<<

307

Probabilistic assessment of urban runoff potential

J.A. Harris and B.J. Adams

Abstract: At the planning or screening level of urban development, analytical modeling using derived probability distribution theory is a viable alternative to continuous simulation, offering considerably less computational effort. A new set of analytical probabilistic models is developed for predicting the erosion potential of urban runoff. The marginal probability distributions for the duration of a in which the critical velocity is exceeded (termed exceedance duration) are computed using derived probability distribution theory. Exceedance duration and peak channel velocity are two random variables upon which erosion potential is functionally dependent. Reasonable agreement exists between the derived marginal probability distributions for exceedance duration and continuous EPA Stormwater Management Model (SWMM) simulations at more common return periods. It is these events of lower magnitude and higher frequency that are the most significant to erosion-potential prediction. Key words: erosion, stormwater management, derived probability distribution, exceedance duration.

Résumé : Au niveau de la planification ou de la sélection en développement urbain, la modélisation analytique au moyen de la théorie de la distribution probabiliste dérivée est une alternative valable à la simulation continue car elle demande un effort computationnel beaucoup moindre. Dans le but de prédire le potentiel d’érosion par des eaux de ruissellement en milieu urbain, un nouvel ensemble de modèles probabilistes analytiques a été développé. Les distributions de probabilité marginales pour la durée d’un hydrogramme dans lequel la vélocité critique de courant dans le est dépassée (appelé durée de dépassement) sont calculées en utilisant la théorie de la distribution de probabilité dérivée. L’érosion potentielle est une fonction de la durée de dépassement et de la vitesse de pointe dans le canal. Une corrélation raisonnable entre les distributions de probabilité dérivée marginales quant à la durée de dépassement et les simulations continues SWMM à des fréquences de retour plus communes. Ce sont ces événements d’amplitude plus faible et à fréquence plus élevée qui ont le plus d’importance pour la prédiction du potentiel d’érosion. Mots clés : érosion, gestion des eaux de ruissellement, distribution de probabilité dérivée, durée de l’excédent. [Traduit par la Rédaction]

1. Introduction 1.1. Erosion potential and stormwater management Increased stormwater into a receiving channel of- The rapid expansion of urban areas into previously unde- ten tends to proliferate the occurrence of downstream flood- veloped land demands extensive infrastructure. With ing and the erosion of the beds and banks of channels that changing land use, the impervious portion of the surface area result from higher discharge rates over longer durations and of a catchment increases while infiltration and evapotranspira- many other significant problems. tion, interflow, and baseflow decrease. To mitigate the effects emerges as one of the key issues of stormwater management. of , one must first understand the behaviour of in- Although accelerated erosion due to agricultural mis- creased stormwater runoff (peak flow rate and duration) and management has long been an issue in rural lands (Cooke and how this relates to erosion potential. The goal of stormwater Doornkamp 1990), erosion is now a serious form of soil degra- modeling is to predict catchment loads, such as runoff rates and dation in urban areas as well. Municipalities face unending volumes and concentrations and masses, from an ex- development pressures and need a comprehensive long-term isting or planned urban area. An analytical stormwater model management strategy to deal with the problems of future de- for predicting stormwater erosion potential is developed in this velopment (Dillon Consulting Engineers and Planners 1982). paper. An important objective of stormwater management is to sus-

Received 23 November 2004. Revision accepted 16 November 2005. Published on the NRC Research Press Web site at http://cjce.nrc.ca/ on 1 April 2006. J.A. Harris1,2 and B.J. Adams. Department of Civil Engineering, University of Toronto, 35 St. George Street, Toronto, ON M5S 1A4, Canada. Written discussion of this article is welcomed and will be received by the Editor until 31 July 2006. 1 Corresponding author (e-mail: [email protected]). 2 Present Address: 19 Thelma Avenue, Toronto, ON M4V 1X8, Canada.

Can. J. Civ. Eng. 33: 307–318 (2006) doi: 10.1139/L05-114 © 2006 NRC Canada 308 Can. J. Civ. Eng. Vol. 33, 2006 tain a fluvial system with its aquatic and aesthetic value and Fig. 1. Derived probability distribution theory. recreation potential while accommodating development needs within a watershed (MOE 1999). Dry-weather flow and runoff from frequent rainfall events of moderate magnitude are conveyed in an active channel, and larger storm flows spill onto the floodplain. Increased peak flow rates and runoff volumes disrupt this dynamic balance. Urban- ization substantially increases the occurrence of mid-bankfull flows (those which only partially fill the active channel), and it is thought that these frequent flow events perform the most work in shaping (i.e., eroding) the channel (MOE 1999). Leopold et al. (1964) generate an erosive work curve which indicates that the greatest quantity of material is transported by events with relatively high frequencies rather than by extreme events. MacRae (1997) further stresses that an erosion-control philos- ophy that does not address these high-frequency events may known CDF of X is used to obtain this probability, as illustrated not adequately meet the intended purpose. A large contribution in Fig. 1. to the erosion of channels is from relatively frequent events of A random variable, Z, may be functionally dependent on two = moderate magnitude (Leopold et al. 1964) as opposed to infre- independent variables, X andY, such that Z g(X,Y). Similar quent events of high magnitude. to the case with one independent variable, the CDF of Z, i.e., the probability that Z ≤ z, describes the probability that X and ≤ 1.2. Evolution of stormwater management modeling Y lie in a region where g(x,y) z. Mathematically, this is approaches described by The practice of urban drainage modeling has seen a shift = [ ≤ ] from the design-storm approach, whereby a modeled catchment [1] FZ(z) P Z z is subjected to a hypothetical storm of a certain = P [X and Y take on values x,y and the hydrologic response analyzed, to continuous simula- such that g(x,y) ≤ z] tion modeling, as it is generally accepted that, in the design of storage facilities and water quality control structures, long-term = fX,Y (x, y)dx dy performance is more critical than single, design-event perfor- R mance (Adams and Papa 2000). The computational burden of z continuous simulation, however, particularly with short time where Rz is the region in the x–y plane where g(x,y) ≤ z. steps, may be prohibitive to the practicing engineer in planning- Assuming independence, the joint probability density function level analysis where numerous alternatives require evaluation. of x and y is simply the product of their marginal distributions, Requiring considerably less computational effort is analytical that is, probabilistic modeling using derived probability distribution theory. This alternative modeling methodology, developed for [2] fX,Y (x, y) = fX(x)fY (y) planning or screening level, returns simple mathematical rela- tionships for system performance statistics such as runoff rates The probability of the occurrence of x and y falling in the region and volumes.Analytical models developed herein are planning- Rz is the volume beneath their joint PDF, fX,Y (x, y). level models intended to predict the erosion potential associated with existing and proposed urban developments. 2. Hydrological applications of derived The fundamental principle behind this research is the deriva- probability theory tion of the probability distribution of a random variable based on that of another variable on which the former is function- ally dependent. The derivation is possible because the inherent Derived probability distribution theory has played an im- randomness of the independent variable is imparted to the de- portant role in water-resources and hydrological applications. pendent variable (Benjamin and Cornell 1970). The probabil- A pioneer in this area of research, Eagleson (1972), used the ity density function (PDF) of the duration of a runoff event in functional relationship of the kinematic wave theory of hydro- which a critical discharge rate is exceeded, d, is derived from graph generation to derive the peak streamflow probability dis- the PDFs of rainfall event volume, v, and total duration, t, the tribution, offering a method to calculate flood frequency in the two random variables upon which d is functionally dependent. absence of streamflow records. More recently, using the joint To illustrate the derivation of the PDF of a dependent variable, PDFs of meteorological inputs (rainfall event volume, dura- one-variable transformations are first described. The dependent tion, intensity, and inter-event time), probability distributions of variable,Y, and independent variable, X, are functionally related event runoff volume and peak discharge rate were developed by by Y = g(X). The inverse of this function solves for the inde- Guo and Adams (1998, 1998a) using EPA stormwater manage- pendent variable, X = g−1(Y ). The cumulative density func- ment model (SWMM) type hydrology (Huber and Dickinson tion (CDF) of the dependent variableY is simply the probability 1988) and triangular runoff as illustrated in Fig. 2, that Y is less than some value y that is equal to the probability where Qp is the peak discharge rate (mm/h), Qc is the critical −1 that X is less than the corresponding value x = g (y). The flow rate (mm/h), t is the storm duration (h), tc is the catchment

© 2006 NRC Canada Harris and Adams 309

Fig. 2. Triangular hydrograph. reaches of a watercourse (MOE 1999). Collected streambank stratigraphy information is used to determine the threshold for erosion in each reach of a watercourse prior to development. The stormwater management plan can then be prepared. The MOE recommends that this analysis be conducted at the water- shed or subwatershed level, rather than at incremental stages of development (MOE 1999). Researchers also recommend using tractive force – permis- sible velocity analysis at the subwatershed plan level (Marshall Macklin Monaghan Limited 1994). This multicriterion concept considers discharge, duration that a critical discharge rate is ex- ceeded, and boundary material characteristics (MacRae 1997). Assuming uniform material, the erodibility of a downstream channel can be expressed by the mean size that is sub- jected to a tractive force whereby the mean particle size cor- time of concentration (h), and d is the duration over which the responds to a mean velocity, above which erosion will occur, critical discharge rate is exceeded. i.e., the critical velocity (Cooke and Doornkamp 1990). The Chan and Bras (1979) derived the frequency distribution of erosion-potential impulse can then be calculated as the product runoff volume above a critical discharge rate from a storm event of the difference between the channel velocity and the critical (i.e., overflow volume) using the joint PDF of rainfall inten- velocity and the exceedance duration. The summation is per- sity and duration. This work assumed that rainfall intensity and formed for the entire duration of the design storm event and duration may be represented by exponential PDFs; these ex- can be extended to a continuous simulation application, since ponential distributions for meteorological characteristics have the active channel is not formed by a single event, but rather its been used extensively by hydrological researchers (e.g., Adams form is a result of the sum of forces exerted on a channel by a and Papa 2000) and are also adopted in this paper. The rainfall continuum of flow events (MOE 1999). volume (v in mm) and duration (t in h) PDFs used to derive the In the absence of a subwatershed plan, a typical criterion for exceedance probability are represented by exponential PDFs as erosion control for a single development in the Province of On- follows: tario is to design a storage facility that will detain runoff from a 25 mm storm event over 24 h. It is thought that this conve- [3] fV(v) = ζ exp(−ζv) ζ = 1/v¯ nient approach may actually underestimate the required erosion control, since receiving conditions (such as stratigraphy, f (t) = λ (−λt) λ = /t¯ [4] T exp 1 channel slope, and cross section) are not taken into considera- where ζ is the parameter of the exponential probability density tion, and the use of a single event to represent erosion poten- function for V, v¯ is the mean rainfall event volume, λ is the tial may be misleading, since erosion is a highly discontinuous parameter of the exponential probability density function for but ongoing process resulting from a continuum of flow events T, and t¯ is the mean rainfall event duration. Because the ran- (MOE 1999). dom variables are considered statistically independent, the joint Alongside the 25 mm storm approach, another commonly PDF of v and t is simply the product of their marginal PDFs as applied method to determine erosion potential is the 2 year peak follows: flow rate attenuation approach, whereby post-development flows are reduced to those of pre-development levels, resulting in a = − − [5] fV,T(v, t) ζλexp( ζv λt) flat hydrograph with a long recession limb. The 2 year storm ap- Further developing analytical models for flood forecasting, proach has met with some success, however, many researchers Mukherjee and Mansour (1991) comment that not enough atten- support the idea that it may actually aggravate erosion (MacRae tion has been paid to using the joint probability of runoff flow 1997). The approach does not address the increased frequency and duration to forecast alarm-level floods. Their later work of mid-bankfull to bankfull flows, the increased high discharge shows that a univariate analysis of flow alone underestimates frequency caused by the peak flow rate attenuation due to stor- the exceedance probability of flood flow and, by using the joint age, or the sensitivity of channel materials to erosion (MacRae probability of flow and duration, more effective management 1997). of flood risk areas can be practiced (Mukherjee and Mansour A univariate approach (i.e., considering peaks of flow rates 1996). Adams and Papa (2000) provide a more detailed account only) to establish the erosion potential of an existing or proposed of the evolution of derived probability distribution and its role development does not consider low-magnitude, high-frequency in and hydrology. events that many researchers believe to be key channel-forming events (Leopold et al. 1964; MacRae 1997; MOE 1999). A sec- ond variable, the duration that a critical tractive force is ex- 2.1. practices in predicting erosion potential ceeded, must be considered when estimating erosion potential. A methodology for determining the erosion potential of a As discussed earlier, this critical tractive force can be equated to development plan was outlined by the Ontario Ministry of the a critical average channel velocity above which erosion occurs Environment (MOE) based on the change in the hydrologic (Cooke and Doornkamp 1990). This paper advances the de- regime that results from the development of a subwatershed– velopment of the joint probability distribution of peak channel watershed and changes in stratigraphy throughout various velocity, up, and the duration of a streamflow event over which

© 2006 NRC Canada 310 Can. J. Civ. Eng. Vol. 33, 2006 the critical velocity is exceeded, d. Given that one method for ment on the erosion potential of a downstream receiving water predicting the erosion potential, Ep, is by taking the product body. The marginal probability distribution of d is derived; how- of up and d, their joint PDF would be a valuable tool at the ever, further research is required to derive the joint PDF of these planning–screening level to predict the effect of land develop- random variables, i.e., fUp,D(up,d).

3. Analytical model development

Using SWMM-type hydrology, the triangular runoff hydrograph of Fig. 2 is generated from a rainfall input, with the runoff duration equalling the sum of the rainfall event duration and the catchment time of concentration. The exceedance duration, d, the length of time that the runoff discharge is greater than a critical discharge, Qc, is determined by the similar triangles of Fig. 2. That is,

d Qp − Qc Qc [6] = or d = (t + tc) 1 − t + tc Qp Qp

The peak discharge rate is estimated from the runoff event volume, the duration of the rainfall event, and several catchment parameters. Following the work of Guo and Adams (1998, 1998a), the event runoff volume, vr, is determined to be

⎧ ⎨0 v ≤ Sdi in region a = − ≤ + [7] vr ⎩h(v Sdi)Sdi Sil + fct in region c

where h is the fraction of the impervious area of the catchment; Sdi is the impervious area depression storage (mm); Sdp is the pervious area depression storage (mm); Sd is the area-weighted average depression storage of the pervious and impervious areas of the catchment (mm); fc is the ultimate infiltration capacity of a soil (mm/h); and Sil is the initial loss in the pervious portion of the catchment (mm), where Sil = Siw + Sdp and Siw is the initial soil wetting infiltration volume. It is evident that the event runoff volume varies within the three mutually exclusive regions (a, b, and c) in the v–t plane. Based on the geometry of the hydrograph in Fig. 2, where the event runoff volume is the area under the triangular hydrograph, the peak discharge rate is determined to be

⎧ ⎪0 in region a ⎪ ⎨⎪ 2h(v−Sdi) 2vr + in region b [8] Qp = or Qp = t tc (t + tc) ⎪ ⎪ 2[v−S −f (1−h)t] ⎪ d c in region c ⎩ t+tc

Figure 2 shows that the exceedance duration is zero when the critical discharge is not exceeded. For the three ranges of Qp, this relationship is described by

⎧ ≤ ⎪v Sdi in region a ⎨⎪ Qc [9] Qp ≤ Qc or v ≤ (t + tc) + Sdi in region b ⎪ 2h ⎩⎪ ≤ Qc + + + − v 2 (t tc) Sd fc(1 h)t in region c

© 2006 NRC Canada Harris and Adams 311

The relationship between d and v and t is then described by combining eqs. [7]–[9] as follows: ⎧ ⎧ ⎧ ⎪ ⎪(region b) S Sil + fct ⎪ ⎪ ⎪ ⎪ ⎨ ⎨ ⎪ and and ⎪0 (region a) v ≤ Sdi or or ⎪ ⎪ ⎪ ⎪ ⎪ ⎪ Qc ⎪ ⎪ Qc ⎪v ≤ (t + t ) + S + f (1 − h)t ⎪ ⎩⎪v ≤ (t + tc) + Sdi ⎩ 2 c d c ⎪ 2h ⎪ ⎪ ⎪ ⎧ ⎪ ⎪S Qc (t + t ) + S ⎪ ⎩ 2h c di ⎪ ⎪ ⎪ ⎧ ⎪ ⎪ + ⎪ ⎪v>Sil fct ⎪ ⎪ ⎪ ⎨ ⎪ Qc(t+tc) and ⎪(t + tc) 1 − ⎪ 2[v−Sd−fc(1−h)t] ⎪ ⎪ ⎪ ⎪ ⎪v>Qc (t + t ) + S + f (1 − h)t ⎪ ⎩ 2 c d c ⎩⎪

The exceedance duration transformation function of eq. [10] is The impulse probability, P [d = 0], can be found by inte- plotted in Fig. 3. grating the joint PDF of v and t over the regions of integration described by eq. [11]. The mutually exclusive impulse integra- 3.1. Exceedance duration impulse probability tion regions are governed by these inequalities in the v–t plane: distribution Impulse integration region 1 (IP ) The impulse probability of zero exceedance duration results 1 from those storm events where the peak discharge rate is less [12] v ≤ Sdi than the critical rate, or Qp ≤ Qc (see eq. [10]). The impulse probability of the critical discharge exceedance duration, com- Impulse integration region 2 (IP2) prised of three parts, is described by the following relationship: S Sil + fct] 2h Impulse integration region 3 (IP3) Qc ∩ P [v ≤ (t + tc) + Sd + fc(1 − h)t] + 2 v>Sil fct [14] Qc v ≤ (t + tc) + Sd + fc(1 − h)t The probability distributions of the meteorological input to 2 the catchment (i.e., rainfall event volume and duration) are Four straight lines are formed by the inequalities of eqs. [12]– satisfactorily represented by exponential PDFs for many cli- [14] and are represented by the following equations: mates (Adams and Papa 2000). The single-parameter exponen- tial distributions, in which the mean and standard deviation are [15] Line 0: v = Sdi equal, best represent the distribution of meteorological param- eters of lower magnitude and higher frequency (i.e., the left Qc [16] Line 1: v = (t + tc) + Sdi side of the PDF) and are not recommended to describe very 2h low frequency, extreme events. Because it is evident that low- [17] Line 2: v = Sil + fct magnitude, high-frequency events have the most erosion po- Qc tential (MacRae 1997), the rainfall volume and duration PDFs [18] Line 3: v = (t + tc) + Sd + fc(1 − h)t used to derive the exceedance probability are assumed to be 2 represented by the exponential PDFs as in eqs. [3] and [4]. The definitions of integration regions IP1,IP2, and IP3 indi- The impulse probability, P [d = 0], can be found by integrat- cate that IP1 is the area in the v–t plane below line 0, IP2 is the ing the joint PDF of v and t (eq. [5]) over the regions of inte- area in the v–t plane above line 0 and below lines 1 and 2, and gration described by eq. [10]. The mutually exclusive impulse IP3 is the area in the v–t plane above line 2 and below line 3. integration regions are governed by the following inequalities By these definitions, the three impulse integration regions are in the v–t plane. mutually exclusive (Fig. 4).

© 2006 NRC Canada 312 Can. J. Civ. Eng. Vol. 33, 2006

Fig. 3. Exceedance duration transformation function. between those of lines 1 and 2. The relative magnitudes of the d slopes and intercepts of lines 1 and 2 will establish the impulse integration regions, IP2 and IP3. The difference between the slopes of lines 1 and 2 is Q [19] c − f 2h c The difference between the intercepts of lines 1 and 2 is Q t Q t [20] S + c c − S = c c − S di 2h il 2h dd

where Sdd = Sil − Sdi. The impulse integration regions are de- termined from two sets of conditions: Qc < 2hf c or Qc ≥ 2hf c (slope condition) and Qc < 2hSdd/tc or Qc ≥ 2hSdd/tc (inter- cept condition 1). The conditions that hold true for a particular [ = ] Fig. 4. Impulse integration regions IP1,IP2, and IP3 for P d 0 catchment are based on the characteristics of that catchment. of type IV catchments. Four possible combinations of these conditions result in the following four catchment types:

2hSdd [21] Type I: Qc < 2hf c and Qc < tc

2hSdd [22] Type II: ≤ Qc < 2hf c tc 2hSdd [23] Type III: 2hf c ≤ Qc < tc

2hSdd [24] Type IV: Qc ≥ 2hf c and Qc ≥ tc The impulse exceedance probability is only developed for type IV catchments in this paper; however, fully developed an- alytical models for all catchments types are developed in Harris (2002) and summarized in Table 1. The joint probability density It is a reasonable assumption that the impervious depression function, fV,T(v, t) of eq. [5] is integrated over the shaded area storage, Sdi, will always be less than the initial hydrologic losses in Fig. 4. from the pervious area of a catchment, Sil, and therefore line 0 The exceedance duration impulse probability for type IV will always be below lines 1, 2, and 3. For this reason, IP1 will catchments is the sum of the integration regions IP1,IP2, and remain unchanged for all scenarios. The algebraic nature of the IP3 as follows: lines is such that the slope and intercept of line 3 will always fall

∞ Qctc/2h+Sd+[fc(1−h)+Qc/2]t [25] P [d = 0]= ζλexp(−ζv − λt)dv dt 0 0 2λ Qctc = 1 − exp −ζ + Sd 2ζfc(1 − h) + ζQc + 2λ 2

3.2. Exceedance duration cumulative density function and d ≤ do, where do is an arbitrary exceedance duration value Thus far, the impulse probability portion of the cumulative that must be greater than zero. density function (CDF) for d, such that the critical discharge rate The probability of d ≤ do (for any do > 0) is derived in the is not exceeded (i.e., P [d = 0]), is developed. The remaining following two mutually exclusive parts: portion of the CDF for d must incorporate those areas in the v–t P [d ≤ do]=P1[d ≤ do]+P2[d ≤ do] plane where Qp >Qc (i.e., the critical discharge is exceeded)

© 2006 NRC Canada Harris and Adams 313

where v and t are such that Qp >Qc. P1 and P2, mutually exclusive areas in the v–t plane, are the regions over which the probability density function, fV,T(v, t), is integrated. These regions are described by the following equations:

Region of integration, P1 ⎧ ⎧ + 2 ⎪ Qc(t tc) ⎪ Qc(t+tc) ⎪(t + tc) 1 − − ≤ do ⎪v ≤ + S ⎨ 2h(v Sdi) ⎨ 2h(t+tc−do) di ≤ + ⎪v ≤ Sil + fct and or equivalently ⎪v Sil fct and ⎩⎪ ⎩⎪ Qc + + v>Qc (t + t ) + S v> 2h (t tc) Sdi 2h c di

Region of integration, P2 ⎧ ⎧ + + 2 ⎪ + − Qc(t tc) ≤ ⎪ Qc(t tc) ⎪(t tc) 1 [ − − − ] do ⎪v ≤ + Sd + fc(1 − h)t ⎨⎪ 2 v Sd fc(1 h)t ⎨⎪ 2(t+tc−do) + v>S + f t and ⎪v>Sil fct and or equivalently ⎪ il c ⎪ ⎪ ⎩ Qctc + + − + Qc ⎩v>Qctc + S + f (1 − h) + Qc t v> 2 Sd fc(1 h) 2 t 2 d c 2

Analogous to the impulse probability derivation, five lines are lines 1 and 4 in the linear portion and then adding this value to formed by these two inequalities, represented by the following line 1 as follows: equations: Q (t + t )2 line 4 – line 1 = c c + S Q t Q 2h(t + t − d ) di line 1 = v = c c + S + c t (equal to eq. [16]) c o 2h di 2h Q − c (t + t ) + S 2h c di line 2 = v = S + f t (equal to eq. [17]) il c + = Qc(t tc)do 2h(t + tc − do) line 3 = v ∼ Qcdo Q t Q = for t>>do = c c + S + f (1 − h) + c t 2h 2 d c 2 (equal to eq. [18]) Q d [28] line 4 = line 1 + c o 2h Q (t + t )2 [26] line 4 = v = c c + S Qc Qc + − di = (tc + do) + Sdi + t 2h(t tc do) 2h 2h 2  Qc(t + tc) Similarly, the linearized line 5, termed line 5 , is found by [27] line 5 = v = + Sd + fc(1 − h)t 2(t + tc − do) taking the difference between lines 3 and 5 in the linear portion and then adding this value to line 3 as follows: According to the definitions of P1 and P2, P1 is the area in the v–t plane above line 1 and below both line 2 and line 4, and Qcdo [29] line 5 = line 3 + P2 is the area in the v–t plane above lines 2 and 3 and below 2 line 5. Line 0 of the impulse probability section will always be Qc Qc below lines 1 and 2 and therefore does not influence integration = (tc + do) + Sd + fc(1 − h) + t 2 2 regions P1 and P2. Analogous to the preceding impulse probability development for d, various combinations of the slopes and intercepts of lines 3.3. Linearization 1–3, 4, and 5 determine the integration regions over which the joint probability density function f (v, t) is integrated to Due to the nonlinear nature of lines 4 and 5, closed-form ex- V,T determine the approximate CDF of d. The probability of d ≤ d pressions of exceedance duration probability distributions can- o (for any d > 0) is again in two mutually exclusive parts: not be obtained. Although an approximation, closed-form ex- o pressions are more readily usable in planning–screening-level P [d ≤ do]=P1[d ≤ do]+P2[d ≤ do] analyses to predict erosion potential. The nonlinear portion of lines 4 and 5 dominates when t is small; as t increases, the lin- where v and t are such that Qp >Qc. P1 is the area in the v–t  ear portion of the lines dominates. The linear approximation of plane above line 1 and below lines 2 and 4 . P2 is the area in the line 4, termed line 4, is found by taking the difference between v–t plane above lines 2 and 3 and below line 5. Linearization

© 2006 NRC Canada 314 Can. J. Civ. Eng. Vol. 33, 2006

Table 1. Summary of exceedance duration analytical probabilistic models for each of the four catchment types.

Type I catchments (Qc < 2hf c and Qc < 2hSdd/tc) ≤ 2hSdd − = − 2hλ − Qc + + For 0 Q tc FD(d) 1 2ζf (1−h)+ζQ +2λ exp ζ 2 (tc d) Sd ζfc(1 h) ζ 2 λ t c c c − 2λ − Qc + + 2ζf (1−h)+ζQ +2λ exp ζ 2 (tc d) Sd c c 2hλ Qc Qc ∗∗ − exp −ζ (tc + d) + Sdi − ζ + λ t ζQc+2hλ 2h 2h

Type II catchments (2hSdd/tc ≤ Qc < 2hf c) = − 2λ − Qc + + For d>0 FD(d) 1 2ζf (1−h)+ζQ +2λ exp ζ 2 (tc d) Sd c c + 2λ − Qc + + − − + Qc + ∗∗ 2ζf (1−h)+ζQ +2λ exp ζ 2 (tc d) Sd ζfc(1 h) ζ 2 λ t c c 2hλ Qc Qc ∗∗ − exp −ζ (tc + d) + Sdi − ζ + λ t ζQc+2hλ 2h 2h

Type III catchments (2hf c ≤ Qc < 2hSdd/tc) ≤ 2hSdd − = + 2hλ − Qc + + − Qc + ∗∗ For 0 − tc FD(d) = 1 − exp −ζ (tc + d) + Sd Qc 2ζfc(1−h)+ζQc+2λ 2

Type IV catchments (Qc ≥ 2hf c and Qc ≥ 2hSdd/tc) 2λ Qc For d>0 FD(d) = 1 − exp −ζ (tc + d) + Sd 2ζfc(1−h)+ζQc+2λ 2

leaves the slope condition and intercept condition 1 unchanged, Fig. 5. Linearized integration regions P1 and P2 for P [0

2hSdd 2hSdd [30] do ≤ − tc or do > − tc Qc Qc The intercept of line 4 is always greater than that of line 1, and in the same way the intercept of line 5 is always greater than that of line 3. Therefore, the ordering of the relative mag- nitudes of intercepts of importance includes lines 1 and 2, 2 and 4, and 2 and 5. Again, the integration regions are defined by various combinations of the slope condition and intercept conditions 1 and 2. Not all combinations of these conditions exist, however. When Qc ≥ 2hSdd/tc, the term 2hSdd/Qc − tc becomes negative, and d cannot assume a negative value. The same combinations of slope and intercept conditions used in the catchment types described earlier are used to determine the integration regions P1 and P2. Lines 1–5 are plotted in the v–t plane for the four catchment regions P1 and P2 is the sum of the following areas: ⎧ types, and the corresponding regions of integration are deter- ⎪0

© 2006 NRC Canada Harris and Adams 315

The probability that the exceedance duration is greater than than zero and d cannot be less than zero). The joint probability an arbitrary amount, do, is found in only one part for do > 0 density function, fV,T(v, t), is integrated over the shaded area (because the term 2hSdd/Qc −tc of intercept condition 2 is less in Fig. 5.

For any do > 0, the probability that d is between zero and do is ∞ Qc(tc+do)/2+Sd+[fc(1−h)+Qc/2]t [31] P [0

When the impulse probability for type IV catchments (eq. [25]) is added to eq. [31], the probability that d ≤ do is given by

[32] F (d) = P [d = 0]+P [0

When do = 0, eq. [32] yields

F (0) = P [d = 0] D 2λ Qc = 1 − exp −ζ tc + Sd 2ζfc(1 − h) + ζQc + 2λ 2 which is in agreement with the impulse probability of eq. [25]. The PDF of d for a catchment with type IV characteristics is determined by taking the derivative of its CDF as follows:

dFD(d) [33] fD(d) = d d ζλQc Qc = exp −ζ (tc + do) + Sd 2ζfc(1 − h) + ζQc + 2λ 2 The expected value of d per rainfall event for type IV catchments is found as follows: ∞ [34] E(d) = 0 · P [d = 0]+ d · fD(d) dd 0 4λ Qctc = exp −ζ + Sd ζQc (2ζfc(1 − h) + ζQc + 2λ) 2 Without significant loss of accuracy, by linearizing the integration regions that determine the probability distribution of ex- ceedance duration, an analytical model that is used with relative ease arises for planning–screening-level analyses. A summary of the analytical probabilistic exceedance duration models is presented in Table 1 for each of the four catchment types.

4. Comparison of results with continuous that continuous simulation is the most reliable approach for es- SWMM simulation results timating runoff quantities from small urban catchments in the absence of historical discharge data and is therefore used for The validity of the derived analytical model for predicting comparison with the analytical models developed in this re- the probability distribution of exceedance duration is verified search. The 33 year historical rainfall record at the Pearson In- by comparing the model results with those from SWMM simu- ternational Airport (years 1960–1992), Atmospheric Environ- lations. A continuous simulation model was chosen to compare ment Service (AES) station 6158655 (Toronto, Ontario), was results with those from the analytical model as opposed to us- used as input to the SWMM module. Runoff quantities ing field data. Continuous gauging of runoff from urban areas is were then simulated using the RUNOFF module, and the sim- rare and often only provides short records. Guo (1998b) notes ulated flow series were subjected to frequency analysis. The

© 2006 NRC Canada 316 Can. J. Civ. Eng. Vol. 33, 2006

Fig. 6. Analytical and SWMM simulation model comparison. 50 Analytical Model Results

40 SWMM Simulation Results

30

20 Critical Discharge Exceedance Duration (h) 10

0 1 10 100 Return Period (years) same rainfall record was used to extract parameter values for This one-parameter distribution is particularly useful to analyze the PDFs of rainfall characteristics used in the analytical model. those events of higher frequency, and an extreme-value distri- Comparative SWMM simulations were performed with the bution analysis is necessary for those more infrequent events. PCSWMM 2002 interface. This version of PCSWWM allows The same may be said for the analytical model developed here the user to plot the historical runoff time series and define an to predict the frequency distribution of erosion-causing runoff “exceedance” or critical discharge, Qc. The output summary events. includes the number of exceedances for the entire runoff time The analytical model return period is consistently lower than series. Because of the difficulties in correlating each runoff that of the SWMM simulations for return periods of 30 years event from the SWMM simulation output with a specific in- or less. The linearized integration regions in determining the put rainfall event (PCSWMM does not allow the user to define cumulative probability density function may account for part an inter-event time), a comparison of the annual duration that of the discrepancies between the models. To some extent, lin- a critical discharge rate is exceeded was performed. Using the earization decreases the area of the integration regions, as the PCSWMM interface, the total critical discharge exceedance du- nonlinear portion is shaved off and the smaller integration re- ration is returned for each year of simulation. The yearly total gions underestimate the exceedance duration CDF. Given that exceedance duration was recorded and ranked, and its corre- return period is directly proportional to the CDF, the return sponding Weibull plotting position determined. period is also underestimated. The analytical model returns the exceedance duration prob- With a rather short rainfall record of 33 years, it would not be ability per rainfall event. To convert the probability per rainfall prudent to make hydrological decisions based on return periods event to a return period, the following expression is used: of 10 years or greater. The highest exceedance duration that results from the SWMM simulation is given a return period of 1 1 [35] TR = = 34 years (slightly greater than the length of the rainfall record); θ · P [d>do] θ · (1 − P [d ≤ do]) however, this duration may actually be associated with a return period of much greater than 33 years. Outliers in the record may where TR is the return period of exceedance duration, do,in years; and θ is the average number of rainfall events per year. explain why the exceedance duration increases exponentially Figure 6 shows a comparison between the analytical and with increasing return period in the tail of Fig. 6. SWMM model results for a type IV catchment. There was rel- atively close agreement between the analytical and SWMM re- 5. Conclusions sults for the lower return periods.As the return period increases, large differences between the model results exist; however, the Urbanization replaces previously pervious areas with imper- events of higher frequency (thus lower return period) are of the vious ones via pavements and rooftops. The resultant increased most interest in this research because it is thought that they stormwater runoff brings about downstream flooding and the are more significant from an erosion standpoint (Leopold et al. erosion of the beds and banks of drainage channels and water 1964; MacRae 1997). In addition, the reliability of the plotting courses. With water as the eroding agent, soil particles are re- position at high frequencies is reduced. It was noted earlier that moved either uniformly by the impact of raindrops or irregularly the frequency distributions for meteorological parameters, rain- by distributed flow in or , i.e., runoff. Erosion control fall volume and storm duration, were assumed to be exponential. must be a priority to planners because of the economic impacts

© 2006 NRC Canada Harris and Adams 317 of disappearing lands abutting waterways and the impairment Ontario Ministry of Transportation, Toronto, Ont. Dillon Consulting of biological activity in channels as a result of transported and Engineers and Planners, Toronto, Ont. deposited . Eagleson, P.S. 1972. Dynamics of flood frequency. Water Resources At the planning- or screening-level analysis of urban develop- Research, 8(4): 878–897. ment, analytical modeling using derived probability distribution Guo,Y. 1998. Development of analytical probabilistic urban stormwa- theory is a viable alternative to complement continuous simula- ter models. Ph.D. thesis, Department of Civil Engineering, Univer- tion, offering considerably less computational effort. This paper sity of Toronto, Toronto, Ont. provides an illustration of the methodology of this approach. Guo, Y., and Adams, B.J. 1998a. Hydrologic analysis of urban catch- Using the probability density functions (PDFs) of meteorolog- ments with probabilistic models. Part I: runoff volume. Water Re- ical inputs (rainfall volume, duration, intensity, and inter-event sources Research, 34(12): 3421–3431. time), screening-level analytical models for the evaluation of Guo, Y., and Adams, B.J., 1998b. Hydrologic analysis of urban catch- urban drainage system quantity and quality control have been ments with probabilistic models. Part II: peak discharge rate. Water developed for a range of control alternatives and system sce- Resources Research, 34(12): 3433–3443. narios (Adams and Papa 2000). Harris, J. 2002. Analytical probabilistic models for urban stormwater Contributing to the analytical modeling research area, new erosion potential. M.A.Sc. thesis, Department of Civil Engineering, probabilistic models are developed herein for predicting the University of Toronto, Toronto, Ont. erosion potential of stormwater runoff. Erosion potential is the Huber, W., and Dickinson, R. 1988. Storm water management model, product of peak channel velocity and the duration that a critical version 4: user’s manual. US Environmental Protection Agency, velocity is exceeded (termed exceedance duration). The joint Athens, Ga. PDF of these two random variables indicates with relative ease Leopold, L.B., Wolman, M.G., and Miller, J.P. 1964. the erosion potential from existing or proposed developments, in geomorphology. W.H. Freeman and Co., San Francisco, Calif. and this is not offered by continuous simulation. The marginal MacRae, C.R. 1997. Experience from morphological research on distribution for exceedance duration, d, is developed, and future Canadian : is control of the two-year frequency runoff event research is required for the derivation of their joint probability the best basis for stream protection? In Effects of Watershed Devel- density function with which the erosion potential of a rainfall opment and Management on Aquatic Systems: Proceedings of the event may be readily computed. Engineering Foundation Conference, Snowbird, Utah, 4–9 August Reasonable agreement between the results of the analytical 1996. Edited by L. Rosner. ASCE, New York. pp. 144–160. model and an equivalent continuous simulation model, SWMM, Marshall Macklin Monaghan Limited. 1994. Stormwater management exists in the range of lower return period or higher frequency practices planning and design manual. Prepared for the Ontario events. This is consistent with the concept behind the analyti- Ministry of Environment and Energy. Marshall Macklin Monaghan cal probabilistic models developed with single-parameter expo- Limited, Thornhill, Ont. nential marginal PDFs for meteorological statistics which are MOE. 1999. Stormwater management planning and design manual, largely influenced by the large number of small- and medium- draft final report. Ontario Ministry of the Environment (MOE), magnitude rainfall events. It is thought that these events of Toronto, Ont. smaller magnitude and higher frequency do most of the work Mukherjee, D., and Mansour, N. 1991. A bivariate stochastic approach in forming a water channel and are therefore most significant to estimate reliability of a pumped storage reservoir. Journal of from an erosion standpoint. Hydrology, 125: 293–310. The developed method for predicting these higher frequency Mukherjee, D., and Mansour, N. 1996. Estimation of flood forecasting events can be very useful when developing a watershed or sub- errors and flow-duration joint probabilities of exceedance. ASCE watershed plan at the screening or planning level. The closed- Journal of Hydraulic Engineering, 122(3): 130–140. form mathematical solutions are easy to use, requiring few input parameters, making them attractive to the practicing engineer when compared to the computational burden often presented List of symbols by the more conventional approach, continuous simulation. d portion of a storm event when critical discharge rate is exceeded (h) References do arbitrary value of d (h) E(d) expected value of d Adams, B.J., and Papa, F. 2000. Urban stormwater management plan- Ep erosion potential ning with analytical probabilistic models. John Wiley and Sons, fc ultimate infiltration capacity of a soil (mm/h) Inc., New York. fV(v), fT(t) probability distributions of rainfall volume and in- Benjamin, J.R., and Cornell, C.A. 1970. Probability, statistics and de- tensity cision for civil engineers. McGraw-Hill, New York. fV,T(v, t) joint probability density function of rainfall vol- Chan, S.-O., and Bras, R.L. 1979. Urban stormwater management: ume and intensity distribution of flood volumes. Water Resources Research, 15(2): fX(x), fY (y) probability density functions of random variables 371–382. X and Y Cooke, R.U., and Doornkamp, J.C. 1990. Geomorphology in environ- fX,Y(x, y) joint probability density function of random vari- mental management. Clarendon Press, Oxford, UK. ables X and Y Dillon Consulting Engineers and Planners. 1982 Vulnerability of natu- FD(d) cumulative distribution function of D ral watercourses to erosion due to different flowrates. Report to the FX(x), FY (y) cumulative distribution functions of X and Y

© 2006 NRC Canada 318 Can. J. Civ. Eng. Vol. 33, 2006

g(x) functional relationship Siw initial soil wetting infiltration volume (mm) h fraction of impervious area of an urban catchment t rainfall event duration (h) IP1,IP2,IP3 impulse integration regions 1, 2, and 3 t ∗∗ intersection of lines 2, 4, and 5 ¯ P1, P2 integration regions 1 and 2 t mean rainfall event duration from an historical Qc critical or threshold discharge rate (mm/h) rainfall record (h) Qp peak discharge rate of a runoff event (mm/h) tc catchment time of concentration (h) Rz region in the x–y plane where g(x,y) ≤ z TR return period (years) Sd area-weighted average depression storage of a up a given peak channel velocity (m/s) catchment = hSdt + (1 − h)Sil (mm) v rainfall event volume (mm) Sdi depression storage of impervious portion of a v¯ mean rainfall event volume from an historical rain- catchment (mm) fall record (mm) Sdd difference between the pervious portion initial vr runoff event volume (mm) losses and the impervious portion depression stor- X, Y, Z random variables age = Sil − Sdi (mm) λ parameter of the exponential probability density ¯ −1 Sdp depression storage of the pervious portion of a function for T = 1/t(h ) catchment (mm) θ average annual number of rainfall events Sil initial losses of the pervious portion of a catchment ζ parameter of the exponential probability density −1 = Siw + Sdp (mm) function for V = 1/v¯ (mm )

© 2006 NRC Canada