PCDO

Jan-2019

Launched portion of Viaduct Deck Structure from S-180 (KATRA- SECTION)

Udhampur-- Rail Link Project

Northern Railway विजय शर्मा vkbZvkj,lb Vijay Sharma IRSE

No. Secy.CAO/USBRL/JAT/PCDO Dated: 07/02/2018

Sub: PCDO for the Month of Jan, 2019. 1. Highlights of the month of Jan, 2019.

1.1 During this month tunneling of 2776 m was done, which is the highest ever monthly progress . This comprises of 1395m of Main Tunnel and 1381m of Escape Tunnel and also 22520m of tunnelling has been completed in this financial year. 1.2 ESPs of Arpinchala and Sumber Station Yards has been approved on 28.12.2018. 1.3 Tender for Manufacture, Supply, Transportation and delivery of prime quality of UIC 60 Kg 1080 Grade Head Hardened Class A Rails at Banihal site for Katra-Banihal section was uploaded on 29.01.2019 and is to be opened on 26.02.2019.

1.4 Progress of tunneling work (Main tunnel) between Katra- Banihal Section

S/No Agency Scope (m) Progress (m) Progress during the month (m)

1 KRCL 46101 33083 580

2 IRCON 48761 27797 815

3 NR 2456 2456 Work Completed

4 Total 97318 63336 1395

1.5 Progress of tunneling work (Escape tunnel) between Katra- Banihal Section.

S/No Agency Scope (m) Progress (m) Progress during the month (m)

1 KRCL 23541 11193 620

2 IRCON 42927 24455 761

3 NR 0 0 Work Completed

4 Total 66468 35648 1381

1

1.6 Status of Bridges between Katra- Banihal Section. Agency KRCL IRCON NR Major 15 10 1 Minor 7 1 3 Total 22 11 4 Work in progress 10 6 0 Work completed 4 Major +7 Minor 3 (Major) 1 Major + 3 Minor Work yet to start 1 2 0 (Br.60) (Br. 61 & Br. 4)

Total bridges in Katra-Banihal section : 37 (26 Major + 11 Minor)

2. Important achievements during the month

2.1 Earth Work: 2.1.1 Earth work and protection work is in progress in station yard, out of 23,60,000 Cum of total quantity 22,67,183 Cum has been done so far. 2.1.2 Earthwork for excavation of Bridges foundation is in progress for Katra Banihal section, out of 16,38,639 cum quantity (i.e. except ) 13,81,370 cum has been completed. 2.1.3 Earthwork for excavation of Chenab Bridge foundations & slope protection is in progress, out of 10,08,545 cum quantity 9,75,697 has been completed (i.e. 97% completed).

2.2 Tunneling i. Progress of underground excavation achieved in various tunnels are as follows.

Progress of Main Tunnels (m) Progress of Escape Tunnels (m) Sr. Tunnel No. During this During this Scope Cumulative Scope Cumulative Month Month 1 T-1 3159 0 2850 - - - 2 T-2 5093 125 3010 5072 139 3108 3 T-5 5959 65 5680 5959 113 5694 4 T-13 9368 390 2163 9368 368 2391 5 T-14 3142 58 146 3142 59 399 5 T-15 9829 247 2449 9829 250 3049 6 T-48 10186 217 6452 9788 226 6163 7 T-49 12758 169 7838 12755 185 8022 8 T-74R 8600 69 7859 7413 41 6822 9 T-77D 1863 55 670 - - - 10 Total 69957 1395 39117 63326 1381 35648

2

ii. Progress of lining achieved during this month is as follows

Progress of Main Tunnel Lining (m) Progress of Escape Tunnel Lining (m) Sr. No. Tunnel During this During this Scope Cumulative Scope Cumulative Month Month 1 T-1 3159 48 2380 - - - 2 T-2 5093 0 0 5072 0 0 3 T-5 5959 154 4488 5959 136 3720 4 T-13 9368 0 0 9368 0 0 5 T-14 3142 0 0 3142 0 0 5 T-15 9829 0 0 9829 0 0 6 T-48 10186 88 1238 9788 108 480 7 T-49 12758 201 1513 12755 90 180 8 T-74R 8600 0 6327 7413 174 5338 9 T-77D 1863 0 0 - - - 10 Total 69957 491 15946 63326 508 9718

iii. Progress of tunnel works/agency wise is as follows,

Main Tunnel

S/No Agency Scope (m) Progress (m) Balance (m) Progress (%) 1 KRCL 46101 33083 13018 72 2 IRCON 48761 27797 20964 57 3 NR 2456 2456 0 100 4 Total 97318 63336 33982 65 Escape Tunnel S/No Agency Scope (m) Progress (m) Balance (m) Progress (%) 1 KRCL 23541 11193 12348 48 2 IRCON 42927 24455 18472 57 3 NR No scope 4 Total 66468 35648 30820 54

3

iv. Month wise Tunneling progress (2018-19)

Tunnel Progress (2018-19)

Main Tunnel (m) Escape Tunnel (m) Month KRCL IRCON Total KRCL IRCON Total Apr-18 295 566 861 259 569 828 May-18 335 503 838 262 477 739 Jun-18 389 500 889 374 498 872 Jul-18 459 615 1074 444 646 1090 Aug-18 510 580 1090 436 550 986 Sep-18 515 669 1184 522 738 1260 Oct-18 486 740 1226 531 934 1465 Nov-18 506 709 1215 535 878 1413 Dec-18 504 802 1306 572 836 1408 Jan-19 580 815 1395 620 761 1381 Feb-19 0 0 Mar-19 0 0 Total 4579 6499 11078 4555 6887 11442

v. Linear progress of tunnel excavation (main +escape) for 2018-19

Tunnel Excavation (Main Tunnel) 2018-19

802 815 740 709 669 615 580 566 580 515 510 486 506 504 503 500 459 389 335 295

KRCL IRCON Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 4

Tunnel Excavation (Escape Tunnel) 2018-19

934 878 836 761 738 620 646 572 569 522 531 535 550 477 498 444 436 374

259 262

KRCL IRCON

Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18

Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19

Tunnel Lining Progress (2018-19) Main Tunnel Lining (m) Escape Tunnel Lining (m) Month KRCL IRCON Total KRCL IRCON Total Apr-18 324 356 680 122 165 287 May-18 269 376 645 116 111 227 Jun-18 345 337 682 181 121 302 Jul-18 238 336 574 235 293 528 Aug-18 347 300 647 223 190 413 Sep-18 295 268 563 211 244 455 Oct-18 237 223 460 151 226 377 Nov-18 115 314 429 150 358 508 Dec-18 175 274 449 164 234 398 Jan-19 202 289 491 136 372 508 Feb-19 0 0 Mar-19 0 0 Total 2547 3073 5620 1689 2314 4003

5

(Main Tunnel Lining) 2018-19

376 347 356 345 337 336 324 314 295 300 289 269 268 274 238 237 223 202 175 115

KRCL IRCON

Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19

(Escape Tunnel Lining) 2018-19

372 358

293

235 244 223 226 234 211 181 190 164 165 151 150 136 122 116 111 121

KRCL IRCON

Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19

6

Tunnel wise last Three Month progress (2018-19)

Total S/No. Tunnel October November December January Progress (2018-19) 1 T-1 Main (m) 0 0 0 0 0 0 0 0 0 Main (m) 91 134 152 125 1590 8 T-2 218 271 301 264 Escape (m) 127 137 149 139 1622 Main (m) 139 76 66 65 1000 2 T-5 263 198 174 178 Escape (m) 124 122 108 113 997 Main (m) 258 296 286 390 1989 9 T-13 541 572 601 758 Escape (m) 283 276 315 368 1936 Main (m) 0 22 66 58 146 11 T-14 66 90 130 117 Escape (m) 66 68 64 59 397 Main (m) 218 217 261 247 1468 7 T-15 498 476 541 497 Escape (m) 280 259 280 250 2001 Main (m) 179 170 187 217 1940 3 T-48 477 453 444 443 Escape (m) 298 283 257 226 2071 Main (m) 185 146 145 169 1783 4 T-49 396 344 311 354 Escape (m) 211 198 166 185 1851 T- Main (m) 84 79 63 69 642 6 161 150 132 110 74R Escape (m) 77 71 69 41 567 T- 10 71 71 80 80 80 80 55 55 520 77D Main (m) 2691 2634 2714 2776 12 Total (MT+ET) Total (2018-19):22520m

Ballast-less Track (BLT) 2.2.1 Tender for design of Broad Gauge BLT (Ballast less track) including supply, installation, testing and commissioning between Banihal - Arpinchalla (Approx. 16 Km.) was discharged on 17.01.2019. Retendering is being done. 2.2.2 Tender for design of Broad Gauge BLT (Ballast less track) including supply, installation, testing and commissioning between Km. 39.01 to Km. 42.21 and Km. 51.935 to Km. 61.817 (Approx. 12.5 Km) on Katra-Dharam Section of USBRL Project has been discharged on 10.01.2019. Retendering is under process. 2.2.3 Tender for design of Broad Gauge BLT (Ballast less track) including supply, installation, testing and commissioning between Km. 91.200 to Km. 101.632 on Katra-Dharam Section of USBRL Project has been discharged on 10.01.2019. Retendering is under process.

2.3 Bridges Progress of bridges between Katra- Banihal section has been shown in Table 3.

7

2.4 Miscellaneous:

2.4.1 ESP of Kata Banihal Section: a) ESP of Sumber and Arpinchala have been approved on 28.12.2018. b) ESP of Sangaldan, Basindadhar, Salal-A and Reasi have been approved by Ferozepur division on 23.01.2019 and submitted at HQ/Baroda House on 30.01.2019. 2.4.2 Tender for Transportation of DEMU Power and Trailer Coaches 17 no’s and Two WDS6 Locos by Road, duly conducting feasibility study, from to Railway Station has been awarded to SAAR Frights Corporation on 12.01.2019.

2.4.3 E&M (Electro and Mechanical Works) for Tunnels: a) Tender for ISS at Sangaldan opened on 26/12/2018 and ISS Reasi opened on 15/01/2019 and same are under evaluation. b) E&M Tender for package-I (tunnel No-6 to T-12) has been invited on 22/12/2018 and scheduled to be opened on 26/02/2019.

2.5 Chenab Bridge Progress of Chenab Bridge has been summarized in table below:

Progress of Chenab Bridge: 2018-19 (KRCL) Target Monthly Balance Achieved Total Balance for Progress Progress for of Item Unit up to Quantity on 1/4/18 2018- Jan F.Y. 2018-19 2018- 31/03/18 19 2019 19 Earth Work in Cum 1008545 968164 40381 - 0 4283 Excavation Fabrication of Deck Nos/MT 164/13450 67/7238 97/7607 6310 0/0 0/2716 3594 Segments Fabrication of Main Arch, MT 15550 12415 3135 0 2887 Piers & Trestles Launching and Erection of Superstructure Deck Nos 164 59 105 - 0 0 - Segments Launching of Main Arch, 429 + 309+ Nos. 120 - 0 82 - Piers & Trestles Trestles Trestles Financial Progress Cr. 1198 1071.68 126.32 110 0 97 13 Total expenditure (Jan 2019) : 1168.68 Cr.

2.6 Major Contract Awarded

All major contract awarded.

8

2.7 Major Tender Invited/Under Finalisation/Under process

2.8.1. Tender for design of Broad Gauge BLT (Ballast less track) including supply, installation, testing and commissioning between Banihal - Arpinchalla (Approx. 16 Km.) has been discharged on 17.01.2019. Retendering is being done.

2.8.2. Tender for Manufacture, Supply, Transportation and delivery of prime quality of UIC 60 Kg 1080 Grade Head Hardened Class A Rails as per Indian Railway Standard Specification for Flat Bottom Rails IRS-T-12-2009 (With latest A&C Slips) at Banihal site for Katra-Banihal section of USBRL Project in J&K, India was uploaded on 29.01.2019 and is to be opened on 26.02.2019.

2.8.3. Financial Bid for the Tender for “Construction of prposed all buildings including station building, RPF & GRP Posts, RPF Barrack & GRP Barracks, Equipment Control Rooms for Tunnels, 33 KV Switch Yard, Electrical Sub- Station (ESS), Portal Sub Stations for Arpinchala Station Yard of USBRL Project for a total value of Rs. 27.91 Cr. was opened on 28.01.2019. Financial T.C. is in under progress.

2.8 Budget and Expenditure

2.8.1 Abstract Cost = 19565 Cr 2.8.2 Last Sanctioned Cost = 27,949 Cr 2.8.3 Latest anticipated Cost = 27,949 Cr 2.8.4 Budget out lay for 2018-19 (USBRL Project) = 1150 Cr (Revised) 2.8.5 Up to date expenditure = Rs. 17640 Cr. (Since inception)

2.8.6 Break up of expenditure under major Plan heads is detailed as under :

Year 2018-19 Total Booking upto Jan.'2019 Plan Expenditure Outlay Expenditure SN (Cr.) % Head up to March (Cr.) up to Jan Net (after ROC Expenditure 2018 (Cr.) Revised Total 2018 (Cr.) from PSU) New 1 Line 16120.09 1150 1628.36 1520.26 2087 181 (8300)

9

Booking details as shown by USBRL finance: Cost (As per S/No. Section Booking up to Jan-2019 detailed estimate) 1 Udhampur- Katra 1111.43 1119 2 Katra- Banihal 21652.33 11520 3 Banihal-Quazigund 1691.88 1687 4 Quazigund- Baraumulla 3493 3314 5 Total 27948.6 17640

Expenditure incurred by IRCON and KRCL (2018-19) Financial/Actual Expenditure during (2018-19) IRCON KRCL NR Month Achieved (2018-19) Target (Cr.) Achieved (Cr.) Target (Cr.) (Cr.) April 50 57.1 65 72.89 13.97

May 60 72.66 75 85.51 4.68

June 65 82.72 80 94.76 22.71

July 80 90.98 90 98.81 31.85

August 90 92.03 90 115.22 23.04

September 100 95.66 105 116 3.71

October 110 86.43 110 120 8.01

November 110 105.29 110 121 5

December 110 107.34 110 126 2.9

January 120 96.45 110 126 8.32

Total 895 886.66 945 1076.19 124.19 Annual planning of Expenditure during 2018-19 for IRCON =1150 Cr Annual planning of Expenditure during 2018-19 for KRCL =1100 Cr. Annual planning of Expenditure during 2018-19 for NR =120 Cr.

10

3. Katra-Banihal Section (Progress in Details)

3.1 For construction convenience and monitoring, this section has been divided into following legs: A. Katra – Banganga (km. 25 - 30): Executed by Northern Railway and works are completed. B. Km. 30 - 100 (KRCL, except 73.78 to 91 as transferred to IRCON): Progress of underground excavation for various tunnels being executed by KRCL are shown in Table 1.

C. Km 100 – 136: Executed by M/s IRCON. Progress of underground excavation for various tunnels being executed by IRCON are shown in Table 2.

3.2 Chenab Bridge, Br. No. 44 (KRCL) Chenab Bridge has been divided in four parts for construction point of view, these are A. Construction of Arch Portion (S-10 to S-70) B. Construction of Viaduct Portion (S-70 to S-180) C. Slope Stabilization - Bakkal end and D. Slope Stabilization - Kauri end

A. Progress on Arch Portion (S10 to S70) :

a. Progress of the Arch:

(i) RCC work: Concreting of S10 (Except 234 Cum), S20, S30, S40, S50, S60 and S70 (Except Pier Cap) has been completed. (ii) Workshop: Main span deck fabrication at S180 & Bakkal is under progress. Arch fabrication work at wheels India Ltd., Wardha & Trestle fabrication at AIML, Raipur has been completed.

iii) Progress on Viaduct Portion (S-70 to S-180): Launching of viaduct portion from S-80 to S-180, Segment AS34 to AS35 and AS36 to AS07 completed.

a. Progress:

(i) RCC Work: All completed except the pier cap of S-70.

B. Slope stabilization – Kauri end: In progress. C. Slope stabilization - Bakkal end: In progress.

4. Progress of bridges between Katra- Banihal section has been shown in Table 3.

11

Table 1: Tunnel Details: KRCL

KRCL Portion Progress Target Lining Length Award of Cumulative Balance Achieved S/No. Tunnel No this Remarks 2018- Progress this Cumulative Balance Target Achieved (m) Contract Progress (m) (2018-19) Scope month 19 month Progress (m) 2018-19 (2018-19) Tunnel Excavation in 1 T-1 3159 Jul-14 0 2850 309 45 0 3159 48 2380 779 1300 1191 progress

T-2 5093 Mar-16 125 3010 2083 1320 1590 5093 0 0 5093 0 0 Tunnel Excavation in 2 progress T-2 5072 Mar-16 139 3108 1964 1320 1622 5072 0 0 5072 0 0

3 T-3 3009 Nov-10 3009 Work Completed 0 Completed Completed

4 T-5 5959 Oct-10 65 5680 279 800 1000 5959 154 4488 1471 1800 1356 Tunnel Excavation in T-5 progress. 4A 5959 41922 113 5694 265 800 997 5959 136 3720 2239 1900 1689 (Escape) 5 T-6 3493 Sep-10 3493 Completed. 0 3493 0 3493 0 0

6 T-9 470 Sep-10 470 Completed 0 470 0 470 0 0

7 T-10 1010 Sep-10 1010 Completed 0 Completed 1010 0 1010 0 0

8 T-11 830 Sep-10 830 Completed 0 830 0 830 0 Excavation completed. 9 T-12 2123 Sep-10 2123 0 2123 0 1971 152 0 Lining in progress. 10 T-13 9368 390 2163 Work awarded to M/s 7205 1690 1989 9368 0 0 9368 0 T-13 Jul-16 HCC on 25/7/16. Work 10A 9368 368 2391 Transferred to KRCL 6977 1810 1936 9368 0 0 9368 0 (Escape) 11 T-14 3142 3142 0 3142 Reflect the part that is Jul-16 T-14 clubbed with T-13 11A 3142 0 3142 (Escape) 12 T-40/41 1346 Oct'05 1346 Work Completed 0 13 T- 42/43 2732 Oct'05 2732 Work Completed 0 14 T-44/45 1483 Oct'05 1483 Work Completed 0 Completed 15 T-46 654 Oct'05 654 Work Completed 0 16 T-47 2230 Oct'05 2230 Work Completed 0 Total (Main 17 46101 580 33083 72% 13018 3855 4579 11106 202 10922 184 3100 2547 Tunnel) Total 18 23541 620 11193 48% 12348 3930 4555 23541 136 3720 19821 1900 1689 (Escape)

12

Table 2: Tunnel Details: IRCON

IRCON Portion Lining Progress Length Award of Cumulative Balance Target Achieved Progress Sr. No Tunnel No this Remarks Cumulative Balance Target Achieved (m) Contract Progress (m) 2018-19 (2018-19) Scope this month Progress (m) 2018-19 (2018-19) month

1 T-14 3142 - 58 146 Tender clubbed with that of T-13 and 2996 180 146 3142 0 3142 0 T-14 T-15. Part clubbed with T-13 1A 3142 59 399 2743 360 397 3142 0 3142 0 (Escape) transferred to KRCL 2 T-15 9829 Mar-16 247 2449 7380 2280 1468 9829 0 9829 0 T-15 Work in progress. 2A 9829 Mar-16 250 3049 6780 2520 2001 9829 0 9829 0 (Escape) 3 T-48 10186 Sept,2012 217 6452 3734 2463 1940 10186 88 1238 8948 3100 653 Work in progress T-48 3A 9788 Sept,2012 226 6163 3625 2290 2071 9788 108 480 9308 2400 480 (Escape) 4 T-49 12758 Dec,2013 169 7838 4920 2445 1783 12758 201 1513 11245 2150 1361 Work in progress T-49 4A 12755 Dec,2013 185 8022 4733 2220 1851 12758 90 180 12578 300 180 (Escape) 5 T-50 255 June,2014 255 Completed 0 0 0 255 0 188 67 255 188

6 T-74 R 8600 Oct,2011 69 7859 Work in progress 741 828 642 8600 0 6327 2273 1247 871

T-74 R Escape 6A Tunnel 7413 Oct,2011 41 6822 Work in progress 591 720 567 7413 174 5338 2075 1010 1654 7 T-77 335 335 Completed 0 335 Completed 0 Completed 8 T-77 A 873 873 Completed 0 873 Completed 0

9 T-77D 1863 July,2016 55 670 Work in progress 1193 1040 520 1760 0 1760 0

10 T-78 920 920 Completed Completed 0 920 Completed 0 Total (Main 13 48761 815 27797 57% 20964 9236 6499 48658 289 9266 37264 6752 3073 Tunnel) Total 14 (Escape 42927 761 24455 57% 18472 8110 6887 42930 372 5998 36932 3710 2314 Tunnel)

13

Table 3: Status of bridge works between Katra-Banihal Section

BRIDGES IN KATRA-BANIHAL SECTION (111 KM) S. Chainage Br. No. Span Arrangement Type of Bridge Bridge Category Status No. C/L Position of bridges from Km 25 to 30 (N.R.) 1 32 28.138 1x34+1x64+1x92+1x64m PSC Girder Major Completed 2 33 29.403 3x3m RCC Box Minor Completed 3 33A 29.512 5.2x5.585m RCC Box Minor Completed 4 34 33.180 3x3m RCC Box Minor Completed i. Bridges with KRCL ( Km 30-100) Steel open web 1 34 33.186 1x24.4 =24.4m Major In progress girder

Main Bridge : 1x290+ 1x80+ 1x75+ 1x28.25 35 (Anji Important 2 38.670 =(473.25m) Cable Stayed In progress Khad) (Mega) Viaduct : 1x25 +2x35 + 1x25 (120m)

Sub structure Composite 3 38 42.270 1x24.4+1x61+1x45.7 = 131.1m Major completed. plate Girder

Composite Important 4 39 42.460 1x53.15+6x64+1x53.15= 490.25m In progress plate Girder (Mega) 5 40 42.900 1x4x3 =12m RCC BOX minor Completed 6 41 48.980 1*5*5=25m RCC BOX minor Completed 7 42 49.240 3x5x5=75m RCC BOX minor Completed 8 43 50.000 1x35+1x53+10x64+1x49 = 777m Girder Bridge Important(Mega) In progress

14

44(Chenab 1x55+2x65+10x48+1x65+1x55+1x40+9x50+1x40 Girder and arch Important 9 51.057 In progress bridge) = 1315 bridge (Mega) Composite 10 53 55.490 3x30.5 = 91.5m Major Completed Plate Girder Composite 11 55 56.260 1x24.4 =24.4m Major Completed Plate Girder Composite 12 56 57.590 1x24.4=24.4m Major Completed Plate Girder Composite 13 57 58.042 1x24.4=24.4m Major Completed Plate Girder S. Chainage Br. No. Span Arrangement Type of Bridge Bridge Category Status No. C/L Composite Sub structure 14 58 60.725 3x30.5= 91.5 m Major Plate Girder completed. Composite Sub structure 15 59 60.930 1x30.5+1x45.7+1x30.5 = 106.7 m Major Plate Girder completed Composite GT investigation Plate Girder 2x30.5(CPG)+2x61(CT)+1x30.5 completed, work 16 60 70.509 (CPG) Major (CPG)+1X18.3(CPG)m=231.8m, awarded. GAD +composite under finalization. truss (CT) 17 81 92.470 2x3x2m =12m RCC BOX minor Completed 18 82 93.080 2x(3x3) =18m RCC BOX minor Completed 19 85 96.443 1x45.7+3x61+1x45.7 =274.4m STEEL GIRDER Major In progress 20 85A 96.693 1x(3x3) m=9m RCC BOX minor Completed COMPOSITE 21 87 98.440 3x61.0 m+1x45.7=228.7m Major In progress GIRDER 22 87A 98.540 1x3x3m=9m RCC BOX minor Completed THROUGH Sub structure 23 88 99.361 1X45.7=45.7m Major GIRDER completed.

15

ii. Bridges with IRCON

GT investigation completed, Composite Plate 24 61 76.971 1x18.3+1x24.4+x30.5m=73.2m Major work awarded. GAD Girder finalised. Steel Girder/Composit 25 1 99.98 1x30=30m Major In progress Girder Composite Steel 26 2 110.6955 11x39= 429m Important In progress Girder Composite Steel 27 3 111.300 8x39= 312m Important In progress Girder RCC Box for rock 28 4 124.2975 1x35=35m Major In progress protection 29 5 124.782 1x5 =5m RCC Box minor In progress 1x30.5+1x45.7+2x30.5 = 30 121 125.2525 Steel Girder (OWG) Major Completed 137.2m 31 138 147.952 3x30.5= 91.5 m Composite Girder Major In progress

32 142 148.439 3x30.48=91.44m Steel Girder Major Completed

33 144 149.48 2x25.51.2m Steel Girder Major Completed

16

5. Progress of land acquisition in various stretches of Udhampur - Srinagar- Baramulla New Line is enclosed as, Annexure-I

भवदीय

(ववजय शर्मा)

17

Annexure-1: Details of land acquisition upto the month of Jan 2019 for USBRL Project

A) Land Acquisition details for Jurisdiction of Dy. CE’s

Revenue Land Diversion Forest Land

S.No Jurisdiction Already Under Already Under Total Total Acquired Process Acquired Process

Dy.CE/Banihal 1 (Banihal- Dharam) 299.36 13.39 312.75 144.56 0.00 144.56 (Banihal- Baramulla) 857.50 0.00 857.50 0.00 0.00 0.00 2 Dy.CE/Sang 129.10 11.22 140.32 66.69 13.06 79.75 3 Dy.Ce/Reasi 206.64 39.78 246.42 240.88 0.63 241.51 4 Dy.CE/UHP 268.92 1.23 270.15 12.31 0.00 12.31 5 Dy.CE/Anji 5.96 0.75 6.71 19.87 0.00 19.87 6 Dy.CE/Chenab 13.24 0.00 13.24 12.39 0.61 13.00

Total 1780.72 66.37 1847.09 496.70 14.30 511.00

B) Abstract of Land Acquisition Status of USBRL:

Total Land Already Percentage Description Required Acquired Balance (Hectare) Balance (Hectare) (Hectare)

Revenue/ Private Land 1847 1781 66 4% Diversion of Forest Land 511 497 14 3%

Total 2358 2277 81 3%

18

Annexure-II

Financials- USBRL

Year Estimate Cost (Rs. Crore)

1994-95 Pink Book 1500

1998-99 DPR 3077

2010 CCEA Approved Cost 19565

Latest Estimate Estimated S/No. Section Cost Remarks (Cr.) 927.61 2nd Revised-2012 1 UHP- Katra 1111.43 Completion cost (with associate finance) 2 Katra (Km 25)-Km 30 183.51 Detailed estimate of 2012 3 Banihal- Quazigund 1691.88 Detailed estimate of 2012 Completion Estimate 3376.22 Cr. 4 Quazigund- Baramulla 3493 submitted to Rly.Board 5 Katra (Km 30)- Banihal 21468.82 Detailed estimate of 2015 6 USBRL Project Cost 27949 Crores

Booking up to Jan-2019

Cost (As per S/No. Section detailed Booking up to Jan-2019 estimate) 1 Udhampur- Katra 1111.43 1119

2 Katra- Banihal 21652.33 11520 3 Banihal-Quazigund 1691.88 1687 4 Quazigund- Baraumulla 3493 3314 5 Total 27948.6 17640