February 6, 2019 30% Design Community Meeting

High School Site 80‐H‐SW‐4

Please sign in on your mobile device: http://communitymeeting.ocps.net/

1 High School Site 80‐H‐SW‐4 Meeting Agenda February 6, 2019, 6:00 PM

• Welcome – School Board Member: Pam Gould • Introductions – Lauren Roth/ Facilities Communications • Project Update – David Torbert, AIA, NCARB • Questions and Answers • Adjournment

2 Site Location DR. PHILLIPS HS

Parkside

Hilton Sand Grand Vacations Lake

ORANGE COUNTY CONVENTION CENTER BEACHLINE

FREEDOM HS Dr. Phillips Community SEAWORLD SITE 80 Park NEW HIGH SCHOOL Villas of S. APOPKA VINELAND ROAD Grand Cypress Jewish Community WINTER GARDEN VINELAND ROAD Center Lake north

Willis STATE ROAD 441 New Lake Connector Ruby

Road S. JOHN YOUNG PARKWAY (By County)

3 Site Aerial

Dr. Phillips Sand Lake Community Park

FENTON ROAD

Jewish Community Center High School Site 80‐H‐W‐4 (+/‐50 Acres) S. APOPKA VINELAND ROAD

New Connector Road (By County)

Park Soleil Lake Willis

north Lake Ruby

4 Site Plan

Retention

Baseball Softball Retention Stadium Track Practice Practice & Field Field Field

Basketball Tennis Shadehouse & Greenhouse Fencing Service Future Expansion

Bus Loop & Staff Parking Student (200 Parking Parking Spaces) 3‐Story New HS Campus (577 Spaces)

Bike Racks FRONT DOOR Parent Drop Visitor Parking Directional Left (105 Spaces) Turn Lane Student Stations = 2,776 Full Median Daryl Carter Parkway Opening 0’ 200’ north Parking = 882 spaces Car Stacking = up to 300 cars On‐site Bus Stacking = 60 buses

5 Project Basis – OCPS Prototype High School

OCPS PROTOTYPE HIGH SCHOOLS Evans High School Windermere High School Oak Ridge High School Evans High School West Orange High School Freedom High School Olympia High School

Oak Ridge High School Wekiva High School

6 Project Basis – OCPS Prototype High School UPGRADES INCLUDED PROTOTYPE Educational Windermere High School Evans High School • 21st Century Collaborative Learning Hubs Technology • Interactive Touchscreen Smart TV’s • WiFi access points throughout Energy Efficiency • LED lighting campus wide (interior, exterior, site and athletic fields) • High efficiency chillers and variable pumping scheme • Low flow plumbing fixtures • Commissioning of MEP systems • ASHRAE 90.1 compliance for lighting and power metering Security • Full security access control and cameras for the school • 2‐way emergency radio system • Voice evacuation fire alarm system • Permanent generator and life safety lighting Oak Ridge High School Wekiva High School 7 Building Program Students: 2,776 Buildings: +/‐350,000 Square Feet Campus Program Administration Media Center Cafeteria Classroom Buildings • Classrooms • Science Labs • Computer Labs MEDIA CENTER • CTE Labs Auditorium & Music Spaces • Band • Vocal • Orchestra • Piano Lab Gymnasium • Locker Rooms • Weight Room • Gymnastics/Dance • Wrestling CAFETERIA

8 Building Program Students: 2,776 Buildings: +/‐350,000 Square Feet Campus Program Administration Media Center Cafeteria Classroom Buildings • Classrooms • Science Labs • Computer Labs COMPUTER LAB • CTE Labs Auditorium & Music Spaces • Band • Vocal • Orchestra • Piano Lab Gymnasium • Locker Rooms • Weight Room • Gymnastics/Dance • Wrestling SCIENCE LAB

9 Building Program Students: 2,776 Buildings: +/‐350,000 Square Feet Campus Program Administration Media Center Cafeteria Classroom Buildings • Classrooms • Science Labs • Computer Labs AUDITORIUM • CTE Labs Auditorium & Music Spaces • Band • Vocal • Orchestra • Piano Lab Gymnasium • Locker Rooms • Weight Room • Gymnastics/Dance • Wrestling GYMNASIUM

10 Site Program Site: +/‐50 Acres Site Amenities Greenhouse and Shade house Athletics • Field House at Stadium/Track •Locker Rooms •Weight Room •Concessions • Practice Fields GREENHOUSE • Baseball Field • Softball Field • Baseball & Softball Concessions • Tennis Courts • Outdoor Basketball Courts

Cars and Buses Student and Faculty parking (+/‐850 Spaces) Parent Drop off / pick up Bus Loop (up to 60 buses) STADIUM/TRACK & FIELD

11 Site Program Site: +/‐50 Acres Site Amenities Greenhouse and Shade house Athletics • Field House at Stadium/Track •Locker Rooms •Weight Room •Concessions • Practice Fields BASEBALL • Baseball Field • Softball Field • Baseball & Softball Concessions • Tennis Courts • Outdoor Basketball Courts

Cars and Buses Student and Faculty parking (+/‐850 Spaces) Parent Drop off / pick up Bus Loop (up to 60 buses) SOFTBALL

12 Site Program Site: +/‐50 Acres Site Amenities Greenhouse and Shade house Athletics • Field House at Stadium/Track •Locker Rooms •Weight Room •Concessions • Practice Fields TENNIS • Baseball Field • Softball Field • Baseball & Softball Concessions • Tennis Courts • Outdoor Basketball Courts

Cars and Buses Student and Faculty parking (+/‐850 Spaces) Parent Drop off / pick up Bus Loop (up to 60 buses) OUTDOOR BASKETBALL

13 Additional Features Safety & Security SECURE ENTRY POINT • Secure Courtyard Design • Single Secure Entry Point • Security System & Cameras • Card Reader Entrance Controls

Educational Technology CLASSROOM TECHNOLOGY • 70” Touch Screen “Smart” Monitors • Audio Enhancement • WiFi Connectivity

Audio Enhancement System 70” Touchscreen

Wireless Access Point

14 Sustainability Building Site • 10% more energy efficient than ASHRAE • Native/low water plants – reduce water 90.1 standard consumption • High Efficiency Chillers (15% energy • Low Impact Design (LID) stormwater design reduction) • Light colored roof to reduce heat gain and improves energy performance • Energy Efficient LED Lighting • Energy Star rated equipment • Water saving toilets, faucets, and fixtures • All classrooms have daylighting • Over 75% of ALL spaces have daylighting • Thermal efficient windows/glazing

15 Planned Schedule

November April April August 2018 2020 2022 2022

Design, Permitting, Bidding New Campus Construction (24 Months) Move-In

16 Questions & Answers