Register in our procurement system CTM Updated The Swedish Transport Administration's Procurement Schedule for more information regarding our ongoing procurements 2017-02-01

Activity Object name / assignment Description Website/ Type of Procurem Transq Road/Rail Type of assignment Region Schedule Scheduled Schedule Scheduled Scheduled Scheduled Procurement Estimate Contact more info procurement ent type d distributio d tender tender assignmen assignmen reliability d cost person distributi n date submissio submissio t start date t start (indicates the SEK on date (month) n date n date (year) date reliability of the millions (year) (year) (month) (month) contract data)

Central Preventative health services The Transport Administration wish to Services Framework No Both road Goods and services- The entire 2017 January 2017 February 2017 June Green - < 1 Dennis functions purchase services in preventative agreement and rail Indirect goods and Transport reliable Axelsson healthcare. The services are to services-HR Work Administration (within 3 prevent illness thus avoiding the environment months) need for sick leave. Central Framework agreement The procurement in question relates Services Framework No Both road Goods and services- The entire 2017 February 2017 March 2017 April Green - 5 - 10 Johan functions Environmental consultants - Air to the provision of consultancy agreement and rail Indirect goods and Transport reliable Widmark support to the Transport services-Operation-wide Administration (within 3 Administration in its assignment Environmental consultants months) involving the reviewing and improvement of the prevailing situation within the aviation sector. Central E-commerce solution Material Procurement of E-commerce Services Object- No Rail Goods and services-IT- The entire 2017 March 2017 April 2017 July Green - 1 - 5 Anders functions Service solution for ordering technically specific Software Transport reliable Hedberg approved material Administration (within 3 months) Central National framework agreement for Combination agreement with Services Framework No Both road Technical consultants- The entire 2017 March 2017 June 2017 October Green - 500 - 700 Bo Harnemo functions investigation, planning and design regional order

Central Increased working-life targeted Services Framework No Not Goods and services- The entire 2018 February 2018 March 2018 October Green - 1 - 5 Magnus functions rehabilitation and reorganisation agreement constructio Indirect goods and Transport reliable Westerberg and outplacement. n, general services-HR Work Administration (within 3 environment months) Central Optical cable with accessories Optical cable, joint boxes, optics- Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2018 March 2018 May 2019 January Green - 20 - 50 Åsa Hörnkvist functions related netting, optical horizontal leverantor/ specific Technically approved Transport reliable cabling, dividers The classification trafikverke material-Cables and Administration (within 3 system TransQ is being used for the ts- accessories months) procurement. Only companies that kvalificerin are prequalified in TransQ and which gssystem--- the Transport Administration invites transq to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Central Service for reception of reports The assignment pertains to a Services Object- No Not Goods and services- The entire 2018 April 2018 May 2018 July Green - < 1 Inger functions regarding suspected irregularities reception function. The reception specific constructio Indirect goods and Transport reliable Nordfors function shall receive, record, n, general services-Other Administration (within 3 transmit and statistically report tips months) on irregularities from the Transport Administration's employees, the general public and from other stakeholders. Central Destruction of unserviceable The classification system TransQ is Så-blir-du- Services Object- Yes Rail Goods and services- The entire 2018 August 2018 September 2019 January Green - < 1 Per Olofsson functions wooden sleepers being used for the procurement. leverantor/ specific Technically approved Transport reliable Only companies that are prequalified trafikverke material-sleepers and Administration (within 3 in TransQ and which the Transport ts- fortifications months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... "

Central Framework agreement regarding The framework agreement pertains Services Framework No Not Goods and services- The entire 2018 August 2018 September 2019 January Green - 10 - 20 Lars-Göran functions consultancy services within to resource and project consultancy agreement constructio Indirect goods and Transport reliable Törnlund documents and case management services within documents and case n, general services-Communications Administration (within 3 management as strategist, specialist months) and project manager/administration manager within the following competence areas: long-term preservation of analogue and electronic material, registration, search, case management and handling, e-services for case management, information/ document management and metadata, and electronic signatures/approval. Central Travel agency services for the The procurement pertains to travel Services Object- No Not Goods and services- The entire 2018 September 2018 November 2019 January Green - 1 - 5 Inger functions Transport Administration agency services for the Transport specific constructio Indirect goods and Transport reliable Nordfors Administration n, general services-HR Meetings and Administration (within 3 travel months) Central Concrete sleepers for the line with Concrete sleepers for the line with Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2018 September 2018 October 2019 October Green - 20 - 50 Magnus functions Pandrol e-clip fastening Pandrol e-clip fastening leverantor/ specific Technically approved Transport reliable Westerberg trafikverke material-sleepers and Administration (within 3 The classification system TransQ is ts- fortifications months) being used for the procurement. kvalificerin Only companies that are prequalified gssystem--- in TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Central Investigative resources To ensure a speedy investigation Services Object- No Not Goods and services- The entire 2018 November 2019 January 2019 February Red - data < 1 Inger functions during suspected irregularities. specific constructio Indirect goods and Transport not Nordfors n, general services-Other Administration confirmed Central Rail anchor Rail anchor. Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2019 January 2019 February 2019 November Green - 5 - 10 Magnus functions leverantor/ specific Technically approved Transport reliable Westerberg The classification system TransQ is trafikverke material-Rails Administration (within 3 being used for the procurement. ts- months) Only companies that are prequalified kvalificerin in TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Ferry Framework agreement – Provision Framework agreement for provision Services Framework No Maritime Goods and services- The entire 2017 February 2017 March 2017 July < 1 Johan operations of necessities for STA Road Ferries of necessities for STA Road Ferries agreement transport Indirect goods and Transport Widmark services-Other Administration Investment Measurement of the construction The procurement relates to Services Object- No Both road Technical consultants- The entire 2017 February 2017 March 2017 March Green - 5 - 10 Bengt process within the Transport consultancy services that will result specific and rail Specific technical areas of Transport reliable Wigernäs Administration’s investment in a framework agreement, which expertise Administration (within 3 activities will be used by the entire Transport months) Administration. The measurement shall relate to the construction process beginning with the production of the construction document and through the entire building phase. Investment Booster transformers in water Services Suborder No Rail Technical consultants- The entire 2017 February 2017 March 2017 March Green - < 1 Jan Snäll protection area services Planning & design Transport reliable Administration (within 3 months) Investment Remote control of output isolator Remote control of output isolator Contract < SEK 15 Suborder No Rail Contracts-BEST-Electrical The entire 2017 March 2017 March 2017 May Green - 1 - 5 Lillemor Bruce million Transport reliable Administration (within 3 months) Investment Booster transformers in water Around 25 booster transformers Contract < SEK 15 Object- No Rail Contracts-BEST-Electrical The entire 2017 March 2017 April 2017 May Green - 1 - 5 Jan Snäll protection area services Production have been identified, which in million specific Transport reliable consultation with an environment Administration (within 3 specialist have been assessed as the months) most important to rectify in terms of water protection The measure primarily involves taking down the pole-mounted transformers and placing them on the ground in a specially produced kiosk with an oil- collecting foundation.

Planning Qualitative and quantitative market Framework agreement for qualitative Services Framework No Not Goods and services- The entire 2017 March 2017 May 2017 August Green - 5 - 10 Sirpa Lindén surveys and quantitative market surveys and agreement constructio Indirect goods and Transport reliable opinion polls. n, general services-Planning Administration (within 3 months) Major projects Framework agreement specialists Framework agreement specialists Services Framework No Rail Technical consultants- The entire 2017 February 2017 February 2017 June Green - 100 - 300 Emma Lorenz traffic management system railway traffic management system railway agreement Specific technical areas of Transport reliable expertise Administration (within 3 months) Major projects National Framework agreement Consultancy services for Technical Services Framework No Both road Technical consultants- The entire 2019 January 2019 March 2019 August Green - 1 - 5 Lars-Göran regarding Consultancy services for specialist Approval support, agreement and rail Specific technical areas of Transport reliable Törnlund Technical specialist Approval Administrator for the approval process expertise Administration (within 3 support, Administrator for the and Technical safety management – months) approval process and Technical Signal and Track superstructure safety management – Signal and Track superstructure Trafikverksskol Procurement of IT courses in Office Procurement of courses within the Services Object- No Not Goods and services- The entire 2017 January 2017 February 2017 June Green - 1 - 5 Lill Ullman an suite and other administrative Office package etc. specific constructio Indirect goods and Transport reliable programs and, where needed n, general services-HR Professional Administration (within 3 teacher-led courses. development months)

Trafikverksskol Courses in leadership for project Courses in leadership for project Services Object- No Not Goods and services- The entire 2017 February 2017 March 2017 July Green - 1 - 5 Lill Ullman an managers managers specific constructio Indirect goods and Transport reliable n, general services-HR Professional Administration (within 3 development months) Maintenance Reserve power station Reserve power station Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2017 February 2017 March 2017 October Green - 20 - 50 Åsa Hörnkvist The classification system TransQ is leverantor/ specific Technically approved Transport reliable being used for the procurement. trafikverke material-Other Administration (within 3 Only companies that are prequalified ts- months) in TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Section insulator and fuse holder Section insulator and fuse holder for Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2017 February 2017 March 2017 July Green - 5 - 10 Bertil catenary line leverantor/ specific Technically approved Transport reliable Westerström The classification system TransQ is trafikverke material-Catenary line Administration (within 3 being used for the procurement. ts- material months) Only companies that are prequalified kvalificerin in TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Fixed signs Static or fixed signs for information Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2017 February 2017 March 2017 July Green - 50 - 100 Joachim Hall for rail passengers. The classification leverantor/ specific Technically approved Transport reliable system TransQ is being used for the trafikverke material-Track switches- Administration (within 3 procurement. Only companies that ts- Traffic information system months) are prequalified in TransQ and which kvalificerin the Transport Administration invites gssystem--- to participate in the procurement transq may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance UPS - uninterruptible power supply Uninterruptible power supply Så-blir-du- Goods Object- Yes Both road Goods and services- The entire 2017 February 2017 March 2017 September Green - 10 - 20 Åsa Hörnkvist The classification system TransQ is leverantor/ specific and rail Technically approved Transport reliable being used for the procurement. trafikverke material-Batteries and Administration (within 3 Only companies that are prequalified ts- reserve power months) in TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance For mobile measurement of road For mobile measurement of road Services Object- No Road Technical consultants- The entire 2017 February 2017 March 2017 July Green - 20 - 50 Patrik markings in Sweden markings in Sweden specific Specific technical areas of Transport reliable Bjerninge expertise Administration (within 3 months) Maintenance Oak sleepers Goods Object- No Rail Goods and services- The entire 2017 February 2017 April 2017 July Green - 1 - 5 Per Olofsson specific Technically approved Transport reliable material-sleepers and Administration (within 3 fortifications months) Maintenance Consultancy services railway The assignment concerns the Så-blir-du- Services Framework Yes Rail Technical consultants- The entire 2017 February 2017 April 2017 September Green - < 1 Lars-Göran engineering, within the categories inspection of fixed track installations leverantor/ agreement Specific technical areas of Transport reliable Törnlund of inspection and assessment in various stages of the construction trafikverke expertise Administration (within 3 and management process. The ts- months) classification system TransQ is being kvalificerin used for the procurement. Only gssystem--- companies that are prequalified in transq TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Consultancy services rail The purpose of the procurement is to Så-blir-du- Services Framework Yes Rail Technical consultants- The entire 2017 February 2017 April 2017 September Green - < 1 Lars-Göran engineering, in the category of draw up a framework agreement leverantor/ agreement Specific technical areas of Transport reliable Törnlund management support with suppliers to satisfy the trafikverke expertise Administration (within 3 Transport Administration's need of ts- months) consultancy services which kvalificerin constitute client support in the area gssystem--- of Rail Engineering Management transq Support. The classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance ISA consultant The classification system TransQ is Så-blir-du- Services Framework Yes Rail Technical consultants- The entire 2017 March 2017 April 2017 May Green - 5 - 10 Bo Ekdahl being used for the procurement. leverantor/ agreement Specific technical areas of Transport reliable Only companies that are prequalified trafikverke expertise Administration (within 3 in TransQ and which the Transport ts- months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Buffer stops and additional Buffer stops and additional Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2017 March 2017 April 2018 January Green - 5 - 10 Magnus elements elements. leverantor/ specific Technically approved Transport reliable Westerberg The classification system TransQ is trafikverke material-Rails Administration (within 3 being used for the procurement. ts- months) Only companies that are prequalified kvalificerin in TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... " Maintenance Periodic non-destructive testing Procure periodic non-destructive testing Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track The entire 2017 March 2017 May 2017 December Green - 100 - 300 Joakim Norell as part of the Transport Administration's leverantor/ million specific Transport reliable safety inspections. trafikverke Administration (within 3 By using non-destructive testing, we ts- months) have the chance to discover cracks and kvalificerin defects to rails, switches and welding gssystem--- before these cause rail fissures that can transq result in serious consequences. The classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... " Maintenance IP-based network cameras Cameras for monitoring with Så-blir-du- Goods Object- Yes Both road Goods and services- The entire 2017 March 2017 April 2017 September Green - 10 - 20 Joachim Hall associated licenses and accessories. leverantor/ specific and rail Technically approved Transport reliable The classification system TransQ is trafikverke material-Cameras Administration (within 3 being used for the procurement. ts- months) Only companies that are prequalified kvalificerin in TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Operation and Maintenance Maintenance Object- No Rail Contracts-Infrasystem- The entire 2017 March 2017 April Information Information Green - 1 - 5 Jan Snäll Electricity in Traffic centres, measures < SEK 5 specific Power railway Transport missing missing reliable Hallsberg, Norrköping, , million Administration (within 3 Göteborg and Malmö months) Maintenance Pile caps of concrete (base, stickers) The pile caps are intended to be a Goods Object- No Both road Goods and services- The entire 2017 March 2017 April 2017 May Green - < 1 Erik base for containers and bridge specific and rail Indirect goods and Transport reliable Oskarsson materiel on the ground. services-Other Administration (within 3 months) Maintenance Framework agreement Clearance The framework agreement relates to Contract > SEK 15 Framework No Rail Goods and services- The entire 2017 March 2017 May 2017 July Green - 20 - 50 Peter Hinders work during accidents clearance work mainly pertaining to million agreement Indirect goods and Transport reliable rail vehicles that have been involved services-Other Administration (within 3 in accidents on state-owned rail months) infrastructure. Maintenance Production of catenary hanger Catenary hanger made of bronze Så-blir-du- Services Object- Yes Rail Goods and services- The entire 2017 April 2017 May 2017 August Red - data 10 - 20 Bertil cable with mounted terminals The leverantor/ specific Technically approved Transport not Westerström classification system TransQ is being trafikverke material-Catenary line Administration confirmed used for the procurement. Only ts- material companies that are prequalified in kvalificerin TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Cantilever The classification system TransQ is Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2017 April 2017 May 2017 September Green - 20 - 50 Bertil being used for the procurement. leverantor/ specific Technically approved Transport reliable Westerström Only companies that are prequalified trafikverke material-Catenary line Administration (within 3 in TransQ and which the Transport ts- material months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... " Maintenance Motor operating device and Motor operating device and Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2017 May 2017 June 2017 September Green - 20 - 50 Sofia Elfving accessories accessories. The classification system leverantor/ specific Technically approved Transport reliable TransQ is being used for the trafikverke material-Other Administration (within 3 procurement. Only companies that ts- months) are prequalified in TransQ and which kvalificerin the Transport Administration invites gssystem--- to participate in the procurement transq may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance Framework agreement Electrical Framework agreement Electrical Så-blir-du- Services Framework Yes Rail Technical consultants- The entire 2017 May 2017 June 2017 September Red - data < 1 Dennis engineering engineering. The classification leverantor/ agreement Specific technical areas of Transport not Axelsson system TransQ is being used for the trafikverke expertise Administration confirmed procurement. Only companies that ts- are prequalified in TransQ and which kvalificerin the Transport Administration invites gssystem--- to participate in the procurement transq may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance RFID - Cabinet for RFID reader Cabinet for RFID equipment The Så-blir-du- Goods Framework Yes Rail Goods and services- The entire 2017 May 2017 June 2018 January Green - < 1 Lars-Göran classification system TransQ is being leverantor/ agreement Technically approved Transport reliable Törnlund used for the procurement. Only trafikverke material-Detection Administration (within 3 companies that are prequalified in ts- months) TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance RFID reader RFID reader. The classification Så-blir-du- Goods Framework Yes Rail Goods and services- The entire 2017 May 2017 June 2018 January Green - < 1 Lars-Göran system TransQ is being used for the leverantor/ agreement Technically approved Transport reliable Törnlund procurement. Only companies that trafikverke material-Detection Administration (within 3 are prequalified in TransQ and which ts- months) the Transport Administration invites kvalificerin to participate in the procurement gssystem--- may submit tenders. For more transq information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance RFID - Solid shaft encoder for RFID Solid shaft encoder for RFID. The Så-blir-du- Goods Framework Yes Rail Goods and services- The entire 2017 May 2017 June 2018 January Green - < 1 Lars-Göran classification system TransQ is being leverantor/ agreement Technically approved Transport reliable Törnlund used for the procurement. Only trafikverke material-Detection Administration (within 3 companies that are prequalified in ts- months) TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Wooden sleepers made of pine for The classification system TransQ is Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2017 May 2017 July 2017 October Green - 20 - 50 Per Olofsson delivery in 2019 being used for the procurement. leverantor/ specific Technically approved Transport reliable Only companies that are prequalified trafikverke material-sleepers and Administration (within 3 in TransQ and which the Transport ts- fortifications months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Framework agreement Bridge Maintenance Framework No Both road Contracts-Construction The entire 2017 May 2017 July 2018 December Green - < 1 Martina maintenance measures < SEK 5 agreement and rail work-Bridges Transport reliable Johansson million Administration (within 3 months) Maintenance Non impregnated wooden sleepers Non impregnated wooden sleepers Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2017 June 2017 July 2017 October Green - 20 - 50 Per Olofsson made of pine for delivery in 2019 made of pine for delivery in 2018 leverantor/ specific Technically approved Transport reliable The classification system TransQ is trafikverke material-sleepers and Administration (within 3 being used for the procurement. ts- fortifications months) Only companies that are prequalified kvalificerin in TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance End post and insulated bushing End post and insulated bushing Goods Object- No Rail Goods and services- The entire 2017 August 2017 September 2018 March Green - < 1 Magnus specific Technically approved Transport reliable Westerberg material-Rails Administration (within 3 months) Maintenance Track switches 60E, UIC60, BV50 Track switches 60E, UIC60, BV50 Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2017 August 2017 October 2019 October Green - > 1000 Magnus (complete and spare parts) and (complete and spare parts) and leverantor/ specific Technically approved Transport reliable Westerberg transition rails transition rails. trafikverke material-Track switches Administration (within 3 ts- months) The classification system TransQ is kvalificerin being used for the procurement. gssystem--- Only companies that are prequalified transq in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Prefabrication and transport of Prefabrication and transport of track Så-blir-du- Services Object- Yes Rail Goods and services- The entire 2017 August 2017 October 2019 October Green - 500 - 700 Magnus track switches switches. leverantor/ specific Technically approved Transport reliable Westerberg trafikverke material-Track switches Administration (within 3 The classification system TransQ is ts- months) being used for the procurement. kvalificerin Only companies that are prequalified gssystem--- in TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Tree securing manager Manage the contract work with Services Object- No Rail Technical consultants- The entire 2017 September Informatio October 2017 November Green - 1 - 5 Erik securing trees along all national lines specific Specific technical areas of Transport n missing reliable Oskarsson expertise Administration (within 3 months) Maintenance Contact wires The classification system TransQ is Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2017 September 2017 October 2018 January Green - 50 - 100 Bertil being used for the procurement. leverantor/ specific Technically approved Transport reliable Westerström Only companies that are prequalified trafikverke material-Catenary line Administration (within 3 in TransQ and which the Transport ts- material months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Construction of cabinets The classification system TransQ is Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2017 September 2017 October 2018 February Green - 10 - 20 Bertil being used for the procurement. leverantor/ specific Technically approved Transport reliable Westerström Only companies that are prequalified trafikverke material-Catenary line Administration (within 3 in TransQ and which the Transport ts- material months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... " Maintenance System product management relay- The assignment involves providing Så-blir-du- Services Object- Yes Rail Goods and services- The entire 2017 October 2017 December 2018 March Green - 20 - 50 Andreas Dahl based systems Management of System products leverantor/ specific Technically approved Transport reliable and the Facilities that include the trafikverke material-Signal box Administration (within 3 System products ts- material months) The assignment includes complete kvalificerin Management (management gssystem--- control/administration and technical transq support). The classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance Road network-wide road surface Services Object- No Road Technical consultants- The entire 2017 November 2018 February 2020 January Red - data 100 - 300 Åke Persson testing using a survey vehicle specific Specific technical areas of Transport not expertise Administration confirmed Maintenance NiCd batteries Coming later. The classification Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2017 December 2018 January 2018 April Green - 20 - 50 Malin system TransQ is being used for the leverantor/ specific Technically approved Transport reliable Hansson procurement. Only companies that trafikverke material-Batteries and Administration (within 3 are prequalified in TransQ and which ts- reserve power months) the Transport Administration invites kvalificerin to participate in the procurement gssystem--- may submit tenders. For more transq information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance Bars + miscellaneous ironwork Bars + miscellaneous ironwork. The Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2018 January 2018 February 2019 January Red - data 1 - 5 Andreas Dahl classification system TransQ is being leverantor/ specific Technically approved Transport not used for the procurement. Only trafikverke material-Track switches Administration confirmed companies that are prequalified in ts- TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Recovery, holding and scrapping of Services Object- No Road Goods and services- The entire 2018 January 2018 February 2018 June Green - < 1 Tim Lees vehicles specific Indirect goods and Transport reliable services-Other Administration (within 3 months) Maintenance Production Manager Monitoring and inspection of tree Services Object- No Rail Technical consultants- The entire 2018 January 2018 February 2018 March Green - 1 - 5 Erik securing works specific Specific technical areas of Transport reliable Oskarsson expertise Administration (within 3 months) Maintenance Tree securing manager Manage contract work with clearing Services Object- No Rail Technical consultants- The entire 2018 February 2018 March 2018 May Green - 1 - 5 Erik next to the railway specific Specific technical areas of Transport reliable Oskarsson expertise Administration (within 3 months) Maintenance Felling manager/timber controller Manage tree specialist contract Services Object- No Rail Technical consultants- The entire 2018 February 2018 March Information May Green - 1 - 5 Erik work/responsible for commercial specific Specific technical areas of Transport missing reliable Oskarsson timber management, and expertise Administration (within 3 Norrland months) Maintenance Felling manager Inspection clearing contracts manage Services Object- No Rail Technical consultants- The entire 2018 February 2018 March 2018 May Green - 1 - 5 Erik contract work level crossings specific Specific technical areas of Transport reliable Oskarsson expertise Administration (within 3 months) Maintenance Metal cable Metal cable. The classification Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2018 February 2018 April 2019 January Green - 100 - 300 Per Olofsson system TransQ is being used for the leverantor/ specific Technically approved Transport reliable procurement. Only companies that trafikverke material-Cables and Administration (within 3 are prequalified in TransQ and which ts- accessories months) the Transport Administration invites kvalificerin to participate in the procurement gssystem--- may submit tenders. For more transq information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance Blocking post with accessories. Blocking post with accessories. Goods Object- No Rail Goods and services- The entire 2018 March 2018 May 2018 August Green - < 1 Per Olofsson specific Technically approved Transport reliable material-Other Administration (within 3 months) Maintenance Periodical permit inspections of Machine measurements of the Så-blir-du- Maintenance Object- Yes Rail Goods and services- The entire 2018 April 2018 May 2018 November Green - 500 - 700 Per Olofsson tracks and overhead lines. Transport Administration's tracks leverantor/ measures < SEK 5 specific Technically approved Transport reliable and overhead lines. These trafikverke million material-Performance Administration (within 3 measurements are part safety ts- assessment months) inspection, part permit inspection kvalificerin component. The contract includes gssystem--- measurements and planning in transq addition to those activities required to access the tracks.

The classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Valve regulated Batteries Coming later. The classification Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2018 August 2018 September 2018 December Green - 20 - 50 Malin system TransQ is being used for the leverantor/ specific Technically approved Transport reliable Hansson procurement. Only companies that trafikverke material-Batteries and Administration (within 3 are prequalified in TransQ and which ts- reserve power months) the Transport Administration invites kvalificerin to participate in the procurement gssystem--- may submit tenders. For more transq information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance Concrete sleepers for track switches Concrete sleepers for track switches Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2018 August 2018 October 2019 October Green - 100 - 300 Magnus and Under Sleeper Pads SJ50, BV50, UIC60 and 60E. leverantor/ specific Technically approved Transport reliable Westerberg trafikverke material-Track switches Administration (within 3 The classification system TransQ is ts- months) being used for the procurement. kvalificerin Only companies that are prequalified gssystem--- in TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Rolling device for retrofitting in Rolling device for retrofitting in track Goods Object- No Rail Goods and services- The entire 2018 August 2018 October 2019 October Green - 1 - 5 Magnus track switches switches specific Technically approved Transport reliable Westerberg material-Track switches Administration (within 3 months) Maintenance Track details Track details The classification Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2018 August 2018 October 2019 April Green - 5 - 10 Per Olofsson system TransQ is being used for the leverantor/ specific Technically approved Transport reliable procurement. Only companies that trafikverke material-sleepers and Administration (within 3 are prequalified in TransQ and which ts- fortifications months) the Transport Administration invites kvalificerin to participate in the procurement gssystem--- may submit tenders. For more transq information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance Accessories snow protectors Accessories snow protectors Goods Object- No Rail Goods and services- The entire 2019 January 2019 February 2019 October Green - 1 - 5 Magnus specific Technically approved Transport reliable Westerberg material-Track switches Administration (within 3 months) Maintenance Tarpaulin for snow protectors Tarpaulin for snow protectors Goods Object- No Rail Goods and services- The entire 2019 January 2019 February 2019 October Green - < 1 Magnus specific Technically approved Transport reliable Westerberg material-Track switches Administration (within 3 months) Maintenance Hatches for track points Hatches for track points Goods Object- No Rail Goods and services- The entire 2019 January 2019 February 2019 October Green - 1 - 5 Magnus specific Technically approved Transport reliable Westerberg material-Track switches Administration (within 3 months) Maintenance Power supply equipment and spare To be supplemented later. The Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2019 January 2019 March 2019 June Green - 20 - 50 Malin parts classification system TransQ is being leverantor/ specific Technically approved Transport reliable Hansson used for the procurement. Only trafikverke material-Batteries and Administration (within 3 companies that are prequalified in ts- reserve power months) TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Coupling cable Coupling cable Goods Object- No Rail Goods and services- The entire 2019 January 2019 March 2019 September Green - 1 - 5 Sofia Elfving specific Technically approved Transport reliable material-Cables and Administration (within 3 accessories months) Maintenance Rubber spacer placed between the Rubber spacer placed between the Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2019 February 2019 March 2020 January Green - 5 - 10 Magnus rails and sleepers rails and sleepers for Fist-mount and leverantor/ specific Technically approved Transport reliable Westerberg Heyback-mount. trafikverke material-sleepers and Administration (within 3 ts- fortifications months) The classification system TransQ is kvalificerin being used for the procurement. gssystem--- Only companies that are prequalified transq in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Insulated joints for field assembly Insulated joints for field assembly. Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2019 March 2019 April 2020 March Green - 20 - 50 Magnus leverantor/ specific Technically approved Transport reliable Westerberg The classification system TransQ is trafikverke material-Rails Administration (within 3 being used for the procurement. ts- months) Only companies that are prequalified kvalificerin in TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... " Maintenance Compromise rails with glued Compromise rails with glued Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2019 March 2019 April 2020 March Green - 50 - 100 Magnus insulated joints insulated joints. leverantor/ specific Technically approved Transport reliable Westerberg trafikverke material-Rails Administration (within 3 The classification system TransQ is ts- months) being used for the procurement. kvalificerin Only companies that are prequalified gssystem--- in TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance National Framework agreement The assignment relates to Så-blir-du- Services Framework Yes Rail Technical consultants- The entire 2019 April 2019 June 2019 September Green - 1 - 5 Lars-Göran regarding Consultancy services consultancy services for statute leverantor/ agreement Project support Transport reliable Törnlund traffic safety statute writers writing relating to work environment trafikverke Administration (within 3 documents and traffic safety ts- months) documents, e.g. revision of kvalificerin regulations and the updating of gssystem--- comprehensive legal requirements transq and regulatory frameworks. The classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Road flaps The classification system TransQ is Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2019 May 2019 July 2019 October Green - 10 - 20 Per Olofsson being used for the procurement. leverantor/ specific Technically approved Transport reliable Only companies that are prequalified trafikverke material-Other Administration (within 3 in TransQ and which the Transport ts- months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Clamp for emergency splice Clamp for emergency splice Goods Object- No Rail Goods and services- The entire 2019 November 2019 December 2020 July Green - 1 - 5 Magnus specific Technically approved Transport reliable Westerberg material-Rails Administration (within 3 months) Maintenance Sleeper bolts Sleeper bolts. Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2020 February 2020 March 2021 January Green - 20 - 50 Magnus leverantor/ specific Technically approved Transport reliable Westerberg The classification system TransQ is trafikverke material-sleepers and Administration (within 3 being used for the procurement. ts- fortifications months) Only companies that are prequalified kvalificerin in TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... " Maintenance Specialist skills within RFID The assignment consists of assisting Så-blir-du- Services Framework Yes Rail Goods and services- The entire 2020 February 2020 April 2020 July Red - data 1 - 5 Lars-Göran the Transport Administration with leverantor/ agreement Technically approved Transport not Törnlund Specialist skills within the area of trafikverke material-Detection Administration confirmed RFID. The classification system ts- TransQ is being used for the kvalificerin procurement. Only companies that gssystem--- are prequalified in TransQ and which transq the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance Rails Rails. The classification system Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2021 March 2021 May 2022 January Green - > 1000 Sofia Elfving TransQ is being used for the leverantor/ specific Technically approved Transport reliable procurement. Only companies that trafikverke material-Rails Administration (within 3 are prequalified in TransQ and which ts- months) the Transport Administration invites kvalificerin to participate in the procurement gssystem--- may submit tenders. For more transq information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance Switch drives for speeds over 200 Switch drives for speeds over 200 Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2023 January 2023 March 2024 October Green - > 1000 Magnus km/h km/h. leverantor/ specific Technically approved Transport reliable Westerberg trafikverke material-Track switches Administration (within 3 The classification system TransQ is ts- months) being used for the procurement. kvalificerin Only companies that are prequalified gssystem--- in TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Snow protectors for the purpose of Snow protectors for the purpose of Så-blir-du- Goods Object- Yes Rail Goods and services- The entire 2023 January 2023 February 2023 October Green - 5 - 10 Magnus avoiding falling snow and ice from avoiding falling snow and ice from leverantor/ specific Technically approved Transport reliable Westerberg trains in track switches trains in track switches. trafikverke material-Track switches Administration (within 3 ts- months) The classification system TransQ is kvalificerin being used for the procurement. gssystem--- Only companies that are prequalified transq in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Central Conversion Swedish Railway Conversion Swedish Railway Contract > SEK 15 Object- No Not Contracts-Structures- Central Region 2017 March 2017 June 2017 August Green - 20 - 50 Peter Hinders functions Museum Museum million specific constructio Properties reliable n, general (within 3 months) Central Work requirements Railway Work requirements for maintenance Contract < SEK 15 Object- No Rail Contracts-Structures- Central Region 2017 April 2017 May 2017 June Green - 1 - 5 Peter Hinders functions Museum Gävle of the Railway Museum's vehicle million specific Properties reliable fleet. (within 3 months) Central Replacement of lifts Gävle Station Replacement of 3 lifts to platforms Contract < SEK 15 Object- No Rail Contracts-Structures- Central Region 2017 April 2017 May 2017 July Green - 1 - 5 Bo Ekdahl functions Gävle Station million specific Properties reliable (within 3 months) Central Replacement of lifts Töreboda Replacement of 2 lifts to platforms Contract < SEK 15 Object- No Rail Contracts-Structures- Central Region 2017 April 2017 May 2017 July Green - 1 - 5 Bo Ekdahl functions Station Töreboda Station million specific Properties reliable (within 3 months) Central Catering and restaurant assignment Catering and restaurant assignment Services Object- No Not Goods and services- Central Region 2017 October 2017 November 2018 January Red - data 1 - 5 Åke Persson functions for the Swedish Transport for the Swedish Transport specific constructio Indirect goods and not Administration's railway museum in Administration's railway museum in n, general services-Other confirmed Gävle Gävle Investment Scrapping of relay rack as well as Production Contract < SEK 15 Object- No Rail Contracts-BEST-Signal Central Region 2017 February 2017 March 2017 June Green - 5 - 10 Emilia updating of drawings (remainder) million specific reliable Edström from the EFBJ project, production (within 3 months) Investment Road 86/622 Timmervägen, Road 86/622 Timmervägen, Services Object- No Road Technical consultants- Central Region 2017 February 2017 March 2017 July Red - data < 1 Peter Karlsson Planning process Trimming and streamlining, road. specific Planning & design not Suborder from framework confirmed agreement Investment Road 622 Segersta Road 622 Segersta and road portal Contract > SEK 15 Object- No Rail Contracts-Construction Central Region 2017 February 2017 March 2018 February Green - 10 - 20 Marie million specific work-Bridges reliable Gustavsson (within 3 months) Investment E14 Future location in , E14 Future location in Sundsvall, Services Object- No Road Technical consultants- Central Region 2017 February 2017 March 2017 July Green - 1 - 5 Peter Karlsson Planning process Planning process specific Specific technical areas of reliable expertise (within 3 months) Investment Road 84 Hede pedestrian and cycle Contract < SEK 15 Suborder No Road Contracts-Ground Central Region 2017 February 2017 March 2017 May Green - 1 - 5 Håkan Sjödin route, Production million reliable (within 3 months) Investment Road 544 Pedestrian and cycle Road 544 Pedestrian and cycle route Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 February 2017 March 2017 September Green - 10 - 20 Håkan Sjödin route -Specksta, Production Matfors-Specksta million specific reliable (within 3 months) Investment Road 83/Road 696 Järvsö Road 83/Road 696 Järvsö Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 February 2017 March 2017 September Green - 5 - 10 Marie Intersection Intersection million specific reliable Gustavsson (within 3 months) Investment Bergsåker, Triangle track contract Preparatory work, Bergsåker triangle Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track Central Region 2017 February 2017 March Information Information Green - 10 - 20 Peter Karlsson E01 preparatory work track, canalisation work, drains, leverantor/ million specific missing missing reliable wells, catenary work, etc. The trafikverke (within 3 classification system TransQ is being ts- months) used for the procurement. Only kvalificerin companies that are prequalified in gssystem--- TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Road 745 Bjuråker-Näsviken- Road 745 Bjuråker-Näsviken- Services Object- No Road Technical consultants- Central Region 2017 February 2017 April 2017 March Green - 5 - 10 Magnus Hudiksvall, Planning process Hudiksvall specific Planning & design reliable Häggström (within 3 months) Investment Turnkey contract fencing measures Fencing measures within Central Contract > SEK 15 Object- No Rail Contracts-Ground Central Region 2017 February 2017 March 2017 April Green - 20 - 50 Lena within Central District District on the following sections million specific reliable Scherman Hisnoret-Ornäs (within 3 -Krylbo- Snickarbo months) Bomansberget-Gävle Brunflo-Ope Borlänge-Stora Tuna -Österut

Investment Gråda roundabout Road 70, Route 70 Gråda Roundabout Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 February 2017 March 2017 April Green - 10 - 20 Emilia production Borlänge TS measures million specific reliable Edström (within 3 months) Investment Road 975 New bridge Road 975 New bridge Näsåkersnipan, Services Object- No Road Technical consultants- Central Region 2017 February 2017 March 2017 July Green - 1 - 5 Håkan Sjödin Näsåkersnipan, Planning process + Ultimate bearing resistance risk specific Planning & design reliable construction document reduction (within 3 Possibly suborder from Framework months) agreement Investment For production of pedestrian and Construction Contract < SEK 15 Object- No Road Contracts-Construction Central Region 2017 February 2017 March 2017 August Green - 5 - 10 Peter Hinders cycle route Västanvik-Karlsarvet million specific work-Bridges reliable stage 2, Road 938 within (within 3 , County months) Investment E4 Through-road Älandsbro, E4 Through-road Älandsbro, Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2017 February 2017 April 2017 May Green - 20 - 50 Håkan Sjödin Production Trimming and streamlining, road million specific reliable (within 3 months) Investment E4 Västernorrland improved traffic Services Suborder No Road Technical consultants- Central Region 2017 February 2017 April 2017 May Green - 1 - 5 Håkan Sjödin safety, Planning process Planning & design reliable (within 3 months) Investment E16 Dala-Järna- For the construction of Road E16 Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2017 February 2017 June 2017 August Green - 100 - 300 Peter Hinders Dala Järna - Vansbro within Vansbro million specific reliable Municipality, County of Dalarna (within 3 Turnkey contract months)

Investment Measures Torsång Centrum and Measures Torsång Centrum and Services Object- No Road Technical consultants- Central Region 2017 February 2017 April 2017 July Green - 1 - 5 Peter Hinders school, Planning process school specific Planning & design reliable Probably framework agreement (within 3 months) Investment Ordinances replacement roads Ordinances/replacement roads Så-blir-du- Contract > SEK 15 Object- Yes Road Contracts-BEST-Signal Central Region 2017 February 2017 April 2018 March Green - 20 - 50 Håkan Sjödin Ånge-Sundsvall, production Central Line Ånge-Sundsvall, leverantor/ million specific reliable Production The classification system trafikverke (within 3 TransQ is being used for the ts- months) procurement. Only companies that kvalificerin are prequalified in TransQ and which gssystem--- the Transport Administration invites transq to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment Road 66 Östra Tandö-Bu, Construction document Services Object- No Road Technical consultants- Central Region 2017 February 2017 April 2017 July Green - 1 - 5 Peter Hinders Construction documents specific Planning & design reliable (within 3 months) Investment National replacement programme The classification system TransQ is Så-blir-du- Services Object- Yes Rail Technical consultants- Central Region 2017 March 2017 April 2017 May Green - 10 - 20 Håkan Sjödin road protection installations Alex, being used for the procurement. leverantor/ specific Planning & design reliable Investigation Only companies that are prequalified trafikverke (within 3 in TransQ and which the Transport ts- months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... "

Investment Refurbishment Röstbo passing Production of tender specifications Så-blir-du- Services Object- Yes Rail Technical consultants- Central Region 2017 March 2017 May 2017 August Green - 5 - 10 Marie station construction document and for turnkey contract BEST (Track, leverantor/ specific Planning & design reliable Gustavsson BPU (Site supervision) Electrical, Signal and Telecom) + BPU trafikverke (within 3 (Site supervision) The classification ts- months) system TransQ is being used for the kvalificerin procurement. Only companies that gssystem--- are prequalified in TransQ and which transq the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment Road 637 Söderala Pedestrian and Road 637 Söderala Pedestrian and Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 March 2017 April 2017 October Green - 10 - 20 Magnus cycle route cycle route million specific reliable Häggström (within 3 months) Investment Gävleborg County, Söderhamn- Söderhamn-Florhed cycle paths Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 March 2017 April 2017 October Green - 5 - 10 Magnus Florhed cycle paths million specific reliable Häggström (within 3 months) Investment Stage 2, project planning Gävle Production of 4 x tender documents, Så-blir-du- Services Object- Yes Rail Technical consultants- Central Region 2017 March 2017 April 2017 August Green - 5 - 10 Magnus Hamn 1 x TE, 3 x UE. The classification leverantor/ specific Planning & design reliable Häggström system TransQ is being used for the trafikverke (within 3 procurement. Only companies that ts- months) are prequalified in TransQ and which kvalificerin the Transport Administration invites gssystem--- to participate in the procurement transq may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment Mora-Garsås, intermediate block Contract < SEK 15 Object- No Rail Contracts-BEST-Signal Central Region 2017 March 2017 April 2017 October Green - 5 - 10 Emilia production million specific reliable Edström (within 3 months) Investment Gävle-Ställdalen (Villersmuren) Production. The classification system Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track Central Region 2017 March 2017 April 2018 April Red - data 50 - 100 Magnus passing station Kungsgården, TransQ is being used for the leverantor/ million specific not Häggström Production procurement. Only companies that trafikverke confirmed are prequalified in TransQ and which ts- the Transport Administration invites kvalificerin to participate in the procurement gssystem--- may submit tenders. For more transq information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment Property-related noise protection Contract < SEK 15 Object- No Rail Contracts-Structures- Central Region 2017 March 2017 April 2017 October Red - data 5 - 10 Magnus measures windows, Dingersjö million specific Properties not Häggström confirmed Investment BK74 E4 Through Central Region BK74 E4 Through Central Region Services Object- No Road Technical consultants- Central Region 2017 March 2017 April 2017 May Green - 1 - 5 Håkan Sjödin (reinforcement of 2 bridges), (reinforcement of 2 bridges) specific Planning & design reliable Construction Suborder from Framework (within 3 document+investigation of bearing agreement months) capacity Investment New platform Torpshammar, New platform Torpshammar, Central Services Suborder No Rail Technical consultants- Central Region 2017 March 2017 March 2017 July Red - data < 1 Magnus Central Line, Planning process incl. Line Planning & design not Häggström BPU confirmed Investment Replacement of road bridge over External assignment - Replacement Contract < SEK 15 Object- No Road Contracts-Construction Central Region 2017 March 2017 April 2017 October Green - 5 - 10 Håkan Sjödin railway at Härnösand Travel Centre, of road bridge over railway at million specific work-Bridges reliable production Härnösand Travel Centre (within 3 months) Investment Road 662 Bonäshamn - Huså, Road 662 Bonäshamn - Huså Services Object- No Road Technical consultants- Central Region 2017 March 2017 April 2017 June Green - 1 - 5 Peter Karlsson Unforeseen step 3 and 4 measures Probably framework agreement specific Planning & design reliable (within 3 months) Investment E4 Ullånger - Docksta E4 Ullånger-Docksta. Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2017 March 2017 June 2018 April Green - 100 - 300 Håkan Sjödin million specific reliable (within 3 months) Investment Co-financing train stop Nälden, Train stop Nälden, Services Object- No Rail Technical consultants- Central Region 2017 March 2017 May 2017 August Red - data 1 - 5 Peter Karlsson Planning process Probably Framework Agreement - specific Planning & design not Renewed exposure to competition confirmed Investment Property-related noise protection Contract < SEK 15 Object- No Rail Contracts-Structures- Central Region 2017 March 2017 May 2017 October Red - data 5 - 10 Magnus measures outdoor areas, Dingersjö million specific Properties not Häggström confirmed Investment V315 pedestrian and cycle route - Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 March 2017 April 2017 April Green - 5 - 10 Peter Karlsson Rätan million specific reliable (within 3 months) Investment Countryside efforts, bus stops Public transport measures Rural Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2017 March 2017 May 2017 October Green - 20 - 50 Marie investment Gävleborg, turnkey million specific reliable Gustavsson contract (within 3 months) Investment Modernisation lime cement Modernisation of lime cement in Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-Ground Central Region 2017 March 2017 May 2017 June Green - 50 - 100 Lillemor Bruce Nykroppa and Ställdalen Nykroppa and in Ställdalen. The leverantor/ million specific reliable project also includes a new trafikverke (within 3 distributing sub-station in Ställdalen. ts- months) The classification system TransQ is kvalificerin being used for the procurement. gssystem--- Only companies that are prequalified transq in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Road 321, Svenstavik - Månsåsen, Road 321, Svenstavik - Månåsen. Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2017 March 2017 May 2018 April Green - 100 - 300 Peter Karlsson Production Production million specific reliable (within 3 months) Investment Catenary measures Duved-Norska Catenary measures Duved-Norska Contract > SEK 15 Object- No Rail Contracts-BEST-Electrical Central Region 2017 March 2017 January Information Information Green - 20 - 50 Peter Karlsson boundary boundary, involves installation of a million specific missing missing reliable reinforcement cable Duved- (within 3 and replacement of existing electrical months) posts between Storlien and the Norwegian border. Investment PLK Central line Line section 221, PLK Central line Line section 221, Contract < SEK 15 Object- No Rail Contracts-BEST-Track Central Region 2017 March 2017 May 2017 October Red - data 10 - 20 Håkan Sjödin production Trimming and streamlining, railway million specific not (incl. maritime transport) confirmed Investment Road 675 Valne-Änge, production Road 675 Valne-Änge, production Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2017 April 2017 May 2018 April Green - 20 - 50 Håkan Sjödin million specific reliable (within 3 months) Investment Road 711, Bräcke - Albacken, Road 711 Bräcke Albacken Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2017 April 2017 May 2018 April Green - 100 - 300 Håkan Sjödin Production million specific reliable (within 3 months) Investment Road 83 Kilafors-Ljusdal Bus stops Road 83 Kilafors-Ljusdal Bus stops, Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 April 2017 May 2017 September Green - 5 - 10 Marie turnkey contract million specific reliable Gustavsson (within 3 months) Investment Infrastructure measures KOLL2020, Services Suborder No Road Technical consultants- Central Region 2017 April 2017 May 2017 August Green - 1 - 5 Håkan Sjödin Planning process Planning & design reliable (within 3 months) Investment Road 611 Dvärsett-Krokom Contract < SEK 15 Suborder No Road Contracts-Ground Central Region 2017 April 2017 May 2017 August Green - 5 - 10 Peter Karlsson pedestrian and cycle route, million reliable Production (within 3 months) Investment Ornäs ESIK, Planning process Services Suborder No Rail Contracts-BEST-Signal Central Region 2017 April 2017 May 2017 August Red - data 1 - 5 Emilia not Edström confirmed Investment Road 659, Så - Vik, production Road 659 Så-Vik Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 April 2017 May 2017 November Green - 5 - 10 Peter Karlsson million specific reliable (within 3 months) Investment Falun-Borlänge 1 Esik Hinsnoret, Bergslagen Line, W, Falun-Borlänge Contract < SEK 15 Object- No Rail Contracts-Ground Central Region 2017 April 2017 June 2017 December Green - 5 - 10 Emilia production 1 Esik Hinsnoret million specific reliable Edström (within 3 months) Investment Aerial scanning Hedesunda- Aerial scanning Hedesunda- Services Object- No Road Technical consultants- Central Region 2017 April 2017 May 2017 September Red - data 1 - 5 Magnus Gävle/Valbo Gävle/Valbo specific Specific technical areas of not Häggström expertise confirmed Investment Extended road protection Central Extended road protection Central Contract > SEK 15 Object- No Rail Contracts-Ground Central Region 2017 April 2017 June 2018 May Green - 50 - 100 Magnus Line Ånge - Sundsvall. Production Line Ånge - Sundsvall million specific reliable Häggström (within 3 months) Investment Road 86 Bergsåker-, section Road 86 Bergsåker-Kovland, section Services Suborder No Road Technical consultants- Central Region 2017 April 2017 June 2017 September Green - < 1 Peter Karlsson Kovland, construction document Kovland Planning & design reliable Suborder from Framework (within 3 agreement months) Investment Gällö, ESIK Contract < SEK 15 Object- No Rail Contracts-BEST-Signal Central Region 2017 May 2017 June 2017 August Red - data 10 - 20 Håkan Sjödin million specific not confirmed Investment Borlänge-, ESIK Construction Contract > SEK 15 Object- No Rail Contracts-BEST-Signal Central Region 2017 May 2017 June 2017 August Red - data 20 - 50 Emilia document million specific not Edström confirmed Investment Bergsåker, triangle track Bergsåker, triangle track The Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track Central Region 2017 May 2017 September 2017 October Green - 100 - 300 Peter Karlsson classification system TransQ is being leverantor/ million specific reliable used for the procurement. Only trafikverke (within 3 companies that are prequalified in ts- months) TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Demolition PLK Ådalen Line Salins Contract < SEK 15 Suborder No Rail Contracts-BEST-Signal Central Region 2017 May 2017 June 2017 August Green - 1 - 5 Peter Karlsson väg Åkrom, Production million reliable (within 3 months) Investment Rämshytte Tunnel Bergslagen Line, Services Object- No Rail Contracts-Construction Central Region 2017 May 2017 June 2017 August Red - data 10 - 20 Emilia Planning specific work-Tunnels not Edström confirmed Investment Sundsvall Travel Centre, Sundsvall, accessibility and travel Services Object- No Rail Technical consultants- Central Region 2017 May 2017 June 2017 October Green - 1 - 5 Magnus accessibility and platforms etc. centre specific Planning & design reliable Häggström (Construction document) Framework agreement (within 3 months) Investment E16 pedestrian and cycle path E16 pedestrian and cycle path Services Suborder No Road Technical consultants- Central Region 2017 May 2017 June 2017 October Green - < 1 Magnus interchange Hagaström, Planning interchange Hagaström Planning & design reliable Häggström process, construction document (within 3 months) Investment Road 678 Improved traffic safety Production Contract < SEK 15 Suborder No Road Contracts-Ground Central Region 2017 May 2017 June 2017 December Green - 1 - 5 Magnus Ullungsfors, production million reliable Häggström (within 3 months) Investment Road 623 Vevlinge-Bollnäs Construction Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 June 2017 July 2018 January Green - 1 - 5 Marie Pedestrian and cycle route, million specific reliable Gustavsson Construction (within 3 months) Investment Road 583 Iggesund-Hudiksvall Road 583 Iggesund-Hudiksvall Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 June 2017 August 2017 October Green - 1 - 5 Magnus Pedestrian and cycle route Pedestrian and cycle route million specific reliable Häggström (within 3 months) Investment Ludvika ESIK, construction Ludvika ESIK Services Suborder No Rail Technical consultants- Central Region 2017 June 2017 August 2017 October Red - data < 1 Emilia document Planning & design not Edström confirmed Investment Road 579 Ockelbo-Wij Gardens Construction Contract < SEK 15 Suborder No Road Contracts-Ground Central Region 2017 June 2017 August 2017 September Red - data 1 - 5 Magnus Pedestrian and cycle route, million not Häggström Construction confirmed Investment Åhlstavägen Fränsta, accident Contract < SEK 15 Suborder No Rail Contracts-BEST-Signal Central Region 2017 July 2017 August 2017 October Red - data 1 - 5 Håkan Sjödin blackspot plk, Production million not confirmed Investment Borlänge-Ornäs intermediate block, Contract < SEK 15 Object- No Rail Contracts-BEST-Signal Central Region 2017 August 2017 September 2018 March Green - 5 - 10 Emilia production million specific reliable Edström (within 3 months) Investment Road 84 left-turn lane Ulvberget, Contract < SEK 15 Suborder No Road Contracts-Ground Central Region 2017 August 2017 October 2017 November Green - 1 - 5 Marie Production million reliable Gustavsson (within 3 months) Investment E16 Through-road Hofors, E16 Through-road Hofors Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 October 2017 November 2018 May Green - 10 - 20 Magnus Gävleborg County million specific reliable Häggström (within 3 months) Investment db Avesta Krylbo-Dalslund, The classification system TransQ is Så-blir-du- Services Object- Yes Rail Technical consultants- Central Region 2017 October 2017 November 2018 March Red - data 20 - 50 Emilia construction document being used for the procurement. leverantor/ specific Planning & design not Edström Only companies that are prequalified trafikverke confirmed in TransQ and which the Transport ts- Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... "

Investment Increased protection e-signal, Production Contract < SEK 15 Object- No Rail Contracts-BEST-Track Central Region 2017 October 2017 November 2018 May Red - data 1 - 5 Magnus Naggen Hällan, Construction million specific not Häggström confirmed Investment Road 83 Norrborn Intersection, Road 83 Norrborn Intersection. Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 November 2017 December 2018 June Green - 1 - 5 Marie Production Potentially packaged with Bollnäs million specific reliable Gustavsson Vallsta (within 3 months) Investment Torpshammar new platform, Production Contract > SEK 15 Object- No Rail Contracts-Ground Central Region 2017 November 2017 December 2018 December Green - 10 - 20 Magnus construction million specific reliable Häggström (within 3 months) Investment Road 56 Hedesunda-Gävle/Valbo Production of a road plan Services Object- No Road Technical consultants- Central Region 2017 November 2017 October 2018 February Red - data 5 - 10 Magnus planning process specific Planning & design not Häggström confirmed Investment Sälen airport production v1053 Sälen Airport Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2017 November 2018 January 2018 February Green - 50 - 100 Emilia Performance contract million specific reliable Edström (within 3 months) Investment Road 592 Nordanede (591) - Road 592 Nordanede (591) - Services Suborder No Road Technical consultants- Central Region 2017 December 2018 January 2018 May Red - data < 1 Peter Karlsson Jämtland County border, Jämtland County border, ultimate Planning & design not Construction document bearing resistance. Construction confirmed document. Suborder from framework agreement Investment Borlänge, speed increase, Contract < SEK 15 Object- No Rail Contracts-BEST-Track Central Region 2017 December 2018 January 2018 March Red - data 1 - 5 Emilia Production million specific not Edström confirmed Investment Road 592 through Hara Pedestrian Road 592 through Hara Pedestrian Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2017 December 2018 February 2018 March Green - 5 - 10 Håkan Sjödin and cycle route, production and cycle route million specific reliable (within 3 months) Investment Railway bridges over RV 50 in Construction documents, road, Services Object- No Both road Technical consultants- Central Region 2017 December 2018 January 2018 May Red - data 1 - 5 Emilia Grängesberg, Construction railway and bridge specific and rail Planning & design not Edström documents confirmed Investment For the performance of Remote Covers the existing operational site. Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Signal Central Region 2017 December 2018 March 2018 March Green - 50 - 100 Claes blocking, new signal box at Mora, Existing signal box to be replaced leverantor/ million specific reliable Andersson Mora Municipality, Dalarna county with a new processor signal box. No trafikverke (within 3 external facility exists. A new facility ts- months) will thus be constructed. The kvalificerin classification system TransQ is being gssystem--- used for the procurement. Only transq companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Road 83 Bollnäs-Vallsta Road 83 Bollnäs-Vallsta Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2018 January 2018 February 2019 February Green - 50 - 100 Marie Packaged with Road 83 Norrborn million specific reliable Gustavsson intersection (within 3 months) Investment Signal measures Gävle C, Services Suborder No Rail Technical consultants- Central Region 2018 January 2018 February 2018 April Red - data 1 - 5 Marie Construction document Planning & design not Gustavsson confirmed Investment Road 983 Bro Edenforsen Contract < SEK 15 Object- No Road Contracts-Construction Central Region 2018 January 2018 February 2018 April Red - data 1 - 5 Håkan Sjödin (reinforcement BK4), Production million specific work-Bridges not confirmed Investment Road 562 Bus stop Travel Centre Contract < SEK 15 Suborder No Road Contracts-Ground Central Region 2018 January 2018 February 2018 April Red - data 1 - 5 Håkan Sjödin Sundsvall, Production million not confirmed Investment Hamn, Line, Sundsvalls Hamn Tunadal Line. The Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-Ground Central Region 2018 January 2018 March 2019 February Red - data 700 - 1000 Peter Karlsson Malandstriangeln etc. classification system TransQ is being leverantor/ million specific not used for the procurement. Only trafikverke confirmed companies that are prequalified in ts- TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Road 50/66 through Ludvika, Contract < SEK 15 Object- No Road Technical consultants- Central Region 2018 February 2018 March 2018 May Red - data 5 - 10 Emilia Bergslagsdiagonalen, Construction million specific Planning & design not Edström document confirmed Investment E14 Vik-Frönäset Pedestrian and E14 Vik-Frönäset Pedestrian and Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2018 February 2018 March 2018 April Red - data 5 - 10 Peter Karlsson cycle route, production cycle route million specific not confirmed Investment Stavre, Platforms, Production Contract < SEK 15 Object- No Rail Contracts-Ground Central Region 2018 February 2018 March 2018 May Red - data 10 - 20 Håkan Sjödin million specific not confirmed Investment Ljusdal, extension of platform Contract < SEK 15 Suborder No Rail Contracts-Ground Central Region 2018 February 2018 March 2018 May Green - 5 - 10 Håkan Sjödin million reliable (within 3 months) Investment Pilgrimstad, Platform Contract < SEK 15 Object- No Rail Contracts-Ground Central Region 2018 February 2018 March 2018 May Red - data 10 - 20 Håkan Sjödin million specific not confirmed Investment Stöde, Platform Contract < SEK 15 Object- No Rail Contracts-Ground Central Region 2018 February 2018 March 2018 May Red - data 10 - 20 Håkan Sjödin million specific not confirmed Investment 3 rest areas on the E45 Svenstavik, Contract > SEK 15 Object- No Road Contracts-Structures- Central Region 2018 February 2018 March 2018 June Red - data 20 - 50 Peter Karlsson Häggeån, Strömsund. Production million specific Properties not confirmed Investment Erikslund ESIK, Production Contract < SEK 15 Object- No Rail Contracts-BEST-Signal Central Region 2018 February 2018 March 2018 May Red - data 10 - 20 Håkan Sjödin million specific not confirmed Investment E16 Hofors-Engelsfors central crash Planning process Services Object- No Road Technical consultants- Central Region 2018 February 2018 March 2018 July Red - data 1 - 5 Magnus barrier, Planning process specific Planning & design not Häggström confirmed Investment E16 Interchange, Tegelbruket- Planning process Services Object- No Road Technical consultants- Central Region 2018 February 2018 March 2018 July Red - data 5 - 10 Magnus Hofors, planning process specific Planning & design not Häggström confirmed Investment Gävle Västra (Gävle hospital Gävle Västra (Gävle hospital Så-blir-du- Services Object- Yes Rail Technical consultants- Central Region 2018 February 2018 March 2018 July Red - data 10 - 20 Magnus platform), planning process platform), planning process. The leverantor/ specific Planning & design not Häggström classification system TransQ is being trafikverke confirmed used for the procurement. Only ts- companies that are prequalified in kvalificerin TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Road 331 Bridge Helgum, Contract > SEK 15 Object- No Road Contracts-Construction Central Region 2018 February 2018 March 2018 May Red - data 10 - 20 Håkan Sjödin Production million specific work-Bridges not confirmed Investment Storvreta - Gävle, Up rail, Rail Services Framework No Rail Technical consultants- Central Region 2018 February 2018 March 2018 May Red - data 1 - 5 Marie replacement, Construction agreement Planning & design not Gustavsson document confirmed Investment Sundsvall, E14 Sundsvall–Blåberget, E14/v86- Blåberget Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2018 February 2018 March 2019 March Green - 100 - 300 Peter Karlsson production million specific reliable (within 3 months) Investment E14 Hållandsbacke construction E14 Hållandsbacke construction Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2018 February 2018 April 2018 September Green - 5 - 10 Peter Karlsson million specific reliable (within 3 months) Investment E14 Rännbergsbacken Production E14 Rännbergsbacken Production Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2018 February 2018 April 2018 September Green - 10 - 20 Peter Karlsson million specific reliable (within 3 months) Investment Rest Area Storlien, production Rest Area Storlien Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2018 February 2018 April 2018 September Red - data 10 - 20 Peter Karlsson million specific not confirmed Investment Road 622 Ljustavägen - Ö Birsta Road 622 Ljustavägen - Ö Birsta Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2018 March 2018 April 2018 September Red - data 5 - 10 Peter Karlsson Pedestrian and cycle route, Pedestrian and cycle route million specific not production confirmed Investment Road 542 Matfors Vigge, production Road 542 Matfors Vigge Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2018 March 2018 May 2018 June Red - data 20 - 50 Peter Karlsson million specific not confirmed Investment Röstbo passing station Earthworks Röstbo passing station Earthworks Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track Central Region 2018 March 2018 April 2019 April Red - data 100 - 300 Marie and BEST contract and BEST contract, turnkey contract. leverantor/ million specific not Gustavsson The classification system TransQ is trafikverke confirmed being used for the procurement. ts- Only companies that are prequalified kvalificerin in TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Road 745 Bjuråker-Näsviken- Construction document Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2018 March 2018 April 2019 April Green - 50 - 100 Magnus Hudiksvall Production million specific reliable Häggström (within 3 months) Investment Road 592- Fillsta - Målsta, Road 592- Fillsta - Målsta, Pedestrian Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2018 March 2018 April 2018 October Red - data 1 - 5 Håkan Sjödin Pedestrian and cycle route, and cycle route million specific not Production confirmed Investment E16 pedestrian and cycle path Contract < SEK 15 Suborder No Road Contracts-Ground Central Region 2018 March 2018 April 2018 October < 1 Magnus interchange Hagaström, Contract million Häggström Investment E4 Kongberget-Gnarp, Production E4 Kongberget-Gnarp Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2018 March 2018 April 2019 April Red - data 500 - 700 Håkan Sjödin million specific not confirmed Investment Road 610 Torsta- Ösabacken- E14 Road 610 Torsta- Ösabacken- E14 Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2018 March 2018 May 2018 October Red - data 5 - 10 Håkan Sjödin Pedestrian and cycle route, Pedestrian and cycle route million specific not production confirmed Investment Borlänge-Ludvika intermediate Services Suborder No Rail Technical consultants- Central Region 2018 March 2018 May 2018 August Green - 1 - 5 Emilia block, Construction document Planning & design reliable Edström (within 3 months) Investment Rest Area Vansbro production Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2018 April 2018 May 2018 October Red - data 5 - 10 Emilia million specific not Edström confirmed Investment Borlänge-Ludvika, intermediate Contract > SEK 15 Object- No Rail Contracts-BEST-Signal Central Region 2018 April 2018 May 2019 April Red - data 20 - 50 Emilia block, Production million specific not Edström confirmed Investment Infrastructure measures KOLL2020, Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2018 April 2018 May 2018 August Red - data 10 - 20 Håkan Sjödin Production million specific not confirmed Investment Road 272 measures to increase Contract < SEK 15 Suborder No Road Contracts-Ground Central Region 2018 April 2018 May 2018 August Red - data < 1 Marie traffic safety Silverkällan-Gramre, million not Gustavsson Production confirmed Investment Road 68 Package of measures X Contract < SEK 15 Suborder No Road Contracts-Ground Central Region 2018 April 2018 May 2018 August Red - data < 1 Marie county, Production million not Gustavsson confirmed Investment Road 593 Through the community Road 593 Through the community of Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2018 April 2018 June 2018 November Red - data 1 - 5 Håkan Sjödin of Hackås Pedestrian and cycle Hackås Pedestrian and cycle route million specific not route, production confirmed Investment Road 592 Nordanede (591) - Road 592 Nordanede (591) - Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2018 April 2018 June 2019 May Red - data 20 - 50 Peter Karlsson Jämtland County border, Jämtland County border, ultimate million specific not Production bearing resistance. Production confirmed Investment Ludvika ESIK, production Ludvika ESIK Contract < SEK 15 Object- No Rail Contracts-Ground Central Region 2018 May 2018 June 2018 December Red - data 5 - 10 Emilia million specific not Edström confirmed Investment Construction of bridge and trough Construction of bridge and trough Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-Construction Central Region 2018 June 2018 August 2019 July Red - data 50 - 100 Magnus (Strömbrovägen) Gävle Harbour (Strömbrovägen) The classification leverantor/ million specific work-Bridges not Häggström system TransQ is being used for the trafikverke confirmed procurement. Only companies that ts- are prequalified in TransQ and which kvalificerin the Transport Administration invites gssystem--- to participate in the procurement transq may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment Moradal switch replacement (rail Contract < SEK 15 Object- No Rail Contracts-BEST-Track Central Region 2018 August 2018 September 2018 October Red - data 10 - 20 Magnus yard refurbishment), Production million specific not Häggström confirmed Investment New passing station Ombenning, Goods corridor, capacity, New Så-blir-du- Services Object- Yes Rail Technical consultants- Central Region 2018 September 2018 October 2019 January Red - data 5 - 10 Emilia construction document passing station Ombenning leverantor/ specific Planning & design not Edström Goods corridor Storvik-Frövi, trafikverke confirmed capacity package 1+2 and Sandviken- ts- Kungsgården passing station. The kvalificerin classification system TransQ is being gssystem--- used for the procurement. Only transq companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Action package through-road Action package through-road Ljusdal Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2018 September 2018 October 2019 October Red - data 10 - 20 Magnus Ljusdal (2 Cpl) (2 Cpl) million specific not Häggström confirmed Investment Bus stops Gustafs Road 70 Production Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2018 September 2018 October 2019 October Red - data 10 - 20 Emilia production million specific not Edström confirmed Investment Borlänge rail yard, construction Borlänge rail yard Services Object- No Rail Technical consultants- Central Region 2018 September 2018 October 2018 October Red - data 5 - 10 Emilia document specific Planning & design not Edström confirmed Investment Road 50 through Ludvika, stage 1 road 50 through Ludvika, Contract > SEK 15 Object- No Road Contracts-Ground Central Region 2018 October 2018 November 2019 April Red - data 20 - 50 Emilia Grängesbergsvägen production Bergslagsdiagonalen. million specific not Edström confirmed Investment Road 86 Bergsåker-Kovland, section Road 86 Bergsåker-Kovland, section Contract < SEK 15 Object- No Road Contracts-Ground Central Region 2018 October 2018 November 2019 May Red - data 10 - 20 Peter Karlsson Kovland, Production Kovland, Production million specific not confirmed Investment Building demolition Part 2 Gavle Building demolition Part 2 Contract < SEK 15 Object- No Rail Contracts-Ground Central Region 2018 December 2019 January 2019 March Red - data 1 - 5 Magnus Harbour million specific not Häggström confirmed Investment Railway bridges over RV 50 in Construction, road, railway and Contract > SEK 15 Object- No Rail Contracts-BEST-Track Central Region 2019 January 2019 February 2020 February Red - data 20 - 50 Emilia Grängesberg, production bridge million specific not Edström confirmed Maintenance Sleeper replacement Stöde - Sleeper replacement Stöde - Contract > SEK 15 Object- No Rail Contracts-BEST-Track Central Region 2017 March 2017 April 2017 May Green - 20 - 50 Emilia Vattjom million specific reliable Edström (within 3 months) Maintenance Framework Agreement Data The task involves the measurement Services Framework No Road Technical consultants- Central Region 2017 March 2017 April 2017 September Green - 20 - 50 Erik capture and updating for ADT of vehicle flows in order to calculate agreement Specific technical areas of reliable Oskarsson measurement in the Central/East the average annual daily traffic expertise (within 3 geographical areas (ADT). The assignment involves months) implementing the following work phases; planning of traffic measurement, traffic measurement, input data management for collected road traffic data, final inspection of collected road traffic data and updating of the Transport Administration’s register for road traffic data.

Maintenance Renovation Gravel road 801, Renovation Gravel road 801, Maintenance Object- No Road Contracts-Ground Central Region 2017 March 2017 April 2017 May Green - 5 - 10 Anders Jämtland County Jämtland County measures > SEK 5 specific reliable Boqvist million (within 3 months) Maintenance Railing measures Road 546, Road Railing measures Road 546, Road Maintenance Object- No Road Contracts-Ground Central Region 2017 March 2017 April 2017 May Green - 5 - 10 Anders 535, Jämtland County 535, Jämtland County measures > SEK 5 specific reliable Boqvist million (within 3 months) Maintenance Relining, central district, Counties of Relining, central district, Counties of Maintenance Object- No Road Contracts-Ground Central Region 2017 April 2017 May 2017 June Green - 10 - 20 Emilia Dalarna & Gävleborg Dalarna & Gävleborg measures > SEK 5 specific reliable Edström million (within 3 months) Maintenance Tree securing manager Manage the contract work with Services Object- No Rail Technical consultants- Central Region 2017 September 2017 October 2017 November Green - 1 - 5 Erik securing trees Bergslagen Line specific Specific technical areas of reliable Oskarsson expertise (within 3 months) Maintenance For performance of Basic road For performance of Basic road Basic contract Object- No Road Contracts-Basic contract Central Region 2017 October 2018 January 2018 September Green - 100 - 300 Emilia maintenance on public roads within maintenance on public roads within Maintenance specific road reliable Edström the area Avesta, County of Dalarna the area Avesta, County of Dalarna (within 3 months) Maintenance For performance of Basic road For performance of Basic road Basic contract Object- No Road Contracts-Basic contract Central Region 2017 October 2018 January 2018 September Green - 100 - 300 Emilia maintenance on public roads within maintenance on public roads within Maintenance specific road reliable Edström the area Rättvik, County of Dalarna the area Rättvik, County of Dalarna (within 3 months) Maintenance For performance of Basic road For performance of Basic road Basic contract Object- No Road Contracts-Basic contract Central Region 2017 October 2018 January 2018 September Green - 100 - 300 Emilia maintenance on public roads within maintenance on public roads within Maintenance specific road reliable Edström the area Krokom, County of the area Krokom, County of Jämtland (within 3 Jämtland months) Maintenance For performance of Basic road For performance of Basic road Basic contract Object- No Road Contracts-Basic contract Central Region 2017 October 2018 January 2018 September Green - 100 - 300 Emilia maintenance on public roads within maintenance on public roads within Maintenance specific road reliable Edström the area Örnsköldsvik, County of the area Örnsköldsvik, County of (within 3 Västranorrland Västranorrland months) Maintenance Basic rail maintenance, East Coast Contract relating to maintenance of Så-blir-du- Basic contract Object- Yes Rail Contracts-Basic contract Central Region 2017 December 2018 April 2019 September Red - data 300 - 500 Åke Persson Line the sections of railway line belonging leverantor/ Maintenance specific rail not to the . The trafikverke confirmed classification system TransQ is being ts- used for the procurement. Only kvalificerin companies that are prequalified in gssystem--- TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Tree securing in section Tree securing in section Grängesberg Maintenance Object- No Rail Contracts-BEST-Track Central Region 2018 March Informatio Information Information Information Green - 5 - 10 Jan Elf Grängesberg - Bredsjö - Bredsjö measures < SEK 15 specific n missing missing missing missing reliable million (within 3 months) Investment Vännäs Raising of the middle Vännäs Raising of the middle Services Suborder No Rail Technical consultants- North Region 2017 January 2017 February 2017 March Green - < 1 Pär Isaksson platform to middle height (FK platform to middle height Planning & design reliable plan/proj CTM-id 153812): (within 3 months) Investment Gällivare- Kiruna Catenary line Gällivare- Kiruna Catenary line Contract > SEK 15 Object- No Rail Contracts-BEST-Electrical North Region 2017 February 2017 March 2017 May Green - 50 - 100 Jan Snäll repair+auxiliary power Foundation repair+auxiliary power million specific reliable setting contract (within 3 months) Investment New blind tracks Lidlund & Contract < SEK 15 Object- No Rail Contracts-BEST-Track North Region 2017 February 2017 February 2017 May Green - 10 - 20 Pär Isaksson Brännberg (contract) million specific reliable (within 3 months) Investment E10 Roadside area Landsjärv- E10 Roadside area Gyljen-Leipojärvi Contract < SEK 15 Suborder No Road Contracts-Ground North Region 2017 February 2017 February 2017 March Green - 1 - 5 Jan Snäll Leipojärvi Production million reliable (within 3 months) Investment Hemavan TS measures Contract > SEK 15 Object- No Road Contracts-Ground North Region 2017 February 2017 March 2017 April Green - 20 - 50 Bo Harnemo million specific reliable (within 3 months) Investment Rectification of Wildlife obstacles Preparation of construction Services Suborder No Road Technical consultants- North Region 2017 February 2017 March 2017 April Green - 1 - 5 Veronica Rickleån (service) document for Rectification of Planning & design reliable Hendriksson Wildlife obstacles Rickleån. Probably (within 3 renewed exposure to competition on months) the framework agreement

Investment Road 818 Kilvo-Mukkavaara Performance of bearing capacity Contract > SEK 15 Object- No Road Contracts-Ground North Region 2017 March 2017 April 2017 May Green - 50 - 100 Kenneth measures. Performance contract million specific reliable Strandh (within 3 months) Investment E10 Bus stop at Abisko turist, Proj Services Suborder No Road Technical consultants- North Region 2017 March 2017 April 2017 June Green - 1 - 5 Jan Snäll Planning & design reliable (within 3 months) Investment Pedestrian and cycle route Buddbyn- Services Suborder No Road Technical consultants- North Region 2017 March 2017 March 2017 May Green - 1 - 5 Jan Snäll Svartbjörsbyn Proj Planning & design reliable (within 3 months) Investment Risk-reducing measures Krångfors, Risk-reducing measures Krångfors, Services Suborder No Road Contracts-Ground North Region 2017 March 2017 April 2017 May Green - 1 - 5 Veronica Skellefteå Municipality, Skellefteå Municipality, Västerbotten reliable Hendriksson Västerbotten County (Service) County (Service) Probably renewed (within 3 exposure to competition on the months) framework agreement

Investment BD 664 Nystrand Risk-reducing BD Road 664 Nystrand Risk-reducing Contract < SEK 15 Object- No Road Contracts-Ground North Region 2017 April 2017 May 2017 May Green - 10 - 20 Veronica measures (Contract) measures million specific reliable Hendriksson (within 3 months) Investment Tender documents, construction Services Suborder No Road Technical consultants- North Region 2017 April 2017 May 2017 May Green - 1 - 5 Veronica documents including construction Planning & design reliable Hendriksson documents for performance (within 3 contract road 363, Hällnäs, Vindelns months) municipality, Västerbotten county

Investment E4 Sikeå-Gumboda Contract > SEK 15 Object- No Road Contracts-Ground North Region 2017 April 2017 May 2018 April Red - data 100 - 300 Bo Harnemo million specific not confirmed Investment Roof measures Boden C (FK Production of tender Services Suborder No Rail Technical consultants- North Region 2017 April 2017 May 2017 June Green - < 1 Pär Isaksson Plan/Proj CTM-id 154071) documents/construction document Planning & design reliable (within 3 months) Investment Rectification of Wildlife obstacles, Rectification of Wildlife obstacles, Contract < SEK 15 Suborder No Road Contracts-Construction North Region 2017 April 2017 May 2017 June Green - 1 - 5 Veronica bridge over Rockbäcken, Road 363 bridge over Rockbäcken, Road 363 million work-Bridges reliable Hendriksson (Contract) possibly renewed exposure to (within 3 competition via the framework months) agreement Investment Performance of bearing capacity Bearing capacity measures. Contract > SEK 15 Object- No Road Contracts-Ground North Region 2017 May 2017 August 2017 September Green - 10 - 20 Victoria measures, Road 805 5-way junction, million specific reliable Davidsson Brutorp (within 3 months) Investment Tornehamn, inspection equipment Contract < SEK 15 Object- No Rail Contracts-BEST-Electrical North Region 2017 May 2017 August 2017 August Green - 10 - 20 Lillemor Bruce station computers million specific reliable (within 3 months) Investment Construction of side guard rail, Construction or rail that separates Contract < SEK 15 Suborder No Road Contracts-Ground North Region 2017 June 2017 August 2017 August Green - 1 - 5 Jan Snäll Road 97 and E4.15 Stage 1 the traffic on this section. Side guard million reliable rail Road 97 and E4.15. (within 3 months) Investment Planning E4 Salmis-Haparanda Construction document for dual Services Object- No Road Technical consultants- North Region 2017 June 2017 July 2017 October Green - 5 - 10 Bo Harnemo carriageway 2+1 specific Planning & design reliable (within 3 months) Investment Pedestrian and cycle route Through SN through Hedenäset Contract < SEK 15 Object- No Road Contracts-Ground North Region 2017 June 2017 August 2017 September Green - 5 - 10 Jan Snäll Hedenäset Production million specific reliable (within 3 months) Investment The Kiruna Project, New Road E10, The Kiruna Project, New Road E10, Contract > SEK 15 Object- No Road Contracts-Ground North Region 2017 June 2017 August 2017 May Green - 300 - 500 Curt-Olof Tuolluvaara-Karhuniemi section Tuolluvaara-Karhuniemi section. million specific reliable Pohjanen Performance contract (within 3 months) Investment Performance of bearing capacity Turnkey contract. Performance of Contract > SEK 15 Object- No Road Contracts-Ground North Region 2017 August 2017 November 2018 June Green - 50 - 100 Victoria measures, Road 726 Bygdsiljum - bearing capacity measures. million specific reliable Davidsson Burträsk within Robertsfors (within 3 Municipality in Västerbotten County months)

Investment Planning E4 Gumboda-Grimsmark Construction document for dual Services Suborder No Road Technical consultants- North Region 2017 August 2017 September 2018 January Red - data 1 - 5 Bo Harnemo carriageway 2+1. Planning & design not confirmed Investment Construction of side guard rail, Contract < SEK 15 Suborder No Road Contracts-Ground North Region 2017 September 2017 October 2017 October Green - 1 - 5 Jan Snäll Road 97 and E4.15 Stage 2 million reliable (within 3 months) Investment Performance of bearing capacity Performance of bearing capacity Contract > SEK 15 Object- No Road Contracts-Ground North Region 2017 September 2017 November 2018 May Green - 20 - 50 Victoria measures, Road 720 Kalix - measures. Turnkey contract. million specific reliable Davidsson Björkfors (within 3 months) Investment Performance of bearing capacity Performance of bearing capacity Contract > SEK 15 Object- No Road Contracts-Ground North Region 2017 September 2017 November 2018 May Green - 50 - 100 Victoria measures, Road 543 Nygård-Åträsk measures. million specific reliable Davidsson (within 3 months) Investment Åmsele new crossing place Åmsele new crossing place Contract > SEK 15 Object- No Rail Contracts-BEST-Track North Region 2017 October 2017 November 2018 January Red - data 20 - 50 Pär Isaksson (contract) million specific not confirmed Investment Gällivare- Kiruna Catenary line Contract > SEK 15 Object- No Rail Contracts-BEST-Electrical North Region 2017 October 2017 November 2018 February Red - data 100 - 300 Jan Snäll repair+auxiliary power Foundation million specific not setting contract confirmed Investment E4 Djäkneboda-Bygdeå Contract > SEK 15 Object- No Road Contracts-Ground North Region 2017 October 2017 November 2018 October Red - data 100 - 300 Bo Harnemo million specific not confirmed Investment Risk-reducing measures, Pansikån, Risk-reducing measures, Pansikån, Contract < SEK 15 Suborder No Road Contracts-Ground North Region 2017 October 2017 November 2017 December Green - 1 - 5 Veronica Road 374, Älvsbyn Municipality, Road 374, Älvsbyn Municipality, million reliable Hendriksson (Contract) Norrbotten County. Probably (within 3 renewed exposure to competition on months) the framework agreement Investment Umeå project, management of Management of approx. 50,000 - Contract < SEK 15 Object- No Road Contracts-Ground North Region 2017 November 2017 December 2018 May Red - data < 1 Bo Harnemo sulphide soil 100,000 m3 million specific not confirmed Investment Risk-reducing measures Risk-reducing measures Contract < SEK 15 Object- No Road Contracts-Ground North Region 2017 November 2017 December 2018 January Green - 5 - 10 Veronica Gammelgården 2 (Contract) Gammelgården 2 million specific reliable Hendriksson (within 3 months) Investment Vännäs Raising of the middle Vännäs Raising of the middle Contract > SEK 15 Object- No Rail Contracts-BEST-Track North Region 2018 January 2018 March 2018 April Green - 20 - 50 Pär Isaksson platform to middle height (contract) platform to middle height million specific reliable (within 3 months) Investment Parked - Production E4 Salmis- Contract > SEK 15 Object- No Road Contracts-Ground North Region 2018 February 2018 March 2018 March Red - data 100 - 300 Bo Harnemo Haparanda million specific not confirmed Investment Road 97 Stage II S Sunderbyn-Sävast Road 97 Stage II S Sunderbyn-Sävast Contract > SEK 15 Object- No Road Contracts-Ground North Region 2018 March 2018 April 2019 March Red - data 100 - 300 Bo Harnemo million specific not confirmed Investment Risk-reducing measures Mo Road Risk-reducing measures Mo Road Contract < SEK 15 Suborder No Road Contracts-Ground North Region 2018 March 2018 April 2018 May Green - 1 - 5 Veronica 573, Nordmaling Municipality, 573, Nodmaling Municipality, million reliable Hendriksson Västerbotten County (Contract). Västerbotten County (Contract). (within 3 Probably renewed exposure to months) competition on the framework agreement Investment Risk-reducing measures, Selet, Road Road 890, Risk-reducing measures Contract < SEK 15 Object- No Road Contracts-Ground North Region 2018 March 2018 April 2018 May Green - 5 - 10 Veronica 890, Västerbotten County Selet between Byske and Fällfors million specific reliable Hendriksson (Contract) (within 3 months) Investment Rectification of wildlife obstacles, Rectification of wildlife obstacles, Contract > SEK 15 Object- No Road Contracts-Construction North Region 2018 March 2018 April 2018 May Green - 10 - 20 Veronica new bridge over Lillån, Road 392, new bridge over Lillån, Road 392, million specific work-Bridges reliable Hendriksson Överkalix Municipality, Norrbotten Överkalix Municipality, Norrbotten (within 3 County (Contract) County months) Investment Roof measures Boden C (Contract) Contract < SEK 15 Object- No Rail Contracts-Structures- North Region 2018 March 2018 May 2018 June Green - 5 - 10 Pär Isaksson million specific Properties reliable (within 3 months) Investment Parked - Production E4 Gumboda- Contract > SEK 15 Object- No Road Contracts-Ground North Region 2018 April 2018 May 2019 April Red - data 100 - 300 Bo Harnemo Grimsmark million specific not confirmed Investment E4 Töre-Kalix Stage 3:3 Contract > SEK 15 Object- No Road Contracts-Ground North Region 2018 April 2018 May 2018 June Red - data 10 - 20 Bo Harnemo Reningsverket-Björkforsvägen million specific not confirmed Investment E10 Morjärv-Överkalix Contract > SEK 15 Object- No Road Contracts-Ground North Region 2018 April 2018 May 2018 May Red - data 10 - 20 Bo Harnemo million specific not confirmed Investment E10 Overtaking lane Contract > SEK 15 Object- No Road Contracts-Ground North Region 2018 April 2018 May 2018 June Red - data 20 - 50 Bo Harnemo Muorjevaarabackarna million specific not confirmed Investment E10 Avvakko-Lappesuando Contract > SEK 15 Object- No Road Contracts-Ground North Region 2018 April 2018 May 2018 June Red - data 100 - 300 Bo Harnemo million specific not confirmed Investment Umeå Project E10, Western Link Umeå Project E10, Western Link Contract > SEK 15 Object- No Road Contracts-Construction North Region 2018 April 2018 August 2018 September Red - data 300 - 500 Bo Harnemo bridge over Umeå River bridge over Umeå River million specific work-Bridges not confirmed Investment Cultural restoration Gammelstads Cultural restoration Gammelstads Contract > SEK 15 Object- No Road Contracts-Ground North Region 2018 April 2018 June 2018 June Green - 10 - 20 Veronica kyrkby, Luleå Municipality, kyrkby, Luleå Municipality, million specific reliable Hendriksson Norrbotten County (Contract) Norrbotten County (within 3 months) Investment Risk-reducing measures Nölviken, Risk-reducing measures Nölviken, Contract < SEK 15 Suborder No Road Contracts-Ground North Region 2018 May 2018 June 2018 June Green - 5 - 10 Veronica Road 370, Malå Municipality, Road 370, Malå Municipality, million reliable Hendriksson Västerbotten County (Contract) Västerbotten County (Contract). (within 3 Probably renewed exposure to months) competition on the framework agreement Investment Wildlife obstacles Rickleån SN Wildlife obstacles Rickleån Contract < SEK 15 Object- No Road Contracts-Ground North Region 2018 May 2018 June 2018 August Green - 5 - 10 Veronica (Contract) million specific reliable Hendriksson (within 3 months) Investment Risk-reducing measures Risk-reduction measures Contract > SEK 15 Object- No Road Contracts-Ground North Region 2018 May 2018 June 2018 July Green - 20 - 50 Veronica Furunäsvägen 755 (Contract) Furunäsvägen 755 million specific reliable Hendriksson (within 3 months) Investment Umeå Project E08, Western Link Umeå Project E08, Western Link Contract > SEK 15 Object- No Road Contracts-Ground North Region 2018 June 2018 October 2018 November Red - data 300 - 500 Bo Harnemo north of Umeå River north of Umeå River million specific not confirmed Investment Åmsele line section 152, new Åmsele line section 152, new passing Contract > SEK 15 Object- No Rail Contracts-BEST-Track North Region 2018 June 2018 August 2019 July Red - data 20 - 50 Jan Snäll passing station Production station million specific not confirmed Investment Umeå Project E09, Western Link Umeå Project E09, Western Link Contract > SEK 15 Object- No Road Contracts-Ground North Region 2018 August 2019 January 2019 February Red - data 300 - 500 Bo Harnemo south of Umeå River south of Umeå River million specific not confirmed Investment Road 522 pedestrian and cycle Contract < SEK 15 Object- No Road Contracts-Ground North Region 2018 October 2018 November 2019 April Red - data 10 - 20 Bo Harnemo route Röbäck-Stöcksjö million specific not confirmed Planning E10 Pedestrian and cycle route Plan, Construction document Services Suborder No Road Technical consultants- North Region 2017 March 2017 April 2017 May Green - 1 - 5 Jan Snäll through Gyljen Planning & design reliable (within 3 months) Major projects Project North Bothnia Line section Procurement of railway plan and Så-blir-du- Services Object- Yes Rail Technical consultants- North Region 2017 March 2017 March 2017 April Green - 20 - 50 Kenneth Dåva-Gryssjön system document. The classification leverantor/ specific Planning & design reliable Strandh system TransQ is being used for the trafikverke (within 3 procurement. Only companies that ts- months) are prequalified in TransQ and which kvalificerin the Transport Administration invites gssystem--- to participate in the procurement transq may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Major projects Project ERTMS - Construction The assignment falls within project Så-blir-du- Services Object- Yes Rail Technical consultants- North Region 2017 February 2017 March 2017 April Green - 10 - 20 Björn document project, Iron Ore Line ERTMS and relates to leverantor/ specific Planning & design reliable Gällivare - (Råtsi) investigations/production of manuals trafikverke (within 3 in facility design for the construction ts- months) document stage as well as the kvalificerin planning of tender documents for an gssystem--- external facility for the section transq Gällivare - (Råtsi). The classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance Consultants for cultural Services Object- No Road Technical consultants- North Region 2017 February 2017 February 2017 March Green - 1 - 5 Anders environment in North specific Specific technical areas of reliable Boqvist expertise (within 3 months) Maintenance For operation and maintenance as The object relates to operation and Maintenance Object- No Road Contracts-Infrasystems- North Region 2017 February 2017 March 2017 April Green - 20 - 50 Jan Snäll well as reinvestments of road maintenance as well as measures > SEK 5 specific Lighting road reliable lighting in County of Norrbotten reinvestments of road lighting in million (within 3 County of Norrbotten. months)

The assignment primarily includes preventive and corrective maintenance. The assignment may also involve new construction and conversion, the addition of devices and other operation and maintenance-related services within the operational area in question.

Maintenance Repair of Bergnäs bridge flaps as Performance contract. Contract < SEK 15 Object- No Road Contracts-Construction North Region 2017 March 2017 April 2017 July Green - < 1 Jan Eliasson well as running surface of rail head million specific work-Bridges reliable (within 3 months) Maintenance Integrated bridge maintenance in The contract relates to the Basic contract Object- No Road Contracts-Construction North Region 2017 May 2017 September 2018 January Green - 50 - 100 Jan Eliasson Västerbotten County construction of time and permit- Maintenance specific work-Bridges reliable controlled bridge maintenance in (within 3 Västerbotten County. months) Maintenance Performance of basic road Performance of basic road Basic contract Object- No Road Contracts-Basic contract North Region 2017 October 2018 February 2018 September Green - 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road reliable the area Arjeplog, County of the area Arjeplog, County of (within 3 Norrbotten Norrbotten months) Maintenance Performance of Basic road Performance of Basic road Basic contract Object- No Road Contracts-Basic contract North Region 2017 October 2018 February 2018 September Green - 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road reliable the area of southern Skellefteå, the area of southern Skellefteå, (within 3 County of Västerbotten County of Västerbotten months) Maintenance Performance of Basic road Performance of Basic road Basic contract Object- No Road Contracts-Basic contract North Region 2017 October 2018 February 2018 September Green - 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road reliable the area Vilhelmina, County of the area Vilhelmina, County of (within 3 Västerbotten Västerbotten months) Maintenance Performance of basic road Performance of basic road Basic contract Object- No Road Contracts-Basic contract North Region 2017 October 2018 February 2018 September Red - data 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road not the area Lycksele, Västerbotten the area Lycksele, Västerbotten confirmed County County Maintenance Performance of basic road Performance of basic road Basic contract Object- No Road Contracts-Basic contract North Region 2017 October 2018 February 2018 September Red - data 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road not the area Piteå, Norrbotten County the area Piteå, Norrbotten County confirmed

Maintenance Subproject manager road markings Subproject manager road markings Maintenance Object- No Road Technical consultants- North Region 2018 February 2018 March 2018 April Green - 1 - 5 Kenneth within Norrbotten County within Norrbotten County measures < SEK 5 specific Project support reliable Strandh million (within 3 months) Maintenance Performance of basic road Performance of basic road Basic contract Object- No Road Contracts-Basic contract North Region 2018 October 2019 February 2019 September Green - 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road reliable the area Storuman, County of the area Storuman, County of (within 3 Västerbotten Västerbotten months) Maintenance Performance of basic road Performance of basic road Basic contract Object- No Road Contracts-Basic contract North Region 2018 October 2019 February 2019 September Green - 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road reliable the area Arvidsjaur, County of the area Arvidsjaur, County of (within 3 Norrbotten Norrbotten months) Maintenance Performance of basic road Performance of basic road Basic contract Object- No Road Contracts-Basic contract North Region 2018 October 2019 February 2019 September Red - data 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road not the area Luleå, County of the area Luleå, County of Norrbotten confirmed Norrbotten Maintenance Performance of Basic road Performance of Basic road Basic contract Object- No Road Contracts-Basic contract North Region 2018 October 2019 February 2019 September Red - data 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road not the area Kiruna, County of the area Kiruna, County of confirmed Norrbotten Norrbotten Maintenance Performance of basic road Performance of basic road Basic contract Object- No Road Contracts-Basic contract North Region 2018 October 2019 February 2019 September Red - data 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road not the area Norsjö, County of the area Norsjö, County of confirmed Västerbotten Västerbotten Maintenance Performance of Basic road Performance of Basic road Basic contract Object- No Road Contracts-Basic contract North Region 2018 October 2019 February 2019 September Red - data 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road not the area Kiruna, County of the area Kiruna, County of confirmed Norrbotten Norrbotten Maintenance Performance of Basic road Performance of Basic road Basic contract Object- No Road Contracts-Basic contract North Region 2019 October 2020 February 2020 September Red - data 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road not the area Boden, County of the area Boden, County of confirmed Norrbotten Norrbotten Maintenance Performance of Basic road Performance of Basic road Basic contract Object- No Road Contracts-Basic contract North Region 2019 October 2020 February 2020 September Red - data 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road not the area Kalix, County of the area Kalix, County of Norrbotten confirmed Norrbotten Maintenance Performance of Basic road Performance of Basic road Basic contract Object- No Road Contracts-Basic contract North Region 2019 October 2020 February 2020 September Red - data 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road not the area Övertorneå, County of the area Övertorneå, County of confirmed Norrbotten Norrbotten Maintenance Performance of Basic road Performance of Basic road Basic contract Object- No Road Contracts-Basic contract North Region 2019 October 2020 February 2020 September Red - data 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road not the area of northern Skellefteå, the area of northern Skellefteå, confirmed County of Västerbotten County of Västerbotten Maintenance Performance of basic road Performance of basic road Basic contract Object- No Road Contracts-Basic contract North Region 2019 October 2020 February 2020 September Red - data 100 - 300 Michaela Mau maintenance on public roads within maintenance on public roads within Maintenance specific road not the area Åsele, County of the area Åsele, County of confirmed Västerbotten Västerbotten Central Pallets and Collars Framework agreement for the Goods Framework No Rail Goods and services- South Region 2019 January 2019 February 2019 July Green - 1 - 5 Erik functions delivery of pallets and pallet collars agreement Indirect goods and reliable Oskarsson (EUR-pallet, half pallet, pallet collars, services-Material (within 3 half pallet collars, etc.) transports months) Investment Main road Minor measures for Services Object- No Road Technical consultants- South Region 2017 January 2017 March 2017 June Green - 5 - 10 Catarina public transport Skåne, bus stop specific Specific technical areas of reliable Fällström- expertise (within 3 Jacobsen months) Investment Main road Minor measures for Services Object- No Road Technical consultants- South Region 2017 January 2017 March 2017 June Green - 20 - 50 Catarina public transport Skåne, bus stop specific Specific technical areas of reliable Fällström- expertise (within 3 Jacobsen months) Investment Road 133 and 1007 Gripenberg’s Services Object- No Road Technical consultants- South Region 2017 January 2017 February 2017 March Green - < 1 Claes urban area Pedestrian and cycle specific Planning & design reliable Andersson paths, consultant plan Jönköping (within 3 County, Public transport and months) Pedestrian and cycle measures Investment Project Lund-Arlöv, four tracks - Must cover the upper part of the Så-blir-du- Services Object- Yes Both road Technical consultants- South Region 2017 February 2017 March 2017 July Green - < 1 Malin Project insurance Excess liability insurance. The classification leverantor/ specific and rail Specific technical areas of reliable Isaksson system TransQ is being used for the trafikverke expertise (within 3 procurement. Only companies that ts- months) are prequalified in TransQ and which kvalificerin the Transport Administration invites gssystem--- to participate in the procurement transq may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment Road 27 bypassing Bor - Consultant Road plan and tender documents? Services Object- No Road Technical consultants- South Region 2017 February 2017 April 2017 June Green - 1 - 5 Jessica Hedin specific Planning & design reliable (within 3 months) Investment Resource consultant work Maintenance Object- No Both road Technical consultants- South Region 2017 February 2017 March 2017 September Green - 1 - 5 Olle environment electricity and traffic measures < SEK 5 specific and rail Specific technical areas of reliable Rosengren safety road/rail million expertise (within 3 months) Investment Simrishamn, new platform - project Simrishamn, new platform Services Object- No Rail Technical consultants- South Region 2017 February 2017 April 2017 July Green - < 1 Mattias planning specific Planning & design reliable Larsson (within 3 months) Investment Nässjö-Eksjö, ATC and speed Nässjö-Eksjö, ATC and speed increase Contract < SEK 15 Suborder No Rail Contracts-BEST-Track South Region 2017 February 2017 March 2017 March Green - 1 - 5 Lillemor Bruce increase million reliable (within 3 months) Investment Roads 13 and 113, pedestrian and Performance contract Contract < SEK 15 Object- No Road Contracts-Ground South Region 2017 February 2017 April 2017 September Green - 5 - 10 Catarina cycle route, Stockamöllan- million specific reliable Fällström- Hasslebro (within 3 Jacobsen months) Investment Olofström noise barrier Volvo Olofström noise barrier Volvo Contract < SEK 15 Object- No Rail Contracts-Ground South Region 2017 February 2017 March 2017 August Green - 5 - 10 Martina million specific reliable Johansson (within 3 months) Investment Road 115 through Båstad urban Services Object- No Road Technical consultants- South Region 2017 March 2017 April 2017 July Green - < 1 Olle area, construction document specific Planning & design reliable Rosengren (within 3 months) Investment Road 115 through Båstad urban Services Object- No Road Technical consultants- South Region 2017 March 2017 April 2017 July Green - < 1 Olle area, planning process specific Planning & design reliable Rosengren (within 3 months) Investment Pedestrian and cycle portal Käglinge Pedestrian and cycle portal Käglinge Contract < SEK 15 Object- No Road Contracts-Ground South Region 2017 March 2017 May 2017 May Green - 5 - 10 Bengt million specific reliable Wigernäs (within 3 months) Investment Road 126 Northern entrance Contract < SEK 15 Object- No Road Contracts-Ground South Region 2017 March 2017 June 2017 August Green - 10 - 20 Jessica Hedin Alvesta million specific reliable (within 3 months) Investment E22 Interchange Gastelyckan - Production of tender documents for Services Object- No Road Technical consultants- South Region 2017 March 2017 April 2017 April Green - 1 - 5 Jessica Hedin Interchange Lund N (Interchange turnkey contract regarding specific Planning & design reliable Ideon) - Consultant conversion of E22 between (within 3 Interchange Gastelyckan and months) Interchange Lund N to ensure the supply of traffic to the operational areas Ideon and Pålsjö, to improve the accessibility on E22 and in Interchange Lund N, and to increase traffic safety through reduced risk of queue-related accidents. The project includes the construction of new additional lanes and the addition to Interchange Lund N of a new off-ramp and on-ramp to the Ideon/Pålsjö area.

Investment SSY Water protection Skåne County Contract < SEK 15 Object- No Road Contracts-Ground South Region 2017 March 2017 April 2017 May Green - 10 - 20 Catharina Tullstorp million specific reliable Selin (within 3 months) Investment Tranås-Vimnarp Rail replacement - Tranås-Flisby, rail replacement Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track South Region 2017 March 2017 April 2018 April Green - 50 - 100 Jessica Hedin Contract Tranås-Gripenberg downline rail leverantor/ million specific reliable replacement. trafikverke (within 3 Turnkey contract ts- months) Rail replacement on the section in kvalificerin question due to a manufacturing gssystem--- error entailing a risk of longitudinal transq vertical cracks The classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment Road 519 Räng Sand and Kämpinge Services Framework No Road Technical consultants- South Region 2017 March 2017 April 2017 August Green - < 1 Olle by, construction document agreement Planning & design reliable Rosengren (within 3 months) Investment Road 519 Räng Sand and Kämpinge Services Framework No Road Contracts-Ground South Region 2017 March 2017 April 2017 August Green - 1 - 5 Olle by, planning process agreement reliable Rosengren (within 3 months) Investment Road 101 TS measure Arrie - Road 101 TS measure Arrie - Käglinge Services Framework No Road Contracts-Ground South Region 2017 March 2017 April 2017 August Green - < 1 Bengt Käglinge and other localities and other localities agreement reliable Wigernäs (within 3 months) Investment Kattegattleden on the Bjäre Kattegattleden is a 370 km-long Contract < SEK 15 Object- No Road Contracts-Ground South Region 2017 March 2017 April 2017 October Green - 1 - 5 Olle peninsula, production national tourist bicycle route million specific reliable Rosengren between the cities of in (within 3 the north and Helsingborg in the months) south. This route should be close to the sea, free of cars and eventful for tourists and businesses.

Certain stretches, where the Transport Administration is the road management body, do not completely fulfil the traffic safety criteria formulated for tourist bicycle routes. In some parts new construction is required, and in certain parts improvements to the existing road network are required to make it suitable for cyclists. For example, there is need for new construction on a limited section on the Bjäre peninsula. Kattegattleden is a co-financed project between the along the stretch and the Transport Administration. The principal for the entire project is Region Halland.

This assignment involves a road plan Investment Road 11 Sjöbo (Anklam) - Tomelilla Roadwith design plan Road type 11 two Anklam (2). This - means Services Object- No Road Contracts-Ground South Region 2017 March 2017 May 2017 June Green - 5 - 10 Claes road plan Tomelilla, meeting separation specific reliable Andersson (within 3 months) Investment Ängelholm, increased speed track 3 - Ängelholm, increased speed track 3 Contract < SEK 15 Object- No Rail Contracts-BEST-Signal South Region 2017 March 2017 April 2017 October Red - data < 1 Mattias contract million specific not Larsson confirmed Investment E 65 Ystad Dragongatan E 65 Ystad Dragongatan intersections Contract < SEK 15 Object- No Road Contracts-Ground South Region 2017 March 2017 May 2017 October Green - 10 - 20 Lars Falk intersections million specific reliable (within 3 months) Investment Åstorp-Hässleholm, 160 km/h - Åstorp-Hässleholm, 160 km/h The Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Signal South Region 2017 March 2017 April 2017 March Green - 50 - 100 Mattias contract classification system TransQ is being leverantor/ million specific reliable Larsson used for the procurement. Only trafikverke (within 3 companies that are prequalified in ts- months) TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Tomelilla-Simrishamn, passing Tomelilla-Simrishamn, passing Services Object- No Rail Technical consultants- South Region 2017 March 2017 April 2017 July Green - 1 - 5 Mattias station - project planning station specific Planning & design reliable Larsson (within 3 months) Investment Road 1357 Glumslöv-Ålabodarna, Contract < SEK 15 Object- No Road Contracts-Ground South Region 2017 April 2017 May 2017 November Green - 1 - 5 Catarina Pedestrian and cycle route million specific reliable Fällström- (within 3 Jacobsen months) Investment E22 Mönsterås, boarding point - Procurement of road plan Services Object- No Road Technical consultants- South Region 2017 May 2017 June 2017 August Green - 1 - 5 Jessica Hedin Consultant Trimming and streamlining, road specific Planning & design reliable (within 3 months) Investment Road 25 Boasjön-Annerstad Trimming and streamlining, road Contract > SEK 15 Object- No Road Contracts-Ground South Region 2017 May 2017 June 2017 July Green - 100 - 300 Jessica Hedin oncoming traffic separation - million specific reliable Contract (within 3 months) Investment Road 108 Rinnebäck - Lackalänga, Road 108 Rinnebäck - Lackalänga, Services Framework No Road Contracts-Ground South Region 2017 May 2017 June 2017 June Green - < 1 Bengt Pedestrian and cycle route Pedestrian and cycle route agreement reliable Wigernäs (within 3 months) Investment Road 1370 Långeberga-Mörarp, Road 1370 Långeberga-Mörarp, Services Framework No Road Contracts-Ground South Region 2017 May 2017 June 2017 June Green - < 1 Bengt Pedestrian and cycle route Pedestrian and cycle route agreement reliable Wigernäs (within 3 months) Investment Road 26/40 Interchange Production of tender specifications Services Suborder No Road Technical consultants- South Region 2017 May 2017 May 2017 June Green - 1 - 5 Lillemor Bruce Hedenstorp, capacity reinforcement Planning & design reliable (within 3 months) Investment E6 Interchange Lomma S Contract < SEK 15 Object- No Road Contracts-Ground South Region 2017 May 2017 June 2017 June Red - data 10 - 20 Catharina million specific not Selin confirmed Investment For the production of a road plan Services Object- No Road Technical consultants- South Region 2017 May 2017 June 2017 July Green - 1 - 5 Claes for Road 23 Huseby - Marklanda specific Planning & design reliable Andersson (within 3 months) Investment Road 13 Hedeskoga-Sövestad, Road 13 Hedeskoga-Sövestad, Contract > SEK 15 Object- No Road Contracts-Ground South Region 2017 May 2017 June 2018 June Green - 10 - 20 Bengt Pedestrian and cycle route Pedestrian and cycle route million specific reliable Wigernäs (within 3 months) Investment Construction of E22 Sätaröd-Vä Construction of new motorway on Contract > SEK 15 Object- No Road Contracts-Ground South Region 2017 May 2017 November 2017 December Green - 500 - 700 Claes E22 between Sätaröd and Vä in million specific reliable Andersson Skåne. (within 3 months) Investment Superbuses in Skåne, investments Contract > SEK 15 Object- No Road Contracts-Ground South Region 2017 May 2017 July 2018 June Green - 100 - 300 Catarina in national infrastructure million specific reliable Fällström- (within 3 Jacobsen months) Investment Road 1722 Förslöv-Vistorpsvägen Contract < SEK 15 Object- No Road Contracts-Ground South Region 2017 May 2017 July 2017 December Green - 1 - 5 Olle Pedestrian and cycle route million specific reliable Rosengren (within 3 months) Investment Road 1723 Förslöv-Fogdarp Services Object- No Road Contracts-Ground South Region 2017 May Informatio Information Information Information Green - < 1 Olle Pedestrian and cycle route specific n missing missing missing missing reliable Rosengren (within 3 months) Investment Road 108 Lund /Gastelyckan - Road 108 Lund /Gastelyckan - Services Framework No Road Contracts-Ground South Region 2017 June 2017 July 2017 October Green - < 1 Bengt Knästorp/Staffanstorp Pedestrian Knästorp/Staffanstorp Pedestrian agreement reliable Wigernäs and cycle route and cycle route (within 3 months) Investment Road 136 Ekerum- Borgholm Bypass Glömminge Services Object- No Road Technical consultants- South Region 2017 June 2017 September 2017 October Green - 1 - 5 Jessica Hedin (bypassing Glömminge) - plan Ekerum-Borgholm Pedestrian/cycle specific Planning & design reliable and oncoming traffic separation (within 3 months) Investment Kävlinge, Rfsi (repeater distant Kävlinge, Rfsi (repeater distant signal Contract < SEK 15 Object- No Rail Contracts-BEST-Track South Region 2017 June 2017 July 2018 January Green - 1 - 5 Lars Falk signal balise group) balise group) million specific reliable (within 3 months) Investment Vinstorpsvägen, grade-separated Contract > SEK 15 Object- No Road Contracts-Construction South Region 2017 June 2017 July 2018 July Green - 20 - 50 Catarina junction million specific work-Bridges reliable Fällström- (within 3 Jacobsen months) Investment E6 at Vellinge Ängar, motorway Contract > SEK 15 Object- No Road Technical consultants- South Region 2017 June 2017 July 2018 July Green - 20 - 50 Catarina stop million specific Specific technical areas of reliable Fällström- expertise (within 3 Jacobsen months) Investment Main road Minor measures for Contract > SEK 15 Object- No Road Contracts-Ground South Region 2017 June 2017 July 2018 July Green - 100 - 300 Catarina public transport Skåne, bus stop million specific reliable Fällström- (within 3 Jacobsen months) Investment For construction of Road 23 Bypass Performance contract, Oncoming Contract > SEK 15 Object- No Road Contracts-Ground South Region 2017 June 2017 August 2017 September Green - 50 - 100 Claes Älmhult and Road 23 Älmhult - traffic separation, widening, and million specific reliable Andersson Ljungstorp oncoming traffic surfacing (within 3 separation, widening, and surfacing months) Investment Road 1613 Vid Äsperöd, Services Framework No Road Technical consultants- South Region 2017 June 2017 August 2017 November Green - < 1 Olle accessibility curve alignment, agreement Planning & design reliable Rosengren planning process (within 3 months) Investment Road 101 TS measure Arrie - Road 101 TS measure Arrie - Käglinge Services Framework No Road Contracts-Ground South Region 2017 July 2017 August 2017 November Green - 1 - 5 Bengt Käglinge and other localities and other localities agreement reliable Wigernäs (within 3 months) Investment Road 858 through Nordanå Road 858 through Nordanå Contract < SEK 15 Object- No Road Contracts-Ground South Region 2017 July 2017 August 2018 January Red - data 1 - 5 Bengt Pedestrian and cycle route Pedestrian and cycle route million specific not Wigernäs confirmed Investment Målilla, speed increase Målilla, speed increase Contract < SEK 15 Suborder No Rail Contracts-BEST-Track South Region 2017 August 2017 September 2017 September Green - 1 - 5 Lillemor Bruce million reliable (within 3 months) Investment Road 670 - Road 670 Listerby-Johannishus Contract < SEK 15 Suborder No Road Contracts-Ground South Region 2017 August 2017 September 2017 September Green - 5 - 10 Lillemor Bruce million reliable (within 3 months) Investment Contract inspection for Lund-Arlöv, Contract inspection for Lund-Arlöv, Så-blir-du- Services Object- Yes Both road Technical consultants- South Region 2017 August 2017 September 2017 October Red - data < 1 Malin four tracks four tracks. The classification system leverantor/ specific and rail Specific technical areas of not Isaksson TransQ is being used for the trafikverke expertise confirmed procurement. Only companies that ts- are prequalified in TransQ and which kvalificerin the Transport Administration invites gssystem--- to participate in the procurement transq may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment County of Skåne Cycle route sign County of Skåne Cycle route sign Services Object- No Road Contracts-Ground South Region 2017 August 2017 September 2018 January Green - < 1 Lars Falk specific reliable (within 3 months) Investment Construction of E4 Ljungby- Turnkey contract, upgrading to a 32- Contract > SEK 15 Object- No Road Contracts-Ground South Region 2017 August 2018 February 2018 March Green - 700 - 1000 Claes Toftanäs, section Kånna-Lagan and km motorway with a number of new million specific reliable Andersson section Lagan-Toftaholm, Ljungby and converted bridges, and water (within 3 Municipality, . source protection at Bergåsen, etc. months)

Investment Road 115 and 1765 in Östra Karup, Contract < SEK 15 Object- No Road Contracts-Ground South Region 2017 September 2017 October 2018 March Green - 5 - 10 Olle conversion of intersection, prod million specific reliable Rosengren (within 3 months) Investment Road 9 through Kivik, urban area Services Framework No Road Technical consultants- South Region 2017 September 2017 October 2018 January Green - 1 - 5 Olle measure, planning agreement Planning & design reliable Rosengren (within 3 months) Investment Road 1613 Vid Äsperöd, Services Framework No Road Technical consultants- South Region 2017 September 2017 October 2018 January Red - data < 1 Olle accessibility curve alignment, agreement Planning & design not Rosengren construction document confirmed Investment Road 108 Staffanstorp - Lund, dual Road 108 Staffanstorp - Lund, dual Contract > SEK 15 Object- No Road Contracts-Ground South Region 2017 September 2017 October 2018 October Green - 50 - 100 Lars Falk carriageway 4F carriageway 4F million specific reliable (within 3 months) Investment Road 108 Staffanstorp - Lund, dual Road 108 Staffanstorp - Lund, dual Services Object- No Road Contracts-Ground South Region 2017 September 2017 October 2018 February Green - 5 - 10 Lars Falk carriageway 4F carriageway 4F specific reliable (within 3 months) Investment For the performance of Remote Covers the existing railway section Så-blir-du- Contract > SEK 15 Framework Yes Rail Contracts-BEST-Signal South Region 2017 September 2017 October 2017 November Green - 100 - 300 Claes blocking, new signal box Ystad- Ystad-Tomelilla-Simrishamn. Existing leverantor/ million agreement reliable Andersson Simrishamn within Ystad and signal box to be replaced with a new trafikverke (within 3 Simrishamn municipalities, Skåne enlarged processor signal box. The ts- months) classification system TransQ is being kvalificerin used for the procurement. Only gssystem--- companies that are prequalified in transq TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Road 26/40 Interchange Road 26/40 Interchange Hedenstorp, Contract > SEK 15 Object- No Road Contracts-Ground South Region 2017 October 2017 November 2017 November Green - 20 - 50 Lillemor Bruce Hedenstorp, capacity reinforcement capacity reinforcement million specific reliable (within 3 months) Investment For production of tender Services Object- No Road Technical consultants- South Region 2017 October 2017 November 2017 December Green - 5 - 10 Claes documents for turnkey contract specific Planning & design reliable Andersson with construction site follow-up for (within 3 E65 Svedala-Börringe months) Investment Road 15 through Olofström Road 15 through Olofström Contract > SEK 15 Object- No Road Contracts-Ground South Region 2017 October Informatio Information 2018 January Green - 10 - 20 Lillemor Bruce million specific n missing missing reliable (within 3 months) Investment Road 557 Vekerum-Stilleryd Road 557 Vekerum-Stilleryd Contract < SEK 15 Suborder No Road Contracts-Ground South Region 2017 November 2017 December 2018 January Green - 5 - 10 Lillemor Bruce Pedestrian and cycle route Pedestrian and cycle route million reliable (within 3 months) Investment Road 133 and 1007 Gripenberg’s Services Object- No Road Technical consultants- South Region 2017 November 2017 December 2018 January Green - < 1 Claes urban area Pedestrian and cycle specific Planning & design reliable Andersson paths, consultant Tender (within 3 documents Jönköping County, months) Public transport and Pedestrian and cycle measures Investment Road 136 Ekerum- Borgholm Services Object- No Road Technical consultants- South Region 2017 November 2018 January 2018 April Green - 1 - 5 Jessica Hedin (bypassing Glömminge) - Consultant specific Planning & design reliable (within 3 months) Investment Road 1613 Vid Äsperöd, Contract < SEK 15 Object- No Road Contracts-Ground South Region 2017 December 2018 January 2018 June Green - 1 - 5 Olle accessibility curve alignment, million specific reliable Rosengren production (within 3 months) Investment Road 679 Rosenholm - Allatorp Road 679 Rosenholm - Allatorp Contract < SEK 15 Suborder No Road Contracts-Ground South Region 2017 December 2018 January 2018 January Green - 1 - 5 Lillemor Bruce million reliable (within 3 months) Investment Construction of Road 892, Rydet- Contract < SEK 15 Suborder No Road Contracts-Ground South Region 2017 December 2018 January 2018 February Green - 1 - 5 Claes Rottne, Pedestrian and cycle route million reliable Andersson (within 3 months) Investment Road 941/945 at Hardeberga, Road 941/945 at Hardeberga, Contract < SEK 15 Object- No Road Contracts-Ground South Region 2018 January 2018 February 2018 March Green - 1 - 5 Bengt intersection intersection million specific reliable Wigernäs (within 3 months) Investment Kävlinge - Arlöv, passing stations, Kävlinge - Arlöv, passing stations, Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track South Region 2018 January 2018 February 2019 February Green - 100 - 300 Lars Falk level crossing measure level crossing measure The leverantor/ million specific reliable classification system TransQ is being trafikverke (within 3 used for the procurement. Only ts- months) companies that are prequalified in kvalificerin TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... " Investment Kävlinge - Arlöv, passing stations, Kävlinge - Arlöv, passing stations, Så-blir-du- Services Object- Yes Rail Contracts-BEST-Track South Region 2018 January 2018 February 2018 June Green - 5 - 10 Lars Falk level crossing measure level crossing measure The leverantor/ specific reliable classification system TransQ is being trafikverke (within 3 used for the procurement. Only ts- months) companies that are prequalified in kvalificerin TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Platforms for passenger exchange Platforms for passenger exchange in Contract > SEK 15 Object- No Both road Contracts-Ground South Region 2018 January 2018 March 2019 February Green - 20 - 50 Lars Falk in Lomma and Furulund, passing Lomma and Furulund, passing tracks million specific and rail reliable tracks in Stävie, demolition of level in Stävie, demolition of level (within 3 crossings, grade-separated crossings, grade-separated months) pedestrian and cycle passages in pedestrian and cycle passages in Furulund. Furulund. The procurement will not be advertised. Pre-qualification is done via the classification system TransQ. Investment Grade-separated junction for road Road 913 Bjärred - Flädie, dual Contract > SEK 15 Object- No Both road Contracts-Construction South Region 2018 January 2018 March 2019 February Green - 50 - 100 Lars Falk 913 in Flädie carriageway million specific and rail work-Bridges reliable (within 3 months) Investment Road 115 through Båstad urban Contract < SEK 15 Object- No Road Contracts-Ground South Region 2018 February 2018 March 2018 August Green - 5 - 10 Olle area, production million specific reliable Rosengren (within 3 months) Investment Forserum, platform crossing Forserum, platform crossing Contract > SEK 15 Object- No Rail Contracts-Ground South Region 2018 February 2018 March 2018 April Red - data 20 - 50 Lillemor Bruce million specific not confirmed Investment Construction of a wildlife crossing Turnkey contract for construction of Contract > SEK 15 Object- No Road Contracts-Construction South Region 2018 February 2018 May 2018 May Green - 50 - 100 Claes Road 21 section Kristianstad- a wildlife crossing Road 21 section million specific work-Bridges reliable Andersson Hässleholm Kristianstad-Hässleholm (within 3 months) Investment Tågarp, new platform - project Services Object- No Rail Technical consultants- South Region 2018 February 2018 April 2018 July Red - data < 1 Mattias planning specific Planning & design not Larsson confirmed Investment Road 108 Rinnebäck - Lackalänga, Road 108 Rinnebäck - Lackalänga, Contract < SEK 15 Object- No Road Contracts-Ground South Region 2018 March 2018 April 2018 May Green - 5 - 10 Bengt Pedestrian and cycle route Pedestrian and cycle route million specific reliable Wigernäs (within 3 months) Investment E22 Lösen -Jämjö - Consultant Services Object- No Road Contracts-Ground South Region 2018 March 2018 April 2018 August Green - 20 - 50 Jessica Hedin Tender documents specific reliable (within 3 months) Investment E22 Bälö-Häggebotorp oncoming Trimming and streamlining, road Services Object- No Road Technical consultants- South Region 2018 March 2018 April 2018 August Red - data < 1 Jessica Hedin traffic separation - consultant specific Planning & design not tender documents confirmed Investment Road 1370 Långeberga-Mörarp, Contract < SEK 15 Object- No Road Contracts-Ground South Region 2018 March 2018 April 2018 May Red - data 5 - 10 Catharina Pedestrian and cycle route million specific not Selin confirmed Investment Ängelholm-Maria, double track Ängelholm - Maria, double track Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track South Region 2018 March 2018 May 2019 April Green - 50 - 100 Lars Falk expansion ( incl. Romaresväg) expansion. The classification system leverantor/ million specific reliable TransQ is being used for the trafikverke (within 3 procurement. Only companies that ts- months) are prequalified in TransQ and which kvalificerin the Transport Administration invites gssystem--- to participate in the procurement transq may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment E22 West , interchange E22 West Ronneby, interchange Services Suborder No Road Technical consultants- South Region 2018 April 2018 May 2018 July Green - 1 - 5 Lillemor Bruce trimming works trimming works Planning & design reliable (within 3 months) Investment Re- or new construction of 2.5 km Re- or new construction of 2.5 km Contract > SEK 15 Object- No Road Contracts-Ground South Region 2018 April 2018 May 2019 April Green - 20 - 50 Lars Falk road bypassing Assmåsa road bypassing Assmåsa million specific reliable (within 3 months) Investment Construction of Road 27 bypassing 7 km long, 3.5 km of which in a new Contract > SEK 15 Object- No Road Contracts-Ground South Region 2018 May 2018 October 2018 November Green - 100 - 300 Claes to Hallabro, Municipality alignment and widening to 2+1 in the million specific reliable Andersson of Ronneby, County of . existing alignment plus 2 bridges (within 3 months) Investment Road 740 Veberöd-Hemmestorp Road 740 Veberöd-Hemmestorp Contract < SEK 15 Object- No Road Contracts-Ground South Region 2018 May 2018 June 2018 December Green - 5 - 10 Lars Falk Pedestrian and cycle route Pedestrian and cycle route million specific reliable (within 3 months) Investment Road 936 Stångby-Håstad, Road 936 Stångby-Håstad, Services Object- No Road Contracts-Ground South Region 2018 May 2018 June 2018 October Green - 1 - 5 Lars Falk Pedestrian and cycle route Pedestrian and cycle route specific reliable (within 3 months) Investment Road 936 Stångby-Håstad, Road 936 Stångby-Håstad, Contract < SEK 15 Object- No Road Contracts-Ground South Region 2018 May 2018 June 2018 December Red - data 10 - 20 Lars Falk Pedestrian and cycle route Pedestrian and cycle route million specific not confirmed Investment Tomelilla-Simrishamn, passing Tomelilla-Simrishamn, passing Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track South Region 2018 May 2018 June 2019 June Red - data 50 - 100 Mattias station - contract station The classification system leverantor/ million specific not Larsson TransQ is being used for the trafikverke confirmed procurement. Only companies that ts- are prequalified in TransQ and which kvalificerin the Transport Administration invites gssystem--- to participate in the procurement transq may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment Åstorp-Teckomatorp III, Pågatåg Åstorp-Teckomatorp III, Pågatåg train Contract > SEK 15 Object- No Rail Contracts-BEST-Track South Region 2018 June 2018 July 2019 July Green - 300 - 500 Lars Falk train traffic traffic million specific reliable (within 3 months) Investment Åstorp-Teckomatorp III, Pågatåg Åstorp-Teckomatorp III, Pågatåg train Contract > SEK 15 Object- No Rail Contracts-BEST-Track South Region 2018 June 2018 July 2019 July Green - 50 - 100 Lars Falk train traffic traffic million specific reliable (within 3 months) Investment Älmhult - Olofström, Track Älmhult - Olofström, Track Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track South Region 2018 June 2018 July 2019 July Green - 100 - 300 Lars Falk replacement replacement The classification leverantor/ million specific reliable system TransQ is being used for the trafikverke (within 3 procurement. Only companies that ts- months) are prequalified in TransQ and which kvalificerin the Transport Administration invites gssystem--- to participate in the procurement transq may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment , exits, Track replacement Kalmar, exits, Track replacement Contract > SEK 15 Object- No Rail Contracts-BEST-Track South Region 2018 June 2018 July 2019 July Green - 10 - 20 Lars Falk million specific reliable (within 3 months) Investment Road 133 and 1007 Gripenberg’s Contract < SEK 15 Object- No Road Contracts-Ground South Region 2018 June 2018 August 2018 September Green - 1 - 5 Claes urban area Pedestrian and cycle million specific reliable Andersson paths, contract Jönköping County, (within 3 Public transport and Pedestrian and months) cycle measures Investment Two passing tracks; one in Kågeröd Two passing tracks; one in Kågeröd Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track South Region 2018 June 2018 August 2019 July Green - 10 - 20 Lars Falk and one in Svalöv. and one in Svalöv. New platforms in leverantor/ million specific reliable Teckomatorp, Svalöv, Kågeröd and trafikverke (within 3 Billesholm. Two pedestrian bridges ts- months) over the tracks; one in Teckomatorp kvalificerin and one in Svalöv. Noise barriers in gssystem--- Kågeröd and Svalöv, Raising of speed transq limit from 120 km/h to 160 km/h The classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Road 1370 Långeberga-Mörarp, Contract < SEK 15 Object- No Road Contracts-Ground South Region 2018 July 2018 August 2019 January Green - 5 - 10 Bengt Pedestrian and cycle route million specific reliable Wigernäs (within 3 months) Investment E22 West Ronneby, interchange E22 West Ronneby, interchange Contract > SEK 15 Object- No Road Contracts-Ground South Region 2018 July 2018 August 2019 October Red - data 10 - 20 Lillemor Bruce trimming works trimming works million specific not confirmed Investment Hässleholm-Vinslöv, medium Hässleholm-Vinslöv, medium Services Object- No Rail Technical consultants- South Region 2018 July 2018 September 2018 December Red - data < 1 Mattias blocking signals - project planning blocking signals specific Planning & design not Larsson confirmed Investment For construction of rest area Rest area Vandalorum E4 Road 27, Contract > SEK 15 Object- No Road Contracts-Ground South Region 2018 August 2018 September 2018 October Green - 10 - 20 Claes Vandalorum E4 Road 27 new rest area at E4 and Road 27 million specific reliable Andersson Värnamo S, performance contract (within 3 months) Investment Ystad, rail yard conversion Ystad, rail yard conversion The Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track South Region 2018 August 2018 September 2019 September Green - 50 - 100 Lars Falk classification system TransQ is being leverantor/ million specific reliable used for the procurement. Only trafikverke (within 3 companies that are prequalified in ts- months) TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Road 25, Österleden in Växjö - Contract > SEK 15 Object- No Road Contracts-Ground South Region 2018 August 2018 November 2019 January Green - 50 - 100 Jessica Hedin Contract million specific reliable (within 3 months) Investment Hässleholm-Vinslöv, medium Hässleholm-Vinslöv, medium Contract < SEK 15 Object- No Rail Contracts-BEST-Track South Region 2018 August 2018 October 2019 March Red - data 5 - 10 Mattias blocking signals - contract blocking signals million specific not Larsson confirmed Investment Road 136 Ekerum- Borgholm Contract > SEK 15 Object- No Road Contracts-Ground South Region 2018 September 2018 November 2019 February Green - 100 - 300 Jessica Hedin (bypassing Glömminge) - Contract million specific reliable (within 3 months) Investment E22 Interchange Gastelyckan - Conversion of E22 between Contract > SEK 15 Object- No Road Contracts-Ground South Region 2018 September 2019 January 2019 February Green - 100 - 300 Jessica Hedin Interchange Lund N (Interchange Interchange Gastelyckan and million specific reliable Ideon) - Contract Interchange Lund N to ensure the (within 3 supply of traffic to the operational months) areas Ideon and Pålsjö, to improve the accessibility on E22 and in Interchange Lund N, and to increase traffic safety through reduced risk of queue-related accidents. The project includes the construction of new additional lanes and the addition to Interchange Lund N of a new off-ramp and on-ramp to the Ideon/Pålsjö area.

Investment E22 Interchange Lund S Contract > SEK 15 Object- No Road Contracts-Ground South Region 2018 September 2018 October 2019 October Green - 100 - 300 Lars Falk million specific reliable (within 3 months) Investment Sandhem-Nässjö, speed adaptation The classification system TransQ is Så-blir-du- Contract > SEK 15 Object- Yes Both road Contracts-BEST-Track South Region 2018 October 2019 March 2019 June Green - 100 - 300 Jessica Hedin 160 km/hour and increased being used for the procurement. leverantor/ million specific and rail reliable capacity Only companies that are prequalified trafikverke (within 3 in TransQ and which the Transport ts- months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... "

Investment Road 32 Traneryd-Tranås S Road 32 Traneryd-Tranås S oncoming Contract > SEK 15 Object- No Road Contracts-Ground South Region 2018 October 2018 November 2019 October Green - 20 - 50 Bengt oncoming traffic separation traffic separation million specific reliable Wigernäs (within 3 months) Investment Månsarp, connection triangle track Månsarp, connection triangle track Contract > SEK 15 Object- No Rail Contracts-BEST-Track South Region 2018 October 2018 November 2019 October Red - data 20 - 50 Lillemor Bruce million specific not confirmed Investment Nässjö, track switch replacement Contract < SEK 15 Object- No Rail Contracts-BEST-Track South Region 2018 October 2018 November 2019 May Red - data 5 - 10 Lillemor Bruce 431, 495, 554 million specific not confirmed Investment Svartån Boxholm (Industrial track), Contract < SEK 15 Object- No Rail Contracts-BEST-Track South Region 2018 October 2018 November 2019 May Red - data 1 - 5 Lillemor Bruce bridge repainting million specific not confirmed Investment Tågarp, new platform - contract Contract < SEK 15 Object- No Maritime Contracts-BEST-Track South Region 2018 October 2018 November 2019 May Red - data 5 - 10 Mattias million specific transport not Larsson confirmed Investment Road 25 Sjöatorp-Forsa, oncoming Road 25 Sjöatorp-Forsa, oncoming Contract > SEK 15 Object- No Road Contracts-Ground South Region 2018 October 2018 December 2019 February Green - 50 - 100 Lillemor Bruce traffic separation traffic separation million specific reliable (within 3 months) Investment Ängelholm, synchronism and the Ängelholm, synchronism and the Contract < SEK 15 Object- No Road Contracts-Ground South Region 2018 October 2018 December 2019 May Green - < 1 Lars Falk platform crossing platform crossing million specific reliable (within 3 months) Investment Road 108 Lund /Gastelyckan - Road 108 Lund /Gastelyckan - Services Framework No Road Contracts-Ground South Region 2018 October 2018 December 2019 March Green - < 1 Bengt Knästorp/Staffanstorp Pedestrian Knästorp/Staffanstorp Pedestrian agreement reliable Wigernäs and cycle route and cycle route (within 3 months) Investment Svedala, switch lock speed . project Svedala, switch lock speed The Så-blir-du- Services Object- Yes Rail Technical consultants- South Region 2018 October 2018 December 2019 March Red - data < 1 Mattias planning classification system TransQ is being leverantor/ specific Planning & design not Larsson used for the procurement. Only trafikverke confirmed companies that are prequalified in ts- TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... " Investment Svedala, switch lock speed - Svedala, switch lock speed The Så-blir-du- Contract < SEK 15 Object- Yes Rail Contracts-BEST-Telecom South Region 2018 November 2018 December 2019 June Red - data 1 - 5 Mattias contract classification system TransQ is being leverantor/ million specific not Larsson used for the procurement. Only trafikverke confirmed companies that are prequalified in ts- TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment For the production of tender Tender documents for Road 136 Services Object- No Road Technical consultants- South Region 2018 December 2019 February 2019 February Green - < 1 Claes documents for Road 136 Rälla Cpl- Rälla Cpl-Ekerum oncoming traffic specific Planning & design reliable Andersson Ekerum oncoming traffic separation separation (within 3 months) Investment For the production of tender Services Object- No Road Technical consultants- South Region 2018 December 2019 February 2019 February Green - < 1 Claes documents for Road 136/966 at specific Planning & design reliable Andersson Rälla, cpl (within 3 months) Investment For preparation of tender Services Suborder No Road Technical consultants- South Region 2019 January 2019 March 2019 March Green - < 1 Claes documents for turnkey contract Planning & design reliable Andersson Road 23 Huseby – Marklanda (within 3 months) Investment Road 101 TS measure Arrie - Road 101 TS measure Arrie - Käglinge Contract < SEK 15 Object- No Road Contracts-Ground South Region 2019 January 2019 February 2019 August Green - 5 - 10 Bengt Käglinge and other localities and other localities million specific reliable Wigernäs (within 3 months) Investment Road 108 Lund /Gastelyckan - Road 108 Lund /Gastelyckan - Contract < SEK 15 Object- No Road Contracts-Ground South Region 2019 January 2019 March 2019 August Green - 1 - 5 Bengt Knästorp/Staffanstorp Pedestrian Knästorp/Staffanstorp Pedestrian million specific reliable Wigernäs and cycle route and cycle route (within 3 months) Trafikverksskol Procurement of green space Procurement of green space Services Object- No Not Goods and services- South Region 2017 January 2017 February 2017 May Green - < 1 Lill Ullman an management for Trafikverksskolan management for Trafikverksskolan in specific constructio Indirect goods and reliable in Ängelholm Ängelholm n, general services-Other (within 3 months) Maintenance For operation and maintenance of Maintenance Object- No Road Contracts-Infrasystem- South Region 2017 February Informatio Information 2017 September Green - 5 - 10 Jan Persson VVIS (Road Weather Information measures > SEK 5 specific VVIS n missing missing reliable System) in the counties of million (within 3 Östergötland, Jönköping, months) Kronoberg, Kalmar, Blekinge and Skåne Maintenance Bridge package Kalmar/Blekinge 1 Contract < SEK 15 Object- No Road Contracts-Construction South Region 2017 February 2017 March 2017 March Green - < 1 Jessica Hedin million specific work-UH Bridges & reliable tunnels (within 3 months) Maintenance Clearance of upkeep corridors after Maintenance Object- No Rail Contracts-BEST-Track South Region 2017 February 2017 March 2017 August Green - 5 - 10 Jan Elf tree securing works for the measures < SEK 15 specific reliable Hässleholm-Åstorp-Helsingborg, million (within 3 Åstorp-Kattarp sections months) Maintenance Clearance of upkeep corridors after Clearance of upkeep corridors after Maintenance Object- No Rail Contracts-BEST-Track South Region 2017 March Informatio Information Information Information Green - < 1 Jan Elf tree securing works for the tree securing works for the measures < SEK 5 specific n missing missing missing missing reliable Ängelholm-Trelleborg stretch Ängelholm-Trelleborg stretch million (within 3 months) Maintenance For operation and maintenance as Maintenance Object- No Road Contracts-Infrasystem- South Region 2017 March 2017 March 2017 November Green - 10 - 20 Jan Persson well as reinvestments of traffic measures > SEK 5 specific Manage traffic road reliable equipment in the counties of million (within 3 Jönköping, Kronoberg, Kalmar, months) Blekinge and Skåne Maintenance Integrated bridge maintenance Contract > SEK 15 Object- No Road Contracts-Construction South Region 2017 March 2017 May 2017 November Green - < 1 Jessica Hedin Kalmar/Blekinge million specific work-UH Bridges & reliable tunnels (within 3 months) Maintenance Basic contract railway Southern The classification system TransQ is Så-blir-du- Basic contract Object- Yes Rail Contracts-Basic contract South Region 2017 May 2017 August 2018 October Green - > 1000 Gunnar Main Line being used for the procurement. leverantor/ Maintenance specific rail reliable Stewén Only companies that are prequalified trafikverke (within 3 in TransQ and which the Transport ts- months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance 6-633-2 and 6-633-1 Röttle Replacement of edge girder, parapet, Contract > SEK 15 Object- No Road Contracts-Construction South Region 2017 October 2017 November 2018 January Green - 10 - 20 Jessica Hedin flyover constructions and bearings million specific work-UH Bridges & reliable tunnels (within 3 months) Maintenance Integrated bridge maintenance, Contract > SEK 15 Object- No Road Contracts-Construction South Region 2018 January 2018 March 2018 December Green - < 1 Jessica Hedin Kronoberg million specific work-UH Bridges & reliable tunnels (within 3 months) Investment Performance contract for measures The measures being addressed are Contract > SEK 15 Object- No Rail Contracts-BEST-Track West Region 2017 January 2017 March 2017 April Red - data 20 - 50 Jessica to increase capacity and safety on curve and level crossing measures. million specific not Dosenius the Fryksdal Line Stage 1 Kil-Sunne The measures have been divided up confirmed in the action package that has been produced within the framework for the work with level crossings on the Fryksdal Line. The line has been split up where Kil – Sunne represents Stage 1 and Sunne – Torsby is Stage 2. It is Stage 1 that this procurement concerns. The section is approx. 41 km long, 8 curves with a radius of 600 m or less have been identified as well as 105 crossing measures. In connection with the crossing measures, it is assessed that 6 km of new road needs to be built. This includes closure of crossings, protection measures and in a few cases new crossings. The road measures aim to connect together several nearby crossings which following the measures will be joined to comprise one crossing. There are relatively few tight curves on the route which keeps costs down. Investment E6 Tingstadsmotet-Backadalsmotet ConstructionThe gain in travel of additional time on the lane section Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 February 2017 April 2017 June Green - 100 - 300 Bo Tjörnbäck (Bäckebolsmotet), City of Tingstadsmotet-Backadalsmotet as million specific reliable Gothenburg well as noise protection measures (within 3 Tingstadsmotet-Bäckebolsmotet . months) Investment Road 27 Tranemo, Wildlife fence Road 27 Tranemo, Wildlife fence, Contract < SEK 15 Object- No Road Contracts-Ground West Region 2017 February 2017 March 2017 May Green - 10 - 20 Lisa Crona Performance contract million specific reliable (within 3 months) Investment Turnkey contract Passing stations Turnkey contract Passing stations Kil- Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track West Region 2017 February 2017 May 2017 June Green - 100 - 300 Jessica Kil-Laxå, Section Pråmkanalen Laxå, Section Pråmkanalen. The leverantor/ million specific reliable Dosenius classification system TransQ is being trafikverke (within 3 used for the procurement. Only ts- months) companies that are prequalified in kvalificerin TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... " Investment Production of tender documents for Production of tender documents for Så-blir-du- Services Object- Yes Rail Technical consultants- West Region 2017 February 2017 March 2017 April Green - 10 - 20 Claes remote blocking Herrljunga - Borås Performance contract remote leverantor/ specific Planning & design reliable Andersson blocking Herrljunga - Borås The trafikverke (within 3 classification system TransQ is being ts- months) used for the procurement. Only kvalificerin companies that are prequalified in gssystem--- TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Production of road plan, tender Production of road plan, tender Services Object- No Road Contracts-Ground West Region 2017 February 2017 March 2017 April Green - 20 - 50 Tommy documents and construction site documents and construction site specific reliable Ghose follow-up for E20 bypassing follow-up for E20 bypassing (within 3 Mariestad Mariestad months) Investment For the execution of tree felling E20 For the execution of tree felling E20 Contract < SEK 15 Object- No Road Contracts-Ground West Region 2017 February 2017 February 2017 March Green - < 1 Tommy Alingsås-Vårgårda, section Bälinge- Alingsås-Vårgårda, section Bälinge- million specific reliable Ghose Vårgårda within Alingsås and Vårgårda within Alingsås and (within 3 Vårgårda Municipality, Västra Vårgårda Municipality, Västra months) Götaland County Götaland County Investment Pedestrian and cycle route Suborders from the framework Contract < SEK 15 Suborder No Road Contracts-Ground West Region 2017 February 2017 March 2017 September Green - 1 - 5 Olle Tänvägen-Öckerövägen agreement will be carried out million reliable Rosengren through renewed exposure to (within 3 competition nationally. months)

The project covers construction of a new pedestrian and cycle route along Road 155 between Tärnvägen and Öckerövägen. The existing pedestrian and cycle route currently goes from Hönö Pinan’s ferry berth and along Road 155 to the intersection with Tärnvägen. Previously the pedestrian and cycle route continued parallel with Road 155 after the intersection to then turn off towards Heden. As it stands, the existing pedestrian and cycle route ends at the intersection, whereby cyclists and pedestrians are forced to take a detour of around 350 m via Heden's country road and Heinövägen, so as not to cycle or walk along Road 155. This detour means that pedestrians and especially cyclists Öckerö nevertheless choose that option, which entails a traffic hazard. Investment Turnkey contract Borås-Catenary Contract > SEK 15 Object- No Rail Contracts-BEST-Electrical West Region 2017 February 2017 March 2017 April Red - data 20 - 50 Jan Snäll replacement Production million specific not confirmed Investment Turnkey contract replacement of Replacement of road portal Contract < SEK 15 Object- No Both road Contracts-Construction West Region 2017 February 2017 March 2017 April Green - 10 - 20 Jessica road portal Heneporten Heneporten as well as connecting million specific and rail work-Bridges reliable Dosenius routes including traffic signals. (within 3 months) Investment Execution Turning track Alingsås, Execution Turning track Alingsås, VSB Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track West Region 2017 February 2017 June 2017 June Green - 100 - 300 Jessica VSB The classification system TransQ is leverantor/ million specific reliable Dosenius being used for the procurement. trafikverke (within 3 Only companies that are prequalified ts- months) in TransQ and which the Transport kvalificerin Administration invites to participate gssystem--- in the procurement may submit transq tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... " Investment E18 Fintatorp - Eriksberg, oncoming E18 Fintatorp - Eriksberg, oncoming Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 February 2017 March 2017 May Green - 10 - 20 Patrik traffic separation, Trimming and traffic separation million specific reliable Bjerninge streamlining, road, Performance (within 3 contract months) Investment Pedestrian and cycle route Steninge- Pedestrian and cycle route Steninge- Contract < SEK 15 Object- No Road Contracts-Ground West Region 2017 February 2017 April 2017 May Green - 10 - 20 Lisa Crona Stensjö and Stranninge - Morup Stensjö and Stranninge - Morup, million specific reliable Performance contract (within 3 months) Investment Replacement of BT with AT (more Replacement of BT with AT (more Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Electrical West Region 2017 February 2017 April 2017 May Red - data 100 - 300 Jessica power) Kil-Öxnered power), 18 locations, transformers, leverantor/ million specific not Dosenius etc. trafikverke confirmed Electric power The classification ts- system TransQ is being used for the kvalificerin procurement. Only companies that gssystem--- are prequalified in TransQ and which transq the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment For production of pedestrian and Pedestrian and cycle route Contract < SEK 15 Object- No Road Contracts-Ground West Region 2017 March 2017 April 2017 June Green - 5 - 10 Lisa Crona cycle route Torpa Torpavägen-Torkelstorpsvägen road million specific reliable Torkelstorpsvägen road 939 939, Turnkey contract (within 3 months) Investment Road 549, Slamby - Charlottenlund, Road 549, Slamby - Charlottenlund, Contract < SEK 15 Object- No Road Contracts-Ground West Region 2017 March 2017 April 2017 May Green - 1 - 5 Jan Elf measures to increase stability measures to increase stability million specific reliable (within 3 months) Investment Construction of Road 928 Section Road 928 Section Hedekas - Gesäter Contract < SEK 15 Object- No Road Contracts-Ground West Region 2017 March 2017 April 2017 May Red - data 10 - 20 Tommy Hedekas - Gesäter Risk-reducing Risk-reducing Measure million specific not Ghose measure confirmed Investment Establishment of road plans and In 2017-2021, the Transport Services Object- No Road Technical consultants- West Region 2017 March 2017 May 2017 July Green - 50 - 100 Lisa Crona tender request documentation for Administration intends to plan and specific Planning & design reliable pedestrian and cycle routes within build approx. 50 pedestrian and cycle (within 3 Västra Götaland, Halland and routes within Västra Götaland, months) Värmland County Halland and Värmland County

Investment For construction of E45 Dual 45 Ånimskog - Åmål, Stage 2 Tösse- Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 April 2017 August 2017 October Green - 100 - 300 Lisa Crona carriageway, Tösse - Åmål, within Åmål, Turnkey contract million specific reliable Åmål municipality, Västra Götaland (within 3 county months) Investment Construction E20 Alingsås – Performance of turnkey contract for Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 April 2017 October 2017 November Green - 700 - 1000 Tommy Vårgårda, section Bälinge - E20 Alingsås – Vårgårda, section million specific reliable Ghose Vårgårda Bälinge - Vårgårda (within 3 months) Investment Construction of Road 47, Pedestrian Road 47, Pedestrian and cycle route Contract < SEK 15 Object- No Road Contracts-Ground West Region 2017 April 2017 May 2017 September Green - 5 - 10 Jan Elf and cycle route Grästorp-Tre älgar Grästorp-Tre älgar million specific reliable (within 3 months) Investment Consultancy assignment for the Consultancy assignment for the Services Object- No Road Technical consultants- West Region 2017 April 2017 June 2017 July Green - 5 - 10 Bo Tjörnbäck preparation of a road plan and preparation of a road plan and specific Planning & design reliable tender documents Noise protection tender documents for performance (within 3 measures E6.20 Västerleden and contract E6.20 Noise protection months) tender documents Noise protection measures Västerleden, within E20 Ånäs, within Gothenburg Gothenburg Municipality, Västra Municipality, Västra Götaland Götaland County County and tender documents for performance contract E20 Noise protection measures Ånäs within Gothenburg Municipality, Västra Götaland County.

Investment Construction document/Tender 49 Axvall - Varnhem Services Object- No Road Technical consultants- West Region 2017 May 2017 June 2017 July Green - 5 - 10 Nathalie documents for Road 49 Axvall- specific Planning & design reliable Mjörnestål Varnhem (within 3 months) Investment Contract E6.21 Port of Contract in collaboration under ECI - Contract > SEK 15 Object- No Both road Contracts-Ground West Region 2017 May 2017 September 2018 April Green - > 1000 Elin Skarin Gothenburg/Lundbyleden, section Early Contract Involvement. The million specific and rail reliable Brantingsmotet-Ringömotet, procurement is carried out using (within 3 Streets in Backaplan and expansion restrictive procedure in two steps. months) of the Bohus Line within This relates to Step 1 Prequalification Gothenburg Municipality, Västra where the bidder submits an Götaland County -Step 1 application to submit tenders in the next step. Investment Painting of poles Kil-Öxnered Turnkey contract Painting poles Contract > SEK 15 Object- No Rail Contracts-BEST-Track West Region 2017 May 2017 June 2017 July Red - data 20 - 50 Jessica along a 150km section Kil-Öxnered million specific not Dosenius confirmed Investment Road 240 Sunnemo, bus transfer Road 240 Sunnemo, bus transfer Contract < SEK 15 Object- No Road Contracts-Ground West Region 2017 May 2017 June 2017 December Red - data 5 - 10 Patrik stop, Värmland County, Public stop million specific not Bjerninge transport confirmed Investment E6.21 Port of Contract > SEK 15 Object- No Both road Contracts-Ground West Region 2017 May 2017 June 2018 June Red - data 10 - 20 Elin Skarin Gothenburg/Lundbyleden - million specific and rail not Intermediate measure confirmed Investment Preparatory work for the Harbour Contract > SEK 15 Object- No Rail Contracts-Ground West Region 2017 May 2017 September 2017 November Red - data 10 - 20 Jonas Melén Line, relocation of football pitch million specific not confirmed Investment Execution Turning track Floda, VSB Execution Turning track Floda, VSB Contract > SEK 15 Object- No Rail Contracts-BEST-Track West Region 2017 June 2017 July 2018 June Red - data 100 - 300 Jan Elf million specific not confirmed Investment E6.20 Hisingsleden, southern E6.20 Hisingsleden, southern section - Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 June 2017 December 2018 January Green - 300 - 500 Patrik section - Halvors Link. Halvors Link. million specific reliable Bjerninge (within 3 months) Investment Varberg, double track (tunnel) A prequalification will be done with a Contract > SEK 15 Object- No Both road Contracts-Construction West Region 2017 July 2017 October 2018 June Red - data > 1000 Jonas Melén including Travel Centre. start date in July-Aug 2017 on condition million specific and rail work-Tunnels not that the project is included in the confirmed Transport Administration's proposal for a national transport plan for 2018-2029. The scheduled time for sending out the request to qualified bidders is December 2017. An ECI contract will be signed. Reference to the project's website http://www.trafikverket.se/varbergstun neln/ Investment E45 Slakthusmotet, City of Conversion of Slakthusmotet. Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 August 2018 January 2018 June Red - data 100 - 300 Bo Tjörnbäck Gothenburg million specific not confirmed Investment Road 675 Ulvesund Road plan Services Object- No Road Technical consultants- West Region 2017 August 2017 October 2018 January Red - data < 1 Roland specific Planning & design not Mårtensson confirmed Investment Completion of Åmål, platform Åmål, platform raising Contract < SEK 15 Object- No Rail Contracts-BEST-Track West Region 2017 September 2017 November Information Information Green - 10 - 20 Jan Elf raising million specific missing missing reliable (within 3 months) Investment Construction of Road 172 Road 172 Härsängen, profile Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 September 2017 November 2017 December Green - 10 - 20 Tommy Härsängen, profile adjustment, adjustment, curve alignment and million specific reliable Ghose curve alignment and widening widening (within 3 months) Investment Construction of 675 Ulvesund, risk- 675 Ulvesund, risk-reducing Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 September 2017 November 2017 December Green - 10 - 20 Tommy reducing measures measures million specific reliable Ghose (within 3 months) Investment Contract E6.21 Port of Contract in collaboration under ECI - Contract > SEK 15 Object- No Both road Contracts-Ground West Region 2017 October 2018 April 2019 March Green - > 1000 Elin Skarin Gothenburg/Lundbyleden, section Early Contract Involvement. The million specific and rail reliable Brantingsmotet-Ringömotet, procurement is carried out using (within 3 Streets in Backaplan and expansion restrictive procedure in two steps. months) of the Bohus Line within This related to Step 2 where the Gothenburg Municipality, Västra invitation to submit tenders is sent Götaland County -Step 2 to selected tender applicants. Investment Construction of Road 2183, Ed- Road 2183, Ed-Nössemark Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 October 2017 November 2018 January Red - data 20 - 50 Tommy Nössemark intermediate stage million specific not Ghose confirmed Investment Road 940 conversion E6-Forsbäck Performance contract Road 940 Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 October 2017 December 2018 May Red - data 50 - 100 Bo Ekdahl conversion E6-Forsbäck million specific not Road plan not established confirmed Investment Production of road plan, tender Production of road plan, tender Services Object- No Road Technical consultants- West Region 2017 November 2017 December 2018 March Green - 10 - 20 Tommy documents and construction site documents and construction site specific Planning & design reliable Ghose follow-up for E20 Götene - follow-up for E20 Götene - Mariestad (within 3 Mariestad months) Investment Road 940 Rösan-Forsbäck Turnkey contract Road 940 Rösan - Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 November 2018 February 2018 May Red - data 100 - 300 Bo Ekdahl Forsbäck AP/BH/Prod million specific not Road plan not established confirmed Investment Construction of E20 Tollered- E20, Tollered - Ingared Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 November 2018 February 2018 April Red - data 100 - 300 Tommy Ingared million specific not Ghose confirmed Investment Construction of Road 161, Rotvik- 161 Bäcken-Rotvik Contract > SEK 15 Object- No Road Contracts-Ground West Region 2017 December 2018 May 2018 July Green - 100 - 300 Patrik Bäcken million specific reliable Bjerninge (within 3 months) Investment Construction of Road 49 Axvall- 49 Axvall - Varnhem Contract > SEK 15 Object- No Road Contracts-Ground West Region 2018 February 2018 June 2018 September Red - data 100 - 300 Nathalie Varnhem million specific not Mjörnestål confirmed Investment Construction of Road 2504 Fåglum Road 2504 Fåglum Södra Härene Contract > SEK 15 Object- No Road Contracts-Ground West Region 2018 February 2018 March 2018 May Red - data 10 - 20 Nathalie Södra Härene (E20) standard- (E20) standard-improving measures million specific not Mjörnestål improving measures confirmed Investment Pedestrian and cycle route Morup- Pedestrian and cycle route Morup-Ås, Contract < SEK 15 Object- No Road Contracts-Ground West Region 2018 March 2018 April 2018 June Red - data 10 - 20 Lisa Crona Ås Completion million specific not confirmed Investment E6.20 Hisingsleden, southern E6.20 Hisingsleden, southern section Contract > SEK 15 Object- No Road Contracts-Ground West Region 2018 March 2018 September 2018 October Green - 500 - 700 Patrik section incl. Halvors Link. incl. Halvors Link. million specific reliable Bjerninge (within 3 months) Investment Gothenburg Harbour Line, double- Gothenburg Harbour line double Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-Construction West Region 2018 March 2018 October 2018 December Red - data > 1000 Jonas Melén track upgrade, stage Eriksberg - track expansion, section Eriksberg - leverantor/ million specific work-Tunnels not Pölsebo Pölsebo. The classification system trafikverke confirmed TransQ is being used for the ts- procurement. Only companies that kvalificerin are prequalified in TransQ and which gssystem--- the Transport Administration invites transq to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment E6.21 Port of Services Object- No Road Contracts-Ground West Region 2018 April 2018 May 2018 September Red - data 1 - 5 Elin Skarin Gothenburg/Lundbyleden, specific not Inlandsgatan confirmed Investment Performance of remote blocking Performance of remote blocking Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Signal West Region 2018 August 2018 October 2018 November Red - data 50 - 100 Claes Fagersta - Ludvika Fagersta - Ludvika Turnkey contract leverantor/ million specific not Andersson The classification system TransQ is trafikverke confirmed being used for the procurement. ts- Only companies that are prequalified kvalificerin in TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Construction of E20 Vårgårda-Vara Construction of E20 Vårgårda-Vara. Contract > SEK 15 Object- No Road Contracts-Ground West Region 2018 August 2018 October 2018 October Red - data 700 - 1000 Tommy The Ribbingsberg-Eling and Eling- million specific not Ghose Vara stages confirmed Can be procured together or separately. Investment Performance of remote blocking Performance of remote blocking Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Signal West Region 2018 November 2019 January 2019 February Red - data 100 - 300 Claes Borås - Herrljunga Borås - Herrljunga performance leverantor/ million specific not Andersson contract. The classification system trafikverke confirmed TransQ is being used for the ts- procurement. Only companies that kvalificerin are prequalified in TransQ and which gssystem--- the Transport Administration invites transq to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment Road 587 Gunnesby, bridge over The road that today crosses the Contract > SEK 15 Object- No Both road Contracts-Construction West Region 2018 December 2019 February 2019 March Red - data 10 - 20 Bo Tjörnbäck railway Bohus Line for Road 587 has become million specific and rail work-Bridges not too old. There is extensive concrete confirmed damage and it needs to be replaced. We will therefore build a new bridge with full carrying capacity. The new bridge will also be safer for traffic for those crossing the bridge. There will, for example, be a pedestrian and cycle route for unprotected road users.

The intersection of Road 570/Road 587 is of insufficient standard and there are inadequate pedestrian and cycle routes. In the road plan we will investigate how we can best improve traffic safety in the intersection.

The project also includes around 600 metres of new pedestrian and cycle route and two new bus stops.

Road 570 and Road 587 are connected to E6 and the nationwide road network in Göteborg. The county roads therefore primarily have a local function as catchment Investment Construction of the E20 bypassing E20roads. bypassing Road 570 Skara also has traffic from Contract > SEK 15 Object- No Road Contracts-Ground West Region 2018 December 2019 January 2019 February Red - data 100 - 300 Tommy Skara million specific not Ghose confirmed Major projects FA06 converter station Olskroken FA06 Converter station Signal box Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Electrical West Region 2017 January 2017 March 2017 April Green - 20 - 50 Maj-Britt signal box contract. Installation of inkrom in new leverantor/ million specific reliable Andtbacka Converter station. The classification trafikverke (within 3 system TransQ is being used for the ts- months) procurement. Only companies that kvalificerin are prequalified in TransQ and which gssystem--- the Transport Administration invites transq to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Major projects Assignment manager Inspection of Assignment manager Inspection of Services Object- No Rail Technical consultants- West Region 2017 January 2017 February 2017 June Yellow (not 1 - 5 Glenn buildings West Link and Olskroken buildings West Link and Olskroken specific Specific technical areas of used) Svensén Grade-Separated Junction Grade-Separated Junction expertise Major projects Coordinator Surplus aggregates Organisationally positioned under Services Object- No Rail Technical consultants- West Region 2017 January 2017 January Information Information Green - 1 - 5 Poneh the subproject manager within the specific Project support missing missing reliable Elfström West Link Project, it relates to a (within 3 coordinator for surplus aggregates months) for the Transport Administration Investments and Major Projects within the West Region, and in consultation with the West Swedish Agreement. To conduct planning and inventory between projects to create conditions regarding the management of surplus aggregates with reference to deposits, storage, intermediate storage, procurement and impact on the surrounding environment. Major projects E05 Contract Korsvägen West Link, E05 Contract Korsvägen Contract > SEK 15 Object- No Rail Contracts-Structures- West Region 2017 February 2017 November 2017 December Green - > 1000 Lillian million specific Properties reliable Brunbäck (within 3 months) Major projects West Link MH04.3 Reception of Several modes of transportation for Contract > SEK 15 Object- No Rail Contracts-BEST-Track West Region 2017 February 2017 April 2017 May Green - 50 - 100 Maj-Britt uncontaminated masses, lorries mass management uncontaminated million specific reliable Andtbacka (conditional permit) masses (within 3 months) Major projects West Link, MH04.2 Reception mass Contract > SEK 15 Object- No Rail Contracts-Construction West Region 2017 February 2017 April 2017 May Green - 50 - 100 Maj-Britt trains million specific work-Tunnels reliable Andtbacka (within 3 months) Major projects West Link MH04.2 Reception of Contract > SEK 15 Object- No Rail Contracts-Construction West Region 2017 February 2017 April 2017 May Green - 50 - 100 Maj-Britt uncontaminated masses by sea million specific work-Tunnels reliable Andtbacka (within 3 months) Major projects West Link PF01 Client-controlled Must cover the upper part of the Services Object- No Not Technical consultants- West Region 2017 March 2017 September 2017 November Green - 10 - 20 Maj-Britt Project insurance Excess liability insurance. specific constructio Specific technical areas of reliable Andtbacka n, general expertise (within 3 months) Major projects FA 26.2 Re-laying track Östra FA 26.2 Re-laying track Östra Contract < SEK 15 Object- No Rail Contracts-BEST-Track West Region 2017 March 2017 April 2017 September Green - 5 - 10 Glenn Hamngatan Hamngatan million specific reliable Svensén (within 3 months) Major projects Project West Link: GK3 reviewer The assignment involves a GK3 Services Object- No Rail Technical consultants- West Region 2017 March 2017 April 2017 June Green - 1 - 5 Lillian engineering area Geotechnics review of the engineering area specific Specific technical areas of reliable Brunbäck Geotechnics. The GK3 review shall be expertise (within 3 an independent review. The GK3 months) reviewer's task is primarily to review the implementation of the project and project results as well as work preparation so as to ensure that the risk of damage to the surrounding environment and third parties is kept at an acceptable level. Independent means a person who has not previously actively participated in the project planning. However, the person may have been involved in the work with a Railway plan and System document or earlier stages. Furthermore, the person cannot be involved in a planning assignment for future contractors within the West Link Project. Major projects FA13 Relocation of Installations in Contract works include construction Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-Structures- West Region 2017 April 2017 June 2017 September Green - 20 - 50 Lillian operational area, West Link of new outer road and relocation of leverantor/ million specific Properties reliable Brunbäck spiral staircase. Canalisation in trafikverke (within 3 maintenance room to be re-routed ts- months) and existing HVAC, electricity, kvalificerin telecommunications and running gssystem--- equipment relocated. The transq classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Major projects Project West Link: FA28 BEST work The contract covers construction of a Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track West Region 2017 April 2017 June 2017 September Green - 50 - 100 Lillian Göteborg C new track, demolition of a track and leverantor/ million specific reliable Brunbäck relocation of a signal kiosk incl. trafikverke (within 3 fence. The classification system ts- months) TransQ is being used for the kvalificerin procurement. Only companies that gssystem--- are prequalified in TransQ and which transq the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Major projects Project West Link: E07 Facilities Facility monitoring encompasses the Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-Infrasystems- West Region 2017 November 2018 April 2018 June Green - 100 - 300 Lillian monitoring tunnel's overall control and leverantor/ million specific Control & regulation reliable Brunbäck monitoring system for controlling trafikverke (within 3 and monitoring the facility's ts- months) technical installations in such a way kvalificerin that a safe and stable facility is gssystem--- achieved. The facility's technical transq installations are the systems used to make the tunnel facility accessible for railway traffic and passengers. It encompasses monitoring and control on both a general facility and operation level and local system level. The system for facility monitoring interacts with the Transport Agency's superordinate systems, such as GELD, a system the agency uses for the electronic operative control and monitoring of tunnels and other facilities. The classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... " Major projects Consultancy assignment regarding Tender documents and construction Så-blir-du- Services Object- Yes Rail Technical consultants- West Region 2017 November 2018 January 2018 June Red - data 500 - 700 Roland production of tender documents documents for 5 major contracts on leverantor/ specific Planning & design not Mårtensson and construction documents for the sub-section Mölnlycke – trafikverke confirmed project Gothenburg - Borås Bollebygd. The classification system ts- TransQ is being used for the kvalificerin procurement. Only companies that gssystem--- are prequalified in TransQ and which transq the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Major projects Project West Link: E06 BEST The BEST contract consists of work Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track West Region 2019 February 2019 October 2019 December Green - > 1000 Lillian with tracks ("bana"), electricity, leverantor/ million specific reliable Brunbäck signals and telecommunications trafikverke (within 3 across the board (Swedish abbrev. ts- months) BEST). kvalificerin The contract encompasses work gssystem--- across the entire span of the project; transq approx. 8 km. This contract will be executed as the final part of the project. In order to reduce excavation depths and maintenance costs, the tracks will likely be constructed as ballastless track. The tunnel is being prepared for the signal system ERTMS (European Rail Traffic Management System). The classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Major projects Deputy Subproject Manager The classification system TransQ is Så-blir-du- Services Object- Yes Rail Technical consultants- West Region Informatio Information 2017 January Information Information Green - < 1 Poneh Planning - BEST and installation being used for the procurement. leverantor/ specific Project support n missing missing missing missing reliable Elfström Central Station, VL Only companies that are prequalified trafikverke (within 3 in TransQ and which the Transport ts- months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... " Major projects Project coordinator for Haga and Coordinate the two projects Så-blir-du- Services Object- Yes Rail Technical consultants- West Region Informatio Information 2017 January Information Information Green - 1 - 5 Poneh Korsvägen, West Link regarding production issues, etc., leverantor/ specific Project support n missing missing missing missing reliable Elfström take into account agreements that trafikverke (within 3 the Transport Administration has ts- months) signed with the City of Gothenburg kvalificerin and property owners regarding the gssystem--- implementation of the project. transq Participate in production meetings and meetings with authorities, transport operators, property owners, etc. Provide support to project management/production management with responsibility for technical scheduling issues relating to production, and be responsible for the development of the inspection plan and production schedule jointly with the contractor for the contracts Haga E04, Korsvägen E05. Ensure and compile documentation and procedures for contracts and agreements that have been signed and which concern the subprojects. The area of responsibility Properties and Agreements is responsible for the agreements relating to the project. The classification system Maintenance For operation and maintenance as TheTransQ object is being relates used to operationfor the and Contract < SEK 15 Object- No Road Contracts-Infrasystems- West Region 2017 January 2017 February 2017 June Green - < 1 Patrik well as possible reinvestments of maintenance as well as million specific Lighting road reliable Bjerninge road lighting in Västra Götaland reinvestments of road lighting in (within 3 County Sub-area East Västra Götaland County Sub-area months) East. The assignment primarily includes preventive and corrective maintenance. The assignment may also involve new construction and conversion, the addition of devices and other operation and maintenance-related services within the operational area in question.

Maintenance Maintenance of bridge 16-670-1 Replacement of edge girder, railing, Maintenance Object- No Road Contracts-Construction West Region 2017 January 2017 February 2017 April Green - 1 - 5 Marlene Gullspång and bridge 16-544-1 waterproofing etc. measures < SEK 5 specific work-UH Bridges & reliable Hansson Ransberg million tunnels (within 3 months) Maintenance Maintenance of bridge 13-14-1 and Replacement plaster, edge lining, Maintenance Object- No Road Contracts-Construction West Region 2017 January 2017 February 2017 April Green - 5 - 10 Marlene 13-410-1 Fyllebro in etc. measures > SEK 5 specific work-UH Bridges & reliable Hansson million tunnels (within 3 months) Maintenance Maintenance of bridge 15-702-1 Replacement of edge girder on the Contract > SEK 15 Object- No Road Contracts-Construction West Region 2017 January 2017 February 2017 March Green - 10 - 20 Marlene over Nordre River (Jordfallsbron) south-east side of the bridge etc. million specific work-UH Bridges & reliable Hansson incl. necessary traffic control devices tunnels (within 3 months) Maintenance Replacement 2 x tubular bridges fd Replacement tubular bridges Maintenance Object- No Road Contracts-Construction West Region 2017 February 2017 March 2017 May Green - 1 - 5 Marlene Skaraborg 2017 measures < SEK 5 specific work-UH Bridges & reliable Hansson million tunnels (within 3 months) Maintenance Maintenance of bridges 15-796, 15- Maintenance of bridges 15-796, 15- Contract < SEK 15 Object- No Road Contracts-Construction West Region 2017 February 2017 March 2017 April Green - 5 - 10 Marlene 797, 15-802 and bridge 15-803 over 797, 15-802 and bridge 15-803 over million specific work-UH Bridges & reliable Hansson road 40 in Borås, Västra Götaland road 40 in Borås, Västra Götaland tunnels (within 3 County, Replacement of bearings County months) Note: new information due to complexity, inter alia, regarding traffic. The procurement will be divided into three contracts and include a time extension. Maintenance Operation and maintenance on Maintenance Object- No Road Contracts-Construction West Region 2017 February 2017 March 2017 May Green - 5 - 10 Marlene moveable bridge across measures > SEK 5 specific work-UH Bridges & reliable Hansson Sötenkanalen, Västra Götaland million tunnels (within 3 County months) Maintenance Maintenance of the new Svinesund Maintenance of new bridge Contract < SEK 15 Object- No Road Contracts-Construction West Region 2017 February 2017 March 2017 May Green - 5 - 10 Marlene bridge Svinesund million specific work-UH Bridges & reliable Hansson tunnels (within 3 months) Maintenance Replacement of counterweight on Replacement of counterweight and Contract < SEK 15 Object- No Road Contracts-Construction West Region 2017 March 2017 April 2017 October Green - 1 - 5 Tommy bridge 15-1-1 over Dalsland canal at repainting of Bridge 15-1-1 over million specific work-UH Bridges & reliable Ghose Längbron in Dalsland Dalsland canal at Längbron in tunnels (within 3 Dalsland months)

Maintenance Installation of inspection and Supplementing of inspection and Contract < SEK 15 Object- No Road Contracts-Construction West Region 2017 March 2017 April 2017 October Green - 1 - 5 Tommy service devices on bridge 15-741-1 service devices on bridge 15-741-1 million specific work-UH Bridges & reliable Ghose over Dalsland canal, Stora tunnels (within 3 Köpmannebro months) Maintenance New escalators at Hässleholm Contract < SEK 15 Object- No Not Contracts-Structures- West Region 2017 March 2017 April 2017 October Green - 5 - 10 Bo Ekdahl Station million specific constructio Properties reliable n, general (within 3 months) Maintenance Delivery tracking basic rail Services Suborder No Rail Technical consultants- West Region 2017 April 2017 May 2017 September Green - 1 - 5 Carl-Henric maintenance VGV, VGÖ, VGG Project support reliable Löfkvist (within 3 months) Maintenance Basic maintenance of railway Maintenance of railway Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-Basic contract West Region 2017 May 2017 September 2019 April Green - 100 - 300 Lisa Crona infrastructure Coast to Coast Line infrastructure on the sections of leverantor/ million specific rail reliable West railway line 641, 654. 655 and 721. trafikverke (within 3 The classification system TransQ is ts- months) being used for the procurement. kvalificerin Only companies that are prequalified gssystem--- in TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Operation and maintenance of Operation and maintenance of Contract > SEK 15 Object- No Road Contracts-Infrasystems- West Region 2017 May 2017 June 2018 May Red - data < 1 Patrik moveable bridges Västra Götaland moveable bridges Västra Götaland million specific Control & regulation not Bjerninge and Värmland and Värmland confirmed Maintenance For operation and maintenance as Contract > SEK 15 Object- No Road Contracts-Infrasystem- West Region 2017 September 2017 October 2018 September Red - data < 1 Patrik well as possible reinvestments of million specific Manage traffic road not Bjerninge Bridges in the counties of Värmland confirmed and Västra Götaland. Maintenance Reinvestment traffic equipment Reinvestment traffic equipment Göta Contract < SEK 15 Object- No Road Contracts-Infrasystem- West Region 2017 September 2017 October 2018 March Red - data < 1 Patrik Göta Tunnel, project planning Tunnel, project planning million specific Manage traffic road not Bjerninge confirmed Maintenance Reinvestment Lundby Tunnel Reinvestment Lundby Tunnel Contract < SEK 15 Object- No Road Contracts-Infrasystem- West Region 2017 September 2017 October 2018 March Red - data < 1 Patrik detection system project planning detection system project planning million specific Manage traffic road not Bjerninge confirmed Maintenance Road markings District Halmstad Turnkey contract for road markings Contract > SEK 15 Object- No Road Contracts-Road marking West Region 2017 October 2017 November 2018 January Green - 20 - 50 Carl-Henric within District Halmstad million specific reliable Löfkvist (within 3 months) Maintenance Operation and maintenance, and Operation and maintenance, and Contract > SEK 15 Object- No Road Contracts-Infrasystems- West Region 2017 November 2017 December 2018 November Red - data < 1 Patrik reinvestment in tunnels Control and reinvestment in tunnels Control and million specific Control & regulation not Bjerninge Regulation Västra Götaland county Regulation confirmed

Maintenance Operation and maintenance and Operation and maintenance and Contract > SEK 15 Object- No Road Contracts - Infrasystem- West Region 2017 November 2017 December 2018 November Red - data < 1 Patrik potential reinvestments potential reinvestments million specific Tele/Data not Bjerninge Telecommunications Västra Telecommunications Västra Götaland confirmed Götaland county county Maintenance Operation and maintenance, and Operation and maintenance, and Contract > SEK 15 Object- No Road Contracts-Infrasystems- West Region 2017 November 2017 December 2018 November Red - data < 1 Patrik potential reinvestments Power potential reinvestments Power million specific Control & regulation not Bjerninge complex facilities complex facilities confirmed Maintenance Operation and maintenance, and Operation and maintenance, and Contract > SEK 15 Object- No Road Contracts-Infrasystems- West Region 2017 November 2017 December 2018 November Red - data < 1 Patrik potential reinvestments Ventilation potential reinvestments Ventilation million specific Water and not Bjerninge complex facilities complex facilities Sewage/Ventilation confirmed Maintenance Maintenance of bridge 14-106-1, Maintenance Object- No Road Contracts-Construction West Region 2018 October 2018 November 2019 January Green - 1 - 5 Marlene Stenung Bridge, County of Västra measures < SEK 5 specific work-UH Bridges & reliable Hansson Götaland million tunnels (within 3 months) Maintenance Framework agreement Data The task involves the measurement Services Framework No Road Technical consultants- West Region 2019 March 2019 April 2019 September Green - 50 - 100 Erik capture and updating for ADT of vehicle flows in order to calculate agreement Specific technical areas of reliable Oskarsson measurement in the South, West, the average annual daily traffic expertise (within 3 Stockholm and North geographical (ADT). The assignment involves months) areas implementing the following work phases; planning of traffic measurement, traffic measurement, input data management for collected road traffic data, final inspection of collected road traffic data and updating of the Transport Administration’s register for road traffic data.

Information Coordinator screens, West Link Services Object- Informati Information Information missing West Region 2017 February 2017 March 2017 March Green - < 1 Poneh missing specific on missing reliable Elfström missing (within 3 months) Central Service agreement for escalators Service agreement for escalators and Contract > SEK 15 Object- No Both road Contracts-Structures- East 2017 June 2017 August 2017 November Green - 50 - 100 Bo Ekdahl functions and lifts, national lifts, national million specific and rail Properties Region/Stockhol reliable m (within 3 months) STA Road Ferry berths Oxdjupet road bridge Oxdjupet road bridge Contract < SEK 15 Object- No Road Contracts-Marine goods East 2017 November 2018 January 2018 March Red - data 1 - 5 Carina Ferries million specific and services Region/Stockhol not Bergamoni m confirmed Investment Preparation of a Road plan traffic Preparation of a Road plan traffic Services Object- No Road Technical consultants- East 2017 January 2017 March 2017 March Green - 1 - 5 Ove safety measures Road 899 safety measures Road 899 specific Planning & design Region/Stockhol reliable Strömberg m (within 3 months) Investment Double track expansion Hallsberg, Double track expansion Hallsberg, Contract > SEK 15 Object- No Rail Contracts-Construction East 2017 February 2017 March Information March Green - 20 - 50 Lena Performance contract Railway Performance contract Railway bridge million specific work-Bridges Region/Stockhol missing reliable Scherman bridge and road relocation and road relocation m (within 3 months) Investment Turnkey contract Fencing measures Contract > SEK 15 Object- No Rail Contracts-Ground East 2017 February 2017 March 2017 March Green - 20 - 50 Lena East District million specific Region/Stockhol reliable Scherman m (within 3 months) Investment Tender documents Performance Services Object- No Rail Technical consultants- East 2017 February 2017 March Information Information Green - 1 - 5 Ove contract Loading area in Enköping specific Planning & design Region/Stockhol missing missing reliable Strömberg m (within 3 months) Investment Contract inspection body for Project The classification system TransQ is Så-blir-du- Services Object- Yes Rail Technical consultants- East 2017 February 2017 March Information Information Green - 1 - 5 Lena Getingmidjan being used for the procurement. leverantor/ specific Project support Region/Stockhol missing missing reliable Scherman Only companies that are prequalified trafikverke m (within 3 in TransQ and which the Transport ts- months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... "

Investment Turnkey contract fence patrol – Implementation of contract fence Contract < SEK 15 Object- Informati Information Information missing East 2017 February 2017 March 2017 July Green - 10 - 20 Lena patrols within the Greater patrol – patrols within the Greater million specific on missing Region/Stockhol reliable Scherman Stockholm areas Stockholm areas missing m (within 3 months) Investment Production of tender documents for Services Object- No Rail Technical consultants- East 2017 February 2017 March Information Information Green - 10 - 20 Lena performance contract for new specific Planning & design Region/Stockhol missing missing reliable Scherman control system Solna m (within 3 months) Investment Road 77 County border - Rösa Road Road plan, tender documents, Services Object- No Road Technical consultants- East 2017 March 2017 December 2017 August Green - 5 - 10 Roberto plan Stage 3 - Section 1-3 construction site follow-up specific Planning & design Region/Stockhol reliable Vespo m (within 3 months) Investment Road 77 County border - Rösa Road Road 77 County border - Rösa Road Services Object- No Road Technical consultants- East 2017 March 2017 May 2017 August Green - 10 - 20 Roberto plan Stage 2-3 Section 4, 5-7 plan Stage 2-3 Section 4, 5-7 specific Planning & design Region/Stockhol reliable Vespo m (within 3 months) Investment Production of railway plan, system Production of railway plan, system Så-blir-du- Services Object- Yes Rail Technical consultants- East 2017 March 2017 May 2017 May Green - 100 - 300 Mikael Lasota document and tender documents document and tender documents leverantor/ specific Planning & design Region/Stockhol reliable including construction site follow- including construction site follow-up trafikverke m (within 3 up for Freight corridor through for Freight corridor through ts- months) Bergslagen, Hallsberg-Degerön, Bergslagen, Hallsberg-Degerön, kvalificerin Hallsberg-Stenkumla section Hallsberg-Stenkumla section. The gssystem--- classification system TransQ is being transq used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Ösmo converter stations Ösmo converter stations Contract > SEK 15 Object- No Rail Contracts-BEST-Electrical East 2017 March 2017 May 2017 May Green - 20 - 50 Lillemor Bruce million specific Region/Stockhol reliable m (within 3 months) Investment Subproject manager for Project Subproject manager for Project Så-blir-du- Services Object- Yes Rail Technical consultants- East 2017 March 2017 April Information Information Green - 5 - 10 Lena Hallsberg - Degerön Hallsberg - Degerön. The leverantor/ specific Project support Region/Stockhol missing missing reliable Scherman classification system TransQ is being trafikverke m (within 3 used for the procurement. Only ts- months) companies that are prequalified in kvalificerin TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment E4/E20 Essingeleden - Södra Länken New ramps between Åby Contract > SEK 15 Object- No Road Contracts-Ground East 2017 March 2017 October 2018 January Green - > 1000 Ove Interchange and Årstalänken. million specific Region/Stockhol reliable Strömberg Possible design unclear at m (within 3 present.Turnkey contract months) Investment Pedestrian and cycle rout 1046 Pedestrian and cycle rout 1046 Contract > SEK 15 Object- No Road Contracts-Ground East 2017 April 2017 June 2017 August Green - 10 - 20 Liselotte Vassunda - Knivsta Vassunda - Knivsta million specific Region/Stockhol reliable Eriksson m (within 3 months) Investment Hagalund-Catenary replacement Contract > SEK 15 Object- No Rail Contracts-BEST-Electrical East 2017 April 2017 May 2017 June Red - data 20 - 50 Jan Snäll Production million specific Region/Stockhol not m confirmed Investment Project planning station measures The classification system TransQ is Så-blir-du- Services Object- Yes Rail Technical consultants- East 2017 April 2017 July Information Information Green - 50 - 100 Kjell Stockholm Central Station being used for the procurement. leverantor/ specific Planning & design Region/Stockhol missing missing reliable Fredriksson Only companies that are prequalified trafikverke m (within 3 in TransQ and which the Transport ts- months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... " Investment Södertälje C rail yard conversion Södertälje C rail yard conversion, Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track East 2017 April 2017 April Information Information Green - 100 - 300 Lena performance contract. The leverantor/ million specific Region/Stockhol missing missing reliable Scherman classification system TransQ is being trafikverke m (within 3 used for the procurement. Only ts- months) companies that are prequalified in kvalificerin TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Investment Performance contract MBEST Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track East 2017 May 2017 September 2017 March Green - 300 - 500 Mikael Lasota Double track function in the freight Performance contract MBEST Double leverantor/ million specific Region/Stockhol reliable corridor through Hallsberg track function in the freight corridor trafikverke m (within 3 through Hallsberg. The classification ts- months) system TransQ is being used for the kvalificerin procurement. Only companies that gssystem--- are prequalified in TransQ and which transq the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment For construction of new bridge over For the performance of a new bridge Contract > SEK 15 Object- No Road Contracts-Construction East 2017 May 2017 December 2018 January Green - > 1000 Roberto Skurusundet and coversion of over Skurusundet, project road 222 million specific work-Bridges Region/Stockhol reliable Vespo interchanges Skuru and Björknäs, New Skuru bridge m (within 3 project road 222 New Skuru Bridge months)

Investment Road 76, road 282, bus stops and Road 76, road 282, bus stops and Contract > SEK 15 Object- No Road Contracts-Ground East 2017 June 2017 July 2017 August Green - 20 - 50 Mattias Kjell roadside area measures (Package 1) roadside area measures (Package 1) million specific Region/Stockhol reliable m (within 3 months) Investment Turnkey contract for expansion of The section of road between Contract > SEK 15 Object- No Road Contracts-Ground East 2017 June 2017 September Information Information Green - 100 - 300 Basu Alam Road 34, Ervasteby - Borensberg in Ervasteby and Borensberg is approx. million specific Region/Stockhol missing missing reliable the County of Östergötland 10 km long. It is to be converted into m (within 3 a new section in which the traffic is months) separated by a central crash barrier; a 2+1 road with a 100 km/h speed limit. Most of the section is part of a new section. Turnkey contract

Investment Road 229 Interchange point Norra Road 229 Interchange point Norra Contract > SEK 15 Object- No Road Contracts-Ground East 2017 June 2017 September 2017 October Green - 20 - 50 Mattias Kjell Sköndal Sköndal million specific Region/Stockhol reliable m (within 3 months) Investment Performance contract, Flen, point Flen, point switches platform and Contract > SEK 15 Object- No Rail Contracts-BEST-Track East 2017 July 2017 August 2017 October Green - 20 - 50 Lena switches platform and cable cable separation power cables - million specific Region/Stockhol reliable Scherman separation power cables execution of ground, catenary line m (within 3 works, four point switches months) platform works and cable separation power cable

Investment Pedestrian and cycle route Frescati - Pedestrian and cycle route Contract > SEK 15 Object- No Road Contracts-Ground East 2017 August 2017 October 2018 January Green - 50 - 100 Basu Alam Mörby million specific Region/Stockhol reliable m (within 3 months) Investment Road 823 Pedestrian and cycle path Road 823 Pedestrian and cycle path Contract > SEK 15 Object- No Road Contracts-Ground East 2017 August 2017 September 2017 March Green - 20 - 50 Mattias Kjell Örebro - Glanshammar Örebro - Glanshammar million specific Region/Stockhol reliable m (within 3 months) Investment Performance contract Western Western Main Line trimming Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Signal East 2017 August 2017 September 2017 October Green - 50 - 100 Lena Main Line trimming measures, measures, Älvsjö-Laxå, replacement leverantor/ million specific Region/Stockhol reliable Scherman Älvsjö-Laxå of repeater balises and new block trafikverke m (within 3 posts. The classification system ts- months) TransQ is being used for the kvalificerin procurement. Only companies that gssystem--- are prequalified in TransQ and which transq the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment Pedestrian and cycle route, Pedestrian and cycle route Contract < SEK 15 Object- No Road Contracts-Ground East 2017 September 2018 January 2018 March Green - < 1 Basu Alam Skyttebrink million specific Region/Stockhol reliable m (within 3 months) Investment Road 276 Rosenkälla and Contract Contract > SEK 15 Object- No Road Contracts-Ground East 2017 September 2017 November 2018 January Green - 50 - 100 Basu Alam Åkersberga_ Stage million specific Region/Stockhol reliable m (within 3 months) Investment Road 261 Ekerövägen E3: Edeby - Expansion public transport lane Contract > SEK 15 Object- No Road Contracts-Ground East 2017 September 2017 December 2018 January Green - 300 - 500 Thomas Nockeby north side, bridge measures, etc. million specific Region/Stockhol reliable Stubbfält Performance contract m (within 3 months) Investment Road 261 Ekerövägen E1:Tappström Expansion public transport lane Contract > SEK 15 Object- No Road Contracts-Ground East 2017 September 2018 February Information Information Green - 300 - 500 Thomas - Lindö tunnel north side, new bridge etc. Turnkey million specific Region/Stockhol missing missing reliable Stubbfält contract m (within 3 months)

Investment 4 x pedestrian and cycle routes 4 x pedestrian and cycle routes, Contract > SEK 15 Object- No Road Contracts-Ground East 2017 November 2018 February 2018 April Green - 100 - 300 Basu Alam Turnkey contract million specific Region/Stockhol reliable m (within 3 months) Investment Road 140 Klintehamn Road Contract > SEK 15 Object- No Road Contracts-Ground East 2017 November 2018 February 2018 April Green - 50 - 100 Basu Alam million specific Region/Stockhol reliable m (within 3 months) Investment Performance contract new control Contract > SEK 15 Framework No Rail Contracts-BEST-Signal East 2017 November 2018 January Information Information Green - 10 - 20 Lena system Solna million agreement Region/Stockhol missing missing reliable Scherman m (within 3 months) Investment Construction of E 18 temporary Contract > SEK 15 Object- No Road Contracts-Ground East 2017 December 2018 March 2018 May Red - data 100 - 300 Basu Alam connection Gillinge and E 18 million specific Region/Stockhol not Interchange Rosenkälla m confirmed Investment Pedestrian and cycle route 584 Pedestrian and cycle route 584 Services Object- No Road Contracts-Ground East 2017 December 2018 April 2018 June Red - data < 1 Basu Alam Fiskarhagen, production Fiskarhagen, Service specific Region/Stockhol not m confirmed Investment Track replacement Flens upper - The classification system TransQ is Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track East 2018 January 2018 March 2018 April Green - 100 - 300 Lena Eskilstuna being used for the procurement. leverantor/ million specific Region/Stockhol reliable Scherman Only companies that are prequalified trafikverke m (within 3 in TransQ and which the Transport ts- months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... " Investment Preparatory contract Grade-Preparatory contract Uppsala Grade- Så-blir-du- Contract > SEK 15 Object- Yes Both road Contracts-Ground East 2018 January 2018 May 2018 August Red - data 20 - 50 Ove separated intersections separated intersections Performance leverantor/ million specific and rail Region/Stockhol not Strömberg contract. The classification system trafikverke m confirmed TransQ is being used for the ts- procurement. Only companies that kvalificerin are prequalified in TransQ and which gssystem--- the Transport Administration invites transq to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment Prime contract Uppsala Grade- Prime contract Uppsala Grade- Så-blir-du- Contract > SEK 15 Object- Yes Both road Contracts-BEST-Track East 2018 March 2018 June 2018 August Red - data 100 - 300 Ove separated intersections separated intersections Performance leverantor/ million specific and rail Region/Stockhol not Strömberg contract. The classification system trafikverke m confirmed TransQ is being used for the ts- procurement. Only companies that kvalificerin are prequalified in TransQ and which gssystem--- the Transport Administration invites transq to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Investment Road 76, road 282, bus stops Road 76, road 282, bus stops Contract > SEK 15 Object- No Road Contracts-Ground East 2018 April 2018 May 2018 June Red - data 20 - 50 Mattias Kjell (Package 2) (Package 2) million specific Region/Stockhol not m confirmed Investment E18 Arninge Travel Centre, E18 Arninge Travel Centre, Contract > SEK 15 Object- No Road Contracts-Ground East 2018 April 2018 August 2018 October Red - data 100 - 300 Basu Alam production production million specific Region/Stockhol not m confirmed Investment Performance contract regarding Performance contract regarding Contract > SEK 15 Object- No Rail Contracts-Ground East 2018 October 2018 December 2019 January Red - data 10 - 20 Lena noise protection at outdoor areas in noise protection for outdoor areas in million specific Region/Stockhol not Scherman Hallsberg Hallsberg m confirmed Performance contract Investment Road 584 Fiskarhagen, pedestrian Pedestrian and cycle route, Contract < SEK 15 Object- No Road Contracts-Ground East 2018 December 2018 April 2018 June Red - data 1 - 5 Basu Alam and cycle route Performance contract million specific Region/Stockhol not m confirmed Investment Renewed exposure to competition, The classification system TransQ is Så-blir-du- Contract < SEK 15 Suborder Yes Rail Information missing East 2017 December Informatio Information Information Information Red - data 5 - 10 Lena Performance contract - Mosås, new being used for the procurement. leverantor/ million Region/Stockhol n missing missing missing missing not Scherman switch for functioning connection Only companies that are prequalified trafikverke m confirmed to Törsjö terminal in TransQ and which the Transport ts- Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... "

Major projects Experienced resource consultant Experienced resource consultant Services Object- No Road Technical consultants- East 2017 January 2017 February 2017 March Green - 1 - 5 Ove Cross link Södertörn Cross link Södertörn specific Project support Region/Stockhol reliable Strömberg m (within 3 months) Major projects Project ERTMS, Installation Test line Project ERTMS, Installation Test line Contract > SEK 15 Object- No Rail Contracts-BEST-Track East 2017 January 2017 March 2017 April Green - 10 - 20 Mattias Kjell Katrineholm - Åby Katrineholm - Åby million specific Region/Stockhol reliable m (within 3 months) Major projects Project ERTMS, installation test line Performance contract to adapt the Contract < SEK 15 Object- No Rail Contracts-BEST-Signal East 2017 January 2017 February 2017 March Green - 10 - 20 Erika Ahlman Katrineholm - Åby facility to a test track. Relates to the million specific Region/Stockhol reliable section Katrineholm - Åby m (within 3 months) Major projects Project ERTMS - Turnkey contract Turnkey contract to construct an Contract < SEK 15 Information No Rail Contracts-Structures- East 2017 February 2017 March 2017 April Green - 1 - 5 Erika Ahlman Office building along the test line office building by the railway tracks million missing Properties Region/Stockhol reliable in Simonstorp. m (within 3 months) Major projects Ostlänken OL2400 Contract Kardon Kardon Line from Åby to and on Contract > SEK 15 Object- No Rail Contracts-Ground East 2017 February 2017 April 2017 July Green - 100 - 300 Johan Sundin Line from Åby to Händelö, Händelö, performance contract million specific Region/Stockhol reliable construction ground and engineering structures. m (within 3 months) Major projects Construction document planning + Coherent construction document Så-blir-du- Services Object- Yes Rail Technical consultants- East 2017 February 2017 April 2017 April Green - 100 - 300 Kjell tender documents for BEST, Project planning + tender documents for all leverantor/ specific Planning & design Region/Stockhol reliable Fredriksson Mälar Line BEST (temporary and permanent trafikverke m (within 3 facility for the entire route) (4+600 to ts- months) 11+000). kvalificerin This project planning is provided for gssystem--- a number of turnkey contracts. The transq classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Major projects Ostlänken, project unit Norrköping, The procurement relates to one (1) Services Object- No Rail Technical consultants- East 2017 February 2017 April 2017 July Green - 5 - 10 Johan Sundin Construction manager for catenary, position for Construction specific Project support Region/Stockhol reliable low-voltage, telecommunications management catenary line, low m (within 3 and remote control voltage, telecommunications and months) remote control. Major projects Ostlänken, project unit Norrköping, Services Object- No Rail Technical consultants- East 2017 February 2017 April 2017 July Green - 5 - 10 Johan Sundin Construction manager Track specific Project support Region/Stockhol reliable m (within 3 months) Major projects Ostlänken, project unit Norrköping, Services Object- No Rail Technical consultants- East 2017 February 2017 April 2017 July Red - data 5 - 10 Johan Sundin Construction manager Signal specific Project support Region/Stockhol not m confirmed Major projects E4 Stockholm Bypass - FSE309 Lovö Two roundabouts, connection to Contract > SEK 15 Object- No Road Contracts-Ground East 2017 March 2017 August 2017 October Green - 300 - 500 Anika Wifréus Interchange tunnel ramps, widening of million specific Region/Stockhol reliable Ekerövägen between the m (within 3 roundabouts. Pedestrian and cycle months) underpass under Ekerövägen.Turnkey contract Major projects E4 Stockholm Bypass - FSE101 Widening the road, demolition of Contract > SEK 15 Object- No Road Contracts-Ground East 2017 March 2017 November 2018 January Green - 300 - 500 Anika Wifréus Roads and bridges, Vårby backe existing pedestrian and cycle bridge, million specific Region/Stockhol reliable a new pedestrian and cycle bridge. m (within 3 The existing bridge across the E 4 at months) Lindvreten junction will be rebuilt as an overhead roundabout. This stretch of road is approx. 1.5 km long.Turnkey contract

Major projects Establishment of location Location investigation for Services Object- No Rail Technical consultants- East 2017 March 2017 May 2017 July Red - data 20 - 50 Johan Sundin investigation Ostlänken, Tallboda- Ostlänken's passage through specific Planning & design Region/Stockhol not Tift Linköping. m confirmed Major projects Project ERTMS - Project manager Project manager with the task of Services Object- No Rail Technical consultants- East 2017 March 2017 March 2017 April Red - data 1 - 5 Erika Ahlman data collection investigating needs and specific Specific technical areas of Region/Stockhol not requirements in terms of the expertise m confirmed creation and building up of databases (existing and possibly new) for the management of all data that generated within all roll-outs.

Major projects Project Ostlänken Kardon Line from Services Object- No Rail Technical consultants- East 2017 March 2017 May 2017 August Green - 1 - 5 Johan Sundin Åby to Händelö, commissioning specific Specific technical areas of Region/Stockhol reliable organisation expertise m (within 3 months) Major projects Pedestrian and cycle route, etc. Pedestrian and cycle route and Contract < SEK 15 Object- No Rail Contracts-Ground East 2017 March 2017 May 2017 October Green - 10 - 20 Kjell Kallhäll, Project Mälar Line various utility lines. million specific Region/Stockhol reliable Fredriksson m (within 3 months) Major projects E4 Stockholm Bypass - FSE814 Supply of prefabricated concrete Goods Object- No Road Contracts-Ground East 2017 April 2017 August 2018 August Green - 100 - 300 Anika Wifréus Prefabricated portal elements portal elements for evacuation roads specific Region/Stockhol reliable in rock tunnels. m (within 3 months) Major projects E9980. Preparatory work re-laying Re-laying of utility lines for Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-Ground East 2017 April 2017 June 2018 May Green - 500 - 700 Kjell of utility lines, Project Mälar Line temporary tracks and permanent leverantor/ million specific Region/Stockhol reliable Fredriksson facility. Duration of assignment > 5 trafikverke m (within 3 years. The classification system ts- months) TransQ is being used for the kvalificerin procurement. Only companies that gssystem--- are prequalified in TransQ and which transq the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Major projects Project Ostlänken Kardon Line from Services Object- No Rail Technical consultants- East 2017 June 2017 August 2017 October Green - 1 - 5 Johan Sundin Åby to Händelö, Inspection specific Specific technical areas of Region/Stockhol reliable organisation expertise m (within 3 months) Major projects Ostlänken OL2400 Contract Kardon Performance contract BEST, Kardon Contract > SEK 15 Object- No Rail Contracts-BEST-Track East 2017 August 2017 October 2018 January Red - data 100 - 300 Johan Sundin Line from Åby to Händelö, BEST Line from Åby to and on Händelö, million specific Region/Stockhol not m confirmed Major projects E4 Stockholm Bypass - FSE401 Two roundabouts with connections Contract > SEK 15 Object- No Road Contracts-Ground East 2017 September 2018 January 2018 February Green - 500 - 700 Anika Wifréus Vinsta Interchange for ramps, conversion of pedestrian million specific Region/Stockhol reliable and cycle route network and m (within 3 connection of local roads to months) Bergslagsvägen, re-laying of utility lines. Concrete tunnels that connect up with ramp tunnels at Skattegårdsvägen. Turnkey contract

Major projects E4 Stockholm Bypass - FSK08 Construction documents for Services Object- No Road Technical consultants- East 2017 September 2017 December 2018 February Green - 5 - 10 Amanda Construction documents for technical buildings specific Specific technical areas of Region/Stockhol reliable Sandin technical buildings expertise m (within 3 months) Major projects E4 Stockholm Bypass - FSE901 Telecom system, e.g. fire detection, Contract > SEK 15 Object- No Road Contracts-Infrasystem- East 2017 October 2018 July 2019 January Green - 700 - 1000 Gabriel Telecom, Control and Monitoring communications platform, cameras, million specific Manage traffic road Region/Stockhol reliable Toanca System message system, radio, telephony. m (within 3 Superordinated control and months) monitoring systems for all technical systems in the facility. Turnkey contract Major projects E4 Stockholm Bypass - FSE902 Electricity supply, receiving stations Contract > SEK 15 Object- No Road Contracts-Infrasystems- East 2017 October 2018 July 2019 January Green - > 1000 Gabriel Electricity supply, lighting, water and distribution systems million specific Lighting road Region/Stockhol reliable Toanca supply and waste water (intermediate andlow voltage) within m (within 3 the whole facility. Lighting in traffic months) areas and general electricity, lighting, ventilation and cooling in all areas.Turnkey contract Major projects E4 Stockholm Bypass - FSE903 Comprises the installation of fans in Contract > SEK 15 Object- No Road Contracts-Infrasystems- East 2017 October 2018 July 2019 January Green - 300 - 500 Gabriel Tunnel ventilation traffic areas, all fan plant rooms and million specific Water and Region/Stockhol reliable Toanca tunnel and fire ventilation control. Sewage/Ventilation m (within 3 Performance contract months) Major projects E4 Stockholm Bypass - FSE903 Comprises equipment and systems Contract > SEK 15 Object- No Road Contracts-Infrasystem- East 2017 October 2018 July 2019 January Green - 700 - 1000 Gabriel Traffic system for monitoring and traffic control, million specific Manage traffic road Region/Stockhol reliable Toanca including adaptation to the existing m (within 3 road network.Turnkey contract months) Major projects E4 Stockholm Bypass - FSE905 Comprises water supply and waste Contract > SEK 15 Object- No Road Contracts-Infrasystems- East 2017 October 2018 July 2019 January Green - 700 - 1000 Gabriel Water supply and waste water, and water systems including water million specific Water and Region/Stockhol reliable Toanca fixed fire extinguishing systems supply and waste water treatment Sewage/Ventilation m (within 3 plants, pumping and drainage months) stations, waste water and firefighting water for fire hydrants. A fixed extinguishing system for the traffic area throughout the entire route.Performance contract Major projects Ostlänken OL2410 Contract Åby, Performance contract for switch Contract > SEK 15 Object- No Rail Contracts-BEST-Track East 2017 October 2018 January 2018 March Green - 20 - 50 Johan Sundin switch work work at Åby, Norrköping. million specific Region/Stockhol reliable m (within 3 months) Major projects E9961, TUNNEL & CHANNEL Earthworks and BEST contract Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track East 2017 October 2017 December 2018 November Green - > 1000 Kjell Sundbyberg-Solna, Project Mälar approx. 1.7 km tunnel and channel leverantor/ million specific Region/Stockhol reliable Fredriksson Line central to Sundbyberg incl. new trafikverke m (within 3 station incl. sheet pile wall and ts- months) underground connection to subway kvalificerin station. ECI contract with high level gssystem--- collaboration with provided transq construction document planning BEST

Major projects E9950. Construction of temporary The classification system TransQ is Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track East 2018 April 2018 May 2019 May Green - 500 - 700 Kjell tracks, station and platforms. The being used for the procurement. leverantor/ million specific Region/Stockhol reliable Fredriksson Mälaren Line Project Only companies that are prequalified trafikverke m (within 3 in TransQ and which the Transport ts- months) Administration invites to participate kvalificerin in the procurement may submit gssystem--- tenders. For more information see transq the link to the right (in Swedish) "Sa- blir-du...... "

Major projects Ostlänken OL2600 Contract Performance contract including Contract > SEK 15 Object- No Rail Contracts-Ground East 2018 August 2018 November 2019 January Red - data 300 - 500 Johan Sundin Norrköping’s new goods yard, ground, engineering structures and million specific Region/Stockhol not construction and BEST BEST. Previously the idea was for this m confirmed contract to be in the form of Early Contractor Involvement, but this has changed. Major projects E4 Stockholm Bypass - FSE816 Supply and erection of doors in traffic Contract > SEK 15 Object- No Road Contracts-Structures- East 2018 September 2019 June 2019 December Green - 20 - 50 Gabriel Doors to traffic areas facility Turnkey contract million specific Properties Region/Stockhol reliable Toanca m (within 3 months) Major projects E4 Bypass Stockholm - FSE705 Establishing tunnel space Contract > SEK 15 Object- No Road Contracts-Ground East 2019 March 2019 September 2021 February Green - 50 - 100 Gabriel Establishing tunnel space million specific Region/Stockhol reliable Toanca m (within 3 months) Major projects Ostlänken OL2300 Contract Performance contract, with Contract > SEK 15 Object- No Rail Contracts-Ground East 2019 June 2020 March 2020 May Red - data > 1000 Johan Sundin Kolmården, construction and track construction responsibility for million specific Region/Stockhol not bridges, between Stavsjö and m confirmed Loddby, 15 km, extensive ground work, bridges, tunnels and fixed track. There will be pre-qualification.

Major projects Ostlänken OL3100 Contract Skavsta, Turnkey contract between Contract > SEK 15 Object- No Rail Contracts-Ground East 2019 September 2020 May 2020 July Red - data > 1000 Johan Sundin construction and track Gerstaberg and Sillekrog, 35 km, million specific Region/Stockhol not extensive ground work, bridges, m confirmed tunnels and fixed track. Combination procurement with the possibility to also submit tenders in the Vagnhärad contract. There will be pre-qualification. Major projects Ostlänken OL3000 Contract Turnkey contract between Skavsta Contract > SEK 15 Object- No Rail Contracts-Ground East 2019 September 2020 May 2020 July Red - data > 1000 Johan Sundin Ålberga, construction and track airport and Stavsjö, 22 km, extensive million specific Region/Stockhol not ground work, bridges, tunnels and m confirmed fixed track. There will be pre- qualification. Major projects Ostlänken OL2100 Contract Performance contract for tunnel Contract > SEK 15 Object- No Rail Contracts-Construction East 2019 September 2020 May 2020 July Red - data > 1000 Johan Sundin Norrköping tunnel, construction between the station in Norrköping million specific work-Tunnels Region/Stockhol not and track and Klinga, 6 km. There will be pre- m confirmed qualification. Major projects Ostlänken OL4000 Contract Turnkey contract between Contract > SEK 15 Object- No Rail Contracts-Ground East 2019 November 2020 May 2020 July Red - data > 1000 Johan Sundin Vagnhärad, construction and track Gerstaberg and Sillekrog, 23 km, million specific Region/Stockhol not extensive ground work, bridges, m confirmed tunnels and fixed track. Combination procurement with the possibility to also submit tenders in the Skavsta contract. There will be pre- qualification. Major projects Ostlänken OL1000 Contract Turnkey contract through central Contract > SEK 15 Object- No Rail Contracts-Ground East 2020 August 2021 February 2021 July Red - data > 1000 Johan Sundin Linköping, construction and track Linköping, 5 km, comprising ground million specific Region/Stockhol not and track. There will be pre- m confirmed qualification. Major projects Ostlänken OL2200 Contract Performance contract between Contract > SEK 15 Object- No Rail Contracts-Ground East 2020 September 2021 May 2021 July Red - data > 1000 Johan Sundin Norrköping central, construction Loddby and central Norrköping, 6 million specific Region/Stockhol not and BEST km, extensive ground work, bridges m confirmed and BEST work. There will be pre- qualification. Major projects E9970, LAND & CONSTRUCTION, Km Land and construction contract from Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track East 2020 September 2020 November 2021 October Green - 500 - 700 Kjell 4+400-5+300 INCL PEDESTRIAN connection Huvudsta to the start of leverantor/ million specific Region/Stockhol reliable Fredriksson AND CYCLE TUNNEL, Project Mälar the channel in the direction of trafikverke m (within 3 Line Sundbyberg (from 4+400 to 5+300) ts- months) incl. demolition and construction of kvalificerin new bridge for Huvudstagatan and gssystem--- construction of new thoroughfare transq Bangatan. Turnkey contract. The classification system TransQ is being used for the procurement. Only companies that are prequalified in TransQ and which the Transport Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Major projects Ostlänken OL4100 Contract Performance contract for Ostlänken's Contract > SEK 15 Object- No Rail Contracts-Ground East 2020 November 2021 May 2021 July Red - data 700 - 1000 Johan Sundin Gerstaberg, construction and BEST coupling point with the Western million specific Region/Stockhol not Main Line, including fly-over. Total m confirmed length 2 km. There will be pre- qualification. Major projects Ostlänken OL1100 Contract Turnkey contract between Klinga in Contract > SEK 15 Object- No Rail Contracts-Ground East 2020 November 2021 May 2021 July Red - data > 1000 Johan Sundin Norsholm, construction and track Norrköping and Linköping, 32 km, million specific Region/Stockhol not comprising ground and bridges. m confirmed There will be pre-qualification. Major projects Ostlänken OL3200 Contract Performance contract regarding Contract > SEK 15 Object- No Rail Contracts-Ground East 2020 November 2021 May 2021 July Red - data > 1000 Johan Sundin Norrköping branch line, branch line through Nyköping, 21 million specific Region/Stockhol not construction and BEST km, comprising ground, bridge and m confirmed BEST. There will be pre-qualification.

Major projects Ostlänken OL5100 Contract signals Performance contract for the entire Contract > SEK 15 Object- No Rail Contracts-BEST-Signal East 2023 October 2024 March 2024 June Red - data 500 - 700 Johan Sundin and electrical engineering low- Ostlänken route comprising, for million specific Region/Stockhol not voltage example, the installation of technical m confirmed environments, cables, positioning system, signals, signs, distribution network 22 kV, transformer stations 50 Hz, 400 V requirements, lighting and switch heating, as well as all line- dependent power supply.

Major projects Ostlänken OL5000 Contract Performance contract comprising Contract > SEK 15 Object- No Rail Contracts-BEST-Electrical East 2023 October 2024 March 2024 June Red - data > 1000 Johan Sundin catenary line catenary line installation along the million specific Region/Stockhol not entire Ostlänken route. Foundation, m confirmed canalisation and distribution network 22 kV are not included. There will be pre-qualification.

Major projects Ostlänken OL5200 Contract Performance contract along the Contract > SEK 15 Object- No Rail Contracts-BEST-Telecom East 2023 December 2024 April 2024 June Red - data > 1000 Johan Sundin telecom/IT entire Ostlänken route for, inter alia, million specific Region/Stockhol not installation and assembly of all m confirmed telecom and IT equipment, detectors, telephony etc. There will be pre-qualification. Maintenance Maintenance of bridge 4-360-1 over The object is located on Road 53 by Contract > SEK 15 Object- No Road Contracts-Construction East 2017 January 2017 February 2017 June Green - 20 - 50 Marlene Torggatan, Bangården and Thams the harbour, Oxelösund million specific work-UH Bridges & Region/Stockhol reliable Hansson väg, Road 53 Reinforcement work, Replacement of tunnels m (within 3 support girders, plaster, Performance months) period 2017-2018 Maintenance Construction manager road lighting Services Object- No Road Technical consultants- East 2017 January 2017 February Information April Green - 1 - 5 Lars Stockholm Uppsala Gotland specific Project support Region/Stockhol missing reliable Lindström m (within 3 months) Maintenance For establishment of ARSC locations Contract > SEK 15 Object- No Road Contracts-Infrasystem- East 2017 January 2017 February 2017 April Green - 20 - 50 Lars million specific Manage traffic road Region/Stockhol reliable Lindström m (within 3 months) Maintenance Basic maintenance of railway Basic maintenance of railway Så-blir-du- Basic contract Object- Yes Rail Contracts-Basic contract East 2017 February 2017 May 2018 October Green - 300 - 500 Ted Linnes installation Svealand Line installations, Svealand line and leverantor/ Maintenance specific rail Region/Stockhol reliable Kolbäck-Rekarne, Eskilstuna-Flen. trafikverke m (within 3 The classification system TransQ is ts- months) being used for the procurement. kvalificerin Only companies that are prequalified gssystem--- in TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Basic maintenance of railway Basic maintenance of railway Så-blir-du- Basic contract Object- Yes Rail Contracts-Basic contract East 2017 February 2017 April 2017 October Red - data 500 - 700 Thomas installations Stockholm North installations Stockholm North leverantor/ Maintenance specific rail Region/Stockhol not Atterling Turnkey contract. The classification trafikverke m confirmed system TransQ is being used for the ts- procurement. Only companies that kvalificerin are prequalified in TransQ and which gssystem--- the Transport Administration invites transq to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance Consultants for cultural Services Object- No Road Technical consultants- East 2017 February 2017 February 2017 March Green - 1 - 5 Anders environment in Sthlm/East specific Specific technical areas of Region/Stockhol reliable Boqvist expertise m (within 3 months) Maintenance For execution of maintenance of For execution of maintenance of Surfacing Object- No Road Contracts-Surfacing East 2017 February 2017 March 2017 April Green - 50 - 100 Liselotte concrete road surfaces within concrete road surfaces within measures specific Region/Stockhol reliable Eriksson Uppsala (C) and Södermanland (D) Uppsala (C) and Södermanland (D) m (within 3 counties. counties. months) Maintenance For execution of partially heated For execution of partially heated Surfacing Object- No Road Contracts-Surfacing East 2017 February 2017 March 2017 April Green - 100 - 300 Liselotte road surface maintenance within road surface maintenance within measures specific Region/Stockhol reliable Eriksson Uppsala (C) Södermanland (D), Uppsala (C) Södermanland (D), m (within 3 Örebro (T) and Västmanland (U) Örebro (T) and Västmanland (U) months) counties. counties.

Maintenance Bridge over Torggatan Bangården Repairs, reinforcements Contract > SEK 15 Object- No Road Contracts-Construction East 2017 February 2017 March 2017 May Green - 20 - 50 Marlene and Thams väg by Oxelösund million specific work-UH Bridges & Region/Stockhol reliable Hansson harbour. 4-360-1 tunnels m (within 3 months) Maintenance Rebuilding of bridge across Rebuilding of bridge across Contract > SEK 15 Object- No Road Contracts-Construction East 2017 March 2017 April 2017 May Green - 10 - 20 Thomas Gothemsån Gothemsån at Västerbjärs, road 624 million specific work-Bridges Region/Stockhol reliable Atterling on Gotland m (within 3 months) Maintenance Reinvestment Muskö UPS Contract < SEK 15 Object- No Road Contracts-Infrasystem- East 2017 March 2017 April 2017 June Green - 1 - 5 Johan million specific Manage traffic road Region/Stockhol reliable Hedlund m (within 3 months) Maintenance Southern link replacement of Contract < SEK 15 Object- No Road Contracts-Infrasystem- East 2017 March 2017 April 2017 June Green - 1 - 5 Johan fittings outer road network million specific Manage traffic road Region/Stockhol reliable Hedlund m (within 3 months) Maintenance ITS conversion E4 Essingeleden Contract < SEK 15 Object- No Road Contracts-Infrasystem- East 2017 March 2017 April 2017 October Green - 10 - 20 Johan million specific Manage traffic road Region/Stockhol reliable Hedlund m (within 3 months) Maintenance Widening and ITS E18 Contract < SEK 15 Object- No Road Contracts-Infrasystem- East 2017 March 2017 April 2017 October Green - 1 - 5 Johan Norrtäljevägen million specific Manage traffic road Region/Stockhol reliable Hedlund m (within 3 months) Maintenance Re-investment in Radar Contract < SEK 15 Object- No Road Contracts-Infrasystem- East 2017 March 2017 April 2017 September Green - 1 - 5 Johan million specific Manage traffic road Region/Stockhol reliable Hedlund m (within 3 months) Maintenance Consultancy procurement Consultancy procurement Services Object- No Rail Technical consultants- East 2017 March 2017 August 2017 December Green - 1 - 5 Martina Investigation Tegnérgatan, bridge Investigation Tegnérgatan, bridge specific Planning & design Region/Stockhol reliable Johansson replacement, 3500-2942-1 and replacement, 3500-2942-1 and 3500- m (within 3 3500-2942-2 2942-2 months) Maintenance Replacement of bridge Brevensbruk Replacement of bridge Brevensbruk Maintenance Object- No Road Contracts-Construction East 2017 April 2017 May 2017 September Green - 5 - 10 Thomas 18-948-1 18-948-1 measures > SEK 5 specific work-UH Bridges & Region/Stockhol reliable Atterling million tunnels m (within 3 months) Maintenance Road assistance Disruption Road assistance Disruption Services Object- No Road Goods and services- East 2017 May 2017 August 2018 December Green - 100 - 300 Ove management Stockholm management Stockholm specific Indirect goods and Region/Stockhol reliable Strömberg services-Other m (within 3 months) Maintenance Basic maintenance of railway Basic maintenance of railway Så-blir-du- Basic contract Object- Yes Rail Contracts-Basic contract East 2017 June 2017 October 2019 May Red - data 500 - 700 Thomas installations installations Southern Main Line leverantor/ Maintenance specific rail Region/Stockhol not Atterling Katrineholm-Mjölby Katrineholm-Mjölby. The trafikverke m confirmed classification system TransQ is being ts- used for the procurement. Only kvalificerin companies that are prequalified in gssystem--- TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance IB - Västmanland County Integrated bridge maintenance in Basic contract Object- No Both road Contracts-Construction East 2017 June 2017 December 2018 January Green - 50 - 100 Thomas Västmanland County Maintenance specific and rail work-UH Bridges & Region/Stockhol reliable Atterling tunnels m (within 3 months) Maintenance Basic maintenance of railway Basic maintenance of railway Så-blir-du- Basic contract Object- Yes Rail Contracts-Basic contract East 2017 August 2017 November 2019 July Green - 100 - 300 Ted Linnes installations Mälaren Line installations Mälaren Line, Turnkey leverantor/ Maintenance specific rail Region/Stockhol reliable contract. The classification system trafikverke m (within 3 TransQ is being used for the ts- months) procurement. Only companies that kvalificerin are prequalified in TransQ and which gssystem--- the Transport Administration invites transq to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... "

Maintenance Bridge over Svartån at Olsbenning Reinforcement stone arch Maintenance Object- No Road Contracts-Construction East 2017 August 2017 September 2018 January Green - 1 - 5 Thomas replacement of superstructure measures < SEK 5 specific work-UH Bridges & Region/Stockhol reliable Atterling bridge million tunnels m (within 3 months) Maintenance Basic maintenance of railway Basic maintenance of railway Så-blir-du- Basic contract Object- Yes Rail Contracts-Basic contract East 2017 September 2018 January 2019 September Red - data 100 - 300 Thomas installations Western Main Line installations Western Main Line leverantor/ Maintenance specific rail Region/Stockhol not Atterling Gnesta Hallsberg Gnesta Hallsberg The classification trafikverke m confirmed system TransQ is being used for the ts- procurement. Only companies that kvalificerin are prequalified in TransQ and which gssystem--- the Transport Administration invites transq to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa-blir-du...... " Maintenance Basic maintenance of railway Basic maintenance of railway Så-blir-du- Basic contract Object- Yes Rail Contracts-Basic contract East 2017 September 2018 January 2019 September Red - data 100 - 300 Thomas installations Western Main Line installations Western Main Line leverantor/ Maintenance specific rail Region/Stockhol not Atterling Hallsberg-Laxå, Hallsbergs RBG Hallsberg-Laxå, Hallsbergs RBG. The trafikverke m confirmed classification system TransQ is being ts- used for the procurement. Only kvalificerin companies that are prequalified in gssystem--- TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Basic maintenance of railway Basic maintenance of railway Så-blir-du- Basic contract Object- Yes Rail Contracts-Basic contract East 2017 November 2018 March 2019 October Green - 500 - 700 Ted Linnes installations Stockholm South installations Stockholm South The leverantor/ Maintenance specific rail Region/Stockhol reliable classification system TransQ is being trafikverke m (within 3 used for the procurement. Only ts- months) companies that are prequalified in kvalificerin TransQ and which the Transport gssystem--- Administration invites to participate transq in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Integrated bridge maintenance Procurement of time and permit- Contract > SEK 15 Object- No Road Contracts-Construction East 2018 April 2018 June 2018 October Green - 50 - 100 Thomas Södermanland County controlled maintenance in million specific work-UH Bridges & Region/Stockhol reliable Atterling Södermanland County tunnels m (within 3 months) Maintenance Integrated bridge maintenance Procurement of time and permit- Contract > SEK 15 Object- No Road Contracts-Construction East 2018 June 2018 August 2018 December Green - 20 - 50 Thomas Östergötland County controlled maintenance in million specific work-UH Bridges & Region/Stockhol reliable Atterling Östergötland County tunnels m (within 3 months) Maintenance Operation and maintenance of Operation and maintenance of Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track East 2018 September 2018 October 2019 April Green - 50 - 100 Thomas hydraulics and pneumatics at hydraulics and pneumatics at leverantor/ million specific Region/Stockhol reliable Atterling Hallsberg marshalling yard Hallsberg marshalling yard. The trafikverke m (within 3 classification system TransQ is being ts- months) used for the procurement. Only kvalificerin companies that are prequalified in gssystem--- TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Hallsberg marshalling yard Hallsberg marshalling yard Så-blir-du- Contract > SEK 15 Object- Yes Rail Contracts-BEST-Track East 2018 September 2018 October 2019 April Green - 100 - 300 Thomas maintenance work brake pistons, maintenance work brake pistons, air leverantor/ million specific Region/Stockhol reliable Atterling air cylinders and material supply cylinders and material supply. The trafikverke m (within 3 classification system TransQ is being ts- months) used for the procurement. Only kvalificerin companies that are prequalified in gssystem--- TransQ and which the Transport transq Administration invites to participate in the procurement may submit tenders. For more information see the link to the right (in Swedish) "Sa- blir-du...... "

Maintenance Integrated bridge maintenance Procurement of time and permit- Basic contract Object- No Road Contracts-Construction East 2018 October 2018 December 2019 April Green - 50 - 100 Thomas Stockholm South controlled maintenance in Stockholm Maintenance specific work-UH Bridges & Region/Stockhol reliable Atterling South tunnels m (within 3 months) Maintenance Integrated bridge maintenance Procurement of time and permit- Contract > SEK 15 Object- No Road Contracts-Construction East 2018 October 2018 December 2019 April Green - 50 - 100 Thomas Stockholm North controlled maintenance in Stockholm million specific work-UH Bridges & Region/Stockhol reliable Atterling North tunnels m (within 3 months) Investment Renewed exposure to competition - Renewed exposure to competition Services Suborder Informati Information Information missing Information 2017 January Informatio Information Information Information Green - < 1 Lena Investigation regarding noise on framework agreement regarding on missing missing n missing missing missing missing reliable Scherman prevention measures on the Nynäs noise investigations - Investigation missing (within 3 Line due to goods traffic to and regarding noise prevention measures months) from Norvik harbour on the Nynäs Line due to goods traffic to and from Norvik harbour

Investment Construction site inspection (BPU) Services Object- Informati Information Information missing Information 2017 June 2017 August 2017 September Green - 1 - 5 Lena Catenary for the Hallsberg double specific on missing missing reliable Scherman track project missing (within 3 months) Information 2 resources for E01, West Link Services Object- Informati Information Information missing Information 2017 February 2017 March 2017 March Green - < 1 Poneh missing specific on missing missing reliable Elfström missing (within 3 months) Information Client consultant, West Link Services Object- Informati Information Information missing Information 2017 February 2017 March 2017 March Green - < 1 Poneh missing specific on missing missing reliable Elfström missing (within 3 months) Information Notified body, West Link Services Object- Informati Information Information missing Information 2017 April 2017 April 2017 May Green - < 1 Poneh missing specific on missing missing reliable Elfström missing (within 3 months) Information Aluminium cabinets Goods Object- Informati Information Information missing Information 2017 April 2017 May 2017 September Green - 20 - 50 Bertil missing specific on missing missing reliable Westerström missing (within 3 months)