JBICI Research Paper No.18
Regional Cooperation Strategy on Interconnected Power Networks in Indochina
August 2002
JBIC Institute Japan Bank for International Cooperation
JBICI Research Paper No. 18 Japan Bank for International Cooperation (JBIC) Published in August 2002 © 2002 Japan Bank for International Cooperation All rights reserved.
This Research Paper is based on the findings and discussion of the JBIC Institute (JBICI). The views expressed in this paper are those of the authors and do not necessarily represent the official position of the JBIC. No part of this Research Paper may be reproduced in any form without the express permission of the publisher. For further information please contact the Planning and Coordination Division of our Institute.
Foreword
This research project is intended to examine the feasibility of interconnected power networks, which play an important role in power sector cooperation, in Cambodia, Laos, Thailand and Vietnam in the Indochina region, identify conditions and issues for the realization of the system interconnection, and make recommendations on future strategies to the governments.
The countries and various organizations, as we have seen, have carried out many studies on the power sectors of the region and reported the effectiveness of the system interconnection. However, the economic benefit from the system interconnection, particularly from system reliability improvement, has not been identified quantitatively. In this report, we measure the benefit of the system interconnection in monetary terms with the analytical tools commonly used in Japan, and examine the financial viability of the networks.
We believe this study bridges the missing part and makes a further step for the realization of the interconnected power networks in Indochina, and hope this report provides valuable information and viewpoints not only to persons involved with the Indochina region, but also persons who are interested in developing strategies and regional cooperation on system interconnections in developing countries.
Finally, I would like to express our deep appreciation for the cooperation and advice offered by the governments of Cambodia, Laos, Thailand and Vietnam, their agencies and various Japanese institutions that have made this survey possible.
August 2002 Koji Fujimoto Executive Director JBIC Institute Japan Bank for International Cooperation
i
(JBIC Institute) Masaya Kawaguchi Researcher, Development Policy Research Division, JBIC Institute
(Survey Team) Noboru Seki Planning Manager, Engineering Department, Tokyo Electric Power Company, Inc. Masahiko Tada Group Manager, Transmission System Department, Overseas Business Center, Tokyo Electric Power Services Co., Ltd. Yasuhiro Yokosawa Manager, International Project Development Group, Transmission & Substation Construction Department, Tokyo Electric Power Company, Inc. Nobuya Maekawa Manager, International Project Development Group, Transmission & Substation Construction Department, Tokyo Electric Power Company, Inc.
ii
Contents
Foreword ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ ⅰ Contents ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ ⅲ List of Tables ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ ⅴ List of Figures ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ ⅶ Acronyms and Abbreviations ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ ⅸ Map of Indochina ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ ⅻ
Executive Summary ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ S-1
Chapter Ⅰ Introduction ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 1 1.1 Background and Purpose ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 1 1.2 Study Methodology ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 1 1.3 Framework of the Study and Report ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 2
Chapter Ⅱ Present State and Future Plans of the Power Sectors ・・・・・・・・・・・・・・・・・ 3 2.1 Present Social Situation ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 3 2.1.1 Summary of the Present Social Situation ・・・・・・・・・・・・・・・・・・・・ 3 2.1.2 Economic Situation ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 4 2.1.3 Potential Energy Resources ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 7 2.2 Present Situation and Future Plans of the Power Sectors ・・・・・・・・・・ 11 2.2.1 Cambodia ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 11 2.2.2 Laos ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 20 2.2.3 Thailand ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 28 2.2.4 Vietnam ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 35 2.3 Support of Various Organizations for the Power Sectors ・・・・・・・・・・・ 44 2.4 Studies on the System Interconnection in the Indochina Region・・・・・ 45
Chapter Ⅲ Plan for the Interconnected Power Networks in Indochina ・・・・・・・・・・・・ 47 3.1 Study Methodology ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 47 3.1.1 For System Reliability Aspects ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 47 3.1.2 For Fuel Cost Aspects ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 50 3.1.3 For Financial Analysis ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 52 3.2 Definition of the Interconnected Transmission Line ・・・・・・・・・・・・・・・ 52 3.3 Feasibility of the Interconnected Transmission Line Project ・・・・・・・ 53 3.3.1 Results on the System Reliability Aspects Study ・・・・・・・・・・・・・ 53 3.3.2 Results on the Fuel Cost Aspects Study ・・・・・・・・・・・・・・・・・・・・・ 66 3.3.3 Economic Performance Comparison ・・・・・・・・・・・・・・・・・・・・・・・・ 79 3.3.4 Verification of the Benefits through the System Interconnection up to 2020 ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 82 3.3.5 Results on the Financial Analysis ・・・・・・・・・・・・・・・・・・・・・・・・・・ 90 3.3.6 Application to Rural Electrification ・・・・・・・・・・・・・・・・・・・・・・・・ 97
Chapter Ⅳ Conditions, Issues, and Recommendations ・・・・・・・・・・・・・・・・・・・・・・・・・ 102 4.1 More Beneficial Plans for the System Interconnection ・・・・・・・・・・・・ 102 4.1.1 Confirmation of the Benefits from the System Interconnection ・ 102 4.1.2 Proposals for the More Beneficial Plans for the System Interconnection ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 102 4.2 Conditions, Issues, and Recommendations for the Realization of the System Interconnection ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 104
iii
4.2.1 Conditions and Issues for the Realization of the System Interconnection Benefits ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 104 4.2.2 Recommendations for the Implementation of the System Interconnection ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 111
Chapter Ⅴ Support for the Realization of the System Interconnection ・・・・・・・・・・・ 113 5.1 Introduction ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 113 5.2 For Analysis of the Present Situations and Planning of the System Interconnection ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 113 5.3 For Arrangement the Necessary Conditions ・・・・・・・・・・・・・・・・・・・・・ 113 5.4 For Construction, Operation and Maintenance of the Inter connected Transmission Line ・・・・・・・・・・・・・・・・・・・・・・・・・ 114
Chapter Ⅵ Closing Remarks ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 116
(Appendix Example of Japan) Chapter A1 Wide Area Coordinated Operation in Japan ・・・・・・・・・・・・・・・・・・・・・・・・ 117 A1.1 System Interconnection in Japan ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 117 A1.2 Wide Area Coordinated Operation ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 117 A1.3 Outline of the Wide Area Coordinated Operation ・・・・・・・・・・・・・・・・・・ 118 A1.3.1 Power Exchange for Mutually Balancing Demand and Supply ・・ 118 A1.3.2 Wide Area Mutual Cooperative Exchange Power ・・・・・・・・・・・・・・ 118 A1.3.3 Power Exchange for Economical Operation ・・・・・・・・・・・・・・・・・・・・ 119 A1.4 New Economical Exchange System ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 119 A1.4.1 Schedule ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 119 A1.4.2 Method for Selecting Companies ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 120 A1.4.3 Accounting ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 120
Chapter A2 Hokkaido and Honshu Power Interconnection ・・・・・・・・・・・・・・・・・・・・・・ 121 A2.1 Wide Area Coordinated Operation System ・・・・・・・・・・・・・・・・・・・・・・・・ 121 A2.2 Operation of the Hokkaido Honshu HVDC Link ・・・・・・・・・・・・・・・・・・・ 121 A2.3 Expense Sharing System ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 121 A2.4 Use Charge ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 122
References ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 123
iv
List of Tables
Table 2-1 Present Situation of the Indochina Region ・・・・・・・・・・・・・・・・・・・・ 3 Table 2-2 Main Power Plants in Cambodia ・・・・・・・・・・・・・・・・・・・・・・・・・・・ 16 Table 2-3 Power Plant Development Plan in Cambodia ・・・・・・・・・・・・・・・ 17 Table 2-4 Main Hydropower Plants in Laos ・・・・・・・・・・・・・・・・・・・・・・・・・・・ 24 Table 2-5 Thailand’s System Installed Capacity ・・・・・・・・・・・・・・・・・・・・・・・ 31 Table 2-6 Vietnam’s System Installed Capacity ・・・・・・・・・・・・・・・・・・・・・・・ 39 Table 2-7 Power Plant Development Plan in Vietnam ・・・・・・・・・・・・・・・・・・ 41 Table 3-1 System Reliability of the Target and the PDP Base in 2015 ・・・ 53 Table 3-2 Maximum Power Demand and Installed Capacity (Base Case, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 54 Table 3-3 Available Reserve Capacity Saving in 2015 ・・・・・・・・・・・・・・・・・・ 66 Table 3-4 Unit Construction Cost and Unit Fuel Cost ・・・・・・・・・・・・・・・・・・ 66 Table 3-5 Annual Cost (Base Case, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 67 Table 3-6 Annual Cost (Case 1, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 68 Table 3-7 Annual Cost Saving (Case 1, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 68 Table 3-8 Energy Generation Change (Case 1, 2015) ・・・・・・・・・・・・・・・・・・・ 68 Table 3-9 Annual Cost (Case 2, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 69 Table 3-10 Annual Cost Saving (Case 2, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 69 Table 3-11 Energy Generation Change (Case 2, 2015) ・・・・・・・・・・・・・・・・・・・ 69 Table 3-12 Annual Cost (Case 3, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 70 Table 3-13 Annual Cost Saving (Case 3, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 70 Table 3-14 Energy Generation Change (Case 3, 2015) ・・・・・・・・・・・・・・・・・・・ 70 Table 3-15 Annual Cost (Case 4, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 71 Table 3-16 Annual Cost Saving (Case 4, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 71 Table 3-17 Energy Generation Change (Case 4, 2015) ・・・・・・・・・・・・・・・・・・・ 71 Table 3-18 Annual Cost (Case 5, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 72 Table 3-19 Annual Cost Saving (Case 5, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 72 Table 3-20 Energy Generation Change (Case 5, 2015) ・・・・・・・・・・・・・・・・・・・ 72 Table 3-21 Annual Cost (Case 6, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 73 Table 3-22 Annual Cost Saving (Case 6, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 73 Table 3-23 Energy Generation Change (Case 6, 2015) ・・・・・・・・・・・・・・・・・・・ 73 Table 3-24 Annual Cost (Case 7, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 74 Table 3-25 Annual Cost Saving (Case 7, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 74 Table 3-26 Energy Generation Change (Case 7, 2015) ・・・・・・・・・・・・・・・・・・・ 74 Table 3-27 Annual Cost (Case 8, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 75 Table 3-28 Annual Cost Saving (Case 8, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 75 Table 3-29 Energy Generation Change (Case 8, 2015) ・・・・・・・・・・・・・・・・・・・ 75 Table 3-30 Annual Cost (Case 9, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 76 Table 3-31 Annual Cost Saving (Case 9, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 76 Table 3-32 Energy Generation Change (Case 9, 2015) ・・・・・・・・・・・・・・・・・・・ 76 Table 3-33 Annual Cost (Case 10, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 77 Table 3-34 Annual Cost Saving (Case 10, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・ 77 Table 3-35 Energy Generation Change (Case 10, 2015) ・・・・・・・・・・・・・・・・・・ 77 Table 3-36 Overview of the Interconnected Transmission Line and Construction Cost ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 78 Table 3-37 Economic Performance Comparison in 2015 (15 years, 15%) ・・・ 79 Table 3-38 Economic Performance Comparison under Different Conditions 80 Table 3-39 Maximum Power Demand and Installed Capacity (Base Case, 2020) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 82 Table 3-40 Available Reserve Capacity Saving in 2020 ・・・・・・・・・・・・・・・・・・ 85 Table 3-41 Annual Cost (Base Case, 2020) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 85
v
Table 3-42 Annual Cost (Case 2, 2020) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 86 Table 3-43 Annual Cost Saving (Case 2, 2020) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 86 Table 3-44 Energy Generation Change (Case 2, 2020) ・・・・・・・・・・・・・・・・・・・ 86 Table 3-45 Annual Cost (Case 5, 2020) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 87 Table 3-46 Annual Cost Saving (Case 5, 2020) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 87 Table 3-47 Energy Generation Change (Case 5, 2020) ・・・・・・・・・・・・・・・・・・・ 87 Table 3-48 Annual Cost (Case 7, 2020) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 88 Table 3-49 Annual Cost Saving (Case 7, 2020) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 88 Table 3-50 Energy Generation Change (Case 7, 2020) ・・・・・・・・・・・・・・・・・・・ 88 Table 3-51 Annual Cost (Case 10, 2020) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 89 Table 3-52 Annual Cost Saving (Case 10, 2020) ・・・・・・・・・・・・・・・・・・・・・・・・ 89 Table 3-53 Energy Generation Change (Case 10, 2020) ・・・・・・・・・・・・・・・・・・ 89 Table 3-54 Economic Performance Comparison in 2020 (15 years, 15%) ・・・ 90 Table 3-55 Financial Analysis (FIRR, 2015) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 95 Table 3-56 Financial Analysis (FIRR, 2020) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 96 Table 3-57 Demand in the Special Economic Ward and Other Areas in Savannekhet ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 99 Table 4-1 Annual Cost Saving of the Top Four Cases in 2015 ・・・・・・・・・・ 103 Table 4-2 Annual Cost Share of the Top Four Cases in 2015 ・・・・・・・・・・・ 103 Table 4-3 Annual Cost Saving (Case 2, 2010) ・・・・・・・・・・・・・・・・・・・・・・・・・ 106 Table 4-4 Energy Generation Change (Case 2, 2010) ・・・・・・・・・・・・・・・・・・ 107
vi
List of Figures
Figure 1-1 Framework of the Study and Report ・・・・・・・・・・・・・・・・・・・・・・・・・ 2 Figure 2-1 Daily Load Curve of the Phnom Penh system in Cambodia ・・・・ 12 Figure 2-2 Demand Forecast in Cambodia (the WB’s Study) ・・・・・・・・・・・・・ 13 Figure 2-3 Maximum Power Demand Forecast (Cambodia) ・・・・・・・・・・・・・・ 15 Figure 2-4 Electric Energy Forecast (Cambodia) ・・・・・・・・・・・・・・・・・・・・・・・・ 15 Figure 2-5 Transition of the EdC’s System Loss ・・・・・・・・・・・・・・・・・・・・・・・・ 18 Figure 2-6 Transitions of Maximum Power Demand and Electric Energy in Laos ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 21 Figure 2-7 Daily Load Curve of the Vientiane system in Laos ・・・・・・・・・・・・ 22 Figure 2-8 Maximum Power Demand Forecast (Laos) ・・・・・・・・・・・・・・・・・・・ 23 Figure 2-9 Electric Energy Forecast (Laos) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 23 Figure 2-10 Transition of Generating Capacity in Laos ・・・・・・・・・・・・・・・・・・・ 25 Figure 2-11 Transition of Domestic Sold Electric Energy in Laos ・・・・・・・・・・ 25 Figure 2-12 Household Electrification Rate in Laos ・・・・・・・・・・・・・・・・・・・・・・ 28 Figure 2-13 Transition of Maximum Power Demand and Electric Energy in Thailand ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 29 Figure 2-14 Daily Load Curve in Thailand ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 30 Figure 2-15 Maximum Power Demand Forecast (Thailand) ・・・・・・・・・・・・・・・ 31 Figure 2-16 Electric Energy Forecast (Thailand) ・・・・・・・・・・・・・・・・・・・・・・・・ 31 Figure 2-17 Transition of Installed Capacity in Thailand ・・・・・・・・・・・・・・・・・ 32 Figure 2-18 Transition of the Total Loss of Generation, Transmission, and Distribution ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 33 Figure 2-19 Transition of an Electrification Rate in Households ・・・・・・・・・・・ 35 Figure 2-20 Transition of Maximum Power Demand and Electric Energy in Vietnam ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 36 Figure 2-21 Daily Load Curve in Vietnam ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 36 Figure 2-22 Transition of Energy Sales in Vietnam ・・・・・・・・・・・・・・・・・・・・・・ 37 Figure 2-23 Maximum Power Demand Forecast (Vietnam) ・・・・・・・・・・・・・・・ 39 Figure 2-24 Electric Energy Forecast (Vietnam) ・・・・・・・・・・・・・・・・・・・・・・・・・ 39 Figure 2-25 Transition of Installed Capacity in Vietnam ・・・・・・・・・・・・・・・・・ 40 Figure 2-26 Transition of Transmission and Distribution Loss ・・・・・・・・・・・・ 42 Figure 3-1 Calculation of the LOLE ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 48 Figure 3-2 Relationship between the LOLE and Reserve Margin ・・・・・・・・・ 48 Figure 3-3 Interconnection Transmission Line ・・・・・・・・・・・・・・・・・・・・・・・・・ 52 Figure 3-4 Installed Capacity and Generation Composition Based on the PDP in 2015 ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 54 Figure 3-5-0 Base Case ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 55 Figure 3-5-1 Case 1: Thailand – Laos Vietnam ・・・・・・・・・・・・・・・・・・・・・・・・・・・ 55 Figure 3-5-2 Case 2: Thailand Laos Vietnam (with Generating Units) ・・・・・・ 56 Figure 3-5-3 Case 3: Thailand Cambodia Vietnam ・・・・・・・・・・・・・・・・・・・・・・・・ 56 Figure 3-5-4 Case 4: Cambodia Vietnam ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 57 Figure 3-5-5 Case 5: Thailand Laos Cambodia Vietnam (with Generating Units) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 57 Figure 3-5-6 Case 6: Thailand Laos Cambodia (with Generating Units) ・・・・ 58 Figure 3-5-7 Case 7: Thailand Laos Vietnam Cambodia (with Generating Units) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 58 Figure 3-5-8 Case 8: Thailand Laos Vietnam Cambodia (with Generating Units) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 59 Figure 3-5-9 Case 9: Cambodia Laos ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 59
vii
Figure 3-5-10 Case 10: Thailand Laos Vietnam Cambodia Laos (with Generating Units) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 60 Figure 3-6 Reserve Capacity Reduction (Case 1, 2015) ・・・・・・・・・・・・・・・・・・ 60 Figure 3-7 Reserve Capacity Reduction (Case 2, 2015) ・・・・・・・・・・・・・・・・・・・61 Figure 3-8 Reserve Capacity Reduction (Case 3, 2015) ・・・・・・・・・・・・・・・・・・・62 Figure 3-9 Reserve Capacity Reduction (Case 4, 2015) ・・・・・・・・・・・・・・・・・・・62 Figure 3-10 Reserve Capacity Reduction (Case 5, 2015) ・・・・・・・・・・・・・・・・・・ 63 Figure 3-11 Reserve Capacity Reduction (Case 6, 2015) ・・・・・・・・・・・・・・・・・・ 63 Figure 3-12 Reserve Capacity Reduction (Case 7, 2015) ・・・・・・・・・・・・・・・・・・ 64 Figure 3-13 Reserve Capacity Reduction (Case 8, 2015) ・・・・・・・・・・・・・・・・・・ 64 Figure 3-14 Reserve Capacity Reduction (Case 9, 2015) ・・・・・・・・・・・・・・・・・・ 65 Figure 3-15 Reserve Capacity Reduction (Case 10, 2015) ・・・・・・・・・・・・・・・・・ 65 Figure 3-16 Hydropower Potential in the Laos System ・・・・・・・・・・・・・・・・・・・ 81 Figure 3-17 Weekly Operation of the Laos System in the Rainy Season ・・・・ 81 Figure 3-18 Weekly Operation of the Thailand System in the Rainy Season ・ 82 Figure 3-19 Reserve Capacity Reduction (Case 2, 2020) ・・・・・・・・・・・・・・・・・・ 83 Figure 3-20 Reserve Capacity Reduction (Case 5, 2020) ・・・・・・・・・・・・・・・・・・ 83 Figure 3-21 Reserve Capacity Reduction (Case 7, 2020) ・・・・・・・・・・・・・・・・・・ 84 Figure 3-22 Reserve Capacity Reduction (Case 10, 2020) ・・・・・・・・・・・・・・・・・ 84 Figure 3-23 Image of the Interconnected Transmission Line Project ・・・・・・・ 92 Figure 3-24 Relationship between Power Exchange Amount and Unit Fuel Cost Difference (Case 5) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 93 Figure 3-25 Relationship between Revenue and Unit Charge (Case 5) ・・・・・ 93 Figure 3-26 Relationship between Power Exchange Amount and Unit Fuel Cost Difference (Case 2) ・・・・・・・・・・・・・・・・・・・・・・・・・・ 94 Figure 3-27 Relationship between Revenue and Unit Charge (Case 2) ・・・・・ 94 Figure 3-28 Comparison with Recovery Cost ・・・・・・・・・・・・・・・・・・・・・・・・・・・ 100 Figure 4-1 Reserve Capacity Reduction (Case 2, 2010) ・・・・・・・・・・・・・・・・・ 106 Figure 4-2 Demand Divergence Between Thailand and Vietnam ・・・・・・・・ 109 Figure 4-3 Reserve Capacity Reduction (Case 1, 2015, Including Demand Divergence) ・・・・・・・・・・・・・・ 109 Figure 4-4 Case 11: Yunnan Thailand Laos Vietnam – Cambodia (with Generating Units) ・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・・ 110 Figure 4-5 Reserve Capacity Reduction (Case 11, 2015) ・・・・・・・・・・・・・・・・ 111 Figure 5-1 Annual Cost Share Comparison of Commercial and Public Loan ・ 115 Figure A1-1 System Interconnection in Japan ・・・・・・・・・・・・・・・・・・・・・・・・・・ 117
viii
Acronyms and Abbreviations
ADB Asian Development Bank ASEAN Association of South East Asian Nations BOT Build, Operate and Transfer CCGT Combined Cycle Gas Turbine CEEP Committee for Energy and Electric Power CEPC Central Electric Power Council Cigre Conseil International des Grands Réseaux Électriques (in French) International Council on Large Electric Systems (in English) CLDLO Central Load Dispatching Liaison Office DSM Demand Side Management DSS Daily Start & Stop EAC Electricity Authority of Cambodia EDC Electricite du Cambodge EDL Electricite du Laos EDP Electricite de Province EGAT Electricity Generating Authority of Thailand EGCO Electricity Generating Public Company Limited EPDC Electric Power Development Co., Ltd. EREPC Eastern Regional Electric Power Council ERLDLC Eastern Regional Load Dispatching Liaison Committee ERLDLO Eastern Regional Load Dispatching Liaison Office EUE Expected Undelivered Energy EVN Electricity of Vietnam FIRR Financial Internal Rate of Return FFC Flat Frequency Control F/S Feasibility Study FTC Flat Tie line Control GDP Gross Domestic Product GMS Greater Mekong Subregion GNP Gross National Product GT Gas Turbine HPP Hydro Power Plant HVDC High Voltage Direct Current IDE-JETRO Institute of Development Economies - Japan External Trade Organization IE Institute of Energy IMF International Monetary Fund
ix
IPP Independent Power Producer JBIC Japan Bank for International Cooperation JEPIC Japan Electric Power Information Center, INC. JETRO Japan External Trade Organization JICA Japan International Cooperation Agency JV Joint Venture LLDC Least Less Developed Countries LNCE Lao National Committee for Energy LOLE Loss-of- Load Expectation LOLP Loss-of-Load Probability MEA Metropolitan Electricity Authority MEF Ministry of Economy and Finance (Cambodia) MIME Ministry of Industry, Mines And Energy (Cambodia) MIH Ministry of Industry and Handicrafts (Laos) MOI Ministry of Industry (Vietnam) MOU Minute of Understanding MP Master Plan NEDO New Energy and Industrial Technology Development Organization NEPO National Energy Policy Office NLDC Northern Load Dispatching Center O&M Operation & Maintenance PEA Provincial Electricity Authority PDPAT Power Development Planning Assist Tool PPA Power Purchase Agreement PPSs Power Producer and Suppliers PRGF Poverty Reduction and Growth Facility PT& D Power Transmission & Distribution Project RETICS Reliability Evaluation Tool for Inter-Connected System SADEP Special Assistance for Development Policy and Projects SAPROF Special Assistance for Project Formation SCADA system Supervisory Control And Data Acquisition system SPP Small Power Plant SPREP Southern Provincial Rural Electrification Project SSGT Single Cycle Gas Turbine ST Steam Turbine TA Technical Assistance TBC Tie line load frequency Bias Control TCF Tera Cubic Feet TEPCO Tokyo Electric Power Company TLFS Thailand Load Forecast Subcommittee
x
TNB Tenaga National Berhad TPP Thermal Power Plant WASP Wien Automatic System Planning Package WB World Bank
xi
Map of Indochina
Border Mekong River
xii
Executive Summary
Introduction
This research project is intended to examine the feasibility and future strategy of interconnected power networks in Cambodia, Laos, Thailand and Vietnam in Indochina as one of the regional cooperation efforts in its power sector. More concretely, the study measured the benefit of interconnected power networks in monetary terms, particularly focusing on the whole system’s reliability, examined the financial viability of the selected networks, identified conditions and issues for the realization of the network, and made recommendations on future strategies of the governments and donors’ assistance.