March 7, 2019 30% Design Community Meeting

High School Site 113-H-W-4

Please sign in on your mobile device: http://communitymeeting.ocps.net/ High School Site 113-H-W-4 30% Design Meeting Agenda March 7, 2019 6:00 PM

• Welcome – School Board Member: Pam Gould • Introductions – Lauren Roth: Facilities Communications • Project Update – • Second Access Point – Julie Salvo: Facilities Planning • Questions and Answers • Adjournment

1 Site Location

WINDERMERE HS Lake Butler

S.R. 429 DR. PHILLIPS HS

Lake Hancock

ORANGE FICQUETTE RD. COUNTY Lake Tibet NATIONAL GOLF COURSE

Huckleberry Lake Lake Mabel Lake Sheen INTERSTATE 4 INTERSTATE

Hickorynut Lake SITE 113 NEW HIGH SCHOOL DISNEY WORLD

Reedy Lake

NEW HS SITE 80 north LAKE COUNTY WINTER GARDEN VINELAND ROAD GARDEN VINELAND WINTER ORANGECOUNTY

2 Site Aerial

Tub Lake Hickorynut Lake

Lakeshore

SEIDEL ROAD

H.S. Site 113-H-W-4 (+/-68 Acres) Reedy Lake

north

3 Village F PD Change Determination Request - CDR-19-01-036 • Request to add access point to school property off of Summerlake Groves St. • Access point needed because original access was eliminated when Seidel Rd. was realigned • Schools are required to have 2 access points to separate traffic

4 Development Plan • School has correct zoning (Village F PD) • Next step is County Development Plan (DP) approval – fully engineered site plan review by all departments • Review will also include a detailed traffic operations analysis

5 Site Plan

SEIDEL ROAD FRONT Parking DOOR (240 Spaces) Parent Drop Wetland

Bus Drop 3-Story HS Campus

FRONTAGE ROAD FRONTAGE Parking (240 Spaces)

Service

Tennis Basketball Baseball Softball Bus Parking (75 buses Stadium & 75 cars) Track & Parking Field (380 Spaces) (lighted) Practice Practice

Access Easement for Retention Reedy Creek north Student Stations = 2,776 Improvement District Parking = 860 spaces 0’ 200’ Car Stacking = up to 233 cars On-site Bus Stacking = 40 buses

6 Project Basis – OCPS Prototype High School

OCPS PROTOTYPE HIGH SCHOOLS Evans High School Windermere High School Oak Ridge High School Evans High School West Orange High School Freedom High School Olympia High School

Oak Ridge High School Wekiva High School

7 Project Basis – OCPS Prototype High School

UPGRADES INCLUDED PROTOTYPE Windermere High School Evans High School Educational • 21st Century Collaborative Learning Hubs

Technology • Interactive Touchscreen Smart TV’s • WiFi access points throughout

Energy Efficiency • LED lighting campus wide (interior, exterior, site and athletic fields) • High efficiency chillers and variable pumping scheme • Low flow plumbing fixtures • Commissioning of MEP systems • ASHRAE 90.1 compliance for lighting and power metering

Security • Full security access control and cameras for the school • 2-way emergency radio system • Voice evacuation fire alarm system • Permanent generator and life safety lighting Oak Ridge High School Wekiva High School 8 Building Program Student Capacity: 2,776 Buildings: +/-350,000 Square Feet Campus Program Administration Media Center Cafeteria Classroom Buildings • Classrooms Science Labs • MEDIA CENTER • Computer Labs • CTE Labs Auditorium & Music Spaces • Band • Vocal • Orchestra • Piano Lab Gymnasium • Locker Rooms • Weight Room • Gymnastics/Dance • Wrestling CAFETERIA

9 Building Program Student Capacity: 2,776 Buildings: +/-350,000 Square Feet Campus Program Administration Media Center Cafeteria Classroom Buildings • Classrooms Science Labs • COMPUTER LAB • Computer Labs • CTE Labs Auditorium & Music Spaces • Band • Vocal • Orchestra • Piano Lab Gymnasium • Locker Rooms • Weight Room • Gymnastics/Dance • Wrestling SCIENCE LAB

10 Building Program Student Capacity: 2,776 Buildings: +/-350,000 Square Feet Campus Program Administration Media Center Cafeteria Classroom Buildings • Classrooms Science Labs • AUDITORIUM • Computer Labs • CTE Labs Auditorium & Music Spaces • Band • Vocal • Orchestra • Piano Lab Gymnasium • Locker Rooms • Weight Room • Gymnastics/Dance • Wrestling GYMNASIUM

11 Site Program Site: +/-68 Acres Site Amenities Greenhouse and Shade house Athletics • Field House at Stadium/Track •Locker Rooms •Weight Room •Concessions • Practice Fields GREENHOUSE • Baseball Field • Softball Field • Baseball & Softball Concessions • Tennis Courts • Outdoor Basketball Courts

Cars and Buses Student and Faculty parking (+/-850 Spaces) Parent Drop off / pick up Bus Loop (up to 60 buses) Bus parking (up to 75 buses) STADIUM/TRACK & FIELD

12 Site Program Site: +/-68 Acres Site Amenities Greenhouse and Shade house Athletics • Field House at Stadium/Track •Locker Rooms •Weight Room •Concessions • Practice Fields BASEBALL • Baseball Field • Softball Field • Baseball & Softball Concessions • Tennis Courts • Outdoor Basketball Courts

Cars and Buses Student and Faculty parking (+/-850 Spaces) Parent Drop off / pick up Bus Loop (up to 60 buses) Bus Parking (up to 75 buses) SOFTBALL

13 Site Program Site: +/-68 Acres Site Amenities Greenhouse and Shade house Athletics • Field House at Stadium/Track •Locker Rooms •Weight Room •Concessions • Practice Fields • Baseball Field TENNIS • Softball Field • Baseball & Softball Concessions • Tennis Courts • Outdoor Basketball Courts

Cars and Buses Student and Faculty parking (+/-850 Spaces) Parent Drop off / pick up Bus Loop (up to 60 buses) Bus Parking (up to 75 buses) OUTDOOR BASKETBALL

14 Additional Features Safety & Security SECURE ENTRY POINT • Secure Courtyard Design • Single Secure Entry Point • Security System & Cameras • Card Reader Entrance Controls • Fencing

Educational Technology CLASSROOM TECHNOLOGY • 70” Touch Screen “Smart” Monitors • Audio Enhancement • WiFi Connectivity

Audio Enhancement System 70” Touchscreen

Wireless Access Point

15 Sustainability Building Site • 10% more energy efficient than ASHRAE • Native/low water plants – reduce water 90.1 standard consumption • High Efficiency Chillers (15% energy • Low Impact Design (LID) stormwater design reduction) • Light colored roof to reduce heat gain and improves energy performance • Energy Efficient LED Lighting • Energy Star rated equipment • Water saving toilets, faucets, and fixtures • All classrooms have daylighting • Over 75% of ALL spaces have daylighting • Thermal efficient windows/glazing

16 Planned Schedule

November April April August 2018 2020 2022 2022

Design, Permitting, Bidding New Campus Construction (20 Months) Move-In

17 Questions & Answers