<<

NGRBA Detail Project Report Sewerage Project, ()

Sewerage Project, Acronyms & Abbreviations Hajipur

AAA

AUWSP : Accelerated Urban Water Supply Programme

ASP : Activated Sludge Process BBB

BOD : Biochemical Oxygen Demand

BUDA : Bihar Urban Development Authority

BUIDCO : Bihar Urban Infrastructure Development Corporation CCC

CDP : City Development Plan

CPHEEO : Central Public Health and Environment Engineering Organization

CWR : Clear Water Reservoir

CSP : City Sanitation Plan DDD

DPR : Detail Project Report GGG

GAP : Ganga Action Plan

GIS : Geographical Information System

GoI : Government of

GoB :

i NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

KKK

kW : Kilo Watt

kWH : Kilo Watt Hour LLL

Lac Lit : Lac Liters

LPCD : Liters Per Capita Per Day MMM

MLD : Million Liters per Day

Ml : Million Liter

M : Meter

mm : Millimeter NNN

NGRBA : National Ganga River Basin Authority

NRCD : National River Conservation Directorate

NRCP : National River Conservation Programme OOO

O&M : Operation & Maintenance

OHSR : Overhead Service Reservoir P

PHED : Public Health Engineering Department

PPP : Public Private Partnership Q

ii NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

QA&QC : Quality assurance & quality control S

SLNA : State Level Nodal Agency

SPS : Sewage Pumping Station

STP : Sewage Treatment Plant

SBR : Sequential Batch Reactor U

UD&HD Urban Development & Housing Department

ULB : Urban Local Body/Bodies W

WSP : Waste Stabilisation Pond

iii NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

SEWERAGE PROJECT , HAJIPUR

UNDER NGRBA

(NATIONAL GANGA RIVER BASIN AUTHORITY )

VOLUME I : MAIN REPORT

Chapter No Particulars

C-1 Project Background

C-2 Project Town

C-3 Design Criteria

C-4 Existing Infrastructure

C-5 Population projection

C-6 Proposed Sewerage System

C-7 Wastewater Treatment Process

C-8 Treatment Plant Design

C-9 Project Cost

C-10 Funding & Implementation

C-11 Operation & Maintenance

C-12 IEC Activities & Capacity Building

iv NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

SEWERAGE PROJECT , HAJIPUR

UNDER NGRBA

(NATIONAL GANGA RIVER BASIN AUTHORITY )

VOLUME II : ANNEXURES

ANNEXURE

Annexure No Particulars

A-1 General Standards for discharge of environmental pollutants

A-2 Population projections

A-3 Hydraulic Design of Sewer network

A-4 Design of Sewage Treatment Plant

A-5 Design of Pumping Main

A-6 Design of Wet well & Pumping Stations

A-7 Structural Design of Sewers

A-8 General Abstract of Cost

A-9 Cost Estimates & Rate Analysis

A-10 Income & Expenditure Statement of Hajipur ULB

A – 11 Operation & Maintenance Cost

A - 12 Minutes of 1st meeting of ESC of NGRBA dated 05-02- 2010

A – 13 NRCD - Revised Guideline for preparation of DPRs for conservation of Rivers & Lakes

v NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

SEWERAGE PROJECT , HAJIPUR

UNDER NGRBA

(NATIONAL GANGA RIVER BASIN AUTHORITY )

VOLUME III : DRAWINGS

DRAWINGS

SN Drawing No Particulars

1 BR/NGRBA/SWG/HAJIPUR/01 Map and State of Bihar showing Hajipur District

2 BR/ NGRBA /SWG/HAJIPUR/02 Town Map of Hajipur

3 BR/ NGRBA /SWG/HAJIPUR/03 Town map showing wards & ward wise population

4 BR/ NGRBA /SWG/HAJIPUR/04 Comprehensive sewerage proposals

5 BR/ NGRBA /SWG/HAJIPUR/05 Town map showing sewer network

6 BR/ NGRBA /SWG/HAJIPUR/06 Typical sewer trench

7 BR/ NGRBA /SWG/HAJIPUR/07 Details of pipe bedding

8 BR/ NGRBA /SWG/HAJIPUR/08 Typical brick manhole Type ‘A’

9 BR/ NGRBA /SWG/HAJIPUR/09 Typical brick manhole Type ‘B’

10 BR/ NGRBA /SWG/HAJIPUR/10 Typical brick manhole Type ‘C’

11 BR/ NGRBA /SWG/HAJIPUR/11 Typical brick manhole Type ‘D’

12 BR/ NGRBA /SWG/HAJIPUR/12 Typical RCC manhole type E & F

13 BR/ NGRBA /SWG/HAJIPUR/13 Typical drop manhole

14 BR/ NGRBA /SWG/HAJIPUR/14 Typical Vent shaft arrangement

15 BR/ NGRBA /SWG/HAJIPUR/15 Typical house sewer connection

vi NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

SN Drawing No Particulars

16 BR/ NGRBA /SWG/HAJIPUR/16 STP layout plan

17 BR/ NGRBA /SWG/HAJIPUR/17 Pumping Station

vii NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

Sewerage Project, Table of Contents Hajipur

Abbreviation i – iii Combined Contents iv - vii Table of Contents viii - xiii Executive Summary xiv – xviii Salient Features xix - xxii

CHAPTER 1. PROJECT BACKGROUND 1

1.1. PROJECT BACKGROUND 1 1.2. ESC APPROVAL 2 1.3. RIVERS 3 1.4. RIVER 4 1.5. RIVER POLLUTION 5 1.6. NGRBA 6 1.6.1. KEY FEATURES OF THE NEW APPROACH OF NGRBA 6 1.6.2. KEY FUNCTIONS OF THE NGRBA 6 1.6.3. ‘P REPARATORY STEPS ’ AFTER SETTING UP NATIONAL GANGA RIVER BASIN AUTHORITY 7 1.7. DOCUMENT ORGANIZATION 9

CHAPTER 2. THE PROJECT TOWN 12

2.1. INTRODUCTION 12 2.2. THE STATE 12 2.3. THE DISTRICT 18 2.4. HISTORY 18 2.5. LOCATION 22 2.6. DEMOGRAPHY 22 2.7. CONNECTIVITY 23 2.8. FACILITIES 23 2.9. TOURIST LOCATIONS 25

CHAPTER 3. DESIGN CRITERIA 29

3.1. THE MANUAL OF SEWERAGE AND SEWAGE TREATMENT (S ECOND EDITION ) 29 3.2. DESIGN PERIOD 29

viii NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

3.3. GROUND WATER INFILTRATION 31 3.4. FLOW FORMULAE 31 3.5. VARIATION IN FLOW 32 3.6. PIPE MATERIAL 32 3.6.1. PRECAST (PC) PIPES : 32 3.6.2. VITRIFIED CLAY PIPES : 33 3.6.3. PLASTIC PIPES : 34 3.6.4. DI PIPES 34 3.7. THE STRUCTURAL DESIGN OF SEWERS 35 3.8. MINIMUM AND MAXIMUM SEWER PIPE SIZES 35 3.8.1. MINIMUM SEWER SIZES 35 3.8.2. MAXIMUM SIZES OF SEWERS 36 3.9. NORMAL MINIMUM DEPTHS FOR SEWERS 36 3.10. MANHOLE DESIGN AND SPACING 37 3.10.1. MANHOLE DESIGN 37 3.10.2. MANHOLE SPACING 38 3.11. FLOW CAPACITY OF SEWERS 39 3.12. SEWAGE SEPTICITY & VENTILATION 39 3.13. SEWAGE PUMPING STATIONS AND PUMPING MAINS 40 3.13.1. GENERAL 40 3.13.2. RECOMMENDATIONS 40 3.13.3. PUMPING MAINS 41 3.14. SEWER CROSSINGS 42

CHAPTER 4. EXISTING INFRASTRUCTURE 43

4.1. EXISTING WATER SUPPLY 43 4.1.1. EXISTING ARRANGEMENTS 43 4.2. EXISTING STORM WATER DRAINAGE FACILITIES 44 4.2.1. RIVER GANDAK 44 4.2.2. EXISTING DRAINS 45 4.3. EXISTING SEWERAGE SYSTEM 46 4.3.1. SANITATION METHODS 46 4.3.2. COMMUNITY TOILETS 47 4.3.3. NEED OF THE PROJECT 47

CHAPTER 5. POPULATION PROJECTION 49

5.1. HISTORICAL TREND 49 5.2. 2001 52 5.3. POPULATION PROJECTIONS METHODOLOGY 54 5.4. POPULATION PROJECTION 55 5.5. MICRO LEVEL POPULATION PROJECTION 57

ix NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

CHAPTER 6. PROPOSED SEWERAGE SYSTEM 59

6.1. INTRODUCTION 59 6.2. PROPOSED SEWERAGE ZONES 59 6.3. PROPOSED NETWORK LAYOUT 61 6.4. DESIGN OF SEWERAGE NETWORK 62 6.5. STRUCTURAL DESIGN OF SEWER PIPES 64 6.5.1. LOAD PRODUCING FORCES 64 6.5.2. SUPPORTING STRENGTH OF RIGID CONDUIT 65 6.5.3. LOAD FACTORS FOR DIFFERENT CLASSES OF BEDDING 66 6.5.4. TECHNO -ECONOMIC ANALYSIS 66

CHAPTER 7. WASTEWATER TREATMENT PROCESS 68

7.1. GENERAL 68 7.2. SEWAGE CHARACTERISTICS 68 7.2.1. IMPORTANT PARAMETERS 69 7.2.1.1. pH value 69 7.2.1.2. Solids 69 7.2.1.3. Nutrients 69 7.2.1.4. Biochemical Oxygen Demand (BOD) 70 7.2.1.5. Chemical Oxygen Demand (COD) 70 7.2.2. EXISTING WATER /W ASTEWATER CHEMICAL ANALYSIS 70 7.2.2.1. Drinking Water Characteristics 71 7.2.2.2. Wastewater characteristics 71 7.2.3. ADOPTED INFLUENT QUALITY 72 7.2.4. EFFLUENT STANDARDS 73 7.3. TREATMENT PROCESSES 74 7.4. SELECTION OF TREATMENT PROCESS 74 7.4.1. STABILIZATION PONDS 74 7.4.1.1. Aerobic ponds 75 7.4.1.2. Anaerobic ponds 75 7.4.1.3. Facultative Ponds 75 7.4.1.4. Disadvantages 76 7.4.2. AERATED LAGOONS 76 7.4.2.1. Aerobic Lagoons 76 7.4.2.2. Facultative Aerated Lagoons 77 7.4.3. UPFLOW ANAEROBIC FILTER PROCESS (UASB) 78 7.4.4. ACTIVATED SLUDGE PROCESS 79 7.4.5. CYCLIC ACTIVATED SLUDGE PROCESS /S EQUENTIAL BATCH REACTOR (CASP/SBR) 81 7.4.6. CONCLUSION 85

CHAPTER 8. TREATMENT PLANT DESIGN 88

x NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

8.1. GENERAL DESCRIPTION 88 8.1.1. RECEIVING OF RAW SEWAGE (I NLET CHAMBER ) 88 8.1.2. COARSE AND FINE SCREENING 88 8.1.3. RAW SEWAGE PUMPING AREA 89 8.1.4. FINE SCREENING CHANNELS 89 8.1.5. DE-GRITTING 89 8.1.6. FLOW MEASUREMENT 90 8.1.7. SBR / CYCLIC ACTIVATED SLUDGE PROCESS 90 8.1.8. CHLORINATION SYSTEM 90 8.1.9. SLUDGE HANDLING SYSTEM 90 8.2. TREATMENT PLANT CAPACITY 91 8.3. STP UNITS 91 8.3.1. RECEIVING CHAMBER 92 8.3.2. COARSE SCREEN CHANNELS 93 8.3.3. RAW SEWAGE PUMPING 94 8.3.3.1. Sump and Pumps 94 8.3.4. MECHANICAL FINE SCREEN AND CONVEYOR 96 8.3.5. GRIT REMOVAL UNIT 97 8.3.6. FLOW MEASUREMENT 98 8.3.7. DIVISION BOX 98 8.3.8. CYCLIC ACTIVATED SLUDGE PROCESS / SBR PROCESS WITH DIFFUSERS AND AIR BLOWERS 98 8.3.8.1. Process Design 99 8.3.8.2. Decanting Device 99 8.3.8.3. Aeration System 100 8.3.8.4. Return Sludge and Excess Sludge Pumps 101 8.3.8.5. Automation and Control 103 8.3.9. SLUDGE HANDLING SYSTEM 103 8.3.9.1. 10.1 Sludge Sump and Pump House 104 8.3.9.2. Sludge Transfer Pumps and Mixing Blowers 104 8.3.9.3. Mechanical Dewatering Unit: 105 8.3.9.4. Polyelectrolyte Dosing: 107 8.3.10. DISINFECTION SYSTEM 107 8.3.10.1. Chlorination Tank: 107 8.3.10.2. Chlorination System: 107 8.3.11. DISPOSAL PIPE/C HANNEL 108 8.3.12. SBR AIR BLOWER CUM ADMINISTRATIVE CUM MCC & CONTROL BUILDING 108 8.4. PROPOSED DISPOSAL METHOD 109 8.5. ANCILLARY FACILITIES 109 8.5.1. SECURITY ROOM 109 8.5.2. PMCC ROOM 109 8.5.3. CONTROL ROOM 109 8.5.4. REST ROOM 109 8.5.5. WORKSHOP CUM STORE 109 8.5.6. OPEN STORE YARD 110 8.5.7. COVERED VEHICLE PARK 110

xi NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

8.5.8. LANDSCAPING 110

CHAPTER 9. PROJECT COST 111

9.1. SOURCES 111 9.2. SEWERS 112 9.3. MANHOLE 112 9.4. PUMPING STATIONS 113 9.5. TREATMENT PLANT 113 9.6. SEWERS IN NARROW LANES 113 9.7. OTHER ITEMS 113 9.8. ABSTRACT OF COSTS 114

CHAPTER 10. FUNDING & IMPLEMENTATION 115

10.1. IMPLEMENTING AGENCY 115 10.2. AGENCY RESPONSIBLE FOR OPERATION & MAINTENANCES 115 10.3. IMPLEMENTATION PLAN 116 10.4. IMPLEMENTATION PERIOD 117 10.5. PACKAGING 117 10.6. IMPLEMENTATION SCHEDULE 117 10.7. FUNDING PATTERN 117

CHAPTER 11. OPERATION & MAINTENANCE 120

11.1. INTRODUCTION 120 11.1.1. CORRECTIVE MAINTENANCE 120 11.1.2. PREVENTIVE MAINTENANCE 121 11.1.3. PREDICTIVE MAINTENANCE 121 11.1.4. FLUSHING PLAN 122 11.2. BENEFITS 123 11.3. TECHNICAL & MANAGERIAL CAPACITY 123 11.4. OUTSOURCING : 124 11.5. SEWERAGE O&M MANAGEMENT PLAN 124 11.6. O&M COSTS 126 11.6.1. PROVISION FOR SEWERAGE CHARGES IN BIHAR MUNICIPAL ACT , 2007 126 11.6.2. MODALITIES FOR SELF SUSTAINING SYSTEM 127 11.6.3. SUSTAINABILITY 128 11.7. MUNICIPAL COUNCIL HAJIPUR 130 11.7.1. BACKGROUND 130 11.7.2. ADMINISTRATIVE SETUP 130 11.7.3. TOOLS & PLANTS 132 11.7.4. INCOMES & EXPENDITURES 133 11.7.5. POWER OF MUNICIPALITIES FOR SEWERAGE CONNECTION 135

xii NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

11.8. SPECIFIC O&M REQUIREMENTS 136 11.9. O&M EQUIPMENT 137

CHAPTER 12. IEC ACTIVITIES & CAPACITY BUILDING 138

12.1. COMMUNICATION STRATEGY 138 12.2. PRINT MEDIA 139 12.3. ELECTRONIC MEDIA 140 12.4. CAPACITY BUILDING 140 12.5. COMMUNITY PARTICIPATION UNITS 143

xiii NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

Sewerage Project, Executive Summary Hajipur

With growing urbanization and emergence of urban areas as growth centers combined with improved living standards, piped water supply with improving service levels has become integral part of basic civic amenity. Safe disposal of human excreta & wastewater is also necessary for health reasons. The options available for disposal of excreta are either on-site or off-site sewerage system. On site sanitation system, prevailing till date, in most of the towns, are individualistic system with inherent problems for collection & disposal of sludge & risks of contamination of ground water. Water carriage sewerage system, more or less, has come to be universally adopted for disposal of excreta. Hajipur Town is the district head quarter of Vaisali District in State of Bihar. The town is situated on the banks of river Gandak and is just 10 kms from River Ganga. The topography of the town is that of a flat plain area. The mean annual rainfall is 1203 mm mostly confined to monsoon season and with maximum temperature during summer between 41.7oC and minimum temperature of 5.6 oC during winter season.

As per 2001 census, the project town had a population of 119,412 souls. Project facilities are proposed to be designed for future requirements of year 2041. An elaborate exercise has been carried out for population projection at both macro & micro level using number of statistical methods & tools. The designed population for year 2041 comes out to be 305,494. The results of population projection for different years are as follows: S.No Census Population Year

1 2001 119412 2 2008 142188 3 2011 152979

4 2021 194122 5 2026 217992 6 2031 244337 7 2041 305494

xiv NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

Town Hajipur has no comprehensive sewerage system. The human excreta is disposed of using on site sanitation methods. Open defection is also not uncommon. Spent water from kitchen & bath rooms is let into surface drains which lead to local depressions. Septic effluent from septic tanks is also let into the surface drains. The proposed project aims effective abatement of pollution of river Ganga by provide a comprehensive wastewater collection, treatment & disposal system using laterals, branches and trunk mains including sewage treatment plant. The project is proposed to be implemented under National Ganga River Basin Authority (NGRBA), a programme launched by with the objectives of pollution abatement and to improve water quality of Ganga River. Under the project, Sewerage system is being proposed to ascertain that no wastewater will be discharges in Gandak river (a tributary of River Ganga) untreated. The provisions, as recommended by Manual of Sewerage and Sewage Treatment, published by Central Public Health and Environmental Engineering Organisation (CPHEEO), of Government of India and revised guidelines for preparation of DPRs by NRCD are largely adopted for design of sewerage system for this project. The most of the town is proposed to discharge at single location on its eastern side in a canal on the northern side of Industrial area. Two pumping stations are proposed to restrict the depth of excavation to 8.0 mtr in general. It is proposed to use Reinforced Cement Concrete non pressure circular pipes for sewers suitably supported with bedding, depending on structural requirements. A minimum size of 150 mm is adopted as per recommendations of CPHEEO Manual. Manhole are proposed to be provided at 30 mtr or more spacing as per prevalent practice & specifications. The summary of sewer lengths for the town is as below:

Diameter Length of (mm) Sewers (m) 150 21078.2 160 20164.0 200 135122.2 250 3367.4 300 2280.2 350 4714.6

xv NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

Diameter Length of (mm) Sewers (m) 400 2807.7 450 13.2 500 1541.9 600 1881.5 700 1848.9 800 768.5 1000 697.3 1200 2129.2 Total 198414.8

A number of available technologies including conventional system like Attached and Suspended growth aerobic systems, Anaerobic systems , oxidation ditch, UASB, Sequential Batch Reactor and unconventional systems like Reed beds or Constructed wetlands, Soil application methods and Waste Stabilization ponds are reviewed. The review of available technologies is made with the consideration to the local climate, Land availability, power requirements and treatment levels. A sewage treatment system, based on Sequential Batch Reactor Process finds favor owing to discharge standards requirement of 30 mg/l BOD and less land requirement. It is increasing difficult to find adequate land in urban towns. The proposed system includes Primary treatment in form of Coarse & Fine Screens, Grit Chamber, SBR Tanks, Centrifuge and Chlorination Contact Tank. The intended treatment levels are to conform to the effluent standards for application on land as per The Environment Protection Act, 1986. The effluent is proposed to be discharged in River Ganga. The effluent standards for inland surface water discharge includes 5 day BOD at 20 0C as 30 mg/l and suspended solids of 100 mg/l. A sewage treatment plant based on Sequential Batch Reactor technology is proposed to be constructed of capacity 22 mld. The costs for sewerage collection system with all ancillary works comes to be Rs 92.12 Crores and that of Rs 21.72 Crores for Sewage Treatment plant & SCADA. The total cost of the project will be Rs 113.84 Crore. Benefits for the implementation of this project could only be achieved with parallel improvements in other related fields. A number of other interventions will be required for reaping full benefits of this project and to

xvi NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

ensure its continual efficient functioning. The major identified interventions are provided below.  Developing comprehensive management system for sewerage facilities  Encouraging property owners to connect to sewers where they are available  Introducing improved Quality Assurance procedures and checks  Improving Solid Waste Management  Sanitation awareness and domestic hygiene Bihar Urban Infrastructure Development Corporation Ltd. (BUIDCo) to act as Execution Agency for all Projects sanctioned under NGRBA., Bihar Urban Infrastructure Development Corporation Ltd. (BUIDCo) is a Govt. of Bihar Undertaking registered under the Company’s Act 1956 (Act 1 of 1956) on 16th June, 2009. The project will be implemented by the BUIDCo. There shall be tripartite contract agreements between BUIDCo, ULB and Contractor for capital works and for O&M of assets created. After successful testing and commissioning of all components, the assets will be transferred to ULB for taking care of O&M responsibilities. Considering the financial, technical & human resource constraints of Municipal Council, it is proposed to club the operation & maintenance of the sewerage system with STP in first five years with Capital works contract. Later, with gradual capacity building of Municipal council, the O&M of the system may be taken over by Municipal council or outsourced to some private operator. To assist the executing agency for activities of Construction supervision, implementation of Quality assurance & quality control (QA&QC) procedures, it is proposed to engage Construction supervision Consultants for this project as a pre execution activity. Another important pre- execution activity is to appoint some experienced Non Governmental Organisation or other suitable agency with the aim to ensure active participation of beneficiaries with the project implementation, carry out social awareness campaign for good sanitation and good hygiene practices and to encourage property owners to connect to sewers laid under this project and to encourage the beneficiaries to pay for sanitation services for efficient O&M operations and overall sustainability.

xvii NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

The project is proposed to be implemented in a single work package to expedite the implementation process. Excluding the first nine months of pre execution activities, project is proposed to be implemented in fifteen months. To ensure sustainability of the project, it is imperative that revenue be generated from the beneficiaries of the system to recover the Operation & maintenance costs and if possible, costs for extension & up-gradation of facilities. In due course of time, it is required to Levy reasonable user charges by ULB with the objective that full cost of operation and maintenance or recurring cost is collected. It is proposed that a suitable system in consultation with users and resident welfare associations is required to be developed for collecting charges for sewerage facilities. Two recommended options are; to levy sewerage charges as %age of water charges and second is to charge property owners based on categorized localities and plot size with preference to first option. Successful Implementation & commissioning of project will considerably improve the water quality of river Ganga & Gandak with additional benefits in form of improvement in living environment, hygienic conditions of town people. The project will help in considerably reducing pollution load on Ganga & Gandak river which will lead to restoration of aquatic ecology of these rivers and flourishing of aquatic flora & fauna.

xviii NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

Programme National Ganga River Basin Authority (NGRBA)

Project Sewerage Project, Hajipur

Project Town Hajipur District Vaisali SALIENT FEATURES

GENERAL INFORMATION

Area : 1993.23 Ha Population, 2001 : 119,412 Av Annual Rainfall : 1203 mm Households : 17050 Max Temperature : 41.7 oC Min Temperature : 5.6 oC

LOCATION

The town is situated on the banks of River Gandak. It is just 10 kilometers from State capital . It is district headquarter of Vaisali District

DEMOGRAPHY

Historical Population Population Projections

Year Population Year Projected Population 1901 21398 Arithmetical Geometric Incremental Graphical Average 1911 19233 Progression Increase Increase Projection of four 1921 16760 methods 1931 19299 2001 119412 119412 119412 119412 119412 1941 21963 2008 134350 147980 139087 147336 142188 1951 25149 2011 140752 162229 148714 160219 152979 1961 34044 2021 162092 220399 185975 208021 194122 1971 41890 2026 172762 256891 207591 234723 217992 1981 62520 2031 183432 299426 231196 263293 244337 1991 87687 2041 204772 406790 284377 326036 305494

2001 119412

xix NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

EXISTING SCENARIO

There is no sewerage system existing in the town. Open defecation is not uncommon in the town. Most of households having sufficient yard area and in newly developed housing societies the wastewater disposal is done through septic tanks and effluent from these septic tanks is discharged in open drains and get collected in local ponds.

WASTEWATER PRODUCTION

Year Population Per Capita Wastewater Wastewater Wastewater Water Supply, Contribution Volume per Volume lpcd capita per (mld) day

2011 152979 135 80% 108 16.52 2026 217992 135 80% 108 23.54 2041 305494 135 80% 108 32.99

PROPOSED SEWERAGE SYSTEM

Sewer Network Pumping Station

Diameter Length of Two pumping stations are proposed one at Gudha (mm) Sewers (m) Pokhar and second at Yusufpur area

150 21078.2 160 20164.0 PS No Flow Head(m) kW Number (cum/hr) 200 135122.2 250 3367.4 1 369.26 13 27 5 300 2280.2 2 136.78 12 9 5 350 4714.6 400 2807.7 450 13.2 Railway & National Highway Crossings 500 1541.9 600 1881.5 There is one Railway crossing near Railway over-bridge 700 1848.9 in northern side of town and there are 5 NH crossings in the town. 800 768.5

1000 697.3 1200 2129.2 Total 198414.8

Treatment Plant

A treatment plant with capacity to treat 22 mld of wastewater is proposed. The treatment process proposed is Activated Sludge Process based on Sequential Batch Reactor technology. The treatment plant shall be sited in north of Industrial Area of Hajipur Town and the treated effluent shall be discharged in nearby natural drain.

xx NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

PROJECT COST

S.NO. PARTICULARS AMOUNT (Rs.)

1 Earthwork, Timbering and Barricading 131,881,804 2 Providing and Laying of Sewer lines with bedding 165,908,487 works 3 Construction of Manholes, Vent-shafts and uPVC 364,318,855 pipe laying 4 Dismantling and Restoration of Roads, structure 83,779,801 and Railway & NH crossing by Trenchless technology etc 5 E. Miscellaneous Items like encasing, equipments 18,146,453 for flushing of sewer lines etc 6 Provision for 2 nos pumping station, rising main and 37,197,511 pumping machineries and for dedicated HT & LT feeders. 7 Provision for STP (Sequential Batch Reactor) 22 MLD 217,250,000 in PHASE I for population of 2026 including SCADA 8 TOTAL "A" to "G" 1,018,482,911 Provision for Land Acquisition 33,000,000 Provision for IEC activities 5,000,000 Centage charges @ 8.0% (excluding land 81,878,633 acquisition cost) GRAND TOTAL 1,138,361,544 SAY RS. Crores 113.84

O&M Expenditure Sustainability

Particulars O&M Exp (Lac Rs) Total O&M Expenditure for Rs 5389.91 project period Year Year 2041 2011 Discounted O&M Rs 1630.02 Expenditure for Project Salaries & Wages 55.92 55.92 period Power Charges 46.53 131.57 Unit user charges required Rs 1.85 Repair & Maint 29.69 29.69 to offset undiscounted O&M Cost Chemical Charges 0.6 0.6 Unit user charges required Rs 1.95 Flushing Charges 6.65 6.65 to offset discounted O&M Total Cost Cost 139.39 224.43

xxi NGRBA Detail Project Report Sewerage Project, Hajipur (Bihar)

COST SHARING

The sharing of funds would be in the ratio of 70:30 between Central Government & State Government & local bodies. The quarterly funds requirement in pre construction & construction phase shall be as follows:

Funding Fund Quarterly Fund Requirements Source Required Pre Construction Phase Construction Phase (Rs Crores) I II III IV V VI VII VIII Central Government 79.69 0.16 0.64 9.25 7.14 17.85 25.00 14.29 5.36 State Government 34.15 0.07 0.27 3.97 3.06 7.65 10.71 6.12 2.29 & Local Bodies Total 113.84 0.23 0.91 13.22 10.21 25.51 35.71 20.41 7.65

IMPLEMENTATION PLAN

The initial nine months will be taken up by preliminary activities like appointment of construction supervision consultants, identification & allotment/transfer of lands for STP & Pumping Stations and Bidding process. Afterwards the project execution period is taken up as 15 months.

xxii NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Chapter 1. Project Background

1.1. Project Background

Bihar Urban Development Agency (BUDA), working under UD&HD, is engaged in systematic planning, infrastructure development, and creation of civic amenities in urban and semi-urban areas in the State of Bihar. BUDA has also been designated as the State Level Nodal Agency (SLNA) for implementation of JNNURM & UIDSSMT programmes to work as a facilitator in effective implementation of the projects in the identified ULBs. These programmes are to be implemented through ULBs. Govt of Bihar has decided Bihar Urban Infrastructure Development Corporation Ltd. (BUIDCo) to act as Execution Agency for all Projects sanctioned under NGRBA., BUIDCo is a Govt. of Bihar Undertaking registered under the Company’s Act 1956 (Act 1 of 1956) on 16th June, 2009; established with a view to accelerate infrastructure development activities across all ULBs and assist the ULBs in developing, augmenting, financing and maintaining municipal services. There shall be tripartite contract agreements between BUIDCo, ULB and Contractor for capital works and for O&M of assets created. After successful testing and commissioning of all components, the assets will be transferred to ULB for taking care of O&M responsibilities. Government of Bihar has posed Sewerage projects of three towns namely Hajipur, Buxar and situated on the banks of river Ganges to

1 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

National Ganga River Basin Authority (NGRBA) for financial support. The broad objectives for the proposed sewerage projects is for rejuvenation of river water quality by preventing passage of untreated municipal sewage into the river. The details of these towns is as below; Area Population No. of SNo. Project ULBs District (Sqkm) Census 2001 Wards

1 Buxer Nagar Parishad Buxer 5.16 83,168 34 2 Hazipur Nagar Parishad 19.64 1,19,412 39 3 Begusarai Nagar Parishad Begusarai 8.98 93,741 36

Total 33.78 2,96,321 109

The National Ganga River Basin Authority (NGRBA) decided that no untreated municipal sewage and industrial effluents would be allowed to enter the river Ganga after 2020 under Mission Clean Ganga. An estimated investment of Rs 15,000 crore would be required over the next ten years to create the necessary treatment and sewerage infrastructure. An amount of Rs 250 crore has been allocated for the NGRBA in the Union Budget for 2009-10. An allocation of Rs 500 crore per year has been agreed to by the Planning Commission for the remaining two years of the XIth Plan. The World Bank, which has promised long-term support for the Authority's work programme, has indicated assistance of $ 1 billion for the first phase. A proposal of $3 million project preparation facility was forwarded to the Bank and it has been approved.

1.2. ESC Approval

First meeting of Empowered Steering Committee (ESC) of the National Ganga River Basin Authority (NGRBA) was held of February 5’ 2010. In the meeting following four projects of State of Bihar was taken into consideration:  Sewerage and Sewage Treatment Plant at Begusarai for pollution abatement of River Ganga in Bihar – Rs 65.40 crores  Sewerage and Sewage Treatment Plant at Buxar for pollution abatement of River Ganga in Bihar – Rs 74.95 crores

2 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 Sewerage and Sewage Treatment Plant at Hajipur for pollution abatement of River Gandak in Bihar – Rs 113.62 crores  Sewerage and Sewage Treatment Plant at for pollution abatement of River Ganga in Bihar – Rs 187.89 crores Empowered Steering Committee has decided the following for these four towns as follows:  Approval of the project of Sewerage and Sewage Treatment Plant at Begusarai for pollution abatement of River Ganga in Bihar – Rs 65.40 crores and release of first installment of Rs 7.0 crores  Approval of the project of Sewerage and Sewage Treatment Plant at Buxar for pollution abatement of River Ganga in Bihar – Rs 74.95 crores and release of first installment of Rs 8.0 crores  Approval of the project of Sewerage and Sewage Treatment Plant at Hajipur for pollution abatement of River Gandak in Bihar – Rs 113.62 crores and release of first installment of Rs 12.0 crores after approval of Project by Union Finance Minister. The minutes of meeting of ESC is available at Annex A-12.

1.3. Rivers

Rivers have been used for navigation for thousands of years. The earliest evidence of navigation is found in the Indus Valley Civilization, which existed in northwestern Pakistan around 3300 BC. Riverine navigation provides a cheap means of transport, and is still used extensively on most major rivers of the world. Rivers have been a source of food since pre-history. They can provide a rich source of fish and other edible aquatic life, and are a major source of fresh water, which can be used for drinking and irrigation. It is therefore no surprise to find most of the major cities of the world situated on the banks of rivers. Rivers help to determine the urban form of cities and neighborhoods and their corridors often present opportunities for urban renewal through the development of foreshore ways such as River walks. Rivers have been important in determining political boundaries and defending countries. The coarse sediments, gravel and sand, generated and moved by rivers are extensively used in construction. in recent decades there has been a significant increase in the development of large scale power generation from water

3 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Rivers also provide an easy means of disposing of waste-water and, in much of the less developed world, other wastes.

1.4. River Ganges

The Ganges is one of the major rivers of the Indian subcontinent, flowing east through the Gangetic Plain of northern India into Bangladesh. The 2,510 km river rises in the western Himalayas in the Uttarakhand state of India, and drains into the Sunderbans delta in the Bay of Bengal. The Ganges Basin drains 1,000,000-square-kilometre and supports one of the world's highest density of humans. The river has been declared as India's National River. After flowing 200 km through its narrow Himalayan valley, the Ganges debouches on the Gangetic Plain at the pilgrimage town of Haridwar. Further, the river follows an 800 km curving course passing through the city of before being joined from the southwest by the Yamuna at Allahabad. Joined by numerous rivers such as the Kosi, Son, Gandaki and Ghaghra, the Ganges forms a formidable current in the stretch between Allahabad and Malda in West Bengal. On its way it passes the towns of Kanpur, Soron, Kannauj, Allahabad, Varanasi, Patna, , , Mirzapur, Ballia, Buxar, Saidpur, and Chunar. The Ganges Basin with its fertile soil is instrumental to the agricultural economies of India and Bangladesh. The Ganges and its tributaries provide a perennial source of irrigation to a large area. Chief crops cultivated in the area include rice, sugarcane, lentils, oil seeds, potatoes, and wheat. Along the banks of the river, the presence of swamps and lakes provide a rich growing area for crops such as legumes, chillies, mustard, sesame, sugarcane, and jute. There

4 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

are also many fishing opportunities to many along the river, though it remains highly polluted. Tourism is another related activity. Three towns holy to – Haridwar, Allahabad, and Varanasi – attract thousands of pilgrims to its waters. Thousands of Hindu pilgrims arrive at these three towns to take a dip in the Ganges, which is believed to cleanse oneself of sins and help attain salvation. The rapids of the Ganges also are popular for river rafting, attracting hundreds of adventure seekers in the summer months.

1.5. River Pollution

The major polluting industries on the Ganga are the leather industries, especially near Kanpur, which use large amounts of Chromium and other chemicals, and much of it finds its way into the meager flow of the Ganga. Also, inadequate cremation procedures contributes to a large number of partially burnt or unburnt corpses floating down the Ganga, not to mention livestock corpses. The Ganga Basin, the largest river basin of the country, houses about 40 percent of population of India. During the course of its journey, municipal sewages from 29 Class-I cities (cities with population over 1,00,000), 23 Class II cities (cities with population between 50,000 and 1,00,000) and about 48 towns, effluents from industries and polluting wastes from several other non-point sources are discharged into the river Ganga resulting in its pollution. The NRCD records put the estimates of total sewage generation in towns along river Ganga and its tributaries as 5044 MLD (Million Litres per Day). According to the Central Pollution Control Board Report of 2001, the total wastewater generation on the Ganga basin is about 6440 MLD.

Urban filth and industrial pollution are scientific causes, but environmentalists believe that apart from industrial pollution and sewage, the increase in number of slaughterhouse, dhobi ghats, crematoria and slums are the major sources of pollution in these rivers. Every year, religious

5 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

idols are immersed in rivers which lose a little more of their life as they are choked yet again.

1.6. NGRBA

The Central Government, by a notification dated 20.2.2009, as set up ‘National Ganga River Basin Authority’ (NGRBA)as an empowered planning, financing, monitoring and coordinating authority for the Ganga river, in exercise of the powers conferred under the Environment (Protection) Act,1986. The Prime Minister is ex-officio Chairperson of the Authority, and it has as its members, the Union Ministers Concerned and the Chief Ministers of states through which Ganga flows, viz., Uttarakhand, Uttar Pradesh, Bihar, Jharkhand and West Bengal, among others. The objective of the Authority is to ensure effective abatement of pollution and conservation of the river Ganga by adopting a holistic approach with the river basin as the unit of planning. The functions of the Authority include all measures necessary for planning and execution of programmes for abatement of pollution in the Ganga in keeping with sustainable development needs.

1.6.1. KEY FEATURES OF THE NEW APPROACH OF NGRBA

 River Basin will be the unit of planning and management. This is an internationally accepted strategy for integrated management of rivers. Accordingly, a new institutional mechanism in the form of National Ganga River Basin Authority (NGRBA) will spearhead river conservation efforts at the national level. Implementation will be by the State Agencies and Urban Local Bodies.  The minimum ecological flows for the entire Ganga will be determined through modeling exercises. NGRBA will take appropriate measures in cooperation with the States to regulate water abstraction for marinating minimum ecological flows in the river.  Attention would also be paid to the restoration of living parts of the river ecosystem for its holistic treatment to enable conservation of species like dolphin, turtles, fishes and other native and endangered species in their river.

1.6.2. KEY FUNCTIONS OF THE NGRBA

 The NGRBA would be responsible for addressing the problem of pollution in Ganga in a holistic and comprehensive manner. This will

6 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

include water quality minimum ecological flows, sustainable access and other issues relevant to river ecology and management.  The NGRBA will not only be regulatory body but will also have developmental role in terms of planning & monitoring of the river conservation activities and ensuring that necessary resources are available.  The NGRBA would work for maintaining the water quality of the river Ganga upto the acceptable standards. The pollution abetment activities will be taken up through the existing implementation mechanisms in the States and also through Special Purpose Vehicles (SPVs) at the pollution hotspots.  The NGRBA will ensure minimum ecological flow in the Ganga by regulating water abstraction and by promoting water storage projects.  The NGRBA will plan and monitoring programmes for clanging of Ganga and its tributaries. To begin with, it will concentrate on Ganga main stem.  The NGRBA would draw upon professional expertise within and outside the Government for advise on techno-economic issues.  The technical and administrative support to NGRBA shall be provided by the Ministry of Environment & Forests.

1.6.3. ‘P REPARATORY STEPS ’ AFTER SETTING UP NATIONAL GANGA RIVER BASIN AUTHORITY

 River Basin Management Plan: a notice inviting Expression of Interest to start the process of selecting an appropriate agency to prepare the Ganga River Basin Management Plan has been issued. This has been prepared taking into account inputs received from the Central pollution control Board and the Central Water Commission on the scope of work to be included in the Plan. 30 proposals have been received from leading consultants. The Consultant will be finalized shortly after two stage selection process.  Status Paper: the Alternate Hydro Energy Centre, IIT, Roorkee has been asked to prepare a Status Paper on Ganga which includes the experience of the Ganga Action Plan and the present water quality. It is being finalized. The Status paper will be presented in the first meeting of meeting of the NGRBA.

7 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 Priority Action plan for pollution hotspots: one of the priority functions of the Authority is to implementation river conservation works at pollution hotspots. These activities should commence even as the comprehensive basin management plan is under preparation. MoEF has requested the concerned State Governments to prepare action plans for comprehensively tackling the problem of pollution in the Ganga at the hotspots locations, such as Hardiwar, Varansani, Ahmadabad, Kanpur, Patna and Howrah. These plans are awaited.  SPVs as mode of implementation: the process of consolations with State Government and Urban Local Bodies has been started to discuss he feasibility of having SPVs in the river clearing sector and to evolve the necessary modalities viz. Contractual arrangements, concessions agreements, etc. A meeting was organized on 16th June 2009 with the representatives of the State Governments and the Heads of the Urban Local Bodies as a brainstorming session to begin the process of identifying appropriate locations and the types of river conservation infrastructure where SPVs would be feasible. A presentation was made by IL&FS. State Governments & ULBs have been requested to formulate proposals for implementing this concept on a pilot basis.  GIS Mapping: The National Information Centre (NIC has been entrusted with the work of GIS based mapping of the entire Ganga Basin. This work has already commenced. This will help the users to view and update maps and tabular data relating to pollution abetment works, water quality etc. and analyze the data for monitoring and effective decision making.  Memoranda of Agreement with States: the National Institute of Urban Affairs has prepared a modal Memorandum of Agreement which would link flow of funds to achievement of milestones such as measurable improvements in water quality indicators, implementation of pre determined reform measures and provision s for O&M.  Compendium of Technologies: A Compendium of the treatment technologies available in India and aboard is being prepared by IIT, Kanpur. This can serve as a store house for the NGRBA and would help the State Governments and the local authorities in choosing the appropriate technologies depending upon the totality of local

8 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

circumstances. The compendium would be presented in the first meeting of NGRBA.  The States have to be at the forefront of implementation of the river conservation programme. The Authority, therefore, provides for the State Governments to constitute State River Conservation Authorities under the chairmanship of their Chief Ministers. However, certain States may want the States Authorities to be constituted under the Environment (Protection) Act in which case the notification will have to be issued by the Central Government. A model notification in this regard has been circulated to the State Governments for their consideration.

1.7. Document Organization

This Project report includes three volumes. This document is volume I and various annexure forms volume II and the Project drawings constitute volume III. Volume I include:  Executive Summary: Executive summary of these proposals summarizes the existing sanitation methods, the wastewater infrastructure requirement, infrastructure proposed and the consequent cost estimates of these proposals. It also highlights the need of these proposals & the objectives it aims to achieve.  Chapter I – Project Background: The Chapter discusses the background of Project, NGRBA programme under which project will be implemented, the Scope of Work for this work and in brief describes the project town. It also details the document organisation.  Chapter 2 – The Project Town: This chapter provides a detailed view of the project town including its physical environment i.e. Topography, climate, geology, Water Table, Water bodies etc., demographics, location, industrial, institutional base and tourist locations.  Chapter 3 – Design Criteria: The various design criteria adopted for preparation of these proposals are listed in this chapter. The options available for different parameters and adopted values are described in detail. This chapter also provides prevailing discharge standards for different discharge locations.

9 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 Chapter 4 – Existing Infrastructure: The existing infrastructure related to civic amenities is detailed in this chapter. The existing water supply arrangement, drain & outfalls, solid waste management, and existing system of disposal of wastewater is described herein. Considering the existing infrastructure, justification/need of this project is described herein.  Chapter 5 – Population Projection: The projected population of town for the design period is provided in this chapter. The historical population of town is analyzed and projected by various projection methods available. Population projections of town at ward level is also available in this chapter.  Chapter 6 – Infrastructure Designs: This chapter includes design of various sewerage infrastructure components which includes network design, structural design of sewers, design of pumping stations and force mains.  Chapter 7 – Treatment Process: Various treatment options for treatment of wastewater are described in details. The relative merits & demerits of these options are evaluated for selection of preferred option considering the specific requirements for the wastewater quality, treated wastewater end use, disposal method in this chapter. Availability of land vis-à-vis land required for preferred treatment process is also provided in this chapter.  Chapter 8 – Design of Treatment Plant: This chapter provides various unit processes in the proposed treatment plant. The designs of various units of treatment plant are also included in this chapter.  Chapter 9 – Cost Estimates: The rate analysis and cost estimates of various designed components are provided in this chapter.  Chapter 10 - Project funding & Implementation Plan: This chapter provides the quarterly requirement of funds for this project for different agencies. The packaging options & preferred option is also provided in this chapter. An implementation programme with suitable Gantt Chart is included in this chapter.  Chapter 11 – Operation & Maintenance: This chapter provides the specific requirements for sustainable operation & maintenance of proposed project in long term. The specific manpower, machinery & funds requirement for sustainable O&M of the proposed system is included here. The existing infrastructure of town ULB is described in

10 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

this chapter. The matters like collection mechanism, revenue & expenditures of last few years of ULB, existing municipal bye-laws are included in this chapter.  Chapter 12 – Capacity building: The requirements for capacity building of ULB in view of additional responsibilities are provided herein. Recommendations for generic capacity building measures are also included. Volume II includes various annexure and Volume III contains various drawings of existing & proposed Infrastructural system in the town.

11 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Chapter 2. The Project ToTownwnwnwn

2.1. INTRODUCTION

Hajipur is a very famous city for it's culture. It is the headquarters of (the land of world's first republic 'Lichhvi') district which is in Bihar. It is famous for bananas, newly build railway zonal office and it's glorious past. Patna, the capital of Bihar is only 10 km far from Hajipur which increases it's popularity. The road bridge across Hajipur and Patna ( Setu) is the longest road bridge of , it acts as a connecting path of south and .

2.2. THE STATE

Location The State of Bihar is Situated in the vast Gangetic plain, Bihar is a land- locked state between West Bengal on the east, Uttar Pradesh on the west, Jharkhand on the south and Nepal (international border) on the north, covering an area of 94,163 sq km. A part of Bihar was separated and formed into a new state Jharkhand on November 15, 2000. Demography According to Census 2001, total population of Bihar is 82,878,796 with 43,153,964 men and 39,724,832 women; the population density is 880 persons per sq. kilometer. The number of Children under 0-6 years is

12 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

16,234,539. Total rural population and urban population is 89.5% and 10.5% respectively. Sex ratio is 921. According to 1991 census, the share of population of the Scheduled Castes was 14.56% and Scheduled Tribes was 7.66% in Bihar. This ratio of the STs has changed drastically after separation of Jharkhand from Bihar. History Bihar's antiquity is evident from its name, which is derived from the ancient word "VIHARA" (monastery). It is indeed a land of monasteries. Hindu, Buddhist, Jain, Muslim and Sikh abound in this ancient land where India's first major empires rose and fell. Where the ruins of the worlds' earliest university slumbers in the void of time. The passage of Ganga, flowing wide and deep enrich the plains of Bihar before distributing in Bengal's deltoid zone. Among all Indian states, Bihar is the one most intimately linked to the Buddha’s life, resulting in a trail of pilgrimages which have come to be known as the Buddhist circuit. The Buddhist trail begins at the capital city, Patna, where a noteworthy museum contains a collection of Hindu and Buddhist sculptures as well as a terracotta urn said to contain the ashes of Lord Buddha. The Khuda Baksh Oriental Library has rare Muslim manuscripts including some from the University of Cordoba in Spain. 40 km away, Vaishali, was the site for the second Buddhist Council is the presence of ruins testify. 90 km south of Patna is which translates as the place that confers the lotus’ (of spiritual knowledge). A monastic university flourished here from the 5th to the 11th century. It is said to have contained nine million books, with 2,000 teachers to impart knowledge to 10,000 students who came from all over the Buddhist world. Lord Buddha himself taught here and Hieun Tsang, the 7th century Chinese traveler, was a student. Ongoing excavations have uncovered temples, monasteries and lecture halls. , ‘the royal palace’, 12 km south, was the venue for the first Buddhist Council. The Buddha spent five years at Rajgir after having attained enlightenment, and many of the remains at Rajgir commemorate various incidents related to life of Buddha, the hill of Gridhrakuta being perhaps the most important, as this is where the Buddha delivered most of his sermons. Bodhgaya is the spot where Lord Buddha attained enlightenment, with the marking the precise location.

13 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Topography The topography of Bihar can be easily described as a fertile alluvial plain occupying the north, the Gangetic Valley. The northern plain extends from the foothills of the Himalayas in the north to a few miles south of the river Ganges as it flows through the State from the west to the east. The tract lying between 25°8' & 27°31' North Latitude and 83°20' & 88°17' East Longitude is Bihar. It is bounded on the north by the Kingdom of Nepal, in the south by Jharkhand, in the east by West Bengal and on the west by Uttar Pradesh. Roughly rectangular in shape it comprises mainly the Gangetic Plains, the dissected highlands of Kaimur plateau and the Himalayan foothills occupying a very small tract of the state. The North Gangetic plain extends from the base of the Tarai in the north to the Ganga in the south, comprising an area of about 22,000 square miles. Except for the Someshwar and the Dun hills in the extreme northwest, it presents an almost flat appearance and has an elevation of less than 250 feet above sea level. The Someshwar and the Dun hills cover an area of about 364 square miles in Champaran. They are the lowest and the outermost of all the Himalayan ranges, immediately overlooking the plain, and form part of a long range which runs along the whole length of Nepal, at the southern base of which lies the swampy submontane tract called the Tarai. The Someshwar range runs along the northern frontier of the State for a distance of about 46 miles and varies in altitude from a few hundred feet to 2884 feet at Fort Someshwar, which commands a magnificent view of the Himalayas wrapped in the grandeur of eternal snow. The Dun hills lie to the south of the Someshwar range from which the Dun Valley separates them. They are a range of low hills land extends from about 20 miles from the northwest to the southeast. The Tarai that lies towards their southern margin forms a narrow belt of submontane forest, followed by a prairie land of long reedy grasses. It is mostly marshy and unhealthy. This area of hills is but sparsely populated by an aboriginal tribe called the Tharus. But for this small area of hills in the northwest, one looks in vain in any direction for la hill or mound, which may interrupt the continuity of the level surface. The North Gangetic plain is the playground of rivers- the Gogra, Gandak, Bagmati, Kosi, Mahananda and a host of minor streams, which descend from the Himalayas and make their way to the Ganga in frequently changing channels. The Kosi particularly has earned the bad name of being the most changeable stream in India, shifting its bed all the time.

14 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Because of the large quantities of silt they deposit the rivers at many points flow on ridges slightly elevated above the general level of the country and frequently inundate the low-lying lands on either side during the rains. The South Gangetic plain occupies the greater part of what is popularly known as South Bihar. It is wide towards the west and the middle, and extremely narrow towards the east. The outlying hills and undulations of the Chotanagpur plateau encroach upon the plain from the south, until near Munger they extend in the Kharagpur hills as far north as the Ganga itself, and after a brief recession run along the bank of the river for a considerable distance as the Rajmahal hills. The South Gangetic differs in many respects from the North Gangetic plain. It is higher in the south and slopes towards the Ganga, but the slope is not so gradual as in the North Gangetic plain. While the North is liable to flood and change, the South Gangetic plain is stable and not subject to floods except in limited areas. Moreover, it is much more diversified than the North, and a great many hills spring as islands of high rock from the level alluvium. Notable among the hills that lie scattered in the South Gangetic plain are the Barabar hills, the Rajgir-Jethian hills, and the Kharagpur hills. These hills lie in the districts of Jehanabad, Nalanda and Munger. Though not quite naked, they have been highly denuded, and most of the vegetation has either been cleared away with the axe or has disappeared with the erosion of the surface soil. They therefore present semi-bare rocky surfaces having a thin covering of grass and scrub. In the Kharagpur hills, areas of jungle still survive as but poor remnants of the dense forests which once clothed these hills. The Barabar and the Rajgir hills are generally less than 1,000 feet above sea level, but they exceed 1,000 feet at several places. The Kharagpur hills have several peaks rising above 1,600 feet. High banks on either side contain the trough occupied by the channel of the Ganga. After the close of the monsoon, there appear within the trough large expanses of sand and silt deposits called ‘diaras’ which vary greatly in extent and position every year. The Rajmahal hills form the northeast angle of the Chotanagpur plateau and are the only considerable mass of hills that approach the Ganga in its course in that region. Although nowhere do they rise higher than 2,000 feet they present an extremely varied and picturesque topography. On its eastern margin, the plateau has a height of less than 1,000 feet but the general configuration is still that of an undulating upland. The Kaimur hills, separated from the rest of the plateau by the valley of the Son, are structurally very different from Chotanagpur. They are the easternmost termination of the Vindhyan range and form an

15 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

undulating tableland rising abruptly from the plain in bold and lofty precipices, to eminences of about 1,200 feet above sea level. Forests & Wildlife Among the wildlife, notable are: deer, bears, numerous species of birds, including the peacock, pheasant, and wild fowl, and most notably, the tiger. The forest around Valmiki Nagar, West Champaran is one of the last remaining refuges of this highly endangered species. The forests of Bihar yield valuable commercial products besides the timber. Cane trees are used in the manufacture of an indigenous product for making furniture. A resinous material secreted by the lac insect is valuable commercially. It is the source of shellac. Also, bangles made of lac are very popular among women of Bihar. The silkworm is the source of magnificent silk - haracteristically, the tusser or tussah silk. The majestic banyan tree (Ficus bengalensis), and the related pipal (), dot the entire landscape of the State. Languages is by far the most common language of the state, understood by all. There is a significant number of Bengali speaking people also. They are descendants of the settlers from the old British Presidency of Bengal. English is the language of commerce and is spoken by the educated masses. In addition people speak many dialects in different regions. The major dialects are: Bhojpuri, Magahi and Maithili. Bhojpuri is spoken in the districts of Champaran (East and West), Saran, and Shahabad. Magahi is the dialect of Central Bihar, i.e., the districts of Patna, Gaya and Bihar. Maithili, and its variants, is the dialect of the people in the north-east, i.e., the districts of , Vaishali, , , Saharsa, and Bhagalpur. Trade & Commerce Rich farmland and lush orchards extend throughout the north. Following are the major crops: paddy, wheat, lentils, sugarcane, jute (hemp, related to the marijuana plant, but a source of tough fibers and "gunny bags".) Also, cane grows wild in the marshes of West Champaran. The principal fruits are: mangoes, banana, jack fruit and litchis. This is one the very few areas outside China which produces litchi. There is very little industry in the plain region except for the sugar factories that are scattered all over the

16 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

northern plains, particularly in the western region. Jute is transported to the jute factories located mostly in Calcutta. The principal commercial products of Bihar are:  Crops - rice, wheat, lentils, maize (corn), sugar cane.  Fruits - mangoes, bananas, jack-fruit, and litchis.  Fibers - silk (particularly from the Bhagalpur region in the East, producers of a distinct quality of silk, namely, tussar or tussah); and jute, transported to factories located mostly near Calcutta for easy export of the finished material.  Forest Products - hard wood timber, saal and sakhua from the north; also cane for weaving, particularly from the swamps in of North Bihar. North Bihar, a rich agricultural area, has many industries associated with agricultural products. There are numerous sugar factories scattered throughout the area. Many rice and edible oilmills also dot the landscape. It also has some sundry, but important, manufacturing plants, for example the Button Factory at (East Champaran), and the old and renowned rail wagon manufacturing plant, the Arthur Butler & Co, at Muzaffarpur. Immediately after independence however, a major industrial complex grew around . The industrial plants located there are: the Fertilizer Factory, the Oil (petroleum) Refinery Plant, and the Thermal Power Station. Recently, a Thermal Power Plant has also begun operation at , in the along its border with East Champaran. Regarding commerce and North Bihar, mention must be made of the gigantic annual cattle fair at Sonpur in the , close to the confluence of the Gandak and Ganges rivers. The fair is held around the religious festival of - full moon in the month of Kartik in lunar calendar (corresponding to some time in Oct-Dec in the Gregorian calendar), which marks the end of the holy month of Kartik. Kartik Purnima in 1998 falls on Nov 4. This fair is reputed to be one of the world's largest such fair, where not just cattle but also exotic animals and horses and are traded in large number. It attracts a large number of tourists from many countries. The Government of Bihar, through their Department of Tourism, provide many amenities for their boarding and lodging.

17 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

2.3. THE DISTRICT

The district of Vaishali came in to existence on 12/10/1972. Earlier it was the part of old Muzzafarpur district. Vaishali has a past that pre-dates recorded history. It is held that the town derives its name from King Vishal, whose heroic deeds are narrated in the Hindu epic Ramayana. However, history records that around the time was the centre of political activity in the Gangetic plains, Vaishali came into existence as centre of the Ganga, it was the seat of the Republic of . Vaishali is credited with being the World's First Republic to have a duly elected assembly of representatives and efficient administration. The Lord Buddha visited Vaishali more than once during his lifetime and announced his approaching Mahaparinirvana to the great followers he had here. Five years after the Enlightenment in , Lord Buddha came to Vaishali, the capital of one the first republican states in the Ganga, Vaishali is bound by the hills of Nepal on the north and the river Gandak on the west. Hundred years after he attained Mahaparinirvana, it was the venue of the second Buddhist Council. According to one belief, the Jain Tirthankar, Lord Mahavir was born at Vaishali. The Chinese travelers Fa- Hien and Hieun Tsang also visited this place in early 5th and 7th centuries respectively and wrote about Vaishali. The District is located at 25° to 30° North latitude and 84° to 85° east longitude. The District is surrounded by river Ganga in south, Gandak in west. District Muzaffarpur is in north & Samastipur in East. The District is in semi tropical Gangetic plane. The state capital Patna is linked with famous . The District is spread over 2036 sq km area. There are three sub divisions and 16 Blocks in the District. The District has 1638 revenue villages and 291 Gram panchayats. Traditionally the District was divided into 11 C.D. Blocks but five more Blocks were created during last decade.

2.4. HISTORY

In ancient times after crossing the Ganges at Patna the first village one came to the other side was Ukkacala, now called Hajipur. HAJIPUR, a town of British India, in the Muzaffarpur district, on the Gandak, just above its confluence with the Ganges opposite Patna. Hajipur figures conspicuously in the history of the struggles between and his rebellious Afghan governors of Bengal, being twice besieged and

18 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

captured by the imperial troops, in 1572 and 1574. Within the limits of the old fort is a small stone mosque, Called Pathar ki masjid, very plain, but of peculiar architecture, and attributed to HAJI ILIYAS, its (Haji Pur) traditional founder (c. 1350). Founded on a deep historical background, the first experiments both in the imperial and democratic forms of governance were initiated in the land of Bihar in the 6th century B.C. The empire formed by the Nandas extended from the river Beas in the Punjab to the mouth of Ganga. The Mauryas gradually extended the till it covered the whole of India except a small strip in the south Indian peninsula, but included the northwestern hilly regions as far as the Hindukush Mountains. Similarly, the first great treatise on political statecraft, which was regarded as the most authoritative text on the subject throughout the ancient period, is that of Kautilya, also associated with Magadh. While Pataliputra was the first imperial city of India, Vaishali has the rare distinction of being the seat of first democratic government of the world as early as in the C. 6th B.C. One of the most important contributions of Bihar is the introduction of the art of writing in form of royal edicts during the tenure of the great emperor Ashok. The seals discovered in Harappan sites are no doubt engraved with inscriptions, but unfortunately no connecting link between these seals and the Brahmi alphabet used in ’s edicts has yet been discovered. The Ashokan edicts enunciate the tenets of welfare state, communal harmony and religious pluralism in a very lucid manner. Bihar made a contribution to the development of the Upnishadas as revealed by the traditions associated with , king of Videha. The Brhadaranyaka Upnishad narrates how great philosophers from distant regions, even from Kuru and Panchal came to the court of Janaka and took part in abstruse philosophical discussions about Brahman, soul etc. According to a tradition recorded in the Skanda Purana, Gautam the founder of the Nyaya School of philosophy was born in . It is significant that the reputation of Mithila for this branch of philosophical knowledge persisted down to the medieval age when it enjoyed the reputation of being the only center for learning Navayanyaya. Mithila has been the homeland of eminent scholars such as Yajnavalkya, the author of a famous Smriti Work, and Mandan Mishra, the famous theoretician in Mimamsa, who carried on public debate with Shankaracharya. But the greatest contribution of Bihar to Indian Culture is in the domain of the development of heterodox religions. The founder of , though not born in Bihar, spent the best part of his active life in this province. He began his meditation and

19 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

attained enlightenment in Bodh Gaya. His missionary activity is associated with many localities in Bihar and the first three general assemblies of the Buddhist monks, which gave the final shape to Buddhism, were all held within the geographical limits of Bihar. Two important off shoots of Buddhism in the shape of the two great universities at Nalanda and Vikramshila, both in Bihar, may be reckoned as the two greatest universities in India. Their contribution to the intellectual development of India and to the expansion of Indian culture to Central Asia, China Tibet, Korea, Japan and South East Asia cannot be under estimated. The scholars assembled in these two universities shed luster on the whole of India. Mahavir, the historical founder of was born in Bihar and the early history of Jainism indissolubly bound up with this region. According to Jain tradition, no less than twenty out of twenty-four Tirthankars attained salvation in Parsvanatha hills and two other, including Mahavir, attained nirvana at and Pava, both in Bihar. Among the notable contribution of Bihar to Indian Culture, prominence must be given to splendid buildings of architecture and sculpture, both in stone and metal made during the ancient times. The wonderful palace at Pataliputra has perished, but we may form an idea of its splendour and excellence from Greek and Chinese accounts. The fine metallic polish of Ashokan Pillars and the wonderful lion capital found at Sarnath, now accepted as the emblem of the republic of India, stands out as undying monuments of Bihar’s contributions to the Indian art. The contribution of caves hewn out of solid rock, which developed into one of the finest arts in India, had its beginnings in Bihar; in the oldest saptaparni cave at Rajgir and somewhat later, the cave at Barabar hills in the district of Gaya. Reference should also be made to the contribution of Bihar to the development of regional languages of eastern India. The Aryan languages of eastern India such as Bengali, Assamese and Oriya, all originated from the Magadhi Prakrita i.e. the form of Prakrita, which was current in Bihar. The medieval period is particularly important in the . For one thing, the province obtained its present nomenclature and more or less geographical boundaries during this period. The Turkish invaders first conquered the area at the turn of the 13th century called it Vihar as it contained a number of Buddhist Vihars. Northern Bihar, then a part of the Karnata kingdom was conquered and annexed by Ghiyasuddin Tughlaq in 1329 and with this northern Bihar (Tirhut) and Southern Bihar were politically and administratively unified. Bihar also served as the springboard for the rise of the great Afghan ruler Sher Shah and the laboratory for his momentous

20 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

administrative reforms especially in the sphere of land revenue. Bihar also developed as a significant center of the activities of the early Sufis in India. Long before the establishment of the Delhi Sultanate, Imam Taj Faqih settled at Maner, near Patna. Another eminent saint Shihabuddin Pir Jagjot settled on the eastern outskirts of Patna around the middle of the 13th century. They preached the gospel of universal love, tolerance and brotherhood, initiating the rapprochement between and Hinduism which, in may ways, has been instrumental in bequeathing the syncretic Indo-Islamic heritage to the succeeding generations and ages. Bihar’s role in India’s struggle for independence has been quite significant. Bihar was one of the important centers of the 1857 movements, which was a national challenge to the growing supremacy of the Company. The hero of 1857 struggle in Bihar was the octogenarian leader, Kunwar Singh of Jagadishpur, who was ably assisted by his brother Amar Singh. Kunwar Singh died a warrior’s death, and his example greatly influenced the leaders in Chotanagpur, the Santhal Parganas and other parts of Bihar to carry on an intensive movement against the British. The Wahabi movement, though essentially a religious movement, had an important role to play in Bihar’s struggle for freedom during the 19th century. The political objective of the movement was to free the country from foreign domination, as Syed Ahmed, the founder of the movement in India repeatedly explained in his numerous letters. As the Indian Independence Movement centered on the Indian National Congress, Bihar became an important place for the congress activities. Bihar played a significant role in all the three stages of national struggle- Moderate, Militant and Gandhian phase. It was in Champaran that Mahatma Gandhi after his return from Africa launched for the first time on Indian soil a bold and successful resistance against the British exploitation. After the Champaran Satyagrah, Gandhijee grew very fond of Bihar and and considered it to be “his second home”. On their side, the people of Bihar not only participated enthusiastically in all the movements launched by Gandhijee but also maintained communal amity and harmony, a cause very dear to his heart. Hajipur is also of interest because a portion of Ananda's ashes were enshrined in the town. Ananda acted as the Buddha's personal attendant for twenty years and outlived him by several decades. Hajipur figures conspicuously in the history of struggles between Akbar and his rebellious Afghan governors of bengal.

21 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

2.5. LOCATION

Hajipur is located at 25 042’45” North latitude and 85 015’00” Eastern longitude. It has an average elevation of 46 metres (150 ft). Some of the villages around the town are Quila Larui, Chandpura, Kutubpur Kothi, Langa, Gomati, , Titra, , Kansara, Nandini, Dayalpur, Subhai Garh, Dighi, etc. The location of Town of hazipur in State of Bihar is shown in map provided on next page.

2.6. DEMOGRAPHY

As of 2001 India census, Hajipur had a population of 119,412. Males constitute 53% of the population and females 47%. Hajipur has an average rate of 60%, higher than the national average of 59.5%: male literacy is 67%, and female literacy is 51%. In Hajipur, 16% of the population is under 6 years of age. Other demographic features as per 2001 census are as follows:

Particulars Value

Number of Households 17,050 Population-Total 119,412 Population-Rural 0 Population-Urban 119412 Population(0-6Years) 20,364 SC Population 20,661 ST Population 86 Literates 69,760 Illiterates 49,652 Total Workers 29,810 Main Worker 25,724 Marginal Worker 4,086 Non Worker 89,602 CL (Main+Marginal) 1,894 Al (Main+Marginal) 4,612 HHI (Main+Marginal) 1,875 OW (Main+Marginal) 21,429

Particulars Value

Average Household Size(per Household) 7 Proportion of Urban Population (%) 100

22 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Sex Ratio 871 Sex Ratio(0-6 Year) 913 Sex Ratio (SC) 884 Sex Ratio (ST) 911 Proportion of SC (%) 17 Proportion of ST (%) 0 Literacy Rate (%) 70 Work Participation Rate (%) 25 % of Main Workers 22 % of Marginal Worker 3 % of non Workers 75 Proportion of CL (%) 6 Proportion of AL (%) 15 Proportion of HHI (%) 6 Proportion of OW (%) 72

2.7. CONNECTIVITY

Hajipur is 10 kilometres across the Ganges from Patna. Hajipur can be reached from Patna, which is 10 km across the River Ganga. The nearest airport is at Patna while the railway station is at Hajipur. There are frequent and taxi services from Patna for Hajipur. Hajipur is the headquarters of East Central Railways. Three rail lines connect it to Muzaffarpur, , and Barauni. Important trains like Guwahati , , Garib Rath Express, Swatantrata Senani Express, Sabarmati Express, Lohit Express, Lichhavi Express and all other trains passing from this route have got stoppages here. It is one of the most important railway stations in bihar . and auto-rickshaws connect the city with the state capital Patna. Buses are also available to Muzaffarpur, Samastipur, , , Betiah, Siwan, Chhapra, and Siliguri.

2.8. FACILITIES

The important educational institutes in the town are as follows:  G.A.Inter.school, hajipur (considered as zila school)  Sri Mulkjada Singh High school, Dighi, hajipur  Guru Vasisth Vidyayan ,kachhari road hajipur

23 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 guru vasisth vidyayan ,durga nagar , hajipur  Gyan Jyoti Public school  St. Pauls high school , baghmali, hajipur  st pauls school, izara ,hajipur  Maiden's mascot or surajdeo memorial school  Indian Public school  St. John's public school, SDO road, Hajipur  DAV Public school  Kendriya vidyalay  TOWN HIGH SCHOOL S.D.O ROAD HAJIPUR VAISHALI  Oasis public school, panapur, hajipur  xaviers school hathsarganj and adlbari hajipur  dighi high school, dighi  girls high school, hajipur  town middle school ,hajipur  oxford high school , hathsarganj hajipur.  vikas vidyala , baghmali hajipur.  prem high school , jadua hajipur.  sks seminary school, jadua , hajipur  R.K high school , hajipur  B.D.Public School

Colleges & institutes  S N S College,Hajipur  Women's College  R.N. College  Deo Chand College  Jamunilal College  RBS college hajipur

24 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 Sukhdew Mukhlal College   Teachers Training College  CRK college , hajipur  B.S. Inter-College  ANM training school , hospital road hajipur  INSTITUTE OF HOTEL MANAGEMENT, CATERING & NUTRITION.  Central Institute of Plastic Engg. and Technology (CIPET)  Kent Homoeopathic Medical College and Hospital  Government Industrial Training Institute (ITI), new by pass road, hajipur  (Setting up) National Institutes of Pharmaceutical Education and Research (NIPER)  Rajkiya polytechnic college (proposed) Cinema Halls  National cinema Hall  Ganesh cinema hall  Naveen cinema hall  Umesh cinema hall  Dhramshobha (Presently not working but Best infrastructure)  Shanker Talkies

2.9. TOURIST LOCATIONS

There are number of famous tourist locations in this area. It constitutes major destination for Buddhism tourists. The important tourist locations are shown below: Ashokan Pillar The Lion Pillar at Kolhua is one of Ashokan pillars, which mark the different stages of the Journey to

25 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Nepal, which Ashoka undertook (249B.C.). It bears no inscription.

Buddha I and II These two most important archaeological sites of Vaishali are those where intensive excavations had been done in the past many years. Those excavations have led to discovery of several objects, specially the earthen casket containing the Holy Ashes of Lord Buddha. This casket, well preserved in the , is an object of great attraction for tourists, particularly from the Buddhist countries. Raja Vishal Ka Gadh There is a huge mound, which is situated close to the north of the modern village. The mound is about 6’ to 10’ high above the surrounding country. There are traces of round towers at corners and of a surrounding ditch. The ramparts rise very slightly above the general level of the area inside the mound but from the outside, from the bottom of the ditch, the height is about 15 ft. This mound is called Raja Vishal Ka Garh with a belief that this was originally the King’s fort. Abhishek Pushkarni It is an ancient tank undergoing renovation. It is believed that the Kings of this ancient kingdom had to be first anointed before their coronation with the sacred water of this holy tank. So, it is still a venerated tank. Chaumukhi Mahadeva There is a local tradition that the limits of the ancient city are marked by four at its four corners, of which the two northern ones are still visible, while the two southern one are hidden and hence are called as Gupta Mahadevas. The northwestern and the are quite modern but may be marking the site of an earlier Shaiva shrine. The northeastern lingam is an ancient Chumukhi Mahadev, i.e. a four-faced lingam that stands

26 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

inside a pit and evidently represents the remains of a brick temple. Vishwa Shanti Stupa Japan has recently constructed another World Peace Pagoda in Bihar here at Vaishali, which is similar to that one built at Rajgir on the Ratnagiri Hill.

Balukaram It is an ancient village in Vaishali block situated on the Hazipur-Vaishali road, 30-kms north of Hazipur. The 6th World Buddhist conference was held here. Ramchaura The place is situated in Vaishali block where a fair is held every year on Ramnavami day. The local tradition has it that Lord Ramchandra had a stopover here for a bath on his way to Janakpur. There are some marks on stone, which are said to be his footprints. Konhara Ghat, Sonepur This is a place at the confluence of two rivers- Gandak and Ganges- in Hazipur block, about 36 kms from Patna. It is traditionally believed to be the place where a crocodile caught the mythical that was saved by Lord himself. There is an ancient temple of Hariharnath close to this place, dedicated both to Lord Vishnu and Lord Shiva. A month long world famous big cattle fair is held nearby at Sonepur every year during the Hindu month of Kartik (October-November). This fair is popularly known as Sonepur fair. The village, about 7-kms from the railway station at , contains a mazar of Hazrat Saheb said to be about 400 years old. It is a Muslim pilgrimage. Nepali Temple (Hazipur) There is an old Nepali temple of Lord Mahadeva at Hajipur, about 32 kms from Patna, on the confluence of the rivers Ganges and Gandak. A Subedar of the Maharaja of Nepal erected it. An inn was also attached to

27 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

it. There are erotic carvings on the wooden pillars of the temple showing tantrik influence. It is said that Lord Ram together with Laxman and his guru Vishwamitra had rested at Ramchaura on their journey and the place came to be known as Rambhadra. A fair is held every year on Ramnavami day.

28 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Chapter 3. Design Criteria

3.1. THE MANUAL OF SEWERAGE AND SEWAGE TREATMENT (S ECOND EDITION )

The Manual of Sewerage and Sewage Treatment (Second Edition), Ministry of Urban Development, 1993 is an excellent publication which comprehensively deals with all aspects of sewerage systems from initial planning through design and construction, including management and legal aspects, and then on to the subsequent operation and maintenance of the systems. The proposals and recommendations of the Sewerage Manual, and its previous version of 1986, are normally complied with by all engineering consultants and authorities throughout India for the design of sewerage systems. A number of design criteria have been adopted from the revised guidelines for preparation of DPRs for conservation of rivers & lakes as issued vide office memorandum G.11011/2/2001-NRCD.I dated 13-08-2002 of National River Conservation Directorate (NRCD), Ministry of Environment & Forest, GoI. In general, these proposals comply with the criteria and recommendations of these documents.

3.2. DESIGN PERIOD

For a sewerage system the main component of the project is to design a suitable system of sewers for collecting the waste water generated by the population as domestic effluent, industrial effluent and also likely ground

29 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

water infiltration. Since sewers once laid are extremely difficult to change in size and slope with increasing flow due to expansion in population, it is necessary to adopt a certain rational figure for the likely projected population. It is a generalized practice to design sewers to match the flow of a projected population for thirty years. Too large period will involve very heavy financial burden on the present population, which will not be able to enjoy the benefits, and a small period will soon get overloaded creating insanitary conditions. “Manual for Sewerage and Sewerage Treatment” recommend to adopt a design period of thirty years for all types of sewers and its components. But for pumping machinery it has to match the life of pumping machinery which is generally limited to fifteen years and has to be replaced. For trunk and outfall the period can be reduced provided that there is technical feasibility of subsequent duplication. In case of this project town which will be still a town of moderate size – much less than a metropolitan or city, a design year of 2041 with effective design period of 30 years is adopted for entire sewerage system. For different lift stations, design year for pumping machinery is adopted as 2026 with design period of 15 years. NRCD Guidelines Recommendations Base year—The year of expected commissioning of the project shall be taken as the base year for design of various components of the projects. Design periods of various components may be adopted as under:

S.No. Component Design Period Clarification from base year 1 Land 30 Land will be required to add acquisition STPs. Accordingly, land should be acquired 2 Sewer system 30 3 Sewage 30 Cost of civil works is economical Pumping for full design period. Station – civil works 4 Pumps 15 Considering modular approach

30 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

5 STP 10 Construction may be done with a modular approach in a phased manner as the population grows. 6 Rising mains 30 In case of low velocities, dual rising mains to be examined 7 Effluent 30 Provision of design capacities in disposal the initial stages itself is economical. 8 LCS Required as of base year 9 Crematoria Required as per assessment 10 RFD Required as per assessment 11 MSW Requirement as per assessment

3.3. GROUND WATER INFILTRATION

The quantum of ground water infiltration in sewers depends largely on the -  Depth of sewers and ground water table.  Material and type of jointing and  Workmanship. As the project town is situated on the banks of River Ganga, the water table in the town is very much near the ground. Looking to possibility of infiltration of ground water, it is proposed to adopt strict quality control measures for material & workmanship. However, a provision of infiltration in sewers is adopted as 250 litre/manhole/day.

3.4. FLOW FORMULAE

The manning’s formula is used to calculate the hydraulic gradient in sewers, as given below: V = 1/n A 2/3 S1/2

Where, V : Velocity of flow in meters per second n : Manning’s Constant S : Slope of channel R : Hydraulic radius of section, meter For salt-glazed pipes value 'n' has been adopted as .012 and for Reinforced Cement Concrete pipes value 'n' is 0.011.

31 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

3.5. VARIATION IN FLOW

Since the flow in sewers varies considerably from hour to hour as such peak flows with the following peak function have been adopted for arriving at design flow as per guide lines provided in the Manual.

Contributory population Peak flow Upto 20,000 3.00 20,000 to 50,000 2.5 50,000 to 7,50,000 2.25 Above 7.5 lacs 2.0

3.6. PIPE MATERIAL

Use of three types of wastewater pipes is more prevalent. These are precast concrete (PC), Vitrified Clay (VC) and plastic pipes). All pipes for wastewater drainage should be manufactured to the relevant Indian Standard. In practice, this does not always seem to be the case and so this needs to be checked before ordering and accepting delivery of pipes. The quality of pipes is also important when jointing. In considering the most appropriate pipe material for use in town, the following factors should be considered :  Availability of sizes and fittings, when required,  Cost of materials and installation,  Durability - life expectancy,  Durability - resistance to chemical and biological attack,  Strength,  Condition of installation,  Size - for example, the maximum size for SWG is 600 mm diameter.

3.6.1. PRECAST CONCRETE (PC) PIPES :

Precast concrete pipes are manufactured as standard sewer pipes and as pressure pipes. For sewers, non-pressure, reinforced concrete pipes are normally used. In the past, collar joints have been used with plain-ended pipes, but these have now been superseded by rubber ring, spigot and socket joints. These pipes are governed by IS:458.

32 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

PC Pipes are manufactured in diameters from 80 to 2600 mm in accordance with BIS Standards, and can be supplied with rubber ring gaskets. The jointing system with rubber rings offers the potential for a water-tight and flexible joint which is easy to make in a trench. The pipes are manufactured in 2.0 m lengths for diameters up to 250 mm, and 2.5 m lengths for diameters above 250 mm. Plain ended PC pipes with collar joints are also manufactured, but these are not recommended. Disadvantages of concrete pipes include:  limited range of fittings,  risk of corrosion following hydrogen sulphide formation in sewers,  need for good quality control and supervision over manufacture and jointing. Nevertheless, they have generally proved to be durable and have been used extensively. They are also relatively cheap. They are therefore recommended with the precaution that the standards and specifications for manufacture and installation will be followed.

3.6.2. VITRIFIED CLAY PIPES :

Salt glazed stoneware pipes (SW pipes) are manufactured to BIS Standards in diameters from 100 mm to 600 mm internal diameter in 50 mm steps. Pipes are manufactured in 600, 750 & 900 mm lengths with spigot and socket, cement mortar type joints. A wide range of fittings, including bends and gully traps, is available. Nowadays, rubber ring joints are also being used for pipes of diameter more than 150 mm. Vitrified clay pipes are brittle rigid pipes which are susceptible to breakages during transport and handling. Nevertheless, they are cheap, durable, and suitable for use with corrosive liquids and aggressive ground conditions. They are not susceptible to sulphide corrosion. They have been used extensively for use in house drains, house connections and for main sewers up to about 300 mm diameter. The main disadvantage of stoneware pipes compared with concrete pipes is the greater number of joints that are required because of the short lengths that are manufactured. This increases the cost of laying and increases the potential for infiltration through badly made joints if strong supervision is lacking during the construction phase.

33 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

SW pipes with flexible joints are not available. The standards for this pipe are governed by IS:651.

3.6.3. PLASTIC PIPES :

uPVC pressure pipes are manufactured in diameters from 75 mm up to 400 mm. The pipes are delivered in 5 or 6 m lengths and can be jointed by either rubber gaskets or by solvent welding. Normally, rubber gaskets are used for pipes larger than 100 mm. uPVC is an inert material, and is suitable for carrying many corrosive effluents and for laying in aggressive ground conditions. However, the pipes are susceptible to poor workmanship, when longitudinal warping, cross-sectional distortion and cracking have been experienced. Many of these factors are exacerbated by the thin walled sewer pipes, and it is recommended that, if uPVC pipes are to be used for sewers, then pressure pipes are used rather than sewer class pipework. It is also recommended that very careful attention is given during installation to pipe stacking, handling, trench bedding and backfilling procedures. The uPVC & HDPE pipe specifications are governed by IS Code 4685 and IS 4984. HDPE pipes are proposed to be used in narrow lanes and connected to main sewers using chambers. It is proposed to utilize uPVC pipe of diameter 110 mm & 160 mm for property connections in connecting individual property to public sewers.

3.6.4. DI PIPES

Ductile Iron pipe is also a possible solution for modern sewers. Ductile’s long laying lengths and bottle-tight joints minimize potential infiltration and aid in construction. For most sizes, its larger inside diameters deliver up to several million gallons per day more flow than nominal pipe diameters. Its standard cement-mortar lining ensures an excellent friction coefficient and resistance to scour and cement deterioration from most domestic sewage. And its high material strength resists heavy impact, handles extreme external loadings, and in many cases, there is no need for special bedding or backfill. Ductile Iron pipe can be used in a wide variety of applications, including challenging conditions like deep trenches, shallow cover, seismic activity, subsequent adjacent excavations, beam loading, and ring crushing.

34 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Ductile Iron pipe is especially suited for pressure sewer applications because its standard pressure classes provide for high operating pressures with a allowance for surge pressures. Surges, or hydraulic transients, are a very serious problem for pressure sewers as pump stations are vulnerable to power outages and surge control devices for raw wastewater are not always dependable. In this project, pressure sewers are proposed of Ductile Iron Pipe. The specifications of DI pipe in india are governed by IS:8329.

3.7. THE STRUCTURAL DESIGN OF SEWERS

Sewers and other water pipelines need to be designed structurally so that when buried they can withstand all the external forces to which they are likely to be subjected. As sewers flow under gravity, there are no significant internal pressures to allow for. Providing bedding, haunching and surrounds, which may be of concrete or sand or gravel, are important ways of strengthening a pipeline to withstand higher loading. The basic data on which the need of additional support is determined are the actual strengths of the pipes used, the depths of the laid pipeline and its location (whether in a main road with fast moving traffic, or in a plot with pedestrian traffic only, etc.) The computation of loads on buried pipelines has been established by the work of Marston, Spangle and others, and is summarised in the CPHEEO manual. To allow for settlement and soil movement, it is recommended that all sewers are provided with flexible joints, which should also be self- centering. Such joints are normally formed using rubber rings. The pipe spigots and the interiors of their sockets should be smooth and sound, and made to tolerances which allow this type of jointing.

3.8. MINIMUM AND MAXIMUM SEWER PIPE SIZES

3.8.1. MINIMUM SEWER SIZES

The Design Manual recommends that the minimum sewer pipe size should be 150 mm diameter except for very hilly areas where it may be reduced to 100 mm diameter.

35 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

In many places, sewer blockages regularly occur in the smaller diameter sewers due to misuse by the public, and it is therefore usual to stipulate a minimum diameter of 200 mm for public sewers. It is proposed to adopt minimum size of proposed public sewers as 150 mm diameter. It should be noted that this minimum size does not apply to property connections. The suggested minimum size for these is 100 mm diameter.

3.8.2. MAXIMUM SIZES OF SEWERS

Theoretically, the maximum required size of a sewer pipe depends upon various factors including anticipated maximum flows, the available gradients and flow criteria. It also depends upon what large sizes of pipes are locally available. Economics are also important but are not the only factor to be considered. After a certain size, it becomes cheaper to construct duplicate sewers instead of a single large sewer, when every cost factor - cost of pipes including handling and transport, costs of trench excavation and backfilling, costs of pipe laying and jointing, costs of pipe bedding and other support and protection, the anticipated annual increase in the flow with which the sewer must deal, etc. - is taken into account.

3.9. NORMAL MINIMUM DEPTHS FOR SEWERS

It is not logical to specify a maximum depth for a sewer as this will be dictated by practical and economic considerations. The choice will normally be between having a deep sewer or having a sewerage pumping station. The suggested rule is that sewerage pumping stations should only be proposed with great reluctance, when absolutely necessary. Sewers should always if feasible be laid at depths which will accommodate not only all existing properties but also any future properties within the area which sewers are designed to serve. Minimum depths of cover over sewers are often given as 1200 mm in roads and 900 mm in all other areas. Normal current practice is to have at least 1 m cover above the top of the sewer. It should be noted that the depth of a sewer is not the distance between the sewer invert and the ground level.

36 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

However, applying these criteria to initial lengths of sewer in flat areas will lead to unnecessarily deep sewers, and the cost of providing protection to the first length of a shallow sewer will be saved by the reduction in depth of all the subsequent sewer lengths. A shallow sewer at a depth of 0.6 m, with adequate protection against damage by proper concrete shrouding, will be considered acceptable when this is justified economically and is not technically detrimental It is recommended to adopt a minimum depth of sewer as 1.0 mtrs in general and 0.6 mtr for shallow sewers.

3.10. MANHOLE DESIGN AND SPACING

3.10.1. MANHOLE DESIGN

The Design Manual has a comprehensive section on recommended manhole design with sizes, depending upon both the depth and the size of the sewers, for circular manholes as shown in the following Table 3.1 which are in general adopted. Table 3.1: Minimum Diameters for Circular Manholes (Sewerage Manual, 1993)

Manhole Depth (m) Minimum Manhole Diameter (mm)

0.90 - 1.65 m 900 mm

1.65 - 2.30 m 1200 mm

2.30 - 9.0 m 1500 mm

9.0 - 14.0 m 1800 mm It is recommended to adopt these recommendations with suitable modification as described below: For Brick manholes, following four configurations have been adopted

Type Manho le Depth (m) Minimum Manhole Diameter (mm)

A 0.90 - 1.65 m 900 mm

B 1.70 - 2.50 m 1200 mm

C 2.60 - 5.0 m 1500 mm

D 5.1 - 9.0 m 1800 mm

37 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

For RCC Manhole, two configurations type E (upto 3.5 mtr diameter) and F (beyond 3.5 mtr diameter) with different depth categories have been adopted:

Type Outgoing Sewer Minimum Manhole Diameter Diameter (mm)

E & F 700 1400 800 1500 900 1550 1000 1750 1200 2000 1400 2200 General observations: Manholes less than 4.5 m deep are normally circular in shape and constructed with cement-mortared Brick masonry with internal plastering. Circular construction is preferred to rectangular from strength considerations.. Manholes equal to 4.5 m depth or greater are constructed from cast in situ reinforced concrete or Precast concrete rings. Recently, pre-constructed plastic manhole have also been introduced in the market and the manufacturers claim several advantages for them such as ease of installation and speedier construction of the system, corrosion free service etc. However, the plastics are thermo-labile and may yield under superimposed loads especially during summers. Further, their protection against UV and abrasion is not yet established and they have to be proven by way of long service in tropical countries before their large-scale adoption can be considered. Manholes covers: Ferro Cement Covers/ Cast Iron covers and frames were commonly used in the past in other towns but, because of the widespread theft of these for the scrap value of the cast iron, manhole covers are now usually Pre- cast Ferro Cement type housed/fit in to a cast iron frame which is embedded in a reinforced concrete manhole cover slab. The same is proposed to be adopted for this project. Step irons: It is proposed to use Cast iron steps in this project.

3.10.2. MANHOLE SPACING

38 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

The Design Manual recommends that the maximum spacing of manholes on sewers which cannot be entered for cleaning or inspection should be 30 meters. For sewers of diameter above 900 mm, subject to operational and maintenance requirements / procedures the spacing may be in the range of 90 meters to 150 meters and for sewers exceeding 1500 mm diameter the spacing may be increased to 200 meters. It should be noted that the above criteria are qualified by the fact that manholes should be provided at every change of alignment, grade or diameter, at the head of every system and at every junction of two or more sewers. Additionally, it is a widely followed norm that all property connections should be connected to the sewerage system at a manhole. Therefore the actual spacing will generally be less than the standard spacing recommended by the Manual.

3.11. FLOW CAPACITY OF SEWERS

The Design Manual recommends that a sewerage system should be designed to flow 80% full at peak dry weather flow. The Design Manual says that storm water should not be expected to enter the sewerage system.

3.12. SEWAGE SEPTICITY & VENTILATION

Positive steps need to be made to minimise the chances of corrosion in the future. The recommended precautions are based mainly upon keeping the sewerage systems well ventilated. Sewer ventilation is necessary for several reasons including:  to prevent undue concentrations of hydrogen sulphide and other gases potentially dangerous to concrete and other materials;  to prevent undue concentrations of methane and other gases potentially dangerous to operatives;  hydraulic requirements. The existing regulations and practices are the following:  The Design Manual recommends that sewers are designed to flow at 80% of full capacity in order to allow for ventilation and indicates that ventilating columns should be considered on the sewerage system where there are older property connections with intercepting traps.

39 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 The National Building Code of India realises the need for and encourages sewer ventilation through ventilating pipes on property connections.  The National Code describes and supports various domestic plumbing systems for dealing with both sullage and human excreta. It is recommended to adopt following practices  Where ventilation pipes are provided as part of the house drainage connections, ventilation columns are not required on area sewers. It is recommended, however, that they are used on main trunk sewers for sizes above 450 mm with a spacing of 300 mtr.  It is proposed that every property drainage system should have a vertical ventilating pipe at the upper end of every drain, in addition to any down-pipes discharging into other parts of the drains and which have ventilators to prevent water seals from being broken.

3.13. SEWAGE PUMPING STATIONS AND PUMPING MAINS

3.13.1. GENERAL

When a sewerage system is being designed the aim should be to avoid sewerage pumping stations wherever possible. This is because the pumps and associated equipment automatically form a weak point in the system. However they are necessary where gravity drainage is not feasible in low lying areas or where gravity drainage is not economical because of the cost of excavation. Sewage pumping is always a management problem. Sewage pumping results in the environmental impacts of noise and odor, and there are always environmental risks associated with failure of the pumping station. Also the station creates an environmental nuisance because of the need of vehicular access for repairs, maintenance and sludge removal.

3.13.2. RECOMMENDATIONS

All pumping station shall be preceded by a mechanical screen. A clear spacing between bars as 25 mm at lift station is adopted. For simplicity of maintenance, the sewerage pumping stations of the wet well type are proposed. The electrically driven submersible pumps should be unchokeable and wear-resisting types, capable of passing solids up to 100 mm spheres, and should operate close to their points of maximum

40 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

efficiency. Standby pump units should be provided at all pumping stations. Manual of Sewerage and Sewage treatment by CPHEEO recommends following arrangement of Pumps “ The capacity of pumps shall be adequate to meet the peak flow rate of flow with 50% standby. The capacity of pump is usually stated in terms of Dry Weather Flow (DWF) estimated for pumping station. 5 pumps are usually provided comprising of 2 of 1/2 DWF, 2 of 1 DWF and 1 of 3 DWF capacity ”.

The vulnerability to power failure, and the potential impact of consequent flooding, is considered for each pumping station. Looking to the doubt for the reliability of the electricity supply, standby power diesel generators are proposed to be provided. All pumping station wet wells need to be ventilated to avoid a build-up of hydrogen sulphide. NRCD Guidelines Recommendations Preference may be given to submersible pumps wherever, feasible, they being cheaper and operation friendly. Configuration of sewage pumps shall be as below;

Where rising main is long Peak flow/2 pumps 2 nos.

Non peak flow pumps 2 nos.

Where rising main is short Peak flow/4 pumps 5 nos. 1 standby

It is proposed to provide submersible pumps 4 working and 1 standby in numbers of capacity Peak flow/4 at all the lift stations as per NRCD recommendations

3.13.3. PUMPING MAINS

The recommendations are as following: Pumping mains should be designed with a minimum velocity of 0.9 m/s to avoid sedimentation. The maximum velocity should be determined from an economic comparison between pipeline and energy costs for different diameters of pipe. The minimum diameter for pumping mains should be 150 mm to minimise the chances of blockages. Anchor blocks are required at all changes in direction of the pumping main.

41 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Where high points in the pumping main are absolutely unavoidable, sewage type air relief valves, including an isolating valve to aid maintenance, should be provided. Washouts, leading to a ditch or preferably to a nallah, should be provided at all low points. Manholes and other chambers into which pumping mains discharge should be well-ventilated to avoid a build-up of hydrogen sulphide, the release of which is commonly caused by turbulence.

3.14. SEWER CROSSINGS

Gravity trunk sewers must obviously cross beneath roads and railway tracks. They can either cross above nallahs on a pipe bridge, or they can cross beneath the nallah: It could be, but this is unlikely, that the sewer is so deep that it can cross under the nallah without altering manhole depths and gradients. Provided that there is sufficient cover between the top of the sewer and the firm, true bed of the river, then there is no problem. However, the sewer must always be protected by concrete against possibilities of scour. It is more likely that it will be possible to cross the nallah via a pipe bridge - that is, by supporting each length of sewer pipe, which should be ductile iron or protected mild steel, on concrete or other rigid, firm pillars. This is acceptable provided that the sewer is sufficiently high so that it is clear of the water during maximum flood flow levels.

42 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Chapter 4. Existing Infrastructure

4.1. EXISTING WATER SUPPLY

4.1.1. EXISTING ARRANGEMENTS

The water supply of town is maintained by Public Health Engineering Department. Most of the areas are covered by water supply network only. There are no piped water supply arrangements maintained by any private body. The source of water for Municipal water supply of the town is ground water. There are number of tube-wells through which ground water is drawn. There are three number of high yield tubewells, the locations of which are as follows:  Ward No 14 – Masjid Chowk  PHED Office – Ward No 17  Meenapur – Ward No 33 All these tubewells are in working conditions and are used for pumping water to Service Reservoirs and for boosting directly in water supply networks. There is no water treatment plant in the town as the source of water supply in the town is ground water. In most of the houses, hand operated handpumps are used to draw water from shallow ground water aquifer. Disinfection using chlorination is being practiced in the town water supply.

43 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

The daily water supply in the town is around 92 LPCD. In addition, almost all the households of the town have shallow hand pumps to meet their daily water requirement and the water table in town is quite shallow due to its proximity with Ganga & Gandak rivers. Considering these private sources of water supply, the average daily water supply of the town is 135 LPCD. The average water table in the town is around 15 mtrs.

4.2. EXISTING STORM WATER DRAINAGE FACILITIES

4.2.1. RIVER GANDAK

The town Hajipur is situated on the banks of River Gandak. The river Gandak flows from North to South Direction. The danger level of river Gandak at Hajipur is 50.32 meters. The flood level of River Gandak at Hajipur town for different years are as follows:

Year Maximum Water Level in meters at Hajipur in Month of September

1990 48.83 1991 50.03 1992 49.05 1993 49.12 1994 49.36 1995 49.11 1996 49.9 1997 49.07 1998 49.72 1999 49.46 2000 49.31

The max water levels in river Gandak in month of September for different years are depicted pictorially below:

44 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

4.2.2. EXISTING DRAINS

There is a major drain from Rajendra Nagar to Subhash Chowk via Bagdulhan to Ghurdaur Pokhar. It drains most of the town. The width & depth of drain is varying along its alignment. It is 6 feet wide and 6 feet deep.

Ghurdaur Pokhar Ghurdaur Pokhar

The condition of existing drains is not satisfactory. The existing drains are in dilapidated condition. Moreover, due to inefficient solid waste disposal system in town, most of the drains are choked by polythene bags and often overflows.

45 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Existing Drains Existing Drains

There are number of surface depression spread all across the town. In these depressions during monsoon, the rain water is collected causing a threat of public health & safety. The major locations where storm water & wastewater get collected are as follows:  Sahi Colony  Vir Kunwar Singh Colony  Sanchi Patti  Hela Bazaar  Power House East & West  Jarua Dhobia Pokhar  Ishupur  Jarua Bari Tola

4.3. EXISTING SEWERAGE SYSTEM

There is no sewerage system in the town. The sewage & wastewater is disposed of using different on-site sanitation methods.

4.3.1. SANITATION METHODS

The most common on-site wastewater treatment & disposal practice adopted in town is Septic Tank. In most of the households in newly developed areas and in areas within already developed city the houses with adequate space within its premises wastewater from water closets is connected to septic tanks. The supernatant from these septic tanks is discharged in road side gutters. This wastewater is drained to nearest depression creating pond there.

46 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Kutcha toilets are not uncommon in the town. Though under various programmes, a large number of kutcha toilets are converted in flushed toilets, still in the high density area where individual households have no open space around, one can find kutcha toilets. Open defecation is also not uncommon in the town. In areas near the bank of river Gandak and in areas lying at outskirts of town, open defecation is very common in the town. In general, the sullage water fixtures & fittings are connected with open storm water collection system. All the sullage from different household activities is discharged in roadside nalis & drains. The sullage after flowing in drains is collected in nearby local surface depressions. This collected sullage create unsightly conditions in the locality. These ponds of collected sullage are potential threat to public health as these are breeding grounds of mosquitoes etc.

4.3.2. COMMUNITY TOILETS

In all, there are six community toilets in the town. The location of these community toilets is as follows:

S.No. Location

1 Gandhi Chowk near Nagar Parishad

2 Samaharanalaya Campus East

3 Hospital Campus

4 Hajipur Guddari Campus

5 Kunhara Ghat near Durga Mandir

6 Jarua Guddari

These community toilets are operated & maintained by NGO “Sulabh”/Municipal Council.

4.3.3. NEED OF THE PROJECT

The general drainage of the town is through open drains and these drains often find their way to nearby rivers Ganga & Gandak increasing the pollution load on receiving waters and consequently deteriorating water quality of these rivers and damaging the aquatic ecology of these rivers.

47 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

The absence of appropriate sanitation facilities has led to gross contamination of nallahs and surface water in and around the town, posing high risks through water borne diseases. The present system of disposal of WC effluents is through open drains or septic tank. These drains dispose in lower areas and ponds thereby creating crude pollution of environment and water bodies. Only few house holders have got septic tanks constructed in their houses. The effluent from septic tanks is discharged in open drains and are often overflow, causing bed smell, unhygienic condition & breeding of mosquitoes. Carrying sullage through open drainage system is entirely unsatisfactory and unhygienic. Generally, disposal through septic tanks are recommended only for isolated dwellings away from habitat. With the increasing population and rise in population density of residential area, the problem may become serious for disposal of effluent from septic tanks, because of poor soaking capacity of the soil. Besides due to increasing pressure on land for residential purposes, sufficient land may not be available for providing on site disposal system in the already developed residential areas (old areas). Location of large number of soak pit/septic tanks within the area of municipal council, must be causing pollution of groundwater in the vicinity. In the absence of safe disposal system of sewage as mentioned above, the people of Hajipur are facing unhealthy and unhygienic environment therefore public representatives are also demanding facilities of sewerage system on priority basis. The town requires sound drainage and sewerage especially because the soil, owing to irrigated area/ canal /high level of water table, does not have soaking capacity. After execution of sewerage system by providing underground sewer pipe line network followed by sewerage treatment plant, there will be a marked improvement in water quality of river Ganga & Gandak and the public of Hajipur would find great relief from unhealthy and unhygienic environment.

48 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Chapter 5. Population Projection

5.1. HISTORICAL TREND

The experience of Indian urbanization can be broadly classified into four periods: pre-1920, 1920-1947, post-1947 till 1991(liberalization) and post liberalization. In the pre-1920 period, urbanization largely was a result of commerce and trade rather than industry, with security playing a small but significant role in some cases. The initial growth, till 1931, was extremely slow, but began to pick up pace as the influence of transportation sector expansion was added to the influence of the manufacturing and service sectors. Bihar is India’s poorest and most backward state. It also has the second highest density of population, despite being the least urbanized. In terms of distribution of age, it is also the “youngest” state in India. Bihar has just 130 in Class I, II and III categories. The state has ten Class I towns, 23 Class II towns and 97 Class III towns. Even more interestingly in Bihar we see a reversal of the trend of fast rising urbanization, seen not only in the rest of the country, but also the entire developing world. In terms of urbanization Bihar has the least number of people living in towns with just 15.2% residing in them as compared to 28.8% in the rest of India.

49 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

There seems to be a reverse flow in the last decade with urban Bihar actually contracting from 11.4 million in 1991 to 8.7 million in 2001, a decrease of 23.6% though the state’s decennial population growth rate of 28.4% was among the highest in the country. One reason for this is the “loss” of Jharkhand with large towns like Ranchi, Dhanbad and Hazaribagh and with the urbanized population accounting for 6 million of its 26.9 million. Even after accounting for this significant event, the level of urbanization in 2001 was 13.19%, which is marginally less than what it was (13.38%) in 1991. The declining pace of urbanization in Bihar can be attributed to low industrialization around (and in) urban areas, which has possibly discouraged youths from rural areas in quest of employment to migrate to the cities of the state. The deteriorating physical conditions in the towns contribute just as much as the lack of economic opportunity to the reversal in urbanization in Bihar. The approach to the process of urbanisation until recently has been largely "reactive" in the sense that problems have sought to the addressed in a knee-jerk manner. Urban planning needs to be anticipating and based upon an integrated approach to address the various dimensions of urban development. Nevertheless, the growth of population and marginal influx into urban areas has put the aging and creaking urban infrastructure and services under a severe stress. The increasing pressure on urban environment is taking its toll on the quality of life of the urban population. In addition to the low industrialization of truncated Bihar, until recently, there is little by way of urban construction or renewal in Bihar. The population figures of Hajipur city must be viewed in the above context as well and interpreted accordingly. Further, the city has a very close proximity to Patna, the State Capital, from which it is only ~12 km away. The census data available from the census year 2001 are reproduced below:

S.No. Year Population 1 1901 21398 2 1911 19233 3 1921 16760 4 1931 19299

50 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

S.No. Year Population 5 1941 21963 6 1951 25149 7 1961 34044 8 1971 41890 9 1981 62520 10 1991 87687 11 2001 119412

The city has shown a negative growth from 1901 to1921 which in part recurrent famines & floods may account for. It has grown steadily thereafter Certain anomalies are clearly visible in population growth trend from these records. There is a high population growth after independence that is quite understandable, in the context of partition and its aftermath, followed up by rural to urban migration. The decadal growth & incremental increase rate in the past decades as per census data is reproduced as below:

S.No. Year Population Decadal Growth % Increase in Incremental (Increase in Population per Increase Population per Decade Decade)

1 1901 21398 2 1911 19233 -2165 -10.12% 3 1921 16760 -2473 -12.86% -308 4 1931 19299 2539 15.15% 5012 5 1941 21963 2664 13.80% 125 6 1951 25149 3186 14.51% 522 7 1961 34044 8895 35.37% 5709 8 1971 41890 7846 23.05% -1049 9 1981 62520 20630 49.25% 12784 10 1991 87687 25167 40.25% 4537 11 2001 119412 31725 36.18% 6558 9801.4 20.46% 3766

The graphical representation of past population trends is shown below:

51 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

The city’s population growth rate has considerably increased in the last decade, and can be considered on higher side. There were two distinct peaks in the growth rate curve. The first one was during decades when the decadal average growth rate was approximately 36 percent and the other one was in the 1971 –81 decade when it abruptly increases up to 49.2% from the past decade. The first of the two peaks can be attributed to the change in-the definition of Urban Areas. The city’s population growth rate is showing a decreasing trend in the since 1981 and was 36.2% percent in the last decade (1991-2001) The decreasing trend of population is a sign of absence of economic opportunities in the city and perhaps an overloading of infrastructure and security not addressed effectively. Thus Patna appears to have acted as the preferred destination for new migrants.

5.2. CENSUS 2001

As per Census 2001, the population of town Hajipur is 119412. The town has 39 number of wards. The ward wise population of town as per 2001 census is as follows:

52 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

S.No. Ward Population No. 2001 1 1 2862 2 2 2613 3 3 3223 4 4 2914 5 5 2563 6 6 3290 7 7 2786 8 8 2743 9 9 2747 10 10 3336 11 11 2917 12 12 2908 13 13 3299 14 14 3486 15 15 3472 16 16 2850 17 17 3317 18 18 3234 19 19 2736 20 20 2725 21 21 2991 22 22 3048 23 23 2941 24 24 3062 25 25 2936 26 26 3485 27 27 2978 28 28 3530 29 29 3143 30 30 3237 31 31 2720 32 32 3017 33 33 3134 34 34 2615 35 35 3207 36 36 2796 37 37 3408 38 38 3547 39 39 3596 Total 119412

Index plan showing city wards is available on the following page

53 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

5.3. POPULATION PROJECTIONS METHODOLOGY

A number of methods for population projection are recommended by Manual of Water Supply and Treatment by CPHEEO and are listed below: i. Demographic Method of Population Projection ii. Arithmetic Increase Method iii. Incremental Increase method iv. Geometric Increase Method v. Decreasing Rate of Growth Method vi. Graphical Method vii. Logistic Method viii. Method of Density The different mathematical formula used for population projections are as follows:

(i) Arithmetic increase Method

(ii) Incremental Increase Method

(iii) Geometric Increase Method

Manual on water supply says that i. Arithmetical Increase method is generally applicable to large and old cities. This method gives a low value and is suitable for well settled and established communities.

54 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

ii. Geometrical increase method gives much higher value and is mostly applicable for growing towns and cities having vast scope for expansion. iii. Incremental increase method increases the figures obtained by the arithmetical increase method. iv. Graphical Method – In this method population curve of the city (i.e. population v/s past decades) is smoothly extended for getting future value. This extension has to be done carefully.

5.4. POPULATION PROJECTION

The Sewerage System is recommended to serve for a period of 30 years as per guidelines of the ‘Manual on Sewerage & Sewage Treatment’ published by C.P.H.E.E.O., Ministry of Urban Development, Government of India, therefore, the design period of the proposed system has been adopted as Year 2041 with the assumption that the project execution will start in 2009 and project facilities will start functioning by Year 2011. The population of Hajipur town has been projected using Arithmetic increase, Incremental Increase, Geometric Increase and Graphical Projection methods. The growth rates for past decades from 1961 onwards have been considered, as pre-independence decades are not representative of currently observed growth trends. The detailed population projection exercise is available at Annexure ‘A-2’. The projected population of town by different methods is summarized below:

S.No Year Projected Population Arithmetical Geometric Incremental Graphical Average of Progression Method Increase Projection four Method Method Method methods

1 2001 119412 119412 119412 119412 119412 2 2008 134350 147980 139087 147336 142188 3 2011 140752 162229 148714 160219 152979 4 2021 162092 220399 185975 208021 194122 5 2026 172762 256891 207591 234723 217992 6 2031 183432 299426 231196 263293 244337 7 2041 204772 406790 284377 326036 305494

55 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

The results of population projections for the town are depicted graphically below:

450000

400000

350000

300000

250000

200000

150000

100000

50000

0 2001 2008 2011 2021 2026 2031 2041 Projected Population Arithmetical Progression Method Projec ted Population Geometric Method Projected Population Incremental Increas e Method Projec ted Population Graphic al Projection Method Projected Population Average of four methods

It is recommended to use average of all the four population projection methods for arriving at the design population of municipal area of Hajipur town for this project as arithmetic increase and increment increase method are providing too low results that do not represent present or likely future growth rates, considering that many of the bottlenecks to the growth are likely to be addressed by UIDSSMT and IHSDP as also to relieve pressure on Patna. The results provided by Geometric growth rate method and Graphical projections made in respect of growth potential provided comparative larger figures. A more realistic assessment for design population can be arrived at by taking average of all the four methods. The future populations for various years is adopted as arrived by averaging all the four projection methods and provided below:

S.No Census Adopted Year Projected Population 1 2001 119412 2 2008 142188 3 2011 152979 4 2021 194122 5 2026 217992

56 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

S.No Census Adopted Year Projected Population 6 2031 244337 7 2041 305494

5.5. MICRO LEVEL POPULATION PROJECTION

Considering the Growth potential and physical limitations, Wards of Hajipur town have been divided in three Categories; which are: I Wards with high growth potential. II Wards with moderate growth potential. III Fully saturated wards The Old city, which is at the heart of the city, is densely populated and has almost reached its saturation density with the caveat that multistory construction is strongly prohibited, as it should be. Quite a few people have migrated to outer colonies. However, vertical growth is taking place of late in the newer areas and should be strictly regulated so as to match the existing and planned infrastructure. The wards in these areas especially near the Highway and towards Patna could have very high growth in future. The areas especially around Old city, eg. 17 to 22 are already in an overly developed state and also some of the other areas such as ward no 5 near Railway Station etc. are comparatively well developed. The wards covering such areas are considered to grow at low pace. The areas in wards e.g. 6,8, 12 to 13, 24 to 26, 29 to 32 , 34, 35 , 37 to 39 have significant open areas and reasonable to good connectivity and are expected to grow at much higher pace on these accounts. Rest of the areas are considered in category II which are either physically constrained e.g. due to railway lines, canals, rivers etc. and have only a moderate scope for future growth. The projected populations at micro level for individual wards as carried out are as follows:

S.No. Ward Population Area Density Growth Density Population No. 2001 (Ha) 2001 category 2041 2041

1 1 2862 91.5312 31 II 70 6407 2 2 2613 54.769 48 II 110 6024 3 3 3223 47.7 68 67 II 160 7642

57 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

4 4 2914 45.243 64 II 150 6786 5 5 2563 20.037 128 III 190 3807 6 6 3290 42.265 78 I 250 10566 7 7 2786 29.959 93 II 215 6441 8 8 2743 41.865 66 I 210 8791 9 9 2747 44.397 62 II 150 6659 10 10 3336 32.032 104 II 250 8008 11 11 291 7 17.303 169 II 400 6920 12 12 2908 66.741 44 I 140 9343 13 13 3299 44.372 74 I 250 11092 14 14 3486 9.765 357 II 840 8202 15 15 3472 17.687 196 II 460 8136 16 16 2850 14.349 199 II 465 6672 17 17 3317 17.257 192 III 280 4831 18 18 3234 28.153 115 III 175 4926 19 19 2736 36.578 75 III 110 4023 20 20 2725 13.400 203 III 300 4019 21 21 2991 28.739 104 III 150 4309 22 22 3048 16.996 179 III 260 4419 23 23 2941 24.390 121 II 300 7317 24 24 3062 15.438 198 I 650 10034 25 25 2936 195.303 15 I 45 878 8 26 26 3485 46.298 75 I 240 11111 27 27 2978 25.055 119 II 280 7015 28 28 3530 76.504 46 II 105 8032 29 29 3143 41.663 75 I 240 9999 30 30 3237 28.840 112 I 370 10670 31 31 2720 145.718 19 I 60 8743 32 32 3017 58.305 52 I 165 9620 33 33 3134 11.58 4 271 II 675 7818 34 34 2615 26.459 99 I 320 8466 35 35 3207 34.342 93 I 300 10302 36 36 2796 9.067 308 II 700 6346 37 37 3408 100.732 34 I 110 11080 38 38 3547 263.572 13 I 40 10542 39 39 3596 128.759 28 I 90 11588 Total 119412 305494

58 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Chapter 6. PPProposedProposed Sewerage System

6.1. INTRODUCTION

Sewer networks are designed to collect & convey the wastewater generated in properties across the town to its treatment/disposal site. Sewer networks are planned & designed to achieve its intended objective throughout its lifetime without any risk to public health, public safety & environment. The objective for properly designed sewer networks is to  Achieve self cleansing velocity to avoid silt depositions.  Effective ventilation  Avoidance of back surcharging  To minimize the infiltration  Structurally safe While designing the sewer network for this project all the above objectives have been kept in consideration.

6.2. PROPOSED SEWERAGE ZONES

The drainage zone boundaries are generally restricted by natural & man- made features such as Railways, National Highways, Rivers, Canal, Drains etc. The major geographical features that delimits the zonal boundries are National Highway No 19 from Patna to Muzzafarpur and railway lines.

59 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Constraints from these features, the town is divided in three major geographical zones as described below:  The Zone in North West direction with its south-east boundary as railway lines passing through the town.  The zone east of National Highway  Rest of the town lying south of National Highway Considering the ground relief, the major sewerage zones emerges are as follows:  The Zone in North West direction in north of railway line comprising of ward No. 1, 2 and 3. This area is draining towards its eastern border.  The zone in between the railway line and national highway comprising of Ward Numbers 4, 5, 6 and 8 is sloping in north-eastern direction near Ramashish Chowk, Golamber.  The zone comprising of ward No. 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24 and 27 is also sloping towards north eastern direction towards Ramashish Chowk, Golambar.  The area along the National Highway to its west direction comprising of ward no 25, 26, 28, 32 and 37 is sloping towards Yusufpur area near National Highway.  The area east of national highway. There is natural drain in the northern side of town which flows from Gandak River towards River Ganga. This canal is about 20 feet wide and 8-10 feet deep. It is proposed to discharge treated effluent in this canal for its ultimate disposal in River Ganga.

Drain Drain

60 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

6.3. PROPOSED NETWORK LAYOUT

Sewer networks layout is planned for the project area keeping in consideration following broad principles.  Minimise the crossings of major barriers like National highways, Railways, Rivers, Drains, canals.  Sewers are laid along natural drainage line to minimize the depth of excavation.  The drainage path from different locations to disposal site is to kept minimum.  Trunk & sub-trunk mains layout is kept along major roads. Looking to the town topography and lateral expanse of town population, whole of town is proposed to discharge at a single location. The selected disposal point is on the northern side of Industrial area of Hajipur Town. The sewer network is laid to follows the ground profile within the zones as described above. Along the National Highway sewers are proposed to be laid on both the sides to avoid crossings. It is proposed to provide two pumping stations in the proposed network to restrict the depth of excavation to 8.0 mtr in general, which are as below: Pumping Station No 1 : This pumping station is proposed to be located near Gudha Pokhar. It will receive wastewater from whole of the north- western area and South-Western area. Pumping Station No 1 is proposed at node 2535. The wastewater collected from this zone is pumped to Node No 2549 through a pumping main of 500 mm diameter. The flow for various years at this pumping station are as follows; Average Flow (lps) Peak Infiltration Peak Flow (lps) 2011 2026 2041 Factor 2026 2041 124.619 177.580 248.86 2.25 10.74 410.29 570 .68

The details of pumps proposed to be provided at this pumping station is as follows: Flow Head Efficiency Number Standby kW Adopted Cum/hr 369.26 13 50% 4 1 26.1 27.0

61 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Pumping Station No 2 : This pumping station is proposed to be located near Yusufpur area. It will receive wastewater from southern area of town. Pumping Station No 2 is proposed at node 1593. The wastewater collected from this zone is pumped to Node No 2556. The flow for various years at this pumping station are as follows; Average Flow (lps) Peak Infiltration Peak Flow (lps) 2011 2026 2041 Factor 2026 2041 46.025 65.584 91.91 2.25 4.41 151.97 211.21 The details of pumps proposed to be provided at this pumping station is as follows: Flow Head Efficiency Number Standby kW Adopt ed Cum/hr 136.78 12 50% 4 1 8.9 9.0 There is one railway crossing near railway over-bridge. There are five National Highway crossing in the town, locations are as follows; It is proposed to get these crossings through trenchless technology.  Firangi Roy Chowk  Ram singh chowk Golambar 1  Paswan Chowk  South of Hotel Food & Fun  Underpass on Nakash Road The outfall will follow the Jandaya road and move eastwards, collecting the wastewater from southern area shall move northwards through Industrial area and terminate at proposed Sewage Treatment Plant Site. The area just at the southern boundary of has general ground profile in southward direction. This area is still undeveloped and connecting this area to proposed sewer network will further deepen the whole network, therefore this area is not considered in the proposed sewer network.

6.4. DESIGN OF SEWERAGE NETWORK

Proposed Sewerage network has been designed using the design principles described in Chapter 3: Design criteria. The major criteria used are provided below:

62 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 A per capita water supply figure of 135 LPCD with 80% contributing to wastewater is adopted to arrive at expected wastewater flows in sewers.  An infiltration value of 250 lit/manhole/day in pipe is adopted considering the high water table in the town.  A minimum diameter of sewer pipe is adopted as 150 mm as currently in practice.  A minimum earth cover of 1.0 m is kept for all the pipes.  For sewer pipes in initial reaches, it is difficult to achieve the minimum velocity of 0.8 m/s. It is proposed to lay 150 mm diameter sewers at a gradient of 1 in 160 and to have provision of mobile flushing units for regular flushing all initial sewers at regular time interval.  All subsequent pipes are designed to achieve a minimum flow velocity of 0.8 m/sec.  Crown of outgoing sewer is matched to crown of lowest of incoming sewers in that particular manhole. The detailed result of hydraulic analysis of sewer network is available at Annexure ‘A-3’. The summary of sewer network is as below:

Diameter Length of (mm) Sewers (m) 150 21078.2 160 20164.0 200 135122.2 250 3367.4 300 2280.2 350 4714.6 400 2807.7 450 13.2 500 1541.9 600 1881.5 700 1848.9 800 768.5 1000 697.3 1200 2129.2 Total 198414.8

63 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

The depth wise summary of different diameters is as follows:

Length of Sewers for Depth (m) Diameter 1-2m 2-3m 3-4m 4-5m 5-6m 6-7m 7-8m 8-9m Total 150 20994 38.6 45.6 21078.2 160 20164 20164 200 77980.7 32819.5 14656.7 5757.1 2852.1 902.2 153.9 135122.2 250 794.7 940.3 1380.2 252.2 3367.4 300 314.9 607.9 1119.3 238.1 2280.2 350 252.3 1531.5 622.1 2153.5 155.2 4714.6 400 279.1 1722.3 712.6 93.7 2807.7 450 13.2 13.2 500 619.4 922.5 1541.9 600 441 478.8 745.4 216.3 1881.5 700 1062.5 786.4 1848.9 800 768.5 768.5 1000 529 143.3 25 697.3 1200 105.8 1526.3 437.8 59.3 2129.2 Total 119138.7 33828.1 16686.3 9115.9 7826.8 8225.4 3534.3 59.3 198414.8

6.5. STRUCTURAL DESIGN OF SEWER PIPES

Generally sewers are laid in ditches or trenches by excavation in natural or undisturbed soil and then covered by refilling the trench to the original ground level.

6.5.1. LOAD PRODUCING FORCES

The vertical dead load to which a conduit is subjected under trench conditions is the result of two major forces. The first component is the prism of soil within the trench and above the top of the pipe and the second is due to the friction or shearing forces generated between the prism of soil in the trench and the sides of the trench produced by settlement of backfill .the resultant load on the horizontal plane at the top of the pipe at the top of the pipe within the trench is equal to the weight of the backfill minus these upward shearing forces. Soil loads The loads on rigid conduits in trench condition is given by the marston’s formula in the form

Wc = C d x w x B2 x d • Wc = the load on the pipe in kg per linear meter • W = the unit of backfill soil in kg/m3 • Bd = the width of trench at the top of the pipe in m and

64 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

• Cd =the load coefficient which is a function of a ratio of height of fill to the friction coefficient between and the backfill and the sides of the trench. Equation gives the total vertical load due to backfill in the horizontal Plane at the top of the conduits as shown in fig, if the pipe is rigid. For Flexible conduits ,the formula may be modified as

Wc = C d w B c Bd Where Bc is the outside width of the conduit in m Concentrated load The formula load due to superimposed load such as a truck wheel is Is given in the following from by Holl’s integration of Boussinesq,s Formula

Wsc = C s (PF/L) Where • Wsc = the load on the conduit in kg/m • p = the concentrated load in kg acting on the surfaces • F = the impact factor(1.0 for air field runways 1.5 for the highway Traffic and the air field taxi ways, 1.75 for the railways traffic • Cs = the load coefficient which is a function of Bc/2H and L/2H • H = the height of the top of the conduits to ground surface in m • Bc = the outside width of conduit in m, and • L = the effective length of the conduit to which the load is transmitted in m. The effective length of the conduit is defined as the length over which the average load due to surface traffic units produces the same stress in the conduit wall as does the actual load which varies in intensity from point to point. This is generally taken as 1M or the actual length of the conduit if ti is less than 1m.)

6.5.2. SUPPORTING STRENGTH OF RIGID CONDUIT

The ability of a conduit to resist safely the calculated earth load depends not only on its inherent strength but also on the distribution of the vertical load and bedding reaction and on the lateral pressure acting against the sides of the conduit. The inherent strength of a rigid conduit is usually expressed in terms of the three edge bearing test results, the conditions of

65 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

which are, however different from the field load conditions. The magnitude of the supporting strength of a pipe as installed in the field is dependent upon the distribution of the vertical load and the reaction against the bottom of the pipe. It also depends on the magnitude and distribution of the lateral pressure acting on the sides of the pipe.

6.5.3. LOAD FACTORS FOR DIFFERENT CLASSES OF BEDDING

The load factors for different class of beddings as recommended by CPHEEO manual are as follows:

Class of Condition Load Bedding factor A a Concrete cradle plain concrete and lightly 2.2 tamped backfill A b Concrete cradle plain concrete with 2.8 carefully tampled backfil A c Concrete cradle RCC with p-0.4% Upto 3.4 A d Arch type plain concrete RCC with p-0.4% RCC with p-0.1% Upto 3.4 (p is the ratio of the area of steel to the area Upto 4.8 of concrete at the crown) B Shaped bottom or compacted granular 1.9 bedding with carefully compacted backfill C Shaped bottom or compacted granular 1.5 bedding with lightlyted backfill D Flat bottom trench 1.1 The granular material used must stabilize the trench bottom in addition to providing a firm and uniform support for the pipe. Well graded crushed rock or gravel with the maximum size not exceeding 25mm is recommended for the purpose

6.5.4. TECHNO -ECONOMIC ANALYSIS

The combination of pipe class and pipe bedding is arrived at by carrying out a detailed techno-economic analysis. The unit rates of pipe laying and pipe beddings are analyzed using SoRs currently enforced in State of Bihar. For different pipe diameters and invert depths, the various combinations of pipe classes and pipe beddings are analyzed for their load carrying capacity with required factor of safety. The loads are computed as per recommendations of CPHEEO manual and as discussed above. The rates of all the combinations of pipe classes and bedding types is calculated. The final pipe class and bedding type combination is selected which can withstand the imposed loads and which is most cost-effective. The

66 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

detailed analysis for different pipe diameters and representative invert depths for this project is available at Annex A-7. The summary of techno economic analysis is provided below:

Diameter Invert Depths (m) (mm) 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 11000 12000 150 NP2 - A NP3 - A NP3 - A NP4 - A NP4 - A NP4 - A NP4 - A NP4 - A NP4 - A NP4 - A 200 NP3 - A NP3 - A NP2 - B NP2 - B NP3 - B NP3 - B NP3 - B NP3 - B NP4 - A NP4 - A NP4 - A 250 NP2 - B NP2 - B NP2 - B NP2 - B NP3 - B NP3 - B NP4 - A NP4 - A NP4 - A NP4 - A NP4 - A NP4 - A 300 NP2 - B NP2 - B NP2 - B NP4 - A NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B 350 NP4 - A NP2 - B NP2 - B NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B 400 NP4 - A NP2 - B NP2 - B NP4 - A NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B 450 NP4 - A NP2 - B NP2 - B NP4 - A NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B 500 NP2 - B NP2 - B NP4 - A NP4 - A NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B 600 NP2 - B NP2 - B NP2 - C NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B 700 NP2 - B NP2 - B NP2 - C NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B 800 NP2 - B NP3 - A NP2 - C NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B 900 NP2 - B NP3 - A NP4 - A NP4 - A NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B 1000 NP3 - A NP3 - A NP4 - A NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B 1100 NP2 - C NP3 - A NP3 - A NP3 - B NP3 - B NP4 - A NP3 - C NP3 - C NP4 - B NP4 - B NP4 - B 1200 NP3 - A NP4 - A NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B NP4 - B 1400 NP3 - A NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - B NP4 - C NP4 - C NP4 - C 1600 NP4 - A NP4 - A NP4 - A NP4 - B NP4 - B NP4 - B NP4 - C NP4 - C NP4 - D NP4 - D The four bedding types adopted in this project are as follows:

Pipe Bedding Type Pipe Bedding description

A Shaped bottom or compacted granular bedding with carefully compacted backfill

B Concrete cradle plain concrete with carefully tampled backfil

C Concrete cradle RCC with p-0.4%

Arch type plain concrete D RCC with p-0.1%

67 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Chapter 7. Wastewater Treatment Process

7.1. GENERAL

Wastewater management is a costly business. Once wastewaters (i.e. any combination of domestic sewage and industrial effluents) are produced and collected in sewerage systems, then treatment becomes a necessity. Sewage has been seen as a problem requiring treatment and disposal. Most conventional sewage treatment options are based on approaches, which usually meant a reduction in biodegradable organic material and suspended solids, plus perhaps some nutrients (nitrogen and phosphorous). Treatment has involved the ‘removal’ of these pollutants, but removal is usually conversion to another product, usually sludge. The disposal of sewage sludge is a major consideration, and it is often seen as an offensive product which is either dumped (now required to be land- filled or used as compost) or burned.

7.2. SEWAGE CHARACTERISTICS

While determining quantity of flow it is essential to decide the capacity of the treatment plant, equally important is to determine the characteristics of the inflowing sewage on which depends the choice of treatment methods/processes that may be adopted. Assessing the quality also helps in

68 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 deciding the beneficial uses that the effluent after treatment may be put to.  presence of industrial discharge, if any, can also be determined  presence of toxicants or other interfering compounds like surfactants  quantity of nutrients present to support biological processes. Domestic sewage primarily consists of spent water from kitchens, bathrooms and toilets etc. The factors that influence the variation in sewage quality are per capita consumption of water and economic status as it affects water usage habits.

7.2.1. IMPORTANT PARAMETERS

Important parameters with relation to sewage quality reaching the proposed STP are discussed below

7.2.1.1. PH VALUE

Normally due to various products used in households, pH of sewage is higher (alkaline) than that of water supply. Discharge of small quantities of trade effluent from textile processing units is not likely to affect the pH of sewage. However if sewage flows long distance and is in not properly ventilated sewers, it may turn septic i.e. pH may get reduced. In present case sewers are of adequate size and well ventilated, therefore development of septic conditions is not expected.

7.2.1.2. SOLIDS

It is obvious that solids, suspended and dissolved in spent water is considerably higher than that in water supply. Though concentration of solids is usually less than 1 percent, it contains substantial quantity of putrescible (biodegradable) matter, which on decomposition yield foul odour. Amount of suspended solids in ambient air is high all through the year. This as well as the fact that in many households (especially in low income group) ash or soil is used for cleaning the utensils results in higher concentration of suspended solids (inorganic) in sewage. Cooking waste, disposal of leftover and toilet effluents contribute to suspended solids of organic nature.

7.2.1.3. NUTRIENTS

Basic nutrients of importance in STP are Nitrogen and Phosphorus compounds. Leftover food materials containing proteins and other food

69 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

residues contain both the N and P compounds. Nutrients concentration in relation to BOD in the approximate ratio of 100(BOD) : 5(N) : 1(P) is considered adequate to support biological processes in STP. The sewage analysis shows the presence of these in adequate quantity.

7.2.1.4. BIOCHEMICAL OXYGEN DEMAND (BOD)

BOD is a measure of concentration of biodegradable matter present in water, measured under a standardized test procedure. Based on the long term studies of sewage from various towns in India, it has been inferred that on an average per person contribution of BOD is 45 gms/day. BOD is an important parameter based on which secondary/tertiary biological processes are designed and effluent discharge standards are set. Wastewater containing degradable organic matter (BOD) when discharged in a water body (river or lake) it consumes oxygen in the process of oxidation of degradable matter, which results in depletion of dissolved oxygen levels. Depletion of dissolved oxygen below the levels of 4 mg/l may result in mortality of fish and other aquatic life. This in a way also governs the BOD concentrations that may be permitted in treated effluent. If the effluent is discharged in a perennial river with substantial discharge, higher BOD may be permitted as the rivers have their own self purification capacity.

7.2.1.5. CHEMICAL OXYGEN DEMAND (COD)

COD represents the total oxygen required to oxidize all the organic matter, degradable and non-degradable (refractory) present in sewage as well as the oxygen consumed in oxidizing some of the inorganic salts under the test conditions. As is clear from the definitions of BOD and COD, COD representing overall oxygen requirements is always higher than BOD. Further BOD to COD ratio is taken as biodegradability of the waste water. Sewage normally has ratios varying from 1:2 to 1:2.5 and is considered as “degradable”.

7.2.2. EXISTING WATER /W ASTEWATER CHEMICAL ANALYSIS

To estimate the expected pollution load on proposed Sewage Treatment Plant & to decide on treatment process, it is essential to have a thorough knowledge of the strength of expected influent in terms on concentration of various pollutants. It is equally necessary to have the knowledge of concentration of various elements & compounds in drinking water supplied to town as the users only add pollution to this supplied water.

70 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

7.2.2.1. DRINKING WATER CHARACTERISTICS

The drinking water supplied to town is analyzed for its composition. Samples are collected from following locations:  1.  2.Diggi West The physical-chemical analysis of these water samples is as follows:

S.No. Parameters Unit Adalpur Diggi West

1 Turbidity JTU 5 2

2 Color Units of Pt-Co Scale 5 5

3 pH 7.5 7.1

4 Conductivity Micromhos/cm 860 1076

5 Hardness Mg/l 420 380

6 Alkalinity Mg/l 260 320

7 Calcium Mg/l 120 80

8 Magnesium Mg/l 72 72

9 Chloride Mg/l 120 120

10 Sulphate Mg/l 100 100

11 Iron Mg/l 0.2 0.1

12 Nitrate Mg/l 5 5

13 Fluoride Mg/l 0.2 0.2

14 TDS Mg/l 700 700

15 Bacteria MPN/100ml -ve -ve

7.2.2.2. WASTEWATER CHARACTERISTICS

71 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

An understanding of the nature of wastewater is fundamental to the design and operation of wastewater collection, treatment, and reuse facilities. Wastewater is characterized in terms of its physical, chemical, and biological composition. Greater emphasis is being It is not possible to assess the quality of sewage being generated as there is no sewerage system. Whatever wastewater is flowing in open drains is primarily sullage water discharged from kitchens and bathrooms mixed with effluent from septic tanks. Even the discharge in open drains is subjected to seepage and can not be representative. On the other hand CPHEEO Manual on Sewerage and Sewage Treatment, based on its vast experience, has recommended values to be adopted for towns in India. Alternatively, the Manual of Sewerage & Sewage Treatment published by CPHEEO recommends a per capita contribution of 90 gms of Suspended

Solids and 45 gms of BOD 5 Days, 20Deg C. The per Capita water supply for the town is 135 LPCD as recommended by Manual of Water Supply Published by CPHEEO. These figures exclude the Unaccounted for Water(UfW). Wastewater manual recommends following: “Generally, a 80% of water supply is expected to reach public sewers unless the data available to the contrary. However, the sewers should be designed for a minimum wastewater flow of 100 liters per capita per day.” Adopting these recommendations, a wastewater contribution per capita per day comes to be 80/100 * 135 i.e. 108 liters. The BOD concentration in wastewater comes to be 45*1000/108 i.e. 417 mg/l and Suspended solids concentration comes to be 90*1000/108 i.e. 834 mg/l. However, as indicated above, this does not include sundry UfW flows into the sewers (which may be as high as 40% of water supplied). Further, it has been established by research that the entire sewerage system acts as flow through reactor with significant load of SS & BOD being removed prior to entry into STP.

7.2.3. ADOPTED INFLUENT QUALITY

Based on the data from STPs from other similar towns, sewage characteristics for the design purpose have been taken as follows:

S.No. Parameters Unit Values

72 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

S.No. Parameters Unit Values

1 BOD Mg/l 300

2 COD Mg/l 700

3 Suspended Soilds Mg/l 600

7.2.4. EFFLUENT STANDARDS

The Environmental Protection Rules 1986, vide its Section Vi provides general standards for discharge of environmental pollutants for discharge of treated effluent to Public Sewers, Inland Surface Waters, Land for Irrigation and marine coastal areas. The important standards for effluent discharging to inland surface waters & land for irrigation are reproduced here.

S.No. Parameters Unit Inland Land for Surface Irrigation Water

1 Suspended Solids, max Mg/l 100 200

2 Biochemical oxygen demand (5 Mg/l 30 100 days at 20 0C), max

3 Chemical Oxygen demand, Mg/l 250 - max

4 Ammonical nitrogen (as N), Mg/l 50 - max

The complete standards for discharge of effluents as per Section VI of Environment(Protection) Rules, 1986 are available at Annexure ‘A-1’. NRCD Guideline recommendations

S. No. Parameters For discharge on land For discharge into water

1 BOD (mg/l) <100 <30

2 SS (mg/l) <200 <50

3 Faecal Desirable Max. Desirable Max.

73 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

S. No. Parameters For discharge on land For discharge into water

coliform permissible permissible

1000 10000 1000 10000

7.3. TREATMENT PROCESSES

Preliminary : this includes simple processes such as screening (usually by bar screens) and grit removal. (through constant velocity channels) to remove the gross solid pollution. Primary : usually plain sedimentation; simple settlement of the solid material in sewage can reduce the polluting load by significant amounts. Secondary : for further treatment and removal of common pollutants, usually by a biological process. Tertiary/Advanced : usually for removal of specific pollutants e.g. nitrogen or phosphorous, or specific industrial pollutants. When reuse is contemplated, the tertiary treatment may comprise of several other unit processes/operations such as disinfection, activated carbon filtration, membrane filtration or even RO, depending on the end use contemplated and also on the ease and cost of the fresh water availability and legal stipulations. Needless to say, this can be by far the costliest step of wastewater treatment.

7.4. SELECTION OF TREATMENT PROCESS

As mentioned above the sewage after giving primary treatment is given secondary treatment to remove the organic purtrescible organic matters and bring down the BOD of the effluent given to the primary treated effluent is described below:-  Waste Stabilization Ponds  Aerated Lagoons  Up Flow Anaerobic Sludge Blanket (UASBR) + FAL  Conventional Activated Sludge Process  Cyclic Activated Sludge Process/SBR

7.4.1. STABILIZATION PONDS

74 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Stabilization ponds are open, flow[through earthen basins specifically designed and constructed to treat sewage. Stabilization pond provides comparatively long detention periods extending from few to several days. During this period purtrescible organic matter in the waste is stabilized in the pond through a symbiotic relationship between bacteria and algae. There are three types of stabilization ponds, a) Aerobic Ponds b) Anaerobic ponds c) Facultative ponds

7.4.1.1. AEROBIC PONDS

In this type of ponds complete aerobic conditions is maintained. These types of ponds are used for soluble wastes which allow penetration of light throughout the liquid depth. These types of ponds are shallow with depth less than 0.5 m. The pond contents are periodically mixed. The major disadvantage is that such ponds develop intense algal growth.

7.4.1.2. ANAEROBIC PONDS

Anaerobic ponds are used as a pretreatment for high strength industrial wastes and sometimes of municipal wastewaters. BOD load of 400[3000 kg/ha./day and 5[50 days detention period would result in 50[855 BOD reduction. Such ponds are constructed for a depth of 2.5[5 m to conserve heat and minimize land area requirement. Major constraint with such ponds is odor problem and hence not widely used.

7.4.1.3. FACULTATIVE PONDS

The facultative ponds functions aerobically at the surface while anaerobic conditions prevail at the bottom. The aerobic layer acts as a good check against odour evolution from the pond. The treatment effected by this type of pond is comparable to that of conventional secondary treatment processes. The functioning of facultative stabilization pond are based on the symbiotic relationship of bacteria and algae. In the tope aerobic layer, where oxygen is supplied through algal photosynthesis, the non[settle able and dissolved organic matter in the incoming sewage is oxidized to carbon dioxide and water. In addition some end products of partial anaerobic decomposition such as volatile acids and alcohol, which may permeate to upper layers are also oxidized aerobically. The settled sludge mass originating from raw waste and microbial synthesis in the aerobic layer and dissolved and suspended organics in bottom layers

75 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

undergo stabilization through conversion to methane which escapes the pond in form of bubble. For each kg of BOD ultimate stabilized 0.25 kg or 0.35 m3 of methane is formed.

7.4.1.4. DISADVANTAGES

 The facultative ponds shall be located far away from habitations or any area likely to be [built up within a reasonable future period.  The pond shall be located such that the direction of prevailing wind is towards uninhabited areas.  The pond location shall be away from ground water source to avoid chemical or bacterial pollution.  It creates mosquito nuisance and hence adversely affects public health.  The system is unable to take care of shock loads.  If the normal working is upstate it creates sight and foul small nuisance.  The effluent quality from stabilization pond is poor, it has high values of total suspended solids and total BOD5.  It requires very high area i.e. around 12 to 13 Hectare for 12 MLD so in view to above disadvantages and limitation for availability of land this method of treatment is not suitable for such towns.

7.4.2. AERATED LAGOONS

Aerated lagoons are simple earthen basins with inlet at one end and outlet at the other end. The mechanical aerators are designed to stabilize the organic matter into CO2 and H2O. The biological process does not include algae, and organic stabilization depends on the mixed liquor that develops within the lagoon. There is no provision for setting and returning activated, sludge. BOD removal is a function of aeration period, temperature and nature of wastewater. Aerated lagoons are of two types, a) Aerobic Flow Through with partial mixing b) Facultative Aerated Lagoons.

7.4.2.1. AEROBIC LAGOONS

76 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

This are fully aerobic from top to bottom as the aeration power input is sufficiently high to keep all the solids in suspension and meeting the oxygen demand of the microbes. No solids settlement occurs in the lagoons and under equilibrium conditions the new microbial solids produced in the system equal the solids leaving the system. Thus, the solids concentration in the effluent is relatively high and some sedimentation facility has to be provided after lagoons. Disadvantages  Problems of odors and low efficiency result when aerated lagoons are improperly designed or poorly operated.  Deposition of solids and reduced oxygenation can result in anaerobic Decomposition which leads to foul odor.  Temperature changes affect the overall performance of the lagoon.

7.4.2.2. FACULTATIVE AERATED LAGOONS

In such types of lagoons some solids may leave the effluent stream and some settle down in the lagoon as the aeration power input is enough for oxygenation and not keeping all solids in suspension. Because the energy input will not maintain the solids in suspension, a portion of the incoming solids will settle along with a portion of the biological solids produced from conversion of the soluble organic substance. The settled solids will undergo anaerobic decomposition. In such types of lagoons lower part may be anoxic or anaerobic and upper layers are aerobic. Facultative lagoons must be dewatered and the accumulated solids must be removed. Where a discharge limit has to be met reliably facultative lagoons are not being used. Comparison of Various Types of Lagoons

Parameters Facultative Aerobic Lagoons TSS, mg/L 40-150 150-350 BOD Removal 80-90% 50-60% Sludge Accumulated internally in Accumulated in the lagoon external sedimentation facility Power Less More Consumption

77 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Total area required for facultative aerated lagoons are very high i.e. 12 to 13 Hectare for 12 MLD and in view to above disadvantages and limitations of availability of required huge land it is not advisable to adopt this technology.

7.4.3. UPFLOW ANAEROBIC FILTER PROCESS (UASB)

This is based on anaerobic process. Raw effluent after screening and grit removal is directly fed into UASB reactors. The reactor maintains a high concentration of anaerobic biomass through formation of highly settle able microbial aggregates. Untreated sewage inside the reactor flows upward through a layer of sludge while getting treated for organics, converting them into methane gas. At top of the reactor, phase separation between gas[solid[liquid takes and treated water is taken out form the reactor. This process is very sensitive to operating conditions like temperature, pH, incoming load and recirculation rate hence treatment efficiency keeps fluctuating. At best operating conditions, the process offer 50 – 70% treatment efficiency, therefore requires second stage biological treatment down stream. Anaerobic process has very slow growth rates of micro organism and hence these systems have poor treatment efficiencies of only 50-70%. In order to achieve disposal outlet quality of treated sewage, second stage aerobic biological units are required. Typical outlet quality from anaerobic reactors is suspended solids 50 ppm, COD: 200 ppm, BOD 100 120 ppm for an inlet quality of TSS 300 ppm, COD 400 ppm and BOD 300 ppm. The system generates bad odor, as process releases gases like H2S and methane. Anaerobic process is very difficult to control. It requires consistent feed quality as well as flow rates. The process of degradation is a 3 step fermentation process comprising different sets of bacteria, to generate methane gas and CO2  Hydrolysis  Acidogenisis  Methanogenisis It requires constant monitoring of acidogenesis and methano genesis phases in the anaerobic reactor.

78 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

The process is pH sensitive. Methanogenisi reaction occurs in a pH range of 6-7.5 only, while during acidogenisis phase the ph may drop to 2.0 also due to formation of complex acids. This disturbs the complete equilibrium and further reduces treatment efficiency. Temperature dependent: The process works in the range of 18 –38 deg centigrade. During winter season when ambient temp Drops to 1[2 degree, provision has to be made to heat the entire contents of the reactor or else treatment efficiency drops drastically. There is No control on any process parameters. The plants run continuously at all times including low flow/ Nil flow conditions. Plant is manually controlled and difficult to monitor. It is susceptible to variation in inlet conditions BOD, COD, sulphide levels, pH and temp condition, which directly influences treatment efficiency as well as quantity of gas generation. Since It is a point load design cannot handle sudden peak flow variation, which is expected for any large scale city sewage system. Normally 0[250% flow variation is present for any sewage treatment plant. Gas can be generated, however process is not economical for low strength effluents like sewage where input BOD is less than 300 ppm. Further more for financial viability it is important to utilize the gas either directly in boilers or house holds. In case power is to be generated it again requires capital investment by putting duel fuel engines. Also provision has to be made for gas storage facility with flare system installed at site. Gas production is not consistent, and varies in case there is any disruption in the process. Due to Process chemistry acids are generated, pH in anaerobic reactors varies from 2-7, which essentially requires SS domes and FRP lining of complete tank internals. Problem of internal corrosion is very high and cost of maintenance is very high. More technical data have been compared with aerobic process in separate sheet..

7.4.4. ACTIVATED SLUDGE PROCESS

Activated Sludge Process (AEROBIC PROCESS) is the most used biological waste water treatment process in the developed and developing countries. Due to aerobic process in Activated Sludge Process, plant has less odor/vector nuisance in compare to anaerobic type process as mentioned above. The conventional activated sludge processes are of three types, a) Conventional System b) Complete Mixed c) Extended Aeration

79 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

a) Conventional System This type of system consists of an aeration tank, a secondary settling tank, a sludge recirculation system and sludge withdrawal system. About 85-92% of BOD removal can be achieved. The sewage and mixed liquor are input at the head of the tank and withdrawn at the end. Air is supplied at uniform rate throughout the length of the tank. b) Completely Mixed In a complete mixing is achieved by distributing the sewage and return sludge uniformly along one side of the tank and withdrawing the aerated sewage uniformly along the opposite side. The complete mix system has a high capacity to hold a high MLSS level in the aeration tank enabling the aeration tank volume to be reduced. The plant has high operational stability at shock loadings and also increased capacity to treat toxic biodegradable wastes. Limitations BOD Removal is 85 [92. In complete mix activated sludge process operation of anaerobic digestion requires a more skill labor here primary settling and anaerobic digestion of the sludge are omitted. The process is susceptible to filamentous sludge bulking. c) Extended Aeration The extended aeration process is little change of the activated sludge process which employs low organic loading, long aeration time, high MLSS concentration and low F/M. Other way which provides a biological treatment for the removal of biodegradable organic waste under aerobic condition. Air may be supplied by mechanical or diffused aeration to provide by aeration or mechanical means to maintain the microbial organisms in contact with the dissolved organics. In addition PH must be controlled to optimize the biological process and essential nutrients must be present to facilitate biological growth and the continuation of biological degradation. Sewage after primary treatment enters to the aeration chamber, where it is mixed and oxygen is provided to the micro organisms. The mixed liquor then flows to a clarifier of secondary settling tank where most micro organisms settle to the bottom of the clarifier. The sludge from clarifier is recycled back to aeration tank and remaining part is withdrawn from the system. Because of the long detention time in the aeration tank,organic solids undergo considerable endogenous respiration and get well stabilized. So the excess sludge from clarifier dose

80 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

not require separate digestion and can directly dried on sand beds. The clarified waste water flows over a weir used for sewage farming purpose. The BOD removal efficiency is high i.e. (90 [95) compare to Completely Mix Methodology. Limitations This treatment requires a slightly larger area than the complete mix activated sludge, Here waste water is brought directly to aeration basin after screening and grit removal. Aeration energy used is high and relatively required large aeration tanks, adaptable mostly to very small plants. However this is better in conventional range of process. Importance of Secondary Settling Tank in Activated Sludge Process Secondary settling assumes considerable importance in the activated sludge process. The secondary settling tank of activated sludge process is particularly sensitive to fluctuation in flow rate and on this account it is recommended that the units be designed not only for average flow rate but also for peak flow rate. The high concentration of suspended solids in the effluent requires that the solids loading rate shall also be considered.

7.4.5. CYCLIC ACTIVATED SLUDGE PROCESS /S EQUENTIAL BATCH REACTOR (CASP/SBR)

This is the most improved and scientific version of activated sludge process which gives excellent treated water quality in sewage treatment plants, requires less area, less energy etc. Batch Operation of the activated sludge process is nothing new as already mentioned in CPHEEO. A Sequencing Batch Reactor (SBR) is a fill and draw activated treatment system. As such, SBR are capable of handling all waste waters commonly treated by conventional activated sludge plants. Municipal and industrial waste waters have both been successfully treated in SBR systems. The unit process involved in the SBR and conventional activated sludge systems are identical. Aeration and sedimentation/clarification are carried out in both systems. However, there is one important difference. In conventional plants, processes are carried out simultaneously in separate tanks, whereas in SBR the processes are carried out sequentially in the same tank. The Process CYCLIC ACTIVATED SLUDGE TREATMENT process provides highest treatment efficiency possible in a single step biological process. The system is operated in a batch reactor mode this eliminates all the

81 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

inefficiencies of the continuous processes. A batch reactor is a perfect reactor, which ensures 100% treatment. Four modules are provided to ensure continuous treatment. The complete process takes place in a single reactor, within which all biological treatment steps take place sequentially. The complete biological operation is divided into cycles. Each cycle is of 3 – 5 hrs duration, during which all treatment steps take place. Explanation of cyclic operation: A basic cycle comprises: 1) Fill- Aeration (F/A) 2) Settlement (S) 3) Decanting (D) These phases in a sequence constitute a cycle, which is then repeated. During the period of a cycle, the liquid is filled in the Basin up to a set operating water level. Aeration Blowers are started for aeration of the effluent. After the aeration cycle, the biomass settles, No extra settling unit is required after the aeration basin. The Cyclic Activated Sludge Process/SBR comprises the following features, 1. Biological Selector zone: ENSURES NO FOAMING AND BULKING PROBLEMS 2. Oxygen Uptake rate control “OUR”: ENSURES 40 - 50% POWER SAVINGS 3. Co Current Nitrification and De nitrification, Phosphorous removal: THIS FEATURE ENSURES MORE THAN 80% NITROGEN AND PHOSPOROUS REMOVAL WITHIN THE SAME BASIN WITHOUT NEED OF ANY EXTERNAL UNITS, MIXERS, and RECYCLE PUMPS ETC. 4. Decanter assembly in Stainless steel: ENSURES NO CORROSION, LONG EQUIPMENT LIFE, NO MAINTENANCE 5. Diffusers, Blowers and Aeration grid: THE DIFFUSERS AND BLOWER ARRANGEMENT ENSURES MAXIMUM POSSIBLE AERATION EFFICIENCY AND MINIMUM POWER USAGE. 6. Submersible pumps for return sludge (RAS) recycle and Surplus sludge (SAS) pumps for sludge wasting: REDUCES SPACE REQUIREMENT, NO SECONDARY CLARIFIER IS USED WHICH DRASTICALLY REDUCES CIVIL COST

82 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

7. PLC unit for complete automatic cycle control and operation: REDUCES MANPOWER COST COMPLETE OPERATION CAN BE HOOKED TO CENTRAL CONTROL DESK Schematic drawing of Cy.ASP/SBR basin

Biological SELECTOR zone The incorporation of a biological SELECTOR in the front end of the Cyclic Activated Sludge process/SBR distinguishes it from all other technologies. The raw effluent enters the SELECTOR zone, where ANOXIC MIX conditions are maintained. Part of the treated effluent along with return sludge from the aeration basin is recycled in here, using RAS pumps. As the micro organisms meet high BOD, low DO condition in the SELECTOR, natural selection of predominantly floc[forming micro organisms takes place. This is very effective in containing all of the known low F/M bulking micro organisms, eliminates problems of bulking and sludge foaming. This process ensures excellent settling characteristics of the bio sludge. SVI of treated effluent of less than 120 is achieved in all seasons. Also due to the anoxic conditions in the SELECTOR zone, De nitrification and phosphorous removal occurs in case the Ammonical nitrogen and phosphorous levels are high in the effluent. The figure below shows the experience with SVI developments in parallel operations with a wastewater that traditionally favours sludge Oxygen Uptake Rate (OUR) Control The process uses measurement of dissolved oxygen (DO) levels in the basin to provide a full[scale control of the activity level in the aeration

83 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

basin. The DO concentration profile is automatically ramped to operate at slightly higher DO concentrations at the end of the cycle. This feature prevents low dissolved oxygen type filaments from proliferating. Once DO level is measured in the basins, the rate of drop in DO level is calibrated to know the actual oxygen uptake rate (OUR) of the biomass. In this way, the metabolic activity of the biomass is measured within the actual process basin and is subsequently used as a control parameter to automatically regulate the duration of the aeration sequence and/ or the rate of aeration. Aeration Cycle time can be altered automatically, or else a variable frequency drive automatically alters the aeration blower rpm. This methodology provides a true in[basin method for the efficient use of energy. Decanter Assembly in Stainless Steel The clean supernatant is removed from the basin using a Decanter assembly complete in stainless steel construction. During decanting there is no inflow to the basin. The moving weir DECANTER is motor driven and travels slowly from its “park” position to a designated bottom water level. Once the Decanting phase sets in, the decanter automatically lowers to the required bottom level. Variable frequency drives are provided to control the rate of movement of the Decanters. After the required level of supernatant is removed the Decanter is returned to its “park” position through reversal of the drive. The basin is now ready for the next cycle to begin.

Operational Simplicity - Fully PLC based intelligent control The complete plant operation is controlled automatically thro a PLC system, which is a major factor in reducing operating costs. This also

84 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

prevents mal operation of the various set process parameters within the plant. All key functions like, RAS, sludge wasting, aeration intensity, cycle time control, decanting rate etc are automatically controlled as well as data logged. Complete historical records of plant operation are available on touch of a button. Using suitable modem, these plants can be monitored and controlled thro Internet from anywhere in the world.

7.4.6. CONCLUSION

A comparison of various treatment technologies is as below:

Item Conventional Extended UASB followed Cyclic Activated Aeration by Facultative Activated Sludge Aerobic Sludge Lagoon Process/SBR Performance Mostly Stable Mostly Stable Varying with Completely (Typical) Temperature Stable Variations BOD removal,% 85 – 92% 90 – 95% 85 – 90% >98% In-built Nutrient No No No Yes removal for N & P Outlet Quality BOD <30ppm <30ppm <30ppm <10ppm COD <250ppm <250ppm <250ppm <100ppm Suspended Solids <50ppm <50ppm <100ppm <10ppm Total Nitrogen No Treatment No Treatment No Treatment < 10ppm Total Phosphorous No Treatment No Treatment No Treatment < 2ppm Coli form removal, 60 – 90 60 – 90 – 99.999% % Re-use Options Can only be Can only be Can only be Can be used used for low used for low used for low for low end end usages end usages end usages usages as well like flushing like flushing like flushing as for high end and and and usages without gardening. gardening. gardening. any tertiary Tertiary Tertiary Tertiary treatment Treatment Treatment Treatment Required for Required for Required for high end high end high end usages like usages like usages like Construction Construction Construction water, water, water, Industrial Industrial Industrial usages, usages, usages, cooling water cooling water cooling water etc. etc. etc. Land requirement 0.1 – 0.18 0.08 – 0.15 0.2 – 0.25 0.035-0.07 (m2/person) Process Power 12 – 15 16 – 19 4-5 6-8 Requirement (kWhr/person/year) Sludge Handling Sludge needs Digested Digested Digested Digestion prior Sludge, Dry on Sludge, Dry on Sludge, Dry on to drying on beds or use beds or use beds or use

85 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Item Conventional Extended UASB followed Cyclic Activated Aeration by Facultative Activated Sludge Aerobic Sludge Lagoon Process/SBR beds or use mech. mech. mech. Devices mech. Devices Devices Devices Equipment Aerators, Aerators, Nil (gas Diffused Requirement Recycle Recycle collection Aeration (excluding Pumps, Pumps, Sludge optional) System, screening and grit Scrapers, scrapers, (for Recycle removal) thickeners, large settlers) Sludge and Digesters, Waste Sludge Dryers, Gas Pumps, Equipment Decanters Operational Skilled Simpler than Simpler than Complete Characteristics Operation Activated Activated Automatic required sludge Sludge operation by Computer and PLC. Negligible manpower intervention required. Special Features Considerable BOD removal Minimal to Highest equipment high, effluent negligible Treatment and skilled nitrified, power Efficiency with operation relatively high requirement crystal clear required, power of the system water quality. especially if requirement. makes it an Power gas collection Favoured for economical requirement is and usage small and alternative if 50% of involved. medium sized gas revenue is conventional Method plants. neglected. technologies. considered Land Land mainly for requirement is requirement is large sized also relatively less than 50% plants. small but of depends on conventional type of post technologies treatment adopted. Activated Sludge Process (AEROBIC PROCESS) is the most used biological waste water treatment process in the developed and developing countries. Due to aerobic process in Activated Sludge Process, plant has less odor/vector nuisance in compare to anaerobic type process as mentioned above. Since Cyclic Activated Sludge Process/SBR is found most improved version of Activated Sludge Process through Sequential Batch Reactor (SBR) mode controlled by PLC and its proven across the world including In India hence Cyclic Activated Sludge Process/ SBR technology has been selected.

86 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Basic key criteria for selection of SBR.  Requires Minimum Space & Requires Minimum Energy for treatment of sewage.  This technology offers in built co current nitrification, de nitrification and bio – phosphorous removal mechanism that differentiates it from other technologies.  Requires Minimum Man Power for treatment of sewage & Minimum Maintenance Cost.  Excellent Treated water quality can be recycling.  Controlled system provided high flexibility and simplified potential of expansion.  A special ability to handle extremely high organic and hydraulic shock loads, No washout of biomass, More than 95 % BOD removal. In built Nitrogen/Phosphorous removal to prevent the natural resources from algae and other problems.  Further SBR process is also recommendation for sewage treatment in CPHEEO Manual, but due to the advancement in technology in last decade, these plants are very favorable for medium to large scale sewage treatment applications. Many large scale plants working efficiently around the world including India based on cyclic activated sludge process/SBR.

87 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Chapter 8. Treatment Plant Design

8.1. GENERAL DESCRIPTION

8.1.1. RECEIVING OF RAW SEWAGE (I NLET CHAMBER )

Raw Sewage from gravity outfall sewer is proposed to be collected into a Receiving Chamber. The function of the Receiving Chamber is to reduce the incoming velocity. Receiving Chamber shall be of adequate size to meet the requirements of workability inside it & can handle the designed flow of main sewer. The Receiving Chamber shall be water tight to prevent seepage of the sewage out of the Receiving Chamber. It is proposed that provision of gates for future balance capacity can be diverted in the STP for future expansion of STP.

8.1.2. COARSE AND FINE SCREENING

Coarse screens are to be provided for removal of floating and oversized material coming with the sewage. The coarse screens should be capable to screen out most of the medium & large floating and oversized material such as plastic rags, debris, weeds, paper, cloth, rags etc which could clog the waste water pump impellers. The coarse screen shall be inclined bar screen. It should be of sturdy design to take care of all sorts of materials envisaged in the gravity sewer. The screenings shall be dropped on conveyor above the top of the screen channel. A conveyor system of suitable width shall be provided which shall be adjacent to the screens. The screening material as collected will drop automatically into a wheelbarrows for its disposal. There shall be 2 nos. of screen one

88 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

mechanical & one Manual operated. The floating material above 50 mm size can be arrested in the screen.

8.1.3. RAW SEWAGE PUMPING AREA

Screened sewage after coarse screening enters into wet well of the pumping station. The capacity of the wet well should be kept such that adequate detention time is available during average and peak flow conditions. The effective liquid volume shall be provided below the invert level of the incoming sewer after leaving provision for freeboard. The capacity of the sump is to be so kept that with any combination of inflow and pumping the operating cycle for any pump will not be less than 5 minutes. Suitable combination of submersible pumps has been provided in the sumps to cater the pumping requirements at average and peak flow conditions. Based on incoming flow conditions, adequate no. of pumps shall operate automatically to cater the pumping requirements. Pumping area should have adequate covered area for installing electrical panels along with suitable arrangement for lifting of pumps. The pumped flow from the pumps shall be taken to the elevated head works Inlet channel above the sump from where sewage will gravitate to fine screen channels.

8.1.4. FINE SCREENING CHANNELS

Fine screens Channels to be provided before Grit removal system to arrest the fine floating material. The fine screens should be capable to screen out most of the small floating material above 6mm size. The fine screen shall be of mat type. The screenings shall be dropped on conveyor above the top of the screen channel. A conveyor system of suitable width shall be provided which shall be adjacent to the screens. The screening material as collected will drop automatically into a wheelbarrows for its disposal.

8.1.5. DE-GRITTING

Screened Sewage will gravitate to Grit separator tank for removal of grit and small inorganic particulate matter of specific gravity above 2.65 and particle size above 150 microns. The Grit separator tank shall be of RCC construction complete with mechanical internals and square in size. The grit separated shall be properly collected and be transferred for disposal.

89 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

The de-gritted sewage shall flow through open channels from the grit separators and confluence into a single channel of suitable width.

8.1.6. FLOW MEASUREMENT

Online Flow measurement shall be done by installing an ultrasonic level measurement device on the common Discharge header of Raw Sewage Pumps.

8.1.7. SBR / CYCLIC ACTIVATED SLUDGE PROCESS

Screened, de-gritted sewage shall be fed into the Cyclic Activated Sludge Process / SBR Process Basins for biological treatment to remove BOD, COD, Suspended Solids, Biological Nitrogen and Phosphorous. SBR / Cyclic Activated Sludge Process shall work on Cyclic / Batch mode in single step. It shall perform biological organic removal, Nitrification, De- nitrification and Biological Phosphorous removal. It shall be capable of simultaneous sludge stabilization. The oxygen required shall be supplied through fixed type fine bubble diffused aeration system with auto control of oxygen level in tank. The system shall have a SVI < 120 for higher settling rates and should be designed in such a way that growth of filamentous bacteria is restricted. Complete operation of SBR / Cyclic Activated Sludge Process including decanting rate, sludge recirculation and wasting of excess sludge shall be controlled by PLC. Treated Sewage from SBR / Cyclic Activated Sludge Process units shall be collected in Chlorination tank for its disinfection.

8.1.8. CHLORINATION SYSTEM

Treated Sewage from SBR / Cyclic Activated Sludge Process units will be collected in a chlorination tank where disinfectant will be added for disinfection at suitable dosing rate. Baffle walls shall be provided in the tank to facilitate hydraulic mixing of treated sewage. Adequate reaction time shall be considered for while selecting the chlorination tank volume to ensure proper disinfection of treated sewage. The treated sewage is to be disposed suitably into Perennial River/ can be utilized for agriculture preferably by gravity.

8.1.9. SLUDGE HANDLING SYSTEM

The sludge from the SBR / Cyclic Activated Sludge Process basins is withdrawn through sludge withdrawal system and collected in the sludge sump. The sludge shall be then pumped to Solid Bowl Centrifuge for dewatering of sludge.

90 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Centrifuge feed pumps shall be of positive displacement type screw pumps. Dewatering Polymer shall be dosed online prior to centrifuge feed. The dosing system shall include one solution preparation and one solution- dosing tank equipped with slow speed mixers and metering type positive displacement pumps. The sludge in form of wet cake from centrifuges will be collected and disposed off. Interconnection of various units shall be made through piping or RCC channels. Piping will be preferred over RCC channel wherever possible but the Engineer-in- Charge reserves the right to select any option.

8.2. TREATMENT PLANT CAPACITY

The designed population of the town comes to be 305494 souls as described in chapter 5 of this report. As per recommendations of Manual of Water Supply published by CPHEEO, the per capita water supply for the town is adopted as 135 LPCD and the portion of this supply which contributes to wastewater generation has been adopted as 80%. The wastewater generated per capita comes to be 108 LPCD. The total wastewater generated in design year will be 32.99 mld. The capacity of treatment plant for design year comes to be 33 mld. It is proposed to develop the designed capacity of treatment plant in modular way with inlet chamber, screens, wet wells & pumping station proposed to be developed for designed capacity. The rest of the STP units are proposed to be developed for intermediate flow of year 2026. For corresponding population of year 2026 i.e. 217992, the wastewater flow comes to be 23.54 mld. It is proposed to construct STP of capacity 22 mld under this project. So that a half of capacity i.e. 11 mld is further added to achieve full capacity for design year.

8.3. STP UNITS

The different components/process units to be covered at each location are as follows:

1. Receiving Chamber (Inlet Chamber for ultimate capacity i.e. 33 MLD).

91 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

2. Mechanical and Manual Coarse Screens.

3. Raw Sewage Sump, Pump.

4. Inlet Channel over sump

5. Mechanical Fine Screens.

6. Mechanical Grit Chambers.

7. Flow Measuring unit

8. Cyclic Activated Sludge Process / SBR Process Units. 9. Chlorine Contact Tank.

10. Chlorine House.

11. Sludge Sump, Pump and Pump House.

12. Mechanical Sludge Dewatering System.

13. Administration Building.

14. Transformer Yard and MEP Room, Electrical Works for STP 15. Interconnecting Piping & Appurtenances

16. Plant Utilities.

8.3.1. RECEIVING CHAMBER

The deep gravity outfall sewers will discharge the raw sewage into a Receiving chamber. The function of the Receiving chamber is to distribute the flow for process units. The Receiving Chamber is designed for peak flow. The Receiving chamber consists of sluice gates on upstream and downstream for flow regulation. In the sidewall of the Receiving chamber, sluice gates are installed such that it is possible to operate them manually, inspection as well as operation by standing on a platform constructed at a suitable elevation adjoining and circumventing the inlet chamber. The inlet chamber is of adequate size to meet the requirements of workability inside it. The receiving chamber is open to sky and shall be water tight to prevent seepage of the sewage out of the inlet chamber. The entire construction is in M30 grade concrete and as per IS 3370. RCC access platform minimum 1000 wide with railing as per specifications shall be provided on one side of the chamber:

Total Average flow : 22 MLD

92 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Peak factor : 2.25

Design Flow : 49.50 MLD

Number of Units : 1 (one)

Detention period : 12 sec.

Min Free board : 0.5m

Size : 4m X 2 m 1.50 m SWD

Minimum volume of the Receiving chamber shall be 10.50 m3. There is a provision of one bye pass channel along with gates. Alternatively, plant bypass can be provided from existing / proposed manhole before pumping station.

8.3.2. COARSE SCREEN CHANNELS

One mechanical screens working and one manual screen standby of 20 mm clear spacing and of peak flow capacity shall be provided. The manual bar screens shall be made of 20 mm thick Stainless Steel (SS 304) flats respectively. The mechanical screens is of Inclined Rake Type of 20 mm opening. Conveyor Belt and chute arrangement is provided to take the screenings to the screenings dropped from chute will be collected in a wheel burrow. Manually operated CI gates are provided at the upstream and downstream ends to regulate the flow. Adequate RCC Platforms is provided at the upper level to enable operation. Railings is provided around the entire periphery of the platform. The entire structure is to be M30 concrete and as per IS 3370 including the platform. RCC staircase 900 mm wide is provided for access from the ground level to the top of the unit & to the operating platform.

Total Average flow : 22 MLD

Peak factor : 2.25

Design Flow : 49.50 MLD

Number of Units : 1 Mechanical (Working)+ 1(manual stand bye)

93 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Approach Velocity at Average : 0.3 Flow (m/sec.)

Velocity through Screen at Average : 0.6 maximum (M/sec.) Flow

Velocity through Screen at Peak : 0.8 maximum Flow (m/sec.)

Min Free board : 0.3 m

Wheeled Trolley : 1 No.

Minimum size of each screen channel shall be 10m long x 0.95 m wide x 0.9 m SWD.

8.3.3. RAW SEWAGE PUMPING

8.3.3.1. SUMP AND PUMPS

Sewage enters into sump after screening. The sump is kept as circular in shape and shall be designed for an average flow. The capacity of sump is such that the detention time in the sump shall be minimum 5 minutes of peak flow and the maximum detention time shall not exceed 20 minutes at average flow. Following criteria’s has been considered to size the sump: 1. That the pump of the minimum duty/ capacity would run for at least 5 minutes considering no inflow or 2. The capacity of the sump is to be so kept that with any combination of inflow and pumping the operating cycle for any pump will not be less than 5 minutes and 3. The arrangement of the submersible pumps as per pump manufacturer’s data i.e. spacing between pumps, minimum space between pump and wall etc. 4. The side water depth (live liquid depth) is minimum 2.5 meter. In addition to the above liquid depth an additional depression is provided to ensure adequate submergence of the pump as per the manufactures recommendations .A operating platform above sump duly covered is proposed for installing electrical panels. Suitable arrangement is to be provided for lifting of pumps.

94 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

5. The effective liquid volume below the invert level of the screen chamber after leaving provision for a minimum of 0.3 m is 4.00 mtr. Pumping arrangement

Total Average flow : 22 MLD

Minimum Retention Time : 20 minutes minimum at Avg. flow.

No. of pumps : 916.70 m3/hr @ 20 MWC (1W + 1S) for Avg. flow 573.75 m3/hr @ 20 MWC (2 W + 1 S) (lean flow) For peak flow one pump of Av.flow+ 2 pumps of lean flow (2064.20 m3/hr )

Head : 13.00 mtr.

Type of pumps : Submersible type non- clog design

Solid passage size through pumps : 100 mm max.

Insulation : Class F

Protection : IP-68

Sump Specific Requirement, Material of Construction and Accessories: i. Number of Units (1) One designed for peak flow ii. Construction material RCC The size of the sump having diameter of 10 mtr is suitable to accommodate the number of pumps required for operation with easy manoeuvrability. Following accessories is proposed to have with sump:

95 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Hoist - comprising of I-Girder and a 1½ ton or more chain pulley (the chain pulley block capacity to be 1½ Ton or 1.5 times the maximum single unit/ weight that may be required to be removed for maintenance) with horizontal travel on the I-beam. A collecting channel above sump is proposed to collect the pumped waste water

8.3.4. MECHANICAL FINE SCREEN AND CONVEYOR

One mechanical working with one mechanical standby screens are proposed in the screen chamber. The screen channels is designed for peak flow. The clear opening for mechanical screen shall be 6 mm for mechanical fine screens. The mechanical bar screens shall be of 2 mm thick Stainless Steel (SS 304) flats. Conveyor Belt and chute arrangement is provided to take the screenings to the screenings dropped from chute will be collected in a wheel burrow. Manually operated CI gates are provided at the upstream and downstream ends to regulate the flow. Adequate RCC Platforms are provided at the upper level to enable operation. Railings are provided around the entire periphery of the platform. The entire structure is to be M30 concrete and as per IS 3370 including the platform.

Total Average flow : 22 MLD

Peak factor : 2.25

Design Flow : 49.50 MLD

Number of Units : 1 Mechanical (Working) + 1 Mechanical (standby) capacity

Approach Velocity at Average : 0.3 Flow (m/sec.)

Velocity through Screen at Average : 0.6 maximum (m/sec.) Flow

Velocity through Screen at Peak : 1.2 maximum Flow (m/sec.)

96 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Min Free board : 0.3m

Wheeled Trolley : 1 No.

Minimum size of each screen channel shall be 6.00 m long x 1.25 m wide x 1.0 m SWD. One mechanical working with one standby screens are proposed in the screen chamber. The screen channels shall be designed for peak flow.

8.3.5. GRIT REMOVAL UNIT

One mechanical grit chamber of peak flow capacity is proposed after fine screen units. The mechanical grit chambers is Square Mechanical Detritus Tank designed for average flow of 22 MLD with a peak factor of 2.25. Detritus tank chamber shall have the following: • One tapered inlet channel running along one side with deflectors for entry sewage into the grit chamber. The minimum SWD of the units shall be 0.9m. • One tapered outlet channel for collecting the de-gritted sewage, which overflow over a weir into the outlet channel. Outlet channel of adequate size and she to ensure that no settling takes place. • One sloping grit classifying channel into which the collected grit will classified. • The grit from classifier will be collected in a wheeled trolley. • A grit scraping mechanism. • Adjustable influent deflector. • Reciprocating rake mechanism to remove the grit. • Organic matter return pump CI gates are provided at the entrance and at the outlet of the chamber. To enable easy operation of the gates, RCC platforms with Gl railing are provided at the upper level. Also access is provided from this level to the mechanism support beam of the grit chamber. The entire construction shall be M25 grade concrete and as per IS 3370.

Total Average flow : 22 MLD

97 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Peak factor : 2.25

Design Flow : 49.5 MLD

Number of Units : 1 (One) Working of peak flow capacity

Type : Mechanical

Size of grit particle : 0.10 mm

Specific gravity of grit : 2.65

Maximum Surface Overflow Rate : 960 m3/m2/day

Free Board : 0.5 m

Side Water Depth : 0.8 m

Wheeled trolleys : 1 No.

Minimum size of the mechanical grit chamber shall be 5.1 m x 5.1 m x 0.8 SWD.

8.3.6. FLOW MEASUREMENT

Flow measurement shall be done using a Parshall flume with throat width of 18 inches. The Parshall flume shall be installed before SBR system. An additional Ultrasonic flow meter mounted on concrete channel shall also be provided having digital type Indicator, Integrator and Recorder fixed in the control room.

8.3.7. DIVISION BOX

Division Box receive the flow from the grit chamber. The 49.5 MLD peak flow is then be equal parts with help of overflow weir channels and distributed to Cyclic Activated Sludge Process/ SBR Process units via pipe / channel. Motorized Sluice gates including all specials is provided on all weirs for isolation. RCC access platform, staircase, railing and covers over division boxes are provided as per requirement.

8.3.8. CYCLIC ACTIVATED SLUDGE PROCESS / SBR PROCESS WITH DIFFUSERS AND AIR BLOWERS

98 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

8.3.8.1. PROCESS DESIGN

The biological treatment section comprising SBR/ cyclic activated sludge process has to be installed and equipped for average flow of 22 MLD. The complete biological system has to be designed for handling peak flow capacity. 2 nos. tanks with minimum total volume of 16641 m3 shall be provided. In addition, 0.5 m free board shall be provided to each tank. Maximum liquid depth of tank shall be restricted to 4.5 m. - Cyclic Activated Sludge Process / SBR Process basins will be constructed in M25 grade concrete and as per IS 3370. RCC staircase 900 mm wide is provided to each basin for access from the ground level to the operating platforms. All platforms and walkways shall be provided hand railings as per tender specifications of 1.2 m width. Plinth protection along periphery shall be provided as per technical specifications. - The system should work on a continuous gravity influent condition. No influent / effluent equalization tanks or flash filling is accepted. The system should be designed for maximum F/M ratio between0.1 - 0.25 kg BOD/kg MLSS day. MLSS maintained in the basin should range from 2500 to 5000 mg/l; SBR/ Cyclic activated sludge cycle times shall be selected adequately considering min. 12 hrs/day basin of aeration and not exceeding decanting of 2.2 m liquid depth at any time with preferred cycle times containing max. 50% not aerated portion. The excess sludge produced shall be fully digested. Sludge production (including percipients) rate shall be about 0.6 – 0.8 kg / kg of BOD removed. In the SBR / cyclic activated sludge basins the NO filling during settling or decanting will be acceptable.

8.3.8.2. DECANTING DEVICE

The decanting device shall be rotating moving weir arm devices of Stainless Steel 304 with top mounted gear box, drive, scum guard, down comers, collection pipe, bearings. The following type of decanter assemblies are not acceptable,

99 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 Rope driven decanters.  Floating decanters.  GRP products.  Valve-arrangement. The maximum design travel rate shall be 60 mm/min. with proven hydraulic discharge capacity of the decanter proportional to the selected basin area. Bidders to provide sample graphs of executed projects with such decanting speeds with decanters of min. same size (length). There should be Maximum 1 decanter per basin. The hydraulic design based on design flow rates as given above shall not exceed flow speeds of 1.3 m/s. Flexible rubber hose kind of decanter sealing is not acceptable. Each Decanter mechanism shall be inclusive of local control boxes with manual operation selection and function buttons, communication to main PLC by DH485 or Ethernet.

8.3.8.3. AERATION SYSTEM

The Aeration facility shall be installed for 22 MLD average flow. - Minimum installed aeration equipment design capacity per day per basin for 22 MLD average flow shall be 193541 Nm3 per day per basin on the basis of 12 hrs aeration per day per basin. - Only fine bubble EPDM / PU membrane diffusers shall be acceptable with minimum membrane diffuser to floor coverage area of 5%. Diffusers shall be submerged fine bubble / fine pore, high transfer efficiency, low tow maintenance, non-buoyant type. Diffusers shall be tubular (membrane) type. Material of construction for (entire under water system including accessories shall be of non corrosive Complete diffuser as a unit shall be assembled at the manufacturing factory level. The grid supports shall of adjustable type made of SS 304. The air blower arrangement shall be capable of handling Total Water Level and Bottom Water Level operation conditions, controlled by process sensors such as DO, temperature and level.

100 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Each set of blower shall have dedicated standby. Minimum One working air blower in each set shall operate via VFD into each tank while others may be operating at a fixed constant speed on soft starter configuration. - The blowers for air diffuser system shall be positive displacement (roots) type, and head for blowers shall be decided on the basis of S.O.R. of diffusers and maximum liquid depth in tank duly considering the losses governing point of delivery (diffusers) and the blowers. Blowers shall be complete with motor and accessories like base frame, anti vibratory pad, silencer, non return valve, air filter etc. as per requirements. Further, blowers shall have acoustic to ensure that the noise level at 1 m from blowers is below 80db. The blower room shall have sufficient ventilation, lighting and working space. The room will be equipped with sufficient capacity EOT (Min 2 T or 1.5 times the weight of blower, whichever is more) to facilitate removal of blower/motor etc. for repairs. The room will also have rolling shutter. - The operation of aeration system shall include PLC based control. The operation and speed of blowers shall be automatically adjusted using parameters like Oxygen Uptake Rate, Dissolved Oxygen and Temperature and liquid level in the basin such that the DO is supplied as per demand and power utilisation for operation of blowers is optimised. The main air header/ring main shall be in MS as per relevant IS painted outside with corrosion resistant paint as per manufacture's recommendations. The header / ring main shall be supported on saddles at suitable intervals or will be protected against external corrosion in case they are laid below ground. The header shall have auto valves to facilitate switch over aeration cycle from one basin to other by PLC operation. The header shall supply air to diffuser grids at various locations through air supply pipes. Air supply pipe above water level shall be in Gl and below water level it shall be in Imported PVC as per relevant standards. All under water lateral pipes shall be of Imported PVC. Junction between air header and air supply pipe shall be suitably protected against corrosion due to dissimilar materials. - All other accessories, whether specified or not, but required for completeness shall form part of contractors scope.

8.3.8.4. RETURN SLUDGE AND EXCESS SLUDGE PUMPS

101 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Dedicated Return sludge and excess sludge pumps shall be provided for each basin. The pump shall be of submersible / horizontal centrifugal type suitable for handling biological sludge of 1 – 2% solids consistency. Capacity and heads shall be decided based on SBR / Cyclic Activated Sludge Process requirements. Each SBR / Cyclic Activated Sludge Process basin shall be provided with suitable lifting arrangements to facilitate lifting of pump, if required for maintenance. a. Return Sludge Pumps

Pumps Capacity and Head : As per SBR / Cyclic Activated Sludge Process requirements

Type : Submersible / Horizontal Centrifugal

Liquid : Bio-sludge of 1 – 2% solids consistency

Specific gravity : 1.05

Solid size : 100mm (Maximum)

Temperature : Min. 20 ° C

Efficiency : more than 40%

Installation : Fixed.

Quantity : 1 No. per Basin + 1 Store Standby

b. Excess Sludge Pumps

Pumps Capacity and Head : As per SBR / Cyclic Activated Sludge Process requirements

Type : Submersible / Horizontal Centrifugal

102 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Liquid : Bio-sludge of 1 – 2% solids consistency

Specific gravity : 1.05

Solid size : 100mm (Maximum)

Temperature : Min. 20 ° C

Efficiency : more than 40%

Installation : Fixed.

Quantity : 1 No. per Basin + 1 Store Standby

8.3.8.5. AUTOMATION AND CONTROL

PLC based automation system with application software based on Rockwell hardware or equal to control Raw Sewage Transfer Pumping Station, Primary Treatment Units and SBR System including all pumps, valves, blowers, VFD, decanters, limit switches and probes as per bidder’s design including I/Os with 20 % spares, power supplies, UPS. HMI Panel to comprise up-to-date standard PC with monitor, printer, mouse, internet connection, RS-view, RS-links (gateway version), entire process and operator software with dynamic flow charts, pictures, screens, alarms, historical trends, reports etc. SACDA based Automation system to monitor continuously in each SBR tank the followings: a. Filling volume b. Filling quantity c. Discharge quantity d. DO-level e. Temperature f. Oxygen Uptake Rate g. Blower speeds h. Decanter speed

8.3.9. SLUDGE HANDLING SYSTEM

103 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

8.3.9.1. 10.1 SLUDGE SUMP AND PUMP HOUSE

Sludge sump shall be provided to collect the excess sludge from Cyclic Activated Sludge Process/SBR Process Basins. There shall be one common sludge sump for all basins. There shall be auto gate valves on discharge sludge pipe of each Cyclic Activated Sludge Process / SBR Process basin. Sludge tank shall be constructed in M25 grade concrete and as per IS3370. The sump shall be equipped with coarse bubble air grid made from HDPE / PVC pipes and Air Blower Assembly to facilitate mixing of contents of sludge sump on continuous basis. Above sludge sump there shall be pump house. This shall be RCC frame brick masonry structure. Minimum height of the pump house shall be 4.5 m form the plinth level. It shall be provided with rolling shutter and doors and windows as per technical specifications. EOT of minimum 1.5 T capacity shall be provided in the pump house to lift the pump assembly. Flooring of the pump house shall be IPS flooring. Pump house shall be plastered from inside and from outside as per tender specifications. Entire pump from inside and from outside shall be painted with approved colour and make as directed by engineer-in-charge. Sludge sump shall be painted inside with bituminous paint.

Number of Units : 1 (One) No.

Free Board : 0.5 m

Minimum SWD : 3.0 m

Detention time : 4 hrs.

Minimum size of the sludge sump in shall be 5.4 m x 5.4m x 3.0 m SWD.

8.3.9.2. SLUDGE TRANSFER PUMPS AND MIXING BLOWERS

Sludge Transfer Pumps shall be provided in Sludge Pump House to feed secondary Sludge to Mechanical Dewatering Device. The pump shall be of screw type suitable for handling biological sludge of 1 – 4% solids consistency.

Pumps Capacity and Head : 15 m3/hr @ 15 MWC

Type : Screw Type

104 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Liquid : Bio-sludge of 1 – 4% solids consistency

Specific gravity : 1.05

Temperature : Min. 20 ° C

Efficiency : more than 30%

Installation : Fixed.

Quantity : 3 Nos. (2W + 1S)

The blowers shall be positive displacement (roots) type, and head for blowers shall be decided on the basis of maximum liquid depth in tank duly considering the losses governing point of delivery and the blowers. The number of standby blower shall be 100% of the number of working blowers. Blowers shall be complete with motor and accessories like base frame, anti vibratory pad, silencer, non return valve, air filter etc. as per requirements.

Air Mixing Rate : 1.0 m3/hr/m3 of liquid volume

Blower Capacity and Head : 100 m3/hr @ 0.4 bar (minimum)

Type : Twin Lobe, Root

Installation : Fixed.

Quantity : 2 Nos. (1W + 1S)

8.3.9.3. MECHANICAL DEWATERING UNIT :

The mechanical dewatering units shall be solid bowl centrifuge designed so as to give a 100% trouble free operation at all times and the sludge dewatering plant should operate for designed flow and capacity conditions and be sized as per the following guidelines. i. The de-watering system should be so located that the de-watered sludge can be loaded into trolleys / drums / bins directly - preferably the

105 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

de-watering unit shall be so located that the de-watered sludge falls into the containers/ bins without requirement of another material handling unit. ii. The de-watered sludge should be truck-able & be suitable for disposal by open body truck and should have a minimum solid concentration of 20% or more (measured as dry solids w/w basis) There shall be one Centrifuge building in framed structure construction, the first floor will house centrifuges. The configuration shall be such that the wet cake discharge will be discharged through single central chute to the parked trailer/lorry below. The centrifuge shall be solid bowl centrifuge of co-current/counter current design. The centrifuge shall have sufficient clarifying length so that separation of solids is effective. The centrifuge and its accessories shall be mounted on a common base frame so that entire assembly can be installed on an elevated structure. Suitable drive with V- belt arrangement and turbo-coupling shall be provided along with overload protection device. Centrifuge shall be with SS304 wetted parts. Differential speed and bowl speed should be adjusted by changing the pulleys; differential speed may be adjustable by use of epicyclical-gear. The bowl shall be protected with flexible connections so that vibrations are not transmitted to other equipment. The base frame shall be in epoxy painted steel construction and provided with anti-vibration pads. All steps necessary to prevent transmission of structure borne noise shall be taken. The drive motor shall be of 1450 rpm. The noise level shall be 85 dB (A) measured at 1m distance under dry run. The vibration level shall be below 50 micron measured at pillow blocks under dry run condition. Adequate sound proof shall be carried out for the housing the centrifuges to ensure that the noise level at 5 m distance from the enclosure is less than 75 dB (A). A hoist shall be provided above centrifuge for maintenance purpose. The hoist shall be such that it shall be possible to erect or de-erect the centrifuge while one centrifuge is in operation.

Number of Centrifuges : 2 Nos. (1 Working+ 1 Standby)

Type : Horizontal

106 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Capacity of each unit : 42 m3/hr

Operating Hours : 20 hrs per day maximum

Mixing arrangement of Polyelectrolyte and sludge: online-mixing

8.3.9.4. POLYELECTROLYTE DOSING :

The polyelectrolyte will be dosed online at the centrifuge inlet. Minimum dosage of polyelectrolyte shall be 1.2 kg/T of dry solids in sludge at 0.5% solution strength. There shall be two poly-dosing tanks each suitable for minimum 8 hrs. of operation. Each-tank shall be equipped with slow speed mixer (100 RPM) to prepare polyelectrolyte solution. The solution will be fed using positive displacement metering type dosing pumps. There shall be dedicated dosing pumps to each centrifuge with one common standby. The pumps shall be interlocked with centrifuge so that it can only be running in auto when centrifuge is on and should shut down when centrifuge stops. The dosing system shall be housed in centrifuge house itself.

8.3.10. DISINFECTION SYSTEM

8.3.10.1. CHLORINATION TANK :

Treated sewage from STP shall be taken to chlorine contact tank by RCC channel/pipe. Chlorine Contact Tank is provided for dosing of chlorine. The tank is constructed in M30 grade concrete and as per IS 3370. Baffle walls are provided to achieve proper disinfection. The baffle walls shall be constructed in M30 grade concrete and 20 mm thick plaster in CM 1:3 on either side.

Design Flow : 22 MLD

No. of Units : 1 No.

Detention Time : 30 minutes of average flow or 30 minutes of decant flow, whichever is higher

Freeboard : 0.5 m

Minimum size of Chlorine Contact Tank shall be 16.5 m x 8 m x 3.5 SWD

8.3.10.2. CHLORINATION SYSTEM :

107 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Average Flow : 22 MLD

Number of Units : 2 (1W + 1S)

Type : Vacuum Type

Chlorine Dosing : 3 ppm max.

Capacity of Chlorinator : Minimum 5 kg/hr

Chlorination system covering chlorine tonners (2 Nos.), chlorinator, water feed pumps, piping, booster pumps, ejector, trunions, lifting device with weighing scale, leak detection and leak absorption system, safety equipments like canisters, gasmasks etc. and other ancillary shall be provided in the chlorine house. Chlorine house of minimum 60 sq. m. plinth area shall be provided. It is proposed to have sufficient ventilation as per the latest norms for safety purpose with necessary lifting arrangement and EOT of minimum 2 T capacity etc. complete.

8.3.11. DISPOSAL PIPE /C HANNEL

Treated sewage after chlorine contact tank shall be disposed into Drain in north of industrial area, Hajipur through RCC Channel/Pipe.

8.3.12. SBR AIR BLOWER CUM ADMINISTRATIVE CUM MCC & CONTROL BUILDING

The SBR Air Blower cum Administrative cum Control Building shall be G+1 structure. Ground Floor shall be SBR Air Blower Room and first floor shall be Admin Block with 240 m2 area at each floor. SBR Air Blower Room shall comprise Air Blower Room, Tool Room and Work shop. The Admin Block shall comprise Office, Laboratory, Conference Room, MCC Room and Control Room. The proposed building shall meet the following minimum carpet requirements.

SBR Air Blower Room : 15 m x 12 m

MCC Room : 10 m x 5 m

PLC & Control Room : 5 m x 5m

Office Block & Laboratory : 15 m x 5 m

Conference Room : 5 m x 5 m

108 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Toilet Block : 5 m x 2.5 m at each Floor

8.4. PROPOSED DISPOSAL METHOD

The treated effluent is proposed to be discharged in drain passing through the outskirts of Hajipur which ultimately discharges in river Ganga. The treated effluent shall be religiously monitored for its polluting nature before discharging in drain. A part of the treated effluent shall be utilized for agriculture purposes in non-rainy periods.

8.5. ANCILLARY FACILITIES

8.5.1. SECURITY ROOM

The security room at entry to the STP shall be a ground floor construction with 3m X 5m carpet area and be of RCC roofing and shall be provided with glass panels on three sides and an air cooler. Necessary fans and lights shall be provided.

8.5.2. PMCC ROOM

There shall be 1 room strategically / appropriately sized to meet statutory and functional requirements.

8.5.3. CONTROL ROOM

There shall be 1 control room strategically / appropriately sized (6m X 4m) to meet the functional requirements. Two no. 1.5 TR air conditioners shall be provided. The wall on all sides shall be glass panelled above 1 m wall. Necessary lighting and fans shall be provided as directed by the employer's representative.

8.5.4. REST ROOM

There shall be 1 rest room of size 4m × 5m with toilet facility. Necessary light fans furniture and air coolers shall be provided. An attached toilet with water facility shall be provided.

8.5.5. WORKSHOP CUM STORE

There shall be a room of size 12m X 4m divided into two equal portions. Necessary light fans furniture and air coolers are proposed to be provided. Necessary facilities for drilling welding machining etc shall be provided to

109 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

shit the maintenance work involved in the pant, a wide rolling shutter shall be provided for shop and also for store with ramp.

8.5.6. OPEN STORE YARD

This shall be of a floor area of 100 sqm fenced with GI barbed wire of 4m tall and RCC posts. The security for stored materials shall be provided with gates that produce audible alarms whenever opened and closed. Rollers moving on rails/flats shall be provided.

8.5.7. COVERED VEHICLE PARK

There shall be provision to park 2 numbers four wheelers, 6 numbers of two wheelers and 10 numbers of cycles for which an area of 60 sqm is adequate with concrete flooring, ramp and FRP roofing.

8.5.8. LANDSCAPING

The landscaping of the woks/STP site is also proposed to be taken up under this project. The open area within the campus after construction sewage treatment plant shall be developed through adequate greenery comprising flowering bushes, thickets and trees. Treated sewage shall used for the development. At least 33% of the open area shall be converted to a green belt/garden. Dense plantation shall be used for control of noise around the blower buildings. Plantation of large trees and green belt including creepers shall be used in the campus to ensure that odours, if at all emitted, get diluted and diffused and a visual barrier is created.

110 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Chapter 9. Project Cost

9.1. SOURCES

The rates for different unit works/Material/Supplies for building, Electrical, Electromechanical, Instrumentation & other components appearing in scope of work of this project have been adopted from number of sources as detailed below: The rates of items such as RCC Non Pressure pipes, uPVC Pipes, Manhole Covers, Ferro Cement Steps Bedding, Manhole, vent-shafts etc have been inquired from manufacturers and rate analysis has been carried out for arriving at on site rates. Schedule of Rates (SoR), Building Construction Department: The rates for almost all the civil works have been taken from Schedule of Rates effective from 01-07-2008 as published by Building Construction Department , Government of Bihar. Schedule of rates of WRD: The rates of some of the items have been adopted from Schedule of rates effective from 01-10-2007 as published by Water Resources Department, Government of Bihar. Schedule of Rates of Road Construction Department: The rates of items for cutting & restoration of roads and other related items have been adopted from Schedule of Rates effective from 24.03.2008 as published by Road Construction Department, Government of Bihar.

111 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Vendors: Some rates have been enquired from vendors, manufacturers etc.

9.2. SEWERS

With the objective of ease of record measurement, verification & other book keeping procedures, the cost estimates for sewers have been categorized depending upon main parameters of Diameter of sewer and Average Depth of invert of sewer. Rate analysis for these categories have been prepared and are used in cost estimates. The major cost items for sewer are as follows:  Dismantling & restoration of Road Surface  RCC NP Pipe with bitumastic anti corrosive painting  Earthwork  Timbering  Laying & Jointing  Bedding  Barricading  Well Point System & Dewatering  Vent Shafts

9.3. MANHOLE

Manholes are proposed to be constructed in Brick Masonry and RCC depending on invert depth as explained in Design Criteria Chapter. With the objective of ease of record measurement, verification & other book keeping procedures, the cost estimates for manholes have been also categorized depending upon main parameters of Diameter of sewer and average depth of Manhole. Rate analysis for these categories have been prepared and are used in cost estimates. Rate analysis for both Brick Masonry & RCC have been prepared separately. The major cost items for manhole construction are as follows:  Dismantling & restoration of Road Surface  Earthwork  Timbering  Shuttering  Brick Masonry/Reinforced Cement Concrete

112 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 Plastering/Pointing  Ferro Cement Manhole Covers  Cast Iron Foot Steps  Barricading

9.4. PUMPING STATIONS

The major cost items for proposed pumping stations are as follows:  Mechanical Screens  Wet Well  Pump sets with prime movers and control equipment  Electric Panel Rooms  Power Connections  DG Sets

9.5. TREATMENT PLANT

The major cost items for proposed Sewage Treatment Plant are as follows:  Preliminary treatment units i.e. Screen Chamber & Grit Chamber  Civil Works related to Different Units  Electromechanical & instrumentation equipments for different units  Pipes/Channel/Pumps to carry wastewater in between units  Cost of land

9.6. SEWERS IN NARROW LANES

The major cost items for sewers in narrow lanes are as follows:  HDPE pipes of size 160 mm  Chambers

9.7. OTHER ITEMS

The following items have been used for arriving at the total cost of the project:  Mobile Flushing Units  Cost of preparation of Detail Project Report (DPR)  Operation & Maintenance for 5 years

113 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

9.8. ABSTRACT OF COSTS

The Abstract of Cost for the sewerage project of town of Hajipur is as below:

S.NO. PARTICULARS AMOUNT (Rs.) 1 PART--"A" Earthwork, Timbering and Baricadding 131,881,804 2 PART--"B" Providing and Laying of Sewer lines with bedding 165,908,487 works 3 PART--"C" Construction of Manholes, Ventshafts and uPVC 364,318,855 pipe laying 4 PART--"D" Dismentalling and Restoration of Roads, structure 83,779,801 and Railway & NH crossing by Trenchless technology etc 5 PART--"E" E. Miscellaneous Items like encasing, 18,146,453 equipments for flushing of sewer lines etc 6 PART--"F" Provision for 2 nos pumping station, rising main 37,197,511 and pumping machineries and for dedicated HT & LT feeders. 7 PART--"G" Provision for STP (Sequential Batch Reactor) 22 217,250,000 MLD in PHASE I for population of 2026 including SCADA 8 TOTAL "A" to "G" 1,018,482,911 9 PART--"H" Provision for Land Acquisition 33,000,000 Provision for IEC activities 5,000,000 10 PART--"J" Centage charges @ 8.0% (excluding land 81,878,633 acquisition cost) GRAND TOTAL 1,138,361,544 SAY RS. Crores 113.84

Detailed estimates & rate analysis based on prevalent Schedule of rates in State of Bihar are available at Annexure A-9.

114 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Chapter 10. Funding & Implementation

10.1. IMPLEMENTING AGENCY

With a view to accelerate infrastructure development activities across all ULBs and assist the ULBs in developing, augmenting, financing and maintaining municipal services, Government of Bihar has established Bihar Urban Infrastructure Development Corporation Ltd. (BUIDCo), a Govt. of Bihar Undertaking registered under the Company’s Act 1956 (Act 1 of 1956) on 16th June, 2009. Govt of Bihar has decided Bihar Urban Infrastructure Development Corporation Ltd. (BUIDCo) to act as Execution Agency for all Projects sanctioned under JNNURM / UIDSSMT /NGRBA., There shall be tripartite contract agreements between BUIDCo, ULB and Contractor for capital works and for O&M of assets created.

10.2. AGENCY RESPONSIBLE FOR OPERATION & MAINTENANCES

After successful testing and commissioning of all components, the assets will be transferred to ULB for taking care of O&M responsibilities.

115 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Considering the financial, technical & human resource constraints of Municipal Council, it is proposed to club the operation & maintenance of the sewerage system with STP in first five years with Capital works contract. Later, with gradual capacity building of Municipal council, the O&M of the system may be taken over by Municipal council or outsourced to some private operator. The operation & maintenance of the project will be responsibility of Urban Local Body (ULB) i.e. Municipal Council of Hajipur Town. This is in line with the 74 Th Constitutional Amendment Act and also confirms the requirement of NRCD guidelines. NRCD guidelines recommends following; “Operation and Maintenance in all its facets is the responsibility of the local body aided and supported by State government. A firm commitment will be given by the local body that it agrees to bear the entire cost of O & M. The State Government shall give an undertaking that it will ensure that assets are properly operated and maintained and any short fall in resources will be met by them. The agency for O & M of the assets created will also be clearly mentioned in the DPR.”

10.3. IMPLEMENTATION PLAN

The major activities proposed for implementation of this project are identified as follows: i. Appointment of Construction Supervision Consultants : It is proposed to appoint Construction Supervision Consultants to assist the executing agency for smooth & timely implementation of Project. Construction Supervision Consultants will have primary responsibility for supervision of project construction activities & to ensure quality assurance & quality control etc. ii. Public awareness activities : A comprehensive programme will be framed and implemented with required assistance with local NGOs for taking up Information, Education & Communication (IEC) activities for the project. Active Public participation is of paramount importance for success of any projects iii. Preparation of Bid Document: Project management consultants will prepare the bid documents, technical specifications etc. iv. Bidding Process & Award of Contract: It is proposed to invite competitive bids at national level. The bid will be evaluated for

116 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

technical competence and work will be awarded to lowest bidder among already qualified bidders in technical evaluation stage. v. Project Execution: The project will be executed by the contractor to whom the work is awarded. The supervision of construction work will be done by Construction Supervision Consultants.

10.4. IMPLEMENTATION PERIOD

The initial nine months will be taken up by preliminary activities like identification & allotment/transfer of land for STP & Pumping Stations, appointment of Construction Supervision consultants, Preparation of bid documents, Bidding process & award of Contract. Afterwards the project execution period is taken up as 15 months.

10.5. PACKAGING

The whole project is proposed to be executed in a single package including sewerage network, pumping stations, sewage treatment plant etc.

10.6. IMPLEMENTATION SCHEDULE

The detailed implementation schedule of various packages is available on the next pages in the form of Gantt Chart.

10.7. FUNDING PATTERN

The funding pattern for the project will be in accordance with NRCD guidelines as determined by Ministry of Environment & Forest, Government of India. The guideline of NRCP programme recommends following: The National River Conservation Authority (NRCA) has decided that the Financing pattern of schemes of the NRCD for the conservation of rivers and lakes will be as follows:-  Government of India (NRCD) to bear 70% of the project cost,  States and the local bodies to bear 30% of project cost of which Share of the public shall be a minimum of 10%.  O & M shall be a part of the project and the costs thereon shall be borne entirely by the state and the local bodies for which additional resources have to be demonstrably raised and committed to O & M.

117 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 The Local Bodies may raise loans from Financial Institutions such as HUDCO to contribute their share,  If for any reason such as delay, wrong design or estimation, omission of items, inflation etc., there is cost overrun in any project, the central share in the total cost will be limited to the ceiling amount approved by the CCEA. Balance, if any, is to be borne by the respective state Government. It is, therefore, necessary to prepare the DPR accurately after investigation and survey and taking all factors into account that can influence the cost of the project. The State Governments should make all efforts to obtain larger plan allocations for such programmes. The contribution of 10 % from the beneficiaries and stakeholders can be raised in one or more of the following forms.  additional development charges, water and sewage cess  fair assessment, levy and recovery of property tax  house connection charges  contribution from Development Funds of local MPs and MLAs  Fines on polluters  Taxes from pilgrim/tourist/floating population visiting the town  Donation from industry, business associations, voluntary agencies such as Rotary and Lion’s clubs and philanthropists.  Any other mode. The funds required from different sources for the project are as follows:

S.No. Funding Source Share(%) Fund Required (Rs Crores)

1 Central Government 70 79.69 2 State Government & Local Bodies 30 34.15

Out of State Government & Local bodies share of Rs 34.15 crores, as per the guidelines of NRCD, the minimum share of public shall be 10% i.e. Rs 3.41 crores. This contribution is proposed to be generated through House connection charges, fine imposed on polluters and water & sewage cess. As required by NRCD guidelines, the quarterly requirement of funds from different agencies as project shall be as follows:

118 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Funding Fund Quarterly Fund Requirements Source Required Pre Construction Phase Construction Phase (Rs Crores) I II III IV V VI VII VIII Central Government 79.69 0.16 0.64 9.25 7.14 17.85 25.00 14.29 5.36 State Government & 34.15 0.07 0.27 3.97 3.06 7.65 10.71 6.12 2.29 Local Bodies

Total 113.84 0.23 0.91 13.22 10.21 25.51 35.71 20.41 7.65

Quarterly Funds requirement (Rs Crore) 40.00 35.71 35.00 30.00 25.50 25.00 20.42 20.00 13.22 15.00 Rs in Crores in Rs 10.20 7.65 10.00 0.91 5.00 0.23 0.00 1 2 3 4 5 6 7 8 Quarters Central Government State Government & Local Bodies Total Funds

119 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Chapter 11. Operation & Maintenance

11.1. INTRODUCTION

The lack of proper maintenance has resulted in deteriorated sewers with subsequent backups, overflows, cave-ins, hydraulic overloads at treatment plants, and other safety, health, and environmental problems in several cities across the world. As one of the most serious and environmentally threatening problems, sanitary sewer overflows—or SSOs—are a frequent cause of water quality degradations and are a threat to public health as well as the environment. Flooded surroundings and overloaded treatment plants are some symptoms of collection systems with inadequate design capacity and improper management, operation, and maintenance. The poor performance of many sanitary sewer systems and resulting potential health and environmental risks experienced frequently in developing countries highlight the need to optimize operation and maintenance of these systems. Commonly accepted types of maintenance include three classifications: corrective maintenance, preventive maintenance, and predictive maintenance. Thus in case like this project town of Hajipur, where entirely new system are to be put in place, predictive maintenance assumes the greatest importance. Schedules for regular preventive maintenance also needs to be developed. It is of note that comprehensive specifications & construction practices go a long way in ensuring an easy & trouble free operation & maintenance for example, ise of SFRC in manholes and sewers where appropriate, laying of adequately designed sewers at recommended grades and selection of robust plant & equipment such as pumps, blowers, aerators etc.

11.1.1. CORRECTIVE MAINTENANCE

Maintenance classified as corrective, including emergency maintenance, is reactive. Only when the equipment or system fails is maintenance

120 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

performed. Reliance on reactive maintenance will always result in poor system performance, especially as the system ages.

11.1.2. PREVENTIVE MAINTENANCE

Maintenance classified as preventive is proactive and is defined by a programmed, systematic approach to maintenance activities. This type of maintenance always results in improved system performance except in the case where major chronic problems are the result of design and/or construction flaws that cannot be completely corrected by O&M activities. Proactive maintenance is performed on a periodic (preventive) basis or as needed (predictive) basis. Preventive maintenance can be scheduled on the basis of specific criteria such as known problem areas (for example—a siphon that often gets clogged, a low point that is often first to overflow in a storm event, or even an area prone to blockages), equipment operating time since the last maintenance was performed, or passage of a certain amount of time (calendar period).

11.1.3. PREDICTIVE MAINTENANCE

The third type of maintenance is predictive. Predictive maintenance, which is also proactive, is a method of establishing baseline performance data, monitoring performance criteria over a period of time, and observing changes in performance so that failure can be predicted and maintenance can be performed on a planned, scheduled basis. It is often said that predictive maintenance begins at the conceptual stage and is half done by the time detailed designs are finalized. Such conceptual and design interventions aim at framing rigorous specifications for each and every component so that it functions with the desired efficiency at-least till the end of design life. Some pointers to predictive maintenance for sewerage system are:  Use of proper design years and flows based on scientific town planning principles & regulations.  Building necessary redundancies, back-ups into the system including use of appropriate factor of safety, especially in regard to mechanical equipment.  Creating/planning bye-pass/overflows arrangements at Sewage Treatment Plant and for various units of STP

121 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 Specifying adequate spares and maintaining proper inventory of chemicals/fuel and other perishables considering delivery time, shelf life and criticality of the spares/chemicals etc for units/STP.  Adopting detailed design of units so that O&M is simplified and facilitated (eg elevated disposal conveyers, chutes capable of discharging to containers/trolleys etc. for grits, screenings etc)  Specifying chemical resistant paint for metal parts/components/ structures subject to corrosion  Specifying adequate instrumentation to inform on health of the system, units, equipment. System performance is frequently a reliable indicator of how the system is operated and maintained. Agencies that historically rely primarily on corrective maintenance as their method of operating and maintaining the system are seldom able to focus on preventive and predictive maintenance since most of their resources are consumed by corrective maintenance.

11.1.4. FLUSHING PLAN

As there are in all 2543 links in the sewerage network and out of which approximately 1011 pipes in the initial stretches of network are having velocities less than 0.3 m/s for peak flow in first year of operation. These pipes will require regular flushing as a preventive measure, as these shall have a higher probability of tendency to choke. A provision of one jetting machines and three tractor with trolley have been taken in the estimates for both corrective and preventive maintenance. It is proposed to employ one tractor with trolley for corrective maintenance for attending complaints as & when received and balance one jetting machines & two tractor with trolley shall be employed for flushing all these identified sewers with higher tendency to choke. The whole of the town may be divided in three zones with a view that each jetting machines/tractor with trolley is equally work allotted. Assuming six working days in a week and one day assigned for workload of corrective maintenance and repairs, it is assumed that each jetting machine/tractor with trolley shall effectively take up work of flushing for five days in a week. Assuming a three week cycle and five working days in a week, each flushing unit will flush 23 pipes each working day. So, a three

122 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

week program will be chalked out for each flushing unit to flush these sewers at least ones in a three week time.

11.2. BENEFITS

The benefits of an effective operation and maintenance program are as follows:  Ensuring the availability of facilities and equipment as intended.  Maintaining the reliability of the equipment and facilities as designed. Utility systems are required to operate 24 hours per day, 7 days per week, and 365 days per year. Reliability is a critical component of the operation and maintenance program. If equipment and facilities are not reliable, then the ability of the system to perform as designed is impaired.  Maintaining the value of the investment. Wastewater systems represent major capital investments for communities and are major capital assets of the community. If maintenance of the system is not managed, equipment and facilities will deteriorate through normal use and age. Maintaining the value of the capital asset is one of the major responsibilities. Accomplishing this goal requires ongoing investment to maintain existing facilities and equipment and extend the life of the system, and establishing a comprehensive O&M program.  Ensuring full functionality of the system throughout its useful life.  Collecting accurate information and data on which to base the operation and maintenance of the system and justify requests for the financial resources necessary to support it.  Planned maintenance and repairs are much more cost effective both in the long and short term because the work can be done with the proper materials during normal working hours and under preferred working conditions. Besides this, they have potential for significant savings in fuel & power by maintaining requisite efficiencies.

11.3. TECHNICAL & MANAGERIAL CAPACITY

Certainly, the operation & maintenance responsibilities are to be shouldered by one or a combination of stakeholders especially the user

123 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

group or nodal agency. Municipal Council is expected to be responsible for operation & maintenance of the proposed sewerage system or at-least overseeing the O&M if some PPP model is adopted for O&M of the proposed system. . As the town does not have sewerage facilities till now, Municipal council does not possess the tools & plant, equipment and manpower required for operation & maintenance of sewerage system. Municipal council is having regular Engineering staff primarily responsible for civil works e.g. buildings, roads, street drains etc. but the capacities & human resources required for efficiently carrying out the O&M are lacking to a large extent.

11.4. OUTSOURCING :

Looking to constrained capacities of Municipal Council in regard to financial, human & equipment resources, it may not be prudent for Municipal Council to shoulder this additional responsibility atleast in the near future. The recommended approach is to • Club the operation & maintenance for certain period with the capital works. This will enable the municipal council to get fully acquainted with the sewerage system for taking up the work in future, if required. • In future the operations could be outsourced to private sector. • Alternatively, if the Municipal Council decides, intensive training in O&M of the system can be imparted to identified personnel. However, such experiments in other cities have been less successful over a period of time.

11.5. SEWERAGE O&M MANAGEMENT PLAN

A comprehensive Sewerage System Management plan is required to be put in place for safe & reliable performance of the proposed system & to enable the sewerage system to deliver its intended objectives. The major components of such management plan are as follows:  Provide adequate operation and maintenance of facilities and equipment.  Maintain an up-to-date map of the collection system showing all gravity line segments and manholes, pumping facilities, pressure pipes and valves. This could be preferably GIS based.

124 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 Maintain relevant information to establish and prioritize appropriate Wastewater Collection System Management Plan activities (such as the immediate elimination of dry weather overflows or overflows into sensitive waters, such as public drinking water supplies and their source waters), and identify and correct/rectify after assessing the causes & selecting appropriate corrective action.  Routine preventive operation and maintenance activities by staff and contractors, including a system for scheduling regular maintenance and cleaning of the collection system with more frequent cleaning and maintenance targeted at known problem areas as well as a tracking system for work orders. Special mention need to be made for flushing of starting sewers in developing areas. A regular schedule of flushing needs to be developed & enforced for say first 5 years after commissioning.  Identify and prioritize structural deficiencies and implement short- term and long-term rehabilitation actions to address each deficiency. This shall include a rehabilitation plan including schedules for the entire system. As with the preventative maintenance program, sewer rehabilitation and replacement is crucial for the prevention of spills.  Provide supervision training on a regular basis for staff in collection system operations, maintenance, and monitoring, and determine if contractors’ staffs are equipped with adequate skill sets.  Provide equipment and replacement parts inventories, including identification of critical replacement parts.  Establish an implementation plan and schedule for a comprehensive IEC aimed at educating public that promotes proper disposal of wastewater and inculcate civic sense.  Describe financial resources necessary to ensure system operation, including fee structure, actual and projected five-year budget expenses for staffing, operation, system extension projects, and reserves.  Describe staffing available to ensure effective supervision/overseeing system operation (identifying individuals and titles) including developing, implementing, and revising the Wastewater Collection System Management Plan. Include an organizational chart, duties, and training frequency.

125 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

There shall be an Overflow Emergency Response Plan that identifies measures to protect public health and the environment. At a minimum, this plan should provide for the following actions.  Ensure proper notification procedures so that the primary responders are informed of all overflows in a timely manner (to the greatest extent possible).  Ensure that all overflows are appropriately responded to, including ensuring that reports of overflows are immediately dispatched to appropriate personnel for investigation and appropriate response.  Ensure immediate notification of health agencies and other impacted entities (e.g., agencies responsible for water suppliers etc) of all overflows.  Ensure that appropriate staff and contractor personnel are aware of the plan, follow the plan, and are appropriately trained.  Provide emergency operations, such as traffic and crowd control, and other necessary emergency response as necessary in case of corrective maintenance.  Take all reasonable steps to contain untreated sewage, prevent sewage discharges to surface waters, and minimize or correct any adverse impact on the environment resulting from the overflows, including additional monitoring as may be necessary to determine the nature and impact of the discharge.  Develop and implement a plan to respond in a timely manner to spills and other emergencies. Collection system staff should be able to respond to a sewage spill in less than an hour from the first call. The Authorities must own or have ready access to spill and emergency response equipment such as vacuum trucks, hydroflushers, pumps, temporary bypass hoses, and portable generators of adequate number and capacity to operate pump stations.

11.6. O&M COSTS

Looking to the financial resources available with municipal Council, It is not sustainable for the project to have municipal Council to bear the operation & maintenance of the proposed system.

11.6.1. PROVISION FOR SEWERAGE CHARGES IN BIHAR MUNICIPAL ACT , 2007

126 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Section 216 of Bihar Municipal Act,2007 stipulates the sewer charges to be collected from property owner connected to public sewers and is reproduced below: 216. Sewerage charge and sewerage cess.- (1) The Municipality shall levy sewerage charge on the owners of premises for connection of such premises to sewerage mains, such amount being not less than one-half of the amount chargeable for water-supply under sub-section (2) of section 171 or sub- section (2) of section 172, as the case may be, as may be determined by regulations from time to time. The provision for water charge in the Bihar Municipal Act,2007 is as follows: 171. Supply of water to connected premises.- (1) The Chief Municipal Officer may, on an application by the owner, lessee or occupier of any building, either on his own or through any other agency, arrange for supply of water from the nearest main to such building for domestic purposes in such quantity as may be deemed to be reasonable and may, at any time, limit the quantity of water to be supplied whenever considered necessary: Provided that the Chief Municipal Officer may, by order in writing, delegate the responsibility of receiving the application to any other agency. (2) For the water supplied under sub-section (1), payment shall be made at such rate as may be fixed by the Municipality from time to time: Provided that such rate shall, as far as practicable, cover the costs on account of management, operation, maintenance, depreciation, debt servicing, and other charges related to waterworks and distribution costs, including distribution-losses, if any. Section 172 of Bihar Municipal Act, 2007 contains similar provision for water supply for Non Domestic purposes. At present, a holding tax of 9% of total rental value of property is being levied from property owners in municipal area. Out of this holding tax, water charges in lieu of supply of drinking water constitute 2%.

11.6.2. MODALITIES FOR SELF SUSTAINING SYSTEM

Some arrangement of sharing of cost between Municipal Council and user in initial phases and gradually shifting the full O&M cost to the user is the preferred choice. The sewerage charges from the consumers could be collected by one of the following methods:

127 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 Sewerage charges may be charged as a %age of water charges and will be collected with water bill. This method is adopted in other towns also.  Sewerage charges may be charged on basis of Plot size & locality and could be collected with land & property taxes.

11.6.3. SUSTAINABILITY

For successful implementation and operation of project, it is imperative that project should be financially and economically sustainable. The benefits accrued from the project should be able to offset the capital and O&M expenses incurred on the project and possible will also provide finances for creating new assets required for future. Sewerage projects are capital intensive. The prevailing mindset among community is that the state is responsible for providing the basic civic amenities and shall bear the costs involved in implementation & operation of such projects. Presently there is increasing stress that a gradual shift is being made to made the beneficiaries bearing the financial burden for development projects. As a first move, it is expected the beneficiaries shall bear the cost to the extent that O&M costs are recovered with gradual realization of capital costs from the beneficiaries. It has sometimes been suggested that financial viability not be made a concern because as long as a project is economically sound, it can be supported through government subsidies. However, in most cases, governments face severe budgetary constraints and consequently, the affected project entity may run into severe liquidity problems, thereby jeopardizing even its economic viability. Expenditures

Cost involved in Operation & maintenance of this project have been categorized in four major divisions; namely  Power Charges: For operation of twelve pumping stations at different locations and thirteenth at STP.  Repair & maintenance Charges: For Sewerage system & Sewage treatment Plant and are adopted as %age of total capital costs.  Salary Charges: For salaries & wages for the operating & maintenance staff. The staff at STP & Sewer network adopted looking to the requirement of respective zone.

128 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 Chemical Charges : For STP, lump sum cost of the chemicals is adopted. Analysis

A detailed analysis of projected operation & maintenance costs for this project has been carried out for the entire project period i.e. from 2011 to 2041. Base Data & Assumptions: The various parameters adopted are as follows:

S.No. Particulars Adopted Values 1 Start Year 2012 2 Project Period 30 3 Efficiency of P/Sets 50% 4 Power Charges 4.5 5 LPCD 135 6 Wastewater Contribution 80% 7 Infiltration 5% 8 Maintenance Cost Civil 0.20% 9 Maintenance Cost Mechanical 1.00% 10 Annual increase 0.00% 11 Discount Rate 10%

The details of various staff for purpose of arriving at cost for salary & wages at Sewage treatment Plant & Sewer Network is as follows: Sewer Network

Monthly S.No. Particular Numbers Salary 1 Supervisors 2 20000 2 Labour, Sweepers 16 8000 3 Drivers 4 10000

Pumping Stations

Monthly S.No. Particular Numbers Salary 1 Pump Driver 6 8000 2 Labour 6 5000

Sewage Treatment Plant

Monthly S.No. Particular Numbers Salary Plant Supervisor Cum Chemist and 1 2 20000 SCADA Operator

129 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

2 Pump Driver/Mechanic 9 8000 3 Lab Assistant 1 8000 4 Labour 9 5000 5 Security Guard 3 5000

The analysis results are available at Annexure A-11. The results of this analysis are as follows: In the analysis the price escalation and annual increase in sewer charges has not been considered to keep the parity between O&M costs and revenues. Annual O&M Cost for this project comes to be Rs 139.39 lacs in year 2012 and increased to Rs 224.43 lacs in year 2042. Price escalation has not been considered while arriving at future O&M costs. The total O&M cost for the entire project period comes to be Rs 5389.91 lacs. Discounted value of these O&M cost for entire project period is Rs 1630.02 lacs at year 2012 prices with a discount rate of 10%. Sewer charges required to be levied from the user to offset the undiscounted operation & maintenance cost comes to be Rs 1.85 per cu.m. Sewer charges required to be levied from the user to offset the discounted cost of O&M comes to be Rs 1.95 per cum. It is proposed to charge Rs 1.95 per cum for ensuring long term sustainability of the project.

11.7. MUNICIPAL COUNCIL HAJIPUR

11.7.1. BACKGROUND

Municipal Council, Hazipur was established in year 1969. The Urban Local Bodies of State of Bihar are governed by The Bihar Municipalities Act, 2007.

11.7.2. ADMINISTRATIVE SETUP

Municipal Council is governed by an elected board with Chairman as its head. Administrative function for the council are carried out by Executive Office assisted by support staff. The various sections in Hazipur Municipal Council for discharging its duties are as follows:  General Administration Section  Revenue Section  Public Health Section  Epidemic Section

130 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 Public Works Section  Drain cleaning section  Street Cleaning Section  Market & slaughterhouses Section Municipal Council, Hajipur has staff strength of 230 numbers. Against which only 125 staff is working at present and balance 105 positions are vacant. The list of various sanctioned, working & vacant positions are as follows:

S.No. Name of Position Sanctioned Number of Number of Posts Working Vacant Posts Employees

1 Accountant 1 - 1

2 Secretary 1 1 -

3 Assistant Engineer 1 1 -

4 Senior Assistant 1 - 1

5 Cashier 1 1 -

6 Upper Divisional 3 3 - Assistant

7 Assistant 5 5 -

8 Tax Collector 1 1 -

9 Assistant Tax 2 - 2 Collector

10 Tehsildar 10 7 3

11 License Inspector 1 1 -

12 Amin 1 1 -

13 Sanitary Inspector 1 1 -

14 Ward Inspector 2 2 -

15 Ward Jamadar 13 9 4

16 Keet Shodhak 2 1 1

17 Driver 1 1 -

131 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

S.No. Name of Position Sanctioned Number of Number of Posts Working Vacant Posts Employees

18 Rickshaw Jamadar 1 1 -

19 Teekakar 1 - 1

20 IV class 20 8 12

21 Guard 1 1 -

22 Sweepers 153 76 77

23 Road Coolie 7 4 3

Total 230 125 105

The Municipal Council carries out the following core functions either directly & independently or with support of other support agencies/contractors: i. Water-supply for domestic, industrial, and commercial purposes, ii. Drainage and Sewerage, iii. Solid Waste Management, iv. Preparation of plans for development and social justice, v. Communication systems, construction and maintenance of roads, footpaths, pedestrian pathways, transportation terminals, both for passengers and goods, bridges, over-bridges, subways, ferries, and inland water transport system vi. Transport system accessories including traffic engineering schemes, street furniture, street lighting, parking areas, and bus stops, vii. Community health and protection of environment including planting and caring of trees on road sides and elsewhere, viii. Markets and slaughterhouses, ix. Promotion of educational, sports and cultural activities, and x. Aesthetic environment.

11.7.3. TOOLS & PLANTS

132 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

ULB, Hajipur has following vehicles, equipment to carry out its responsibilities:

S.No. Particulars Total

1. JCB 1

2. Tipper 1

3. Suction Machine 1

4. Tractor with Trolley 3

5. Ricksaw trolley 20

11.7.4. INCOMES & EXPENDITURES

The incomes & expenditures of Municipal Council, Hajipur as obtained from its office is available at Annexure ‘A-10’. The incomes and expenditures for item related to Water Supply & Sanitation are as below: Incomes

Income Estimate for Actual Actual Revised the Next Year Income for Income Budget for 2008-09 Last year Current Year Current Year 2006-07 2007-08 for 9 2007-08 Month 1 2 3 4 5 Revenue from Transportation of Sewage a) Fertilizer Sale b) Wastage Sales c) Workshop Rent Watering a) Water Connection Fee 50,000.00 50,000.00 b) Fee for Inspection of Water 10,000.00 Connection 10,000.00 Municipal Tax a) Toilet Tax - Due 5,983,539.00 5,903,549.00 - Current 1,248,701.00 1,248,701.00 b) Water Charges - Dues 3,856,137.00 3,849,137.00 - Current 826,178.00 826,178.00 Subsidy from 12th Finance Commission by the Govt. a) Drainage & Sewerage System 125,000.00 125,000.00

133 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Income Estimate for Actual Actual Revised the Next Year Income for Income Budget for 2008-09 Last year Current Year Current Year 2006-07 2007-08 for 9 2007-08 Month 1 2 3 4 5 Sanitary Equipment 1,500,000.00 1,500,000.00 Water Consumption Scheme 110,867,000.00 30,000,000.00 75,000,000.00

Sanitation of Dig 100,000.00 100,000.00 Water Supply Scheme Construction of Dig 3,000,000.00 3,000,000.00 Land Acquired TOTAL INCOME 127,566,555.00 - 30,000,000.00 91,612,565.00 Expenditures

Expenditure Estimate for Actual Actual Revised the Next Year Income for Income Budget for 2008-09 Last year Current Year Current Year 2006-07 2007-08 for 9 2007-08 Month 6 7 8 9 10 Water Recharging and Drain Est. Work a) Basic Work 6,000,000.00 b) Maintenance 2,000,000.00 c)Construction Charge Water Supply and Water Works a) Basic Work 110,867,000.00 b) Maintenance 10,000,000.00 c)Construction Charge Transporati on for Sewage a) Public Toilet Construction b) Community/Pvt. Toilet Construction c) Tractor and Trailor d) Watering on the Road

e) Land Acquired f) Drain Construction Sulabh Complex 3,000,000.00 Sanitary Equipment

134 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Expenditure Estimate for Actual Actual Revised the Next Year Income for Income Budget for 2008-09 Last year Current Year Current Year 2006-07 2007-08 for 9 2007-08 Month 6 7 8 9 10

TOTAL EXPENDITURE - - - 131,867,000.00

11.7.5. POWER OF MUNICIPALITIES FOR SEWERAGE CONNECTION

The various provisions in Bihar Municipal Act, 2007 are adequate enough to motivate the household to take house sewer connection and to discharge the property generated wastewater in public sewers in safe & environmentally friendly manner. The Act also includes provisions to deal with defaulters. The various related provisions are reproduced below: Article 201 201. Premises not to be erected without drains.- (1) It shall not be lawful to erect or re-erect any premises in the municipal area or to occupy any such premises unless - (a) a drain is constructed of such size, materials and description, at such level, and with such fall, as may appear to the Chief Municipal Officer to be necessary for the effectual drainage of such premises, (b) there have been provided and set up on such premises such appliances and fittings as may appear to the Chief Municipal Officer to be necessary for the purposes of gathering or receiving the filth and other polluted and obnoxious matters, and conveying the same, from such premises and of effectually flushing the drain of such premises and every fixture connected therewith. (2) The drain so constructed shall empty into a municipal drain situated at a distance of not exceeding thirty metres from the premises, but if no municipal drain is situated within such distance, then, such drain shall empty into a cesspool situated within the distance to be specified by the Chief Municipal Officer for the purpose. Article 216 216. Sewerage charge and sewerage cess.- (1) The Municipality shall levy sewerage charge on the owners of premises for connection of such premises to sewerage mains, such amount being not less than one-half of the amount chargeable for water-supply under sub-section (2) of section 171 or sub-

135 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

section (2) of section 172, as the case may be, as may be determined by regulations from time to time. (2) Where the owner of any premises in a locality where sewer is laid by the Municipality has not taken connection from the sewerage mains, he shall be liable to pay a sewerage cess of such amount, not being more than one-half of the amount chargeable as sewerage charge under sub-section (1), as may be determined by regulations from time to time. (3) Where the owner fails to pay the sewerage charge or sewerage cess, such sewerage charge or sewerage cess, as the case may be, shall be realized from the occupier, and the occupier shall be entitled to recover the amount from the owner. (4) The connection of premises to sewerage mains shall be provided within a period of thirty days from the date of receipt of an application in this behalf from the owner of the premises. (5) The charges received by the Municipality from the owner or the occupier for connecting the premises to sewerage mains shall be spent only for the works relating to the sewerage system.

11.8. SPECIFIC O&M REQUIREMENTS

The specific O&M requirements for the proposed infrastructure for sewerage & Sewage Treatment Plant are listed below: Regular Basis  Remove weeds from facility areas & keep the area tidy & clean.  Check/service/repair/rebuild electrical as necessary including wiring, circuit breakers, starters, capacitors, circuit boards, switches, motors, DG Sets, diesel inventories etc.  Inspect Manholes for deposition of silt, flow, damaged manhole cover & steps specifically during making new connections & Clean out if debris found  Inspect the sewers between successive manholes for deposition of silt & flow and if required, clean manually or flush hydraulically the sewer line, if required.  Check air release valves in force mains, sluice gates or stoppages in the sewers.  Check for any harmful or extraneous matter entering the sewer lines.

136 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

 Shutdown, Start and test lift stations and cycle pumps by lifting floats on regular basis  Report any adverse conditions, such as spills, illegal dumping, out of compliance conditions to the authorities. Emergency Repairs  Repair sewer line breaks, blockages. Pump out & safe disposal of wastewater in case of overflows.  Repair/replace lift station pumps/ pump house/other equipment  Pull & remove debris plugging lift station pumps when plugged  Respond to emergency/trouble calls

11.9. O&M EQUIPMENT

The equipment normally required for operation & maintenance of sewerage system are as follows:  Portable Pump Sets & hose pipes for effective & quick pumping out the impounded overflows  Bamboo Sticks, Manila rope & cloth balls for manual cleaning of small sewers up to 300 mm dia sewers  Sewer cleaning bucket machine for cleaning a section of sewer.  Dredger (Clam Shell) for removing debris from manholes  Roding machine with flexible sewer rods for mechanical removal of blockages  Scraper for removal of silts usually in large diameter sewers  Jetting machines for removal of obstructions using high velocity water jets  Suction units for siphoning of slurry material from manholes, catch pits etc  Pneumatic plugs for sectionalizing the sewer lengths  Safety equipment for O&M requirement such as half & full face masks, gum boots, safety lamps, harnesses, hard hats and communication systems.

137 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

Chapter 12. IEC Activities & Capacity Building

12.1. COMMUNICATION STRATEGY

Information sharing & Communication Planning is an integral part of planning for sustained development. The development of human society has largely been due to its ability to communicate information and ideas with each other and to use such information and ideas for progress. This project being implemented by the Municipality aims at sustainable holistic development in Sanitation Sector. The success of this project is heavily dependent on the participation of the people, in the implementation process. To enable people to participate in the development process, it is necessary that people have adequate knowledge about the nature and content of these projects. Information Education and Communication, therefore, assumes added significance in the context of the this project. The feedback received on the implementation of such projects in the field indicate that these projects are critically dependent on the awareness level about them, transparency in the implementation process at the field level, participation of the people in the development process and accountability of different groups of stakeholders with different stakes e.g. Municipality, beneficiaries, contractors etc. In this context it is proposed to adopt a 4- pronged strategy of creating Awareness about the project, ensuring Transparency in the

138 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

implementation, encouraging People’s Participation in the development process and promoting the concept of Social Audit for ensuring Accountability. All the four elements of the above strategy are complementary to each other and appropriate IEC activities are an essential part of actualizing this strategy. Information, Education and Communication plays a pivotal role in creating awareness, mobilizing people and making development participatory through advocacy and by transferring knowledge, skills and techniques to the people. It is also critical for bringing about transparency in implementation of the project at the field level and for promoting the concept of accountability and social audit. It is proposed to formulate appropriate IEC strategy in tune with the communication needs of the this project. The IEC activities are to be undertaken through the available & effective modes of communication in order to inform the people with messages and details on Sewerage Project. Dissemination of information has to be sustained over a period of time and also that in order to make communication effective, it has to be in the language and idiom of the target groups. Accordingly, efforts are required to be made through Electronic Media and Print Media to disseminate information in regional languages and dialects, besides Hindi and English. In addition, the Action Plan also envisages IEC activities through other modes of communication, outdoor publicity and other conventional and non-conventional modes of communication for reaching out to the people in project areas.

12.2. PRINT MEDIA

The power of the press arises from its ability of appealing to the minds of the people and being capable of moving their hearts. Despite the fast growth of the electronic media, the printed word continues to play a crucial role in disseminating information and mobilizing people. It is required to ensure that the Project is portrayed in proper perspective, several steps need to be taken to sensitize the media about health & sanitation issues. During the implementation period, it is proposed to organize press conferences, press tours and workshops, so as to sensitize press persons about these issues. It is also proposed to issue advertisements at regular intervals in State and Regional Press. It is also proposed to publish booklets, leaflets providing information about the project & need for proper health & sanitation simple language in Hindi and Regional

139 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

languages. The other possible means for publicity could be printing & distribution of wall calendars, desk calendars.

12.3. ELECTRONIC MEDIA

An intensive IEC campaign over the Electronic Media (Radio and TV) is also required for optimum dissemination of information on these issues. In order to meet the area and region specific communication needs of this project, audio and video programmes of suitable time period shall be produced and broadcast/telecast over local and primary stations of All India Radio and Regional Kendras of Doordarshan. In addition short duration spots on different themes relating to health & sanitation shall need to produced in different languages and broadcast over AIR and Doordarshan. Synergies between different media can be exploited to great advantage. For meeting expenditure on IEC activities, a suitable provision in cost estimates has been taken.

12.4. CAPACITY BUILDING

Capacity building often refers to assistance which is provided to entities, usually lacking in resources to achieve required objectives, which have a need to develop a certain skill or competence, or for general upgrading of performance ability. UNDP defined 'capacity building' as the creation of an enabling environment with appropriate policy and legal frameworks, institutional development, including community participation (of women in particular), human resources development and strengthening of managerial systems, adding that, UNDP recognizes that capacity building is a long-term, continuing process, in which all stakeholders participate (ministries, local authorities, non-governmental organizations and user groups, professional associations, academics and others). Capacity Building is much more than training and includes the following:  Human resource development, the process of equipping individuals with the understanding, skills and access to information, knowledge and training that enables them to perform effectively.  Organizational development, the elaboration of management structures, processes and procedures, not only within organizations

140 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

but also the management of relationships between the different organizations and sectors (public, private and community).  Institutional and legal framework development, making legal and regulatory changes to enable organizations, institutions and agencies at all levels and in all sectors to enhance their capacities The capacity building measures proposed under this project are summarized below:  Human Resource Development Human resources development is very essential for internal capacity building for any organization. Training, motivation, incentives for outstanding service and disincentives for those who fail to perform are essential for human resources development. This includes: Training Management of sewerage system is a new responsibility with Municipal Council. Integrated & comprehensive systems have to be developed to operate & maintain the sewerage system effectively. Knowledge of new technology and methods coupled with training at all levels is necessary. Short and medium term courses should, therefore, be designed for the sanitation workers and supervisory staff. Special training and refresher courses may also be conducted as under:- • Special Training To Unqualified Staff • Refresher Courses For All Levels of Staff o Roles & Responsibilities o Jurisdiction o Training on use of new equipment o Safe way to work • Exposure to Municipal Commissioner/ Chief Executives • Exposure to Elected Members In this connection, CPHEEO sponsored training programmes in different institutions can impart much needed knowledge.  Data acquisition & retrieval

141 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

It is proposed to equip the Municipal Council with tools that will ease the collection, analysis and retrieval of all system data in timely & economical manner. The tools proposed to be provided under this project are: • Computers • Printers • Plotter • Operating System Software • Office Software • CAD Software • Geographical Information System (GIS) : (may be implemented to begin with and should be hosted centrally for use of different agencies, proper authorization levels for access & modifications to database need to be decided at al services. • A toll free and automated response phone number goes a long way in facilitating transmittal of advance warnings on system health, emergencies, failures (e.g. pipe bursts or overflows) which may be useful in reducing response time.  Involvement of Voluntary organization/ NGO/ Private Sector Participation Management of Sewerage system services is highly labour intensive on account of increased wage structure of the Government and municipal employees this service is becoming more and more expensive. Besides, the efficiency of the labour force employed in the urban local bodies is far from satisfactory. High wage structure and inefficiency of the work force results into steep rise in the cost of service and yet the people at large are not satisfied with the level of service being provided by the urban local bodies. Efforts to increase the efficiency by Human Resource Development and institutional strengthening will, to some extent improve the performance but that may not be enough. It is proposed to involve Voluntary Organisations/NGO/Private sector participation in Sewerage System management. Private sector participation or public private partnerships are proposed to be considered for this project by clubbing O&M of system for five years with civil contract.

142 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

12.5. COMMUNITY PARTICIPATION UNITS

For successful implementation of project and its consequent efficient & uninterrupted operations, the active participation of all the stakeholders is of utmost importance which includes the actual users. The primary task is to educate, inform and enlighten the public for do’s and don’ts for effective utilization of sewerage system. The required do’s and don’ts are as below:  For connecting the property to Public Sewer as soon as the system is commissioned.  To Connect all the sullage disposal units to Sewers  Not to dump any solid waste in property connection to manholes  Not to discharge any objectionable liquid in public sewers  Not to connect rain spouts to sewers To achieve these objectives, it is proposed to setup a community participation unit which will perform following activities:  Devise & implement a Communication Plan  Implement a Media Plan for dissemination of information  Catalyze formation of user groups, resident welfare association for effective involvement of users The various components for these activities shall be as follows:

S. No. Activity Remark

1 Engagement of Public relation To be done with Consultants specific objectives

2 Social Surveys For ascertaining level of awareness and willingness to pay for improved services

3 Advertisement in TV, Radio, For enhancing Newspapers in vernacular awareness & sensitization of all stakeholders

143 NGRBA Detailed Project Report Sewerage Project, Hajipur (Bihar)

S. No. Activity Remark

4 Publication & Distribution of - do - Booklets, Pamphlets etc in vernacular

5 Engagement of NGOs for Street - do - Plays, Kathputli shows, Local cultural communication techniques

144