Draft Basic Assessment Report

Proposed Development Of A Timeshare Resort Located On Portion 101 Tenbosch Near The Crocodile River, Province

Prepared by:

Contents Acronyms and abbreviations ...... iv GLOSSARY OF TERMS ...... iv SECTION A: ACTIVITY INFORMATION ...... 1 1. PROJECT DESCRIPTION ...... 1 2. FEASIBLE AND REASONABLE ALTERNATIVES ...... 2 3. SITE ACCESS...... 5 4. LOCALITY MAP ...... 5 5. LAYOUT/ ROUTE PLAN ...... 6 6. SENSITIVITY MAP ...... 6 7. SITE PHOTOGRAPHS ...... 6 8. FACILITY ILLUSTRATION ...... 6 9. ACTIVITY MOTIVATION ...... 6 10. APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES ...... 7 11. WASTE AND EFFLUENT ...... 12 12. WATER USE ...... 12 SECTION B: SITE/AREA/PROPERTY DESCRIPTION ...... 13 13. GROUNDWATER, SOIL AND GEOLOGICAL STABILITY OF THE SITE ...... 13 14. GROUNDCOVER ...... 13 15. SURFACE WATER ...... 14 16. LAND USE CHARACTER OF SURROUNDING AREA ...... 14 17. CULTURAL/HISTORICAL FEATURES ...... 15 18. SOCIO-ECONOMIC CHARACTER ...... 15 19. BIODIVERSITY ...... 15 20. VISUAL ...... 22 SECTION C: PUBLIC PARTICIPATION ...... 22 1. ADVERTISEMENT AND NOTICE...... 22 2. DETERMINATION OF APPROPRIATE MEASURES...... 23 3. ISSUES RAISED BY INTERESTED AND AFFECTED PARTIES ...... 23 4. COMMENTS AND RESPONSE REPORT ...... 23 5. AUTHORITY PARTICIPATION ...... 24 6. CONSULTATION WITH OTHER STAKEHOLDERS ...... 24 SECTION D: IMPACT ASSESSMENT ...... 24 1. IMPACTS THAT MAY RESULT FROM THE PLANNING AND DESIGN, CONSTRUCTION, OPERATIONAL, DECOMMISSIONING AND CLOSURE PHASES AS WELL AS PROPOSED MANAGEMENT OF IDENTIFIED IMPACTS AND PROPOSED MITIGATION MEASURES ...... 24 2. ENVIRONMENTAL IMPACT STATEMENT ...... 40 SECTION E. RECOMMENDATION OF PRACTITIONER ...... 43 SECTION F: APPENDIXES ...... 45

List of Appendices Appendix A: Maps A.1: Locality A.2.1: Preferred Alternative- Layout A.2.2: Alternative 2- Layout A.3.1: Preferred Alternative- Sensitivity A.3.2: Alternative 2- Sensitivity

Appendix B: Photographs

PROPOSED TENBOSCH TIMESHARE RESORT I

Appendix C: Facility illustration(s)

Appendix D: Specialist reports D.1: Geotechnical Report D.2: Riparian and Wetland Report D.3: Heritage Report D.4: Ecology Report D.5: Visual Report

Appendix E: Public Participation

Appendix F: Impact Assessment

Appendix G: Environmental Management Programme (EMPr)

Appendix H: Details of EAP and expertise

Appendix I: Specialist’s declaration of interest

Appendix J: Additional Information

PROPOSED TENBOSCH TIMESHARE RESORT II

Foreword This report constitutes the Draft Basic Assessment Report, and has been circulated digitally for Stakeholder Comment on 8 November 2016. NuLeaf Planning and Environmental would like to thank all Stakeholders for their participation and input into this process to date, and hereby invite Stakeholders to review this draft report and to provide feedback, input, concerns and comments. All written comments received, including NuLeaf’s response to each, will be captured in a Comments and Responses Register, which will be made available to all I&AP’s and included in the Final Basic Assessment Report for submission to the Mpumalanga Department of Agriculture, Rural Development, Land and Environmental Affairs. All comments on the Draft BAR must be in writing and must reach NuLeaf by no later than close of business on 8 December 2016. Please mark all comments for the attention of: Bryony van Niekerk Email: [email protected] Tel: (012) 753 5792 Fax: (086) 571 6292

PROPOSED TENBOSCH TIMESHARE RESORT III

Acronyms and abbreviations

BA: Basic Assessment BAR: Basic Assessment Report CBA: Critical Biodiversity Area CMP: Construction Management Plan DARDLEA: Mpumalanga Department of Agriculture, Rural Development, Land and Environmental Affairs DWS: South African National Department of Water and Sanitation EA: Environmental Authorisation ECO: Environmental Control Officer EIA: Environmental Impact Assessment EMPr: Environmental Management Programme EMS: Environmental Management System EO: Environmental Officer I&AP: Interested and Affected Party IDP: Integrated Development Plan IEM: Integrated Environmental Management KNP Kruger National Park LED: Local Economic Development MTPA: Mpumalanga Tourism and Parks Agency NEMA: National Environmental Management Act, Act No. 107 of 1998 NEMPAA: National Environmental Management: Protected Areas Act, Act No. 57 of 2003 NPAES: National Protected Area Expansion strategy OMP: Operational Management Plan SAHRA: South African Heritage Resources Agency

GLOSSARY OF TERMS

Alien Vegetation: Alien vegetation defined as undesirable growth which shall include, but not be limited to all declared category 1 and 2 listed invader as set out in the Conservation of Agricultural Resources Act (CARA) regulations.

Alien Species: A plant or animal species introduced from elsewhere: neither endemic nor indigenous.

Alternatives: In relation to a proposed activity, means different means of meeting the general purpose and requirements of the activity, which may include alternatives to: (a)The property on which or location where it is proposed to undertake the activity; (b) The type of activity to be undertaken; (c) The design or layout of activity; (d) The technology to be used in the activity; and (e) The operational aspects of the activity.

Applicant: Any person who applies for an authorization to undertake an activity or to cause such activity to be undertaken as contemplated in the National Environmental Management Act (Act No. 107 of 1998), as amended and the Environmental Impact Assessment Regulations, 2010.

PROPOSED TENBOSCH TIMESHARE RESORT IV

Buffer zone: Is a collar of land that filters out inappropriate influences from surrounding activities, also known as edge effects, including the effects of invasive plant and animal species, physical damage and soil compaction caused by trampling and harvesting, abiotic habitat alterations and pollution. Buffer zones can also provide more landscape needed for ecological processes, such as fire.

Construction Activity: Any action taken by the Contractor, his subcontractors, suppliers or personnel during the construction process.

Ecology: The study of the inter relationships between organisms and their environments.

Environment: All physical, chemical and biological factors and conditions that influence an object and/or organism.

Environmental Impact: An Impact or Environmental Impact is the degree of change to the environment, whether desirable or undesirable, that will result from the effect of a defined activity. An Impact may be the direct or indirect consequence of the activity and may be simple or cumulative in nature.

Environmental Impact Assessment: Assessment of the effects of a development on the environment.

Environmental Management Programme: A legally binding working document, which stipulates environmental and socio-economic mitigation measures that, must be implemented by several responsible parties throughout the duration of the proposed project.

Indigenous: Means a species that occurs, or has historically occurred, naturally in a free state within the borders of . Species that have been introduced to South Africa as a result of human activity are excluded (South Africa (Republic) National Environmental Management: Biodiversity Act, 2004: Chapter 1).

Interested and Affected Party: Any person, group of persons or organization interested in or affected by an activity contemplated in an application, or any organ of state that may have jurisdiction over any aspect of the activity.

Invasive vegetation: Plant species that show the potential to occupy in unnatural numbers, any disturbed area, including pioneer species.

Mitigate: The implementation of practical measures to reduce adverse impacts Public Participation Process: is a process in which potential interested and affected parties are given an opportunity to comment on, or raise issues relevant to, specific matters.

Public Participation: The legislated process contemplated in terms GN R543, in which all potential interested and affected parties are informed of the proposed project and afforded the opportunity to input, comment and object. Specific requirements are listed in terms of advertising and making draft reports available for comment.

Road Reserve: The road reserve is a corridor of land, defined by co-ordinates and proclamation, within which the road, including access intersections or

PROPOSED TENBOSCH TIMESHARE RESORT V

interchanges, is situated. A road reserve may, or may not, be bounded by a fence.

Road Width: The area within the Road Reserve including all areas beyond the Road Reserve that are affected by the continuous presence of the road i.e. the verge.

Red data plant species: Are fauna and flora species that require environmental protection based on the World Conservation Union (IUCN) categories and criteria.

RoD: Record of Decision pertaining to the Application for Environmental Authorisation issued by the Competent Authority. The RoD is legally binding on the Applicant and may contain a positive or negative decision on the Application as well as conditions and provisions for each.

Soil Compaction: Mechanically increasing the density of the soil, vehicle passage or any other type of loading. Wet soils compact easier than moist or dry soils.

Species: Means a kind of animal, plant or other organism that does not normally interbreed with individuals of another kind. The term “species” include any sub-species, cultivar, variety, geographic race, strain, hybrid or geographically separate population (South Africa [Republic] National Environmental Management: Biodiversity Act, 2004: Chapter 1).

The Contractor: The contractor, as the developers agent on site, is bound by the ROD and EMP conditions through his/her contract with the developer, and is responsible for ensuring that conditions of the EMP and ROD are strictly adhered to at all times. The contractor must comply with all orders (whether verbal or written) given by the ECO, project manager or site agent in terms of the EMPr.

The Developer: Remains ultimately responsible for ensuring that the development is implemented according to the requirements of the EMP and the conditions of the Environmental Decision throughout all phases of the project.

The Environmental Control Officer (ECO): The ECO is appointed by the developer as an independent monitor of the implementation of the EMP i.e. independent of the developer and contractor.

The Environmental Officer (EO): The Contractor shall submit to the Site Agent a nominated representative of the Contractor as an EO to assist with day to day monitoring of the construction activities for the contract.

Vegetation: Is a collective word for occurring in an area.

Vulnerable: A taxon is ‘Vulnerable’ when it is not ‘Critically Endangered’ or ‘Endangered’ but is facing a high risk of extinction in the wild in the medium term future.

Watercourse: A river or spring; a natural channel in which water flows regularly or intermittently; a wetland, lake or dam into which, or from which, water flows; and any collection of water which the Minister may by notice in the Government Gazette, declare to be a watercourse, and a reference to a

PROPOSED TENBOSCH TIMESHARE RESORT VI

watercourse includes, where relevant, its bed and banks” (South Africa [Republic] National Water Act, 1998).

PROPOSED TENBOSCH TIMESHARE RESORT VII

Executive Summary SECTION A: ACTIVITY INFORMATION Section A details all of the activities that will be undertaken during the development of the Proposes Timeshare Resort on Tenbosch Farm, as well as, the identification of reasonable and feasible alternatives, activity motivation and waste management. Project Description The proposed development entails the construction of tourist accommodation in the form of a timeshare resort within the Portion 101 Tenbosch Farm, 162 JU adjacent to the Crocodile River. The timeshare will comprise between 60-100 chalets and a central complex inclusive of recreational facilities. A third of the existing water rights from the river will be converted to be used for the development. All associated civil infrastructure (water, electricity, waste treatment) will be included, as well as, internal access tracks. Key staff will be housed on site while the remainder of the staff will be housed off site. Feasible Alternatives - Site Alternative Only one site alternative is under consideration for the timeshare resort. The preferred site is a ‘brownfields’ site which used to function as a citrus orchard. Majority of these citrus trees have been cleared, though there are other large trees on site and along the riverbank. The areas where the citrus orchards have been cleared will be replanted as agriculture. The site is situated adjacent to the Kruger National Park boundary on the southern bank of the Crocodile River. Agricultural, commercial and residential developments lie to the west, south and east of the site. Services (water, electricity and sewage) will be obtained by extending the existing infrastructure at the farmhouses located on site. - Layout Alternatives Two layout alternatives are under consideration for the proposed timeshare resort. Preferred Alternative: Alternative 1 The layout of the timeshare resort is designed to capitalize on the views provided by the Crocodile River and KNP to the north. The chalets will be grouped in pairs, 1 storey in height and constructed out of brick and mortar. Majority of the chalets will be located near the northern boundary of the site overlooking the Crocodile River and the Kruger National Park beyond. The remainder of the chalets will be clustered around two central complexes located in the east and west. The western central complex (an existing farmhouse) will consist of a communal recreational area with a swimming pool and a tennis court, while the eastern complex will consist of a swimming pool. This Preferred Layout respects all recommended buffer areas, the flood line along the Crocodile River and all riparian buffers along the watercourses located on site. Existing drainage line crossings have been utilized where possible. Layout Alternative: Alternative 2 The Layout Alternative is very similar to the layout of the Preferred Alternative, with the exception of the placement of the chalets in the eastern portion of the site. In this layout, approximately 12 of the chalets in the north eastern corner are located within the riparian buffer which is a high sensitivity area and no-go zone for development.

PROPOSED TENBOSCH TIMESHARE RESORT VIII

- Technology Alternatives Two technology alternatives are under consideration for the proposed timeshare resort. Preferred Alternative: Alternative 1 Raw water will be sourced from the conversion of existing water rights from the Crocodile River Irrigation System listed for 35ha and stored in a 350 kl storage tank. The water will then be distributed to each unit within the development via a water distribution network. A sewage treatment plant will be constructed at a suitable position within the development site and all the sewage from the reticulated units within the development will be treated at this treatment plant. Outflow will be used for irrigation purposes. The key staff accommodation will be provided with onsite septic tank sewage disposal systems which will be located outside the 1:100 year flood plains. The treatment processes for the plant will include screening, anaerobic digestion, trickling filter, settler and chlorine contact tank. Electricity supply will be via the Eskom lines on site whereby an underground reticulation system will be installed. Technology Alternative: Alternative 3 All service aspects will be as per the Preferred Alternative, with the exception that power will not be supplied by Eskom, but via solar power. Solar panels will be roof mounted on the roofs of the units and recreation areas. Waste and Effluent Solid waste will be separated into non-recyclables and recyclables and stored separately for collection. Non- recyclables will be collected and stored in fenced ‘scavenger proof’ areas at a holding facility at the entrance gate to the development site. The waste will then be collected by the Resort Management/Service provider and transported to the Nkomazi Municipality’s approved landfill site at Steenbok.

A water treatment plant will be constructed which will be constructed at a suitable position on the development area. Collector sewer lines will be constructed to convey the sewage to two sewage pump stations. Sewer rising mains will be provided to convey the wastewater to the wastewater treatment plant. Septic tanks and soakaways may be required for key staff and administration facilities. Effluent emanating from the septic tank at the units will be dissipated via a soak away by means of properly designed and installed soak away systems.

SECTION B: SITE/AREA/PROPERTY DESCRIPTION This section provides a detailed description of the proposed development in terms of the groundwater, soil, biodiversity, visual and cultural/historical features found on site. Groundwater and soil The study area is underlain by transported sandy and gravelly soils overlying basalt bedrock belonging to the Letaba Formation, Lebombo Group, Karoo Supergroup.

Isolated outcrops of very hard rock basalt are present in the central, northern portion of the property which has been apportioned into three prominent geotechnical soil zones, Soil Zones “A” to “C.”

Soil Zone A materials cover the majority of the site, Soil Zone B materials cover the central portion of the site and Soil Zone C occupies the two low-lying areas and drainage features including the dam located in the east. The timeshare units will be located along the northern boundary of the proposed site where Soil Zones A and B are found.

PROPOSED TENBOSCH TIMESHARE RESORT IX

Groundcover The study area is situated in Tshokwane - Hlane Basalt Lowveld within the Lowveld Bioregion in the Savanna Biome. This vegetation type is considered well protected and has a conservation status of Least Concern (Lötter et al., 2014). This is largely due to much of this community occurring within the Kruger National Park. It is not listed as a Threatened Ecosystem (Notice 1002 of Government Gazette 34809, 9 December 2011).

Most of the terrestrial ecosystems within the study area on Tenbosch is classified as Heavily or Moderately Modified Areas by the Mpumalanga Biodiversity Sector Plan (MBSP). The scattered untransformed sections are classified as Other Natural Areas.

The entire study area is also situated within the Ecological Support Areas (ESA): Protected Area Buffers. The wetland vegetation around the dam is classified as ESA: Wetlands in the MBSP. Both drainage lines in the study area are classified as ESA: Important Sub catchments, Fish Support Areas.

The study area is not situated in any of southern Africa’s floristic centres of endemism, which are areas that have an unusually high number of plants unique to that area (Van Wyk & Smith, 2001).

Biodiversity A specialist terrestrial ecology assessment was undertaken by ECOREX Consulting Ecologists CC in May 2016.

- Flora A total of 140 plant species was recorded within the study area during fieldwork. Three of these are protected under the National Forests Act (No. 30 of 1998): violacea, Combretum imberbe and Sclerocarya birrea subsp. caffra, and two by the Mpumalanga Nature Conservation Act (No.10 of 1998): Aloe marlothii and Crinum stuhlmannii. Dalbergia melanoxylon is assessed as Near Threatened and Crinum stuhlmannii as Declining.

Three untransformed vegetation communities were identified within the study area on the basis of distinctive vegetation structure (grassland, woodland, thicket, etc.), floristic composition (dominant and diagnostic species) and position in the landscape (mid-slopes, terrace, crest, etc.). Transformed and degraded areas make up approximately 30 ha, or 75 % of the study area. Most of the transformed and degraded land is covered by citrus orchards, various buildings, a short golf course and old lands. The untransformed vegetation communities are Ficus sycomorus - Hypoestes forskaolii Disturbed Riparian Forest, Acacia nigrescens – Panicum maximum Disturbed Closed Woodland, and Phragmites australis – Typha capensis Wetland.

- Fauna Situated in the savanna biome immediately south of the Kruger National Park (KNP), the area has very high mammal diversity, relatively low numbers of endemics and a moderate number of Red Data species. The study area is mostly transformed (75 %) and little habitat remains, especially for larger mammals. However, it is located on the boundary fence of the KNP and animals can and do wander in through gates or the fence or via the stream channel in the east. Evidence of this was found in a small tract of woodland in the west where old Hippopotamus (Hippopotamus amphibius) faeces were located. An estimated 32 conservation-important mammals potentially occur within the project area, although most of these are more likely in adjacent conservation land than in the project area. Several bat species are highly likely to occur overhead, such as Geoffroy’s Horseshoe Bat (Rhinolophus clivosus), but these species are only likely to feed over the site because of the shortage of suitable roosting sites.

- Birds

PROPOSED TENBOSCH TIMESHARE RESORT X

Eighty-eight bird species were confirmed to occur in the study area during fieldwork. Thirty-six species were recorded from Riparian Forest, 26 from the Wetland and 13 from Transformed. Three broad assemblages or species-habitat associations were identified, namely Forest Assemblage, Woodland Assemblage and Wetland Assemblage. A pair of Martial Eagles (Polemaetus bellicosus) were observed flying over Closed Woodland in the study area and not actually utilising the habitat within, although it may occasionally hunt over the study area. No suitable breeding habitat is present on Tenbosch. - Reptiles and Frogs

The Lowveld and foothills of far eastern Mpumalanga support a high diversity of reptile species with 102 species already recorded from the degree grid 2531 . Forty-seven species of reptiles have been recorded from the QDS 2531 BD, in which Tenbosch is situated. Of the potentially occurring species, only two conservation-important reptiles potentially occur. One of these has been assessed as Vulnerable: Nile Crocodile (Crocodylus niloticus), which is also protected under NEMBA ToPS. Southern African Python (Python natalensis) is protected under the National Environmental Management: Biodiversity Act (No.10 of 2004) and was confirmed during fieldwork from Riparian Forest immediately north of the dam. No frogs were recorded during the assessment although summer fieldwork with nocturnal surveys will result in a fair number of species. Riparian Ecology A specialist wetland/riparian survey was undertaken by Wet-Earth Eco-Specs to identify and delineate wetlands and riparian area, as well as, determine the present ecological state (PES) and the ecological importance and sensitivity (EIS). Three (3) water courses were identified and can be described as riverine areas. There are wetland areas which form part of these riparian areas. These wetland areas occur around the dam and upstream of road crossings and weirs. These water courses have been named T01, T02 and T03 for ease of discussion.

- T01 Water course T01 is the dam located in the east of the proposed site. The riparian zone extends upstream from the edge of the property and downstream where it joins the Crocodile River. The Riparian Index of Habitat Integrity (RIHI) is a C/D (57.7). this is mainly owing to the road crossings, orchard footprint which has extended into the riparian areas, the dam which destroyed approximately 71 % of the original riparian area, a weir in an active channel and an extensive presence of exotic vegetation. The PES is D/E and the PES Ecostatus is D/E (largely modified/ seriously modified).

- T02 Watercourse T02 is the drainage line located in the western portion of the site. The riparian zone extends from the edge of the property upstream to where it joins with the Crocodile River downstream. The RIHI is a D (53.8 %). This is due to roads traversing the riparian zone, dumping, agriculture, vegetation clearing and water quality issues. PES is D while the PES Ecostatus is also a D (53.8%) (largely modified).

- T03 Watercourse T03 is the Crocodile River which forms the northern border of the proposed site. The RIHI is a C/D (57.9%) with the main impacts being flood events. Grazing and trampling, water abstraction and presence of exotic species. PES is C/D and the PES Ecostatus is a C/D (57.9%).

Visual

PROPOSED TENBOSCH TIMESHARE RESORT XI

A visual impact assessment was undertaken by NuLeaf Planning and Environmental in order to determine the possible visual impact of the proposed timeshare resort located on Tenbosch Farm. The visual quality of the broader study area is high, generally as a result of the lack of development and the large areas given over to conservation within the region. There is no evidence of widespread erosion or natural degradation, and development, where this occurs, is domestic in scale. Viewer incidence is expected to be the highest along the roads surrounding the proposed development area and the properties directly adjacent to the site. Second to these are homesteads in close proximity to the proposed site. Tourists using the roads, residents of the area and tourist accommodation are considered the most sensitive to visual intrusion as they will be exposed to visual intrusion during their rest and relaxation times. The overall visual absorption capacity (VAC) is low-medium. SECTION C: PUBLIC PARTICIPATION A list of interested and affected parties (I&AP’s), as well as, compliance authorities was compiled inclusive of Local and District Municipalities, local landowners and environmental organizations.

Written notification of the proposed development, including a background information document, was sent to all identified I&AP’s and Compliance Authorities on 13 May 2016.

A printed advertisement was placed in the Lowvelder, a local publication, on the 13 May 2016.

Site notices were placed at the entrances to the affected property, Crocodile Bridge Gate Reception, and the local Spar in Komatipoort on 10 May 2016.

SECTION D: IMPACT ASSESSMENT Majority of the terrestrial ecosystems of Tenbosch Farm lie within areas classified as Heavily/Moderately Modified Areas as per the MBSP. The remaining untransformed sections of the farm are classified as Other Natural Areas. Tenbosch also does not lie within a Threatened Ecosystem.

- Preferred Alternative: Alternative 1

The Preferred Alternative is deemed to have the lowest environmental impact of all the alternatives considered in terms of the significance of the impacts during both the construction and operational phases.

The construction impacts, if effectively and sufficiently managed according to the mitigation measures proposed in this report, specialist reports and the draft environmental management programme (EMPr), will mostly be of low significance, post mitigation. It should be noted that a moderate post mitigation significance rating is anticipated in terms of the loss of faunal habitat. This is mainly due to the placement of infrastructure in areas of high sensitivity. No post mitigation impacts of high significance are expected.

Operational impacts can be similarly mitigated and residual impacts are expected to be of low significance overall. However, it should be noted that post mitigation significance is anticipated to be moderate in terms of air pollution due to emissions from increase number of vehicles to the area and the operational cost of services pertaining to the use of Eskom power. No post mitigation impacts of high significance are expected.

Positive impacts, which will be applicable to all alternatives, include job creation and employment opportunities for both the construction and operational phases, skills transfer and development. Diversifying the tourism offerings within the region will also have an overall positive impact.

PROPOSED TENBOSCH TIMESHARE RESORT XII

With the above in mind, it is recommended that the Preferred Alternative be supported on the condition that all mitigation measures mentioned in this report, the specialist studies and the draft EMPr are implemented and adhered to throughout the project lifecycle. No fatal flaws are evident and the design approach and layout is deemed to be environmentally responsible. Additionally, the burying of the power cable will help to minimize the visual impact on the adjacent KNP and other tourism accommodation facilities within the area.

- Layout Alternative: Alternative 2

The Layout Alternative will result in slightly higher significance ratings for aspects such as hydrology and flora, particularly during the construction phase. This is owning to the placement of a number of chalets and section of the internal access roads being located within the riparian buffer which has a high sensitivity rating.

Post mitigation significance for the construction phase will be mostly low. However, moderate post mitigation significance ratings are expected for hydrology due to certain chalets being located just outside of the flood line of the Crocodile River, the disturbance of sensitive habitats due to the placement of a number of chalets within the riparian buffer and the cumulative impact of the disturbance of sensitive habitats.

The operational impacts will be similar to those of the Preferred Alternative, with post mitigation impacts being predominately of low significance. Slightly elevated post mitigation significance, as compared to the Preferred Alternative, is expected for the disturbance of sensitive habitats. Additionally, moderate post mitigation significance rating is anticipated for the cumulative disturbance/ destruction of sensitive habitats.

The placement of a number of chalets and a portion of the internal access road in the buffer of the riparian habitat is not environmentally responsible a this area has a high sensitivity and is declared a no development zone. In spite of the application of mitigation measures, certain impacts- particularly relating to ground and surface water and disturbance of sensitive habitats- will be of a slightly higher significance than in the Preferred Alternative. In light of this, it is recommended that the Layout Alternative is not supported.

- Technology Alternative: Alternative 3

The Technology Alternative will result in similar low post mitigation significance ratings as that of the Preferred Alternative for the construction phase. Slightly lower impacts are also anticipated for the loss of vegetation due to the fact that power will be supplied by solar panels which is less invasive in nature than the burying of cables.

The operational impacts will be similar to those of the Preferred Alternative, with residual impacts being mostly of low significance. Slightly elevated post mitigation impacts, as compared to the Preferred Alternative, is anticipated for soil erosion owing to the increase in hard surfaces and storm water runoff from the solar panels.

Solar panels are prohibitive from a capital cost perspective and are not considered ideal for this project of this size. Additionally, the potential visual impact on the KNP in terms of glare could be impact on KNP tourist visitor experience, particularly at certain times of the day.

With the above in mind, it is recommended that the Technology Alternative not be supported due to the potential visual impact on the KNP visitors.

- No-go Alternative

The No-go Alternative implies that the proposed development of the timeshare resort on Tenbosch Farm 101 will not take place. In this scenario receiving environment will not be negatively impacted upon in any manner, particularly with regard to biodiversity and surface water.

It should be noted that while no negative impacts will be incurred, the same can be said for positive impacts such as, the creation of employment and job opportunities, skills transfer and development.

PROPOSED TENBOSCH TIMESHARE RESORT XIII

SECTION E: RECOMMENDATION OF PRACTITIONER

As discussed in the preceding section, all significant negative impacts can be successfully mitigated and managed to acceptable levels (moderate to low) during the entire project lifecycle. All mitigation measures as detailed n this BAR, the attached specialist reports and the draft EMPr must be implemented and adhered to for all phases of the project i.e. planning, construction and operation. In addition, the following specific recommendations apply: Planning and Design

 A minimum buffer zone of 16 m should be adhered to around the dam located in the east of the site.  A minimum buffer zone of 15 m should be adhered to around the drainage line located in the west of the site.  A minimum buffer zone of 67 m should be adhered to around the Crocodile River located to the north of the site.  All activities should stay out of the 1:100 year flood line area.  The sensitivity map must be used as a decision making tool to guide the layout design. Development on areas of high environmental sensitivity must be avoided.  If infrastructure is planned within any natural vegetation, the areas should be checked by a suitably experienced botanist to locate all conservation-important species. These plants should be marked and the relevant permits applied for before removal and translocated to nearby suitable habitat prior to vegetation being cleared.  A follow-up survey in late summer (February / March) should take place to search for the succulent Aloe komatiensis. This species is listed as Endangered and is confirmed from just outside the study area. This is a small aloe which may have been overlooked during fieldwork and a search during its flowering period will make it far more visible.  The trees Sclerocarya birrea subsp. caffra, Combretum imberbe and Philenoptera violacea are nationally protected and a permit would be required to destroy them.  Aloe marlothii and Crinum stuhlmannii are protected under provincial legislation and need to be rescued and relocated to adjacent suitable habitat if they are found to be within the development footprint. A permit to move these plants would also be required Construction

 A suitably experienced botanist should be present on site at the time of pegging so as to identify sensitive plants or habitats.  The nationally protected trees to be protected (Sclerocarya birrea subsp. cafra, Combretum imberbe and Philenoptera violacea), Aloe marlothii and Crinum stuhlmannii protected under provincial legislation and any other identified subsequent to the initial survey, should be clearly marked prior to construction.  No natural watercourse is to be used for the cleaning of tools or any other apparatus. This includes for purposes of bathing, or the washing of clothes etc.  No construction camps should be allowed in or within 20 m of a riparian areas.  No stockpile areas should be located in or within 20 m of a riparian areas.  Construction should preferably take place during the low flow/winter months in order to minimize the risk of sediment and debris being washed into riparian areas.  Stockpiling of soil and of supplies for the construction camps must take place clearly away (at least 20 m where possible) from the edge of riparian areas to prevent soil being washed into the riparian areas habitat.

PROPOSED TENBOSCH TIMESHARE RESORT XIV

 Developers should implement an alien plant control program to combat the infestation present around the wetlands. This program should include regular inspections and follow-ups. Operation

 Regulate and control movement over the site. Personnel, vehicles and equipment to move along designated routes.  Ensure that all conserved species and specimens are suitably protected for the duration of the operational phase.  No protected trees or plants may be removed without the relevant permits from the local authority.  Maintenance workers and guests may not trample natural vegetation and work should be restricted to dedicated roads, paths and gardens within the development footprint.  The operator must develop a management and monitoring programme for alien and invasive species detailing basic ID information, actions to prevent the establishment of invasive plants and methods of removal of site during construction.  No unauthorised access is permitted to buffer areas or any natural areas outside of the facility footprint

PROPOSED TENBOSCH TIMESHARE RESORT XV

SECTION A: ACTIVITY INFORMATION 1. PROJECT DESCRIPTION

1.1. Development Components The proposed development entails the construction of tourist accommodation in the form of a timeshare resort within the Portion 101 Tenbosch Farm, 162 JU adjacent to the Crocodile River. The timeshare will comprise between 60-100 chalets and a central complex inclusive of recreational facilities. A third of the existing water rights from the river will be converted to be used for the development. All associated civil infrastructure (water, electricity, waste treatment) will be included, as well as, internal access tracks. Key staff will be housed on site while the remainder of the staff will be housed off site. Refer to Appendix A. The areas where the citrus orchards were cleared will be replanted as agriculture. The total footprint of the timeshare resort will not exceed 20 hectares. The proposed timeshare resort will consist of the following:

 60-100 chalets  A central complex  2x swimming pools  Tennis court  Club house  Recreation area  Restaurant  Viewpoints/ bird hides  Parking area  Staff accommodation  Maintenance workshop  Access control point/ reception

1.2. Detailed description of the listed activities associated with the project as applied for

Government Describe the portion of the development as per the Describe the relevant Basic Assessment Activity in Notice R983 project description that relates to the applicable writing as per Listing Notice 1 (GN No. R983) Activity No. listed activity 9 (i) (ii) The development of infrastructure exceeding 1000 m in Potable water and storm water infrastructure may length for the bulk transportation of water or storm exceed 1000m in length and may have an internal water with (i) internal diameter of 0,36 m or more or (ii) diameter of 0,36m, depending on the final storm water peak throughput of 120 litres per second or more. design. 10 (i) (ii) The development and related operation of Sewage reticulation infrastructure may exceed 1000m in infrastructure exceeding 1000 m in length for the bulk length and may have an internal diameter of 0,36m, transportation of sewage, effluent, process water, depending on the final storm water design. return water, industrial discharge or slimes with (i) internal diameter of 0,36 m or more or (ii) peak throughput of 120 liters per second or more. 12 (vi) (x) The development of (vi) bulk storm water outlet Depending on the storm water design, outlets may be (xii) (c) structures exceeding 100 square meters in size, (x) developed within 32m of the Crocodile River or dam buildings exceeding 100 square meters in size, (xii) located within the site. Buildings or infrastructure may infrastructure or structures with a physical footprint of be constructed within 32 m of the drainage lines or dam. 100 square meters in size or more where such development occurs within 32 meters of a watercourse. 27 The clearance of an area of 1 hectare or more, but less The total cleared footprint of indigenous vegetation is than 20 hectares of indigenous vegetation. not expected to exceed 20 Ha.

PROPOSED TENBOSCH TIMESHARE RESORT 1

Government Describe the portion of the development as per the Describe the relevant Basic Assessment Activity in Notice R985 project description that relates to the applicable writing as per Listing Notice 3 (GN No. R985) Activity No: listed activity 2 (a) (iii) (ff) The development of reservoirs for bulk water supply Water storage for the timeshare resort may have a with a capacity of more than 250 cubic meters in (a) capacity of more than 250 cubic meters. The Kruger Mpumalanga (iii) outside urban areas within (ff) 10 Km National Park is located less than 1 Km from the from a national park identified in terms of NEMPAA. proposed site. 4 (a)(ii)(gg) The development of a road wider than 4 meters with a The internal access tracks may exceed 4 meters in reserve less than 13,5 m in (a) Mpumalanga (ii) outside length. The Kruger National Park is located less than 1 urban areas within (gg) areas 10 Km from national Km from the proposed site. parks identified in terms of NEMPAA. 6 (a) (ii) (gg) The development of resorts, lodges, hotels, and The proposed development will comprise of between (ii) tourism or hospitality facilities that sleeps 15 people or 60-100 chalets and will be located within 100 meters of more in (a) Mpumalanga (ii) outside urban areas in (gg) the Crocodile River. The Kruger National Park is located areas within 10 Km from national park as identified in less than 1 Km from the proposed site. terms if NEMPAA and (ii) areas within 100 meters from the edge of a watercourse. 12 (c) (iv) The clearance of an area of 300 square meters or more The total footprint will exceed 300 square meters. of indigenous vegetation in (c) Mpumalanga (iv) on land zoned open space or had an equivalent zoning. 14 (vi) (x) The development of (vi) bulk storm water outlet Buildings and/or infrastructure may be within 32 m of (xii) (c); (a) structures exceeding 10 square meters in size, (x) the Crocodile River or other watercourse. The Kruger (ii) (hh) buildings exceeding 10 square meters in size, (xii) National Park is located less than 1 Km from the infrastructure or structures with a physical footprint of proposed site. 10 square meters or more, where such development occurs within (c) 32 meters or a watercourse; in (a) Mpumalanga (ii) outside urban areas in (hh) areas within 10 Km of a national park as identified in terms of NEMPAA. 18 (a) (ii) The widening of a road by more than 4 meters, or the Access roads may be lengthened by more than 1 Km. (gg) (ii) lengthening of a road by more than 1 Km in (a) The Kruger National Park is located less than 1 Km Mpumalanga (ii) outside urban areas in (gg) areas from the proposed site. within 10 Km of a national park identified in terms of NEMPAA and (ii) within 100 meters of a watercourse.

2. FEASIBLE AND REASONABLE ALTERNATIVES

2.1. Site Alternatives Only one site alternative is under consideration for the timeshare resort. The preferred site is a ‘brownfields’ site which used to function as a citrus orchard. Majority of these citrus trees have been cleared, though there are other large trees on site and along the riverbank. The areas where the citrus orchards have been cleared will be replanted as agriculture. The site is situated adjacent to the Kruger National Park boundary on the southern bank of the Crocodile River. Agricultural, commercial and residential developments lie to the west, south and east of the site. Services (water, electricity and sewage) will be obtained by extending and upgrading the existing infrastructure at the farmhouses located on site. Advantages of this site for the proposed development include the following:

 The site is a ‘brownfields’ site  The site has a high aesthetic value owing to the presence of the Crocodile River and KNP beyond  Existing large trees will help to conceal the visual impact of the timeshare resort

PROPOSED TENBOSCH TIMESHARE RESORT 2

 The site is classified as Heavily or Moderately Modified Areas by the Mpumalanga Biodiversity Sector Plan (MBSP) Disadvantages of this site for the proposed activity include the following:

 This site is located close to Bucklers Africa Lodge  Site could potentially have a visual impact on the adjacent KNP

2.2. Lay-out Alternatives Two layout alternatives are under consideration for the proposed timeshare resort. Preferred Alternative: Alternative 1 Refer to Appendix A.2.1 for the preferred layout of the timeshare resort. The layout of the timeshare resort is designed to capitalize on the views provided by the Crocodile River and KNP to the north. The chalets will be grouped in pairs, 1 storey in height and constructed out of brick and mortar. Majority of the chalets will be located near the northern boundary of the site overlooking the Crocodile River and the Kruger National Park beyond. The remainder of the chalets will be clustered around two central complexes located in the east and west. The western central complex (an existing farmhouse) will consist of a communal recreational area with a swimming pool and a tennis court, while the eastern complex will consist of a swimming pool. The existing farmhouse and buildings located in the east will be upgraded to a clubhouse, recreation area, restaurant and a parking area will also be included. Five (5) bird hides/ viewpoints will be located throughout the property- one near the centre of the property near the northern boundary, one adjacent to the clubhouse and recreation area in the north east, one in the extreme north eastern corner of the property and two overlooking the dam in the south eastern portion of the property. An existing workshop in the centre of the property will be upgraded to a maintenance facility and key staff accommodation. An access control point, a parking area and a reception office will be located south east of the maintenance facility as you enter the property from the District road 1870. This Preferred Layout respects all recommended buffer areas, the flood line along the Crocodile River and all riparian buffers along the watercourses located on site. Existing drainage line crossings have been utilized where possible. Advantages of this layout for the proposed development include the following:

 Areas of high sensitivity have been avoided, with the majority of the development lying in areas of moderate sensitivity to low/transformed  The 1:100 year flood line is respected  The riparian buffer is respected  Existing drainage line crossings have been utilized where possible Disadvantages of this layout for the proposed development include the following:

 Certain chalets are located in close proximity to other tourism accommodation facilities  Bird hides are located within high sensitivity areas  Species of conservation concern occur on the site and could potentially be impacted upon

PROPOSED TENBOSCH TIMESHARE RESORT 3

 Small portions of the internal access roads encroach into areas of high sensitivity Layout Alternative: Alternative 2 Refer to Appendix A.2.2 for the Layout Alternative for the proposed timeshare resort. The Layout Alternative is very similar to the layout of the Preferred Alternative, with the exception of the placement of the chalets in the eastern portion of the site. In this layout, approximately 12 of the chalets, as well as, a portion of the internal access road in the north eastern corner are located within the riparian buffer which is a high sensitivity area and no-go zone for development. Advantages of this layout for the proposed development include the following:

 The 1:100 year flood line is respected  Existing drainage line crossings have been utilized where possible Disadvantages of this layout for the proposed development include the following:

 Certain chalets are located in close proximity to other tourism accommodation facilities  The riparian buffer is not respected  Species of conservation concern occur on the site and could potentially be impacted upon  A portion of the chalets are located in high sensitivity areas  Small portions of the internal access roads are located in areas of high sensitivity  Bird hides are located within a high sensitivity areas

2.3. Technology Alternatives Two technology alternatives are under consideration for the proposed timeshare resort. Preferred Alternative: Alternative 1 Raw water will be sourced from the conversion of existing water rights from the Crocodile River Irrigation System listed for 35ha and stored in a 350 kl storage tank. The water will then be distributed to each unit within the development via a water distribution network. The elevation of the development area is not sufficient to provide sufficient pressure for ground reservoirs, and a booster system with standby electricity will be provided. A sewage treatment plant will be constructed at a suitable position within the development site and all the sewage from the reticulated units within the development will be treated at this treatment plant. A sewage pump station or stations will be required to convey the sewage from the lowest positions to the plant. Outflow will be used for irrigation purposes. The key staff accommodation will be provided with onsite septic tank sewage disposal systems which will be located outside the 1:100 year flood plains. The treated effluent will comply with the General Standards required by the DWS and will be discharged into a large earth embankment dam located within the development area. The treatment processes for the plant will include screening, anaerobic digestion, trickling filter, settler and chlorine contact tank. Electricity supply will be via the Eskom lines on site whereby an underground reticulation system will be installed. Each unit will be supplied with a 60A single phase connection and the diversity maximum demand for the unit will be taken as 5kVA. Advantages of this technology for the proposed activity include the following:

 Irrigating with purified effluent lowers the potable water abstraction requirements and consumption. This is of relevance and importance in a water scarce country, such as ours.

PROPOSED TENBOSCH TIMESHARE RESORT 4

 Existing service infrastructure is already in place Disadvantages of this technology for the proposed activity include the following:

 Existing energy supply, which will be extended, is not renewable and sustainable green technology  The long term cost of energy from Eskom is set to increase significantly in the future, meaning a long term escalation in operational energy costs  Burying the cable could pose risks to the drainage lines, as well as, areas of high sensitivity Technology Alternative: Alternative 3 All service aspects will be as per the Preferred Alternative, with the exception that power will not be supplied by Eskom, but via solar power. Solar panels will be roof mounted on the roofs of the units and recreation areas. Advantages of this technology for the proposed activity include the following:

 The use of renewable energy (solar power) as a primary source of energy generation at the timeshare resort is an ecologically sustainable solution  The use of off-grid power negates the requirement for ecologically invasive electrical infrastructure (cabling) to the units.  The use of off-grid renewable energy at the timeshare resort will mostly likely bring a long term saving on operational energy costs. Disadvantages of this technology for the proposed activity include the following:

 The decision to make use of renewable energy (solar power) will imply a higher capital cost for the timeshare resort, as this infrastructure is expensive when compared to conventional on-grid energy solutions  Solar panels represent additional hard surfaces, which in turn imply higher storm water and runoff volumes from within the timeshare resort footprint  Solar panels could potentially have a high visual impact on the adjacent KNP tourists and impact on their visitor experience

2.4. No- project Alternative The No-Project Alternative implies that the proposed development of the timeshare resort on Tenbosch Farm and all associated infrastructure will not take place. In this scenario no negative environmental impacts relating to ground/surface water and biodiversity will be incurred. The No Project Alternative also implies that no positive impacts or benefits will be experienced such as the generation of employment opportunities, job creation and diversification of tourism offerings in the region.

3. SITE ACCESS

Ready access is available to the proposed development site via the District Road 1870 that runs parallel to the property. Existing internal dirt roads are also located throughout the property. These may be upgraded (paved) and expanded for use for the proposed development. 4. LOCALITY MAP

PROPOSED TENBOSCH TIMESHARE RESORT 5

Please refer to Appendix A1 for the locality map. 5. LAYOUT/ ROUTE PLAN

Please refer to Appendix A2.1 for the Preferred Alternative layout map and Appendix A2.2 for the Alternative 2 layout map. 6. SENSITIVITY MAP

Please refer to Appendix A3.1 for the Preferred Alternative sensitivity map and Appendix A3.2 for the Alternative 2 sensitivity map. 7. SITE PHOTOGRAPHS

Please refer to Appendix B for photographs taken at the 8 compass points. 8. FACILITY ILLUSTRATION

Please refer to Appendix C for the facility illustration(s). 9. ACTIVITY MOTIVATION

a) IDP, SDF other guidelines Areas of pristine natural environment in the northern part of Nkomazi include the Kaalrug Mountain range to the west, the Lebombo Mountain range to the east and the whole length of the Crocodile River. These areas have excellent potential for eco-tourism uses. The existing conservation developments of , Lionspruit Game Reserve, Ligwalagwala Conservancy, Dumaneni Reserve, Mahushe-Shonge Nature Reserve, Mawewe Cattle/Game Project as well as the proposed Vlakbult, Ntunda, Madadeni-Sikwahlane and Masibekela-Mananga Cattle Game projects create the opportunity for an uninterrupted conservation zone in the centre of Nkomazi. This forms one large ecological unit that stretches from Kruger National Park in the north to Lubombo Conservancy in the south-east. Associated land uses may include nature conservation, cattle ranching, game breeding, tourist facilities and hunting. Kruger National Park – the Kruger National Park dictates the type of land uses to be found adjacent to its border, including agriculture, tourism related developments i.e. eco areas, conservancies and uses focusing on nature conservation. In this regard, the proposed development of a timeshare resort on Tenbosch Farm falls within the Nkomazi IDP. b) Need and Desirability Tenbosch Farm is located on the banks of the Crocodile River, adjacent to the Kruger National Park. The motivation and reasoning behind the proposed development of the timeshare resort is to further develop the growing tourism industry and possible tourism linkages within the area. Tenbosch farm is situated in a prime position. The Kruger National Park forms the northern boundary of the proposed site. Other game reserves nearby are the Mjejane Private Game Reserve and Lionspruit Game Reserve. These Game Reserves are within easy driving distance from Gauteng and are also popular Big 5 game viewing destinations. It is, therefore, important that the natural recreational potential of this region be explored. In order to do this, accommodation facilities need be developed in the greater region that will help to unlock the natural potential of the region.

PROPOSED TENBOSCH TIMESHARE RESORT 6

10. APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES

The following legislation may also be applicable:

PROPOSED TENBOSCH TIMESHARE RESORT 7

TITLE OF LEGISLATION, APPLICABILITY TO THE PROJECT ADMINISTERING DATE POLICY OR GUIDELINE AUTHORITY LEGAL FRAMEWORK Constitution of Republic of This is the fundamental law of South Africa, setting out the Bill of Rights as well as the relationship National Government 1996 South Africa (Act No.108 of of various government structures to each other. 1996): Conservation of Provides for control over the utilization of the natural agricultural resources of the Republic. The Department of 1983 Agricultural Resources Act proposed project will be required in terms of this legislation to ensure that: Agriculture (Act No. 43 of 1983): re protected,

National Environmental To provide for co-operative environmental governance by establishing principles for decision- Department of 1998 Management Act (Act No. making on matters affecting the environment, institutions that will promote cooperative governance Environmental Affairs 107 of 1998) and procedures for co-ordinating environmental functions exercised by organs of state; to provide for certain aspects of the administration and enforcement of other environmental management laws; and to provide for matters connected therewith. National Environmental The Act provides for the protection and conservation of ecologically viable areas representative of Department of 2003 Management: Protected South Africa’s biological diversity and its natural landscapes and seascapes; for the establishment Environmental Affairs Areas Act (Act No. 57 of of a national register of all national, provincial and local protected areas; for the management of 2003): those areas in accordance with national norms and standards; for intergovernmental co-operation and public consultation in matters concerning protected areas, and for matters in connection therewith. The proposed development is adjacent to the Kruger National Park, a Protected Area in terms of this Act. National Environmental The purpose of the Biodiversity Act is to provide for the management and conservation of South Department of 2004 Management: Biodiversity Africa’s biodiversity within the framework set out by NEMA and the protection of species and Environmental Affairs Act (Act No. 10 of 2004): ecosystems that warrant national protection. As part of its implementation strategy, the National Spatial Biodiversity Assessment was developed (see below). Rare or protected species may be affected during construction. The Act lists species that are threatened or require protection to ensure their survival in the wild, while regulating the activities, which may involve such listed threatened or protected species and activities which may have a potential impact on their long-term survival. The Act has listed flora and fauna species. National Spatial The National Spatial Biodiversity Assessment (NSBA) classifies areas as worthy of protection Department of 2011 Biodiversity Assessment, based on its biophysical characteristics, which are ranked according to priority levels. Environmental Affairs

PROPOSED TENBOSCH TIMESHARE RESORT 8

2011: National Forests Act (Act This Act provides for the management, utilisation and protection of forests through the enforcement Department of 1998 No. 84 of 1998): of permitting requirements associated with the removal of protected tree species, as indicated in a Agriculture, Forestry and list of protected trees (first promulgated in 1976 and updated since). Fisheries Although not anticipated, should any protected tree species require removal or relocation within the project area, a permit will be required. National Veld and Forest The purpose of this Act is to prevent and combat veld, forest and mountain fires throughput the Department of Water 1998 Fire Act (Act No. 101 of Republic. The Act provides for a variety of institutions, methods and practices for achieving this Affairs 1998) purpose. National Heritage The National Heritage Resources Act legislates the necessity for cultural and heritage impact South African Heritage 1999 Resources Act (Act No. 25 assessment in areas earmarked for development, which exceed 0.5 hectares (ha) and where linear Resources Agency of 1999) developments exceed 300 metres in length. (SAHRA) In this regard, the proposed development site will be subject to engagement with the South African Heritage Resources Agency (SAHRA). Potential impact on cultural heritage, paleontological or archaeological resources through excavation activities or disturbance will need to be monitored. Permits may be required per the National Heritage Resources Act (Act No. 25 of 1999). The National Water Act This Act aims to provide management of the national water resources to achieve sustainable use of Department of Water 1998 (Act No. 36 of 1998) water for the benefit of all water users. Affairs The proposed development will have to ensure that local water resources are protected, used, developed, conserved, managed and controlled in a responsible way. The National Water The Act legislates the necessity to provide for the rights of access to basic water supply and basic Department of Water 1997 Services Act (Act No. 108 sanitation; to provide for the setting of national standards and of norms and standards for tariffs; to Affairs of 1997) provide for water services development plans; to provide a regulatory framework for water services institutions and water services intermediaries; to provide for the establishment and disestablishment of water boards and water services committees and their powers and duties; to provide for the monitoring of water services and intervention by the Minister or by the relevant Province; to provide for financial assistance to water services institutions; to provide for certain general powers of the Minister; to provide for the gathering of information in a national information system and the distribution of that information; to repeal certain laws; and to provide for matters connected therewith. National Environmental The Waste Act reforms the law regulating waste management in order to protect the environment Department of 2008 Management Waste Act by providing reasonable measures for the prevention of pollution and ecological degradation. Environmental Affairs (Act No. 59 of 2008) The proposed development will be subject to this Act in terms of the disposal of waste. Hazardous Substances Act To provide for the control of substances which may cause injury or ill-health to or death of human Department of Health 1973

PROPOSED TENBOSCH TIMESHARE RESORT 9

(Act No. 15 of 1973) beings by reason of their toxic, corrosive, irritant, strongly sensitizing or flammable nature or the generation of pressure thereby in certain circumstances, and for the control of certain electronic products; to provide for the division of such substances or products into groups in relation to the degree of danger; to provide for the prohibition and control of the importation, manufacture, sale, use, operation, application, modification, disposal or dumping of such substances and products; and to provide for matters connected therewith. National Environmental To reform the law regulating air quality in order to protect the environment by providing reasonable Department of 2004 management Air Quality measures for the prevention of pollution and ecological degradation and for securing ecologically Environmental Affairs Act (Act No. 39 of 2004) sustainable development while promoting justifiable economic and social development; to provide for national norms and standards regulating air quality monitoring, management and control by all spheres of government; for specific air quality measures; and for matters incidental thereto. Occupational Health and The purpose of this Act is to provide for the health and safety of persons at work and for the health Department of Labour 1993 Safety Act, 1993 (Act No. and safety of persons in connection with the use of plant and machinery; the protection of persons 85 of 1993): other than persons at work against hazards to health and safety arising out of or in connection with, the activities of persons at work. The proposed development will therefore be subject to this Act during the construction and operational Application for Environmental Authorisation. Integrated Environmental IEM is a key instrument of NEMA and provides the overarching framework for the integration of Department of 1992 Management Information environmental assessment and management principles into environmental decision-making. Environmental Affairs Series The aim of the information series is to provide general information on techniques, tools and processes for environmental assessment and Management. These various documents have been referred to for information on the most suitable approach to the environmental assessment process for the proposed development. Local Government: To provide for the establishment of municipalities in accordance with the requirements relating to National Government 1998 Municipal Structures Act, categories and types of municipality; to establish criteria for determining the category of municipality No. 117 of 1998 to be established in an area; to define the types of municipality that may be established within each category; to provide for an appropriate division of functions and powers between categories of municipality; to regulate the internal systems, structures and office-bearers of municipalities; to provide for appropriate electoral systems; and to provide for matters in connection therewith Local Government: To provide for the core principles, mechanisms and processes that are necessary to enable National Government 2000 Municipal Systems Act, municipalities to move progressively towards the social and economic upliftment of local No. 32 of 2000 communities, and ensure universal access to essential services that are affordable to all; to define the legal nature of a municipality as including the local community within the municipal area, working in partnership with the municipality’s political and administrative structures; to provide for the manner in which municipal powers and functions are exercised and performed; to provide for

PROPOSED TENBOSCH TIMESHARE RESORT 10

community participation; to establish a simple and enabling framework for the core processes of planning, performance management, resource mobilisation and organisational change which underpin the notion of developmental local government. REGIONAL PLANNING POLICIES Nkomazi Local Municipality The Kruger National Park has influenced the spatial form of the local municipality and dictates the Nkomazi Local 2015/2016 IDP type of land uses to be found adjacent to its border, including agriculture and tourism related Municipality developments. Tourism has been identified as one of the five key pillars for economic development within the municipality.

PROPOSED TENBOSCH TIMESHARE RESORT 11

11. WASTE AND EFFLUENT

11.1. Solid Waste Management Solid waste will be separated into non-recyclables and recyclables and stored separately for collection. Non-recyclables will be collected and stored in fenced ‘scavenger proof’ areas at a holding facility at the entrance gate to the development site. The waste will then be collected by the Resort Management/Service provider and transported to the Nkomazi Municipality’s approved landfill site at Steenbok.

11.2. Liquid effluent A water treatment plant will be constructed at a suitable position on the development area. Collector sewer lines will be constructed to convey the sewage to two sewage pump stations. Sewer rising mains will be provided to convey the wastewater to the wastewater treatment plant.

The treated effluent will comply with the General Standards required by the DWS and will be discharged into a large earth embankment dam located within the development area. The treatment processes for the plant will include screening, anaerobic digestion, trickling filter, settler and chlorine contact tank.

Septic tanks and soakaways may be required for key staff and administration facilities. Effluent emanating from the septic tank at the units will be dissipated via a soak away by means of properly designed and installed soak away systems.

It is assumed that the sewage flow per unit will be 1200 litres/day and 200 litres/capita for staff. The total annual average daily wet weather flow is approximately 96.8 m3/day for a 100% occupancy rate.

12. WATER USE

Water will be sourced from converted water rights from the Crocodile River.

The anticipated total gross annual average daily water demand is 119.5 m3/day for a 100% occupancy rate (74 units at 111 Kl/day, 10 on site staff at 2.5 Kl/day, 45 non-resident staff on site at 2.25 Kl/day and 75 visitors to the clubhouse/restaurant at 3.75 Kl/day).

The storage capacity of reservoirs serving fire areas should, over and above the allowance for domestic demand, include for the design fire flow. The minimum additional storage capacity require for firefighting is therefore 900 l/min for a duration of 2 hours, which equates to 108 m3. The total storage capacity required equates to 335 m3 (227 m3 for 48 hours domestic and commercial demand and 108 m3 for firefighting purposes).

The storage requirements are 239 m3 for domestic consumption (48 hours of GAADD) plus 108 m3 for firefighting which equates to 347 m3. The elevation of the development area is not sufficient to provide sufficient pressure for ground reservoirs, and a booster system with standby electricity will have to be provided.

Trenching for electricity and potable water will be consolidated into single trench alignments which will follow road and pathway alignments where possible. Wastewater will have its own alignment.

PROPOSED TENBOSCH TIMESHARE RESORT

SECTION B: SITE/AREA/PROPERTY DESCRIPTION

13. GROUNDWATER, SOIL AND GEOLOGICAL STABILITY OF THE SITE

The study area is underlain by transported sandy and gravelly soils overlying basalt bedrock belonging to the Letaba Formation, Lebombo Group, Karoo Supergroup.

Isolated outcrops of very hard rock basalt are present in the central, northern portion of the property which has been apportioned into three prominent geotechnical soil zones, Soil Zones “A” to “C.”

Soil Zone A materials cover the majority of the site, Soil Zone B materials cover the central portion of the site and Soil Zone C occupies the two low-lying areas and drainage features including the dam located in the east. The timeshare units will be located along the northern boundary of the proposed site where Soil Zones A and B are found.

Soil Zone A (thin to moderate horizon of loose to medium dense, colluvial clayey sand, loose pebble marker and medium dense to dense residual basalt over soft rock to hard rock basalt). This soil zone has a potentially low degree of expansiveness.

Soil Zone B (This soil zone consists of moderate horizon of loose silty sand and very stiff, sandy clay over medium dense, alluvial clayey sand and loose pebble marker over dense residual basalt over soft rock to hard rock basalt). The soils blanketing portions of this zone are, in general, clayey and have the potential to be medium in the degree of expansiveness.

Minor to moderate seepage of ground water was encountered in two test in the eastern portion of the site from below a depth of 1,5m in the lower-lying areas adjacent to the earth dam. No water seepage were encountered elsewhere, however, the necessary damp-proofing precautions should therefore be taken underneath structures. The site soils are expected to be potentially chemically aggressive with regards to underground ferrous metal pipes (pH values ranging from 6,83 to 7,43 and electrical conductivity values ranging from 4,83 to 152,9 mS/m) and the use of non-ferrous metal pipes or plastic pipes are recommended for wet services. The chemical tests conducted on the ground water sample have shown the water to be of good quality for human consumption although the water is corrosive towards metals and concrete.

Refer to Appendix D.1 for the full Geotechnical Report.

14. GROUNDCOVER

According to Mucina & Rutherford (2006), the study area is situated in Tshokwane - Hlane Basalt Lowveld within the Lowveld Bioregion in the Savanna Biome. This vegetation type is restricted to a strip running parallel to the Lebombo Mountains from central Swaziland in the south to the Olifants River in the north. Tshokwane - Hlane Basalt Lowveld originally covered 281 929 ha in Mpumalanga, of which 12.1 % has been transformed, mostly through sugarcane and settlements. This vegetation type is considered well protected and has a conservation status of Least Concern (Lötter et al., 2014). This is largely due to much of this community occurring within the Kruger National Park. It is not listed as a Threatened Ecosystem (Notice 1002 of Government Gazette 34809, 9 December 2011).

Most of the terrestrial ecosystems within the study area on Tenbosch is classified as Heavily or Moderately Modified Areas by the Mpumalanga Biodiversity Sector Plan (MBSP). The scattered untransformed sections are classified as Other Natural Areas. Other Natural Areas refer to areas that have not been identified as a priority in the current systematic biodiversity plan but retain most of their natural character, while performing a range of biodiversity and ecological functions. Other Natural Areas offer much more flexibility in terms of permissible land

PROPOSED TENBOSCH TIMESHARE RESORT 13 uses, but the desired management objective should be to minimise habitat and species loss and ensure ecosystem functionality through strategic landscape planning.

The entire study area is also situated within the Ecological Support Areas (ESA): Protected Area Buffers. ESA’s are “areas that are not essential for meeting (conservation) targets, but play an important role in supporting the functioning of CBA’s and that deliver important ecosystem services” (Lötter et al., 2014). Protected Area Buffers are areas that surround proclaimed protected areas that moderate the negative impacts of land-uses that may affect the ecological functioning of those protected areas .

The wetland vegetation around the dam is classified as ESA: Wetlands in the MBSP. These areas are not essential for meeting biodiversity conservation targets but play an important role in supporting the functioning of Critical Biodiversity Areas and deliver important ecosystem services. Both drainage lines in the study area are classified as ESA: Important Sub catchments, Fish Support Areas. These are areas that are important for supporting threatened and near threatened indigenous freshwater fish populations.

The study area is not situated in any of southern Africa’s floristic centres of endemism, which are areas that have an unusually high number of plants unique to that area (Van Wyk & Smith, 2001).

Refer to Appendix D.4 for the full Ecology Report

15. SURFACE WATER

According to the MBSP freshwater assessment there are some ESA wetlands within the study area. These are associated with the dam occurring within the study area as well as with the Crocodile River, which lies on the northern border of the site. The NFEPA project classifies the wetlands within the study area as channelled valley- bottom wetlands.

According to the NBA 2011, all of the wetlands in the vicinity of the study area belong to wetland ecosystem types that are Critically Endangered. A Critically Endangered ecosystem type is one in which most of the ecosystem type has been severely or moderately modified from its natural state and few natural or near-natural examples of this ecosystem remain; these remaining healthy examples should be the focus of urgent conservation action (Driver et al., 2012).

The sub-catchment within which the study area falls has been classified by the MBSP as an ‘ESA Important Sub-catchment’, but does include large sections of ‘Heavily Modified’ areas as well as a dam. The sub- catchment is important as it is a Fish Support Area. This is owing to the presence of a fish species of conservation concern (Tiger Fish Hydrocynus vittatus).

The study area is associated with one perennial river (Crocodile) and several non-perennial rivers. The extent to which a river has been modified by human activity is referred to as the river condition (Nel et al., 2011). According to NFEPA, the Crocodile River has a condition of ‘D’, which means that it is largely modified such that a large loss of natural habitat, biota and basic ecosystem functions have occurred (Nel et al., 2011).

Refer to Appendix D.2 for the full Wetland Report 16. LAND USE CHARACTER OF SURROUNDING AREA

The proposed development is situated on Portion 101 of the farm Tenbosch 162 JU, approximately 8 km north- west of the town of Komatipoort, Ehlanzeni District, Mpumalanga. The study area lies adjacent to the Kruger National Park boundary on the southern bank of the Crocodile River between the town of Marloth Park to the west and the Crocodile Bridge Gate to the east. Surrounding land uses include agricultural, commercial and residential developments to the west, south and east and conservation land to the north.

PROPOSED TENBOSCH TIMESHARE RESORT 14

17. CULTURAL/HISTORICAL FEATURES

Francois P. Coetzee, an independent Cultural Heritage Consultant, was commissioned by NuLeaf Planning and Environmental to undertake a Heritage Impact Assessment of Portion 101 of the farm Tenbosch 162 JU in order to determine the heritage potential and the impact on possible heritage resources.

No Stone Age or Iron Age settlements, structures, features, assemblages or artefacts were recorded during the survey. Also, no graveyards or individual graves were recorded.

No buildings over 60 years old were found on site. The two (2) houses located on site were built in the 1960/70s.

Refer to Appendix D.3 for the full Heritage Impact Report.

18. SOCIO-ECONOMIC CHARACTER

Agriculture and tourism have been identified as one of the building blocks for economic development within the municipality and has been experiencing growth thereof.

Due to the fact that Nkomazi municipality is mostly a rural municipality, the municipality suffers from a high rate of unemployment as it is struggling to attract investments. Other factors contributing to the high employment rate is the shortage of skills and illiteracy rates. As it is generally applicable throughout the country, unemployment is at the heart of poverty within the municipality.

The latest official statistical information suggests that unemployment rate has been on a downward trend. In 2007 the total unemployment rate of Nkomazi was approximately 34.2% which can be attributed to the 26% and 43% of males and females respectively. According to the 2011 STATS SA Census the total unemployment rate in the municipality is 34% with 26.8% being males and 42.5 % being females.

There were major improvements in educational attainment within the municipality between 2001 and 2011. In1996 47% had had no schooling and this decreased to 26% in 2011 which indicates favourable improvements in educational attainment over a period of 15 years.

19. BIODIVERSITY

19.1. Terrestrial Ecology

A specialist terrestrial ecology assessment was undertaken by ECOREX Consulting Ecologists CC in May 2016.

19.1.1. Flora

A total of 140 plant species was recorded within the study area during fieldwork. Three of these are protected under the National Forests Act (No. 30 of 1998): Philenoptera violacea, Combretum imberbe and Sclerocarya birrea subsp. caffra, and two by the Mpumalanga Nature Conservation Act (No.10 of 1998): Aloe marlothii and Crinum stuhlmannii. Dalbergia melanoxylon is assessed as Near Threatened and Crinum stuhlmannii as Declining. The latter two species are discussed below:

 Dalbergia melanoxylon Guill. & Perr. Zebra Wood: This species usually grows as a small to medium- sized tree and is found throughout the Lowveld and as far north and west as Senegal. Although not locally listed, it is assessed by the IUCN as Near Threatened due to over-collection for the wood

PROPOSED TENBOSCH TIMESHARE RESORT 15

carving industry and in the manufacturing of musical instruments. A single small plant was found in the western portion of the study area.

 Crinum stuhlmannii Baker Candy-striped Crinum: A single large Crinum species, most likely C. stuhlmannii, was located within Transformed vegetation in a line of trees between the large lawn of the eastern building complex and the Kruger National Park fence. This large bulbous plant is listed as Declining due to the ongoing and uncontrolled harvesting of bulbs for the medicinal plant trade.

Three untransformed vegetation communities were identified within the study area on the basis of distinctive vegetation structure (grassland, woodland, thicket, etc.), floristic composition (dominant and diagnostic species) and position in the landscape (mid-slopes, terrace, crest, etc.). Transformed and degraded areas make up approximately 30 ha, or 75 % of the study area. Most of the transformed and degraded land is covered by citrus orchards, various buildings, a short golf course and old lands. The untransformed vegetation communities are described in detail below:

- Ficus sycomorus - Hypoestes forskaolii Disturbed Riparian Forest

This vegetation community occurs in two portions within the study area. The larger tract is located in the eastern section below the dam, running down along the small stream to the Crocodile River. Vegetation structure is mostly Low to Tall Forest (sensu Edwards, 1983; Figure 2). Riparian Forest covers approximately 3 ha which equates to 7.5 % of the study area. Evergreen trees and woody shrubs dominate this vegetation community, with the dominant canopy species being Ficus sycomorus, Diospyros mespiliformis and Trichilia emetica. Other common canopy species include Bridelia micrantha, Rauvolfia caffra and Acacia xanthophloea. Woody shrubs dominating the understory include Grewia monticola, Bridelia cathartica, Phyllanthus reticulatus, Gymnosporia senegalensis, Pluchea dioscoridis and Gymnanthemum coloratum. Much of the understory of Riparian Forest had been slashed, particularly west of the channel, but in less disturbed parts the common understory plants included the herbs Hypoestes forskaolii, Cucumis zeyheri and Jasminum fluminense and the grasses Setaria megaphylla and Panicum maximum. A feature of this community is the high level of alien plant infestation with many species forming monospecific stands (such as Hedychium gardnerianum). Some are declared alien invasive plants but many are growing as garden escapes, and at least 21 species were recorded from this community.

A total of 62 species (44 % of the entire list) was recorded from Riparian Forest, the second highest of all the vegetation communities. Species fidelity, which is closely linked to community uniqueness, is also high, with 34 species (55 % of the community list) occurring nowhere else in the study area.

Only two conservation-important species were recorded. Philenoptera violacea and Sclerocarya birrea subsp. caffra are protected under the National Forests Act (No. 30 of 1998).

- Acacia nigrescens – Panicum maximum Disturbed Closed Woodland

Acacia – Panicum Disturbed Closed Woodland covers 2.2 ha or 5.5 % of the study area. Vegetation structure can best be described as Short to Tall Closed Woodland, although some bush clearing has taken place in parts which has resulted in an Open Shrubland vegetation structure (Edwards, 1983).

A moderate variety of trees dominate the canopy with the most dominant including various legumes such as Acacia nigrescens, Acacia nilotica and Peltophorum africanum. Other common trees located include Combretum hereroense and C. imberbe, Sclerocarya birrea subsp. caffra and Ziziphus mucronata. Common shrubs found include Grewia bicolor, G. flavescens, Dichrostachys cinerea subsp.

PROPOSED TENBOSCH TIMESHARE RESORT 16

africana and Gymnosporia senegalensis. Dwarf shrubs were prominent, and include Barleria elegans, Abutilon austro-africanum, Solanum campylacanthum subsp. panduriforme and Maerua parvifolia. Forbs, bulbs and herbs recorded included Kalanchoe rotundifolia, Acalypha villicaulis, Cucumis zeyheri and Justicia flava. Scattered Aloe marlothii were also observed. The dominant grasses found include Panicum maximum, Cenchrus ciliaris, Digitaria eriantha, Eragrostis superba, Heteropogon contortus and Urochloa mosambicensis.

A total of 78 species was recorded in Acacia – Panicum Disturbed Closed Woodland, representing 56 % of the entire species list and the highest of the three vegetation communities. Species fidelity is high, with 39 species (50 % of the community list) occurring nowhere else in the study area. One Near Threatened tree species was recorded: Dalbergia melanoxylon, as well as three species protected under the National Forests Act (No. 30 of 1998): Philenoptera violacea, Combretum imberbe and Sclerocarya birrea subsp. caffra, and one by the Mpumalanga Nature Conservation Act (No.10 of 1998): Aloe marlothii.

- Phragmites australis – Typha capensis Wetland

Tall and dense wetland vegetation surrounds the artificial dam in the eastern part of the study area. Vegetation structure is mostly Tall Closed Grassland (sensu Edwards, 1983, Table 6). Wetland areas cover approximately 4.6 ha or 11.5 % of the entire study area. This figure, though, includes the unvegetated open water of the dam itself. The reed Phragmites australis and the rush Typha capensis strongly dominate this community. Other species located include the sedges Cyperus dives and C. sexangularis, the grass Leersia hexandra, the herbs Persicaria decipiens and Commelina diffusa subsp. scandens, the shrubs Ludwigia octovalvis and Phyllanthus reticulatus, and the fern Thelypteris confluens.

A total of 15 species (11 % of the entire list) was recorded from the Wetland community, the lowest species richness of the three untransformed vegetation communities in the study area. Species fidelity, which is closely linked to community uniqueness, is high, with 8 species (53 % of the community list) occurring nowhere else in the study area.

No conservation-important species were recorded within this vegetation community.

- Transformed/degraded

Approximately 30 ha, or 75 % of the study area, are transformed either through agriculture (mostly citrus), sheds, houses and a golf course. However, four conservation-important plant species were recorded from Transformed areas including Crinum stuhlmannii (Declining and protected under the MNCA), Philenoptera violacea and Sclerocarya birrea subsp. caffra (protected under the NFA) and Aloe marlothii (protected under the MNCA). Most of these plants grow around the homesteads or golf course.

19.1.2. Fauna

- Mammals

Situated in the savanna biome immediately south of the Kruger National Park (KNP), the Komatipoort area has very high mammal diversity, relatively low numbers of endemics and a moderate number of Red Data species. The study area is mostly transformed (75 %) and little habitat remains, especially for

PROPOSED TENBOSCH TIMESHARE RESORT 17

larger mammals. However, it is located on the boundary fence of the KNP and animals can and do wander in through gates or the fence or via the stream channel in the east. Evidence of this was found in a small tract of woodland in the west where old Hippopotamus (Hippopotamus amphibius) faeces were located. An estimated 32 conservation-important mammals potentially occur within the project area, although most of these are more likely in adjacent conservation land than in the project area. Several bat species are highly likely to occur overhead, such as Geoffroy’s Horseshoe Bat (Rhinolophus clivosus), but these species are only likely to feed over the site because of the shortage of suitable roosting sites.

Of the 32 potentially occurring species, 26 are considered to be of conservation concern with only four considered threatened. Hippopotamus (Hippopotamus amphibius), was confirmed in Closed Woodland during fieldwork and is discussed below:

 Hippopotamus (Hippopotamus amphibius): Desiccated faeces were located in the small tract of Closed Woodland in the western part of the study area. This large even-toed ungulate may also occasionally utilise the dam and stream in the east. However, due to human disturbance and access problems due to the fence, it would probably only frequent the study area occasionally. It is listed as Vulnerable due to habitat loss, range contraction, conflict from farmers and a decline in water quality . This species is resident in the adjacent Crocodile River (pers.obs.). The remaining three potentially occurring threatened species, namely African Wild Dog (Lycoan pictus, Endangered), Lion (Panthera leo, Vulnerable) and Ground Pangolin (Smutsia temminckii, Vulnerable), all have a low likelihood of occurrence due to disturbance, lack of prey or general scarcity. Eight potentially occurring species are Near Threatened, which are species close to or likely to soon qualify for the status of Vulnerable. Four of these have a moderate likelihood of occurring due to the presence of suitable habitat, namely Honey Badger (Mellivora capensis), Side-striped Jackal (Canis adustus), Welwitsch's Hairy Bat (Myotis welwitschii) and Rusty Bat (Pipistrellus rusticus).

- Birds

Eighty-eight bird species were confirmed to occur in the study area during fieldwork. Thirty-six species were recorded from Riparian Forest, 26 from the Wetland and 13 from Transformed. Three broad assemblages or species-habitat associations were identified, each of which is briefly described below:

 Forest Assemblage: This assemblage occurs in the tall evergreen forest patches, best represented in the eastern portion of the study area. Although some overlap occurs with the Woodland assemblage, the composition of species differs sufficiently to justify the inclusion of this assemblage. Bird species found include those species not commonly found in the adjacent KNP due to habitat transformation through large herbivores. These include Scaly-throated Honeyguide, Red-backed Mannikin, African Goshawk, Tambourine Dove, Yellow-rumped Tinkerbird and Black-throated Wattle-eye. Thirty-six species (41 %) were recorded from the Forest assemblage, the highest of the three assemblages.

 Woodland Assemblage: The drier woodlands across the study area provide refuge for a number of generalist species that will occasionally forage in any type of wooded habitat including the Riparian Forest. These include Black-backed Puffback, White-bellied Sunbird and Yellow-breasted Apalis. Some species, though, are restricted to this assemblage and include Jameson’s Firefinch, White-browed Scrub Robin, Brown-crowned Tchagra and Southern

PROPOSED TENBOSCH TIMESHARE RESORT 18

Yellow-billed Hornbill. Due to the small size of the woodland patches, many woodland species will probably only visit the study area to forage or include the patches as part of larger territories extending into the KNP Thirty-one species (35 % of the entire species list) were recorded from the Woodland assemblage, the second highest of the three.

 Wetland Assemblage: The artificial dam and associated reed and rush beds in the eastern portion of the study area provide habitat for a number of wetland-dependant species not found in the other assemblages. These include shy reedbed skulkers such as Little Rush and Lesser Swamp Warblers, Black Crake and African Swamphen, open water species such as African Darter, Pied and Giant Kingfishers and African Fish Eagle and the floating macrophyte specialist African Jacana. Twenty-six species were recorded in this assemblage, representing 30 % of the total species list.

The savanna biome supports the highest diversity of bird species within the Southern African sub-region and the KNP supports the largest bird list of all conservation areas in South Africa with an estimated 57 % of the birds found within the entire southern African sub-region recorded. Eighty-eight bird species were confirmed to occur within the actual habitats represented in the study area during fieldwork.

Twenty-nine of the bird species potentially occurring within the study area (confirmed to occur in 2531 BD during SABAP2 or potentially occur due to presence of suitable habitat) have Red Data status. One of these was confirmed to occur during fieldwork:

 Martial Eagle (Polemaetus bellicosus): Africa’s largest eagle is listed as Endangered due to many factors including habitat loss, direct persecution from small-stock farmers and indirect persecution from electrocution and reservoir drownings . A pair of eagles was observed flying over Closed Woodland in the study area and not actually utilising the habitat within, although it may occasionally hunt over the study area. No suitable breeding habitat is present on Tenbosch. Twenty-one additional species of conservation-concern have a low likelihood of foraging over the study area. This is primarily due to a lack of suitable prey such as small antelope and gamebirds, human disturbance from farming and recreational activities and insufficient habitat area available due to habitat transformation. Seven potentially occurring species are listed as Near Threatened with three having a moderate likelihood of occurring within the study area, namely Half-collared Kingfisher (Alcedo semitorquata), European Roller (Coracias garrulous) and Marabou Stork (Leptoptilos crumeniferus). - Reptiles and Frogs

The Lowveld and foothills of far eastern Mpumalanga support a high diversity of reptile species with 102 species already recorded from the degree grid 2531 . Forty-seven species of reptiles have been recorded from the QDS 2531 BD, in which Tenbosch is situated. Of the potentially occurring species, only two conservation-important reptiles potentially occur. One of these has been assessed as Vulnerable: Nile Crocodile (Crocodylus niloticus), which is also protected under NEMBA ToPS. This species was confirmed during fieldwork and is discussed below:

 Nile Crocodile (Crocodylus niloticus): Africa’s largest reptile is listed as Vulnerable due to a number of factors including habitat transformation, water pollution, direct persecution from landowners and harvesting for the medicinal market (Bates et. al., 2014). The Kruger National Park supports an estimated 3000 individuals which constitutes the largest population in South

PROPOSED TENBOSCH TIMESHARE RESORT 19

Africa (Thorbjarnarson, 1992). The adjacent Crocodile River supports a resident population of crocodiles (pers.obs.) and smaller individuals are able to enter the study area at the junction of the Crocodile River and the small stream in the eastern portion (pers.obs.). In communication with a number of farm labourers, the presence of a few juvenile Nile Crocodiles was confirmed to occur in the dam on the stream but larger specimens potentially occur. No breeding habitat (sandy river banks) is available around the dam though. Southern African Python (Python natalensis) is protected under the National Environmental Management: Biodiversity Act (No.10 of 2004) and was confirmed during fieldwork from Riparian Forest immediately north of the dam. Two additional reptile species were recorded during fieldwork: Rainbow Skink (Trachylepis margaritifera) and Common Giant Plated Lizard (Matobosaurus validus).

No frogs were recorded during the assessment although summer fieldwork with nocturnal surveys will result in a fair number of species.

Refer to Appendix D.4 for the full Ecology report.

19.2. Riparian Ecology

A specialist wetland/riparian survey was undertaken by Wet-Earth Eco-Specs to identify and delineate wetlands and riparian area, as well as, determine the present ecological state (PES) and the ecological importance and sensitivity (EIS). Three (3) water courses were identified and can be described as riverine areas. There are wetland areas which form part of these riparian areas. These wetland areas occur around the dam and upstream of road crossings and weirs. These water courses have been named T01, T02 and T03 for ease of discussion.

- T01 Water course T01 is the dam located in the east of the proposed site. The riparian zone extends upstream from the edge of the property and downstream where it joins the Crocodile River. The Riparian Index of Habitat Integrity (RIHI) is a C/D (57.7). This is mainly owing to the road crossings, orchard footprint which has extended into the riparian areas, the dam which destroyed approximately 71 % of the original riparian area, a weir in an active channel and an extensive presence of exotic vegetation. The PES is D/E and the PES Ecostatus is D/E (largely modified/ seriously modified).

 Marginal zone: The presence of a dam indicates a disturbed environment with the result that a large portion of this zone is dominated by reeds, grasses and sedges. The section downstream of the dam is dominated by trees and scattered clumps of grass and sedge. The substrate consists of soil with rocky features occurring in places. The dominant tree species are Ficus sycomorus and Trichilia emetica. The following grass and sedge species occur in this zone: Phragmites australis, Typha capensis, Cyperus dives, Cyperus sexangularis, etc. Exotic vegetation, such as: Melia azedarach, Tecoma stans, Verbena bonariensis, Tagetes minuta, Ricinus communis, Lantana camara, etc. occurs.

 Non-marginal zone: A reed and tree dominated state exists along the edges of the dam. Downstream of the dam the dominant vegetation is mostly trees and herbs. The substrate consists mainly of soil material and rocky habitat in places. The banks are steep in places. The following woody species occur: Bridelia micrantha, Acacia xanthophloea, Philenoptera violacea, Phyllanthus reticulatus, Ficus sycomorus, Syzygium cordatum, Celtis africana, Sclerocarya birrea subsp. caffra, Bridelia micrantha, Rauvolfia caffra, Grewia monticola, Bridelia cathartica, Phyllanthus reticulatus, Gymnosporia senegalensis, Pluchea dioscoridis

PROPOSED TENBOSCH TIMESHARE RESORT 20

and Gymnanthemum coloratum, etc. Understory plants such as: Setaria megaphylla, Hypoestes forskaolii, Cucumis zeyheri, Jasminum fluminense, and Panicum maximum occur. Some exotic vegetation such as: Melia azedarach, Solanum mauritianum, Lantana camara, Ageratum conyzoides, etc. were also found.

- T02 Watercourse T02 is the drainage line located in the western portion of the site. The riparian zone extends from the edge of the property upstream to where it joins with the Crocodile River downstream. The RIHI is a D (53.8 %). This is due to roads traversing the riparian zone, dumping, agriculture, vegetation clearing and water quality issues. PES is D while the PES Ecostatus is also a D (53.8%) (largely modified).

 Marginal zone: The dominate vegetation consists of shrub species with scattered grass and herbs. Within the riparian section adjacent to the storage facilities, upstream of the road crossing, the understory has been cleared and is dominated by trees and scattered clumps of grass and sedges. The substrate consists mainly of soil with rocky banks in places. Dominant woody species present include Ficus sycomorus, Rauvolfia caffra, Phyllanthus reticulatus and Trichilia emetica. The following grass and sedge species occur: Persicaria decipiens, Commelina diffusa subsp. scandens, Phragmites australis, Typha capensis, Cyperus dives, Cyperus sexangularis, etc. In the area between the two road crossings the grass Leersia hexandra dominates. Exotic vegetation such as Melia azedarach, Tecoma stans, Verbena bonariensis, Tagetes minuta, Ricinus communis, Lantana camara, etc. occurs.

 Non-marginal zone: A tree and grass-dominated state occurs upstream of the road-crossing. In this area the groundcover and some shrubs have been felled to clear the space. The substrate consists mainly of soil and rocky material. The downstream section is dominated by a woodier component. Upstream of the lower road crossing the dominant vegetation consists of grass and sedges. The following woody species occur: Rhoicissus tridentata subsp. cuneifolia, Bridelia micrantha, Acacia nigrescens, Acacia xanthophloea, Philenoptera violacea, Phyllanthus reticulatus, Ficus sycomorus, Ziziphus mucronata, Syzygium cordatum, Celtis africana, Sclerocarya birrea subsp. caffra, Rauvolfia caffra, Grewia monticola, Grewia flavescens, Phyllanthus reticulatus, Gymnosporia senegalensis, Pluchea dioscoridis and Gymnanthemum coloratum, etc. Understory plants such as Setaria megaphylla and Panicum maximum are present. Some exotic vegetation such as, Melia azedarach, Solanum mauritianum, Lantana camara, Ageratum conyzoides, etc. were also found. The climber Ipomoea purpurea occurs abundantly and has a smothering effect on the vegetation. - T03 Watercourse T03 is the Crocodile River which forms the northern border of the proposed site. The RIHI is a C/D (57.9%) with the main impacts being flood events. Grazing and trampling, water abstraction and presence of exotic species. PES is C/D and the PES Ecostatus is a C/D (57.9%).

 Marginal zone: Reeds and sedges are the dominate vegetation type. The substrate consist mainly of alluvial sand. The following grass and sedge species occur: Cynodon dactylon, Persicaria decipiens, Commelina diffusa subsp. scandens, Phragmites australis, Typha capensis, Cyperus dives, Cyperus sexangularis, Leersia hexandra etc. Exotic vegetation such as: macrophyte Eichhornia crassipes occurs along the edge of the active channel. Other exotic species, such as Ricinus communis, Centella asiatica, Sesbania bispinosa, etc. occur.

 Non-marginal zone: Reeds with scattered trees and shrub species are the dominate vegetation type. Continuous grazing and trampling has resulted in the reeds and trees being

PROPOSED TENBOSCH TIMESHARE RESORT 21

stunted. The woody species are obviously recovering after major flood destruction in the not- too-distant past. The substrate consists mainly of alluvial material and rocky dykes crossing the riverine area. The following woody species are dominant: Dichrostachys cinerea, Gymnosporia senegalensis, Ziziphus mucronata, Lippia javanica, Bridelia micrantha, Acacia nigrescens, Philenoptera violacea, Phyllanthus reticulatus, Pluchea dioscoridis, Gomphocarpus physocarpus, Asparagus cooperi, etc. Grass species such as Cynodon dactylon, Setaria sphacelata and Panicum maximum, are also present. Cyperus sexangularis and Schoenoplectus spp. are the dominant sedges. Some exotic vegetation such as, Centella asiatica, Spathodea campanulata, Melia azedarach, Solanum mauritianum, Lantana camara, Parthenium hysterophorus, Ageratum conyzoides, etc. were also identified.

Refer to Appendix D.2 for the full Wetland Report. 20. VISUAL

A visual impact assessment was undertaken by NuLeaf Planning and Environmental in order to determine the possible visual impact of the proposed timeshare resort located on Tenbosch Farm. The study area lies adjacent to the Kruger National Park boundary on the southern bank of the Crocodile River between the town of Marloth Park to the west and the Crocodile Bridge Gate to the east. Land cover within the study area is characterised by a moderately developed shrub layer and a dense herbaceous layer. Land use is deemed predominately cultivation. The visual quality of the broader study area is high, generally as a result of the lack of development and the large areas given over to conservation within the region. There is no evidence of widespread erosion or natural degradation, and development, where this occurs, is domestic in scale. Viewer incidence is expected to be the highest along the roads surrounding the proposed development area and the properties directly adjacent to the site. Second to these are homesteads in close proximity to the proposed site. Tourists using the roads, residents of the area and tourist accommodation are considered the most sensitive to visual intrusion as they will be exposed to visual intrusion during their rest and relaxation times. Tourists within the neighbouring Kruger National Park, including visitors to the nearby lodges and tourists making use of internal game drive routes, represent additional visual receptors. The overall visual absorption capacity (VAC) is low-medium. Refer to Appendix D5 for the full Visual Impact Assessment.

SECTION C: PUBLIC PARTICIPATION 1. ADVERTISEMENT AND NOTICE

An advertisement was placed in the Lowvelder, a local publication, on 13 May 2016. Site notices were placed at the following locations in and around the proposed property on 10 May 2016:

Site Notice Position Latitude Longitude Entrance gate to the proposed S25°23'18.34" E31°53'22.84" property Entrance gate to the proposed S25°23'15.18" E31°53'4.51" property

PROPOSED TENBOSCH TIMESHARE RESORT 22

Spar in Komatipoort S25°26'11.89" E31°57'35.75" Crocodile Bridge Gate Reception - -

2. DETERMINATION OF APPROPRIATE MEASURES

The following details the measures taken to include all potential I&APs as required by Regulation 41(2)(e) and 41(6) of GN 733:

 A list of interested and affected parties (I&AP’s), as well as, compliance authorities was compiled inclusive of Local and District Municipalities, local landowners and environmental organizations.  Written notification of the proposed development, including a background information document, was sent to all identified I&AP’s and Compliance Authorities on 13 May 2016.  A printed advertisement was placed in the Lowvelder, a local publication, on the 13 May 2016.  Site notices were placed at the entrances to the affected property, Crocodile Bridge Gate Reception, and the local Spar in Komatipoort on 10 May 2016. The following key stakeholders (other than organs of state) identified in terms of Regulation 41(2)(b) of GN 733 were notified:

Name Affiliation Contact Details Cheryl Venter Buckler’s Africa Lodge [email protected] Sascha Hippo Hills Lodge [email protected] Mike Klopper Elephant Walk Retreat [email protected] Tracy-lee Peterson SANParks [email protected] Greg Beyers RCL Foods Sugar and Milling/ [email protected] Libuyile Farming Services Ronelle Putter Crocodile River Major Irrigation [email protected] Board Gerhard Kuhn Tenbosch Irrigation Board [email protected] Proof of stakeholder engagement is included in Appendix E.2.

3. ISSUES RAISED BY INTERESTED AND AFFECTED PARTIES

Interested and Affected Party Issue Tracy-Lee Petersen (SANParks) Potential negative impact the development could have on the KNP RCL Foods Sugar and Milling Water quantity and availability Water quality and waste Impact of existing farming activities in the area on the proposed development

4. COMMENTS AND RESPONSE REPORT

No comments have been received.

PROPOSED TENBOSCH TIMESHARE RESORT 23

5. AUTHORITY PARTICIPATION

Authorities and organs of state identified as key stakeholders:

Authority/ Organ of State Contact Person Contact Details DARDLEA Robyn Luyt [email protected] Ehlanzeni District Municipality Pretty Masego [email protected] Nkomazi Local Municipality Shirely Shabungu [email protected] DAFF Themba Khoza [email protected] MTPA Johan Eksteen [email protected] DWS Silo Kheva [email protected]

Refer to Appendix E.4 for proof that the Authorities and Organs of State received written notification of the proposed activities. 6. CONSULTATION WITH OTHER STAKEHOLDERS

Refer to Appendix E.5 for a list of registered I&APs.

SECTION D: IMPACT ASSESSMENT 1. IMPACTS THAT MAY RESULT FROM THE PLANNING AND DESIGN, CONSTRUCTION, OPERATIONAL, DECOMMISSIONING AND CLOSURE PHASES AS WELL AS PROPOSED MANAGEMENT OF IDENTIFIED IMPACTS AND PROPOSED MITIGATION MEASURES

1.1. Potential impacts

All potential environmental impacts, both positive and negative, have been identified for the entire lifecycle of the project i.e. Planning / design, construction and operations. The decommissioning of the proposed development is not anticipated and has therefore not been assessed.

1.1.1. Planning and Design Phase

Planning and design phase impacts refer to those impacts that may be mitigated through planning decisions.

Direct Impacts:

GROUND WATER

 None.

SURFACE WATER

 Risk to ecological and hydrological function of the riparian habitat along the Crocodile River due to the placement of structures and infrastructure within the habitat/ buffer zones.  Risk to hydrological function (quality and fluctuation properties) along the Crocodile River and drainage lines due to activity and disturbance within the watercourse.

PROPOSED TENBOSCH TIMESHARE RESORT 24

SOIL

 Erosion risk to soils due to increased hard surface and associated increase in storm water runoff.

AIR

 None.

BIODIVERSITY (FLORA)

 Risk to Tshokwane-Hlane Basalt Lowveld vegetation classified as Least Threatened and associated loss of species richness due to the placement of structures and infrastructure.  Risk to sensitive habitats due to the placement of structures and infrastructure.  Risk to plant species of conservation importance and protected trees due to the placement of structures and infrastructure within the habitat.

BIODIVERSITY (FAUNA)

 Risk to faunal habitat and habitat fragmentation due to removal and alteration of the existing habitat and the development of structures and infrastructure.

LAND USE AND AGRICULTURAL POTENTIAL

 Loss of potentially arable land due to the development of permanent structures and infrastructure.

HERITAGE

 None.

VISUAL

 Risk to visual quality of the surrounding area and sense of place due to the development of structures and infrastructure within an otherwise natural environment.  Risk of lighting impact at night due to the operation of the Resort.

SOCIO-ECONOMICS

 None.

MUNICIPAL SERVICES AND TRAFFIC

 None.

Indirect Impacts:

 None.

Cumulative Impacts:

BIODIVERSITY (FLORA)

PROPOSED TENBOSCH TIMESHARE RESORT 25

 Cumulative loss of Tshokwane-Hlane Basalt Lowveld vegetation classified as Least Threatened and associated loss of species richness.  Cumulative loss of sensitive habitats.  Cumulative reduction of plant species of conservation importance and protected trees.

BIODIVERSITY (FAUNA)

 Cumulative loss of faunal habitat.

1.1.2. Construction Phase

Direct Impacts:

GROUND WATER

 Depletion of ground water due to overuse and waste during construction activities.  Pollution and contamination of ground water due to surface runoff, unmanaged sewage discharge, leaks and spills, solvent, paints and chemical spills, hydrocarbon and fuel leaks and spills.

SURFACE WATER

 Disturbance and loss of ecological function of the habitat (physical structure) along the Crocodile River and drainage lines due to clearing and destruction of riparian and wetland vegetation, loss of fringing vegetation and erosion of denuded areas, invasion by alien invasive trees and plants, alteration in natural fire regimes, shading of natural vegetation.  Pollution and contamination of surface water resources.  Disturbance and loss of hydrological function (quality and fluctuation properties) of the Crocodile River and the drainage lines

SOIL

 Soil contamination and pollution.  Soil erosion by wind and rain due to the removal of stabilising vegetation, soil compaction, decrease in water infiltration and an increase of water runoff in construction areas. AIR

 Air pollution due emissions from construction vehicles and equipment.  Dust liberated by general construction activities and movement of construction vehicles.

BIODIVERSITY (FLORA)

 Removal of invader alien species found on site (positive impact).  Loss of Tshokwane-Hlane Basalt Lowveld vegetation classified as Least Threatened and associated loss of species richness due to site clearing ahead of construction, general construction activities and movement of construction vehicles, unmanaged sewage discharge, leaks and spills, solvent, paints and chemical spills, hydrocarbon and fuel leaks and spills, litter and other inert construction waste.  Destruction and damage to Conservation important and protected trees.

BIODIVERSITY (FAUNA)

PROPOSED TENBOSCH TIMESHARE RESORT 26

 Loss of faunal habitat due to site clearing ahead of construction, general construction activities and movement of construction vehicles, construction dust, construction material, litter and other inert construction waste.  Loss of general faunal habitat and ecological connectivity.  Mortality of fauna due to dangerous trenches and excavations, persecution and extermination, solvent, paints and chemical spills (poisoning), construction material, litter and other inert construction waste (suffocation), collisions with construction vehicles.  Poaching and snaring of fauna on site and in the greater Kruger National park by construction staff.

LAND USE AND AGRICULTURAL POTENTIAL

 None.

HERITAGE

 Possible discovery of new important artefacts (Positive Impact).  Damage to and / or destruction of archaeological, paleontological or historical artefacts unearthed during construction due to site clearing ahead of construction, general construction activities and movement of construction vehicles. VISUAL

 The visual impact of construction, lighting and dust on adjacent tourism developments and KNP tourists  Visual impact of construction, lighting and dust on observers travelling along game drive routes within the KNP  The visual impact of construction, lighting and dust on locals using the District Road owing to the presence of construction equipment, camps and workers

SOCIO-ECONOMICS

 Stimulation of the local economy, especially the local service delivery industry (i.e. accommodation, catering, cleaning, transport and security, etc.) (positive impact).  Creation of short-term employment and business opportunities and the opportunity for skills development and on-site training (Positive impact).  Noise, dust and safety impacts and disturbance to KNP tourists and adjacent tourism developments.  Increase in casual workers and associated increase in poaching.

MUNICIPAL SERVICES AND TRAFFIC

 Increase in traffic on the D1870 and other local roads due to construction vehicles.  Increase in the number and frequency of construction vehicles accessing the site and the resultant noise, dust, and safety impacts on other road users, residents of the local community and adjacent tourism developments.

Indirect Impacts:

BIODIVERSITY (FLORA)

 Loss of floral biodiversity, plant species of conservation importance and protected trees due to increased incidence of veld fires.

SOCIO-ECONOMICS

PROPOSED TENBOSCH TIMESHARE RESORT 27

 Loss of property and threat to human life due to increased incidence of veld fires.

TRAFFIC AND SERVICES

 Degradation of local roads due to the increase in the numbers of heavy vehicles.

Cumulative Impacts:

BIODIVERSITY (FLORA)

 Cumulative loss of Tshokwane-Hlane Basalt Lowveld vegetation classified as Least Threatened and associated loss of species richness.  Cumulative loss of ecological function of sensitive habitats, specifically riparian zones.  Cumulative reduction and damage to Conservation important species and protected trees.

BIODIVERSITY (FAUNA)

 Cumulative loss of faunal habitat.

SOCIO-ECONOMICS

 Community upliftment and the opportunity to up-grade and improve skills levels in the area (positive impact).

SERVICES AND TRAFFIC

 Cumulative increase in traffic and the resultant noise, dust, and safety impacts on other road users, residents of the local community and adjacent tourism developments.

1.1.3. Operational Phase

Direct Impacts:

GROUND WATER

 Depletion of ground water resources due to over use and waste during operation.  Pollution and contamination of ground water due to unmanaged storm water runoff, unmanaged sewage discharge, sewage leaks and spills, herbicides, pesticides and fertilisers, discharge and spill of solvents, paints, chemicals and cleaning products, discharge and spill of hydrocarbons and fuel.

SURFACE WATER

 Disturbance and loss of ecological function of the habitat (physical structure) along the Crocodile River and drainage lines  Pollution and contamination of surface water due to unmanaged storm water runoff, litter and uncontrolled waste, sewage leaks and spills, herbicides, pesticides and fertilisers.  Disturbance and loss of hydrological function (quality and fluctuation properties) along the Crocodile and drainage lines

SOIL

 Soil contamination and pollution.

PROPOSED TENBOSCH TIMESHARE RESORT 28

 Soil erosion due to soil compaction by uncontrolled movement of staff and guests (especially vehicles), runoff over exposed or cleared areas that have failed to rehabilitate.

AIR

 Air pollution by emissions from increased number of vehicles

BIODIVERSITY (FLORA)

 Loss of Tshokwane-Hlane Basalt Lowveld vegetation classified as Least Threatened and associated loss of species richness due to uncontrolled vegetation clearing and access by staff and guests, encroachment of alien invasive species, litter and waste.  Disturbance of sensitive habitats, specifically riparian zones  Destruction and damage to Conservation important species and protected trees due to uncontrolled vegetation clearing and access by staff and guests.  Increase in exotic vegetation/alien species and bush encroachment into disturbed soils and areas in the event that the rehabilitation process is not successful.

BIODIVERSITY (FAUNA)

 Loss of faunal habitat due to uncontrolled vegetation clearing and access by staff and guests, encroachment of alien invasive species, litter and waste.  Faunal disturbances, displacement of taxa and changes in distribution and abundance due to uncontrolled vegetation clearing and access by staff and guests, general operations (activities) of the facility, noise from guests, staff and vehicles,  Mortality of fauna due to persecution and extermination, solvents, paints, chemicals and cleaning products (poisoning), litter and waste (suffocation).  Poaching and snaring of faunal species by staff.

LAND USE AND AGRICULTURAL POTENTIAL

 None.

HERITAGE

 None.

VISUAL

 Visual Impact of the timeshare resort and infrastructure on KNP tourists using game drive routes  Visual Impact of the timeshare resort on protected and conservation areas (i.e. KNP)  Visual impact of the resort on observers travelling along local roads  Visual Impact of the resort and infrastructure on adjacent tourism developments.  Visual Impact of lighting of the resort on adjacent tourism developments and observers residing in close proximity.  Impact on the character of the landscape and sense of place of the region

SOCIO-ECONOMICS

 Stimulation of the local economy, especially the local service delivery industry (accommodation, catering, cleaning, transport, security etc.) (positive impact).  Creation of long term employment and business opportunities as well as opportunities for skills development and transfer (positive impact).

PROPOSED TENBOSCH TIMESHARE RESORT 29

 Creation of opportunities for local SMME’s (positive impact).

MUNICIPAL SERVICES AND TRAFFIC

 Operational cost of running services and infrastructure, specifically electricity  Increase in traffic on the D1870 and on other roads due to increased visitor numbers.  Increase in the number and frequency of vehicles accessing the site, and the resultant noise, dust, and safety impacts on other road users, residents of the local community and adjacent tourism developments.

Indirect Impacts:

VISUAL

 Visual impact of the proposed development of the timeshare resort on the sense of place and visual character of the region.

Cumulative Impacts:

BIODIVERSITY (FLORA)

 Cumulative loss of Tshokwane-Hlane Basalt Lowveld vegetation classified as Least Threatened and associated loss of species richness.  Cumulative disturbance of sensitive habitats, specifically riparian zones  Cumulative reduction and damage to Conservation important and protected trees.

HERITAGE

 None.

VISUAL

 The accumulation of built forms and within an otherwise natural environment.

SOCIO-ECONOMIC

 Creation of permanent employment and skills and development opportunities for members from the local community and creation of additional business and economic opportunities in the area (positive impact).  Promotion of social and economic development in the local communities and improvement in the overall wellbeing of the community (positive impact).

SERVICES AND TRAFFIC

 Cumulative increase in traffic on the D1870 and on other roads due to increased visitor numbers.  Cumulative increase in the number and frequency of vehicles accessing the site, and the resultant noise, dust, and safety impacts for other road users, adjacent tourism development and residents of the local communities.

1.1.4. Decommissioning Phase

The decommissioning of the facility is not anticipated at this stage and, therefore, no impacts are anticipated

PROPOSED TENBOSCH TIMESHARE RESORT 30

1.2. Impact assessment

Activity Impact summary Significance Proposed mitigation Preferred Alternative (Alternative 1) Planning and Direct impacts: Design Phase Ground Water None. Hydrology (Surface Water) Risk to ecological function of the 30  Planning and compliance, including ground riparian habitat along the Crocodile L water, surface water and storm water River management as per the EMPr (section 7.1). Risk to hydrological function 33  Development footprint planning as per the (quality and fluctuation properties) M EMPr (section 7.2). along the Crocodile River and drainage lines Soil Erosion risk to soils 18  Planning and compliance, including ground L water, surface water, storm water management and waste management as per the EMPr (section 7.1).  Development footprint planning as per the EMPr (section 7.2). Air None. Biodiversity (Flora) Risk to Tshokwane-Hlane Basalt 27  Planning and compliance, including protected Lowveld vegetation classified as L species, storm water management and waste Least Threatened management as per the EMPr (section 7.1). Risk to sensitive habitats, 22  Development footprint planning as per the specifically riparian zones L EMPr (section 7.2). Risk to plant species of 36 conservation importance: M protected trees Sclerocarya birrea subsp. cafra, Combretum imberbe and Philenoptera violacea and provincially protected species Aloe marlothii and Crinum stuhlmannii Biodiversity (Fauna) Risk to Riparian forest, Closed 27  Planning and compliance, including protected Woodland and wetland faunal L species, storm water management and waste habitat and habitat fragmentation management as per the EMPr (section 7.1).  Development footprint planning as per the EMPr (section 7.2). Land use and Agricultural potential Loss of potentially arable land 14  Development footprint planning as per the L EMPr (section 7.2). Heritage None. Visual Risk to visual quality of the 22  Development footprint planning as per the surrounding area and sense of L EMPr (section 7.2). place  Visual environment planning as per the EMPr Risk of lighting impact at night due 33 (section 7.3). to the operation of the Resort. M Socio-economic None. Municipal services and Traffic None.

PROPOSED TENBOSCH TIMESHARE RESORT 31

Activity Impact summary Significance Proposed mitigation Indirect impacts: None. Cumulative impacts:

Biodiversity (Flora) Cumulative loss of Tshokwane- 27  Planning and compliance, including protected Hlane Basalt Lowveld vegetation L species, storm water management and waste classified as Least Threatened management as per the EMPr (section 7.1). Cumulative loss of sensitive 22  Development footprint planning as per the habitats, specifically riparian zones L EMPr (section 7.2). Cumulative reduction of plant 36 species of conservation M importance: protected trees Sclerocarya birrea subsp. cafra, Combretum imberbe and Philenoptera violacea and provincially protected species Aloe marlothii and Crinum stuhlmannii Biodiversity (Fauna) Cumulative loss of Riparian forest, 24  Planning and compliance, including protected Closed Woodland and wetland L species, storm water management and waste faunal habitat. management as per the EMPr (section 7.1).  Development footprint planning as per the EMPr (section 7.2). Construction Direct impacts: Phase Ground Water Depletion of ground water due to 18  Pre-construction planning, including planning overuse and waste during L and preparation as per the EMPr (section 8.1) construction activities  Site establishment, including site Pollution and contamination of 18 demarcation, accommodation, pollution ground water L control and access roads as per the EMPr (section 8.2)  Materials management, including solid, liquid and hazardous waste, concrete and cement work, fuel and hazardous material as per the EMPr (section 8.3).  Vehicles and equipment management as per the EMPr (section 8.7). Hydrology (Surface Water) Disturbance and loss of ecological 14  Pre-construction planning, including planning function of the habitat (physical L and preparation as per the EMPr (section 8.1) structure) along the Crocodile  Site establishment, including site River and drainage lines demarcation, accommodation, pollution Pollution and contamination of 18 control, access roads and protection of the surface water of the Crocodile L riparian system as per the EMPr (section 8.2) River and drainage lines  Materials management, including solid, liquid Disturbance and loss of 22 and hazardous waste, concrete and cement hydrological function (quality and L work, fuel and hazardous material as per the fluctuation properties) of the EMPr (section 8.3). Crocodile River and the drainage  Stockpiles, storage and handling as per the lines EMPr (section 8.4).  Erosion control, including water management, storm water management, excavation, backfilling and trenching as per the EMPr (section 8.5).  Alien plant control as per the EMPr (section 8.6).

PROPOSED TENBOSCH TIMESHARE RESORT 32

Activity Impact summary Significance Proposed mitigation  Vehicles and equipment management as per the EMPr (section 8.7).  Socio-economic management, including staff, visual as per the EMPr (section 8.8).  Fire management as per the EMPr (section 8.9).  Rehabilitation as per the EMPr (section 8.10). Soil Soil contamination and pollution 14  Pre-construction planning, including planning L and preparation as per the EMPr (section 8.1) Soil erosion by wind and rain 18  Site establishment, including site L demarcation, accommodation, pollution control and access roads as per the EMPr (section 8.2)  Materials management, including solid, liquid and hazardous waste, concrete and cement work, fuel and hazardous material as per the EMPr (section 8.3).  Stockpiles, storage and handling as per the EMPr (section 8.4).  Erosion control, including water management, storm water management, excavation, backfilling and trenching as per the EMPr (section 8.5).  Vehicles and equipment management as per the EMPr (section 8.7).  Rehabilitation as per the EMPr (section 8.10). Air Air pollution due emissions from 24  Site establishment, including site construction vehicles and L demarcation, accommodation, pollution equipment. control and access roads as per the EMPr Dust liberated by general 21 (section 8.2) construction activities and L  Stockpiles, storage and handling as per the movement of construction EMPr (section 8.4). vehicles.  Erosion control, including water management, Smoke from open fires used by 14 storm water management, excavation, site staff for heating and cooking L backfilling and trenching as per the EMPr as well as from uncontrolled fires (section 8.5).  Vehicles and equipment management as per the EMPr (section 8.7).  Socio-economic management, including visual as per the EMPr (section 8.8).  Fire management as per the EMPr (section 8.9).  Rehabilitation as per the EMPr (section 8.10). Biodiversity (Flora) Removal of invader alien species 30  Pre-construction planning, including planning found on site (positive impact). L and preparation as per the EMPr (section 8.1) Loss of Tshokwane-Hlane Basalt 28  Site establishment, including site Lowveld vegetation classified as L demarcation, accommodation, pollution Least Threatened control, access roads, protection of flora, and Disturbance of sensitive habitats, 26 protection of the riparian system as per the specifically riparian zones L EMPr (section 8.2) Destruction and damage to plant 20  Materials management, including solid, liquid species of conservation L and hazardous waste, concrete and cement importance: protected trees work, fuel and hazardous material as per the Sclerocarya birrea subsp. cafra,

PROPOSED TENBOSCH TIMESHARE RESORT 33

Activity Impact summary Significance Proposed mitigation Combretum imberbe and EMPr (section 8.3). Philenoptera violacea and  Stockpiles, storage and handling as per the provincially protected species Aloe EMPr (section 8.4). marlothii and Crinum stuhlmanni  Erosion control, including water management, Increase in exotic vegetation/alien 22 storm water management, excavation, species and bush encroachment L backfilling and trenching as per the EMPr into disturbed soils and areas (section 8.5).  Alien plant control as per the EMPr (section 8.6).  Vehicles and equipment management as per the EMPr (section 8.7).  Fire management as per the EMPr (section 8.9).  Rehabilitation as per the EMPr (section 8.10). Biodiversity (Fauna) Loss of faunal habitat 20  Pre-construction planning, including planning L and preparation as per the EMPr (section 8.1) Loss of general faunal habitat and 33  Site establishment, including site ecological connectivity. M demarcation, accommodation, pollution Mortality of fauna 14 control, access roads, protection of flora and L protection of fauna as per the EMPr (section Poaching and snaring of fauna on 18 8.2) site and in the greater Kruger L  Materials management, including solid, liquid National Park and hazardous waste, concrete and cement work, fuel and hazardous material as per the EMPr (section 8.3).  Erosion control, including excavation, backfilling and trenching as per the EMPr (section 8.5).  Alien plant control as per the EMPr (section 8.6).  Vehicles and equipment management as per the EMPr (section 8.7).  Socio-economic management, including staff as per the EMPr (section 8.8).  Fire management as per the EMPr (section 8.9).  Rehabilitation as per the EMPr (section 8.10). Land use and Agricultural potential None. Heritage Damage to and / or destruction of 8  Pre-construction planning, including planning archaeological, paleontological or N and preparation as per the EMPr (section 8.1) historical artefacts unearthed  Site establishment, including site during construction demarcation, access roads and protection of cultural heritage as per the EMPr (section 8.2) Visual Visual impact of construction, 21  Pre-construction planning, including planning lighting and dust on adjacent L and preparation as per the EMPr (section 8.1) tourism developments and KNP  Site establishment, including site tourists demarcation, accommodation, pollution Visual impact of construction, 14 control and access roads as per the EMPr lighting and dust on observers L (section 8.2) travelling along game drive routes  Materials management, including solid, liquid within the KNP and hazardous waste, concrete and cement The visual impact of construction, 21 work, fuel and hazardous material as per the lighting and dust on locals using L EMPr (section 8.3).

PROPOSED TENBOSCH TIMESHARE RESORT 34

Activity Impact summary Significance Proposed mitigation the District Road  Stockpiles, storage and handling as per the EMPr (section 8.4).  Erosion control, including water management, storm water management, excavation, backfilling and trenching as per the EMPr (section 8.5).  Vehicles and equipment management as per the EMPr (section 8.7).  Socio-economic management, including staff, visual as per the EMPr (section 8.8).  Fire management as per the EMPr (section 8.9).  Rehabilitation as per the EMPr (section 8.10). Socio-economic Stimulation of the local economy, 24  Socio-economic planning as per the EMPR especially the local service delivery L (section 7.4). industry (i.e. accommodation,  Pre-construction planning, including planning catering, cleaning, transport and and preparation as per the EMPr (section 8.1) security, etc.)(positive impact)  Site establishment, including accommodation Creation of short-term employment 40 and access roads as per the EMPr (section and business opportunities and the M 8.2) opportunity for skills development  Vehicles and equipment management as per and on-site training (Positive the EMPr (section 8.7). impact).  Socio-economic management, including staff Noise, dust and safety impacts and 21 as per the EMPr (section 8.8). disturbance to adjacent tourism L  Fire management as per the EMPr (section developments and KNP 8.9). An increase in construction 21 workers and associated increase L in social problems for the community Increase in casual workers and 28 associated increase in poaching. L Increased risk of veld fires due to 24 the presence of construction L workers on site. Municipal services and Traffic Increase in traffic on the D1870 21  Pre-construction planning, including planning and on other local roads due to L and preparation as per the EMPr (section 8.1) construction vehicles.  Site establishment, including access roads as Increase in the number and 15 per the EMPr (section 8.2) frequency of construction vehicles L  Vehicles and equipment management as per accessing the site and the the EMPr (section 8.7). resultant noise, dust, and safety  Socio-economic management, including impacts on other road users, visual as per the EMPr (section 8.8). residents of the local community and adjacent tourism developments. Indirect impacts: Biodiversity (Flora) Loss of floral biodiversity, Red data 16  As above species and protected trees due to L increased incidence of veld fires Socio-economics Loss of property and threat to 16  As above human life due to increased L incidence of veld fires

PROPOSED TENBOSCH TIMESHARE RESORT 35

Activity Impact summary Significance Proposed mitigation Traffic and services Degradation of local roads due to 21  As above the increase in the numbers of L heavy vehicles. Cumulative impacts: Biodiversity (Flora) Cumulative loss of Tshokwane- 18  Pre-construction planning, including planning Hlane Basalt Lowveld vegetation L and preparation as per the EMPr (section 8.1) classified as Least Threatened and  Site establishment, including site associated loss of species demarcation, accommodation, pollution richness. control, access roads, protection of flora, and Cumulative loss of ecological 26 protection of the riparian system as per the function of sensitive habitats, L EMPr (section 8.2) specifically riparian zones.  Materials management, including solid, liquid Cumulative reduction and damage 24 and hazardous waste, concrete and cement to plant species of conservation L work, fuel and hazardous material as per the importance: protected trees EMPr (section 8.3). (Sclerocarya birrea subsp. cafra,  Stockpiles, storage and handling as per the Combretum imberbe and EMPr (section 8.4). Philenoptera violacea and  Erosion control, including water management, provincially protected species Aloe storm water management, excavation, marlothii and Crinum stuhlmanni) backfilling and trenching as per the EMPr (section 8.5).  Alien plant control as per the EMPr (section 8.6).  Vehicles and equipment management as per the EMPr (section 8.7).  Fire management as per the EMPr (section 8.9).  Rehabilitation as per the EMPr (section 8.10). Biodiversity (Fauna) Cumulative loss of faunal habitat. 20  Pre-construction planning, including planning L and preparation as per the EMPr (section 8.1)  Site establishment, including site demarcation, accommodation, pollution control, access roads, protection of flora, and protection of fauna as per the EMPr (section 8.2)  Materials management, including solid, liquid and hazardous waste, concrete and cement work, fuel and hazardous material as per the EMPr (section 8.3).  Erosion control, including excavation, backfilling and trenching as per the EMPr (section 8.5).  Alien plant control as per the EMPr (section 8.6).  Vehicles and equipment management as per the EMPr (section 8.7).  Socio-economic management, including staff as per the EMPr (section 8.8).  Fire management as per the EMPr (section 8.9).  Rehabilitation as per the EMPr (section 8.10). Socio-economics Community upliftment and the 24  Socio-economic planning as per the EMPR opportunity to up-grade and L (section 7.4).

PROPOSED TENBOSCH TIMESHARE RESORT 36

Activity Impact summary Significance Proposed mitigation improve skills levels in the area  Pre-construction planning, including planning (positive impact) and preparation as per the EMPr (section 8.1)  Site establishment, including accommodation and access roads as per the EMPr (section 8.2)  Vehicles and equipment management as per the EMPr (section 8.7).  Socio-economic management, including staff as per the EMPr (section 8.8).  Fire management as per the EMPr (section 8.9). Traffic and services Cumulative increase in traffic and 16 the resultant noise, dust, and L  Pre-construction planning, including planning safety impacts on other road and preparation as per the EMPr (section 8.1) users, residents of the local  Site establishment, including access roads as community and adjacent tourism per the EMPr (section 8.2) developments.  Vehicles and equipment management as per the EMPr (section 8.7).  Socio-economic management, including visual as per the EMPr (section 8.8). Operational Direct impacts: Phase Ground Water Depletion of ground water 18  Biodiversity management, including access resources due to over use and L roads and resource management as per the waste during operation. EMPr (section 9.1) Pollution and contamination of 22  Materials management, including solid liquid ground water L and hazardous waste, fuel and hazardous material as per the EMPr (section 9.2)  Erosion control as per the EMPr (section 9.3)  Socio economic management, including staff management as per the EMPR (section 9.5)  Vehicles and equipment management as per the EMPr (section 9.4) Hydrology (Surface Water) Disturbance and loss of ecological 18  Biodiversity management, including access function of the habitat (physical L roads, resource management, protection of structure) along the Crocodile flora and alien plant control as per the EMPr River and drainage lines (section 9.1) Pollution and contamination of 20  Materials management, including solid, liquid surface water L and hazardous waste, fuel and hazardous Disturbance and loss of 18 material as per the EMPR (section 9.2) hydrological function (quality and L  Erosion control as per the EMPr (section 9.3) fluctuation properties) along the  Vehicles and equipment management as per Crocodile and drainage lines the EMPr (section 9.4)  Socio economic management, including staff management as per the EMPR (section 9.5)  Fire management as per the EMPR (section 9.6) Soil Soil contamination and pollution 18  Biodiversity management, including access L roads, resource management, protection of Soil erosion 18 flora and alien plant control as per the EMPr L (section 9.1)  Materials management, including solid liquid and hazardous waste, fuel and hazardous material as per the EMPR (section 9.2)

PROPOSED TENBOSCH TIMESHARE RESORT 37

Activity Impact summary Significance Proposed mitigation  Erosion control as per the EMPr (section 9.3)  Vehicles and equipment management as per the EMPr (section 9.4)  Socio economic management, including staff management as per the EMPR (section 9.5) Air Air pollution by emissions from 33  Socio economic management, including staff increased numbers of vehicles M management as per the EMPr (section 9.5) Biodiversity (Flora) Loss of Tshokwane-Hlane Basalt 18  Biodiversity management, including access Lowveld vegetation classified as L roads, resource management, protection of Least Threatened and associated flora and alien plant control as per the EMPr loss of species richness (section 9.1) Disturbance of sensitive habitats, 18  Materials management, including solid liquid specifically riparian zones L and hazardous waste, fuel and hazardous Destruction and damage to plant 20 material as per the EMPR (section 9.2) species of conservation L  Erosion control as per the EMPr (section 9.3) importance: protected trees  Vehicles and equipment management as per (Sclerocarya birrea subsp. cafra, the EMPr (section 9.4) Combretum imberbe and  Socio economic management, including staff Philenoptera violacea and management as per the EMPR (section 9.5) provincially protected species Aloe  Fire management as per the EMPR (section marlothii and Crinum stuhlmanni) 9.6) Increase in exotic vegetation/alien 24 species and bush encroachment L into disturbed soils and areas in the event that the rehabilitation process is not successful. Biodiversity (Fauna) Loss of faunal habitat 18  Biodiversity management, including access L roads, resource management, protection of Faunal disturbances, displacement 18 flora, alien plant control and protection of of taxa and changes in distribution L fauna as per the EMPr (section 9.1) and abundance  Materials management, including solid liquid Mortality of fauna 20 and hazardous waste, fuel and hazardous L material as per the EMPR (section 9.2) Poaching and snaring of faunal 24  Erosion control as per the EMPr (section 9.3) species by staff. L  Vehicles and equipment management as per the EMPr (section 9.4)  Socio economic management, including staff management, and visual impact management as per the EMPR (section 9.5)  Fire management as per the EMPr (section 9.6) Land use and Agricultural potential None.  Heritage None.  Visual Visual Impact of the timeshare 16  Socio economic management, including staff resort and infrastructure on KNP L management and visual impact management tourists using game drive routes as per the EMPr (section 9.5) Visual Impact of the timeshare 16 resort on protected and L conservation areas (i.e. KNP) Visual impact of the resort on 8 observers travelling along local N

PROPOSED TENBOSCH TIMESHARE RESORT 38

Activity Impact summary Significance Proposed mitigation roads Visual Impact of the resort and 16 infrastructure on adjacent tourism L developments. Visual Impact of lighting of the 20 resort on adjacent tourism L developments and observers residing in close proximity. Impact on the character of the 22 landscape and sense of place of L the region Socio-economic Stimulation of the local economy, 33  Socio economic management, including staff especially the local service delivery M management, and visual impact management industry (accommodation, catering, as per the EMPr (section 9.5) cleaning, transport, security etc.) (positive impact) Creation of long term employment 60 and business opportunities as well H as opportunities for skills development and transfer (positive impact) Creation of opportunities for local 52 SMME’s (positive impact) M Noise impact on conservation 21 areas within the region, specifically L KNP Municipal services and Traffic Operational cost of running 44  Socio economic management, including staff services and infrastructure, M management and visual impact management specifically electricity as per the EMPR (section 9.5) Increase in traffic on the D1870 30 and on other roads due to L increased visitor numbers. Increase in the number and 22 frequency of vehicles accessing L the site, and the resultant noise, dust, and safety impacts on other road users, residents of the local community and adjacent tourism developments. Indirect impacts: Visual Visual impact of the proposed 24  Socio economic management, including staff development of the timeshare L management, and visual impact management resort on the sense of place and as per the EMPr (section 9.5) visual character of the region. Cumulative impacts: Biodiversity (Flora) Cumulative loss of Tshokwane- 22  Biodiversity management, including access Hlane Basalt Lowveld vegetation L roads, resource management, protection of classified as Least Threatened and flora and alien plant control as per the EMPr associated loss of species (section 9.1) richness..  Materials management, including solid liquid Cumulative disturbance of 22 and hazardous waste, fuel and hazardous sensitive habitats, specifically L material as per the EMPr (section 9.2) riparian zones  Erosion control as per the EMPr (section 9.3) Cumulative reduction and damage 24

PROPOSED TENBOSCH TIMESHARE RESORT 39

Activity Impact summary Significance Proposed mitigation to plant species of conservation L  Vehicles and equipment management as per importance: protected trees the EMPr (section 9.4) (Sclerocarya birrea subsp. cafra,  Socio economic management, including staff Combretum imberbe and management as per the EMPr (section 9.5) Philenoptera violacea and  Fire management as per the EMPr (section provincially protected species Aloe 9.6) marlothii and Crinum stuhlmanni) Visual The accumulation of built forms 22  Socio economic management, including and within an otherwise natural L staff management and visual impact environment. management as per the EMPr (section 9.5) Socio-economics Creation of permanent 33  Socio economic management, including employment and skills and M staff management and visual impact development opportunities for management as per the EMPr (section 9.5) members from the local community and creation of additional business and economic opportunities in the area (positive impact) Promotion of social and economic 27 development in the local L communities and improvement in the overall wellbeing of the community (positive impact) Services and traffic Cumulative increase in traffic on 22  Planning and compliance, including waste the D1870 and on other roads due L management as per the EMPr (section 7.1) to increased visitor numbers.  Materials management, including solid liquid Cumulative increase in the number 22 and hazardous waste, fuel and hazardous and frequency of vehicles L material as per the EMPR (section 9.2) accessing the site, and the  Socio economic management, including staff resultant noise, dust, and safety management, and visual impact management impacts for other road users, as per the EMPr (section 9.5) adjacent tourism development and residents of the local communities.

Please refer to Appendix F for the full impact assessment 2. ENVIRONMENTAL IMPACT STATEMENT

The majority of the terrestrial ecosystems of Tenbosch Farm lie within areas classified as Heavily/Moderately Modified Areas as per the MBSP. The remaining untransformed sections of the farm are classified as Other Natural Areas. Tenbosch also does not lie within a Threatened Ecosystem.

The development site is located within the ESA: Protected Area Buffer which is a buffer area of 10 Km around National Parks. The primary objective is to maintain or improve ecological and tourism functionality of the Protected Area (in this case the KNP). Permissible activities/land uses include low and high impact tourism and linear structures. In this regard, the development of a timeshare resort falls within the guidelines where majority of the development will fall within Heavily/Moderately modified areas and Other Natural Areas.

The dam located near the eastern boundary of the site is classified as an ESA: Wetland which is described as a non-FEPA wetland where the main objective is to maintain it in a natural state with limited loss of ecosystem, functionality or species without lowering the PES. Low impact tourism is the preferred land use. The dam has

PROPOSED TENBOSCH TIMESHARE RESORT 40 been declared as a no-go area for development with just 2 low impact bird hides/lookout points to be constructed along the edge of the dam.

The drainage lines (one near the centre of the site and the other near the eastern boundary) are classified as ESA: Important Sub catchment & Fish Support Area. The main objective is to maintain it in a natural state with limited loss of ecosystem or functionality without lowering the PES. Low impact tourism is preferable, followed by high impact tourism. The drainage lines have a high sensitivity rating and have been declared as no development zones. As a result, no development shall take place within these areas with the exception of the internal access road which will cross over the drainage line in the centre of the site at an existing crossing, thereby minimizing the impact.

Preferred Alternative: Alternative 1

Majority of the chalets in the western portion of the site fall within the Acacia nigrescens-Panicum maximum Disturbed Closed Woodland (Least Threatened) which has a moderate sensitivity rating, with the central recreation area, pool, tennis court and remaining chalets falling within Transformed vegetation community which has a low sensitivity rating. The chalets in the eastern portion of the farm, the pool and the maintenance facility and staff accommodation all lie within Transformed vegetation which has a low sensitivity rating. The recreation area, restaurant and clubhouse fall within Acacia nigrescens-Panicum maximum Disturbed Closed Woodland (Least Threatened) which has a moderate sensitivity rating.

All areas with a high sensitivity rating have been avoided and declared no-go areas for development, with the exception of 2 small low impact bird hides/lookout points. The area around the dam, while having a moderate biodiversity value, has been avoided and declared as a no-go area as per the specialist recommendation.

The Preferred Layout respects all recommended buffers, namely the riparian buffers around the watercourses. A 16 m buffer has been implemented around the dam in the east, a 15 m buffer around the drainage line near the centre of the site and a 67 m buffer has been implemented from the Crocodile River in the north. The 1:100 year flood line along the Crocodile River is also respected.

Species of conservation importance are found within the site.

In terms of fauna, Hippopotamus (Hippopotamus amphibious) listed as vulnerable was confirmed to occur on site, as well as, the Martial Eagle (Polemaetus bellicosus), the Nile Crocodile (Crocodylus niloticus) also listed as Vulnerable and the Southern African Python (Python natalensis) which is protected.

Sewage treatment will be via a waste water treatment plant. All the sewage from the reticulated sites within the development will be treated at this treatment plant. A sewage pump station or stations will be required to convey the sewage from the lowest positions to the plant. Outflow will be used for irrigation purposes.

Power will be supplied by the existing Eskom line located onsite. This existing line will be extended whereby an underground reticulation system will be installed to minimize the visual impact. Each unit will be supplied with a 60A single phase connection.

Statement:

The Preferred Alternative is deemed to have the lowest environmental impact of all the alternatives considered in terms of the significance of the impacts during both the construction and operational phases.

The construction impacts, if effectively and sufficiently managed according to the mitigation measures proposed in this report, specialist reports and the draft environmental management programme (EMPr), will mostly be of low significance, post mitigation. It should be noted that a moderate post mitigation significance rating is anticipated in terms of the loss of faunal habitat. This is mainly due to the placement of infrastructure in areas of high sensitivity. No post mitigation impacts of high significance are expected.

PROPOSED TENBOSCH TIMESHARE RESORT 41

Operational impacts can be similarly mitigated and residual impacts are expected to be of low significance overall. However, it should be noted that post mitigation significance is anticipated to be moderate in terms of air pollution due to emissions from increase number of vehicles to the area and the operational cost of services pertaining to the use of Eskom power. No post mitigation impacts of high significance are expected.

Positive impacts, which will be applicable to all alternatives, include job creation and employment opportunities for both the construction and operational phases, skills transfer and development. Diversifying the tourism offerings within the region will also have an overall positive impact.

With the above in mind, it is recommended that the Preferred Alternative be supported on the condition that all mitigation measures mentioned in this report, the specialist studies and the draft EMPr are implemented and adhered to throughout the project lifecycle. No fatal flaws are evident and the design approach and layout is deemed to be environmentally responsible. Additionally, the burying of the power cable will help to minimize the visual impact on the adjacent KNP and other tourism accommodation facilities within the area.

Layout Alternative: Alternative 2

In the Layout Alternative most arguments for the Preferred Alternative hold true.

The layout of the timeshare resort is that of the Preferred Alternative with the exception that approximately 12 of the chalets in the eastern portion and a section of road are located within the riparian buffer which has a high sensitivity rating and is declared as a no development zone. The placement of these chalets and infrastructure within an area of high sensitivity is not recommended or ideal.

The services as that of the Preferred Alternative.

Statement

The Layout Alternative will result in slightly higher significance ratings for aspects such as hydrology and flora, particularly during the construction phase. This is owning to the placement of a number of chalets and section of the internal access roads being located within the riparian buffer which has a high sensitivity rating.

Post mitigation significance for the construction phase will be mostly low. However, moderate post mitigation significance ratings are expected for hydrology due to certain chalets being located just outside of the flood line of the Crocodile River, the disturbance of sensitive habitats due to the placement of a number of chalets within the riparian buffer and the cumulative impact of the disturbance of sensitive habitats.

The operational impacts will be similar to those of the Preferred Alternative, with post mitigation impacts being predominately of low significance. Slightly elevated post mitigation significance, as compared to the Preferred Alternative, is expected for the disturbance of sensitive habitats. Additionally, moderate post mitigation significance rating is anticipated for the cumulative disturbance/ destruction of sensitive habitats.

The placement of a number of chalets and a portion of the internal access road in the buffer of the riparian habitat is not environmentally responsible as this area has a high sensitivity rating and is declared a no development zone. In spite of the application of mitigation measures, certain impacts- particularly relating to ground and surface water and disturbance of sensitive habitats- will be of a slightly higher significance than in the Preferred Alternative. In light of this, it is recommended that the Layout Alternative is not supported.

Technology Alternative: Alternative 3

This alternative includes the layout of the Preferred Alternative, and as such, all arguments hold true for this alternative. All service aspects will also be as per the Preferred Alternative, with the exception that the power will not be supplied by Eskom, but rather by solar panels mounted on the roofs of the units.

PROPOSED TENBOSCH TIMESHARE RESORT 42

Statement

The Technology Alternative will result in similar low post mitigation significance ratings as that of the Preferred Alternative for the construction phase. Slightly lower impacts are also anticipated for the loss of vegetation due to the fact that power will be supplied by solar panels which is less invasive in nature than the burying of cables.

The operational impacts will be similar to those of the Preferred Alternative, with residual impacts being mostly of low significance. Slightly elevated post mitigation impacts, as compared to the Preferred Alternative, is anticipated for soil erosion owing to the increase in hard surfaces and storm water runoff from the solar panels.

Solar panels are prohibitive from a capital cost perspective and are not considered ideal for this project of this size. Additionally, the potential visual impact on the KNP in terms of glare could be negatively impact on KNP tourist visitor experience, particularly at certain times of the day.

With the above in mind, it is recommended that the Technology Alternative not be supported due to the potential visual impact on the KNP visitors.

No-go Alternative

The No-go Alternative implies that the proposed development of the timeshare resort on Tenbosch Farm 101 will not take place. In this scenario receiving environment will not be negatively impacted upon in any manner, particularly with regard to biodiversity and surface water.

It should be noted that while no negative impacts will be incurred, the same can be said for positive impacts such as, the creation of employment and job opportunities, skills transfer and development.

SECTION E. RECOMMENDATION OF PRACTITIONER

The proposed development of the Timeshare Resort on Tenbosch Farm will take place in predominately disturbed/transformed areas and is considered a ‘brownfields’ site. Limited encroachment into sensitive areas will occur and both the riparian buffer and 1:100 flood line of the Crocodile River is respected. As discussed in the preceding section, all significant negative impacts can be successfully mitigated and managed to acceptable levels (moderate to low) during the entire project lifecycle. All mitigation measures as detailed in this BAR, the attached specialist reports and the draft EMPr must be implemented and adhered to for all phases of the project i.e. planning, construction and operation. In addition, the following specific recommendations apply: Planning and Design

 A minimum buffer zone of 16 m should be adhered to around the dam located in the east of the site.  A minimum buffer zone of 15 m should be adhered to around the drainage line located in the west of the site.  A minimum buffer zone of 67 m should be adhered to around the Crocodile River located to the north of the site.  Buildings and other hardened surface infrastructure (including storm water attenuation measures) should be located outside of buffered watercourses, sensitive areas and riparian habitat.  All activities should stay out of the 1:100 year flood line area.

PROPOSED TENBOSCH TIMESHARE RESORT 43

 All storm water should be diverted to a point where the water must be released in a controlled manner that will not initiate or enhance any erosion.  The sensitivity map must be used as a decision making tool to guide the layout design. Development on areas of high environmental sensitivity must be avoided.  If infrastructure is planned within any areas of natural vegetation, the areas should be checked by a suitably experienced botanist to locate all conservation-important species. These plants should be marked and the relevant permits applied for before removal and translocated to nearby suitable habitat prior to vegetation being cleared.  A follow-up survey in late summer (February / March) should take place to search for the succulent Aloe komatiensis. This species is listed as Endangered and is confirmed from just outside the study area. This is a small aloe which may have been overlooked during fieldwork and a search during its flowering period will make it far more visible.  The trees Sclerocarya birrea subsp. caffra, Combretum imberbe and Philenoptera violacea are nationally protected and a permit would be required to destroy them.  Aloe marlothii and Crinum stuhlmannii are protected under provincial legislation and need to be rescued and relocated to adjacent suitable habitat if they are found to be within the development footprint. A permit to move these plants would also be required Construction

 A suitably experienced botanist should be present on site at the time of pegging so as to identify sensitive plants or habitats.  The nationally protected trees to be protected (Sclerocarya birrea subsp. cafra, Combretum imberbe and Philenoptera violacea), Aloe marlothii and Crinum stuhlmannii protected under provincial legislation and any other identified subsequent to the initial survey, should be clearly marked prior to construction.  Locate construction camps and stock yards in the least visible areas. Make use of the natural screening capacity of the site by placing these facilities adjacent a dense vegetation patch with sufficient height to conceal these project components. Alternatively, the screening capacity of the site can be temporarily enhanced through the erection of a 3 m high shade cloth fence around the construction camp during construction. The colour of the shade cloth should be similar to that of the adjacent vegetation, i.e. a light brown or green  No natural watercourse is to be used for the cleaning of tools or any other apparatus. This includes for purposes of bathing, or the washing of clothes etc.  The construction of pathways (disturbance zones) in or adjacent to the riparian areas is to be closely managed and strictly controlled to minimize damage to riparian areas.  No construction camps should be allowed in or within 20 m of a riparian area.  No stockpile areas should be located in or within 20 m of a riparian area.  Construction should preferably take place during the low flow/winter months in order to minimize the risk of sediment and debris being washed into riparian areas.  Stockpiling of soil and of supplies for the construction camps must take place clearly away (at least 20 m where possible) from the edge of riparian areas to prevent soil being washed into the riparian areas habitat.  During the construction and operation phases erosion and siltation measures should be implemented (e.g. the use of temporary silt traps downstream of construction areas).  Developers should implement an alien plant control program to combat the infestation present around the wetlands. This program should include regular inspections and follow-ups. Operation

 Regulate and control movement over the site. Personnel, vehicles and equipment to move along designated routes.

PROPOSED TENBOSCH TIMESHARE RESORT 44

 Ensure that all conserved species and specimens are suitably protected for the duration of the operational phase.  No protected trees or plants may be removed without the relevant permits from the local authority.  Maintenance workers and guests may not trample natural vegetation and work should be restricted to dedicated roads, paths and gardens within the development footprint.  The operator must develop a management and monitoring programme for alien and invasive species detailing basic ID information, actions to prevent the establishment of invasive plants and methods of removal of site during construction.  No unauthorised access is permitted to buffer areas or any natural areas outside of the facility footprint

SECTION F: APPENDIXES

Appendix A: Maps

Appendix B: Photographs

Appendix C: Facility illustration(s)

Appendix D: Specialist reports

Appendix E: Public Participation

Appendix F: Impact Assessment

Appendix G: Environmental Management Programme (EMPr)

Appendix H: Details of EAP and expertise

Appendix I: Specialist’s declaration of interest

Appendix J: Additional Information

PROPOSED TENBOSCH TIMESHARE RESORT 45

PROPOSED TENBOSCH TIMESHARE RESORT 46

APPENDIX A: MAPS APPENDIX A.1: LOCALITY

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX A.2.1: PREFERRED ALTERNATIVE LAYOUT

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX A.2.2: ALTERNATIVE 2 LAYOUT

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX A.3.1: PREFERRED ALTERNATIVE SENSITIVITY

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX A.3.2: ALTERNATIVE 2 SENSITIVITY

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX B: PHOTOGRAPHS

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX C: FACILITY ILLUSTRATIONS

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX D: SPECIALIST REPORTS APPENDIX D.1: GEOTECHNICAL REPORT

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX D.2: RIPARIAN AND WETLAND REPORT

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX D.3: HERITAGE REPORT

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX D.4: ECOLOGY REPORT

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX D.5: VISUAL IMPACT REPORT

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX E: VISUAL PUBLIC PARTICIPATION

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX F: IMPACT TABLES

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX G: EMPR

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX H: DETAILS OF EAP

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX I: SPECIALIST DECLARATION

PROPOSED TENBOSCH TIMESHARE RESORT

PROPOSED TENBOSCH TIMESHARE RESORT

APPENDIX J: ADDITIONAL INFORMATION

PROPOSED TENBOSCH TIMESHARE RESORT