BUS RAPID TRANSIT PROJECT ENVIRONMENTAL ASSESSMENT

Environmental Assessment Appendix A Technical Report Purpose and Need

September 2019

Purpose and Need Technical Report CONTENTS METRO Gold Line Bus Rapid Transit Project

CONTENTS

Acronyms and Abbreviations ...... 1-iii

1. Purpose and Need ...... 1-1 1.1. Project Description ...... 1-1 1.1.1. Project Location ...... 1-1 1.1.2. Project Setting ...... 1-3 1.1.3. Regional Transit System ...... 1-5 1.2. Project Background ...... 1-8 1.2.1. Policy Direction and Prior Planning ...... 1-8 1.2.2. Environmental Review Process ...... 1-9 1.3. Purpose and Need ...... 1-10 1.3.1. Project Purpose ...... 1-10 1.3.2. Project Need...... 1-10 1.4. Goals and Objectives ...... 1-34

TABLES Table 1.1-1: Transitways with Connections to the Project Area ...... 1-7 Table 1.3-1: Existing Transit Service Characteristics ...... 1-11 Table 1.3-2: Existing and Future Population ...... 1-21 Table 1.3-3: Existing and Future Employment ...... 1-23 Table 1.3-4: Vehicle Ownership and Income in the Project Area Communities ...... 1-26 Table 1.3-5: County Plans for Growth and Transportation ...... 1-29 Table 1.3-6: Community Local Plans for Growth and Transportation ...... 1-31 Table 1.4-1: Project Goals and Objectives ...... 1-34

SEPTEMBER 2019 A1-i

Purpose and Need Technical Report CONTENTS METRO Gold Line Bus Rapid Transit Project

FIGURES Figure 1.1-1: METRO Gold Line Bus Rapid Transit Project ...... 1-2 Figure 1.1-2: Project Area and Activity Centers ...... 1-4 Figure 1.1-3: Regional Transitway System ...... 1-6 Figure 1.2-1: Previous Relevant Studies and Plans in the Project Area ...... 1-8 Figure 1.3-1: Existing Transit Service and Facilities (Twin Cities Metropolitan Area System) ...... 1-14 Figure 1.3-2: Midday Transit Frequency (Twin Cities Metropolitan Area System) ...... 1-15 Figure 1.3-3: 2017 Metro Freeway Congestion (Daily) ...... 1-18 Figure 1.3-4: Percent Change in Average Daily Traffica – Existing to 2040 ...... 1-19 Figure 1.3-5: 2010-2040 Population Growth in the Project Area ...... 1-22 Figure 1.3-6: 2010-2040 Employment Growth in the Project Area ...... 1-24 Figure 1.3-7: Zero-Vehicle Households in the Project Area Communities ...... 1-27

SEPTEMBER 2019 A1-ii

Purpose and Need Technical Report ACRONYMS AND ABBREVIATIONS METRO Gold Line Bus Rapid Transit Project

ACRONYMS AND ABBREVIATIONS

2040 TPP (2018 Update) 2040 Transportation Policy Plan (2018 Update) BRT Bus Rapid Transit Council CSAH County State Aid Highway EA Environmental Assessment EB Eastbound EAW Environmental Assessment Worksheet FTA Federal Transit Administration I- Interstate LRT Transit MEPA Environmental Policy Act MnDOT Minnesota Department of Transportation NEPA National Environmental Policy Act NB Northbound Project METRO Gold Line Bus Rapid Transit Project RCRRA Ramsey County Regional Railroad Authority SB Southbound TH Trunk Highway TOD Transit-Oriented Development USC U.S. Code vpd Vehicles per Day WB Westbound

SEPTEMBER 2019 A1-iii

Purpose and Need Technical Report ACRONYMS AND ABBREVIATIONS METRO Gold Line Bus Rapid Transit Project

Page left intentionally blank.

SEPTEMBER 2019 A1-iv

Purpose and Need Technical Report PROJECT DESCRIPTION METRO Gold Line Bus Rapid Transit Project

1. PURPOSE AND NEED

This report describes the location and setting of the METRO Gold Line Bus Rapid Transit (BRT) Project (Project), the purpose of the Project, the needs driving the study of the Project, and the parameters the Metropolitan Council (Council) used to evaluate the Project. This report also provides an overview of previous planning studies and the environmental review process.

1.1. Project Description

1.1.1. Project Location The Project is a planned 9- to 10-mile transitway located in Ramsey and Washington counties in the eastern part of the Twin Cities Metropolitan Area (see Figure 1.1-1). The Project generally would operate parallel to Interstate 94 (I-94) and would better connect downtown Saint Paul with the suburban cities of Maplewood, Landfall, Oakdale and Woodbury. More broadly, the Project would better connect the eastern Twin Cities Metropolitan Area to the regional transit network via the Union Depot multimodal hub in downtown Saint Paul. The Project also intends to serve and draw ridership from other portions of the metropolitan area, including portions of eastern Washington County, Dakota County to the south, and the City of and Hennepin County to the west. While the intended service area for the Project is larger, the documentation of the Project purpose and need focuses on those communities the Project expects to serve most directly: the communities within 2 miles of the proposed Build Alternatives. These are either communities in which the Project is physically located (Saint Paul, Maplewood, Landfall, Oakdale and Woodbury) or a community within 2 miles of the proposed alignment (Lake Elmo). Together, these communities make up the Project area discussed below.

SEPTEMBER 2019 A1-1

Purpose and Need Technical Report PROJECT DESCRIPTION METRO Gold Line Bus Rapid Transit Project

FIGURE 1.1-1: METRO GOLD LINE BUS RAPID TRANSIT PROJECT

SEPTEMBER 2019 A1-2

Purpose and Need Technical Report PROJECT DESCRIPTION METRO Gold Line Bus Rapid Transit Project

1.1.2. Project Setting The character of the Project area changes from an urban setting in downtown and the east side of Saint Paul to a transitional suburban setting as it extends further east. The Project area includes a wide range of land uses including single-family, multifamily and mixed use residential; retail and other commercial; office; mixed use commercial; industrial; utility; parks; and undeveloped areas. Low-density, auto-oriented land uses heavily influenced much of the area’s existing development patterns, which primarily reflect highway-oriented regulations and traditional suburban development forms. The communities within the Project area include several key activity centers located along I-94 including downtown Saint Paul, Union Depot, Metro State University, the White Bear Avenue commercial area, Sun Ray Shopping Center, 3M campus, The Oaks Business Park, Tamarack Hills, 500 Bielenberg, and the Tamarack and Woodbury Villages (see Figure 1.1-2). This report defines key activity centers as employment, education and shopping destinations. Key transportation facilities in the Project area include the I-94 corridor, Saint Paul Downtown Airport shown in Figure 1.1-1, the regional transitway system shown in Figure 1.1-3, and multiple freight railways.

SEPTEMBER 2019 A1-3

Purpose and Need Technical Report PROJECT DESCRIPTION METRO Gold Line Bus Rapid Transit Project

FIGURE 1.1-2: PROJECT AREA AND ACTIVITY CENTERS

SEPTEMBER 2019 A1-4

Purpose and Need Technical Report PROJECT DESCRIPTION METRO Gold Line Bus Rapid Transit Project

1.1.3. Regional Transit System A mix of local and express bus service provided by Metro Transit currently serves the Project area. Service in the western portion of the Project area consists of urban local routes serving densely populated areas, the Sun Ray Shopping Center in Saint Paul, and the 3M campus in Maplewood. Commuter express service during peak travel periods, primarily provided through park-and-ride facilities, serves the eastern portion of the Project area. Key transit facilities on the Project alignment include the Smith Avenue Transit Center located on Smith Avenue1 and Union Depot, both located in downtown Saint Paul; the Sun Ray Transit Center located on Pedersen Street in east Saint Paul; 2 and the Woodbury Theatre Park-and-Ride on Queens Drive in Woodbury. Additional transit infrastructure in the Project area includes other park-and-ride facilities farther from I-94 and bus-only shoulders on most of I-94 in both directions. Metro Transit is also planning a new park-and-ride facility in the northwest quadrant of the I-94/Manning Avenue interchange in Lake Elmo to open in late 2019. The Council’s 2040 Transportation Policy Plan (2018 Update) (2040 TPP (2018 Update))3 envisions the bus system will continue to be the workhorse of the regional transit system by providing the majority of transit trips, providing essential connections to transitways, and providing options throughout the entire region. The region will also continue development of a regional system of transitways to meet mobility needs and increase transit system ridership. A transitway is a combination of infrastructure and transit service improvements that allows transit customers to avoid congestion on roadways and connect to regional activity centers and that boosts the potential for transit-oriented development (TOD). The Project would provide additional transit access and reliability between the region’s eastern suburbs and the growing regional transitway system (see Figure 1.1-3). Key among these is the METRO Green Line, which began operations in 2014 and connects Union Depot in downtown Saint Paul to downtown Minneapolis and several other transitways.

1 Metro Transit. Smith Avenue Transit Center. Available at: https://www.metrotransit.org/smith-avenue-transit-center. Accessed March 2019. 2 Metro Transit. Sun Ray Transit Center. Available at: https://www.metrotransit.org/sun-ray-transit-center. Accessed March 2019. 3 Metropolitan Council. 2040 Transportation Policy Plan (2018 Update). Adopted October 24, 2018. Available at: https://metrocouncil.org/tpp-update.aspx?source=child. Accessed October 2018.

SEPTEMBER 2019 A1-5

Purpose and Need Technical Report PROJECT DESCRIPTION METRO Gold Line Bus Rapid Transit Project

FIGURE 1.1-3: REGIONAL TRANSITWAY SYSTEM

Source: Metropolitan Council4

4 Metropolitan Council. 2040 Transportation Policy Plan (2018 Update). Adopted October 24, 2018. Available at: https://metrocouncil.org/tpp-update.aspx?source=child. Accessed October 2018.

SEPTEMBER 2019 A1-6

Purpose and Need Technical Report PROJECT DESCRIPTION METRO Gold Line Bus Rapid Transit Project

Table 1.1-1 identifies existing and planned transitways with connections to the Project that are included in the 2040 TPP (2018 Update).

TABLE 1.1-1: TRANSITWAYS WITH CONNECTIONS TO THE PROJECT AREA

Transitway Connection Point Status Connections in Saint Paul METRO Green Line Union Depot/Downtown Saint Paul  Existing (Light Rail Transit (LRT)) (Modern Union Depot/Downtown Saint Paul  Planned Streetcar)  Pre-project development study completed Union Depot/Downtown Saint Paul  Planned (Dedicated BRT)  Environmental analysis phase underway Robert Street Transitway Union Depot/Downtown Saint Paul  Planned  Alternatives study completed in 2015 (Highway BRT) Union Depot/Downtown Saint Paul,  Planned Mounds Boulevard Station, Earl  Implementation plan approved in Street Station, Etna Street Station 2016 Connections via METRO Green Line METRO Blue Line (LRT) Downtown Minneapolis (Target  Existing Field Station) METRO Red Line (Highway BRT) METRO Green Line to METRO  Existing Blue Line to Station Northstar Commuter Rail Downtown Minneapolis (Target  Existing Field Station) (Arterial BRT) Saint Paul (Snelling Avenue  Existing Station) (Arterial BRT) Downtown Minneapolis (short walk  Existing to ) (Arterial BRT) Downtown Minneapolis (short walk  Engineering underway to Target Field Station) METRO Orange Line (I-35W South Downtown Minneapolis  Under construction BRT) Southwest LRT Downtown Minneapolis (Target  Under construction (METRO Green Line Extension) Field Station) METRO Blue Line Extension (LRT) Downtown Minneapolis (Target  Engineering underway Field Station)

SEPTEMBER 2019 A1-7

Purpose and Need Technical Report PROJECT BACKGROUND METRO Gold Line Bus Rapid Transit Project

1.2. Project Background

1.2.1. Policy Direction and Prior Planning Previous studies addressing transit in the Project area include feasibility studies, park-and-ride plans, managed lane studies and long-range transportation plans. The most recent study for the Project was the Gateway Corridor Alternatives Analysis Final Report,5 completed in February 2013. Figure 1.2-1 summarizes regional transportation plans and past studies in the Project area.

FIGURE 1.2-1: PREVIOUS RELEVANT STUDIES AND PLANS IN THE PROJECT AREA

a Minnesota Department of Transportation b Ramsey County Regional Railroad Authority

The 2040 TPP (2018 Update) identifies the Project as one of seven transitway corridors assumed to be funded within the current revenue scenario (see Figure 1.1-3).

5 Gateway Corridor Commission. Gateway Corridor Alternatives Analysis Final Report. February 2013. Available at: http://thegatewaycorridor.com/alternative-analysis. Accessed October 2018.

SEPTEMBER 2019 A1-8

Purpose and Need Technical Report PROJECT BACKGROUND METRO Gold Line Bus Rapid Transit Project

1.2.2. Environmental Review Process The Federal Transit Administration (FTA) and the Council prepared this statement of purpose and need as part of the environmental review process for the Project. The FTA and Council, along with the Ramsey County Regional Railroad Authority and the Washington County Regional Railroad Authority (on behalf of the Gateway Corridor Commission) initiated the environmental review process for the Project in February 2014 with a Notice of Intent to develop and Environmental Impact Statement.6 The Council is planning to pursue federal funding for the Project through the FTA’s Capital Investment Grant Program; therefore, the FTA is the Project’s designated lead federal agency, and it is undertaking the environmental review in compliance with the National Environmental Policy Act (NEPA).7 The Council is the Project’s lead local agency and the State’s Responsible Governmental Unit for complying with Minnesota Environmental Policy Act (MEPA)8 requirements. The FTA and Council together completed this Environmental Assessment (EA) and the Environmental Assessment Worksheet (EAW) for the Project. Appendix F of this EA includes the EAW. The NEPA and MEPA processes identify how the Project could produce potential impacts to the environment, so the FTA and Council can consider these impacts when making Project-related decisions; the EA/EAW will assist decision-makers as they assess potential Project-related impacts. The EA/EAW records the purpose and need for the Project and the alternatives considered for the Project; addresses the Project’s anticipated transportation, social and environmental impacts; and defines appropriate avoidance, minimization and mitigation measures. Federal, state and local agencies, and the public will use this EA/EAW to review the Project. The Council will provide this EA/EAW for review by interested parties including individuals, community groups, the business community, elected officials and public agencies in accordance with federal and state requirements. The Council will conduct public meetings as forums for participation and commenting. The Council will respond to comments it receives about the EA/EAW, and a decision document will record both the comments and the Council’s responses.

6 In 2017, after the Locally Preferred Alternative was adopted, the Federal Transit Administration rescinded its notice for development of an Environmental Impact Statement, and analysis was instead completed for an Environmental Assessment, which the FTA determined as the appropriate class of action per the National Environmental Policy Act. See the Alternatives Technical Report in Appendix A for additional information. 7 The National Environmental Policy Act of 1969, as amended. (“The Public Health and Welfare,” Title 42, USC, Sec. 4321 et seq. (1969)). Available at: https://www.gpo.gov/fdsys/pkg/USCODE-2011-title42/pdf/USCODE-2011-title42-chap55- sec4321.pdf. Accessed November 2018. 8 “Environmental Policy,” Chap. 116D., Minnesota Statutes, 2018. Available at: https://www.revisor.mn.gov/statutes/cite/116D. Accessed October 2018.

SEPTEMBER 2019 A1-9

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

1.3. Purpose and Need

1.3.1. Project Purpose The following statement specifically defines the fundamental reasons why the Council is proposing the Project: The purpose of the Project is to provide transit service to meet the existing and long-term regional mobility and local accessibility needs for businesses and the traveling public within the Project area.

1.3.2. Project Need This section outlines the foundation for the Project purpose statement. Project “needs” are the issues and problems that the Project intends to address. The following primary factors contribute to the need for the Project: • Limited existing transit service throughout the day and demand for more frequent service over a larger portion of the day • Policy shift toward travel choices and multimodal investments • Population and employment growth, increasing access needs and travel demand • Needs of people who depend on transit • Local and regional objectives for growth and prosperity

1.3.2.1. Limited Existing Transit Service Summary: The Project area and the I-94 corridor lack all-day, bidirectional transit service that would operate from 5 a.m. to midnight on weekdays and weekends, particularly east of Saint Paul and Maplewood, limiting the ability of people in the Project area to use transit to meet their transportation needs.

TRANSIT SERVICE LIMITATIONS Fixed-service bus routes serve the Project area today including local, high-frequency local and express services. Table 1.3-1 describes the routes and their respective service characteristics, and Figure 1.3-1 shows these routes’ geographic coverages. All-day local bus service that operates during midday, evenings and weekends is concentrated in Saint Paul and primarily serves the western half of the Project area and peak-travel-period-only express service with access at select park-and-ride locations on the I-94 corridor serves the eastern half. The communities served by I-94 have no all-day, bidirectional transit service connection, particularly east of Saint Paul and Maplewood (see Figure 1.3-2). Much of the Project area is not accessible to transit or has only peak-period service.

SEPTEMBER 2019 A1-10

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

TABLE 1.3-1: EXISTING TRANSIT SERVICE CHARACTERISTICS

Frequency (Minutes) Number of Number of Route Span of Service (Peak/Mid/Eve/Wknd) Weekday Trips Weekend Trips Cities Served Urban Local Routes 61 4:51 AM – 10:27 PM 15-30/30/60/60 Eastbound: 38 Saturday EB: 14  Saint Paul Westbound: 36 Sunday EB: 13  Minneapolis 63 4:22 AM – 12:40 AM 10-20/20/20-30/20-30 Eastbound: 56 Saturday EB: 49  Saint Paul Westbound: 56 Saturday WB: 49 Sunday EB: 48 Sunday WB: 48 64 4:57 AM – 1:16 AM 9-15/10-15/15-30/15-60 Eastbound: 83 Saturday EB: 67  Saint Paul Westbound: 83 Saturday WB: 66  North St. Paul Sunday EB: 43  Maplewood Sunday WB: 48 70 5:45 AM –10:11 PM 30/30/60/60 Eastbound: 30 Saturday EB: 10  Saint Paul Westbound: 30 Saturday WB: 11  Maplewood Sunday EB: 10 Sunday WB: 10 74 3:28 AM – 12:43 AM 15-20/20/30/20-30 Eastbound: 57 Saturday EB: 49  Saint Paul Westbound: 60 Saturday WB: 49  Maplewood Sunday EB: 37 Sunday WB: 38 80 6:42 AM – 7:12 PM 30/60/None/30-60 Southbound: 19 Saturday SB: 19  Saint Paul Northbound: 19 Saturday NB: 18  Maplewood Sunday SB: 10 Sunday NB: 10

SEPTEMBER 2019 A1-11

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

Frequency (Minutes) Number of Number of Route Span of Service (Peak/Mid/Eve/Wknd) Weekday Trips Weekend Trips Cities Served Suburban Local Routes 219 5:48 AM –9:42 PM 30/30/60/60 Southbound: 30 Saturday SB: 14  Saint Paul Northbound: 30 Saturday NB: 14  Maplewood  White Bear Lake  North St. Paul  Oakdale  Landfall Minneapolis Oriented Express and Limited Stop Routes 353 5:41 AM – 6:23 PM 1 trip/None/None Eastbound: 1 None  Minneapolis  Saint Paul  Woodbury 355 6:04 AM –6:12 PM 10-20/None/None Eastbound: 13 None  Minneapolis Westbound: 13  Woodbury 365 5:38 AM – 6:12 PM 10-30/None/None Southbound: 10 None  Minneapolis Northbound: 10  Cottage Grove 375 5:51 AM – 5:37 PM 10-30/None/None Eastbound: 10 None  Minneapolis Westbound: 9  Oakdale

SEPTEMBER 2019 A1-12

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

Frequency (Minutes) Number of Number of Route Span of Service (Peak/Mid/Eve/Wknd) Weekday Trips Weekend Trips Cities Served Saint Paul Oriented Express and Limited Stop Routes 294 5:24 AM – 5:39 PM 30-60/None/None Eastbound: 8 None  Saint Paul Westbound: 9  Maplewood  Oakdale  Lake Elmo  Stillwater  Oak Park Heights 350 5:32 AM – 5:47 PM 4 Trips/None/None Eastbound: 4 None  Saint Paul Westbound: 4  Maplewood 351 6:19 AM – 5:46 PM 15-30/None/None Eastbound: 7 None  Saint Paul Westbound: 8  Woodbury 361 6:16 AM – 5:12 PM 5-6 Trips/None/None Southbound: 6 None  Saint Paul Northbound: 5  Cottage Grove  Newport 364 5:53 AM – 5:25 PM 3 Trips/None/None Southbound: 3 None  Saint Paul Northbound: 3  St. Paul Park  Newport  Cottage Grove

SEPTEMBER 2019 A1-13

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

FIGURE 1.3-1: EXISTING TRANSIT SERVICE AND FACILITIES (TWIN CITIES METROPOLITAN AREA SYSTEM)

SEPTEMBER 2019 A1-14

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

FIGURE 1.3-2: MIDDAY TRANSIT FREQUENCY (TWIN CITIES METROPOLITAN AREA SYSTEM)

SEPTEMBER 2019 A1-15

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

As Figure 1.3-2 shows, Woodbury and Lake Elmo have no off-peak express or local service. Several routes in the Project area have off-peak frequencies that exceed 30 minutes: • Route 61 is an urban local service that operates on Larpenteur Avenue, Arcade Avenue and East 7th Street in the Project area. On evenings and weekends, it operates at a 60-minute frequency. • Route 70 is an urban local service that runs between downtown Saint Paul and Maplewood along East 7th Street, Mounds Boulevard, Burns Avenue, White Bear Avenue and Upper Afton Road. On evenings and weekends, it operates at a 60-minute frequency. • Route 80 is an urban local service that operates primarily along White Bear Avenue, connecting the and Sun Ray Transit Center. It operates at a 30-minute frequency during peak periods; 60- minute frequency during midday; and 30- to 60-minute frequencies on weekends. Route 80 has no evening service. • Route 219 is a suburban local service that circulates between the Maplewood Mall and Sun Ray Transit Center, and it includes the communities of Saint Paul, Maplewood, White Bear Lake, North Saint Paul, Oakdale and Landfall along the Trunk Highway (TH) 120/Century Avenue corridor. Route 219 operates at a 60-minute frequency during evenings and on Saturdays. The route does not have Sunday service.

OPPORTUNITY FOR GREATER REGIONAL CONNECTIVITY Enhanced transit service would improve the ability of people in the Project area to access employment and other destinations in the greater Twin Cities Metropolitan Area. To access the area’s rapidly growing regional transitway network, residents, employees and other potential transit-users in the Project area need a reliable and time- competitive option for travel to and from downtown Saint Paul, which serves as a key access point to the regional transitway system (see Figure 1.1-3). The region’s extensive bus network that connects Saint Paul to Minneapolis and suburban cities currently serves downtown Saint Paul. The METRO Green Line began operating in 2014, improving access to University Avenue, the State Capitol Complex, the University of Minnesota and downtown Minneapolis. Union Depot in downtown Saint Paul opened in 2013 as one of two regional multimodal transportation hubs. The facility provides connections to the METRO Green Line and the regional transitway system, Amtrak passenger rail to Chicago and the Pacific Northwest, intercity and regional buses, local bus service, car-sharing service, car- rental service, and bicycle and pedestrian facilities. Figure 1.3-2 shows the existing transit service and facilities in the Project area. Downtown Saint Paul also has several planned local and regional transit improvements including the Rush Line BRT, Riverview Corridor, Robert Street Transitway, East 7th Street Arterial BRT, and potential future Saint Paul Streetcar (see Table 1.1-1). Transitways, by definition, provide bidirectional, high-frequency, all-day service. A lack of corresponding service levels in the Project area would limit the benefits of the rest of the regional system.

GROWING DEMAND Metro Transit’s ridership totaled 81.9 million rides in 2017. Metro Transit has provided more than 80 million rides in each of the past seven years, sustaining the highest ridership the agency has seen in three decades. Ridership in the Project area is part of this regional growth.

SEPTEMBER 2019 A1-16

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

Between 2009 and 2015, park-and-ride use at five park-and-rides within the Project area increased by 16 percent.9 These include Guardian Angels Catholic Church, Walton Park, Christ Episcopal Church, Woodbury Lutheran Church and Woodbury Theatre. Because nearly all park-and-ride users are express bus riders, it follows that express bus ridership in the Project area grew similarly during this period. As of 2017, 78 percent of available spaces at the five-Project area park-and-rides were occupied. Park-and-ride demand has been growing, particularly in the Woodbury/Lake Elmo area. To address this demand, the Council is planning to build a new 550-space park-and-ride in the northwest quadrant of the I-94/Manning Avenue Interchange in Lake Elmo to open in late 2019, when the Council also plans to extend express bus service to downtown Minneapolis and downtown Saint Paul from the new park-and-ride.

1.3.2.2. Policy Shift Toward Travel Choices and Multimodal Investments Summary: I-94 and local roadways in the Project area are congested today during peak periods. Modeling forecasts anticipate increased traffic volumes and congestion in the future. Funding for roadway projects will not be adequate to address the congestion problem. State and regional transportation policies identify the need to provide alternatives to traveling in congested conditions.

CONGESTION I-94 experiences significant recurring congestion, particularly during the morning peak period between downtown Saint Paul and at Century Avenue at the Maplewood/Oakdale border. Morning westbound congestion ranges from one to two hours daily at the eastern end of this segment to two to three hours near downtown Saint Paul. In the evening, three or more hours of recurring eastbound congestion occurs daily on I-94 in downtown Saint Paul. The Minnesota Department of Transportation (MnDOT) defines congestion as any 15-minute period where travel speeds are less than 45 mph. The speed threshold of 45 mph is significant because it is the speed at which “shock waves” can occur.10 A shock wave is the phenomenon where most of the vehicles in a traffic stream brake. Several events can create the shock wave condition including a lane ending, large traffic volumes entering the freeway, traffic incidents or weather conditions. As the rate of movement of the shock wave increases, the potential for rear-end or sideswipe collisions increases. Multiple shock waves can spread from one instance of a slowdown in traffic and blend together with other extended periods of congestion upstream. As with recurring freeway congestion in other locations, the congested locations on I-94 in the Project area result not just in slower traffic and potential safety concerns but also in decreased reliability and predictability of the highway in terms of travel time. Figure 1.3-3 shows daily freeway congestion.

9 Metropolitan Council. 2017 Annual Regional Park-and-Ride System Report. January 2018. Available at: https://www.metrotransit.org/Data/Sites/1/media/park-and-ride/07-013-01-18_2017-annual-regional-park-and-ride-report- revised2.pdf. Accessed October 2018. 10 Minnesota Department of Transportation. 2017 Congestion Report – Metropolitan Freeway System. January 2017. Available at: http://www.dot.state.mn.us/rtmc/reports/congestionreport2017.pdf. Accessed October 2018.

SEPTEMBER 2019 A1-17

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

FIGURE 1.3-3: 2017 METRO FREEWAY CONGESTION (DAILY)

Source: Minnesota Department of Transportation

SEPTEMBER 2019 A1-18

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

FORECASTED INCREASES IN TRAVEL VOLUMES East of Century Avenue, where there is less congestion today than in the rest of the Project area, forecasts anticipate substantial traffic growth over the next 10 years. The Council anticipates the percentage of congested miles on Twin Cities urban freeways will grow by 24 to 34 percent over the next 10 years. Forecasts also anticipate that arterial roadway volumes in the eastern part of the Project area will grow by 2040. The Council anticipates approach volumes north and south of I-94 at County State Aid Highway (CSAH) 13 (Radio Drive/Inwood Avenue), CSAH 19 (Woodbury Drive/Keats Avenue), and CSAH 15/TH 95 S (Manning Avenue) will reach volumes between 24,200 and 50,800 vehicles per day (vpd), representing growth of 9,200 to 18,300 vpd for each approach (see Figure 1.3-4). This growth in arterial volume is anticipated to result in operational deficiencies in both the AM and PM peak hours.11

FIGURE 1.3-4: PERCENT CHANGE IN AVERAGE DAILY TRAFFICa – EXISTING TO 2040

80% 73% 70%

60% 56%

50%

40% 33% 32% 34% 29% 29% 30% 26%

20%

10%

0%

to to I-494

Manning Ave Manning

St. Croix Trail to Trail St. Croix

I-94 to Rd Hudson I-94 to Rd Hudson I-94 to Rd Hudson I-94

Ave/Woodbury Dr Ave/Woodbury

I-494 to Century to Ave I-494

Inwood Ave/Radio Dr Ave/Radio Inwood

Manning Ave to Keats Ave to Manning

to Inwood Ave/Radio Ave/Radio Dr to Inwood Keats Ave/Woodbury Dr Ave/Woodbury Keats I-94 I-94 I-94 I-94 I-94 Manning AveWoodbury Dr Radio Dr a 2014 average weekday daily traffic on freeways and 2010/2012 annual average daily traffic on arterial roadways.

11 Minnesota Department of Transportation. Rethinking I-94 Phase I Report. August 2018. Available at: http://www.dot.state.mn.us/I-94minneapolis-stpaul/pdf/vision/phase-1-report.pdf. Accessed November 2018.

SEPTEMBER 2019 A1-19

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

LIMITED MAJOR INVESTMENTS PLANNED TO ADDRESS CAPACITY NEEDS MnDOT’s 2019-2022 State Transportation Improvement Program12 does not identify projects that would add capacity within the Project area. There are two MnDOT projects factored in the No-Build Alternative that would add auxiliary lanes in the Project area. These projects increase traffic flow but do not add capacity in the form of additional travel lanes. The first project, completed in October 2018, provides auxiliary lanes on I-94 eastbound between East 7th Street and Mounds Boulevard in Saint Paul. The second project, programmed for 2019, includes auxiliary lanes at the I-694/I-494/I-94 interchange. Also included in the No-Build Alternative is the managed lanes project along I-94 between Minneapolis and Saint Paul that could overlap the Project between Mounds Boulevard and TH 61. Concepts for this project are currently being studied by MnDOT. The Minnesota State Highway Investment Plan: 2018-203713 includes a 20-year investment direction that focuses on maintaining the existing state highway system while making limited mobility investments. The lack of programmed projects in the Project area is consistent with highway funding constraints locally and nationally.

REGIONAL AND STATE POLICY EMPHASIS ON MULTIMODAL INVESTMENTS The State of Minnesota and the Twin Cities Metropolitan Area are shifting away from addressing highway congestion through investments in just a single mode of transportation – automobile – and are instead including multiple travel modes such as transit, bicycling and walking in addition to automobile. This policy shift will provide alternatives to traveling in congested highway conditions. To this end, a key strategy in the Statewide Multimodal Transportation Plan: 2017-203614 is: Maintain and improve multimodal transportation connections essential for Minnesotans’ prosperity and quality of life. Strategically consider new connections that help meet performance targets and maximize social, economic and environmental benefits…. As a state agency, MnDOT, in cooperation with other transportation partners, strives to provide connections that move people and goods across the state and within regions. This includes roadways, waterways, intercity and regional bus, airports, rail and bicycle routes. The Council’s 2040 TPP (2018 Update) for the Twin Cities Metropolitan Area also prioritizes multimodal investments and the importance of a balanced approach to meeting travel demand. The 2040 TPP (Update 2018) includes the following strategies that emphasize transit and the need for alternatives to traveling on congested highways: • C1. Promoting Alternatives: Regional transportation partners will continue to work together to plan and implement transportation systems that are multimodal and provide connections between modes. The Metropolitan Council will prioritize regional projects that are multimodal and cost-effective and encourage investments to include appropriate provisions for bicycle and pedestrian travel.

12 Minnesota Department of Transportation. State of Minnesota 2019-2022 State Transportation Improvement Program. September 2018. Available at: http://www.dot.state.mn.us/planning/program/pdf/stip/2019_22%20Final%20STIP.pdf. Accessed December 2018. 13 Minnesota Department of Transportation. Minnesota State Highway Investment Plan: 2018-2037. January 2017. Available at: http://minnesotago.org/application/files/7914/8431/7219/MnSHIP_Final_Jan2017_With_Appendices.pdf. Accessed November 2018. 14 Minnesota Department of Transportation. Statewide Multimodal Transportation Plan: 2017-2036. January 2017. Available at: http://minnesotago.org/application/files/7414/8642/7717/SMTP_Plan_Final_Jan2017_small.pdf. Accessed November 2018.

SEPTEMBER 2019 A1-20

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

• C4. Access to Destinations: Regional transportation partners will promote multimodal travel options and alternatives to single-occupant vehicle travel and highway congestion through a variety of travel demand management initiatives with a focus on major job, activity, and industrial and manufacturing concentrations on congested highway corridors and corridors served by regional transit service.

1.3.2.3. Population and Employment Growth Summary: Forecasts anticipate population and employment growth in the Project area. This growth will in turn increase access needs and travel demand, particularly in the I-94 corridor.

POPULATION GROWTH As Table 1.3-2 shows, the Twin Cities Metropolitan Area population15 is continuing to grow, with a projected growth rate of 31 percent between 2010 and 2040, according to the 2010 census and the regional forecasts from the Council’s Thrive MSP 2040 plan.16 Population growth within Washington County accounts for approximately 10 percent of the region’s 2010 to 2040 projected growth, with approximately 92,064 anticipated new residents. Within the Project area, forecasts anticipate particularly strong population growth in Woodbury, which only has express bus service (see Figure 1.3-5).

TABLE 1.3-2: EXISTING AND FUTURE POPULATION

Area 2010 2040 % Change 2010-2040 Ramsey County 508,640 594,120 16.8% Washington County 238,136 330,200 38.6% Saint Paul 285,068 334,100 17.2% Maplewood 38,018 48,600 27.8% Landfall 663 630 -4.9% Oakdale 27,401 30,200 10.2% Woodbury 61,961 87,800 41.7% City Total 413,111 501,330 21.4% Twin Cities Metropolitan Area 2,855,245 3,738,047 30.9%

15 The Metropolitan Council’s 2040 projections formed the basis for the population and employment forecasts, which this Environmental Assessment updated based on input from Project area communities. The Council uses a regional economic model to forecast population, household and employment figures. After the regional forecast is complete, the Council used land use modeling to determine future population, households and employment data to specific communities within the region. Finally, the Council adjusts these results based on input from local governments and planners who supplied information about local development. The Council updates its 30-year regional and local forecasts at least once per decade. (Metropolitan Council. “Census Data, Forecasts, and Population Estimates”. Available at: http://www.metrocouncil.org/Data- and-Maps/Data/Census-Forecasts-Estimates.aspx. Accessed September 2018.) 16 Metropolitan Council. Thrive MSP 2040: One Vision, One Metropolitan Region. Adopted May 28, 2014. Available at: https://metrocouncil.org/Planning/Projects/Thrive-2040/Thrive-MSP-2040-Plan.aspx?source=child. Accessed October 2018.

SEPTEMBER 2019 A1-21

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

FIGURE 1.3-5: 2010-2040 POPULATION GROWTH IN THE PROJECT AREA

SEPTEMBER 2019 A1-22

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

EMPLOYMENT GROWTH Forecasts anticipate Project-area employment will grow rapidly between 2010 and 2040. In this time frame, Ramsey County expects to add about 76,000 jobs and Washington County expects to add about 33,000 jobs. Together, these numbers account for 20 percent of the seven-county Twin Cities Metropolitan Area’s anticipated employment growth during that period. Table 1.3-3 shows current employment and future employment forecasts for the Project area. Net job gains are concentrated in Saint Paul (+37,567), Maplewood (+7,165), and Woodbury (+9,262). Anticipated employment growth in Woodbury and Oakdale is concentrated along the I-94 corridor (see Figure 1.3-6).

TABLE 1.3-3: EXISTING AND FUTURE EMPLOYMENT

Area 2010 2040 % Change 2010-2040 Ramsey County 316,937 393,070 24.0% Washington County 71,897 105,410 46.6% Saint Paul 175,933 213,500 31.6% Maplewood 27,635 34,800 25.9% Landfall 25 30 20.0% Oakdale 8,651 14,000 61.8% Woodbury 19,438 28,700 47.6% City Total 231,682 291,030 25.6% Twin Cities Metropolitan Area 1,543,872 2,039,000 32.0%

Source: Minnesota Department of Employment and Economic Development (2013), Thrive 2040 MSP (Metropolitan Council, January 2018), 2010 census, Woods & Poole (2013)

SEPTEMBER 2019 A1-23

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

FIGURE 1.3-6: 2010-2040 EMPLOYMENT GROWTH IN THE PROJECT AREA

SEPTEMBER 2019 A1-24

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

1.3.2.4. Needs of People Who Depend on Transit Summary: Deficiencies in transit service limit the ability of people in the Project area who depend on transit for access to employment and other needs. The communities in the Project area are home to several populations that depend on transit to meet their transportation needs. These communities have 18,100 households without a vehicle, over one-fifth of the seven- county Twin Cities Metropolitan Area’s zero-vehicle population (see Table 1.3-4). Most of these households (87 percent) are in Saint Paul, including the City’s east-side neighborhoods that the Project would serve. The following narrative assumes that people who depend on transit would access the Project directly or via other existing transit service; for this reason, the data presented are for the communities within the Project area only and not the community that does not currently have transit access to the Project area. In these communities, the number of zero-vehicle households is 3.2 percent greater than for the Twin Cities Metropolitan Area as a whole. This is due to significantly higher-than-average numbers in Saint Paul, Maplewood and Landfall. People who are transit-dependent rely on transit for most or all of their travel needs17 including work, shopping and social trips. Such trips can occur throughout the day and throughout the week, including in the evenings or on weekends when transit service is often infrequent. The peak-hour express service in the I-94 corridor today does not serve people whose jobs are outside of the traditional workday. People who depend on transit are more likely to require transfers to complete their trips.18 Thus, the limitations in the existing transit service described in Section 1.3.2.1 are particularly acute for these populations. The number of zero-vehicle households (see Figure 1.3-7) illustrates the transit dependence of the communities in Ramsey and Washington counties. The percentage of the population that is low-income is also higher in these communities than it is in Ramsey County, Washington County and the Twin Cities Metropolitan Area (see Table 1.3-4). Of these communities, Landfall and Saint Paul have the highest percentages of low-income individuals at approximately 35 percent and 22 percent, respectively. The section addressing environmental justice in the Community and Social Resources Technical Report in Appendix A provides a more detailed discussion of low-income communities.

17 Delbosc, Alexa. "Transit Dependence." Encyclopedia of Transportation: Social Science and Policy. Ed. Mark Garrett. Vol. 19 Thousand Oaks, CA: SAGE Publications Inc., 2014. 1434-36. SAGE knowledge. Accessed December 2015. 18 Thompson, Gregory, Ph.D.; Brown, Jeffrey, Ph.D.; Bhattacharya, Torsha; Jaroszynski, Michal. “Understanding Transit Ridership Demand for a Multi-Destination, Multimodal Transit Network in an American Metropolitan Area: Lessons for Increasing Choice Ridership While Maintaining Transit Dependent Ridership.” Mineta Transportation Institute Report 11-06. 2012. Available at: http://transweb.sjsu.edu/sites/default/files/1003-multi-destination-multimodal-metropolitan-area-transit- riders.pdf. Accessed December 2015.

SEPTEMBER 2019 A1-25

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

TABLE 1.3-4: VEHICLE OWNERSHIP AND INCOME IN THE PROJECT AREA COMMUNITIES

% of Total Households Low- % Low- Total Occupied Zero-Vehicle with Zero Income Income Area Population Households Households Vehicles Population Population Ramsey 531,528 207,327 22,107 10.7% 82,252 15.9% County Washington 248,745 91,282 2,926 3.2% 12,496 5.1% County Saint Paul 297,160 112,571 15,688 13.9% 62,405 21.6% Maplewood 39,678 15,153 1,385 9.1% 3,574 9.2% Landfall 793 297 26 8.8% 272 34.8% Oakdale 27,956 11,274 594 5.3% 1,753 6.3% Woodbury 66,699 24,283 404 1.7% 2,192 3.3% City Total 432,286 163,578 18,097 11.1% 70,196 16.6% Twin Cities Metropolitan 2,978,822 1,157,541 91,186 7.9% 302,192 10.3% Area a Defined as all persons living below the poverty line. Source: U.S. Census Bureau19

19 U.S. Census Bureau. 2012-2016 American Community Survey 5-Year Estimates. Available at: https://factfinder.census.gov/faces/nav/jsf/pages/index.xhtml. Accessed November 2018.

SEPTEMBER 2019 A1-26

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

FIGURE 1.3-7: ZERO-VEHICLE HOUSEHOLDS IN THE PROJECT AREA COMMUNITIES

SEPTEMBER 2019 A1-27

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

1.3.2.5. Local and Regional Objectives for Growth and Prosperity Summary: Without improved transit service, Project area communities have limited abilities to implement local and regional policies that encourage multimodal transportation, transit, compact development and environmental preservation. Local, county and regional governments in the Project area have established planning frameworks for growth that emphasize multimodal transportation systems, encourage transit, and support maintaining and improving environmental quality.

REGIONAL PLANS As the greater Twin Cities regional government, the Council developed the Thrive MSP 2040 plan to guide the orderly economic development of the seven-county region. The plan focuses on five outcomes that reflect a regional vision: stewardship, prosperity, equity, livability and sustainability. The plan calls out specific ways in which the Council should leverage its authority to support each of these outcomes. Many of these put emphasis on transit and TOD including the following: • Pivot from expanding to maintaining our region’s wastewater and highway infrastructure (stewardship outcome) • Leverage transit investments with higher expectations of land use (stewardship outcome) • Plan for and invest in infrastructure, amenities, and quality of life needed for economic competitiveness (prosperity outcome) • Create real choices in where we live, how we travel and where we recreate for all residents, across race, ethnicity, economic means and ability (equity outcome) • Provide housing and transportation choices for a range of demographic characteristics and economic means (livability outcome) • Align resources to support TOD and walkable places (livability outcome) • Operate the region’s wastewater treatment and transit systems sustainably (sustainability outcome) Building upon these and other outcomes, Thrive MSP 2040 establishes four policies to guide growth in the region: 1. Accommodate growth in a flexible, connected and efficient manner

2. Plan and invest in multimodal transportation choices to slow the growth of traffic congestion and serve the region’s economic needs

3. Encourage expanded choices in housing locations and types and improved access to jobs and opportunities

4. Conserve, protect and enhance the region’s vital natural resources

SEPTEMBER 2019 A1-28

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

COUNTY PLANS Ramsey and Washington counties’ land use and transportation plans include policies and other language emphasizing transit and TOD. Table 1.3-5 gives key examples. Draft comprehensive plan updates for the Ramsey and Washington County have been submitted to the Council and are currently under review and are not in effect.

TABLE 1.3-5: COUNTY PLANS FOR GROWTH AND TRANSPORTATION

Plan Language/Content Ramsey County 2030 Adopts the policies outlined in the Council’s 2030 Regional Development Framework21 and further promotes Comprehensive Plan20 multimodal transportation and transit solutions including TOD and compact growth strategies. Specific citations are paraphrased below.

 Page A-4: Policy 2. Plan for and invest in multimodal transportation, factoring the full range of costs and benefits, to slow congestion growth and serve the region’s economic needs  Page A-6: Goal. Promote multimodal transit and transportation solutions that effectively serve our citizens  Page B-5: Transportation. Ramsey County will:  Encourage compact development that will provide a mix of housing, jobs, and services within easy walking distance  Cluster jobs and commerce  Design developments to accommodate walking, biking or transit use, which balances automobile and alternate forms of transportation. Due to the relationship between land use and transportation, Ramsey County and the municipalities should plan for future growth and transportation needs together.

20 Ramsey County. Ramsey County 2030 Comprehensive Plan. Adopted 2008. Available at: https://www.ramseycounty.us/sites/default/files/Open%20Government/Ramsey%20County%202030%20Comprehensive%20Plan%20%28Nov.%202009%29.pdf.. Accessed October 2018. 21 Metropolitan Council. 2030 Regional Development Framework. Amended December 14, 2006. Available at: https://metrocouncil.org/Planning/Publications-And- Resources/2030-Regional-Development-Framework.aspx. Accessed November 2018.

SEPTEMBER 2019 A1-29

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

Plan Language/Content Washington County 2030 Includes a series of policies and strategies aimed at effectively planning for and implementing transit (Policies 3-18, 4- Comprehensive Plan22 8, 4-9, 4-11) and encouraging TOD (Policies 3-10, 4 12). The plan identifies the I-94 corridor as a potential future transitway, with reference to the Gateway Corridor Alternatives Analysis study. The following citations are paraphrased:

 Policy 3-10: Encourage TOD, pedestrian-oriented, neotraditional, suburban-style growth that uses land in an efficient manner in locations that connect to transportation and transit systems  Policy 3-18: Support land use patterns that efficiently connect housing, jobs, transportation, transit, and retail and commercial centers  Policy 4-8: Support the delivery of appropriate levels and types of transit service to match the specific needs of the county, based on its unique values, geography, economy and socioeconomic profile  Policy 4-9: Coordinate investment in transit infrastructure with land use and transportation planning  Policy 4-11: Advocate and promote long-term investments in transit infrastructure that increase operating efficiency, lower operating costs and increase ridership  Policy 4-12: Support land use policies and densities that promote the development of transit-supportive districts to focus transit service and capital investment

22 Washington County. Washington County 2030 Comprehensive Plan – A Policy Guide to 2030. Adopted 2010. Available at: https://www.co.washington.mn.us/DocumentCenter/View/131/CP-Final-Book-02-14-11?bidId=.%20. Accessed October 2018.

SEPTEMBER 2019 A1-30

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

CITY AND OTHER LOCAL PLANS Local land use plans for the communities within the Project area identify areas for compact growth along existing transit corridors, including I-94, and emphasize regional and local connections as critical to economic competitiveness. Maintaining and improving environmental quality is a local priority within the communities within the Project area. Table 1.3-6 summarizes and paraphrases relevant elements of local plans. Draft comprehensive plan updates for the cities of Saint Paul, Maplewood, Oakdale and Woodbury have been submitted to the Council and are currently under review and are not in effect. The City of Landfall Village 2040 Comprehensive Plan was adopted in September 2017.

TABLE 1.3-6: COMMUNITY LOCAL PLANS FOR GROWTH AND TRANSPORTATION

Plan Language/Content City of Saint Paul  Land Use Comprehensive Plan  Designate the following uses along the Project area: downtown, mixed use corridor, residential corridor, transportation, (Adopted February industrial, opportunity sites, and neighborhood centers. The strategies below describe Neighborhood Centers and 23 2010) Mixed Use Corridors more specifically in terms of their relationships to transit and TOD.  Strategy 1.2: Permit high-density residential development in Neighborhood Centers, Mixed Use Corridors, the Central Corridor, and Downtown. For Mixed Use Corridors, the City should permit residential development of 30-150 dwelling units per acre, including Neighborhood Centers within Mixed Use Corridors. Residential development in Downtown should be permitted at a density of 35-200 dwelling units per acre.  Strategy 1.12: Balance the following objectives for Neighborhood Centers through the density and scale of development: accommodating growth, supporting transit use and walking, providing a range of housing types, providing housing at densities that support transit, and providing open space and recreational opportunities  Strategy 1.14: Plan for growth in Neighborhood Centers  Strategy 1.28: Promote conditions that support those who live and work along Mixed Use Corridors, including frequent transit service, vibrant business districts and a range of housing choices

23 City of Saint Paul. “Comprehensive Plan – Adopted February 24, 2010”. Available at: https://www.stpaul.gov/departments/planning-economic- development/planning/citywide-plans. Accessed May 31, 2018.

SEPTEMBER 2019 A1-31

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

Plan Language/Content  Transportation  The plan aims to “provide balance and choice,” “support active lifestyles and a healthy environment,” and “enhance and connect the city.” As a part of these strategies, the plan notes that regional and local connections are critical to the City’s competitiveness. The plan calls out the Union Depot as a critical hub for growing transportation connections.  Page T-11: The map illustrating Saint Paul’s preferred transitway network identifies the I-94 corridor as a transitway  Strategy 2-6: Calls for Saint Paul to work with other agencies to study and implement new limited-stop, express service, BRT or rail service where ridership or future land use potential warrants City of Maplewood  Land Use Comprehensive Plan  Page 5-4: Goal 6-8: encourage coordinating land use planning with transportation and intensifying development along 24 (Adopted January 2010) existing transit corridors, while maintaining and upgrading environmental quality  Transportation  Page 8-5: Transit Policies: » Maplewood will work with regional transit agencies to help secure transit service that better serves the needs of the residents of the City » Maplewood supports Metro Transit’s construction of new or improved bus stops and shelters » The City supports efforts by Metro Transit to ... improve off-peak service and improve express service to Saint Paul and Minneapolis » Maplewood supports efforts by other agencies to improve transit service in the City by the addition of transitways on the arterial roadways. The City will encourage higher-density economic development and redevelopment near corridors where transitways are added to arterials » The City should coordinate its sidewalk and trails plan to encourage walking, biking, and bus usage

24 City of Maplewood. “2030 Comprehensive Plan”. Adopted January 25, 2010. Available at: https://maplewoodmn.gov/DocumentCenter/Index/110. Accessed November 2018.

SEPTEMBER 2019 A1-32

Purpose and Need Technical Report PURPOSE AND NEED METRO Gold Line Bus Rapid Transit Project

Plan Language/Content City of Landfall Village  Housing 2040 Comprehensive  Policy 3: “It is the policy of the City of Landfall Village to protect its natural resources and environment while 25 Plan (September 2017) maintaining housing affordability.”  Policy 6: “It is the policy of the City of Landfall Village to offer access to transit for all residents.”

2030 Oakdale  Land Use and Redevelopment Comprehensive Plan  Land Use Goal 2, Redevelopment Goals 1 and 2: Direct development where opportunity exists in a way that conserves 26 (May 2010) and protects environmental features and amenities  Page 7-19: Redevelopment/Transit Access, “When possible, connections to transit facilities should be made to enhance accessibility”  Transportation  Goal 3 promotes an integrated approach to transportation and land use planning  Page 8-19: The transit section identifies potential local incentives to encourage transit, as well as park-and-rides and car/van pool lots City of Woodbury 2030  Vision and Guiding Principles Comprehensive Plan  Woodbury’s Guiding Principles include, “provide for a safe and healthy community,” “manage growth,” and “plan for an 27 (July 2010) effective transportation system”  Land Use  High-density residential and mixed land uses are directed to areas transit serves  Transportation  The plan identifies the I-94 corridor as important to Woodbury’s transportation system and development, and as suitable for LRT or BRT to the east

25 City of Landfall Village. “2040 Comprehensive Plan”. September 18, 2017. Available at: http://citcms.cityoflandfall.com/FileUpload/2040%20Comp%20Plan%20Update%2009182017.pdf. Accessed November 2018. 26 City of Oakdale. “2030 Oakdale Comprehensive Plan”. May 2010. Available at: https://www.ci.oakdale.mn.us/DocumentCenter/View/183/Table-of-Contents-PDF. Accessed November 2018. 27 City of Woodbury. “2030 Comprehensive Plan”. Adopted July 2010. Available at: https://www.woodburymn.gov/departments/planning/current_comprehensive_plan.php. Accessed November 2018.

SEPTEMBER 2019 A1-33

Purpose and Need Technical Report GOALS AND OBJECTIVES METRO Gold Line Bus Rapid Transit Project

1.4. Goals and Objectives Goals and objectives articulate the desired benefits of the Project and establish a foundation for evaluation measures including quantitative and qualitative criteria for comparing the No-Build and Build alternatives. The following goals (see Table 1.4-1) provide a framework for evaluating the Project alternatives: • Goals 1 and 2 (Tier 1 goals) identify the minimum requirements that the Project would expect an alternative to meet for continued consideration • Goals 3 through 5 (Tier 2 goals) reflect broader community goals and may be helpful in comparing alternatives that meet the Tier 1 goals. These goals, along with the identified Project needs, provide the basis for the analysis of alternatives discussed in the EA.

TABLE 1.4-1: PROJECT GOALS AND OBJECTIVES

Goals Objectives Measures Tier 1 Goals Goal 1: 1 Maximize number of people  2040 population and employment Improve Mobility served (future) within ½-mile of stations  Number of zero-car households within ½-mile of stations in 2040 2 Maximize transit ridership  Weekday transit trips  New transit trips  Total corridor-wide transit trips 3 Maximize travel time savings  Performance against regional guidelines  Travel times during the morning peak hour compared with single-occupant vehicle and express bus service 4 Minimize traffic mobility  Changes in local street capacity and impacts accessibility (intersection restrictions, lane reductions, traffic diversions) Goal 2: 5 Minimize costs and maximize  Capital costs Provide a Cost-Effective, cost-effectiveness  Annual operating and Economically Viable maintenance costs Transit Option  Cost-effectiveness Tier 2 Goals Goal 3: 6 Maximize number of people Population and employment within Support Economic served (existing) ½-mile of stations Development 7 Maximize future development Capacity and likelihood of development opportunities and/or redevelopment in station areas

SEPTEMBER 2019 A1-34

Purpose and Need Technical Report GOALS AND OBJECTIVES METRO Gold Line Bus Rapid Transit Project

Goals Objectives Measures Goal 4: 8 Minimize potential  Acres of surface water (wetlands, Protect the Natural environmental impacts waterbodies and waterways), Environmental Features floodplain and parkland impact of the Project Area  Net new impervious surface  Impacts to potential environmentally sensitive areas (historic districts, wild and scenic rivers, national river recreation areas) Goal 5: 9 Maximize potential benefits to  Consistency with land use and Preserve and Protect and minimize potential impacts transportation plans Individual and on the community  Provide multimodal infrastructure to Community Quality of Life promote transportation alternatives  Number of full and partial property acquisitions  Impact on noise sensitive land uses 10 Minimize adverse parking,  Intersection closures circulation, and safety impacts  Intersections converted to right-in/right-out  Estimated loss of on-street parking  Number of at-grade transitway street crossings

SEPTEMBER 2019 A1-35

Purpose and Need Technical Report GOALS AND OBJECTIVES METRO Gold Line Bus Rapid Transit Project

Page left intentionally blank.

SEPTEMBER 2019 A1-36