Initial Environmental Examination

Document Stage: Draft Project Number: 42486-016 September 2016

IND: Urban Services Improvement Program – Water Supply Improvement in Athana, Kukdeshwar, Nayagaon, Sarwaniya Maharaj and Nagri

Package No: MPUSIP-3A

Prepared by Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank.

This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Draft Initial Environmental Examination

October 2017

IND: Madhya Pradesh Urban Services Improvement Program –Subproject of Water Supply Improvement in Kukdeshwar, Nayagaon, Sarwaniya Maharaj & Nagri Towns (Package 3A)

Prepared by Project Management Unit, Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank

CURRENCY EQUIVALENTS (as of 1 Dec2015)

Currency unit – Conversion INR1.00 = $.0.015 $1.00 = INR 66.00

Abbreviations

AC – Asbestos Cement ADB – Asian Development Bank ASO – Assistant Safeguards Officer CFE – Consent for Establishment CFO – Consent for Operation CPCB Central Pollution Control Board EA – Executing Agency EAC – Expert Appraisal Committee EC – Environmental Clearance EHS – Environmental Health & Safety EIA – Environmental Impact Assessment EMP – Environmental Management Plan; ESR – Elevated Service Reservoir GOI – Government of GOMP – Government of Madhya Pradesh IA – Implementing Agency IEE – Initial Environmental Examination; NP – Nagar Parishad LPCD – Liters per Capita per Day MLD – Million Liters per Day MOEF – Ministry of Environment and Forest MPPCB – Madhya Pradesh Pollution Control Board MPUDC – Madhya Pradesh Urban Development Company NOC – No Objection Certificate PE – Polyethylene PHED – Public Health Engineering Department PIU – Project Implementation Unit; PMC – Project Management Consultant PMU – Project Management Unit PO – Project Officer PWD – Public Works Department REA – Rapid Environmental Assessment Checklist RoW – Right of Way SEIAA – State Environmental Impact Assessment Authority SPS – Safeguard Policy Statement, 2009 UDED – Urban Development & Environment Department ULB – Urban Local Body WHO – World Health Organization WRD – Water Resources Department WSS – Water Supply Scheme WTP – Water Treatment Plant

3

WEIGHTS AND MEASURES C Degree Celsius km kilometre lpcd litres per capita per day mm milli meter m metre MLD million litres per day mm millimetre Nos Numbers sq.km Square Kilometer

TABLE OF CONTENTS

I. EXECUTIVE SUMMARY ...... 5 II. INTRODUCTION ...... 10 A. Background...... 10 B. Purpose of this IEE Report ...... 11 C. Report Structure ...... 12 III. DESCRIPTION OF THE PROJECT ...... 13 A. Project Area ...... 13 B. Existing Water Supply Situation ...... 13 C. Proposed Project ...... 15 IV. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ...... 33 A. ADB Policy ...... 33 B. National Environmental Laws ...... 33 V. DESCRIPTION OF THE ENVIRONMENT ...... 36 A. Methodology Used for Baseline Study ...... 36 B. Baseline Environmental Profile ...... 36 C. Subproject Site Environmental Features ...... 48 VI. aNTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 57 A. Pre-Construction Impacts – Design & Location ...... 58 B. Construction Impacts ...... 64 C. Operation and Maintenance Impacts ...... 65 D. Project benefits ...... 66 A. Overview ...... 67 B. Public Consultation ...... 67 C. Information Disclosure ...... 68 VII. GRIEVANCE REDRESS MECHANISM ...... 69 A. Project Specific Grievance Redress Mechanism ...... 69 VIII. ENVIRONMENTAL MANAGEMENT PLAN ...... 71 A. Implementation Arrangements ...... 71 B. Environmental Management Plan ...... 71 C. EMP Compliance Responsibilities ...... 90 D. Training Needs ...... 92 Monitoring and Reporting ...... 93 E...... 93 EMP Implementation Cost ...... 94 F...... 94 IX. CONCLUSION AND RECOMMENDATIONS ...... 96

LIST OF TABLES

Table 1: Proposed Water Supply Subproject Components ...... 17 Table 2: Applicable Environmental Regulations ...... 34 Table 3:Table 3: WHO Ambient Air& Noise Quality Guidelines ...... 35 Table 4: Baseline Environmental Features of the Subproject Towns ...... 37 Table 5: Site Environmental Features - Kukdeshwar ...... 48 Table 6: Site Environmental Features - Nayagaon ...... 50 Table 7: Site Environmental Features – Sarvaniya Maharaj ...... 53 Table 8: Site Environmental Features – Nagri ...... 55 Table 9: Water Source Selection & Sustainability ...... 59 Table 10: Design Stage Environmental Management Plan ...... 73 Table 11: Pre-Construction State Environmental Management Plan ...... 75 Table 12: Construction Stage Environmental Management Plan ...... 78 Table 13: Operation Stage Environmental Management Plan ...... 86 Table 14: Construction Stage Environmental Monitoring Plan ...... 87 Table 15: Operation Stage Environmental Monitoring Plan ...... 89 Table 16: Outline Capacity Building Program on EMP Implementation ...... 92 Table 17: Cost Estimates to Implement the EMP ...... 94

LIST OF FIGURES

Figure 1: Subproject location ...... 13 Figure 2: Project locations in Kukdeshwar ...... 20 Figure 3: Key plan of Kukdeshwar WSS ...... 21 22 Figure 4: Cross Section of Gandhi Sagar Dam and intake arrangement for Kukdeshwar Town ...... 23 Figure 5: PROJECT LOCATIONS IN NAYAGAON ...... 24 Figure 6: Base Map of Nayagaon ...... 25 Figure 7: Layout Plan & Section of Intake at CCI Pong in Nayagaon ...... 26 Figure 8: Project locations in sarwaniya maharaj ...... 27 Figure 9: Base Map of Sarwaniya Maharaj ...... 28 Figure 10: Project Locations in Nagri ...... 29 Figure 11: Base Map of Nagri Town ...... 30 Figure 12: Layout Plan & Cross Section of Intake for Nagri ...... 31 Figure 13: Typical WTP Schematic Flow Diagram ...... 32 This map shows WTP schematic flow diagram. WTPs in the remaining 3 towns also has same features...... 32 Figure 14: KUKDESHWAR SUBPROJECT AREA & ENVIRONS ...... 44 Figure 15: Nayagaon Subproject Area & Environs ...... 45 Figure 16: Sarwaniya Maharaj Subproject Area & Environs ...... 46 Figure 17: NAGRI SUBPROJECT AREA & ENVIRONS ...... 47

4

LIST OF APPENDICES APPENDIX 1– REA Checklist……………………………………………………………………98 APPENDIX 2: NATIONAL AMBIENT AIR QUALITY STANDARDS…………………………116 APPENDIX 3: VEHICLE EXHAUST EMISSION NORMS…………………………………….116 APPENDIX 4: NATIONAL AMBIENT AIR QUALITY STANDARDS IN RESPECT OF NOISE………………………………………………………………………………………………116 APPENDIX 5: EXTRACT FROM CONSTRUCTION & DEMOLITION MANAGEMENT RULES, 2016………………………………………………………………………………………………..117 APPENDIX 6: SALIENT FEATURES OF MAJOR LABOR LAWS APPLICABLE TO ESTABLISHMENTS ENGAGED IN CONSTRUCTION OF CIVIL WORKS…………………123 APPENDIX 7: PROVIDE WARD-WISE POPULATION OF SUBPROJECT TOWNS………125 APPENDIX 8: CLIMATIC CHARACTERISTICS OF SUBPROJECT DISTRICTS – AND MANDASAUR………………………………………………………………………………126 APPENDIX 9: SALIENT FEATURE OF GANDHISAGAR DAM……………………………..127 APPENDIX 10: WATER QUALITY RESULTS OF GANDHI SAGAR DAM………………….128 APPENDIX 11A– COMPREHENSIVE SAMPLING AND WATER QUALITY RESULTS OF CCI POND, NAYAGAON…………………………………………………………………………129 APPENDIX 11B– COMPREHENSIVE SAMPLING AND WATER QUALITY PROGRAM FOR CCI POND, NAYAGAON ...... 132 APPENDIX 12– SALIENT FEATURES OF MOREWAN DAM ...... 133 APPENDIX 13- YIELD TEST RESULTS OF OPEN WELL SOURCE OF SARWANIYAMAHARAJ ...... 134 APPENDIX 14 - OPEN WELL (SARWANIYA MAHARAJ) WATER QUALITY RESULTS .. 135 APPENDIX 15– SALIENT FEATURES OF RUPANIYAKHAL DAM ...... 136 APPENDIX 16– WATER QUALITY RESULTS OF RUPANIYAKHAL DAM ...... 137 APPENDIX 17: STAKEHOLDER CONSULTATION ...... 138 APPENDIX 19: SAMPLE OUTLINE SPOILS (CONSTRUCTION WASTE) MANAGEMENT PLAN ...... 153 APPENDIX 20: SAMPLE OUTLINE TRAFFIC MANAGEMENT PLAN ...... 154 APPENDIX 22: DRINKING WATER STANDARDS ...... 161 APPENDIX 23: SAMPLE ENVIRONMENTAL SITE INSPECTION REPORT ...... 163 APPENDIX 24: QUARTERLY REPORTING FORMAT FOR ASSISTANT SAFEGUARDS OFFICER ...... 165

5

I. EXECUTIVE SUMMARY

1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns ➢ Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and ➢ Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening ➢ Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services; ➢ Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and ➢ Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is “effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

4. The Subproject. Subproject covers 4 towns -Kukdeshwar, Nayagaon, and Sarwaniya Maharaj in and Nagri in , in north western part of Madhya Pradesh state bordering state. Subproject town Nayagoan shares borders with Rajasthan state. These are small towns, recently upgraded to Nagar Parishad status, and population as per 2011 census was: Kukdeshwar–11,956; Nayagaon–6,553, Sarwaniya Maharaj–6,737,and Nagri– 7,034. Improvement of water supply in these five towns will be implemented under a single Design-Build-Operate (DBO) contract package.The objective of the subproject is to achieve safe and sustainable water services both in terms of services to customers, cost recovery, providing 100% coverage with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject includes the following civil works. a. Kukdeshwar (i) Submersible Floating Pumps to lift water from Gandhi Sagar Dam (ii) 2.0 MLD WTP (iii) Construction of 400 KL OHT (iv) Construction of 18000 m of

6

raw water and 3450m of clear water feeder mains. Distribution network of 13866 m b. Nayagaon: (i) Submersible Pumps to be installed on Floating Barge / Contoon that will float on the water in CCI Pond (Poundage at Limestone mine) (ii) Water treatment plant of 1.5 mld capacity; (iii) Construction of one new OHT of 200 KL and using of existing 100 KL OHT (iv) 2000 m of raw water and 750m of clear water feeder mains (v) 10225 m of distribution lines proposed in Nayagaon. c. Sarwaniya Maharaj: (i) Submersible Pump sets at well near Moorwan dam (ii) Construction of one new OHT of 250 KL (iii) construction of 1.5 MLD WTP (iv) 8700 m of raw water and 900m of clear water feeder mains. (v) 11847 m of distribution lines proposed in Sarwaniya Maharaj. d. Nagri include (i) Intake well at Rupaniyakhal dam (ii) construction of 1.5 MLD WTP (iii) 9050m of raw water feeder mains and 125 m of clear water feeder mains. (iv) 14012 m of distribution lines proposed in Nagri.

5. Screening and Assessment of Potential Impacts: ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB’s Safeguard Policy Statement (SPS), 2009. As per the GoI EIA Notification, 2006, this subproject do not require EIA study or environmental clearance. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply. Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure.

6. Categorization: Based on results of the assessment and ADB SPS, the subproject is classified as environmental Category B, i.e., the subproject is judged to be unlikely to have significant adverse environmental impacts. An initial environmental examination (IEE) is required to determine whether significant environmental impacts warranting an environmental impact assessment are likely.

7. This IEE aims to (i) provide critical facts, significant findings, and recommended actions; (ii) present the national and local legal and institutional framework within which the environmental assessment has been carried out; (iii) provide information on existing geographic, ecological, social and temporal context including associated facilities within the subproject’s area of influence; (iv) assess the subproject’s likely positive and negative direct and indirect impacts to physical, biological, socioeconomic, and physical cultural resources in the subproject’s area of influence; (v) identify mitigation measures and any residual negative impacts that cannot be mitigated; (vi) describe the process undertaken during project design to engage stakeholders and the planned information disclosure measures and the process for carrying out consultation with affected people and facilitating their participation during project implementation; (vii) describe the subproject’s grievance redress mechanism for resolving complaints about environmental performance; (viii) present the set of mitigation measures to be undertaken to avoid, reduce, mitigate, or compensate for adverse environmental impacts; (ix) to describe the monitoring measures and reporting procedures to ensure early detection of conditions that necessitate particular mitigation measures; and (x) identify indicative costs and who is responsible for carrying out the mitigation and monitoring measures.

8. Description of the Environment: The subproject components locations are in subproject towns of Kukdeshwar, Nayagaon, Sarwaniya Maharaj, Nagriand their surroundings. In all the towns water sources are located outside the towns (~5 to 20 km) and intakes will be constructed at or near the sources on a government owned land, and intake pipes will be laid into the sources to draw water. WTPs will be constructed on government owned land parcels either within or close to the towns. Most of these facilities are surrounded

by agricultural lands. Raw water pipes from source to WTPs will be laid along the existing roads. None of the components are located in or near any sensitive lands like forests. Rest of the components – water tanks, distribution lines, connections etc., will be located within the towns/urban areas. The raw water transmission pipes, connecting intake and WTP, will be essentially outside the town, and clear water transmission pipes, from WTP to distribution reservoirs, will be partly outside and partly within the towns. Project area experience a subtropical climate, typical to north India, hot summers, cold and dry winters and monsoon rains. While there is no natural habitat left within the town areas, the areas near the sources are converted mostly into agricultural. A forest area is located near the source at Sarwaniya Maharaj, however, no encroachment/damage to forest envisaged due to project. There are no protected areas, like wildlife sanctuaries, national parks, nor there are any historically, archeologically protected areas in the vicinity. Towns are densely populated in the core/old town areas with narrow lanes, and small and closely built houses, while most of the areas are undeveloped and are still under agricultural use. Commercial areas are along the main roads, which are mostly congested with activities, pedestrians and traffic.

9. Potential Environmental Impacts: The subproject is unlikely to cause significant adverse impacts because: (i) relatively small scale as the population and water demand is minimal, (ii) the components will involve straightforward construction and operation, so impacts will be mainly localized; and (iii) predicted impacts are site-specific and likely to be associated with the construction process and are produced because the process is invasive, involving excavation and earth movements.

10. Environmental impacts as being due to the project design or location are not significant. The proposed water supply schemes include design of new water sources for two towns (Kukdeshwar and Nagri), and continuation of existing sources in the remaining 2 towns (Sarwaniya Maharaj and Nayagaon). Source analysis conducted on these sources confirmed that source is sustainable, and there are unlikely to have any adverse impacts on environment or existing uses and unlikely to create social conflicts. Yield tests are conducted on open wells at downstream of Morwan Dam for Sarwaniya Maharaj, and confirmed that water is adequate to meet the demand. Water will be sourced from existing dams (Gandhisagar Dam for Kukdeshwar and Rupaniyakhal Dam for Nagri), which have comparatively large storage, and necessary water allocation will be obtained from the Water Resources Department. In Nayagaon, existing source – an abandoned lime stone quarry pond of a Cement Plant, which in use for many years, will be continued. Random water quality test conducted during the project preparation indicated that the water quality is suitable for domestic supply after conventional treatment. However, considering the nature and location of source within a cement factory compound receiving runoff also from the factory areas, a comprehensive water quality testing program is suggested in the IEE to confirm the quality, and it will be conducted prior to the start of work.

11. During construction, potential negative impacts mainly arise from disturbance of residents, businesses, increase in traffic, increase in noise level and dusts, and the need to dispose moderate quantities of waste soil during construction phase and generation of sludge from the WTP during operation and maintenance phase. However, there are well-developed methods for mitigation, minimization to acceptable levels. Operation phase impacts are likely to be insignificant.

12. Environmental Management Plan: An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels. Locations and siting of the proposed infrastructures were considered to further reduce impacts. These include (i) locating facilities on government-owned land to avoid the need for land acquisition and relocation of people; and (ii) laying of pipes in RoW alongside main/access roads, to reduce acquisition of land and impacts on livelihoods specifically in densely populated areas of the town.

8

13. The EMP includes design measures such as (i) wash water recovery for the WTP to reduce effluent to be discharged and safe sludge disposal (ii) energy efficient pumping equipment and (iii) quick leak detection and rectification to save the resources, etc. During construction, the EMP includes mitigation measures such as (iv) implementation of traffic management plan in coordination with local traffic police to minimize traffic impacts; (v) awareness campaigns and consultations to inform residents and businesses of potential disturbances; (vi) provision of walkways and planks over trenches to ensure access will not be impeded; (vii) use of noise-dampening measures in areas with sensitive receptors such as hospitals, schools, places of worships and other silence-zones; (viii) use of dust-suppression methods such as watering and/or covering of stockpiles; and (ix) finding beneficial use of excavated materials to extent possible to reduce the quantity that will be disposed off. As for the O&M phase, facilities will need to be repaired from time to time, but environmental impacts will be much less than those of the construction period as the work will be infrequent, affecting small areas only. The design of the WTP includes dewatering and drying areas as part of sludge management. The EMP includes mitigation measures and monitoring plan to ensure compliance to environmental standards during O&M phase.

14. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between Madhya Pradesh Urban Development Company (MPUDC), project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

15. The contractor will be required to submit to PMU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

16. Consultation, Disclosure and Grievance Redress Mechanism: The stakeholders were involved in developing the IEE through discussions on-site and public consultation at several places in the town, after which views expressed were incorporated into the IEE and in the planning and development of the project. The IEE will be made available at public locations and will be disclosed to a wider audience via the ADB, MPUDC and PMU websites. The consultation process will be continued and expanded during project implementation to ensure that stakeholders are fully engaged in the project and have the opportunity to participate in its development and implementation. A grievance redress mechanism is described within the IEE to ensure any public grievances are addressed quickly.

17. Implementation Arrangements: Urban Development and Environment Department (UDED) of Government of Madhya Pradesh is the Executing Agency and Madhya Pradesh Urban Development Company (MPUDC) is the Implementing Agency. Project Management

Unit (PMU) attached to MPUDC is responsible for implementation, and will be supported by Program Implementation Units (PIUs). Several teams of Design Consultants, and a Program Management Consultant (PMC), will support PMU & PIUs. Infrastructure will be designed, built, and operated by DBO contractor for 10 years, after which it will be transferred to ULBs. Project Officer (Environment) at PMU and Assistant Safeguard Officer (ASO) at each of the PIU will be responsible for environment safeguards tasks, and will be supported by PMC. Contractor personnel will include an Environment, Health and Safety (EHS) supervisor.

18. Monitoring and Reporting: The PMU and PMC will be responsible for monitoring. The PMC will submit quarterly and semi-annual monitoring reports to PMU, and the PMU will review and send the semi-annual monitoring reports to ADB. ADB will post the environmental monitoring reports on its website.

19. Conclusions and Recommendations: The subproject is therefore unlikely to cause significant adverse impacts. The potential impacts that are associated with design, construction and operation can be mitigated to standard levels without difficulty through proper engineering design and the incorporation or application of recommended mitigation measures and procedures. Based on the findings of the IEE, there are no significant impacts and the classification of the project as Category “B” is confirmed. No further special study or detailed environmental impact assessment (EIA) needs to be undertaken to comply with ADB SPS (2009) or GoI EIA Notification (2006). Project will require permission of (i) Water Resources Department (WRD) for water abstraction of water for Kukdeshwar, Nagri and Sarwaniya Maharaj, and from Cement Corporation of India (CCI) for Nayagaon water source, and (ii) consent of Madhya Pradesh Pollution Control Board (MPPCB) for WTPs. These permissions/approvals shall be obtained prior to award of contracts.

20. Comprehensive water quality tests will be conducted for Nayagaon CCI source to confirm the water quality. This IEE will be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

10

II. INTRODUCTION

A. Background

1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns ➢ Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and ➢ Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening ➢ Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services; ➢ Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and ➢ Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is “effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

(i) Access to piped water supply coverage increased to 95% of the households from 33% in 2015 in 64 towns; (ii) Women's drudgery for fetching water reduced by 80% (from spending an average of 55 minutes in 2015 to 10 minutes); (iii) Coverage of households with access to improved sanitation systems increased to 80% from 30% in 2015; (iv) Wastewater collection and/or safe sanitation service coverage increased to at least 80% of the households from 0% in 2015 in two towns; (v) Incidence of water logging/flooding reduced to two incidents per annum in four towns; and (vi) Women access to functioning sanitation systems increased to 95% from 25% in 2015 (in poor settlements) in four towns

4. The key outputs envisaged from the project are:

(i) Output 1: Water supply infrastructure improved in 64 project towns and flood and sanitation infrastructure improved in two project towns with the following measurable indicators: ➢ Improved water supply capacity of 186ml/day installed in 64 towns; ➢ 4,000 km water supply networks installed in 64 towns; ➢ 350,000 households provided with metered house connections including 100 government schools; ➢ 8 MLD sewage or septage treatment plants constructed; and ➢ Installation of 120 km sewer and drainage mains and networks.

(ii) Output 2: Sustained urban infrastructure operation and management

➢ 23 performance-based contract (PBC) operation and maintenance (O&M) water supply contracts for 64 ULBs signed and operated; ➢ ULBs institute volumetric water charges for recovery of water service O&M costs ➢ ULBs’ water tariff collection ratio improved to 90% from 50% in 2014 based on the water meters’ readings ➢ 100% operating cost recovery (excluding debt service) achieved; ➢ GIS system established for effective O&M of water services

5. The subproject towns of Kukdeshwar, Nayagaon, Sarwaniya Maharaj and Nagri are located in the northwestern part of Madhya Pradesh state, and improvement of water supply in these five towns is one of the subprojects proposed under MPUSIP. The objective of the subproject is to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The subproject envisages providing 100% coverage of population with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject includes civil works (stop dams, intake, WTP, raw and clear water transmission, storage tanks, distribution network, consumer connections and flow meters), project implementation and management, and non- physical investments. A detailed description of the components is provided in Section III.

B. Purpose of this IEE Report

6. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB’s Safeguard Policy Statement (SPS), 2009. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply (Appendix 1). Then potential negative impacts were identified in relation to pre- construction, construction and operation of the improved infrastructure, and results of the assessment show that the subproject is unlikely to cause significant adverse impacts. Thus, this initial environmental examination (IEE) has been prepared in accordance with ADB SPS’s requirements for environment category B projects.

7. This IEE is based on the detailed engineering report prepared by the Design Consultant team and will be finalized during implementation stage by DBO contractor to reflect any changes and latest subproject designs. The IEE was based mainly on field reconnaissance surveys and secondary sources of information. No field monitoring (environmental) survey was conducted however, the environmental monitoring program developed as part of the environmental management plan (EMP) will require the contractors to establish the baseline environmental conditions prior to commencement of civil works. The

12 results will be reported as part of the environmental monitoring report and will be the basis to ensure no degradation will happen during subproject implementation. Stakeholder consultation was an integral part of the IEE.

C. Report Structure

8. This Report contains the following nine (9) sections: (i) Executive summary; (ii) Introduction (iii) Description of the project (iv) Policy, legal and administrative framework (v) Description of the environment; (vi) Anticipated environmental impacts and mitigation measures; (vii) Public consultation and information disclosure; (viii) Grievance redress mechanism; (ix) Environmental management plan, and, (x) Conclusion and recommendation.

III. DESCRIPTION OF THE PROJECT

A. Project Area

9. Project area comprises the urban areas and surroundings of Kukdeshwar, Nayagaon, and Sarwaniya Maharaj in Neemuch District and Nagri in Mandsaur District in region in western part of Madhya Pradesh state. Towns are located at about 15-30 km the respective district headquarters. These towns are located about 400 km northwest of from state capital Bhopal and are well connected by highways and railways. Nearest airport is at , about 250 km (Figure 1).

10. Subproject components are located within the urban areas and surroundings. While water sources, intakes and WTPs are located outside the towns, all other components are located within the towns.

Figure 1: Subproject location

B. Existing Water Supply Situation

1. Kukdeshwar

11. Kukdeshwar is located on State highway 31A, about 40 km east of district headquarter Neemuch. The area of the town 2.59 sq. Km. and population as per 2011 census is 11,956.

12. Present water supply of the Kukdeshwar town is mostly depend on ground water i.e. on 3 tube wells, 38 nos. of hand pumps and 2 open wells. Water from the tube wells and open wells are pumped to two OHT’s. Total 75 Hp (15 Hp on each tube well and 15 Hp on each open well) capacity pumps are installed at 3 tube wells and 2 open wells. Both the OHT’s are filled only once in a day. It takes approximately 8 hours to fill the 169 KL OHT and

14 approximately 6 - 7 hours to fill 150 KL OHT. Then the water is distributed with the help of 7 km of distribution system having PVC pipes from 65 to 100 mm diameter and ACP pipes having diameter 80 mm to 150 mm laid in the town. Thus the total water supplied to the Kukdeshwar town at present is 3.2 LacsLitres i.e. 27 LPCD.

13. In year 1991 group water supply scheme was partially executed by Public Health Engineering Department. Proposed source was Gandhi Sagar Dam. Under this scheme 0.5 MLD WTP was constructed in Rampur town and 300 mm CI Pipeline was laid down for some distance. Since the scheme was not completed, Nagar ParishadKukdeshwar has handed over 0.5 MLD WTP to Rampura town. The present condition of WTP is not in working condition.

14. Present water supply arrangements are not adequate and ground water source level is depleting day by day, therefore water scarcity conditions are arising. Water supply losses during transmission are also very high i.e. more than 40%, that leads to a high energy consumption and loss of ULB. Therefore, new water supply scheme is proposed to be implemented for population of 17,500 souls for a year 2048 (Ultimate Year of Design) considering water supply at the rate 70 LPCD and source as surface source to ensure adequate quantity, quality and desired pressure at doorstep of each household.

2. Nayagaon

15. Nayagaon is on the border of the Neemuch District and Chittorgarh District of Rajasthan. It is located along NH (national highway) 79, about 16 km northwest of Neemuch. Nayagaon and surroundings are famous for limestone mines and is home for some of the well- known cement industries in India. The total area of the town is 14.83 sq.km and total population as per 2011 census is 6553.

16. At present water supply source is water storage at CCI limestone mine for catering water supply to the town which comprises of two 8-HP motor. Water from Pondage is pumped to 2 OHTs having capacity 100 KL each. Then water supply distribution system is laid of diameters 90 / 100 / 160 mm PVC pipes. Total 5.0 km water supply distribution system is laid in the Nayagaon town. Thus, total water supply to the Nayagaon town maid is 0.35 MLD i.e. 53 LPCD, which is far below the guidelines of MPUSIP as 70 LPCD. As 100 KL tank at Nagar Parishad is constructed in the year of 2000, covering ward no 1,9,10,11,12,14 and 15.

17. Present water supply arrangements are not adequate and ground water source level is depleting day by day, therefore water scarcity conditions are arising. Water supply losses during transmission are also very high approximately 40%, that leads to a high energy consumption and loss of ULB. Therefore, new water supply scheme is proposed to be implemented for population of 11,200 souls for a year 2048 (Ultimate Year of Design) considering water supply at the rate 70 LPCD and source as surface source to ensure adequate quantity, quality and desired pressure at doorstep of each household

3. Sarwaniya Maharaj

18. Sarwaniya Maharaj town is located about 16 km northeast of district head quarter, Neemuch. Town is connected by Neemch – Ratangard Road.The total area of the town is 3sqkm and total population as per 2011 census is 6,737.

19. At present water supply source is Ground Water as well as surface water for catering water supply to the town which comprises of 1 working tube wells, 12 hand pumps (8 working) and 3 open wells. Major water supply of the town is done by open wells. One of the open well is situated near Morwan Dam Water from this well is pumped to Town. Around 9Km of pumping is done. Water from all these sources is pumped to 2 OHTs having capacity 100 KL and 50 KL. Then water supply distribution system is laid of diameters 90 / 100 mm PVC pipes and

100/ 150 mm ACP Pipes. Thus total water supply to the Sarwaniya Maharaj town maid is 0.40 MLD i.e. 50 LPCD, which is below the guidelines laid by MPUSIP for supplying water to smaller towns @ 70lpcd.

20. The 2 OHTs in the town, which are constructed in the year 1979 (50KL tank) and 2005 (100KL tank). Out of these two tanks only one tank of capacity 100KL is proposed to be used in the new scheme with some renovation. Present water source is not sufficient to meet the water demand of the town therefore new water supply scheme is needs to be implemented for population for the of 13,800 souls for a year 2048 (Ultimate Year of Design) considering 70 LPCD water supply and source as surface source to ensure adequate quantity, quality and desired pressure at doorstep of each household.

4. Nagri

21. Nagri is one of the oldest municipalities and a tehsil headquarter in Mandsaur District. It is located at a distance of 25 km south of Mandsaur city, and on a road 4 km off of NH 79. The total area of the town is 4 sqkm and population as per 2011 census is 7,034.

22. At present water supply source is Ground Water Source catering water supply to the town which comprises of 3 working tube wells, 12 hand pumps and 2 open wells. Water from all these ground water is pumped to 2 OHTs having capacity 100 KL and 450 KL. Then water supply distribution system is laid of diameters 90 / 100 / 160 mm PVC pipes and 100/ 150mm ACP Pipes. Total 7 Km water supply distribution system is laid in the Nagri town. Thus, total water supply to the Nagri town maid is 0.15 MLD i.e. 21 LPCD, which is far below the service level benchmarking of 135 LPCD.

23. The OHT of 450 KL capacity is constructed in the year of 2010, covering ward no 14 & 15. It is proposed to use this in new scheme with some reconditioning and renovation. Present water supply arrangements are not adequate and ground water source level is depleting day by day, therefore water scarcity conditions are arising. Water supply losses during transmission are also very high approximately 40%, that leads to a high energy consumption and loss of ULB. Therefore, new water supply scheme is needs to be implemented for population for the of 12,000 souls for a year 2048 (Ultimate Year of Design) considering 70 LPCD water supply and source as surface source to ensure adequate quantity, quality and desired pressure at door step of each household.

24. Overall, the current water supply systems in all the fivetowns face similar issues predominantly resulting from receding groundwater sources, low coverage and unreliable supply, inadequate infrastructure and heavy water losses. There is no treatment facility, and the water is supplied without any treatment.

C. Proposed Project

25. As part of this project, it is proposed to develop comprehensive water supply schemes in each of the five project towns. Proposals include new/improved water sources and/or intakes, treatment facilities, storage reservoirs, pumping, transmission and distribution infrastructure. Project will also provide consumer connections with flow meters. Bulk flow meters are proposed at strategic locations to monitor the system performance efficiency.

26. Following Table 1 shows the proposed water supply systems along with nature and size of components in four subproject towns. Figure 2 to Figure 13 show the proposed water systems, component layouts etc.

27. Project benefits. The subproject aims to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water

16 resources. The subproject will provide continuous, pressurized and safe drinking water services to entire population of the towns (100% coverage). Besides achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency, the subproject will improve the overall environmental quality of the town. It will reduce the reduced time and costs of households in accessing alternative sources of water, and will lead to better public health particularly reduction in waterborne and infectious diseases.

17

Table 1: Proposed Water Supply Subproject Components Particulars Kukdeshwar Nayagaon SarwaniyaMaharaj Nagri I. Water demand 1 Base year 1.2 MLD 0.70 MLD 0.70 MLD 0.8 MLD (2018) 2 Intermediate 1.4 MLD 0.90 MLD 1.00 MLD 0.9 MLD year (2033) 3 Design year 1.6 MLD 1.10 MLD 1.30 MLD 1.1 MLD (2048) II. Source 1 Alternatives 1. Danderi River 2. Jannod 1. Stop dam constructed 1. Existing source - open 1. Existing groundwater River & 3. Gandhi Sagar by CCI across Gambhiri well on the downstream source & 2. Dam River& 2. Existing side (d/s) of Morwan Rupaniyakhal Dam source (CCI abandoned Dam lime stone quarry/ mine) 2 Selected Gandhi Sagar Dam Existing source - CCI Existing source - open Rupaniyakhal Dam source abandoned lime stone well on the d/s of quarry pond Morwan Dam

This is one of major dams in It is located in the It is located at about 8 It is located at about 8 Madhya Pradesh, and is southern side of the town km northeast of town, km southern direction of constructed across in the CCI factory and on the d/s of town . It is about campus, which is now Morwan dam across 16 km east of Kukdeshwar abandoned. Gambiri River. Well is Town. This falls within the located in land owned by Nayagaon municipal Nagar Parishad. area. III. Proposed system 1 From source Raw water abstraction from Raw water abstraction Raw water abstraction Raw water abstraction to consumer Gandhi Sagar Dam → raw from CCI pond → raw from Open well → raw from Rupaniyakhal Dam supply water transmission water transmission water transmission → raw water (pumping)→ treatment → (pumping) → treatment (pumping) → treatment transmission (pumping) clear water transmission → → clear water → clear water → treatment → clear storage → distribution → transmission (pumping) transmission (pumping) water transmission → house connections & meters → storage → distribution → storage → distribution storage → distribution → → connections & meters → house connections house connections

18

Particulars Kukdeshwar Nayagaon SarwaniyaMaharaj Nagri with meters &meters

1 Water intake Water will be lifted from Water will be lifted from Water will be extracted Intake well (5 m diameter Gandhi Sagar Dam with the CCI pond using from the existing open & 15 m depth) will be help of submersible Floating submersible pumps with well, no new civil works constructed in the dam,. Pumps mounted on a a Floating Barrage proposed. Including an access Floating Platform in the arrangement bridge (100 m long & 3m dam. wide), and approach road (300 m & 3m wide). Land owned by government (WRD). 2 Raw water Pump house (10 m x 10 m) Raw water pump house Pump house near the Pump house will be pumping in the existing Rampura near CCI Pond open well above the intake well station WTP campus Submersible Floating Submersible pump sets - Vertical turbine pumps-2 Submersible Floating Pump Pump sets -2 nos. 2 nos. (discharge12 nos. (discharge11 LPS, sets -2 nos. (discharge16.92 (discharge10.87 LPS, LPS, head 43 m, and head 71 m, and Motor 20 LPS, head 30 m, and Motor head 33 m, and Motor 10 Motor 12.50 HP) HP) 70 HP) HP) Land owned by GoMP Land owned by Nagar Land owned by (WRD) Land owned by CCI (a Parishad government (WRD) GoI company) 3 Raw water 19.5 km length - 200 mm dia 2 km length - 150 mm 8.7 km length - 200 mm 9050 m length -150 mm transmission DI pipe dia DI pipe dia DI pipe dia DI pipe From raw water pump house From raw water pump Raw water pipe will be Raw water pipe will be to the WTP site at xxxx house to WTP site along Neemuch – along Nagri road to WTP village; the pipe will be laid (alignment in the land Ratangarh Road within site within the Row. along Rampura – owned by CCI and the RoW. Kukdeshwar Road (SH31A) partially along a road within RoW. within the RoW) 4 WTP Capacity:2.0 MLD Capacity: 1.5 MLD Capacity: 1.5 MLD Capacity: 1.5 MLD

Location: On a government Location: On a Location: On a Location: On a owned vacant land (0.65 government owned land government owned government owned ha) at on Rampura Road in land (3.01 ha), in ward 8 vacant land (0.67 ha) vacant land (3.78 ha) in Phoolpura Village village along NH 79 in the town near secondary school Nagri town

Particulars Kukdeshwar Nayagaon SarwaniyaMaharaj Nagri within the town 5 Clear water Pump house within WTP. Pump house within Pump house within Pump house within pumping Centrifugal pumps -4 no,s (3 WTP. WTP. WTP. station HP each) Centrifugal pumps (2 Centrifugal pumps –(3 Centrifugal pumps –(2 no,s - 3HP, 2 no.s–8 no,s - 10 HP) no,s - 7.5 HP) HP) 5 Reservoirs / 1 no. of clear water sump at 1 - Clear water sump at 1 - Clear water sump at Nil tanks WTP (38 KL) WTP (38KL) WTP (38 KL) Overhead tank – 1 No. 1 - OHT (200 kL), on a 1 - OHT (250 kL) near Capacity: 400 KL ULB owned land near WTP at secondary Nayagaon Nagar school; government Location: 1 existing 150 KL Parishad Office owned land. at ward-15 and one proposed at ward-8. 6 Clear water 1.66 km – 100 to 150 mm dia 1.06 km – 100 mm dia DI 0.9 km – 150 mm dia DI 125 m – 150 mm dia DI transmission DI pipe pipe pipe pipe From the clear water sump From the clear water From the clear water From the clear water (at WTP) to service sump (at WTP) to sump (at WTP) to sump (at WTP) to reservoirs service reservoirs service reservoirs service reservoirs Location: along the public Location: along the Location: along a public Location: along a public roads within RoW public roads within RoW road within the RoW road within the RoW 7 Distribution 13.866 km -100 mm HDPE 17.29 km – 90 mm to 11.85 km – 110 mm to 14 km – 75 mm to 110 network Location: Along the public 100 mm HDPE 180 mm HDPE mm HDPE roads in the entire town. Location: Along the Location: Along the Location: Along the public roads in the entire public roads in the entire public roads in the entire town. town. town. 8 Bulk flow Nil Nil Nil Nil meters 9 Consumer 2646 no,s – at each house in 940 no,s – at each house 1292 no,s – at each 1522 no,s – at each connects the town in the town house in the town house in the town with meters

20

Figure 2: Project locations in Kukdeshwar

Figure 3: KEY PLAN OF KUKDESHWAR WSS

22

23

Figure 4: Cross Section of Gandhi Sagar Dam and intake arrangement for Kukdeshwar Town

24

Figure 5: PROJECT LOCATIONS IN NAYAGAON

25

Figure 6: Base Map of Nayagaon

26

Figure 7: Layout Plan & Section of Intake at CCI Pong in Nayagaon

27

Figure 8: PROJECT LOCATIONS IN SARWANIYA MAHARAJ

28

Figure 9: Base Map of Sarwaniya Maharaj

29

Figure 10: Project Locations in Nagri

30

Figure 11: Base Map of Nagri Town

Figure 12: Layout Plan & Cross Section of Intake for Nagri

32

Figure 13: Typical WTP Schematic Flow Diagram

THIS MAP SHOWS WTP SCHEMATIC FLOW DIAGRAM. WTPS IN THE REMAINING 3 TOWNS ALSO HAS SAME FEATURES.

33

IV. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

A. ADB Policy

28. ADB requires the consideration of environmental issues in all aspects of ADB’s operations, and the requirements for environmental assessment are described in ADB SPS, 2009. This states that ADB requires environmental assessment of all ADB investments.

29. Screening and categorization. The nature of the environmental assessment required for a project depends on the significance of its environmental impacts, which are related to the type and location of the project; the sensitivity, scale, nature, and magnitude of its potential impacts; and the availability of cost-effective mitigation measures. Projects are screened for their expected environmental impacts, and are assigned to one of the following four categories:

(i) Category A. Projects could have significant adverse environmental impacts. An EIA is required to address significant impacts. (ii) Category B. Projects could have some adverse environmental impacts, but of lesser degree or significance than those in category A. An IEE is required to determine whether significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report. (iii) Category C. Projects are unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are reviewed. (iv) Category FI. Projects involve a credit line through a financial intermediary or an equity investment in a financial intermediary. The financial intermediary must apply an environmental management system, unless all projects will result in insignificant impacts.

30. Environmental management plan. An EMP, which addresses the potential impacts and risks identified by the environmental assessment, shall be prepared. The level of detail and complexity of the EMP and the priority of the identified measures and actions will be commensurate with the project’s impact and risks.

31. Public disclosure. ADB will post the safeguard documents on its website as well as disclose relevant information in accessible manner in local communities:

(i) for environmental category A projects, draft EIA report at least 120 days before Board consideration; (ii) final or updated EIA and/or IEE upon receipt; and (iii) environmental monitoring reports submitted by the implementing agency during project implementation upon receipt.

B. National Environmental Laws

32. Environmental Assessment: The GoI EIA Notification of 2006 (replacing the EIA Notification of 1994), sets out the requirement for Environmental Assessment in India. This states that Environmental Clearance (EC) is required for specified activities/projects, and EC must be obtained before any construction work or land preparation (except land acquisition) may commence. Projects are categorized as A or B1 or B2 depending on the scale of the project and the nature of its impacts. None of the components of this water supply subproject falls under the ambit of the EIA Notification 2006, and, therefore no category assigned, and thus no EIA study and EC required for the subproject.

34

33. Applicable Environmental Regulations: Besides EIA Notification 2006, there are various other acts, rules, policies and regulations currently in force in India that deal with environmental issues that could apply to infrastructure development. The specific regulatory compliance requirements of the subproject are shown in Table 2.

Table 2: Applicable Environmental Regulations Law Description Requirement Madhya Pradesh Prepared in accordance with the National Water Permission of WRD, State Water Policy, it states that “for environmental balance, GoMP: Policy, 2003 skillful and planned management of all types of • Water allocation / developmental activities, economic use on abstraction from equitable basis and in view of the prime importance Gandhi Sagar Dam for of water for all human and other living beings, an Kukdeshwar; from effective and sound water policy is necessary”. Rupaniyakal Dam for Policy is detailed in 17 sections dealing with Nagri and from open different aspects of water resources. No. 7 deals well below Morwan with Water Allocation Priorities, and according to dam for Sarwaniya which drinking water supply shall have the highest Maharaj priority followed by irrigation, power, tourism, etc. Water Resource Department is nodal department for permitting different uses of water resources. Policy also states that “clear provision for reservation of drinking water shall be made in irrigation projects” Water (Prevention Act was enacted to provide for the prevention and WTPs require CTE (prior and Control of control of water pollution and the maintaining or to start of constriction) and Pollution) Act of restoring of wholesomeness of water, by Central CFO (prior to start of 1974, Rules of and State Pollution Control Boards and for operation) from MPPCB. 1975, and conferring and assigning to CPCB/SPCBs powers amendments &functions relating to water pollution control. Application has to be submitted online at Control of water pollution is achieved through http://www.mppcb.nic.in/x administering conditions imposed in consent gn.html issued under to this Act. These conditions regulate the quantity and quantity of effluent, the location of discharge and the frequency of monitoring of effluents. Any component of the subproject having the potential to generate sewage or trade effluent will come under its purview. Such projects have to obtain Consent to Establish (CTE) & Consent to Operate (CTO) under Section 25 from Madhya Pradesh Pollution Control Board (MPPCB) Environment Emissions and discharges from the facilities to be Appendix 2 provides (Protection) Act, created or refurbished or augmented shall comply applicable standards for 1986 and CPCB with the notified standards ambient air quality. Environmental Appendix 3 provides Standards. vehicular emission norms Noise Pollution Rule 3 of the Act specifies ambient air quality Appendix 4 provides (Regulation and standards in respect of noise for different applicable noise Control) Rules, areas/zones. standards. 2000 amended up to 2010. Municipal Solid Rules to manage municipal solid waste generated; Solid waste generated at Wastes provides rules for segregation, storage, collection, proposed facilities shall be Management processing and disposal. managed and disposed in Rules, 2016 accordance with the MSWM Rules

Law Description Requirement Construction & Rules to manage construction & to waste resulting Construction & demolition Demolition Waste from construction, remodeling, repair and waste generated from the Management demolition of any civil structure. Rules define C&D project construction shall Rules, 2016 waste as waste comprising of building materials, be managed and disposed debris resulting from construction, re-modeling, as per the rules repair and demolition of any civil structure. (Appendix 5) Labor Laws The contractor shall not make employment Appendix 6 provides decisions based upon personal characteristics applicable labor laws unrelated to job requirements. The contractor shall including amendments base the employment relationship upon equal issued from time to time opportunity and fair treatment, and shall not applicable to discriminate with respect to aspects of the establishments engaged employment relationship, including recruitment and in construction of civil hiring, compensation (including wages and works. benefits), working conditions and terms of employment or retirement, and discipline. The contractor shall provide equal wages and benefits to men and women for work of equal value or type.

34. ADB SPS Requirements. During the design, construction, and operation of the project the PMU and PIUs are required to apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety Guidelines. These standards contain performance levels and measures that are normally acceptable and applicable to projects. When regulations differ from these levels and measures, the PMU and PIUs will achieve whichever is more stringent. If less stringent levels or measures are appropriate in view of specific project circumstances, the PMU and PIUs will provide full and detailed justification for any proposed alternatives that are consistent with the requirements presented in ADB SPS. International acceptable air and noise quality guidelines are provided below:

Table 3:Table 3: WHO Ambient Air& Noise Quality Guidelines

36

V. DESCRIPTION OF THE ENVIRONMENT

A. Methodology Used for Baseline Study

35. Data collection and stakeholder consultations. Data for this study has been primarily collected through literature survey, discussion with stakeholder agencies, and field visits to the proposed subproject sites.

36. The literature survey broadly covered the following:

(i) Project details, reports, maps, and other documents prepared by technical experts of design consultant team (ii) Discussions with technical experts, municipal authorities, relevant government agencies like WRD, Forest Department, MPPCB, etc. (iii) Secondary data from previous project reports & published articles, if any, and (iv) Literature on land use, soil, geology, hydrology, climate, socioeconomic, and planning documents collected from Government agencies and websites.

37. Ocular inspection. Several visits to the project sites were made during IEE preparation period in 2016 to assess the existing environment (physical, biological, and socioeconomic) and gather information with regard to the proposed sites and scale of the proposed project. A separate socioeconomic study was conducted to determine the demographic information, existing service levels, stakeholder needs and priorities.

B. Baseline Environmental Profile

38. Following Table 4, presents the baseline environmental profile of subproject towns of Kukdeshwar, Nayagaon, Sarwaniya Maharaj and Nagri. It is organized in terms of physical, ecological, economical, and socio cultural resources. Relevant data tables, further information, if any, is provided in appendices (Appendix 7 to 19) for further reference.

37

Table 4: Baseline Environmental Features of the Subproject Towns Baseline Kukdeshwar Nayagaon SarwaniyaMaharaj Nagri characteristics Location Kukdeshwar is located at 24028'38'' N Nayagaon is located at 230 33’ N SarwaniyaMaharaj is located at Nagri is located at Latitude and 75016'13" E Longitude, at Latitude and 740 46’ ELongitude, at 230 0’23”’ N Latitude and780 23050’ 52”’ N Latitude an elevation of 434m above the MSL ), an elevation of 460 m above the 13’48” ELongitude, at an and75006’10” in Neemuch District in western MP. It MSL, in Neemuch District in elevation of 480 m above the ELongitude, at an is located at about 400 km northwest western MP. It is located at about MSL, in Neemuch District in elevation of 480 m of state capital, Bhopal. 410 km northwest of state capital, western MP. It is located at above the MSL, in Bhopal. about 470km northwest of state Mandasaur District in capital, Bhopal western MP. It is located at about 320 km northwest of state capital, Bhopal Connectivity Kukdeshwar is located on the state Nayagaon is located at the state SarawaniyaMaharaj is located at Nagri is located off 4 km highway 31A and is well connected border with Rajasthan. NH 79 about 16 km Neemuch, and is of NH79. It is located at with surrounding villages and towns, passes through the town and located on the Neemuch- 25 km from Mandasaur. and the state Capital Bhopal. Udaipur provides good connectivity in MP Ratangarh Road. Nearest It is well connected wih, and Indore are the nearest airports and as well as in the neighboring railway stations is at Neemuch. and nearest railway (150 – 250 km) Rajasthan state. Udaipur and Udaipur and Indore are the station is at Indore are the nearest airports nearest airports (150 – 250 km) Mandasaur.daipur and (150 – 250 km) Indore are the nearest airports (150 – 250 km) Area & The area of the town is 2.59 sq.km and The area of the town is 14.83 The area of the town is 3 sq.km The area of the town is Population has a population of 11,956 (2011 sq.km and has a population of and has a population of 6,737 4 sq.km and has a census). The town is divided into 15 6,553 (2011 census). The town is (2011 census). The town is population of 7,034 municipal wards (ward wise population divided into 15 municipal wards divided into 15 municipal wards (2011 census). The is given in Appendix 7). (ward wise population is given in (ward wise population is given in town is divided into 15 Appendix 7). Appendix 7). municipal wards (ward wise population is given in Appendix 7). Topography Kukdeshwar town is situated on Malwa Situated in the Malwa plateau, the Topographical features of the The topography of the Plateau. It is situated on semiarid topography of the town is flat and town explain the variations from town is a little uneven. geological formation. The strata sloping gently towards north-north RL 489m to RL 476 m. The Major undulations are Comprises of majorly Black Cotton soil west. Average elevation is 460 m elevation differences from on the eastern part of and red Soil. The rock formation is above the MSL. highest of 489 m to 476 m the city. The slope of the Deccan trap massive basalt overlain accounted a maximum town is in the south by alluvial plain. Topographical difference of 13 m in the town. direction. Areas in ward

38

Baseline Kukdeshwar Nayagaon SarwaniyaMaharaj Nagri characteristics features of the town explain the no 5 and ward no 6 are variations from RL 445m to RL 433 m. flood prone areas of the The elevation differences from highest town. Some upper of 445m to 433 m accounted a grounds are also seen maximum difference of 12 m in the on the eastern part of town. the town. Soils & The city is situated on the Malwa The Soil type can be seen in the The soil strata in the town are Mainly two types of soil geology Plateau. Black soil, Laterite soil, red town is Black soil, Red Loamy soil, mostly Black cotton soil and formations are observed soil and alluvial soilare the key soil Laterite soil and alluvial soil upto 6 kankar mix red soil. in the area, Black cotton types which are found in the city. feet. and alluvium soil. Climate The climate of Neemuch district is generally dry except during the southwest monsoon. Thereare four seasons: Climate of Nagri Winter (mid-November to end of February), Summer (March to June until onset of SW monsoon - May is the (Mandasaur district) is hottest month of the year), Monsoon - the southwest monsoon starts from middle of June and lasts till end of similar to that of September, and Post monsoon ( October to middle of November) Neemuch district.

• The normal annual rainfall: 798 mm. Over 90% of rainfall is received during the south west monsoon The annual average period i.e. June to September. rainfall is 657.3 mm, • The normal maximum temperature in May: 39.80 C; minimum during the month of January: 9.80 C. The less than Neemuch normal daily mean monthly maximum temperature is 31.60 C and daily mean minimum temperature is district. Given the lower 190 C. The summer season is the driest period of the year. rainfall, Nagri is • The relative humidity generally exceeds 87% in the month of August. comparatively dry. • The average normal annual wind velocity of the district is 9.2 km./hr.

Climatic characteristics of subproject districts – Neemuch and Mandasaur are provided in Appendix 8. Surface water There is a two water body of area 4.7 A large pond created by the No water bodies within the town Within the municipality ha and 0.4ha is situated in municipal abandoned lime stone quarry pit in limit there is no surface boundary. These water body id CCI Cement Factory compound water source in Nagri generally recharge by rain water. within the Nayagaon municipal limit Morwan dam, constructedin Smaller water body gets dry up in is the only notable surface water 1959, across River Gambhiri, is summer season. body. Area of this pond is about 35 the nearest notable surface ha and a depth of 23 m water body, located at 8 km from (maximum). CCI plant started its the town.Submergence area of operation 1984, and closed down the dam is 391 hectare. in 1994, and the pond is being used as source of water since then. It has an estimated capacity of 8

Baseline Kukdeshwar Nayagaon SarwaniyaMaharaj Nagri characteristics MCM. Apart from this, no surface water source in Nayagaon Apart from this, no water body in Nayagaon.

Groundwater The ground water report of The ground water report of Jawad The CGWB report of Sarwaniya The CGWB report of Kukdeshwar shows the improvement Tehasil consisting Nayagaon town Maharaj show that there is Daloha Tehsil show in ground water level. It increase from shows the continuous continuous depletion of ground that there is slight 14 meter to 6 meter from 2001 to 2014 improvement of ground water level. water level from 10 m to 14 m improvement in ground as per CGWB report It increase from 12 meter to 4 from 2010 to 2014. water level . It increase meter below ground level from from 14m to 12 m from 2010 to 2014 as per CGWB report 2010 to 2014. Groundwater quality of Neemuch district as assessed by Central Ground Water Board is as follows: ground Groundwater quality of Water in the district is generally low to medium saline as the Electrical conductivity value varies between 361 Mandsaur district as to4040µ S/cm at 250C. Constituent like Chloride, Sulphate, Calcium and Magnesium werewithin the safe limits assessed by Central of drinking water as per BIS standards. Nitrate in the groundwater of Neemuch district is varying between 2 to Ground Water Board is 280 ppm. Fluoride in the district is generally below 1.5 mg/l. No arsenic has been detected in the district. as follows: ground Water in the district is generally low to medium saline as the Electrical conductivity value varies between 609 to 2870µ S/cm at 250C. Constituent like Chloride, Sulphate, Calcium and Magnesium werewithin the safe limits of drinking water as per BIS standards. Nitrate in the groundwater of Neemuch district is varying between 45 to 140 ppm. No arsenic

40

Baseline Kukdeshwar Nayagaon SarwaniyaMaharaj Nagri characteristics has been detected in the district. Air quality No air quality data available for the subproject towns. However, there are no air pollution sources, except the dust, which is mainly due to dry weather, activities like traffic movement. In the area surrounding Nayagaon, there are cement industries, which are potential air polluting industries. Ecological Project area mostly comprises urban areas, agricultural areas of Athana, Kukdeshwar, Nayagaon, SarwaniyaMaharaj and Nagri which are converted to human use many years back. Extent of forest areas in the project area is very limited, and none of the project components are located in the forest areas. In Athana, forest areas are located near the source at SukhanandSagar Dam. While dam is located on a valley portion, and occupied by mostly with agricultural lands, the surrounding hills are under forests. These are open forests with shrubs and bushes, and trees. Flora in that area consist of mixed forest,bamboo, teak, sal etc.

The raw water pipeline from SukhanandSagar to Athana will be laid along a road, that is adjoining one-side the dam, and one side by the forest areas. The pipeline will be laid in the road right of way, and and will not encroach into the forest as these are clearly demarcated and separated by boundary fence.

Economic The area of the town is spread over in The development of Nayagaon The area of the town is spread The area of the town is development 2.59 sq. kmmainly in two settlements: Nagar Parishad has been primarily over in 3 sqkm (as per Censes spread over in 24.69 sq. (i) Northern part - Densely populated towards the north-western side 2011). The major population of km. The major Land use main city area, and (ii) Southern Part: along the highway and towards the city lives in the centre of the population of the city Scattered, populated area at the other Jawad road. The national highway city around the Nagar Parishad lives in the centre of the Agriculture & side of the Highway.Newly developing passing from the centre and the and ward No. 8. Two to three cityaround the Nagar industry areas mainly in the South-West and railway line divides the pockets in ward no 14 and 15 Parishad. Two to three Eastern Part of the town due to nearby development of the city in three are a little bit farther than the pockets in ward no 1, 14 proximity of National Highway. parts: C. C. I. Area, city. Newly developing areas are and 15 are a little bit along Neemuch road. farther than the city. Kukdeshwaris an agro based the core village area and the Newly developing areas economy and presently there are no western part towards railway line. In case of SarwaniyaMaharaj are along main road. industrial units. Betel Leafs, Garlic, To achieve balance development major development of the town Soya bean, Ajwain and Isabgol are in the city and to minimize the is towards Neemuch road Town is predominantly some of the large scale agricultural use of agricultural land for future towards South-East of the town. agricultural based produce in the region. development, it is suggested that it economy, and there are should take place in northern part Town is predominantly still large tracts of lands in ward number 1 and in ward agricultural based economy, and in the municipal numbers 13 and 15 in the southern there are still large tracts of boundary under part of the city. lands in the municipal boundary agriculture. Town and under agriculture. surrounding area is

Baseline Kukdeshwar Nayagaon SarwaniyaMaharaj Nagri characteristics The economic activity of Nayagaon famous for Garlic is largely based on agriculture.A cultivation. Other large amount of garlic, wheat and predominant crops are soya beans are cultivated here. Wheat, Maize, Groundnut, Gram, Nayagaon is famous for its Soyabean,Mustard, limestone mines. Cement Corn, Potato, Onion and industries are located in and different types of pulses. around Nayagaon Cement Corporation of India (CCI) plant is located in the outskirts with 535 acre area, but the factory was closed since 1997. Infrastructure - Total length of roads in Kukdeshwar is Total length of roads in Total length of roads in Total length of roads in transport 14.65 km, of 11.5 km are BT roads and Nayagaonis 17.20 km, of which SarwaniyaMaharajis 14.5 km, of Nagriis 15.80 km, of 2.65 km are un-surfaced roads and 8.65 km are CC roads, 3.0 km are which 2.0 km are CC roads, 8.0 which 7.5 km are CC 0.50 km are WBM. BT roads and 3.35km are un- km are BT roads and 4.5 km are roads, 1.8 km are BT surfaced roads and 2.5 km are un-surfaced roads. roads and 6.5 km are The old town area ofKukdeshwar is highway. WBM roads. characterized by very narrow roads. In The old town area the outer area, newly developing The old town area ofNayagaon is ofSarwaniyaMaharaj is The old town area areas, roads are comparatively wide characterized by very narrow characterized by very narrow ofNagri is characterized and has no much traffic. Commercial roads. In the outer area, newly roads. In the outer area, newly by very narrow roads. In activities are mainly concentrated developing areas, roads are developing areas, roads are the outer area, newly along the main roads, and in the town comparatively wide and has no comparatively wide and has no developing areas, roads areas, where roads are very narrow much traffic. Commercial activities much traffic. Commercial are comparatively wide congested with pedestrians, cycles are mainly concentrated along the activities are mainly and has no much traffic. and motor cycles. main roads, and in the town areas, concentrated along the main Commercial activities where roads are very narrow roads, and in the town areas, are mainly concentrated congested with pedestrians, cycles where roads are very narrow along the main roads, There are trees along the main roads, and motor cycles. congested with pedestrians, and in the town areas, however, these will not be cut for cycles and motor cycles. where roads are very laying pipelines by selecting, There are trees along the main narrow congested with amending the alignment as required. roads, however, these will not be pedestrians, cycles and cut for laying pipelines by There are trees along the main motor cycles. selecting, amending the alignment roads, however, these will not be as required. cut for laying pipelines by

42

Baseline Kukdeshwar Nayagaon SarwaniyaMaharaj Nagri characteristics selecting, amending the There are trees along alignment as required. the main roads, however, these will not be cut for laying pipelines by selecting, amending the alignment as required. Sewerage, There is no sewerage collection and treatment system in any of the subproject towns. Households mainly depend on individual sanitation sanitation & systems like pit latrines, septic tanks etc. Open defecation is also prevalent in the subproject area. Open drains are provided along the drainage roads, which carry both wastewater and rainwater during the rains. Drains dispose the water directly into natural water bodies. Solid waste There is no proper solid waste management system in the towns. Respective municipal councils are responsible for SWM services in their management areas. Waste generated in the towns are collected and disposed by crude open dumping method in the outskirts of the towns. Power supply: Thermal power is the main source of energy in Madhya Pradesh, contributing nearly 90% of the electricity, compared to hydropower, which produces the remainder. Power supply situation. Demographic Population of the town as per 2011 Population of the town as per 2011 Population of the town as per Population of the town characteristics census was 11,956 increased from census was 6553, increased from 2011 census was 6,737, as per 2011 census was 10,793 in 2001. 6023 in 2001 increased from 5,328 in 2001 7,034, increased from Growth rate 2001-2011:10.8% Growth rate 200-11 – 8.8% Growth rate 200-11 – 26.4% 6,565 in 2001 Average HH size: 4.95 Average HH size: 4.43 Average HH size: 4.04 Growth rate 200-11 – Sex ratio – 976 Sex ratio – 934 Sex ratio – 950 7.1% Literacy rate (total) – 80.95% Literacy rate (T) – 73.66% Literacy rate (T) – 74.01% Average HH size: 5.19 Literacy rate (male) –93.61% Literacy rate (M) – 85.3 %. Literacy rate (M) –87.25 %. Sex ratio – 979 Literacy rate (female) – 68.2% Literacy rate (F) – 61.5% Literacy rate (F) – 60.06% Literacy rate (T) – SC population – 8.4% SC population – 15.3% SC population – 16.9% 75.73% ST population – 0.84% ST population – 5.7% ST population – 2.2% Literacy rate (M) – 88.46 (ward wise population is given in (ward wise population is given in (ward wise population is given in %. Appendix 7) Appendix 7) Appendix 7) Literacy rate (F) – 62.88% SC population –10.2% ST population – (ward wise population is given in Appendix 7) History, Kukdeshwar is famous for its large There are no protected or notable There are no protected or There are no protected culture & scale cultivation of betel leaves (Pan historical, cultural or tourism places notable historical, cultural or or notable historical, tourism KePatte) which is done by a special in the town. tourism places in the town cultural or tourism community called “Tambolies” and places in the town

Baseline Kukdeshwar Nayagaon SarwaniyaMaharaj Nagri characteristics thus is also known as “The Town of Tambolies”. The city is also famous for its The famous Jain SahastramuktsehwarBhagwanTemple Temple (1000 faces of Lord Shiva). It is BahiPashwanath is approximately 400 year old temple. about 7 km and the This temple is situated here from famousPashupatinath ancient time and is the prime attraction Temple is 18 km from for pilgrims coming to this city. This the city. history of Kukdeshwar is believed to be about 1050 years old. There is also a 108 Parsavnath Jain Mandir which is very popular in the Jain community.

44

Figure 14: KUKDESHWAR SUBPROJECT AREA & ENVIRONS

Figure 15: Nayagaon Subproject Area & Environs

46

Figure 16: Sarwaniya Maharaj Subproject Area & Environs

Figure 17: NAGRI SUBPROJECT AREA & ENVIRONS

48

C. Subproject Site Environmental Features

39. Features of the selected subproject sites are presented in the following table.

Table 5: Site Environmental Features - Kukdeshwar S. Infrastructure Location & Environmental Site Photograph No Features 1 Intake Water will be lifted from Gandhi Sagar Dam with the help of Submersible Floating Pumps. Submersible Pumps will be mounted on Floating Platform. So no civil works will be conducted in the dam.

2 Raw water Pumping station will be pumping constructed in the existing stations WTP premises at Rampura near the Gandhi Sagar Dam. Land owned by GoMP (WRD)

3 Raw water Pipe will be laid from pumping transmission station to WTP, along the line (18.0 km) Rampura – Kukdeshwar Road (SH 31A) within the RoW. There is adequate space in the road earthen shoulder to lay the 200 mm dia pipeline.

4 WTP The proposed site for WTP is located at Phoolpura village about 2 km outside the town. It is about 100 m from Rampura – Kukdeshwar Road (SH 31A). Site is currently vacant, and is owned by GoMP (Revenue Department). Site is located adjacent (~50 m) from Poolpuravillag habitation (about 150-200 houses are there in the village). There are two big trees in the site, and these

will be included in the WTP layout design and will not be cut. 5 Clear water Within the WTP campus, as As above sump (1 LL) above and pumping station 6 Clear water Pipes will be laid within the transmission road right of way (ROW) - in (3.45 km) road’s earthen shoulder in wider roads

7 Distribution Pipes will be laid within the network road right of way (ROW) - in (13.866 km) road’s earthen shoulder in wider roads, and within the carriageway in narrow roads, where there is no space. Roads in the old part of the town are quite narrow and pipes will be laid mostly in the centre of the road

50

Table 6: Site Environmental Features - Nayagaon S. Infrastru Location & Environmental Site Photograph N cture Features o 1 Intake Water will be lifted from CCI pond using submersible pumps with a Floating Barrage arrangement. No civil works are proposed. CCI pond is located with CCI factory compound under the possession of CCI.

Pond is created naturally by open cut lime stone quarry spread over an area of 35 ha within the factory campus. This cement factory was established in 1984, and was operational till 1994. Presently the pond is filled with water, and local enquiries indicated that water is always available in the pond, the fluctuation in water level is very low. The water from the surrounding areas, factory premises. Water is visually clear, and is being used as source, however, there is aquatic life in the lake. 2 Raw Pumping station near CCI pond water within the factory compound. Site is pumping vacant, no tree will be cut. stations

3 Raw From raw water pump house to WTP water site (alignment in the land owned by transmis CCI and partially along a road sion line (National Highway) within the RoW. (2 km) There are no trees in the alignment.

4 WTP On a government owned land parcel located along the national highway (NH 79) in the town. Site is vacant, and is located within the town area.

5 Clear Within the WTP campus, as above As above water sump (1 LL) and pumping station 6 Clear Pipes will be laid within the road right water of way (ROW) - in road’s earthen transmis shoulder in wider roads sion (0.75 km)

52

7 Overhea On a ULB owned land near Nayagaon d tank Nagar Parishad Office. Site is vacant, and there are no tree in the ste

7 Distributi Pipes will be laid within the road right on of way (ROW) - in road’s earthen network shoulder in wider roads, and within (17.29 the carriageway in narrow roads, km) where there is no space. Roads in the old part of the town are quite narrow and pipes will be laid mostly in the centre of the road.

Table 7: Site Environmental Features – Sarvaniya Maharaj S. Infrastructure Location & Site Photograph No Environmental Features 1 Intake / Raw water Water will be extracted pumping stations from the existing open well, no new civil works proposed. Existing open well is located within a land parcel owned by ULB surrounded by agricultural areas. Well is located on the downstream side of Morewan Dam. Pump house will be constructed near the well, within the land owned by ULB.

2 Raw water From the open well to transmission line WTP site in the town. Pipe (8.7 km) will be laid along Neemuch – Ratangarh Road within the RoW.

3 WTP On a government owned land parcel in the town near the Secondary School. Sit is currently vacant, and there are no trees, except some shrubs and bushes. Site located close to a school, and the other sides are surrounded by agricultural/barren lands covered with shrubs and bushes. Site is owned by Revenue Department (GoMP). 4 Clear water sump Within the WTP campus, As above (1 LL) and as above pumping station

54

5 Overhead tank OHT will also be As above constructed within the WTP compound near the School 6 Clear water Pipes will be laid within the transmission (0.9 road right of way (ROW) - km) in road’s earthen shoulder in wider roads

7 Distribution Pipes will be laid within the network (11.85 road right of way (ROW) - km) in road’s earthen shoulder in wider roads, and within the carriageway in narrow roads, where there is no space. Roads in the old part of the town are quite narrow and pipes will be laid mostly in the centre of the road.

Table 8: Site Environmental Features – Nagri S. Infrastructure Location & Site Photograph No Environmental Features 1 Intake An intake well will be constructed in the Rupanikhayal Dam under the possession of WRD. An access road including an access bridge will be constructed. Aquatic life in the reservoir is limited

to local specifies of fishes, and aquatic plants. There are no notable sensitive features. 2 Raw water Pump house will be As above pumping located above the intake stations well in the dam. 3 Raw water Pipe will laid along the transmission RoW line (9.05 km)

4 WTP 115 MLD WTP is proposed at Khasra no. 1825/1. The land is vacant and of Revenue department, GoMP

5 Clear water Within the WTP campus, As above sump (1 LL) and as above pumping station

56

6 Clear water Pipeline will be laid from transmission WTP to OHT which are (125m) located in the same premises; land owned by Revenue department.

7 Distribution Pipes will be laid within network (14 km) the road right of way (ROW) - in road’s earthen shoulder in wider roads, and within the carriageway in narrow roads, where there is no space. Roads in the old part of the town are quite narrow and pipes will be laid mostly in the centre of the road.

57

VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

40. Potential environmental impacts of the proposed infrastructure components are presented in this section. Measures to minimize/mitigate negative impacts, if any, are recommended along with the agency responsible for implementation. Monitoring actions to be conducted during the implementation phase is also recommended.

41. Screening of potential environmental impacts are categorized into four categories considering subproject phases: location impacts and design impacts (pre-construction phase), construction phase impacts and operations and maintenance phase impacts.

a. Location impacts include impacts associated with site selection and include loss of on-site biophysical array and encroachment either directly or indirectly on adjacent environments. It also includes impacts on people who will lose their livelihood or any other structures by the development of that site. b. Design impacts include impacts arising from Investment Program design, including technology used, scale of operation/throughput, waste production, discharge specifications, pollution sources and ancillary services. c. Construction impacts include impacts caused by site clearing, earthworks, machinery, vehicles and workers. Construction site impacts include erosion, dust, noise, traffic congestion and waste production. d. O&M impacts include impacts arising from the operation and maintenance activities of the infrastructure facility. These include routine management of operational waste streams, and occupational health and safety issues.

42. Screening of environmental impacts has been based on the impact magnitude (negligible/moderate/severe – in the order of increasing degree) and impact duration (temporary/permanent).

43. This section of the IEE reviews possible project-related impacts, in order to identify issues requiring further attention and screen out issues of no relevance. ADB SPS (2009) require that impacts and risks will be analyzed during pre-construction, construction, and operational stages in the context of the project’s area of influence.

44. The ADB Rapid Environmental Assessment Checklist in http://www.adb.org/documents/guidelines/environmental_assessment/eaguidelines002.aspis used to screen project for environmental impacts and to determine the scope of the IEE.

45. In the case of this project (i) most of the individual elements are relatively small and involve straightforward construction and operation, so impacts will be mainly localized and not greatly significant;(ii) proposed water abstraction from the sources is very small compared to overall water availability, and necessary water allocations are being made from Water Resources Department(iii) most of the predicted impacts are associated with the construction process, and are produced because that process is invasive, involving excavation and earth movements; and some works are located in the reservoir and (iv) being mostly located in an urban area, will not cause direct impact on biodiversity values. The project will be in properties held by the local government and access to the project location is through public rights-of-way and existing roads hence, land acquisition and encroachment on private property will not occur.

58

A. Pre-Construction Impacts – Design & Location

46. Design of the Proposed Components. Technical design of the (i) intake facilities, (ii) water treatment plant; (iii) raw water and clear water mains, (iv) storage reservoirs, and (v) distribution network, connections, flow meters, etc., follows the relevant national planning and design guidelines, focusing on providing a robust system which is easy to operate, sustainable, efficient and economically viable. Besides, the project also included the following environmental considerations:

(i) Discontinuation of current unsustainable groundwater sources and creating a new water supply system based on nearest surface water sources, and continuation of existing sources, where feasible (ii) Recovering backwash water from treatment process (iii) Treatment and reuse of sludge from treatment process (iv) Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques (HDPE pipes up to 150 mm dia joined by electro fusion couplers using on-site electro fusion welding, and all higher dia pipes by on site butt welding) (v) Designing the entire system to maintain optimal flow and terminal pressure, and optimising the overall energy usage (vi) Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies (vii) Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor (viii) Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections (ix) Using low-noise and energy efficient pumping systems

47. Water Source& Sustainability. As the subproject towns are located far from each other there was no possibility of a combined source/ bulk water scheme. Therefore, independent water supply schemes are proposed for 5 towns separately based on the most feasible water source considering techno-economic and environmental considerations as elucidated below (Table 9).

59

Table 9: Water Source Selection & Sustainability Subproject Town Alternative Sources Selected Source and Associated Impacts due to abstraction Kukdeshwar Groundwater: Presently only 0.32 MLD of water is being supplied For the Kukdeshwar town, the demand of water through ground sources (3 nos of tube wells, 12 nos of Hand Pumps & supply for the year 2018, 2033 & 2048 are estimated 2 nos of open well). These sources are giving very less yield. Based on to the tune of 1.20 MLD, 1.40 MLD & 1.60 MLD the available data the present tube wells may supply water to the town respectively. Thus maximum of1.60 MLD intake form at the tune of maximum 0.16 MLD. And therefore no considered for the source per annum i.e. 585 ML (0.59 MCM) of future project. drawl of water is to be ensured. Annual average Danderi River flows from North-West to South- East direction and recoupment of water in the tank every year is located around 9 km away on the west side of Kukdeshwar Town on around6910MCM. While the recoupment of water Manasa Road. It starts from the Bherpura village of Manasa Tehsil and during rainy season is 6910 MCM which is12000 ends in Gandhi Sagar Dam. Total length of travel is approximately times than the annual water demand of Kukdeshwar 19km. This river flows mostly during the rainy season and remains dry town. The salient feature of Gandhisagar dam is almost8 months of a year. Also the river bed is flat and there is no deep given in Appendix 12. The water quality of the dam is valley in the entire length of travel. Hence it is not possible to construct good for consumption and given in Appendix 10. a check dam or bund where we can store and fulfill the water demand of Kukdeshwar town. Jannod River is not a perennial river. Rain water from the Jannod and Amad hill ranges and surrounding areas like Chikli Block, Amarpura and Danta are coming to the river. Jannod River starts from Danta village of Manasa Tehsil and ends in Gandhi Sagar Dam near Jannod village. The approximate length of travel is around 13 km. This river is also a subsidiary of Gandhi Sagar Dam. This river flows mostly during the rainy season and remains dry almost8months of a year. There is no assurance to getting the 100% water demand of Kukdeshwar town during the entire year The Gandhi Sagar Dam is one of the four major dams built on India's Chambal River. The dam is located in the Mandsaur district of the state of Madhya Pradesh. It is a masonry gravity dam, standing 62.17 metres (204.0 ft.) high, with a gross storage capacity of 7.322billion cubic metres from a catchment area of 22,584 Km2 (8,720 Sq Miles). The construction of the main dam was completed in 1960. Nayagaon CCI Dam on Gambhiri River as a source: CCI has constructed a Dam For the Nayagaon town, the demand of water supply on Gambhiri River in 1990 as a source for their need for industrial for the year purpose. It is a stop dam located near the Kamavat village around 12 2018, 2033 & 2048 are estimated to the tune of 0.7

60

km from the town. CCI had used the dam for 5years. Presently water is MLD, 0.8 MLD & 0.9 MLD respectively. Thus not taken from the dam as it is very far from the and also not a reliable maximum of 0.9 MLD intake form the source per source for the town. annum i.e. 328.5 ML (0.328 MCM) of drawl of water is CCI limestone mine Water Pond as a Source. Cement corporation of to be ensured. While the calculation if the Pond shows India had started there cement factory in 1984 and stopped their work that the average water storage in the reservoir is in 1995. Since then the lime stone mine that is been used since then got 8.05MCM which is 25 times the yearly requirement of abundant and water got started stored in it during rainfall and there also the town. Thus from the calculation we can say that an existence of some ground water. By the present time the limestone the quantity of water from the source can be ensured. mine got filled with water. Since there is no fault zone in the mine the Salient features of the pond is given below: water gets stored in the mine. At present Nagar Parishad is supplying 1. Area of CCI Pond 35 Ha (349944 Sq water from the same mine. As the mine is lime stone mine it works as a m) natural disinfectant which makes the stored water fit for daily use. There is no any aquatic life in CCI pond during site visit. Upon consultation 2. Top Level of Pond 465.32 m with local public, it was known that aquatic life is not found in CCI pond. 3. Bottom Level of Pond 442.45 m 4. Average Maximum Depth of Pond 23 m 5. Volume of Pond 8048712 m3 6. Capacity of Pond 8048 MLD ( 8.05 MCM) Random water quality test is conducted to study the quality of water in source. Results are presented in Appendix 14A. Water quality is good and suitable for domestic water supply after conventional treatment. However, considering the nature and location of source within a cement factory compound receiving runoff from the factory areas, a comprehensive water quality monitoring testing program will be conducted to confirm the quality prior to the start of work. Appendix 14B presents the suggested monitoring program. Sarwaniya Maharaj Groundwater: Presently only 0.40 MLD of water is being supplied Open well near Morwan Dam is selected for water through ground sources like 1 nos of tube wells, 8 nos of Hand Pumps supply source as the well is continuously recharged &3 nos of open well. These entire sources are giving very less yield. with Morwan dam. Quality of water is also safe for

Based on the available data the present tube wells may supply water to water supply. The open well is currently used as water the town at the tune of maximum 0.04 MLD. source for the SarwaniyaMaharaj.

Open well at the downstream side of Morewan Dam Yield test of open well in Morwan was conducted on This well is in use since xxxx year, the depth of well xx m and diameter 24.05.2016 as per advice of PPTA safeguard team is xx. This is located just downstream of the dam, and the water level is and MPUDC officers. The depth of open well was 30.0 always maintained with the dam water level. Dam holds water feet (10.00 meter). Ground level of open well is throughout the year, though level fluctuated between fill level in 469.243 meter and pre test static level of water was monsoon to minimum level in summer. Details of Morewan dam are 464.79 meter. During the test, open well submersible provided in Appendix 15. pump of capacity 14.7 LPS and motor having capacity 15 HP is being used for yield test. In yield test, constant pumping was done for 15 hours and water recovery test was done for 8 hours. Constant rate pumping test was started at 7.00 AM, at that time the water level in the well was 464.79 meter and the depth of water was 4.69 meter. At the end of yield test at 10.00 PM, the RL of water was 462.96 meter and depth of water was 2.87 meter. During the last 10 hours of yield test, the water level was reduced from 3.63 to 2.87 meter indicate the rate of water recharge of well is quite good.

Detailed Yield test report id given in Appendix 16. The yield of the well is 11.17 LPM. Water level is recovered in just 10 hours. Hence it shows that the well is self to cater the water demand of SarwaniyaMaharaj town for proposed water supply scheme. Since water quality test for deciding source to be taken as water source, it is proved to be good source based on the water sample test reports obtained from recognized PHED Laboratory, Bhopal. Water quality results are presented in Appendix 14. Nagri Groundwater: Presently only 0.15 MLD of water is being supplied Rupaniyakhal Dam is selected for water supply in through ground sources like 3 nos of tube wells, 12 nos of Hand Pumps town as water availability in dam throughout the year. & 2 nos of open well. These entire sources are giving very lessyield. Based on the available data the present tube wells may supply water to For the Nagri town, the demand of water supply for the town at the tune of maximum 0.07 MLD. the year 2018, 2033 & 2048 are estimated to the tune

62

Rupaniyakhal dam of WRD department is constructed in Tehsil – of 0.8 MLD, 0.9 MLD & 1.0 MLD respectively. Thus Jawara, Dist – Ratlam, about 8 km from the town. It is constructed in maximum of 1.1 MLD intake from the source per 1994. The total length of the dam is 785 m and height is 18.70 m. annum i.e. 401.5 ML (0.4 MCM) of drawl of water is to Details of dam are provided in Appendix 18. be ensured. In dam, the recoupment of water during rainy season is 24.02 MCM which is 60 times than the annual water demand of Nagri town.

Water quality is appropriate to use as domestic source after conventional treatment. Water quality details are provided in Appendix 16.

63

48. Source Sustainability and Environmental Considerations. Of the four project towns, for two towns – Kukudeswar and Nagri, water is proposed to be sourced from the existing dams, with comparatively huge storage. Necessary permissions and water allocation in the dam for domestic water supply will be obtained from the Water Resources Department. Adequate water is available to meet the demand, no conflicts or impacts on existing uses are envisaged as the water allocation will be made. The water withdrawal for the project is very less compared to water availability and therefore no significant impacts envisaged. For Sarwaniya Maharaj water will be sourced from existing open shallow wells located very close to the dams. These sources are already under use as source for respective municipalities. The dams directly recharge wells, and therefore yield of the wells is adequate to meet the demand. Yield tests conducted during the project preparation confirmed adequate yield and water recuperation. No impacts therefore envisaged. For the remaining town – Nayagaon, water is proposed to be sourced from an abandoned lime quarry pit, which has become a pond with huge water storage. This is already being used as source by Nayagaon nagar parishad and it will be continued to be used for the project also. The estimated storage in the pond is huge compared to the demand, and the water is exclusively used for the water supply to the town only. Necessary permission from the CCI is being obtained.

49. Water quality of all the sources is suitable for drinking water after conventional treatment and disinfection, and there are no notable pollution sources in the vicinity. Random water quality tests conducted at sources indicated that the water quality is good and suitable for domestic water supply after conventional treatment. However, for Nayagaon, as the source (CCI pond) is originally a lime stone quarry, and located within the factory compound, has been receiving surface runoff from the premises and other open areas, further comprehensive water quality testing program is suggested to be conducted to confirm the water quality during the implementation. The fact that there is no aquatic life observed in the pond also makes it important that to confirm water quality in a comprehensive manner. Suggested monitoring program is given in Appendix 14B

50. Use of Chlorine as disinfectant. It is proposed to use chlorine at WTP to disinfect the water prior to supply to consumers. There is invariably a safety risk when chlorine is handled. Although facilities are not located close to habitations, safety precautions are necessary to ensure the safety of workers and citizens. To avoid any risk, chlorination facility will be provided with safety provisions, which are presented in the EMP (Table 11 to 13)

51. Sensitive project locations. Located mostly in dry and semi-arid region of western Madhya Pradesh bordering Rajasthan state, there are no notable sensitive environmental features in or near project towns. The source and surroundings were once agricultural lands (now falls under the dam submergence area). The raw water pipeline is aligned in the road right of way, and therefore no encroachment into forest is envisaged. Necessary precautions will be taken during the construction to avoid any accidental fall of wild animals in the pipeline trench: No trench will be kept open during the night, and the pipe laying work will be undertaken in small stretches, so that excavation, pipe laying and refilling is done on the same day. In unavoidable circumstances if the trenches are kept open at night, proper barricading will be done.

52. Similarly proposed works in the Rupaniya khal dam river bed (for intake and approach bridge) may damage the bed, lead to degradation of water quality due to increase in turbidity and contamination from fuels and lubricant used in construction work. Increase in silt content and water turbidity, chemical quality can affect the aquatic life. Though works are very small scale, the contractor will be required to implement certain measures. These measures are included in the EMP to avoid, minimize these impacts (Table 10 to 12).:

53. Removal of trees and vegetation will be minimized by best pipe alignments and layout planning of facilities, however, this cannot be avoided fully. Appropriate measures in terms of

64 compensatory tree plantation is included in the EMP (Table 10 to 12).

54. Utilities. Telephone lines, electric poles and wires, water lines within the proposed project locations may require to be shifted in few cases. To mitigate the adverse impacts due to relocation of the utilities, the contractor, in collaboration with ULB will be required to implement appropriate measures. These are given in the EMP (Table 10 to 12).

55. Site selection of construction work camps, stockpile areas, storage areas, and disposal areas. Priority is to locate these near the project location. However, if it is deemed necessary to locate elsewhere, sites to be considered will not promote instability and result in destruction of property, vegetation, irrigation, and drinking water supply systems. Residential areas will not be considered for setting up construction camps to protect the human environment (i.e., to curb accident risks, health risks due to air and water pollution and dust, and noise, and to prevent social conflicts, shortages of amenities, and crime). Extreme care will be taken to avoid disposals near forest areas, water bodies, or in areas which will promote instability.

56. Site selection of sources of materials. Significant quantities of coarse aggregate and fine aggregate will be required for construction works. Requirement of gravel is limited. Contractor should procure these materials only from the quarries permitted/licensed by Mines and Geology Department. Contractor should, to the maximum extent possible, procure material from existing quarries, and creation of new quarry areas should be avoid as far as possible. It will be the construction contractor’s responsibility to verify the suitability of all material sources and to obtain the approval of Department of Mines & Geology and local revenue administration.

B. Construction Impacts

57. Construction works. Civil works in the project include linear excavation for laying pipes along the roads, placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4 m – 0.7 m wide and 0.8 to 1 m depth. Subsequent to completion of works, the contractor as part of the civil works will undertake road reinstatement. The roads in the core city area of all the towns are very narrow and congested with pedestrians and vehicles (mainly 2-wheelers), while the roads in outer areas are wide.

58. Earth work excavation will be undertaken by machine (backhoe excavator) or manually and include danger lighting and using barricades at every 100 m.. Sufficient care will be taken while laying so that existing utilities and cables are not damaged and pipes are not thrown into the trenches or dragged, but carefully laid in the trenches. As trenches are a maximum of 1.2 m, there is no risk of collapse of trenches or risk to surrounding buildings. Once they are laid, pipes will be joined as per specification and then tested for any cracks of leakages. The minimum working hours will be 8 hours daily, the total duration of each stage depends on the soil condition and other local features. About 95% of the excavated soil will be used for refilling the refilling the trench after placing the pipe and therefore residual soil after pipe laying and refilling is not significant. This excess soil shall be used for construction.

59. Other civil works in the subproject include construction of intake cum pump house and approach bridge/road in Rupaniyakal Dam for Nagri, raw water pumping stations in all towns, water treatment plants, water tanks (ground level / overhead), pumping stations at identified sites. These works will be confined to sites, and construction will include general activities like excavation for foundation, construction of foundations, columns, walls and roof in cement concrete and masonry, and fixing of mechanical and electrical fixtures, etc.

60. Although construction of these project components involves quite simple techniques of civil work, the invasive nature of excavation and the project locations in the built-up areas

of the town where there are a variety of human activities, will result in impacts to the environment and sensitive receptors such as residents, businesses, and the community in general. The following are anticipated impacts, which are temporary and for short duration:

(i) Dust and air emissions from construction activities and equipment / vehicles affecting the ambient air quality (ii) Impacts on natural drainage, surface water bodies due to disposal of construction waste and silt / chemical laden run off from work areas (iii) Impacts on river eco-system due to river bed construction (iv) Impacts due to disposal of surplus soil, construction waste, debris etc., (v) Impacts due to noise and vibration from consultation activities (vi) Impacts due to collection of groundwater in trenches & disposal of the same (vii) Impact/public inconvenience/ accessibility issues due to excavation on public roads (narrow old town roads), movement of trucks carrying construction material (viii) Impacts on business, activities, people due to loss/restricted access to public/private/business/sensitive areas (schools, hospitals), etc., (ix) Occupation health and safety impacts on workers (x) Health Impacts due to removal of existing AC (asbestos cement) pipes (xi) Community health and safety impacts due to construction in an urban area (xii) Impacts due to establishment/operation of temporary construction camps

61. The above impacts are typical for construction in urban areas, and therefore are common to all the three subproject towns. These are negative but short-term and reversible by mitigation measures. There are well-developed and proven measures and construction practices to avoid, mitigate and/or minimize these impacts to acceptable levels. These measures are given in the construction phase EMP (Table 13) applicable to all three towns.

C. Operation and Maintenance Impacts

62. Operation and Maintenance of the water supply system will be carried out by the DBO Contractor for 10 years, and after which the respective municipalities will operate and maintain the infrastructure. During the system design life (15/30 years for mechanical/civil components),it shall not require major repairs or refurbishments and should operate with little maintenance beyond routine actions required to keep the equipment in working order. The stability and integrity of the system will be monitored periodically to detect any problems and allow remedial action if required. Any repairs will be small-scale involving manual, temporary, and short-term works involving regular checking and recording of performance for signs of deterioration, servicing and replacement of parts.

63. Recurrence of pipe bursting and leakage problems can be managed by the leak detection and water auditing surveys. The ULBs will be required to ensure that the leak detection and rectification time is minimized.

64. Provision for recirculation system for filter backwash – backwash water from filter beds will be sent to a storage tank, and after allowing adequate time for settlement of solids, clarified water will be pumped to WTP inlet. This arrangement will avoid pollution and also minimize wastage of water. Water treatment process will generate sludge from sedimentation of particulate matter in raw water, flocculated and precipitated material resulting from chemical coagulation, residuals of excess chemical dosage, plankton etc. and waste from rinsing and back washing of filter media containing debris, chemical precipitates, straining of organic debris and plankton. Accumulated sludge from Tube Settler, filter backwash etc., will be disposed-off at sludge drying beds for natural drying. Dried sludge will be disposed off in a land fill or used as soil conditioner if it is suitable.

66

D. Project benefits

65. During the construction phase, there are likely to be positive impacts through employment generation, increase in local revenue from the project activities. During the operation phase also, there is potential for employment generation, though limited, as the improved and expanded water infrastructure requires additional workforce.

66. The citizens of Kukdeshwar, Nayagaon, SarwaniyaMaharaj and Nagri will be the major beneficiaries of the improved water supply system, as they will be provided with a constant supply of better quality water, piped into their homes at an appropriate pressure. The project will improve the over-all health condition of the towns as water borne diseases will be reduced, so people should spend less on healthcare and lose fewer working days due to illness, so their economic status should also improve, as well as their overall health. This should also improve the environment of these areas, should deliver major improvements in individual and community health and well-being.

VI. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

A. Overview

67. The active participation of stakeholders including local community, NGOs/CBOs, and the media in all stages of project preparation and implementation is essential for successful implementation of the project. It will ensure that the subprojects are designed, constructed, and operated with utmost consideration to local needs, ensures community acceptance, and will bring maximum benefits to the people. Public consultation and information disclosure is a must as per the ADB policy.

68. Most of the main stakeholders have already been identified and consulted during preparation of this IEE, and any others that are identified during project implementation will be brought into the process in the future. Primary stakeholders of the subproject are: residents, shopkeepers and businesspeople who live and work alongside the roads in which network improvements will be provided and near sites where facilities will be built (WTP and water tanks), and government and utility agencies responsible for provision of services in Kukdeshwar, Nayagaon, Nagri and Sarwaniya Maharaj, WRD and MPPCB, etc. Secondary stakeholder are: NGOs and CBOs working in the area, community representatives, beneficiary community in general, government agencies, the executing and implementing agencies (MPUDC, PMU and PIUs), Government of India and the ADB.

B. Public Consultation

69. The public consultation and disclosure program is a continuous process throughout the project implementation, including project planning, design and construction.

1. Consultation during Project Preparation

70. Institutional consultations were conducted with the relevant Governmental Departments such as WRD, PHED, MPPCB, FD, etc. The subproject proposalsare formulated in consultation with Kukdeshwar, Nayagaon, Sarwaniya Maharaj and Nagri Nagar Parishads to suit the requirements of the respective towns.

71. Focus-group discussions with affected persons and other stakeholders were conducted to learn their views and concerns. A socio-economic household survey has been conducted in the town, covering sample households, to understand the household characteristics, health status, and the infrastructure service levels, and also the demand for infrastructure services. General public and the people residing along the project activity areas were also consulted during visits to the project sites. Formal town-level consultation meetings were conducted in March - June2016 in all the five subproject towns. Besides, several other meetings also conducted at ward-level with communities, and at market with street vendors and hawkers. The details of consultation are provided in Appendix 20.

72. The people are willing to extend their cooperation as the activities are proposed to improve the water supply service levels and the living standards. Stakeholder expressed their concern regarding water charges, affordability, disturbance and loss of business due to the work in market area (dust, road closure etc.). The project team explained the proposed mitigation measures to mitigate / minimize such issues. In Nayagaon people are aware of the existing source (Lime stone pond) and have no problem in continuing it as future source as well. Stakeholders observed that there have no health issues due to this source. Some people requested to give priority of local people in employment during construction work.

.

68

2. Consultation during construction

73. Prior to start of construction, ULBs and PIU with the assistance of PMC will conduct information dissemination sessions at various places and solicit the help of the local community, leaders/prominent for the project work. At each ward/neighborhood level, focus group meetings will be conducted to discuss and plan construction work with local communities to reduce disturbance and other impacts.

74. A constant communication will be established with the affected communities to redress the environmental issues likely to surface during construction phases and also regarding the grievance redress mechanism. ULB/PIU and PMC will organize public meetings and will appraise the communities about the progress on the implementation of EMP. Meeting will also be organized at the potential hotspots/sensitive locations before and during the construction.

C. Information Disclosure

75. Executive summary of the IEE will be translated in Hindi and made available at the offices of PMU, PIU, Nagar Parishad offices, and also displayed on their notice boards. Hard copies of the IEE will be accessible to citizens as a means to disclose the document and at the same time creating wider public awareness. Electronic version of the IEE in English and Executive Summary in Hindi will be placed in the official website of the MPUDC, PMU after approval of the IEE by Government and ADB. Stakeholders will also be made aware of grievance register and redress mechanism.

76. Public information campaigns to explain the project details to a wider population will be conducted. Public disclosure meetings will be conducted at key project stages to inform the public of progress and future plans. Prior to start of construction, the PMU/PIU will issue Notification on the start date of implementation in local newspapers A board showing the details of the project will be displayed at the construction site for the information of general public.

77. Local communities will be continuously consulted regarding location of construction camps, access and hauling routes and other likely disturbances during construction. The road closure together with the proposed detours will be communicated via advertising, pamphlets, radio broadcasts, road signage, etc.

VII. GRIEVANCE REDRESS MECHANISM

A. Project Specific Grievance Redress Mechanism

78. A program-specific grievance redress mechanism (GRM) shall be established to receive, evaluate, and facilitate the resolution of AP’s concerns, complaints, and grievances about the social and environmental performance at the level of the project. The following GRM provides a time-bound and transparent mechanism to voice and resolve social and environmental concerns linked to the project.

79. A common GRM will be in place for social, environmental, or any other grievances related to the project. The GRM will provide an accessible and trusted platform for receiving and facilitating resolution of affected persons’ grievances related to the program. The multi- tier GRM for the project is outlined below, each tier having time-bound schedules and with responsible persons identified to address grievances and seek appropriate persons’ advice at each stage, as required. ULB-wide public awareness campaigns will ensure that awareness on grievance redress procedures is generated through the campaign.

80. Who can complain: A complaint may be brought by persons who are, or could be, “directly, indirectly, materially, and adversely” affected by the project. A complaint can be submitted on behalf of the affected person/people by a representative, provided that he or she identifies the affected person/people and includes evidence of the authority to act on their behalf.

81. What the Grievance/Complain should contain: Any concerns pertaining to safeguard compliance - environment, involuntary resettlement, indigenous people, design related issues, compensation, service delivery or any other issues or concerns related to the project. The complaint must contain name, date, address/contact details of the complainant, location of the problem area, along with the problem.

82. Where to file a Complaint: Complainants will have the flexibility of conveying grievances/suggestions by dropping grievance redress/suggestion forms in complaints/suggestion boxes to be installed by project at respective Nagar Parishad Offices, PIU offices or by e-mail or by writing in a complaint register in the PIU offices or at construction site offices.

83. How to file a Complaint: The application should be precise and specific. The application can be sent either by post or through electronic means or deliver personally. A sample grievance form is at Appendix 21.

(i) Offline System - The application can be made on the application form available at all accessible places (NPs/ Office of PIUs/ construction site offices). The application should have the name and complete postal address of the applicant. (ii) Online System - Grievances pertaining to the implementation of the project can also be filed online at the website of MPUDC/PMU or by e-mails.

84. Documentation: Documentation of the complaints is important and must contain name of the complainant, date of receipt of the complaint, address/contact details of the person, location of the problem area, and how the problem was resolved. PMU with the support of PIU will have the overall responsibility for timely grievance redress, and for registration of grievances, related disclosure, and communication with the aggrieved party. All the documents made available to the public at the community level (at ward offices) and will include information on the contact number, address and contact person for registering grievances, and will be disseminated throughout the project area by the PIU.

70

85. Grievance/Problem Redress through Participatory Process: Efforts must be made by the PIU with the support of safeguard consultants to resolve problems amicably, conflicts through participatory process with the community and the Nagar Parishads. In case of grievances that are immediate and urgent in the perception of the complainant, the Contractor, and supervision personnel from the PIU will provide the most easily accessible or first level of contact for the quick resolution of grievances. Contact phone numbers and names of the concerned staff and contractors, will be posted at all construction sites at visible locations.

86. Following process will be followed:

(i) 1st level grievance. In case of grievances that are immediate and urgent in the perception of the complainant, PMC supervising staff will direct the contractor to and ensures that it is resolved. If the grievance is not under the contractor scope, but under the program, PMC (field office) will resolve this issue. All the grievances should be resolved within 3 days of receipt of a complaint/grievance.

(ii) 2nd level grievance. All grievances that cannot be redressed at first level within 3 days will be brought to the notice of PIU and PMC Assistant Environmental Specialist. PIU will review the grievance and act appropriately to resolve it within 10 days of receipt.

(iii) 3rd level grievance. All the grievances that are not addressed at 2nd level by PIU within in 10 days of receipt will be brought to the notice of notice of the Grievance Redressal Committee (GRC)1. GRC will meet twice a month and determine the merit of each grievance brought to the committee. The GRC will resolve the grievance within 1 month of receiving the complaint. All decisions taken by the GRC will be communicated to complainant by the Nodal Officer.

87. The project GRM notwithstanding, an aggrieved person shall have access to the country's legal system at any stage, and accessing the country's legal system can run parallel to accessing the GRM and is not dependent on the negative outcome of the GRM. Alternatively, if the grievance is related to land acquisition, resettlement & rehabilitation2, the APs can approach the Land Acquisition, Rehabilitation and Resettlement Authority (LARRA) of Madhya Pradesh, established under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation, and Resettlement Act, 2013.

88. Record-keeping. PIU will keep records of grievances received, corrective actions taken and the final outcome. The number of grievances recorded and resolved and the outcomes will be displayed/disclosed in the PIU office, ULB offices, and on the web.

1 Grievance redress committee (GRC) will be formed at town-level with members composed of: ULB Chairperson, ULB CMO, Environmental Specialist of PMC, PIU Dy.PM and PIU Community Development Officer. 2 the Authority admits grievance only with reference to the LA and R&R issues under the new Act

VIII. ENVIRONMENTAL MANAGEMENT PLAN

A. Implementation Arrangements

89. Urban Development and Housing Department (UDHD) of Government of Madhya Pradesh will be the Executing Agency for the Program, responsible for management, coordination and execution of all activities funded under the loan. Implementing Agency will be the recently established Madhya Pradesh Urban Development Company (MPUDC), a wholly owned subsidiary of GoMP. A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. Program Implementation Units (PIUs) will support the PMU with flexibility to redeployment depending upon the implementation requirements.

90. The PMU and PIUs will be supported by several teams of Design Consultants in preparation of preliminary engineering designs.

91. Water Resource Review Committee (WRRC) is constituted to undertake a thorough review of the source when recommended by the Design Consultant in regard to techno- economic feasibility and sustainability especially ensuring climate change resilience, and Technical Review Committee (TRC) to review and approve the preliminary designs developed by the Design Consultants.

92. Program Management Consultant (PMC) centrally located in PMU and with field teams located in PIUs shall be responsible for implementation of the Program. All infrastructure contracts will be procured through performance-based contracts (PBCs) and include build- operate (BO) framework. Based on the preliminary designs prepared by Design Consultants, the DBO (design-build-operate) Contractor will design, construct, commission and operate for 10 years, after which it will be transferred to the respective ULB.

93. Two Committees - an Empowered Committee cum Executive Committee and a Technical Clearance and Tender Committee have been constituted by the Government to be responsible for effective and timely implementation of the Program.

94. Safeguards. At PMU, there will be two safeguard specialists: (i) Project Officer (Environment) and (ii) Social & Gender Offer, who will responsible for compliance with the environmental and social safeguards in program implementation. PO (Environment) will have overall responsibility in implementation of the investment program as per the Environmental Assessment & Review Framework (EARF) agreed between ADB and the government. At individual subproject level, PO will ensure that environmental assessment is conducted, and a project-specific is prepared and implemented, and the compliance, and corrective actions, if any are reported as required.

B. Environmental Management Plan

95. An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels.

96. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between MPUDC, project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail

72 specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

97. The contractor will be required to submit to PIU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP.

98. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

99. For civil works, the contractor will be required to (i) carry out all of the mitigation and monitoring measures set forth in the approved SEP; and (ii) implement any corrective or preventative actions set out in safeguards monitoring reports that the employer will prepare from time to time to monitor implementation of this IEE and SEP. The contractor shall allocate budget for compliance with these SEP measures, requirements and actions.

100. The following tables show the potential environmental impacts, proposed mitigation measures and responsible agencies for implementation and monitoring.

73

Table 10: Design Stage Environmental Management Plan Field Anticipated Mitigation Measures Responsible for Cost Impact Implementation and Source of Funds Design of water Unsustainable • Discontinuation of current unsustainable groundwater source and creating These measures Part of supply system source; new water supply system based on a nearest surface water sources are already project resource & (Gandhi Sagar Dam for Kukdeshwar and Rupaniyakhal Dam for Nagri) included in the costs energy use • Continuation of existing sources at Sarwaniya Maharaj and Nayagaon, preliminary which are sustainable designs. • Recovering wash water from treatment process • Treatment and reuse of sludge from treatment process DBO Contractor • Minimizing water losses from pipelines by perfect jointing and alignments (DBOC)to follow, using appropriate techniques (HDPE pipes up to 150 mm dia joined by enhance where electro fusion couplers using on-site electro fusion welding, and all higher possible. dia pipes by on site butt welding) • Designing the entire system to maintain optimal flow and terminal PMU to ensure pressure, and optimising the overall energy usage compliance. • Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies • Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor • Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections • Using low-noise and energy efficient pumping systems Site safety Kukdeshwar • Houses are located close to the proposed OHT site and proper measures are required during construction to avoid any risks due to excavation and/or working on heights. Proper shoring/barricading/safety nets etc., shall be used Fencing / compound wall shall be provided all-around. A peepal tree of local significance (used by local women for religious ceremonies) is in the site, and layout plan of OHT to be drawn such that the tree is not disturbed and protected. Nayagaon • This is potentially risky considering that source is quarry pit.Intake shall be appropriately designed considering the safety of O&M staff and

74

Field Anticipated Mitigation Measures Responsible for Cost Impact Implementation and Source of Funds equipment. Proper arrangements shall be made to avoid risks during construction as well as operation. Sarwaniya Maharaj • Provide appropriate safety measures at the open well – fencing/compound, gate, jaali/ fabricated protective metal cover etc., • WTP and OHT sites are within a school campus. A proper compound wall around the facility shall be provided, and entrance to the WTP should be separated from that of school. Compound wall/fencing shall be erected prior to start of any excavation work, so that no children enter the construction area. • Land adjacent to WTP site is covered shrubs, bushes (though privately owned it looks like a forest), and there is likely hoods of wild animals. Boundary wall shall be erected first, and no worker shall be allowed to remove any trees/vegetation in the adjacent land. Water Project • Obtain permission from Water resources department, GoMP PMU & respective No abstraction from sustainability o Gandhi Sagar Dam for Kukdeshwar and Rupaniyakhal Dam for Nagri– Nagar Parishads costs; Dam & water use permission / water allocation for water abstraction from dams and (process already scope conflicts construction of intakes initiated) of IA • CCI permission to use the lime stone pond as source Waste Environmental • Obtain consent from MPPCB for WTPs at Kukdeshwar, Nayagaon, PMU / Nagar No generation from pollution Sarwaniya Maharaj and Nagri prior to start of construction Parishad; DBOC costs; WTP operations to prepare scope application, and of IA & assist as required DBO Chlorine usage Chlorine • Provide the following measure at the chlorine application unit: These measures Project as disinfectant handling & o Chlorine neutralization pit with a lime slurry feeder are already Costs at WTPs application o Proper ventilation, lighting, entry and exit facilities included in the Kukdeshwar, risk – health o Facility for isolation in the event of major chlorine leakage (if needed) preliminary Nayagaon, &safety risk to o Personal protection and safety equipment for the operators in the designs. Nagri and workers and chlorine plant Sarwaniya general public o Provide training to the staff in safe handling and application of DBOC to follow, enhance where Maharaj chlorine; this shall be included in the contract of Chlorinator supplier o Supplier of Chlorinator equipment shall provide standard operating possible. manual for safe operation and as well as maintenance and repairs;

75

Field Anticipated Mitigation Measures Responsible for Cost Impact Implementation and Source of Funds preferably these shall be provided both in English and Hindi PMU to ensure Languages compliance.

Table 11: Pre-Construction State Environmental Management Plan Field Anticipated Impact Mitigation Measures Responsible for Cost and Implementation Source of Funds EMP Unsatisfactory • Appoint EHS supervisor and designate 1 EHS coordinator DBO contractor Cost for Implementation compliance to EMP (among the technical staff) in each town implementation & reporting • Ensure that all pre-construction activities are complete prior of mitigation to start of construction work measures • Ensure timely submission of monitoring reports responsibility of contractor. Source water Unsuitable raw water • Conduct comprehensive water quality monitoring program DBO Contractor Cost for quality - quality as per Appendix 14B, and confirm the water quality is implementation Nayagaon suitable for domestic supply of mitigation source measures responsibility of contractor. Estimated cost INR 240,000 (cost involve in project cost) Utilities Damage/ • Identify and include locations of utilities in the detailed DBOC with PIU Project costs – disturbance to designs/drawings to prevent unnecessary disruption of collaboration. general telephone lines, services PMU to ensure construction electric lines, water • Prepare a contingency plan to include actions to be taken in compliance practice lines in project area case of unintentional interruption of services. Construction Disturbance / • No construction material storage/ancillary works shall be DBOC with PIU Project costs – works near damage to forest conducted in the forest area; this shall be limited to actual collaboration. general forest areas areas, wildlife construction area and the access roads construction • No labour camps shall be located near forests (maintain PIU/ PMU to practice minimum 1km buffer) ensure • Limit the work to daylight hours only; no work after sunset compliance

75 76

Field Anticipated Impact Mitigation Measures Responsible for Cost and Implementation Source of Funds • No workers /personnel shall enter forest areas; it is the DBOC responsibility to take necessary precautions & prevent workers removing/damaging trees/vegetation, hunting animals • Create awareness among workers on environment & safety • No high noisy works shall be conducted • Barricade the construction area properly so that no wild animals entre the work area Construction Degradation of water • Schedule the works during summer where there is no/low DBOC to follow Project costs – works in dam quality – construction water at the location general work Rupaniyakhal • Select a construction methodology that is least disturbing, PIU/ PMU to construction Dam and appropriate for the in-situ soil condition, and able to ensure practice complete the construction work prior to onset of monsoon compliance • Erect temporary barriers, if work is constructed in water, to form enclosed construction area with least disturbance • Allow adequate time to settle the distributed solids to prior to pumping out water; only clear/clarified water shall be pumped back into the reservoir; any silt laden water should be pumped to a silt pond • Avoid/minimize use of fuels, chemicals and lubricants; ensure no spillage Construction Conflicts with local • Prioritize barren, waste, infertile, vacant lands within the DBOCto identify Part of project work camps, community; area, locations following costs stockpile disruption to traffic • Shall not be located in productive agricultural lands, water the criteria areas, storage flow and sensitive bodies, natural drainage channels, flood plains & areas and receptors groundwater recharge areas, forests, vegetative lands, etc. PIU to ensure waste disposal • Locate at sites that will not promote instability, flooding and compliance and areas result in destruction of natural drainage, vegetation, approve irrigation, & drinking water supply; • For private lands, obtain land owner’s (not lessees) written consent; indicate the requirement for reinstatement to original • Site should have a minimum buffer of 0.5 – 1 km from all socially, environmentally sensitive areas (eg., residential, socio-cultural areas & water bodies (0.5 km), forests (1km), etc.,)

77

Field Anticipated Impact Mitigation Measures Responsible for Cost and Implementation Source of Funds • Take extreme care in selecting sites to avoid direct disposal to water body which will inconvenience the community. • Document site’s pre-project conditions Sources of Extraction of • Obtain material only existing borrow sites/quarries already DBOC to identify Part of project Materials materials can disrupt permitted by the Department of Mines and Geology; sources that have costs natural land contours • If new quarries sites/quarries are necessary, contractor shall all permits, if and vegetation be obtain all necessary permissions as per the law in force. required, obtain resulting in • Contractor to obtain construction materials only after written permits, and accelerated erosion, permission / approval of PIU for respective sources submit to PIU disturbance in • Maintain a construction material register at the site natural drainage PIU to check and patterns, ponding approve and water logging, and water pollution. Consents, Failure to obtain • Obtain all necessary consents, permits, clearance, NOCs, PMU / PIU to Part of project permits, necessary consents, etc required for the project prior to award of contact or start obtain project costs clearances, permits, NOCs, etc. of civil works, as necessary. clearances; NOCs, etc. can result to design • Include in detailed designs, drawings and documents all DBOC to provide revisions and/or regulatory conditions and provisions, where required necessary stoppage of works • Contractor to identify & obtain all necessary approvals, assistance including in compliance with labour laws, before start of construction; DBOC to obtain • Contractor to acknowledge in writing to PIU and provide construction copies of all obtained permits, clearance, NOCs, etc. permits & PIU to ensure Asbestos Health risk due to • Obtain details from PHED/NPson location ofunderground DBOC in Part of project Cement Pipes exposure to AC pipes coordination with costs asbestos materials • Locate the new piper carefully to avoid encountering AC PIU and ULB pipes • Leave the AC pipes undisturbed in the ground.

77 78

Table 12: Construction Stage Environmental Management Plan Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Mitigation Funds EMP Implementation Irreversible impact • Project manager and all key workers will DBOC Cost of EMP Training to the environment, be required to undergo training on EMP Implementation Orientation workers, and implementation including spoils/waste PMC Construction Training to contractor is community management, Standard operating and responsibility of PMU. procedures (SOP) for construction Environmental works; occupational health and safety Specialists to Other costs responsibility (OH&S), core labor laws, applicable conduct the of contractor. environmental laws, etc. training Air Quality Emissions from • Control dust by water sprinkling on DBO Contractor Cost for implementation of construction exposed soil, stock stockpiled material mitigation measures vehicles, equipment, on site responsibility of contractor. and machinery used • Barricade area, provide wind sheets for installation of • Use tarpaulins to cover sand and other Air quality monitoring costs pipelines resulting to loose material when transported by are included in the EMP dusts and increase trucks; costs of project in concentration of • Clean wheels and undercarriage of haul vehicle-related trucks prior to leaving construction site pollutants such as • Prevent entry of traffic, public in carbon monoxide, construction area sulfur oxides, • Fit all heavy equipment, and machinery particulate matter, with air pollution control devices which nitrous oxides, and are operating correctly; all the vehicle hydrocarbons. shall meet the emission norms and shall have valid pollution under control (PUC) certificate (Appendix 3) • Conduct air quality monitoring as per the monitoring plan

Surface water quality Mobilization of • Avoid earthworks during the rainy DBO Contractor Cost for implementation of settled silt materials, season mitigation measures and chemical • Avoid stockpiling of earth fill especially responsibility of contractor. contamination from during the monsoon season unless fuels and lubricants covered by tarpaulins or plastic sheets; Water quality monitoring during installation of • Reuse excess spoils & materials in the costs are included in the pipelines can construction as far a possible EMP costs of project contaminate nearby

79

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Mitigation Funds surface water • Identify disposal sites prior to quality. construction & dispose construction waste only at designated areas • Install temporary silt traps basins along the drainage leading to the water bodies; • Place storage areas for fuels and lubricants away from any drainage leading to water bodies; • Conduct surface quality inspection according to the Environmental Management Plan (EMP). Noise Levels Increase in noise • Conduct noise generating activities (eg, DBO Contractor Cost for implementation of level due to earth- cc road cutting) during day time mitigation measures moving and • Minimize noise from construction responsibility of contractor. excavation equipment (by using vehicle silencers, equipment, and the fitting jackhammers with noise-reducing transportation of mufflers, and use portable street barriers equipment, to minimise sound impact to surrounding materials, and sensitive receptor; people • Maintain maximum sound level not exceeding 80 decibels (dBA) when measured at a distance of 10 m or more from the vehicle/s. • Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity; • Consult local communities in advance to avoid working at sensitive times, such as religious and cultural festivals. Landscape and Impacts due to • Prepare and implement a Construction DBO Contractor Cost for implementation of aesthetics excess excavated Waste Management Plan mitigation measures earth, excess • Stockpiles, lubricants, fuels, and other responsibility of contractor. construction materials should be located away from materials, and solid steep slopes and water bodies; waste such as • Avoid stockpiling any excess spoils; removed concrete, dispose immediately to designated areas

79 80

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Mitigation Funds wood, packaging • Domestic solid waste generated at materials, empty construction camps and work sites shall containers, spoils, be properly managed (collected, oils, lubricants, and segregated, disposed properly); waste other similar items. should not burned • Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed through approved recyclers • Environmentally restore the work sites to at least pre-project conditions; PIU to approve in writing that site is restored Ecological Resources Loss of vegetation • Avoid removal of vegetation / tree cutting DBOContractor Cost for implementation of – Terrestrial and tree cover • If unavoidable, minimize as far as mitigation measures possible, and obtain tree-cutting permit responsibility of contractor. • Plant 10 trees for every one cut • At Kukudehswar OHT site, a peepal tree of local significance (used by local women for religious ceremonies) is in the site, and layout plan of OHT to be drawn such that the tree is not disturbed and protected. • In proposed WTP site at Kukudehswar, there are 2 big trees within the site, which are to be integrated into the layout design, and should not be cut. Land use Environmental • The impact due to change in land use will Not applicable Not applicable Issues due to land be negligible due to this project. use change Accessibility Traffic problems and • Confine work areas along the roads to DBO Contractor Cost for implementation of conflicts near the minimum possible extent; all the mitigation measures project locations activities, including material & responsibility of contractor. and haul road waste/surplus soil stocking should be confined to this area. Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately remove

81

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Mitigation Funds from site/ or brought to the as and when required • Leave spaces for access between mounds of soil; • Provide walkways and metal sheets where required to maintain access across for people and vehicles; • Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites; • Schedule transport and hauling activities during non-peak hours; • Keep the site free from all unnecessary obstructions; • Drive vehicles in a considerate manner; • Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids • Prepare and implement Traffic Management Plan where required (template is provided in Appendix 23) • Notify affected area by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints. • For works in very narrow roads o Inform the affected local population 1-week in advance about the work schedule o Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. o Provide pedestrian access in all the locations until normalcy is restored.

81 82

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Mitigation Funds Provide wooden/metal planks over the open trenches at each house to maintain the access. Socio-Economic – Impede the access • Do not obstruct access; provide DBO Contractor Cost for implementation of Income. of residents and temporary access, by leaving spaces in mitigation measures customers to nearby excavation, provide walkways and metal responsibility of contractor. shops sheets for people and vehicles where necessary to continue business • Increase workforce in the areas with predominantly institutions, place of worship, business establishment, hospitals, and schools; • Consult businesses and institutions regarding operating hours and factoring this in work schedules Socio-Economic – Generate temporary • Employ local persons in construction DBO Contractor Cost for implementation of Employment employment and work if manpower is available mitigation measures increase in local responsibility of contractor. revenue Occupational Health Occupational • Comply with all national, state and local DBO Contractor Cost for implementation of and Safety hazards which can core labor laws (see Appendix 6of this mitigation measures arise during work IEE) responsibility of contractor. • Implement site-specific occupational health and safety (OH&S) measures, such as the following • Provided personal protective equipment (PPE) to workers (like helmet, gumboot, safety belt, gloves, nose musk and ear plugs), and ensure that they are used • Conduct OH&S training workers/staff • Do no employ ad-hoc work procedures, follow best & acceptable work practices • Document work-related accidents • Provide qualified & easily accessible first-aid facilities all times at all sites

83

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Mitigation Funds • Secure all installations from unauthorized intrusion and accident risks; • Provide potable drinking water; • Provide clean eating areas where workers are not exposed to hazardous or noxious substances; • Provide H&S orientation training to all workers to ensure that they are apprised of the basic site rules of work at the site, PPEs, and preventing injuring to fellow workers; • Ensure that visitor/s do not enter hazard areas unescorted • Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; • Ensure moving equipment is outfitted with audible back-up alarms; • Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and • Disallow worker exposure to noise level greater than 85 dBA for a duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

83 84

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Mitigation Funds Community Health Traffic accidents • Plan routes to avoid times of peak- DBO Contractor Cost for implementation of and Safety. and vehicle collision pedestrian activities and high-risk areas. mitigation measures with pedestrians • Prevent public entry in to work areas responsibility of contractor. during material and through barricading and security guards waste transportation • Maintain regularly the vehicles and minimize potentially serious accidents caused by equipment malfunction or premature failure. • Provide road signs and flag persons to warn of on-going trenching activities. • In very narrow streets, conduct work section-wise (~100 m), and complete excavation, pipe laying and backfilling in minimum possible time (1 day preferably) Work Camps and Temporary air and • Establish camps only after site approval DBO Contractor Cost for implementation of worksites noise pollution from • Avoid cutting of trees/ clearing bushes mitigation measures machine operation, • Provide adequate drinking water, water responsibility of contractor. water pollution from for other uses, and sanitation facilities storage and use of • Ensure conditions of livability at work fuels, oils, solvents, camps are maintained at the highest and lubricants standards possible at all times; • Prohibit employees from poaching Unsanitary and poor wildlife and cutting of trees for firewood; living conditions for • Train employees in the storage and workers handling of materials which can potentially cause soil contamination; • Recover used oil and lubricants and reuse or remove from the site; • Manage solid waste according to the preference hierarchy: reuse, recycling and disposal to designated areas; • Ensure unauthorized persons specially children are not allowed in any worksite Post-construction Damage due to • Remove all spoils wreckage, rubbish, or DBO Contractor Cost for implementation of clean-up debris, spoils, temporary structures (such as buildings, mitigation measures excess construction shelters, and latrines) which are no responsibility of contractor. materials longer required

85

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Mitigation Funds • All excavated roads shall be reinstated to original condition. • All disrupted utilities restored • All affected structures rehabilitated/compensated • The area that previously housed the construction camp is to be checked for spills of substances such as oil, paint, etc. and these shall be cleaned up. • All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be topsoiled and regrassed • The contractor must arrange the cancellation of all temporary services. • Restore the work sites to pre-project conditions; PIU to approve in writing that site is restored

85 86

Table 13: Operation Stage Environmental Management Plan Field Anticipated Impact Mitigation Measures Responsible for Monitoring of Cost and Mitigation Mitigation Source of Funds Check for Loss of water, • Effective leak detection and water auditing DBO Contractor PIU and Operating blockage and increased demand to reduce the water losses respective Nagar costs leakage problems and inconvenience to Parishads reducing the consumers & general water losses public Water Impacts on public • Ensure protection of water source quality, Respective Nagar PMU in Operating contamination – health any entry of wastewater into the CCI pond Parishads coordination with costs raw water at Nayagaon should be checked WRD contamination at • Contamination of treated water during DBO Contractor source and transmission and distribution should be PIU and treated water prevented by quickly identifying, isolating respective Nagar during and repairing the leak section. Develop a Parishads transmission system of leak detection and rectification. • Conduct regular monitoring of raw & treated water and ensure that water supplied at all times meets the drinking water standards (Appendix 24) Discharge the Pollution of streams • Backwash water will be recirculate so no DBO Contractor PIU and Operating impurities and /drains wastewater generated from WTPs respective Nagar costs other solids • Maintain the mechanical parts as per the Parishads collected due to maintenance plan to avoid any hazards filtration and back wash Sludge Land and water • Collect the sludge from WTP units, dry in DBO Contractor PIU and Operating generation pollution, impacts on sludge drying beds, and reuse / dispose respective Nagar costs health & environment safely as per the design Parishads Increased in Water pollution, and • Sanitation facilities needs to be improved Respective Nagar PMU To be sewage impacts on public at community level and at the town level to Parishads identified - generation health and meet the increased sewage demand respective environment NPs Generation of Impacts on public • Collect solid wastes and dispose to DBO Contractor PIU and Operating waste materials health and approved disposal yards respective Nagar costs environment Parishads

87

Field Anticipated Impact Mitigation Measures Responsible for Monitoring of Cost and Mitigation Mitigation Source of Funds Occupational Health, social and • Provide appropriate PPE to workers& DBO Contractor PIU and Operating health and safety economic impacts on training on its proper use respective Nagar costs the workers • Use fall protection equipment when Parishads working at heights. • Maintain work areas to minimize slipping and tripping hazards. • Implement a training program for operators who work with chlorine regarding safe handling practices and emergency response procedures. • Prepare escape plans from areas where there might be a chlorine emission. • Install safety showers and eye wash stations near the chlorine equipment and other areas where hazardous chemicals are stored or used. • Prohibit eating, smoking, and drinking except in designated areas.

Table 14: Construction Stage Environmental Monitoring Plan Monitoring field Monitoring location Monitoring parameters Frequency Responsibility Cost & Source of Funds Construction All work sites Implementation of dust Regularly as required Supervising Part of TOR of PIU, disturbances, control, noise control, during construction; staff and PMC and PMU nuisances, public traffic management, & checklist to be filled safeguards & worker safety, safety measures. monthly once specialists Site inspection checklist to review implementation is appended at Appendix 25 Ambient air quality 12 locations • PM10, PM2.5 NO2, Once before start of DBO Contractor Cost for (1 at WTP + 2 SO2, CO construction and then implementation of location in each Quarterly (yearly 4- monitoring measures town – exact times) during construction responsibility of location to be (2 year period contractor considered)

87 88

finalized prior to (108 samples x 5000 start of per sample = INR construction) 540,000) Ambient noise 12 locations • Day time and night time Once before start of DBO Contractor Cost for (1 at WTP + 2 noise levels (24 hours) construction and then implementation of location in each Quarterly (yearly 4- monitoring measures town – exact times) during construction responsibility of location to be (2 year period contractor considered) (108 samples x finalized prior to 1500 per sample = start of INR 162,000) construction) Surface water 4 locations • pH, Oil & grease, Cl, Once before start of DBO Contractor Cost for quality (1 location in each F, NO3, TC, FC, construction and then implementation of town – exact location Hardness, Turbidity half-yearly (yearly 2- monitoring measures to be finalized prior BOD, COD, DO, Total times) during construction responsibility of to start of Alkalnity (2 year period contractor construction) considered) (20 samples x 4000 per sample = 80,000) Nayagoan source Six sampling points • Colour , Odour , 2 times during detailed DBO Contractor Cost for water quality – shall be selected in Turbidity,Temperature, engineering design or implementation of comprehensive the pond– one each pH, Total Hardness, prior to start of work monitoring measures monitoring on four sides (10-20 Electrical conductivity, (i) pre-monsoon and (ii) responsibility of program m inside from the Total dissolved & post-monsoon contractor boundary, 2 in the suspended solids, (12 samples x upper and lower Nutrients - NH3-N, 20000 per sample = centre of the lake. NO2 + NO3, Total P; INR 240,000). Cost Sample shall be DO; BOD; COD; Iron; includes the collected from at Chlorides; Calcium; expenses towards least 4-5 m below the Magnesium; Sulphate; collection of samples water surface or as Potassium; CO3, appropriate during HCO3; Nitrate; the sampling. Fluoride; Mercury; Cadmium; Lead; Zinc; Chromium; Pesticides; Aluminum; Boron; Total and Faecal Coliforms

89

Table 15: Operation Stage Environmental Monitoring Plan

Monitoring field Monitoring Monitoring parameters Frequency Responsibility Cost & location Source of Funds Source water Near intake point pH, Cl, F, NO3, TC, FC, Hardness, Yearly twice DBO O&M costs quality at all sources Turbidity BOD, COD, DO, Total (pre & post Contractor Alkalnity monsoon) heavy metals & pesticides Monitoring of Consumer end- pH, Nitrite, Nitrate, Turbidity BOD, Monthly DBO O&M costs quality of water random sampling Total Alkalnity, Total coliform and once Contractor supplied to in all zones Feacal coliform consumers

89 90

C. EMP Compliance Responsibilities

101. PIU Responsibilities. Safeguard Officer will be supported by PMC, which will be staffed with an Environmental Specialist. Key tasks and responsibilities of the PO (Environment) include the following:

Bidding stage: (i) Prior to invitation of bids for civil works contract, ensure that

a. Water Resources Department (WRD) permission is obtained for sourcing water from Gandhisagar Dam, Rupaniyakhal Dam and Open Wells in Morewan Dam, b. Permission from CCI for souring water from Lime Stone Quarry pond in Nayagaon c. Consent for establishment (CFE) is obtained from MPPCB for WTP construction in all tons

(ii) Ensure that EMP is included in bidding documents and civil works contracts (iii) Ensure that the bid/contract documents include specific provisions requiring contractors to comply with all applicable labor laws and core labor standards including:

a. Labour welfare measures and provision of amenities b. prohibition of child labor as defined in national legislation for construction and maintenance activities; c. equal pay for equal work of equal value regardless of gender, ethnicity, or caste; d. elimination of forced labor; e. the requirement to disseminate information on sexually transmitted diseases, including HIV/AIDS, to employees and local communities surrounding the project sites. (iv) Ensure that staff required for implementation of EMP is included in the bid requirements (v) Ensure that EMP cost is included in the project cost (vi) In the pre-bid meeting, provide insight into the EARF requirements, IEE update, EMP measures, and overall compliance requirements to the bidders

Construction stage: (i) Facilitate and ensure that all necessary environmental clearances/permissions, including that of contractor’s are in place prior to start of construction (ii) Organize an induction course for the training of contractors, preparing them on EMP implementation, environmental monitoring, and on taking immediate action to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation. (iii) provide oversight on environmental management aspects of subprojects and ensure EMPs are implemented by PIU and contractors (iv) Supervise and provide guidance to the PIUs to properly carry out the environmental monitoring as per the EMP (v) Oversee grievance redress mechanism to address any grievances brought about in a timely manner; ensure that records are properly maintained (vi) Consolidate monthly environmental monitoring reports from PIU and submit semi-annual monitoring reports to ADB (vii) Oversee site closures to ensure that all work / facility sites are restored properly prior to issuing work completion certificate to the contractor

91

Operation stage: (i) Ensure and consent for operation (CFO) is obtained from MPPCB for WTP prior to start of operation

102. PIU Responsibilities. PIU will be headed by a Project Manager and supported by PMC. An Assistant Project Manager of PIU will be given additional responsibilities of safeguard tasks and will be designated as Assistant Environmental Officer (ASO). ASO will be supported by PDMC Environmental Specialist and Environmental Coordinator. Key tasks and responsibilities of the ASO for this subproject include the following:

(i) Provide necessary support to PIU and Nagar Parishads in obtaining permission from WRD and MPPCB; liaison with PMU and regulatory agencies (ii) Oversee day-to-day implementation of EMPs by contractors, including compliance with all government rules and regulations, take necessary action for obtaining rights of way (iii) Oversee environmental monitoring by contractors (iv) Take corrective actions when necessary to ensure no environmental impacts (v) Submit monthly environmental monitoring reports to PMU (vi) Conduct continuous public consultation and awareness (vii) Address any grievances brought about through the grievance redress mechanism in a timely manner as per the EMP

103. Contractor’s responsibilities.

Bidding stage: (i) Understand the EMP requirements and allocate necessary resources (budget, staff, etc.,) (ii) Understand the regulatory compliance requirements related to labour welfare, safety, environment etc.,

Design stage: (i) Review the IEE Report including the REA checklist, category and the EMP, and conduct site visits to understand the environmental sensitivity of the project sites. (ii) Update the REA checklist, confirm the category, and update/revise the IEE Report of the project reflecting the changes /amendments /additions that are effected in the project during the detailed design (iii) Update / revise and finalize the EMP (iv) Provide all necessary technical assistance to PIU / ULB in obtaining regulatory clearances/approvals. (v) Ensure that all design-related measures of the EMP, and conditions, if any, of government regulatory agencies (like MPPCB consent conditions) are duly included in the final designs. (vi) Conduct comprehensive water quality monitoring tests for Nayagaon source and confirm water quality is suitable prior to start of work

Construction stage: (i) Ensure that all regulatory clearances (both project related and contractor related) are in place before start of the construction work. (ii) Mobilize EHS officer and Archaeological supervisor prior to start of work (iii) Confirm with PIU availability of rights of way at all project sites prior to start of work. (iv) Prepare and submit: a. Construction waste management (CWM) plan b. Traffic management (TM) plan (v) Implement the mitigation measures as per the EMP including CWM & TM Plans

92

(vi) Follow the EMP measures/guidelines for establishment of temporary construction camps, construction waste disposal sites, and material borrow areas, etc., (vii) Implement EMP and ensure compliance with all the mitigation and enhancement measures (viii) Conduct environmental monitoring (air, noise, water etc.,) as per the EMP (ix) Undertake immediate action as suggested by PIU / PMU / PMC to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation (x) Submit monthly compliance reports on EMP implementation (xi) Act promptly on public complaints and grievances related to construction work and redress in a timely manner in coordination with PIU (xii) Comply with applicable government rules and regulations

Operation stage: (i) Obtain CFO from MPPCB in coordination with the ULB, and comply with MPPCB conditions, if any, during the operation phase (ii) Implement the operation phase EMP including the monitoring plan (iii) Submit quarterly EMP implementation report

D. Training Needs

104. The following Table 17 presents the outline of capacity building program to ensure EMP implementation. The estimated cost is Rs.275,000 (excluding trainings of contractors which will be part of EMP implementation cost during construction) to be covered by the project’s capacity building program. The detailed cost and specific modules will be customized for the available skill set after assessing the capabilities of the target participants and the requirements of the project by the ES of PDMC.

Table 16: Outline Capacity Building Program on EMP Implementation Description Target Participants& Estimate Cost and Source Venue (INR) of Funds 1. Introduction and Sensitization to All staff and consultants - Included in the Environmental Issues (1 day) involved in the project overall program - ADB Safeguards Policy Statement cost - Government of India and Madhya At PMU, Bhopal Pradesh applicable safeguard laws, (combined program for all regulations and policies including but subprojects) not limited to core labor standards, OH&S, etc. - Incorporation of EMP into the project design and contracts - Monitoring, reporting and corrective action planning

93

Description Target Participants& Estimate Cost and Source Venue (INR) of Funds 2. EMP implementation (1/2 day) All PIU staff, contractor - Part of overall - EMP mitigation & monitoring staff and consultants program costs – measures involved in the PMC will conduct -Roles and responsibilities Kukdeshwar – Nayagaon at PIU office - Public relations, - Consultations – Sarwaniya Maharaj - - Grievance redress Nagri subproject Part of scope of - Monitoring and corrective action work of PMU, planning At PIU PIU, PMC & - Reporting and disclosure DBOC - Construction site standard operating procedures (SOP) - AC pipe protocol - Traffic management plan - Waste management plan - Site clean-up & restoration 3. Contractors Orientation to Workers Once before start of work, - Contractors cost (1/2 day) and thereafter regular - Environment, health and safety in briefing every month project construction once. Daily briefing on safety prior to start of work

All workers (including unskilled laborers)

E. Monitoring and Reporting 105. During the detailed design stage, DBO Contractor should confirm PMU the mobilization of Environmental Expert for IEE update and integrating design stage EMP into designs. DBO will confirm through comprehensive water quality tests at Nayagaon water source, prior to start of work, that water quality is fit for domestic supply after conventional treatment.

106. Prior to commencement of the works, the contractor will submit a compliance report to PIU that all identified pre-construction mitigation measures as detailed in the EMP are undertaken. Contractor should confirm EHS supervisor is mobilized and EHS coordinators are designated for each town for effective implementation of the EMU. PMU with the assistance of the PMC will review the report and permit commencement of works.

107. During construction, results from internal monitoring by the contractor will be reflected in their monthly EMP implementation reports to the PIU. PMU will review and advise contractors for corrective actions if necessary. Quarterly report summarizing compliance and corrective measures taken will be prepared by PMC field team at PIU and submitted to PMU (Appendix 26). During operation, the contractor will conduct management and monitoring actions as per the operation stage EMP, and submit to PMU and ULB a quarterly report on EMP implementation and compliance.

108. Based on monthly & quarterly reports and measurements, PMU will submit to ADB, semi- annual (6-monthly) Environmental Monitoring Reports (EMR).Once concurrence from the ADB is received the report will be disclosed on the MPUDC and PMU websites.

109. ADB will review project performance against the MPUSIP commitments as agreed in the legal documents. The extent of ADB’s monitoring and supervision activities will be commensurate

94 with the project’s risks and impacts. Monitoring and supervising of social and environmental safeguards will be integrated into the project performance management system

F. EMP Implementation Cost 110. Most of the mitigation measures require the contractors to adopt good site practice, which should be part of their normal procedures already, so there are unlikely to be major costs associated with compliance. The costs which are specific to EMP implementation and are not covered elsewhere in the projects are given below. The total costs are estimated at INR 1.84 million, which are to be covered by contractor costs.

Table 17: Cost Estimates to Implement the EMP Particulars Stages Unit Total Rate Cost Costs No. (INR) (INR) Covered By A Implementation staff 1 EHS Supervisor Construction per 24 30,000 7,20,000 Civil works month contract Subtotal (A) 7,20,000 B Mitigation Measures 1 Consent for Pre & Post- Lump 300,000 Project establishments & constructio sum costs consent for operation n from MPPCB 2 Provision for tree Construction Per tree 100 1,000 100,000 DBO cutting & compensatory contract plantation Measures 3 Traffic management at Construction Lump - - 100,000 Civil works work sites(Pavement sum Contract Markings, Channelizing Devices, Arrow Panels and Warning Lights, barricading); Preparation of plans etc.) Subtotal (B) 5,00,000 C Monitoring Measures 1 Nayagaon source water Prior to start Per 12 20,000 240,000 Civil works quality comprehensive of work sample contract (cost monitoring involve in project cost)

2 Air quality monitoring Construction per 90 5,000 540,000 Civil works sample contract

3 Noise levels monitoring Construction Per 90 1,500 162,000 Civil works sample Contract

4 Surface water monitoring Construction Per 50 4,000 80,000 Civil sample works contract

Subtotal (C) 10,22,000 D Capacity Building 1 Training on EMP Pre- lump 100,000 PMU . Implementation construction sum

95

2 Preparation of plans and Pre- Lump 50,000 DBO protocols (traffic constructio sum contract management plan, waste n (spoils) management plan etc., chance find protocal 3 Contractors Orientation to Prior to Lump 25,000 DBO . Workers on EMP dispatch to sum contract implementation Subtotal (D) 175,000 Total (A+B+C+D) 2,417,000

96

IX. CONCLUSION AND RECOMMENDATIONS

111. The process described in this document has assessed the environmental impacts of all elements of the Kukdeshwar, Nayagaon, Sarwaniya Maharaj and Nagri water supply improvement subproject. All potential impacts were identified in relation to pre-construction, construction, and operation phases. Planning principles and design considerations have been reviewed and incorporated into the site planning and design process wherever possible; thus, environmental impacts as being due to the project design or location were not significant.

112. Environmental impacts as being due to the project design or location are not significant. The proposed water supply schemes include design of new water sources for two towns (Kukdeshwar and Nagri), and continuation of existing sources in the remaining 3 towns (Sarwaniya Maharaj and Nayagaon). Source analysis conducted on these sources confirmed that source is sustainable, and there are unlikely to have any adverse impacts on environment or existing uses and unlikely to create social conflicts. Yield tests are conducted on open wells at dowmstream of Morwan Dam for Sarwaniya Maharaj, and confirmed that water is adequate to meet the demand. Water will be sourced from existing dams (Gandhisagar Dam for Kukdeshwar and Rupaniyakhal Dam for Nagri), which have comparatively large storage, and necessary water allocation will be obtained from the Water Resources Department.

113. In Nayagaon, existing source – an abandoned lime stone quarry pond of a Cement Plant, which in use for many years, will be continued. Random water quality test conducted during the project preparation indicated that the water quality is suitable for domestic supply after conventional treatment. However, considering the nature and location of source within a cement factory compound receiving runoff also from the factory areas, a comprehensive water quality testing program is suggested in the IEE to confirm the water quality, and this will be conducted prior to the start of work.

114. There are no sensitive features like forests near the project sites, except a protected forest near the raw water pipeline location, however, no works will encroach into forest, as the forest is fenced along the road, and pipeline works will be confined to the road right of way. Therefore, no significant impacts envisaged. General precautions like refilling trench after the day’s work is suggested.

115. During the construction phase, impacts mainly arise from the construction dust and noise, the need to dispose of large quantities of waste soil and import of construction material, and from the disturbance of residents, businesses, traffic and important buildings by the construction work. The social impacts (access disruptions) due to construction activities are unavoidable, as the residential and commercial establishments exist along the roads where pipes will be laid. As some of the works are conducted in water bodies (intake in dam), there is a risk of water contamination, river bed damage, etc. Appropriate measures are suggested.

116. Anticipated impacts of water supply during operation and maintenance will be related to detection and repair of leaks, pipe bursts. These are, however, likely to be minimal, as proper design and selection of good quality pipe material shall mean that leaks are minimal. Leak repair work will be similar to the pipe-laying work. Appropriate measures to deal with backwash water and sludge from WTP is included in the project design. Application and handling of chlorine gas will involve certain risks, and appropriate measures are suggested for safe application. The DBO Contractor will implement the operation stage EMP during contract period.

97

117. The public participation processes undertaken during project design ensured stakeholders are engaged during the preparation of the IEE. The planned information disclosure measures and process for carrying out consultation with affected people will facilitate their participation during project implementation.

118. The project’s grievance redress mechanism will provide the citizens with a platform to redress of their grievances, and describes the informal and formal channels, time frame, and mechanisms for resolving complaints about environmental performance.

119. The EMP will assist the PMU, PIU, PMC and DBO contractor in mitigating the environmental impacts, and guide them in the environmentally sound execution of the proposed project.

120. A copy of the EMP/approved SEP shall be kept on-site during the construction period at all times. The EMP shall be made binding on all contractors operating on the site, and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document shall constitute a failure in compliance.

121. The project will benefit the general public by contributing to the long-term improvement of water supply systems and community livability in Kukdeshwar, Nayagaon, Sarwaniya Maharaj and Nagri.

122. Therefore, as per ADB SPS, the project is classified as environmental category B and does not require further environmental impact assessment. However, to conform to government guidelines, the project requires (i) permission of WRD, GoMP for water abstraction from Gandhi Sagar Dam, Rupaniyakhal Dam, and for Open wells in d/s of Morewan dam,, (ii) CCI permission for drawing water from CCI lime quarry pond, and(iii)Consent for Establishment (CFE) and Consent for Operation (CFO) for WTPs in all 5 towns from MPPCB. These permissions/approvals shall be obtained.

123. Comprehensive water quality tests will be conducted by for Nayagaon CCI source to confirm water quality is fit for supply. This IEE shall be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

98

APPENDIX 1 REA CHECK LIST

KUKDESHWAR TOWN Country/Project: India/Madhya Pradesh Urban Services Improvement program- Kukdeshwar- Water Supply Subproject Sector/Division: Urban Development & Environment Department/MPUDC Screening Questions Yes No Remarks A. PROJECT SITING IS THE PROJECT AREA As Kukdeshwar is having average density 4616/SqKm. Project covers entire town including the density population areas. There are no major negative impacts envisaged because pipeline will be located in unused • Densely populated? Government lands along side the existing roads and can be constructed without causing disturbance to houses and commercial establishments. In narrow streets disruption to road users is likely and measures like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels.WTP is located at on Rampura road in Kukdeshwar which is less dense area ,so no negative  impact envisaged. • Heavy with development activities?  No • Adjacent to or within any environmentally sensitive areas?  No The history of Kukdeshwar is believed to be about • Cultural heritage site/religious 1050yrs old. City is famous for its importance  SahastramukSehwarBhagwan temple app.400 yrs old. • Protected area  No • Wetland  No • Mangrove  No • Estuarine  No • Buffer zone of protected area  No • Special area for protecting biodiversity  No • Bay  No B. POTENTIAL ENVIRONMENTAL IMPACTS Will the project cause… • Pollution of raw water supply from upstream wastewater There are no significant water pollution sources in the discharge from communities, catchment. Raw water quality is tested and found that it industries, agriculture, and  is suitable for Domestic use. soil erosion runoff?

99

• Impairment of historical /cultural monuments/areas, and  loss/damage to these sites? No Hazard of land subsidence • Not applicable, subproject does not involve groundwater caused by excessive ground abstraction water pumping?  • Social conflicts arising from Project does not involve land acquisition /displacement displacement of communities  .No social conflicts envisaged. • Conflicts in abstraction of raw water for water supply with other No, the water will be abstracted with due permission of beneficial water uses for surface Water Resource Department .Gandhi Sagar dam having and ground waters?  gross storage capacity of 7746 MCM and it is presently used for irrigation purpose & net capacity required for Kukdeshwar. Water Supply scheme demand is 0.60MCM. • Unsatisfactory raw water supply (e.g. excessive pathogens or mineral Raw water Quality is tested and found that it is suitable constituents)?  for Domestic use. • Delivery of unsafe water to distribution system?  Water will be treated and disinfected prior to supply. • Inadequate protection of intake works or wells, leading to Water is abstracted from Gandhi Sagar Dam there are no pollution of water supply?  major polluting sources in the catchment • Over-pumping of ground water, leading to salinization and No Ground water pumping is required as Surface water ground subsidence?  source is selected for the project • Excessive algal growth in Regular cleaning of storage tanks will be conducted storage reservoir?  during operation. Increase in production of • As per CPHEEO manual the rate of water supply is sewage beyond capabilities of 70lpcd for the town where sewerage scheme is not community facilities?  anticipated. • Inadequate disposal of sludge Appropriate provision for sludge drying and disposal is from water treatment plants?  included in the project • Inadequate buffer zone around pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities?  No • Impairments associated with transmission lines and access roads?  No • Health hazards arising from Measures for safe handling of Chlorine are included inadequate design of facilities for \receiving, storing, and handling of chlorine and other hazardous chemicals? 

100

• Health and safety hazards to workers from the management of Measures for safe handling of Chlorine are included chlorine used for disinfection and other contamination  • Dislocation or involuntary There is no resettlement of people for project resettlement of people  implementation. The contractor will be utilizing the local labour forces as Social conflicts between • far as possible; in case if it is unavoidable, labour camps construction workers from other and facilities will be provided appropriately. No conflicts areas & community workers  envisaged. • Noise and dust from construction Dust suppression measures such as water sprinkling will activities  be employed Excavation & Laying pipelines along public road will • Increased road traffic due to interfere with the traffic. interference of construction Construction material transport will increase traffic activities? within city and dumping construction material on road cause traffic congestion. Proper traffic & Construction planning will be ensured to  minimize the interference. Construction work during monsoon shall be carried out • Continuing soil erosion, silt runoff with due care so that silt run off due to construction from construction operation  operation is prevented. • Delivery of unsafe water due to poor O&M treatment processes (especially mud accumulations in  Appropriate O&M will be conducted. filters) and inadequate

chlorination due to lack of

adequate monitoring of chlorine residuals in distribution systems? • Delivery of water to distribution system, which is corrosive due to inadequate attention to feeding of corrective chemicals?  Not envisaged • Accidental leakage of Chlorine gas  Measures for safe handling of chlorine are included. • Excessive abstraction of water affecting downstream water Water abstraction will be limited to allocate quantity for users?  Kukdeshwar • Competing uses of water? Water abstraction will be limited to allocate quantity for  Kukdeshwar As per CPHEEO manual the rate of water supply is • Increased sewage flow due to 70lpcd for the town where sewerage scheme is not increased water supply?  anticipated • Increased volume of sullage (wastewater from cooking and washing)and sludge from waste water treatment plant?  No minimum influx of population during the construction • Large population influx during  and operation period. project construction and operation

101

that causes increased burden on social infrastructure and services (such as water supply and sanitation systems)? The contractor will be advised to absorb local labour • Social conflicts if workers forces as far as possible; in case if it is unavoidable, labour from other regions or countries are would be hired for temporary phase. No conflicts hired?  envisaged. • Risks to community health and safety due to the transport, storage, and use and/or disposal of materials such as explosives, fuel, and other chemicals during No such materials are used in project so no risk to operation and construction ?  community health & safety • Community safety risks due  Proper safety measures would be ensured during the to both accidental and natural hazards, construction & operation and decommissioning. especially where the structural elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning ?

102

Climate Change and Disaster Risk Yes No Remarks Questions The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks. Is the Project are a subject to hazards such √ Semi-arid zone, unreliable rainfall, less as earthquakes, floods, landslides, vegetation cover. Promote more efficient use tropicalcy clone winds, storm surges, of water by reducing losses and wastage to tsunami or volcanic eruptions and climate counter increased demands due to higher changes? temperatures.

Could changes in temperature, √ Reduction in rainfall may affect the water precipitation, or extreme events patterns availability from dam. Given the priority for over the Project lifespan affect technical or drinking water supply, dead storage will be financial sustainability(e.g., changes in utilized in case of low rain fall years rainfall patterns disrupt reliability of water supply; sea level rise creates salinity intrusion into proposed water supply source)? Are there any demographic or socio- √ No economic aspects of the Project area that are already vulnerable(e.g., high in cadence of marginalized populations, rural- urban migrants, illegal Settlements, ethnic minorities, women or children)? Could the Project potentially increase the √ No climate or disaster vulnerability of the surrounding area(e.g. ,by using water from A vulnerable source that is relied upon by many user groups, or encouraging

103

NAYAGAON

Country/ Project: India/ Madhya Pradesh Urban Service Improvement Program – ` NayagaonWater Supply Subproject

Sector/ Division: Urban Development and Environment Department/ UDED

SCREEINING QUESTION YES NO REMARKS A. Project Siting Is the project area ▪ Densely populated?  The average density of Nayagaon is found 4.41 Person/ Hactare, that is considered low. Only during construction phase, population would be affected adversely due to excavation, construction. But the impact would be very low. During operation, local of town would be more beneficiary ▪ Heavy with development activities?  No ▪ Adjacent to or within any  No environmentally sensitive areas? ▪ Cultural heritage site  No ▪ Protected Area  No ▪ Wetland  No ▪ Mangrove  No ▪ Estuarine  No ▪ Buffer zone of protected area  No ▪ Special area for protecting biodiversity  No ▪ Bay  No B. Potential Environmental Impacts

Will the Project cause… • Pollution of raw water supply  There are no significant water pollution from upstream wastewater sources in the catchment. Raw water discharge from quality is tested and found that it is • Communities, industries, suitable for Domestic use. agriculture, and soil erosion runoff? • Impairment of historical/cultural  Not applicable monuments/areas and loss/damage to these sites? • Hazard of land subsidence caused  Not applicable, subproject does not by excessive ground water involve groundwater abstraction pumping? • Social conflicts arising from  Project does not involve land displacement of communities? acquisition /displacement. No social conflicts envisaged

104

• Conflicts in abstraction of raw  No, the water will be abstracted with water for water supply with other due Permission of Water Resource beneficial water uses for surface Department. and ground waters? • Unsatisfactory raw water supply  Raw water Quality is tested and found (e.g. excessive pathogens or that it is suitable for Domestic use. mineral constituents)? • Delivery of unsafe water to  Water will be treated and disinfected distribution system? prior to supply. • Inadequate protection of intake  Construction of no intake well works or wells, leading to pollution of water supply? • Over pumping of ground water,  No Ground water pumping is required leading to salinization and as Surface water source is selected for ground subsidence? the project • Excessive algal growth in storage  Regular cleaning of storage tanks will reservoir? be conducted during operation. • Increase in production of sewage  As per CPHEEO manual the rate of beyond capabilities of water supply is 70lpcd for the town community facilities? where sewerage scheme is not anticipated • Inadequate disposal of sludge  Appropriate provision for sludge from water treatment plants? drying and disposal is included in the project • Inadequate buffer zone around  No pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities? • Impairments associated with  No transmission lines and access roads? • Health hazards arising from  Measures for safe handling of Chlorine inadequate design of facilities for are included receiving, storing, and handling of chlorine and other hazardous chemicals. • Health and safety hazards to  Measures for safe handling of Chlorine workers from the management of are included chlorine used for disinfection and other contaminants? • Dislocation or involuntary  There is no resettlement of people for resettlement of people project implementation. • Social conflicts between  The contractor will be utilizing the construction workers from other local labour forces as far as possible; in areas and community workers? case if it is unavoidable, labour camps and facilities will be provided

105

appropriately. No conflicts envisaged. • Noise and dust from construction  Dust suppression measures such as activities? water sprinkling will be employed • Increased road traffic due to  Excavation & Laying pipelines along interference of construction public road will interfere with the activities? traffic. Construction material transport will increase traffic within city and dumping construction material on road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference. • Continuing soil erosion/silt  Construction work during monsoon runoff from construction shall be carried out with due care so operations? that silt run off due to construction operation is prevented. • Delivery of unsafe water due to  Appropriate O&M will be conducted poor O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems? • Delivery of water to distribution  Not envisaged system, which is corrosive due to inadequate attention to feeding of corrective chemicals? • Accidental leakage of chlorine  Measures for safe handling of chlorine gas? are included. • Excessive abstraction of water  Water abstraction will be limited to affecting downstream water allocate quantity for Nayagaon users? • Competing uses of water?  Water abstraction will be limited to allocate quantity for Nayagaon. • Increased sewage flow due to  As per CPHEEO manual the rate of increased water supply water supply is 70 lpcd for the town where sewerage scheme is not anticipated • Increased volume of sullage  No (wastewater from cooking and washing) and sludge from wastewater treatment plant ▪ Large population influx during project  Minimum influx of population during construction and operation that causes the construction and operation period. increased burden on social infrastructure and services (such as water supply and sanitation systems)?

106

▪ Risks to community health and safety due  No such materials are used in project to the transport, storage, and use and/or so no risk to community health & disposal of materials such as explosives, safety fuel, and other chemicals during operation and construction? ▪ Community safety risks due to both  Proper safety measures would be accidental and natural hazards, especially ensured during the construction & where the structural elements or operation and decommissioning. components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning?

ClimateChangeandDisaster RiskQuestions Yes No Remarks Thefollowingquestionsarenotfor environmental categorization.Theyareincluded inthischecklisttohelp identifypotentialclimate anddisaster risks. Is theProjectareasubjectto hazardssuchas √ Semi-aridzone, unreliablerainfall, earthquakes, lessvegetationcover. Promote floods,landslides,tropicalcyclonewinds,st moreefficientuseofwater by ormsurges, tsunamior volcanic reducinglossesandwastageto counter eruptionsandclimatechanges? increased demands due to highertemperatures. Couldchanges intemperature, √ Reductioninrainfallmayaffectthe water precipitation,or extreme events patterns availabilityfromdam.Given overtheProjectlifespan affecttechnicalor the priorityfordrinkingwater supply, financial dead storagewill beutilized sustainability(e.g.,changesinrainfallpatternsdi incaseoflowrain fallyears sruptreliability ofwater supply;sealevelrisecreatessalinity intrusion into proposedwatersupplysource)? Are thereanydemographicor socio- √ No economicaspects ofthe Project area that arealready vulnerable(e.g.,highincidenceof marginalized populations,rural- urbanmigrants,illegal Settlements, ethnicminorities,women or children)?

CouldtheProject potentiallyincrease √ No theclimateor disaster vulnerability ofthesurroundingarea(e.g.,byusingwater from a vulnerable source thatisrelied upon by many user groups, or encouragingsettlementinearthquakezones)

107

SARWANIYA MAHARAJ

Country/ Project: India/ Madhya Pradesh Urban Service Improvement Program – SarwaniyaMaharaj Water Supply Subproject Sector/ Division: Urban Development and Environment Department/ UDED

SCREEINING QUESTION YES NO REMARKS A. Project Siting Is the project area ▪ Densely populated?  The average density of SarwaniyaMaharaj is found 22.46 Person/ Hectare that is moderate high. Only during construction phase, population would be affected adversely due to excavation, construction. But the impact would be very low. During operation, local of town would be more beneficiary ▪ Heavy with development activities?  No ▪ Adjacent to or within any environmentally No sensitive areas?  ▪ Cultural heritage site  No ▪ Protected Area  No ▪ Wetland  No ▪ Mangrove  No ▪ Estuarine  No ▪ Buffer zone of protected area  No ▪ Special area for protecting biodiversity  No ▪ Bay  No B. Potential Environmental Impacts

Will the Project cause… • Pollution of raw water supply from  There are no significant water upstream wastewater discharge from pollution sources in the catchment. • Communities, industries, agriculture, Raw water quality is tested and and soil erosion runoff? found that it is suitable for Domestic use. • Impairment of historical/cultural  Not applicable monuments/areas and loss/damage to these sites? • Hazard of land subsidence caused by  Not applicable, subproject does not excessive ground water pumping? involve groundwater abstraction

108

• Social conflicts arising from  Project does not involve land displacement of communities? acquisition /displacement. No social conflicts envisaged • Conflicts in abstraction of raw water for  No, the water will be abstracted water supply with other beneficial water with due Permission of Water uses for surface and ground waters? Resource Department. • Unsatisfactory raw water supply (e.g.  Raw water Quality is tested and excessive pathogens or mineral found that it is suitable for constituents)? Domestic use. • Delivery of unsafe water to distribution  Water will be treated and system? disinfected prior to supply. • Inadequate protection of intake works or  Construction of no intake well wells, leading to pollution of water supply? • Over pumping of ground water, leading  No Ground water pumping is to salinization and ground subsidence? required as Surface water source is selected for the project • Excessive algal growth in storage  Regular cleaning of storage tanks reservoir? will be conducted during operation. • Increase in production of sewage  As per CPHEEO manual the rate beyond capabilities of community of water supply is 70lpcd for the facilities? town where sewerage scheme is not anticipated • Inadequate disposal of sludge from  Appropriate provision for sludge water treatment plants? drying and disposal is included in the project • Inadequate buffer zone around pumping  No and treatment plants to alleviate noise and other possible nuisances and protect facilities? • Impairments associated with  No transmission lines and access roads? • Health hazards arising from inadequate  Measures for safe handling of design of facilities for receiving, Chlorine are included storing, and handling of chlorine and other hazardous chemicals. • Health and safety hazards to workers  Measures for safe handling of from the management of chlorine used Chlorine are included for disinfection and other contaminants? • Dislocation or involuntary resettlement  There is no resettlement of people of people for project implementation. • Social conflicts between construction  The contractor will be utilizing the workers from other areas and local labour forces as far as community workers? possible; in case if it is unavoidable, labour camps and facilities will be provided appropriately. No conflicts envisaged.

109

• Noise and dust from construction  Dust suppression measures such as activities? water sprinkling will be employed • Increased road traffic due to  Excavation & Laying pipelines interference of construction activities? along public road will interfere with the traffic. Construction material transport will increase traffic within city and dumping construction material on road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference. • Continuing soil erosion/silt runoff from  Construction work during construction operations? monsoon shall be carried out with due care so that silt run off due to construction operation is prevented. • Delivery of unsafe water due to poor  Appropriate O&M will be O&M treatment processes (especially conducted mud accumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems? • Delivery of water to distribution system,  Not envisaged which is corrosive due to inadequate attention to feeding of corrective chemicals? • Accidental leakage of chlorine gas?  Measures for safe handling of chlorine are included. • Excessive abstraction of water affecting  Water abstraction will be limited to downstream water users? allocate quantity for Nayagaon • Competing uses of water?  Water abstraction will be limited to allocate quantity for Nayagaon. • Increased sewage flow due to increased  As per CPHEEO manual the rate water supply of water supply is 70 lpcd for the town where sewerage scheme is not anticipated • Increased volume of sullage  No (wastewater from cooking and washing) and sludge from wastewater treatment plant ▪ Large population influx during project Minimum influx of population construction and operation that causes  during the construction and increased burden on social operation period. infrastructure and services (such as water supply and sanitation systems)? ▪ Risks to community health and safety No such materials are used in due to the transport, storage, and use  project so no risk to community and/or disposal of materials such as health & safety

110

explosives, fuel, and other chemicals during operation and construction? ▪ Community safety risks due to both Proper safety measures would be accidental and natural hazards,  ensured during the construction & especially where the structural operation and decommissioning. elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning?

111

Climate Change and Disaster Risk Yes No Remarks Questions The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks.

Is the Project area subject to hazards such √ Semi-arid zone, unreliable rainfall, less as earthquakes, floods, landslides, tropical vegetation cover. Promote more efficient cyclone winds, storm surges, tsunami or use of water by reducing losses and volcanic eruptions and climate changes? wastage to counter increased demands due to higher temperatures.

Could changes in temperature, √ Reduction in rainfall may affect the water precipitation, or extreme events patterns availability from dam. Given the priority over the Project lifespan affect technical or for drinking water supply, dead storage financialsustainability (e.g., changes in will be utilized in case of low rain fall rainfall patterns disrupt reliability of water years supply; sea level rise creates salinity intrusion into proposed water supply source)?

Are there any demographic or socio- √ No economic aspects of the Project area that are already vulnerable (e.g., high incidence of marginalized populations, rural-urban migrants, illegal Settlements, ethnic minorities, women or children)?

Could the Project potentially increase the √ No climate or disaster vulnerability of the surrounding area (e.g., by using water froma vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

112

NAGRI TOWN Country/Project: India/Madhya Pradesh Urban Services Improvement program- Nagri- Water Supply Subproject Sector/Division: Urban Development & Environment Department/MPUDC

Screening Questions Yes No Remarks A. PROJECT SITING IS THE PROJECT AREA As per census 2011 the density of Nagri town is 285/Sq.km Densely populated?  therefore it is not a densely populated town. Project covers entire town including the densely populated areas. There are no major negative impacts envisaged because pipeline will be located in unused Government lands along side the existing roads and can be constructed without causing disturbance to houses and commercial establishments. In narrow streets disruption to road users is likely and measures like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. Heavy with development activities?  No Adjacent to or within any environmentally sensitive areas?  No

Cultural/ heritage site The famous Jain temple bahiPashwanath is about 7km and Religious  famous Pashupatinath temple is 18kms from Nagri.

Protected area 

Wetland  Mangrove  Estuarine  Buffer zone of protected area  Special area for protecting biodiversity  Bay  B. POTENTIAL ENVIRONMENTAL IMPACTS Will the project cause… Pollution of raw water supply There are no significant water pollution sources in the from upstream wastewater catchment. Raw water quality is tested and found that it is discharge from communities, suitable for Domestic use. industries, agriculture, and soil erosion runoff?  Impairment of historical /cultural monuments/areas, and loss/damage to these sites?  No Hazard of land subsidence caused by excessive ground water Not applicable, subproject does not involve groundwater pumping?  abstraction Social conflicts arising from Project does not involve land acquisition /displacement .No displacement of communities  social conflicts envisaged.

113

Conflicts in abstraction of raw No, the water will be abstracted with due of Water water for water supply with other Resource Department .RupaniyaKhal dam having gross beneficial water uses for surface storage capacity of 13.54 MCM and it is presently used and ground waters? for irrigation purpose & net capacity required for Nagri  .Demand of Water Supply scheme is 0.4 MCM. Unsatisfactory raw water Raw water Quality is tested and found that it is suitable for supply (e.g. excessive pathogens or mineral  Domestic use. constituents)? Delivery of unsafe water to Water will be treated and disinfected prior to supply. distribution system?  Inadequate protection of intake Water is abstracted from RupaniyaKhal Dam there are no works or wells, leading to  major polluting sources in the catchment pollution of water supply?

Over-pumping of ground water, leading to salinization and ground No Ground water pumping is required as Surface water subsidence?  source is selected for the project Excessive algal growth in Regular cleaning of storage tanks will be conducted during storage reservoir?  operation. Increase in production of sewage beyond capabilities of As per CPHEEO manual the rate of water supply is 70lpcd community facilities?  for the town where sewerage scheme is not anticipated. Inadequate disposal of sludge Appropriate provision for sludge drying and disposal is from water treatment plants?  included in the project Inadequate buffer zone around pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities?  No Impairments associated with transmission lines and access roads?  No Health hazards arising from inadequate design of facilities for Measures for safe handling of Chlorine are included \ receiving, storing, and handling of chlorine and other hazardous chemicals?  Health and safety hazards to Measures for safe handling of Chlorine are included workers from the management of chlorine used for disinfection and other contamination?  Dislocation or involuntary There is no resettlement of people for project resettlement of people  implementation. The contractor will be utilizing the local labour forces as social conflicts between  far as possible; in case if it is unavoidable, labour camps construction workers from other and facilities will be provided appropriately. No conflicts areas & community workers envisaged. noise and dust from construction Dust suppression measures such as water sprinkling will be activities  employed increased road traffic due to Excavation & Laying pipelines along public road will interference of construction interfere with the traffic. activities? Construction material transport will increase traffic within city and dumping construction material on road cause traffic congestion. Proper traffic & Construction planning will be ensured to  minimize the interference. Construction work during monsoon shall be carried out continuing soil erosion, silt runoff with due care so that silt run off due to construction from construction operation  operation is prevented.

114

Delivery of unsafe water due to Appropriate O&M will be conducted poor O&M treatment processes (especially mud accumulations in  filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems? Delivery of water to distribution system, which is corrosive due to inadequate attention to feeding of  corrective chemicals? Not envisaged Accidental leakage of Chlorine gas  Measures for safe handling of chlorine are included. Excessive abstraction of water affecting downstream water Water abstraction will be limited to allocate quantity for users?  Nagri Competing uses of water? Water abstraction will be limited to allocate quantity for  Nagri Increased sewage flow due to As per CPHEEO manual the rate of water supply is 70lpcd increased water supply?  for the town where sewerage scheme is not anticipated Increased volume of sullage (wastewater from cooking and washing)and sludge from waste water treatment plant?  No Large population influx during minimum influx of population during the construction and project construction and operation period. operation that causes increased burden on social infrastructure and services (such as water supply and sanitation systems)?  The contractor will be advised to absorb local labour forces Social conflicts if workers as far as possible; in case if it is unavoidable, labour from other regions or countries would be hired for temporary phase. No conflicts are hired?  envisaged.

Risks to community health and safety due to the transport, storage, and use and/or disposal of materials such as explosives, fuel, and other chemicals during No such materials are used in project so no risk to operation and construction ?  community health & safety Community safety risks due to both accidental and natural Proper safety measures would be ensured during the hazards, especially where the construction & operation and decommissioning. structural elements or components of the project are accessible to members of the affectedcommunity or where their failure could result in injury to the  community throughout project construction, operation, and decommissioning ?   

115

Climate Change and Disaster Risk Questions Yes No Remarks The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks. Is the Project are a subject to hazards such as earthquakes, floods, √ Semi-arid zone, unreliable rainfall, landslides, tropical cyclone winds, storm surges, tsunami or less vegetation cover. Promote more volcanic eruptions and climate changes? efficient use of water by reducing losses and wastage to counter increased demands due to higher temperatures. Could changes in temperature, precipitation , or extreme events √ Reduction in rainfall may affect the patterns over the Project lifespan affect technical or financial water availability from dam. Given sustainability(e.g., changes in rainfall patterns disrupt reliability the priority for drinking water of water supply; sea level rise creates salinity intrusion into supply, dead storage will be utilized proposed water supply source)? in case of low rain fall years Are there any demographic or socio-economic aspects of the Project √ No area that are already vulnerable(e.g., high incidence of marginalized populations, rural-urban migrants, illegal Settlements, ethnic minorities, women or children)? Could the Project potentially increase the climate or disaster √ No vulnerability of the surrounding area(e.g., by using water from A vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

116

APPENDIX 2: NATIONAL AMBIENT AIR QUALITY STANDARDS

SL Pollutants Time Concentration in ambient air Method of measurement NO: weighted average Industrial, Ecologically Residential, Sensitive Rural & Other Areas Areas 1 Sulphur Dioxide Annual 50 20 Improved West and Geake- (SO2) 24 hours 80 80 Ultraviolet fluorescence µg/m3 2 Nitrogen Dioxide Annual 40 30 Modified Jacob 3 (NO2) µg/m 24 hours 80 80 &Hochheiser (Na-Arsenite) Chemiluminescence 3 Particulate Matter Annual 60 60 Gravimetric (Size less than 10 24 hours 100 100 -TOEM µm) or PM10 µg/m3 -Beta attenuation 4 Particulate Matter Annual 40 40 Gravimetric (Size less than 2.5 24 hours 60 60 -TOEM µm) or PM2.5 -Beta attenuation µg/m3 5 Carbon Monoxide 8 hours 02 02 Non Dispersive Infra Red (CO) mg/m3 1 hours 04 04 (NDIR) Spectroscopy

APPENDIX 3: VEHICLE EXHAUST EMISSION NORMS 1. Passenger Cars Norms CO( g/km) HC+ NOx(g/km) 1991Norms 14.3-27.1 2.0(Only HC) 1996 Norms 8.68-12.40 3.00-4.36 1998Norms 4.34-6.20 1.50-2.18 India stage 2000 norms 2.72 0.97 Bharat stage-II 2.2 0.5 Bharat Stage-III 2.3 0.35 (combined) Bharat Stage-IV 1.0 0.18 (combined)

2. Heavy Diesel Vehicles Norms CO( g/kmhr) HC (g/kmhr) NOx (g/kmhr) PM(g/kmhr) 1991Norms 14 3.5 18 - 1996 Norms 11.2 2.4 14.4 - India stage 2000 norms 4.5 1.1 8.0 0.36 Bharat stage-II 4.0 1.1 7.0 0.15 Bharat Stage-III 2.1 1.6 5.0 0.10 Bharat Stage-IV 1.5 0.96 3.5 0.02 Source: Central Pollution Control Board CO = Carbon Monixide; g/kmhr = grams per kilometer-hour; HC = Hydrocarbons; NOx = oxides of nitrogen; PM = Particulates Matter APPENDIX 4: NATIONAL AMBIENT AIR QUALITY STANDARDS IN RESPECT OF NOISE Area code Category of area/zone Limit in dB (A) Day time Night time A Industrial area 75 70 B Commercial area 65 55 C Residential area 55 45 D Silence zone 50 40

117

APPENDIX 5: EXTRACT FROM CONSTRUCTION & DEMOLITION MANAGEMENT RULES, 2016

118

119

120

121

122

123

APPENDIX 6: SALIENT FEATURES OF MAJOR LABOR LAWS APPLICABLE TO ESTABLISHMENTS ENGAGED IN CONSTRUCTION OF CIVIL WORKS

(i) Workmen Compensation Act, 1923 - The Act provides for compensation in case of injury by accident arising out of and during the course of employment.

(ii) Payment of Gratuity Act, 1972 - Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed 5 years’ service or more or on death at the rate of 15 days wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees.

(iii) Employees’ PF and Miscellaneous Provisions Act, 1952 - The Act provides for monthly contributions by the employer plus workers @10 % or 8.33 %. The benefits payable under the Act are: (a) Pension or family pension on retirement or death as the case may be; (b) deposit linked insurance on the death in harness of the worker; (c) payment of PF accumulation on retirement/death etc.

(iv) Maternity Benefit Act, 1951 - The Act provides for leave and some other benefits to women employees in case of confinement or miscarriage etc.

(v) Contract Labour (Regulation and Abolition) Act, 1970 - The Act provides for certain welfare measures to be provided by the Contractor to contract labor and in case the Contractor fails to provide, the same are required to be provided by the Principal Employer by Law. The principal employer is required to take Certificate of Registration and the Contractor is required to take a License from the designated Officer. The Act is applicable to the establishments or Contractor of principal employer if they employ 20 or more contract labor.

(vi) Minimum Wages Act, 1948 - The employer is supposed to pay not less than the Minimum Wages fixed by appropriate Government as per provisions of the Act if the employment is a scheduled employment. Construction of Buildings, Roads, Runways are scheduled employment.

(vii) Payment of Wages Act, 1936 - It lays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers.

(viii) Equal Remuneration Act, 1979 - The Act provides for payment of equal wages for work of equal nature to Male and Female workers and not for making discrimination against Female employees in the matters of transfers, training and promotions etc.

(ix) Payment of Bonus Act, 1965 - The Act is applicable to all establishments employing 20 or more workmen. The Act provides for payments of annual bonus subject to a minimum of 8.33 % of wages and maximum of 20 % of wages to employees drawing Rs. 3,500/- per month or less. The bonus to be paid to employees getting Rs. 2,500/- per month or above up to Rs.3,500/- per month shall be worked out by taking wages as Rs.2,500/- per month only. The Act does not apply to certain establishments. The newly set up establishments are exempted for five years in certain circumstances. Some of the State Governments have reduced the employment size from 20 to 10 for the purpose of applicability of the Act.

(x) Industrial Disputes Act, 1947 - The Act lays down the machinery and procedure for resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or retrenching the employees or closing down the establishment.

(xi) Industrial Employment (Standing Orders) Act, 1946 - It is applicable to all establishments employing 100 or more workmen (employment size reduced by some of the States and Central Government to 50). The Act provides for laying down rules governing the conditions of employment by the employer on matters provided in the Act and get the same certified by the designated Authority.

124

(xii) Trade Unions Act, 1926 - The Act lays down the procedure for registration of trade unions of workmen and employees. The trade unions registered under the Act have been given certain immunities from civil and criminal liabilities.

(xiii) Child Labor (Prohibition and Regulation) Act, 1986 - The Act prohibits employment of children below 14 years of age in certain occupations and processes and provides for regulation of employment of children in all other occupations and processes. Employment of child labor is prohibited in Building and Construction Industry.

(xiv) Inter-State Migrant Workmen's (Regulation of Employment and Conditions of Service) Act, 1979 - The Act is applicable to an establishment which employs 5 or more inter-state migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The inter-state migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, medical aid, traveling expenses from home up to the establishment and back, etc

(xv) The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 and the Cess Act of 1996 - All the establishments who carry on any building or other construction work and employ 10 or more workers are covered under this Act. All such establishments are required to pay Cess at rate not exceeding 2% of the cost of construction as may be notified by the Government. The employer of the establishment is required to provide safety measures at the building or construction work and other welfare measures, such as canteens, first-aid facilities, ambulance, housing accommodation for workers near the workplace etc. The employer to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government.

125

APPENDIX 7: PROVIDE WARD-WISE POPULATION OF SUBPROJECT TOWNS Ward Kukdeshwar Nagri Nayagaon SarwaniyaMaharaj No. 1 953 568 422 475 2 842 466 407 441 3 941 530 430 467 4 737 576 456 430 5 742 653 440 452 6 493 344 459 457 7 720 446 449 471 8 782 392 449 450 9 744 360 417 489 10 682 365 441 486 11 748 369 438 425 12 388 508 445 480 13 642 613 423 440 14 1465 542 444 396 15 1077 302 433 378 Total 11956 7034 6553 6737

126

APPENDIX 8: CLIMATIC CHARACTERISTICS OF SUBPROJECT DISTRICTS – NEEMUCH AND MANDASAUR

127

APPENDIX 9: SALIENT FEATURE OF GANDHISAGAR DAM Attribute Value Attribute Value Name of the Dam Gandhi Sagar Dam Name of the Reservoir Gandhi Sagar Reservoir Nearest City Manasa Catchment Area (Sq.km) 23025 District Neemuch Full Reservoir Level (m) 399.9 State Madhya Pradesh Minimum Draw Down Level (m) --- Basin Name Ganga Maximum Water Level (m) --- River CHAMBAL Gross Storage Capacity at FRL (MCM) 7746 Dam Type Gravity / Masonry Live Storage Capacity (MCM) 6910 Dam Status Completed Dead Storage Capacity (MCM) 5.25 Purpose Hydroelectric, Irrigation Storage Capacity at MWL (MCM) ---

Completion Year 1960 Submergence Area /Reservoir Area 6 (Th. Ha) Length of Dam (m) 514 Land affected - Total (Th Ha) 66.838 Dam Height (m) 62.17 Land Affected - Culturable (Th Ha) 29.28 Design flood (cumec) Land Affected - Forest (Th Ha) 3.3 Type of Spillway --- Land Affected - Others (Th Ha) 34.258 Length of Spillway (m) 254 Number of Villages Affected 218 Type of Spillway Gates --- Number of the Families Affected - Total 302 Number of Spillway Gates 10 Number of the Families Affected - SC 11 Size of Spillway Gates (m X --- Number of the Families Affected - ST 30 m) Crest Level of Spillway --- Forest Plantation (Area in Th Ha) --- Commencement Year --- Total Volume Content of --- Dam (TCM) Spillway Capacity (cumec) 21238 Seismic Zone Seismic Zone-II

128

APPENDIX 10: WATER QUALITY RESULTS OF GANDHI SAGAR DAM

129

APPENDIX 11A – COMPREHENSIVE SAMPLING AND WATER QUALITY RESULTS OF CCI POND

130

131

132

APPENDIX 11B– COMPREHENSIVE SAMPLING AND WATER QUALITY PROGRAM FOR CCI POND, NAYAGAON

Water quality tests shall be conducted two times: (i) pre-monsoon (May – early June), and (ii) post-monsoon (July-August)

Number of samples: The pond is very large, as per the design consultant estimate it is about 35 ha. Six sampling points shall be selected – one each on four sides (10-20 m inside from the boundary, 2 in the upper and lower centre of the lake. Sample shall be collected from at least 4- 5 m below the water surface or as appropriate during the sampling. Extreme caution shall be maintained during sample collection, as this is an abandoned mine and profile is unknown. Samples shall be tested for the following parameters:

No. Substance or characteristic 1 Colour , Odour, Turbidity, Temperature, pH 2 Total Hardness, Electrical conductivity 3 Total dissolved & suspended solids 4 Nutrients - NH3-N, NO2 + NO3, Total P 5 DO 6 BOD 7 COD 8 Iron 9 Chlorides 10 Calcium 11 Magnesium 12 Sulphate 13 Potassium 14 CO3, HCO3 15 Nitrate 16 Fluoride 17 Mercury 18 Cadmium 19 Lead 20 Zinc 21 Chromium 22 Pesticides 23 Aluminum 24 Boron 25 Total and Faecal Coliforms

133

APPENDIX 2– SALIENT FEATURES OF MOREWAN DAM Attribute Value Name of the Dam Morwan Dam Nearest City Jawad District Neemuch State Madhya Pradesh Basin Name Ganga River Gambhiri river Dam Type Earthen Dam Status Completed Purpose Irrigation Completion Year 1959 Length of Dam (m) 990 Dam Height (m) 27.43 Design flood (cumec) 429.915 Type of Spillway Ogee spillway Length of Spillway (m) 112.78 Type of Spillway Gates Stone Masonry, Cut Stone Slab Number of Spillway Gates 0 Size of Spillway Gates (m X m) 1.10 m (H) X 1.075m (W) Crest Level of Spillway 504.59 Commencement Year 1960 Total Volume Content of Dam (TCM) --- Spillway Capacity (cumec) 219 Seismic Zone Seismic Zone-II Name of the Reservoir Morwan Reservoir Catchment Area (Sq.km) 62.16 Full Reservoir Level (m) 503.53 Minimum Draw Down Level (m) 491.76 Maximum Water Level (m) 504.59 Gross Storage Capacity at FRL (MCM) 16.46 Live Storage Capacity (MCM) 15.76 Dead Storage Capacity (MCM) 0.7 Storage Capacity at MWL (MCM) 16.46 Submergence Area /Reservoir Area (Th. Ha) 0.321

134

APPENDIX 3- YIELD TEST RESULTS OF OPEN WELL SOURCE OF SARWANIYAMAHARAJ

135

APPENDIX 4 - OPEN WELL (SARWANIYA MAHARAJ) WATER QUALITY RESULTS

136

APPENDIX 5– SALIENT FEATURES OF RUPANIYAKHAL DAM General Data:- 1 District Ratlam 2 Tahasil Jawar 3 River / Nala RupniyaKhal River 4 Location of Dam Near Village Ranayara 5 Name of River Basin Chambal 6 Latitude 23 0 48 ' N 7 Longitude 78 0 10' E 8 Year Of Start 1981 9 Year of Completion June – 1994 Hydraulic Data:- 10 Mean Rainfall (over 40 years) 33.94 Inches 11 Annual Rainfall 33.91 Inches 12 Mean Mansoon Runoff Average 854 MCFT (24.20 MCM) Maximum 1758 MCFT (49.78 MCM) Minimum 78 MCFT (2.20 MCM) 13 Flood Maximum Observed 20350 Cusecs Maximum Q = CM^(3/4) 11455 Cuses When C = 1400 Reservior Data :- 14 Catchment Data 35.50 Sq Miles (91.95 Sq Km) 15 Mean MansoonYeild 16 Gross Storage Capacity 478.44 MCFT (13.54 MCM) 17 Dead Storage Capacity 80.04 MCFT (2.26 MCM) 18 Live Storage 398.40 MCFT (11.28 MCM) Percentage & Gross Storage 19 68.19% Normal MansoonYeild

20 Percentage of Dead Storage Gross Capacity 16.72%

21 Full Tank Level (Top Level of Spillway) 461.45 m 22 Maximum Water Level 462.97 m 23 Lowest Seal Level 456.00 m 24 Top Tank Level 464.80 m 25 Water Spread Area at FTL 374.90 Ha 26 Water Spread Area at LSL 84.00 Ha

137

APPENDIX 6– WATER QUALITY RESULTS OF RUPANIYAKHAL DAM

138

APPENDIX 7: STAKEHOLDER CONSULTATION

KUKDESHWAR TOWN

139

List of Participants

Minutes of Meeting in Kukdeshwar

• In Kukdeshwar Town, Stakeholders meeting was conducted for proposed water supply scheme in town. In this meeting Local representatives, ULB staffs and local people have participated. • During meeting, present water supply was found not adequate in terms of water quantity in town.

• All stakeholders express their happiness for upcoming water supply scheme as town has urgent need for this.

• All the existing water sources for Kukdeshwar town have been discussed and Gandhi Sagar Dam is selected for water source.

• Some people requested to give priority of local people in employment during construction work.

140

• Some people complained about the delayed work during construction with their past experience. So they requested to appoint good contractor, so that constructed work will be finished in given timeline.

• People also requested to maintain the water pressure in households.

141

NAYAGAON TOWN

142

143

Minutes of Meeting in Nayagaon • In Nayagaon Town, Stakeholders meeting is conducted for proposed water supply scheme in town. on dated 05.06.2016. In this meeting Local representatives, ULB staffs and local people have participated.

• Water Supply in town is found very less in comparison to national standard during consultation work.

• Location of all water supply components like WTP, OHT has been indentified in consultation meeting.

• Water sources for domestic supply in town have been reviewed with all and CCI pond has been selected for water supply in town.

• At present also, CCI pond is used for supplying water in town and no water borne diseases has been identified by the local water consumers. That’s why CCI pond is found suitable for the water supply.

• All the representatives stress to complete the construction work in given time period to avoid problems due to excavation of roads.

144

SARWANIYA MAHARAJ

145

146

147

Minutes of Meeting in Sarwaniya Maharaj • In SarwaniyaMaharaj Town, Stakeholders meeting was conducted for proposed water supply scheme in town. In this meeting Local representatives, ULB staffs and local people have participated.

• With consultation with all, location of components of proposed water Supply scheme has been finalized with identification of government land.

• All the existing water structure nearby town has been identified and Open well near Morwan dam has been selected for source of water supply in SarwaniyaMaharaj.

• People informed about very less water supply in town in comparison to standard.

• Condition of all the existing component of the water supply has been reviewed for their further uses in proposed water supply scheme.

• People requested for selection of good contractor to speed up the construction work.

148

Nagri Town

149

List of Participants

150

Minutes of Meeting in Nagri

• In Nagri Town, Stakeholders meeting was conducted for proposed water supply scheme in town. In this meeting Local representatives, ULB staffs and local people have participated.

151

• People complained about the very poor water supply in the town in terms of quantity of water as well as connectivity of water supply network in town. • With consultation with all, location of components of proposed water Supply scheme has been finalized with identification of government land. • All the existing water structure nearby town has been identified and Rupaniyakhal Dam has been selected for source of water supply in Nagri Town. • Condition of all the existing component of the water supply has been reviewed for their further uses in proposed water supply scheme. There are two OHT in town with capacity of 450 KL and 100 KL respectively. People requested to construct a new 100 KL OHT at the place of ole one. But he was informed that 450 KL is self sufficient for supplying water in town. • People requested for selection of good contractor to speed up the construction work.

152

APPENDIX 18: SAMPLE GRIEVANCE REGISTRATION FORM (To be available in Hindi and English)

The ______Project welcomes complaints, suggestions, queries, and comments regarding project implementation. We encourage persons with grievance to provide their name and contact information to enable us to get in touch with you for clarification and feedback. Should you choose to include your personal details but want that information to remain confidential, please inform us by writing/typing *(CONFIDENTIAL)* above your name. Thank you.

Date Place of registration Project Town

Project: Contact information/personal details Name Gender * Male Age * Female Home address Place Phone no. E-mail Complaint/suggestion/comment/question Please provide the details (who, what, where, and how) of your grievance below:

If included as attachment/note/letter, please tick here: How do you want us to reach you for feedback or update on your comment/grievance?

FOR OFFICIAL USE ONLY Registered by: (Name of official registering grievance)

Mode of communication: Note/letter E-mail Verbal/telephonic Reviewed by: (Names/positions of officials reviewing grievance)

Action taken:

Whether action taken disclosed: Yes No Means of disclosure:

153

APPENDIX 8: SAMPLE OUTLINE SPOILS (CONSTRUCTION WASTE) MANAGEMENT PLAN

• The Spoil Management Plan should be site specific and be part of the monthly Construction Management Plan. • The contractor, in consultation with the PIU, has to find out appropriate location/s for the disposal of the excess soil generated. The spoils should be deposited only at these sites. • Further precautions need to be taken in case of the contaminated spoils • The vehicle carrying the spoil should be covered properly. • The spoils generating from each site should be removed on the same day or immediately after the work is complete. The site / road should be restored to the original condition.

I. Spoils information The spoil information contains the details like a) The type / material, b) Potential contamination by that type, c) Expected volume (site / component specific), d) Spoil Classification etc.

II. Spoils management The Spoil Management section gives the details of a) Transportation of spoil b) disposal site details c) Precautions taken d) Volume of contaminated spoil, if present, d) Suggested reuse of disposal of the spoil

III. Documentation The volume of spoil generated (site specific, date wise), site disposed, reuse / disposal details should be documented properly.

154

APPENDIX 9: SAMPLE OUTLINE TRAFFIC MANAGEMENT PLAN

A. Principles for TMP around the Water Pipes Construction Sites

1. One of the prime objectives of this TMP is to ensure the safety of all the road users along the work zone, and to address the following issues: (i) the safety of pedestrians, bicyclists, and motorists travelling through the construction zone; (ii) protection of work crews from hazards associated with moving traffic; (iii) mitigation of the adverse impact on road capacity and delays to the road users; (iv) maintenance of access to adjoining properties; and (v) addressing issues that may delay the project.

B. Operating Policies for TMP

2. The following principles will help promote safe and efficient movement for all road users (motorists, bicyclists, and pedestrians, including persons with disabilities) through and around work zones while reasonably protecting workers and equipment. (i) Make traffic safety and temporary traffic control an integral and high-priority element of project from planning through design, construction, and maintenance. (ii) Inhibit traffic movement as little as possible. (iii) Provide clear and positive guidance to drivers, bicyclists, and pedestrians as they approach and travel through the temporary traffic control zone. (iv) Inspect traffic control elements routinely, both day and night, and make modifications when necessary. (v) Pay increased attention to roadside safety in the vicinity of temporary traffic control zones. (vi) Train all persons that select, place, and maintain temporary traffic control devices. (vii) Keep the public well informed. (viii) Make appropriate accommodation for abutting property owners, residents, businesses, emergency services, railroads, commercial vehicles, and transit operations.

3. Figure A2 to Figure A12illustrates the operating policy for TMP for the construction of water pipes and the sewers along various types of roads.

C. Analyze the impact due to street closure

4. Apart from the capacity analysis, a final decision to close a particular street and divert the traffic should involve the following steps:

(i) approval from the ULB/Public Works Department (PWD) to use the local streets as detours; (ii) consultation with businesses, community members, traffic police, PWD, etc, regarding the mitigation measures necessary at the detours where the road is diverted during the construction; (iii) determining of the maximum number of days allowed for road closure, and incorporation of such provisions into the contract documents; (iv) determining if additional traffic control or temporary improvements are needed along the detour route;

155

(v) considering how access will be provided to the worksite; (vi) contacting emergency service, school officials, and transit authorities to determine if there are impacts to their operations; and (vii) developing a notification program to the public so that the closure is not a surprise. As part of this program, the public should be advised of alternate routes that commuters can take or will have to take as result of the traffic diversion.

5. If full road-closure of certain streets within the area is not feasible due to inadequate capacity of the detour street or public opposition, the full closure can be restricted to weekends with the construction commencing on Saturday night and ending on Monday morning prior to the morning peak period.

Figure A1: Policy Steps for the TMP

• Review construction schedule and methods Review

Traffic Re- • Identify initial traffic recirculation and control policy Circulation

• Identify routes for traffic diversions Traffic • Analyse adverse impact & mitigation at the detours Diversions

• Begin community consultation for consensus Full Road • Finalise or determine alternate detours Colsures

• Identify temporary parking (on and off -street ) Temporary • Discuss with CMC, owner, community for use parking

• Coordinate with theTraffic Police to enforce traffic and diversions Police Coordination

• Install traffic control devices (traffic cones, sgns, lightings, etc) Install control devices

• Conduct campaigns, publicity, and notify public about street closure Awareness

Develop a mechanism to address public grievances regarding disruptons (traffic, utilities, and diversions) Public • Redress

D. Public awareness and notifications

6. As per discussions in the previous sections, there will be travel delays during the constructions, as is the case with most construction projects, albeit on a reduced scale if utilities and traffic management are properly coordinated. There are additional grounds for travel delays in the area, as most of the streets lack sufficient capacity to accommodate additional traffic from diverted traffic as a result of street closures to accommodate the works.

6. The awareness campaign and the prior notification for the public will be a continuous activity which the project will carry out to compensate for the above delays and minimize public claims as result of these problems. These activities will take place sufficiently in advance of the

156 time when the roadblocks or traffic diversions take place at the particular streets. The reason for this is to allow sufficient time for the public and residents to understand the changes to their travel plans. The project will notify the public about the roadblocks and traffic diversion through public notices, ward level meetings and city level meeting with the elected representatives.

7. The PIU will also conduct an awareness campaign to educate the public about the following issues:

(i) traffic control devices in place at the work zones (signs, traffic cones, barriers, etc.); (ii) defensive driving behaviour along the work zones; and (iii) reduced speeds enforced at the work zones and traffic diversions.

8. It may be necessary to conduct the awareness programs/campaigns on road safety during construction.

9. The campaign will cater to all types of target groups i.e. children, adults, and drivers. Therefore, these campaigns will be conducted in schools and community centres. In addition, the project will publish a brochure for public information. These brochures will be widely circulated around the area and will also be available at the PIU, and the contractor's site office. The text of the brochure should be concise to be effective, with a lot of graphics. It will serve the following purpose:

(i) explain why the brochure was prepared, along with a brief description of the project; (ii) advise the public to expect the unexpected; (iii) educate the public about the various traffic control devices and safety measures adopted at the work zones; (iv) educate the public about the safe road user behaviour to emulate at the work zones; (v) tell the public how to stay informed or where to inquire about road safety issues at the work zones (name, telephone, mobile number of the contact person; and (vi) indicate the office hours of relevant offices.

E. Install traffic control devices at the work zones and traffic diversion routes

10. The purpose of installing traffic control devices at the work zones is to delineate these areas to warn, inform, and direct the road users about a hazard ahead, and to protect them as well as the workers. As proper delineation is a key to achieve the above objective, it is important to install good traffic signs at the work zones. The following traffic control devices are used in work zones:

• Signs • Pavement Markings • Channelizing Devices • Arrow Panels • Warning Lights

11. Procedures for installing traffic control devices at any work zone vary, depending on road configuration, location of the work, construction activity, duration, traffic speed and volume, and pedestrian traffic. Work will take place along major roads, and the minor internal roads. As such,

157

the traffic volume and road geometry vary. The main roads carry considerable traffic; internal roads in the new city areas are wide but in old city roads very narrow and carry considerable traffic. However, regardless of where the construction takes place, all the work zones should be cordoned off, and traffic shifted away at least with traffic cones, barricades, and temporary signs (temporary “STOP” and “GO”).

12. Figure A2 to Figure A6 illustrates a typical set-up for installing traffic control devices at the work zone of the area, depending on the location of work on the road way, and road geometrics: • Work on shoulder or parking lane • Shoulder or parking lane closed on divided road • Work in Travel lane • Lane closure on road with low volume • Street closure with detour

13. The work zone should take into consideration the space required for a buffer zone between the workers and the traffic (lateral and longitudinal) and the transition space required for delineation, as applicable. For the works, a 30 cm clearance between the traffic and the temporary STOP and GO signs should be provided. In addition, at least 60 cm is necessary to install the temporary traffic signs and cones.

14. Traffic police should regulate traffic away from the work zone and enforce the traffic diversion result from full street closure in certain areas during construction. Flagggers/ personnel should be equipped with reflective jackets at all times and have traffic control batons (preferably the LED type) for regulating the traffic during night time.

16. In addition to the delineation devices, all the construction workers should wear fluorescent safety vests and helmets in order to be visible to the motorists at all times. There should be provision for lighting beacons and illumination for night constructions.

158

Figure A2 & A3: Work on shoulder or parking lane & Shoulder or parking lane closed on divided road

159

Figure A4 & A5: Work in Travel lane & Lane closure on road with low volume

160

Figure A6: Street closure with detour

Appendix 161

APPENDIX 10: DRINKING WATER STANDARDS

No. Substance or Requirement Undesirable effect outside Permissible Remarks characteristic Desirable the desirable limit in the limit absence of alternate Source Essential Characteristic 1. Colour Hazen 5 Above 5, consumer 25 Extended to 25 only if Units, Max acceptance decreases toxic Substance are not suspect in absence of alternate sources 2. Odour Unobjectiona - - a) test cold and when ble heated b) test are several dilutions 3. Taste Agreeable - - Test to be conducted only after safely has been established 4. Turbidity (NTU) 5 Above 5, consumer 10 - Max acceptance decreases 5. pH value 6.5 to 8.5 Beyond this range the No relaxation - water will after the mucous membrane and/or water supply system 6. Total 300 Encrustation in water 600 - Hardness supply structure and (mg/L) adverse effects on CaCO3 domestic use 7. Iron (mg/L, Fe) 0.3 Beyond this limit 1.0 - Max taste/appearance are affected; has adverse effects on domestic uses and water supply structure and promotes iron bacteria 8. Chlorides 250 250 Beyond effects outside the 1000 - (mg/L, Cl) Max desirable limit 9. Residual free 0.2 - - To be applicable only Chlorine (mg/L), when water is Max chlorinated. Tested at customer end. When protection against viral infection is required, it should be min. 0.5 mg/L. Desirable Characteristics 10. Dissolved solids 500 Beyond this, palatability 2000 - mg/L. Max decreases and may cause gastrointestinal irritation. 11. Calcium (mg/L, 75 Encrustation in water 200 - Ca) Max. supply structure and adverse effects on domestic use. 12. Magnesium (mg/L, 30 Encrustation in water 100 - Mg) Max supply structure and adverse effects on domestic use. 13. Copper (mg/L, Cu) 0.05 Astringent taste dis 1.5 - Max coloration and corrosion of

162Appendix

pipes fittings and utensils will be caused beyond this. 14. Manganese 0.1 Beyond this limit 0.3 - (mg/L, Mn) Max taste/appearance are affected, has advers effect on domestic use and water supply structure 15. Sulphate 200 Beyond this causes gastro 400 May be extended upto (mg/L, SO4) Max. intestinal irritation when 400 provided magnesium or sodium are magnesium (as Mg) present does not exceed 30 16. Nitrate (mg/L, 45 Beyond this 100 - NO3) Max. methaemoglobinemia takes place. 17. Fluoride (mg/L, F) 1.0 Fluoride may be kept as 1.5 - Max. low as possible. High fluoride may cause fluorosis. 18. Phenolic 0.001 Beyond this, it may cause 0.002 - Compounds (mg/L objectionable taste and C6H5OH) Max. odour 19. Mercury (mg/L Hg) 0.001 Beyond this the water No Relaxation. To be tested when Max becomes toxic pollution is suspected 20 Cadmium 0.01 Beyond this the water No Relaxation. To be tested when (mg/L, Cd) Max becomes toxic pollution is suspected 21. Selenium 0.01 Beyond this the water No Relaxation. To be tested when (mg/L, Se) Max becomes toxic. pollution is suspected 22. Arsenic 0.05 Beyond this the water No Relaxation To be tested when (mg/L, As) Max. becomes toxic pollution is suspected 23. Cyanide 0.05 Beyond this the water No Relaxation To be tested when becomes toxic pollution is suspected 24. Lead (mg/L Pb) 0.05 Beyond this the water No Relaxation To be tested when Max. becomes toxic pollution is suspected 25. Zinc (mg/L, Zn) 5 Beyond this limit it can 15 To be tested when Max. cause astringent taste and pollution is suspected an opalescence in water 26. Anionic detergents 0.2 Beyond this limit it can 1.0 To be tested when (mg/L, MBAS) cause a light froth in water pollution is suspected Max 27. Chromium 0.05 May be carcinogenic above - - (mg/L, Cr6+ this limit 28. Polynuclear - May be carcinogenic - - Aromatic Hydrocarbons (mg/l, PAH) Max 29. Mineral oil 0.01 Beyond this limit, 0.03 To be tested when (mg/L) undesirable taste and pollution is suspected odour after chlorination takes place 30. Pesticides (mg/L) Absent Toxic 0.001 - max Radioactive materials 31. Alpha emitters - - 0.1 - Bq/L Max 32. Beta emitters - - 1.0 - Pci/L Max 33. Alkalinity (mg/L,) 200 Beyond this limit, taste 600 - Max becomes unpleasant 34. Aluminum (mg/L, 0.03 Cumulative effect is 0.2 Al) Max reported to cause dementia 35. Boron (mg/L) Max 1.0 - 5.0 -

Appendix 163

APPENDIX 11: SAMPLE ENVIRONMENTAL SITE INSPECTION REPORT

Project Name Contract Number

NAME: ______DATE: ______TITLE: ______DMA: ______LOCATION: ______GROUP: ______

WEATHER: Project Survey Activity Design Stage Implementation Pre-Commissioning Guarantee Period

Monitoring Items Complianc e Compliance marked as Yes / No / Not applicable (NA) / Partially Implemented (PI) EHS supervisor appointed by contractor and available on site Archaeological Supervisor appointed by contractor and available on site Construction site management plan (spoils, safety, schedule, equipment etc.,) prepared Traffic management plan prepared Dust is under control Excavated soil properly placed within minimum space Construction area is confined; no traffic/pedestrian entry observed Surplus soil/debris/waste is disposed without delay Construction material (sand/gravel/aggregate) brought to site as & when required only Tarpaulins used to cover sand & other loose material when transported by vehicles After unloading , wheels & undercarriage of vehicles cleaned prior to leaving the site No AC pipes disturbed/removed during excavation No chance finds encountered during excavation Work is planned in consultation with traffic police Work is not being conducted during heavy traffic Work at a stretch is completed within a day (excavation, pipe laying & backfilling) Pipe trenches are not kept open unduly Road is not completely closed; work is conducted on edge; at least one line is kept open Road is closed; alternative route provided & public informed, information board provided Pedestrian access to houses is not blocked due to pipe laying Spaces left in between trenches for access Wooden planks/metal sheets provided across trench for pedestrian No public/unauthorized entry observed in work site Children safety measures (barricades, security) in place at works in residential areas Prior public information provided about the work, schedule and disturbances Caution/warning board provided on site Guards with red flag provided during work at busy roads Workers using appropriate PPE (boots, gloves, helmets, ear muffs etc) Workers conducting or near heavy noise work is provided with ear muffs Contractor is following standard & safe construction practices Deep excavation is conducted with land slip/protection measures

164Appendix

First aid facilities are available on site and workers informed Drinking water provided at the site Toilet facility provided at the site Separate toilet facility is provided for women workers Workers camps are maintained cleanly Adequate toilet & bath facilities provided Contractor employed local workers as far as possible Workers camp set up with the permission of PIU Adequate housing provided Sufficient water provided for drinking/washing/bath No noisy work is conducted in the nights Local people informed of noisy work No blasting activity conducted Pneumatic drills or other equipment creating vibration is not used near old/risky buildings

Signature ______

Sign off

______Name Name Position Position

Appendix 165

APPENDIX 12: QUARTERLY REPORTING FORMAT FOR ASSISTANT SAFEGUARDS OFFICER

1. Introduction • Overall project description and objectives • Description of sub-projects • Environmental category of the sub-projects • Details of site personnel and/or consultants responsible for environmental monitoring • Overall project and sub-project progress and status

Status of Sub-Project Sub-Project List of Progress No. Design Pre- Construction Operational Name Works of Works Construction Phase            

2. Compliance status with National/ State/ Local statutory environmental requirements No. Sub-Project Name Statutory Environmental Status of Action Required Requirements Compliance

3. Compliance status with environmental loan covenants No. (List schedule Covenant Status of Compliance Action Required and paragraph number of Loan Agreement)

4. Compliance status with the environmental management and monitoring plan • Provide the monitoring results as per the parameters outlined in the EMP. Append supporting documents where applicable, including Environmental Site Inspection Reports. • There should be reporting on the following items which can be incorporated in the checklist of routine Environmental Site Inspection Report followed with a summary in the semi-annual report send to ADB. Visual assessment and review of relevant site documentation during routine site inspection needs to note and record the following: o What are the dust suppression techniques followed for site and if any dust was noted to escape the site boundaries; o If muddy water was escaping site boundaries or muddy tracks were seen on adjacent roads; o adequacy of type of erosion and sediment control measures installed on site, condition of erosion and sediment control measures including if these were intact following heavy rain; o Are their designated areas for concrete works, and refuelling; o Are their spill kits on site and if there are site procedure for handling emergencies; o Is there any chemical stored on site and what is the storage condition?

166Appendix

o Is there any dewatering activities if yes, where is the water being discharged; o How are the stockpiles being managed; o How is solid and liquid waste being handled on site; o Review of the complaint management system; o Checking if there are any activities being under taken out of working hours and how that is being managed.

167

Summary Monitoring Table Impacts Mitigation Parameters Method of Location Date of Name of (List Measures Monitored (As a Monitoring of Monitoring Person from IEE) (List from minimum those Monitoring Conducted Who IEE) identified in the Conducted IEE should be the monitored) Monitoring Design Phase

Pre-Construction Phase

Construction Phase

Operational Phase

Overall Compliance with CEMP/ EMP No. Sub-Project EMP/ CEMP CEMP/ EMP Status of Action Name Part of Being Implementation Proposed and Contract Implemented (Excellent/ Satisfactory/ Additional Documents (Y/N) Partially Satisfactory/ Measures (Y/N) Below Satisfactory) Required

5. Approach and methodology for environmental monitoring of the project • Brief description on the approach and methodology used for environmental monitoring of each sub-project

6. Monitoring of environmental impacts on project surroundings (ambient air, water quality and noise levels) • Brief discussion on the basis for monitoring • Indicate type and location of environmental parameters to be monitored • Indicate the method of monitoring and equipment to be used • Provide monitoring results and an analysis of results in relation to baseline data and statutory requirements

168Appendix

As a minimum the results should be presented as per the tables below.

Air Quality Results Parameters (Government Standards) Site No. Date of Testing Site Location PM10 SO2 NO2 µg/m3 µg/m3 µg/m3

Parameters (Monitoring Results) Site No. Date of Testing Site Location PM10 SO2 NO2 µg/m3 µg/m3 µg/m3

Water Quality Results Parameters (Government Standards) Site Date of Sampling Site Location pH Conductivity BOD TSS TN TP No. µS/cm mg/L mg/L mg/L mg/L

Parameters (Monitoring Results) Site Date of Sampling Site Location pH Conductivity BOD TSS TN TP No. µS/cm mg/L mg/L mg/L mg/L

Noise Quality Results LAeq (dBA) (Government Standard) Site No. Date of Testing Site Location Day Time Night Time

LAeq (dBA) (Monitoring Results) Site No. Date of Testing Site Location Day Time Night Time

7. Summary of key issues and remedial actions • Summary of follow up time-bound actions to be taken within a set timeframe.

8. Appendixes • Photos

169

• Summary of consultations • Copies of environmental clearances and permits • Sample of environmental site inspection report • Other