Use of a Pathfinder Optical Telescope Element for James Webb Space Telescope Risk Mitigation

Lee D. Feinberga*,Ritva KeskiKuhaa, Charlie Atkinsonb, Scott C. Texter” aNASA Goddard Space Flight Center, Greenbelt, MD, USA 20771; 1’Northrup Grumman, Redondo Beach, CA USA

ABSTRACT

A Pathfmder of the James Webb Space Telescope (JWST) Optical Telescope Element is being developed to check out critical ground support equipment and to rehearse integration and testing procedures. This paper provides a summary of the baseline Pathfmder configuration and architecture, objectives of this effort, limitations of Pathfinder, status of its development, and future plans. Special attention is paid to risks that will be mitigated by Pathfmder. Keywords: Space Telescope, JWST, OTE, James Webb Space Telescope, Pathfmder, Risk

1. INTRODUCTION The testing of JWST Optical Telescope Element 1(OTE) and Integrated Science Instrument System (ISIM) occurs as an integrated entity called the OTE-ISIM (OTIS) at the Johnson Space Center”. In order to assure the test is successful with asfewcryogenic cycles as is possible,anOTE Pathfinder is being funded by the prime contractor Northrop Grumman as an IR+D funded effort. NGAS’s current plan emphasizes optical checkout at cryogenic temperatures though an augmentation to the Pathfmder plan is in the process of being added to the program that would add thermal checkout and dynamics objectives.

2. BIsT0RY OF PATHFINDER The OTE Pathfmder has its roots in the Verification Engineering Test Articles implemented on the Chandra program wherein unfinished flight optics were used to aid in the development of, and to demonstrate the integration operations and X-ray optical testing of, the critical optical components of the telescope using GSE that was uniquely designedfor the purpose. A significant component of the VETA-I and VETA-Il effort was the rehearsal and demonstrations of integration and testing operations. This served to significantly reduce the implementation risk of the GSE and integration and X-Ray optical testing of the flight optical assembly. Similarly, the JWST OTE Pathfinder is intended to reduce the implementation risk of the assembly, integration, and cryogenic optical test of the JWST optical assembly. A key goal for the OTE Pathfinder is to allow early checkout of the optical test procedures and test equipment to be used for cryogenic optical testing prior to their use in testing the flight hardware. This is the original key objective of Pathfinder because it significantly reduces the likelihood that the Flight OTIS will require extra JSC test cycles because of optical GSE not performing as expected. Additional unplanned JSC cryogenic cycles pose a risk to flight hardware, risks performance degradation, and have large cost and schedule implications risks, as a single cool-down and warm-up cycle is expected to take of order two months to complete.

The be

Beam process

testing temperatures,

Assembly The

connections driven set cryogenic The the Mirror PMSA

OTIS this and

(SMSS) and

in structure

support only

construction

to

A4

second Offloader

is

Pathfinder

second

OTE

contains

achieve

so

Image

removed

below

Assembly

of

and

C-segment

controls,

only

is

that

to

the

Pathfmder

test

(PMSA)

flight-like

C4

cryogenic

RMS

allow

augmentation

that

the

Analyzer

the

OTIS; its

interfaces

and

approximately

with

System

locations

to

effort

for

cold

will

optics

suspension

and

at

(SMA)

the

for

flow.

spare

cryogenic

the

A-segment

cryo)

however,

configuration

be

in

inspection

survival mounting,

at

flight

test

(HOSS),

(BIA)

AOS,

described,

the

structure,

used

for

The in that

that

Pathfinder

O-g,

will

the

Primary

cryogenic

the

system

is

the

last

and

for

in

testing.

is

temperature.

the

be and

Pathfinder

uncoated

(the

2

cryogenic

place

uncoated

handling

data

same

flight.

cryogenic

PMSAs,

then

performed

Pathfinder

but

and

for

consists

Engineering

can Mirror

J

test to

without

to

test

The

to

a

temperatures egress.

ensure

3.

be

limited

Ballast

collect

withstand

and

will

and

and

(PF)

testing

facility

the

Figure

OTE

tuned

PATHFINDER

of

Backplane

test

The

with

is

polished

follow

polished

shipment.

SMSS,

mechanisms

a

The

nanometer

Center

not

mass

time,

of

images

Center

Pathfinder

Pathfinder

Design

and

without

the

at

1:

the

intended

first

transportation

on

JSC

the

Pathfinder

is

JSC

the the

the

Pathfinder

to

Section.

Support

to

the

Section

at

added

Pathfmder

Unit

basic

approximately

is

Some

isolation flight

AOS,

approximately

the

the

level

shrouds

OTE

engaged.

shown

shown

OTE to

-

AOS,

Pathfinder

DESCRIPTION

to

timeline

EDU)

match

Aft

of

Structure structure

stability

The

and

Configuration

Pathfinder

the

is

will

loads

the

in in

and

set

cryogenic

Optics

mounted

an

hard-points

Pathfinder

HOSS

Figure

Figure

The

that

the

Pathfinder

have

to

augmentation

damping

of

and

lOOnrn

at

no

focal

and

lOOnm

(PMBSS),

dynamic

is

Pathfinder

the

System

operating

the

as

to

lower

polished

support

2

1

to

enough

test

flight

replicate will and contains

surface.

AOS

the

Secondary

RMS

to

can

RMS

BSF

will

than

(AOS).

includes

response

support

be

HOSS

test

the

but

be

in

temperatures.

Center

test

Backplane

to

at

achieved

is

be

at

30K,

place,

a

exercised

Due

the

test flight

in

ambient

without

used

ambient

Primary

of

operated

using

terms

Mirror

ground

The

expected

installation

thermal

configuration

of

to Section

to

only

but

requirements

the

limitations

ensure

with

PMSAs

the

the

Support

O-g,

of

as

will (currently

Mirror

Support

handling.

OTIS. with

for

balance

It

same

pre-preg

it

GSE,

the

is

mass

the

is

also

will

ambient

the

without

on

the

are

flight

designed

Fixture

EDU

Segment

hardpoint

BIA

at

and

of the

and

Structure

be

have

JSC

points, and

positioned

expected

cryo.

the

bleedout,

It

during

Hardpoint

OTIS

a

CG

handling

Secondary

is

wings

is

coated,

shrouds

the

BIA,

(B

not

similar

to

of

SF)

test.

the

to

and

in a

being

last JSC. relationship

The

colunm some

Backplane

elements testing

cooldown A

key

column,

testing

The

form.

used

objective

of

describes

that

the

second

and

Support

for

planned

between

They

nearly

OTIS

will

warm-up

the

of

the

column

not

are

test.

the

every

Fixture,

at

with

the

objective

also

be

JSC.

OTE

timelines

The

OTIS

replicated

the

optical

describes

intended

To

and

Pathfmder

last

OTE

and

of

do

the

column

test

each than

Pathfinder

this

the

during

the

to

ISIM

can

exercise

most

planned

will

key

is

specific

describes

be

to

and

the

be

optical 4.

check

checked

efficiently,

is

the

OTE

experienced

Figure

OPTICAL

the

OTE

intended

tests

IEC.

out

parameter optical

what

Pathfmder

planned.

Pathfinder

out

2:

the

MU

is

at

to

Pathfinder

procedures

test

planned

for

some

exercise

OBJECTIVES

is

that

equipment

The

flight.

testing,

not

testing

level

is

put

third

using

at

measured

all

and

There

JSC

using

including

on

is

the

colunm

the

that

summarized

GSE

the

optical

are

the

OTE

Pathfinder

will

during

that

also

OTE

describes the

be

Pathfinder.

tests

will

Center

a

used

the

Pathfinder.

in

large

planned

be

OTE

Table

fmal

the

in

used

Section

number

the

optical to

flight

As

I

for

as

OTIS

enable

below.

can

part

the

wings,

test of

test

be

test’ 11 .

flight

OTIS

of

much

of

The

seen

equipment

the

the

the

hardware

in

The

first

optical

faster

from

OTIS

at

least

the at

Image

Image Radiornethc

Stability

WFSC

Sensitivity

tional

Parameter

Quality

Quality

Thermal

PM

Multi-field mid

Ambient

motion

PM Fine WF

(SMA Thermal PM FPMSA

Change tRogue

during (Figure S&C Pupil 1PM

Plate

(single

SI low ISIM

SMA WFS&C

(tilt

FOV

conic

RoC

to

freq of

Control

Collection

frequency

Guidance

Scale

to

to Alignment/Truant

alignment

AOS

warm

single

Path

ACF

Envelope

control

drift

Survey AOS

AOS

Distortion:

Distortion: PM

PMSA

Influence Demo

PSF

alignment

Signal

of

aperture,

WFE

up

ACF

alignment

alignment

PM

Lqp

Area

PM

sign

Table

from

WFE

drift

Control

Test

&

WFE

Functions

Path

over

check

Alignment PM

NIRCam)

cryo

1:

each

over

WFE

(PMSA,

temp

Pathfinder

Limit

Path

test)

test

temp Si) ______

______

change)

&

temp) Change

______

change

RoC

SMA

_____Rogue

JOA

Testing

grammetry

otogrammetry

4ucial

poapmetiy

fCoA,

ICOCOA

Pass

[Pass

Photogrammetry

COCOA,

{alf

Pass photogrammetry

Pass Pass

COCOA

cocoA

Half COCOA

COCOA

COCOA Optical

-—

and

Pass,

and Pass,

and

and

and

path

lights

a

a

a

a a

(reflection

Test

ADM

ADM

Fiducial

Pass

Half

Half

Half, Half, Half

illumination

Equipment

and

COCOA,

COCOA,

Lights

a

area) Half

-

Jves

Yes With

With

With With

With With With

With With

Yes Partial With

Partial

for With With With With

PMSA

closed With

&

SMA & With

Pathfinder

BIA

BIA,

monitoring)

2 BIA

BJA

2 2

2 2

BIA

2 2

BIA BIA

2

2PMSAs 2PMSAs

1

loop

(no (no

PMSAs

PMSAs

PMSAs PMSAs

PMSAs

PMSAs

PMSA

PMSAs,

PMSAs, and

limited

B3

FGS)

SMA

control

Approach

segment

to

&

&

SMA

SMA BIA

those

necessary place

accuracy translation AOS this

Interferometer analyzed performance the

comparison however, veracity

OTIS The

OTIS.

changes

All

exercised. fiducial multi-wavelength

addition, imaging

cryogenic

OTE

the

measurement

as-measured

Source

used

of

test.

The

aspects

the

lights

of

during

Pathfinder of

of via

the

the

for

test.

for

stage

the

The

PMSAs

DM1

the

of

Science

phase

Plate.

will

incoherent

method

phase

the

(see

predicted

in

COCOA

of

comparison

a

optical This

large

is

the

thermal

WFE

not

on

OTIS

aligning

interferometry,

retrieval

section

positioned

The

retrieval

test, using

Instruments

BIA

the includes

be

to

enough

metrology

(manually

of

introduce

testing.

measurement.

created.

limiting illumination

the

optical

OTE

Fine

Mounting

excursion

will

the

the

3.4).

the

will

Subsystem

to

shroud Alignment

and

PMSAs

camera

using

Pathfinder

to

Figure

allow

to

PMSAs

recover

adjustable)

performance

The

be

Focus

Hexapod

and

capture aperture Aperture—

pupil

view

The

the

of

for

esAIignm)Cj://\

coarse.

Plate

temperature

in

the

process

some

the

provide

of

in

3:

the

temperature

Half-Pass

will

a

the

the

alignment

to

diversity

The

coarse

the

the

manner

2

the

Center

is

thermal

Enclosure the

in

PMSAs.

C4

WFE.

level

be

Pressure

Subsystem

PMSA

to

interferometer

DM1

this

focal

of

COCOA,

change

a

compared

PMSA,

ensure

and

science-grade

in-situ

of

of

test

)

comparable

change

case

is

using

will

The

distortion

(PTE)

Tight

surface

change

comparison

Curvature

provided

fine

and

The

configuration

to

the

is

be

so

phase

calibration

edge

shown

the alignment

measured

the

will

to

steps

it

used

measurement

over

will

what

will

can

inward

FSM

test

retrieval

by

detection

to

dominate

Optical

detector

involved

in

in

differ

be

to

the

the

also

g

BIA

will

was

conjunction

Mask.

Figure

the

using

data, used

subsystems

shown

FoV.

sources.

PM

be

be

motion.

measured

due

recovered

Assembly

algorithms

V

at LI

methodology

the

performed,

systems

during

Figure

hence

the

in

the

3,

For

the

to

Through-focus

in

aligning

temperature

will

same

reflective

the

In

Figure

Pathfinder

the

with

Translatton

Pupil

a

and

the

Stability

addition,

at

be

difference

quantitative lnterferometers

will Displacement

Multi

WFE

(COCOA)

Pathfinder

will

on

the

Pathfmder

exercised

the

the

as

the

4

imaging

Wavelength

work

the

using

XRCF

uses

be will

hologram

via

interferometer

identification

Stage

COCOA

change.

OTE

measurement

OTE

a similar

images

phase

r(MWIF)

the

together,

in

Point

the

downward

Measuring

test,

(DMIs)

expectation

as

during

is

thermal

focal

test

Pathfinder

camera’s

COCOA

also

a

retrieval,

Moreover,

will

to,

Diffraction

to

the

will

means

as

the

surface

but

provided not

the

BIA

well

and

also

be

to

configurations.

planned

sources

two

not

to

imaging

OTE

camera

monitor

to

collected

of

phasing,

as

will

as

be

though

enable

assess

on

PMSAs

identical observed

the

for

during

exercised.

Pathfinder

by

take

a

on

for

the

intent

will

the

of

RoC

the

the a

the

via

and the

the

OTIS;

the the

via

BIA,

be

to,

of

For In

by

provides

fields The parameter part

and

illumination Exercising

Focal

in include comparing of Exercising

3000

the

defocus,

the

re-imaged

Pass-and-a-Half

of

nm

presence

of

Surface

SMA

the

the

view

a

mis)

to

OTE

check

the

the

the

providing

location

of and

the

by

relative

that

at

half-pass

focus, half-pass

3

of

optical

phase

PM

the

PMSAs

tilting

of

the

will

the

in

OTE

test

and

astigmatism

background

additional

to

1 retrieval

also

location

design.

the

g

test

test

the

configuration

that

in

of

focal

ACF(s).

exist

the

the

AOS will

enables

collimated

flight

surface.

algorithms.

It

AOS

of

diagnostic

also

in

and

levels

interface will

the

the

practicing

The

allow

configuration and

coma

sources

also

uses

OTIS

that

light

Figure

The

limiting

source

produce

capability.

in

for

upward-looking

from

The

will

images

test

is

six

relative

WFE

practicing

4:

reflected

larger

plates,

exist

degrees

due

the

aperture

Half

and pupil

recovery

are

retrieved

to

to

in

range

partial

Past

along

the

steered

the

the

back

intensity

of

determination

in

imperfect

freedom.

sources

TM. Test

JSC

this

of

with

in

through phase

illumination

motion

to

the

case

chamber

Configuration

It

maps

various

an

presence

on

also

map

is initial

imaging

Other

the

the

of

of

the

from

provides

to

the

during

OTE

field

field

AOS

of

ACF

AOS

practice

Plate

that

valuable

of

the

BIA

the

at

tilt

locations

by

the

expected

Source

the

aperture

inward

testing.

2 AOS

a

(tens

the

and

PMSAs

residual

check

run

Cassegrain

Source

information

Autocollimating

image

Plate.

of

for

sources,

representing

which

by

of

mm)

in

imaging uncorrected

the

the

centroiding.

the

The

enables

focus

location

includes

source

an

that

OTE

light

important

and

the

will that

Pathfmder Flats

locations

several

is

WFE

of

image

partial

various

is

be

collimated

In

the

an

(ACF5)

gained

addition,

(up

input

OTE

analysis waves

inherent

SI to where only a single ACF is used. During the Pathfmder test, the BIA will take the place of the Science Instruments as in the Half Pass test. Once again, phase retrieval using through-focus images recovers the WFE.

Other important optical testing includes pupil testing and ciyo photogrammetry which measures alignment of the system. The testing will also check out the rogue path illumination system shown in Figure 5. During the Pathfmder test the Signal to Background ratio and overall illumination levels can be assessed whereas during the flight OTIS testing, these rays should be blocked and no illumination should be detected. This enables the Pathfinder test to demonstrate the rogue path test process and also demonstrate that a sufficient signal should be present if the OTIS rogue path mitigation is in error. It also checks the aligmnent of the rogue path sources to the 0Th under cryogenic conditions.

String(6x)of sources ouId

L— Rogue Path I Sources +v1

H

Figure 5: Rogue Path Configuration

The Pathfinder testing will also check out the cryo position metrology which consists of an Absolute Distance Meter (ADM) and the Photogrammetry system, which includes targets, cameras, rotating mechanisms and data collection and processing.

5. DYNAMICS

The risk reduction aspects of the Patbfmder testing at JSC as it applies to dynamics is entirely within the realm of ensuring that viable optical data can be obtained. To that end, the JSC test configuration will have the suspension system isolators and TMDs and the HOSS damper, plus some representation of the shorts to ground provided by the cables and the HOSS cooling lines. Ballast mass is added to the HOSS to replicate the expected mass and CG of the OTIS so that the suspension system can be tuned. Successfully collecting optical performance data with the interferometer in the COCOA during the first Pathfinder cryo test, and then with the Pass-and-a-half test during the second Pathfinder cryo test, will provide the desired risk reduction associated with dynamics effects on the optical measurements. / •

risoiator Ballast

6 Isolators to chamber

TMD j WingTMD L14,L123L14 (GSE) 71

HOSSSpring a: &MagDamper

1_BallastMass Figure 6: Dynamics Configuration

Before the OTE Pathfinder test, a dynamics model will be run using the input PSDs measured at JSC during its certification, the model of the test configuration representing the design as implemented on the JSC chamber, and a dynamics model of the OTE Pathfmder to provide an expectation for the magnitude of the vibration in the optical measurements. In addition, planning is ongoing to add cryo accelerometers and stingers to help check out the dynamics and also to address the cryo performance of the flight dynamic system.

6. THERMAL

The thermal configuration of the OTE Pathfmder will be quite different than for the OTIS test. Most notably, the ISIM and IEC will not be present, nor will the TMS hardware including the ISIM radiators, +/-V2 radiators, PTR and the MU and SLI closeouts of the OTE. What will be present are the 2 non-flight PMSAs (one uncoated), non-flight SMA (uncoated), and the AOS. The flight FSM de-contamination heater will be in place and used during warm up. The method for warming up the Tertiary Mirror and SMA is undefined for the flight OTIS test, but will be replicated for the Pathfinder test at JSC. The PMSA warm-up method has been defined for the flight OTIS test. Its implementation for the Pathfmder OTE will be similar, using the OTIS decontamination heaters and some Pathfmder-specific local blanketing.

Work is ongoing to define a thermal augmentation effort that will include development of a 3D thermal model using the PMBSS thermal model. The augmentation test will propose to test the same temperature profile planned for the flight

“Feinberg The program.

‘Feinberg,

“ limited

The

installation be

experience, including The

dynamics. OTIS. enables removed a The be monitoring

onto Warmup the

fully with

During

the

test

large

flight correlation

Atkinson

dry

placed

demonstrated

Pathfmder

operations

including

authors OTE

handling

electrical

the

re-pressurization

exercised

run

contamination-sensitive

will

Installation

to

the

checkout

HOSS

procedures,

from

for

Pathfmder

monitoring

key

adjacent

be

et

Keski-Kuha,

This

OTE

et efforts

and

during

we

would

those

al,

exercised

operations

al,

balance

teammates

and

between

the on

during

expect

will

handling

“New

will

Pathfmder

during

“Architecting

of

the

container

data

aimed

operations

operations. to

like

of

be

the

serves

assure

using

HOSS,

the

of

the

points

rates

the

the

Approach

handling

similar

both

to

the

alignment

the

Atkinson,

critical

during

procedures

PM

at

Ball

OTE

thank

Pathfinder

Pathfinder

two

the

to practicing

the

OTE operations

1

using

to

moving

and

like

in

structure.

reduce

Aerospace,

to,

Pathfinder

protect

a

The

FSM

GSE

Torr/min

OTE

clearances the

the

the

aspects

Revised

to

Pathfmder thermal

they

though

the

Texter,

on

OTE

Cryogenic

OTE

very

JSC

and

intended

heater

Pathfmder

test.

to

the

the

the

same

for

will the

at

be

of

Contamination

ISO

large

optical

OTE

Pathfmder

risk Pathfinder

will

JSC,

HOSS,

much

Optical

distortion.

the

into

ITT,

hardware

“Results,

However,

an

through

the

be

and

processes

testing.

9.

Class

flight

of

also

extremely

for

7.

for

the Pathfinder both

team

Optical

OGSE

and

reduced

any

ACKNOWLEDGEMENT

cryo

implementing

GSE.

and

use

Test

the

JSC

be

OTHER

REFERENCES

the

7

ATK

test.

inside

GSE

across

Status will

will

on

8.

Re-pressurization

the

The

tests

several

cleanroom

will demonstrated.

flight

will

as

Approach

Testing

chamber

We

chamber

the

monitoring

from,

valuable

be

science

be

the

SUMMARY

as

decontamination

into

effort

work

the

and

be

and the

are

OTE

OTIS

a

transported

well

flight

other

the

subset

chamber

the

CHECKOUT

the

during

country

the in

the

Plans

will

as

will

door.

that

pipeline

Pathfinder

as

for

same

the

tool

test.

chamber,

operations

needed

testing

OTIS.

JWST”,

key

L3

includes

include

of

JWST”,

use

process include

for

exodus

for

working those

as

alignments

SSG-Tinsley,

operations

and

using

many

the

and

reducing

in

at

The

during

heaters

SPIE

out,

performing

and

the

thermal

JSC.

JWST

particulate,

unloading

performed

to

of

SPIE

from

spacecraft

the

operations

of

install

the

adding flight to

on

Proc.

the

same

the

A using

for

practice

critical

the

risk

Proc.,

the

OTE”,

contamination

and

key

flight

same

SAO

OTIS

the

the

JSC

JWST

6265-23

container

to

checkout

the

ambient

on

ISO

simulator

molecular,

thermal

element

to

70

Tertiary

the

OTIS

to

SPIE

and

operations their

flight

test.

OTE

facility.

10-26 install

test

properly

Class

OTE overall

NASAIMSFC.

(2006)

operations,

on and

implementation

Proc,

Based

Pathfinder,

of

distortion

as

and

of

Mirror

protocols

will

(2008)

the

5

including

the

Witness

thermal

the

temperature,

this

therefore

(Class

integration

will

configuring

as

(2010)

OTE

not

HOSS.

on

OTIS;

is

the

and

therefore

past

be

to

model

performing

100)

Pathfinder

and

samples planned

installing

OTIS,

but

check

used.

SMA,

will

it

This

will

on

and

not

gas

and

the

be

act

out

a

will

be

test

for

will

RH as