL

1.6 Name and Address of the Owner ______

1.7 Name and Address of the Tenant ______

1.8 From how long you are running business in this structure (in years)? ______

1.9 How much rent do you pay/month? Rs. ______

1.10 Do you have a Rental Agreement ? 1. Yes 2. No

1.11 Do you have any helping hand? 1. Yes 2. No

1.12 If yes, how many (in Nos.)? ______

95

1.13 What type of business you are doing? ______

1. Tea Stall 2. Grocery 3. Garments 4. Cloth Shop 5. Medical Store 6. Auto repair 7. Auto spare parts 8. Sweat Stall 9. Eatery (Dhaba) 10. Fruits and 11. Only fruits 12. Only vegetable Vegetable 13. Snacks 14. Pan/Cigarette 15. Bicycle repair 16. Tyre repairing 17. Tailoring 18. General Merchant 19. Clinic 20. School/College 21.Motel/Hotel 22. Electrical goods 23. Barber 24. Bakery 25. Others (specify)

1.14 Usage of structure? 1.Shop 2.Godown 3.Workshop 4.Office

1.15 Turnover per month? Rs. ______

96

PART – V EMPLOYEES IN COMMERCIAL ESTABLISHMENTS Employee No.1 1. Name ______

2. Address ______

3. Age (years) ______

4. Sex M F

5. Working Full time Part-time

6. Education ______

7. Income (Rs.) ______

8. Any other source (specify) ______

9. Any other income generating skill known ______

Employee No.2 1. Name ______

2. Address ______

3. Age (years) ______

4. Sex M F

5. Working Full time Part-time

6. Education ______97

7. Income (Rs.) ______

8. Any other source (specify) ______

9. Any other income generating skill known ______

Employee No.3 1. Name ______

2. Address ______

3. Age (years) ______

4. Sex M F

5. Working Full time Part-time

6. Education ______

7. Income (Rs.) ______

8. Any other source (specify) ______

9. Any other income generating skill known ______

98

PART VI

18 EXTENT OF LOSS

(NOT TO BE ASKED BUT TO BE ASSESSED BY THE INVESTIGATOR)

1. Losing Total House 2. Losing Partial House 3. Losing Total House and part of Plot (Aangan or Courtyard) 4. Losing Total Plot and Total House 5. Losing Total Plot and Partial House 6. Losing Partial Plot 7. Losing Total Commercial Structure 8. Losing Partial Commercial Structure 9. Losing Total Commercial Structure and Partial Plot 10. Losing Total Commercial Structure and Total Plot 11. Losing Partial Commercial Structure and Total Plot 12. Losing Total House and Total Commercial Structure 13. Losing Total House, Total Commercial Structure and Total Plot 14. Losing Total House, Total Commercial Structure and Part of Plot 15. Losing Total House, Partial Commercial Structure and Part of Plot 16. Losing Partial House, Partial Commercial Structure and Part of Plot 17. Losing Total House and Partial Commercial Structure 18. Losing Total Commercial Structure and Part of House 19. Losing Total Boundary Wall 20. Losing Partial Boundary Wall 21. Losing Total Agricultural Land 22. Losing Partial Agricultural Land 23. Losing Total Cattle Shed 24. Losing Part of Cattle Shed 25. Losing Water bodies 26. Losing Total Livelihood for Commercial Tenant 27. Others (Specify)

99

In case the tenancy/ownership is under dispute (legal or otherwise) please make a short note below

Field Supervisor:______Date: ______

Endorsed by:

Revenue Officer:______Date: ______

PWD Officer: ______Date: ______

100

18.1 Community Asset Schedule

Q.No.: ______

Name of Investigator: ______Date : ______

1.0 GENERAL IDENTIFICATION

1.1 Corridor Name

1.5 Corridor No

1.6 Link Name

1.7 Link No

1.9 Chainage

1.10 Side ((LHS/RHS)

1.11 i) District

ii) Taluk

iii) Village/Town

1.12 Name of the owner

1.9 Name of the Respondent

2.0 STRUCTURE IDENTIFICATION

2.1 Sl. No. of the structure :______

2.2 Address of the structure: ______

2.3 Tick the relevant community asset affected:

Primary High school Anganavadi Samadhi College (C ) Mosque (M) school (PS) (HS) (A) (S) Temple (T) Shrine (SH) Primary Health Community Aralikatte Hospital (H) Center Hall/Club (CH) (AK) (PHC/PHU) Bus stand Grazing land Well (W) Handpump (HP) Irrigation (IP) Pond (P) (BS) (GL) Points Mini Water Others Supply tank including (MWS) cultural 101

properties (SPECIFY)

2.4 Type of Ownership Tick the relevant box

Private Government Panchayat Pvt. Trust Public Trust Community

2.5 Measurement of the structure

OFFSET FROM EXISTING OFFSET FROM EDGE OF ASSET CENTRAL LINE (in Sq m) UP TO AREA GETTING AFFECTED (in Sq m)

LAND STRUCTURE LAND STRUCTURE

Starting Metre Ending Metre Width Total Area (in sq m)

2.6 What is the approximate location of the community asset?

1. In the beginning 2. Central part 3. Towards End

2.7 Diagram of the structure

2.8 Please attach a photograph of the structure with the assigning number.

102

Annex 4: Details of Land Acquisition Land Acquisition Owner Details 31 A Area in Acre-Gunta % of Sl. Survey Affected Village OwnerName Total Area Affected No. No. Area Area Kaseemsab S/o 1 Mudgal 394 0.08 14.07 0.57 Dodda Nabisab Shankrappa S/o 2 Vyakaranala 47/Cp 0.15 12.21 1.23 Lakshmana Balappa S/o 3 Vyakaranala 48/1/8 0.00 0.00 0.00 Venkappa Nagalapura 4 Vyakaranala 48/1-A Venkappa S/o 0.09 0.00 0.00 Balappa Venkoba S/o 5 Vyakaranala 48/1/C 0.00 0.00 0.00 Venkappa Balappa S/o 6 Vyakaranala 48/2-C 0.00 0.00 0.00 Ramappa Madivalappa S/o 7 Vyakaranala 48/2A 0.00 0.00 0.00 Ramappa Shankrappa S/o 8 Vyakaranala 48/2B 0.00 0.00 0.00 Ramappa Tippanna S/o 9 Vyakaranala 48/3 0.00 0.00 0.00 Hanumappa Venkanagowda S/o 10 Nagalapura 65/0 0.11 4.32 2.55 Hanumanagowda Beerappa S/o 11 Nagalapura 44/A 2.16 3.22 67.08 Lachumappa Narasappa S/o 12 Nagalapura 44/D 0.00 0.00 0.00 Lachumappa Gyanappa S/o 13 Todaki 4 0.00 31.18 0.00 Sagarappa Adappa S/o 14 Todaki 4 0.05 0.00 0.00 Chatrappa Amarappa S/o 15 Todaki 4 0.00 0.00 0.00 Chatrappa Venkanagowda S/o 16 Todaki 4 0.00 0.00 0.00 Hanumanagowda Channannagowda 17 Killarahatti 86 0.00 0.00 0.00 S/o Chatrappa Venkappa S/o Sanna 18 Killarahatti 86/P4 0.00 0.00 0.00 Chatrappa Hanumappa S/o 19 Killarahatti 86/P5 0.00 0.00 0.00 Sanna Chatrappa 103

% of Sl. Survey Affected Village OwnerName Total Area Affected No. No. Area Area Husainsab S/o 20 Konapura 36/1 0.05 11.10 0.45 Balesab Mariyappa S/o 21 Konapura 36/1 0.00 5.30 0.00 Durugappa Ananda S/o 22 Konapura 36/2 0.00 5.32 0.00 Mariyappa Harijana Rajasab S/o9 23 Konapura 36/3 0.00 0.14 0.00 Sajjulasab Beerapa S/o 24 Konapura 49 0.00 0.00 0.00 Hanumappa Chandrashekhara 25 Mullura 77/A 0.10 6.00 1.67 S/o Sangappa Rajashekhara S/o 26 Mullura 77/A 0.00 1.03 0.00 Sangappa Kanteppa S/o 27 Ulimeshwara 33/1A 0.00 0.00 0.00 Hanumappa Nagalapura 28 Vyakaranala 44/1 Husainsab S/o 0.04 8.00 0.50 Husainsab Sanganagowda S/o 29 Vyakaranala 44/2 0.00 0.00 0.00 Basanagowda Siragumpi 30 Vyakaranala 44/3 Hanumanagowda S/o 0.00 0.00 0.00 Ramanagowda

31 Vyakaranala 44/4 New Road 0.00 0.35 0.00

Hanumanagowda S/o 32 Todaki 3/1 0.03 5.27 0.57 Girigowda Lokenayaka S/o 33 Killarahatti 76/1A 0.00 0.00 0.00 Naryana Nayka Gopi Nayka S/o 34 Killarahatti 76/1E 0.00 3.00 0.00 Seetharama Shivappa S/o 35 Killarahatti 76/2A 0.00 0.32 0.00 Purunayka 76/2A, Kamalavva W/o 36 Killarahatti 0.00 4.02 0.00 76/2E Govinda Nayka 76/4, Krishnappa S/o 37 Killarahatti 76/3, 0.00 0.14 0.00 Surya Nayka 76/1 M Lakshminarayana 38 Killarahatti 77/P1 0.00 5.20 0.00 S/o Poolaiah Mahadevanagowda 0.00 39 Killarahatti 82 0.00 0.00 S/o Mananagowda

104

% of Sl. Survey Affected Village OwnerName Total Area Affected No. No. Area Area Gyanappa S/o Sanna 40 Killarahatti 81/1/P1 0.06 9.26 0.65 Chatrappa Gangappa S/o 41 Killarahatti 81/1P3 0.00 4.36 0.00 Bhimappa Yankappa S/o 42 Killarahatti 39/1/P1 0.00 0.00 0.00 Gangappa Hokrani Hanumappa S/o 43 Killarahatti 39/1/P2 0.00 5.36 0.00 Nariyappa Hire Thimmappa S/o 44 Killarahatti 39/1P3 0.00 0.00 0.00 Nariyappa Sanna Thimmappa 45 Killarahatti 39/1P4 0.00 0.00 0.00 S/o Nariyappa Hanmappa S/o 46 Konapura 2 0.02 9.36 0.21 Hanmappa Jainabee W/o Noor 47 Konapura 2 0.00 0.00 0.00 Ahmada Maniyur Noor Ahmad S/o 48 Konapura 20 0.02 3.10 0.65 Bashasab Maniyar Sarkari Gayarana 49 Konapura 20 0.00 10.34 0.00 Aranya Ilake

Land Acquisition Owner Details 31 B Area in Acre-Gunta % of Sl. Survey Affected Village OwnerName Total Area Affected No. No. Area Area Mahanthappa S/o 1 Tavaragere 521/A 0.03 14.03 0.21 Veerappa Narayanappa S/o 2 Tavaragere 521/P2 Shankarappa 0.00 5.00 0.00 Kondakundi Channamma W/o 3 Tavaragere 522 0.02 0.00 0.00 Mallanna Shama Singh S/o 4 Tavaragere 224/1A 0.00 4.05 0.00 Babanna Govinda Singh S/o 5 Tavaragere 224/1/A 0.00 0.00 0.00 Shama Singh Venkanna S/o 6 Tavaragere 224/2 0.00 1.01 0.00 Hanumanthappa Khabarsthan 7 Tavaragere 224/3 Government. 0.00 0.00 0.00 Masanavadi 105

% of Sl. Survey Affected Village OwnerName Total Area Affected No. No. Area Area Narasubai W/o 8 Tavaragere 228/1A 0.05 9.23 0.54 Padmanabhacharya Karnataka Grama 9 Tavaragere 228/2 Seva Sangha 0.00 0.00 0.00 Charaka 10 Tavaragere 228/3 Sarkari Sadak 0.00 0.00 0.00 Shivanagowda S/o 11 Tavaragere 228/4 0.00 0.00 0.00 Ayyanagowda Somamma W/o 12 Tavaragere 228/5 Basanagowda Polisa 0.00 0.00 0.00 Patila Seethabai W/o 13 Tavaragere 237/2 0.04 13.15 0.30 Shama Singh 14 Tavaragere 237/3 Sarkari Sadak 0.00 0.00 0.00 Ramappa S/o 15 Tavaragere 238/1 Naraharappa 0.01 17.08 0.06 Maddina Yamanamma W/o 16 Tavaragere 238/A 0.00 0.00 0.00 Rudrappa Lakshmamma W/o 17 Tavaragere 238/AP1 0.00 0.00 0.00 Shamanagowda 18 Hulihydara 1 Masana Mata Sarkari 0.20 0.00 0.00 Tayamma W/o 19 Hulihydara 21/E 0.00 0.00 0.00 Venkappa Gaddi Yankanna S/o 20 Hulihydara 21/E 0.03 28.34 0.11 Shankrappa Basavaraja S/o 21 Hulihydara 21/E 0.00 0.00 0.00 Shankrappa Mudakappa S/o 22 Hulihydara 21/E 0.00 0.00 0.00 Shankrappa Gaddi Hanumanthappa S/o 23 Hulihydara 21/E 0.00 0.00 0.00 Virupakshappa Hanumanthappa S/o 24 Hulihydara 21/E1 0.00 0.00 0.00 Virupakshappa Vijaya S/o 25 Hulihydara 21/EP1 0.00 0.00 0.00 Venkareddy Pushpavathi W/o 26 Hulihydara 21/EP1 0.00 0.00 0.00 Yankanna Gaddi Huligevva W/o 27 Tippanala 37/A 0.07 0.00 0.00 Pamappa Harijana Hulugappa S/o 28 Tippanala 37/E 0.00 8.00 0.00 Basappa Tippamma W/o 29 Tippanala 38/B 0.00 0.00 0.00 Maridurgappa

106

% of Sl. Survey Affected Village OwnerName Total Area Affected No. No. Area Area 37/B2- Pamappa S/o 30 Tippanala 0.02 0.00 0.00 p1 Thimmappa Sangappa S/o 31 Sulekal 133/A/1 0.00 0.14 0.00 Malleshappa Shivappa S/o 32 Sulekal 133/A/2 0.00 5.11 0.00 Malleshappa Kallurappa S/o 33 Sulekal 133/A/3 0.00 0.00 0.00 Malleshappa Channabasappa S/o 34 Sulekal 133/B1 0.00 3.00 0.00 Pampapathi Channabasava S/o 35 Sulekal 133/B2 0.00 0.13 0.00 Virupakshappa Veerabasamma W/o 36 Sulekal 133/C/2 0.00 4.01 0.00 Virupakshappa Desai Anusuya W/o 37 Sulekal 133/G 0.00 0.05 0.00 Shivappa G Sridhar S/o 38 Aralihalli 83 0.02 5.08 0.39 Beerappa Shankrappa S/o 39 Aralihalli 84 0.02 0.00 0.00 Satyappa Fakirappa S/o 40 Herur 78/1 0.06 9.10 0.66 Erappa Channagowda S/o 41 Herur 79/2B Pampanagowda Sa: 0.00 2.21 0.00 Herur 79/2D- Somanagowda S/o 42 Herur 0.00 1.09 0.00 p2 Pampanagowda Basavaraja S/o 43 Herur 78/CP1 0.00 2.20 0.00 Erappa Shekharagowda S/o 44 Herur 76/2C 0.00 1.12 0.00 Sakkaragowda Gowramma W/o 45 Herur 78/D 0.00 Pampanagowda Mallikarjunagowda 46 Herur 78/E 0.00 S/o Pampanagowda Devendragowda S/o 47 Herur 78/F 0.00 Pampanagowda Mekaraju S/o 48 Herur 78/G 0.00 Ramaiah Mallikarjunagowda 49 Herur 78/E 0.00 S/o Pampanagowda Sanna Fakirappa S/o 50 Herur 78/1A 0.00 Erappa 32/-1/B, Pampapathi S/o 51 Gonala 0.04 1.10 3.64 32/P5 Honnappa 107

% of Sl. Survey Affected Village OwnerName Total Area Affected No. No. Area Area Basappa S/o Rajavva 52 Gonala 32/-2/1 0.00 Harijana Nagappa S/o 53 Gonala 32/P6 0.00 Lenkappa 36/-1, Virupakshagowda 54 Gonala 0.00 32/P3 S/o Sakkaragowda Durugamma W/o 55 Gonala 36/1/4 Venkappanasapudi 0.00 0.30 0.00 Sa:Gonala Sambashivarao S/o 56 Gonala 36/1/6 0.00 Kanakam Nagappa S/o 57 Gonala 36/P1 0.00 Mukhappa Pampanagowda S/o 58 Gonala 36/P2 0.00 Pampanagowda Nagamma W/o 59 Gonala 36/1/5 0.08 1.10 7.27 Sanna Pampanna Basappa S/o 60 Gonala 36-2/p2 0.00 Rajamma Venkatesha S/o 61 Gonala 36/P2 Bhimappa Sa: 0.00 Gundamma Camp 36/11.3 Durugamma W/o 62 Gonala 0.00 0P1 Kenchappa Harijana Honnurappa S/o 63 Gonala 36/2 0.00 Sanna Durugamma Chakote Pampanna 64 Gonala 35/A 0.00 S/o Basanna Mallikarjuna S/o 65 Gonala 35-1/B 0.00 Venkatareddy 35- Thimmareddy S/o 66 Gonala 0.00 1/BP1 Venkatareddy 35- Sangappa S/o 67 Gonala 0.00 1/BP1 Venkatareddy 35/1/BP Channabasappa S/o 68 Gonala 0.00 1 Venkatareddappa Kotramma W/o 69 Gonala 35/P1 0.04 1.23 3.25 Amarappa Palakshappa S/o 70 Gonala 35/P4 0.00 Sharanappa Akki Channappa S/o 71 Gonala 35/P6 0.00 1.09 0.00 Malleshappa 35/P2, Basappa S/o 72 Gonala 0.00 35/P3 Thimmanna

108

% of Sl. Survey Affected Village OwnerName Total Area Affected No. No. Area Area 209/A, Chennamma W/o 73 Tavaragere 209/1/P 0.03 0.37 8.11 Papanagowda 1 209/1, Basanagowda S/o 74 Tavaragere 0.00 209/2 Amaregowda Ayyanagowda S/o 75 Tavaragere 209/2p2 0.00 Pampanagowda Sathyanarayana 76 Tavaragere 208/1 Shetty S/o Sanna 0.08 18.08 0.44 Vittobanna Daroji Narahareppa S/o 77 Tavaragere 208/1P1 Sanna Vittobanna 0.00 Daroji Praneshappa S/o 78 Tavaragere 208/1P2 Sanna Vittobanna 0.00 Daroji Srinivasa S/o Sanna 79 Tavaragere 208/1P3 0.00 Vittobanna Daroji Hanumeshappa S/o 80 Tavaragere 208/1P4 Sanna Vittobanna 0.00 Daroji Keshavarao S/o 81 Tavaragere 208/2 0.00 Shyamarao Kulkarni Narayana Singh S/o 82 Tavaragere 298/1 0.07 3.07 2.28 Basavanth Singh Govinda Singh S/o 83 Tavaragere 208/1P6 0.00 1.08 0.00 Venkata Singh Narayana Singh S/o 84 Tavaragere 298/4 0.00 6.21 0.00 Basavanth Singh Kanaka Reddy S/o 85 Kanakagiri 15 0.02 7.05 0.28 Kanakappa Reddy Bhima Reddy S/o 86 Kanakagiri 15/A 0.00 3.23 0.00 Rama Reddy Veeresha S/o 87 Kanakagiri 15/C 0.00 7.05 0.00 Gopalappa Prakasha Reddy S/o 88 Kanakagiri 15/D 0.00 Surendra Reddy Virupaksha Reddy 89 Kanakagiri 15/P1 0.00 S/o Rama Reddy 152/1,2, B Khadarsab S/o 90 Kanakagiri 0.04 7.09 0.56 3,4,5 Peersab Hazi 91 Kanakagiri 152/6 Parampoka Sarkari 0.00 1.01 0.00 109

% of Sl. Survey Affected Village OwnerName Total Area Affected No. No. Area Area Neelamma W/o 92 Sulekal 92/1A 0.00 3.17 0.00 Mudiyappa Desai Lingappa S/o 93 Sulekal 92/1/C 0.00 2.09 0.00 Dampanna Desai Virupakshappa S/o 94 Sulekal 92/1D 0.00 1.09 0.00 Lingappa Desai Devappa S/o Sanna 95 Sulekal 92/2/A 0.00 8.35 0.00 Hampanna Hanmanthappa S/o 96 Sulekal 92/2B 0.00 4.20 0.00 Balappa Pampapathi S/o 97 Sulekal 92/B 0.00 2.08 0.00 Shivalingappa Desai Sathyanarayana S/o 98 Herur 79/1 0.08 3.12 2.56 Pattabhi 79/2D- Mallikarjuna Gowda 99 Herur 0.00 p1 S/o Veerana Gowda

110

Annex 5: Structure Details Details of Structure losers – 31 A % of Total Str. Str. Struct Str. Sl. Chain Occu. Affected Gettin Side Village Name Loss Type ure Area No. age Status Area (in g Type (in Sq Sq m) Affect m) ed Khaja Ajmeersab Semi 1 1.712 RHS Mudgal S/o Owner Residential 1.50 21.00 7.14 Pucca Mohammad Rafalsab Sunnusab S/o 2 1.720 LHS Mudgal Squatter Commercial Kutcha 3.00 4.00 75.00 Rasoolsab

Ameersab S/o 3 1.750 RHS Mudgal Squatter Commercial Kutcha 4.00 4.00 100.00 Rajasab

Rehmansab Legal 4 1.752 LHS Mudgal Residential Pucca 2.00 40.00 5.00 S/o Husainsab Tenant

Ajmeersab 5 1.752 RHS Mudgal Squatter Commercial Kutcha 4.00 4.00 100.00 S/o Rajasab

Ajmeersab 6 1.755 RHS Mudgal Squatter Commercial Kutcha 4.00 4.00 100.00 S/o Khajasab

Karimsab S/o 7 1.756 LHS Mudgal Owner Residential Pucca 2.25 30.00 7.50 Rajasab Azmeersab 8 1.760 LHS Mudgal S/o Owner Residential Pucca 5.00 70.00 7.14 Dasthagirsab Ameerbaig 9 1.773 LHS Mudgal S/o Squatter Commercial Kutcha 3.90 10.50 37.14 Yaseenbaig Mallikarjunapp Semi 10 1.773 RHS Mudgal a S/o Owner (O) Toilet 3.00 4.00 75.00 Pucca Adavappa (O) Semi 11 1.774 RHS Mudgal Dheenusab Owner 4.80 12.00 40.00 Projection Pucca

Maibusab S/o Legal 12 1.780 RHS Mudgal Commercial Kutcha 4.00 4.00 100.00 Shameersab Tenant Kanakanagow Ulimesh da S/o 13 8.545 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 wara Venkanagowd a Ulamger Mallappa S/o 14 8.555 RHS Squatter Commercial Kutcha 12.00 12.00 100.00 e Siddappa

Nagalap Katyappa S/o Semi 15 9.945 LHS Owner Residential 7.00 15.00 46.67 ura Kuppanna Pucca

Nagalap Mutthu S/o 16 11.308 LHS Squatter Commercial Kutcha 6.25 6.25 100.00 ura Sharanappa

Nagalap Yamunappa 17 11.312 LHS Squatter Commercial Kutcha 17.10 18.00 95.00 ura S/o Chatrappa

Nagalap Jagganath S/o 18 11.365 LHS Owner (O) Staircase Pucca 2.40 4.00 60.00 ura Kuppa Rao Rudramma Nagalap Encroach 19 11.397 LHS W/o Commercial Pucca 14.00 40.00 35.00 ura er Sharanappa 111

% of Total Str. Str. Struct Str. Sl. Chain Occu. Affected Gettin Side Village Name Loss Type ure Area No. age Status Area (in g Type (in Sq Sq m) Affect m) ed Bhadrappa Nagalap 20 11.402 LHS S/o Squatter Commercial Kutcha 6.25 6.25 100.00 ura Sharanappa Mudukanagow Nagalap da S/o 21 11.423 LHS Squatter Commercial Kutcha 2.25 2.25 100.00 ura Kanaka Reddy Basavaraj S/o Nagalap 22 11.427 LHS Krishna Squatter Commercial Kutcha 3.00 3.00 100.00 ura Reddy Hanumanthag Nagalap owda S/o 23 11.435 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 ura Basavanagow da Nagalap Ramesh S/o 24 11.437 LHS Squatter Commercial Kutcha 28.00 28.00 100.00 ura Shambaiah

Nagalap Tippamma 25 11.440 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 ura W/o Mallaiah

Nagalap Chowdamma 26 11.448 LHS Squatter Commercial Kutcha 9.00 9.00 100.00 ura W/o Yellappa Ambamma Nagalap 27 11.451 LHS W/o Squatter Commercial Kutcha 2.25 2.25 100.00 ura Lakshmana Nagalap 28 11.470 LHS Chandamma Squatter Commercial Kutcha 9.00 9.00 100.00 ura Nagalap Gangappa S/o Semi 29 11.520 LHS Owner (O) Toilet 9.80 21.00 46.67 ura Gangappa Pucca

Nagalap Shameedsab 30 11.557 LHS Squatter Commercial Kutcha 9.00 9.00 100.00 ura S/o Husainsab Nagamma Nagalap 31 11.610 LHS W/o Owner Residential Pucca 37.50 105.00 35.71 ura Sharanappa Yamanaiah Nagalap 32 11.622 RHS S/o Squatter Residential Kutcha 18.00 36.00 50.00 ura Hanumaiah Nagalap Yamanappa 33 11.625 LHS Owner Residential Pucca 12.50 80.00 15.63 ura S/o Chatrappa Hanumamma Nagalap Semi 34 11.628 LHS W/o Owner Residential 7.00 56.00 12.50 ura Pucca Chatrappa Balappa S/o Semi 35 14.366 RHS Chattara Owner Residential 6.75 25.00 27.00 Kamalappa Pucca

Somappa S/o 36 14.372 RHS Chattara Squatter Commercial Kutcha 3.00 9.00 33.33 Arjuanappa Lakshmipathi Shetty S/o 37 16.000 LHS Chattara Squatter Commercial Kutcha 9.00 18.00 50.00 Thimmaiah Shetty Narasaiah S/o Semi 38 16.005 RHS Chattara Squatter Commercial 9.90 36.00 27.50 Venkanna Pucca

Ayyappa S/o 39 16.013 RHS Chattara Squatter Commercial Kutcha 2.00 4.00 50.00 Mallappa

Basavaraja 40 16.016 LHS Chattara Squatter Commercial Kutcha 2.25 2.25 100.00 S/o Chatrappa

112

% of Total Str. Str. Struct Str. Sl. Chain Occu. Affected Gettin Side Village Name Loss Type ure Area No. age Status Area (in g Type (in Sq Sq m) Affect m) ed Bhimaiah 41 16.017 LHS Chattara Shetty S/o Squatter Commercial Kutcha 4.00 4.00 100.00 Rajappa Basavaraja 42 16.022 LHS Chattara Squatter Commercial Kutcha 2.25 2.25 100.00 S/o Manappa Balanagowda Semi 43 16.024 LHS Chattara S/o Owner Commercial 6.00 15.00 40.00 Pucca Balanagowda Hanumeshgo Encroach Semi 44 16.027 LHS Chattara wda S/o Commercial 19.50 65.00 30.00 er Pucca Balanagowda Venkatesha 45 16.035 RHS Chattara S/o Squatter Commercial Kutcha 14.00 28.00 50.00 Shyamanna Balanagowda (O) 46 16.045 LHS Chattara S/o Squatter Pucca Basement Balanagowda Neelaiahswa 47 16.062 RHS Chattara Owner Residential Kutcha 21.00 70.00 30.00 my Chatrappa S/o 48 16.072 RHS Chattara Owner Residential Kutcha 28.00 28.00 100.00 Hanumappa Amaregowda 49 16.080 LHS Chattara S/o Owner Residential Kutcha 20.30 28.00 72.50 Balanagowda Yamanappa 50 16.080 RHS Chattara S/o Owner Cattle Shed Kutcha 12.00 12.00 100.00 Kantyappa Siddappa S/o 51 16.087 RHS Chattara Owner Residential Kutcha 30.00 60.00 50.00 Chatrappa Channabasam Semi 52 16.095 RHS Chattara ma W/o Owner Residential 3.50 28.00 12.50 Pucca Kariyappa Yamanura S/o Semi 53 16.110 RHS Chattara Owner Residential 24.00 24.00 100.00 Hanumappa Pucca

Yankappa S/o 54 16.120 RHS Chattara Owner Residential Kutcha 9.00 9.00 100.00 Hanumappa Shivarudrappa 55 16.126 RHS Chattara S/o Squatter Commercial Kutcha 4.00 4.00 100.00 Adibasavanna Hanumappa Killarahat 56 21.585 LHS S/o Owner Residential Kutcha 10.50 28.00 37.50 ti Mahadevappa Killarahat Erappa S/o Semi 57 21.754 RHS Squatter Commercial 30.00 30.00 100.00 ti Narasappa Pucca

Killarahat Amaresh S/o Semi 58 21.768 RHS Squatter Commercial 9.00 9.00 100.00 ti Nagappa Pucca

Killarahat Ramamurthy Semi 59 21.772 RHS Squatter Commercial 10.50 10.50 100.00 ti S/o Subbaiah Pucca Sanganagowd Tavarage 60 30.585 LHS a S/o Squatter Commercial Kutcha 2.50 25.00 10.00 re Linganagowda Tavarage Basappa S/o 61 30.590 LHS Squatter Commercial Kutcha 1.00 4.00 25.00 re Gyanappa

Tavarage Shankrappa 62 30.592 RHS Squatter Commercial Kutcha 2.25 2.25 100.00 re S/o Bhimappa 113

% of Total Str. Str. Struct Str. Sl. Chain Occu. Affected Gettin Side Village Name Loss Type ure Area No. age Status Area (in g Type (in Sq Sq m) Affect m) ed Tavarage Nagaraja S/o 63 30.594 LHS Squatter Commercial Kutcha 1.50 9.00 16.67 re Basappa Tavarage Legal 64 30.594 RHS Mahalingappa Commercial Kutcha 4.80 32.00 15.00 re Tenant Shalamsab Tavarage 65 30.598 RHS S/o Husain Squatter Commercial Kutcha 4.50 12.00 37.50 re Khan Mohammad Tavarage 66 30.605 RHS Jaffar S/o Squatter Commercial Kutcha 1.00 4.00 25.00 re Usmansab Shyamavva Tavarage 67 30.845 LHS W/o Squatter Residential Kutcha 3.00 12.00 25.00 re Shyamanna Tavarage Mariyappa S/o 68 30.854 LHS Squatter Residential Kutcha 4.00 16.00 25.00 re Ningappa

Tavarage Husenamma 69 30.860 LHS Owner Residential Pucca 16.50 48.00 34.38 re W/o Ulagappa

Tavarage Durgesh S/o 70 30.866 LHS Owner Residential Pucca 17.50 40.00 43.75 re Hulugappa Renukamma Tavarage Legal 71 30.872 LHS W/o Commercial Pucca 20.63 44.00 46.88 re Tenant Parashuram Parasappa Tavarage Legal 72 30.878 LHS S/o Commercial Pucca 48.00 88.00 54.55 re Tenant Thimmappa Tavarage Ameedsab 73 30.895 RHS Squatter Commercial Kutcha 3.00 9.00 33.33 re S/o Rajasab

Tavarage Khajavali S/o 74 30.915 RHS Squatter Commercial Kutcha 12.50 25.00 50.00 re Mehaboobsab Tavarage Suresh S/o 75 30.957 RHS Squatter Commercial Kutcha 4.00 4.00 100.00 re Mallappa Devendra S/o Tavarage 76 31.210 LHS Lakshman Squatter Commercial Kutcha 2.00 4.00 50.00 re Rao Shyamaraju Tavarage 77 31.220 LHS S/o Squatter Commercial Kutcha 1.00 4.00 25.00 re Channappa Tavarage Mutthamma Legal 78 31.225 RHS Commercial Kutcha 1.00 6.00 16.67 re W/o Adeppa Tenant Gurulingaiah Tavarage S/o Legal 79 31.230 LHS Commercial Kutcha 2.25 2.25 100.00 re Veerabhadrai Tenant ah Tavarage Sridhar S/o 80 31.230 RHS Squatter Commercial Kutcha 1.00 4.00 25.00 re Basappa Gurulingaiahs Tavarage wamy S/o Legal 81 31.232 LHS Commercial Kutcha 17.50 35.00 50.00 re Veerabhadrai Tenant ah Tavarage Amaresh S/o 82 31.240 LHS Squatter Commercial Kutcha 0.75 2.25 33.33 re Lakshmana

Tavarage Shameedsab 83 31.246 LHS Squatter Commercial Kutcha 7.20 16.00 45.00 re S/o Gavisab

Tavarage Murthuja S/o 84 31.248 RHS Squatter Commercial Kutcha 2.25 2.25 100.00 re Shameedsab

114

% of Total Str. Str. Struct Str. Sl. Chain Occu. Affected Gettin Side Village Name Loss Type ure Area No. age Status Area (in g Type (in Sq Sq m) Affect m) ed Tavarage Legal 85 31.250 LHS Tippanna Commercial Kutcha 9.00 50.00 18.00 re Tenant Tavarage 86 31.255 LHS Vacant Shop Squatter Commercial Kutcha 2.25 2.25 100.00 re Tavarage Venkatesha 87 31.257 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 re S/o Balappa Mangal Singh Tavarage 88 31.260 LHS S/o Mahendra Squatter Commercial Kutcha 4.00 4.00 100.00 re Singh

Details of Structure losers – 31B % of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Tavarag Ashok S/o 1 0.007 RHS Squatter Commercial Kutcha 2.00 4.00 50.00 ere Ramanna Raju Singh Tavarag 2 0.020 LHS S/o Rana Squatter Commercial Kutcha 6.25 6.25 100.00 ere Singh Matti Tavarag Basavaraja 3 0.022 LHS Squatter Commercial Kutcha 2.25 2.25 100.00 ere S/o Pampanna Tavarag Sabuddin S/o 4 0.024 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 ere Hucchusab

Tavarag Ganesh S/o 5 0.026 LHS Squatter Residential Kutcha 12.00 12.00 100.00 ere Nagappa Shyamanna Tavarag 6 0.080 RHS S/o Squatter Commercial Kutcha 3.00 6.00 50.00 ere Shyamanna Tavarag Vittal S/o 7 0.083 RHS Squatter Commercial Kutcha 4.50 6.00 75.00 ere Mallappa Yamanagowd Tavarag a S/o Hire 8 0.090 RHS Squatter Commercial Kutcha 1.00 4.00 25.00 ere Yamanagowd a Tavarag Mallikarjuna 9 0.100 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 ere S/o Veeraiah Sharadhamm Tavarag 10 0.110 RHS a W/o Squatter Commercial Kutcha 6.00 15.00 40.00 ere Tippanna Shyamamma Tavarag W/o 11 0.114 RHS Squatter Commercial Kutcha 4.50 6.00 75.00 ere Hanumanthap pa Noorjaan Tavarag 12 0.117 RHS Begum W/o Squatter Commercial Kutcha 6.00 18.00 33.33 ere Husainsab Tavarag Nagubai W/o 13 0.120 RHS Squatter Commercial Kutcha 6.00 18.00 33.33 ere Venkatasingh 115

% of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Tavarag Huligeppa S/o 14 0.190 RHS Squatter Residential Kutcha 1.50 9.00 16.67 ere Yamanappa

Tavarag Husainsab S/o 15 0.196 LHS Squatter Commercial Kutcha 2.25 2.25 100.00 ere Husainsab Tavarag Shyamanna 16 0.198 RHS Squatter Commercial Kutcha 2.25 2.25 100.00 ere Gunduru Tavarag Husainsab S/o 17 0.202 RHS Squatter Commercial Kutcha 4.00 4.00 100.00 ere Husainsab Linganagowda Tavarag Legal 18 0.220 RHS S/o Commercial Kutcha 3.00 12.00 25.00 ere Tenant Vittobagowda Linganagowda Tavarag Legal 19 0.225 RHS S/o Commercial Kutcha 2.00 12.00 16.67 ere Tenant Vittobagowda Tavarag Alibaba S/o 20 0.250 RHS Squatter Commercial Kutcha 4.00 16.00 25.00 ere Nabisab Pundalika Tavarag Gowdru S/o Legal 21 0.292 LHS Commercial Kutcha 2.00 4.00 50.00 ere Vittala Tenant Gowdru Pundalika Tavarag Gowdru S/o 22 0.298 LHS Squatter Commercial Kutcha 2.25 2.25 100.00 ere Vittala Gowdru Syedpasha Tavarag 23 0.302 RHS S/o Syed Squatter Commercial Kutcha 4.50 15.00 30.00 ere Nabisab Tavarag Renamma 24 0.426 LHS Owner Residential Kutcha 3.50 21.00 16.67 ere W/o Ramanna

Tavarag Bhimanna S/o 25 0.454 RHS Squatter Commercial Kutcha 4.00 4.00 100.00 ere Rajappa Chandrashekh Tavarag 26 0.485 RHS araiah S/o Owner Commercial Kutcha 41.20 64.00 64.38 ere Veeraiah Gopalappa Tavarag Legal 27 0.503 RHS S/o Yankanna Commercial Kutcha 10.00 25.00 40.00 ere Tenant Daroji Tavarag Prabhakar S/o Legal 28 0.505 LHS Commercial Kutcha 4.00 4.00 100.00 ere Sharanappa Tenant Gopala S/o Tavarag Legal 29 0.515 RHS Yankanna Commercial Kutcha 2.25 2.25 100.00 ere Tenant Daroji Tavarag Virupanna S/o 30 0.515 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 ere Basappa Dodda Tavarag 31 0.517 RHS Basappa S/o Squatter Commercial Kutcha 2.25 2.25 100.00 ere Doddappa Narayanasing Tavarag 32 0.523 RHS h S/o Owner Residential Kutcha 18.00 18.00 100.00 ere Makramsingh Mehaboobsab Tavarag 33 0.624 LHS S/o Squatter Commercial Kutcha 6.00 9.00 66.67 ere Mruthujasab Mahanthaiah Tavarag S/o 34 0.735 LHS Squatter Commercial Kutcha 2.25 2.25 100.00 ere Veerabhadrai ah

116

% of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Tavarag 35 0.738 LHS Krishnappa Squatter Commercial Kutcha 8.00 12.00 66.67 ere Basavanagow Tavarag da S/o 36 0.882 LHS Owner Residential Kutcha 24.00 24.00 100.00 ere Pampanagow da Tavarag Somashekhar 37 1.040 RHS Squatter Commercial Kutcha 8.40 12.00 70.00 ere S/o Balappa

Tavarag Shankrappa 38 1.130 LHS Squatter Commercial Kutcha 3.00 12.00 25.00 ere S/o Ningappa

Tavarag Shankrappa 39 1.154 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 ere S/o Ningappa

Tavarag Mahadevappa 40 1.160 RHS Squatter Commercial Kutcha 4.00 4.00 100.00 ere S/o Siddappa Rajaramsingh Menada 41 4.585 RHS S/o Squatter Commercial Kutcha 2.25 2.25 100.00 l Tukaramsingh Ramesha S/o Menada 42 4.998 RHS Venkateshach Squatter Commercial Kutcha 4.00 4.00 100.00 l arya Channabasav Menada 43 5.000 LHS a S/o Squatter Commercial Kutcha 2.00 4.00 50.00 l Huligeppa Menada Babusab S/o Residential/C 44 5.033 RHS Owner Kutcha 10.00 30.00 33.33 l Sulemansab ommercial Shankrappa Menada 45 5.053 RHS S/o Owner Commercial Kutcha 3.00 9.00 33.33 l Somalingappa Mehaboob S/o Menada 46 5.503 RHS Budansab Squatter Commercial Kutcha 4.00 4.00 100.00 l sunkad Hulihyd Tippanna S/o 47 9.140 LHS Owner Residential Kutcha 5.00 20.00 25.00 ara Mudukappa

Hulihyd Siddappa S/o 48 11.890 RHS Owner Residential Kutcha 28.00 28.00 100.00 ara Yamanappa Kanakachala Hulihyd 49 11.910 RHS Rao S/o Owner Residential Pucca 20.00 80.00 25.00 ara Ranga Rao Hulihyd Husainsab S/o 50 12.040 RHS Squatter Commercial Kutcha 16.00 16.00 100.00 ara Maliksab Durgappa S/o Hulihyd 51 12.060 LHS Hanumanthap Owner Residential Kutcha 2.40 24.00 10.00 ara pa Hulihyd Amareshappa 52 12.078 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 ara Shetty Gramapanchy Hulihyd Legal 53 12.094 LHS ath Malige, Commercial Pucca 2.25 9.00 25.00 ara Tenant Hulihydara Eshappagowd Hulihyd a S/o 54 12.097 LHS Squatter Commercial Kutcha 2.00 4.00 50.00 ara Ambannagow da Hulihyd Mahesh S/o 55 12.109 RHS Squatter Commercial Kutcha 2.25 2.25 100.00 ara Sharanappa 117

% of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Hulihyd Maruthiyappa 56 12.110 LHS Squatter Commercial Kutcha 1.00 4.00 25.00 ara S/o Rajappa Pundalika S/o Hulihyd 57 12.114 LHS Pampanagow Squatter Commercial Kutcha 1.00 4.00 25.00 ara da Vasantha Hulihyd Semi 58 12.115 RHS Shetty S/o Owner Residential 8.00 40.00 20.00 ara Pucca Somanna Nagappa S/o Hulihyd 59 12.117 LHS Virupakshapp Squatter Commercial Kutcha 2.00 4.00 50.00 ara a Narayanaswa Hulihyd my S/o 60 12.125 LHS Squatter Commercial Kutcha 2.00 4.00 50.00 ara Kabbaiah Shetty Hulihyd Manappa S/o 61 12.142 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 ara Naganna Hanumesh Hulihyd (O) 62 12.146 RHS Naik S/o Owner Kutcha 11.00 22.00 50.00 ara Projection Manappa Naik Hulihyd Nagappa S/o 63 12.250 RHS Squatter Commercial Kutcha 2.00 4.00 50.00 ara Mariyappa Hanumanthap Hulihyd 64 12.278 RHS pa S/o Squatter Commercial Kutcha 2.00 4.00 50.00 ara Yamunappa Hulihyd Sangama W/o Semi 65 12.355 RHS Squatter Commercial 12.00 24.00 50.00 ara Shivappa Pucca Nagappa S/o Hulihyd 66 12.368 RHS Hotte Owner Residential Kutcha 12.00 24.00 50.00 ara Hanumappa Hulihyd Sriram S/o (O) Semi 67 12.380 RHS Owner 10.00 50.00 20.00 ara Ranganna Projection Pucca

Hulihyd Hanumesh Semi 68 12.415 RHS Owner Residential 28.00 48.00 58.33 ara S/o Mallappa Pucca

Hulihyd Durgappa S/o Semi 69 13.875 RHS Owner Residential 8.00 24.00 33.33 ara Durgappa Pucca

Kanaka Manjappa S/o 70 16.823 RHS Squatter Commercial Kutcha 24.00 36.00 66.67 pura Manappa

Kanaka Kalappa S/o 71 16.826 RHS Squatter Commercial Kutcha 4.00 4.00 100.00 pura Manappa

Kanaka Manjappa S/o Semi 72 16.885 LHS Owner Residential 16.00 32.00 50.00 pura Manappa Pucca

Kanaka Azia S/o Semi 73 22.155 RHS Squatter Commercial 81.00 81.00 100.00 giri Mardansab Pucca

Kanaka Shamanna (O) 74 22.210 LHS Owner Kutcha 13.00 117.00 11.11 giri Chimpagi Projection Huligemma Kanaka 75 22.217 RHS W/o Squatter Residential Kutcha 7.50 15.00 50.00 giri Husenappa Kanaka Ningavva W/o Semi 76 22.225 RHS Squatter Commercial 40.00 160.00 25.00 giri Hanumanth Pucca

118

% of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Hasanbee Kanaka Semi 77 22.232 RHS Begum W/o Squatter Residential 12.00 12.00 100.00 giri Pucca Valisab Kanaka Shameedsab Semi 78 22.236 RHS Squatter Residential 20.00 20.00 100.00 giri S/o Khajasab Pucca

Kanaka Suresh S/o Semi 79 22.241 RHS Squatter Commercial 27.00 27.00 100.00 giri Shanmukha Pucca

Kanaka Somanna S/o 80 22.265 RHS Squatter Residential Kutcha 15.00 15.00 100.00 giri Yamunappa Kanaka 81 22.270 RHS Kanakappa Squatter Commercial Kutcha 4.00 4.00 100.00 giri Rukayya Kanaka Residential/C 82 22.270 RHS Begum W/o Squatter Kutcha 60.00 60.00 100.00 giri ommercial Mehaboobsab Anand Reddy Kanaka 83 22.274 LHS S/o Palaksha Squatter Commercial Kutcha 6.00 16.00 37.50 giri Reddy Janardhana Kanaka Reddy S/o 84 22.290 RHS Squatter Commercial Kutcha 40.00 40.00 100.00 giri Venkata Reddy Kanaka Yamanursab 85 22.298 RHS Squatter Commercial Kutcha 6.00 6.00 100.00 giri S/o Imamsab

Kanaka Mehaboobsab 86 22.301 RHS Squatter Commercial Kutcha 4.00 4.00 100.00 giri S/o Rajasab

Kanaka M Ramesh 87 22.308 RHS Squatter Commercial Kutcha 12.50 12.50 100.00 giri and Brothers

Kanaka Harish S/o Semi 88 22.314 RHS Squatter Commercial 45.00 45.00 100.00 giri Hulagappa Pucca Shivamma Kanaka 89 22.327 RHS W/o Squatter Residential Kutcha 20.00 20.00 100.00 giri Husenappa Kanaka Prakasha S/o 90 22.345 RHS Squatter Commercial Kutcha 4.00 4.00 100.00 giri Ramanna Kanaka 91 22.349 RHS Honnursab Squatter Commercial Kutcha 4.00 4.00 100.00 giri Kanaka Ramanna 92 22.380 RHS Squatter Commercial Kutcha 4.00 4.00 100.00 giri Naik Chandusab Kanaka 93 22.382 RHS Gurikara S/o Squatter Commercial Kutcha 12.00 12.00 100.00 giri Hasansab Kanaka Karimsab S/o 94 22.386 RHS Squatter Commercial Kutcha 4.00 4.00 100.00 giri Allasab Ramanna S/o Kanaka 95 22.401 RHS Chidanandapp Squatter Commercial Kutcha 9.00 15.00 60.00 giri a Kanaka Khadarpasha 96 22.404 RHS Squatter Commercial Kutcha 6.90 15.00 46.00 giri S/o Jaffarsab Vishwanatha Kanaka Reddy S/o 97 22.407 RHS Squatter Commercial Kutcha 7.50 15.00 50.00 giri Kanaka Reddy Kanaka Murthujasab 98 22.410 RHS Squatter Commercial Kutcha 7.50 15.00 50.00 giri S/o Razaksab 119

% of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Kanaka Ghulamsab 99 22.415 RHS Squatter Commercial Kutcha 7.50 25.00 30.00 giri S/o Khajasab

Kanaka Ramesh S/o 100 22.415 RHS Squatter Commercial Kutcha 2.25 2.25 100.00 giri Husenappa Abdul Ghani Kanaka 101 22.425 RHS S/o Squatter Commercial Kutcha 3.00 4.00 75.00 giri Mahaboobsab Kanaka Rajasab S/o 102 22.427 RHS Squatter Commercial Kutcha 7.50 25.00 30.00 giri Khadarsab

Kanaka Dadapeer S/o 103 22.435 RHS Squatter Commercial Kutcha 4.00 4.00 100.00 giri Husainsab

Kanaka Khajasab S/o 104 22.861 RHS Squatter Commercial Kutcha 1.25 6.25 20.00 giri Karimsab

Kanaka Bashasab S/o 105 22.865 RHS Squatter Commercial Kutcha 2.00 4.00 50.00 giri Imamsab

Kanaka Shabbir S/o 106 22.885 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 giri Budensab

Kanaka Mallikarjuna 107 22.910 LHS Squatter Commercial Kutcha 1.00 4.00 25.00 giri S/o Shivappa

Kanaka Honnamma 108 22.913 LHS Squatter Residential Kutcha 1.00 6.00 16.67 giri W/o Ayyappa Sharanappa Kanaka 109 22.970 RHS S/o Squatter Commercial Kutcha 24.00 24.00 100.00 giri Chandrappa Kanaka Imamsab S/o Residential/C Semi 110 23.170 LHS Owner 24.50 60.00 40.83 giri Husainsab ommercial Pucca

Kanaka Honnursab 111 23.202 LHS Owner Residential Pucca 5.00 32.00 15.63 giri S/o Rajasab Shameedsab Kanaka 112 23.260 LHS S/o Squatter Commercial Kutcha 3.00 4.00 75.00 giri Hucchusab Basanna S/o Kanaka 113 23.272 RHS Hanumanthap Squatter Commercial Kutcha 10.00 24.00 41.67 giri pa Kanaka Pamanna S/o 114 23.275 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 giri Mallappa

Kanaka Veerpadi S/o 115 23.300 RHS Squatter Commercial Kutcha 2.40 4.00 60.00 giri Kantyappa

Kanaka Dharmappa 116 23.306 RHS Squatter Commercial Kutcha 4.00 4.00 100.00 giri S/o Hulgappa

Kanaka Razia W/o 117 23.308 RHS Squatter Commercial Kutcha 14.00 35.00 40.00 giri Rajahusain Thimmanna Kanaka 118 23.316 RHS S/o Squatter Commercial Kutcha 4.00 4.00 100.00 giri Thimmappa Kanaka Hanumanthap Semi 119 23.492 RHS Squatter Commercial 5.60 32.00 17.50 giri pa S/o Erappa Pucca

Kanaka Gudusab S/o 120 24.155 RHS Squatter Commercial Kutcha 8.00 16.00 50.00 giri Miyasab

120

% of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Kanaka Ramanna S/o 121 24.410 RHS Squatter Cattle Shed Kutcha 9.00 9.00 100.00 giri Manappa Gangadhara Kanaka (O) 122 24.605 LHS S/o Owner Kutcha 20.40 24.00 85.00 giri Projection Hampanna Saleem Pasha Kanaka S/o 123 24.898 RHS Owner Commercial Kutcha 16.00 32.00 50.00 giri Mohammadsa b Hanumanthap Tippana 124 26.320 RHS pa S/o Squatter Commercial Kutcha 12.00 24.00 50.00 l Cross Mariyappa Kesara Vishwanatha 125 30.732 LHS Owner Residential Kutcha 20.00 40.00 50.00 hatti S/o Nagappa Pampaiahswa Aralihall 126 31.794 RHS my S/o Squatter Commercial Kutcha 28.00 28.00 100.00 i Mallaiah Aralihall Nagaraj S/o 127 31.808 RHS Squatter Commercial Kutcha 28.00 28.00 100.00 i Eshappa

Kesara Ramalingappa Boundary 128 34.043 LHS Owner Pucca 10.00 10.00 100.00 hatti S/o Rudrappa Wall Shekharappa Kesara 129 34.110 RHS S/o Squatter Commercial Kutcha 2.40 9.00 26.67 hatti Venkareddy Sharanaiahsw Kesara amy S/o 130 34.128 RHS Squatter Commercial Kutcha 1.50 9.00 16.67 hatti Ramalingiahs wamy Channabasav Kesara 131 34.132 RHS a S/o Squatter Commercial Kutcha 1.00 4.00 25.00 hatti Veerappa Kesara Kumara S/o 132 34.136 RHS Squatter Commercial Kutcha 1.00 4.00 25.00 hatti Anandrao

Kesara Buddappa S/o 133 34.140 RHS Squatter Commercial Kutcha 1.00 4.00 25.00 hatti Honnurusab Sakkaragowd Kesara 134 34.152 LHS a S/o Squatter Commercial Kutcha 1.60 4.00 40.00 hatti Rudragowda Kesara Nagappa S/o 135 34.154 RHS Squatter Commercial Kutcha 1.00 6.00 16.67 hatti Thimmanna Kesara 136 34.167 RHS Atalsab Squatter Commercial Kutcha 2.25 2.25 100.00 hatti Basavaraj S/o Kesara Legal 137 34.169 RHS Mallikarjun Commercial Kutcha 2.50 6.25 40.00 hatti Tenant Desai Basavaraju Kesara 138 34.172 RHS S/o Squatter Commercial Kutcha 1.50 9.00 16.67 hatti Mallikarjun Kesara Yamanuru S/o 139 34.173 RHS Squatter Commercial Kutcha 4.00 6.00 66.67 hatti Shankrappa Hanuma Kesara 140 34.180 RHS Reddy S/o Squatter Commercial Kutcha 4.00 4.00 100.00 hatti Lakshmappa Lingana Kesara 141 34.183 RHS Gowda S/o Squatter Commercial Kutcha 4.00 4.00 100.00 hatti Basanagowda 121

% of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Kesara Nagesh S/o 142 34.183 LHS Squatter Commercial Kutcha 1.00 4.00 25.00 hatti Linganagowda

Kesara Rudrappa S/o 143 34.192 RHS Squatter Commercial Kutcha 4.00 4.00 100.00 hatti Mudukappa

Kesara Malleshappa 144 34.196 RHS Squatter Commercial Kutcha 3.00 4.00 75.00 hatti S/o Kalakappa Lingaiahswam Kesara y S/o 145 34.200 RHS Squatter Commercial Kutcha 2.25 2.25 100.00 hatti Shankraiahsw amy Kesara Yamanura S/o 146 34.204 RHS Squatter Commercial Kutcha 2.25 2.25 100.00 hatti Erappa Veerabhadrag Kesara 147 34.206 RHS owda S/o Squatter Commercial Kutcha 4.00 4.00 100.00 hatti Linganagowda Veeranagowd Kesara a S/o 148 34.211 RHS Squatter Commercial Kutcha 3.00 4.00 75.00 hatti Shekharagow da Kesara Sharanappa 149 34.215 LHS Squatter Commercial Kutcha 1.40 4.00 35.00 hatti S/o Devappa

Kesara Veerappa S/o 150 34.220 LHS Owner Commercial Kutcha 7.60 32.00 23.75 hatti Doddappa Siddanagowd Kesara a S/o 151 34.225 RHS Owner Residential Pucca 1.35 30.00 4.50 hatti Pampanagow da Kesara 152 34.228 LHS Ramesh Owner Residential Pucca 9.75 30.00 32.50 hatti Siddanagowd Kesara a S/o (O) 153 34.233 RHS Owner Kutcha 1.80 30.00 6.00 hatti Pampanagow Projection da Basavaraja Kesara S/o 154 34.233 LHS Owner Residential Pucca 1.65 30.00 5.50 hatti Virupakshigow da Balamma W/o Kesara (O) 155 34.250 RHS Hanumanthap Owner Kutcha 13.20 60.00 22.00 hatti Projection pa Kesara Basamma 156 34.253 LHS Squatter Commercial Kutcha 1.00 4.00 25.00 hatti W/o Mallanna Pampapathi Kesara S/o 157 34.300 RHS Owner Residential Kutcha 3.75 50.00 7.50 hatti Nagareddapp a Bhimanagowd Kesara a S/o 158 34.320 RHS Owner Residential Pucca 21.45 130.00 16.50 hatti Rudranagowd a Shivareddapp Kesara 159 34.335 RHS a S/o Owner Residential Pucca 11.55 70.00 16.50 hatti Ramalingappa Kesara Ramalingappa 160 34.350 RHS Owner Residential Pucca 6.00 48.00 12.50 hatti S/o Rudrappa

122

% of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Kesara Karibasappa 161 34.360 RHS Owner Residential Pucca 22.40 112.00 20.00 hatti S/o Siddappa

Kesara Huligemma 162 34.440 RHS Owner Residential Kutcha 15.75 49.00 32.14 hatti D/o Lingappa

Kesara Durgamma 163 34.447 RHS Owner Residential Kutcha 15.75 49.00 32.14 hatti W/o Erappa

Kesara Durgamma 164 34.465 RHS Owner Residential Kutcha 24.00 24.00 100.00 hatti D/o Erappa

Kesara Durgappa S/o 165 34.475 RHS Owner Residential Kutcha 15.00 15.00 100.00 hatti Erappa Yamanurappa Kesara 166 34.485 RHS S/o Owner Residential Pucca 27.50 40.00 68.75 hatti Mariyamma Kesara Balappa S/o Semi 167 34.492 RHS Owner Residential 10.50 18.00 58.33 hatti Kanakappa Pucca

Kesara Galeppa S/o 168 34.502 RHS Owner Residential Pucca 20.10 48.00 41.88 hatti Ningamma

Kesara Nagappa S/o 169 34.508 RHS Owner Residential Kutcha 12.00 18.00 66.67 hatti Sannamma

Kesara Yamunappa Semi 170 34.516 RHS Owner Residential 17.60 24.00 73.33 hatti S/o Sannappa Pucca

Kesara Rajappa S/o Semi 171 34.553 RHS Owner Residential 10.50 24.00 43.75 hatti Sannappa Pucca

Kesara Ningappa S/o Semi 172 34.561 RHS Owner Residential 24.00 24.00 100.00 hatti Sannappa Pucca

Kesara Bhimappa S/o 173 34.574 RHS Owner Residential Kutcha 24.00 24.00 100.00 hatti Parasappa

Kesara Veeresh S/o 174 34.690 LHS Owner Residential Pucca 9.60 120.00 8.00 hatti Mallaiah Mallikarjun Gowda S/o 175 36.330 LHS Herur Owner Residential Pucca 8.40 40.00 21.00 Muddanna Gowda Shekhargowd a S/o 176 36.333 RHS Herur Owner Residential Pucca 3.00 16.00 18.75 Pampanagow da Channabasav 177 36.349 LHS Herur a S/o Squatter Residential Kutcha 2.50 12.50 20.00 Hoovanna Pampanagow 178 36.380 LHS Herur Owner Residential Pucca 6.40 20.00 32.00 da Nagappa S/o Residential/C 179 36.385 RHS Herur Owner Pucca 17.80 32.00 55.63 Vaggappa ommercial

Virupanna S/o 180 36.389 RHS Herur Owner Residential Pucca 23.10 66.00 35.00 Ayyappa Lakshmi Reddy S/o Semi 181 36.389 LHS Herur Owner Commercial 3.40 20.00 17.00 Hire Pucca Ayyanagowda 123

% of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Manjunatha 182 36.400 LHS Herur S/o Squatter Commercial Kutcha 2.25 2.25 100.00 Gurubasappa Basappa S/o 183 36.403 RHS Herur Squatter Commercial Kutcha 0.75 2.25 33.33 Pampapathi

Hasansab S/o Legal 184 36.403 LHS Herur Commercial Kutcha 3.00 18.00 16.67 Husainsab Tenant Chennappa Naik S/o Residential,B Semi 185 36.405 RHS Herur Owner 2.50 20.00 12.50 Ambanna oundary Wall Pucca Naik Semi 186 36.405 LHS Herur Umapathi Owner Residential 3.40 24.00 14.17 Pucca Gramapancha Legal 187 36.420 RHS Herur Commercial Pucca 2.25 15.00 15.00 yath Tenant Gramapanchy Legal 188 36.423 RHS Herur Commercial Pucca 1.50 15.00 10.00 ath Tenant Boraiah Legal Semi 189 36.427 RHS Herur Commercial 1.40 20.00 7.00 Hiremath Tenant Pucca

Ramesh S/o 190 36.450 RHS Herur Squatter Commercial Kutcha 1.00 4.00 25.00 Husenappa

Hasansab S/o 191 36.450 LHS Herur Owner Residential Kutcha 4.40 20.00 22.00 Husainsab

Kantibasappa Legal 192 36.455 LHS Herur Commercial Kutcha 5.00 20.00 25.00 S/o Dandeppa Tenant

Shivappa S/o Legal 193 36.460 RHS Herur Channabasav Commercial Kutcha 7.50 36.00 20.83 Tenant ana Gowda

194 36.467 RHS Herur Ramesha Squatter Commercial Kutcha 2.25 2.25 100.00 Veerappa S/o 195 36.478 RHS Herur Squatter Commercial Kutcha 1.20 2.25 53.33 Parappa Sharanappa 196 36.480 LHS Herur S/o Squatter Commercial Kutcha 2.25 2.25 100.00 Pampanna Shankrappa 197 36.492 RHS Herur S/o Squatter Commercial Kutcha 1.50 2.25 66.67 Mudukappa Amaresha S/o 198 36.512 RHS Herur Squatter Commercial Kutcha 1.50 2.25 66.67 Siddappa

Nazeer S/o 199 36.518 RHS Herur Squatter Commercial Kutcha 1.50 2.25 66.67 Marthujasab

Mahanthesh 200 36.555 RHS Herur Squatter Commercial Kutcha 1.00 4.00 25.00 S/o Amarappa 201 36.650 LHS Herur Junappa Squatter Commercial Kutcha 2.25 2.25 100.00 Hanumantha 202 36.655 RHS Herur S/o Squatter Residential Kutcha 4.00 12.00 33.33 Savareppa Ramesh S/o 203 36.655 LHS Herur Hanumanthap Squatter Commercial Kutcha 2.60 4.00 65.00 pa

124

% of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Shekharaiah S/o 204 36.660 RHS Herur Squatter Commercial Kutcha 3.00 9.00 33.33 Basaiahswam y Pampanna 205 36.673 LHS Herur Owner Residential Kutcha 3.00 4.00 75.00 S/o Siddappa

Mabusab S/o 206 36.703 RHS Herur Squatter Commercial Kutcha 4.00 24.00 16.67 Mruthyusab

Akbarsab S/o 207 36.704 RHS Herur Squatter Commercial Kutcha 3.00 16.00 18.75 Fakeersab 208 36.720 LHS Herur Kasimali Squatter Commercial Kutcha 4.00 4.00 100.00 Husain S/o 209 36.724 LHS Herur Squatter Commercial Kutcha 1.00 4.00 25.00 Muktumsab Reddy Soda 210 36.730 RHS Herur Squatter Commercial Kutcha 2.00 4.00 50.00 Shop Subramanya 211 36.733 RHS Herur S/o Squatter Commercial Kutcha 5.00 10.00 50.00 Ramakrishna Shammau S/o (O) 212 36.738 RHS Herur Squatter Kutcha 4.00 8.00 50.00 Mabusab Projection 213 36.775 RHS Herur Call Refused Owner Commercial Kutcha 15.00 20.00 75.00 Kotrappa S/o 214 36.815 LHS Herur Squatter Commercial Kutcha 1.50 2.25 66.67 Kotrappa Parvathamma W/o 215 36.823 LHS Herur Squatter Commercial Kutcha 1.50 2.25 66.67 Veeraiahswa my Sharanayya 216 36.850 LHS Herur Squatter Commercial Kutcha 2.00 4.00 50.00 S/o Basayya 217 36.918 RHS Herur Yamunappa Squatter Residential Kutcha 12.00 12.00 100.00 Kesara Ramanna S/o 218 37.454 RHS Owner Residential Kutcha 28.00 28.00 100.00 hatti Erappa Thimmanna Gonaha 219 38.895 LHS S/o Squatter Commercial Kutcha 3.00 4.00 75.00 lli Venkareddy Galem Mallamma 220 40.080 LHS ma W/o Squatter Commercial Kutcha 16.00 20.00 80.00 Camp Hanumanth Galem Honnurubee 221 40.080 LHS ma Squatter Residential Kutcha 20.00 20.00 100.00 W/o Kasimsab Camp Galem Danelappa 222 40.105 LHS ma Squatter Cattle Shed Kutcha 22.50 25.00 90.00 S/o Kariyappa Camp Galem Rangamma Residential/C 223 40.125 LHS ma Squatter Kutcha 96.00 96.00 100.00 W/o Anjaneya ommercial Camp Galem Prabhavathi 224 40.150 RHS ma Squatter Commercial Kutcha 4.00 4.00 100.00 D/o Basappa Camp Galem Venkatesha 225 40.160 RHS ma Squatter Commercial Kutcha 4.00 4.00 100.00 S/o Tikkanna Camp 125

% of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Galem Yamunamma Residential/C 226 40.195 RHS ma W/o Squatter Kutcha 32.50 45.00 72.22 ommercial Camp Shankrappa Galem Annapurnam 227 40.345 LHS ma ma W/o Squatter Commercial Kutcha 4.00 4.00 100.00 Camp Nagaraja Galem 228 40.360 LHS ma Danaiah Squatter Commercial Kutcha 2.00 4.00 50.00 Camp Galem Jilan S/o 229 40.363 RHS ma Squatter Commercial Kutcha 12.00 12.00 100.00 Salamsab Camp Galem 230 40.366 RHS ma Ashok Squatter Commercial Kutcha 16.00 16.00 100.00 Camp Galem 231 40.370 LHS ma Reddy Squatter Commercial Kutcha 2.25 2.25 100.00 Camp Galem Sharanappa 232 40.372 RHS ma Squatter Commercial Kutcha 4.00 4.00 100.00 S/o Amarappa Camp Gangav Basavaraj S/o 233 40.780 RHS Squatter Commercial Kutcha 6.00 36.00 16.67 athi Balanagowda Venkataraman Gangav 234 40.835 RHS a S/o Squatter Commercial Kutcha 2.00 4.00 50.00 athi Gangaiah Ambamma Gangav W/o 235 40.850 RHS Squatter Commercial Kutcha 2.00 4.00 50.00 athi Hanumanthap pa Gangav Mallamma 236 40.860 RHS Squatter Commercial Kutcha 8.00 16.00 50.00 athi W/o Nagappa Hanumanthap Gangav 237 41.660 RHS pa S/o Squatter Commercial Kutcha 16.00 16.00 100.00 athi Kallappa Gangav Husainsab S/o 238 42.055 LHS Squatter Commercial Kutcha 2.25 2.25 100.00 athi Ameensab

Gangav Municipality Legal Semi 239 42.890 RHS Commercial 3.00 4.00 75.00 athi Complex Tenant Pucca

Gangav Moulasab S/o 240 42.890 LHS Squatter Commercial Kutcha 4.00 4.00 100.00 athi Imamsab

Corporation Gangav Legal Semi 241 42.894 RHS Commercial Commercial 3.00 4.00 75.00 athi Tenant Pucca Complex

Gangav Corporation Legal Semi 242 42.898 RHS Commercial 3.00 4.00 75.00 athi Complex Tenant Pucca

Gangav Corporation Legal Semi 243 42.900 RHS Commercial 3.00 4.00 75.00 athi Complex Tenant Pucca

Gangav Corporation Legal Semi 244 42.902 RHS Commercial 3.00 4.00 75.00 athi Complex Tenant Pucca

Gangav Municipality Legal Semi 245 42.904 RHS Commercial 3.00 4.00 75.00 athi Complex Tenant Pucca

Gangav Municipality Legal Semi 246 42.906 RHS Commercial 3.00 4.00 75.00 athi Complex Tenant Pucca

126

% of Str. Total Str. Affecte Str. Sl. Chaina Occu. Structu Gettin Side Village Name Loss Type d Area Area No. ge Status re Type g (in Sq (in Sq Affect m) m) ed Gangav Municipality Legal Semi 247 42.908 RHS Commercial 3.00 4.00 75.00 athi Complex Tenant Pucca

Gangav Municipality Semi 248 42.910 RHS Squatter Commercial 3.00 4.00 75.00 athi Complex Pucca

Gangav Municipality Legal Semi 249 42.912 RHS Commercial 3.00 4.00 75.00 athi Complex Tenant Pucca

Gangav Municipality Legal Semi 250 42.914 RHS Commercial 3.00 4.00 75.00 athi Complex Tenant Pucca

Gangav Municipality Legal Semi 251 42.916 RHS Commercial 3.00 4.00 75.00 athi Complex Tenant Pucca

Gangav Municipality Legal Semi 252 42.918 RHS Commercial 3.00 4.00 75.00 athi Complex Tenant Pucca

Gangav Municipality Legal Semi 253 42.920 RHS Commercial 3.00 4.00 75.00 athi Complex Tenant Pucca

Municipality Gangav Legal Semi 254 42.922 RHS Complex, Commercial 3.00 4.00 75.00 athi Tenant Pucca Gangavathi

Municipality Gangav Legal Semi 255 42.924 RHS Complex, Commercial 3.00 4.00 75.00 athi Tenant Pucca Gangavathi

Municipality Gangav Legal Semi 256 42.926 RHS Complex, Commercial 3.00 4.00 75.00 athi Tenant Pucca Gangavathi

Municipality Gangav Legal Semi 257 42.928 RHS Complex, Commercial 3.00 4.00 75.00 athi Tenant Pucca Gangavathi

Municipality Gangav Legal Semi 258 42.930 RHS Complex, Commercial 3.00 4.00 75.00 athi Tenant Pucca Gangavathi

Municipality Gangav Legal Semi 259 42.932 RHS Complex, Commercial 3.00 4.00 75.00 athi Tenant Pucca Gangavathi

Municipality Gangav Legal Semi 260 42.935 RHS Complex, Commercial 3.00 4.00 75.00 athi Tenant Pucca Gangavathi

Municipality Gangav Legal Semi 261 42.937 RHS Complex, Commercial 3.00 4.00 75.00 athi Tenant Pucca Gangavathi

Municipality Gangav Legal Semi 262 42.939 RHS Complex, Commercial 3.00 4.00 75.00 athi Tenant Pucca Gangavathi

127

Annex 6 : List of Participants for Meeting – 31A

128

129

130

Annex 6 :List of Participants for Meeting – 31B

131

132

133

134

Consultation Meetings

Meeting at Nagalapura village on 05.07.2010 – Meeting at Nagalapura village on 05.07.2010 Link 31A – Link 31A

Meeting at Herur village on 05.07.2010 – Link Meeting at Herur village on 05.07.2010 – 31B Link 31B

135

Annex 7 TERMS OF REFERENCE FOR NGO CONSULTANCY FOR IMPLEMENTATION OF RESETTLEMENT PLAN I. BACKGROUND OF THE PROJECT 1. The aim of the project is to improve the performance of the State's road transport sector. The KSHIP Stage I roads have been selected based on the Feasibility Study of State Roads for proposed KSHIP. The PWD has carried out a Poverty and Social Assessment study for 633 km of roads and prepared a Resettlement Plan . Keeping in view the impact to the people due to the implementation of the project, the PIU will require to appropriately resettle and rehabilitate the DPs in accordance with the RP proposed for the purpose. For the implementation of the RP, the PIU will require to appoint local NGO who not only have the experience in carrying out such activities, but also have a better access with the people at the grassroots for effective implementation. II. TASKS 2. The NGO shall play a role of secondary stakeholder in implementation of the RP and in mitigating the adverse effects of the project. The NGO shall remain responsible for the development of a comprehensive livelihood system to facilitate the project affected persons DPs to take advantages of the options available as per the RP. The NGO shall assist PWD in ensuring social responsibilities of the KSHIP, such as, compliance with labour laws, prohibition of child labour, HIV/AIDS and gender issues. The main tasks of the NGO thus appointed will be: 1. Verification 3. All Verification has to be conducted jointly with local SDRC offices: 4. (i) The NGO shall undertake joint verification of the project affected persons and shall update the database on the eligible DPs and Displaced households (DHs). The NGO shall verify the information already contained in the RP and the individual losses of the DPs and validate the same and make suitable changes if required. 5. (ii) During the identification and verification of the eligible DPs/DHs, the NGO shall ensure that each of the DPs are contacted and consulted. The NGO shall ensure consultation with the women from the DP households especially women-headed households. 6. (iii) Verification exercise shall include actual measurement of the extent of total property loss/damage, and valuation of the loss/damage/affect along with the SDO. The NGO shall display the list of eligible DPs in prominent public places like Panchayat Offices, Taluk and District Headquarters. 7. (iv) The NGO has to identify any DP, DH or community asset coming within the Right of Way after the cut-off date, and notify the same to the local SDRC office. The NGO shall through consultation remove the DP, DH or community structure from the ROW, and inform them that any project benefits do not apply to them.

136

2. Distribution of Identity Cards 8. After verification the NGO shall distribute Identity Cards to all Project affected persons. The identity card should include a photograph of the DP, the extent of loss suffered due to the project, and the choice of the DP with regard to the mode of compensation and assistance, with necessary household details. The Identity Cards are to be signed by the local Social Development office counter signed by the Assistant Director Social Welfare at PIU. 3. Consultation 9. The NGO shall educate the DPs on their rights, entitlements and obligations under the RP. It shall disseminate information to the DPs on the possible consequences of the project on the communities' livelihood systems and the options available, so that they do not remain ignorant. It shall explain to the DPs the need for land acquisition, the provisions of the policy and the entitlements under the RP. This shall include communication to the roadside squatters and encroachers about the need for their eviction, the timeframe for their removal and their entitlements as per the RP. 4. Prepare Micro Plan 10. The NGO shall prepare Micro plans indicating category of entitlement; alternate livelihood options; land identification; skill upgrading and institutions responsible for training. A separate plan has to be prepared for shifting of community assets. 5. Training and Support for income restoration 11. In addition to providing assistance given in the entitlement package, the NGO shall be responsible for training and assisting the DPs to establish linkages with government programmes. 12. The NGO shall train DPs losing their livelihood, in suitable income restoration programmes, depending on the skills and interest of the DPs. The NGO shall prepare individual Income Restoration Plan, as a part of the Micro Plan for all DPs whose livelihoods are getting affected. The NGO shall explore the potential of employment opportunities with the local contractors, and wherever possible ensure suitable employment with the contractors. This will include providing the list of people wiling to work under contractors and to facilitate these types of jobs to PDPs and local people; 13. NGO shall assist the DP to establish linkage with Financial institutions for facilitating access to credit. 14. Assist the DP to establish linkages with Government departments, district administration, etc., to ensure that the DPs are included in the development schemes, as applicable especially with reference to vulnerable groups such as pension schemes for Senior citizens, schemes for women for women-headed household households, widow pensions, schemes for physically challenged persons etc. 15. Link up DPs to Training institutes for imparting skill and management training for enterprise creation and development. For those DPs who are interested in skill upgrading or training for economic generation programmes. 137

6. Disbursement of Assistance and delivery of entitlements 16. The NGO shall ensure that DPs obtain their full entitlements under the RP; to ensure benefits due to the DPs under the R & R policy and RP are provided to the DPs. Where options are available, the NGO shall provide advice to DPs on the relative benefits of each option. 17. The NGO shall assist the project authorities in ensuring a smooth transition helping the DPs to take salvaged materials and shift with proper notices. In close consultation with the DPs, the NGO shall inform the SDRC about the shifting dates agreed with the DPs in writing and the arrangements desired by the DPs with respect to their entitlements. 18. The NGO shall assist the DPs in opening bank accounts explaining the implications, the rules and the obligations of a joint account and how he/she can access the resources s/he is entitled to. 19. Ensure proper utilization by the DPs of various grants available under the R & R package. The NGO will be responsible for advising the DPs on how best to use any cash that may be provided under the RP. Emphasis should be placed on using such funds in a sustainable way e.g. purchasing replacement land for that acquired 20. The NGO shall ensure proper utilisation of the R & R budget available for each of the packages. It shall identify means and advise the SDO to disburse the entitlements to the eligible persons/households in a transparent manner and shall report to the SDRC/PIU on the level of transparency achieved in the project. 7. Grievance Redressal 21. The NGO shall make DPs aware of the grievance mechanism set out in the RP and shall assist PDPs who have grievances to pursue a suitable remedy. The NGO shall help the DPs to file a grievance application. 22. The NGO shall record the grievance and bring the same to the notice of the Grievance Redressal Committees (GRC) within 7 (seven) days of receipt of the grievance from the DPs. It shall submit a draft resolution with respect to the particular grievance of the DP, suggesting solutions, if possible, and deliberate on the same in the GRC meeting through the NGO representative in the GRC. 23. The NGO shall assist in the GRC process when ever necessary. 8. Identification of sites 24. As part of the RP, eligible AFs will receive alternative sites for residential and commercial structures getting affected. The NGO will identify with PIU and the Revenue Department suitable government land and assist in negotiating its transfer to the DP. Where suitable government land is not available, the NGO will assist the DP to locate a land owner willing to sell his land and will assist in the negotiation of the purchase price. 25. The NGO has to identify the need for Resettlement Centres in consultation with the project affected persons, according to the R & R Policy. In case the need arises, the NGO shall identify suitable site for the same. The NGO will have to develop Self Help Groups and impact skill training to the affected persons.

138

9. Coordination between DPs and the SDRC 26. The NGO shall develop rapport between the DPs and the SDRC. This will be achieved through regular monthly meeting with both the SDRC representatives and the DPs. All meetings and decisions taken are to be documented. 10. Conduct Public information campaign 27. The NGO shall assist the SDRC to undertake public information campaign at the commencement of the project to inform the affected communities of the project RP, the R & R policy and the entitlement package. 11. Conduct Gram Sabhas 28. The NGO shall ensure that gram sabhas (village level meetings) are held in every village. Besides contacting DPs on an individual basis to regularly update the baseline information, Gram Sabhas will be conducted by the NGO on a regular basis. The frequency of such meetings will depend on the requirements of the DPs, to allow the PDPs to remain up to date on project developments. NGO will encourage participation of individual PDPs in such meetings by discussing their problems regarding LA, R & R and other aspects relating to their socioeconomic lives. Such participation will make it easier to find a solution acceptable to all involved. 12. Report the Status of PDPs after shifting 29. The NGO shall submit a status report of the PDPs after shifting to the SDRC. 13. Assist the PWD in Actions to HIV/AIDS Awareness/prevention Campaigns/Gender/Child Labour 30. Information campaign/advertisement in collaboration with line agencies (such as National AIDS Control Organisation, State AIDS Control Organisation etc.) including provision of signage/hoardings at suitable locations, distribution of vechicle stickers and provision of condom vending machines at suitable locations (rest areas, truck parking lay-byes etc. The Ngo shall assist the PWD to implement these measures including collaborating with line agencies. 31. The NGO shall ensure in collaboration with Engineer that Medical facilities and health checkups which may include detecting STD/AIDS for the workers are provided at the construction camps. 32. The NGO shall assist PWD to ensure that the Contractors comply with applicable labour laws (including prohibition of child labour) and gender issues.

III. CONDITION OF SERVICES 33. Two NGOs will be selected for implementation. One for North Karnataka and one for South Karnataka. No NGO should submit for more than one package. 34. The roads for RP implementation will provided to the NGO in a staggered manner. The time line for each of the links for RP implementation will be provided by the PIU. However, the ultimate end date remains the same 1.e two years from the start of signing of the contract. 139

35. The NGO shall ensure that the RP is implemented in an effective and proper manner. The prime responsibility of the NGO shall be to ensure that each and every eligible PDPs receive appropriate and due entitlement (within the Entitlement Framework). Additionally the NGO shall help the SDRC/PIU in all other matters deemed to be required to implement the RP in its spirit and entirety including activities involving some financial implications. 36. All documents created, generated or collected during the period of contract, in carrying out the services under this assignment will be the property of the SDRC/PIU. No information gathered or generated during and in carrying out this assignment shall be disclosed by the NGO without explicit permission of the SDRC/PIU. 1. Location of NGO 37. In order to carry out the above tasks, employees of NGO are to be stationed in each division as identified by the PIU. Each division office shall have one key person along with support staff. 2. Reporting 38. Reports will have to be submitted, as well as photographs, videotapes etc., taken during the assignment shall be submitted in support of the reports, along with an electronic copy of the documents. All reports should be in English language only. The following documentation have to be submitted. (i) Inception Report 39. The NGO shall submit to the PIU/SDRC an inception report-detailing plan of action, manpower deployment, time schedule, and detailed methodology within 21 days of the commencement of the assignment. (ii) Monthly progress Reports 40. The NGO should also submit monthly progress reports on the activities carried out during that month and proposed activities for the coming month. The monthly progress reports will include data on input and output indicators as required by the SDRC, with work charts as against the scheduled timeframe of RP implementation. All progress reports shall include data on input and output indicators as required by the SDRC. 41. The NGO shall document in full details, the consultation/counselling processes, the process of identification of the resettlement sites, and a full description of the training imparted (or facilitated) as part of the assignment. The progress achieved in land acquisition as per entitlements have to be documented. This documentation shall be submitted to the SDRC as a part of the monthly progress report. 42. Copies of the monthly report have to be submitted to (i) Assistant Commissioner; (ii) Local SDRC and (iii) PIU/SDRC. (iii) Final Report 43. Submit a completion report at the end of the contract period summarizing the actions taken during the project, the methods and personnel used to carry out the assignment, and a summary of supports/assistance given to the DPs.

140

(iv) Records of Meetings 44. All minutes of the meetings for GRC, gram sabhas, between SDRC and DPs etc have to be recorded and submitted to (i) Assistant Commissioner; (ii) Local SDRC and (iii) PIU/SDRC. (v) Record of Grievances 45. All grievances have to recorded and the process of redressal documented and submitted to (i) Assistant Commissioner; (ii) Local SDRC and (iii) PIU/SDRC on a monthly basis. (vi) Submission of Micro Plans 46. All micro plans have to be submitted, with the status of disbursement and payment of compensation, on a monthly basis. Where changes occur during the project requiring changes to the micro level plans, the NGO will update the relevant plans and resubmit them to the (i) Assistant Commissioner; (ii) Local SDRC and (iii) PIU/SDRC.

3. Data, Services and Facilities to be provided by the Client 47. The SDRC/PIU will provide to the NGO copies of the RP, Social Assessment Report , DP database, land acquisition details, and any other relevant reports/data prepared by the Project Preparation Consultants. All facilities required in the performance of the assignment, including office space, office stationery, transportation and accommodation for staff of the NGO etc., shall be arranged by the NGO. 4. Time Schedule 48. It is estimated that the NGO services will be required initially for two years for participating in the implementation of RP. The NGO shall carry out all assigned tasks based on the milestones as set out by the SDRC. 5. Payment 49. All payments will be linked to the completion of tasks as per milestones. As the implementation will be done in a staggered manner, payment will be linked to the completion of links/contract packages, based on the timeline provided by PIU. 50. The payment schedule will be made against outputs as given below. Output Payment Schedule 1. After unequivocal acceptance of Letter of 10% Total Contract value. At the Award and submission of inception report end of 1st month form should be completed within 1st Month. commencement of the services. With Bank Guarantee of 10% of Contract value. 2. a) Joint verification of Assets within Corridor 15% Total Contract Value. of Impact of all Packages information, dissemination and distribution of R & R Policy b) Issue of Identity card for eligible DPs should be completed within 6th Month 3. a) submission of Micro plan for Title Holders/ 20% Total Contract Value. Non Title Holder approval b) Disbursements for 50% of total PAHs. c) Final Data Analysis Report containing 141

additional and or missing Census details. d) Identification of Relocation sites for shifting of DHs/CPRS. Should be completed within 12th Month 4. a) Submission of Micro plan for Title Holders/ 25% Total Contract Value. Non Title Holder approval b) Disbursement of entitlements for 50% of total DHs. Should be completed within 16th Month 5. c) Training and need assessment for income 15% Total Contract Value. restoration. d) submission of monitoring and evaluation schedule of DPs on the implementation of RP Should be completed within 20th Month 6. a) on approval of final report summarizing 15% Total Contract Value. the action taken and other resettlement works to be fulfilled by NGO b) Should be completed within 24th Month

Bank Guarantee of 10% Contract Value shall be valid up to time period specified in C 1.2.3 of Special Conditions of contract.

6. Team for the Assignment 51. The NGO shall depute a team of professionals to the site. The constitution of the team and the qualification for the team members is given below: Sl. No. Of No Position Position Qualification . s 1. Team Leader 1 The Team Leader should be a post-graduate, preferably in social sciences. S/he should have about 10 years experience in implementation of R & R and rural development works. S/he should have held responsible position in the previous assignments should possess participatory management skills. Knowledge of local language is a necessary qualification. The team leader must have been with the NGO for at least 2 years. In case of Joint Ventures the Team Leader must be from the lead partner 2. Key 5 Should be a post-graduate in social sciences. S/he Professionals should have about 5 years of working experience of which about 2 years in R & R or rural development projects. Should have sound understanding of the land acquisition process and experience in participatory management. Knowledge of local language is a necessary qualification. One key professional has to have a minimum qualification of Diploma in Civil Engineering. One key professional has to be a woman.

142

Sl. No. Of No Position Position Qualification . s One key professional should have about 10 years experience of working in community development and community awareness projects. Should have about 5 years experience in the field of HIV/AIDS. 3. Sub 1 for Should be graduate or equivalent in social sciences with professionals every at least two years field experience. Knowledge of local 100 language and experience of working in the region major desired, One – third must be women. impacte d househ olds 4. Other support One support staff to be provided to each key Personnel professional

143

Annex 8

TERMS OF REFERENCE FOR MONITORING & EVALUATION CONSULTANTS FOR THE IMPLEMENTATION OF THE RESETTLEMENT PLAN

I. BACKGROUND

1.1. The aim of the project is to improve the performance of the State’s road transport sector. The KSHIP Stage II roads have been selected based on the Feasibility Study of State Roads for proposed KSHIP. The Asian Development Bank Assisted programme covers 650 kms of roads covering 20 links of 9 contract packages spread over in 15 districts. The up gradation and bypasses of roads will have direct /indirect impact on the population along the project corridor. Common property resources, residential structures, commercial structures are likely to be affected. Non-Titleholders within the ROW are likely to be displaced.

1.2. The proposed road improvement involves land acquisition, appropriation of structures and resettlement of squatters. The affected persons on account of the road improvements are covered under the Resettlement Plan (RP). All possible steps have been taken to minimize land acquisition and demolition of structures so as to reduce adverse affect on people settled along the road. Among others, the RP stipulates involvement of a consulting agency for monitoring and evaluation (M&E) of implementation of the RP, and compliance with the targets given in the RP.

1.3. It is in the background that the PIU/KSHIP intends to hire the services of a qualified and experienced external consultant to monitor and evaluate implementation of the RP being carried out by the PIU with the support of the NGO/s deployed.

II. OBJECTIVES OF THE ASSIGNMENT a. The objectives of the M&E consultancy services are (a) to assess the implementation of the RP; (b) to monitor the schedules and the achievement of targets; (c) to evaluate whether the outcomes of social development objectives of the project are being achieved.

III. SCOPE OF SERVICES

3.1. The CA will undertake to do the following assignments:

3.2 Undertake the supervision of RP implementation to ensure the delivery of entitlements to Project Displaced Persons/ Project Affected Persons in accordance with the provisions and procedures provided for in the Resettlement Plans.

3.3 Advise and guide the NGOs to implement the RP in accordance with their Terms of Reference; 3.4 To monitor the effectiveness and efficiency of PIU and NGO in the RP implementation.

144

3.5 To assess whether resettlement objectives, particularly livelihoods and living standards of the Displaced Persons ( DPs) have been restored or enhanced.

3.6 To assess the efforts of the PIU and NGO in ensuring 'Community Participation' with particulatr attention on participation of vulnerable groups namely a) those who are below the poverty line ( BPL);b) those who belong to scheduled castes ( SC), scheduled tribes ( ST); c) female headed households (FHH); d) elderly and e) disabled persons.

3.7 To assess resettlement efficiency, effectiveness, impact and sustainability, drawing both on policies and practices and to suggest any corrective measures if necessary.

3.8 To review the project impacts on Indigenous People and groups if any and assess the effectiveness of the mitigation measures adopted.

3.9 Assist the PIU and field units to oversee the implementation of RP;

3.10 Participate in periodical meetings held between PIU and NGOs/district administration to assist the PIU for successful outcomes of the meetings;

3.11 Undertake reviews on behalf of PIU of all documents and reports related to land acquisition and resettlement received from the NGOs and consultants and advise the PIU for taking appropriate decisions on such reports;

3.12 Assist the PIU to respond to the ADB on any matters related to the implementation of RP and related matters;

3.13 Provide certification prior to invitation of bid and at the time of handing over of the milestone stretches to the contracts confirming the completion of land acquisition, payment of compensation, mitigation of resettlement impacts and reconstruction of community properties in the respective stretches;

3.14 Ensure synchronization of R&R implementation with civil works time table to avoid time and cost over runs. This should be done in close co- ordination with the construction supervision consultants;

3.15 Assist PIU in reviewing any additional reports submitted by the consultants or NGOs during the implementation;

3.16 Prepare annual reports on the implementation of RP including land acquisition and payment of compensation;

3.17 Organization of periodical training in the implementation of RP and delivering of entitlements, consultations etc. to PIU staff and NGOs as necessary.

145

3.18 The consultant will carry out limited impact assessment twice during the contract period, one at the end of 15 months of the contract period and another at the end of 21 months of the contract period. Each evaluation will cover all Project Displaced Persons/ Project Affected Persons who have spent more than 6 months after receiving compensation or assistance or both.

3.19 For concurrent Impact Evaluation, the M& E Consultant shall:

Develop specific monitoring indicators for undertaking monitoring implementation of Resettlement Plans.

3.20 Review results of internal monitoring and verify through random checking at the field level to assess whether the objectives of resettlements have been realized, particularly the changes in the in the living standards;

3.21 Identify the strengths and weaknesses of the resettlement objectives and approaches and implementation strategies.

3.22 Review and verify the progress in resettlement implementation on the sample basis and prepare quarterly reports for the EA/ PIU and ADB.

3.23 Evaluate and assess the adequacy of compensation/ assistances given to the DPs/ PAPs and the livelihood opportunities and incomes as well as the quality of life of DPs/ PAPs after the project induced changes.

3.24 To evaluate and assess the adequacy and effectiveness of the consultative process with the affected DPs/ PAPs, particularly those vulnerable including the adequacy and effectiveness f grievance procedures and legal redress available to the affected parties, and dissemination of information about these.

146

3.25 Impact assessment is to be compared with the baseline values for key socioeconomic as given in the RP. If such information is not available information based on the same time of survey, has to be collected on recall basis;

3.26 to assess whether the compensation is adequate to replace the lost assets;

3.27 to assess how the compensation has been utilized;

3.28 assess the perceived benefits and losses of resettlement;

3.29 Assess the level of satisfaction of the various assets provided as part of R&R implementation;

3.30 Based on the impact assessment, suitable remedial measure are to be proposed for any shortcomings and;

3.31 Remedial measure if Project Displaced Persons/ Project Affected Persons are not able to improve their living standards.

IV REPORTING

The qualified and experienced external monitoring consultant will be responsible for monitoring of the R&R activities carried out by the EA/PIU and will submit quarterly review directly to ADB and determine whether resettlement goals have been achieved more importantly whether livelihoods and living standards have been restored/ enhanced and suggest suitable recommendations for improvement.

4.1 The CA shall submit the following reports: Inception Report with mobilisation details Quarterly Monitoring Reports Evaluation Reports (2)

Annual progress Reports Final Completion Report (containing implementation, experience and lessons learned).

All reports should be submitted in hard copy and soft copy in MS Word for easy transmission.

V METHODOLOGY

5.1 As a part of the proposal, the consultants will propose the methodology to carry out the assignment.

VI TIME LINE 147

6.1 The CA shall be hired for the period of project implementation that is 2 years.

VII BUDGET AND LOGISTICS

The proposal both technical and financial should be submitted and budget should include all costs and any other logistics details necessary for resettlement monitoring. Additional expense claims whatsoever outside the budget will not be entertained.

VIII QUALIFICATIONS

The qualified and experienced external monitoring consultants should have significant experience in resettlement policy analysis and RP implementation.

Proposals shold be submitted with relevant information concerning previous experience on monitoring of resettlement implementation and preparation of reports. In case of experts detailed CVs should be submitted providing the detils of the previous experience in monitoing and resettlement related activities.

IX TEAM FOR ASSIGNMENT

9.1 The CA shall deploy a team of which the positions and minimum qualification are stated in the following, with least one woman professional:

9.2 Team Leader: S/he should be a post-graduate in social sciences with at least 10 years of experience in the field of social development and projects requiring land acquisition. (Experience in land Acquisition is mandatory) S/he should have monitoring and evaluation experience of more than 5 projects, and should have held responsible positions in the previous assignments including as team leader. S/he should have adequate managerial skill and should be conversant with the region and the regional language.

9.3 Sub-Professional I: S/he should be a graduate in social sciences with at least 7 years of experience in the field of social development and participating rural appraisal. S/he should

148

adequate knowledge of computers and should be conversant with the region and the regional language.

9.4 Sub-Professional S/he should be a graduate in statistics with II: good knowledge of computerized database development and management and should be conversant with the region and the regional language.

9.5 Sub-Professional S/he should be a graduate in civil III: engineering with at least 7 years of experience in construction/maintenance of National/State Highways. S/he should good knowledge of land measurement and should be conversant with the region and the regional language.

9.6 Support Staff: There should be an adequate number of support staff. They should be able to perform as asked be the members of the team. There should be a good mix of women and men.

9.7 Location of office The CA is required to have an office in Bangalore and in the field.

X. PAYMENT SCHEDULE

10.1 The payment schedule will be made against outputs as given below:

Sl. Output Payment No. Schedule 1. Inception Report : 20%

2. After submission of 2nd : 20% quarterly Report

3. After submission of 2nd : 30% Evaluation Report after 15 months

4. After submission and : 30% approval of Final Completion Report

149

Note1: In the Road Development Projects taken up by the KSHIP, Project Affected Households/ Persons will be more when compared to Project Displaced Persons as the affected people will be mainly Title Holders, Squatters, Encroachers, Tenants & workers & that the affected structures & lands will also be partial. Hence PAPs (Project Affected Persons) are included along with PDPs (Project Displaced Persons).

2. Serial numbers have been changed taking into consideration of the suggestions made.