<<

E426 Volume 3 (revised)

Data (11) Submitted to the World Bank

World Bank Loan Project: Inland Waterway III Public Disclosure Authorized

XiangjiangWaterway Construction & Development

ZhuzhouNavigation Complex Project

Public Disclosure Authorized EnvironmentalAssessment Summary Public Disclosure Authorized

Hunan EnvironmentalProtection ResearchInstitute ,

January2001 Public Disclosure Authorized

L'LLu" Y Environmental Assessment Summary

Content

1. General

2. Outline of project

3.Present Environmental Situation

4. Impact on Water Environment

5. Ecological Impact

6. Impact on Social, Atmospheric & Acoustic Environments

7. Alternatives Analysis

8. Environmental Impact Analysis of - Section Waterway Dredging & Expansion Project

9. Environmental Impact Analysis of Hengshan Kilo-tonnage Dock Project

10. Public Consultation

11. Environment Management Plan

Attachments:

1. Sketch Map of Xiangjiang Waterway Construction & Development

2. Schematic Diagram of Inundated Area for Zhuzhou Navigation Complex Project

1I- Environmental Assessment Summary

1. General

1.1 Motivation

Xiangjiang River, originating from HaiyangshanMountain of Linchuan County, Guangxi Zhuang Autonomous Region, is the biggest river within Hunan Province and a first-grade branch of River. It runs through Hunan Province from south to north and empties into YangtzeRiver at Chenglingjiof city, with a total length of 969 km and a drainage area of 94,660 km2. Hunan's major industrial cities such as Yueyang, Changsha,Xiangtan, Zhuzhou and are all situated on its riverside. 70% of the large & medium-scale enterprises thereof are sited along Xiangjiang River, therefore, Xiangjiang River is regarded as the economic corridor of Hunan Province.

In 1999, Hunan Provincial Party Committee and Government set forward a strategic target aiming at acceleratingthe priority regional economy development, known as One Point and One Line, and speeding up the economic integration program of three cities, respectivelyknown as Changsha,Zhuzhou and Xiangtan. Zhuzhou Navigation & Power Complex Project is now officially listed in the Government'sagenda. MOC and Hunan Province have included XiangjiangRiver Rolling Development Project - Zhuzhou Navigation & Power Complex Construction into national and provincial early-stageschedule of The Tenth Five- Year Plan. Hunan Provincial Communications Department (HPCD) entrusted Hunan CommunicationsPlanning & Designing Instituteto prepare the Feasibility Study and the Project Proposal in March 1999. Upon the completion of which, HPCD further entrusted Hunan Environmental Protection Science Institute (HEPSI) to prepare Environmental Impact Report of Xiangjiang River Zhuzhou Navigation & Power Complex; Upon the receipt of the assignment, HEPSI promptly established an EnvironmentSubject Assessment Division, which after carefully analyzing the relevant project information, conducted a site survey at Zhuzhou Complex dam & reservoir area, monitored the present regional environment and collected a series of routine monitoringdata regarding pollution source and water quality at the site. On which basis, the Environmental Impact Report of Xiangjiang River Zhuzhou Navigation& Power Complexwas prepared.

Besides the self-raised funds, Zhuzhou Complex Project intends to apply to the World Bank for an $100 million loan. In accordance with the Assessments Categorizing Standards provided in Notification on Reinforcing Environmental Impacts Assessment Administration over International Financial Organizations Funded Construction Projects reference No. [1993] 324 issued by National EnvironmentalMonitoring Division (NEMD), the environmentalAssessment of the Project was categorizedas Type A.

-- 2- Environmental Assessment Summary

1.2 Assessment Objective The preparation of EnvironmentalAssessment is designed to confirm the scale and extent of the impacts on the surroundingenvironments in order to work out practical measures to avoid the adverse impacts and provide technical supports for engineering designs and environmentaladministration.

1.3 Assessment Basis

The policies and regulations governing the environmentassessments are listed as below:

* Environmental ProtectionLaw of People's Republic of China, Water Pollution Prevention Law, Atmosphere Pollution Prevention Law, Noise Pollution Prevention Law,Water & Soil ConservationLaw; * Construction Projects EnvironmentalProtection Control Rules State Council Decree ReferenceNo.: 253; * Notificationon ReinforcingEnvironmental Impacts Assessment Administration over International Financial Organizations Funded Construction Projects NEMD ReferenceNo. [1993] 324; * Hunan Xiangjiang River Drainage Area Water Pollution Prevention Regulations; * Xiangjiang River Waterway Development Zhuzhou Navigation & Power Complex; - Project FeasibilityStudy; HunanCommunication Planning Institute; and * The World Bank, OP4.01 EnvironmentalAssessment.

1.4 Sphere of Assessment This project is composedof two phases: constructionphase and operationphase. The impacted area of the constructionphase is the KongzhouDam site, while that of operation phase covers the entire 96km reservoirbackwater area.

1.5 Assessment Standards

* The executive standards reviewed and approved by Hunan Environmental Protection Bureau for environmentassessment in this project are provided as below: * Water environment assessmentstandard: In accordancewith Water Quality Type 2, 3 and 4 Standards specified in GHZB1-1999 Surface Water environmentQuality Standard. * Atmospheric Environment Quality Standard: Type 2 Standard specified in GB3095-1996 Atmospheric EnvironmentQuality Standard is to be observed for all assessmentareas. * Acoustic Environment Quality Standard: In construction phase, GB12523- 93 Construction Site Noise Limit Value is to be observed; In operation

-- 3 - Environmental Assessment Summary

phase, Type 4 Standard specified in GB3096-93 Urban Noise Limit Value is to be observed for highways at the two sides of the Dam; And Type 1 Standard specified in GB3096-93 is to be observed for present situation assessment. Sewage Discharge Limits: Limit Grade 1 specified in General Sewage Discharge Limits is to be observedfor sewage discharged to water areas of Type 2 & 3 specified in GHZB1-1999. Limit Grade 2 specified in General Sewage Discharge Limits is to be observed for sewage discharged to water areas of Type 4 specifiedin GB8978-1996. 1.6 Objectives of EnvironmentalProtection

* Protect the source of drinking water in the 96km reservoir area. According to the functional plan of regionalwater areas, livingwater sourcesin the reservoir area mainly includetwo places: the intake of HengshanCounty Water Supply Factory and the intake of Shiwan Town Water Supply Factory. * To protect the ecological environment, including the water organisms, vegetation in the assessment area and Kongling'an Tourist Attraction Site, 1km downstreamfrom the Dam. * To protect the residentsin the vicinity of the Dam from noise and dust pollution.

1.7 AssessmentAssignments

The assessmentis conductedby Hunan EnvironmentalProtection Institute (HEPI) assisted by Hengyang EnvironmentalProtection Institute (HYEPI) and Zhuzhou Environmental Protection Monitoring Station (ZEPMS). HEPI is responsible for the preparation of the Outline& the Reportand partial site work while ZEPMS and HYEPI are responsible for the site monitoring and pollution sources data- collecting. HEPI has been engaging in the environmental assessment and management ever since the early 1980's. It has been categorized as National First Grade Unit. Over 50% of the major or secondaryprojects' assessments were conducted by HEPI. 2. Outline of Project

2.1 Overview

Zhuzhou Navigation Complex is located at Kongzhou,within Zhuzhou County in the downstream of Xiangjiang River. This project is categorized as Class IlIl project, and the major buildings are designed accordingto the standardsfor Class ll. The designed flood repetitionperiod is 50 years and the check flood repetition period is 500 years. The site of KongzhouDam is recommendedas the dam site for ZNCP, which is 83 km from HengshanCounty, 24 km from Zhuzhou City, and 96 km from the completed dam site of Dayuandu Navigation Complex. It is located between HengshanHydrologic Station and Zhuzhou HydrologicStation.

-- 4 - Environmental Assessment Summary

Zhuzhou Navigation Complex Project (ZNCP) is an integrated project, which combines navigation, power generation, communications and irrigation. Main buildings in this project consist of sluice gate, power plant house, navigation lock and highway bridge. The total constructionphase is 5 years. It will take 32 months to complete the navigation lock and 36 monthsto put the first generatingset into operation. The total investmentis 1.814 billion RMB, which includes 1.753 billion RMB for the Navigation Complex Project and 0.017 billion RMB for Hengshan Kilo-tonnage Dock Project is and 0.014 billion RMB for Waterway Dredging Projects. 0.1 billion USD will be loanedfrom the World Bank and the balance will be obtained from the Ministry of Communicationsand Hunan Province (i.e, subsidies and self-raisedfund).

According to the plane layout of the dam, power plant is placed on the left branch, with a 12-hole sluice gate, and a permanentnavigation lock on the right branch, with a 14-holesluice gate. The height of dam is 50.8 m and crest length 1068.5 m.

The normal water level of the reservoir of Zhuzhou NavigationComplex is 40.5m and the relative capacity 0.4743 billion m3. It is a low-dam runoff adjustable reservoir. After water is retained, the average surface width of the reservoir is about 600m. Water level at the end of the dam is 3.5-4.5 m lower than the banks and water level at the far end of the reservoir is 10-12 m lower than the banks. This reservoir is of channel-formreservoir, which does not affect the functions of the existing dams and water conservancyfacilities.

In order to meet the growing demand in communications development and operation and managementin Zhuzhou city, a two-lane highwaybridge is built on the dam crest. The highwayconnecting the bridge with 815 Provincial Highwayis about 7km in length. The highway connecting the bridge with Bejing- Expressway is also 7km in length. The two connecting highways are designed accordingto the standards for Class l1l.

The total construction time for this project is 5 years. The first phase will be 3 years, in which the first generatingset on the left branch will be put into operation, the navigation lock on the right branch and the sluice gate on the left branch will be completed.The second phase will be two years, in which the sluice gate on the right branch will be completed.

2.2 Auxiliary Works

2.2.1 Special-purposeHighway

According to the topography of the dam site, requirements of body building construction and the navigation complex layout, temporary special-purpose highwaysshall be built to reach slag yard, dock, sand & stone processingsystem, concrete system, explosive magazine and the road around the weir. Total length

-- 5- EnvironmentalAssessment Summary of these temporaryhighways of cement pavementis 3.7km. There are no environment-sensitivepoints along these highways.

2.2.2 Stone Pit and Slay Yard

Stone Pit: Shanshanwu Stone Pit is primarily determined as the self-provided stock ground, which is 10.5 km away from the dam site, with limestone as its major composition.Thickness of stone layer is 15-20 m. The exploitable area is 15,000 m2 and its reserves is 0.22-0.30 million m3. Ground exploitation method shall be employed. Both stone quality and exploitationconditions are good. In the northeast and southwest of stone pit are settled a few local residents;in the west are oil-tea camellia fields; in the east is a pool. There are no environment- sensitivepoints around the stonepit. The stonepit is connectedto thedam site by a temporaryhighway. SlagYard: There will be a slag yardon eachside of thedam. DachongSlag Yard (on the left side of dam) is mainly reserved for the slag producedduring the first phase of this project. It is about 1.5km away from the dam site.

ChangtangchongSlag Yard, Jipochong Slag Yard and ShangganliSlag Yard are located on the right side of the dam and reserved for slag and solids produced during the second phase of this project. They are far away from the dam site with their averagedistance being about 2.5 km.

2.2.3 Living Quarters and Work Shed

Living quartersfor the staff and the office buildingare proposedto the built on the left bank of Xiangjiang River. Worker's temporary shed and material warehouse shall be built on both banks of XiangjiangRiver. According to the analogous analysis of Dayuandu Navigation Complex Project, the peak population on the site is about 4,000 during construction.

2.2.4 Auxiliary Work-HengshanKilo-tonnage dock

Hengshan Kilo-tonnagedock shall be built as an auxiliary work of ZNCP. It will have only one berth, with its throughput being designed to be 0.18 million ton in 2005 and total investment being 1.692 million RMB. The newly-built Hengshan Kilo-tonnage dock will mainly handle general cargo transportation, especially nonmetal ores as well as cement,fertilizer, and cereals.

2.2.5 Dredging the Waterwaysfrom Zhuzhou to Xiangtan for KilotonShips

Waterwaysfrom Zhuzhouto Xiangtan is 37 km in length,where there are 8 shoals. The waterways shall be dredged so that 1 Kilo-tonnagefleet of 4 ships can navigate from Chenglingjito Hengyang.

-6 - EnvironmentalAssessment Summary

Total investmentis 1.458 million RMB.

2.2.6 Number of Staff and Workers

442 staff and workers shall be needed for this project, which includes 327 staff and workers for the power plant and 68 staff and workers for navigationlock. 3. PresentEnvironmental Situation

3.1 Natural Environment

3.1.1 Geographic Location

The Kongzhou Dam site is 24km upstreamfrom Zhuzhou city, 6 km upstream from Zhuzhou county, 158km downstream from Hengyang city and 96km downstream from the Dayuandu Navigation and Power Complex. There are highways passing on both banks of the proposed dam. It connects with 107 National Highway, Jingzhu Expressway and 1815 provincial Highway. The JingguangTrunk Railway runs on its right bank.

3.1.2 EngineeringGeology

The topography of dam-site is broad. The left bank is conglomeratehillock and the right bank is sedimentaryterrace which can be divided into class 1,11, and lIl. The bottom bedrock elevation of the terrace and ground water table are higher than the normal reservoir level (El. 40.15m), there are reliable abutment joints. There are shoals in the river. The overburden thickness of the silty sand and pebble of the shoals is 10-14m.The pebble overburdenon both sides of riverbed is 2-3m in thickness. The underlyingbedrock of right bank and riverbed consists of purplish red weakly weathered conglomerateand sandy conglomerateand the right bank consistsof muddysilt-stone with conglomerate.The bearing capacityof rocks can fully meet the requirementsof the proposedstructures and it has weak permeability.The bedrock on left and right bank dips towards left and right bank with an angle of 5-20o and the rocks are intact with no serious fracture zones. Gravel bed in the riverbed and right terrace has good hydraulic permeability. Therefore, special permeation-proofmeasures shall be taken. The bed rock is exposed on its left bank. The side slope is stable. The right bank also exists outcrops nearwater body.

3.1.3. MeteorologicalFeatures

Climate is mild within the reservoirarea and four seasons are sharply contoured. It has sufficient heat. The annual average temperature is 16-18C and the extremely highest temperature is mostly over 38C and the extremely lowest temperature is below-6C.The rainfall is plentiful in this area with annual average plenty of 1423.3 mm. It rains mostly betweenApril and June, which covers nearly

-- 7 - EnvironmentalAssessment Summrwy

45% of total rainfall in a year. It becomesdry from July to September,during which the rainfall covers 18% of total rainfall in a year. There is little rainfall from Oct. to the next Mar. and the days with rains are 140-180days. Most rainfall is distributed to mountain area and few to hill and plain area.

The annual average relative humidity in the region is about 77%-85%.The area is affected by the north wind or northeastwind in the whole year due to the seasonal wind. The averagewind speed is 1.7-2.7m/s, however,south wind prevails in July and August. The prevail wind direction is NW in this area.

3.1.4 HydrologicFeature of XiangjiangRiver

Trunk stream of the Xiangjiang River is 969 km in length. It runs through Hunan Province with a length of 670km. The length between Hengyangand Zhuzhou is 182 km, belongingto the upper part of lower reaches of the XiangjiangRiver. The drop is 15m in dry season and the average gradient is 0.0824%.

* Runoff Features Rainfall is the major replenishmentfor the river in the region, where the laws of the runoff is very similar to that of rainfall with widely changes and uneven distributionin a year. Every year, usually,the flood occurs from April to June and there is few rainfall from July to August and from Octoberto the Februaryof next year. As a result, two drought periods appear, namely,dry autumn and drought winter. * Floods Features Floods in the Xiangjiang River are caused by rainstorm. Usually, it is the flood period from April to September every year and the most serious floods appear between April and July, especially in May and June. According to the statistics between 1956 and 1998 collected by Hengshan Hydrologic Station, the most annual serious floods, which take place in May and June covers 66% of total amount. The duration of eachflood usually lasts for 10 days and the flood patterns is fat with single peak in most cases. * Flow The annual average runoff at the dam site is 52.3 billion m3. The annual average flow rate is 1,680 m3/s, the maximum annualaverage flow rate 2,500m3/s and the minimum annual averageflow rate 730 m3/s.

The maximum flow measured at Hengshan Hydrologic Station (June 18,1994) was 20,200m3/s and the minimumflow rate was 58.2 m31s. * Hydrologic Featuresof River Mishui River is the first-grade branch of the Xiangjiang River, entering into the Xiangjiang River at the place 2.5km downstream from Dayuandu. Its drainage area is 9,500 km2 and its length is 230 km. It runs through Hengdong county, Youxian county,, and Yanlingcounty with an annual average runoff rate of 245 m3/s.

-- 8- EnvironmentalAssessment Summary

3.2 Social Environment

3.2.1 Townsand PopulationDistributions

Zhuzhou Navigation and Power Complex involves 182km-long Xiangjiang river section from Hengyangto Zhuzhou. The area includes such cities as Hengyang, Zhuzhou,Changsha and Xiangtanwith an area of 43,560 m2, which covers 19 per cent of the area of Hunan Province. According to the statistics, population in above-mentionedarea is 19.195 million,which covers 29.5 per cent of population in Hunan Province.

The inundationarea due to the Zhuzhou Navigationand Power Complex involves 14 towns and one company in Zhuzhou county, Hengdong county, county, and Xiagntan county. The population in the region is 0.2965 million (accordingto the agriculturalpopulation in 1998).The populationis mainly of agriculture. There are few rural resident quarter and urban population. The natural population growth rate is 2.45-5.74%o. The average population density is 324 person/km2. The total land area is 915.96 km3.

3.2.2 Social and EconomicSituation

The river section between Hengyangand Chenglingjiis 439 km in length. It is rich in rainfall, flat in gradient and stable in riverbed. Therefore, there are excellent natural conditions for developing water transport. Regions along the river are beautiful and rich in resources and advanced in agriculture and industry. Changsha,Xiangtan, Zhuzhou and Hengyangare located in the central region of the Xiangjiang River between Hengyang and Zhuzhou. Regional gross domestic product (GDP) is 130.616 billion RMB, which constitutes 40.67 per cent of total GDP of Hunan Province. It is an important economic, culture and science and technology gallery in the province and is a center in political, economy and culture.

Rural economy is flourishing in the reservoir area, including agriculture industry, and building construction and animal husbandry.Agricultural income constitutes 46 per cent of total income and nonagriculturalincome constitutes 54 per cent of total income. Crop cultivation prevails in the agricultural economy, which constitutes 62 per cent of total agricultural value of out-put. Animal husbandry income constitutes 26 per cent of total agricultural value of out-put. According to the statistics in 1998,average grain yield is 839 kg/peasantfor 14 town within the reservoir area. Total area of farmland is 0.3687 million mu and average farmland area is 1.24 mu/peasant. Maximum average value is 1.38 mu/peasant and minimumaverage value is 1.04 mu/peasant.

3.2.3 Cultural Relics & TourismResources

Accordingto the investigationsin site and the date collected,there are no cultural

9- EnvironmentalAssessment Summary relics and historical sites in the area of river Channel, which need protection. Konglingan is located at the upstream with 1km away from dam site. It is the tourism spot of Zhuzhou city with the annualtravelling people about ten thousand.

3. 3 Water Environment

3.3.1 Water Quality

According to the present situation of regional water pollution and main pollution sources, following parameters were monitored in the project area in 1999: permanganateindex, BOD5, PH, SS, ammonia & nitrogen, DO, petroleum, total phosphorus,volatile phenol, S2- and heavymetals. The monitoringresults show that all parametersbut petroleum,total phosphorusand ammonia & nitrogen meet the relevant water quality standards. For petroleum, all sections except for S. (Zhuting)exceeds the standard.Total phosphorus surpasses the standard at each section monitored.Ammonia nitrogenexceeds the standard at S2 (Mishui River),

S 4 (Shiwan Town)and S.; As viewed from maximumvalue, pollution in Hengyang segment is more serious than that in Zhuzhou segmentwithin the reservoir area.

3.3.2 Boftom Sludge

The quality of bottom sludge was monitoredfor Total Cr, Pb, Cd, Cu and total Hg, together with water quality monitoringin December1999. The monitoringresults, assessed accordingto GB 4284 PollutantsControlling Standard in Sludge, show all of elements meet the standards,except for Cd at the mouth of the Mishui River, which are 35% higherthan standard.

3.4 EcologicalEnvironment

3.4.1 Vegetation Distribution

The reservoir area is typical subtropical hilly land. Elevation is about 80-200m. Acid red soil prevails.There is also partial purple soil. Forest in this area has been destroyed until recent years. There are no rare plants in the evaluated area. The main vegetation includes: abbor, economictrees, shrub plants. In addition, there are farmlands along the river where vegetable, all kinds of melon or gourd, rice, corn and bean etc are grown.

3.4.2 TerrestrialAnimal in ReservoirArea

Because reservoir area belongsto typical subtropicalplot, there are very few big wild animals, of which, medium and small type animals are simple. No rare animals are found there. Main wild animals include wild rabbit, field mouse, frog, snake and bat etc. Domesticanimals includewild rabbit, field mouse, frog, snake and bat etc. Domestic animals and birds include dog, pig, cattle, chicken, duck, rabbit and goose etc, where dog, cattle and pig constitute most percentage.

-- 10 - EnvironmentalAssessment Summary

3.4.3 Aquatic Organisms

There are many kinds of fish in XiangjiangRiver. According to the statistics made by Hunan Water ProductResearch Institute, there are 149 kinds of fish, which can be divided into 11 orders, 26 families and 86 genera. Followinglists the main fish in the trunk stream of Xiangjiang River, black carp, grass carp, silver carp, variegated carp, silver xenocypris, carp, crucian carp, loach, gudgeon and macular hemibarbus,within the assessedreservoir area, carp-familyfish prevails, then serranid. According to the investigation by fishery department, fishing amount of black carp, grass carp, silver carp and variegated carp constitutes about 40 per cent of total fishing amount. 4. Impacts on Water Environment

4.1 Impacts on Water Environmentduring ConstructionPhase

4.1.1 Impact of DomesticSewage

This project is a large-scale project. During construction,the living quarters are located nearby the dam site. The population can reach about 4000 at peak-time during constructionPhase. If averagedomestic sewage dischargeis estimated to be 10OL/person/day, total domesticsewage discharge will be 400 t/d. According to the investigation on similar projects, after the sewage is treated by the settling tank and the septic tank, the content of each pollutant is lower than those in municipal sewage. Usually, COD concentrationis about 50-100 mg/l and BOD5 concentration 30-60 mg/L. Domestic sewage at construction site after being centrally treated can meet the discharge standard. Domestic sewage has little impact on XiangjiangRiver during constructionPhase.

4.1.2 Impact of ProductionSewage

Settlingtanks must be set up to treat the dreg dressing wastewater,Water can be reused after settlement. Dreg dressing wastewater is not discharged after treatment, thus it has little impact on the river. Concrete flushing and curing wastewater will also produce SS pollution. Howeverthe quantity of this kind of wastewater is very small, it has little impact on XiangjiangRiver.

4.2 Impact on HydrologicSituation during OperationPhase

4.2.1 Impact on Water Temperature

When the reservoir reaches the normal impounded level, the total storage capacitywill be 4.7X103m 3 , and the average flow at the dam site is 1670m3 Is. That is to say, the water in the reservoir can be replaced every 3.3 days. The water depth at the dam site is 10m. It is of the typical low-dam run-off-river

-- 11- EnvironmentalAssessment Summary

regulating reservoir. Water temperature structure in the reservoir area of this project is of mixed type. Therefore,the naturalwater temperaturestate will not be affected by the dam construction.

4.2.2 Impact of Project on Hydrology

The reservoir of ZNCP will be controlled together with Dayuandu Navigation Complex. During the flood period, when the reservoir inflow at Hengshan Station is less than or equal to the maximum outflowof PowerPlant, level of reservoirwill remain normal and power will be generated by natural water. When the inflow is higher than the maximum oufflow, gate shall be gradually opened to relieve the flood. When water head in PowerPlant is less than 3m, shutdownshall be carried out. At this time, the navigation complex is fully used to relieve the flood. During the drought period, when the river segment in the downstreamof the dam site is not deep enough for navigation,Dayuandu NavigationComplex will be controlled to compensatethe navigableflow. Navigableflow for Zhuzhou and Xiangtan are 245 m3 /s and 270 m3 /s respectively. After Dayuandu and Zhuzhou navigation complexesare completed,the flow can be adjusted in the drought period. At that time, flow in the segment between Zhuzhou and Xiangtan can reach 342-366 m 31s.

From above, it shows that ZNCP has no impact on downstream hydrology. In special cases, water flow can be controlledby Dayuandu navigation complex. If gate is opened for flood relief, there is no impact on the hydrologyand the safety of dam site.

4.3 Impact on Integral Water Quality in Reservoir Area during Operation Phase

4.3.1 Predictionof Impact on OverallWater Quality Future water quality (year 2015) in the reservoir was predicted through the complete-mixedmodel. As shown in Table 4-1, even in the worst case scenario (dischargewithout treatment in drought period), the water quality still meets the relevant standardsexcept for Total Phosphorus.

Table4-1 FutureOverall Water Quality in ReservoirArea in 2015 (Unit:mg/I)

NormalPeriod DroughtPenod ClassII Item Discharge Discharge Dischargeup stanrnenZI up without to Standard Dscharge without GGZBI- to Standard Treatment Treatment 1999 Ammonia& Nitrogen 0.366 0.382 0.393 0.476 0.5 VolatilePhenol 0.001 0.001 0.001 0.001 0.002 Total Phosphorus 0.111 0.113 0.112 0.123 0.1 S2- 0.002 0.006 0.003 0.025 0.1 COD 2.00 2.05 2.21 2.50 4 SS 8.0 8.1 8.2 8.6 CN- 0.002 0.002 .02 0.002 0.05

-- 12 - Environmental Assessment Summary

4.3.2 Predictionof Oil PollutionImpact in ReservoirArea

Based on the present monitoringresults, we understandthat the oil content in the reservoir area during the drought period is 0.067mg/l, 34% higher than the standard (0.05mg/I). The oil pollution dischargingsource is very few at the reservoirarea for the 96km of Xiangjiang trunk stream. The major oil pollution comes from the discharges from vessels and oil pollution brought about by Xiangjiang Upstream and its branch Mishui River.

1) Impactof Vessel PollutionStandard Dischargeon ReservoirArea

The background value of oil pollution of the water in reservoir area is 0.067mg/l during drought period in 1999. Xiangjiang River is a major river, 90% guarantee flow rate at the dam site during drought period is 320m3/s. Vessel pollution discharging activity is in a random manner. One-dimensionalwater quality model will be used in the prediction,the results of which is provided as below:

In 2005, the external dischargingoil pollutionwill be 12.18t/a,3.65t/a higher than that of 1999. Including the background value, the oil pollution content will be 0.0674mg/l in the reservoirarea.

In 2015, the external dischargingoil pollutionwill be 16.95t/a, 8.42t/a higher than that of 1999. Including the background value, the oil pollution content will be 0.0679mg/lin the reservoirarea.

2) Impact of Vessel Pollution Discharge without Prior Treatment on Reservoir Area

The impact of vessel pollution dischargewithout prior treatment on reservoir area is predicted as below:

Including the background value, the oil pollution content will be 0.1204mg/l in 2005 and 0.1415mg/Iin 2015.

From the above, we understandthat the vessel pollution discharge without prior treatment will cause certain impact on the water in the reservoir area. Therefore, the navigation administrations and the environmental protection units must reinforce control over vessels in order to ensure a standard discharge from all vessels.

4.4 Impact on Water Intake during OperationPhase

4.4.1 Impact on DrinkingWater Intake in HengshanCounty

-- 13 - EnvironmentalAssessment Summary

Organic pollution is the dominant in the assessed area of Xiangjiang River. Accordingto the presentwater quality and main pollutionsources, COD and total phosphorus are determinedfor prediction. A chemical company for pesticide is located in the upstreamof drinkingwater intake of HengshanCounty and is about 7 km away,which is the dominantpollution source in the assessed river segment. The supply of pesticide has exceededdemand in recent years, so this company will not expand. So it is predictedthat sewagedischarge in 2005 and 2015 will be the same as presentcondition.

Taking average value of monitoringresults of S3 section as background value-- 2.16 mg/l of COD and 0.131mg/l of Total P, COD will not exceed the limit at water intake of Hengshancounty in 2015, but total P will exceed in all conditions.

Table4-2 PredictedWater Quality at HengshanWater Intake Unit: mg/f Item Dischargeafter treatment Discharaewithout treatment Normal Low-water NormalPeriod Low-water Standard Period Period Period COD 2.17 2.24 2.38 3.24 4 Total-P 0.131 0.138 f0.136 0.151 0.1 4.4.2 Impact of Project Operationon Water Intake in ShiwanTown

Accordingto the investigation,domestic sewage is the biggest pollution source on water quality in Shiwan Town. Sewage outlet is located in the upstreamof water intake and is about 1500 m away. Based on economic growth rate of 7%, future water quality in 2015 will meet the standardseven in low water level period.

5. Ecological Impact

5.1 Impact on Vegetation

5.1 Impact on Vegetationduring ConstructionPhase

Dam construction, construction site arrangement, highway construction, substation construction,explosive magazine setup and stock ground construction etc. will occupy the land and destroy the vegetation. According to the site investigation, there are no precious or rare plants within the reservoir area. Vegetation to be affected includes pine, China fir, tea tree, shrub and weeds. According to the preliminary estimate, 124.3 mu of forestland will be occupied, which includes 5 mu of garden plot, 43.8mu of timber forest, 74.1 mu of economic forest and 1.4 mu of bambooforest. Besides,790 mandarinorange tress, 315 fruit trees, 90 economictrees, 2,782 timbers and 852 bambootrees will be destroyed. After the project is completed, the vegetation destroyed by the construction of substation,dam and buildingscan not be recovered,but the rest of the destroyed vegetation can be recovered.Besides, vegetation covering rate nearby dam site

-- 14 - Environmental Assessment Summary can be increased by strengthening plantation and planting turf so as to further reduce the soil erosion. Therefore, impact of constructionon regional vegetation is temporaryand recoverable.

Building removal and reconstruction will occupy some forestland and shrub. Besides, partial vegetation will be destroyed. 99 mu of forest will be inundated by the reservoir. Since Inundated vegetation mainly includes rice, China fir, economic tree and shrub and there is no rare plant, impact of inundation on vegetation source is temporary. Vegetation covering rate can be increased by plantationand planting.

5.2 Impact on AquaticOrganism

5.2.1 Aquatic Life

According to the monitoringdata for the completed reservoirs in Hunan Province (such as Dongjiang), community structure of water life will change from river phase to lake phase after the dam retains water. In addition, algae composition and original productivitywill change with aging of reservoir.Quantity of plankton and water plant will greatly increase. Furthermore, community structure of benthos will change.

5.2.2 Fish

(1) Impact on Fish Quantity

After the project is put into operation, water flow velocity will be lowered, especially in drought period. This is very beneficial to the sedimentation and accumulation of organic decay and nutrient inorganic salt, which created good external conditionsfor the growth and reproductionof water plants and planktonic algae. Quantity of economic fish will be increased in water body within reservoir area due to the increaseof food organismssuch as planktonicalgae and protozoa etc. After the dam is constructed, a stable water space will be formed in the reservoir area (total length is 96km). Water surface area will be changedfrom 48 km2(before water storage )to 58.9 km2 (after water storage). Besides, volume of water body will be changedfrom 0.25 billion m3 to 0.4734 billion m3. Because the drought period of XiangjiangRiver is long, water surface and water body will form a continuous and stable waters for about 8 months after water storage. This will be beneficial to the growth of water life and the natural reproduction of fish, especially to the net fish-farming. In a word after Zhuzhou Navigation Complex is completed, fishery output will greatly increase. This shows that this project is beneficialto the fishery.

(2) Impact of Fish Population

After the project is put into operation,fish populationstructure will change in the reservoir area. Quantity of fishes which like to live in runningwater will decrease

-- 15 - Environmental Assessment Summary and quantity of fishes which like to live in steady water will increase.At that time, crucian carp. carp and bream will be the dominant fish. Black carp, grass carp, carp and crucian carp are of migration floating fishes. Dam construction will change their living environment,which will be not beneficial to their growth and reproduction. Therefore artificial cultivation and net & box fish-farming methods will be used. At that time, quantity of above-mentionedfour fishes will not decrease but increase greatly.

(3) Impact on Fish Reproduction

Water level difference between upstream and downstream of the dam is about 12m. Thus migrationpassageway will be separated,which is not beneficialto fish reproduction. For the river segment between Zhanghepu and Jiaohegou (total length is 75km),it is suitablefor food fishes to spawn due to its geographiclocation and rive characteristics.A great number of food fishes will come to the above- mentioned river segment to spawn during April to June every year. Original fish source protection programfor Dayuanduproject is that a fish passageway(400m in length) will be constructedto settle the problem of fish migration. However, according to the suggestionsof fishery experts, 9-stage channelizationprogram should be taken for the long-termshipping developmentof Xiangjiang.Therefore if fishes want to go to upstreamspawning place, they have to pass several stages, which will seriously consume their physical power and greatly reduce their reproductivecapability. Above all, the ecology will change for the spawning place after channelization. Therefore the above-mentionedprogram has no practical impact. As viewed from long-termplan, artificial cultivationof fry and periodicalfry introductionwill be more effectiveto protect fish resource in Xiangjiang River and . This program can solve the problem of fish resource protection and compensation.After having been approved by the world Bank, this program has been successfully executed in Dayuandu Navigation Complex in 1999, 80 million fries have been introducedinto the river at two times till now.According to the fishery resource survey conductedby water product sectors, ever since the beginning till now, the four domestic fishery resources within the reservoir area have increased instead of declining, thus resulting in an increase in the fishing output. In order not to influencethe fishery resource,kind, quantity and location of fry introductioncan be adjusted accordingto actual situation.

5.3 Impact on Public Health

5.3.1 Analysis of Public Health in ConstructionSite

Population density and mobilitywill be both high during constructionof this project. As some servicescan not keep up with the development,infectious diseases may easily appear and spread, such as plague, malaria etc. Therefore sanitation managementshould be strengthenedon the constructionsite. Specific persons should be appointedto be in charge of sanitationand anti-epidemicwork. Drinking water must be sterilized. Health check should be periodically made for the

-- 16- EnvironmentalAssessment Summary workers. If any infectiousdisease is found, the person must be isolated and cured immediately. Sanitation knowledge should be taught to the workers before construction.

5.3.2 Analysis of Public Health in ResettlementArea

Residents resettlementis directly involved with populationflow and goods flow. Following preventive measures should be taken during migrant arrangement so as to reduce the bad impacton health: * Health check must be made for the emigrants before emigration. If any infectiousdisease is found, the person must be given timely treatment. * Drinkingwater source must be carefullyconsidered, and water quality checked by local environmentalprotection department. * A thorough hygienic work must be done in newly-built settlement, such as eradication of rat and mosquito. * Local public health departmentmust check it out regularlyafter resettlement.

5.4 Impact on Soil Erosion

According to site investigation,Classification Standard for Soil Erosion and Water and Soil ConservationPlanning Report are used for assessment. Slopes of occupied farmland, resident quarter and land for communication are between 0C and 5° , and soil erosion is mini-scale.The erosion modulus is less than or.equal to 200t/ km2 year. However,for the occupiedforest land, flood land and grassland, their slopes are between 50 and 15° , and therefore soil erosion is slight-scale.The erosion modulus is 200-10OOtIkm2year. Backgroundvalue of soil erosion is 351.5t/year in the constructionsite of this project,

Constructionsite is taken as predictionrange and constructionphase is taken as prediction time. Prediction of loss of water and soil is based on on-the-spot investigationand the influenceof constructionon the topography,vegetation and slope according to classification Standard for Soil Erosion. The loss of abandoned slag will mainly be measured through the analogue analysis of the observed data. Accordingto above-mentionedanalysis, if measuresfor soil and water conservation are not taken, volume of soil erosion will be increased by 0.7764 million ton. If soil erosion due to waste yard constructionis not considered, volume of soil erosion will be increasedby 3,677 ton.

6. Impact on Social, Atmospheric& Acoustic Environments

6.1 Impact on Social Environment

6.1.1 Land Acquisitionand Resettlement

-- 17 - Environmentaf Assessment Summary

6.1.1.1 PrincipalTangible Material Indices a) Reservoirarea NPL is 40.5 meters,the reservoirinundation will cover some units and 538 villager groups I 90 villages in 14 townships in Zhuzhou, Hengdong, Hengshan and Xiangtan Counties and Liling City. The principal tangible material indices affected by the reservoir inundation are as below: 1,165 displaced persons, 68,737 M2 of housing area; 20,124 mu (1 ha.=15 mu) of farmland, 99.9 mu of forest land, 886 mu of fish ponds; 2.4 km of Grade IV highway,223 drainage culverts and sluices, 246 pump stations, 17.15 km of transmissionlines at 10 kV or more, and 6.2 km of telecommunicationslines. About 95% of the affectedfarmlands are within Zhuzhou Countyand the affected farmland at EI.38.5mor higher accounts for 83% of the total affected farmland. The affected farmland is relatively concentratedwith minor submergencedepth. Most of the affected farmland may be protected fro inundation by taking appropriate measures. About 99.5% of the affected housing are in Zhuzhou County and 62% of the affected housing is of brick-concretestructure. Most of the affected housing may be protectedby taking consolidationmeasures as only the ground floor is affected. b) Dam area

Due to the dam construction,385 persons and 21,000m2 of housing have to be displaced.727.5 mu of farmland,of which 577.2muis paddy field, will be occupied for the dam construction. c) Hengshandock

The total land area of the Hengshandock is 26 mu. 58 persons in 13 households and 4,121m2 of housing have to be displaced. 19mu of orchards and 2 mu of fishpondswill be occupiedfor the wharf construction.

6.1.1.2 ResettlementPlan a) Reservoirarea

Productionresettlement channels: the protectedfarmland area is 17,339mu.The actual farmland area to be compensatedis 2,785mu.The productionresettlement population in the target year 2003 is 2,189. In order to achieve comprehensive resettlement,1,094.5 mu of paddy field will be adjusted,363.8mu of fishponds will be improved,and 1,825.2muof fishpondswill be newly established. Resettlementfor affected persons: In the planned target year, 1,205 persons will be affected, of which 925 will be within protectedarea, 156 will be provided with housing consolidationor heighteningat the ground floor, and 124 will be moved nearby.

-- 18 - Environmental Assessment Summary

Specialfacilities rehabilitationand protectionworks: Basedon the plan design, 34 bridges capableof passingfarming machineswill be reconstructed,175 drainage culverts and sluices and 204 pump stationswill be improvedor extended,24.2 km of reservoir shore will be protected, 8.06km of telecommunicationlines and 20.3km of transmissionlines at 10kv or higher will be reconstructed,and 3.32km of railway side slopes and 17,339muof farmlandwill be protected. b) Dam area The 385 displaced persons in the dam area are relatively dispersed. The move- back resettlement option will be employed, and the affected persons will be moved out of the constructionredline and resettled in differentareas.

About 457 persons need productionresettlement. It is plannedto return 200mu of construction site to paddy field, and to adjust 324 mu of paddy field for vegetable plantation. c) Hengshandock

The affected 58 persons in 13 householdswill be moved backwardto resettle in the area with the elevationabove the Hengshan-Xuanzhouhighway. 6.1.1.3 ResettlementCompensatory Investment

Calculated based on the 1999 price level, the total resettlement compensatory investmentof the Project is 304.4138million yuan, of which:

a) Reservoir area: Basedon the NPL 40.5m scheme,the static investmentfor the reservoir inundationhandling is 271.6599million yuan.

b) Dam area: The static investmentis 30.6852 million yuan (including 10 million yuan for the Kongzhouislet). c) Hengshan dock: The static investmentis 2.0687 million yuan.

6.1.1.4 Impact of Land Acquisitionand Resettlementon Social Environment

(1) FavorableImpact * To make full use of the superiority in water resource and promote industrial structure adjustment. * To enhance the capabilitiesto cope with natural disasters. * To improve the quality of life for relocatees. * To raise the productiveforce of land by properly developingland resource in resettlementarea.

(2) Adverse Impact * Average farmland area per person is small and back-upfarmland resource is

-- 19 - EnvironmentalAssessment Summary

limited. Reservoir inundation, resettlementand special facilities construction will occupy some land. Therefore, contradictionbetween farmland resource and populationsize becomes more prominent. * During resettlement,village migration,house constructionand special facilities reconstructionwill occupy some land and destroy original vegetation. Surface soil will be peeled and original landform will be changed, which cause soil erosion to some degrees. * Resettlementproblem is very sensitive.Some people have to give up original stable living conditionsand rebuildtheir home village. If resettlementproblem is improperlysolved, it will bring some unstablefactors to the society.

6.1.2 Impact on RegionalEconomic Development

Construction of Zhuzhou Navigation Complex Project will speed up implementationof the strategy,namely giving priority to One point and One Line economic development. After the navigation complex is completed, irrigation conditions will be improvedfor 0.128 million mu of farmland on the both bank of reservoir.Besides, fishery can be developed.Thereby, construction of this project will provide excellent conditions for economic development in reservoir area. This project is an importantpart of XiangjiangRiver Basin plan. It is beneficial to full utilizationof water resource in XiangjiangRiver. This project will further raise the comprehensiveutilization rate of water resourcein XiangjiangRiver.

6.1.3 Impact on CulturalRelic and Historic Sites

According to field surveying and investigation,the historical sites of Kangwang Templeand Jianning Countyand ZhutingjunTown are far awayfrom the banks of Xiangjiang.The tomb of the martyre Mao Zejian is 300 meters away from the bank at the end of the reservoir.Konglin temple is about 1 kilometerfrom the dam of the Complex. The reservoirtakes the shape of a channel.When it is filled with water, the water will be confined within the river course. As the historical sites are far away from the banks, thus the constructionwill have very little impact on them.

6;2 Impact on AtmosphericEnvironment The main air pollution sources during the construction phase are the mixing stations, truck (carrying earth) haulage and loading and dumping sites. The assessment factor is TSP at this period and the analysis is done by the comparisonmethod. The concrete used for the constructionof a dam is chiefly preparedat the mixing stations.So the dust productionis concentratedaround the mixing station, normallywithin a radius of 200m areas.

6.3 Impact on Acoustic Environment

-- 20 - EnvironmentatAssessment Summary

6.3.1 Noise Impact duringConstruction Phase

The noise level reduces to 75dB at a location 30m away from the source. The bigger the distance, the lower the noise level. It is 60dB when the distance reaches 120m and 55dB when the distance goes beyond 200m. Thus the noise level at locations 30m away from the operatingmachines conforms to the daytime standard of "the threshold values of noise at building & construction site" (GB12523-90).At locations 200m away it satisfies the night standard. Since the project locates in the countrysideand there are few noise-sensitivepoints in the region, the noise level is acceptable as long as due attention is paid to overall layout and working schedule.

6.3.2 Noise Impact during OperationPhase

Upon the completion of the Dam, the highway on the crest will be put into use which will certainly bring about traffic noises to some extent, which will be measured according to Specificationof Highway Project Environmental Impact Assessment by the Ministry of Transport. According to the above prediction pattern, the calculatedresults of the noise impact caused by the traffic on the both side of the highwayon top of the Dam are listed as below:

Distance (m) 15 30 50 100 150 Predicted Noise 60.9 56.1 53.2 50.8 48.9 Value (dB(A))

From the above, it shows that in daytime, the noise value 50m away from the highwayon top of the Dam is in compliance,with Class I Standard in GB3096-93 Urban Area Noise Environment Standard. Therefore the traffic noise arising during the operationphase has little impact on the outer environment. 7. AlternativesAnalysis

7.1 Dam Site Alternatives

In the feasibilitystudy of this project,the recommendeddam site has been moved down 22km from Gantianto Kongzhou.

As the distance between Gantian and Kongzhou is only 22 km, so they are located in the same environmental region. Therefore their land and aquatic ecology, vegetation coverage,water losses and soil erosion etc are very similar. There is no distinct difference in environmental compatibility. Therefore, considerationis mainly given to geology,economic benefits and social benefits in the selection of dam site. Through the alternative analysis, it is found that Kongzhoudam site is closer to Zhuzhou City and the channeledwaterway is 22 km longer than Gantiandam site. In addition, installedcapacity of generating sets in Kongzhou is higher than that in Gantian, which will bring about greater

-- 21 - EnvironmentalAssessment Summary economic efficiency. Besides, emigrated population number and inundated farmland area will be smaller and the geologicalin Kongzhouis beKterthan that in Gantian. Either from the perspective of economy or from the perspective of environmentalprotection, Kongzhou dam site is better than Gantian dam site.

7.2 Alternativesof Carrying out he Projectand Not Carryingout the Project

The two alternatives are reviewed from the aspects of society, economy and environmentalprotection. It shows that Alternative I (carryingout the Project) is a better choice than Alternative II (not carrying out the Project)from all aspects with respect to economy, society and environmental protection. Therefore, this Assessment recommendsthe Alternative I known as "carrying out the Zhuzhou NavigationComplex Project". 8. EnvironmentalImpact Analysis of Zhuzhou-Xiangtan SectionWaterway Dredging& ExpansionProject

8.1 Outline of Project

This project is to rectify, expand and newly build the channel (waterway) on the basis of the completed kiloton-class channel (width is 60m). 270,350 m3 of waterway will be dredged for the waterway between Zhuzhou and Xiangtan. 44700 m3 of stone dam will be constructed.4000m 3 of rock will be blasted and 5100 m3 of bank revetmentwill be constructed.Total investmentin this project is 14.58 million RMB.

8.2 Present AquaticEnvironment for XiangjiangRiver Zhuzhou-Xiangtan

8.2.1 Water Quality in ZhuzhouSegment

Concentrationof N-NH3, petroleum and mercury are above standard values at Xiawan section either in drought period or in normal period. Maximum surpassing time of N-NH3 is 10( in normal period), of petroleumis 1.5 (in drought period) and Hg is about 9(in drought period). Only petroleumconcentration is above standard value at Baishi section and its maximum surpassingtime is 1. Pollutionat Xiawan section is more serious than that at Baishi section because Xiawan section is polluted by the wastewaterdischarged from Xiawan Port.

8.2.2 Water Quality in Xiangtan Segment

According to the historical monitoring information, water in this segment is polluted to some degree either in drought period or in normal period. Main pollution factors such as petroleum, N-NH3, Hg and Cd etc are above the standard values. Their surpassingrates range 25-75%.

8.3.3 Bottom Sludge in RiverSegment betweenZhuzhou and Xiangtan

-- 22 - Environmental Assessment Summary

The bottom sludge is monitoredin Dec. 1999,sampled, naturallydried and oven- dried for analysis: the control specifications of contaminants for Agricultural sludge (GB4284-84)is taken as the standardfor the assessment.Compared with the standardvalues, such items as Hg, Cd, As, Pb, Zn in the bottom sludge at the Xiawang section are above the assessmentstandards to some degree. However, the heavy metals in other sections meet the standards.

8.3 Environmental Impact Analysis of Waterway Dredging & Expansion Project

8.3.1 Impact on Commonwater Body

Channel dredging and excavationwill disturb the sludge deposits in water body, which will make water temporarilymuddy. Constructionboats and machinerywill also discharge oils and other pollutants into water body during work and maintenance. Domestic rubbish domestic sewage and dung for constructorswill be discharged into water. Thereby,if it is not properlymanaged, water body will be polluted to some degree. However,because the construction site is dispersed in the river channel with its length of 37km and work is not concentrated at a fixed time, it will not greatlyaffect the water quality of water body,on the other hand, the constructors are dispersed, thus domestic sewage dischargewill have very few impact on water body. Furthermore,the impact is temporaryand recoverable.

8.3.2 Impact on Water Quality in SanitaryZone for DrinkingWater Source

There are eight shoals in the river segment from Zhuzhou to Xiangtan. Seven water intakesfor waterworksare involvedwithin the assessmentarea. Except for water-intakes for Zhuzhou First Waterworks and Zhuzhou Second Waterworks are located in the upstreamof TongLuoShoal, other five water intakesare located within the range of this WaterwayDredging Project.According to the investigation, water quality at each water intake is polluted by petroleum, N-NH3 and COD to some degree. Thereby, importancemust be put on water pollution prevention in sanitary zone for drinking water during the constructionof Waterway Dredging & Extension Project. For that reason, effective measures must be taken to protect the drinking water source. Water source monitoring work must be well done during construction. If any pollution to water quality is found, suitable measures must be taken immediately.

8.3.3 Impact of secondary Pollution of Heavy Metals in Boftom Sludge on Water Quality of Water Body

According to the present situation of bottom sludge pollution in the assessment area of this project, no surpassing heavy metal content is found in the bottom sludge except for Xiawan section. As it is surrounded by alkaline water, the heavy metal content is relativelystable in the bottom sludge with a low solubility,

-- 23 - EnvironmentalAssessment Summary only a very little amount of the heavy metal content was left over in the bottom sludge and had certain impact on the water quality by causing suspending substance. As the aqueous phase of this section shows pH>7, the water is categorized as micro-alkli body. The heavy metals containedin the bottom sludge is in a stable condition, The possibilityof heavy metal dissolution due to bottom sludge re-suspension is very small. Although the heavy metals content in the bottom sludge of Xiawan Section is excessive, the dredging project does not include Xiawan Section, therefore, little heavy metals containedin bottom sludge will arise, thus causing no secondarysuspensions and affectingthe water quality. 9. Environmental Impact Analysis of Hengshan Kilo- tonnage Dock Project

9.1 Outline of Project

Hengshan port is located on Xiangjiang River reach between Hengdong County and Hengshan County, and waterway and inland transportation are well developed. Transport industry is featured by local mineral transportation, especially such nonmetallic mineral as plaster,porcelain clay, albite, potash spar etc. In considerationof the navigablecapacity of Xiangjiang River,the throughput is designed to be 18 X 104 t as per universaldock. One kiloton-classberth will be built. Dock type is of generalcargo dock. The highestwater line is designed to be 52.26m (for 20-year encounteredflood, the same elevationas Huanghai,similarly hereinafter) and the lowest 38.80m (the dead water level of Zhuzhou Navigation Complex). Total investmentfor this program is 16.85 million RMB.

9.2 Survey of Present Regional Environment at Hengshan Kilo-tonnage Dock site

This kilo-tonnage dock will be on the lower reach, around 8km away from Dayuandu dam and the port zone on the lower reach, around 550m away from water intake for Hengshan Waterworks. To confirm the existing water quality, a monitoring cross-section was selected at upstream,around 100m away from the water intake. Ten monitoring factors such as PH, SS, DO and petroleum are included in the monitoringfrom Dec. 4 to 6,1999 (totally three days). The result shows, except for petroleumand total phosphorus,pollutants do not exceed limits. Petroleum on its peak is 4 times exceeding limits, with exceeding rate of 33%, which means this river reach has been polluted by petroleum contaminant that mainly come from transport ships. Thus, petroleum contaminant is one of the most selective control factors for pollution prevention. Total phosphorus on its peak is 0.87 times exceeding limits, with exceedingrate of 66%.

9.3 Impact Analysis of HengshanDock Construction

9.3.1 Impact on Flood Discharge

-- 24 - Environmental Assessment Summary

The proposedconstruction place for the Dock faces a 600m wide XiangjiangRiver reach. Under the highest historicalwater level, flood-relief section area is about 7500 m2. The head of the Dock extends about 28m from the boundary line of river bank, with water-tight area 210 m2 , occupied only 2.8% of total flood-relief area, comparingwith Xiangjiang River Large Bridge on the lower reach, it has a piers water-tight area 600 m2 . Since completion of the Bridge, Hengshan reach of Xiangjiang River has stood up flood tests for years. In contrast, Hengshan Dock construction program has much smaller water-tightarea. To this understanding,it is predicted that construction of this project will not markedly impact flood discharge.

9.3 2 Impact of Oily Sewageon Water Body

Usually, oily sewage from berthed vessels is not allowed to be freely discharged into water body except that it has been treated and up to the effluent standard. The effluent concentrationof oily sewage after treatment is 10 mg/L. If sewage dischargeis counted as 2t per day, dischargeintensity of petroleum pollutantswill be only 20g/d, impactingthe water bodyvery little. Thus, oily sewage impacts very little on the quality of drinkingwater for HengshanCounty. 10. PublicConsultation

According to the World Bank's guideline, two stage public consultation was carried out; namely a) shortly after environmentalscreening and before the terms of referencefor the EA are finalized(First Public Consultation),and b) once a draft EA report is prepared(Second Public Consultation).

10.1 First Public Consultation a. Survey date: End of July 1999 (Outlineof EIA preparationperiod); b. Survey location: Cities and counties along the reservoir area including Zhuzhou city, Zhuzhou county, Hengshan county, Hengdong county, etc.; c. Survey method:Hunan Provincial Environmental Protection Institute and Zhouzhu & Hengyang Municipal Monitoring Stations jointly handing out 180 survey questionnaires,recovering 149; d. Survey object: 30 residentsat the vicinityof the dock site, 50 residents along the river banks, 30 representativesfrom National People's Congress and the Chinese People's Political ConsultativeConference, 10 staff from environmental protection units and 29 staff from governmentalsectors; e. Survey results: Table 10-1 is the public survey opinion results. Table10-1 Resultof First PublicConsultation

-- 25 - EnvironmentalAssessment Summary

Age 20-30 30-50 50-70 Over 70 13% at 20 51% at 76 28% at 44 9% at 9 Occupation Cadre Farmer Worker Teacher 33 (22%) _ 108 (72% 7 (5%) 1 (0.7%) Education College Senior High Junior High Others School School 20 (13%) 40 (26%) 27 (18%) 62 (43%) Opinion on the For Against Ambiguous Reservoir Project 126 (85%) 7 (5%) 16 (10%) Opinion on land Obey Disobey Conditionally acquisition and obey resettlement 75 (50%) 6 (4%) 68 (46%) Beneficiary of the Country Collectives Individual reservoir project 122 (82%) _ 84 (56%) 81 54%) Most serious Noise Ecocide Water Pollution Fish environmental Reduction pollution to people 36 (24%) _57 (38%) 59 (40%) 25 (17%) Proposed measures Plantation Fish fry Reinforcing the Others to minimize the Cultivation dikes and dams impacts 54 (36%) 34 (23%) 68 (46%) 12 (89%

10.2 Second Public Consultation a. Survey date: Upon the completion of EIA draft in July of 2000, the preliminary result was released to the public in reservoir area for opinions; b. Survey location: As the most affected people living in reservoir area, the major survey locations including Panshi Town, Sanmen Town, Zhouping Village and Gantian Town in Zhuzhou County;

C. Survey method: Public consultation meetings being held four times with respect to ZNCP; d. Survey object: The to-be-affected public of this project (local villagers) being asked to provide their opinions and suggestions on the environmental protection in this project, 30 people from Zhouping Village (meeting held on July 18, 2000), 28 people from Sanmen Town (meeting held on July 20, 2000), 22 people from Panshi Town (meeting held on July 21, 2000), 20 people from Gantian Town (meeting held on July 22, 2000) e. Survey results: The attendees of the four meetings totaling 100, most of which in favor of this project and also giving out a variety of opinions and suggestions.

Positive opinions are based on the following reasons: * The project will be beneficial to promoting the regional economic development, expediting the urbanization proceedings and speeding up the development of

-- 26 - Environmental Assessment Summary

tertiary industry as well as the adjustment of industrialstructures in reservoir area.

* This project constructionwill upgrade Xiangjiang River navigation waterway. Besides and be beneficial to the development of waterway transport. At the same time, dam-crest highwaywill connect 107 National Highwayon the east bank with -ZhuhaiExpressway on the west bank and bring convenience for highwaytransport.

Negativeopinions are based on the following reasons: * In their opinions, after the dam is constructed,water flow velocity will slow down within the reservoir area and the natural degradationcapability will also be weakened,which will be adverse to dilution and diffusion of the pollutants. Besides, they showed great concern for the water quality in reservoir area, especially the water quality of drinkingwater source in reservoir area (such as drinking water intake for Hengshancounty).

Public suggestionsand requirements: * The project is expected to be constructed,operated and profitable as soon as possible. * In view of cultivatable land is rare in the construction area, mitigation measures must be taken to reduce inundationon farmland and the number of the resettledas much as possible. * Environmentalprotection shall be sufficiently implementedduring the course of constructionto minimizeecocide and environmentalpollution. * This project may cause the reduction of fishes in Xiangjiang River, compensation given according to the policy or remedies to be taken are suggested. * Along with constructionof the project, land acquisitionshall be well settled by unified planning with due considerationfor all concerned. Full the amount of compensation shall be given to the resettled according to the policy so that farmers can survivetheir land acquisition. * Dam-cresthighway is an importantlink betweeneastern and western regional transport, vehicle flow is great. Since the current design for (9m wide with two-lane) is too narrow and can not meet the demands of transport in rapid development. The Government an the Owner are suggested to widen the dam-crest highwayup to four-lane.

Prior to the finial completionof the EnvironmentalImpact Statement, the above public opinions have been carefully reviewedand referredto in the major chapters and environmentalprotection programs.

11. EnvironmentManagement Plan

11.1 EnvironmentalProtection Measuresfor Zhuzhou Navigation Complex

-- 27 - EnvironmentalAssessment Summary

Project

11.1.1 Design Phase

1) Flood Preventionin the ReservoirArea

Select correctly the site of the dam, the type of the dam, the style of flood discharge, the width of overflow edge and the normal storage level so as to reduce the loss of inundationand avoid influencingflood prevention in reservoir area. In order to reduce the inundated area and not to influence the flood protection in the reservoir area, general layoutand normal storage level has been carefully studied and demonstratedduring project design. Overflow leading edge has been widened. Height of bed sill for overflow gate is lowered as far as possible (near original riverbedelevation). Therefore, a low and open gate dam is formed. During flood discharge, Flow State of flood will approachthe Flow State of natural water. Normal storage level of the reservoiris 40.5m. Water level in the upstreamof the dam will be limitedwithin the flood banks.

2) Embankment Protection

During design phase, topographical survey is required for the embankment protection in orderto confirmthe locationsof embankmentwith potentialhazard of permeation, which shall be treated accordingly. As the water level rises, the water surface becomes wider and the embankmentis immersed in water longer and is exposed to greater influenceof the wavesand water erosion. In the design, measures like laying stones, building slopes and growing grass are taken to harden some soft and cragged banks.

3) Water DischargeFacilities

In the design, the inundatedwater dischargesluice, flood dischargechannels and electrical drainage facilities will be renovatedand improved before water is filled into the reservoir.

4) Field Protection:

Before water is filled into the reservoir,flood discharge channels will be built or renovated, new electrical pumping station built and various plans improved. The follow-up supportivework will be seen to.

5) Ecological Protection

Efforts will be strengthenedin afforestationin the reservoir area to increase the area of vegetation coverage and preventthe loss of water and soil and promote ecological agriculture.

-- 28 - EnvironmentalAssessment Summary

6) Preservationof CulturalRelics

In the phase of designing, the department of relic preservation will make an investigation in the would-be inundated area. If such dangers are detected, measures should be taken immediatelyat the designingstage.

7) Protectionof the Species of Fish

On the basis of the Dayuandubreeding program,the number of fish fry releasing locations and times will be increased.

11.1.2Construction Phase

1) Dust Control

* Concrete mixing plant and cement piling area should be located leeward. Besides,there must be no residentialarea in the neighborhoodwithin 300m. • Roads with heavy traffic shall be watered regularlyto controldust. * Construction machinery must slow down on the roads where dust can raise easily.

2) PreventiveMeasures for Wastewaterin ConstructionSite

* Living quarters for constructorsmust be dispersedso as to reduce the central wastewater discharge. * The site living sewage will be processed at the septic tanks first and then discharged to embeddedsewage processorsfor final emission in compliance with the standards. The concrete residue-flushingwater from the concrete system will be settled at the settlementtanks for recycling, none of which be discharged out. * Machine repairing yard must be located at the downstream of construction site. * Oil-water separator should be installed in the machine-repairingworkshop. Oily wastewatershall be dischargedafter treatment.

3) PreventiveMeasures for Noise Control in ConstructionPhase.

* Noise produced by constructionmachinery. Noise mainly has an impact on the constructors. Work schedule should be properly arranged for the constructorsduring construction.High noise-contacttime should be shortened as far possible. Besides,living quartersfor constructorsmust be far away from high noise work-site as far as possible. * Construction machinery must be rationally selected. Low noise equipment should be used as far as possible. Preventive maintenanceshould be often made for the construction machinery during construction so as to avoid the noise increase due to equipment performance drop. Noise insulation and

-- 29 - EnvironmentalAssessment Summary

elimination measures should be taken for the generators. Besides, the generatorsmust be far awayfrom dense-populationarea. * For the construction machinery whose noise level is above 9OdB(A), for example, pilling machine,pneumatic hammer and rock drill etc, work schedule should be properlyarranged, besides, night constructionshould be reducedas far as possible. * Blast should be performed during daytime. And no blasting is operated from 18:00to 7:00 (next morning).

4) Processingmeasures for residue

* Site living garbageshall be jointly transportedto garbageprocessing station at Zhuzhou for disposal. * Constructionwaste soil and stones can be transportedto and stockpiledat the nearest residue-disposalsite. 3 specialwaste soil stockpilingsites with a total area of 477,900 m2 will be constructedat the both banks of the Dam site.

5) Farm land protectionmeasures

ZNCP will inundate farmland of 20,142 mu at the reservoir area, 17,339 mu of which could be protectedby taking the following proper protection measures:

- To construct drainage channel:the ponding water in farm fields will be drained to the river at the Dam's downstreamthrough drainage channel; * To raise the farm land: farm fields will be raised to over 41.0m; (practical for the areas with low water level discrepancybetween outer and inner banks or the areas with great permeability) * To drain out ponding water: Ponding water inside the farm fields will be forcedly drained out with pumps; (practical for areas with high water level discrepancy between outer and inner banks or the areas with low permeability).

Table 11-1Major ProtectionMeasures for Farmlandat ReservoirArea

ProtectionLocation To-be-Inundated ProtectionMethod Protection area(mu) Area (mu) 1. SanmenTown 5,973 Drainagechannel & 5,358 raising 2. LongchuanPort 1,385 Raisin & draining 1,290 3. ZhutingTown 2,066 Raising& draining 1,634 4. GantianVillage 1,872 Raising& draining 1,619 5. ZhaolingVillage 2,220 Raising& draining 2,095

6) Inundationand SeepageControl Measures

* To protect reservoir banks from seeping or collapsingowing to saturation by rock-layingand plantingat abruptand soft & loose banks;

--30- Environmental Assessment Summary

* To build flood discharging channels in the farm fields within the banks before water-storingat the reservoirand rebuild or build new water-pumpingstations to protect farm lands and irrigationinstallations in case of high water level at the reservoir; * To reinforcethe dikes beforewater-storing of the Dam; * To conduct regular inspectionson the dikes during preliminary water-storing period to preventseeping and ensure prompt repairing.

7) Measuresfor Soil and Water Conservation a) Measuresfor Soil and Water Conservationin ConstructionSite

According to the characteristic of soil and water erosion, vegetation recovery method and reclamation method are adopted. We must consider not only their fitness but also their economy and beauty, such as masson pine, China fir, fragrant tree, camphortree etc. b) Measures for Soil Water Conservation for Waste Yard Retaining Wall Construction:

According to the topography of waster yard, a retaining wall shall be built by grouted stones at the gully. Total length of the retaining wall is 945m and total 3 volume of earthwork is 7620 m . Among them, length of the retaining wall at Changchogtangwaste yard is 660m and total volume of earthwork is about 530 m 3 ; Retaining wall length at Jipochong waste yard is 175 m and its volume of earthwork is about 1220 m3; Besides; length of retaining wall at Dachong waste yard is 11Omand its volume of earthworkis 1100m3.

After all the wastes and solids are dumped. its surface should be leveled and some soils should be put on its surface. We should select suitable trees to plant, such as mason pine, tea tree etc. c) Measures for Soil and Water Conservationin Other Places.

Stone processingsystem and concretemixing system are divided into right-bank system and left-banksystem. For the right-banksystem, after the body project is completed, temporary buildings should be removed and the rubbish should be treated. Beside, the compacted surface soil must be ploughed to be used as farmland again. d) Measuresfor Soil and Water Conservationfor TemporaryRoads

After the project is completed,the pavementand two sides of the temporary roads should be leveled so as to preventsoil erosion and maintainthe regional ecology. Cultivationarea of plants is 37,000m2 and 4,046 trees will be planted.

-- 31- Environmental Assessment Sumnmary e) Residue SettlementTank

Ponding-watersettlement tanks shall be constructedat the three waste soil & stone quarries. Residue wastewater shall be fully clarified prior to being dischargedto XiangjiangRiver in orderto keep it free from residue water pollution. The size and location of settlementtanks shall be determinedas to ensure a full complianceof the dischargingwater with specifications. 8) Cultural Relics Protection

Accordingto the investigation,cultural relics within the project area are located far from the dam site and reservoir bank so that this project has no impact on these cultural relics. However, if any cultural relics are found during construction, excavation will be stopped immediatelyand the local cultural authority will be informed of such discovery. Excavationwill not be resumed until identificationof cultural relics by the authorized institution is completed and necessary preservationmeasures are taken

11.1.3 Operation Phase

1) Water Quality Protection a) Total amount control should be strictly carried out for pollutant load discharged into the reservoir.Overall planningand correspondingregional planning should be worked out to control water pollution in reservoir area. Constructionof enterprises or factories with large quantity of pollutants must be strictly controlled in the reservoir area. For the old pollution sources in reservoir area, pollution control must be strengthened.For some pollution sourceswhich can't be treated, shut- down must be implementedunder the supervisionof competentauthorities. b) Oil-water separatingsystem must be installedon the ships, which drive in the reservoirall the year round. Oily wastewaterdischarge must be strictly controlled. No oily wastewater will be discharged to rivers. All oily wastewater will be transported to processinginstallations along the banks for treatment to ensure a full compliancewith the controlspecifications. c) Environmental protection planning should be well done for relocatees resettlement. Environmental protection investment should be verified, Environmental protection planning should be implemented during relocatees resettlement. It is estimated that the investment on environment protection in migration area such as sanitation protect, water and soil conservation,vegetable recovering,pollution treatment and etc. shall be 1,000,000yuan. As the residents within construction site, totaling 124 people, will be relocated dispersedly, secondary bio-chemical living sewage processing installations shall be established at the new resettlement areas to ensure a full compliance of the sewage discharging with specifications. Meanwhile, garbage collecting station and marsh gas tanks also shall be establishedto processliving garbage.

-- 32 - EnvironmentalAssessment Summary d) Monitoringand research should be strengthenedfor water quality and bottom sludge. e) No solid waste and living garbage from ships will be directly dumped into waters without prior process at garbage stations. No on-board lavatories shall be directly connected to the waters. No living sewage from ships will be directly discharged to Xiangjiang River. All the living sewage from large ships shall be processed in full compliance with specificationprior to discharging,while that of small ships shall be jointly transportedto sewage processingstations on shore.

2) FisheryResources Protection

To mitigate the impact of dam construction,fish fries grown up at the artificial cultivation ponds will be periodicallyreleased into Xiangjiang River so as to raise the fishery resources. Fry shall be put into river by Hunan Provincial Aquatic Product Bureau. Sluice gate opening time will be properly prolonged during the peak time of fish reproduction

3) Preventionof Soil Erosion in ReservoirArea

Turf or trees should be planted on all dams and hillsides in reservoir area. For the farmland whose slope is above 250 on the both banks of reservoir, they should be returned to forestry. Plantation and forest protection must be tightened. After this project is put into operation, the barren mountains and wasteland should be gradually planted. Besides, protection forest should be planted in reservoirarea so as to preventand reduce soil and water erosion. 4) Preventionof AccidentalLeakage

Accident leakage may happenduring loading and unloadingof dangerous goods. This will cause serious impact on water and air environment.Therefore, policy of " PreventionFirst " should be thoroughlyimplemented, Besides, some emergency measures should be worked out so as to minimize the environmental impact if accident leakage happens. Safety consciousness should be strengthened for those who are engaged in loading and unloadingof goods: "TemporaryRules for Inspection and Supervision for Handling Dangerous Goods" and "Rules for Supervision and Managementfor shipping Dangerous Goods," issued by the Ministry of Communicationsof the People's Republic of china, should be strictly executed. Once accident leakage happens, emergency measures must be taken immediately so as to prevent pollutant diffusion as far as possible. In addition, it must be reported to local navigation supervision department immediatelyso that effectiveemergency measures can be taken in time.

11.2 EnvironmentalProtection Measures for HengshanKiloton-class Dock Project

11.2.1 DesignPhase

-- 33 - EnvironmentalAssessment Summary

The dock site shall comply with Port ConstructionEnvironment Protection Design Specifications;The designed dock structure and shape shall be suitable for the flood control; Plantation at the docks shall be well designed;The general design shall include the designs for oily wastewater processing installations and floor flushing water settlement tanks; According to the design requirements, only grocerieswill be allowed to transport. No substances,which have major negative effects on the water such as pesticide,fertilizer, etc., will be allowed to transport in order to avoid any possiblewater contaminationat the upstreamintakes.

11.2.2 ConstructionPhase

Construction sites will be regularly watered to control dust. Atmospheric environment will be regularly monitored during construction phase; Equipment with low noise will be used and constructiontime will be well arrangedto minimize night construction operations; Site living sewage will be processed by bio- chemical means prior to discharging;Construction waste soil and living garbage will be transported to and stockpiledat garbagestation at Hangshancounty.

11.2.3Operation Phase

* Turf and trees will be planted to preventthe soil from erosion; * Oily wastewater processing installationsand garbage collection relay station will be establishedat all docks; * Settlement tanks and bio-chemical processors will be constructed and establishedto processfloor-flush water and living sewage at all docks; * Contingency plans shall be well prepared to deal with any possible water contaminationcaused by leakageor overturnof ships; * Special staff shall be assigned to maintain environmental protection installations and all the employees shall receive environmental protection training.

11.3 Environmental Protection Measures for Kiloton-class Waterway Dredging Project betweenZhuzhou and Xiangtan

11.3.1 DesignPhase

Proper silt disposal and stockpiling sites on shore shall be well selected for dredging project. Structures re-building shall be well arranged to avoid bank flushing.

11.3.2Construction Phase In order to guaranteethe safetyof water quality of sanitary zonefor drinking water source, construction and wastewater discharge must be prohibited within the designated sanitary zone for drinking water source (including oily wastewater, domestic sewage, rubbish and dung etc.)

-- 34 - Environmental Assessment Summary

Dredging of reef and shoal must be approved by public security organs and navigation administrative authority. Navigation administrative authority should announce the time and location of reef blast in advance. Besides, the contractor should estimate the protectionscope of reef blast. Warning line should be set in river channel and alarm signal should be sent out before blasting. People and cars and ships must be evacuated before blasting. Operation rules must be strictly carried out so as to avoid occasionalaccidents.

The quality of boftom sludge to be dredged will be monitored before dredging starts. Based on the result of monitoring, the appropriate measures will be identified and implemented to prevent water pollution from dredging. The disposal plan for dredged sludge will be developed, and reviewed and approved by local environmental protection authorities. Waste materials from dredging project such as sand or rocks can be directly filled into the nearest deep water areas or Dam D's field site if they are not contaminated,while waste materials from dredging project such as silt shall be transported to and stockpiled at the banks. The silt field shall be covered with 20cm thick dry soil and planted with trees and turf.

Measures should be taken to prevent oil leakage during work or maintenance of ships.

Environmental health managementshould be strengthenedfor the construction site. Rubbish, sewage and dung must be centrally collected, transported and treated. It is prohibitedto dischargethem into XiangjiangRiver without treatment, Effective measures should be taken to protect drinking water source during construction of this project. Water quality monitoring must be well done for regional drinking water source. If water is found to be polluted by this project, effective measures must be taken immediately

11.3.3Operation Phase

No oily wastewater, living sewage or garbage from the ships will be allowed to discharged or dumped into the river, all of which shall be processed on shore. Ships with excessive operation noise will be kept off the navigation waterway. National regulations governing dangerous substances transportation shall be strictly followed and contingencymeasures shall be well preparedto minimize any possible leakageand the impactsthereof on environment. All crew shall receive environmentalprotection training.

11.4 InstitutionalArrangement for EnvironmentalProtection

The EnvironmentalProtection Office (EPO) will be strengthenedfrom 3 staff to 5 in order to coordinateand superviserelative environmentalproblems for Zhuzhou Navigation Complex and Dayuandu Navigation Complex. Besides the EPO, 5

-- 35 - Environmental Assessment Summary environmentalprotection supervisorswill be assigned to Zhuzhou Complex and the Hengshandock.

|EnvironmentProtection Office of XiangjiangCo.

Supervisionof constructionat the Complexand ports as wellas thoEnvironment protection at the operationstage

11.5Environmental Training To enhanceenvironmental protection knowledge and skill, all the staff including constructionworkers shall receiveenvironmental training at leastone time while the major environmental protection staff shall receive intensive training. The trainingprogram includes; a) ExpertLecture, b) Site Visit to Similar Environmental Protection Installations,and c) Irregular national or international long-termor short-termtraining.

11.6 EnvironmentalMonitoring

Environmental monitoringwill be undertakenduring construction and operation period. The monitoringcovers, as shown in Tablesbelow, water, bottom sludge, air, noise and ecology. The monitoring works will be entrusted to local environmentalprotection departments.

A systemof reportingthe monitoringresult should be established.After each monitoringwork is finished, the monitoringunit must submit the monitoring report to the Employerimmediately and report it to the higherlevel. The Employer's environmentalprotection office should collect the environmentalmonitoring report once a season to make readyfor examinationby Hunan EnvironmentalProtection Bureau. At the same time, an annual monitoring report will be furnished to the World Bank by January 31 of each year starting in 2003 during constructionperiod, and for each of the first three years followingthe completionof construction.

-- 36 - EnvironmentalAssessment Summary

Table11-1 Water environmental Monitoring Plan

StageStage ~~Place9Monitoring LocationMonitoring Pit t ItemsMonitoring FeunyFrequency Organs.Supervision Domestic Sewage pH, SS, Hunan sewagein outletin COD,DO, twicea year Environmental Construction constructio BOD,Total Protection site n site phosphorus Bureau pH,SS, Eachin Construction COD, DO, drought Phase Downstrem left middle Permanganatperiod and Kongling aboutd km and center e index,N- normal Section awayfrom (three NH3,I periodin a damsite points) petroleum, year.Three total daysin phosphorus succession. Domestic domestic pH,SS COD Sewagein sewag DO, BOD, twicein a directorial sewage total year area oPhosphorus_ Operation Waterquality DO,pH, SS, Oncea Phase of drinking Water COD,BOD, seasonin waterintake intake NCNH3,total the firstthree in Hengshan (Totally2 phosphorus, years.Next, countyand points). peoleum oea year Shiwantown petroleum onceayear

Table11-2 Bottom Sl dge MonitoringPlan MonitoringLocation Monitorin Items MonitoringFrequency SupervisionOrgans EachDredging River Hg,Cd, As, Pb,Cu, BeforeInitial Stage of HunanProvincial Course Zn EachConstruction EnvironmentProtection Bureau

Table 11-3Air EnvironmentMonitoring Plan

Stage MonitoringLocation Item Frration Same Supervision 1.Concretemixing station Threedays 2. Air sensitive in Hans pointsinside succession Onehour Hunan Construction construction site TSP Twicea Eah Oneah Environmental Phase boundary300m)~(within ~ ~~Tac yayear morningon and monitoringfor each Bureau.Protection 300m) afternooninBue. 3. Roadsseriously a day pollutedby dustin constructionsite l

-- 37 - EnvironmentalAssessment Summary

Table 11-4 Noise Monitoring Plan

Stage Monitoring Location Item Frequency Duration Sampling Supervision I ~~~~~~~~~~~~TimeOr ans 1. Boundary of construction site ecat Hunan Constructi 2. Sound sensitivepoints Noise Once a 1 day each at Environmental on Phase inside the boundary of month daytime Protection construction site (within and night Bureau 150m) _ J

Table 11-5Ecological Monitoring Plan

Stage Monitoring Monitoring Frequency SupervisionOrgans Location Factors Construction dam site region tation once before Phase stoneyard vegetio construction Hunan once a seasonin the Environiental Operation ReservoirArea fish Resources first three years, once a Protection Bureau

Phase(96 kmin length) ~~~~yearafter three years ______

11.7 EstimatedInvestment for EnvironmentProtection Total investmentfor environmentalprotection measures is estimated 7.35 million RMB, among which 5.88 million RMB will be used for Zhuzhou Navigation Complex Project, 0.56 million RMBfor Hengshan Kiloton-classDock Project, 0.11 million RMB for Waterway Dredging Project and 0.8 million RMB for overseas training.

-- 38 - 51+R'T '~ '- @ ZR j+'- SKETCH MAP OF XIANGJIANGWATERWAY CONSTRUCTION & DEVELOPMENT

Dao O Xia gyin

I4km VI Wn 1 t Wan7~~~~~~~~~~~~,5hengat

j GuiLi/ X $ / Xiangtan 2 ° ~~~~~Zhuzhou

in HunanProvtpnce QiS/ lng g t lt t - ; ~~ ~ ~~ ~ ~~~~~~~~~~~~~~~~~~yr -S~Et e g PoeYueyangesnni ing io Legend Hagshan SCenlCSpot ( Gnta ZhzoNvi-

ThecokmpietedIII class_waterways Changsha~ ~ ~ ~ ~ ______~ onjin ____)JJ *iX9flXrXaMti Dayuandu Naviga- Hottsa"Ilo Watenwaysin DayuanduReservoir area tion C:omplex / mat*A498aXElVis Wi31Z>oHengdong Propmsedwaterways n ZhujzhouJ/XrIXF

1*:N4fffR?FJX III(3 )iati91tf fr 1 *F7Cti <\ Zhuzhouto Xiangtan Heng-yag9 Hy Pr-, Stt

I Planningdamsite and proposed Cdl fdo'wrllo/4

= >Distance calculatedfrom Chenglingji 2|8 Jw GuyPH f 2e; Lo.ngshuita%g,4 ogo A t$F ALDonganO km1 X;;ISkx1oin eiyang rgqjW Ti \ Hyd. P.er Station.T.t HydroPXowienrlitmat 77gzo lgon7 Changning * ( 5

E tj i1 3 Quanzhou96km(a3) /hgfHdpl>slo 13x 0x00( A >

) | / 7 J 4D ~~~~~~~~~~~~~~~HydroPwrSo tf / ~~~~~~Daoxian°0? e

1Y mafl 2k (3 1i.3fiE x4fixx300(m) U@fl vU

"igi - X9Xi3tEfi 96km V (3) L 1. 3 x 40 x 300 (m) Schematic Diagram of Inundated Areafor Zhuzhou Navigation Complex Project

,T1] 1 1127

It9S,L8S!U,;-2..... ,l 21()- ______| 03

(i * $ ffirU,, + , w ,, z -r r 4-nJ> .2

SitS >' - (--- 2--n!-)42 w .

A~~~~~~~~~~~~~~~~~~~~~

Ahuzhou ~~~~~~~ / 4 ¼..

tU 1:*i500000 :k 7 A#k4 0. 1:20002 004 _.

2. Pgj3d: tY,8.'3 5 k )t gB t 1-I1 Pf Atxtl A Rr. I , ,f vA,$ .\,3 A#

t"'1_ -L-r2 1 2-95 j)/, Legend ,-

0 y'2ernrilentotac(011311\ e\pressxxay

© e ~~~~~~~~proecli'uc mI2nc I -. -I 0 Iag e Hlyl\d t,,1,,_(4.ighnoo I,_<._ In .11,1 . 3 4'9 b : ,,,,,022dl

. trealn1.. r r(r- )t( F rw@

_=iniindawi0 lInle 0 2 3 4 5 'i2

...... , . .. ',,, ,~~~~~~~~~~~~~~~~~~~~~~~~~~~~~4112 ,, ,@ _ _~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~fr